California Department of
Veterans Affairs
The State Paid Nearly $28 Million for a Flawed System
That Fails to Meet the Needs of Its Veterans Homes
Report 2015‑121
COMMITMENT
INTEGRITY
LEADERSHIP
The first five copies of each California State Auditor report are free. Additional copies are $3 each, payable by check
or money order. You can obtain reports by contacting the California State Auditor’s Office at the following address:
California State Auditor
621 Capitol Mall, Suite 1200
Sacramento, California 95814
916.445.0255 or TTY 916.445.0033
OR
This report is also available on our website at www.auditor.ca.gov.
The California State Auditor is pleased to announce the availability of an online subscription service.
For information on how to subscribe, visit our website at www.auditor.ca.gov.
Alternate format reports available upon request.
Permission is granted to reproduce reports.
For questions regarding the contents of this report,
please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
For complaints of state employee misconduct, contact the California State Auditor’s
Whistleblower Hotline: 1.800.952.5665.
Elaine M. Howle State Auditor
Doug Cordiner Chief Deputy
June 16, 2016 2015‑121
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the California State Auditor presents this audit report concerning
the policies and procedures for the planning, development, and implementation of the California Department of Veterans
Affairs’ (CalVet) Enterprise‑Wide Veterans Home Information System (system).
This report concludes that CalVet paid nearly $28 million for the implementation of a system that has not improved
the veterans homes’ process for documenting medical care or reduced the homes’ reliance on paper records, as it was
intended to do. In addition, system instability and concerns about functionality resulted in CalVet implementing fewer
system functions at some homes than originally planned, thus limiting CalVet’s ability to provide more consistent,
efficient care for veterans. CalVet’s project management failed to promptly identify and address the system’s functionality
issues. Although it was aware of the problems as early as mid‑2012, CalVet did not begin to address them until late 2013,
and the steps it did take did not ultimately fix the problems. Further, although the California Department of Technology
(Technology Department) facilitated the contract dispute negotiations between CalVet and the system contractor, it
could not provide sufficient documentation to demonstrate its efforts to ensure that the agreements reached were in the
best interests of the State.
Several key deficiencies contributed to CalVet’s failure to implement a system that meets its needs. CalVet did not exercise
adequate oversight of its system project. Specifically, it did not complete or partially completed six of the 12 management
oversight plans required by state policy for ensuring effective project management. For the six completed plans, CalVet
fully followed only four. For instance, it did not consistently conduct impact analyses on change requests, and therefore
was unable to demonstrate that it properly understood the impact of various change requests on the project’s costs,
scope, and timelines. CalVet also hired an oversight contractor to provide both independent project oversight (IPO)
and independent verification and validation services for its system project, but that oversight contractor’s work was
inadequate, and by using the same contractor to perform both services, CalVet did not ensure it had effective oversight.
The Technology Department also did not adequately fulfill its oversight responsibilities for CalVet’s system project.
Specifically, it did not identify significant concerns with the system until August 2012. The Technology Department
indicated that because of the nature of its oversight for this project—consisting of reviewing reports created by the
oversight contractor—and because the reports did not indicate any critical errors with the project, the Technology
Department did not raise any concerns. However, our information technology expert reviewed the IPO reports and
indicated that they were consistently lacking in critical analysis, and that this omission alone should have been a red flag
triggering the Technology Department’s closer review and inspection.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
621 Capitol Mall, Suite 1200 Sacramento, CA 95814 916.445.0255 916.327.0019 fax www.auditor.ca.gov
Blank page inserted for reproduction purposes only.
California State Auditor Report 2015-121 v
June 2016
Contents
Summary 1
Introduction 7
Audit Results
The Enterprise‑Wide Veterans Home Information System
Does Not Meet the Needs of the Veterans Homes 19
Project Management Failed to Promptly Recognize the Severity of
System Problems 25
Failure to Follow Project Management Oversight Plans Contributed
to CalVet’s Unsuccessful Implementation of Its System 30
Inadequate Independent Oversight of the System Project Left
Stakeholders Without the Information Necessary to Ensure a
Successful Implementation 35
The Technology Department Did Not Adequately Fulfill Its
Responsibilities in the Oversight of CalVet’s System 38
CalVet Did Not Maintain Adequate Documentation for Its Selection of
the System Contractor and for Some Key Deliverables 42
CalVet Identified Some Lessons Learned but Rarely Used Them to
Improve Future Phases of Implementation 46
Recommendations 48
Appendix A
Comparison of the California Department Of Veterans Affairs’
Estimated and Actual Costs for the Enterprise‑Wide Veterans Home
Information System 51
Appendix B
An Expanded View of Enterprise‑Wide Veterans Home Information
System Use by the California Department of Veterans Affairs’
Veterans Homes 55
Responses to the Audit
California Department of Veterans Affairs 59
California Government Operations Agency,
California Department of Technology 63
vi California State Auditor Report 2015-121
June 2016
Blank page inserted for reproduction purposes only.
California State Auditor Report 2015-121 1
June 2016
Summary
Audit Highlights . . .
Results in Brief Our audit concerning the development
and implementation of the California
The mission of the California Department of Veterans Affairs Department of Veterans Affairs’ (CalVet)
(CalVet) is to serve California’s veterans and their families. Further, Enterprise‑Wide Veterans Home
the mission of CalVet’s veterans homes is to provide the State’s Information System (system) revealed
aged and disabled veterans with rehabilitative, residential, and the following:
medical care and services in a homelike environment at the State’s
» The system has not improved the
eight veterans homes.
efficiency of the homes’ process for
documenting medical care nor has it
In 2006, to support the healthcare information needs of its
reduced reliance on paper because of
five planned new veterans homes and its three existing homes,
system flaws.
CalVet decided to implement a computerized information
system, called the Enterprise‑Wide Veterans Home Information » System instability and concerns
System (system), to ensure that veterans receive consistent and about functionality resulted in CalVet
integrated care in any veterans home. In its feasibility study report implementing fewer system functions
(FSR)—the planning document used to assess the practicality of at some homes, thereby limiting CalVet’s
a proposed project—CalVet described the need for a system that ability to provide more efficient care
would make its processes more efficient and reduce its reliance for veterans.
on paper records. The FSR projected the cost of the system to
» CalVet’s project management failed to
be $34 million and estimated that it would be complete in 2010.
promptly recognize the severity of the
Actual implementation of the system began in mid‑2012. However,
system’s problems and address them.
the system has not achieved the expected or planned efficiencies
that CalVet anticipated. Specifically, the system has not improved
» The California Department of Technology
the homes’ process for documenting medical care nor has it
(Technology Department) lacked
reduced their reliance on paper records because of flaws that staff
documentation to demonstrate that its
encountered with the system. Additionally, system instability and
efforts to ensure that the settlement with
concerns about functionality resulted in CalVet implementing
the system contractor was in the State’s
fewer system functions at some homes than originally planned,
best interest.
thereby limiting CalVet’s ability to provide more consistent,
efficient care for veterans. Further, although some of CalVet’s » CalVet did not exercise adequate oversight
claims of noncompliance with state and federal regulations are of its system project.
overstated, its need to take additional steps outside of the system
• It did not complete or partially
to remain compliant demonstrates that it has not achieved its
completed six of the 12 required
goal of implementing a system that improved that compliance
management oversight plans to
with regulations.
ensure effective project management.
CalVet’s project management failed to promptly identify and • It hired one contractor to provide
address the system’s functionality issues. Although it was aware of both independent project oversight
such issues as early as mid‑2012, CalVet’s project management did and independent verification and
not begin to take steps to address those issues until late 2013. By validation services, and those services
that time, it had spent nearly $6 million since staff began notifying were inadequate.
them of the functionality problems. The steps CalVet’s project
management did take—pausing the implementation of the system, continued on next page . . .
sending the system contractor a cure letter to identify specific
documents required in its contract that the system contractor
had not provided, conducting an assessment of the system, and
ultimately ending the contract with the system contractor in
2 California State Auditor Report 2015-121
June 2016
» The Technology Department did December 2014—did not fix the problems. Although the California
not adequately fulfill its oversight Department of Technology (Technology Department) facilitated the
responsibilities for CalVet’s contract dispute discussions and the negotiations between CalVet
system project. and the contractor, the Technology Department could not provide
sufficient documentation to demonstrate its efforts to ensure that
• It did not identify significant concerns
the agreements reached were in the best interests of the State.
until August 2012, after Cal Vet
When CalVet signed the settlement agreement in December 2014,
had already spent $15 million on
it had spent $26.2 million on its implementation of the system. By
the system.
the time it completed its post‑implementation evaluation report in
» CalVet’s limited documentation June 2015, its project costs totaled $27.9 million. Although CalVet
for the selection of the system is now in the process of identifying a replacement system, it plans
contractor prevents it from to continue to use the current system as best it can until it replaces
demonstrating it complied with state the system.
contracting requirements.
We noted several key deficiencies that contributed to CalVet’s
• It could not provide proposals for six of
failure to implement a system that meets its needs. First, CalVet
the seven vendors or the evaluations
did not exercise adequate oversight of its system project.
for three proposals, including the
Specifically, it did not complete or partially completed six of the
winning proposal.
12 management oversight plans state policy requires for ensuring
effective project management. For the six completed plans, CalVet
» CalVet approved payments totaling
fully followed only four. For instance, in its configuration change
$733,000 for some of its key system
control management plan, which describes the process the project
implementation deliverables but could
team will follow to document, control, and manage changes to
not provide adequate documentation of
key project components and deliverables throughout the project,
receiving these final deliverables.
CalVet stated that the change control manager would assign an
analyst to conduct impact analyses on each change request to
properly understand how each one would affect project costs,
scope, and timeline. However, CalVet did not consistently conduct
impact analyses on the project’s change requests. Because it did
not always follow this plan, it was unable to demonstrate that it
properly understood the impact of various change requests on
the project’s costs, scope, and timeline. Additionally, the project
executive, who is charged with the highest level of project review
within the CalVet organization, was not involved with oversight of
the management plans. CalVet’s final project manager stated that
if project management plans were not being followed during the
project, the individual assigned ownership of the plan would have
been responsible to escalate the problem to the project manager.
Then if the project manager could not resolve the problem, it
should have been elevated to the project executive. CalVet did not
show that problems regarding the plans were ever escalated to the
project executive.
Moreover, although CalVet hired one contractor (oversight
contractor) to provide both independent project oversight
(IPO) and independent verification and validation (IV&V)
services for its system project, those services were inadequate.
Therefore, CalVet did not identify deficiencies with the system
as early as it should have. IPO provides an independent review
California State Auditor Report 2015-121 3
June 2016
and analysis of project management practices to determine if
the project is being well managed. IV&V provides a client with
technically proficient “eyes and ears” to oversee a system vendor
while an information technology (IT) system is being developed
and implemented. CalVet’s oversight contractor provided both
IPO and IV&V services. However, according to our IT expert,
separation of IV&V and IPO duties is important and provides a
number of advantages to the project and to the State. An important
function of IPO is to determine whether IV&V functions are
being performed appropriately, and by using the same contractor
to perform both functions, CalVet did not ensure that it had
effective oversight for this project. For example, our IT expert
stated that effective IPO should have raised concerns that IV&V
was not managing requirements traceability—the tracing of project
requirements throughout the project life cycle to ensure that
the system meets specified contract requirements; however, the
oversight contractor did not provide this. Although the oversight
contractor’s IPO reports should have identified these types of
deficiencies in its own IV&V work, it did not. Because the IPO
reports did not identify critical work IV&V was not performing,
neither CalVet nor the Technology Department received an
accurate assessment of whether the system contractor’s processes
were effective and whether the system reflected the agreed‑upon
quality and solution.
The Technology Department also did not adequately fulfill its
oversight responsibilities for CalVet’s system project. Since 2008
the Technology Department and its predecessor agencies have
been responsible for providing oversight to IT projects, such
as CalVet’s system, by reviewing their IPO and other oversight
reports. Specifically, the Technology Department did not identify
significant concerns with the system until August 2012, after CalVet
had already spent $15 million on the system. The deputy director of
the Technology Department’s IT Oversight Division indicated that
because of the nature of its oversight—that is, reviewing reports
that the oversight contractor created—and because the reports did
not indicate any critical errors with the project, the Technology
Department did not raise any concerns about the project. However,
our IT expert reviewed the IPO reports and indicated that they
were consistently lacking in critical analysis and that this omission
should have raised concerns at the Technology Department.
CalVet maintained limited documentation for its process both
for selecting a contractor to implement its system and for
approving payment of some invoices. This limited documentation
prevents it from demonstrating that it made a prudent decision in
awarding the contract and in approving payment for deliverables.
Specifically, it could not provide the proposals it received from
six of the seven vendors that responded to the system’s request
4 California State Auditor Report 2015-121
June 2016
for proposals and it could not provide the evaluations for three of
the proposals, including the winning proposal. Because it did not
maintain proper documentation, CalVet cannot demonstrate that it
complied with state contracting requirements. Additionally, CalVet
accepted and approved for payment claims totaling $733,000 for
some of its key system implementation deliverables even though
it could not provide adequate documentation of receiving these
final deliverables.
Finally, although CalVet conducted lessons‑learned sessions at
various points throughout the project, it cannot demonstrate it
used those lessons learned to make improvements in its subsequent
implementation. CalVet did, however, capture final lessons learned
and has an opportunity to incorporate these lessons in the future.
Recommendations
CalVet
To ensure that its project management of IT projects promptly
identifies potential problems and develops resolutions, by
September 2016 CalVet should define the project executive and
project manager responsibilities to ensure that the individuals who
fill those positions take an active role in each project.
To ensure that it adequately identifies and monitors problems in
its future IT projects, by September 2016 CalVet should establish
a formal process for its project executive to verify that the project
team prepares all of the required project management plans and
other required plans. This formal process should also include a
process to periodically verify that the project team is adhering to all
these plans.
To ensure accountability and independence between the provision
of IPO and IV&V services on future IT projects, by September 2016
CalVet should establish a policy requiring it to use separate
contractors for IPO and IV&V services when IPO services are not
provided directly by the Technology Department.
To ensure that it complies with state contracting laws and can
demonstrate the basis for its decisions when awarding contracts, by
September 2016 CalVet should establish a process to periodically
verify that its staff follow state contracting requirements and
maintain all required contract documentation.
California State Auditor Report 2015-121 5
June 2016
To ensure that it only accepts and pays for deliverables that
are complete and that meet the contract requirements, by
September 2016 CalVet should establish a process to verify
and maintain documentation of all contract deliverables before
approving payment.
To ensure that it maximizes its opportunity to successfully
implement future IT projects, by September 2016 CalVet should
establish a formal process to verify that its staff conduct lessons
learned sessions for all key phases of future projects.
Technology Department
To ensure that it can demonstrate that it is acting in the best
interest of the State, by December 2016 the Technology Department
should create a formal process to summarize its involvement
and document key actions taken and decisions reached during
agencies’ contract disputes and negotiations for the termination of
a contract and maintain those documents according to its records
retention schedules.
Although the Technology Department indicated that its intent
is not to outsource its statutory responsibility for IPO, in any
instances when its staff conduct a portfolio review of a project’s
IPO, the Technology Department should, by December 2016,
establish a process for its review of documents the agency’s IPO
contractor creates that verifies whether these reports include
critical analysis of project progress and vendor performance so that
it can intervene when necessary.
Agency Comments
CalVet indicated it understands and agrees with each of our
recommendations and plans to have several completed by
September 2016. The Technology Department agreed with
our recommendations and indicated it will take steps to
implement them.
6 California State Auditor Report 2015-121
June 2016
Blank page inserted for reproduction purposes only.
California State Auditor Report 2015-121 7
June 2016
Introduction
Background
The mission of the California Department of Veterans Affairs
(CalVet) is to serve California’s veterans and their families. Further,
the mission of CalVet’s veterans homes is to provide the aged
and disabled veterans residing in the State’s eight veterans homes
(residents) with rehabilitative, residential, and medical care and
services in a homelike environment. The eight veterans homes are
located in Yountville, Barstow, Chula Vista, Ventura, Lancaster,
West Los Angeles, Fresno, and Redding. As of the end of 2015, they
had the budgeted capacity to care for more than 2,300 veterans.
Figure 1 on the following page shows the timeline of the opening of
each of the homes.
CalVet’s veterans homes provide different levels of care to their
residents, including domiciliary care, residential care for the elderly,
intermediate nursing care, and skilled nursing care. In addition,
CalVet provides on‑site outpatient clinics at all of its homes as
a service to its residents. These clinics provide comprehensive,
multidisciplinary assessments as well as ongoing primary care to
address residents’ routine medical needs. Table 1 shows the levels of
care available at each of the homes.
Table 1
Levels of Care Available at the California Veterans Homes
LOCATIONS OF THE VETERANS HOMES
WEST
LEVEL OF CARE YOUNTVILLE BARSTOW CHULA VISTA LANCASTER VENTURA LOS ANGELES FRESNO REDDING
Domiciliary care:
Minimum care and supervision for members who are
able to perform all the activities of daily living.
Residential care for the elderly:
Provides assistance and supervision to members in
activities of daily living.
Intermediate nursing care:
Provides skilled nursing supervision and supportive
care to members on less than a continuous basis.
Skilled nursing care:
Provides skilled nursing and supportive care to
members on an extended basis, including 24-hour
inpatient care, with medical, nursing, dietary,
pharmaceutical, and rehabilitation services, and an
activity program.
