CSA
Summary
Read the report at California State Auditor ↗
February 2015
California Department
of Consumer Affairs’
BreEZe System
Inadequate Planning and Oversight Led to
Implementation at Far Fewer Regulatory Entities
at a Significantly Higher Cost
Report 2014-116
COMMITMENT
INTEGRITY
LEADERSHIP
The first five copies of each California State Auditor report are free. Additional copies are $3 each, payable by check
or money order. You can obtain reports by contacting the California State Auditor’s Office at the following address:
California State Auditor
621 Capitol Mall, Suite 1200
Sacramento, California 95814
916.445.0255 or TTY 916.445.0033
OR
This report is also available on our Web site at www.auditor.ca.gov.
The California State Auditor is pleased to announce the availability of an online subscription service.
For information on how to subscribe, visit our Web site at www.auditor.ca.gov.
Alternate format reports available upon request.
Permission is granted to reproduce reports.
For questions regarding the contents of this report,
please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
For complaints of state employee misconduct, contact the California State Auditor’s
Whistleblower Hotline: 1.800.952.5665.
Elaine M. Howle State Auditor
Doug Cordiner Chief Deputy
February 12, 2015 2014-116
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the California State Auditor presents this audit report
concerning how the California Department of Consumer Affairs (Consumer Affairs) planned, developed, and
implemented BreEZe—an information technology (IT) system Consumer Affairs envisioned would support all of
the primary functions and responsibilities of 37 of its 40 boards, bureaus, committees, and a commission (regulatory
entities). This report concludes that the BreEZe project has been plagued with performance problems, significant
delays, and escalating costs, which based on a January 2015 estimate were $96 million—more than triple the original
cost estimate—for implementation of a system at only half of the regulatory entities originally planned for BreEZe.
As of that date, only 10 regulatory entities had transitioned to BreEZe, eight more intend to transition to it in
March 2016, and it is unknown whether or when the remaining 19 will transition to the system.
Although doing so is critical to the successful development of IT systems, Consumer Affairs failed to adequately
plan, staff, and manage the project for developing BreEZe. For example, while an up-to-date assessment of business
needs is essential to developing adequate system requirements, Consumer Affairs failed to properly perform such an
assessment for the regulatory entities when developing the system requirements for BreEZe, which specify what the
system should do. Instead, Consumer Affairs relied on requirements from earlier projects that were abandoned and
incorrectly assumed that the entities could use similar business processes to, for example, process license applications.
Further, although staff of the California Department of Technology (CalTech) in its oversight role raised nearly
180 significant and persistent concerns about the BreEZe project in monthly reports between December 2010 and
September 2014 in areas including project management, staffing, system requirements, and vendor performance,
it allowed the project to continue without significant intervention. We believe the volume and significance of these
concerns should have prompted both CalTech and Consumer Affairs to analyze fully the costs and benefits of
suspending or terminating the project versus proceeding.
Additionally, during the procurement process for the BreEZe project, the California Department of General Services
(General Services) and Consumer Affairs approved revisions to the BreEZe contracts’ terms and conditions proposed
by the vendor, Accenture LLP, which transferred significant risk to the State. For example, the revised language
limited Consumer Affairs’ ability to terminate the contracts and eliminated protections Consumer Affairs otherwise
would have had against the possibility of intellectual property rights violations. We question the prudence of some of
the decisions General Services and Consumer Affairs made regarding the terms and conditions, as they substantially
increased Consumer Affairs’ financial risks related to these contracts.
Despite assertions by the Board of Registered Nursing (BRN) that it was exceeding maximum time frames for
processing certain license applications since implementing BreEZe, we found little evidence that it tracks the
information needed to support such claims. In addition, we interviewed executive officers of the 10 regulatory
entities that have implemented BreEZe and most told us that they are generally dissatisfied with their BreEZe
experience because it did not meet their expectations in a variety of ways, and eight including BRN reported that the
system has decreased their operational efficiency.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
621 Capitol Mall, Suite 1200 Sacramento, CA 95814 916.445.0255 916.327.0019 fax www.auditor.ca.gov
Blank page inserted for reproduction purposes only.
California State Auditor Report 2014-116 v
February 2015
Contents
Summary 1
Introduction 9
Chapter 1
Poor Planning and Decision Making Have Led to Increased Costs
and Extended Timelines and Have Placed the Future of BreEZe
in Doubt 23
Recommendations 49
Chapter 2
The State Entities Responsible Did Not Ensure That the
BreEZe Contract Terms Sufficiently Protect the State 53
Recommendations 60
Chapter 3
The Board of Registered Nursing Made Some Unsubstantiated
Reports of Difficulties From Implementing BreEZe, and Other
Regulatory Entities Also Report Challenges With BreEZe 63
Recommendations 78
Appendix
Summary of Significant BreEZe Project Concerns Noted by
Independent Oversight Reports, December 2010 Through
September 2014 81
Responses to the Audit
California Department of Consumer Affairs 99
California Department of Consumer Affairs, Board of
Registered Nursing 107
California State Auditor’s Comments on the Response From
the Board of Registered Nursing 113
California Department of Technology 115
California State Auditor’s Comments on the Response From
the California Department of Technology 125
vi California State Auditor Report 2014-116
February 2015
Blank page inserted for reproduction purposes only.
California State Auditor Report 2014-116 1
February 2015
Summary
Results in Brief
Audit Highlights . . .
The California Department of Consumer Affairs (Consumer Our audit concerning the California
Affairs) encompasses 40 boards, bureaus, committees, and Department of Consumer Affairs’ (Consumer
a commission (regulatory entities) that regulate and license Affairs) planning, development, and
professional and vocational occupations to protect the health, implementation of BreEZe—an information
safety, and welfare of the people of California. Annually, these technology (IT) system envisioned to support
regulatory entities process more than 350,000 applications for all primary functions and responsibilities
professional licensure and an estimated 1.2 million license renewals. of its regulatory entities—revealed
The regulatory entities establish the minimum qualifications and the following:
levels of competency for licensure, register or certify practitioners,
» Consumer Affairs failed to adequately
investigate complaints, and discipline violators. Although these
plan, staff, and manage the project for
entities are responsible individually for activities related specifically
developing BreEZe.
to the professions they oversee and they are semiautonomous
bodies whose members are appointed by the governor and the
• It did not effectively assess the
Legislature, Consumer Affairs establishes general administrative
regulatory entities’ business needs to
policies for them and provides them with administrative support.
determine system requirements.
Historically, the regulatory entities have used multiple computer • Inadequate system requirements led
systems to fulfill their required duties and meet their business to significant delays at key stages of
needs. However, significant issues with these systems reportedly the project.
resulted in excessive turnaround times for licensing and
• It relied on faulty assumptions in
enforcement activities, impeding the ability of the regulatory
selecting a commercial “off-the-shelf”
entities to meet their goals and objectives. In 2009, after
system as the foundation for BreEZe,
undertaking several unsuccessful efforts to develop or procure
which contributed to an increase in
an information technology (IT) system that would improve the
project costs—from $28 million
capabilities of the regulatory entities it administratively supports,
in 2009 to $96 million as of
Consumer Affairs proposed, and the California Department of
January 2015 for half of the entities
Technology (CalTech) approved, BreEZe—a system Consumer
originally planned.
Affairs envisioned would support all of the primary functions and
responsibilities of its regulatory entities.1 Unfortunately, this has not • It did not have adequate staffing
been the case. to execute and implement BreEZe
through critical project phases.
The work Consumer Affairs undertook on the BreEZe project has
» Between December 2010 and
lacked adequate planning. Although an up‑to‑date assessment
September 2014, the California
of business needs is critical to the successful development of an
Department of Technology’s (CalTech)
IT project, Consumer Affairs failed to properly perform such
independent oversight raised nearly
an assessment for its regulatory entities when developing the
180 significant project concerns, yet both
system requirements, resulting in requirements that did not
CalTech and Consumer Affairs’ officials
allowed the project to continue without
significant intervention.
1 Although Consumer Affairs consists of 40 regulatory entities, only 37 of these entities were
originally scheduled to implement BreEZe. Specifically, the Bureau of Real Estate and the Bureau
of Real Estate Appraisers were brought under Consumer Affairs as a result of the governor’s continued on next page . . .
reorganization plan, effective July 2013, after the BreEZe project was approved and underway.
According to Consumer Affairs, it planned to implement BreEZe at these regulatory entities once
the system was fully implemented at the 37 regulatory entities. Another entity, the Arbitration
and Certification Program, does not issue licenses and will not be included in BreEZe.
2 California State Auditor Report 2014-116
February 2015
» Despite significant problems with adequately reflect their individual needs. According to our IT
the BreEZe project, CalTech approved expert, system requirements define a business problem to be solved
additional funding for it. and specify what the system should do. For example, a system
requirement for a regulatory entity could be that the system allow
» The California Department of General
the entity to record the date it receives an application. In planning
Services and Consumer Affairs revised the
the BreEZe system, Consumer Affairs should have taken steps to
BreEZe contracts’ terms and conditions, at
ensure that the system requirements were based on the current
the request of the project vendor, in ways
business needs of its regulatory entities, so that the resulting system
that significantly increased the financial
would aid the entities in conducting their business operations
risk to the State.
and in fulfilling their regulatory responsibilities. Instead, when
» As of January 2015 only 10 regulatory developing the requirements for BreEZe, Consumer Affairs relied
entities had transitioned to BreEZe, on requirements for earlier projects that were abandoned.
eight more intend to transition in
March 2016, and it is unknown if the Because Consumer Affairs did not properly determine the business
remaining 19 regulatory entities will needs of its regulatory entities, it incorrectly assumed, for example,
implement BreEZe. that the entities could use similar business processes to process
applications and issue licenses. This misconception, coupled with
» Most executive officers of the
the fact that Consumer Affairs wanted BreEZe to be developed
10 regulatory entities that had
quickly, informed Consumer Affairs’ decision to select an existing
transitioned to BreEZe reported that it
commercial “off‑the‑shelf,” or COTS, system as the foundation
has decreased their regulatory entity’s
for BreEZe. Consumer Affairs believed that this type of product,
operational efficiency.
rather than a custom‑developed system, would require only
moderate modifications and resources to implement. These faulty
» Due to lack of evidence, the Board of
assumptions have led to significant project delays and a substantial
Registered Nursing’s claim that the
increase in the estimated costs of the project, from $28 million
implementation of BreEZe caused
in 2009 to $96 million as of January 2015, for implementation
inefficiency in processing applications
of a system that will include only half of the regulatory entities
could not be substantiated.
originally planned for BreEZe. Thus, it appears that Consumer
Affairs’ selection of this COTS product may not have been the most
appropriate and most cost‑effective decision.
In part, because the foundation of BreEZe—its system
requirements—was inadequately developed, the BreEZe project has
experienced delays at key stages of the project. The most extreme
delay involved the key milestone of user acceptance testing—testing
that future users of the system conduct to confirm that the system
operates as its requirements specify. User acceptance testing for
the 10 regulatory entities included in the first implementation
of BreEZe (phase 1) was originally planned to occur over an
eight‑week period; instead it spanned 11 months, from the end
of November 2012 to October 2013, significantly exceeding the
original time frame. This likely occurred in part because the BreEZe
system had almost 1,700 unresolved system defects at the beginning
of user acceptance testing. According to our IT expert, many of
these defects were likely attributable to the poor development of the
system requirements. Although user acceptance testing is one of
the final and more critical procedures undertaken before system
implementation to ensure that the system operates appropriately,
in this case it morphed into a redesign of the requirements and
California State Auditor Report 2014-116 3
February 2015
a rework of the system. Specifically, in conducting the testing
of the system, some of the 10 regulatory entities included in the
first phase of implementation, as well as Consumer Affairs itself,
learned that the system did not operate as they expected or needed.
Had Consumer Affairs performed a complete, current assessment
of the regulatory entities’ needs when determining the system
requirements for BreEZe, some of the delays the project has
experienced might have been avoided.
Further, although CalTech began providing independent oversight
of the BreEZe project approximately one year after the project’s
inception, neither CalTech nor Consumer Affairs responded
appropriately to the significant and persistent concerns that the
CalTech staff and consultants charged with overseeing the project
were raising. In addition to having the statutory authority to
suspend or terminate IT projects, state law assigns responsibility
for IT project oversight to CalTech; this project oversight mainly
consists of two types of independent oversight. Independent
verification and validation (IV&V) is used to ensure that a
system satisfies its intended use and user needs. Independent
project oversight (IPO) is used to ensure that effective project
management practices are in place and in use. In their reports from
December 2010 through September 2014 on the BreEZe project,
the CalTech IV&V consultant and the IPO specialist raised nearly
180 significant concerns relating to project management, staffing,
system requirements, and vendor performance. According to our
IT expert, the volume and significance of these concerns should
have prompted both CalTech and Consumer Affairs to analyze
fully the costs and benefits of suspending or terminating the project
versus proceeding. However, although Consumer Affairs officials
and CalTech management were fully aware of these concerns,
neither group took sufficient action to ensure that these concerns
were appropriately addressed; instead, they allowed the project to
continue for more than three years without significant intervention.
Given CalTech’s authority and the numerous concerns the IV&V
consultant and the IPO specialist raised about the project, we
question why CalTech did not take steps to ensure that Consumer
Affairs heeded its advice. For instance, CalTech could have formally
warned Consumer Affairs that it would suspend the project if
Consumer Affairs did not bring the project back into alignment
with its planned scope, cost, and schedule. As an example, the
estimated cost to complete the project had almost tripled to
$78 million and the project had experienced significant delays
in its schedule before completion of user acceptance testing. We
believe these problems, along with the significant cost increases the
project had already experienced, should have been enough to elicit
4 California State Auditor Report 2014-116
February 2015
CalTech’s greater involvement in the project. Instead, it approved
Consumer Affairs’ Special Project Report (SPR) 2, which requested
additional funding for the project, in October 2013.2
Consumer Affairs submitted SPR 3 to CalTech in June 2014; in
it, it requested additional funding and estimated the costs to
complete the project through phase 2 at $118 million. However,
it was not until after Consumer Affairs informally estimated the
cost of completing the project had risen to $300 million that same
month that CalTech changed its oversight approach on the BreEZe
project.3 Although CalTech approved SPR 3 in July 2014, according
to the BreEZe project director, Consumer Affairs withdrew
its submission of SPR 3 upon direction from CalTech and the
California Department of Finance in September 2014.
As discussed previously, CalTech has the authority and
responsibility to oversee IT projects. If CalTech had chosen
to suspend the project, BreEZe development would have been
paused temporarily, giving Consumer Affairs additional time to
conduct a cost‑benefit analysis and correct fundamental problems,
such as requirements issues, that occurred during planning and
development. However, in October 2014 the CalTech director—
who has overseen the BreEZe project since Consumer Affairs
executed its contracts with the project vendor, Accenture LLP
(Accenture)—told us that CalTech has not halted BreEZe for
several reasons: because BreEZe is moving in the right direction,
because the system’s problems are not incurable, and because the
system is working and functional. 4 However, Consumer Affairs’
SPR 3.1, which it submitted to CalTech in January 2015, indicates
the project is not moving in the right direction and proposes a
rescoping of the project because of significant concerns relating to
staffing and increasing project costs, and because its contracts with
Accenture are no longer financially feasible for Consumer Affairs.
For these reasons, among others, the future implementation of
BreEZe is uncertain at best and, as it relates to the regulatory
entities originally included in the final phase (phase 3), likely
unfeasible. As of January 2015, 10 regulatory entities had
implemented the system, with the first of three phases occurring
in October 2013. Another eight regulatory entities are included
2 An SPR provides a summary of proposed changes to the original project cost, schedule, or
scope. An SPR is generally required when the project costs or total financial program benefits
deviate or are anticipated to deviate by 10 percent or more, or a major change occurs in project
requirements or methodology.
3 The BreEZe project team developed the estimate informally and not in the same manner as an
SPR requires.
4 There are three contracts related to the BreEZe project—one contract for design,
development, and implementation; another contract for maintenance support; and a
third contract for the system license. When we discuss a specific contract, we identify it
as either the design, maintenance, or system license contract.
California State Auditor Report 2014-116 5
February 2015
in phase 2, which is currently planned for March 2016. However,
Consumer Affairs has indicated that it needs additional staffing to
successfully implement BreEZe at the phase 2 regulatory entities,
and as of January 2015 lacked the funding to fill those positions.
Additionally, it is unknown whether or when the remaining
19 phase 3 regulatory entities will implement BreEZe. Specifically,
CalTech officials indicated that it completed renegotiating Consumer
Affairs’ design contract with Accenture on December 1, 2014, and
according to Consumer Affairs’ director, these 19 regulatory entities
had been removed entirely from the project. Although the director
of Consumer Affairs maintains that the department intends to
implement BreEZe at those 19 regulatory entities, it lacks a plan to do
so. In fact, SPR 3.1 indicates that the project will end after the phase 2
regulatory entities implement BreEZe, and only after its successful
implementation of that phase will Consumer Affairs reassess the
best implementation approach for the phase 3 regulatory entities.
However, the director of Consumer Affairs acknowledged that the
department has not assessed the extent to which the business needs
of the 19 regulatory entities will require changes to the system.
Moreover, Consumer Affairs has not conducted a formal cost‑benefit
analysis to determine whether BreEZe is the most cost‑beneficial
solution for meeting those needs.
Additionally, the contracts Consumer Affairs executed with
Accenture for developing BreEZe do not adequately protect
the State. Consumer Affairs executed the BreEZe contracts
with Accenture in September 2011, under the direction of the
California Department of General Services (General Services).
Although its role at that time was to administer state IT
procurements and conserve the fiscal interests of the State,
General Services and Consumer Affairs agreed to revise the
contracts’ terms and conditions during the procurement process, at
Accenture’s request, in ways that significantly increased risk to the
State. During the request for proposal (RFP) bidding period (RFP
phase), General Services provided every potential bidder with the
opportunity to submit a protest for issues such as the selection of
prequalified bidders or RFP requirements before submitting a bid
and to have General Services review its concerns. During the RFP
phase in the BreEZe procurement process in January 2011, only
Accenture submitted a protest, in which it proposed modifications
to the State’s standard IT general provisions and model contract
language (standard IT contract).5 Of the 44 modifications to the
State’s standard IT contract that Accenture proposed, General
Services accepted 18, proposed its own revisions to 19, and rejected
just seven. Subsequently in April 2011, in accordance with state law,
Consumer Affairs entered into a negotiation with Accenture during
5 At the time of the BreEZe procurement, General Services had several modules of standard
contract language related to IT contracts.
6 California State Auditor Report 2014-116
February 2015
which further changes were made to the contract, with General
Services’ approval. However, some of those accepted changes to the
standard IT contract’s terms and conditions decrease Consumer
Affairs’ ability to obtain rights to work product that Accenture
builds if Consumer Affairs terminates the contracts early, and they
reduce Consumer Affairs’ financial protections in the event of
intellectual property rights violations.
Although General Services cited reasons for approving the modified
terms and conditions in the BreEZe contracts, we question the
prudence of some of the decisions it and Consumer Affairs made,
as they increased Consumer Affairs’ financial risks related to these
contracts. CalTech’s current authority over procurements for IT
projects, a role that was not in place at the time the BreEZe contracts
were being negotiated, together with its authority for approving
and overseeing IT projects, position it well to ensure that future IT
procurements do not jeopardize the State’s financial interests.
Various stakeholders of the Board of Registered Nursing (BRN),
one of the 10 phase 1 regulatory entities, raised concerns about
the timeliness with which it has processed applications after
implementing BreEZe in October 2013. According to BRN, it
has faced significant delays in processing license applications
and has been forced to modify its business processes since
implementing the BreEZe system. However, although BRN asserted
that it was exceeding the maximum time frames for processing
certain applications and was facing a backlog of applications after
implementing the system, we found little evidence demonstrating that
it consistently tracks the information needed to support such claims.
For the selection of applications we reviewed, BRN processed these
applications, on average, well within the allowable maximum time
frames. However, we did determine that as of September 2014, BRN
had a significant number of applications that were pending its review—
more than 7,000, of which 63 had already exceeded the respective
maximum processing time frames. Yet because BRN does not formally
track this information, it cannot adequately assess its workload.
Additionally, BRN indicated that it has faced, and continues to face,
obstacles in its implementation of the BreEZe system; for example,
the system requires that staff take additional steps to enter applicant
information. However, BRN does not track the information needed
to assess the impact of such obstacles. Further, because it believes
its efficiency in processing applications has decreased since
implementing BreEZe, it has requested additional staff it believes
it needs to process applications within required time frames.
However, this request is based on data from the two fiscal years
preceding BRN’s implementation of BreEZe. Thus, because the
analysis BRN used to support its need for the additional positions
California State Auditor Report 2014-116 7
February 2015
does not reflect its current workload and business processes since
implementing the BreEZe system, the additional positions it
requested are not adequately justified.
Most of the executive officers of the 10 phase 1 regulatory entities
are generally dissatisfied with their BreEZe experience because it has
not met their expectations. We interviewed the executive officers
of each of the regulatory entities that have implemented the system
regarding various aspects of their experience with the project,
including their satisfaction with BreEZe and their overall experience
with the system. Each regulatory entity reported experiencing
issues with certain aspects of the BreEZe project. For example, the
majority were unsatisfied with the testing they were able to conduct
before implementing the system, and most found the training to be
inadequate. In addition, all 10 of the executive officers indicated that
BreEZe’s reporting capability was unsatisfactory. Of greater concern,
most executive officers reported that BreEZe has decreased their
regulatory entity’s operational efficiency.
Recommendations
CalTech
To help ensure the success of the BreEZe project going forward,
CalTech should ensure that Consumer Affairs responds promptly
to, and adequately addresses, concerns the IPO specialist and
the IV&V consultant raise.
If Consumer Affairs receives the necessary funding and resources
to successfully implement BreEZe at the phase 2 regulatory entities
and the project continues to face escalating costs, CalTech should
require Consumer Affairs to analyze the costs and benefits of
moving forward with the project as planned versus suspending or
terminating the project.
To ensure that future IT project procurements do not jeopardize
the State’s financial interests, CalTech should document its reasons
for approving any deviations from standard contract language.
Consumer Affairs
Consumer Affairs should develop a process to ensure that it
undertakes all required oversight activities with respect to BreEZe
so that it can prevent or identify and monitor any problems as
they arise. This includes taking steps to sufficiently respond to any
concerns the IPO specialist and the IV&V consultant raise.
8 California State Auditor Report 2014-116
February 2015
To ensure that BreEZe is a cost‑effective solution to meet the
business needs of the phase 3 regulatory entities, should it elect to
pursue implementing BreEZe at these entities, Consumer Affairs
should first complete a formalized cost‑benefit analysis. This
analysis should include an assessment of the potential changes
those regulatory entities may require be made to the BreEZe system
and the associated costs.
Consumer Affairs should continue to work with the phase 1
regulatory entities to ensure that the issues they are facing with
BreEZe are being resolved in a timely manner.
BRN
To ensure that it has adequate data to effectively use its resources
and manage its workload, BRN should do the following:
• Formally track and monitor the timeliness of its processing of
applications by type and track the cause of any delays.
• Formally track and monitor the applications pending its review
by type and original receipt date.
Conduct an analysis no later than June 30, 2015, of its application
processing since implementing BreEZe to identify its workload
capability. To the extent that it determines additional resources are
necessary, BRN should submit a request for these resources that is
appropriately justified.
Agency Comments
Consumer Affairs and BRN agreed with our recommendations and
outlined the actions they plan to take to implement them. Although
CalTech states that our report’s recommendations are for the
most part appropriate and in line with actions and initiatives that
it has already undertaken, it explained that it has general concerns
with the report and did not indicate whether it agrees with our
recommendations. Our comments on CalTech’s response begin on
page 125.
California State Auditor Report 2014-116 9
February 2015
Introduction
Background
The primary function of the California Department of Consumer
Affairs (Consumer Affairs) is to protect and serve consumers
and ensure a competent, fair marketplace. Consumer Affairs
encompasses 40 boards, bureaus, committees, and a commission
(regulatory entities) that regulate and license professional and
vocational occupations to protect the health, safety, and welfare
of the people of California. The regulatory entities that comprise
Consumer Affairs license doctors, dentists, contractors, and
cosmetologists, among other professions. Each year these
regulatory entities process more than 350,000 applications
for professional licensure and an estimated 1.2 million license
renewals. The regulatory entities also establish the minimum
qualifications and levels of competency for licensure, register
or certify practitioners, investigate complaints, and discipline
violators. Although these entities are semiautonomous bodies
that are responsible individually for activities related specifically
to the professions they oversee and their members are appointed
by the governor and the Legislature, Consumer Affairs establishes
general administrative policies for them and provides them with
administrative support. For example, Consumer Affairs processes
payments for goods and services and travel reimbursements for the
regulatory entities.
Historically, Consumer Affairs’ regulatory entities have used
multiple computer systems, referred to as legacy systems, to fulfill
their required duties and meet their business needs. The Applicant
Tracking System (ATS) and Consumer Affairs System (CAS)
are the two database applications that Consumer Affairs uses
to maintain its core licensing and enforcement information for
regulatory entities. The ATS, which tracks and monitors activities
for cashiering, initial license application, and examinations for
32 regulatory entities, was developed in the 1990s and last upgraded
in 2003. The CAS, an enterprise licensing and enforcement system,
was developed in the 1980s to track license‑related activities
such as initial licenses, renewals, complaints, investigations, and
enforcement for 38 regulatory entities.
According to Consumer Affairs, significant issues with these legacy
systems have resulted in excessive turnaround times for licensing
and enforcement activities, thus impeding the ability of the
regulatory entities to meet their business goals and objectives. In
its November 2009 Feasibility Study Report (FSR) for the proposed
BreEZe system, Consumer Affairs identified many deficiencies
within the existing systems that were affecting consumers. For
example, Consumer Affairs reported that the existing licensing
10 California State Auditor Report 2014-116
February 2015
and enforcement systems lacked automated workflow and case
management functionality that could help staff ensure that
licensing and enforcement activities are accurately and completely
documented. Additionally, the existing licensing and enforcement
systems did not interface with partner agencies, such as the
California Department of Justice, to share information. Consumer
Affairs stated that these deficiencies, among others, had resulted in
various negative effects, including a prolonged licensing process,
an average complaint resolution time of over two years for existing
licensees, and lost documents.
In 2008 and 2009 Consumer Affairs and one of its regulatory
entities, the Board of Registered Nursing (BRN), came under
scrutiny from the media for delays in completing enforcement
activities. The Los Angeles Times reported that BRN was facing
significant enforcement backlogs that extended more than
three years and thereby allowed nurses with criminal convictions
or with documented histories of incompetence, drug theft, or
abuse to continue working while action was pending. For example,
the Los Angeles Times reported the results of an investigation it
conducted that found more than 100 cases in which the State did
not seek to revoke or restrict licenses until the nurses involved had
accumulated three or more criminal convictions.
In July 2009 the governor stated that Consumer Affairs’
enforcement backlogs were absolutely unacceptable. That summer
Consumer Affairs initiated a major effort to reform its enforcement
programs, which were plagued with various investigative, legal,
procedural, and technical impediments. These impediments
hindered Consumer Affairs’ ability to process complaint and
enforcement caseloads within a reasonable time, and in turn they
diminished Consumer Affairs’ ability to protect consumers and
the integrity of the licenses it issued. This initiative, the Consumer
Protection Enforcement Initiative (CPEI), intends to overhaul
the enforcement process at the healing arts boards—boards
that regulate a variety of professions from doctors and nurses to
physical therapists and optometrists—through administrative
improvements, increased staffing and information technology (IT)
resources, and legislative changes. Once it has fully implemented
the CPEI, which is largely dependent on its implementation of
BreEZe, Consumer Affairs expects the healing arts boards to reduce
the average enforcement completion time from 36 months to
between 12 and 18 months.
California State Auditor Report 2014-116 11
February 2015
History and Evolution of the BreEZe System
Consumer Affairs began efforts to develop an updated IT
system in 1993. More recently, beginning in 2000, it initiated
several IT projects: the Professional Licensing and Enforcement
Management System; iLicensing; and the Complaint Resolution
Information Management System, a system that was formerly
being developed by and for the Medical Board of California.
According to the director for the BreEZe project, these projects
were ultimately canceled during either the planning or request for
proposal (RFP) stages. In 2009 Consumer Affairs modified the
system requirements for the projects and combined them into
one new, integrated, enterprisewide enforcement and licensing
system, referred to as BreEZe. Consumer Affairs views BreEZe as
a technological solution to assist it in achieving the goals the CPEI
sets forth.
As stated in the 2009 FSR for BreEZe, Consumer Affairs believed
that BreEZe, at an estimated cost of roughly $28 million, would
provide the regulatory entities with an enterprisewide system that
supported all applicant tracking, licensing, renewal, enforcement,
monitoring, cashiering, and data management capabilities.
BreEZe would also be Web‑enabled to allow license application,
license renewal, and payment processing on the Internet for
applicants and licensees. Further, it would allow the public to file
complaints and look up licensee information and complaint status
through the Internet. Part of BreEZe’s implementation, according to
the 2009 FSR, would involve establishing interfaces to electronically
share data with external and internal systems as well as converting
existing data from ATS and CAS and migrating it into BreEZe,
conducting user training, and creating system documentation. In
its FSR for BreEZe, Consumer Affairs also stated its belief that a
commercial “off‑the‑shelf” system (COTS) was the appropriate
solution and would involve acquiring a systems integrator—a
person or company that specializes in bringing together component
subsystems into a whole and ensuring that those subsystems
work together—to work with appropriate software and service
providers to implement the COTS software package that meets
all final functional and technical requirements for all participating
Consumer Affairs’ regulatory entities.6 Table 1 on the following page
presents the objectives of BreEZe.
6 Although Consumer Affairs consists of 40 regulatory entities, only 37 of these entities were
originally scheduled to implement BreEZe. Specifically, the Bureau of Real Estate and the Bureau
of Real Estate Appraisers were brought under Consumer Affairs as a result of the governor’s
reorganization plan, effective July 2013, after the BreEZe project was approved and underway.
According to Consumer Affairs, it planned to implement BreEZe at these two regulatory entities
once the system was fully implemented at the 37 regulatory entities. Another entity, the
Arbitration and Certification Program, does not issue licenses and will not be included in BreEZe.
12 California State Auditor Report 2014-116
February 2015
Table 1
BreEZe Project Objectives
OBJECTIVES
Track all licensing and enforcement activities within an automated system.
Reduce average initial license processing time by 15 percent.
Reduce average renewal license processing time by 50 percent.
Reduce average complaint resolution time by 5 percent.
Address existing backlog issues through proactive management of licensing timelines.
Provide accurate performance reporting to stakeholders.
Provide accurate enforcement cost reports.
Increase data usage during statistical analysis to 90 percent.
Reduce average statistical report turnaround time by 50 percent.
Reduce average information request turnaround time by 50 percent.
Centrally locate and protect licensee personal data.
Provide access to cross-entity data.
Provide ability for licensees to submit one information update for all licenses.
Allow consumers to access licensees’ professional standards violations.
Allow legislative changes to be quickly implemented.
Reduce the number of cashiering systems from three to one.
Achieve 60 percent of applications and renewals submitted via the internet.
Enable applicants and licensees to submit, update, and pay via the Internet.
Provide the ability to view real-time licensing and enforcement action updates.
Sources: California Department of Consumer Affairs’ Feasibility Study Report,
November 2009.
