Department of General Services
The Division of the State Architect Lacks Enforcement
Authority and Has Weak Oversight Procedures,
Increasing the Risk That School Construction Projects
May Be Unsafe
December 2011 Report 2011-116.1
Independent
NONPARTISAN
Accountability
TRANSPARENT
The first five copies of each California State Auditor report are free. Additional copies are $3 each, payable by
check or money order. You can obtain reports by contacting the Bureau of State Audits at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
916.445.0255 or TTY 916.445.0033
OR
This report is also available on the World Wide Web http://www.bsa.ca.gov
The California State Auditor is pleased to announce the availability of an on-line subscription service. For
information on how to subscribe, please contact the Information Technology Unit at 916.445.0255, ext. 456,
or visit our Web site at www.bsa.ca.gov.
Alternate format reports available upon request.
Permission is granted to reproduce reports.
For questions regarding the contents of this report,
please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
CALIFORNIA STATE AUDITOR
Elaine M. Howle
State Auditor
Doug Cordiner B u r e a u o f S t a t e A u d i t s
Chief Deputy
555 Capitol Mall, Suite 300 Sacramento, CA 95814 916.445.0255 916.327.0019 fax www.bsa.ca.gov
December 8, 2011 2011-116.1
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the California State Auditor presents this
audit report concerning the Department of General Services, Division of the State Architect’s
(division) oversight and certification of school construction projects.
This report concludes that the division is unable to certify that a large number of completed
school construction projects meet requirements in the Field Act, a law designed to protect
the safety of pupils, teachers, and the public. The division reports that over 16,000 projects
remain uncertified. Elements of the act hamper the division’s ability to enforce the certification
requirements. For example, the act allows school districts to occupy uncertified projects
and does not give the division the express authority to penalize school districts that do not
comply with certification requirements. Further, the division infrequently uses its authority to
stop construction of projects when it determines there is a risk to public safety. In addition,
the division lacks a clear system for classifying uncertified projects, increasing the risk that
it will miscommunicate the true risks associated with uncertified projects and that efforts to
strategically follow up on these projects will be impeded.
We also found that the division’s oversight of project construction is not effective. The division
lacks a process for planning oversight it will perform, and in some cases could not demonstrate
that it provided adequate field oversight. We found examples of projects with an estimated
cost of up to $2.2 million that had no evidence of a visit by the division’s field staff. Further,
the division relies on project inspectors to ensure that projects are constructed according to
approved plans, but these inspectors are employees or contractors of the school districts, which
increases the risk of them being improperly influenced and the division has not implemented
robust strategies to mitigate this risk. Additionally, the division is not always able to approve
project inspectors for work before the beginning of construction as the Field Act requires. Also,
the division does not complete field oversight of school construction in the areas of fire and
life safety and accessibility, raising the risk that safety issues in these areas will go uncorrected.
Finally, the division lacks performance measures that could help it to improve its field oversight
and certification efforts.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
Blank page inserted for reproduction purposes only.
Department of General Services
The Division of the State Architect Lacks Enforcement
Authority and Has Weak Oversight Procedures,
Increasing the Risk That School Construction Projects
May Be Unsafe
December 2011 Report 2011-116.1
Blank page inserted for reproduction purposes only.
California State Auditor Report 2011-116.1 vii
December 2011
Contents
Summary 1
Introduction 5
Chapter 1
A Significant Number of School Construction Projects
Remain Uncertified, in Part Because the Field Act Hampers
the Ability of the Division of the State Architect to Enforce
Certification Requirements 15
Recommendations 26
Chapter 2
The Division of the State Architect’s Oversight of the Construction
Process Is Neither Effective Nor Comprehensive 27
Recommendations 42
Response to the Audit
State and Consumer Services Agency, Department of
General Services 45
California State Auditor’s Comments on the Response
From the State and Consumer Services Agency,
Department of General Services 53
viii California State Auditor Report 2011-116.1
December 2011
Blank page inserted for reproduction purposes only.
California State Auditor Report 2011-116.1 1
December 2011
Summary
Results in Brief Audit Highlights . . .
As mandated by a state law known as the Field Act, the Division of Our review of the Department of General
the State Architect (division), part of the Department of General Services’ implementation of the Field Act
Services (department), supervises design and construction for (act), revealed the following about the
K-12 schools and community colleges. The Field Act requires the Division of the State Architect (division):
department—which delegates its responsibilities to the division—
to certify school construction projects when they comply with » While the division must certify school
requirements in the act and with the building standards in Title 24 construction projects when they comply
of the California Code of Regulations (building standards). with the act, as of December 2010
However, a significant number of the State’s school construction approximately 16,400 projects
projects remain uncertified. Twenty-three percent of the projects statewide remained uncertified.
that the division closed in the last three fiscal years remain
uncertified. Statewide, the division closed more than 2,000 projects » Statewide, 23 percent of projects
out of nearly 8,800 without certifying them during the last closed in the last three fiscal years
three fiscal years. As of December 2010 the division estimated there remain uncertified.
were approximately 16,400 uncertified projects in the State.
» The division inconsistently used its
The number of uncertified projects may be in part due to the Field authority to order districts to stop work on
Act, which hampers the division’s ability to ensure that projects projects after identifying a potential threat
comply with certification requirements. The act expressly allows to public safety.
school districts1 to occupy projects regardless of whether the
division has certified them, and it does not grant the division » The division did not effectively document
sufficient authority to penalize school districts for noncompliance. its determinations about the risk level
The act does grant the division certain limited tools it could use to of uncertified projects or to use these
encourage districts to pursue certification; however, the division has determinations to guide its approach to
used these tools infrequently and inconsistently. For example, the following up on those projects.
division has inconsistently used its authority to order districts to
stop work on projects in situations where the division has identified » The division’s level of oversight of
a potential threat to public safety. school construction processes is not
comprehensive—of 24 projects we
In addition, the division has failed to effectively document its reviewed, three did not have evidence of
determinations about the risk level of uncertified projects or to use any site visits by its field engineers and
these determinations to guide its approach to following up on those eight had evidence of only one site visit.
projects. Without well-documented decisions and a meaningful
classification system, the division risks miscommunicating the true » Although districts must submit inspectors
risks associated with uncertified projects. Moreover, by not using its for approval prior to construction, for 22
classification system to drive its follow-up efforts regarding projects of 34 projects we reviewed, the division
with outstanding issues, the division may miss an opportunity to did not approve the inspectors until after
encourage districts to address serious safety concerns. In recent construction began.
years, the division has made infrequent attempts to complete such
» The division does not provide the same
level of construction oversight for fire and
life safety and accessibility as it does for
1 The Field Act, building standards, and the division’s interpretation of regulations use terms structural safety even though it reviews
including school district, school board, and governing board of a school district to refer to local
entities with responsibilities under the act. In our report, we use the term school district(s) plans for all three disciplines.
or district(s).
2 California State Auditor Report 2011-116.1
December 2011
follow-up with school districts regarding uncertified projects.
Since 2008 it has only performed such follow-up three times and
can only speak to the success of one of those efforts.
Further, the division has not provided an effective, comprehensive
level of oversight of school construction processes. Specifically,
although the Field Act directs the division to visit sites as it
deems necessary for enforcement of the act and for the safety
of pupils, teachers, and the public, the division does not have a
process for planning the oversight it will perform for projects of
similar size and complexity. It also cannot demonstrate that it has
provided adequate or consistent field oversight. For example, we
found no evidence on file of site visits by its field engineers for
three of 24 projects we reviewed; these projects had estimated
costs of $270,000, $1.8 million, and $2.2 million. Additionally, we
found evidence of only one site visit for each of eight other projects,
three of which had estimated values over $500,000. This does not
appear to be an adequate level of oversight given that, in a recent
field pilot program, the division established criteria of a minimum
of one visit by field engineers to all sites and monthly site visits for
projects with construction activity lasting more than three months.
Because the division’s field engineers spend a limited amount of time
at each site, the division relies heavily on project inspectors—who
are employees or contractors of the school districts—to ensure that
districts build school projects according to approved plans. However,
we noted several areas of concern related to the division’s oversight
of inspectors. Specifically, the relationship between inspectors and
the entities involved in construction creates an inherent risk that
construction may not comply with approved plans. Several of the
division’s regional managers indicated to us that school districts and
contract managers sometimes interfere with the work of project
inspectors. Nonetheless, the division has not implemented robust
mitigation strategies. Moreover, in violation of regulations, school
districts often start construction on projects before the division
formally approves project inspectors. In our review of 34 projects,
we found that the division had not approved the inspectors for
22 projects until a month after the districts had begun construction.
Further, the division has sometimes excused inspectors from required
trainings, has not always ensured that all inspectors have passed the
current version of the inspector examination, and recently ceased its
formal evaluation of inspector performance.
We noted additional problems with the division’s construction
oversight process as well. Although the division reviews plans for
school construction projects in three disciplines—structural safety,
fire and life safety, and accessibility—it does not provide a similar
level of construction oversight in the latter two categories as it
does for structural safety. Without conducting regular oversight
California State Auditor Report 2011-116.1 3
December 2011
of all aspects of the construction projects, the division risks that
significant issues related to public safety may not receive the
attention they deserve. Further, the division lacks performance
measures for the construction and close-out phases of projects.
Such standards could help the division identify areas needing
improvement and then evaluate its success in making sure
these improvements are completed over time. According to the
manager of the division’s Performance Metrics Section, the division
has not developed performance measures for these phases because
it lacks data. However, we identified several statistics that the
division could use as performance measures that we believe would
enable it to better assess the adequacy of its oversight.
Recommendations
To ensure public safety and to provide public assurance that school
districts construct projects in accordance with approved plans,
the department in conjunction with the division should pursue
legislative changes to the Field Act that would prohibit occupancy
in cases in which the division has identified significant safety
concerns. Further, the Legislature should consider implementing
additional penalties for school districts that do not provide all
required documents.
To better use the enforcement tools at its disposal, the division
should continue and expand its use of both orders to comply and
stop work orders.
To ensure that it clearly justifies the reasons a project’s noted issues
merit a particular classification, the division should either modify its
current policies regarding classifying types of uncertified projects
or develop new policies, including requiring documentation of the
rationale behind project-specific classifications. It should use its
classifications to prioritize its efforts to follow up on uncertified
projects based on risk and to better inform the public regarding the
reasons it has not certified projects.
To reduce the number of uncertified projects, the division
should implement initiatives to follow up with school districts on
uncertified projects.
To ensure that it is providing adequate oversight of school
construction projects, the division should develop and document an
overall strategy that establishes specific expectations for conducting
site visits and monitoring construction. The division should then
record and compare its actual visits and monitoring efforts to its
planned actions. The division should document explanations for
any deviations from its plans.
4 California State Auditor Report 2011-116.1
December 2011
To mitigate risks arising from the relationship among inspectors,
school districts, and project managers, the division should develop
formal procedures and explicit directions for field engineers to
ensure that they establish a presence on project sites and provide
adequate oversight of inspectors during construction.
To ensure that it approves inspectors before the start of project
construction, the division should streamline its approval process by
reviewing inspectors’ workloads and past experience using the data
it already maintains.
To ensure that certified inspectors are knowledgeable about current
code requirements, the division should not excuse inspectors from
required trainings and should improve its process for identifying
expired certification exam scores.
To ensure that it formally monitors inspectors’ performances, the
division should reestablish a process for evaluating inspectors that
provides consistent documentation of performance. The division
should make this information accessible to appropriate staff.
To address areas in which its staff do not currently have expertise,
the division should finalize the results of its field pilot program
related to field oversight of accessibility-related and fire and life
safety-related issues by qualified individuals.
To better manage its construction oversight and close-out
functions, the division should develop performance measures to
assess those functions and it should periodically report the results
to the public on its Web site.
Agency Comments
The department agreed with our recommendations and outlined
steps the division will take to implement them.
California State Auditor Report 2011-116.1 5
December 2011
Introduction
Background
On March 10, 1933, a magnitude 6.3 earthquake hit Long Beach,
California. According to the Department of General Services
(department), that earthquake destroyed 70 schools and inflicted
major structural damage on another 120. The earthquake struck
when the buildings were unoccupied; otherwise, according
to the department, hundreds of children might have died. On
April 10, 1933—only one month after the earthquake—the Field
Act became law, to protect the safety of pupils, teachers, and the
public. The act requires that the department supervise the design
and construction of any school building or the reconstruction
or alteration of any school building to ensure that plans and
specifications comply with the act and the building standards
published in Title 24 of the California Code of Regulations (building
standards). Although the act exempts certain types of facilities
from some or all of its requirements, it generally mandates that the
department both approve design plans and supervise construction
to ensure that projects comply with approved plans for the
protection of life and property.2
Although the Field Act directs the department to supervise the
design and construction of school buildings, the department
delegated this authority to the Division of the State Architect
(division). The division consists of a headquarters in Sacramento
and four regional offices located in Oakland, Sacramento,
Los Angeles, and San Diego. The headquarters includes the
office of the state architect, a branch dedicated to codes and
standards, and sections or units dedicated to human resources,
inspector certification, fiscal services, contracts, training,
performance metrics, and information technology. The state
architect is appointed by the governor and heads the division; since
August 2010, an acting state architect has held this position. A
principal structural engineer, known as a regional manager, leads
each regional office and plans, organizes, and directs the plan
review and field oversight activities for that office. The regional
offices serve the counties assigned to them, as shown in Figure 1 on
the following page. For fiscal year 2011–12, the division has
345 authorized positions and a budget of $53.8 million. The division
receives its revenue from fees it charges for its services.
