CSA
Recommendations
Read the report at California State Auditor ↗
California Department of
Toxic Substances Control
The State’s Poor Management of the Exide
Cleanup Project Has Left Californians at
Continued Risk of Lead Poisoning
October 2020
REPORT 2020‑107
CALIFORNIA STATE AUDITOR
621 Capitol Mall, Suite 1200 | Sacramento | CA | 95814
916.445.0255 | TTY 916.445.0033
For complaints of state employee misconduct,
contact us through the Whistleblower Hotline:
1.800.952.5665
Don’t want to miss any of our reports? Subscribe to our email list at auditor.ca.gov
For questions regarding the contents of this report, please contact Margarita Fernández, Chief of Public Affairs, at 916.445.0255
This report is also available online at www.auditor.ca.gov | Alternative format reports available upon request | Permission is granted to reproduce reports
Elaine M. Howle State Auditor
October 27, 2020
2020-107
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As directed by the Joint Legislative Audit Committee, my office conducted an audit of the steps
taken by the Department of Toxic Substances Control (DTSC) to identify and remove lead
contamination from over 10,000 properties surrounding a former lead battery recycling facility in
Vernon, California. Lead contamination can have detrimental effects on the health of individuals
who are exposed, and in some cases can be lethal. Despite the importance of removing lead
contamination, we found that DTSC’s cleanup efforts are behind schedule.
We are particularly concerned that DTSC has not removed contaminated soil from a total
of 31 school, childcare facility, and park properties even though it had available options for
cleaning those sites. This is troubling because the children who may frequent these locations are
at particularly high risk from the negative health effects of lead. Additionally, DTSC is behind
schedule in its effort to clean 3,200 of the most contaminated properties. DTSC estimated it could
clean these properties by June 2021. However, it has not cleaned properties at its expected pace
and recently slowed its cleanup pace further due to a dispute with a contractor. At its current
pace, DTSC will not finish cleaning the most contaminated properties until more than one year
after the expected completion date. Finally, after DTSC finishes cleaning these 3,200 properties,
an estimated 4,600 properties will remain contaminated and DTSC has not established a timeline
or strategy to clean those properties.
Furthermore, the cleanup project is likely to cost hundreds of millions of dollars more than the
State has provided DTSC to date. The State has provided DTSC about $250 million to clean the
3,200 most contaminated properties. We estimate that by the time DTSC spends all of this funding,
269 of these properties will still be contaminated. The department’s poor cost estimation and
cost overruns by one of its contractors have contributed to DTSC spending more than expected
to clean the contamination. At current spending rates, we estimate that DTSC will need about
$390 million more than it has been allocated to date to completely clean all 7,800 contaminated
properties. Although the State expected it would recover its costs from Exide, in October 2020 a
federal court approved a bankruptcy settlement that leaves significant questions about the State’s
ability to obtain reimbursement for the cleanup.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
621 Capitol Mall, Suite 1200 | Sacramento, CA 95814 | 916.445.0255 | 916.327.0019 fax | www.auditor.ca.gov
iv Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
Selected Abbreviations Used in This Report
DTSC California Department of Toxic Substances Control
Exide Exide Technologies
ISE Imminent or Substantial Endangerment
ppm parts per million
TCRA Time Critical Removal Action
CALIFORNIA STATE AUDITOR | Report 2020-107 v
October 2020
Contents
Summary 1
Introduction 3
DTSC Is Behind Schedule on Its Cleanup and Has Yet to
Address Contaminated Properties That Pose a High Risk to Residents 9
The Cleanup Project Is Likely to Cost Hundreds of Millions of
Dollars More Than the State Has Provided DTSC to Date 19
Appendix A
Scope and Methodology 29
Appendix B
Sampling and Cleanup Status as of May 2020 of Properties in
the Cleanup Site 31
Response to the Audit
Department of Toxic Substances Control 33
California State Auditor’s Comments on the Response From
the Department of Toxic Substances Control 39
vi Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
CALIFORNIA STATE AUDITOR | Report 2020-107 1
October 2020
SUMMARY
Since 2015 the Department of Toxic Substances Control (DTSC) has been working to
identify and remove lead contamination from about 10,160 properties surrounding
a former lead battery recycling facility that Exide Technologies (Exide) operated in
Southern California.1 Approximately 100,000 people live in the area surrounding the
facility and are thus at risk of lead exposure, which can cause significant health problems
for vulnerable populations such as children. DTSC’s data indicate that a significant
majority of the properties—including residences, childcare centers, parks, and schools—
had dangerous levels of lead contamination. This audit report concludes the following:
DTSC Is Behind Schedule on Its Cleanup and Has Yet to Address Page 9
Contaminated Properties That Pose a High Risk to Residents
In the early stages of its cleanup effort, DTSC identified 50 properties—
including childcare centers, schools, and parks—where lead contamination
posed a particularly high risk to children who frequently spend time at
these locations. Despite the risk these properties present, DTSC has yet to
clean 31 of them. In fact, it has cleaned only one of these properties since
May 2018. In addition, DTSC has been unable to maintain the cleanup
pace it presented in its 2017 plan for cleaning the most contaminated
properties. As a result, it is significantly behind schedule and is unlikely
to meet its goal to clean the 3,200 most contaminated properties by
June 2021—extending the time that residents in the cleanup site are
exposed to dangerous levels of lead. Finally, DTSC has not established a
timeline or strategy for cleaning an estimated 4,600 remaining properties
that also have dangerous levels of contamination. Until DTSC creates a
plan for cleaning all lead-contaminated properties, stakeholders and policy
makers will have little information about the level of effort and time the
cleanup project will require.
The Cleanup Project Is Likely to Cost Hundreds of Millions of
Dollars More Than the State Has Provided DTSC to Date
Page 19
The State has already provided $251 million to DTSC to complete the
cleanup of the 3,200 most contaminated properties. However, we
estimate that DTSC will exhaust this funding before cleaning 269 of
these properties. Moreover, based on DTSC’s current spending rate, we
estimate the total cost of the cleanup project will approach
1 Our presentation of numbers throughout most of the report is based on parcels of land. However, to align our report with the
way DTSC describes the cleanup project, we use the term properties when describing our findings.
2 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
$650 million. DTSC’s estimates of per-property cleanup costs
were inaccurate because it failed to account for predictable costs,
such as inflation and payment of legally required prevailing wages.
Finally, DTSC has paid about $17 million more than it anticipated
to clean 768 properties because it did not establish adequate
protections in its agreement with its largest cleanup contractor. In
particular, it agreed to a cost structure that requires it to pay for all
cost overruns related to labor and materials instead of a fixed-price
structure that held the contractor responsible for cost overruns.
Summary of Recommendations
To ensure that it promptly and effectively addresses the risk that
lead-contaminated properties pose to children and other individuals,
DTSC should do the following:
• Immediately begin cleaning all childcare centers, parks, and schools.
• Immediately deploy sufficient resources to clean the 3,200 most
contaminated properties on schedule.
• By no later than April 2021, identify and publicize the date by which it
expects to complete its cleanup of all 7,800 contaminated properties.
• To ensure that it has sufficient funding to clean up all
lead-contaminated properties, DTSC should identify the full amount
of funding it needs to complete the cleanup of these properties.
It should submit a request for funding in time for the spring 2021
budget discussions that includes a range of funding options that spans
from funding for the full cleanup to funding for only a portion of the
remaining contaminated properties.
• To protect against the unsustainably high costs it has incurred thus
far in the cleanup project, DTSC should structure any future cleanup
contracts so that they at least partially incorporate fixed prices.
Agency Comments
DTSC expressed concern about our conclusions that it is behind
schedule to complete the cleanup of the 3,200 most contaminated
properties and that it has not developed a cleanup plan for the remaining
4,600 properties. DTSC believes that it has cleaned properties more
quickly than comparable cleanup projects and that it could not anticipate
certain factors that have slowed its rate of progress. Further, DTSC cited
a lack of funding as a reason it has not developed a plan to clean the
remaining 4,600 properties. However, DTSC concurred with and agreed
to implement all of our recommendations.
CALIFORNIA STATE AUDITOR | Report 2020-107 3
October 2020
Introduction
Background
Since 2015 the Department of Toxic Substances
Control (DTSC) has been working to identify Common Effects of Lead Poisoning
lead contamination and, where present, remove
it from about 10,160 residential properties, In babies
childcare centers, parks, and schools surrounding • Premature birth
• Low birth weight
a former lead battery recycling facility in Southern
• Slowed growth
California. About 100,000 people live in the
contaminated area and are therefore at risk of In children
exposure to lead-contaminated soil. Exposure to • Developmental delays
lead can cause serious health issues, including brain • Learning difficulties
damage, memory loss, reproductive disorders, and • Irritability
• Loss of appetite
other conditions, as the text box indicates. Even
• Weight loss
small amounts of lead can cause serious health
• Sluggishness and fatigue
problems, particularly for children, because it can
• Abdominal pain
cause developmental delays and seizures. At very
• Vomiting
high levels, lead exposure can result in death.
• Constipation
• Hearing loss
DTSC’s mission is to protect California’s residents • Seizures
and environment from the harmful effects of toxic
In adults
substances. Its responsibilities include enforcing
• High blood pressure
hazardous waste laws and restoring resources
• Joint and muscle pain
contaminated with toxic substances. To accomplish
• Difficulties with memory or concentration
its responsibilities, it has around 930 staff members
• Headache
who work at 11 offices located throughout the State. • Abdominal pain
When necessary, DTSC uses contractors to assist • Mood disorders
with cleanup of hazardous wastes. • Reproductive disorders
Source: Mayo Clinic.
