Elaine M. Howle State Auditor
Doug Cordiner Chief Deputy
January 27, 2015 Letter Report 2014‑136
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
The California State Auditor (state auditor) presents this letter report concerning administration
of the Coastal Improvement Fund (improvement fund) by Los Angeles County (county). This
report concludes that the county needs to do a better job of communicating to the public
its plans for using improvement funds to create public open space. To date, the county has
neither established a time frame nor developed specific plans for when and how it will use
the improvement fund’s resources. The county’s lack of clarity and urgency on this issue may
result from the improvement fund’s small ending balance of only $250,000, a figure well below
the $1.45 million the county intended to collect when it established the improvement fund fee
nearly 20 years ago. The fund balance is small because residential developers can legally avoid
paying the fee by obtaining credits for including certain qualifying features in their projects,
which, in some cases, appear to have questionable public value. Our review of seven projects that
were assessed the fee found that developers for two of the projects avoided paying the fee by
obtaining a sufficient amount of credits. Additionally, we noted instances in which the county
issued building permits before receiving payments of the fee, and, in one case, the county let
several years elapse before receiving payment. Finally, there was one instance in which the
county undercollected about $22,000 for the improvement fund because it did not verify that a
developer had fully earned its project credits. When we raised the issue with Regional Planning,
it took prompt corrective action and recalculated the improvement fund fee. It then notified the
developer of the amount owed and received payment in late December 2014.
Background
The Improvement Fund
The county established the improvement fund in 19951 with the intended purpose of offsetting the
effects of an increased residential population in Marina del Rey by ensuring sufficient open space
for its residents. Thereafter, developers of new residential housing units have been required to
pay a fee to the improvement fund—$600 per new residential unit2—and the county has been
required to use the proceeds from these fees to develop new open space or to improve existing
1 In 1996 the California Coastal Commission approved the creation of the improvement fund as part of its certification of the Marina del Rey
Land Use Plan (land use plan).
2 A 2012 amendment to the county code established an improvement fund fee of $1,200 per new residential unit for certain residential
developments that replace public parking lots, and it required the county to start adjusting the $600 fee amount for inflation using the
Bureau of Labor Statistics’ Consumer Price Index (CPI). For 2014 the fee was $619 per new residential unit.
621 Capitol Mall, Suite 1200 Sacramento, CA 95814 916.445.0255 916.327.0019 fax www.auditor.ca.gov
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 2
facilities, such as parks and public walkways.
Calculations Behind the County’s
The text box to the right shows the method
Coastal Improvement Fund Fee
and assumptions behind the calculation of the
for Marina del Rey
improvement fund fee. However, the county
code also contains several provisions that allow New Residents Calculation
developers to obtain project credits that can
New residential units 2,420
offset their payment of improvement fund fees.
Estimated residents per unit x 1.5
Specifically, developers may obtain project Estimated new residents 3,630
credits amounting to $2.30 per square foot if
they develop 500 or more contiguous square feet Required Open Space Calculation
of public open space.3 The text box below Estimated new residents 3,630
County park standard (1 acre per 250 residents) ÷ 250
Acres of open space required 14.5
Public Amenities That Reduce Amounts
Fee Calculation
Owed to the Coastal Improvement Fund
Estimated development cost per acre $100,000
Residential developers can receive credit reducing the Acres of open space required x 14.5
payment due to the Coastal Improvement Fund by Total estimated cost to fund required open space $1,450,000
including amenities such as:
New residential units ÷ 2,420
• Bicycle paths Calculated fee per unit $599.17
• Community buildings
Applied fee per residential unit $600.00
• Drinking fountains
Source: Title 22, Division 1, Chapter 22.46.1950 of the
• Interpretive displays Los Angeles County Code of Ordinances.
