CSA
Summary
Read the report at California State Auditor ↗
Energy
Deregulation:
The State’s Energy Balance Remains
Uncertain but Could Improve With
Changes to Its Energy Programs and
Generation and Transmission Siting
May 2001
2000-134.2
rotiduA
etatS
ainrofilaC
S
T
I
D
U
A
E
T
A
T
S
F
O
U
A
E
R
U
B
The first five copies of each California State Auditor report are free.
Additional copies are $3 each, payable by check or money order.
You can obtain reports by contacting the Bureau of State Audits
at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
Alternate format reports available upon request.
Permission is granted to reproduce reports.
C S A
ALIFORNIA TATE UDITOR
ELAINE M. HOWLE STEVEN M. HENDRICKSON
STATE AUDITOR CHIEF DEPUTY STATE AUDITOR
May 21, 2001 2000-134.2
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its audit report concerning the
operations of the State Energy Resources Conservation and Development Commission (energy commission) and the California
Public Utilities Commission (CPUC) and the role each plays in the State’s deregulated energy market.
This report concludes that a growing demand for electricity, the failure of true competition to develop, and a lack of new power
plant construction proposals have all contributed to California’s current energy crisis. It is also likely that this summer’s
demand will outstrip supply, and California will have to endure some level of electricity shortage during the months ahead.
To cope with the energy supply gap, the Legislature passed AB 970, aimed at bringing new supplies of electricity on-line
quickly and reducing energy demand, especially during peak hours. To comply with these mandates, the energy commission
and CPUC have been creating new programs and revising existing ones. However, the estimates and timing for the additional
supplies or reduced demand for electricity associated with several of these programs may not materialize in time to safeguard
the State from power outages this summer. Nevertheless, other efforts such as ensuring that renewable power plants stay in
production and updating building and appliance efficiency standards are helping the State currently or will produce future
electricity savings. Assembly Bill 970 also requires the energy commission and the CPUC to speed up power plant permitting
and reduce limitations of the electrical transmission grid. However, the time it takes the energy commission to approve or
reject applications to site power plants has often exceeded the 12-month limit contained in law, pushing back the dates that
plants will come on-line. Further, the CPUC has not responded to the energy crisis with an expedited process to site urgently
needed transmission lines and frequently takes longer than the law allows to complete environmental reviews of transmission
sites.
Finally, the expectations that consumer choice would create retail competition and drive down the costs of electricity have not
materialized. Energy service providers had little chance to compete in price with the investor-owned utilities because of their
small customer base and inability to negotiate wholesale purchase prices that were low enough to be attractive. Now with the
State acting as the main buyer of wholesale electricity and negotiating long-term contracts with energy generators, consumer
choice may not have a future.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
BUREAU OF STATE AUDITS
555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019
CONTENTS
Summary 1
Introduction 7
Chapter 1
Plans to Reduce Energy Demand by
Summer 2001 Overestimate Potential
Peak Energy Savings 15
Recommendations 40
Chapter 2
Some Long-Term Programs Will Improve
California’s Balance of Energy Supply and
Demand, but the State May Still Need to
Help Prevent Wide Market Swings in Supply 43
Recommendations 55
Chapter 3
Efficient Planning and Permitting of New Power
Plants and Transmission Lines Are Needed to
Address the Energy Crisis in the Long Term 57
Recommendations 83
Chapter 4
Numerous Factors Limited the Success of
Consumer Choice 85
Recommendation 94
Appendix
Projected Demand Reductions and Supply
Additions for Summer 2001 and Beyond 95
Responses to the Audit
State Energy Resources Conservation
and Development Commission 105
California State Auditor’s Comments
on the Response From the
State Energy Resources Conservation
and Development Commission 111
California Public Utilities Commission 113
California State Auditor’s Comments
on the Response From the
California Public Utilities Commission 117
SUMMARY
RESULTS IN BRIEF
I
n 1996 the California Legislature passed Assembly Bill (AB)
1890, deregulating the State’s electricity industry to allow
Audit Highlights . . . energy customers to switch from one of the three investor-
owned utilities to another provider. The California Public Utilities
Despite programs to add
Commission (CPUC), along with the Legislature, believed
supply and reduce demand,
deregulation would bring about free market competition and
the State’s energy balance
remains uncertain: lower electricity costs for the State’s residents and businesses. The
failure of true competition to develop, a growing demand for
(cid:1)
Even with projections to
electricity, and a lack of new power plant construction proposals
the contrary, there is little
assurance that the State have all contributed to California’s current energy crisis. As of
will meet energy supply March 2001, the State Energy Resources Conservation and
needs this summer.
Development Commission (energy commission) projects that
(cid:1) newly legislated programs will bridge the gap between energy
The State Energy
Resources Conservation supply and demand, safely carrying California through a perilous
and Development summer. However, we are concerned that demand will outstrip
Commission’s (energy
supply and that California will have to cope with some level of
commission) AB 970
demand reduction electricity shortage.
programs are estimated to
save 281 megawatts at
In September 2000, after a summer when the fragility of the
June 1, however, over
energy supply became painfully evident as rolling blackouts hit
one-half of this savings is
expected to come from the San Francisco Bay Area, the Legislature responded by enacting
programs that are AB 970. This legislation primarily aims to bring new supplies of
voluntary in nature.
electricity on-line quickly and to reduce energy demand through
(cid:1) incentives to customers who cut back their energy use, especially
The California Public
Utilities Commission’s during peak summer hours. As summer 2001 approaches,
(CPUC) interruptible California’s citizens are concerned that the blackouts occurring
program—the State’s
on four separate days of this past January and March are only a
buffer for avoiding rolling
blackouts—includes many prelude to what may happen in July and August, when demand
customers who were not for air-conditioning will peak. Although the energy commission
prepared to reduce their
estimates that California will have enough new supply and
demand for electricity. The
reduced demand to avoid rolling blackouts this summer, uncer-
CPUC recently changed
the program, but its tainties in its projections regarding these programs leave little
viability will not be known assurance that the State will escape further power outages. To
for some time.
comply with AB 970’s mandates, the energy commission and the
CPUC have been creating new programs and revising existing
ones. Among other features, these programs aim to cut energy
continued on next page . . .
use in commercial and state buildings, install energy-efficient
traffic lights, and install heat-reflective roof surfaces. The energy
commission estimates that its new Peak Load Reduction Program
1
can save 281 megawatts (MW) of power by June 1, 2001, but
(cid:1)
Changes the energy more than half of this savings depends on building owners and
commission made to operators complying with repeated requests to reduce air-condi-
building and appliance
tioning and other power use during the hot summer months.
standards will not result in
energy savings this Moreover, the CPUC’s costly new efficiency programs, aimed at
summer but will benefit residential and small business consumers, have many unresolved
the State in 2002
problems, including a similar consumer compliance issue. Finally,
and beyond.
the CPUC in reviewing its interruptible program (program),
(cid:1) Since 1996 the energy which for some years has had a mechanism to free up electricity
commission has approved during peak demand hours, has found that program participants
12 power plants, but
are unprepared for frequent requests to curtail energy use. The
only 4 of those within
megawatts these programs are estimated to supply or save are
12 months, its
statutory goal. summarized in the Appendix.
(cid:1)
Despite adding three
Although the energy commission’s updating of the building and
new processes to hasten
power plant siting, only appliance efficiency standards mandated by AB 970 will not lower
one will add a significant this summer’s energy demand, this effort will produce future
amount of energy to the
electricity savings. The Renewable Energy Program, part of the
State’s supply in time for
1996 legislation that deregulated electricity in California, is also
summer 2001.
currently helping the State through this precarious time by
(cid:1)
The CPUC does not have
ensuring that renewable power plants—plants fueled by renewable
an expedited transmission
sources such as the wind—stay in production and continue to
siting process for urgent
projects. provide enough electricity to power about 4.4 million homes.
(cid:1)
Although the CPUC relies
In addition to mandating new efficiency programs, AB 970
on them for approving
transmission projects, the requires the energy commission and the CPUC to speed up power
investor-owned utilities’ plant permitting and to address the limitations of the electrical
projections of trans-
transmission grid. Although legally required to reject or approve
mission demand growth
power plant siting applications within 12 months of the completion
may not be reliable.
of an application, the energy commission generally does not
Finally, because of the State’s
meet that time goal. By pushing back the dates that plants come
role in purchasing electricity
on-line, these siting delays have kept badly needed megawatts
for the investor-owned
utilities, it remains unclear from being available to relieve energy shortages. Since 1996 the
whether retail competition is energy commission has approved 12 plants for construction
consistent with the State’s
using its standard siting process. If the siting for these plants had
goal of returning the utilities
taken the 12 months specified by law and assuming no changes in
to a credit worthy status.
their construction schedules, one plant would be operating now
and a second would be coming on-line this June, by which time
the 2 plants would be contributing 1,059 MW of power to the
State’s transmission grid. Both these power plants are now esti-
mated to be operational in July 2001.
The time it takes the energy commission to site power plants has
lengthened since the early 1980s, as more private power companies
that are less familiar with the application process have planned
larger plants that take more time to evaluate than the previous
2
smaller ones. The energy commission also reports that public
opposition to power plants, application project changes, and
delays of other involved agencies have caused recent siting
delays. Although it has made changes to speed up its siting
process, the energy commission is not evaluating the results of
these changes, and so it cannot be sure that the power plant
siting process will be improved. Recently, the energy commission
began using three new expedited siting processes of varying
lengths, but it estimates only one process will add a significant
amount of energy (several hundred megawatts) to the State’s
electricity supply in time for this summer’s peak demand.
Unlike the energy commission’s effort to expedite power plant
siting, the CPUC has not responded to the current energy crisis
with a faster process to issue transmission line permits for its
more urgent projects. Not only does a congested transmission
grid risk power outages under adverse conditions, but congested
lines increase costs for buyers of wholesale electricity because
such congestion triggers price surcharges. Although the lack of
transmission lines to transfer power from the southern to the
northern parts of the State caused rolling blackouts in Northern
California on January 17 of this year, the CPUC has not acted to
expedite transmission siting. In almost half of the transmission
permits the CPUC considered after 1990, its environmental
review process has taken considerably longer than prescribed
timelines set up by the California Environmental Quality Act.
Major causes of the CPUC’s delays are the need to coordinate
with the federal government on some projects, a slow process for
contracting with consultants, and other involved agencies’ late
permitting requirements. Although one of these causes is out of
its control, and even though it has tried to minimize the
contracting delays, the CPUC has not addressed the delayed
involvement by other agencies.
Further complicating the transmission picture, applications for
transmission projects come from the State’s three investor-owned
utilities, which are primarily responsible for transmission planning.
However, the utilities’ transmission plans use varying assumptions
about demand growth in their respective service areas. Not only
do these three individual plans hinder comprehensive statewide
planning, but the utilities may often have little economic incen-
tive to expand transmission lines in their respective areas because
the increased transmission capacity would simply allow competition
by other power generators. Thus, the investor-owned utilities’
projections of transmission demand growth may not be reliable.
3
When deregulation was implemented in March 1998, the Legisla-
ture and the CPUC had great expectations that consumer choice
would create retail competition and drive down the costs of
electricity. Unfortunately, the details of deregulation provided
little incentive for customers of investor-owned utilities to switch
providers. As a result, true competition never emerged, and
Californians never received the supposed benefits of “direct
access” to energy providers. The independent energy service
providers (ESPs) had little chance to compete in price with the
investor-owned utilities because of their small customer base and
inability to negotiate low enough wholesale purchase prices.
Also, the ESPs found that electricity is not a product they could
endow with brand recognition. Now, with the State being the
main buyer of wholesale electricity and negotiating long-term
contracts with energy generators, consumer choice may not have
a future—because expanding competition now could result in the
State paying for unneeded power.
Even if retail competition had taken hold in California, an ideal
model of free market forces may not exactly fit the electricity
industry. In theory, a lack of supply drives up prices and creates
an economic incentive for energy producers to build more power
plants. But because the process of bringing a power plant on-line
takes several years from the initial planning to the delivery of
power, energy producers may not be able to respond quickly
enough to market signals, resulting in boom-bust cycles as they
adjust to shortages and excesses of electricity. To spare residents
and businesses in California the effects of disruptive swings in
the energy supply, the State may need to continue to play a part
in energy planning. As the State’s primary energy policy agency,
the energy commission (in the former regulated energy market)
used to ensure that the investor-owned utilities did not build too
many power plants. Now the energy commission may need to
take on an expanded role of planning for electricity supply,
ensuring that neither too many nor too few power generation
plants are built.
RECOMMENDATIONS
To provide the Legislature with information it could use to
measure whether and to what extent legislative action is needed
to help California meet its energy supply and demand needs in
the future, the energy commission should do the following:
4
(cid:127) Consult with the California Independent System Operator and
develop an annual projection of summer supply compared to
peak demand that acknowledges the full range of constraints
within the State’s electricity system, including transmission
constraints.
(cid:127) As part of its projection, provide the Legislature with a
range of possible supply and demand outcomes that reflect the
likelihood that the underlying assumptions will prove true.
To ensure that it achieves its goal of reducing peak demand on an
ongoing basis, the energy commission should consider modifying
its Peak Load Reduction Program as follows:
(cid:127) As a condition of program participation, require participants in
its commercial building program to meet specified compliance
levels for reducing lighting and the energy used to power
air-conditioning levels for a certain period of time, such as
24 months. If the compliance levels are not met, the participants
should be penalized. After 24 months, the participants’
compliance could become voluntary.
(cid:127) Develop a plan to actively evaluate itself and program partici-
pants in all components of the program against set milestones,
such as:
♦ Securing a certain number of participants by milestone dates.
♦ Verifying that equipment is ordered and delivered by sched-
uled due dates.
♦ Ensuring that projects are installed, tested, and operational
according to scheduled dates.
In an effort to maximize energy conservation over the next
several years, while at the same time making the best use of
funds collected from the utilities’ ratepayers, the CPUC should
expand conservation measures to include those types of customers
that will produce the most energy savings. This may not necessarily
prompt the CPUC to abandon more costly residential and small
commercial programs in favor of larger commercial, industrial, or
governmental projects, but it will permit the CPUC to take
advantage of potentially greater energy savings at a lower cost
to ratepayers.
To help the State avoid large swings in the supply of electricity
relative to demand, the Legislature and the energy commission
should consider augmenting the energy commission’s role in
5
electricity planning. For example, the energy commission’s
existing planning role could be expanded to include integrating
supply and demand projections and using them as a basis for
making decisions regarding whether to site new power plants.
In assessing the future role of retail competition, the CPUC
should consider the effects of competition at the retail level to
evaluate whether retail competition is viable in the current
market environment, in which the State is the primary purchaser
of electricity for the investor-owned utilities.
AGENCY COMMENTS
The CPUC stated that it is working on a number of efforts to
improve reliability, including energy efficiency programs,
transmission planning and siting, and programs that interrupt
the energy used by large customers and stated that the efforts are
often consistent with our recommendations. The CPUC did
express concerns that emphasizing only those energy efficiency
programs with the largest savings presents equity issues in
allocating funds for those programs. Moreover, the CPUC offered
several aspects that it believes new legislation for expedited
transmission siting should include. Finally, the CPUC agreed
that the actual success or failure of changes it made to its inter-
ruptible program will not be immediately known, but noted that
these changes were developed by consensus reflecting many
parties’ input.
The energy commission noted that the State is facing significant
challenges and one of the primary contributors to the crisis is
electrical generators’ withholding of needed power supplies. The
energy commission also stated that its siting process is complex
and it works to balance many issues within its timelines but
acknowledged that its average permitting time has run beyond its
statutory timeline. With regard to its Peak Load Reduction
Program, the energy commission stressed that its demand reduc-
tion estimates were conservative and understated the energy
savings that will be achieved. The energy commission disagreed
with our analysis of the commercial buildings demand response
program, stating that there are certain penalties in place which
will substantially reduce the level of potential noncompliance.
However, the energy commission did agree with our analysis of
its water systems replacement program, stating that its tracking
n
could be more systematic.
6
INTRODUCTION
THE RESTRUCTURING OF CALIFORNIA’S
ELECTRICITY INDUSTRY
I
n 1992 California’s high electricity prices and a shift in
federal energy policy prompted the California Public Utilities
Commission (CPUC) to begin a comprehensive review of the
State’s electricity industry. That review led, in 1994, to a formal
rule-making hearing on approaches to deregulation, and by
January 1996, the CPUC had adopted a set of policies to guide
the State’s major investor-owned utilities in restructuring their
operations. Before deregulation, the investor-owned utilities—
Pacific Gas and Electric Company (PG&E), Southern California
Edison (SCE), and San Diego Gas & Electric Company (SDG&E)—
had a virtual monopoly on their electricity markets. Not only did
they own most of the power plants, the three investor-owned
utilities also controlled the transmission and distribution of
electricity to retail customers. The primary idea behind deregulation
was to allow other energy producers into the market, breaking
the utilities’ retail monopoly with the expectation that doing so
would increase competition and lower the price of electricity.
In 1996 the Legislature passed Assembly Bill (AB) 1890, which
enacted many of the CPUC policies for deregulating the electricity
industry in California. Under this newly restructured system,
retail customers of all sizes were allowed to choose their electricity
suppliers, although they could continue to maintain service with
their investor-owned utilities if they desired. The Legislature also
created two nonprofit public-benefit corporations, the California
Power Exchange (PX) and the California Independent System
Operator (ISO), designating the PX as the State’s commodity
market that facilitated the buying and selling of wholesale electrical
power through a competitive auction.1 The ISO gained control of
the statewide transmission system and is responsible for the
reliable operation of the system that supplies wholesale power to
the State’s investor-owned utilities. Because the State imports and
exports electricity, the Federal Energy Regulatory Commission
(FERC) is also central to California’s deregulated energy industry.
FERC oversees the rates, terms, and conditions governing the
1 On January 31, 2001, the PX ceased trading; it filed for bankruptcy shortly thereafter.
7
interstate sale and transmission of wholesale power and is
responsible for ensuring that wholesale electricity rates are just
and reasonable.
THE STATE ENERGY RESOURCES CONSERVATION AND
DEVELOPMENT COMMISSION AND THE CALIFORNIA
PUBLIC UTILITIES COMMISSION
Two other regulatory entities that play important roles in the
deregulated energy market are the State Energy Resources Conser-
vation and Development Commission (energy commission) and
the CPUC. Created in 1974 by the Warren-Alquist State Energy
Resources Conservation and Development Commission Act, the
energy commission is the State’s primary energy policy and
planning agency, working to ensure that a dependable supply of
energy exists to meet California’s needs and at the same time
monitoring compliance with environmental, safety, and land use
goals. Comprising five commissioners appointed by the governor
to staggered five-year terms, the energy commission has experi-
enced little change in its role since the passage of AB 1890, the
State’s electricity deregulation law.
Among its responsibilities, the energy commission processes
applications for siting new power plants; encourages measures to
reduce wasteful and inefficient use of energy; and collects and
analyzes information regarding alternative ways to conserve,
generate, and supply energy. State law gives the energy commission
broad authority to decide that a power plant is in California’s best
interest and to approve the plant despite opposition based on
significant adverse environmental impacts, such as air pollution
or water contamination. Nevertheless, in siting power plants, the
energy commission takes into account the California Environmen-
tal Quality Act (CEQA), a law requiring the State to perform an
environmental review of all new projects, including power plant
projects, that may have a significant effect on the environment.
The energy commission’s siting process is not required to
follow CEQA guidelines precisely, because the California Resources
Agency has certified the energy commission’s siting process as
being essentially equal in function and purpose to CEQA. The
energy commission is also responsible for the following:
8
(cid:127) Forecasting future energy needs and keeping historical data.
(cid:127) Performing independent analyses of demand growth.2
(cid:127) Licensing thermal power plants3 that are 50 megawatts4 (MW)
or larger. Thermal power plants are ones that derive electric
power from a source of heat, including natural gas, oil, coal,
nuclear, geothermal, and solar sources. Plants smaller than
50 MW are licensed by city and county agencies.
(cid:127) Developing energy technologies and supporting renewable
energy programs.
(cid:127) Promoting energy efficiency through appliance and
building standards.
Whereas the energy commission focuses on energy policy and
planning, the CPUC regulates the investor-owned utilities in the
State and ensures that California utility customers have safe,
reliable utility service at reasonable rates by establishing service
standards and safety rules and authorizing utility rate changes.
To protect consumers, the CPUC also prosecutes unlawful utility
marketing and billing activities and resolves customer complaints
against utilities. Under AB 1890, the CPUC is charged with:
(cid:127) Facilitating competition at the retail level.
(cid:127) Regulating retail rates charged by investor-owned utilities.
(cid:127) Registering alternative energy service providers.
(cid:127) Implementing consumer protection provisions relating to retail
electricity services.
(cid:127) Implementing education programs about retail electricity
services.
(cid:127) Ensuring retail power reliability.
2 The energy commission is no longer required to make findings regarding the
conformance of individual power plants with the analysis of demand growth.
3 The State Water Resources Control Board and FERC license all hydroelectric power
plants regardless of size; the CPUC also helps license hydroelectric power plants
greater than 50 MW.
4 At any given time, one 100 MW power plant provides enough power to supply
roughly 100,000 households.
9
The CPUC is also responsible for evaluating the economic need
for additional transmission lines, for siting transmission lines, and
for reviewing the reasonableness of transmission construction
costs for rate-making purposes. As part of its transmission line
siting process, the CPUC analyzes environmental consequences
and determines whether transmission projects are justified and
necessary. It also regulates investor-owned telecommunication
and transportation companies. The CPUC comprises five commis-
sioners appointed by the governor to staggered six-year terms.
CALIFORNIA’S CURRENT ENERGY CRISIS
California’s ongoing energy problems converged in the summer
of 2000, causing wholesale electricity prices in the spot markets—
commodity markets that sell electricity—to reach very high levels.
The wholesale energy prices were symptomatic of deeper problems,
some of which—like the weather and recent high natural gas
prices—were beyond state regulatory control. For example,
abnormal weather patterns in the western region in the summer
of 2000 exacerbated a long-standing energy imbalance, in which
demand for electricity increased faster than the supply in California.
However, the legislated terms of deregulation and the way in
which it was implemented also added to California’s power woes.
For example, the CPUC initially required the investor-owned
utilities to sell and purchase all of the electricity they needed to
serve their customers on the volatile spot market. At the same
time, the two largest investor-owned utilities were unable to pass
on much of these higher wholesale costs to their customers
because of the legislated freeze on retail rates. As a result, by
December 2000, both PG&E and SCE had amassed huge debts
and teetered on the verge of bankruptcy. Moreover, because of
the deteriorated credit status of these two investor-owned utilities,
the State had to step in as the primary purchaser of electricity for
most Californians, beginning in mid-January 2001.
On four separate days in early 2001 (two days in January and two
in March), severe energy shortages forced the ISO to order the
major utilities to cut power to millions of citizens, using rolling
blackouts to keep the State’s electricity system from crashing.
Recently, the CPUC approved a rate increase that—depending on
the time and energy usage—could range anywhere from no
increase at all up to 47 percent for residential customers of PG&E
and SCE, hoping that it would allow them to repay the State for
its power purchases, restore their creditworthiness, and encourage
10
conservation during the summer of 2001. Nevertheless, PG&E
had already voluntarily filed for Chapter 11 bankruptcy protec-
tion in federal court on April 6, 2001.
Recognizing that California is facing potentially serious electricity
shortages that call for immediate action, the Legislature crafted a
number of bills aimed directly at quickly increasing energy
supply and reducing demand. In August 2000, the Legislature
passed AB 970, the California Energy Security and Reliability Act
of 2000. This legislation mandates that the energy commission
and the CPUC hasten to bring new power plants on-line, address
limitations in the electrical transmission and distribution system,
and make significant new investments in conservation. However,
the primary purpose of the legislation is to reduce demand during
peak hours in time for summer 2001. AB 970 requires the energy
commission and the CPUC to implement demand reduction
programs, including ones offering incentives to electricity
customers who take specific steps to conserve and ones aimed at
reducing demand for electricity during peak periods. Some
features of these programs include the following:
(cid:127) Installing energy-efficient traffic lights and heat-reflective
roof surfaces.
(cid:127) Replacing aging equipment owned by public and private water
systems with more efficient models.
(cid:127) Developing systems to cut the energy used by commercial and
state buildings for heating, air-conditioning, and lighting.
(cid:127) Installing Internet-based technology to adjust thermostats in
homes and small commercial businesses.
SCOPE AND METHODOLOGY
The Joint Legislative Audit Committee requested the Bureau of
State Audits to assess the structures, operations, and overall
functionality of the PX and ISO and their contributions to the
rising cost of wholesale electricity in California. In March 2001
we issued a report on the PX and ISO titled Energy Deregula-
tion: The Benefits of Competition Were Undermined by Structural
Flaws in the Market, Unsuccessful Oversight, and Uncontrollable
Competitive Forces. While working on that report, however, we
realized the integral roles played by the energy commission and
11
the CPUC in California’s deregulated energy market, specifically
in the siting and planning of power plants and transmission lines
and in the implementation of energy conservation and demand
response programs. Thus, we are issuing this second report on
energy deregulation, focusing on the responsibilities of the
energy commission and the CPUC in the State’s energy market.
To gain an understanding of these two commissions’ roles in the
State’s energy market, we reviewed relevant federal and state laws
and regulations, including CEQA. In addition, we studied relevant
sections of procedures and protocols used by the energy commis-
sion and the CPUC. We also interviewed energy commission and
CPUC staff to understand how the entities operate and their
respective roles in deregulation and in responding to the energy
crisis. Further, we reviewed internal documentation of the two
entities to understand and assess their decision-making processes.