In September 2011, after receiving approval from the California
Department of Technology (CalTech) for its first Special Project
Report (SPR) for the BreEZe system, Consumer Affairs entered
into a nine‑year contract overseen and approved by the California
Department of General Services (General Services) with a
systems integrator vendor—Accenture LLP (Accenture)—to
assist Consumer Affairs in implementing the COTS.7 As part
of this agreement, Accenture subcontracted with Iron Data,
the COTS vendor, to provide the BreEZe system for Consumer
Affairs. In total, Consumer Affairs executed three contracts with
Accenture, totaling $45.7 million, to develop and implement the
BreEZe system: a design, development, and implementation
contract; a maintenance support services contract; and a software
7 An SPR is a report that provides a summary of proposed changes to the original project cost,
schedule, or scope. An SPR is generally required when the project costs or total financial program
benefits deviate or are anticipated to deviate by 10 percent or more, or a major change occurs in
project requirements or methodology.
California State Auditor Report 2014-116 13
February 2015
license contract.8 According to the project director, Consumer
Affairs is not responsible for funding the project costs; rather, the
total costs of the project are funded by the regulatory entities’
special funds, and the amount each regulatory entity pays is based
on the total number of licenses it processes in proportion to the
total number of licenses that all regulatory entities process.
Consumer Affairs also executed contracts with other nonstate
entities to provide services and expertise to assist with
implementation of the BreEZe system. For example, Consumer
Affairs contracted with private companies to obtain database
consulting services and system testing managers. In total,
Consumer Affairs awarded about $6.3 million in contracts to these
entities, in addition to the Accenture contracts. Table 2 on the
following page lists each contract’s purpose, duration, amount, and
total expended as of September 30, 2014.
Initially, Consumer Affairs had planned for BreEZe to be
implemented across the regulatory entities in five sequential
phases, with a specified group of entities included in each phase.
However, in its contract negotiations with Accenture, Accenture
proposed—and Consumer Affairs agreed—that the number of
phases be reduced to just three, with each phase containing its
own separate design, configuration, and implementation work
efforts while sharing project management processes and refined
system requirements. As shown in Table 3 on page 15, 10 regulatory
entities implemented phase 1 in October 2013, while another eight
are scheduled to implement the system in March 2016 (phase 2),
leaving 19 regulatory entities for phase 3. However, as we describe
further in Chapter 1, CalTech and Consumer Affairs recently
finalized negotiations with Accenture to exclude from the current
design contract the phase 3 regulatory entities. Consumer Affairs
indicated in SPR 3.1, which it submitted to CalTech in January 2015,
that after the successful implementation of phase 2, it will reassess
the best implementation approach for the remaining 19 regulatory
entities; thus, the timing, benefits, costs, and feasibility of that
implementation are unknown.
The Budget Act of 2013 required Consumer Affairs to submit a
report to the Legislature on the status of the BreEZe project no later
than October 1, 2014. The report was to include information on
the implementation of BreEZe by the healing arts boards, funding
allocations, preliminary usage information among new and existing
licensees, and a workload analysis for the positions established to
support this project. However, according to the BreEZe project
director, because the project was not completed by that date
Consumer Affairs did not submit the report.
8 For purposes of our report, when we discuss a specific contract, we identify it as either the design,
maintenance, or system license contract.
14 California State Auditor Report 2014-116
February 2015
Table 2
All Contracts Related to the BreEZe Project and Expenditures Through September 30, 2014
AMOUNT
TOTAL CONTRACT EXPENDED UNDER
VENDOR PURPOSE OF CONTRACT DURATION AMOUNT CONTRACT
Accenture LLP Design development and implementation of the 9/22/2011–12/31/2020 $34,303,065.43 $5,704,000.00
BreEZe system
Accenture LLP BreEZe solution license support 9/22/2011–11/30/2021 7,853,489.75 515,000.00
Accenture LLP Maintenance support services 9/22/2011–9/2/2017 3,544,050.00 519,000.00
LCS Technologies Provide the California Department of Consumer Affairs 5/11/2012–9/11/2012 226,840.00 186,000.00
(Consumer Affairs) with Oracle database
administrator consultant—one consultant
LCS Technologies Oracle database administrator consultant services— 7/15/2013–7/1/2014 242,000.00 242,000.00
one consultant
LCS Technologies Provide Consumer Affairs with Oracle 7/7/2014–7/6/2015 220,000.00 36,000.00
database administrator—one consultant
LCS Technologies Provide Consumer Affairs with a Crystal Reports 7/16/2014–7/15/2015 172,480.00 24,000.00
Enterprise solution architect/Oracle PL/SQL
information technology (IT) consultant—
one consultant
Visionary Integration Provide Consumer Affairs with data conversion senior 8/1/2011–2/28/2015 799,250.00 679,000.00
Professionals* analyst services—one analyst (plus one-year option
to renew)
Sacramento IT Consulting Provide Consumer Affairs with a Natural/Adabas data 12/16/2013–8/15/2015 360,000.00 110,000.00
conversion consultant—one consultant
Informatix Provide Consumer Affairs with project management 6/1/2010–5/31/2015 1,148,760.80 865,000.00
consultant services—one consultant
Infiniti Consulting Group* Provide Consumer Affairs with a user acceptance test 10/15/2011–10/31/2014 710,000.00 675,000.00
manager senior analyst—one analyst (plus one-year option
to extend)
Infiniti Consulting Group Analyze, document, and redesign license renewal 4/22/2013–4/21/2014 115,650.00 94,000.00
forms to make them suitable for optical character
recognition software—one management consultant
and one forms design specialist
Infiniti Consulting Group Provide Consumer Affairs with four IT interface 6/17/2013–6/16/2015 1,386,000.00 605,000.00
systems analysts—four analysts
Infiniti Consulting Group Provide Consumer Affairs with user acceptance 2/1/2014–8/31/2015 920,000.00 247,000.00
testing (UAT) manager and software release manager
consultant—two consultants, one UAT manager, and
one software release manager
MetaVista Consulting† Independent verification and validation (IV&V) 1/3/2011–8/31/2015 991,100.00 601,000.00
consultant—one consultant
Interagency Agreement With Independent project oversight consultant— 7/1/2013–9/30/2017 443,700.00 245,000.00
the California Department of one consultant
Technology (CalTech)
Totals $53,436,385.98 $11,352,000.00
Sources: Contracts provided by Consumer Affairs and its accounting records.
* These contracts include an option to extend the contract for an additional one-year period. In both cases, the additional cost to the State if the option is
exercised is up to $230,000.
† The MetaVista Consulting contract is a contract between CalTech and MetaVista to provide IV&V services specifically on the BreEZe project. As such, we
included the costs for that contract here.
California State Auditor Report 2014-116 15
February 2015
Table 3
California Department of Consumer Affairs’ BreEZe System Release Schedule
IMPLEMENTED IMPLEMENTATION PLANNED IMPLEMENTATION UNKNOWN
PHASE 1 PHASE 2 PHASE 3 *
NUMBER OF NUMBER OF NUMBER OF
RELEASE DATE: OCTOBER 2013 LICENSEES RELEASE DATE: MARCH 2016 (PLANNED) LICENSEES RELEASE DATE: UNKNOWN LICENSEES
Board of Barbering and Cosmetology 484,420 Board of Optometry 26,500 Acupuncture Board 15,490
Board of Behavioral Sciences 90,600 Board of Vocational Nursing and 141,800 Board of Accountancy 134,670
Psychiatric Technicians
Board of Podiatric Medicine 2,650 Bureau of Security and 1,290,960 Board of Chiropractic Examiners 46,430
Investigative Services
Board of Psychology 20,950 California Board of 17,680 Board of Guide Dogs for the Blind 110
Occupational Therapy
Board of Registered Nursing 514,640 Dental Board of California 178,420 Board of Pharmacy 257,810
Medical Board of California 153,820 Dental Hygiene Committee 28,970 Board for Professional Engineers, 236,050
of California Land Surveyors, and Geologists
Naturopathic Medicine Committee 540 Physical Therapy Board of California 46,200 Bureau of Automotive Repair 149,530
Osteopathic Medical Board of 7,890 Veterinary Medical Board 33,800 Bureau of Electronic and Appliance 137,710
California Repair, Home Furnishings and
Thermal Insulation
Physician Assistant Board 9,900 Bureau for Private 2,150
Postsecondary Education
Respiratory Care Board 20,430 California Architects Board 47,540
California Athletic Commission 2,780
Cemetery and Funeral Bureau 35,330
Contractors State License Board 286,620
Court Reporters Board 13,030
Landscape Architect 5,270
Technical Committee
Professional Fiduciaries Bureau 800
Speech-Language Pathology 32,720
and Audiology and Hearing Aid
Dispensers Board
Structural Pest Control Board 118,240
Telephone Medical Advice 60
Services Bureau
Totals 1,305,840 1,764,330 1,522,340
Sources: The California Department of Consumer Affairs (Consumer Affairs), its BreEZe Web site, BreEZe Special Project Reports (SPR) 3 and 3.1, and interviews
with Consumer Affairs’ BreEZe project director.
Note: Although Consumer Affairs consists of 40 regulatory entities, only 37 of these entities were originally scheduled to implement BreEZe. Specifically, the
Bureau of Real Estate and the Bureau of Real Estate Appraisers were brought under Consumer Affairs as a result of the governor’s reorganization plan, effective
July 2013, after the BreEZe project was approved and underway. According to Consumer Affairs, the plan was to implement BreEZe at these two regulatory entities
once the system was fully implemented at the 37 regulatory entities. Another entity, the Arbitration and Certification Program, does not issue licenses and will not
be included in BreEZe.
* Consumer Affairs indicated in SPR 3.1, which it submitted to the California Department of Technology in January 2015, that the project will end after the
phase 2 regulatory entities implement BreEZe, and only after that successful implementation will Consumer Affairs reassess the best implementation
approach for the 19 phase 3 regulatory entities.
16 California State Auditor Report 2014-116
February 2015
Issues With BRN’s Implementation of BreEZe
After BRN implemented BreEZe in October 2013, it reported
experiencing significant delays in the processing of certain types
of license applications, which stakeholders asserted had negatively
affected the employment of both new and experienced nurses. This
issue caused BRN to be the subject of news articles and legislative
hearings. As the regulatory entity responsible for implementing and
enforcing the Nursing Practice Act—the law pertaining to nursing
education, licensure, practice, and discipline—BRN regulates
registered nursing and advanced practice registered nurses to
ensure consumer protection. State regulations require BRN
to process applications for new and renewal licenses according to
specific time frames, which we describe further in Chapter 3. BRN’s
deputy chief of licensing and administrative services reported that
before implementing BreEZe, BRN processed an application to take
a nursing examination, which is the first step in the process to
receive an original license, in approximately three to eight weeks,
using ATS and CAS. In contrast, BRN’s 2014 Sunset Review Report
stated that after the implementation of BreEZe, processing times
for these application types had extended significantly beyond
the 90 days (approximately 13 weeks) specified in regulation
as the upper limit for such processing, and that this had contributed
to a backlog of applications.
Roles and Responsibilities of CalTech and General Services
CalTech and General Services have had certain responsibilities for
overseeing the State’s IT project procurements and, as shown in
Table 4, each entity’s roles have changed since the commencement
of the BreEZe project in 2009. At the time that Consumer Affairs
executed the BreEZe contracts in 2011, General Services had
authority over state agencies’ IT project procurements. Legislation
effective in 2011 required General Services and CalTech to review
all IT RFPs. Subsequent legislation effective July 2013 transferred
General Services’ share of this authority as well as General Services’
authority over IT project procurement to CalTech. As shown
in Table 4, presently CalTech is authorized to undertake all key
responsibilities related to procuring large IT projects whereas
General Services’ responsibilities are limited to contracts for the
acquisition of IT goods and services.9 This shift of responsibilities
9 According to state law, all contracts for the acquisition of IT projects exceeding specified
thresholds—referred to as reportable IT projects—shall be made by or under the supervision
of CalTech. According to CalTech’s Web site, the specified thresholds vary by department and
generally range from $200,000 to $5 million. Contracts for the acquisition of IT projects that
fall below these specified thresholds are overseen by the respective department and must be
reviewed by General Services on a selective basis.
California State Auditor Report 2014-116 17
February 2015
from General Services to CalTech, and the increase in CalTech’s
responsibilities, reflects the Legislature’s conclusion that the unique
aspects of IT projects and their importance to state programs
warrant a separate acquisition authority.
Table 4
Information Technology Oversight Roles and Responsibilities by Key Milestone of the BreEZe Project
FIRST
INITIAL REQUEST FINAL RFP AND IMPLEMENTATION FIRST CONTRACT
FEASIBILITY STUDY REPORT FOR PROPOSAL CONTRACT AWARD, OF BREEZE, AMENDMENT,
KEY RESPONSIBILITY (FSR), NOVEMBER 2009 (RFP), MAY 2010 SEPTEMBER 2011 OCTOBER 2013 FEBRUARY 2014 PRESENT
Information technology California Department of CalTech CalTech CalTech CalTech CalTech
(IT) project approval Technology (CalTech)†
and oversight*
Review of IT RFP California Department General Services CalTech and CalTech CalTech CalTech
of General Services General Services
(General Services)
Review of IT Project General Services General Services General Services CalTech CalTech CalTech
Procurement
Sources: Deering’s California Codes Annotated, 2009–2014; California Government Code, sections 11545 and 11546 (2009, 2011, 2013, 2014);
and California Public Contract Code, sections 12100 and 12104 (2009, 2011, 2013, 2014).
* IT project approval and oversight includes numerous activities, such as evaluating IT projects based on the business case justification;
resource requirements; proposed technical solutions; project management; oversight and risk mitigation approach; and compliance with
statewide strategies, policies, and procedures.
† Until July 2013 CalTech was known as the California Technology Agency and prior to that the Office of the Chief Information Officer.
In addition to its authority to approve IT projects, CalTech is
responsible for IT project oversight. Although CalTech’s project
oversight policy defines both independent verification and
validation (IV&V) and independent project oversight (IPO),
CalTech generally provides IPO while state entities undertaking
IT projects are responsible to contract for IV&V. However, on
the BreEZe project, CalTech has assigned a staff member to
perform IPO and it contracted with a private firm to provide
IV&V to Consumer Affairs. To ensure independence, contracting
directly for IV&V is a practice that CalTech employs based on its
assessment of a project’s risk, criticality, and complexity as well as
the associated state entity’s staff experience. For purposes of our
report, we refer to the individuals who performed these activities
as the IV&V consultant and IPO specialist.
IV&V provides a client, such as Consumer Affairs, with technically
proficient “eyes and ears” to oversee a system vendor while an IT
system is being developed and implemented, and it also provides
early warning of process and technical discrepancies, issues, and
problems that might not otherwise be detected until late in testing
or implementation. Without this early feedback, detection of
anomalies and the resulting system changes required to correct
them are typically delayed until later in the system development
18 California State Auditor Report 2014-116
February 2015
process, resulting in greater costs and schedule delays. In contrast,
IPO provides an independent review and analysis of project
management practices to determine if the project is being well
managed, will be completed within the estimated schedule and cost,
and will provide the functionality the client requires, in this case,
Consumer Affairs. IPO consists of three main components: review
and assessment, reporting, and tracking.
Other Troubled IT Projects California Agencies Have Initiated
Several California state agencies have experienced difficulty
in developing IT systems. For instance, the California State
Controller’s Office’s (state controller) 21st Century Project’s
MyCalPAYS system faced many difficulties and the state controller
has twice terminated project contracts. According to a May 2009
SPR, MyCalPAYS was intended to replace existing statewide human
resource management systems with a fully integrated solution,
including organizational management and payroll functions, among
many others. In April 2005 the state controller contracted with SAP
Public Services, Inc. (SAP) for off‑the‑shelf software that would
be customized to meet the State’s needs. A year later the state
controller hired BearingPoint Inc. as the systems integrator, the
primary contractor, to customize the software as necessary to build
the new system. According to an August 2013 California Senate
Office of Oversight and Outcomes report, in January 2009 the State
terminated the contract with BearingPoint Inc. because it failed to
develop accurate, reliable data conversion programs and scripts.
In February 2010 the state controller hired SAP to develop, test,
deliver, and implement the MyCalPAYS system. In June 2012
the first pilot of the project went live with 1,300 state controller
employees and revealed numerous errors, including employees
being paid too much or too little. In February 2013 the state
controller terminated its contract with SAP, and the director of
CalTech—the oversight authority for the project—suspended the
project. The director of CalTech explained that the department
took action on MyCalPAYS because the contractor refused to
acknowledge issues on the project and to comply with contract
provisions that required the vendor to cure defects the state
controller documented. In May 2013 the Legislative Analyst’s
Office (LAO) reported that at the time of the contract termination,
the State had spent over $262 million on the project.
The California Department of Motor Vehicles’ (DMV)
IT Modernization Project also faced troubles and was ultimately
terminated before its completion. According to an April
2013 LAO report, the goal of the project was to modernize
DMV’s driver license and vehicle registration system. In 2007
California State Auditor Report 2014-116 19
February 2015
DMV awarded a $76 million contract to Electronic Data Systems,
with CalTech performing oversight. Electronic Data Systems was
later purchased in 2008 by HP Enterprise Services. In May 2012
DMV informed HP Enterprise Services that it had serious concerns
regarding HP Enterprise Services’ ability to successfully complete
the project. Specifically, according to the LAO report, DMV
raised concerns regarding vendor staff experience, system delays,
and programming language replacement delays. After observing
a lack of progress between DMV and HP Enterprise Services for
eight months, CalTech exercised its oversight authority to terminate
most of the project, except for one nearly finished component.
As the project was left incomplete, DMV and CalTech are
collaborating to determine the best way to complete the remaining
portions of the project. According to CalTech, the total cost of the
project as of December 2014 was approximately $208 million.
Another recent state IT project that faced challenges during its
rollout is the Continued Claims Redesign subproject (subproject)
of the Employment Development Department’s Unemployment
Insurance Modernization (UI MOD) project. The goal of the
subproject was to enhance Web processes, provide claimants
with increased self‑service, increase efficiency, reduce mail
processing costs, and provide for better detection of fraud. The
contract for the subproject was awarded in February 2010 to
Deloitte Consulting, LLP. According to status reports, the subproject
experienced nine months of delays because of unacceptable
levels of defects before its internal system was accepted. As of
the October 2014 status report, the subproject was developing a
new rollout strategy to use in implementing the online portion of
the system. According to a May 2012 LAO report, the UI MOD
project, including the subprojects, was initially estimated to cost
$96 million, with the Continued Claims Redesign subproject to be
completed by June 2008. However, as of December 2014, CalTech
listed the UI MOD project cost at nearly $190 million and, according
to the October 2014 project status report, the completion date of
the Continued Claims Redesign subproject is unknown.
Finally, Covered California’s California Healthcare Eligibility,
Enrollment and Retention System (CalHEERS) project faced
difficulty before and after its implementation. In May 2012 the
Covered California News Center announced its intent to award
the CalHEERS contract to Accenture for $359 million. The contract
includes the initial development and implementation of the system
and once the system is in place, the continued development and
initial operating costs over approximately three and a half years.
CalHEERS is a Web portal that provides eligibility information
about affordable coverage and offers health plan choice information,
among other things. Because Covered California is an independent
public entity and is statutorily excluded from the regular oversight
20 California State Auditor Report 2014-116
February 2015
of many state control agencies, CalTech officials explained that
CalTech lacked statutory authority to provide oversight on the
project. Rather, Covered California contracted with a private
company to provide IV&V for CalHEERS. A May 2013 consultant
report, before Covered California opened for business, raised
various concerns regarding the project. These concerns included
discrepancies between the schedule and key release dates as
well as inadequate project management processes. According
to a January 2014 progress report produced by the Nicholas C.
Petris Center on Health Care Markets and Consumer Welfare
at the University of California, Berkeley, after the system was
implemented, Web site issues were reported including generally
slow response times and repeated error messages.
Scope and Methodology
The Joint Legislative Audit Committee (audit committee)
directed the California State Auditor (state auditor) to
conduct an audit of Consumer Affairs’ planning, development,
and implementation of its online system for licensing and
enforcement—BreEZe—to determine whether the chosen solution
was justified and whether the solution is meeting the needs of
Consumer Affairs’ regulatory entities. The audit committee also
asked the state auditor to determine the BreEZe system’s effect on
processing license applications at BRN. Table 5 outlines the audit
committee’s objectives and our methodology for addressing each
objective.
Table 5
Audit Objectives and the Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, rules, • Reviewed relevant laws, regulations, and other background materials.
and regulations significant to the • Reviewed state policies regarding procurement and information technology (IT) projects.
audit objectives.
2 Assess whether the California Department • Interviewed key staff of selected Consumer Affairs’ boards, bureaus, committees, and a
of Consumer Affairs (Consumer Affairs) commission (regulatory entities).
followed laws, rules, regulations, policies, • Reviewed BreEZe project oversight documentation, such as independent verification and
and/or best practices when planning, validation (IV&V) consultant and independent project oversight (IPO) specialist reports from
developing, and implementing BreEZe, January 2011 through September 2014.
including the level of outreach provided
• Interviewed key staff at Consumer Affairs, California Department of Technology (CalTech), and
to stakeholders and the adequacy of
the California Department of General Services (General Services).
training provided to staff.
• Consulted an IT expert to identify IT best practices and assessed Consumer Affairs’ compliance
with the identified best practices.
• Reviewed relevant project management planning documents for the BreEZe system.
• Reviewed relevant documents related to the origin and development of the BreEZe system,
including training materials for phase 1 regulatory entities.
California State Auditor Report 2014-116 21
February 2015
AUDIT OBJECTIVE METHOD
3 Review and assess Consumer Affairs’ • Interviewed the BreEZe project director to determine justification for selecting BreEZe.
justification for selecting BreEZe. • Reviewed documentation regarding Consumer Affairs’ justification for selecting BreEZe.
• Reviewed BreEZe procurement documentation to determine if Consumer Affairs appropriately
assessed and vetted bids.
4 Evaluate whether Consumer Affairs • Reviewed BreEZe project documentation and evaluated whether the oversight Consumer
provided sufficient oversight and testing Affairs provided adhered to its internal project planning documents and IT best practices
during the planning, development, and during BreEZe planning, development, and implementation.
implementation of BreEZe, including • Interviewed key staff at Consumer Affairs and CalTech, including the BreEZe
whether the executive office was involved oversight consultant and specialists.
in making key decisions and ensuring
• Reviewed IV&V and IPO reports to determine whether those oversight services were provided
that BreEZe met the needs of the Board of
consistently throughout the course of the project.
Registered Nursing (BRN).
• Reviewed documentation related to results of BreEZe system testing during
system development.
5 Review and evaluate all contracts and • Interviewed key staff related to procurement and contract management at Consumer Affairs,
contract amendments that Consumer General Services, and CalTech.
Affairs entered into with BreEZe’s • Reviewed the three contracts Consumer Affairs has with Accenture LLP related to the
developer and determine whether goals planning, development, and implementation of the BreEZe system—design, development,
have been met based on the expenditures and implementation; maintenance support; and system license—all amendments, and
to date. To the extent possible, determine related procurement documents, to determine the contract requirements and adequacy of
whether the State has adequate recourse recourse options.
in the event that BreEZe vendors and/
• Consulted an IT expert to assess the reasonableness of the contracts and adequacy of
or developers do not fulfill contract
contract terms.
requirements.
• Reviewed 21 key deliverables Consumer Affairs accepted from November 2011 through
June 2014. Based on this review, we did not find any reportable issues.
6 Determine the estimated and actual • Interviewed key staff at Consumer Affairs.
implementation timeline for BreEZe • Reviewed documentation to determine the BreEZe estimated project implementation timeline
and Consumer Affairs’ estimated and and the actual implementation timeline as of January 2015.
actual costs.
• Reviewed original and revised BreEZe project cost estimates through January 2015. These cost
estimates are presented in Table 6 on page 35.
• Obtained BreEZe’s financial tracking documentation and reconciled the invoiced costs to the
California State Accounting and Reporting System accounting records.
7 Determine and evaluate whether • Interviewed Consumer Affairs and BRN staff.
BreEZe’s system design and requirements • Reviewed BRN-specific changes made to the BreEZe system from November 2012 as part
impacted BRN’s implementation of user acceptance testing through phase 1 implementation in October 2013, and from
timeline and business processes. In implementation through July 31, 2014.
addition, determine whether Consumer
• Identified the types of defects BRN noted or enhancements BRN requested and whether those
Affairs modified BreEZe as a result
defects were resolved or enhancements were accepted or rejected.
of the regulatory entities’ business
processes or whether BRN modified its • Determined whether enhancements were processed in accordance with established processes.
business practices to conform with the • Observed changes BRN made to its processes following the implementation of BreEZe.
implementation of BreEZe.
8 Determine the average amount of time • Reviewed BRN’s available documentation regarding its tracking of application processing.
it took BRN to process licenses before • Interviewed key BRN executive staff to determine how BRN tracked its processing of
and after Consumer Affairs implemented license applications.
BreEZe. If processing times increased after
• Obtained database reports from BreEZe and the legacy systems that identified all BRN
implementation, determine the causes for
applicants for licensure from July 1, 2011, through July 30, 2014.
the increases.
• Selected 30 license applications records before BreEZe implementation and 30 applications
after BreEZe implementation, and calculated and compared BRN’s time to process the
applications before and after implementing BreEZe.
9 Assess the current backlog of license • Because of BreEZe and legacy system information limitations, we counted by hand all of the
applications, if any, and determine applications BRN had on site that staff had not yet reviewed as of September 2014, and we
what steps Consumer Affairs and BRN calculated the number of days the application had been waiting to be processed.
are taking or have taken to address any • Interviewed BRN and Consumer Affairs staff to determine steps taken to address BRN’s backlog.
backlog and to provide services for new
and renewing applicants.
continued on next page . . .
22 California State Auditor Report 2014-116
February 2015
AUDIT OBJECTIVE METHOD
10 Determine and evaluate whether • Interviewed key staff at Consumer Affairs and BRN.
Consumer Affairs and/or BRN had • Documented Consumer Affairs’ efforts to address any gaps in staffing, including reviewing
contingency plans in place to address Special Project Reports requesting additional staff.
potential delays in implementing
• Consulted with an IT expert to identify best practices relating to contingency plans.
BreEZe and gaps in staff capacity or the
processing of license applications.
11 Review and assess any other issues that • Developed a questionnaire and interviewed the 10 phase 1 regulatory entities to identify
are significant to the audit. whether their needs were considered in developing the BreEZe system, their satisfaction
with their level of involvement in developing and testing the system, their perspective on the
adequacy of training, and their overall satisfaction with BreEZe.
• Conducted limited research of other state IT projects.
• Obtained and reviewed Statements of Economic Interests for key staff involved in the BreEZe
project from Consumer Affairs, CalTech, and General Services to assess whether any financial
conflicts may exist. Our review covered the period 2009 through 2013, and we did not identify
any reportable issues.
Source: California State Auditor’s analysis of the Joint Legislative Audit Committee’s audit request number 2014-116, and analysis of information and
documentation identified in the column titled Method.
California State Auditor Report 2014-116 23
February 2015
Chapter 1
POOR PLANNING AND DECISION MAKING HAVE LED TO
INCREASED COSTS AND EXTENDED TIMELINES AND HAVE
PLACED THE FUTURE OF BREEZE IN DOUBT
Chapter Summary
Although doing so is critical to the successful development of
information technology (IT) systems, the California Department
of Consumer Affairs (Consumer Affairs) failed to adequately
plan, staff, and manage the project for developing BreEZe, an IT
system it envisioned would support all of the primary functions
and responsibilities of its 40 boards, bureaus, committees, and
a commission (regulatory entities). For example, the foundation
of any IT system is its requirements, which define the business
problem to be solved and specify what the system should do.
However, Consumer Affairs did not adequately assess its regulatory
entities’ business needs to determine BreEZe’s system requirements;
instead, it used high‑level, overly general requirements that it had
gathered for prior projects it had initiated but abandoned. As a
result, the BreEZe project has been plagued with performance
problems, delays, and escalating costs, which, based on a
January 2015 estimate, were $96 million—more than triple the
original estimate—for implementation of a system that will include
only half of the regulatory entities originally planned for BreEZe.
Moreover, staff of the California Department of Technology
(CalTech), in its oversight role, raised significant concerns about
the BreEZe project, ranging from the project’s lack of adequate
resources to the system’s poor planning and development. Despite
the seriousness of these concerns and the various points in the
project’s life when they could have used their authority to intervene,
both CalTech and Consumer Affairs officials allowed the project to
continue without adequately addressing these concerns. Had either
party exercised its authority earlier than the summer of 2014—nearly
five years after the project began—such as during the planning
phase, BreEZe could have been suspended and either rescoped,
adequately resourced, or terminated, thereby avoiding potentially
unnecessary costs.
Because of the many issues the BreEZe project has encountered,
particularly its cost increases, Consumer Affairs and CalTech
renegotiated the contract with the project vendor, Accenture LLP
(Accenture), to remove the regulatory entities originally scheduled
to implement the system in the final phase (phase 3). As of
January 2015 only 10 regulatory entities had transitioned to BreEZe
(phase 1); eight more intend to transition to it in March 2016, and it
24 California State Auditor Report 2014-116
February 2015
is unknown whether or when the remaining 19 will transition to the
system. Although Consumer Affairs has indicated it will reassess
the best implementation approach for these 19 regulatory entities
after the successful completion of phase 2, it has yet to assess the
extent of the changes these entities may require be made to the
system and it lacks an implementation plan. We believe that should
Consumer Affairs elect to implement BreEZe at these 19 regulatory
entities, it should include this assessment as part of an analysis of
the costs and benefits of moving forward with this implementation
to ascertain whether its proposed approach is feasible and
cost‑beneficial.
Consumer Affairs Did Not Adequately Identify the Business Needs of
Its Regulatory Entities When Planning the BreEZe Project
Consumer Affairs failed to properly assess the regulatory entities’
business needs when developing the system requirements for
BreEZe. According to our IT expert, system requirements define
the business problem to be solved and specify what the system
should do. For example, a system requirement could be that the
system allows a regulatory entity to record the date it receives
an application. In its 2014 Chaos Report, the Standish Group
presented results of a survey of IT executives that identified a clear
statement of requirements is one of the major factors leading to
project success and that incomplete requirements are a main factor
leading to impaired and ultimately canceled projects. 10 Therefore,
Consumer Affairs should have taken steps to ensure that the system
requirements for BreEZe were based on the current business
needs of its regulatory entities so that the resulting system would
Consumer Affairs relied on system be designed and built in a manner that would aid those regulatory
requirements from earlier projects entities in conducting their business operations and fulfilling their
that were abandoned when regulatory responsibilities. However, when developing the system
developing the requirements requirements for BreEZe, Consumer Affairs relied on requirements
for BreEZe. from earlier projects that were abandoned.
According to the BreEZe project director, Consumer Affairs used
the requirements it had identified from three earlier IT project
initiatives; the first started as early as 2000 and the last abandoned
in 2009. The project director stated that the regulatory entities had
been involved in developing the requirements for those earlier
unsuccessful initiatives. He also asserted that the system
requirements for each of the initiatives were combined into
one comprehensive project—BreEZe. Thus, it is likely that the
requirements Consumer Affairs had identified for its previous
10 The Standish Group is a primary research advisory organization that focuses on software
project performance.
