BSCC
Board of State and Community Corrections
Read the report at Board of State and Community Corrections ↗
Youth Programs and Facilities Grant
Program (SB 823)
October 2024
Youth Programs and Facilities Grant Program
Executive Summary
On September 30, 2020, Governor Newsom signed Senate Bill 823 (Chapter 337,
Statutes of 2020), which began the closure of the state’s Division of Juvenile Justice
(DJJ), realigning those state functions to county governments. Under SB 823, DJJ intake
closed for most youth on July 1, 2021, and counties then become fully responsible for
housing, programming, and treatment of youth at higher offense and needs levels who
can no longer be committed to DJJ.
As part of SB 823, $9.6 million was set aside for the Board of State and Community
Corrections to “award one-time grants, to counties for the purpose of providing resources
for infrastructure-related needs and improvements to assist counties in the development
of a local continuum of care.” (Welf. & Inst. Code, § 2250, subd. (a).) This report
is submitted in compliance with SB 823. 1
Purpose of the YPFG Program
The purpose of the YPFG Program was to award one-time funding to counties solely for
infrastructure needs to facilitate youth programming that would provide trauma-informed,
culturally relevant and gender appropriate services to youth in the care of counties.
Infrastructure and improvement needs were defined as:
• Site preparation, fixed equipment and fixed furnishings, installation of fixed
equipment and fixed furnishings necessary for the operation of the facility or
program.
• Movable equipment, and movable furnishings necessary for the activation and
operation of the facility or program.
• Additional infrastructure-related needs and improvements to assist counties in the
development of a local continuum of care including but not limited to supplies;
transportation acquisitions; and training material acquisition.
1 The Board of State and Community Corrections shall complete and submit, no later than October 1, 2024,
a report to the budget and public safety policy committees of the Legislature describing the expenditures of
the Youth Programs and Facilities Grant Program, including, but not limited to, recipients and award amounts,
how funding was spent, how many regional placements were supported and a detailed description
of the counties that contracted to utilize the regional facility beds. The report shall also be made
available to the public on the board’s internet website. (Welf. & Inst. Code, § 2250, subd. (e).)
Page | 2
Consideration of SB 823 Intent
SB 823 made the following statements of the Legislature’s intentions and goals:
• Justice system involved youth remain closer to their families and communities
and they receive age-appropriate treatment.
• Youth needs are met by providing and implementing public health approaches to
support positive youth development and building the capacity of a continuum of
community-based approaches.
• The use of evidence-based and promising practices and programs that improve
the outcomes of youth and public safety.
• Further the development of a local “continuum of care”.
• Reduce the transfer of youth into the adult criminal justice system.
• Ensure that dispositions are in the least restrictive appropriate environment.
• Reduce and then eliminate racial and ethnic disparities.
• Reduce the use of confinement in the juvenile justice system by utilizing
community-based responses and interventions.
The infrastructure funding was intended to further support these goals.
Funding Information
Of the $9.12 million available to grantees (after BSCC administrative cost), funding was
available for two project types:
• Regional Hubs (Part A)
• All County Distribution (Part B)
See Appendix A for a list of Part A and Part B counties that applied/received funding.
See Appendix B for a summary of accounting expenditures.
See Appendix C for a summary of enhancements.
Regional Hubs (Part A)
A total of $2 million was awarded to Fresno and Sonoma counties ($1 million each) to
develop regional hubs to serve youth referred by other counties to serve the programming
and treatments needs of youthful sex offenders. As of August 2024, Fresno was
reimbursed their full grant of $1 million, and Sonoma has been reimbursed $305,359 and
has until December 1, 2024 to claim their remaining grant funds up to $694,641.
Regional Beds
A total of 116 regional beds were supported with the SB 823 grant with 12% contracted
to other counties.
Fresno has 43 regional beds: Contracts with Merced and Tulare.
Humboldt has 6 regional beds: No current contracts.
Mariposa has 4 regional beds: No current contracts.
Page | 3
Riverside has 26 regional beds: No current contracts.
Sonoma has 16 regional beds: Contracts with Contra Costa, Del Norte, Lassen, Marin,
Mendocino, Modoc, Napa, Nevada, San Benito, and Santa Cruz.
Tuolumne has 21 regional beds: Contracts with Amador, Calaveras, Inyo, and Mariposa.
Part A Grantee Summary
Medium Large
Small Counties Totals
Counties Counties
Number of Grantees 0 2 0 2
Total grant funds made available $0 $2,000,000 $0 $2,000,000
Maximum grant per County
$0 $1,000,000 $0 N/A
applicant
Total grant funds distributed $0 $1,305,359 $0 $1,305,359
All County Distribution (Part B)
A total of $7.12 million was available pro rata (by formula) to 37 counties based on county
juvenile population (age 12 – 17) to support infrastructure and improvements for local
programs and facilities for their in-county population of realigned youth. These Part B
funds were spent on infrastructure or improvements to programs, services, or facilities
serving youth who are realigned to counties as a result of the closure of the Division of
Juvenile Justice. As of August 2024, a total of $5,843,778 has been reimbursed to
grantees. 27 Part B counties have been fully reimbursed and the remaining 10 have until
December 1, 2024 to claim up to $1,140,750 in grant funds.