• Irrigation
• Jogging paths
• Landscaping
• Nonmotorized low-cost boating describes the types of projects for which
• Nonmotorized public boating facilities a developer may receive these credits. The
county’s Department of Regional Planning
• Parking lots
(Regional Planning) and Department of
• Pedestrian promenades
Beaches and Harbors (Beaches and Harbors)
• Picnic tables and benches jointly administer the improvement fund, as
• Playgrounds the county code requires.
• Recreation centers
• Recreational fields
The County’s Process for Assessing Improvement
• Restroom facilities
Fund Fees
• Turf
• View decks and areas
All development in Marina del Rey requires
• Walkways a coastal development permit to ensure
that the development conforms to
Source: Title 22, Division 1, chapters 22.46.1950 and 22.46.1970
of the Los Angeles County Code of Ordinances. the Marina del Rey land use plan and the
3 The 2012 amendment to the county code also required the county to use the CPI to adjust the $2.30 credit amount for inflation.
For 2014 the county gave developers a credit amount of $2.37 per square foot of public open space.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 3
Specific Plan,4 which is contained in the county code. A coastal development permit for
Marina del Rey is a discretionary permit that generally requires the Los Angeles County
Regional Planning Commission (planning commission) to exercise judgment and to
deliberate at a public hearing before deciding to approve or disapprove a project seeking this
type of permit.5 In addition to reviewing the application and the project plans for coastal
development permits, Regional Planning staff also determine whether improvement fund fees
apply to projects; when applicable, the staff calculate those fee amounts. If the developer claims
any improvement fund credits, Regional Planning staff determine whether the credits are
consistent with the land use plan.
For the planning commission hearing, Regional Planning prepares a staff report with project
information and recommendations, draft findings, and draft conditions stipulating the
improvement fund requirements. At times the conditions also specify the estimated amount
due to the improvement fund, if applicable. The county code requires the county to collect
the improvement fund fee from the developer before the developer obtains a building permit
from the county’s Department of Public Works (Public Works). Public Works issues building
permits only after receiving notice from all applicable agencies—including Regional Planning
as well as Beaches and Harbors—that all conditions have been satisfied for issuance of the
building permit.
An Overview of Existing and Proposed Open Space Improvements in Marina del Rey
According to county documents, Marina del Rey has more than 44 acres designated as open
space. As of November 2014 the county had developed about 25 of these acres and had
proposed plans for developing open space on the remaining 19 acres, as shown in Figure 1 on
the following page. The largest undeveloped portion of open space is Parcel P, which includes
Oxford Basin and which was previously an underdeveloped wetland area of roughly 10 acres.
According to Beaches and Harbors, the county began an open space development project
on Parcel P in December 2014 that it expects to complete in 12 months. Another significant
undeveloped section of open space is the planned expansion of Parcel EE—Chace Park. The
county intends to expand the park into parcels 45, 47, and 77; however, when this expansion
will take place is uncertain.
4 The Specific Plan serves as an implementation mechanism for the Marina del Rey land use plan, and it establishes development standards
and guidelines that are the regulatory basis for future development, preservation, and reconstruction efforts in Marina del Rey.
5 Following the planning commission’s decision on a coastal development permit, any interested party may appeal decisions about
certain development projects in Marina del Rey to the county’s board of supervisors. Appeals must be submitted within 14 days of the
hearing decision. Similarly, the board of supervisors’ hearing decisions regarding certain projects may be appealed to the California
Coastal Commission.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 4
Figure 1
Existing and Proposed Park Areas Designated as Open Space in Marina del Rey
51
ACRE
PARCEL SIZE (AC) DESCRIPTION
SS
Existing Park Areas
Q 2.74 Burke Park; open space and parking
RR 45 RR 2.12 Burke Park
77 SS 3.40 Burke Park
51 0.52 Gateway green space
Q 47 XT 1.23 Area A buffer
EE 7.19 Chace Park
BR 0.67 Green space near main channel
EE DS 0.72 Green space near gateway
XT
JS 0.36 Green space near gateway
P
18 HS 5.90 Marina Beach
Total AC 24.85
147 20 12
Proposed Park Areas
45 1.80 Chace Park expansion
140 HS 47 1.92 Chace Park expansion
77 2.92 Chace Park expansion
9 1.46 Wetland park
JS
IR 111 IR 1.00 Open space in support of Marina Beach
15
112 P* 10.26 Oxford Basin
14
Total AC 19.36
101 10
100
DS 9
BR
# = Other parcels we discuss in the report where residential development has occurred or is planned.
Sources: Los Angeles County Department of Beaches and Harbors (Beaches and Harbors) staff and the Los Angeles County Code Section 22.46,
maps 3 and 8.
