Department of
Transportation:
Its Seismic Retrofit Expenditures Generally
Comply With the Bond Act, and It Has
Begun to Reimburse the Interim Funding for
Fiscal Years 1994–95 and 1995–96
December 2001
2001-010
rotiduA
etatS
ainrofilaC
S
T
I
D
U
A
E
T
A
T
S
F
O
U
A
E
R
U
B
The first five copies of each California State Auditor report are free.
Additional copies are $3 each, payable by check or money order.
You can obtain reports by contacting the Bureau of State Audits
at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
The California State Auditor is pleased to announce
the availability of an online subscription service.
For information on how to subscribe,
please visit our Web site at www.bsa.ca.gov/bsa.
If you need additional information, please contact
David Madrigal at (916) 445-0255, ext. 201.
Alternate format reports available upon request.
Permission is granted to reproduce reports.
C S A
ALIFORNIA TATE UDITOR
ELAINE M. HOWLE STEVEN M. HENDRICKSON
STATE AUDITOR CHIEF DEPUTY STATE AUDITOR
December 18, 2001 2001-010
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As required by Chapter 310, Statutes of 1995, the Bureau of State Audits presents its audit report
concerning the Department of Transportation’s (department) revenues and expenditures
authorized by the Seismic Retrofit Bond Act of 1996 (Bond Act).
This report concludes that the department, in general, has ensured that seismic retrofit projects
funded with bond proceeds are consistent with the purpose of the Bond Act. In addition, the department
has begun to reimburse the State Highway Account (highway account) and the
Consolidated Toll Bridge Fund (toll bridge fund) for expenditures incurred during fiscal years
1994–95 and 1995–96 as required by the Bond Act. As of June 30, 2001, the department has
reimbursed the highway account $26.3 million and, according to the department, it intends to
complete the reimbursement process for the highway account and the toll bridge fund before the
Bond Act expires in 2005.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
BUREAU OF STATE AUDITS
555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019 www.bsa.ca.gov/bsa
CONTENTS
Summary 1
Introduction 3
Audit Results
The Department Has Continued to Make
Progress Toward Completing Its Seismic
Retrofit Projects 7
The Department Inappropriately Charged
Some Expenditures to Seismic Retrofit Projects 7
The Department Has Begun to Reimburse
Early Seismic Retrofit Expenditures 8
Recommendation 9
Appendix A
Bond Act Issuances as of June 30, 2001 11
Appendix B
Status of the Seismic Retrofit Program 13
Appendix C
Bond Act Expenditures as of June 30, 2001 15
Appendix D
Bond Act Reimbursements as of June 30, 2001 17
Response to the Audit
Business, Transportation and Housing Agency,
Department of Transportation 19
SUMMARY
I
n March 1996 California voters approved the Seismic Retro-
fit Bond Act (Bond Act), which authorized the State to sell
$2 billion in general obligation bonds to reconstruct,
replace, or retrofit state-owned highways and bridges. Legisla-
tion passed in 1995 requires the Bureau of State Audits to ensure
that projects funded by the Bond Act are consistent with that
measure’s purposes. This is the sixth in a series of annual reports
on the Department of Transportation’s (department) revenues
and expenditures authorized by the Bond Act.
Overall, the department has moved forward toward its goal of
retrofitting more than 1,150 state-owned highway bridges and
7 state-owned toll bridges. As of June 30, 2001, the department
had spent $1.49 billion for retrofit projects and had completed
work on 98.1 percent of the highway bridges. It had also
finished retrofitting 2 of the 7 toll bridges, while the other
5 bridges were either in retrofit design or under construction.
In general, the department has done a good job of ensuring that
its seismic retrofit projects meet the criteria for funding outlined
by the Bond Act. However, we did find two instances in which
the department charged expenditures to the Bond Act that
were not eligible for such funding. In both instances, depart-
ment staff stated that they were unaware of the department’s
policies requiring the allocation of certain types of facility costs.
As a result, the staff inappropriately charged approximately
$6,800 for a lease payment and a repair bill entirely to seismic
projects rather than allocating the amount among seismic and
nonseismic projects that benefited from the expenditure.