Part B Grantee Summary
Medium Large
Small Counties Totals
Counties Counties
Number of Grantees 17 14 6 37
Total grant funds made available
$2,847,993 $2,135,994 $2,136,000 $7,119,987
per county size
Maximum grant per County
$167,529 $152,571 $356,000 N/A
applicant
Total grant funds distributed $2,207,489 $1,959,693 $1,676,596 $5,843,778
Page | 4
Grant Extension
A total of 11 grantees received an extension through December 1, 2024 to make
purchases, due to the continued effects of implementation delays and supply chain
issues. Sonoma, Part A and the following Part B grantees received extensions: Alameda,
Contra Costa, El Dorado, Glenn, Riverside, San Francisco, Santa Clara, Santa Cruz,
Shasta, and Tulare.
Part A & B Grantee Summary
Small Medium Large
Totals
Counties Counties Counties
Total number of Grantees 17 16 6 39
Total grant funds made available $2,847,993 $4,135,994 $2,136,000 $9,119,987
Total grant funds distributed $2,207,489 $3,265,052 $1,676,596 $7,149,137
Page | 5
The chart and pie chart displays total grant reimbursements per spending category:
Grant Spending Categories Total Reimbursed
Construction $ 3,013,620.00
Moveable Furnishing/Equipment $ 1,640,430.00
Fixed Furnishings/Equipment $ 1,604,038.00
Programing Materials/Supplies $ 267,097.00
Transportation/Equipment $ 236,498.00
Architectural $ 144,244.00
One-Time Personnel Costs $ 138,459.00
Training Materials/Supplies $ 104,751.00
Grand Total $ 7,149,137.00
Transportation/Equipment One-Time Personnel
Training
Architectural Costs
Materials/Supplies
Programing
Materials/Supplies
Construction
Fixed
Furnishings/Equipment
Moveable
Furnishing/Equipment
Page | 6
Appendix A: Part A and B Grantees
Large Counties Medium Counties Small Counties
(pop. 95,001 +) (pop. 25,001-95,000) (pop. below 25,000)
Alameda Contra Costa Butte Colusa
Los Angeles Fresno (Part A) El Dorado Glenn
Orange Fresno (Part B) Humboldt Kings
Riverside Kern Madera Mendocino
Sacramento Merced
Mariposa San Benito
Santa Clara Monterey
Santa
Plumas
Placer Cruz
San Francisco San Luis Obispo Shasta
San Joaquin Sutter Tuolumne
Santa Barbara Yuba
Solano
Sonoma (Part A)
Sonoma (Part B)
Stanislaus
Tulare
Ventura
Data Source:
California Department of Finance. Demographic Research Unit. Report P-2B: Population Projections
by Individual Year of Age, California Counties, 2010-2060 (Baseline 2019 Population Projections;
Vintage 2020 Release). Sacramento: California. March 2021
https://www.dof.ca.gov/Forecasting/Demographics/Projections/documents/P2B_County_Age.xlsx
Appendix B: Summary of Accounting Expenditures
Part A: Grantee Spending Summary:
Fresno, Part A
Architectural $58,683.00
Construction $770,226.00
Moveable Furnishing/Equipment $127,764.00
Programing Materials/Supplies $22,027.00
One-Time Personnel Costs $21,300.00
Grand Total $1,000,000.00
Sonoma, Part A extension granted
Construction $164,871.00
Fixed Furnishings/Equipment $103,695.00
Moveable Furnishing/Equipment $21,056.00
Training Materials/Supplies $15,737.00
Grand Total $305,359.00
Part B Grantee Spending Summary:
Alameda, Part B extension granted
Architectural $52,300.00
Grand Total $52,300.00
Butte, Part B
Construction $70,041.00
Fixed Furnishings/Equipment $3,065.00
Moveable Furnishing/Equipment $17,508.00
Programing Materials/Supplies $9,265.00
Training Materials/Supplies $1,057.00
Grand Total $167,529.00
Colusa, Part B
Construction $140,614.00
Fixed Furnishings/Equipment $22,693.00
Moveable Furnishing/Equipment $3,048.00
Grand Total $166,355.00
Contra Costa, Part B extension granted
Fixed Furnishings/Equipment $17,734.00
Programing Materials/Supplies $11,270.00
Moveable Furnishing/Equipment $2,040.00
Construction $515.00
Grand Total $31,559.00
El Dorado, Part B extension granted
Construction $11,891.00
Grand Total $11,891.00
Fresno, Part B
Construction $36,548.00
Fixed Furnishings/Equipment $79,579.00
Moveable Furnishing/Equipment $36,444.00
Grand Total $152,571.00
Glenn, Part B extension granted
Training Materials/Supplies $4,968.00
Grand Total $4,968.00
Humboldt, Part B
Fixed Furnishings/Equipment $167,529.00
Grand Total $167,529.00
Kern, Part B
Construction $83,834.00
Fixed Furnishings/Equipment $6,609.00
Transportation/Equipment $62,128.00
Grand Total $152,571.00
Kings, Part B
Fixed Furnishings/Equipment $167,529.00
Grand Total $167,529.00
Los Angeles, Part B
Construction $72,038.00
Fixed Furnishings/Equipment $17,335.00
Moveable Furnishing/Equipment $266,627.00
Grand Total $356,000.00
Madera, Part B
Construction $41,588.00
Fixed Furnishings/Equipment $121,274.00
Moveable Furnishing/Equipment $4,667.00
Grand Total $167,529.00
Mariposa, Part B
