CSA
Recommendations
Read the report at California State Auditor ↗
California Department of
Fish and Wildlife
It Is Not Fulfilling Its Responsibilities Under
the California Environmental Quality Act
June 2019
REPORT 2018-119
CALIFORNIA STATE AUDITOR
621 Capitol Mall, Suite 1200 | Sacramento | CA | 95814
916.445.0255 | TTY 916.445.0033
For complaints of state employee misconduct,
contact us through the Whistleblower Hotline:
1.800.952.5665
Don’t want to miss any of our reports? Subscribe to our email list at auditor.ca.gov
For questions regarding the contents of this report, please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255
This report is also available online at www.auditor.ca.gov | Alternative format reports available upon request | Permission is granted to reproduce reports
Elaine M. Howle State Auditor
June 27, 2019
2018-119
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As directed by the Joint Legislative Audit Committee, the California State Auditor performed
an audit of the California Department of Fish and Wildlife’s (department) duties and activities
related to the California Environmental Quality Act (CEQA). The following report concludes that
the department has failed to meet its responsibilities under CEQA.
As the highest state authority overseeing California’s fish and wildlife resources, the department’s
input on CEQA documents, such as environmental impact reports, is critical. However, in
recent years, the department has reviewed less than half of the CEQA documents it received.
The department frequently does not respond to consultation requests and rarely provides
comments on draft CEQA documents. In 2018 the department provided formal comments on
just 8 percent of draft CEQA documents it received. Because it lacks policies for prioritizing
and reviewing CEQA documents, the department cannot ensure that its staff are consistently
reviewing projects with potentially significant impacts on the environment.
Further, the department has not ensured that it spends the filing fee paid by project applicants and
public agencies subject to CEQA exclusively on its CEQA activities. Although state law restricts
the use of the filing fee revenue to fund only activities related to its CEQA responsibilities, the
department keeps this revenue in a shared account with revenues for other functions, and it does
not track the CEQA revenue and expenditures separately from the other functions. In fact, we
determined that from fiscal years 2012–13 through 2016–17, the department spent $5.7 million in
CEQA filing fee revenue to subsidize non‑CEQA programs.
Similarly, the department’s current timekeeping practices do not differentiate between staff time
spent on CEQA activities and staff time spent on other departmental work. Even though the
department has frequently cited insufficient staff resources as the cause for its inability to meet its
CEQA responsibilities, without accurately capturing the amount of time staff spend working
on CEQA activities, it cannot correctly determine either its necessary staff resources or the
amount it should charge for filing fees.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
621 Capitol Mall, Suite 1200 | Sacramento, CA 95814 | 916.445.0255 | 916.327.0019 fax | www.auditor.ca.gov
iv Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Selected Terms and Abbreviations Used in This Report
CEQA California Environmental Quality Act.
CEQA document A document—either an environmental impact report, negative declaration, or mitigated negative
declaration—that a public agency prepares to comply with CEQA.
CESA California Endangered Species Act.
Draft review period The time period within which state agencies may review and comment on draft CEQA documents.
Environmental impact report A document describing and analyzing a proposed project’s likely significant environmental effects. It lists ways
in which the project applicant might mitigate significant effects and indicates alternatives to the project.
Environmental scientist Department staff who review CEQA documents and permit applications. These scientists are located at the
department’s regional offices and state headquarters.
Exemption Statutory or categorical criteria that define projects that are not subject to CEQA.
Final phase The CEQA review phase during which the lead agency certifies or adopts its CEQA document.
LSA Lake and Streambed Alteration.
LSA agreement A permit the department issues that details mitigation measures to protect lake and streambed habitats.
LSA agreements are necessary for projects that substantially impact a body of water.
Lead agency The agency that is primarily responsible for carrying out or approving a project. A lead agency prepares or
contracts for the preparation of CEQA documents, which it must also certify. Typically, a local government
agency, such as a city or county, acts as a lead agency.
Negative declaration A document stating why a project will not significantly affect the environment. When the project will not
significantly affect the environment as a result of mitigation measures the project applicant incorporated into
the project, the document is called a mitigated negative declaration.
Notice of determination A notice that a lead agency sends to inform the public and responsible agencies that it has approved or
decided to carry out a project and has certified or adopted a CEQA document.
Notice of preparation A notice that a lead agency sends during the preliminary phase of CEQA review to inform responsible and
trustee agencies that it will be preparing an environmental impact report for a project.
Operation of law A term that the department uses to describe projects that proceed without LSA agreements because of the
department’s failure to draft an agreement within the 60‑day time period outlined in state law.
Preliminary phase The CEQA review phase prior to the lead agency preparing a draft CEQA document. During this phase, the
lead agency consults with responsible agencies on the type of CEQA document to prepare for a project.
Project applicant The party that proposes a project for lead and responsible agency approval.
Responsible agency An agency that helps the lead agency prepare adequate CEQA documents through consulting with the lead
agency and commenting on draft CEQA documents. An agency is a responsible agency if it has authority
to approve an aspect of a project by, for example, issuing a permit. A state or local agency may act as a
responsible agency. A single project may have more than one responsible agency.
Trustee agency A state agency that helps the lead agency prepare adequate CEQA documents for projects that affect
resources within that state agency’s jurisdiction. The department is one of four public agencies specified in
state regulations as a trustee agency.
CALIFORNIA STATE AUDITOR | Report 2018-119 v
June 2019
CONTENTS
Summary 1
Introduction 5
The Department Has Failed to Meet Its Obligations as a
Responsible Agency Under CEQA 13
The Department Has Not Used All Available Funding to
Fulfill Its CEQA Obligations 27
Other Areas We Reviewed 33
Appendix A
Scope and Methodology 37
Appendix B
The Department’s Positions and Expenditures by Funding Source 41
Response to the Audit
California Department of Fish and Wildlife 43
California State Auditor’s Comments on the Response From
the California Department of Fish and Wildlife 51
vi Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2018-119 1
June 2019
SUMMARY
The Legislature enacted the California Environmental Quality Act (CEQA) in 1970
in an effort to disclose and mitigate the potential environmental damage that certain
development projects—such as housing developments and shopping centers—might cause.
CEQA requires the California Department of Fish and Wildlife (department) to act as
what the law refers to as a responsible agency for many of these development projects.
In this role, the department must work with other public agencies, known as lead agencies,
to inform decision makers and the public about the potential environmental impacts of
the proposed projects and to reduce those environmental impacts to the extent feasible.
The department is the highest state authority on California’s fish and wildlife resources
and is responsible for issuing permits for projects affecting lake and stream habitat or
endangered species; therefore, there is no adequate substitute for the department’s input
on a project’s impacts on sensitive habitat and species. Our audit examined whether
the department has met its statutory requirements under CEQA and whether it has
appropriately managed its available funding to meet its CEQA responsibilities. This
report concludes the following:
The Department Has Failed to Meet Its Obligations as a
Page 13
Responsible Agency Under CEQA
One of the department’s key roles under CEQA is to provide
consultation and commentary to lead agencies when those lead
agencies are developing CEQA‑related documents. Nonetheless,
the department’s project tracking database shows that in 2018 the
department responded to only 20 percent of the requests for
consultation that it documented receiving from lead agencies.
Without early consultation from the department, these lead
agencies may be less likely to prepare appropriate and complete
CEQA documents. Further, according to regulations, the department
should—as a responsible agency—comment on CEQA documents for
projects that are within its jurisdiction. However, it seldom provides
such comments, even though doing so could make its subsequent
permitting process more efficient. Finally, the department has
provided its staff with neither policies and procedures for selecting
CEQA documents to review nor guidance for conducting those
reviews. Without such policies and guidance, the department cannot
ensure that its environmental scientists consistently conduct their
CEQA reviews and that its staff select for comments the CEQA
documents for projects that pose the greatest risk to the State’s fish
and wildlife resources.
2 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
The Department Has Not Used All Available Funding to Fulfill Its
Page 27
CEQA Requirements
State law requires the department to impose and collect a filing
fee to defray the cost of protecting fish and wildlife resources
through CEQA, and it also requires the department to use this fee
for CEQA‑related activities only. However, from fiscal years 2012–13
through 2016–17, the department spent a total of $5.7 million in
CEQA filing fee revenue on non‑CEQA activities. Moreover, the
department cannot adequately determine the full cost of its CEQA
activities because it has not tracked the number of hours staff spend
reviewing CEQA documents and performing other CEQA‑related
tasks. Although state law requires the department to evaluate the
cost of its CEQA activities and recommend changes to the CEQA
filing fee every five years to ensure that the fees cover its costs, the
chief of the Habitat Conservation Planning Branch stated that
the department delayed the assessment due in 2017 because of
changes to its accounting system and staff turnover. Without an
accurate assessment of the resources it uses for the CEQA program,
the department cannot accurately determine whether a change in
fees is necessary.
Other Areas We Reviewed
Our audit found that the department has created unnecessary delays
in its CEQA review process by mailing CEQA documents to its
environmental scientists rather than distributing those documents
electronically. Staff at the regional offices indicated that it has historically
taken one to two weeks for them to receive CEQA documents for
review. In addition, the department has paid nearly $30,000 in postage
to ship these documents over the last five years. We also determined
that although the majority of the department’s revenues are restricted to
specific uses, the department might be able to request additional funding
from the California Environmental License Plate Fund to support its
CEQA activities.
Summary of Recommendations
To ensure that it consistently prioritizes, reviews, and comments on
CEQA documents for development projects with potentially significant
impacts on the environment, the department should establish a policy
by March 2020 for determining the CEQA documents it will review and
provide comments on, and by this same date, it should develop policies
and procedures outlining its expectations for conducting CEQA review.