2 Charter schools may, but are not required to, comply with the Field Act. Private schools are
exempt from its provisions.
6 California State Auditor Report 2011-116.1
December 2011
Figure 1
Territories of the Division of the State Architect’s Regional Offices
DEL Region I - Oakland
NORTE
SISKIYOU MODOC Region II - Sacramento
Region III - Los Angeles
Region IV - San Diego
SHASTA LASSEN
HUMBOLDT TRINITY
TEHAMA
PLUMAS
GLENN BUTTE SIERRA
MENDOCINO
LAKE COLUSA S U
YUBA NEVADA
PLACER
TTE
R
YOLO EL DORADO
SONO
M
M
A
A
RIN
NAPA
C
S
O
O
N
LA
T
N
R
O
A
SACR
J
A
O
ME
S A
N
A
T
Q
O
N UIN
AMAD
CA
O
L
R AVERAS
TUO
A
L
L
U
P
M
IN
N
E
E MONO
COSTA
SAN FRANCISCO
SAN MATEO
ALA
S
M
A
E
N
D
T
A
A
STANISLAUS
MARIPOSA
CLARA MERCED MADERA
SANTA CRUZ
SAN FRESNO
BENITO INYO
TULARE
MONTEREY
KINGS
KERN
SAN LUIS OBISPO
SAN BERNARDINO
SANTA BARBARA
VENTURA
LOSANGELES
RIVERSIDE
ORANGE
SANTA CATALINA ISLAND
IMPERIAL
SAN DIEGO
SAN CLEMENTE ISLAND
Source: Division of the State Architect’s Web site.
California State Auditor Report 2011-116.1 7
December 2011
The Division’s Approval of Projects and Oversight of Construction
The division reviews and approves plans for school construction
projects, which vary widely in size and scope. For instance, a project
may include the installation of a scoreboard or the construction of a
new campus. Table 1 identifies the estimated cost of projects active
between fiscal years 2008–09 and 2010–11. The Field Act mandates
that an appropriately licensed architect or structural engineer
(design professional) prepare the drawings and specifications.
The design professional is responsible for coordinating all
consultants, observing construction, interpreting drawings and
specifications, and preparing all changes to the design plans.
Table 1
Estimated Cost of Projects Active in
Fiscal Years 2008–09 Through 2010–11
ESTIMATED COST OF PROJECTS NUMBER OF PROJECTS TOTAL ESTIMATED COST OF PROJECTS
< $100,000 4,271 $199,581,061
100,000–500,000 5,289 1,325,874,316
500,001–1,000,000 2,122 1,589,688,028
1,000,001–5,000,000 4,061 9,589,530,006
5,000,001–10,000,000 1,001 7,235,082,215
> 10,000,000 1,069 24,559,523,834
Totals 17,813 $44,499,279,460
Source: Bureau of State Audits’ analysis of data obtained from the Division of the State Architect’s
Tracker database.
The division’s plan review and approval process occurs before
any construction takes place. To initiate this process, school
districts3 must submit an application to the division, along with
the plans and specifications for the project and required fees.
Once the division verifies that the application packet is complete,
it schedules the project for plan review. Three experts review the
plans in three disciplines—structural, fire and life safety, and access.
Once they have completed their reviews and approved the plans,
the division issues a letter to inform the school district that its plans
meet pertinent code requirements. According to the Field Act,
school districts cannot contract for construction until the division
has approved their plans and specifications. Figure 2 on the
following page depicts the division’s process for ensuring that
projects comply with legal requirements.
3 The Field Act, building standards, and the division’s interpretation of regulations use terms
including school district, school board, and governing board of a school district to refer to local
entities with responsibilities under the act. In our report, we use the term school district(s)
or district(s).
8 California State Auditor Report 2011-116.1
December 2011
Figure 2
Division of the State Architect’s Process for Ensuring That Projects Comply
With Legal Requirements
PLAN REVIEW AND APPROVAL PHASE
The Division of the State Architect (division)
reviews plans for structural safety, fire and
life safety, and access compliance.
CONSTRUCTION PHASE
The contractor completes the work covered
by his or her contract according to
division-approved plans and specifications.
The design professional ensures that
completed work conforms to the
division-approved plans and specifications.
The contractor, design The project inspector is a school district
professional, and project inspector employee or contractor who continuously
sign verified reports that the work inspects construction work.
has been performed in
compliance with the approved The division field engineer (field engineer)
plans and specifications. approves the project inspector and observes
the construction process through site visits and
review of project reports and communications.
CLOSE-OUT AND CERTIFICATION PHASE
The division initiates project closing
The division initiates closeout because it receives the final report from the project
inspector, the field engineer determines that the project is essentially complete, or the district
occupies the project.
The division generates a 90-day letter
The division examines the project file to determine if any documents required for certification
are missing. The division sends a letter to the district requesting any outstanding documents
and noting any outstanding deficiencies.
The division closes the project file
When the 90-day period expires, the division reviews the file to determine whether the
pertinent parties have submitted all required documents and addressed all outstanding issues.
The division sends a close-out letter to the district, either with or without certification.
Sources: Title 24 of the California Code of Regulations, and the division’s Project Certification Guide
and Implementation of Field Supervision Procedures.
California State Auditor Report 2011-116.1 9
December 2011
As shown in Figure 3 on the following page, the two parties most
responsible for directly overseeing the construction process for the
division are field engineers and project inspectors. The division’s
field engineers are state employees who are based in one of
the division’s four regional offices. Field engineers are licensed
structural engineers with at least five years of structural engineering
experience. They review and approve any changes to plans that
school districts make during construction. They also occasionally
visit construction sites to ensure that the districts perform work
according to building code requirements and to supervise project
inspectors. Field engineers record the results of these visits in field
trip notes, copies of which the division distributes to inspectors
and field team supervisors while filing the originals in the field
engineers’ project records. The division assigns field engineers to
multiple projects—for example, one field engineer in Sacramento
was responsible for more than 75 active projects—and it
consequently does not expect them to maintain a constant presence
at each construction site.
In contrast, school districts directly employ or contract with the
project inspectors, who are also responsible to the division for
ensuring that the school districts comply with approved plans
and specifications. Building standards require that inspectors
successfully complete a division-administered certification exam
that tests their understanding of applicable codes and their
knowledge about acceptable construction practices, plan reading,
and techniques of construction and inspection. Inspectors may
renew their division certifications—which are valid for four years—
by attending training classes and passing a recertification exam.
The division approves inspectors for work on particular projects as
requested by school districts. Its approval process considers, among
other factors, an inspector’s certification status, work history,
performance on prior construction projects, and workload in the
context of the time commitment needed for the proposed project.
Like field engineers, inspectors complete tasks aimed at ensuring
that construction matches the approved plans; however, the
Field Act requires inspectors to perform continuous inspection
of construction for projects on which the division has approved
them to work. State regulations require inspectors to document the
progress of construction, including any problems or noncomplying
conditions, by submitting semimonthly reports to the division.
Additionally, inspectors are responsible for issuing written
notifications if school districts do not correct any deviations
in construction immediately after the inspector brings those
deviations to the attention of the project contractors.
10 California State Auditor Report 2011-116.1
December 2011
Figure 3
Key Players in Construction Oversight
DIVISION OF THE
SCHOOL DISTRICT
STATE ARCHITECT
(division)
Regional Manager Design Professional
Plans, organizes, and directs • Ensures that completed work conforms
field review activities to approved plans and specifications
• Provides general direction for the
project inspector
Field Supervisor
Supervises the work of staff
performing field oversight of
projects under construction
Field Engineer
•Assesses inspectors’ performance Construction Contractor
Completes the work
of code-prescribed duties
covered by his or her contract
•Visits sites to determine if work
with the school district
complies with approved plans
according to division-approved
and specifications
plans and specifications*
Project Inspector
Continuously inspects construction work
• Certified by the division • Selected by the district with the
• Approved for the project by advice of the design professional
the division • Paid by the district
• Subject to supervision by the • Directed by the design professional
field engineer
Testing Facilities and Special Inspectors
Specially qualified individuals required to
perform special inspections on aspects of
construction that either are performed away
from the construction site or require special
knowledge or expertise to inspect
Sources: State law, Title 24 of the California Code of Regulations, and the division’s Project
Certification Guide, Implementation of Field Supervision Procedures, duty statements, and
Interpretation of Regulations Manual.
* According to the acting state architect, many school districts employ construction managers
whose purpose is to ensure the project finishes on time and within budget.
The Division’s Certification of School Projects
The Field Act requires the division to certify that construction
projects are built in compliance with the law. When construction
on a project ends, the division notifies the school district about
California State Auditor Report 2011-116.1 11
December 2011
any outstanding issues that prevent the division from certifying
the project as compliant with the act and building standards.
The division sends a letter to the school district requesting that
it submit all outstanding documents within a 90-day period. The
documents in question might include the final, verified reports that
design professionals, project inspectors, and other key individuals
must submit. These reports are legally required statements, made
and signed under the penalty of perjury, that verify that the work
complies with approved plans and specifications. Additionally, the
division’s letter details any issues with project construction that
inspectors or field engineers have identified that the district must
address and resolve.
When the 90-day period has expired, the division examines
the project file to determine whether the pertinent parties have
submitted any missing documents and whether the district has
appropriately addressed any outstanding issues. Upon satisfactory
completion of construction and receipt of all required documents,
the division will certify a project. The division closes the project
without certification if, after the 90-day period, it has not received
all required documents or if the district has failed to correct
reported deviations in construction and to resolve all safety issues.
If a school district cannot obtain all of the required documents, the
Field Act permits the district to request that the division review
all of the project records and make such examinations as it deems
necessary to enable it to certify the project. Further, school districts
may request that the division reopen uncertified projects for
examination and certification at any time. However, as we discuss
in Chapter 1, the division does not have the authority to stop school
districts from occupying or using projects even if the projects
are uncertified.
Scope and Methodology
The Joint Legislative Audit Committee (audit committee) directed
the Bureau of State Audits (bureau) to review the division’s
implementation of the Field Act, which we describe in the
Introduction. The audit committee’s request divided the audit
into two phases: Phase one focuses on the division’s construction
oversight and project close-out functions, and phase two focuses
on its plan review functions. This report covers phase one of the
audit request. Table 2 on the following page outlines the audit
committee’s objectives for phase one and our methodology for
addressing each objective.
12 California State Auditor Report 2011-116.1
December 2011
Table 2
Methods of Addressing Audit Objectives
AUDIT OBJECTIVE METHODOLOGY
Review and evaluate the laws, rules, and regulations significant to the We reviewed relevant laws, rules, and regulations.
audit objectives.
Review and evaluate the management, control, and operational We reviewed laws and regulations that govern construction oversight
structure of the Division of the State Architect (division) in the areas of and project closeout, reviewed division policies and reports related
construction oversight and project closeout. to construction oversight and closeout, and interviewed division staff
responsible for construction oversight and closeout. We determined that the
management, control, and operational structure is adequate for construction
oversight and project closeout, except as we discuss in Chapter 2.
Determine the effectiveness of the division’s structure in ensuring We interviewed division staff responsible for construction oversight and
consistent compliance throughout the State with the Field Act and the reviewed a random selection of 40 project files to determine whether
fire and safety provisions of the California building code. the division appropriately implemented its project oversight and
close‑out procedures. We also assessed the extent to which projects
remain uncertified, reviewed the division’s construction oversight and
close‑out processes to identify why projects remain uncertified,
and reviewed a random selection of 21 uncertified projects to determine
whether such projects were appropriately classified on closeout. Finally,
we reviewed a draft division report on a field pilot in the Sacramento
region that expanded fire and life safety oversight during the
construction phase and we compared the expertise of the division’s plan
review staff to that of its construction oversight staff.
Review and evaluate performance measures used by the division to We interviewed the division’s Performance Metrics Section manager.
measure effectiveness in performing construction oversight and project
close‑out functions.
To the extent possible, determine whether performance measures As discussed in Chapter 2, the division does not have performance
used by the division are consistent with standards or best practices measures for the construction oversight and project close‑out phases.
established in the construction planning and oversight community.
Review and evaluate the methods used by the division to determine We interviewed division staff about the methods used to determine staffing
appropriate staffing levels and to ensure that staff possess the levels and reviewed the last division document that estimated needed
knowledge, skills, and abilities required to perform construction staffing levels. We also compared the minimum qualifications for division
oversight and project close‑out functions. staff to duty statements to assess whether these requirements match the
functions of the positions. Further, we reviewed training requirements and
classes offered by the division.
Determine if staff shortages have occurred in the construction oversight We compared the division’s actual staffing levels to positions authorized
and/or project close‑out functions and how they were addressed. in the budget. We also reviewed a division action plan that shifted
Further, determine the extent to which staff performing construction some staff time at regional offices to plan review and a memorandum
oversight and project close‑out functions have been shifted to other of understanding between the division and another division of the
functions within the division, and assess the reasonableness of the department intended to backfill the shifted time. We estimated
criteria used by the division to determine if those staff had the requisite the impact of these actions on the time devoted to construction
knowledge, skill, and ability to perform such other functions. oversight, and interviewed division staff about their view of the effect of
these actions on construction oversight. For staff shifted to plan review
and those used to backfill, we compared their position descriptions
to the new tasks required of them and found that they were aligned
and appropriate.
