Seismic Retrofit Costs of State-Owned Toll
Bridges Have Significantly Exceeded the
Department’s Original Estimates and May
Go Even Higher
August 2002
2001-122
rotiduA
etatS
ainrofilaC
S
T
I
D
U
A
E
T
A
T
S
F
O
U
A
E
R
U
B
The first five copies of each California State Auditor report are free.
Additional copies are $3 each, payable by check or money order.
You can obtain reports by contacting the Bureau of State Audits
at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
The California State Auditor is pleased to announce
the availability of an online subscription service.
For information on how to subscribe, please contact
David Madrigal at (916) 445-0255, ext. 201, or
visit our Web site at www.bsa.ca.gov/bsa
Alternate format reports available upon request.
Permission is granted to reproduce reports.
� � �
��������� ���� ������
������������� �������������������
������������ �����������������������
August 1, 2002 2001-122
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its audit report
concerning the California Department of Transportation (Caltrans) and the Metropolitan Transportation
Commission (MTC) to examine the delays and higher cost estimates for the seismic upgrades of toll
bridges in the Bay Area.
This report concludes that the seismic retrofit costs of state-owned toll bridges have significantly
exceeded Caltrans’ original estimates for many reasons; however, the largest contributor is the east span
replacement of the San Francisco-Oakland Bay Bridge with an estimated cost increase of $1.3 billion.
Overall, the program was likely to experience such increases because statute allows the Bay Area to
purchase a more expensive east span replacement than Caltrans originally envisioned and estimated for.
This statute also requires that bridge users fully fund the cost increase with the seismic retrofit surcharge
imposed for passage on all Bay Area toll bridges. Caltrans also recognizes that the lack of including
escalation rates in most of its estimates played a role in the understatement of estimated costs in the
initial legislation. Additionally, external parties delayed project progress and subsequently increased
costs. Although Caltrans maintains that its current funding is sufficient to cover estimated program costs,
recent information suggests that Caltrans may need additional funding.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
�������������������
�������������������������������������������������� ���������������������������������������� ������������������
CONTENTS
Summary 1
Introduction 5
Chapter 1
Various Factors Have Led to Significant
Cost Increases and Time Delays in Retrofitting
the Bay Area Toll Bridges 13
Chapter 2
Due to Remaining Uncertainties, the Potential
Still Exists for Costs to Exceed Funding Levels 31
Appendix A
Detailed Cost Estimate Variances Between
Senate Bill 60 and Assembly Bill 1171 for the
Toll Bridge Seismic Retrofit Program 39
Appendix B
Timeline of Major Decisions Affecting the
Toll Bridge Seismic Retrofit Program 43
Responses to the Audit
Business, Transportation and Housing Agency
Department of Transportation 45
Metropolitan Transportation Commission 49
California State Auditor’s
Comments on the Response
From the Metropolitan
Transportation Commission 51
SUMMARY
RESULTS IN BRIEF
Rising costs and time delays plague the State’s efforts to
complete seismic retrofitting of selected toll bridges. To
ensure maximum public safety and the continuous opera-
tion of the State’s transportation network in the event of a major
Audit Highlights . . . earthquake, the California Department of Transportation (Cal-
trans) determined that six state-owned toll bridges need seismic
Our review of the California
retrofitting, and one other needs a partial retrofit and a partial
Department of Transportation
replacement. Initial estimates prepared by Caltrans set costs at
(Caltrans) and the
Metropolitan Transportation $2.6 billion, with work to be completed by 2004; however, its
Commission (commission) current estimates increase these costs to $4.6 billion and delay
to examine the delays and
project completion until 2009. The estimated $2 billion increase
higher cost estimates for the
in cost and the 5-year time delay occurred for many reasons, but
seismic upgrades of Bay Area
toll bridges revealed that: the replacement of the San Francisco-Oakland Bay Bridge (Bay
Bridge) east span is the largest contributor with an estimated
þ Efforts to seismically
cost increase of $1.3 billion.
retrofit the toll bridges
have resulted in
significant cost increases Overall, the program was likely to experience increases to its
and time delays.
cost estimates because the initial legislation passed to aid in
þ The estimated $2 billion financing retrofit efforts allows the Bay Area to purchase a
increase in cost occurred more expensive “signature” east span for the Bay Bridge than
for several reasons; Caltrans originally envisioned and estimated for. Figure 4 on
however, the east span
page 20 shows the chosen signature bridge for the east span
replacement of the
San Francisco-Oakland and labels some of the significant features. The Metropolitan
Bay Bridge is the largest Transportation Commission (commission)—the regional
contributor with an
transportation planning, coordinating, and financing agency
estimated cost increase
for the Bay Area—has the authority to choose the bridge
of $1.3 billion.
replacement for the east span, including the ability to select
þ The program was likely to amenities not included by Caltrans.
exceed its initial estimates
because legislation
Although legislation allows for the purchase of a different and
allowed the Bay Area to
select a more expensive more expensive bridge, it also requires that the commission
replacement for the east fully fund any chosen amenities, such as a bicycle/pedestrian
span than envisioned
path, with the seismic retrofit surcharge equal to $1 per
by Caltrans.
vehicle imposed for passage on all Bay Area toll bridges
continued . . . (seismic surcharge). Partially based on initial cost estimates,
the commission extended the seismic surcharge, originally
imposed for no longer than 10 years, for 2 years to pay for these
additional amenities and to generate a pool of reserve funds for
future eligible projects. Later, when Caltrans updated its cost
estimates, it became clear that more funding would be needed.
1
þ Caltrans did not include Subsequent legislation, passed in 2001 to provide this
escalation rates in most additional funding, addressed the majority of the expected
of its estimates, a factor
$2 billion funding shortfall by allowing for an overall 30-year
that contributed to
extension of the original seismic surcharge, with the remaining
the understatement of
estimated costs in the funds coming from federal sources. Currently, the Bay Area toll
initial legislation. surcharge overseen by Caltrans will pay for 49 percent of the
þ A recent review by a entire toll bridge seismic retrofit program, an increase from its
consulting firm reports original 35 percent share.
the potential for an
additional $250 million
Aside from the higher cost estimates resulting from the selection
to $630 million in
of a different and more expensive Bay Bridge east span replace-
program costs.
ment, Caltrans recognizes that the lack of including escalation
þ Caltrans says that it will rates in most of its estimates played a role in the understatement
aggressively pursue cost
of cost estimates in the initial legislation. Also, the costs for the
saving measures to stay
within its existing funding Bay Bridge east span replacement increased due to both efforts
authority. by the U.S. Navy to impede test drilling on Yerba Buena Island
and a delay in the environmental review process. A few other
bridges, such as the Richmond-San Rafael Bridge, experienced
cost increases due to difficulties in estimating costs for under-
water work, and like the Bay Bridge east span replacement, the
Carquinez Bridge encountered problems with outside parties
that resulted in cost increases and time delays.
A review by a commission-hired consulting firm concludes that
program costs may go even higher than reported by Caltrans—as
much as $250 million to $630 million more. The consulting firm
based its conclusions on preliminary seismic retrofit designs
provided by Caltrans, some of which are likely to experience
additional changes. Furthermore, the consulting firm relied on a
few assumptions, including that the program would not experi-
ence any more time delays. At this time, Caltrans says it will
pursue cost-saving measures aggressively to stay within the
funding levels established by the subsequent legislation. In
addition, Caltrans explained that the consulting firm chose a
different and more costly approach to demolishing the current
east span of the Bay Bridge. However, we were able to confirm
that the consultant was correct with regard to the significant
underestimating of a time-related overhead cost. This seems to
suggest that Caltrans may need additional funding to complete
the Bay Bridge unless the contingency reserves it has planned for
the other retrofit projects are overstated. However, past experi-
ence has shown that Caltrans’ planned costs for retrofitting its
toll bridges are generally understated rather than overstated.
2 3
If costs do go higher, the subsequent legislation requires
Caltrans to acquire the additional funds of $448 million
from the State Highway Operation and Protection Program
(SHOPP), the Interregional Transportation Improvement Plan,
or federal bridge funds. Caltrans has already committed to using
$642 million from the federal bridge funds to cover earlier
estimated cost increases. It considered recommending the use of
SHOPP funds to cover overruns previously identified; however,
it indicated that doing so would require using funds already
earmarked for other projects. This particular solution would
require approval by the California Transportation Commission.
AGENCY COMMENTS
The Business, Transportation and Housing Agency and the
commission agree with the conclusions presented in our report.
In addition, the commission offered a few clarifying points
and proposed two suggestions directed toward the Legislature
for funding and reporting on future large and complex
transportation projects. n
2 3
Blank page inserted for reproduction purposes only.
4 5
INTRODUCTION
BACKGROUND
The California Department of Transportation (Caltrans) is
responsible for the design, construction, maintenance,
and operation of California’s state highway system,
and for assessing the seismic safety of all publicly owned
bridges, with the exception of those not on the state highway
system in the counties of Los Angeles and Santa Clara. The
October 1989 Loma Prieta earthquake presented Caltrans with
the task of repairing or replacing damaged highway facilities
in the San Francisco Bay Area. In addition, the State’s seismic
retrofit program, created after the Loma Prieta earthquake,
required the retrofit or replacement of all publicly owned bridges
throughout the State, including highway overpasses and other
structures, to meet the higher seismic safety standards estab-
lished after the earthquake. The seismic retrofit program requires
that Caltrans identify each bridge’s seismic vulnerabilities and
develop a retrofit project to address structural deficiencies, which
may include reinforcing bridge columns, strengthening bridge
footings, and adding redundant systems.
After reviewing all 12,000 state highway bridges, Caltrans identi-
fied 750 single- and multiple-column bridges in need of seismic
retrofit that were either the most vulnerable to a seismic event
or necessary for emergency response during a widespread civil
disaster. In addition, Caltrans determined that
7 state-owned toll bridges needed seismic retrofit-
Seven State-Owned Toll Bridges in
ting. However, repairs on these toll bridges did not
Need of Seismic Retrofitting
begin immediately because retrofit strategies for
1. Benicia-Martinez Bridge
such complex structures did not exist at that time.
