CSA
Recommendations
Read the report at California State Auditor ↗
Electrical System Safety
California’s Oversight of the Efforts by
Investor‑Owned Utilities to Mitigate the Risk
of Wildfires Needs Improvement
March 2022
REPORT 2021‑117
CALIFORNIA STATE AUDITOR
621 Capitol Mall, Suite 1200 | Sacramento | CA | 95814
916.445.0255 | TTY 916.445.0033
For complaints of state employee misconduct,
contact us through the Whistleblower Hotline:
1.800.952.5665
Don’t want to miss any of our reports? Subscribe to our email list at auditor.ca.gov
For questions regarding the contents of this report, please contact our Public Affairs Office at 916.445.0255
This report is also available online at www.auditor.ca.gov | Alternative format reports available upon request | Permission is granted to reproduce reports
Michael S. Tilden Acting State Auditor
March 24, 2022
2021-117
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
From 2013 through 2021, investor-owned utilities (utilities) in California initiated 67 public safety power
shutoffs (power shutoffs), affecting more than 3.6 million customers. In addition, as of June 2021, utilities
reported that nearly 40,000 miles of bare power lines exist in high fire-threat areas. Those bare lines
contribute to the need to use power shutoffs as a last resort to prevent wildfires, but the work necessary
to improve the bare lines will cost billions of dollars.
In light of the dramatic impact of wildfires and power shutoffs, and to assess two oversight entities’
roles in ensuring California’s safe and reliable electrical system, the Joint Legislative Audit Committee
directed my office to conduct an audit of the California Public Utilities Commission (CPUC) and the
Office of Energy Infrastructure Safety (Energy Safety Office). We determined that utilities are making
improvements to the electrical grid that are necessary to reduce the risk of wildfires and prevent power
shutoffs, but even if all of the improvements they completed in 2020 consisted of replacing bare power
lines in high fire-threat areas with covered or underground lines, they would have addressed only
4 percent of such lines.
As a result, the State must prioritize the areas utilities need to address first. A state law that took effect
in January 2022 requires utilities to begin identifying sections of line that are regularly affected by power
shutoffs and what they will do to reduce the need for and impact of future power shutoffs. The State could
strengthen this law by requiring utilities to identify what is necessary to prevent future power shutoffs
if the conditions leading to those shutoffs were to occur again, and to address a type of power outage
caused by altering equipment settings that led to more than 600 unplanned power outages in 2021.
The Energy Safety Office’s process for approving utilities’ plans for mitigating the risk of wildfires does
not ensure that the improvements are in high fire-threat areas. The office approved plans despite some
utilities’ failure to demonstrate that they are appropriately prioritizing their mitigation activities, and
subsequent reviews have found that some utilities failed to focus their efforts in high fire-threat areas.
The CPUC also conducts audits to determine whether utilities comply with rules designed to ensure that
they are operating safely, but it did not audit all utility service territories on a consistent basis, did not
audit several areas that include high fire-threat areas, and has not used its authority to penalize utilities
when its audits uncover violations.
Respectfully submitted,
MICHAEL S. TILDEN, CPA
Acting California State Auditor
621 Capitol Mall, Suite 1200 | Sacramento, CA 95814 | 916.445.0255 | 916.327.0019 fax | www.auditor.ca.gov
iv Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Selected Abbreviations Used in This Report
CPUC California Public Utilities Commission
EPIC Electric Program Investment Charge
PG&E Pacific Gas and Electric
RAMP Risk Assessment Mitigation Phase
SCE Southern California Edison
SDG&E San Diego Gas and Electric
CALIFORNIA STATE AUDITOR | Report 2021-117 v
March 2022
CONTENTS
Summary 1
Introduction 5
Utilities Will Need to Make Further Improvements to the
Electrical Grid to Reduce the Risk of Wildfires and to Prevent
Power Shutoffs and Unplanned Outages 17
Recommendations 33
The Energy Safety Office Awarded Safety Certifications to
Utilities Despite Serious Deficiencies in Their Mitigation Plans 35
Recommendation 39
The Energy Safety Office’s Mitigation Plan Approval Process
and the CPUC’s Audit Process Do Not Hold Utilities
Sufficiently Accountable 41
Recommendations 48
Other Areas We Reviewed 51
Appendix A
Scope and Methodology 55
Appendix B
Summary of Public Safety Power Shutoffs 61
Responses to the Audit
California Public Utilities Commission 63
California State Auditor’s Comments on the Response From
the California Public Utilities Commission 67
Office of Energy Infrastructure Safety 69
California State Auditor’s Comments on the Response From
the Office of Energy Infrastructure Safety 79
vi Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2021-117 1
March 2022
SUMMARY
Over the past decade, California has experienced some of its most devastating and costly
wildfires. Utility-caused fires are often more destructive than those resulting from other
sources because many occur in remote areas during high wind events, and those same
weather conditions cause the fire to spread quickly, making it difficult to control. Since 2015
power lines have caused six of the State’s 20 most destructive wildfires. Six investor-owned
utilities (utilities) that serve much of California are regulated by the California Public Utilities
Commission (CPUC). In addition, the Office of Energy Infrastructure Safety (Energy Safety
Office/office) within the Natural Resources Agency oversees and enforces utilities’ compliance
with wildfire safety requirements.1 It also approves wildfire mitigation plans (mitigation
plans) that describe the strategies and programs a utility will adopt to minimize the risk of
catastrophic wildfires caused by its electrical lines and equipment. One of these strategies is
the use of public safety power shutoffs (power shutoffs), which utilities have used to prevent
fires when strong winds, low humidity, and related conditions are present. However, doing so
leaves communities and essential facilities without power, imposing hardships and increased
risks, including the inability of the disabled and others to rely on electric-powered devices and
life support equipment.
Utilities Will Need to Make Further Improvements to the Electrical
Page 17
Grid to Reduce the Risk of Wildfires and to Prevent Power Shutoffs
and Unplanned Outages
California is at a higher risk of wildfires and more frequent
power shutoffs in part because of the nearly 40,000 miles of bare power
lines in areas where there is a greater threat of wildfire. In 2020 the
six utilities reported completing hardening projects—improvements
to make electrical equipment more fire resistant or to reduce the
risk of them igniting a fire—on only 1,540 miles of lines. The cost of
making the improvements on all 40,000 miles of bare power lines in
high fire-threat areas is generally significant, and because these costs
are included in the utilities’ rates, could pose a substantial burden
to ratepayers.
In January 2022, a new state law (shutoff reduction law) began
requiring that utilities identify circuits—sections of power lines
within a utility’s electrical grid—that have been subject to frequent
power shutoffs, and the improvements the utilities have already taken
or plan to take to reduce the need for and impact of future power
shutoffs. According to CPUC data, there were 67 power shutoffs
1 We use the term Energy Safety Office to refer to either the CPUC’s Wildfire Safety Division or the Office of Energy Infrastructure
Safety depending on when actions occurred. The Legislature transferred all the functions of the Wildfire Safety Division to
the Office of Energy Infrastructure Safety effective July 1, 2021. Thus, the actions we describe in the text that occurred prior to
July 1, 2021, were taken by the Wildfire Safety Division and any actions that occurred after were taken by the Office of Energy
Infrastructure Safety.
2 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
from 2013 through 2021, de-energizing thousands of circuits across
California and affecting more than 3.6 million customers. The shutoff
reduction law could be strengthened by requiring that utilities
identify the improvements that are necessary to prevent future power
shutoffs on those circuits, such as moving power lines underground.
This law could also be amended to address a type of power outage
that is occurring more frequently. Specifically, some utilities have
altered settings on equipment that have resulted in unplanned
outages. Although taking such action may prevent wildfires, one
utility’s alteration of electrical equipment settings caused hundreds
of unplanned power outages from July through November 2021 with
no advance notice. Despite the adverse impacts these outages cause,
the Energy Safety Office does not consider the requirements of the
shutoff reduction law to apply to this type of outage and thus, it has
not issued guidelines regarding utilities use of them.
Page 35 The Energy Safety Office Awarded Safety Certifications to Utilities
Despite Serious Deficiencies in Their Mitigation Plans
The Energy Safety Office must issue safety certifications to utilities
that demonstrate they meet certain criteria established in law—such
as having an approved mitigation plan. These safety certifications
affect requirements for utilities to repay certain amounts to a fund
they can use to help pay for the costs of wildfires they cause. The
Energy Safety Office issued the 2020 safety certifications to the
three largest utilities, even though it identified serious deficiencies
in each of their mitigation plans. Although for 2021 the Energy
Safety Office no longer approved mitigation plans without the utility
first addressing critical issues, we question the appropriateness of
the process it followed to approve mitigation plans and issue the
2020 safety certifications. In addition, the law does not allow the
Energy Safety Office to deny a safety certification based on a utility’s
failure to implement a prior mitigation plan—state law requires the
Energy Safety Office to consider whether a utility is in the process
of implementing its most recently approved mitigation plan when
issuing a safety certification. Thus, whether a utility has previously
implemented its mitigation plan has no bearing on the office’s
decision to issue its safety certification.
CALIFORNIA STATE AUDITOR | Report 2021-117 3
March 2022
The Energy Safety Office’s Mitigation Plan Approval Process and the
Page 41
CPUC’s Audit Process Do Not Hold Utilities Sufficiently Accountable
The Energy Safety Office approved utilities’ mitigation plans despite
some utilities’ failure to demonstrate that they are appropriately
prioritizing their mitigation activities. As referenced earlier, utilities
reported that their hardening projects had addressed relatively few miles
of bare power lines in high fire-threat areas during 2020. However, we
found that the Energy Safety Office approved mitigation plans that did
not provide adequate information on how utilities prioritized those
projects. For example, the office conditionally approved Pacific Gas and
Electric’s (PG&E’s) 2020 mitigation plan in June 2020 even though it
found that PG&E had not described where vegetation management—
trimming trees and vegetation from around power lines—was most
necessary. Further, a court-established Federal Monitor found that
PG&E had conducted a certain type of vegetation management in
relatively low-risk portions of its power grid instead of in high fire-threat
areas and had not conducted planned inspections of some equipment
in its highest threat areas. Nevertheless, the Energy Safety Office
guidelines for 2022 mitigation plans do not require that the utilities
clearly delineate in their plans where mitigation activities will occur. As a
result of this weakness, the Energy Safety Office does not assess whether
utilities plan to conduct these mitigation activities in areas of highest
risk for wildfire as a condition for approving their mitigation plans.
Moreover, the CPUC conducts audits to determine whether utilities
are in compliance with rules designed to ensure that they are operating
safely, but those audits could be improved to better ensure such
compliance, thereby helping mitigate the risk of utility-caused wildfires.
Specifically, the CPUC does not consistently audit all areas in the
utilities’ service territories, it did not audit several areas that include
high fire-threat areas, and it does not use its authority to penalize
utilities when its audits uncover violations.
Summary of Recommendations
Legislature
To reduce the number of power shutoffs, rather than only reducing
their scope and impact, the Legislature should amend the shutoff
reduction law to require that utilities describe in their mitigation
plans the improvements that would be necessary to prevent power
shutoffs on the circuits routinely affected by them, such as installing
covered power lines.
4 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
To address the risks and hazards resulting from future unplanned
outages, the Legislature should amend the shutoff reduction law
to include circuits frequently de-energized as a result of utilities
altering settings on equipment.
To ensure that safety certifications encourage utilities to invest
in safety and limit wildfire risks, the Legislature should require
that, as a prerequisite to issuing a safety certification, the Energy
Safety Office’s most recently completed compliance assessment
of a utility’s mitigation plan must conclude that the utility has
substantially implemented that plan.
To better hold utilities accountable for safely operating the electrical
grid, the Legislature should require the CPUC to do the following:
• Create a risk-based audit plan for consistently auditing all utility
service areas and prioritizing districts in high fire-threat areas.
• Create a schedule of penalties for violations identified through
its audit process and apply the schedule pursuant to its existing
authority to impose penalties as established in state law.
Energy Safety Office
To ensure that utilities are targeting the areas of highest fire risk for
mitigation activities, the Energy Safety Office should designate the
prioritization of mitigation activities as a critical issue that must be
addressed by utilities before it approves mitigation plans.
Agency Comments
The CPUC generally agreed with our recommendations. The
Energy Safety Office disagreed with several of our conclusions
and recommendations.
CALIFORNIA STATE AUDITOR | Report 2021-117 5
March 2022
Introduction
Background
Over the past decade, California has experienced some of its most
devastating and costly wildfires. There are three elements required to
start a fire: fuel (such as dry vegetation), oxygen, and heat (an ignition
source). According to the state fire marshal, wildfires are inevitable
throughout most of California. However, some ignition sources,
such as vegetation contacting power lines and causing sparks, are
preventable. Further, a California Department of Forestry and Fire
Protection (Cal Fire) assistant deputy director stated that fires caused
by utilities (utility-caused fires) are often more destructive than those
resulting from other sources because many utility-caused fires occur
in remote areas during high-wind events—bringing branches, trees,
or debris in contact with power lines and sparking fires—which
cause the fires to spread rapidly. A 2020 California Public Utilities
Commission (CPUC) report also noted that a growing population
in areas where human development meets combustible wildland
vegetation results in more communities exposed to wildfire risk
and in more electrical infrastructure being built in wildfire-prone
areas—where downed power lines may come into contact with fuels,
or objects such as trees may come into contact with power lines,
potentially generating sparks that ignite wildfires.
Addressing preventable ignition sources has become critical as
wildfires have grown larger and more destructive. As Figure 1
shows, eight of the 10 largest California wildfires have occurred
during the past five years, including the 2017 Thomas Fire and the
2021 Dixie Fire, which were both caused by utilities. According to
Cal Fire, fires caused by electrical power—such as electrical power
distribution or transmission equipment—accounted for about 10
percent of all wildfires in the areas for which it has responsibility
each year from 2016 through 2020, as Table 1 shows. Once the fire
starts, the same weather conditions that contribute to electrical
power-caused fires—the most critical of which is high wind—also
cause the fire to spread rapidly and make it difficult to control. Since
2015 power lines have caused six of the State’s 20 most destructive
wildfires. The State’s fourth climate change assessment report
issued in 2018 indicates that under a scenario in which changes do
not occur to reduce emissions, by 2100 the average area burned by
wildfires in California will increase by 63 percent.
6 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Figure 1
Utilities Caused Two of the 10 Largest Wildfires in California From 1932 Through 2021
DEL
NORTE
SISKIYOU MODOC
RUSH *
August 2012
SHASTA LASSEN
HUMBOLDT TRINITY
DIXIE†
AUGUST
July 2021
COMPLEX
TEHAMA PLUMAS
August 2020
GLENN BUTTE SIERRA NORTH COMPLEX
MENDOCINO August 2020
NEVADA
M
C
E
O
N
M
D
P
O
L
C
E
IN
X
O
LAKE
COLUSA SUTTER YUBA
PLACER
July 2018 CREEK
YOLO EL DORADO
SONOMA September 2020
NAPA
SOLANO
SACRAMENTO
AMADOR
ALPINE
LNU LIGHTNING CALAVERAS MONO
COMPLE X MARIN C
C
O
O
N
S
T
T
R
A
A
JOA
SA
Q
N
UIN
TUOLUMNE RANK FIRE NAME ACRES BURNED
August 2020 SAN FRANCISCO 1 August Complex 1,033,000
SAN MATEO ALAMEDA STANISLAUS MARIPOSA 2 Dixie† 963,000
SANTA
SANTA CLARA MERCED MADERA 3 Mendocino Complex 459,000
CRUZ
4 SCU Lightning Complex 397,000
BE S N A I N TO FRESNO 5 INYCOreek 380,000
SCU LIGHTNING
MONTEREY TULARE 6 LNU Lightning Complex 363,000
COMPLE X
KINGS
August 2020 7 North Complex 319,000
8 Thomas† 282,000
SAN LUIS OBISPO KERN 9 Cedar 273,000
10 Rush* 272,000
SANTA BARBARA
SAN BERNARDINO
VENTURA LOS ANGELES
THOMA S † ORANGE RIVERSIDE
December 2017
SAN IMPERIAL
CEDAR
DIEGO
October 2003
Source: Cal Fire’s website, National Interagency Fire Center’s website, and Cal Fire’s 2020 Fire Siege report.
Notes: As of October 25, 2021, these are the 10 largest fires that Cal Fire has identified since 1932, regardless of jurisdiction or whether they were
federal, state, or local responsibility.
Fire location is not to scale, is approximate, and does not represent the exact boundaries of the fire.
* This fire burned an additional 44,000 acres in Nevada.
† This wildfire was caused by power lines.
CALIFORNIA STATE AUDITOR | Report 2021-117 7
March 2022
Table 1
Wildfires Caused by Electrical Power Account for 19 Percent of Cal Fire‑Reported Acres Burned
2016 Through 2020
WILDFIRES WILDFIRES CAUSED BY ELECTRICAL POWER
TOTAL TOTAL ACRES
YEAR WILDFIRES BURNED NUMBER PERCENT ACRES BURNED PERCENT
2016 2,816 245,000 270 10% 3,000 1%
2017 3,470 467,000 408 12 250,000 54
2018 3,504 1,063,000 297 8 247,000 23
2019 3,086 130,000 304 10 84,000 65
2020 3,501 1,459,000 335 10 59,000 4
Totals 16,377 3,364,000 1,614 10% 643,000 19%
Source: Cal Fire’s Wildfire Activity Statistics reports, 2016 through 2020.
Note: These data consist primarily of wildfire incidents within the Cal Fire direct protection area responded to by Cal Fire personnel.
Not only has average wildfire size and the area burned annually
increased, the cost of combating the fires has grown. From fiscal
years 2016–17 through 2020–21, the State’s annual expenditures for
Cal Fire—the state agency responsible for providing fire protection
and prevention—nearly doubled, from $1.9 billion to an estimated
$3.5 billion. According to the National Interagency Fire Center
database for large wildfires and other significant events, as of
December 2021 California’s large fires in that year cost $2.6 billion
to suppress—accounting for more than half of the $4.3 billion of
such costs reported nationally. In addition, these data show that
the total cost of suppressing large wildfires in California from 2015
through 2021 was more than $9.1 billion.
Wildfires result in many additional costs beyond the cost of
suppressing them. A 2018 research report, funded in part by the
U.S. Forest Service, described both short-term wildfire costs—such
as those for suppressing the fire, evacuation services, relief aid,
and home and property losses—and longer-term damage—such as
habitat restoration, business losses, and medical costs, including
those associated with exposure to smoke. This research estimated
that suppression costs represent only 9 percent of total wildfire
costs. The other costs of wildfires have been significant, and not all
of them are financial costs. In the last six years, California wildfires
have killed nearly 200 people and damaged or destroyed more
than 53,000 structures. The California Natural Resources Agency’s
communications director indicated that the State does not regularly
track or estimate the cost of wildfires in a way that accounts for
public health costs or ecological damage. Other research has
attempted to estimate these costs. For example, researchers
from several international universities conducted an analysis of
California’s 2018 wildfires that suggests that the economic impact
8 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
of wildfires may be significantly larger than the cost of suppressing
them and may affect economic activities in areas beyond the
location of the physical destruction or smoke. That analysis
calculated suppression costs for California’s 17 largest wildfires in
2018 to be nearly $1 billion but estimated that the damage totaled
$149 billion, including destroyed and damaged buildings and
infrastructure, health costs, and economic losses.
In a 2020 report, the CPUC’s Wildfire Safety Division recognized
that the threat of wildfire is increasing and that utility-related
ignitions are responsible for a “disproportionate” share of
wildfire-related consequences. According to a 2019 report from
a gubernatorial strike force, more than a quarter of California’s
population—about 11 million people—live in areas where human
development meets combustible wildland vegetation, known as the
wildland‑urban interface, and there are an estimated 4.5 million
homes in that interface. The number of people living in the interface
will continue to rise if nationwide trends continue. Further, there
is significant overlap between the wildland-urban interface and the
areas the CPUC considers high fire-threat areas.
Oversight of the State’s Electrical Grid
The electrical grid is a network of components, including
transmission and distribution lines (power lines), substations, and
transformers. Power plants generate electricity, but electricity must
have a path, or circuit, in order to travel to homes and businesses
where it is used. Generally, there are two classifications of power
lines carrying electricity from one location to another. High-voltage
transmission lines, such as those that hang between tall metal
towers, carry electricity over long distances. Higher voltage
electricity is more efficient and less expensive for long-distance
electricity transmission than lower voltage. Transformers at
substations reduce the voltages from long-distance transmission
lines before electricity is transferred to the distribution lines that
carry it to homes and businesses. Several types of entities provide
electricity in California, including publicly owned utilities, rural
electric cooperatives, and investor-owned utilities. Investor-owned
utilities (utilities) are privately owned utilities whose stock is
publicly traded. Six such utilities serve much of California, as
Figure 2 shows.2 State law requires utilities to provide adequate,
efficient, just, and reasonable service, and the Legislature considers
electricity essential to the health, safety, and economic well-being of
all California consumers.