Determine whether, and to what extent, the division uses contractors to We interviewed division staff responsible for contracting and determined
perform construction oversight and project close‑out functions. that the division uses contractors primarily for plan review. We will assess
plan review‑related contracting in phase two of this audit.*
Review and evaluate division processes used to ensure the competency of We will assess the processes the division uses to ensure the competence
contractors used in construction oversight and project close‑out functions. of plan review contractors in phase two of this audit.*
Review and evaluate the ongoing training requirements for division staff We interviewed staff responsible for the division’s staff training program
and contractors used in construction oversight and project close‑out and reviewed associated records. We will review training requirements
functions. Determine what division processes ensure that staff and for contractors during phase two of this audit.*
contractors meet these training requirements.
California State Auditor Report 2011-116.1 13
December 2011
AUDIT OBJECTIVE METHODOLOGY
Determine and assess the adequacy of the processes the division uses to We interviewed supervisors regarding staff performance evaluations,
monitor staff and contractor performance and to take appropriate action reviewed the division’s processes for conducting staff evaluations, and
when necessary. reviewed evaluations for a selection of staff at each regional office. We
determined that staff received evaluations as required. We will review the
monitoring of contractor performance in phase two of this audit.*
Review and evaluate the procedures used by the division to ensure that We reviewed the division’s procedures for resolving deficiencies during
building safety violations are corrected prior to pupil occupancy. the construction and close‑out phases, reviewed a random selection of
projects with identified deficiencies that closed without certifications,
and interviewed division staff.
Determine if the division has a backlog in construction oversight or We calculated the number of projects at June 30, 2011, where
project close‑out functions. If there is a backlog, determine how the construction had been completed for at least six months but the division
division is addressing the backlog in the short term and long term. had not sent 90‑day letters (described earlier) and closed the projects.
Determine if there are significant statutory, regulatory, or other We reviewed the Field Act and related regulations and interviewed
impediments to the timely and judicious completion of the division’s division staff to obtain their opinion on legal or regulatory barriers.
seismic safety responsibilities under the Field Act.
Review and assess any other issues that are significant to the division’s Because inspectors play an important role in construction oversight, we
construction oversight and project close‑out functions. interviewed division staff regarding inspector certification, reviewed
the division’s inspector certification process, and examined a random
selection of 29 certified inspectors† to assess whether the division
implemented its procedures. We also interviewed regional office
managers regarding inspector performance evaluations and reviewed
the division’s process for conducting inspector evaluations.
* The division contracts for plan review services. While the division may use these contractors to review changes to plans during construction, the
primary purpose of these contracts is plan review. Therefore, we will evaluate the competency of contractors in the second phase of this audit.
† Because the division did not comply with its record retention policy and maintain inspector certification records for all active inspectors, we were
unable to verify the completeness of the division’s entire active inspector list and only randomly selected inspectors whose most recent certification
record still existed: inspectors who recertified since January 2007 and all inspectors who were certified for the first time or who upgraded their
certification since January 2008.
To support its work, the division uses a database called
Tracker (database), which it developed in 1997 to manage the
projects submitted by school districts. This database tracks project
applications, key dates (such as plan approval and construction start
and end dates), the inspectors assigned to projects, and the types of
project closure. The database also generates invoices and calculates
the various fees owed to the division for certain aspects of its work.
The database links to scanned copies of documents, when available.
To address several of the audit committee’s objectives, we
relied on data the division provided. The U.S. Government
Accountability Office, whose standards we follow, requires us to
assess the sufficiency and appropriateness of computer-processed
information. To comply with this standard, we assessed the
reliability of the division’s database for the purpose of identifying
the number and estimated cost of projects that were in the
construction oversight or project close-out phases in fiscal
years 2008–09 through 2010–11. We also assessed its reliability
for determining which projects within this universe had received
close-out letters and the amount of time between construction
completion and June 30, 2011, for projects that had not begun the
close-out process as of that date.
14 California State Auditor Report 2011-116.1
December 2011
To assess the reliability of the division’s data, we reviewed
documentation and interviewed appropriate division staff. In
addition, we performed data-set verification procedures and
electronic testing of key data elements. We also tested the
completeness and accuracy of the data by tracing random selections
of records to and from supporting documentation. Our review of
existing information identified two data limitations. The division’s
database does not track information on any projects submitted
to the division before November 1997. Further, the database does
not track if projects reopen regardless of whether the project
was initially recorded in the database. Because some projects are
required to pay a fee when they reopen, we were able to identify
a portion of the reopened projects using the fee information.
The reopened projects we identified, although incomplete, were
included in our analysis.
We identified no issues when performing data-set verification
procedures, but found minor errors in our electronic testing,
some of which we were able to correct. Further, we tested the
completeness of the database by selecting 29 projects from regional
files and verifying that these projects existed in the database; we
found no errors in this testing. We also tested the accuracy of
the database by testing key data elements for a random sample
of 29 projects and tracing the selected elements to the project files.
In this sample, we found one error, so we continued testing until
we had tested a total of 47 randomly selected projects and found
no additional errors. However, because the division did not have a
consistent method for identifying the date construction ended, we
were unable to test the accuracy of this field.
Based on our testing and the known limitations of the data, we
determined the division’s Tracker data to be of undetermined
reliability for identifying the number and estimated cost of projects
that were in the construction oversight or project close-out phases
in fiscal years 2008–09 through 2010–11, identifying which projects
received close-out letters, and determining the amount of time
between construction completion and June 30, 2011, for projects
which had not yet begun the close-out process as of that date.
California State Auditor Report 2011-116.1 15
December 2011
Chapter 1
A SIGNIFICANT NUMBER OF SCHOOL CONSTRUCTION
PROJECTS REMAIN UNCERTIFIED, IN PART BECAUSE
THE FIELD ACT HAMPERS THE ABILITY OF THE DIVISION
OF THE STATE ARCHITECT TO ENFORCE CERTIFICATION
REQUIREMENTS
As discussed in the Introduction, the Division of the State
Architect (division) is responsible for overseeing most construction
projects at K-12 schools and community colleges to certify that
these projects comply with the requirements of the Field Act
and the building standards in Title 24 of the California Code of
Regulations (building standards). However, a significant number
of the state’s closed school construction projects remain uncertified.
Statewide, the division closed more than 2,000 projects out of
nearly 8,800 without certification during the last three fiscal years.
This large number of uncertified projects is in part because the
division’s ability to ensure that projects comply with certification
requirements is hampered by the Field Act, which allows school
districts4 to occupy projects regardless of whether the division
has certified them and which grants the division little authority to
penalize school districts for noncompliance.
Despite the limitations the Field Act places on it, the division
could take steps to attempt to increase the number of projects it
certifies and to mitigate the risks that uncertified projects may
pose. However, it has not consistently chosen to do so. Although
the act grants the division some tools it could use to encourage
compliance, the division uses them infrequently and inconsistently.
In particular, the division has the ability to order that districts stop
work on a project when it identifies a potential threat to public
safety; however, it has not consistently used this authority.
Moreover, the division has not effectively documented its
determinations about the risk level of uncertified projects, nor has
it used its risk-level classifications to guide its approach to following
up on uncertified projects. Without well-documented decisions
and a classification system that impacts operations, the division
risks miscommunicating the true risks associated with uncertified
projects and clouding efforts it might make to follow up on projects
with serious outstanding issues. In fact, since 2008, the division has
only followed up three times on projects that remained uncertified
and it can only speak to the success of one of those efforts.
4 The Field Act, building standards, and the division’s interpretation of regulations use terms
including school district, school board, and governing board of a school district to refer to local
entities with responsibilities under the act. In our report, we use the term school district(s)
or district(s).
16 California State Auditor Report 2011-116.1
December 2011
Elements of the Field Act Make it Difficult for the Division to
Ensure That All School Construction Projects Comply with
Certification Requirements
The Field Act establishes certification as a mechanism to ensure
that school districts construct projects according to approved plans
and that key individuals document required processes and controls.
However, the division closed a substantial proportion of projects in the
past three fiscal years without certification. As Table 3 demonstrates,
the division was unable to certify 23 percent of approximately
8,800 projects that it closed during fiscal years 2008–09 through 2010–11,
or more than 2,000 projects. In addition, the division’s tracking reports
indicate that an accumulated total of nearly 16,400 closed projects
with a total estimated cost of over $17.6 billion remained uncertified as
of December 2010.
Table 3
Status of Projects the Division of the State Architect Closed
Between July 1, 2008, and June 30, 2011,
by Region and Fiscal Year
FISCAL YEAR FISCAL YEAR FISCAL YEAR
2008–09 2009–10 2010–11 TOTALS
Statewide
Certified 2,251 2,002 2,475 6,728
Uncertified 575 651 812 2,038
Total closed 2,826 2,653 3,287 8,766
Percent of projects closed
that were uncertified 20% 25% 25% 23%
Oakland
Certified 584 400 611 1,595
Uncertified 182 89 166 437
Total closed 766 489 777 2,032
Percent of projects closed
that were uncertified 24% 18% 21% 22%
Sacramento
Certified 619 586 623 1,828
Uncertified 124 149 204 477
Total closed 743 735 827 2,305
Percent of projects closed
that were uncertified 17% 20% 25% 21%
Los Angeles
Certified 473 457 569 1,499
Uncertified 114 338 291 743
Total closed 587 795 860 2,242
Percent of projects closed
that were uncertified 19% 43% 34% 33%
San Diego
Certified 575 559 672 1,806
Uncertified 155 75 151 381
Total closed 730 634 823 2,187
Percent of projects closed
that were uncertified 21% 12% 18% 17%
Source: Bureau of State Audits’ analysis of data obtained from the Division of the State Architect’s (division) Tracker database.
Note: This table excludes projects that the division closed because school districts cancelled them.
California State Auditor Report 2011-116.1 17
December 2011
The Field Act allows school districts to occupy projects regardless of
whether the division has certified them. According to the act,
“nothing . . . shall prevent beneficial occupancy by a school district
prior to the issuance of . . . certification.” This means that the division
cannot deny a school district the ability to use a project, even if the
division is aware of a serious issue preventing certification. For
example, in the division’s records for one project we reviewed, the
division noted that the district did not install a required fire hydrant for
a multipurpose building by the end of construction in August 2007.
The district nevertheless began using the building at that time.
According to the records, the field engineer responsible for oversight of
the project did not receive confirmation from the district that it had
installed the hydrant until December 2009, after the division’s repeated
communications about this issue. This means that the district may have
used the building for nearly two and a half years without the
installation of the required hydrant. In another instance, a school
district constructed bleachers inside an athletic center in 2004 without
using an inspector. According to division records, an after-the-fact
inspection of the project in 2008 showed that the district had not
completed planned work on a fire alarm, and as of September 2011, the
division still noted this issue as outstanding. Despite
this incomplete work, the district put this project to
Documents the Division of the State Architect
use seven years ago.
Requires for Certification
The Field Act grants the division certain limited
• Notice of Completion*—Includes the date
tools it can use during construction to ensure that
of completion and the signature of the
districts complete projects without deviating from district representative.
approved plans, which we discuss in greater detail in
• Final Verified Reports*—Includes attestations
the next section. However, certification also requires
from the inspector, design professional, and
documentation of processes and controls established
contractor that construction does or does not
in the act. This documentation, such as final verified
comply with division-approved plans. The division
reports from key individuals, provides additional
may also require reports from special inspectors,
assurance that districts have constructed projects in such as masonry inspectors, depending on
accordance with the approved plans. The text box project specifications.
shows the documents that the division requires before
• Testing and Inspection Documents—Includes
it certifies projects. Despite the importance of these
laboratory-verified reports of material tests and
documents, the act does not provide the division with
verified reports from geotechnical engineers.
express statutory authority to penalize districts that do
• Application†—Includes the names of the design
not provide them, aside from authorizing the denial
professional(s) whom the division will require to sign
of certification.
verified reports.
Though various parties are responsible for different • Contract Information Form—Includes information
aspects of these certification requirements, school about contractors on the project.
districts are ultimately responsible for obtaining
Source: The division’s Project Certification Guide.
certification of projects. According to regulations * The pertinent parties cannot submit these documents
and the Field Act, school districts initiate the until the district completes construction.
process of project plan approval, employ project † The district submits an application prior to plan review
and approval.
inspectors, and receive letters of certification
from the division. The act even provides districts
18 California State Auditor Report 2011-116.1
December 2011
with the ability to pursue certification if other responsible parties
fail to submit final verified reports to the division. Without the
authority to penalize districts for not complying with certification
requirements by denying them the ability to use facilities or by
imposing monetary penalties, the division has little leverage to
ensure that projects meet certification requirements and are safe for
public use.
The Division Rarely Exercises Its Authority to Stop Work on Projects
That Do Not Comply With State Law
Although the division’s enforcement Although the division’s enforcement authority is limited, it does
authority is limited, the division have the ability to block new projects from moving forward if
may be less effective in correcting they are associated with existing uncertified projects or to stop
identified safety concerns before work on a project if the division identifies safety concerns during
districts complete construction and the construction process. According to division staff, the division
occupy school facilities by not fully regularly uses the first of these tools; however, our review indicated
taking advantage of the authority it rarely uses the second. By not fully taking advantage of the
state law does grant it. authority state law grants it, the division may be less effective in
correcting identified safety concerns before districts complete
construction and occupy school facilities.
As part of its process for approving new projects, the division
usually requires the certification of associated, previously
uncertified projects. According to the division’s interpretation of
regulations, it may deny approval to a new construction project if
the new project is connected to a previously uncertified project,
unless the new project is solely for the purpose of upgrading fire
and life safety aspects of a building. When design professionals
submit plans for approval to the division, they must identify any
previous construction projects that are associated with the plans.
