CSA
Recommendations
Read the report at California State Auditor ↗
California
High‑Speed Rail Authority
Its Flawed Decision Making and Poor
Contract Management Have Contributed to
Billions in Cost Overruns and Delays in the
System’s Construction
November 2018
REPORT 2018-108
CALIFORNIA STATE AUDITOR
621 Capitol Mall, Suite 1200 | Sacramento | CA | 95814
916.445.0255 | TTY 916.445.0033
For complaints of state employee misconduct,
contact us through the Whistleblower Hotline:
1.800.952.5665
Don’t want to miss any of our reports? Subscribe to our email list at auditor.ca.gov
For questions regarding the contents of this report, please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255
This report is also available online at www.auditor.ca.gov | Alternate format reports available upon request | Permission is granted to reproduce reports
Elaine M. Howle State Auditor
November 15, 2018
2018‑108
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the California State Auditor presents
this audit report regarding the California High-Speed Rail Authority’s (Authority) contracting
and cost control practices. This report concludes that the Authority’s flawed decision making
regarding the start of high-speed rail system construction in the Central Valley and its ongoing
poor contract management for a wide range of high-value contracts have contributed to billions
of dollars in cost overruns for completing the system.
The Authority began construction in the Central Valley in October 2013 despite being aware of the
risks associated with beginning construction early—the fact that the Authority had not acquired
sufficient land for building, had not determined how it would relocate utility systems, and had
not obtained agreements with external stakeholders. These unmitigated risks have contributed to
$600 million in costs overruns thus far for the three active Central Valley construction projects,
with another $1.6 billion in additional costs needed to complete the projects. The Authority has
cited the terms of a 2010 federal grant—which originally required construction to be complete
by 2017—as the primary factor in its decision to begin construction when it did. However, we
determined that even with a grant deadline extension until December 2022, the Authority could
miss the new deadline unless Central Valley construction progresses twice as fast as it has to
date. Missing the deadline could expose the State to the risk of having to pay back as much as
$3.5 billion in federal funds.
The Authority has partially offset Central Valley cost overruns, as well as those projected elsewhere
in the system, by planning to share existing rail infrastructure where possible. However, the
Authority acknowledges that it has identified every feasible option to do so and therefore cannot
continue to use this approach to offset costs. Moreover, despite its challenging financial situation,
we determined that the Authority has failed to implement sound contract management practices.
As a result, it cannot demonstrate that the large amounts it has spent on its contracts have been
necessary or appropriate.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
621 Capitol Mall, Suite 1200 | Sacramento, CA 95814 | 916.445.0255 | 916.327.0019 fax | www.auditor.ca.gov
iv California State Auditor Report 2018-108
November 2018
Selected Abbreviations Used in This Report
CMSU Contract Management Support Unit
DBE Disadvantaged Business Enterprises
DGS Department of General Services
DVBE Disabled Veteran Business Enterprise
GAO Government Accountability Office
MTC Metropolitan Transportation Commission
PG&E Pacific Gas and Electric
RDP Rail delivery partner
California State Auditor Report 2018-108 v
November 2018
Contents
Summary 1
Introduction 7
Chapter 1
The Authority’s Decision to Begin Construction Before Completing
Proper Planning Led to Cost Overruns and Delays 17
Recommendations 36
Chapter 2
The Authority Has Not Successfully Enforced the Policies It Adopted
to Address Ongoing Deficiencies With Its Contract Management 37
Recommendations 58
Chapter 3
The Authority Can Improve the Quality and Transparency of Its
Monitoring and Reporting For Key Goals 61
Recommendations 68
Appendix
Scope and Methodology 71
Response to the Audit
California High‑Speed Rail Authority 73
California State Auditor’s Comments on the Response From
the California High‑Speed Rail Authority 85
vi California State Auditor Report 2018-108
November 2018
California State Auditor Report 2018-108 1
November 2018
Summary
Audit Highlights . . .
Results in Brief Our audit of the California High‑Speed
Rail Authority and its contracting and cost
Conceived as the nation’s first bullet train, the California high-speed control practices highlighted the following:
rail system promises to transform how Californians travel across
» Although the Authority has secured and
the State. However, the California High-Speed Rail Authority
identified funding of over $28 billion that
(Authority)—the state agency responsible for planning, building,
it expects will be sufficient to complete
and operating the system—faces serious challenges. Although the
initial segments, that funding will not
Legislature created the Authority in 1996, voters did not approve
be enough to connect those segments or
major funding until 2008, when they authorized $9.95 billion in
finish the rest of the system—estimated
general obligation bonds, $7.5 billion of which is for the system’s
to cost over $77 billion.
planning and construction. Two years later, the Authority
received $2.6 billion in funding through the American Recovery » It has incrementally modified its plans for
and Reinvestment Act (Recovery Act) to begin planning and a fully dedicated high‑speed rail system
construction. In 2011 it received an additional $929 million in since 2012 and now intends to share—
federal grant funding, bringing total federal support to $3.5 billion. blend—existing transit infrastructure
The Authority receives 25 percent of the revenues from the State’s wherever feasible. Although blending is
cap-and-trade program, resulting in $1.7 billion as of December 2017. less costly, it subjects high‑speed trains
In total, the Authority has secured $12.7 billion in funding and to lower speed limits and may require
identified up to $15.6 billion in possible future funding. The Authority sharing time on the tracks with other
expects this funding will be sufficient to complete initial segments rail operators.
of the system between Madera and north of Bakersfield and between
» The fact that it has now exhausted
San Francisco and Gilroy, but not to connect those segments or finish
all feasible options to use existing
the rest of the system between San Francisco and Los Angeles. Its
infrastructure raises concerns about its
most recent cost estimate for the larger system, which it presented
ability to mitigate future cost increases.
in its 2018 business plan, is $77.3 billion.
» The risk of additional cost increases is
high. Costs to date have been significantly
Since 2012 the Authority has incrementally modified its plans for
greater than originally projected because
a fully dedicated high-speed rail system. Instead, it now intends
the Authority moved forward before it
to share existing transit infrastructure wherever feasible, an
completed many critical tasks such as
approach known as blending that has helped to offset rising costs
purchasing land, planning how to relocate
in the system. It currently plans to blend with local rail service on
utility systems, or obtaining agreements
the San Francisco Peninsula and in Los Angeles, as well as to share
with external stakeholders.
a freight corridor between San Jose and Gilroy. Although less costly
than the dedicated approach, blending also subjects high-speed • This risk contributed to $600 million in
trains to lower speed limits and sometimes requires sharing time on changes to construction contracts.
the tracks with other rail operators. The extent to which blending
• The Authority estimates that finishing
will negatively affect rail service will not be known until a private
the construction that is currently
sector operator, which will ultimately run the system for the
underway will require another
Authority, makes service decisions, such as how fast and frequently
$1.6 billion.
to operate the trains. The fact that the Authority has now exhausted
all feasible options to use existing infrastructure raises concerns • If the Authority does not complete
about its ability to mitigate future cost increases. construction by the federal
government’s December 2022
The Authority’s spending to date and future projections suggest deadline, it may need to repay
that the risk of such additional cost increases is high. Costs for the $3.5 billion.
three current construction projects in the Central Valley have been
significantly greater than the Authority originally projected, in large continued on next page . . .
2 California State Auditor Report 2018-108
November 2018
» It needs to improve its contract part because the Authority did not complete many critical planning
management to control soaring costs— tasks before moving forward with construction. Although the
it currently has 56 contract managers Authority has asserted that the early start was necessary to comply
throughout its organization, but these with the requirements for the system’s federal grant funding, it was
individuals generally do not serve in aware that beginning construction without completing sufficient
contract management roles full time. planning would expose the construction projects to a number of
Moreover, it has placed portions of its risks it had not addressed. The risks associated with beginning
oversight of large contracts into the construction early—the fact that the Authority had not acquired
hands of outside consultants. sufficient land for building, had not determined how it would
relocate utility systems, and had not obtained agreements with
• In reviewing nine planning,
external stakeholders, including impacted local governments and
engineering, and consulting
other railroad operators—developed into costly problems. These
contracts, few contract managers
risks have contributed to more than $600 million in changes to
could provide evidence of reviewing
construction contracts to pay for work for which the Authority had
each monthly invoice for accuracy,
not sufficiently planned or budgeted.
none maintained tracking logs of
deliverables, and most were unable
Despite being aware of these risks, the Authority did not account
to demonstrate how they ensured the
for them in its project cost estimates until this year. It now forecasts
quantity and quality of the work for
that finishing the construction that is currently underway will
which the Authority paid.
require still another $1.6 billion in contract changes. In addition,
» Although it has estimated the it estimates that it will need to push completion dates back as far
environmental impacts of its current as March 2022—close to the federal government’s December 2022
construction, it has not comprehensively grant deadline. If the Authority does not complete the construction
evaluated its performance against by this deadline, it may need to repay $3.5 billion in federal
those estimates. funding, $2.6 billion of which it reports it has already spent. To
meet the current schedule, the Authority will need to ensure that
construction proceeds twice as fast as it has thus far. Meeting this
schedule, which the Authority acknowledges is aggressive, will be
possible only if it effectively monitors and mitigates risks—tasks it
has performed inconsistently to date. Moreover, looking beyond the
Central Valley, the Authority’s precarious funding situation means
it cannot repeat past mistakes.
In addition, the Authority will need to do more to control
the soaring costs of its contracts by improving its contract
management. After the Authority conducted two internal audits
in 2015 and 2016 that identified significant deficiencies with
its contract management practices, it established a contract
administration organization in 2016, which included the
Contract Management Support Unit (CMSU). This unit then
oversaw the development of revised policies and procedures that
emphasize the specific processes contract managers must perform
and document. The Authority also tasked CMSU to monitor
compliance with the policies. However, the potential effectiveness
of the policies has been limited by the Authority’s contract
management structure. The Authority has 56 contract managers
throughout its organization, but these individuals generally do
not serve in contract management roles full-time. Moreover, the
Authority has in essence placed portions of its oversight of large
California State Auditor Report 2018-108 3
November 2018
contracts into the hands of outside consultants, for whom the
State’s best interests may not be the highest priority. In addition,
CMSU—which is staffed by consultants rather than Authority
employees—has performed only weak and inconsistent oversight.
Likely as a consequence of these organizational weaknesses, when
we reviewed nine planning, engineering, and consulting contracts,
with a combined value of $1.3 billion, we noted significant problems
with the Authority’s adherence to its requirements related to
invoice review, deliverables monitoring, and change management.
For example, Authority procedures require a systematic approach
to ensure that contractors bill only appropriate and allowable
costs. Although Authority contract managers asserted through
standardized checklists that they had complied with those
procedures by reviewing each monthly invoice for accuracy, few
could provide evidence of those reviews.
We found similar problems when we reviewed the Authority’s
monitoring of deliverables—the services or work products for
which it contracted. To document the timeliness and quality of a
contract’s deliverables, the Authority requires each contract manager
to maintain a tracking log of those deliverables and to provide
the contractor with written notices of acceptance. Nonetheless,
none of the contract managers for the nine contracts we reviewed
maintained tracking logs. Further, only two contract managers
could demonstrate any formal documentation for the acceptance
of deliverables, and we have concerns regarding the timeliness
with which these two contract managers evaluated and accepted
deliverables. Moreover, for nearly all the contracts we reviewed,
the only documented information about the timeliness and status
of deliverables came from the contractors themselves, leaving us
unable to determine how the Authority ensured it received the
quantity and quality of work for which it paid. Because of the lack
of documentation, we were also generally unable to determine how
the Authority identified and resolved problems with deliverables.
Without the contract management documentation its policies
require, the Authority cannot demonstrate that the hundreds of
millions of dollars it has spent to date on the contracts we reviewed
has been necessary or appropriate.
We also found that the Authority often amended its contracts to
add time or additional funds and that when doing so, it relied on
the contractors’ own estimates and projections of the associated
costs and delays. The Authority designed its contract management
procedures, as well as the related tracking requirements, to ensure
that it identifies the need for contract changes in a timely manner
and that it appropriately ensures the justification of those changes
before adopting them as amendments. However, we found little
documentation demonstrating whether or how the Authority
4 California State Auditor Report 2018-108
November 2018
independently evaluated the validity and size of the amendments
to contracts we reviewed. In some instances, we noted that
the Authority approved the amendments based wholly on the
information the contractors reported to it.
Construction of the high-speed rail system is not only a major
undertaking in terms of its costs, but it also affects the State’s
environment. Although the Authority is aware that it needs to
manage the environmental effects of construction, we identified
ways it could improve its monitoring and measurement of these
impacts. For example, the Authority intends for the system to be
a model for future rail infrastructure, but it has not sufficiently
identified key objectives in its sustainability policy to ensure that its
active construction projects follow sustainable practices. Further,
an expert we retained determined that although the Authority
appropriately estimated the environmental impacts of its current
construction before beginning work, it has not comprehensively
evaluated its performance against those estimates.
Summary of Key Recommendations
Before executing its next construction contract, the Authority
should establish formal prerequisites for beginning construction to
prevent avoidable cost overruns and project delays. At a minimum,
these prerequisites should identify specific benchmarks related
to property acquisition, utility agreements and relocations, and
agreements with external stakeholders, including impacted local
governments and other railroad operators.
To enable policymakers and the public to track the Authority’s
progress toward meeting the Recovery Act deadline in 2022,
the Authority should begin providing quarterly updates to the
Legislature detailing the progress of Central Valley construction by
January 2019.
To improve its contract management, increase accountability, and
demonstrate that the significant amounts it pays for contracted
services are justified, the Authority should take the following steps
by May 2019:
• Prioritize contract management efforts by establishing a process
for hiring and assigning full-time, experienced contract managers.
• Require CMSU to establish a schedule to monitor contract
manager compliance, and help ensure the unit’s integrity by staffing
it with full-time contract managers who are state employees.
California State Auditor Report 2018-108 5
November 2018
• Hold contract managers accountable for performing the duties
that the Authority’s policies assign to them. The Authority should
require and review documentation of the contract managers’
compliance with these policies and related procedures.
To help ensure that it meets its sustainability goals, the Authority
should comprehensively compare the environmental impact of its
construction to its baseline estimates on a quarterly basis by May 2019.
Agency Comments
The Authority agreed with our recommendations and identified
actions it is taking or planning to take to implement them.
6 California State Auditor Report 2018-108
November 2018
California State Auditor Report 2018-108 7
November 2018
INTRODUCTION
Background
California considered developing a high-speed rail network for many
years; as early as 1981, the State evaluated working with Japanese
partners to construct a high-speed rail line in Southern California.
However, planning did not begin in earnest until the mid-1990s.
In 1996, the California Intercity High-Speed Rail Commission,
which had investigated whether a high-speed train system could be
possible in California, issued a report concluding that high-speed
rail in the State was feasible. Following that report, the Legislature
formed the California High-Speed Rail Authority (Authority), which
is responsible for planning, building, and operating high-speed,
intercity passenger rail service in the State. If completed, the
high-speed rail system promises to transform how people travel in
California and would be the first bullet train in the nation.
A part of the California State Transportation Agency, the
Authority is overseen by board of directors (board). The Governor
appoints five of the board’s voting members, and the Legislature
selects the other four, along with appointing one senator and
one assemblymember to serve as nonvoting members. The board
supervises the Authority’s employees, who numbered more
than 190 as of June 2018. In addition, since 2006 a consulting firm
has helped manage the high-speed rail project by acting in a role
that the Authority labels rail delivery partner (RDP consultants).
As of June 2018, the RDP consultants had 485 staff working on the
project. Figure 1 on the following page summarizes key events in
the Authority’s history, as well as projected completion dates for
portions of the eventual rail system.
Funding
The Authority has secured a total of $12.7 billion in funding and
has identified an additional $15.6 billion in possible future funding
for the high-speed rail system. Although the Authority completed
some preliminary planning tasks in the years following its creation,
it did not have a dedicated revenue stream until November 2008,
when voters approved Proposition 1A, which provided funding for
the system. Also known as the Safe, Reliable High-Speed Passenger
Train Bond Act for the 21st Century, Proposition 1A allowed for
the issuance of $9.95 billion in state general obligation bonds,
$7.5 billion of which is for the system’s planning and construction.
Two years later, the State secured federal funding for the project
through the American Recovery and Reinvestment Act (Recovery
Act), which provided $2.6 billion through a matching grant.
8 California State Auditor Report 2018-108
November 2018
Figure 1
Timeline of High-Speed Rail Development
11999966 The Authority is formed by Senate Bill 1420, the High-Speed Rail Act.
22000000 The Authority releases its first business plan.
22000088 Proposition 1A passes, authorizing $9.95 billion in general obligation bonds.
22001100 The Authority is awarded $2.6 billion in a federal American Recovery and Reinvestment Act grant.
2011
The Authority’s 2012 business plan introduces blending between San Francisco and San Jose, and it plans to have initial
22001122 construction connect the Central Valley and Los Angeles.
22001133 The Authority executes its first construction contract for work in the Central Valley.
22001155 Central Valley construction officially breaks ground.
22001166 The Authority’s 2016 business plan focuses on finishing the Silicon Valley to Central Valley line (Valley-to-Valley segment) in
Northern California first.
22001188 The Authority’s business plan shows construction overruns and other cost increases, which raise the overall system cost
estimate to $77.3 billion.
2020 Completion date for Central Valley construction based on current contracts.
March 2022: New expected completion date for Central Valley construction based on projected contract changes.
2022
December 2022: Federal Recovery Act deadline for Central Valley construction.
2027 Potential start of high-speed rail operations between Madera and Bakersfield and, separately, between San Francisco and Gilroy.
2029 Planned completion of Valley-to-Valley segment with service between San Francisco and Bakersfield.
2033 Assumed completion of Phase 1 system.
Source: State law, state election records, federal grant agreements, and the Authority’s business plans, contracts, and press releases.
California State Auditor Report 2018-108 9
November 2018
In 2011, the State received an additional $929 million in federal
grant funding, bringing the total federal support to $3.5 billion.
The Authority also receives a continuous appropriation of
25 percent of revenues from the State’s Greenhouse Gas Reduction
Fund, which is funded by the State’s cap-and-trade program.
As of December 2017, this funding stream had provided the
Authority $1.7 billion, and the Authority projects it will receive
between $4 billion and $4.5 billion in future revenues from the
fund through 2030. The Authority also projects receiving an
additional $3.9 billion to $11.1 billion if it is able to use federal loan
programs or public-private partnerships to borrow against future
cap-and-trade revenue.
The Authority presented its most recent cost estimate for the
system—$77.3 billion—in its 2018 business plan. The Authority stated
in the 2018 business plan that it would continue to pursue all possible
options for funding the project, including additional federal grants
and private sector partnerships. However, these funding sources
have not yet materialized. The Authority is also exploring additional
funding scenarios with local governments in the cities and counties
where it plans to build stations. In recognition of the expected
economic impact of the new rail stations, the local governments that
partner with the Authority would use future property tax revenues
to help support the development of such stations within their
jurisdictions. Although recent state legislation has expanded these
types of funding options and the Authority has worked with cities to
evaluate their feasibility, it is still in the early stages of this planning.
Similarly, the Authority has researched the prospect of receiving
advertising and station parking revenue in the future.
System Planning and Construction
According to its 2000 business plan, the California high-speed
rail system was originally conceived as a stand-alone, dedicated
system spanning over 700 miles and connecting some of the State’s
largest cities, including San Diego, Los Angeles, San Francisco,
and Sacramento. Early plans for the system also called for stations
throughout the Central Valley, including in Bakersfield and Fresno.
Since that initial vision, the Authority’s plans have changed
dramatically. Most notably, in its 2012 revised business plan, the
Authority introduced the concept of blending—the practice of
sharing existing infrastructure with other rail operators instead
of constructing dedicated infrastructure for high-speed trains—
which partially offset the system’s rising cost estimates. Although
previous business plans had considered opportunities to integrate
the system with other railways, the 2012 plan was the first time the
Authority formally introduced blending into the system by deciding
to share the corridor between San Francisco and San Jose with an
10 California State Auditor Report 2018-108
November 2018
existing regional carrier, Caltrain. Since then, the Authority has
incrementally adopted blended options elsewhere in the system,
including between Burbank and Los Angeles and—as it announced
in its 2018 business plan—between San Jose and Gilroy. Figure 2
details how planned blending has expanded across portions of the
system over time. We further discuss the projected cost savings
associated with blending, as well as the service implications, in
Chapter 1 of this report.
In the 2012 business plan, the Authority also announced that it
would use a segmented approach to building the system, in part due
to the lack of sufficient funding for the full system. The segmented
plan initially called for the Authority to construct a segment
between Merced and the Los Angeles basin on which it would
operate high-speed service before completing the rest of the system.
However, in its 2016 business plan, the Authority changed course
and stated that it planned to build first between San Jose and an
interim station north of Bakersfield, an approach the Authority has
named the Silicon Valley to Central Valley Line (Valley-to-Valley
segment). In 2018, the Authority announced that it would expand
the planned Valley-to-Valley segment to San Francisco in the north
and downtown Bakersfield in the south; previously, the southern
terminus had been Shafter, a small farming community north
of Bakersfield. However, the Authority’s 2018 business plan
acknowledges that although it has the funds necessary to complete
work in the Central Valley between Madera and Bakersfield, as
well as between San Francisco and Gilroy, the funds will not be
sufficient to complete the tunnels necessary to connect those
two lines or extend the system south to Los Angeles. Figure 3 on
page 12 illustrates the Authority’s current and projected funding as
compared to the estimated cost of different segments.
Construction of the system is now underway in the Central Valley.
Current construction is focused on developing the initial
infrastructure, such as bridges and viaducts. Future construction
will lay the physical track and will install other needed support
services and maintenance facilities. As Figure 4 on page 13
shows, the Authority has divided its current construction into
three projects, which this report refers to as Project 1, Project 2/3,
and Project 4. The Authority has entered into contracts with
different construction firms for the delivery of each project. These
construction contracts represent $3.1 billion of the $5.6 billion in
contracts that the Authority currently oversees. Chapter 1 of this
report includes our review of each construction project, including
its cost and status.
