CSA
Summary
Read the report at California State Auditor ↗
Grade Separation Program:
An Unchanged Budget and Project Allocation Levels Established
More Than 30 Years Ago May Discourage Local Agencies From
Taking Advantage of the Program
September 2007 Report 2007-106
C A L I F O R N I A
S T A T E A U D I T O R
The first five copies of each California State Auditor report are free. Additional copies are $3 each, payable by
check or money order. You can obtain reports by contacting the Bureau of State Audits at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
916.445.0255 or TTY 916.445.0033
OR
This report is also available on the World Wide Web http://www.bsa.ca.gov
The California State Auditor is pleased to announce the availability of an on-line subscription service. For
information on how to subscribe, please contact the Information Technology Unit at 916.445.0255, ext. 456,
or visit our Web site at www.bsa.ca.gov.
Alternate format reports available upon request.
Permission is granted to reproduce reports.
CALIFORNIA STATE AUDITOR
Elaine M. Howle
State Auditor
Doug Cordiner B u r e a u o f S t a t e A u d i t s
Chief Deputy
555 Capitol Mall, Suite 300 Sacramento, CA 95814 916.445.0255 916.327.0019 fax www.bsa.ca.gov
September 13, 2007 2007-106
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its
audit report concerning the funding and approval process required for grade separation projects
by state and local transportation agencies.
This report concludes that although the Public Utilities Commission’s (Commission) priority
list of grade separation projects for the last several years has contained more than 50 projects,
the California Department of Transportation has been unable to allocate all of the Grade
Separation Program funds because local agencies have often not taken the additional steps
necessary to apply for the funds once their projects are included on the Commission’s priority
list. Part of the reason for this failure to apply for funds is that the cost of grade separation
projects has increased more than tenfold over the past 30 years while the funds available from
the Grade Separation Program have remained unchanged. Specifically, the average cost of a
grade separation project has increased from $2.5 million in 1974 to a current average of just
more than $26 million. Local agencies say they are experiencing difficulties securing the funding
necessary to pay for their share of grade separation projects; thus, some are not nominating new
projects to be included on the Commission’s priority list and many are not applying for funds
for the projects already on the priority list.
A report prepared by the Commission in March 2007 showed that $165 million is needed to
provide funding for the same number of grade separation projects that $15 million provided
in 1974. Additional funding will be available for grade separation projects from a bond measure
approved by California voters in November 2006, which will provide a one-time amount of
$250 million to improve railroad crossing safety. The bond measure makes $150 million of these
funds available for allocation under the process established for the Grade Separation Program.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
California State Auditor Report 2007-106 vii
September 2007
Contents
Summary 1
Introduction 5
Audit Results
Local Agencies Believe Allocations Are Not Sufficient to Allow Them
to Take Advantage of the Grade Separation Program 13
The Final Costs of Grade Separation Projects Often Exceeded the
Preliminary Cost Estimates 21
Caltrans Does Not Always Follow Regulations When Allocating
Supplemental Funds, and Some Regulations Are Inconsistent
With Statutes 23
Recommendations 24
Response to the Audit
Business, Transportation and Housing Agency—
Department of Transportation 27
California State Auditor Report 2007-106 1
September 2007
Summary
Results in Brief AAuuddiitt HHiigghhlliigghhttss .. .. ..
According to data from the Federal Railroad Administration, OOuurr rreevviieeww ooff tthhee GGrraaddee SSeeppaarraattiioonn
167 accidents occurred near at-grade crossings throughout PPrrooggrraamm ffoouunndd tthhaatt::
California in 2006. An at-grade crossing, often referred to as a
railway crossing, is an intersection of railway tracks and a roadway »»AAlltthhoouugghh tthhee aavveerraaggee ccoosstt ooff aa ggrraaddee
at the same elevation, or grade. One method used to address sseeppaarraattiioonn pprroojjeecctt hhaass iinnccrreeaasseedd ffrroomm
dangerous at-grade crossings is to eliminate them by separating $$22..55 mmiilllliioonn iinn 11997744 ttoo aa ccuurrrreenntt aavveerraaggee
the railway and roadway so they no longer intersect, usually ooff jjuusstt mmoorree tthhaann $$2266 mmiilllliioonn,, tthhee aannnnuuaall
via an overpass or bridge. Grade separation projects involving ffuunnddiinngg ooff $$1155 mmiilllliioonn aavvaaiillaabbllee ffoorr
local roadways are the responsibility of the local agency that has tthhee GGrraaddee SSeeppaarraattiioonn PPrrooggrraamm hhaass nnoott
jurisdiction over the roadway. The average cost of these projects cchhaannggeedd ssiinnccee 11997744..
is $26 million, according to the Public Utilities Commission
(Commission), based on a current list of high-priority grade »»LLooccaall aaggeenncciieess ssaayy tthheeyy aarree eexxppeerriieenncciinngg
separation projects. ddiiffifficcuullttiieess sseeccuurriinngg tthhee ffuunnddiinngg nneecceessssaarryy
ttoo ppaayy ffoorr tthheeiirr sshhaarree ooff ggrraaddee sseeppaarraattiioonn
To help local agencies pay for these projects, the State makes some pprroojjeeccttss;; tthhuuss,, ssoommee aarree nnoott nnoommiinnaattiinngg
funding available through what is commonly referred to as the nneeww pprroojjeeccttss ttoo bbee iinncclluuddeedd oonn tthhee PPuubblliicc
Grade Separation Program. As part of the process of determining UUttiilliittiieess CCoommmmiissssiioonn’’ss ((CCoommmmiissssiioonn))
which grade separation projects will receive funding from the pprriioorriittyy lliisstt aanndd mmaannyy aarree nnoott aappppllyyiinngg
Grade Separation Program, state law requires the Commission to ffoorr ffuunnddss ffoorr tthhee pprroojjeeccttss aallrreeaaddyy oonn tthhee
establish a list by July 1 of each year prioritizing each eligible project pprriioorriittyy lliisstt..
nominated by local agencies. Further, state law gives the California
Transportation Commission (CTC) the responsibility for allocating »»AA rreeppoorrtt pprreeppaarreedd bbyy tthhee CCoommmmiissssiioonn iinn
the annual Grade Separation Program appropriation of $15 million MMaarrcchh 22000077 sshhoowweedd tthhaatt $$116655 mmiilllliioonn iiss
to the projects included on the Commission’s priority list. CTC nneeeeddeedd ttoo pprroovviiddee ffuunnddiinngg ffoorr tthhee ssaammee
has delegated this responsibility to the California Department of nnuummbbeerr ooff ggrraaddee sseeppaarraattiioonn pprroojjeeccttss tthhaatt
Transportation (Caltrans). $$1155 mmiilllliioonn pprroovviiddeedd iinn 11997744..