CALIFORNIA STATE AUDITOR | Report 2018-119 3
June 2019
To ensure that it complies with state law requiring it to use CEQA
fee revenue only for CEQA activities, the department should
immediately begin tracking and monitoring its CEQA‑related
revenues and expenditures separately from its revenues and
expenditures for other programs and activities.
To accurately estimate the resources it needs to review all CEQA
documents that it receives, the department should implement a
timekeeping mechanism by December 2019 that requires staff to
track the hours they spend on CEQA‑related activities.
Agency Comments
The department generally agreed with our recommendations and in
some cases provided information on how it would implement them.
4 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2018-119 5
June 2019
INTRODUCTION
Background
Enacted in 1970, the California Environmental Quality Act (CEQA) requires
state agencies to give major consideration to preventing environmental damage
when regulating activities under their jurisdiction. The California Department of
Fish and Wildlife (department) refers to CEQA as California’s broadest and most
important environmental law. Both public and private development projects in
California—such as community centers and apartment buildings—are generally
subject to CEQA.1 CEQA generally requires state and local government agencies
to inform decision makers and the public about the potential environmental
impacts of proposed projects and to reduce those environmental impacts to the
extent feasible.
CEQA has been the subject of some controversy. Project applicants have been
critical of CEQA for increasing the costs of development. Critics of CEQA have
also claimed that opponents of development projects use the law to slow down
the projects for nonenvironmental reasons, such as to prevent transit stations in
certain neighborhoods or to gain leverage in labor negotiations. However, since
its implementation, public agencies and the public have used CEQA to protect the
environment, as well as public health and safety. For example, in 2003 local groups
and labor unions realized that a proposal to expand an oil refinery to produce
lower sulfur diesel fuel would increase pollution and harm public health in the
area. Through CEQA, the groups worked with the refinery owner to mitigate
the increased pollution yet still allow the expansion to go forward. A 2016 report
commissioned by a charitable foundation supporting environmental work found
that since the Legislature enacted CEQA, California has outperformed other states
in conserving and protecting its natural resources while also enjoying economic
prosperity. Thus, CEQA can be an effective tool for protecting the public and the
environment while allowing development and growth.
The Department’s Mission
The mission of the department is to manage California’s diverse fish, wildlife, and
plant resources—and the habitats upon which they depend—for their ecological
value and for their use and enjoyment by the public. Its many functions include
law enforcement and issuing hunting and fishing licenses. In addition, the
department has authority to approve projects with impacts on fish, wildlife, and
their habitats in part through its permitting process. Although its CEQA duties
are separate from its permitting duties, the department’s CEQA work may serve
as a precursor to its permitting process. Under CEQA, the department is generally
responsible for reviewing the impact that development projects may have on fish
and wildlife resources and for recommending options for mitigating potentially
significant effects on those resources. We discuss the department’s specific
responsibilities related to CEQA in more detail below.
1 Certain development projects are statutorily or categorically exempt from CEQA.
6 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
The Department’s Structure and Budget
The Habitat Conservation Planning Branch (conservation branch)
conducts the department’s work related to CEQA and accounts
for 14 percent of the department’s total staff. Dispersed among the
department’s regional and satellite offices, environmental scientists
from the conservation branch handle work related to CEQA reviews
and to permitting based on the locations of projects. Figure 1 shows
the area assigned to each region and the location of each region’s
headquarters. When a project spans multiple regions or may have
statewide impact, conservation branch staff at the department’s state
headquarters oversee the project’s CEQA reviews.
The department’s budget was $600 million in fiscal year 2018–19,
and it used half of this budget for conservation programs.
Appendix B provides a breakdown of the department’s enacted
fiscal year 2018–19 budget by function and revenue source. The
State’s General Fund contributed $121 million to the department in
fiscal year 2018–19. The remainder of its funding came from
different sources, including fees related to CEQA reviews, permits,
and hunting and fishing licenses. The department receives about
$6 million annually—roughly 1 percent of its overall budget—from
fees that project applicants and public agencies that are subject to
CEQA pay during the review process.
The Department’s Duties Under CEQA
CEQA Agency Roles
Lead Agency—Typically, a local government agency, such
As we indicate above, the CEQA process occurs
as a city or county, acts as a lead agency. The lead agency
after a public or private entity—which we refer
is responsible for either carrying out or approving a project.
to as a project applicant—decides to construct
A lead agency prepares—or contracts for the preparation
a development project, but before it applies for a
of—CEQA documents, which the lead agency must also
permit from the department. The project applicant
certify or adopt.
must submit an application for approval to a
Responsible Agency—A state or local agency is a
lead agency, usually a city or county. As Figure 2
responsible agency if it has authority to approve an aspect
shows, the lead agency must then consult with
of a project by, for example, issuing a permit. A responsible
the department regarding the project’s potential
agency helps the lead agency prepare adequate CEQA
environmental impacts. This step begins the
documents by consulting with the lead agency and by
CEQA process, which has three separate phases—
commenting on draft CEQA documents. A single project
preliminary, draft, and final—that we discuss later
may have more than one responsible agency.
in this section. At the end of the CEQA process,
Trustee Agency—A trustee agency is a state agency that
the lead agency decides whether to approve the
helps the lead agency prepare adequate CEQA documents
project, after which the project will proceed to
for projects that affect resources within that state agency’s
the permitting process, if necessary. Although
jurisdiction. The department is one of four public agencies
portions of the CEQA process have deadlines, it
specified in state regulations as a trustee agency.
can take years for a project to complete the CEQA
Source: Analysis of CEQA laws and regulations and a report process and obtain permits if necessary.
from the Association of Environmental Professionals.
CALIFORNIA STATE AUDITOR | Report 2018-119 7
June 2019
Figure 1
The Department’s Regional Offices
REGIONS
1 Northern
2 North Central*
Redding 3 Bay Delta*
4 Central
5 South Coast
6 Inland Deserts
7 Marine†
State Headquarters
Rancho Cordova
Sacramento Regional Headquarters
Fairfield
Fresno
Monterey
Ontario
San Diego
Source: Analysis of the department’s website.
* Sacramento, San Joaquin, and Yolo counties are split between regions 2 and 3. The majority of the counties are within Region 2.
† Region 7 covers the entire coast within three nautical miles off of the shore.
8 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Figure 2
The Three Phases of CEQA Review
SESAHP
WEIVER
AQEC
PROJECT Project applicant applies for
APPLICANT approval from the lead agency.
Lead agency must consult with the department
LEAD
on potential environmental impacts.
AGENCY
Preliminary
DEPARTMENT
The department must provide feedback on the type
of CEQA document the lead agency must prepare.
Lead agency consults with and requests comments
LEAD
from the department on the draft CEQA document.*
AGENCY
Draft
DEPARTMENT
The department may comment on the adequacy of the
document or on additional mitigation measures.
Lead agency:
LEAD • Considers the department’s input.
AGENCY • Makes necessary changes and certifies or adopts
Final its CEQA document.
DEPARTMENT
• Decides whether to allow the project to proceed.
• Pays CEQA fees to the department. $ $
$ $
CEQA ends
Project applicant may apply for permit
from the department, if necessary.
DEPARTMENT
Source: Analysis of CEQA‑related laws and regulations and the department’s permit application instructions.
Note: We define these phases for the purpose of our report. This process does not apply to projects that are statutorily or categorically exempt
from CEQA.
* The lead agency must consult with and request comments from the department when preparing an environmental impact report. It must give
notice to and allow comments from the department when preparing most negative declarations and mitigated negative declarations. If the lead
agency receives comments from the department on these documents, it must consider them.
Depending on the projects’ particular circumstances, the
department has different roles and responsibilities in the CEQA
process. As the text box explains, CEQA mandates specific
requirements to the three roles in which agencies may serve: lead
agency, responsible agency, and trustee agency. The department
functions as a lead agency when it carries out its own projects
in, for example, state wildlife areas. In contrast, the department
CALIFORNIA STATE AUDITOR | Report 2018-119 9
June 2019
functions as a trustee agency for all projects that may affect,
among other things, California’s fish, wildlife, and their habitats.
Finally, the department functions as a responsible agency only
when it will eventually have responsibility for approving projects
by, for example, issuing a permit. A project may have more than
one trustee agency or responsible agency.
This report focuses primarily on the department’s duties as a
responsible agency. Determining early in the CEQA process
whether the department will be a responsible agency can be
difficult. According to the department, the initial documents
describing a project may not include the level of detail necessary to
determine if a permit will be required. However, because state law
and regulations establish activities that a responsible agency must
or should undertake—such as consulting or reviewing draft CEQA
documents—before the permitting process begins, the department
must sometimes perform the duties of a responsible agency before
it is certain that it will serve in that role. The department also has
responsibilities as a trustee agency that extend to all projects—not
just those for which it will eventually issue permits. The duties of
a responsible and a trustee agency are similar; in this report, we
identify those instances when the department’s duties as a trustee
agency differ from its duties as a responsible agency.
The State Clearinghouse, located within the Governor’s Office of
Planning and Research, also has a role in the CEQA process. When a
lead agency determines that a project potentially will have statewide
significance or an environmental impact on natural resources over
which one or more state agencies has jurisdiction, the State
Clearinghouse acts as the liaison between the lead agency and the
state trustee and responsible agencies. State law and regulations
require that, upon the lead agency’s request, the State Clearinghouse
must help identify which state agencies will be
responsible agencies. Further, regulations require it
Types of CEQA Documents
to distribute CEQA documents to the state trustee
and responsible agencies for review and comment.