California State Auditor Report 2018-108 11
November 2018
Figure 2
The Authority’s System Plans for Phase 1 Have Evolved Over Time
Sacramento 2000 Sacramento 2012
San San
Francisco Francisco
MillbraeSan Francisco International Airport (SFO) MillbraeSFO
San Jose San Jose
Merced Merced
Gilroy Madera Gilroy Madera
Fresno Fresno
Introduced blending between
San Francisco and San Jose
Kings/Tulare Kings/Tulare
Bakersfield Bakersfield
Palmdale
Burbank Burbank
Los Angeles Union Station Los Angeles Union Station
San Diego San Diego
Sacramento 2016 Sacramento 2018
San San
Francisco Francisco
MillbraeSFO MillbraeSFO
San Jose San Jose
Merced Merced
Gilroy Madera Gilroy Madera
Fresno Fresno
Extended blending
Kings/Tulare south to Gilroy Kings/Tulare
Bakersfield Bakersfield
Palmdale Palmdale
Burbank Burbank
Los Angeles Union Station Los Angeles Union Station
Added blending between
Burbank and Los Angeles
San Diego San Diego
Dedicated high-speed rail infrastructure Change to previous business plan
Blended (shared) infrastructure
Source: The Authority’s published business plans, budgets, and planning documents.
Note 1: The Authority has not consistently planned to operate service between Los Angeles and Anaheim. As recently as 2014, the Authority did not
plan to operate trains on this segment. The Authority now plans to operate high‑speed trains on this segment by sharing track with Metrolink. However,
because these plans do not represent a shift from dedicated to blended infrastructure over time, this segment is not included in the above analysis.
Note 2: The Authority has consistently stated that it intends to eventually complete Phase 2, which will extend the system to San Diego (via the
Inland Empire) and Sacramento after it finishes Phase 1 between San Francisco and Los Angeles. The maps above show Phase 1 only.
12 California State Auditor Report 2018-108
November 2018
Figure 3
The Authority Has Secured Funding to Finish Construction in the Central Valley but Not the Rest of the System
$80
70
60
50
40
30
20
10
0
Funding Segment Costs
)snoilliB
ni(
sralloD
PHASE 1 TOTAL COST:
$77.3 billion
Remaining cost for Phase 1
(San Francisco to Anaheim):
$47.8 billion
VALLEY-TO-VALLEY
TOTAL COST:
$29.5 billion
Financing of
cap-and-trade revenue
through 2050: UNSECURED Remaining cost for
up to $11.1 billion FUTURE FUNDING: Valley-to-Valley segment
up to $15.6 billion*
(San Francisco to Bakersfield):
$18.9 billion
Future cap-and-trade revenue:
up to $4.5 billion
SECURED FUNDING:
$12.7 billion
Proposition 1A bonds: Cap-and-trade revenue:
$7.5 billion $1.7 billion Central Valley cost:
$10.6 billion
Federal grants: $3.5 billion
Source: The Authority’s 2018 business plan.
* The Authority presents its unsecured funding in ranges. This graph uses the high end of its estimates; the Authority’s low‑end estimates of unsecured
future funding is $7.9 billion.
California State Auditor Report 2018-108 13
November 2018
Figure 4
Current Construction Projects Are Between Madera and Bakersfield
Madera
FRESNO COUNTY
PROJECT 1
Fresno
South of Fresno
PROJECT 2/3
KINGS COUNTY
TULARE COUNTY
North of
Kings County Line
PROJECT 4
Shafter
(North of Bakersfield)
Source: The Authority’s maps and construction contracts.
Past Audits of the Authority’s Contract Management and Oversight
The Authority has been aware of shortcomings in its processes for
managing its wide range of contracts for at least the past three years.
It published internal audits in 2015 and 2016 that identified significant
deficiencies in its contract management and oversight, including its
failure to implement necessary policies and procedures, its lack of
documentation of contract management activities, and its failure
to establish sufficient oversight structures to ensure effective
14 California State Auditor Report 2018-108
November 2018
contract management. In February 2015, the Authority’s Audits Office
completed the first of these audits to determine whether the Authority
was managing contracts in accordance with state and Authority
expectations. The Authority conducted a follow-up audit in May 2016
with the same focus.
The 2015 audit emphasized that a structured contract management
process is necessary to define responsibilities for administering
contracts and for monitoring and evaluating contractors’ performance.
However, the audit found that the Authority’s contract managers did
not always receive proper guidance and often lacked the technical
expertise to thoroughly manage contracts. The audit also identified
numerous instances in which poor communication between the RDP
consultants and the Authority meant that the Authority’s contract
managers were uncertain whether invoices that the RDP consultants
approved were for appropriate services and whether contractor
work products were reasonable based on their costs.
Released 15 months later, the 2016 audit confirmed that these contract
management issues persisted and were widespread. After reviewing a
wider range of contracts and contract managers, the Authority’s
auditors concluded that contract managers continued to delegate core
contract management tasks to the RDP consultants, that roles and
responsibilities for contract managers and the RDP consultants were
not clearly defined, and that oversight of contract management was still
insufficient. Further, this report highlighted that
contract managers did not proactively document
Key Recommendations From the
their expectations for work products, putting the
Authority’s Internal Audits
Authority at risk of paying for inappropriate or
February 2015: unsatisfactory work.
• Develop effective, comprehensive contract management
processes unique to the types of contracts that the The Authority has repeatedly acknowledged the
Authority manages. need to address its contract management
• Implement a formal system of review and oversight of deficiencies. Each internal audit report contained
contract managers. recommendations intended to address inadequate
• Establish performance standards for contract management. contract management policies and structures. The
• Develop individual contract work plans that include how the Authority’s management concurred with these
Authority will manage segmented responsibilities through a recommendations, which the text box summarizes.
communication plan that identifies roles and responsibilities.
In response to the 2015 internal audit, management
May 2016: asserted that the Authority had contract
• Establish oversight for contract managers, along management policies, procedures, roles, and
with clearly documented expectations and regular responsibilities in place. However, it acknowledged
communication to ensure contract requirements are met.
that contract managers had not consistently
• Ensure that persons performing contract management adopted those policies and procedures. After the
have sufficient information to determine if invoiced costs
2016 internal audit revealed ongoing widespread
are reasonable and deliverables meet requirements.
deficiencies, the Authority’s management
Source: The Authority’s February 2015 and May 2016 internal recognized that the implementation of existing
audits of contract management.
contract management policies had not yet yielded
the desired results.
California State Auditor Report 2018-108 15
November 2018
Current Contract Management Policies and Procedures
In response to its 2015 and 2016 internal audits, the Authority
established a contract administration organization in 2016, which
included the Contract Management Support Unit (CMSU). The
Authority tasked CMSU with developing revised and improved
policies and procedures, governance structures, and training and
other resources applicable to all contract management areas. In
April 2017, the Authority approved nine new policies and procedures
related to contract management. These policies cover key areas for
contract management, including invoicing and payment, performance
monitoring and reporting, and contract compliance. Additionally,
the procedures outline processes to ensure that contract managers
effectively manage contract documents, deliverables, risks, changes,
and disputes. When we compared the 2017 policies with requirements
in California’s State Contracting Manual, we found that the Authority’s
policies were consistent with those requirements in areas related to
controlling costs, such as prompt invoice review and comprehensive
monitoring of contractor work products, referred to as deliverables.
We also found that the 2017 policies improved upon the Authority’s
previous policies by specifying required contract management processes
and the documentation of those processes. That is, although both the
2014 contract manager handbook and the 2017 policies are broadly
consistent with the State Contracting Manual, the 2017 policies
emphasize specific process steps that contract managers must perform,
require the use of tracking logs and other documents, establish a
standardized file system for maintaining contract management
documentation, and create a process for transferring files to
new contract managers to preserve the consistency of contract
oversight. Table 1 on the following page lists the
documentation that the policies require contract
managers to maintain to demonstrate how they are CMSU’s Oversight Responsibilities
monitoring each contract. In these ways, the policies
• Review and report on contract managers’ compliance.
recognize both the deficiencies uncovered by the
• Communicate noncompliance to appropriate supervisors.
Authority’s internal audits and the need to document
• Follow up on concerns until completely resolved.
processes to facilitate and demonstrate compliance.
Source: The Authority’s contract management policies
and procedures.
Although the Authority as a whole is responsible for
writing contracts in a manner that safeguards the
State’s interests, its contract management policies
identify contract managers as the personnel responsible for overseeing
those contracts once executed. Further, the Authority’s 2017 policies
and procedures assign CMSU oversight responsibility to help ensure
contract managers’ compliance with policies, as the text box describes.
The Authority also requires CMSU to collect feedback to help develop
lessons learned and identify areas for continued improvement.
In Chapter 2, we evaluate the Authority’s implementation of its
new contract management policies and procedures.
16 California State Auditor Report 2018-108
November 2018
Table 1
The Authority’s Procedures Require Contract Managers to Keep Clear Documentation Related to Ensuring
Contract Value and Controlling Costs
CONTRACT
MANAGEMENT REQUIRED DOCUMENTATION TO ENSURE CONTRACT VALUE, CONTRACT MANAGERS MUST...
AREA
Invoice tracking log Use this log to track the contract’s invoices, expenditures, budget, and forecast. This
process is essential to managing the contract and ensuring the contractor does not
incur costs over the contract’s limit.
Invoices Invoice approval checklist Complete an approval checklist to verify that each invoice submitted for payment is true,
correct, and in accordance with law for all contracts with value greater than $5 million.
Dispute tracking log Use this log to track and document invoice dispute information and the status of the
resolution process.
Deliverables tracking log Use this log to document the contract deliverables’ status and the determination of
whether the deliverables are timely and meet the quality terms of the contract.
Deliverable acceptance notice Use this notice to attest that a deliverable meets the acceptance criteria and to indicate
Deliverables acceptance of the final deliverable.
Recovery plan Request this plan from the contractor if a contract deliverable has fallen behind schedule,
does not meet contract requirements or documented acceptance criteria, or may
require repeated work.
Risk register Use this register to identify risks, as well as strategies to accomplish contract objectives
in the face of those risks.
Change tracking log Assess any potential amendments to a contract for merit, and use this log to document
Performance and the outcome of this assessment, the potential amendment’s impact on the project’s
Amendments schedule and proposed cost, and a description of the issue or need for change.
Contract compliance assessment Conduct assessments of contract requirements, including—at a minimum—
insurance, small business utilization, deliverables, invoicing, schedule, change orders,
and subcontracts.
Source: The Authority’s contract management policies and procedures.
California State Auditor Report 2018-108 17
November 2018
Chapter 1
THE AUTHORITY’S DECISION TO BEGIN CONSTRUCTION
BEFORE COMPLETING PROPER PLANNING LED TO COST
OVERRUNS AND DELAYS
Chapter Summary
After years of planning for a fully dedicated high-speed rail system,
mounting costs led the Authority to decide instead to use existing
infrastructure wherever possible—a cost control technique known
as blending. Blending requires lower train speeds and imposes other
service limitations, but the Authority will not know the full effect
of these limitations until service planning and operations begin.
Although blending has resulted in significant projected savings,
those savings have only partially offset cost overruns. Further,
potential time savings from reduced construction needs will be at
least partially offset by the years that the Authority spent studying
the dedicated options rather than pursuing blended options. The
Authority has now exhausted every major opportunity available
to share infrastructure with existing rail systems; thus, sharing
infrastructure no longer represents a source of future cost savings.
The Authority’s decision to begin construction despite not
having sufficiently accounted for known risks contributed to
its significant cost overruns. The Authority told us it decided
to proceed with construction because it was concerned about
deadlines for using $2.6 billion in federal grant funds. However,
the risks in question—not having acquired the land to build on, a
lack of agreements with existing utility systems, and uncertainty
about the requirements that external stakeholders might impose—
manifested in changes to its construction contracts that have thus
far increased the three current construction projects’ costs by more
than $600 million. Further, the Authority estimates that it will
need an additional $1.6 billion in contract changes to finish these
three projects, pushing its total cost overruns above $2 billion.
The contract changes have also resulted in significant time delays,
and consequently the Authority has had to continually extend the
projects’ expected completion dates, pushing them back from 2018
to March 2022. Even with the extended schedules, construction will
need to proceed much faster than it has to date for the Authority to
meet the federal government’s construction completion deadline of
December 2022. If the Authority misses this deadline, the federal
government could require it to repay the grant funds it received;
therefore, it is vital that the Authority do all it can to ensure its
time and cost projections are accurate so that it can detect and
address any further risks. Moreover, as it moves forward with the
18 California State Auditor Report 2018-108
November 2018
construction of the rest of the system, the Authority must take steps
to ensure that it does not repeat the types of decisions that led to its
significant cost and time overruns to date.
After Years of Planning a Dedicated High-Speed Rail System, the
Authority Has Now Pursued Every Option to Reduce Costs by Using
Existing Infrastructure
By incrementally modifying its plans for the high-speed rail
system, the Authority reduced planned costs for some segments.
However, these cost savings have also resulted in decreased service
capabilities. When the Authority elects to blend a segment of the
system by sharing existing rail corridor owned by another railroad,
it significantly reduces planned costs by limiting the preparation
needed to lay track. However, the Federal Railroad Administration
sets a speed limit of 125 miles per hour for high-speed trains
sharing a corridor or track with other rail traffic and of 110 miles
per hour limit if the tracks intersect roads, which can be avoided
by elevating tracks over or tunneling under roads. These blended
segment speeds are significantly lower than those for dedicated
high-speed segments of the system, where regulations allow speeds
up to 220 miles per hour.
Further, sharing track means that high-speed rail trains must split
time on the tracks with other operators, limiting how frequently
high-speed trains can operate on a segment. For example, on
the San Francisco Peninsula, sharing tracks with Caltrain means
that the Authority can only operate four high-speed trains
per hour, instead of 12 per hour, as it originally planned. The
Authority similarly plans to share track between Burbank and
Los Angeles with Metrolink, Amtrak, and Union Pacific Railroad
(Union Pacific). Figure 5 shows how these limitations will affect
eventual service options for the three segments where the Authority
has implemented blending: San Francisco to San Jose, San Jose to
Gilroy, and Burbank to Los Angeles.
Although blending a segment of Although blending will impose limitations on eventual high-speed
the system by sharing existing rail rail operations, the extent to which the limitations will negatively
corridor owned by another railroad affect actual rail service is not yet clear. According to the Authority’s
will impose limitations on eventual deputy chief of rail operations, one reason why the limitations are
high‑speed rail operations, the not yet known is that service decisions, such as how fast and how
extent to which the limitations will frequently to operate the trains, have not yet been determined by
negatively affect actual rail service the private sector operator that the Authority will select to run the
is not yet clear. system. Until the operator decides how many trains are needed,
the Authority will not know the effect of sharing track. Similarly,
although reducing speed limits imposes a restriction with which the
train operator must contend, other service considerations also will
influence how fast the operator will run the trains. For example,
California State Auditor Report 2018-108 19
November 2018
Figure 5
The Authority Has Adopted Blending in Three Segments
SAN FRANCISCO to SAN JOSE
Original Plan Blended Infrastructure
High-Speed Rail Caltrain Shared tracks with Caltrain
Shared Corridor Shared Tracks
125 110
HSR trains per hour HSR trains per hour
MPH MPH
speed limit speed limit
Sacramento
San
Francisco
MillbraeSFO
SAN JOSE to GILROY
San Jose
Merced
Original Plan Blended Infrastructure Gilroy Madera
Fresno
Shared tracks with Caltrain
Kings/Tulare
Dedicated Viaduct Shared Tracks Bakersfield
220 110
HSR trains per hour Undetermined†
MPH MPH Palmdale
speed limit* speed limit
Burbank
Los Angeles Union Station
BURBANK to LOS ANGELES
Original Plan Blended Infrastructure San Diego
Shared tracks with Metrolink
OR
Dedicated Viaduct or Tunnel Shared Tracks
160 125
HSR trains per hour HSR trains per hour
MPH MPH
speed limit* speed limit
Source: Review of the Authority’s business plans, capital cost basis of estimate reports, preliminary and supplemental alternative analysis reports,
preliminary engineering for project design reports, service planning studies, and additional cost estimates provided by Authority staff.
* Maximum speed limit shown; speed limited to 140 miles per hour in some segments.
† The Authority stated that it plans to run 12 trains per hour on this segment but did not provide us with any studies or agreements showing how it
will accomplish this number.
20 California State Auditor Report 2018-108
November 2018
the distance necessary to safely accelerate or decelerate high-speed
trains means that the trains may not be able to operate at 220 miles
per hour in parts of the system even if speed limits allow it because
of the need to navigate curves and stop in stations.
We attempted to identify how the new speed limits have affected
the Authority’s projections of the blended segments’ travel times,
but the Authority was largely unable to provide any supporting
documentation for the travel times it projected for these segments
before 2016. Because the Authority had already implemented
much of the system blending by then, it was generally unable to
demonstrate how much time blending added to its travel time
estimates. One exception was the segment between San Jose and
Gilroy, for which the Authority did not adopt blending until 2018.
For this forty-mile segment, the projected travel time increased from
fourteen to eighteen minutes when the Authority switched from a
dedicated line to shared track, decreasing the maximum speed for
this segment.
Blending has allowed the Authority Blending has allowed the Authority to expedite the system’s planned
to expedite the system’s planned time for construction by eliminating the time needed to design
time for construction, but the and build tunnels, viaducts, and other dedicated infrastructure,
effect of those time savings may but the effect of those time savings may be offset by the Authority’s
be offset by the Authority’s past past decisions to continue to study dedicated options. Rather than
decisions to continue to study adopting a blended model for as much of the system as possible early
dedicated options. on, the Authority has incrementally accepted blended alternatives
over the past six years. As of 2012, the Authority planned to construct
two new, dedicated tracks, including tunnels and viaducts, between
San Jose and San Francisco. Rising cost estimates for this section
contributed to the $98 billion system cost the Authority reported
in its draft 2012 business plan. To address the rising costs and local
governments’ concerns about the potential impacts to environmental
and community resources on the Peninsula, the Authority proposed
a blended model in its revised plan. Shortly thereafter, the State
Legislature mandated for this segment that the Authority could not
use state funds to expand beyond Caltrain’s existing tracks in the
corridor. In its revised 2012 business plan, the Authority reported
the segment’s estimated costs had decreased from $13.6 billion to
$5.6 billion, or 59 percent, after it adopted the blended approach.
Table 2 provides the Authority’s estimates for the decreased costs
of the blended segments, which have partially offset increases in its
systemwide cost estimates.
Despite its adoption of the blended model in its 2012 revised
business plan for one segment, the Authority continued to study
dedicated options for at least two more years and did not begin
studying a blended option in Los Angeles until 2015, limiting the
time savings it might have realized had it acted more quickly.
In 2012, the Authority’s original plans for Burbank to Los Angeles
California State Auditor Report 2018-108 21
November 2018
called for either a tunnel under central Los Angeles or an aerial
viaduct—similar to a bridge—running through it. In its May 2014
analysis document supporting the 2014 business plan, the Authority
was still planning for dedicated options including a tunnel,
ground-level track, and viaducts. The Authority did not introduce
the blended, shared-track model for this segment in its planning
document and business plan until 2016.
Table 2
Blending Significantly Reduced Planned Costs for Affected Segments
(Dollars in Billions)
EFFECTS OF BLENDING
COST CHANGE
SEGMENT BEFORE AFTER AMOUNT PERCENTAGE
San Francisco to San Jose $13.6 $5.6 ‑$8.0 ‑59%
San Jose to Gilroy 4.4 2.8 ‑1.6 ‑36
Burbank to Los Angeles 2.9 1.6 ‑1.3 ‑45
Source: The Authority’s published business plans, budgets, and internal planning documents.
Note: This table only reflects cost estimates before and after blending was implemented on
each segment in order to demonstrate the effect of blending on costs. Other factors, such as a
reduction in the planned number of bridges in a segment, have lowered cost estimates after the
implementation of blending.
The Authority’s Southern California regional director confirmed
that the Authority did not seriously begin studying a blended
option for Los Angeles until 2015, when it procured a new planning
contractor, and that it waited this long to ensure the blended
model would not have unexpected consequences. Additionally,
the regional director stated that because very little funding was
available during this time period, the Authority could not conduct
the study of the blended option. However, the 2012 revised business
plan states that the Authority’s position is that the system’s benefits
will be delivered faster through the blended approach. We therefore
question why it waited three years to begin studying the blended
option in Los Angeles to determine whether it was viable. Had
the Authority acted earlier, it could have captured more of the
time savings blending represents. For example, the Authority’s
2012 decision to use blending on the San Francisco Peninsula
has led to construction already beginning in that location.
By comparison, the Authority has yet to finalize its planned
route between Burbank and Los Angeles.
22 California State Auditor Report 2018-108
November 2018
Although the process took several years, the Authority states it has
now adopted blending in every segment of the system where sharing
infrastructure is possible. In its 2018 business plan, it indicated for
the first time that it intends to blend the segment between San Jose
and Gilroy by operating within existing freight corridors and
possibly sharing track with other carriers. Because the Authority
is already pursuing blending on the San Francisco Peninsula and
in Los Angeles, its chief of rail operations asserted that no further
blending options are available. Additionally, he stated that travel
time requirements mean that the Authority cannot implement
additional blended segments even if opportunities become available.
State law requires that the system be designed to achieve a nonstop
travel time from San Francisco to Los Angeles Union Station of
two hours and 40 minutes; according to the Authority’s model, the
travel time incorporating the current level of blending is expected to
be two hours, 36 minutes, and 56 seconds.
Our review similarly noted that the blending of additional segments
is unlikely because of characteristics of the remaining segments.
For example, the only existing rail line traversing the Tehachapi
Mountains in Southern California is a winding freight line built in
the 1870s. In the north, where the Authority plans to connect the
Central Valley to the Bay Area via the Pacheco Pass, no current
rail system exists. In both regions, the Authority plans to pursue
complicated tunneling projects that include tunnels over 20 miles
long and more than 2,000 feet underground.
