CSA
Recommendations
Read the report at California State Auditor ↗
August 2018
Toll Bridge
Seismic Retrofit Program
The State Could Save Millions of Dollars Annually by
Implementing Lessons Learned
Report 2018-104
COMMITMENT
INTEGRITY
LEADERSHIP
CALIFORNIA STATE AUDITOR
621 Capitol Mall, Suite 1200 | Sacramento | CA | 95814
916.445.0255 | TTY 916.445.0033
For complaints of state employee misconduct,
contact us through the Whistleblower Hotline:
1.800.952.5665
Don’t want to miss any of our reports? Subscribe to our email list at auditor.ca.gov
For questions regarding the contents of this report, please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255
This report is also available online at www.auditor.ca.gov | Alternate format reports available upon request | Permission is granted to reproduce reports
Elaine M. Howle State Auditor
August 28, 2018 2018-104
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the California State Auditor presents this audit
report concerning the Toll Bridge Seismic Retrofit Program (seismic program) including work to replace
a section of the San Francisco–Oakland Bay Bridge construction project. This report concludes that the
State could save millions of dollars annually by mandating oversight and risk management lessons learned
from the seismic program.
We found that the effective use of oversight and risk management in the $9 billion seismic program
provides a valuable lesson for the State. In 2005, concerned about escalating costs, the Legislature created
the Toll Bridge Program Oversight Committee (Oversight Committee) to oversee the seismic program,
and required the California Department of Transportation to develop a comprehensive risk management
plan. These two factors minimized delays and controlled costs. For example, Oversight Committee
decisions resulted in cost avoidance and savings totaling at least $505 million. Moreover, comprehensive
risk management played a critical role in preventing more than $455 million in potential costs and
seven years in probable delays. With more than $600 billion in transportation infrastructure projects
projected to occur over the next several decades in three of the State’s largest metropolitan areas alone, a
lack of sufficient oversight and risk management could result in significant delays and cost escalations that
taxpayers ultimately would bear. Requiring early oversight committee involvement and risk management
plans for major publicly funded transportation projects could mitigate these risks and ensure transparency
and accountability throughout California.
Further, we found that the seismic program will end in 2019 roughly on budget at a cost of about $9 billion;
however, maintenance and debt service costs will continue. The seismic program experienced significant
cost growth between 1997 and 2005, before additional oversight helped to stabilize the cost. Revenues
from tolls on San Francisco Bay Area bridges, as well as debt backed by that revenue, accounts for nearly
two-thirds of all funds for the seismic program and will pay for maintenance costs in the future. The
Bay Area Toll Authority (Toll Authority) is responsible for administering toll revenues. As of the end
of fiscal year 2016–17, the Toll Authority projects that its remaining debt service payments—principal
and interest on all of its current bonds—through fiscal year 2055–56 will total $18.7 billion. The Toll
Authority had also projected the possible need for a toll increase in fiscal year 2026–27; however, it will be
reevaluating its projections in light of a recent voter-approved measure to increase tolls to fund a variety
of transportation projects.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
621 Capitol Mall, Suite 1200 Sacramento, CA 95814 916.445.0255 916.327.0019 fax www.auditor.ca.gov
iv California State Auditor Report 2018-104
August 2018
Blank page inserted for reproduction purposes only.
California State Auditor Report 2018-104 v
August 2018
Contents
Summary 1
Introduction 5
Audit Results
Lessons Learned From the Seismic Program Could Improve
the State’s Oversight of Future Projects 15
The Remediation of Defective Components on the Bay Bridge
Represented a Small Portion of the Project’s Total Costs 24
The Seismic Program Will Cost About $9 Billion, but Debt
Service and Ongoing Maintenance Costs Will Continue 27
Recommendations 34
Appendix
Funding Sources for the Seismic Program 37
Response to the Audit
Metropolitan Transportation Commission 39
California State Auditor’s Comments on the Response
From the Metropolitan Transportation Commission 41
vi California State Auditor Report 2018-104
August 2018
Blank page inserted for reproduction purposes only.
California State Auditor Report 2018-104 1
August 2018
Summary
Audit Highlights . . .
Results in Brief
Our audit regarding the management
of seismic program costs highlights
The Toll Bridge Seismic Retrofit Program (seismic program), and the following:
particularly the work completed within the program to replace a
» The legislatively mandated oversight
section of the San Francisco—Oakland Bay Bridge (Bay Bridge),
of the seismic program successfully
is one of the most expensive and controversial transportation
minimized potential delays and
infrastructure programs in California history. It is also a valuable
controlled costs.
lesson on how a major project experienced rapid cost escalations
before the implementation of robust oversight and risk management
• Oversight Committee decisions
brought them under control.
resulted in hundreds of millions of
dollars in cost avoidance and savings.
By 2005 the projected costs of the seismic program had soared far
beyond the initial estimates of $2.6 billion to $8.7 billion. In response • The comprehensive risk management
to the seismic program’s growing price tag, we recommended in a implemented for the seismic program
2004 audit report that the California Department of Transportation ultimately avoided more than
(Caltrans) increase its risk management of the program. Following $455 million in potential costs and
our review, the Legislature imposed certain requirements on Caltrans seven years of potential delays.
and the seismic program that included the establishment of an
» Large-scale transportation infrastructure
oversight committee, known as the Toll Bridge Program Oversight
projects have posed challenges for
Committee (Oversight Committee), which is required to provide
public entities and state statutes do
program management and approve significant change orders.
not generally require all state and local
Beginning in 2005, this legislatively mandated oversight of the seismic
sponsors of such projects to institute
program successfully minimized potential delays and controlled
oversight and risk management.
costs. For example, the Oversight Committee cites its decision to
alter the method used to demolish the old east span of the Bay Bridge
• A lack of mandated oversight and risk
(east span) as saving $94 million and cutting the demolition time
management could result in project
by four years. In aggregate, our review indicates that Oversight
delays and cost escalations.
Committee decisions resulted in hundreds of millions of dollars in
cost avoidance and savings. The seismic program also benefitted from » Expenses related to the repair or
a 2005 state law requiring Caltrans to implement comprehensive replacement of components accounted
risk management for the program that would inform Oversight for a small portion of the Bay Bridge
Committee decisions. Caltrans documentation indicates that this project’s overall cost.
approach ultimately avoided more than $455 million in potential costs
» Although the seismic program will end
and seven years of potential delays related to the seismic program.
roughly on budget in 2019, borrowing
and maintenance costs are significant and
Large-scale transportation infrastructure projects—federal
will continue for decades.
law defines a major highway project as one costing over $500
million—such as the seismic program have posed challenges for
public entities in California, and we identified no state statute
that generally requires all state and local sponsors of large
transportation infrastructure projects to institute oversight and risk
management similar to what it requires in the seismic program.
With more than $600 billion in anticipated infrastructure projects
contemplated in the next several decades in just three of the State’s
largest metropolitan areas, a lack of mandated oversight and risk
management could result in project delays and cost escalations.
For example, San Francisco’s Transbay Terminal experienced cost
2 California State Auditor Report 2018-104
August 2018
increases of $1.1 billion before instituting additional oversight
through a cost review committee and increased involvement
by the San Francisco Department of Public Works to manage
construction. Without additional mandated oversight and risk
management, future projects will face significant risk of similar cost
increases that must be borne by the State and local governments,
and ultimately the taxpayers who support them.
Our review also suggests that expenses related to the repair or
replacement of components accounted for a small portion of the
Bay Bridge project’s overall cost. Specifically, we determined that
the project has resulted in at least $86 million worth of work to
address defects—using a definition of defect based on project
management best practices. Our review noted instances in which
Caltrans had to pay to repair or replace a component after a
contractor had installed it, as well as problems with fabrication
that ultimately led to additional costs. For example, Caltrans spent
more than $22 million remediating issues involving broken bolts—
widely reported in the media—intended to anchor portions of the
east span. However, our identification of costs associated with
remediation of defects does not indicate the presence of current
safety issues on the bridge, as multiple panels of engineers and
construction experts have concluded that critical components
of the bridge are safe. Further, although $86 million represents
a significant investment of funds, in the context of the overall
$6.6 billion Bay Bridge project it amounts to only 1.5 percent of
the total cost.
Although the seismic program will end roughly on budget in 2019,
borrowing and maintenance costs are significant and will continue
for decades. Funding for the seismic program includes a mix of
state, federal, and, overwhelmingly, regional bond funds backed by
tolls paid by drivers crossing the seven state-owned San Francisco
Bay Area (Bay Area) toll bridges. As of June 2017, the Bay Area
Toll Authority (Toll Authority) held $9 billion in bond debt for the
seismic program and other transportation projects, and will pay
approximately $9 billion in interest over the life of those bonds—
as far out as 2056. Routine and long-term maintenance costs on
bridges in the Bay Area amounted to more than $100 million in
fiscal year 2016–17, and while the Toll Authority anticipates that
those costs will continue to increase over time, it projects it will
have sufficient revenue to meet its obligations well into the future.
California State Auditor Report 2018-104 3
August 2018
Selected Recommendations
Legislature
To ensure that large transportation infrastructure projects
throughout the State benefit from appropriate oversight, the
Legislature should require that all publicly funded major
transportation infrastructure construction projects that are
estimated to cost $500 million or more form oversight committees
subject to open meeting laws. When practical, each oversight
committee should include individuals from at least three major
agencies involved in the project, with roles that reflect financial
interests as well as project execution and oversight. Further, when
possible, each committee should include at least five members to
support the ability of its members to conduct day-to-day business
without violating open meeting law requirements. The oversight
committees should act as the authorities for critical decisions and
have sufficient staff to support decision-making.
To ensure that oversight committees and the agencies involved in
large transportation infrastructure projects engage in sufficient and
appropriate risk management, the Legislature should also require
all publicly funded transportation infrastructure projects with a
total estimated cost of $500 million or more to develop and use risk
management plans throughout the course of the projects.
Agency Comments
The Metropolitan Transportation Commission agreed with
our recommendations and provided its perspective on our
recommendations to the Legislature.