2. Carquinez Bridge
3. Richmond-San Rafael Bridge Following the 1994 Northridge earthquake,
Caltrans expanded and revised its seismic retrofit
4. San Diego-Coronado Bridge
program for state highway bridges (except the toll
5. San Francisco-Oakland Bay Bridge
bridges) by implementing a two-phase retrofitting
6. San Mateo-Hayward Bridge approach. Phase 1 includes the retrofitting of the
1,039 bridges that Caltrans identified during its
7. Vincent Thomas Bridge
first screening process following the Loma Prieta
earthquake. Phase 2 includes the retrofitting of an
additional 1,155 bridges that Caltrans identified
following the Northridge earthquake. Caltrans completed the
retrofitting of the phase 1 bridges in May 2000, while work
on the phase 2 bridges is an ongoing effort. As of June 2002,
4 5
FIGURE 1
The Seven State-Owned Toll Bridges in Need of Seismic Retrofitting
���������
��
���
��
6 7
��������
���������
���������������
�
���
����
�
� � �
��
������� �� � � � � � � � � � ��
����� ��������
������
��������
��������
���
�����
��������
��
��������������
���������� ������
��� �� ��
��� �� �� �����������
�� ��������� ��������
������ ���
������ ���
�� � ��� ��� � �
���������
��� ���������������
� ��� �� ���
� ���
�� ����� ���
���������
�� �������������
������������ ��������� ������������
� ������ ���
��������� ���
��
� � ������� ��� ��
��� ������ ���
��
��� �� �� �� �� ���� � � �� ����
�� ��� ���
�� � ��
���
��� �� ���������� �� ��� ����� � � � � �
��
���
�� ��
� � �� �� ���
� � �� ��
������������ �������
���
�������
������
� ��
�� ��
���
�������
�������
�������� �� ����
�����
�
�������
������ �� ��� ������ ��������
����� �
����� � � � � � �� � � �� � � � � ��� ��� ������
�������
��������
����� ��������
���
�������� ������
Caltrans had completed the retrofi tting of 1,135 (or 98 percent)
of its phase 2 bridges. Completion of the remaining 20 bridges
is not expected until 2008 due to the more complex retrofi t
and replacement work needed on a number of these bridges.
Caltrans is managing the retrofi t and replacement strategies
for the 7 state-owned toll bridges separately from these two
phases. Figure 1 shows the location of each toll bridge in need
of seismic retrofi tting.
Following the Loma Prieta earthquake, Caltrans engaged
two universities, numerous private consulting fi rms, and the
Lawrence Livermore National Laboratory to conduct research
to better understand the seismic vulnerabilities of the toll
bridges. In the last half of the 1990s, Caltrans
began preparing a retrofi t strategy for each of
Lifeline Serviceability the toll bridges, with the exception of the east
span of the San Francisco-Oakland Bay Bridge
• Allows emergency relief access to and
(Bay Bridge). With the assistance of its seismic
through the affected region
advisory board and toll bridge peer review panel
• Connects major population centers within
(peer review panel), Caltrans recommended the
the affected region
replacement of the Bay Bridge east span to achieve
• Serves as the most effective of several
what is known as “lifeline serviceability” after an
routes for emergency relief access
earthquake. Lifeline structures are designed to
• Provides direct or nearby access to and
meet a standard greater than the typical collapse or
from major emergency supply centers
catastrophic failure standard, so that the structure
• Links various modes of transportation will continue to function after an earthquake.
• Provides access to major traffic However, to reduce the risk to Bay Area commuters
distribution centers from a moderate-level earthquake prior to the
construction of the new east span, Caltrans
completed an interim retrofi t of the existing
Bay Bridge east span in June 2000. The seismic
advisory board and peer review panel that aided in Caltrans’
replacement decision consisted of numerous experts from the
earthquake engineering, seismology, major bridge design, and
construction communities.
Funding the Seismic Retrofi tting of State-Owned Toll Bridges
Is an Ongoing Effort
To fi nance the $1.1 billion actual cost of retrofi tting the phase 1
bridges, Caltrans indicated it drew mostly from four federal
sources: highway bridge replacement and rehabilitation,
interstate maintenance, national highway system, and surface
transportation program funds. However, these same sources
could not provide suffi cient funds for retrofi tting or replacing
the phase 2 bridges or the toll bridges. Therefore, in March 1996
6 7
California voters approved the Seismic Retrofit
Funding Sources for the Toll Bridge Bond Act of 1996 (Bond Act) authorizing the
Seismic Retrofit Program
sale of $2 billion in general obligation bonds.
Proposition 192 (1996)—sets initial costs The breakout of the Bond Act funding was
at $650 million
$1.4 billion for phase 2 bridges and $650 million
for the toll bridges. However, the toll bridges
SB 60 (1997)—raises program costs
required substantially more funding, so
to $2.6 billion
Chapter 327, Statutes of 1997 (SB 60), allocated
AB 1171 (2001)—raises program an additional $2 billion, consisting mostly of
costs again, to $4.6 billion state highway funds and proceeds from a newly
created seismic surcharge equal to $1 per vehicle,
imposed for passage on all Bay Area toll bridges
(seismic surcharge). SB 60 also allocated tolls
collected on the San Diego-Coronado and Vincent Thomas
bridges to the seismic retrofit program for the toll bridges. The
total cost estimate established in SB 60 for the seismic retrofit
program was $2.6 billion. As allowed in SB 60, the Metropolitan
Transportation Commission (commission) extended the seismic
surcharge, originally set to expire no later than January 2008,
to January 2010 to pay for some amenities chosen for the
Bay Bridge east span and to generate a pool of reserve funds.
This was a 2-year extension on the 10-year maximum duration
of the original surcharge.
More recently, funding levels for the retrofitting of the toll
bridges increased again with the passage of Chapter 907, Statutes
of 2001 (AB 1171), which allocated an additional $2 billion in
Bay Area seismic surcharge proceeds and federal bridge funds
to the retrofitting effort, bringing the total funding for the
toll bridges to $4.6 billion. AB 1171 allows the commission to
request that the surcharge be extended to January 2038, subject
to the approval of the director of Caltrans, to help raise the
needed proceeds. The commission has requested and received
approval for this extension. Additionally, AB 1171 includes a
provision to make available to the toll bridges an additional
$448 million in Interregional Transportation Improvement Plan,
State Highway Operations and Protection Plan, or federal bridge
funds if it becomes necessary.
State Law Allows for the Purchase of a More Expensive
Bay Bridge East Span
In addition to providing funding for the toll bridges, SB 60
formalized the commission’s role in selecting a design for
the replacement of the Bay Bridge east span. As the regional
transportation planning, coordinating, and financing agency
for the Bay Area, the commission has the option to purchase
8 9
a few amenities for the Bay Bridge, such as a more expensive
“signature” east span and a bicycle/pedestrian path. Figure 4
on page 20 depicts the commission’s ultimate bridge selection
and labels some of the significant features. Aiding in its decision
was the Engineering and Design Advisory Panel, consisting of
technical experts in structural and civil engineering, geology,
seismology, and architectural bridge design. Although SB 60
gives the commission the authority to purchase a more
expensive bridge, it also intended that the commission fund
the cost increase with the Bay Area seismic surcharge. As we
discussed previously, the commission extended the surcharge
from January 2008 to January 2010, partially based on
preliminary cost estimates, to fulfill its responsibilities under
SB 60. Upon completion of the toll bridges, AB 1171 requires
Caltrans to turn over any remaining surcharge proceeds to the
commission for use in other projects that relieve congestion on
the toll bridges.
Caltrans’ April 2001 Annual Report to the Legislature Projects
Significant Cost Increases
In April 2001, Caltrans issued an annual report to the Legislature
and governor that detailed the rising cost estimates and project
time delays for the toll bridges in the seismic retrofit program.
The annual report contains revised cost estimates and project
completion dates, along with explanations of the anticipated
cost increases. The report shows that the Bay Bridge east span
replacement is the largest contributor to the overall projected
cost increase for the toll bridges, with an anticipated shortfall
of $1.3 billion from SB 60’s initial cost estimate. The Richmond-
San Rafael Bridge is the next largest contributor to the projected
cost increase, with a reported $336 million in expected addi-
tional costs. The additional funds provided by AB 1171 cover the
project cost increases discussed by Caltrans in its annual report.
SCOPE AND METHODOLOGY
The Joint Legislative Audit Committee (audit committee)
requested that the Bureau of State Audits review Caltrans
and the commission to examine the delays and higher cost
estimates for the seismic upgrades of toll bridges in the
Bay Area. Specifically, the audit committee requested that
we determine the roles that Caltrans and the commission
hold in planning, implementing, and managing the costs of
the retrofit and replacement projects. In addition, the audit
8 9
committee asked that we determine whether the procedures for
modifying cost estimates and completion dates are adequate,
evaluate the underlying reasons for the cost and time increases,
and determine whether the current cost estimates are based
on conditions rather than assumptions. Finally, the audit
committee asked that we examine an independent cost review
of Caltrans’ current estimates, prepared by a commission-hired
consulting firm, to identify bridge retrofit projects whose costs
were likely to be significantly higher than those currently
reported by Caltrans.
To comply with this request, we reviewed and evaluated
the laws, rules, and regulations associated with the seismic
retrofitting of toll bridges, including Chapter 327, Statutes of
1997, and Chapter 907, Statutes of 2001. Based on these statutes
and various interviews with management and engineers, we
determined the roles that Caltrans and the commission play
in planning, implementing, and managing the costs of the
toll bridge seismic retrofit program. Furthermore, we reviewed
Caltrans’ April 2001 annual report to the Legislature and
governor to identify the reasons it cites for the cost increases
and time delays in retrofitting seven state-owned toll bridges.
We selected a sample of toll bridges—the San Francisco-Oakland
Bay Bridge east span replacement, the Richmond-San Rafael
Bridge, and the Carquinez Bridge—to evaluate the reasons cited
in the annual report.
For each of the sampled bridges, with the exception of the
Bay Bridge east span replacement, we reconciled the SB 60
and AB 1171 cost estimates to identify areas with significant
increases. We did not perform this same comparison for the
Bay Bridge because the SB 60 cost estimate was not based on the
bridge currently under construction. Instead, we compared the
earliest cost estimate for the selected replacement to the
AB 1171 estimate to identify areas with significant increases.
We selected these three bridges for our sample because the
Richmond-San Rafael Bridge and the Bay Bridge are two of the
largest and least complete retrofit projects, and therefore they
have the greatest potential impact on the overall cost of the
seismic retrofitting of the toll bridges. We selected the Carquinez
Bridge because this project is nearly complete and therefore
provides a contrasting cost perspective, given that few uncer-
tainties remain.
10 11
In addition to reconciling the numerous cost estimates in the
toll bridge seismic retrofit program, we reviewed Caltrans’
policies and procedures for preparing cost estimates, including
those that relate to contingency reserves and escalation. We
also reviewed Caltrans’ procedures governing contract change
orders, since they have the potential to increase costs above
original estimates. To understand the potential for additional
cost increases above those Caltrans cites in its annual report,
we reviewed the commission-hired consulting firm’s cost review
report and interviewed one of its representatives to determine
whether it had relied on any assumptions rather than conditions
in drawing its conclusions. n
10 11
Blank page inserted for reproduction purposes only.