Blending has allowed the Authority to partially offset significant
Our analysis shows that the cost overruns for the system as a whole. Our analysis shows that
Authority’s cost estimates would have the Authority’s cost estimates would have increased by 111 percent
increased by 111 percent since the since the publication of its 2009 business plan had the Authority
publication of its 2009 business plan not implemented blending; instead, overall costs have increased by
had the Authority not implemented 81 percent. However, the fact that the Authority has now exhausted
blending; instead, overall costs have all blending options limits its ability to mitigate the effects of future
increased by 81 percent. cost overruns through additional blending.
The Authority Has Approved Hundreds of Millions of Dollars’ Worth of
Change Orders to Date, Most of Which Were for Changes It Initiated
Changes and additions that the Authority has made to its
three active construction contracts in the Central Valley have
driven costs significantly higher than it originally projected. The
Authority uses the change order process to account for unexpected
developments, project delays that generate new contractor costs,
and other changes to its construction contracts. The construction
contracts allocate a specific dollar amount for each component of
a project’s design and construction. For any additional work that
is not contained in the contract, the Authority must authorize a
California State Auditor Report 2018-108 23
November 2018
change order, which assigns a cost for the new work and increases
the overall contract value. The Authority may direct a contractor to
do additional work through a change order, or the contractor
may request a change order for work it identifies as necessary.
Change orders can also extend a project’s timeline either to allow
additional work or to account for delays. To date, the Authority has
approved more than $600 million worth of change orders related to
the three construction projects in the Central Valley.
The Authority relies on contracted construction oversight firms
(oversight firms)—which are responsible for overseeing the
construction contracts on behalf of the Authority—to evaluate
potential change orders’ merits and provide independent
estimates of how much they should cost. However, we found that
the Authority did not always follow the oversight firms’ advice.
We reviewed 11 of these change orders with a total value of The Authority approved change
$38 million and found that the Authority obtained the required orders for dollar amounts that
levels of management approval before executing each.1 However, were more than its oversight firms
in four instances, the Authority approved change orders for dollar recommended or for work that the
amounts that were more than its oversight firms recommended or oversight firms initially determined
for work that the oversight firms initially determined was already was already covered under
covered under the contracts. the contracts.
Specifically, in two of these four change orders, the Authority
executed changes for amounts that were greater than the oversight
firms recommended. For example, the construction contractor for
Project 1 requested more than $21 million for unanticipated bridge
construction. The oversight firm disagreed with the contractor,
estimating a cost of only $7.4 million. The Authority ultimately
authorized a change order for $18.6 million—more than twice the
amount the oversight firm recommended. When we discussed
with the Authority’s director of design and construction why the
Authority authorized more than the oversight firm recommended,
he stated that the Authority’s initial position was that the
construction contractor would cover the cost of some of the new
work because it should already have been aware of the need for
that work. However, he was unable to provide any documentation
showing how the Authority determined the higher number was
appropriate. In the other change order involving a higher amount
than the oversight firm recommended, the Authority authorized an
$868,000 change when the oversight firm had recommended only
$854,000. The Authority’s documentation did not explain why the
higher amount was appropriate.
1 We also reviewed two change orders that the Authority’s legal unit settled through a different
process. Including these two change orders, the total value of our selection is $139 million. As of
June 2018, the Authority had executed more than $600 million in change orders.
24 California State Auditor Report 2018-108
November 2018
In two other instances, the Authority approved change orders
involving work the oversight firms initially determined was already
required by the existing contract terms. However, the contract
language was undermined by the assumptions that the Authority
had made during the bidding process. For example, the contractor
for Project 2/3 requested additional compensation for increased
costs associated with disconnecting existing utility lines. In
response, the oversight firm correctly identified that the contract
assigned responsibility for utility disconnection tasks to the
contractor, and therefore the contractor bore responsibility for
these costs. However, the oversight firm also noted that Pacific
Gas and Electric (PG&E), the utility owner, had begun to charge
a fee for disconnections that the Authority had not specified in
The Authority’s failure to adequately the information it provided to the construction contractor during
coordinate with a key external the bidding process. As a result, the Authority and the contractor
stakeholder before beginning negotiated the issue, and the Authority agreed to a change order
the bidding process undermined of $2.7 million. In this case, the Authority’s failure to adequately
its subsequent ability to use the coordinate with a key external stakeholder before beginning
oversight firm to enforce contract the bidding process undermined its subsequent ability to use the
terms and limit costs. oversight firm to enforce contract terms and limit costs.
In the other case we identified, the oversight firm initially
concluded that the construction contractor should bear the cost to
redesign a bridge that did not meet Union Pacific’s standards. The
Authority later approved a change order against this advice because
it had not previously executed an agreement with Union Pacific,
thereby limiting the contractor’s ability to coordinate with the
railroad. We discuss this change order in greater detail later in
this chapter.
We found that the majority of all executed change orders came
at the request of the Authority rather than the request of the
contractors. Some of these change orders were the result of
fundamental changes to the construction projects’ plans. For
example, the Authority requested and executed a $153 million
change order to extend one of the projects 2.7 miles north to
connect to the Madera County Amtrak station. Because the
Authority did not include this work in the original contract, it
clearly required a change order. However, as we discuss in the
following section, the Authority requested many other changes that
were not the result of fundamental changes to the planned system,
but rather related to its decision to begin construction before
completing critical tasks.
California State Auditor Report 2018-108 25
November 2018
The Authority Did Not Sufficiently Account for Known Risks in Its
Initial Cost Estimates
The Authority approved the start of construction in the Central
Valley in 2013 despite knowing that moving forward was likely
premature from a planning perspective and thus carried significant
risks for unknown costs. According to its chief engineer, the primary
factor in the Authority’s decision to execute a construction contract
in August 2013 was to meet deadlines for project completion and
spending of funds under the terms of its 2010 grant agreement with
the federal government. The agreement provided $2.6 billion for the
project under the Recovery Act. Because the purpose of the Recovery
Act was to create and preserve jobs and revitalize state and local
economies, the agreement required that the Authority complete
the Central Valley construction by 2017.2 In coordination with the
federal government, the Authority determined that it needed to begin
construction as soon as possible to meet that deadline. Therefore,
the Authority executed its first construction contract in August 2013
and authorized the construction contractor to begin work in
October 2013. Figure 6 on the following page details the three projects
currently underway—all of which are funded in part by federal
money—and provides a timeline of Central Valley construction.
The Authority did not complete many critical planning tasks before
beginning construction, which ultimately resulted in significant
delays and led to increased costs. Because the Authority’s planning Because the Authority’s planning
was incomplete, it has used change orders to direct its contractors was incomplete, it has used change
to perform additional work and to compensate them for delays. orders to direct its contractors
Quantifying the total cost of the change orders resulting from to perform additional work and to
the Authority’s insufficient planning is difficult, largely because the compensate them for delays.
Authority’s change order summaries do not show which changes
stemmed from the early start of construction. However, the majority
of the change order costs relate to risk areas that the Authority
had identified but not effectively quantified when it decided to
move forward with construction. Some of these risks, such as not
securing the property on which it intended to build, directly led to
cost overruns and project delays. In other instances, the Authority
did not sufficiently account for the costs arising from issues it
knew it would eventually need to address, such as relocating utility
infrastructure from project sites and addressing the concerns of
external stakeholders. At the time, it indicated that it did not have
the information or finalized agreements it needed to plan or budget
for the mitigation of these issues. Figure 7 on page 27 summarizes
the total impact that executed change orders have had on the
three current construction projects in terms of cost and delay.
2 As we discuss later in this chapter, the federal government extended this deadline to
December 2022.
26 California State Auditor Report 2018-108
November 2018
Figure 6
The Authority’s Three Current Construction Projects Have Been Phased In but Share a Deadline
CONSTRUCTION MAP
Madera Station
Madera
2010
2011
PROJECT 1
2012
Fresno Station
2013 South of Fresno
2014
2015
Project 4 started
Kings/Tulare
Regional Station
2016
PROJECT 2/3
2017
2018
Original/current end date
2019
Expected end date
2020 North of
Kings County Line
2021
PROJECT 4
2022
Shafter
(North of Bakersfield)
4
TCEJORP
Project 2/3 started
Original end date
Current end date
Expected end date
3/2
TCEJORP
Project 1 started
Original end date
Current end date
Expected end date
1
TCEJORP
CONSTRUCTION TIMELINE
Signed Recovery Act
Recovery Act deadline
Source: The Authority’s contracts, business plans, baseline schedules, and maps.
California State Auditor Report 2018-108 27
November 2018
Figure 7
The Authority’s Change Orders Have Increased the Cost and Length of Its Construction Contracts
ORIGINAL CONSTRUCTION CONTRACTS CHANGE ORDERS CURRENT CONSTRUCTION CONTRACTS
FOR ALL THREE PROJECTS (78% AUTHORITY-DIRECTED) FOR ALL THREE PROJECTS
Original Cost: Additional Cost: Current Cost:
$2.5 Billion + $600 Million = $3.1 Billion
Original End Date: Schedule Delay: Current End Date:
August 2019 9 Months May 2020
Source: The Authority’s change order records and construction contracts.
Land Acquisitions
The Authority’s decision to enter construction contracts despite
not owning the required land—as well as its subsequent inability
to acquire land on schedule—directly resulted in delays to the
construction schedules. These delays in turn led to additional
costs related to labor, materials, and equipment under contract but
not in use. The Authority’s acquisition of the land was delayed in
part by a 2011 lawsuit over whether the Authority had met legal
requirements to issue bonds, which the Authority stated it needed
to do in order to purchase property. Despite knowing that the
lawsuit could restrict access to its funds, the Authority still initiated
the request for proposals for Project 1 in March 2012 and executed
its first construction contract in August 2013. In fact, the Authority
signed the contract the same day that the superior court ruled
against the Authority—effectively freezing its bond funds. Although
the superior court’s decision was eventually overturned, the delay
significantly set back the construction contractor’s schedule. Land
acquisition delays have cost $64 million for Project 1 and extended
its completion deadline by 17 months. The Authority also issued
change orders because of land acquisition delays in Project 2/3 and
Project 4. In total, these change orders have resulted in more than
$115 million in additional costs.
Utility Infrastructure Relocations
The Authority also proceeded with construction in the Central
Valley without completing agreements with utility companies
or ensuring it had a full understanding of the magnitude of the
utility infrastructure that it would need to relocate or how it would
relocate those utilities. As a result, it could not properly budget
for these costs. For example, the Authority originally expected
to directly pay utility providers, such as PG&E and AT&T Inc., to
relocate utilities for Project 1’s planned sites before construction,
28 California State Auditor Report 2018-108
November 2018
and it set aside nearly $69 million for this work. However, the
Authority later determined the utilities would not be able to
complete the relocations in time to meet construction deadlines,
and in June 2015, it reassigned the work to the construction
contractor. In February 2017, the Authority estimated that
completing all of this work for Project 1 would ultimately cost
$216 million. However, in April 2018, it provided the board with
another revised estimate, which projected that costs would rise
to $396 million. Unlike delays in land acquisition, the Authority’s
poor estimates for utility work did not create costs where it might
Given that Project 1’s original otherwise have had none. However, given that Project 1’s original
construction contract was for construction contract was for $970 million, we find it concerning
$970 million, we find it concerning that the Authority failed to anticipate what it now expects will be
that the Authority failed to nearly $400 million in additional costs. Had it developed a better
anticipate what it now expects understanding of the costs related to relocating utilities before
will be nearly $400 million in beginning construction, it might have explored ways of mitigating
additional costs. those costs.
For the next project—Project 2/3—the Authority preemptively
assigned utility relocations to the construction contractor.
However, the Authority still did not execute an agreement with
PG&E specifying the distribution of relocation work between
the contractor and the utility for over a year after signing the
construction contract. As a result, it accounted for this delay,
along with delays related to right-of-way acquisition and other
issues, by approving additional cost and time for the construction
contract. The Authority has not had to add time for Project 4,
but utility relocations have created additional costs. According to
information it provided to us in July 2018, problems with utilities
across the three Central Valley projects had already accounted
for $215 million in costs not included in the Authority’s original
budgets. The majority of these costs—$167 million—have come
from Project 1, likely because it is the furthest along. Project 2/3 and
Project 4 have experienced $29 million and $19 million in additional
costs, respectively.
External Stakeholders’ Requirements
The Authority also did not ensure it was fully aware of the
requirements that other external stakeholders, such as other
railroads, would impose on the three projects. These requirements
led to still more costs for which the Authority did not originally
budget. For example, the Authority asked construction contractors
to bid on Project 1 and in fact began construction before it finalized
a coordination agreement with Union Pacific that specified the
circumstances under which the construction contractor could
build within Union Pacific’s right of way. The lack of such an
agreement led to the construction contractor incorrectly assuming
California State Auditor Report 2018-108 29
November 2018
that it could construct a pillar for a bridge within Union Pacific’s
right of way. When Union Pacific declined to permit the pillar,
the construction contractor argued that the Authority was at fault
because it had not previously identified this issue and alerted the
construction contractor. Although the Authority initially disagreed,
it later agreed to share the costs with the construction contractor,
with the Authority’s share being $414,000. The lack of an executed
agreement was not unique to Union Pacific; in a June 2014 letter
to the Authority, the construction contractor for Project 1 noted
that the Authority had not executed needed agreements with
several other external stakeholders—including two other railroad
operators and the city of Fresno—which resulted in delays to
the project.
In total, the Authority has approved change orders worth In total, the Authority has approved
$27 million related to requirements from external stakeholders change orders worth $27 million
across the three Central Valley projects, and it anticipates that related to requirements from
these extra costs will increase significantly during remaining external stakeholders across the
construction. For example, freight carriers are currently insisting three Central Valley projects.
that the Authority construct intrusion protection barriers to
prevent freight trains from derailing onto high-speed rail tracks
along certain portions of the Central Valley segment. The Authority
has projected that these barriers will cost an additional $315 million.
The Authority Was Aware That Its Early Start to Construction Could
Lead to Significant Additional Costs
Although its 2018 business plan asserted that the early start of
construction in the Central Valley resulted in unforeseen or
underestimated costs, the Authority had long been aware that
there were risks associated with its decisions to begin construction
without completing key preconstruction tasks and that these
decisions could lead to significant additional costs. For example, a
plan that consultants prepared for the Authority in 2011 identified
land acquisition, utility relocation, and external stakeholder
coordination as risks that would require mitigation. Similarly, the
Authority’s chief engineer confirmed that the Authority knew
in 2013 that it had not acquired sufficient land, and although it
had a plan to secure the needed land, it also knew that its ability
to use its bond funding for that purpose was uncertain because of
legal challenges. The Authority noted in a March 2013 report to
the Legislature that delays in acquiring property could affect costs
and deadlines, and it disclosed in the same report that it had not
yet entered into the necessary agreements with utility companies,
which could lead to additional costs and delays. The Authority was
also aware that it would need to work closely with Union Pacific to
coordinate construction work on and around its right-of-way, yet
the 2013 report noted that it had not yet executed an agreement
30 California State Auditor Report 2018-108
November 2018
with the railroad. It acknowledged that if the Authority could
not reach such an agreement, design work in progress or already
completed might be affected, leading to potentially significant cost
increases or schedule delays.
The Authority reported total Nonetheless, the Authority did not account for the potential costs
cost estimates when beginning of these risks in its estimates until recently. As a result, it reported
construction in 2013 that were total cost estimates when beginning construction in 2013 that were
unreasonably low. unreasonably low. In fact, the Authority’s May 2018 business plan
was the first to assign costs to known program risks, even though
we identified concerns with the Authority’s risk management
processes in our 2012 audit report.3 In that report, we found
that although the Authority had identified risks that could affect
the system’s cost and schedule—such as the lack of a finalized
agreement with Union Pacific—it was not promptly and effectively
addressing these risks.
A 2013 report by the U.S. Government Accountability Office (GAO)
expressed similar concerns about the Authority’s risk management,
specifically identifying that the Authority had not completed a
risk analysis to determine how the risks it had identified, such
as right-of-way delays, would affect cost estimates. For example,
according to the report, the Authority acknowledged the risk that
its acquisition of 100 of 400 properties it needed for construction
Project 1 would be delayed. However, the Authority did not include
the possible effect of this delay in its reported cost estimates. The
GAO consequently determined that the Authority only partially
met best practices intended to help ensure the credibility of its
cost estimates.
Although the Authority has acknowledged that beginning
construction when it did resulted in inaccurate cost estimates and
contributed to additional costs, it has not yet taken sufficiently
detailed steps to ensure a similar situation does not occur on future
segments. For example, the Authority’s director of design and
construction told us that the Authority planned to address these
planning issues at a high level in a new program management plan
that it was developing. We reviewed the program management
plan, published in October 2018, and confirmed that it discusses
the need to ensure land acquisition and utility relocations do
not adversely affect construction timelines. However, it does not
explain in detail about how the Authority will do so. Similarly, the
Authority’s recently released comprehensive schedule delineates
that these “early work” tasks should begin before the design and
construction phase on future segments, but the schedule does
3 California High-Speed Rail Authority Follow-Up: Although the Authority Addressed Some of Our Prior
Concerns, Its Funding Situation Has Become increasingly Risky and the Authority’s Weak Oversight
Persists, January 2012, Report 2011‑504.
California State Auditor Report 2018-108 31
November 2018
not establish specific benchmarks the Authority must achieve
before procuring a construction contractor—though we note
that the Authority does not plan to procure another construction
contractor until 2020.
When discussing the Authority’s future plans, its chief engineer
stated that the uncertain nature of the Authority’s funding makes
it continually reliant on the terms of available funding sources. The
chief engineer stated that if the Authority were to receive another
grant with short timeframes like those of the Recovery Act grant
agreement, it might have to reevaluate its plans. He further stated
that the decision to begin construction when the Authority did
was partially driven by a desire to show visible progress as various
groups were trying to stop the program, raising concerns that
future external pressures may drive the Authority to make similarly
poorly planned decisions again.
Although we acknowledge that the Authority must secure
additional funding to complete the high-speed rail system, we
disagree that it should accept similar levels of risk brought on by
beginning construction before it adequately performs planning.
Looking past the Central Valley, the next planned construction
segments, between San Francisco and Gilroy and then over the
Pacheco Pass between the South Bay and the Central Valley,
will present new challenges beyond what the Authority has
faced in the Central Valley, including performing construction
in dense urban areas and boring 15 miles of tunnels through the
mountains. It is therefore imperative that the Authority formalize
the lessons it indicates that it has learned in the Central Valley and
that it implement a process to incorporate those lessons into its
future planning.
To Complete Construction of Its Three Current Projects, the Authority
Believes It Will Need $1.6 Billion in Additional Change Orders and
Extended Project Timelines
Baseline estimates that the Authority and its oversight firms
provided to us in July 2018 indicate that the Authority will
need $1.6 billion in additional change orders to complete the
three current construction projects, for an anticipated total cost
of $4.7 billion. These changes include additional costs for ongoing
activities we discuss in the previous section, such as utility
relocation and land acquisition. The $4.7 billion total also includes
costs for new activities, such as construction of intrusion protection
barriers and efforts to mitigate problems with soil stability in
the Central Valley. According to the RDP consultants, who are
responsible for coordinating the Authority’s estimation process,
32 California State Auditor Report 2018-108
November 2018
the new baseline estimates represent a budget—and accompanying
timeline—that the Authority believes is achievable and realistic,
provided it takes appropriate actions as needed.
Because of these projected changes, the Authority will need to
extend its schedule significantly. As of June 2018, the Authority had
extended the contract completion dates for Project 1 from 2018
to 2019 and for Project 2/3 from 2019 to 2020. However, given the
work needed to complete the anticipated $1.6 billion in additional
change orders, the Authority’s new baseline schedule indicates
that it will need to extend the completion dates once again, with
the latest—for Project 2/3—in March 2022. If the work does
not progress as quickly as planned or if more changes become
necessary, the Authority will likely need to push completion dates
further into the future.
Additional delays to the three current construction projects pose
their own significant risks for the Authority, which must finish the
Central Valley construction by December 2022 to avoid violating its
federal grant agreements. The Authority received two federal grants
for the Central Valley segment, one under the Recovery Act for
$2.6 billion and a second for $929 million. Violating the grant
agreements could require the Authority to repay this $3.5 billion in
federal grant funds, $2.6 billion of which it reports it has now spent.
The Recovery Act grant agreement’s deadline has been extended once
before—from 2017 to 2022—at the Authority’s request. The Authority
has not indicated any plans to request a second extension or to
request an extension for its other grant, and it has no guarantee it
would receive such an extension if it asked. In a legal opinion, the
GAO concluded that the federal government could require the State
to repay all $2.6 billion of the Recovery Act funds if it determines the
Authority has violated the agreement, and it could recover the funds
by offsetting any other payments by the federal government to the
State. Consequently, the Authority’s 2018 business
plan listed meeting the December 2022 deadline as
Earned Value Analysis its first priority.
According to the Project Management Institute, earned
Meeting the federal deadlines for the Central
value analysis is a tool that allows entities to measure the
Valley projects will be challenging and will require
progress of projects and to forecast their total costs and
construction to occur significantly faster than it has
dates of completion.
in the past. Figure 8 illustrates how the Authority’s
Planned value: How far along the project work is supposed change orders have added more work and extended
to be at any given point in the project schedule and the construction schedule over time. The Authority
cost estimate.
uses a project management tool called earned
Earned value: Actual progress to date in terms of project value analysis, which is described in the text box.
schedule and cost. Figure 8, which is based on this tool, demonstrates
the Authority’s planned and actual progress on its
Source: Project Management Institute.
three projects. Change orders affect the planned
schedule (blue line) by increasing the amount of
California State Auditor Report 2018-108 33
November 2018
work, which is expressed in terms of cost and time. As a result, the
Authority’s actual progress (yellow line) needs to accelerate from its
historical average for the Authority to complete the three projects by
the federal deadline. As the green line that represents the required
rate to meet the December 2022 deadline demonstrates, finishing
the projects in time will require the Authority to work twice as fast
over the next four years as it has since it began construction in 2013.
If the Authority continues to work at its current rate, it will not
complete all anticipated work until 2027, as the red line in Figure 8
shows. Further, the federal grant requires the Authority to lay track
across the segment, a task for which the Authority has not yet
procured a contractor. It plans to lay the track concurrently with the
current construction projects beginning in 2020.