California State Auditor Report 2014-116 25
February 2015
initiatives and used as the basis for BreEZe were outdated, further
hindering Consumer Affairs’ ability to develop a system that would
sufficiently meet its regulatory entities’ needs.
Although Consumer Affairs invited the majority
of its regulatory entities to participate in refining BreEZe System Request for Proposal
the requirements for BreEZe during the request Working Sessions Requirements Statistics
for proposal (RFP) process for the project, the
• Reviewed over 900 requirements with bidders in the
BreEZe project director stated that only some
working sessions.
regulatory entities participated. During this process
in October 2010, Consumer Affairs held working • Deleted over 350 requirements.
sessions over a three‑week period with the potential • Revised nearly 500 requirements.
bidders and regulatory entities to review and
• Created approximately 230 new requirements.
modify the system requirements. Consumer Affairs
revised hundreds of the more than 900 system Source: BreEZe System Independent Project Oversight Report,
December 2010.
requirements as a result of the working sessions.
The text box presents the statistics of these
revisions. However, according to the BreEZe project
director, these sessions typically resulted in high‑level requirements
that described general functionality, not the specific business
processes of the regulatory entities. As we discuss in Chapter 3,
most of the executive officers of the phase 1 regulatory entities are
generally dissatisfied with BreEZe because it did not meet their
expectations in a variety of ways.
In addition, Consumer Affairs incorrectly assumed that the
regulatory entities could all use similar business processes. For
example, the BreEZe project team had the misconception that the
regulatory entities used similar processes to collect and record
licensing fees, process license applications, and issue licenses.
The BreEZe project director explained that Consumer Affairs did
not understand the depth and breadth of the regulatory entities’
operations and licensing functions, nor did it understand the lack
of flexibility within the regulatory entities to make changes to
their processes. Further, he indicated that the assumption of these
similarities in the regulatory entities’ processes led Consumer
Affairs to intentionally write the system requirements at a high level
to attract a vendor with a commercial “off‑the‑shelf” (COTS)‑based
solution, such as the BreEZe system.
Pressure to Move the Project Forward Caused Consumer Affairs to
Expedite the Planning Process and Choose an “Off‑the‑Shelf” Solution
The BreEZe project director stated that part of the reason the BreEZe
project team, which is composed of Consumer Affairs staff and was
responsible for developing the project’s Feasibility Study Report (FSR)
and its requirements, did not reach out to the regulatory entities
before issuing the RFP was because of pressure the project team
26 California State Auditor Report 2014-116
February 2015
received from Consumer Affairs’ executive office, control agencies,
and agency officials to expedite the development of the FSR for
BreEZe, which it completed during October and November 2009.
The RFP was released six months later, in May 2010.
The BreEZe project director perceived that much of the pressure
resulted from an internal review of Consumer Affairs’ enforcement
processes at the healing arts boards, which regulate a variety of
professions, from doctors and nurses to physical therapists and
optometrists. Consumer Affairs undertook this review in 2009
in response to delays in certain investigation and enforcement
actions that the governor described as “completely unacceptable.”
We describe this initiative, the Consumer Protection Enforcement
Initiative, in the Introduction. However, when we inquired with
Consumer Affairs’ director and its current agency—the California
Business, Consumer Services and Housing Agency—neither entity
could confirm whether there had been pressure to expedite the FSR.
Because Consumer Affairs wanted BreEZe to be developed quickly,
it identified as an alternative to its legacy systems a COTS solution,
which is an existing, commercially available software product
that can be put to use more quickly than a product designed from
scratch. At least in part because of faulty assumptions that the COTS
In 2009 Consumer Affairs estimated product would require only minor modifications and that minimal
that BreEZe would cost about resources and time would be necessary to make these modifications,
$28 million. In January 2015 it the estimated costs for the BreEZe project have drastically outpaced
estimated it could cost $96 million initial projections. Although Consumer Affairs initially estimated in
for implementation and would 2009 that the project would cost about $28 million, in January 2015
include only half of the regulatory it estimated it could cost $96 million for implementation of BreEZe
entities that originally planned to and that implementation would include only half of the regulatory
use the system. entities that originally planned to use the system.
It appears that Consumer Affairs’ selection of the BreEZe COTS
product may not have been the appropriate and most cost‑effective
decision. In particular, according to the project director, the
BreEZe project team believed that similarities in the regulatory
entities’ processes and their respective leadership’s commitment to
the project vision, including implementing a COTS solution and
standardizing the regulatory entities’ processes, would mitigate
some of the issues created by using such high‑level requirements.
However, the BreEZe project director indicated that there was
a disconnect between the expectations of the regulatory entities
and the expectations of Consumer Affairs, in that Consumer
Affairs expected that the regulatory entities would modify their
business processes and the regulatory entities were not expecting
to need to do so. In addition, Consumer Affairs’ director noted
that Accenture’s approach to understanding the business needs of
the phase 1 regulatory entities resulted in a system design that did
not reflect the business requirements of the regulatory entities.
California State Auditor Report 2014-116 27
February 2015
Consumer Affairs’ director further stated that had Consumer
Affairs known of these challenges at the time it was developing the
FSR for BreEZe, which contained its analysis of the need for a new
IT system and the proposal for a COTS, the department might
had chosen to procure the development of a new, fully customized
system to meet its needs.
Although Consumer Affairs described the development of a fully
customized system as an alternative to a COTS in its FSR, it cited
unacceptable risks for this type of system, stating that it would
have the highest overall costs of any IT solution and would take
the longest time to develop and implement. The BreEZe project
director explained that Consumer Affairs estimated at the time it
developed the FSR that it would cost about $30 million to procure
a COTS product, while the development of a new system would
have cost around $80 million. Nevertheless, as we previously stated,
as of January 2015, the estimated cost of the COTS solution has
more than tripled to $96 million and will include only half of the
regulatory entities as originally planned.
Consumer Affairs Failed to Maintain a Baseline of Requirements for
the BreEZe Project
A fundamental problem related to the BreEZe system design that
the independent verification and validation (IV&V) consultant
raised as early as February 2011 was that Consumer Affairs failed
to maintain an effective baseline of requirements—the official
agreed‑upon set of requirements defining how the system should
operate. According to our IT expert, these requirements define
the scope of the solution to be delivered and are the basis for cost
and schedule estimation, planning, execution, and monitoring. The
RFP established the initial baseline of requirements for the BreEZe
system, which was included in the design contract.11 Subsequent
development activities that refine the requirements must be
documented and then they become the new baseline.
Our IT expert noted that establishing and maintaining a baseline Our IT expert noted that establishing
of requirements is essential and that before a vendor builds a and maintaining a baseline of
system, there should be a standard process to refine, confirm, and requirements is essential and that
maintain the requirements baseline. This means that for the BreEZe before a vendor builds a system,
project, Accenture and Consumer Affairs should have agreed to there should be a standard process
and documented clear and measurable requirements for the BreEZe to refine, confirm, and maintain the
system that must be satisfied so that both entities can determine requirements baseline.
11 There are three contracts related to the BreEZe project—one contract for design, development,
and implementation; another contract for maintenance support; and a third contract for
the system license. When we discuss a specific contract, we identify it as either the design,
maintenance, or system license contract.
28 California State Auditor Report 2014-116
February 2015
whether the system operates as needed. However, according
to the BreEZe project director, Consumer Affairs intentionally
did not maintain a baseline of requirements that reflected the
requirements for the phase 1 regulatory entities because the design
of the system was meant to be established through an iterative
process as Accenture defined in its RFP response. According to
our IT expert, although an iterative approach can be appropriate,
because Consumer Affairs failed to maintain and update a system
requirements baseline to reflect any changes identified during
this iterative process, it did not effectively support the design
and implementation of the system. Because establishing and
maintaining a baseline of requirements is a critical process for
effectively building a system, our IT expert believes the project
should have been suspended when concerns were raised about the
quality of the baseline of requirements, and that it should have been
revised accordingly, as we discuss later in this chapter.
The BreEZe Project Has Experienced Significant Delays
The BreEZe project has experienced significant delays at key stages
of the project. Figure 1 displays the project’s planned and actual key
User acceptance testing for phase 1 milestones since its commencement. As shown in the figure, the
regulatory entities spanned most extreme delay involved the key milestone of user acceptance
11 months, significantly exceeding testing—testing that future users conduct of the system that confirms
the originally planned eight weeks. that the system operates as the requirements specify. User acceptance
testing for phase 1 regulatory entities spanned 11 months, from
the end of November 2012 through October 2013, significantly
exceeding the originally planned eight weeks. According to the IV&V
consultant, this extensive testing period likely resulted in part from
the BreEZe system having almost 1,700 unresolved system defects
at the beginning of user acceptance testing.
According to our IT expert, the bulk of the defects were likely
attributable to the poor system requirements. Although user
acceptance testing is one of the final and most critical procedures
undertaken before system implementation to ensure that the system
operates appropriately, this phase morphed into a redesign of the
requirements and a rework of the system. Specifically, in conducting
the testing of the system, some of the 10 phase 1 regulatory entities as
well as Consumer Affairs itself learned that the system did not operate
as they expected or needed. For example, during user acceptance
testing in January 2013, the average rate at which the system failed
on the first attempt to provide the anticipated result was 61 percent.
Had Consumer Affairs performed a complete, current assessment of
the regulatory entities’ needs to determine the system requirements
for BreEZe, it is likely that user acceptance testing could have been
completed within a more reasonable time frame, thus avoiding some
of the 15‑month implementation delay in phase 1.
California State Auditor Report 2014-116 29
February 2015
1 erugiF
senotseliM
yeK lautcA
dna dennalP
tcejorP
eZEerB
1 esahP
PFR sesaeler
secivreS lareneG
snigeb
gnitset metsys
tnemtrapeD
ainrofilaC
sriaffA
remusnoC fo
detelpmoc
si
ngised
deliated
1 esahP
defiilauqerp
era sreddiB
)sriaffA
rem st u im sn b o u C s (
ytilibisaeF
eZEerB
)RSF(
tropeR ydutS
—ecnatpecca
metsys
lluF
secivreS
lareneG
tcejorp
detamitsE
ylno
2 dna
1 sesahp
fo gninepo
devorppa
noillim
5.72$ :tsoc
2 RPS
stimbus
sriaffA
remusnoC
gnitset
metsys
1 esahP
htiw noitaitogen
noillim
9.77$
:tsoc
tcejorp
detamitsE
detelpmoc
si
stimbus
sriaffA remusnoC
evisnopser
ylno
2 esahp
detcejorP
1 )RPS( tropeR
tcejorP laicepS
PLL erutneccA
rodnev
noitatnemelpmi
ecnatpecca
resu
1 esahP
noillim
8.54$ :tsoc
tcejorp detamitsE
)erutneccA(
detnemelpmi
1 esahP
snigeb
gnitset
dedrawa
era stcartnoC *erutneccA
ot
ecnatpecca
resu
1 esahP
tcartnoc
laniF
etelpmoc
si gnitset
stnemeriuqer
eludehcs
tcejorP
desaeler
era
devorppa si
3102
2102
1102
0102
9002
2
esahP
1 esahp
etelpmoC
noitatnemelpmi
gnitset
ecnatpecca
resu
tcejorp
e e l v u o d r e p h p c A s
yfilauqerP
noitatnemelpmi
1 esahP
sreddib
etelpmoc
sesahp
eerht
lla—ecnatpecca
metsys
lluF
tcartnoc
lanfi esaeleR
stnemeriuqer
1 esahp nigeB
gnitset
ecnatpecca
resu
rodnev
tceleS
noitatnemelpmi
3
esahP
1 esahp etelpmoC gnitset metsys
tcartnoc
drawA
1 esahp
nigeB
secivreS lareneG
fo tnemtrapeD
ainrofilaC
gnitset
metsys
’sriaffA remusnoC
sesaeler )secivreS
lareneG(
)PFR( lasoporp
rof tseuqer
ngised
deliated 1
esahp
etelpmoC
ceD
voN
tcO
tpeS
guA
luJ
nuJ
yaM rpA
raM beF
naJ
ceD
voN
tcO
tpeS guA luJ
nuJ
yaM
rpA
raM
beF naJ ceD voN
tcO tpeS guA
luJ
nuJ
yaM
rpA
raM beF
naJ ceD voN tcO
tpeS guA luJ nuJ
yaM rpA
raM
beF naJ ceD voN
ygolonhceT
fo tnemtrapeD
ainrofilaC
3 RPS
sevorppa
)hceTlaC(
3
RPS stimbus
sriaffA
remusnoC
†noillim
4.811$
:tsoc
tcejorp
detamitsE
6102
5102
4102
ceD voN
eht
retfa
dne lliw tcejorp
eZEerB
ehT
yllufsseccus
seititne yrotaluger
2 esahp
noitatnemelpmI
.metsys
eht tnemelpmi
yrotaluger
3 esahp
eht yb eZEerB
fo
stsoc eht
suht
dna ,dennalpnu
si seititne .nwonknu
era
sriaffA
remusnoC
3 RPS
swardhtiw
nuJ yaM
rpA
raM naJ
tcO
tpeS
guA
luJ
nuJ
yaM rpA
raM beF
naJ
LAUTCA DENNALP gnitseT fo noitaruD
gnitset
ecnatpecca
resu 1 esahP
sriaffA
remusnoC
1.3
RPS stimbus
detamitsE :tsoc
tcejorp
‡noillim
1.69$
.slaicffio
’sriaffA
remusnoC
htiw
sweivretni
dna
;4102
rebmetpeS
fo
sa
eludehcs
tcejorp
devorppa
;tropeR
ytivitcA thgisrevO
tcejorP
tnednepednI
1102 rebmevoN
;PFR
eZEerB
;sRPS dna
RSF eZEerB ’sriaffA
remusnoC
:secruoS
.esnecil
metsys
eht
rof
tcartnoc
driht
a dna
;troppus
ecnanetniam
rof rehtona
;noitatnemelpmi
dna ,tnempoleved
,ngised rof tcartnoc
eno—tcejorp
eZEerB
eht ot detaler
stcartnoc erutneccA
eerht era erehT
*
detcejorp
eht
edulcni
ton seod
tnuoma
siht
,suhT
.seititne
yrotaluger
2
esahp
eht
ta eZEerB
fo
noitatnemelpmi
eht hguorht
detcejorp
sriaffA
remusnoC
stsoc
esoht
ylno
serutpac 3 RPS
ni detneserp
etamitse
tsoc latot ehT
†
.3 esahp
ni dedulcni
yllanigiro
seititne
yrotaluger
eht ta eZEerB
gnitnemelpmi
rof stsoc
ton
seod
tnuoma
siht ,suhT
.tcejorp
eZEerB
eht
morf
yleritne
3
esahp
evomer
ot ,4102
,1
rebmeceD
no
erutneccA
htiw
snoitaitogen
dedulcnoc
seititne
eseht
retfa
hceTlaC
ot sriaffA
remusnoC yb
dettimbus
saw 1.3 RPS
‡
.3 esahp
ni
dedulcni
yllanigiro seititne
yrotaluger
91
eht
ta eZEerB
gnitnemelpmi
rof stsoc
detcejorp
eht edulcni
30 California State Auditor Report 2014-116
February 2015
CalTech and Its Contractor Raised Significant Concerns About the
BreEZe Project Throughout the Oversight Process
CalTech did not begin providing independent oversight of the
BreEZe project until roughly one year after it approved the FSR
for the project. However, once oversight began, Consumer Affairs
failed to respond appropriately to the significant and persistent
concerns CalTech raised, while for its part, CalTech did not
intervene to ensure that Consumer Affairs took corrective action.
Under state law, CalTech is responsible for oversight of IT projects.
CalTech generally uses two types of independent oversight:
IV&V—used to ensure that a system satisfies its intended use and
user needs—and independent project oversight (IPO)—used to
ensure that effective project management practices are in place and
in use. On the BreEZe project, which CalTech acknowledged is
large, complex, and costly, its own staff have provided IPO services,
whereas CalTech contracted with MetaVista Consulting—an IT
consulting firm—to provide IV&V services.
As shown in Figure 2, the IV&V consultant and the IPO specialist
raised significant concerns about the project from early 2011, after
they began providing oversight, through phase 1 implementation
in October 2013. Moreover, in their reports from December 2010
through September 2014, they collectively raised what our IT expert
categorized as nearly 180 significant concerns in areas including
project management, staffing, system requirements, and vendor
performance. We present these concerns in detail in the Appendix.
According to our IT expert, the volume and significance of these
The volume and significance concerns should have prompted both CalTech and Consumer
of concerns raised by the IV&V Affairs to analyze fully the costs and benefits of proceeding
consultant and the IPO specialist versus suspending or terminating the project. However, although
about the BreEZe project should the IV&V consultant and the IPO specialist presented these
have prompted both CalTech and concerns to the BreEZe project team and CalTech management
Consumer Affairs to analyze fully in monthly reports, neither entity took sufficient action to ensure
the costs and benefits of proceeding that all concerns were appropriately addressed and CalTech
versus suspending or terminating allowed the project to continue for more than three years without
the project. significant intervention.
California State Auditor Report 2014-116 31
February 2015
2
erugiF
3102
rebotcO
hguorhT
noitpecnI
eZEerB
morF
snrecnoC
thgisrevO
yeK
detceleS dna
senotseliM
yeK
fo enilemiT
eZEerB
1 esahP
secivreS
lareneG fo tnemtrapeD
ainrofilaC
snigeb
gnitset
metsys
tseuqer sesaeler )secivreS
lareneG(
tnemtrapeD
ainrofilaC
lasoporp
rof
sriaffA remusnoC
fo
)sriaffA
remusnoC(
detelpmoc
si ngised
deliated
1 esahP
defiilauqerp
era sreddiB
stimbus
ytilibisaeF
eZEerB
)RSF( tropeR
ydutS
secivreS
lareneG
tcejorp
detamitsE
fo
gninepo devorppa
noillim
5.72$
:tsoc
2
RPS
stimbus
sriaffA
remusnoC
gnitset
metsys
1 esahP
stimbus
sriaffA
remusnoC
htiw
noitaitogen tsoc
noillim
9.77$
:tsoc
tcejorp
detamitsE
detelpmoc
si
1
)RPS(
tropeR
tcejorP
laicepS
evisnopser
ylno eht
noillim
8.54$
:tsoc
tcejorp
detamitsE
saw
hcihw ,rodnev
PLL
erutneccA
ecnatpecca
resu
1 esahP
)erutneccA(
detnemelpmi
1 esahP
snigeb
gnitset
dedrawa
era
stcartnoC
*erutneccA
ot
ecnatpecca
resu 1 esahP
etelpmoc
si gnitset
laniF tcartnoc
eludehcs
tcejorP
stnemeriuqer
devorppa
si
desaeler era
SENOTSELIM TCEJORP YEK SNRECNOC THGISREVO
3102
2102
1102
0102
9002
gnitset
ecnatpecca
resu hgiH etar eruliaf
si 1 esahP
revo
htiw
detnemelpmi
gnitubirtnoc
si erawtfos
ytilauq-rooP
ffats delliks etauqeda
skcal
maet
tcejorP
seussi
devlosernu
000,1
syaled
gnitset
ecnatpecca
resu
ot
stnemeriuqer
etauqedani
sniatnoc
PFR
gnilbuort
era secitcarp tnemeganam
ksiR
yrotaluger
eht
enilesab
ton did sriaffA
remusnoC
nehw
stnemeriuqer
lanoitcnuf
’seititne
dewollof
gnieb
ton era sdradnats gnireenigne
erawtfoS
1 esahp
fo ngised
eht gnivorppa
gnitroper
tsoc
ro
nalp
tnemeganam
tsoc evah
ton seod
tcejorP
eludehcs
no
sksat
1 esahp
etelpmoc
ot elbaliava
si
gnffiats
tneicffiusnI
ot
serusaem
skcal
sriaffA
remusnoC
detelpmoc
krow
fo
tnuoma
enimreted
era
stnemeriuqer
hcihw
yfitnedi
ot
yaw
on
si erehT
ytitne yrotaluger
hcae
rof
detnemelpmi
gnieb
secruoser
ecnarussa
ytilauq
etis-no
oN
detareneg
ton era
stroper
nalP
noisrevnoC
ataD
erutneccA
snalp
tnemeganam
tcejorp
gniwollof
ton
si
sriaffA
remusnoC
selbareviled
etauqedani
gnittimbus
si
erutneccA
dna
tsilaiceps
thgisrevo
tcejorp
tnednepednI
tnatlusunoc
noitadilav
dna noitacfiirev
tnednepednI
tcO
tpeS
guA
luJ
nuJ
yaM rpA
raM beF
naJ ceD
voN
tcO
tpeS
guA
luJ
nuJ
yaM
rpA
raM
beF
naJ
ceD
voN
tcO
tpeS
guA
luJ
nuJ
yaM
rpA
raM
beF
naJ ceD voN tcO tpeS
guA
luJ
nuJ
yaM
rpA
raM beF
naJ
ceD
voN
htiw
snigeb
gnitset
ecnatpecca
resU
seussi
devlosernu
286,1
thgisrevO
)hceTlaC(
s’ygolonhceT
fo tnemtrapeD
ainrofilaC
tsilaiceps
thgisrevo
tcejorp
tnednepedni
oN
tnatlusnoc
noitadilav
dna
noitacfiirev
tnednepedni
oN
nrecnoC
thgisrevO
eht
desiaR
ytraP
hcihW
setacidnI
roloC
txeT
.tnatlusnoc
noitadilav
dna
noitacfiirev
tnednepedni
eht
dna
tsilaiceps
thgisrevo
tcejorp
tnednepedni
hceTlaC
eht
yb stroper dna ,sRPS
dna
RSF
eZEerB
’sriaffA
remusnoC
:secruoS
.esnecil
metsys
eht
rof
tcartnoc
driht
a dna
;troppus
ecnanetniam
rof
rehtona
;noitatnemelpmi
dna
,tnempoleved
,ngised
rof
tcartnoc
eno—tcejorp
eZEerB eht ot
detaler
stcartnoc
erutneccA
eerht
era
erehT
*
32 California State Auditor Report 2014-116
February 2015
The IV&V Consultant and the IPO Specialist Raised Concerns About
Consumer Affairs’ Decisions That Significantly Affected Phase 1 of the
BreEZe Implementation
One of the concerns the IV&V consultant raised in October 2012
was that Consumer Affairs was not maintaining an updated
requirements baseline, as discussed previously, and this issue
became a significant problem for the BreEZe project. For example,
it prevented the IV&V consultant from conducting a critical
oversight activity, in that the consultant could not verify whether
the system being developed functioned as Consumer Affairs
and the regulatory entities needed. This oversight activity, which the
IV&V consultant reported as a concern in May 2012, is an ongoing
process that occurs throughout the development of a system. The
IV&V consultant reported that many of the problems identified
during testing of the BreEZe system were related to specific
functional requirements of the regulatory entities that Consumer
Affairs had not included in the requirements baseline.
CalTech and the regulatory entities also expressed concern over
Consumer Affairs ending user acceptance testing before all of the
problems with BreEZe’s operation had been addressed. Overall,
More than 1,000 defects of more than 1,000 defects of various severity levels remained
various severity levels remained unresolved at the end of the testing period for phase 1. According to
unresolved at the end of the CalTech’s IT project oversight and consulting division’s (oversight
testing period for phase 1 of division) branch chief (branch chief), given the severity of some
the BreEZe implementation. of the outstanding issues, CalTech advised Consumer Affairs that
user acceptance testing should be extended to allow Accenture
time to resolve the most significant issues. Separately, several
regulatory entities expressed concerns before they began using
the system that BreEZe was not functioning as needed. However,
Consumer Affairs asserted that it fixed the most critical system
issues during the original extended user acceptance testing period
and, despite the numerous concerns, it moved forward with the
phase 1 implementation.
Given CalTech’s authority and the significant concerns it had raised
about the status of the project, we question why it did not take
steps to ensure that Consumer Affairs heeded its advice to extend
user acceptance testing. For instance, CalTech could have formally
warned Consumer Affairs that it would suspend the project if the
department did not bring the project back into alignment with its
planned scope, cost, and schedule. As illustrated in Figure 1 on
page 29, the estimated project costs had increased from roughly
$28 million to almost $78 million and the project experienced
significant delays in its schedule before Consumer Affairs ended
user acceptance testing. In addition, CalTech could have required
Consumer Affairs to conduct an analysis of the BreEZe project so
California State Auditor Report 2014-116 33
February 2015
that CalTech could determine whether the benefits of suspending
or terminating the project outweighed the costs of moving forward
as planned; however, it has not required such an analysis.
The IV&V Consultant and the IPO Specialist Reported That Consumer
Affairs Lacks Sufficient Staff to Adequately Manage the BreEZe Project
One of the key concerns that both the IV&V consultant and the
IPO specialist raised has been that the BreEZe project team lacks
appropriate resources. For example, in a June 2013 report, the
IPO specialist indicated that the project team was inadequately
staffed to complete phase 1. In addition, the IPO specialist reported
periodically, beginning in April 2012, that he also had concerns
with the resources the regulatory entities committed before and
during user acceptance testing for phase 1, as the staff were not
assigned exclusively to the project and their availability was in
question in the face of project delays. Further, a CalTech branch
chief in the oversight division who oversaw the IPO specialist’s
work from May 2012 through February 2014 told us that Consumer
Affairs did not and still does not have enough skilled personnel to
handle the complex BreEZe contracts with Accenture. As a result Consumer Affairs has not had
of these combined factors, it appears Consumer Affairs has not had adequate staffing to execute and
adequate staffing to execute and implement BreEZe through critical implement BreEZe through critical
project phases. project phases.
As of June 2014 Consumer Affairs’ executive management
acknowledged that primarily because of an expanded project scope,
Consumer Affairs needs additional staff to manage the development
and implementation of the project through phase 2. As explained
in the Special Project Report (SPR) 3, since the inception of the
BreEZe project in 2009, the project has been able to borrow
from within Consumer Affairs and from the regulatory entities
to fill critical project positions and keep the project moving.12 It
appears, however, that given the project’s evolution, that is no
longer possible.
Furthermore, Consumer Affairs did not have sufficient
staff to conduct organizational change management at the
phase 1 regulatory entities, which is critical for preparing the
affected employees to adapt to changes. In the case of BreEZe,
organizational change management, including business process
analysis, would have identified the changes the regulatory entities
12 An SPR is a report that provides a summary of proposed changes to the original project cost,
schedule, or scope. An SPR is generally required when the project costs or total financial program
benefits deviate or are anticipated to deviate by 10 percent or more, or a major change occurs in
project requirements or methodology.
34 California State Auditor Report 2014-116
February 2015
needed to make to their internal operations so that they could
prepare for those changes. According to the BreEZe project
director, Consumer Affairs did not undertake organizational change
management because the department redirected the funding
for that activity to support other higher‑priority project needs,
which he defined as every other activity that was completed for
the BreEZe project. In other words, Consumer Affairs considered
organizational change management to be a lower priority than
everything else the project has completed. By ignoring this essential
step in project management for phase 1, Consumer Affairs missed
a key opportunity to improve the regulatory entities’ transition to
using BreEZe and may have contributed to the executive officers
of several phase 1 regulatory entities indicating that they felt
unprepared to implement the system.
Another negative effect of the BreEZe project team not having
enough staff is that in August 2014, Consumer Affairs began
considering making payments to Accenture to extend the project
schedule to complete necessary work. Specifically, in two instances,
Consumer Affairs requested that Accenture add a total of 28 days
to the project schedule for designing phase 2 at an estimated
cost to the State of nearly $2 million. According to Consumer
Affairs’ documents requesting the additional days, it does not have
sufficient resources available to review certain planning documents
for phase 2 within the existing schedule.
Despite Significant Cost Increases, CalTech Did Not Significantly Increase
Its Involvement on the BreEZe Project Until Summer 2014
Although CalTech was well aware CalTech was well aware of the significant problems with the BreEZe
of the significant problems with project, yet it approved additional funding for it. As shown in
the BreEZe project, it approved Table 6, estimated project costs have increased from an original
additional funding for it. estimate of approximately $28 million in 2009 to more than
$96 million in 2015 for implementation of the system at only half
of the regulatory entities included in Consumer Affairs’ original
cost estimate. Specifically, Consumer Affairs indicated in two SPRs
it submitted in June 2011 (SPR 1) and July 2013 (SPR 2) that the
project’s estimated costs had increased by nearly 70 percent (SPR 1)
and by more than 180 percent (SPR 2) from the original estimate
of nearly $28 million as reported in its 2009 FSR. According to
CalTech’s analysis of SPR 2, there were three key reasons for this
increase as of June 2013. First, the single most important driver
for the cost increase was the extended project duration of more
than two years past the original completion date of October 2013.
Second, the project team planned to hire additional project
contractors because it had underestimated the complexity of the
BreEZe system. Finally, Consumer Affairs increased the budget for
Accenture to perform unanticipated tasks. However, as we discuss
California State Auditor Report 2014-116 35
February 2015
later, CalTech did not ensure that Consumer Affairs addressed the
CalTech director’s concerns about project management, project
governance, and contract management before approving two SPRs
that identified significant project cost increases.
Table 6
BreEZe Estimated Cost Increases Since the Project’s Inception From November 2009 Through January 2015
(Dollars in Millions)
AMOUNT CHANGE PERCENTAGE CHANGE
TOTAL COST FROM INITIAL FROM INITIAL
DOCUMENT DATE OF ESTIMATE ESTIMATE ESTIMATE IN 2009 ESTIMATE IN 2009
Feasibility Study Report November 10, 2009 $27.5 $0.0 0%
Special Project Report 1 June 22, 2011 45.8 18.3 66.5
Special Project Report 2 July 22, 2013 77.9 50.4 183.3
Special Project Report 3* June 25, 2014 118.3 90.8 330.2
Special Project Report 3.1† January 7, 2015 96.1 68.6 249.5
Sources: California Department of Consumer Affairs’ (Consumer Affairs) BreEZe Feasibility Study Report, and Special Project Reports (SPR).
* The total cost estimate presented in SPR 3 captures only those costs Consumer Affairs projected through the implementation of BreEZe
at the phase 2 regulatory entities. Thus, this amount does not include the projected costs for implementing BreEZe at the 19 phase 3
regulatory entities. Further, although SPR 3 was initially approved by the California Department of Technology (CalTech) in July 2014,
Consumer Affairs withdrew the report in September 2014. According to the BreEZe project director, Consumer Affairs withdrew SPR 3
at the direction of CalTech and the California Department of Finance.
† SPR 3.1 was submitted by Consumer Affairs to CalTech after these entities concluded negotiations with Accenture LLP on
December 1, 2014, to remove phase 3 from the BreEZe project.
At the time that CalTech approved SPR 2, it believed the additional
project funding was necessary to help ensure BreEZe’s success.
When we asked CalTech officials why the department did not
become more involved in the project at the time it reviewed and
approved SPR 2 in October 2013, CalTech’s oversight division
deputy director (deputy director) pointed to CalTech’s analysis for
approving SPR 2. In addition, she stated that the additional funding
Consumer Affairs had requested was warranted so that the future
phases of BreEZe would be better planned and executed than
phase 1. Although this may have been the intent of the additional
funding, it did not resolve the requirements issues that had
negatively affected the BreEZe project. Moreover, in its approval of
SPR 2, CalTech did not address all of the key problems it identified
in its analysis of the SPR, such as inadequate resources assigned
to the project. Thus, we believe that rather than approving SPR 2
and the significant cost increase, CalTech should have taken action
to compel Consumer Affairs to address the requirements issues
including, if necessary, suspending the project.