The department has also begun to reimburse other accounts
for interim funding obtained during fiscal years 1994–95 and
1995–96. During those years, the State Highway Account
(highway account) and the Consolidated Toll Bridge Fund
(toll bridge fund) provided a total of $114 million for the
retrofitting of California’s bridges. Although the Bond Act
requires that the department use bond proceeds to reimburse these
expenditures, the State Treasurer’s Office objected to reimbursing
these funds directly because it believes such an action could
jeopardize the bonds’ tax-exempt status. To avoid this problem,
the department decided to use Bond Act proceeds to fund future
projects that would normally have been paid for by the highway
1
account and toll bridge fund. As of June 30, 2001, the depart-
ment had used this method to reimburse the highway
account $26.3 million. It intends to fully reimburse both the
highway account and the toll bridge fund before the Bond Act
expires in 2005.
RECOMMENDATION
To ensure that Bond Act proceeds are used only to pay for
eligible expenditures under the Bond Act, the department
should direct its staff to follow its policy of allocating facility
costs among all projects benefiting from the expenditure.
AGENCY COMMENTS
The department agrees with the report and recommendation and
states that it is taking steps to correct the identified problems. (cid:1)
2
INTRODUCTION
BACKGROUND
A
fter the Sylmar earthquake struck the Los Angeles area in
1971, the Department of Transportation (department)
established a program to seismically retrofit bridges
throughout the State. Seismic retrofit involves structural
analysis to determine a bridge’s potential vulnerability during
earthquakes and a strategy meeting with engineers to discuss
retrofit approaches and to determine the final retrofit design.
This design may involve strengthening the bridge columns by
encircling them with steel casings, fortifying some of the bridge
footings by placing additional pilings in the ground or by using
steel tie-down rods to better anchor the footings to the ground,
and enlarging the hinges that connect sections of the bridge
decks to help prevent them from separating during severe
ground movement.
Prior to the January 1994 Northridge earthquake, the
department classified all state-owned highway bridges
except toll bridges into two groups: single-column bridges and
multiple-column bridges. After the Northridge earthquake, the
department reclassified the bridges into Phase I and Phase II
categories. Phase I bridges included those that were identified
prior to January 1, 1994, as requiring retrofitting, while Phase II
bridges included all of the remaining state-owned bridges,
excluding toll bridges. In March 1996 California voters
approved the Seismic Retrofit Bond Act (Bond Act), which
authorized the State to sell $2 billion in general obligation
bonds to reconstruct, replace, or retrofit Phase II bridges and
the seven state-owned toll bridges.
The Bond Act initially required the department to use
$650 million of the bond proceeds to retrofit the toll bridges and
the remaining $1.35 billion to retrofit Phase II bridges. However,
on August 20, 1997, the governor signed into law Chapter 327,
Statutes of 1997, which shifted the allocation of expenditures to
$790 million for the toll bridges and $1.21 billion for Phase II
bridges. Since the department estimated in 1997 that the cost to
retrofit or replace state-owned toll bridges would be $2.62 billion,
the legislation also authorized additional retrofitting funds from
various state and toll bridge revenue accounts.
3
As of June 30, 2001, the department estimated the total cost
to retrofit the State’s seven toll bridges at $4.64 billion, or
$2.02 billion more than its 1997 estimate. In addition, the
department does not expect to complete the east and west spans
of the San Francisco-Oakland Bay Bridge until 2007 and 2008,
respectively, which is at least three years later than it estimated
in 1997. As amended by Chapter 327, Statutes of 1997, the
Bond Act will remain in effect until all construction activities
for the retrofit of the toll bridges are complete or until
June 30, 2005, whichever is sooner.
The Bond Act also required the department to use bond proceeds
to reimburse the State Highway Account and the Consolidated
Toll Bridge Fund for approximately $114 million in interim
funding that it expended for retrofits of Phase II and toll bridges
during fiscal years 1994–95 and 1995–96. We discuss these
reimbursements in greater detail in the Audit Results.