Figure 8
The Authority Must Double the Rate of Central Valley Construction to Meet the Federal Deadline
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Year
noitelpmoC
rof
deriuqeR
noitcurtsnoC
)snoilliB
ni
sralloD(
$5
4
3
2
1
0
2202
rebmeceD
enildaeD
tnarG
laredeF
Anticipated construction Anticipated total cost: $4.7 billion
change orders
REQUIRED
RATE
Executed construction
change orders
Original construction plan
CURRENT
RATE
PLAN
A
N
C
E
T
D
UAL
Jun
P
e
r
2
o
0
g
1
r
8
e
—
ss t
$
o
1 .
d
4
a
b
te
il
:
lion
Source: Analysis of the Authority’s estimates at completion, baseline schedules, construction contracts, monthly invoices, and monthly reports.
Note: This figure only presents information on Projects 1, 2/3, and 4, which cover project infrastructure between Madera and north of Bakersfield.
The Authority’s recently adopted schedule predicts that it can finish
on time, but only if it effectively monitors and mitigates risks. When
presenting the new schedule to its board, the Authority’s deputy
chief operating officer stated his belief that the Authority can
achieve the planned schedule, but he conceded that the approach
34 California State Auditor Report 2018-108
November 2018
is “very aggressive.” For the Authority to effectively mitigate future
problems and accelerate the rate of construction, it must have
accurate, realistic information on all the risks it faces. According to
the Authority’s chief engineer—who oversees risk management
for the system—the oversight firms play a significant role in the risk
management process. However, as we discuss in detail in the next
chapter, the Authority’s management of its contracts with the
oversight firms has been flawed. Further, when we asked about
certain information that the oversight firms had provided through
the risk management process, an RDP consultant responsible for
managing the schedule stated that the firms’ risk assessments
were sometimes potentially misleading. He attributed this issue
to the Authority not always closely or consistently monitoring the
oversight firms.
As the cost overages and delays As the cost overages and delays the Authority has experienced
the Authority has experienced in the in the Central Valley to date demonstrate, insufficient risk
Central Valley to date demonstrate, identification and management can have serious implications. If
insufficient risk identification the Authority allows deficiencies in its risk assessment process
and management can have to continue, it may not properly identify and respond to threats to
serious implications. the system’s development. This could in turn prevent the Authority
from meeting its December 2022 deadline.
The High-Speed Rail Project Might Benefit From the Establishment of
an Independent Oversight Committee
Our review identified several similarities between the high-speed
rail project and the California Department of Transportation’s
(Caltrans) Toll Bridge Seismic Retrofit Program (retrofit program),
another major transportation infrastructure project our office
has evaluated several times. Our past audits noted that the
retrofit program—which was tasked with retrofitting or replacing
state-owned toll and highway bridges—had experienced cost
overruns in part because of its management’s failure to perform
adequate risk management to quantify potential cost increases.
For example, our 2004 report on the retrofit program noted that
Caltrans had identified certain risks, but it had not quantified the
potential dollar costs until August 2004, when it reported soaring
cost estimates to the Legislature. Our current audit identified
similar problems with the Authority’s failure to effectively account
for preconstruction risks in its cost estimates, as we note earlier in
this chapter.
In response to these and other concerns with the retrofit program’s
costs and schedule, the Legislature required that Caltrans and
the Metropolitan Transportation Commission (MTC) create an
independent oversight committee to provide program direction,
review costs and schedules, and approve significant change orders,
California State Auditor Report 2018-108 35
November 2018
which the oversight committee deemed to be those over $1 million.
Our most recent audit report on the retrofit program, released
in August 2018, concluded that the oversight committee’s actions
had resulted in $866 million in cost avoidance and savings, as well
as the avoidance of seven years of potential delays. As a result,
the retrofit program was completed generally on budget. We
recommended in that report that the Legislature implement similar
oversight committees for other large transportation projects that
the State undertakes.
The Authority’s efforts to deliver the eventual rail system might The Authority’s efforts to deliver
benefit from similar additional oversight. That said, differences the eventual rail system might
between the Authority’s and retrofit program’s governance benefit from similar additional
structures make it unclear exactly what role a high-speed rail oversight as the retrofit program,
oversight committee would play and which specific public entities but it is unclear exactly what role a
should serve on it. Before the implementation of the retrofit project high‑speed rail oversight committee
oversight committee, Caltrans managed the program directly. would play and which specific
In contrast, the Authority’s board, which the Legislature and the public entities should serve on it.
Governor appoint, governs the Authority. In 2008 the Legislature
also required the Authority to create a peer review group composed
of experienced individuals appointed by the state treasurer, state
controller, director of finance, and secretary of transportation
to review and analyze the Authority’s planning, engineering,
and financing, and to report its findings to the Legislature. If the
Legislature appointed a high-speed rail oversight committee, it
would need to determine how that committee would work with
the board and peer review group, as well as which entities would
serve on the committee. Not all of the members that served on
the retrofit program’s oversight committee—the chief executives
of Caltrans, the MTC, and the California Transportation
Commission—would be appropriate for the high-speed rail project.
Of these entities, the California Transportation Commission could
potentially provide additional guidance based on its statewide
responsibility to manage transportation improvements. However,
Caltrans is a current contractor on the high-speed rail system,
which may limit its ability to provide objective oversight.
Nonetheless, the Authority’s history of cost overruns and delays
suggests that additional oversight may be warranted, especially
considering the impending federal deadline for the Central
Valley projects and the funding challenges the Authority faces
in completing the system. The Authority has previously set cost
estimates and timelines that its board allowed to be revised as
challenges arose; an independent oversight committee may be
better positioned to push back against changes to help maintain the
current schedule and budget in the Central Valley and beyond.
36 California State Auditor Report 2018-108
November 2018
Recommendations
To ensure that the change orders it approves are necessary and
that their costs are appropriate, the Authority should adhere
to the guidance and estimates the oversight firms provide to it.
If the Authority chooses to deviate from the oversight firms’
recommendations, it should clearly document why it made
those deviations.
Before executing its next construction contract, the Authority
should establish formal prerequisites for beginning construction to
prevent avoidable cost overruns and project delays. At a minimum,
these prerequisites should identify specific benchmarks related to
land acquisition, utility agreements and relocations, and agreements
with external stakeholders, including impacted local governments
and other railroad operators.
To better position itself to complete the three Central Valley
projects by the December 2022 federal grant deadline, the
Authority should improve its monitoring and evaluation of
the oversight firms’ risk assessment processes and should take
steps to ensure that these processes are consistent across the
three projects by May 2019.
To enable policymakers and the public to track the Authority’s
progress toward meeting the federal grant deadline of
December 2022, the Authority should, by January 2019, begin
providing quarterly updates to the Legislature detailing the progress
of the three Central Valley construction projects using an earned
value model that compares construction progress to the projected
total completion cost and date. The Authority should base these
updates on the most current estimates available.
To ensure that it is adequately prepared if it is unable to meet the
federal grant deadline of December 2022, the Authority should,
by May 2019, develop a contingency plan for responding to
such a scenario.
California State Auditor Report 2018-108 37
November 2018
Chapter 2
THE AUTHORITY HAS NOT SUCCESSFULLY ENFORCED THE
POLICIES IT ADOPTED TO ADDRESS ONGOING
DEFICIENCIES WITH ITS CONTRACT MANAGEMENT
Chapter Summary
Although the Authority recently adopted contract management
policies to help ensure that it monitors its contracts and controls
costs, it lacks an effective organizational structure to implement them.
Under its current structure, the Authority’s contract managers
experience high rates of turnover and receive little oversight.
Further, they generally serve as contract managers in addition
to their other professional responsibilities. Although the RDP
consultants assist in contract management, they may not always
have the State’s best interests as their primary motivation.
Likely in part as a result of these weaknesses in the Authority’s
contract management structure, we identified significant problems
in its management of its contracts. We reviewed a selection of
engineering and other service contracts to assess the Authority’s
compliance with its policies and procedures most directly relevant
to controlling costs and ensuring value: invoice review, deliverables
monitoring, and change management. We found that although
the contract managers complied to varying degrees with the
invoice review procedures, they consistently did not document
the receipt or evaluation of contractor deliverables, nor did they
independently evaluate the need for contract changes that added
cost and time. In fact, the contract managers’ lack of documented,
independent review prevented us from reaching conclusions about
the Authority’s effectiveness in assessing the quality, timeliness,
or cost of the work performed under these contracts. Without
such documentation, the Authority cannot demonstrate that
the hundreds of millions of dollars it has spent to date on the
selected contracts—including for cost overruns in the form of
amendments—has been necessary or appropriate.
Similarly, our review of the Authority’s construction contracts
found that it has implemented a construction invoicing process
capable of significantly limiting the risk that it overpays these
contractors for the work they perform. However, the Authority
has not provided reliable monitoring of the oversight firms that are
responsible for managing this invoicing process. Further, it has only
recently developed formal monitoring to evaluate the performance
of the oversight firms.
38 California State Auditor Report 2018-108
November 2018
The Authority Has Not Established an Effective Contract
Management Structure
As we discuss in the Introduction, the Authority adopted policies
related to contract management and oversight in April 2017.
However, these policies will only prove effective if Authority
staff follow them, and the Authority has yet to create a contract
management structure that adequately ensures such adherence.
Instead, its contract managers experience high turnover and
receive little oversight. Moreover, weaknesses in the Authority’s
contract management structure have contributed to its reliance on
contractors for important functions—such as contract oversight—
that state employees should perform.
The Authority’s Contract Managers Experience High Turnover and
Receive Little Oversight
The Authority’s contract managers’ official responsibilities do not
always specify contract management duties. As of September 2018,
the Authority’s 56 contract managers were collectively responsible
for 204 contracts with values totaling $5.6 billion. However,
according to the contract administration manager, only three of those
56 contract managers serve in contract management roles full-time.
Although records from the Contract Management Support Unit
(CMSU) show that each of the eight contract managers responsible
for the contracts we reviewed completed the Authority’s required
contract management training, our review of these individuals’ duty
statements found that only three specifically mentioned contract
management duties.4 Further, only one of the individuals mentioned
in this chapter carries the job title of contract manager. Although we
refer to them all as such for the purposes of their responsibilities,
their actual titles include administrator, engineer, and executive.
The former manager of CMSU acknowledged that the Authority has
not established a formal practice for selecting contract managers
and assigning them to contracts. Perhaps as a result of that fact,
the Authority frequently changes the individuals responsible for
managing each contract, resulting in high rates of turnover among
its contract managers. For the nine contracts we reviewed, CMSU’s
roster of contract managers shows that five contracts had two or
three different contract managers in the past year alone. In fact,
the contract managers for three of the contracts changed during the
period of our review from March through June 2018. High turnover
has not only likely contributed to noncompliance with policies, but
it also underscores the need for strong documentation practices.
4 One contract manager was responsible for two of the nine contracts we reviewed.
California State Auditor Report 2018-108 39
November 2018
For example, one new contract manager told us she received a
transfer form from the previous contract manager indicating that
all the required contract documentation was available and up to
date. However, she did not sign the form because much of the
documentation listed on the form was not actually available.
The responsibility for ensuring that contract managers perform
required tasks lies with their direct supervisors, who themselves are
not consistently trained in the Authority’s contract management
policies and procedures. Six supervisors managed the eight contract Six supervisors managed the
managers in our review, and half of them had not received training on eight contract managers in our
the Authority’s contract management policies and procedures at the review, and half of them had not
time of our review. If they do not understand the Authority’s specific received training on the Authority’s
requirements for contract management, supervisors may not be able contract management policies and
to intervene effectively when contract concerns arise or to provide procedures at the time of our review.
strong oversight to ensure contract managers adhere to policies
and procedures. Additionally, these supervisors also have full-time
responsibilities unrelated to contract management. In fact, some of
the supervisors are in executive leadership positions, including the
chief executive officer and the chief financial officer (CFO), each
of whom oversees multiple contract managers in addition to their
responsibilities for large segments of the Authority’s operations.
The Authority established CMSU within the Contract Administration
Branch in part to oversee compliance with contract management
policies and procedures, but its oversight has been weak and
inconsistent. The extent of its oversight activities to date has
been a fall 2017 review of whether contract managers had filed
documentation in the locations and structure that the Authority’s
policies and procedures required. Although this review consistently
found that contract managers had not filed required tracking logs
as expected, CMSU did not take any additional steps to determine
whether the contract managers were actually using those logs or
to verify compliance with any other policy requirements. If CMSU
had performed such additional reviews, it could have identified
some of the more significant compliance issues we discuss later in
this chapter.
In response to our concerns, the CFO asserted that the current set of
contract management policies and procedures took significant effort
to develop, as did developing and conducting the Authority’s contract
management training. However, he also acknowledged that the
Authority has not yet taken additional steps to ensure compliance.
Similarly, the director of the Contract Administration Branch
(contracts director) asserted that only a short time has elapsed since
the implementation of the Authority’s new contract management
policies and procedures and that the branch is relatively new. Given
that these policies and procedures have been in effect for over a year
and that the contract managers signed forms pledging to comply
40 California State Auditor Report 2018-108
November 2018
with them, we believe ample time has passed for the Authority to
have conducted meaningful oversight. The CFO informed us that
the Authority intended for CMSU to conduct contract manager
compliance assessments and submit the results of these assessments
to the contract managers’ supervisors, as the Authority’s policies
and procedures specify. However, he confirmed that CMSU has not
conducted these assessments and thus has not implemented the
process of notifying supervisors of any noncompliance.
The CFO further expressed his belief that timing and leadership
transitions have contributed to the Authority’s general challenges
in ensuring its staff comply with its contract management policies
and procedures. He stated that since adopting its contract
management policies and procedures in April 2017, the Authority
has directed its efforts toward creating two new executive
positions—the chief deputy director and the chief operating
officer—to oversee new offices that would more appropriately
include contract management. In October 2018, the Authority
adopted a project management plan that includes placing
contract management under the direction of these new executive
positions. However, the plan is not sufficiently detailed to address
shortcomings in the Authority’s current contract management
related to defining contract managers’ formal duties and ensuring
enforcement of those duties. We also do not agree that the
time spent rearranging the high-level organization of contract
management supplants the responsibility to simultaneously
strengthen the existing system. If the Authority believes, as we
do, that strong and accountable contract management is key to
controlling the system’s costs, it must commit to fully implementing
and enforcing its contract management policies and procedures.
Weaknesses in the Authority’s Contract Management Structure Have
Likely Contributed to Its Overreliance on Contractors
The Authority’s inadequate enforcement of its contract management
policies and procedures may encourage its reliance on contractors
to perform important functions, further hindering its ability to
control costs. As we noted in our 2012 audit report, the Authority’s
organizational structure places large portions of its program
planning, construction, and oversight in the hands of the RDP
consultants, who may not have the best interests of the State as their
primary motivation. Further, as we discuss in the Introduction, the
Authority’s internal audits concluded that roles and responsibilities
for contract managers and RDP consultants were not clearly defined.
To address this issue, the Authority’s contract management policies
and procedures clearly assign contract managers the responsibility
for tracking and monitoring all aspects of the contracts they manage.
Nonetheless, we observed that the contract managers for the
California State Auditor Report 2018-108 41
November 2018
regional planning contracts—which are for preliminary engineering Even though RDP consultants may
and environmental work in locations where the Authority plans not have the best interests of the
to develop the high-speed rail system—still often rely on the State as their primary motivation,
RDP consultants to provide the oversight for which the contract the contract managers for the
managers are ultimately responsible. In fact, during our review, the regional planning contracts still
Authority’s contract managers for the regional planning contracts often rely on the RDP consultants
directed our contract management questions to the RDP consultants to provide the oversight for
for answers and were generally unable to provide documentation which the contract managers are
related to contract management that did not originate from the ultimately responsible.
RDP consultants. As a result, the RDP consultants have become
the de facto contract management body, working closely with
contractors with insufficient Authority oversight.
Further, the Authority has also placed the oversight responsibility
for contract management with the RDP consultants, which creates
a potential conflict of interest. Specifically, although an Authority
employee heads CMSU, the RDP consultants fill its seven positions.
When the Authority’s contract managers inappropriately rely
on the RDP consultants to perform their contract management
responsibilities, it may not be reasonable to expect CMSU staff—
who are also RDP consultants—to tell state contract managers to
stop this practice. Consequentially, CMSU’s current composition
raises questions about the Authority’s ability to use the unit as a
tool to prevent the Authority’s continued overreliance on the RDP
consultants to perform contract management, which we believe
should be among CMSU’s priorities.
The Authority tasked contractors with duties that state employees
could have performed in other instances as well. For example,
the Authority’s documentation for its $40 million contract for
financial advisory services states that contracting for those services
is justified because the tasks are of a highly technical nature
and equivalent expertise is unavailable within state civil service.
However, in December 2016, the Authority’s former chief executive
officer (CEO) sent the CFO an email in which he expressed concern
over high spending rates for the contract, particularly in the areas
of accounting support and budgets. In his email, the CEO stated
that contract spending should focus on nontraditional areas of
work, such as financing analyses and commercial and real estate
strategies, and that employing state staff to perform basic budgeting
and accounting work would be more appropriate and cost-effective.
The CFO responded to the CEO’s concerns by stating that a core
group of state staff provided services for budgeting and accounting,
but that the financial advisory contractors were needed to help
perform responsibilities that had no precedent in state service,
including implementing information technology systems. The CFO
reiterated this position to us during our audit. However, our review
of the contract’s work plans and invoice materials determined
42 California State Auditor Report 2018-108
November 2018
that, although some of the contractor’s duties included information
Given the fact that the contractor technology tasks, many of the tasks it reported performing were
billed the Authority $3.5 million in described as support for general budgeting and accounting activities.
fiscal year 2016–17 and $1.1 million Given the fact that the contractor billed the Authority $3.5 million
in fiscal year 2017–18 for the in fiscal year 2016–17 and $1.1 million in fiscal year 2017–18 for
budgeting and accounting portions the budgeting and accounting portions of the contract, we believe the
of the contract, we believe the Authority should have taken steps to ensure and document that its
Authority should have taken steps use of contracted resources was necessary and prudent.
to ensure and document that its
use of contracted resources was The Authority also assigned work related to contract management
necessary and prudent. to outside contractors that may have been more appropriately
performed by state employees. For example, the Authority tasked
its financial advisory contractor to perform analysis and support
for its Contract Administration Branch from July 2016 through
June 2018. As part of this work, the contractor developed the
contract management policies we reviewed during this audit.
The CFO explained that these policies and procedures took
significant effort because no equivalent state criteria directly apply
to the Authority. However, we do not believe that the Authority is so
unique in its contract management needs that state resources could
not develop similarly adequate tools. Further, the Authority also
tasked the contractor with monitoring and reporting on the status
of the RDP consultants’ deliverables and with supporting CMSU
in its compliance reviews of the Authority’s contract managers. As
we discuss above, these compliance reviews have been insufficient.
We do not believe that any of these tasks are so highly technical or
specialized that state employees could not have performed them.
Nonetheless, the financial advisory contractor billed the Authority
almost $4 million for these tasks over two years.
Finally, just as the Authority staffed CMSU with RDP consultants
to oversee contract manager compliance, it also staffed its separate
administrative unit for supporting contracts entirely with RDP
consultants, who filled all 17 positions as of June 2018. We question why
using RDP consultants in place of state employees to perform contract
management oversight and support is necessary. The Authority agreed
that it should place state employees in these positions in the future.
The Authority Has Not Ensured That Its Contract Managers Actively
Manage Expenditures and Deliverables in Compliance With
Its Requirements
We found that the contract managers generally complied with the
Authority’s documentation requirements for reviewing invoices but
did not comply with the procedures for documenting timely and
thorough review of deliverables. Figure 9 illustrates that although
contract managers were often able to provide us documentation to
demonstrate their compliance with invoice requirements for using
California State Auditor Report 2018-108 43
November 2018
a tracking log and completing an invoice approval checklist, they
could not consistently demonstrate how they validated invoiced
costs to ensure they were appropriate and allowable. The contract
managers were also generally unable to demonstrate their review
of deliverables or their efforts to monitor contractor performance.
This lack of documented, independent review prevented us from
reaching conclusions about the quality, timeliness, or cost of work
performed under these contracts. Further, when we did identify
references to concerns with contractors’ work products, the lack of
documentation meant that we were generally unable to determine
how contract managers identified or resolved such issues. Without
clear documentation that its contract managers ensured deliverables
were consistent with requirements before approving payments or that
they appropriately monitored contractor performance, the Authority
cannot demonstrate that the hundreds of millions of dollars it has
spent to date on those contracts—including for cost overruns—has
been necessary and appropriate.
Figure 9
Contract Managers Failed to Consistently Document Completion of Tasks Necessary to Control Costs and Ensure Value
100
95%
80
60
38%
40
20
14%
4%
0
sreganaM
tcartnoC
yb
detnemucoD
sksaT
fo
egatnecreP
Task Required to Tasks Required to
Pay Contractors Control Costs and Ensure Value
Review Ensure Costs Evaluate Assess Performance
Invoices Are Allowable Deliverables and Amendments
Source: Analysis of the Authority’s available contract management documentation.
44 California State Auditor Report 2018-108
November 2018
The Contract Managers Could Not Consistently Demonstrate That They
Performed Thorough Reviews of Contractors’ Invoices
In order to assess the Authority’s compliance with its own policies
and procedures, we reviewed nine active contracts overseen by
eight contract managers. The contracts we reviewed include
planning, engineering, consulting, and construction oversight
services and have a total value of $1.3 billion.5 The services on
these contracts include a combination of discrete deliverables and
day-to-day work involving on-site staff support. Our review focused
on the Authority’s compliance with those contract management
policies and procedures most closely linked to controlling costs and
ensuring value, including invoice and deliverables review.