Fixed Furnishings/Equipment $69,463.00
Transportation/Equipment $86,569.00
Grand Total $156,032.00
Mendocino, Part B
Construction $113,649.00
Fixed Furnishings/Equipment $4,278.00
Moveable Furnishing/Equipment $15,825.00
Programing Materials/Supplies $7,169.00
Training Materials/Supplies $5,400.00
Transportation/Equipment $21,208.00
Grand Total $167,529.00
Merced, Part B
Moveable Furnishing/Equipment $152,571.00
Grand Total $152,571.00
Monterey, Part B
Moveable Furnishing/Equipment $71,400.00
Programing Materials/Supplies $68,030.00
Training Materials/Supplies $13,139.00
Grand Total $152,569.00
Orange, Part B
Moveable Furnishing/Equipment $356,000.00
Grand Total $356,000.00
Placer, Part B
Architectural $7,520.00
Construction $73,237.00
Fixed Furnishings/Equipment $62,418.00
Moveable Furnishing/Equipment $9,396.00
Grand Total $152,571.00
Plumas, Part B
Construction $47,086.00
Grand Total $47,086.00
Riverside, Part B extension granted
Moveable Furnishing/Equipment $20,859.00
One-Time Personnel Costs $89,000.00
Programing Materials/Supplies $78,845.00
Training Materials/Supplies $30,475.00
Grand Total $219,179.00
Sacramento, Part B
Construction $356,000.00
Grand Total $356,000.00
San Benito, Part B
Fixed Furnishings/Equipment $122,361.00
Moveable Furnishing/Equipment $45,168.00
Grand Total $167,529.00
San Francisco, Part B extension granted
Moveable Furnishing/Equipment $75,479.00
Fixed Furnishings/Equipment $259.00
Programing Materials/Supplies $26,491.00
Grand Total $102,229.00
San Joaquin, Part B
Moveable Furnishing/Equipment $152,571.00
Grand Total $152,571.00
San Luis Obispo, Part B
Construction $92,321.00
Fixed Furnishings/Equipment $40,218.00
Moveable Furnishing/Equipment $34,990.00
Grand Total $167,529.00
Santa Barbara, Part B
Construction $111,839.00
Fixed Furnishings/Equipment $40,732.00
Grand Total $152,571.00
Santa Clara, Part B extension granted
Architectural $10,370.00
Construction $221,361.00
Fixed Furnishings/Equipment $103,682.00
Moveable Furnishing/Equipment $1,704.00
Grand Total $337,117.00
Santa Cruz, Part B extension granted
$
Grand Total $0.00
Shasta, Part B extension granted
Construction $9,442.00
Fixed Furnishings/Equipment $53,692.00
Moveable Furnishing/Equipment $56,003.00
One-Time Personnel Costs $28,159.00
Programing Materials/Supplies $914.00
Grand Total $148,210.00
Solano, Part B
Fixed Furnishings/Equipment $152,571.00
Grand Total $152,571.00
Sonoma, Part B
Construction $42,275.00
Fixed Furnishings/Equipment $4,742.00
Moveable Furnishing/Equipment $71,579.00
Training Materials/Supplies $33,975.00
Grand Total $152,571.00
Stanislaus, Part B
Construction $106,363.00
Fixed Furnishings/Equipment $3,419.00
Moveable Furnishing/Equipment $41,229.00
Programing Materials/Supplies $1,560.00
Grand Total $152,571.00
Sutter, Part B
Construction $140,614.00
Fixed Furnishings/Equipment $1,741.00
Moveable Furnishing/Equipment $24,001.00
Grand Total $166,356.00
Tulare, Part B extension granted
Construction $104,642.00
Fixed Furnishings/Equipment $42,984.00
Grand Total $147,626.00
Tuolumne, Part B
Fixed Furnishings/Equipment $167,529.00
Grand Total $167,529.00
Ventura, Part B
Architectural $15,371.00
Construction $62,009.00
Fixed Furnishings/Equipment $25,000.00
Moveable Furnishing/Equipment $8,665.00
Programing Materials/Supplies $41,526.00
Grand Total $152,571.00
Yuba, Part B
Construction $140,616.00
Fixed Furnishings/Equipment $1,907.00
Moveable Furnishing/Equipment $23,836.00
Grand Total $166,359.00
Appendix C: Summary of Enhancements
Fresno, Part A
Pod 708A was converted from double beds to single beds, top bunks were removed and holes were
patched. Rooms were painted which included multiple calming colors throughout the pod. Sound boards
were installed throughout the common area (the dayroom). All metal doors, door frames, and window
frames were painted with calming colors. The floors were all polished. Mattresses Puchased includes:
10 standard mattresses. 709 Programming rooms: metals installed, thermal and moisture protected,
openings and closings of walls and ceilings, HVAC and electrical secured, and exterior improvements
has been made. Construction has been completed, along with fire alarm and sprinkler renovations. An
awning has been installed. Programming Materials/Supplies and Moveable Furnishings/Equipment
purchased: 6 TVs, 6 webcams, 6 TV carts, 6 micro PCs, 5 Rugged Two seater Chairs, 6 Locked
Cabinets, 6 Standing Fans, 6 Flip Chart Stands, 18 Whiteboards, 6 Laptops; Housing pod furniture
consisting of chairs and tables. Assessment and Planning Training, Curriculum Training, and Technical
Assistance, Coaching and Fidelity Monitoring.
