CSA
Summary
Read the report at California State Auditor ↗
California Energy
Commission:
Although External Factors Have Caused
Delays in Its Approval of Sites, Its
Application Process Is Reasonable
August 2001
2001-118
rotiduA
etatS
ainrofilaC
S
T
I
D
U
A
E
T
A
T
S
F
O
U
A
E
R
U
B
The first five copies of each California State Auditor report are free.
Additional copies are $3 each, payable by check or money order.
You can obtain reports by contacting the Bureau of State Audits
at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
Alternate format reports available upon request.
Permission is granted to reproduce reports.
C S A
ALIFORNIA TATE UDITOR
ELAINE M. HOWLE STEVEN M. HENDRICKSON
STATE AUDITOR CHIEF DEPUTY STATE AUDITOR
August 20, 2001 2001-118
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its
audit report concerning our review of the California Energy Commission’s (energy commission)
process for siting new and repowered energy generation facilities.
This report concludes that the energy commission missed the 12-month standard for approving
Applications for Certification (applications) by more than 30 days for 10 of the 23 applications it has
approved since 1990. However, while the energy commission is responsible for coordinating the
efforts of all parties involved in the application process, the delays were generally due to factors
outside its control. For example, applicants and local, state, and federal agencies were major
contributors to the delays we identified.
Additionally, while the energy commission did not always approve applications promptly, its process
appears reasonable and is comparable to four of five states we surveyed. However, on average,
the energy commission takes longer to approve applications than three of the states with compa-
rable processes. This is due, in part, to the inclusion of three projects that required more than two
years to approve.
Finally, the energy commission has implemented three expedited siting processes with the intent to
accelerate the construction of power plants in the short term. In fact, the energy commission has
approved 10 projects with a total generating capacity of 850 megawatts under its new 21-day
process. We were unable to evaluate the other two expedited processes because only one applica-
tion has been approved under either of these processes.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
BUREAU OF STATE AUDITS
555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019 www.bsa.ca.gov/bsa
CONTENTS
Summary 1
Introduction 5
Chapter 1
Delays in the Energy Commission’s Approval
of Applications Were Caused in Part by
Factors Outside Its Control 13
Recommendations 26
Chapter 2
Although the Energy Commission’s Process
for Approving Applications Is Slower Than
Those of Some States, Recent Changes
May Improve the Process 27
Recommendation 40
Response to the Audit
California Energy Commission 41
SUMMARY
RESULTS IN BRIEF
Audit Highlights . . .
C
oncerns have been raised about the inability of the State
Our review of the California Energy Resources Conservation and Development
Energy Commission’s (energy
Commission (energy commission) to approve applica-
commission) siting and
tions for the siting of power plants—known as Applications for
approval process revealed
that: Certification (applications)—in a timely manner. These concerns
have intensified recently because of California’s energy crisis. It
(cid:1)
Although the energy
is true that the energy commission has not always approved
commission has not
always approved applications within the standard 12-month period. For
applications within the 10 (43 percent) of the 23 applications approved since 1990, the
standard 12-month
energy commission missed the 12-month standard for approval
period, setbacks were
by more than 30 days. Although the energy commission is
due to a combination
of factors. ultimately responsible for the approval process, multiple factors
contributed to the delays for most of these 10 projects and some
(cid:1)
Of the four states with
of the delays were outside the energy commission’s control. For all
comparable processes,
of the 10 applications that were approved late, applicants did
only Oregon, at
30 months, took longer not submit some of the required information in a timely man-
than California to ner. For 7 of these applications, other local, federal, and state
approve applications.
agencies failed to process approvals promptly. In addition,
Minnesota, Florida, and
Connecticut took between outside parties raised objections to some of the proposed sites,
7 and 15 months to thus delaying the approval of 3 applications. Finally, for 7 of the
approve applications,
applications the energy commission held public workshops well
while the energy
beyond its 180-day standard. However, because the energy
commission averaged
nearly 17 months. commission continued to attempt to resolve all outstanding issues
while waiting for other agencies to issue their final decisions, the
(cid:1)
The energy commission is
average approval time for applications over the past 11 years was
able to approve projects
14 months, only 2 months beyond the 12-month standard.
quicker than other
permitting processes in
California because it In addition to the 23 applications it has approved since 1990,
combines activities that
the energy commission has also performed various levels of review
are performed
consecutively under on 13 other power plant applications. However, the developers
other processes. withdrew these applications before the energy commission
(cid:1) completed its reviews. Although the staff resources devoted to
Ten applications have
reviewing these applications may have had some effect on the
been approved under the
new 21-day expedited energy commission’s ability to approve other projects within the
process, adding over required time frame, we do not believe the impact was significant
850 megawatts of
on recent projects.
electricity to the
State’s supply.
1
The energy commission’s process for approving applications is
comparable to those used by four of five states we surveyed. Our
review of Minnesota, Texas, Florida, Connecticut, and Oregon
suggested that, with the exception of Texas, the tasks performed
by each state when approving applications were generally
similar. Of the four comparable states, only Oregon took longer
than California to approve applications. Minnesota, Florida, and
Connecticut each averaged approval times of between 7 and
15 months, Oregon averaged 30 months, and the California
energy commission averaged nearly 17 months—2.5 months to
assess the adequacy of the application and more than 14 months
to approve it. However, when we omit from these calculations
three projects that involved serious emissions concerns, the energy
commission’s average approval time decreases to 15 months.
The energy commission’s process is more efficient than other
permitting processes in California. The California Environmental
Quality Act and the Permit Streamlining Act allow up to
24 months for the approval of similar types of projects. The
energy commission is able to approve projects more quickly
because it combines activities that are performed consecutively
under these other processes.
In addition to its standard 12-month siting process, the energy
commission recently implemented three expedited siting processes
of varying lengths: 6 months for thermal power plants with no
adverse environmental impacts, 4 months for simple cycle facili-
ties, and 21 days for plants that would produce extra electricity
during peak times. The intent was to accelerate the construction
of power plants in response to the threat of potentially serious
electricity shortages over the next few years. It is too early to tell
how effective the 6- and 4-month processes will be, as only
1 application has been approved under either of these processes.
On the other hand, 11 applications have been approved under
the 21-day process, and the energy commission expects that
10 of these projects—1 project has since been withdrawn—will
add over 850 megawatts of electricity to the State’s supply by the
end of September 2001.
RECOMMENDATIONS
To encourage applicants to submit sufficient data in a timely
manner, the energy commission should exercise its authority to
terminate applications when the applicant does not appropri-
ately respond to requests for data.
2
To assist the energy commission in its efforts to approve applica-
tions within a 12-month period, it should also more strictly
enforce its standard that limits to 180 days the time allowed for
parties to raise new issues and submit additional requests for
data. Moreover, the Legislature should consider establishing a
firm 180-day deadline for parties to raise issues and request data.
To ensure that the expedited 6- and 4-month processes are
effective and to determine their long-term viability, the energy
commission should evaluate the success of these new processes
after a sufficient time.
AGENCY COMMENTS
The agency did not have any significant concerns with the audit
report and believes it accurately portrays the issues that influence
the time required to review applications for energy facilities. (cid:1)
3
Blank page inserted for reproduction purposes only.
4
INTRODUCTION
CALIFORNIA’S CURRENT ENERGY CRISIS
I
n 1996 the Legislature passed Assembly Bill 1890, enacting
many policies for deregulating the State’s electricity industry.
These policies had been proposed by the California Public
Utilities Commission (CPUC) after a shift in federal energy
policies. The newly restructured system allowed retail customers
of all sizes to choose their electricity suppliers, although they
could continue to maintain service with one of the three inves-
tor-owned utilities—Pacific Gas and Electric Company (PG&E),
Southern California Edison (SCE), and San Diego Gas & Electric
Company (SDG&E)—if they desired. One purpose of deregulation
was to allow other energy producers into the market, with the
expectation that doing so would lower the price of electricity.
However, a combination of factors, including a continued growth
in the demand for electricity coupled with a lack of ample
supply, resulted in the current energy shortage and high energy
prices. Various state and federal agencies are still investigating
the causes of these problems.
At the time the deregulation legislation was enacted, there was an
excess supply of electricity in California as well as in the western
region, which kept short-term energy prices low. However, popula-
tion expansion and rapid economic growth during 1999 and
2000 contributed to a rising demand for electricity that was not
met with a similar increase in supply. Apparently due to a
combination of factors, including excess supply and uncertainty
about the future of deregulation, investor-owned utilities built
fewer new power plants in the early 1990s than they had in
previous years. In fact, from 1991 to 1995, the investor-owned
utilities submitted only one application to the State Energy
Resources Conservation and Development Commission (energy
commission) to site a new power plant. The proposed concepts of
deregulation, which the CPUC was studying following a shift in
federal energy policy, may have served as a disincentive to build
additional power plants. For example, if the investor-owned
utilities believed that after deregulation they would be required
to sell their power plants to facilitate competition, they might
have been uncertain of their ability to recoup their building
costs. Even if they believed they would be allowed to keep their
power plants after deregulation, they might have been unsure as
5
to whether the wholesale price of electricity in a newly deregulated
market would be high enough to warrant their investment in
new power plants. A November 1998 ballot initiative may have
compounded these uncertainties. If it had
passed, this initiative, Proposition 9, would
have further modified deregulation in a way
Types of Power Plants that, according to the Legislative Analyst’s
ballot analysis, would probably have been
• Hydro: Produces electricity from falling
water that turns a turbine generator. challenged in court. Therefore, the uncer-
(cid:127) Wind: Produces electricity from tainties surrounding deregulation may have
wind that spins the blades on contributed to the investor-owned utilities’
a turbine.
reluctance to build new power plants.