To understand California’s likely electricity supply and demand
balance for summer 2001, we analyzed projections by the energy
commission and ISO, and obtained the Legislative Analyst’s Office
evaluation of these projections. We also interviewed energy
commission and CPUC staff and examined historical documenta-
tion of events that contributed to the current energy shortage.
To gain an understanding of the energy commission’s various
power plant siting processes and certain ongoing changes, we
examined laws, regulations, and other documentation and
interviewed energy commission staff. We also analyzed data
related to the energy commission’s 12-month siting process to
determine how long the process takes and how that length has
changed over time. For certain siting applications that took in
excess of 12 months, we spoke with energy commission staff and
examined staff analyses of siting applications, energy commission
siting decisions, and other materials to determine the causes of
the delay.
To understand the CPUC’s transmission siting process, we exam-
ined the relevant laws, general orders, and other documentation
and interviewed CPUC staff. We analyzed data related to the
length of the CPUC’s transmission siting process and conducted
interviews and examined documents, such as environmental
documents and correspondence, to determine the causes of
delays in the siting process.
12
To determine the extent to which the energy commission and the
CPUC have implemented AB 970, we reviewed program guidelines,
status reports, and project contracts. We also interviewed
appropriate staff and looked at independent reviews prepared by
other entities critiquing these programs. Further, we evaluated
the CPUC’s decisions related to energy efficiency programs, drafts
of proposed programs, and information submitted by the investor-
owned utilities regarding their implementation of these programs.
To understand the CPUC’s role in consumer choice, we examined
reports, orders, and decisions made by the commissioners, inter-
viewed staff, and assessed the effectiveness of the decisions that
were made. Finally, to determine the outcome of consumer
choice, we analyzed the investor-owned utilities’ monthly data
reports showing the number of former utility customers who had
selected other energy service providers and the number of utility
n
customers, broken down by customer classes.
13
Blank page inserted for reproduction purposes only.
14
CHAPTER 1
Plans to Reduce Energy Demand by
Summer 2001 Overestimate
Potential Peak Energy Savings
CHAPTER SUMMARY
T
he State faces immediate electricity supply and demand
concerns that first became apparent in the summer of
2000. As California’s wholesale electricity prices shot up,
some consumers’ utility bills tripled, and two investor-owned
utilities reported losses in the billions of dollars. Further, in
January and March of 2001, Californians experienced four separate
days of rolling blackouts, estimated to cost businesses millions
of dollars.
As summer 2001 approaches, the State’s citizens are asking
whether there will be further outages. In order to estimate the
State’s supply and demand balance for summer 2001, the California
Independent System Operator (ISO) and the State Energy Resources
Conservation and Development Commission (energy commission)
have developed projections of supply and demand. In addition,
the Legislature requested that the Legislative Analyst’s Office
(LAO) evaluate whether the ISO’s and the energy commission’s
projections were reasonable. Although both the ISO’s and energy
commission’s projections indicated a potential supply shortfall in
summer 2001, the energy commission identified new programs
that it believes should be adequate to avoid an electricity shortage.
However, certain assumptions in the projections—such as power
plants not operating and consumer response to conservation
programs—leave room for uncertainty regarding whether
California’s residents and business owners will be secure from
power outages in the summer ahead.
In anticipation of these summer outages, both the energy commis-
sion and the CPUC have set up programs mandated by Assembly
Bill (AB) 970, which the Legislature passed in August 2000 and
became effective in September 2000, to reduce peak energy
consumption and establish new levels of energy efficiency state-
wide. For example, the energy commission created the Peak Load
Reduction Program, which contracts with public and private
entities to reduce peak demand by various means, including
installing heat-reflective roof surfaces and developing systems to
15
cut electrical use in commercial and state buildings during peak
demand periods. However, the energy commission’s projection
that the Peak Load Reduction Program can save 281 megawatts
(MW) of power by June 2001 is unduly optimistic. Over half of
this savings relies on the unlikely scenario of building operators
accepting repeated requests to reduce electricity use during the
hot summer months.
Established in the mid-1980s, another program to reduce peak
energy use is the CPUC’s interruptible program (program), which
can free up more than 2,340 MW of electricity during an energy
crunch. However, this program is in chaos because increased
requests for those in the program to curtail their energy use have
begun to meet with resistance. Customers who are inappropriate
for this program, such as hospitals and nursing homes, signed up
for it to save money on their electric bills, but in reality they are
not prepared to endanger their patients by cutting their power.
The CPUC issued revised program guidelines in April 2001,
intended to stabilize the program and keep it viable for summer
2001. Although the changes appear reasonable, it is not yet
known whether they will be effective.
Adding to the uncertainty of this summer’s energy supply is the
fact that the CPUC may not achieve the energy savings it antici-
pates through the programs it has developed to fulfill AB 970’s
mandate that it expand existing energy efficiency programs and
create new ones. The three investor-owned utilities run the
CPUC’s energy efficiency programs. Despite indications that the
investor-owned utilities may not be meeting their past program
goals and that they failed to provide sufficiently detailed and
effective program plans for implementing AB 970, the CPUC
approved the utilities’ plans in January 2001. As a result, it is
unclear whether the CPUC will successfully achieve its AB 970
program goals.
RECENT PROJECTIONS THAT THE STATE CAN AVOID
ROLLING BLACKOUTS IN SUMMER 2001 ARE BASED
ON ASSUMPTIONS THAT MAY NOT COME TRUE
Despite projections to the Despite projections to the contrary, there is little assurance that
contrary, there is little the State will meet its energy supply needs during the summer of
assurance the State will 2001. Responding to the increased public awareness of
escape rolling blackouts California’s energy crisis, the ISO and the energy commission
this summer. released projections of the State’s likely balance between electricity
supply and demand for the coming summer. Seeking to determine
16
how reliable the ISO’s and energy commission’s projections were,
the Legislature requested that the LAO review the projections for
reasonableness. The ISO’s projection was the most pessimistic,
showing a gap between supply and demand sufficient to cause
The ISO’s and energy rolling blackouts. Although it also indicated a potential supply
commission’s projections shortfall in summer 2001, the energy commission identified new
are based on assumptions programs that could make up the gap. In its evaluation, the LAO
about power outages, modified the energy commission’s projection using more pessi-
customer actions, and mistic assumptions, but it still concluded that the State’s energy
other factors that may supply should be adequate to meet peak demand, although the
not come true. ISO may have to dip into its reserves to do this. The ISO’s and
energy commission’s projections, however, are based on assump-
tions about power plants not operating, customer actions, and
several other factors that may not prove true. Furthermore, the
projections do not consider transmission limitations between
certain parts of the State or expand the prediction to include more
than one possible outcome. Because of these limitations, California
residents and business owners may not be secure from power
outages in the summer ahead.
In February 2001 the ISO and energy commission each issued
projections of electricity supply and demand for summer 2001.5
Focusing on those areas of the State serviced by the transmission
grid it operates,6 the ISO projected electricity shortages of about
5,300 MW during August 2001, unless new supply comes on-line
beyond that already approved or new programs are implemented
that reduce demand.7 The ISO and energy commission projected
that, relative to the other summer months (May through July),
the demand for electricity will be the greatest in August. As
detailed in Table 1 on page 19, a significant portion of these
shortages will simply reduce the ISO’s required 7 percent operating
reserves. However, even if all reserves are depleted, the ISO
projected that the August 2001 peak demand will still exceed
supply by more than 2,100 MW, enough to cause rolling blackouts.
The energy commission projected summer 2001 supply and
demand for the entire state, assuming hotter weather conditions
than the ISO’s projection, but also making more optimistic
5To be consistent in comparing the entities’ projections, we used projections that the
ISO and energy commission issued at about the same time. The ISO has since issued
an updated projection that still projects an electricity supply shortfall in all months
of summer 2001.
6The ISO’s control area is composed primarily of the transmission grids owned by the
State’s three investor-owned utilities, which cover approximately three-fourths of the
State. The rest of the State, including far Northern California and the area served by
the Los Angeles Department of Water and Power, among others, is not under
ISO control.
7The ISO also projects that blackouts will occur in June and July 2001.
17
assumptions than the ISO about the amount of electricity supply
the State could count on from existing independent energy
producers and hydroelectric facilities. Table 1 shows that the
energy commission predicted a supply shortfall of only about
1,200 MW during the State’s peak summer demand, which, as
previously noted, is assumed to be August 2001. Because it is less
than the State’s operating reserve, this shortfall would not result
in rolling blackouts. The energy commission went on to identify
new programs to increase supply and reduce demand that could
make up not only its own projected shortfall but the larger
shortfall projected by the ISO as well. Assuming that these new
programs are in place by their stated goal of July 1, 2001, the
State would be able to avoid the late summer shortages projected
by the ISO, thus potentially avoiding rolling blackouts in July
and August. However, the energy commission’s new programs
would not be on-line in time to prevent the shortages the ISO is
predicting for June 2001.
On March 5, 2001, the Legislature requested the LAO to determine
whether the ISO’s and energy commission’s projections were
reasonable and whether legislative action was required to meet
The LAO determined peak electricity supply and demand needs for summer 2001. The
the energy commission’s LAO’s analysis, issued on March 13, found that the energy
projection was optimistic commission’s projection was too optimistic and revised downward
and revised several several estimates of programs that added supply or reduced
estimates downward. demand. Despite its revisions to the energy commission’s projec-
tion, the LAO still determined that with the new programs the
State would have enough supply in place on paper to meet the
peak electricity demand expected in August. Thus, as detailed in
Table 1, though the ISO’s and energy commission’s forecasts
projected a supply shortfall if no action is taken, the energy
commission projects that new programs will make up the shortfall.
However, both of these projections contain several aspects that may
prevent them from reliably indicating the State’s summer 2001
balance between electricity supply and demand. First, the energy
commission’s projection and the LAO’s evaluation of it is based
on programs whose results are difficult to predict because they
have not been tried before. In fact the LAO acknowledges the
difficulty in making projections about this summer by pointing
out that “roughly one-quarter of potential energy supply is
produced by private generators and there is no guarantee that all
this amount will be sold for use within California.” Moreover, the
LAO noted “numerous assumptions about difficult-to-predict-
factors in arriving at our ‘bottom line’ figures—such as the levels
18
TABLE 1
ISO and the Energy Commission Projections of August 2001
Electricity Supply and Demand (in Megawatts)
After LAO’s
Entity ISO* Energy Commission† Adjustments†
Existing supply, reflecting
expected outages and imports 42,700 56,166 53,991
New supply already approved
and expected on-line by August 2001 2,828 3,741 3,333
Projected peak demand‡ (50,825) (61,125) (61,125)
Projected supply shortfall (5,297) (1,218) (3,801)
Actions intended to alleviate the shortfall by August 2001
New supply 0 1,312 562
Demand reduction 0 6,246 4,301
Projected balance with new supply
and demand programs (5,297) 6,340 1,062
Operating reserves (7%) 3,122 3,999 3,999
Supply and demand balance without
operating reserves (2,175) 10,339 5,061
Source:ISO Estimated Resource Plan 2001, February 1, 2001; Energy Commission California Summer 2001 Forecasted Peak
Demand—Resource Balance; Legislative Analyst’s Office—Report to the Assembly Subcommittee on Electrical Energy
Oversight, March 13, 2001.
* Projection limited to ISO control area.
† Projection includes entire state.
‡ Assumes operating reserve of approximately 7 percent.
of power outages, participation in interruptible programs, availabil-
ity of out-of-state supplies, customer behavioral responses, and
federal actions.”
For example, the energy commission projected a 2,000 MW
reduction in demand due to a public outreach campaign for
which the State may allocate up to $20 million. The LAO’s
evaluation of the energy commission’s projection estimated that
this megawatt savings is significantly overstated and revised it
down to 1,300 MW, explaining in its report that the lower figure
is “consistent with the maximum savings that the ISO was able
to identify during the January stage 3 alerts8 and rolling black-
outs.” Although the lower figure is more realistic, we question
whether anything short of a stage 3 alert and rolling blackouts
would cause Californians to reduce demand for electricity by
8 A stage 3 alert occurs when the ISO’s energy reserves drop below 1.5 percent.
19
1,300 MW. If this is the most Californians have conserved when
threatened with having their power cut off entirely, it seems
unlikely that a public outreach program would be able to achieve
a similar level of savings prior to a stage 3 alert being declared.
Although 1,300 MW may ultimately be saved, it is more likely
that they will be saved after stage 3 alerts have been declared,
rather than to preclude stage 3 alerts. Without operational experi-
ence with a public outreach program or the time to conduct a
detailed analysis of its potential for reducing demand, the energy
commission cannot be sure of the actual level of demand reduction.
Later in this chapter, we conclude that several of the new demand
reduction programs included in these projections may not reach
their stated goals.
Second, the ISO’s and energy commission’s projections do not
take into account transmission constraints, or areas throughout
the State where the infrastructure limits the amount of power
that can flow in and out.9 These constraints can cause blackouts
in certain areas of the State even when overall generation capacity
is adequate to supply the State’s needs, as demonstrated by the
rolling blackouts in Northern California in January 2001. These
blackouts occurred because the primary transmission connection
between Northern and Southern California could not physically
transmit the amount of electricity the north needed, although
Southern California had enough excess supply to make up
Northern California’s shortfall. Thus, even if the forecasts are
correct in predicting an adequate supply to meet California’s total
demand, transmission constraints could still cause rolling blackouts
in parts of the State.
The ISO’s and energy commission’s analyses do not provide
adequate assurance that the State will meet its energy supply
needs because they do not provide enough information to assess
The Legislature may be how likely their scenarios are, thus reducing their usefulness to
better served by future the Legislature. Although the energy commission issued demand
projections that reflect a projections for several different weather scenarios, each with a
best, worst, and average given probability of occurring, it did not do so for supply. Each of
case scenario from which the two projections of possible new supply additions included
to gauge how urgent its only one possible outcome. Although we recognize that these
actions are. entities were not asked to provide more than a single supply
projection, we believe that a range of supply possibilities (such as
a best, worst, and average case scenario) would better serve the
Legislature. From such a range, the Legislature could see how
9The ISO’s subsequent projection prepared in March 2001 explicitly acknowledged
the possibility that transmission constraints could cause rolling blackouts.
20
urgently needed and how useful its actions might be to increase
California’s chances of meeting its future energy supply and
demand needs.
THE ENERGY COMMISSION’S PEAK LOAD REDUCTION
PROGRAM MAY MISS ITS ESTIMATE OF ELECTRICITY
TO BE SAVED BY JUNE
In August 2000, in response to the State’s energy problems, the
Legislature passed AB 970, authorizing the energy commission to
use $50 million from the State’s General Fund to create programs
that would reduce peak energy consumption statewide. Known as
the Peak Load Reduction Program, this broad effort aims to reduce
peak demand by 200 MW from June 1 through September 30
for a four-year period beginning June 1, 2001. As recently as
April 23, 2001, the energy commission estimated that by
June 1, 2001, its Peak Load Reduction Program would surpass its
original goal, reducing demand by 281 MW and ultimately
providing as much as 335 MW of peak demand reduction.
However, the energy commission may be overly optimistic in
its 281 MW estimate. This is because more than half of its
estimated 281 MW savings are projected to come during periods
of high demand from the voluntary curbing of electricity use in
commercial and state government buildings located throughout
California. Although state government facilities are more likely to
comply for financial and political reasons, it may be unrealistic to
expect operators of commercial buildings to turn up thermostats
voluntarily, and the energy commission has no way of penalizing
participants if they fail to comply. Unless at least 50 percent of
these building operators comply, the program will not meet
its original goal of saving 200 MW, let alone the energy
commission’s higher estimate. Also, the energy commission’s
efforts to monitor its water-systems equipment program, which
provides grants to replace inefficient water pumps and equipment
with more efficient models, may not be sufficient to ensure that
each project scheduled will actually be completed by June 1, 2001,
in time to provide the planned peak demand reduction for June,
which represents 17 percent of its estimated peak energy savings.
Through the Peak Load Reduction Program, the energy commis-
sion has implemented six separate programs to accomplish such
goals as to install energy-efficient traffic signals and heat-reflective
roof surfaces, replace aging water-systems equipment with more
efficient models, and develop systems to cut electricity use in
21
commercial and state buildings during periods of high demand.
These programs and their estimated megawatt savings are sum-
marized in the Appendix.
The Energy Commission May Not Achieve Its Estimated
281 MW Peak Demand Reduction
One part of the Peak Load Reduction Program provides $10 million
to assist commercial building owners with the installation of
The energy commission computerized systems to reduce heating, ventilation, and air-
may be overly optimistic conditioning and lighting levels during ISO alerts and/or peak
in estimating its peak demand periods. The energy commission will also use $5.5 million
demand savings since to help certain state-owned and operated facilities develop cus-
over one-half of the tomized peak demand reduction plans. It estimates that these
savings will come from programs will reduce peak demand by 186 MW of the estimated
the voluntary actions of 281 MW reduction to be achieved by June 1, 2001. However,
program participants. these estimates may be overly optimistic if operators of commercial
and state buildings do not always reduce energy use when called
on to do so. Because actual energy savings will depend on the
operators’ responses to potentially frequent requests to reduce
electricity use, the actual megawatt savings this program will
provide are uncertain. This uncertainty does not give Californians
much assurance that they will be spared rolling blackouts in the
coming summer months.
For the energy commission to achieve its estimated 186 MW
goal, all participants in these programs will have to act as
planned: During hours of high demand or when the ISO issues a
signal to reduce energy usage, operators of commercial and state
buildings need to adjust the buildings’ lighting and air-conditioning
or take other actions to reduce peak energy consumption. Although
this plan sounds fairly simple, these programs have several
inherent risks. First, the contractors who install the computerized
systems in commercial buildings to monitor energy use are
required to offer a method to override the emergency signal. State
facility operators will manually execute the energy reduction
tasks in response to an ISO directive or during hours of high
demand. Therefore, each commercial and state building operator
has a choice to comply with the directives to reduce energy
consumption during peak hours. An energy commission program
manager said that the override function was needed to convince
22
commercial building owners to participate in the program. How-
ever, unless there is substantial voluntary compliance with
requests to curtail energy use, the energy commission will likely
not achieve its estimated megawatt savings.
Moreover, the energy commission does not plan to penalize those
building owners or managers who override the signal, increasing
the likelihood of noncompliance. For example, assume that the
owner or manager of a commercial building is signaled to cut
lighting by 25 percent and adjust the temperature to 77 degrees
twice a week for the duration of the summer. If the owner or
manager is influenced more by angry tenants than by a desire to
help during the State’s energy crunch, and there is no incentive
to comply (such as a penalty), the end result may be more frequent
The ability of operators overrides of the building’s system. With the resulting lack of
to override emergency energy savings during peak periods, the State faces a greater risk
signals to curtail energy of rolling blackouts during peak periods.
use without fear of
penalty for non- Compared to the owners and managers of commercial buildings
compliance, increases the participating in the program, state building operators may have
risk of rolling blackouts more of an incentive to comply with demand reduction directives
during peak periods. because they are financially and politically answerable to the
State’s policy makers. Nevertheless, although the ISO observed a
measurable reduction in demand during a test of several state
agencies who participated in a similar effort in summer 2000,
tenant attitudes, facility operator preferences, and human error
could potentially affect the energy commission’s estimated goal
to reduce energy use in state buildings.
We combined the estimated megawatt savings for the commercial
and state building programs and calculated a range of peak
energy savings based on a possible range of building and facility
operator compliance. As Table 2 demonstrates, if compliance
among participants in the state and commercial building programs
drops to 70 percent, the State will lose roughly 56 MW of the
energy commission’s estimated June 1 demand reduction. If only
half of the buildings respond to the signal to reduce their energy
consumption, the gap widens to 93 MW. Moreover, assuming
that the full measure of demand reduction is achieved in the
other program areas, such as water-systems replacement and
traffic signal retrofit, compliance by 50 percent or less of the
building operators will keep the State from achieving the 200 MW
demand reduction—the minimum amount originally envisioned.
23
TABLE 2
Range of Peak Energy Savings Based on a Possible Range of
Building and Facility Operator Compliance (in Megawatts)
Percent of Commercial
and State Buildings That
Comply With Demand Difference in Total Program
Reduction Directives Projected Reduction Demand Reduction*
100% 0 281
90 (18) 263
80 (37) 244
70 (56) 225
60 (74) 207
50 (93) 188
40 (111) 170
30 (130) 151
* This assumes that all other Peak Load Reduction Program areas achieve their full estimated demand reduction.
The energy commission could also do more to ensure that partici-
pants in its water-systems replacement program meet their peak
energy demand goals. Through grants to entities that supply
water to the public, the program subsidizes the replacement of
inefficient water pumps and equipment with more efficient ones.
Because this program is the energy commission’s third largest
effort in the Peak Load Reduction Program and represents
17 percent of the total energy savings estimated by June 1, 2001,
we would have expected the energy commission to be actively
evaluating itself and program participants against set milestones
such as the following:
(cid:127) Securing a certain number of participants by set dates that
represent the megawatt reduction goal to be reached.
(cid:127) Verifying that equipment is ordered and delivered by set dates.
(cid:127) Ensuring that equipment is installed, operational, and tested
by set dates.
However, based on our discussions with the manager of the
water-systems replacement program, these types of activities
have not occurred. As of April 24, 2001, the manager and his
24
staff had communicated with program participants on the phone,
received progress reports from participants, and visited at least 2
of approximately 64 pending project sites. However, the manager
indicated that because of limited resources, neither he nor his
staff would visit all of the sites. Rather, the manager intends to
have his staff call all of the grantees around June 1 to determine
whether the equipment has been installed and is operating.
Without monitoring itself and project participants against estab-
lished milestones such as those listed, the energy commission
reduces its chances of achieving its peak energy reduction goals
for this program. Thus, the energy commission may be overly
optimistic in estimating a peak demand reduction of 281 MW by
June 1, 2001.
SERIOUS PROBLEMS WITH THE INTERRUPTIBLE
PROGRAM MAKE ITS FUTURE UNCERTAIN
Since the mid-1980s California’s investor-owned utilities have
operated the interruptible program (program), which offers
discounted electricity rates to customers who agree to curtail
their energy use when demand is high and the reliability of the
electricity system is jeopardized. The CPUC oversees the
program and recently revised it in an attempt to keep it viable for
summer 2001. However, the program’s effectiveness is threatened
by problems such as noncompliance. Because this vital program
Noncompliance by can free up about 2,340 MW of electricity during an energy
program participants pinch, without it the State faces the increased possibility of
threatens the interruptible rolling blackouts during the hot summer months, adversely
program, which is affecting public health and safety.
capable of curtailing
more than 2,340 MW The program’s instances of actual energy curtailments since 1990
of electricity in an has been minimal. Recently, however, as demand for electricity
energy emergency. has begun to exceed supply, curtailments have become a frequent
reality. Indeed, by the end of January 2001, requests to partici-
pants to interrupt their power use had exhausted most of the
program’s annual ability to request electrical curtailments. Late in
2000, the CPUC began to recognize compliance problems with
the program. With more curtailment requests, more participants
refused to comply, making it difficult for the utilities to reduce
demand when the ISO requested. Later, responding to public
health and safety concerns, the CPUC temporarily suspended the
provision allowing participants to opt out of the program and also
suspended all penalties to participants for not curtailing their
25
demand when directed. Finally, in April 2001, the CPUC developed
revisions to the program, meant to maintain its viability through
the summer of 2001. However, it is not yet known whether the
revised program will adequately fulfill its role as a buffer that can
decrease or avoid the need for rolling blackouts.
The Interruptible Program Offers Participants a Discount for
Curtailing Electricity Use During Shortages
This program gives participants reduced electrical rates in exchange
for agreeing to curtail their use of electricity when directed, up to
a certain number of hours per year. The program’s annual cost, in
discounts given mainly to commercial and industrial customers
of the three investor-owned utilities, is more than $220 million a
year and has totaled $2 billion since 1990, according to the
CPUC. Because they use large amounts of electricity, industrial
and large commercial operations are the program’s targets.
However, the size and provisions of the three utilities’ programs
differ. As Table 3 shows, SCE has the largest amount of megawatts
that can be curtailed, and PG&E has the next largest amount.
(Because SDG&E’s program, at 40 MW, is so small in comparison,
our analysis focuses mainly on the SCE and PG&E programs.)
Each year, SCE and PG&E can interrupt a participating customer’s
electricity supply 25 and 30 times, respectively. The combined
duration of these interruptions cannot exceed 100 hours per year
for PG&E customers and 150 hours per year for SCE customers.
When curtailments are needed, the utilities notify their custom-
ers, giving them 30 minutes to reduce their electrical use. The
financial incentive for participating customers is significant—
discounts of about 15 percent of their electricity cost. This
discount is tied to how much energy is subject to interruption,
Tight energy supplies in which customers can designate up to 100 percent. If they do not
January 2001 nearly reduce their energy use by the agreed-upon percentage when
exhausted PG&E’s and directed, they are penalized. The penalty is purposely set high, so
SCE’s interruptible that about 10 to 25 hours of noncompliance will consume a
programs—leaving participant’s program discount for the year.
participants less willing
to curtail energy use in
The Program Nearly Exhausted Its Yearly Capacity in
the summer when it is
One Month
most needed.
By the end of January 2001, just four weeks into the new year,
tight energy supplies had already caused PG&E to nearly exhaust
its program, having reached its 100-hour annual limit for the
majority of its program participants. Similarly, SCE had already
called on its participants to curtail power use nearly half of the
26
TABLE 3
Size and Provisions of the Investor-Owned
Utilities’ Interruptible Program
(As of Summer 2000)
SCE PG&E
Amount of curtailable
peak use under contract 1,800 MW 500 MW
Contract terms per participant
Maximum interruptions
per year 25 30
Maximum hours
per interruption 6 6
Total interruptible hours
per year 150 100
Average discount per interruptible
program participant 15% 15%
Source: CPUC Energy Division’s Report on Interruptible Programs and Rotating
Outages, February 8, 2001.
