CSA
Summary
Read the report at California State Auditor ↗
California
Public Utilities
Commission:
State Law and Regulations Establish
Firm Deadlines for Only a Small Number
of Its Proceedings
November 2003
2003-103
rotiduA
etatS
ainrofilaC
S
T
I
D
U
A
E
T
A
T
S
F
O
U
A
E
R
U
B
The first five copies of each California State Auditor report are free.
Additional copies are $3 each, payable by check or money order.
You can obtain reports by contacting the Bureau of State Audits
at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TTY (916) 445-0033
OR
This report is also available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
The California State Auditor is pleased to announce
the availability of an on-line subscription service.
For information on how to subscribe, please contact
the Information Technology Unit at (916) 445-0255, ext. 456,
or visit our Web site at www.bsa.ca.gov/bsa
Alternate format reports available upon request.
Permission is granted to reproduce reports.
� � �
��������� ���� ������
������������� �������������������
������������ �����������������������
November 25, 2003 2003-103
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its audit report
concerning our review of whether the California Public Utilities Commission (commission) promptly resolves the
various types of administrative proceedings it is responsible for conducting. This report concludes that few of the
1,602 proceedings the commission initiated between January 1, 2000, and June 30, 2003, were actually subject to
statutory deadlines. Additionally, although the commission did not complete 11 percent of its proceedings within
statutory requirements when applicable, or within its own internal guidelines, most times it did. Commission staff
provided various reasons, including delays caused by the commissioners themselves, delays caused because the
outcomes of some proceedings were dependent on other decisions or investigations, or delays that occurred when
the commission purposely kept certain proceedings open to take up related issues or to manage multiple phases. In
processing its more informal advice letters, which the commission uses to approve minor requests from utilities,
two factors contributed to delays: One was that some had a lower workload priority and the other was that some
required formal resolution or investigation.
Finally, according to several reports prepared by the Department of Finance between February 1998 and
February 2003, the commission lacks an adequate tracking system that would allow it to provide quantifiable
justification to support its requests for staffing. Thus, although the commission cited workload and inadequate
staffing as contributing to delays in processing its formal proceedings and advice letters, it was unable to provide
us with any staffing workload analyses to support its belief.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
�������������������
�������������������������������������������������� ���������������������������������������� ������������������
CONTENTS
Summary 1
Introduction 5
Chapter 1
Although Some of the Commission’s Proceedings
Were Delayed, Most Are Excluded From
Statutory Deadlines 15
Recommendations 32
Chapter 2
The Commission Processed Most of Its Advice
Letters Within Its Internal Goal of 90 Days 33
Recommendations 40
Chapter 3
Although the Commission Cited Workload and
Inadequate Staffing as Contributing to Delays,
the Lack of a Workload Tracking System Hinders
Its Ability to Justify Staffing Needs 43
Recommendation 46
Response to the Audit
California Public Utilities Commission 47
California State Auditor’s Comments
on the Response From the
California Public Utilities Commission 51
SUMMARY
RESULTS IN BRIEF
Audit Highlights . . . In conducting its various regulatory activities, the California
Public Utilities Commission (commission) typically uses
Our review of whether the
a formal proceeding to review an issue and to ultimately
California Public Utilities
Commission (commission) make a final policy, procedural, or other type of decision.
promptly resolves formal and Although Senate Bill 960 (SB 960), Statutes of 1996, establishes
informal proceedings found
several deadlines for processing them, few of the 1,602 formal
the following:
proceedings the commission initiated between January 1, 2000,
þ Few of the 1,602 formal and June 30, 2003, are subject to those deadlines. SB 960
proceedings the
requires that the commission resolve only those proceedings
commission initiated
categorized as adjudicatory that require hearings within
between January 1, 2000,
and June 30, 2003, 12 months. According to its chief administrative law judge (ALJ),
were subject to the commission further interprets SB 960 to apply only to those
statutory deadlines.
proceedings subject to evidentiary types of hearings, making the
þ Commission staff provided deadline applicable to only 39 of the proceedings during the time
various reasons for delays, period we reviewed. Our legal counsel advised that in view of
including that the outcomes
the commission’s broad rule-making authority, the commission’s
of some proceedings
interpretations of statutes and its own rules are given great weight
were dependent on other
decisions or investigations by the courts. Thus, we relied on the commission’s interpretations
or the proceedings were of the relevant statutes in determining whether the commission
purposely kept open to
is complying with statutory and regulatory deadlines for
take up related issues
proceedings. In so doing, state law and regulations apply to only a
or to manage them in
multiple phases. few of the commission’s proceedings.
þ Two factors contributed
The Legislature did include intent language in SB 960 that
to delays in processing
the more informal the commission should establish reasonable time periods (not
advice letters, which to exceed 18 months) for resolving proceedings not covered
the commission uses to
by the deadline. According to the chief ALJ, the commission
approve minor requests
considers the SB 960 language to be a guideline encouraging
from utilities: Some had
a lower workload priority rigorous case management, and our legal counsel advises that
and some required formal it does not legally compel the commission to complete other
resolution or investigation.
proceedings within 18 months. However, Assembly Bill 1735
Although the commission cited (AB 1735), which takes effect January 1, 2004, statutorily
workload and inadequate requires the commission to resolve rate-setting and quasi-
staffing as contributing
legislative proceedings within 18 months of issuing a scoping
to delays in processing its
formal proceedings and advice memo.1 Unlike SB 960, the new law does not explicitly state
letters, the lack of a workload that only proceedings with hearings are subject to its legal
tracking system hinders its
requirements. Nevertheless, the chief ALJ explained that the
ability to justify staffing needs.
1 The commission typically issues a scoping memo early on in a proceeding that includes
a proposed schedule.
California State Auditor Report 2003-103 11
new law explicitly states that it applies when there is a scoping
memo and, according to statute and regulation, scoping memos
are required in proceedings that require evidentiary hearings.
Therefore, the chief ALJ noted that the commission intends to
apply AB 1735 to only those types of proceedings. Thus, if the
new law had been in effect during the period we reviewed for
our audit, it would have applied to only 105 of 1,323 rate-setting
and quasi-legislative proceedings. Because AB 1735 applies to so
few proceedings when using the commission’s interpretation,
this new requirement may not be as effective in reducing the
time it takes to resolve such proceedings as would a statute that
clearly applies to all proceedings.
The commission provided various reasons to explain the delays
in resolving 45 proceedings we reviewed that exceeded either
statutory deadlines or guidelines. For example, the commission
held four proceedings open to resolve numerous related issues
or to manage multiple phases of the same proceeding. The chief
ALJ stated that the commission will hold proceedings open if it
believes evidence taken earlier will continue to be referred to in
subsequent phases or when successive decisions will contribute
to completing a single project. The commission actually resolved
five of the proceedings promptly that appeared to exceed
deadlines, but its tracking system does not appropriately reflect
their resolution when they are reopened. The commissioners
or management staff delayed another eight proceedings
beyond their deadlines for various reasons, including the
need to reassign a proceeding to a new commissioner who
required additional time to become familiar with it, assigning
a proceeding a lower priority, or allowing commissioners more
time to consider how the energy crisis of 2000 and 2001 would
affect a proceeding.
The commission uses more informal advice letters to address
minor requests from utilities. We identified various factors that
contributed to delays in the resolution of a sample of 90 such
letters. For example, the commission either delayed or failed
to input a closing date in its tracking system for 27 of the
advice letters it processed on time. Consequently, the electronic
database does not provide the commission with accurate data
regarding the status of advice letters. The commission indicated
that it considered another 16 advice letters as lower priority due
to workload. However, we were unable to determine whether
it requires additional staff to promptly process advice letters
22 California State Auditor Report 2003-103 California State Auditor Report 2003-103 33
because it has not implemented a workload tracking system that
would allow us to assess the adequacy of current staffing levels.
The commission was unable to provide us an explanation for
its delay in resolving another 17 advice letters, 16 of which were
the responsibility of the telecommunications division—one of the
three divisions that process them. This same division has not
adequately tracked and maintained its advice letters, which may
have contributed to its inability to provide explanations for
delays in resolving them.
Although the commission indicated that staffing is a limiting
factor in promptly processing its formal proceedings and advice
letters, it was unable to provide us with workload analyses to
support these contentions. In fact, the Department of Finance
(Finance), in various reports and management letters it prepared
between February 1998 and February 2003, reported that the
commission lacks a workload tracking system that would allow
it to justify its staffing needs. In response to a February 2003
management letter, the commission began to revise its workload
tracking system to address Finance’s concerns; however, it does
not anticipate implementing key phases of the new system until
the end of 2003 or the beginning of 2004. Thus, during our audit
the commission was unable to provide us any staffing analyses
that would allow us to determine whether its staffing levels are
adequate to promptly process formal proceedings and advice letters.
RECOMMENDATIONS
To ensure that it accurately reports the closing date of a
proceeding, the commission should modify its tracking system
to retain the original closing date as well as record its subsequent
closing date for those proceedings it reopens.
To ensure that the information included in its tracking system
is accurate for reporting on the timeliness of advice letters, the
commission should review all advice letters in the system and
close those that it has completed.
The commission should continue to work with Finance on
improving its workload tracking system so that it can justify its
staffing needs.
22 California State Auditor Report 2003-103 California State Auditor Report 2003-103 33
AGENCY COMMENTS
The commission indicates that it agrees with the numerical facts
contained in the report and it accepts the recommendations.
However, the commission provided brief comments concerning
three aspects of the report. n
44 California State Auditor Report 2003-103 California State Auditor Report 2003-103 55
INTRODUCTION
BACKGROUND
The California Public Utilities Commission (commission)
consists of five commissioners appointed by the governor,
with Senate approval, for six-year staggered terms. The
governor appoints one of the five to serve as the commission
president. The commission has broad powers to regulate
privately owned and operated telephone, electric, natural
gas, water, and transportation companies in California. Its
responsibilities include establishing service standards and safety
rules, approving retail rate changes, monitoring the safety of
operations under its jurisdiction, overseeing the electricity
and natural gas markets to inhibit anticompetitive activities,
prosecuting unlawful utility actions, and governing business
relationships between utilities and their affiliates.
As of June 30, 2003, the commission had 882 filled and
74 vacant positions. It employs economists, engineers,
administrative law judges (ALJ), accountants, lawyers,
and safety and transportation specialists in addition to
support staff.
Currently, the commission is organized into 10 divisions, which
include three industry divisions and an administrative law
judge division that we discuss in this report. The administrative
law judge division supports commission decision making
by processing formal filings, facilitating alternative dispute
resolution, conducting hearings, developing an adequate
administrative record, preparing timely proposals for com-
mission consideration, and preparing and coordinating
commission business meeting agendas. The commission has
organized three industry divisions to assist it as follows:
• The telecommunications division develops and implements
policies and procedures to facilitate competition in all
telecommunications markets, addresses regulatory
changes required by state and federal legislation, assures
affordable access to essential services, and provides
consumer protections.
44 California State Auditor Report 2003-103 California State Auditor Report 2003-103 55
• The energy division advises whether to approve, deny, or
modify all electric and natural gas utility requests not assigned
for hearings; oversees compliance of orders; provides technical
assistance; and advises and informs the commission about
major developments affecting energy utilities.
• The water division investigates water and sewer system
service quality issues and analyzes and processes utility rate
change requests.
In conducting its various regulatory activities, the commission
often uses a formal proceeding to review an issue and to
ultimately make a final policy, procedural, or other type of
decision. These proceedings may require that hearings take place
as well. Utilities use a more informal advice letter to request the
commission’s approval for minor or noncontroversial actions,
most often for a rate or service change.