Exide Technologies’ Lead Battery Recycling Facility
In 2000 Exide Technologies (Exide) acquired a 15-acre facility located in Vernon,
California. Exide processed used lead-acid batteries and other lead-bearing
materials to recover lead and other materials at this facility until 2014, when it
ceased operations to address air pollution concerns that the South Coast Air Quality
Management District (SCAQMD) had raised. DTSC’s permit history records state
that the facility accepted about 11 million used lead-acid batteries each year, from
which it recovered 100,000 to 120,000 tons of lead.
When it took over the Vernon facility in 2000, Exide assumed the previous owner’s
interim status hazardous waste permit, which DTSC’s predecessor agency had
granted in 1981, when the State first began requiring such permits. Part of DTSC’s
responsibility includes the issuance of operating permits for hazardous waste
facilities, such as the Exide facility, and their regular inspection. However, since
2007, actual monitoring of airborne emissions from the facility has been conducted
by SCAQMD. Over the next 13 years, Exide submitted at least seven hazardous
4 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
waste permit application revisions to DTSC. Exide intended these
revisions to address repeated deficiencies in its application. In 2015
DTSC notified Exide that it intended to deny Exide’s application
revision. Exide and DTSC jointly agreed that Exide would withdraw
its permit application, permanently cease operations, and close the
facility in accordance with a DTSC-approved closure plan.
In December 2016, DTSC approved Exide’s closure plan,
which described how it would shut down the facility while
protecting public health and the environment. That plan includes
decontaminating, deconstructing, and disposing of the equipment
and structures that the facility used to manage hazardous waste.
DTSC’s Identification of Lead Contamination
State law allows DTSC to take enforcement action against polluters
or take other action, such as hazardous substance removal, when
it determines that these substances may pose an imminent or
substantial endangerment (ISE) to public health, welfare, or the
environment. In November 2015, DTSC determined that pollution
surrounding the Exide facility constituted an ISE situation. The ISE
determination gave DTSC significantly more flexibility to procure
cleanup contractors than state law normally allows.
In April 2016, the Legislature approved a $176.6 million loan from
the State’s General Fund to DTSC for activities related to the
investigation and cleanup of the lead-contaminated properties in
the communities surrounding the Exide facility. DTSC determined
that an area of about a 1.7-mile radius around the facility was
contaminated because of activities from the facility—in this report,
we refer to the area as the cleanup site.2 Although the former Exide
facility is located in Vernon, the cleanup site extends into the cities
of Los Angeles, Huntington Park, Commerce, Bell, and Maywood,
as well as unincorporated Los Angeles County. Figure 1 shows the
cleanup site.
2 As of August 2020, Exide was disputing that it is responsible for lead contamination in the
residential areas near its former facility.
CALIFORNIA STATE AUDITOR | Report 2020-107 5
October 2020
Figure 1
DTSC Has Divided the Cleanup Site Into Seven Zones
.
–
SITE Boundary
24% Clean
Zone A
Zone B
31% Clean Zone C
Zone D
Zone E
29% Clean 23% Clean Zone F
Zone G
35% Clean
EXIDE FACILITY 17% Clean
19% Clean
17%
Clean
17% Clean
Source: DTSC property cleanup records.
Note: The areas within the cleanup site that are not in the labeled zones are industrial and/or commercial properties. Industrial properties are not part
of DTSC’s cleanup plan because it had ordered Exide to clean them under a separate effort.
In ISE situations, DTSC may order the responsible party to clean
up the contamination or it can do so itself or through a contractor
and seek to recover its costs from the responsible party. Here,
DTSC chose to clean up the contamination by using contractors
because Exide disputed the extent of its responsibility for the
contamination, and DTSC determined that the contamination
posed a significant threat.
As of June 2020, the State had provided nearly $260 million
to DTSC, mostly in loans from the General Fund, to clean the
lead-contaminated properties and conduct related activities at
6 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
the cleanup site. The Legislature provided these loans with the
expectation that DTSC would successfully recoup the cost of
the cleanup from Exide. However, in early 2020 Exide filed for
Chapter 11 bankruptcy, and in October 2020 a federal court
approved a bankruptcy settlement that leaves significant questions
about the State’s ability to obtain reimbursement for the cleanup.
As part of its preparation for possible cost recovery, DTSC has
been storing soil samples that it collects from each property as
evidence of contamination. It also will probably need to provide
documentation of the actions it has taken to clean properties and
the amount its cleanup contractors have charged. Figure 2 outlines
key events in the timeline of the Exide cleanup project.
Figure 2
Key Events in the Exide Cleanup Timeline
2014
March 2014
Exide ceases operations at its Vernon, California facility
to address emission concerns raised by the SCAQMD.
2015
March 2015
June 2015 The United States Department of Justice and Exide
reach an agreement requiring Exide to permanently
The State provides $734,000 and five positions August 2015 cease operations and close the facility.
to DTSC to oversee an enforcement order that The State provides $7 million in
requires Exide to investigate possible 2016 emergency funding to allow DTSC
contamination and begin cleaning properties. to perform emergency cleanup
April 2016 activities and analyze soil samples
in the neighborhoods surrounding
The State lends DTSC $176.6 million
the Exide facility.
for activities related to the
investigation and cleanup of
2017
properties contaminated with lead
in the cleanup site.
July 2017
DTSC finalizes its environmental impact report to inform decision
2018 makers and the public of potential environmental impacts from the
cleanup activities outlined in its cleanup plan. The plan indicates
that DTSC will clean 2,500 of the most contaminated properties
April 2018
with its available funding. However, the plan also indicates a
DTSC awards a contract, with some fixed-price elements and a broader goal to clean additional lead-contaminated properties.
not-to-exceed amount for the remaining elements, to its first
contractor (Contractor A). This contract is for $10.4 million to August 2018
clean up lead-contaminated soil at 215 properties. 2019 DTSC awards a second contract, with a hybrid fixed-cost
After seven amendments, this contract's value eventually and time-and-materials structure, to Contractor A for
reaches $13 million, with an expiration date of December 2019. $11.6 million to clean up lead-contaminated soil at up to
200 properties. After seven amendments, this contract's
June 2019
October 2018 value reaches $74.6 million to clean up to 1,100 properties.
State lends DTSC $24.5 million to complete the
cleanup of the most contaminated properties. DTSC awards a
2020
The State also lends it an additional time-and-materials contract to a
$50 million to clean another 700 properties. second contractor (Contractor B)
April 2020 for $82 million to clean up
lead-contaminated soil at up to
DTSC instructs Contractor B to stop work
1,610 properties.
on cleaning any further properties
because of the contractor's
greater-than-expected costs.
Source: DTSC’s cleanup plan, environmental impact report, contracts, and state appropriations.
CALIFORNIA STATE AUDITOR | Report 2020-107 7
October 2020
DTSC’s Cleanup Plan
Although the vast majority of the 10,160 properties in the cleanup site
are residential, others—such as schools and childcare centers—are
publicly owned. In July 2017, DTSC finalized its removal action plan
(cleanup plan) for cleaning the lead-contaminated properties within
the cleanup site. According to multiple DTSC staff, this effort was the
largest cleanup of its kind in California. The cleanup plan prioritizes
properties with the highest levels of lead contamination and the
greatest potential health risk to sensitive individuals, which the plan
defines as children younger than 7 years of age and pregnant women.
The department has sampled more than 8,500 properties and identified
more than 7,700 with lead concentrations over 80 parts per million
(ppm), which makes them dangerous to sensitive individuals who live
in or visit these properties. According to the assistant deputy director
of DTSC’s Exide division (assistant deputy director), DTSC plans to
address the 3,200 of these properties that have lead concentration of
300 ppm or greater, essentially prioritizing the most dangerous among
all contaminated properties. Appendix B shows a detailed breakdown
of the status of the cleanup effort as of spring 2020, including the
number of properties for which property owners have not granted
DTSC permission to sample for lead contamination.
The majority of DTSC’s cleanup activities to date have been
performed by two contractors under three separate contracts. DTSC
entered into an agreement with the first contractor (Contractor A)
in April 2018 to clean 215 properties, with an amended value of
$13 million. In August 2018, DTSC entered into another agreement
with Contractor A, which—after subsequent amendments—includes
the cleanup of an additional 1,100 properties for about $75 million.
In October 2018, DTSC hired a second contractor (Contractor B) to
clean up to 1,610 properties for $82 million. DTSC also has additional
cleanup-related contracts, including a $5.4 million contract with a
consultant to assist with project management and a $186,000 contract
with an independent auditor to provide an outside review of the
department’s use of Exide-related funds.
DTSC’s process for cleaning up lead-contaminated soil includes
multiple steps. First, it must obtain an owner’s or tenant’s permission
to sample a property’s soil. A testing crew then takes multiple soil
samples from the property to determine whether it is contaminated
and, if so, the depth of contamination. If the property is contaminated
with lead, a cleaning crew removes the contaminated soil, DTSC stores
a sample of the contaminated soil, and the cleaning crew replaces
contaminated soil with clean soil and replaces landscaping destroyed
by the removal of contaminated soil. DTSC estimates that this process
in its entirety takes about a week. Finally, DTSC offers property
owners interior cleaning of structures on the property to remove
lead-contaminated dust.
8 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
CALIFORNIA STATE AUDITOR | Report 2020-107 9
October 2020
DTSC Is Behind Schedule on Its Cleanup and Has
Yet to Address Contaminated Properties That
Pose a High Risk to Residents
Key Points
• As of June 2020, DTSC had not cleaned 31 out of 50 lead-contaminated
childcare centers, parks, and schools in the cleanup site, even though it identified
contamination at these properties as early as 2014. Its failure to use the options
available to it to clean these properties quickly has unnecessarily put the children
who may visit them at higher risk of negative effects to their mental and physical
development from lead poisoning.