Furthermore, CalTech had not ensured before approving SPR 3
that Consumer Affairs had addressed the conditions CalTech
established in approving SPR 2 in October 2013. For example,
36 California State Auditor Report 2014-116
February 2015
when CalTech approved Consumer Affairs’ SPR 3 in July 2014,
it knew that Consumer Affairs should have provided it with a
baseline workplan, which is essentially the project schedule, for
phase 2 before starting design activities for phase 2, which began in
December 2013, according to the BreEZe project director. However,
according to an IPO report in June 2014, Consumer Affairs still had
not provided the baseline workplan. Even though CalTech’s analysis
for SPR 3 acknowledged that Consumer Affairs had not met all of
the conditions in CalTech’s approval of SPR 2, CalTech nonetheless
approved SPR 3, which increased the estimated cost of the project
from roughly $78 million to more than $118 million, along with
14 conditions. Consumer Affairs was to address these conditions
in exchange for CalTech’s approval of SPR 3. Further, unlike the
previous estimates that reflected the entire cost of the project,
the $118 million cost estimate only reflected the costs of the project
through phase 2.
It was not until after Consumer Affairs estimated the cost of
completing the project at $300 million in June 2014 that CalTech
changed its oversight approach on the BreEZe project.13 According
to the BreEZe project director, Consumer Affairs withdrew
its submission of SPR 3 upon direction from CalTech and the
California Department of Finance in September 2014. According to
CalTech’s oversight division deputy director, CalTech’s vision going
forward is to complete the project only for the phase 2 regulatory
entities. In fact, she stated that CalTech finalized negotiations with
Accenture on December 1, 2014, and removed phase 3 from the
design contract, which we describe later.
Despite the Serious Oversight Concerns, CalTech Allowed Consumer
Affairs to Press Forward With BreEZe
Both Consumer Affairs and CalTech acknowledge that they were
aware of the oversight concerns raised about the BreEZe project.
As was mentioned previously, Consumer Affairs officials were
aware of the IV&V consultant’s and the IPO specialist’s concerns
regarding the BreEZe project, but they did not take appropriate
action to address all of the concerns. Similarly, CalTech did not
require Consumer Affairs to remedy the problems the IV&V
consultant and the IPO specialist raised, although according to the
state chief information officer (CalTech’s director), he has met with
IT project teams, such as the BreEZe project team, and Consumer
Affairs officials monthly since June 2012 to discuss the issues raised
in the IPO reports and project status reports.
13 The BreEZe project team developed the estimate informally and not in the same manner as an
SPR requires.
California State Auditor Report 2014-116 37
February 2015
Consumer Affairs’ BreEZe project director indicated that he
did not always act on the concerns raised in the IPO reports,
largely because he believed many of the comments were factually
inaccurate. According to the project director, Consumer Affairs
communicated this concern regarding inaccuracy to CalTech
management in 2013. However, when we asked CalTech’s branch
chief in the oversight division whether Consumer Affairs had
discussed the accuracy of the reports with anyone at CalTech, she
responded that Consumer Affairs had complained only about the
sternness of the language in the IPO reports. The BreEZe project
director stated that Consumer Affairs does act on concerns the
IPO specialist raises that it believes are valid. He also explained
that Consumer Affairs has not tracked the IV&V and IPO concerns
from the inception of the BreEZe project. Rather, Consumer Affairs
has chosen to respond to the concerns that CalTech has asked it
about. The BreEZe project director indicated that Consumer Affairs
has taken this approach because it lacks resources and he believes
that the concerns raised in the reports are not very meaningful. Our
IT expert believes that Consumer Affairs’ failure to act in the face of
the significant and persistent issues that the IV&V consultant and
IPO specialist raised constitutes poor management of the project.
For its part, CalTech did not use its authority to ensure that
Consumer Affairs addressed the significant and persistent
warnings of the IV&V consultant and the IPO specialist, which
would have better prepared Consumer Affairs to successfully
complete a complex project such as BreEZe. Although state law State law provides CalTech with the
provides CalTech with the authority to suspend, terminate, and authority to suspend, terminate,
reinstate technology projects, it did not take any of these actions and reinstate technology projects;
on the BreEZe project or warn Consumer Affairs in writing that however, it did not take any of these
it would take one or more of these actions if the project did not actions on the BreEZe project.
meet specific performance measures. However, according to the
CalTech director, in the February or March 2013 monthly portfolio
meeting, he verbally cautioned officials at Consumer Affairs that
CalTech had just suspended or terminated two other projects and
that BreEZe would be next if CalTech did not see the department
improve its rigor in project management, project governance, and
contract management. Nonetheless, CalTech still had concerns in
these three areas in July 2014, when it approved SPR 3.
According to CalTech’s director, it views its role on a project that
is in progress as providing oversight in a manner that supports
a successful completion of the project. Separately, according to
the branch chief in the oversight division, CalTech believes that
departments can seek its assistance, particularly the assigned IPO
specialist, with questions or issues that may arise on IT projects.
She explained that CalTech also monitors a project to ensure
that it is within budget and scope of resources and that a major
crash is not imminent; to the extent that these issues do not arise,
38 California State Auditor Report 2014-116
February 2015
CalTech will work with the department in a supportive role. Yet, we
question why CalTech did not intervene instead of approving SPR 3,
given that Consumer Affairs was not appropriately addressing the
concerns the IV&V consultant and the IPO specialist raised; these
concerns were numerous and were identified in CalTech’s analysis of
SPR 2 in 2013. Although CalTech was aware that Consumer Affairs
was not heeding the concerns the independent oversight staff raised,
it allowed Consumer Affairs to continue with the project.
Despite its awareness that Consumer Affairs has experienced
noteworthy difficulties in developing the BreEZe system, CalTech
demonstrated through its approval of SPR 3 in July 2014 that the
BreEZe project should continue. However, we question this position
and CalTech’s decision to allow the BreEZe project to receive
additional funding in light of the many concerns its oversight staff
have raised. Further, CalTech does not have guidance that would
help it evaluate whether projects should continue. Although there
is no written guidance, the oversight division’s deputy director
explained that she developed a framework since arriving at CalTech
in April 2014 for the oversight division to use in evaluating the
health of projects. Depending on the magnitude and types of
problems a project may have, such as experiencing significant delays
in the project schedule or project cost increases, the oversight
division escalates concerns through the monthly IPO reports,
project steering committee reports, CalTech portfolio meetings,
meetings with relevant agency leadership, and with the Governor’s
Office. She further stated that when the factors are not being
resolved within a reasonable time frame, the oversight division will
recommend to the director of CalTech that the project be placed
in a pause, suspension, or termination status. Nevertheless, when
we asked for the BreEZe project recommendations the oversight
division has made to the CalTech director, the oversight division’s
deputy director stated that she has not seen any documentation
about a recommendation concerning pausing the project or other
action for BreEZe.
When we asked CalTech’s director in October 2014 his thoughts on
halting the BreEZe project, he cited several reasons for letting the
project continue uninterrupted: BreEZe is moving in the right
direction, the system’s problems are not incurable, and Consumer
Affairs and Accenture have been able to work through issues
toward resolution. In addition, he stated that the BreEZe project is
working and functional. However, according to the September 2014
IPO report, while BreEZe was in production for the 10 phase 1
regulatory entities, it identified that the project’s overall health was
poor. The IPO report also states that the online application feature,
which the IPO specialist considers a key part of BreEZe, had not
been “turned on” for some phase 1 regulatory entities. The IPO
California State Auditor Report 2014-116 39
February 2015
specialist concluded that it was inefficient of these entities to not be
using the online functionality one year after
phase 1 implementation.
CalTech’s reasons for approving SPR 2, which are
shown in the text box, provide other reasons that
California Department of Technology’s
it has allowed the BreEZe project to continue. Reasons for Approving the BreEZe System
However, CalTech’s explanation for approving Special Project Report 2
SPR 2 and allowing the BreEZe project to continue
is perplexing given the actions CalTech and • The BreEZe business case remained valid, and BreEZe could
be a benefit to the State.
Consumer Affairs have recently taken to remove
phase 3 of BreEZe from the design contract with • The project had already completed one of the
Accenture. In fact, Consumer Affairs’ SPR 3.1, three phases, and the system continued to stabilize.
which it submitted to CalTech in January 2015,
• The California Department of Technology (CalTech)
indicated the project is not moving in the right
expected that future phases would take advantage of the
direction and proposed a rescoping of the project
benefits of lessons learned and avoid some of the issues
to remove phase 3 because of significant concerns associated with phase 1.
related to staffing and increasing project costs, and
• The project and Special Project Report (SPR) 2 underwent
because its contracts with Accenture are no longer
extensive scrutiny by all control agencies, and all open
financially feasible for Consumer Affairs.
issues were receiving attention.
As discussed previously, CalTech has the authority • Approving SPR 2 would give the California Department of
Consumer Affairs (Consumer Affairs) the funding it needed
and responsibility to oversee and approve IT
to continue implementing BreEZe for the remaining
projects. If CalTech had chosen to suspend
regulatory entities, as well as pay for approved changes
the project, it could have temporarily paused
through the unanticipated tasks budget.
BreEZe development and could have provided
Consumer Affairs with additional time to conduct Source: CalTech’s analysis of Consumer Affairs’ SPR 2.
a cost‑benefit analysis and to correct fundamental
problems, such as the baseline of requirements and
other requirement issues, it encountered during
planning and development. However, according to the CalTech
director in October 2014, who has overseen the BreEZe project
since Consumer Affairs executed its contracts with Accenture,
CalTech has not suspended BreEZe for several reasons, including
the following: Consumer Affairs badly needs a new system,
suspending the project could cause project delays that might
result in Consumer Affairs needing to pay Accenture for those
delays, and stopping the project now may affect fixes that were due
after phase 1. In addition, CalTech’s director told us that should
CalTech terminate BreEZe, it would be abandoning Consumer
Affairs. Specifically, the director indicated that although CalTech
has the authority to terminate the BreEZe project, it cannot
terminate the contracts Consumer Affairs has with Accenture
and that terminating the project would leave Consumer Affairs
without the means to meet its contractual obligations. We do not
agree with the CalTech director’s assessment that terminating
the project will leave Consumer Affairs stranded with a contract.
CalTech has the authority to terminate the project, and Consumer
Affairs could subsequently terminate the contract with Accenture
40 California State Auditor Report 2014-116
February 2015
for convenience—meaning that the State may terminate the contract
at its own discretion even if the contractor has performed. In other
words, Consumer Affairs could unilaterally terminate the contract,
even if Accenture did not breach it, but it would be obligated to
pay Accenture for certain costs, such as the costs of completed and
partially completed work and winding down operations.
In 2011, before Consumer Affairs Despite CalTech’s reasons for not intervening in the beginning
awarded the BreEZe contracts, stages of the BreEZe project, had it done so the project might
the IV&V consultant reported have become more stable and might have better met the needs
significant concerns with the system of the regulatory entities included in phase 1 of the system’s
requirements, concluding they were implementation. For instance, in the spring of 2011, before
inadequate and posed a high risk. Consumer Affairs awarded the BreEZe contracts, the IV&V
consultant reported significant concerns with the requirements
Consumer Affairs had defined for the system, essentially concluding
that they were inadequate and posed a high risk. If CalTech had
chosen to suspend the project at that time and required Consumer
Affairs to address the issues with the system requirements, it is
likely the project would not have faced the subsequent delays that
it has experienced in its schedule.
CalTech Did Not Ensure Oversight for BreEZe Until More Than One
Year After the Project’s Commencement
Consumer Affairs did not secure IV&V services for BreEZe and
CalTech did not assign an IPO specialist to the project for over a
year after CalTech approved the project’s FSR. State IT policies
require that IPO begin immediately following project approval
and continue through project closeout. State IT policies hold state
entities responsible for establishing required oversight activities,
which include both IPO and IV&V services, and since CalTech
approved the project’s FSR in November 2009, it was aware of
the need for this oversight and should have assigned an IPO
specialist at that time, according to CalTech’s oversight division
deputy director, given that its practice at the time was to initiate an
agreement to do so.
For IV&V services, CalTech defers to the corresponding standard
of the Institute of Electrical and Electronics Engineers, Inc. (IEEE),
which states that IV&V shall be performed in parallel with all
system life cycle stages, starting at the very beginning of the process
when the system requirements are being defined and continuing
throughout the project.14 However, the IPO specialist and the
IV&V consultant did not begin work until December 2010 and
14 The IEEE is a leading developer of international standards that support many products and
services, including IT.
California State Auditor Report 2014-116 41
February 2015
January 2011, respectively, more than a year after the FSR was
approved. By that time, Consumer Affairs was about to issue the
eighth of what would ultimately be 10 amendments to the RFP.
CalTech noted that in state IT policy, the purpose of IPO is to
identify and quantify any issues and risks affecting schedule, cost,
and system functionality. Similarly, the IEEE standard for IV&V
indicates that without early feedback from independent oversight,
detection of anomalies and the resulting system changes required to
correct them are typically delayed until later in the project, resulting
in greater costs and schedule delays. Not surprisingly, cost increases Cost increases and schedule delays
and schedule delays are some of the problems that have plagued the are some of the problems that have
BreEZe project. plagued the BreEZe project.
The CalTech oversight division deputy director stated that
CalTech’s practice has been to add oversight staff by a project’s
start as identified in its FSR, which for the BreEZe project was
December 2009. Moreover, she noted that before July 2014,
CalTech assigned an IPO specialist to a project after initiating
an interagency agreement with a department, whereas effective
July 2014 departments submit service requests for IPO services.
In addition, according to available documentation, Consumer
Affairs canceled an existing agreement with a private sector IPO
in June 2009 because CalTech informed Consumer Affairs that
it would assume responsibility for providing IPO services in the
following month, which did not occur. Thus, apparently CalTech
was aware of the need for IPO services to begin early in the project,
but it did not secure them until more than a year later. In July 2014
CalTech streamlined the IPO request procedure by changing it
from a process requiring an interagency agreement to one that can
be initiated simply by a service request, which the deputy director
believes will help ensure that IPO oversight starts earlier than it
did under the old system. The CalTech oversight division deputy
director told us she is unaware of the circumstances concerning
IV&V oversight on the BreEZe project before January 2011.
Separately, the BreEZe project director stated that the start of IV&V
services was delayed for two reasons. First, he prepared the RFP
for IV&V services at the same time that he was preparing the RFP
for the overall project, and the project RFP was a higher priority.
The BreEZe project director’s need to prioritize among these
RFPs is another result of Consumer Affairs’ insufficient project
resources, as discussed earlier in this chapter. Second, Consumer
Affairs found the initial bids for its IV&V RFP to be higher than it
expected, which led it to rescope the IV&V RFP and delay obtaining
these services. While the BreEZe project director told us he found
many of the IPO specialist’s concerns to be of limited merit, had
both forms of oversight been provided from the start of the project
and had Consumer Affairs promptly addressed the concerns the
42 California State Auditor Report 2014-116
February 2015
oversight staff raised regarding the system requirements, the project
would likely not have faced cost increases and schedule delays of
the magnitude that it has.
Consumer Affairs Did Not Comply With the State’s Policies for IT
Project Management
CalTech’s California Project Management Methodology defines
a series of IT project management plans that are meant to serve
as a formal framework for managing a project, including its cost,
scope, and staffing. These plans should be developed during the
planning stage of a project. Table 7 shows the 12 necessary plans
and indicates whether Consumer Affairs completed and followed
each plan. As shown in the table, for the nine plans Consumer
Affairs developed, four were not created until after it had awarded
the contracts to Accenture, and in seven cases, they were not
created until 21 months to 54 months after it received project
approval. In September 2011 the IV&V consultant reported a
concern that the BreEZe project still lacked a significant number of
project plans that were key references for performing his oversight
activities. Consequently, execution of the BreEZe project was under
way before Consumer Affairs had fully determined some of the
processes it would use to manage the project.
The completion of the project management plans is a key activity
of the planning stage, and if properly completed, these plans would
have defined the work that Consumer Affairs would complete in
the contract execution stage of the project. As a result, delays by
Consumer Affairs in completing the project management plans may
have led to omissions on its part. According to CalTech officials,
state entities are not required to submit these plans to CalTech;
however, in its IPO role, CalTech does review, evaluate, and provide
feedback on any such plans. Available documentation suggests that
CalTech undertook these activities to some extent on the BreEZe
project. In addition, according to CalTech officials, it monitors
and provides feedback on a project’s ability to execute these
Consumer Affairs failed to develop plans. Not surprisingly, in the areas in which Consumer Affairs
IT project management plans for failed to develop the plans entirely—costs, scope management,
costs, scope management, and and human resources—CalTech’s IPO specialist and the IV&V
human resources, raising significant consultant identified significant concerns. In other cases, such as
concerns by CalTech’s IPO specialist organizational change management, Consumer Affairs developed
and the IV&V consultant. the plans but failed to implement them. Consequently, several of the
phase 1 regulatory entities reported that they were ill‑prepared to
adjust to the effects of the new system on their business processes.
California State Auditor Report 2014-116 43
February 2015
Table 7
California Department of Consumer Affairs’ Adherence to Necessary Project Plans
MONTHS AFTER IF COMPLETED,
FEASIBILITY DID CONSUMER
WAS THE STUDY REPORT MONTHS AFTER AFFAIRS
PLAN DATE PLAN WAS APPROVED CONTRACT AWARD FOLLOW THE
PURPOSE OF PLAN COMPLETED? FIRST EFFECTIVE (NOVEMBER 2009) (SEPTEMBER 2011) PLAN?
Project Management Plan
Scope management plan Documents how the project scope will No – – – –
be defined, verified, and controlled, and
how the work breakdown structure will
be created and defined.
Configuration change Describes how to document, control, Yes August 2011 21 0 No
control plan and manage any changes to key
project components and deliverables
throughout the project life cycle.
Human resource Identifies how and when labor needs No – – – –
management plan will be met to ensure that the project
has sufficient staff with appropriate skill
sets and experience.
Communication Determines the information and Yes September 2011 22 0 Partially
management plan communications needs of project
stakeholders and how to meet them.
Risk management plan Indicates how to approach, plan, and Yes October 2011 23 1 Partially
execute risk management activities for
the project.
Cost management plan Used to plan, estimate, budget, and No – – – –
control costs so that the project can be
completed within the approved budget.
Quality management plan Identifies which quality standards are Yes June 2010 7 0 No
relevant to the project and describes
how to satisfy them.
Schedule management plan Establishes how the project schedule Yes August 2011 21 0 Yes
will be managed and controlled by
estimating the duration of activities.
Procurement management plan Determines which project needs can Yes May 2010 6 0 Partially
best be met by purchasing or acquiring
products, services, or results outside the
project organization, and which project
needs can be accomplished by the
project team during project execution.
Contract management plan Documents the products, services, and Yes May 2014 54 32 Partially
results requirements needed to meet the
project’s objectives.
Other Necessary Plans
Organizational change Assesses stakeholders’ awareness and Yes October 2011 23 1 No
management plan influence, describes any resistance
or concerns, and identifies optimum
communication and actions to be taken.
Maintenance and operations Describes how the project will be Yes December 2012 37 15 Partially
transition plan transitioned from the team executing
development to the operations team.
Sources: California Department of Technology’s Statewide Information Management Manual, interviews with California Department of Consumer Affairs
(Consumer Affairs) officials, and California State Auditor’s review of Consumer Affairs’ BreEZe project management plans and associated oversight reports.
44 California State Auditor Report 2014-116
February 2015
The BreEZe project director cited various reasons for the
deficiencies we identified in the execution of the project plans.
He said that in a number of cases, inadequate staffing was the
reason the project team did not complete project management
activities. For some of these management activities, the project
director claimed that other activities or reports provide functional
equivalencies. For example, Consumer Affairs’ configuration change
control plan specifies that it is to complete seven reports regarding
requests for changes to the system; however, rather than submitting
these reports, the contract manager substituted one log tracking the
requested changes. Although this log does contain most of the same
information that would have been included in the seven separate
reports, it is missing the information required for one of them.
In another example of functional equivalency, the project
director substituted informal daily interactions with Accenture
for the periodic performance management reviews the contract
management plan specifies. However, that plan notes that a number
of other parties are expected to attend these meetings, including
the entire project management team and other appropriate team
members. These meetings would likely have offered the team an
opportunity to address issues and concerns that were larger than
those that arise day to day.
Another project management problem occurred when the project
director officially acted as the project manager for the greater
part of 2014 and thus was responsible for an even greater range
of significant duties. Consumer Affairs combined the positions of
project director and project manager in January 2014, following the
implementation of phase 1 of BreEZe, because the former project
director retired. This bundling of positions by Consumer Affairs
during 2014 removed an important layer of management oversight,
thereby reducing the effectiveness of project management. In fact,
the IPO specialist identified this as a concern in January 2014,
noting that the positions of project director and project manager
In 2014 the BreEZe project are distinct roles that focus on different areas, with the project
director officially acted as the director overseeing and providing a second opinion on matters
project manager, resulting in for the project manager. Consumer Affairs then separated the
the removal of an important layer positions again in June 2014 following CalTech’s direction that the
of management oversight, thereby combination of the positions was not supportable over the long
reducing the effectiveness of term, and as of mid‑September 2014, Consumer Affairs had hired a
project management. project manager.
Finally, the State Administrative Manual requires all departments to
use the California Project Management Methodology for their large
IT projects, and it also requires that all project managers and team
leads receive training in this methodology. However, according to
Consumer Affairs’ chief information officer, the project director
is the only one of the three Consumer Affairs’ BreEZe project
team leads who has met this requirement. When staff serving in
California State Auditor Report 2014-116 45
February 2015
leadership roles do not fulfill the minimum project management
training requirements, assurance is lacking that they have the
knowledge necessary to successfully manage a large IT project.
Further, this lack of training may have contributed to some of the
problems the BreEZe project has encountered.
Implementation of BreEZe at All Originally Scheduled Regulatory
Entities Is No Longer Planned
The future implementation of BreEZe by the phase 2 regulatory
entities is at risk, and it is unknown whether or when the 19 phase 3
regulatory entities will implement the system. As we explained in
the Introduction, 10 regulatory entities implemented the system
in October 2013 as part of phase 1, and another eight regulatory
entities are included in phase 2, which is currently planned for
March 2016. The remaining 19 regulatory entities—among them
some of the largest in terms of licenses issued as we illustrated in
Table 3 on page 15—were originally included in phase 3; however,
it is now unknown whether or when these entities will begin
using BreEZe. Specifically, CalTech informed us that it completed
renegotiating Consumer Affairs’ design contract with Accenture
on December 1, 2014, and these 19 regulatory entities had been
removed entirely from the design contract.
Under certain conditions, CalTech has the authority to negotiate
IT contracts, including amendments, under Public Contract Code,
Section 6611. This section of law pertains to contracts, such as
the BreEZe contracts, that are conducted through a negotiation
process. Although it has had this authority since July 2013, CalTech
has not previously exercised it on the BreEZe project; however,
according to the BreEZe project director, it did previously coach
Consumer Affairs for earlier negotiations. According to CalTech’s
director, CalTech increased its involvement in 2014 because of
the BreEZe project’s increasing costs, large scope, and high risk.
He also acknowledged various concerns with the design contract,
described further in Chapter 2, and stated that the BreEZe project
has been a learning experience with respect to contracts, vendors,
and expectations. In terms of a new contract amendment that will
remove phase 3, a CalTech deputy director explained that SPR 3.1
and a notification to the Legislature are required before one can
be executed, and she does not expect to finalize these actions until Only after the successful
the first quarter of 2015. In fact, SPR 3.1 indicates that the project implementation of phase 2 will
will end after the phase 2 regulatory entities implement BreEZe, Consumer Affairs reassess the
and only after the successful implementation of that phase will best implementation approach
Consumer Affairs reassess the best implementation approach for for the remaining 19 phase 3
the 19 phase 3 regulatory entities. regulatory entities
46 California State Auditor Report 2014-116
February 2015
Consumer Affairs is requesting over Consumer Affairs has explained that it needs additional staffing
$18 million in additional funding to successfully implement BreEZe at the phase 2 regulatory
for 34 new dedicated staff and entities and to maintain BreEZe into the future; however, as of
indicated that if it does not receive January 2015, it lacks the funding to fill these positions. In SPR 3.1,
this funding, it will not be able to in which it is requesting additional funding of over $18 million,
complete the BreEZe project. Consumer Affairs is requesting 34 new dedicated staff resources.
According to SPR 3.1, Consumer Affairs needs the additional
dedicated staff in order to mitigate project risk and successfully
complete the remaining phase 2 activities with high quality. In
addition, Consumer Affairs states that these positions are needed
as soon as possible. According to the SPR, these positions will
fill critical project roles in areas such as data conversion support,
organizational change management, and maintaining existing IT
systems for the remaining regulatory entities not using BreEZe after
phase 2 is completed. Further, Consumer Affairs indicated that if it
does not receive the additional funding for the positions, it will not
be able to complete the BreEZe project.
Consumer Affairs lacks a plan to implement BreEZe at the 19
phase 3 regulatory entities that were removed from its design
contract with Accenture during recent negotiations. According to
SPR 3.1, Consumer Affairs will reassess the best implementation
approach for the phase 3 regulatory entities after the successful
completion of phase 2; thus, Consumer Affairs does not yet have
a plan to implement BreEZe for these 19 regulatory entities. In a
December 2014 memorandum to the regulatory entities regarding
the future of BreEZe, the director explained that Consumer Affairs
anticipates a staggered transition to the BreEZe system for the
phase 3 regulatory entities, as opposed to having all 19 make the
transition at once. Further, the director stated that the current
design contract was not sustainable in terms of both financial and
human resources and that the decision to end the contract at the
conclusion of phase 2 was the fiscally responsible thing to do, as it
will allow Consumer Affairs to better manage and contain costs.15
This perspective is echoed in SPR 3.1, in which Consumer Affairs
states that following the implementation for phase 2 of continuous
improvements identified during phase 1, it became apparent that
the current contract structure presented resource and economic
challenges that gave Consumer Affairs and its regulatory entities
grave concerns about being able to accurately predict and control
project costs and schedule beyond phase 2.
Moreover, in its analysis of SPR 3, CalTech highlights the
complexity of phase 3 as a risk. Specifically, the analysis states that
phase 3 contains some of the most complex and largest regulatory
15 Consumer Affairs only renegotiated the design contract. The other two contracts that Consumer
Affairs has with Accenture, the maintenance and system license contracts, remain in place.
California State Auditor Report 2014-116 47
February 2015
entities, those with the highest number of license types—160 in
total, more than the license types of the phase 1 and phase 2
regulatory entities combined. SPR 3 concludes that this makes
phase 3 larger than all of the BreEZe work that will have been
accomplished through the completion of phase 2. Despite this
complexity, the director of Consumer Affairs acknowledged that
Consumer Affairs has not determined the extent to which the
business needs of the 19 regulatory entities will require changes
to the BreEZe system. Because the magnitude of the changes that
these regulatory entities may require is unknown and given the
project’s history of significant cost increases and schedule delays,
it is likely that Consumer Affairs will encounter similar issues
if and when it attempts to implement BreEZe at these phase 3
regulatory entities.
Consumer Affairs has also not conducted a formalized cost‑benefit
analysis, which would include assessing the magnitude of the
changes required by those 19 regulatory entities, to inform its
decision about implementing BreEZe at them. A cost‑benefit
analysis compares the benefits of a project’s outcomes with the cost
required to produce them as well as the costs and benefits of an
alternative project. This analysis is of particular importance given
that the Budget Act of 2014 mandates an ongoing department‑wide
budget reduction of $500,000 for Consumer Affairs beginning
in fiscal year 2017–18 in recognition of anticipated operational
efficiencies resulting from the implementation of BreEZe by the
regulatory entities. Consumer Affairs acknowledges in SPR 3.1
that based on the experience of the phase 1 regulatory entities,
there will be no staffing or other operational efficiencies resulting
from BreEZe that will produce cost savings. Thus, according to
the director of Consumer Affairs, although it will be continuing its
design contract with Accenture to complete phase 2, those phase 3
regulatory entities may not realize any operational efficiencies if
and when they implement the system. The likelihood of such an
outcome occurring underscores the importance of Consumer
Affairs conducting an analysis of both the costs and benefits of
moving forward with phase 3.
CalTech Is Developing a New Approach for Its Oversight Role in the
Planning of IT Projects
CalTech has initiated a project that, if fully implemented, will
expand its role in the planning phase of IT projects and potentially
contribute to an increase in the successful execution of reportable
IT projects.16 The State Technology Approval Reform (STAR)
16 As of July 1, 2013, CalTech is responsible for all contracts for the acquisition of reportable IT
projects with costs that exceed an agency’s delegated cost threshold.
48 California State Auditor Report 2014-116
February 2015
project aims to transform CalTech’s current IT project approval
process and assist departments in identifying weaknesses in areas
critical to IT project success. However, because CalTech has yet to
fully implement the STAR project, it is too early to tell whether it
will improve the success rate of IT projects.
In September 2013 CalTech initiated In September 2013 CalTech initiated the STAR project, with a
the STAR project, with a mission mission of improving the planning, quality, value, and likelihood of
of improving the planning, IT project success. According to CalTech’s oversight division deputy
quality, value, and likelihood of director, the STAR project will revamp the current FSR process,
IT project success. which generally requires a department to document the need for a
proposed IT project, along with the cost and benefits of the project,
following instructions included in the Statewide Information
Management Manual. The deputy director also indicated that the
new process will bring greater coordination between CalTech and
departments during the planning phase of reportable IT projects.
She stated that in coordination with a department, CalTech will
evaluate the department’s readiness for its IT project using analyses
of multiple stages: a business analysis, an alternatives analysis,
a procurement analysis, and a solution analysis. According to a
June 2014 presentation, CalTech decided to undergo this change
for a variety of reasons, including the fact that the State’s approval
of IT projects has been identified by the Governor’s Office, the
Legislature, and the State’s policy and IT communities as an area
that needs to be revised and updated. CalTech believes this new
process will reduce project risk, build collaborative partnerships,
increase efficiency, better define project data needs, and improve
project approval integrity. CalTech also believes it will provide the
opportunity to redirect efforts or even stop projects earlier, when
needed, before significant budget actions have been taken.
According to the deputy director, as of January 2015 CalTech was in
the process of piloting the first two stages of the STAR project and
plans to continue doing so through June 2015; however, CalTech
had not yet finalized the list of IT projects that will be included
in the pilot. She explained that CalTech would prefer to work
with departments on a voluntary basis until at least January 2016,
before mandating that departments use the new process for
their IT projects. Again according to the Caltech’s oversight
division deputy director, the STAR project is currently developing
procedures for examining an IT project’s risk, its business value,
and the department’s organizational readiness to implement the
project. As guidance for developing these procedures, CalTech
is using, among other information, lessons learned from past IT
projects, including lessons learned from BreEZe. As an example,
CalTech’s oversight division deputy director noted that on the
BreEZe project, a decision was made to use standard commercial
software requiring little customization, with insufficient
consideration paid to the business needs of the regulatory entities,
California State Auditor Report 2014-116 49
February 2015
the dependencies of their processes, and impediments to successful
implementation. She explained that the initial planning for the
BreEZe project depended on all of Consumer Affairs’ regulatory
entities being able to use the same system, which was unreasonable
given their different needs.