4 California State Auditor Report 2018-104
August 2018
Blank page inserted for reproduction purposes only.
California State Auditor Report 2018-104 5
August 2018
Introduction
Background
In October 1989, the Loma Prieta earthquake caused the collapse
of a section of a highway in Oakland and a section of the upper
deck of the San Francisco–Oakland Bay Bridge (Bay Bridge). Under
state law, the California Department of Transportation (Caltrans)
is responsible for maintaining and reconstructing state highways
and state toll bridges. Following the earthquake, Caltrans began to
use hazard analyses based on individual bridge locations to address
the effects of probable seismic events—and for critical structures
such as the Bay Bridge—to incorporate projections of the strongest
credible earthquake into their retrofit or replacement calculations.
In 1996 the State established a retrofit program to meet the latest
seismic safety standards. This program, which Caltrans based
on likely seismic events, required the retrofit or replacement of
California’s state-owned toll and highway bridges.
Caltrans is responsible for the retrofit or replacement of the
state-owned toll bridges separately from other bridges in the State,
and manages the Toll Bridge Seismic Retrofit Program (seismic
program), for this purpose. Figure 1 on the following page shows
the locations of the state-owned toll bridges in the San Francisco
Bay Area (Bay Area).1 Following the Northridge earthquake in
January 1994, Caltrans began preparing retrofit strategies for each of
the toll bridges, except for the east span of the Bay Bridge (east span),
which it scheduled for replacement instead. By 2002 Caltrans had
finished seismic retrofits for the Benicia–Martinez, Carquinez, and
San Mateo–Hayward bridges in the Bay Area, and the San Diego–
Coronado and Vincent Thomas bridges in Southern California.2
Caltrans finished retrofitting the main portion of the west span
of the Bay Bridge in 2004 and the Richmond–San Rafael Bridge
in 2005. Figure 2 on page 7 shows the history of the seismic program.
Management of the Seismic Program
Caltrans has been responsible for implementing the seismic
program since 1996. In addition to requiring Caltrans to complete
seismic program projects on Bay Area bridges, state law prior
to 2005 also required Caltrans to report to the Legislature on
1 The Golden Gate Bridge is not a state–owned toll bridge, nor is it a part of the seismic program.
Rather, it is operated by the Golden Gate Bridge, Highway and Transportation District.
2 The eastbound portion of the Carquinez Bridge was retrofit. The westbound replacement
of the Carquinez Bridge, which opened in 2003, was part of Regional Measure 1 (1988) and
not the seismic program. The Legislature later added the remaining two state–owned toll
bridges—the Antioch and Dumbarton bridges—to the seismic program.
6 California State Auditor Report 2018-104
August 2018
program status, issues identified, and actions taken to address those
issues. During this period, a number of factors led to cost increases
in the seismic program, including the cost of steel, contractor
overhead, and support costs. For example, after construction
began on the east span in the early 2000s, the price of steel
increased substantially, while lengthened construction schedules
also contributed to an increased need for contractor overhead and
a corresponding increase in Caltrans support costs.
Figure 1
Bay Area Seismic Program Toll Bridges
1 2
4
3
1
San Francisco–
Antioch Bridge Oakland Bay Bridge 6
3 4
2
Benicia–Martinez 7
Bridge Carquinez Bridge
5
5 6 7
Richmond– San Mateo–
Dumbarton Bridge San Rafael Bridge Hayward Bridge
Source: Oversight Committee quarterly report, first quarter 2018.
Note: The Golden Gate Bridge is overseen by the Golden Gate Bridge, Highway and Transportation District, and is not part of the seismic program.
However, as we described in a prior audit report published
in December 2004—Department of Transportation: Various
Factors Increased Its Cost Estimates for Toll Bridge Retrofits, and
Its Program Management Needs Improving, report 2004-140—
Caltrans failed to provide timely reporting to the Legislature when
it experienced cost overruns on the Bay Bridge. Caltrans also
underestimated its need for additional funds and failed to perform
adequate risk management to quantify the potential for future
cost increases.
California State Auditor Report 2018-104 7
August 2018
Figure 2
History of the Seismic Program
2002
Construction officially begins on the east span
2001 2005
The Legislature sets funding for the The Legislature creates the Oversight Committee,
seismic program at about $5.1 billion authorizes an additional $3.6 billion for the seismic
program, and gives the Toll Authority funding
1997
responsibility for any additional cost overruns on
Caltrans decides to replace rather
the east span of the Bay Bridge
than retrofit the east span
1996 2009
California voters approve Proposition 192, The Legislature adds two bridges—
which authorizes $650 million for the Antioch and Dumbarton—to the
seismic retrofit of state-owned toll bridges seismic program
1989 2013
The Loma Prieta earthquake The east span
causes the collapse of a deck opens to traffic
section on the east span of
the Bay Bridge
1989 1996 1997 2000 2001 2002 2004 2005 2009 2012 2013 2019
Bridge
retrofit or Carquinez, East span of
San Mateo–Hayward West span of Richmond–
replacement and Vincent Thomas San Diego–Coronado, the Bay Bridge San Rafael Antioch Dumbarton the Bay Bridge
and Benicia–Martinez (estimated)
completed
Source: State law and quarterly reports of the Oversight Committee.
In response to these issues, the Legislature provided additional
funding in 2005, but also required Caltrans and the Metropolitan
Transportation Commission (MTC) to establish the Toll Bridge
Program Oversight Committee (Oversight Committee). The
Oversight Committee is required to provide oversight and
management to the seismic program, while reporting regularly to
the Legislature and the California Transportation Commission. As
shown in Figure 3 on the following page, the Oversight Committee
is composed of three members—the chief executives of Caltrans,
MTC, and the California Transportation Commission—who
represent agencies with a wide array of responsibilities. State law
requires the Oversight Committee to provide program direction,
review costs and schedules, and approve significant change orders.
8 California State Auditor Report 2018-104
August 2018
The Oversight Committee has interpreted significant change orders
to mean those over $1 million; Caltrans approves change orders under
$1 million. In addition, the Oversight Committee is to resolve seismic
program issues and regularly update cost estimates.
At the same time it provided additional funding, the Legislature
also consolidated financial management of the seismic program
within the Bay Area Toll Authority (Toll Authority) by placing
Bay Area toll revenues within the Toll Authority’s purview.
State law allows the Toll Authority to issue bonds backed by toll
revenues for a variety of transportation projects including the
seismic program.
Figure 3
Oversight Committee Composition
Members
The Oversight Committee consists of the executive director of the California
Transportation Commission, the director of Caltrans, and the executive
director of the Toll Authority.
Duties
Provides oversight and direction to the State’s seismic program, reviews
project status and costs, evaluates project changes, and provides program
The OVERSIGHT
direction. As part of its duties, the Oversight Committee approves change i
COMMITTEE orders for more than $1 million, resolves issues, and provides quarterly
Executives from . . . reporting to the Legislature, the California Transportation Commission,
and the public. In 2016 the Oversight Committee became subject to open MTC and the Toll
meeting laws. The Oversight Committee is supported by a program Authority are legally
management team that includes staff from each member organization.
separate entities but
share the same staff,
directors, and facility.
California Caltrans MTC Toll Authority
Transportation Plans, designs, constructs, operates, and Provides regional transportation Administers all toll revenues
Commission maintains transportation systems for planning for the Bay Area, which from the state-owned Bay
which it is responsible. Further, Caltrans includes developing a financial Area bridges and sets toll
Advises the secretary of builds bridges and transportation plan for the regional transportation prices subject to certain
transportation and the Legislature facilities, develops risk management system, and seeks to assist in limitations.
on transportation matters. plans for the seismic program, and developing funding sources for
reports on the status of seismic program transportation projects.
projects to the Oversight Committee.
Source: State law and Oversight Committee documents.
California State Auditor Report 2018-104 9
August 2018
To provide the Bay Area with a lifeline structure for use following
an earthquake, the Oversight Committee prioritized timely
completion of the east span over potential cost savings until
the east span opened to traffic in 2013. This decision was in
line with state law, which also recognizes the Bay Bridge as a
lifeline structure. Caltrans designs lifeline structures to remain
functional following a major earthquake in order to facilitate
disaster response activities. In the case of the Bay Bridge, Caltrans
designed the structure to withstand rare but potentially devastating
seismic events expected to occur at the bridge site once in a
1,500-year period.
Bay Area Toll Increases
The Legislature and Bay Area voters have approved a number of toll
increases to accommodate the Bay Area’s regional transportation
needs, including the seismic program. As Figure 4 on the following
page shows, in 1988 voters approved Regional Measure 1, which
in part financed toll bridge rehabilitation and replacement. This
measure established a uniform toll of $1 on state-owned Bay Area
toll bridges; from 1984 through 1988 bridge tolls had averaged about
65 cents. In 1997 the Legislature approved another toll increase to
bring Bay Area tolls to $2 and dedicated the additional toll revenue
to the seismic program.
Voters approved Regional Measure 2 in 2004, which raised tolls
to $3 to fund a number of transportation projects including the
San Francisco Transbay Terminal. The Legislature again increased
tolls in 2005, primarily to support the completion of the east span
of the Bay Bridge. In 2009 the Legislature added the Dumbarton
and Antioch bridges to the seismic program. In 2010, with the
Legislature’s authorization and citing the need for an increase
in the toll rates to fund seismic program work that included the
retrofit of the two additional bridges, the Toll Authority board
voted to increase the base toll by an additional $1. Currently, the
base toll on state-owned Bay Area bridges is $5; however, it can
vary depending on the type of vehicle, time of day, and whether
the vehicle is part of a carpool.3
The Legislature requested this audit in part to ascertain MTC’s and
Caltrans’ ability to manage future projects because of a measure on
the June 2018 ballot, which Bay Area voters subsequently approved.