The Authority has established procedures requiring a systematic
approach to its contract managers’ receipt and handling of
invoices, appropriate invoice documentation and review, and
required approvals for timely processing of payments. For example,
Authority contract managers must ensure that contractors bill
hourly rates appropriately, that all direct costs are eligible and
supported with receipts, and that the totals of each invoice are
calculated correctly. In addition, the Authority’s procedures require
contract managers to complete an approval checklist for each
invoice for contracts with values greater than $5 million. These
checklists require contract managers to attest to the accuracy of
the invoices and the sufficiency of supporting documentation
by checking boxes stating that the invoices comply with relevant
contract provisions and that all expenses are eligible and supported
with receipts. The procedures also require contract managers to
keep logs that track invoiced and approved amounts, key dates,
and any disputed costs.
When we examined a selection of invoice approval checklists
for the nine contracts we reviewed, we found that the contract
managers completed checklists indicating that they evaluated
The contract managers for each invoice for accuracy. However, the contract managers for
only three of the nine contracts only three of the nine contracts could provide documentation
we reviewed could provide to support the checklists’ assertions that they ensured invoiced
documentation to support the rates and expenses were allowable. For example, one contract
checklists’ assertions that they manager provided us with a review spreadsheet in which, in
ensured invoiced rates and addition to monitoring monthly spending against the contract’s
expenses were allowable. value, he tabulated each individual billing rate, the hours reported
by task, and all direct expenses. The manager of the Contract
Administration Support Unit told us that contract managers can
5 We also reviewed the Authority’s oversight of its three construction contracts, which have a
combined current value of $3.1 billion. We discuss the management of these contracts in the
following sections of this report.
California State Auditor Report 2018-108 45
November 2018
request support from this unit to verify that contractors bill hours
against allowable rates, but only one of the contract managers in
our review used this resource.
We expected to see documentation from contract managers
verifying that costs were allowable and accurate because most
of the invoices we reviewed were complex; they included many
individual pay rates for contractor staff, tens or hundreds of
thousands of dollars in direct costs that the contract managers had
to verify, and many subcontractor costs. When it relies primarily
on the contract managers’ attestations on the invoice approval
checklists, the Authority risks that those contract managers may
not have performed thorough and comprehensive invoice reviews.
As a result, the Authority could pay for unauthorized costs. We An internal audit that the Authority
observed one such instance in which an internal audit that the issued in June 2017 identified that it
Authority issued in June 2017 identified that it had paid for more had paid for more than $1.2 million
than $1.2 million in questioned and disallowed costs to one of its in questioned and disallowed costs
contractors—costs that either were not supported by adequate to one of its contractors—costs that
documentation or were not in compliance with the contract terms either were not supported or were
or applicable rules and regulations. not in compliance with requirements.
Similarly, although the contract managers we reviewed consistently
used required invoice tracking logs, these logs had limited utility.
Specifically, the invoice tracking logs serve as a record of the
amounts that the contractors bill and the Authority approves
each month. When the contract managers enter approved invoice
amounts, the tracking logs automatically calculate the remaining
contract balance. Although they help ensure that the Authority
does not overspend the contract balance, the tracking logs do
not demonstrate detailed invoice review any more than the
invoice checklists. More importantly, none of the required invoice
documents demonstrate whether or how the contract managers
performed the critical task of determining that invoiced costs were
appropriate for the amount and quality of the contractors’ work.
The Authority Lacks Evidence Supporting the Quality, Timeliness, and
Cost of Contract Deliverables
Most of the managers for the contracts we reviewed asserted
that when they approved invoices, they reviewed narratives
summarizing the work performed. However, these narratives are
generated by the contractors and do not serve to independently
verify that the contractors have, in fact, performed the work
to the standards of the contracts. In establishing its 2017 policies,
the Authority acknowledged the limitations of this invoice review
process by creating a parallel but distinct process through which it
requires contract managers to identify, document, track, receive,
review, and accept contract deliverables.
46 California State Auditor Report 2018-108
November 2018
The Authority’s policies and procedures clearly
Requirements for Contract Managers’ Oversight state that this process—known as deliverables
of Deliverables:
management—is meant to ensure the Authority is
able to construct the high-speed rail system on
• Identify all deliverables, along with associated timelines.
schedule and within budget. The text box
• Define and document tasks, performance expectations,
describes the Authority’s procedural requirements
and timelines for contracts that do not identify
for managing deliverables and identifies the
specific deliverables.
documentation required to track that process.
• Organize the deliverables and all relevant information,
The fundamental purpose of these tracking
including objectives, due dates, responsible individuals,
activities is ensuring that the contractors’
estimated budget, and acceptance criteria, into a
deliverables are consistent with quality, timeliness,
deliverables tracking log.
and cost requirements.
• Review deliverables to ensure they meet all requirements
before formally accepting them as complete.
Despite the specificity of the Authority’s
• Document each complete deliverable by issuing an
requirements related to deliverables, the contract
acceptance notice to the contractor.
managers we reviewed did not comply with the
• Request a recovery plan, including an updated schedule
required actions. None of the contract managers
and budget, for late or unsatisfactory deliverables.
for the nine contracts we reviewed used the
• Track and escalate contractor performance issues if the
standardized deliverables tracking log—or
contractor continues to provide inadequate deliverables
any other document—to independently track
and is unable to meet its contractual obligations.
the status and review of contract deliverables.
Source: The Authority’s deliverables management procedures. Further, contract managers did not document
their formal reviews of deliverables; instead, they
described various alternative methods for these
reviews. Some contract managers claimed to
monitor contracted work simply by observing and working closely
with contracted staff on a daily basis. Others relied on the RDP
consultants to approve contractor-generated progress reports
and individual deliverables, after which the contract managers
would approve payment. Still others stated they relied on other
Authority staff and subject matter experts to evaluate and approve
individual deliverables, although those delegated evaluations were
also generally not documented. Though we recognize that subject
matter experts play an important role in assessing the quality of
work, their expertise does not supplant the responsibilities of the
contract managers.
Finally, instead of using the Authority’s required templates for
tracking the receipt and sufficiency of deliverables, contract
managers for four of the nine contracts we reviewed provided
documents that they use to verify the extent to which deliverables
were timely and adequately completed. However, we noted that
the contractors prepared these documents. In fact, for nearly all the
contracts we reviewed, the only documented source of information
regarding the timeliness and status of deliverables came from the
contractors themselves. As a result, we were generally unable to
determine how the Authority independently ensured it received the
deliverables for which it paid and that they were of the quality that
it required.
California State Auditor Report 2018-108 47
November 2018
The Authority Paid for Deliverables Without Performing Proper Review
Our review of nine contracts also found that the contract managers
rarely had documentation for their acceptance of deliverables.
In fact, the contract managers for seven of the nine contracts
did not have any acceptance notices on file. Authority policies
and procedures require contract managers to review deliverables
for compliance with contract requirements and the Authority’s
acceptance criteria. The contract managers must then officially
accept the deliverables in writing. This documented communication
marks the point in time when the Authority takes care, custody, and
control of the deliverable.
Despite this requirement, when we asked the contract manager for
an environmental contract about the missing acceptance notices, he
stated that the contract had only two real deliverables, one of which
is the environmental impact report. He stated that he planned
to evaluate that report upon its completion and that he would
issue the acceptance notice at that time. However, the contract
documentation makes clear that the contractor is responsible for
many individual work products as part of developing this larger
report. When we asked about these work products, the contract
manager stated that instead of reviewing deliverables as the
contractor submits them, he plans to later issue a memorandum
to summarize all deliverables. We received similar responses from
other contract managers, who stated that acceptance notices
were not applicable because the contracts they managed did not
include what they considered to be formal deliverables. However,
we disagree with this assertion; for each of these contracts, we
identified evidence of discrete work products—or deliverables—
that the Authority policies and procedures would require contract
managers to evaluate and formally accept.
In fact, only two of the nine contracts had acceptance notices Contrary to Authority policies
on file that documented the timing of deliverable submission and procedures, only two of the
and review, and this documentation was minimal and used nine contracts had acceptance
inconsistently. When we requested acceptance notices for one of notices on file that documented the
the two contracts—a four-year, $40 million contract for financial timing of deliverable submission and
advising services—the contract manager provided nine notices, review, and this documentation was
all of which he signed and dated June 11, 2018—after the date of minimal and used inconsistently.
our request on June 4. Further, none of the notices contained any
comments in the template fields that contract managers can use to
record the details of their reviews. When we subsequently followed
up to ask about additional deliverables for which the contract
manager had not provided acceptance notices, he produced another
three notices, each of which he signed on July 9, 2018—again,
after our request. In some instances, the contractor had submitted
the deliverables in question as early as October 2017. Because the
Authority pays the contractor for its work on a monthly basis,
48 California State Auditor Report 2018-108
November 2018
even if the contract manager had performed a detailed review in
June and July 2018 and had found issues with the deliverables, the
Authority had already long since paid the contractor for the work.
When we asked the contract manager about his signing the
nine notices on the same day, he asserted that the process was for
the contractor to submit the acceptance notices to him at the end
of the fiscal year, rather than with the deliverables. However, as
we state above, he provided the original set of acceptance notices
before the end of the fiscal year, and soon after we requested them.
Further, because the acceptance notices are a part of the Authority’s
policies and procedures, we would expect the contract manager
to initiate the process, not the contractor. When we expressed
concern about the contract manager’s approach, he replied that he
believed the process was sufficient because he would complete the
notices before the contract was closed. However, if the Authority
waits until the contract’s end to review deliverables, it will have
already substantially paid for these deliverables. When we asked
about any other evidence to demonstrate his review of deliverables,
the contract manager provided emails intended to demonstrate his
review. Our review of those emails found that the contract manager
was not included on many of them, some of which were between
contractors only. The contract manager told us that going forward,
he plans to complete an acceptance notice contemporaneously
with receipt of each deliverable. To the extent that the contract
manager also performs and documents his comprehensive review
of each deliverable at this time, we agree it is appropriate for him to
complete the process by signing and issuing acceptance notices.
We also identified significant concerns with the Authority’s
collection and evaluation of deliverables for its $666 million RDP
consulting contract, which includes tasks in 30 subject matter areas.
In late 2017, the contract manager tasked a contractor—from a firm
The Authority was missing formal other than the RDP consultants—with conducting an assessment
acceptance notices for 70 of of the deliverables and corresponding acceptance notices that the
the 80 deliverables and did not Authority had on file dating back to the start of the RDP contract in
have 145 of the 184 deliverables July 2015. To conduct this assessment, the contractor compared the
that the RDP consultants had RDP consultants’ self-reported information about the deliverables
reported as having completed it had submitted to the Authority to the deliverables the Authority
since the beginning of the contract actually had on file. The review determined that for the work
in July 2015. Nonetheless, from plans that were active when the Authority’s contract management
July 2015 through December 2017, the policies and procedures went into effect, the Authority was missing
Authority paid the RDP consultants formal acceptance notices for 70 of the 80 deliverables that the
over $200 million for the tasks that RDP consultants reported as complete. Further, the Authority did
included these deliverables. not have 145 of the 184 deliverables that the RDP consultants had
reported as having completed since the beginning of the contract.
These missing deliverables ranged from engineering documents to
software updates to white papers and other strategic documents.
California State Auditor Report 2018-108 49
November 2018
Nonetheless, from July 2015 through December 2017, the Authority
paid the RDP consultants over $200 million for the tasks that
included these deliverables.
When we asked about the Authority’s efforts to follow up on the
missing and unapproved deliverables, the contract manager told us
that because of funding constraints, the non-RDP contractor was
no longer working on the deliverables issue. However, he stated that
he had requested help from other Authority staff in identifying and
recovering the deliverables. Nonetheless, as of July 2018, he had
not yet received any new information. Without documentation of
formal review and approval, the Authority cannot demonstrate that
it received the quantity and quality of work for which it paid the
RDP consultants.
Moreover, the Authority’s tracking and evaluation of this contract’s
deliverables has continued to be an issue. In July 2018, the contract
manager provided us a list of deliverables that the RDP consultants
had reported submitting, which he originally represented as an
updated tracking log. However, the contract manager later stated
that because of the aforementioned funding constraints and a
lack of support staff, he had not had the opportunity to verify the
submission and timing of the deliverables on this list. He asserted
that subject matter experts, who are state employees, are involved
in developing the monthly status reports that the RDP consultants
submit to the Authority, which include the status of deliverables.
However, he acknowledged at the time that he had not reached
out to subject matter experts to collect the deliverables that the
RDP consultants had reported as complete and therefore had not
yet completed deliverable reviews in order to issue acceptance
notices. Despite having confirmed this lack of acceptance notices
on multiple occasions, the contract manager informed us in
October 2018 that he did in fact have completed acceptance notices
for some of the RDP consultants’ deliverables. He then provided
77 signed acceptance notices dated as far back as January 2018.
These acceptance notices do not alleviate the need for detailed Even though the contract manager
deliverable tracking and review documentation. The acceptance asserted that the acceptance
notices on their own do not allow the contract manager to notices are the formal deliverable
determine whether the RDP consultants’ work is generally on review documents, neither the
schedule. Along with the acceptance notices, the contract manager acceptance notices that he
also provided a log his staff began compiling in August 2018 to track provided nor the log contain detail
the status of deliverable acceptance. If used going forward, the log about how the contract manager
will help the contract manager more proactively track the status determined that deliverables met
of all deliverables. However, even though the contract manager contract requirements.
asserted that the acceptance notices are the formal deliverable
review documents, neither the acceptance notices that he provided
nor the log contain detail about how the contract manager
determined that deliverables met contract requirements.
50 California State Auditor Report 2018-108
November 2018
Given the large dollar amount associated with this contract, it is
crucial that the Authority improve its practices for tracking the
status of deliverables and reviewing them for quality.
Because of the Authority’s Failure to Track Deliverables, Determining
How It Resolved Quality Issues Is Difficult, If Not Impossible
The contract managers’ insufficient tracking of deliverables
also means that when the contract documentation alluded to
issues with contractors’ work products, we generally could not
determine how the Authority identified the issues or confirm that
they were resolved appropriately. When contractor deliverables
are unsatisfactory, a contract manager must not only identify the
unsatisfactory work, but also ensure the Authority does not pay
for the hours spent to fix it. For example, in September 2017, a
regional planning contractor in Southern California had to revise its
design for a train station access road because it adversely affected
a historical bridge. The Authority considered the hours spent
revising the design as repeated work for which it had already paid.
Although the contract documentation indicated that the Authority
contract manager formally disputed the invoice that included
charges for this work, it provided no further information. When we
Neither the contract manager nor asked for details about the dispute, the contract manager stated that
the RDP consultants documented the RDP consultants were responsible for identifying the issue and
how they ensured that they determining the total amount that the Authority should not pay.
accounted—and therefore avoided However, neither the contract manager nor the RDP consultants
paying—for the contractor’s documented how they ensured that they accounted—and therefore
repeated work. avoided paying—for the contractor’s repeated work.
In another example from January 2018, an RDP consultant
expressed concern to his RDP supervisor about the quality and
timeliness of a contractor’s deliverables for a Northern California
environmental planning project. When we asked how the issue
was resolved, the RDP consultant stated that he did not dispute the
related invoice because the contractor did not claim the deliverables
for payment because of their deficiencies. To demonstrate this, the
consultant provided an invoice from the contractor that showed
hours worked for which the contractor did not bill the Authority.
However, because of the lack of detail in the RDP consultant’s
tracking documentation and the fact that the contract manager
had no additional documentation, we could not substantiate that
the hours on the invoice accounted for all of the repeated work the
contractor performed.
Both of these examples also demonstrate the Authority’s
overreliance on the RDP consultants to provide oversight of
certain contracts. In the first example regarding the train station
access road, the available documentation about the origin of the
California State Auditor Report 2018-108 51
November 2018
issue was limited to communications among the RDP consultants,
and we identified no evidence that the contract manager took
steps to independently evaluate the situation. Similarly, in the
second example, the contract manager for the environmental
planning contract asserted that because his background is
engineering, he relies on the RDP consultants to recommend when
the Authority should dispute invoices for environmental work.
However, as of April 2018, the contract manager was still not aware
of the issues the RDP consultants discovered in January 2018.
Instead, the contract manager believed that the contractor had not
had to repeat work on the contract.
Despite these and other quality concerns, the contract manager
for only one of the nine contracts we reviewed requested that
a contractor submit a recovery plan—a document Authority
policy directs contract managers to request if deliverables have
fallen behind, do not meet contract requirements, or may require
repeated work. Specifically, the contract manager for the RDP
consulting contract requested a recovery plan in December 2017
for a single deliverable for the development of cost management
software. This deliverable had delays spanning multiple years.
The contract manager communicated his expectations for the
recovery plan in a formal letter to the RDP consultants, stating
that he expected the plan to include a schedule with detailed
implementation activities, a list of all remaining project scope
items and necessary resources, and a detailed mitigation
strategy should the RDP consultants miss any milestones. The
contract manager’s request was consistent with Authority contract
management policies and procedures. However, because this
example is the Authority’s only use of a recovery plan for any of the
nine contracts we reviewed, we are concerned that the Authority
may have missed other opportunities to address untimely or
unsatisfactory deliverables.
In fact, the RDP consultants missed deadlines for other deliverables
for this same contract, suggesting problems may exist that the
Authority has not actively tried to mitigate. The contract’s current Although the contract’s current work
work plan was originally scheduled to be eight months, with plan was originally scheduled with
the RDP consultants completing all deliverables by the end of the RDP consultants completing
February 2018. However, as of January 2018, the RDP consultants all deliverables by the end of
had reported submitting only 10 of 81 deliverables, despite February 2018, as of January 2018,
spending nearly $70 million of the work plan’s $90 million budget. the RDP consultants had reported
According to the contract manager, the Authority extended this submitting only 10 of 81 deliverables,
work plan twice, for a total of seven months, because the RDP despite spending nearly $70 million
consultants had not yet completed the deliverables. When it of the work plan’s $90 million budget.
extended the work plan, the Authority also assigned additional
deliverables and added funds to the work plan, now valued at
$157 million.
52 California State Auditor Report 2018-108
November 2018
Although the contract manager asserted that the Authority expects
the RDP consultants to complete outstanding deliverables with
no additional resources, the Authority added dollar amounts with
the extensions that do not appear proportional to the additional
deliverables it assigned. For example, the most recent extension
added nearly $30 million but just eight new deliverables. As of
October 2018, the RDP consultants reported to us that they had
submitted 101 of the 111 deliverables due by the work plan’s revised
September 30, 2018 deadline. However, as we explain in the
previous section, the contract manager provided acceptance notices
for only 77 deliverables and has only recently begun proactively
tracking the timeliness of the RDP consultants’ work. Overall, the
work plan’s shifting deadlines and large dollar increases make us
question why the Authority did not initiate the formal corrective
actions that its policies and procedures indicate it should.
Given the types of challenges Given the types of challenges some of the contracts we reviewed
some of the contracts we reviewed have presented, we found the lack of formal intervention by
have presented, we found the the Authority concerning. Most of the contract managers, and
lack of formal intervention by even the RDP consultants who identified the quality issues that
the Authority concerning. resulted in repeated work, insisted that there had been no need to
establish recovery plans. Moreover, we identified evidence of formal
invoice disputes for only two of the nine contracts we reviewed,
and the disputed items generally had to do with incorrect billing
rates or unsubstantiated costs for invoiced expenses, rather than
deliverable quality. Some of the other contract managers explained
the lack of formal intervention by asserting that when quality
issues arose, they resolved them informally with the contractors.
Although Authority policies allow for the informal resolution
of issues as an alternative to formal documented disputes, the
lack of documented deliverable review and tracking by contract
managers, along with the deliverable delays we discussed above,
creates the risk that the Authority is not detecting or resolving
issues with contractor performance. Further, without the contract
management documentation its policies and procedures require,
the Authority cannot demonstrate that the hundreds of millions of
dollars it has spent to date on these contracts—including for cost
overruns—has been necessary and appropriate.
Although the Authority Has Amended Many of Its Contracts, Contract
Managers Have Not Sufficiently Documented Attempts to Control
Costs or the Reasons for Overruns
The Authority frequently amends its contracts to add additional
time or funds. Of the nine contracts totaling more than $1.3 billion
in our review, the Authority used amendments to increase the value
of six by a total of $183 million and to extend the contract terms
for five of those six. In addition, it amended two other contracts to
California State Auditor Report 2018-108 53
November 2018
reduce their value by nearly $40 million when reassigning tasks and
funds to other contractors. Only one contract that we reviewed,
for financial advisory services, has no amendments. As Table 3
shows, the amendments increasing the contracts’ value represent
significant additional costs. These amendments more than doubled
the value of two contracts and increased the value of three others
by more than 40 percent. Amendments have thus unquestionably
contributed to the high-speed rail system’s cost overruns.
Table 3
The Authority Has Added Large Amendments to Many of the Contracts We Reviewed
TOTAL VALUE NUMBER OF ORIGINAL CURRENT TOTAL TIME ORIGINAL
CONTRACTOR/SERVICE
OF AMENDMENTS AMENDMENTS CONTRACT VALUE CONTRACT VALUE EXTENSION CONTRACT TERM
Caltrans January 2013–
$64,200,000 3 $225,900,000 $290,100,000 —
State Road 99 construction June 2020
Wong+Harris, Joint Venture May 2013–
35,500,000 3 34,209,000 69,709,000 12 months
Construction oversight firm December 2018
T.Y. Lin International
February 2014–
Bakersfield to Palmdale 26,558,000 3 46,100,000 72,658,000 24 months
January 2019
regional consultant*
Parsons Transportation Group
December 2008–
Central Valley Wye 25,640,000 6 55,000,000 80,640,000 63 months
June 2014
regional consultant*
Nossaman, LLP January 2009–
18,500,000 10 500,000 19,000,000 114 months
Legal services† June 2011
HNTB Corporation January 2016–
12,800,000 1 30,064,000 42,864,000 1 month
Construction oversight firm* November 2020
KPMG, LLP June 2016–
— 0 40,000,000 40,000,000 —
Financial advisors June 2020
WSP USA, Inc. July 2015–
(33,630,000) 3 700,000,000 666,370,000 —
RDP consultant‡ June 2022
Arcadis US, Inc. November 2014–
(6,000,000) 1 71,885,000 65,885,000 —
Construction oversight firm‡ April 2019
Totals $143,568,000 30 $1,203,658,000 $1,347,226,000
Source: Authority’s contracts and contract amendments.