As part of the STAR project, the oversight division deputy
director indicated that CalTech also plans to address a lack of
critical IT project management leadership experience in state
departments. To remedy this issue, CalTech is developing as part
of the STAR project a voluntary organizational self‑assessment
that will help a department understand its internal strengths and
weaknesses in areas critical to IT project success. CalTech hopes
these self‑assessments will lead to more informed planning for IT
projects, perhaps including the use of CalTech consulting services.
Recommendations
Legislature
To ensure that it receives timely and meaningful information
regarding the status of the BreEZe project, the Legislature should
enact legislation that requires Consumer Affairs to submit a
statutory report annually, beginning on October 1, 2015, that will
include the following:
• Consumer Affairs’ plan for implementing BreEZe at those
regulatory entities included in the project’s third phase, including
a timeline for the implementation.
• The total estimated costs through implementation of the system
at the remaining 19 regulatory entities and the results of any
cost‑benefit analysis it conducted for phase 3.
• A description of whether and to what extent the system
will achieve any operational efficiencies resulting from
implementation by the regulatory entities.
CalTech
To help ensure the success of the BreEZe project going forward,
CalTech should do the following:
• Ensure that Consumer Affairs responds promptly to, and
adequately addresses, concerns raised by its IPO specialist and its
IV&V consultant.
50 California State Auditor Report 2014-116
February 2015
• Require Consumer Affairs to develop and follow all project
management plans and ensure that the BreEZe project team
leads receive all required training.
• Document key discussions with Consumer Affairs in which
significant concerns are raised about Accenture and assessments
of the department’s performance by the IV&V consultant and the
IPO specialist.
If Consumer Affairs receives the necessary funding and resources
to successfully implement BreEZe at the phase 2 regulatory entities
and the project continues to face escalating costs, CalTech should
require Consumer Affairs to conduct an analysis of the costs and
benefits of moving forward with the project as planned or of
suspending or terminating the project.
Continue implementing the STAR project for state departments and
ensure that its framework maintains the following requirements:
• Undertakes detailed business process analyses before submitting
FSRs to CalTech for approval.
• Uses those business process analyses to justify the type of
IT solution they are proposing, such as a COTS or a fully
customized system.
• Uses those business process analyses to inform the
resulting RFPs and that they ensure that the RFPs contain
adequate requirements.
To ensure that IT projects have the oversight needed to better
position them for success, CalTech should do the following:
• Require state departments to follow its IT policies, including
developing all necessary plans and receiving all required training.
• Ensure that departments obtain IPO and IV&V services as
soon as an IT project is approved. Additionally, CalTech
should document key discussions with any department in
which the IV&V consultant and the IPO specialist raise
significant concerns about a project, and ensure that the
respective department responds promptly to, and adequately
addresses, the concerns that the IPO specialist and the IV&V
consultant raise.
• Require state departments to appropriately address deficiencies
identified in CalTech’s approval of any SPRs as conditions that
must be met, and to do so according to specified timelines.
If the deficiencies are not adequately addressed within the
California State Auditor Report 2014-116 51
February 2015
specified timelines, CalTech should take action to suspend the
project until the department has either resolved the identified
deficiencies or adequately documented its justification for not
addressing the deficiencies.
• Develop thresholds relating to IT project cost increases and
schedule delays to inform and better justify its decision to allow
an IT project to continue. If a department’s IT project reaches or
exceeds these thresholds, CalTech should require the department
to conduct a cost‑benefit analysis for the project and include
this analysis in an SPR. CalTech should consider the results
of this analysis in its decision to approve or deny the SPR and,
if warranted, take action to suspend or terminate the project
so that it does not allow projects with significant problems to
continue without correction.
Consumer Affairs
To make certain that Consumer Affairs has a project team that
consists of staff trained in managing IT projects, it should ensure
that all the BreEZe project team leads obtain all required project
management training.
Consumer Affairs should develop a process to ensure that it
prepares all required project management documents and
undertakes all oversight activities related to BreEZe as CalTech
requires so that it can prevent or identify and monitor future
problems as they arise. This includes taking steps to sufficiently
respond to any concerns that the IPO specialist and the IV&V
consultant raise.
To the extent that Consumer Affairs chooses to implement BreEZe
at the phase 3 regulatory entities, it should first complete a formal
cost‑benefit analysis to ensure that BreEZe is a cost‑effective
solution to meet these regulatory entities’ business needs. To make
certain this analysis is complete, it should include an assessment
of the potential changes these regulatory entities may require to be
made of the BreEZe system and the associated costs. Consumer
Affairs should complete the cost‑benefit analysis before investing
any more resources into the implementation of BreEZe at the
phase 3 regulatory entities, and it should update this analysis
periodically as significant assumptions change.
52 California State Auditor Report 2014-116
February 2015
If Consumer Affairs determines that a new IT project is warranted
in the future, it should develop a process to ensure the success of
that project that includes, at a minimum, the following:
• System requirements that are specific to each regulatory entity
as applicable.
• A project team that is qualified and experienced.
• Development of and adherence to all project management plans.
• Planning and implementation of effective organizational
change management.
• Timely response to concerns that the IV&V consultant and the
IPO specialist raise.
• Sufficient staffing.
California State Auditor Report 2014-116 53
February 2015
Chapter 2
THE STATE ENTITIES RESPONSIBLE DID NOT ENSURE
THAT THE BREEZE CONTRACT TERMS SUFFICIENTLY
PROTECT THE STATE
Chapter Summary
In September 2011, under the direction of the California
Department of General Services (General Services), the
California Department of Consumer Affairs (Consumer Affairs)
awarded three BreEZe contracts to Accenture LLP (Accenture).
These contracts do not adequately protect the State. 17 General
Services’ role at that time was to administer state information
technology (IT) procurements and conserve the fiscal interests
of the State. However, during the procurement process for the
BreEZe project, General Services and Consumer Affairs approved
revisions to the contracts’ terms and conditions proposed by
Accenture that transferred risk to the State. In addition, the
revised language limited Consumer Affairs’ ability to terminate the
contracts and eliminated protections Consumer Affairs otherwise
would have had against the possibility of intellectual property
rights violations. General Services’ staff explained that the contract
revisions reflect what Consumer Affairs was willing to accept.
Consumer Affairs staff stated that they were concerned that if
they did not agree to the changes Accenture proposed, Consumer
Affairs would lose the opportunity to contract with Accenture.
Nevertheless, General Services and Consumer Affairs approved
contract terms and conditions that do not adequately protect the
State’s interests.
Although All Vendors Had the Opportunity to Protest the
State’s Standard IT Contract Language, Only Accenture Did So
General Services and Consumer Affairs agreed to changes to
the State’s standard IT general provisions and model contract
language (standard IT contract) during two phases of the BreEZe
procurement process. These changes are not beneficial to the
State.18 During the request for proposal (RFP) phase, General
Services provided every potential bidder with the opportunity to
17 There are three contracts related to the BreEZe project—one contract for design, development,
and implementation; another contract for maintenance support; and a third contract for
the system license. When we discuss a specific contract, we identify it as either the design,
maintenance, or system license contract.
18 At the time of the BreEZe procurement, General Services had several modules of standard
contract language related to IT contracts.
54 California State Auditor Report 2014-116
February 2015
submit a protest for issues such as the selection of prequalified
bidders or RFP requirements before submitting a bid and to
have General Services review its concerns. During this phase in
the BreEZe procurement process, specifically in January 2011,
only Accenture submitted a protest, in which it proposed
44 modifications to provisions of the State’s standard IT contract.
Of these proposed modifications, General Services accepted 18,
proposed its own revisions to 19, and rejected the remaining seven.
Subsequently, in April 2011, in accordance with state law, Consumer
Affairs entered into negotiations with Accenture—deemed to be the
only responsive bidder. According to its former director, Consumer
Affairs believed these negotiations were a prudent and necessary
next step to fully explore all possible options before it would
consider canceling the BreEZe procurement.
The contracts that Consumer Affairs executed in September 2011
and that General Services approved with Accenture for developing
BreEZe contained certain terms and conditions that are not
included in the State’s standard IT contract language. Specifically,
General Services and Consumer Affairs accepted terms and
conditions that decrease Consumer Affairs’ ability to obtain a
system that meets the needs of its boards, bureaus, committees,
and a commission (regulatory entities) and that reduce Consumer
Affairs’ financial protections in the event Accenture performs
poorly. According to Consumer Affairs’ officials, some of the
contract changes they accepted resulted in cost savings. General
Services’ chief procurement officer provided the department’s
perspective for why it agreed to the contract changes Accenture
proposed. First, Consumer Affairs had unsuccessfully attempted
to procure a licensing system at least twice before the BreEZe
General Services and Consumer procurement. Second, Consumer Affairs described its legacy
Affairs accepted contract terms systems as broken because they had significant limitations.
and conditions that decrease Consequently, General Services was willing to accept the risk of
Consumer Affairs’ ability to obtain the contract revisions so that Consumer Affairs could replace its
a system that meets the needs of its legacy systems. However, we still question the prudence of some
regulatory entities and that reduce of the decisions it and Consumer Affairs made regarding the terms
its financial protections in the event and conditions, as they increased Consumer Affairs’ financial risk
Accenture performs poorly. related to these contracts.
General Services Significantly Weakened the State’s Financial
Protections Should Consumer Affairs Relieve Accenture of Its
Contractual Duties
As a result of the changes to the State’s standard IT contract that
General Services accepted for the BreEZe contracts during the RFP
phase, state money is not protected if Consumer Affairs decides to
terminate the BreEZe contracts for convenience—meaning that the
State may terminate the contract at its own discretion, even if the
California State Auditor Report 2014-116 55
February 2015
contractor has performed. General Services’ standard IT contract General Services accepted contract
language establishes that the State will have rights to the work language from Accenture that
product that is delivered or required to be delivered to the State. limits Consumer Affairs’ ability to
However, General Services accepted language from Accenture obtain rights to the work product
that limits Consumer Affairs’ ability to obtain rights to the work Accenture builds unless the State
product Accenture builds unless the State pays the full amount pays the full amount due under the
due under the design contract. Specifically, Consumer Affairs design contract.
could have to pay the remaining contract amount rather than only
certain of Accenture’s costs through the termination date to obtain
rights to Accenture’s work product, such as the source code that
Accenture wrote for BreEZe, so that it could be used in the future.
This source code is critical because it is part of the programming
instructions that operate BreEZe. For example, if Consumer Affairs
had terminated the design contract for convenience at the end
of September 2014, it could have been required to compensate
Accenture for the remaining design contract amount of up to
roughly $30 million of the total contract amount of $34 million to
obtain Accenture’s work product, unless Accenture was willing to
offer it for less. General Services’ chief procurement officer stated
that his reading of the amended contract language concerning
Consumer Affairs’ rights if it terminates the contract indicates that
it provides the State greater flexibility than the standard contract
terms because it narrows the scope of the payment Consumer
Affairs would need to make in the event of a contract termination.
However, unless the project were substantially complete, the
amount due under this provision could significantly exceed what
would be due under the standard IT contract.
Consumer Affairs also risks losing the maintenance contract
and system license contract if it terminates the design contract
in whole. As a result of their negotiations with Accenture,
General Services and Consumer Affairs agreed to include a clause
in the two contracts that makes those contracts contingent upon
the design contract being in effect. Thus, any complete termination
of the design contract terminates the remaining contracts, unless
Accenture and Consumer Affairs agree otherwise. By including this
clause in the maintenance contract and system license contract,
General Services and Consumer Affairs have further impaired the
State’s ability to terminate the main design contract.
General Services Accepted Terms and Conditions That Place the State at
Greater Risk of Business Losses and Legal Liability
In addition to the problematic contract provisions just discussed,
General Services also accepted contract language that affected the
State’s indemnification, or protection, from possible future damage,
loss, or injury. General Services’ standard IT contract language
includes a section regarding intellectual property that requires
56 California State Auditor Report 2014-116
February 2015
contractors to indemnify the State against third‑party claims for
violations of intellectual property rights. This language was in the
original RFP for the BreEZe procurement; however, during the
RFP phase, General Services accepted Accenture’s proposal to
delete a provision that required the contractor to certify that state
funds would not be used to violate copyright laws. Further, General
Services accepted additional contract language Accenture proposed
that restricts the State to certain remedies for a contractor’s possible
violations of patents, copyrights, and trade secrets, which effectively
prohibits the State from invoking other potential remedies
elsewhere in the contract or in law. In our opinion, these changes
increase the risk of Accenture violating intellectual property rights
by reducing its potential liability, which is a key incentive to avoid
such violations. Thus, if Accenture unlawfully used copyrighted
software rather than writing its own code, Consumer Affairs could
be liable to the copyright holder, depending on the facts of the
case. Further, the revised contracts language limits the State’s ability
to recover its losses from a violation.
Consumer Affairs’ Ability to Protect Itself Against Poor Performance by
Accenture May Be Hindered
The maintenance contract for BreEZe lacks measures to help
ensure that Accenture performs work as Consumer Affairs
expects. The best practices contained in the 2011 Information
Technology Infrastructure Library’s IT Service Design recommend
that a service‑level agreement be created between an IT service
provider and the IT customer to define the key service targets and
responsibilities of both parties. According to our IT expert, this
type of agreement should be included in the BreEZe maintenance
contract. For example, a service target that we would expect the
maintenance contract to include is the amount of time Accenture
can take to respond to and resolve technical problems, based
on the severity of the problem. CalTech’s deputy director of the
statewide technology procurement division (procurement division)
agreed that this type of agreement is common. We also noted that
although state agencies are not required to follow it, guidance
from the U.S. Department of Health and Human Services indicates
that a service‑level agreement should also specify performance
guarantees, with associated penalties should the service not be
performed as contracted.
The BreEZe project director stated that as a means to reduce
the contract cost, the maintenance contract did not include a
service‑level agreement. However, he did not recall the specific
cost savings resulting from this omission. Lacking this agreement,
Consumer Affairs is likely hindered from effectively managing the
services Accenture should be providing under the maintenance
California State Auditor Report 2014-116 57
February 2015
contract. For example, without a service target specifying the
amount of time within which Accenture must make design changes
to BreEZe, Consumer Affairs could face difficulty in holding
Accenture accountable for correcting defects to the BreEZe system
in a timely manner.
The State Entities Responsible Cited Various Reasons for Approving
the BreEZe Contract, Despite Its Inadequacies
Given the deficiencies with the BreEZe contracts we describe in
this chapter, we question whether General Services adequately
protected the financial interests of the State in its oversight role
relating to these contracts. Until July 2013 state law required
General Services to oversee all procurements for IT projects. As
part of those responsibilities, state law at that time also specified
that General Services develop and enforce policies and procedures
to conserve the rights and interests of the State. In addition, the
State Contracting Manual indicates that in approving contracts,
General Services assists state agencies by conserving the fiscal
interests of the State and preventing imprudent financial acts.
According to its chief procurement officer, although General
Services will not approve agreements that are illegal or unethical
in nature or that violate stated policy, each contracting department
decides how much risk it is willing to accept. When we discussed General Services’ chief procurement
with the chief procurement officer the BreEZe contract concerns officer agreed that some of the
we had identified, he explained that Consumer Affairs and the clauses in the BreEZe contracts
State retain a measure of protection from any poorly constructed with Accenture place the State at
contract sections by contract provisions that allow the State to additional risk.
terminate the project.19 He agreed that some of the clauses in the
BreEZe contracts with Accenture place the State at additional
risk; however, he indicated that he relied on Consumer Affairs’
attestation that it acknowledged the risks within the BreEZe
contracts and would take proper steps to address those risks.
However, General Services could not provide us evidence that
it had ensured that Consumer Affairs had mitigated the risky
provisions. When we asked General Services and Consumer
Affairs whether their respective legal counsel had any concerns
with the final terms and conditions in the BreEZe contracts, each
department asserted that any such information is confidential and
they would not consent to its disclosure in our report.
19 For example, the BreEZe contracts have a section that allows Consumer Affairs to terminate the
contracts if the Legislature does not appropriate funding for the BreEZe project.
58 California State Auditor Report 2014-116
February 2015
Consumer Affairs’ BreEZe project Consumer Affairs’ BreEZe project director provided two key
director told us that if Consumer reasons that the BreEZe contract changes we described in
Affairs had not revised the BreEZe earlier sections were necessary. Specifically, he told us that if
contract sections to include Consumer Affairs had not revised the BreEZe contract sections
Accenture’s proposed changes, it to include Accenture’s proposed changes, it would have risked
would have risked losing Accenture losing Accenture as a bidder and would have risked needing to
as a bidder and would have risked restart the 18‑month procurement process. Accenture’s letter of
needing to restart the 18-month January 2011 during the RFP process proposing contract revisions
procurement process. tends to support the project director’s claim that Accenture
would not bid on the proposal unless the original contract was
significantly changed.
While Consumer Affairs’ desire to keep the project moving forward
is understandable, the numerous problems it has encountered
with the project, as described in Chapter 1, illustrate the danger
of rushing to implement a complex IT project without proper
safeguards that ensure that the State’s interests are protected and
the project’s goals can be achieved within reasonable time frames
and costs.
General Services and the California Department of Technology
Have Failed to Ensure That Consumer Affairs Complies With
Contract Requirements
Despite a provision in the BreEZe contracts requiring Consumer
Affairs to forward all requests for changes to the BreEZe system
to General Services for review, neither General Services nor its
successor with regard to IT project procurement, the California
Department of Technology (CalTech), could demonstrate that they
had reviewed any of these requests. As described earlier, General
Services approved the original BreEZe contracts. In addition, as
of July 2013, CalTech had authority over and responsibility for
procurements for IT projects such as BreEZe and was responsible for
approving the first BreEZe contract amendment in 2014.20 Provisions
of the BreEZe contracts require that Consumer Affairs submit certain
contract documentation to General Services for review.
Among the requests for changes that General Services or
CalTech should have reviewed were those that requested changes
to the statement of work in the design contract or a work
authorization (change requests); both of these actions could
20 Although the contract refers to General Services, we believe the intent of the parties was to
involve whichever state entity was responsible for overseeing IT project procurement during the
period covered by the contract, which would be CalTech effective July 1, 2013.
California State Auditor Report 2014-116 59
February 2015
amend a contract.21 These change requests originate from project
staff, vendor staff, or regulatory entities and seek to change aspects
of the BreEZe design requirements. If Consumer Affairs and
Accenture determine that a change request is an enhancement
to BreEZe not covered by the original BreEZe contract or the
system warranty, the regulatory entities must pay Accenture for
applicable related costs, according to the BreEZe project director.
However, as of late October 2014, neither General Services nor
CalTech could demonstrate that they had collectively reviewed
all of the more than 250 change requests that Consumer Affairs
had considered for approval according to a log Consumer Affairs
maintained. Specifically, during the time that General Services had
IT project procurement authority, Consumer Affairs considered
approximately 100 change requests, while under CalTech’s IT
project procurement authority it considered roughly 150. Of the
approximately 250 change requests, Consumer Affairs approved 130 Of the approximately 250 contract
that have already or will result in additional payments to Accenture change requests, Consumer Affairs
of almost $3 million. In addition to these costs, without ongoing approved 130 that have already or
review by the responsible oversight entity, there is the risk that will result in additional payments to
implemented change requests may improperly exceed the scope of Accenture of almost $3 million.
the BreEZe contracts.
General Services could not explain why it had not reviewed the
change requests. Specifically, General Services’ chief procurement
officer stated that, based on his review of the procurement file
for BreEZe, it does not appear that General Services was aware
of or reviewed the change requests. However, documentation
that Consumer Affairs provided us showed that it had provided
11 change requests to General Services in April 2012, which
General Services acknowledged receiving at that time. General
Services’ chief procurement officer did acknowledge that
Consumer Affairs had previously entered into a large number
of contractual agreements related to BreEZe in November 2011
without General Services’ knowledge, for which General Services
later admonished the department in January 2012. Given this
history, we would have expected General Services to have been
more diligent in ensuring that Consumer Affairs complied with its
contract requirements for the nearly 18 months of General Services’
remaining IT project procurement authority.
Separately, CalTech believes it is meeting the contract requirement
to review the change requests through its independent project
oversight (IPO) specialist for the BreEZe project, but we disagree.
CalTech’s deputy director of its procurement division stated that
21 Consumer Affairs issues a work authorization after both it and Accenture accept a work
request. According to the Accenture project director, work authorizations include requests for
change after BreEZe is implemented and are handled under the BreEZe maintenance support
services contract.
60 California State Auditor Report 2014-116
February 2015
her division has responsibility for procurement approval and that
CalTech’s IT project oversight and consulting division (oversight
division) is responsible for project approval and oversight.
She explained that as a result, the oversight division holds the
responsibility for reviewing the actual implementation of project
management processes and procedures necessary for IT projects,
which includes change requests and work authorizations. However,
when we asked the deputy director of the oversight division
for evidence of those reviews, she provided us a summary of
two reviews that occurred in October 2013 and June 2014 rather
than evidence of reviews occurring contemporaneously with the
change requests. Thus, the reviews that she indicated her division
had performed could not timely evaluate potential changes to the
scope of the contract.
Although Consumer Affairs acknowledged that it has not sent
the majority of the change requests to the appropriate entities, it
still believes it is in compliance with the contract. Specifically, the
manager for change requests for the BreEZe project stated that the
IPO specialist, who is a CalTech employee, had access to all of the
change request documents. She further explained that the contract
does not state when Consumer Affairs will forward the change
requests for review, nor does it state that the review is required
for any subsequent action. Therefore, Consumer Affairs believes it
would be appropriate to forward all the change request documents
to CalTech when the contract is complete or upon request. We do
not believe this interpretation reflects the intent of the language
in the contracts concerning change requests, because submitting
change requests after the contract is complete, or upon request,
would eliminate the possibility that CalTech could intervene during
the contract term if it thought a change request was outside the
scope of the contract. Moreover, because neither General Services
nor CalTech reviewed the vast majority of the change requests, the
State lacks assurance that approved changes did not compensate
Accenture inappropriately.
Recommendations
CalTech
To ensure that future IT project procurements do not jeopardize
the State’s financial interests, CalTech’s procurement division
should do the following:
• Document its reasons for approving any deviations from
standard contract language.
California State Auditor Report 2014-116 61
February 2015
• Ensure that contract language gives departments the rights to
the source code necessary to complete the project if a contract is
terminated for convenience.
• Ensure that contract language contains assurances that state
funds will not be used for unauthorized purposes.
• Ensure that contracting departments can appropriately manage
IT maintenance support contracts by including service‑level
agreements in these contracts.
To ensure that contracting departments comply with requirements,
CalTech should periodically monitor the status of contracts and
enforce adherence to procurement requirements. For example,
CalTech should ensure that contracting departments forward all
change requests to it and that it conducts reviews of all change
requests to determine whether the changes exceed the scope of the
respective contract.
Consumer Affairs
To ensure that it complies with all terms of the BreEZe contract,
Consumer Affairs should develop and follow a process for doing so,
including documenting how it has met applicable contract terms,
such as forwarding all change requests to CalTech.
62 California State Auditor Report 2014-116
February 2015
Blank page inserted for reproduction purposes only.
California State Auditor Report 2014-116 63
February 2015
Chapter 3
THE BOARD OF REGISTERED NURSING MADE SOME
UNSUBSTANTIATED REPORTS OF DIFFICULTIES FROM
IMPLEMENTING BREEZE, AND OTHER REGULATORY
ENTITIES ALSO REPORT CHALLENGES WITH BREEZE
Chapter Summary
The Board of Registered Nursing (BRN) indicated that since
implementing the BreEZe system, it has faced significant delays
in processing applications and has been forced to modify its
business processes. However, although BRN asserted that it
was exceeding maximum time frames for processing certain
applications, we found little evidence that it tracks the information
needed to support such claims. Our review of a selection of
license applications found that BRN, on average, processed these
applications well within allowable maximum time frames. Further,
as of September 2014, BRN was facing a significant number of
applications that were pending its review—more than 7,000.
Because BRN does not track this information, it cannot adequately
assess its workload and whether it is using staff appropriately.
BRN attributes its reported delays in processing applications to
a variety of issues it has encountered in implementing BreEZe,
including the cumbersome nature of entering applicants’
information into the system. Although some of the issues it points
to are valid, BRN does not track the information necessary to
assess their impact. Further, BRN asserts that without additional
resources, it will not be able to process license applications within
applicable time frames; however, it has not adequately justified its
recent request for additional positions.
Additionally, in September and October of 2014, we interviewed
the executive officers of the regulatory entities the California
Department of Consumer Affairs (Consumer Affairs) included in
phase 1 of the BreEZe implementation and learned that few of them
are generally satisfied with the system. In fact, most of the executive
officers reported decreased operational efficiencies for their entities
after implementing BreEZe. Nonetheless, most executive officers
reported that they are hopeful the system will function adequately
once their concerns are addressed.
64 California State Auditor Report 2014-116
February 2015
BRN Lacks Information Critical to Assessing Its Efficiency, and Its
Claims About Increased Processing Times Are Unsubstantiated
Various BRN stakeholders, including the media and members of
the Legislature, have raised concerns recently about the timeliness
with which BRN has processed applications since implementing the
BreEZe system. Media reports regarding BRN, as mentioned in the
Introduction, have largely focused on its untimely processing of
license applications received from students who recently graduated
from nursing programs and were seeking to take the nursing
examination for licensure for the first time—referred to as the
application for licensure by examination (examination application).
BRN’s 2014 Sunset Review Report indicates that the average
processing times for examination applications more than doubled
from 37 days in fiscal year 2011–12 before it implemented BreEZe
to 82 days in fiscal year 2013–14 after implementing the system.22
BRN reported that when it first Additionally, BRN reported that when it first implemented BreEZe,
implemented BreEZe, its staff could its staff could not complete an initial review of an application within
not complete an initial review of the 90 days specified by its regulations. Although BRN attributes
an application within the 90 days its inefficiency in processing applications to the implementation
specified by its regulations. of BreEZe, we found that it is unable to substantiate such
claims because it does not track the amount of time it takes to
process applications.
In fact, BRN could provide little evidence demonstrating that it
tracks the timeliness of its application processing. For instance,
BRN officials provided examples of some reports they said they
had used before implementing BreEZe to track the timeliness
within which BRN processed applications. However, we found
these reports to be of limited value for assessing specific
application processing times. For example, the reports generally
presented information on the number of applications received and
processed but did not contain the average number of days it took
to process applications by type. Only one report that BRN provided
presented information on the average number of days it took to
process applications; however, again this report did not present
these averages by type of application, thus hindering BRN’s ability
to identify which types of applications take staff longer to process
than others. Further, in providing us with this report, BRN officials
informed us that the average number of days for processing was
overstated, calling into question the accuracy of the data.
Moreover, the assistant executive officer explained that since
implementing BreEZe, BRN has been unable to track the timeliness
of its processing of license applications using the BreEZe system
22 BRN’s Sunset Review Report is submitted to the Senate Business, Professions and Economic
Development Committee and the Assembly Business, Professions and Consumer Protection
Committee for their consideration.
California State Auditor Report 2014-116 65
February 2015
because the system provides poor‑quality data and does not track
the receipt date identified in regulations as the starting point for
time measurement. The assistant executive officer added that BRN
is working with Consumer Affairs to update BreEZe in order to
resolve the issue related to the receipt date. Without this ability,
BRN’s deputy chief of licensing and administrative services (deputy
chief) said that staff perform a visual review of applications to gauge
the length of time they have been pending review.
Further, although BRN included average application processing
times in its Sunset Review Report for both pre‑ and post‑BreEZe
implementation, these averages were created specifically for the
report, and the time frames are of limited value for evaluating
BRN’s ability to process applications within regulated time frames
because of their lack of accuracy. For example, BRN officials
acknowledged that the average processing times for license
applications presented in the Sunset Review Report include
time other than what BRN staff spent processing applications.
Specifically, when BRN determines a license application does
not contain all of the necessary applicant information, it should
notify the applicant of this deficiency and the applicant may
submit the information to resolve the deficiency. Because the
averages provided in the Sunset Review Report include the time an
applicant takes to provide the missing information to BRN, these
averages should not be used in evaluating BRN’s ability to process
applications within regulatory time frames. In fact, BRN states
in the Forward section of the Sunset Review Report that in many
instances the data provided are a “best estimate” of the true data
and consequently the fiscal year 2013–14 data should be viewed
with caution, especially when attempting to compare them to data
from previous years.
Regulations require BRN to review, within 90 days of receipt,
whether an examination application is complete. From the point
that BRN accepts an application as complete, it has another
390 days to evaluate whether the applicant meets licensure
requirements and to notify the applicant of its decision regarding
the application. Thus, BRN conducts its evaluation of this
application type in two reviews. Two other ways individuals
may apply for licensure are through licensure by endorsement
(endorsement), which is similar to the examination application but
for out‑of‑state registered nurses seeking a California license, and
license by renewal (renewal), which is used to renew currently valid
licenses for California registered nurses. According to the deputy
chief, BRN’s practice is to perform its review for completeness
and licensure requirements simultaneously for these two
application types, since these applicants are not required to pass an
examination, as is the case with the examination application.
66 California State Auditor Report 2014-116
February 2015
Lacking sound data from BRN to substantiate its claims of
increased inefficiencies caused by BreEZe, we conducted our
own review of selected license applications to get a sense of
the impact BreEZe has had on the efficiency with which BRN
processes applications. We selected 30 applications processed
before, and another 30 applications processed after, BRN’s
implementation of BreEZe, for a total of 60 applications. As shown
in Figure 3, our analysis of these applications indicates that BreEZe
might not have significantly affected BRN’s ability to process
applications within maximum time frames; however, it might
have delayed its processing of one application type. Specifically,
for endorsement applications included in the applications we
reviewed, BRN’s processing time increased from an average of
35 days before implementing BreEZe to an average of 60 days
after implementation. Nonetheless, the average processing times
indicate that for the limited selection of applications we reviewed,
BRN has processed the applications well within the maximum
time frames. In the case of BRN’s first review of examination
applications, Figure 3 shows that BRN’s average processing times
for the applications we reviewed increased by only two days,
from an average of 29 days before implementing BreEZe to an
average of 31 days after implementation. On the other hand, BRN’s
average processing time for its second review of the examination
applications we reviewed decreased since implementing BreEZe,
from an average of 76 days to 52 days, which is significantly less
than the maximum allowed time frame of 390 days. Similarly,
BRN’s processing of renewal applications we reviewed also
BRN needs to formally track license decreased, from an average of 17 days before implementing BreEZe
application processing times to to 14 days after implementation. Although these results are based
ensure it is properly identifying on a selection of applications, they highlight the need for BRN to
areas where it could improve its formally track such information so it can ensure that it is properly
use of staff and its procedures for identifying areas where it could improve its use of staff and its
evaluating applications that are procedures for evaluating those applications that are now taking
now taking longer to process. longer to process.
Because average processing times for the applications we reviewed
did not align with the delays BRN reported facing in processing
applications, particularly examination applications, for the first
several months after implementing BreEZe in October 2013 we
reviewed an additional six examination applications received during
November 2013 through January 2014. We found that BRN took an
average of 62 days to conduct the first review of these applications—
double the average time it took BRN to conduct the first review of
the examination applications we included in Figure 3, but still well
within the 90‑day maximum time frame. The increased processing
time for the additional applications we reviewed is consistent with
the reported difficulties BRN faced when first implementing BreEZe.
Following Figure 3, we describe the reasons BRN stated that it faced
delays in processing examination applications.