25 times allowable under the program. This extensive use of their
allotted curtailments so early in the year means that they will be
less willing to curtail energy use during the summer, when
curtailment is traditionally needed most to relieve the demand for
electricity. Under this scenario, rolling blackouts are more likely
during the summer, causing cuts in productivity, disruptions to
the economy, and potential threats to public health and safety.
Since 1999 the wholesale electricity market has become more
volatile, subjecting program customers to unpredictable electricity
service. In 2000 and so far in 2001, California’s investor-owned
utilities have dramatically increased the number of interruptions
called for under the program. PG&E and SCE each requested that
their participants curtail power on 20 separate occasions in 2000,
with PG&E requesting curtailments eight times between June
and September alone. In contrast Table 4 shows that prior to 2000
PG&E generally made curtailment requests only one to
five times a year in order to maintain system reliability, and SCE’s
curtailments, even during the summer, were rare.
27
TABLE 4
Number of Curtailment Requests Spiked in 2000
Year PG&E SCE
1992 1 0
1993 1 0
1994 0 0
1995 5 0
1996 4 0
1997 1 0
1998 5 4
1999 2 0
2000 20 20
Source: CPUC Energy Division’s Report on Interruptible Programs and Rotating
Outages, February 8, 2001.
Serious Problems Have Recently Surfaced With the
Interruptible Program
The last few months have revealed the following serious prob-
lems with the program:
(cid:127) Some participants have refused to curtail their electricity use at
all or have not curtailed the full amount promised when
requested.
(cid:127) Some participants were not well suited for the program to
begin with yet had designated all of their energy use as
curtailable.
Because the program acts as a buffer when the State’s electricity
system is threatened, if the program does not deliver the energy
savings it is designed to provide, the possibility of rolling blackouts
increases. In January 2001 in response to risks to public health
and safety, the CPUC suspended certain aspects of the program,
including imposing penalties for noncompliance. Although the
CPUC released a restructuring plan in early April 2001, the
program’s future is uncertain.
28
When Compliance Drops, Rolling Blackouts Are Harder to Avoid
With requests to curb their electricity use becoming more frequent,
an increasing number of participants in the program are refusing
to comply or are not fully complying when asked to curtail their
energy use. When compliance drops, the State’s buffer for avoiding
With frequent requests to rolling blackouts grows thinner. Rather than having the agreed-
curb electricity use, more upon scenario in which a select few experience power curtailments,
participants refuse or do the whole state becomes subject to the health, safety, and economic
not fully comply when effects of blackouts. When PG&E requested its program participants
requested to reduce their to curtail their electricity use eight times over the summer of 2000,
energy use. participants reduced their use by an average of 490 MW, an
average of 19 MW less than they had agreed to under contract. In
contrast, over the same period, SCE’s participants reduced their
electricity use by an average of 1,213 MW, an average of 636 MW
less than called for under contract. Although PG&E’s compliance
rate remained high at 96 percent, SCE’s compliance rate was
relatively low at 62 percent.
Eligibility Resulted in a False Sense of Potential
Energy Curtailment
The CPUC’s energy division analyzed program participation data
for 2000 and concluded that SCE’s relatively low compliance rate
probably resulted from SCE enrolling in its program a number of
customers that were unsuited for the program. Reasoning that
each participant, rather than the utility, can best decide whether
it can sensibly and responsibly interrupt its power upon request,
the CPUC has not previously required the investor-owned utili-
ties to screen program participants, and indeed, SCE lacked
eligibility criteria for its participants. As a result, SCE enrolled
customers such as hospitals, nursing homes, and prisons in the
program, many of which were unwilling or unable to reduce their
energy use when requested. Further, the CPUC found that several
of these participants designated their entire energy use as subject
to curtailment so that they could qualify for lower rates. By doing
so, these participants provided a false sense of security that their
energy use would be available for curtailment, when in reality it
is not feasible for customers providing essential services to curtail
their entire operation. The CPUC’s analysis revealed that in 2000,
the SCE’s compliance rates were only 2 percent for participating
nursing homes, 8 percent for medical offices, and 40 percent for
hospitals. Overall, the CPUC concluded that participants repre-
senting more than 1,000 MW of SCE’s electricity use designated
29
as interruptible should not have been enrolled in the program.
SCE participants— About 60 percent of these participants, representing more than
representing over 600 MW, failed to curtail their use of electricity when requested
1,000 MW—should not to do so, diminishing the program’s buffer against rolling black-
have been enrolled in the outs. Although these customers were assessed over $92 million in
program, and 60 percent penalties, almost all of them had been enrolled in the program
failed to curtail energy use since 1996 and had received at least $300 million in reduced rates
when requested to do so. between January 1, 1998, and December 31, 2000, according to
the CPUC.
The CPUC Has Taken Steps to Improve the Reliability of
the Program
Responding to problems the program is facing as a result of the
current energy situation in the State, the CPUC has evaluated the
program and acted to try to improve it. After stabilizing the
program, the CPUC has restructured its features to allow inappro-
priate customers to exit the program, to offer more reasonable
curtailment time frames, and to require the utilities to screen
customers that offer services related to public health and safety.
Also, the CPUC is overseeing other similar programs to increase
the amount of electricity available to be cut during summer peak
hours. These decisions to restructure the program and to adopt
similar programs seem reasonable, but at a minimum, it will not
be until the summer of 2001 or later that anyone will know for
certain whether the changes to the program will enhance its role
as a buffer that can deliver energy savings and decrease or avoid
the need for rolling blackouts.
Seeing that customers were exiting the program, the CPUC in
October 2000 temporarily suspended the SCE program’s annual
opt-out provisions, preventing customers from departing the
program, or from reducing the amount of energy they originally
agreed to curtail, until March 31, 2001. This suspension allowed
the CPUC sufficient time to evaluate the program and to main-
tain maximum flexibility in shaping it to address reliability
concerns for the summer of 2001. Then in January 2001, the
CPUC waived noncompliance penalties for all customers and also
waived the tracking of the hours and number of curtailments
that counted toward the participants’ program limits. These
actions followed an energy commission recommendation, based
on a threat to public health and safety, noting that multiple
curtailments of electricity had caused pipeline companies to be
unable to deliver petroleum products, leading to shortages of
gasoline, diesel, and jet fuel at a number of California terminals
and ultimately causing a sharp rise in fuel prices across the State.
30
Though prompted by this threat to suspend noncompliance
penalties, the CPUC made it clear that it fully expected all pro-
gram customers to voluntarily respond to the maximum extent
feasible when called upon to reduce their energy usage and to
assist in maintaining a reliable electrical system.
In April 2001 the CPUC released a decision that revised certain
aspects of the program. First, the CPUC reinstated penalties for
noncompliance, as well as an annual opt-out period for SCE
program participants. Based on comments from program
participants, the CPUC concluded that it is reasonable to allow
participants to periodically reassess their ability to curtail power or
the level of power they commit to curtail. Under the reinstated
opt-out period, SCE participants can choose to:
(cid:127) Opt out retroactive to November 1, 2000, if they repay the
discounts received between then and the date they decide to
The CPUC recently opt out.
decided to revise various
aspects of the program in (cid:127) Opt out at the beginning of the next billing cycle and be
an attempt to improve its obligated to pay any penalties incurred for failure to curtail
viability in time for the electricity use when requested through the time the opt out
summer of 2001. is effective.
(cid:127) Opt out at an earlier date, such as a date between when the
SCE notifies its customers that they have a choice and the
beginning of the next billing cycle, if mutually agreeable
to the participant and SCE, and pay any penalties incurred
for noncompliance.
Second, the CPUC developed program limits restricting the
number of curtailments and the length of time that a participant
in any of the investor-owned utilities’ programs can be continu-
ously curtailed. Under the program’s earlier criteria, especially in
January 2001, participants were often asked to curtail their
energy use almost constantly from day to day, placing unreason-
able expectations on them and nearly exhausting the program’s
ability to reduce power demand. The CPUC is now directing the
investor-owned utilities to limit program curtailment requests
directed at individual participants to no more than one 6-hour
event per day, four events per week, and 40 hours total per
month. In contrast, the prior provisions contained no daily,
weekly, or monthly limits, aiding in the rapid exhaustion of the
program’s ability to curtail energy use. The annual hourly limits
for SDG&E will increase from 80 to 120 hours per year, whereas
annual limits for SCE and PG&E will remain unchanged. As
31
indicated in Table 5, the revised program will help participants
avoid shutting down operations continuously over a day or a
week, until the program’s annual limits are achieved. The CPUC
hopes that limiting program participants’ interruptions to reason-
able time frames will increase their compliance and prolong the
program’s viability.
TABLE 5
Revised Provisions of the CPUC’s Interruptible Program
Prior Revised
Interruptions per day Unlimited Maximum of
1 six-hour block=6 hours
Interruptions per week Unlimited Maximum of
4 six-hour blocks=24 hours
Hours per month Unlimited 40 hours
Annual limit PG&E—100 hours PG&E—100 hours
SCE—150 hours SCE—150 hours
SDG&E—80 hours* SDG&E—120 hours
Source: CPUC Decision 01-04-006, April 3, 2001.
*Under the prior program, SDG&E tarriffs required that participants curtail energy
use whenever the ISO declared a stage 2 or stage 3 emergency even when the
participants’ annual maximum hourly limits had been reached.
Third, the CPUC declared that essential customers, such as
hospitals and nursing homes, may continue to participate in the
program, but utilities must screen them against eligibility criteria.
To qualify as essential, a customer must provide goods or services
that are vital to public health, safety, and welfare. The investor-
owned utilities must now discuss with each current and future
customer enrolled in the program whether or not that customer is
reasonably eligible to participate. The CPUC stated that a participant
should demonstrate, for example, sufficient backup generation or
other means to meet essential demand if electrical power is
curtailed. In guiding the utilities regarding consistent criteria to
use in screening for eligibility, the CPUC suggested that each
utility require essential customers to provide a declaration under
penalty of perjury including a statement that they will curtail a
specified percentage of their energy use when called upon and
can continue to meet essential needs when curtailed through
back up generation or other means. To balance these customers’
participation in the program with their need to deliver essential
32
goods or services, the CPUC also directed the utilities to limit the
amount of energy curtailment an essential participant could
commit to the program to no more than 50 percent of the
participant’s average peak demand.
Finally, the CPUC will oversee other related programs that may
increase the amount of electricity available to prepare for tight
supplies this summer. One of these, the Base Interruptible Program,
is a version of the program, giving customers rate discounts for
designating a portion of their energy use as interruptible and
being subject to curtailments of up to 120 hours per year. New
participants or those in the existing program who have fulfilled
Other interruptible the annual maximum obligation under the program can partici-
programs, such as the pate in the Base Interruptible Program. Also, the Voluntary
Base Interruptible Demand Response Program allows customers to reduce demand
Program and Voluntary voluntarily on any given day. Either the day before or the day of
Demand Response the needed cutback, the utilities will notify participants of requested
Program, may attract energy reductions, and participants will receive a cash payment of
new customers and make 35 cents per kilowatt hour of reduction provided. The amount of
more electricity use program participation is currently unknown, making it difficult
available for curtailment to estimate how much savings this program might provide. Finally,
when needed. the CPUC is requiring SCE to reopen and expand its voluntary air
conditioner cycling program for residential and commercial
customers. As part of this program, the utility attaches radio-
controlled devices to air conditioners, allowing it to lower the air
conditioner’s energy use during times of peak demand. PG&E and
SDG&E do not currently have air conditioner cycling programs,
but they are required by the CPUC to explore the most reasonable
options for implementing such programs or other curtailment
programs and report to the CPUC by May 1, 2001.
Giving program participants more flexible program limits should
improve their overall compliance rates, resulting in increased
assurance that the program can fulfill its purpose. Further, adding
new programs or expanding existing ones will likely attract new
customers to the programs and make more electricity use available
for interruption when the need arises. Finally, instituting eligibility
criteria for essential customers should help ensure that program
participants understand the requirements of the program and are
suited to meet them, leading to improved compliance rates.
Although the changes appear reasonable, it remains uncertain
whether these program revisions will adequately enhance the
program’s role to deliver energy savings in the summer of 2001
and act as a buffer against rolling blackouts.
33
THE CALIFORNIA PUBLIC UTILITIES COMMISSION’S
ENERGY EFFICIENCY PROGRAMS MAY NOT ACHIEVE
PLANNED PEAK ENERGY SAVINGS
Beyond the peak savings coming from the CPUC’s interruptible
program and the energy commission’s Peak Load Reduction
Program, AB 970 also charged the CPUC with the following:
(cid:127) Creating a program to increase power from self-generating
energy systems such as solar panels.
(cid:127) Developing a new program to reduce energy consumption in
residences and small commercial businesses.
(cid:127) Expanding the existing energy efficiency programs that the
State’s investor-owned utilities administer.
However, the CPUC’s plans for implementing AB 970 may not
deliver the anticipated amount of peak energy savings, and some
aspects of one plan duplicate others’ efforts. In addition, the
CPUC has yet to resolve several issues regarding its plans to
expand existing energy efficiency programs. For example, the
plans the utilities submitted to the CPUC for programs they
administer lacked sufficient information to confirm that AB 970
goals would be met. Consequently, in all areas, the CPUC may
fall short of its AB 970 energy efficiency goals.
The CPUC Is Adding New Energy Efficiency Programs and
Expanding Existing Ones
As the CPUC was planning its 2001 energy efficiency program,
the Legislature adopted AB 970, requiring the CPUC, within
180 days of its enactment, to develop new energy efficiency
programs and expand existing ones, using funds earmarked for
these purposes and collected as part of the monthly billing
process from customers of the investor-owned utilities. Although
the CPUC interpreted AB 970 as not setting a date when these
new and expanded programs must be in place, on January 31 and
March 27, 2001, the CPUC adopted plans of action. The CPUC’s
plans include a self-generation program to subsidize customers
for installing a means to generate their own power, such as solar
panels. Additionally, the plans outline a new program to auto-
matically control heating, ventilation, and air conditioning,
thereby reducing residential and commercial businesses’ energy
consumption. The self-generation program is intended to reduce
peak demand by an increasing amount over four years. Specifically,
in its first year, the self-generation program is projected to provide
34
savings of 90 MW. In the second year, this program’s savings are
anticipated to be an additional 90 MW, for a second year total of
180 MW. In the third and fourth years, the CPUC estimates that
this program will save an additional 90 MW each year. Thus, the
CPUC estimates that by the fourth year, the self-
generation program will reduce peak demand by
AB 970 requires the CPUC to expand
360 MW. Additionally, the demand control program
existing programs and develop new
is estimated to save 8 MW by 2002. The CPUC’s
programs based on these requirements:
estimate of the megawatts the self-generation and
(cid:127) Expand/accelerate residential and
commercial weatherization programs. demand control programs will save are summarized
in the Appendix. Finally, as directed by AB 970, the
(cid:127) Expand/accelerate programs that inspect
and improve heating, ventilation, and air- CPUC plans to expand existing energy efficiency
conditioning (HVAC) equipment in new
programs by emphasizing ways to reduce peak
and existing buildings.
energy demand.
(cid:127) Expand/accelerate programs that improve
energy efficiency in new buildings.
(cid:127) Provide incentives to commercial Programs for Electricity Self-Generation and
buildings with the capacity to shut down
Demand Control Are Not Likely to Achieve
or dim lighting and HVAC equipment
during energy emergencies. Anticipated Energy Savings
(cid:127) Evaluate the installation of local
In its largest new program, the CPUC dedicates
infrastructure to link thermostats to real-
time price signals. $125 million annually to its self-generation program
to subsidize the purchase and installation of solar
(cid:127) Provide incentives for controlling demand
and enhancing self-generation systems. panels, fuel cells, and nondiesel internal combustion
(cid:127) Provide incentives for the use of engines by electricity customers, to allow these
renewable self-generation resources. customers to generate their own electricity rather
(cid:127) Reevaluate energy efficiency cost- than drawing energy from the transmission grid.
effectiveness tests in light of increases in
However, because the CPUC’s plan is unstructured,
wholesale electricity costs.
it leaves it up to customers to choose the technology
they will employ and may result in the CPUC not
achieving its estimated energy savings goals. In
addition, the CPUC’s demand control efforts,
which include a plan to adjust thermostats during times of peak
electricity use, may fall short of its estimated megawatt savings
goal because participants in this program can override the tech-
nology. Finally, although not intended to reduce the demand for
electricity, the Web site the CPUC directed PG&E to develop dupli-
cates existing sites and appears to be a poor use of ratepayer funds.
In its self-generation program, the CPUC’s goal is to shift peak
energy demand away from the power grid to new self-generation
resources. However, the program the CPUC has developed allows
customers their choice of the type of self-generating technology
they wish to install rather than focusing on maximizing the
reduction in peak demand. As a result, customers’ technology
choices will greatly affect the megawatt savings the CPUC will
achieve. For example, if all customers decide to install nondiesel
35
internal combustion engines as their means of generating power,
the CPUC could expect to achieve about 100 MW of peak energy
savings annually, the maximum amount offered by this technol-
The CPUC did not struc- ogy. However, if all customers elect to install solar panels, the
ture its program to ensure CPUC would achieve peak energy savings of only 22 MW annually,
a mix of technologies are the maximum savings this technology offers. The CPUC did not
installed to reduce structure its program to encourage the use of various methods of
dependence on the energy self-generation as a means of reducing dependence on the energy
grid while maximizing grid while at the same time maximizing the energy savings that
energy savings. the mix of technologies would yield. Therefore, although the
adoption of any of these technologies will produce some energy
savings, the CPUC cannot confidently predict what the program’s
energy savings will be. To put the possible effect of this policy
decision into context, consider that if all of the program’s cus-
tomers opt to install solar panels, the 22 MW of energy savings
they achieve will be only one-twentieth of the peak energy
savings needed to avoid the rolling blackouts that occurred on
March 19, 2001.
Additionally, the CPUC’s new demand control programs may not
achieve the peak energy savings it anticipates. By installing
Internet-based technology to adjust heating, ventilation, and air-
conditioning thermostats during peak energy periods, the CPUC’s
new residential and small commercial pilot programs are designed
to reduce energy consumption by 8 MW beginning in 2002.
However, like the participants in the energy commission’s program
to conserve energy in commercial buildings, the new residential
and small commercial participants will have the ability to override
the signal to adjust their thermostats, partially or wholly negating
any energy savings.
Unfortunately, the override option leaves the CPUC with a wide
range of possible megawatt savings during peak times of energy
demand. Assuming that all residents and small commercial
building operators comply with the signal when received, the
CPUC could achieve the full 8 MW of estimated savings. However,
some or all of these participants could reject the signal to their
thermostat, reducing the savings to little or nothing.
Though Costing Much More, the Self-Generation and
Demand Control Programs Will Yield Far Fewer Peak Energy
Savings Than Larger Commercial and Industrial Programs
The CPUC’s goal of attaining 368 MW of peak energy reduction
by the end of 2004 will cost the ratepayers of the three investor-
owned utilities $551.5 million, compared to the energy
36
commission’s Peak Load Reduction Program, with a goal of
reducing peak energy by 200 MW each year over a four-year
period at a total cost of $50 million. As a result, the CPUC’s
demand control and self-generation programs will be nearly six
times more costly per megawatt saved than the energy
commission’s programs.
The CPUC explained that energy efficiency programs aimed at
residential and small commercial customers are much more
costly than the energy commission’s large commercial and
industrial energy efficiency programs because, whereas the
number of residential and small commercial sites is large, they
CPUC’s demand control use smaller amounts of electricity, and the opportunity for energy
and self-generation savings is less. Even though AB 970 requires the CPUC to address
programs will be nearly these smaller energy customers, it does not preclude the CPUC
six times more costly on a from including larger industrial and commercial customers in its
per megawatt basis than demand reduction programs. Therefore, we question whether the
the energy commission’s CPUC should continue to commit utility ratepayers’ funds only
programs. to residential and small commercial programs when the funds
collected from the utilities’ larger ratepayers could achieve greater
peak energy savings when applied to large commercial, industrial,
and governmental sources, such as the community college
system, which the CPUC’s energy efficiency programs could target.
A New $3 Million Web Site Development Program
Duplicates Existing Efforts
As part of its demand control programs, the CPUC directed PG&E
to develop a new Web site for its customers to obtain information
about electricity. The site will, among other things, show customers
how much energy they have consumed, provide information
about how electricity is priced, and provide electronic links to the
Web sites of retailers that offer energy-efficient appliances. The
CPUC does not intend to measure any energy savings directly
attributable to the Web site and has earmarked $3 million annually
for the following:
(cid:127) Developing and maintaining the Web site.
(cid:127) Assessing users’ satisfaction with the Web site.
(cid:127) Providing energy customers with incentives for viewing the
Web site.
However, because the CPUC’s plan for PG&E to develop this new
Web site calls for it to duplicate information already residing on
the respective Web sites of PG&E, private entities, and public
37
entities, we believe the $3 million annual cost for the Web site is
a poor use of ratepayer funds.
When we asked the CPUC staff why the CPUC had directed
PG&E to develop what seemed to be a redundant Web site, they
said PG&E would tailor the site to include only information
relevant to PG&E customers and stated that PG&E’s existing Web
site and those of other entities contain broad information that
applies to many utilities and geographic areas. However, as
Table 6 demonstrates, much of the Web site information is
already available on PG&E’s existing Web site, as well as on the
Web sites of the energy commission and the ISO.
TABLE 6
Extent of Duplication Between PG&E’s Proposed New Web Site and Existing Web Sites
Information Expected to Be on Other Web Sites That Already
the New PG&E Customer Web Site Maintain This Information
Up-to-date information about
California’s electricity market structure ISO
Information regarding how electricity is priced PG&E
Rate tariff options for residential customers
explained in simple terms PG&E
Historical energy billing information for customers PG&E
Energy usage and cost information for common
appliances (refrigerators, ovens, etc.) PG&E
Links to manufacturers or retailers of high-efficiency
appliances tailored to the needs of the individual PG&E
Information about low-cost efficiency options and
how much energy and cost savings they could
produce (geographically) PG&E
Information about renewable self-generation options,
costs, and benefits Energy commission
Links to manufacturers or retailers of self-generation equipment Energy commission
Unresolved Issues Exist Regarding the CPUC’s Plans to
Expand Energy Efficiency Programs
Historically, the CPUC and the investor-owned utilities have
worked together to implement energy efficiency programs that
serve the utilities’ customers throughout the State; the investor-
owned utilities act as administrators of these programs on the
38
CPUC’s behalf. To administer the programs, the utilities use a
designated portion of the funds they collect from their ratepayers,
and they earn financial incentives for meeting various program
milestones set by the CPUC.
As required by AB 970, the CPUC directed the investor-owned
utilities to expand their residential and commercial weatherization
programs; heating, ventilation, and air-conditioner programs; and
It is unclear whether the new construction programs. In a January 2001 decision, the
CPUC will be successful in CPUC approved the plans for the investor-owned utilities’ 2001
overseeing the expansion energy efficiency programs. The CPUC took this action despite
of AB 970 programs indications that the investor-owned utilities may not have met
intended to increase earlier program goals. Specifically, the CPUC had information
energy conservation. indicating that the investor-owned utilities had not fully spent
previous years’ program funds. Moreover, as it reviewed the
utilities’ plans for meeting AB 970 goals, the CPUC determined
that the plans lacked sufficient information to confirm that the
goals would be met. As a result, it is unclear whether the CPUC
will be successful in overseeing the expansion of AB 970 programs
and ultimately in increasing energy conservation during the
energy crunch.
In 1999 PG&E, SCE, and SDG&E jointly collected $227 million
for energy efficiency programs such as appliance rebates,
energy seminars, and home energy ratings, but they spent only
$183 million on these programs. Similarly, in 2000, the utilities
projected they would spend $193 million by the end of the year,
or $65 million less than the $258 million they collected. Assuming
that expenditures are a measure of program effectiveness, the
CPUC has an early indication that the investor-owned utilities are
not performing adequately.
Moreover, the CPUC determined that the information the investor-
owned utilities supplied related to the AB 970 programs they are
administering was incomplete. According to the CPUC’s January
decision, it was unsuccessful in obtaining from the utilities
additional clarifying program plans, budget modifications, and
anticipated peak energy savings information. Nonetheless, the
CPUC approved the utilities’ 2001 energy efficiency programs in
January of this year, even though it was still unclear as to how
the investor-owned utilities would successfully increase energy
conservation through the programs outlined in AB 970. In
addition, because the CPUC gave the investor-owned utilities
until June 2001 to report on how they would expand existing
programs, it will be halfway through the 2001 program year
before the CPUC will have an understanding of how or whether
39
the utilities are meeting the mandates of AB 970. As a result, it
remains unclear whether the CPUC will be successful in its efforts
to oversee the expansion of AB 970 programs and ultimately to
increase energy conservation during the current energy shortage.
RECOMMENDATIONS
To provide the Legislature with information it could use to
measure whether and to what extent legislative action is needed
to help California meet its electricity supply and demand needs in
the future, the energy commission should do the following:
(cid:127) Consult with the ISO and develop an annual projection of
summer supply compared to peak demand that acknowledges
the full range of constraints within the State’s electricity
system, including transmission constraints.
(cid:127) As part of its projection, provide the Legislature with a range of
possible supply and demand outcomes that reflect the likeli-
hood that the underlying assumptions will prove true.