Environmental Impact Report—A document describing
and analyzing a proposed project’s likely significant
environmental effects. It lists ways in which the project
The Preliminary Phase of CEQA Review
applicant might mitigate significant effects and indicates
alternatives to the project.
The preliminary phase of the department’s CEQA
Negative Declaration—A document stating why a project
review helps to shape the type and content of the
will not significantly affect the environment. When the
CEQA documents, which the text box describes.
project will not significantly affect the environment as a
During this phase, regulations require the result of mitigation measures the project applicant has
department—as a responsible agency—to respond incorporated into the project, the document is called a
to a lead agency’s consultation request and help mitigated negative declaration.
the lead agency determine whether a project
Source: State laws and regulations pertaining to CEQA.
will have a significant effect on the environment.
This consultation informs the lead agency’s
10 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
determination of whether it must prepare a negative declaration or
an environmental impact report for the project. If the lead agency
determines it will prepare an environmental impact report, it sends
a notice of preparation to the department. Regulations require the
department to respond in writing to that notice as soon as possible,
but not longer than 30 days after receiving it, and to include in its
response the environmental issues the lead agency should address
in its draft environmental impact report.
The Draft Phase of CEQA Review
In the draft phase, the department—as a responsible agency—should
receive a draft environmental impact report, negative declaration, or
mitigated negative declaration that the lead agency has completed.
The department and the lead agency must again consult on—
and the department may comment on—an environmental impact
report in the draft CEQA phase. Regulations generally give the
department 45 days to review a draft environmental impact report.
Although state law does not require the department to consult on
a draft negative declaration, regulations generally allow 30 days
for it to review and comment on a draft negative declaration if it
chooses to do so. The department’s consultation and comments
can help ensure that the lead agency’s draft environmental impact
report or negative declaration is adequate. Regulations state that
the department should limit its comments to project activities
within its area of expertise. For example, as a responsible agency,
the department’s comments could inform the lead agency of ways
to mitigate a project’s impact on endangered species. Figure 3
illustrates the timeline within which a responsible agency must fulfill
the preliminary and draft phase requirements.
The Final Phase of CEQA Review
If the department agrees that the environmental impact report
or negative declaration is adequate, it does not play a role as a
responsible agency in the final phase of CEQA review. The lead
agency carries out this phase when it certifies the environmental
impact report or adopts the negative declaration or mitigated
negative declaration before it approves the project. Before certifying
or adopting the respective document, the lead agency must
consider any comments it received from responsible agencies
during the draft review period; it must respond to those comments
when the comments concern an environmental impact report. The
State’s policy is that public agencies should not approve projects as
proposed if feasible alternatives or mitigation measures are available
that would substantially lessen the significant environmental effects
of the projects. However, if specific economic, social, or other
CALIFORNIA STATE AUDITOR | Report 2018-119 11
June 2019
conditions make alternatives or mitigation measures infeasible,
lead agencies may approve individual projects even if they have
significant environmental effects.
Figure 3
Timeline for Responsible Agencies to Consult and Comment on CEQA Documents
Lead agency determines Lead agency sends a notice of preparation Lead agency sends its draft
what type of CEQA only if it decides to prepare a draft environmental impact report or
document it will environmental impact report. negative declaration for
prepare for a project.* responsible agencies’ review.
Responsible agencies Deadline for responsible Typical deadline for
consult with the lead agencies to respond to a responsible agencies
agency.* notice of preparation. to comment on a
draft environmental
Lead agency prepares impact report or
its draft environmental negative declaration.
impact report or
negative declaration.*
30 days 30–45 days†
PRELIMINARY PHASE DRAFT PHASE
Source: Analysis of CEQA laws and regulations.
* Regulations do not provide a specific time limit for consultation or for the lead agency to prepare a draft CEQA document; however, state law
generally allows the lead agency 180 days to finalize a negative declaration and one year to finalize an environmental impact report, starting from
the date the lead agency received the application for the project.
† Regulations generally establish a draft review period of 30 days for negative and mitigated negative declarations and 45 days for environmental
impact reports.
If a lead agency approves a project to proceed, it presents evidence
of its decision by filing a notice of determination with a county
clerk or the State Clearinghouse. At this time, project applicants
pay a filing fee, which we describe later in this report. Although
the lead agency has approved it, a project may still require one or
more permits before the project applicant may proceed with
construction. We discuss the department’s permits and how they
relate to CEQA in the next section.
The Relationship Between CEQA and the Department’s
Permitting Process
As we indicated previously, the department’s permitting process
is separate from the CEQA review process. However, the
department’s authority to approve project permits is one reason it
acts as a responsible agency under CEQA. As a responsible agency,
the department helps the lead agency prepare an appropriate
and complete CEQA document that identifies the significant
environmental impacts of a project; similarly, the department may
determine through its permitting process that a project needs
12 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
additional mitigation measures. Before approving a permit, the
department must issue findings explaining that the measures
included in its permit and in the lead agency’s CEQA document will
substantially lessen any significant environmental impacts within its
jurisdiction that the project may cause.
The department’s two permits—California Endangered Species
Act (CESA) permits and Lake and Streambed Alteration (LSA)
agreements—may build upon the lead agency’s CEQA document.
A project applicant obtains a permit from the department
through a collaborative process. First, the project applicant submits
to the department its CEQA document and an application. If the
application does not contain sufficient information, the department
will follow up with the applicant. Next, the department may require
additional mitigation measures to minimize harm to fish and
wildlife resources. To obtain a CESA permit, an applicant must
fully plan to mitigate the project’s impacts on endangered and
threatened species. To obtain an LSA agreement, an applicant must
ensure that the project does not substantially divert or obstruct
the flow of lakes, rivers, or streams, or alter their beds. A project
applicant seeking a CESA permit must wait until it receives
that permit before proceeding with the project. However, if the
department does not issue a draft LSA agreement within 60 days,
a project applicant may generally proceed without an agreement.
The project applicant must still conduct the activity as described in
its application to the department, including implementing measures
intended to protect fish and wildlife resources.
CALIFORNIA STATE AUDITOR | Report 2018-119 13
June 2019
The Department Has Failed to Meet Its
Obligations as a Responsible Agency Under CEQA
Key Points
• The department has not consistently responded to consultation requests or
commented on draft CEQA documents, allowing lead agencies to approve
projects without its input on whether those projects may affect sensitive fish and
wildlife resources.
• When the department does not comment on draft CEQA documents, it does
not provide important guidance to project applicants and fails to inform them
of mitigation measures they may be required to adopt during the subsequent
permitting process. As a result, the permitting process may take more time.
• The department’s lack of policies, procedures, and training related to CEQA review
increases the risk that its environmental scientists will review CEQA documents
in an inconsistent manner. Moreover, without standards to guide its staff’s
decision making, the department cannot be sure that its supervisors and
scientists select CEQA documents for review and comment that are the highest
priority in terms of protecting the State’s fish and wildlife resources.
The Department Has Not Consistently Consulted and Commented on Development
Projects, Allowing Lead Agencies to Approve Projects Without Its Input
Although lead agencies do not always request early consultation, the department
often does not respond when they do. State law requires the lead agency to consult
with the responsible agencies in the preliminary phase of a development project.
When the department is a responsible agency for a project, regulations require that
it respond to a consultation request to help ensure that the lead agency prepares
the appropriate CEQA document.2 However, the department enters only some
consultation requests it receives in its project tracking database. For example, an
administrative staff member from one of the department’s regions explained that she
enters all consultation requests the office receives through email or mail; however,
she is not always aware of requests by phone and thus does not enter them. Once
staff enter requests into the project tracking database, they then may enter the
department’s responses to the requests, if any.
According to the information in the database, the department responded to only
100 of around 500 (20 percent) documented requests for consultation it received
from lead agencies in 2018. In some cases, the department cited in the database
2 As we discuss in the Introduction, we use the term responsible agency throughout this report to refer to all of the
department’s duties related to the CEQA process from early consultation through reviewing the draft documents.
We specifically note those instances when the department’s duties as a trustee agency differ from its duties as a
responsible agency.
14 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
insufficient time as its reason for not responding to the requests.
Frequently, however, the department did not record any reason for
not responding to a consultation request. The Chief of the Habitat
Conservation Planning Branch (conservation branch chief) stated that
the department’s low rate of response might be due to a number of
different issues, including insufficient staff time and incomplete data
in the database. According to one of the department’s environmental
scientist supervisors, staff at his regional office prioritize early
consultation because making changes to projects is easier during
the preliminary phase. Nevertheless, he acknowledged that the
department may not have the staff resources to respond to every early
consultation request it receives.
Without early consultation from the department, a lead agency cannot
ensure that it will prepare an appropriate and complete CEQA document,
which could lead to challenges in the final phase of CEQA review.
Regulations require the department to help the lead agency determine
whether a project may significantly affect the environment, in which
case the lead agency must prepare or contract for the preparation of an
environmental impact report; otherwise, the lead agency must prepare
a negative declaration. Without the department’s input, the lead agency
may inappropriately determine that a project will not significantly affect
the environment and prepare the wrong document. Regulations require
responsible agencies to take action if they deem a CEQA document
to be inadequate. Specifically, a responsible agency may initiate legal
challenges to CEQA documents it believes are inadequate; if it does
not do so, it is deemed to have waived any objections. It also has the
option of either preparing a subsequent environmental impact report,
if statutorily permissible, or assuming the role of the lead agency, if
specific legal conditions are met.