• Because of a slower-than-expected cleanup pace, DTSC will likely miss its
target date of June 2021 to clean the 3,200 most contaminated properties in the
cleanup site.
• DTSC does not have a timeline or planned approach for cleaning the remaining
4,600 contaminated properties. Because it has not planned for the cleanup of
these properties, stakeholders and the Legislature lack critical information about
the time and funding DTSC will need to complete the cleanup effort.
As a Result of Its Missteps, DTSC Has Not Cleaned Properties That Pose a Significant
Threat to Residents
DTSC has not yet cleaned a high percentage of 50 of the 3,200 most contaminated
properties where it has identified lead contamination as disproportionately affecting
the residents who are at the greatest risk. DTSC’s cleanup plan identifies childcare
centers, parks, and schools as particularly sensitive-use properties because these are
property types where a large number of individuals sensitive to lead poisoning—
particularly young children—may be exposed to lead-contaminated soil. However, as
Figure 3 shows, DTSC had still not cleaned 31, or 62 percent, of these properties as of
June 2020. Further, with the exception of a single childcare center that it cleaned in
May 2020, the department has not cleaned any childcare centers, parks, or schools
since May 2018. As a result, it has continued to put the children and other at-risk
individuals who spend time at these properties at unnecessary risk of the serious
consequences of lead poisoning.
10 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
Figure 3
Certain Sensitive-Use Properties Remain Contaminated Years After DTSC Learned About Dangerous Levels of Lead
LEAD CONTAMINATION
Battery
Recycling Facility
26 3 2
CHILDCARE CENTERS PARKS SCHOOLS
Source: Analysis of DTSC’s July 2017 cleanup plan and property cleanup data as of June 30, 2020.
DTSC allowed this delay to occur despite the fact that it learned
about the contamination levels on these properties from 2014
through 2017, when it conducted soil sample testing. DTSC’s
assistant deputy director stated that schedule conflicts have
prevented DTSC from cleaning some properties, and other records
it shared with us show that some property owners were unsure
about whether they wanted to proceed with the cleaning. However,
we identified several other factors that explain the department’s lack
of progress. Most significantly, its program staff did not act to
amend existing contracts or engage new contractors
to expedite the cleanup of these properties.
Types of Bonds The assistant deputy director stated that because
some of these properties are publicly owned, state
Performance Bond: A bond that guarantees the contractor’s
law requires DTSC to use contractors that have
performance of required work.
100 percent payment and performance bonding,
Payment Bond: A bond that covers the costs of labor and/ which neither of DTSC’s existing contractors has.
or materials in the event that the contractor fails to make
The text box describes these types of bonds. State
those payments.
law requires every contractor that directly contracts
Source: State Contracting Manual. with a state agency for a public works contract to
file a payment bond for 100 percent of the contract
price, if that price exceeds $25,000. Under state
law, the contracting state agency must require
CALIFORNIA STATE AUDITOR | Report 2020-107 11
October 2020
the contractor to provide the bond and must determine whether
that bond is legally and financially sufficient. If the state agency fails
in these duties and the contractor does not pay its subcontractors
or suppliers, the subcontractors or suppliers may sue the state
agency. Because DTSC’s existing contractors do not have this level
of bonding, it could not use its existing contracts to clean childcare
centers, parks, and schools in the cleanup site. However, despite the
limits of its existing agreements, it has not amended those contracts
or found new contractors to perform this essential work.
When we asked why DTSC did not address the risk that these publicly
owned properties pose to children by promptly seeking another
contractor who could perform the work, the assistant deputy director
stated that the department had intended to use a new contractor
to clean the properties. According to the assistant deputy director,
in May 2018, DTSC created a list of publicly owned properties by
grouping all schools, parks, childcare centers, and properties with
five or more residential units. However, the assistant deputy director
stated that DTSC never secured the necessary contract because its
resources for contract solicitation and procurement were limited.
Further, she indicated DTSC was focusing on other priorities at
the time, including ramping up its residential cleanup efforts at
the cleanup site and renegotiating an existing cleanup agreement.
However, by failing to prioritize contracting for these properties to
be cleaned, DTSC placed children and other at-risk individuals in
unnecessary danger of continued exposure to lead contamination.
By failing to prioritize contracting for these
properties to be cleaned, DTSC placed
children and other at-risk individuals in
unnecessary danger of continued exposure
to lead contamination.
Moreover, DTSC misidentified the ownership of some of
these properties, thus unnecessarily delaying their cleanup. In
December 2019, DTSC staff identified that 24 childcare centers
on its May 2018 list were actually private, residential childcare
centers. Given its new understanding of their ownership status,
DTSC assigned these properties to one of its existing cleanup
contractors in December 2019. Nonetheless, its error in identifying
property ownership meant that for over a year and a half DTSC
incorrectly believed these 24 properties could not be cleaned by its
existing contractors.
12 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
Finally, DTSC has not used all available options to ensure that
it quickly cleans childcare centers, parks, and schools. Before
it substantively stopped cleanup of these types of properties in
May 2018, DTSC cleaned several under a process called a time
critical removal action (TCRA). Under a TCRA, DTSC can take
action to reduce or prevent an ISE to the public health or welfare or
to the environment resulting from the release or threatened release
of a hazardous substance. When DTSC makes a determination
about implementing a TCRA, it considers certain factors
established under federal regulation, such as the actual or potential
exposure of a hazardous substance to nearby people. If it decides a
TCRA is warranted, it can expedite the process to clean properties.
DTSC has not used all available options
to ensure that it quickly cleans childcare
centers, parks, and schools.
Early in the cleanup effort, DTSC cleaned three schools and
11 childcare centers using the TCRA process. When we asked
DTSC’s assistant deputy director why it did not use the TCRA
process to clean all contaminated childcare centers, parks, and
schools, she indicated that the average cost of cleaning these initial
properties had been above $95,000 per property, which would be
greater than the cost of a property that was cleaned without using
a TCRA. She also stated that once DTSC approved a cleanup plan
in July 2017, it decided that it was prudent to clean the remaining
properties in accordance with its plan and that it would use a TCRA
only under emergency circumstances because of the higher cost
of a TCRA. However, nearly a year after DTSC’s approved cleanup
plan, DTSC has only used a TCRA to clean 12 additional properties
from March through May 2018 after it failed to receive any bids to
perform the cleanup of these properties. Contractor A cleaned the
12 properties for $53,000 per property—44 percent less than the
earlier cleanup. Using a TCRA is thus a viable option for DTSC to
clean properties so that it can expeditiously address the ongoing
risks lead contamination poses.
DTSC believes it can complete the cleanup of the remaining
childcare centers, parks, and schools by June 30, 2021—more
than four years after it identified the last of these properties as
contaminated in April 2017. After completing preliminary work,
such as creating property design plans and conducting confirmation
soil sampling, DTSC anticipates soliciting a cleanup contractor in
late 2020. However, given the significant risks these properties pose,
CALIFORNIA STATE AUDITOR | Report 2020-107 13
October 2020
we would expect DTSC to use every option available—including
using the TCRA process—to prioritize and complete the cleanup
of these schools, parks, and childcare centers as quickly and safely
as possible. By delaying the cleanup of these properties, even for
a short time period, DTSC may be unnecessarily continuing to
endanger children and at-risk individuals.
DTSC Is Likely to Miss Its Target Date to Clean the 3,200 Most
Contaminated Properties
DTSC established a target of June 30, 2021, to clean the 3,200
most contaminated properties it identified by soil sampling at the
cleanup site, but it will not meet this target at its current cleanup
pace. As we describe in the Introduction, DTSC’s cleanup plan
prioritizes cleaning properties that have the highest levels of lead
and pose the greatest health risk to sensitive individuals. The
cleanup plan, finalized in July 2017, indicates that after an initial
two-month period during which it would clean 10 to 15 properties
per week, DTSC expected its average pace would increase to 25 to
35 properties per week. However, its average pace from March 2019
through February 2020 was only 20 properties per week. At this
pace, we estimate that it would take DTSC until December 2021 to
clean up all of the 3,200 most contaminated properties, causing it to
miss its target date by six months.
DTSC’s average cleanup pace from
March 2019 through February 2020
was only 20 properties per week.
Moreover, DTSC is highly unlikely to maintain even its 20
properties-per-week pace because of two significant and recent
developments. The first is the COVID-19 pandemic, which caused
DTSC to temporarily stop its contractors’ work at the cleanup site
in spring 2020 for about six weeks. Contractor A resumed work
in May 2020. The second is DTSC’s efforts to limit cost overruns.
In mid-April 2020, DTSC ordered Contractor B to cease all new
cleanup efforts in an attempt to control costs—a decision we
describe in detail later in this report. Without two contractors
working simultaneously, DTSC has been unable to maintain the
pace of 20 properties per week. Instead, as of mid-August 2020 it
has averaged only 16 properties per week, 20 percent slower than its
prior pace. Figure 4 shows DTSC’s actual cleanup pace compared to
its target.
14 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
Figure 4
DTSC Will Likely Miss Its Targeted Completion Date for Cleaning 3,200 Highly Contaminated Properties
5,000
4,500
Original Targeted Completion
4,000
3,500 GOAL
3,200 Cleaned Properties by June 2021
3,000
2
2
1
1
,
,
,
,
5
0
5
0
5
0
0
0
0
0
0
0
0
0
0
HISTORIC
Cleanup
Pace
of
20
Properties
Per
Week* CURRENT
Cleanup
Pace
of
16
Properties Per
Week†
June '18 Dec. '18 June '19 Dec. '19 June '20 Dec. '20 June '21 Dec. '21 June '22 Dec. '22
seitreporP
fo
rebmuN
Source: DTSC’s cleanup plan and property cleanup records.