To ensure that it achieves its peak demand reduction goal on an
ongoing basis, the energy commission should consider modify-
ing its Peak Load Reduction Program as follows:
(cid:127) Eliminate the override function from the commercial building
program guidelines and modify contract language so that
building managers will more readily comply with directives to
reduce lighting and air-conditioning levels as agreed.
(cid:127) As a condition of program participation, require commercial
building program participants to meet specified compliance
levels for reducing lighting and energy used to power air-
conditioning for a certain period of time, such as 24 months. If
the compliance levels are not met, the participants should be
penalized. After 24 months, the participants’ compliance could
become voluntary.
(cid:127) Because state government facility operators will be carrying
out energy reduction plans manually rather than through
computerized systems, identify ways to minimize the potential
for human error or misinterpretation of directives to reduce
energy usage.
40
(cid:127) Develop a plan to actively evaluate itself and program partici-
pants in all components of the program against set milestones,
such as:
♦ Securing a certain number of participants by milestone dates.
♦ Verifying that equipment is ordered and delivered by sched-
uled due dates.
♦ Ensuring that projects are installed, tested, and operational
according to scheduled dates.
In an effort to maximize energy conservation over the next
several years while at the same time making the best use of funds
collected from the utilities’ ratepayers, the CPUC should give
priority to conservation measures for those types of customers
that will produce the most energy savings. This may not necessarily
prompt the CPUC to abandon more costly residential and small
commercial programs in favor of larger commercial, industrial, or
governmental projects, but it will permit the CPUC to take
advantage of potentially greater energy savings at a lower cost
to ratepayers.
Although energy conservation is essential to avoiding rolling
blackouts in the summer of 2001 and beyond, the CPUC’s demand
control, self-generation, and energy efficiency programs may not
achieve their anticipated peak energy savings for a number of
reasons. Therefore, the CPUC should do the following to maximize
the energy savings produced through these programs:
(cid:127) Amend the new residential and small commercial pilot programs
to remove the override option from the program and to require
participants to reduce peak demand as and when directed.
(cid:127) Remove the Web site from its portfolio of demand control
programs.
(cid:127) Increase its vigilance in its oversight of the investor-owned
n
utilities’ administration of energy efficiency programs.
41
Blank page inserted for reproduction purposes only.
42
CHAPTER 2
Some Long-Term Programs Will
Improve California’s Balance of
Energy Supply and Demand, but the
State May Still Need to Help Prevent
Wide Market Swings in Supply
CHAPTER SUMMARY
A
fter the State deregulated its electricity industry, the
State Energy Resources Conservation and Develop-
ment Commission (energy commission) stopped basing
its decisions on new power plant applications on projections of
California’s energy supply needs. In theory, a competitive market
is supposed to adjust supply to meet demand, so that an
undersupply of energy would drive up prices, creating an
economic incentive for energy companies to build new power
plants. However, given the reality that power plants take a long
time to site and construct, this model may subject the State to
boom-bust cycles—periods of excess supply followed by periods
of undersupply—as the market adjusts to shortages and surpluses
of electricity. To spare the residents and businesses of California
from the disruptive swings of energy supply, it is reasonable for the
State to augment its role in energy planning.
To encourage the production of electricity from nonpolluting,
renewable resources, the Legislature directed the energy commis-
sion to develop the Renewable Energy Program (renewable
program). This legislative mandate was part of Assembly Bill (AB)
1890, which deregulated California’s electricity industry in 1996.
The renewable program subsidizes power plants that use renewable
resources, such as solar, wind, and solid waste technologies, to
produce electricity. By assisting the production of energy through
renewable, nonpolluting sources, the renewable program contrib-
utes to improving the State’s air quality as it lessens the State’s
dependence on finite fuel sources used to generate electricity.
Moreover, with participating power plants now having the capacity
to power about 4.4 million average households, the renewable
program is also benefiting California in the current power shortage.
The energy commission’s renewable program maximizes available
funds by subsidizing owners of existing renewable-resource
power plants only for electricity they produce and only when
wholesale market prices do not exceed pre-set rates. In 2000 the
43
energy commission used unspent subsidy payments to make
$40 million in new pledges of subsidies to power producers when
they bring on-line 471 megawatts (MW) of new power plant
capacity from renewable resources that the energy commission
estimates will occur by the end of March 2002.
In an effort aimed at alleviating the current energy shortage, the
Legislature passed AB 970 in August 2000 to reduce peak energy
consumption and establish new levels of energy efficiency
statewide. However, the legislation’s mandate to update the
energy efficiency standards for buildings and appliances will not
have an impact on the State’s energy demand in summer 2001,
although it will lessen the demand for electricity in the future.
For example, the energy commission has approved new building
standards to require buildings constructed after June 1, 2001, to
be 12 percent more efficient. The equivalent energy savings for
one year’s worth of new construction using the revised building
standards ranges from 162 MW to 275 MW.
THE POTENTIAL FOR WIDE SWINGS IN ELECTRICITY
SUPPLY MAY REQUIRE THAT THE STATE AUGMENT ITS
ROLE IN ENERGY PLANNING
After the State deregulated its electricity industry, the energy
Relying on the commission no longer played a role in restraining the State’s level
marketplace to determine of electricity supply. Instead, the State relied on the competitive
when to build new power market to encourage the construction of sufficient power plants
plants may not be in the to ensure an adequate supply of power. However, relying on the
State’s best interests. marketplace to determine when to increase supply may not be in
the State’s best interests. Because power plants take a significant
amount of time to site and construct, the industry may not be
able to respond quickly enough to market signals to ensure that
the State is not exposed to a boom-bust cycle. To avoid these
large fluctuations in electricity supply, it may be valuable for the
State to augment its planning role, ensuring that California never
reaches extreme levels of oversupply or undersupply.
As the State’s primary energy policy and planning agency, the energy
commission has traditionally had the role of ensuring that power
plant construction did not outpace the State’s growth in energy
demand. This role made sense under regulation, where investor-
owned utilities had an incentive to overbuild because they were
guaranteed to recover their costs of building and operating
plants, plus a set profit margin. The energy commission coun-
tered this incentive by incorporating its projection of the State’s
44
needs for new supplies of electricity into its decisions to approve
or deny applications for new power plants. This process worked to
provide a stable level of supply growth to match the State’s
projected demand growth. However, with deregulation on the
horizon, the investor-owned utilities’ incentives changed in the
early 1990s, and their applications to build new power plants
declined. Not being designed to encourage new power plant
construction, the energy commission took no action to mitigate
this reduction in applications. In fact, energy commission staff
state that they were not concerned by the lack of new supply in
the early 1990s because at that time California still had a large
margin of excess supply over demand, and they expected
California’s new competitive market to encourage the construction
of the necessary supply.
According to economic theory, in a competitive market,
undersupply will drive up prices, creating an incentive for energy
companies to build more plants, and oversupply will drive down
prices, causing plant owners to stop building plants that might
not turn a profit. In a normally competitive market, these forces
will cause suppliers to adjust the supply of the product to a
quantity that just prevents them from losing money, thereby
driving the price to equilibrium. In such an environment, there
would be no justification for the energy commission to be involved
in electricity planning for supply. Indeed, legislation in 1999
reduced the energy commission’s planning role by removing the
requirement that the commission base power plant siting decisions
on its estimate of the State’s future needs for new power plants.
However, even if it functioned perfectly, the market for electricity
would not quite fit the standard model of a competitive market,
because electricity cannot easily be stored for later use, and
building large power plants can take more than two years. Thus,
even when undersupply causes prices to increase rapidly, suppli-
ers cannot respond immediately, causing prices to remain high in
the interim until new plants come on-line. In fact, the State
currently appears to be in this situation because demand signifi-
cantly exceeds supply. The wholesale price of electricity is high,
and the energy commission has approved applications for more
megawatts of supply since the restructuring legislation passed in
1996 than it did in the 20 years prior to restructuring, as shown
in Figure 1. However, the long siting and construction times of
large power plants prevented them from coming on-line to
provide new supply by the summer of 2000, when California’s
supply shortage contributed to the sharp rise in wholesale prices.
45
FIGURE 1
Megawatts of New Supply Approved Through the Energy Commission’s
Standard Siting Process Since 1979
5,000 Before restructuring After restructuring
4,294 MW 8,413 MW approved
4,000
3,000
2,000
1,000
0
9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1
7 8 8 8 8 8 8 8 8 8 8 9 9 9 9 9 9 9 9 9 9 0 0
9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 0 0
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2
Source: Energy Commission—Siting Case History Report; Energy Facility Siting Status Report.
Note: Of the 4,294 MW approved before restructuring, 693 MW were never built. Of the 8,413 MW approved between
restructuring and April 1, 2001, only 4,367 MW were under construction as of April 1.
* The amount of megawatts approved for 2001 is through April 1, 2001.
Conversely, if suppliers build an abundance of new power plants
in response to the current high prices, it may cause the price of
electricity to drop sharply until demand once again catches up
with supply, raising prices and beginning the cycle anew. This
type of boom-bust cycle could cause consumers to face alternating
electricity surpluses and shortages, with the wholesale price of
electricity fluctuating to match. To avoid these large fluctuations,
it may be valuable for the State to have a planning role through
which it attempts to prevent extreme levels of oversupply or
undersupply while allowing the competitive market to operate
between these extremes.
46
devorppA
sttawageM
*
THE ENERGY COMMISSION’S RENEWABLE ENERGY
PROGRAM BENEFITS THE STATE AND MAXIMIZES THE
USE OF ITS FUNDS
The 1996 legislation that deregulated energy also required the
energy commission to preserve the State’s commitment to devel-
oping diverse, environmentally sensitive electricity resources as
California made the transition to a competitive electricity market.
In response, the energy commission developed the renewable
As of March 2001 the program, which uses funds collected from customers of the
renewable energy investor-owned utilities to subsidize power plants that rely on
program had 275 plants renewable resources like solar, wind, and solid waste technologies
with a capacity of within California. These technologies significantly reduce the
4,394 MW—enough to State’s reliance on power plants fueled by finite natural resources,
power nearly 4.4 million such as coal and natural gas that pose air quality concerns,
average households. because they use sun, wind, and solid waste to create electricity.
As of March 2001 the renewable program includes 275 existing
and new power plants with a capacity of 4,394 MW—enough to
power approximately 4.4 million average households.
The energy commission structured the renewable program to
maximize the use of its funds, subsidizing only the electricity
that renewable power plants deliver to the State’s power grid and
subsidizing existing renewable power plants only when wholesale
market prices are too low to make renewable power generation
feasible. The renewable program has not had to make any subsidy
payments to owners of existing power plants since August 2000.
Moreover, the renewable program’s flexibility has allowed the
energy commission to shift these unused program funds to
maximize other goals, such as encouraging the future operation
of an additional 471 MW of new, renewable-resource power plant
capacity, almost doubling the 552 MW of capacity the energy
commission sought originally and increasing the future electricity
supply within the State. Finally, by keeping existing renewable-
resource facilities on-line and securing new ones, the energy
commission is helping the State survive the current energy
shortage.
The Renewable Program Was Mandated by AB 1890
With the passage of AB 1890 in 1996, the energy commission
began developing the renewable program. The Legislature man-
dated that the State, with funds collected from customers of the
investor-owned utilities, support the operation and development
of existing and new renewable-resource technologies in California.
Through subsidy payments to eligible power plant owners for
47
producing electricity, the renewable program supports existing
and new power plants that employ renewable-resource technolo-
gies such as solar, wind, geothermal, and solid waste. Power
plants are eligible for the renewable program if they meet certain
criteria, including their location, date of operation, and their
adherence to sales limitations and contracting restrictions.
The Renewable Program’s Design Maximizes Its Funds
The renewable program’s design, by maximizing the benefits of
the program’s funds, has contributed to the successful development
of additional renewable power plants and has kept existing
renewable power plants operational in the State. The following
three design elements allows the energy commission to maximize
the renewable program’s funds by:
(cid:127) Subsidizing existing and new power plant owners only for the
electricity they produce.
(cid:127) Limiting its payments to existing power plants to the lesser of
three possible pre-set rate calculations that consider wholesale
market prices, available renewable program funds, and
production incentive caps.
(cid:127) By using its flexibility to shift underutilized funds from one
program area to another.
At the core of the renewable program is a subsidy-for-production
mechanism: By subsidizing electricity production, rather than
facility repair or construction, the energy commission subsidizes
only the electricity that owners of existing and new renewable
By subsidizing owners of power plants actually deliver to the grid. Historically, the investor-
renewable resource power owned utilities paid participants simply to be available to generate
plants only for the power when called upon and then also paid them for the actual
electricity they deliver energy they produced. These methods were successful in
to the State’s power grid, stimulating the building of renewable power plants but were not
the energy commission effective in keeping ratepayer costs down. Perhaps in response to
helps maximize the this historical inefficiency, the energy commission designed the
program’s funds. renewable program to subsidize owners of new and existing
renewable-resource power plants only for producing and delivering
electricity to the State’s power grid.
Also, the energy commission makes subsidy payments to each
owner of an existing renewable power plant based on the lowest
of a three-rate calculation that considers wholesale market prices,
available program funds, and production incentive caps. When
48
wholesale market prices are below a specified target price, the
energy commission performs the three-rate calculation and pays
the power plant owner the lesser amount. When wholesale
market prices are above the target price, the energy commission
does not make a subsidy payment to the power plant owner. For
example, assume in the year 2000 the energy commission set
3.5 cents per kilowatt hour as the target price for existing wind
power plants. Based on the three-rate calculation, if the wholesale
market price of electricity then dipped to 2.5 cents per kilowatt
hour, the energy commission would pay each wind power plant
owner a subsidy in an effort to keep these power plants operating.
However, if the wholesale market price rose to 5 cents per kilo-
watt hour, the energy commission would not subsidize the
owners’ electricity production. This latter scenario played out
during the months that high wholesale market prices prevailed in
late 2000 and early 2001; the energy commission did not make
any subsidy payments to owners of existing eligible power plants
from August 2000 through April 2001.
Another effective element of the program’s design is the energy
commission’s ability to shift funds from one area of the program
to another as surplus funds accumulate. The energy commission
Because it has flexibility significantly reduced subsidy payments to owners of existing
in how it uses program renewable power plants during the later months of 2000, ending
funds, the energy the calendar year with a surplus of $41.9 million that had been
commission was able to budgeted for subsidies. To encourage the future operation of new
nearly double the 552 MW renewable power plants, the energy commission shifted $40 million
of supply it originally of this surplus and will use it to pay future subsidies to power plant
sought to add. developers who, through a competitive auction, have agreed to
place in operation 471 MW of new renewable capacity within the
State. The energy commission will pay these new plant operators
only for electricity produced and delivered to the State’s power
grid; the developers of the renewable power plants will bear the
up-front construction or repair costs. By having the flexibility to
utilize funds where they can provide the greatest benefit, the
energy commission was able to nearly double the 552 MW of
energy supply it originally sought to add.
The Renewable Program Is Helping the State Weather the
Current Energy Crunch
The renewable program is helping to alleviate the State’s current
electricity supply shortage. For example, through its subsidy
payments to owners of renewable power plants that were in
operation before the passage of AB 1890, the energy commission
49
has helped these power plants compete over time with power
producers that use less costly finite fuels. By subsidizing their
production when necessary, the energy commission has helped
keep approximately 4,276 MW of the State’s existing supply of
renewable-resource electricity available. In addition, through two
competitive auctions, the energy commission’s renewable program
will have added nearly 1,000 MW of new renewable power plant
energy supply to California by the end of 2003.
Past efforts of the renewable program are now expanding the
State’s electricity supply. In June 1998 the energy commission
held a competitive auction for prospective developers of new,
renewable-resource power plants. Prospective developers submitted
bids with the cents-per-kilowatt-hour incentive desired over a
five-year period, and the energy commission awarded future
subsidy payments to each successive low-cost bidder until the
available funds were allocated. As a result of the auction, the
energy commission committed to subsidize about 552 MW of
renewable supply once these new power plants begin producing
and delivering electricity. However, three projects totaling approxi-
mately 9 MW were canceled.10 Thus, power plants delivering only
543 MW of the 552 MW awarded are or will be operational.
As shown in Table 7, 111 MW of the renewable power generation
resulting from that first competitive auction are on-line and
delivering electricity to the State’s power grid. An additional
90 MW are expected to be on-line by July 2001, and all of the
remaining plants are expected to be on-line by December 2003.
Nearly all of the unfinished projects have filed the appropriate
construction applications, environmental permits, and land
use permits.
Although the 552 MW awarded were initially expected to be on-
Although the 552 MW line no later than January 1, 2002, several of the projects have
were expected to be been delayed. According to a manager of the renewable program,
operational by the current power crisis may have contributed to these delays
January 2002, because of because some developers cannot secure from the investor-owned
financing difficulties and utilities the purchase agreements needed to get the financing to
some public opposition build new plants. Also, some projects have faced public opposi-
several projects have tion over the environmental effects constructing these new
been delayed. plants might cause. It is possible that these types of difficulties
may contribute to similar project delays for the 471 MW that the
10 One power plant developer encountered difficulties in obtaining a secure fuel source,
another faced litigation, and the last was too small for the plant to be economical.
50
energy commission awarded during its most recent auction. The
energy commission’s on-line estimates for both auctions are
summarized in the Appendix.
TABLE 7
On-Line Dates and Megawatts of Supply of New Renewable
Power Plants Resulting From the Energy Commission’s
June 1998 Auction
Cumulative
Added MW Total MW
Original award: 552 MW
Power plants currently on-line 111 111
Power plants expected on-line
by July 2001 90 201
Power plants expected on-line
by December 2001 241 442
Power plants expected on-line
by December 2003 101 543
Canceled power plants 9 552
Source: Energy Commission, Energy Technology Development Division—Renewable
Energy Program.
THE ENERGY COMMISSION HAS UPDATED ITS
ENERGY EFFICIENCY STANDARDS FOR BUILDINGS
AND APPLIANCES
Assembly Bill 970 charged the energy commission with adopting
and implementing updated building and appliance energy
efficiency standards. As a result, in January 2001, the energy
commission approved new building standards, which take effect
June 1, 2001. The energy commission intends to finalize its new
appliance standards in May 2001, to take effect in January 2002
and thereafter. Updates to the building standards include stricter
window energy efficiencies, more efficient heating and air-
conditioning systems, and new, nonresidential exterior building
lighting standards. Electricity savings from these stricter efficiency
standards for buildings and appliances will manifest primarily in
2002 and beyond. The energy commission estimates that one
year’s worth of new residential and nonresidential construction
under the updated building standards will create energy savings
in the range of about 162 MW to 275 MW statewide. Although
51
new construction does put an added strain on the State’s power
grid, these more stringent standards will improve energy efficiency
and make better use of existing energy resources. Similarly,
energy commission data show that one year’s worth of appliance
usage that meet the new standards will create energy savings of
approximately 40 MW statewide. Over time, the electricity
needed to operate buildings and appliances will decline as new
construction, building renovations, and new appliances meet the
more stringent energy efficiency standards.
Updated Building Standards Will Produce Energy Savings in
the Future
Although they will not create significant energy savings in the
summer of 2001, the stricter energy efficiency standards for
Although too late for the buildings will provide energy savings in 2002 and into the future.
summer of 2001, stricter When these standards go into effect in June 2001, energy com-
building energy efficiency mission staff estimate that new residential and nonresidential
standards will provide construction will be approximately 12 percent more energy
energy savings in 2002 efficient than similar buildings constructed using the earlier
and into the future. standards. Even though all new construction increases the strain
on the State’s power grid, it is unrealistic to think that no new
residential or nonresidential buildings will be constructed in the
State. Over time, these more stringent standards will improve
energy efficiency in new and remodeled buildings, and the
standards will help make better use of existing resources and slow
the demand for new power plants.
Since 1978 the energy commission has typically been issuing
statewide energy efficiency standards for residential and nonresi-
dential buildings every three years (they were last updated in
1998). These standards set statewide minimum energy efficiency
levels for new and remodeled residential and nonresidential
buildings. For example, the building standards include wall,
ceiling, and flooring insulation and window standards that will
help minimize both the escape of heat in the winter and the
escape of cool air in the summer. Local building officials are
generally responsible for enforcing the building standards.
Through AB 970 the Legislature required the energy commis-
sion to update its building energy efficiency standards by
January 4, 2001, or as soon thereafter as possible. The energy
commission met this legislative mandate when it adopted updated
52
standards on January 3, 2001. The standards require that all build-
ings that are constructed or remodeled after June 1, 2001, meet the
new energy efficiency standards, unless specifically exempted.11
The energy commission’s revisions to the 1998 standards addressed
a number of areas that will significantly reduce energy demand
during peak periods. For example, energy commission staff
estimate that large energy savings will come in the form of
stricter standards for windows, heating, and air-conditioning. In
addition, they estimate that other potentially large energy savings
will come from new standards for sealing air distribution ducts
Residential buildings and lighting the exteriors of nonresidential buildings, and from
conforming to the revised the optional installation of heat-reflective cool roof technologies.
standards are expected to
save from 105 MW to The energy commission estimates that one year’s worth of new
205 MW of energy per residential construction under the updated standards will save
year compared to from 105 MW to 205 MW of energy when compared to one year’s
buildings constructed worth of new residential construction under the old standards. For
under the old standards. new and remodeled nonresidential buildings, the energy commis-
sion estimates a range of roughly 57 MW to 70 MW of peak
energy savings per construction year under the new standards.
Although the updated standards apply to remodeled residential
buildings, the energy commission has not estimated the associated
megawatt savings.
New Appliance Standards Will Also Produce Future
Energy Savings
Since 1978, when the first such standards were created, the
energy commission has updated its appliance energy efficiency
standards on an as-needed basis, with the last update occurring in
1991. However, AB 970 required the energy commission to
update its appliance standards by January 4, 2001, or as soon
thereafter as possible. Although the updated appliance energy
efficiency standards will not create significant energy savings in the
summers of 2001 or 2002, they will begin to create energy savings
in 2003.
In May 2001 the energy commission plans to adopt updated
appliance standards that will generally take effect in January 2002.
These new standards include new and revised efficiency standards
for 20 types of appliances. Overall, the commission estimates that
the energy savings derived from one year’s operation of these new-
11 The energy commission may grant an exemption if it finds that before the adoption
of a provision, substantial funds have been expended for planning, designing,
architecture, or engineering of a building.
53
generation appliances will be about 40 MW of peak energy. Table 8
lists some examples of appliances affected by the proposed new
standards and their estimated statewide energy savings.
TABLE 8
Examples of Appliances Affected by the 2001 Appliance
Standards and Their Estimated Energy Savings
Estimated Megawatt Percent of
Savings per Appliance Estimated Increase
Appliance Type Type Statewide in Energy Efficiency
Commercial clothes washer 0.8 MW 62%
Commercial refrigerator—
solid door 1.9 35
Commercial refrigerator—
transparent door 4.1 35
Emergency exit sign 5.8 21
Torchiere lamp 5.6 60
Traffic signal 11.6 92
Source:Estimated increase in energy efficiency provided by the Energy Commission,
Energy Efficiency Division, Residential Buildings and Appliances Office.
After they are adopted, these new standards should help make
most of the State’s regulations consistent with federal law.
However, many appliances for which California has developed
proposed revised standards are more stringent than corresponding
federal standards. This discrepancy creates a problem because in
these instances the State’s standards would be preempted by
federal law. For example, the energy commission is considering
standards for air conditioners and water heaters that will save
approximately 19 MW of peak energy in addition to the 40 MW
projected for other appliance types affected by the new appliance
standards, but parts of these standards for air conditioners and
water heaters are more stringent than their federal counterparts.
Therefore, even though the energy commission may approve
these stricter State standards, manufacturers would not be
mandated to comply with them until the State gets a waiver from
the federal government exempting California from the federal
54
standards. According to the energy commission, if started now, this
process of receiving a federal exemption will likely take until 2004
or 2006, and until then the energy commission could not require
manufacturers to meet California’s stricter appliance standards.
Even though the federal government generally does not allow the
energy commission to mandate stricter standards without first
obtaining a waiver, the State could still achieve the benefits these
stricter standards offer. For example, through the use of incen-
tive programs, such as appliance rebate programs run by the
investor-owned utilities, the State could encourage demand for
these more efficient appliances. Then, as older appliances of the
same type are replaced with more efficient ones, the State would
benefit from the immediate energy savings.
RECOMMENDATIONS
Power plants take a significant amount of time to site and
construct, and energy suppliers may not be able to respond to
market signals quickly enough to ensure that the State is not
repeatedly exposed to periods of oversupply and undersupply.
Therefore, the Legislature and the energy commission should
consider augmenting the energy commission’s role in electricity
planning to help the State avoid large swings in the supply of
electricity relative to demand. For example, the Legislature should
consider expanding the energy commission’s existing planning
role to include integrating supply and demand projections and
requiring it to use them as a basis for making decisions regarding
whether to site new power plants.
While the energy commission pursues a waiver from the federal
government that would allow it to require manufacturers to offer
appliances that are more energy efficient in certain cases than the
federal government now requires, it should coordinate with the
CPUC and the investor-owned utilities to incorporate these
appliances into new and existing incentive programs, such as
appliance rebate programs, to create demand for these appliances
so that the State could benefit from the more immediate energy
n
savings until such time as the waiver is granted.
55
Blank page inserted for reproduction purposes only.