12 13
CHAPTER 1
Various Factors Have Led to
Significant Cost Increases and Time
Delays in Retrofitting the Bay Area
Toll Bridges
CHAPTER SUMMARY
Efforts to seismically retrofit selected California toll bridges
have resulted in significant time delays and higher cost
estimates. To ensure the safety of the traveling public,
the California Department of Transportation (Caltrans) has
determined that six state-owned toll bridges—Benicia-Martinez,
Carquinez, Richmond-San Rafael, San Diego-Coronado,
San Mateo-Hayward, and Vincent Thomas—need retrofitting,
and one—the San Francisco-Oakland Bay Bridge (Bay Bridge)—
needs a partial retrofit and a partial replacement. Chapter 327,
Statutes of 1997 (SB 60), set original cost estimates for the seven
toll bridges at $2.6 billion, with completion by 2004; however,
revised estimates presented in Chapter 907, Statutes of 2001
(AB 1171), raise the costs to $4.6 billion, with completion
by 2009.
Several factors contributed to the estimated $2 billion cost
increase and 5-year time delay. From the beginning, the funding
for toll bridges was likely to exceed the original estimates
in SB 60, because this legislation allows the Metropolitan
Transportation Commission (commission) to purchase a more
expensive “signature” east span of the Bay Bridge than was
originally envisioned, as long as Bay Area bridge users fund the
increase in cost. Under AB 1171, Bay Area bridge users will also
pay for other anticipated increases in cost not associated with
the selection of a bridge design, with the remainder covered by
federal highway bridge replacement and rehabilitation program
funds (federal bridge funds).
Aside from the cost increases resulting from selecting a different
and more expensive bridge, Caltrans recognizes the exclusion
of escalation rates that typically apply to large construction
projects for all of the toll bridges, except for the Bay Bridge
east span replacement, also resulted in underestimated costs.
In addition, for the Bay Bridge, efforts by the U.S. Navy to
prevent test drilling on Yerba Buena Island, and a delay in
12 13
the environmental impact review process due to the selected
alignment of the replacement for the Bay Bridge east span,
resulted in time delays and rising costs. Retrofitting projects
on other bridges, such as the Richmond-San Rafael Bridge,
experienced higher than anticipated costs for underwater work.
Like the Bay Bridge, the Carquinez Bridge encountered problems
with outside parties that affected project costs.
RISING COSTS AND TIME DELAYS PLAGUE
COMPLETION OF THE STATE’S LARGEST PUBLIC
SAFETY PROJECT
In its April 2001 annual report (annual report) to the Legislature
and governor, Caltrans disclosed cost estimates for the toll
bridges in the seismic retrofit program that are nearly double
its initial estimates prepared only a few years earlier. This is
not surprising, given that SB 60, which in 1997 set initial costs
Current cost estimates at $2.6 billion for the toll bridges, recognized the possibility
for the toll bridges in the that more funds may be needed and provided Caltrans with
seismic retrofit program a mechanism to obtain the additional capital. Caltrans first
are nearly double the became concerned about the sufficiency of the funding levels
initial estimates prepared in SB 60 when the market prices escalated for projects awarded
only a few years earlier. after its passage and when it became clear that the design
and environmental process for the replacement of the
Bay Bridge east span would delay completion by at least two
years. Therefore, Caltrans reevaluated the estimates and
raised the costs for the toll bridge seismic retrofit program
to $4.6 billion, explaining the reasons for the projected cost
increases in its annual report, along with recommendations on
how to cover some of the funding shortfall. Shortly thereafter,
AB 1171 adjusted the funding levels for the toll bridge seismic
retrofit program to reflect these revised estimates by allocating
additional Bay Area tolls and federal bridge funds.
Table 1 summarizes the substantial differences between the SB 60
and AB 1171 cost estimates for each of the seven state-owned
toll bridges. As the table shows, the revised cost estimates for the
toll bridges total $2 billion more than the initial cost estimates
prepared for SB 60. Of this increase, Caltrans estimates that about
$1.3 billion relates to many issues that affected the cost of a
signature bridge for the east span replacement of the Bay Bridge.
14 15
TABLE 1
The Toll Bridge Seismic Retrofit Program Has Experienced
Significant Increases in Projected Costs
(In Millions of Dollars)
Original Revised
SB 60 AB 1171 Cost Percentage
Toll Bridges Estimate Estimate Increases Increase
San Francisco-Oakland Bay Bridge
East span replacement $1,285 $2,600 $1,315 102%
West span retrofit and
approach replacement 553 700 147 27
Richmond-San Rafael Bridge 329 665 336 102
San Mateo-Hayward Bridge 127 190 63 50
Benicia-Martinez Bridge 101 190 89 88
Carquinez Bridge 83 125 42 51
San Diego-Coronado Bridge 95 105 10 11
Vincent Thomas Bridge 45 62 17 38
Totals $2,618* $4,637 $2,019 77%
Sources: Chapter 327, Statutes of 1997 (SB 60) and Chapter 907, Statutes of 2001 (AB 1171).
* SB 60 provides the toll bridge seismic retrofit program with total funding of $2,620 million;
however, the allocation of this funding to each individual toll bridge accounts for only
$2,618 million.
As part of its planning and design phases, Caltrans prepared
detailed cost estimates reflecting the materials and services
needed to retrofit each toll bridge. To identify the areas
where significant cost increases are anticipated, we obtained
these detailed cost estimates, placed each type of cost into a
descriptive category, and then compared the SB 60 estimates to
the later AB 1171 estimates for the Richmond-San Rafael and
Carquinez bridges. For the Bay Bridge east span, the SB 60 cost
estimates are not based on the bridge design currently under
construction; therefore, we acquired the first cost estimates for
the bridge design currently being constructed and compared
them to the AB 1171 estimates. Although SB 60 was passed in
August 1997, the first cost estimates for the signature bridge
were not available until May and June of 1998.
For two parts of the east span—the skyway and the signature
span—we analyzed where the cost increases occurred.
Figure 4 on page 20 illustrates these two parts of the bridge.
When the design was 30 percent complete, the skyway and
signature span were expected to cost $536 million and
$312 million, respectively; however, the AB 1171 estimates are
14 15
for $723 million and $590 million, resulting in cost increases
of $187 million and $278 million, respectively. The summary
of the cost estimate increases for the selected toll bridges
presented in Table 2 shows significant increases in concrete,
micropiles, overhead, structural steel, and support. A more
detailed presentation of the variances in the cost estimates for
the bridges is presented in Appendix A.
In addition to project cost increases, the toll bridge seismic
retrofit program has also experienced significant time delays.
Significant time delays Given the large volume of traffic that crosses these bridges on
in retrofitting the toll any given day and the importance of the bridges to the Bay Area
bridges raise economic economy, this delay raises economic and public safety concerns.
and public safety The U.S. Geological Survey believes that a 70 percent probability
concerns given the large exists that an earthquake with a magnitude 6.7 or greater will
volume of traffic that hit the Bay Area before 2030. Following the Loma Prieta earth-
crosses these bridges and quake, then-Governor George Deukmejian convened a Board
their importance to the of Inquiry and commissioned it to prepare a report. The report,
Bay Area economy. titled Competing Against Time, emphasized the importance of the
Bay Area crossings to the economical transportation of people
and products.
The report stated that future earthquakes in California are
inevitable, representing a clear and continuing danger to the
State’s population and economy. Caltrans believes that if a
seismic event like the Loma Prieta earthquake hit closer to the
Bay Bridge, the east span would be vulnerable to a collapse. A
subsequent report published by Caltrans’ Seismic Advisory Board
titled The Continuing Challenge, urged that a greater emphasis
be placed on the toll bridges to ensure their timely completion.
Figure 2 on page 18 reflects the significant time delays affecting
the toll bridge seismic retrofit program.
VARIOUS FACTORS CONTRIBUTED TO THE HIGHER
COST ESTIMATES AND TIME DELAYS
No one factor alone caused the significant rising cost estimates
that are affecting the seismic retrofitting of selected toll bridges.
One factor is that SB 60 permitted the commission to select
a more expensive Bay Bridge east span replacement than this
legislation reflected in its cost estimates. Another is that Caltrans
incorporated escalation rates into the SB 60 cost estimates only
for the east span replacement of the Bay Bridge, but did not
include escalation rates for the other toll bridges. In addition,
actions by parties external to the toll bridge seismic retrofit
16 17
TABLE 2
Significant Increases Have Occurred in Concrete, Micropiles, Overhead, Structural Steel,
Contingencies, and Support Cost Estimates*
San Francisco-Oakland Bay Bridge
Richmond-
Signature Other Total East San Rafael Carquinez
Skyway† Span† Contracts Span Bridge Bridge
Cast-in-place concrete $(27,011,709) $3,518,370 $ 7,070,372 $ (228,716)
Core concrete/drill and bond/
prestressing (4,213,080) (78,300) (348,675) 1,137,145
Environmental preservation — 242,100 1,001,812 1,026,877
Excavation and cleanup 5,850,000 (631,800) 2,225,519 4,043
Marine access 15,660,000 NA 18,250,000 200,000
Micropiles NA NA 44,748,308 NA
Other materials and services 8,031,960 4,535,126 985,309 1,154,878
Overhead 32,400,041 36,754,884 58,772,218 2,137,883
Pilings (66,149,100) 6,175,260 (3,530,086) 360,486
Precast concrete 102,167,640 NA 14,685,899 NA
Removal and demolition NA NA 913,027 (753,066)
Seismic safety 1,954,800 (135,000) (2,481,060) 247,000
Structural steel and miscellaneous
metal 102,397,860 143,260,155 26,421,563 7,708,563
Temporary items 2,570,400 NA 6,011,384 NA
Traffic control and safety (3,202,740) (234,000) 8,316,786 (2,019,972)
Utility work and services — NA 2,494,900 237,550
Water pollution control measures — NA 876,000 4,900
Contingencies 1,136,299 83,822,827 91,470,273 11,157,947
Other minor items‡ 3,830,000 — 6,862,344 11,201,054
Unreconciled difference§ 11,314,760 292,554 17,254,107 (5,576,572)
Subtotals: Capital outlay cost
differences 186,737,131 277,522,176 211,548,011 675,807,318 302,000,000 28,000,000
Support cost differences 224,543,000 34,000,000 14,000,000
Total Project Cost Differences $900,350,318 $336,000,000 $42,000,000
Sources: Toll bridge seismic retrofit program’s 30 percent design cost estimates; Chapter 327, Statutes of 1997 (SB 60) cost
estimates; and Chapter 907, Statutes of 2001 (AB 1171) cost estimates.
* The line item variances are intended to be representative of where variances occurred. However, in some cases, bidders or
subsequent estimators used line item categories that were not consistent with initial budget categories.
† The increases in cost estimates for the Bay Bridge skyway and signature span do not include roadway work, such as traffic
control, landscaping, and lighting.
‡ Other minor items include supplemental work, state-furnished materials, right-of-way, and anticipated claims.
§ Unreconciled differences include rounding and timing of estimates versus SB 60 and AB 1171.
16 17
FIGURE 2
Retrofitting the Toll Bridges Is Taking Significantly Longer Than Planned
���������������
���������������
�����������������������������
���������������������
�����������������������������
��������������������
��������������������
������������������������
����������������������
����������������������
���������������
�����������������������
�������������������
� � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �
Source: Caltrans’ project plans as of August 1997 and June 2002.
program delayed projects, thereby affecting program progress.