(cid:127) Thermal: Produces electricity from sources of
heat, including:
In recent years, applications to the energy
(cid:127) Natural gas
commission to build new power plants have
(cid:127) Oil
increased significantly. Developers submitted
(cid:127) Nuclear
19 applications between January 1997,
(cid:127) Solar thermal
shortly after deregulation was approved, and
(cid:127) Geothermal
June 2000, when energy prices first spiked,
Examples of thermal power plants include:
and 18 applications were submitted between
(cid:127) Simple Uses gas to operate a turbine to
cycle: generate electricity and does not July 2000 and June 2001, at least partially
recycle the waste heat generated in response to the shortage. The efficient
by the process.
siting of new power plants by the energy
(cid:127) Combined Uses gas to operate a turbine to
commission is rapidly becoming vital to the
cycle: generate electricity, and recycles
its waste heat by using it to produce State’s ability to avoid rolling blackouts and
steam. It then uses the steam to to deliver reliable power over the next
operate conventional steam
several years.
turbines, to produce even
more electricity.
(cid:127) Cogenerator: Uses the waste heat created by
one process, for example,
THE RESPONSIBILITIES OF THE
manufacturing, to produce
steam that is used, in turn, to ENERGY COMMISSION
operate a turbine and generate
electricity. It can also use gas to
The Legislature established the energy
run a turbine, using the steam
to generate more electricity. commission in 1974 to address the energy
challenges facing the State at that time.
(cid:127) Peaker A simple cycle power plant that is
plant: normally used to produceelectricity Created by the Warren-Alquist State Energy
during peak load times.
Resources Conservation and Development
Commission Act (Warren-Alquist Act), the
energy commission is composed of five
commissioners appointed by the governor to staggered five-year
terms. As the State’s primary energy policy and planning agency,
it is responsible for ensuring that a dependable supply of energy
exists to meet California’s needs and for monitoring power
plants’ compliance with environmental, safety, and land use
goals. It is the energy commission’s mission to assess, advocate
for, and act to improve energy systems that promote a strong
6
economy and a healthy environment while providing Californians
with energy choices that are affordable, reliable, diverse, safe,
and environmentally acceptable.
The energy commission’s specific responsibilities include
the following:
(cid:127) Processing applications for the licensing of thermal power
plants that are 50 megawatts (MW) or larger. Plants smaller
than 50 MW are licensed by city and county agencies.
(cid:127) Encouraging measures to reduce wasteful and inefficient use
of energy.
(cid:127) Collecting and analyzing information regarding alternative
ways to conserve, generate, and supply energy.
(cid:127) Forecasting future energy needs and keeping historical data.
(cid:127) Developing energy technologies and supporting renewable
energy programs.
(cid:127) Promoting energy efficiency through appliance and building
standards.
THE SITING PROCESS
To ensure that a reliable supply of energy is maintained at the
level necessary for public health and safety, the Legislature
established a comprehensive energy forecasting and power plant
siting process. This process requires that anyone proposing to
construct a thermal power plant with a net generating capacity
of 50 MW or larger must file a Notice of Intention (NOI), an
Application for Certification (application), or a Small Power Plant
Exemption (SPPE). The type of proposal that must be filed depends
upon the size and nature of the project: for instance, an SPPE is
optional for any thermal power plant with a net generating
capacity of more than 50 MW but less than 100 MW and does
not have any significant environmental effects.
Under current law, any developer proposing a large and complex
project, such as a direct-fired coal or nuclear facility, must
complete a 12-month NOI process before filing an application.
Essentially, the objective of the NOI process is to determine the
need for, acceptability of, and suitability of a proposed site and to
evaluate whether any alternatives to the proposal would better
7
carry out the aims of the Warren-Alquist Act and the California
Environmental Quality Act (CEQA). During the NOI process, the
applicant must propose at least three alternative sites, and the
energy commission must ultimately evaluate the suitability and
approve at least one of these. To make its determination, the
energy commission conducts hearings during which it considers
the analyses of energy commission staff as well as the testimony
of the applicant and any intervenors. SDG&E filed the last NOI
in 1989 and then withdrew it in 1991. Prior to 1989, the last
NOI filing occurred in 1984. All projects currently proposed in
California are exempt from the NOI process.
Instead of an NOI, applicants proposing to construct a thermal
power plant must submit an application. Figure 1 describes the
various phases of the application process. During the application
process, the energy commission examines the design, construc-
tion, and operation of the facility in relation to applicable laws
FIGURE 1
Seven Phases of the Energy Commission’s Application Process
Prefiling The applicant, energy commission staff, and/or other agencies may meet to
(Optional) discuss the project, application process, filing requirements, specific issues,
workshops, site visits, and the scheduling of public workshops. Energy
commission staff may perform a preliminary review of the application before
Determination
it is filed.
of Completeness
Phase Data Adequacy Energy commission staff review the application to determine if it complies
Up to 45 days with the information requirements per the siting regulations. The staff make
a recommendation to the energy commission.
Discovery Following acceptance of an application by the energy commission, there is a
Days 0 to 45 period of data gathering by the staff; intervenors (formal parties to the process);
and local, state, and federal agencies. Also, staff prepares an Issue Identification
Report and presents it at a public information hearing(s) conducted by the
energy commission committee. Staff members may also hold public workshops.
Analysis Staff, agencies, and intervenors analyze the project and its various issues during
Days 45 to 220 this period. The staff prepares aPreliminary Staff Assessment. After a pre-hearing
12-Month conference, the staff submits the Final Staff Assessment, which usually serves as
Application the staff’s testimony.
Approval
Hearings An energy commission committee consisting of two commissioners conducts a
Process
Days 90 to 305 pre-hearingconference followed by hearings to hear the findings and
conclusionsof the applicant, staff, intervenors, and other agencies. The public
also can present its comments.
Decision The energy commission committee prepares and issues a Presiding Member’s
Days 305 to 365 Proposed Decision (PMPD). Subsequently, the committee holds a hearing. The
full energy commission generally considers whether to approve or deny the
PMPD at its regularly scheduled bi-monthly business meeting.
Compliance The staff monitor a project’s conformance with the conditions of the energy
Days 365+ commission’s decision regarding its design, construction, operation, and
closure phases.
Source: Energy Commission Siting Program Manual.
8
and regulations. According to the energy commission, the
application process is intended to ensure that proposed facilities
are safe, reliable, and environmentally sound and that they com-
ply with applicable laws, ordinances, regulations, and standards.
State law gives the energy commission broad authority to decide
whether a power plant is in California’s best interest, regardless
of possible local government and public opposition, which may
be based on a concern that a project could have significant
adverse environmental impacts such as air pollution or water
contamination. To ensure that environmental concerns are
properly considered, the energy commission’s guidelines require
that it perform the same basic functions as those required under
CEQA, the law that outlines the environmental review that the
State or local agency must conduct for all new projects that
might have a significant impact on the environment. The
energy commission’s application process does not have to follow
CEQA guidelines precisely because the California Resources
Agency has certified that the application process is essentially
equal in function and purpose to the review required by CEQA.
REVIEWS BY OTHER AGENCIES
When a developer submits an application, the energy commis-
sion notifies the California Independent System Operator and
other governmental agencies, such as local air and water boards,
the California Air Resources Board, the United States Fish and
Wildlife Service, and the Federal Environmental Protection
Agency, to coordinate their reviews in the application process.
These agencies review the application for compliance with the
laws and regulations that apply to the proposed facility. They
then either issue comments and recommendations or request
that the applicant perform additional analyses or studies.
SCOPE AND METHODOLOGY
The Joint Legislative Audit Committee (audit committee) requested
the Bureau of State Audits to examine the application process used
by the energy commission for approving new and repowered
energy generation facilities. Specifically, the audit committee
requested, among other things, a review of appropriate procedures
and time limits of the site and permit approval process, the nature
of all applications filed with the energy commission since 1990,
9
the viability of the energy commission’s expedited permitting
processes, and the appropriateness of certifying the application
process as functionally equivalent to CEQA.
To gain an understanding of the energy commission and its
application process, we reviewed relevant state laws and regula-
tions, including CEQA and the Permit Streamlining Act (PSA). In
addition, we studied the applicable sections of the protocols
used by the energy commission. We also interviewed energy
commission staff to understand its role in reviewing and certifying
applications as well as its role in ensuring public participation in
the approval process.
We reviewed all applications approved by the energy commission
since 1990 to ascertain the overall success rate of the siting process,
the reasons power plants were permitted but not constructed,
and the reasons applications were withdrawn or otherwise failed
in the process. To accomplish this, we acquired the energy
commission’s database of all power plant applications and
reviewed in detail each siting case, including key dates, analyses,
and correspondence. We also focused specifically on identifying
the causes of delays in the completion of each of the phases of
the process.
To identify possible ways to improve or streamline the energy
commission’s process for siting new power plants, we compared
it to the application processes of five other states: Oregon, Texas,
Minnesota, Connecticut, and Florida. We selected these states
based on recent changes in their application process, the number
of facilities sited since 1990, and a geographical representation.
Consultants with expertise in the energy industry conducted
extensive interviews with state siting commissions, utilities, and
power plant developers in the five states. They analyzed data
about power plants sited during the 1990s to determine what
processes each state used and the amount of time each required
to site facilities.
In examining the viability of the energy commission’s recently
developed expedited permitting processes, we identified the
reasons each process was developed and analyzed the regulations
that applied to that process. Also, the consultants talked to
developers regarding their experiences with the new processes.