56
CHAPTER 3
Efficient Planning and Permitting of
New Power Plants and Transmission
Lines Are Needed to Address the
Energy Crisis in the Long Term
CHAPTER SUMMARY
C
alifornia’s power supply remains uncertain in the after-
math of a deregulation process that was supposed to
create more competition, lower prices for consumers, and
provide reliable electric services. Efficient planning and siting of
new power plants and transmission lines is vital to the State’s
ability to deliver reliable power over the long term. However, the
process used by the State Energy Resources Conservation and
Development Commission (energy commission) to site new power
plants generally takes longer than the 12-month goal set by its
governing statutes. Although these delays in siting new plants
did not cause California’s electricity shortage, they have contrib-
uted to the lack of some new power plants coming on-line before
summer 2001. The energy commission has made changes to
improve its siting process, but it is not measuring the effective-
ness of those changes, so it does not know whether they are
making a difference. The energy commission has also started
using several new, shorter siting processes, but so far they have
had little effect on the State’s electricity supply.
In addition to new power plants, an adequate transmission grid is
important in the energy crisis. In times of high energy demand,
the transmission lines are used to send large amounts of power
from one part of the State to another to avoid regional power
outages, thus having sufficient transmission lines is crucial. For
example, because the primary transmission connection between
Northern and Southern California could not transmit the amount
of electricity Northern California needed, rolling blackouts occurred
in January 2001. However, the State’s processes for identifying
and permitting transmission projects are flawed. In the first place,
although the California Independent System Operator (ISO)
coordinates transmission grid planning with the State’s investor-
owned utilities, the utilities still have the responsibility for making
the demand growth projections that the ISO uses for its trans-
mission expansion plans. These projections may be based on
57
conflicting assumptions that make them difficult to combine into
a statewide plan. In addition, the major utility companies may
have a conflict of interest between deciding to build new transmis-
sion lines and spending the money on more lucrative ventures,
such as building new unregulated power plants. Also, the California
Public Utilities Commission (CPUC) does not have an expedited
siting process for new transmission lines that may be needed to
alleviate transmission grid constraints both in the short term and
in the future. Finally, because the CPUC’s standard transmission
siting process often takes longer than state law recommends, the
State’s recovery from its present energy crisis may be slowed.
THE ENERGY COMMISSION’S STANDARD SITING
PROCESS HAS LENGTHENED OVER TIME BUT DID
NOT CAUSE CALIFORNIA’S SUPPLY SHORTAGE
The energy commission is responsible for siting large thermal
power plants in California. Although the Warren-Alquist State
Energy Resources Conservation and Development Act (act) states
that new power plants should be sited within 12 months, the
energy commission usually does not meet this goal. In fact, the
energy commission’s siting process has generally grown longer
over its more than 25-year history, as the characteristics of the
proposed plants and the types of applicants have changed. Delays
in siting new plants delay the dates those plants can come on-
line and supply California with much-needed new electricity to
meet demand. According to the energy commission, the primary
causes of recent siting delays have been project changes made by
the applicant, public opposition to power plants, and the inability
of other agencies to quickly complete their reviews.
The Energy Commission’s Siting Process Usually Takes
Longer Than Its 12-Month Statutory Goal
Although the Legislature created the energy commission in part
to reduce the time involved in approving new power plants, it is
Only 4 of 12 power plant not meeting its statutory goal of ruling on most power plant
siting applications under applications within 12 months. Of the twelve applications it
consideration by the approved through its standard siting process between
energy commission were April 14, 1999, and April 1, 2001, only four approvals took
approved in 12 months 12 months or less. The siting process has lengthened as the types
or less. of power plant applications have changed. Over the past decade,
the energy commission has received more applications from
private generating companies less acquainted with the siting
process, more applications for larger-capacity power plants, and
58
more applications for fossil-fueled plants than in previous years.
External factors such as applicant changes to plant proposals,
public opposition to applications, and the inability of other
agencies to complete their reviews quickly are also delaying the
siting process. Delays in siting have postponed the opening of
power plants that could help California meet the current energy
shortage and avoid further blackouts.
Partly to establish a faster, more coordinated power plant siting
process, the act created the energy commission in 1974.12 The
act initially set up a two-part siting process that took a total of
36 months. The first part was an 18-month Notice of Intention
process, during which the energy commission would decide
whether an applicant’s new power plant site was appropriate,
considering environmental, public health and safety, economic,
social, and technological factors. The second part was an
18-month Application for Certification process, during which the
energy commission ensured that the proposed plant itself was
designed, sited, and operated to protect the environment and
assure public health and safety. In 1978 the Legislature revised
the act and replaced the two-part process with a single, 12-month
Application for Certification process for certain types of plants,
and it later expanded this revised process to cover most types of
power plants.13 The revised certification process, in which the
energy commission examines both the proposed site and the
proposed plant simultaneously, is essentially the same process
now used to site new power plants.
Although it requires the energy commission to issue a decision
on a new plant application for construction within 12 months of
the date the application is complete, the act allows the energy
The law requires the commission and the applicant to mutually agree to a longer
energy commission to process when necessary. According to the deputy director of the
issue a decision on energy commission’s siting division, if there is a delay in a case,
completed applications to the need for an extension is usually identified by energy commis-
construct most power sion staff or another party, discussed with the applicant and the
plants within 12 months commissioners, and then decided by a written order from the
unless the applicant agrees commissioners based on input from the applicant and all the
to a longer timeline. parties. However, these orders generally do not document the
applicant’s agreement with the need for an extension. Such
delays have been the rule rather than the exception. For example,
12 Before this, multiple agencies worked to site power plants; data on the overall
length of these processes is not available.
13 Only nuclear and coal-fired plants must still go through the Notice of Intention
process. The last plant application filed using this process occurred in 1989.
59
between January 1997 and December 2000, the energy commis-
sion received twenty applications requiring the use of its
12-month siting process. Using the 12-month criterion, fifteen
of the twenty proposed plants should have been approved or
rejected on or before April 1, 2001. However, by that date, the
energy commission had made decisions on only twelve of the
fifteen, and only four of the twelve approved applications for
construction were completed in a year or less. For the remaining
eight approved applications, the length of time between
completed application and construction approval averaged more
than 17 months. Figure 2 shows the relevant timelines for each
of the power plant applications the energy commission received
for its standard siting process between January 1, 1997, and
December 31, 2000. In the Appendix we summarize the energy
commission’s on-line dates for power plants that are under
construction or currently part of its 12-month siting process.
The act also requires that the energy commission determine
whether an application is complete within 45 days of the initial
filing date. During that time, the energy commission may decide
an application is incomplete and request whatever data it believes
is missing. Once the applicant submits the additional data, the
energy commission must decide within 30 days whether this
additional data completes the application. This process can be
repeated as many times as is necessary for the energy commission
to judge the application complete, at which point the 12-month
siting timeline begins. Thus, the act essentially allows the process
to take as long as necessary for the applicant to provide all of the
information that the energy commission requires. For the twelve
applications approved by April 1, 2001, applicants and the energy
commission took an average of 76 days to ensure that the appli-
cations were complete, including the time it took applicants to
submit new information. Although this review period is not
considered part of the overall time to site a power plant, it can
delay the power plant’s construction and on-line dates. Considering
that the 76-day average includes occasions when the initial
applications were incomplete and additional information was
requested and evaluated, we believe it is reasonable.
60
FIGURE 2
Siting and Construction Timelines for All Plants That Applied to the
Energy Commission’s 12-Month Siting Process 1997 Through 2000
Megawatts
High Desert 720 882 days
Sutter 500 448
Los Medanos 559 384
La Paloma* 1,048 406
Delta 880 357
Sunrise† 320 658
Elk Hills 500 546
Three Mountain‡ 500
Metcalf‡ 600
Moss Landing 1,060 441
§
Otay Mesa 510 560
Pastoria 750 330
Blythe 520 364
Midway-Sunset 500 378
Contra Costa‡ 530
Mountainview 1,056 308
Nueva Azalea 550 suspended 3-01
Potrero‡ 520
Morro Bay‡ 1,200
El Segundo‡ 630
1997 1998 1999 2000 2001 2002 2003
Past siting Application filed
Future siting Application complete
Past construction Commission decision
Future construction Construction start
Construction complete/plant on-line
Source: Energy Commission—power plant siting case data.
Note: Future dates are projected by the energy commission as of March 31, 2001, and assumes that all plants are
approved and constructed.
*La Paloma consists of four turbines of approximately 250 MW each. The first turbine is projected to come on-line in
December 2001, with one turbine following each month so that all are on-line by March 2002.
† The applicant filed an amendment in September 2000 changing the project from a cogeneration facility to a ‘peaker’ plant with
a much shorter construction time. According to the deputy director of the energy commission’s siting division, had the applicant
not amended the project, the plant would have taken two years to construct.
‡ These plants do not have projected construction start dates, as they have not yet been approved. Their projected construction
complete dates are tentative.
§ Because this application was approved after April 1, 2001, we did not include it in our analysis of the 12 project applications that
had received an energy commission decision as of that date.
61
The Siting Process Has Lengthened as the Types of Power Plant
Applications Have Changed
The process of making decisions on the siting and building of
power plants has historically been a long one, and it has length-
ened over time. As Figure 3 indicates, the average length of the
energy commission’s siting process for those plants that did not
file a Notice of Intention increased steadily from the late 1970s to
the late 1980s, after which it has remained fairly constant. The
siting process lengthened as the types of applications before the
energy commission changed and as the source of the applications
switched from investor-owned and municipal utilities to
independent generators.
FIGURE 3
Average Length of the Energy Commission's
Standard Siting Process
1975 Through 2000
Year Application Was Completed
Source: Energy Commission—Siting Case History Report and siting case data.
*Four additional applications completed in the late 1970s and two completed in the
early 1980s filed a Notice of Intention prior to filing their Application for
Certification. These plants are not reflected in this figure.
In the late 1970s and early 1980s, the investor-owned utilities
and municipal utility districts, which were familiar with the
energy commission’s process, proposed primarily geothermal
power plants capable of generating an average of about
120 megawatts (MW) each. From the late 1980s to the present,
private generating companies that have less experience with the
energy commission’s siting process have generally proposed
natural gas power plants averaging more than 200 MW of
62
syaD
500
460 459
443
400
378*
365*
300
200
100 Number
of plants
1 9 8 5 12
0
1975–1979 1980–1984 1985–1989 1990–1994 1995–2000
generating capacity. As shown in Table 9, these factors may have
contributed to the lengthening of the energy commission’s siting
process. Our analysis of these factors indicates the following
average effects on the siting process:
(cid:127) Large plants have taken longer to site than smaller plants.
(cid:127) Fossil-fueled plants have taken longer to site than solar and
geothermal plants.
(cid:127) Plants proposed by private generating companies have taken
longer to site than plants proposed by investor-owned utilities
and municipal utility districts.
TABLE 9
Average Length of the Energy Commission’s Standard Siting Process
By Type of Plant For Years 1975 Through 2000
(in Days)
All Plants
All Plants Proposed by All Plants
Between All Plants All Solar and All Fossil- Investor-Owned Proposed
50 MW Over Geothermal Fueled and Municipal by Other
and 200 MW 200 MW Plants Plants Utilities Entities
Application
completeness
to approval 397 467 360 466 387 452
Other External Factors Delay the Energy Commission’s
Siting Process
In addition to changes in the types of applications, other outside
factors have delayed the energy commission’s siting process.
Among these factors are public opposition to projects, delays by
other regulatory agencies, and applicants’ changes to projects
once applications are complete. These factors are at least part of
the reason that one stage in the siting process has been taking
about 100 days longer than the time goal set by the energy
commission. Applicant changes and federal delays slowed the
approval for one plant that, had it met the 12-month goal, could
have been on-line and helping with the State’s energy shortage
by April 2001, rather than its current projected date of July 2001.
The energy commission has attempted to mitigate delays caused
by other agencies by signing agreements with them stating they
should complete their reviews within a specified period of time,
and the Legislature has since made this a legal requirement.
63
To meet its 12-month siting goal, the energy commission has
created a detailed internal timeline that specifies when each
major step in the siting process should be completed. Table 10
shows these stages, the energy commission’s goal for completing
each stage, and the average time each stage in the siting process
actually took for the 12 applications approved prior to
April 1, 2001. This comparison reveals that most of the delay
occurs between the preliminary and final staff assessments of the
application, which takes about 100 days longer than the energy
commission’s goal. In contrast, the energy commission has accu-
rately estimated the length of time needed for all of the other
phases of its process.
TABLE 10
Average Length of Each Stage in the Energy Commission’s Standard Siting
Process for the 12 Applications Approved Prior to April 1, 2001
(in Days)
Goal for
Stage in Completing Average Actual Days Average
Siting Process the Stage Days Required* Exceeded Goal*
Complete application to
preliminary staff assessment 165 165 0
Preliminary staff assessment to
final staff assessment 35 to 55 144 89 to 109
Final staff assessment to presiding
member’s proposed decision 85 to 105 93 (12) to 8
Presiding member’s proposed
decision to final decision 60 43 (17)
Totals 365 459 94
*Numbers do not add up to the total because 3 of the 12 plants did not receive preliminary staff assessments, and so are not
included in the first two stages.
To explain the causes of the delays between the preliminary and
final staff assessment in five recent siting cases, all of which ex-
ceeded the 12-month goal for approval, siting project managers for
the energy commission referred to three primary causes: changes to
the project made by the applicant, public opposition to the project,
and delays by other regulatory agencies involved in the energy
commission’s siting process. Our review of the documentation from
the individual siting applications supported these statements. For
example, in one application, the applicant wanted to build a water
pipeline over land owned by the U.S. Bureau of Land Management
(BLM), so the U.S. Fish and Wildlife Service delayed issuing its
biological opinion while it consulted with the BLM. An advocacy
group also delayed the energy commission’s approval of this plant
64
by filing detailed opposition to several of the plant’s environ-
mental effects, demanding pollution controls not typically
installed in plants of this nature. In total, this plant took 546 days
from the completion of the application to the final decision, just
over 6 months beyond the 12-month goal.
The same advocacy group raised similar issues that delayed
another plant proposed for the same area of the State. This plant
was further delayed when the applicant made multiple changes
to the proposal. For example, in addition to generating electricity,
the original proposal would have produced steam for use by other
industries in the area. However, after the energy commission had
already released its proposed decision on the project, the applicant
changed the original proposal to exclude this steam generation
feature, requiring energy commission staff to revise their analysis
and adding 6 months to the siting process. In total, this plant’s
approval took 658 days. According to project managers, these
types of delays are common to the energy commission’s other
recent siting applications.
In an effort to minimize delays caused by other review agencies,
the energy commission has attempted to ensure that the other
agencies conduct their permitting activities as quickly as possible.
Whereas the energy commission has the primary responsibility
for siting new thermal power plants, other entities—such as the
California Department of Fish and Game, the Regional Water
Quality Control Boards, and various local agencies—often have
jurisdiction or a special interest in specific aspects of these
projects. In most cases, the energy commission will not make a
final decision on a project until these other agencies have com-
pleted their reviews and submitted their findings as testimony in
the energy commission’s hearings on the project.
According to the assistant division chief of the energy
commission’s siting division, in the late 1980s the energy
commission began negotiating memoranda of understanding
with the other involved agencies to prevent their processes from
dragging out the siting process. These agreements stated that
these other agencies were to complete their reviews and submit
their findings to the energy commission within 180 days of the
date the commission received a completed application. Upon the
energy commission’s recommendation, the Legislature included
this 180-day comment period in legislation passed in
August 2000. This restriction should improve the energy
commission’s chances of having the information needed from
other agencies when it holds formal hearings on the siting of a
65
power plant. In turn, the energy commission should be better
able to deliver a final decision on the plant within its 12-month
timeline. Even if the energy commission does not make its
decision within 12 months, this coordination among agencies at
least helps ensure that projects will not require further approval
after the energy commission issues its decision.
Siting Delays Did Not Cause California’s Supply Shortage but
Contributed to the State’s Precarious Situation
Although the energy commission generally takes longer than
12 months to render decisions on the siting of power plants, this
The energy commission does not appear to have been a cause of California’s electricity
received few power plant supply shortage. The energy commission received and approved
applications in the early few power plant applications in the early 1990s, apparently due to
1990s, apparently due to a combination of excess supply at that time and uncertainty on
a combination of excess the part of the investor-owned utilities about the effects of
supply, uncertainty about deregulation, as well as a series of regulatory decisions limiting
the effect that deregulation the construction of qualifying facilities—plants that produce
might have, and federal energy through resources such as wind, solar, and natural gas.
regulatory decisions. Although they are not the cause of California’s supply shortage,
siting delays have prevented badly needed megawatts from
coming on-line by pushing back the dates that new plants can
begin construction. With the prospect of rolling blackouts looming
this summer, California would be better positioned had the plants
met the 12-month siting goal and were now delivering power to
the State. However, some plant owners have also made business
decisions to delay the start of construction on their plants,
further pushing back some plants’ on-line dates.
One factor contributing to the slowdown in the growth of the
State’s electricity supply was that the investor-owned utilities
built fewer new power plants in the early 1990s than they had in
previous years. In fact, as indicated in Figure 4 on page 68, from
1991 to 1995 the investor-owned utilities submitted only one
application to the energy commission to site a new power plant
through its standard siting process, whereas they submitted six
such applications between 1980 and 1990. During the early
1990s, the CPUC was studying whether to deregulate the electric-
ity market, and this appears to have been a disincentive to build
more power plants. For example, if the investor-owned utilities
66
believed that after deregulation they would be required to sell
their plants to other entities to facilitate competition, they might
be unsure as to whether they would be able to recoup the cost of
building the plants at that time. Even if they believed they would
be allowed to keep their power plants, they might be unsure as to
whether the wholesale price of electricity in the new deregulated
market would be high enough to allow them to recoup their
investment in new power plants. Therefore, uncertainty about
what deregulation would require appears to have given the
investor-owned utilities incentives to reduce their efforts to build
new power plants.
Second, because it believed the CPUC was violating federal law in
the way it was contracting with certain independent energy
producers, the Federal Energy Regulatory Commission (FERC)
ended the CPUC’s process for determining which independent
producers could build new power plants and how much the
investor-owned utilities were required to pay them for their
electricity. These independently owned plants, called qualifying
facilities (QFs), provide about 20 percent of California’s power
supply and produce electricity through resources such as wind,
solar, and natural gas. They were created by a 1978 federal law that
required the investor-owned utilities to buy the electricity that
QFs produced, after which applications for new QFs in California
expanded rapidly throughout the 1980s, as shown in Figure 4.
The CPUC recognized that the contracts it awarded to QFs in the
1980s gave them an incentive to overbuild, and so it created a new
process in July 1989 to determine how much new supply should be
added by QFs and how much the investor-owned utilities should
pay them for their electricity. The CPUC and the investor-owned
utilities worked together for several years to attempt to implement
this process. However, the utilities complained to FERC in
A FERC decision greatly January 1995 that the prices set by the CPUC under the new
limited the number of process were higher than federal law permitted because they
qualifying facilities built included a bonus based on how environmentally friendly the QFs
after 1995—this also were. FERC agreed with the utilities and issued its decision in
contributed to the State’s February 1995, effectively putting an end to the process before it
energy supply shortage. was ever implemented. This greatly limited the number of QFs
that independent energy producers built in the State.
67
FIGURE 4
Applications Submitted Using the Energy Commission's
Standard Siting Process by Investor-Owned Utilities and
Independent Energy Producers
1975 Through 1995
Source: Energy Commission—Siting Case History by Applicant Type.
The energy commission approved twelve plants through its
12-month siting process between September 1996, when
AB 1890 became effective, and April 1, 2001. All of these plants
are large natural gas plants proposed by private companies that
will potentially sell their electricity in the wholesale market. If the
siting process for these twelve plants had taken 12 months, as
specified by law, two of them, representing 1,059 MW, could
have been generating power by April and June 2001, assuming
no change in plant construction schedules. As it now stands,
neither of these plants are currently expected to be operational
before July 2001. As more power plants come on-line and the
State’s supply margin increases over the next few years, the
negative effect of delays in the energy commission’s siting
process will gradually decrease.
In addition to delays in the siting process, delays in starting
construction are affecting the eventual opening of 5 of the
12 plants the energy commission has already approved for
construction. As of April 1, 2001, 5 of the 12 power plants
(totaling over 3,500 MW) are projected to begin construction four
or more months after the energy commission approved them,
with one 720 MW plant not scheduled to begin construction
until almost a year after the energy commission approved it. The
68
snoitacilppA
fo
rebmuN
20
Independent
energy producers 17
Investor-owned utilities
15
10 7
5
5
4
1
2
1
0
1975–1979 1980–1984 1985–1990 1991–1995
assistant division chief of the energy commission’s siting division
said that some power plant owners have made business decisions
Although already to delay construction based on their interpretation of market
approved, five power conditions. Nevertheless, these construction delays will contribute
plant developers plan to to the ultimate length of time it takes to bring much-needed new
wait four or more months supplies of electricity on-line. According to the energy commission,
before beginning it intends to condition all applications received after May 1, 2001,
construction. to require that construction begin within one year of the date an
application is approved.
THE ENERGY COMMISSION HAS MADE CHANGES
TO IMPROVE ITS SITING PROCESS BUT IS NOT
EVALUATING THE EFFECTIVENESS OF THOSE CHANGES
In 1999 the Legislature mandated that the energy commission
report on improvements that it could make to its siting process,
and the energy commission issued its report in March 2000. As of
April 1, 2001, the energy commission states that it has imple-
mented over half of those changes. However, without a plan to
measure whether these changes have been successful, the energy
commission does not know whether they will improve the
generation siting process as intended.
Several changes the energy commission recommended were
intended to address delays encountered in its siting process,
including some delays mentioned earlier in this report. For
example, the energy commission recommended that its applica-
tion criteria be modified to encompass the information other
agencies needed for their review, thereby limiting or eliminating
these agencies’ requests for additional information.
As of April 1, 2001, the energy commission indicated that of the
25 report recommendations that required its action, it has fully
implemented 15, has partially implemented 3, and is working on
6 others. One recommended change has been put on hold until
the energy crisis is resolved. However, the energy commission
has not developed methods to judge the effectiveness of its
changes. For example, the energy commission changed its
regulations to specify that outside parties could only request
information on applications within 180 days of the date the
application is complete. The energy commission found that late
requests for information could delay the siting process, and it
implemented this change to prevent such delays. However, the
energy commission has not attempted to measure whether this
69
new procedure has actually prevented the delays it previously
Because the energy identified. Thus, the energy commission cannot guarantee that
commission is not this change and others it has made have actually improved the
evaluating the siting process as intended.
effectiveness of changes to
its siting process, it
cannot tell whether the
SEVERAL NEW EXPEDITED SITING PROCESSES HAVE
process is improving.
YET TO YIELD SIGNIFICANT RESULTS
In addition to trying to improve its 12-month siting process, the
energy commission recently began using three new expedited
siting processes of varying lengths. Although to date none of these
processes has resulted in many new plant approvals, according to
the energy commission one is estimated to add several hundred
megawatts to the State’s electricity supply in time to meet this
summer’s peak demand. The energy commission’s total estimated
megawatts and on-line dates for plants sited under these processes
are summarized in the Appendix.
The first of these new processes is a 6-month siting process
intended to replace the energy commission’s existing Small Power
Plant Exemption (SPPE)14 for projects meeting certain criteria.
The energy commission recommended this 6-month process to the
Legislature, which put the new process into law with its passage of
AB 970 but did not repeal the SPPE process. The energy commis-
sion recommended the change because it found that the SPPE
process was not necessarily simpler or shorter for applicants than
the standard 12-month process. Although the SPPE process
exempted qualified applicants from its normal siting process, the
energy commission found that approval took 6 to 8 months, after
which applicants still needed to get permits from the relevant
state and local agencies. Further, SPPE projects could be delayed
for months due to inadequate applications because the process
had no filing requirements. In contrast, under its new 6-month
siting process, any other agencies having jurisdiction or special
interest in the proposed plant must provide their comments,
determinations, and opinions within 100 days of the date the
energy commission judges the application complete. Also, the
energy commission created stricter application criteria for this
process to ensure that the plants will have minimal environmen-
tal and public health effects. Plants that meet those criteria can
14 Included in the Warren-Alquist State Energy Resources Conservation and
Development Act, the Small Power Plant Exemption was intended as a means to
avoid the energy commission’s 12-month process for plants of 50 MW to 100 MW
that the energy commission finds will have no substantial adverse environmental
impact. The energy commission has granted 16 such exemptions since 1976.
70
receive the energy commission’s approval in half the time of the
standard siting process. As of April 2001 the energy commission
had not completed evaluating any applications under this pro-
cess, so it will not have an immediate impact on the State’s
current supply problem by getting more power plants on-line by
summer 2001. Nevertheless, the process may provide an effective
tool for approving certain plants more efficiently and may yield
benefits in the long run.
The energy commission’s second expedited procedure is a four-
month siting process meant for so-called “peaker” plants, intended
for use only during periods of peak electricity demand, to make up
some of the shortfall in the State’s supply. Included in AB 970,
which took effect in September 2000, the four-month process was
created specifically to site power plants that could be on-line by
August 1, 2001. The four-month expedited process originally
applied only to those companies able to file complete applications
or amendments to pending applications for new plants by the end
of October 2000. Although companies managed to submit
applications for seven plants by the October deadline, six of the
seven applications were withdrawn. According to the deputy
Only one of seven director of the energy siting division, severe time constraints limited
applications to the the applications’ success. The seventh application was approved,
4-month siting process and as of April 1, 2001, the plant was expected to be on-line by
was approved—this August 2001. The energy commission approved this 51 MW plant
51 MW plant is expected in March 2001, taking just over four months. By executive order,
to be on-line by the governor has since extended the deadline to apply for the four-
August 2001. month process to December 31, 2001, with the stipulation that
plants approved under the process be on-line by August 31, 2002.
Energy commission staff expect to receive several applications
under the new deadline and believe the four-month process will be
more successful now that applicants have more time to prepare
their applications.
