April 2015
San Francisco Bay Area
Rapid Transit District
Billions Are Needed to Repair and Replace
Infrastructure, Yet Availability of Funding Is Uncertain
Report 2013-118
COMMITMENT
INTEGRITY
LEADERSHIP
The first five copies of each California State Auditor report are free. Additional copies are $3 each, payable by check
or money order. You can obtain reports by contacting the California State Auditor’s Office at the following address:
California State Auditor
621 Capitol Mall, Suite 1200
Sacramento, California 95814
916.445.0255 or TTY 916.445.0033
OR
This report is also available on our Web site at www.auditor.ca.gov.
The California State Auditor is pleased to announce the availability of an online subscription service.
For information on how to subscribe, visit our Web site at www.auditor.ca.gov.
Alternate format reports available upon request.
Permission is granted to reproduce reports.
For questions regarding the contents of this report,
please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
For complaints of state employee misconduct, contact the California State Auditor’s
Whistleblower Hotline: 1.800.952.5665.
Elaine M. Howle State Auditor
Doug Cordiner Chief Deputy
April 28, 2015 2013-118
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the California State Auditor presents this audit
report concerning the San Francisco Bay Area Rapid Transit District’s (BART) financial projections and
workers compensation practices.
This report concludes that over the next 10 years BART will need billions in reinvestment to repair and
replace its infrastructure and other assets, but that its capital funding outlook is uncertain. BART has
identified over $9.6 billion in capital reinvestment projects, the majority of which is unfunded. Included in
its capital improvement program are three large capital projects to replace and expand its fleet of railcars,
expand its vehicle maintenance facility, and replace its train control system. While BART has identified
a mix of funding from federal, state, and local sources for the new railcar project it will need to commit
roughly $468.5 million of its own money to fully fund the 775-car project’s $2.5 billion budget. Furthermore,
all three of these projects face funding shortfalls in some years during the life of each project. In addition to
these three capital projects, which it expects to cost $4 billion, it has identified over $5.6 billion in capital
projects needed to repair or replace infrastructure that is in poor or very poor condition and to maintain
a state of good repair and expand the system.
Although we found BART’s focus on its future capital expenditure needs to be reasonable, its current
funding commitments and internal financial resources are insufficient to meet those needs. To begin
addressing this issue, the BART board of directors (board) held workshops in January 2015 to discuss
several funding options, which include, among other funding opportunities, ballot measures to issue
general obligation bonds. The board has yet to decide on an appropriate mechanism to finance BART’s
capital needs.
Separate from BART’s capital needs, its past financial projections for its operating budget between fiscal
years 2007–08 through 2012–13 proved to be accurate. BART management demonstrated a reasonable
track record of developing projections that generally fell within 5 percent of actual performance, indicating
that its projection methodology yielded valid results. Moreover, our impression is that BART’s projections
for fiscal years 2015–16 through 2018–19 appear to be reasonably plausible, although financial forecasts
are by nature imprecise estimates. In addition, we noted that audits conducted by the Department of
Industrial Relations and BART’s internal audit staff did not find any significant issues with BART’s workers’
compensation practices and their use of a third-party administrator. Finally, we found that violence against
BART employees did not continuously increase between fiscal years 2009–10 and 2013–14.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
621 Capitol Mall, Suite 1200 Sacramento, CA 95814 916.445.0255 916.327.0019 fax www.auditor.ca.gov
Blank page inserted for reproduction purposes only.
California State Auditor Report 2013-118 v
April 2015
Contents
Summary 1
Introduction 3
Audit Results
The San Francisco Bay Area Rapid Transit District Is Taking Steps to
Replace Its Aging Infrastructure but Must Secure Additional
Funding Sources for the Projects 9
BART’s Past Financial Projections Have Proved Accurate, and Current
Projections Appear Reasonable 17
The State and BART Have Both Reviewed BART’s Workers’ Compensation
Administrator, Finding No Significant Issues 22
Instances of Violence Against BART Employees Did Not Continuously
Increase Between Fiscal Years 2009–10 and 2013–14 23
We Did Not Find Any Evidence That BART Denied Employees Their
Original Positions After Recovering From Injuries or Inappropriately
Used Contract Employees 26
vi California State Auditor Report 2013-118
April 2015
Blank page inserted for reproduction purposes only.
California State Auditor Report 2013-118 1
April 2015
Summary
Results in Brief Audit Highlights . . .
The San Francisco Bay Area Rapid Transit District (BART)—the Our review of the San Francisco Bay Area
fifth largest heavy‑rail transit system in the United States, with a Rapid Transit District’s (BART) revenues,
weekday average of 400,000 users—faces uncertainty regarding expenditures, and workers’ compensation
how it plans to pay for all $9.6 billion in capital improvement practices highlighted the following:
and reinvestment projects it has identified. Further, BART’s fiscal
situation leaves little room for additional revenue allocations from » BART has identified $9.6 billion in
its operating budget to address these underfunded capital projects, capital improvement and reinvestment
requiring it to seek funding through bonds, tax increases, or projects, but its capital funding outlook
other means. is uncertain.
BART is currently engaged in three large capital projects (referred » BART faces cash‑flow shortfalls for some
to as the Big Three within BART) to replace and expand its fleet significant capital projects.
of railcars, expand its vehicle maintenance facility, and replace
its train control system. BART is also in the planning stages of » BART is considering options for additional
identifying its capital needs to repair or replace other infrastructure capital funding, which may include bond
beyond its Big Three projects. The need for BART to make measures, tax increases, or fare increases.
significant investments in its infrastructure is not surprising given,
for example, that 439 of BART’s 669 railcars have been in service » Past financial projections for its
since the district opened in 1972. Our review of the depreciation operating budget proved accurate and
schedules shows that the current fleet of railcars will reach the its current projections appear to be
end of their useful lives by 2026. According to BART’s assistant reasonably plausible.
general operations manager, it first attempted to replace its fleet
of railcars in 2004, but stopped due to a lack of funding. Similarly, » BART’s workers’ compensation
BART has been trying to replace its train control system since practices and their use of a third‑party
1994, but its first attempt went awry because of technological and administrator are adequate.
vendor‑acquisition issues that ultimately resulted in litigation and a
settlement with the vendor in December 2010. » Violence against BART employees did
not continuously increase between fiscal
Although our audit found that BART’s focus on its future capital years 2009–10 and 2013–14.
expenditure needs appears reasonable, BART faces uncertainty
regarding how it will pay for anticipated capital spending. For
example, although it anticipates receiving sufficient funding from a
mix of federal, state, local, and internal revenue sources for 775 new
railcars and an expanded maintenance facility, BART still faces
potential cash‑flow shortfalls in some years in which the projects’
expenses are forecasted to exceed the revenues designated for these
projects. BART also has yet to secure all of the necessary funding
for the train control system project.
In addition to its Big Three capital projects currently planned,
which it expects to cost $4 billion, BART has identified over
$5.6 billion in capital projects needed to repair or replace
infrastructure that is in poor or very poor condition and to
maintain a state of good repair and expand the system. This need
touches on all aspects of BART’s infrastructure, including tracks,
2 California State Auditor Report 2013-118
April 2015
stations, and power systems. In response to federal requirements,
BART began implementing a capital asset management program in
fiscal year 2012–13. Although this process is still evolving, BART is
working toward fully implementing this program, which identifies
and prioritizes capital projects based on risk.
BART’s ability to meet its operating and capital expenditure needs
is constrained by operating budget deficits that are projected
beginning in fiscal year 2015–16. These operating budget deficits
are projected to grow from $5.9 million in fiscal year 2015–16 to
$57.3 million in fiscal year 2017–18. As a result, BART will not be
able to rely on its operating budget to pay for its capital needs.
Instead, it is considering several options to close the capital funding
shortfall, including placing revenue measures on the 2016 or 2018
ballot for general obligation bonds or sales tax increases.
To determine the accuracy of its projected revenues and
expenditures, we compared BART’s operating projections from
fiscal years 2007–08 through 2012–13 to its actual financial
performance. BART management demonstrated a reasonable track
record of developing projections that generally fell within 5 percent
of actual performance, indicating that its projection methodology
yielded valid results. We also reviewed significant components and
the key assumptions underlying BART’s financial forecasts for fiscal
years 2015–16 through 2018–19. For these forecasts, BART used a
similar projection methodology, which employed modest growth
assumptions, generally between 3 percent and 5 percent. Although
financial forecasts are by nature imprecise, our impression is
that BART’s projections for fiscal years 2015–16 through 2018–19
appear plausible.