* The board recently approved amendments for these three contracts; although the amendments have not yet been officially executed, they are
included in this table.
† State law requires that the Authority, as a state agency, obtain written consent of the attorney general before contracting with outside counsel.
The contract manager explained that the attorney general typically gives approval for outside counsel in two‑year increments, which has
necessitated regular contract amendments for legal services.
‡ Two of these contracts received amendments that decreased their original values. The Authority moved $6 million from the Arcadis US, Inc. contract
into an increase for the Wong+Harris, Joint Venture contract. The Authority removed $33.6 million from the WSP USA, Inc. contract as a result of
removing certain tasks from the contract’s scope of work.
54 California State Auditor Report 2018-108
November 2018
The Authority designed its contract management policies and
procedures, as well as its associated tracking requirements, to
ensure that it identifies the need for changes in a timely manner
and that it appropriately ensures those changes’ justification before
adopting them as amendments. For example, when an involved
party identifies a potential need for a change, such as a change in
the scope of the contract or in required deliverables, the policies
and procedures require the contract manager to include the
change in the change tracking log; document who identified the
need for it; describe the issue or potential change; and identify its
proposed cost, its impact to the contract schedule, and the relevant
dates in the process. The policies and procedures also require the
contract manager to assess the potential change for merit and
discuss this determination with an appropriate supervisor for
approval. The Authority may also provide amendment details in
a staff report to the board, which during the period of our review
had to approve any amendments to existing engineering and
architectural contracts with values that exceed $5 million. The
Authority presented all of the proposed amendments we reviewed
to the board.
Despite these requirements, the contract managers for the contracts
we reviewed could not consistently provide documentation
demonstrating the Authority’s independent evaluations of potential
amendments. Since April 2017, when the Authority established its
new policies and procedures, it has approved 13 amendments for
We reviewed three amendments, eight of the nine contracts in our review. We reviewed three of
each for a different contract, and these amendments, each for a different contract. However,
found that none of the contract when we tried to identify the details related to the amendments’
managers had maintained change necessity and size, we found that none of the contract managers
tracking logs, despite a requirement had maintained change tracking logs. Further, when we asked for
to do so. supporting documents with the information we expected to find
in the tracking logs, the contract managers frequently provided
the documentation that Authority staff had used to present the
recommended amendments to the board. When we requested
documentation showing how the Authority determined these
three amendments had merit as the board materials attested,
contract managers for two of the contracts had to request this
documentation from the RDP consultants or from the contractors
themselves. The Authority documented its analysis of the
third amendment we reviewed, but that analysis was incomplete.
An example involving a $3 million amendment with a one-year
extension demonstrates why relying on contractor-provided
evidence is problematic. When we asked about this amendment,
the contract manager first provided us with the formal high-level
amendment request that the former contract manager signed.
According to Authority procedures, a contract manager should sign
this form only after determining that the proposed amendment has
California State Auditor Report 2018-108 55
November 2018
merit. The contract manager also provided the staff report that the
Authority presented to the board when the board considered the
amendment. The staff report asserted that a number of unforeseen
changes had impacted the scope, budget, and overall schedule of
the contract’s work, precipitating the need for the amendment.
When we asked for evidence supporting the claims that the board
documents made regarding the amendment’s merit, the current
contract manager provided additional documentation that
the Authority received from an RDP consultant working with the
contractor. This documentation showed that the contractor was
the source of information regarding the amendment’s necessity and
accompanying costs, and it included no evidence that the Authority
independently verified the contractor’s claims. In fact, the content
in the Authority’s report to the board came directly from the
contractor’s amendment request. When it does not independently
verify and document the need for contract amendments, the
Authority risks authorizing additional funds for unnecessary or
unwarranted changes.
Contract managers were also unable to demonstrate if and how Contract managers were also
they independently determined that the approved amendment unable to demonstrate if and how
costs were appropriate and justified. When we reviewed another they independently determined that
amendment, we found that the contract manager had originally the approved amendment costs
drafted an amendment request for $26.7 million based on the were appropriate and justified.
contractor’s estimates for the cost of land acquisitions and utility
relocations. The contractor later determined that it required an
additional $2.5 million, causing the contract manager to increase
this amendment proposal to $29.2 million, which the board
ultimately approved. When we questioned how the Authority had
evaluated the need to add the $2.5 million or the appropriateness
of the $29.2 million total cost, the contract manager stated that
the contractor had increased the amount of additional funds it
claimed to need after further consideration and analysis. However,
the contract manager was unable to provide documentation
showing the Authority had independently determined the accuracy
of the amendment’s costs either before or after the contractor
increased them.
For the third amendment we reviewed, the Authority documented
a justification for why it required the amendment, but its analysis
was incomplete. Specifically, when one of the oversight firms that
manage the Authority’s construction contracts was projected to
deplete its contract funds nine months ahead of schedule, Authority
staff requested that the board approve a third amendment for
$28.5 million to retain the oversight firm’s services for an additional
year. The amendment documents the Authority presented to
the board indicate that the Authority considered seeking a new
vendor to replace the oversight firm, but it decided to recommend
the amendment instead. The Authority’s documents assert that the
56 California State Auditor Report 2018-108
November 2018
need for the amendment stemmed from its assigning work to
the oversight firm that was outside of the original contract because
of changes to the construction contract. However, the contract
manager could not tell us how much money went to the oversight
firm for performing out-of-scope work and acknowledged that he
had not documented the oversight firm’s adequate performance,
as we discuss in more detail later. The board expressed concerns
about substantial cost increases, stating that the Authority
generally had some issues in the past with oversight of construction
management, and it directed Authority staff to return in 90 days to
update it on the oversight firm’s progress in fulfilling the objectives
of the contract. However, it also unanimously approved the
amendment. When staff reported back, they presented the board
with a template they planned to use to evaluate the three oversight
firms’ performance in the future.
Our analysis of the amendment documents indicates that future
cost overruns may be likely for this contract. In the documents,
Authority staff calculated that retaining the existing oversight firm
was more cost-effective because of its familiarity and experience
with the project. In reaching this conclusion, the staff compared
the amendment amount to what they indicated was the remaining
value of the work still to be completed for the corresponding
construction contract. However, when making this comparison,
the Authority failed to account for a significant amount of expected
future construction costs. The amendment documents, dated
March 2018, projected that $545 million of additional construction
work would remain as of July 2018. However, a status report from
July 2018 shows $676 million remaining, for a total contract value
of $1.5 billion. Further, cost projections from December 2017,
three months before the amendment discussion, indicated that the
construction contract would ultimately cost more than $2 billion
due to expected changes. The Authority’s failure to account for this
expected work suggests that it may need additional amendments
for the oversight firm’s contract in the future. If the Authority
continues to account for expected construction cost increases
only after those increases take effect, it must develop a process for
tracking the actual impacts of those increases on its oversight firms
to ensure their spending is reasonable and to reduce the likelihood
that the contracts run out of funds prematurely.
Although the Authority’s Construction Contracts Include Potentially
Effective Methods for Verifying Progress and Costs, Those Methods
Require Improved Oversight
The Authority has separate management structures to oversee its
three active construction projects. As we discuss in Chapter 1, the
Authority has assigned an oversight firm to manage—under its
California State Auditor Report 2018-108 57
November 2018
direction—each of the three current construction contracts. In
addition, the Authority has assigned a contract manager to be its
authorized representative for each construction contract and to also
manage the pertinent oversight firm’s contract. Because managing
its construction contracts is distinctly different than managing its
other contracts in terms of how it measures and pays for work,
the Authority has developed requirements specific to this process.
Specifically, the Authority’s policy requires oversight firms
to provide primary, day-to-day oversight of the construction
contractors’ progress in meeting contract requirements.
Because the current construction contracts include provisions
that require the contractors to base their invoices on their
progress instead of on the costs they incur, the total amount each
construction contractor can earn is the total value of the contract—
inclusive of contract increases due to change orders—regardless of
the contractor’s actual costs to perform the work. The Authority
tasks the oversight firms with evaluating and verifying the
construction contractors’ claimed progress as part of reviewing
the contractors’ monthly invoices. When an oversight firm has
verified a construction contractor’s progress, it communicates
that fact to the Authority’s contract manager, who then approves
payment based on the agreed-upon value of the work as identified
in the invoice materials.
The Authority’s construction invoicing approach has the potential The Authority’s construction
to significantly limit the risk of it overpaying the construction invoicing approach has the
contractors, but the extent to which the Authority can rely on it potential to significantly limit the
as a cost control tool depends on how well the Authority oversees risk of it overpaying the construction
the work of the oversight firms. When we reviewed the invoicing contractors but depends on how
processes for the three construction contracts, we determined that well the Authority oversees the work
the invoicing documents contained the required documentation of the oversight firms.
to allow the oversight firms to evaluate construction progress.
However, as a matter of practice, the Authority’s contract managers
stated that they rely on formal review and approval from the
oversight firms without reviewing additional information to
independently verify the accuracy of the invoices. Determining
whether the oversight firms have effectively performed their roles
would require the Authority to actively monitor the oversight firms
and to document that monitoring. However, the contract managers
are only now beginning to institute this type of active monitoring.
In early 2018, in response to board concerns, the contract managers
for the three oversight firms developed a performance evaluation
template for the oversight firms, as we discuss above. Authority
staff presented the preliminary performance evaluation template to
the board in June 2018, but this presentation did not include actual
evaluation data. Instead, the contract managers stated that they
expected to conduct formal evaluations using the template on a
quarterly basis moving forward.
58 California State Auditor Report 2018-108
November 2018
The Authority has not yet established any formal methodology
or procedures for using the performance evaluation template. For
example, the template asks contract managers to rank the oversight
firms’ performances on a scale from one (poor) to five (excellent)
across a range of categories, but it does not make clear how contract
managers are to determine the scores. The fact that three contract
managers will use the template while monitoring different oversight
firms creates the risk that their evaluations will be inconsistent.
Although the contract managers have discussed setting specific
criteria for determining how they will assign values, they have not
yet done so. Further, the contracts director acknowledged that
Because the Authority’s oversight as of September 2018, the Authority is still evaluating the initial
structure for construction contracts methodology and that it plans to monitor monthly trends shown
relies heavily on the oversight through the reports. Because the Authority’s oversight structure
firms, it is crucial that the Authority for construction contracts relies heavily on the oversight firms,
provide a clear methodology it is crucial that the Authority provide a clear methodology for
for consistently evaluating the consistently evaluating the oversight firms’ performance.
oversight firms’ performance.
The Authority’s construction contract management structure also
does not mitigate the risks of cost overruns by the oversight firms.
In fact, two of the three oversight firms expended their funds ahead
of schedule and needed substantial contract amendments to continue
performing their oversight duties. When we asked the pertinent
contract managers about the reasons for these cost overruns, they
referred to changes that the Authority had made to the construction
contracts that the firms oversee. These change orders, which we discuss
in Chapter 1, added significant costs and time to the construction
contracts and thus—according to the contract managers—caused
significant additional work and expense for the oversight firms.
However, the Authority did not amend the oversight firms’ scopes of
work and funding contemporaneously with these changes. Rather, as
we discuss in the previous section, the Authority amended one of the
oversight firms’ contracts to add $28.5 million when it was projected to
deplete its contract funds nine months ahead of schedule.
Recommendations
To improve its contract management, increase accountability, and
justify the significant amount it pays for contracted services, the
Authority should take the following steps by May 2019:
• Prioritize contract management efforts and reduce the frequency
with which contract management responsibilities shift among
Authority staff by establishing a formal process for hiring and
assigning full-time, experienced contract managers. These
contract managers should have duty statements reflecting
their contract oversight responsibilities, and they should report
to supervisors who understand those responsibilities and
California State Auditor Report 2018-108 59
November 2018
have extensive knowledge about the contracts’ deliverables.
In addition, those supervisors’ duty statements should clearly
lay out their responsibility for addressing any contract manager
noncompliance with the Authority’s contract management policies
and procedures, whether reported by CMSU or identified by
another means.
• Require CMSU to establish a schedule to monitor individual
contract manager compliance and report annually the results of
this monitoring to Authority executive leadership. To help ensure
the integrity of its oversight role, CMSU should be composed of
state staff in place of RDP consultants.
• Hold contract managers accountable for performing the duties
that the Authority’s policies assign to them. Specifically, CMSU
and, to the extent necessary, contract managers’ supervisors
should require and review evidence from contract managers
demonstrating their approval of deliverables, detection and
resolution of contractor performance issues, and assessment
of contract amendments for merit. The Authority should not
accept observations and reports from its contractors or the RDP
consultants in place of this evidence.
To prevent the inappropriate use of contractors to perform state
functions, the Authority should develop procedures by May 2019 for
evaluating whether new and existing administrative duties should be
assigned to contractors or to state employees.
To ensure that contract managers’ invoice reviews are complete and
that invoiced costs are allowable under contract terms, the Authority
should amend its applicable procedures by May 2019 to require contract
managers to document their review of invoiced rates and expenses.
To ensure the consistency and effectiveness of its efforts to monitor
the performance of the oversight firms with which it contracts, the
Authority should develop a formal methodology by May 2019 for using
the performance evaluation tool it has implemented. This methodology
should include procedures for assessing the sufficiency of the oversight
firms’ review and approval of invoices for construction contracts.
To ensure that the oversight firms’ spending is reasonable, the
Authority should develop a formal process by May 2019 for tracking
any out-of-scope work that the oversight firms perform. To reduce the
likelihood that its contracts with the oversight firms run out of funds
prematurely as a result of this additional work, the Authority should
also develop a formal process for amending the oversight firms’
contracts contemporaneously to change orders that significantly
extend the timelines or increase the scope of work of the construction
contracts that oversight firms oversee.
60 California State Auditor Report 2018-108
November 2018
California State Auditor Report 2018-108 61
November 2018
Chapter 3
THE AUTHORITY CAN IMPROVE THE QUALITY AND
TRANSPARENCY OF ITS MONITORING AND REPORTING
FOR KEY GOALS
Chapter Summary
As one of the most expensive transportation projects in the
United States, the construction of the high-speed rail system
has significant implications for the State’s environment, its small
and disadvantaged businesses, and its economy. However, we
identified several ways that the Authority can better measure and
report on these impacts. The Authority’s sustainability policy has
relevant goals to limit the negative environmental impacts of the
high-speed rail system, but it does not sufficiently focus on the
environmental impacts of construction activities. Additionally,
the Authority has not collected complete and accurate data on the
environmental impact of its construction activities, and thus far
it has not comprehensively measured construction impact trends
and set targets for future construction. The Authority reports
consistently on its contracting with small, disabled veteran, and
disadvantaged businesses, having set goals for the percentage of
its total expenditures that will go to those businesses. However,
its reporting could be more complete and transparent, as that
reporting has omitted $930 million in contracts. In contrast,
although the Authority faces some limitations that may affect the
precision with which it estimates the overall economic impact of its
activities in the Central Valley and elsewhere, it has appropriately
disclosed these limitations as part of its reporting.
The Authority Can Better Account for the Environmental Impact of the
System’s Construction by Strengthening Its Sustainability Policy,
Monitoring, and Measurement
According to its sustainability policy, the Authority intends
its approach to the design, construction, and operation of the
high-speed rail system to contribute to a more sustainable
California. The policy also states the Authority’s commitment to
employing leading edge construction methods to make the project
a model for future rail infrastructure. Described by the Authority
as “all-encompassing,” the sustainability policy is supposed to
guide the system’s energy and natural resource use, impact on local
communities, construction practices, and operations. State and
federal commitments mandate certain aspects of the Authority’s
focus. For example, Proposition 1A—which provided funding
for the high-speed rail system—requires the Authority to plan
62 California State Auditor Report 2018-108
November 2018
and construct the system in a manner that minimizes the impact
on the natural environment. Further, in a 2010 memorandum
of understanding with the federal government, the Authority
pledged to be environmentally conscious throughout the design,
construction, and operation of the system. Other aspects of the
Authority’s sustainability policy, such as encouraging transit
development in local communities, are compatible with legislative
priorities for sustainable transportation planning.
Although the Authority’s sustainability policy includes goals
consistent with best practices, it also has shortcomings that limit
its effectiveness. According to the expert we retained to assist us
in assessing the sustainability policy, it includes valuable objectives
that generally align with established best practices. However, our
expert found the policy does not sufficiently distinguish between
construction of the system—which has a significant impact on
the State’s environment—and its eventual operation. Some of the
policy’s priorities, such as reducing car and other vehicle travel,
clearly focus on the effects of system operations and have no
direct construction implications. However, the Authority has not
identified construction-related objectives for all of its priorities
even though the priorities themselves have relevance during
the construction stage. For example, although the policy lists
conservation of nonrenewable energy as a priority, the related
objectives pertain only to the system’s operations. Our expert
noted that best practices concerning this priority, including those
from the Global Reporting Initiative—with whose standards the
Authority claims compliance—require a project to consider
the total amount of energy used during construction.6
Our expert observed that because the policy does not consistently
and explicitly address the impacts caused by the construction phase
of the system, the Authority’s implementation plan—which details
how it will assess compliance with the policy—is not always specific
about what the Authority should measure during construction
in order to determine success. Further, the implementation plan
The Authority’s implementation does not include measurable, process-focused metrics related to
plan does not include measurable, construction for many of the objectives. For example, the plan states
process‑focused metrics related that the Authority will monitor the degree to which the system’s
to construction for many of the eventual operation improves air quality by tracking the number
objectives in its sustainability of emergency room visits for asthma sufferers; however, the plan
policy; this lack of actionable does not include a metric to measure the degree to which the
detail makes ensuring the system’s construction affects current air quality. Our expert concluded that
current and future compliance with this lack of actionable detail makes ensuring the system’s current
the policy’s goals challenging. and future compliance with the policy’s goals challenging.
6 The Global Reporting Initiative is an international organization that develops sustainability
standards that many of the world’s largest corporations use.
California State Auditor Report 2018-108 63
November 2018
Because construction is significantly underway in the
Central Valley, we asked our sustainability expert to review
best practices for monitoring sustainable construction and
compare those practices to the Authority’s plans and actions.
After reviewing 13 comparable infrastructure projects as well
as guidelines published by the American Public Transportation
Association, our expert determined that current industry standards
call for organizations to estimate the material impacts resulting
from construction before beginning projects. Organizations should
then establish specific goals and—once construction has begun—
measure actual progress against those goals to determine where
they have been successful.
The Authority has set initial estimates for some construction
impacts, but it has not comprehensively measured actual progress
against those estimates. Before beginning construction on the
system, the Authority estimated the level of greenhouse gases
and other pollutants that construction activities would emit.
Our expert reviewed the Authority’s calculations and found them
to be reasonable and in line with guidance from the California
Air Resources Board. Further, the Authority required each of its
construction contractors to submit estimates of impacts, such as
greenhouse gas emissions, within sixty days of receiving approval
to begin work. Relying on contractors to determine these estimates
presents a risk that they may overestimate emissions, but our expert
concluded that doing so is a standard industry practice.
Although it properly completed initial estimates, the Authority Although it properly completed
did not ensure the accuracy of subsequently collected sustainability initial estimates, the Authority
data. The Authority relies on each of its construction contractors did not ensure the accuracy
to self-report information on their sustainability performance— of subsequently collected
such as their usage of heavy equipment and water—into a central sustainability data, which could
database. The oversight firms for the three current construction limit the Authority’s ability
projects then review these submissions and pass them on to to reliably compare actual
the Authority’s sustainability unit, which RDP consultants lead performance against estimates.
and almost completely staff. Despite these protocols, when we
attempted to validate a selection of nine database entries against
supporting documentation, we found that the Authority could
provide sufficient supporting documentation for only three entries.
We therefore were unable to determine the accuracy of the
Authority’s data. An inability to ensure accurate data could limit
the Authority’s ability to reliably compare actual performance
against estimates.
Further, our expert found that the Authority has not comprehensively
evaluated the sustainability performance of the currently active
construction projects. Neglecting to monitor all pertinent aspects
of performance continuously throughout construction could result
in the individual construction projects falling short of their goals;
64 California State Auditor Report 2018-108
November 2018
if it reviews progress only after it completes a specific project,
the Authority will have missed any opportunity to intervene in
order to improve sustainability outcomes. The Authority provided
documentation showing that it is tracking two environmental
impacts, greenhouse gas emissions and other air pollutants,
against benchmark estimates. However, that documentation did
not include equivalent comparisons related to the environmental
impact of waste produced from construction, despite the fact that
each construction contractor provided a benchmark estimate for
waste. In addition, our expert observed that the documentation
the Authority provided also does not allow it to effectively project
whether contractors will meet or exceed their estimates because it
does not account for actual construction progress to date. Finally,
we noted that the current construction contracts do not require
contractors to estimate the environmental impact of water usage
for the project, and as a result, construction contractors did not
provide benchmark estimates for water use.
Evaluating the sustainability impact of the system’s construction on
an ongoing basis is also critical because it will enable the Authority
to set standards for future construction. The Authority has not
yet developed a systemwide baseline or identified a universal
metric against which to anchor future construction projects,
which may differ in scope and type from current projects. For
example, the Authority’s plans for completing the system call for
significant tunneling, which it has not yet attempted. Although its
sustainability report from 2016 stated that the Authority planned
to adopt 2015 as its baseline year, the Authority has not moved
forward with this plan. Therefore, it is not yet prepared to hold
future construction contractors to a baseline it has established
using current construction activities. The Authority’s sustainability
director told us that her team is in the process of using recently
completed systemwide construction plans and current construction
data to develop a metric that will allow the Authority to set
standards for future projects. She stated that the Authority plans
to complete this process before it enters into any additional
construction contracts, but that the process is complex and will
be challenging.
Although the Authority Reports Regularly on Its Utilization of Small,
Disabled Veteran, and Disadvantaged Businesses, It Excludes
$930 Million in Contracts From Its Reporting
State law, regulations, and policy, as well as federal regulations,
mandate that the Authority report on its contracting activity with
small businesses, disabled veteran owned businesses, and
disadvantaged businesses. In particular, executive orders require
certain state agencies, including the Authority, to establish
California State Auditor Report 2018-108 65
November 2018
processes to meet a small business participation
goal of 25 percent and a Disabled Veteran Business The Authority’s Small Business
Program Categories
Enterprises (DVBE) participation goal of 3 percent.