* Pace is based on actual pace and a 12-month period through February 2020 projected forward.
† Pace is based on Contractor A’s current average pace projected forward.
In addition to the pandemic and its cease-work order, DTSC’s
assistant deputy director identified several factors that have
contributed to the cleanup’s slow pace. She explained that if
property owners do not keep their appointments, DTSC’s
contractors must delay the cleanup of those properties. In
addition, if property owners do not remove personal items from
the excavation area, such as nonoperating vehicles or debris,
the contractor may need to move the items or reschedule the
cleanup. The assistant deputy director stated that when DTSC
must reschedule a cleanup appointment, it must coordinate with
other property owners to fill the empty appointment and reassign
contractor operations to other properties, steps that slow the pace
of cleanup. Finally, she also identified that weather and difficult
terrain have slowed down the cleanup pace because they require
contractors to adjust their schedules or make changes to continue
cleaning. For example, rain may necessitate that contractors stop
CALIFORNIA STATE AUDITOR | Report 2020-107 15
October 2020
the cleanup activities or excavate in small sections that can be easily
covered. In addition, if property is not accessible to equipment
because of structures or trees, crews may need to manually remove
contaminated soil using shovels, which can be time-intensive.
However, all of these explained reasons for delays are issues that
DTSC should have been able to anticipate and factor into its cleanup
pace estimates. For example, DTSC should have been aware that
certain times of year have greater rainfall, and thus it should have
accounted for weather when determining its target cleanup pace.
Moreover, problems such as uncooperative property owners and
difficult terrain would likely affect similar cleanup efforts and should
have been possible to anticipate. The cleanup plan states that DTSC
calculated its expected pace based on its prior experiences cleaning
properties within the cleanup site and its consultations with the U.S.
Environmental Protection Agency (EPA) about similar projects in
other states. However, when we asked the assistant deputy director
for the data from prior DTSC cleanup efforts, she stated that her
department did not have any such data and that the prior cleanup
efforts had progressed at a slower pace than 25 to 35 properties per
week. Further, DTSC shared multiple examples of the correspondence
it had with the EPA. The correspondence related to cleanup pace was
limited to a handbook on lead contamination at residential sites that
contained only a single reference to the pace at which a cleanup effort
could potentially progress. Specifically, the handbook indicates a pace
of 800 properties per year—an average of 15 properties per week—
is possible. That pace is far below DTSC’s published estimate of
how fast it could clean properties. DTSC’s lack of evidence for its
estimated cleanup pace leads us to conclude that it had little basis for
publicizing that it could clean 25 to 35 properties per week.
DTSC’s lack of evidence for its estimated
cleanup pace leads us to conclude that it had
little basis for publicizing that it could clean
25 to 35 properties per week.
In addition to its failure to anticipate the predictable factors that
would slow the progress of its cleanup, DTSC also did not enforce
its requirement that contractors maintain a minimum cleanup pace.
DTSC publicly estimated that it could achieve a pace of 25 to 35
properties per week before contracting with either of its two major
cleanup contractors. Those cleanup contracts require each contractor
to employ a project manager whose responsibilities include ensuring
the use of sufficient staff and cleanup crews to achieve the expected
16 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
pace. However, DTSC has not enforced this requirement.
According to the assistant deputy director, DTSC does not want
to dictate the time necessary for a contractor to clean a property
because it considers the contractor the field expert that is best
situated to make such determinations. However, without enforcing
the required performance standard, DTSC’s options for ensuring
that the overall cleanup project remains on schedule are limited.
When it does not use all available options to ensure that cleanup
of lead contamination progresses as quickly as possible, DTSC
places all residents in the cleanup site at risk of the negative effects
of prolonged exposure to lead. As we describe in the Introduction,
these effects can include serious and debilitating health conditions.
Unless it significantly increases its cleanup pace, DTSC will leave
many properties contaminated for a longer period of time than it
originally projected. The continued presence of high concentrations
of lead threatens the health of these properties’ residents and
visitors. To increase its cleanup pace, DTSC will need to make two
key changes to its approach to the cleanup effort. Most importantly,
it will need to ensure that it has sufficient contracted staff working
on the project. Before DTSC ordered Contractor B to cease work,
the contractor had cleaned an average of 14 properties per week.
DTSC will need to find an alternative way to clean these properties,
such as hiring another contractor or ordering Contractor A to use
additional crews. It also needs to hold Contractor A and any future
contractors to an expected pace of properties cleaned per week.
Unless it significantly increases its cleanup
pace, DTSC will leave many properties
contaminated for a longer period of time
than it originally projected.
The assistant deputy director acknowledged that DTSC has the
authority to monitor whether contractors meet the expected
cleanup pace. However, she indicated that the pace may be affected
by factors unrelated to contractor performance, such as DTSC’s
responsibility to ensure that properties are scheduled and prepared
for excavation and a lack of cooperation from property owners. She
also asserted that as the list of contaminated properties becomes
shorter, DTSC will find it harder to maintain a pool of available
properties to clean. These factors are poor reasons for failing
to enforce a performance standard. For example, DTSC could
ensure that its contracts clearly explain what factors are beyond a
contractor’s control with regard to the pace of cleanup. Further, our
CALIFORNIA STATE AUDITOR | Report 2020-107 17
October 2020
analysis—described in more detail below—shows that it is likely to be many
years before the list of contaminated properties would grow so short as to
make it difficult to keep a contractor busy. By monitoring its contractors,
DTSC can better ensure that they provide sufficient staff and crews to clean
contaminated properties in a timely manner.
Finally, after we informed DTSC of our conclusion that it would be
unable to meet its targeted deadline for cleaning the most contaminated
properties, DTSC provided us with a comparison it made between this
cleanup effort and cleanup efforts in other states that it considered most
comparable. DTSC asserted that this comparison showed that its cleanup
effort has progressed at fast rates when compared to those other projects.
DTSC acknowledged that it only very recently compiled this comparison to
other projects and that it was not considered when it originally developed
its pace estimate of at least 25 properties cleaned per week. However,
this comparison does not provide an explanation for why DTSC has
not achieved its anticipated cleanup pace. When considering the largest
comparable project in DTSC’s analysis, the comparison shows that DTSC
has cleaned more total properties than the other cleanup project when
compared at similar points in their project lifetime. The comparison also
shows that—over the course of a longer period of time—the other large
cleanup project cleaned more properties on average per month than
DTSC’s cleanup project has achieved over its shorter lifetime.
DTSC Has No Timeline or Planned Approach for Cleaning an Additional
4,600 Contaminated Properties
DTSC does not yet have a timeline or planned approach to clean all of the
properties contaminated with lead. Its cleanup plan states that DTSC will
identify the soil lead concentration levels at all properties in the cleanup site
and then clean each that has a soil lead concentration level above 80 ppm.
A cleanup based on this level would protect the health of children and
other at-risk individuals. However, DTSC’s current cleanup efforts—which
we describe in the previous two sections—have been focused only on
3,200 of the most contaminated properties, which generally have either an
average lead concentration of 300 ppm or greater based on a representative
soil sampling or a lead concentration of 1,000 ppm or greater based on
a single sample. We estimate an additional 4,600 properties have a lead
concentration of 80 ppm to 299 ppm that will require cleanup.3 These
properties will remain contaminated at the end of DTSC’s initial effort.
3 DTSC has identified an additional 4,199 properties with lead concentrations of 80 ppm to 299 ppm. However,
it has not yet sampled 1,604 properties in the cleanup site. DTSC has permission to sample 454 of these
properties, while the owners of the remaining 1,150 properties have not provided access. In the past, DTSC
has determined that about 10 percent of the properties it tests do not require cleanup. Therefore, we
estimate that 410 of 454 properties will require cleanup, for a total of about 4,600 properties. We did not
include an estimate for the remaining 1,150 properties because it is unknown whether the property owners
will ever provide access to sample their soil to determine whether it is contaminated.
18 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
According to the assistant deputy director, DTSC has not
developed a financial plan or a timeline for cleaning the remaining
4,600 properties. Its failure to complete these tasks has reduced the
transparency of the cleanup effort. Without such plans, the Legislature
and the public lack the information necessary to easily understand the
full scope of the cleanup effort. In fact, we found only one instance
when DTSC publicly indicated that more than 7,000 properties
have a soil lead concentration level above 80 ppm—a legislative
committee hearing in 2018. Other than that acknowledgement, DTSC
has focused its public statements on the initial 3,200 properties
that it prioritized for cleanup. By concentrating its focus on these
properties only, DTSC has restricted the discussion about the speed
of its cleanup efforts to a subset of the entire cleanup site. In reality,
full remediation of the cleanup site is likely to extend for many years
beyond the period DTSC has emphasized.
Our calculations show that if DTSC maintains its current pace
of 16 properties per week, it will not complete its cleanup of the
3,200 properties in its initial cleaning effort until August 2022. At
that same pace, it will take until February 2028 to clean the additional
4,600 contaminated properties. We are concerned that if DTSC does
not take action now to increase the pace of its cleanup efforts and
to plan for cleaning all contaminated properties, lead poisoning will
continue to pose a danger to children and other at-risk individuals in
the cleanup site for many years to come.
Recommendations
To ensure that it minimizes the exposure of children and other at-risk
individuals to lead contamination, DTSC should immediately solicit
a contractor to clean the 31 remaining childcare centers, parks, and
schools. It should use the TCRA process to expedite this cleanup
if necessary.
To ensure its ability to clean as many lead-contaminated properties
as possible in a timely manner, DTSC should immediately begin
soliciting an additional contractor to clean properties within the
cleanup site. It should include performance standards for the pace
of cleanup in its existing and future cleanup contracts.