Agency Comments
BART is aware that it needs to develop a plan to fund its significant
capital projects and, as our report acknowledges, it is evaluating
how best to secure the additional funding. We met with BART’s
executive management in mid‑March 2015 to discuss our report’s
conclusions. We also provided BART with a copy of our draft
report in early April 2015. BART’s management provided limited
oral comments that were technical in nature. We considered
BART’s comments when preparing this public report.
California State Auditor Report 2013-118 3
April 2015
Introduction
Background
The San Francisco Bay Area Rapid Transit District (BART) was
created by the California Legislature in 1957. Construction of its
rail system began in 1964, and BART opened its doors to the public
in 1972. According to BART, it is the fifth largest heavy‑rail transit
system in the United States, with a weekday average of more than
400,000 riders. BART infrastructure includes 104 miles of total
track, with 44 transit stations spread over 21 cities. BART operates
and maintains a wide variety of capital‑intensive assets and physical
infrastructure throughout the San Francisco Bay Area, such as
railcars, tracks, stations, and maintenance facilities. It estimates that
the replacement value of its infrastructure is $21 billion. According
to BART’s Short Range Transit Plan and Capital Improvement
Program, dated October 2014, most of this infrastructure is over
40 years old and is at, or close to, the end of its useful life. In fact,
BART staff estimate that $6.5 billion of BART’s infrastructure
is now in poor or very poor condition. BART is planning major
investments over the next 10 years that will add capacity and
expand the system while also improving its existing infrastructure.
Organizational Structure
BART is governed by a nine‑member, publicly elected board
of directors (board) representing voters in Alameda, Contra
Costa, and San Francisco counties. San Mateo County is served
by six BART stations but is not represented by a member of the
BART board. BART’s general manager, general counsel, controller/
treasurer, and district secretary are board‑appointed officers and
report directly to the board.
BART’s activities relating to transit construction, funding,
and planning also fall under the authority of the Metropolitan
Transportation Commission (MTC), the agency responsible
for transportation planning, coordinating, and financing for the
nine‑county San Francisco Bay Area. This entity monitors transit
operators’ budgets, conducts performance audits, and ensures that
the region’s numerous bus, rail, and ferry systems are in sync in
terms of their routes, fares, transfer policies, schedules, passenger
information, and facilities. The MTC also reviews any application
for federal or state grant money submitted by local transit agencies,
such as BART, to ensure that the application is consistent with the
region’s transportation plan.
4 California State Auditor Report 2013-118
April 2015
BART has five collective bargaining agreements with labor unions,
covering over 85 percent of its workforce. The remainder of BART’s
staff are not represented by a union. BART also employs its own
police force to provide safety for riders and reduce crime. As of
fiscal year 2014–15, BART employed more than 3,000 people.
Budget
BART relies on financial assistance from local governments and
other external entities to help fund its operations and pay for
capital projects. Between fiscal years 2009–10 and 2012–13, as the
San Francisco Bay Area’s economy recovered from the recession,
BART’s revenues from fares and other operating sources increased
as a proportion of its total revenue sources. However, as shown
in the fiscal year 2012–13 income statement in Table 1, BART still
relied on sales tax revenue and other forms of financial assistance to
help pay for its operating expenses.
Table 1
San Francisco Bay Area Rapid Transit District Income Statement
Fiscal Year 2012–13
INCOME
FISCAL YEAR 2012–13 INCOME STATEMENT (IN MILLIONS)
Operating revenue (i.e., fares and parking revenue) $443.3
Net operating expenses (712.5)
Net Operating Loss (269.2)
Nonoperating revenue* and other expenses (net) 245.8
Change in Net Position Before Contributions (23.4)
Financial assistance for capital projects† 419.9
Change in net position‡ $396.5
Source: San Francisco Bay Area Rapid Transit District’s (BART) financial statements, fiscal year 2012–13.
* Nonoperating revenue includes sales tax and property tax revenue, and other financial assistance
revenues provided by state and local entities to support ongoing operations.
† Financial assistance consists of funding received from federal, state, and local agencies to fund
capital projects outside of the operating budget.
‡ Change in net position reflects the change in BART’s assets over its liabilities from the prior
fiscal year. In fiscal year 2012–13, BART’s total net position was $5.78 billion, an increase of
$396.5 million (shown in the table above) from the prior year’s total of $5.39 billion.
BART also relies on external contributions from federal, state, and
local governments to fund a significant amount of its planned capital
expenditures. For example, BART is relying on roughly $2.4 billion in
funding from MTC to help pay for its new railcars and a train control
system. The funding provided by the MTC will come from a variety
of sources including federal, state, and potentially local funds.
California State Auditor Report 2013-118 5
April 2015
Scope and Methodology
The Joint Legislative Audit Committee (audit committee) directed the
California State Auditor to perform an audit of BART’s revenues,
expenditures, and workers’ compensation practices. Table 2 outlines the
audit committee’s objectives and our methods for addressing them.
Table 2
Audit Objectives and the Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, Reviewed relevant laws, regulations, and other background materials. We also reviewed the collective
rules, and regulations significant bargaining agreements (agreements) between the San Francisco Bay Area Rapid Transit District (BART) and
to the audit objectives. its unions.
2 Review and assess annual We obtained BART audited financial statements for fiscal years 2008–09 through 2012–13 and identified
financial statements for the the significant sources of revenues and expenses. Further, we examined the classifications of a selection of
most recent four fiscal years. 40 BART employees between fiscal years 2009–10 through 2012–13. Our results showed that all 40 selected
In addition, identify salaries by employees were paid appropriately according to their job classifications.
employee classification.
3 Review revenues and We selected 40 operating transactions from fiscal years 2009–10 through 2012–13. We determined that
expenditures over the most recent each of the expense transactions we reviewed were reasonably justified and often resulted from competitive
four fiscal years to determine procurements. Further, we noted that BART management and accounting staff approved payment.
whether they were reasonable
and allowable.
4 Review and assess projected • Obtained BART’s projections of revenue and expenditures for fiscal years 2007–08 through 2012–13 and
revenues and expenditures for the compared projected amounts to actual performance.
next four fiscal years, including an • Obtained BART’s projections of revenue and expenditures for fiscal years 2015–16 through 2018–19 and
assessment of the projected costs determined how BART models future revenues and expenditures, we then applied auditor judgment to assess
and funding sources for capital the reasonableness of BART’s projections as discussed further in the body of our audit report.
equipment replacement.
• Reviewed and assessed BART’s plans and estimated costs for its three biggest capital projects. For each of the
three projects, we evaluated the key inputs used to estimate costs. We also determined what key assumptions
BART made in its expenditure projections and whether it had identified funding sources for each of these
three projects.
5 For the time period beginning
in 2009 through June 30, 2013,
perform the following:
a. Determine for a selection of • Reviewed the 2005 and 2010 audits by the Department of Industrial Relations’ Division of Workers’
cases whether BART followed all Compensation (DWC) of BART’s third‑party workers’ compensation administrator, Athens Administrators.
applicable laws, rules, policies, We also reviewed the nature of any violations identified by DWC during its review of records pertaining to
and procedures related to BART employees from its 2010 audit.
workers’ compensation practices. • Determined what steps BART took to assess whether Athens Administrators was performing its
job adequately.
• Obtained the contract between BART and Athens Administrators to determine if there were any financial
incentives for limiting workers’ compensation payments. We found no such incentives in the contract.
continued on next page . . .
6 California State Auditor Report 2013-118
April 2015
AUDIT OBJECTIVE METHOD
b. Review BART’s workers’ Selected 20 workers’ compensation claims for each of the four fiscal years using the data obtained from
compensation practices to Athens Administrators and determined whether the employees were given back their old position after being
determine whether BART used cleared to return to work by their treating physician using personnel records. We also determined whether
contract employees in lieu of the employee accepted a temporary modified assignment if cleared by their treating physician.