Note: The figure does not include the publicly accessible open space, such as pedestrian promenades along the waterfront, which have been
provided by residential developers. Also, with the exception of parcels 9 and IR, the figure does not show portions of other parcels that have
existing or proposed open space.
* According to a planning specialist at Beaches and Harbors, Parcel P development will begin on December 9, 2014, and is expected to take
12 months to complete.
Scope and Methodology
The Joint Legislative Audit Committee (audit committee) directed the state auditor to audit
the county’s administration of the improvement fund. Specifically, the audit committee
asked the state auditor to review the improvement fund’s revenues, expenditures, and fund
balance for the past three years. The audit committee also asked us to identify the number
of residential building permits issued and whether the fees were collected. Finally, the audit
committee asked us to determine whether the reasons and justification for the county’s not
collecting any fees complied with applicable criteria.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 5
We obtained an understanding of Regional Planning’s process for approving development
requests and for assessing the improvement fund fee by reviewing project files and by
conducting interviews with the staff responsible for development projects in Marina del Rey.
We also reviewed Regional Planning’s case‑processing manual and draft management policy
for the improvement fund. Additionally, we reviewed documentation for development projects
that the planning commission approved, including the conditions of approval.
To identify revenues, expenditures, and the fund balance of the improvement fund, we
interviewed personnel and obtained and reviewed accounting records from Beaches and
Harbors, which is responsible for the improvement fund’s accounting. We noted that between
July 2011 and June 2014, the county did not charge any expenditures to the improvement fund
and that only one developer made a payment to the improvement fund. Finally, we evaluated
the county auditor‑controller’s 2013 review of the improvement fund balance.
Although the audit committee requested that the state auditor review improvement fund
activities for the past three years, when possible, we expanded our period of review to
19 years—from the 1995 establishment of the fund to 2014—because most of the new residential
development projects to which improvement fund fees might have applied were approved
more than three years ago. To determine the number of building permits issued and whether
the improvement fund fees were collected, we interviewed personnel at Regional Planning
and at Public Works and obtained data from the departments’ respective databases. We
first reviewed each database independently to identify all the projects and building permits
to which improvement fund fees might have applied. Next, we identified the date that Public
Works issued a building permit and identified when the developer submitted payment to the
improvement fund. Finally, we reviewed how Regional Planning awards credits to developers
that are seeking reductions to the amounts they owe to the improvement fund.
The County’s Plan for Using the Improvement Fund Is Unclear, Contributing to Public Confusion
About Plans for the Funds Collected
When it established the improvement fund, the county contemplated using money in the
improvement fund to create park facilities on specific parcels in Marina del Rey, including
Parcel FF (now Parcel 14). However, in February 2012, the California Coastal Commission
certified an amendment to the land use plan that altered the designation of Parcel FF from
open space to residential. After that, it became clear that the improvement funds would no
longer be used to develop park facilities on what was Parcel FF. However, as the land use plan
has evolved, the county has not clearly updated the public regarding how it specifically intends
to use the amounts collected in the improvement fund to develop additional open space
throughout Marina del Rey. For example, an individual reading the county code today would
continue to see mention of Parcel FF (which no longer exists) and that parcel’s linkage to open
park space and the improvement fund fee.