For example, the U.S. Navy delayed test drilling on Yerba Buena
Island and the Union Pacific Railroad did not promptly relocate
railroad tracks interfering with bridge construction. Overall,
difficulties in estimating the costs for the unique and complex
retrofit strategies have created many uncertainties and chal-
lenges that affect program cost.
The Bay Area’s Decision to Purchase a Signature Bridge
Increased the Price Tag on the Bay Bridge East Span
Replacement
In exercising its option under SB 60 to purchase a more
expensive signature bridge, the commission set in motion some
of the events that contributed to the projected cost increases
for the new Bay Bridge east span replacement. However,
18 19
along with its authority to select a more expensive bridge, the
commission was responsible for ensuring that bridge users pay
for the increase in cost. In late 1996 Caltrans completed cost
estimates for several different alternatives for the Bay Bridge east
span replacement. Of these alternatives, it recommended the
construction of a concrete skyway bridge spanning the entire
width of the bay between the city of Oakland and Yerba Buena
Island. Caltrans estimated the price tag for this replacement as
being $1 billion, based on the preliminary bridge design and
cost estimates. Figure 3 depicts Caltrans’ recommendation.
FIGURE 3
Caltrans Recommended a Skyway Bridge Design
for the Bay Bridge East Span Replacement
Oakland
Yerba Buena Island
Treasure Island
Under the guidelines of SB 60, the commission has the authority
to select the new east span replacement, including the option
to incorporate certain amenities, such as a more expensive
bridge design than was originally envisioned and a bicycle/
pedestrian path. In June 1998, the commission exercised its
option and selected a bridge design that differed dramatically
from Caltrans’ recommendation. Therefore, the replacement
alternative recommended by Caltrans was not commissioned
for construction. The commission based its decision on a
preliminary bridge design and cost estimates available in
May and June of 1998 and prepared by a joint venture design
team under contract to Caltrans. Figure 4 on the following page
depicts the commission’s selection.
18 19
FIGURE 4
The Commission Chose a Signature Bridge Design for the
Bay Bridge East Span Replacement
Signature span
To Oakland
Skyway
Yerba Buena Island
The timing of these choices plays an important role in the
higher cost estimates for the Bay Bridge. The original cost
estimates for the east span replacement, outlined in SB 60
in August 1997, were based on Caltrans’ initial design
recommendation, not on the bridge design currently under
construction. The Legislature did contribute an additional
$80 million in SB 60 for the future inclusion of a signature
span, but this amount is also not based on the cost of the
commission-selected signature span replacement. As we
mentioned previously, SB 60 permits the commission to select
a more expensive bridge design than was originally estimated
as long as bridge users pay for the increase in cost. In June 1998
the commission approved a 15-month extension of the seismic
retrofit surcharge equal to $1 per vehicle, imposed for passage
on all Bay Area toll bridges (seismic surcharge) to generate an
additional $141 million to cover the preliminary estimates for
its more expensive bridge design selection. In September 1999
and June 2000 the commission extended the seismic surcharge
again, for 9 months, to generate additional funds related to its
bridge design selection and to generate a pool of reserve funds
for future eligible projects. Finally, in late 2001, due to cost
increases above the SB 60 estimates, the commission requested
and Caltrans approved, an overall 30-year extension of the
original surcharge, as allowed by AB 1171.
20 21
Caltrans Excluded Escalation Rates From Most Estimates,
Thus Understating Initial Cost Estimates
When undertaking large construction projects that extend
over a period of time, it is prudent to take into consideration
the time value of money. In other words, estimates need to
allow for escalating market prices (escalation rates). However,
Caltrans incorporated escalation rates in the SB 60 cost estimates
Caltrans factored only for the east span replacement of the Bay Bridge, thereby
escalation into its cost for contributing to the understatement of initial cost estimates on
the Bay Bridge east span the other toll bridges. In discussing the subject of reliable cost
replacement but not into estimates in recent testimony before a congressional committee,
the cost estimates for the the inspector general of the U.S. Department of Transportation
other toll bridges. stated that early cost estimates are often inaccurate for a number
of reasons. For example, projects may undergo considerable
change during design, or the estimates may not have included
all reasonably anticipated costs.
Caltrans clearly states in its guidelines for preparing cost
estimates that reliable project estimates are necessary for
responsible fiscal management. It further states that unreliable
cost estimates result in severe problems in programming and
budgeting and in local and regional planning, and that they
may impair the effective use of resources. Additionally, Caltrans
recognizes that to be able to accurately estimate costs on larger
projects with longer time limits, it may be necessary to take into
account escalation of costs. As we stated previously, Caltrans
factored escalation into its cost estimate for the Bay Bridge east
span replacement but not into the cost estimates for the other
toll bridges. Although cost estimating can never be an exact
science, Caltrans knew that completing the retrofit projects
would take a number of years; therefore, one would reasonably
expect the estimates to include a consideration for escalation.
However, Caltrans stated that, consistent with past practice,
it provided current dollar estimates to the Legislature for all
projects except the new east span of the Bay Bridge.
Increases in Support Cost Estimates Contributed
Significantly to the Overall Project Price
Support costs for the toll bridge seismic retrofit program
increased significantly between the SB 60 and AB 1171 estimates,
accounting for 26 percent of the overall reported cost increases.
Support costs include such expenses as staff salaries, consultant
fees, and other operating costs incurred in supporting the
construction activities involved in retrofitting the toll bridges.
Caltrans reports that for the bridges we sampled, the majority
20 21
of these costs—58 percent—are forecasted amounts rather than
actual expenditures. For the SB 60 cost estimates, Caltrans says
its project engineers estimated support costs based on their
professional discretion. The actual percentage of support costs
to estimated consultant staff and construction costs varied
among the toll bridges, with the project engineer deciding
the appropriate amount for the toll bridge under his or her
supervision.
When Caltrans became concerned about the sufficiency of the
funding levels for the toll bridge seismic retrofit program and
revised its cost estimates, it also updated the estimates for sup-
port costs. Of the AB 1171 support cost estimates, 42 percent are
Increases in support costs, based on actual expenditures incurred from project inception
such as staff salaries through May 2000, with the remainder attributed to forecasted
and consultant fees, amounts for certain costs indirectly related to the program and
contributed significantly for Caltrans direct staff and consultant services. To arrive at the
to the seismic retrofit forecasted amounts for staff, various Caltrans’ managers within
program’s overall the toll bridge seismic retrofit program estimated the number
estimated rise in cost. of hours needed to complete assigned tasks for their projects.
Caltrans then multiplied these hours by an hourly rate to derive
a forecasted cost for staff. It calculated this hourly rate based on
its historical billing rates, adjusted for overhead expenses and
escalation. To forecast consultant services, Caltrans relies on
the value of open and anticipated consultant contracts. The toll
bridge seismic retrofit program must also absorb its share of costs
not directly related to the program but for which it derives ben-
efits. The AB 1171 estimates reflect $45 million in such costs.
Project Delays Raised Toll Bridge Seismic Retrofit
Program Costs
Seismically retrofitting the toll bridges is an enormous project
that requires the involvement and coordination of numerous
organizations. A few of these organizations, including the
U.S. Navy and the Union Pacific Railroad, have delayed the
work on some of the toll bridges. These delays have not only
lengthened the project but have also increased costs due to
escalation rates and contractor delays. For the Bay Bridge east
span replacement, the commission’s selection of a path north
of the existing bridge (northern alignment) caused some
controversy. With the Carquinez Bridge, problems arose with
adjacent landowners.
22 23
Disagreement Over the Selected Northern Alignment Delayed
Progress and Raised Costs
A general disagreement with the U.S. Navy over the proposed
northern alignment of the Bay Bridge east span replacement
Disagreement with resulted in almost one year of design delays, which eventually
the U.S. Navy over ended when the Federal Highway Administration (FHWA)
the selected northern executed a formal federal land transfer in October 2000 giving
alignment resulted a portion of Yerba Buena Island to Caltrans. Important to
in a one-year design the seismic safety of any erected structure is the geotechnical
delay for the east span understanding of the proposed development site. According
replacement. to Caltrans, a series of drillings into the underlying soil and
rock on Yerba Buena Island was critical to the design of the
replacement span.
In September 1998 Caltrans requested an on-shore drilling
license so that it could perform this seismic testing. Citing its
opposition to the selected northern alignment because of the
project’s substantial adverse impact on Yerba Buena Island’s
historic and environmental resources and on the city of
San Francisco’s ability to redevelop the island under the
Federal Base Closure Act, the U.S. Navy denied Caltrans’
request. It finally granted Caltrans the license a year later,
in September 1999. Ultimately, the U.S. Navy’s ability to further
delay the completion of the replacement span was eliminated
when the FHWA executed a federal land transfer giving Caltrans
title to a portion of Yerba Buena Island.
The U.S. Navy’s position was that the path of the replacement
span should be to the south of the existing span. During its
federal environmental impact review, Caltrans considered the
three alignment alternatives (N-2, N-6, and S-4) shown in
Figure 5 on the following page. Caltrans and the FHWA identified
replacement alternative N-6 as their preferred alternative since
the geologic conditions would make construction of the main
tower easier, because that alignment would bring greater aesthetic
benefits and it was consistent with the regionally preferred
alignment and design features as expressed by the commission.
The controversy over the proposed northern alignment also
delayed the necessary environmental approval process for
the replacement span by one year. Although this project is
statutorily exempt from state environmental requirements
because it qualifies as a seismic safety upgrade, Caltrans is still
required under the National Environmental Policy Act (NEPA)
to undergo a formal federal environmental review. Critical to
22 23
FIGURE 5
Caltrans Considered Three Alignment Alternatives
for the Bay Bridge East Span Replacement
���
����
�����
�
���
��
��� ��������� ���
���������
��� � � �� � � � � � � �
� ���
�� �
� � �
� � �� ���
��� � �
�
�
��
���
���������������������
���������� ����������������
������
� � � � � � �
����������������
the NEPA process is the identification by the U.S. Environmental
Protection Agency (EPA) and the U.S. Army Corps of Engineers
of the Least Environmentally Damaging Practicable Alternative
(LEDPA) under the federal Clean Water Act.
As part of the LEDPA identification process, Caltrans was sched-
uled to meet with the FHWA, the U.S. Army Corps of Engineers,
and the EPA in September 1999. However, this meeting was
delayed until October 2000 so that the following six steps could
be completed:
• The FHWA was to provide the U.S. Navy with information on
the environmental impact of drilling on Yerba Buena Island.
• A meeting was to take place between the U.S. Navy, the
FHWA, the U.S. Coast Guard, Caltrans, and the city of
San Francisco to discuss the differing construction impacts
for the northern and southern alignment alternatives.
• The U.S. Army Corps of Engineers was to serve as a neutral
third party to review engineering analyses related to the
southern alignment.
• The U.S. Navy agreed to evaluate the historic impact of
alternative alignments, and the FHWA was to work with the
U.S. Navy to reach an agreement regarding this issue.