FORMAL PROCEEDINGS
Generally, the commission uses three types of formal proceedings,
as shown in Table 1, to regulate utilities. When a utility,
consumer, or the commission itself initiates a proceeding, the
appropriate documents must first be filed with its docket office.
The docket office staff review the documents for completeness,
provide them with a “date-filed” stamp, and assign them an
identifying number. The commission uses the date filed as the
beginning date for the proceeding when determining whether it
has met certain deadlines established in law. The commission also
notifies the public of the new proceeding by listing it in the daily
calendar located on its Web site. Finally, the docket office staff
also enter the proceeding into the commission’s case information
system for tracking purposes.
In all formal proceedings, the chief ALJ, who is also the chief
of the administrative law judge division, and the commission
president assign at least one commissioner and an ALJ to
guide the case through the commission’s review process. The
commission also makes a preliminary determination of the
categorization of each proceeding initiated by an application
and whether or not evidentiary hearings will be required.
Generally, the ALJ conducts the hearings, meets with the
assigned commissioner to discuss developments and issues,
and, in consultation with the assigned commissioner, prepares
66 California State Auditor Report 2003-103 California State Auditor Report 2003-103 77
TABLE 1
The Commission Categorizes Proceedings Into Three Types
Proceeding Generally
Type of Activity Description Categorized as Indicated
Application Used when a utility or transportation company requests Rate setting
commission authority to do something, such as increase rates.
Formal complaint Used when a consumer advocacy group or individual alleges Adjudicatory
that a utility company has done something inappropriate and
wants the commission to correct the problem.
Order instituting investigation Used when the commission initiates an investigation to examine Quasi-legislative or
specific issues that may lead to new or changed legislation, Adjudicatory
programs, enforcement, policies, or rates.
Order instituting rule making Used to create or revise rules or guidelines that affect a utility or Quasi-legislative
a broad sector of an industry.
a proposed decision. After making these assignments, the
commission holds a prehearing conference to schedule hearing
dates and to give participants a chance to outline the issues on
which they intend to focus. The assigned commissioner will
consider the application, protests, responses, and the prehearing
conference statements, and will issue a ruling, referred to as a
scoping memo. The scoping memo designates the category or
may confirm the category of the proceeding as adjudicatory, rate
setting, or quasi-legislative; establishes a schedule and scope for
the proceeding; and may also confirm whether the commission
believes the proceeding will require evidentiary hearings.
According to the chief ALJ, how a proceeding is categorized and
whether it requires a hearing is significant when determining
its timelines. In fact, in 1996, the Legislature and the governor
approved Senate Bill 960 (SB 960), which establishes several
deadlines for those specific proceedings that require hearings.
According to the chief ALJ, SB 960 was enacted in an effort
to improve the quality and promptness of the commission’s
decision-making process. For example, SB 960 requires that
the commission resolve within 12 months of initiation any
proceeding it has categorized as an adjudicatory case requiring
hearings, unless it issues an order extending the deadline. The
chief ALJ indicated that the commission interprets “resolve”
to mean that it has addressed and disposed of the substantive
issues identified in the scoping memo and it has assigned a
decision number to an order it has adopted.
66 California State Auditor Report 2003-103 California State Auditor Report 2003-103 77
Although SB 960 does not define hearings, the chief ALJ
indicated that the commission has continued its long-standing
administrative practice of interpreting a “hearing” to refer only
to evidentiary hearings. Typically, adjudicatory proceedings or
fact-specific complaint cases involve material disputed facts that
must be tested by evidentiary hearings. Evidentiary hearings
are those in which parties present their evidence through direct
testimony and exhibits. Additionally, other parties may question
witnesses in an attempt to clarify or challenge aspects of the
testimony. The commission’s interpretation of hearings excludes
other types of hearings such as workshops, law and motion
hearings, public participation hearings, and arbitration hearings.
The Legislature also included in the intent language of SB 960
that the commission should establish reasonable timelines for
the resolution of proceedings other than adjudicatory, that
it meet those timelines, and that the timelines not exceed
18 months. The commission views this intent language as
encouraging rigorous case management and uses it as a planning
tool for all other proceedings not categorized as adjudicatory
and requiring evidentiary hearings. This would include all
rate-setting and quasi-legislative cases—both those requiring
hearings and those that do not—in addition to the remaining
adjudicatory cases not requiring evidentiary hearings. The
chief ALJ also points out that although the Legislature did not
codify the 18-month timeline in statute, the commission’s
rules of practice and procedures, Article 2.5, Rule 6(e), which
are also codified in the California Code of Regulations,
require that parties to a proceeding propose time schedules
for consideration by the assigned ALJ and commissioner.
Rule 6(e) also indicates that the proposed time schedule should
be no longer than 12 months for adjudicatory proceedings
or 18 months for rate-setting or quasi-legislative proceedings.
However, Rule 6.6 states that whenever the commission
determines that a proceeding does not require evidentiary
hearings, the rules and procedures of this article do not apply.
While this seems inconsistent with the broad intent language
of SB 960, the rules are consistent with the commission’s
long-standing administrative practice of limiting the 12-month
deadline to proceedings requiring evidentiary hearings.
According to the chief ALJ, the commission does depart from
these rules of practice and procedures when circumstances
justify it to do so, but any departure would have to be consistent
with statute and due process.
88 California State Auditor Report 2003-103 California State Auditor Report 2003-103 99
The California Constitution and the Public Utilities Code
empower the commission to establish its own procedures,
subject to statute and due process requirements. Further,
California courts have found that the commission is “not an
ordinary administrative agency, but a constitutional body
with broad legislative and judicial powers.” Our legal counsel
advised that in view of the commission’s broad rule-making
authority, the commission’s interpretations of statutes and its
own rules are given great weight by the courts. Thus, we relied
on the commission’s interpretations of the relevant statutes
in determining whether the commission is complying with
statutory and regulatory deadlines for proceedings.
For all proceedings requiring hearings, state law has also
established shorter, more specific deadlines within the overall
12- and 18-month timelines as shown in the Figure on the
following page.
According to the chief ALJ, the submission of a proceeding
is the date when the formal record of the proceeding closes;
thus, the time between initiation and submission signifies
the beginning and the end of the period during which the
parties provide the pleadings, evidence, comments, and briefs
on which the commission will base its decision. As the Figure
indicates, for those proceedings categorized as adjudicatory,
state law requires that the assigned commissioner or ALJ prepare
and file a decision not later than 60 days after the proceeding
has been submitted for decision. The chief ALJ indicated that
the commission believes these 60 days must occur within the
12-month deadline for resolving an adjudicatory proceeding.
State law also requires that the decision become final 30 days
after its filing unless an appeal is filed or the commission
requests a review. Additionally, as shown in the Figure, the chief
ALJ stated that for those proceedings categorized as rate setting
and quasi-legislative, the deadlines related to the preparation
of a proposed decision, final decision, and alternate decision
must all occur within the 18-month guideline for resolving
those proceedings. An alternate decision is one prepared by a
commissioner who did not prepare the proposed decision and
the alternate decision substantially revises the original.
88 California State Auditor Report 2003-103 California State Auditor Report 2003-103 99
FIGURE
The Commission’s Formal Proceeding Process
����������������������������������������
��������������������
��������������������������������������������������������������������
�������������������������������������������
�����������������������������������������������
��������������������������������������������������
�������� ����������
�������� ��������
��������������������
����������������������������������������
���������������������������������������������������
�����������������������������������������������������
����������������������������������������������������
����������������������������������������������������
�������������������������������������������
����������������������� �������������������������������������������
�����������������
����������������������������������������� ���������������������������������������
���������������������������������������������� ������������������������������������������
�������������������������������������������� �����������������������������������������
������������������������������������������
��������������������������������������� ���������������������������������������
����������������������������������������� �����������������������������������������
���������������������������������� ����������������������������������
����������������� �����������������
������������������������������������������� ����������������������������������������
������������������������������������������ ������������������������������������������
���������������������������������� ������������������������������������������
����������������� �����������������
������������������������������������������� ����������������������������������������������
���������������������������������������������� �����������������������������������������������
�������������������������������������� �����������������������������������������������
�������������������������� �������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������
1100 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1111
ADVICE LETTERS
The commission generally uses advice letters as a more informal
procedure to address utility companies’ requests that are minor,
noncontroversial, or otherwise appropriate for processing
without a hearing or formal proceeding. Typically, a utility
company initiates and files with the commission an advice letter
to change the lawful rates, charges, rules, or conditions under
which the utility must operate, or to change a service or offer
a new one. According to commission staff, some advice letters
require very complex, time-consuming analysis by senior staff
and a commission vote on a formal resolution.
Advice letters are processed by one of three divisions depending
on the type of utility—the telecommunications division, the
energy division, or the water division. When an advice letter is
received, the appropriate division stamps the letter with a filed
date and the commission notifies the public of the advice letter
by publishing the letter in the daily calendar located on its Web
site. Eventually, the appropriate division’s staff also inputs the
advice letter into the commission’s proposal and advice letter
tracking system.
State law and regulations do not establish any deadlines for the
commission to review and approve advice letters. However,
the Public Utilities Code, Section 455, provides that advice
letters generally become effective 30 days from the date filed by the
utility unless the commission suspends them. Additionally,
the commission itself, pursuant to its rule-making authority,
which is founded in the California Constitution and statutes,
adopted General Order 96-A, which provides that advice letters
become effective not less than 40 days after filing because this
is the time frame typically necessary for approval. According
to commission staff, the commission interprets these two
requirements as generally allowing a utility to implement the
proposed action in its advice letter 40 days after filing unless
the commission suspends the advice letter within 30 days.
However, according to commission staff, many utilities choose
not to place the advice letter into effect under this time frame,
instead preferring to first obtain the commission’s approval
because, ultimately, Section 455 allows the commission to later
disapprove or modify the action taken by a utility. If this were
to occur, the utility might be required to undo the actions in the
advice letter, which could negatively affect it and its customers.
As a result, commission staff indicated that they will often reach an
agreement with a utility on what both consider to be a reasonable
1100 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1111
effective date, and the utility will include that date in the
advice letter or include a statement in the advice letter that it is
effective upon the commission’s approval.
However, commission staff indicated that for those instances
when a utility insists that an advice letter become effective in
less than the minimum of 40 days the commission believes it
will require for review and approval, it will suspend the advice
letter within 30 days of filing as outlined in the Public Utilities
Code, Section 455.
According to commission staff, the use of advice letters has
somewhat expanded in recent years, and they believe that the
historic advice letter process as outlined in General Order 96-A
has become inadequate in relation to the volume and variety
of advice letters submitted for review. Energy division staff also
noted that because of the increase in the quantity of advice
letters, the complexity of the issues raised, and the need to
prioritize them, processing time has lengthened. The three
divisions that process advice letters have an internal goal of
90 days after filing to process and close them. Therefore, when
we reviewed reasons for delays in processing advice letters, we
focused on those that exceeded the internal goal of 90 days
rather than the 30- or 40-day time frames described earlier.
SCOPE AND METHODOLOGY
The Joint Legislative Audit Committee (audit committee)
requested that the Bureau of State Audits determine whether
the commission promptly completes the various types of
administrative proceedings it is responsible for conducting. The
audit committee asked that we determine how the commission
sets priorities in the water, telecommunications, and energy
areas when conducting its various types of administrative
proceedings. Additionally, we were asked to review staffing levels
to assess whether these levels are adequate for the commission to
comply with its statutory mandates regarding administrative
proceedings. As part of the assessment, we were to consider
other studies that may have been performed related to staffing.