2 Our use of the term utilities in this report refers to a subset known as electrical corporations.
CALIFORNIA STATE AUDITOR | Report 2021-117 9
March 2022
Figure 2
Investor‑Owned Electric Utilities Served Most of the State in 2020
PACIFICORP
LIBERTY
UTILITIES
SOUTHERN
CALIFORNIA
PACIFIC GAS
EDISON COMPANY
AND ELECTRIC
COMPANY
BEAR VALLEY
ELECTRIC
SERVICE
SAN DIEGO
GAS AND ELECTRIC
COMPANY
Source: California Energy Commission and utility district maps.
Note: The unmarked areas of the map are served by other types of electric utilities, such as publicly owned utilities and rural electric cooperatives.
10 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
The CPUC has the authority to regulate utilities. Through a process
known as a general rate case, described in more detail below, the
CPUC approves utility cost and spending plans in the first phase
of the process, which are the basis for the rates utilities charge
consumers that it approves in the second phase of the process.
The Governor appoints and the Senate approves the CPUC’s
five commissioners (the Commission), and a portion of the
CPUC’s revenue comes from fees it imposes on utilities. The CPUC
is responsible for implementing and enforcing standards for the
maintenance and operation of facilities that generate electricity that
are owned by a utility or located in the State. The CPUC has also
stated that it is responsible for ensuring that the utilities it regulates
are providing service and facilities that do not constitute a threat
to the public or the environment. For fiscal year 2020–21, it spent
nearly $740 million and had a staff of 581 employees responsible for
its regulatory function, as Table 2 shows. The scope of the CPUC’s
oversight is significant given the size of the entities it oversees. The
six utilities collectively employed more than 47,000 individuals
and had revenues of nearly $43 billion in 2020. The CPUC also
regulates privately owned communications, natural gas, and water
companies, in addition to overseeing railroad and rail transit,
moving, and transportation companies.
Table 2
Electric Utility Regulation Is a Small Portion of the CPUC’s Total Expenditures
CPUC REGULATORY EXPENDITURES
PERCENT OF REGULATORY
TOTAL CPUC TOTAL REGULATORY REGULATORY EXPENDITURES EXPENDITURES FOR
FISCAL YEAR STAFF POSITIONS EXPENDITURES FOR ELECTRIC UTILITIES* ELECTRIC UTILITIES
2016–17 432 $671,000,000 $57,000,000 8%
2017–18 419 598,000,000 59,000,000 10
2018–19 411 717,000,000 72,000,000 10
2019–20 496 837,000,000 130,000,000 16
2020–21 581 737,000,000 101,000,000 14
Source: State budgets for fiscal years 2016–17 through 2020–21, CPUC accounting data, and interviews with CPUC staff.
Note: The CPUC regulates the six utilities, as well as privately owned telecommunications, natural gas, and water companies, in addition to overseeing
railroad and rail transit, moving, and transportation companies.
* The CPUC indicates there may be additional legal, administrative law judge, and other divisional costs pertaining to electric utilities that are not
included in this total, and some figures may include expenditures for activities unrelated to electricity, such as costs related to regulating a utility
that provides both gas and electricity.
CALIFORNIA STATE AUDITOR | Report 2021-117 11
March 2022
The CPUC approves the rates that utilities can charge for electricity
every four years. Through the general rate case process—which
is overseen by a commissioner and CPUC’s administrative law
judges—the utilities request the CPUC’s approval for rate changes
based on the revenue required to pay for their operating expenses
and capital costs (revenue requirement). According to the CPUC,
utilities may also request additional revenues and rate changes in
between general rate cases, in some circumstances. The revenue
requirement consists of a number of factors, such as the utility’s
normal business expenses, depreciation, and taxes; and it is the
basis for designing the rates consumers are charged. Since 2015
the CPUC has required California’s large utilities—Pacific Gas and
Electric Company (PG&E), San Diego Gas and Electric Company
(SDG&E), and Southern California Edison Company (SCE)—to file
a Risk Assessment Mitigation Phase (RAMP) proceeding in advance
of their general rate cases. A RAMP proceeding examines a utility’s
assessment of its key risks, including those posed by wildfires, and
its proposals for mitigating those risks, and the CPUC requires the
utility to incorporate the results of its RAMP proceeding into its
general rate case.
The CPUC is also responsible for ensuring the protection and
safety of utility customers at large, and it exercises its regulatory
authority in part by issuing General Orders that govern the activity
of multiple utilities under its jurisdiction. A General Order has the
force and effect of law, and its violation may result in penalties. To
ensure that utilities are following the construction, maintenance,
and inspection requirements outlined in its General Orders, the
CPUC performs audits of the utilities. It also investigates certain
wildfires, including those caused by utilities, to assess utilities’
compliance with applicable rules and regulations. To oversee and
enforce utilities’ compliance with wildfire safety requirements,
the Legislature required the CPUC to create the Wildfire Safety
Division by January 1, 2020. The Legislature also established the
Office of Energy Infrastructure Safety (Energy Safety Office/office)
within the California Natural Resources Agency and, effective
July 1, 2021, transferred the activities of the CPUC’s Wildfire
Safety Division to that office, as Figure 3 shows. Because the
director, the staff, and the activities of the Wildfire Safety Division
were transferred to the Energy Safety Office, for the purposes
of this report, we use the term Energy Safety Office to refer to
both the newly formed Office of Energy Infrastructure Safety
and the Wildfire Safety Division that previously existed as a part
of the CPUC.
12 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Figure 3
State Law Shifted Certain Activities From the CPUC to the Office of Energy Infrastructure Safety
Office of Energy Infrastructure
CPUC Activities Safety Activities
Activities Transferred
Prior to July 1, 2021 As of July 1, 2021
on July 1, 2021
Wildfire Safety Division
• Approve or deny wildfire mitigation plans.
• Approve or deny wildfire mitigation plans.
• Conduct inspections and audits to ensure utilities
• Conduct inspections and audits to ensure utilities implement their mitigation plans.
implement their mitigation plans.
• Issue safety certifications to utilities that meet
• Issue safety certifications to utilities that meet certain requirements.
certain requirements.
• Conduct annual safety culture assessments for
• Conduct annual safety culture assessments for each utility.*
each utility.*
• Require an independent third-party safety
culture assessment for each utility at least once
every five years.
• Review RAMPs.
• Approve or deny rate changes for utilities.
• Supervise and regulate every utility, including by
making orders, decisions, directions, and rules
utilities must obey.
• Investigate the cause of utility-related accidents
resulting in loss of life, injury to a person, or
damage to property, and requiring investigation
in the CPUC's judgement.
Source: State law and CPUC rulemaking.
* Safety culture assessments evaluate how effectively an organization embraces and practices safety.
The Energy Safety Office is a relatively small organization, with
only 30 employees as of January 2022. State law assigns it the
responsibility for reviewing and approving utilities’ wildfire
mitigation plans (mitigation plans) and overseeing utilities’
compliance with approved mitigation plans. Among other things,
mitigation plans describe the preventive strategies and programs
a utility will adopt to minimize the risk that its electrical lines
and equipment will cause catastrophic wildfires. The Energy
Safety Office is also responsible for issuing safety certifications
CALIFORNIA STATE AUDITOR | Report 2021-117 13
March 2022
to utilities that meet certain requirements outlined in state law.
Safety certifications affect the amount utilities must reimburse
the Wildfire Fund in certain situations—described in more detail
below—which is intended to provide electrical corporations that
are safe actors a mechanism to guard against the financial effects of
wildfires that is more cost-effective than traditional insurance.
The Legislature established the Wildfire Fund in 2019 to pay for
certain claims against utilities for damages due to wildfires they
cause, to support the creditworthiness of utilities, and to reduce
the cost to ratepayers in addressing utility-caused catastrophic
wildfires. The Wildfire Fund is funded through a loan from the
State’s surplus money investment fund, contributions from
participating utilities, and surcharges on some of the utilities’
ratepayers, with a goal of ultimately reaching a claim-paying
capacity of approximately $21 billion. Each large utility—PG&E,
SCE, and SDG&E—participates in the Wildfire Fund, and according
to the Wildfire Fund administrator, the balance was nearly
$11 billion as of December 2021.
Participating utilities may seek payment from the Wildfire Fund
to satisfy third-party claims for covered wildfires that exceed the
greater of $1 billion in any year or the amount of insurance the
utility must maintain. State law requires participating utilities to
maintain reasonable insurance coverage, the amount of which the
fund administrator must periodically review and recommend. In
general, utilities must reimburse the fund for costs that the CPUC
determines are not just and reasonable. By law, utilities with a valid
safety certification for the period in which the wildfire ignited are
presumed to have acted reasonably, and if the CPUC determines
the costs for which they claim reimbursement are not just and
reasonable, the amount the utility must reimburse the Wildfire
Fund is capped.
However, if the CPUC determines that the utility’s costs were
not reasonable and it did not have a safety certification or the
fund administrator determines that its actions or inactions
constituted a conscious or willful disregard of the rights and
safety of others, the utility must reimburse the Wildfire Fund
in full. As of December 2021, none of the participating utilities
had made a claim on the Wildfire Fund. However, in a quarterly
report to the Securities and Exchange Commission, PG&E
indicated that to the extent liabilities related to the 2021 Dixie Fire
exceeded $1 billion, it was eligible to make a claim to cover the
excess amount, and that as of September 2021, it had recorded
an accounting entry for probable recoveries of $150 million from
the Wildfire Fund in connection with that fire.
14 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Power Shutoffs Can Be Effective in Preventing Potential Wildfire
Ignitions During Certain Conditions
State law declares that reliable electric service is of utmost
importance to the safety, health, and welfare of the State’s citizenry
and economy. However, in a 2012 decision, the CPUC concluded
that utilities have the authority under state law to proactively shut
off electric power to customers when it is necessary to protect
public safety. Such actions are known as public safety power
shutoffs (power shutoffs). Utilities use these power shutoffs when
they deem it necessary for public safety, such as to prevent fires
when strong winds, low humidity, and related conditions are
present. However, doing so leaves consumers, communities, and
essential facilities, such as hospitals and fire departments, without
power from the electrical grid, thereby imposing increased risks
and hardships.
In an effort to better prepare the public and local officials for power
shutoffs, the Commission adopted a resolution in 2018 to, among
other things, increase communication and notify customers as soon
as practicable before the power shutoff and to require utilities to
submit a post-event report to the CPUC within 10 days after each
shutoff. From 2019 through 2021, the Commission expanded the
power shutoff guidelines that utilities must follow. For example, a
utility must now include in its post-event report the alternatives
it considered before it initiated the power shutoff. The CPUC also
requires that a utility report on how it determined that the benefits
of a power shutoff outweighed potential public safety risks and use
a power shutoff only as a mitigation measure of last resort.
All three large utilities (PG&E, SCE, and SDG&E) noted in their
2021 mitigation plan updates that power shutoffs are a necessary
fire prevention mechanism of last resort. All six of the utilities
describe power shutoffs in their mitigation plans and four of them
have implemented power shutoffs in the past. The decision to
de-energize electric facilities for public safety depends on several
factors, including the dryness of vegetation near power lines
and local weather conditions, such as wind speed and humidity.
Extended droughts, extreme wind events, and the relative dryness
of the surrounding vegetation—among other things—can propagate
large wildfires.
As the State’s risk of wildfire has increased, power shutoffs have
proven effective at preventing possible ignitions resulting from
broken equipment and hazards during high wind conditions, such
as tree limbs blown onto power lines. After a utility concludes a
power shutoff, the CPUC requires the utility to submit a post-event
report that details, among other things, any wind-related damage
to overhead power lines where power was shut off. Our review
CALIFORNIA STATE AUDITOR | Report 2021-117 15
March 2022
of 15 such reports found that 11 of them described wind-related
damage, including vegetation in direct contact with power lines
and damage to electrical equipment, such as broken power poles,
that might have ignited a wildfire had the power not been shut
off. In two of these reports, the utilities indicated there were more
than a hundred instances of wind-related damage to equipment.
Until utilities make improvements to power lines to withstand
such weather conditions without the risk of igniting a wildfire,
de-energizing power lines will continue to be a necessary mitigation
tool to protect the public.
Although they prevent wildfires, power shutoffs can have a number
of adverse effects. As Appendix B shows, during 2019 and 2020,
individual power shutoffs affected anywhere from fewer than
20 people to more than 940,000. Power shutoffs affect public safety
in a variety of ways, as the text box shows. Further, they can be very
costly. A 2019 SCE study surveyed customers to collect detailed
information on the costs that they incur during power outages. The
study found that the costs varied based on the length of the outage,
but it estimated that the average cost to residential and small or
medium business customers were $0.07 and nearly
$21 per minute of the power outage, respectively,
which SCE stated generally aligned with those of a
A power shutoff event can have significant
2012 PG&E study. Based on these figures, a power
adverse impacts on the general public, including
shutoff lasting 10 hours would cost a residential
the following:
customer $42 and a small or medium business
$12,600. A February 2021 report published by the • Inability of the disabled, the elderly, and the medically
Lawrence Berkeley National Laboratory that cited fragile to rely on electric-powered devices and life-support
equipment, such as hemodialysis machines and respirators.
the SCE study, described limitations of outage data
collected through surveys, such as SCE’s study, • Loss of news services to disseminate emergency
including possible biases, and consequences and information to the public.
costs that the respondent does not consider.
• Increased risk of vehicle accidents due to loss of
Although SCE’s estimates may not be the most
functioning traffic and street lights.
precise measure of all outage-related costs, the cost
• Significant costs incurred by utility customers, such as
of the 62 power shutoffs for which there was
businesses.
duration information was more than $21 billion in
total—based on the SCE average cost estimates for • Unique hardships suffered by economically disadvantaged
residential and small or medium business utility customers.
customers. The majority of those costs are the
• Increased dangers from the use of portable generators,
result of two PG&E outages in 2019 with costs that
such as fire ignition risk.
totaled more than $14 billion. In its 2020 utility
• Adverse impact on water supply, sewage services, and
wildfire mitigation strategy, the Energy Safety Office
sanitary services.
emphasized that the State’s leadership and residents
view the magnitude of past years’ power shutoff Source: Commission decisions from 2009 and 2021, and the
CPUC’s website.
events as unacceptable and that utilities must
minimize the need to use power shutoffs as a
wildfire mitigation tool.
16 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2021-117 17
March 2022
Utilities Will Need to Make Further Improvements to
the Electrical Grid to Reduce the Risk of Wildfires and
to Prevent Power Shutoffs and Unplanned Outages
Key Points:
• There is a higher risk of wildfires and power shutoffs in California in part because of the
nearly 40,000 miles of bare power lines in areas with a greater threat of wildfires. In 2020 the
six utilities reported hardening projects—improvements to make electrical equipment more
fire resistant or to reduce the risk of equipment igniting a fire—on only 1,540 miles of lines.
• In January 2022, a new state law began requiring utilities to identify circuits in their mitigation
plans that have been frequently de-energized during power shutoffs and to identify the
measures, such as moving power lines underground, that the utilities have taken or plan
to take to reduce the need for and impact of future power shutoffs. The Legislature could
better ensure that utilities are taking adequate steps to reduce the need for power shutoffs by
requiring that utilities’ mitigation plans also identify the improvements necessary not only to
reduce the scope, but to prevent power shutoffs on the circuits routinely affected by them.
• The three largest utilities have altered settings on their equipment, which resulted in hundreds
of unplanned power outages with no advance notice to customers. However, unlike planned
power shutoffs, the Energy Safety Office does not currently require utilities to identify in their
mitigation plans the power lines that are frequently experiencing these unplanned outages
and improvements to reduce their impact.
Implementing Improvements, Such as Installing Covered Power Lines and Managing Vegetation,
Can Reduce the Risk of Wildfires and the Need for Power Shutoffs
A 2020 Energy Safety Office report stated that the impact of power shutoffs on safety and climate
change goals is intolerable, indicating that it is not a long-term solution to mitigating the risk
of wildfires.3 However, operating portions of the electrical grid in certain weather conditions
increases the risk of utility-caused wildfires. In some circumstances, the risk of a catastrophic
wildfire in certain areas is so high that utilities determine there is no alternative to turning off
the electricity. Thus, all three of the large utilities continue to rely on power shutoffs as a method
of last resort to prevent wildfires. According to CPUC data, there were 67 power shutoffs from
2013 through 2021, de-energizing thousands of circuits—sections of power lines within a utility’s
electrical grid—across California and affecting more than 3.6 million customers. The CPUC
publishes a fire threat map that designates significant portions of the State to be at an elevated or
extreme risk of fire, as Figure 4 shows, which we refer to collectively as high fire‑threat areas. The
utilities reported information for 57 power shutoffs, and all of them occurred in, or partially in,
high fire-threat areas. Those individuals who were affected lost power for 37 hours on average,
and some shutoffs involved repeatedly de-energizing the same section of power lines. Further,
the CPUC’s power shutoff data indicate that from 2017 through 2021, utilities de-energized
approximately 270 circuits during three or more different power shutoffs in the same calendar year.
3 The report stated that utilities’ mitigation activities should also advance climate change goals, such as limiting diesel generator usage
during power shutoffs.
18 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Figure 4
Large Areas of California Are at Elevated or Extreme Risk of Utility‑Caused Wildfires
Elevated Risk
Extreme Risk
Source: CPUC’s fire-threat map data.
Esri, HERE, Garmin, (c) OpenStreetMap contributors, and the GIS user
community
CALIFORNIA STATE AUDITOR | Report 2021-117 19
March 2022
One significant aspect of the electrical grid that contributes to
the need for power shutoffs is the number of miles of bare power
lines in high fire-threat areas. Nearly 27 percent—more than
74,000 miles of the nearly 277,000 miles of the six utilities’ power
lines—are located in these areas. The utilities collectively reported
that at least 54 percent of these power lines are bare lines, as Table 3
shows. Notably, PG&E accounted for the vast majority of these
bare lines—more than 33,000 of the nearly 40,000 miles of bare
power lines among utilities in the State. Further, 80 percent of
PG&E’s power lines in high fire-threat areas are bare.
Table 3
At Least 54 Percent of the Distribution Power Lines in High Fire‑Threat Areas Are Bare
TOTAL MILES LINE TYPE
IN HIGH
FIRE‑THREAT
AREAS BARE UNDERGROUND COVERED OTHER*
PERCENT OF PERCENT OF PERCENT OF PERCENT OF PERCENT OF
TOTAL TOTAL UTILITY UTILITY UTILITY UTILITY
UTILITY MILES PERCENT MILES PERCENT MILES PERCENT MILES PERCENT MILES PERCENT
PG&E 41,410 56% 33,268 80% 4,996 12% 767 2% 2,379 6%
SCE 23,085 31 5,397 23 10,893 47 None reported 6,795 29
SDG&E 5,953 8 664 11 2,520 42 None reported 2,769 47
Liberty 1,893 3 628 33 525 28 None reported 740 39
PacifiCorp 1,421 2 None reported 486 34 115 8 820 58
Bear Valley 689 1 None reported 124 18 None reported 565 82
Totals 74,451 39,957 54% 19,544 26% 882 1% 14,068 19%
Source: Geographic data for power lines that utilities reported to the Energy Safety Office, as of June 2021, and interviews with Energy Safety Office
staff for the categorization of power line status.
Note: This table reflects data submitted to the Energy Safety Office as of June 2021. As we describe in the data reliability section of the report, we
determined that these data were of undetermined reliability for our purposes. In addition, utilities have performed additional work on power lines
since these data were submitted. Some percentages do not add up to 100 due to rounding.
* This category includes power lines with geographic data that were missing descriptions, as well as power lines that were partially covered or did not
fall within any of the other categories.
Bare lines are of particular concern because nearly half of the fire
incidents that utilities reported from 2015 through 2020 were
caused by power lines coming into contact with foreign objects,
including vegetation. The three largest utilities’ data on certain
ignitions they caused from 2015 through 2020 reveal that power
lines themselves accounted for at least 74 percent of ignitions,
not including ignitions caused by transformers, fuses, and poles.4
Figure 5 shows the locations of 3,550 utility-caused ignitions
reported by utilities from 2015 through 2020. An SCE study found
4 A 2014 CPUC decision requires only PG&E, SDG&E, and SCE to collect and report these
fire-incident data.
20 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
that bare power lines are much less effective than other types
of power lines at preventing certain types of faults, or abnormal
electrical currents, that can lead to ignitions—such as those caused
by vegetation contact, which SCE considers one of the highest risks
for causing wildfires.5 Although only some of the ignitions shown
in Figure 5 caused a large wildfire, these are the general types of
ignitions that have resulted in catastrophic utility-caused wildfires.