Sources: California Department of Veterans Affairs’ website, Titles 12 and 22 of the California Code of Regulations.
wal wal wal wal wal
Rene Rene Rene Rene Rene
8 California State Auditor Report 2015-121
June 2016
Figure 1
Location of California Veterans Homes and Timeline of Opening Dates
Fresno, Redding— 2013
West Los Angeles, Lancaster, Ventura— 2010
Chula Vista— 2000
Barstow— 1996
Yountville— 1884
SRAEY
211
RREEDDDDIINNGG
YYOOUUNNTTVVIILLLLEE
FFRREESSNNOO
BBAARRSSTTOOWW
LLAANNCCAASSTTEERR
WWEESSTT LLOOSS AANNGGEELLEESS
VVEENNTTUURRAA
CCHHUULLAA VVIISSTTAA
Source: California Department of Veterans Affairs’ website.
History and Evolution of the Enterprise-Wide Veterans Home
Information System
In late 2006, to support the health care information needs of its
planned five new veterans homes and its three existing homes,
CalVet sought approval for a new information system that could be
California State Auditor Report 2015-121 9
June 2016
used across its eight homes as well as in its headquarters. Former
state policy required agencies wishing to launch an information
technology (IT) project to prepare a feasibility study report
(FSR) that describes the relative need for, cost of, and benefits
to be derived from the proposed IT investment. The FSR for the
proposed Enterprise‑Wide Veterans Home Information System
(system) indicated that the new system would replace an existing
implementation of Meditech, a commercial software product that
CalVet had used since 1996 to support acute care, ambulatory
care, and long‑term care operations at its homes. The FSR defined
acute care services as hospital‑like services oriented toward clinically
complex patients who need a high level of care; ambulatory care as
care provided on an outpatient basis, similar to that provided by a
physician’s office; and long‑term care as care delivered over a longer
period of time and that includes skilled nursing home, rehabilitation,
assisted living, and other services. The FSR stated that the primary
reason for the limited use of Meditech was that the software lacked
specific functionality for supporting long‑term care operations.
In its FSR, CalVet further indicated that considerable technical
progress had occurred since the Meditech system was originally
installed and that systems were available that could provide
coverage across all care settings that CalVet offered. CalVet
indicated that newer systems provided improved efficiency, better
clinical documentation, and automated medication orders with
edits to prevent common medication errors.
The proposed new system was intended to be a
Key Business Opportunities of the
catalyst to transition CalVet from semi‑autonomous
Enterprise-Wide Veterans Home
homes to an eight‑home integrated system of Information System
care. As shown in the text box, in its FSR CalVet
described the key business opportunities to be • Improve care management by providing information on
realized from the new system. care quality and efficiency.
• Improve clinical quality, regulatory compliance, and
According to the FSR, CalVet’s implementation of reimbursement by improving clinical documentation.
a new system presented an opportunity to take an
• Reduce vulnerability to local disasters by reducing
affirmative step toward its vision of ensuring that
reliance on paper records.
veterans receive consistent and integrated care
in any CalVet health care facility in California. Source: Enterprise-Wide Veterans Home Information System
Feasibility Study Report.
It indicated that with the Meditech system,
when a veteran transferred between facilities,
staff at the new facility were unable to access the
veteran’s medical history electronically. This lack of access to care
information across facilities hampered clinicians’ ability to provide
optimal care and led to increased costs, among other effects.
For example, CalVet noted that patients’ tests might need to be
repeated when information was not available. The new system was
also intended to eliminate the need for cumbersome workarounds
and unnecessary paperwork, to automate medication orders, to
10 California State Auditor Report 2015-121
June 2016
reduce the potential for medication errors, and to improve the
quality of care veterans receive. The FSR estimated the cost of
the system at nearly $34 million and gave a projected completion
date of December 2010.
In January 2007, the California Department of Finance (Finance)
approved CalVet’s FSR for the system. By the time CalVet issued its
first special project report (SPR) for approval in August 2008, the
project was already experiencing significant delays.1 The FSR stated
that CalVet would release the vendor request for proposal (RFP) in
September 2007, but delays occurred in the review, validation, and
updates to the original system requirements. Further, CalVet added
two additional homes (Fresno and Redding) to the scope of the
project. These changes, in part, required the creation of the first SPR.
Additionally, CalVet took more than six months longer than planned
to contract for independent project oversight (IPO) and independent
verification and validation (IV&V) services. The SPR indicated that
the new release date for the RFP would be November 2008, a delay
of 14 months; however, the RFP was not actually released until
February 2009, a further delay of three months.
Although the RFP was issued, it was canceled in June 2009, as
described in the second SPR that CalVet submitted, because only
one vendor submitted a proposal and that proposal did not address
all of the required system functionality. A request for information
(RFI) was issued in July 2009 to a broader vendor pool to determine
their ability to meet CalVet’s system requirements. The outcome
of the RFI indicated that none of the vendors could meet all of
CalVet’s mandatory requirements; as a result, CalVet revised the
RFP. For instance, according to the second SPR, the revised RFP
listed significantly fewer mandatory requirements and contained
a new “highly desirable” category of requirements that were not
mandatory. The second RFP was released in November 2009. In
December 2010, CalVet awarded the project to Solutions West
Consulting, LLC (Solutions West; later Brekken Technology, Inc.) as
its system contractor. The project was contained in two contracts.
The first contract and two subsequent contract amendments of
work included the purchase of system hardware and software, the
installation and configuration of the system, and the training of
CalVet staff on how to use the new system. The second contract
provided for the post‑implementation maintenance and support
services for the system by the system contractor. CalVet’s third and
final SPR, in January 2013, adjusted the projected cost of the system
to $36.7 million.
1 An SPR provides a summary of proposed changes to the original project cost, schedule, or scope.
It is generally required when the project cost or total financial program benefits deviate or are
anticipated to deviate from the original by 10 percent or more, or when a major change occurs in
project requirements or methodology.
California State Auditor Report 2015-121 11
June 2016
CalVet’s headquarters and its homes in Barstow, West Los Angeles,
Lancaster, and Ventura started using selected modules of the
system during the system’s pilot implementation in May 2012.
The home in Chula Vista implemented and began using the
system in June 2013. The final three homes—in Yountville, Fresno,
and Redding—implemented and began using modules of the
system in November 2013. The eight homes’ use of the system
modules currently varies. According to the manager of the project
management office (PMO manager) of CalVet’s Information
Services Division (ISD), the system was not fully implemented and
used at all of the homes because of certain functionality problems
staff experienced with the system.
Although both CalVet and the California Department of
Technology (Technology Department)—the department that
now has responsibility for oversight of state IT projects—had
identified project delays during the development and early
implementation of the system, according to CalVet’s June 2015
response to questions from the Legislature regarding the project,
new leadership in CalVet’s ISD reported critical project problems
to the Technology Department in December 2013.2 According to
the final project manager for the system, CalVet identified these
problems in late 2013 through a review of outstanding unpaid
invoices, many of which lacked sufficient documentation to
support the work performed. The June 2015 response document
stated that the critical project problems CalVet identified related
to project oversight, project management, contract management,
contract deliverables, and the viability of the system contractor. The
response document noted that to resolve these deficiencies, CalVet
effectively suspended the project in December 2013 and, after a
12‑month period for reevaluation and remediation, terminated the
implementation contract with the system contractor and a system
support contract with the software vendor in December 2014. The
response document also stated that CalVet and the Technology
Department mutually agreed to close out the system project
in January 2015. CalVet agreed to pay the system contractor
$350,000 to settle the implementation contract. By the time CalVet
reached its settlement agreement with the system contractor, it
had spent $26.2 million, including the settlement costs. These
costs had increased to $27.9 million when CalVet completed its
post‑implementation evaluation report in June 2015. Figure 2
on the following page shows key milestones during the course of
the project.
2 Until July 2013 the Department of Technology was known as the California Technology Agency,
and before that, it was the Office of the Chief Information Officer.
12 California State Auditor Report 2015-121
June 2016
Figure 2
Enterprise-Wide Veterans Home Information System Project Timeline
2007
January 2007
Indicates project oversight’s identification of 2007
I s n y d st isc e ya m tse o tse r p p mr r o o j e j o e c c rt t po c v o reo n r c sj e ieg r ch n tt s ’ . sc iodenncteifircnatsio.n of J C a al n ifo u r a n r ia y D 2 e 0 pa 0 r 7 tment of Finance C ap al p if r o o r v n e i d a D fe e a p si a b r i t l m ity e n st t u o d f y F r in ep an o c r e t (FSR)
approved feasibility study report (FESsRt)i mated project cost: $34 million
Estimated project cost: $34 million
2008 Decemb2e0r 200087 December 2007
California Department of VeteransC Aafflaiifros (rCnailVae Dt) epartment of Veterans Affairs (CalVet)
contracted for independent project
oversight and independent verificactoionntracted for independent project
and validation services oversight and independent verification
2009 and validation services
January 2009
The Office2 of0 th0e S9tate Chief Information Officer
(OCIO) approved special project reJpaornt (SuPRa) r1y 2009
Estimated project cost: $35.5 million
The Office of the State Chief Information Officer
November 2009 (OCIO) approved special project report (SPR) 1
2010
CalVet published its request for pro Epsotsiaml (aRFtPe)d project cost: $35.5 million
November 2009
2010
December 2010 2011 November 2010 CalVet published its request for proposal (RFP)
Department of General Services OCIO approved SPR 2
(General Services) approved the Estimated project cost: $37.3 million
implementation contract
December 2010 February 2012 November 2010
May 2012 2012 General S2erv0ice1s a1pproved the maintenance and
Pilot implementation at hDeeadpqauratrmteres,n Bta rostfo Gw,e neral Services support contract with the system cOonCtIrOac taoprproved SPR 2
West Los Angeles, Lancaster(, Ganedn Veernatul rSa eacrcveipcteeds) approved the June 2012 Estimated project cost: $37.3 million
implementation contract CalVet identifies that it is having issues
August 2012 with the pharmacy implementation in an
California Department of Technology 2013 executive steering committee (steering
(Technology Department) January 2013 committee) meetinFgebruary 2012
identified project schedule February 2013
variance a n m d i s o s v e e d r s b i y g P h p t i r l o c o o je t n c t i t r m a te c a p to m l r emen C c a to l a V mt e im t o n int o t t ea e e d t m i h n e e a ea t s i t nd e gq e t r uh in aa g tr t M ers a , y Ba 2 rs 0 to 1 w 2 , T E e st c i h m n a o te lo d g p y r o D j e e p c 2 t a c r0 o tm st 1 : e $ n 3 2t 6 a .7 p p m r i o ll v io e n d SPR 3G s u e p n p e o ra rt l S co er n v t i r c a e c s t a w p i p th ro t v h e e d s y th st e e m m a c in on te t n ra a c n t c o e r and
West Los Angbe B el a ien rs gs t , o d L w roa h pn a p s ce m ad s e frt d oe i m c r a , t ta i h o ne n sd o y r sV d te e em r n s tura accepted June 2013 June 2012
Completed implementation at Chula Vista
CalVet identifies that it is having issues
NoAveumgbuesr t2 0210312
with the pharmacy implementation in an
Completed implementation at
California DFerepsnaor, tRmedednintg o, afn dT Yeocuhnntvoillleogy 2013 December 2013 executive steering committee (steering
(Technology Department) January 2014 2014 CalVJeat rnepuoraterd ycr it2ic0al 1co3ncern toc ommittee) meeting
va Ca ri lV a e n itd c see ei a n n n n m t a t a d d i i fic iss o u s e p r v eu ed e td l e e r p t s bb tr i e eo y g t r w j h t p eo e t r c e t o c ht n e o j s Ce s n c ac yh l t s Vt r te e e a tt dm e c aa u t n c o md ole n r t h tr e a c s t y o s r t e w C m c h a i o c l c o V h m n e r t e m r t a s Fu n c i t l t e o t o t e r t b e d * e e r d u m in a e a r e y t s i t n 2 e g e 0 t r 1 h in a 3 g t F T d h i e s e c b u T r s e u s c i h a o n n r o y s l – b o e M g t y w a D e r e e c p n h a C r 2 t a m l 0 V e 1 e n t 4 t a f n a d c ilitated t p r m e h r o s e o o v p T T E l i o e v n e s i c s g n t ce h i g f d n h mo c o p r n r wa l a i o o t u ta g ic e ls r y o a d i d n l D g g c p e o yt p r n h a o D c e r e j t ep e r m n rp c o e s t aj n b e c r t c e o t a t f m o n s a r t d n e : e d $ n 3 t 6 a .7 p p m r i o ll v io e n d SPR 3
May–August 2014 the system contractor
As directed by the Technology Departm
B
en
a
t
r
,
s
C
t
a
o
lV
w
et c
h
o
a
nd
s
u
m
cte
e
d
d ication orders JSuepnteem 2b0e1r 320 14
an assessment of the system to debteermininge dwrhoetphepre itd w afsr om the system CalVet suspended the use of
functioning properly and met CalVet’s needs * Cthoem orpdeler teentdry i fmunpctlieomnaelitnytation at Chula Vista
November 2014
November 20D1e3cember 2014 2015 Maintenance and support
• CalVet signed a maintenance and support contract with contractor expired
Completedco inmtrapclte wmithe tnheta etxiisotnin ga sto ftware vendor
Fresno, Redding, and Yountville December 2013
• CalVet, Technology Department, and the
contractor signed a settlement agreemeJnat. nuary 2014January 2015 2014 CalVet reported critical concern to
CalVet sent a cure l • e A t s t$ e o 2 f r6 t .t h 2o e m e tih n ll d ieo o ns f yo 2 sn 0 t 1 te 4 h me C a s l yc V so e t t en h mt a r p d a r s co p tj e eo n crt t which resulted C ag a r lV e e e t d a t n o d c l t o h s e e T o e u c t h t n h o e lo p g r y o j D ec e t p F† a e rtm b e r n u t m a u r tu y a – lly M arch 2014 t p h r e o p T o ec se h d n o p l a o u g s y i n D g e t p h a e r t p m ro e j n e t c a t n a d n d
in a dispute between CalVet and the system contractor*
The Technology Department facilitated resolving critical concerns before
discussions between CalVet and moving forward
May–August 2014 the system contractor
September 2014
As directed by the Technology Department, CalVet conducted
an assessment of the system to determine whether it was CalVet suspended the use of
functioning properly and met CalVet’s needs * the order entry functionality
November 2014
December 2014
2015 Maintenance and support
• CalVet signed a maintenance and support contract with contractor expired
contract with the existing software vendor
• CalVet, Technology Department, and the
contractor signed a settlement agreement.
January 2015
• As of the end of 2014 CalVet had spent CalVet and the Technology Department mutually
$26.2 million on the system project agreed to close out the project†
Sources: CalVet’s FSR and SPRs for the Enterprise-Wide Veterans Home Information System (system), FSR and SPR approval letters, contracts for the system, project
management documents, cure letter, the implementation contract settlement agreement, post-implementation evaluation report—June 2015, and the Technology
Department’s system briefing document.
* The cure letter identified the contract requirements that the system contractor had not met and required that the system contractor meet those requirements by
February 13, 2014.
† According to steering committee meeting minutes, direction was given to close out the system project through the post-implementation evaluation report (PIER)
and initiate efforts to replace the system. In June 2015 CalVet submitted its PIER to the Technology Department to support its request for the Technology Department
to consider the system project complete and to terminate project reporting. At that point, CalVet’s project costs totaled $27.9 million. According to CalVet’s deputy
secretary of veterans homes division, CalVet continues to use the system as best it can until it completes the process of finding a replacement system.
California State Auditor Report 2015-121 13
June 2016
Changing Roles and Responsibilities for Project Approval
and Oversight
Both the Technology Department and the Department of General
Services (General Services) have had certain responsibilities for
overseeing the State’s IT project procurements, and as shown in
Figure 3 on the following page, each entity’s roles have changed
since January 2007 when Finance approved CalVet’s FSR for the
system. Figure 3 also identifies the roles and responsibilities held by
oversight agencies at key milestones during the development and
implementation of CalVet’s system project. Effective January 2008,
a change in state law transferred the authority to approve, suspend,
or terminate IT projects from Finance to the Office of the Chief
Information Officer—the predecessor entity to the Technology
Department. In December 2010, when CalVet executed the
contract to develop and implement the system, General Services
had responsibility to review state agencies’ IT RFPs. Then state law
effective in 2011 required General Services and the Technology
Department to review all IT RFPs. Subsequent legislation operative
in July 2013 transferred General Services’ share of this authority as
well as General Services’ authority over IT project procurement
to the Technology Department. This shift in responsibilities
from General Services to the Technology Department, and the
increase in the Technology Department’s responsibilities, reflects
the Legislature’s conclusion that the unique aspects of IT projects
and their importance to state programs warrant a separate
acquisition authority.
State policy requires departments to implement independent
oversight for all reportable projects. The Technology Department,
which assumed IT project oversight responsibility under state law
effective in 2008, generally provides the IPO services while state
entities undertaking the IT projects are responsible to contract
for the IV&V services. IPO services provide an independent
review and analysis of project management practices to determine
if the project is being well managed. IV&V services provide
a client with technically proficient “eyes and ears” to oversee
a system vendor while an IT system is being developed and
implemented, and they also provide an early warning of process
and technical discrepancies, issues, and problems that might not
otherwise be detected until late in testing or implementation For
its system, CalVet contracted with a single outside consultant
(oversight contractor) to provide both IPO and IV&V services.