The planning specialist at Beaches and Harbors asserted that the primary purpose of the
improvement fund is not necessarily to finance the development of specific open space on
specific parcels, but rather to increase the overall density of public open space in Marina del Rey
to correspond with the area’s planned increase of 2,420 new residential units. Staff from
Beaches and Harbors believe they are achieving this goal by incentivizing developers to include
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 6
certain features in their development projects in exchange for credits, which developers then
use to reduce or eliminate the need to pay the improvement fund fee. In essence, the county
has foregone the money it otherwise would have received from developers in exchange
for residential projects that include space that is open to the public, such as promenades,
landscaping, and parking lots.
Since establishing the improvement fund nearly two decades ago, the county has received
significantly less than the $1.45 million it originally planned when it established the fee. Based
on past performance of the fund and the county’s willingness to accept the public space that
residential developers provide in lieu of fee payments, it seems unlikely that the improvement
fund will ever accumulate sufficient amounts to become a significant single funding source
for the development of new open space, such as a neighborhood park. Instead, according to
the planning specialist at Beaches and Harbors, the county intends to use other county funds,
along with the improvement fund, to develop open space projects in Marina del Rey, such as
the expansion of Chace Park and the development of a wetland park proposed for Parcel 9.
However, when these projects will actually begin remains uncertain. Without a clear plan and
timeline for using improvement funds, and with developers receiving credits for open space that
has questionable public value, as we discuss in the next section, the public will likely continue
to ask whether the county is sufficiently mitigating the impact of the increasing local population
through the creation of additional public open space.
Generous Yet Permissible Project Credits Allow Developers to Avoid Paying Into the
Improvement Fund
Since it established the improvement fund in 1995, the county has approved nine development
projects in Marina del Rey. However, developers have been able to significantly reduce the
amounts they owe to the improvement fund by receiving credits from the county in exchange
for creating or improving public open space. As Table 1 on the following page shows, the
nine development projects would have generated $1,308,000 in gross fees for the improvement
fund; however, the awarded credits allowed developers to reduce their payments. Specifically,
the $642,000 in credits for the five projects shown in Table 1 reduced the gross fees on those
projects by 83 percent, from roughly $775,000 to $133,000. Overall, the $642,000 in credits
that developers received thus far for promenades, walkways, and landscaping, among other
improvements, have translated to more than six acres of developed public open space, when
converted at roughly $2.30 per square foot.
We believe that the county’s extending of some of these credits to developers may be too
generous. For example, Regional Planning has been generous in awarding about $241,000 in
credits to developers for pedestrian promenades that also serve as fire access roads. Regional
Planning’s practice has been to award credits for the entire area of the pedestrian promenades
instead of for just those portions unrelated to fire access that conform to the open space policy.
Although the land use plan does not legally preclude Regional Planning from granting credits to
developers for entire promenades, we noted that doing so means the improvement fund loses
additional revenue to achieve its goals. The county awarded about $212,700 in project credits to
the developer of a project on parcels 12 and 15 for portions of pedestrian promenades that also
serve as fire access roads. Additionally, Regional Planning awarded almost $28,300 in project
credits to another developer of a project on Parcel 20 for portions of a waterfront promenade
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 7
that also serves as a fire access road. If Regional Planning had granted credits only for the
portions of the promenades not pertaining to fire access, these two developers would have
received about $94,400.
Table 1
Coastal Improvement Fund Contributions
GROSS
COASTAL IMPROVEMENT NET NET
PARCEL FUND (IMPROVEMENT FUND) PROJECT CREDIT IMPROVEMENT FUND IMPROVEMENT FUND
NUMBER FEE ASSESSED RECEIVED* FEE DUE FEE PAID
18 $76,800 $0 $76,800 $76,800
12/15 374,043 297,921 76,122 76,122
20 59,400 37,513† 21,887† 0†
111/112 72,000 72,000 0 0
140 64,800 29,578 35,222‡ 35,220‡
100/101 205,200 205,200 0 0
0§
(building
147 138,966 0 138,966 permit
obtained)
Not paid
ll
10 163,416 Not yet determined Not yet finalized (no building
permit)
Not paid
ll
14 153,594 Not yet determined Not yet finalized (no building
permit)
Totals $1,308,219 $642,212 $348,997 $188,142
Sources: California State Auditor’s review of Los Angeles County Department of Regional Planning (Regional Planning) and Department
of Beaches and Harbors’ coastal development project files, review of Department of Public Works’ database of building permits issued in
Marina del Rey, and interviews with Regional Planning’s principal planner.
