CSA
Summary
Read the report at California State Auditor ↗
REPORT BY THE STATE AUDITOR
OF CALIFORNIA
A REVIEW OF CALTRANS' MANAGEMENT OF THE
CONTRACT WITH MORRISON KNUDSEN CORPORATION
FOR THE DESIGN AND CONSTRUCTION OF RAILCARS
93114 MARCH 1994
A Review of Caltrans' Management of the
Contract with Morrison Knudsen Corporation
for the Design and Construction of Railcars
93114, March 1994
California State Auditor
Bureau of State Audits
Table of Contents
Page
Summary S-1
Introduction 1
Chapters
1 Responsibilities of the Contractor for
Creating Jobs in California 5
2 Changes Imposed Through Contract Change
Orders Have Affected the Overall Cost
and Delivery Time of the Railcars 11
3 A Change in the Participation Goal for
Disadvantaged Business Enterprises and
Its Effect on the California Car Contract 29
Recommendation 37
4 Caltrans' Ownership Rights To Design Plans and
Technical Specifications for the California Car 39
5 Incurred and Projected Overhead Costs Associated
With the California Car Contract
43
Responses
to the
Audit
Page Left Intentionally Blank
Summary
Results in Brief In June 1990, the voters of California approved Proposition 108 and
Proposition 116 authorizing the sale of nearly $3 billion in general
obligation bonds. The purpose of these propositions was to provide
funds for the acquisition of rights-of-way, capital expenditures and
improvements, and the acquisition of passenger railcars and
locomotives for intercity rail, commuter rail, and urban rail transit
systems.
According to Proposition 116, the state Department of Transportation
(Caltrans) will be allocated $100 million to fund a competitive proposal
program for the acquisition of standardized state-of-the-art intercity and
commuter railcars. As of January 1, 1994, Caltrans had committed
approximately $214 million of the funds raised from bond sales
authorized by both propositions to fund a contract for the purchase of
113 railcars. Of these, 66 are intercity cars and 47 are commuter cars.
The focus of this audit was to review and evaluate specific aspects of
the contract that Caltrans entered into with Morrison Knudsen
Corporation (M-K) for the purchase of the 113 railcars. (Throughout
this report, we refer to this project as the California Car project.)
.
During our review we noted the following conditions:
Through the California Car project, Caltrans sought, among other
goals, to create jobs in California by accomplishing some part of
the production of the railcars here in the State. Because of
previous court decisions and an Attorney General opinion on the
subject of preference for California or American companies which
had found requiring such preferences unenforceable, Caltrans
determined it could not include a provision in the contract for the
California Car Project that would have required the contractor to
maximize the amount of work on the California Car to be
accomplished in California. Rather, Caltrans "encouraged" the
proposers on the project to commit to maximizing the amount of
work to be done in the State. Consequently, in its initial proposal
to Caltrans, M-K did not indicate a commitment concerning the
creation of jobs in California. During the negotiation of the
original contract, (January 1992), M-K eventually informed
Caltrans that it intended to maximize California content. But it
was not until November 1993 when Caltrans exercised an option to
have M-K produce an additional 25 railcars that Caltrans and M-K
S-1
agreed to more specific and enforceable provisions regarding
California content. The change order that outlines M-K's
responsibility to produce the 25 additional cars also defines the
amount of California content that Caltrans expects M-K to provide,
both for the 25 additional cars as well as for the 88 cars to be
provided under the original contract. The change order requires
that M-K create the equivalent of about 580 full-time jobs at its
Pittsburg, California facility doing the assembly and final testing on
66 cars, 45 from the original order and 21 from the additional order.
Caltrans originally contracted with M-K for the production of
88 California cars for an amount totaling $153.7 million. The first
cars were to be delivered by August 1993. However, Caltrans and
M-K have agreed to changes to the original contract that have
increased M-K's contract to $214 million and have delayed the
delivery date of the first railcars by 12 months to August 1994.
One of the changes to the contract added 25 railcars to the original
order, at a cost of $54.6 million. The remainder of the change
orders, which mostly dealt with design changes and optional
features to the railcars, added $6.1 million to the cost of this
contract. (This amount includes two change orders totaling
approximately $1.1 million that are pending approval.)
Several factors contributed to the changes on this contract that have
added to the cost and delivery time of the railcars. First, as is
typical in the railcar building industry, Caltrans and M-K entered a
contract that only spelled out in general terms the design
characteristics of the California Car. After first obtaining input
from the Rolling Stock Advisory Committee, which was
established to provide input to the design of the railcars in
accordance with Proposition 116, Caltrans developed a Request for
Proposals (RFP) based on general parameters or "performance
specifications" rather than detailed design specifications.
According to the chief of the Office of Rail Equipment for Caltrans,
it is not surprising that there were change orders on this type of
contract, since not all of the design characteristics of the California
Car were spelled out in detail in the performance specifications.