California State Auditor Report 2014-116 67
February 2015
Figure 3
Board of Registered Nursing Average License Application Processing Times for a Selection of License Applications
Before and After the Implementation of BreEZe
syaD
80 Average Number of Days to Process
76 Pre-BreEZe Implemention
70
Post-BreEZe Implemention
Maximum Time Frame
60
60
50 52
40
35
30
31
29
20
17
14
10
0
Application for Original License Application for Application for
by Examination* Original License by License by Renewal‡
Endorsement†
90 Days 390 Days 90 Days 60 Days
First Review Second Review
Application Type
Sources: California State Auditor’s analysis of 30 applications processed before BreEZe implementation, for the period July 1, 2011, through October 2, 2013,
and 30 applications processed after BreEZe implementation for the period October 8, 2013, through July 31, 2014; the Board of Registered Nursing (BRN) Web
site; and California Code of Regulations, sections 1410.1 and 1419.2.
Note: There are other types of applications the BRN processes that are included in Table 8 on page 69; however, those application types are not included in
this table as they are not applications to obtain a California registered nurse license.
* Applications for original license by examination have two reviews. Regulations require BRN to review, within 90 days of receipt, whether an examination
application is complete. From the point that BRN accepts an application as complete, BRN has another 390 days to evaluate whether the applicant meets
licensure requirements and notify the applicant of its decision regarding the application.
† An application for original license by endorsement is an application for a California registered nurse license for applicants who are already licensed in
another state or Canada and do not need to take the registered nurse license examination.
‡ An application for license renewal is an application for renewal of a currently valid California registered nurse license.
While Figure 3 shows that on average BRN processed the
applications that we reviewed within the time frames specified
in regulations, there were two instances in which BRN exceeded
the maximum time frame. One of these applications was an
endorsement application that took 27 days longer than the required
90 days BRN has to complete its review. The second application was
a renewal that took 73 days for BRN to review, which exceeded the
60‑day maximum review period. When we asked BRN about these
specific applications, BRN’s deputy chief offered several reasons for
not meeting the review time frame for the endorsement application:
the application was received during the time of year when the
68 California State Auditor Report 2014-116
February 2015
largest number of applications are received, BRN was dealing with
several issues related to BreEZe that slowed down application
processing, and BRN was focused on examination applications.
The deputy chief attributed the delay in BRN’s processing the
renewal application in question to a hold that the BreEZe system
erroneously placed on the application; staff subsequently identified
and corrected the error.
BRN reports it is unable to track the number of license
applications it has received but has yet to review using BreEZe,
and therefore it cannot adequately assess its workload with
BreEZe. For the purposes of this report, we refer to applications
BRN has received but not yet started to review as its pending
workload. Because BRN lacks BreEZe data that would allow us to
identify its pending workload, we manually counted the number of
applications that made up BRN’s pending workload on a specific
day during the course of our audit work. As shown in Table 8,
on September 2, 2014, BRN’s pending workload was more than
7,000 applications. Of this number, just less than 1 percent, or
63 applications, of which 54 were applications for endorsement,
had exceeded the processing time frame specified in regulations.
BRN’s deputy chief explained that some of the applications
for endorsement, which comprised almost 40 percent of the
applications in its pending workload, were not processed within
the maximum 90‑day time frame because BRN has focused its
resources on processing a large number of examination applications
submitted by recent nursing graduates in June, July, and
August 2014. Such decisions further underscore the importance of
BRN making decisions that are based upon actual data, in this case
the amount, type, and age of applications pending review rather
than estimating based on a visual review of its files.
BRN Asserts That It Has Faced Various Obstacles in Processing
Applications Because of BreEZe
According to BRN’s deputy chief, BRN reports that it has faced, and continues to face, obstacles
BRN provided system requirements in its implementation of the BreEZe system. BRN’s deputy chief
to Consumer Affairs and Accenture, explained that BRN provided system requirements to Consumer
but the BreEZe system did not Affairs and Accenture LLP (Accenture), but the BreEZe system did
include all of these requirements. not include all of these requirements. As described in Chapter 1,
system requirements define the business problem to be solved and
specify what the system should do, which is critical to successful
system development. Further, BRN told us it did not have adequate
opportunity to test the BreEZe system before it was implemented,
citing, for example, that the cashiering module did not work when
BRN tested the system. The BreEZe project director disputed
this claim, stating that each phase 1 regulatory entity had the
opportunity to test the system before its implementation and that
California State Auditor Report 2014-116 69
February 2015
BRN conducted this testing in June 2013, which included processing
several complete transactions that BRN subject matter experts had
identified as most important. Nevertheless, BRN’s deputy chief
maintained that even the BreEZe sandbox—a version of BreEZe
available during user acceptance testing that phase 1 regulatory
entities (that is, 40 boards, bureaus, committees, and a commission)
could use to simulate completing work in the system—did not
provide simulation of real‑world transactions. Rather, BRN staff
tested subfunctions of the system, such as a new application
being initiated by cashiering, in a controlled environment with
planned results.
Table 8
Status of Applications Pending Review by the Board of Registered Nursing as of September 2, 2014
MAXIMUM
NUMBER OF DAYS AVERAGE TIME FRAME NUMBER OF
ELAPSED SINCE DAYS ELAPSED TO EVALUATE APPLICATIONS
NUMBER OF THE OLDEST SINCE A LICENSE EXCEEDING
APPLICATIONS APPLICATIONS APPLICATIONS APPLICATION FOR THE MAXIMUM
TYPE OF APPLICATION PENDING REVIEW WERE RECEIVED WERE RECEIVED COMPLETENESS TIME FRAME
License by Examination 761 85 36 90 0
License by Examination (Web-Based) 337 107 34 90 3
License by Examination (Repeat) 438 103 36 90 5
License by Endorsement 2,865 92 45 90 54
License by Renewal 230 62 11 60 1
Advanced Practice Certification 1,206 154 48 NA NA
Verification of License 1,325 70 24 NA NA
Duplicate License Record 90 25 18 NA NA
Re-Activation of License 3 8 8 NA NA
Re-Activation of License (8+ years) 4 89 58 NA NA
Totals 7,259 63
Sources: California State Auditor’s analysis of applications pending initial review by the Board of Registered Nursing (BRN), and California Code of
Regulations, sections 1410.1, 1419.2, 1483, and 1493.
Note: As described on page 68, because BRN does not track the number of applications it has received but has not yet reviewed, we manually counted the
number pending its review as of September 2, 2014.
NA = Not applicable.
The BRN deputy chief also indicated that the increased time
BRN has reported it takes to process applications is due, in part,
to new steps in the process as a result of BreEZe. For example,
she explained that since implementing BreEZe, BRN must wait
three to five days for Consumer Affairs’ central cashiering unit to
produce a certain report that BRN must receive before it can begin
to process a license application. Although this additional step in
BRN’s process is a permanent change, some other steps will be
resolved as BreEZe is updated in the future, such as an extra step
BreEZe has caused BRN to take in its processing of temporary
license applications, which we describe later. However, because
70 California State Auditor Report 2014-116
February 2015
BRN has not been systematically tracking information pertaining Further, according to the deputy chief, when BRN implemented
to the timeliness of its application processing before implementing BreEZe, the system did not notify BRN’s examination vendor of
BreEZe or after, including which stages of the process might be applicants that BRN had determined were eligible to sit for the
contributing to any delays, BRN could not substantiate the effect of license examination, as BRN expected BreEZe to do, and it was
these additional steps on its application processing. several months before the problem was corrected. According to
the deputy chief, this function did not work properly from the
BRN’s executive officer explained that BreEZe operates much implementation of BreEZe in October 2013 until December 2013.
differently than the previous legacy systems and that this has also She indicated that Consumer Affairs and BRN worked together and
contributed to delays. For instance, according to the BRN deputy resolved the problem. Nevertheless, this issue caused significant
chief, the number of screens within BreEZe requiring information delays for BRN in its processing of applications. Specifically, the
from BRN staff has increased. To support its contention that deputy chief stated that because the examination vendor was not
BreEZe has increased application processing times, the deputy chief notified of applicants’ examination eligibility, BRN and Consumer
shared with us the results of a time study BRN staff conducted in Affairs had to create new eligibility transactions for thousands of
January 2014 to determine the amount of time it takes to process applicants. BRN cited this issue as the primary factor contributing
applications in BreEZe compared to the legacy systems. BRN’s to the delays faced by nursing program graduates applying for
time study indicates that entering information into BreEZe has the examination application and in obtaining employment in
taken anywhere from 2.5 minutes to 13 minutes longer for each October 2013 through January 2014.
application, depending on the type of application. However, BRN’s
time study is of limited value because it does not take into account According to BRN officials, BRN had to develop numerous According to BRN officials, BRN had
the total number of applications it processes by type. Without workarounds in all areas of its operations because BreEZe was to develop numerous workarounds
including this information, BRN cannot adequately assess the not fully functional when implemented. An example of such in all areas of its operations because
impact the increase in processing times has had on its workload a workaround concerns temporary licenses that BRN issues BreEZe was not fully functional
by application type and make necessary changes to its use of staff. to certain applicants. The deputy chief explained that from when implemented.
Furthermore, the deputy chief indicated in November 2014 that BRN’s perspective, the system should expire temporary licenses
the average application processing times with BreEZe have likely automatically when the true license is approved, as this function
decreased from what they were in the time study because BRN was reportedly available in the legacy systems; however, this
staff have become more comfortable using BreEZe and some of the functionality was not included in the design of the BreEZe system,
problems with BreEZe have been fixed. Thus, while the results of and staff have had to monitor and manually expire the temporary
the time study may highlight differences in application processing licenses. To resolve issues like these, BRN and all of the regulatory
times before and after implementing BreEZe, the results are entities can submit issues they identify to Consumer Affairs for
apparently outdated. review. If necessary, Consumer Affairs logs the issue as a system
investigation request (SIR). According to Accenture’s BreEZe
Of additional concern to BRN is that it lacks confidence in the project director, Consumer Affairs and Accenture work together
total number of licensed California nurses reported in BreEZe. to determine if a SIR is a defect or an enhancement. A SIR is
The deputy chief explained that according to BreEZe data as of a defect when BreEZe is not operating as designed and, thus,
September 2014, the total number of licensed nurses in California Accenture is obligated to correct it. The SIR is an enhancement
According to BRN’s deputy chief, was the same as the amount reported by its legacy systems about if BreEZe is operating as designed and to resolve such a SIR
when BRN implemented BreEZe, a year earlier. This is disconcerting to BRN because, according requires pursuing a change request. According to the BreEZe
the system did not notify BRN’s to the deputy chief, it expects annual growth of approximately project director, regulatory entities pay for such enhancements.
examination vendor of applicants 10,000 licensed nurses. However, the former business project According to documentation Accenture’s BreEZe project director
that BRN had determined were manager for BreEZe explained that the legacy systems overstated provided, as of September 30, 2014, BRN had submitted the
eligible to sit for the license the number of licensees because it sometimes double‑counted highest number of SIRs of any regulatory entity included in phase 1.
examination. certain individuals, whereas BreEZe counts each individual Specifically, BRN had submitted over 1,000 SIRs, of which roughly
only once. Nonetheless, the deputy chief explained that BRN 200 were submitted after implementing BreEZe. According to
is not satisfied with this response and maintains that BreEZe is Consumer Affairs, BRN has paid a total of more than $300,000 for
understating the number of licensed nurses. enhancements. Our information technology (IT) expert believes
that the sheer volume of the changes BRN requested suggest that
Consumer Affairs may not have adequately planned the system.
California State Auditor Report 2014-116 71
February 2015
Further, according to the deputy chief, when BRN implemented
BreEZe, the system did not notify BRN’s examination vendor of
applicants that BRN had determined were eligible to sit for the
license examination, as BRN expected BreEZe to do, and it was
several months before the problem was corrected. According to
the deputy chief, this function did not work properly from the
implementation of BreEZe in October 2013 until December 2013.
She indicated that Consumer Affairs and BRN worked together and
resolved the problem. Nevertheless, this issue caused significant
delays for BRN in its processing of applications. Specifically, the
deputy chief stated that because the examination vendor was not
notified of applicants’ examination eligibility, BRN and Consumer
Affairs had to create new eligibility transactions for thousands of
applicants. BRN cited this issue as the primary factor contributing
to the delays faced by nursing program graduates applying for
the examination application and in obtaining employment in
October 2013 through January 2014.
According to BRN officials, BRN had to develop numerous According to BRN officials, BRN had
workarounds in all areas of its operations because BreEZe was to develop numerous workarounds
not fully functional when implemented. An example of such in all areas of its operations because
a workaround concerns temporary licenses that BRN issues BreEZe was not fully functional
to certain applicants. The deputy chief explained that from when implemented.
BRN’s perspective, the system should expire temporary licenses
automatically when the true license is approved, as this function
was reportedly available in the legacy systems; however, this
functionality was not included in the design of the BreEZe system,
and staff have had to monitor and manually expire the temporary
licenses. To resolve issues like these, BRN and all of the regulatory
entities can submit issues they identify to Consumer Affairs for
review. If necessary, Consumer Affairs logs the issue as a system
investigation request (SIR). According to Accenture’s BreEZe
project director, Consumer Affairs and Accenture work together
to determine if a SIR is a defect or an enhancement. A SIR is
a defect when BreEZe is not operating as designed and, thus,
Accenture is obligated to correct it. The SIR is an enhancement
According to BRN’s deputy chief, if BreEZe is operating as designed and to resolve such a SIR
when BRN implemented BreEZe, requires pursuing a change request. According to the BreEZe
the system did not notify BRN’s project director, regulatory entities pay for such enhancements.
examination vendor of applicants According to documentation Accenture’s BreEZe project director
that BRN had determined were provided, as of September 30, 2014, BRN had submitted the
eligible to sit for the license highest number of SIRs of any regulatory entity included in phase 1.
examination. Specifically, BRN had submitted over 1,000 SIRs, of which roughly
200 were submitted after implementing BreEZe. According to
Consumer Affairs, BRN has paid a total of more than $300,000 for
enhancements. Our information technology (IT) expert believes
that the sheer volume of the changes BRN requested suggest that
Consumer Affairs may not have adequately planned the system.
72 California State Auditor Report 2014-116
February 2015
Although BRN Has Taken Steps to Make Its Business Process More
Efficient, It Also Is Requesting More Staff
Since implementing BreEZe, BRN has taken some steps to
review and modify its business process in order to increase its
efficiency in processing applications. For example, BRN changed
its practice of assigning license applications to evaluators based on
the alphabetical order of applicants’ names to having evaluators
pull applications from a central location with applications stored
according to receipt date, a change we observed. In addition, BRN
told us it eliminated the support services duties of its application
evaluators so they are able to focus on application reviews.
In February 2014 Consumer Affairs provided BRN with a team of
employees from Consumer Affairs’ consumer information center
and the Bureau of Automotive Repair to assist BRN in processing
license applications. The team ultimately spent nearly five months
assisting BRN and in June 2014, at the request of Consumer Affairs’
director, the team provided 13 suggestions to BRN’s executive officer
on how to increase efficiencies in processing applications. For
example, to speed up application processing, the team suggested
that BRN forward the fingerprint cards submitted by license
applicants to the California Department of Justice for clearance
once cashiering confirms payment of the applicable fee. As of
November 2014, BRN’s assistant executive officer indicated that it
was considering this suggestion. When we asked BRN’s assistant
executive officer as to whether BRN has taken steps to implement
the remaining suggestions, she told us that either the suggestions
were too labor‑intensive to consider implementing at that time or
BRN’s processes already reflected the suggestions. For example,
although one of the suggestions was that BRN produce procedure
manuals describing the process it uses to evaluate applications, it
has had such procedure manuals in place since 2005.
According to BRN, it has requested additional resources it believes
it needs to be able to process license applications within maximum
time frames. Specifically, BRN’s Sunset Review Report states that
BRN submitted a request to the California Department of Finance
for another 26 positions for fiscal year 2015–16. BRN explained
that the additional staff would cost approximately $2.6 million to
hire. But as described earlier in this chapter, we found the data
in the Sunset Review Report to be of limited value for evaluating
BRN’s ability to process applications within regulatory time
frames. Further, because BRN did not support its request for the
26 additional positions in the Sunset Review Report with specific
analysis, we asked BRN to provide us with this analysis. The analysis
BRN provided to us was based on data from fiscal years 2011–12
and 2012–13, the two years preceding its implementation of BreEZe,
which means the analysis does not reflect its workload and business
California State Auditor Report 2014-116 73
February 2015
processes since implementing the BreEZe system. Thus, the
additional positions it has requested are not adequately justified by
this analysis.
Most Regulatory Entities That Implemented BreEZe More Than a Year
Ago Report That They Continue to Face Significant Challenges With
the System
Most of the executive officers of the 10 phase 1 regulatory entities
told us that they are generally dissatisfied with their BreEZe
experience because it has not met their expectations in a variety
of ways. Our interview questions addressed their satisfaction with
BreEZe, including their experiences during user acceptance testing
and whether they believe the training their staff received was
adequate. Further, we inquired about the sufficiency of BreEZe’s
reporting capabilities and data accuracy, as well as the regulatory
entities’ overall experience with the system as of the date we
conducted our interviews, which occurred in mid‑September 2014
through mid‑October 2014.
Table 9 on the following page presents responses to selected
questions from our interviews with the executive officers, showing
that each reported experiencing issues with certain aspects of the
BreEZe project. For example, the majority were unsatisfied with
the testing they were able to conduct before implementing the
system, and most found the training for BreEZe was inadequate.
Of greater concern is that eight of the 10 executive officers
reported that BreEZe has decreased their regulatory entity’s
operational efficiency.
Our interviews indicated that Consumer Affairs and Accenture did Our interviews with 10 phase 1
not deliver the system that the regulatory entities expected based regulatory entities indicated that
on the design phase of the BreEZe project. Most of the executive Consumer Affairs and Accenture
officers we spoke with indicated that they wanted a new system did not deliver the system that
for a variety of reasons, including to better meet their business the regulatory entities expected
needs. For example, the executive officer of the Physician Assistant based on the design phase of the
Board said board staff thought BreEZe would lead to efficiencies BreEZe project.
in the licensing and enforcement functions of the board. Most of
the executive officers also indicated that Consumer Affairs did
an adequate job of obtaining their buy‑in to BreEZe. However,
several commented that the system they were originally promised
by Consumer Affairs officials is certainly not the system they
received. Some of them had assumed that the BreEZe system would
effectively perform the functions of the legacy systems in use by
the regulatory entities. To illustrate, the Board of Psychology had
expected BreEZe to include legacy‑like system functions, such
as the ability to manually enter data relating to school codes and
74 California State Auditor Report 2014-116
February 2015
examination no‑shows, but it found that BreEZe did not.23 Similarly,
several executive officers reported that the planning work they
did initially for BreEZe, in which they described their business
processes to Accenture and Iron Data (the builder of BreEZe and
an Accenture subcontractor), appeared adequate. However, in
hindsight, several other executive officers from different regulatory
entities indicated that Accenture and Iron Data exaggerated what
the system could accomplish.
Table 9
Selected Responses From 10 Regulatory Entities to Questions Regarding Their Experiences With the BreEZe System
CONCERNS
READY TO SATISFIED ADDRESSED
CALIFORNIA DEPARTMENT OF OVERALL SATISFIED SATISFIED IMPLEMENT WITH REPORTS EFFECT ON IN ADEQUATE
CONSUMER AFFAIRS (CONSUMER AFFAIRS) SATISFACTION WITH DESIGN SATISFIED WITH BREEZE IN AND DATA OPERATIONAL AND TIMELY
REGULATORY ENTITY WITH BREEZE PLANNING WITH TESTING TRAINING OCTOBER 2013 ACCURACY EFFICIENCY MANNER
Board of Barbering and Cosmetology Fair Yes No No Yes No Decreased No
Board of Behavioral Sciences Fair Yes Yes Yes Yes No Decreased Yes
Board of Podiatric Medicine Good Yes Yes Yes No No Increased Yes
Board of Psychology Fair No No No No No Decreased No
Board of Registered Nursing Poor Yes No No No No Decreased No
Medical Board of California Fair No No No Yes No Decreased No
Naturopathic Medicine Committee Poor No No No Yes No Decreased No
Osteopathic Medical Board Poor No No No Yes No Decreased No
Physician Assistant Board Fair No No No No No Decreased No
Respiratory Care Board Very Good No Yes Yes Yes No Increased Yes
Sources: The 10 Consumer Affairs’ regulatory entities included in phase 1 of the BreEZe implementation.
Note: The column titled Overall Satisfaction With BreEZe presents the regulatory entities’ responses to a question regarding their overall satisfaction with
the BreEZe system as of the dates we conducted our interviews, which occurred in mid-September 2014 through mid-October 2014. Thus, this column does
not represent a summary of the responses we received to the remaining questions presented in this table. Rather, the regulatory entities’ responses to the
remaining questions in this table represent their experiences with the BreEZe system at different points in time during the course of the project.
Some executive officers also commented that they had informed
Iron Data or Consumer Affairs of their specific needs for BreEZe,
yet BreEZe did not meet those needs at the time of implementation.
For example, the executive officer of the Board of Barbering and
Cosmetology (Cosmetology) told us that although Cosmetology
communicated to Iron Data during the BreEZe design phase its
need for an inspection module in BreEZe to include counting
and adding features, Iron Data did not include these features in
phase 1. The executive officer explained that Cosmetology found
it necessary to submit a change request to have these functions
implemented at a cost of $116,000. Similarly, the executive officer
23 In December 2014 the BreEZe project director furnished us with evidence that BreEZe now
provides these functions.
California State Auditor Report 2014-116 75
February 2015
for the Medical Board of California stated that it has had to use
workarounds since BreEZe was implemented to meet a legal
requirement to disclose malpractice settlements, because the
system does not currently provide a feature that allows the Medical
Board of California to access the information necessary to make the
disclosures, despite Accenture and Iron Data knowing of this need
from the beginning of the BreEZe project.
Seven of the 10 regulatory entities told us that they experienced a
variety of problems during user acceptance testing. Some of the
executive officers commented that testing had a significant impact
on daily operations or noted they had to commit qualified staff
to the process for many more months than originally planned.
Several also noted that the BreEZe system they tested during user
acceptance testing was not the system they had been promised
during the design phase. As a result, the regulatory entities wrote
and submitted many SIRs. According to data Accenture provided,
Consumer Affairs and the regulatory entities submitted over
7,300 SIRs in total, including over 5,800 during user acceptance
testing and nearly 1,500 following the phase 1 implementation of
BreEZe. While the Accenture BreEZe project director provided an
estimate that less than 30 percent of the SIRs closed during user
acceptance testing were system defects and Accenture’s data show
that only 17 percent of the SIRs closed during implementation were
system defects, the sheer number of instances—over 7,300—in
which BreEZe did not function as its users expected or desired is an
indication of the extent of the deficiencies in the system’s design.
Another example of these design deficiencies is the approximately
$3 million that Consumer Affairs and its regulatory entities have
approved for enhancements to BreEZe as of December 2014.
According to the BreEZe project director, the regulatory entities The BreEZe project director
had the opportunity to specify their needs during the design explained that during user
phase of the project, but he believes that Accenture did not acceptance testing, which occurred
document the information conveyed in related interviews with the from November 2012 through
regulatory entities; instead it proceeded with the design according October 2013, Consumer Affairs
to memory recall and incomplete informal notes. Further, he realized that the system Accenture
explained that during user acceptance testing, which occurred from built was not what Consumer
November 2012 through October 2013, Consumer Affairs realized Affairs had asked for. Consequently,
that the system Accenture built was not what Consumer Affairs the regulatory entities have had
had asked for. Consequently, the regulatory entities have had to to pay extra for changes to the
pay extra for changes to the system in order to have it meet their system in order to have it meet their
functional requirements. functional requirements.
Some executive officers told us that they communicated their
concerns about BreEZe to the director of Consumer Affairs
throughout user acceptance testing, largely during weekly meetings
the director held with the executive officers. Further, although the
regulatory entities prioritize SIRs, a few executive officers stated
76 California State Auditor Report 2014-116
February 2015
that Consumer Affairs or Accenture addressed minor concerns
adequately and in a timely manner, but larger, more critical SIRs
have remained unresolved, sometimes for months. In response,
the BreEZe project director noted that SIRs of greater work effort
and complexity, regardless of their criticality, naturally take more
time to plan, design, develop, test, and implement than minor
SIRs. Nonetheless, we believe this approach may negatively affect
the regulatory entities because it can allow significant BreEZe
deficiencies to persist for extended periods of time, which in turn
interferes with the entities’ ability to meet their business needs.
All but three of the regulatory entities we interviewed found
that the BreEZe training that Consumer Affairs provided was
inadequate. Many of these regulatory entities stated that the
training was overly general rather than specific to their business
processes, and some indicated that the BreEZe system available
during training was of limited functionality and thus did not
provide an appropriate training environment. Most of these
regulatory entities also told us that the training was untimely, as
it was provided roughly nine months before user acceptance testing
was completed. Consumer Affairs’ former organizational change
manager stated that Consumer Affairs provided both high‑level
and specific training, distributed tip sheets and job aids, and
offered refresher courses when new functionality was introduced.
Nonetheless, training as a whole remained inadequate in the view
of the regulatory entities.
Although more than half of the executive officers of the phase 1
regulatory entities indicated that they were ready to implement
the system in October 2013, many nonetheless had concerns
about the system itself. For example, the assistant executive
officer of the Osteopathic Medical Board stated that while the
board was ready, “the [BreEZe] system was not.” In addition,
although the executive officer of the Board of Psychology
indicated that the board could have been much more prepared for
implementation than it was, the board felt it best to proceed with
implementation because of the extended user acceptance testing
period; Cosmetology’s executive officer expressed a similar belief.
A few of the executive officers of A few of the executive officers commented that Consumer Affairs
the phase 1 regulatory entities and Accenture pressured them to certify that they were ready to
commented that Consumer implement the system. The director of Consumer Affairs noted
Affairs and Accenture pressured that he held weekly meetings with the regulatory entity executives
them to certify they were ready to regarding the BreEZe project and that these executives approved
implement the system. the BreEZe design and later the product itself at the conclusion of
user acceptance testing. In addition, as a matter of record, shortly
before the BreEZe implementation, Consumer Affairs had the
regulatory entities in phase 1 complete implementation readiness
certifications, which were forms that list eight different readiness
California State Auditor Report 2014-116 77
February 2015
areas for certification, such as regulatory entity staff have completed
planning for business process adjustments following BreEZe
implementation and staff are familiar with the procedures for
processing work under BreEZe.24 However, on these certifications,
several executive officers indicated reservations regarding their
readiness for BreEZe implementation. For example, the Osteopathic
Medical Board executive officer did not indicate her board’s
readiness for external user support. In addition, the assistant
executive officer of BRN wrote “concerned” along with her initials
for two areas—business process adjustments and familiarity with
workarounds needed to facilitate board business upon BreEZe
implementation—and also included a statement noting her concern
with the number of workarounds the system required.
While one of the key selling points of BreEZe was its ability to
produce reports, all 10 of the executive officers agreed that its
reporting capability remains unsatisfactory. According to some
executive officers, at the time it was implemented, BreEZe could
not produce any reports for their entities. However, according to a
Consumer Affairs manager whose unit develops certain customized
BreEZe reports, regulatory entities could generate some reports
when Consumer Affairs implemented BreEZe, but they did not
have the ability to create customizable reports as they had been able
to do under the legacy systems. Several executive officers also told
us that they do not believe that the data in BreEZe are accurate,
including in some cases the number of licensees for their entities
and in other cases amounts related to revenue. A Consumer Affairs Because of system reporting
cashiering subject matter expert confirmed that BreEZe sometimes deficiencies, BreEZe is not always
assigns revenue to the wrong fiscal year, which can result in providing regulatory entities
boards’ fund balances being misstated. Because of these reporting the information necessary to
deficiencies, BreEZe is not always providing regulatory entities meet their business needs, such
the information necessary to meet their business needs, such as as managing their budgets and
managing their budgets and producing annual reports. producing annual reports.
According to Consumer Affairs’ director, BreEZe has reporting
capabilities; however, the design process to get the reports to meet
the business needs of the regulatory entities has been difficult.
He also indicated that he assigned a business manager to oversee
the planning and organization of the reports. The BreEZe project
director explained that as of December 2014, of the 24 report
development requests outstanding, 14 have clearly defined
requirements and could be deployed within four to five months
given current staffing levels, barring any higher priority requests
being submitted. The BreEZe project director further explained
24 Two of the regulatory entities that Consumer Affairs included in BreEZe phase 1 did not sign this
form. The executive officer of the Naturopathic Medicine Committee did not attend the meeting
at which the forms were signed, and a staff member for the Medical Board of California attended
in place of the executive director and did not sign the form.
78 California State Auditor Report 2014-116
February 2015
that at the time of implementation, BreEZe produced all of the
reports the regulatory entities approved during the design phase,
although Consumer Affairs has no documentation of the approvals.
The project director also indicated that because the regulatory
entities make numerous requests for new reports and changes to
existing reports, Consumer Affairs is considering IT solutions,
such as business intelligence and data warehouse systems, which
would provide them with the independent capability to produce the
ongoing reporting changes they desire.
Most executive officers believe that once all of the remaining
problems with the BreEZe system are fixed, it will meet their
business needs. For example, the executive officer of the Board of
Psychology stated that the BreEZe system does not yet efficiently
serve all of its business needs, but it “can get there.” The project
director stated he is unable to determine when all outstanding
SIRs for the phase 1 regulatory entities will be resolved. The BreEZe
project director added that focusing only on SIRs outstanding
as of November 2014, he estimated these could be resolved by
August 2015—nearly two years after the implementation of phase 1.
Recommendations
BRN
To ensure that BRN has adequate data to effectively use its
resources and manage its workload, it should do the following:
• Formally track and monitor the timeliness of its processing of
applications by type and the cause of any delays.
• Formally track and monitor its pending workload of applications
by type and original receipt date.
• Conduct an analysis no later than June 30, 2015, of its application
processing since implementing BreEZe in order to identify the
workload capability of each of its units, such as the licensing
support unit; to the extent it determines additional resources are
necessary, BRN should submit a request for these resources that
is appropriately justified.
To ensure that BRN continues to process applications within
regulatory time frames, it should continue its efforts to refine its
business processes to increase efficiency and reduce the amount of
time applications are pending its review.
California State Auditor Report 2014-116 79
February 2015
Consumer Affairs
Consumer Affairs should continue to work with the phase 1
regulatory entities to ensure that the issues they are facing with
BreEZe are being resolved in a timely manner, with particular
attention to understanding their reporting needs and improving the
system’s reporting capabilities.
To ensure that future training for BreEZe system rollouts is timely
and effective, Consumer Affairs should:
• Provide training on the BreEZe system as close to the rollout
date as possible to ensure that staff retain the information for
using the system as it is implemented.
• Work with the regulatory entities to develop training that is
specific to each entity’s business processes.
We conducted this audit under the authority vested in the California State Auditor by Section 8543
et seq. of the California Government Code and according to generally accepted government auditing
standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate
evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives
specified in the scope section of the report. We believe that the evidence obtained provides a
reasonable basis for our findings and conclusions based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
Date: February 12, 2015
Staff: John Billington, Audit Principal
Laura G. Kearney
Myriam K. Czarniecki, MPA, CIA
Sean D. McCobb, MBA
Charles H. Meadows III
Derek J. Sinutko, PhD
IT Expert: Catalysis Group
Legal Counsel: Joseph L. Porche, Staff Counsel
For questions regarding the contents of this report, please contact
Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
80 California State Auditor Report 2014-116
February 2015
Blank page inserted for reproduction purposes only.