Finally, using the energy commission’s power plant project
status sheets, we examined the applications that had been
submitted under the new processes to determine whether the
processes had been effective.
10
To determine how the approval of applications compared to the
approval of projects under CEQA and PSA, we prepared side-by-
side comparisons of the time and informational requirements of
each process. In addition, we met with staff at the State Clear-
inghouse—a branch of the governor’s Office of Planning and
Research that provides technical assistance on CEQA matters—to
solidify our understanding of the similarities and differences of
each process. To evaluate the appropriateness of certifying the
energy commission’s application process as functionally
equivalent to CEQA, we interviewed the general counsel of the
California Resources Agency as well as the assistant chief counsel
of the energy commission. We identified the mandated criteria
used to certify the energy commission’s application process as
equivalent to CEQA, analyzed recent changes in the energy
commission’s regulations, and determined whether or not each
regulation fulfilled the designated criteria.
We were also asked to examine the availability of dispute
resolution mechanisms in the application process. Throughout
our audit work, we determined that the energy commission is
constantly involved in resolving disputes, largely during the
various hearings and workshops that it holds. While reviewing
case documentation, we read transcripts, agendas, and other
correspondence supporting the fact that the energy commission
takes on an active role in dispute resolution. (cid:1)
11
Blank page inserted for reproduction purposes only.
12
CHAPTER 1
Delays in the Energy Commission’s
Approval of Applications Were
Caused in Part by Factors Outside
Its Control
CHAPTER SUMMARY
S
ince 1990 the State Energy Resources Conservation and
Development Commission (energy commission) has
approved 23 Applications for Certification (applications)
for power plant projects. For 10 of these 23 applications, the
energy commission missed the required 12-month standard for
approval by more than 30 days. However, in many cases, the
actions of other parties involved in the process contributed to
these delays. Applicants did not always submit needed informa-
tion on time; federal, state, and local agencies sometimes failed
to process approvals promptly; and in some instances outside
parties raised objections to proposed sites. Faced with these
circumstances, the energy commission continued acting to
resolve those issues within its control while waiting for the other
parties to complete their responsibilities. As a result, the average
approval time for applications over the past 11 years was
14 months, only 2 months beyond the deadline generally
required by state law.1 Figure 2 on the following page shows the
location of these 23 projects.
In addition to the 23 applications approved since 1990, the
energy commission also performed various levels of review on
13 other power plant applications that were eventually with-
drawn by the applicants. Although the staff resources devoted to
reviewing these applications may have had some effect on the
energy commission’s ability to approve other projects in a
timely manner, the withdrawn applications do not appear to
have affected the approval process for recent projects.
1 State law provides that the deadline may be exceeded if agreed to by both the energy
commission and the applicant.
13
FIGURE 2
Location of the 23 Power Plants the Energy Commission Approved Since 1990
Procter & Gamble
,
,
,
c i f
h n b
,
Source: Energy Commission Power Plant Licensing Cases’ Maps.
14
THE ENERGY COMMISSION’S APPROVAL PROCESS HAS
GENERALLY TAKEN LONGER THAN 12 MONTHS
The energy commission has taken an average of more than
14 months to review applications approved since 1990, despite
state law generally requiring it to issue its decisions within
12 months. As we discussed in the Introduction, siting process
guidelines dictate that the energy commission complete the
various phases of the application process within a specific
number of days after an application is deemed adequate. From
January 1990 through June 2001, the energy commission
approved 23 power plant projects, for which approval times
ranged from a low of 92 days to a high of 882 days, with the
average approval taking 430 days. Table 1 on the following page
lists the time for completing each phase for each project. The
average times for completing the various phases of the process,
with the exception of the discovery and decision phases, were
longer than expected. For example, the analysis phase, which
should take 175 days, took 254 days on average to complete.
Even relatively small delays in different phases of the application
process can have a significant cumulative effect. For instance,
delays in the discovery and analysis phases may make it difficult
for the energy commission to issue its final decision within
12 months. Longer delays in the earlier phases can affect the
timeline for the entire process. In 3 of the 23 applications
approved since 1990, the analysis phase alone took more than
12 months to complete, thus making it impossible for approval
to be granted within the required time frame. As Table 2 on
page 17 shows, when the approval process was significantly
delayed, several factors combined, rather than a single factor,
caused the delays.
SOME APPLICANTS SUBMITTED INSUFFICIENT
DATA, CAUSING ADDITIONAL DELAYS IN THE
APPLICATION PROCESS
The energy commission’s processing of applications was slowed
at times by the actions of the applicants themselves. In most
Applicants contributed to cases, applicants delayed the process by not responding to data
the delays in all 10 of the requests or not performing required studies in a timely manner.
applications that In other instances, applicants filed amendments to applications
exceeded the 12-month months or years into the process, causing the energy commis-
deadline by more than sion staff to review and analyze the change. In addition, staff
30 days. may have to issue new or revised staff reports or testimony as a
result of these changes.
15
TABLE 1
On Average, the Total Application Processing Time Exceeded the
12-Month Standard by 65 Days for Applications for Certification
Approved From January 1990 Through June 2001
(e)
Days Required to Complete Each Task
Total
(a) (b) (c) (d) Application
Applicant and Discovery Analysis Hearing Decision Processing
Project Name Phase Phase Phase Phase Time
AES—Huntington Beach Generating Station Retool Project 8 29 13 42 92
El Paso Merchant Energy Company—United Golden Gate Power Project Phase l 22 56 22 33 133
Thermo Ecotek––Mountainview Power Plant Project 27 223 16 42 308
Southern Energy Delta, LLC––Contra Costa (Antioch) Power Plant Project 26 263 56 33 378
Western Midway-Sunset Cogeneration Company––Western 33 218 94 33 378
Midway Sunset Cogeneration Power Plant Project
Blythe Energy, LLC—Blythe Energy Power Plant Project 43 193 99 29 364
Pastoria Power Project, LLC (Enron North America Corporation)–– 47 176 72 34 329
Pastoria Energy Facility
Otay Mesa Generating Company (PG&E National Energy Group)— 40 347 136 37 560
Otay Mesa Generating Project
Duke Energy Moss Landing, LLC—Moss Landing Power Plant Project 27 267 90 57 441
Three Mountain Power, LLC (Ogden Pacific Power)–– 54 463 143 33 693
Three Mountain Power Plant Project
Elk Hills Power, LLC—Elk Hills Power Project 33 291 119 103 546
Sunrise Cogeneration & Power Project (Texaco, Inc.)––Sunrise Power Project 29 592 21 16 658
Calpine Corporation and Bechtel Enterprises, Inc.––Delta Energy Center 33 231 45 48 357
La Paloma Generating Company, LLC––La Paloma Generating Project 21 208 99 78 406
Pittsburg District Energy Facility, LLC––Pittsburg 36 223 77 48 384
District Energy Facility (Los Medanos Power Plant Project)
Calpine Corporation––Sutter Power Project 41 259 64 84 448
High Desert Power Project, LLC––High Desert Power Plant Project 43 370 329 140 882
San Francisco Energy Company––San Francisco 34 254 124 132 544
Energy Company’s Cogeneration Project
Sacramento Power Authority at Campbell Cogeneration Project 19 248 50 47 364
Sacramento Cogeneration Authority—Sacramento Cogeneration 27 203 92 42 364
Authority’s Procter & Gamble Cogeneration Project
Sacramento Power, Inc.—Sacramento Ethanol and 29 333 130 61 553
Power Cogeneration Project (SEPCO)
Crockett Cogeneration, LP—Crockett Cogeneration C&H Sugar Refinery Project 19 184 82 84 369
Luz Development and Finance Corporation–– 44 214 59 19 336
Solar Electric Generating Systems (SEGS) Units IX & X
Average Time Frames, All Projects 32 254 88 55 430
Expected Time Frames, All Projects 45 175 85 60 365
(a) Days between the date the application is deemed data adequate and the date the informational hearing and site visit are held.
(b) Days between the date the informational hearing and site visit are held and the date of the Final Staff Assessment.
(c) Days between the date the Final Staff Assessment is issued and the date the Presiding Member’s Proposed Decision is issued.
(d) Days between the date the Proposed Decision is issued and the date the energy commission issues its Final Decision.
(e) Days between the date the application is deemed data adequate and the date the energy commission issues its Final Decision.
Source: Energy Commission Application Database and Docket Unit.
16
State regulations require applicants to respond to data requests
made by the energy commission, public agencies, and interested
parties within 30 days of receipt of the request. In 3 of the
10 applications that were approved late, applicants requested
formal extensions to the process when they realized it would
take them additional time to respond to the requests. In other
cases, however, applicants ignored or objected to data requests
or submitted inadequate responses, necessitating additional time
for the energy commission to reissue the requests. Since 1990 all
10 of the applications that exceeded the 12-month deadline by
more than 30 days were partially the result of applicant-caused
delays. For example, according to an energy commission status
report, the Elk Hills Power Project approval was delayed in part
because the applicant did not submit required information to
the local air district on time. In fact, the local air district did not
issue its final decision until 338 days after the energy commis-
sion had deemed the application adequate.