Sonoma, Part A
Supplies, materials, design/architect and other costs associated with the approved greenhouse and
garden project, which will provide agricultural education and programming to youth in juvenile hall.
Uprades and enhancements made to the juvenile hall data bases to improve tracking & reporting on
SB823 youth and youth from out-of-county. Purchase of music equipment to provide programming to
youth in juvenile hall; intent is to offer a wider variety of activities including music education. Welding
program supplies - career tech education.
Alameda, Part B
In order to prepare the site for the proposed outdoor structures, 4,000 square feet of soil must be
excavated and the replaced with 4,000 square feet decomposed granite to provide sufficient equipment
anchoring and to prepare for the rubberized safety surface beneath the equipment. Additionally, a
separation curb will be installed for the safety of the outdoor activity structures. Purchase and contract
with a vendor, or potentially multiple vendors to install permanently affixed exercise equipment at the
Juvenile Justice Center (JJC) to promote the health and well-being of youth residing in the JJC. The
equipment would consist of one cross fit structure and stand-alone fixed exercise equipment that
allowing a full regimen of physical workout activity like what would be experienced in a traditional gym.
Purchase and install four outdoor, permanently affixed shade structures or pergolas. These structures
will each by 10'x10' covering a single table and two benches. They will be able to seat up to six people
at each structure.
Butte, Part B
Painting was completed at Juvenile Hall to make it more home like. Garbage cans, an area rug, 10
night stands, 8 armless chairs, 1 coffee table, 10 mattress memory foams, 13 weighted blankets, and
lockers were added for the same purpose. Phoenix gang curriculum was purchased to administer to
youth. According to The Phoenix Curriculum, it provides effective resources for both gang prevention
and gang intervention in schools, communities, and corrections. Our highly successful and innovative
resources are used nationwide to address the risk factors underlying gang recruitment and gang
involvement. Lockers were purchased to provide youth to store personal belongings. A Little Nomad
Pay Mat in Fawn, Nature Scenery Wall Art Décor, and Cordless Blinds were purchased in MSDR
Supplies to make the room feel more home like and provide privacy. In addition, for the Multisensory
De-Escalation Room, flourescent light covers, sensory fidget toys, sound machines, building block
games, putty, anger management ball, sensory crash pad, oil diffusers, journals, markers, excercise
balls, feeling charts, mental health posters, and stickers were purchased. Materials were purchased to
enhance security fencing to the existing exterior fencing. A van was purchased to transport CSP youth
to medical and other appointments as needed, and to evacuate youth from the facility as needed. Dr.
Bruce Perry Nuerosequential Model of Therapeutics training and certification for contracted mental
health clinician (Youth For Change) was purchased. This model is developmentally-informed,
biologically-respectful approach to work with at-risk youth.
Colusa, Part B
Paint all interior surfaces, apply interior epoxy floor finish to concrete floors in the 15 bed Secure
Housing Unit (SHU). Weatherproof and paint all exterior surfaces of the 15 bed Secure Housing Unit.
Purchase new privacy doors for two regular shower stalls and one handicap shower stall. Replace
existing fixed stainless dining table/stool with a new folding moveable table for the dining in the
community day area. Purchase television and wall mount bracket to hang TV in main living unit.
Furnish and equip programming spaces with items to include, but not limited to modular seating/large
chairs, table(s) for the designated living space on pod in the main living area. Furnish and equip
indivdiual cell spaces with items to include, but not limited to: new mattresses and storage cabinet(s)
for cells; new pillows, bed sheets, blankets, and towels for distribution to the youth; book shelf, chair
and wall mounted desk for each individual room.Purchase new cameras for the main living facility and
classroom. Purchase hand held radios for staff and mobile security screening systems/metal detectors.
Contra Costa, Part B
The space for the planned culinary program was updated to accommodate the needs of the class. New
power (the installation of electrical outlets) was installed in the area to allow the flexibility to run multiple
cooking appliances at the same time as the youth are exposed to the courses hands-on curriculum. The
space now have ventilation by installing one (1) exhaust fan. Student workstations and the refrigerator
was secured to the floor or wall forsafety. The ultimate goal of the Tamalpais Program unit is to help
transition youth from the facility to independent living by equipping them with knowledge and tools to
help them be successful with life away from our facility. Our goal is to provide youth meaningful
educational programs, vocational training, and in a home-like environment. In-room desks are a key to
providing youth with more of a sense of home, allowing them the space to work privately on classwork
or personal projects. The facility is also adding to its available exercise area options with a
comprehensive exercise space in its Tamalpias unit, which is essential for our youth’ physical and
mental health. The addition of a horticulture program is an opportunity we have with our available space
to have an educational program that allows youth to take ownership over a space where they have a
direct impact on its success. A greenhouse will give the students a place to work and learn while giving
the plants they care for the best opportunity to be healthy. A storage shed is required to protect
materials like soil and tools from the elements for proper maintenance to ensure the longevity of the
items and for the safety of our students. Unit Seating: we strive to provide a home-like environment for
our Tamalpias youth. The common area seating is in need of an update to give youth a space to relax
and socialize in an area they can be proud of. The SNUG furniture is a modern take on detention
furnishings that is safe yet promotes a comfortable and healing space. Monticello Unit - The culinary
program is intended to provide participants with life skills and job readiness. The hands on approach to
this course will provide all students with their own space to prepare and cook food. The stainless-steel
food prep carts will familiarize the youth with what they may see if they were to choose to work in food
service after leaving the facility. In addition to the culinary program preparing youth with necessary life
skills, it will also introduce the students to food preparation, proper food handling, and food born
illnesses. Each student will earn a SERV Safe certificate which is recognized throughout the food
service industry and is a requirement for employment. The culinary program will be set up to provide
each student with their own area to prepare and cook. This includes small appliances, pots, pans,
knives, and utensils.