The division investigates these previous projects and requires
school districts to complete certification of uncertified projects
before it grants plan approval for new projects. According to the
acting state architect, the division’s authority to deny approval
to new projects is the main reason that school districts take the
actions necessary to gain certification of previously uncertified
projects. However, the division cannot quantify the impact this
policy has on reducing the number of uncertified projects because
it does not separately track projects it has certified as a result of
this approach.
A workgroup composed of representatives of school districts, the
division, other state agencies, and construction industry
stakeholders released a review of public school construction in
October 2010. This workgroup report noted three priority issues,
one of which was new projects being held up because of past
uncertified projects. The review suggested a number of solutions
California State Auditor Report 2011-116.1 19
December 2011
including that the division not block new projects that are limited
in scope to resolving health and safety issues. According to the
acting state architect, the division is considering revisions to its
interpretation of regulations that outline its blocking policy.
Nevertheless, as the division asserts that the blocking policy is an
effective policy for encouraging districts to pursue certification, it
should ensure that any modifications to the policy do not weaken
its enforcement powers.
The Field Act also gives the division the authority
to issue orders to stop work on projects when
districts are not performing construction in Examples of circumstances under which
accordance with building standards, and thus are the Division of the State Architect may stop
compromising the structural integrity of buildings construction on a project:
and putting public safety at risk. According to
• A district undertakes construction without division
the division’s interpretation of regulations, it can
approval of plans and specifications.
issue either an order to comply, which informs a
district that the division may order construction • The construction work is defective.
to stop on a project unless the district resolves • A district uses unapproved or noncomplying materials.
identified problems, or a stop work order, which
• Construction does not meet building codes
shuts down construction until the district resolves
or standards.
the problems. The text box describes examples
of situations in which the division may order a • A district does not perform required tests
district to stop work on a project. Depending on or inspections.
the circumstances, the division may issue an order • Other circumstances occur that the division determines
to comply before issuing a stop work order or it could endanger public safety.
may simply issue the stop work order. However,
Source: The division’s Interpretation of Regulations Manual.
once the district completes construction, the
division cannot use either of these means to resolve
identified deficiencies.
Although the division has the authority to issue orders to comply
and to stop work, it has rarely used these tools. According to
records provided by the regional managers, the division issued
only 23 orders to comply and six stop work orders during the
last three fiscal years. Of the 23 orders to comply, 14 were related
to situations in which districts moved forward on construction
without division-approved inspectors. The remaining nine orders
to comply were related to circumstances in which districts
undertook construction without division-approved plans or after
changing their plans without approval. None of the stop work
orders were due to construction deficiencies. The division issued all
six stop work orders to districts that started construction without
division-approved plans. In each instance, division records indicate
that the school districts resolved identified issues.
The ability to stop construction on a project provides the division
with a useful tool to enforce compliance with the Field Act.
However, the division is not taking full advantage of that tool.
20 California State Auditor Report 2011-116.1
December 2011
We found that on 22 of For example, we found that on 22 of 34 projects we reviewed,
34 projects we reviewed, the division had not yet approved inspectors a month after the
the division had not yet districts had started construction. Yet the division did not issue an
approved inspectors a order to comply or a stop work order for any of these projects. As
month after the districts had further discussed in Chapter 2, the division cannot demonstrate
started construction. that it is providing adequate oversight of construction projects.
With improved oversight, the division could more readily identify
circumstances warranting the use of such orders.
If the division does not stop work on projects in a timely fashion,
it risks that construction will not adhere to approved plans and
thus not be certifiable. According to the acting state architect, the
division usually informally resolves situations that could warrant
the issuance of one of the described orders so that it can maintain
good collaborative relationships with the school districts. Regional
managers further indicate that division staff usually give school
districts the opportunity to correct noncompliant situations
voluntarily before issuing these orders and that the issuance of these
orders usually indicates that the division’s working relationship with
a district is strained. Nevertheless, the large number of uncertified
projects strongly suggests the division should make broader use of
these tools.
The Division Lacks a Consistent, Transparent Process for Identifying
and Addressing Uncertified Projects That May Pose Safety Risks
The division may deny certification for a wide variety of reasons.
In our testing, we observed that these reasons ranged from a lack
of required reports to construction problems that might put the
public at risk. The division recently undertook efforts to ensure
consistency in its process for distinguishing between projects with
and without identified outstanding potential safety issues. However,
when it classifies uncertified projects as having safety issues, the
division does not document the basis for its decisions. Moreover,
it does not use these classifications to prioritize actions related to
projects with safety concerns.
As discussed in the Introduction, when it closes a project, the
division issues a letter to a school district stating whether it can or
cannot certify that project. As shown in Table 4, there are four types
of closure letters. The division classifies uncertified projects into
two categories: type three projects and type four projects. However,
the division’s statewide implementation of its classification system
has not always been consistent. According to the acting state
architect, when media attention focused on uncertified projects
in late 2009, the division became aware that the four regions
were not consistently categorizing projects. After discussion
among the regional managers, the division issued a new definition
California State Auditor Report 2011-116.1 21
December 2011
of the type of problems that would cause projects to merit a
type four classification. Specifically, it revised its policy to state
that type four projects are those for which the division has evidence
of unresolved safety deficiencies related to construction. An
internal memo to division staff dated July 2010 further defined the
type four classification, including only examples involving situations
that could potentially cause injury or death.
Table 4
Conditions for Issuing Different Types of Project Closure Letters
TYPE OF CLOSURE CERTIFICATION
LETTER STATUS LETTER IS ISSUED WHEN…
• The Division of the State Architect (division) has received all
required documents.
Type One Certified
• The school district has completed construction in compliance
with the requirements of the Field Act.
• The school district has requested that the division certify a
project using alternative documents or procedures due to
the incapacitating illness, death, or default of an individual
Type Two Certified responsible for filing final verified reports.
• The division has determined that the school district has
completed construction in compliance with the requirements of
the Field Act.
• The pertinent parties have not submitted or properly
completed required documents, OR
• There is a reported and unresolved deviation during
Type Three Uncertified
construction, including unconstructed elements of a project
that were required, OR
• The school district has not paid all required fees to the division.
• The division, the project inspector, or the design professional
Type Four Uncertified has noted a safety issue that remains unresolved.
• Conditions noted for type three may also be present.
Source: The division’s Project Certification Guide.
According to the acting state architect, the division’s regional field
staff subsequently reviewed all existing type four projects in their
regions to ensure that they were aligned with the new definition. He
explained that the regional managers reclassified as type three those
projects that they thought no longer met the definition of a type
four project. Type three projects are still uncertified but do not have
identified safety concerns according to the division’s classification
system. The acting state architect said that the division also
implemented a new process for making type four determinations
after its reevaluation effort. A regional manager now receives a
recommendation from the field engineer assigned to a project
and the regional manager must give final approval for a type
four classification.
22 California State Auditor Report 2011-116.1
December 2011
We noted a number of problems We noted a number of problems with the division’s implementation
with the division’s implementation of its classification system. Specifically, although the division
of its classification system, documents any problems that prevent certification in the project
including that it does not document record, according to the acting state architect, the division does
the rationale for classifying a not document the rationale for classifying a project as type
project as type four rather than four rather than type three. This makes it difficult to distinguish
type three. between some type threes and type fours. For instance, we
reviewed 22 uncertified projects and noted projects that appeared
to have similar deficiencies that the division had categorized
differently. For example, the records for one project that the division
identified as type four noted that the district had given the project
inspector drawings that the division had not approved and for
which the design professional on the project had not assessed
the path of travel.5 However, the division categorized two other
projects with similar issues as type three. In one of those projects,
a district had not completed a curb ramp on a project.6 In the
other, a district constructed a project without approved plans or
approved inspectors. Because the division did not provide any
justification for why similar problems would sometimes trigger
type four designations and sometimes type three designations, the
meaningfulness of its classification process appears questionable.
Despite the effort the division put into reclassifying projects
after media attention focused on the large number of uncertified
projects, it does not give much weight to the type four designation.
The acting state architect said that the type four designation is not
tangible evidence of safety concerns and that type three projects are
not necessarily any less dangerous than type four projects.
Further, he elaborated that the division notifies a school district
only of a “potential” safety concern when it classifies a project
as a type four because the division has not always verified in the
field that problems exist. Further, in e-mail correspondence with
the Department of General Services, the division’s policy deputy
stated that the issues that remain outstanding with type four
projects do not rise to a level of significance that would warrant
immediate concern. The acting state architect stated that the
current classification system does not accurately capture the relative
level of risk of a project’s deficiencies and therefore should not be
used to notify the public about safety concerns. These statements
appear to contradict the definition of type four projects that
the division provided in the certification guide and an internal
memo dated July 2010 that guides division staff in making
classification decisions.
5 The building standards define a path of travel as a continuous, unobstructed way of passage for
pedestrians and/or wheelchair users.
6 The building standards define a curb ramp as a potential component of a path of travel, intended
for pedestrian traffic.
California State Auditor Report 2011-116.1 23
December 2011
Moreover, the division does not use the type four designation
to guide its monitoring or follow-up of projects. According to
the acting state architect, the division treats type four projects
essentially the same way it does type three projects. In either case,
when the division closes a project without certification, it completes
little to no additional follow-up work, as we discuss further in
the next section. The acting state architect also reported that the
division has not explicitly considered notifying the public about
the projects it has classified as type four.
The existence of a classification system that identifies projects with The existence of a classification
deficiencies that could cause serious injury or death suggests that system that identifies projects
the division is aware that such projects may exist. Yet its statements with deficiencies that could cause
regarding type four projects and its lack of action regarding these serious injury or death suggests
projects demonstrate that the division lacks concern about them. By that the division is aware that such
maintaining a system that purports to identify safety concerns but projects may exist but its lack of
does not document the reasoning behind classification decisions action regarding these projects
or affect follow-up activities, the division may miscommunicate demonstrates that the division lacks
the risks associated with uncertified projects and impede concern about them.
efforts it might make to follow up on projects with serious
outstanding issues.
The Division Has Infrequently Attempted to Persuade School Districts
to Pursue Certification of Closed Projects
Although the division faces a limited set of options to persuade
school districts to comply with the Field Act, it can remind districts
of their responsibilities regarding uncertified projects. However,
once the division notifies districts that it has closed projects
without certification, it does not regularly communicate with them
about those projects. The division informed us of three statewide
efforts since 2008 to contact districts to encourage them to pursue
certification. First, in 2008, the division sent a form letter to school
district superintendents to remind them of the importance of
Field Act certification. According to the acting state architect, the
division sent this letter to all K-12 and community college school
districts and did not include information on specific uncertified
projects. Second, according to the division’s performance metrics
manager, in early 2010 the division sent letters related to all projects
that its records showed were closed and uncertified. By offering a
reduced reopening fee, this effort encouraged districts to respond
to the division. However, according to the performance metrics
manager, the division did not measure the response to this letter.
Third, the division sent another letter to select districts in April 2011
related to 98 projects the division had identified as having been
closed as category fours. These letters contained project-specific
24 California State Auditor Report 2011-116.1
December 2011
details and encouraged the districts to contact the division to
reopen these projects. As of October 2011 the acting state architect
said that the division has been able to clear 10 of the 98 projects.
Because the division does not Because the division does not believe it has a responsibility beyond
believe it has a responsibility issuing closure letters to districts, it has not adopted a statewide
beyond issuing closure letters policy for any additional follow-up. According to the acting state
to districts, it has not adopted architect, once the division sends closure letters to school districts,
a statewide policy for any the division has fulfilled its obligation and school districts are
additional follow-up. responsible for taking the next step. Each of the four regions offered
its own perspective on following up on uncertified projects: The
regional managers from the Sacramento and Oakland regions
stated that they do not follow up with districts because of limited
resources, the San Diego regional manager stated that his office
does not follow up because the division has no formal follow-up
policy, and the Los Angeles regional manager stated that his
office will occasionally remind two large districts that they have
outstanding type four projects and will less frequently contact
others about uncertified projects.
Nevertheless, the acting state architect provided us with a business
plan that the division drafted in partnership with the department
to increase its efforts to follow up on uncertified projects. The plan
details objectives the division will address with a target completion
date of June 30, 2012. According to the business plan, the division
plans to categorize all projects uncertified as of January 2011 by size,
complexity, and district. The business plan notes that identifying
uncertified projects in this manner will allow the division to
effectively use its resources to meet its certification workload.
According to the acting state architect, identifying the projects’
size and complexity will allow the division to prioritize larger and
more complex projects in future follow-up work. He also stated that
the division had considered implementing a repeating notification
system that would regularly remind school districts of their
uncertified projects. However, the business plan does not require
the division to actually contact school districts regarding uncertified
projects. Unless the division takes more proactive steps to address
uncertified projects, including contacting school districts, the
division is likely to continue to be unable to provide assurance to
the public that these projects meet state requirements and thus
are safe.
The Los Angeles Region Had a High Rate of Uncertified Projects
Compared to the other regions, the Los Angeles region has recently
had a significantly higher rate of projects closed without certification.