TABLE 2
Factors Contributing to Delays in Approving Applications
Applicant
Submitted Local, State, Public
Days From Insufficient and/or Public Workshops
Determination of Data or Federal Agencies Intervention Held Well Past
Completeness to Amendments Issued Required Extended the 180-Day
Project Name Final Decision to Projects Permits Late the Process Deadline
High Desert Power Plant Project 882 x x x x
Otay Mesa Generating Project 560 x x x x
Three Mountain Power Plant Project 693 x x x
Sunrise Power Project 658 x x x
Elk Hills Power Project 546 x x
Sutter Power Project 448 x x
Moss Landing Power Plant Project 441 x x x
San Francisco Energy Company’s 544 x x x
Cogeneration Project
Sacramento Ethanol and Power 553 x x
Cogeneration Project
La Paloma Generating Project 406 x
In six instances the California Air Resources Board, the Federal
Environmental Protection Agency (EPA), or both had to step in to
ensure that the applicant submitted adequate data indicating that
air quality standards would be fully met. For example, the
17
High Desert Power Plant Project application was originally
submitted in June 1997. In December 1997, when the application
was deemed adequate, the applicant sent a letter to the energy
commission stating that it had met with the local air district
several times since 1994 and thus had a firm understanding of
the requirements for an air permit; moreover, it assured the
energy commission that it was fully prepared to meet all data
requests and timetables. Despite this, the applicant continuously
failed to submit required studies and information related to air
The energy commission quality. Finally, the EPA informed the local air district that
spent approximately unless the problems were corrected, it intended to take action if
2.5 years processing the applicant attempted to begin construction of the facility. It
one application because was not until February 2000, approximately 2.5 years after the
the applicant application data was deemed adequate, that the applicant, the
continuously failed to local air district, and the EPA finally resolved all issues for this
submit required data. application. Staff reports, local air district communications, and
letters from the EPA confirm that this applicant continuously
missed deadlines, failed to respond to data requests in a timely
manner, and did not perform required studies.
As the example above shows, the failure of applicants to submit
sufficient information affects not only the energy commission
but also the local, state, and federal agencies involved in the
approval process. At a recent information gathering workshop
held by the energy commission, the EPA stated that insufficient
data from applicants was one factor delaying its reviews. The only
remedy given to the energy commission by state regulations in
these situations is the power to terminate the application if it
determines that the applicant has failed to diligently pursue the
application. We noted that the energy commission’s staff
worked to keep in constant communication with the applicant
in an attempt to keep the application process on schedule.
However, occasionally the energy commission had to wait until
the applicant submitted the necessary studies and information
or resolved all issues with outside agencies.
The time to approve an application is sometimes extended when
applicants file amendments to their applications. Amendments
are filed either to resolve concerns with the application or to
modify the original project. Yet even when amendments are
filed to correct deficiencies in applications, they add to the
application processing time. For example, the Three Mountain
Power Plant Project applicant submitted an amendment to its
application 425 days, or more than a year, after the energy
commission deemed the application adequate. The applicant
submitted the amendment to address soil and water concerns.
18
Ultimately, the energy commission approved the application with
the amendment; however, the revision necessitated additional
reviews by energy commission staff, which contributed to the
delay in the project’s approval.
On a few occasions, applicants also filed amendments that
substantially altered the nature of the projects. Such amendments
generally caused delays. For example, 194 days after the High
Desert Power Plant Project application was deemed adequate, the
applicant notified the energy commission that it was amending
the project to add a 32-mile natural gas pipeline. Because of the
significance of this change and because the pipeline crossed land
under the aegis of the Bureau of Land Management, additional
reviews were required by state and federal agencies, one of
which had not previously been involved with the project. In
another example, the applicant for the Sunrise Power Project
informed the energy commission 573 days into the process that,
rather than constructing a cogeneration facility, it intended to
construct a simple cycle facility in order to begin operations in
time to deliver power during the peak summer demand of 2001.
However, because the applicant did not submit the amendment
until after the energy commission had already issued its proposed
decision, the energy commission was required to prepare a
revised staff assessment, hold additional evidentiary hearings,
and issue a revised proposed decision. Despite this, the energy
commission approved the revised application only 3 months
after the applicant filed the amendment.
The Failure of Federal, State, and Local Agencies to Issue
Timely Approvals Resulted in Delays in the Application Process
To complete its application process by the required deadlines,
the energy commission must rely on timely responses from a
By submitting their number of outside parties. These include the federal, state, and
decisions well past local agencies responsible for issuing approvals for various
the 180-day deadline, portions of the project. Delays by those agencies in issuing
local air districts required approvals or decisions contributed to delays in 7 of the
contributed to delays in 10 applications that were approved more than 30 days late. In
7 of 10 applications that particular, local air districts tended to submit their final decisions
were approved more than well past the 180-day deadline required by state law.
30 days late.
Currently, state law requires local air districts to submit a final
decision on the potential impact of the power plant on air
quality within 180 days from the date that the application is
deemed adequate. However, until a January 2000 legislative
amendment addressed the problem, the energy commission’s
19
time requirements conflicted with the past joint policy agree-
ment between the energy commission and the California Air
Resources Board, which allowed local air districts 240 days to
issue final decisions. Yet even using the 240-day deadline, our
analysis revealed that in many cases local air districts did not
reach final decisions within the allowed time. Since 1990 the
average time for the energy commission to receive final decisions
from local air districts has been 319 days, 139 days more than
the 180-day deadline and 79 days more than the 240-day deadline.
According to energy commission staff, some of these delays may
have occurred either because local air districts did not have
sufficient resources to produce final decisions within the 180 days
or because they gave other projects higher priority. To ensure
that power plants were sited quickly to address public health,
safety, and welfare threats posed by the energy supply emergency,
the governor issued an Executive Order in February 2001 requir-
ing all local, regional, and state agencies to expedite energy
commission projects to the extent possible while continuing to
protect the State’s environmental interests and the health and
safety of the public. Because the governor issued this order so
recently, the local districts have not had sufficient time to
complete their reviews of applications currently in progress;
therefore, we cannot determine the effect of the governor’s
order. However, according to energy commission staff, local air
districts are making more of an effort to meet deadlines.
Delays also occurred when the EPA objected to the local air
districts’ decisions because of its concerns with the air analyses.
For example, the Three Mountain Power Plant Project’s local air
Some delays occurred district took 475 days to issue its decision because of the need to
when the Federal negotiate with the applicant and the EPA. Similarly, the EPA
Environmental Protection informed the applicant of the Elk Hills Power Project that its
Agency objected to local permit under the Federal Clean Air Act was insufficient and that
air districts’ decisions it needed to perform additional air analyses. The local air district
because of concerns with did not issue its final decision in this instance until 338 days after
the air analyses. the data adequacy determination had been made, while the EPA
took 443 days to grant its approval. According to the energy
commission, problems occur in part because federal agencies
have no established review deadlines and some federal agencies
lack sufficient staff to review applications in a timely manner. As
we described earlier, the EPA can and does step in when it finds
that state and local agencies have not met the federal requirements
of the Federal Clean Air Act.
20
In order to further expedite the processing of applications, the
energy commission organizes public workshops and meetings
with federal, state, and local agencies when problems arise.
Further, in December 2000, the energy commission also issued
an order creating an informational proceeding committee. This
committee has been conducting information-gathering workshops
with other agencies, applicants, and public interest groups to
discuss critical issues affecting the energy commission’s ability to
license power plants and related facilities in light of the State’s
increasing demand for electricity. It is also developing recommen-
dations to improve the energy commission’s application process.
To date, the informational committee has held meetings on issues
such as local agency participation, public participation, and
timing of federal permits, among others. According to the
energy commission, it will produce a report by the end of
August 2001 with the results of these workshops.
In a Few Instances, Public Intervention Slowed the Energy
Commission’s Approval Process
Another party that plays a role in the approval of power plant
applications is the public. As we discussed earlier, both the
applicants and the agencies involved in the approval process at
times contributed to delays. The public’s responsibility for delays
tends to be more indirect, although for three of the applications
approved since 1990, public opposition was partially responsible
for delays in the approval process. For example, the San Francisco
Energy Company’s Cogeneration Project experienced a delay of
179 days. Public opposition was only one of several causes of the
delay, and it was not successful in blocking the application on
the basis of environmental concerns. However, the project was
not ultimately completed because the applicant was denied a
required lease, a denial that was at least in part influenced by
public outcry.
The public’s indirect influence on the timely approval of projects
is more difficult to measure. While it is not possible to have
complete public support for all projects, the energy commission
Although difficult to attempts to ensure that interested parties are able to participate
measure, public in the application process. To achieve this end, it holds public
opposition has indirectly workshops in which it attempts to resolve issues such as air
contributed to delays in quality, biological, and visual concerns with the applications.
approving applications. These workshops take staff time and resources away from other
projects. For example, the energy commission is required to notify
by mail parties and agencies involved in the application review
21
at least 10 days in advance of a workshop, and it must also prepare
agendas, organize presentations, and compile the issues to be
discussed at the meeting. Moreover, energy commission staff
must travel to and from the workshop site, which is generally
held in the city or county in which the project is to be located.
Furthermore, state regulations allow any person to become an
“intervenor,” or formal party to the application process. Interve-
nor status allows individuals or groups to request data from the
applicant, file motions, testify, and conduct cross examinations
in formal hearings. Many intervenors are environmental interest
groups or residents affected by the proposed power plant
project. For example, California Unions for Reliable Energy
(CURE) is a coalition of unions whose members construct,
maintain, and operate power plants in California. According to
CURE, it participates in the review of applications with the goal
of ensuring that California citizens, including union members,
receive the optimum environmental and economic benefits
from proposed power plants. This means that although CURE
According to one seeks full compliance with environmental requirements, it also
intervenor, its efforts seeks employment for local union workers to build, maintain,
contributed to and operate the power plants. One of the member agencies of
postponing a project for CURE, the International Brotherhood of Electrical Workers
almost two years. Union 569, stated that it believes CURE’s efforts contributed to
postponing the High Desert Power Plant Project for almost two
years until the applicant reached an agreement with the union.