Furthermore, the department frequently does not reply to official
early notices—called notices of preparation—for projects that may
significantly affect the environment. When a lead agency determines that
a project may have a significant impact on the environment and that the
department will be a responsible agency, it notifies the department that
it intends to prepare an environmental impact report. State regulations
require the department to provide a written reply to each notice of
preparation within 30 days and to specify within its reply the scope and
content of the information that the draft environmental impact report
should include. However, according to the department’s project tracking
database, it replied to only 14 percent of these notices in 2018.
The database includes a field for the department to record its reason
for not responding to a notice of preparation; however, in many
cases, we found that the department left this field blank. For the
two projects we reviewed where the department did not reply to
the notices of preparation, the assigned scientists stated that they did
not have sufficient time to reply within the required 30 days. If the
CALIFORNIA STATE AUDITOR | Report 2018-119 15
June 2019
department does not either respond or request additional time within
those 30 days, the lead agency has the legal right to assume that the
department does not have a response to make. However, because
the department has jurisdiction over the conservation, protection,
and management of California’s fish and wildlife resources, its input
on a project’s impacts on sensitive habitats and species is critical.
The preliminary phase of review is not the department’s last chance
to provide input on projects; however, the department frequently
fails to provide input during the draft phase, as well. In fact, the
percentage of draft CEQA documents that the department reviewed
has dropped significantly over the past five years. Although state law
does not require the department to provide comments on every draft
CEQA document in its role as a responsible agency, regulations state
that it should comment on the adequacy of the lead agency’s draft
environmental impact report or negative declaration for projects that
it will later be asked to approve. However, the department seldom
comments on draft CEQA documents. As Figure 4 shows, the
department did not take any action at all for most of the documents
it received from 2014 through 2018.
Figure 4
The Number of Draft Environmental Impact Reports and Negative Declarations the Department Reviewed Has
Decreased Over the Past Five Years
2,500
2,000
1,500
1,000
500
0
2014 2015 2016 2017 2018
Year
Total received Reviewed Commented on
stnemucoD
AQEC
tfarD
fo
rebmuN
2,347
2,141
2,078
1,774 1,768
1,470
63%
1,202
56%
832
40%
579
526
33%
341 30%
227
15% 150 119 144
11%
7% 7% 8%
Source: Analysis of the department’s project tracking database as of January 2019.
16 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Even when the department did review draft CEQA documents,
it did not always provide comments to the lead agencies. For
example, according to its database, the department reviewed
30 percent of the documents it received in 2018. However, of those
526 reviewed documents, it commented on only 144. Regulations
generally allow the department 30 days to review and comment
on negative declarations and 45 days to review and comment on
draft environmental impact reports. After that period expires,
the department may still provide comments on draft CEQA
documents, but state law does not require the lead agencies to
respond to those comments. Nevertheless, lead agencies must
consider all comments received until a CEQA document is certified
or adopted.
Even when the department reviewed
draft CEQA documents, it did not always
provide comments to the lead agencies.
As a result of the department’s failure to fulfill its responsibilities in
the preliminary and draft phases, lead agencies have approved some
projects’ CEQA documents without any input from the department.
After the draft phase, a lead agency must finalize a project’s CEQA
document and decide whether to approve the project. Before it does
so, state law requires the lead agency to consider draft comments
from responsible agencies. Therefore, the draft phase is generally the
department’s last opportunity during the CEQA process to inform
the lead agency of the project’s effects on sensitive species and
habitats within its jurisdiction and possible mitigation measures for
these effects.
When we reviewed a selection of 20 projects for which lead agencies
completed CEQA documents and for which the department was
a responsible agency, we found that the department conducted
varying levels of review during the preliminary and draft phases.
For six of these 20 projects, early consultation did not occur and
the department did not comment on draft CEQA documents.
For example, in 2016 a water district approved a project that
involved constructing a pump station and installing a new pipeline.
The department did not have a record of early consultation and
did not comment on the water district’s draft mitigated negative
declaration. For another seven projects, the department provided
input during only one of the phases. Finally, for the remaining
seven cases, the department provided input during both the
preliminary and draft phases. However, the department acted after
CALIFORNIA STATE AUDITOR | Report 2018-119 17
June 2019
the review period had expired in four of these seven cases. When the
department does not fulfill its responsibilities, lead agencies may
not be aware of potential significant impacts to fish and wildlife
resources that they should consider.
The department indicates that it does not have enough resources to
fulfill all of its CEQA responsibilities. In 2012 it told the Legislature
that it could review only 50 percent of the documents it received
with the funding and staffing levels it had at that time. According
to the conservation branch chief, this is still the case. However, as
Figure 4 shows, the percentage of CEQA documents the department
reviewed has fallen below 50 percent over the last five years— in 2018
it reviewed only about 30 percent of the documents it received.
This decrease occurred, as Figure 5 shows, even though the number
of CEQA‑funded positions has remained relatively stable.
Figure 5
The Department’s Number of CEQA Positions Has Remained Relatively Stable
40
30
20
10
0
2013–14 2014–15 2015–16 2016–17 2017–18
Fiscal Year
dednuF
yltceriD
fo
rebmuN
snoitisoP
AQEC
Source: Analysis of the department’s staffing data.
The department offered several possible explanations for the decrease
in the documents it reviewed. According to the conservation branch
chief, the department’s number of LSA staff—some of whom
also spent time reviewing CEQA documents—has decreased by
50 percent in recent years. In addition, the number of split positions,
which are positions receiving funding from multiple sources, such
as CEQA fees, LSA agreement fees, and CESA permit fees, has
increased. He said that although these changes might have increased
the number of permits the department issued, they also might have
decreased the number of CEQA documents it reviewed. Further,
he said that the department has received CEQA documents that
18 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
involve more complicated environmental issues and that the reviews
therefore take longer. Finally, some lead agencies, such as the
California Department of Transportation (Caltrans), contract with
the department for staff dedicated to those lead agencies’ CEQA
and permitting activities. However, according to the department and
Caltrans, the main purpose of these reimbursed positions is to assist
with the permitting process, rather than to review CEQA documents.
The department may, in fact, need additional resources to meet
its responsibilities. However, as we discuss later in this report,
the department has not tracked the time its staff spent on CEQA
activities in a manner that would enable it to estimate the resources
it would need to fully meet its CEQA responsibilities. Moreover, the
department has not spent all of the CEQA fees it received on CEQA
activities. The department will need to address these problems
before it can adequately justify the need for additional resources.
The Department’s Failure to Comment on Draft CEQA Documents
May Slow Its Permitting Process and Lead to Avoidable Harm to
the Environment
When the department does not comment on draft CEQA documents,
the process for applicants to obtain permits for projects may take
more time. According to the department scientists we interviewed,
the department’s comments can strengthen the permitting process.
They further stated that when the department ensures that a
lead agency knows of and can consider all known or reasonably
anticipated significant environmental impacts before approving a
project, it enables that lead agency to require the project applicant
to implement additional measures to protect fish and wildlife. In
addition, when a project applicant knows early in a project that
it will need to implement costly mitigation measures, it has more
time to consider ways to modify the project to reduce or avoid
these costs. Furthermore, when the department comments on draft
CEQA documents, it could reduce the need to request additional
information from project applicants during the permitting process.
Our review suggests that when the department does not comment
on draft CEQA documents, it may slow its permit processes.
We reviewed a selection of 25 projects for which the department
approved LSA agreements. The department did not comment
on the draft CEQA documents for 18 of these projects. On average,
the department took 354 days to finalize LSA agreements for
these 18 projects. This is more than double the amount of time
the department took—175 days—to finalize LSA agreements
on the seven projects on which it did comment. According to the
senior scientist overseeing the LSA program for the central regional
office, the department’s comments on draft CEQA documents
CALIFORNIA STATE AUDITOR | Report 2018-119 19
June 2019
could ideally make the permit process easier, but in practice the
lead agencies’ draft documents do not always contain enough detail
for the department to comment on permit‑specific issues. However,
we question this assertion, given the results of our review. Although
our selection was not a statistical sample, it represents a variety of
projects across four regional offices.
The department’s commenting on draft documents may speed the
permitting process in part because it may reduce the need for
the department to request additional information during that
process, saving both the department’s and the project applicants’
time. According to the lead scientist in the LSA program for
the north central region, delays during the permitting process
often occur because of the time applicants take to respond to
the department’s requests for additional information. Although the
department cannot control how long applicants take to submit
additional information, it can—by commenting on the draft
CEQA document—specify needed information years before the
permitting process begins. For example, the department’s reply
to the notice of preparation for a solar park project asked the lead
agency to include a detailed analysis of the project’s stream impacts
in its CEQA document. That reply noted that the analysis would
make the environmental compliance process more efficient by
saving the department effort during the LSA permit process. The
LSA agreement process for the solar park took just over 200 days
to complete, much less than the average of about 350 days for
the projects we reviewed that did not receive the department’s
comments on their draft CEQA documents.
By commenting on draft CEQA
documents, the department can
specify needed information years
before the permitting process begins.
In a converse example, in 2011 the department did not comment
on the draft environmental impact report for a city’s planned civic
center because, according to the assigned environmental scientist,
he did not have time. In 2014 the project applicant applied for an
LSA agreement for the project. However, the department deemed
the application incomplete and asked for additional information
about the project’s stream impacts. After reviewing the additional
information, the department requested yet more information about
the project, and it did not issue the LSA agreement until almost
two years after it received the application. Had the department
20 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
commented on the project’s draft CEQA document, it could
have asked the lead agency to include additional information on
stream impacts, which could have reduced the amount of time the
department spent requesting and reviewing additional information
during the permitting process. According to the department, CEQA
documents that do not address all lake and streambed impacts are a
common cause for delayed LSA agreements.