During the last three fiscal years, 33 percent of projects the division
closed in the Los Angeles region were uncertified, compared to
California State Auditor Report 2011-116.1 25
December 2011
22 percent or less at each of the other regions. Part of the discrepancy
between regions may be due to the Los Angeles region’s size and
staffing levels. As shown in Table 5, the Los Angeles region is the
largest, according to several measures. In fact, the Los Angeles
region represents nearly one-third of the state’s population and
one-third of its K-12 students. Further, the Los Angeles regional
office had a higher number of projects active in fiscal years 2008–09
through 2010–11 than any of the other offices. However, with 14 staff
focused on oversight and project close-out activities, the Los Angeles
regional office has about the same number of authorized staff as each
of the other regional offices.
Table 5
Division of the State Architect’s Population Served and Estimated Value of Active Projects, by Regional Office
REGION
LOS ANGELES OAKLAND SACRAMENTO SAN DIEGO TOTALS
Population 11.9 8.1 6.8 10.5 37.3
Percent of total population 32.05% 21.62% 18.13% 28.20% 100.00%
Total 2010–11 K‑12 enrollment 2.0 1.1 1.2 1.9 6.2
Percent of enrollment 31.79% 18.05% 19.93% 30.23% 100.00%
Total number of projects active,
fiscal years 2008–09 through 2010–11 5,557 4,146 3,529 4,581 17,813
Percent of all active projects 31.20% 23.28% 19.81% 25.72% 100.00%
Total estimated cost of active projects,
fiscal years 2008–09 through 2010–11 $14.0 $9.3 $7.8 $13.3 $44.5
Percent of total estimated cost 31.66% 20.79% 17.60% 29.94% 100.00%
Sources: U.S. Census Bureau, 2010 Census data; the California Department of Education’s DataQuest Enrollment Report; and the Bureau of State
Audits’ analysis of data obtained from the Division of the State Architect’s Tracker database.
Additionally, as previously depicted in Table 3 on page 16, the
Los Angeles region experienced a large increase in the number of
uncertified projects closed, from 114 in fiscal year 2008–09 to 338 in
fiscal year 2009–10. According to the interim regional manager,7
the increase resulted from a statewide effort to close projects,
during which the Los Angeles region discovered many cases for
which it had not sent 90-day notifications when they were due. In
other words, the region had a pool of projects that it should have
already closed.
7 According to the division’s operations branch deputy, the San Diego regional manager was
also the interim regional manager for the Los Angeles region at the time he communicated this
information to us.
SNOILLIM
NI
SNOILLIB
NI
26 California State Auditor Report 2011-116.1
December 2011
Recommendations
To ensure public safety and provide public assurance that
school districts construct projects in accordance with approved
plans, the department, in conjunction with the division, should
pursue legislative changes to the Field Act that would prohibit
occupancy in cases in which the division has identified significant
safety concerns. Further, the Legislature should consider
implementing additional penalties for school districts that do not
provide all required documents.
To better use the enforcement tools at its disposal, the division
should continue and expand its use of both orders to comply and
stop work orders, as defined in its regulations. The division should
also develop performance measures to assess the success of any
efforts it makes to address safety concerns and reduce the number
of uncertified projects.
To ensure that it clearly justifies the reasons a project’s noted issues
merit a particular classification, the division should either modify its
current policies regarding classifying types of uncertified projects
or develop new policies, including requiring documentation of the
rationale behind project-specific classifications. It should use its
classifications to prioritize its efforts to follow up on uncertified
projects based on risk and to better inform the public regarding the
reasons it has not certified projects.
To reduce the number of uncertified projects, the division
should implement initiatives to follow up with school districts on
uncertified projects. Those initiatives should include, at a minimum,
regularly sending each district a list of its uncertified projects and
assessing the success of the division’s follow-up efforts.
California State Auditor Report 2011-116.1 27
December 2011
Chapter 2
THE DIVISION OF THE STATE ARCHITECT’S OVERSIGHT
OF THE CONSTRUCTION PROCESS IS NEITHER EFFECTIVE
NOR COMPREHENSIVE
The Division of the State Architect (division) has not provided an
effective, comprehensive level of oversight of school construction
processes. Specifically, although the Field Act directs the division to
visit sites as it deems necessary for enforcement of the act and for the
safety of pupils, teachers, and the public, the division does not have a
process for planning the oversight it will perform for projects of similar
size and complexity and cannot demonstrate that it has provided
adequate field oversight. For example, three of 24 closed projects we
reviewed did not have any evidence of a site visit on file; one of these
closed projects had an estimated cost of $2.2 million. Additionally,
another eight closed projects had evidence of only one site visit each.
Moreover, although the division relies on project inspectors
who are paid by school districts8 to ensure that districts build
projects according to approved plans, we noted several areas of
concern related to the division’s oversight of inspectors. Although
the relationship between inspectors and entities involved in
construction creates an inherent risk that projects may not comply
with approved plans, the division has not implemented robust
mitigation strategies. Additionally, in violation of regulations,
school districts often start construction on projects before the
division formally approves project inspectors. Further, the division
has sometimes excused inspectors from required trainings, has
not ensured that all inspectors have passed the most current
version of the inspector exam, and recently ceased its formal
evaluation of inspector performance.
We noted other problems with the division’s construction
oversight process as well. Although the division reviews plans
for school construction projects in three disciplines—structural
safety, fire and life safety, and accessibility—it does not provide
construction oversight in the last two of these disciplines. Further,
it lacks performance measures it could use to gauge the success of
its oversight of the construction and close-out phases of projects.
The division’s inability to provide effective oversight of school
construction processes may be in part the result of staffing
challenges; however, it was not possible to determine the extent
of this problem because the division has not recently performed
8 The Field Act, building standards, and the division’s interpretation of regulations use terms
including school district, school board, and governing board of a school district to refer to local
entities with responsibilities under the act. In our report, we use the term school district(s)
or district(s).
28 California State Auditor Report 2011-116.1
December 2011
an assessment of its staffing needs. Without assurance that it is
conducting regular, comprehensive oversight of construction
projects, the division cannot be certain that all of the projects it
oversees meet the requirements of the Field Act and are safe.
The Division Lacks a Formal Policy for Planning Field Visits, and Its
Processes for Documenting Its Oversight Are Weak
Many of the required inspector reports were missing from the
project files we reviewed. State regulations require that project
inspectors submit semimonthly reports to the division. These
reports, which detail a project’s status as well as problems or
noncompliant conditions, serve as evidence that the inspector has
provided continuous inspection. Failure to submit timely reports is
one cause for the division to withdraw its approval of an inspector.
Although its policy requires field engineers to review inspectors’
semimonthly reports, the division does not have a procedure
for ensuring that field engineers receive all required reports.
Consequently, we found that many inspector reports were missing.
For example, five of 34 projects we reviewed that the division had
noted as having started construction had no semimonthly reports
on file even though construction on each had lasted between
two and 21 months. For another 17 of these projects, at least one of
the inspector reports—which are numbered sequentially—was
In total, 95 of the 384 required missing. In total, 95 of the 384 required semimonthly reports
semimonthly reports were missing were missing from the project files we reviewed. Without receiving
from the project files we reviewed. these reports, the division has less assurance that project inspectors
are providing the continuous inspection the Field Act mandates.
In addition to monitoring inspector reports, the Field Act directs
the division to visit school construction project sites as it deems
necessary for enforcement of the act and the safety of pupils,
teachers, and the public. As described in the Introduction,
projects can range in scope from simple alterations to the complex
construction of an entire school campus. The division relies heavily
on project inspectors—school district employees or contractors—
to ensure that these diverse projects comply with approved plans.
As its means of overseeing this important activity, the division
uses periodic contact from its own field engineers to ensure that
inspectors are properly performing their prescribed duties. Given
these circumstances, we expected that the division would have
a well-defined process for determining how many times field
engineers should visit a particular project and a mechanism for
ensuring that these visits actually occur.
However, we found that the division does not have a process
for planning the oversight it will perform for projects of similar
size and complexity. Division policy requires field engineers to
California State Auditor Report 2011-116.1 29
December 2011
visit project sites at critical points during construction and to
avoid arbitrarily scheduled visits. It also states that the process of
inspector evaluation must be consistent for all projects even though
large projects normally receive regular site visits and performance
observations. The acting state architect explained that the division
bases the number of visits on the needs of the project and the
judgment of the assigned field engineer. Giving field engineers
this much latitude to determine how many visits a project should
receive is likely to result in inconsistent oversight across the State.
Further, this approach neither establishes an expectation against
which the division can measure its performance, nor allows the
division to hold its field engineers responsible for performing
sufficient visits to similar projects. Interestingly, when developing
the field pilot program—which we describe later—the division did
establish criteria of a minimum of one visit to all sites and monthly
site visits for projects with construction activity lasting more than
three months, noting that this was the historical criteria it had
used for field visits. However, the division never implemented the
field pilot program criteria statewide. The division’s lack of setting
an expectation as to the number of field visits different types of
projects require, makes it difficult for the division to demonstrate
that it provides adequate oversight.
In addition, for a number of tested projects, the division could not
demonstrate that it had provided adequate field oversight. The
division’s field manual states that field engineers will complete
field trip notes for each visit that describe, among other things,
any concerns they have about the inspector’s performance or
about the project. However, we found no field trip notes on file for We found no field trip notes on
three of 24 closed projects we reviewed, even though construction file for three of 24 closed projects
on the projects had lasted between five and 32 months. These we reviewed, even though
projects had estimated costs of $270,000, $1.8 million, and construction on the projects had
$2.2 million, respectively. Additionally, we found notes for only lasted between five and 32 months
one field visit in each of the files associated with eight other and the projects had estimated
projects—three with estimated costs of over $500,000 each. The costs of $270, 000, $1.8 million, and
acting state architect explained that field trip notes provide all dates $2.2 million, respectively.
of the division’s field interaction. He also stated that although he
believes that engineers document most site visits with field trip
notes, there could be exceptions. Without notes documenting
each field visit, the division cannot demonstrate that it is providing
adequate oversight of projects and project inspectors, increasing
the risk that construction may not comply with approved plans.
Further, because the dates the division records in its database for
the start and end of construction can come from different and
sometimes undocumented sources, assessing whether its oversight
efforts cover the entire construction period can be difficult.
According to division procedures, field engineers may learn of the
start of construction in several ways, including receiving a notice
30 California State Auditor Report 2011-116.1
December 2011
of the start of construction from the school district, receiving a
phone call from the inspector, or visiting the site. Each of these
sources could potentially provide a different start date that would
not necessarily coincide with the date the district actually began
construction. Similarly, the division may draw on several sources
for the construction end date, which may not accurately or
consistently represent the actual end of construction. For example,
one project we reviewed had an inspector’s semimonthly report
dated nearly six months after the date the division’s database stated
that the district had ended construction. Because the start and
end dates that the division records are not always accurate, neither
we nor the division are able to determine with certainty whether
the division’s oversight activities adequately covered the entire
construction process. However, because the division’s database was
the only source of such information across all projects, we used it in
evaluating the division’s oversight efforts.
While the division generally Finally, while the division generally adheres to its process for
adheres to its process for closing closing projects, it has a backlog of over 400 projects, representing
projects, it has a backlog of over 5 percent of projects closed in the last three fiscal years. Specifically,
400 projects, representing 5 percent as of June 30, 2011, the division had 142 projects that were still
of projects closed in the last active between six months and one year after the date when it had
three fiscal years. noted that construction had ended, and 284 more were listed as still
active more than a year after the noted construction end date. The
division had not yet sent 90-day letters for any of these projects.
The 90-day letter provides school districts with information on
what the division requires in order to certify projects. If school
districts do not receive this information in a timely manner, they are
more likely to have trouble obtaining required reports or correcting
any deficiencies noted by inspectors as the parties involved in
the project move on to new ventures. The regional managers
cited several reasons why delays in sending out the 90-day letters
might occur, including limited close-out staff; the inclusion
of incorrect construction end dates in the division’s database;
and poor communication among field engineers, architects, and
close-out staff.
The Division Does Not Adequately Approve, Train, and Supervise
Project Inspectors
As discussed in the Introduction, the division relies heavily on
project inspectors to ensure that school districts build projects in
accordance with approved plans. However, this reliance presents
an inherent risk because districts contract with or employ the
inspectors, creating the possibility that the districts may attempt
to influence them. The division does not have an adequate
process to mitigate this risk. In addition, the division has not
always approved inspectors before construction starts. Finally, its
California State Auditor Report 2011-116.1 31
December 2011
training and certification processes for inspectors have weaknesses,
and it lacks a process for evaluating inspectors. Without stronger
safeguards in place, the division cannot be sure that districts
construct projects in a way that maximizes public safety.
The Relationship Between Project Inspectors and the Other Entities
Involved in the Construction Process Increases the Risk That Districts
May Improperly Construct Projects
The process established to oversee project construction creates
an inherent risk that buildings may not comply with approved
plans. The Field Act requires that inspectors be responsible to
school districts as employees or contractors and to the division
as enforcers of building standards. Because project inspectors
are responsible to two entities, districts may take advantage of
their position as employers to attempt to unduly influence their
inspectors. The acting state architect further explained that
many districts employ construction managers—whose purpose
is to ensure projects finish on time and within budget—who
may also attempt to influence inspectors. Several of the regional
managers confirmed that school districts or construction managers
sometimes interfere with the work of project inspectors.