To reduce the risk of utility-caused wildfires and the need for power
shutoffs to prevent these types of wildfires, utilities must make
improvements to the electrical grid to reduce the likelihood that
electrical equipment will cause a fire. For example, at least three
of the utilities have altered their power shutoff protocols for areas
where they have installed covered power lines to allow for higher
wind speeds before resorting to a power shutoff. Installing covered
power lines—wires sheathed in a plastic covering that provides an
insulating effect—and other mitigation efforts, including burying
power lines underground and trimming trees and vegetation
from around power lines, have been found to reduce the risk of
utility-caused ignitions. According to SCE’s 2021 mitigation plan
update, making such grid-hardening improvements is one of the
most—if not the most—important mitigations that SCE can deploy
to reduce power shutoffs. However, data that utilities reported
to the Energy Safety Office identified that only 27 percent of the
power lines in high fire-threat areas are underground or covered.
For example, although the land around Arrowhead Lake is in a high
fire-threat area, Figure 6 shows that many of its power lines are
bare, other, or unknown. Figure 6 also shows a summary by county
of the percentage of power lines that five of the utilities reported are
underground or covered.
At least three utilities have altered their
power shutoff protocols for areas where
they have installed covered power lines
to allow for higher wind speeds before
resorting to a power shutoff.
5 In 2018 SCE compiled a comprehensive review of the research, benchmarking, engineering
analysis, and testing to evaluate the effectiveness of covered lines used in the development of its
application for its grid safety and resiliency program.
CALIFORNIA STATE AUDITOR | Report 2021-117 21
March 2022
Figure 5
There Were 3,550 Utility‑Caused Fire Incidents Reported by the Three Largest Utilities From 2015 Through 2020
Utility-Caused Fire Incident
Source: CPUC’s utility-reported fire incident data.
Notes: CPUC requires only the three largest utilities—PG&E, SDG&E, and SCE—to report these fire incident data.
We present an interactive dashboard for viewing additional detail about the location, suspected initiating event, and size of the resulting fires at
www.auditor.ca.gov/reports/2021-117/supplemental-fire-incident.html
The Camp Fire is not included in this figure. According to the CPUC’s wildfire safety enforcement branch program manager, it was not included in
PG&E’s 2018 ignition report because the investigation of the fire was still open when the data were reported. After we brought this oversight to the
CPUC’s attention, the program manager stated that CPUC would work with PG&E to obtain amended data for 2018 that includes the Camp Fire.
22 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Figure 6
The Percentage of Utilities’ Distribution Lines That Were Underground or Covered as of June 2021 Varied by Location
Lake Arrowhead
Bare
Other or Unknown
Underground
Percent of County Power Lines
Underground or Covered
0.0 100.0
Source: Geographic data for primary and secondary distribution lines that Bear Valley Electric Service, PacifiCorp, PG&E, SCE, and SDG&E reported to
the Energy Safety Office, as of June 2021, and interviews with Energy Safety Office staff.
Notes: We present an interactive dashboard for viewing the status of individual power lines in greater detail at
www.auditor.ca.gov/reports/2021-117/supplemental-line-status.html.
Liberty Utilities did not provide consent to publish detailed data.
CALIFORNIA STATE AUDITOR | Report 2021-117 23
March 2022
Trimming and removing trees and other vegetation to maintain a
minimum distance from power lines, known as vegetation management,
is another important strategy that can help reduce the risk of
utility-caused wildfires and the need for power shutoffs. Cal Fire’s reports
on the wildfire incidents it responded to within its direct protection
area from 2018 through 2020 indicate that on average, fires caused
by vegetation contact accounted for 74 percent of all acres burned
by electrical power-caused wildfires.6 In some instances, high winds
blow vegetation into bare power lines, causing sparks that lead to fires.
A CPUC General Order requires utilities to keep areas near power lines
clear of vegetation, as Figure 7 shows. In some cases, utilities conduct
enhanced vegetation management exceeding the standard vegetation
management requirements. For example, one utility reported that it
planned to go beyond the CPUC minimum standards and perform
enhanced vegetation management on its distribution lines in elevated
and extreme fire-threat districts to the standard shown in the right-hand
image in Figure 7. A PG&E analysis of 414 historical ignitions from
2015 through 2017 found that a combination of enhanced vegetation
management and system hardening, including installing covered power
lines and other improvements, would have mitigated nearly 80 percent
of those ignitions. Further, from 2015 through 2020, at least 24 percent of
the reportable ignitions the three largest utilities reported were caused by
vegetation coming into contact with utility equipment.
According to PG&E, a combination of enhanced
vegetation management and system hardening
would have mitigated nearly 80 percent of
414 ignitions from 2015 through 2017.
Despite the important benefits that vegetation management provides,
at least one utility has failed to perform it sufficiently. According to a
November 2021 report on PG&E from the Federal Monitor—an entity
originally established by a federal court to prevent the criminal conduct
that gave rise to the 2010 San Bruno gas explosion and also assigned
the responsibility of assessing PG&E’s wildfire mitigation and wildfire
safety work—PG&E’s routine and enhanced vegetation management
work could be improved. For example, PG&E’s enhanced vegetation
management, which it plans to perform on all circuits in high fire-threat
districts, is being performed so slowly that it will take more than 10 years
to complete. In 2020 a federal judge found that PG&E had diverted
6 A direct protection area is the area for which a particular fire protection organization has primary
responsibility by law or contract for attacking an uncontrolled fire and directing suppression activities.
24 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
funds from work projects, including vegetation management, for bigger
employee bonuses, shareholder dividends, and political contributions,
among other things. According to a federal court, the primary cause of
wildfires ignited by PG&E were hazardous trees and limbs that should
have been, by law, removed. In its September 2020 quarterly report on its
mitigation plan, PG&E itself stated that vegetation-caused ignitions are
one of the largest drivers of utility-caused wildfires and that vegetation
that is not actively managed can come into physical contact with utility
equipment year-round, creating additional ignition opportunities.
Figure 7
Vegetation Management Consists of Clearing Vegetation Within a Certain Distance of Power Lines
One utility's enhanced vegetation
Required vegetation management
management standard
4 feet
of clearance
4 feet 12 feet
of clearance of clearance
In high fire-threat areas, a CPUC General Order In this example, the utility has proposed enhanced
requires utilities to ensure that bare power lines of vegetation management in high fire-threat areas that
certain voltages have at least 4 feet of clearance consists of trimming, at a minimum, any vegetation
in any direction from vegetation. within 12 feet of the power line, and overhanging
branches and limbs for certain trees 4 feet out from
either side of a line and up to the sky.
Source: CPUC’s General Order 95 and PG&E’s 2020 Wildfire Mitigation Plan.
CALIFORNIA STATE AUDITOR | Report 2021-117 25
March 2022
Although moving power lines underground is considered one of
the best ways to reduce the risk of utility-caused wildfires, that
approach is generally expensive to implement. According to the
U. S. Energy Information Administration, buried power lines are
protected from the wind, ice, and tree damage, so they are subject
to fewer weather or vegetation-related outages. However, the
U.S. Energy Information Administration also notes that the cost
of underground power lines is significant—up to five to 10 times
more than overhead distribution lines—and that converting existing
overhead power lines to underground lines includes the added cost
of dismantling the overhead system. For example, SDG&E and PG&E
estimated that moving power lines underground costs approximately
$2.6 million and $3 million per mile, respectively. Costs for moving
power lines underground also vary by location. A report prepared
by the Edison Electric Institute found that the cost of moving power
lines underground ranged from $93,000 per mile in rural areas to
$5 million per mile in urban areas.
Installing covered power lines is another mitigation activity that
can reduce the risk of wildfire and power shutoffs. Figure 8 shows
the difference between bare and covered power lines. According
to the U.S. Department of Energy and the Institute of Electrical
and Electronics Engineers, covered power lines are very effective
in preventing potential ignitions resulting from foreign objects that
come in contact with traditional bare power lines under high-wind
conditions. Moreover, an SCE study found that each dollar spent
replacing existing bare power lines with covered lines provided
four times as much value in wildfire risk mitigation as a dollar spent
on converting the bare lines to underground power lines.
Figure 8
Some Power Lines Are Covered With an Insulating Material to Protect Them From Contact With Other Objects
INSULATION NO INSULATION
Covered lines have a
protective material
Bare lines have
that insulates the
no insulation.
electricity that passes
through them.
Source: SCE study.
26 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Despite the risk posed by bare lines, the geographic data and quarterly
reports that utilities submitted to the Energy Safety Office indicated
that their hardening initiatives have addressed only a relatively small
number of the miles of bare power lines in high fire-threat areas. From
July 2020 to June 2021, the geographic data the six utilities collectively
reported indicate that they completed 628 miles of hardening
projects—projects that involve physically manipulating electrical
equipment to make it more fire-resistant or to reduce the risk of
igniting a fire. The Energy Safety Office’s data manager stated that it
relies on separate quarterly initiative reports that utilities submit to
the Energy Safety Office that summarize their progress in completing
the goals enumerated in their mitigation plans. Those reports also
show that utilities’ hardening projects addressed relatively few miles
of the bare power lines in high fire-threat areas. Utilities report on
a variety of hardening projects, some of which measure progress by
the number of poles inspected or trees removed, rather than in miles
of line. However, according to the Energy Safety Office, the 2020
fourth-quarter initiative reports indicate that of the initiatives that
are measured in miles, the utilities reported performing hardening on
only 1,540 miles of power lines in 2020. Even if all of these hardening
projects consisted of replacing bare lines in high fire-threat areas with
covered power lines or moving them underground, the utilities would
have addressed only 4 percent of the nearly 40,000 miles of bare
power lines in areas of elevated or extreme fire risk.
Utilities reported performing hardening on
only 1,540 miles of power lines in 2020, and
there are nearly 40,000 miles of bare power
lines in areas of elevated or extreme fire risk.
Installing Certain Equipment Can Reduce the Impact of Power Shutoffs
but Does Not Fully Prevent Future Shutoffs From Occurring
Effective January 2022, a new state law requires that utilities’
mitigation plans identify circuits that have frequently been
de-energized and the measures the utilities have taken or plan to
take to reduce the need for and impact of future de-energization
of those circuits (shutoff reduction law). The shutoff reduction law
also requires utilities to estimate their annual decline in circuit
de-energization. As part of its 2022 mitigation plan update guidelines,
the Energy Safety Office is requiring utilities to include in their plans
a list of each circuit that was de-energized to mitigate the risk of
wildfires three or more times in a calendar year and the measures
CALIFORNIA STATE AUDITOR | Report 2021-117 27
March 2022
the utility has taken, or plans to take, to reduce the need for and
impact of future power shutoffs of that circuit. There are various
types of improvements that utilities can make to reduce the scope
and impact of power shutoffs, including installing microgrids and
sectionalizing devices.
State law defines a microgrid, in part, as an interconnected system
of sources of energy and energy demands with clearly defined
electrical boundaries that can connect to, disconnect from, or
run in parallel with, larger portions of the electrical grid. Thus,
some microgrids can be disconnected from the electrical grid
and operate autonomously to maintain the electrical supply to
the critical infrastructure connected to it during power shutoffs.
Figure 9 illustrates how a microgrid is able to disconnect from the
electrical grid and rely on local power resources and storage to
provide electricity for critical services. For example, PG&E installed
temporary microgrids that provided electricity for crucial services
during at least five power shutoffs in 2020 and 2021. In another
instance, a microgrid that received funding through the CPUC’s
Electric Program Investment Charge (EPIC) program allowed the
continued provision of power to approximately 10,000 people in
Humboldt County during a 2019 PG&E power shutoff.
Figure 9
Microgrids Can Allow the Continued Provision of Electricity for Critical Services When an Area Is Disconnected
From the Larger Electrical Grid
(cid:24)(cid:23)(cid:30)(cid:22)(cid:30)(cid:23)(cid:21)(cid:20)(cid:26)(cid:28)(cid:30)(cid:25)
(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:25)(cid:28)(cid:24)(cid:28)(cid:27)(cid:23)(cid:22)(cid:30)(cid:27)
(cid:21)(cid:30)(cid:20)(cid:23)(cid:19)(cid:26)(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:18)(cid:28)(cid:17)(cid:30)(cid:16)(cid:27)(cid:20)(cid:28)(cid:17)(cid:26) (cid:11)(cid:24)(cid:28)(cid:27)(cid:10)(cid:13)(cid:26)(cid:9)(cid:22)(cid:30)(cid:27)(cid:23)(cid:10)(cid:28)
(cid:15)(cid:22)(cid:14)(cid:19)(cid:14)(cid:22)(cid:13)(cid:26)(cid:25)(cid:27)(cid:14)(cid:12)
(cid:6)(cid:27)(cid:14)(cid:22)(cid:14)(cid:20)(cid:23)(cid:19)(cid:26)(cid:5)(cid:23)(cid:20)(cid:14)(cid:19)(cid:14)(cid:22)(cid:13)(cid:26)
(cid:8)(cid:30)(cid:7)(cid:28)(cid:17)
Power ON Power OFF Disconnected from the larger grid
(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:28)(cid:30)(cid:25)
Source: State law, California Energy Commission microgrid project report, and the U.S. Department of Energy’s website.
Note: This figure demonstrates some common elements of microgrids. Microgrids come in a variety of designs and sizes, and they can be set up for
operation in various ways and for different purposes.
28 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
The CPUC established the EPIC program in December 2011 to
fund public investments in microgrids and other technologies,
tools, and strategies that benefit electricity ratepayers. Reports
on EPIC-funded microgrids published by the California Energy
Commission, which helps administer the program, indicate that
they reduced the scope and impact of electric outages and resulted
in economic benefits. According to the CPUC, the EPIC program
has funded at least 23 microgrid-related projects since 2015. The
cost of installing microgrids can vary. For example, EPIC-funded
microgrid projects ranged in cost from $1.2 million to more than
$9 million.
Sectionalizing devices can also limit the scope of a power shutoff
event. For the purpose of this report, we define sectionalizing
devices as equipment that allows utilities to turn off power to
smaller segments of the electrical grid and reduce the impact of a
de-energization event. Figure 10 shows how sectionalizing devices,
in conjunction with reclosers or automatic circuit breakers, can
help reduce the number of customers affected by a power shutoff
event by limiting its extent. Reclosers and circuit breakers are types
of equipment that allow utilities to interrupt power at the point
they are located within a circuit. The three largest utilities installed
approximately 1,000 sectionalizing devices from 2019 through
2020, and they rely on these devices to reduce the extent of power
shutoffs and to help minimize the number of customers impacted
by them. Both PG&E and SDG&E also indicated that they plan to
install additional sectionalizing devices by the end of 2022.
Although microgrids and sectionalizing devices can reduce the
impact of power shutoffs and the number of customers affected,
they do not fully eliminate the need for future power shutoffs if
weather conditions occur that are similar to those that triggered
the earlier power shutoffs. To prevent the need for power shutoffs,
utilities must make improvements, such as installing covered
power lines or moving them underground to increase power lines’
resilience in high-wind conditions and reduce the likelihood of the
power lines igniting a wildfire.
Although microgrids and sectionalizing
devices can reduce the impact of power
shutoffs and the number of customers
affected, they do not fully eliminate the
need for future power shutoffs.
CALIFORNIA STATE AUDITOR | Report 2021-117 29
March 2022
Figure 10
Sectionalizers Allow Utilities to Turn Off Smaller Portions of the Grid, Which Can Reduce the Scope and Impact of
Power Shutoffs
Power Shutoff Without Sectionalizers
(cid:31)(cid:30)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:25)(cid:24)(cid:23)(cid:22)(cid:21)(cid:26)(cid:29)(cid:20)(cid:24)(cid:26)(cid:22)(cid:29)(cid:19)(cid:24)(cid:18)(cid:22)(cid:21)
(cid:14)(cid:27)(cid:13)(cid:30)(cid:25)
(cid:12)(cid:30)(cid:11)(cid:30)(cid:25)(cid:19)(cid:21)(cid:27)(cid:25)
(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:30)(cid:25)(cid:24)(cid:27)(cid:25)
(cid:23)(cid:22)(cid:21)(cid:27)(cid:20)(cid:19)(cid:21)(cid:18)(cid:29)
(cid:17)(cid:18)(cid:25)(cid:29)(cid:22)(cid:18)(cid:21)(cid:24)(cid:16)(cid:25)(cid:30)(cid:19)(cid:15)(cid:30)(cid:25)
(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:29)(cid:29)(cid:25)(cid:24)(cid:23)(cid:22)(cid:27)(cid:21)(cid:30)(cid:24)(cid:25)(cid:29)(cid:30)(cid:24)(cid:28)(cid:27)
(cid:20)(cid:19)(cid:30)(cid:27)(cid:28)(cid:27)(cid:18)(cid:19)(cid:17)(cid:29)(cid:30)(cid:27)(cid:16)(cid:15)(cid:14)(cid:25)(cid:19)(cid:13)
Power Shutoff With Sectionalizers
(cid:28)(cid:27)(cid:26)(cid:25)(cid:24)(cid:23)(cid:22)(cid:21)(cid:26)(cid:29)(cid:17)(cid:16)(cid:29)(cid:25)(cid:15)(cid:22)(cid:29)(cid:31)(cid:21)(cid:22)(cid:14)(cid:29)(cid:13)(cid:22)(cid:22)(cid:25)(cid:12)(cid:16)(cid:11)(cid:29)(cid:28)(cid:21)(cid:12)(cid:25)(cid:22)(cid:21)(cid:12)(cid:14)(cid:29)(cid:10)(cid:24)(cid:21)(cid:29)(cid:14)(cid:29)(cid:19)(cid:24)(cid:18)(cid:22)(cid:21)(cid:29)(cid:9)(cid:15)(cid:27)(cid:25)(cid:24)(cid:8)(cid:29)(cid:20)(cid:24)(cid:26)(cid:22)(cid:29)(cid:19)(cid:24)(cid:18)(cid:22)(cid:21)
(cid:14)(cid:27)(cid:13)(cid:30)(cid:25)
(cid:12)(cid:30)(cid:11)(cid:30)(cid:25)(cid:19)(cid:21)(cid:27)(cid:25)
(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:30)(cid:25)(cid:24)(cid:27)(cid:25)
(cid:23)(cid:22)(cid:21)(cid:27)(cid:20)(cid:19)(cid:21)(cid:18)(cid:29)
(cid:17)(cid:18)(cid:25)(cid:29)(cid:22)(cid:18)(cid:21)(cid:24)(cid:16)(cid:25)(cid:30)(cid:19)(cid:15)(cid:30)(cid:25)
(cid:9)(cid:22)(cid:7)(cid:25)(cid:12)(cid:24)(cid:16)(cid:14)(cid:30)(cid:12)(cid:6)(cid:22)(cid:21)(cid:26)
Power ON Power OFF
(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:29)(cid:29)(cid:25)(cid:24)(cid:23)(cid:22)(cid:27)(cid:21)(cid:30)(cid:24)(cid:25)(cid:29)(cid:30)(cid:24)(cid:28)(cid:27)
(cid:20)(cid:19)(cid:30)(cid:27)(cid:28)(cid:27)(cid:18)(cid:19)(cid:17)(cid:29)(cid:30)(cid:27)(cid:16)(cid:15)(cid:14)(cid:25)(cid:19)(cid:13)
Source: The CPUC.
30 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
The Legislature Should Strengthen the Shutoff Reduction Law
to Require That Utilities Identify Measures Necessary to Prevent
Power Shutoffs
The cost of making the improvements necessary to prevent power
shutoffs throughout the State, such as installing covered power
lines or moving lines underground, is generally significant and
could pose a burden to ratepayers. Although utilities report that
installing covered lines is generally cheaper than placing them
underground, it may well cost billions of dollars to address bare
power lines in high fire-threat areas. Based on the amounts the
three largest utilities reported spending to install covered power
lines in 2020, it cost about $700,000 per line mile on average.
Using this figure, the cost of replacing the nearly 40,000 miles of
bare lines utilities reported in areas of elevated and extreme fire
risk would be $28 billion. The CPUC’s Public Advocates Office and
other stakeholders have raised concerns about the cost-effectiveness
of installing covered power lines when utilities have proposed
such programs because portions of certain utility proposals were
not located in the highest-risk portions of the electrical grid. For
example, The Utility Reform Network—a nonprofit consumer
advocacy organization—argued in 2019 that SCE’s general rate case
for 2021, 2022, and 2023 was unaffordable and recommended that
SCE focus on its highest-risk segments and reduce its budget for
installing covered power lines from $2.7 billion to $643 million.
It may well cost billions of dollars for
utilities to address bare power lines in high
fire‑threat areas.