* Project Credit Received include only those credits given to the developer up to the amount of the Gross Improvement Fund Fee Assessed.
Two developers received credits in excess of the gross assessed improvement fund fee, including $83,950 in credits for Parcel 111‑112 and
$228,965 in credits for Parcel 100‑101.
† This developer initially received credits in excess of the gross improvement fund fee assessed; however, it did not build all of the public
open space outlined in the coastal development permit approval conditions. Therefore, Regional Planning recalculated the improvement
fund fee and project credits and in November 2014 charged the developer the difference of $21,887. Payment was received in late
December 2014.
‡ Due to an immaterial error in the improvement fund fee calculation, the developer was charged and paid $2.30 less than it owed.
§ Although this developer has not started building, it was issued a building permit prematurely as it has not paid the improvement fund fee.
Regional Planning billed the developer for the full improvement fund fee amount in November 2014.
ll The developers for these projects have not requested any credits; however, Regional Planning staff indicated that these developers can still
request credits since they have not started building these developments. The net improvement fund due will depend on the final project
credits received.
As Figure 2 on the following page shows, some developers received credits for space that is
clearly marked as public open space and that is accessible to the public. However, in another
case, a developer received credits for space that was not clearly marked as available to the
public, and we question whether anyone other than the residents of that development will
benefit from such space. In particular, a developer built an additional 342 residential units on
parcels 100 and 101 in Marina del Rey and received credits that offset more than $205,000 in
improvement fund fees by including landscaping, pedestrian walkways, parking spaces, and
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 8
roadway access to the parking spaces. These credits appear to be allowable improvements
according to the county code; however, as the photographs in Figure 3 on the following page
demonstrate, it is unclear whether the general public is aware of, benefits from, or even uses
these open spaces. For example, we think it unlikely that the general public will benefit from
the gravel courtyard in front of the residential building. Furthermore, we noted that the parking
spaces at this property were marked “guest parking” or were not marked at all, and this situation
may cause some members of the public to assume that the parking spaces are for residents only.
Figure 2
Examples of Project Credits Claimed in Marina del Rey That Are Clearly Accessible to the Public
Parcel 140
Parcel 12
Parcel 12
Sources: Photographs taken at Parcel 140 (top) and Parcel 12 (middle, bottom) by auditors during site visits.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 9
Figure 3
Examples of Generous Yet Permissible Project Credits Claimed on Parcel 100‑101 in Marina del Rey
Sources: Site plan obtained from the Los Angeles County Department of Regional Planning’s coastal development project file and photographs taken at Parcel 100‑101
by auditors during site visits.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 10
Because the developers received significant credits for their respective projects, the
improvement fund balance, including interest, was just below $204,000 at the end of fiscal
year 2013–14, as Table 2 shows. Further, from September 2004 through November 2014, all
of the improvement fund revenues—with the exception of one developer’s contribution of
$35,220 in November 2011—have come from interest earnings. Before this November 2011
contribution, the last payment to the improvement fund by a developer occurred in
August 2004. In addition, since it was established, no expenditures have ever been made
from the improvement fund.
Table 2
Coastal Improvement Fund Balance
Fiscal Years 2011–12 Through 2013–14
FISCAL YEARS
2011–12 2012–13 2013–14
Beginning Balances $164,973 $201,436 $202,721
Revenue
Developer fees 35,220 0 0
Interest earnings 1,243 1,285 1,277
Expenditures 0 0 0
Ending Balances $201,436 $202,721 $203,998
Source: Fiscal years 2011–12 through 2013–14 unaudited accounting data from the Los Angeles County’s Electronic Central
Accounting and Purchasing Systems.