California State Auditor Report 2014-116 81
February 2015
Appendix
SUMMARY OF SIGNIFICANT BREEZE PROJECT CONCERNS
NOTED BY INDEPENDENT OVERSIGHT REPORTS,
DECEMBER 2010 THROUGH SEPTEMBER 2014
As explained in the Introduction, the California Department of
Technology (CalTech) is required to perform oversight
of information technology (IT) projects. This consists mainly of
two types of independent oversight: independent verification and
validation (IV&V)—used to ensure that software conforms to
requirements and satisfies user needs—and independent project
oversight (IPO)—used to ensure that effective project management
practices are in place and in use. On the BreEZe project, which
CalTech acknowledges is large, complex, and costly, its own
specialist provided IPO services whereas it contracted with
MetaVista Consulting to provide IV&V services. During the course
of the BreEZe project, the IV&V consultant and the IPO specialist
produced monthly reports to document their findings regarding
the project. Our IT expert reviewed these reports and produced
a table summarizing nearly 180 of the most significant concerns
that the IPO specialist and the IV&V consultant reported since
they began providing oversight on the project in December 2010
and January 2011, respectively. Table A beginning on the following
page presents these concerns and categorizes them according to
one or more of the key project oversight areas under which they
fall, such as project management and the contract. We describe in
Chapter 1 some of the significant and persistent concerns the IV&V
consultant and the IPO specialist raised.
82 California State Auditor Report 2014-116
February 2015
A
elbaT
stropeR
thgisrevO
tnednepednI
yb defiitnedI
snrecnoC
tcejorP
eZEerB
tnacfiingiS
fo
yrammuS
4102
rebmetpeS
hguorhT
0102
rebmeceD
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
x
gnirud
defiidom yllaitnatsbus erew
stnemeriuqeR
tcejorP
tnednepednI
0102
rebmeceD
.0102 rebmevoN
ni weiver
rodnev
)OPI(
thgisrevO
x
x
x
x
.stnemeriuqer fo ytilauq
eht htiw
seussI
x
ni detadpu dna detaerc
retrahc
tcejorP
OPI
1102
yraunaJ
no
noitamrofni evah ton seod
0102 rebmetpeS
litnu tiaw
ot stnaw eZEerB dna ,ecnanrevog
tcejorp
ecnanrevog
tcejorp a etaerc ot
esahp ngised
eht
ksir rojam
a setaerc siht taht setacidni
OPI
.erutcurts
.yletaidemmi desserdda
eb dluohs
dna
x
x
x
ecnamrofrep
metsys dna erutcetihcra
taht
snrecnoC
OPI
.denfied yletauqedani
erew
x
x
x
dna egatrohs
ffats ot del ezeerf gnirih
taht
snrecnoC
OPI
yeht
hcihw rof sksat gnimrofrep
maet ni
detluser
.gniniart ro lliks
tneicffiusni
dah
x
x
x
ot deriuqer
level lliks eht ssessop
ton seod
tcejorP
OPI
ezis siht
fo tcejorp a rof eludehcs etauqeda
na
dliub
.ytixelpmoc
dna
x
x
.coh-da era sessecorp tnemeganam
tcejorP
OPI
x
.gnippils
si
eludehcS
OPI
x
x
x
x
detamitserednu
evah ot sraeppa
maet
tcejorP
OPI
.ytixelpmoc
tcejorp
x
x
x
noitamrofni detimil tuoba
snrecnoc
desiaR
noitacfiireV
tnednepednI
tcejbus
ytiruces dna lacinhcet
)TI( ygolonhcet
)V&VI(
noitadilaV
dna
gnirud
tupni dna noitapicitrap
trepxe
rettam
.stnemeriuqer
fo tnempoleved
x
x
x
x
ton seod
maet tcejorp eZEerB eht
taht denrecnoC
V&VI
eht etelpmoc
ot secruoser defiilauq
tneicffius
evah
.daeha
krow
California State Auditor Report 2014-116 83
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
reganam egnahc
lanoitazinagro na rof noisivorp oN
OPI
1102
yraurbeF
.tropeR
ydutS ytilibisaeF eZEerB eht ni
x
x
x
x
ytilanoitcnuf
)PFR( slasoporp rof tseuqer eZEerB
OPI
sdeen laudividni
eht sserdda yletauqeda ton seod
dna senibmoc
ylpmis tI .uaerub ro draob yna fo
dna sdraob lla rof
stnemeriuqer fo tesrepus a setaerc
.enilesab
a sa etauqedani ti gnikam suaerub
x
x
x
a sa stnemeriuqer
PFR sefiitnedi tnemssessa ksiR
V&VI
.ksir fo ecruos
x
x
x
’sriaffA remusnoC
fo tnemtrapeD ainrofilaC ehT
V&VI
ksir eht rof pets
noitagitim tsrfi )sriaffA remusnoC(
htiw ecneirepxe
tnecer fo kcal a htiw detaicossa
noitatnemelpmi
dna noitisiuqca metsys egral
na edulcni ot
rodnev gninniw eht eriuqer ot saw
.dib
sti ni reganam tcejorp decneirepxe
x
x
seigolonhcet htiw
ecneirepxe evah ton seod maeT
V&VI
.noitulos laitnetop htiw detaicossa
x
x
etad fo tuo
si noitatnemucod ecafretni tnerruC
V&VI
rof desu dohtem
tnerruc ehT .etelpmocni dna
.etairporppani
si secafretni eht gnitnemucod
x
x
x
x
x
tcejorp decneirepxe
dna elbaegdelwonk fo kcaL
V&VI
regnol ehT
.nrecnoc rojam a era secruoser ffats
eht retaerg eht
,desserdda gnieb tuohtiw seog siht
ro enod eb ton
lliw sksat yrassecen taht doohilekil .tcejorp eht ot etauqeda eb ton lliw
x
x
.eludehcs dniheb
gninnur puorg ]sisylana[ ecafretnI
OPI
1102
hcraM
x
.gnilbuort era secitcarp
tnemeganam eussi dna ksiR
V&VI
x
x
x
x
eludehcs tcejorp
eht netaerht secruoser tneicffiusnI
OPI
1102
lirpA
esuaceb tsoc desaercni
ni tluser lliw dna yltnacfiingis
.egaugnal
tcartnoc revo snoitaitogen fo
x
x
x
x
era stnemeriuqer
taht rucnoc V&VI dna OPI
OPI
.)elbatsetnu ,etelpmocni
,suougibma( etauqedani
x
x
gnikat yb stsoc
rewol ot skees sriaffA remusnoC
OPI
1102
yaM
etipsed ,tnempoleved
ecafretni rof ytilibisnopser
.esitrepxe
fo kcal dna egatrohs ecruoser
x
x
x
tub tsixe sdradnats
gnireenigne erawtfos taht setoN
V&VI
.dewollof gnieb ton era
. . . egap
txen
no
deunitnoc
84 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
gniniatbo syaled tnacfiingis gnicneirepxe si tcejorP
OPI
1102
enuJ
.slavorppa ytitne yrotaluger
x
x
x
x
naht eludehcs evissergga erom a sesoporp rodneV
OPI
sriaffA remusnoC dna detseuqer sriaffA remusnoC sgnidnfi OPI dna V&VI etipsed eludehcs taht stpecca decneirepxe dna delliks fo srebmun tneicffiusni no sriaffA remusnoC fo noisnapxe na dna secruoser no gnikat sriaffA remusnoC morf gnitluser epocs eht ni ecirp rodnev ecuder ot krow lanoitidda .noitaitogen tcartnoc
x
.deganam ylevitceffe gnieb ton era sksiR
V&VI
x
x
x
.dewollof gnieb ton si ssecorp tnemeganam egnahC
V&VI
x
x
x
remusnoC eht taht nrecnoc desserpxe sah V&VI
OPI
1102
yluJ
ot ecneirepxe yrassecen eht skcal maet TI ’sriaffA remusnoC taht won metsys desoporp eht niatniam desuoh hceTO morf egnahc ot esohc sriaffA si taht eno ot noitarugfinoc erawtfos/erawdrah hcihw( retneC ataD detaredeF eht ni deganam eht ni lortnoc sriaffA remusnoC erom swolla .)sehctap fo tnemeganam
x
x
x
x
ton era sessecorp tnemeganam noitarugfinoC
OPI
na eb ot mees ton seod erehT .defiitnedi ylraelc evah stnemucod hcihw enimreted ot yaw suoivbo .devorppa yllamrof neeb
x
x
x
era stnemeriuqer ssenisub dna lacinhcet deliateD
OPI
.PFR eZEerB eht ni dedulcni ton
x
x
dna nalp tnemeganam tsoc a evah ton seod tcejorP
OPI
on si erehT .ecalp ni eno tup ot snalp evah ton seod .gnitroper tsoc
x
x
x
x
x
gnisu stnemeriuqer gninfier neeb sah maet eZEerB
OPI
DFR esuaceb ;)sDFR( smargaid wofl stnemeriuqer rodnev eht ,tcartnoc eht fo trap ton era stnemucod .noitatnemucod eht esu ot deriuqer ton
si
x
x
detaicossa era sksir defiitnedi fo rebmun egral
A
V&VI
1102
tsuguA
tneuqesbus dna PFR eht ni stnemeriuqer eht htiw suoires tuohtiw deretla eb tonnac dna tcartnoc .tnemerucorp eht ot stcapmi evitagen
x
x
x
lanoitazinagro ’sriaffA remusnoC tuoba snrecnoC
V&VI
dna dehsilbatse fo kcal eht ot detaler ,ytirutam .metsys TI na gniniatniam rof ,sessecorp detnemucod
California State Auditor Report 2014-116 85
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
gninnur si gninnalp tnemeganam
tcejorp stropeR
V&VI
.eludehcs dniheb
x
x
gnitnemucod ot hcaorppa
na sesu tcejorP
V&VI
retaerg a ni tluser lliw seveileb
V&VI taht secafretni
ecafretni eht ngiseder ot
troffe
gnireenigne-er .eZEerB
rof
x
x
gnieb noitatnemucod ecafretni
taht setaretier
V&VI
OPI
1102
rebmetpeS
ot desu dohtem eht dna etelpmocni
si decudorp
.etairporppani si secafretni
eht tnemucod
x
x
x
x
x
x
ytiliba eht skcal sriaffA remusnoC
taht denrecnoC
V&VI
1102
rebotcO
eht ni tnetnoc derised
enfied
dna yfitnedi
ot
era taht )sDED( stnemucod noitatcepxe
elbareviled
.rodnev eht
htiw
detaitogen gnieb
x
x
x
x
selbareviled fo noitpircsed )WOS(
krow fo tnemetatS
V&VI
rof elbisnopser si sriaffA
remusnoC
dna roop
si
hcae ni dedulcni eb dluohs
tahw
yltcaxe gninfied .elbareviled
x
x
x
.evissergga
si eludehcs eZEerB
OPI
1102
rebmevoN
x
x
rodnev neewteb sgniteem
gnirud
taht sevresbO
V&VI
evah ffats ’sriaffA remusnoC
,sriaffA
remusnoC
dna
”.gnihsarht“ fo tnuoma
tnacfiingis
a deyalpsid
neewteb snoissucsid htrof-dna-kcab
snaem
sihT
yllaunitnoc ni tluser taht
ffats
’sriaffA remusnoC
ot edam sdeen rodnev eht taht
noisiced a gnignahc
.tnempoleved
htiw eunitnoc
x
x
x
x
x
)erutneccA( s’PLL erutneccA
,WOS
eht ot gnidroccA
V&VI
nalP tnempoleveD dna
noitarugfinoC
metsyS
erawtfos sti ebircsed
dluohs
)ygolodohtem(
gnidrocca ,revewoH .)CLDS(
elcycefil
tnempoleved
eht ,DED devorppa-sriaffA
remusnoC eht
ot
sessecorp CLDS edulcni
ton
lliw ygolodohtem
noisulcxe eht ni gnitluser( esahp
dliub eht dnoyeb
ecnanetniam dna ,noitatnemelpmi
,gnitset eht
fo
rof noitpircsed ehT .)sesahp
snoitarepo
dna
ni dedulcni eb ot era
sesahp
gniniamer
eht
,V&VI eht ot gnidroccA .selbareviled
tneuqesbus
dezingocer lla htiw tciflnoc tcerid
ni si hcaorppa
siht
.sdradnats yrtsudni
x
x
.secruoser ecnarussa ytilauq
etis-no
on sah rodneV
V&VI
. . . egap
txen
no
deunitnoc
86 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
x
x
ton
PFR morf stnemeriuqer lanoitcnuf setoN
OPI
1102
rebmeceD
yrotaluger
yna rof txetnoc ssenisub ni defiiceps
ytilanoitcnuf
deriuqer eht ,erofereht ,dna ytitne
ton
saw seititne yrotaluger eht ot cfiiceps .denfied ylraelc
x
x
x
enilesab
morf( ni htnom eno si tcejorp eht setoN
OPI
.eludehcs
dniheb shtnom owt dna )eludehcs
x
x
x
x
x
neeb
evah taht snalp tnemeganam tcejorP
V&VI
,tsom
ton fi
,ynaM .dewollof gnieb ton era devorppa
fo
edistuo
rucco seitivitca tnemeganam tcejorp
sloot
tnemeganam
tcejorP .sessecorp denfied eht
,ksir ,egnahc
sa hcus( snalp devorppa eht ni denfied
eht
retfa
detatonna era )sgol eludehcs dna ,eussi .lla ta ton ro tcaf
x
x
x
x
x
x
rodnev
gniweiver ton si sriaffA remusnoC
V&VI
selbareviled
eht ot gnidrocca selbareviled
selbareviled
,yllanoitiddA .ssecorp tnemeganam
sevresbo
V&VI .etar hgih a ta detcejer gnieb era
neewteb
spag tnacfiingis neeb evah ereht
tA
.snoitatcepxe
s’rodnev dna ’sriaffA remusnoC
yltnacfiingis
saw elbareviled dettimbus eno tsael
tnetnoc
deriuqer
eht teem ton did dna etelpmocni .DED eht fo
x
x
x
x
x
eht
dlosrevo
evah yam erutneccA taht raelc si tI
OPI
2102
yraunaJ
.egats
tnemerucorp eht ta loot etargiM asreV
naht
regral eb lliw troffe noisrevnoc atad ehT
sa
pleh
ton yam sloot detamotua dna detcepxe .detapicitna sa hcum
x
x
x
x
x
x
stnemeriuqer
sti ni yticfiiceps skcal sriaffA remusnoC
OPI
yaled
dluoc
sihT .PFR eht ni deman stroper eht rof .stsoc lanoitidda ot dael dna tcejorp eht
x
x
eht htob
morf
syaled fo degreme sah nrettap raelc A
OPI
.sriaffA remusnoC dna rodnev
x
x
x
x
x
lanretxe
dna
lanretni tsubor a si ereht stressa rodneV
OPI
fo tsom
fo
weiver a tub ,ssecorp ecnarussa ytilauq
gnikrow
ton
si ssecorp eht tseggus selbareviled eht
.yttops
tseb ta si ssecorp eht ot ecnerehda ro
x
x
x
x
x
lliw
dna
tsisrep seussi ytilauq elbareviled rodneV
OPI
.syaled eludehcs ot dael ylekil
California State Auditor Report 2014-116 87
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
x
x
eht wohs
ot dednetni
era hcihw ,stroper
elfiorP
OPI
,ytitne yrotaluger
hcae rof
stnemeriuqer
lanoitcnuf
lliw yeht
sraeppa ti ,rehtruF
.etelpmoc
morf raf era
.snoitareti
lanoitidda
ot tcejbus eb
x
x
x
.gnippils
eludehcs
swohs sisylana
eludehcS
V&VI
x
x
x
x
x
dna
llew gnikrow
ton si ssecorp
elbarevileD
V&VI
,sweiver
elpitlum deriuqer
evah selbareviled
tsom
.snoissimbuser
dna ,setadpu
x
x
x
.eludehcs
dniheb
si tcejorP
OPI
2102
yraurbeF
x
x
x
x
x
tsissa
ot sriaffA remusnoC
no gninael
si rodneV
OPI
.selbareviled
htiw
x
x
x
x
x
x
tnacfiingis
deriuqer
evah selbareviled
ynaM
OPI
rof rodnev
eht ot kcab
tnes erew
dna snoisiver
eludehcs
dna ecruoser ni
detluser sah
sihT .krower .smelborp
x
x
x
x
x
gnieb era
sksat etelpmocni
taht ecnedive
si erehT
OPI
.etelpmoc
dekram
x
x
x
x
yam stroper
elfiorp ytitne
yrotaluger
etelpmocnI
OPI
ni ecnedfinoc
esol ot ffats
ytitne yrotaluger
esuac
eht fo ecnatpecca
llarevo
gnizidrapoej
,metsys eht
si ksir siht
sserdda ot nalp
ehT .metsys
detelpmoc
tcudnoc ot
dne kcab eht no
emit lanoitidda
wolla ot
.snoisses
no-wollof
x
x
x
x
x
tnecrep 06
revo swohs eludehcs
rodnev
fo sisylanA
V&VI
.citsilaernu
si eludehcs eht—kcals
orez
evah sksat fo
x
x
x
x
od setadpu
nalp krow desoporp
eht
taht nrecnoC
OPI
2102
hcraM
eht ,elpmaxe
roF .eludehcs
llarevo
eht tfihs ton
3 esahp dna
2 esahp rof setad
noitatnemelpmi
lanfi
palrevo
eht esaercni segnahc
ehT .egnahc
ton did
gnisserdda
tuohtiw 2 esahp
dna 1 esahp
neewteb
.nalp ni seussi
larutcurts
x
x
x
x
sessecorp
ot gnirehda
ton si sriaffA
remusnoC
OPI
.snalp
devorppa sti
ni debircsed
x
x
x
gnisnaelc
atad rof elbisnopser
si sriaffA
remusnoC
V&VI
si rodneV
.atad htiw seussi
sefiitnedi
rodnev retfa
seussi yfitnedi
ot stroper
yrassecen gnitareneg
ton
.eludehcs
ot gnidrocca
x
x
x
.deweiver erew
snoitacfiiceps
ecafretnI
V&VI
ecafretni
eht tahw fo sliated
skcal noitatnemucoD
nI .noitcnuf
taht mrofrep
lliw ti woh
dna od lliw
eht fo
selur ssenisub eht
fo sisylana
na ,noitidda
.detnemucod
ton saw smetsys
ycagel
. . . egap
txen
no
deunitnoc
88 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
1 esahp
dna nalp krow enilesab
neewteb
paG
OPI
2102
lirpA
.worg ot seunitnoc etad
noitatnemelpmi
x
x
x
x
x
ot gnihtyreve
seriuqer nalp krow
rodnev
detadpU
OPI
sihT .eludehcs
no yats ot tcejorp
eht
rof thgir og
doog
ton si hcihw ,oiranecs esac
tseb
a semussa
.gninnalp
tcejorp
x
x
x
x
x
dettimbus
saw taht elbareviled ngised
deliated ehT
V&VI
ssenetelpmoc
fo kcaL .DED htiw
tnetsisnocni
si .tnerappa si
x
x
x
x
x
deraperp
gnieb era stpircs gnitset
ecnatpecca
resU
V&VI
.srekrow
emit-trap fo maet deffatsrednu
na yb
x
x
x
x
.etelpmocni
era stpircs gnitset metsys
taht
snrecnoC
V&VI
x
x
x
x
gnirud
defiitnedi smelborp emos
taht
ecnedivE
OPI
.devlosernu
niamer tolip moor
ecnerefnoc
eht
era seussi
rieht taht denrecnoc seititne
yrotalugeR
.desserdda
gnieb ton
x
x
gnffiats
si sriaffA remusnoC yaw
eht
fo esuaceB
OPI
eht deecxe
ylekil lliw ti ,gnitset
ecnatpecca
resu
.detacolla
emit
x
x
x
x
)hceTlaC(
ygolonhceT fo tnemtrapeD
ainrofilaC
OPI
snrecnoc
fo esuaceb devlovni
gnitteg
si hceTlaC
.ytilauq
rodnev
tuoba
x
x
x
x
x
.seussi
ytilauq rof eciwt detcejer
ngised
deliateD
OPI
2102
yaM
x
x
si ereht
dna ,eludehcs dniheb
sniamer
tcejorP
OPI
.emoc ot syaled lanoitidda
fo ecnedive
x
.tcejorp
eht no tcapmi na evah
lliw
shguolruF
OPI
x
x
x
ron nalp eht
wollof ton ot seunitnoc
noisrevnoc
ataD
V&VI
.emit
no ydaer eb ot yrassecen
ssergorp
ekam
x
x
x
gnitset ecnatpecca
resu gniyfidom
sriaffA
remusnoC
V&VI
.stpircs
tset metsys detaerc-rodnev
erom esu ot
x
x
x
x
x
x
tuohtiw
tset metsys gnitrats setapicitna
rodneV
V&VI
.nalp
tset sti ni deniltuo airetirc
eht gniteem
x
x
x
x
x
x
elfiorp
cireneg ot decart gnieb
era stnemeriuqeR
V&VI
fo stnemeriuqer
lanoitcnuf cfiiceps
ot
ton ,stroper
.seititne
yrotaluger
eht
California State Auditor Report 2014-116 89
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
degdelwonkca reganam tcejorp eZEerB eht setoN
OPI
2102
enuJ
ytiliba ezidrapoej ot gninnigeb si erusserp ecruoser .tcudorp ytilauq a reviled
ot
x
x
x
x
.nalp tnemeganam egnahc gniwollof ton llits tcejorP
V&VI
x
x
x
x
x
x
dna gniman etaerc ot desoppus saw tcejorp ehT
V&VI
.deneppah ton sah siht dna ,sdradnats gnidoc
x
x
x
x
x
x
,gnitset metsys ni ssergorp rodnev tneicffiusnI
OPI
2102
yluJ
stekcit nepo fo rebmun egral yb dewols .)stcefed 008(
x
x
x
ot elbatsnu oot sniamer tnemnorivne lacinhcet ehT
OPI
.gnitset ecnatpecca resu nigeb
x
x
x
eZEerB eht ,shtnom eerht tsal eht fo esruoc eht revO
OPI
2102
tsuguA
eludehcs eht nalp-er ot dah sah maet tcejorp ot detcelgen evah yam yeht ylekil si ti ;semit eerht .sksat gnidnatstuo lla fo sisylana hguoroht a tcudnoc
x
x
x
x
x
etelper“ ti sdnfi ngised deliated fo weiver V&VI
OPI
”.sgnimoctrohs htiw
x
x
x
x
1 esahp no sucof ot stroffe 2 esahp sesuap rodneV
OPI
.elbatsnu oot si 1 esahp esuaceb
x
x
x
x
x
x
x
ssenisub deriuqer yfirev ton lliw tset metsyS
OPI
2102
rebmetpeS
ytilanoitcnuf ssenisub srefed rodneV .ytilanoitcnuf resu gnirud sriaffA remusnoC ot noitamrfinoc .gnitset ecnatpecca
x
x
x
x
x
x
tset evah ton od sesac tset metsys fo rebmun
A
OPI
si ereht dna drocer noitucexe tset a ro stpircs nwo sti gniwollof ton si rodnev eht ecnedive .nalp tset
x
x
x
x
x
eht lortnoc ylluferac ot sdeen sriaffA remusnoC
OPI
seititne yrotaluger eht yb segnahc detseuqer segnahc evah-tsum eht ylno taht erusne
ot
.gnitset ecnatpecca resu tixe ot deriuqer era eb dluoc gnitset ecnatpecca resu ,esiwrehtO .yletinfiedni degnolorp
x
x
,skeew xis rof deludehcs yllanigiro ,tset metsyS
OPI
2102
rebotcO
.shtnom xis retfa gniogno sniamer
x
x
x
morf nalp krow tfard ni sesaercni krow gniniameR
OPI
fo sa sruoh 554,03 ot 21 rebmetpeS no sruoh 527,71 .61 rebotcO
x
x
x
x
x
x
x
22 fo 01 dnuof ecart stnemeriuqer fo tiduA
OPI
.detsil esac tset eht yb defisitas ton stnemeriuqer
. . . egap
txen
no
deunitnoc
90 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
x
x
nalp krow
dna elbareviled gniniart resu lanretnI
OPI
ot eud
rodnev ot denruter elbareviled enilesab
deunitnoc fo
noitacidni na si hcihw ,seussi larutcurts .smelborp ytilauq
x
x
x
x
kcal a ot ecart
gnitset gnirud defiitnedi gnieb seussI
V&VI
fo noitatnemelpmi
eht rof stnemeriuqer enilesab
fo
.seititne
yrotaluger ot cfiiceps ytilanoitcnuf
x
x
x
x
x
x
x
enilesab tuohtiw
devorppa ngised metsys deliateD
V&VI
taht ksir
tnacfiingis stneserper—stnemeriuqer .ytilibaecart dna gnitset stceffa
x
x
x
x
x
x
gnidnatstuo
286,1 htiw detixe tset metsyS
V&VI
2102
rebmevoN
erofeb
desolc eb tsum taht stnedicni/stcefed .noitatnemelpmi 1 esahp
x
x
x
x
x
x
x
1 ytiroirp fo
erusolc refed ot deerga sriaffA remusnoC
V&VI
.tixe tset
metsys wolla ot stcefed 2 ytiroirp dna
x
x
x
x
x
x
286,1
htiw deretne si gnitset ecnatpecca resU
V&VI
.stcefed gnidnatstuo
x
x
x
krow fo tnecrep
57 dewohs nalp krow rebmetpeS
OPI
2102
rebmeceD
.tnecrep
36 swohs nalp krow rebotcO .etelpmoc .tnecrep 57 swohs nalp krow rebmeceD
x
x
x
x
x
gnitcapmi
gnitset fo kcal ot detubirtta smelborP
OPI
.gnitset ecnatpecca resu
x
x
x
x
x
x
si erawtfos
ytilauq roop stroper sriaffA remusnoC
OPI
.syaled
gnitset ecnatpecca resu ot gnitubirtnoc
x
x
fo
dne eht ta gol eht ni stcefed nepo 402,2
V&VI
.2102 rebmeceD
x
x
x
x
tcejorp—stcefed
ot eud etar eruliaf tset hgiH
OPI
3102
yraunaJ
tnerruc ;etar
eruliaf ssap tsrfi tnecrep 02 detcepxe
etar
eruliaf ssap dnoceS .tnecrep 16 si etar .tnecrep 56
si
x
x
x
x
era taht stnemeerga
lautum ot gnitroser era smaeT
OPI
.gnidnib yllautcartnoc ton
x
x
sa noitapicitrap
ytitne yrotaluger ni pord suotipicerP
OPI
.etamitse
sti sdeecxe gnitset ecnatpecca resu
x
x
x
x
esu eht ni
deniart ton erew strepxe rettam tcejbuS
OPI
dna elbuod
ni gnitluser si hcihw ,loot gnitset eht
fo
.yrtne atad elpirt semitemos
California State Auditor Report 2014-116 91
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
x
x
x
tnemeganam
sriaffA remusnoC ,3102 ,11 yraunaJ nO
OPI
dna reganam tcejorp rodnev ot rettel a deussi sriaffA remusnoC ,rettel eht nI .tnemeganam
ot
deriuqer saw rodnev taht smeti fo ynatil a detats
hcihw
,gnitset ecnatpecca resu gnidulcni ,etelpmoc
yeht
taht saw esnopser rodneV .gnidnatstuo niamer
,eludehcs
”deerga yllautum“ eht ot gnimrofnoc erew eht—”eludehcs lautcartnoc“ eht ton si hcihw .nalp krow devorppa yllamrof dna enilesab
x
x
x
,rotargetni smetsys eht neve ton ,eno on . . .“
OPI
3102
yraurbeF
xelpmoc siht eb dluow eZEerB dezilaer dah ”.tnemelpmi ot
x
x
x
x
detcepxe na susrev tnecrep 13 si etar liaf/xfi ehT
OPI
.tnecrep 5
x
x
x
x
.tnecrep 81 etar liaf tseteR
OPI
3102
hcraM
x
x
x
lliw
seitud snoitarepo dna ecnanetniam woh raelcnU
OPI
.sriaffA
remusnoC dna rodnev neewteb detacolla eb
x
x
x
x
x
x
x
x
ecnatpecca resu ot trats etal a fo tnemssessA
V&VI
enilesab on ,snoitarud ksat citsimitpo—gnitset noitatnemelpmi deyaled/wols ,stnemeriuqer fo flehs-eht-ffo laicremmoc fo noitarugfinoc dna ot tset metsys fo epocs eht gniworran ,stcudorp
ton
,stnemeriuqer tcartnoc ]level-hgih[ mrfinoc ylno
remusnoC
.stnemeriuqer cfiiceps-ytitne yrotaluger
resu
trats ot gniyrt ylevissergga rodnev dna sriaffA
remusnoC
.elbissop sa noos sa gnitset ecnatpecca
egarevel
lautcartnoc eht evah ton did ti tlef sriaffA etipsed trats gnitset ecnatpecca resu yaled ot
ytilauq
roop stressa sriaffA remusnoC .seussi ytilauq ecnatpecca resU .tset otni dereviled stcudorp —yrtne ta etelpmoc ton saw gninnalp gnitset on ,stpircs gnitset ecnatpecca resu enilesab on .stnemeriuqer enilesab
x
x
x
x
x
erew
taht stnemele hcihw ta etar eht ,etar liaf/xfi ehT
OPI
3102
lirpA
yletamixorppa
saw ,tset-er a deliaf dexfi sa defiitnedi .tnecrep 52
x
x
x
x
x
x
metsys ylno ,evil-og ta taht detats sah rodneV
OPI
”,stekcit tcefed“ ro ,)sRIS( stseuqer noitagitsevni dexfi eb lliw niamod s’rodnev ni eb ot deredisnoc stnemecnahne deredisnoc stcefeD .tsoc on ta tcartta lliw niamod ’sriaffA remusnoC nihtiw ro htiw gnikrow sriaffA remusnoC .stsoc lanoitidda remusnoC“ setutitsnoc tahw yfiralc ot tinu lagel ”.niamod ’sriaffA
. . . egap
txen
no
deunitnoc
92 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI
FO
YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
refed ot dezitiroirper
gnieb
era sRIS taht setoN
V&VI
3102
yaM
.noitatnemelpmi 1 esahp
retfa litnu
noitca evitcerroc
x
x
x
ton od seititne yrotaluger
taht denrecnoc
si rodneV
V&VI
detceffa eb lliw sessecorp
ssenisub
rieht woh wonk .eZEerB
yb
x
x
x
roirp on sah reganam
tcartnoc
’sriaffA remusnoC
OPI
3102
enuJ
.reganam
tcartnoc
a sa ecneirepxe
x
.enuJ ot yaM morf
sesaercni
sRIS
nepo fo rebmuN
V&VI
x
x
x
taht raelc edam sah
evitucexe
deddebme-rodneV
OPI
3102
yluJ
rehtruf tuohtiw 1
esahp
yolped
ot si etadnam
sih
.yaled
x
x
x
x
erofeb tixe ot tset metsys
dewolla
sriaffA remusnoC
OPI
.tem saw
noiretirc tixe
eht
x
x
x
x
x
x
x
erew stnemeriuqer ecnamrofrep
taht stressa rodneV
OPI
saw ti nehw nalp erutcetihcra
lacinhcet
yb defiidom
OPI .seergasid V&VI
.sriaffA
remusnoC
yb detpecca
siht tnemucod ot tcejorp
eht degaruocne
tnatlusnoc
.tey detnemucod
neeb
sah ti
noitacidni on ;eussi
x
x
x
x
x
htiw gnitset noisserger
retne
ot seerga tcejorP
OPI
3102
tsuguA
eb dluow deerga ylsuoiverp
erew
taht sRIS nepo
88
.dliub
lanfi erofeb desolc
x
x
x
x
x
yltnacfiingis slaog/hcaorppa
gnitset
ecnamrofreP
V&VI
sriaffA remusnoC“
ot liaf/ssap
morf defiidom
skramhcneb eht taht
denrecnoc
V&VI ”.elbatpecca
eb ton yam
nosirapmoc
erutuf rof nesohc
.sdeen ssenisub ’sriaffA
remusnoC
fo evitatneserper
x
x
x
x
x
x
era taht selbareviled
detpecca
sah
sriaffA remusnoC
V&VI
3102
rebmetpeS
.tcerrocni
dna
,tnetsisnocni
,etelpmocni
x
x
x
x
dah V&VI detressa
tsilkcehc
gnitset
ecnamrofreP
V&VI
taht dna ton did eh
syas
V&VI
.stluser eht defiirev
.eslaf
si noitressa
eht
California State Auditor Report 2014-116 93
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
x
x
x
ot eerga yllautum rodnev dna sriaffA remusnoC
OPI
3102
rebotcO
.derrefed eb ot sRIS 610,1 htiw tnemelpmi
x
ekat ot detamitse gnitset ecnatpecca resu 1 esahP
V&VI
.syad krow etats 112 sekat yllautca ,skeew
8
x
x
x
x
x
x
x
.sRIS nepo 610,1 htiw evil tnew 1 esahP
V&VI
x
x
x
x
x
x
x
litnu denilesab ton ytilanoitcnuf ssenisuB
V&VI
ot demrofrep saw ytilibaecart oN .3102 ,32 rebotcO rof stnemeriuqer lautcartnoc 087 eht taht mrfinoc oN .gnitset ecnatpecca resu yb detset erew 1 esahp 1 esahp lautcartnoc fo lla mrfinoc ot stsixe ecnedive .tem erew stnemeriuqer
x
x
x
x
x
x
.selbareviled rodnev htiw tsisrep seussi ytilauQ
OPI
3102
rebmevoN
x
x
x
x
x
x
no noitcudorp ni detroper si 10.1 esahP
V&VI
,3102 ,52 rebmevoN fo sa hguohtla ,3102 ,52 rebotcO sa defiitnedi erew taht nepo sRIS 13 era ereht saw tahw raelc ton si tI .10.1 esahp ot gnignoleb .esahp siht ni deriuqer yllautcartnoc
x
x
x
x
x
x
tcejorP laicepS fo lavorppa fo noitidnoc a sA
OPI
3102
rebmeceD
fo noitelpmoc deriuqer hceTlaC ,2 )RPS( tropeR erofeb nalp krow enilesab a dna ygolodohtem eht gnieb si tnemeriuqer taht tub ngised fo trats eht si ngised 2 esahp taht setamitse V&VI .derongi .etelpmoc tnecrep 06
x
x
x
s’rodnev eht taht snoitacidni ydaerla era erehT
OPI
.gnippils si eludehcs detadpu
x
x
x
x
fo emos ,stcefed 766,11 htiw pu dedne 1 esahP
OPI
.devloser tey ton era hcihw
x
x
x
x
x
lamrof“ sa sweiver lamrofni gnitaert si tcejorP
OPI
4102
yraunaJ
elbarevileD eht ni debircsed sa ”sweiver .nalP tnemeganaM
x
x
dengissa won reganam tcejorp ’sriaffA remusnoC
OPI
rotcerid tcejorp/reganam tcejorp fo elor laud eht eht taht snrecnoc seciov tnatlusnoc OPI .)DP/MP( mrofrep ot htdiwdnab eht evah ton seod DP/MP .ylevitceffe selor htob
x
x
x
x
,)1.2( elbareviled ygolodohtem tfard s’rodnev reP
OPI
syad 02 ylno sriaffA remusnoC wolla ot snalp rodnev htiw gnitset ecnatpecca resu fo ssap tsrfi eht rof seton OPI .noisserger rof edisa tes syad 01 rehtona dna 1 esahp htiw yrotsih eht nevig citsilaernu si siht esnecil erom tnemelpmi lliw 2 esahp taht tcaf eht .1 esahp naht sepyt
. . . egap
txen
no
deunitnoc
94 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
sexfi rof sRIS gningissa sriaffA remusnoC
OPI
ecnanetniam
diaperp eht yb derevoc yllamron(
)IDD(
tnemelpmi
dna poleved ,ngised ot )tcartnoc .tcartnoc tnemecnahne
x
x
x
mrofrep
ot
IDD gnisu taht seton tnatlusnoc OPI ehT
OPI
a si tcartnoc
eht fo epocs eht nihtiw ton si taht krow
.secitcarp
gnitcartnoc etats fo noitaloiv raelc
x
x
x
x
.)4102
,72 yraunaJ
fo sa( sRIS 003,1 yltnerruc era erehT
OPI
detluser
evah
evil-og retfa defiitnedi stcefed lacitirC
ta nepo
deniamer
taht stcefed fo noitazitiroirper
ni
ot
elba
ton si maet ecnanetniam rodneV .evil-og
ecap
eht
ta sdnamed ecnanetniam gniogno teem .seititne yrotaluger eht yb derised
x
x
x