Although the shutoff reduction law requires utilities to identify
circuits that have been routinely de-energized to mitigate the risk
of wildfires, the law could be strengthened by requiring that utilities
identify specific improvements that are necessary to prevent future
power shutoffs. To implement the shutoff reduction law, the Energy
Safety Office requires utilities’ 2022 mitigation plans to map and
list frequently de-energized circuits and list the measures they
have taken or will take to reduce the need for and impact of future
de-energization of those circuits. Its director stated that the Energy
Safety Office will determine what next steps are necessary after it
evaluates how well utilities plan to reduce the scope and frequency
of the power shutoffs described in their 2022 mitigation plans.
CALIFORNIA STATE AUDITOR | Report 2021-117 31
March 2022
Although such planned reductions in the scope and frequency of
power shutoffs may represent an improvement, any power shutoff
generally imposes risks and hardships. Further, if the Energy
Safety Office is to minimize the need to use power shutoffs as
a wildfire mitigation tool and meet its stated objective of pursuing
wildfire mitigation activities that do not significantly impact
electric utility reliability, it will need to ensure that utilities make
improvements to the electrical grid that eliminate the need for
power shutoffs in the weather conditions that have led to their
routine use in the past. The Legislature could better ensure that
utilities are taking adequate steps to reduce the need for power
shutoffs by requiring that utilities’ mitigation plans also identify the
improvements necessary not only to reduce the scope, but also to
prevent power shutoffs on the circuits routinely affected by them if
the conditions leading to those shutoffs were to occur again.
The number and cost of improvements utilities will need to make
is not known, in part because the shutoff reduction law took effect
in January 2022. Further, the shutoff reduction law does not require
utilities to estimate the cost of future improvements to circuits
that are frequently de-energized. The significant cost of making
improvements necessary to prevent the need for power shutoffs,
such as installing covered power lines or moving them underground,
may be one of the reasons why the improvements have not yet been
made. However, even if these improvements cost billions of dollars,
SCE’s estimates of customers’ costs during power shutoffs indicate
that power shutoffs have cost more than $21 billion to date, as
discussed earlier.
Utilities’ Alteration of Power‑Line Settings Have Resulted in
Hundreds of Unplanned Power Outages, Affecting More Than a
Half Million Customers
The three largest utilities have altered settings on their equipment,
including circuit breakers and reclosers, resulting in unplanned
power outages (unplanned outages) throughout the State. When
there is excessive current flowing in a circuit—which could be
caused by an object like a tree blown over in high winds making
contact with an energized line—a circuit breaker or recloser
automatically interrupts power to the circuit. Typically, after
a preset duration, a recloser restores the power to determine
whether the fault still exists and interrupts power again if it does.
The recloser repeats this sequence a set number of times, and if it
continues to detect the fault, it will de-energize the line. However,
utilities are able to change settings on some breakers and reclosers
so that they turn off the power more quickly if there is an issue on
an energized line. PG&E stated that adjusting these settings in 2021
32 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
to turn electricity off more quickly resulted in an approximate
46 percent reduction in ignitions in high fire-threat areas compared
to the three-year historical average.
Although those actions may have effectively prevented wildfires,
PG&E’s alteration of breaker and recloser settings in 2021, known
as enhanced powerline safety settings (power-line settings program),
also triggered hundreds of unplanned outages that affected more
than a half million customers. PG&E stated that in July 2021, it
altered these settings along 11,500 miles of power lines located in
high fire-threat areas. From late July through early November 2021,
its power-line settings program resulted in nearly 600 unplanned
outages that affected more than 650,000 customers. These outages
occurred with no advance notice, affected an average of more than
1,000 customers per outage, and averaged more than 17.5 hours
per customer in duration. The CPUC indicates these outages are
more than a matter of inconvenience—they are disruptive, and
for customers who rely on electricity to maintain necessary life
functions, they can be life-threatening. However, unlike a planned
shutoff, customers and public safety partners receive no warning of
these outages before their power is interrupted.
Unlike a planned shutoff, customers and
public safety partners receive no warning
of these outages before their power
is interrupted.
According to the CPUC’s website, all six utilities will include altering
settings on their equipment (power-line setting measures) in their
2022 mitigation plans, and both PG&E and SDG&E have already
indicated that they plan to use these settings in the future, resulting
in more unplanned outages. Although some utilities reported
reductions in the extent and duration of proactive power shutoffs
in 2020 and anticipated further reductions in 2021, this decrease
may be related to the additional use of power-line setting measures
that more frequently trigger unplanned outages for customers. For
instance, although PG&E expects to see further reductions in the
scope of proactive power shutoffs, according to the CPUC’s wildfire
safety enforcement branch program manager, PG&E indicated to the
CPUC that it anticipates expanding the power-line settings program
in 2022.
CALIFORNIA STATE AUDITOR | Report 2021-117 33
March 2022
Despite the hundreds of unplanned outages and more than a
half million customers affected by PG&E’s use of the power-line
settings program in 2021, the Energy Safety Office does not
consider power-line settings programs to fall under the definition
of a de-energization event as described in the shutoff reduction
law. Thus, the office does not require utilities’ mitigation plans
to identify the circuits that are frequently experiencing these
unplanned outages or the measures the utilities have taken or
plan to take to reduce the need for and impact of unplanned
outages in the future. The Energy Safety Office’s director indicated
that the office may issue guidelines regarding utilities’ use of the
program in the future. However, the unplanned outages due to
the power-line settings program that are caused by power lines
contacting vegetation are the result of the same situations that
power shutoffs are intended to prevent. Until utilities make
improvements to those power lines that are routinely de-energized
because they have altered settings on their equipment, it is likely
that customers will continue to be subject to additional unplanned
outages in coming years.
Until utilities make improvements to
power lines that are routinely de‑energized
because they have altered settings on
their equipment, it is likely that customers
will continue to be subject to additional
unplanned outages in coming years.
Recommendations
To prevent power shutoffs rather than only reducing their scope
and impact, the Legislature should amend the shutoff reduction
law to require that utilities describe in their mitigation plans the
improvements that would be necessary to prevent power shutoffs
on the circuits routinely affected by them—such as installing
covered power lines—and the costs of those improvements.
To address the risks and hazards resulting from future unplanned
outages, the Legislature should amend the shutoff reduction law
to include circuits frequently de-energized as the result of utilities’
power-line setting measures. In doing so, the Legislature will
create a requirement that utilities identify in their mitigation plans
34 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
the circuits frequently de-energized as a result of their power-line
setting measures and the improvements they have made or plan to
make to those circuits.
CALIFORNIA STATE AUDITOR | Report 2021-117 35
March 2022
The Energy Safety Office Awarded Safety
Certifications to Utilities Despite Serious
Deficiencies in Their Mitigation Plans
Key Points:
• The Energy Safety Office issued safety certifications even though it identified
deficiencies in utilities’ mitigation plans.
• Further, state law does not require the Energy Safety Office to ensure that
utilities have implemented prior mitigation plans before they are issued
safety certifications.
Our review of the 2020 safety certifications issued to PG&E, SCE, and SDG&E found
weaknesses in the Energy Safety Office’s process for issuing them.7 As we discuss in the
Introduction, the office must issue safety certifications to utilities that demonstrate they
meet certain criteria established in statute. Having an approved mitigation plan—which
identifies the activities the utility intends to undertake to mitigate wildfire risks—is
one of these legal requirements. However, the office identified significant deficiencies
in the 2020 mitigation plans that PG&E, SCE, and SDG&E submitted. Specifically, it
determined that each utility’s plan had one or more Class A deficiencies—the most
serious type of deficiency—which it describes as an aspect of the mitigation plan that
is lacking or flawed. For example, the office determined that all three plans failed to
demonstrate how they were using risk modeling to inform decision making, and thus
they could not demonstrate that they were targeting the highest-risk portions of the
electrical grid. Nonetheless, the Energy Safety Office issued a conditional approval of
the mitigation plans for all three of these utilities we reviewed. Conditional approval
is a term not defined in the statute pertaining to mitigation plans, yet as we describe
below, the office treated it as an approval. As a part of the conditional approval, the
office required utilities to file remedial plans to resolve the deficiencies it had identified.
However, the office found that all of the three utilities’ remedial plans were insufficient.
Although the Energy Safety Office identified significant concerns with each of the
three large utilities’ 2020 mitigation plans, it approved the plans through its conditional
approval process and issued safety certifications to the utilities. The director of the
office stated that for the 2020 mitigation plans approved while she was director of the
Wildfire Safety Division, a conditional approval constituted approval pursuant to state
law, and that although the utilities were required to submit remedial plans, its analysis
of these plans was not a condition of its approval. As we discuss later, the office revised
its mitigation plan review process for 2021 mitigation plans and now requires utilities to
address critical issues before it approves their plans. However, the office’s own definition
7 As we discuss in the Introduction, we use the term Energy Safety Office to refer to either the CPUC’s Wildfire Safety Division
or the Office of Energy Infrastructure Safety depending on when actions occurred. The Legislature transferred all the functions of
the Wildfire Safety Division to the Office of Energy Infrastructure Safety effective July 1, 2021. Thus, the actions we describe in the
text that occurred prior to July 1, 2021, were taken by the Wildfire Safety Division and any actions that occurred after were taken
by the Office of Energy Infrastructure Safety.
36 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
of the deficiencies it identified as mitigation plan aspects that are
lacking or flawed, and its revision of its approval process, calls into
question the appropriateness of the process it followed to approve
mitigation plans and issue safety certifications for 2020.
Even if the Energy Safety Office’s process for issuing safety
certifications had not included conditional approvals, the
requirements in state law are insufficient to assure that utilities that
are issued certifications have implemented their mitigation plans.
The bill establishing the requirements for safety certifications
describes how the Wildfire Fund will support the credit worthiness
of electrical corporations. It also describes how utilities must invest
in hardening electrical infrastructure and performing vegetation
management, and that a safety certification encourages utilities to
invest in safety and improve safety culture to limit wildfire risks.
However, the state law does not allow the Energy Safety Office to
deny a safety certification on the basis that a utility
did not implement a prior mitigation plan.
The Energy Safety Office must issue a safety
certification if a utility demonstrates that it: As the text box shows, state law requires that the
Energy Safety Office issue a safety certification
1. Has an approved mitigation plan.
to a utility that meets a number of requirements,
2. Is in good standing, and has agreed to implement the including demonstrating that it is implementing
findings of its most recent safety culture assessment, if its approved mitigation plan and submitting
applicable. quarterly notifications about implementation.
3. Has established a safety committee of its board of directors, State law does not include the utility’s
composed of members with relevant safety experience. implementation of a prior year’s plan as criteria
for issuance of the safety certification. It does
4. Has an approved executive incentive compensation
require the office to issue a safety certification if a
structure that promotes safety as a priority.
utility is implementing its most recently approved
5. Has established board-of-director-level reporting on safety mitigation plan, among other things. However,
issues to the CPUC and the Energy Safety Office.
the implementation of the plan is occurring in
6. Has established a compensation structure for executive the same time frame as the safety certification
officers that is based on principles, including limits on determination. The Energy Safety Office’s director
guaranteed cash compensation, no guaranteed monetary stated that the compliance period for a mitigation
incentives, and incentives for performance, including safety plan is defined as the calendar year in which the
performance. plan was filed, and a utility must be afforded the
7. Is implementing its most recently approved mitigation full compliance period to determine whether it
plan and submits quarterly information detailing has substantially implemented its plan. Because
implementation of the plan and safety culture the rate at which a utility completes initiatives
assessment recommendations. varies throughout the year, the director also stated
that the Energy Safety Office does not expect a
Source: State law.
utility to accomplish an equal 25 percent in each
quarter of the work it plans to complete.
CALIFORNIA STATE AUDITOR | Report 2021-117 37
March 2022
Further, the Energy Safety Office’s final assessment of whether
a utility has implemented its mitigation plan does not occur
until well after the safety certificate expires. As the example in
Figure 11 shows, the office is not required to make a determination
of whether the utility complied with its mitigation plan during
calendar year 2020 until September 2022—more than eight months
after the end of the period for which the 2020 safety certification
was valid. Therefore, whether a utility substantially implements the
projects in its mitigation plan has no bearing on the issuance of its
safety certification as a result of these two factors: first, because the
implementation of the plan is in progress, the Energy Safety Office
performs only a limited review of whether a utility is implementing
its current mitigation plan, and second, determinations of whether
a utility substantially implemented its prior mitigation plans are not
one of the criteria established in law for it to assess when issuing a
safety certification.
Whether a utility substantially implements
the projects in its mitigation plan
has no bearing on the issuance of its
safety certification.
The Energy Safety Office’s inability to deny a safety certification
based on poor implementation of prior mitigation plans led it to
issue a safety certification to PG&E despite concerns about PG&E’s
progress in mitigating wildfire risks. In October 2020, before
the office issued PG&E’s 2020 safety certification, the Federal
Monitor concluded that it strongly appeared that PG&E had
failed to adhere to its risk models when executing its wildfire risk
reduction work. Specifically, the Federal Monitor noted that PG&E
had completed the majority of its 2019 enhanced vegetation work
in relatively low-risk portions of its high fire-threat areas, and it
had performed approximately 1,000 inspections of transmission
towers outside of high-threat areas, but it had not conducted any
of its planned enhanced inspections of transmission structures
in its highest-threat areas. The office noted these concerns in the
issuance letter for PG&E’s safety certification but nonetheless
stated that PG&E had met the minimum statutory requirements for
issuance of a safety certification.
38 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Figure 11
Energy Safety Does Not Determine Whether a Utility Has Implemented Its Mitigation Plan Until After Issuing Its
Safety Certification
Timeline for One Utility's 2020 Safety Certification and Mitigation Plan
SAFETY CERTIFICATION MITIGATION PLAN
2020
February Utility submits 2020
mitigation plan
June The Energy Safety Office
July Utility submits request for approves utility’s 2020 mitigation plan
2020 safety certification
January 2020 until January 1, 2021
2020 mitigation plan is valid
2021
January The Energy Safety Office issues
2020 safety certification
March Utility submits report on its
compliance with the mitigation plan
during 2020
January 2021 through January 14, 2022
2020 safety certification is valid
2022
The safety certification expires 8 months
prior to the Energy Safety Office's
determination of whether the utility
complied with its 2020 mitigation plan
September The Energy Safety Office
completes its review of the utility's
compliance with its mitigation plan
during 2020
Source: State law and safety certification and mitigation plan documents.
Note: Dates for other utilities varied.
CALIFORNIA STATE AUDITOR | Report 2021-117 39
March 2022
Although the office’s director stated that if the law were amended to
require that the office consider completed compliance assessments
of previous mitigation plans, it could incorporate the assessments
into the process, she nonetheless expressed concern that it would
change the statutory intent of the safety certification. Specifically,
she noted that the certification is currently designed to encourage
utilities to invest in safety and improve their safety cultures to
limit wildfire risks and reduce costs, but it was not designed
to be retrospective or punitive. Although we agree that the law
establishing the Wildfire Fund describes the intent of the safety
certification in this manner and that its focus is directed to utilities
that are safe actors, it is unclear how issuing safety certifications
to utilities that fail to implement their mitigation plans furthers
this intent.
Recommendation
To ensure that safety certifications encourage utilities to invest
in safety and limit wildfire risks, the Legislature should require
that as a prerequisite of issuing a safety certification, the Energy
Safety Office’s most recently completed compliance assessment
of a utility’s mitigation plan must conclude that the utility has
substantially implemented that plan.
40 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2021-117 41
March 2022
The Energy Safety Office’s Mitigation Plan Approval
Process and the CPUC’s Audit Process Do Not Hold
Utilities Sufficiently Accountable
Key Points:
• The Energy Safety Office approved mitigation plans despite identifying deficiencies in
how utilities planned to prioritize mitigation activities. Subsequent external reviews
established that these planning deficiencies were followed by a lack of mitigation efforts
in areas of highest risk of wildfire.
• To better hold utilities accountable for the initiatives identified in their past mitigation
plans, the Energy Safety Office needs to require utilities to systematically address the
findings of external reviews in their plans.
• The CPUC conducts audits to determine whether utilities are in compliance with rules
designed to ensure that they are operating safely, but those audits could be improved
to better ensure utilities’ compliance and consequently help mitigate the risk of
utility-caused wildfires. Specifically, the CPUC does not consistently audit all areas in
the utilities’ service territories, did not audit several areas that were designated as being
in high fire-threat areas, and does not use its authority to penalize utilities when its
audits uncover violations.
The Energy Safety Office Has Failed to Ensure That Utilities Focus Mitigation Activities in the
Areas of Highest Fire Risk
The Energy Safety Office has approved some utilities’ mitigation plans even though the utilities’
failed to demonstrate that they are appropriately prioritizing their mitigation activities. As
we discuss earlier, utilities’ reports submitted to the office indicated that their hardening
initiatives have addressed a relatively small number of the miles of bare power lines in high
fire-threat areas. However, we found that the office approved mitigation plans that did not
provide adequate information on how utilities prioritized those initiatives. State law requires
utilities to submit mitigation plans to the office for review and approval. According to the
Energy Safety Office’s director, the office’s approach to reviewing mitigation plans is focused on
evaluating the utilities’ processes for considering risks, such as ignition risk from equipment
failure or vegetation contact, when making their decisions.8 Despite this focus, the office
approved utilities’ 2020 and 2021 mitigation plans even though the utilities had not provided
sufficient information on how they used risk modeling outcomes to inform decision-making
processes, circuit prioritization for mitigation efforts, and mitigation selection. Moreover, the
Energy Safety Office acknowledged the absence of this information in its summary of changes
for the 2022 mitigation plan update guidelines. As described below, external reviews and the
8 According to the 2021 mitigation plan guidelines template, a risk-informed decision-making process incorporates an assessment of the
overall ignition probability, estimated wildfire consequence for specific electric lines and equipment, and estimation of wildfire and
power shutoffs’ risk-reduction impact, among other factors.
42 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
office’s own audits confirmed the significance of this deficiency, as
these reviews and audits established that PG&E did not focus its
mitigation activities on the highest risk areas.
For example, the Energy Safety Office conditionally approved PG&E’s
2020 mitigation plan in June 2020 even though it found that PG&E
did not describe in sufficient detail where vegetation management
was most necessary or how it prioritized deployment of vegetation
management initiatives in its plan. In subsequent months, this
weakness in PG&E’s vegetation management efforts was confirmed
and highlighted by external reviews and audits. As discussed
previously, the Federal Monitor noted in October 2020 that PG&E
had completed the majority of its 2019 enhanced vegetation work in
relatively low-risk portions of its high fire-threat areas and had not
conducted any of its planned enhanced inspections of transmission
structures in its highest threat areas. Moreover, the Energy Safety
Office published an audit in February 2021, which found that during
2020, PG&E continued to conduct enhanced vegetation management
primarily in areas of lower fire risk. The audit concluded that
PG&E’s 2020 vegetation management program appears not to have
sufficiently prioritized or reduced the risk of wildfires.
The Energy Safety Office’s audit concluded
that PG&E’s 2020 vegetation management
program appears not to have sufficiently
prioritized or reduced the risk of wildfires.
In its review of PG&E’s 2021 mitigation plan, the Energy Safety Office
determined that PG&E made progress in updating its vegetation
risk model in a way that PG&E claimed would allow it to prioritize
work in greater detail. However, the office’s review found that the
utility failed to demonstrate that it was properly prioritizing other
mitigation activities, particularly power line replacement and
system hardening efforts. Despite these and other concerns, the
office approved PG&E’s 2021 mitigation plan in September 2021.
Once again, a subsequent external review confirmed the extent of
the problem with PG&E’s inadequate prioritization of mitigation
activities. In its 2021 mitigation plan, PG&E committed to conducting
180 miles of system hardening in 2021, 80 percent (or 144 miles) of
which would be in high wildfire risk areas, in fire rebuild areas, or
in power shutoff mitigation areas. The Federal Monitor published
a report in November 2021 indicating that up to that point PG&E
had hardened 168 total miles but only 36.5 (22 percent) of these
miles were in high wildfire risk areas. The Energy Safety Office
CALIFORNIA STATE AUDITOR | Report 2021-117 43
March 2022
identified similar problems with other utilities’ mitigation plans that
it approved. For example, it approved SDG&E’s 2021 mitigation plan
despite noting that the utility did not provide sufficient detail on how
it prioritized high fire-threat areas for mitigation activities, such as
moving power lines underground and installing covered power lines.