The energy commission’s third new siting process implements an
emergency process written into its existing statute. By declaring a
state of emergency in January 2001, the governor allowed the
energy commission to use that emergency process to authorize the
construction of peaker plants or renewable energy plants that can
be on-line by July 31, 2001, under whatever terms it believed were
necessary to protect the public interest. The energy commission has
since instituted a 21-day siting process for peaker plants. As
requested by the governor in a February 2001 executive order, the
energy commission issued a report that month detailing 33
potential sites throughout the State that would make appropriate
peaker plant locations for new plants approved under the 21-day
71
siting timeline. By identifying these sites in advance, the energy
commission removed the need to determine on a case-by-case basis
the acceptability of proposed sites, thereby reducing the time
needed to approve each plant. According to the governor’s Web site,
this emergency process was intended to get 1,000 MW of capacity
on-line by July 2001 (in addition to 1,133 MW of peaker plants the
ISO had already contracted for that were also expected to be on-line
by summer 2001).15
The energy commission has begun reviewing several peaker plants
under the expedited process, but as of April 1 these plants were all
part of the megawatts originally contracted for by the ISO.16
Although they will not meet the July 2001 goal, energy
The energy commission’s commission staff expect to receive many new applications
21-day siting process is under this process and believe they can approve applications
unlikely to bring a totaling more than 1,000 MW for plants that can be on-line by
significant amount of September 1, 2001. However, the State’s summer peak demand
new supply on-line until will likely come before September, and the energy commission
September 2001. concedes that no new supply will be brought on-line because of
this process (except for those plants contracted for by the ISO) until
August 1, 2001, with the number steadily increasing to 1,000 MW
or more by the end of summer. Also, as of April 6, 2001, the new
supply the ISO contracted for had increased to 1,324 MW, but the
ISO predicted that only about 250 MW of this would complete the
energy commission’s 21-day process and be on-line by July 2001,
with this number also increasing through the summer.
HAVING UTILITIES RESPONSIBLE FOR TRANSMISSION
PLANNING MAY HINDER THE DEVELOPMENT OF NEW
TRANSMISSION LINES
With its push to bring new power plants on-line to solve the
energy supply shortage, the State also has to consider the means
of delivering the electricity California needs this summer and
beyond. The investor-owned utilities are primarily responsible for
transmission planning, determining through their own separate
analyses of demand growth what new transmission lines are
15 Recognizing the State’s need for new generation by summer 2001, the ISO
requested bids in August 2000 for up to 3,000 MW of new peaker plants. As of
February 2001 the ISO had signed contracts for 1,133 MW. However, the ISO does
not have authority to site new power plants, so the energy commission must still
approve all of the ISO’s contracted plants of 50 MW or more.
16 The energy commission has since received peaker plant applications that, as of
April 23, 2001, it estimates will bring 207 MW on-line in August 2001.
72
needed and where. The ISO and CPUC coordinate, plan, and
oversee the expansion of the State’s transmission grid. Because
the three investor-owned utilities create three individual transmis-
sion expansion plans, based on potentially varying assumptions
of the future demand growth in their respective service areas, the
ISO’s ability to create a comprehensive statewide expansion plan
may be hindered. Also, the investor-owned utilities may have
incentives that conflict with their responsibility to expand the
grid where necessary—in part because transmission constraints
may be protecting some of the investor-owned utilities’ power
plants from competition. Therefore, the investor-owned utilities’
demand analyses may not be the best basis for determining when
and where transmission lines are needed. In relying on these
analyses to determine transmission line expansion, rather than
on analyses prepared independently, the ISO and CPUC lack
assurance that the utilities’ proposed transmission projects are
optimizing the transmission grid.
Investor-Owned Utilities Have the Primary Responsibility for
Planning the Transmission Grid
The transmission grid currently operated by the ISO was not
originally built to function as an integrated system. Historically,
each of the three investor-owned utilities, as well as the munici-
pal utility districts throughout the State, built their own separate
transmission systems to serve their individual needs. Because
California’s transmission these entities owned most of the power plants and were the
grid was not originally monopoly provider of electricity to customers in their area, their
designed to function as a transmission systems were built to do little more than get the
single integrated system. power from their generating facilities to their customers. These
individual transmission systems were interconnected such that
each investor-owned utility and municipal utility could import
the electricity it might need under adverse conditions. However,
these interconnections were not intended to allow generators
from outside each area of monopoly control to regularly serve
demand within that area. To ensure that their transmission
systems were adequate to meet future electricity demand, the
investor-owned and municipal utilities created periodic transmis-
sion expansion plans. These plans identified specific transmission
projects that the various utilities determined would be necessary
to meet their own analyses of projected electricity demand.
When California restructured its electricity industry, it created the
ISO to control the operation of the investor-owned utilities’
transmission grids and coordinate the long-term grid planning
processes of the investor-owned utilities. Under the system
73
currently employed by the ISO, the investor-owned utilities each
create a transmission expansion plan, as they did before restructur-
ing, submitting the plans and supporting data to the ISO. The ISO
analyzes the plans and identifies any additional transmission
projects it determines are needed to allow for greater competition
among generators or to ensure that the entire grid meets the ISO’s
minimum reliability criteria. However, it does not independently
verify the utilities’ demand growth projections, which form part
of the basis for the ISO’s list of needed projects. The investor-
owned utilities add the additional projects the ISO has identified
to their respective plans and submits individual transmission
projects to the CPUC to receive environmental reviews and the
final construction permits.
Although the ISO and CPUC Rely on the Investor-Owned
Utilities’ Projections, the Utilities May Have a Conflict of
Interest in Expanding Transmission
Having created transmission expansion plans for many years,
each investor-owned utility bases its demand growth projections
on individual assumptions that may conflict with the others,
Because both the ISO and potentially making it difficult to create a single statewide projection.
CPUC rely on the In addition, the utilities may be understating their current demand
investor-owned utilities’ growth projections. Although the law requires them to ensure
data, their current that their transmission systems are adequate to serve all customers
transmission planning in their service area, the investor-owned utilities have economic
efforts may not be incentives that may limit their decisions to expand their
optimizing the State’s transmission systems beyond the required minimum level of
transmission grid. service. Because both the ISO and the CPUC rely on the investor-
owned utilities’ demand growth data, they lack assurance that
the current transmission planning process is optimizing the
transmission grid. Therefore, the State may have barriers to
competition among power generators and also may run a higher
risk of experiencing blackouts because of transmission constraints.
Investor-owned utilities base their plans for transmission expansion
partly upon their individual assumptions of future demand
growth within their respective service areas. Even if the investor-
owned utilities are making their best effort to project future
demand growth, these differing assumptions may make the
individual plans inconsistent with one another. For example, one
investor-owned utility may assume statewide economic growth
of 1 percent, while another may assume a 4 percent growth. Such
74
inconsistencies in the utilities’ projections would make the ISO’s
statewide transmission plan inconsistent as well, because it is
based in part on these projections.
In addition, the investor-owned utilities may have a disincentive
to project the need for new transmission lines. Because
transmission lines are not a competitive resource, FERC regulates
Several areas of the rates that investor-owned utilities may charge for their use,
California’s transmission ensuring that the utilities can recover their transmission line
grid currently do not construction and operating costs, plus a fair profit margin.17
have adequate capacity However, each investor-owned utility is actually a subsidiary of a
to allow free competition parent corporation that is involved in multiple energy-related
among generators. activities, and transmission lines are only one of the means by
which the investor-owned utilities’ parent companies make a
profit. Other activities, such as building unregulated power plants
to compete in various energy markets, are likely to be much more
lucrative. Moreover, several areas of California’s transmission grid
currently do not have adequate transmission capacity to allow
free competition among power generators. As required by
AB 970, the CPUC completed a report in February 2001
identifying constraints in the State’s transmission grid. Based on
ISO data, the CPUC identified eight congested transmission lines
in the State that limit certain areas’ access to outside sources of
power. When their power plants are located in these restricted
areas, the investor-owned utilities’ parent companies have limited
incentive to build more lines for other power generators to use to
compete with them. Therefore, the utilities may have an
incentive to underestimate future growth in electricity
demand and to reduce the number of transmission lines they
project that they need to build.
Although the ISO reviews the transmission expansion plans
created by the investor-owned utilities to ensure that they meet
its reliability criteria, it still relies primarily on the utilities’ demand
growth projections to show where future grid constraints may
arise. The ISO’s director of grid planning observed that since the
ISO has limited ability to review the investor-owned utilities’
17 Because they are a means for conducting interstate commerce, transmission lines
and the rates charged for their use are regulated by the federal government.
However, the CPUC regulates the ultimate retail rates that investor-owned utilities
can charge their consumers.
75
projections, the energy commission (which already does statewide
demand growth projections) would be an appropriate independent
source of this information.
In addition, the CPUC has the legal authority to determine whether
transmission projects are required for “public convenience and
necessity,”18 meaning that when the CPUC assesses the benefit the
transmission lines provide by transmitting electricity to consumers,
it considers the project’s impact on community or aesthetic values,
and any significant influence on the environment. However,
according to a CPUC administrative law judge, the CPUC does
not independently verify the investor-owned utilities’ demand
growth projections, which are the basis for hearings determining
when and where a new transmission line will be needed. Rather,
if it finds the testimony persuasive, the CPUC accepts the utili-
ties’ word regarding demand growth. The administrative law
judge stated that the CPUC would reject the investor-owned
utility’s data only if an intervenor19 in the process submitted
conflicting information and the CPUC found the intervenor’s
argument more persuasive than the investor-owned utility’s.
THE CALIFORNIA PUBLIC UTILITIES COMMISSION’S
TRANSMISSION SITING PROCESS IS NOT RESPONSIVE
TO THE CURRENT ENERGY CRISIS
Although it is responsible for siting the electrical transmission
lines that the investor-owned utilities propose,20 the CPUC does
not have an expedited transmission siting process that could
better assist California’s recovery from the energy crisis. Moreover,
in almost half of the CPUC’s siting cases using the environmental
18 Although the statute states that no investor-owned utility may build a new
transmission line without the CPUC first determining that public convenience and
necessity requires it, the CPUC grants a Certificate of Public Convenience and
Necessity only for projects of 200 or more kilovolts. For projects between 50 and
200 kilovolts, the CPUC grants a Permit to Construct, which has somewhat less
stringent application requirements but also includes an environmental review
process. The CPUC does not exercise its authority over projects of 50 kilovolts or less.
19 Intervenors are individuals or organizations that request official standing in the
CPUC’s hearings on a transmission siting case. Intervenors receive all documents
related to the case, may submit testimony, and may make oral arguments in the
hearing.
20 According to the CPUC, transmission projects proposed by independent parties are
under the jurisdiction of local agencies. Projects proposed by municipal utility
districts are licensed by the municipal utilities themselves, as public agencies.
Transmission lines required to connect most new generating plants to the existing
transmission grid are licensed by the energy commission as part of its licensing of a
plant, including municipal and independent plants.
76
review process outlined in the California Environmental Quality
Act (CEQA), the CPUC significantly exceeded the 180- and 365-day
goals CEQA sets for completing environmental reviews. Recent
events show that a lack of adequate transmission capacity in
some areas of the State can be devastating—transmission
constraints have already caused rolling blackouts and have the
potential to do so again in the near future. Long delays in siting
added transmission could slow the State’s recovery from the
current energy crisis. For example, an ISO study has found that
the primary transmission connection between Northern and
Southern California must be expanded to ensure delivery of
electricity to Northern California from the south in adverse
conditions, when rolling blackouts are a threat. The CPUC will
likely have to conduct an environmental review for this expansion,
and the longer this review takes, the later the expansion will
occur. Major causes of delay in transmission siting cases include
the need to coordinate with the federal government, contracting
delays, and late involvement by other agencies. Although one of
these delays is beyond the CPUC’s control, it could still improve
its transmission siting process.
The CPUC Lacks an Expedited Siting Process, and Its
Standard Siting Process Takes Longer Than the Time Goals
Almost half of the
Outlined in CEQA
environmental reviews the
CPUC has conducted on The CPUC is responsible for granting certificates to the investor-
proposed transmission owned utilities to build proposed electrical transmission lines. In
projects since 1990 have spite of the likely need for near-term expansion of certain parts of
taken longer than CEQA the transmission grid, the CPUC does not have an expedited
recommends. siting process for high-priority projects. Also, for almost half of
the transmission permits requiring environmental review that the
CPUC considered after 1990, it took or is taking longer than the
CEQA timelines for completing those reviews. According to the
ISO, at least one of these delayed permits was for a project that
would reduce transmission constraints expected in the
San Francisco Bay Area by summer 2001. Thus, the CPUC’s
inability to meet the CEQA timelines may contribute to the
State’s energy crisis.
Recent events in California indicate that certain parts of the
transmission grid may need to be expanded quickly, yet the
CPUC has no expedited transmission siting process for urgently
needed lines. Rolling blackouts occurring in Northern California
on January 17, 2001, could have been avoided if the primary
transmission connection between the northern and southern
parts of the state had been able to transmit more electricity. The
77
ISO has recommended expanding this line, which will likely
require an environmental review by the CPUC. The length of this
review will affect how quickly the connection can be expanded.
In an April 3, 2001 order, the CPUC directed PG&E to begin
certain biological studies along this line that have to be completed
before any construction could begin and, because of the nature
of the studies, must be conducted during the spring. In its order,
the CPUC stated that it took this step so that the study would not
be delayed until the spring of next year because such a delay
would also delay starting construction on this transmission
project once the CPUC ordered such construction. However, even
The CPUC does not have if the CPUC orders an expansion of this transmission line, CEQA
an expedited transmission requires that it still conduct a full environmental review once the
siting process for more application is filed. Unlike the energy commission, which has
urgent projects. expedited processes for siting new power plants, the CPUC does
not have any expedited siting processes for transmission projects
needed to address short-term problems in the transmission grid.
The CPUC’s lack of an expedited process also contrasts with recent
actions of the ISO, which is modifying its tariff agreement with
FERC to allow the ISO to expedite its approval of new transmission
projects it determines are necessary for near-term grid reliability.
Thus, the CPUC is the only one of the three entities responsible
for planning or siting new electrical generation or transmission
that is not implementing an expedited process to speed the
expansion of California’s electricity infrastructure in response to
the energy crisis. When asked about the possibility of creating an
expedited process, the director of the CPUC’s energy division
indicated that the law requires the CPUC to use the standard
CEQA siting process except in an emergency. According to the
energy division’s director, it is the CPUC’s position that although
the governor declared an emergency requiring the energy commis-
sion to expedite its power plant siting process, he did not make a
similar declaration relating to CPUC’s transmission siting process.
The CPUC’s standard transmission siting process often takes longer
than state law recommends. For proposed transmission projects over
50 kilovolts21 that it determines are not exempt from its siting
process, the CPUC must determine whether the public would
benefit from the line being built and follow the CEQA guidelines to
identify the environmental effects. The CEQA guidelines indicate
that for projects that are likely to have a significant environmen-
tal effect that cannot be mitigated, the CPUC must complete an
21 Volts are a measurement of the amount of force with which electricity is pushed
through a transmission line. One kilovolt (kV) is 1,000 volts.
78
Environmental Impact Report (EIR) within 365 days of the date
the project’s application is complete. For projects that will not
Three of the four EIRs the have any significant impacts, the CPUC must complete a nega-
CPUC began in the 1990s tive declaration, and for projects for which any potential signifi-
have taken or are taking cant impact can be avoided or mitigated, a mitigated negative
significantly longer than declaration must be completed within 180 days of the application’s
365 days. completion. The CPUC hires consultants, overseen by CPUC staff,
to complete these reports and declarations.
However, CEQA provides an exception to the time requirements
if compelling circumstances justify additional time and the
project applicant agrees—and in almost half of its environmental
reviews, the CPUC has used that exception. As shown in Figure 5,
almost half of the environmental reviews the CPUC has conducted
for proposed transmission lines since 1990 have taken or are
taking significantly longer than the prescribed CEQA timelines.
Of 17 environmental reviews of transmission projects, 8 were not
completed on or near the timeline set forth in CEQA. Of the
4 projects requiring EIRs:
(cid:127) The CPUC completed one EIR in the past decade, taking
695 days to approve it and issue a permit.
(cid:127) The CPUC began a second in 1996, which was finally sus-
pended in 2000, after about 4 years of work, when it became
apparent that a permit would not be issued.
(cid:127) The two other EIRs were still ongoing as of April 1, 2001; one
has been under review for 16 months.
The ISO has identified at least one of these delayed projects as
being needed to address transmission constraints expected in the
San Francisco Bay Area by summer 2001. Although the investor-
owned utility completed its application to the CPUC for a
permit for this line by December 1999, the CPUC will not make
a decision on whether to adopt an EIR or grant a permit before
May 2001, at least 5 months beyond the one-year CEQA timeline.
If approved, this project will not be operating before June 2002,
according to the ISO’s current projection.
The remaining 13 projects required mitigated negative
declarations, and 5 of these greatly exceeded the CEQA timeline
of 180 days. The average length of time from completed
application to final decision for these 5 projects was 343 days, or
more than 5 months beyond the CEQA deadline.
79
FIGURE 5
Duration of CPUC Environmental Reviews of Transmission
Siting Projects Begun After 1990
1,451*
695
471
Projects still ongoing as of April 1, 2001
352
406
393
353
293
272
211
199
199
181
176
172
156
129
Days
Source: CPUC—Transmission project siting decisions and project-specific Web sites.
* Project suspended in October 2000.
Certain types of projects are exempted by the CPUC from detailed
review, such as replacement or minor relocation of existing lines.
The CPUC automatically approves these exempted projects
without a CEQA review. Of the 60 transmission project applications
it received between January 1, 1998, and November 2, 2000, the
CPUC automatically approved 47 in this manner.
Even after the threat of blackouts has passed, congestion in the
transmission grid may limit how competitive the State’s electricity
market can be. For example, the ISO has identified seven transmis-
sion paths, connecting various regions of California to each other
or to other states, that were so congested in 1999 and the first
half of 2000 that together they cost wholesale electricity buyers
an additional $128.5 million over the wholesale price for the
80
latnemnorivnE
detagitiM
stropeR
tcapmI
snoitaralceD
evitageN
365–
day deadline
0 300 600 900 1,200 1,500
180–
day deadline
power transmitted over those paths. When transmission lines are
overly congested, the ISO assesses a usage charge to buyers of
the electricity delivered through those lines. The higher prices paid
for the wholesale electricity that arrives over congested transmis-
sion paths also signals the power generators within those affected
areas to raise their prices above the levels they would ordinarily
have been able to charge in a truly competitive market. The
longer it takes to site and build new transmission lines to alleviate
these constraints, the longer these prices will remain artificially
high, and the longer the State will delay true competition.
One Cause of Transmission Siting Delays Is Beyond the
CPUC’s Control, but Others Could Be Addressed by Revising
the Transmission Siting Process
According to CPUC siting project managers, transmission siting
projects are delayed because of a slow consultant contracting
process, late involvement by other agencies, and the need to
coordinate with the federal government on certain projects,
among other reasons. We reviewed five projects in which the
environmental reviews exceeded CEQA’s deadlines and confirmed
the CPUC project managers’ statements. For example, upon
completing the draft mitigated negative declaration for one
project, the CPUC received notices from two agencies indicating
that the project would need to obtain additional permits beyond
the one granted by the CPUC. These permitting processes were
presumably still ongoing after the CPUC approved the project.
Although coordination with the federal government is largely
beyond its control, the CPUC has attempted to address the
contracting delays. However, the CPUC has not addressed late
involvement by other state agencies.
As noted earlier, the CPUC hires consultants to perform its
environmental reviews, with CPUC staff overseeing the consult-
ants’ activities. The State contracting process the CPUC uses to
hire contractors for many of its transmission siting projects has
lengthened some siting projects by months. For example, the
CPUC judged one application complete in February 1994 but was
not able to sign a contract for the environmental review until
May 1994. Therefore, the contractor could not begin performing
the environmental review until almost three months after the
CEQA timeline had begun. The CPUC indicates it addressed this
type of delay by creating “on-call” contracts in 1995, through
which it annually preselects contractors to perform environmental
reviews during the following year. Thus, when an investor-owned
utility tells the CPUC that it is preparing a new transmission
81
application that will require an environmental review, the CPUC
can simply amend the contract with the preselected contractor to
reflect the details of the siting case, with the contractor ideally
being ready to begin work by the time the application is filed.
CPUC staff indicate that this process has allowed them to assign
work to contractors relatively quickly.
The Department of General Services (DGS) indicated to the CPUC
in 1999 that its contracting rules did not allow the CPUC to use
on-call contracts. However, the CPUC and DGS reached an
agreement in August 2000 allowing the CPUC to continue to use
on-call contracts on an interim basis while it updated its contracting
rules. A representative of the CPUC’s legal division anticipates
that these revisions will be completed by July 2001.
As with the energy commission’s siting process, several other
agencies are involved in granting permits for transmission
projects reviewed by the CPUC. Although the CPUC encourages
these other agencies to conduct their reviews concurrently to the
Transmission projects may extent possible, it does not actively coordinate the activities of
still require additional these other agencies to the extent that the energy commission
permits after the CPUC has does in its siting process. In fact, while the Warren-Alquist Act
completed its review, requires other agencies to complete their reviews before the
adding to the overall time energy commission issues its permit for a power plant, CEQA
it takes to site proposed requires other agencies to use the CPUC’s completed environ-
transmission lines. mental document to decide whether to grant their own permits
for a transmission project. Therefore, transmission projects may
still need several permits after they have completed the CPUC’s
process, adding to the time needed to site the proposed transmis-
sion line. For example, in August 1999, the CPUC completed a
draft mitigated negative declaration and subsequently received a
comment letter from a regional water quality control board
stating that the project may need two separate permits that
together could take up to 180 days to grant from the date the
board received completed applications for these permits. Similarly,
the California Department of Transportation submitted a com-
ment letter indicating that the same project may need a permit
from the Federal Aviation Administration because it is close to an
airport. Although the CPUC approved the project in January 2000,
these additional permitting processes were presumably still
ongoing after that point.
If the CPUC coordinated the activities of the other agencies
involved in permitting transmission projects, as the energy
commission does for siting power plants—requiring other agen-
cies to complete their reviews within 180 days of the date the
82
CPUC received a completed application—it could greatly speed
the transmission siting process. According to the director of the
energy division, even though the CPUC is supportive of such a
change, it may be difficult to convince the other agencies it
works with in siting transmission lines that such a change will
benefit all the concerned parties.
The CPUC must also work together with the federal government
on transmission siting projects in which the federal government
has a specific interest. For example, on a project that began in
1996 and was suspended in October 2000, the CPUC and the
federal government worked together to produce an environmen-
tal impact document because the proposed transmission project
crossed land owned by several federal agencies. The CPUC and
the federal government disagreed on one aspect of the project,
which delayed the process, and the federal government was slow
in completing part of its environmental assessment. After ulti-
mately concluding that it could not reasonably perform a study
the federal government required, the applicant suspended the
application process and decided to meet its electricity needs in
the area by attempting to build a power plant. Given that the
applicant’s disagreement was with the federal government, it does
not appear that the CPUC could have prevented this outcome.
RECOMMENDATIONS
To assess the impact of recent changes to its process for siting
power plants, the energy commission should establish an
evaluation plan.
So that the State has an independent projection of demand
growth on which to base transmission expansions, the energy
commission should make regional demand growth projections for
the ISO and the CPUC to use in their transmission planning and
siting processes.
The Legislature should create an expedited electricity transmission
siting process for projects that are needed for short-term
transmission system reliability.
The Legislature should institute a coordinated electricity
transmission siting process as it relates to other agencies
similar to the coordinated power plant siting process used at
n
the energy commission.
83
Blank page inserted for reproduction purposes only.
84
CHAPTER 4
Numerous Factors Limited the
Success of Consumer Choice
CHAPTER SUMMARY
O
n March 31, 1998, California implemented the deregula-
tion of its electricity industry, shifting from the prior
monopolistic structure to one in which energy customers
could choose to stay with the investor-owned utilities or purchase
their electricity from another provider. The California Public
Utilities Commission (CPUC) and the Legislature had high
expectations that consumer choice would increase competition
and lead to lower electricity prices. However, Californians never
fully realized these benefits of consumer choice because certain
features of deregulation and its implementation kept consumer
choice from flourishing. Moreover, if true retail competition
among energy service providers (ESPs) and the investor-owned
utilities had materialized, it might have helped to mitigate the
skyrocketing of wholesale electricity prices, which began in the
summer of 2000.
Part of the implementation strategy in deregulating the electricity
industry that took place on March 31, 1998, initially required the
investor-owned utilities to buy energy at spot market prices
(prices charged in a commodity market that sells electricity) in
the California Power Exchange (PX). The utilities in turn passed
these spot prices on to their customers as the power generation
portion of their rates (excluding fixed transmission and distribu-
tion rates). With a very small customer base, ESPs had difficulty
negotiating purchase prices for wholesale electricity that were
lower than those the power generators could afford to charge the
investor-owned utilities in the spot market. As long as the ESPs
had to try to beat spot market prices for their wholesale electricity
purchases, they found it nearly impossible to offer their customers
any substantial savings. With few customers seeking their
services, California’s new ESPs have struggled to remain competi-
tive. Now, the future of consumer choice is in doubt because the
State has become the main purchaser of wholesale electricity for
the investor-owned utilities, negotiating long-term contracts with
energy generators. The goals of consumer choice may conflict
85
with the State’s goal of returning the investor-owned utilities to
creditworthy status—because expanding competition at this
point might find the State paying for unneeded power.