Regional Measure 3 will increase tolls to fund major transportation
projects. Specifically, tolls will increase by $1 in 2019, 2022, and
2025, thereby eventually raising the base toll on Bay Area bridges
3 The $5 toll does not include the Golden Gate Bridge, which is not part of the seismic program.
10 California State Auditor Report 2018-104
August 2018
to $8. The measure lists $4.5 billion in highway and transit capital
improvements, including support for the Bay Area Express Lane
Network, an expansion in the number of Bay Area Rapid Transit
cars, and a ferry enhancement program. Further, MTC’s regional
transportation plan, Bay Area 2040, which shares certain projects
with Regional Measure 3, anticipates $303 billion in transportation
projects and investments throughout the region by 2040. MTC
estimates that more than $212 billion to support its plan will come
from local and regional sources, including Bay Area tolls. However,
Regional Measure 3 must first pass additional legal scrutiny due to a
lawsuit filed in July shortly after the measure’s passage. The lawsuit
alleges that the measure is in fact either a state tax, which would
require approval by two-thirds of the Senate and Assembly, or a
local special tax that would require approval by two-thirds of voters
from the nine Bay Area counties.
Figure 4
Increase in Base Bay Area Toll Prices Over Time
1988 1997 2004 2005 2010
$$55
$$33 $$44
$$22
$$11
Regional Toll Bridge Regional Amended Addition of
Measure 1 Seismic Measure 2 Toll Bridge Antioch and
Program Seismic Dumbarton to the
Program Seismic Program
Source: State law and documents from MTC’s website.
Note: The base toll on the seven Bay Area bridges is currently $5; however, the Toll Authority has
established discounted rates for carpools and certain low-emission vehicles, as well as variable rates
on the Bay Bridge depending on the time of day. Voters approved an additional $3 in toll increases
in 2018, which will be phased in through 2025.
The Design for Replacing the East Span of the Bay Bridge
In late 1997, Caltrans reported on the cost estimates for several
different design alternatives for the east span between Yerba Buena
Island and the city of Oakland. According to Caltrans, MTC
then became involved in the design selection at the request of
California State Auditor Report 2018-104 11
August 2018
the Governor and Bay Area legislative leaders to ensure that
region-wide interests would be appropriately addressed. Caltrans
recommended construction of a concrete skyway—a form of
elevated freeway—which it estimated would cost $1.2 billion.
However, the Bay Bridge Design Task Force’s Engineering Design
and Advisory Panel, which was formed by MTC, drafted guidelines
that sought to produce a bridge that would be visually memorable,
and in harmony with the existing western span of the Bay Bridge.
After significant public input, in June 1998 MTC selected an
alternative design known as the self-anchored suspension span
(suspension span) rather than the skyway or a different suspension
design. The preliminary estimate for the suspension span design
was $141 million greater than Caltrans’ estimate for the skyway.
While cost increases related to the suspension span have proven
significant, we cannot quantify the potential for similar increases
had the skyway design been implemented. Caltrans predicted
that other design alternatives would be less costly, but the true
cost of these designs is uncertain because the design phase
could not capture all potential costs associated with each of the
design options. For example, another seismic program bridge,
Richmond–San Rafael, underwent significant cost increases due
to complications with its underwater foundation that Caltrans
did not anticipate until construction was underway. Further,
contract bidding for the seismic program took place during a time
of increased market volatility, in which consolidation within the
construction industry resulted in fewer competitors to bid on large
projects. Any bridge design would have been subject to the same
market volatility that influenced cost increases on the east span.
Scope and Methodology
The Joint Legislative Audit Committee (Audit Committee)
directed the California State Auditor (State Auditor) to perform an
audit related to the management of Bay Area bridge costs by MTC,
the Toll Authority, and Caltrans. Table 1 on the following page
outlines the Audit Committee’s objectives and our methods for
addressing them.
12 California State Auditor Report 2018-104
August 2018
Table 1
Audit Objectives and Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, rules, and Reviewed relevant laws, rules, and regulations related to Caltrans, MTC, the California
regulations significant to the audit objectives. Transportation Commission, the Oversight Committee, and the seismic program.
2 a. Review records related to the Bay Bridge • Reviewed Caltrans’ expenditure reports and the Oversight Committee’s quarterly
construction project to determine the source reports from 2005 through the first quarter of 2018.
of funding used to pay for cost overruns of
• Identified and documented costs associated with the seismic program and work
the Bay Bridge project and whether there are
concerning the east span of the Bay Bridge in particular.
any existing obligations, including debt, from
those overruns. • Interviewed MTC and Caltrans financial staff and reviewed documentation related to
cost savings and funding sources.
• Reviewed the Toll Authority’s audited financial statements to determine the authority’s
debt and debt service payments.
b. Review records related to the Bay Bridge • Reviewed MTC documents and the Oversight Committee’s quarterly reports,
construction project to determine whether and interviewed key Caltrans staff regarding retrofitting the Antioch and
the Bay Bridge project cost overruns affected Dumbarton bridges.
capital improvement projects on other
• Reviewed Caltrans documentation showing estimated completion dates for seismic
Bay Area bridges. If funding was diverted
program bridges and compared them to the respective completion dates. For bridges
from other projects to pay for the overruns,
with completion delays, we reviewed Caltrans documentation to ascertain the cause.
determine what plans exist to pay for those
other projects.
c. Review records related to the Bay Bridge • Worked with Caltrans staff to confirm outstanding contract costs for the east span.
construction project to determine whether
• Reviewed contingency data provided by Caltrans to confirm the amount remaining for
there is any continued financial risk as a result
future costs on the Bay Bridge.
of the construction of the Bay Bridge and,
if so, what funding source is planned to cover • Reviewed MTC documentation for tracking maintenance costs.
the risk. • Interviewed Caltrans and MTC staff to obtain their perspective on ongoing risks and
costs on the Bay Bridge.
3 Determine the total cost of Bay Bridge defects • Interviewed Caltrans staff to gain Caltrans’ perspective on defects.
identified by MTC, the Toll Authority, and
• Reviewed reports and correspondence from MTC and Caltrans regarding defects on
Caltrans and the source of funds that have
the Bay Bridge.
been used or are planned to be used to pay
for remediation of those defects. To the extent • Consulted the Project Management Institute’s Guide to the Project Management Body
possible, for each defect, determine the cost of Knowledge for guidance regarding the definition of defect.
associated with remediation.
• Obtained more than 2,000 contract change orders related to permanent work on the
east span.
• Judgmentally selected and reviewed more than 800 contract change orders based
on terms indicating repairs or replacements, as well as information provided in
correspondence from MTC and the Oversight Committee’s quarterly reports.
• Identified instances in the reviewed contract change orders where Caltrans or the
Oversight Committee approved and paid for repairing or replacing bridge components.
• Calculated the costs of defect remediation and determined applicable funding sources.
4 Determine whether MTC and Caltrans have • Reviewed Caltrans reports, legislative reports, and prior audits regarding seismic
modified their approaches to prevent and retrofit project management and oversight.
address cost overruns on major infrastructure
• Interviewed Caltrans and MTC staff to get their perspective on how their approach to
projects since the construction of the Bay Bridge.
large infrastructure projects changed due to their experience with the seismic program.
As part of this effort, identify any steps that
MTC and Caltrans have taken to reduce project • Interviewed staff and reviewed documentation regarding the use of oversight and risk
defects or budget for defect remediation. management on Caltrans projects.
California State Auditor Report 2018-104 13
August 2018
AUDIT OBJECTIVE METHOD
5 Identify any risk-management plans MTC • Interviewed MTC staff and reviewed documentation related to risk management
has developed to properly spend and by MTC.
effectively manage any future funding for
• Reviewed the PMBOK Guide and assessed the extent to which MTC incorporated best
infrastructure projects.
practices related to risk management.
• Interviewed MTC staff concerning plans for risk management in Regional Measure 3.
6 Determine how long it will take to pay off the • Reviewed information on the Toll Authority’s debt in MTC’s audited
debt obligations for the seismic program and financial statements.
what will be the total cost of the program.
• Interviewed Toll Authority staff regarding seismic program financing and confirmed
that the Toll Authority does not track debt service costs specifically for the
seismic program.
• Reviewed Toll Authority revenue projections and interviewed financial staff to assess
the Toll Authority’s ability to meet its debt obligations.
7 Review and assess any other issues that are To determine ongoing costs associated with maintenance and rehabilitation on the
significant to the audit. seismic program bridges after the program is complete, we performed the following:
• Worked with MTC and Caltrans staff to calculate routine and long-term maintenance
costs on seismic program bridges.
• Interviewed staff at MTC and Caltrans and reviewed documentation to assess the
adequacy and sufficiency of maintenance funding.
• Obtained and reviewed risk management documents from Caltrans concerning
maintenance risks and risk methodology.
• Reviewed Caltrans maintenance manuals.
Source: Analysis of the Audit Committee’s audit request number 2018-104 and information and documentation identified in the table column titled Method.
Assessment of Data Reliability
In performing this audit, we obtained information from Caltrans’
and the Toll Authority’s accounting systems to ensure the figures
presented in the Oversight Committee’s quarterly reports were
reliable for the purposes of our audit. The U.S. Government
Accountability Office, whose standards we are statutorily required
to follow, requires us to assess the sufficiency and appropriateness
of computer-processed information that we use to support findings,
conclusions, and recommendations. The Oversight Committee
constructs the quarterly report of costs related to the seismic
program using a report on expenditures from Caltrans’ accounting
system. We performed data-set verification and electronic testing
of key data elements in the expenditure reports from 2006
through 2017 and did not identify any issues. To ensure the reports
were complete, we compared the reports to the amounts recorded
in the Toll Authority’s system and found them to be materially
identical. To assess the accuracy of the data in the reports, we
reviewed quarterly audits of Caltrans’ billing statements to the
Toll Authority, reviewed records and interviewed Toll Authority
and Caltrans’ staff and determined the organizations addressed
14 California State Auditor Report 2018-104
August 2018
issues the audits discovered. We determined that Caltrans reports
on expenditures are sufficiently reliable for the purposes of this
audit. Thus, we have adequate assurance that the Oversight
Committee’s quarterly reports reasonably represent the costs
of the seismic program.