“ready to return to work” union
employees. If so, determine
whether this practice resulted
in a cost savings to BART.
c. Review the number of • Reviewed data obtained from the administrator’s claims database and BART’s violence in the workplace
reported batteries against database, and reports from the BART police department, to determine if assaults and batteries against
BART employees to determine BART employees were increasing. We also reviewed the data from the administrator to determine
whether this number whether costs associated with assaults and batteries had increased during our audit period.
has increased and, if so, • Interviewed BART staff responsible for the violence in the workplace database to determine how
determine the impact this instances were entered into the system, whether the data are reviewed for accuracy, and whether they
increase has had on workers’ are used to track and monitor possible increases in the instances of violence against employees.
compensation claims.
d. Determine what actions BART Interviewed BART management to determine what steps it has taken to reduce instances of violence
has taken or plans to take against its employees and whether it monitors and evaluates the success of its specific strategies. We also
to reduce batteries against obtained documentation to support BART’s programs and activities aimed at reducing instances of violence
its employees. against employees.
e. Compare the ratio of We compared the percentage of management relative to the total workforce at BART to other transit
management to labor agencies with comparable average weekday ridership. We selected the Los Angeles County Metropolitan
employees at BART to those of Transportation Authority (12 percent), the Washington Metro Area Transportation Authority (8 percent), and
rail systems with comparable the Southeastern Pennsylvania Transportation Authority (19 percent) to compare to BART (13 percent). We
daily ridership. found the number of managers at BART is generally consistent with these other transportation authorities.
6 Review and assess any other We did not identify any other significant issues.
issues that are significant to the
BART District.
Sources: California State Auditor’s analysis of Joint Legislative Audit Committee audit request number 2013‑118, and information and documentation
identified in the table column titled Method.
Assessment of Data Reliability
In performing this audit, we obtained electronic data files
extracted from the information systems listed in Table 3. The
U.S. Government Accountability Office, whose standards we are
statutorily required to follow, requires us to assess the sufficiency
and appropriateness of computer‑processed information that
we use to support findings, conclusions, or recommendations.
Table 3 describes the analyses we conducted using data from these
information systems, our methodology for testing them, and the
limitations we identified in the data.
California State Auditor Report 2013-118 7
April 2015
Table 3
Methods Used to Assess Data Reliability
INFORMATION SYSTEM PURPOSE METHOD AND RESULT CONCLUSION
San Francisco Bay Area To determine the For a random selection of 29 records of reported violence, Not sufficiently reliable for
Rapid Transit District number of instances we attempted to verify that key data elements match source the purposes of the audit.
(BART) of assaults and documentation. However, we could not verify the accuracy of As discussed in the Audit
batteries against six of the 29 records we reviewed because source documentation Results, we noted that this
Violence in BART employees. was unavailable. In other instances, we noted that source database shows a similar
the Workplace documentation was available but was limited in a manner that pattern to separate data
Program database prevented us from verifying certain key data fields. Therefore, we maintained by Athens
did not conduct completeness testing on these data. Administrators (BART's
BART's data related to workers’ compensation
specific instances of claims administrator), we
violence against BART do not present specific
employees from fiscal data from BART's Violence
years 2008–09 through in the Workplace Program
2012–13 database in our report.
BART To determine whether We did not perform accuracy and completeness testing of the Undetermined reliability for
BART employees are Peoplesoft System payroll data because the system is primarily the purposes of this audit.
Peoplesoft System being paid within paperless and sufficient hardcopy source documentation was
their classifications. not available for review. Alternatively, following U.S. Government
BART's personnel Accountability Office guidelines, we could have reviewed the
and payroll data from adequacy of selected system controls that include general and
January 2009 through application controls. However, we did not conduct these reviews
December 2013 because this audit is a one‑time review of a local transit system and
we determined that it did not warrant the same level of resource
investment as a state agency whose system produces data that may
be used during numerous future audit engagements.
BART To make a selection We randomly selected 29 contracts and traced key data elements We used information from
of contracts for to source documentation and did not identify any issues. To assess this spreadsheet to select
Excel Spreadsheet testing to determine the completeness of the data, we haphazardly selected 29 contracts 20 contracts for substantive
Listing of Contracts whether BART and found that the spreadsheet lacked information for six of testing. We found BART's
documented its reasons 29 contracts included in our completeness testing. spreadsheet was incomplete
BART's procurement for using contract for the purpose of selecting
data for public works labor instead of contracts to test whether
construction contracts unionized employees. BART documented its
valued at over $10,000 reasons for using contract
and all other contract labor instead of unionized
types over $100,000 employees. Since we did not
from fiscal make statistical projections
years 2009–10 to based on our selected
2012–13 items, we believe our use of
this data was appropriate
to support our report's
conclusions.
Athens Administrators To determine the We performed data‑set verification procedures and electronic Sufficiently reliable for the
number of workers’ testing of key data elements and did not identify any issues. We purposes of the audit.
SIMS Claims Database compensation randomly selected 29 workers’ compensation claims and traced key
claims related to data elements to source documentation and did not identify any
Athens Administrators' violence against BART issues. To assess the completeness of Athens Administrators' SIMS
workers’ compensation employees and the data, we haphazardly selected 29 workers’ compensation claims
claims data for fiscal amount paid for the and traced them from Athens Administrators' source documents
years 2009–10 through resulting workers back to SIMS and found the data to be complete.
2012–13 compensation claims.
Source: California State Auditor’s analysis of various documents, interviews, and data obtained from BART.
8 California State Auditor Report 2013-118
April 2015
Blank page inserted for reproduction purposes only.
California State Auditor Report 2013-118 9
April 2015
Audit Results
The San Francisco Bay Area Rapid Transit District Is Taking Steps to
Replace Its Aging Infrastructure but Must Secure Additional Funding
Sources for the Projects
The San Francisco Bay Area Rapid Transit District (BART) is engaged
in three large capital projects expected to cost $4 billion (referred
to as the Big Three within BART) to replace and expand its fleet of
railcars, expand its vehicle maintenance facility, and replace its train
control system. Aside from these three projects, BART is also in the
planning stages of identifying capital needs to repair or replace much
of its other infrastructure that is in poor or very poor condition, with
a goal of maintaining a state of good repair. Although BART allocates
some of its internal operating revenues toward capital expenditures,
capital projects are funded mainly by external capital contributions
from federal, state, and regional funding sources. BART has secured
adequate funding for two of its Big Three projects: replacing its fleet
of railcars and expanding its vehicle maintenance facility. However,
it has yet to secure all of the necessary funding for the train control
system or for the other necessary repairs to its infrastructure. BART
is currently considering a number of funding opportunities to help
pay for these capital improvements, which may include bond sales or
sales tax increases.
BART has recently taken steps to improve its process for planning
capital improvements. Specifically, in fiscal year 2012–13, BART
began implementing an asset management program. According to
BART’s manager of operations and planning, the program is meant
to integrate a consistent, risk‑based framework for planning capital
expenditures and to better inform long‑term financial planning. As
such, it has implications for reducing both capital and operating
expenditures, such as maintenance expenses.
BART Has Received Commitments for Most of the Funding for Its Big
Three Capital Projects, but It Anticipates Cash‑Flow Problems
A ridership forecast completed by BART estimated that ridership
will grow by 36 percent between 2012 and 2025, and that peak
ridership during the morning and evening peak hours will increase
by 36 percent and 42 percent, respectively. To increase its service
capacity and meet this expected growth in ridership, a study funded
by the Metropolitan Transportation Commission (MTC) and the
California Department of Transportation (Caltrans) recommended,
in June 2013, that BART deploy a modern 1,000‑railcar fleet,
implement a modernized train control system to allow more trains
to operate at the same time, and develop larger and more efficient
maintenance facilities.
10 California State Auditor Report 2013-118
April 2015
BART’s original fleet of 439 railcars In addition to the need to expand capacity for the expected growth
has been in service since BART in ridership, BART’s current railcar fleet is in need of replacement
opened in 1972 and is currently over because of its age. BART’s original fleet of 439 railcars has been in
42 years old, while its two other service since BART opened in 1972 and is currently over 42 years
more recently added fleets are over old, while its two other more recently added fleets are over 26 and
26 and 20 years old, respectively. 20 years old, respectively. According to BART’s assistant general
operations manager, BART first attempted to replace its fleet of
railcars in 2004, but stopped due to a lack of funding. To continue
providing reliable service as its railcars approach the end of their
typical useful life, while meeting projected increases in future
ridership, BART contracted with a vendor in 2012 to provide
775 new railcars to be constructed and delivered incrementally
over several years, with the first pilot cars to be delivered in late
fiscal year 2014–15 and the final cars in early fiscal year 2021–22. At
some point in the future, BART hopes to purchase an additional
225 railcars through a separate procurement effort, to bring its total
fleet up to 1,000.