Because the division relies so heavily on inspectors to ensure Because the division relies so
proper construction, we believe the possibility that the districts or heavily on inspectors to ensure
their construction managers may influence inspectors demands proper construction, we believe
the division’s attention. For example, the inspector for one of the the possibility that the districts or
projects we reviewed submitted reports in which he indicated their construction managers may
that the construction manager had instructed the building influence inspectors demands the
contractor not to comply with the architect’s instructions to install division’s attention.
specified fireproofing materials. The project inspector also stated
that the construction manager had directed the architect not to
communicate with the project inspectors. The project inspector
alleged that the construction manager had violated the Field Act
by interfering with the design of the building and with his and
the project architect’s responsibilities. For another project, we
found evidence that a school district prodded an inspector to
check the installation of modular school buildings without having
division-approved plans on which to base the inspection. After the
inspector communicated the problem to both the school district
and the division, records we reviewed indicate that the division
took issue with the district’s constructing facilities in advance
of plan approval but did not try to stop the project. The district,
acknowledging its liability, went ahead with construction, and
the inspector performed his job using plans that had not been
approved. In fact, the district completed the project before the
division approved the plans and, as of October 2011, this project
remained uncertified.
32 California State Auditor Report 2011-116.1
December 2011
The division needs to strengthen its method for combating possible
interference with the work of inspectors. Several regional managers
said that the best way for the division to ensure that districts or
project managers are not inappropriately influencing inspectors is
to have field engineers make periodic visits to construction sites.
The acting state architect stated that the division’s field presence
is the only effort the division uses to counteract influence over
inspectors. He also said that the division could benefit from
developing explicit direction for field staff that would address
potential conflicts. However, as explained earlier in this chapter,
the division does not have a well-defined process for planning
site visits and sometimes cannot demonstrate that it has visited
project sites.
In Violation of Regulations, School Districts Often Start Construction on
Projects Before the Division Formally Approves Their Inspectors
Many school districts proceed with projects before the division
approves their inspectors because the districts do not provide
the necessary information that would allow approval to occur
in a timely manner or at all. Regulations require that school
districts submit the names of proposed inspectors for the
division’s approval at least 10 days before starting construction.
Additionally, regulations prohibit construction from proceeding
without a division-approved inspector. However, we found that
We found that the division had not the division had not yet approved inspectors a month or more
yet approved inspectors a month after districts started construction on 22 out of 34 projects we
or more after districts started reviewed. Although 14 of these projects had an approval form
construction on 22 out of 34 projects on record, because the school districts submitted requests for
we reviewed. approval 30 or more days late, the division was not able to approve
inspectors before construction started. In fact, for two of the
14 projects, the districts did not submit approval forms until
after the division’s database indicated the districts had finished
construction. Of the eight remaining projects where we noted
problems, four had no approval request form on file, and the
other four had inspector approval request forms that were either
unsigned or undated. Nevertheless, 18 of these 22 projects had
semimonthly inspector reports on file, indicating that inspectors
had overseen construction.
Because getting the required signatures for the inspector approval
request form takes time, the acting state architect stated that field
engineers may informally approve inspectors through discussions
with school districts and design professionals before the districts
submit the form. He also said that field engineers know whether
the inspectors are qualified and if their workload will allow them
to take on another project for inspection. However, the division
does not record its informal approvals in project files, and its
California State Auditor Report 2011-116.1 33
December 2011
process circumvents the controls put in place by regulations.
These controls are intended to allow the division to demonstrate
that inspectors are qualified and have sufficient time available to
provide ongoing inspection of projects.
We believe the division could take advantage of available
resources to make the approval process more efficient instead
of circumventing it. The division currently requires that school
districts report information on the workload and past experience
of proposed inspectors on the approval request form. The division
could use its database to create a report of each inspector’s current
workload and past work experience. Rather than having informal
discussions with the school districts, the division could use these
reports to determine whether proposed inspectors are qualified
and have workloads that allow them sufficient time to perform
the work.
Weaknesses in the Division’s Inspector Certification Program Increase
the Risk That Inspectors May Not Be Knowledgeable About the Latest
Building Standards
In violation of its policy, the division sometimes excuses inspectors
from required trainings, extending the amount of time they can
go without receiving training. According to regulations, division
certification of an inspector is valid for four years. The Field Act
and division policies make renewal of that certification dependent
in part on attendance at a division training class. However,
inspectors who upgrade their certifications in order to inspect
more complex projects restart the four-year certification period
upon obtaining the upgrade. In this situation, the division’s policy
requires inspectors to attend training prior to sitting for an upgrade
exam. When the division waives this training requirement, it lets
more than the allowed four-year period elapse between trainings.
According to the certification unit manager, staff familiar with the
building standards will occasionally excuse inspectors from training
because the required class has not been updated since the last time
they attended the class.
In our review of 21 inspector certifications, we noted one instance
in which the division excused an inspector who applied for a
certification upgrade from attending required training. The
certification unit manager explained that a headquarters staff
person familiar with building standards excused this individual
from the training. However, when the division ignores upgrade
requirements, it may allow some inspectors to go long periods
of time without required training. In this instance, the division
previously certified this inspector in March 2007 and, because it
excused him from a required training in 2009 when it upgraded
34 California State Auditor Report 2011-116.1
December 2011
The practice of excusing inspectors his certification, it will not require him to attend training again
from training is problematic until 2013. The practice of excusing inspectors from training is also
because the division has not problematic because the division has not formalized it. As a result,
formalized it and thus, may create the division may create the perception that its decisions to excuse
the perception that its decisions certain individuals are arbitrary or show favoritism.
to excuse certain individuals are
arbitrary or show favoritism. In addition, the division has not always ensured that the inspectors
it has certified have passed all parts of the latest certification
examination. The Field Act requires that inspectors pass a
competency examination in order to receive certification. The
division uses a two-part exam to verify an inspector candidate’s
competence: The first part of the exam focuses on plan reading,
and the second part on building codes. The division’s policy
permits candidates who fail one part but pass the other to take the
failed part again while maintaining provisional credit for the part
they passed until the division revises the exam. However, after a
March 2009 revision to the exam, the division did not immediately
invalidate scores from the previous version of the exam for
inspector candidates with provisional credit. Instead, it issued a
notice that it would invalidate provisional scores from the previous
version of the exam in January 2010. Therefore, for nine months
the division allowed candidates to obtain certification without
passing both parts of the new exam. Further, out of four inspectors
we reviewed who were required to pass this two-part exam,
one individual passed one part of the certification exam in 2008
and the other part of the exam in 2010. The division certified
this individual even though the terms of its exam announcement
stated that his 2008 exam score was no longer valid. Although the
certification unit manager stated that her staff review applicants’
previous exam results to identify any scores that are no longer
valid, that process does not appear to have been effective in
this case.
Finally, the division has not always clearly documented its
verification of an inspector candidate’s prior experience. State
regulations require that inspectors have at least three years of work
experience on projects of a type similar to those they will inspect
as division-certified inspectors, and the division’s application
for inspector examinations requires that candidates provide a
description of their related work experience. However, in our
review of inspectors, we found three cases out of eight in which the
division did not clearly indicate that it had verified the experience
of inspector candidates prior to certifying them. In one of these
cases, the candidate did not describe any previous experience on his
application but the division nonetheless noted that the individual
could proceed with certification. According to the certification
unit manager, her staff verify the experience of all candidates by
calling the candidates’ references and making note of these calls on
the application. However, in the three cases previously mentioned,
California State Auditor Report 2011-116.1 35
December 2011
we could not identify any notes or other evidence of this sort of
reference check. When the division does not follow its procedures
for checking that candidates have the required level of experience,
it cannot demonstrate that all inspectors meet the prerequisites for
working as project inspectors.
As discussed earlier, inspectors are critical to the division’s oversight
of school project construction. Without consistently applied
policies and controls, the division elevates the risk that some
inspectors may lack training, knowledge of building standards, or
relevant experience in construction.
The Lack of an Evaluation Process for Inspectors Increases the Risk That
Construction Will Not Comply With Approved Plans
The division’s field engineers have made recommendations for
changing the disciplinary process for inspectors. According
to a statewide team of field engineers, rigorous construction
inspection is a central provision of the Field Act; however, According to the San Diego field
according to the San Diego field team supervisor, inspectors team supervisor, inspectors have
have falsified reports, been absent from job sites, been unable to falsified reports, been absent
comprehend construction plans, and failed to communicate with from job sites, been unable to
the regional office about their projects. In addition, the Sacramento comprehend construction plans,
region provided documents showing that it has removed inspectors and failed to communicate with the
from projects for approving deficient concrete and wood framing regional office about their projects.
connections and failing to identify deficient welds. The Sacramento
region has also denied approval to inspectors after they failed to
turn in required reports on previous projects. In June 2010 the field
engineers’ statewide team submitted recommendations to division
headquarters for improving the disciplinary process for inspectors,
including establishing a disciplinary panel and creating a database
for field staff to track inspector evaluations statewide. According
to the division’s certification unit manager, the division has moved
slowly on the proposal because of workload and staffing constraints;
as a result, this is still a work in progress.
Until recently, the division evaluated inspector performance
using a rating form; however, it changed its interpretation of
regulations related to inspector performance and discontinued
this process in October 2010. According to the acting state
architect, before its discontinuance, the division did not use the
rating form consistently. Further, he stated that a large volume of
Public Records Act requests for inspector evaluations caused the
division to spend considerable time notifying inspectors that it
would be releasing their evaluations. In turn, the inspectors wanted
to review their evaluations. He said that given the consternation
the requests caused, the division decided to discontinue using the
rating form, pending clarification of its purpose. The division’s
36 California State Auditor Report 2011-116.1
December 2011
latest interpretation of regulations on inspector performance states
that it is reviewing its policy on rating inspectors’ performance.
However, according to the acting state architect, the division has
not developed plans to reinstate the use of inspector rating forms as
of October 2011.
In the absence of the rating form, the division monitors inspector
performance through the field engineers’ field trip notes and
reviews of inspector reports and other communications. According
to the acting state architect, field trip notes are the primary means
through which field engineers communicate to the inspector, design
professional, and school district those issues that must be remedied.
However, he also stated that in cases in which significant issues
arise related to inspector performance, field engineers may exclude
their concerns from field trip notes and instead either request a
meeting with the inspector or contact the design professional or
school district directly. In these instances, the division may fail to
document issues related to inspectors’ performance. Further, as
previously noted in this chapter, the division does not consistently
ensure that field engineers perform a sufficient number of site
visits, where they could observe inspectors at work. Moreover, we
found cases where field engineers prepared no field trip notes. As a
result, they either may not notice performance issues or may fail to
document such issues related to inspectors.
Without a formal evaluation Without a formal evaluation process, the division risks failing to
process, the division risks failing consistently and adequately address performance issues, and it
to consistently and adequately may also be unable to defend its disciplinary actions. New state
address performance issues and regulations in effect since January 2011 outline the steps the division
it may also be unable to defend can take to discipline inspectors who are performing poorly, steps
its disciplinary actions. that range from requiring them to attend counseling meetings in
the regional office to withdrawing their certification. Although it
lacks a formal evaluation process, the division has gone forward
with disciplinary actions against some inspectors. For example, the
Oakland region met with an inspector who, it found, had inspected
projects even after the division had rejected his appointment
because of workload concerns; he also did not submit semimonthly
reports. The inspector subsequently provided written assurances
that he would comply with the division’s requirements. According
to the acting state architect, division field supervisors and field
engineers are responsible for monitoring this inspector’s future
performance to ensure compliance with division requirements. In
another example of disciplinary action, the Sacramento regional
office has informed inspectors who have not submitted required
reports for closed projects that they risk the division not approving
them for future projects. According to the Sacramento regional
office’s field supervisor, his office has held up inspector approvals
based on the failure to submit forms. Although the division has
disciplined some inspectors, it cannot remove inspectors from
California State Auditor Report 2011-116.1 37
December 2011
projects or withdraw their certification, as its regulations allow,
without providing the inspectors with notice of the reasons
for the discipline and an opportunity to appeal the discipline. For
this reason, it would be difficult to undertake and sustain such
disciplinary actions without adequate documentation of inspectors’
poor performance.
The Division’s Absence of Expertise in Key Construction Disciplines
Increases the Risk That It Will Not Adequately Oversee Construction in
These Areas
Although the division reviews plans for school construction
projects in three key disciplines, it does not provide a similar level
of construction oversight for two of these areas. The division hires Specifically trained technical
specifically trained technical staff to review and approve project staff review and approve project
plans related to structural safety, fire and life safety, and accessibility. plans related to structural
However, it does not employ similar subject matter experts to safety, fire and life safety, and
provide oversight of construction in those same disciplines. Rather, accessibility; however, no similar
the division employs structural engineers as field staff who focus subject matter experts provide
on structural safety. This approach does not ensure that fire and oversight of construction in these
life safety and accessibility issues receive an equivalent level of same disciplines.
oversight during construction. The acting state architect questions
whether the division has a statutory obligation to provide oversight
of the fire and life safety and accessibility aspects of school
construction. However, he also stated that review staff for fire and
life safety and accessibility plans are available to the field engineers
for consultation.