El Dorado, Part B
El Dorado County collaborated with County Facilities on the installation of heat in the outdoor/indoor
covered recreation area. Made the facility a more home-like environment, including a mural in the Multi-
Sensory De-Escalation Room (MSDR) that was converted from a holding cell at the Juvenile Treatment
Center. This room is needed in order to have a space where youth who are struggling with controlling
themselves have a safe space to collect themselves. Stand-alone storage shed/building, shelves,
bins/containers, for vocational equip. & materials to support long term youth including clothing,
educational equip., & counseling materials. Moveable desks/tables, couches and soft seating, homelike
furnishings for youth will be installed in the unit day room. Furniture for the private interview rooms.
Smart board for group counseling & group learning in unit day room. New mattresses and mattress
covers for sleeping rooms. Training for staff to work with long term youthful residents, including CBT
programming, Evidence Based programs focused towards Psych Educational Resource Groups,
individual services, group programs, Journaling Therapy, family support and counseling, and
therapeutic activities to promote rehabilitation. Mental Health Program Staff attended FMHAC Forensic
Mental Health Association of California Conference with a focus on Community Assistance, Recovery,
& Empowerment, Incarceration Trauma, and the Impact of Incarceration on Mental Health. Multi-
Sensory De-Escalation Room (MSDR): Personal items for youth such as weighted blankets, fidget
spinners, educational materials focused on feelings, bean bag chairs, stability balls, and essential oils.
Fresno, Part B
Furniture purchased includes: 6 gray armless side chair, 2 large linen tables, 4 walnut tables, 4 medium
linen tables, 2 small linen tables, 6 backless fabric seat, 14 fabric single seats, 8 two-seaters, 20 lounge
chairs, and 2 TV rolling carts. Mattresses Puchased includes: 28 standard mattresses. Electronics: 1
Ipad Pro, 1 Apple Keyboard, 1 Ipad Otterbox Case. Completed awning in building 703. Moveable
Furnishings/Equipment purchased: 2 Micro PCs, 2 webcams, 2 TVs, 4 Picnic tables, 1 table tennis, 5
Additional bed mattresses.
Glenn, Part B
Forward Thinking Journals. Furnishings: chairs to be used in programming space, and storage bins to
be used for storing program materials. Computer Equipment: laptop computers with video and audio
capabilities to be used for assessments and remote individual and group meetings.Purchase a van.
Training materials:75 cognitive behavior journal series and facilitator guides, assessment software,
laminator and laminator supplies, office supplies, personnel costs to implement programs.
Humboldt, Part B
The project includes 3 components: 1) the installation of an upgraded digitial camera system in the
Juvenile Hall 2) the installation of a redundant station making all Regional Facility doors operarable
from the Juvenile Hall control room 3) wiring the new recreation yard door in the Regional Facility to be
operated on the same redundant station system.
Kern, Part B
Extended railing from existing railing up to ceiling in the housing pods second tier.The extended railing
prevents youth and staff injuries from self-harm and assaultive behaviors. Added additional/upgraded
perimeter fencing,allowing for more robust outdoor programming opportunities within the grounds of the
facility. Purchased weightlifting equipment. Purchased two passenger vans and GPS tracking systems.
Kings, Part B
Installation of new security cameras and digital control panel. The installation of this system along with
the control panel will greatly increase the safety and security of the youth and staff.
Los Angeles, Part B
Furniture was purchased for Units W & X at Barry J. Nidorf Juvenile Hall. This included tables, chairs,
wall units and game tops. Flooring was prep and installed for Unit Z 1 and Z 2. Furniture was
purchased for Units W & X at Barry J. Nidorf Juvenile Hall. This included tables, chairs, wall units, game
tops, floor mount endurance desk, and Sabre Chair. Install new flooring for Berry J. Nidorf Juvenile
Hall - Boys' Dorm Unit Z1 and Z2 and for Unit TV area.
Madera, Part B
The units in the facility were painted to update the appearance, brighten the rooms, and provide a
therapeutic environment. Furnishings of desks and stools will add to the environment used to complete
education, writing and tablet area. Laptops were purchased to aid the youth in online classes and
family engagement via Zoom or Duo. Installed wireless access points throughout the facility to provide
wifi for the youth to attend college course, counseling session, and family engagement online.
Mariposa, Part B
Install new Security Cameras, Higher Definition 4MP and 6MP IP Security Cameras. Included in the
installation was a 12TB Surveillance Hard Drive. In addition, there is a wireless bridge that allows
Remote Viewing Access. Included in the installation was the hardware, Alarm System, Wireless
Keypads, Receiver, Cellular Communicator, Transmitter and Wireless Motion sensors. The contract
calls for 24 hour 7 days a week monitoring service. Installation of a Close Circuit System (CCTV),
installation of the Communications alarm system and additional keypad. Security monitoring services.