In its guidelines for utilities’ preparation of their 2022 mitigation
plans, the Energy Safety Office attempted to address the problems
described above by requiring utilities to detail how their risk
models will be used to inform how they prioritize mitigation
activities. However, the office’s internal procedures for reviewing
mitigation plans still contain a fundamental flaw that needs to be
addressed. These procedures indicate that certain deficiencies in
a utility’s mitigation plan should not prevent the office’s approval of a
mitigation plan and that the office may allow the utility to address
these deficiencies in a subsequent mitigation plan. In contrast, other
deficiencies—known as critical issues—are major concerns and must
be addressed before the office can consider the plan for approval. The
procedures provide examples of both critical issues and deficiencies.
However, an example in the procedures that states, “Utility provides
little discussion in how it uses the results of its risk scoring to
determine grid hardening,” is classified as a deficiency that can be
addressed in a subsequent year’s mitigation plan. This procedure and
accompanying example as stated enable the Energy Safety Office to
continue to approve mitigation plans that do not clearly define where
mitigation activities will occur. By not characterizing this example
as a critical issue, the office does not hold utilities accountable for
conducting these activities in areas of highest risk for wildfire.
The Energy Safety Office’s internal procedures
for reviewing mitigation plans still contain a
fundamental flaw that needs to be addressed.
Current Mitigation Plans Do Not Incorporate the Results of
External Reviews
The Energy Safety Office has not required that utilities address in their
mitigation plans the issues identified by oversight mechanisms—such
as audits and external reviews of their mitigation activities—resulting
in plans that are not responsive to previously identified deficiencies.
As discussed earlier, the Federal Monitor reported deficiencies with
PG&E’s vegetation work and also reported that as of August 2020,
PG&E had failed to conduct any of the enhanced inspections of
approximately 1,000 transmission structures in high fire-threat areas
44 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
as planned for in its 2020 inspections. We reviewed PG&E’s 2021
mitigation plan submitted in February 2021 and found that the
utility referenced how it would address the Federal Monitor’s finding
on its vegetation management program, but it did not address the
Federal Monitor’s finding relating to its lack of enhanced inspections.
Although PG&E’s 2021 mitigation plan indicated that it intended to
complete enhanced inspections of transmission structures, the Federal
Monitor reported in November 2021 that PG&E had not in any
previous year met the inspection commitments in its mitigation plans.
Requiring PG&E and other utilities to specifically address these types
of findings from external reviews would help the Energy Safety Office
better hold utilities accountable for achieving year-over-year progress.
Requiring utilities to specifically address
findings from external reviews would
help the Energy Safety Office better
hold utilities accountable for achieving
year‑over‑year progress.
The Energy Safety Office’s director expressed concern that there is no
definitive source for all the oversight mechanisms to which the utilities
are subject. She also stated that she believed tracking and including
issues identified by oversight mechanisms in their mitigation plans
must be the responsibility of the utilities. However, if utilities are to
bear the responsibility for tracking the issues identified by external
reviews, the office needs to update its mitigation plan guidelines to
establish that requirement. By doing so, the office can define the types
of oversight entities, mechanisms, and issues that need to be included
in the mitigation plan and also take steps to verify the information
utilities include.
The CPUC’s Audits Could Be Improved to Ensure That Utilities Are
Performing Critical Wildfire Mitigation Efforts in High Fire‑Threat Areas
The CPUC’s audits play an important role in ensuring that utilities
safely operate the electrical grid, but they could be improved to better
ensure utilities’ compliance and help mitigate the risk of utility-caused
wildfires. The CPUC’s mission is to, among other things, assure that
utility services are safe. According to the program manager for the
CPUC’s Electric Safety and Reliability Branch (safety and reliability
program manager), in addition to conducting incident investigations
and reviewing reports the utilities provide, the CPUC uses audits to
CALIFORNIA STATE AUDITOR | Report 2021-117 45
March 2022
determine whether utilities are in compliance with the rules designed
to ensure that they are safely operating the electrical grid.9 These
audits determine whether utilities are following the construction,
maintenance, and inspection requirements outlined in various
General Orders. For example, some of these General Orders require
utilities to replace electrical equipment that may be at risk of failing,
to perform inspections of their electrical equipment, and to conduct
vegetation management around power lines. However, there are
problems with key aspects of the CPUC’s audit process.
The CPUC does not consistently audit all utility districts, and for
those audits it does perform, it cannot demonstrate that it prioritizes
districts that are in areas of increased fire risk.10 Although the safety
and reliability program manager indicated that the CPUC’s audit
manual calls for it to audit each utility’s districts within a five-year
cycle, we found that the CPUC did not audit each power line
distribution district (distribution district) within the most recent
five-year period, as we show in Figure 12. Specifically, we noted that
during the five-year cycle of 2016 through 2020, the CPUC audited
fewer than 70 percent of the utilities’ distribution districts. The safety
and reliability program manager indicated that the CPUC was unable
to complete all of those audits because the branch had other duties,
including investigating utility-related wildfires, which necessitated
significant efforts and limited its ability to perform additional
audits. However, the safety and reliability program manager also
acknowledged that since 2019, the branch has had a diminished role
in investigating these fires.
The CPUC does not consistently audit all
utility districts, and for those audits it
does perform, it cannot demonstrate that
it prioritizes districts that are in areas of
increased fire risk.
9 We reviewed the CPUC’s distribution and transmission power line audits, which address overhead
and underground electrical systems.
10 Utility districts are geographic service areas designated by utilities.
46 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Figure 12
It Has Been More Than Five Years Since the CPUC Audited Certain Utility Districts
(cid:31)(cid:30)(cid:29)(cid:28)(cid:27)(cid:26)(cid:29)(cid:28)(cid:25)(cid:24)(cid:29)(cid:23)(cid:25)(cid:27)(cid:29)(cid:22)(cid:23)(cid:21)(cid:20)(cid:26)(cid:19)(cid:28)(cid:27)
(cid:18)(cid:24)(cid:19)(cid:18)(cid:28)(cid:27)(cid:17)(cid:16)(cid:27)(cid:19)(cid:21)(cid:19)(cid:15)(cid:18)(cid:25)(cid:19)(cid:26)(cid:27)(cid:18)(cid:22)(cid:26)(cid:27)
(cid:19)(cid:14)(cid:25)(cid:24)(cid:19)(cid:13)(cid:19)(cid:27)(cid:16)(cid:29)(cid:24)(cid:19)(cid:27)(cid:24)(cid:29)(cid:28)(cid:12)(cid:11)(cid:27)
(cid:29)(cid:22)(cid:23)(cid:21)(cid:20)(cid:26)(cid:29)(cid:22)(cid:10)(cid:27)(cid:9)(cid:17)(cid:24)(cid:25)(cid:29)(cid:17)(cid:22)(cid:28)(cid:27)(cid:17)(cid:16)(cid:27)
(cid:8)(cid:20)(cid:25)(cid:25)(cid:19)(cid:11)(cid:27)(cid:7)(cid:30)(cid:18)(cid:28)(cid:25)(cid:18)(cid:11)(cid:27)(cid:18)(cid:22)(cid:26)(cid:27)
(cid:31)(cid:19)(cid:30)(cid:18)(cid:13)(cid:18)(cid:27)(cid:23)(cid:17)(cid:20)(cid:22)(cid:25)(cid:29)(cid:19)(cid:28)(cid:11)(cid:27)
(cid:6)(cid:30)(cid:19)(cid:24)(cid:19)(cid:27)(cid:13)(cid:18)(cid:5)(cid:17)(cid:24)(cid:27)(cid:16)(cid:29)(cid:24)(cid:19)(cid:28)(cid:27)(cid:30)(cid:18)(cid:15)(cid:19)(cid:27)
(cid:17)(cid:23)(cid:23)(cid:20)(cid:24)(cid:24)(cid:19)(cid:26)(cid:27)(cid:29)(cid:22)(cid:27)(cid:25)(cid:30)(cid:19)(cid:27)(cid:9)(cid:18)(cid:28)(cid:25)(cid:4)(cid:27)
LEGEND
Audited between 2016–2020.
Not audited between 2016–2020.
The unmarked areas of the map are served by
other types of electric utilities, such as publicly
owned utilities and rural electric cooperatives
and are not subject to CPUC oversight.
Additional PacifiCorp service territory.*
Source: CPUC utility district audits from 2016 through 2020 and utility district maps.
* According to the CPUC’s Electric Safety and Reliability Branch program manager, a large portion of PacifiCorp’s service territory is national forest,
and approximately 60 percent has designations that limit growth, and thus the need for utility assets. She further explained that no distribution
equipment or customers are present there.
CALIFORNIA STATE AUDITOR | Report 2021-117 47
March 2022
The CPUC did not audit several districts that contain areas of
elevated or extreme fire risk. Notably during the five-year period
from 2016 through 2020, the CPUC failed to conduct audits of
distribution power lines in counties that contain areas of elevated and
extreme fire risk, including portions of Butte, Tehama, and Shasta
counties—where major fires have occurred in the past. Although
the safety and reliability program manager stated that the CPUC
used risk factors identified in the audit manual, including past audit
performance, accident data, or indications of safety or reliability
problems, she was unable to provide any documentation showing
how the risk factors were applied when selecting which districts to
audit. As a result, the CPUC could not demonstrate how it weighs
the risk of utility-caused wildfires when prioritizing the audits
it performs.
We also found that the CPUC does not use its authority to
penalize utilities when its audits uncover violations. In 2014 the
CPUC adopted an electric safety citation program that gave staff
the authority to issue penalties for certain violations of law and
of General Orders, including those identified through audits.
However, as of November 2021, the CPUC had not issued any
penalties resulting from violations that its safety and enforcement
division found during audits. The safety and reliability program
manager informed us that it is the CPUC’s practice to issue
penalties for significant issues, which may be found through
incident investigations where individuals were hurt or killed, or
where buildings were destroyed, but that these types of immediate
safety hazards are rarely found during audits.
The CPUC does not use its authority
to penalize utilities when its audits
uncover violations.
In our review of CPUC audits, we identified several instances
where the CPUC identified violations of General Orders that
were the same as those for which it issued penalties in incident
investigations. For example, the CPUC issued a $2.5 million penalty
to a utility in 2021 for nearly 55,000 violations of a General Order
requiring inspections of distribution poles, and we found that the
CPUC had identified similar issues in at least two of its distribution
district audits. The CPUC identified more than 200 violations of
the same General Order in one 2020 distribution district audit,
and about 2,400 similar violations in a second 2020 distribution
district audit. Additionally, we found that in 2017 the CPUC issued
48 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
a $50,000 penalty to a utility for a single violation of a General
Order requiring vegetation management. Although we identified
three audits that the CPUC performed in 2019 and 2020 that
identified similar violations, it did not issue any penalties for
those violations.
We asked the CPUC for perspective on why it did not issue
penalties for audit findings. The safety and reliability program
manager indicated that penalties may be viewed as a punitive
method for gaining compliance, but they do not necessarily ensure
an increase in the utility’s compliance. However, the CPUC issues
penalties for violations of General Orders it uncovers during
incident investigations, and if it believes that those penalties are
merited, it is not clear why similar violations discovered during
audits should not be similarly penalized. Because the CPUC’s
mission includes assuring that utility services are safe, its focus
should be on preventing deficiencies that could result in negative
outcomes, rather than only imposing penalties after an incident
such as a fire, injury, or death. Although penalties associated with
audit findings may not result in the same dollar amounts as those
applied after an investigation, issuing penalties based on audit
findings would elevate the importance of the safety practices that
CPUC audits review.
Recommendations
Legislature
To better hold utilities accountable for safely operating the electrical
grid, the Legislature should require the CPUC to do the following:
• Create and implement a risk-based audit plan for transmission
and distribution infrastructure audits that prioritizes districts
based on risk factors, including high fire-threat areas, and aligns
with the requirement established in its audit manual to audit
each district at least once every five years.
• Create a schedule of penalties for violations identified through
its audit process and apply the schedule pursuant to its existing
authority to impose penalties established in state law.
Energy Safety Office
To ensure that utilities are targeting the areas of highest fire risk
for mitigation activities, the Energy Safety Office should revise its
internal procedures for reviewing mitigation plans by March 2023
CALIFORNIA STATE AUDITOR | Report 2021-117 49
March 2022
to designate the prioritization of mitigation activities as a critical
issue that must be appropriately addressed before a mitigation plan
can be approved.
To make mitigation plans more responsive to the causes of fires and
serious concerns raised through oversight mechanisms, the Energy
Safety Office should require in its 2023 mitigation plan guidelines
that utilities address issues identified by oversight mechanisms—
such as external audits—in their mitigation plans.
50 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2021-117 51
March 2022
Other Areas We Reviewed
Recent Audits of Utilities’ Mitigation Expenditures
Recent audits of utility expenditures questioned whether the CPUC
should allow the three largest utilities to recover through their rates
approximately $2.5 billion, collectively, as wildfire mitigation costs.
According to the CPUC, ratemaking is done on a prospective basis,
and its practice is not to authorize increased rates to account for
previously incurred costs. The general rate case dictates the electrical
rates that the utilities can charge customers for the cost of owning,
operating, and maintaining their facilities, and they include the cost
of utilities’ efforts to mitigate the risk of causing wildfires. However,
state law requires utilities to track in a specific account (mitigation
account) actual expenditures for fire risk mitigation that are not
otherwise covered by rates approved in their general rate case.
State law also allows utilities the alternative to recover those costs
through an application for cost recovery at the end of the period
covered by the mitigation plan. Under either scenario, the utility
must certify that it did not receive authorization for the costs from a
previous proceeding.
In June 2020—with the Wildfire Safety Division, the predecessor to
the Energy Safety Office, acting as a project manager—CPUC hired
a contractor to assess whether costs in the six utilities’ 2019 and
2020 mitigation plans duplicated expenditures approved in previous
general rate cases. The audit reports for PG&E, SCE, and SDG&E
determined that nearly $2.5 billion in costs were already paid for
through the utilities’ previously approved rates, or that additional
justification and documentation from the utilities was necessary
to make a determination of whether the costs were already paid
for through the utilities’ previously approved rates. The utilities
disagreed with many of the audit results and in several instances
stated either that they did not intend to claim reimbursement for
the costs in question or that they disagreed with the contract auditor
about whether the costs were part of the activities described in their
general rate case. Nevertheless, the contract auditor generally stood
by its findings and in multiple instances stated that utilities should
provide additional information or that the CPUC should carefully
monitor future claims by the utilities to ensure that these costs are
not passed on to customers again in the form of higher rates.
The CPUC’s Energy Division program manager stated that there are
several safeguards in place to prevent utilities from double-charging
customers for the same expenditures. Specifically, she discussed
how the CPUC’s proceedings for setting rates may include requiring
utilities to provide proof that expenditures are different from
those authorized in the past. She also cited the involvement of
others, such as outside stakeholder groups, filing protests during
52 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
those proceedings and in some cases the individual overseeing
the proceeding, the utility itself, or an advocates office ordering or
conducting an audit. However, the recently conducted audits highlight
potential weaknesses in the rate-setting process, and until the CPUC
addresses these findings, questions remain about the appropriateness
of the rates utilities are authorized to charge.
Recommendations
To ensure that it does not authorize cost recovery, and the resulting
rate increases, for activities that were part of a utility’s previous general
rate case, the CPUC should perform audits of the utilities’ wildfire
mitigation costs before approving recovery of those costs. In addition,
the CPUC should implement sufficient safeguards to ensure the
appropriateness of the costs passed on to customers.
To ensure that utilities do not over-recover, or charge ratepayers more
than they should for the activities they perform, the CPUC should
make certain that if utilities request reimbursement for the costs
questioned in the contractor audits, the utilities provide sufficient
quantifiable and detailed analyses to substantiate that the costs were
not paid for through the utilities’ previously approved rates.
CPUC Safety Culture Assessments
The CPUC has not required safety culture assessments of utilities,
which are reviews that emphasize appropriately prioritizing employee
safety and that are responsive to risk factors, such as wildfires—
pursuant to the state law that requires such assessments. An
amendment to state law that took effect in January 2019 established
that the Commission must require a safety culture assessment of
each of the utilities by an independent third-party evaluator at least
once every five years. Because catastrophic safety failures often result
from multiple failures, rather than the action or inaction of a single
individual, a safety culture supports the process of identifying hazards
and implementing adequate safeguards throughout the organization.
Essentially, a safety culture is a set of organizational principles,
beliefs, and norms in which safety is a predominant objective and is
continuously reinforced. Safety culture assessment practices in other
industries often include document reviews and interviews with and
surveys of staff throughout the organization. However, the CPUC did
not initiate a rulemaking for performing safety culture assessments
until October 2021.
The Commission delayed initiating its safety culture assessment
rulemaking for more than two years after the state law took effect.
The amendment to state law requiring these assessments also
CALIFORNIA STATE AUDITOR | Report 2021-117 53
March 2022
established the requirement for utilities to annually prepare and
submit a mitigation plan, among other things. According to the
director for the CPUC’s Safety Policy Division (safety policy director),
in implementing the new state law, the CPUC focused on developing
the process for mitigation plans and developing and implementing
policy related to wildfire cost recovery. He explained that the
CPUC anticipates that it will be ready to begin conducting culture
assessments in 2023. When we asked why the CPUC did not prioritize
the safety culture requirement, the safety policy director indicated
that the five-year period for safety culture assessments seemed less
time sensitive than other requirements, such as developing a process
for annual mitigation plans. According to the program manager
for the Safety Policy Division, the CPUC views the PG&E safety
culture assessment resulting from the San Bruno explosion as the
first assessment conducted under this new state law. However, this
assessment was initiated in April 2016, more than two years before
the law requiring safety culture assessments took effect. Further, the
CPUC had not yet initiated a rulemaking for conducting these safety
culture assessments when the PG&E assessment began. Nonetheless,
until the CPUC begins requiring culture assessments as state law
requires, it lacks assurance of the extent to which utilities’ cultures are
prioritizing safety.
The Energy Safety Office’s Compliance Program
In September 2021, the Energy Safety Office established emergency
regulations for the process it uses to ensure that utilities comply with
mitigation plans and requirements related to mitigating the risk of
wildfires. State law authorizes the office to issue a notice of defect
or notice of violation, which we refer to collectively as compliance
notices, to direct utilities to correct any noncompliance with approved
mitigation plans, laws, regulations, or guidelines, and it authorizes the
office to perform compliance investigations. According to emergency
regulations that took effect in September 2021, a notice of defect
identifies a deficiency, error, or condition that requires correction
because it increases the risk of ignition posed by electrical lines and
equipment. A notice of violation identifies noncompliance with an
approved mitigation plan, law, regulation, or guideline within the
Energy Safety Office’s authority, such as failing to perform inspections
described in a mitigation plan.
The Energy Safety Office’s emergency regulations allow it to issue
compliance notices on a temporary basis, but it is in the process of
creating permanent regulations. The emergency regulations will expire
in June 2022; however, the Energy Safety Office’s general counsel
stated that the office has engaged a contractor to help manage the
implementation of permanent regulations.
54 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
We conducted this performance audit in accordance with generally accepted government auditing
standards and under the authority vested in the California State Auditor by Government Code
section 8543 et seq. Those standards require that we plan and perform the audit to obtain sufficient,
appropriate evidence to provide a reasonable basis for our findings and conclusions based on the audit
objectives. We believe that the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.
Respectfully submitted,
MICHAEL S. TILDEN, CPA
Acting California State Auditor
March 24, 2022
CALIFORNIA STATE AUDITOR | Report 2021-117 55
March 2022
Appendix A
Scope and Methodology
The Joint Legislative Audit Committee (Audit Committee) directed
the California State Auditor to conduct an audit of the role of
the CPUC in ensuring a safe and reliable electrical system in
California. Because the Legislature transferred all of the functions
of the CPUC’s Wildfire Safety Division to the Office of Energy
Infrastructure Safety during the course of our audit, we included
the office in our review. Specifically, we reviewed the CPUC’s audit
process to determine whether it consistently assessed utilities’
compliance with General Orders, determined whether the three
largest utilities submitted required elements for their 2020 safety
certifications, and assessed the CPUC’s efforts to oversee utilities’
power shutoffs. We also reviewed the Energy Safety Office’s review
and approval of mitigation plans and safety certifications. Table A
lists the objectives that the Audit Committee approved and the
methods we used to address them.
Table A
Audit Objectives and the Methods Used to Address Them
AUDIT OBJECTIVE METHOD
1 Review and evaluate the laws, rules, and Reviewed relevant laws and regulations related to electrical grid safety as well as the
regulations significant to the audit objectives. CPUC’s General Orders.
2 Review the CPUC’s mission and determine • Selected and reviewed the approved 2020 safety certifications of the three largest
whether the CPUC is performing all of its required utilities, each with more than 250,000 customers.
functions related to overseeing the safety of the • Determined whether the utilities submitted all required elements for their 2020 safety
electrical system. certifications.
• Reviewed the CPUC records of completed audits to determine whether the CPUC
performed audits from 2016 through 2020 in a timely manner.