Nevertheless, the division conducted a field pilot beginning in
August 2007 intended to expand its construction oversight to
address fire and life safety and accessibility compliance. In addition,
the division focused the pilot on adding oversight related to the
mechanical, electrical, and plumbing aspects of projects, which are
part of the building standards. The pilot grew out of a review by the
Department of General Services (department) that recommended
employing additional staff to monitor adherence to approved plans
and building standards in these three areas. The pilot set criteria of
one visit to all sites and monthly visits to projects lasting more than
three months, and it estimated that the Sacramento region—where
the division carried out the pilot—would require seven additional
field staff to meet the expanded scope. In 2007 and 2008 the
division undertook the pilot, adding staff to the Sacramento region
focused on accessibility; fire and life safety; and the mechanical,
electrical, and plumbing aspects of projects. According to the
acting state architect, staff submitted the draft report on the pilot—
which provided a framework for statewide implementation—
to the previous state architect and the four regional managers,
but the division undertook no further action related to it. He
38 California State Auditor Report 2011-116.1
December 2011
By not providing adequate stated that he does not know why the previous state architect did
oversight of the fire and life safety not act on the pilot. He also stated that since the pilot, the division
or accessibility aspects of school has made no efforts to expand oversight of the fire and life safety
construction, the division risks that or accessibility aspects of construction. By not providing adequate
significant issues related to public oversight of these facets of school construction, the division risks
safety may not receive the attention that significant issues related to public safety may not receive the
they deserve. attention they deserve.
Additionally, according to its administrative services manager,
the division conducted update trainings on building standards in
November 2010. According to this manager, there were trainings
in each of the three key disciplines discussed previously. However,
the regional managers reported that their field staff were only
required to attend the structural training and not the accessibility
or fire and life safety trainings. Further, the manager of the division’s
training unit explained his unit did not receive training evaluation
surveys from all field staff and therefore could not determine if all
of them had attended the update training on building standards; the
division did not maintain attendance rosters. The administrative
services manager explained that regional offices were responsible
for ensuring that their staff attended the training. However, without
a complete attendance record, the division cannot demonstrate
that all field staff attended the building standards training or what
aspects of training they received.
The Division Lacks Performance Measures for the Construction and
Close‑out Phases of Projects
The division has developed performance measures for the plan
review phase of projects but has not done so for the construction
oversight or close-out phases. The division currently publishes
monthly reports on the number of days it takes to assign plans
to plan review staff and the number of days it subsequently takes
review staff to approve the plans. However, it has not put into place
similar measures related to the construction oversight and project
close-out phases.
According to the manager of the Performance Metrics Section, the
division has not developed performance measures for these phases
because it lacks data. However, we identified several statistics that
we believe the division could track as useful performance measures,
based on data it currently maintains. For example, the division
could track and report the number and the percentage of projects
that are certified or uncertified when it closes them. Further, if
the division were to improve the consistency and reliability of the
construction start and end dates in its database, it could measure
the length of construction time and the length of time from the
California State Auditor Report 2011-116.1 39
December 2011
end of construction to project closeout and certification. Also,
as discussed previously, regulations require that school districts
submit the names of inspectors for approval before construction
begins. By tracking the projects that have approved inspectors
before the start date of construction, the division could determine
whether qualified inspectors are providing continuous inspection
of projects.
The division also indicated that it does not have performance
measures for the construction oversight and close-out phases
because it has less control over processes during these
phases. The manager of the Performance Metrics Section stated
that during the plan review phase, one employee is normally
associated with each project, and the division can track the
number of days that a project spends in review. However, he
noted that during the construction oversight and close-out
phases, the division has less control over the process. During
the construction phase, field engineers have multiple projects
in different stages of construction to monitor, and during the
close-out phase, the division is dependent on school districts,
design professionals, and project inspectors to provide
required documentation.
We acknowledge that the division’s oversight and close-out
activities may be more difficult to assess than its plan
review process. Nevertheless, performance measures
related to actions, such as the number of field visits per
project, or to outcomes, such as the rate of projects closed
without certification, could help the division identify areas
needing improvement and then evaluate its success in making
these improvements over time. In fact, the regional offices have Although the division indicated
developed tools that the division could use statewide to measure that it does not have performance
performance. For example, in the Oakland, Sacramento, and measures for the construction
San Diego regions, field engineers submit travel itineraries oversight and close-out phases
for field visits to their field team supervisors, who maintain a because it has less control over
record of such visits. The division could use this information processes during these phases, the
to assess whether staff are visiting projects as indicated. Also, regional offices have developed
the Los Angeles region maintains a record of the different tasks tools that the division could use
close-out staff complete, such as the number of 90-day and statewide to measure performance.
certification letters issued. The division could use these data to
assess its efficiency in closing down projects. By not establishing
performance measures for construction oversight and project
closeout, the division has failed to take advantage of management
tools that could give better focus to staff and the organization as a
whole. Further, without such measures, it is less able to demonstrate
that it is meeting its mission.
40 California State Auditor Report 2011-116.1
December 2011
Although Staffing Challenges May Have Contributed to Oversight
Problems, the Division Has Not Recently Assessed Its Staffing Needs
Although the division has not recently assessed its staffing needs,
staffing challenges may have contributed to its inconsistent
oversight of the construction process. According to division
reports, the division has 345 authorized positions, and vacancies
divisionwide increased from 25 in July 2010 to 47 in July 2011, or
14 percent. Although not as affected by vacancies as other parts
of the division, the construction oversight and project close-out
functions of the regional offices have suffered the temporary loss of
employees due to long-term leaves of absence, as shown in Table 6.
For example, of its nine authorized field positions, Los Angeles had
one vacant field engineer position in July 2010 and two missing
field engineers due to leaves of absence, a loss of one-third of its
field staff. Further, the Los Angeles regional manager retired in
September 2011 and, because the division has not appointed a
replacement, the regional manager and a project services supervisor
from the San Diego region currently each spend two days a week in
Los Angeles. As we discussed in Chapter 1, the Los Angeles region
had the highest number of active projects and the greatest number
of uncertified closed projects in our three-year review period. As of
October 2011, the division has requested but not received a formal
decision regarding exemptions from a state hiring freeze to fill the
vacant oversight and close-out positions.
Part of the division’s oversight Part of the division’s oversight challenges may also have stemmed
challenges may also have stemmed from an effort it recently completed related to plan review. In
from a recently completed effort January 2010 the division took action to reduce the time it was
to shift 50 percent of regional taking to review and approve construction project plans. This effort
managers’ and field supervisors’ shifted 50 percent of regional managers’ and field supervisors’ time
time and 40 percent of field and 40 percent of field engineers’ time to plan review. To offset
engineers’ time to plan review. this shift, the division entered into an 11-month memorandum
of understanding in February 2010 with another division of the
department, which provided nine staff to assist the division with
construction oversight and close-out activities. Although regional
managers stated that this shift affected field oversight, they could
not quantify the impact. Because the division does not measure
oversight or close-out activities, determining the effect of this shift
on the division’s output is not possible.
The division never formalized its most recent effort to estimate its
staffing needs. According to the division’s deputy of operations, the
Sacramento field pilot program initiated in 2007 is the only recent
effort the division has made to estimate needed staffing levels. As
previously mentioned, the pilot established an expected number
of visits for each project and recommended adding seven field
staff to the Sacramento regional office—where the division
conducted the pilot—to cover additional construction disciplines.
California State Auditor Report 2011-116.1 41
December 2011
Table 6
Division of the State Architect’s Staffing Levels for Field Review and Project
Closeout as of July 1, 2011
POSITION
Oakland FIELD REVIEW CLOSEOUT TOTALS
Authorized 8 5 13
Filled* 8 4 12
Vacant 0 0 0
Sacramento
Authorized 11 6 17
Filled 11 4 15
Vacant 0 2 2
Los Angeles
Authorized 9 5 14
Filled* 6 5 11
Vacant 1 0 1
San Diego
Authorized 7 5 12
Filled* 7 4 11
Vacant 0 0 0
Total authorized 35 21 56
Total filled* 32 17 49
Total vacant 1 2 3
Sources: Division of the State Architect and the 2011–12 Governor’s Budget, Salaries and Wages.
* One close‑out position in Oakland, one in San Diego, and two field review positions in Los Angeles
are not counted as filled due to employees’ extended leaves; however, these positions are
not vacant.
However, the deputy of operations believes that the staffing levels
in this 2008 draft study are not necessarily appropriate for current
circumstances, and the acting state architect believes that different
classifications from those the pilot put forward would be a better fit.
The deputy of operations stated that the division has made no other
efforts to assess staffing levels due to hiring freezes and furloughs,
which have limited available staff and resources. However,
without a current estimate of appropriate staffing levels based on
documented workload metrics, the division cannot be certain that
it has sufficient staff to provide adequate construction oversight,
and it has no justification for requesting additional staff.
42 California State Auditor Report 2011-116.1
December 2011
Recommendations
To ensure it is providing adequate oversight of school
district construction projects, the division should take the
following actions:
• Develop robust procedures for monitoring inspectors’
submission of semimonthly reports. The division should also
maintain all semimonthly reports in its project files.
• Develop and document an overall strategy that establishes
specific expectations for conducting site visits and monitoring
construction. The division should then record and compare its
actual visits and monitoring efforts to its planned actions. The
division should document explanations for any deviations from
its plans.
• Establish consistent criteria for entering data into its database on
key aspects of projects, such as the dates for the start and end
of construction.
To mitigate risks arising from the relationship between inspectors,
school districts, and project managers, the division should develop
formal procedures and explicit directions for field engineers to
ensure that they establish a presence on project sites and provide
adequate oversight of inspectors during construction.
To ensure that it approves inspectors prior to the start of project
construction, the division should streamline its approval process by
reviewing inspectors’ workloads and past experience using the data
it already maintains.
To ensure that certified inspectors are knowledgeable about current
code requirements, the division should not excuse inspectors from
required trainings and should improve its process for identifying
expired certification exam scores. Further, the division should
consistently follow and document its procedures for verifying the
past employment of inspector applicants.
To ensure that it formally monitors inspectors’ performance, the
division should reestablish a process for evaluating inspectors that
provides consistent documentation of performance. The division
should make this information accessible to appropriate staff.
To address areas in which its staff do not currently have expertise,
the division should finalize its field pilot and take subsequent steps
to ensure it has qualified staff to provide oversight of accessibility;
fire and life safety; and the mechanical, electrical, and plumbing
aspects of construction.
California State Auditor Report 2011-116.1 43
December 2011
To better manage its construction oversight and close-out functions,
the division should develop measures to assess those functions and
it should periodically report the results to the public on its Web site.
To address possible staffing problems, the division should use
documented workload metrics to perform an assessment of its
current staffing levels and determine its staffing needs. It should
revisit the field pilot and make necessary changes to reflect its
understanding of its current staffing situation.
We conducted this audit under the authority vested in the California State Auditor by Section 8543
et seq. of the California Government Code and according to generally accepted government
auditing standards. Those standards require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings and conclusions based on our
audit objectives specified in the scope section of the report. We believe that the evidence obtained
provides a reasonable basis for our findings and conclusions based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
Date: December 8, 2011
Staff: Jim Sandberg-Larsen, CPA, CPFO, Audit Principal
John Lewis, MPA
Bob Harris, MPP
Greg Martin
Jordan Wright, MPA, CFE
Legal Counsel: Stephanie Ramirez-Ridgeway, JD
ITAS Staff: Michelle J. Baur, CISA, Audit Principal
Richard W. Fry, MPA
For questions regarding the contents of this report, please contact
Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
44 California State Auditor Report 2011-116.1
December 2011
BBllaannkk ppaaggee iinnsseerrtteedd ffoorr rreepprroodduuccttiioonn ppuurrppoosseess oonnllyy..
California State Auditor Report 2011-116.1 45
December 2011
(Agency comments provided as text only.)
State and Consumer Services Agency
915 Capitol Mall, Suite 200
Sacramento, CA 95814
MEMORANDUM
TO: Elaine M. Howle, State Auditor*
Bureau of State Audits
FROM: Anna M. Caballero, Secretary
DATE: November 17, 2011
RE: Bureau of State Audit’s Report No. 2011-116.1
Pursuant to the Bureau of State Audit’s (BSA) Report No. 2011-116.1, enclosed are the Department of General
Services’ comments pertaining to the results of the audit.
The State and Consumer Services Agency would like to thank the BSA for the comprehensive review of the
Division of the State Architect. The results provide us with the opportunity to better serve our clients and
protect the public.
(Signed by: Anna M. Caballero)
Anna M. Caballero, Secretary
State and Consumer Services Agency
Enc.
* California State Auditor’s comments appear on page 53.
46 California State Auditor Report 2011-116.1
December 2011
(Agency comments provided as text only.)
Department of General Services MEMORANDUM
Date: November 17, 2011
To: Anna M. Caballero, Secretary
State and Consumer Services Agency
915 Capitol Mall, Suite 200
Sacramento, CA 95814
From: Fred Klass, Director
Department of General Services
Subject: RESPONSE TO BUREAU OF STATE AUDITS’ REPORT NO. 2011-116.1
Thank you for the opportunity to respond to the Bureau of State Audits’ (BSA) Report No. 2011-116.1 which
addresses recommendations to the Department of General Services’ (DGS) Division of the State Architect
(Division). The audit focused on the Division’s construction oversight and project close-out functions. The
following response addresses each of the recommendations.
OVERVIEW OF THE REPORT
The DGS has reviewed the findings, conclusions and recommendations presented in Report No. 2011-116.1. The
DGS will take appropriate actions to address the BSA’s recommendations.
In summary, the BSA accurately reports in Chapter 1 that thousands of school construction projects remain
uncertified by the Division. This condition is due in part to provisions of the Field Act which specifically
provide that the State does not have the authority to prevent beneficial occupancy by a school district
of a facility prior to the issuance of certification of the construction project by the Division. Despite the
limitations placed on the Division by the Field Act, the BSA’s report identifies a number of steps the Division
could take to attempt to increase the number of projects it certifies and to mitigate risks that uncertified
projects may pose.