A lengthy permitting application process may also contribute to
the department’s inability to issue some LSA agreements. As we
mention in the Introduction, state law allows a project to proceed
without additional mitigations to protect fish and wildlife when
the department fails to draft an LSA agreement within 60 days
of receiving a complete application, through a process that the
department calls operation of law. An application is complete
when it sufficiently describes the project’s impacts on lake and
stream habitat. If the department deems an application incomplete,
the project applicant has unlimited time to submit additional
information until the department deems the application complete.
As Table 1 shows, the department has allowed numerous projects to
proceed without LSA agreements through operation of law.
Table 1
A Significant Number of Projects Have Proceeded Without LSA Agreements
2014 2015 2016 2017 2018
Operation of law projects 269 256 297 338 396
Total applications 1,959 2,232 2,264 2,872 2,646
Source: The department’s reports generated from its project tracking database.
The amount of staff time dedicated to reviewing and returning
incomplete applications may contribute to the department’s not
being able to draft some LSA agreements within 60 days. According
to the senior environmental scientist overseeing the LSA program
in the conservation branch, staff do not always have time to issue
draft agreements for projects that apply for LSA agreements. He
also acknowledged that reviewing incomplete applications takes
more staff time than reviewing complete applications because staff
must follow up with the project applicants to obtain the missing
information and must continue working with the project applicants
until the applications are complete. Therefore, it is reasonable to
conclude that the time staff spend reviewing incomplete applications
may divert their attention from reviewing complete applications.
CALIFORNIA STATE AUDITOR | Report 2018-119 21
June 2019
When the department does not issue a draft LSA agreement, it
may miss an opportunity to ensure that a project applicant has
adopted adequate mitigation measures to protect fish and wildlife.
For example, in 2017 the department’s central regional office
allowed a solar park to proceed through operation of law. In a letter
to the project applicant, the department acknowledged that the
project could proceed through operation of law but stated that it
still had concerns over the project’s risk of water pollution and
underestimated stream impacts. Determining a project’s long‑term
detrimental impact on the environment can require significant
analysis, but ultimately the department’s agreements can reduce the
projects’ adverse impacts to fish and wildlife.
The Department Has Not Provided Guidance for Its Regional Offices,
Which Could Result in Inconsistent CEQA Review
The department has established neither centralized policies and
procedures nor mandatory training regarding CEQA review,
increasing the risk that regions will review CEQA documents
inconsistently. When the department’s regional offices receive a
CEQA document, staff enter the basic details of the project into
the department’s project tracking database. Next, all but one of the
regions triage the documents to determine which to prioritize
for review and comment. The northern region’s Redding office
does not triage documents because it is able to review all of the
relatively small number of documents that it receives. In some
regions, scientists triage the documents, while in other regions the
supervising scientists do. According to the conservation branch
chief, a scientist is assigned to review the chosen CEQA documents
and may make informal or formal comments to the lead agency
about affected natural resources and mitigation measures necessary
to protect these resources.
Neither the department nor its regional offices have policies
describing how the regions should determine which documents to
prioritize for review and comment. According to the conservation
branch chief, the department must prioritize CEQA documents
because it receives more than it has resources to handle. Because
the department must select which documents to review, we
expected either the state headquarters, the regions, or both
would have formal guidance for staff conducting the triage to
ensure the department is consistent in the kind of projects it
prioritizes. However, according to the conservation branch chief,
the department does not have a standardized process by which
staff triage CEQA documents. Scientists in two regions stated that
the department’s lack of such a process makes it difficult for newer
scientists and supervisors to determine which documents they
should review and on which documents they should comment.
22 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Without such standards, supervisors and scientists cannot be sure
that they select for review documents that are the most important
in terms of protecting the State’s fish and wildlife resources.
The department and the regional offices also lack policies for
regional staff that describe how they should review CEQA
documents. Regulations require that public agencies, including
the department, adopt specific procedures for administering their
responsibilities under CEQA, including the orderly evaluation of
projects. Although the department has regulations for reviewing
CEQA documents, they are general and largely mirror other
state regulations. The conservation branch chief stated that the
department had not developed written policies for CEQA review
because there is such variation between the regions that regional
managers should be able to use their knowledge and expertise to set
priorities and policies specific to their regions. He also stated that
creating such policies might require regulations. However, according
to managers at the regional offices, the regions also do not have
written policies regarding CEQA review. Without written policies at
both the departmental and regional levels, the department cannot
ensure that its environmental scientists are conducting CEQA
reviews consistently either within or across regions.
Without written policies, the
department cannot ensure that
its environmental scientists are
conducting CEQA reviews consistently.
The department has known for years that its lack of policies for
prioritizing which documents to review and its lack of policies for
conducting CEQA review are problematic. In fact, a 2002 Legislative
Analyst’s Office’s report stated that the department lacked both a
formal triage process for CEQA documents and standard protocols
for guiding the extent of the department’s comments. Nonetheless,
the department has not rectified this issue. However, when we
presented our concerns to the conservation branch chief, he
recognized that the lack of formal standards increased the risk that
staff could be inconsistent in reviewing documents. He stated that he
would support the department developing written procedures for
CEQA triage and review, as well as requiring regional offices to create
written policies on CEQA triage and review.
CALIFORNIA STATE AUDITOR | Report 2018-119 23
June 2019
Because the department lacks written guidance on triaging and
reviewing CEQA documents, regions may implement practices
that conflict with the department’s responsibilities under law. For
example, according to the environmental program manager for the
southern coastal region, that region developed a practice of not
reviewing any CEQA documents from a significant portion of the
Los Angeles metropolitan area from 2010 through 2013. In fact,
she estimated that during that time, the department provided no
review on more than 450 projects. The program manager stated
that the region made this decision because it lacked adequate
resources for reviewing CEQA documents at the time; because
the area was highly developed, the regional office assumed any
additional development would have minimal impact on wildlife.
However, none of the other regions have had recent policies that
excluded entire areas for review, even though several also have
highly urbanized areas within their jurisdictions. Additionally, the
conservation branch chief stated that even in a largely urbanized
area, CEQA projects might present significant environmental
concerns. Without sufficient guidance from the department, its
regional offices could adopt policies that effectively exempt projects
from CEQA review when, according to regulations, the department
should be evaluating the environmental impact of such projects.
Because the department lacks written
guidance on CEQA documents, regions may
implement practices that conflict with the
department’s responsibilities under law.
In addition to lacking standardized policies for how its scientists
should conduct their CEQA reviews, the department also offers
only limited training on the subject. According to the conservation
branch chief, the department’s basic CEQA training course
largely focuses on the laws and concepts of CEQA and the stages
of review; it does not describe how to complete a review. He
further stated that no policy or legal obligation exists for staff
training in CEQA and that the trainings the department offers are
not mandatory. When viewed together, the department’s lack of
guidance on CEQA activities and the absence of consistent, robust
training for its scientists means that no common standard exists
by which the department’s staff review and comment on CEQA
documents, both departmentwide and within each region. The lack
of a common standard for review increases the risk that staff will
apply different standards when determining what environmental
24 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
issues or mitigating strategies the documents ought to include. The
conservation branch chief stated that he supports developing more
robust training for scientists.
The department offers only
limited, nonmandatory training
in CEQA for its scientists.
Finally, neither the department nor its regional offices have policies
to describe how staff should enter data into the department’s project
tracking database. In our review, we found inconsistencies in the
quality of the data across regions. The department admits that its
data are incomplete and that the regional offices are inconsistent
in how they use the database. The conservation branch chief
stated that the department has not created policies or procedures
regarding data entry into the project tracking database because the
conservation branch does not have the authority to set such policy.
He stated that the department’s chief deputy director would need to
establish such a policy because the regional directors report directly
to that position. According to the conservation branch chief, past
chief deputy directors have not established a policy for database
entry. Nevertheless, this database is the only source of data the
department has on its CEQA review activities, and the department
uses it to report its activities to the Legislature. Therefore, it is
important for the department to ensure the information it enters
into the database or into any future database it adopts is accurate
and consistent across regions. The current chief deputy director
expressed interest in creating a statewide data entry policy.
Recommendations
To ensure that it consistently prioritizes and reviews projects with
potentially significant impacts on the environment, the department
should do the following:
• Establish a departmentwide policy for prioritizing CEQA
documents for review and comment by December 2019 and
require regional offices to adopt region‑specific procedures by
March 2020.
CALIFORNIA STATE AUDITOR | Report 2018-119 25
June 2019
• Develop policies and procedures outlining departmentwide
expectations for CEQA review and comment by December 2019
and require regional offices to develop region‑specific
policies and procedures for CEQA review by March 2020.
• Develop ongoing training for environmental scientists that
covers subjects including the complexities and technical aspects
of CEQA review by June 2020.
• Should it determine that the new policies and procedures
create rules of general application, incorporate the policies
and procedures into regulations in full compliance with the
Administrative Procedure Act.
To ensure regional staff enter data into the project tracking
database accurately and consistently, the department should, by
December 2019, develop, implement, and provide training on
departmentwide written policies and procedures that outline the
requirements and process for entering data related to CEQA review
into the department’s project tracking database.
26 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2018-119 27
June 2019
The Department Has Not Used All Available
Funding to Fulfill Its CEQA Obligations
Key Points
• From fiscal years 2012–13 through 2016–17, the department did not spend about
$5.7 million in CEQA fee revenue on CEQA‑related activities. Instead, that
revenue helped the department cover shortfalls in other programs because,
although state law requires the department to use CEQA filing fee revenue for
CEQA activities, the department does not track CEQA revenues separately from
certain other program revenues.