BART’s decision to procure most of its new railcar fleet all at
once seems consistent with the approaches taken by other transit
agencies. According to a 2010 U.S. Government Accountability
Office (GAO) report, heavy‑rail transit agencies have unique
infrastructure requirements, such as weight limitations, that
necessitate a great deal of customization in their railcar designs.
According to railcar manufacturers interviewed for the GAO
report, the order size necessary to capitalize on economies of scale
and reduce per‑car prices varies depending on a variety of factors,
including the degree of customization of the car design. In general,
producing more cars using the same design and production line
reduces the cost per car due to the manufacturer’s ability to spread
the design and other fixed production costs over a larger number
of cars. The GAO report states that transit agencies often replace
entire fleets or generations of railcars at one time as the railcars
approach their replacement age—typically 25 years, at which point
their lives can be extended with an overhaul. This follows Federal
Transit Administration guidelines for transit agencies to use railcars
for a minimum of 25 years. According to BART, its original fleet of
439 railcars was refurbished between 1997 and 2002 after roughly
25 years of operation and is now over 40 years old.
BART’s depreciation schedules show that the current fleet of
669 railcars will all have reached the end of their useful lives by
2026. More than half (422 cars) will have reached the end of their
useful lives by fiscal year 2016–17. BART awarded a contract in 2012
for 410 new railcars and, in 2013, exercised contract options allowing
it to procure an additional 365 cars, for a total of 775 new railcars.
However, BART does not expect to take delivery of its first 360 new
railcars until March 2019. Figure 1 shows when BART’s current
669 railcars will reach the end of their useful lives, along with the
California State Auditor Report 2013-118 11
April 2015
expected delivery of the new cars. Based on these data, it appears
that BART will need to continue to maintain many of its current
railcars beyond their useful lives until it can obtain the new cars.
Figure 1
Railcars With a Useful Life Remaining in the Current Fleet Versus Expected Delivery of New Railcars
sracliaR
fo
rebmuN
800
New railcars received*
6
700
5
600
500 4
400
3
300
2
200 Railcars with a useful life remaining
in the current fleet†
100
1
0
2012–13 2013–14 2014–15 2015–16 2016–17 2017–18 2018–19 2019–20 2020–21 2021–22 2022–23 2023–24 2024–25 2025–26
Fiscal Year
Sources: California State Auditor’s analysis of the San Francisco Bay Area Rapid Transit District’s (BART) railcar depreciation schedules and new railcar
procurement schedule.
* The total number of new railcars is based on the procurement schedule and the estimated number of railcars to be delivered to BART by the end of
each fiscal year. The following delivery milestones labeled above are based on the new railcar procurement schedule:
1. Delivery of the 10th pilot vehicle 4. Delivery of the 510th railcar
2. Delivery of the 260th railcar 5. Delivery of the 660th railcar
3. Delivery of the 360th railcar 6. Delivery of the 775th railcar
† The number of railcars with a useful life remaining in the current fleet is based on our analysis of depreciation schedules and does not imply that
the railcars will be retired from service during the same year they approach the end of their typical useful lives.
BART followed a competitive bid process to award the contract
for the new railcars, and will pay more than $1.5 billion to obtain
the 775 cars, which will be delivered incrementally through fiscal
year 2021–22. Overall, BART has budgeted roughly $2.5 billion
for the project. Aside from the $1.5 billion for its prime vendor,
BART’s budgeting approach makes considerations for a healthy
reserve amount for unexpected contingencies (nearly $360 million,
or roughly 14 percent of the total budget), allowances for growth
in project costs over the several years of the project (another
$360 million), amounts for expected sales tax ($188 million),
12 California State Auditor Report 2013-118
April 2015
and consideration for the costs of its own staff and other
supporting contractors associated with the railcar project (roughly
$143 million), for a total budget of over $2.5 billion.
As shown in Figure 2, BART is relying on a mix of federal, state, and
regional funding—on top of its own contributions from operating
revenues—to cover the railcar project’s budget. Funding provided
through commitments made by the MTC—a transportation
planning and financing agency for the nine‑county San Francisco
Bay Area—accounts for most of the project’s funding. In particular,
the MTC has issued two resolutions committing nearly $2 billion
in funding for a total of 873 railcars.1 Although specific funding
sources and amounts are subject to change based on the availability
of funds and on whether BART awards another procurement
contract beyond the current 775‑car order, the MTC’s resolutions
call for roughly $1.6 billion to come from federal funds and
$385 million to come from other state and local sources (such as
bridge tolls and funds from the State’s Cap‑and‑Trade Program,
which seeks to reduce greenhouse gas emissions). Further, BART
was able to secure a grant from Caltrans to use $140 million in
high‑speed rail bond funds because the BART system is expected
to be an intercity rail connector with California’s future high‑speed
train system. BART is also planning to expand into the Santa Clara
region and received a commitment from the Santa Clara Valley
Transportation Authority amounting to roughly $215 million for
60 of the 775 new railcars to serve that expansion. Ultimately,
if all of these funding commitments come to fruition, which is
uncertain, BART would need to commit roughly $468.5 million of
its own money to fully fund the 775‑car project’s $2.5 billion budget.
BART’s financial model, which it uses to project its future revenues
and expenses over the long term, allocates a total of more than
$600 million from fiscal years 2013–14 through 2027–28 toward its
ultimate goal of obtaining 1,000 new railcars.
The railcar project faces funding Despite having funding commitments for most of the railcar
shortfalls in some years during the project, the project faces funding shortfalls in some years during
project’s life because the funding the project’s life because the funding it expects to receive will be
BART expects to receive will be insufficient to pay for estimated project costs at particular times. For
insufficient to pay for estimated example, BART expects to spend roughly $2.1 billion of its $2.5 billion
project costs at particular times. budget (or 84 percent of the project) between fiscal years 2016–17
and 2020–21, the time frame during which it expects to take delivery
of its new railcars. However, without additional financing, BART
expects to receive only $983.7 million in funding during this same
time period. Beginning in fiscal year 2021–22, BART expects that its
expenditures for the project will significantly decrease, while it will
continue to receive funding, primarily from federal funds previously
1 The MTC’s commitment of nearly $2 billion includes $1.76 billion for the first 775 railcars currently
scheduled for delivery, with an additional $238.5 million for an additional 98 railcars that have yet
to be procured.
California State Auditor Report 2013-118 13
April 2015
committed by the MTC and from payments made by the Santa Clara
Valley Transportation Authority. Given the timing of the expected
cash flows, BART will need to identify financing so that it will have
adequate cash on hand to cover payments to its vendor.
Figure 2
Projected Revenue Sources for the New Railcar Project
High-Speed Rail Bond (State)—$140 Million (5%)
Santa Clara Valley Transportation
Authority (Local)—$215.4 Million (7%)
Bay Area Rapid
$2.9 Billion Transit District—
$551 Million (19%)
Metropolitan Transportation
Commission (mostly federal funds)
$1.99 Billion (69%)
Source: California State Auditor’s analysis of new railcar project cash‑flow summary and
funding agreements.
Note: The figure reflects total funding agreements amounting to $2.9 billion for 873 cars, or 98
more cars than the 775 under contract for delivery.
BART also faces cash‑flow challenges for the two other projects
that make up the Big Three. It has taken the initial steps to expand
its Hayward maintenance facility to service the new fleet of
railcars, and it projects that these expanded facilities will cost over
$432 million. According to an analysis it prepared in May 2014,
BART expects that by fiscal year 2015–16 the funding it will have
received for the maintenance complex will be inadequate to
cover expected spending, likely necessitating the need for interim
financing that can be paid back at a later date. In addition, BART
has been trying to replace its train control system since 1994,
although its first attempt went awry because of technological and
vendor‑acquisition issues that ultimately resulted in litigation
and a settlement with the vendor in December 2010. It is currently
preparing a request for proposals to find a vendor to supply
the new train control system, which it expects will cost over
$915 million. This project—for which BART has yet to identify all
necessary funding—will have cash‑flow challenges as early as fiscal
year 2016–17. To address the temporary cash needs of the Big Three
projects, MTC has set aside additional money to cover the cost of
14 California State Auditor Report 2013-118
April 2015
financing loans against future federal funds that, as noted earlier,
will continue to be available after the peak expenditure years of the
projects. Although the terms and financing of the loans have yet to
be finalized, the senior planner we spoke with at MTC anticipates
that the loan structure will be finalized and ready for use by the end
of fiscal year 2015–16.