CONSUMER CHOICE WAS SUPPOSED TO INCREASE
RETAIL COMPETITION AND LOWER ELECTRICAL RATES
In passing Assembly Bill (AB) 1890, which deregulated
California’s electricity markets, the Legislature expected that
increased competition would lower energy prices for the residents
and businesses of California. The CPUC informed the public
about the new choices in electricity providers through a program
The electricity industry
of public information and expected that giving customers a
restructuring was
choice would create competition. This concept of consumer
designed around
choice, called “direct access,” allowed customers of Pacific Gas and
competition—more than
Electric (PG&E), Southern California Edison (SCE), and San Diego
70 percent of California’s
Gas & Electric (SDG&E) to purchase their power from other
consumers could now
sources if they chose to. The more than 70 percent of California
choose where to purchase
consumers who were buying electricity from the investor-owned
their power.
utilities were eligible to make such a switch to an ESP. Through
some of the CPUC’s policies, enacted in AB 1890, the CPUC and
the Legislature designed the electricity industry restructuring
with the expectation that competitive forces—including customers
being free to search for electricity providers other than their
traditional investor-owned utility—would result in lower electricity
rates. Competition was also expected to encourage innovation,
efficiency, and better service from all market participants.
Deregulation statutes required the CPUC, in conjunction with
the investor-owned utilities, to give customers the information
necessary to make appropriate electricity service choices. To this
end, the CPUC devised and implemented a consumer education
program, spending upward of $90 million by May 1998 to inform
customers of the changes that deregulation had brought. The
CPUC was careful not to advocate any particular provider but
simply to emphasize that consumers now had a choice of electricity
companies. The education program also informed the public
about their rights as electricity customers. The CPUC used a call
center, written materials, and television and radio advertisements
to disperse its messages to utility customers.
In promoting competition in the new retail market, the director
of the CPUC’s energy division indicated that the CPUC took a
‘hands off’ approach, believing that giving consumers a choice of
ESPs would in itself create competition at the retail level, without
86
the need for regulatory or government intervention. Moreover,
the director of the energy division stated that the CPUC saw its
role as ensuring that the investor-owned utilities competed fairly
and that it resolved any consumer complaints concerning either the
utilities or ESPs.
NEW ENERGY SERVICE PROVIDERS FACED MANY
CHALLENGES TO REMAIN COMPETITIVE
Competition—the focal point of deregulation—never fully material-
ized. Consumer choice was stunted from the beginning by the
following factors that effectively undermined retail competition
and gave the utilities a distinct advantage over newcomers:
(cid:127) Because their customer base was so small, ESPs were unable to
negotiate lower prices from electricity generators than the
investor-owned utilities paid the power generators in the newly
created wholesale spot market.
(cid:127) A lack of product differentiation made it difficult for ESPs to
establish a niche in the new marketplace.
(cid:127) Residential customers had virtually no incentive to switch
electricity providers, making it difficult for new providers to
attract customers.
As a result of these factors, the number of customers currently
using alternative energy providers remains quite small and the
absence of retail competition has effectively removed what may
have served as a brake on skyrocketing wholesale electricity prices.
Being Unable to Compete With Spot Market Prices, the
Energy Service Providers Had Limited Opportunity to Profit
in the Retail Market
Because they lacked the customer base to negotiate a competitive
price for wholesale purchases of electricity, the ESPs were largely
unable to offer lower retail prices and still make a profit. Yet the
ESPs were supposed to provide competition to the investor-owned
utilities under deregulation. As a result, retail competition and its
associated benefits never fully materialized.
87
As part of deregulation, AB 1890 created the PX,22 an open spot
market where electricity was generally bought and sold no more
than a day before it was needed. The State’s investor-owned
utilities were initially required by the CPUC to sell and purchase
all of their power through the PX on behalf of their customers.
The utilities then passed on the wholesale spot price of the
electricity they purchased—up to the limit provided in their
respective frozen rate structures—in the power generation portion
of the retail bills they sent to their customers. Although the
power transmission and distribution parts of the retail bills were
fixed, the wholesale spot price of electricity tended to fluctuate.
ESPs, along with other wholesale energy buyers and sellers under
deregulation, could participate in the PX spot market, buy
wholesale electricity through other markets, or contract directly
To compete with the with a power generator for the energy they needed. However,
investor-owned utilities, when billing their customers, ESPs were required by AB 1890 to
ESPs had to offer lower levy certain charges, such as transmission and distribution
retail prices for electricity, charges equal to those charged by the investor-owned utilities.
which turned out to be Thus, the amount charged for the electricity used, called the
very difficult. generation charge, was the only part of the retail rate charge the
ESPs could compete on. To effectively compete with the investor-
owned utilities, the ESPs had to offer lower overall retail prices for
electricity, which turned out to be very difficult.
For example, to negotiate lower contract prices than the wholesale
spot price offered in the PX or other spot markets, an ESP would
have to buy in quantities larger than the amounts purchased by
the investor-owned utilities through the PX. Otherwise, the ESP’s
purchase would not be economically worthwhile for the power
generator. Yet none of the ESPs had enough customers whose
aggregate demand for electricity rivaled even the smallest investor-
owned utility. The other choices that ESPs had to secure wholesale
power—other spot markets or the PX spot market—would allow
them only to match the prices the investor-owned utilities were
charging their customers, the ESPs would be unable to better
those prices and certainly would not be able to earn a profit.
Again, the ESPs were unable to gain any competitive pricing
advantage. Because the ESPs were not able to compete in price
with the investor-owned utilities, their rates presented little or no
economic incentive for customers to switch away from the
investor-owned utilities.
22 On January 31, 2001, the PX ceased trading; it filed for bankruptcy shortly thereafter.
88
Energy Service Providers Faced Other Challenges in
Trying to Compete
Although competitive pricing was their major concern, the ESPs
had other challenges in trying to compete in the new deregulated
structure. Because electricity is the same regardless of who
provides it, the ESPs were unable to distinguish what they were
selling from what the investor-owned utilities sold. Also, the
legislation establishing deregulation had no built-in mechanism
for moving customers from the utilities to ESPs. Finally, their
long-term relationship with their utility companies had given
customers a level of comfort that made them unmotivated to
switch providers. These challenges contributed to the failure
of competition to lower retail energy prices in California’s
deregulated market.
One underlying factor that enables true competition was missing—
product differentiation. According to the CPUC’s energy division
director, the one form of product differentiation that did occur
was from providers of renewable energy, who provided “clean”
electricity, made from nonpolluting sources like wind, water, sun,
and geothermal. These ESPs were able to differentiate their product
from that of the utilities based on their sources of energy and
Unable to differentiate were thus able to carve out a niche market for themselves, although
their product from that of some charged higher prices than the utilities. However, unable to
the investor-owned highlight a product difference, most ESPs could not give the
utilities, most ESPs could utilities’ customers a compelling incentive to switch providers.
not give customers a
compelling incentive A lack of legislated incentives for customers to switch electricity
to switch. providers further compounded the challenges facing the ESPs.
The new electricity industry offered no compelling reason why
customers should transfer service from their long-time utility and
enlist with a new provider about whom they knew little or noth-
ing. Moreover, deregulation did not require the investor-owned
utilities to turn over any of their customers to the new providers;
rather, it simply allowed customers of the investor-owned utilities
to choose an alternate energy supplier. In contrast, Pennsylvania,
where retail competition under deregulation has been more
successful than in California, required most of its utilities to
surrender some of their customers, in some cases auctioning off
customers to the retailer that could promise them the most
savings. Close to 1 million customers throughout Pennsylvania
have switched from utilities to other energy suppliers, compared
to a peak of 223,400 California customers using ESPs in
March 2000 (only about 2.2 percent of the 10.1 million customers
served by the three investor-owned utilities at that time). The
89
Legislature’s and the CPUC’s omission of any incentive or reason
for customers to change electricity providers likely failed to
motivate customers to switch to a new energy company.
Yet another barrier to the ESPs’ success in marketing their services
was consumers’ loyalty to their long-term providers. The three
investor-owned utilities had been serving customers in their
respective service areas for many years, so that without a good
reason, most customers were not inclined to make a change just
because they now could. According to the director of CPUC’s
energy division, this “customer culture” is ingrained in most
people, so many customers appeared to be uninterested or apathetic
toward the new industry that existed. It was plainly not worth the
time to these customers to research other companies, compare
prices, and exert the necessary effort to make the change. The
energy division director confirmed that most customers
perceived no incentive strong enough for them to initiate a
change in providers.
After An Initial Increase in Customers Changing Energy
Providers, the Numbers Began to Decline
At the outset of deregulation, customers choosing new ESPs
increased at a steady rate, although the number switching was
immaterial compared to the total number of customers eligible.
As of the end of June 1998, roughly 51,000 residential customers
had chosen a new ESP, just over one-half of 1 percent of the
The number of residential almost 8.7 million residential customers of the investor-owned
customers choosing an ESP utilities at that time. As illustrated in Figure 6, the number of
peaked in March 2000 at residential customers switching to a new ESP slowly but steadily
165,600 but has steadily increased until the spring of 2000. By the end of March 2000, the
declined since that time. number of residential customers who had switched providers had
tripled, reaching a peak of approximately 165,600, or 1.9 percent
of the investor-owned utilities’ residential customers. However,
according to the CPUC’s energy division director, many ESPs have
since gradually lost customers. This is likely due to the volatility
in the wholesale electricity market. If customers of an ESP did not
contract for a fixed electricity rate, they are forced to pay the
prevailing wholesale market rate, which reached unprecedented
levels in the summer of 2000. As a result, many customers may
have chosen to switch back to their investor-owned utility, where
they are protected from volatile spot-market prices by the retail
rate freeze. This effect of the volatile electricity market is evi-
denced by the total number of residential customers served by
90
FIGURE 6
Number of Residential Customers Choosing Alternative Energy Service Providers
June 1998 Through March 2001
200
150
100
50
888888899999999999900000000000011 1
999999999999999999900000000000000 0
999999999999999999900000000000000 0
111111111111111111122222222222222 2
J u ne J u A S ly u e g p u te st m O be c N t r o o b v e e D r m e b c e e r m b Ja e n r u Fe a b ry r uar M y arc h A pril May J u ne J u A S ly u e g p u te st m O be c N t r o o b v e e D r m e b c e e r m b Ja e n r u Fe a b ry r uar M y arc h A pril May J u ne J u A S ly u e g p u te st m O be c N t r o o b v e e D r m e b c e e r m b Ja e n F r u e b ar r y u ary M arc h
Source: CPUC Energy Division—Monthly Direct Access Implementation Activities Reports from June 30, 1998, through
March 31, 2001.
the ESPs as of March 2001—roughly 87,500 residential customers
received their electricity service from providers other than the
investor-owned utilities, a 47 percent drop from the high of only
one year earlier.
In percentage terms, nonresidential customers were initially more
inclined than residential customers to change energy providers.
Between June 1998 and March 2000, the percentage of nonresi-
dential customers using an ESP almost tripled, from roughly
1.7 percent to 4.5 percent, or 58,000 out of a base of 1.3 million
customers. In contrast, residential customers who switched to an
ESP never exceeded 1.9 percent of the residential customer base.
However, Figure 7 indicates that since May 2000 the number of
nonresidential ESP customers has steadily declined. In fact, by
March 2001, ESPs were serving only about half the number of
nonresidential customers they had served in June 1998, at the
beginning of deregulation. As the number of ESPs and their
customer bases continue to shrink, retail competition is fading.
91
)sdnasuohT
ni(
sremotsuC
fo
rebmuN
FIGURE 7
Number of Nonresidential Customers Choosing Alternative Energy Service Providers
June 1998 Through March 2001
Source: CPUC Energy Division—Monthly Direct Access Implementation Activities Reports from June 30, 1998, through
March 31, 2001.
THE FUTURE OF CONSUMER CHOICE IS UNCLEAR
As California’s electricity crisis chiefly focuses on soaring wholesale
electricity prices, both the CPUC’s energy division director and
staff from the Office of Rate Payer Advocates—an independent
body within the CPUC charged with representing the interests of
all public utility customers—agree that if competition among
retailers had flourished, producing the expected number of ESPs
with their respective customer bases, the resulting competition
may have helped hold wholesale prices in check. From an economic
standpoint, the existence of many more direct access customers
would have reduced the number of customers served by the
investor-owned utilities, thereby lowering the utilities’ aggregate
electrical demand. This lowered demand might in turn have
relieved pressure on the spot market and reduced the wholesale
prices of electricity the investor-owned utilities were forced to
pay. Increased competition might also have enhanced the ESPs’
92
)sdnasuohT
ni(
sremotsuC
fo
rebmuN
70
60
50
40
30
20
10
0
888888899999999999900000000000011 1
999999999999999999900000000000000 0
999999999999999999900000000000000 0
111111111111111111122222222222222 2
J u n e J u A S l e u y p g t u e s m t O b N c e t r o o v b e D e m r e c b e e m r J b a e n r F u e a b r y r u a M r y a rc h A pril M a y J u n e J u A S l e u y p g t u e s m t O b N c e t r o o v b e D e m r e c b e e m r J b a e n r F u e a b r y r u a M r y a rc h A pril M a y J u n e J u A S l e u y p g t u e s m t O b N c e t r o o v b e D e m r e c b e e m r J b a e n F r u e b ar r y u ar M y arc h
viability, forcing the utilities to purchase power in a manner that
smoothed out costs and avoided wide fluctuations in order to
retain their respective market shares. The utilities might then
have been more aggressive in hedging risk by entering into more
fixed-rate contracts for future electricity purchases, thereby
reducing their customers’ exposure to wholesale price variations.
In any event, the decreasing number of ESPs and customers
served by them casts considerable doubt on the future of consumer
choice. Perhaps more importantly, however, because the State of
California is currently the primary purchaser of wholesale electricity
for the investor-owned utilities, it is now unclear whether the
objective of consumer choice—increased competition—is
consistent with the State’s aim of returning the utilities to
creditworthy status. In the past few months, the State has
negotiated and continues to negotiate long-term contracts with
energy generators—authority for which was specifically granted
under ABX1 1—to supply enough electricity at the lowest possible
prices to meet the hourly demand beyond what the investor-
owned utilities are capable of generating themselves or are
guaranteed to receive through contracts. Even though these
long-term State contracts are still being written and we have not
reviewed them, we understand that they can cover any time
period, and some have been reported to extend out 20 years.
Presumably, the amount of electricity purchased through these
long-term contracts is reflective of the current aggregate customer
base of the investor-owned utilities. Therefore, if the price freeze
were to be removed and competition were to expand at the retail
level and other energy suppliers not burdened by long-term
commitments could offer lower prices, large numbers of utility
customers might decide to switch suppliers. In such a case,
depending on the terms of the contracts, the State may be paying
for power that it was required to buy but for which there were no
customers. ABX1 1 may mitigate such a situation since it autho-
rizes the CPUC to determine if or when it should suspend the
right of utility customers to acquire electricity services from other
providers. According to a manager in the CPUC’s energy division,
the CPUC has not yet made this determination; thus, customers
still have the right to switch their electricity service from an
investor-owned utility to an ESP. Uncertainties such as these
will undoubtedly continue until the future role of consumer
choice in today’s fluid market environment becomes clear.
93
RECOMMENDATION
In assessing the future role of customer choice, the CPUC should
consider the effects of competition at the retail level to evaluate
whether it is viable in the current market environment, where
the State is the primary purchaser of electricity for the
investor-owned utilities.
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
Date: May 21, 2001
Staff: Doug Cordiner, Audit Principal
Sharon L. Smagala, CPA
Robert Hughes
Joel Riphagen
Ryan Storm
94
APPENDIX
Projected Demand Reductions and
Supply Additions for Summer 2001
and Beyond
T
he State Energy Resources Conservation and Development
Commission (energy commission) and California Public
Utilities Commission (CPUC) have developed, expanded,
and implemented various programs targeted at reducing the
State’s energy demand, some in time for summer 2001. In this
Appendix we summarize the energy commission’s and CPUC’s
various program efforts, their projected megawatt savings, and
the challenges these two commissions face in meeting their
program goals.
In addition to working to reduce demand, the energy commission
is actively siting power plants through a variety of processes
including its standard 12-month process and several expedited
processes, two of which were implemented specifically to address
the State’s immediate supply needs. Similar to its demand reduc-
tion programs, in this Appendix we sum up the total megawatts
of new supply the energy commission has approved or is in the
process of approving and categorize these megawatts by the date
the energy commission projects them to come on-line through
2004. Our summary also includes ‘peaker’ plants the California
Independent System Operator (ISO) has contracted for, but that
may not all come under the energy commission’s jurisdiction.
Finally, our summary of new supply includes the energy
commission’s Renewable Energy Program, through which it
subsidizes renewable energy power plants within California that
rely on such sources as solar, wind, and solid waste technologies
to produce electricity. This program stemmed from the 1996 leg-
islation that deregulated California’s electricity industry and as of
March 2001, 275 new and existing plants providing 4,394 MW of
electricity—enough to power approximately 4.4 million average
households—were participating in the program.
95
TABLE 11
Energy Commission and CPUC Demand Reduction Programs
Estimated in Megawatts as of April 1, 2001
Megawatts saved by After During
June 1 July 1 August 1 Subtotals August 1 2002 2003 2004 Totals
Energy Commission
AB 970 Programs
Commercial building
demand response 107 28 135 135
State buildings
demand response 79 1 80 80
Water-systems
equipment replacement 48 1 49 49
Heat reflective roof surfaces 6 7 10 23 23
Innovative products 39 2 1 42 42
Energy efficient
traffic signal retrofit 2 1 3 6 6
Subtotals 281 39 15 335 – – – – 335
CPUC
AB 970 Programs
Self-generation resources 45* 45 45* 90 90 90 360
Residential and small commercial
building air-conditioning, heating,
and ventilation cycling – 8 8
Subtotals – – 45 45 45 98 90 90 368
Totals 281 39 60 380 45 98 90 90 703
Note: Data reflects the first point in time that the incremental megawatts estimated are available to meet peak demand.
* This program is new and the CPUC expects to achieve 90 MW of participation in its first year. We assumed, based on the
newness of the program, that only half of the megawatts would be available for summer.
ENERGY COMMISSION ESTIMATED
DEMAND REDUCTION
AB 970 Programs
These programs are collectively called the Peak Load Reduction
Program and are intended to reduce peak energy demand during
the high-demand months starting on June 1 and running
through September 30, beginning in June 2001 and repeating in
each of the three subsequent years. The energy commission,
through contracts and grants is assisting program participants to
do such things as develop systems to cut commercial and state
96
buildings’ electricity use during periods of high demand, replace
aging water-systems equipment with more efficient models, and
install heat-reflective roof surfaces and energy efficient traffic
signals.
Although the energy commission estimates that is will achieve
281 MW of demand reduction by June 1, 2001, and ultimately
save 335 MW, these estimates appear too high for the following
reasons:
(cid:127) Even though the commercial building heating and air condi-
tioning responsiveness program is computer based, participants
can override directives to reduce energy use by adjusting
heating and air conditioning levels. The override feature makes
commercial building owners’ and managers’ participation
voluntary and the energy commission has no penalties in place
for noncompliance. In addition, operators may be less willing
to comply with directives to reduce energy use as they receive
more and more such requests. Thus, any savings derived from
this effort will depend on the operators’ responses to potentially
frequent requests to reduce electricity use.
(cid:127) State facility operators are preparing plans on how to respond
to directives to reduce energy use. When directed, personnel
will implement these plans manually by taking such steps as
adjusting heating and air conditioning levels and turning off
lights and other non-essential equipment. In summer 2000,
the ISO observed a measurable reduction in demand during a
test of several state agencies that participated in a similar effort.
However, despite that test and the fact that state facility operators
have more of an incentive to comply with demand reduction
directives because they are answerable to state policy makers, the
manual nature of this program makes its level of demand reduc-
tion subject to human error and building operator preference.
(cid:127) The energy commission has engaged in limited monitoring
and has not thus far evaluated the level of participation in the
water-systems equipment replacement program against set
milestones such as equipment order and delivery dates and
project installation and test dates. Without performing such
activities, the energy commission reduces its chances of
achieving its peak energy reduction goals; the third largest
in its Peak Load Reduction Program.
97
Commercial and Residential Building Standards and
Appliance Standards
The energy commission updated its building standards in
January 2001 and plans to complete its update of appliance
standards in May 2001. These standards dictate the energy
efficiency levels to be met in constructing buildings and for
certain new appliance use in the State and will go into effect
beginning June 2001 and thereafter. Because any new building
construction and increased appliance use puts an added strain on
the State’s power grid and because these standards are designed
simply to slow the demand for electricity rather than reduce
existing levels, these programs are not reflected in Table 11.
Nonetheless, once they go into effect, the energy commission
estimates that buildings constructed using these revised
standards will be 12 percent more efficient; the peak energy
demand associated with one year’s worth of construction will be
162 MW to 275 MW less than buildings constructed using the
previous standards. Similarly, appliances that meet the revised
energy standards and that are placed in use over one year’s time
will require 40 MW less peak energy. The energy savings
provided by both of these standards will most likely occur in
2002 and into the future.
CPUC ESTIMATED DEMAND REDUCTION
AB 970 Programs
The CPUC is implementing AB 970 to reduce peak energy demand
in several ways. The self-generation program is designed to shift
peak energy demand away from the power grid and toward new
technologies that participants install such as solar panels, fuel
cells, and certain nondiesel engines. The CPUC estimates that the
amount of peak energy savings from this program will grow over
four years culminating in 360 MW of savings in its last year.
However, because the CPUC’s plans for the self-generation
program are unstructured and allow participants to choose their
own form of technology from certain approved technology types,
energy savings ultimately derived from this program will depend
upon the mix of technologies participants choose to install. For
example, the energy savings could range from 22 MW to 100 MW
per year depending upon whether participants were to choose all
solar or all engine-driven technologies.
98
The CPUC’s second program, demand control, is meant to affect
heating, ventilation, and air-conditioning thermostats in residential
and small commercial buildings using Internet-based technology.
However, these participants will have the ability to override the
signal to adjust their thermostats, therefore, any energy savings
may be partially or wholly negated.
Interruptible Program
This program gives participants reduced electric rates in exchange
for agreeing to curtail their electrical use if called upon for no
more than a certain number of hours per year. As of summer
2000, the three investor-owned utilities had about 2,340 MW of
curtailable power under contract. However, after repeated calls to
curtail their power, participants began dropping out of the program
or simply stopped complying with curtailment requests. Moreover,
because of tight energy supplies in January 2001, frequent calls
for curtailment over one month’s time have nearly exhausted the
yearly requirement for participants of two of the investor-owned
utilities’ programs. Because of the uncertainty surrounding
compliance levels and the small amount of program capacity
remaining, Table 11 does not reflect the megawatts of curtailable
demand this program may provide in 2001. Furthermore, we do
not show the curtailable megawatts in subsequent years either
because the program has recently undergone significant change
and information regarding future participation was unavailable.
In April 2001 the CPUC released a decision containing program
revisions meant to maintain the program’s viability through
summer 2001. The revisions the CPUC made included providing
choices for opting out of the program or changing the amount of
energy to be curtailed, setting new restrictions on the number
and length of power interruptions, and better defining participant
eligibility criteria. Although the changes the CPUC made appear
reasonable, until participants are called upon under the new
requirements it will not be certain whether these program revi-
sions will adequately enhance the program’s role in curtailing
energy demand and acting as a buffer against rolling blackouts.
Also, in its April 2001 decision the CPUC approved several addi-
tional curtailment-type programs. Among these programs are the:
(cid:127) Base Interruptible Program another version of the interruptible
program, gives customers rate discounts for agreeing to curtail
their power use up to 120 hours per year. Participants may be
99
TABLE 12
Energy Commission Estimated Supply Additions
As of April 1, 2001 (in Megawatts)
Megawatts Available in After During
June July August Subtotals August 2002 2003 2004 Totals
Energy Commission
Application Review Processes
12-month siting process—
approved for construction 1,059 320 1,379 262 3,782 2,990 8,413
12-month siting process—
applications submitted but
not yet approved – 2,680 2,390 5,070
AB 970—6-month siting
process—approved for
construction – 0
AB 970—6-month process—
applications submitted but
not yet approved – 570 250 820
AB 970—4-month siting process
for ‘peaker’ plants—approved
for construction 51 51 51
AB 970—4-month siting process
for ‘peaker’ plants—submitted
but not yet approved – 0
21-day emergency siting process
for ‘peaker’ plants—approved for
construction – 0
21-day emergency siting process for
‘peaker’ plants—submitted but
not yet approved* 207 207 207
ISO contracted ‘peaker’ plants† 74 176 400 650 675 1,325
Small power plant exemption—
submitted but not yet approved – 99 99
2-month repowers—submitted
but not yet approved 450 450 450
Subtotals 74 1,685 978 2,737 937 3,782 6,339 2,640 16,435
AB 1890 Programs
Renewable energy—resource
development phase 1 111 90 201 241 51 50 543
Renewable energy—resource
development phase 2 28 32 60 341 70 471
Subtotals 139 122 – 261 582 121 50 – 1,014
Totals 213 1,807 978 2,998 1,519 3,903 6,389 2,640 17,449
Note: Data reflects the first point in time that the incremental megawatts estimated are available to meet peak demand.
* Estimated by the energy commission as of April 23, 2001.
† Estimated by the ISO as of April 6, 2001. These estimates include plants under the energy commission’s or local agencies’
review. These figures also include peaker plants the ISO is expecting on-line but for which an application has not yet been
filed with the appropriate agency.
100
sessecorP
gnitiS
detidepxE
new or customers who have already fulfilled their contractual
obligations under the original interruptible program.
• Voluntary Demand Response Program, which allows customers
to voluntarily reduce demand on any given day once they are
notified by a utility. The participants will receive a cash payment
of 35 cents per kilowatt hour of reduction provided.