Finally, the audit committee requested that we identify any
timelines contained in law or regulations for the completion of
proceedings. We were asked to select a sample of proceedings
that exceeded the timelines and remain unresolved and another
sample that exceeded the timelines but were resolved and
determine the reasons for delays.
1122 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1133
To find out how the commission sets priorities for formal
proceedings, we interviewed staff and reviewed its criteria and
procedures for prioritizing its formal proceedings. Further,
we selected a sample of 40 proceedings to confirm whether
the commission prioritized them in accordance with its
criteria. To determine how the commission sets priorities for
informal advice letters, we interviewed staff in the energy,
telecommunications, and water divisions. We also reviewed
those letters within our sample that the commission considered
low priority to assess whether each division prioritizes its advice
letters in accordance with stated criteria.
To understand the commission’s responsibilities and timelines
for resolving formal proceedings, we interviewed staff, reviewed
policies and procedures, and researched all relevant state laws
and regulations. Our review identified a 12-month statutory
deadline and an 18-month guideline—depending on whether
the category of a proceeding is adjudicatory, rate setting, or
quasi-legislative. Additionally, the commission is required to
meet three shorter, more specific deadlines within the overall
12- and 18-month timelines. We selected a sample of 45 of a
total 1,602 proceedings that the commission initiated between
January 1, 2000, and June 30, 2003, for which the commission’s
case information system showed that it did not resolve
within the statutory deadline of 12 months for adjudicatory
proceedings requiring hearings or the guideline of 18 months
for all other formal proceedings it conducts. We excluded from
our sample selection 480 proceedings related to transportation
because these were not within the scope of our audit. Of the
45 proceedings we selected for testing, 20 had been resolved
and closed and 25 were still open as of June 30, 2003. We
ensured our sample represented the commission’s three major
areas—telecommunications, energy, and water. To understand
why they were delayed, we reviewed each proceeding’s files
and interviewed the ALJs, commissioners, and commission
management responsible for each proceeding.
We selected another sample of proceedings for which the
commission failed to meet the three shorter statutory deadlines
that are within the overall 12- and 18-month timelines,
excluding any transportation proceedings, and further limited
our sample to only those with evidentiary hearings because
of the commission’s interpretation of the statutory deadlines.
We interviewed the ALJs, commissioners, or commission staff
responsible for the selected proceedings to determine the
reasons for any delays.
1122 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1133
We also selected a sample of 90 of a total 16,128 advice letters
initiated between January 1, 2000, and June 30, 2003. All of
the letters we sampled exceeded the commission’s internal goal
of 90 days. We selected the letters in proportion to the total
advice letters processed by the three divisions. This resulted in
our sample comprising 54 telecommunications, 29 energy, and
seven water advice letters. Our sample included 46 letters that
had been resolved and closed and 44 that were still active as of
June 30, 2003. We reviewed advice letter files and interviewed
staff from each of the three divisions to determine why the
commission took more than 90 days to process them.
Finally, to perform our assessment of the commission’s staffing
levels, we reviewed several reports prepared by the Department
of Finance (Finance) between February 1998 and February 2003
in which Finance concluded that the commission lacks an
adequate workload tracking system. In addition, we interviewed
commission staff and obtained preliminary documents to gain
an understanding of the new workload tracking system it is
currently developing. However, because the commission will
not complete its new workload tracking system until after the
completion of our audit, we were unable to assess the adequacy
of current staffing levels because we had no quantifiable
justifications to support its staffing needs. n
1144 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1155
CHAPTER 1
Although Some of the Commission’s
Proceedings Were Delayed, Most Are
Excluded From Statutory Deadlines
CHAPTER SUMMARY
The California Public Utilities Commission (commission)
typically uses formal proceedings to review and issue
decisions in policy, procedural, and other areas. State law
has established several deadlines the commission must follow
when processing formal proceedings. Although it initiated
1,602 proceedings between January 1, 2000, and June 30, 2003,
few of them are subject to the deadlines established by
Senate Bill 960 (SB 960). The legal framework established
in SB 960 requires that the commission resolve only those
proceedings categorized as adjudicatory requiring hearings
within 12 months. The commission interprets SB 960, according
to its chief administrative law judge (ALJ), as applying only to
those proceedings subject to evidentiary hearings. Our legal
counsel advised that in view of the commission’s broad rule-
making authority, the commission’s interpretations of statutes
and its own rules are given great weight by the courts. Thus,
we relied on the commission’s interpretations of the relevant
statutes in determining whether the commission is complying
with statutory and regulatory deadlines for proceedings. Using
this interpretation, the 12-month deadline applies to only
39 proceedings initiated during the period we reviewed.
Although the Legislature did not mandate a similar deadline
for the remaining proceedings, it did include intent language
in SB 960 that the commission should establish reasonable
time periods for resolving other proceedings not to exceed
18 months. The chief ALJ stated that the commission considers
this intent language to be a guideline encouraging rigorous case
management, and our legal counsel has advised that it does not
legally compel the commission to complete these proceedings
within 18 months.
Although it did not complete 11 percent of its proceedings
within the applicable statutory requirements or its own internal
guidelines, most times it did. The commission provided various
reasons to explain the delays in resolving the 45 proceedings
1144 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1155
we reviewed. For example, it held four proceedings open to
resolve numerous related issues or to manage multiple phases
of the same proceeding. The commission actually resolved
five proceedings that appeared to exceed the timelines within
the statutory limits, but the system tracking them does not
appropriately reflect their resolution when they are reopened.
Commissioners or management staff delayed eight other
proceedings beyond their timelines for various reasons,
including reassigning them to a new commissioner who
required additional time to become familiar with the issues,
assigning them a lower priority, or allowing the commissioners
more time to consider how the energy crisis of 2000 and 2001
would affect them.
State law also includes three deadlines within the 12- and
18-month time frames that direct the commission to issue draft
decisions within 60 or 90 days of submission, depending on the
type of proceeding, and to approve final decisions for rate-setting
and quasi-legislative cases within 60 days of the draft decision. We
identified three main factors that delayed 19 draft decisions and
four final decisions—commissioners needing additional time to
review and research complicated issues, the heavy workload of the
administrative law judges, and the impact of the energy crisis.
THE COMMISSION INITIATED 1,602 PROCEEDINGS
BETWEEN JANUARY 1, 2000, AND JUNE 30, 2003
Although the commission resolved most proceedings within
the time frames established in California laws and regulations,
it experienced delays for roughly 11 percent of the proceedings.
The proceedings it did not resolve promptly were frequently
complex, and sometimes the reasons for the delays were beyond
its control. For example, the energy crisis that gripped California
beginning in 2000 caused delays in several proceedings while
the commission worked to resolve issues that directly affected
California ratepayers.
Using the commission’s case information system, we identified
The commission 1,602 proceedings it initiated during our review period
experienced delays in of January 1, 2000, through June 30, 2003. As shown in
closing 177, or 11 percent, Table 2, the commission experienced delays in closing 177, or
of the proceedings initiated 11 percent, of them. As described in the Introduction, for each
between January 1, 2000, type of proceeding SB 960 established timelines for resolving
and June 30, 2003. them, either in statute or through its intent language. For
adjudicatory proceedings that require hearings, statutes require
1166 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1177
commission resolution within 12 months of filing, whereas
for rate-setting and quasi-legislative proceedings, the intent
language establishes a time period for resolution of 18 months.
However, according to its reading of SB 960, the commission
makes a further distinction by interpreting the 12-month
deadline to apply only to those proceedings with hearings that
are considered evidentiary in nature.
TABLE 2
Few Proceedings Exceeded the Statutory or Intent Language Deadlines
Total Resolved Total Exceeding Total Number
Type of Proceeding Deadline Within Deadline Deadline of Proceedings
Rate setting with hearing 18 Months 57 47 104
Rate setting without hearing 18 Months 1,106 82 1,188*
Adjudicatory with hearing 12 Months 20 19† 39
Adjudicatory without hearing 18 Months 222 18 240‡
Quasi-legislative with hearing 18 Months 0 1 1
Quasi-legislative without hearing 18 Months 20 10 30
Totals 1,425 177§ 1,602
Source: The commission’s case information system for proceedings initiated between January 1, 2000, and June 30, 2003.
*Included in these 1,188 are 32 rate-setting proceedings that, as of June 30, 2003, were active and for which the commission
may yet hold hearings.
† Sixteen adjudicatory proceedings with hearings were extended by order of the commission within the initial 12 months as
allowed by state law.
‡ Included in these 240 are 13 adjudicatory proceedings that, as of June 30, 2003, were active and for which the commission may
yet hold hearings.
§ It initially appeared as if the commission had exceeded its established timelines for 220 proceedings. However, we found that 43
had been incorrectly coded in the case information system as open, when in fact they were closed and, thus, not actually delayed.
THE LAW EXCLUDES MOST PROCEEDINGS FROM THE
STATUTORY DEADLINE
Current state law establishes that only adjudicatory proceedings
with hearings are subject to statutory deadlines. Furthermore,
according to the chief ALJ, the commission has interpreted
state law to apply to only those proceedings for which it has
conducted evidentiary hearings. Consequently, only 39 of the
1,602 proceedings it opened in the time period we reviewed
are subject to current statutory deadlines. The Legislature
and governor recently approved a new law that takes effect
January 1, 2004, which establishes a deadline of 18 months to
1166 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1177
resolve rate-setting and quasi-legislative proceedings. The chief
ALJ explained that the new law explicitly states that it applies
when there is a scoping memo and, according to statute and
regulation, scoping memos are required in proceedings that
require evidentiary hearings. Therefore, the chief ALJ noted that
the commission intends to apply the new law to only those
types of proceedings. Because the commission has interpreted
it to apply to so few proceedings, this new requirement may
not be as effective in reducing the time it takes to resolve
such proceedings as would a statute that clearly applies to all
proceedings. Our legal counsel advised that in view of the
commission’s broad rule-making authority, the commission’s
interpretations of statutes and its own rules are given great
weight by the courts. Thus, we relied on the commission’s
interpretations of the relevant statutes in determining whether
the commission is complying with statutory and regulatory
deadlines for proceedings.
The categorization of a proceeding as adjudicatory, rate setting,
or quasi-legislative and whether the proceeding requires a
hearing is significant in determining whether the commission
must meet statutory deadlines. According to state law,
adjudicatory proceedings for which hearings have been held
must be completed within 12 months after filing, unless the
commission issues an order extending the deadline. However,
Using the commission’s the other types of proceedings are not subject to a statutory
interpretation of statutes, deadline for completion.
of the 1,602 proceedings
initiated from As Table 3 illustrates, the commission has held evidentiary
January 1, 2000, hearings for only 144 of the 1,602 proceedings initiated between
through June 30, 2003, January 1, 2000, and June 30, 2003; however, it categorized
only 39 were subject to a only 39 of these 144 proceedings as adjudicatory requiring an
statutory deadline. evidentiary hearing. Thus, according to its interpretation, state
law requires it to resolve only 39 proceedings within 12 months.