• Although the department asserts it does not have enough staff to meet all of its
CEQA responsibilities, it has not tracked the time that staff spend on CEQA
activities in a way that would allow it to accurately estimate the number of staff
it needs to meet these responsibilities.
• The department’s audits have identified thousands of dollars in CEQA revenue
that counties did not collect or remit. However, the department has not yet
recovered that revenue because it determined that it was giving conflicting
guidance to the counties on requirements for collecting and remitting fees and it
has not been able to provide training to county clerks in recent years to the same
extent that it did in the past.
The Department Has Not Spent All of the CEQA Fee Revenue It Received Each Year on
CEQA Activities
The department has not spent all of the revenue it received from CEQA filing fees
on CEQA review. State law requires the department to impose and collect a filing
fee to defray the costs of protecting fish and wildlife resources through CEQA.
A project applicant pays the fee after the department’s review period for the draft
CEQA document, upon the lead agency’s submission of the notice of determination.
The department’s filing fees in 2019 are $2,350 for a negative or mitigated negative
declaration and $3,270 for an environmental impact report. State law requires the
department to adjust the fees each year to account for inflation and restricts the use
of CEQA filing fee revenue to funding only CEQA‑related activities.
However, we found that from fiscal years 2012–13 through 2016–17, the department
did not use $5.7 million in filing fee revenue for its CEQA activities.3 As Figure 6
shows, we calculated that the department spent less on CEQA activities than it
collected in fees in four of the five fiscal years from 2012–13 through 2016–17.
The department tracks this revenue, along with revenue from other program activities,
3 The department stated that because it converted to a new fiscal system, it does not yet have a full accounting of revenues
and expenditures related to CEQA for fiscal year 2017–18.
28 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
in a shared account—which the department calls the nondedicated
account—within the Fish and Game Preservation Fund; however, it
does not manage the CEQA revenues within the account separately
from other revenue. We worked with the assistant deputy director
of fiscal operations to confirm our calculations. He explained that
the department does not monitor each individual revenue source
and related activities within the account. Thus, the department
cannot ensure that it uses restricted CEQA fee revenue only for
CEQA purposes.
Figure 6
The Department Has Not Spent All of Its CEQA Revenue on CEQA‑Related Activities
$7
6
5
4
3
2
1
0
2012–13 2013–14 2014–15 2015–16 2016–17*
Fiscal Year
CEQA revenue not spent
CEQA revenue CEQA expenditures
on CEQA-related activities
snoilliM
nI
$6.1 $6.0
$5.6 $5.7 $5.8
$5.2
$4.7 $4.7
$4.1
$3.6
$1.6 $1.5 $1.4 $1.3
-$0.1
Source: Analysis of the department’s yearly revenue and expenditure data.
* According to the department, its conversion to a new fiscal system means that its fiscal year 2016–17 revenues and expenditures in this figure will
change after it finalizes revenue and expenditures that it posted after July 1, 2017.
In fact, other programs in the shared account have used CEQA
fee revenue to supplement their own deficits. The chief of the
department’s accounting branch (accounting chief) explained that
when programs within the shared account spend more than they
bring in, those programs use funds from others with a surplus—
such as CEQA—before using the shared account’s reserve. For
example, in fiscal year 2014–15, the department’s CEQA fee revenue
exceeded its CEQA‑related expenditures by $1.4 million, whereas
CALIFORNIA STATE AUDITOR | Report 2018-119 29
June 2019
the other programs using the shared account had a deficit of about
$25 million. Therefore, according to the department’s accounting
records, it used $1.4 million in CEQA fees to cover a portion of
the deficits of other programs in the account in that year. If the
department had managed CEQA’s revenue separately and not
used it to cover other programs’ deficits, the department could
have used these funds to better meet its CEQA responsibilities.
The department noted that staff from other programs sometimes
worked on CEQA activities, but the accounting records do not
reflect the costs of those staff. As we describe in the next section,
the department does not track staff activity in a way that would
allow it demonstrate who was working on CEQA activities.
The Department Has Not Adequately Tracked the Time Its Staff Spend
on CEQA Review
Because the department has not accurately tracked how much time
its staff spend on CEQA activities, it cannot estimate the full cost
of the program or determine how many additional resources it may
need. According to the accounting chief, the scientists who review
CEQA documents record their time under a single line item on
their timesheets, rather than recording it per project or task. Some
of these scientists may also spend part of their time working on the
issuance of permits, meaning that the department cannot use their
timesheets to accurately track the time they spent on CEQA review
versus other activities, like permitting. Although the department’s
project tracking database contains a field for the amount of time
scientists spend reviewing specific CEQA documents, we observed
many instances where the field was blank. Further, all four of the
regions we visited stated that these data are incomplete and often
do not accurately capture the actual hours staff spend on review.
Because the department cannot use either timesheets or the data
in its project tracking database to assess the time its scientists
spend on CEQA review, it cannot accurately measure the cost of
administering its CEQA responsibilities.
State law requires the department to adjust the CEQA fees
annually for inflation and to estimate the cost of the program and
report to the Legislature the need for any other fee adjustments
every five years. The department has adjusted the fees each year
for inflation; however, according to the environmental program
manager for the Sacramento headquarters, the department has
not recommended any additional adjustments to the Legislature in
more than 10 years. The department last reported to the Legislature
on the cost of conducting CEQA reviews in 2012. In that year, the
department told the Legislature that the CEQA filing fees would be
adequate to cover the cost of reviewing half the CEQA documents
30 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
it received. However, as we discussed earlier, the department has
reviewed significantly less than 50 percent of the documents that it
received in recent years.
The department last reported
to the Legislature on the cost of
conducting CEQA reviews in 2012.
The program manager stated that the department did not report
on the cost of conducting CEQA reviews to the Legislature
in 2017 because of staff turnover and changes to the department’s
accounting system. Nevertheless, unless the department
periodically estimates the full cost of the CEQA program, it cannot
recommend fees adequate to cover that cost, as state law requires.
As a result, it will not be able to review all CEQA documents,
as it should. Although the department is currently undergoing
a budgeting analysis that will enable it to calculate the average
amount of resources it uses to review a CEQA document, the
analysis is not due to the Legislature until 2021.
The Department Did Not Recover Unpaid Fees It Identified in Its Audits
Although the department has identified instances when counties
did not collect all CEQA fees due, it has not taken steps to recover
that revenue. Once a lead agency approves a project, the project
applicant pays the filing fee to the lead agency. If the lead agency is a
local agency, it remits the fee to the county clerk. If the lead agency
is a state agency, it remits the fees to the State Clearinghouse.
State law requires that county clerks and the State Clearinghouse
maintain records of all CEQA documents received and the fees for
the projects and that they provide those records and the fees to the
department each month. However, some of the department’s audits
have found instances when counties did not collect fees for some
projects when such fees were due.
The department conducts periodic audits of county clerks to
determine compliance with CEQA fee collections; it has conducted
11 such audits since July 2015. At times, those audits have uncovered
concerns. In a 2018 audit of San Joaquin County, for example, the
department’s auditors found that the county did not collect or
remit filing fees for 81 projects from July 2016 through March 2017.
Fees from these projects would have totaled about $180,000.
Further, another audit from the same year of Santa Barbara County
CALIFORNIA STATE AUDITOR | Report 2018-119 31
June 2019
found eight project applicants filed notices of determination with
the county, but the county did not have proof of the applicants’
filing fee payments. If, in fact, the eight applicants did not pay,
the department lost another $21,000 in fee revenue. According
to the chief of the audits branch (audits chief), the former audits
chief chose not to recommend that San Joaquin County recover
the revenue because the department determined its conservation
branch had given conflicting guidance to the counties about which
projects were exempt from filing fees. He also noted that the
department did not require Santa Barbara County to recover
the fees because there were only a few instances of noncompliance.
The department’s conservation branch gave
conflicting guidance to the counties about
which projects were exempt from filing fees.
Although the department conducts periodic audits, it could do
more to communicate the results of those audits beyond the
counties audited and to provide information on requirements
for collecting and remitting CEQA fees. According to the audits
chief, the department does not share its audit findings with all
counties unless it observes similar issues across multiple counties.
However, doing so would allow counties to learn from each
others’ mistakes. The department could also use its attendance at
an annual meeting of county clerks to communicate its findings.
Specifically, the environmental program manager stated that until
recently, the department attended an annual conference of county
clerks. However, because of a staffing reduction, the department
has not been able to attend the conference since 2014. Unless the
department informs counties of the mistakes they might make in
collecting, documenting, and remitting CEQA fees, it risks that the
counties will not collect all fees due.
Recommendations
To ensure that it complies with state law requiring it to use CEQA
fees only for CEQA activities, the department should immediately
begin tracking and monitoring CEQA revenues and expenditures
separately from other program activities within the nondedicated
account in the Fish and Game Preservation Fund.
32 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
To determine more accurately the resources that it needs to review
all CEQA documents it receives, the department should implement
a timekeeping mechanism by December 2019 that requires staff to
track the hours they spend on CEQA‑related activities.
To determine the costs for its CEQA review and set appropriate
fees, the department should complete its five‑year review
of program costs and revenues and report the results to the
Legislature by March 2020. To provide the Legislature with a more
accurate estimate of the costs of CEQA activities, the department
should prepare an update to this review no more than two years
after it has modified its time‑tracking procedures.
To ensure it receives all CEQA revenues to which it is entitled, the
department should immediately begin collecting any unpaid fees it
identifies in audits of counties.