California State Auditor Report 2018-104 15
August 2018
Audit Results
Lessons Learned From the Seismic Program Could Improve
the State’s Oversight of Future Projects
The Legislature’s decision to shift oversight of the seismic program
from Caltrans to the Oversight Committee had positive results.
The Oversight Committee provided examples of $866 million
in cost avoidance and savings due to its oversight and the use of
risk management to inform decisions. Further, the use of risk
management resulted in avoiding seven years of potential delays.
The seismic program is one of the largest transportation projects
in California, and the experience of the Oversight Committee
shows that similar oversight of the hundreds of billions of dollars
in transportation projects that state and local agencies are either
engaged in or anticipating can produce significant benefits.
When the Legislature formed the Oversight Committee in
2005, it also required Caltrans to develop a comprehensive risk
management plan for the seismic program. Since then, Caltrans has
adopted a policy to make risk management a part of all of its major
construction and maintenance projects. Conversely, although MTC
has taken a more active role in managing regional transportation
projects, it has not yet created a policy to ensure that future projects
it directs will benefit from appropriate levels of risk management.
While MTC has stated it will create such a policy, there is little to
ensure the application of risk management statewide because state
legislation does not impose a general requirement on all sponsors of
state or locally funded major transportation infrastructure projects
to develop risk management plans.
The Oversight Committee’s Actions Curtailed the Soaring Costs of the
Seismic Program
The Oversight Committee’s involvement curbed cost overruns
on the seismic program. As we discuss in the Introduction, the
Legislature created the Oversight Committee so that it would
provide oversight and management to the seismic program.
Before the establishment of the Oversight Committee, the seismic
program experienced significant cost escalations. However,
after the Legislature established the Oversight Committee, the
budget for the program remained relatively constant—in fact,
the Oversight Committee forecasts that the seismic program
will complete its work roughly on budget.
Members of the Oversight Committee provided examples of
savings of at least $505 million resulting from its actions and
decisions. State law requires it to resolve project issues, perform
16 California State Auditor Report 2018-104
August 2018
risk assessments and monitor staffing levels among other duties.
According to members of the Oversight Committee, it achieved
these savings in part by combining project responsibility with
approval authority and by incorporating the multiple viewpoints
the committee’s members represent. Table 2 provides examples
of cost avoidance and savings achieved through Oversight
Committee action.
Table 2
Examples of Savings and Avoided Costs Achieved by the Oversight Committee
ESTIMATED SAVINGS
AREA DESCRIPTION
AND AVOIDED COSTS
Demolishing the The Oversight Committee directed the $94 million
old east span of creation of an alternative demolition
the Bay Bridge* strategy, which relied on marine implosions.
Encouraging • Only one bidder responded to Caltrans’ $49 million
multiple bids on the original solicitation for construction of
suspension span of the suspension span.
the Bay Bridge • The Oversight Committee offered a
$3 million stipend to up to the three lowest
bidders to encourage multiple bidders.
• Increased competition resulted in a bid
below Caltrans’ estimated cost.
Retrofitting the • The Oversight Committee voted to remove $353 million
Antioch and $353 million saved in the two projects from
Dumbarton bridges the seismic program’s budget.
• The Toll Authority made these savings
available to other regional projects.
Reducing The Oversight Committee reduced a $9 million
staffing levels proposed Caltrans fiscal year 2016–17
staff support budget from $32 million to
$23 million after in-depth inquiry into
project staffing levels.
TOTAL $505 million
Source: MTC, California Transportation Commission, and Oversight Committee records.
* Potential costs avoided related to the demolition of the old east span are also referenced in Table 3
on page 19.
In one example, the Oversight Committee took action to encourage
multiple bidders on the suspension span, resulting in savings of
nearly $50 million. The original solicitation for construction of the
suspension span in 2004 resulted in a response from one bidder,
and the bid was $666 million higher than Caltrans’ initial
engineers’ estimate. As the State Auditor’s Office reported in 2004,
Caltrans chose not to disclose program information according to
the regular reporting schedule established by law; as a consequence,
California State Auditor Report 2018-104 17
August 2018
Caltrans had placed the Legislature in the awkward position of
having to try to devise a funding solution six weeks before the bid
on the suspension span was set to expire. When the Legislature did
not approve funding by September 2004, the bid expired.
According to an Oversight Committee report, when Caltrans rebid
the work on the suspension span in 2005, the Oversight Committee
used its authority to approve bid stipends of $3 million to each of
the three lowest responsive bidders. The stipends acted as partial
compensation for expenses the contractors incurred in preparing
the complex bids for the suspension span and were designed to
prevent having only one contractor bid, as had occurred in 2004.
According to the Oversight Committee, the increased competition
resulted in two bids, one of which was $49 million below the
engineers’ revised 2006 estimate. This decrease from the expected
cost was especially noteworthy because in 2005 a Caltrans market
analysis noted that Caltrans had been experiencing fewer bidders
and increasing bid prices for its awarded contracts.
Although the Oversight Committee was successful in managing the
seismic program, committee representatives we spoke to suggested Committee representatives we
improvements for future oversight committees. For example, spoke to suggested improvements
the Legislature amended state law to require that the Oversight for future oversight committees.
Committee be subject to open meeting laws beginning in 2016. The
committee had already opted to institute a modified version of open
meetings before the legislative requirement. Although the legislative
change resulted in increased transparency for the public according
to the executive director of MTC, it also increased the difficulty
of conducting day-to-day business. In a three-person committee,
two members constitutes a majority; thus, when any two members
of the committee discuss, hear, or deliberate on any issue
pertaining to the Oversight Committee, it would constitute a
meeting of the Oversight Committee. This could lead to committee
members inadvertently holding a “meeting” when conducting other
business. For example, Caltrans and the California Transportation
Commission work closely together and it is reasonable to assume
that their directors would need to meet from time to time. The
executive director of the California Transportation Commission
indicated that the Oversight Committee may benefit from
having its own attorney to ensure that legal issues that affect the
committee as a whole—such as compliance with open meeting
laws—are addressed. She stated that counsel from the members’
respective agencies currently represents members of the Oversight
Committee; however, there is no attorney assigned to represent the
Oversight Committee as a whole.
Although increasing the number of Oversight Committee members
and assigning dedicated counsel would likely increase costs, the
Oversight Committee’s current quarterly report notes the cost
18 California State Auditor Report 2018-104
August 2018
of Oversight Committee operations from 2005 to 2018 as being
about $17 million, or slightly more than $1 million per year. This is
a small fraction of the $9 billion cost of the seismic program and
significantly less than the cost savings the Oversight Committee
achieved. The cost of the Oversight Committee derives mostly from
the labor costs of support staff and consultants at each respective
Oversight Committee agency.
Caltrans’ Risk Management Plan Played a Critical Role in the Oversight
Committee’s Ability to Prevent Unnecessary Costs and Delays
Caltrans risk management handbook, published in 2003, notes that
risk management is most effective when it is performed early and
continues throughout the project. However, in 2004 our office
found that Caltrans failed to embody these principles early in the
seismic program. The Project Management Institute’s Guide to
the Project Management Body of Knowledge, 6th Edition (PMBOK
Guide) recommends that organizations make a conscious decision
to manage risk in a controlled and intentional manner in order to
prevent deviations from a project plan that could cause a project
to fail to achieve its objectives.4 In 2004, as the seismic program
was experiencing significant cost overruns, we recommended that
Caltrans implement a comprehensive risk management plan for the
seismic program using its risk management handbook. In 2005, as
part of the same legislation that created the Oversight Committee,
the Legislature required Caltrans to develop and conduct
comprehensive risk management for the seismic
program, including identifying project risks and
quantifying such risks in financial terms.
The Definition of Qualitative and Quantitative
Risk Analysis According to the PMBOK Guide
Following this legislation, risk management
Qualitative: The process of prioritizing individual played a critical role in informing the decisions
project risks for further analysis or action by assessing of the Oversight Committee. Qualitative and
their probability of occurrence and impact as well as quantitative risk analysis informed Oversight
other characteristics. Committee decisions that led to avoiding
hundreds of millions of dollars in potential costs,
Quantitative: The process of numerically analyzing the
combined effect of identified individual project risks and and seven years of potential delays, as shown in
other sources of uncertainty on overall project objectives. Table 3. The text box describes qualitative and
quantitative risk analysis. In one case, the risk
Source: PMBOK Guide.
management team performed an analysis in 2008
that identified up to $305 million in potential costs
for schedule delays and fabrication issues related
to the suspension span. As a result, the Oversight Committee
approved a $13.9 million mitigation procedure to improve quality
4 Recognized for its development of standards for project management, the Project
Management Institute publishes the PMBOK Guide, which provides guidelines for managing
individual projects.
California State Auditor Report 2018-104 19
August 2018
control with Caltrans’ fabrication contractors, which Caltrans
projected would enable the project to avoid between $132 million
and $291 million in costs. In another instance, according to the
Oversight Committee in 2005, its risk management team conducted
an analysis of two contracts to weigh the cost of accelerating one
to avoid delay to the other. The team’s analysis accurately predicted
that the first contract would finish in time for work to begin on
the other without needing to accelerate the first contract; Caltrans
estimated that this decision avoided $12 million in potentially
wasted costs.
Table 3
Examples of Costs Avoided Through Risk Management in the Seismic Program
POTENTIAL POTENTIAL
EXAMPLE OF RISK
DESCRIPTION COSTS AVOIDED DELAY
MITIGATION
(IN MILLIONS) AVOIDED
Demolishing the Risk analysis demonstrated the high costs associated with traditional demolition of $94 4 years
old east span* certain east span components, leading to the Oversight Committee’s decision.
Avoiding • In 2009 the Oversight Committee estimated the seismic retrofit of the Antioch and $200
underwater Dumbarton bridges would cost $950 million.
construction • The risk management team determined underwater construction would be
precarious, prompting the team to devote resources towards developing an
alternative strategy.
• As a result, the potential costs significantly decreased.
Suspension span • The risk management team identified several risks related to the fabrication of $132 to $291 2 years
fabrication suspension span components.
• The Oversight Committee used this information to approve a process that would
ensure quality and timely fabrication in China.