In its decision, the CPUC did not estimate the megawatt
curtailment these programs would produce; therefore, these new
programs are not reflected in Table 11. And because of their
relative newness, their effectiveness in reducing peak demand
will not be known until this summer.
ENERGY COMMISSION ESTIMATED SUPPLY ADDITIONS
Power Plant Siting Processes
It is well known that the supply of electricity within California is
insufficient to meet the State’s current demand. Efficient siting
of new power plants is vital to the State’s ability to deliver reliable
power over the long-term. According to the energy commission’s
April 2001 estimates for power plants it has either already approved
for construction or is still in the process of reviewing more than
2,000 MW of additional electrical capacity to meet the State’s
energy needs by the end of August. When added to the 261 MW
of new supply that the energy commission is projecting will be
provided by new power plants as a result of its Renewable Energy
Program and those peaker plants the ISO has contracted for, the
total new capacity estimated to be available by the end of August
rises to just under 3,000 MW. However, the energy commission’s
estimates for the delivery of much of this supply is contingent on
power plant construction schedules over which it has no control.
What follows is a description of the various processes the energy
commission is using to add to the State’s energy supply and the
challenges it faces.
(cid:127) Notwithstanding construction delays, beginning in July 2001,
the State will begin to benefit from the electricity generated by
the numerous power plants currently approved for construction
under the energy commission’s 12-month process. As shown
in Table 12, between now and 2004, 8,413 MW are scheduled
to be brought on-line, with the largest number of megawatts
scheduled to come on-line during 2002.
101
(cid:127) The energy commission’s 12-month siting process, the process
under which many power plants are sited, is averaging longer
than the 12-month goal contained in statute. The energy
commission took an average of 17 months to approve eight of
twelve power plant applications it reviewed between
January 1, 1997, and December 31, 2000. Although the delays
in siting new plants did not cause California’s electricity
shortage, they have contributed to the lack of some new power
plants coming on-line before the summer months of 2001.
Because the process of approving or rejecting applications to
site power plants often takes over a year, those power plants
comprising 5,070 MW that are under review but not yet
approved may slip beyond the energy commission’s current
projected 2003 and 2004 dates for when the plants will
come on-line.
Moreover, the energy commission has recently started using
three expedited siting processes of varying lengths, but they will
have little effect on the State’s summer 2001 electricity supply.
(cid:127) As reflected in Table 12, the 6-month siting process is not
estimated to yield any megawatts until 2003. Assuming the
energy commission approves all the applications to site power
plants that it has received within its 6-month timeline and
construction schedules for these plants do not slip, the State
will have an additional 820 MW of electrical supply by the end
of 2004.
(cid:127) The 4-month siting process mandated by AB 970 was initially
created specifically to site ‘peaker’ power plants that could be
on-line by August 1, 2001. The energy commission received
seven applications under this process but six were withdrawn.
The siting process on the remaining plant is complete and as of
April 2001 it was estimated to provide 51 MW of new electrical
supply by August 2001. The governor extended the deadline to
apply using this process until December 31, 2001, for plants
that can be on-line by August 31, 2002, but as of April 1, 2001,
the energy commission had not received any additional appli-
cations for its review under this process.
(cid:127) As of April 23, 2001 the energy commission was estimating
that its 21-day emergency siting process for peaker power
plants would bring 207 MW of new supply on-line in
August 2001. However, the megawatts added by this process
102
are falling short of the original intent which, according to the
governor’s Web site, was to bring 1,000 MW of capacity on-line
by July 2001.
In August 2000 the ISO solicited bids for peaker power plants
hoping to secure 3,000 MW of power for summer 2001. As of
April 6, 2001 it has only been able to contract for 1,325 MW—
less than half the original goal. Moreover, the ISO estimates only
250 MW will be available in July 2001. The energy commission
as well as other local agencies are responsible for reviewing these
applications (the energy commission will review applications for
peaker plants of 50 MW or larger). The ISO’s estimates assume
that the energy commission and other reviewing agencies can
review and approve the ISO’s contracted sites promptly, and that
the developers of these plants can bring them on-line by the
dates scheduled.
Table 12 also reflects two other processes through which the
energy commission is reviewing applications for additional short-
term and longer-term electrical supply that include:
(cid:127) The Small Power Plant Exemption (SPPE) process–the energy
commission uses this process to site plants between 50 MW
and 100 MW that meet certain other requirements. According
to the energy commission, siting under the SPPE can take 6 to
8 months not including the time other state and local agencies
may need to provide relevant approvals. Thus, the 99 MW
projected to come on-line in 2003 assumes that no delays
occur in the energy commission’s siting process, other agencies’
approval processes, or in the plant’s construction schedule.
(cid:127) Repowering Project process–this process is for existing power
plants that are not currently operating which, with relatively
minor refurbishing, can be reactivated and brought back on-line.
The energy commission, in response to the State’s energy
crisis, is attempting to review applications to repower plants
within 60 days. On February 7, 2001 the energy commission
began reviewing a repower application for a 450 MW plant; but
as of April 2001 its review was still not complete. Assuming
that the energy commission completes its review soon and the
power plant owner completes any necessary refurbishment,
this plant is expected to be on-line in July 2001.
103
AB 1890 Renewable Energy Program
The 1996 legislation that deregulated the State’s electricity
industry also required the energy commission to preserve the
State’s commitment to developing diverse, environmentally
sensitive electricity resources as California made the transition to
a competitive electricity market. In response, the energy commis-
sion developed the Renewable Energy Program, which uses funds
collected from customers of the investor-owned utilities to
subsidize power plants within California that rely on renewable
resources such as solar, wind, and solid waste. In June 1998 and
again in December 2000, the energy commission held auctions
and agreed to subsidize developers once they put into production
power plants totaling 552 MW (9 MW from the first auction was
subsequently canceled leaving 543 MW) and 471 MW respec-
tively. Although the energy commission expects the first
139 MW of renewable energy from these two auctions to be on-line
by June 1, 2001, its estimate reflects that the majority of new
supply coming from renewable power plants will not be available
until late 2001 and 2002.
Originally, the energy commission expected that all of the 543 MW
in its first auction would be on-line by January 1, 2002, however,
several of the projects have been delayed. According to the
energy commission, reasons for the delays include:
(cid:127) Developers being unable to secure purchase agreements from
the investor-owned utilities in order to obtain construction
financing.
(cid:127) Public opposition over the environmental effects constructing
these new plants might cause.
It is possible that these types of difficulties may contribute to
similar project delays for the 471 MW the energy commission
secured during its most recent auction, which is all anticipated to
be on-line by 2002.
104
Agency’s comments provided as text only.
California Energy Commission
Steve Larson, Executive Director
1516 Ninth Street
Sacramento, California 95814-5512
May 14, 2001
Ms. Elaine M. Howle*
State Auditor
California State Auditor
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Dear Ms. Howle:
Thank you for the opportunity to comment on your recent audit report addressing California's
energy programs and siting processes. We greatly appreciate the professionalism of your audit
team. California is facing significant challenges. As a result, the Governor, Legislature and State
agencies are working to increase electricity generation and reduce peak use. We have the
following comments on your review of these efforts.
Power Plant Licensing
Although they had a relatively short amount of time to investigate a very complex topic, the audit
team developed an understanding of many aspects of electricity restructuring in California and
the Energy Commission's power plant licensing program. We would like to express our compli-
ments to the audit team for their openness, objectivity, and professional manner of dealing with
these issues.
"Results in Brief"
Page 3, Paragraph 1, Sentence 3 **- As the report indicates, during the 1990s, few power plants
were proposed in California and the rest of the nation. This was primarily because of uncertainty
regarding restructuring. We would like to note that one of the primary contributions to California's
energy crisis is the withholding of critical power supplies by the electrical generators. Current
"forced" outages are two to four times higher than have been historically experienced. Needed
electricity from generation facilities currently on the ground within California is not available
resulting not only in higher electricity prices that benefit the owners of those same generation
facilities but the prospect of rolling blackouts.
Page 3, Paragraph 1 and 2 - The Energy Commission's evaluation of supply and demand this
summer reflected expected historical outage rates. Given the amount of existing generation
capacity in-state, the number of new facilities that are expected to come on-line, and other
programs such as conservation and efficiency grants/loans, from a numerical perspective there is
sufficient generating capacity to meet peak demand this summer. However, for economic and
perhaps other reasons, not all of this generation capacity may be available to
*California State Auditor’s comments appear on page 111.
**The page numbers refer to an earlier draft report.
105
Ms. Elaine M. Howle
May 14, 2001
Page 2
California consumers. The higher-than-expected "forced" outage rates demonstrate that genera-
tion capacity is in place but not always available.
Page 4 and 5 - The Energy Commission's licensing process is expected by law to meet several
objectives. On occasion, attaining some objectives - ensuring legally sustainable decisions,
ensuring adequate public participation, accommodating project changes requested by the appli-
cant, ensuring coordination of all agencies, or making the findings required by an override - may
result in extending the schedule of a project. The Energy Commission works to balance consider-
ation of all issues and protect the interests of all parties in each case within the identified
timeframe.
Page 5, Paragraph 1, Last Sentence - To update the progress on bringing additional generation
on-line for the Summer of 2001, as of May 11, 2001, the Energy Commission has approved six
projects using the Emergency Siting process for a total of 450 megawatts (MW). All of these
projects are in construction. Four more projects are currently in review under that process for
420 MW and eight more are preparing applications for an additional 600 MW of capacity. The
other two processes referred to in the report are currently expected to allow in excess of 1,000
MW of additional generation to come on-line by next summer.
"Introduction"
Page 12, Paragraph 1, Sentence 1 - We recommend noting that the Governor's declaration of an
energy emergency allowed the Energy Commission to use its emergency permitting authority to
permit projects that are exempt from CEQA.
"Chapter 1"
Pages 19 - 21 - As discussed in our comments in the section entitled, "Results in Brief," the
amount of installed generation that is off-line because of "forced" outages greatly exceeds
historical levels. In its estimates, the Energy Commission did not anticipate that level of existing
generation would be unavailable in its evaluation of supply and demand.
"Chapter 3"
Pages 47 and 48 - As mentioned in our comments above, the Energy Commission seeks to
accomplish multiple objectives in the licensing process as defined by the Warren-Alquist Act,
California Environmental Quality Act, and other statutes. In addition to issuing decisions within
the established time-frame, these objectives include:
106
Ms. Elaine M. Howle
May 14, 2001
Page 3
(cid:127) producing legally sustainable decisions
(cid:127) basing decisions on an objective evaluation of the facts and consideration of all information
(cid:127) appropriately balancing competing interests and needs
(cid:127) integrating the comments and recommendation of all applicable local, State and federal
agencies
(cid:127) ensuring public participation throughout the decision-making process
(cid:127) protecting public health, safety, and environmental quality
(cid:127) being fair and consistent for all projects
(cid:127) providing regulatory certainty
Based on the unique circumstances of each project, achieving all of these objectives may require
an extension of the 12-month timing objective. Information on the unique aspects of each project
are available.
As of May 11, 2001, the Energy Commission has now approved 14 major power plants (plants
over 300 MW) since 1996. The most recent project was permitted in about 90 days under the
Governor's Executive Orders. If this project were included, the average time for permitting those
plants would be a few days less than one year. Without this project, the average permitting time
is about 15 months. One project, High Desert, took two years and five months because of
significant changes in the project description and issues in the case which were subsequently
challenged unsuccessfully in court.
Page 62, Paragraph 1, First Sentence - As an update to the information in the report, the seventh
application was approved by the Energy Commission in March 2001, but is not expected to go to
construction due to lease and contract difficulties between the applicant and the City and County
of San Francisco.
In addition to these projects, AB 970 allowed the project under review to be modified from a
combined cycle to a simple cycle configuration and approved by the Energy Commission in four
months. The applicant of the Sunrise project made this modification. The change was approved
by the Energy Commission in less than four months and the project will bring 320 MW on-line this
summer.
Peak Load Reduction Programs
The title of Chapter 1, "Plans to Reduce Energy Demand by Summer 2001 Overestimate Poten-
tial Peak Energy Savings," may lead readers to a different conclusion than can be drawn from the
analysis in the report. The analysis concludes that the savings "may not come true" and that
projections are "difficult to predict because they haven't been tried before." The Energy Commission
107
Ms. Elaine M. Howle
May 14, 2001
Page 4
agrees that the peak load savings are difficult to accurately forecast. As a result, the Energy
Commission has used conservative estimates of the savings. The evidence of the savings to date
should reassure the Legislature that the Energy Commission's estimates understate the energy
savings that will be achieved.
For example, on page 23 the report states that "it seems unlikely that a public outreach program"
will be able to save the 2,000 MW the Energy Commission forecasts. The report reaches this
conclusion based on the ISO experience of 1,300 MW of demand reduction occurred during
1
January Stage 3 alerts and rolling blackouts. The 1,300 MW represents the firm electricity load
that was shed by the ISO to ensure system reliability. It does not estimate the amount of demand
reduction Californians have taken in reaction to the energy crisis and higher prices.
To estimate actual demand reduction, the Energy Commission conducted an analysis comparing
the Year 2000 demand to 2001. The analysis shows demand is significantly lower this year than
last year. This demand reduction of over 2,500 megawatts has occurred without the proposed
new media campaigns, peak load reduction program, much higher electricity prices or the
Governor's 20/20 program. If Californians conserve only at the same rate this summer as they
have in March and April (9 percent), the reduction will be 4,500 megawatts. While it is uncertain
how much peak reduction will occur this summer, the 2,000 megawatts estimate seems conser-
vative.
Demand Responsive HVAC
The report suggests that the Energy Commission may be overestimating the demand reduction
from the Demand Responsive HVAC program. The Report's reasoning is that the program
participants voluntarily choose to react to a signal from the ISO or during high demand periods.
The report states that: "it may be unrealistic to think that commercial buildings will voluntarily turn
up thermostats."
The Energy Commission chose a voluntary curtailment program that provides customers with
information on market conditions and the available payment for performance because they are
much more likely to deliver MW savings. Mandatory programs in the past have triggered cus-
tomer resentment and dramatically reduced the potential number of customers willing to partici-
pate. One example is the extreme dropout rate currently being experienced in the SCE interrupt-
ible curtailable program.
2
The report correctly observes that the Energy Commission will not penalize participants if they
override a load curtailment signal but omits the vital fact that participants will be penalized for
108
Ms. Elaine M. Howle
May 14, 2001
Page 5
failure to respond to the signal and reduce peak load. For example, in the ISO Demand Reduc-
tion program there is a significant cash penalty for failure to provide the contracted for load
reductions. In addition, the Energy Commission's installation contractors have strong financial
3
incentives to ensure that participating customers respond to these signals. This is because up to
40 percent of each contractor's total contract payments will be withheld if these customers do not
provide the contracted for system wide load reductions as measured in the pilot test. Thus, if the
participants fail to comply with load reduction signals this summer, there will be a significant
penalty to them and the installation contractors. This fact will substantially reduce the
amount of potential of non-compliance.
Water/Wastewater Program
The report looked at the Water/Wastewater Program and observed that they would have ex-
pected the Energy Commission to be actively evaluating itself and program participants against
set milestones such as:
1.Setting a goal of securing a certain number of participants by set dates that represent the
MW reduction to be reached and tracking progress toward the goal.
2.Verifying that equipment is ordered and delivered by set dates.
3.Ensuring that projects are installed, completed and tested by set dates.
The Energy Commission is tracking the commitments by set dates and is presenting that data on
a frequent basis. However, the report accurately observes that the program managers' tracking
of equipment and installations could be more systematic. The report observed that the Water/
Wastewater Program Manager said, that because of limited resources, the evaluation against the
milestones suggested above did not occur.
The Energy Commission established the Water/Wastewater program to encourage a wide variety
of projects on a first-come first-served basis and was not organized as suggested in the report. It
could have been operated in the suggested manner and future programs will consider doing so.
However, the Energy Commission has recently received $367 million of new peak load reduction
programs but has not yet received any new staff to implement the programs. Given current
resource constraints, there are no plans to visit every site. Verification will rely on telephone calls
around June 1 to determine if the equipment had been installed. In addition, the Energy Com-
mission requires monthly progress reports on the status of the projects.
109
Ms. Elaine M. Howle
May 14, 2001
Page 6
The Report's suggestion to track items 2 and 3 is an excellent recommendation and represents a
more intensive and formal effort to evaluate progress against milestones. The Energy Commis-
sion shall consider developing procedures to obtain more detailed milestone information such as
described above if resources permit.
Sincerely,
(Signed by: Steve Larson)
STEVE LARSON
Executive Director
110
COMMENTS
California State Auditor’s Comments
on the Response From the State
Energy Resources Conservation and
Development Commission
T
o provide clarity and perspective, we are commenting on
the State Energy Resources Conservation and Devel-
opment Commission’s (energy commission) response to our
audit report. The number corresponds to the number we have
placed in the response.
1
The energy commission is incorrect. According to the Legislative
Analyst’s Office, the 1,300 megawatts represents the average
reduction in demand for energy that the California Independent
System Operator (ISO) observed during stage 3 alerts and black-
outs in January 2001; it does not represent actions taken by the
ISO to curtail energy use to ensure system reliability.
2
The energy commission’s reference to both the ISO’s demand
reduction program and its own program confuses the issue. The
energy commission suggests that there is a penalty for failure to
respond to the signal to reduce peak demand in the ISO program.
However, there is no requirement that participants of the energy
commission’s peak demand reduction program for commercial
buildings also participate in the ISO demand reduction program.
Moreover, as the energy commission does not track the number
of its participants that may also be participating in the ISO’s
demand reduction program, it does not know the number that
would be penalized by the ISO should they override demand
reduction signals.
3
The energy commission missed the point. As we indicate on
page 22 of the report, our concern is that program participants
will not voluntarily comply to reach peak demand reduction
goals; we do not discuss the contractors the energy commission
uses for its program.
111
Blank page inserted for reproduction purposes only.
112
Agency’s comments provided as text only.
Public Utilities Commission
State of California
Loretta Lynch, President
505 Van Ness Avenue
San Francisco, California 94102
May 11, 2001
Elaine M. Howle*
State Auditor
555 Capitol Mall
Suite 300
Sacramento, CA 95814
Dear Ms. Howle,
Thank you for giving the CPUC this opportunity to comment on the State Auditor’s Draft
report on the state’s oversight of California’s energy markets. Our state’s energy crisis
evolves from a mistaken view that unregulated electricity markets could provide the state
with lower cost, reliable and environmentally sound power supplies without the active
oversight of state agencies. Consistent with that view, the previous administration pared
back the state’s regulatory infrastructure in ways that have hampered the state’s response
to the current crisis.
As addressed below the current Commission has embarked on a number of efforts to
revitalize the state’s energy efficiency programs, transmission planning and siting efforts,
and programs that interrupt large customers to improve reliability. In each case, we are
improving the regulatory process and programs, often in ways that are consistent with the
report’s recommendations.
Energy Efficiency Programs
The investor-owned utilities do not have a stellar record in managing energy efficiency
programs to optimize use of ratepayer funds. The fundamental problem is that the utilities
are in the business of providing energy, and they profit from increased sales of electricity
and natural gas. Even though the Commission has historically instituted programs to
offset the incentives that utilities have to sell more product, it is clear that other entities
may make better administrators of these programs due to the inherently conflicted nature
of the utility. For that reason, the Commission has initiated programs whereby non-utility
organizations may administer various energy efficiency programs.
*California State Auditor’s comments appear on page 117.
113
However, in the current crisis, the Commission had little choice but to rely on existing utility
programs, which are already up and running. Given the need for immediate results, the Commis-
sion could not rely on new, unproven administration of all programs. The Commission is explor-
ing the use of non-utility administration for future programs.
In approving the utility programs for 2001, the Commission gave the utilities’ considerable flexibil-
ity to allocate funds to maximize energy savings. The Commission did not want to constrain the
utilities’ ability to redeploy program funds as need to respond to consumer demand for the
programs.
Finally, the auditor’s recommendation that the Commission maximize energy savings by prioritiz-
1
ing measures for customers that produce the most energy savings raises equity concerns. At
present, the Commission requires the utilities to allocate funds collected from each customer
class (e.g. residential, commercial, and industrial) back to that customer class. If the Commission
implements the auditor’s recommendation, residential ratepayers will be required to subsidize
energy efficiency programs for large commercial and industrial customers. In addition, SB X1 5
2
specifically directed that funds be allocated to low-income customers to allow such customers to
participate. The audit reports conclusions to emphasize only the programs with the largest
savings would negate this effort to more equitably allocate funds, and include all customers in the
program efforts.
AB970 Demand Response Programs
The Commission’s AB970 programs were developed to minimize overlap with the California
Energy Commission’s programs and to maximize customer participation in the program. Consis-
tent with the statutory mandates of AB970 regarding the specific types of programs and policy
objectives, the Commission developed a tiered approach, allocating the funds among renewable,
clean fossil generation, and traditional fossil generation.
The audit report recommends that the Commission eliminate funding for the $3 million for a new
3
utility administered website. However, in allocating $3 million for a statewide website, the Com-
mission intended to make it easier for utility customers to find information in one location, rather
than having to go to various different utility and agency sites to find the information.
Transmission Siting
The state needs the CPUC to be the primary agency responsible for transmission planning and
siting. Transmission provides major public benefits and will require major investments funded
ultimately by the people of California. AB 1890 established a reliability-centered planning process
at the Independent System Operator, independent from the Commission’s broader review of
applications for Certificates of Public Convenience and Necessity (CPCNs).
114
The ISO’s process concentrates on technical studies aimed at satisfying reliability criteria, without
consideration of environmental and siting impacts, or the extent to which lines will reduce electric-
ity acquisition costs or produce other economic benefits. Because the Commission’s CPCN
process also considers public comments, environmental studies, and economic scenarios, the
Commission may pick a very different set of transmission alternatives. This process is obviously
prone to duplication and cannot respond ideally when needs are urgent, as in the current crisis.
Unlike the ISO, which is governed by a board of directors who are legally bound to protect the
interests of that agency, the Commission is a public body fully accountable to the legislature and
the governor, with the experience and the legal authority to conduct environmental reviews. PUC
already regulates and is familiar with the IOUs who own the bulk of the state’s transmission
network, and is best situated to compare the costs and benefits of new transmission and the
effect on rates consumers will pay. Finally, the CPUC already regulates the distribution network
and can assure that the system as a whole is developed in a coordinated fashion.
Legislation is needed to authorize the Commission expedite the siting of transmission lines.
The auditor’s report noted that the CEC’s expedited siting process has proven to be effective, and
that the CPUC often runs into delays in siting transmission projects because of sluggish re-
sponses by other agencies involved in the CEQA process. The commission recommends that the
expediting legislation include the following components:
(cid:127) The authority to impose deadlines on studies by other state agencies,
(cid:127) The ability to override local authorities (and possibly other state agencies) where necessary to
establish needed transmission facilities, and
(cid:127) Authority to resolve environmental issues, independent of current CEQA requirements where
necessary.
Interruptible programs
The concerns expressed by the State Auditor in this section mirror similar concerns of the Com-
mission that prompted it to institute a rulemaking to comprehensively review the interruptible
programs of each utility (R.00-10-002 issued in October 2000). A significant portion of the
findings and analysis contained in the Auditor’s Report are based on the results of the
Commission’s Energy Division’s own report (February 2001) on the operation of these programs.
As a result of this report, the Commission (through D.01-04-006) significantly revised the existing
interruptible programs, as well as developing new programs. The Auditor’s report concludes “the
changes appear reasonable” but cautions that their actual success will not be known “until the
Summer of 2001 or later.” While it is true that the actual success or failure will not be immediately
115
known, it should be noted that the changes were largely developed based upon a consensus
proposal that reflected the input of a large number of parties.
We will continue to work with the California Legislature and the State Auditor to resolve the crisis
that has threatened the health and welfare of the state’s economy and every one of its citizens.
Thank you for your consideration.
Sincerely,
(Signed by: Robert Kinosian)
Loretta M. Lynch
President
116
COMMENTS
California State Auditor’s Comments
on the Response From the California
Public Utilities Commission
T
o provide clarity and perspective, we are commenting on
the California Public Utilities Commission’s (CPUC) response
to our audit report. The number corresponds to the
number we have placed in the response.
1
As we state on page 41 of the report, we are not recommending
that residential ratepayers subsidize efficiency programs aimed at
large commercial and industrial customers. Rather, we recom-
mend that the CPUC look for opportunities that will produce the
greatest energy savings. In doing so, the CPUC need not use
funds collected from residential and small commercial classes, it
can use the funds the utilities already collect from their large
commercial and industrial ratepayers.
2
The CPUC is misleading in bringing up a discussion of SB X1 5 at
this point. SB X1 5 is a new program, which specifically directs
that money provided from the State’s General Fund be used for
energy efficiency programs that benefit low-income households,
among others. Thus, it has no bearing on the use of ratepayer
funds for energy efficiency and conservation programs, which are
the energy efficiency programs discussed in the report.
3
As stated on pages 37 and 38 of our report, we believe the
$3 million annual cost for the Web site the CPUC directed PG&E
to create is a poor use of ratepayer funds. Much of the informa-
tion that will be found on the proposed Web site duplicates
information already residing on either PG&E’s existing Web site
or the sites of other public and private entities. It seems reasonable
that the information the CPUC wants made available to the
public via PG&E’s Web site could be accessed through links from
PG&E’s existing Web site to other Web sites at significantly less
cost to ratepayers.
117
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California State
Government Organization and Economy
Department of Finance
Attorney General
State Controller
State Treasurer
Legislative Analyst
Senate Office of Research
California Research Bureau
Capitol Press