24 25
• A discussion with Oakland Mayor Jerry Brown about the
alignment alternative.
• The FHWA was to arrange a meeting with the city of
San Francisco and the U.S. Navy to discuss the economic
impact of the different alignments as they affected the
development of Yerba Buena Island.
In February 2001 the U.S. Army Corps of Engineers identified
alternative N-6 as its LEDPA selection, and in March 2001 the
EPA identified alternative N-6 as its LEDPA selection. Although
the issues with the U.S. Navy and the LEDPA were ultimately
resolved, the effect was a nearly 2-year delay in the design and
environmental process of the Bay Bridge east span replacement.
Construction Delays by Property Owners Slowed Caltrans’
Project Timeline
Caltrans attributes significant delays in retrofitting the
Carquinez Bridge to construction delays involving the Union
Pacific Railroad and Pacific Gas & Electric Company (PG&E).
These delays led the construction contractor to file contract
change orders to recover costs it had incurred as a result of the
delays, thereby increasing program costs.
A critical part of the retrofit strategy for this toll bridge requires
the relocation of railroad tracks belonging to the Union Pacific
Railroad that conflict with construction and the shifting of a
high-pressure PG&E gas line from the west side of the bridge to
the east side. During the project’s early stages, Caltrans indicated
that it began negotiations with Southern Pacific Railroad, which
owned the tracks at that time, for the relocation. However,
before an agreement was reached, the Union Pacific Railroad
acquired Southern Pacific Railroad and subsequently took
143 days longer to perform the relocation than Caltrans
originally anticipated. Regarding the gas line, PG&E originally
estimated the scheduling of this work; however, due to delays
The construction for the in awarding the contract and additional design modifications,
Carquinez Bridge incurred it took twice as long to shift the gas line as PG&E had initially
certain reimbursable costs estimated, resulting in 87 days of delay.
as a result of delays by
external parties. During these delays, Caltrans had a construction firm under
contract to perform the retrofit work. This contractor incurred
costs that would not have been necessary if Union Pacific
Railroad had relocated the railroad tracks and PG&E had
shifted the gas line by the dates Caltrans had anticipated. The
24 25
contractor submitted a number of contract change orders, of
which the project manager attributes $9 million relating to
these delays. These costs accounted for over 20 percent of the
total projected increases on the Carquinez Bridge. Caltrans or
the contractor can initiate contract change orders to recoup
costs associated with design changes, actual conditions that
vary from expectations, and delays such as those related to
Union Pacific Railroad and PG&E. Caltrans has an established
process for reviewing and approving contract change orders. In
this instance, several of its bridge engineers concluded that the
costs the construction contractor incurred were reasonable and
unavoidable, and therefore reimbursable by Caltrans.
The Seismic Retrofit Work Has Proven Difficult to Estimate
According to Caltrans, not only are the toll bridges the largest
and most complicated bridges in the State, but nowhere in
the world have bridges as complex as these been seismically
retrofitted. Furthermore, a consulting firm hired to perform
an independent cost review of the toll bridge seismic retrofit
program reported that the new Bay Bridge east span is
sufficiently unique that traditional highway construction
estimating metrics do not apply. In addition, the joint venture
design firm for the Richmond-San Rafael Bridge claims that
Circumstances unique to it is employing retrofit strategies at scales never used before.
the seismic retrofitting Such circumstances as these produce a greater degree of cost
of toll bridges result in uncertainty and limit the ability to draw from past experiences
a greater degree of cost and employ traditional estimating practices.
uncertainty and limit the
ability to use traditional Recognizing these significant challenges, Caltrans used numer-
estimating practices. ous outside experts and academic advisors when estimating
project cost. In fact, private consulting firms, under Caltrans’
supervision, prepared the cost estimates for all seven of the toll
bridges, with the exception of the west span of the Bay Bridge,
which Caltrans solely prepared. Even considering this additional
expertise, each of the bridges is expected to experience cost
increases above their original estimates. Additionally, Caltrans
attributes much of the difficulty in retrofitting the structures
to factors such as variable soils and foundations, seismic forces
much stronger than the original design forces, aged structures,
heavy traffic volumes, conflicts with utilities, and various envi-
ronmental concerns. These factors present Caltrans with a
unique and unprecedented task when estimating project cost.
26 27
For example, several of the Northern California toll bridges
span geologic formations that place some portions of the
respective bridges and their foundations in locations of rock and
others portions in soft bay mud. Also, much of the foundation
work is marine-based, which, as Table 2 on page 17 shows,
is a condition that Caltrans has found difficult to accurately
estimate. For instance, the construction bid for the micropile
work on the Richmond-San Rafael Bridge came in significantly
higher than estimated. This toll bridge was also faced with strict
environmental restrictions that affected project costs by forcing
the contractor into three cycles of marine mobilization and
demobilization during construction.
The challenges faced in retrofitting the Northern California toll
bridges also help explain why the cost increases for these bridges
are far more dramatic than those for the two Southern California
toll bridges. Specifically, Caltrans indicates that its retrofit
strategies on the Southern California toll bridges have minimal
foundation work in comparison, and since the geologic site
conditions found in Northern California are more challenging,
they are also more costly.
Contingency Reserves Provide Funding for Potential
Cost Increases
To cover the rising costs related to the unique estimating
challenges that the toll bridge seismic retrofit program presents,
Caltrans looks to its Caltrans looks to its contingency reserves. Contingency reserves
contingency reserves to do not represent costs but rather are budgetary amounts
cover the rising costs of representing a portion of the cost estimate not allocated to
the toll bridge seismic cost categories. Therefore, a part of the anticipated $2 billion
retrofit program. increase includes these budgetary amounts. The intent of
contingencies is to compensate for the limited information
available during the planning phase of a retrofit project.
Early in a project’s development, allocations for contingency
reserves are high. They then decrease as funding is transferred
from the contingency reserve to cost categories, either to a
newly established cost category or to increase funding for cost
categories where actual costs exceed the original estimate. At
project completion, amounts remaining in the contingency
reserve represent the extent to which the project was completed
for less than the budget or cost estimate.
Although the procedures for estimating costs differ depending
upon the type of project, Caltrans has established a cost esti-
mating methodology in an effort to promote consistency in the
26 27
development of reliable cost estimates. Caltrans’ policy dictates
that in the early stages of a project, contingencies should range
from 30 percent to 50 percent of the project cost. Once a project
is approved and progresses into its planning and design phases,
the contingency percentage is lowered. By the time a project is
advertised for bid, contingency levels are normally reduced to
about 5 percent of the project’s cost. Any percentage higher
than this needs to be justified based on the atypical nature of
the project.
The contingency amounts that Caltrans reflects in its AB 1171
cost estimates for the Richmond-San Rafael and Carquinez
bridges are higher than the levels included in the SB 60 cost
estimates, and greatly exceed levels related to more typical
projects under normal Caltrans guidelines. When AB 1171 was
passed, both of these toll bridges had construction contracts
already awarded; as discussed above, normal policy dictates
contingency reserves of 5 percent. Regarding the Bay Bridge
east span replacement, a comparison of contingency reserves
would not be meaningful, given that the bridge budgeted for in
SB 60 is not the same as the bridge currently under construction
and budgeted for by AB 1171. Caltrans raised its contingency
amounts for the Richmond-San Rafael and Carquinez bridges
because it believed the levels included in SB 60 were not
consistent with the lack of refinement in the planning level
studies and with the number of uncertainties, given the unique
nature of the toll bridge seismic retrofit program.
TABLE 3
AB 1171 Contingency Reserves Increased From Those Designated in SB 60
Percentage of Amount of
Contingency Contingency
Reserves Reserves
Legislation (Includes Rounding) (Includes Rounding) Project Stage
Carquinez Bridge SB 60 (1997) 10% $5,974,385 Late stage of design
AB 1171 (2001) 19 16,488,718 Construction
Richmond-San Rafael Bridge SB 60 (1997) 6 15,057,198 Late stage of design
AB 1171 (2001) 14% $77,567,577 Construction
Sources: Consultant prepared cost estimates and Caltrans’ project plans.
28 29
Table 3 shows the increase in contingency amounts between
SB 60 and AB 1171. Both the percentage and amount of
contingency reserves for the Carquinez and Richmond-
San Rafael bridges increased between SB 60 and AB 1171.
Additionally, Caltrans recently increased the Richmond-San
Rafael Bridge’s contingency levels by another $32.7 million,
or 6 percent, for an overall total of about 20 percent. In the
case of the Bay Bridge east span replacement, the contingency
reserves represented in the SB 60 cost estimates were not based
on the bridge design ultimately chosen. When the commission
made its final design selection in 1998, the cost estimates for
the skyway and signature span portions included contingency
amounts of $93 million (21 percent) and $62 million (25 percent),
respectively, of the contracted or to-be-contracted items. The
contingency amounts included in the AB 1171 cost estimates
are $94 million (15 percent) for the skyway, which was in a
later stage of design, in comparison to the signature span, with
contingency amounts of $146 million (33 percent).
BRIDGE USERS AND FEDERAL BRIDGE FUNDS WILL
PAY FOR THE PROJECTED COST INCREASES OF THE
RETROFIT PROGRAM
Although SB 60 gives the commission the authority to select a
more expensive bridge design than Caltrans originally estimated
for, it also requires the commission to ensure that bridge users
pay for the additional cost by extending the seismic surcharge
Legislation requires the
imposed on all Bay Area toll bridges. Initially, the Legislature
commission to ensure
established the seismic surcharge in 1997 to cover the Bay
that bridge users pay the
Area’s share of retrofit costs by generating an estimated $907
additional cost of a more
million and then expiring in 2008. The commission could
expensive bridge design.
extend the expiration date for the surcharge if it chose to
purchase amenities for the Bay Bridge east span replacement.
During the early design phase of the east span replacement,
Caltrans estimated that the additional costs of the commission-
selected bridge design and amenities would total $141 million
more than the amount funded by SB 60. Therefore, the
commission extended the seismic surcharge by 15 months to
generate sufficient funds to cover the increase in cost. Later, the
commission extended the seismic surcharge again, for 9 months,
to pay for costs related to the amenities and to generate a pool
of reserve funds for future eligible costs.
28 29
In late 2000, Caltrans became concerned that the funding levels
outlined in SB 60 for the toll bridge seismic retrofit program
would not be sufficient to cover program costs, so it undertook
efforts to reevaluate its cost estimates for the seven toll bridges.
The resulting updated estimates raised the cost for retrofitting
the toll bridges to $4.6 billion. Caltrans addressed a portion of
the $2 billion cost increase by recommending the use of federal
bridge funds, but it provided no recommendation for how to
cover the cost increase for the Bay Bridge. Ultimately, AB 1171
provided for the seismic surcharge to be extended for an overall
30 years, until 2038, to supply the projected funds needed. Thus,
under Caltrans’ current funding plan, Bay Area bridge users
will pay for 49 percent of the entire toll bridge seismic retrofit
program, an increase from their original 35 percent share. The
remaining funding increase was addressed by drawing from fed-
eral bridge funds, as recommended by Caltrans. Table 4 shows
the funding mix.