x
x
sRIS
derrefed
sevom 051 )CFR( egnahC rof tseuqeR
V&VI
.IDD
ot etatS
eht ot tsoc on ta dexfi eb ot erew taht
x
x
x
eht ot gnirehda ton si tcejorP
V&VI
.ygolodohtem devorppa
x
x
x
x
x
x
x
gnitset
ecnatpecca
resu desoporp eht taht nrecnoC
V&VI
tneicffius
edivorp ton lliw ]2 esahp rof[ hcaorppa
evah
stnemeriuqer lla taht yfirev ot ecnegilid .dereviled neeb
x
x
x
x
x
x
etatS
eht
setacidni reganam tset ’sriaffA remusnoC
V&VI
ot gnitset
metsys s’rodnev eht nopu yler dluow
’sriaffA
remusnoC
eht fo lla taht noitacfiirev mrofrep .dereviled erew stnemeriuqer devorppa
x
x
x
x
x
rodnev
eht
eriuqer ton seod nalp tset devorppa ehT
V&VI
lla erussa
ot liated fo level yrassecen eht ta yfirev
ot
ti dna
tem
era stnemeriuqer level ngised devorppa
dessap
era
stset fi noinipo ’sretset rodnev eht eb lliw .)tnemevlovni sriaffA remusnoC tuohtiw(
x
x
x
x
x
x
si ygolodohtem
eht fo tnenopmoc ngised ehT
V&VI
esahp
ngised eht elihw yraunaJ ni desiver gnieb .gniogno
si
x
x
x
x
x
segnahc
dnuof tnemssessa tseuqer egnahC
V&VI
ot
segnahc
dna stnemucod denilesabnu tsniaga
.tcejorp
eht fo trap ydaerla saw taht epocs dda
senilesab
eht fo lortnoc ni ton si sriaffA remusnoC
ytilibaecarT
.segnahc devorppa eht tnemucod taht .tneicffiusni
si
California State Auditor Report 2014-116 95
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
eb ot eunitnoc
stnemecnahne dna stcefed eroM
OPI
4102
yraurbeF
.1 esahp tsniaga defiitnedi
x
x
x
x
ecruoser
fo esuaceb nwod gniwols 2 esahP
OPI
revo won era
ereht(
stcefed 1 esahp xfi ot noitcerider .)evil-og rebotcO ecnis sRIS 002,1
x
x
x
x
x
x
x
stnemeriuqer
eht devorppa sriaffA remusnoC
V&VI
tey gnivah
tuohtiw )MTR( xirtam ytilibaecart
MTR devorppa
ehT .ygolodohtem eht devorppa
si V&VI dna
,2 esahp
rof stnemeriuqer 56 sefiitnedi
rof stnemeriuqer
erom eb dluohs ereht denrecnoc .2 esahp
x
ni esaercni
laitnatsbus
a seveileb tnatlusnoc OPI
OPI
4102
hcraM
.3
esahp rof dedeen eb lliw secruoser
x
x
x
x
x
smaet rodnev
eht dna etats eht htob raelc si tI“
OPI
troffe ecnanetniam
fo level eht detamitserednu
dna
seititne
yrotaluger 1 esahp rof deriuqer
ni esahp
eht
rof stroffe ecnanetniam lanoitidda ”.deriuqer eb lliw noitcudorp
x
x
x
x
x
x
eb tsum stnemeriuqer
56 ylno taht stressa rodneV
OPI
4102
yaM
.)tcartnoc
ni 009,1 susrev( 2 esahp rof detset
x
x
tuoba nrecnoc
s’tnatlusnoc OPI eht ot esnopser nI
OPI
tnemecnahne
eht fo noitpmusnoc fo deeps eht
revo lortnoc
on sah
ti taht sdnopser tcejorp ,tegdub
.seititne yrotaluger
eht yb stseuqer tnemecnahne
x
lla rof lavorppa
enilesab
dna gninnalp fo noitelpmoC
OPI
4102
enuJ
lavorppa hceTlaC
fo noitidnoc a saw sesahp tcejorp
ton sah noitidnoc
siht tub ,3102 rebotcO ni 2 RPS fo .defisitas neeb tey
x
x
yb setamitse
deecxe
ot detcepxe era stsoc 2 esahP
OPI
fo noitrop
tnacfiingis
A .noillim 54$ ot noillim 23$
egnahc noitazinagro
dna secruoser tcejorp rof si siht
seod esaercni
tsoc sihT .lennosrep tnemeganam
era snoitacidni
lla
tub ,stsoc 3 esahp yna sserdda ton
.2 esahp
naht
erom neve tsoc lliw 3 esahp taht
. . . egap
txen
no
deunitnoc
96 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
emulov hgih eht lortnoc ot elbanu si tcejorp
ehT
OPI
stseuqer tnemecnahne ’seititne yrotaluger
fo
fo esuaceb tcartnoc ecnanetniam eht rednu yrotaluger eht fo erutan suomonotua-imes
eht
noitpmusnoc retsaf ni gnitluser si sihT .seititne tcejorp eht naht sdnuf ecnanetniam elbaliava
fo
eerged
eht etapicitna ton did tcejorp ehT .detcepxe yrotaluger eht htiw[ tnemngilasim noitatcepxe
fo
enilesab ot gniliaf morf tluser dluow taht ]seititne .ngised 1 esahp
eht
x
x
x
x
stsoc tcartnoc eZEerB eht fo noitanimaxe
nA
OPI
gnitroper esnepxe tcartnoc tcejorp taht swohs .etaruccani
si
x
x
x
sriaffA remusnoC“ ,maet tcejorp eht ot gnidroccA
OPI
tseuqer
suaerub dna sdraob eht tahw etatcid tonnac
erised
seititne yrotaluger eht fI .stnemecnahne
rof
sriaffA remusnoC ,stnemecnahne eht rof yap
ot
esuaceb sdnamed rieht etadommocca ot sdnet sekam hcihw ,erutan suomonotua-imes rieht
fo
tcejorp eht ,suhT .eussi eht ecrof ot tlucffiid
ti
ylno sdeen ’seititne yrotaluger ot egatsoh
si
”.secruoser elbaliava yb deniartsnoc
x
x
noitatnemelpmi 3 esahp rof stsoc tcejorp latoT
V&VI
.nwonknu niamer
x
x
x
x
x
eht yb detabrecaxe gnieb era seussi secruoseR
OPI
4102
yluJ
yb
depoleved eludehcs noitatnemelpmi evissergga .sriaffA remusnoC yb devorppa dna rodnev
eht
x
x
x
x
x
x
rodnev
eht no kcab gnihsup era seititne yrotalugeR
OPI
.ytilauq roop tuoba gninialpmoc dna elbatemit
x
x
x
x
x
egnahc lanoitazinagro gnirucorp ni syaleD
V&VI
eht ecuder yam secruoser )MCO( tnemeganam ngised eht erofeb emit gnidraob no dennalp MCO lla rof ytiliba eht timil yam hcihw ,tixe esahp 2 esahp eht yb detelpmoc eb ot selbareviled .etad tnemyolped
California State Auditor Report 2014-116 97
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI FO YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
x
x
htiw tcejorp
eht no noitirtta fo etar hgih a si erehT
OPI
4102
tsuguA
selor
wen gnimussa secruoser yek fo rebmun
a
remusnoC
eht nihtiw tcejorp eht ot detalernu
ssenisub
lareves ,yllanoitiddA .noitazinagro sriaffA
eht no
neeb osla evah )sAIB( stsylana noitargetni
snoitisop
emos effluhser ot tcejorp eht gnicrof evom
fo eno nI
.tcejorp eht no selor tnatropmi eseht llfi
ot
ot detcerider
saw reganam ytilauq eht ,sevom eht
tuoba snrecnoc
desiar OPI .AIB a fo elor eht emussa
dna gnikatrednu
si tcejorp eht taht nevig evom siht
lliw taht
selbareviled ngised yek lareves gniweiver .tcejorp eht no stcapmi gnitsal evah
x
x
x
remusnoC
,nalp ecnanetniam eht ot gnidroccA
OPI
rodnev
wodahs ot erew srebmem maet sriaffA revo ekat ot eraperp dna ffats ecnanetniam
dengissa
ton sah tcejorp ehT .ecnanetniam metsys
.refsnart
egdelwonk siht ni etapicitrap ot ffats yna
sriaffA
remusnoC fi laitnesse si siht seveileb OPI
2 esahp
fo dne eht ta ecnanetniam revo ekat ot
si
era
ffats sriaffA remusnoC esuaceb ,dennalp
sa
cilbup
siht troppus ot deraperp yltnerruc ton .metsys gnicaf
x
x
x
fo esuaceb
deyaled saw ngised smetsys deliateD
OPI
.noitnetnoc ecruoser ’seititne yrotaluger
x
x
ot dedeen
secruoser setanimile 3 RPS fo lawardhtiW
OPI
.ecnanetniam metsys gniogno troppus
x
x
x
x
yrassecen
secruoser setanimile 3 RPS fo lawardhtiW
OPI
.ygolodohtem
nopu-deerga ylwen eht troppus
ot
x
x
x
x
x
eht rehtie
no reganam ecnarussa ytilauq on si erehT
OPI
4102
rebmetpeS
.emit siht ta smaet rodnev ro etats
x
x
yrotaluger
dna tcejorp htob( sriaffA remusnoC
OPI
on htiw
lacitirc era stniartsnoc ecruoser )seititne .3 RPS fo lawardhtiw eht retfa thgis ni feiler
x
x
x
wodahs
ot enoyna dengissa ton llits sah tcejorp ehT
OPI
.maet ecnanetniam eht
. . . egap
txen
no
deunitnoc
98 California State Auditor Report 2014-116
February 2015
AERA
THGISREVO
TCEJORP
YEK
SMETSYS
TCEJORP
TCARTNOC
RODNEV
SECRUOSER
ELUDEHCS
EPOCS
GNIREENIGNE
TNEMEGANAM
YTILAUQ
STNEMERIUQER
EUSSI
FO
YRAMMUS
THGISREVO
FO
EPYT
ETAD
TROPER
x
x
sih
detatser
sah
rotcerid
tcejorp
eZEerB
ehT
OPI
secruoser
deriuqer
no gnirb
ot tnemtimmoc
si
tI
.eZEerB
tnemelpmi
yllufsseccus
ot
yrassecen
ni
detseuqer
secruoser
eht
fo ynam
woh
raelc
ton
.detiurcer
eb
nac
3 RPS
x
x
2
esahp
troppus
ot
secruoser
tcejorp
lanoitidda
ehT
V&VI
tcejorp
latot
desaercni
3
RPS
ni detalucitra
erew
taht
.noillim
811$
ot )2
RPS(
noillim
77$
morf
stsoc
tcejorp
42
lanoitidda
na
detroppus
gnidnuf
3 RPS
tnemeganam
egnahc
lanoitazinagro
,snoitisop
gnffiats
snoitarepo
dna ecnanetniam
,sdeen
detapicitnanu
eht
desaercni
dna
,sesaercni
eht
tuohtiW
.epocs
2 esahp
rof gnidnuf
ksat
sraeppa
ti
,3
RPS
ni desoporp
secruoser
lanoitidda
dluoc
sriaffA
remusnoC
taht
ylekilnu
ylhgih
2 esahp
hsilpmocca
ot
secruoser
tneicffius
tcerider
.slaog
tcejorp
.4102
rebmetpeS
hguorht
0102
rebmeceD
detad
tnatlusnoc
V&VI
dna
tsilaiceps
OPI
hceTlaC
eht yb
stroper
fo sisylana
s’trepxe
TI
s’rotiduA
etatS
ainrofilaC
ehT
:secruoS
California State Auditor Report 2014-116 99
February 2015
100 California State Auditor Report 2014-116
February 2015
California State Auditor Report 2014-116 101
February 2015
102 California State Auditor Report 2014-116
February 2015
California State Auditor Report 2014-116 103
February 2015
104 California State Auditor Report 2014-116
February 2015
California State Auditor Report 2014-116 105
February 2015
106 California State Auditor Report 2014-116
February 2015
California State Auditor Report 2014-116 107
February 2015
*
* California State Auditor’s comments begin on page 113.
108 California State Auditor Report 2014-116
February 2015
1
2
3
4
California State Auditor Report 2014-116 109
February 2015
110 California State Auditor Report 2014-116
February 2015
California State Auditor Report 2014-116 111
February 2015
112 California State Auditor Report 2014-116
February 2015
Blank page inserted for reproduction purposes only.
California State Auditor Report 2014-116 113
February 2015
Comments
CALIFORNIA STATE AUDITOR’S COMMENTS ON THE
RESPONSE FROM THE BOARD OF REGISTERED NURSING
To provide clarity and perspective, we are commenting on the
response to our audit report from the Board of Registered Nursing
(BRN). The numbers below correspond to the numbers we placed
in the margin of BRN’s response.
BRN misunderstood the information presented in Table 3 on 1
page 15, which is in the Introduction and not in Chapter 3 of our
report. Specifically, for each of the 37 boards, bureaus, committees,
and a commission (regulatory entities) that were originally
scheduled to implement BreEZe, Table 3 shows their respective
number of licensees. In the case of BRN, Table 3 shows that BRN
has 514,640 licensees. This amount is not limited to registered
nurse licensees, as BRN incorrectly understood; rather, it includes
other types of BRN licensees, such as nurse practitioners and public
health nurses.
We are perplexed as to why BRN is singling out certain application 2
types in its response, when the amount of all application types
pending its review is clearly a more accurate representation of
its pending workload. Specifically, BRN emphasizes that Table 8
on page 69 states that it only had 4,631 applications for initial or
renewal licensure, excluding initial international applications.
Although this number can be determined from the data in Table 8
by combining the first five types of applications listed, it is not
discretely presented. Furthermore, we clearly state on pages 63
and 68 that, as of September 2014, BRN was facing a significant
number of applications pending its review—more than 7,000—an
amount that includes all application types. Further, BRN incorrectly
states that Table 8 does not include initial international applications.
For presentation purposes, we included these applications in
Table 8 under the respective type of application the international
applicant submitted.
BRN is incorrect. Our report does not state that BRN overstates 3
its application processing times. Rather, on page 64, we conclude
that although BRN attributes its inefficiency in processing
applications to the implementation of BreEZe, we found it is unable
to substantiate such claims because it does not track the amount
of time it takes to process applications. Further, as we point out on
page 65, the BRN acknowledged in its 2014 Sunset Review Report
that the data in that report concerning application processing times
are in many instances “best estimates” and should be viewed with
caution, which would lead one to question the accuracy of the data.
114 California State Auditor Report 2014-116
February 2015
4 As we describe in Table 5 on page 21, objective 8 specifically
asked us to determine the average amount of time it took BRN to
process applications before and after the California Department of
Consumer Affairs implemented BreEZe. On page 66 we explain that
lacking sound data from BRN to substantiate its claims of increased
inefficiencies due to BreEZe, we conducted our own review of
selected license applications to obtain a sense of the impact BreEZe
has had on the efficiencies with which BRN processes applications.
For purposes of addressing the audit objective, we present the
results of our review of the selected license applications as averages.
California State Auditor Report 2014-116 115
February 2015
*
1
2
* California State Auditor’s comments begin on page 125.
116 California State Auditor Report 2014-116
February 2015
3
4
5
6
5 6
3 7
8
California State Auditor Report 2014-116 117
February 2015
9
118 California State Auditor Report 2014-116
February 2015
10
10
California State Auditor Report 2014-116 119
February 2015
10 11
10 12
120 California State Auditor Report 2014-116
February 2015
10
California State Auditor Report 2014-116 121
February 2015
10
10
122 California State Auditor Report 2014-116
February 2015
4
10
13
California State Auditor Report 2014-116 123
February 2015
4 14
10 15
10 16
124 California State Auditor Report 2014-116
February 2015
10 15
10 15
10
California State Auditor Report 2014-116 125
February 2015
Comments
CALIFORNIA STATE AUDITOR’S COMMENTS ON THE
RESPONSE FROM THE CALIFORNIA DEPARTMENT
OF TECHNOLOGY
To provide clarity and perspective, we are commenting on the
response to our audit report from the California Department of
Technology (CalTech). The numbers below correspond to the
numbers we placed in the margin of CalTech’s response.
CalTech incorrectly states that it has provided independent project 1
oversight (IPO) on the BreEZe project since inception of the
project. As we point out on page 40 of our report, CalTech did
not assign an IPO specialist to the project for over a year after it
approved the project’s Feasibility Study Report (FSR).
We disagree that our report does not recognize the current state 2
of BreEZe and therefore does not provide a clear picture of the
current status of the system. On pages 45 through 47 we provide
information on the current status of BreEZe, including that future
implementation of BreEZe by regulatory entities scheduled for
phase 2 of BreEZe is at risk and it is unknown whether or when
the 19 regulatory entities originally included in phase 3 will
implement the system. In addition, as we describe on page 73,
we interviewed the 10 executive officers of the phase 1 regulatory
entities during mid‑September through mid‑October 2014
and found that eight reported that BreEZe has decreased their
regulatory entities’ operational efficiency. Further, we find it
puzzling that CalTech asserts in its response that the BreEZe
system was successfully put into production in 2013 when, as
shown in the Appendix beginning on page 81, the IPO specialist
and independent verification and validation (IV&V) consultant
have identified nearly 50 significant issues with the project in
their monthly reports following the implementation of BreEZe
in October 2013 at the phase 1 regulatory entities. In fact, as we
explain on page 38, the September 2014 IPO report identified
that the project’s overall health was poor and also states that the
online application feature, which the IPO specialist considers a key
part of BreEZe, had not been “turned on” for some of the phase 1
regulatory entities.
We state on page 36 that it was not until after the California 3
Department of Consumer Affairs (Consumer Affairs)
estimated the cost of completing the project at $300 million in
June 2014, the same month it submitted Special Project Report
(SPR) 3 to CalTech for approval, that CalTech changed its oversight
approach on the BreEZe project. According to the BreEZe project
director, Consumer Affairs withdrew its submission of SPR 3,
126 California State Auditor Report 2014-116
February 2015
which CalTech previously approved in July 2014, upon direction
from CalTech and the California Department of Finance (Finance)
in September 2014. This direction from CalTech was a change in
its oversight approach in that it was the first time it had directed
Consumer Affairs to take an action that significantly altered the
project. We discuss CalTech’s involvement in the BreEZe project
beginning on page 30.
4 CalTech challenges our conclusion that it should have suspended
BreEZe. We stand by our conclusion. As discussed in detail on
pages 36 through 40, CalTech did not use its authority to ensure
that Consumer Affairs addressed the significant and persistent
warnings of the IV&V consultant and the IPO specialist. For
example, on page 38 we question why CalTech did not intervene
instead of approving SPR 3, given that Consumer Affairs was
not appropriately addressing the concerns raised by the IV&V
consultant and IPO specialist; these concerns were numerous
and were identified in CalTech’s analysis of SPR 2 in 2013. Further,
on page 39 we explain that had CalTech chosen to suspend the
project, it could have temporarily paused BreEZe development
and could have provided Consumer Affairs with additional time to
conduct a cost‑benefit analysis and correct fundamental problems,
such as requirements issues, it encountered during planning
and development.
5 CalTech indicated that suspending the project as suggested by the
report would have exposed the State to contractual liability to
the prime contractor at a rate of up to $1.2 million per month up
to the full value of the contract. Our report indicates on page 40
that CalTech could have suspended the project while it was still
in the planning phase, in the spring of 2011, prior to formation of
the prime contract. Suspending the project at that juncture would
not have exposed the State to any such liability. The requests for
proposal contained provisions expressly reserving the State’s right
to cancel the solicitation prior to awarding the contract. Similarly,
Consumer Affairs could have canceled the negotiations with
Accenture LLP (Accenture) conducted under California Public
Contract Code, Section 6611, at any time prior to awarding the
contract without incurring any liability. This section of law pertains
to contracts, such as the BreEZe contracts, that are conducted
through a negotiation process. We recognize that suspending
the project after the prime contract was awarded could make
the State liable for certain costs. However, we believe there are
mechanisms in the contract that allow for the containment of
potential liability. In particular, there are provisions that allow for a
partial or complete stop work order and they require the contractor
to take all reasonable steps to minimize the resulting costs and they
specify that the State is not liable for lost profits.
California State Auditor Report 2014-116 127
February 2015
CalTech indicated that terminating the contract for convenience 6
could have allowed the contractor to claim as much as $38 million.
However, our report does not recommend a termination for
convenience. Instead, it recommends on page 50 that if Consumer
Affairs receives the necessary resources to successfully implement
BreEZe at the regulatory entities included in phase 2 and the project
continues to face escalating costs, then CalTech should require
Consumer Affairs to conduct an analysis of the costs and benefits
of moving forward with the project as planned or suspending
or terminating the project. Without this analysis, CalTech is not
positioned to make an informed decision about whether Consumer
Affairs’ current plan to partially complete the project at a total
estimated cost of $96 million is the most prudent course of action.
We clearly state on page 36 that the $300 million estimate was 7
informally developed by the BreEZe project team and the estimate
was not developed in the same manner as required by an SPR.
Further, although CalTech reported it had extensive engagement
with Consumer Affairs from the beginning of the project, it did
not use its authority to ensure Consumer Affairs addressed the
significant and persistent warnings of the IV&V consultant and the
IPO specialist, as we discuss on pages 36 through 40.
CalTech misses our point. Although Consumer Affairs has taken 8
some actions to address concerns raised by the IV&V consultant
and the IPO specialist, our point on pages 36 and 37 is that
Consumer Affairs did not take appropriate action to address all
of the concerns raised and CalTech did not require Consumer
Affairs to remedy the problems raised. In fact, on page 37 we
describe that the BreEZe project director acknowledged he did
not always act on the concerns raised in the IPO report. For
instance, the IPO specialist raised concerns related to staffing and
resources throughout the course of the project. Further, we explain
on pages 34 and 35 that CalTech did not ensure that Consumer
Affairs addressed the CalTech director’s concerns about project
management, project governance, and contract management
before approving two SPRs that identified significant project cost
increases.
CalTech is incorrect. We do not conclude in the report that CalTech 9
never reviewed or acted on the 1,700 reported initial project defects
after the BreEZe system went into production, as CalTech claims
in its response. Rather, on page 28 we explain that according to
the IV&V consultant, the extensive user acceptance testing period
likely resulted in part from the BreEZe system having almost 1,700
unresolved defects at the beginning of the testing period. Further,
in contrast to its assertion, we never received information from
CalTech that it assisted Consumer Affairs in “reviewing each one of
these reported defects.”
128 California State Auditor Report 2014-116
February 2015
10 Throughout its response, CalTech does not explicitly agree or
disagree with our recommendations. Instead, in its responses to our
recommendations, CalTech generally describes actions it has taken
in the past and fails to explain what actions it intends on taking in
the future to implement the recommendations. We look forward to
CalTech’s 60‑day, six‑month, and one‑year responses to our report
in which it should provide evidence of its progress in implementing
our recommendations.
11 CalTech appears to miss the point of our recommendation.
Although we agree that the IPO and IV&V reports document
project issues, risks, and concerns raised on a project, these
reports do not document key discussions CalTech may have with
Consumer Affairs in which significant concerns are raised about
the project vendor Accenture and Consumer Affairs’ performance,
or their proposed actions to address such concerns. For example,
on page 37, we explain that, according to the CalTech director, in a
meeting in February or March 2013, he verbally cautioned officials
at Consumer Affairs that CalTech had just suspended or terminated
two other projects and that BreEZe would be next if CalTech did
not see the department improve its rigor in project management,
project governance, and contract management. However,
CalTech did not document this discussion or its outcome. By not
documenting key discussions, we believe that CalTech is hindered
in its ability to hold departments, such as Consumer Affairs,
accountable for addressing significant concerns raised.
12 CalTech has misunderstood our recommendation. CalTech refers
to the determination made to end the contract with Accenture
following phase 2 implementation and a gap analysis that will
guide future efforts to address phase 3 regulatory entities.
However, our recommendation on page 50 is for a cost‑benefit
analysis to be conducted if the necessary resources are received to
successfully implement phase 2 and the project continues to face
escalating costs.
13 CalTech’s response appears to indicate that it need not implement
our recommendation because of existing thresholds for IT project
reporting. In as much as these reporting requirements did not
prevent the numerous problems with the BreEZe project we
identified in the report nor spur CalTech to significantly intervene
in the project earlier than it did, we believe they are insufficient for
those purposes and our recommendation is needed.
14 Although CalTech did not suspend the BreEZe project, it did
change its oversight approach in the summer of 2014, as we indicate
on page 36, by directing Consumer Affairs to withdraw SPR 3.
California State Auditor Report 2014-116 129
February 2015
This action, which is the type of action we expected CalTech to
take sooner, led to SPR 3.1 and the replanning efforts it describes in
its response.
In response to recommendations we made in Chapter 2 on 15
pages 60 and 61, CalTech indicated that it has processes in
place that address our recommendations. However, because our
recommendations were based on issues we identified in reviewing
the Consumer Affairs’ BreEZe contracts with Accenture, which
were executed under the direction of the California Department of
General Services (General Services), we did not review and verify
whether CalTech’s current processes address our recommendations.
Thus, we look forward to CalTech’s 60‑day, six‑month, and one‑
year responses to our report in which it should provide evidence
of its progress in implementing our recommendations, such as
policies, procedures, or other relevant documentation.
CalTech indicated that the State’s current General Provisions, 16
Section 37, is required for all department projects and CalTech
is in the process of updating the language. It is correct that the
State’s current General Provisions, Section 37, is required for all
department projects. The issue, however, is that instead of using the
standard language, the contractor for the BreEZe project proposed
and Consumer Affairs and General Services approved a deviation
from the standard language that increased Consumer Affairs’
financial risks, as we explain on page 55.