Contract • The risk management team performed a risk analysis of two contracts to determine $12
acceleration whether funds should be expended to accelerate completion on a contract to
analysis support work in another area.
• The analysis revealed less than a 5 percent chance such acceleration would
be necessary.
• The Oversight Committee elected not to accelerate the contract.
Nesting • In 2011 the risk management team identified bird nesting as a large delay risk to $17 1 year
birds permit† the old east span’s demolition.
• This led the project team to obtain special permits, which allowed for the safe
relocation of birds.
• As a result, the contract did not experience any delays due to nesting birds.
TOTALS $455 to $614 7 years
Source: Auditor-generated using Caltrans and MTC project documentation and unaudited savings estimates.
* Potential costs avoided related to the demolition of the old east span are also referenced in Table 2 on page 16.
† Multiple species of protected birds’ nests were relocated as a result of this effort, indicating that the project would have suffered without this
mitigation strategy.
20 California State Auditor Report 2018-104
August 2018
Risk management on the seismic program has also resulted
in reduced environmental and societal impacts. For example,
Caltrans noted that in 2011 its risk management team identified
nesting birds as one of the largest delay risks to the demolition
of the old east span. According to Caltrans, if certain protected
birds lay eggs on site, work needs to stop until any chicks hatching
from the eggs leave their nests. Caltrans states that federal law
prohibits the removal of certain migratory birds—one species, the
double-crested cormorant is pictured in Figure 5—or their nests
without a permit. Based on Caltrans’ data, each day of delay in the
demolition project could cost more than $44,000, and a nest could
cause a delay of up to 12 weeks. Thus, a single nest could potentially
have resulted in costs of more than $2.5 million. These financial
and ecological concerns drove Caltrans to develop a strategy for
responsibly managing the bird population, which included securing
Fish and Wildlife permits, collaborating with International Bird
Rescue, and providing alternative nests on the new span before the
beginning of nesting season in 2014.
Figure 5
Cormorants Relocated From the Prior East Span During Construction
Source: Johnson Marigot Consulting.
California State Auditor Report 2018-104 21
August 2018
Risk management on the seismic program has also reduced the
impact of the project on the public. Caltrans stated that its risk
management analysis led it to plan for a four-day bridge closure
over Labor Day weekend in 2009, instead of relying on the
contractor’s estimate of three days. To provide transportation
agencies enough time to arrange alternatives, Caltrans needed
to announce the bridge closure months in advance. The decision
proved correct, as the contractor completed work just under the
scheduled four-day allotment. Considering that almost 125,000 cars
crossed the Bay Bridge daily in 2009, an unscheduled closure would
have led to traffic delays and frustration for thousands of drivers
during a long holiday weekend.
State Law Should Require Oversight Committees and Risk Management
Plans for All Major Transportation Infrastructure Projects
The Oversight Committee, combined with Caltrans’ risk
management, contributed to significant cost savings for the
seismic program. The Bay Bridge and the Transbay Terminal faced
significant cost increases of $3 billion and $1.1 billion, respectively,
before instituting increased oversight.5 In order to respond to its
increasing costs, the Transbay Terminal project implemented a
cost review committee to provide additional financial oversight and
enlisted the help of the San Francisco Department of Public Works
to provide construction oversight beginning in 2016.
State statutes do not impose a general requirement for all major
transportation infrastructure projects to institute similar
measures. The importance of a general requirement is particularly
evident given that regional plans in the Bay Area, San Diego,
and Los Angeles—three of the largest metropolitan regions in Without assurance that large-scale
California—forecast transportation infrastructure projects totaling projects have sufficient oversight,
more than $600 billion over the coming decades. Although not California and its communities
all cost increases are avoidable, without assurance that large-scale are at greater risk that these
projects have sufficient oversight, California and its communities projects will have unplanned cost
are at greater risk that these projects will have unplanned cost increases—costs ultimately borne
increases—costs ultimately borne by taxpayers. by taxpayers.
While Caltrans may use executive steering committees to provide
advice and direction on some projects, it does not always do so.
According to the chief deputy director of Caltrans’ District 4,
Caltrans and its partners may choose to use a steering committee
on a case-by-case basis for large projects as it deems necessary.
The current replacement of the Gerald Desmond Bridge in
5 The Transbay Joint Powers Authority originally estimated the Transbay Terminal to cost $1.2 billion
in 2007, but its budget grew to $2.3 billion in 2016. Located in downtown San Francisco, this
terminal will serve as the primary bus and rail terminal for the Bay Area.
22 California State Auditor Report 2018-104
August 2018
Long Beach, for example, has a multiagency steering committee
that, according to its charter, provides direction and facilitates
actions across partnering agencies. Caltrans has acknowledged
the need for additional project oversight: when Caltrans reported
to the Legislature in 2014 on lessons learned throughout the
seismic program, among its recommendations was the use of
multiagency oversight structures on large transportation projects.
An investigation completed in July 2014, on behalf of the Senate
Transportation Committee, reached a similar conclusion.
Following its use of risk management in the seismic program,
Caltrans developed a scalable risk management policy based on
the project’s size, from $1 million to over $100 million, that applies
increasing levels of risk management. In 2012 Caltrans issued a
directive requiring staff to apply risk management practices to all
capital and major maintenance projects. The directive outlines
a scalable policy with increasing levels of risk management
depending on the size of the project. Without establishing a
general requirement for all major state and local transportation
infrastructure projects to develop and conduct comprehensive risk
management from the outset of a project, the application of risk
management relies on either Caltrans involvement in projects or
federal oversight.
Not all projects involve Caltrans However, not all projects involve Caltrans and even when federal
and even when federal oversight oversight is required there is no assurance that it will be sufficient
is required there is no assurance to prevent cost overruns. For example, because Caltrans estimated
that it will be sufficient to prevent that the Bay Bridge project would cost more than $1 billion, it was
cost overruns. subject to enhanced federal oversight.6 This oversight included the
assignment of a full-time Federal Highway Administration project
manager. However, the oversight proved insufficient to prevent cost
increases prior to the establishment of the Oversight Committee.
In its 2014 report to the Legislature on lessons learned in the
seismic program, Caltrans noted that the project did not get the full
benefits from risk management that would have accrued had it been
implemented earlier than 2005. A statutory requirement applicable
to all major publicly funded transportation infrastructure projects
would ensure that projects sponsored by Caltrans, and other state
and local entities, would benefit from similar requirements from
the onset.
6 Previously, projects over $1 billion were required to submit annual financial plans. However,
in 2005 Congress revised this to define a major project as a project with an estimated cost of
$500 million or more and required such projects to submit project management and annual
financial plans.
California State Auditor Report 2018-104 23
August 2018
MTC Should Develop a Policy to Ensure That Future Projects Will Also
Benefit From Risk Management
MTC lacks a formal policy to ensure that future projects it
directs will benefit from appropriate levels of risk management,
although it is using risk management on the projects it is currently
managing. Under state law, MTC’s primary role is that of a regional
transportation planning agency but in recent years it has taken
a more active role by directly managing some projects. MTC
currently manages several projects including the Bay Area Express
Lanes Program, for which MTC is responsible for implementing
270 miles of express lanes throughout the region that will use
MTC’s FasTrak toll collection system. To support this effort, MTC
has developed a program-specific risk management plan that clearly
identifies roles, responsibilities, and expectations. For instance,
the program risk manager’s responsibilities on MTC’s express lanes
program include reporting to the program manager, ensuring that
project managers maintain project risk registers, and preparing
quarterly risk management reports.
However, according to MTC’s deputy director, MTC does not
have a formal policy ensuring that it will develop similar plans
for future projects it directs. Instead, it has historically made risk
management decisions for the projects it directs on a case-by-case
basis. He also stated that risk management costs could sometimes
exceed what MTC believes to be fiscally prudent for a project.
However, it is possible to develop a scalable risk management
policy, as Caltrans has done, to accommodate projects of varied
complexity and cost. For example, Caltrans’ policy encourages risk
documentation on extremely small projects of under $1 million but
requires increasingly in-depth risk management as costs increase
up to and above $100 million. Without a formal policy, MTC
may apply risk management inconsistently—or neglect to apply
it altogether—on future projects, which could increase costs and
Ensuring judicious and measured
ultimately the financial burden on toll payers. As Caltrans has
risk management on all projects
discovered, ensuring judicious and measured risk management on
requires a policy that allows
all projects requires a policy that allows flexibility but ensures the
flexibility but ensures the universal
universal application of best practices. According to its executive
application of best practices.
director, MTC intends to develop a policy for projects it directs,
which will improve efficacy and ensure the systematic application
of risk management.
MTC’s risk management policy should include the asset
management plan the Toll Authority is currently creating.7 State law
requires the Toll Authority to fund maintenance and rehabilitation
7 As noted in the Introduction, MTC and the Toll Authority are legally separate entities that share
the same board, staff, and facilities.
24 California State Auditor Report 2018-104
August 2018
programs on the Bay Area toll bridges after the seismic projects are
completed. However, due to the long lifespan of Bay Area bridges,
MTC cannot reasonably rely on the expertise of its current staff
to ensure it applies appropriate engineering considerations to
future maintenance funding decisions. To address this issue, the
Toll Authority is assembling a panel of independent engineering
consultants to assist it in creating an asset management plan that
supplements similar Caltrans efforts. The asset management plan
will assist in MTC’s current efforts, which prioritize projects based
on a scoring system that heavily weighs life and structural safety
while considering current bridge conditions. Including the asset
management plan as a component of an overall risk management
policy will help ensure that MTC appropriately manages critical
assets throughout their projected lifespans.
The Remediation of Defective Components on the Bay Bridge
Represented a Small Portion of the Project’s Total Costs
State statutes do not define what constitutes a
defect for major transportation infrastructure
The Definition of Defect
According to the PMBOK Guide projects. Similarly, Caltrans and MTC have not
created a definition for defects generally, or on
An imperfection or deficiency in a project component the Bay Bridge in particular, and therefore have
where that component does not meet its requirements or generally not identified items as defective. For
specifications and needs to be either repaired or replaced.
the purposes of this report, we used the PMBOK
Source: PMBOK Guide. Guide definition of defect as detailed in the
text box.