Note: In December 2014 the Los Angeles County Department of Beaches and Harbors received a payment of $45,461, which
increased the Coastal Improvement Fund’s ending balance to about $250,000.
The County Did Not Always Ensure That Developers Paid Improvement Fund Fees Before They
Obtained Building Permits, as the County Code Requires
Our review showed that the county did not always collect improvement fund fees before
developers obtained building permits, as the county code requires. According to the code,
improvement fund fees must be collected before Public Works issues building permits.
However, Regional Planning and Beaches and Harbors lack a formalized process for
ensuring compliance with this requirement. As a result, Public Works issued building
permits to two developers before they paid the improvement fund fees they owed.
Public Works provides developers with a form listing all of the agencies, including Beaches
and Harbors as well as Regional Planning, from which developers must obtain approval before
receiving their building permits. According to a senior civil engineer at Public Works, although
Public Works must ensure that each agency listed on that form gives its approval before Public
Works issues a building permit, each agency is responsible to ensure that the developer has
met all requirements related to that particular agency. Once Public Works staff receive approval
from all applicable county agencies, Public Works assumes that the developer has satisfied all
relevant requirements, such as payment of the improvement fund fee.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 11
Before June 2013 Regional Planning and Beaches and Harbors jointly administered the
improvement fund, and both agencies collected and deposited fees into their own separate
accounts. A county review in June 2013 took issue with this practice and recommended that all
fees be deposited into a single interest‑bearing account and that both agencies develop formal
policies for administering the fund. Both agencies now agree that Regional Planning awards
credits and calculates the fees due from developers while Beaches and Harbors collects and
deposits the amounts collected; however, formal policies and procedures that will preclude
Public Works from issuing building permits prematurely have yet to be finalized. For example,
the county has not completed protocols for how Regional Planning should inform Beaches and
Harbors of the amounts due from developers, and Beaches and Harbors has yet to formalize
how it will inform Public Works that developers have paid their fees. Regional Planning
provided us with draft procedures that it plans on finalizing in February 2015. However, these
draft procedures do not currently specify necessary communications with Public Works
regarding fee payments.
In fact, the prior lack of clarity about which department was responsible for collecting the
applicable fees and for informing Public Works that the fees were paid may have contributed
to developers’ obtaining building permits without first paying their improvement fund fees.
For example, one developer received a building permit in 2007 and did not pay the $35,000 fee
until more than 4.5 years later. Another developer, whose project on Parcel 147 Regional
Planning approved in 2012, obtained a building permit in August 2013—just after the county
auditor‑controller’s review was published—but the developer has yet to pay the nearly
$139,000 in improvement fund fees that it owes. When we raised this issue with Regional
Planning, the principal planner acknowledged that this delayed payment was an oversight but
asserted that the developer had not yet started construction. Regional Planning sent a letter
in November 2014 informing the developer of the error and requesting immediate payment
of improvement fund fees. As of early December 2014, the county had not yet received this
payment. We are concerned that even after the county auditor‑controller published its review—
and despite the specific requirement in the county code that payment of the fee must take place
before a developer receives a building permit—this developer was able to obtain a building
permit without paying the applicable improvement fund fee. Until both Regional Planning
and Beaches and Harbors finalize their procedures, the county will continue to run the risk
of issuing building permits to developers that have not paid their respective improvement
fund fees.
Regional Planning Did Not Verify That a Developer Fully Earned Its Project Credits, Resulting in an
Undercollection of Approximately $22,000 for the Improvement Fund
One developer initially received nearly $22,000 in project credits for a public parking structure
that was supposed to be built by December 2007, but was not.6 However, the county failed to
adjust the amount of improvement fund credits and failed to recalculate the improvement fund
fees due until we raised the issue during our audit. The county acknowledged its oversight and
billed the developer for the amount owed.