In addition to the Big Three capital projects just discussed, BART
has identified other capital projects needed to maintain or enhance
its passenger rail service. These include numerous projects focused
on system reinvestment, such as improving the quality of BART’s
various train stations (for example, upgrading escalators, elevators,
and station lighting), replacing electrical substations that supply
the power to help move BART’s trains, and pursuing earthquake
According to its fiscal year 2014–15 safety projects. According to its fiscal year 2014–15 capital
capital improvement program, improvement program, BART’s total capital needs are projected to
BART’s total capital needs are cost over $9.6 billion between fiscal years 2014–15 and 2023–24. In
projected to cost over $9.6 billion addition to its Big Three capital projects currently planned, which
between fiscal years 2014–15 and it expects to cost $4 billion, BART has identified over $5.6 billion in
2023–24. capital projects needed to repair or replace infrastructure that is
in poor or very poor condition, to maintain a state of good repair,
and to expand the system.
BART Is Planning to Seek Voter Approval for Additional Capital Funding
Because current funding commitments and its net operating cash
flow are insufficient to pay for BART’s capital needs, BART is
currently in the process of determining how it will pay for its capital
projects. The BART board of directors (board) held workshops
in January 2015 to discuss several capital funding options, which
include ballot measures to issue general obligation bonds, raising
sales or property taxes, increasing fares, and other opportunities.
The board also discussed the results of a rider survey to gauge
support for potential funding measures on the November 2016
ballot, which showed 66 percent and 64 percent support,
respectively, for a ¼‑cent sales tax increase and a $4.5 billion bond
measure. As shown in Figure 3, BART’s survey also found greater
support for lower levels of bond funding.
According to BART’s assistant general manager, based on the
survey results and the amount of funding needed, the board
showed a preference for the bond measure option over the sales and
property tax increases and the fare increases. However, the board
was still undecided as to the amount of the bond and whether
to place a funding measure on the 2016 ballot or wait until the
2018 election, because of uncertainty regarding voter support and
competition with other transit agency funding measures in 2016.
The board directed BART staff to conduct another survey later in
California State Auditor Report 2013-118 15
April 2015
the year to better gauge voter support for different amounts of bond
funding. The assistant general manager also stated that until BART
is able to secure additional funding for capital projects, the backlog
of unfunded capital needs would continue to grow, likely requiring
more maintenance spending from future operating budgets, and
that while BART had no specific contingency plans if no additional
revenue measures are passed, it will likely have to enact a number of
cost‑cutting measures that could result in less reliable rail service.
Figure 3
Results From the San Francisco Bay Area Rapid Transit District’s September 2014 Survey of Voter Support for
Capital Funding Measures
74% $850 million bond (73%)
$1.5 billion bond (72%)
72
1/8-cent ($1.4 billion) sales tax (71%)
70
$3 billion bond (67%)
68
Two-Thirds Vote Threshold
1/4-cent ($2.8 billion) sales tax (66%)
66
$4.5 billion bond (64%)
64
62
$0 $1 $2 $3 $4 $5
sesnopseR
”seY“
fo
egatnecreP
Funds Generated (in Billions)
Source: San Francisco Bay Area Rapid Transit District (BART) Marketing and Research Department’s January 29, 2015, presentation to BART’s board
of directors.
BART Is Working Toward Fully Implementing a New Capital Asset
Management Program That Identifies Assets for Replacement Based
on Risk
According to the manager of operations and support (manager),
before it implemented its current capital asset management
program, BART did not have a systemwide approach for selecting
capital projects for funding. Instead, capital projects were selected
and funded through an annual operating and capital budgeting
process in which each department within BART would make an
assessment of its needs and present capital projects to BART’s
executive team for consideration. A final list would then be
submitted to BART’s board for approval. According to the manager,
capital needs were informed by each department’s knowledge
16 California State Auditor Report 2013-118
April 2015
and judgment, but BART did not have a holistic assessment of
its capital assets, nor did it have a way to consistently prioritize
potential capital projects based on risk. However, BART was not
alone in its lack of a comprehensive asset management program.
In a 2009 study, the Federal Transit Administration described
four components that are most relevant for a comprehensive
asset management program: asset inventories, asset condition
assessments, decision support tools and processes, and an
investment prioritization process. The study surveyed seven large
rail transit agencies, including BART, to reflect on the current use
of asset management processes within the transit industry, and
noted that while all seven agencies maintained comprehensive asset
inventories for capital planning purposes, other asset management
practices—such as the use of a rigorous process to rank and
prioritize investment needs—were lacking. For example, the study
found that the majority of the seven agencies tended to rely on
investment prioritization processes that were both informal (i.e., the
process is not well defined) and implicit (the agencies’ investment
goals and objectives are not explicitly stated or defined). The study
also concluded that rail transit agencies generally lagged behind
the rest of the transportation sector, most notably highways, in the
development and implementation of asset management practices.
In October 2012 the federal government adopted legislation
requiring transit agencies that receive federal financial assistance,
such as BART, to develop a transit asset management plan that
includes, at a minimum, capital asset inventories and condition
assessments, decision support tools, and investment prioritization
for capital projects. Although, the federal Department of
Transportation—the agency responsible for implementing this
legislation—has yet to adopt final regulations that define how these
provisions will be enforced, BART responded to the requirement
for a transit asset management plan, in part, by implementing its
own asset management program.
In fiscal year 2012–13 BART began In fiscal year 2012–13 BART began developing its asset management
developing its asset management program, a process of systematically surveying its assets and
program, a process of surveying identifying risks, developing capital projects to address those risks,
its assets and identifying risks, and prioritizing projects for financing when funding becomes
developing capital projects to available. Because the asset management program is still evolving,
address those risks, and prioritizing BART has yet to formalize the process in a procedural manual.
projects for financing when funding According to the manager, the asset management process begins
becomes available. with compiling an inventory of all of BART’s assets and gathering
information on each asset’s condition, function, and capacity. BART
then uses the asset inventory to identify and analyze risks and
develop treatments, such as mitigation options or capital projects,
to address identified concerns. For example, BART’s analysis of its
station/tunnel lighting identified risks for worker and patron safety
from poor lighting in its tunnels, and BART developed a lighting
California State Auditor Report 2013-118 17
April 2015
retrofit project to address this risk. BART staff develop proposals
for capital projects such as the lighting retrofit. They then submit
these proposals for rating and approval to be included in BART’s
capital needs inventory. Managers in charge of assets rate project
proposals using a consistent set of criteria, including risk, safety,
and compliance with federal, state, or local laws, and then develop
an overall project ranking for the capital needs inventory. Other
than the Big Three projects, these projects in the capital needs
inventory make up most of BART’s $9.6 billion in capital
needs between fiscal years 2014–15 and 2023–24. Management
then selects projects for funding from the top‑ranked projects in
the capital needs inventory. Although BART has yet to identify
a funding mechanism to address all of its capital needs, its asset
management program’s risk‑based approach for prioritizing capital
projects represents an improvement in BART’s process for selecting
capital projects for funding.
BART’s Past Financial Projections Have Proved Accurate, and Current
Projections Appear Reasonable
We found that BART’s projections for its operating budgets
for fiscal years 2007–08 through 2012–13 were reasonably
consistent with BART’s actual financial performance, indicating
that its projection methodology yields valid results. Further, our
assessment of BART’s financial projections for fiscal years 2015–16
through 2018–19 found that BART’s financial model considers
numerous inputs with various assumptions when projecting
future financial results. Our review focused on the output from
BART’s financial model for certain significant line items, such
as passenger fare revenue, sales tax revenue, and labor costs,
and then examined the amount of expected growth in these
revenue and expense items. Recognizing that financial forecasts
are by nature imprecise and are essentially estimates, we found We found that BART’s financial
that BART’s financial model uses modest growth assumptions model uses modest growth
(generally between 3 percent and 5 percent) that produce results assumptions—generally between
that appear plausible. However, BART’s ability to make significant 3 percent and 5 percent—that
financial contributions to its various capital improvement projects produce forecast results that
is uncertain, given its projected deficits. As a result, BART appear plausible.
acknowledges the possibility that it may need to either curtail the
amount of its planned capital contributions or seek additional
financial resources, such as through short‑term borrowing, to
address its needs.