• Evaluated the CPUC’s process for complying with the requirement in state law that
utilities submit safety culture assessments.
• Reviewed the CPUC’s process for evaluating the sufficiency of RAMPs. We found that
although the CPUC’s development of this process is ongoing, it has implemented
requirements for utilities to demonstrate that they are prioritizing safety in their risk
framework. The CPUC is currently undertaking a rulemaking proceeding to improve
this process.
• Determined whether the Energy Safety Office issued any corrective actions before
approving the utilities’ 2021 mitigation plans.
continued on next page . . .
56 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
AUDIT OBJECTIVE METHOD
3 For the past five years, evaluate the steps that the • Obtained and reviewed budgeted and actual expenditures for the CPUC for the past
CPUC has taken to oversee the safety of utilities’ five fiscal years.
electric systems by determining the following: • Reviewed budget change proposals submitted by the CPUC and the Energy Safety
Office over the past five years, from fiscal years 2016–17 through 2020–21. We
a. The staffing and budget resources the CPUC has concluded that the CPUC requested additional staff positions from fiscal years
allocated to this purpose. 2017–18 through 2020–21, some of which were positions for the establishment of
the Energy Safety Office.
b. Whether the CPUC has assessed needed
• Analyzed the Energy Safety Office’s data to determine the total mileage of utility
infrastructure improvements.
power lines in the State and the total mileage of utility power lines in high fire-threat
areas. We found that the six investor-owned utilities reported to the Energy Safety
c. Whether the CPUC has developed all reasonable
Office that they have nearly 277,000 miles of power lines in the State, and of those,
wildfire mitigation protocols.
more than 74,000 miles are in high fire-threat areas.
d. Whether the CPUC has identified and procured • Determined the total miles of power lines that have undergone improvement to
needed wildfire mitigation equipment. mitigate the risk of wildfire in fiscal year 2020–21—such as covering conductors,
burying lines, and vegetation removal using available CPUC and Energy Safety Office
GIS data.
• Obtained data from the CPUC for the past five years to determine the number and
location of fires the three largest utilities reported causing.
• Obtained power line data from the CPUC and the Energy Safety Office but
determined that both entities lacked the historical data necessary for us to determine
how many miles of power lines in high fire-threat areas the utilities have improved to
mitigate the risk of wildfire for the last five years.
• Obtained data from the CPUC for the past five years to determine the number and
location of fires caused by the three largest utilities.
• Reviewed standards for equipment in other localities and countries and found few
requirements for installing covered power lines or otherwise hardening electrical
grids. We found that Victoria, a state in Australia, requires that all new or replaced
electrical lines be either covered or underground. We discussed utilities’ needs to
make improvements to the electrical grid in our report.
• Obtained CPUC’s perspective on setting design standards for power line hardening
in high fire-threat areas. CPUC expressed concerns that establishing design standards
for equipment in high fire-threat areas would limit flexibility and innovation and
would not be a good alternative to its risk-based decision-making oversight.
4 For the past five years, review the CPUC’s efforts to • Reviewed factors the CPUC may evaluate after a power shutoff to determine
fulfill its mission through its oversight of utilities’ reasonableness.
power shutoffs by determining the following: • Reviewed the CPUC’s process for evaluating post-event reports to determine if the
process is sufficient and appropriate. Selected five power shutoff post-event reports
a. Whether the CPUC’s oversight decisions have and determined whether the CPUC’s assessment addressed key elements.
been objectively reasonable and consistent
• Determined whether CPUC’s power shutoff draft compendium includes key elements
with its mission, state laws, and CPUC rules and
from the relevant CPUC General Orders.
regulations.
• Reviewed the CPUC’s efforts to track, measure, and evaluate utilities’ corrective
b. Whether the CPUC’s efforts have been actions in response to post-event report findings for the five reports we selected. We
appropriately targeted and whether determined that it does not currently follow up on these issues.
the outcomes of these efforts are being • Reviewed 15 post-event reports from 2020 and 2021 and determined if there was
appropriately tracked, measured, and evaluated. damage to the utility’s infrastructure during the shutoff that could have created a
wildfire ignition had the shutoff not occurred.
c. The extent to which the CPUC is reporting
accurate and reliable information and data on
power shutoffs.
5 Evaluate the processes the CPUC has established • Determined whether the CPUC or the Energy Safety Office assesses whether the
for reviewing and approving utilities’ plans for thresholds utilities use for triggering a power shutoff are sufficient and appropriate
power shutoffs or, in the case of PG&E, its biweekly and concluded that they do not perform such assessments.
reports. Include an identification and evaluation • Identified the criteria for PG&E’s biweekly reports established in a Commission ruling.
of the criteria the CPUC uses to review and approve We reviewed two biweekly reports and found that they contained the required
the plans and reports. elements. We also determined that the CPUC released PG&E from the requirement to
submit biweekly reports in November 2021.
CALIFORNIA STATE AUDITOR | Report 2021-117 57
March 2022
AUDIT OBJECTIVE METHOD
6 Evaluate whether any identified concerns should Interviewed key staff and reviewed relevant materials to determine if the Energy Safety
be addressed through changes in state law or the Office requires utilities to address issues identified by oversight mechanisms in their
CPUC’s practices. mitigation plans.
7 Review and assess any other issues that are • Reviewed relevant program information and determined that the microgrid incentive
significant to the audit. program is currently designed to incentivize placement of microgrids in areas that
are at most risk for power shutoffs and that will be most adversely affected by power
outages. The anticipated program launch date is 2022.
• Assessed the criteria for the CPUC’s solar incentive program and concluded that
it provides financial incentives to increase grid resiliency for communities in high
fire-threat districts.
• Assessed the criteria for the CPUC’s net energy metering (NEM) program and
interviewed staff. The CPUC has not, to date, adopted a decision relating to NEM that
prioritizes high fire-threat districts.
Source: Audit workpapers.
Assessment of Data Reliability
The U.S. Government Accountability Office, whose standards
we are statutorily obligated to follow, requires us to assess the
sufficiency and appropriateness of the computer-processed
information we use to support our findings, conclusions,
and recommendations.
In performing this audit, we relied on extracts from the CPUC’s
accounting system to determine its total expenditures for regulatory
purposes and its expenditures related to regulating electric utilities
for fiscal years 2016–17 through 2020–21. The data came from the
California State Accounting and Reporting System (CALSTARS)
and the Financial Information System for California (FI$Cal).
However, a report our office issued in February 2022 identified
findings in FI$Cal’s overall information technology general controls
environment.11 These deficiencies resulted in pervasive risks that
impact the ability to rely on FI$Cal data used for financial reporting.
Because of the multiple systems involved and our inability to rely on
information reported in FI$Cal, it was not cost-effective to conduct
a data reliability assessment.
We obtained cost data for large wildfires and other significant
events from 2015 through 2021 from the National Interagency Fire
Center to identify fire suppression costs. Because we use these
data solely for background or context, we determined that a data
reliability assessment was not necessary.
11 State of California: Internal Control and Compliance Audit Report for the Fiscal Year Ended
June 20, 2020, Report 2020-001.1.
58 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
We obtained data from the CPUC identifying the microgrid
projects funded through the EPIC program from 2015 through 2020
to determine the number of microgrids it funded. Because we used
these data solely for background or context, we determined that a
data reliability assessment was not required.
We obtained a list of utility distribution districts from the CPUC
to determine whether it had performed audits of each district. To
evaluate the data, we performed dataset verification and identified
no issues. We verified the accuracy and completeness of the data
by comparing the CPUC’s utility distribution district list to the
utilities’ district maps and found that the list did not include
three utility districts. We obtained corrected information that
aligned with the district maps and used this list for our analysis.
Although we found the CPUC’s list of utility district data to be not
sufficiently reliable for the purposes of determining the full list of
utility distribution districts, the corrected information provided
sufficient evidence in total to support our findings, conclusions,
and recommendations.
We obtained ignition data reported by PG&E, SCE, and SDG&E
to the CPUC from 2015 through 2020 to determine the causes
of utility-caused ignitions. To evaluate these data, we performed
dataset verification procedures and electronic testing of key data
elements and did not identify any issues. We were unable to
perform accuracy and completeness testing for these data because
the three utilities provided the ignition data to the CPUC; thus the
data cannot be corroborated. As a result, we concluded that they
are of undetermined reliability. Although this determination
may affect the precision of the numbers we present, there is
sufficient evidence in total to support our findings, conclusions,
and recommendations.
We obtained data on outages caused by PG&E’s power-line
settings program from July 2021 through November 2021 from the
CPUC. We used these data to determine the number of unplanned
outages, the average outage time per customer, and the number of
customers impacted as a result of these outages. To evaluate these
data, we performed dataset verification procedures and electronic
testing of key data elements and did not identify any issues. We
were unable to perform accuracy and completeness testing for these
data because it is the only source of unplanned outage data available
and therefore could not be compared against another source. As a
result, we concluded that the data are of undetermined reliability.
Although this determination may affect the precision of the
numbers we present, there is sufficient evidence in total to support
our findings, conclusions, and recommendations.
CALIFORNIA STATE AUDITOR | Report 2021-117 59
March 2022
We obtained CPUC data on power shutoff events since 2013
to determine whether the CPUC is reporting accurate and
complete information on the power shutoff events and to calculate
summary information regarding those events. We performed
accuracy testing on a random sample of five power shutoff events
by tracking key data elements to their supporting post-event
reports, and we found more than one error each in the power
shutoff event end dates and the total customers impacted. We
also traced all post-event reports available on the CPUC website
to the CPUC data to ensure that all power shutoff events from
2017 through 2021 were accounted for in the data. We found that
data for five power shutoff events were missing, and we compiled
summary information for those missing events. We concluded that
the detailed data were not sufficiently reliable for our purposes.
Although this determination may affect the precision of the
numbers we present, there is sufficient evidence in total to support
our findings, conclusions, and recommendations.
We relied on electronic data obtained from the Energy Safety Office
that contain geographical data it obtained from the six utilities
for the period July 2020 through June 2021. We performed
electronic testing of the data and interviewed staff knowledgeable
about the data. We found the Energy Safety Office’s data to be of
undetermined reliability for our purpose of determining the status
of power lines throughout the State and assessing the utilities’
mitigation efforts. Although this determination may affect the
precision of the numbers we present, there is sufficient evidence in
total to support our findings, conclusions, and recommendations.
60 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2021-117 61
March 2022
Appendix B
Summary of Public Safety Power Shutoffs
Table B reflects the total number of power shutoff events the
utilities implemented from 2013 through 2021. The table includes
the minimum and maximum length of each power shutoff and the
total number of customers affected per event.
Table B
Summary of Public Safety Power Shutoff (PSPS) Events
MINIMUM AND MAXIMUM
LENGTH OF POWER TOTAL CUSTOMERS
UTILITY PSPS YEAR PSPS START DATE PSPS END DATE SHUTOFF (HOURS) IMPACTED
SDG&E 2013 5-Oct 6-Oct 5.52–8.88 183
SDG&E 2014 14-Jan 15-Jan 19.52–32.1 85
SDG&E 14-May 15-May 7.43–32.3 1,192
SDG&E 24-Nov 25-Nov 9.45–12.62 90
SDG&E 2017 21-Sep 22-Sep 18.33–18.33 3
SDG&E 20-Oct 21-Oct 37.97–37.97 3
SDG&E 23-Oct 25-Oct 6.1–50.82 175
SDG&E 5-Dec 11-Dec 21.07–144.87 2,164
SDG&E 14-Dec 15-Dec 9.12–17.28 658
PG&E 2018 14-Oct 17-Oct 12.6–60.38 60,086
SDG&E 15-Oct 16-Oct 7.08–27.7 379
SDG&E 19-Oct 20-Oct 30.53–30.53 19
SDG&E 11-Nov 16-Nov 5.48–93.68 24,081
PG&E 2019 8-Jun 9-Jun 11.77–20.63 22,327
SCE 16-Sep 19-Sep * 14,500
PG&E 23-Sep 26-Sep 0.4–32.12 69,627
SCE 24-Sep 24-Sep 5.8–5.8 85
PG&E 5-Oct 6-Oct 12–17.7 11,304
PG&E 8-Oct 12-Oct 5.37–89.13 728,980
SCE 9-Oct 12-Oct 0.02–62.77 24,113
SDG&E 10-Oct 11-Oct 18.53–23.72 395
SCE 16-Oct 21-Oct 3.78–25.37 440
PG&E 23-Oct 25-Oct 5.13–51.55 176,620
SCE 23-Oct 28-Oct 2.32–106.18 30,958
SDG&E 24-Oct 1-Nov 0.13–58.25 47,616
SCE 27-Oct 3-Nov 4.87–110.33 126,364
PG&E 26-Oct 4-Nov 0.02–162.77 941,269
SCE 17-Nov 17-Nov 4.7 49
continued on next page . . .
62 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
MINIMUM AND MAXIMUM
LENGTH OF POWER TOTAL CUSTOMERS
UTILITY PSPS YEAR PSPS START DATE PSPS END DATE SHUTOFF (HOURS) IMPACTED
SDG&E 17-Nov 18-Nov * 21
PG&E 20-Nov 21-Nov 7.43–38.68 49,086
SCE 25-Nov 27-Nov 5.67–42.8 1,192
SCE 2020 2-Aug 4-Aug 44.27 17
PG&E 7-Sep 13-Sep 0.03–133.83 168,599
SDG&E 8-Sep 9-Sep 3.4–13.5 49
SCE 9-Sep 11-Sep 8.92–54.78 252
PacifiCorp 13-Sep 14-Sep 7.6–32.9 2,559
PG&E 26-Sep 29-Sep 14.65–60.48 64,295
PG&E 13-Oct 17-Oct 0.02–62.95 40,574
SCE 16-Oct 16-Oct 4.5–9.75 86
PG&E 21-Oct 23-Oct 7.2–47.48 30,154
PG&E 25-Oct 28-Oct 1.45–78.92 345,470
SCE 26-Oct 28-Oct 7.08–57.02 36,257
SDG&E 26-Oct 27-Oct 5.47–8.12 4,373
SCE 6-Nov 7-Nov 3.2–20.65 1,327
SCE 16-Nov 18-Nov 2.67–38.17 506
SCE 26-Nov 28-Nov 0.27–53.43 20,619
SCE 2-Dec 4-Dec 0.32–56.15 63,494
SDG&E 2-Dec 9-Dec 12.1–61.68 89,505
PG&E 2-Dec 3-Dec 0.76–22.07 617
SCE 7-Dec 11-Dec 0.27–53.75 78,997
SCE 18-Dec 24-Dec 0.18–31.48 27,513
SDG&E 23-Dec 24-Dec 7.58–23 6,797
SCE 2021 14-Jan 21-Jan 3.52–175.83 116,234
PG&E 18-Jan 26-Jan 10.7–184.02 5,099
SCE 13-Apr 13-Apr 2.87 78
PG&E 17-Aug 20-Aug 15.98–62.65 48,155
PacifiCorp 17-Aug 18-Aug 4.77–9.2 1,953
PG&E 20-Sep 21-Sep 7.72–18.58 2,968
SCE 30-Sep 30-Sep 9.82 9
PG&E 11-Oct 14-Oct 11.98–79.35 23,504
SCE 11-Oct 12-Oct 20.17–21.05 40
SCE 15-Oct 16-Oct 5.2–26.27 67
PG&E 15-Oct 16-Oct 13.17–39.42 666
SCE 22-Oct 22-Oct 7.05 112
SCE 24-Nov 26-Nov * 78,514
SCE 21-Nov 22-Nov * 5,235
SDG&E 24-Nov 26-Nov * 5,858
Source: The CPUC’s utility-reported power shutoff data.
* During our data reliability assessment, we identified five events not included in the CPUC’s data. According to the CPUC, it inadvertently excluded
two 2019 power shutoffs and it did not include three 2021 power shutoffs because the utilities had not yet submitted their data in the correct
format. We obtained general information regarding the power shutoffs, but detailed duration information was not available.
CALIFORNIA STATE AUDITOR | Report 2021-117 63
March 2022
STATE OF CALIFORNIA GAVIN NEWSOM, Governor
PUBLIC UTILITIES COMMISSION
.
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3298
March 4, 2022
Michael Tilden, CPA*
Acting California State Auditor
621 Capitol Mall, Suite 1200
Sacramento, CA 95814
CALIFORNIA PUBLIC UTILITIES COMMISSION RESPONSE TO CSA AUDIT (2021-
117) - ELECTRICAL SYSTEM SAFETY AUDIT
Dear Mr. Tilden:
The California Public Utilities Commission (CPUC) hereby provides our response to the draft
report findings of the California State Auditor’s (CSA) report entitled, Electrical System Safety:
California’s Oversight of the Efforts by Investor-Owned Utilities to Mitigate the Risk of Wildfires Needs
Improvement.
The CPUC is committed to the continuous improvement of its operations. Accordingly, the CPUC
will establish a corrective action plan and timelines toward implementing the recommendations
identified in this report.
The CPUC appreciates the work performed by the CSA and the opportunity to provide our
response to the findings. If you have further questions, please contact me at (415) 757-7844 or Staff
Attorney Matt Yergovich at (415) 596-3474.
Sincerely,
Rachel Peterson
Executive Director
Enclosure
cc: Alice Reynolds, President
California Public Utilities Commission
Christine Hammond, General Counsel
Legal Division
Angie Williams, Director
Utility Audits, Risk and Compliance Division
* California State Auditor’s comments begin on page 67.
64 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
CALIFORNIA PUBLIC UTILITIES COMMISSION RESPONSE TO CSA AUDIT (2021-117) -
ELECTRICAL SYSTEM SAFETY OVERSIGHT AUDIT
“California’s Oversight of the Efforts By Investor-Owned Utilities to Mitigate the Risk of Wildfires Needs Improvement”
Finding 1: The CPUC’s Audits Could Be Improved to Ensure That Utilities are Performing
Critical Wildfire Mitigation Efforts In High-Risk Areas.
To better hold utilities accountable for safely operating the electrical grid, the Legislature should
require the CPUC to do the following:
Recommendation A: Create and implement a risk-based audit plan for transmission and
distribution infrastructure audits that prioritizes districts based on risk factors, including in
high fire-threat areas, and aligns with the requirement established in its audit manual to audit
each district at least once every five years.
CPUC Response: ☒ Agrees ☐ Disagrees with the recommendation or partially agrees.
This recommendation is for the Legislature. The CPUC also agrees that it should use a risk-based
approach for audits and will take steps to ensure its procedures reflect this approach and are
implemented.
Additionally, the CPUC notes the following considerations relevant to create and implement a risk-
based audit plan.
The term “audit” associated with this recommendation refers to the reviews and inspections
performed by the CPUC’s Safety Enforcement Division (SED). The CPUC appreciates that the
California State Auditor’s report recognizes the CPUC’s constitutional responsibilities to ensure
safety more broadly than just wildfire safety; consistent with this mandate the CPUC takes an “all
risks” approach. The CPUC will also consider whether this recommendation can be implemented
with existing resources.
Recommendation B: Create a schedule of penalties for violations identified through its
audit process and apply the schedule pursuant to its existing authority to impose penalties
established in state law.
CPUC Response: ☐ Agrees ☒ Disagrees with the recommendation or partially agrees.
This recommendation is for the Legislature. The CPUC notes that if the Legislature adopts the
1 recommendation, it will require implementation time to conform the changes to the Commission’s
existing enforcement orders. The CPUC also partially agrees in that it will consider options for
penalty schedules, noting they must take into account the following considerations relevant to the
development of a schedule of penalties, among others.
First, the CPUC notes the importance of its statutory Notice of Violations (NOV) enforcement
mechanism. NOVs serve as an initial, timely first step of enforcement that can be used to correct
2
utility deficiencies to prevent negative outcomes without citations or penalties. An NOV identifies
potential (alleged) violations and provides the utility an opportunity to rectify the deficiency
promptly.
Page 1 of 2
CALIFORNIA STATE AUDITOR | Report 2021-117 65
March 2022
Second, the CPUC notes that it will require time to undertake proceedings necessary to expand the
CPUC’s existing rules delegating penalty authority to SED staff. See Decision 16-09-055 (Phase
Two Decision Adopting Necessary Improvements and Refinements to the Gas and Electric Safety
Citation Programs). Any penalty schedule proposed for the Commission’s consideration must
satisfy requirements prescribed by the Constitution, statute, and Commission orders.
Finding 2: (In Re:) Recent Audits of Utilities’ Mitigation Expenditures.
Recommendation: To ensure that it does not authorize cost recovery, and the resulting rate
increases, for activities that were part of a utility’s previous general rate case, the CPUC
should perform audits of the utilities’ mitigation costs before approving recovery of those
costs. In addition, the CPUC should implement sufficient safeguards to ensure the
appropriateness of the costs passed on to customers.