Furthermore, although the commission’s records indicate that
19 of these 39 proceedings exceeded the 12-month deadline,
in 16 instances the commission issued an order extending the
deadlines before the 12-month period had elapsed, as permitted
by law. The commission also issued extension orders for another
two proceedings late but within two months of the 12-month
deadline. The remaining proceeding was resolved within
16 months with no extension order being issued. Moreover,
1188 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1199
TABLE 3
Most Formal Proceedings Do Not Require Evidentiary Hearings;
Thus Are Not Subject to Statutory Requirements
Evidentiary Proceeding Still Active and May Evidentiary Hearings
Type of Proceeding Hearings Held Yet Hold Evidentiary Hearings Not Required Totals
Adjudicatory 39 13 227 279
Rate setting 104 32 1,156 1,292
Quasi-legislative 1 0 30 31
Totals 144 45 1,413 1,602
Source: The commission’s case information system for proceedings initiated between January 1, 2000, and June 30, 2003.
during the period we tested, rate-setting, quasi-legislative, and
adjudicatory proceedings without evidentiary hearings were
not subject to a statutory deadline for resolution. However,
the intent language in SB 960 calls for the commission to
resolve these types of proceedings within 18 months of filing.
According to the chief ALJ, the commission considers this intent
language to be a guideline for rigorous case management, and
our legal counsel advises that this does not legally compel the
commission to complete these proceedings within 18 months.
Therefore, the statutory oversight mechanisms created by
SB 960 that apply to the commission involve only 39 of
1,602 proceedings initiated during the period we reviewed.
The Legislature and governor recently approved Assembly Bill 1735
(AB 1735), which becomes effective January 1, 2004, and requires
the commission to resolve all quasi-legislative and rate-setting cases
within 18 months of issuing a scoping memo unless the commission
makes a written determination that the deadlines cannot be met.
The commission typically issues a scoping memo that includes
a proposed schedule early on in a proceeding. AB 1735 does not
explicitly state that only proceedings with hearings will be subject
to its legal requirements. However, the chief ALJ explained that
the new law explicitly states that it applies when there is a scoping
memo and, according to statute, regulation, and the commission’s
interpretation, scoping memos are required in proceedings that
require evidentiary hearings. Therefore, the chief ALJ noted that
the commission intends to apply AB 1735 to only those types of
1188 California State Auditor Report 2003-103 California State Auditor Report 2003-103 1199
proceedings. If the new law had been in effect during the period
If the new law, AB 1735, reviewed in our audit, it would have applied to 105 proceedings with
had been in effect during evidentiary hearings of the 1,323 rate-setting and quasi-legislative
the period reviewed in proceedings shown in Table 3 (1,292 rate setting plus 31 quasi-
our audit, it would have legislative). Because the commission has interpreted AB 1735 to
applied to only 105 of apply to so few additional proceedings, this new requirement
the 1,323 rate-setting may not be as effective in reducing the time it takes to resolve such
and quasi-legislative proceedings as would a statute that clearly applies to all proceedings.
proceedings.
The commission narrowly interprets hearings to refer only
to evidentiary-type hearings and excludes from its definition
other types of hearings such as law and motion hearings, public
participation hearings, arbitration hearings, and workshops.
Using this definition, of the 1,602 proceedings initiated from
January 1, 2000, through June 30, 2003, only 39 were subject to
a statutory deadline. Therefore, if the Legislature intended that
all the types of proceedings the commission initiates should
be subject to statutory deadlines, it would need to revise the
law to either provide deadlines for all proceedings, regardless
of whether hearings are required, or to a lesser degree, expand
the definition of hearings to include other types not specifically
identified as evidentiary.
MANY FACTORS CONTRIBUTED TO THE COMMISSION’S
DELAYS IN RESOLVING FORMAL PROCEEDINGS
Although the commission did not complete 11 percent of its
proceedings within statutory requirements when applicable,
or within its own internal guidelines, most times it did.
Commission staff provided various reasons, including
delays by commissioners themselves, delays caused because
the outcomes of some proceedings were dependent on other
decisions or investigations, or delays when the commission
purposely kept certain proceedings open to take up related
issues or to manage multiple phases. We made no judgment as
to whether the commission’s explanations for these delays were
reasonable; however, nothing came to our attention that would
lead us to believe its explanations were not reasonable.
To determine the reasons for delays, we selected a sample of
25 open and 20 closed proceedings from those that exceeded
either the statutory deadline or internal guideline without
regard to whether the proceedings involved evidentiary hearings
or were extended through a commission order. Applying the
commission’s interpretation, only seven of the adjudicatory
2200 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2211
proceedings in our sample were subject to the statutory
deadline of 12 months and the remaining 38 were subject to the
18-month timeline established in the intent language of SB 960.
Table 4 summarizes the commission’s reasons for the delays it
experienced in resolving these proceedings.
TABLE 4
Various Reasons Contributed to Delays in Resolving Formal Proceedings
Open Closed
Reasons for Delay Proceedings Proceedings Totals
A commissioner or management delayed the proceeding for various reasons. 4 4 8
Resolution of the proceeding depended on other commission decisions or investigations. 3 3 6
Proceeding was resolved promptly but was reopened in the tracking system and shown
as active to resolve a related issue or to resolve a past issue. 0 5 5
The proceeding was directly related to the energy crisis. 4 1 5
The commission kept the proceeding open to resolve numerous related issues or to
manage multiple phases. 4 0 4
Proceeding received a lower priority in response to the energy crisis or when compared
to other proceedings assigned to an administrative law judge. 2 2 4
Resolution of the proceeding depended on a California Environmental Quality Act review. 1 2 3
The commission, generally at a party’s request, chose not to resolve the proceeding
while the utility or other parties attempted to act on or settle the matter themselves. 2 1 3
Proceeding required additional evidence or other documentation from the parties to
the proceeding. 2 1 3
Several proceedings consolidated under one delayed the original proceeding. 0 1 1
The commission was required to reassign staff to the proceeding, the parties delayed
hearings, and the final decision was appealed. 1 0 1
Proceeding was resolved on time; however, the commission’s tracking system incorrectly
identified it as active rather than closed. 1 0 1
The proceeding was complex and highly contentious, requiring many public
participation hearings and workshops. 1 0 1
Totals 25 20 45
A Commissioner or Management Delayed the Proceeding for
Various Reasons
For eight proceedings, either management staff or the
commissioners themselves delayed proceedings for various
reasons, as described in the text box on the following page. For
example, according to the assigned ALJ, the commission delayed
one proceeding because of a change in commissioners. The ALJ
responsible for drafting the decision had prepared one that the
originally assigned commissioner approved, but because a lack
2200 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2211
of staff prevented the preparation of required
supplementary information, the proposed decision
A commissioner or commission manage-
ment delayed eight proceedings for the was never submitted to the full commission for
following reasons:
its review and approval. According to the ALJ, the
• Pending regulatory changes in the tele- newly assigned commissioner required additional
communications industry may affect the time to become familiar with the issues related to this
fi nal decision of the proceeding.
proceeding and to review the previously prepared
• A new commissioner was assigned to
decision. Ultimately, the new commissioner elected
the proceeding.
to revise the decision before submitting it to the full
• Management instructed the administrative
commission for approval. The combination of all
law judge (ALJ) to take no action on the
proceeding while the commission developed these circumstances resulted in a delay of several
strategies regarding the PG&E bankruptcy.
months, causing the commission to resolve the
• The assigned commissioner worked on proceeding well past the 18-month guideline.
revisions to the decision with the ALJ.
• Resolving the proceeding was a low
priority on the commissioner’s agenda. Resolution of the Proceeding Depended on
• The assigned commissioner held the Other Commission Decisions or Investigations
decision to determine its impact on the
energy crisis. The commission delayed resolving another
• The assigned commissioner spent time six proceedings because they depended on
negotiating with the parties in an attempt other commission decisions or investigations.
to resolve the issue.
For example, the commission initiated an
• The decision was complex and required the
adjudicatory proceeding in November 2001
assigned commissioner to meet with various
stakeholders before issuing a decision. that, according to the assigned ALJ, raised
identical issues to those of an earlier proceeding
the commission was already examining. The
assigned ALJ noted that the parties to the
November adjudicatory proceeding also participated in a
settlement involving the earlier proceeding that would probably
resolve the November proceeding but kept the adjudicatory
proceeding open until the commission acted on the settlement
of the earlier proceeding. Ultimately, the commission and the
parties to the fi rst proceeding reached a settlement that rendered
the later adjudicatory proceeding moot. However, when the
commission fi nally issued its decision to dismiss the November
proceeding, the 18-month guideline had already passed.
The Commission Closed Some Proceedings Promptly That It
Later Reopened
The commission resolved fi ve proceedings within the statutory
deadline or guideline, but because its tracking system does
not appropriately refl ect the resolution of proceedings that
are reopened, these proceedings appeared to have been
delayed. The commission’s system tracks numerous pieces of
information about each proceeding, including the title and
2222 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2233
type of proceeding, when it was opened and closed, and when
it was reopened. However, when the commission reopens a
proceeding, such as when it considers requests for a rehearing,
and then closes the proceeding again, the later closing date
replaces the initial one. Because only the later closing date is
used in measuring how long the commission took to resolve the
proceeding, the commission appears to have required more time
than it actually did. For example, it initiated one proceeding
in August 2000 and initially closed it in August 2001, within
the 12-month deadline. However, it reopened this proceeding
to process a request to award compensation to a party that
assisted the commission in resolving the case and reclosed the
proceeding in May 2002. The tracking system only reflected
the reclose date, making it appear as if the proceeding had
exceeded the deadline when it had not. Because the system fails to
accurately track all of the relevant closing dates, the commission
cannot rely on its tracking system alone to determine whether it
promptly resolves proceedings. When we became aware that the
closing dates in the tracking system were not always accurate, we
reviewed all 70 of the proceedings that had reopen dates and found
that the commission resolved 43 within the original deadlines.
Delays in the Proceeding Were Directly Related to the
Energy Crisis
Five of the delayed proceedings we reviewed related to the
energy crisis. For example, the commission initiated one of
the proceedings to determine the impact of wholesale price
spikes on retail electric rates in August 2000. Although this
proceeding remained open as of June 30, 2003, 17 months
beyond the 18-month guideline, the assigned ALJ explained that
the commission did so to allow the investigation to continue.
As of September 2003, the commission had issued four decisions
related to this one proceeding.
According to the chief ALJ, because of the energy crisis the
According to the chief ALJ, commission shifted its priorities to address these complex
because of the energy crisis issues. It initiated several proceedings to implement legislation,
the commission shifted its consider the underlying causes and problems associated with the
priorities to address these energy crisis, and establish programs and rate-making tools to
complex issues, initiating address the energy crisis. In fact, according to a list subsequently
a total of 20 proceedings provided to us by the chief ALJ, the commission initiated a total
that directly related to of 20 proceedings between January 1, 2000, and June 30, 2003,
the crisis. that directly related to the energy crisis.
2222 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2233
The Commission Held Proceedings Open to Resolve Related
Issues or Manage Multiple Phases of the Proceeding
The commission held four nonadjudicatory proceedings open to
manage multiple phases or to resolve related issues. For example,
the assigned ALJ stated that the commission decided to manage
a proceeding in our sample in two phases. It resolved the fi rst
phase of a rate-setting proceeding through a decision reached
within its 18-month guideline; however, it was still considering
the second phase of the proceeding as of October 14, 2003,
nearly 10 months beyond the guideline for resolution. The
commission also issued at least one decision within 18 months
for one of the remaining three proceedings.