Although the Commission’s priority list of grade separation »»AAddddiittiioonnaall ffuunnddiinngg wwiillll bbee aavvaaiillaabbllee ffoorr
projects for the past several years has contained more than ggrraaddee sseeppaarraattiioonn pprroojjeeccttss ffrroomm aa bboonndd
50 projects, Caltrans has been unable to allocate all the Grade mmeeaassuurree aapppprroovveedd bbyy CCaalliiffoorrnniiaa vvootteerrss
Separation Program funds because local agencies often have not iinn NNoovveemmbbeerr 22000066,, wwhhiicchh wwiillll pprroovviiddee
taken the additional steps necessary to apply for the funds once aa oonnee--ttiimmee aammoouunntt ooff $$225500 mmiilllliioonn ttoo
their projects are included on the Commission’s priority list. Part iimmpprroovvee rraaiillrrooaadd ccrroossssiinngg ssaaffeettyy..
of the reason for this failure to apply for funds is that the cost of
grade separation projects has increased more than tenfold over the »»TThhee CCaalliiffoorrnniiaa DDeeppaarrttmmeenntt ooff
past 30 years, while the funds available from the Grade Separation TTrraannssppoorrttaattiioonn ddooeess nnoott aallwwaayyss ccoommppllyy
Program have remained unchanged. Specifically, based on data wwiitthh ssttaattee rreegguullaattiioonnss wwhheenn aallllooccaattiinngg
provided by the Commission, we found that the average cost of a ssuupppplleemmeennttaall ffuunnddss ttoo pprroojjeeccttss ffoorr wwhhiicchh
grade separation project has increased from $2.5 million in 1974 tthhee fifinnaall ccoossttss eexxcceeeedd tthhee pprreelliimmiinnaarryy
to a current average of just more than $26 million. However, the ccoosstt eessttiimmaatteess..
annual funding of $15 million available for the Grade Separation
Program has not changed since 1974. Local agencies say they are
experiencing difficulties securing the funding necessary to pay
for their share of grade separation projects. As a result, some are
not nominating new projects to be included on the Commission’s
2 California State Auditor Report 2007-106
September 2007
priority list. Furthermore, many are not proceeding with projects
that are already on the priority list, so they are not applying for
funds for the projects.
A report prepared by the Commission in March 2007 showed
that $165 million is needed to provide funding for the same
number of grade separation projects that $15 million provided
for in 1974. Although the report identified a need to increase the
funding for the Grade Separation Program, according to a deputy
director, the Commission has not performed an analysis to identify
where it could obtain additional funding. The Grade Separation
Program currently is funded through the State Highway Account,
which also funds other transportation programs. Consequently,
increasing the funding for this program would redirect funds
from other transportation programs and projects unless another
funding source is identified. Some of this additional funding will
be available from a bond measure approved by California voters
in November 2006, which will provide a one-time amount of
$250 million to improve railroad crossing safety. The bond measure
makes $150 million of these funds available for allocation under
the process established for the Grade Separation Program. In
addition to the funds made available from the bond measure, the
State Transportation Improvement Program can provide funding
to local agencies for various transportation projects including grade
separation projects.
When applying for an allocation from the Grade Separation
Program, local agencies generally submit a preliminary cost
estimate—a rough estimate based on such things as the scope
of work to be performed, data from previous projects, and
experience—to Caltrans. They are reluctant to spend the money
needed to develop a more accurate estimate of a project’s costs
until they receive an allocation. As a result, the final costs of eight
of the nine grade separation projects we reviewed exceeded the
preliminary cost estimates local agencies submitted to Caltrans
in their applications by amounts ranging from $1.5 million to
$19.6 million. However, when we compared the final costs for
seven of these projects to the preconstruction estimates (two cost
estimates were not available), the cost overruns were much less,
between $80,000 and $3.7 million. The preconstruction estimate
is an estimate of a project’s cost based on the final design, using
current construction and material costs.
Finally, we found that Caltrans does not always comply with
state regulations when allocating supplemental funds to projects
for which the final costs exceed the preliminary cost estimates. For
example, four of the six applications we reviewed did not include
one or more of the required certifications, and two were missing
a statement explaining in detail why the original allocation
California State Auditor Report 2007-106
September 2007
was insufficient. Additionally, Caltrans’ current regulations are
inconsistent with statutes; thus, applicants may not be aware of
changes in law and may either choose not to submit an application
or submit inconsistent applications.
Recommendations
In light of local agencies’ limited participation in the Grade Separation
Program, the Legislature should reconsider its intent for the program
and the extent to which it wishes to continue assisting local agencies
with their grade separation projects. Among possible courses of
action, the Legislature could:
• Discontinue the program after the proceeds from the bond
measure approved in November 2006 have been allocated
and require local agencies to compete with a broader range of
projects for funding available to them through other programs
such as the State Transportation Improvement Program.
• Continue the program and increase the annual budget of
$15 million and allocation limits per project because it desires to
continue providing a specific source of funding focused on grade
separation projects.
To ensure that it administers the Grade Separation Program in
compliance with state regulations, Caltrans should follow state
regulations when making supplemental allocations. Further, to be
consistent with statute, it should seek to revise current regulations
to conform to recent amendments to statute.
Agency Comments
Caltrans agrees with our recommendation and will take steps to
address it.
California State Auditor Report 2007-106
September 2007
Blank page inserted for reproduction purposes only.
California State Auditor Report 2007-106
September 2007
Introduction
Background
Data from the Public Utilities Commission (Commission) show
that there are more than 7,700 at-grade crossings in California.
An at-grade crossing is an intersection of railway tracks and a
roadway at the same elevation, or grade, and often is referred to
as a railway crossing. According to data from the Federal Railroad
Administration, 167 accidents occurred near at-grade crossings
throughout California during 2006. One method used to address
this hazard is to eliminate dangerous at-grade crossings by
separating the railway and roadway so they no longer intersect.
As Figure 1 shows, grade separation involves having the railway or
roadway pass over the other, typically by building a bridge structure.
According to data provided by the Commission, there are currently
more than 2,300 grade-separated crossings in California.
Figure 1
A Grade Separation Involves Placing Railroad Tracks and a Road on Separate Levels
Before After
Source: Illustrations prepared by the Bureau of State Audits based on the definition of grade separation.
6 California State Auditor Report 2007-106
September 2007
Grade separation projects involving local roadways are the responsibility
of the local agency that has jurisdiction over the roadway. The average
cost of these projects is $26 million, according to the Commission,
based on a current list of high-priority grade separation projects.
To help local agencies pay for these projects, the State makes some
funding available through what is commonly referred to as the
Grade Separation Program. Specifically, the California Streets and
Highways Code, Section 190, requires the California Department
of Transportation (Caltrans) to include $15 million annually in its
budget for this program. State law also requires that local agencies
secure at least 10 percent of the cost of the project from the affected
railroad companies in order to receive funds from the Grade
Separation Program. The railroad company’s contribution can be
less if the local agency obtains federal funds to assist in paying for
a project.
Although state law makes the funds for the Grade Separation
Program available without regard to fiscal year, the Budget Act
generally limits the availability of these funds to three fiscal years.
If Caltrans does not allocate all funds to local agencies within
three years, the funds revert to the State Highway Account (highway
account)—the original source of funding for this program—and are
no longer available for allocation.
Commission’s Role
The Commission receives nominations for grade separation projects
from local agencies and prioritizes them for possible funding.
Local agencies, which include cities, counties, separation-of-grade
districts, and public entities providing rail passenger transportation
services, nominate crossings in need of grade separation or existing
grade separations that require alteration or reconstruction. The
Commission reviews the nominated projects to ensure that they
are eligible for the Grade Separation Program. According to the
Commission, projects exclusively involving light rail or pedestrian
grade separation are not eligible for the program because state law
defines “railroad” as a railroad corporation and “grade separation” as
a structure that separates a vehicular roadway from railroad tracks.
State law requires the Commission to establish a list by July 1 of each
year prioritizing each eligible project nominated by local agencies. As
Figure 2 shows, the Commission uses a two-year process to establish
the priority list. Specifically, it spends a year developing the priority
list (Fiscal Year 1 in the figure). It then issues the new priority list
by July 1, the beginning of the next fiscal year. It uses the priority
list for that fiscal year (Fiscal Year 2 in the figure) and then, at the
end of the year, revises the list by deleting the projects to which
funds were allocated during the year. It then uses the revised list
California State Auditor Report 2007-106 7
September 2007
for the following fiscal year, at the same time that it is going through
the process of developing a completely new list. In other words, the
Commission uses the same priority list for two years, revising it at
the beginning of the second year to eliminate projects that already
have been funded. During the second year, the Commission begins
the year-long process of creating a new list, which takes effect in the
following year.