Additionally, as a condition of receiving federal
Small Business: State law defines small businesses as
financial assistance from the Federal Railroad
independently owned and operated businesses that
Administration, the Authority must report on its
are located in California and whose officers also live in
actual use of Disadvantaged Business Enterprises California. Small business must have 100 or fewer employees
(DBEs), with a goal of 10 percent utilization. The and average annual gross receipts of $10 million or less.
Authority has established its own small and Of these small businesses, a business is a microbusiness if
disadvantaged business enterprise program (small it has 25 or fewer employees and average gross receipts of
business program) that, as the text box describes, $2.5 million or less.
includes small and microbusinesses, as well as
Disabled Veteran Business Enterprise (DVBE): State
DVBE and DBE firms. The Authority established an regulations define DVBEs as businesses that are at least
overall 30 percent participation goal for its small 51 percent owned and controlled by one or more
business program participants, inclusive of the disabled veterans who live in California.
10 percent DBE goal and 3 percent DVBE goals.
Disadvantaged Business Enterprise (DBE): Federal
regulations define DBEs as for‑profit, small businesses
To determine the extent to which the Authority
that are at least 51 percent owned and controlled by
contracts with these types of businesses, we one or more individuals who are both socially and
reviewed the small business utilization reports economically disadvantaged.
(utilization reports) that the Authority posts
Source: California Government Code section 14837(d);
on its website and provides to the Federal California Code of Regulations, title 2, section 1896.81; and
Railroad Administration. These reports include Federal Code of Regulations title 49, section 26.5.
the Authority’s actual utilization rates for 37 of
its professional services contracts as well as its
three construction contracts, with a total contract
value for all 40 contracts of just over $4 billion. When we reviewed
10 of these contracts, we found that the documentation the Authority
had collected from contractors sufficiently supported the utilization
that the contractors reported. The documentation also supported
the utilization percentages that the Authority reported for the
six of these contracts that were active at the time of our review. In
its most recent report, which it issued in June 2018, the Authority
reported a nearly 30 percent actual utilization rate—inclusive of
small businesses, DVBE firms, DBE firms, and microbusinesses—
for its professional service contracts and a utilization rate of almost
16 percent for its construction contracts.
Although both state and federal programs require reporting, neither
of their reporting formats fully capture the extent of the Authority’s
contracting activities with relevant businesses. For example, in its
role administering the State’s small business and DVBE programs,
the Department of General Services (DGS) instructs state
departments to exclude contracts with federal and state entities,
as well as contracts with any counties or cities. Furthermore, DGS
requires reporting only on the dollar amounts awarded to small
businesses and DVBE firms, rather than actual expenditures; thus,
its reporting requirements do not provide the Authority’s actual
impact on these businesses. In contrast, the federal Department of
66 California State Auditor Report 2018-108
November 2018
Transportation and the Federal Railroad Administration instruct
the Authority to report on commitments, awards, and payments
to DBE firms for federally funded contracts. According to the
Authority’s contract compliance administrator, its quarterly
utilization reports list active contracts that are at least partially
paid for with federal funding and that are subject to small business
utilization goals. However, the utilization report does not include
federally funded contracts for highly specialized services, such as
expert witness services, for which the Authority has asserted it
cannot find small business contractors.
We reviewed the Authority’s utilization report and found that it
As of January 2018, two‑thirds of excluded $930 million of the Authority’s contracts. As of January 2018,
the contracts that the Authority two-thirds of the contracts that the Authority excluded were with
excluded in its utilization report public entities, such as California cities and counties. These contracts
were with public entities, which represent $627 million in contract value and $326 million in actual
represent $627 million in contract expenditures. The utilization report also excludes $303 million of
value and $326 million in contract value for services from private entities. Given the limitations
actual expenditures. and exclusions inherent in each reporting format, the Authority does
not currently release a report that includes its total small business
program utilization out of its total contracting dollars.
Because the Authority does not mention that it exempts contracts
with public entities on its reports—including its quarterly utilization
reports, business plans, and economic impact reports—we asked the
Authority about its reasons for not reporting on these contracts.
The Authority’s recently appointed chief administrative officer
explained that its contracts with public entities and utilities generally
do not contain small business provisions primarily because they
are not the result of a competitive bidding process. Instead, the
Authority enters into contracts with these entities because of specific
program needs that only the public entities or utilities can serve.
An example is contracting with a city or a county for permitting
activities in its jurisdiction. In such instances, the Authority has no
bargaining power to compel the public entities to participate in its
business utilization program. The chief administrative officer also
stated that DGS specifically instructs state entities not to include
these types of contracts in their small business and DVBE reporting,
as we previously describe.
Nonetheless, we believe that the Authority could better account
for its contracts with these public entities in its reporting. For
example, Caltrans—with whom the Authority has a $290 million
contract—participates in the Authority’s small business program.
However, the Authority does not include this contract on its
utilization report. When we asked the Authority why it does not
include the Caltrans contract on its utilization report, a contract
compliance administrator stated that it had not received utilization
reporting from Caltrans on a consistent enough basis to allow the
California State Auditor Report 2018-108 67
November 2018
Authority to confidently include the agency in its reporting. The
contract compliance administrator asserted that as it receives
more information from Caltrans, the Authority will incorporate
Caltrans’ small business utilization rates into its reports, as well
as monitor Caltrans’ small business utilization through to the
contract’s completion.
The Authority provided a different reason for not reporting on
all of its contracts with private entities. Although it is required
to include all of its contracts with private entities on its quarterly
utilization reports, those reports have not included $303 million
in such contracts. The chief administrative officer stated that
the Authority exempts certain contracts because the scopes of the
work are too specific for it to require the contractors to be small,
DVBE, or DBE businesses or to subcontract with such businesses.
For example, many of the contracts omitted from the report are for
expert witness or legal services. The chief administrative officer
also explained that partly due to our inquiries, she realized that
the Authority has no written policy explaining these exemptions
or the process by which it determines whether to include these
provisions in its contracts. She stated that she intends to oversee
the development of such a policy.
Although there are few consequences if the Authority or its
contractors do not meet their utilization goals, the emphasis on
reporting in both state and federal requirements suggests that
transparency and accountability related to contracting practices
are key principles of the business utilization programs. However,
by limiting the contracts it includes in its public reporting, the
Authority is not accurately reflecting the proportion of its total
expenditures that go to these businesses. We believe that given We believe that given the
the magnitude of the Authority’s contracting, the public would magnitude of the Authority’s
be best served by a higher degree of transparency in its reporting. contracting, the public would
An important part of increasing that transparency would be for be best served by a higher
the Authority to disclose both the total value of its contracts degree of transparency in its
as well as the extent to which it has exempted contracts from reporting of its utilization of
small business requirements. The Authority’s reasons for making small, disabled veteran, and
those exemptions—whether its own prospective policies or state disadvantaged businesses.
guidelines—would be an important part of that disclosure.
The Authority Followed Industry Standards When Estimating Its
Economic Impact and Has Adequately Disclosed the Limitations of
Those Estimates
The Authority used two widely accepted economic modeling
programs to measure the total economic impacts of its spending
from its contracting and construction activities. In September 2017,
the Authority issued a retrospective report regarding the
68 California State Auditor Report 2018-108
November 2018
total economic impact from its spending activities from fiscal
years 2006–07 through 2015–16, which it estimated to be between
$3.5 billion and $4.1 billion. In its 2018 business plan, it updated
this information to include fiscal year 2016–17, estimating that its
economic impact increased an additional $1.6 billion to $1.8 billion
during this time.
Although we identified some inconsistencies between the data that
the Authority used for its economic modeling and the documentation
supporting those data, these inconsistencies were relatively minor.
To determine the accuracy of the Authority’s data, we randomly
selected and reviewed 58 data entries, including expenditure amounts
and geographic locations at the zip code level, and we verified the
information’s accuracy by comparing it to the original invoices or
other expenditure data sources. We identified certain inconsistencies:
for example, the Authority attributed some expenditures to incorrect
counties, which affected the Authority’s estimations of jobs in a
particular county. In other instances, the Authority explained that
due to incomplete expenditure information, it used higher-level
financial or past geographical data to make assumptions about the
size of expenditures, which could affect the precision of the dollar
amounts it reported.
Nonetheless, given the magnitude of the total amounts that the
Authority reported and the fact that the amounts are intended to
be estimates, we are not concerned that the Authority’s economic
impact reporting is misleading or substantially under- or overstated.
Further, the Authority disclosed the assumptions it made when
designing its methodology by discussing those assumptions in the
public technical memorandum that accompanied its reports.
Recommendations
To help improve the effectiveness of its sustainability policy, the
Authority should revise the policy by May 2019 to more clearly
differentiate between the construction and operation phases of the
high-speed rail system. Further, it should ensure that each objective
in each section of the policy is associated with quantifiable metrics
for evaluating implementation.
To allow it to evaluate the sustainability of the high-speed rail
system’s construction, the Authority should, by May 2019, perform
and document a review of its compliance with its existing quality
controls related to ensuring the validity and completeness of
contractor-reported data. The Authority should also establish a
formal process to perform such reviews periodically.
California State Auditor Report 2018-108 69
November 2018
To help ensure that it meets its sustainability goals, the Authority
should comprehensively compare the three construction projects’
performances to their construction contractors’ original baseline
estimates on a quarterly basis. It should perform the first of these
comparisons no later than May 2019.
To help ensure that its contractors’ proposed environmental
impacts are reasonable and to measure the progress of its
sustainable construction efforts over time, the Authority should, by
November 2019, identify and track standardized measures—such
as project miles—that will allow it to compare construction impacts
across the high-speed rail system’s different construction projects.
To increase the transparency of its reporting, the Authority
should, by May 2019, expand its quarterly small business, DVBE,
and DBE utilization reporting to account for the total value
of all its contracts and to identify the reasons it has exempted
specific contracts.
We conducted this audit under the authority vested in the California State Auditor by section 8543 et seq.
of the California Government Code and according to generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence
to provide a reasonable basis for our findings and conclusions based on our audit objectives specified
in the Scope and Methodology section of the report. We believe that the evidence obtained provides a
reasonable basis for our findings and conclusions based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
November 15, 2018
70 California State Auditor Report 2018-108
November 2018
California State Auditor Report 2018-108 71
November 2018
Appendix
Scope and Methodology
The Joint Legislative Audit Committee (Audit Committee)
directed the California State Auditor to perform an audit related
to the Authority’s costs and contracting processes, as well as
several other audit objectives. Table A below outlines the Audit
Committee’s objectives and our methods for addressing them.
Table A
Audit Objectives and the Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, rules, and Reviewed relevant laws, regulations, policies, and procedures.
regulations significant to the audit objectives.
2 Review and assess the Authority’s policies, • Reviewed prior audit findings from our office and the Authority’s internal audits office
procedures, and processes for managing related to contract management policies, procedures, and practices.
contracts and containing costs for the project,
• Reviewed the Authority’s 2017 revised contract management policies and procedures.
including its processes for tracking, reviewing,
and paying contractor invoices. • Identified areas of the 2017 policies and procedures most closely related to controlling
costs and ensuring value. We compared those areas to the Authority’s previous policies
and to the State Contracting Manual.
• Selected nine active environmental, engineering, or professional services contracts with
a total value of $1.3 billion and reviewed the contract managers’ compliance with the
Authority’s policies and procedures. We also reviewed the Authority’s management of
its three active construction contracts, with a total value of $3.1 billion.
• When necessary, reviewed contract materials provided by persons other than
contract managers, such as other Authority staff, outside consultants, or the
contractors themselves.
3 Evaluate the Authority’s process for reviewing and • Reviewed Authority construction data and documentation to determine the number
approving design‑build contract change orders. and value of the change orders it has executed to date and of those it expects to
execute before the completion of the Central Valley construction.
• Judgmentally selected 16 change orders, including three rejected changes. We
reviewed supporting documentation to determine if the Authority followed the
processes outlined in its policy for processing change orders.
• Analyzed the Authority’s future cost estimates to determine the major risk areas
contributing to executed and expected change orders. We interviewed Authority staff and
reviewed documentation to assess how the Authority’s decisions contributed to changes.
• Analyzed the Authority’s baseline schedules and other planning documents to determine
the current and expected effects of change orders on the system’s cost and schedule.
4 To the extent possible, review and evaluate the • Reviewed the Authority’s reporting on the economic impact of its expenditures from
Authority’s efforts to determine the economic July 2006 through June 2017.
impact the project has had on communities in
• Reviewed documentation to determine the extent to which the Authority supported its
those areas where construction is underway.
reported expenditures.
continued on next page . . .
72 California State Auditor Report 2018-108
November 2018
AUDIT OBJECTIVE METHOD
5 Determine the extent to which the • Reviewed state laws and other state and federal criteria related to utilizing small,
Authority contracts with small and disadvantaged, and disabled veteran owned businesses.
disadvantaged businesses.
• Selected 10 contracts included on the Authority’s utilization reports and reviewed
supporting documentation.
• Identified the number, type, and value of contracts for which the Authority does not
report its utilization of small, disadvantaged, and disabled veteran owned businesses.
6 Review the Authority’s sustainability policy and • Reviewed the Authority’s sustainability policy and implementation plan.
assess its compliance with the policy. Assess the
• Reviewed nine entries from the Authority’s sustainability database to assess the extent
Authority’s efforts to evaluate the economic and
to which the data are valid and supported by required documentation.
environmental outcomes of its policy.
• Engaged a sustainability consulting firm to evaluate the Authority’s sustainability
policy, implementation plan, reporting, and progress toward goals in comparison to
industry best practices and other, similar projects.
7 Determine whether there are opportunities • Reviewed the Authority’s business plans to determine how the system plans have
for the Authority to expedite the project and evolved over time to increasingly include blending with existing infrastructure.
reduce costs through cooperation with other
• Interviewed Authority staff and reviewed Federal Railroad Administration regulations
transportation entities, such as other transit or
to determine how blending is likely to affect rail service operations.
rail lines, or through capturing additional value
through construction of project facilities. • Reviewed the Authority’s environmental and engineering planning documents to
determine when the Authority made key decisions about blended infrastructure.
• Compared the Authority’s system cost estimates over the past six years to assess how
blending has led to reduced costs.
• Interviewed staff and reviewed documentation to determine whether additional
options exist to blend elsewhere in the system.
• Reviewed academic and industry materials on opportunities to capture additional value
through construction of project facilities and determined that the Authority has worked
with cities to evaluate their feasibility, but is still in the early stages of this planning.
8 Review and assess any other issues that are We did not identify any additional issues that are significant to the audit.
significant to the audit.
Source: Audit Committee’s audit request number 2018‑108, planning documents, and information and documentation identified in the table
column titled Method.
Assessment of Data Reliability
In performing this audit, we relied on electronic data files we
obtained from the Authority’s oversight firms related to the dollar
amount and nature of changes to the Authority’s construction
contracts. The GAO, whose standards we are statutorily required
to follow, requires us to assess the sufficiency and appropriateness
of any computer-processed information we use to support our
findings, conclusions, or recommendations. To perform this
assessment, we evaluated the oversight firms’ data against sources
of corroborating documentation from both the Authority and
its construction contractors. We determined that the data was
sufficiently reliable for the purposes of summarizing change orders
in this report.
California State Auditor Report 2018-108 73
November 2018
*
* California State Auditor’s comments begin on page 85.
74 California State Auditor Report 2018-108
November 2018
October 22, 2018
Brian Annis, Secretary
California State Transportation Agency
915 Capitol Mall, Suite 350-B
Sacramento, CA 95814
Dear Secretary Annis:
The California High-Speed Rail Authority (Authority) appreciates the opportunity to respondto
the California State Auditor (CSA) draft audit report issued on October 15, 2018. The CSA
conducted this audit at the request of the Joint Legislative Audit Committee. The audit’s scope
addressed the efficiency and efficacy of the policies and practicesemployed by the Authority.
We concur with and willwork to implement the CSA’srecommendations as an integral part of
the Authority’s commitment to excellence and continuous improvement. We are pleased to
report that we have begun implementing these and other corrective actionsto remedy the issues
identified.
The Authority is making progress on delivering the Californiahigh-speed rail system. The
Authority’schallenge has beento evolve its organization and improve its program management
processes, while concurrently deliveringthis complex mega-program. We are working to meet
this challenge through a continuous improvement process by whichwe methodically and
regularly identify and apply lessons learned. Through this ongoing process, we are taking
systematic steps to expedite the Authority’s transition to a more rigorous program management
and delivery organization. This evolution included establishing new governance structures in
mid-2017--that we further strengthened in 2018--to more effectively manage the program
through highlystructured configuration management and change processes.
To advance and expedite this organizational transition, the Board of Directors recruited new
leadership in 2017. The Board appointed me as the Authority’s Chief Executive Officer and my
tenure began in February 2018. I was joined immediately thereafter by two newlyappointed
senior executives Iselected to support me in leading this organization –a new Chief Operating
Officer and a Chief Deputy Director. Those individuals brought specific skill sets in construction
and program delivery and in administrative management. Together, we and the rest of the senior
executive team take the audit’s recommendations seriously.
My senior executive team has reviewed the audit and is working with staff to address the CSA’s
recommendations. This will include conducting root cause analyses and implementingadditional
corrective actions beyond the audit’s recommendations,if necessary. We regard this as an
opportunity to further solidify the systemic improvements that the Authority has continued to
establishandthat we have strengthened over the last year.
Also, theCSA’s auditcoincides with the Authority’s development of three key foundational
governance documentsthat are essential to our ongoing processof continuous improvement.
770 L Street, Suite 620,Sacramento, CA 95814 • T: (916) 324-1541 • F: (916) 322-0827 • www.hsr.ca.gov
California State Auditor Report 2018-108 75
November 2018
Secretary Brian Annis
Page 2
October 22, 2018
First, in May 2018, the Board of Directors adopted the 2018 Business Plan,which lays out the
Authority’s implementation strategy for delivering California high-speed rail. Second, in June, the Board
adopted our 2018 Program Baseline, which is an essential management document that outlines the scope,
schedule and budget for the Authority Program’s early delivery objectives. Third, inOctober 2018 we
finalized our Project Management Plan(PMP), which clarifies our integrated organizational framework
and presents a governance structure stressing program management and delivery.
As detailed below, we are actively addressing the audit’s recommendations through implementation and
other remedial steps. As it has done in the past, the Authority will move swiftly to fully implement the
recommendations of the State Auditor that bear on the efficacy of program delivery. We hope and trust
that our rapid implementation of these recommendations will bolster confidence in the Authority’s
commitment to active management and continuous improvement of this most important program.
The CSA recommendations and the Authority’s responses (in bold) are as follows:
Chapter 1:
The Authority’s Decision to Begin Construction Before Completing Proper Planning Led to Cost
Overruns and Delays
1. To ensure that the change orders it approves are necessary and that theircosts are appropriate, the
Authority should adhere to the guidance and estimates the oversight firms provide to it. If the
Authority chooses to deviate from the oversight firms’ recommendations, it should clearly document
why it made those deviations.
Response:
The Authority concurs with this recommendation.In 2017, the Authority initiated a governance
process to assess the construction, financial, legaland other programperspectivesfor all
changes. The Board of Directors adopted the 2018 Business Plan that included the new
governance (see page 63of the Plan)and adopted the programBaseline in June 2018. The
Authority then updated and formalized this process in the Program Management Plan (PMP).
Thecurrent process includes:aProgram Delivery Committee,which is a management
committee that holds the functional groups accountable for program delivery and evaluates all
pending and potential change orders;and aBusiness Oversight Committee, whichacts as a
change control committee and must approve all change orders before they go to the Executive
Committee and,when needed,the Board of Directors(Board)for approval to execute.
Each governance committee has an approved charter that outlines itspurpose and decision-
making authority. In accordance with the CSArecommendation, the Authority will revise the
charters to require documentation when a governancecommittee overrules a Project
Construction Management (PCM) firm’srecommendation.
This will be accomplished through a Business Case, which is the document forrequestinga
proposed change order or achange to the Baseline. The Business Case is required to provide a
summary andjustification of the recommended actions/changes and includes signatures from
the relevant functional, legal, construction and program teams. For construction change
orders, the accompanying Business Case will documentthe PCM recommendationand cost
estimate with an explanation of any differences.
Planned completion date: June 2019
76 California State Auditor Report 2018-108
November 2018
Secretary Brian Annis
Page 3
October 22, 2018
2. Before executing its next constructioncontract, the Authority should establish formal prerequisites for
beginning construction to prevent avoidable cost overruns and project delays.At a minimum, these
prerequisites should identify specific benchmarks related to landacquisition, utility agreements and
relocations, and agreements with externalstakeholders, including impacted local governments and
other railroadoperators.
Response:
The Authority concurs with this recommendation and has placed significantfocus on this issue.
The 2018 Business Plan identifies this as a critical lesson learned and it continues to be a point of
emphasis (see Chapter 4, Lessons Learned and Managing Risk, page 53of the Plan).Key among
the lessons learned wasthat the Authority’s decision to awarddesign-build contracts before
acquiring right of way and completing agreements with utilities, local governments and railroads
meant there were many unknowns thatcreated risks of delays and highercosts. The same chapter
also describes the governance andmanagementprocedures initiated in 2017 to strengthen
decisionmaking through a highlystructuredprocess, which our response to Recommendation 1
outlines briefly.
1 More specifically, the Business Oversight Committeeconsidersbenchmarks prior to progressing
to procurement or to the next phase of project delivery.For example, the Business Oversight
Committeewould consider the progress of pre-construction activities, including right-of-way
acquisition, prior to approving procurement activities to select a construction contractor.
Further, delivering projects in accordance with the Program Baseline, which was adopted by the
Board of Directors in June 2018, also ensuresthat certain predecessor tasks (or prerequisites) are
2 sufficiently advanced prior to beginning construction,asthe Baseline incorporatesthe lessons
learned outlined in the 2018 Business Plan.The Authority continues todevelop Baseline project
work plans composedof discretely definedtasks.Thesetasks are linked together based on project
delivery sequencing, whichestablisheswhattasks must be completed prior to beginning other
tasks (i.e., predecessortasks and successortasks).