14 California State Auditor Report 2015-121
June 2016
Figure 3
Information Technology Roles and Responsibilities by Key Milestone for the Enterprise-Wide Veterans
Home Information System Project
California Department of Technology
California Department of Finance
(Technology Department)*
Department of General Services Shared
May 2012
First implementation of the Enterprise-Wide
Veterans Home Information System
December 2013
January 2007 November 2009 Second contract
Feasibility study RFP amendment
report approved December 2010
January 2015
Contract awarded
California Department
July 2011 of Veterans Affairs and
the Technology
First contract
Department mutually
amendment
agree to close project
Information
Technology (IT)
Project Approval
and Oversight†
Review of
IT Request for
Proposal (RFP)
Review of
IT Project
Procurement
2007 2008 2009 2010 2011 2012 2013 2014 2015
Sources: Government Code, sections 11545 and 11546 and Public Contract Code, sections 12100 and 12104.
* Until July 2013, the Technology Department was known as the California Technology Agency and before that the Office of the State Chief
Information Officer.
† IT project approval and oversight include numerous activities, such as evaluating IT projects based on the business case justification,
resource requirements, proposed technical solution, project management, oversight and risk mitigation approach, and compliance with
statewide strategies, policies, and procedures.
California State Auditor Report 2015-121 15
June 2016
Scope and Methodology
The Joint Legislative Audit Committee (audit committee)
directed the California State Auditor to conduct an audit of the
development and implementation of CalVet’s Enterprise‑Wide
Veterans Home Information System. Table 2 outlines the audit
committee’s audit objectives and our methods for addressing them.
Table 2
Audit Objectives and the Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, rules, • Reviewed relevant laws, rules, and regulations.
and regulations significant to the • Reviewed relevant state policies regarding procurement and information technology (IT) projects.
audit objectives.
2 Evaluate the level of oversight the • Identified requirements for oversight of development and implementation of IT projects.
California Department of Veterans • Obtained and reviewed documentation related to CalVet’s project management and other
Affairs (CalVet) management required plans to determine compliance with the California Project Management Methodology.
exercised regarding development
• Obtained and reviewed executive steering committee (steering committee) meeting minutes to
and implementation of the
determine the extent of oversight by CalVet’s management, and involvement and decision making
Enterprise-Wide Veterans Home
by its executive office related to its system project.
Information System (system),
including whether the executive office • Obtained and reviewed independent project oversight (IPO) and independent validation and
was involved in making key decisions verification (IV&V) reports prepared by CalVet’s oversight contractor to determine whether IPO and
and ensuring that the system met the IV&V services were provided over the course of the system project and that they adhered to state
needs of the veterans homes. policy and contractual requirements.
• Our IT expert identified requirements traceability monitoring as an important function of IV&V.
Because he did not see evidence that this function was performed by CalVet’s oversight contractor,
we obtained and reviewed invoices approved for payment and requested that CalVet provide us
with evidence of an accepted deliverable for proof that this work was performed.
• Interviewed key staff at CalVet to understand its oversight role.
3 Assess whether CalVet followed laws, • Identified relevant laws, regulations, and policies regarding the selection of the contractor to
rules, regulations, policies, and best implement CalVet’s system.
practices when selecting vendors • Obtained documentation to confirm CalVet’s request for proposals (RFP) was properly advertised
for the system, including, to the in the California State Contracts Register.
extent possible, those prohibiting
• Requested and reviewed the proposals CalVet received in response to its RFP for implementation
a conflict of interest during the
of its system and documentation for the evaluations of the proposals.
selection process.
• Requested and reviewed CalVet’s Statement of Incompatible Activities (SIA) and
Conflict-of-Interest Code.
• Requested and reviewed the California Fair Political Practices Commission’s Statements of
Economic Interests (Form 700) for applicable staff that participated in the selection of the system
contractor. The forms we obtained did not identify any reported conflicts.
• Requested and reviewed CalVet’s certified SIAs for members of the committee selecting the
contractor implementing the system. The forms we obtained did not identify any reported
incompatible activities. Interviewed key individuals at CalVet to determine whether any additional
methods existed at CalVet to determine potential conflicts of interest.
continued on next page . . .
16 California State Auditor Report 2015-121
June 2016
AUDIT OBJECTIVE METHOD
4 Determine the estimated and actual • Reviewed documentation to determine the approved project cost estimates.
implementation costs and timeline • Obtained California State Accounting and Reporting System (CalSTARS) accounting records to
for the system as well as the number identify the project’s total cost, as reported in CalSTARS.
of and reasons for change orders and
- Estimated and actual implementation costs are located in Table A.1 in Appendix A.
contract amendments.
• Reviewed project documentation to determine the estimated project implementation timelines
and the actual implementation timeline.
- Estimated and actual implementation timelines are located in Table A.2 in Appendix A.
• Reviewed the two contract amendments to determine the reason for each.
- The first amendment increased the contract costs to include unanticipated tasks—as permitted
by the contract—and made minor changes or clarifications to the scope of work.
- The second amendment extended the contract by one year, updated the statement of work
to reflect the system contractor’s name change, and updated the contact information for the
project site coordinators.
• Reviewed the list of change requests and determined that there were 304 approved
change requests. We reviewed a total of 64 change requests to determine the reason for the
changes including all change requests categorized as a significant change, a portion of those
categorized as a minor change, and a portion of those that were uncategorized. We identified five
main reasons for the change requests we reviewed:
- Contract language update or clarification.
- Deliverable or requirement change.
- Requirement start or due date change.
- System enhancement or software change.
- Business process change.
5 Determine whether the original • Interviewed key staff at CalVet to determine whether the system contractor met all
project requirements, as defined by contract requirements.
the scope of work, were delivered • Compared the original statement of work to each amended statement of work to determine what
during implementation of the changes were made to the project requirements.
system project.
• Reviewed change requests to determine how those changes affected the original requirements.
• Reviewed selected contract deliverables documentation (that is, deliverable expectation
documents and deliverable acceptance documents) for the 33 deliverables to assess whether the
system contractor met the project requirements, as defined by the statement of work.
• Reviewed CalVet’s post-implementation evaluation report and steering committee
minutes to determine the cause for any gaps between the contract requirements and the
deliverables documentation.
6 Evaluate the steps CalVet took when • Reviewed CalVet’s executive summary reports, project status reports, special project reports, and
project variances were identified. IPO and IV&V reports to determine when CalVet identified project variances and what steps Cal Vet
To the extent possible, determine took to address those variances.
whether CalVet could have identified • Interviewed key staff at CalVet.
problems with the system earlier.
• Provided the IPO and IV&V reports to our IT expert for his professional opinion as to whether
CalVet should have identified problems with the system earlier.
7 Review the role of the California • Reviewed relevant laws and policies to identify the Technology Department’s oversight
Department of Technology responsibilities throughout the life of the system project.
(Technology Department) in this • Interviewed key individuals at the Technology Department to determine the Technology
project and evaluate whether it Department’s role throughout the life of the system project.
fulfilled its roles and responsibilities.
• Requested and reviewed documentation from the Technology Department to determine the
extent of oversight it provided to CalVet and whether it fulfilled its oversight responsibilities.
California State Auditor Report 2015-121 17
June 2016
AUDIT OBJECTIVE METHOD
8 Determine the steps CalVet has • Interviewed key project management at CalVet headquarters and the homes and reviewed
taken to improve the functionality available documentation to gain an understanding of the following:
of the system and what affect - The system’s lack of functionality.
any lack in functionality has had
- The impact the lack of functionality has on the homes’ quality of care and cost and efficiency.
on quality of care and cost and
efficiency of the homes’ operations. - Steps CalVet has taken to address the lack of functionality.
In addition, determine whether • Reviewed documentation related to lessons learned to determine what changes, if any, CalVet
CalVet has documented lessons made as a result of the lessons learned.
learned for use in future phases of
system implementation.
9 Identify the level of system • Interviewed key staff at CalVet and the eight veterans homes.
functionality and use within CalVet’s • Obtained a list of system functionality implemented and used at headquarters and each veterans
veterans homes and administrative home. We asked staff at headquarters and each home to verify their use of system components.
offices and evaluate CalVet’s efforts
• Reviewed training documentation for a selection of training course evaluations from CalVet and
to train staff and otherwise address
found generally positive comments about the training. We followed up with staff at the homes
resistance to using the system.
who mostly expressed positive comments about the training.
• Reviewed CalVet’s organizational change management strategy to address resistance to the
system brought about by organizational change. We followed up with staff at the homes and
found that, in general, staff indicated that there was buy in to the system.
10 Review and assess any other issues • Interviewed key staff at the Technology Department to understand its facilitation of the contract
that are significant to the audit. disputes between CalVet and the system contractor.
• Obtained and reviewed documentation to assess whether the Technology Department’s actions as
the dispute facilitator were in the best interests of the State.
Sources: California State Auditor’s analysis of the Joint Legislative Audit Committee’s audit request number 2015-121, and information and documentation
identified in the column titled Method.
Assessment of Data Reliability
In performing the audit, we obtained financial records from the
California State Accounting and Reporting System (CalSTARS) for
CalVet’s expenditures related to its system. The U.S. Government
Accountability Office, whose standards we are statutorily required
to follow, requires us to assess the sufficiency and appropriateness
of the computer‑processed information that we use to support
our findings, conclusions, and recommendations. Specifically,
we used expenditure reports from CalSTARS from July 2007 to
June 2015. For each fiscal year, we used these data to report CalVet’s
total expenditures for its system implementation. However, we
did not conduct accuracy or completeness testing on these data
because, in accordance with its records retention policy, CalVet
did not maintain source documents for many of its historical
transactions that we would need to test. As a result, any testing we
performed would be incomplete. Further, CalVet stores the source
documents it does maintain at locations throughout the State,
making this testing cost‑prohibitive. Thus, we determined that
the State’s CalSTARS data were of undetermined reliability for
the purposes of this audit. Although this determination may
affect the precision of the numbers we present, there is sufficient
evidence in total to support our audit findings, conclusions,
and recommendations. To gain some assurance of the accuracy of
18 California State Auditor Report 2015-121
June 2016
CalVet’s system transactions recorded in CalSTARS, we tested a
selection of expenditures and hours worked for fiscal years 2013–14
and 2014–15, and we determined that CalVet accurately recorded
the transactions we reviewed.
California State Auditor Report 2015-121 19
June 2016
Audit Results
The Enterprise-Wide Veterans Home Information System Does Not
Meet the Needs of the Veterans Homes
The California Department of Veterans Affairs (CalVet)
implemented the Enterprise‑Wide Veterans Home Information System
(system), but the system does not meet the original primary goals of
the project. In its feasibility study report (FSR) requesting approval
for the system, CalVet described the need for an information system
that would improve the quality of care delivered to veterans by making
its clinical documentation process more efficient; reducing reliance
on paper records; providing a consistent, safe, integrated system of
care; and improving regulatory compliance. However, the system
implemented did not achieve those improvements.
The System Has Not Achieved Key Project Objectives of Improving
Efficiency and Improving Quality of Care to Veterans
The system implemented has not improved the efficiency of the
homes’ clinical documentation process or reduced their reliance
on paper records because of flaws that staff encountered with the
system. The administrators from four of the veterans homes, which
use a majority of the system’s modules, including ADL Clinical—a
main module of the system that the homes use to manage electronic
health records—identified shortcomings with how the system
works and indicated that the system is not user‑friendly or intuitive.
Specifically, some of the administrators told us that the system is
difficult to navigate and results in staff spending unnecessarily long
amounts of time locating or entering information multiple times
into residents’ patient care records.
The chief medical officer at the home in Chula Vista told us that
because of concerns staff had about the functionality of the system,
given the numerous problems they experienced while using it, he
had the staff conduct time studies of some routine tasks in July and
early August 2013. Specifically, in a document he provided to CalVet
headquarters, he described that staff in four departments performed
five different routine tasks and the results revealed that these tasks
required approximately twice as much time on average after the
system was implemented. For example, a registered nurse determined
that it took 105 minutes to conduct a new resident’s initial assessment
using the system, compared to the 30 minutes for the same
task before the system was implemented. In another example, a
pharmacist found that it took seven minutes to process a medication
order using the new system, a task that required 3.5 minutes
before the system was implemented. Despite these concerns, in
late August 2013 CalVet’s then‑undersecretary of Veterans Homes
20 California State Auditor Report 2015-121
June 2016
responded that the time it was taking staff to complete processes
with the system would likely decrease over time as they became more
comfortable with the system and refined the business processes.
In addition to the extra time it was taking them to complete tasks
using the system, staff found that they had to enter the same
resident information into multiple modules of the system to provide
care to the residents. The administrator at one home stated, for
example, that when a home receives a new resident, staff must
enter the resident’s information into the system’s admission module
before they can admit the resident. A nurse then has to reenter that
same information into the system’s assessment module before staff
can conduct the assessment of the resident. Staff also reported that
some system functions would regularly freeze or lock up during use.
In one extreme instance, the entire system was down for more than
a week at the end of August and beginning of September 2013.
Because of continuing concerns, in mid‑2014 CalVet conducted an
assessment of the system to determine if it was functioning properly
and if it met the quality and needs of CalVet. In its response to
CalVet’s assessment, the system contractor indicated that a majority
of the more than 500 items identified required setup and training,
and many other items could be resolved through enhancements.
Further, the system contractor stated there were a dozen identified
bugs or issues and that it needed clarification on about 100 items.
CalVet’s final project manager stated that the system problems the
homes experienced—for example, system slowness and freeze‑ups—
were a result of the system’s poor architecture and configuration.
Administrators of the homes Administrators of the homes indicated that at times, they resorted
indicated that at times, they to manual processes to manage patient care because of the problems
resorted to manual processes to they encountered with the system. Two of the five homes that use
manage patient care because of the the system’s ADL Clinical functionality—Barstow and Ventura—
problems they encountered with indicated that staff reverted back to paper processes when the system
the system. freezes or crashes. In fact, the management of the Ventura home
stated that staff use paper documentation as a backup because they
do not trust the system to work properly. Two other homes that use
the system’s ADL Clinical module—the Chula Vista and Lancaster
homes—also indicated that staff use paper documentation in
addition to the electronic system for assurance. For the remaining
three homes—those that use only a minimal number of the ADL
Clinical module’s components—two stated that they continue to
use paper records for clinical documentation while the third home
continues to use the old system—Meditech—and other workarounds.
When we asked CalVet about how these functional problems have
affected the quality of care veterans receive, its deputy secretary
of Veterans Homes stated that the quality of care has not changed
and that the homes continue to pass surveys performed by the
United States Department of Veterans Affairs and the California
California State Auditor Report 2015-121 21
June 2016
Department of Public Health with the system in place. However, he
added that the system is not maximizing efficiency because nurses
are having to spend more time entering information in the system,
limiting the time they are able to spend with residents. Therefore,
we believe the overall quality of care provided to the veterans is
negatively affected by these inefficiencies because of the increase in
time that staff spend using the system.
Additionally, staff have encountered serious problems while using
the order entry component—the system component that staff use
to place a resident’s medication order—that have created a risk of
harm to the residents. Specifically, staff reported problems that Staff reported serious problems
included the system recording incorrect medication dosages on with the system’s medication
prescriptions, failing to notify staff that a resident was allergic order entry module that
to a medication, and failing to note verification of whether the included the system recording
pharmacy had received prescription orders, resulting in the system incorrect medication dosages on
not placing medication orders. For example, in March 2014, staff prescriptions and failing to notify
in one home placed on hold a resident’s medication to lower her staff that a resident was allergic to
cholesterol, and the system automatically expired the medication a medication.
order after seven days because staff did not release the hold. Staff
reported to the chief medical officer that the system did not alert
the nursing staff that the medication order had expired, and as a
result, the resident did not receive her medication for five months.
In another example, the administrator at the Ventura home stated
that although a veteran’s allergies are recorded in one module of the
system, the system does not alert the nurse if a medication to which
a resident is allergic is entered in the medication order module.
In August 2014, staff at another home reported that a resident’s
order for eye drops to treat glaucoma dropped from the system
and the patient did not receive the drops for two months; the staff
at the home were not aware that the resident was missing the eye
drop medication until his son notified them. In response to these
types of problems, CalVet suspended the use of the medication
order entry module of the system in September 2014.
As CalVet identified during its assessment of the system in 2014,
staff have to enter patient information more than once and they
have encountered various problems in the medication order
entry functionality. According to the final project manager,
these problems occurred because the system contractor did not
configure the system correctly. In April 2015, ADL—the software
provider—also communicated to CalVet that based on its work to
resolve outstanding trouble tickets over the past three months, it
had concerns with the system’s configuration during installation
and with the instruction of CalVet staff on the proper setup and
implementation of the software. Our information technology (IT)
expert reviewed the system’s draft configuration document and
determined that it was incomplete and could not be reviewed for
quality or correctness. He also noted that the draft architecture
design document was incomplete and insufficient and would likely
22 California State Auditor Report 2015-121
June 2016
be a source of implementation problems. However, as we describe
later in this report, it was CalVet’s responsibility to monitor its system
contractor’s performance and to ensure that the system contractor
provided deliverables consistent with the terms of the contract.
The Veterans Homes’ Use of the System’s Modules Varies
The system has also failed to serve as the integrated system of
care that CalVet had planned and expected. CalVet envisioned its
integrated system of care as enabling any veterans home to operate
seamlessly with any other home, providing access to care information
should a veteran move between homes. Because of the problems
with the system, however, CalVet implemented only a portion of
the system at the last three homes to receive it. According to the
final project manager, headquarters and all of the homes received all
modules of the system software but some did not receive training
on all modules. He stated that when some of the planned tasks,
such as training, are not completed, the module is not considered
fully implemented. Specifically, three homes—Fresno, Redding,
and Yountville—confirmed that although CalVet installed the
ADL Clinical module, their staff either did not receive training on
it or received training on only a minimal number of the module’s
components. Additionally, according to CalVet’s deputy secretary
of Veterans Homes, because of the problems the homes have
encountered with the system, CalVet allowed individual homes to use
the system’s modules in ways that worked best for each one.