In 1997, in response to a challenge by the applicant, the energy
commission issued a decision in the High Desert Power Plant
Project case stating that CURE’s participation was “undeniably
relevant” to the proceedings. According to the energy commission,
its decision was based on CURE’s goals of ensuring that future
jobs are not jeopardized by approval of power plants that harm
the environment. Since that time no one has challenged
CURE’s participation.
The Energy Commission Contributed to Delays by
Conducting Workshops Well Beyond Its 180-Day Standard
Some of the delays caused by public intervention may be the
result of the energy commission’s failure to enforce its own
standards for public workshops and requests for information.
The energy commission’s regulations generally allow 180 days
from the date an application is deemed complete for groups to
become intervenors and request additional information. Interve-
nors may request information beyond the 180 days if they can
22
demonstrate good cause. In addition, the energy commission’s
internal guidelines establish the same time frame for holding
The energy commission public workshops. However, in some cases since 1990, intervenors
contributed to delays in submitted data requests, and staff held public workshops, well
7 of the 10 applications past the 180-day standard. In fact, for 7 of the 10 applications
approved late because that were approved late, workshops were held 220 days or more
it held workshops after the energy commission determined that the application
220 days or more after it was adequate. The energy commission holds public workshops
determined the and issues data requests during the discovery and analysis
application was complete. phases in an attempt to allow parties to solicit and exchange
information and to analyze projects and its various issues.
Our consultants found two states, Connecticut and Oregon, that
use a Notice of Intent or prefiling process to give the public,
local governments, and any affected agencies an opportunity to
raise issues early in their processes. According to our consultants,
this early-warning phase, coupled with a hearing in which
parties are required to raise issues, seems to efficiently address
the conflicts and concerns of the affected parties. Once this
hearing has occurred, outside parties can no longer raise additional
issues unless they file appeals and are granted exceptions. An
examination of this model suggests that the energy commission
might benefit by more strictly enforcing its own 180-day standard.
This would limit the ability of outside parties to raise new issues
late in the application process, thus potentially freeing energy
commission staff to focus on other concerns, such as air quality.
DESPITE DELAYS CAUSED BY EXTERNAL FACTORS, THE
ENERGY COMMISSION WORKS TO MEET DEADLINES
To its credit, the energy commission did not wait for resolution
of all issues before moving forward with the processing of
applications. For example, it was able to issue its final decisions
in less than 12 months for eight applications despite the fact
that it did not receive decisions from the government agencies
involved until 218 to 330 days after the applications had been
deemed complete. Moreover, even though the local air district
for the La Paloma Generating Project did not issue its final
decision until 392 days after the application had been deemed
adequate, the energy commission was able to issue its final
decision only 14 days later.
For the eight cases just mentioned, the energy commission
developed Final Staff Assessments, held hearings and public
workshops, and worked to resolve all outstanding issues with
23
the exception of air quality while waiting for the final decisions
to be issued by the local air districts. As a result, once the local
Energy commission staff air districts made their decisions, the energy commission was
have been diligent in able to complete the application process quickly and meet the
keeping the commission 12-month standard. For applications approved since 1990, when
aware of issues causing delays occurred energy commission staff issued staff reports on a
delays in the approval monthly basis, held update meetings periodically, and kept the
of applications. energy commission aware not only of issues causing delays, but
also of issues that had the potential to cause delays. We also
found that the energy commission acted to keep projects on
schedule by holding data resolution workshops, convening
formal meetings, and issuing scheduling orders to the applicant.
THE WITHDRAWAL OF SOME APPLICATIONS HAS NOT
SIGNIFICANTLY AFFECTED THE ENERGY COMMISSION’S
TIMELY CONSIDERATION OF RECENT PROJECTS
Since 1990 the energy commission has devoted staff time to
13 projects that were ultimately withdrawn by the applicants,
3 projects that were never constructed, and 1 project that is
currently stalled. Nonetheless, except for one application, these
projects do not appear to have seriously affected the commission’s
ability to approve recent applications within the required time
frame. Five of the projects were withdrawn prior to 1997 and
thus had no effect on more recent applications. As shown in
Table 3 on the following page, of the eight applications withdrawn
after August 1999, six were withdrawn early in the siting process. A
seventh application was ultimately refiled by the applicant.
The eighth application withdrawn after August 1999 did use
some of the energy commission’s time and resources for more
than one year. When the applicant first submitted its application
on March 8, 2000, the energy commission found the data to be
sufficient in only 2 of the 20 technical areas and requested that
the applicant submit supplemental information. However, the
applicant did not submit this information until more than two
months after the request. Eventually, on August 9, 2000, the
energy commission found the application complete. Subsequently,
the energy commission submitted to the applicant over 180 data
requests in various areas including air quality, traffic, transporta-
tion, environmental justice, and public health. According to the
energy commission, the applicant did not file adequate responses
for the first set of data requests—it was up to six weeks late on
some responses—and the applicant objected to some of the
staff’s second-round requests. Furthermore, the applicant did not
24
25
TABLE 3
The Energy Commission Generally Spent Minimal Time Processing Recently Withdrawn Applications
Date
Application Application Date Months from Months from
Applicant and File Deemed Reason for of File Date to Adequacy to
Project Name Date Adequate Withdrawal Withdrawal Withdrawal Withdrawal
Duke Energy North America— 8/31/99 N/A Duke withdrew its application to accommodate the 10/27/99 1.9 N/A
Morro Bay Modernization City of Morro Bay’s request for additional time to
and Replacement Project conduct further analysis prior to the data adequacy
hearing. Duke refiled a new application on
October 23, 2000, which is currently under review.
Em-One Power Station, LLC— 3/8/00 8/9/00 Em-One asked to suspend the project until 3/12/01 12.3 7.2
Nueva Azalea Power September 2001 to consider other options for a
Plant Project successful siting of this project because South Gate
residents voted against a measure to construct a
power plant in their city.
Calpine c* Power— 10/10/00 10/31/00 Calpine did not disclose why it decided not to 11/14/00 1.2 0.5
Silicon Valley pursue this project.
Power Scott Substation
Calpine c* Power—San Mateo 10/10/00 10/31/00 Calpine did not disclose why it decided not to 11/6/00 0.9 0.2
Substation Peaking Project pursue this project.
Calpine c* Power—Martin 10/10/00 10/31/00 Calpine did not disclose why it decided not to 11/6/00 0.9 0.2
Substation Peaking Project pursue this project.
Calpine c* Power—Newark 10/10/00 10/31/00 Calpine did not disclose why it decided not to 11/6/00 0.9 0.2
Substation Reliability pursue this project.
Generation Project
Calpine c* Power—Eastshore 10/10/00 N/A Calpine did not disclose why it decided not to 10/20/00 0.3 N/A
Substation Reliability pursue this project.
Generation Project
Calpine c* Power—Warnerville 10/10/00 10/31/00 According to the energy commission, Calpine 12/5/00 1.9 1.2
Substation Reliability proposed this power plant on private property and
Generation Project did not obtain permission from the site owner. In
addition, Stanislaus County identified the property
as protected under the California Land Conservation
Act of 1965. Calpine decided not to pursue the issue.
Source: Energy Commission Application Database and Docket Unit.
N/A = Not applicable.
submit the necessary information promptly to the air quality
management district to allow the air district to complete its
review. This further delayed the energy commission’s issuance of
its preliminary assessment. Finally, on March 12, 2001, the
applicant requested that the energy commission suspend its
application for up to six months because residents near the
proposed site had voted against the measure to build a power
plant in their city. At that time, the energy commission still had
some outstanding issues with the application and had not yet
approved it. State regulations allow the energy commission to
terminate an application if it finds the applicant has failed to
pursue an application with due diligence. However, in this case
the energy commission chose to continue to process the applica-
tion for more than a year, even though the applicant seemed
reluctant to respond appropriately to data requests.
Three additional projects were never constructed even though
the energy commission approved them, and a fourth project is
currently stalled. According to the energy commission, one
project was not constructed because the city and county of
San Francisco did not approve the company’s lease due to public
opposition. The city and county of San Francisco is also blocking
the construction of a more recently approved project. In another
instance, the company applying declared bankruptcy soon after
the energy commission approved its application. Although the
processing of these applications certainly required the energy
commission’s time and resources, three of the four were approved
prior to April 1996. Therefore, they had little or no bearing on
the commission’s ability to review and approve applications
submitted during the last four years.
RECOMMENDATIONS
To encourage applicants to submit sufficient data in a timely
manner, the energy commission should exercise its authority to
terminate applications when the applicant does not appropriately
respond to requests for data.
The energy commission should also more strictly enforce its
standards that limit the time allowed for intervenors and other
agencies to raise new issues and submit data requests to 180 days
from the date the energy commission accepts the application.
Additionally, the Legislature should consider establishing a firm
180-day deadline for intervenors to raise issues and submit
data requests. (cid:1)
26
CHAPTER 2
Although the Energy Commission’s
Process for Approving Applications
Is Slower Than Those of Some
States, Recent Changes May Improve
the Process
CHAPTER SUMMARY
T
he process that the State Energy Resources Conservation
and Development Commission (energy commission) uses
to approve Applications for Certification (applications) for
power-generating facilities has come under scrutiny recently
because of the current energy crisis in California and the ensu-
ing desire to quickly increase the number of such facilities
throughout the State. The rolling blackouts that occurred during
January and March of this year throughout much of California
fueled the concern that delays in siting new plants under the
energy commission’s existing process may have contributed to
the crisis. However, while the immediate need to approve and
construct additional power plants focused attention on the
energy commission’s application process, we do not believe that
the existing process is unreasonable or that it has played a
significant role in California’s current power shortage. Moreover,
because the energy commission has approved 13 new power
plants with a total generating capacity of 9,024 megawatts
(MW), currently scheduled to go on-line between July 2001 and
January 2004, minor delays in approving applications may be
even less critical in the future.