According to the chief ALJ, the commission considers several
factors when deciding to keep a proceeding open rather than
closing it and opening a new one to resolve the issue. The chief
ALJ explained that the commission reviews the proceeding to
determine whether substantially the same parties will continue
to be affected and will continue to participate, whether the
evidence taken earlier will continue to be referred to, and
whether successive decisions will all contribute to completing a
single project. The chief ALJ also stated that some proceedings
either have so many substantive issues that many
decisions are required, or issues may be added as
the case progresses and the commission keeps the
Types of Draft Decisions
proceeding open.
Before the commission approves a fi nal
decision, it will issue a draft decision to the The remaining 17 proceedings included in our
involved parties, who then have 30 days
sample were delayed for the variety of reasons
to review it. In proceedings with hearings,
the commission issues two types of draft listed in Table 4 on page 21.
decisions, each guided by its own set of rules:
Presiding Offi cer’s Decision—the commission
issues this type of decision in adjudicatory
THREE MAIN FACTORS CONTRIBUTED TO
proceedings only. State law requires that
it issue the decision not later than 60 days DELAYS IN MEETING DEADLINES WITHIN
after submission. Generally, the decision
THE 12- AND 18-MONTH TIME FRAMES
becomes fi nal within 30 days of issuance
unless an involved party fi les an appeal or the
commission requests a review. As described in the Introduction, state law added
three deadlines within the 12- and 18-month time
Proposed Decision—the commission issues
frames that direct the commission to issue draft
this type of decision in both rate-setting and
quasi-legislative hearings. State law requires decisions within the deadlines identifi ed in the
that the commission issue the decision not
textbox. Our review of 19 draft decisions and four
later than 90 days after submission. The
commission’s fi nal decision will be issued fi nal decisions that did not meet these deadlines
not later than 60 days after the issuance of identifi ed three main factors that delayed them.
the original one. This deadline is extended
to 90 days if the commission proposes an
alternate decision.
2244 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2255
According to the commission, it generally did not meet the
60-day deadline for final decisions because commissioners
needed additional time to review and research complicated issues.
Further, the commission indicated that the ALJs often did not
issue draft decisions within the 60- or 90-day deadline because of
a combination of the ALJ’s workload and the impact of the energy
crisis. The ALJ’s heavy workload may indicate the commission’s
need for additional staff; however, as we discuss further in
Chapter 3, we cannot determine whether staff levels are sufficient
because the commission lacks an adequate workload tracking
system. Finally, although the commission reports to the Legislature
on whether it is meeting the deadline for issuing final decisions, it
neither tracks nor reports whether it is meeting the deadlines for
submitting draft decisions.
Workload Issues and the Energy Crisis Generally Contributed
to Delays in Issuing Draft Decisions
State law requires that the assigned commissioner or the ALJ
(presiding officer) in an adjudicatory proceeding, most often an
ALJ, file a presiding officer’s decision within 60 days of the date
the commission deems the proceeding submitted for decision.
The commission considers a proceeding submitted for decision
once the parties have filed pleadings and briefs, and taken the
evidence and comments upon which the commission will
base its decision. According to its chief ALJ, the commission
interprets this deadline to apply to only those proceedings with
evidentiary hearings. Consequently, as we discussed earlier, the
statutory requirement applied to only 39 of the 279 adjudicatory
proceedings initiated between January 1, 2000, and June 30, 2003.
In 23, or 59 percent of Although the commission neither reports to the Legislature
adjudicatory proceedings whether it is meeting this deadline nor comprehensively tracks
with evidentiary hearings, the submission dates, we were able to obtain submission dates
the presiding officer for the 39 proceedings. In 23, or 59 percent of these proceedings,
issued the decision within the presiding officer issued the decision within the 60-day
the 60-day deadline. deadline. Of the 16 remaining proceedings, the presiding officer
issued seven decisions within 30 days of the deadline and nine
others more than 30 days late. We examined these last nine
proceedings to determine the factors that contributed to their
delay, which we have categorized in Table 5 on the following page.
2244 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2255
TABLE 5
The Workload of the Administrative Law Judges and
the Impact of the Energy Crisis Contributed to the
Majority of Delays in Filing Draft Decisions
Reasons for Delay* Proceedings†
Administrative law judges’ (ALJ) workload 4
Proceeding had a low priority in comparison to energy crisis
related proceedings 4
Complex proceeding required extensive review by the ALJ 3
ALJ’s decision was dependent on federal ruling 1
*We reviewed draft decisions that were issued more than 30 days beyond the 60-day deadline.
† Although we selected nine proceedings for our review, the ALJ cited two reasons for the
delay related to three of them.
Although the commission substantially exceeded the 60-day
deadline for these nine proceedings, it did not surpass the
12-month deadline for final resolution of one of them but did
so on the other eight. The chief ALJ believes that exceeding
the 12-month deadline is allowable in these cases because the
commission issued an order extending the deadline, as provided
in state law, for each of the eight proceedings when it became
aware that it would be unable to resolve them within 12 months.
As shown in Table 5, the ALJs cited their heavy workload; the
need to work on other, higher priority proceedings involving
the energy crisis; complexity; and dependency on federal rulings
as the reasons they did not meet the 60-day deadline for filing
draft decisions. In fact, for three of these proceedings, the ALJs
cited more than one reason as contributing to the delays,
including heavy workloads. Although the ALJs’ heavy workload
may indicate the commission’s need for additional staff, we
could not determine whether its staffing levels are sufficient
because it lacks an adequate workload tracking system.
According to the assigned ALJs, the commission’s priority for
handling energy crisis proceedings contributed to delays in four
proceedings. For one proceeding submitted in August 2000, the
assigned ALJ did not issue a draft decision until November 2002,
more than 800 days after submission. According to the assigned
ALJ, this proceeding, as well as several others, was placed on
hold to work on a number of energy crisis proceedings.
2266 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2277
For three of the nine proceedings selected, the assigned ALJs
explained that the complexity of the issues further delayed their
drafting of a decision. For instance, the assigned ALJ in one
proceeding issued the draft decision 96 days after submission
because the ALJ was waiting for technical assistance from the
commission’s telecommunications division. The ALJ obtained
the information necessary to draft the decision 43 days after
submission and issued the decision 53 days later.
State law also requires that the assigned commissioner or ALJ
in rate-setting and quasi-legislative proceedings issue a draft
decision within 90 days of the date the commission deems
the proceeding submitted for decision. The commission
considers only rate-setting and quasi-legislative proceedings
with evidentiary hearings to be subject to this deadline. Thus,
the statutory requirement applied to only 105 of the 1,323
rate-setting and quasi-legislative proceedings initiated between
January 1, 2000, and June 30, 2003. Although the commission
does not report to the Legislature on whether it meets this
deadline, it was able to provide us with information pertaining
to submission dates for the 96 draft decisions related to these
105 proceedings. The proceedings only required 96 draft
decisions because the commission combined several under
one decision. The commission did not meet the 90-day
deadline for 37 of the 96 draft decisions. Of these, the
commission issued 27 decisions within 180 days of their
submission, and 10 took even longer. We reviewed the
10 decisions that took the longest to determine the causes of
their delay, which we have categorized in Table 6.
TABLE 6
The Administrative Law Judges Cited Workload as
Contributing to Delays in Several Draft Decisions
Reasons for Delay* Proceedings†
Administrative law judges’ (ALJ) workload 5
Complex issue required extensive review by the assigned ALJ 2
Proceeding was held by the commissioner for various reasons 3
Replacement of originally assigned commissioner or ALJ 3
The energy crisis and PG&E bankruptcy 3
*We reviewed draft decisions that were issued more than 90 days beyond the 90-day deadline.
† The ALJs cited two or more reasons for the delay of some proceedings.
2266 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2277
Although the commission more than doubled the 90-day
timeline for issuing the draft decisions for these 10 proceedings,
it still resolved one within the overall 18-month guideline.
As footnoted in Table 6, the ALJs cited more than one reason as
contributing to delays for some of the proceedings. They again
cited workload as a reason for delays in the majority of the draft
decisions and also explained that the energy crisis and the
PG&E bankruptcy prolonged three more. The assigned ALJ in
a PG&E rate increase proceeding did not issue the draft decision
until 765 days after submission because of PG&E’s April 2001
bankruptcy filing. The commission could not rule on the rate
increase while the bankruptcy case was pending, and realizing
the bankruptcy case would continue for some time, the ALJ
issued a draft decision dismissing the original proceeding in
December 2002.
The commission also noted that the reassignment of two
commissioners and one ALJ delayed three draft decisions.
The commissioners who were originally assigned to two
proceedings left the commission at the end of their respective
terms without completing the reviews. According to the ALJs
involved, they could not issue their draft decisions until the
newly appointed commissioners had reviewed all the relevant
documents. For the remaining proceeding, the commission
temporarily promoted the originally assigned ALJ to interim
chief ALJ, a position that required her to dedicate a significant
part of her time to managerial matters. The ALJ assigned to take
over the proceeding explained that she did not issue the draft
decision by the deadline because she had to become familiar
with hundreds of pages of testimony and legal briefs.
The Commission Did Not Report Certain Proceedings
Although the commission tracks and reports to the Legislature
whether it has met certain deadlines established in law, it does
Although the commission not report whether it is meeting the 60- and 90-day deadlines
tracks and reports to the previously discussed. Moreover, it does not adequately track
Legislature whether it the submission date that would allow it to do so. Although
has met certain deadlines commission staff provided us with submission dates for
established in law, it rate-setting and quasi-legislative proceedings, two of the
does not report whether 12 submission dates we reviewed for accuracy were erroneous. In
it is meeting the 60- and addition, the commission initially was unable to provide us with
90-day deadlines for submission dates for adjudicatory proceedings. It eventually
issuing draft decisions. was able to provide submission dates in October 2003, after
we had completed our review. According to the chief ALJ, the
2288 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2299
commission based its decision to report only certain deadlines
to the Legislature on its belief that the Legislature is most
concerned with the portion of these proceedings involving
commissioners’ actions; therefore, it tracks and reports whether
the commissioners have met the 60-day deadline to approve final
decisions, which we discuss in the next section. However, because
ALJs are most often responsible for meeting the 60- and 90-day
deadlines to prepare draft decisions, the commission’s decision
not to report compliance with these deadlines to the Legislature
overlooks the portion of the proceedings subject to these deadlines.
Therefore, because state law requires the commission to issue draft
decisions within either 60 or 90 days of submission, we believe it
is important to accurately track all submission dates in order to
monitor compliance with these requirements.
The Commissioners Delayed Final Decisions to Conduct
Additional Analysis and Revise Draft Decisions
We identified 87 final decisions related to proceedings initiated
between January 1, 2000, and June 30, 2003, that required a
commissioner’s action and were subject to either the 60- or
90-day deadline. The commission failed to meet these deadlines
for 16 (18 percent) of the 87 final decisions. It exceeded the
deadlines by 30 days or less for 12 decisions and by more than
30 days for four, the longest exceeding the deadline by 117 days.
We examined the four decisions with the longest delays to
determine the causes, which we have categorized in Table 7. The
commission also exceeded the 18-month guideline for two of
these four proceedings.
TABLE 7
The Commission Delayed Approval of Final Decisions in
Rate-Setting and Quasi-Legislative Proceedings for
Five Reasons
Reasons for Delay* Proceedings†
Assigned commissioner modified proposed decision 2
Commissioner held decision to conduct an additional analysis 2
Commissioner issued an alternate decision 1
Commissioner’s decision was dependent on a federal ruling 1
Commissioner deemed proceeding as low priority 1
*We reviewed final decisions that were issued more than 30 days beyond the deadline.