In September 2007 BART released a planning document titled
Short‑Range Transit Plan (FY 08 through FY 17) & Capital
Improvement Program (FY 08 through FY 32) (2007 transit plan)
that projected operating revenues and expenditures for the next
10 fiscal years. These revenues and expenditures pertain to the
18 California State Auditor Report 2013-118
April 2015
operating budget and are organized separately from the external
funding contributions and capital expenditures discussed previously,
although a portion of operating revenues are allocated for capital
BART’s financial performance is projects.2 BART’s financial performance is significantly influenced
significantly influenced by certain by certain key revenues—such as passenger fare revenue and the
key revenues—such as passenger proceeds from local sales taxes—and by its operating expenses, which
fare revenue and the proceeds include the amounts it pays to its employees and its suppliers. To
from local sales taxes—and by its test the accuracy of BART’s projections, we compared its estimates
operating expenses. for certain key revenue and expenditure items from the 2007 transit
plan to its subsequent actual financial performance as noted in its
Short Range Transit Plan and Capital Improvement Program (FY 15
through FY 24) (2014 transit plan). To ensure that the 2014 transit
plan contained reasonable revenue and expenditure data from prior
years, we further compared this information against similar data from
BART’s audited financial statements.
Ultimately, our analysis found that BART’s previous projections
compared favorably to its actual financial performance, with estimates
generally being within 5 percent of actual revenue or spending. For
example, the 2007 transit plan estimated that the average weekday
ridership would steadily increase from just under 350,000 people in
fiscal year 2007–08 to nearly 380,000 in fiscal year 2012–13. Actual
ridership closely mirrored this estimate, increasing to just over
390,000 in fiscal year 2012–13 (a difference of less than 4 percent).
Further, BART’s estimated and actual passenger revenue varied
by less than 5 percent overall during fiscal years 2007–08 through
2012–13. BART also did well in predicting its labor and the amounts
that would be paid to its suppliers. In the 2007 transit plan, BART
predicted that its labor and supplier costs would gradually increase to
a combined total of $580.5 million during fiscal year 2012–13. Actual
performance closely mirrored this projection, with BART actually
paying $567 million during that same year. This actual spending differs
from the projection by only $36.2 million (or roughly 6 percent of the
original estimate).
One area where BART demonstrated difficulty was in its estimation
of sales tax revenue. BART receives sales tax revenue from amounts
collected within its jurisdiction by the State Board of Equalization.
It uses the sales tax revenue it receives to pay for a portion of its
operating expenses and to make principal and interest payments on
its various sales tax revenue bonds.3 In its 2007 transit plan, BART
2 According to BART’s assistant general manager, it has separate projections for the operating and
capital budgets because most funding for capital expenditures is from federal or state sources,
and some of it is dedicated to specific capital projects. The assistant manager went on to state
that if BART combined the projected revenues for operating and capital budgets, it could give the
impression that some of this prescribed capital funding was available for operating purposes.
3 BART has used sales tax revenue bonds to finance various capital improvement projects, such as
various railway extension projects, the construction of new transit stations and parking structures,
and the rehabilitation of railcars.
California State Auditor Report 2013-118 19
April 2015
estimated that sales tax revenues would increase from
$203.4 million during fiscal year 2007–08 to nearly $250 million
by fiscal year 2012–13. However, actual sales tax revenue declined
during the recent recession and was only $208.6 million in fiscal
year 2012–13. We do not believe BART could have foreseen the
recent recession and noted that another large transit agency
in the State—the Los Angeles Metropolitan Transportation
Authority—similarly experienced declines in sales tax revenue.
Following the decline in its sales tax revenue in fiscal years 2008–09
and 2009–10, we noted that BART reduced its labor costs by
almost $29 million (from $382 million in fiscal year 2008–09 to
$353 million during fiscal year 2010–11). This reduction, along with
reduced spending on nonlabor items, helped BART make up for
lost revenues during the recession.
In addition to comparing previous projections to actual results,
we reviewed BART’s financial forecasts for fiscal years 2015–16
through 2018–19 to identify the key components and assumptions
used in its analysis. BART continued to use a forecasting approach
similar to the one it used for the previous forecasts. Its projections
for fiscal years 2015–16 through 2018–19 show that significant
revenue sources will continue to consist of rail passenger revenue
and sales tax collections, while significant expense items include
projected labor and nonlabor costs and planned allocations from
its operating budget for various capital projects and renovation
programs. We deemed each of these revenue and expense items
to be significant because each exceeded $100 million annually in
BART’s projections. Cumulatively, the specific revenue and expense
items we examined in BART’s financial forecasting model represent
more than 80 percent of all funding sources and uses.
Projected passenger revenue is the largest revenue source in
BART’s financial model, accounting for roughly $440 million to
$550.5 million annually over the four‑year period we reviewed (or Over the four‑year period we
more than 50 percent of funding from all operating budget sources). reviewed, projected passenger
BART’s passenger revenue projections assume annual ridership revenue is the largest revenue
increases of roughly 1.5 percent to 2 percent annually. Beyond fiscal source in BART’s financial model,
year 2018–19, BART’s financial model projects that annual ridership accounting for roughly $440 million
growth will generally be less than 2 percent. This projected increase to $550.5 million annually.
in ridership appears modest, especially with BART’s recent and
planned expansions, such as its recent connection to the Oakland
International Airport and planned expansion to other localities
such as Warm Springs and Antioch. Aside from considering
ridership growth, BART’s financial model also factors in scheduled
fare increases with the intent that this incremental additional
revenue will be used to fund priority capital replacement projects,
such as its project to replace its railcars, among other initiatives.
BART’s financial model assumes continuation of an inflation‑based
fare increase program that results in biennial fare increases of
20 California State Auditor Report 2013-118
April 2015
roughly 2 percent each year. The additional revenue generated
from the fare increases, according to BART’s financial model,
will result in $163.4 million in additional revenue between fiscal
years 2015–16 and 2018–19. However, we note that this additional
revenue for capital projects does not fully cover the $298.4 million
BART expects to contribute toward priority capital projects over
this time period. As noted in presentations before BART’s board,
BART management is sensitive to public reaction to fare increases
and has considered rider feedback through surveys when evaluating
whether to continue the inflation‑based fare increase program.
Nevertheless, with projected ridership growth and fare increases—
each at roughly 2 percent each year—BART forecasts that its overall
passenger revenue will increase by roughly 4 percent to 5 percent
each year through fiscal year 2018–19.
Sales tax revenue is the second largest contributor to BART’s
income, accounting for more than $200 million annually (or
roughly 30 percent of funding from all operating budget sources).
BART’s financial model assumes that its share of sales tax proceeds
will increase by 3 percent each year. While forecasts of sales
tax revenue are difficult and depend on the local economy, we
found BART’s estimate of sales tax growth to be reasonable. We
noted that BART’s long‑term average growth rate for its sales tax
revenue ranged between 2.3 percent and 3.4 percent between fiscal
years 2009–10 through 2012–13.
BART’s labor costs are its largest BART’s labor costs, which include salaries and benefits, are its
operating expense—paying nearly largest operating expense. During fiscal year 2012–13, BART paid
$400 million to its employees nearly $400 million to its employees, and its financial model
during fiscal year 2012–13, and it projects that its labor and benefit costs will reach $552.5 million
projects labor and benefit costs by fiscal year 2018–19 (or more than 50 percent of all funding
will reach $552.5 million by fiscal uses). Between fiscal years 2015–16 and 2018–19, BART expects
year 2018–19. that its labor costs will increase by between roughly 6 percent and
9 percent annually. A variety of different factors within BART’s
financial model contribute to this increase. For example, BART has
negotiated scheduled wage increases with its employee unions
amounting to roughly 4 percent annually over the next few years. In
addition, BART’s financial projections assume that it will be paying
higher costs for employee pension plans as a result of various
actions taken by the California Public Employees’ Retirement
System (CalPERS). According to BART, CalPERS decisions to
change key actuarial assumptions—such as an increased life
expectancy for retirees and a decreased expected return on its
investments—will increase the expected amounts BART will
contribute toward its employee retirement plans. Specifically,
BART expects that its contributions toward employee retirement
will increase from a projected $74.1 million in fiscal year 2015–16 to
$101 million in fiscal year 2018–19. Finally, BART’s labor projections
California State Auditor Report 2013-118 21
April 2015
assume increased labor costs associated with planned expansions
of its existing rail lines, amounting to $125.1 million between fiscal
years 2015–16 and 2018–19.4
BART’s financial model projects roughly 6 percent growth per
year in nonlabor costs between fiscal years 2015–16 and 2018–19,
growing by $23.7 million, from $116.4 million to $140.1 million,
over this period. Nonlabor costs include expense items such
as rent, insurance, inventory, equipment maintenance, and
fees that BART pays to the MTC and financial institutions to
administer the Clipper card, which serves as patrons’ regional
transit smart card to pay transit fares. BART’s model projects
most of these expenses to increase by about 2 percent annually.