Our consultants surveyed the process for approving applications
in five other states and found that California’s process is similar
to those used in four of the five states. They also found that the
energy commission takes longer to approve applications than
three of these four states. However, if we exclude three projects
that were delayed due to significant emissions concerns raised
by the Federal Environmental Protection Agency (EPA), the
average time for the energy commission to process an application
27
from receipt to approval decreases from nearly 17 months2 to
15 months, only 1.5 months longer than the 13.5 months that
state law generally allows. Additionally, a comparison of the
energy commission’s siting process to equivalent processes in
California demonstrates that it is more efficient.
In response to the current crisis, the energy commission has also
implemented three expedited siting processes aimed at providing
new generating capacity in the short term until the larger power
plants currently under construction come on-line. Although we
were unable to evaluate the effectiveness of the 6- and 4-month
processes because only one application has been approved under
either of these, the energy commission has approved 11 projects
under the emergency siting (21-day) process, which is used to
approve power plants that produce electricity during peak load
times and can be operational by September 30, 2001. Ten of
these “peaker plants”—one project has since been withdrawn—
are scheduled to be completed by the end of September, providing
more than 850 additional megawatts, enough power to supply
roughly 850,000 homes.
ALTHOUGH THE ENERGY COMMISSION MAY TAKE
SLIGHTLY LONGER TO APPROVE APPLICATIONS, ITS
PROCESS IS COMPARABLE TO THOSE OF OTHER STATES
In order to determine the reasonableness of the energy
commission’s process for approving applications, we hired
consultants to study the procedures used in five other states: Texas,
Oregon, Connecticut, Florida, and Minnesota. As shown in Table 4
Four comparable states on the following page, our consultants found that, with the
required an average of exception of Texas, the processes these states follow are compa-
between 7 and 30 months rable to those employed by the California energy commission.
to review and approve The four comparable states required an average of between 7 and
applications. 30 months to review and approve applications, while the energy
commission spent an average of nearly 17 months reviewing the
23 applications that it has approved since 1990. However, if we
2 This 17-month average differs from the 14-month average discussed in Chapter 1
because it measures the application process from the moment an application was first
submitted to the siting office until it was approved, including the time necessary to
determine whether the application was complete. On average, the energy commission
takes 2.5 months to deem an application complete, although the statutory limit is 45
days. This alternative average was necessary in order to perform a reasonable
comparison to other states.
28
TABLE 4
The Energy Commission’s Application Process Is Comparable
to Some Other State’s Processes
Activity California Oregon Minnesota Connecticut Florida Texas*
Comparable 12-month 12-month 12-month 6-month 14-month No statutory
Statutory process process† process process† process timeline
Timeline
Prefiling/Notice Prefiling review— Notice of Intent N/A Prefiling review— Optional N/A
of Intent Phase Optional approximately 60 days Notice of Intent
for Approving 6 months‡ approximately
Applications 6 months§
Application Filing
Determination of Reviews application No mandated Environmental Reviews Reviews No mandated
Completeness of for completeness. time period Quality Board application for application for time period for
Application for review. advises applicant completeness. completeness. review.
of deficiencies.
Public Hearings, Staff files data request, Holds public Holds public Holds at least one Agency files Issues public
Siting, and Other holds public meetings/ hearings, meetings public hearing statements notices, conducts
Agency Reviews workshops, and conducts issues draft and drafts and can schedule of issues technical review,
analysis focusing on proposed order, environmental additional hearings and holds and responds to
environmental impacts conducts reviews, impact statement. as needed. Council hearings. Staff comments by
and mitigation measures. and consults with Administrative records must issues written executive director.
Applicants respond other agencies law judge remain open for analysis.
to data requests. Staff on proposed holds contested public comment Administrative
files Final Staff site certificate case hearings for several law judge
Assessment. conditions. and issues weeks after first holds hearing.
report. public hearing.
Proposed Energy commission Hearing officer For remainder of Department of If executive
Decision committee (two issues proposed the six months, the Administrative director
members of the order and holds council deliberates Hearings issues recommends
commission) holds contested case in publicly recommended hearings, the
hearings and files hearing. announced order. administrative
proposed decision. meetings. law judge presides
and makes
recommendations.
Final Energy commission Energy Facility Environmental Connecticut Siting Siting Board Texas Natural
Decision renders decision. Siting Council Quality Board Council renders renders Resource
renders decision. renders decision. decision. decision. Conservation
Commission grants
air quality permit.
Post-Decision Files decision with Any appeal Department of
Activity State Register must be filed Environmental
within 30 days. within 15 days Protection
after decision. must issue air
permit within
30 days after
certification.
Sources: Energy Commission; National Conference of State Legislatures.
* The Texas Natural Resource Conservation Commission’s authority is limited to reviewing applications for the purpose of granting air
quality permits during the application process.
† Oregon and Connecticut do not include their Notice of Intent and prefiling periods within their respective 12- and 6-month processes.
‡ According to the Oregon Office of Energy, this is an estimate rather than a mandatory time frame.
§ According to Florida’s siting office, no applicant has opted to use this step in the last 10 years.
N/A = Not applicable.
29
omit from this average three projects that involved significant
emissions concerns raised by the EPA and the public, the energy
commission’s average time to approve applications would be
reduced to 15 months.
In terms of the procedures followed, the energy commission’s
power plant siting process is generally equivalent to those used
in four of the five states our consultants reviewed. As shown in
Table 4, the siting procedures for nearly all of the states include,
in varying forms, a review of applications to determine their
completeness, analyses of the applications by agency staff, and
hearings to certify the projects. Most of the states are committed
to siting power plants quickly while minimizing their impact on
the environment, and all require that their procedures create
opportunity for public participation.
Despite these important similarities, some differences between
the states do exist. For instance, unlike California, Oregon and
Connecticut require a Notice of Intent or prefiling stage before
applications are filed. According to the Oregon and Connecticut
siting offices, this allows affected parties to resolve potential
conflicts early in the siting process. In addition, the timing of
the specific phases of the process differs in each state as does the
length of time allotted for the various steps of the process.
Unlike the other states our consultants surveyed, the Texas
Natural Resource Conservation Commission (TNRCC) plays a
limited role in siting power plants. TNRCC, which receives its
authority from the State Legislature, is responsible for reviewing
power plant applications for the purpose of granting air quality
and water rights permits. Like California, Texas holds public
Texas’s review during the comment proceedings and conducts technical reviews focusing
application period on industrial and scientific aspects of the project; however, Texas’s
extends primarily to air review during the application period extends primarily to air
quality, whereas quality, whereas California reviews 20 technical areas, including
California reviews 20 land use, biological resources, and traffic and transportation.
technical areas. According to TNRCC, other technical reviews beyond air quality
and water rights may be covered by the Texas Public Utility
Commission. As part of its air quality permit review, TNRCC
evaluates the proposed facility design to ensure that the proposal
does not exceed allowable emissions. TNRCC also performs
limited reviews of public health concerns to demonstrate com-
pliance with National Ambient Air Quality Standards. In addition
it reviews whether hazardous materials are used in the project
and, if used, it ensures that such materials are stored properly
and that emissions are minimized.
30
According to TNRCC, once a Texas developer obtains its air
quality permit, it can begin construction; however, developers
also need to obtain a water rights permit prior to operating.
Obtaining this permit from TNRCC can take an additional four
to six months, but power plant developers tend to contract
water from existing water rights permits, which is usually faster,
according to TNRCC. Additionally, Texas developers are respon-
sible for obtaining all other necessary state and federal permits
by the time the power plant has been constructed. Despite the
obvious difficulties in comparing Texas’s siting procedures to
California’s, we believed it was important to include Texas in our
survey to show that it has very different laws and regulations
governing the approval processes, which can drastically affect
the time needed to approve power plants.
In comparing the efficiency of application processes, we found
that California’s average approval time was longer than that of
any of the four comparable states surveyed except for Oregon’s.
As Table 5 shows, the average length of time necessary for the
energy commission to approve a power plant is nearly 17 months.
TABLE 5
The Energy Commission Certifies Power Plants in an
Average of Nearly 17 Months, Which Is Slower Than Three
of the Four Comparable States Surveyed*
In Months
Number of Shortest Longest Average
Power Plants Approval Approval Approval
State Sited Since 1990 Time Time Time Median†
Minnesota 3 6 8 7 7
Connecticut‡ 5 7 10 9 9
Florida 14 9 24 15 14
California§ 23 5 35 17 15
Oregonll 4 23 37 30 31
Sources: Energy Commission Application Database; National Conference of
State Legislatures.
* Because the Texas Natural Resource Conservation Commission’s power plant
application process differs significantly compared to the other states surveyed, we did
not include its application approval times.
† Median represents the middle number in the range of months.
‡ Includes prefiling phase.
§ The average shown here includes the time it took the energy commission to deem the
application data adequate.
ll Includes Notice of Intent phase.
31
However, it is important to note that three of the projects
included in the average involved serious air emissions concerns.