A 2023 Mercedes Benz Sprinter full sized passenger van was purchased along with corresponding
Camera upgrades that enhance backing capability and interior monitoring. The van was also equipped
with a radio communication device that will allow transportation officers to effectively communicate. In
addition, a Kenwood radio system, Speco 6" horn and Stico radio antenna was purchased. Finally, a
camera system was purchased for the interior of the van (Red Tiger).
Mendocino, Part B
Installation of additional upgrades to video surveillance system. 2 Samsung 55" Smart TV's, 2 TV
Mounts, 2 wireless keyboards, Upgraded Surveillance System, 5' Round classroom activity table, 6 Dell
Laptops, 3 Bookcase/Shelves, 8 lounging chairs, GEM Elec Vehicle. Purchase of Dynamic Mindfullness
Trainings for staff. Courage to Change Materials.
Merced, Part B
Probation utilized grant funds to expand vocational training services by purchasing solar training
installation and maintenance simulators for youth to obtain certification that they can utilize upon
release from custody. Through a partnership with the Merced Union High School District, a
credentialed solar technologies teacher will utilize curriculum provided by the solar kit provider, Amatrol.
The curriculum includes all testing, authentic (skills) assessment resources, and rubrics for consistent
student assessment. Youth will be able to re-enter the community with a valuable skillset, and be able
to obtain employment in the solar photovoltaic industry by becoming certified through the North
American Board of Certified Energy Practitioners.
Monterey, Part B
Purchase of sofa for dorm area at the juvenile hall to promote a homelike setting. Purchase of four (4)
contraband body screeners to enchance safety and security at the youth facilities of the juvenile hall
and youth center. Purchase of assessment softaware and associated staff training - YASI software
licenses and eTraining to enhance staff knowledge on assessments. Purchase of training services for
staff on topic of DJJ Realignment Preparing for Transitional Aged Youth.
Orange, Part B
TruNarc Devices are installed at Orange County Juvenile Hall and at the Youth Guidance Center to
enhance the ability to rapidly detect materials and/or substances that may be harmful to youth and
staff.A Body Scanner was installed at Orange County Juvenile Hall to reduce incoming contraband
during intake and during contact visitation between secure track youth and family. A Mail Scanner was
installed at Orange County Juvenile Hall to reduce incoming contraband in correspondence received via
the mail.
Placer, Part B
Wifi capability to aid in programming has been added throughout the B unit and Max unit. Smart board
and four dell pc's have been installed in B unit for use in education and program delivery. Additional
framing and electric was completed in the Maximum Security Unit, to allow for a partian wall to be
installed. Once installed, this wall will allow us the opportunity to provide additional programming,
education, and therapy to our Secure Track youth, without disturbing other youth.
Riverside, Part B
Behavior Health furniture to create homelike environment, Equipment & furnishings for Multi-Sensory
Dimensional Room for a trauma informed approach, Inspirations Signs & custom posters to provide a
positive & trauma informed environment. Preloaded educational tablets to assist with instruction and
research, Journals to assist with writing skills and expressing emotions. Sporting eqipment/ Craft/Art
Supplies/ Therapy Musical Program/ Projector/Screen for Educational Purposes/ Food Therapy
Program/ Plant Therapy/ Therapeutic Spa/ Video Game System with games.
Sacramento, Part B
Renovating of the North Field recreational area of the Youth Detention Facility (YDF) to support health
and fitness programming for the youth in custody. The project consisted of installing a decomposed
granite running track around the perimeter of the flag football field, laying a cement pad for the future
construction of bleachers, as well as the installation of additional wiring around the perimeter of the field
for additional security.
San Benito, Part B
Upgraded the camera system to make full use of an existing outdoor space for vocational training
programs and recreation. The personal living spaces and programming rooms were updated with warm,
soothing, paint colors and comfortable furniture. New laptops replaced outdated tower computers and
will be used as portable devices during booking, intake release procedures, data entry, visitation, court
appearances and programing for quarantine and Secure Track youth. The culinary cart will serve as an
enhancement to our garden and Agg in the classroom program, since the facility is not equipped with a
kitchen. This culinary program will teach the youth basic food preparation, safety including a
SafeServe® Food Handler certification, and career opportunities in the food services industry once
released from custody. A new refrigerator was needed within the Juvenile Hall for the youth due to a
mechanical breakdown.
San Francisco, Part B
Two sofas were purchased to furnish spaces to create a college lounge setting. This will give our older
students a better, more developmentally appropriate space in which to learn and participate in their
education. Equipment, moveable furniture, and supplies were purchased to create an outdoor kitchen.
This will serve an education purpose since it will support a culinary program. It also served as an
upgrade to our outdoor space for recreational use and family visitation.Ten arm chairs were purchased
for youth classrooms. Two patio sofas and two outdoor rugs are for Unit 7 & 8 youth outdoor area.The
rest paints and painting supplies purchasd were for the painting of two showrooms. All the purchases
are trying to enhance youth study or living conditions.Four Sofars are for Unit 7 Youth & Merit Center.