STATUS OF THE BOND ISSUANCES
Since the inception of the seismic retrofit program, the State
has issued 15 general obligation bonds under the Bond Act.
Appendix A shows the date and amount of each issuance.
SCOPE AND METHODOLOGY
Chapter 310, Statutes of 1995, requires the Bureau of State
Audits to annually audit revenues and expenditures authorized
by the Bond Act to ensure that the projects funded are consis-
tent with the act’s purpose.
To gain an understanding of the seismic retrofit program,
we reviewed the Bond Act’s provisions, its amendment by
Chapter 327, Statutes of 1997, and the related policies and
procedures developed by the department. We also interviewed
administrators and staff to determine their responsibilities for
implementing provisions of the Bond Act and their approach to
meeting those responsibilities.
To determine how fully the department complied with the
requirements of the Bond Act, we reviewed a sample of seismic
retrofit projects from fiscal year 2000–01 and assessed whether
4
these projects should have been eligible for funding. In addition,
we reviewed a sample of seismic retrofit expenditures incurred
by the department in fiscal year 2000–01.
We also followed up on the issues raised by the State Treasurer’s
Office regarding the federal tax implication of using bond
proceeds to reimburse Phase II and toll bridge seismic retrofit
expenditures from the fiscal years 1994–95 and 1995–96. We
reviewed the department’s records and interviewed administra-
tors to determine if the steps the department has taken satisfy
the reimbursement requirement of the Bond Act and resolve
federal tax concerns.
Finally, we reviewed bond-issuance records available through
June 2001 to determine the status of the bond issuances and
their use. (cid:1)
5
Blank page inserted for reproduction purposes only.
6
AUDIT RESULTS
THE DEPARTMENT HAS CONTINUED TO MAKE
PROGRESS TOWARD COMPLETING
ITS SEISMIC RETROFIT PROJECTS
A
s of June 30, 2001, Department of Transportation’s
(department) records showed that it had retrofitted
98.1 percent of the Phase II bridges, or a total
1,133 bridges. Of the 22 Phase II bridges that still required
retrofitting, the department had begun construction on 4 and
was in the process of deciding upon retrofit designs for the
remaining 18. In addition, the department was moving forward
appropriately on the retrofits of 6 of the 7 state-owned toll
bridges. In fact, it had finished retrofitting 2 of these 6 bridges
while the other 4 bridges are currently under construction.
The department also made progress on the seventh toll bridge,
the San Francisco-Oakland Bay Bridge. As of June 30, 2001, the
department had awarded 3 of the approximately 12 contracts
needed for the Bay Bridge’s retrofitting, and it projected that it
would award the remaining 9 contracts by the end of 2001.
Although the department began construction on the Bay Bridge
in 1994 and planned to finish in late 2004, it more recently
estimated that work would not be complete until 2008.
Appendix B shows the status of the seismic retrofit program.
As of June 30, 2001, the department had recorded approximately
$1.49 billion in expenditures for retrofit projects funded
with Bond Act proceeds. Appendix C shows the breakdown
of these expenditures.
THE DEPARTMENT INAPPROPRIATELY CHARGED SOME
EXPENDITURES TO SEISMIC RETROFIT PROJECTS
We reviewed a sample of 46 of the department’s seismic retrofit
projects and found that all were appropriate under the terms of
the Seismic Retrofit Bond Act of 1996 (Bond Act). We also
analyzed 40 expenditures totaling more than $5 million that the
department charged to seismic retrofit projects during fiscal year
7
2000–01. Although the majority of these costs were eligible
for Bond Act funds, the department inappropriately charged
the entire amount of some laboratory expenditures to seismic
retrofit projects rather than allocating the costs among
several projects.
According to departmental policies, laboratory supervisors are
responsible for allocating facility costs such as rent and utilities
on a proportionate basis to all construction projects assigned to
that particular laboratory. However, we found that some staff
were not aware of this policy and inappropriately charged the
entire amount of a laboratory lease payment totaling $6,601 to a
seismic retrofit project rather than allocating the cost among
three projects—one seismic project and two nonseismic projects.