Because CalVet did not overcome CalVet’s decision to halt the training and limit the use of a system
the problems with the system’s module that was not fully working and to allow each home to use the
functionality, it failed to achieve modules that worked best for that particular home is understandable
its goal of having a fully integrated given the significance of the problems the homes were experiencing.
system of care in which the However, because CalVet did not overcome the problems with the
homes’ use of the system is system’s functionality, it failed to achieve one of its primary goals: a
standardized and veterans receive fully integrated system of care in which the homes’ use of the system
consistent care. is standardized and veterans receive consistent care. For example, as
we discussed in the Introduction, CalVet’s FSR stated that under the
previous system, when a resident transferred to another home, the
staff at the new facility were unable to access the individual’s medical
history electronically, hampering their ability to provide optimal care
and increasing costs. In addition, the FSR indicated that increasing
the amount of clinical documentation that the homes recorded
electronically would improve CalVet’s ability to evaluate the outcome
of services and procedures. It also indicated that improved cost
reporting would enable CalVet to monitor and manage the costs of
services across different facilities. However, because the homes’ use
of the system’s modules varies and because the ADL Clinical module
was not fully implemented at all of the homes, the staff at the homes
cannot communicate with each other’s systems to share any necessary
resident information. Table 3 shows when CalVet implemented the
California State Auditor Report 2015-121 23
June 2016
system at its headquarters and each of the eight homes as well as the
extent of the system modules in use at each of those locations. Without
a fully integrated system that is used in a standardized way, the homes
cannot operate seamlessly with other homes and electronically share care
information as the planned integrated system envisioned.
Table 3
Enterprise-Wide Veterans Home Information System Module Use by Location and Date of Implementation
WEST
HEADQUARTERS, BARSTOW, CHULA VISTA, FRESNO, LANCASTER, REDDING, VENTURA, LOS ANGELES, YOUNTVILLE,
MAY 2012 MAY 2012 JUNE 2013 NOVEMBER 2013 MAY 2012 NOVEMBER 2013 MAY 2012 MAY 2012 NOVEMBER 2013
Multiple Component Modules
ADL Clinical (23 components)
Software designed to address critical functions of providing long-term care by capturing and managing patient information.
Fully (F) 1 14 9 1 11 2 13 11 3
Partially (P) 0 5 5 0 4 0 3 6 1
Not used (N) 2 3 8 0 3 0 2 5 0
Not Implemented (NI) 0 0 0 22 0 21 0 0 19
Not applicable (NA) 20 1 1 0 5 0 5 1 0
ADL Financial (36 components)
Software used to support third-party billing, Medi-Cal, Medicare, accounts receivable, transaction history, withdrawals and charges; making,
tracking, and controlling financial events.
Fully 12 30 29 23 13 24 26 21 29
Partially 7 3 4 5 11 5 2 7 2
Not used 1 3 3 6 10 5 6 8 2
Not Implemented 0 0 0 2 0 2 0 0 3
Not applicable 16 0 0 0 2 0 2 0 0
Single Component Modules
Dynamics
Financial accounting and business management software that automates creation and management of accounting data and workflow.
Used to augment ADL Financial to support financial management. The specific component used is for purchasing and inventory.
N F P F F F F F F
Gerimenu
Software used for resident meal planning to help facilities run their nutrition departments more efficiently.
NA P P F N NI N F P
Documentum
An enterprise content management system used to house and manage electronic documents.
N F N NI N NI F F NI
Framework LTC
Pharmacy management software designed for long-term care and institutional facilities.
NA F F NI N NI F F F
Sources: California Department of Veterans Affairs’ (CalVet) system use chart provided by system final project manager, and confirmed or updated by
staff at headquarters and the eight homes, draft system architecture design document, and the CBORD Group Inc. Gerimenu website, and contractor’s
response to the request for proposals.
Note: A complete table of system use by components is located at Table B in Appendix B.
F = The veterans home indicated it fully used this module.
P = The veterans home indicated it partially used this module.
N = Although CalVet implemented the module, headquarters or the veterans home indicated it did not use it.
NI=CalVet did not implement the module at the veterans home.
NA= Although these modules were available for use, staff at headquarters or the homes indicated that components marked NA were generally not
applicable for their operations.
24 California State Auditor Report 2015-121
June 2016
CalVet’s Assessment Results Overstated System Compliance Concerns
In a June 2015 response to questions it received from the
Legislature, CalVet included the results of its assessment of the
system and identified several areas in which its system was not
complying with the provisions of certain federal and state laws and
regulations. However, we found that CalVet is compliant with the
laws and regulations it identified or, in one instance, can take steps
to avoid reductions to federal reimbursements.
Although CalVet indicated that the Although CalVet’s assessment results indicated that the system
system does not comply with HIPAA does not comply with the federal Health Insurance Portability and
regulations related to its ability to Accountability Act (HIPAA) regulations related to its ability to audit
audit record activity, we found that record activity, we found that it is compliant. The HIPAA privacy
it is compliant. and security regulations require covered entities to implement
appropriate administrative safeguards to ensure the protection of
electronic personal health information. The regulations require,
among other things, the implementation of audit controls, such as
audit logs that record and examine activity in information systems
that contain or use protected electronic health information. CalVet
indicated that the system’s limited ability to audit health record
activity makes it noncompliant with HIPAA. Specifically, according
to CalVet’s agency information security officer, rather than having
the ability to access audit logs directly from its system, CalVet must
request audit logs from the software provider. Additionally, CalVet’s
chief information officer stated that based on her experience, the
time it takes the software provider to produce the logs for CalVet
is unreasonable. However, the assistant director of the State of
California Office of Health Information Integrity—which has
statutory oversight of state entities’ HIPAA compliance—stated that
as long as CalVet can request and receive audit logs, it is compliant
with that requirement of HIPAA.
Additionally, CalVet indicated that the system does not comply
with federal and state laws that prohibit the use of color coding in
federal and state agency information systems as the only means
of conveying information. For example, a form that requires a
user to complete only the areas in red would be noncompliant.
CalVet identified a concern that critical on‑screen indicators
within the system are coded based on color, and these indicators
do not work for individuals who are color blind. However, in each
example CalVet provided to us from the system, we found that
the color coding was in addition to another means of conveying
the information. For example, a patient’s discharge date is listed
in red to indicate that the patient has been discharged; however,
the existence of a discharge date would notify a staff member
that the patient has been discharged; thus, the system does not
California State Auditor Report 2015-121 25
June 2016
rely solely on color coding to convey that information. As a result,
CalVet could not demonstrate that the system inappropriately relied
on color coding.
Further, a key provision of the American Recovery and
Reinvestment Act of 2009 (ARRA) went into effect in January 2014,
requiring public and private health care providers and other eligible
professionals to adopt and demonstrate meaningful use of electronic
medical records to maintain existing Medicaid and Medicare
reimbursement levels. As part of ARRA, Congress mandated
a reduction to Medicare Part B reimbursements for eligible
professionals’ services if the eligible professionals performing the
service did not demonstrate meaningful use of certified electronic
health records. CalVet indicated in its assessment results that
ADL—the system software vendor—is not certified. To determine
the extent of these reductions in reimbursements for eligible
professionals, we asked CalVet how many of its professionals were
affected by the reductions. The staff services manager of CalVet’s
Medical Cost Recovery and Support Unit indicated that although
her staff reviewed accounting records and identified some eligible
professionals who received the Medicare reimbursement reductions
in 2016, the staff have not reviewed all facilities’ accounting records
to determine all of the individuals affected. As of early May 2016,
CalVet did not know how many of the homes’ eligible professionals
will be impacted by the Medicare reimbursement reductions.
However, in our review we noted that eligible professionals can
apply for hardship exceptions through the federal Centers for
Medicare and Medicaid Services in certain categories to avoid this
payment reduction. One of the exemption categories is extreme or CalVet’s eligible professionals can
uncontrollable circumstances and includes, as an example, that the apply for a hardship exemption
eligible professional’s electronic health record vendor was unable as an option to avoid Medicare
to obtain certification. Therefore, CalVet’s eligible professionals can Part B reductions until ADL
apply for a hardship exemption as an option to avoid the reductions receives its electronic health
until ADL receives its electronic health records certification. records certification.
Although it is possible for CalVet to take reasonable steps to
remain compliant with these laws and regulations, the need for
such additional work contradicts the intent of the new system—to
improve its operational efficiency. CalVet also intended for the
system to improve its regulatory compliance; thus, the need for
additional steps, as reasonable as they may be, indicates the system
has not improved regulatory compliance.
Project Management Failed to Promptly Recognize the Severity of
System Problems
In its governance plan for the project to implement the system,
CalVet outlined the governance bodies that steered, controlled, and
managed the project. The plan includes descriptions of the
26 California State Auditor Report 2015-121
June 2016
two main bodies—the project management team (management
team) and the executive steering committee (steering committee)—
responsible for overseeing the project, their roles and responsibilities,
and the structure of each. The management team, led by the project
manager (a role filled by CalVet’s deputy secretary for Veterans
Homes Information Management), was responsible for managing
the day‑to‑day operations of the project—such as the scope,
schedule, and resources for the project—to ensure that the project
achieved outcomes as planned. The steering committee was an
advisory body that supported and provided
perspective to the project executive (a role filled
California Department of Veterans by CalVet’s undersecretary of Veterans Homes)
Affairs’ Enterprise-Wide Veterans Home that held total decision‑making authority.
Information System Project: According to the governance plan, the steering
Selected Key Roles and Responsibilities committee was to meet monthly to discuss major
issues and risks related to the project and to make
Project Management Team
decisions. The steering committee was not directly
• Responsible for addressing issues related to system
responsible for managing project activities, but it
design, development, and implementation. Resolves
was supposed to provide support and guidance to
project issues as they arise.
those who did. The text box shows selected key
Project Manager—California Department of Veterans
roles and responsibilities as described in the
Affairs (CalVet) deputy secretary for Veterans Homes
project’s governance plan.
Information Management
• Plans, directs, and oversees the daily activities of
As early as June 2012, staff began reporting
the project.
problems with the system’s pharmacy component
• Has decision‑making authority within the current
to the project executive and the former project
project scope to address project changes, issues, and
manager, but they did not address the problems.
the direction of assigned resources.
The steering committee meeting minutes show
• Responsible for monitoring system contractor progress.
that staff began reporting these problems in
• Responsible for regular scheduled project reporting June 2012 and continued to note problems
to the project executive. with pharmacy implementation in the monthly
• Escalates problems not resolved at the project meetings through the beginning of 2013.
manager level or below. Specifically, in July 2012, the pharmacist
• Leads the project management team. implementation coordinator noted that the
pharmacy team had developed a problem
Executive Steering Committee
log and would meet weekly to discuss concerns
• Responsible for reviewing, resolving, and
deciding on problems escalated from the project and attempt to identify a resolution. Again, in
management team. the August and October 2012 meetings, the
pharmacist implementation coordinator noted
Project Executive— CalVet’s undersecretary of
the pharmacy team was identifying and tracking
Veterans Homes
problems. The minutes from the October 2012
• Responsible for the ultimate success of the project.
steering committee meeting also showed that
• Responsible for reviewing and resolving project
the project executive had noted that the system
problems that cannot be resolved at lower levels.
contractor had done a good job on the pharmacy
• Highest level of project review within CalVet and
problems and that it had arranged regular meetings
chairs the executive steering committee.
with software vendors to address problems.
Source: CalVet’s governance plan for its Enterprise-Wide
However, in November 2012 the pharmacist
Veterans Home Information System project.
implementation coordinator noted that the
pharmacy component was still experiencing
California State Auditor Report 2015-121 27
June 2016
problems receiving orders from the order entry component in ADL
Clinical. For example, in January and February 2013, he noted that
one home was experiencing medication orders missing from the
system and as a result, the system was not generating some orders for
the pharmacy to fill.
Given the severity and recurrence of the problems being reported—
and the fact that they were clearly communicated in the steering
committee minutes—we expected the meeting minutes to indicate
that the project executive or project manager had discussed
resolutions or actions to be taken to resolve the problems. However,
in the minutes from February 2013, the project executive noted
that the home administrators were keeping her updated on how
they felt about the system and that it seemed many problems were
being resolved through direct communication with the project
team even though correspondence between one of the homes
and headquarters showed otherwise as the problems continued.
Specifically, correspondence to CalVet from the chief medical officer
at the Chula Vista home in August 2013 indicated that significant
problems with the pharmacy component remained and were
increasing the risk of medication error. The chief medical officer
noted that no verification was occurring that all medication orders
were successfully transmitted, and some orders were not processed
and fell into an error queue without notifying staff that the order had
not been processed. In fact, CalVet eventually suspended the use of
the medication order component at all eight homes.
Because that project executive and the project manager during
that time are no longer at CalVet, we were unable to obtain their
perspectives as to why they did not address the concerns with the
pharmacy component raised in the steering committee meetings.
According to the manager of the project management office
(PMO manager) in CalVet’s Information Services Division (ISD), who
was present at the time, the steering committee meetings were only
status updates to the committee and resolutions were never discussed.
Further, she stated that management originally thought the problems
with the order entry functionality were mainly a result of user error
and that staff needed more training.
CalVet’s project management did not begin to take steps to address CalVet did not begin to take steps
reported problems until late 2013, having spent nearly $6 million to address reported problems until
from the time staff began reporting problems to the steering late 2013, having spent nearly
committee in mid‑2012. According to the final project manager, when $6 million from the time staff began
he stepped into his role in November 2013, he learned of numerous reporting problems to the steering
problems with the project from CalVet leadership and staff and from committee in mid-2012.
his review of project communications, documents, and invoices.
In the same month, a staff member from CalVet’s Veterans Homes
Division visited the five homes that had implemented the system’s
ADL Clinical module—Barstow, Chula Vista, Lancaster, Ventura,
28 California State Auditor Report 2015-121
June 2016
and West Los Angeles—and noted the functionality problems the
staff were reporting. Notes from those visits indicate that staff
were experiencing several problems, including system modules
that would freeze, information showing correctly in the system but
appearing inaccurate when a report was generated, and their need
to use paper documents or other workarounds as backup or in lieu
of the system. According to the final project manager, he, the agency
information officer, and the former deputy secretary of administrative
services reported critical concerns to the California Department
of Technology (Technology Department) in December 2013.
In December 2013 CalVet decided to CalVet then decided to pause the project to resolve critical system
pause the project to resolve critical problems. The Technology Department’s director at the time
system problems. Additionally, the indicated that the Technology Department directed CalVet to follow
Technology Department directed the dispute resolution process outlined in the contract with the
CalVet to follow the contract’s system contractor, which was to issue a cure letter, a formal written
dispute resolution process with the request to provide specific deliverable documents and meet other
system contractor. requirements according to the terms of its contract. In January 2014,
CalVet sent the system contractor a cure letter requesting the
documents for the system architecture and system configuration
deliverables, which provide the organizational structure of the
system and the arrangement of a computer system’s components.
The letter also required the system contractor to meet the identified
requirements by February 13, 2014.
In early 2014, after the system contractor disputed CalVet’s claims
in the cure letter, the Technology Department began facilitating
discussions between CalVet and the system contractor. CalVet’s
post‑implementation evaluation report (PIER) stated that the
Technology Department facilitated these discussions from February
through March 2014.3 Although Technology Department staff
told us it facilitated a series of meetings to try and resolve the
dispute between CalVet and the system contractor, the Technology
Department could only provide one document summarizing
outstanding problems as of January 28, 2014. That summary identifies
CalVet’s and the system contractor’s position on 16 problems. The
summary also provides the Technology Department’s comments on
most of the problems. Although the document provides a summary
of the disputed issues, it does not include any specific action plans to
resolve differences or any final resolutions.
Under the direction of the Technology Department, CalVet conducted
an assessment of the system from May to August 2014 to determine
if the system was functioning properly and was meeting its needs.
The Technology Department’s former director told us that it required
CalVet to conduct a series of assessments to figure out what was
causing the problems. He also stated that the Technology Department
3 The PIER is a report submitted to the Technology Department in support of an agency’s request
to consider the project complete and to terminate project reporting.
California State Auditor Report 2015-121 29
June 2016
lent a staff member—an enterprise architect—to CalVet to perform
the assessment. However, the only documentation that the Technology
Department provided from its enterprise architect’s review of the
system is a one‑page summary that lacks details of his assessment and
a conclusion as to whether the system design was functioning properly.
CalVet staff at the homes continued to experience serious functionality
problems with the pharmacy component, such as errors in medication
orders. As a result, in September 2014—just over a year and a half after
it should have reasonably recognized the severity of the problems—
CalVet suspended the use of that component of the system in all of
the homes.
In December 2014, after unsuccessful negotiations, CalVet, the
Technology Department, and the system contractor signed a
settlement agreement to terminate the contract. We asked the
Technology Department whether it performed an assessment
to ensure that the settlement agreement was in the State’s
best interest. The former director stated that the Technology
Department performed an assessment of the deliverables listed in
the cure letter and found that the system contractor had submitted
some of the deliverables but identified others that it had not
submitted, which were used as part of the settlement with the
system contractor. However, the Technology Department was The Technology Department was
unable to provide us with documentation to support its claim that unable to provide documentation
it conducted such an assessment of the deliverables to ensure that it conducted an assessment
that the settlement amount was in the State’s best interest. The of the deliverables to ensure that
former Technology Department director stated that a negotiator the settlement with the system
in its Statewide Technology Procurement Division (technology contractor was in the State’s
procurement division) negotiated the settlement agreement and best interest.
that the negotiations were meant to determine what CalVet needed
and what the system contractor was owed. Although we requested
documentation from the Technology Department to demonstrate
its efforts during the negotiations to ensure that the agreement
reached was in the State’s best interest, it did not provide such
documentation. According to the deputy director of the technology
procurement division, the individual who led the negotiations
and his manager have left state service and no documents on the
negotiations are in the file they left behind.