6 The planned parking structure was to be 12,740 square feet and valued at $29,302 (or $2.30 per square foot) in project credits. Regional
Planning ultimately billed the developer about $22,000 because the developer had excess credits resulting from other project features,
such as waterfront promenade space.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 12
For this particular development, the developer initially received credits in excess of the
improvement fund fee for a two‑phase project on Parcel 20 in Marina del Rey. The first
phase largely consisted of constructing a 99‑unit apartment building, which the developer
has completed. The second phase, which has not been built, includes building a five‑level
parking structure containing 231 public parking spaces for which the developer received
roughly $22,000 in project credits. The coastal development permit conditions for this project
specifically required the developer to complete this phase no later than December 21, 2007.
Seven years later, the developer has yet to start building this structure. Furthermore, the lot
where the structure should have been built is currently being used as private parking (as
Figure 4 on the following page shows), which does not constitute legitimate public open space.
When we raised the issue with Regional Planning, the principal planner acknowledged that
this development had not been completed and took prompt corrective action. Following our
inquiry, Regional Planning recalculated the improvement fund fee for the project, removed the
credits awarded for the parking structure, and notified the developer that it owed the remaining
balance of about $22,000. Although Regional Planning billed the developer in November 2014,
the county had yet to receive payment as of early December 2014.7
Regional Planning has a zoning enforcement unit (enforcement unit) responsible for inspecting
this and other developments annually to determine compliance with permit conditions.
However, in this case, the enforcement unit did not verify that the developer actually earned
some of the credits it received from the county because, according to the principal planner,
the county neglected to communicate the amount due for the improvement fund fee and the
related project credits in the permit’s conditions. In late December 2014 the principal planner
also stated that Regional Planning had developed standard condition language that will be
incorporated into all future conditions of approval for projects subject to the improvement
fund fee.
Recommendations
To ensure that the public is informed of the county’s plans for using the improvement
fund, the county needs to more clearly communicate its intentions and then update such
communications as its plans change. The county’s communications could be as simple as a
public notice and a posting to its Web site that include the following:
• Information on the specific projects and parcels in Marina del Rey where it intends to spend
money from the improvement fund for the development of open space (or a time frame for
making such a decision).
• The time frame for the expected start and completion of such projects.
7 The developer submitted payment in late December 2014, subsequent to the conclusion of our audit fieldwork.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 13
Figure 4
Planned Development Versus Actual Development and “No Parking” Signs on Parcel 20
Phase 1 Phase 2
Public Parking
Stucture Not Built
Sources: Los Angeles County Department of Regional Planning’s coastal development project files (top), Google Earth maps (middle), and photographs (bottom)
taken at Parcel 20 by auditors during site visits.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 14
To better ensure that developers do not obtain building permits before they pay the fee to the
improvement fund, the county needs to finalize its improvement fund management procedures
regarding the collection of the fee and the reporting of that collection to Public Works.
Specifically, such policies should include the following:
• A protocol for how Regional Planning communicates the amount due to Beaches
and Harbors.
• A protocol for how Beaches and Harbors informs Public Works that the developer has paid
the fee to the improvement fund.
To ensure that developers do not receive project credits to which they are not entitled,
the county should develop a mechanism that will allow its enforcement unit to verify
that the developer actually earned the credits it received.
We conducted this audit under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. Those standards require that we plan and perform the audit
to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and
conclusions based on our audit objectives specified in the scope section of the report. We
believe that the evidence obtained provides a reasonable basis for our findings and conclusions
based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
Date: January 27, 2015
Staff: Grant Parks, Audit Principal
Tram Thao Truong
Brett Noble, MPA
Legal Counsel: Stephanie Ramirez‑Ridgeway, Sr. Staff Counsel
For questions regarding the contents of this report, please contact
Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 15
*
1
* California State Auditor’s comments begin on page 20.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 16
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 17
2
3
4
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 18
5
6
7
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 19
*
* We are not publishing the attachment because it contains confidential financial information.