To ensure that the public and policy makers have the information
they need to make informed decisions, DTSC should, by no later
than April 2021, identify and publicize a date by which it expects to
complete cleanup for all properties that meet or exceed the standard
for lead contamination of 80 ppm identified in DTSC’s cleanup plan.
It should post this information on its website and, at least every
six months, publish an update that indicates whether it is on track to
meet that expected completion date based on its rate of progress.
CALIFORNIA STATE AUDITOR | Report 2020-107 19
October 2020
The Cleanup Project Is Likely to Cost Hundreds
of Millions of Dollars More Than the State Has
Provided DTSC to Date
Key Points
• Without additional funding, DTSC will be unable to clean about 8 percent—
269 out of 3,200—of the properties it estimated it could clean with the existing
$260 million in funding the Legislature has provided for the cleanup efforts.
At current spending rates, we estimate DTSC will need to spend $650 million to
completely clean all of the 7,800 contaminated properties.
• DTSC used outdated and inaccurate data when initially estimating its cleanup
costs. Because of the flaws in its approach to creating this estimate, the
Legislature and public have not received from DTSC accurate information about
the likely cost of the project.
• DTSC’s costs to clean properties have been higher than it expected in part
because it did not establish adequate protections when it entered into its largest
cleanup contract. As a result, it paid $17 million more than it anticipated to clean
the first 768 properties under this contract.
DTSC Will Likely Need an Additional $390 Million to Complete the Cleanup Project
The funding that DTSC has received to date from the State will not allow it to clean
as many properties as it projected. In August 2015, the State provided $7 million to
DTSC to analyze soil samples and perform emergency cleanup activities. In July 2017,
DTSC estimated it could clean 2,500 of the most contaminated properties using the
funding available to it at the time, which consisted of $176.6 million the Legislature
lent it from the General Fund. Since then, at DTSC’s request, the Legislature
provided an additional $24.5 million to clean these same 2,500 properties because
of greater-than-anticipated costs. Further, in 2019 the State lent DTSC $50 million
to clean an additional 700 properties. These allocations and estimates bring the
total amount of funding the State has provided to DTSC to about $260 million,
and the total number of properties that DTSC has estimated it can clean to 3,200.
Nonetheless, our analysis indicates DTSC will lack the funding to clean 269 of the
properties it planned to clean, as Figure 5 shows.
20 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
Figure 5
DTSC Will Not Have Enough Funding to Clean 269 Properties It Planned to Clean
DTSC Estimated It Could Clean 3,200 Properties with about $251,000,000 . . .
269
But of these properties will remain
contaminated when DTSC exhausts this funding.
Source: Analysis of DTSC cleanup plan, budget change proposals, and property cleanup data.
We project that DTSC will require an additional $21 million to finish
cleaning the 3,200 properties it estimated it could clean. DTSC’s
assistant deputy director agrees that DTSC will lack the funding
necessary to clean all these properties. In fact, the calculations she
shared with us suggest that it will require even more additional funding
than our estimate of $21 million. However, she stated that she based
her method for determining how many properties DTSC will be able to
clean with existing funding on information that is subject to change.
The additional $21 million to complete the cleaning of the
3,200 properties is small compared to the cost to clean the full number
of properties that remain contaminated. Using DTSC’s actual costs
to date, we calculated that total cleaning costs will be $630 million,
as Figure 6 shows.4 Moreover, the soil sampling costs brings the
total project cost to almost $650 million. As we discuss previously,
the Legislature has provided $260 million to DTSC for cleaning the
lead-contaminated properties and performing related activities.
As of May 2020, DTSC had spent $139 million of this funding on
cleaning and other related activities, such as sampling soil for lead
contamination and operating a statutorily mandated jobs program
4 In this report, the total number of properties we discuss and the related cost calculations do not
include two types of properties: parkways—narrow strips of land typically found between sidewalks
and streets—and industrial facilities. As of June 2020, DTSC did not have sufficient information to
enable us to calculate cost estimates for these types of properties.
CALIFORNIA STATE AUDITOR | Report 2020-107 21
October 2020
to help local residents gain employment assisting with the lead
cleanup, leaving DTSC with $121 million in remaining funding.
Pending any action by a court that requires Exide to pay for cleanup
costs, we estimate that the State will need to provide approximately
an additional $390 million to DTSC to complete the cleanup project.
Figure 6
DTSC Cleaning the Entire Cleanup Site Will Cost About $630 Million
COST ESTIMATE
Cost to date to clean
1,529 properties............. $122,000,000
Cost to clean remaining*
6,375 properties............ $508,000,000
TOTAL............................ $630,000,000
Department of
TOXIC SUBSTANCES CONTROL
Source: Analysis of DTSC’s financial reports and property cleanup data.
* Cost figures include DTSC’s costs to clean properties along with its administrative costs, operating a statutorily mandated jobs program, and cost
recovery efforts. It does not include soil sampling costs, which will total $18 million and bring total project cost, to almost $650 million.
22 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
DTSC Based Its Cleanup Cost Estimates on Outdated and
Inaccurate Data
In 2016 DTSC believed that each lead-contaminated property
would cost $50,000 to clean. However, it significantly
underestimated its actual cleanup costs. That same year, the State
lent DTSC $176.6 million for activities related to the cleanup,
including the cleaning of lead-contaminated properties. By 2018
DTSC’s per-property estimate had risen to $60,000 to $80,000,
depending on the property type. As of June 2020, DTSC’s actual
average per-property cost was almost $64,000.
In 2016 DTSC believed that each
lead-contaminated property would
cost $50,000 to clean, but it significantly
underestimated its actual cleanup costs.
DTSC’s initial method for estimating the project’s likely costs was
flawed and shortsighted. It based its estimate on fiscal year 2015–16
contractor costs, including cleanup work Exide paid for under a 2014
legal agreement between DTSC and Exide in which Exide agreed
to clean 39 properties. However, although DTSC is the State’s toxic
cleanup oversight entity, it did not verify that its own costs would be
similar to Exide’s. Moreover, it did not account for predictable costs
it would incur, such as payment of prevailing wages to contracted
laborers, inflation, and the need to store soil samples so that the
State could effectively recover its costs from Exide.
According to DTSC’s deputy director for its Site Mitigation and
Restoration Program, no one at the department knew how long
the project would take, and it gave its best cost estimate available
at the time. However, we expect that as the State’s lead agency for
toxic cleanup activities, DTSC would have the expertise to know
the cost of these activities and that its cleanup cost estimate would
take these activities into consideration. DTSC’s failure to do so
is a significant lapse in judgment. Because it failed to accurately
estimate per-property costs in 2016, it had to ask for additional
funding in 2019, which the State provided. The table shows the
factors that DTSC used to explain why it needed additional funding
in 2019 and our assessment as to whether it could have reasonably
anticipated them when developing its original estimated cost.
CALIFORNIA STATE AUDITOR | Report 2020-107 23
October 2020
Table
DTSC Did Not Include Foreseeable Key Factors in Its Initial Per-Property Cost Estimate
FACTORS DTSC USED IN
FORESEEABLE IN 2016?
2019 TO JUSTIFY ADDITIONAL FUNDING
1. Prevailing wages under the project labor YES. DTSC’s cleanup contracts are subject to certain statutory provisions that require paying
agreement (PLA), a collective bargaining prevailing wages.
agreement with the Los Angeles/Orange
Counties Building and Construction Trades
Council. The PLA increased wage rates for
project work.
2. Inflation. YES. DTSC knew the project would last for multiple years.
3. Change in anticipated contract type, from No. DTSC was anticipating a fixed-price contract. After an extended solicitation process, it agreed
fixed-price to time-and-materials. to an $82 million time-and-materials contract. Fixed-price contracts pay vendors a specified
amount for work performed, whereas vendors charge for actual labor and materials used with
time-and-materials contracts.
4. Performance and payment bonds. YES. DTSC should have been aware that payment bonds were required by law for certain public
works contracts.
5. Soil sample storage costs YES. DTSC knew that the State would likely be pursuing cost recovery and should have known
that retaining evidence of contamination would be integral to that effort.
6. Project manager YES, given the size and scope of the project.
7. Financial auditor YES, given the size and scope of the project.
Source: Analysis of DTSC’s 2019 budget change proposal (approved).
Because it did not independently verify whether its cleanup costs
were likely to be similar to Exide’s, DTSC inaccurately estimated
both the cost it would incur to clean each property and the overall
cost of the cleanup. As we indicate previously, DTSC is certain
to need additional money to finish the cleanup project. Further,
in light of the State’s recent budgetary constraints associated
with the COVID-19 pandemic, it will be important for DTSC to
provide decision makers a range of options for funding additional
cleanup activities. Providing accurate estimates of its remaining
costs is critical to informing the Legislature’s decision on whether
to approve this additional funding. If DTSC currently lacks the
necessary expertise, it should contract for assistance in making
accurate and complete cost estimates.
DTSC Did Not Ensure That Its Largest Cleanup Contract Included
Adequate Protections Against Cost Overruns
As we previously explain, DTSC’s costs to clean properties have
been higher than it expected. This increase in costs is partially
attributable to the structure of DTSC’s largest cleanup contract,
which is the project’s only active cleanup contract that is over
budget. In October 2018, DTSC entered into an $82 million
agreement with Contractor B to clean up to 1,610 residential
properties for an average expected per-property cost of about
24 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
$51,000. However, by April 2020—over a year after it began work—
Contractor B’s per-property costs averaged about $73,000, more
than 40 percent higher than it originally estimated. DTSC projects
the per-property cost to increase to $81,000 because Contractor B’s
billing for the properties has not yet been finalized. In contrast,
Contractor A’s per-property costs have averaged about $53,000. As a
result of Contractor B’s high costs, DTSC paid $17 million more than
it anticipated to clean the first 768 properties under this contract.