CalVet’s documentation indicates that the system contractor
had outstanding invoices to CalVet for over $1.9 million for full
implementation and maintenance of the system in the homes
in Fresno, Redding, and Yountville as well as for the remaining
deliverables it indicated it had already completed. However, the
staff in those three homes did not receive training on and are not
using the ADL Clinical module, a large portion of the system that
the homes would have used to manage their electronic health
records. As such, CalVet valued the portion of the system that the
system contractor did implement and agreed to a lower settlement
30 California State Auditor Report 2015-121
June 2016
amount of $350,000. At that point, CalVet had spent $26.2 million
implementing the system. In January 2015, CalVet and the
Technology Department mutually agreed to close out the project.
As of January 2015, CalVet discontinued its efforts to address
the functionality problems it had identified and decided to use the
functionality available from the system to the best of its ability
while it explored options for a replacement solution. According
to minutes of the steering committee meeting, CalVet’s acting
secretary gave direction in January 2015 to cease any work to
As of November 2015, CalVet restore the order entry functionality, to prepare the system’s PIER,
continues to use the functionality and to initiate efforts to replace the system. As of November 2015,
available from the system CalVet continues to use the functionality available from its system.
while it explores options for a According to the current deputy secretary of Veterans Homes,
replacement system. CalVet is in the process of looking for a replacement system.
Failure to Follow Project Management Oversight Plans Contributed to
CalVet’s Unsuccessful Implementation of Its System
Because it did not establish and follow all of the key activities of
the project management plan that the Technology Department’s
California Project Management Methodology (project management
methodology) requires, CalVet missed opportunities to detect
deficiencies and take corrective actions earlier. The planning
stage of that project management methodology describes the
development of a project management plan that includes a series
of 10 plans that serve as a customized, orchestrated project
management workflow for IT projects. The project management
methodology document states that the purpose of project
management is to ensure that the delivered product, service, or
result meets the customer’s requirements and is delivered on time
and within budget. Further, it states that a project management
methodology improves the quality of project planning,
communication, and control of executive and closure processes and
thus improves the quality of the deliverables. The completion of
the project management plan is the main objective of the planning
stage of the project management methodology, which CalVet
specified that it would comply with in its FSR.
Although CalVet hired a consultant to assist it in creating the series
of 10 plans that make up the required project management plan, it
did not develop one of those plans and four others were incomplete.
Further, CalVet did not complete one of two additional required
plans separate from the series of project management plans and did
not consistently follow the plans it did develop. Of the six complete
plans, CalVet fully followed only four. Table 4 shows the 12 required
plans and indicates which ones CalVet developed and followed.
California State Auditor Report 2015-121 31
June 2016
Table 4
California Department of Veterans Affairs’ Adherence to Required Project Plans
IF DEVELOPED, DID
WAS THE PLAN CALVET FOLLOW
PURPOSE DEVELOPED? THE PLAN?
Project Management Plan
Scope Management Plan Define and document what is and is not within the project boundaries,
and ensure that the project includes all the work required, and only the No NA
work required, to complete the project successfully.
Configuration Change Control Document, control, and manage changes to key project components
Yes No
Management Plan and deliverables throughout the project life cycle.
Human Resources Management Plan Identify how and when labor needs will be met to ensure the
project has sufficient staff with appropriate skill sets and experience.
Partially Partially
Additionally, identify and document project roles, responsibilities, and
reporting relationships.
Communication Management Plan Determine information and communications needs of project
stakeholders: who they are, when they will need information, what Partially Partially
information they will need, and how it will be given to them.
Risk Management Plan Decide how to approach, plan, and execute risk management activities
for the project. Establish agreed-upon basis for evaluating risks and
Yes Yes
ensuring that sufficient resources and time are allocated for risk
management activities.
Cost Management Plan Plan, estimate, and control costs so that the project can be completed
Yes Yes
within the approved budget.
Quality Management Plan Identify which quality standards are relevant to the project and
Yes Partially
determine how to satisfy them.
Schedule Management Plan Provide for the timely completion of the project. The plan establishes
how the project schedule will be managed and controlled and includes Partially Yes
estimating the duration of activities.
Procurement Management Plan Determine which project needs can best be met by purchasing products
or services outside the project organization, and which project needs Yes Yes
can be accomplished by the project team.
Contract Management Plan Document the products, services, and results requirements needed to
Partially No
meet the project’s objectives.
Other Required Plans
Organizational Change Assess stakeholders’ awareness and influence, determine any resistance
Management Plan or concerns, and identify optimum communication and actions to Yes Yes
be taken.
Maintenance and Operations Document how the project will be transitioned to the operational
Transition Plan team that will own the new system. Also includes a bridge between
No NA
the team executing development, the transition team, and the
operations team.
Sources: California Department of Technology’s Statewide Information Management Manual, interviews with project staff at the California Department of
Veterans Affairs (CalVet), and California State Auditor’s review of CalVet’s project management and other required plans and related documentation for
its Enterprise-Wide Veterans Home Information System.
For example, CalVet did not develop a scope management plan,
which defines and documents what is and is not within the project
boundaries. That plan describes how a project’s scope is defined,
verified, and controlled. If developed and followed, it helps a project’s
decision makers determine whether the benefits of a proposed
32 California State Auditor Report 2015-121
June 2016
change in scope are worth the change in costs. This question needs One aspect of the change plan
to be answered every time someone on a project requests a change procedures that CalVet did not
in scope. Because CalVet did not develop this plan, it did not have follow required the change control
a process to ensure that proposed changes to the project included manager to assign an analyst to
only the work required to complete the project successfully and to conduct an impact analysis of
remain within the boundaries of the defined scope. each change request the project
team received.
Additionally, as shown in Table 4, although CalVet had a complete
quality management plan, it only partially followed that plan.
The quality management plan identifies quality control activities
as a key component of overall quality management, essential to
CalVet’s quality management ensuring a successful project. CalVet’s quality management plan
plan stated that it would conduct stated that the project team would conduct structured reviews to
structured reviews to determine determine whether project baselines were being maintained and
whether project baselines were to confirm the implementation of change requests and corrective
being maintained, but it never actions, among other tasks. These reviews were to evaluate project
conducted these reviews. progress against project objectives for quality, as defined in the
SPR or project charter, and to determine whether shortfalls and
causes of problems had been addressed, including compliance with
organizational and project policies, processes, and procedures.
CalVet’s PMO manager stated that CalVet never conducted
these structured reviews. As a result, it did not recognize that it
incorrectly reported project progress in its project status reports.
As part of its oversight, in August 2012 the Technology Department
identified that CalVet’s July 2012 project status report contained
costs and milestones that were not aligned with the last approved
governance document. As discussed later in this report, CalVet’s
project status reports gave the impression that the project was still
progressing according to the approved schedule when it was in
reality nearly seven months behind. Had CalVet been conducting
structured reviews to determine whether the project baseline
was being maintained, it would have been able to identify this
issue itself.
Further, CalVet did not follow its configuration change control
management plan (change plan). This plan describes the process
the project team will follow to document, control, and manage
changes to key project components and deliverables throughout
the project. For example, CalVet’s change plan specified that
changes to technical or functional requirements, deliverables, or
the project schedule were subject to the formal processes specified
in the plan. Because CalVet did not follow the change plan, it was
unable to demonstrate that it properly understood the impact
of different change requests on the project’s costs, scope, and
timeline. For example, one aspect of the change plan procedures
that CalVet did not follow required the change control manager
to assign an analyst to conduct an impact analysis of each change
request the project team received. According to the change
California State Auditor Report 2015-121 33
June 2016
change in scope are worth the change in costs. This question needs plan, the analyst was to complete an assessment of the proposed One aspect of the change plan
to be answered every time someone on a project requests a change change and the change control manager would indicate whether procedures that CalVet did not
in scope. Because CalVet did not develop this plan, it did not have the impact analysis affected the project’s scope, cost, schedule, follow required the change control
a process to ensure that proposed changes to the project included or resources. The change plan also specified that the analyst manager to assign an analyst to
only the work required to complete the project successfully and to would document the methodology followed and the steps taken conduct an impact analysis of
remain within the boundaries of the defined scope. to perform the analysis, clearly describing all assumptions and each change request the project
constraints. The change plan also stated that the analyst should team received.
Additionally, as shown in Table 4, although CalVet had a complete summarize all final recommendations in a succinct fashion for
quality management plan, it only partially followed that plan. subsequent review by the project manager, change control board,
The quality management plan identifies quality control activities and project executive, including whether the change would have an
as a key component of overall quality management, essential to impact on the project’s scope, cost, schedule, or resources.
CalVet’s quality management ensuring a successful project. CalVet’s quality management plan
plan stated that it would conduct stated that the project team would conduct structured reviews to Despite these requirements, CalVet made a significant change
structured reviews to determine determine whether project baselines were being maintained and without following its formal change process. Specifically, a
whether project baselines were to confirm the implementation of change requests and corrective change request the system contractor submitted in September 2011
being maintained, but it never actions, among other tasks. These reviews were to evaluate project requested a modification to the conditions under which user
conducted these reviews. progress against project objectives for quality, as defined in the acceptance testing (UAT) could proceed. UAT tests what the
SPR or project charter, and to determine whether shortfalls and system contractor delivers to determine whether the deliverables
causes of problems had been addressed, including compliance with conform to contract requirements. The change request asked to
organizational and project policies, processes, and procedures. modify the language in the contract’s statement of work related
CalVet’s PMO manager stated that CalVet never conducted to the commencement of UAT. The original language required
these structured reviews. As a result, it did not recognize that it CalVet to approve the system contractor’s certification of successful
incorrectly reported project progress in its project status reports. completion of system integration testing before proceeding to UAT,
As part of its oversight, in August 2012 the Technology Department and the change requested that CalVet and the system contractor
identified that CalVet’s July 2012 project status report contained be allowed to approve acceptable progress in system integration
costs and milestones that were not aligned with the last approved testing before proceeding to UAT. The change request justification
governance document. As discussed later in this report, CalVet’s states that delays in the system environment readiness and in
project status reports gave the impression that the project was still the development of certain modules would prevent CalVet from
progressing according to the approved schedule when it was in completing verification of all requirements before beginning UAT.
reality nearly seven months behind. Had CalVet been conducting A review of this change request indicates that it was approved by
structured reviews to determine whether the project baseline CalVet without completion of the impact analysis that its change
was being maintained, it would have been able to identify this plan required.
issue itself.
Because CalVet did not conduct an impact analysis for this change
Further, CalVet did not follow its configuration change control request, it cannot demonstrate that it properly considered the
management plan (change plan). This plan describes the process effects this proposed change would have on the project. As a
the project team will follow to document, control, and manage result of this approved change request, CalVet began UAT before
changes to key project components and deliverables throughout the system integration testing was completed, according to its
the project. For example, CalVet’s change plan specified that project schedule. Therefore, CalVet could not test parts of the
changes to technical or functional requirements, deliverables, or system for which development was delayed and it could not ensure
the project schedule were subject to the formal processes specified that what the system contractor delivered conformed to contract
in the plan. Because CalVet did not follow the change plan, it was requirements. As we described in an earlier section, CalVet’s final
unable to demonstrate that it properly understood the impact project manager indicated that some of the problems identified
of different change requests on the project’s costs, scope, and during its assessment of the system, such as the need to enter
timeline. For example, one aspect of the change plan procedures patient information more than once and problems using the
that CalVet did not follow required the change control manager medication order entry functionality, were the result of incorrect
to assign an analyst to conduct an impact analysis of each change system configuration by the system contractor. Had an impact
request the project team received. According to the change analysis been conducted for this change request, it would have
34 California State Auditor Report 2015-121
June 2016
considered the negative impacts of beginning UAT testing before
system integration testing was completed, allowing CalVet’s project
management to make an informed decision.
By not fully developing and following all of the plans that made up
the required project management plan, CalVet limited its ability
to detect deficiencies earlier in the development of the system.
According to the final project manager, based on this review
of project documents, the project management plans were not
followed because oversight was lacking and because problems with
the plans were not being escalated to the project executive. He
stated that if project management plans were not being followed
during the project, the individual assigned ownership for the plan
would have been responsible to escalate the problem to the project
manager. He further stated that if the project manager could not
resolve the problem, it should have been elevated to the project
executive, who could also move the problem on to the steering
Our review of steering committee committee. CalVet’s governance plan states that the project
meeting minutes from the executive provides oversight as needed and has responsibility to
project repository did not show resolve project problems that cannot be resolved at lower levels.
that problems regarding the Our review of steering committee meeting minutes from the
plans were ever escalated to project repository did not show that problems regarding the plans
the project executive. were ever escalated to the project executive.
CalVet hired a contractor to perform both independent verification
and validation (IV&V) services and independent project oversight
(IPO) services for its system project. We refer to this contractor
as the oversight contractor. CalVet’s contract management plan
stated that the oversight contractor, in its IPO role, was responsible
for monitoring the project plans and processes, assessing the
project’s adherence to required project management processes and
methodologies, and providing recommendations for improvement
related to the project management effort. The final project manager
stated that the oversight contractor should have independently
been reporting on and identifying any nonadherence to project
management plans and that this would have ensured that even if
the problems were not being escalated up the chain of command,
decision makers were being made aware of the problems. However,
as we describe in the next section, the IPO reports the oversight
contractor created did not identify the critical problems with the
project. CalVet could not explain why the problems regarding
adherence to the project management plan were not escalated to
the project executive. Had the problems with the plans been so
escalated or had the oversight contractor detected these problems,
many of the problems experienced with the system project, such as
incomplete project management plans, could have been addressed
at an early stage.
California State Auditor Report 2015-121 35
June 2016
Inadequate Independent Oversight of the System Project Left
Stakeholders Without the Information Necessary to Ensure a
Successful Implementation
The services that the oversight contractor provided were We noted missing critical
inadequate. Specifically, we noted missing critical deliverables deliverables we expected the
we expected it would have provided through its contracted oversight contractor would
IV&V services. Additionally, our IT expert stated that in his have provided through its
opinion, the IPO was largely ineffective. As discussed in the contracted IV&V services.
Introduction, IV&V services provide a client with technically
proficient “eyes and ears” to oversee a system vendor while an
IT system is being developed and implemented, and these services
also provide an early warning of process and technical discrepancies
and problems that might not otherwise be detected until late in the
project life cycle. IPO services provide an independent review and
analysis of project management practices to determine whether the
project is being well managed.
CalVet’s oversight contractor provided both IPO and IV&V
services. CalVet’s contract required the oversight contractor to
perform tasks and activities in accordance with applicable Institute
of Electrical and Electronic Engineers (IEEE) standards, which are
industry standards also recommended in state policy. According
to our IT expert, the relevant IEEE standard focusing on system,
software, and hardware verification and validation processes does
not require an organization that is performing traditional technical
IV&V services to be organizationally independent from one that
is performing optional project management oversight support.
However, he stated that separation of IV&V and IPO duties is
important and provides a number of advantages to the project and
to the State. For example, IPO should assess whether appropriate
IV&V services have been procured for the project. It is also within
the purview of IPO activities to assess whether the IV&V contractor
is doing its job well, such as whether IV&V services are effective
and timely. If a contractor is performing both activities, there is also
a potential conflict of interest because IPO might recommend that
more of the IV&V services it is providing be used.
Our IT expert reviewed the IPO and IV&V reports the oversight
contractor provided to CalVet and noted that he did not find
evidence that the oversight contractor prepared certain key
IV&V reports that the contract required. These reports should
have provided insights into the technical quality of the work being
performed. Some of the more critical missing IV&V deliverables
included the following:
• Requirements traceability reports monitoring the tracing of
project requirements throughout the project life cycle to ensure
that the system meets specified requirements.
36 California State Auditor Report 2015-121
June 2016
• System and software verification report assessing whether the
work products satisfied the conditions established at the start of
the development phase and fully addressed the requirements.
• System and acceptance report and testing report assessing
whether the delivered products had been thoroughly
tested to confirm that they were functional and met
contractual requirements.
According to our IT expert, these IV&V reports are all critical.
However, CalVet’s final project manager stated that the oversight
contractor did not provide these deliverables to CalVet and that
poor contract management by CalVet was the reason it did not
identify the oversight contractor’s failure to submit the reports and
require that it do so. By failing to obtain the technical assessments
from these reports, CalVet neglected its responsibility to ensure
that it was providing stakeholders with information about whether
its project to implement a new system fulfilled all technical
requirements and was functioning as expected.
In addition to missing critical IV&V deliverables, our IT expert
concluded that the IPO was largely ineffective. He stated that IPO is
there to make sure that the project manager is accurately reporting
project status and that IV&V is providing independent technical
analysis. His review of IPO and IV&V reports found almost no
technical assessment; in addition, although the reports indicated
what happened, they offered minimal analysis, with no explanation
of root causes or trends. For example, one IV&V report referred
to a checklist for delivered training materials indicating that there
were problems, but it did not identify the problems and stated that
the IV&V review could not be completed. In this case, according to
our IT expert, IPO should have raised concerns that IV&V could
not complete its work. Similarly, effective IPO should have raised
concerns that IV&V was not managing requirements traceability,
as mentioned earlier. Although the oversight contractor’s IPO
Although the oversight contractor’s reports should have identified these types of deficiencies in the
IPO reports should have IV&V work—performed by the same contractor—they did not.
identified deficiencies in the IV&V Because the IPO reports did not identify that IV&V was failing
work—performed by the same to perform critical work, neither CalVet nor the Technology
contractor—they did not. Department received an accurate assessment of whether the
processes the system contractor was using were effective and
whether the system reflected the agreed‑upon quality and solution.