TABLE 4
Bridge Users Will Pay for the Majority of the Increase in Funding
(In Millions of Dollars)
Original Revised
Estimate Estimate Funding
Funding Sources SB 60 AB 1171 Increase
Bay Area Regional Toll Surcharge $ 907 $2,282 $1,375
State Highway Account 795 795 —
Transportation Planning and Development Account 80 80 —
Seismic Retrofit Bond Act of 1996 650 650 —
Seismic Retrofit Bond Act of 1996 Surplus 140 140 —
San Diego-Coronado Toll Bridge Revenue Account 33 33 —
Vincent Thomas Toll Bridge Revenue Account 15 15 —
Federal Highway Bridge Replacement and Rehabilitation Program — 642 642
Totals $2,620 $4,637 $2,017
Percentage of total cost estimates paid by Bay Area bridge users 35% 49%
Percentage of funding increases paid by Bay Area bridge users 68%
Sources: Chapter 327, Statutes of 1997 (SB 60) and Chapter 907, Statutes of 2001 (AB 1171).
30 31
CHAPTER 2
Due to Remaining Uncertainties,
the Potential Still Exists for Costs to
Exceed Funding Levels
CHAPTER SUMMARY
A consulting firm hired by the Metropolitan Transportation
Commission (commission) reports that costs for the
toll bridge seismic retrofit program may increase an
additional $250 million to $630 million above what the
California Department of Transportation (Caltrans) currently
reports. The consulting firm concludes that the majority of these
potential cost increases will result from capital construction,
which includes contractor-charged overhead rates, as well as
from higher support costs. If the consulting firm’s estimates
prove to be accurate, Caltrans will need to identify additional
funding sources to cover the shortfall. Current law limits
Caltrans’ funding options to three programs: the State Highway
Operation and Protection Program (SHOPP), the Interregional
Transportation Improvement Plan (ITIP), and federal bridge
funds, for a combined limit of $448 million in additional
funding. Currently, Caltrans maintains that the toll bridge
seismic retrofit program will be completed within the funding
authority provided by AB 1171.
A CONSULTING FIRM HIRED TO REVIEW THE
CURRENT ESTIMATES BELIEVES THAT COSTS MAY
CONTINUE TO RISE
After Caltrans reported that costs for the toll bridge seismic
retrofit program would nearly double from $2.6 billion to
$4.6 billion, the California State Senate Select Committees on
Bay Area Infrastructure and Transportation requested that the
commission conduct an independent review of Caltrans’ cost
projections. In July 2001, a commission-hired consulting firm
performed this review, focusing the majority of its efforts on
the San Francisco-Oakland Bay Bridge (Bay Bridge) east span
replacement and west approach projects, the retrofitting of the
Richmond-San Rafael Bridge, and the program-wide issues of
escalation, contingency, and support. The Bay Bridge east span
and Richmond-San Rafael projects account for approximately
30 31
75 percent of the overall program costs. Based on this review,
the consulting firm not only agreed that the costs for the toll
bridges would double, but it also asserted the potential for
additional costs ranging from $250 million to $630 million
more than Caltrans estimated. The consulting firm concluded
that increases may stem from higher capital construction costs,
which include contractor-charged overhead rates, as well as from
higher support, escalation, and demolition costs, and it stated
that the allocated contingency reserves are insufficient to cover
these and other costs.
The limited time permitted for the review led the consulting
firm to focus on the work with the greatest potential to
A commission-hired affect the cost of the toll bridge seismic retrofit program. Its
consulting firm not only cost review was therefore influenced by a project’s stage of
agrees that costs will design and construction and its relative construction value.
double, but also reports For work awarded that was complete or nearly complete,
the potential for costs to like the Carquinez Bridge, the cost review consisted of a
rise higher than estimated limited examination to ensure that the amounts Caltrans had
by Caltrans. reported were supportable. For work awarded that was largely
incomplete—for example, the Richmond-San Rafael Bridge—the
cost review focused on reserves set aside for potential contract
change orders, as well as on projected support costs. Finally,
for work not yet bid and awarded, such as the Bay Bridge east
span replacement, the review focused on the scope, basis,
and approach in estimating construction and support costs;
on validating key quantities and prices; and on analyzing
contingency reserves.
The consulting firm relied on a few assumptions and scope
exclusions in arriving at its conclusions, a significant one
being that the projects would be advertised and awarded at
the times indicated in their current bidding schedules. The
consulting firm reports that if additional delays occur, one could
reasonably expect costs to exceed the potential $250 million
to $630 million increase it estimates. The consulting firm was
also careful to mention that its cost review was neither a value-
engineering analysis nor a newly prepared comprehensive
estimate of program costs. That is, the consulting firm did
not question the effectiveness or efficiency of the retrofit or
replacement designs that underlie Caltrans’ cost estimates unless
they appeared not to be feasible or conflicted with the design. A
representative of the consulting firm further explained that any
design changes taking place after the cost review would have
the potential to affect the cost of retrofitting the toll bridges.
At the time of the cost review, the design of the Bay Bridge east
32 33
span replacement was not fully completed. Table 5 summarizes
where additional costs may occur and shows that the majority of
the potential cost increases the consulting firm identified in its
review relate to capital construction, which includes contractor-
charged overhead rates, and support costs.
TABLE 5
An Independent Cost Review Identified Additional Cost Increases
(In Millions of Dollars)
Toll Bridge Low Range High Range
Richmond-San Rafael Bridge
Capital construction and contingency reserves due to higher construction costs
and anticipated contract change orders $ (10) $ 25
Caltrans’ support costs 0 25
Subtotals (10) 50
San Francisco-Oakland Bay Bridge: West Approach Replacement
Capital construction due to higher materials cost and general conditions* 50 60
Caltrans’ support costs 5 25
Additional contingency reserves to cover potential increased costs 20 30
Demolition costs and escalation rates (5) 25
Subtotals 70 140
San Francisco-Oakland Bay Bridge: East Span Replacement
Capital construction due to higher construction costs and general conditions* 125 205
Demolition costs 40 40
Caltrans’ and consultant support costs† 120 125
Escalation rates and additional contingency reserves to cover potential
increased costs (95) 70
Subtotals 190 440
Totals $250 $630
Source: Bechtel Infrastructure Corporation’s Toll Bridge Seismic Retrofit Program Cost Review Report, July 2001.
*General conditions include contractor-charged overhead rates and profit.
† Includes $90 million in additional support costs identified by Caltrans but not included in its April 2001 annual report.
A month following the issuance of this cost review, the Federal
Highway Administration (FHWA) conducted its own review
regarding the sufficiency of Caltrans’ most recent cost estimate.
The FHWA’s review focused solely on the Bay Bridge east span
replacement, not the entire toll bridge seismic retrofit program.
Although at that time the FHWA concluded that the current
32 33
$2.6 billion cost estimate was reasonable, it went on to say that
assurances can never be made that project costs will not change.
Therefore, it recommended that Caltrans annually update its
cost estimate until the project’s full completion. The FHWA’s
review did not suggest an alternative method for demolishing
the east span of the Bay Bridge suggested by the consulting firm
and reflected in its estimate.
TABLE 6
Uncertainties Remain That Have the Potential to Increase Final Project Costs
Stage of Completion at Time of
Consulting Firm’s Cost Review Current Status
(As of April 2001) (As of June 2002)
Project Contract Design Construction Design Construction
Richmond-San Rafael
Bridge retrofit 100% 4% 100% 30%
San Francisco-Oakland Bay Bridge: west
approach
West approach replacement 90 0 100 0
West approach archaeology and retrofit 100 0 100 44
San Francisco-Oakland Bay Bridge: east
span replacement
Pile installation demonstration 100 100 100 100
Skyway 100 0 100 2
Oakland touchdown geofill 90 0 100 28
Oakland touchdown structure 65 0 80 0
Signature span and Yerba Buena Island
touchdown 65 0 90 0
Bridge demolition 10 0 45 0
Sources: Bechtel Infrastructure Corporation’s Toll Bridge Seismic Retrofit Program Cost Review Report, July 2001, and Caltrans.
Table 6 shows the stage of design and construction for the
toll bridges at the time of the consulting firm’s cost review
and currently as of June 2002. As the table shows, the retrofit
program has progressed in many areas. For instance, Caltrans
has begun construction on the skyway portion of the Bay Bridge
east span replacement, a contract which was awarded to
the lowest bidder at $321 million above the cost estimate
included in AB 1171. The fact that this contract award far
exceeded Caltrans’ cost estimates validates the consulting firm’s
conclusion that the Bay Bridge east span replacement may
34 35
experience additional cost increases above those reported by
Caltrans. Furthermore, our analysis shows that the east span
replacement may experience even greater increases than those
predicted by the consulting firm.
As shown in Table 5 on page 33, the consulting firm expects
a possible increase in capital construction costs of between
$125 million and $205 million for the east span replacement,
due to higher construction costs and general conditions. Of
this increase, the consulting firm attributes $52 million to
$58 million to a skyway-related general conditions increase,
which includes time-related overhead. However, based on the
bid that has been accepted on the skyway contract, even the
consultant’s projected cost increases may prove to be too low.
Just taking into account time-related overhead, the bid on the
skyway contract exceeded the consultant’s high estimate by
$94 million. And, compared to Caltrans’ estimate reported in
2001 for AB 1171, these costs, as bid, exceed that estimate by
$152 million.
In its most recent annual report for the toll bridge seismic
retrofit program, Caltrans states that it will cover these
The program may need additional costs with existing contingency reserves; however,
additional funding Caltrans will also need to use these reserves to cover any
because the skyway increased costs due to contract change orders that arise during
used a disproportionate and after construction. As shown in Table 7 on the following
share of the contingency page, the skyway will use a disproportionate share of the overall
reserves for the east span contingency reserves for the east span of the Bay Bridge, due
of the Bay Bridge. to the large amount by which the successful bid for the skyway
exceeds Caltrans’ current estimate. The skyway, which represents
approximately one-third of the budgeted retrofit costs of the
east span of the Bay Bridge, has already used two-thirds of the
project’s planned contingency reserves. This depletion of the
reserves may result in a funding shortfall for the Bay Bridge
east span replacement. Furthermore, contract change orders
filed after the contract award to resolve disputes with the
contractor could potentially use even more of the project’s
planned contingency reserves and drive the amount attributed
to the skyway even higher. This seems to suggest that Caltrans
may need additional funding to complete the east span unless
the contingency reserves it has planned for the other retrofit
projects are overstated. However, past experience has shown
that Caltrans’ planned costs for retrofitting its toll bridges are
generally understated rather than overstated.