We find it troubling that DTSC awarded this large cleanup contract
to Contractor B given that Contractor B had already shown it could
not clean properties within expected costs. In 2015 DTSC entered
into an agreement with Contractor B for work related to the Exide
cleanup that, after two amendments, totaled $5 million to clean
100 properties, for an average expected per-property cost of $50,000.
However, Contractor B ultimately cleaned only 76 properties for
the $5 million, with an average per-property cost of $66,000—a
32 percent increase over what DTSC had expected. Nonetheless,
three years later, DTSC awarded Contractor B an $82 million
contract for an estimated per-property cost that was essentially the
same as in its previous contract.
According to the assistant deputy director, she did not think
Contractor B’s bid to clean properties at an average of $51,000 per
property was achievable, but DTSC awarded the contract because
Contractor B submitted the lowest bid for the job. She also stated
that because Contractor B had already done some cleanup work
and knew more about the project than the other bidders, DTSC
concluded its bid was likely to be more informed. However, under
its ISE authority, DTSC was not bound to offer the contract to the
lowest responsible bidder; in fact, the State does not require any
agencies to do so in all procurement situations. If DTSC had used
other criteria for its selection, such as selecting the vendor offering
the best value rather than the lowest price, it would have provided
itself greater flexibility in choosing a contractor.
Once DTSC decided to use Contractor B for
a second contract, an alternate contract cost
Types of Contracts
structure could have helped the department control
costs. The agreement DTSC entered into allows
• Fixed-price contract: Provides a total price for all work
Contractor B to charge the department for the
to be performed under a contract. This price is not
subject to adjustment based on a contractor’s cost to full costs of its hourly labor and the materials it
perform the work. uses to clean properties. This structure—called a
time-and-materials contract—requires an agency
• Time-and-materials contract: Provides for actual labor
to pay for any greater-than-expected resources
hours at specified fixed hourly rates plus actual cost for
a contractor uses, as the text box shows. Best
materials.
practices for managing public contracts indicate
Source: Federal Acquisition Regulations.
that a fixed-price contract—in which an agency
pays a contractor a specified amount for work
CALIFORNIA STATE AUDITOR | Report 2020-107 25
October 2020
performed—is preferable to a time-and-materials contract, which an
agency should use only when no other contract type is suitable. Under
a fixed-price contract, a contractor is responsible for paying greater-
than-anticipated costs, which would have protected DTSC against
Contractor B’s cost overruns.
DTSC’s time-and-materials agreement allowed Contractor B to use
techniques to complete its tasks that were not cost-effective. According
to the assistant deputy director, one example of an unnecessary but
allowable cost is the manner in which Contractor B stored excavated
soil before hauling it from a work site. Contractor B stored the excavated
soil in a container that had to be moved around a property several times
by a forklift operator—who incurred labor wages each time—rather
than placing a container on the street for the duration of the cleanup.
According to the assistant deputy director, DTSC’s Contractor A uses
the latter approach, but DTSC’s contract did not prohibit Contractor B’s
more labor-intensive and costly method. She asserted that Contractor
B’s approach is an acceptable industry technique for cleaning properties
even though it adds to the labor cost of a property’s cleanup.
DTSC realized within a few months that
Contractor B’s costs were problematic and took
several steps to try to control its costs.
A fixed-price contract would have encouraged Contractor B to take
steps to control the cost of its cleanup activities. DTSC realized within a
few months that Contractor B’s costs were problematic and took several
steps to try to control its costs. According to the assistant deputy
director, DTSC anticipated higher-than-average costs in Contractor B’s
first few months on the job because of start-up costs. However, these
costs did not flatten out as DTSC expected. In April 2019, DTSC first
raised the higher-than-expected costs as a problem with Contractor B,
and over the next six months, DTSC repeatedly asked Contractor B
to reduce its costs. Further, in March 2019, DTSC hired a consultant
for $5.4 million to help control Contractor B’s costs by, among other
tasks, providing technical assistance in reviewing its invoices and
assisting the DTSC field oversight staff with overseeing its work on-site.
Finally, in July 2019, DTSC attempted to renegotiate with Contractor B
the contract’s time-and-materials cost structure. However, following
its efforts to introduce fixed price elements, DTSC abandoned its
negotiation effort in February 2020. In April 2020, DTSC instructed
Contractor B to cease cleanup work and focus only on completing
administrative tasks for the properties it had already cleaned.
26 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
DTSC explained that the time-and-materials agreement was the
best possible contract agreement it could sign when it needed a
contractor to clean properties. Before entering into an agreement
with Contractor B, the department attempted to negotiate with
potential vendors for a price structure that would have included
more fixed-price elements. However, these negotiations failed.
According to an attorney for DTSC, potential contractors were
hesitant to accept a fixed-price structure without several conditions
that—in DTSC’s estimation—effectively undermined the fixed-price
elements of the proposed contracts. For example, one vendor
told DTSC that it would not submit a bid because of DTSC’s
requirement for a maximum total price. In light of these failed
negotiations, DTSC’s solicitation for the agreement it obtained
with Contractor B did not propose a fixed-price agreement.
Rather, the cost sheet that DTSC asked bidders to complete
indicates that it was seeking a contract that was primarily based on
a time-and-materials cost structure.
If DTSC was unable to enter into a fully fixed-price contract, other
alternatives were available to it. Specifically, two months before it
executed the time-and-materials agreement with Contractor B, the
department entered into a smaller contract with Contractor A that
includes a mix of fixed and unit prices. If vendors were unwilling to
enter into a fixed-price agreement, DTSC could have considered a
hybrid structure that included fixed costs for some elements—such as
the administrative documentation steps required to finalize a property
as cleaned—and time-and-materials costs for other elements. The
assistant deputy director agreed that it would make sense to use such
a hybrid contract structure. Alternatively, DTSC could have sought
a smaller agreement to clean fewer properties. Doing so may have
limited the risk that potential contractors perceived in entering into a
cleanup agreement with so many unknowns.
Because its agreement with Contractor B did not include adequate
cost protections, DTSC has spent more than it expected to clean
fewer properties than it had planned. As a result, DTSC now has
less funding to secure another contractor to continue the cleanup.
If DTSC does solicit for a new contract, it will be essential for
it to negotiate an agreement that includes strong controls on
per-property cleaning costs.
CALIFORNIA STATE AUDITOR | Report 2020-107 27
October 2020
Recommendations
To ensure that it has sufficient funding to clean up all
lead-contaminated properties in the cleanup site, DTSC should do
the following:
• Identify the full amount of funding it needs to complete the
cleanup of the 3,200 most contaminated properties and the
remaining 4,600 contaminated properties. It should submit a
request for funding in time for spring 2021 budget discussions
that includes a range of funding options that spans from funding
for the full cleanup to funding for only a portion of the remaining
contaminated properties.
• Immediately revise its cost estimation methods to encompass the
factors that it now knows will affect its overall costs. If needed,
it should contract for expertise in determining accurate and
complete estimates of the remaining cleanup cost.
To protect against the unsustainably high costs it has incurred thus
far in the cleanup project, DTSC should structure its future cleanup
contracts to at least partially incorporate fixed prices.
We conducted this performance audit in accordance with generally accepted government auditing
standards and under the authority vested in the California State Auditor by Government Code 8543
et seq. Those standards require that we plan and perform the audit to obtain sufficient, appropriate
evidence to provide a reasonable basis for our findings and conclusions based on the audit objectives.
We believe that the evidence obtained provides a reasonable basis for our findings and conclusions
based on our audit objectives.
Respectfully submitted,
ELAINE M. HOWLE, CPA
California State Auditor
October 27, 2020
28 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
CALIFORNIA STATE AUDITOR | Report 2020-107 29
October 2020
Appendix A
Scope and Methodology
The Joint Legislative Audit Committee (Audit Committee) directed
the California State Auditor to review DTSC’s activities related to the
cleanup of lead soil contamination in the area surrounding the former
Exide facility located in Vernon, California. The Audit Committee
specifically requested that we review DTSC’s contracting practices
and its costs and time frames to complete the cleanup of lead-
contaminated properties. The table below lists the objectives that the
Audit Committee approved and the methods we used to address them.
Table
Audit Objectives and the Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, rules, and Reviewed relevant laws, regulations, rules, policies, procedures, and best practices related
regulations significant to the audit objectives. to the Exide cleanup project.
2 For the contracts that DTSC has executed for • Reviewed DTSC’s cleanup contracts to identify anticipated costs per property.
cleanup activities, determine the following: • Reviewed DTSC contractors’ billing and DTSC payment records to identify the cleanup
a. Whether the cleanup cost per property cost per property for each of its Exide-related contracts.
varies between contracts, the causes for • Reviewed contract documentation and interviewed key personnel to determine the
any such differences, and whether such reasons that cleanup costs per property for DTSC’s Exide-related contracts differed and
differences are reasonable; if not, identify whether these differences were appropriate and supportable.
actions DTSC could take in the future to
• Reviewed comparable site mitigations and interviewed DTSC and EPA staff to identify
prevent cost differences.
major factors that determine per-property cleanup costs. We found that size of
b. Which major factors, apart from parcel size, property, depth of excavation, and need for transportation of contaminated soil were
determine the per-property cleanup costs. major cost factors.
c. Whether DTSC complied with relevant • Reviewed all of DTSC’s active Exide cleanup contracts to determine whether it awarded
state contracting rules in awarding cleanup them in compliance with state requirements. Because state law exempts DTSC from
contracts. If DTSC did not comply, identify many state contracting requirements in response to hazardous waste mitigation, we
the major reasons why not. did not identify any noncompliance with state requirements for awarding contracts.
d. What actions DTSC has taken to avoid • Reviewed all of DTSC’s active Exide cleanup contracts to determine whether its cleanup
contractors exceeding contract amounts. contract payments have exceeded original contract amounts.
e. Whether DTSC’s administrative costs for • Interviewed DTSC staff to identify what actions the department has taken to avoid
oversight and administration of the contracts contract cost overruns.
are consistent with its actual expenses.