Figure 2
The Commission Uses a Two-Year Process to Establish Priority Lists of Grade
Separation Projects
October March
Due date for local The Commission
agencies to send holds hearings April
project nominations before an Due date for local
July to the Commission. administrative agencies on priority list
The Commission law judge. developed in the previous
sends nomination year to send applications
packages to local for funding to Caltrans.
agencies.
Fiscal Year 1 June
The Commission
issues the
Two-year process priority list by
This cycle repeats itself every two fiscal years. July 1 for use in
the fiscal year
beginning on
that date.
Fiscal Year 2
June
Caltrans notifies
the Commission
regarding which April
projects are Due date for local agencies on the
allocated funds.* priority list developed in the previous
year to send applications for funding
to Caltrans.
Source: Information provided by the Commission.
* Upon notification by Caltrans of which projects are allocated funds, the Commission removes
them from the previous list and issues a new priority list by July 1 for the following fiscal year.
June
In developing the list, the Commission requires local agencies to
submit a nomination package for grade separation projects by October.
After reviewing all nomination packages, the Commission prioritizes
projects that involve either the construction of a new grade separation
or the alteration of an existing grade separation. It uses two formulas
it developed through public hearings and with input from local
agencies and Caltrans. These formulas take into account various
factors, including vehicular and train volumes, accident history, and
the amount of funding requested by the local agency. Projects may
include alteration or reconstruction of existing grade separations,
construction of new grade separations to eliminate existing or
proposed grade crossings, or removal or relocation of highways or
railroad tracks to eliminate existing grade crossings.
California State Auditor Report 2007-106
September 2007
After it initially prioritizes the nominated projects, the Commission
holds formal public hearings at which local agencies can provide
testimony concerning their nominations. After the Commission
staff revises the priority list based on the results of the hearing, the
administrative law judge approves it and the Commission issues
the new priority list to be used during the next two fiscal years.
Caltrans’ Role
Caltrans allocates the Grade Separation Program funds to projects
on the Commission’s priority list. State law gives the California
Transportation Commission (CTC) the responsibility of allocating
the annual Grade Separation Program appropriation of $15 million
to the projects included on the Commission’s priority list. CTC has
delegated this responsibility to Caltrans.
When local agencies are ready to begin construction on a project
included on the Commission’s priority list, state regulations require
them to submit an application to Caltrans. The application must
include satisfactory evidence that the Commission approved the
project for construction, that sufficient local funds will be made
available as the project progresses, that all necessary agreements
with affected railroad companies have been executed, that all
required environmental impact reports were approved, and that
all other prerequisites to the awarding of the construction contract
can be accomplished within two years after the allocation.
Depending on the type of project, state law limits allocations from
the Grade Separation Program to either 50 percent or 80 percent
of a project’s estimated cost and imposes maximum allowable
contributions of $5 million, $15 million, or $20 million. Projects
involving the construction of grade separations at locations where
there were previously no at-grade crossings and those involving
the elimination of at-grade crossings that have been in existence
for fewer than 10 years, are eligible to receive allocations no greater
than 50 percent of the estimated costs. This limit increases to
80 percent for all other projects.
In addition to these limits, under state law each grade separation
project generally can receive no more than $5 million. However,
Caltrans can allocate more than $5 million to eligible projects under
certain circumstances. For example, grade separation projects that
have the highest priority are eligible for as much as $15 million.
Projects that alleviate traffic and safety problems or that provide
improved rail services can receive as much as $20 million regardless
of their ranking on the priority list. Caltrans cannot allocate more
than half of the Grade Separation Program funds available in a
given fiscal year to these types of projects, however, and they must
California State Auditor Report 2007-106
September 2007
be funded over two to five years at a rate not greater than $5 million
per year. Lastly, if the final cost of projects exceed the preliminary
cost estimates the local agencies provided to Caltrans as part of
their application for Grade Separation Program funds, state law
allows Caltrans to augment the projects proportionately with
supplemental allocations.
Funding Source for the Grade Separation Program
The Grade Separation Program is funded primarily from the
highway account, for which the principal sources of funds are excise
taxes on motor vehicle fuels, commercial vehicle weight fees, and
federal highway trust funds. State law requires the highway account
to provide funding for the administration of Caltrans; the State
Highway Operations and Protection Program; and local assistance
programs, such as the Grade Separation Program, required by state
or federal laws. Any amount remaining in the highway account after
funding the required programs is available for capital improvement
projects under the State Transportation Improvement Program
(STIP). However, according to CTC, the STIP has not received
funds from the highway account since 2004. Finally, state law
requires that the highway account be reimbursed for $5 million of
the $15 million funding it provides the Grade Separation Program.
It receives this reimbursement from motor vehicle fuel license
taxes and use fuel taxes that otherwise would be distributed to
cities and counties.
Recently Approved Bond Measure
California voters recently approved the Highway Safety, Traffic
Reduction, Air Quality, and Port Security Bond Act of 2006
(Bond Act), which provides $250 million to improve railroad crossing
safety. The Bond Act makes these funds available to Caltrans, upon
appropriation by the Legislature, for the completion of high-priority
grade separation and railroad crossing safety improvements. Of
the $250 million in Bond Act funds, $150 million are available for
allocation using the process established for the Grade Separation
Program. Other states have taken similar measures to provide
funding for grade separation projects. For example, Ohio’s Grade
Separation Program is a 10-year, $200 million program to fund
30 projects that were selected using criteria such as safety, train
frequency, traffic volume, and project costs.
10 California State Auditor Report 2007-106
September 2007
Scope and Methodology
The Joint Legislative Audit Committee (audit committee) requested
that the Bureau of State Audits (bureau) perform an audit of the
funding and approval process required for state and local transportation
agencies for grade separation projects. Specifically, the audit committee
asked the bureau to assess the roles and responsibilities of the various
agencies involved in the funding and approval of grade separation
projects to determine if any duplication of effort or program exists.
Further, the audit committee requested that the bureau determine
whether the Grade Separation Program is being administered
and operated in accordance with the appropriate statutes and
regulations, and that it identify any obstacles that state and local
agencies face in meeting the program’s legislative goals.
We also were asked to identify the funding sources for the Grade
Separation Program and to determine whether the program uses
the sources available and whether funding levels are reasonable
and consistent with other comparable programs. The audit
committee asked that we identify any changes in statutes that
would improve the program’s administration or any alternative
funding mechanisms that could facilitate meeting its legislative
goals. In addition, we were asked to determine which local agencies
have received state funding for grade separation projects and, to
the extent possible, to review estimated and actual costs for the
projects. We also were asked to review a sample of these projects
to determine the reasons for any cost overruns, the efforts local
agencies made in planning and funding the projects, best practices
available to local agencies to improve projections and control
costs, and whether all local agencies face similar issues with
projecting and controlling costs.
To identify the roles and responsibilities of the various entities
involved, we reviewed the laws and regulations related to the Grade
Separation Program and interviewed appropriate state agency
personnel. We also reviewed the policies and procedures of the
state agencies involved to determine if there was a duplication
of effort. We have described the roles of the two major state
agencies—the Commission and Caltrans—responsible for
administering the Grade Separation Program. We did not identify
any areas of duplication. We also discussed with staff at both the
Commission and Caltrans whether administration of the Grade
Separation Program should be the responsibility of one agency
rather than shared by both. According to Commission staff, the
Commission is legally responsible for regulating activities involving
railroad crossings in California, and thus it believes that it should be
responsible for prioritizing the railroad grade separation projects.