† Assigned commissioner cited more than one reason for delay.
2288 California State Auditor Report 2003-103 California State Auditor Report 2003-103 2299
Among the reasons commissioners gave for delaying their final
decisions in three of the four proceedings was the necessity of
either conducting additional analysis or drafting an alternate
decision. For example, the commissioners did not issue a
final decision in one proceeding until 94 days after the ALJ
issued the draft decision. This occurred because a commissioner
who was not assigned to the proceeding held the draft decision
for 50 days to conduct an additional analysis to determine whether
the decision would conflict with a pending decision and
assess whether the decision would create perverse incentives
within the gas market, according to the commissioner’s chief
of staff. Another proceeding did not meet the 60-day deadline
because the assigned commissioner was waiting for a Federal
Communications Commission ruling that affected the outcome
of this proceeding.
THE COMMISSION RECENTLY DEVELOPED A NEW
PROCESS FOR PRIORITIZING FORMAL PROCEEDINGS
Between January 2000 and January 2003, the commission
did not formalize and provide to the public or the Legislature
its criteria or the procedures it used to prioritize its formal
proceedings. Beginning in February 2003, the commission
established a more defined process for doing so. However,
because it has yet to develop a comprehensive workload tracking
system that links the administrative law judge division’s
workload to all other divisions, which we discuss in more detail
in Chapter 3, the commission cannot determine whether its
staffing levels are sufficient to manage the formal proceedings as
it has prioritized them.
More specifically, although state law requires that the commission
develop, publish, and annually update a work plan access
guide (work plan), it did not prepare the work plan for 2000
Although state law through 2002. Among other things, state law requires the
requires that the commission to include within the work plan a description of
commission develop, the scheduled rate-making proceedings and other decisions it
publish, and annually may consider during the calendar year, information on how the
update a work plan, it did public and ratepayers can gain access to the commission’s rate-
not prepare the work plan making process, and information regarding the specific matters
for 2000 through 2002. to be decided. Ultimately, the commission did prepare a work
plan for 2003 that included its criteria for determining regulatory
priorities and a list of the 2003 major proceedings. The commission
states in its 2003 work plan that it allocates its staff resources for
decision making according to a stated set of priorities established
3300 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3311
by its president. When establishing its priorities and
objectives, it considers the information shown in the
The Commission’s February 2003 Criteria
for Determining Regulatory Priorities textbox in no particular order.
Law—the commission sets priorities to assure Although the commission did not prepare a work
compliance with and enforcement of the law;
plan for the three years preceding 2003, in response
where needed, the commission may advocate
changes in the law. to the energy crisis it did prepare three internal
documents, the fi rst dated October 31, 2000, the
Interests of the public—consistent with
statute, the commission puts the interest of second covering the period of March through
the public at large and the State ahead of
August 2001, and the third for September 2001
any single entity or constituency.
through February 2002. The last two briefl y
Dollars at stake—the commission sets described the commission’s priorities between
priorities considering the amount of money
March 2001 and February 2002 as follows:
at stake and the impact on consumers and
the State’s economy.
• Resolve the energy crisis.
Vulnerability of target groups—the
commission places a higher priority on
promoting the interests of the public, the • Address critical telecommunications matters.
State, and consumers than on arbitrating
disputes between regulated service providers;
it addresses issues affecting captive consumers • Enhance consumer protection, especially for
ahead of consumers of services available from those industries where competition, in varying
a variety of providers, and; considers the
degrees, has been introduced.
needs of consumers who are most vulnerable
ahead of those who are more sophisticated.
Additionally, these internal documents contained
Number affected—the commission
sets priorities considering the number of tables that designated proceedings as low, moderate,
consumers and businesses affected. or high priority. Although the commission prepared
Importance of the service, product, or these documents, it apparently did not share them
policy—in setting priorities, the commission with others outside of the commission.
considers the importance of the service,
product, or policy to the welfare of the State
and its consumers; generally, the commission Beginning in February 2003, using the criteria
addresses issues related to essential services
established in the work plan, the commission began
ahead of nonessential services.
to internally prioritize specifi c proceedings by
Degree of monopoly characteristics designating them as A-, B-, or C-level priority and
present—the commission addresses problems
preparing a listing of the proceedings according to
with industries and services with monopoly
characteristics ahead of those that have some their priority ranking. According to the chief ALJ,
degree of competitive characteristic.
the commission considers many of the proceedings
“Bang for the buck”—because it does not to be routine and, therefore, does not include
have the resources to address every issue, the
them on this list. In constructing the list of priority
commission must set priorities by evaluating
the relative costs and benefi ts of acting or proceedings, the administrative law judge division
not acting. fi rst consults with the commission’s division
managers; the list is reviewed by the commissioners,
and then is distributed to all divisions within the
commission. We selected a sample of proceedings
it included on its priority list as well as a sample of the routine
proceedings to determine whether the commission was
prioritizing according to its stated criteria in the work plan.
Our testing found that the commission generally prioritized its
proceedings as outlined in the work plan.
3300 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3311
In addition, the chief ALJ for the division explained that, to
ensure staff are working on higher priority items, proceedings
are tracked on a work tracking system. Further, according to
the chief ALJ, the commission’s executive director meets on
a regular basis with the industry division managers and they
each prepare an internal “roadmap” to track the commission’s
proceedings that are relevant to them and their respective roles
in those priority proceedings. However, because it has yet to
develop a comprehensive workload tracking system that links
the ALJs’ workload to all other divisions, the commission cannot
determine whether its staffing levels are sufficient to manage the
formal proceedings as it has prioritized them.
RECOMMENDATIONS
To ensure that it accurately reports the closing date of a
proceeding, the commission should modify its tracking system
to retain the original closing date as well as record its subsequent
closing date for those proceedings it reopens.
To ensure that it is complying with the 60- and 90-day
deadlines between submission date and filing a draft decision,
the commission should better track its submission dates and
monitor whether it is meeting its deadlines.
To ensure that it discloses to the public and the Legislature
its process for prioritizing its proceedings, the commission
should continue to annually prepare and publicize a work plan
that includes its criteria for prioritizing formal proceedings, as
required by law. n
3322 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3333
CHAPTER 2
The Commission Processed Most of
Its Advice Letters Within Its Internal
Goal of 90 Days
CHAPTER SUMMARY
Unlike formal proceedings, state law and regulations
do not establish any deadlines for the California
Public Utilities Commission (commission) to review
and approve advice letters. However, the three divisions that
process advice letters—telecommunications, energy, and
water—indicated that they have an internal goal of 90 days after
the utility files the letter to process and close it. Considering
the divisions’ internal goal, the commission closed more than
13,500 advice letters submitted between January 1, 2000, and
June 30, 2003, or 88 percent within the 90-day time frame.
Our review of a sample of 90 advice letters that took longer
than 90 days to process found that two factors contributed
to delays: One was that some had a lower workload priority
and the other was that some required formal resolution or
investigation. Although two of the divisions promptly processed
27 of these advice letters, staff either delayed closing or failed
to close them in the proposal and advice letter (PAL) tracking
system. This represents 30 percent of the 90 advice letters we
selected for testing. We believe that this should be of concern to
the commission because it recently began using data recorded
in the PAL tracking system to report on the status of advice
letters. Furthermore, because its records were in such disarray,
the telecommunications division was unable to provide us any
explanations for the delays in processing 16 of its advice letters.
STATE LAW AND REGULATIONS DO NOT ESTABLISH
DEADLINES FOR THE COMMISSION TO REVIEW OR
APPROVE ADVICE LETTERS
Utility companies submitted to the commission for its review and
approval more than 16,100 advice letters between January 1, 2000,
and June 30, 2003. According to the commission, many of
these letters deal with minor and noncontroversial issues; thus,
commission staff could further process them without the need
for hearings. Other advice letters are about more complex issues
3322 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3333
requiring staff to spend a greater amount of time processing them.
Table 8 summarizes the amount of time that elapsed between the
receipt of the advice letters and either the date the commission
ultimately approved and closed them in its PAL tracking system or
June 30, 2003, if the advice letter was still open.
TABLE 8
The Commission Resolved 88 Percent of Advice Letters
Within Its Internal Goal of 90 Days
91 Days
Divisions 0-40 Days* 41-90 Days† or More Totals
Open advice letters
Telecommunications 229 95 151 475
Energy 57 33 86 176
Water 23 9 23 55
Subtotals 309 137 260 706
Closed advice letters
Telecommunications 8,626 3,078 1,202 12,906
Energy 735 522 573 1,830
Water 439 156 91 686
Subtotals 9,800 3,756 1,866 15,422
Grand Totals 10,109 3,893 2,126 16,128
Source: The commission’s proposal and advice letter tracking system for advice letters
submitted between January 1, 2000, and June 30, 2003.
*40-day general order timeline as identified in General Order 96-A.
† 90-day internal goal timeline.
As discussed in the Introduction, state law and regulations
do not establish any deadlines for the commission to review
and approve advice letters. However, the commission has
adopted General Order 96-A, which provides that advice letters
become effective 40 days after filing. According to commission
staff, the order envisions the commission typically needing
at least that amount of time to approve advice letters so
that they become effective. For those advice letters that the
3344 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3355
commission anticipates needing more than 40 days to review
and approve, the commission can allow for a later effective
date. As Table 8 shows, according to the PAL tracking system,
the commission resolved 9,800 advice letters within 40 days,
61 percent of those it received between January 1, 2000, and
June 30, 2003. Although General Order 96-A establishes the
40-day time frame, the three divisions that process advice
The commission closed letters—telecommunications, energy, and water—indicated that
more than 13,500 advice they have an internal goal of 90 days to resolve and close them.
letters, or 88 percent, The energy division indicated that the processing time has
within the divisions’ lengthened as the result of the increase in quantity received and
90-day time frame. the complexity of the issues raised. The commission closed more
than 13,500 advice letters, or 88 percent, within the divisions’
90-day time frame. For the remainder, the commission took
from 91 days to more than three years. We selected a sample
of advice letters from those that required more than 90 days to
resolve and reviewed them to identify the reasons for the delays.
TWO FACTORS CONTRIBUTED TO DELAYS IN
APPROVING ADVICE LETTERS
Our review revealed that two factors contributed to delays in the
commission’s review and approval of more than one-third of our
sample of 90 advice letters. First, the commission considered the
subject of 16 advice letters to be of low priority; thus, staff spent
time on higher priority tasks rather than promptly reviewing
and approving them. Second, 17 advice letters required a formal
resolution or investigation by the commission, which took
additional time to complete. In addition, although two of the
divisions processed 27 of the advice letters sampled within
90 days, staff either delayed closing or failed to close them in
the PAL tracking system. Furthermore, the telecommunications
division could not provide us any explanation for what caused
the delays in processing 16 of its advice letters, and the water
division could not explain another. Table 9 on the following
page provides a breakdown of the advice letters by division and
the factors contributing to their delay.
3344 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3355
TABLE 9
Various Factors Contributed to Delays in Promptly Resolving Advice Letters
Number of Advice Letters by Division
Total Number of
Reasons for the Delay Telecommunications Energy Water Advice Letters
Division processed the advice letter within 90 days but
either delayed or failed to close it in the tracking system. 17 10 0 27
Commission staff were unable to recall circumstances
surrounding the advice letter. 16 0 1 17
The advice letter required a formal resolution or
investigation by the commission. 9 4 4 17
Division considered the advice letter a low priority
item (workload). 3 12 1 16
Utility company was not responsive to the commission’s
requests for information or clarification. 3 3 1 7
The advice letter dealt with a complex issue
that required numerous document requests and
correspondence with the utility. 3 0 1 4
Staff had the information needed to promptly process
the advice letter but failed to do so. 3 0 0 3
Division could not process the advice letter until
the commission issued a final decision in a related
formal proceeding. 0 2 0 2
Totals 54 31 8 93*
*Two energy division advice letters and one water division advice letter were delayed by more than one factor.