We also found an office repair bill for $221 that the department
charged to a seismic project that it should have allocated among
eight projects. If it does not properly allocate its expenditures,
the department cannot ensure that Bond Act proceeds are used
only for intended purposes.
THE DEPARTMENT HAS BEGUN TO REIMBURSE
EARLY SEISMIC RETROFIT EXPENDITURES
Article 2 of the Bond Act requires that the department use bond
proceeds to reimburse the State Highway Account (highway
account) and the Consolidated Toll Bridge Fund (toll bridge
fund) for seismic retrofit expenditures they incurred during fiscal
years 1994–95 and 1995–96. According to department records,
these expenditures totaled $114 million, including $103 million
from the highway account and $11 million from the toll bridge
fund. However, during the department’s initial attempt to
comply with the Article 2 requirement, the State Treasurer’s
Office (STO) raised the concern that reimbursing these past
expenditures with bond proceeds could jeopardize the bonds’
federal tax-exempt status.
To address this issue, the department proposed that, rather than
reimbursing the highway account and toll bridge fund directly,
it would instead use bond proceeds to pay for future projects
that would not otherwise be eligible for funding under the
terms of the Bond Act. Specifically, the department proposed
that $103 million of the bond proceeds would be applied to state
transportation projects that would normally be funded with
8
highway account funds and that another $11 million would be
applied to construction work that would normally be paid for by
the toll bridge fund. By paying for these projects with bond
proceeds, the department would in effect reimburse the highway
account and toll bridge funds for their earlier seismic retrofit
expenditures. The State’s bond counsel believed that the
proposed plan would satisfy federal tax concerns.
According to the department, it needed to select projects
scheduled for construction and completion within the life of the
Bond Act in order to implement its proposed plan. Thus, on
July 20, 2000, the department reported to the California
Transportation Commission—the agency responsible for evalu-
ating plans for transportation programs—that it had elected to
use Bond Act proceeds to fund $103 million of minor State
Highway Operations and Protection Program (SHOPP) projects
that would normally have been funded by the highway
account. As shown in Appendix D, our review found that as of
June 30, 2001, the department had reimbursed the highway
account $26.3 million by using Bond Act proceeds to pay for
active SHOPP projects.
The department also moved forward with its plan to reimburse
the toll bridge fund. It selected three toll bridge fund projects to
finance with bond proceeds: the new Benicia-Martinez project,
the Timber Fender System project, and the Arch Span Traveler
project. As of June 30, 2001, the department had not yet
reimbursed the toll bridge fund for any of its $11 million
of seismic retrofit expenditures. However, according to the
department, it intends to complete the reimbursement process
for both the highway account and the toll bridge fund before
the Bond Act expires in 2005.
RECOMMENDATION
To ensure that Bond Act proceeds are used only to pay for
eligible expenditures under the Bond Act, the department
should direct its staff to follow its policy to allocate certain
types of costs, such as lease payments and repair bills, among
all projects benefiting from the expenditure.
9
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
Date: December 18, 2001
Staff: Denise L. Vose, CPA
Jerry A. Lewis
Chris Lief
10
APPENDIX A
Bond Act Issuances as of
June 30, 2001
TABLE 1
Seismic Retrofit Bond Act
General Obligation Bond Issuances
Amount Sold
Bond Series* Date Sold (In Millions)
A 03/18/97 $50.0
B 10/08/97 300.0
C 10/07/98 344.9
D 02/23/99 100.0
E 04/07/99 76.0
F 06/09/99 20.0
G 10/20/99 66.0
H 04/19/00 134.5
I 10/17/00 50.0
K 11/29/00 45.0
M 02/27/01 48.0
O 06/12/01 28.0
Total $1,262.4
* Series J, L, and N were refunding series that were issued to retire already out-
standing bonds. Because these issues did not increase the overall amount sold, we
did not include them.
11
Blank page inserted for reproduction purposes only.