So, as the design characteristics of the California Car became more
detailed, change orders became necessary. A second factor that
has added cost and time to this contract is that Caltrans exercised a
contract option to have M-K produce an added 25 cars to the
original 88-car order. By exercising this option, Caltrans added
$54.6 million to the contract cost and extended the delivery
schedule two months. A third factor that has contributed to the
added cost and extended delivery is that in overseeing the design of
the railcars, Caltrans has had to be responsive to the input of local
S-2
transportation agencies and railroad operators. One of the change
orders that we discuss in this report was the result of negotiations
between local transportation agencies and Caltrans about the
internal configuration of the commuter car. These negotiations led
to a five-month delay in the original delivery schedule.
By the time that the contract for designing and producing the
railcars was awarded to M-K, Caltrans had substituted the less
rigorous federal goals for the statewide goals for the participation of
disadvantaged businesses in the project. This substitution took
place because of the involvement of $5 million of federal dollars on
this project. Then, eight months after the contract had been
awarded to M-K, Caltrans was in the midst of negotiating a change
order with M-K. As part of an agreement reached on this change
order, Caltrans reiterated that the federal goals were to apply for
this contract, although Caltrans also required that M-K make a good
faith effort to attain the State's goals throughout this contract.
However, the change order does not outline M-K's responsibilities
in making "a good faith effort" in seeking the participation of
disadvantaged businesses in the event it is unsuccessful at attaining
the statewide participation goals.
We recommend that Caltrans clearly specify M-K's responsibilities
to make a good faith effort in seeking the participation of
disadvantaged businesses in the event it is unsuccessful at meeting
the statewide goals.
The Legislature asked us to determine whether Caltrans could have
entered an agreement with a contractor other than M-K to build the
25 railcars beyond the 88 railcars called for in M-K's original
contract. Caltrans chose not to do this, instead exercising an
option in its contract with M-K to have M-K build the 25 cars.
However, in the opinion of the Legislative Counsel, if Caltrans had
decided to seek a contractor other than M-K for the additional 25
cars, Caltrans would have been free to use the design drawings
developed by M-K to solicit proposals from other contractors.
One of the other issues we were asked to address was whether it
would have been less costly for Caltrans to use a contractor other
than M-K to build the 25 additional railcars. However, we cannot
conclude on whether the State would have saved money using other
contractors without actually going through the process of
advertising for this work and receiving and evaluating proposals
from competing firms. According to the consultant for Caltrans,
the design drawings are refined over the life of the contract.
However, the closer the plans are to the as-built phase, the more
S-3
value the plans have to other contractors who might bid on the
production of additional railcars.
Another purpose of this audit was to assess the reasonableness and
propriety of the overhead costs associated with managing the
California Car Project. Over the life of the contract with M-K, an
estimated $8.2 million, or 3.8 percent of the total cost, will be spent
on managing the contract. This includes the costs of both the
Office of Rail Equipment (part of Caltrans) and the consultant,
Booz-Allen & Hamilton, Inc. (Booz-Allen). To assess the
reasonableness of the $8.2 million expenditure, we contacted three
public entities other than Caltrans that manage contracts of
comparable size and scope. However, these entities were either
unable or unwilling to share information with us on the costs of
managing their respective contracts. Caltrans' Division of Rail
informed us that the costs associated with managing contracts of
this size and scope usually range from 5 percent to 8 percent of the
contract total.
To gauge the propriety of the amounts charged by Booz-Allen for
overseeing the M-K contract, we reviewed a sample of the
supporting documentation for all billings received to date by
Caltrans. We ensured that the amounts being charged were
allowable costs according to the terms of Booz-Allen's contract
with Caltrans. We found no improper expenditures among the
items we tested.
S-4
Introduction
Passenger rail transportation in California includes intercity rail,
commuter rail, and urban rail services. Intercity rail primarily serves
business or recreational travelers between cities in California and other
parts of the country. An example of this service is the San Diegans,
which runs from San Diego to Santa Barbara. Intercity rail service is
typically operated by Amtrak. Commuter rail service generally offers
frequent service during commute hours to serve commuters, with
limited service during other periods of the day. The Peninsula
Commute Rail Service (Caltrain) from San Francisco to San Jose is an
example of this type of service. Urban rail service provides regular
service throughout the day, generally within an urban or metropolitan
area. Examples of this service include the Sacramento Light Rail
System, the San Diego Trolley System, and the San Francisco Bay
Area Rapid Transit (BART) System.
Under current law, the California Transportation Commission (CTC)
reviews highway, rail, and other transportation projects proposed for
state funding. The CTC decides which projects are a priority for
funding. The projects considered include those proposed by the state
Department of Transportation (Caltrans) and by local and regional
transportation agencies. The projects selected are scheduled in a
seven-year funding plan adopted by the CTC.