If we omit these three projects from the average, the energy
commission’s average approval time decreases to 15 months,
which is only 1.5 months slower than its standard 13.5-month
process. The three projects—High Desert, Three Mountain, and
Sunrise power plants—took 35, 27, and 24 months, respectively,
to certify.
As indicated in Table 5, Oregon requires the longest time to
approve its applications, in part because its Notice of Intent
process appears to lengthen its average approval time by
13 months. Oregon does not have a mandatory time frame for
this phase, during which it serves notice to the public and
agencies of the pending power plant development and begins its
own review preparations, as discussed earlier. According to
Oregon, the Notice of Intent phase, combined with limits on the
time during which intervenors are allowed to raise issues, have
enabled it to certify applications within mandated deadlines
once they are filed. However, the energy commission manages
to hold the same public information meetings while still
having an approval process that is 13 months faster on average
than Oregon’s.
According to our consultants, Texas, Minnesota, Connecticut, and
The energy commission’s Florida have approved power plant applications more quickly than
siting process is the energy commission. Although Texas approves applications in
significantly faster than an average of nine months, its approval requirements are quite
those processes used in dissimilar to California’s, as we mentioned previously. According
California for to Minnesota’s siting office, the three power plants it approved
other environmentally since 1990 were sited with relative ease and little public opposition
sensitive projects. because they were natural gas-fired, the plants created only a
small footprint, and the last two were not located near any
population centers. Florida’s average application process is
15 months, which is only minimally faster than California’s.
Our consultants were unable to identify a specific overriding
reason why Connecticut’s process is faster than California’s, but
as we discussed in Chapter 1, the reasons for delays in
California’s process are complicated and often caused by entities
other than the energy commission. Furthermore, although
California approved applications slower than other states, the
energy commission’s siting process is significantly faster than
those processes used in California for other environmentally
sensitive projects, as we discuss in the next section.
32
THE ENERGY COMMISSION’S SITING PROCESS
PROVIDES FOR A MORE TIMELY REVIEW OF
APPLICATIONS THAN EQUIVALENT STATE PROCESSES
A comparison of the energy commission’s approval process to
equivalent processes in the State suggests that the energy
commission’s process is reasonable. Whereas state regulations
generally require the energy
commission to approve applications
The Criteria Necessary to Be a within 12 months after deeming them
“Certified Regulatory Program” complete, the California Environmental
Quality Act (CEQA) and Permit
(cid:127) The program must require an “interdisciplinary approach that
will ensure the integrated use of the natural and social Streamlining Act (PSA) allow up to
sciences in decision making.”
24 months for the approval of other
(cid:127) The program must include “protection of the environment
types of projects that have a similar
among its principal purposes.”
environmental impact. CEQA requires
(cid:127) The enabling legislation of the regulatory program must
authorize the agency to “adopt rules and regulations for the California’s public agencies to perform a
protection of the environment, guided by standards set forth review of all new projects that may have
in the enabling legislation.”
a physical impact on the environment
(cid:127) The agency’s regulations must require that “an activity will
in order to identify the significant
not be approved or adopted as proposed if there are feasible
alternatives or feasible mitigation measures available which environmental effects of their actions
would substantially lessen any significant adverse effect which
and either avoid those effects or
the activity may have on the environment.”
mitigate them, depending upon what is
(cid:127) The regulations must include “guidelines for the orderly
evaluation of proposed activities and the preparation of the most feasible. PSA—which is
plan or other written documentation in a manner intertwined with CEQA—requires public
consistent with the environmental protection purposes of the
regulatory program.” agencies to follow standardized time
limits and procedures for specified types
(cid:127) The agency’s regulations must require the agency to consult
with “all public agencies which have jurisdiction, by law, with of land use decisions. Because the
respect to the proposed activity.”
California Government Code states that
(cid:127) The agency’s regulations must require that the final action
PSA does not apply to activities of the
include “written responses of the issuing authority to
significant environmental points raised during the evaluation energy commission, the energy
process.”
commission is exempt from these time
(cid:127) The agency’s regulations must require filing a notice of the limits. Moreover, because the Secretary
final decision with the Secretary of the Resources Agency.
of the Resources Agency approved the
(cid:127) The agency’s regulations must require notice of the agency’s
energy commission’s standard
written documentation to the public and to any person who
requests notification in writing. application process as a certified
(cid:127) The written documentation must include a “description of regulatory program, its process is
the proposed activity with alternatives to the activity, and considered equivalent to CEQA’s, and it
mitigation measures to minimize any significant adverse
effects on the environment of the activity.” Second, the is faster.
agency’s documentation must be “available for a reasonable
time for review and comment by other public agencies and
the general public.” The energy commission is able to
approve projects in 12 months instead
Source: Public Resources Code. of 24 because it combines many of the
activities that are performed
consecutively under CEQA and PSA, and
its process reduces the number of
33
documents prepared. As shown in Figure 3 on the following
page, the energy commission’s process includes the steps
necessary to satisfy the intent of CEQA and PSA, including the
performance of significant environmental reviews and
independent analyses. However, the energy commission is not
required to prepare environmental impact reports when
reviewing applications as long as its process meets certain criteria,
and it is allowed to combine certain analyses that in the CEQA
process must be presented separately.
In July 2000, in response to a legislative mandate, the Secretary
of the Resources Agency reviewed the energy commission’s
application process to ensure that it continued to meet the
requirements necessary to qualify as a certified regulatory program.
In December 2000 the Secretary of the Resources Agency con-
cluded that it did meet these criteria and continued the original
certification. Because the energy commission’s siting process
accomplishes the critical objectives of CEQA and PSA in less
time, we believe that continued exemption from the specific
requirements of CEQA and PSA is appropriate.
THE ENERGY COMMISSION’S DEVELOPMENT OF
EXPEDITED SITING PROCEDURES MAY ALLOW FOR
FASTER APPROVAL OF APPLICATIONS
Responding to the fact that California faces potentially serious
electricity shortages over the next few years, the energy commis-
sion recently implemented three expedited siting processes of
varying lengths that it can use to quickly approve different sorts
of projects. It developed new 4-month and 21-day expedited
The energy commission processes to bring more power on-line specifically for the summer
developed two new of 2001. The 4-month process allows for the expedited approval
expedited siting processes of simple cycle facilities, and the 21-day process allows for the
with the expectation of expedited approval of plants that will produce extra electricity
adding to the State’s during peak demand times. To address concerns that construction
electricity supply by the of new power plants has seriously lagged in the past decade, the
end of September 2001. energy commission also established a 6-month certification
process for thermal plants that have no adverse environmental
impact. It remains too early to determine whether the 6- and
4-month processes will be effective, but the commission has
already approved 11 applications under the 21-day process,
although one project has since been withdrawn. It expects that
these projects will gradually add over 850 MW of electricity to
the State’s supply between July and the end of September 2001.
34
35
FIGURE 3
Comparison of the CEQA/PSA Environmental Review Process With the Energy Commission’s Application Process
Requirements of CEQA and PSA for a Full Environmental Review
(24 months)
Applicant Decision on
files application
EIR Notice of preparation for EIR* Responsible Agencies discuss Assembling EIR document Notice of Public Final EIR
determination agency response scope of EIR completion filed review period
-30 days 0 30 60 90 120 150 180 210 240 270 300 330 365 days
Responsible agencies give final approval within 180 days
Lead agency gives final approval within 180 days of certified EIR
after lead agency approval
545 725 days
Requirements of the Energy Commission's Application Process
(12 months)
Comments from local, state, or special interest
Proposed decision
Applicant Decision on Adoption hearings
files application Comment period
Final report and hearings
Information hearings Data request Energy commission commences public hearings
and site visits workshops
-45 days 0 30 60 90 120 150 180 210 240 270 305 365 days
Sources: Public Resources Code; California Code of Regulations; Energy Commission Siting Program Manual.
* Environmental Impact Report.
The Energy Commission Has Yet to Approve Any Applications
Under Its 6-Month Process
As of July 31, 2001, the energy commission had not approved
any thermal power plant projects under its 6-month expedited
process. As shown in Table 6 on the following page, developers
have filed only four applications, one of which has made it past
the first phase of the process—full completion of the application.
This may be partially due to the fact that under the 6-month
process a number of initial studies and preparations must be done
prior to filing an application. These same studies are completed
after an application is filed under the 12-month process, which
many developers may prefer.
The energy commission developed its 6-month expedited process
to comply with Assembly Bill 970 (AB 970), which was passed in
response to concerns that efforts to construct new power plants
have seriously lagged in the past decade. Taking effect in
September 2000, the legislation directed the energy commission
to establish a process to issue its final certification for any
thermal power plant and related facilities within six months
after it had deemed the application complete. To achieve this
goal, the legislation directed that the certification should take
place based on an initial review in which the applicant demon-
strated substantial evidence that the project would not cause
significant adverse impacts on the environment or the electrical
system—including transmission lines—and would comply with
all federal, state, and local laws and regulations.
The energy commission designed its current 6-month process in
The requirements of the order to meet these directives. However, the terms of the new
new 6-month application procedures may be acting as a deterrent to developers. Because
process may be too an application filed under the 6-month process must demonstrate
cumbersome for up front that the project will not cause significant adverse
developers, as evidenced impacts, it must contain, among other things, a detailed analysis
by the limited number of of the effects of pollutants, toxic substances, and hazardous
applications filed. materials specific to the project and how they can be mitigated;
studies identifying impacts to the electrical system as well as to all
interconnected facilities; and information concerning how the
project will affect various populations. This is all information that
is normally prepared during the course of the 12-month process.