The Commission also indicated that, because Caltrans can be the
lead agency for a project that requests an allocation from the Grade
California State Auditor Report 2007-106 11
September 2007
Separation Program, it would not be appropriate for Caltrans to
determine a project’s priority. Additionally, the chief of Caltrans’
Office of Rail Equipment and Track Construction indicated that
the process for developing the priority list and the process for
administering the allocations are very distinct, with little or no
overlap, as provided for in statute. Thus, the chief did not see any
significant advantages or disadvantages of having either one agency
or two agencies administer the Grade Separation Program. Further,
we identified similar state and federal programs and reviewed
their requirements to determine if the Grade Separation Program
duplicated these other programs.
To determine if the state agencies involved in administering the
Grade Separation Program complied with the program’s legal
requirements, we compared their policies and procedures to
the legal requirements. We also tested a sample of 15 projects on the
Commission’s priority list for fiscal years 2004–05 to 2006–07 to
determine whether the Commission appropriately followed state
laws, regulations, and its own policies when calculating the priority
for these projects. We found that the Commission appropriately
calculated the priorities for the projects we tested. Further, we
analyzed the Commission’s formulas for establishing a project’s
priority. We found that in 2001 the Commission modified the
formulas after conducting workshops with interested parties. We
also selected a sample of three applications for new projects and
six supplemental applications that were approved or rejected by
Caltrans to determine whether the reasons for such approvals
and rejections were in accordance with the laws and regulations.
We found that Caltrans complied with the laws and regulations in
approving or rejecting applications for new projects.
To determine the obstacles that state agencies face in meeting
program goals, we compared the number of projects included
on the Commission’s priority list during fiscal years 2002–03 to
2006–07 to the number of projects awarded allocations during the
same time. We reviewed Caltrans’ accounting records to determine
whether it allocated all available Grade Separation Program funds.
We also interviewed appropriate personnel at the Commission and
Caltrans to determine what obstacles they face in administering the
Grade Separation Program and in meeting program goals.
To identify local agencies’ efforts in planning and funding projects
and the obstacles they face in seeking and obtaining approval and
funding for the Grade Separation Program, we surveyed a sample
of 75 local agencies. Specifically, using data available from the
Commission and Caltrans, we identified 422 local agencies that were
responsible for the more than 10,000 at-grade and grade-separated
crossings in California. We also identified 57 local agencies
that nominated grade separation projects to the Commission
12 California State Auditor Report 2007-106
September 2007
during fiscal years 2000–01 to 2006–07 and we sent a survey to
48 of them. These 48 local agencies included nine that received
an allocation from the Grade Separation Program and 12 that did
not renominate a project in subsequent years. Finally, we selected
27 other local agencies to survey that did not nominate any projects
during the seven years we reviewed. Of the 75 local agencies we
surveyed, 57 responded. We analyzed the survey responses to
determine whether all local agencies face similar obstacles in
obtaining approval and funding for the Grade Separation Program.
To determine whether the local agencies are completing the grade
separation projects within budget, we reviewed Caltrans’ records
for the 17 projects completed as indicated by its accounting
records for fiscal years 2000–01 through 2006–07 and identified
those projects that had cost overruns. We selected nine of the
17 completed projects to further analyze their cost overruns,
ensuring coverage throughout the State and a range of cost
overruns. We then visited or contacted staff at each local agency
responsible for these nine projects to obtain an understanding
of the reasons for the cost overruns and, if available, reviewed
supporting documents. We analyzed their responses to determine
whether local agencies throughout the State face similar issues with
projecting and controlling costs.
California State Auditor Report 2007-106 1
September 2007
Audit Results
Local Agencies Believe Allocations Are Not Sufficient to Allow Them
to Take Advantage of the Grade Separation Program
Once they have nominated a grade separation project to the
Public Utilities Commission (Commission) and the project has
been placed on the Commission’s priority list, many local agencies
we surveyed are not taking the additional steps to apply to the
California Department of Transportation (Caltrans) for funding
under the Grade Separation Program. Many of these agencies
indicated that they are not applying for this funding because they
are having difficulty securing the funds to cover their portion of the
costs of grade separation projects. We found that the portion of
project costs that local agencies are expected to pay has increased
dramatically over the past 30 years. According to data provided
by the Commission, the average cost of a grade separation project
increased from $2.5 million in 1974 to more than $26 million
currently, while the annual budget of $15 million for the Grade
Separation Program has remained unchanged since 1974. A report
prepared by the Commission showed that $165 million is needed to
provide funding for the same number of grade separation projects
as $15 million provided in 1974. However, some local agencies have
been able to secure funding from other sources to pay for their
projects without using funds from the Grade Separation Program.
A recently approved bond measure will provide additional funding
for grade separation projects.
Funding for the Grade Separation Program Has Not Kept Pace With
Increased Construction Costs, So Some Local Agencies Choose Not to
Nominate Potential Projects
Although the average cost of a grade separation project has
increased considerably, the budget for the Grade Separation
Program has not changed since 1974. In 1971 an amendment to
state law increased the annual Grade Separation Program budget
from $5 million to $10 million. Legislation that became operative in
1974 again increased the budget, this time to $15 million annually.
This legislation also increased the amount of allocation a local
agency was eligible to receive from no more than 50 percent to no
more than 80 percent of the estimated costs of a project. At that
time, according to our calculations based on Commission data,
the average cost of a grade separation project was $2.5 million.
Since 1974, however, this average cost has increased by more than
tenfold, to more than $26 million in fiscal year 2006–07, while the
budget for the Grade Separation Program has remained unchanged.
1 California State Auditor Report 2007-106
September 2007
This disparity between project costs and available funding has
greatly increased the portion that local agencies are expected to
pay for a grade separation project. As Figure 3 shows, local agencies
currently must pay about 81 percent of the project costs, either
by using their own funds or by finding other funding sources.
In 1974 local agencies generally were expected to pay only about
20 percent of the costs for a grade separation project receiving an
allocation from the Grade Separation Program. In fact, a legislative
committee’s analysis of the 1974 legislation that ultimately increased
the budget for the Grade Separation Program to $15 million and
increased the allocation limit to 80 percent indicated that the bill’s
purpose was to reduce the cost to local agencies because many
of them had been unable to meet their share of the cost at the
previous levels.
Figure 3
Local Agencies Currently Are Required to Provide a Greater Proportion of
Funding for Grade Separation Projects Than in the Past
$30
25
20
15 81%
10
5
20% 19%
80%
0
June
)snoillim
ni
srallod(
tsoc
tcejorp
egarevA
Portion of total cost that
local agencies must fund
$26.3 million Portion of total cost that
the Grade Separation
Program can fund
$2.5 million
1974 2006
Sources: Public Utilities Commission’s February 2005 report and its 2006 priority list and California
Streets and Highways Code, Section 2454.
Some local agencies we surveyed indicated that they do not even
nominate projects to be considered for the Commission’s priority
list because they are unable to secure funds for their share of the
costs. For example, an official with the city of Torrance estimates
that one potential grade separation project the city would like to
construct will cost roughly $25 million. According to the official, the
city would have to secure $17.5 million in other funding, provided it
California State Auditor Report 2007-106 1
September 2007
receives a $5 million allocation from the Grade Separation Program
and the 10 percent railroad contribution. The city has been unable
to secure the other funding, so it has not nominated the project to
be considered for the Commission’s priority list. We found that
18 of the 57 local agencies (32 percent) that responded to our survey
did not nominate or renominate all their potential grade separation
projects during the past seven years because they were unable to
obtain the funding needed to pay for their portion of the costs. Of
these 18 local agencies, 13 also indicated that the $5 million limit per
project was not a sufficient amount, considering the total cost of
their projects.