12
APPENDIX B
Status of the Seismic Retrofit Program
T
ables 2 and 3 depict the status of the seismic
retrofit program for Phase II and toll bridges as
of June 30, 2001.
TABLE 2
Status of Phase II Bridges
Retrofit Under
District Complete Construction In Design Totals
1 64 1 4 69
2 12 0 0 12
3 36 0 0 36
4 143 2 6 151
5 105 1 1 107
6 77 0 0 77
7 292 0 1 293
8 124 0 6 130
9 7 0 0 7
10 40 0 0 40
11 172 0 0 172
12 61 0 0 61
Totals 1,133 4 18 1,155
Source: Quarterly Seismic Retrofit Report, 4th quarter, 2000–2001, issued by the
Department of Transportation.
13
TABLE 3
Status of Toll Bridges
Number of Current Retrofit
Toll Facility Projects Current Status Completion Date
San Francisco-Oakland Bay Bridge
East Bay Span* 4 Design Spring 2007
West Bay Span 8 Construction/Design Spring 2008
Benicia-Martinez Bridge 2 Construction Winter 2002
San Mateo-Hayward Bridge 3 Completed Spring 2000
Richmond-San Rafael Bridge 1 Construction Spring 2005
Carquinez Bridge (eastbound)† 1 Construction Fall 2001
Vincent Tomas Bridge 1 Completed Spring 2000
San Diego-Coronado Bridge 4 Construction Winter 2002
Source: Quarterly Seismic Retrofit Report, 4th quarter, 2000-2001 issued by the Department of Transportation.
* Although the department has completed an interim retrofit of the East Bay Span, it intends to construct a new bridge.
† The retrofit of the westbound Carquinez Bridge will be accomplished by a new bridge.
14
APPENDIX C
Bond Act Expenditures as of
June 30, 2001
TABLE 4
Breakdown of Seismic Retrofit Expenditures
(In Thousands)
Fiscal Year
Expenditures 1994–95 1995–96 1996–97 1997–98 1998–99 1999–2000 2000–01 Totals
Phase II bridges
State operations
Administration 0 0 $ 7,248 $ 18,314 $ 24,038 $ 10,010 $ 6,055 $ 65,665
Legal 0 0 0 0 0 0 0 0
Operations 0 0 0 0 1 17 2 20
Capital outlay—support $12,452 $19,248 70,609 80,542 34,928 21,321 17,675 256,775
Subtotals 12,452 19,248 77,857 98,856 58,967 31,348 23,732 322,460
Capital outlay
Major construction 0 0 0 0 0 0 0 0
Major contracts 4,085 1,880 185,215 172,184 65,256 63,250 41,713 533,583
Minor construction 0 0 0 0 0 0 0 0
Minor contracts 1,043 1,961 4,615 1,718 219 796 380 10,732
Right-of-way 57 259 562 1,118 443 373 69 2,881
Subtotals 5,185 4,100 190,392 175,020 65,918 64,419 42,162 547,196
Total Phase II 17,637 23,348 268,249 273,876 124,885 95,767 65,894 869,656
Toll bridges
State operations
Administration 0 0 3,490 11,789 15,694 6,536 3,953 41,462
Legal 0 0 0 0 0 0 0 0
Operations 0 0 0 0 0 0 0 0
Capital outlay—support 14,978 48,447 44,548 47,511 7,339 23 3 162,849
Subtotals 14,978 48,447 48,038 59,300 23,033 6,559 3,956 204,311
Capital outlay
Major construction 0 0 0 0 0 0 0 0
Major contracts 877 7,285 5,938 39,572 161,658 120,082 51,888 387,300
Minor construction 0 0 0 0 0 0 0 0
Minor contracts 0 0 0 0 0 0 0 0
Right-of-way 2 0 492 7,334 15,512 38 429 23,807
Subtotals 879 7,285 6,430 46,906 177,170 120,120 52,317 411,107
Total toll bridges 15,857 55,732 54,468 106,206 200,203 126,679 56,273 615,418
Grand Totals $33,494 $79,080 $322,717 $380,082 $325,088 $222,446 $122,167 $1,485,074
15
Blank page inserted for reproduction purposes only.