In Chapter 2, the BSA identifies a number of areas of concern with the Division’s construction oversight
function. As a result, the BSA concluded that the Division has not provided an effective and comprehensive
level of oversight of school construction processes.
Upon my appointment as DGS Director in early May 2011, I became aware that thousands of school facilities
have been occupied prior to certification that those facilities were constructed in compliance with the
Field Act. I also learned of concerns about apparent deficiencies in the Division’s oversight of construction
projects, including the oversight of project inspectors. Consequently, I immediately initiated an internal
1 review of the Division’s operations and procedures governing those activities. The findings noted in the BSA’s
audit report are consistent with that review. The internal review also includes an action plan to address areas
for improvement in the Division’s construction oversight and project close-out functions. In conjunction
with the findings and action plan of the DGS’ internal review, the findings and recommendations of the BSA’s
audit will be of great assistance in implementing changes that will improve the Division’s ability to carry out
its mission of ensuring that schools meet the State’s seismic, structural safety and accessibility standards.
California State Auditor Report 2011-116.1 47
December 2011
Anna M. Caballero -2- November 17, 2011
The DGS appreciates the BSA’s in-depth audit and is fully committed to promptly and completely
addressing the issues identified in the audit report. In general, the actions recommended by the BSA have
merit and will be promptly addressed.
RECOMMENDATIONS
CHAPTER 1
RECOMMENDATION # 1: To ensure public safety and provide public assurance that school districts construct
projects in accordance with approved plans, the department, in conjunction with
the division, should pursue legislative changes to the Field Act that would prohibit
occupancy in cases in which the division has identified significant safety concerns.
DGS RESPONSE # 1:
In its report, the BSA correctly states that the Field Act specifically provides that the State does not have the
authority to prevent beneficial occupancy by a school district of a facility prior to the issuance of certification
of the construction project by the Division. The DGS shares the BSA’s concern that occupancy or use of
facilities should not occur if significant code deficiencies have been identified that effect the safety of facility
users. Consequently, the DGS will discuss within the Administration the option of pursuing legislation that
would change the Field Act to prohibit occupancy in cases in which the Division has identified significant
safety concerns.
RECOMMENDATION # 2: To better utilize the enforcement tools at its disposal, the division should continue
and expand its use of both orders to comply and stop work orders, as defined in its
regulations. The division should also develop performance measures to assess the
success of any efforts it makes to address safety concerns and reduce the number
of uncertified projects.
DGS RESPONSE # 2:
In the near future, Division headquarters’ management will meet with the managers of its four regional
offices to discuss the current use of both Orders to Comply and Stop Work Orders. Subsequently, additional
policies and procedures will be issued to assist in ensuring the appropriate and consistent use of these
enforcement tools as part of the construction project oversight function.
As to the development of performance measures, the Division will task its Performance Metrics Unit with the
responsibility for developing metrics to measure the success of the primary actions taken to address safety
concerns and reduce the number of uncertified projects. These actions include requiring school districts to
complete certification of uncertified projects before granting plan approval of new projects and the use of
Orders to Comply and Stop Work Orders during a project’s construction.
48 California State Auditor Report 2011-116.1
December 2011
Anna M. Caballero -3- November 17, 2011
RECOMMENDATION # 3: To ensure that it clearly justifies the reasons a project’s noted issues merit a
particular classification, the division should either modify its current policies
regarding classifying types of uncertified projects or develop new policies,
including requiring documentation of the rationale behind project-specific
classifications. It should use its classifications to prioritize its efforts to follow up
on uncertified projects based on risk and to better inform the public regarding the
reasons it has not certified projects.
DGS RESPONSE # 3:
The Division will modify or create new policies regarding classifying projects closed without certification,
including the rationale behind the specific classification, and the use of letters to notify districts of the reason
a project was not certified. Consequently, the Division will use the new process to prioritize its efforts to
follow up on uncertified projects based on risk and to better inform the public regarding the reasons it has
not certified projects.
RECOMMENDATION # 4: To reduce the number of uncertified projects, the division should implement
initiatives to follow up with school districts on uncertified projects. Those initiatives
should include, at a minimum, regularly sending each district a list of its uncertified
projects and assessing the success of its follow-up efforts.
DGS RESPONSE # 4:
2 As noted in the BSA’s report, the Division has developed a performance measure that provides for the
identification of projects closed without certification and the categorization of those projects by Project Class and
school district. The size and complexity of a project will be included as part of the categorization process. Project
Class is defined as follows:
§ Project Class 1 (non-wood) and Class 2 (wood) are construction of new buildings that house students
and staff;
§ Project Class 3 is alterations/modernization and miscellaneous construction to existing buildings; and,
§ Project Class 4 is site placement of pre-manufactured relocatable school buildings (factory inspected
with Division oversight).
It is currently planned that this activity will be completed by June 30, 2012. Consequently, a school district
communication and outreach plan will be developed that, at a minimum, includes regularly sending each
district a list of its uncertified projects. The success of the Division’s outreach efforts in reducing the number
of uncertified projects will be tracked and regularly evaluated.
California State Auditor Report 2011-116.1 49
December 2011
Anna M. Caballero -4- November 17, 2011
CHAPTER 2
RECOMMENDATION # 1: To ensure it is providing adequate oversight of school construction projects, the
division should take the following actions:
• Develop robust procedures for monitoring inspectors’ submission of
semimonthly reports. The division should also maintain all semimonthly
reports in its project files.
• Develop and document an overall strategy that establishes specific
expectations for conducting site visits and monitoring construction. The
division should then record and compare its actual visits and monitoring
efforts to its planned actions. The division should document explanations for
any deviations from its plans.
• Establish consistent criteria for entering data into its database on key aspects
of projects, such as the dates for the start and end of construction.
DGS RESPONSE # 1:
The Division will develop additional processes to ensure that inspectors are submitting the semimonthly
reports and that received reports are maintained in the project files. As part of this activity, the Division will
periodically reemphasize to its field engineers the importance of obtaining the reports. The Division will also
determine the feasibility of assigning administrative staff with responsibilities for tracking, obtaining and
filing the inspector reports.
Pertaining to conducting site visits and monitoring construction, the Division has implemented a
policy which requires that all Project Class 1 and 2 projects be regularly visited by its field engineers,
including a face-to-face meeting with project inspectors. Project Class 1 and 2 projects must have at least
one documented visit by a field engineer with an overall objective that ongoing projects be visited at four to
six week intervals. Currently, the Division is developing a measurement tool and a training program for its
field engineers on this process. The training will focus on ensuring that consistent construction oversight is
being provided and that project inspector’s performance is actively being overseen.
It should be noted that by June 30, 2012, the Division plans that all active Project Class 1 and 2 projects
will be visited and meetings held and documented with project inspectors. This metric is included within the
Division’s 2011/12 fiscal year business plan. After the completion of the activity for Project Class 1 and 2 projects,
a similar process will be developed for Project Class 3 and 4 projects.
Finally, the Division will develop standard criteria for entering data into its project management system. This
activity will include establishing clear criteria for identifying the start and end dates of construction.
RECOMMENDATION # 2: To mitigate risks arising from the relationship between inspectors, school districts,
and project managers, the division should develop formal procedures and explicit
direction for field engineers to ensure that they establish a presence on project sites
and provide adequate oversight of inspectors during construction.
50 California State Auditor Report 2011-116.1
December 2011
Anna M. Caballero -5- November 17, 2011
DGS RESPONSE # 2:
As discussed above, the Division is developing a training program that focuses on ensuring that consistent
construction oversight is being provided by its field engineers. The training will include modules that
address overseeing project inspector performance and record keeping during construction.
For future projects, field engineers will be required to conduct face-to-face meetings with project inspectors
(including an audit of inspector records) to establish a presence on the project and provide adequate
oversight of inspector performance during construction.
RECOMMENDATION # 3: To ensure that it approves inspectors prior to the start of project construction, the
division should streamline its approval process by reviewing inspectors’ workloads
and past experience using the data it already maintains.
DGS RESPONSE # 3:
The Division will evaluate the inspector approval process for activities that could be streamlined to assist in
approving inspectors prior to the start of project construction. As part of this evaluation, the Division will
determine the feasibility of using existing inspector data on-file to assist in the approval process.
RECOMMENDATION # 4: To ensure that certified inspectors are knowledgeable about current code
requirements, the division should not excuse inspectors from required trainings
and should improve its process for identifying expired certification exam scores.
Further, the division should consistently follow and document its procedures for
verifying the past employment of inspector applicants.
DGS RESPONSE # 4:
The Division has tasked its certification unit manager with developing written policies which provide that
inspectors must not be excused from required training. Further, the Division will take action to strengthen
existing processes regarding identifying expired certified exam scores and maintaining documentation of
staff verifying the past employment history of inspector applicants.
RECOMMENDATION # 5: To ensure that it formally monitors inspectors’ performance, the division
should reestablish a process for evaluating inspectors that provides consistent
documentation of performance. The division should make this information
accessible to appropriate staff.
DGS RESPONSE # 5:
The Division concurs that a process for evaluating inspector performance is important and should be
reestablished as part of the construction oversight program. Consequently, the Division will assign staff
to review the prior inspector evaluation process to identify lessons learned and to develop a plan for the
completion of performance evaluations by the field engineer at the final site visit.
California State Auditor Report 2011-116.1 51
December 2011
Anna M. Caballero -6- November 17, 2011
RECOMMENDATION # 6: To address areas in which its staff do not currently have expertise, the division
should finalize its field pilot and take subsequent steps to ensure it has qualified
staff to provide oversight accessibility; fire and life safety; and the mechanical,
electrical, and plumbing aspects of construction.
DGS RESPONSE # 6:
The Division will revisit the results of the field pilot and determine the current feasibility of expanding its 3
construction oversight for schools beyond structural safety. The field pilot was conducted during portions
of 2007 and 2008 and primarily involved an expansion of construction oversight activities to include
accessibility, fire and life safety, and the mechanical, electrical, and plumbing aspects of construction. In
late 2008, a draft report discussing the results of the pilot was issued to a prior State Architect. However, the
report recommendations were not acted on at that time.
RECOMMENDATION # 7: To better manage its construction oversight and closeout functions, the division
should develop measures to assess its construction oversight and closeout efforts
and should periodically report the results to the public on its Web site.
DGS RESPONSE # 7:
As previously discussed, the Division has developed performance measures that involve the identification 2
of projects closed without certification and the categorization of those projects by Project Class and school
district. Further, the Division has developed a performance metric that involves monitoring that all active
Project Class 1 and 2 projects are visited and meetings held and documented with project inspectors by 4
June 30, 2012.
In addition, the Division will task its Performance Measurement Unit with developing additional
performance measures and related training for the construction oversight and closeout phases of projects.
As part of this process, regional office management will be consulted on existing data that could be
tabulated and used as an additional tool to assess the adequacy and effectiveness of the construction
oversight and closeout phases. The results of any implemented measurement process will be posted to the
Division’s Web site.
RECOMMENDATION # 8: To address possible staffing problems, the division should use documented
workload metrics to perform an assessment of its current staffing levels and
determine its staffing needs. It should revisit the field pilot and make necessary
changes to reflect its understanding of its current staffing situation.
DGS RESPONSE # 8:
In the near future, the Division will initiate an assessment of its current staff levels and needs based on
available workload metrics. Further, as previously discussed, the Division will revisit the results of the field
pilot and determine the current feasibility of expanding its construction oversight for schools beyond
structural safety.
52 California State Auditor Report 2011-116.1
December 2011
Anna M. Caballero -7- November 17, 2011
CONCLUSION
The DGS is firmly committed to effectively and efficiently overseeing the implementation of the Field Act.
As part of its continuing efforts to improve this process, the DGS will take appropriate actions to address the
issues presented in the report.
If you need further information or assistance on this issue, please contact me at (916) 376-5012.
(Signed by: Fred Klass)
Fred Klass, Director
Department of General Services
California State Auditor Report 2011-116.1 53
December 2011
Comments
CALIFORNIA STATE AUDITOR’S COMMENTS ON THE
RESPONSE FROM THE STATE AND CONSUMER SERVICES
AGENCY, DEPARTMENT OF GENERAL SERVICES
To provide clarity and perspective, we are commenting on the
response to our audit report from the Department of General
Services (department). The numbers below correspond to the
numbers we placed in the margin of the department’s response.
The department first informed the Bureau of State Audits (bureau) 1
of this internal review on November 4, 2011, and provided a draft
copy of the review on November 10, 2011.
According to the Division of the State Architect’s (division) business 2
plan, this measurement tracks the percentage of projects that
the division has managed to categorize. It will not be useful as an
ongoing measure of the division’s performance. Further, it does not
measure the division’s efforts to follow up on uncertified projects.
However, the department says that an outreach plan will eventually
be developed sometime after June 30, 2012 that will measure
the success of the division’s efforts in reducing the number of
uncertified projects.
We appreciate that the department is willing to revisit the field 3
pilot, and look forward to additional information on the division’s
progress in implementing this recommendation in the department’s
60-day, six-month, and one-year responses.
The department asserts that the division has developed a 4
performance metric, but as the department states in Response #1
to Chapter 2 at page 49, the division is currently developing this
measurement tool and estimates it will be completed by June 30, 2012.
54 California State Auditor Report 2011-116.1
December 2011
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California
State
Government Organization and Economy
Department of Finance
Attorney General
State Controller
State Treasurer
Legislative Analyst
Senate Office of Research
California Research Bureau
Capitol Press