In March 2007 the Commission prepared a report showing that
$165 million is needed to provide funding for the same number
of grade separation projects that $15 million provided in 1974.
Additionally, this report recommended that the maximum IInn MMaarrcchh 22000077 tthhee CCoommmmiissssiioonn
allocation for a single project be increased from $5 million to pprreeppaarreedd aa rreeppoorrtt sshhoowwiinngg tthhaatt
$25 million. This increase in the maximum amount allowed for $$116655 mmiilllliioonn iiss nneeeeddeedd ttoo pprroovviiddee
each project would mean that local agencies would need to secure ffuunnddiinngg ffoorr tthhee ssaammee nnuummbbeerr ooff
a smaller portion of the funding for grade separation projects. Of ggrraaddee sseeppaarraattiioonn pprroojjeeccttss tthhaatt
the 41 local agencies that responded to our survey and indicated $$1155 mmiilllliioonn pprroovviiddeedd iinn 11997744..
that they were aware of the Grade Separation Program and had
crossings in need of separation, 35 (or 85 percent) indicated that
they would nominate more projects if funding for the Grade
Separation Program and the limit on the allocation per project
were increased.
Although the report prepared by the Commission identified the
need to increase the funding for the Grade Separation Program,
according to a deputy director, the Commission has not done an
analysis to identify a source of additional funding. As we stated in
the Introduction, the funding for the Grade Separation Program
currently comes from the State Highway Account (highway
account), which also is required by law to provide funding for
the administration of Caltrans, the State Highway Operations
and Protection Program (SHOPP), the State Transportation
Improvement Program (STIP), and local assistance programs
required by state or federal laws. Therefore, increasing the funding
for the Grade Separation Program would redirect funds from other
transportation programs and projects unless another funding
source were identified.
In 1999 the Commission sponsored legislation to increase the
Grade Separation Program’s annual budget from $15 million to
$60 million. At that time the Commission pointed out that funding
for the Grade Separation Program had remained at $15 million
since 1974 and that increases in the cost of land acquisition and
project construction had resulted in allocations to fewer projects
over time. The analysis of the bill indicated that an increase in the
16 California State Auditor Report 2007-106
September 2007
annual appropriation for the Grade Separation Program would
reduce the funding available to local transportation agencies and
the State through the STIP by the same amount. Ultimately, the
legislation did not make it through the legislative process. Seven
years later, in 2006, Assembly Bill 1785 again sought to increase the
Grade Separation Program’s annual budget, this time to $70 million.
However, as with the earlier bill, the bill analysis indicated that the
increase in the program’s allocation would reduce funds available
for other transportation programs and projects such as the SHOPP
and the STIP. This more recent bill also failed to make it through
the legislative process.
Caltrans Has Received Few Applications for Funds Over the Past
Five Years, and Some Grade Separation Program Funds Have Reverted
to the Highway Account
AAlltthhoouugghh tthhee CCoommmmiissssiioonn’’ss pprriioorriittyy As we discussed in the Introduction, after the Commission
lliisstt hhaass iinncclluuddeedd 5500 ttoo 7700 pprroojjeeccttss includes a project on its priority list, the local agency must submit
eeaacchh yyeeaarr ffoorr tthhee ppaasstt fifivvee yyeeaarrss,, an application to Caltrans before it can receive funding from
CCaallttrraannss hhaass rreecceeiivveedd aapppplliiccaattiioonnss the Grade Separation Program. As shown in Table 1, although the
ffrroomm oonnllyy 1100 llooccaall aaggeenncciieess Commission’s priority list has included 50 to 70 projects each
rreeqquueessttiinngg ffuunnddss ffoorr pprroojjeeccttss year for the past five years, according to Caltrans, it has received
dduurriinngg tthhaatt ttiimmee.. applications from only 10 local agencies requesting funds for their
projects during that time. Caltrans has awarded allocations to eight
of these 10 local agencies and two are pending consideration. We
found that many local agencies did not apply for an allocation, even
though some of their projects ranked higher on the Commission’s
priority list than the ones for which agencies applied and received
allocations. Specifically, projects that ranked as low as 25, 40,
and 60 on the priority list have applied for and received Grade
Separation Program funds. In fact, only one of the eight projects for
which Caltrans awarded an allocation during the last five years was
among the top 10 projects on the priority list.
Additionally, we found that 20 of the 57 local agencies that
responded to our survey had nominated a project for inclusion
on the priority list during the last seven years but did not take
the additional step of submitting an application to Caltrans for
program funding. As Table 2 on page 18 shows, 10 of these 20 local
agencies indicated they could not raise the local funds needed for
their portion of the project, and four of these 10 also noted that
they could not reach an agreement with the railroad company to
contribute to the project as required. Further, four of the 10, as well
as six others, indicated that they did not apply because they did
not believe the project would be funded, given their projects’ low
priority on the Commission’s list.
California State Auditor Report 2007-106 17
September 2007
Table 1
Very Few Local Agencies Applied for a Grade Separation Program Allocation
During the Last Five Years
Number oF Number oF
Number oF Number oF New Number oF New suPPlemeNtal suPPlemeNtal
Projects oN the aPPlicatioNs allocatioNs aPPlicatioNs allocatioNs
Fiscal Year PrioritY list caltraNs received awarded caltraNs received awarded
2002–03 56 3 3 0 0
2003–04 53 0 0 5 5
2004–05 58 0 0 1 1
2005–06 58 5* 0 0 0
2006–07 70 2† 5‡ 0 0
Sources: Data from Public Utilities Commission and Caltrans.
* Caltrans initially rejected all five applications submitted in fiscal year 2005–06 in general
because they contained deficiencies related to railroad agreements. According to Caltrans,
three of the local agencies requested additional time to resolve the deficiencies and did so. The
remaining two local agencies resubmitted their applications in fiscal year 2006–07.
† This number reflects two new applications submitted by local agencies in fiscal year 2006–07,
but does not include the two applications that local agencies resubmitted after Caltrans rejected
them in fiscal year 2005–06. These two applications are already included in the count for that
fiscal year.
‡ Caltrans awarded allocations to five of the seven local agencies that applied during fiscal
years 2005–06 and 2006–07. The remaining two are pending consideration.
Because so few local agencies applied for funding during the
last five years, Caltrans’ records show that all local agencies that
applied for funding, in fact, were awarded funding or are pending
consideration, regardless of their ranking on the Commission’s
priority list. However, even though Caltrans awarded funding to
all that applied, it has been unable to allocate the entire $15 million
budgeted annually because it has received so few applications since
fiscal year 2002–03. As we stated in the Introduction, the California
Streets and Highways Code, Section 190, makes these funds
available without regard to fiscal year, but the Budget Act generally
limits the availability of these funds to three fiscal years. Thus,
approximately $5.7 million has reverted to the highway account
since fiscal year 2002–03. Further, as of July 2007 Caltrans still had
approximately $9.3 million that it had not yet allocated to projects.
If it is unable to allocate $4.3 million of these funds to eligible
projects by June 30, 2008, and $5 million by June 30, 2009, these
funds also will revert to the highway account.
1 California State Auditor Report 2007-106
September 2007
Table 2
Local Agencies Identified Two Main Reasons for Not Applying to Caltrans for an Allocation
did Not believe the Project would could Not reach aN agreemeNt
be FuNded because it received a verY with the railroad comPaNY to
low PrioritY oN the commissioN’s did Not aPPlY because oF coNtribute 10 PerceNt oF the
local ageNcY PrioritY list comPared to others lack oF local FuNds Project’s cost as required other*
City of Delano X
City of Elk Grove X
City of Encinitas X
City of Los Angeles X X X
City of Merced X
City of Newark X X X
City of Palmdale X X X X
City of Redding X
City of Riverside X X
City of San Mateo X
City of Santa Fe Springs X
City of South San Francisco X
City of Stockton X
City of Vista X
Greater Bakersfield
X
Separation of Grade District
Los Angeles County X X
San Bernardino County X
San Joaquin County X
San Mateo County
Transportation Authority† X X
Tehama County X
Totals 10 10 4 6
Sources: Survey responses from 57 local agencies.