However, on top of this modest growth, BART’s financial model
assumes that future expansion of its rail lines beginning in fiscal
year 2015–16 and additional activity at its Hayward maintenance
facility in fiscal year 2017–18 will add significantly to its nonlabor
costs. This additional activity accounts for $15.8 million of the
$23.7 million increase in nonlabor costs. BART arrived at this
amount by estimating the effects of the expansions—generally
by adding between 2 percent and 8 percent to existing labor and
nonlabor costs.
BART’s planned contributions to its capital projects from its
operating budget make up the last category of expense we reviewed
from BART’s forecasting model. Between fiscal years 2015–16
and 2018–19, BART plans to contribute $298.4 million toward
its priority capital replacement projects. BART’s financial model
assumes that this funding will be used to pay a portion of the
expected costs to purchase new railcars ($180 million) and to pay
for the train control modernization project ($50.3 million) and
the expansion of the Hayward maintenance facility ($49.6 million),
and it will use the increased portion of fare revenue ($18 million) as
capital reserves. BART’s financial model continues to allocate
funding to these projects well beyond fiscal year 2018–19.
However, whether BART can maintain its planned contributions
toward capital replacement is uncertain. BART’s financial model BART’s financial model shows
shows growing annual deficits, beginning at $5.9 million in fiscal growing annual deficits, beginning
year 2015–16 and increasing to an annual deficit of $57.3 million by at $5.9 million in fiscal year 2015–16
fiscal year 2017–18 and nearly $80 million by fiscal year 2023–24. and increasing to $57.3 million by
To address these deficits, BART’s 2014 transit plan states that fiscal year 2017–18, and nearly $80
its forecasts do not consider economic cycles and that revenues million by fiscal year 2023–24.
could be higher than expected, which could ease the strain
on its operating budget. However, if higher revenues do not
4 BART’s financial forecasting model assumes additional labor and nonlabor costs for certain
service expansions such as the Warm Springs expansion and the East Contra Costa BART
extension beginning in fiscal year 2015–16, with additional labor associated with its Hayward
maintenance facility in fiscal year 2017–18.
22 California State Auditor Report 2013-118
April 2015
materialize, BART stated that it will consider redirecting a portion
of its fare revenues back to its operating budget and/or consider
short‑term financing.
The State and BART Have Both Reviewed BART’s Workers’
Compensation Administrator, Finding No Significant Issues
Audits conducted by the Department of Industrial Relations’
Division of Workers’ Compensation (DWC) and BART’s
internal audit staff have not found any significant issues with
how BART’s workers’ compensation administrator processes
or requests reimbursement for claims filed by its employees.
BART contracts with a third‑party administrator (administrator)
to process its workers’ compensation claims. All third‑party
administrators in California are audited by the DWC every
five years. Upon completion of the audit, the DWC rates each
workers’ compensation administrator according to a set of criteria
and ultimately publishes a report that compares the performance
of all workers’ compensation administrators audited that year. If a
workers’ compensation administrator does not pass the audit, it is
subject to administrative financial penalties imposed by the DWC.
BART’s administrator successfully passed two audits by the DWC
in 2005 and 2010, and according to the DWC it will be audited
again in 2015. In the 2005 audit the administrator ranked fifth out
of 45 entities audited that year and was cited for 35 violations. In the
2010 audit, it ranked 33rd out of 52 entities, with 113 violations found
in the 59 files audited. Nineteen of the 113 violations concerned
BART employee claims. Twelve of the 19 violations found in BART
claims were related to late or inaccurate notices sent to employees
regarding their rights or changes to their benefits, four were related
to late payments, and three concerned failure to pay the correct
amount to claimants. Despite these violations and being required to
pay the corrected compensation amounts identified during the audit,
the administrator still received a passing score from the DWC.
Claims paid to injured workers are processed by the administrator
from a trust account that is established and periodically replenished
by BART. As the administrator makes claims payments from
the trust account, the balance in the trust declines until the
administrator provides BART with an accounting of the previous
payments made and requests that the trust be replenished with
additional funds. In 2012 BART’s internal audit department
published an audit of payments to its administrator and found
that the reimbursements were for BART employees only and
were made in accordance with the agreement between BART
and the administrator. For example, the audit found that claim
settlements over $25,000 were approved by BART staff before the
California State Auditor Report 2013-118 23
April 2015
settlement was finalized, in accordance with the agreement. In
addition, our review of four invoices for workers’ compensation
claim payments made between fiscal years 2009–10 and 2012–13
showed that the administrator invoiced BART only for workers’
compensation claims brought by BART employees.
Instances of Violence Against BART Employees Did Not Continuously
Increase Between Fiscal Years 2009–10 and 2013–14
We found that violence against BART employees, as measured in
either workers’ compensation claims or data kept by BART, did not
continuously increase between fiscal years 2009–10 and 2013–14.
During the course of their employment, front‑line transportation
employees may witness or be directly involved in traumatic events
and incidents. We reviewed data pertaining to assaults and batteries
against BART employees. An assault is an unlawful attempt,
coupled with a present ability, to commit a violent injury on the
person of another, such as a patron waving a knife in a station
agent’s direction. A battery is any willful and unlawful use of force
or violence upon the person of another, such as a patron punching a
station agent who refuses entry to a secure area.
Although data from BART’s administrator and BART did not show
that violence continuously increased between fiscal years 2009–10
through 2013–14, we did find evidence that station agents, followed
by BART police and then train operators, had the most workers’
compensation claims involving assault or battery. The administrator
records the cause for each claim, and BART maintains its own
database of reported instances of violence against employees. As
shown in Figure 4 on the following page, workers’ compensation
claims involving instances of violence against BART employees
did fluctuate but did not continuously increase between fiscal
years 2009–10 and 2013–14. These data were consistent with
information in BART’s violence in the workplace database. In Assaults and batteries against
addition, as shown in Table 4 on page 25, assaults and batteries BART employees made up less
made up less than 3 percent of the total amount spent on all than 3 percent of the total
workers’ compensation claims and constituted only between amount spent on all workers’
approximately 4 percent and 8 percent of all claims filed during our compensation claims filed during
review period. our review period.
BART’s manager of transportation operations support views
instances of violence against employees as a problem that will
continue to grow along with increases in ridership. To reduce
violence against employees, BART has expanded its training
to include methods to identify preassault indicators and how to
respond if confronted. BART also maintains a list with names and
photos of patrons banned from using BART facilities.
24 California State Auditor Report 2013-118
April 2015
Figure 4
Assaults and Batteries Against San Francisco Bay Area Rapid Transit District
Employees by Year
70
60
50
40
30
20
10
0
2009–10 2010–11 2011–12 2012–13 2013–14
smialC
noitasnepmoC
’srekroW
fo
rebmuN
Claims by police officers
Claims by other employees
Fiscal Year
Source: San Francisco Bay Area Rapid Transit District’s third‑party workers’ compensation
administrator’s claims tracking database.