• Identified DTSC’s costs for the Exide cleanup that do not directly relate to its cleanup
contracts. These other costs totaled $35 million as of May 2020. DTSC did not track
these costs in a manner that allowed us to identify the portion specific to its oversight
and administration of the cleanup contracts.
3 Evaluate DTSC’s per-property cleanup cost • Reviewed DTSC’s cost estimates and comparable site mitigations and interviewed DTSC
estimates. Determine what factors contributed staff to determine the reasonableness of its per-property cleanup cost estimates.
to increases in cost estimates in 2018 and • Reviewed DTSC’s budget change proposals to identify the factors it determined to have
whether those factors are consistent with the contributed to its cost estimate increases in 2018.
reasons cited in DTSC’s budget documents.
• Reviewed DTSC’s cleanup contracts and budget change proposals and interviewed
Determine whether the magnitude of the
DTSC staff to determine whether the magnitude of its contracts or additional causes
contracts was a factor in the increase in
were factors in the increase in per-property cleanup costs.
per-property cleanup costs. To the extent
possible, determine whether DTSC’s current • Interviewed DTSC staff to obtain their perspectives on whether DTSC’s cost estimates
per-property estimates will further increase. will further increase.
continued on next page . . .
30 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
AUDIT OBJECTIVE METHOD
4 Determine when DTSC anticipates completion • Reviewed DTSC’s cleanup plan and budget change proposals to identify its time frames
of the Exide cleanup efforts of different kinds for the completion of different types of properties within the cleanup site.
of properties, such as commercial properties • Reviewed property cleanup data from DTSC’s property database and interviewed DTSC
and private residences, and assess the staff to identify factors that contributed to the duration of the cleanup efforts. Assessed
reasonableness of the projected time frames. the completeness and accuracy of DTSC’s property database and determined that the
Specifically, identify the factors that contributed information in the database was sufficiently reliable for our purposes.
to the duration of the cleanup efforts.
• Analyzed the reasonableness of DTSC’s time frames to determine whether it is likely to
meet its expected deadline of June 2021 to clean the most contaminated residences
and all contaminated childcare centers, parks, and schools.
5 Determine the total expected cost of the Exide • Reviewed state and departmental financial reports. We compared the amounts the
cleanup efforts, including actual costs so far State has lent to DTSC and the amount DTSC has spent thus far for the Exide cleanup.
and, to the extent possible, the estimated cost • Projected the expected remaining cleanup costs for residences, childcare centers, parks,
of expected remaining cleanup efforts. and schools based on DTSC’s actual prior costs and number of properties cleaned.
6 Determine whether there are additional steps Reviewed the contracts DTSC holds for cleanup of contaminated properties to determine
that DTSC can take to improve the efficiency of the available options under these contracts for DTSC to accelerate the speed of cleanup
the Exide cleanup process. efforts.
7 Review and assess any other issues that are • Contacted the Office of the Attorney General to inquire about the status of the State’s
significant to the audit. cost-recovery efforts.
• Reviewed DTSC’s outreach activities and interviewed DTSC staff to determine the
sufficiency of and adherence to DTSC’s Public Participation Plan. The plan includes
informing affected communities about the cleanup plan and identifies key community
stakeholders, local governments, nonprofit organizations, legislative offices, and
other agencies. We found that DTSC conducted sufficient outreach efforts to the
affected communities.
• Reviewed the status of Exide’s permit application since 2000 and DTSC’s actions in
response to the application.
Source: Analysis of Audit Committee’s audit request number 2020-107, state law, and information and documentation identified in the column
titled Method.
CALIFORNIA STATE AUDITOR | Report 2020-107 31
October 2020
Appendix B
Table B
Sampling and Cleanup Status as of May 2020 of Properties in the Cleanup Site
SOIL SAMPLING STATUS PROPERTIES
Sampled 8,555
Not sampled* 1,604
TOTAL PROPERTIES 10,159
CLEANUP STATUS PROPERTIES
Cleaned by DTSC 1,529
Cleaned by Exide 186
Cleaned by Los Angeles Unified School District 49
Remaining to be cleaned† 6,375
Total properties needing cleaning 8,139
No Permission to sample/clean 1,150
Sampled and did not need cleaning‡ 870
Total properties without permission to clean or not needing cleaning 2,020
TOTAL PROPERTIES 10,159
CLEANUP BY PRIORITY PROPERTIES
Cleaned before implementation of DTSC’s cleanup plan 330
Prioritized for cleanup 3,200
Additional contaminated properties needing to be cleaned to meet 4,609
DTSC’s target
Total needing to be cleaned 8,139
Total properties not needing cleaning or without permission to clean 2,020
TOTAL PROPERTIES 10,159
Source: DTSC property database.
* For 1,150 properties, owners have not granted DTSC permission to sample the soil and determine the lead contamination level. DTSC has permission
to sample the remaining properties but has not yet done so.
† Includes an estimate of the number of unsampled properties with permission to sample that will likely require cleaning.
‡ Includes an estimate of the number of unsampled properties with permission to sample that will likely not require cleaning.
32 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
CALIFORNIA STATE AUDITOR | Report 2020-107 33
October 2020
October 7, 2020
Elaine M. Howle, CPA*
California State Auditor
621 Capitol Mall
Suite 1200
Sacramento, California 95814
Dear Ms. Howle:
The Department of Toxic Substances Control (DTSC) appreciates the opportunity to respond to
the findings and recommendations in the California State Auditor’s (CSA) Audit Report. DTSC
would like to thank you and your staff for the time and effort dedicated to conducting this
audit. We would also like to thank Assembly Member Santiago for requesting this audit.
The State of California made a strong commitment to immediately help people who live around
the former Exide facility by jumpstarting a cleanup while DTSC worked to hold Exide
accountable to finish the cleanup it was responsible for performing. The State provided
approximately $250 million for DTSC to conduct cleanups at up to 3,200 of the most heavily‐
contaminated parcels. Without this commitment, communities would have been forced to wait
for cleanups to commence.
DTSC appreciates the insights gained from discussions with your staff and from your audit’s
findings and recommendations. We believe this process provided DTSC with information we
will use to better serve the people who live around the former Exide facility in Vernon,
California. This is especially important given that only one other site in the nation exceeds the
size of DTSC’s residential cleanup, which is the largest, most logistically complex residential
cleanup project the state of California has ever undertaken.
DTSC concurs with the recommendations in the audit report and, as described below, has
started to implement some and will implement all of the audit’s recommendations. The 1
following provides our specific responses to several issues in the audit.
DTSC has Begun to Implement Some and Will Implement All Recommendations
* California State Auditor’s comments begin on page 39.
34 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
As described below, DTSC has begun to implement some of the audit’s recommendations and
will implement all additional recommendations.
2 DTSC has overseen the cleanup of 17 daycare centers and seven schools. DTSC has
inspected all other facilities and verified that barriers to soil, such as mulch or grass, are
present at all remaining facilities.
In response to your recommendations, we have undertaken the procurement process
for Time Critical Removal Actions (TCRA) to clean up the two remaining publicly‐owned
daycare centers, two private schools and three parks.
At the 19 remaining daycare centers, we have directed our cleanup contractor to
prioritize the facilities for cleanup. We have initiated the cleanup process at eight of
these facilities. Three have declined DTSC’s request to conduct a cleanup. We are
conducting outreach needed to initiate the cleanup process at the eight remaining
facilities.
DTSC has increased our outreach efforts by deploying our consultants to get additional
properties signed up for cleanups and increasing the number of cleanup crews to clean
up the most contaminated properties.
DTSC has already tasked a team to work on updating our engineers’ estimate on the
cost to clean up properties. This will be DTSC’s third such comprehensive updated
estimate and DTSC will use the information collected from cleaning up 2,000 properties
for estimates to account for changing economic, labor and other conditions.
DTSC will use this new, updated estimate to project the cost for cleaning up the
remaining approximately 4,600 properties with lead contamination down to 80 parts
per million.
DTSC Has Cleaned Up More Properties More Quickly Than Any Other Residential Lead
Cleanup in the Nation
DTSC’s mission is to protect California's people and environment from the harmful effects of
toxic substances by cleaning up contamination and enforcing safeguards against hazardous
waste, among other important actions.
3 For this cleanup, DTSC has cleaned up more properties, more quickly than any other residential
lead cleanup in the nation. DTSC is conducting cleanups faster in the project’s first six years
than the other large projects, only one of which achieved higher cleanup rates after nine years.
2
Printed on Recycled Paper
CALIFORNIA STATE AUDITOR | Report 2020-107 35
October 2020
DTSC has completed over 2,000 cleanups as of October 2, 2020. We are cleaning up 24 4
properties a week as of September 21, 2020. DTSC is also moving to contract for cleanups at
400 additional properties.
DTSC accomplished these cleanups using a more protective lead cleanup standard than the
federal government, which increases the scope and intensity of cleanup activities.
DTSC entered into complex contractual agreements, such as the Project‐Labor Agreement with
the Los Angeles/Orange Counties Building and Construction Trades Council. This agreement
promotes training and employment opportunities and careers in the construction industry, with
a focus on environmental remediation, while also fostering the participation of small and
disabled veteran owned businesses.