As indicated in Table 4, we found that Caltrans
spent at least $66.6 million on remediating construction defects
and at least another $19.7 million resolving fabrication problems in
the contract change orders that we reviewed. Construction defect
costs are those that indicate Caltrans paid to repair or replace a
component that had already been installed on the bridge, while
fabrication problems involve repairing or replacing a component
before installation. Costs associated with Table 4 do not indicate
the existence of current defects, but rather detail the cost of work
conducted after Caltrans identified an issue and resolved it to the
satisfaction of the engineers on the project. As we discuss later,
multiple peer reviews and engineer panels have reviewed critical
elements of the Bay Bridge and noted that they were safe.
Although Caltrans has developed specifications in its contracts
which utilize technical industry standards to define certain
defects, this information is specific to each contract and would
not provide a general definition for the project as a whole. Because
contractors are generally responsible for the cost and effort to
California State Auditor Report 2018-104 25
August 2018
remediate defective work if they fail to meet contract specifications,
our review focused on instances in which Caltrans compensated
a contractor to repair or replace a component. While Caltrans
and MTC may disagree with respect to work we identified as
defect remediation, the seismic program nevertheless incurred
expenses while repairing or replacing bridge components. In total,
our review of a selection of 800 contract change orders—out of
about 2,500 total change orders for permanent work—identified
$86 million of defect remediation costs on the Bay Bridge,
or 1.5 percent of the project cost. Our review did not include
temporary structures or work that was tangential to the bridge
itself, such as electrical substations providing power to the bridge.
Table 4
Cost of Remediation in Change Orders We Reviewed
(In Thousands)
CONSTRUCTION FABRICATION
AREA OF THE BRIDGE TOTAL
DEFECT PROBLEM
Suspension span $56,550 $17,591 $74,141
Yerba Buena Island 2,315 620 2,935
Skyway 1,746 755 2,501
Oakland touchdown 6,017 726 6,743
TOTALS $66,628 $19,692 $86,320
Source: Analysis of selected east span contract change orders.
Note: Of the approximately 2,500 change orders for permanent work on the Bay Bridge, we reviewed a
selection of 800.
Caltrans has procedures to identify and address problems
experienced during construction, such as work that does not
meet specifications. Federal law requires Caltrans to develop a
quality assurance program for federal-aid highway construction
projects and according to Caltrans, its quality assurance program
generally seeks to improve production and avoid defects. When
Caltrans personnel identify an issue, they are to document it and
communicate with both the resident engineer and the contractor
on the project to resolve it. For example, in one instance, Caltrans
personnel found that a contractor working on the east span
allowed the use of a protective coating technique that was out of
compliance with the contract’s specifications. Caltrans staff worked
with the contractor to resolve the issue at the contractor’s expense.
26 California State Auditor Report 2018-104
August 2018
Resolution may sometimes result in a contract change order,
depending on the nature and severity of the issue. For example,
quality assurance personnel detected a problem and issued a
report when metal plates failed to meet quality requirements,
which prompted Caltrans to work with the contractor to develop
a solution that could be implemented without additional cost.
However, there were other cases in which Caltrans incurred
significant expenses remediating defects. For example,
resolving problems surrounding well-publicized broken bolts—
originally intended to anchor a segment of the bridge—required
developing and implementing an alternative anchoring method.
Caltrans’ procedures allow it to identify a variety of issues and
remediate defects when necessary, but not all defects can be
proactively prevented.
Caltrans incurred increased costs remediating fabrication problems
and construction defects depending on the complexity of the issue
identified. For instance, Caltrans paid more than $400,000 to
make modifications to a fabrication process for certain beams after
Caltrans spent more than
the original process caused the steel to behave in unanticipated
$22 million remediating problems
ways. Further, in correspondence with the requestor of this audit,
surrounding broken bolts
the executive director of the Toll Authority and MTC stated that
and developing an alternate
the well-publicized broken bolts, part of the anchoring system
anchoring method.
on the eastern side of the suspension span, were unquestionably
a construction defect. Experts noted that a confluence of
environmental factors and metallurgical conditions caused the
bolts to fail, despite meeting industry standards. Caltrans spent
more than $22 million remediating problems surrounding the
broken bolts and developing an alternate anchoring method.
Another significant expenditure, $13.9 million, provided for the
development of a quality control process improvement after
Caltrans personnel identified welding defects during fabrication of
support structures. Caltrans also spent more than $12 million to
make repairs, modifications, and adjustments to resolve fit issues
between various complicated components.8 Examples similar
to these account for the vast majority of remediation costs we
identified and were paid for using contingency funds.
In spite of increased costs associated with remediating defects,
according to multiple peer review panels from as recently as 2014,
remediated defects such as those identified in our review do not
indicate the presence of safety issues on the bridge. Caltrans designates
the Bay Bridge as a lifeline structure, which requires that the bridge
be able to provide a high level of post-earthquake transportation
service for emergency response and support for the economic
8 Fit issues occurred when a component required modification to fit properly with
another component.
California State Auditor Report 2018-104 27
August 2018
livelihood of the Bay Area. According to Caltrans, the east span is
designed to withstand a once-in-1,500-years seismic event. To ensure
that problems have been resolved effectively, and that the Bay Bridge
is ready to function in a seismic event, the project has undergone
multiple peer reviews, in which internal and external engineering
experts have conducted in-depth evaluations and determined that
critical components are safe. For example, the Toll Bridge Seismic
Safety Peer Review Panel stated that the tower foundation, part of
the suspension span, was designed and constructed in a manner that
meets or exceeds structural safety standards.
The Seismic Program Will Cost About $9 Billion, but Debt Service and
Ongoing Maintenance Costs Will Continue
The seismic program will end in 2019 at a cost of about $9 billion,
roughly on budget. Although costs associated with debt on bonds
backed by toll revenues as well as ongoing maintenance and
rehabilitation costs on all of the Bay Area bridges will continue into
the future, the Toll Authority forecasts that it will have sufficient
revenues to cover those expenses.
The Seismic Program Will Have Cost About $9 Billion at Completion
The Oversight Committee estimates that the seismic program
will end by 2019 having cost just under $9 billion, not including
ongoing maintenance and rehabilitation. As of August 2018, the
Oversight Committee estimated that the final cost of the program
will be about $34 million under the program's current budget.
Nevertheless, as we discussed previously, the history of the seismic
program has been one of escalating costs. Table 5 on the following
page shows the evolution of the program’s budget by bridge, as well
as the anticipated final costs of the program.
The cost estimates of the seismic program increased substantially
from 1997 through 2005. In 1997 the Legislature allocated $2.6 billion
in funds from various sources to finance what was at that point
projected to be the entirety of the seismic program—five Bay Area
toll bridges and two toll bridges in Southern California. A 2001
Caltrans report on the seismic program cited several factors leading
to increased cost estimates including rising construction costs
and delays in selecting a design for the east span. The Legislature
responded in 2001 by allocating additional funds, bringing the
new total for the seismic program to $5.1 billion. By 2005 Caltrans’
estimates of the cost of the seismic program had grown well beyond
$5 billion to $8.7 billion. In that year, the Legislature identified an
additional $3.6 billion of funds to pay for the estimated cost overruns,
with $2.2 billion to come from toll revenues and the remainder from
28 California State Auditor Report 2018-104
August 2018
several state funding sources. The Legislature further indicated that
the Toll Authority would be responsible for covering any excess costs
associated with the east span of the Bay Bridge through toll revenues.
Table 5
Seismic Program Budgets and Costs by Bridge
(In Millions)
CURRENT PROJECTED
1997 2001 COSTS TO
BRIDGE RETROFIT OR 2005 2009 APPROVED COSTS AT
COST COST DATE (AS OF
REPLACEMENT BUDGET BUDGET BUDGET (AS OF CLOSEOUT
ESTIMATE ESTIMATE JUNE 2018)
JUNE 2018) (2019)
Bay Bridge,
$1,285.0 $2,600.0 $5,486.6 $5,486.6 $6,509.0 $6,428.3 $6,533.0
east span replacement
Bay Bridge, west span 553.0 700.0 736.9 736.9 757.9 757.7 757.9
Benicia–Martinez 101.0 190.0 177.8 177.8 177.8 177.8 177.8
Carquinez* 83.0 125.0 114.1 114.1 114.2 114.2 114.2
Richmond–San Rafael 329.0 665.0 914.0 914.0 811.9 794.8 794.9
San Mateo–Hayward 127.0 190.0 163.5 163.5 163.4 163.4 163.4
Vincent Thomas 45.0 62.0 58.5 58.5 58.5 58.4 58.5
San Diego–Coronado 95.0 105.0 103.5 103.5 103.2 103.2 103.2
Antioch 267.0 71.1 71.1 71.2
Dumbarton 483.0 112.4 111.8 112.2
Contingency† 448.0 900.0 900.0 46.7
Misc program costs 30.0 30.0 26.0 26.0 26.0
Net programmatic risk 5.6
TOTALS $2,618.0 $5,085.0 $8,684.9 $9,434.9 $8,952.1 $8,806.7 $8,917.9
Source: State law and Oversight Committee quarterly reports.
Note: The cost estimates in 1997 and 2001 are as expressed in legislation; the budgets and costs from 2005 onward are as noted in the Oversight
Committee’s quarterly reports.
* The eastbound portion of the Carquinez bridge was retrofit. The westbound replacement of the Carquinez Bridge, which opened in 2003, was part
of Regional Measure 1 (1988) and not the seismic program.
† In 2001 the Legislature appropriated $448 million in additional funds to cover potential cost overruns. Caltrans referred to this amount as a
“program contingency.” In 2005, based on earlier Caltrans estimates, the Oversight Committee established a program contingency budget of
$900 million. The contingency does not appear in the columns for 2018 and 2019, as contingency funds are incorporated into the costs of the
individual bridges when spent.