34 35
TABLE 7
The Bid for the Bay Bridge Skyway Used More Contingency
Reserves Than Caltrans Expected
(In Thousands of Dollars)
Difference
Between
AB 1171 Percentage Bid and Percentage
Cost of Total Contingency Bid Cost of Total
East Span Replacement Contracts Estimate Estimate Reserves Amount Estimate Contingency
Skyway* $ 769,680 30% $ 99,133 $1,043,541 $273,861 67%
Pile installation demonstration project 9,560 0 536 7,299 (2,261)
Oakland touchdown geofill 9,000 0 1,759 6,890 (2,110)
Self-anchored suspension span 590,000 23 146,611 NA NA
Other contracts 1,221,820 47 161,501 NA NA
Totals $2,600,060 100% $409,540
Sources: Chapter 907, Statutes of 2001 (AB 1171) cost estimates and awarded construction contracts as of June 2002.
*Skyway cost estimates include roadway items such as traffic control, landscaping, and lighting.
NA: Caltrans has not awarded a contract for these projects as of June 2002.
THE TOLL BRIDGE PROGRAM MUST DRAW
FROM OTHER FUNDING SOURCES IF COSTS DO
ACTUALLY INCREASE
If the commission-hired consulting firm’s estimates prove to be
accurate and costs for the toll bridges do exceed the currently
reported estimates, Caltrans must report these differences to
the Legislature and give the reasons for the increase in costs.
Some of the funding solutions that may cover the cost increases
could postpone the completion of other planned transportation
projects in the State. AB 1171 currently limits Caltrans’ funding
options to three programs: SHOPP, ITIP, and federal bridge
funds, for a combined total of $448 million. Although the
consulting firm concluded that costs may increase more than
previously reported, Caltrans maintains that its current estimates
and funding levels are sufficient to cover program costs, and
therefore it does not anticipate requesting any additional funds.
In its April 2001 annual report, Caltrans considered
recommending the use of SHOPP funds to cover the cost
overruns that it previously identified and that we discussed in
Chapter 1. However, it indicated that doing so would require
using funds previously earmarked for other projects. Projects
funded under SHOPP address the safety and integrity of the
36 37
state highway system, not increased road capacity. Most projects
covered relate to rehabilitation and traffic safety improvements
and require the approval of the California Transportation
Commission. ITIP addresses efforts to facilitate the interregional
movement of people and goods on the state highway and
transit systems, and receipt of its funds also requires the
approval of the California Transportation Commission.
Additionally, Caltrans has already committed to drawing from
federal bridge funds to cover a portion of the previously reported
cost overruns.
When questioned about the consulting firm’s findings,
Caltrans indicated that overall it could not form a detailed
opinion about the additional costs because the consulting
firm declined to share its back-up information supporting
its findings. According to the chief deputy district director,
the consulting firm asserted, and Caltrans agreed, that the
information was proprietary. As a result, even though the
commission contracted with the consulting firm in response
to a legislative request, Caltrans was precluded from reviewing
the specific information it would need to review in order to
form a detailed opinion about the additional costs. Caltrans
did state, with regard to the $90 million in additional support
costs reported by the consulting firm, that the amount reflects
an estimate of potential costs associated with using additional
consultants, should Caltrans decide to use them. Since the mix
of Caltrans and consultant staff is not fixed, Caltrans decided
Caltrans maintains that not to incorporate the $90 million into its estimates but rather to
it will complete the manage the resource mix within the AB 1171 funding limitations
seismic retrofitting of by using Caltrans’ staff to complete the necessary work.
the Bay Area toll bridges
within the existing Further, Caltrans explains that in one instance the consulting
funding authority. firm’s cost estimating methodology differed from its own.
Specifically, Caltrans planned a different and less expensive
method for demolishing the existing Bay Bridge east span than
that used in the consultant’s estimate. However, this example
represents only $40 million of the $250 million to $630 million
potential cost increases identified in the consulting firm’s cost
review. Currently, Caltrans maintains that the toll bridge seismic
retrofit program will be completed within the funding authority
provided by AB 1171.
36 37
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
Date: August 1, 2002
Staff: Reed M. McDermott, CPA, Project Manager
Theresa Gartner, CPA
Mandi Gallardo
Ben Belnap
38 39
APPENDIX A
Detailed Cost Estimate Variances Between Senate Bill 60 and
Assembly Bill 1171 for the Toll Bridge Seismic Retrofit Program*
Bay Bridge Bay Bridge Richmond-
Skyway Signature Span San Rafael Carquinez
Cast-in-place concrete
Bar reinforcing steel $6,815,340 $(2,783,700) $3,632,820 $692,275
Structural concrete (39,674,700) 6,302,070 2,383,390 (1,032,806)
Other 5,847,651 — 1,054,162 111,815
Category totals (27,011,709) 3,518,370 7,070,372 (228,716)
Core concrete/drill and bond
prestressing
Core and pressure grout — — (42,674) 1,037,770
Core concrete — — (2,835,332) (722,155)
Drill and bond dowell — — 41,147 107,864
Prestressing (4,213,080) (78,300) 2,488,184 264,106
Other — — — 449,560
Category totals (4,213,080) (78,300) (348,675) 1,137,145
Environmental preservation
Erosion control — — — (523)
Excavation — — — 958,800
Rock slope protection — 242,100 691,980 —
Remove and patch concrete — — 541,450 —
Other — — (231,618) 68,600
Category totals — 242,100 1,001,812 1,026,877
Excavation and cleanup
Backfill — (55,800) 379,584 181,192
Structure excavation 5,850,000 (36,000) 852,573 (173,299)
Test borings — — 583,830 —
Other — (540,000) 409,532 (3,850)
Category totals 5,850,000 (631,800) 2,225,519 4,043
Marine access 15,660,000 — 18,250,000 200,000
Micropiles — — 44,748,308 —
Other materials and services
Asphalt — — 121,671 346,620
Elevator — (380,700) — —
continued on the next page
38 39
Bay Bridge Bay Bridge Richmond-
Skyway Signature Span San Rafael Carquinez
Jacking 180,000 — — 645,000
Joint seal 2,597,850 (1,228,500) 72,434 —
Lumber 1,228,500 — 650,665 —
Minor concrete and grout — 173,700 — —
Overlay 1,547,370 1,383,156 — —
Piping — — — 89,900
Survey monument — — (13,650) —
Scaffolds 1,592,640 — 154,189 —
Other 885,600 4,587,470 — 73,358
Category totals 8,031,960 4,535,126 985,309 1,154,878
Overhead
Mobilization 17,060,482 19,349,116 14,689,318 1,007,938
Time related overhead 15,339,559 17,405,768 43,852,500 905,345
Other — — 230,400 224,600
Category totals 32,400,041 36,754,884 58,772,218 2,137,883
Pilings
Cast-in-drilled hole concrete pilings — 6,115,860 14,955,788 360,486
Furnish cast-in-steel shell concrete
pilings (64,930,500) (459,000) (12,155,009) —
Furnish steel pipe pilings — — 1,448,640 —
Drive cast-in-steel shell concrete
pilings 1,805,400 518,400 (7,101,012) —
Drive steel pipe pilings — — (757,934) —
Other (3,024,000) — 79,441 —
Category totals (66,149,100) 6,175,260 (3,530,086) 360,486
Precast concrete
Furnish precast concrete pile
cap assemblies — — (3,368,800) —
Furnish precast concrete
jacket assemblies — — 1,706,840 —
Furnish other precast concrete 80,967,330 — 6,051,644 —
Furnish and erect precast concrete
wall 2,274,480 — — —
Erect precast concrete jacket
assemblies — — 7,925,901 —
40 41
Bay Bridge Bay Bridge Richmond-
Skyway Signature Span San Rafael Carquinez
Erect precast concrete pile
cap assemblies — — (1,010,080) —
Erect other precast concrete 18,925,830 — 3,380,394 —
Category totals 102,167,640 — 14,685,899 —
Removal and demolition
Bridge removal — — (521,348) (2,629)
Removal structural steel — — — (774,447)
Remove truss shoe pin — — 1,385,600 —
Other — — 48,775 24,010
Category totals — — 913,027 (753,066)
Seismic safety
Bearings 1,954,800 (135,000) — —
Viscous damping device — — (2,196,996) —
Other — — (284,064) 247,000
Category totals 1,954,800 (135,000) (2,481,060) 247,000
Structural steel and miscellaneous
metal
Casings — — 6,940,990 (165,158)
Clean and paint 2,790,000 3,105,000 11,599,524 1,227,612
Column bracket — — 670,800 —
Furnish and erect assemblies — 2,090,385 — —
Furnish and erect structural steel 99,739,800 123,482,610 357,612 5,873,172
Install structural steel — 71,100 — —
Miscellaneous metal (1,391,940) 968,760 1,681,861 714,181
Rivet removal and hole reaming — — 5,170,776 —
Other 1,260,000 13,542,300 — 58,756
Category totals 102,397,860 143,260,155 26,421,563 7,708,563
Temporary items 2,570,400 — 6,011,384 —
Traffic control and safety
Area signs — — 977,840 97,000
Concrete barriers 19,170 — 163,467 1,141,900
Fenders (3,510,000) (234,000) — (1,260,000)
Traffic control system — — 2,154,000 (1,733,000)
Traffic railing — — 4,230,288 161,200
continued on the next page
40 41
Bay Bridge Bay Bridge Richmond-
Skyway Signature Span San Rafael Carquinez
Traffic stripes — — 21,316 16,133
Other 288,090 — 769,875 (443,205)
Category totals (3,202,740) (234,000) 8,316,786 (2,019,972)
Utility work and services
Clay sewer pipes — — — $24,950
Communication system — — 700,000 —
Lighting — — (36,100) —
Mechanical work — — 896,000 —
Modify electrical systems — — 1,121,100 —
Other — — (186,100) 212,600
Category totals — — 2,494,900 237,550
Water pollution control measures — — 876,000 $4,900
Contingencies 1,136,299 83,822,827 91,470,273 11,157,947
Other minor items† 3,830,000 — 6,862,344 11,201,054
Unreconciled difference‡ 11,314,760 292,554 17,254,107 (5,576,572)
Totals $186,737,131 $277,522,176 $302,000,000 $28,000,000
Sources: Toll bridge seismic retrofit program’s 30 percent design cost estimates; Chapter 327, Statutes of 1997 (SB 60) cost
estimates; and Chapter 907, Statutes of 2001 (AB 1171) cost estimates.
* The line item variances are intended to be representative of where variances occured. However, in some cases, bidders or
subsequent estimators used line item categories that were not consistent with initial budget categories.
† The increases in cost estimates for the Bay Bridge skyway and signature span do not include roadway work, such as traffic
control, landscaping, and lighting.
‡ Other minor items include supplemental work, state-furnished materials, right-of-way, and anticipated claims.