Stopwatch Clock, Treadmill, and Fan are for JJC Fitness Center. 9/18/23 procurements are for Family
Playroom for JJC detainees' family members including movable furnishings, Wall Decors, and various
Children Books and other toys. Clary Guest Chairs and Table are for JJC Workplace for Credible
Messengers. Floor Cushions, Sherpa Chair, and other toys are for JJC Family Playroom. Seven Garrett
Metal Detectors are safty and security equipments for JJC. One Multifunction Gym System, two floor
mats, two Flex Timers, and five MEDICINE Weight Balls are for JJC Fitness Center. Twelve Paint
Brushes and three Paint Poles are for the painting of two showrooms.One Weight Ball for JJC Fitness
Center and one Basketball Backboard and Rim with Mounting Kit which located at the living Unit 7 & 8
improve Youth fitness equipment . Paint, Mater Weaves, Hammer Heads and Stain Removers are
additional suppliers to support the painting of Unit 8 for a better living environment. A hundred pieces of
GoGuardian Licenses for Admin with Fleet, DNS & AdDeflect and a hundred for Teacher with Video
Conferencing enhance the protection of the Youth using of Cromebook and enable teachers to provide
better learning experiences.Storage totes are used to store youth clothes and other personal
belongings. One commericial grade threadmill, ten indoor basketballs , five outdoor basketballs, two
footballs, five soccer balls and five mesh ball bags are for JJC Fitness Center. Gardening items and
supplies for YPFG Garden Project - garden home kits, wheelbarrows, watering cans, soils, electric
skillet, hoses, greenhouse metal work benchs, mulch, nuggets, buckets, and steel garden arch arbors.
Switches are installed for the mirror project. Two smart TVs with wall mounts are installed to improve
access to programs. GoDaddy domain registration, Google workspace licenses, Chrome enterprise
upgrade enable content blocking security and monitoring by staff. One locked laptop charging cart
keeps chromebook be used in safety. Washers and dryers at both SYTF units are for youth to learn
how to launder their own clothes and linens.
San Joaquin, Part B
Two virtural reality simulators for forklift training were purchased as part of the Logistics Vocation
Program to prepare youth for employment and training in the local Logistics job market. With the forklift
simulators, youth will obtain a higher level of knowledge and skills, such as front-line materials
handling, that is needed before obtaining employment in the Logistics field. Furniture, such as chairs,
tables, desks and storage units, will be used as part of the educational programs offered to youth,
which includes college courses through San Joaquin Delta College and landscaping vocational courses
through the Greater Valley Conservation Corps. These educational and vocational programs will
enhance and prepare successful rehabilitiation and community reentry for the youth.
San Luis Obispo, Part B
Update and install 15 video security cameras. Project design and construction services for
kitchen/laundry remodel project. Purchase and installation of 2 Metrasens Ultra w/ Xact ID System and
Platinum Service Contracts.
Santa Barbara, Part B
The Project entails the renovation of the Recreation Yard (Play Area 3) out at the Juvenile Justice
Center in Santa Maria, CA. This renovation includes: sawcut and removal of existing asphalt pavement
for the construction of the synthetic turf soccer field; weed removal & crack seal of the remaining
asphalt pavement; Construction of a 1.5" asphalt concrete overlay; Construction of concrete curbing
separating the soccer field from the asphalt ball court areas; The construction of the Workout Station
Area & the installation of the Workout Station equipment; The painting & striping of the new asphalt
surface defining the separate ball courts (i.e. basketball, volleyball/pickleball & handball courts); The
installation of the court poles (i.e. basketball standard & backboard, volleyball/pickleball poles);
Construction of the shade structure for the picnic area; Construction of the drinking fountain; and
Construction of new yard perimeter screening. Site furniture includes: New picnic tables;Soccer goals;
Workout station equipment; and a cantilever shade umbrella.
Santa Clara, Part B
The Juvenile Hall has been identified as the current facility to begin the Secure Youth Treatment Facility
program. The Probation Department acknowledges that the Juvenile Hall is being used as an initial
option but may not be the ideal setting for a long-term treatment facility for youth and young adults. The
Probation Department has contracted with a architect to provide designs to “soften” the look and feel of
the two designated living environments within the Juvenile Hall to the extent feasible. This will support
limited infrastructure redesign and improvements that are rooted in a trauma-informed design. The goal
is to create spaces that are welcoming, demonstrating a safe environment and providing some degree
of privacy for youth and young adults. Funding will also be utilized to redesign the existing double
occupancy rooms to single occupancy rooms and add a desk and appropriate furniture within each
room. Behavioral Health room will be utilized for Behavioral Health sessions/therapy. The room will be
painted to set a therapeutic environment. It will be furnished with a comfortable couch and chairs for
sessions. The carpet is a step in the process to transform the room into a more therapeutic
environment. The refrigerator is used to help youth store their food in the unit. Our young adults cook
their food and have culinary courses. Unit A3 is a newly remodeled unit, the units were empty and the
furniture is to create and support a learning environment and space for books. We purchased 18 sets of
Norix Prodigy anti-ligature furniture for A3 unit. Each set consists of bed, desk, chair, nightstand, and
open chest. Each piece of furniture was secured to the floor in each unit with steel anchoring system
and any space between the furniture and the floor/wall was sealed with OEM recommended adhesive.
Each chair was filled with 75 pounds of sand and the filler cap was secured with adhesive.