* Other reasons local agencies cited for nominating a project for the priority list but not ultimately applying to Caltrans for an allocation included the
following: they were not aware of the need to submit an application to Caltrans after nominating the project to the Commission, the agreement
with the railroad had not been initiated, or they were not ready to apply for funding because the project was still in an early phase or was taking
longer than expected to develop.
† We originally sent the survey to the San Mateo County Transportation Authority. However, the survey was completed and returned by the Peninsula
Corridor Joint Powers Board. These two entities operate as part of the San Mateo County Transit District and share the responsibilities for grade
separation projects.
California State Auditor Report 2007-106 1
September 2007
Some Local Agencies Are Not Aware of the Grade Separation Program,
and Some Have Received Adequate Funds From Other Sources
Of the 57 local agencies that responded to our survey, 10 told us that
they were not aware of the Grade Separation Program. Two of these
10 local agencies noted that they have a need for grade separation.
However, we found that the Commission appears to appropriately
inform local agencies of the existence of the Grade Separation
Program. According to the Commission, as part of its process for
establishing the priority list, it mails nomination request letters to
all parties on its mailing list. The mailing list includes local agencies
that have nominated a project previously, as well as all other public
agencies known to have crossings under their jurisdiction. The
mailing list also includes railroad corporations operating in California,
light-rail transit agencies, the League of California Cities, and the
California State Association of Counties. The Commission also
publishes the letter on its Web site. Although these 10 local agencies
indicated that they were unaware of the Grade Separation Program,
we found that all 10 are included on the Commission’s mailing list.
We also found that some local agencies constructed grade
separation projects without using Grade Separation Program
funds. State law requires that the Commission approve any railroad
crossing construction. According to the Commission, during
fiscal years 2005–06 and 2006–07 it approved 18 projects that
were eligible for the Grade Separation Program. According to the
Commission, of these 18 projects, only five were nominated to be EEiigghhtt ooff tthhee 5577 llooccaall aaggeenncciieess
included on the priority list for the Grade Separation Program. rreessppoonnddiinngg ttoo oouurr ssuurrvveeyy iinnddiiccaatteedd
Further, eight of the 57 local agencies responding to our survey tthhaatt tthheeyy hhaadd ccoommpplleetteedd aa ggrraaddee
indicated that they had completed a grade separation project sseeppaarraattiioonn pprroojjeecctt wwiitthhoouutt GGrraaddee
without Grade Separation Program funds. A project for one of SSeeppaarraattiioonn PPrrooggrraamm ffuunnddss..
these eight local agencies was not eligible for the Grade Separation
Program because it involved grade separation for pedestrians only.
Further, two of the eight agencies incorrectly believed their projects
were ineligible because they were building a new grade-separated
crossing where no at-grade crossing existed previously.
Additional Sources of Funds Are Available for Local Grade
Separation Projects
Although the Grade Separation Program’s annual budget has not
increased since 1974, other sources can provide funds for grade
separation projects. In November 2006 California’s voters approved
the Highway Safety, Traffic Reduction, Air Quality, and Port Security
Bond Act of 2006 (Bond Act), which provides $250 million to
improve railroad crossing safety. Of the $250 million, the Bond Act
makes $150 million available, upon appropriation by the Legislature,
for allocation under the process established for the Grade Separation
20 California State Auditor Report 2007-106
September 2007
Program. However, high-priority projects funded by the Bond
Act can qualify to receive 50 percent of the total cost of a project,
PPrroovviiddeedd tthhaatt llooccaall aaggeenncciieess without the limits established under the Grade Separation Program.
aarree aabbllee ttoo sseeccuurree tthheeiirr hhaallff ooff Even with an allocation of 50 percent of the project cost, some local
tthhee ffuunnddiinngg,, tthhee $$115500 mmiilllliioonn agencies might be unable to secure the remaining funding. For
iinn BBoonndd AAcctt pprroocceeeeddss aavvaaiillaabbllee example, one local agency, with a project estimated at $136 million,
ffoorr aallllooccaattiioonn uunnddeerr tthhee pprroocceessss would have to secure $68 million in other funds. Nevertheless,
eessttaabblliisshheedd ffoorr tthhee GGrraaddee provided that local agencies are able to secure the remaining
SSeeppaarraattiioonn PPrrooggrraamm ccoouulldd hheellpp 50 percent of the project cost from other sources, the $150
ffuunndd tthhee eeiigghhtt hhiigghheesstt--rraannkkeedd million could help fund the eight highest-ranked projects on the
pprroojjeeccttss oonn tthhee CCoommmmiissssiioonn’’ss fifissccaall Commission’s fiscal year 2006–07 priority list, which total about
yyeeaarr 22000066––0077 pprriioorriittyy lliisstt.. $300 million. The remaining 62 projects on the priority list have a
total cost of more than $1.5 billion.
The Bond Act authorizes the California Transportation Commission
(CTC), in consultation with Caltrans, the High-Speed Rail Authority,
and the Commission, to allocate the remaining $100 million to
high-priority railroad crossing improvements, including grade
separation projects. CTC and Caltrans say they have not developed
guidelines to determine how to fund projects under this part of the
Bond Act. The fiscal year 2007–08 budget includes $123 million of
the $250 million to carry out the purposes of the Bond Act, with the
remainder to be appropriated in subsequent years. According
to CTC, approximately $75 million of the budget is for projects
that are part of the process for the Grade Separation Program,
and the remaining amount is to be allocated in consultation with
Caltrans, the High-Speed Rail Authority, and the Commission.
The Commission and CTC indicated they will use the priority list
already in place when allocating the $75 million budgeted for fiscal
year 2007–08.
In addition to the Bond Act, the STIP can provide funding to local
agencies for grade separation projects. The STIP is a multiyear
capital improvement program consisting of transportation projects,
including grade separation projects, adopted by the CTC. According
to Caltrans, CTC has allocated $24 million from the STIP for a grade
separation project for fiscal year 2006–07 and will be allocating an
additional $87 million for four other local grade separation projects.
To nominate projects for inclusion in the STIP, local agencies
must work through their designated authority, such as a regional
transportation planning agency, a county transportation commission,
or a metropolitan planning organization, as appropriate. However,
the designated authority ultimately decides which projects to
submit to the CTC for possible funding. The CTC then conducts
public hearings before selecting the projects to be funded under
this program. The STIP provides funding for many different types of
projects, so grade separation projects compete with other projects
California State Auditor Report 2007-106 21
September 2007
for funding. Therefore, some local agencies stated that they have
been unsuccessful in obtaining the STIP funding for their grade
separation projects.
The Final Costs of Grade Separation Projects Often Exceeded the
Preliminary Cost Estimates
State regulations require local agencies to provide a project cost
estimate (preliminary cost estimate) as part of the application they
submit to Caltrans when applying for funding. We compared the
preliminary cost estimates submitted by local agencies to the final
costs for nine of the 17 grade separation projects that received
final payments from Caltrans between fiscal years 2000–01
and 2006–07. As Table 3 on the following page shows, the final
costs differed dramatically from the preliminary cost estimates
for eight of the nine projects we reviewed, exceeding them by
amounts ranging from $1.5 million to $19.6 million. However,
when we compared the final costs for seven of these projects to the
preconstruction cost estimates (one local agency was unable to
provide these cost estimates for two projects), the cost overruns were
much less, between $78,000 and $3.7 million. These overruns
typically were due to unexpected conditions on the construction
site, such as the discovery of objects that had been buried in the
roadway a long time ago and needed to be moved.