To reduce the risk of counties not collecting and remitting CEQA
filing fees, the department should begin sharing any findings from
internal audits with counties and reminding county officials of their
responsibilities related to CEQA fees.
CALIFORNIA STATE AUDITOR | Report 2018-119 33
June 2019
OTHER AREAS WE REVIEWED
To address the audit objectives approved by the Joint Legislative
Audit Committee (Audit Committee), we also reviewed the
department’s practice of mailing paper CEQA documents to its
regions, identified other funding sources that may be available to
fund CEQA activities, and reviewed the department’s process for
refunding filing fees. Table 2 describes the results of our review and
presents any related recommendations that we have not already
discussed in this report.
Table 2
Other Areas Reviewed as Part of This Audit
The Department’s Process for Distributing CEQA Documents
As we discuss in the Introduction, the State Clearinghouse acts as the liaison between lead agencies
and the responsible agencies, such as the department. After receiving CEQA documents from lead
agencies, the State Clearinghouse physically mails them to the department’s regional offices. Staff
at the regional offices indicated that it has historically taken one to two weeks to receive a CEQA
document from the State Clearinghouse and distribute it to the department’s environmental
scientists. Because of these delays, the scientists—particularly those not working at the main
regional offices—may have two weeks or less to review what can be long and complex documents.
In addition to losing time waiting for mail in transit, the department has paid nearly $30,000 in
postage to ship these documents over the last five years.
According to the conservation branch chief, the department has not prioritized developing a
process for electronically distributing CEQA documents because scanning documents would
be time‑consuming and electronic copies have not been available on the State Clearinghouse’s
database. However, a new public electronic database at the State Clearinghouse should enable
the electronic collection, storage, retrieval, and dissemination of most CEQA documents. State
law required the State Clearinghouse to report to the Legislature on its plans for implementing
the system in 2017 and to report on the status of that implementation by July 2019. According
to its director, the State Clearinghouse has spent the last 18 months working with the California
Department of Technology to create the new online system, which the State Clearinghouse plans
to switch to in the fall of 2019. Further, the State Clearinghouse is already using some elements of
the database, including online access to some CEQA documents. The conservation branch chief
asserted that when the State Clearinghouse’s new database is fully operational, it will have a
positive impact on the CEQA review process.
Recommendation
To maximize the amount of time that environmental scientists have to review CEQA documents, the
department should establish procedures for the electronic distribution of CEQA documents for review by
December 2019. These procedures should include the utilization of the State Clearinghouse’s electronic
system when it becomes available.
continued on next page . . .
34 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Additional Funding for CEQA Reviews
The department cannot use the majority of its non‑CEQA funding for its CEQA reviews because
state law restricts a significant portion of the department’s funding to specific purposes unrelated
to CEQA. The department has little discretion over how it spends this revenue. For example,
state law requires the department to use the oil fee proceeds from its Oil Spill Prevention and
Administration Fund for, among other things, implementing oil spill prevention programs
and studying prevention and response efforts. Additionally, the department receives restricted
funding from sources such as federal grants and contract reimbursements. Similarly, when we
analyzed the department’s Fish and Game Preservation Fund—which accounted for 18 percent
of the department’s fiscal year 2018–19 budget—we found that almost all of its funding sources
are restricted for other purposes. Finally, the deputy director of administration stated that the
department uses the General Fund revenue it receives to fund programs that are not completely
funded by fee revenues—such as law enforcement and marine life protection—and that are
necessary to fulfill the department’s mission.
However, we did identify a potential source of revenue that the department could use. Specifically,
state law allows the department to use proceeds from the sale of environment‑themed license
plates to protect threatened and endangered species and to review projects’ environmental impacts
on fish and wildlife habitat. The Department of Motor Vehicles collects the revenue and deposits
it in the California Environmental License Plate Fund (environmental plate fund). Multiple state
agencies draw from the environmental plate fund, including the department, the Department of
Parks and Recreation, and the California Department of Forestry and Fire Protection. Although
the environmental plate fund’s balance has fallen in recent years, the fiscal year 2019–20 budget
projects a $9 million reserve balance; thus, the department may request additional revenue from the
fund should CEQA fee revenues be insufficient. According to the deputy director of administration,
the department stopped using the environmental plate fund for CEQA review in 2008, after the
Legislature approved a fee increase to fund CEQA review.
The Department’s Fee Refunds
The department has refunded project applicants’ filing fees in compliance with state law. State
law and regulations exempt a project applicant from paying the CEQA filing fee if the department
determines that the project has no effect on fish and wildlife. The department notifies the applicant
or lead agency through a document called a no effect determination. According to the department’s
data, it issued 950 no effect determinations from 2014 through 2018. In all other cases when the
project is not exempt, state law requires a filing fee when a lead agency other than the department
submits a notice of determination—with either an environmental impact report or a negative
declaration—to a county clerk or the State Clearinghouse, as appropriate.
According to the conservation branch chief, the department generally issues no effect
determinations before applicants need to pay the fee, but it is the lead agencies’ responsibility
to inform project applicants that they should apply for a no effect determination. He also stated
that the department works closely with project applicants, lead agencies, and other parties, such
as project consultants, if they believe projects qualify for such determinations. The department
also makes information on applying for a determination readily available, and it informs recipients
of such determinations that they do not need to pay a filing fee. However, if a project applicant
has already paid the fee, and the department subsequently issues a no effect determination, the
department allows the applicant to request a refund. From 2013 through 2017, the department
received 13 refund requests and appropriately issued a refund in each case.
CALIFORNIA STATE AUDITOR | Report 2018-119 35
June 2019
We conducted this audit under the authority vested in the California State Auditor by Government
Code 8543 et seq. and according to generally accepted government auditing standards. Those
standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to
provide a reasonable basis for our findings and conclusions based on our audit objectives specified in
the Scope and Methodology section of the report. We believe that the evidence obtained provides a
reasonable basis for our findings and conclusions based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
Date: June 27, 2019
36 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2018-119 37
June 2019
APPENDIX A
Scope and Methodology
The Audit Committee directed the California State Auditor to
determine how the department allocates resources for its role
as a responsible agency under CEQA. Specifically, it directed us
to determine whether the department is meeting its statutory
requirements for CEQA, to assess the adequacy of its CEQA staffing,
and to determine how it manages its funds to meet its CEQA
responsibilities. Table A outlines the Audit Committee’s approved
objectives and our methods for addressing them.
Table A
Audit Objectives and the Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, rules, and Reviewed relevant laws, rules, and regulations related to the department’s CEQA roles.
regulations significant to the audit objectives.
2 Determine how frequently over the past For the last five years, identified the number of CEQA documents the department has been
five years the department received requests asked to comment on according to its project tracking database and identified how many
to be a responsible agency for a CEQA review requests it reviewed and responded to.
and its actions in response to the requests.
3 Review a selection of CEQA requests where • Judgmentally selected 20 projects for which the lead agency completed CEQA
the department was a responsible agency and documents and for which the department was a responsible agency. We evaluated
determine whether it met statutory requirements. whether the department fulfilled its CEQA role as a responsible agency for these projects
If it did not meet statutory requirements, identify by examining its comments and the timeliness of its response to the CEQA documents.
the major reasons why not. We selected and reviewed projects from regions 2 through 5, since they received the
most CEQA documents in the past five years.
• Reviewed the department’s process for consulting with lead agencies before their
submission of CEQA documents.
• Evaluated the department’s process for deciding whether to review documents during
the CEQA process.
• Identified and analyzed the factors that contributed to instances when the department
did not meet its CEQA responsibilities.
continued on next page . . .
38 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
AUDIT OBJECTIVE METHOD
4 Review and assess the sufficiency of the
department’s allocation of resources.
In particular, perform the following:
a. Assess whether it employs a sufficient • Calculated the department’s number of CEQA‑funded positions for the past five fiscal years.
number of staff to meet its CEQA‑related legal • Interviewed department staff and reviewed the department’s most recent report on
obligations as a responsible agency. its fiscal analysis of CEQA activities to obtain the department’s perspective on its CEQA
staffing levels.
• Reviewed the department’s CEQA workload tracking practices.
b. Identify the expenditure and staffing levels • Analyzed the department’s revenue sources and determined whether it could reallocate
for other functions within the department funds for CEQA review.
unrelated to CEQA and, for those functions, • Identified the department’s revenues and budgeted expenditures for its major program
assess the department’s justification for its areas in fiscal year 2018–19 in Appendix B.
staffing and expenditure levels. To the extent
• Interviewed department staff to determine the department’s justification for its General
possible, identify opportunities to reduce
Fund expenditures.
these levels to fund CEQA‑related activities.
• Reviewed staffing levels to identify if the department could reallocate any chronically
unfilled General Fund positions to CEQA review. We determined that the department
has had no General Fund positions unfilled for more than 6 months that it could have
reallocated to CEQA.
c. Identify how each major function is • Identified the department’s major program areas and their funding sources.
funded, including its CEQA process and • Calculated the number of staff in the department’s conservation branch, which includes
habitat management. Further, determine staff who work in habitat management, as of fiscal year 2018–19.
the percentage of staff dedicated to
• Analyzed the conservation branch’s staffing level relative to the department as a whole.
habitat management.
5 Determine whether the department’s CEQA • Judgmentally selected and analyzed 12 LSA agreements where the department had not
process affects its other programs and whether commented during the CEQA process.
there are opportunities—such as early • Determined the effects of the department’s not commenting on CEQA documents on
participation in the process—that could benefit the LSA agreements by adding these 12 judgmentally selected projects to 13 of the
those other programs. 20 projects selected for Objective 3 for which the department issued LSA agreements. For
these 25 projects, we compared how long the department took to issue LSA agreements
for projects on which it commented during CEQA versus for projects on which it did
not comment.