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 20
Comments
CALIFORNIA STATE AUDITOR’S COMMENTS ON THE JOINT
RESPONSE FROM THE LOS ANGELES COUNTY DEPARTMENT
OF REGIONAL PLANNING AND THE DEPARTMENT OF
BEACHES AND HARBORS
To provide clarity and perspective, we are commenting on the joint
response from the Los Angeles County Department of Regional Planning
(Regional Planning) and the Department of Beaches and Harbors
(Beaches and Harbors). The numbers below correspond to the numbers
we have placed in the margins of the response.
1 We stand by the factual accuracy of our letter report and do not believe
it requires further clarification. We more fully address Regional Planning
and Beaches and Harbors’ joint responses in our comments below.
2 Regional Planning and Beaches and Harbors incorrectly claim that our
report disfavors the awarding of credits for the on‑site public open
space created by developers. To clarify, our report concludes that
some of the credits awarded were generous (albeit allowable) under
the Marina del Rey local Land Use Plan (land use plan). For example,
Figure 3 on page 9 depicts examples of a project that we considered to
have received generous credits, such as a gravel courtyard at the entry
way of a residential property and parking spaces not clearly marked as
available for public use. We do not believe these are examples of open
space that would benefit the general public.
3 Regional Planning takes issue with our conclusion that it was generous
in awarding credits for the entire portion of various public promenades,
instead of just the portion not needed for fire access lanes. We stand
by our conclusions. We recognize, as we state on page 6, that nothing
legally precludes Regional Planning from granting credits for the entire
promenade. However, developers were already required to provide
space for fire access lanes and nothing requires Regional Planning to
grant credit for that space. In fact, the county’s municipal code states
that credits shall be granted (that is, at a minimum) for that portion
of the pedestrian promenade or view corridor not designated as a fire
access road.
4 We stand by the statements in our report. On page 5 we state that the
Coastal Improvement Fund (improvement fund) and the related fee
were established with the thought of developing public park facilities on
specific parcels in Marina del Rey. However, those goals and plans have
changed over time with amendments to the local land use plan. Our
critique was that Regional Planning and Beaches and Harbors should
be more explicit with the public regarding their planned uses for the
improvement fund. We are pleased that both agencies fully intend to
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
January 27, 2015
Page 21
implement our recommendation and identify which specific projects
will receive financial support from the improvement fund. We will be
monitoring Regional Planning and Beaches and Harbor’s efforts in its
60‑day, six‑month, and one‑year response to our audit.
5 Regional Planning and Beaches and Harbors imply that they have already
made clear to the public their plans for using the proceeds from the
improvement fund. Contrary to this assertion, the Los Angeles County’s
(county) own code currently links Parcel FF—a parcel which no longer
exists—in Marina del Rey to the creation of open space by using the
improvement fund as we state on page 5. Such a condition only serves to
confuse the public regarding how the improvement fund will be used.
6 Our report makes no such assumption regarding a maximum build
out of residential units. The county’s goal at the time it created the
improvement fund was to collect $1.45 million to develop open space
on specific parcels. If over 1,000 units have been built—or roughly half
the planned number of residential units as indicated in the response—
then our report’s conclusion that the improvement fund is unlikely to
become a significant single source of funding is further confirmed. The
improvement fund has a balance of $250,000, well below $725,000,
which is one‑half of the county’s $1.45 million funding goal, as stated in
the county’s code.
7 Regional Planning and Beaches and Harbors have mischaracterized what
we said in the report. Page 6 of our report states that the $1.3 million
amount represents the gross fees (prior to applying credits). Table 1
on page 7 provides an overview of gross fees, applied credits, and the
resulting amounts paid and due to the improvement fund. Furthermore,
Table 1 clearly shows that three projects have not been built yet. Finally,
on page 6 we further explain how, for a subset of completed projects
shown on Table 1, developers were able to reduce what they owed to the
improvement fund by 83 percent.