Planned completion dates:
Project Work Plans (with benchmarks) -Draft: January 2019
Project Work Plans (with benchmarks) -Final: February 2019
3. To better position itself to complete the three Central Valley projects by the December 2022 federal
grant deadline, the Authority should improve its monitoring and evaluation of the oversight firms’
risk assessment processes and should take steps to ensure that these processes are consistent across
the three projects by May2019.
Response:
The Authority concurs with this recommendation.The Authority recognizes the risks
associated with complying with the deadline established by the American Recovery and
Reinvestment Act of 2009 and is in the process of reorganizing its risk team overseeing the
Central Valley projects. It is hiring additional risk management personneland will prioritize
both risk management and mitigation in a way that is consistent across the three construction
projects. Further, to verify that the risk assessment processesare consistent across the three
projects, the Authority will continue to enforce all policies and procedures related to PCM
California State Auditor Report 2018-108 77
November 2018
Secretary Brian Annis
Page 4
October 22, 2018
oversight, revise the PCM manual to be more explicit on risk management, and will publish a
program estimate-to-complete and risk management manual.
Planned completion date: April 2019
4. To enable policymakers and the public to track the Authority’s progress toward meeting the federal
grant deadline of December2022, the Authority should, by January 2019, begin providing quarterly
updates to the Legislature detailing the progress of the three Central Valley construction projects
using an earned value model that compares construction progress to the projected total completion
cost and date.The Authority should base these updates on the most current cost estimates available.
Response:
The Authority concurs with this recommendation.The Authority recentlydeveloped a Program
Delivery Status Report (PDSR) that itproduces on a monthly basis.The PDSR includes
comprehensive status information within the Authority’s three main areas of project delivery:
1) right-of-way procurement, third party agreements,and environmental clearance; 2)
engineering/designand construction; and 3) rail infrastructure. This PDSR and associated
procedures will be codified within the Program Controls Manual to be published.
The PDSR provides detailed information on the progress of the three Central Valley
construction projects withinthe Infrastructure Deliverysection, including cost varianceand
schedule performance index (SPI).
Moving forward, the Authority will use the most current cost information and an earned value
model to refine the cost variance and SPI for each of the three Central Valley construction
projects.On a monthly basis, the cost variance and SPI information will be used to estimate the
projected total completion cost and date for each of the Central Valley construction projects.
This information will be included in the PDSR.
By January 2019, the Authority will use information from the PDSR–including earned value,
cost variance and SPI–to develop and provide quarterly updates to the Legislature.The
updates will include detailed information on the progressof the three Central Valley
construction projects.This information will be used to actively manage the construction
projects to ensure that the 2022federal grant deadline is met.
Planned completion dates:
PDSR Quarterly Update -Draft: December 2018
PDSR Quarterly Update -Final: January 2019
PDSR Manual –May 2019
5. To ensure that it is adequately prepared if it is unable to meet the federal grant deadline of
December2022, the Authority should, by May2019, develop a contingency plan for responding to
such a scenario.
Response:
The Authority concurs withthis recommendation.The Authority intends to meetthe federal
grant deadline and,to achieve that, we continuously monitor and assess the program through
the ProgramDelivery Committee and the Business Oversight Committee. As part of this
monitoring process we routinely update the individual project risk registers in coordination
with the Federal Railroad Administration(FRA) on a quarterly basis. The ProgramDelivery
78 California State Auditor Report 2018-108
November 2018
Secretary Brian Annis
Page 5
October 22, 2018
Committee and the Business Oversight Committee use the Project Update Report, Business
Plan and Baselinein their monitoring activities. We will continue to assess different contingency
plans/options through eachof these activitiesand will prepare a contingency plan in accordance
with the CSA recommendation, which will be updated on an annual basis.
Planned completion date: May2019
Chapter 2:
The Authority Has Not Successfully Enforced the Policies It Implemented to Address Ongoing
Deficiencies WithIts Contract Management
1. To improve its contract management, increase accountability, and justify the significant
amount it pays for contracted services, the Authority should take the following steps by
May2019:
• Prioritize contract management efforts and reduce the frequency with which contract
management responsibilities shift among Authority staff by establishing a formal process
for hiring and assigning full-time, experienced contract managers. These contract
managers should have duty statements reflecting their contract oversight responsibilities
and they should report to supervisors who understand those responsibilities and have
extensive knowledge about the contracts’ deliverables. In addition, those supervisors’
duty statements should clearly lay out their responsibility for addressing any contract
manager noncompliance with the Authority’s contract management policies and
procedures, whether reported by Contract Management Support Unit (CMSU)or
identified by another means.
Response:
The Authority concurs with the recommendation. The Authority will create a formal
process for hiring and assigning full-time experienced contract managersto reduce the
frequency with which contract management responsibilities shift among Authority staff.
This will include emphasizing contract management experience/skills as well as desirable
contract manager qualifications.In addition, all new advertised positions that require
contract management will specify the skills required for a contract manager within the duty
statement.
In addition, all existing duty statements will be reviewed and modified to reflect contract
management/oversight responsibilities for all contract managers and their supervisors.
Contract manager supervisors’ duty statements will also address their responsibility to hold
their contract management staff accountable for compliance with the Authority's contract
management policies and procedures. While only contract managers are currently required
to be trained in contract management, contract manager supervisors will also be required
to attend contract management training to ensure that the contract managers they
supervise are adhering to the Authority’s policies and procedures. The Authority will also
create a separate contract management training specifically for supervisors.
Planned completion date:May2019
California State Auditor Report 2018-108 79
November 2018
Secretary Brian Annis
Page 6
October 22, 2018
• Require CMSU to establish a schedule to monitor individual contract manager compliance
and report annually the results of this monitoring to Authority executive leadership. To help
ensure the integrity of its oversight role, CMSU should be composed of state staff in place of
RDP consultants.
Response:
The Authority concurs with the recommendation. A schedule to monitor contract
managers’ compliance has been created and assessments of contract manager performance
are to begin no later than November 2018, to comply with the Authority’s PROC-FIS-038,
Contract Compliance Procedure.The assessments will be electronically tracked for
resolution status and an executive report will be prepared no less than annually.
In addition, the Authority concurs that CMSU should be composedof state staff. The
Authority will prepare a Budget Change Proposal for the 2020/21 fiscal year to request staff 3
augmentation to removecontractedRail Delivery Partner (RDP)consultants and replace
withstate employees.
Planned completion date:The contract manager assessment schedule has been developed and
the Budget Change Proposal concept will be submitted to the Authority Executive Committee
for consideration in May2019.
• Hold contract managers accountable for performing the duties that the Authority’s policies
assign to them.Specifically, CMSU and, to the extent necessary, contract managers’
supervisors should require and review evidence from contract managers demonstrating their
approval of deliverables, detection and resolution of contractor performance issues, and
assessment of contract amendments for merit.The Authority should not accept observations
and reports from its contractors or RDP consultants in place of this evidence.
Response:
The Authority concurs with the recommendation. The Authority’s contract compliance policy
POLI-FIS-038 established requirements for performing assessments and reports on contract
manager compliance with the Authority’s policies and procedures. The Authority will begin
performing assessments of contract managers no later than November 2018. We will begin with
the contracts identified in this audit and continue until all contracts have been fully assessed.
These assessments will ensure that contract managers are following the Authority's policies and
procedures, which arethe foundation of a well-managed contract. The assessments will also
provide documented evidence that contract managers, not RDP consultants,are properly
approving deliverables/invoices, resolving contractor disputes or performance issues
appropriately, and justifying contract amendments with verifiable documentation in all
contracts. The assessmentswill not only provide supervisors/management with documentation
demonstrating accountability (conformance/nonconformance), but also contain
recommendations for best practices and opportunities for improvement.
Once an assessment is issued, it will be tracked to closure/resolution. The process also maintains
the tracking mechanism to verify the implementation of the corrective action. This plan provides
a framework for review of the contract managers’ performance by contract manager and by
contract, providing a quantitative assessment of contract manager performance.
80 California State Auditor Report 2018-108
November 2018
Secretary Brian Annis
Page 7
October 22, 2018
4 Planned completion date: The Authority will begin performing assessments of contract
managers no later than November 2018 and anticipates that all contract manager assessments
will be completed by or before November 2020 and be ongoing thereafter.
2. To prevent the inappropriate use of contractors to perform state functions, the Authority should
develop procedures by May 2019 forevaluating whether new or existing administrative duties should
be assigned to contractors or to state employees.
Response:
The Authority concurs with this recommendation.The Authority’s Administration Office will
develop procedures for evaluating whether new or existing administrative duties should be
assigned to contractors or to state employees.
Planned completion date: May 2019
3. To ensure the completeness of contract managers’invoice reviews and that invoiced costs are
allowable under contract terms, the Authority should amend its applicable procedures by May 2019 to
require contract managers to document their review of invoiced rates and expenses.
Response:
The Authority concurs with this recommendation.As part of a larger plan to revise, fieldtest,
and finalize the contract management procedures,the Authority will revise its invoice review
procedures (FIS-PROC-033) to require contract managers to document their review of invoiced
rates and expenses.
Planned completion date: May2019
4. To ensurethe consistency and effectiveness of its efforts to monitor the performance of the oversight
firms with which it contracts,the Authority should develop a formal methodologyby May 2019for
using the performanceevaluation tool it has implemented.This methodology should include procedures
for assessing the sufficiency of the oversight firms’review and approval forconstruction contracts.
Response:
The Authority concurs with this recommendation.The Authority has developed and
implemented monthly performance-based evaluations for its construction oversight firms that
5 are updated by each contract manager.A formal methodology will be developed for the
performance evaluations. Contract Performance Monitoring and Reporting Policy POLI-FIS-
034 and Procedure PROC-FIS-034 will berevised to document this formal methodology.
The Authority’s contract manager and quality team will evaluate the PCM’s procedure for
compliance with section 3.9 Contractor’s Monthly Payments of the Project and Construction
Management Manual (For Design-Build Contracts) on all construction packages;specifically,
for the purpose of assessing construction progress to validate invoice submissions and earned
value from the design-builder.The Authority will amend its Quality Manual to reflect this
process and the frequency of the assessments.Any non-conformance will be formally
documented.
Planned completion date: May2019
California State Auditor Report 2018-108 81
November 2018
Secretary Brian Annis
Page 8
October 22, 2018
5. To ensure oversights firms’spending is reasonable, the Authority should develop a formal process by
May2019, for tracking any out-of-scope work the oversight firms perform.To reduce the likelihood
that its contracts with these oversight firms run out of funds prematurely as a result of this additional
work, the Authority should also develop a formal process for amending these oversight firm’s
contracts contemporaneous to change orders that significantly extend timelines or increase the scope
of work of the construction contracts that theyoversee.
Response:
The Authority concurs with this recommendation.The June 2018 Program Baseline, approved
by the Boardof Directors, details the scope, schedule and budget for all work on the high-speed
rail program, including PCMfirms’ contract budgets and schedule. Any PCM contract 6
amendment requires approval from the Business Oversight Committee.As outlined in the
response to Recommendation 1, the Business Oversight Committeerequires a Business Case
with subject matter expert signatures beforeconsideringany contract change. Additionally, the
Authority will revisethe PCM manual to reflect their responsibility to identify, manage and
request amendments for out-of-scope work. The PCM contract managers will separately be
responsible for tracking and identifying any potential out-of-scope workand the necessity to
amend contracts at each PCM work plan revision and approval.
The Program Delivery Committeeis responsible for governance oversight of contracts and will
consider the impact on PCMcontracts by programmatic trends (such as schedule delays) or
changesapproved by the Business Oversight Committee(such as a change to adesign-build
contract).A key component of Program Delivery Committee meetings will focus on upcoming
key milestones and decision-points, including when or if contracts need amending.
Planned completion date: May2019
Chapter 3:
The Authority Can Improve the Quality and Transparency of Its Monitoring and Reporting for Key
Goals
1. To help improve the effectiveness of its sustainability policy, the Authority should revise the policy
by May2019 to more clearly differentiate between construction and operation phases of the high-
speed rail system.Further, it should ensure that each objective in each section of the policy is
associated with quantifiable metrics for evaluating implementation.
Response:
The Authority concurs with this recommendation.The Authority will revise its Sustainability
Policy to more clearly differentiate between construction and operations.Since the end of audit
fieldwork, the Authority has revised the implementation plan to match each existing policy 7
objective with a quantitative metric, posted here:
http://www.hsr.ca.gov/docs/programs/green_practices/sustainability/Sustainability_implementation_p
lan_SUMMARY_Oct2018.pdf.
Planned completion date: The Policy will be updated by May2019.
2. To allow it to evaluate the sustainability of the high-speed rail system’s construction, the Authority
should perform and document a review of its compliance with its existing quality controls related to
ensuring the validity and completeness of contractor-reported data by May2019.The Authority
should also establish a formal process to perform such reviews periodically.
82 California State Auditor Report 2018-108
November 2018
Secretary Brian Annis
Page 9
October 22, 2018
Response:
8 The Authority concurs with this recommendation.The Authority improved its environmental
and sustainability data gathering and analysis system in July 2017. As an additional
improvement, the Authority will develop a quality assurance process to perform periodic
reviews of its compliance with the quality controls related to validity and completeness of
contractor-reported data.
The updated system has a datafield validation feature, which is a quality control measure that
involvesa cross check at the data entry level, next level review and confirmation of data by
PCMs, and a final data quality review and acceptance by the Authority.This process is
enforced by the system and isongoing and continuous. The recommended periodic reviews will
verify that the above-described controls are functioning as expected.
Planned completion date: May2019
3. To help ensure it meets its sustainability goals, the Authority should comprehensivelycomparethe
three construction project’s performance to their construction contractors’ original baseline estimates
on a quarterly basis by May2019.
Response:
The Authority concurs with this recommendation.Since 2015, the Authority has collected and
organized data which it uses to analyze construction activities related to air quality and
9 greenhouse gasemissions. The Authority thencompares that to the contractuallyidentified
baseline estimates;this comparison is done on a quarterly basis. The Authority compares the
contractor’s required performance for waste, absolute targets for recycling of concrete and
steel and a percentage target for remaining nonhazardous waste, as recycling records are
submitted.Other sustainability performancetracking, related to fuel usage, water usage, and
recycling, had previously been analyzed and compared to baseline estimates on an annual basis.
The Authority will begin comparison of these performance areason a quarterly basisand will
adjust the analysis to include the relationship to construction progress.
Planned completion date: May2019
4. To help ensure that itscontractorsproposed environmental impacts are reasonable and to measure the
progress of its sustainable construction efforts overtime, the Authority should, by November2019,
identify and track standardized measure–such as project miles –that will allow it to compare
construction impacts across the high-speed rail system’s different construction projects.
Response:
The Authority concurs with this recommendation.Currently, the Authority has a model that
assessesprogramenvironmental impacts using standardized metrics, including tons of CO2e,
kgCO2e/kg, kgCO2e/gallon, kgCO2e/kWh, normalized by miles and construction typology.
The Authority is in the process of updating thismodel to incorporate refined project lengths
and infrastructure typologies adopted in the Baselineand to incorporate relevant, validated
data (e.g.,tons of CO2eand environmental product declarations for actual materials installed)
tracked on each construction package.This updated model will allow comparison across
construction projectsand support establishing targets for future construction contracts.
Planned completion date: November2019
California State Auditor Report 2018-108 83
November 2018
Secretary Brian Annis
Page 10
October 22, 2018
5. To increase the transparency of its reporting, the Authority should, by May 2019,expand its quarterly
small business, DBVE, and DBEutilization reporting to account for the total value of all its contracts
and to identify the reasons it has exempted specific contracts.
Response:
The Authority concurs with this recommendation.In an effort toincrease transparency, the
Authority will post the total value of all current contracts within the Small Business Program
section of the Authority’s website.The Authority will also post the total value of any contracts
that require small business, DVBE and/or disadvantaged business, which will appropriately
reflect the Authority’s utilization percentages per state and federal guidelines.
While the Authority reports utilization on a quarterly basis for federally funded contracts, the
stateprocess,administeredby the Department of General Services, only requires an annual
report from all state agencies/departments.However, the Authority will create an internal
process to closely align the state timelinetothe federal quarterly process.In addition, a policy
will be created that will clearly specify what contracts are exempt from small business, DVBE
and/or disadvantaged business according to state and/or federal regulations, policies, and
guidelines.
Planned completion date:May2019
Again, weappreciate the opportunity to provide a response to our plans to implement the California State
Auditor’s recommendations.If you have any questions, please contact Paula Rivera, Chief Auditor, at
paula.rivera@hsr.ca.govor (916) 403-2679
Sincerely,
for Brian P.Kelly
Chief Executive Officer
84 California State Auditor Report 2018-108
November 2018
California State Auditor Report 2018-108 85
November 2018
Comments
CALIFORNIA STATE AUDITOR’S COMMENTS ON THE
RESPONSE FROM THE CALIFORNIA HIGH‑SPEED
RAIL AUTHORITY
To provide clarity and perspective, we are commenting on the
Authority’s response to the audit. The numbers below correspond
to the numbers we have placed in the margin of its response.
Although the Authority states that the Business Oversight 1
Committee (BOC) considers benchmarks prior to progressing to
procurement or the next phase of project delivery, this committee,
which the Authority established in September 2017, has not
yet overseen the procurement of a construction contractor. As
Figure 6 on page 26 shows, the Authority executed the most
recent of its three construction contracts—for Project 4—in 2016.
Therefore, any oversight the committee provides regarding key
preconstruction activities is still prospective.
As we discuss on pages 30 and 31 of the report, the Authority’s 2
recently released comprehensive schedule delineates that early
work tasks, such as land acquisition, should begin before the design
and construction phase. However, the schedule does not establish
specific benchmarks the Authority must achieve before procuring
a construction contractor. Therefore, to avoid cost overruns and
delays from moving to the construction phase too soon, as our
recommendation on page 36 specifies, the Authority should
establish formal prerequisites for beginning construction and these
prerequisites should identify specific benchmarks related to land
acquisition, utility agreements and relocations, and agreements
with external stakeholders.
As we state on page 39, CMSU’s oversight of contract management 3
policies and procedures has been weak and inconsistent. We also
explain on page 41 that placing oversight responsibility with RDP
consultants creates a potential conflict of interest. However, under
the Authority’s proposed approach, it would not have funding for
state employees to staff CMSU until at least July 2020. Given the
issues we found and the amount of public funds at stake, we believe
the Authority should move faster to secure professional state staff
to perform CMSU’s crucial oversight duties.
We state on page 38 that as of September 2018, the Authority’s 4
56 contract managers were collectively responsible for 204 contracts.
Although we recognize the amount of work necessary to hold each
contract manager accountable for each of their assigned contracts,
we do not believe the State can afford for the Authority to take
two years to complete its assessments of contract managers, as its
86 California State Auditor Report 2018-108
November 2018
response indicates. Additionally, we encourage the Authority to
focus its initial efforts not only on the contracts identified in this
audit but also its other largest and highest risk contracts.
5
The Authority’s response does not specify whether its methodology
for evaluating its PCMs—which we refer to in our report as
construction oversight firms (oversight firms)—will include
procedures for assessing the sufficiency of the oversight firms’
reviews and approvals of invoices for construction contracts. As
we state in our recommendation on page 59, such procedures
are important to ensure consistency and the effectiveness of the
Authority’s efforts to monitor the performance of the oversight
firms with which it contracts. Therefore, the Authority should
include these procedures in its methodology.
6
The Authority states that any oversight firm contract amendment
requires approval by the BOC. However, we identified concerns
with an oversight firm contract amendment that the Authority
approved in March 2018. Specifically, as we describe on pages 55
and 56, the Authority’s documents assert that the amendment
stemmed from it assigning work to the oversight firm that was
outside the original contract. However, the contract manager was
unable to tell us the amount of funding that went to the oversight
firm for this out-of-scope work and acknowledged that he had not
documented the oversight firm’s adequate performance. Therefore,
until the Authority implements our recommendation on page 59
to track any out-of-scope work that oversight firms perform,
the Authority, including its BOC, will not know whether the
oversight firms’ spending rates are reasonable or if amendments
are appropriate.
7
We appreciate that the Authority is taking steps to match existing
sustainability policy objectives with quantitative metrics in its
implementation plan. However, our recommendation on page 68
is that the Authority first revise its sustainability policy to more
clearly differentiate between construction and operation phases of
the system, a process we would expect to generate new policy goals
and objectives. At that point, the Authority should reevaluate its
implementation plan to ensure that the plan contains appropriate
metrics for those new policy objectives.
8
Although the Authority asserts that it improved its environmental
and sustainability data gathering and analysis system in July 2017,
the Authority’s sustainability director confirmed during our
audit that the Authority was still in the process of collecting
and reviewing sustainability data for calendar year 2017 and that
the transition to this system was still ongoing. Additionally, the
Authority’s response describes quality control measures for the new
California State Auditor Report 2018-108 87
November 2018
data system, but these measures are not fundamentally different
from those that were in place under the previous system. We
describe our concerns with the accuracy of the data on page 63.
9
The Authority’s assertion that it has completed these comparisons
since 2015 is inconsistent with the evidence it provided during
our audit. During the audit, the Authority’s sustainability director
confirmed for us that the Authority was beginning the process of
comparing actual sustainability impacts to contractor estimates,
but that the Authority did not expect to have preliminary findings
until the end of 2018. The Authority also provided documentation
showing that some comparisons were underway. However, as
we state on page 64 of our report, our expert observed that this
documentation does not allow the Authority to effectively project
whether contractors will meet or exceed their estimates because
it does not account for actual construction progress to date. On
page 64 we also state that documentation did not include equivalent
comparisons related to the environmental impacts from waste
or water use. Therefore, we stand by our recommendation on
page 69 that the Authority should comprehensively compare the
three construction projects’ performances to their original baseline
estimates on a quarterly basis, and it should begin doing so no later
than May 2019.