The IPO reports also missed critical information about a variation
from the approved project schedule, a variation later identified by
the Technology Department. State policy requires that IPO reports
assess the expected completion of tasks and milestones compared
to the approved project schedule contained within the most
recent SPR. However, in its August 2012 IPO report, the oversight
California State Auditor Report 2015-121 37
June 2016
contractor acknowledged that previous reports had looked at past
project milestone dates and their actual completion dates rather
than dates in the most recent approved SPR as it should have to
determine whether the project was on schedule. Further, the IPO
report stated that beginning with the August 2012 report, future
tasks and milestones would be compared to the most recent project
schedule approved in the SPR to determine whether the project Because the oversight contractor
was on schedule. Because the oversight contractor did not use the did not use the correct dates to
correct dates to measure project progress, the variation from measure project progress, it gave
the approved schedule was not identified, giving the impression the impression that the project was
that the project was still progressing according to the approved still progressing according to the
schedule when it was not. approved schedule when it was not.
CalVet’s final project manager, who identified the variance while he
was employed at the Technology Department, informed us he met
with CalVet’s former project manager and the oversight contractor
to discuss the variance. As a result, the oversight contractor
adjusted its tracking in the August 2012 IPO report to correctly
reflect the schedule contained in the approved SPR. In that
August IPO report, the oversight contractor reflected that the
project was nearly seven months behind the approved schedule.
However, if the oversight contractor had been using the correct
dates to measure the project’s progress, it would have better
informed project stakeholders on the true status of the project’s
progress. Further, both CalVet and the project’s decision makers
would have been aware earlier that the project was behind schedule
and could have taken steps to address variances. CalVet’s final
project manager could not explain why his predecessor or the
oversight contractor did not use the approved schedule to measure
performance, but in his opinion, it was likely that they were familiar
with the requirements.
As we discussed earlier, our IT expert believes that by using
the same contractor to perform both IPO and IV&V functions,
CalVet did not ensure it had effective oversight for the project.
The deputy director of the Technology Department’s IT
Project Oversight Division stated that starting in July 2013, the
Technology Department began assigning its own staff for IPO
on reportable IT projects it deemed to be of medium or high
complexity and that agencies would have to obtain explicit
approval to contract for IPO services; this approval would only be
granted if the Technology Department did not have enough staff
to provide the services itself. She also stated that the Technology
Department does not have a policy requiring agencies to obtain
IPO and IV&V services from separate contractors; however, it is the
department’s expectation that agencies receiving permission to use
outside IPO services will obtain IV&V from separate contractors
and she agreed this would be a good policy to formalize.
38 California State Auditor Report 2015-121
June 2016
The Technology Department Did Not Adequately Fulfill Its
Responsibilities in the Oversight of CalVet’s System
The Technology Department’s review of IPO reports for CalVet’s
system project was inadequate, and as a result, it did not identify
critical concerns and take timely action. The Technology
The Technology Department Department received oversight authority after CalVet’s system
received oversight authority after project was already under way, and it made the decision to
CalVet’s system project was already allow CalVet to continue with its contracted oversight rather
under way, and it made the decision than perform the IPO role itself. According to the deputy
to allow CalVet to continue with its director of the Technology Department’s IT Oversight Division,
contracted oversight rather than because its oversight consisted of a review of project reports
perform the IPO role itself. that CalVet’s oversight contractor was producing, it would have
had no way of consistently identifying critical concerns related
to the project if no significant problems were reported in these
documents, as was the case with the CalVet project. However, our
IT expert’s assessment of the IPO reports indicated that the fact
that these reports did not contain critical information about the
project or offer analysis of project progress or vendor performance
should have triggered closer review and inspection.
State law transferred IT oversight authority from Finance to
the Technology Department in January 2008.4 The Technology
Department’s Statewide Information Management Manual
defines project oversight as independent review and analysis of
specific project activities and documentation to determine if the
project is on track to be completed within the estimated schedule
and cost and if it will provide the functionality the sponsoring entity
requires. The oversight responsibilities include requiring agencies
to provide the Technology Department with periodic reporting
that describes the degree to which an IT project is within approved
scope, cost, and schedule; project issues, risks, and corresponding
mitigation efforts; and the current estimated schedule and costs for
project completion.
According to the Technology Department’s former director, before
December 2013, its primary role in the oversight of CalVet’s project
was reviewing IPO and IV&V reports that CalVet’s oversight
contractor prepared. The FSR for CalVet’s system, which was
approved in 2007 by Finance—before state law transferred oversight
responsibility for IT projects to the Technology Department—
specified that CalVet would retain a contractor to perform IPO
and IV&V for the overall project. In December 2007, CalVet
entered into a contract, totaling just over $1.8 million, for these
services. Although the former director added that he had regular
4 Until July 2013, the California Department of Technology was known as the California Technology
Agency, and before that it was the Office of the Chief Information Officer.
California State Auditor Report 2015-121 39
June 2016
verbal briefings—referred to as portfolio reviews—with both
CalVet and the oversight contractor to discuss the status of the
project, the frequency of these meetings could vary, ranging from
monthly to quarterly. He told us no documentation exists from
these meetings.
Although we previously described one instance in August 2012
when the Technology Department identified concerns with
information in the IPO report and took action to address its
concerns by meeting with the oversight contractor, overall we
found that the Technology Department’s oversight of the IPO
reports for CalVet’s system project was inadequate. Specifically, The Technology Department’s
its oversight was not rigorous enough to detect concerns reported oversight was not rigorous enough
in the IPO reports or to question why the reports the oversight to detect concerns reported in the
contractor prepared did not contain critical information about IPO reports or to question why the
the project. As previously noted, our IT expert stated that the reports the oversight contractor
IPO reports the oversight contractor prepared did not offer an prepared did not contain critical
analysis of project progress or vendor performance and that information about the project.
should have triggered the Technology Department’s closer review
and inspection. For example, the IPO report for February 2011
indicated that the project was using about half of the allocated
resources for the fiscal year but did not offer an analysis of the
cause or the implications this would have for the project. The same
IPO report identified a risk that the system contractor might not
be able to perform or meet the requirements according to its
bid for the project; however, the IPO report did not include any
significant analysis, thus missing an opportunity for IPO to provide
an explanation of what it was seeing. In another example, our IT
expert noted that in comparing the IPO reports for March 2011
and April 2011, he found a two‑month delay in the projected end
date for the design, configure and development phase; however,
there was no comment explaining the sudden two‑month slippage
in the schedule.
Our IT expert also noted that in the IPO report for June 2011,
the rating in “quality for architecture/system performance” was
suddenly listed as inadequately defined even though in previous
reports the notation was not applicable. He stated that this is a
huge red flag, and he noted that the corresponding analysis said
that the current draft of the system architecture document did not
adequately and accurately reflect the planned system. However,
no further analysis or context was provided about the impact of
this change. Our IT expert stated that the lack of analysis and
general comments should have been a red flag to anyone familiar
with the IPO report format. He explained that there is a difference
between tracking the project—what is happening, and oversight —
reporting what is happening and providing context for people to
understand what is important, what is not, and the implication
40 California State Auditor Report 2015-121
June 2016
of what is being observed. He stated that CalVet’s project IPO
reports all fell into the tracking category as they rarely offered
analysis or perspective on what was happening; they simply
reported schedule slips and risks. He added that any review
of these IPO reports should have resulted in the Technology
Department’s further inquiry of the oversight contractor and
perhaps coaching to improve the quality of the reports. Although
the IPO reports generally lacked this analysis of events and risks
reported, we found no evidence that the Technology Department
raised concerns about the quality of the reports with either the
oversight contractor or with CalVet.
The Technology Department In fact, the Technology Department could not demonstrate that
could not demonstrate that it it had even reviewed IPO reports before August 2012, when,
had reviewed IPO reports before as discussed earlier, it raised an issue about the information
August 2012. At that point, in the oversight contractor’s report. At that point, CalVet had
CalVet had spent $15.8 million on spent $15.8 million on the project. Additionally, the Technology
the project. Department could not locate any IV&V reports for CalVet’s
project. Had the Technology Department’s oversight of the
system been more rigorous, it should have identified and raised
concerns about the deficiencies of the IPO reports and missing
IV&V reports, which likely would have resulted in the oversight
contractor informing CalVet earlier of problems with the
system’s implementation.
The deputy director of the Technology Department’s IT Oversight
Division stated that division staff were reviewing IPO and
IV&V reports from CalVet’s oversight contractor, but because the
reports were not indicating critical errors with the project,
the Technology Department did not raise any concerns. However,
we believe it should have. As we noted earlier, our IT expert stated
that the lack of critical information about the project or analysis
of project progress or system contractor performance in the
IPO reports should have been sufficient cause for concern.
According to that deputy director, starting in July 2013 the
Technology Department began assigning its own staff to perform
project oversight. However, the former director told us that it
devoted its limited staff resources to other troubled projects and
only provided a portfolio review of CalVet’s relatively small system
project when compared to those other troubled projects going
on at the same time. Further, the deputy director indicated that
because the Technology Department had an insufficient number
of qualified staff to replace vendors on existing projects, CalVet
was allowed to continue to use its oversight contractor. She stated
that the Technology Department’s practice as of July 2013 has been
California State Auditor Report 2015-121 41
June 2016
that any IT projects deemed to be of medium or high complexity As of July 2013, any IT projects
must obtain explicit approval from the Technology Department deemed to be of medium or high
to contract for their own IPO services and approval is granted complexity must obtain explicit
only if the Technology Department does not have enough staff to approval from the Technology
provide the IPO services itself. Department to contract for their
own IPO services.
In a previous audit report issued by our office, we identified
concerns with the Technology Department’s limited resources and
with its poor documentation of its oversight efforts on IT projects.5
The problems that we noted in that report were occurring at the
time the Technology Department was providing oversight to
CalVet’s implementation of its system. Specifically, our previous
report noted that the Technology Department’s oversight and
consulting division hired additional IPO analysts between fiscal
years 2011–12 and 2013–14; however, we found it was unclear
whether the division had enough positions at that time to effectively
oversee the State’s IT projects. As a result, we recommended
that the Technology Department conduct a workload assessment
to determine the level of staffing and expertise required for the
projects it oversees and using that workload assessment, it should
make decisions to assign its staff to oversee each IT project. In
March 2016, the Technology Department indicated in its one‑year
response to our earlier report that it had established processes to
capture and evaluate workload information. If it follows these new
processes, the Technology Department can better identify the level
of oversight it can provide to state IT projects.
That previous audit report also noted that although the Technology
Department is generally able to hire personnel to fill its IPO analyst
positions, the job classification it uses may not attract applicants
with the most relevant skills and experience required for IT project
oversight. To ensure that it attracts and retains employees with
appropriate experience and qualifications to perform IT project
oversight, we recommended that the department continue its
efforts to gain approval to use the project manager classification
for its IPO analyst role. In its one‑year response in March 2016,
the Technology Department reported that it determined in
October 2015 that the project manager classification was
not suitable for use by the IT project oversight division. The
Technology Department also indicated that the California
Department of Human Resources (CalHR) is leading a significant
effort to modernize a variety of state classifications, including
IT classifications and the Technology Department is an active
participant in CalHR’s reform initiative. Therefore, the Technology
Department stated that until better options become available, it
5 High Risk Update—California Department of Technology: Lack of Guidance, Potentially Conflicting
Roles, and Staffing Issues Continue to Make Oversight of State Information Technology Projects
High Risk, Report 2014-602, March 2015.
42 California State Auditor Report 2015-121
June 2016
will continue to use the current classification—data processing
manager—to fill its project oversight role. Nevertheless, we believe
that by fully implementing the recommendations from our prior
report and fully implementing the additional recommendations we
present in this report, the Technology Department can ensure that
it fulfills its responsibility of providing oversight to state IT projects.
CalVet Did Not Maintain Adequate Documentation for Its Selection of
the System Contractor and for Some Key Deliverables
Because it did not maintain required documentation for selection
of the contractor to implement its system, CalVet cannot
demonstrate it complied with contracting requirements, and
this lack of documentation raises questions about the prudence
of its decisions. As of July 2010, the State Contracting Manual
requires state entities to use an RFP for acquisitions of IT projects
exceeding $1 million. State law in 2010 required agencies to award
the contract to the bidder that achieves the highest score on its
proposal. Regarding record retention, the State Contracting Manual
states that departments are responsible for maintaining records
in sufficient detail to allow anyone to review that documentation
and understand how the procurement was requested, conducted,
awarded, and administered. The State Contracting Manual further
states that record retention varies depending on document type
and can vary by department, depending on its internal retention
schedule. Generally, these procurement documents should be
retained for seven years from the end of the fiscal year in which
the contract amount is liquidated—either through completion
or termination.
CalVet could not provide some of the documentation it should
have maintained related to its award of the contract for its system.
CalVet’s contract records show that CalVet’s contract records show that in June 2010 it received
in June 2010 it received proposals proposals from seven vendors in response to its RFP. However,
from seven vendors in response to according to its final evaluation and selection report (evaluation
its RFP. However, it reviewed only report), it reviewed six proposals and CalVet’s selection committee
six proposals and deemed five of deemed five of them nonresponsive because of material deviations.
them nonresponsive because For example, according to the evaluation report, the selection
of material deviations. committee found that the documents submitted for one proposal
did not substantiate that the project manager met the experience
requirements outlined in the RFP. The evaluation report noted
that other proposals did not provide supporting references or
documentation verifying that the vendor could carry out the RFP
requirements. In addition, one of the seven proposals included on
the receipt log was not included in the evaluation report as having
been evaluated. When we asked CalVet why it was not included,
the PMO manager could not answer the question as she was not
part of the procurement; further, she stated that there is no one
California State Auditor Report 2015-121 43
June 2016
remaining at CalVet that had worked on the procurement. CalVet’s
final evaluation report indicated that CalVet scored and ultimately
awarded the contract to the only responsive bidder. However, CalVet could not provide
CalVet could not provide the proposals for six of the seven the proposals for six of the
responding vendors, nor could it provide its evaluation documents seven responding vendors, nor
for three proposals, including the winning proposal. When CalVet could it provide its evaluation
does not ensure that it maintains this documentation, it cannot documents for three proposals,
demonstrate that it made a prudent decision or that it complied including the winning proposal.
with state contracting requirements when selecting the vendor for
its project.
CalVet could not adequately explain why it did not follow
contracting requirements. The PMO manager agreed that poor
record keeping by the previous contract manager contributed to
the difficulty in locating the required contract documentation.
Further, she stated that CalVet does not have a policy to periodically
verify whether its staff are following contract documentation
requirements. Although CalVet’s policy states that each division
must provide a records retention schedule approval form annually
to its Office of Procurement and Contracting (OPC), according to
an OPC manager, OPC does not have a record retention schedule
from CalVet’s ISD, the division responsible for CalVet’s IT
contracts. Additionally, the final project manager could not provide
a records retention schedule for ISD.
CalVet also could not demonstrate that it received sufficient
documentation for some key system deliverables even though it
approved payments for them. Specifically, CalVet’s project files
indicate that it accepted and approved payments totaling $733,000
for three key deliverables—system design, system configuration, and
UAT—even though it could not provide adequate documentation
of receiving these final deliverables. The State Contracting Manual
requires state agencies to verify that the goods and services they
receive are satisfactory before approving payment for them. Further,
CalVet’s contract for implementation of the system required
that the system contractor submit all deliverables to CalVet for
acceptance and then approval.
The system architecture design and configuration deliverables
provide the organizational structure of the system and the
arrangement of the computer system’s components. Although
the contract manager at the time accepted the system configuration
and architect design deliverables and approved the payment of
$104,500, CalVet could not provide the final documentation.
Instead, it could only provide us with a draft version of those
documents. CalVet’s final project manager confirmed that no
one has been able to provide the final documents for these
two deliverables. He stated that many of the system problems
the homes encountered were generally related to deficiencies
44 California State Auditor Report 2015-121
June 2016
in the system’s configuration, design, and training. For example,
as discussed earlier, some homes indicated that staff have to enter
the same resident information into multiple modules within the
system, which the final project manager indicates is a result of
poor system configuration. Communication between CalVet and
executives at ADL—the system’s software provider—indicated that
based on its work with CalVet to resolve outstanding trouble tickets
over three months in early 2015, ADL was concerned with the
system’s configuration during installation and with the instructions
to CalVet staff on the proper setup and implementation of the
software. In June 2014, in response to CalVet’s system assessment of
functionality problems, the system contractor acknowledged there
In June 2014, the system contractor were more than 500 outstanding items of which about 240 would
acknowledged there were more require further system configuration and additional training of
than 500 outstanding items subject matter experts. Because the contract manager at the time
of which 240 would require CalVet accepted the system design and configuration deliverables is
further system configuration and also no longer at CalVet, it is unclear why she signed the acceptance
additional training of subject letter and approved payment for those deliverables as CalVet does
matter experts. not have proof it received the final deliverables.
The UAT deliverable documents the testing that verifies that the
system meets contract requirements and performs at a satisfactory
level. For deliverables related to UAT, the contract required the
system contractor, among other things, to develop a UAT report
that included a description of the defects CalVet identified during
UAT, the business processes and system functions or interfaces
impacted by each defect that could not be resolved, and a corrective
action plan for defects that could not be resolved. CalVet’s final
project manager indicated that after he started at CalVet in
November 2013, he looked for the UAT documentation but there
were no tangible test results or tracking of specific requirements.