CPUC Response: ☒ Agrees ☐ Disagrees with the recommendation or partially agrees.
The CPUC agrees it is critical to not allow double-recovery of costs. The CPUC is committed to
taking additional actions to assess whether safeguards provided through current ratemaking
processes and wildfire mitigation cost reviews ensure appropriate cost approval, or if additional
safeguards or audits (a term that includes a variety of possible cost recovery review processes) are
needed and feasible.
First, to provide an overview of existing processes that provide safeguards against double recovery
of costs: The CPUC’s evidentiary hearing litigation serves as a critical platform for the CPUC and
other experts to scrutinize, test, and challenge the veracity and prudence of utilities’ costs. These
heavily-litigated proceedings place the burden of proof on utilities to demonstrate the
reasonableness of proposed costs and allow intervenors to challenge them. Through these
processes, many of which are dictated by statute, the CPUC ensures that costs approved are just and 3
reasonable, and incremental where the application is filed outside of a general rate case. We will
review these safeguards to ensure they sufficiently protect ratepayers in light of the significant costs
being incurred to prevent destructive wildfires.
Second, the CPUC agrees that it should assess the need for additional audits (or other cost recovery
reviews) of wildfire mitigation expenditures conducted on appropriate time frames to inform cost
recovery. An assessment is required to develop a specific course of action. The CPUC would
require additional resources if consultants are engaged to validate utility wildfire mitigation spending
approved in general rate cases and other decisions. These studies require time to complete,
compliance with state contracting processes, and oversight by CPUC staff. The CPUC must also
consider what time frame is most valuable to best inform general rate cases and other cost recovery
applications. Accordingly, the CPUC is committed to assessing and developing recommendations
on how to leverage the benefits of audits of utility wildfire mitigation expenditures on a meaningful
and practicable time frame to inform ongoing approvals of wildfire mitigation costs.
Page 2 of 2
66 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2021-117 67
March 2022
COMMENTS
CALIFORNIA STATE AUDITOR’S COMMENTS ON
THE RESPONSE FROM THE CALIFORNIA PUBLIC
UTILITIES COMMISSION
To provide clarity and perspective, we are commenting on the
response to our audit from the CPUC. The numbers below
correspond to the numbers we have placed in the margin of
the response.
Our recommendation is not intended to suggest that the CPUC 1
should issue penalties in violation of existing Commission orders.
Rather, our recommendation is that the Legislature require the CPUC
to create a schedule of penalties for violations, and apply that schedule
pursuant to its existing authority to impose penalties established
under state law. Nevertheless, as we state on pages 47 and 48, if the
CPUC believes that imposing penalties is merited when a person
is injured or dies, or buildings have been destroyed, it is not clear
why similar violations discovered during audits should not also
be penalized.
The CPUC’s existing methods for following up on the violations 2
identified through its audits does not provide adequate assurance that
those violations are addressed in a timely manner. According to the
CPUC’s safety and reliability program manager, it requires utilities
to respond in writing to the violations it identifies. For violations of
certain general orders, the utility may provide a response indicating
that it will resolve the violation within a year. However, the CPUC
does not perform physical inspections or require in every instance that
a utility provide evidence that the work was completed. Moreover, as
we note on page 48, the CPUC already issues penalties for violations
of General Orders it uncovers during incident investigations, so it is
not clear why similar violations discovered during audits should not
be similarly penalized. Because the CPUC’s mission includes assuring
that utilities’ services are safe, its focus should be on encouraging
utilities to proactively identify and address deficiencies that could
result in negative outcomes. If CPUC issued penalties associated with
audit findings, it would elevate the importance of the utilities’ safety
practices, and thus, we are recommending that the Legislature direct
the CPUC to create a schedule of penalties for violations identified
through its audit process.
We stand by our recommendation that the CPUC should perform 3
audits of utilities’ mitigation costs before approving recovery of those
costs. Although the CPUC cites the existence of various safeguards
to prevent utilities from duplicating expenditures approved in
68 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
previous general rate cases, which we describe on pages 51 and 52,
relying on the efforts of other entities to question these costs is
not a systematic method of fulfilling the CPUC’s responsibility of
ensuring that they are appropriate. The CPUC also describes placing
the burden of proof on utilities to demonstrate the reasonableness
of costs, but the requirement to do so provides little value without
systematic oversight. Accordingly, it is unclear whether the CPUC’s
current practices identify cost recovery for activities that were a
part of a utility’s previous general rate case. We believe that our
recommendation for the CPUC to perform audits of the utilities’
mitigation costs before approving recovery of those costs will
strengthen the CPUC’s processes and better ensure utilities do not
recover costs approved in a previous general rate case.
CALIFORNIA STATE AUDITOR | Report 2021-117 69
March 2022
State of California – A Natural Resources Agency Gavin Newsom, Governor
OFFICE OF ENERGY INFRASTRUCTURE SAFETY Caroline Thomas Jacobs, Director
715 P Street, 20th Floor | Sacramento, CA 95814
916.902.6000 | www.energysafety.ca.gov
March 4, 2022
Michael Tilden, CPA *
Acting California State Auditor
1621 Capitol Mall, Suite 1200
Sacramento, CA 95814
Dear Acting Auditor Tilden,
The Office of Energy Infrastructure Safety (Energy Safety) acknowledges receipt by the Natural
Resources Agency of the California State Auditor's (CSA) redacted draft report titled
“California’s Oversight of the Efforts By Investor-Owned Utilities to Mitigate the Risk of
Wildfires Needs Improvement” (Report).
Energy Safety appreciates CSA’s audit and recommendations intended to make the state safer.
Utility wildfire safety is an immensely complex problem that requires expert technical
knowledge and the ability to balance overarching, and sometimes competing, goals to achieve
meaningful change. As Energy Safety has said in many forums, utilities will not get ahead of
their wildfire risk until they reimagine how they build, operate, and manage their
infrastructure. Energy Safety shares the CSA’s perspective that the utilities must move faster 1
and be smarter.
Energy Safety shares many of the specific goals identified such as reducing adverse effects on
Californians from public safety power shutoffs and unplanned outages as well as incentivizing
utilities to advance their risk modeling and mitigation prioritization. Energy Safety defers to the
Legislature as to whether the recommended legislative changes should be made to the statute.
However, Energy Safety has the authority it needs to act on the concerns identified in the 2
Report. In the two years since its inception, Energy Safety has implemented many
improvements to regulatory safety oversight as it has grown from the Wildfire Safety Division in
the CPUC to the Office of Energy Infrastructure Safety under the California Natural Resources
Agency. As this nascent department matures, it will continue to learn and drive utilities to move
toward long-term wildfire safety.
Energy Safety’s implementation of the legislative framework is progressing. In the short time
since the birth of the department, there has been a massive shift in the way utilities plan for
safety and implement those plans. Energy Safety has pushed the utilities to develop risk
modeling, and respond to that modeling, in a way that did not exist before the department’s
creation. Energy Safety is confident this progress in wildfire safety planning and the associated
* California State Auditor’s comments begin on page 79.
70 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Michael Tilden
March 4, 2022
Page 2 of 9
outcomes will compound over time and result in a vastly safer California. Energy Safety’s
responses to specific recommendations are detailed below.
Procedural Concerns
Energy Safety must caveat its response by noting that it was not provided an opportunity to
3 review this report in its entirety when responding. Roughly 30% of the draft report Energy
Safety received was redacted, notwithstanding that those portions appear to address the work
that Energy Safety leadership and staff conducted as the Wildfire Safety Division when it was
housed in the CPUC. One of three section headers and an entire recommendation, as well as
many other pages of text, were redacted. Accordingly, readers of the Report should be aware
that it may contain errors or statements that Energy Safety disagrees with, and that are not
addressed in this response, because Energy Safety was not permitted to review them prior to
preparing this response. Indeed, because Energy Safety has specialized expertise in the matters
addressed by the Report, and Energy Safety staff has personal experience related to the
functioning of the Wildfire Safety Division, to the extent those redacted portions address that
experience and expertise, Energy Safety may provide further responses once the full Report is
shared with the public. Energy Safety encourages readers of this response to consider it as
preliminary until Energy Safety has had the chance to review this report in its entirety.
Background
On January 1, 2020, the WSD was established within the CPUC by Assembly Bill 1054 (Holden)
and Assembly Bill 1111 to oversee and enforce electrical corporations’ compliance with new
wildfire safety laws. Effective July 1, 2021, the division, including its leadership, staff,
procedures, and authority, was transferred to the California Natural Resources Agency and
reconstituted as a new department, called Energy Safety. Energy Safety's mission is to advance
long-term utility wildfire safety by developing data-driven, comprehensive utility wildfire
mitigation evaluation and compliance criteria, collaborating with local, state and federal
agencies, and supporting efforts to improve utility wildfire safety culture and innovation.
The new regulatory framework created by AB 1054 and AB 111 is a unique and innovative
approach to drive reduction of utility-related wildfire risk. Designed to incentivize safety
investments and ensure utilities improve safety outcomes, the Legislature’s approach relies on
both incentives and deterrents.
To implement this new regulatory framework, Energy Safety recruited a talented pool of
engineers, scientists, and analysts with a breadth of experience related to the complex issue of
utility-related wildfire risk. In a very short time, Energy Safety has developed a new,
comprehensive and data-informed approach for evaluating utility-related wildfire safety. Since
January 2020, the WSD—and now Energy Safety—has increased standardization, transparency,
and objectivity in the wildfire mitigation plan evaluation process. This includes designing
1 AB 111 (Committee on Budget)
CALIFORNIA STATE AUDITOR | Report 2021-117 71
March 2022
Michael Tilden
March 4, 2022
Page 3 of 9
performance metrics to monitor progress on mitigation initiatives and their impact on safety
outcomes, establishing a rigorous compliance assurance program, implementing a first-of-its-
kind utility wildfire maturity model, and developing a unique safety culture assessment process
that reviews both traditional workplace safety dynamics and wildfire and public safety.
In two short years, in addition to hiring, equipping, and training a full team of experts,
developing procedures and protocols, and successfully standing up both a new division within
the CPUC and subsequently a new department under the Natural Resources Agency—Energy
Safety has successfully completed all its statutory responsibilities, including:
• Evaluated 17 wildfire mitigation plans across more than 50 specific technical areas,
including within grid design, asset inspections and maintenance, vegetation
management, and grid operations
• Designed and conducted 8 first-of-its-kind safety culture assessments
• Reviewed for approval or issuance 9 executive compensation structures and 9 safety
certification submissions
• Conducted more than 14,000 inspection activities
• Identified and directed corrective action for more than 500 defects and violations
• Conducted 15 performance audits and independent evaluations of mitigation plan
implementation
• Issued numerous policy guidelines to facilitate the above.
Foundational to all of Energy Safety’s work is its insistence that California’s electrical
corporations constantly and continually improve their wildfire safety efforts. Energy Safety
expects and pushes utilities to do more and to be better—to think more deeply, be smarter,
and be more aggressive in their wildfire mitigation efforts.
Energy Safety is committed to continuing to build upon the novel and innovative regulatory
framework designed by AB 1054 and AB 111 in the years to come and further its mission to
drive reduction of utility-related wildfire risk.
Management Response to Recommendations
Recommendation 1: To reduce the number of power shutoffs, rather than just reducing their
scope and impact, the Legislature should amend the shutoff reduction law to require that
utilities describe in their mitigation plans the improvements that would be necessary to prevent
shutoffs on the circuits routinely affected by them, such as installing covered power lines.
Response 1:
Energy Safety agrees that proactive power shutoffs, known as public safety power shutoffs, are
inconvenient, expensive, and can have adverse effects on Californians and public safety. Energy
Safety also agrees that utilities must make improvements to the electrical grid, commit to
thoughtful and well-planned vegetation management, and harden powerlines to greatly reduce
72 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Michael Tilden
March 4, 2022
Page 4 of 9
the need for public safety power shutoffs. Currently, California Public Utilities Code section
8386(c)(8) requires that, as part of their mitigation plans, utilities identify circuits that have
frequently been deenergized and the measures taken or planned to reduce the need for, and
impact of, future deenergization of those circuits.
Energy Safety defers to the Legislature regarding this recommendation but notes that this
4 statutory framework was just amended in 2021. Energy Safety’s authority is not limited to
requesting information about the scope and impact of public safety power shutoffs. The law
requires utilities to describe the measures taken or planned to reduce the need for these
shutoffs. Energy Safety has operationalized this requirement in its Wildfire Mitigation Plan
Guidelines. (See Wildfire Mitigation Plan Update Guidelines, Attachment 2: 2022 Wildfire
Mitigation Plan Update Guidelines Template, pages 33-34.)
The current statutory framework requires the utilities to plan for continued, incremental
reduction of the use of shutoffs. As utilities implement upgrades and improvements to reduce
the risk of wildfires, the need for these events will decrease. As the Report explains, in 2012 the
CPUC concluded that California Public Utilities Code Sections 451 and 399.2(a) give utilities the
authority under state law to proactively shut off electric power to customers when necessary to
5 protect public safety. Directing utilities to eliminate public safety power shutoffs is outside the
purview and authority of Energy Safety and may be at odds with existing law and CPUC
precedent.
Recommendation 2: To address the risks and hazards resulting from future unplanned outages,
the Legislature should amend the shutoff reduction law to include circuits frequently de-
energized as a result of utilities’ altering settings on equipment.
Response 2:
Unplanned outages are disruptive and can create cascading consequences to public safety.
Similarly, overly sensitive protective settings can have significant, detrimental effects and must
be balanced with maintaining a reliable grid. The aim of these protective devices is safe
operation, but they must also strike a balance with reliability – two objectives that sometimes
conflict. Energy Safety defers to the Legislature regarding this recommendation for statutory
change but notes that the current statutory framework was created to balance the competing
6 objectives of reliability and safety. This recommendation prioritizes reliability over safety. While
unplanned outages due to these devices affecting thousands of customers are inconvenient and
present potential safety risks, those risks must be viewed in light of the safety, ecological, and
climatological risks associated with catastrophic wildfires.
The “shutoff reduction law”, the focus of this recommendation, applies specifically to planned
shutoffs implemented as a wildfire risk reduction measure. The recommendation would include
7 in that law a subset of “unplanned outages” that are triggered by unexpected events, thus
expanding the scope of the shutoff law, which was enacted to reduce planned public safety
CALIFORNIA STATE AUDITOR | Report 2021-117 73
March 2022
Michael Tilden
March 4, 2022
Page 5 of 9
power shutoffs. Further, Energy Safety can obtain the recommended information and will
consider its appropriateness for inclusion in 2023 Wildfire Mitigation Plan Guidelines.
Energy Safety is proactively addressing protective powerline settings. Energy Safety’s analysis of
grid operations in 2022 will evaluate the efficacy of this strategy in terms of ignition reduction
and assess utilities’ long-term strategies to reduce the use of protective powerline setting
measures. Through that process, Energy Safety will develop data and greater understanding
regarding utilities’ use of powerline settings as a safety measure and its impact on ignition risk
reduction—information that will be helpful to inform policymaking on this topic. In the
meantime, discouraging a utility from using their operator discretion and expertise in the use of 8
protective devices to operate the grid as safely as possible could be dangerous.
Recommendation 3: To ensure safety certifications encourage utilities to invest in safety and
limit wildfire risk, the Legislature should require that as a prerequisite to issuing a safety
certification, the Energy Safety Office’s most recently completed compliance assessment of a
utility’s mitigation plan conclude that the utility has substantially implemented the plan.
Response 3:
The current regulatory framework balances incentives and deterrents to drive utility wildfire
risk and achieve safety goals. As part of that framework, the safety certification process is
forward-looking and designed to encourage and incentivize electrical corporations to invest in 9
safety and improve safety culture within their organizations to limit wildfire risks and reduce
costs in the future. (AB 1054, Section 2(f).) Notwithstanding its name, the “safety certification”
was not designed by the Legislature to be a backward-looking mark of approval (nor a reward
to be withheld as punishment for past conduct).
Energy Safety has other tools to engage in backward-looking compliance review to hold utilities 10
accountable in meeting their commitments. If utility efforts are found to be lacking, Energy
Safety will issue notices of violation and defect directing corrective actions. Where appropriate,
Energy Safety will refer cases to the CPUC for consideration of penalty enforcement. The CPUC
also independently evaluates utility safety and can initiate its own punitive actions.
Each of the seven documentation requirements Energy Safety evaluates during the safety
certification review process looks at the utility’s planned efforts to operate more safely. The
requirements are forward focused. Among those requirements, a utility must demonstrate that
it has an approved mitigation plan, it has agreed to implement safety culture assessment
findings, it is incentivizing its leadership to prioritize safety through its executive compensation
structure, and that it is documenting implementation of its current mitigation plan to prevent
future ignitions. Utilities are incentivized to take these actions because obtaining a safety
certification can affect the amount, if any, the electrical corporation must repay the Wildfire
Fund for costs and expenses associated with a covered wildfire.
74 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Michael Tilden
March 4, 2022
Page 6 of 9
It is worth considering how the Report’s recommendation would alter the careful balance the
11 Legislature struck in 2019 by transforming the safety certification process into a punitive
enforcement tool and whether the structure of the safety certification process is well suited to
be used as an enforcement tool. As explained in the Report, the “most recently completed
compliance assessment” would be an assessment on mitigation plan actions from two to three
years prior. Given the constantly evolving understanding of how best to address utility wildfire
risk, any findings in the “most recently completed compliance assessment” may not be directly
relevant or applicable to utilities’ maturing wildfire strategies. Using the safety certification as a
backward-looking, punitive enforcement action could undermine its value as a stabilizing
incentive to invest in safety and, as the Report states, “support credit worthiness,” which
enables utilities to raise capital at a lower cost to make those investments.
12 The current safety certification regulatory framework established by the Legislature has only
been operative for less than three years. Energy Safety respectfully suggests that it be given the
time to drive the safety improvements it was created to achieve.
Recommendation 4: To ensure that utilities are targeting highest fire risk activities, Energy
Safety should designate the prioritization of mitigation activities as a critical issue that must be
addressed before it approves mitigation plans.
Response 4:
13 Energy Safety strongly disagrees with the Report’s characterization of its 2020 and 2021
mitigation plan evaluation as having “failed to ensure that utilities focus mitigation activities in
the areas of highest fire risk.” Energy Safety has focused extensively on driving the utilities to
develop their risk modeling capabilities so that the utilities can accurately prioritize their
mitigation activities. The Report’s recommendation that Energy Safety designate prioritization
of mitigation activities as a “critical issue that must be addressed before it approves mitigation
plans” fails to recognize the many factors that go into making such an evaluation. The Report
14 also confuses compliance assessments, which hold utilities accountable for implementing their
mitigation plan, with the mitigation plan evaluation process, which holds utilities accountable
for planning their mitigation activities.
In 2021, for example, Energy Safety experts designated PG&E’s failure to provide sufficient
information about its overhauled risk model a critical issue and subsequently issued a Revision
Notice, which is Energy Safety’s mechanism to require modification of the plan. Energy Safety
experts conducted an exhaustive analysis of PG&E’s Revision Notice response and revised plan.
Upon completing its expert review, Energy Safety deemed that PG&E’s revised plan was
sufficient to determine that PG&E’s updated risk model was significantly more robust and
effective than its previous model. The approval simultaneously required PG&E to provide more
15 information and take further action to continue to improve on risk modeling. Energy Safety
stands by its evaluation that PG&E’s progress was sufficient to warrant approval of its
CALIFORNIA STATE AUDITOR | Report 2021-117 75
March 2022
Michael Tilden
March 4, 2022
Page 7 of 9
mitigation plan, and PG&E must address the issues highlighted in Energy Safety’s decision in the
next plan.
Energy Safety’s mitigation plan approvals push the utilities to constantly think more deeply, be
smarter, and be more rigorous in their efforts by requiring additional information and actions.
In its inaugural year as WSD within the CPUC, the department used the 2020 mitigation plans to
establish a baseline understanding of utilities’ wildfire risk capabilities. Each utility was assessed
to determine where it was in its maturity, and Energy Safety evaluated whether the plan was
appropriate for that utility at that point in time while laying out the department’s expectations
for growth. In undertaking this analysis, WSD exposed weaknesses in the utilities risk modeling
and prioritization that resulted in a significant effort on the part of the utilities to mature these
areas. For example, PG&E revamped its risk model between 2020 and 2021, creating improved
risk assessment outcomes. Risk-based decision-making and consequence evaluation is a
nascent area that is continuously evolving in real time. Requiring a utility to achieve a yet-to-be- 16
developed gold standard for risk modeling prior to mitigation plan approval would result in the
denial of mitigation plans for years—a result that would deter, rather than foster, critical
improvements. Without approved plans, the utilities cannot be held accountable for the
progress promised in those plans and denial would prevent them from implementing
incremental progress over their prior approved plan. Instead, Energy Safety evaluates utility
improvement over the previous year and, if sufficient, approves the WMP while providing clear
direction on how to mature the capability going forward.