The budget for the seismic program increased again after 2009
legislation that added two bridges to the program. The seismic
program did not initially include the Antioch and Dumbarton
bridges because they met seismic standards established in the early
1970s. However, after a series of earthquakes both in California
and abroad, in 2008 the Toll Authority and Caltrans determined
California State Auditor Report 2018-104 29
August 2018
that the two bridges needed retrofitting. The Legislature added
both bridges to the seismic program and directed the Oversight
Committee to pay for the projects through cost savings or with toll
revenue from the Toll Authority, authorizing the Toll Authority to
increase tolls to complete work on the bridges. Early the following
year, the Toll Authority approved adding $750 million to the seismic
program’s budget—a figure based on cost projections for retrofitting
the Antioch and Dumbarton bridges. Because the Toll Authority
was responsible for costs exceeding prior legislative appropriations,
the $750 million would come from toll revenues. This brought the
total budget for the seismic program to $9.4 billion.
Much of the increasing cost of the program was due to rising
costs for replacing the east span. In 2005 Caltrans estimated In 2005 Caltrans estimated the
the budget for the east span at $5.5 billion, an amount roughly budget for the east span at
equal to the prior legislative appropriation for the entire seismic $5.5 billion, an amount roughly
program. As described in the bill analysis and supported by equal to the prior legislative
Caltrans estimates, this increase absorbed most of the $3.6 billion appropriation for the entire
for overruns appropriated by the Legislature in 2005. Further, seismic program.
the cost of the east span would continue to grow; the Oversight
Committee projects that the final cost of the east span will be about
$6.5 billion. The additional $1 billion was the result of increased
costs in three areas: the diversion of traffic from the old bridge to
a detour structure at Yerba Buena Island, the suspension span, and
Caltrans’ support costs. Of these projects, the Yerba Buena Island
detour accounted for over $340 million due to contract changes
that combined the detour with other foundation work related
to the Yerba Buena Island portion of the Bay Bridge. According to
Caltrans, it advanced the foundation work on the Yerba Buena
Island contract as a risk mitigation measure to get foundation work
completed on schedule. It incurred more than $260 million in
additional costs on the suspension span in an attempt to mitigate
delays, resolve complex construction issues, and keep the Bay
Bridge opening on schedule.
Caltrans’ support costs accounted for an additional $390 million
of the costs of the east span; this amount represents the cost of
support personnel involved in developing and delivering the
project, including staff such as project managers, engineers, and
others. Any delays in the project, as well as contract changes, will
increase costs in this area. The Oversight Committee projects that
support costs on the east span will amount to about 26 percent
of capital costs upon project completion. By comparison, in fiscal
year 2015–16 Caltrans reported that the ratio of support to capital
costs across all of its projects was much higher at about 38 percent.
Despite the continued growth in the cost of the east span, overall
the seismic program will end in 2019 roughly on budget, due to the
Oversight Committee and the application of risk management,
30 California State Auditor Report 2018-104
August 2018
as we discussed previously, as well as cost savings in other parts
of the program and a $900 million contingency in the program
budget. In fact, the Oversight Committee reduced the overall
program budget after achieving cost savings on other bridges. The
final cost of retrofitting the Antioch and Dumbarton bridges was
about $180 million, nearly $570 million less than projected. These
reductions were largely the result of Caltrans’ assessment that it
could reduce project scope and risk by eliminating underwater
work on the bridges. Further, Caltrans received significantly lower
bids than anticipated for the work on both bridges. As Figure 6
demonstrates, in 2010 and 2013 the Oversight Committee chose
to remove funds from the seismic program’s budget entirely,
reducing the budget from $9.4 billion to about $9 billion. State law
gives the Toll Authority latitude in the use of toll revenues, and
according to the Toll Authority’s chief financial officer (CFO), MTC
returned some of the Antioch and Dumbarton savings to the Toll
Authority’s toll account for use on other projects but generally did
not direct them to a specific use. However, in 2013, MTC redirected
$130 million of savings from the seismic program to other Bay Area
transit agencies for replacing buses and rail cars.
The inclusion of a contingency The inclusion of a contingency fund in the budget has allowed
fund in the budget has allowed the the Oversight Committee to manage cost increases to the east
Oversight Committee to manage span without going over budget. In 2001 Caltrans included
cost increases to the east span a $448 million contingency in the program budget. By 2004
without going over budget. Caltrans had increased the estimated contingency to $900 million.
According to a 2004 report on the seismic program from the Toll
Authority, Caltrans arrived at the $900 million amount through
a quantitative analysis that established a contingency range of
between $500 million and $900 million. That amount was part
of the estimate Caltrans provided to the Legislature in 2005
showing an increase of nearly $3.6 billion in the seismic program.
According to Caltrans’ breakdown of contingency expenditures, the
bulk of the $900 million contingency has gone to the east span.
Our review of the Oversight Committee’s most recent budget and
cost projections indicates that the Oversight Committee anticipates
$112 million in remaining work before project closeout. The vast
majority of the remaining expenditures relate to work on the east
span. For instance, the largest item, $76 million, is to dismantle
the old east span and to retain and improve piers to allow for
public access, collectively the final major phase of project closeout.
Further, Caltrans’ most recent risk management estimate show
a reduced draw on the program’s contingency fund, which will
result in a surplus of roughly $34 million at project closeout. Due
to the resolution of several issues, including a recent settlement
with the firm that built the suspension span, costs have come
down slightly and Caltrans staff predict the seismic program
will finish slightly under budget.
California State Auditor Report 2018-104 31
August 2018
Figure 6
Effect of Oversight Committee Actions on Seismic Program Budget and Costs
(Billions of Dollars)
$483
Oversight Committee Oversight Committee reduced total budget by:
is formed
$9.44*
$8.69 $8.95 $8.81 $8.92
$5.09
$2.62
7 1 5 9 0 3 8 9
9 0 0 0 1 1 1 1
9 0 0 0 0 0 0 0
1 2 2 2 2 2 2 2
SNPEO
NAPS
TSAE
ETAD
OT
TSOC
NOITELPMOC
TA
TSOC
DETCEJORP
Million
Removed $353 million in savings
from the program’s budget
The Legislature allocated Removed $130 million in savings from the program’s
funds to cover increasing costs budget to fund other regional transit needs
Source: State law and Oversight Committee quarterly reports.
Note: The 1997–2013 amounts represent budgeted amounts. In 2013 the Bay Bridge opened to traffic.
* The Antioch and Dumbarton bridges were added to the seismic program.
Based on contemporaneous Caltrans and MTC documents,
cost overruns on the east span of the Bay Bridge did not cause
significant delays on other bridges in the seismic program. Before
the creation of the Oversight Committee, state law required
Caltrans to issue annual reports on funds spent on the seismic
program. These reports include information on anticipated
32 California State Auditor Report 2018-104
August 2018
completion dates for each of the bridges. After examining those
reports and comparing them to project completion dates, we
determined that of the six bridges in the initial seismic program
other than the Bay Bridge, Caltrans completed two on time, and it
completed another—the Richmond–San Rafael Bridge—on time
Caltrans finished the retrofit of after revising its initial estimate. Caltrans finished the retrofit of
two bridges within a year of its two bridges within a year of its initial estimates, and it finished
initial estimates, and it finished one within two years. According to Caltrans, the delays on the
one within two years. Richmond–San Rafael Bridge were the result of complications
related to underwater foundation work and environmental
restrictions. Further, Caltrans completed work on the main portion
of the west span of the Bay Bridge earlier than its initial estimate,
although it completed the approach to the west span on time after
revising the initial estimate by one year. In fact, Caltrans had
completed work on most of the bridges, aside from the east span, by
2005, when the Oversight Committee began managing the seismic
program. MTC’s executive director stated that MTC's increased
responsibility after 2005 did not negatively affect other projects
that were in progress. Caltrans finished retrofitting the Antioch
and Dumbarton bridges, added to the seismic program in 2009,
on time and well under budget.
The Toll Authority Forecasts Sufficient Toll Revenues to Meet
Maintenance Expenditures Over the Next Decade
In addition to funding toll bridge retrofitting and eventual
replacement, the Toll Authority funds bridge maintenance. Bridges
are complex structures that require both routine and long-term
maintenance throughout their lifespans. State law specifies
that Caltrans is responsible for maintaining the Bay Area toll
bridges, and once seismic work is complete on each bridge, the
Toll Authority will be responsible for funding that maintenance.
According to Caltrans’ records, the cost of routine maintenance—
which includes activities such as graffiti cleanup, deck repair, and
inspections—on the Bay Area toll bridges ranged from about
$8 million to $13 million annually from fiscal years 2012–13 through
fiscal year 2016–17. Costs associated with rehabilitation—which
includes all nonroutine activities such as replacement of damaged
or worn components, improved toll collection systems, and
studies—totaled about $110 million in fiscal year 2016–17. The Toll
Authority already pays for maintenance and rehabilitation costs
for most of the Bay Area toll bridges, and when Caltrans completes
work on the Bay Bridge, it will begin billing the Toll Authority for
maintenance and rehabilitation costs on that bridge as well.
The Toll Authority forecasts that it will collect sufficient revenue
to meet the bridges’ maintenance and rehabilitation needs over
the next 10 fiscal years, projecting that toll revenues will increase
California State Auditor Report 2018-104 33
August 2018
from $724 million in fiscal year 2016–17 to $889 million in fiscal
year 2026–27. This revenue would also be sufficient to cover
the Toll Authority’s expenses, including payments on bonds.
After reviewing the revenue forecasts for the previous 10 fiscal
years, we determined that actual revenues have consistently
exceeded revenue forecasts by small amounts, suggesting that
future forecasts are reasonable. Before the passage of Regional
Measure 3 in June 2018, the Toll Authority had projected the
need for a $1 toll increase in fiscal year 2026–27. According to
the Toll Authority’s CFO, this was to prepare for the replacement
of the region’s oldest toll bridges, several of which are over
50 years old. However, because Regional Measure 3 authorizes a
series of toll increases and transportation projects beginning in
2019, the Toll Authority’s most recent projections are outdated.