He stated that for UAT, test cases are usually developed that
include the test steps and the success criteria used to evaluate
whether the given test case or scenario passed or failed. He added
that there should be documentation for each test case completed by
each tester.
Although the contract required specifics on the testing and
results, the deliverable from the contractor for the UAT that
CalVet provided to us included only a summary of the tests
completed. That summary report did not include information
about the specific requirements tested, who conducted the tests,
the outcome of each test, the defects identified during the testing,
or corrective action plans for each defect that could not be resolved.
CalVet’s test manager confirmed that CalVet does not have the
completed scripts that indicate who conducted the tests and what
the outcomes were. As a result, CalVet cannot demonstrate that
UAT was completed even though it approved payment of three
invoices totaling $628,527 for UAT. In fact, CalVet’s oversight
California State Auditor Report 2015-121 45
June 2016
contractor reported in February 2014 that during UAT, CalVet had
not accurately captured the results from the testers, and as a result,
there was no empirical evidence to assess to determine whether
the developed system met CalVet’s business needs. Because CalVet
accepted deliverables and approved payment without sufficient
documentation to demonstrate that the system contractor
had satisfactorily completed them, CalVet failed in its contract
management responsibilities to verify that the system it paid for
was properly designed and configured, met contract requirements,
and performed satisfactorily.
A number of factors contributed to CalVet’s failure to assess the
adequacy of UAT deliverables. The test manager stated that because
she did not have experience as a test manager in 2011, she could not
determine whether the documentation the contractor submitted
for testing was sufficient. She further explained that when she
voiced her concern that she had never been a test manager to
the project manager at the time, the previous contract manager,
and the previous agency information officer, they told her it was
okay and that they just needed someone to sign off on the testing.
She further indicated that CalVet did not complete UAT before
the system contractor implemented the system in the homes.
Because CalVet did not complete UAT, it missed its opportunity to
identify functionality issues before implementing the system in the
homes. The test manager indicated that because UAT took longer
than expected, the project team received outside pressure from
the former project executive, CalVet’s former secretary, and the
Technology Department to move forward with implementation to
keep the project on schedule. Therefore, CalVet did not complete
UAT before implementing the system.
Additionally, despite the lack of evidence for certain key IV&V Despite the lack of evidence for
deliverables, CalVet approved invoices from its oversight contractor certain key IV&V deliverables,
for those deliverables. As we described earlier, our IT expert CalVet approved invoices from
reviewed IV&V deliverables and did not find evidence that the its oversight contractor for those
oversight contractor prepared requirements traceability matrix deliverables.
reports—reports monitoring the tracing of project requirements
throughout the project life cycle to ensure that the system meets
specified contract requirements. In our review of invoices from
the oversight contractor, we identified invoices totaling just over
$12,000 for monitoring requirements traceability, but the contract
records did not contain any evidence of project manager review or
approval of those invoices. Further, CalVet was unable to provide
us with documentation that its oversight contractor actually
completed the review of requirements traceability. Therefore, it
is unclear why the previous contract manager approved payment
of the oversight contractor’s invoices. Additionally, according to
a 2014 report, the oversight contractor stated that CalVet did not
accurately capture the results from the UAT testers and as a result,
46 California State Auditor Report 2015-121
June 2016
there is no empirical evidence to assess whether the developed
solution met the users’ business needs. The final project manager
cited poor contract management as the reason why CalVet did not
identify deficiencies and require the oversight contractor to fulfill
the deliverables. However, he indicated that the IV&V contract
CalVet signed with its oversight contractor in September 2014
now requires the oversight contractor to submit deliverable
acceptance documents signed by the system’s project manager and
contract manager along with invoices to ensure that only accepted
deliverables are paid.
CalVet Identified Some Lessons Learned but Rarely Used Them to
Improve Future Phases of Implementation
Although CalVet conducted lessons‑learned sessions at points
throughout the project from initial procurement through
implementation at the Chula Vista home, it generally cannot
demonstrate that it used those lessons learned to make
improvements during later implementation phases. Additionally,
CalVet did not conduct sessions to identify lessons learned
during the final implementation phase at the Fresno, Redding,
and Yountville homes, preventing it from gaining the full benefit
of lessons learned: the ability during future similar projects to
duplicate the successes and avoid the shortfalls experienced on
earlier projects.
CalVet’s implementation plan stated that its PMO would lead
lessons‑learned sessions throughout the implementation of the
system, to document any lessons that could be usefully applied to
implementation at the next site. CalVet implemented the system in
three phases: the pilot phase, which included headquarters and the
CalVet conducted 14 lessons-learned homes in Barstow, West Los Angeles, Lancaster, and Ventura;
sessions from its initial procurement the second phase, which included Chula Vista; and the final phase,
efforts in March 2009 through which included Fresno, Redding, and Yountville. Documentation
implementation at Chula Vista summarizing the lessons‑learned sessions held shows that CalVet
in August 2013, but it generally conducted 14 of these sessions, from its initial procurement
cannot demonstrate that it used efforts in March 2009 through implementation at Chula Vista in
those lessons learned to make August 2013. According to CalVet’s summary of these sessions, they
improvements during later focused on what went well, what did not go as planned, and areas
implementation phases. for improvement.
Given that CalVet implemented the system in phases, it could
have used the lessons it learned during the pilot implementation
to improve the Chula Vista implementation, and it could have
used the lessons learned from both the pilot implementation and
at Chula Vista to improve the final phase of its implementation.
Specifically, CalVet’s summary from its lessons‑learned session
after the pilot implementation stated that staff indicated that there
California State Auditor Report 2015-121 47
June 2016
was a lack of on‑site support during evening shifts during the
implementation. Following the implementation at Chula Vista,
CalVet’s lessons‑learned session notes again identify that
evening support was not consistent. Additionally, after the pilot
implementation, CalVet’s lessons‑learned summary identified
concerns with training and noted as an improvement going forward
the need to maintain binders with the training materials and
processes in a central location. However, CalVet’s summary from
its lessons‑learned session for the implementation at the home
in Chula Vista again notes the need to maintain materials in a
central location. These examples demonstrate that CalVet repeated
mistakes and therefore did not effectively use the lessons it learned.
In fact, CalVet’s PMO manager identified only one change that
CalVet did make as a result of lessons learned. Specifically, CalVet
increased the time allotted for training at Chula Vista. She stated
that CalVet did not go back and document how it implemented
changes based on lessons learned, so she is unsure whether any
other lessons learned were implemented.
CalVet did not conduct lessons‑learned sessions following CalVet did not conduct
the final implementation phase at the Fresno, Redding, and lessons-learned sessions following
Yountville homes, limiting its ability to identify problems that the final implementation phase,
it could correct or avoid and successes it could repeat in future limiting its ability to identify
similar projects. According to the PMO manager, CalVet did not problems that it could correct or
conduct those lessons‑learned sessions because the system was avoid and successes it could repeat
not fully implemented at those three homes. However, CalVet’s in future similar projects.
implementation plan specified that the PMO would conduct
lessons‑learned sessions throughout the implementation, and
since the homes still implemented modules of the system, we
believe there were opportunities to document lessons learned for
future projects. When we pointed out these missed opportunities
to the PMO manager, she did not remember whether project
management considered that lessons could be learned from its
partial implementation at the three homes. However, she stated that
it is reasonable to think so.
According to its PIER, CalVet captured final lessons learned during
interviews with key management and executive staff. The report
states that participants were given the opportunity to look back
and identify the most significant problems and successes of the
project that would benefit future CalVet project efforts. CalVet
summarized these final lessons learned into eight categories, such
as scope management, requirements or change management,
contract management, and project governance, and it described
findings and recommendations for each category. For example,
one finding noted that CalVet did not actively manage the system
contractor, resulting in the system contractor not always delivering
services according to its contract, and agreed‑upon deliverables
were not reflected in contract amendments. The corresponding
48 California State Auditor Report 2015-121
June 2016
recommendation was to make sure the right resource is assigned
to not only manage the contract but also to enforce the terms of
the contract. In another example, CalVet’s finding stated that the
requirements were loosely managed throughout the project life
cycle, referring to its early identification of too many requirements,
the removal of many requirements in the subsequent RFP, the
significant gap between the two RFPs, and the large number of
change requests. The related recommendation states that CalVet
should establish a requirements management plan that defines
the process of scheduling, coordinating, and documenting the
requirements engineering activities including elicitation, analysis,
specification, and verification. CalVet’s incorporation of these final
lessons learned into its preparation for its planned future project is
critical to ensure that the next system implementation is successful.
Recommendations
CalVet
To ensure that its project management of IT projects promptly
identifies potential problems and develops resolutions, by
September 2016 CalVet should define the project executive’s and
project manager’s responsibilities to ensure that the individuals who
fill those positions take an active role in each project.
To ensure that it adequately identifies and monitors problems in
its future IT projects, by September 2016 CalVet should establish
a formal process for its project executive to verify that the project
team prepares all of the required project management and other
required plans. This formal process should also include a process
to periodically verify that the project team is adhering to all
these plans.
To ensure accountability and independence between the provision
of IPO and IV&V services on future IT projects, by September 2016
CalVet should establish a policy requiring it to use separate
contractors for IPO and IV&V services when IPO services are not
provided directly by the Technology Department.
To ensure that it complies with state contracting laws and can
demonstrate the basis for its decisions when awarding contracts, by
September 2016 CalVet should establish a process to periodically
verify that its staff follow state contracting requirements and
maintain all required contract documentation.
California State Auditor Report 2015-121 49
June 2016
To ensure it maintains all documentation related to its IT contracts,
CalVet should, by September 2016, establish a process to verify
that all divisions comply with its policy requiring each division to
submit a records retention schedule to its Office of Procurement
and Contracting.
To ensure that it only accepts deliverables and approves payment
for deliverables that are complete and meet contract requirements,
by September 2016 CalVet should establish processes to do
the following:
• Ensure that the project executive verifies that individuals
assigned to project roles are adequately qualified
and experienced.
• Verify and maintain documentation of receipt of all contract
deliverables before approving payment.
• Strengthen its contract management on all future projects by
requiring the project manager to sign off on invoices along with
the contract manager before approving payment.
To ensure that it maximizes its opportunity to successfully
implement future IT projects, including its plan to replace its
current system, CalVet should, by September 2016, establish a
formal process to do the following:
• Document the changes it makes as a result of the lessons‑learned
sessions it conducts.
• Verify that its staff conducts lessons‑learned sessions for all key
phases of the next project.
• Incorporate the recommendations identified in its PIER.
Technology Department
To ensure that it can demonstrate that it is acting in the best
interest of the State, the Technology Department should, by
December 2016, create a formal process to summarize its
involvement and document key actions taken and decisions
reached during agencies’ contract disputes and negotiations for the
termination of a contract and maintain those documents according
to its record retention schedule.
50 California State Auditor Report 2015-121
June 2016
To ensure accountability and independence between the provision
of IPO and IV&V services, the Technology Department should,
by December 2016, establish a written policy requiring departments
that request and receive approval to contract for IPO services to use
a different contractor than the one providing IV&V services.
Although the Technology Department indicated that its intent
is not to outsource its statutory responsibility for IPO, in any
instances where its staff conduct a portfolio review of a project’s
IPO, the Technology Department should, by December 2016,
establish a process for its review of documents created by the
agency’s IPO contractor that includes verifying whether these
reports include critical analysis of project progress and vendor
performance so it can intervene when necessary.
We conducted this audit under the authority vested in the California State Auditor by Section 8543
et seq. of the California Government Code and according to generally accepted government auditing
standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate
evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives
specified in the Scope and Methodology section of the report. We believe that the evidence obtained
provides a reasonable basis for our findings and conclusions based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
State Auditor
Date: June 16, 2016
Staff: Tammy Lozano, CPA, CGFM, Audit Principal
Richard D. Power, MBA, MPP
Fahad Ali, CFE
Brian D. Boone, CIA, CFE
Karen Jenks, MBA
IT Expert: Catalysis Group
Legal Counsel: J. Christopher Dawson, Senior Staff Counsel
For questions regarding the contents of this report, please contact
Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
California State Auditor Report 2015-121 51
June 2016
Appendix A
COMPARISON OF THE CALIFORNIA DEPARTMENT
OF VETERANS AFFAIRS’ ESTIMATED AND ACTUAL
COSTS FOR THE ENTERPRISE‑WIDE VETERANS HOME
INFORMATION SYSTEM
The Joint Legislative Audit Committee asked us to determine the
estimated and actual costs, as well as the estimated and actual
timelines, for the California Department of Veterans Affairs’
(CalVet) Enterprise‑Wide Veterans Home Information System
(system) project. Table A.1 on the following page presents CalVet’s
estimated and actual costs for implementing this system.
As shown in Table A.1, CalVet initially estimated the costs to
implement the system in its feasibility study report (FSR) at just
under $34 million. CalVet increased its estimate as the project
progressed. However, the actual costs of implementation, as of
the completion of its post‑implementation evaluation report in
June 2015, were lower than its estimate, at roughly $27.9 million.
Although the cost of the project was nearly $9 million less than the
last approved special project report (SPR), CalVet implemented
much less functionality than it initially planned for and that
was approved in its FSR and subsequent SPRs. Specifically, as
discussed on page 22, because of the functionality problems that
staff encountered during implementation of the system at the
first few veterans homes, CalVet indicated that staff either did
not receive training or received training on a minimal number of
components for the ADL Clinical module functionalities at the
Fresno, Redding, and Yountville homes; the ADL Clinical module
is a main module of the system through which the homes manage
electronic health records. According to their administrators, two of
the homes continue to use paper processes to document resident
medical information, while a third home uses the previous system,
Meditech. Therefore, CalVet spent $27.9 million for implementation
of a system that has not been fully implemented at all of the homes,
and it did not fulfill one of its primary goals for the project—a
fully integrated system of care in which the system used at any
home could seamlessly operate with the other homes and in which
veterans would receive consistent care throughout the homes—and
therefore, does not meet the needs of the veterans homes.
52 California State Auditor Report 2015-121
June 2016
Table A.1
Estimated and Actual Costs for Implementation of the California Department
of Veterans Affairs’ Enterprise-Wide Veterans Home Information System
DOCUMENT
PROJECT DOCUMENT DATE ESTIMATED COSTS ESTIMATED COMPLETION DATE
Feasibility Study Report December 2006 $33,982,315 December 2010
Special Project Report #1 August 2008 35,469,331 June 2012
Special Project Report #2 November 2010 37,311,098 October 2013
Special Project Report #3 October 2012 36,744,638 April 2014
ACTUAL COSTS ACTUAL COMPLETION DATE
California State Accounting
and Reporting System NA 27,914,733* June 2015†
Reports (CalSTARS)
Sources: Documents referenced in the table column titled Project Document and the respective
approval letters, if applicable, for these documents.
NA = Not applicable.
* Costs recorded in CalSTARS are from July 1, 2007, through June 30, 2015. Costs include CalVet’s
and the system contractor’s settlement agreement amount of $350,000.
† In June 2015 the California Department of Veterans Affairs (CalVet) submitted its
post-implementation evaluation report to the California Department of Technology in support
of its request to consider the project complete and to terminate project reporting.
Comparison of CalVet’s Estimated and Actual Timelines to Implement
the System
Table A.2 presents CalVet’s estimated and actual dates for
completing major project milestones to implement the system.
CalVet initially estimated the project schedule in the FSR and
updated the estimated dates in the subsequent SPRs. CalVet
extended the overall project schedule in each of the SPRs.
Specifically, although CalVet originally expected to complete the
system (final acceptance) by December 2010, the system was still
not complete in January 2015, when, as we describe on page 30,
CalVet and the California Department of Technology agreed to
close the project. Several factors contributed to project delays. For
instance, CalVet’s initial request for proposal (RFP) was delayed
because of changes that were made to the project scope, such as
the decision to implement the system at the Fresno and Redding
homes. In addition, CalVet issued a second RFP with updated
system requirements after its initial RFP failed to generate any
responsive proposals. CalVet also delayed the implementation of
the system at the Chula Vista home to provide additional support
to some of the pilot homes that were struggling with certain
complex functionalities of the system. Finally, CalVet postponed
the implementation of the system at the Fresno and Redding homes
because of delays in the opening of those homes.
California State Auditor Report 2015-121 53
June 2016
Table A.2
California Department of Veterans Affairs’ Enterprise-Wide Veterans Home Information System Timeline Comparison
ESTIMATED COMPLETION DATES
FEASIBILITY STUDY SPECIAL PROJECT SPECIAL PROJECT SPECIAL PROJECT
REPORT REPORT #1 REPORT #2 REPORT #3 ACTUAL
MAJOR MILESTONES DECEMBER 2006 AUGUST 2008 NOVEMBER 2010 OCTOBER 2012 COMPLETION DATES
Solution procurement March 2008 June 2009 December 2010 January 2011 December 2010*
User acceptance testing March 2009 April 2010 September 2011 June 2012 June 2013*
Implementation at headquarters NI NI January 2012† August 2012† May 2012*
Implementation at the Veterans Homes:
Barstow September 2010 March 2012 January 2012†
West Los Angeles April 2010 August 2012
August 2012† May 2012*
Lancaster April 2009 June 2010† May 2012
Ventura April 2009 July 2012
Chula Vista July 2010 January 2012 March 2012 March 2013 June 2013‡
Redding NI April 2011 July 2013 November 2013
Fresno NI July 2011 September 2013 November 2013 November 2013§
Yountville December 2010 June 2012 April 2013 March 2014
Final acceptance December 2010 June 2012 October 2013 April 2014 January 2015ll
Post-implementation evaluation report (PIER) NI June 2013 October 2014 October 2014 June 2015
Sources: California Department of Veterans Affairs’ (CalVet) feasibility study report, special project reports (SPR), the PIER, Enterprise-Wide Veterans
Home Information System Implementation Contract (implementation contract), and Enterprise Wide Veterans Home Information System deliverable
acceptance documents.