The three divisions indicated that 16 advice letters had a lower
priority. For example, in four cases the utility was notifying
the commission, as required, of the creation of a new affiliate.
According to a project manager with the energy division, this
type of advice letter is informational and requires little action by
the commission; therefore, these letters are designated a lower
priority than other tasks assigned to the division’s analysts. Our
comparison showed that the divisions appear to follow their
stated priority criteria.
Although the telecommunications and energy divisions frequently
cited a staffing shortage as a reason they believe contributes to
their need to prioritize advice letters, we were unable to determine
whether the divisions’ claims have merit because the commission
lacks a workload tracking system. We discuss the tracking of the
commission’s workload more fully in Chapter 3.
3366 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3377
Table 9 also shows that the three divisions indicated 17 advice
letters required a formal resolution or investigation by the
commission necessitating additional time to either develop
the resolution or perform the investigation. For example, the
telecommunications division has not resolved and closed
six of the nine advice letters in this category because
they are the subject of an ongoing formal investigation
that the commission’s consumer protection and safety
division is conducting. According to a program manager, the
telecommunications division is holding these advice letters open
until the investigation is complete. In another example, the
energy division indicated that a utility used an advice letter to
request the commission’s approval to implement a surcharge for
direct access customers. The subject of this advice letter required
the energy division to spend additional time to review its details
and draft a resolution for the commission’s approval.
Also shown in Table 9, staff apparently reviewed and approved
17 of the telecommunications division’s and 10 of the energy
division’s advice letters promptly. However, the staff either
Although staff apparently delayed closing or failed to close them in the PAL tracking
promptly reviewed and system. This represents 30 percent of the 90 advice letters we
approved 30 percent selected for testing. Staff in the telecommunications division
of the 90 advice letters indicated that they generally did not close the advice letters in
we reviewed, they either the tracking system because of a processing error or oversight.
delayed closing or failed In addition, a program and project supervisor with the energy
to close them in the division typically provided the same explanation, except in
proposal and advice letter three instances where energy division staff asserted they had
tracking system. more pressing priorities and, as a result, failed to close the letters
in the tracking system. We believe that the high proportion of
advice letters in our sample that remain open according to the
dates in the PAL tracking system when they are actually closed
should be of concern to the commission because it recently
began using data recorded in the PAL tracking system to report
to the commissioners on the status of advice letters. This type
of erroneous data generated by the tracking system could be
misleading to the commission and to those the commission
reports to using this information.
To help expedite matters before the commission, in April 2003,
its executive director prepared for the first time a report that
describes the status of advice letters, which he shared with
the commissioners during a public meeting. According to the
executive director, he will prepare this report and provide it to
the commissioners twice a year. The commission included in the
April 2003 status report the number of advice letters resolved
3366 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3377
and closed in 2002 and the number of advice letters pending in
March 2003 for each division. According to commission staff, they
obtained this information directly from the PAL tracking system.
Based on the results of our sample, if we assume that 30 percent
of all the advice letters included in the PAL tracking system are
incorrectly coded as pending rather than resolved and closed, we
question whether the information included in the status report
is a reliable source on which to base decisions. We believe that it
is important for the commission to review all the advice letters
currently included in its PAL tracking system and make corrections
where appropriate to ensure that the status report it is sharing with
the commissioners in a public meeting is accurate.
The telecommunications division could not recall or was unable
to provide reasons for the delays in processing 16 of its advice
letters, and the water division failed to provide a reason for
the delay in processing one. As we will discuss in a subsequent
section of this chapter, the telecommunications division does
not adequately maintain and track its advice letters.
TWO DIVISIONS USE A SIMILAR SET OF CRITERIA TO
PRIORITIZE THEIR ADVICE LETTERS, WHILE THE THIRD
DIVISION PRIORITIZES ON A CASE-BY-CASE BASIS
Because of the high Although the telecommunications and energy divisions provided us
volume of advice letters with descriptions of the criteria they use to prioritize advice letters,
the telecommunications they had not documented these criteria as part of their policies
and energy divisions and procedures in advance of our request. Moreover, the advice
receive, they routinely letter files do not contain any indication of how either of the two
prioritize them to divisions classified the letters. Consequently, we could not confirm
promptly resolve those whether the divisions consistently applied their criteria, although
that are of the highest our review of the 16 advice letters the divisions identified as low
priority first. priority appeared to be consistent with the criteria described to us.
The energy division received more than 2,000 and the
telecommunications division received more than 13,300 advice
letters between January 1, 2000, and June 30, 2003. According to
the divisions, it is because of this high volume that they routinely
prioritize advice letters to promptly resolve those that are of the
highest priority first. The two divisions’ criteria for prioritizing
advice letters are somewhat similar. Both indicated that they give a
higher priority to letters that will have a significant impact on rates,
customers, and the utility markets. The two divisions also stated
that they give a higher priority to those advice letters that utilities
file to comply with a commission decision. In addition, the director
for the telecommunications division indicated that the division
3388 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3399
also considers whether a letter involves issues so controversial as
to elicit protests. Furthermore, according to its director, staff of
the energy division also consider the age of an advice letter and
attempt to address the oldest letters first among those that are
pending, after attending to any with a higher priority.
Unlike the telecommunications and energy divisions, the water
division has received substantially fewer advice letters—741
during the time period reviewed. A program manager of the
water division indicated that consequently, the division has
been better able to promptly resolve and close advice letters and
therefore has less need to prioritize them. Instead, the water
division’s staff evaluates each letter on a case-by-case basis and
prioritizes those that need to be completed more quickly.
THE TELECOMMUNICATIONS DIVISION DOES NOT
ADEQUATELY MAINTAIN AND TRACK ITS ADVICE LETTERS
The telecommunications division (telecommunications) lacks
a filing system that allows it to store advice letters and the
supporting documentation for the letters in a central location.
Thus, telecommunications had difficulties locating advice
letter files and related supporting documents, which may have
contributed to its inability to provide reasons for delays in
resolving 16 advice letters as we described earlier in this chapter.
We requested that telecommunications provide us with the
files, including supporting documents, for 60 advice letters.
Telecommunications staff required several weeks to locate the
advice letter files we requested and were ultimately unable
to locate six of them. We observed that in many instances,
advice letters were located at an analyst’s desk or piled on tables
rather than in a central filing area. For some advice letters,
telecommunications had to request a copy from the utility
because it was unable to locate its own copy. For those advice
In many instances, advice letters staff did eventually locate, the files contained only limited
letters were located at an documentation to illustrate the reasons for their processing
analyst’s desk or piled on delays. Telecommunications staff conceded that maintaining and
tables rather than in a tracking advice letters has been and continues to be a problem.
central filing area.
In an attempt to address its filing problems, telecommunications
has initiated a pilot project that allows utilities to submit advice
letters and supporting documents in an electronic format. A
program manager indicated that telecommunications intends to
maintain electronic copies of the advice letter and supporting
3388 California State Auditor Report 2003-103 California State Auditor Report 2003-103 3399
documents, which he believes will facilitate their storage and
tracking. He also stated that the utilities participating in the
pilot project represent 46 percent of the advice letters submitted
and, ultimately, telecommunications intends to include all
utilities in its electronic filing process. Although this may
eventually prove successful, telecommunications still needs to
file and track the advice letters and supporting documents of
utilities that currently choose not to file electronically in such a
way that it is able to accurately and promptly retrieve them.
Finally, as part of its processing, telecommunications requires
utilities to submit a summary sheet with their advice letters.
Telecommunications uses this summary sheet to track the
advice letter’s progress by indicating the differing levels of
review and approval it has received and, ultimately, support staff
Telecommunications staff use the summary sheet to input and update the information
often could not locate the included in the PAL tracking system. However, staff often
advice letter summary sheet could not locate the relevant summary sheet or, when
used to indicate differing found, it was not fully completed. A program manager for
levels of review and telecommunications indicated that in the past, after resolving
approval or, when found, it and closing an advice letter, staff discarded the summary sheets,
was not fully completed. which apparently occurred for several of our sample items.
He stated that telecommunications recently discontinued this
practice and now maintains the summary sheet along with the
advice letter. The program manager also noted that although
telecommunications has implemented the electronic pilot
project, the utilities will still be required to submit the summary
sheet and telecommunications staff will still need to complete
it. Therefore, for purposes of oversight and internal and external
review, telecommunications still needs to ensure that its staff
complete and maintain the summary sheet.
RECOMMENDATIONS
To ensure that the information included in the PAL tracking
system is accurate for reporting to the commissioners in public
meetings on the timeliness of advice letters, the commission
should review all advice letters in the system and close those
where it is appropriate to do so.
As part of implementing its new electronic filing process,
the commission should ensure that the telecommunications
division creates an effective centralized filing system for those
advice letters and supporting documents not submitted in
electronic format.
4400 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4411
For purposes of oversight and external and internal review,
the commission should ensure that telecommunications staff
consistently complete and retain summary sheets to evidence
appropriate approval and review and that telecommunications
maintains the summary sheets in its advice letter files. n
4400 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4411
Blank page inserted for reproduction purposes only.
4422 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4433
CHAPTER 3
Although the Commission Cited
Workload and Inadequate Staffing as
Contributing to Delays, the Lack of
a Workload Tracking System Hinders
Its Ability to Justify Staffing Needs
CHAPTER SUMMARY
The Department of Finance (Finance), in various
reports and management letters it prepared between
February 1998 and February 2003, reported that the
California Public Utilities Commission (commission) lacked
a workload tracking system that would allow it to justify its
staffing needs. In response to a February 2003 management
letter, the commission began to revise its workload tracking
system to address Finance’s concerns; however, it does not
anticipate implementing key phases of the new system until the
end of 2003 or the beginning of 2004. Thus, the commission
was unable to provide us any staffing analyses that would allow
us to determine whether its staffing levels are adequate to
promptly process its formal proceedings and advice letters.
THE COMMISSION LACKS A WORKLOAD TRACKING
SYSTEM THAT WOULD ALLOW IT TO JUSTIFY ITS
STAFFING NEEDS
According to several reports prepared by Finance between
February 1998 and February 2003, the commission lacks an
adequate workload tracking system that would allow it to
provide quantifiable justification to support its requests for
staffing. Consequently, although the commission indicated
that understaffing is a limiting factor in promptly processing its
formal proceedings and advice letters, it was unable to provide
us with any staffing workload analyses to support this belief.
According to Finance, it first issued a report concerning a historical
review of the commission’s positions, expenditures, and funding
sources in February 1998 that found the commission used a
standard time reporting system to account for its employees’
time that was based on employee time sheets and was used
4422 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4433
to allocate personnel costs to specific funds. However, Finance’s
report disclosed several weaknesses in the commission’s reporting
In various reports and system, including incorrectly charging programs and program
management letters funding sources and the system’s inability to track authorized
it prepared between positions. During a second review that resulted in a report issued
February 1998 and in November 2001, Finance ascertained that the commission
February 2003, Finance had abandoned its standard time reporting system subsequent
reported that the to Finance’s 1998 review and, at the direction of its president,
commission lacks a initiated a new time reporting system—the workload tracking
workload tracking system system—effective July 2000. However, in its 2001 report, Finance
that would allow it to noted that although the commission had taken significant steps to
justify staffing needs. address workload data problems by establishing and implementing
the new tracking system, limitations and weaknesses in available
data impeded its ability to determine current staffing and workload
levels. Thus, Finance made several recommendations to improve
the tracking system.