The increased revenue from Regional Measure 3 may make the
$1 increase in fiscal year 2026–27 unnecessary. According to
the Toll Authority’s CFO, the Toll Authority will update its revenue
projections in the next fiscal year. In fact, it will need to do so when
it prepares to issue bonds to fund future projects.
Finally, the Toll Authority maintains a reserve for maintenance
and rehabilitation costs to help ensure that it is able to meet
future needs. The Toll Authority retains consultants to help
it predict future maintenance and rehabilitation needs. Based
on the consultants’ work, the Toll Authority created a reserve
for maintenance and rehabilitation. That reserve is currently
$120 million and is based on costs of $60 million per year. Although
this is below the maintenance and rehabilitation costs for fiscal
year 2016–17, these costs fluctuate from year to year. According to
the Toll Authority’s CFO, the authority builds the rehabilitation
budget on a “life-to-date” basis—that is, it is less concerned about a
single fiscal year’s expenditures, and focuses instead on whether the
expenditures do not exceed the authorized budget over the life of
the project. Nevertheless, according to its CFO, the Toll Authority
is planning to reevaluate all of its reserves sometime next year
in order to take into consideration changes due to the passage of
Regional Measure 3 in June 2018. Further, an updated consultant’s
assessment estimated that annual maintenance and rehabilitation
costs would increase to an average of slightly more than $90 million
a year beginning in 2017, although this has not yet resulted in an
update to the reserve.
The Toll Authority’s Payments on the Debt It Incurred as a Result of the
Seismic Program Will Continue for Decades
Although state law allocated state funds for the seismic program,
the total funding was a mix of state, federal, and, overwhelmingly,
bond money backed by toll revenues. In fact, of the anticipated
34 California State Auditor Report 2018-104
August 2018
$9 billion final cost of the seismic program, more than $6 billion
will have come from toll revenues paid by drivers. The appendix
on page 37 provides a breakdown of revenue sources for the
seismic program.
The Toll Authority’s debt service on bonds related to the seismic
program will continue for decades. Based on the Toll Authority’s
power in state law to issue revenue bonds and use the proceeds for
financing projects, it has generally issued bonds for both seismic
and non-seismic projects. According to the Toll Authority’s CFO,
due to this pooling of bond funds it cannot separately identify
interest payments for the seismic program. However, according
to MTC’s most recent financial statements, it will pay $9.3 billion
from fiscal years 2017–18 through 2055–56 in interest on various
MTC projects. When outstanding principal is included, the Toll
Authority’s remaining debt service payments through fiscal
year 2055–56 will total $18.7 billion.
The Toll Authority’s practice of pooling bond proceeds from both
seismic and non-seismic projects is within its authority and benefits
the region. Not only does state law give the Toll Authority broad
powers to issue bonds and use bond proceeds, its CFO stated
that doing so creates several advantages such as reducing risk for
investors and creating additional funding to cover debt. He also said
that pooling has led to more favorable financing terms that allow
the Toll Authority to maximize the amount of funding it receives
for the bonds it issues.
Recommendations
Legislature
To ensure that large transportation infrastructure projects
throughout the State benefit from appropriate oversight, the
Legislature should require that all publicly funded major
transportation infrastructure construction projects estimated to
cost $500 million or more, have oversight committees subject
to open meeting laws. When practical, each oversight committee
should include individuals from at least three major agencies
involved in the project, with roles that reflect financial interests
as well as project execution and oversight. Further, when possible,
each committee should include at least five members to support
its ability to conduct day-to-day business without violating open
meeting law requirements. The oversight committees should act
as the authorities for critical decisions and have sufficient staff to
support their decision-making roles.
California State Auditor Report 2018-104 35
August 2018
To ensure that oversight committees perform their duties in a
manner commensurate with the demands of large transportation
infrastructure projects, the Legislature should require that the
oversight committees have duties similar to those of the Oversight
Committee, including the following:
• Providing project direction.
• Reviewing project status, costs, schedules, and staffing levels.
• Resolving project issues and evaluating project changes.
• Developing and regularly updating cost estimates, risk
assessments, and cash-flow requirements.
To ensure that oversight committees effectively address both the
fiscal and project management elements of large transportation
infrastructure projects, the Legislature should require consolidated
reporting at least annually detailing cost savings, cost overruns, and
updates on project completion.
To ensure that oversight committees and the agencies involved in
large transportation infrastructure projects engage in sufficient and
appropriate risk management, the Legislature should require all
publicly funded transportation infrastructure projects with a total
estimated cost of $500 million or more to develop risk management
plans that use both qualitative and quantitative risk analyses
throughout the course of the projects.
MTC
To ensure that future projects have adequate risk management,
MTC should formalize a scalable risk management policy by
June 2019 so that the projects it directs benefit from sufficient and
ongoing risk management.
36 California State Auditor Report 2018-104
August 2018
We conducted this audit under the authority vested in the California State Auditor by Government
Code 8543 et seq. and according to generally accepted government auditing standards. Those
standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to
provide a reasonable basis for our findings and conclusions based on our audit objectives specified in
the Scope and Methodology section of the report. We believe that the evidence obtained provides a
reasonable basis for our findings and conclusions based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
Date: August 28, 2018
Staff: John Lewis, MPA, Audit Principal
Nicholas B. Phelps, JD
Christina L. Downard
Joseph S. Sheffo, MPA
Ashley Snyder
Legal Counsel: Heather Kendrick, Sr. Staff Counsel
For questions regarding the contents of this report, please contact
Margarita Fernández, Chief of Public Affairs, at 916.445.0255.
California State Auditor Report 2018-104 37
August 2018
Appendix
FUNDING SOURCES FOR THE SEISMIC PROGRAM
Upon California voters passing the Seismic Retrofit Bond Act of 1996, the Legislature began appropriating
funds for the seismic program from a variety of sources. In 2005 the Legislature required that toll
revenues—which account for about two-thirds of total revenues in the seismic program—cover any
excess costs associated with the east span of the Bay Bridge. The table lists the sources of these funds.
Table
Seismic Program Funding Sources
SOURCE AMOUNTS APPROPRIATED
Toll Authority Financing LEGISLATION (IN MILLIONS)
Bay Area Seismic Surcharge Assembly Bill 1171 (2001) $2,282
Assembly Bill 144 (2005) 2,150
Assembly Bill 1175 (2009)* 750
Toll revenue consolidation: Assembly Bill 144 (2005) 820
Funds made available as a result of legislative action consolidating toll
revenues under the Toll Authority’s management and the refinancing
of the Toll Authority’s bonds
TOLL AUTHORITY SUBTOTAL $6,002
State Financing
Seismic Retrofit Bond Act Proposition 192 (1996) $790
Senate Bill 60 (1997)
State Contributions
State Highway Account Senate Bill 60 (1997) $745
Transit Capital Improvement Program funded by the Transportation Senate Bill 60 (1997) 130
Planning and Development Account in the State Transportation Fund
Vincent Thomas Toll Bridge Revenue Account Senate Bill 60 (1997) 15
San Diego–Coronado Toll Bridge Revenue Fund Senate Bill 60 (1997) 33
Interregional Transportation Improvement Plan/ Assembly Bill 1171 (2001) 448
State Highway Operation Protection Plan
State Highway Account (for the demolition of the east span) Assembly Bill 144 (2005) 300
State Highway Account Assembly Bill 144 (2005) 130
Motor Vehicle Account Assembly Bill 144 (2005) 75
Public Transportation Account Assembly Bill 144 (2005) 125
STATE SUBTOTAL $2,791
Federal Contributions
Federal Highway Bridge Replacement and Rehabilitation Program Assembly Bill 1171 (2001) $642
FEDERAL SUBTOTAL $642
TOTAL $9,435
Source: State law and Oversight Committee reports.
* Assembly Bill 1175 appropriated funding for the retrofit of the Antioch and Dumbarton bridges from savings in other parts of the seismic program
and authorized the Toll Authority to raise tolls to pay for the retrofit's completion. The Oversight Committee appropriated $750 million from toll
revenues, and the Toll Authority increased tolls by $1 in 2010.
38 California State Auditor Report 2018-104
August 2018
Blank page inserted for reproduction purposes only.
California State Auditor Report 2018-104 39
August 2018
*
1
2
* California State Auditor’s comments appear on page 41.
40 California State Auditor Report 2018-104
August 2018
3 4
3 5
3 6
3 7
8
3 9
California State Auditor Report 2018-104 41
August 2018
Comments
CALIFORNIA STATE AUDITOR’S COMMENTS
ON THE RESPONSE FROM THE METROPOLITAN
TRANSPORTATION COMMISSION
To provide clarity and perspective, we are commenting on
the response to our audit report from MTC. The numbers below
correspond to the numbers we placed in the margin of the response.
1
We reviewed the 2nd quarter 2018 Progress Report for the Seismic
Program and updated our report where appropriate.
2
We appreciate MTC’s perspective related to our recommendation that
the Legislature set the threshold for oversight committees on large
transportation infrastructure projects at $500 million. However, as
we note on page 22, we set the threshold in our recommendation at
$500 million because that is the definition of a major project in federal
law. When we reviewed the draft 2019 Transportation Improvement
Plan, we determined that some of the 19 projects MTC mentions in
its response would not be affected by our recommendation because
they are not construction projects for transportation infrastructure.
Further, our recommendation on page 34 provides flexibility as
to which agencies should comprise an oversight committee. We
recommend that when practical the committee should include
representatives from at least three major agencies involved in the
project, but we do not specify which agencies.
3
While preparing our draft report for publication, some page
numbers shifted. Therefore, the page numbers MTC cites in its
response do not correspond to the page numbers in our final report.
4
We incorporated MTC’s suggested revision in Figure 3 on page 8.
5
Streets and Highways Code section 188.5 specifies the name of the
Vincent Thomas Bridge.
6
Figure 3 on page 8 and our footnote on page 23 makes this
distinction clear.
7
We clarified that Regional Measure 3 provides support for the Bay
Area Express Lanes Network on page 10.
8
We clarified that the Toll Authority is implementing the asset
management plan on page 24.
9
We corrected the typographical error MTC identified on page 34.