According to energy commission staff, the preparation of these
reports prior to the filing of an application is necessary in part to
ensure that the information is available in time for other agencies
to provide their comments, opinions, and determinations by the
36
TABLE 6
The Energy Commission Approved More Applications Under the 21-Day Expedited
Process Than the 6- and 4-Month Processes Combined
(As of July 31, 2001)
Application Duration of
Found Decision Approval
Project Name Megawatts Complete Date On-line Process (Days)
6-Month Process
Under Review
Southern California Public Power Authority— 250.0 * † Nov-2003
Magnolia Power Project
Calpine/Bechtel Joint Development— 600.0 07/11/01 † Dec-2003
Russell City Energy Center
United Golden Gate Power Company, LLC— 570.0 * † Nov-2003
Golden Gate Power Plant Phase II Project
Reliant Energy—Colusa Power Plant Project 600.0 * † Jul-2004
Total Megawatts 2,020.0
4-Month Process
Approved
El Paso Merchant Energy— 51.0 10/25/00 03/07/01 ‡ 133
United Golden Gate Power Project Phase I
Under Review
Ocotillo Energy, LP—Ocotillo Energy Project Phase I 456.0 06/22/01 † Jun-2002
Valero Refining Company—Valero Cogeneration Project 102.0 * † Apr-2002
Calpine Corporation—Gilroy Energy Center Phase ll 135.0 * † Jul-2004
Total Megawatts 744.0
21-Day Process
Approved
Wildflower Energy, LLP/InterGen—Larkspur Energy Facility 90.0 03/16/01 04/04/01 Jul-2001 19
Wildflower Energy, LLP/InterGen—Indigo Energy Facility 135.0 03/16/01 04/04/01 Jul-2001 19
RAMCO, Inc.—Chula Vista Power Project 62.4 05/21/01 06/13/01 § 23
Alliance Colton, LLC—Alliance Century 40.0 04/06/01 04/25/01 Aug-2001 19
Alliance Colton, LLC—Alliance Drews 40.0 04/06/01 04/25/01 Aug-2001 19
Calpine Corporation–King City Peaker Project 50.0 04/11/01 05/02/01 Sep-2001 21
GWF Power Systems Company, Inc— 95.0 04/12/01 05/10/01 Aug-2001 28
Hanford Energy Park Peaker
Calpine Corporation—Calpine Gilroy Phase l 135.0 05/01/01 05/21/01 Sep-2001 20
Pegasus Power Partners, LLC—Pegasus Power Project, Chino 180.0 05/11/01 06/06/01 Sep-2001 26
CalPeak Power, LLC—CalPeak Escondido 49.5 05/17/01 06/06/01 Sep-2001 20
CalPeak Power, LLC—CalPeak Border 49.0 06/20/01 07/11/01 Sep-2001 21
Total Megawatts 925.9
Filed, but Withdrawn
Electricity Provider, Inc.—Lancaster Energy Facility ll
Evergreen Power Company— ll
Evergreen Concord Peaking Facility
CENCO Electric Company—CENCO Electric ll
Source: Energy Commission Power Plant Status Worksheet as of July 2001.
* An application has been submitted but the energy commission has not yet deemed it complete.
† The energy commission has not yet made a decision on this application.
‡ Construction is currently stalled due to site control issues with the city and county of San Francisco.
§ This project has been suspended due to financial issues.
ll Application has been withdrawn but applicant intends to file under the 4- or 6-month process.
37
required 100-day deadline. In fact, one developer expressed a
preference for participating in the 12-month process rather than
making the necessary investments required by the 6-month
process. In any event, the limited number of applications filed
under the 6-month process make it too early to determine
whether these procedures will be effective in allowing the energy
commission to approve new power plants in less time.
Due to Severe Time Constraints, the Energy Commission’s
4-Month Expedited Siting Process Has Yielded Only One
Approved Project
When the Legislature passed AB 970, which created the 6-month
approval process, it also directed the energy commission to
implement a 4-month process in an attempt to bring additional
simple cycle thermal power plants on-line by August 1, 2001.
Applications are eligible for the 4-month approval process if the
proposed project is not a major stationary source or modification
to a major source of power, it will be equipped with the best
available control technology, and it will not have a significant
adverse impact on the environment. However, the energy
commission has received only a small handful of applications
from developers who want to push their projects through the
4-month process.
The 4-month process originally applied only to those developers
able to file complete applications or amendments to pending
applications by the end of October 2000. Although developers
managed to submit applications for seven projects by the October
deadline, six of these seven applications were withdrawn. Accord-
ing to the deputy director of the energy siting division, the
severe time constraints imposed by the deadline limited the
success of these applications. The seventh application was
determined to be complete on October 25, 2000, and was given
Since the deadline to final approval by the energy commission on March 7, 2001. The
submit applications total approval time was 133 days, only 13 days longer than the
under the 4-month required 4 months. However, according to the energy commission,
process was extended, the unresolved issues with the city and county of San Francisco have
energy commission has stalled the construction of this plant, which has no expected
received three additional on-line date.
applications with up to
26 other projects either Senate Bill 28 of the 2001-2002 First Extraordinary Session—which
announced or planned. became effective on May 22, 2001—extended the deadline for
4-month projects, requiring them to be put into service on or
before December 31, 2002. As of July 2001 the energy commission
38
had received three additional applications for the 4-month
process, with up to 26 more projects either announced or
planned. Apparently, developers are seeing some advantages to
the 4-month process, although it is still too early to tell how many
projects will be approved. Until more 4-month applications are
approved, it is difficult to determine the effectiveness of the
4-month process.
Peaker Plants Approved Under the Energy Commission’s
21-Day Expedited Process Will Soon Boost the State’s
Electricity Supply
In response to rolling blackouts and numerous stage 3 energy
alerts, Governor Davis declared an energy emergency in
January 2001, allowing the energy commission to implement its
emergency siting process and exempting projects from CEQA.
Ten peaker plants are This allowed for a quicker process to permit the construction of
expected to be on-line by peaker plants that could be on-line by July 31, 2001, a deadline
September 30, 2001, later extended to September 30, 2001. Peaker plants are used to
adding over 850 MW to produce extra electricity during peak load times. Many more
the State’s electricity power plant applications have been filed and approved under
supply. the energy commission’s 21-day siting process than under the
6- and 4-month processes combined. Although these power
plants are generally small, 10 are expected to add over 850 MW
to the State’s electricity supply by September 30, 2001.
The energy commission was able to implement the 21-day
process by identifying project sites in advance, thus removing
the need to determine site acceptability on a case-by-case basis.
As requested by the governor, the energy commission issued a
report in February 2001 detailing 33 potential sites throughout
the State that would make appropriate peaker plant locations.
The energy commission expects that some of these projects will
be temporary, removed after three years. Others will remain as
permanent peaking facilities or will be converted into combined
cycle or cogeneration power plants. Permanent or converted
facilities will need to be recertified by the energy commission or
demonstrate that they meet certain criteria.
As shown in Table 6 on page 37, 8 of the 11 applications that
have been approved under the new process were completed by
the 21-day deadline, with 6 actually approved in less than 21 days.
Of the three that exceeded the deadline, one project took
23 days, while the other two took 26 and 28 days. Thus, the
majority of the approved projects have been successful at meet-
ing the 21-day timeline, with only a few taking slightly longer.
39
Moreover, the energy commission has stated that all of the
projects are on schedule to be completed by September 30, 2001,
when they should add more than 850 MW to the State’s electricity
supply. Two of the projects, totaling 225 MW, became operational
in July, and another three projects totaling 175 MW are due on-
line by the end of August. As a result, the peaker plants recently
approved by the energy commission—if brought on-line as
planned—will add a needed boost to the State’s electricity supply
this summer.
RECOMMENDATION
To ensure that it is successful at approving new power plants in
less time, the energy commission should evaluate the effectiveness
of the expedited 6- and 4-month processes and determine their
long-term viability after an appropriate amount of time has
elapsed.
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
Date: August 20, 2001
Staff: Denise L. Vose, CPA, Audit Principal
Steven A. Cummins, CPA
Anna K. Escuadro
Robert A. Hughes
Celina M. Knippling
40
Agency’s comments provided as text only.
CALIFORNIA ENERGY COMMISSION
WILLIAM J. KEESE, CHAIRMAN
1516 NINTH STREET–MS 32
SACRAMENTO, CA 95814-5512
Telephone (916) 654-5000
Telefax (916) 653-3478
August 6, 2001
Ms. Elaine M. Howle
State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
RE: AUDIT REPORT ON THE ENERGY COMMISSION’S SITING PROCESS
Dear Ms. Howle:
Thank you for the opportunity to review the report entitled “California Energy Commission:
Although External Factors Have Caused Delays in Its Approval of Sites, Its Application Process Is
Reasonable,” resulting from your audit of the Energy Commission’s siting process. We do not
have any significant concerns with the report. We feel it accurately portrays the complex issues
that influence the time required to review energy facilities under the Commission’s jurisdiction. It
also responds to the questions left unanswered by the previous audit.
I would also like to express my appreciation for the thorough work and professional behavior of
your staff. They performed a complete review of the details associated with the siting cases,
interviewed numerous members of the Energy Commission and other organizations, and attended
several hearings and workshops to gain first-hand knowledge of how the process works.
Please let us know if you or your staff have any additional questions on the Commission’s
siting process.
Sincerely,
(Signed by: William J. Keese)
WILLIAM J. KEESE
Chairman
41
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California State
Government Organization and Economy
Department of Finance
Attorney General
State Controller
State Treasurer
Legislative Analyst
Senate Office of Research
California Research Bureau
Capitol Press
42