According to Finance, in March 2002 the commission requested
that it review and comment on the commission’s proposed
improvements to its tracking system, scheduled for implementation
during 2002. Finance reported that the proposed improvements
would not address the concerns it initially identified in its
2001 review. In fact, Finance stated that the proposed improvements
did not allow the system to track the relational data necessary
to develop workload standards and determine staffing needs.
According to Finance, the commission responded to its concerns in
a March 2002 memo, which indicated that the commission believed
the output from the then-current version of its workload tracking
system would enable it to develop staffing standards.
Ultimately, in accordance with an interagency agreement
between Finance and the commission, Finance again reviewed
the workload tracking system to determine whether it was
providing sufficient data to identify priorities and develop
workload standards and reported its results in early 2003. In its
management letter dated February 2003, Finance reiterated the
concerns identified in its previous reviews and, more specifically,
noted that the current form of the tracking system would not allow
for a determination of workload requirements or the development
of workload standards. Further, Finance noted that management
in some divisions had implemented certain improvements that
made the tracking system a somewhat productive management
tool for those divisions. However, Finance indicated that these
independent systems and ad hoc modifications would not
form an integrated system that could provide data useful on an
organization-wide or even a division-specific basis. It again made
4444 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4455
several recommendations, including developing a standardized
system that could be used throughout the commission. In response
to Finance’s February 2003 management letter, the commission’s
president acknowledged that it had serious work to do to make
its time reporting and the workload tracking system accurate and
useful commission-wide.
THE COMMISSION IS REVISING ITS WORKLOAD
TRACKING SYSTEM
According to the commission, it is in the process of modifying its
The commission does not current workload tracking system to address Finance’s concerns
anticipate implementing so that the “new” system will be a useful management and
key phases of its new reporting tool at both the commission and division level. The
workload tracking system program manager responsible for implementing the new tracking
until the end of 2003 or system indicated that the commission would not complete its
the beginning of 2004 and modification to allow a common reporting format until the end
the final version of the of 2003 or the beginning of 2004 and that the final version of
system will take longer. the system will take longer. Consequently, the commission was
unable to provide the analyses or documents we needed to assess
whether its staffing levels were adequate at the time we performed
our audit.
As of June 2003, the commission noted that five different
versions of the workload tracking system exist, and although it
is possible to produce limited division-specific reports, it is not
yet possible to generate reports on a commission-wide basis.
However, according to commission staff, the new tracking
system will be a unified version that allows work to be entered
consistently throughout the commission and also allows the
entire commission to use the system. Further, commission staff
indicated that it has discussed the proposed modifications with
Finance and believes it has addressed all of Finance’s concerns.
More specifically, the commission indicated that the new
tracking system will allow it to quantify the work it performs. As
a result, it believes that the system will provide information such
as how many hours staff spend on specific types of proceedings,
the average time it takes for staff to complete an advice letter,
and the type of work staff performs related to energy advice
letters, among other things. Ultimately, the program manager
believes that the new tracking system will allow the commission
to determine whether it needs to increase its staffing levels in
the various divisions based on workload data.
4444 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4455
RECOMMENDATION
The commission should continue to work with Finance on
improving its workload tracking system so that it can justify its
staffing needs.
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
Date: November 25, 2003
Staff: Doug Cordiner, Audit Principal
Denise L. Vose, CPA
Rafael Garcia
Anissa C. Nachman
Matt Taylor
4466 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4477
Agency’s comments provided as text only.
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102-3298
November 13, 2003
Ms. Elaine M. Howle*
State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Re: California Public Utilities Commission (CPUC): State Law and Regulations
Establish Firm Deadlines for Only a Small Number of Its Proceedings
Dear Ms. Howle:
Thank you for the opportunity to comment on your draft audit report. We found the State Auditor
study to be professional and accurate. We do not take exception to any of the numerical facts con-
tained in the report. Likewise, we accept the recommendations that the CPUC should:
1. Modify the Case Information System database so that it retains multiple closing dates
for complex proceedings. (Database programming cost issue)
2. Better track proceeding submission dates. (Database programming cost issue)
3. Continue to prepare an annual work plan that contains work priorities and criteria for
determining the priorities.
4. Review all open Advice Letters and close those that have been completed. (Staffing
resource issue.)
5. Create a more effective filing system for Telecommunication Division Advice Letters.
(Staffing resource issue.)
6. Make sure that the Telecommunications Division staff complete and retain advice letter
approval and review forms. (Staffing resource issue)
7. Improve our Work Tracking System.
* California State Auditor’s comments begin on page 51.
4466 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4477
Ms. Elaine M. Howle
November 13, 2003
Page 2
We will implement the recommendations as best as we are able with our existing resources.
However, three aspects of the report that deserve brief comment are: (1) Cost of implementing the
recommendations, (2) Failure to study staffing levels, and (3) Interpretation of Assembly Bill 1735.
Our comments on these subjects are attached.
Sincerely,
(Signed by: William Ahern)
William Ahern
Executive Director
Enclosure
4488 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4499
Cost of Implementing the Recommendations
The report finds a structural problem with the CPUC’s Case Information System (CIS-a very old
legacy database system) in that the system does not allow for the retention of multiple “close”
dates – the date on which a proceeding is closed. In addition, the audit report identified the difficulty
of determining “submission” dates for some complex proceedings. Likewise the report found that
some Advice Letters (PAL System) that were completed remained “open.” The report goes on to
recommend that these shortcomings be corrected.
What we find lacking in the report is the acknowledgment that the CPUC (like all state agencies) is
operating under very tight resource constraints. Likewise the report fails to contemplate the perhaps
1
significant cost of either enhancing or replacing the two existing database systems – CIS and PAL.
Failure to Study Staffing Levels
The State Auditor report details the efforts of the CPUC to work with the Department of Finance
to create a new Work Tracking System that would allow the Commission to quantitatively justify
staffing needs. The report finds that since the new system has not been implemented, it could not
pursue any analysis of CPUC staffing levels.
2
We are disappointed in the State Auditors decision in this regard. We had hoped that if it were not
possible for the State Auditor to perform quantitative analysis of the CPUC staffing levels, then the
State Auditor might have performed some qualitative analysis. The State Auditor could have inter-
viewed CPUC management to see what activities/projects the CPUC management believed should
be undertaken but are prevented by inadequate staffing levels. The report seems to endorse our
methodology of prioritizing our activities.
In addition, both the Telecommunication division and the Administrative Law Judge division attempted
to show that much of the problem of tracking and maintaining proper records (Recommendations # 2,4,
5, and 6 in our cover letter) was the result of inadequate support staff staffing levels.
Interpretation of AB 1735
3
Although the report does not indicate that our interpretation of AB 1735 is legally incorrect, it uses
language (for instance the wording of the title of the report) that implies that the commission should
interpret AB 1735 so that the 18 month deadlines are applicable not only to proceedings that go to
hearing but also, to proceedings that do not go to hearing.
4488 California State Auditor Report 2003-103 California State Auditor Report 2003-103 4499
This strong implication in the report caused us to reconsider our interpretation. Our reconsideration has
led us to believe that our legal interpretation is correct and that the deadlines imposed by AB 1735
apply only to proceedings that have had Evidentiary Hearings.
In addition, we reviewed our interpretation in terms of both Legislative intent as well as cost effective
administration. Our conclusion remains the same. One example of cost effective administration is
that, as the report points out, there are very few problems of timeliness with proceedings that do
not go to hearing. If we were to monitor, track and manage proceedings that do not have hear-
ings in the same manner as those that do, then there would be a substantial cost involved with
insignificant benefits.
However, as the report points out we have applied rigorous case management to cases that do
not go to hearing which means that we make every attempt to insure that all cases are processed
within the 18 month time period. Of course, we will continue this practice.
5500 California State Auditor Report 2003-103 California State Auditor Report 2003-103 5511
COMMENTS
California State Auditor’s Comments
on the Response From the California
Public Utilities Commission
To provide clarity and perspective, we are commenting on
the response by the California Public Utilities Commission
(commission) to our audit report. The numbers below
correspond to the numbers placed in the margins of the
commission’s response.
1
Based on discussions with our information technology staff, we
do not believe that the cost to modify the commission’s case
information system (CIS) to retain the original closing date
and subsequent closing date for reopened proceedings would
be significant. However, since the commission acknowledges
in its comments that it does not know whether the costs to
enhance or replace its CIS would be significant, it should first
determine what those costs are. If they are prohibitive, the
commission should manually track the original closing dates for
all proceedings it reopens.
Additionally, the commission is mischaracterizing our report
because we are not reporting any “structural problems” with
the commission’s proposal and advice letter (PAL) tracking system,
thus we did not recommend that the commission enhance
or replace the PAL tracking system. Instead, as we describe
on page 37, staff either delayed closing or failed to close
advice letters in the PAL tracking system and, consequently,
the tracking system contains incorrect data. Therefore, we
recommended that the commission review all advice letters in
the system and close those where it is appropriate to do so. This
does not entail enhancing or replacing the PAL tracking system.
2
We are confused by the commission’s concerns regarding our
inability to review its staffing levels because it lacked a workload
tracking system. Contrary to the commission’s response, we
met with the commission’s management staff from both its
telecommunications and administrative law judge divisions on
several occasions. During these meetings, management staff
from both divisions asserted that workload and inadequate
5500 California State Auditor Report 2003-103 California State Auditor Report 2003-103 5511
staffing contributed to delays. However, as we state on pages 36
and 43, while the commission’s management staff asserted
they were short of staff, they could not provide evidence to
support their claims.
3
We strongly disagree with the commission’s statement that
our report implies it should interpret Assembly Bill 1735
(AB 1735) so that the 18-month deadline is applicable to
proceedings that require hearings as well as those that do not.
Moreover, it is the commission that implies we are somehow
challenging its legal interpretation of the bill’s provisions.
Nothing could be further from the truth. In fact, on page 18,
our legal counsel advised that in view of its broad rule-making
authority, the commission’s interpretations of statutes and its
own rules are given great weight by the courts. Thus, we relied
on the commission’s interpretation of the relevant statutes
in determining whether the commission is complying with
statutory and regulatory deadlines. However, the fact remains
that the commission’s interpretation of AB 1735 is that it applies
to only those proceedings requiring evidentiary hearings and,
as such, if the new law had been in effect during the period we
reviewed for our audit, it would have applied to only 105 of the
1,323 rate-setting and quasi-legislative proceedings. Therefore,
we believe it is important to point out to the Legislature, as
stated on page 20, that if it intended all the types of proceedings
the commission initiates be subject to statutory deadlines, the
Legislature would need to revise the law to provide deadlines
for all proceedings, regardless of whether hearings are required.
We do not believe this implies in any way that the commission
should revise its interpretation of AB 1735.
5522 California State Auditor Report 2003-103 California State Auditor Report 2003-103 5533
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California State
Government Organization and Economy
Department of Finance
Attorney General
State Controller
State Treasurer
Legislative Analyst
Senate Office of Research
California Research Bureau
Capitol Press
5522 California State Auditor Report 2003-103 California State Auditor Report 2003-103 5533