The evaluation of mitigation plans is separate from assessments of implementation and
compliance. The Report notes that a Federal Monitor Report found that in October 2020 “PG&E
completed the majority of its 2019 enhanced vegetation work in relatively low-risk portions of
its high fire-threat areas and had not conducted any of its planned enhanced inspections of
transmission structures in its highest threat areas.” While the Report cites valid and serious
concerns with PG&E’s implementation of its 2020 and 2021 mitigation plans, Energy Safety is
addressing those issues through its compliance process.2 Energy Safety should not and cannot
reject a utility’s forward-looking plan because of actions the utility takes (or fails to take) while 17
implementing its previous plan.
Finally, as noted by the Report, Energy Safety is requiring “utilities to detail how their risk
18
models will be used to inform how they prioritize mitigation activities” in the 2022 Wildfire
Mitigation Plan Guidelines. The Report is utilizing this change to the guidelines as evidence that
Energy Safety did not evaluate overall risk prioritization in the 2021 plans. However, while it is
true that the 2021 Wildfire Mitigation Plan Guidelines did not explicitly require detail regarding
2 For example, as the WSD, Energy Safety conducted an audit of PG&E’s 2020 Enhance Vegetation Management
(EVM) program and found that PG&E did not sufficiently prioritize EVM work to reduce wildfire risk. The CPUC
used the WSD findings in this audit to take an enforcement action and place PG&E in Step 1 of the Enhanced
Oversight and Enforcement Process.
76 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Michael Tilden
March 4, 2022
Page 8 of 9
overall risk prioritization, each initiative required discussion of how utilities determined region
prioritization. Energy Safety delved into risk models and prioritization during its evaluation
process through follow-up data requests and by issuing a Revision Notice. The change to the
2022 Wildfire Mitigation Plan Guidelines serves to make it explicit that Energy Safety requires
this information in plan submittals.
The Report is similarly critical of Energy Safety’s 2021 internal review procedures document3
because risk prioritization was not characterized as an example of a critical issue. However,
19 under the 2021 internal review procedures, Energy Safety had the flexibility to determine that
shortcomings in risk prioritization constituted a critical issue. In fact, it did. As discussed above,
Energy Safety determined risk prioritization was a critical issue that would have prevented
approval of PG&E’s plan and thus issued a Revision Notice. Energy Safety ultimately approved
PG&E’s 2021 Wildfire Mitigation Plan because the Revision Notice sufficiently addressed Energy
Safety’s concerns4.
20 The flexibility of these procedures5 does not prejudge the severity of any one issue as critical.
The internal procedures serve as the underpinnings upon which Energy Safety can layer its
expertise when conducting its evaluation. To prescribe the severity of an issue prior to
evaluation would lead to a “check-box” effort. Under the internal procedures, Energy Safety’s
experts have discretion based on their technical knowledge to designate the severity of an issue
as “critical” and trigger a Revision Notice. Energy Safety stands behind the comprehensive and
extensive evaluation conducted by its team of engineers, scientists, firefighters, and utility
experts and their conclusions.
Recommendation 5: To make mitigation plans more responsive to causes of fires and serious
concerns raised through oversight mechanisms, the Energy Safety Office should require in its
2023 mitigation plan guidelines that utilities address issues identified by oversight mechanisms
– such as external audits—in their mitigation plans.
Response 5:
Energy Safety agrees that, where applicable and as appropriate, utilities should account for and
21
address recommendations from external entities—what the Report calls “oversight
mechanisms” —in their mitigation plans. Energy Safety requires utilities to continuously assess
their performance and implement lessons learned to make improvements over time. In fact, in
the Wildfire Mitigation Plan Guidelines, Energy Safety requires utilities to discuss lessons
learned in each section of the mitigation plan. Where a utility is subject to external oversight,
3 Report relied upon an example in the 2021 internal evaluation procedures to make its conclusion.
4 With the approval, Energy Safety required PG&E to provided additional information and take additional actions to
continue improving risk prioritization in its subsequent filing.
5 The 2022 internal evaluation procedures are currently in draft form.
CALIFORNIA STATE AUDITOR | Report 2021-117 77
March 2022
Michael Tilden
March 4, 2022
Page 9 of 9
Energy Safety expects that a utility addresses the findings and recommendations from that
oversight entity.
The Report repeatedly cites the Federal Monitor as an example of an “oversight mechanism.” It
is important to note that the Federal Monitor was only applicable to one utility and ended its
oversight role as of January 25, 2022. Specifying piecemeal oversight mechanisms that do not
consistently oversee utilities across the state, may lead to a scattershot approach to wildfire
mitigation oversight that cannot be repeated or applied with any consistency. This approach
risks introducing inconsistencies in plan structures across utilities.
The department will evaluate the need for any changes to the Wildfire Mitigation Plan
Guidelines, including changes to the Lessons Learned section, through its established annual
process.
Conclusion
Energy Safety was created with a clear purpose to reduce utility-related wildfire risk and build
sustaining safety cultures within the electrical corporations that run California’s energy
infrastructure. The Legislature created a novel and carefully balanced regulatory framework to
empower Energy Safety to achieve this purpose. Energy Safety is implementing this new
framework through first-of-its-kind oversight tools and innovative approaches to drive
behavioral and organizational change. It will take time to realize the impact and ultimately
success of these efforts due to the amount of wildfire risk utilities must overcome and the
relentless pace of climate change impacts.
Energy Safety is committed to driving timely, meaningful, and effective changes to the way
California’s electrical corporations build, operate, and maintain their infrastructure. Energy
Safety will continue to challenge them, question them, and demand continuous improvements
to safety. Energy Safety expects California electrical corporations to reduce the number of
ignitions caused by their infrastructure and eliminate all ignitions that result in catastrophic
wildfires.
Sincerely,
Caroline Thomas Jacobs
Director
Office of Energy Infrastructure Safety
78 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
Blank page inserted for reproduction purposes only.
CALIFORNIA STATE AUDITOR | Report 2021-117 79
March 2022
COMMENTS
CALIFORNIA STATE AUDITOR’S COMMENTS ON
THE RESPONSE FROM THE OFFICE OF ENERGY
INFRASTRUCTURE SAFETY
To provide clarity and perspective, we are commenting on the
response to our audit from the Energy Safety Office. The numbers
below correspond to the numbers we have placed in the margin of
the response.
The Energy Safety’s Office’s characterization of our perspective is 1
imprecise. As we state in the Scope and Methodology on page 55, our
audit focuses on the roles of the CPUC and the Energy Safety Office in
ensuring a safe and reliable electrical system in California. The utilities
were not the entities we audited.
Although the Energy Safety Office believes that it has the authority 2
to act on the concerns identified in the report, we question why it
has not yet taken such action. As Figure 1 on page 6 shows, six of
the State’s largest wildfires, including the utility-caused Dixie Fire
that started in July 2021, have occurred since January 2020, when
the office’s predecessor organization, the Wildfire Safety Division,
was created. Given the damage that utility-caused wildfires have
caused and the threat they continue to pose, a more proactive
approach is necessary. Adding specific requirements to state law, as
we recommend on pages 33 and 34, will prioritize utilities’ efforts to
ensure that these concerns are addressed.
The Energy Safety Office’s concerns about redactions in the draft 3
report are unfounded. The draft report that we provided to the
Energy Safety Office contained all the findings, conclusions, and
recommendations that pertain to it since it became a separate entity
in July 2021. Additionally, prior to releasing the draft report to the
Energy Safety Office, we met with its staff, director, and legal counsel
on several occasions and discussed all the findings, conclusions and
recommendations that pertain to it since it became a separate entity.
Throughout the audit, we explained to its staff and legal counsel that
the Government Code sections 8545 and 8545.1 require us to keep
all substantive information about the audit confidential until we
publish our audit report. Consistent with the law, generally accepted
government auditing standards, and our long-standing practice, we
provided each audited entity with the text that pertains to it, but
not with the text that pertains to other entities. Further, consistent
with generally accepted government auditing standards, our reports
undergo a rigorous process of quality reviews to ensure their accuracy
and completeness before we publish them.
80 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
4
Although the Energy Safety Office states that the statutory framework
was amended in 2021, we believe that the hardships power shutoffs
cause warrant the Legislature’s consideration of how the statutory
framework could be improved. From 2013 through 2021, power
shutoffs affected 3.6 million individuals, and as we state on page 17,
approximately 270 circuits were de-energized three or more times
during different power shutoffs in the same calendar year. These
recurring power outages, the impact of which we describe on page 15,
illustrate the need for statutory changes to ensure that utilities rapidly
identify the improvements necessary to prevent the need for power
shutoffs in the future.
5
The Energy Safety Office misrepresents the nature of our
recommendation. We did not recommend that the office direct the
utilities to eliminate power shutoffs. As we describe on page 14, power
shutoffs have proven effective at preventing possible ignitions during
high wind conditions. Rather, our recommendation on page 33 focuses
on taking steps to prevent the need for shutoffs. At no point in the
report do we recommend eliminating power shutoffs as a potential
mitigation measure.
6
The Energy Safety Office’s description of our recommendation is
inaccurate. Rather than accepting that either reliability or safety should
be prioritized over the other, as the Energy Safety Office suggests, our
recommendation focuses on identifying measures to improve safety,
which in turn enhances reliability. Further, although the Energy Safety
Office describes unplanned outages as inconvenient, according to the
CPUC, as we describe on page 32, unplanned outages are more than
a matter of inconvenience—they are disruptive, and for customers
who rely on electricity to maintain necessary life functions, they can
be life-threatening. These effects highlight the need for the Legislature
to ensure that utilities are taking steps to address sections of line
frequently de-energized as the result of these outages.
7
The Energy Safety Office’s reference to the focus of the original law is
not relevant to the issue that we recommend the Legislature address.
Whether incorporated into this law or added as a separate section
of law, the intent of our recommendation on pages 33 and 34 is to
limit the impact on Californians of unplanned outages due to wildfire
mitigation measures.
8
We disagree with the Energy Safety Office’s perspective that our
recommendation would discourage utilities from using their “operator
discretion and expertise.” Rather, it encourages the utilities to identify
improvements that will increase the safety of the electrical grid and
reduce the need for utilities to exercise that discretion and expertise.
In light of the impact that these unplanned outages had on more than
a half million Californians in 2021, it is unclear why the Energy Safety
Office appears to be opposed to this recommendation.
CALIFORNIA STATE AUDITOR | Report 2021-117 81
March 2022
We disagree with the Energy Safety Office’s characterization of 9
the safety certification process and have highlighted significant
weaknesses in that process in our report. A safety certification
process that focuses only on looking forward does not hold utilities
accountable for actually performing the work to mitigate wildfire risk.
Moreover, the Energy Safety Office’s response does not address our
concern that the requirements in state law are not sufficient to assure
that utilities that are issued safety certifications actually implement
their mitigation plans. As we describe on page 37, state law does not
allow the office to deny a safety certification on the basis that a utility
did not implement a prior mitigation plan. Linking the assessment
of a utility’s implementation of its mitigation plan to the issuance of
its safety certification is a reasonable approach for ensuring the value
and relevance of the safety certification process. Further, it is unclear
how issuing safety certifications to utilities that fail to implement their
mitigation plans would accomplish the Legislature’s intent.
We question the accuracy of the Energy Safety Office’s statement 10
regarding other tools for holding utilities accountable based on
our finding that the CPUC does not use its authority to penalize
utilities when its audits uncover violations. The Energy Safety Office
asserts that where appropriate it will refer cases to the CPUC for
consideration of penalty enforcement. However, as we state on
page 47, the CPUC’s practice is to issue penalties for significant
issues, such as when individuals were hurt or killed, or where
buildings were destroyed. Therefore, the Energy Safety Office’s
statement that it will refer cases to CPUC for consideration of penalty
enforcement does not align with the reality of the CPUC’s practices
for assessing penalties.
We disagree with the Energy Safety Office’s statement that our 11
recommendation would transform the safety certification process
into a punitive enforcement tool. This process already requires
that utilities meet certain requirements in order to receive a safety
certification. Adding another criterion to those requirements will
not fundamentally alter the nature of the safety certification process.
Further, we are not suggesting that utilities’ implementation of past
plans be assessed against “the constantly evolving understanding of
how best to address utility wildfire risk.” Although the Energy Safety
Office has not yet completed its first mitigation plan compliance
assessment, we would expect the office’s compliance assessments to
determine whether utilities adhered to their plans. We would question
the office’s approach if it were to assess utilities’ compliance with their
plans in the manner that its response indicates. Finally, the practice of
approving safety certifications based on mitigation plans that are not
meaningfully linked to outcomes is not prudent. As an example, we
describe on page 37 that when the Energy Safety Office issued PG&E’s
82 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
2020 safety certification, it noted concerns identified by oversight
entities but nonetheless stated that PG&E had met the minimum
statutory requirements for issuance of a safety certification.
12
The Energy Safety Office’s response does not acknowledge the
urgency of addressing the wildfire risk that California faces. As we
state on page 7, the average wildfire size and the annual area burned
have increased during the past several years. The issuance of a safety
certification is intended to encourage utilities to invest in safety
and improve safety culture to limit wildfire risks, as we describe on
page 36. However, whether a utility substantially implements the
projects in its mitigation plan has no bearing on the Energy Safety
Office’s decision to issue its safety certification, as we describe
on page 37. Being given additional time to improve the existing
framework, as the Energy Safety Office suggests, may delay holding
utilities accountable for substantially implementing their mitigation
plans and making safety improvements to help decrease the likelihood
of utility-caused wildfires.
13
The Energy Safety Office’s statement that it strongly disagrees with
our report’s characterization of its 2020 and 2021 mitigation plan
evaluations contradicts its own assessments of those mitigation
plans. As we describe on page 42, the Energy Safety Office found that
PG&E did not describe in sufficient detail in its 2020 mitigation plan
how it prioritized deployment of vegetation management initiatives,
and the utility failed to demonstrate in its 2021 mitigation plan that
it was properly prioritizing power line replacement and system
hardening efforts. Further, as we reference on page 43, the Energy
Safety Office also noted that SDG&E did not provide sufficient detail
in its 2021 mitigation plan on how it prioritized high fire-threat areas
for moving power lines underground and installing covered power
lines. Although the Energy Safety Office states that it has focused
extensively on driving the utilities to develop their risk modeling,
we are concerned about its continued practice of approving utilities’
mitigation plans despite having identified insufficient information to
support their prioritization of mitigation activities.
Further, the Energy Safety Office’s suggestion that our
recommendation fails to recognize the many factors that go into a
mitigation plan evaluation is incorrect. Although we are aware of
the many factors that must be considered, we also recognize the
critical importance of ensuring that mitigation activities are properly
prioritized. As we describe on page 43, the Energy Safety Office’s
internal procedures already categorize some issues as critical items
that must be addressed before it approves a mitigation plan. We
recommend that the office consider the prioritization of mitigation
activities to be one of these critical issues.
CALIFORNIA STATE AUDITOR | Report 2021-117 83
March 2022
The Energy Safety Office’s belief that we have confused the planning 14
of mitigation activities with compliance assessments is incorrect. On
the contrary, we recognize that these processes are distinct—separated
by a significant gap in time—as we illustrate in Figure 11 on page 38.
However, these processes are inextricably linked: the compliance
assessment determines whether the utility has implemented
the mitigation plan. Unless a utility’s mitigation plan specifically
identifies the nature and location of the work to be performed,
it will not be possible for the office’s compliance assessments to
provide a meaningful determination of whether a utility substantially
implemented its plan. Accordingly, we stand by our recommendation
that until the Energy Safety Office designates the prioritization of
mitigation activities as a critical issue that must be resolved before it
approves mitigation plans, it cannot ensure utilities are targeting the
areas of highest fire risk.
Although the Energy Safety Office asserts that it stands by its 15
evaluation of PG&E’s 2020 and 2021 mitigation plans, its response
does not address our concern that it determined the utility had
not provided sufficient information on how it used risk modeling
outcomes to inform how it planned to conduct various mitigation
activities. Page 42 of our report acknowledges that in the office’s
review of PG&E’s 2021 mitigation plan, it determined that PG&E
made progress in updating its vegetation risk model. However, the
office found that the utility failed to demonstrate that it was properly
prioritizing other activities, particularly power line replacement and
system hardening efforts. Further, other entities also identified issues
regarding PG&E’s prioritization of the mitigation efforts it performed.
Based on its own descriptions of the weaknesses in PG&E’s mitigation
plans and the critical nature of the activities for which PG&E failed
to provide sufficient information, it is unclear why the Energy Safety
Office believes its evaluation was sufficient.
The Energy Safety Office’s comments do not align with our 16
conclusions and recommendation. We did not recommend that
utilities achieve a “gold standard” for risk modeling prior to mitigation
plan approval. Rather, on pages 48 and 49 we recommend that
the office designate the prioritization of mitigation activities as a
critical issue. Without such prioritization, the Energy Safety Office
cannot ensure utilities target the areas of highest wildfire risk.
Notwithstanding the office’s statement that the utilities need approved
mitigation plans to be held accountable for the progress promised, if
those plans do not contain sufficient detail, the Energy Safety Office
will not be able to effectively assess whether utilities targeted activities
in areas of highest risk for wildfires and hold the utilities accountable
for performing those activities.
84 Report 2021-117 | CALIFORNIA STATE AUDITOR
March 2022
17
We do not disagree with the Energy Safety Office’s statement that
it should not and cannot reject a utility’s mitigation plan because
of actions the utility takes while implementing its previous plan.
Nor did we recommend that it do so. We described evaluations of
utilities’ wildfire mitigation work to illustrate that the Energy Safety
Office identified concerns with mitigation plans, but it nevertheless
approved them. Subsequently, its concerns were proven to be correct.
Thus, instead of approving plans when the office identifies such
concerns, it should require mitigation plans to include information
on the prioritization of mitigation activities so that it can hold utilities
accountable when it ultimately performs its compliance assessments
of those plans.
18
The Energy Safety Office’s response correctly notes that its 2021
mitigation plan guidelines did not explicitly require detail regarding
overall risk prioritization. However, despite its claim that its 2021
guidelines required utilities to discuss how they prioritized initiatives
by region, the office approved mitigation plans even when it
determined that utilities did not provide sufficient information on
how they prioritized those initiatives.
Further, the Energy Safety Office describes changes to the 2022
mitigation plan guidelines as evidence that it has addressed the
concern we raise. Because these guidelines were in draft form at the
time of our audit and thus confidential, we were unable to describe
them in our report. When they are finalized, we look forward
to reviewing the guidelines as part of our process for following
up on the Energy Safety Office’s implementation of the audit’s
recommendations.
19
In its response, the Energy Safety Office provides one example of
when it determined risk prioritization was a critical issue for PG&E.
However, it omits that it approved PG&E’s mitigation plan despite
its concerns that the utility failed to demonstrate that it was properly
prioritizing its power line replacement and system hardening efforts,
as we describe on page 42.
20
The Energy Safety Office’s statement contradicts its own existing
procedures, which already establish the relative severity of certain
issues. As we describe on page 43, the Energy Safety Office’s
internal procedures classify some items as critical issues that must
be addressed before it approves a mitigation plan and others as
deficiencies that may be addressed in a subsequent mitigation
plan. We recommend only that the Energy Safety Office elevate
the prioritization of mitigation activities to be a critical issue. This
recommendation is not intended to create a “check box” approach,
but rather as we note on page 43, to have the office hold utilities
accountable for conducting mitigation activities in areas of highest risk
for wildfire.
CALIFORNIA STATE AUDITOR | Report 2021-117 85
March 2022
The Energy Safety Office’s criticism of our recommendation to require 21
that utilities address issues identified by oversight mechanisms in their
mitigation plans is inconsistent with other statements in its response.
It states here that “where applicable and as appropriate, utilities
should account for and address recommendations from external
entities,” but in the following paragraph it suggests that specifying
oversight mechanisms that do not consistently oversee utilities across
the State may lead to a scattershot approach and risks introducing
inconsistencies in plan structures across utilities. The suggestion
that it is problematic if different oversight mechanisms apply to
different utilities contradicts the office’s perspective on mitigation
plans it described previously in this response. On page 75, it indicates
that utilities are at differing levels of maturity in their wildfire risk
capabilities, and that “Energy Safety evaluated whether the plan was
appropriate for that utility at that point in time…” Consistent with the
office’s belief that it is appropriate to apply different considerations
to utilities’ mitigation plans based on what is appropriate for a utility
at that time, it should consider whatever oversight mechanisms are
applicable to that utility at that point in time.