When we discussed the reasons for the significant differences
between the preliminary cost estimates and the final costs, most
local agencies explained that the preliminary cost estimate is simply
a rough estimate based on such things as the scope of work to
be performed, data from previous projects, and experience. For
example, one local agency told us that the preliminary cost estimate
it prepared in 1995 and submitted to the Commission and to
Caltrans was based on designs completed during the 1960s and
updated using construction cost data from the 1990s. The local
agencies also told us that the preconstruction cost estimate they
prepare at a later date is much more accurate because they derive
it from the project’s final designs, using current construction and
material costs. They indicated that it is easier to estimate costs that
are otherwise hard to predict, such as right-of-way acquisition, after WWhheenn wwee aasskkeedd wwhhyy tthheeyy ddoo nnoott
they have actual project designs. When we asked why they do not bbaassee tthhee pprreelliimmiinnaarryy ccoosstt eessttiimmaattee
base the preliminary cost estimate on project designs, several local oonn pprroojjeecctt ddeessiiggnnss,, sseevveerraall llooccaall
agencies indicated they are reluctant to spend the money needed aaggeenncciieess iinnddiiccaatteedd tthheeyy aarree
to develop the project designs until they know they will receive rreelluuccttaanntt ttoo ssppeenndd tthhee mmoonneeyy
Grade Separation Program funding and they do not invest in a nneeeeddeedd ttoo ddeevveelloopp tthhee pprroojjeecctt
design until funds are secured. In fact, 30 of the 57 local agencies ddeessiiggnnss uunnttiill tthheeyy kknnooww tthheeyy
that responded to our survey indicated that they had nominated a wwiillll rreecceeiivvee GGrraaddee SSeeppaarraattiioonn
project for inclusion on the Commission’s priority list since fiscal PPrrooggrraamm ffuunnddiinngg..
22 California State Auditor Report 2007-106
September 2007
year 2000–01. Of these 30 local agencies, 20 noted that they had
submitted rough cost estimates based on the scope of work to be
performed rather than on actual designs for the project.
Table 3
Final Costs Generally Far Exceeded the Preliminary Estimates, but Preconstruction Cost Estimates
Were More Accurate
diFFereNce diFFereNce
betweeN betweeN
date oF date oF PrelimiNarY PrecoNstructioN
PrelimiNarY PrelimiNarY PrecoNstructioN PrecoNstructioN date oF Project cost estimate cost estimate
local ageNcY cost estimate cost estimate cost estimate cost estimate FiNal cost comPletioN aNd FiNal cost aNd FiNal cost
City of
$6,521,000 March 1995 $7,496,520 July 2000 $11,225,611 August 2003 $4,704,611 $3,729,091
Hayward*
City of
Ontario† 8,156,400 April 1991 18,568,157 June 2001 18,646,273 March 2004 10,489,873 78,116
City of
10,513,000 December 1995 11,542,340 June 1998 12,079,435 May 1999 1,566,435 537,095
Riverside‡
City of
6,092,680 December 1997 11,638,284 June 1999 14,043,406 December 2003 7,950,726 2,405,122
Stockton§
Fresno
4,537,000 April 1995 6,377,283 September 1997 1,840,283
Countyll
Fresno
5,122,760 April 1995 6,643,434 November 2003 1,520,674
Countyll
Los Angeles
County# 26,000,000 April 1995 42,430,000 May 1999 45,598,667 March 2003 19,598,667 3,168,667
Los Angeles
County# 5,130,000 May 1995 14,788,957 April 1999 14,711,473 March 2003 9,581,473 (77,484)
San Joaquin
6,759,000 March 2001 7,344,700 July 2002 6,406,845 September 2003 (352,155) (937,855)
County**
Source: Grade separation project records obtained from Caltrans and local agencies.
* The agency explained that cost overruns arose because of the delay between the time the project was nominated and the time it was completed,
that it encountered unexpected conditions on the construction site, and that it had to invest funds in a detour it did not expect to have to build.
† The agency explained that the preliminary and preconstruction cost estimates are significantly different because of design changes and increases
in construction costs occurring during the period separating the two estimates.
‡ The agency explained that it submits the preliminary cost estimate to the Commission in order to be on the priority list as soon as possible, and that
construction cost overruns are typical.
§ The agency explained that the project was urban and therefore right-of-way issues were hard to estimate until a final detailed design was
completed and that an increase in material costs escalated prices.
ll Although the agency was unable to locate the entire preconstruction cost estimate, it provided an estimate for the most significant portion of
the project’s costs—the contruction costs. For the first project, the preconstruction cost estimate dated April 1996 was $4,975,000, while the
construction cost component of the final costs was $4,358,000. Thus, for this project, the construction cost component of the final costs was
actually less than the preconstruction cost estimate by $617,000. For the second project, the preconstruction cost estimate dated June 2002
was $4,744,000, while the construction cost component of the final costs was $5,139,000. Thus, the construction cost component of the final
costs exceeded the preconstruction cost estimate by $395,000.
# The agency explained that the most expensive project encountered much greater right-of-way and utility relocation costs than expected, and
that the other project experienced costly construction-related delays and received construction bids higher than had been estimated.
** The agency explained that, because the project was rural, it was easier to estimate its cost accurately compared to urban projects, which typically
have larger overruns because of right-of-way acquisition.
California State Auditor Report 2007-106 2
September 2007
Further, two local agencies we contacted also indicated that the
preliminary cost estimates can differ significantly from the final
costs because of the delay between the nomination of a project for
inclusion on the Commission’s priority list and the project’s final
completion. During this lengthy time period, there are usually
design changes and increases in construction costs, which
often exceed provisions built into preliminary cost estimates to
allow for inflation as well as unforeseen expenses encountered
during construction. As shown in Table 3, the time between the
preliminary cost estimate and project completion ranged from
2.5 years to 13 years for the nine projects we reviewed.
Caltrans Does Not Always Follow Regulations When Allocating
Supplemental Funds, and Some Regulations Are Inconsistent
With Statutes
State law allows Caltrans to award supplemental funds to local
agencies if a project’s final cost exceeds the preliminary cost estimates
the local agency provided to Caltrans. Local agencies provide the
preliminary cost estimates as part of their application for Grade
Separation Program funds. The Commission informs the local
agencies of the requirements for requesting supplemental allocations
when it invites them to nominate grade separation projects to be
included on its priority list. We reviewed all six projects that received
supplemental funds from Caltrans between fiscal years 2003–04
and 2006–07 to determine if Caltrans followed the requirements
of state law and regulations when approving the requests for these
supplemental funds. We found that Caltrans did not always follow
state regulations when it awarded the supplemental allocations.
State regulations governing the Grade Separation Program specify
the content of applications for supplemental allocations. For
example, these regulations require that a local agency’s governing
body must certify that the project was completed, that railroad
companies paid the share required by state law, and that the final SSttaattee rreegguullaattiioonnss ggoovveerrnniinngg
cost has been determined and is set forth in the supplemental tthhee GGrraaddee SSeeppaarraattiioonn PPrrooggrraamm
application. Further, the regulations also require local agencies ssppeecciiffyy tthhee ccoonntteenntt ooff aapppplliiccaattiioonnss
to include in the application statements that explain in detail ffoorr ssuupppplleemmeennttaall aallllooccaattiioonnss,,
why the original allocation was insufficient and a final accounting iinncclluuddiinngg vvaarriioouuss llooccaall aaggeennccyy
of the project’s cost. However, four of the six applications we cceerrttiifificcaattiioonnss.. HHoowweevveerr,, ffoouurr ooff
reviewed did not include one or more of the required certifications. tthhee ssiixx aapppplliiccaattiioonnss wwee rreevviieewweedd
In addition, two of the six applications were missing a statement ddiidd nnoott iinncclluuddee oonnee oorr mmoorree ooff tthhee
explaining in detail why the original allocation was insufficient. rreeqquuiirreedd cceerrttiifificcaattiioonnss..