DTSC also created a local workforce development and job training program to train and
promote the hiring of residents in communities near the former Exide facility. This program
expands community engagement in the testing and cleanup process, provides skills and health
and safety training, and supports job placement on the project.
One reason that DTSC has been able to implement this massive and logistically challenging
cleanup is that we began researching and learning from others in 2014. We spoke with United
State Environmental Protection Agency (U.S. EPA) staff, including Project Managers at other
lead‐contaminated residential cleanups. DTSC also sent project staff to a U.S. EPA conference
that brought together experts on urban lead cleanups from across the country. DTSC’s early
work created a foundation that contributed to DTSC’s ability to deliver cleanups to people in
communities around the former Exide facility.
DTSC has an ongoing commitment to improve the cleanup by learning, from other experts,
from people in the communities we serve, and from our mistakes. Any entity that claims
perfect implementation of a large, unique, and challenging project like this residential cleanup
isn’t truly assessing its performance. The key points in any such assessment are to identify and
anticipate problems, take corrective action and continue to improve our ability to protect the
people we serve.
DTSC Developed an Estimated Schedule for Implementation of this Large, Logistically 5
Complex Project and Some Factors that Affect the Pace of Cleanups are Unpredictable
As part of DTSC’s environmental review of the cleanup project, DTSC developed estimates of
project activities to assess their impact on traffic, vehicle emissions and other factors. DTSC
used this information to determine when state law would require mitigation measures.
DTSC included this environmental review information to provide estimates of cleanups that
would keep the environmental effects within tolerable margins and to provide a sense of what
this pace of cleanup would mean in the community and for the project. DTSC intentionally and
responsibly caveated this information with the terms “estimates,” “anticipates,” and “expects.”
3
Printed on Recycled Paper
36 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
6 In one later section of the audit, it acknowledges that DTSC “estimated” a pace of cleanup.
However, in the “Summary” section, the audit charges that “DTSC is significantly behind
schedule…” and “has been unable to maintain the cleanup pace it presented…” DTSC
appreciates the audit including the term “estimated” in the later section of the report.
5 The audit also asserts that when DTSC produced its documents for the cleanup, we should have
anticipated factors that were unpredictable prior to conducting the cleanup. For example, the
audit says that DTSC should have known the following factors before starting the cleanup of
thousands of properties over several years:
The number of properties configured in a way to require soil excavation by hand or
specialized types of excavation equipment;
The number of days rain would delay work; and
The number of properties where people would need to change the date of scheduled
sampling, cleanup and restoration activities.
Importantly, DTSC has kept the public informed about the various factors that can affect the
pace of cleanups as we have gained knowledge during project implementation. For example,
DTSC has informed the public that rain, extreme heat, property configuration, changes in
scheduled work, smoke from fires and the recent pandemic affect the pace of cleanups. DTSC
works diligently to keep the public informed about the cleanup and to answer questions.
DTSC has Focused on Implementing the State of California’s Commitment to Conduct
Cleanups
DTSC is focused on using the approximately $250 million provided by the State to conduct
cleanups at up to 3,200 of the most heavily‐contaminated parcels. Without this commitment,
communities would have been forced to wait for cleanups to commence.
7 However, the audit presumes DTSC should have developed a timeline or planned approach for
cleaning approximately 4,600 properties that will remain after DTSC completes the cleanup of
several thousand properties.
DTSC does have an approach to continue cleaning up sites. We also modify this approach to
account for the unique circumstances at each parcel and to increase our efficiency.
DTSC has provided the public and legislature with our estimate of the amount of time that we
expect different phases of the cleanup that we have funds to implement.
7 DTSC does not currently have the funding to clean up the remaining 4,600 properties. Without
knowing a sustained level of funding, providing people in the community with an end date for
the cleanup of their properties is at best a guess.
4
Printed on Recycled Paper
CALIFORNIA STATE AUDITOR | Report 2020-107 37
October 2020
DTSC will comply with the audit’s recommendation to create a timeline and additional planning
documents for all remaining properties. When doing so, DTSC will note that we are providing
this information pursuant to the audit’s recommendations.
DTSC is committed to continuing to improve the safety of the people we serve throughout the
state of California, including the communities around the former Exide facility. If you have any
questions regarding DTSC’s response, please contact Grant Cope by email at
Grant.Cope@dtsc.ca.gov.
Sincerely,
For:
Meredith Williams, Ph.D.
Director
Department of Toxic Substances Control
5
Printed on Recycled Paper
38 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
2 Schools, Parks and Daycares Property Summary as of October 7, 2020
Current Status of Work at Daycares, Parks and Schools
Category Day cares Parks Schools
Sampled 48 16 33
Cleanup is not Required 10* 13 24**
Prioritized for Cleanup 38 3 9
Prioritized and Cleanup is Complete 17 0 7
Properties to be Cleaned 21 3 2
TCRAs for Publicly Owned Facilities 2 3 2
Expedited in residential cleanup contract (NEC) 19
Initiated the cleanup process 8
Outreach to initiate the cleanup process 8
Declined Cleanup 3
* Includes three daycares no longer operating
** Includes three schools outside the PIA
6
Printed on Recycled Paper
CALIFORNIA STATE AUDITOR | Report 2020-107 39
October 2020
COMMENTS
CALIFORNIA STATE AUDITOR’S COMMENTS ON
THE RESPONSE FROM THE DEPARTMENT OF
TOXIC SUBSTANCES CONTROL
To provide clarity and perspective, we are commenting on DTSC’s
response to our audit. The numbers below correspond to the
numbers we have placed in the margin of DTSC’s response.
1
In its response, DTSC indicates that it has started implementing
some of our recommendations; however it did not provide any
evidence to support the actions it has taken. We look forward to
reviewing documentation of DTSC’s progress when it provides us its
60-day, six-month, and one-year responses to our recommendations.
2
DTSC presents numbers related to cleanup activities in its response
that are different than those in our report. These discrepancies are
due to its numbers and ours coming from different points in time.
DTSC provides figures from October 2020 but didn’t provide us
with any additional evidence to support its numbers. As we discuss
on pages 9 and 10 of our report, when reviewing the cleanup status
of daycare facilities, schools, and parks, we relied on information as
of June 30, 2020, which was the most recent available data during
the time of our review.
3
DTSC did not provide any evidence to support its assertion
that it has “cleaned up more properties more quickly than any
other residential cleanup project in the nation.” Accordingly, we
cannot validate this assertion nor did we attempt to compare the
cleanup pace to other projects. Regardless, we remain concerned
that DTSC has been unable to achieve the pace of cleanup that it
estimated it would achieve, as we report on pages 13 through 17.
Further, as we report on pages 15 and 16, DTSC has not enforced
that its contractors follow the pace-related performance standards
in its cleanup contracts. Because of these shortcomings, we
conclude on page 13 that DTSC will leave some of the 3,200 most
contaminated properties uncleaned for six months longer than it
originally estimated.
4
DTSC’s description of its cleanup pace is not specific enough to
understand whether the department has stepped up the pace of its
cleanup activities. DTSC asserts that it is cleaning 24 properties
a week as of September 21, 2020. However, as we report on
page 13, the most recent data we reviewed showed that as of
mid-August 2020, the department was only cleaning an average
of 16 properties per week. Further, on page 13 we note that from
March 2019 through February 2020, DTSC’s average cleanup pace
40 Report 2020-107 | CALIFORNIA STATE AUDITOR
October 2020
was only 20 properties cleaned per week. Therefore, it appears that at
best, DTSC may have achieved a cleanup pace of 24 properties a week
for about one month. Even then, this pace is less than DTSC’s estimated
pace of 25 to 35 properties per week in its original plan as we note on
page 13. For DTSC to demonstrate that it has corrected the issues we
found with its slower than expected cleanup pace and it is on track
to clean all 3,200 of the most contaminated properties by its targeted
completion date of June 2021, it will need to sustain a cleanup pace well
above its historic averages.
5
We acknowledge that variations in certain factors that affect cleanups
may be unpredictable. However, we would expect that, as the State’s
lead agency for toxic cleanup activities, DTSC would possess the
experience and professional qualifications necessary to account for
these factors and the variations it would likely encounter, such as the
layout of the properties, weather, and scheduling cleanup activities,
when it developed the estimate of how quickly DTSC could clean
properties. Although we agree that DTSC could not have had precise
knowledge of the extent to which variability in these factors would affect
its cleanup pace, it should have known that these factors could slow its
rate of progress. Therefore, when DTSC offered these as explanations
for why it had not achieved its anticipated pace of cleanup, we found
them to be inadequate. DTSC should have accounted for the effect of
variations in these predictable factors when it developed its expected
pace of cleanup, rather than using variations in these factors later to try
to justify why it has cleaned properties at a slower than expected pace.
6
Our conclusion that DTSC is behind schedule is correct and supported
by the evidence we present in this report. As we state on page 13,
DTSC is unlikely to meet its targeted end date for cleaning the 3,200
most contaminated properties primarily because it has not cleaned
properties at the pace it expected. Further, on page 16 we note that
DTSC has ordered one of its contractors to stop working and this
contractor has historically cleaned an average of 14 properties per week.
Therefore, DTSC faces, a significant challenge in achieving its targeted
completion date.
7
DTSC’s response discounts the importance of project planning for
an estimated 4,600 properties that will remain contaminated after it
completes the cleanup of the 3,200 most contaminated properties.
DTSC suggests that its lack of funding to clean the 4,600 properties
is a reason not to create a plan and timeline to clean those properties.
However, creating a plan and timeline is critical to informing
stakeholders. As we describe on page 18 of our report, without such a
plan, the Legislature and the public lack the information necessary to
easily understand the full scope of the cleanup effort. We look forward
to reviewing the timeline and cost estimate that DTSC states it will
create in response to our recommendation.