In addition to actions BART initiated to reduce instances of
violence against its employees, the 2013 through 2017 collective
bargaining agreement (agreement) between BART and the
Amalgamated Transit Union requires the formation of a
Transportation Peer Support Program (program). The program
is developing policies, procedures, and training to enable peer
group personnel to provide routine follow‑up and support after
a violent or traumatic incident. The agreement also states that
BART will install Dutch doors and bullet‑resistant glass in station
booths. According to BART’s manager of transportation operations
support, the Dutch doors put a barrier between station agents and
the general public and provide time to call for police support if a
patron attempts to enter the booth. A prototype Dutch door and
bullet‑resistant glass have already been installed at the Coliseum
station in Oakland, and BART’s chief maintenance and engineering
officer said that the Dutch door is still in the evaluation stage as
of April 2015. Also, BART’s manager of transportation operations
support stated that bullet‑resistant glass will be installed at a
selection of stations to be determined at a later date, pending
station staff feedback.
California State Auditor Report 2013-118 25
April 2015
4
elbaT
seeyolpmE
tsniagA
ecneloiV
gnivlovnI
smialC
noitasnepmoC
’srekroW
no
diaP
tnuomA
dna
fo
rebmuN
RAEY
LACSIF
LATOT
41–3102
31–2102
*21–1102
11–0102
01–9002
991,441$
26
955,91$
01
542,53$
41
163,8$
91
813,56$
8
617,51$
11
†stluassA
166,858
331
772,75
41
522,311
32
204,735
14
702,74
83
155,301
71
‡seirettaB
068,200,1$
591
638,67$
42
074,841$
73
367,545$
06
525,211$
64
762,911$
82
slatoT
’srekrow
llA
708,551,53$
714,3
808,249,2$
736
952,440,7$
907
115,996,9$
637
152,975,6$
096
979,988,8$
546
smialc
noitasnepmoc
dna
tluassa
fo
egatnecreP
%58.2
%17.5
%16.2
%77.3
%11.2
%22.5
%36.5
%51.8
%17.1
%76.6
%43.1
%43.4
ot
evitaler
smialc
yrettab smialc
lla
.esabatad
gnikcart
smialc
s’rotartsinimda
noitasnepmoc
’srekrow
ytrap‑driht
s’tcirtsiD
tisnarT
dipaR
aerA
yaB
ocsicnarF
naS
:ecruoS
.raey
taht
diap
tnuoma
latot
eht
fo
685,754$
rof
detnuocca
21–1102
raey
lacsfi
ni
seirettab
owT
*
.noitcerid
s’tnega
noitats
a
ni
efink
a gnivaw
,elpmaxe
roF
.rehtona
fo
nosrep
eht
no
yrujni
tneloiv
a
timmoc
ot
,ytiliba
tneserp
a
htiw
delpuoc
,tpmetta
lufwalnu
na
si
tluassa
nA
†
.aera
eruces
a
ot
yrtne
sesufer
ohw
tnega
noitats
a
gnihcnup
,elpmaxe
roF
.rehtona
fo
nosrep
eht
nopu
ecneloiv
ro
ecrof
fo
esu
lufwalnu
dna
luflliw
yna
si
yrettab
A
‡
26 California State Auditor Report 2013-118
April 2015
We Did Not Find Any Evidence That BART Denied Employees Their
Original Positions After Recovering From Injuries or Inappropriately
Used Contract Employees
We found that union employees were allowed to return to their
original positions following an injury when the employee was
capable of resuming work, and were not replaced by contract labor.
State labor law prohibits employers from discharging employees
who file a workers’ compensation claim. We selected 80 workers’
compensation claims for injuries occurring between fiscal
years 2009–10 and 2012–13 to determine when the employees left
work, when they were cleared to return to work by their physician,
and if and when they returned to their original positions. Of the
80 claims we reviewed, 74 either returned to their positions upon
being cleared by their physicians, or had not left their original
positions despite the disability. The remaining six were still on
medical leave as of the end of fiscal year 2012–13, two of which
subsequently settled their disability claims with BART. We did not
observe an instance in which an employee capable of returning to
his or her original position was denied that opportunity.
We also found that BART offered some employees temporary
modified assignments when they were unable to return to their
pre‑injury position. The agreements between BART and two of its
unions allow employees to accept a temporary modified assignment
while on industrial disability when cleared by their physician.
However, the employee does not have to accept the temporary
position offered by BART and can remain on disability until
cleared to return to his or her original position. Of the 80 disabled
employees we selected, 11 accepted a modified assignment, and as
noted above, all but a few of the 80 employees returned to their
original positions upon being cleared by their physicians. According
to BART’s senior personnel analyst, an assignment that meets the
We found no evidence to indicate employee’s work modifications may not be immediately available, so
that employees on temporary an employee recently cleared for modified work may not be offered
modified assignment were a job immediately. In our review, we found no evidence to indicate
prevented from returning to their that employees on temporary modified assignment were prevented
original positions when cleared to from returning to their original positions when cleared to do so by
do so by their treating physician. their treating physician.
Moreover, our review of 20 service contracts found that BART
had documented its reasons for using contract labor instead of
unionized employees. The agreements allow for BART to contract
for outside labor when BART employees cannot fulfill a task. In
addition, when BART contracts for outside labor, it must send a
notification to the unions, which have the right to respond. While
employee unions have the right to advise BART management,
ultimately BART managers decide when it is appropriate to hire
contract labor. All 20 contracts we reviewed demonstrated that
California State Auditor Report 2013-118 27
April 2015
BART has a process for notifying its employee unions of the
contracts, involving faxing a contract notification form to BART
union officials.
In some instances, BART and its unions may not agree on whether
a particular need can be satisfied with union employees. Officials
with Service Employees International Union (SEIU) stated that
BART has too few union employees and that past contracting
activity suggests there should be more permanent employees. In
contrast, according to BART’s assistant chief employee relations
officer, BART does not want to hire permanent employees whom
it will have to lay off later when the need for that type of labor goes
away, so it is careful to add positions only when past years’ data
and/or input from department managers show that a long‑term
need exists. Determining which perspective is correct is difficult
given the nature of some of the contracts we reviewed. For example,
one contract from July 2009 was for graffiti removal throughout
the BART system for $873,000. While the layperson might think
BART’s maintenance or janitorial employees have the skills to
remove graffiti—such as by painting or sandblasting affected
surfaces, BART’s managers indicated that such work could not be
performed satisfactorily by these employees. In another contract
from August 2009, BART agreed to pay $2.3 million for the dry
cleaning, repair, and supply of replacement transit vehicle passenger
seat cushions. In this case, BART informed the union that it was
contracting out this work because it had no “dry cleaning or sewing
personnel.” Although the decision to use contractors in these
instances may not be viewed favorably by the employee unions, it
is one that BART’s management is ultimately permitted to make, as
provided by the agreements.
BART’s union agreements require that union employees be able BART’s union agreements require
to bid on temporary job assignments created when another that union employees be able to
employee is sick, injured, or otherwise on leave. For example, bid on temporary job assignments
according to its agreement with the Amalgamated Transit Union— created when another employee is
which covers its train operators, station agents, and various sick, injured, or otherwise on leave.
other classifications—BART is to establish board postings of
available assignments so that employees can submit bids to receive
these assignments. During the audit, we noted examples of these
postings being used to fill job openings, such as when a regularly
scheduled employee is on indefinite medical leave. For example,
we tracked a BART union employee who filled in for a disabled
train operator for over two months until the injured operator was
healthy enough to return to work. BART’s agreement with the SEIU
contains similar provisions for filling temporary vacancies. Further,
many of BART’s unionized employees hold certain certifications
required for their jobs. The California Public Utilities Commission
(CPUC) requires that BART establish training, testing, and
certification programs for personnel whose duties may affect the
28 California State Auditor Report 2013-118
April 2015
safety of passengers, employees, or equipment. Specifically, the
CPUC requires station agents and train operators, among others,
to hold safety certifications due to the nature of their jobs, and to
renew the certifications every two or three years depending on
the employee’s job classification. Roughly 60 percent of BART’s
personnel are required to hold certain safety certifications. Because
of the union agreements specifying how job openings will be filled,
along with the safety certifications required for many of these
positions, the likelihood of BART hiring contracted labor to replace
union employees appears limited.
We conducted this audit under the authority vested in the California State Auditor by Section 8543
et seq. of the California Government Code and according to generally accepted government auditing
standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate
evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives
specified in the scope section of the report. We believe that the evidence obtained provides a
reasonable basis for our findings and conclusions based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
Date: April 28, 2015
Staff: Grant Parks, Audit Principal
Aaron Fellner, MPP
Oswin Chan, MPP, CIA
Taylor William Kayatta, JD, MBA