NI = Not indicated.
* Dates differ from those presented in CalVet’s PIER. The date for solution procurement differs because CalVet used the effective date of its
implementation contract, as noted in SPR 3, and we used the date that the Department of General Services approved the contract. The date
for user acceptance testing differs because CalVet used the date the system contractor submitted the corresponding deliverable, as noted in
SPR 3, and we used the date that CalVet accepted the deliverable. The date for the implementation differs because CalVet was unable to provide
supporting documentation for the dates it used. Therefore, we relied on the date that CalVet accepted the deliverable.
† In SPR 1, CalVet determined it would implement the system in the homes located in West Los Angeles, Lancaster, and Ventura as a pilot
implementation to validate the system before statewide roll out. In SPR 2, the pilot implementation was reduced to include CalVet headquarters
and the home located in Barstow. In SPR 3, the pilot implementation was expanded to include headquarters and the homes located in Barstow,
West Los Angeles, Lancaster, and Ventura.
‡ Because CalVet did not have a deliverable acceptance document for the implementation in the home in Chula Vista, we relied on the dates CalVet
listed in its PIER.
§ According to the PIER, the implementation at the homes located in Fresno, Redding, and Yountville was not fully completed. Specifically, while the
financial modules were implemented, the clinical modules—by which the homes manage electronic health records—were never implemented at
these homes.
ll In January 2015, CalVet and the California Department of Technology mutually agreed to close the Enterprise-Wide Veterans Home Information
System project.
54 California State Auditor Report 2015-121
June 2016
Blank page inserted for reproduction purposes only.
California State Auditor Report 2015-121 55
June 2016
Appendix B
AN EXPANDED VIEW OF ENTERPRISE‑WIDE VETERANS
HOME INFORMATION SYSTEM USE BY THE CALIFORNIA
DEPARTMENT OF VETERANS AFFAIRS’ VETERANS HOMES
The Joint Legislative Audit Committee asked us to determine
the level of Enterprise‑Wide Veterans Home Information System
(system) use within the California Department of Veterans Affairs’
(CalVet) veterans homes. Table 3 on page 23 provides an overview
of when CalVet implemented the system at its headquarters and
each of the eight veterans homes as well as the extent of the system
modules in use at each of those locations. Table B provides an
expanded view of those data.
Table B
Enterprise-Wide Veterans Home Information System Module Use by Location and Date of Implementation
CHULA WEST
HEADQUARTERS, BARSTOW, VISTA, FRESNO, LANCASTER, REDDING, VENTURA, LOS ANGELES, YOUNTVILLE,
COMPONENTS MAY 2012 MAY 2012 JUNE 2013 NOVEMBER 2013 MAY 2012 NOVEMBER 2013 MAY 2012 MAY 2012 NOVEMBER 2013
ADL Clinical
Software designed to address critical functions of providing long-term care by capturing and managing patient information.
1. Rehabilitation (Rehab) Touch NA F F NI NA F NA F F
2. Rehab Editor NA F F NI NA NI NA F F
3. Care Plans NA F F NI F NI F F NI
4. Virtual Body NA P P NI F NI P N NI
5. Certified Nursing Assistant (CNA) NA F N NI F NI F F NI
6. CNA Reports NA F N NI F NI P P NI
7. CNA Assignments NA F P NI F NI F F NI
8. Progress Notes NA F F NI F NI F F NI
9. Shift Reports NA N N NI F NI F N NI
10. Assessments NA P P NI F NI F P NI
11. Rehab Assessment NA F N NI NA NI NA F NI
12. Vitals NA F N NI F NI F F NI
13. Order Entry NA P N NI N NI N N NI
14. Electronic Medication
Administration Record
NA N N NI N NI N N NI
(eMAR)/ Electronic Treatment
Authorization Request (eTAR)
15. Minimum Data Set (MDS) NA F F F NA F NA F F
16. Clinical Dashboards N P N NI P NI P N NI
17. Quality Assurance NA NA NA NI NA NI NA NA NI
18. Infection Control NA N F NI F NI F P NI
19. Allergy Management NA F F NI P NI F F NI
20. Diagnosis Management NA F F NI F NI F F P
21. Facility Reports—
F P P NI P NI F P NI
Clinical/Order Reports
22. Precautions NA F F NI N NI F P NI
23. Forms N F P NI P NI F P NI
continued on next page . . .
56 California State Auditor Report 2015-121
June 2016
CHULA WEST
HEADQUARTERS, BARSTOW, VISTA, FRESNO, LANCASTER, REDDING, VENTURA, LOS ANGELES, YOUNTVILLE,
COMPONENTS MAY 2012 MAY 2012 JUNE 2013 NOVEMBER 2013 MAY 2012 NOVEMBER 2013 MAY 2012 MAY 2012 NOVEMBER 2013
ADL Financial
Software used to support third-party billing, Medi-Cal, Medicare, accounts receivable, transaction history, withdrawals and charges; making, tracking, and controlling
financial events.
24. Admissions, Discharge,
NA F F F F F F F F
Transfers (ADT) Registration
25. ADT History F F F F P F P F F
26. Census Actions NA F F F P F F F F
27. Census Control NA F F F P F F F F
28. ADT Corrections NA F F F N F F F F
29. Trust Funds NA F F F F F F F F
30. Cash Receipts NA F F F P F F F F
31. Cash Receipts—
P P P P P F P P F
Veterans Affairs (VA) Per Diem
32. Online Receipts NA F F F F F F N F
33. Batch Receipts NA F F F F F F F F
34. Rating Calculation NA F F F F F F F F
35. Paysources F F F P P P F P F
36. Medicare NA F F P P P F P F
37. Insurances F F F F N F F F F
38. Rehab Module NA F F NI N NI N N F
39. Ancillary Charges NA F F P N P F P F
40. Professional F F F N N N N N F
41. Wait List NA F F F P F F F F
42. Billing F F F N P N F N F
43. Pre-Billing P P P F N F F P P
44. Off Hours Admissions by Nurses NA F F F F F F F F
45. Forms NA F F F F F F F NI
46. Dashboards F P P F N P N P NI
47. Immunizations NA F P NI F NI F F NI
48. VA Per Diem Charges P F F F P F F F F
49. VA Per Diem Cash Receipts F N N N N F N N F
50. Veterans P F F F P F F F F
51. Ledgers F F F F F F F F F
52. Medical Diagnosis F F F F F F F F F
53. Reports F F F F F F F F F
54. MDS Data P F F P NA P NA P F
55. Recurring Charges N N N N N N N N N
56. Errors Tracking P F F F F F F F F
57. TAR Authorizations-
P F F N NA N NA N P
Medi-Cal TARs
58. Expected Income and Budget F N N N N N N N N
59. End Period Process F F F F F F F F F
California State Auditor Report 2015-121 57
June 2016
CHULA WEST
HEADQUARTERS, BARSTOW, VISTA, FRESNO, LANCASTER, REDDING, VENTURA, LOS ANGELES, YOUNTVILLE,
COMPONENTS MAY 2012 MAY 2012 JUNE 2013 NOVEMBER 2013 MAY 2012 NOVEMBER 2013 MAY 2012 MAY 2012 NOVEMBER 2013
Dynamics
Financial accounting and business management software that automates creation and management of accounting data and workflow. Used to augment ADL Financial
to support financial management. The specific component used is for purchasing and inventory.
60. Purchasing and Inventory N F P F F F F F F
GeriMenu
Software used for resident meal planning to help facilities run their nutrition departments more efficiently.
61. Resident Meal Planning NA P P F N NI N F P
Documentum
An enterprise content management system used to house and manage electronic documents.
62. Document Management N F N NI N NI F F NI
Framework LTC
Pharmacy management software designed for long-term care and institutional facilities.
63. Pharmacy Management NA F F NI N NI F F F
Sources: California Department of Veterans Affairs’ (CalVet) system use chart provided by the system final project manager, and confirmed or updated by staff at
headquarters and the eight homes, draft system architecture design document, and the CBORD Group Inc. Gerimenu website, and system contractor’s response to the
request for proposals.
F = The veterans home indicated it fully used this module.
P = The veterans home indicated it partially used this module.
N = Although CalVet implemented the module, headquarters or the veterans home indicated it did not use it.
NI=CalVet did not implement the module at the veterans home.
NA= Although these modules were available for use, staff at headquarters or the homes indicated the components marked NA were generally not applicable for
their operations.
58 California State Auditor Report 2015-121
June 2016
Blank page inserted for reproduction purposes only.
California State Auditor Report 2015-121 59
June 2016
STATE OF CALIFORNIA Edmund G. Brown Jr., Governor
DEPARTMENT OF VETERANS AFFAIRS
OFFICE OF THE SECRETARY
POST OFFICE BOX 942895
SACRAMENTO, CALIFORNIA 94295-0001
Telephone: (916) 653-2158
Fax: (916) 653-2456
June 9, 2016
Elaine M. Howle, State Auditor
Bureau of State Audits
621 Capitol Mall, Suite 1200
Sacramento, CA 95814
Dear Ms. Howle:
Thank you for the opportunity to review and comment on the redacted copy of the California
State Auditor (CSA) draft report titled, “The State Paid Nearly $28 Million for a Flawed System
That Fails to Meet the Needs of Veterans Homes.”
At the request of the Joint Legislative Audit Committee, the CSA conducted an audit of the
California Department of Veterans Affairs (CalVet) Enterprise-wide Veteran Home Information
System (Ew-VHIS) Project. The project was initiated in 2007 via an approved Feasibility Study
Report (FSR) by the California Department of Technology (CDT) and concluded in 2015 with
the goal to implement an Electronic Health Record System for its eight veteran homes.
As further explained below, CalVet generally agrees with allseven recommendations in the State
Auditor’s report, which serve to introduce departmental processes and policies related to
information technology projects at CalVet.CalVet also agrees with the Report’s references to
costs and scope. We take our fiduciary responsibilities very seriously and remaincommitted to
the safeguarding of public resources.
In retrospect, we could have moved more quickly or acted with greater urgency. However,
CalVet took steps to address our concerns about the project. In December 2013, we reported
critical concerns about the project to CDT and then, in partnership with CDT, took the initiative
toimplement stronger IT project management processes and practices, in alignment with industry
best practices and standards, to prevent a similar situation in the future. Some of the new
processesinclude the implementation of the following plans for current and future projects:
• Project Governance Plan
• Project Change Management Plan
• Project Requirements Management Plan
• Project Risk and Issue Management Plan
• Project Test Management Plan
CalVet is also under new leadership, includingmyself as SecretaryandRussell Atterberry as
Undersecretary, and we believe that the Auditor’s recommendations will further
HONORING CALIFORNIA’S VETERANS
60 California State Auditor Report 2015-121
June 2016
Elaine M. Howle
June 9, 2016
Page 2
strengthen the department in areas of project oversight, project management, and contract
managementgoing forward. Furthermore, I believe CalVet has already made great strides
towards implementing the resolutions.
CalVetrecently began the process to find a replacement system. On May 31, 2016, the
department successfully completedthe first of four stages of the contracting process. CalVet aims
for implementation of the replacement system in 2017.
The following are CalVet’sspecific responses to each recommendation provided within the
report.
Recommendation #1
To ensure that its project management of IT projects promptly identifies problems and develops
resolutions, by September 2016, CalVet should define the project executive and project manager
responsibilities to ensure that the individuals who fill those positions take an active role on each
project.
CalVet Response #1
CalVet understands and agrees with this recommendation. Existing IT projects at CalVet
have documented roles and responsibilities for the project executive, project manager,
and project team. A governance plan is created for each IT project to define the
escalation process and ensure effective risk and issue management.
Recommendation #2
To ensure that it adequately identifies and monitors problems in its future IT projects, by
September 2016, CalVet should establish a formal process for its project executive to verify that
the project team prepares all of the required project management and other required plans. This
formal process should also include a process to periodically verify that the project team adheres
to all these plans.
CalVet Response #2
CalVet understands and agrees with this recommendation. Existing IT projects at CalVet
have documented formal processes for ensuring required project management plans are
created, adhered to, and kept up to date, in accordance with the policies of our control
agencies. CalVet is currently working on its IT governance structure, which will be rolled
out in a phased approach. By September 2016, the IT governance structure will
implement a formal process for ensuring a project executive is identified for each IT
project. This project executive will verify that the project team prepares required plans
and ensures the plans are followed.
Recommendation #3
To ensure accountability and independence between the provision of Independent Project
Oversight [IPO] and Independent Verification and Validation [IV&V] on future IT projects, by
September 2016, CalVet should establish a policy requiring it to use separate contractors for IPO
and IV&V services when IPO services are not provided directly by CDT.
HONORING CALIFORNIA’S VETERANS
California State Auditor Report 2015-121 61
June 2016
Elaine M. Howle
June 9, 2016
Page 3
CalVet Response #3
CalVet understands and agrees with this recommendation. In late 2013, CalVet reported
this issue to the CDT relative to the Ew-VHIS project. While previously IPO and IV&V
services were provided by the same contractor, CalVet ensured the CDT provided IPO
services moving forward. CalVet is currently drafting a department-wide IT policy to
ensure IPO and IV&V services on future IT projects use separate contractors for each
service. CalVet expects to have this policy implemented by no later than September 2016.
Recommendation #4
To ensure that it complies with state contracting laws and can demonstrate the basis for its
decisions when awarding contracts, by September 2016, CalVet should establish a process to
periodically verify that its staff follows state contracting requirements and maintainsall required
contract documentation.
CalVet Response #4
CalVet understands and agrees with this recommendation. By September 2016, a formal
process will be implemented to periodically verify that state contracting requirements are
followed and contract documentation is maintained and kept current.
Recommendation #5
To ensure it maintains all documentation related to its IT contracts, CalVet should,by September
2016, establish a process to verify that all divisions comply with its policy requiring each
division to submit a records retention schedule to its Office of Procurement and Contracts.
CalVet Response #5
CalVet understands and agrees with this recommendation. By September 2016, a formal
process will be implemented to ensure that each division submits a records retention
schedule to its Office of Procurement and Contracts as required by departmental policy.
Recommendation #6
To ensure that it only accepts and pays for deliverables that are complete and meet the contract
requirements, by September 2016, CalVet should establish a process to verify and maintain
documentation of all contract deliverables before approving payment.
CalVet Response #6
CalVet understands and agrees with this recommendation. This is an existing practice at
CalVet for acceptance and payments related to all IT contracts and associated
deliverables. By September 2016, a formal process will be created to reinforce this
expectation of all contract managers.
HONORING CALIFORNIA’S VETERANS
62 California State Auditor Report 2015-121
June 2016
Elaine M. Howle
June 9, 2016
Page 4
Recommendation #7
To ensure that it maximizes its opportunity to successfully implement future IT projects, by
September 2016, CalVet should establish a formal process to verify that its staff conducts lessons
learned sessions for all key phases of future projects and incorporate the recommendations
identified in its post implementation evaluation.
CalVet Response #7
CalVet understands and agrees with this recommendation. Currently, CalVet is applying
this process to existing IT projects. By September 2016, the management expects to
conduct lessons learned sessions for all key phases of future projects and incorporate the
recommendations identified in its post implementation evaluation report in future
projects and/or project phases via a formalized process.
Sincerely,
Vito Imbasciani MD
Secretary
HONORING CALIFORNIA’S VETERANS
California State Auditor Report 2015-121 63
June 2016
May 24, 2016
Elaine M. Howle, State Auditor
California State Auditor
621 Capitol Mall, Suite 1200
Sacramento, CA 95814
Re: CALIFORNIA STATE AUDITOR’S REPORT NO. 2015-121
Pursuant to the above audit report, enclosed are the Department
of Technology’s comments pertaining to the results of the
audit.
The Government Operations Agency would like to thank the state
auditor for its comprehensive review. The results provide us with
the opportunity to better serve our clients and protect the public.
Sincerely,
Marybel Batjer, Secretary
Government Operations Agency
Enc
64 California State Auditor Report 2015-121
June 2016
CALIFORNIA DEPARTMENT OF TECHNOLOGY State of California
Amy Tong, Interim Director Edmund G. Brown Jr., Governor
Memorandum
To: Marybel Batjer, Secretary Date: May 24, 2016
Government Operations Agency
J4
From: Amy Tong, Interim Director
California Department of Technology
Subject: Response to California State Auditor's Draft Report No. 2015-121
We are providing for your review the draft California State Auditor's Report No.
2015-121 concerning CalVet's Enterprise Wide Veterans Home Information System
(EWVHIS). The following responses address the California State Auditor's
recommendations regarding the California Department of Technology's (CDT)
operations.
RECOMMENDATIONS
RECOMMENDATION #1: To ensure it can demonstrate that it acts in the best interest
of the State, the Technology Department should, by December 2016, create a formal
process to summarize its involvement and document key actions taken and decisions
reached during agencies' contract disputes and negotiations for the termination of a
contact and maintain those documents according to its record retention schedule.
Department of Technology's Response #1:
The Department of Technology agrees with this recommendation. CDT will develop
internal procedures for documenting the formal process associated with contract dispute
or contract termination negotiations. The procedures would include retaining a
summary of negotiation outcomes which will be maintained with applicable law and
CDT's records retention schedule.
RECOMMENDATION #2: To ensure accountability and independence between the
provisions of /PO and IV&V services, the Technology Department should, by December
2016, establish a written policy requiring departments that request and receive approval
to contract for /PO services to use a different contractor than the ones providing IV& V
services.
California State Auditor Report 2015-121 65
June 2016