Finally, for two of the six applications, the local agencies did not
submit a final accounting of the project’s cost until after Caltrans
awarded them the supplemental allocations. However, although
2 California State Auditor Report 2007-106
September 2007
Caltrans did not have the final costs for these two projects, it
ultimately allocated the appropriate amounts to the local agencies
as prescribed by state law.
The chief of Caltrans’ Office of Rail Equipment and Track
Construction noted that his office was not aware of the regulations
for supplemental allocations. However, he stated that, because of
the lack of new applications, the noncompliance with regulations
did not prevent otherwise eligible projects from being funded
through the Grade Separation Program. Although we agree that,
because of the low number of applications received, Caltrans’
noncompliance with regulations for supplemental allocations did
not prevent other eligible local agencies from receiving Grade
Separation Program funds, we believe it is important to administer
the Grade Separation Program in compliance with state regulations.
Lastly, state regulations governing the Grade Separation Program
specify the required application process and content of applications
for the allocation of funds for grade separation projects. However,
certain state regulations are inconsistent with statute because of
recent amendments to statutes governing the Grade Separation
Program. In 2005 the Legislature amended the California Streets
and Highways Code, Section 2456, to allow local agencies two years
to accomplish all matters prerequisite to the awarding of the
construction contract. Current state regulations do not reflect
this change and allow local agencies only one year. Additionally,
the Legislature amended the California Streets and Highways
Code, Section 2454, in 2006 to authorize CTC to allocate up to
$15 million to the highest-priority grade separation project on the
priority list established by the Commission. However, current state
regulations limit an allocation for a single project to $5 million.
When regulations do not conform to statutory law, applicants may
not be aware of changes in law and may either choose not to submit
an application or submit inconsistent applications.
Recommendations
In light of local agencies’ limited participation in the Grade
Separation Program, the Legislature should reconsider its intent for
the program and consider the extent to which it wishes to continue
assisting local agencies with their grade separation projects. Among
possible courses of action, the Legislature could:
• Discontinue the program after the proceeds from the bond
measure approved in November 2006 have been allocated
and require local agencies to compete with a broader range of
projects for funding available to them through other programs
such as the STIP.
California State Auditor Report 2007-106 2
September 2007
• Continue the program and increase the annual budget of $15 million
and allocation limits per project because it desires to continue
providing a specific source of funding focused on grade
separation projects.
To ensure that it administers the Grade Separation Program in
compliance with state regulations, Caltrans should follow state
regulations when making supplemental allocations. Further, to be
consistent with statute, it should seek to revise current regulations
to conform to recent amendments to statute.
We conducted this review under the authority vested in the California State Auditor by Section 8543
et seq. of the California Government Code and according to generally accepted government auditing
standards. We limited our review to those areas specified in the audit scope section of the report.
Respectfully submitted,
ELAINE M. HOWLE
State Auditor
Date: September 13, 2007
Staff: Denise L. Vose, CPA, Audit Principal
Kris D. Patel
Simon Jaud, Ph.D.
Erik Stokes, MBA
26 California State Auditor Report 2007-106
September 2007
Blank page inserted for reproduction purposes only.
California State Auditor Report 2007-106 27
September 2007
(Agency response provided as text only.)
Business, Transportation and Housing Agency
980 9th Street, Suite 2450
Sacramento, CA 95814-2719
September 4, 2007
Elaine M. Howle, State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Dear Ms. Howle:
Attached is a response from the Department of Transportation (Department) to your draft audit report,
Grade Separation Program: An Unchanged Program Budget and Project Allocation Levels Established More Than
Thirty Years Ago May Discourage Local Agencies From Taking Advantage of the Program (#2007-106). Thank you
for this opportunity to respond to the report.
We appreciate and agree with your conclusion that the limited financing available from the Grade
Separation Program is a major obstacle to the participation of local agencies. As for the recommendation
that the Department adhere to State regulations when making supplemental allocations, we are
pleased that the Department has already developed a check list to verify that requests for supplemental
allocations include all required documents. Furthermore, the Department is currently revising
regulations to conform with recent amendments to statute. More specifics are provided in the attached
Department response.
If you need additional information regarding this response, please do not hesitate to contact me, or
Michael Tritz, Deputy Secretary for Audits and Performance Improvement at the Business, Transportation and
Housing Agency, at (916) 324 7517.
Sincerely,
(Signed by: M. M. Berte for)
DALE E. BONNER
Secretary
Attachment
2 California State Auditor Report 2007-106
September 2007
Department of Transportation
Office of the Director
1120 N Street
P. O. Box 942873
Sacramento, CA 94273-0001
August 30, 2007
Dale E. Bonner, Secretary
Business, Transportation and Housing Agency
980 9th Street, Suite 2450
Sacramento, CA 95814
Dear Mr. Bonner:
I am pleased to provide our five-day response to the Bureau of State Audits’ (BSA) draft report entitled,
“Grade Separation Program: An Unchanged Program Budget and Project Allocation Levels Established More
Than Thirty Years Ago May Discourage Local Agencies From Taking Advantage of the Program.”
At the request of the Joint Legislative Audit Committee, the BSA conducted an audit of the funding and
approval process required for State and local transportation agencies for grade separation projects.
The BSA concluded that funding for the Grade Separation Program has not kept pace with the increased
cost of construction, causing some local agencies not to nominate potential projects. The average cost of
a grade separation project has increased considerably and the budget for the Grade Separation Program
has not changed since 1974. The BSA also found that the Department of Transportation (Caltrans) did not
always follow regulations when allocating supplemental funds and that some regulations are inconsistent
with statutes.
The BSA is recommending that the Legislature reconsider the intent of the program and the extent to which
it wishes to continue assisting local agencies with their grade separation projects. The BSA is offering the
following specific recommendation for Caltrans:
“To ensure that it administers the Grade Separation Program in compliance with state regulations,
Caltrans should follow state regulations when making supplemental allocations. Further, to
be consistent with statute, it should seek to revise current regulations to conform to recent
amendments to statute.”
Caltrans Response:
Caltrans has developed a check list to verify that requests for supplemental allocations include all of the
documentation required by the California Code of Regulations. In addition, Caltrans is in the process of
revising the current regulations to conform to recent changes in statute. Caltrans anticipates that the
regulation amendments will be scheduled in the Office of Administrative Law 2008 Rulemaking Calendar
with the Notice of Proposed Rulemaking published prior to June 2008.
California State Auditor Report 2007-106 2
September 2007
Dale E. Bonner
August 30, 2007
Page 2
Caltrans appreciates the opportunity to provide a response to the draft report. If you have any questions,
or require further information, please contact Steve Cates, Chief, Office of Rail Equipment and Track
Construction, at (916) 654-6920, or Gerald Long, External Audit Coordinator, at (916) 323-7122.
Sincerely,
(Signed by: Will Kempton)
WILL KEMPTON
Director
0 California State Auditor Report 2007-106
September 2007
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California State
Government Organization and Economy
Department of Finance
Attorney General
State Controller
State Treasurer
Legislative Analyst
Senate Office of Research
California Research Bureau
Capitol Press