42 43
42 43
B
XIDNEPPA
margorP
tfiorteR
cimsieS
egdirB
lloT
eht
gnitceffA
snoisiceD
rojaM
fo
enilemiT
��������������������������� ���������������������������
����������������������������
���������������������������
��������������������
����������������������������
��������������������������� �������������������������
�����������������������������
��������������
����
����
����
����
����
���������������������������������� ��������������������������������
������������������������������������� �������������������������������������
���������������������������������
���������������������������
�����������������������������������
������������������������������������������������
�������������������������������
��������������������
�������������������������������
���������������������������������
������������������������
��������������������������������������
�������������������������������
�������������������
������������������������ ��������������������������
�����������������������������
�������������������������
�����������������������
����������������
���������������������������������
���������������������������������
����������������������
���������������
��������������������
�������������������
�������������������������������
����������
�������������� ���������������
����
����
����
����
����
egap
txen
eht
no
deunitnoc
44 45
DEUNITNOC
1.B
ERUGIF
����������������������������������
����������������������������� ����������������������������
������������������������������������������
�����������������������
������������������������������
�������������������
�������������������������������������
�������������������������������
����������������������������������
����������������������������������������
�����������������������������
������������������������������������
�����������������������
�����������������������������
�����������������������������
����������������������
���������������������������� ���������������������������������� �������������������������� ������������������������������
�����������������������������������
�������������������������������� ������������������
��������������
���������������
����
����
����
����
����
Agency’s comments provided as text only.
Business, Transportation and Housing Agency
980 9th Street, Suite 2450
Sacramento, CA 95814-2719
July 22, 2002
Elaine M. Howle
State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Dear Ms. Howle:
Attached is the Department of Transportation’s (Department) response to your draft report,
Department of Transportation: Seismic Retrofit Costs of State-Owned Toll Bridges Have
Significantly Exceeded the Department’s Original Estimates and May Go Even Higher
(#2001-122). I appreciate that your report points out that a variety of factors, most of
which were beyond the Department’s control, led to the cost increases and time delays in
retrofitting the toll bridges in the San Francisco Bay Area. Additionally, although remaining
uncertainties may result in a further increase in costs, I am confident that the Department
will continue to contain those costs under its control.
I am proud of the job the Department has done to develop the extremely complex,
unprecedented retrofit projects designed to meet the seismic safety standards for
California’s toll bridges. Through its efforts, the Department has overcome great
challenges to develop a seismic retrofit strategy that will maximize public safety and ensure
that the State’s transportation network will continue to operate in the event of a major
earthquake.
I appreciate the opportunity to respond to your audit report. If you need additional
information, please do not hesitate to contact me, or Michael Tritz, Chief of the Office of
Internal Audits within the Business, Transportation and Housing Agency,
at (916) 324-7517.
Sincerely,
(Signed by: Catherine J.K. Sandoval for)
MARIA CONTRERAS-SWEET
Secretary
Attachment
44 45
Department of Transportation
Office of the Director
1120 N Street
P.O. Box 942873
Sacramento, CA 94273-0001
July 18, 2002
Maria Contreras-Sweet, Secretary
Business, Transportation and Housing Agency
980 - 9th Street, Suite 2450
Sacramento, CA 95814
Dear Secretary Contreras-Sweet:
I am pleased to provide our response to the Bureau of State Audits’ (BSA) draft audit
report titled “Department of Transportation: Seismic Retrofit Costs of State-Owned Toll
Bridges Have Significantly Exceeded the Department’s Original Estimates and May
Go Even Higher.” The audit report recognizes the various reasons for rising costs and
time delays in completing the seismic retrofitting of selected toll bridges and does not
offer recommendations for the California Department of Transportation (Department) to
implement. However, the Department has the following general response to the draft
report.
The Department has worked hard over the past 10 years to deliver what are perhaps the
most challenging major bridge projects in the world. We are pleased that the audit of the
Toll Bridge Seismic Retrofit Program (Program) recognizes the Department’s effort on this
unique program.
The Program consists of seven of the State’s toll bridges. These projects are both
complex and unique and require resourcefulness, technical expertise, and persistence to
deliver. The State toll bridges are the largest and, from an engineering perspective, the
most complicated bridges in the State. Nowhere in the world have bridges as complex
as these been seismically retrofitted. Diverse soil conditions and foundations, seismic
forces ten times the original design forces, aged structures, heavy traffic volumes, conflicts
with utilities, air space lease concerns, handling of hazardous waste, and care to protect
sensitive resources all contribute to the difficulty in retrofitting these structures. As this
report is released, five of the seven bridges have been strengthened to resist the maximum
credible earthquake. Seismic standards have been achieved on the Benicia-Martinez,
Carquinez, San Mateo-Hayward, Vincent Thomas and San Diego-Coronado. Work to
achieve seismic safety on the Richmond-San Rafael and San Francisco-Oakland Bay
Bridges is underway. To date, approximately $1.2 billion has been spent to seismically
upgrade the State’s toll bridges.
46 47
Maria Contreras-Sweet
July 18, 2002
Page 2
The audit identifies a few challenges that caused the cost of the Program to increase to the
level incorporated into Assembly Bill 1171, Dutra, 2001. Elements contributing to the cost
increase are 1) the cost of engineering (capital outlay support) and 2) increases to various
items of work.
With regard to the first issue, the initial costs for engineering were developed when the
Department was using a statistical model to estimate such costs. That model did not
logically extend to such unique and large projects, so another method was chosen. This
method estimated the cost of engineering as a percentage of capital cost. As the Program
has progressed, the engineering effort has been detailed in a resource planning set of
tools and now captures the effort required to manage these projects. The Department
continues to monitor and aggressively manage the planning for and utilization of staff to
make sure the right work is done within the budget provided.
Secondly, estimating the cost to perform retrofit work on the toll bridges has proven quite
challenging. While the Department has drawn upon world-renowned expertise in the
development of the projects, much of the work has no historical precedence. Because
of the unique requirements and strategies for each project and the challenge to deliver
seismic safety quickly, the Department did not have cost histories needed to validate
estimates of these types of projects prior to SB 60. The cost estimates used as a basis
for AB 1171 contained contingencies to address uncertainties that still exist in this very
unique and complex Program. As an example, in order to award the Skyway contract on
the New East Span Project (Project), the Department did draw down contingencies for the
Project that were incorporated in the AB 1171 estimate. Efforts are underway to identify
cost saving measures in order to contain and reduce the costs of the future contracts on
the San Francisco-Oakland Bay Bridge so that the remaining contingency is sufficient to
address the needs of the Project.
While the Department has successfully overcome many challenges to complete the retrofit
of five bridges and begin construction on the other two, there are still many challenges
ahead. Continuous efforts are underway to review the costs, identify cost saving measures
for all remaining construction contracts and identify ways to lower the costs while achieving
seismic safety as quickly as possible.
46 47
Maria Contreras-Sweet
July 18, 2002
Page 3
The result of the Department’s continued effort to review the Program’s cost will be
contained in future Annual Reports to the Legislature. Just as was the case in previous
years, external factors beyond the Department’s control can affect the cost and schedule
of the Program. For example, the events of September 11, 2001, have created significant
uncertainties in the construction market which could be reflected in future contracts.
However, the Department is working aggressively to deliver the Program within the
funding authority provided by AB 1171. We look forward to the day when seismic safety is
achieved on all of the State’s toll bridges.
If you have any questions, or require further information, please contact Gerald Long,
External Audit Coordinator, at (916) 323-7122.
Sincerely,
(Signed by: Jeff Morales)
JEFF MORALES
Director
48 49
Agency’s comments provided as text only.
Bay Area Toll Authority
Metropolitan Transportation Commission
101 8th Street
Oakland, CA 94607-4700
July 24, 2002
Ms. Elaine M. Howle*
State Auditor
Bureau of State Audits
555 Capital Mall, Suite 300
Sacramento, California 95814
Dear Ms. Howle:
Thank you for an opportunity to comment on the draft report prepared by the Bureau
of State Audits titled Seismic Retrofit of State-Owned Toll Bridges Have Significantly
Exceeded the Department’s Original Estimates and May Go Even Higher. Based on
our review of the report, it appears that your staff has completed a thorough review and
assessment of a very complicated process and set of projects. I would like to offer a few
additional comments and suggestions for your report.
The report appears to imply that MTC’s process for and selection of a “signature” span
of the San Francisco-Oakland Bay Bridge East Span Replacement project was the major
1
cause of the project delay and cost increases. It should be noted that MTC selected the
design for the new east span less than one year after Senate Bill 60 was signed and only
six months after the bill became law on January 1, 1998. The delays on the project were
2
caused by other parties (notably the U.S. Navy) after the design selection was made. Also,
pursuant to Senate Bill 60, MTC provided the funding necessary to fully fund the selected
design “amenities” based on the estimates that Caltrans provided at that time. I believe that
these points need to be better clarified in your report.
I have also noticed that your report does not include any conclusions or recommendations.
Based on the information presented in the report, I believe that two recommendations
could be formulated, as follows:
1. Specific project cost estimates should not be incorporated into state statutes. As your
report indicates, for projects as large and as complex as the toll bridge seismic retrofit
program, project costs will fluctuate for a number of reasons. Inclusion of specific cost
estimates in state law will almost always require later legislative action to revise them.
* California State Auditor’s comments appear on page 51.
48 49
Ms. Elaine Howle
Page 2 of 2
July 24, 2002
2. For projects of this magnitude, Caltrans or any other state agency should be required
to provide more regular and on-going reports to the Legislature and the public. Current
statutes require Caltrans to provide annual reports of the seismic program and to report
to the Legislature if costs will exceed current estimates. I believe that Caltrans should
be required to provide quarterly or semi-annual reports that update costs, schedule and
progress of the toll bridge seismic program. As stated in your report, Caltrans did not
report cost increases until it issued its annual report in April 2001, more than four years
after the original cost estimates in SB 60.
If you have any questions regarding our response to you report or need any other
information, please do not hesitate to call Peter Lee of my staff at (510) 817-3206.
Sincerely,
(Signed by: Steve Heminger)
Steve Heminger
Executive Director
50 51
COMMENTS
California State Auditor’s
Comments on the Response
From the Metropolitan
Transportation Commission
To provide clarity and perspective, we are commenting
on the Metropolitan Transportation Commission’s
(commission) response to our audit report. The number
corresponds to the number we have placed in the response.
1
The commission says that our report appears to imply that
its process for and selection of a “signature” span of the
San Francisco-Oakland Bay Bridge east span replacement was the
major cause to the project delay and cost increase. As a point of
clarification, our report does not state, and is not intended to
imply, that the commission’s selection process for the signature
span caused a project delay. However, its choice, within its
authority, to have a signature span rather than a simple span did
result in a more expensive bridge.
2
The commission offers various reasons for cost increases and
time delays and states that these points need to be better
clarified in our report. In fact, we discuss each of the points
raised by the commission. Specifically, we note on page 19 that
the commission exercised its option and selected a bridge design
for the east span replacement in June 1998. In addition, we
discuss on page 23 the delays that resulted from the U.S. Navy’s
disagreement with the selected northern alignment.
50 51
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California State
Government Organization and Economy