Santa Cruz, Part B
Construct security improvements (doors, window, ceiling, cameras) in small meeting room for use in
secure Juvenile Hall operational space to serve the realigned population and provide youth meetings,
programming, and family visits. Convert two existing rooms/cells to "soft" counseling/de-escalation
rooms to support behavioral health services to address the needs of the realigned youth. Purchase
furniture for two new soft counseling rooms and upgrades to family and children waiting area. Purchase
one 12-passenger van with added accessories to provide long-distance transportation of youth and
families who would not otherwise be able to travel on their own for visitation. Purchase new tablets and
MiFi units to support families in maintaining consistent contact with their children. Purchase supplies
and materials for counseling rooms and family waiting area.
Shasta, Part B
Installed a safety cell door food port. Purchase two personel computers to support the upgraded
monitoring system and security cameras. The PC's are customized with high end video cards and larger
hard drives for space. Replaced and purchase 30 hand held radios, along with michrophones and ear
pieces for better communicationa and enhance safety and security. Leased Edovo tablets to expand
educational and vocational programming. Programming software, upgrades, and cameras for the
monitoring system and security cameras within the facility and in the recreation area. A Norix Tabla
Drum Table and six lounge arm chairs for programming and free recreation for the Secure Track
treatment Program residents. A purchase of Vinyl Wall Mural to support life skills. Train the Trainer
Training for Staff, by the Unitvesity of Cincinnati Institute. Crisis Prevention Training provided to staff by
the Mandt System, Inc.
Sonoma, Part B
Modifications were made to soften visitation, programming, education, interview, and telehealth areas
for youth including with as much home-like/non-insitutional furniture and features as possible and
appropriate, including decor and painting. Installed smart TVs for tele-visits/teletherapy/programming.
Installed prox card readers, work desks, phones and computers for staff to use for training and
programming.
Stanislaus, Part B
The facility has had the HVAC unit replaced, floors resurfaced, walls painted, wall murals added, and
new furniture installed to refresh the environment. The fencing has been reinforced and raised to meet
the needs of the facility. The De-Escalation room has been decorated with items to help create a
calming sanctuary for the youth.
Sutter, Part B
Paint all interior surfaces, apply interior epoxy floor finish to concrete floors in the 15 bed Secure
Housing Unit (SHU). Weatherproof and paint all exterior surfaces of the 15 bed Secure Housing Unit.
Purchase new privacy doors for two regular shower stalls and one handicap shower stall. Replace
existing fixed stainless dining table/stool with a new folding moveable table for the dining in the
community day area. Purchase television and wall mount bracket to hang TV in main living unit.
Furnish and equip programming spaces with items to include, but not limited to modular seating/large
chairs, table(s) for the designated living space on pod in the main living area. Furnish and equip
indivdiual cell spaces with items to include, but not limited to: new mattresses and storage cabinet(s)
for cells; new pillows, bed sheets, blankets, and towels for distribution to the youth; book shelf, chair
and wall mounted desk for each individual room.Purchase new cameras for the main living facility and
classroom. Purchase hand held radios for staff and mobile security screening systems/metal detectors.
Tulare, Part B
The project requires installation of additional security cameras. Twenty-two (22) cameras and
accessories are purchased and projected to be installed. Install a perimeter fence to expand vocational
education and recreational space.
Tuolumne, Part B
Updated and enhanced security electronics system throughout the facility to improve the visual and
audio surveillance of youth, including the addition of more closed-circuit television (CCTV) cameras in
high risk areas. These upgrades included the weatherization of security electronics equipment that are
installed on the outside of the facility which are exposed to the outdoor elements and often fail or
prevent effective use as a result. The updates will also increase the overall security and oversight of
the youth by resolving issues with the current system such as blind spots, poor audio quality, poor
visual capabilites, inability to zoom-in on visual surveillance (video), etc. These modifications to our
automated security electronics system, including the installation of a security camera at the
intake/release gate control and security camera, will improve the overall surveillence, security, and
safety of the facility. Additionally, in an effort to improve surveillence, security, and safety of the facility,
the county upgraded room check devices to smart wand technology to ensure the regular and timely
monitoring of detained youth every 15 minutes.
Ventura, Part B
2 Promethean Boards, security screen fencing along the property, purchased furniture items (bench,
sofa set, and coffee table) for lounge seating at the Vocational Center. Purchased books for the
Vocational Center, these will be used to teach life and job skills, assist with career planning, and
promote personal growth. Installed security cameras inside classrooms. Purchased computers for
exams and online courses. Purchased learning modules from Paxton Patterson, used to teach life skills,
and vocational jobs such as building and carpentry.
Yuba, Part B
Paint all interior surfaces, apply interior epoxy floor finish to concrete floors in the 15 bed Secure
Housing Unit (SHU). Weatherproof and paint all exterior surfaces of the 15 bed Secure Housing Unit.
Purchase new privacy doors for two regular shower stalls and one handicap shower stall. Replace
existing fixed stainless dining table/stool with a new folding moveable table for the dining in the
community day area. Purchase television and wall mount bracket to hang TV in main living unit.
Furnish and equip programming spaces with items to include, but not limited to modular seating/large
chairs, table(s) for the designated living space on pod in the main living area. Furnish and equip
indivdiual cell spaces with items to include, but not limited to: new mattresses and storage cabinet(s)
for cells; new pillows, bed sheets, blankets, and towels for distribution to the youth; book shelf, chair
and wall mounted desk for each individual room.Purchase new cameras for the main living facility and
classroom. Purchase hand held radios for staff and mobile security screening systems/metal detectors.