16
APPENDIX D
Bond Act Reimbursements as of
June 30, 2001
TABLE 5
Status of Reimbursements for Interim Funding
(In Thousands)
State Highway Consolidated
Account Toll Bridge Fund Totals
Expenditures
Fiscal Years 1994–95 and 1995–96 $103,048 $11,003 $114,051
Reimbursements
Fiscal Year 2000–01 26,302 0 26,302
Balance to Be Reimbursed $ 76,746 $11,003 $ 87,749
17
Blank page inserted for reproduction purposes only.
18
Agency’s comments provided as text only.
Business, Transportation and Housing Agency
980 9th Street, Suite 2450
Sacramento, CA 95814-2719
December 5, 2001
Elaine M. Howle
State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Dear Ms. Howle:
Attached is the Department of Transportation's (Caltrans) response to your draft report,
Department of Transportation: Its Seismic Retrofit Expenditures Generally Comply With
the Bond Act, and It Has Begun to Reimburse the Interim Funding for Fiscal Years 1994-95
and 1995-96 (#2001-010). I am pleased that Caltrans indicates it has already begun
action to address the finding and recommendation to direct staff to follow its policy of
allocating costs to all projects benefiting from the expenditure.
Thank you for acknowledging the progress Caltrans has made both in retrofitting more
than 1,150 state-owned highway bridges and the 7 state-owned toll bridges and in reim-
bursing the interim funding obtained during fiscal years 1994-95 and 1995-96. I look
forward to Caltrans' continued advance toward its goals of finishing the retrofits and com-
pleting the fund reimbursement.
I appreciate the opportunity to respond to your audit report. If you need additional informa-
tion, please do not hesitate to contact me, or Michael Tritz, Chief of the Office of Internal
Audits within the Business, Transportation and Housing Agency, at (916) 324-7517.
Sincerely,
(Signed by: Maria Contreras-Sweet)
MARIA CONTRERAS-SWEET
Secretary
Attachment
19
Department of Transportation
Office of the Director
1120 N Street
P.O. Box 942873
Sacramento, CA 94273-0001
December 4, 2001
MARIA CONTRERAS-SWEET, Secretary
Business, Transportation and Housing Agency
980 - 9th Street, Suite 2450
Sacramento, CA 95814
Dear Secretary Contreras-Sweet:
I am pleased to provide our response to the Bureau of State Audits' (BSA) draft audit
report entitled, "Department of Transportation: Its Seismic Retrofit Expenditures Generally
Comply With the Bond Act, and It Has Begun to Reimburse the Interim Funding for Fiscal
Years 1994-95 and 1995-96."
The report noted that the Department inappropriately charged some expenditures (lab
costs in District 4) to seismic retrofit projects. BSA is recommending that to ensure that
Bond Act proceeds are only used to pay for eligible expenditures under the Bond Act, the
Department should direct its staff to follow its policy to allocate certain types of costs, such
as lease payments and repairs, among all projects benefiting from the expenditure.
Although the total discrepancy was only $6,822 and was the result of an administrative
oversight, the Department takes the finding seriously, and has taken steps to correct the
identified problems. The Department has reminded its District 4 construction lab personnel
of its current procedures for prorating lab costs to multiple projects. Further, the
Department will update its current supplemental administrative guidelines (i.e., "Blue
Memos") used in its District 4 construction offices for charging practices. The update will
be consistent with the Department's current Deputy Directive DD-41 entitled "Departmental
Charging Practices" issued by the Department's Headquarters office on April 11, 1995.
Specifically, DD-41 requires that all employees use proper departmental charging practices
when coding source documents and input to automated systems. Once the Blue Memo is
updated, District staff will be given specific guidance on required charging techniques. This
will be done through quarterly Resident Engineer meetings in the District.
If we can provide further information, or if you have any questions, please contact Gerald
Long, External Audit Coordinator, at (916) 323-7122.
Sincerely,
(Signed by: Jeff Morales)
JEFF MORALES
Director
20
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California State
Government Organization and Economy