• Reviewed the department’s reports from its project tracking database to determine the
number of LSA agreements that proceeded through operation of law and interviewed
department staff to determine the department’s perspective on why projects proceed
through operation of law.
• Reviewed litigation related to permitting and CEQA.
6 Determine how the department manages the • Reviewed the department’s process for collecting fees to determine if it ensures that lead
funds received from CEQA fees and whether agencies pay appropriate fees.
it expends or refunds the funds in compliance • Reviewed the revenue and expenditures for CEQA and programs unrelated to CEQA for
with state law and in a manner consistent with the past five fiscal years to determine if any unrelated programs may be using CEQA filing
meeting its CEQA responsibilities. In particular, fees for funding.
determine how the department manages these
• Obtained documentation for cases within the past five years when project applicants
funds in cases where it does not respond to
submitted refund requests and determined whether the department issued the refunds.
requests from local governments.
7 Review and assess any other issues that are Identified what steps the department took to resolve the data issues that it identified in
significant to the audit. its 2012 fiscal analysis of CEQA activities report to the Legislature. We also reviewed the
department’s practice of mailing paper CEQA documents to its regions.
Source: Analysis of the Audit Committee’s audit request number 2018‑119, as well as information and documentation identified in the column
titled Method.
CALIFORNIA STATE AUDITOR | Report 2018-119 39
June 2019
Assessment of Data Reliability
In performing this audit, we relied on electronic data and
physical files that we obtained from the department and the State
Clearinghouse. The U.S. Government Accountability Office, whose
standards we are statutorily obligated to follow, requires us to
assess the sufficiency and appropriateness of computer‑processed
information that we use to support our findings, conclusions, or
recommendations. We obtained financial information for CEQA
revenue and expenditures, verified the datasets, and conducted
testing of key data elements. We determined the data were
sufficiently reliable for our purposes. We also obtained data from
the department’s project tracking database that recorded the
department’s CEQA activities. Based on conversations with
the department and with staff at each of the regional offices, as well
as our own observations of the data, we determined that the project
tracking data are incomplete and that the department’s data entry
is inconsistent. However, this database is the only comprehensive
source of data the department has on its CEQA review activities
and is the source the department uses to generate reports on its
activities to the Legislature. We performed supplemental tests,
based on available information, to gain some assurance that the
data would support our conclusions and recommendations.
We recognize that the limitations in the department’s data may
affect the precision of the numbers we present. Nevertheless,
there is sufficient evidence in total to support our audit findings,
conclusions, and recommendations.
40 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2018-119 41
June 2019
APPENDIX B
The Department’s Positions and Expenditures by Funding Source
As part of an audit objective, the Legislature asked us to identify
the staffing levels and funding for each of the department’s major
program areas. Table B lists the department’s budgeted positions
and expenditures for each of the department’s seven program areas,
as well as its administration, for the 2018–19 fiscal year. The table
also identifies key revenue sources for each program area. Much of
the department’s funding comes from revenue dedicated to specific
purposes, often from fees. For example, the environmental plate
fund contains revenue from a fee paid by individuals who choose to
obtain special license plates. The Fish and Game Preservation Fund
includes a number of different fees, including hunting and fishing
license fees and CEQA filing fees.
Table B
Budgeted Positions and Expenditures by Source for the Department’s Major Program Areas
Fiscal Year 2018–19 (Dollars in Thousands)
FUND SOURCE
CALIFORNIA
FISH AND GAME TOTAL FISCAL
BUDGETED ENVIRONMENTAL FEDERAL
PROGRAM AREA GENERAL FUND PRESERVATION REIMBURSEMENTS OTHER FUNDS* YEAR 2018–19
POSITIONS LICENSE PLATE TRUST FUND
FUND BUDGET
FUND
Biodiversity
Conservation 704 $68,876 $8,179 $13,955 $14,040 $19,553 $163,925 $288,528
Program
Hunting, Fishing,
and Public Use 435 9,800 843 21,770 39,868 1,343 26,455 100,079
Program
Management of
Department Lands 370 6,878 3,322 18,640 12,200 6,525 26,579 74,144
and Facilities
Enforcement 218 33,879 2,689 4,735 39,342 3,774 8,730 93,149
Communications,
Education and 23 361 937 3,133 125 121 26 4,703
Outreach
Spill Prevention
171 288 0 151 1,627 3,049 37,082 42,197
and Response
Fish and Game
10 721 148 0 760 0 0 1,629
Commission
Administration† 142 — — — — — — —
Totals 2,073 $120,803 $16,118 $62,384 $107,962 $34,365 $262,797 $604,429
Source: Analysis of the department’s fiscal year 2018–19 enacted budget.
* Other funds includes funds budgeted for local assistance and other funds budgeted for specific purposes, such as the Salton Sea Restoration Fund and
the Hatcheries and Inland Fisheries Fund.
† Administrative costs—budgeted at $50.6 million in fiscal year 2018–19—are distributed to each of the other program areas and included in those
totals. The department allocates these costs to each program based on an internal model it develops annually.
42 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2018-119 43
June 2019
*
1
2
3
4
* California State Auditor’s comments begin on page 53.
44 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
1
1
3
CALIFORNIA STATE AUDITOR | Report 2018-119 45
June 2019
1
3
5
6
46 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
1
7
1
CALIFORNIA STATE AUDITOR | Report 2018-119 47
June 2019
8
9
48 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
CALIFORNIA STATE AUDITOR | Report 2018-119 49
June 2019
8
50 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2018-119 51
June 2019
COMMENTS
CALIFORNIA STATE AUDITOR’S COMMENTS ON THE RESPONSE
FROM THE CALIFORNIA DEPARTMENT OF FISH AND WILDLIFE
To provide clarity and perspective, we are commenting on the
department’s response to our audit. The numbers below correspond to
numbers we have placed in the margin of the department’s response.
We stand by the language we use to describe the department’s 1
challenges related to CEQA. Our report provides appropriate
context and sufficient evidence to support our report’s headings
and conclusions.
The standard we used to assess the department’s responses to 2
requests for consultation and to CEQA documents it receives was
state law and regulations. As we note on page 9, state law requires
the department to respond to all requests for consultation. We
further note on page 15 that regulations indicate that the department,
as a responsible agency, should comment on CEQA documents for
projects that it will later be asked to approve.
On page 21, we acknowledge that the department triages the CEQA 3
documents it receives because it does not have the resources to
review and respond to all of them. However, as we state on page 21,
the department does not have policies describing how its staff should
triage CEQA documents to ensure it is consistent in the kind of
projects it prioritizes.
The department’s contention that fees would significantly increase 4
if it were to meet a 100 percent response rate is premature. As we
describe beginning on page 29, the department cannot estimate the
full cost of the program or determine how many additional resources
it may need because it does not accurately track staff time related to
CEQA. The department cannot accurately assess the fee level it will
require until it can also accurately assess the resources it needs.
The department’s citation of an “acceptable standard” misdirects 5
the reader. We base the analysis in our report on the standards in
state law and regulation that, as we describe in Comment 2, state
that the department shall respond to requests for consultation
and should comment on CEQA documents. Further, as we state
on page 15, although state law does not require the department to
provide comments on every draft CEQA document in its role as
a responsible agency, regulations state that it should comment on
the adequacy of the draft environmental impact report or negative
declaration for projects that it will later be asked to approve.
52 Report 2018-119 | CALIFORNIA STATE AUDITOR
June 2019
6 The department is conflating its responsibilities under CEQA
with those of the lead agency. Whether the department responds
to a notice of preparation is entirely within its control. The fact
that the lead agency controls other parts of the process does not
absolve the department from fulfilling its responsibilities. We
note on page 15 that because the department has jurisdiction over
California’s fish and wildlife resources, its input on a project’s
impacts on sensitive habitats and species is critical. As a result,
on page 17, we conclude that when the department does not
fulfill its responsibilities, a lead agency may not be aware of
potential significant impacts to fish and wildlife resources that it
should consider.
7 The department’s response mentions ways in which it educates the
general public; however, our review, starting on page 18, focuses on
how the department’s input on specific projects during the CEQA
review process could benefit applicants for those projects later
when seeking permits from the department.
8 The department agrees with our recommendation, but adds
that it has already offered some training. However, on page 23,
we note that the conservation branch chief stated that the
department’s basic CEQA course did not describe how to complete
a review and that the department’s trainings on CEQA are not
mandatory. Neither he nor others in the department to whom
we spoke mentioned the trainings the department lists in its
response on pages 47 and 49. As we state on page 23, the current
lack of common training across all CEQA staff risks those staff
inconsistently reviewing CEQA documents and applying different
standards to those documents.
9 The department is correct that its accounting records show that
CEQA expenditures matched revenues for fiscal year 2016–17.
However, as we discuss in a note on Figure 6, the department has
not finalized its accounting for CEQA fees in fiscal year 2016–17;
thus a definitive conclusion that expenditures match revenues
is premature. Further, the department used CEQA revenues to
cover deficits in other areas through the way it has structured its
nondedicated account. On page 28, we quote the department’s
explanation that it uses surpluses from programs within the
nondedicated account to cover deficits in other programs
within that account before it uses the account’s reserves. As the
department commingles all of the funds within this account and
does not track CEQA revenues and expenditures separately,
the department cannot demonstrate it used all CEQA funds for
CEQA purposes.