In June 1990, the voters of California approved Proposition 108 and
Proposition 116, authorizing the sale of nearly $3 billion in general
obligation bonds. The purpose of these propositions was to provide
funds for the acquisition of rights-of-way, capital expenditures and
improvements, and the acquisition of passenger railcars and
locomotives for intercity rail, commuter rail, and urban rail transit
systems.
The CTC allocates the money raised through the bond sales authorized
by Proposition 116 to state, local, and regional agencies according to a
grant process established by the proposition. According to the
proposition, Caltrans will be allocated $100 million to fund a
competitive proposal program for the acquisition of standardized
state-of-the-art intercity and commuter railcars.
1
In general, the CTC allocates the funds raised through the bond sales
authorized by Proposition 108 to Caltrans. Caltrans, in turn, spends
the funds on approved transportation projects, including the acquisition
of railcars.
As of January 1, 1994, Caltrans had committed approximately
$214 million of the funds raised from the bond sales authorized by the
two propositions to fund a contract for the purchase of 113 railcars. Of
these, 66 are intercity cars and 47 are commuter cars.
Scope and The focus of this audit was to review and evaluate various aspects of
Methodology the contract that Caltrans entered into with Morrison Knudsen
Corporation (M-K) for the purchase of standard design intercity and
commuter railcars. (Throughout the rest of this report we will refer to
this project as the California Car Project.)
Through the award of this contract, Caltrans hoped, among other goals,
to create jobs here in California by accomplishing some or all of the
design and assembly of the cars in California. To determine what
obligations the contractor has for creating jobs in California, we
reviewed the terms of the Request for Proposals (RFP) developed by
Caltrans and sent to prospective proposers for the California Car
contract. We also reviewed the provisions of the contract awarded to
M-K and all the changes to the contract. All changes made to the
contract are formalized into "change orders" that specify the work to be
done in connection with the change made. In addition, we interviewed
the project manager for M-K regarding the planned use of resources
such as labor and materials originating from California during the life
of the contract. Throughout this report, we refer to these resources as
"California content."
Because the cost of this project has increased beyond the original
estimate and because there have been delays in the projected delivery
of the completed railcars, some concern has been expressed over how
effective Caltrans has been in managing the contract with M-K. To
determine what rights Caltrans has in controlling contract costs and
requiring specific performance by the contractor when significant
change orders are made to the original contract, we assessed the effect
that change orders had in terms of price increases or time delays.
Originally, the funding for the design and construction of the railcars
was to be exclusively from state funds. However, Caltrans now
projects that $5 million of federal funds will also be part of the funding
for the railcars. To determine what effect the use of federal funds had
on the contractor's participation goals for businesses of minorities,
2
women, and disabled veterans, we researched both the state and federal
laws about this issue. We also interviewed Caltrans staff and reviewed
various documents to determine why federal funds were used as part of
the funding source for the contract with M-K.
During the course of this contract, Caltrans decided to acquire
additional railcars beyond the 88 cars specified in the original contract.
Caltrans could have contracted with M-K or solicited proposals from
other contractors to produce the additional cars, using the standardized
designs developed under the original contract. To determine what
rights Caltrans has regarding the design plans and technical
specifications developed for the manufacture of the California Car, we
reviewed the terms of the RFP and the executed contract. In addition,
we interviewed consultants and staff from Caltrans involved in the
negotiation and administration of the M-K contract.
We were also asked to determine whether it would be more economical
for the State if, instead of exercising the option contained in the original
California Car contract to purchase additional railcars at a negotiated
price from M-K, Caltrans were to seek competitive proposals from
other contractors for the additional railcar purchase. However, without
actually conducting a competitive process, we cannot accurately
evaluate a prospective outcome such as this.
Another of the purposes of this audit was to determine the propriety
and reasonableness of the overhead costs for the M-K contract.
Overhead includes the cost of approving and inspecting each of the
deliverables produced by M-K, such as the designs, plans, and railcars.
Overhead also includes the costs of administering the M-K contract.
To do this, we reviewed the terms of a contract between Caltrans and a
consultant hired to administer the M-K contract and to inspect the
quality of the finished product. We also reviewed the consultant's
billings sent to Caltrans. In addition, we assessed the amount of
overhead Caltrans is allocating to the M-K contract. We also reviewed
the amounts spent from Proposition 116 bond sales to determine if the
purposes of such expenditures conformed with the law. Finally, we
contacted other entities to assess what is a reasonable cost for
inspections and administration of other contracts of a similar size and
scope.
Also, as part of this audit we sought a Legislative Counsel opinion on
several issues related to the California Car project. These issues
included the enforceability of certain provisions of Caltrans' contract
with M-K. Legislative Counsel provided us their analysis of the
liquidated damages provisions of the contract, the contractual
provisions on producing some portion of the railcars in California, the
3
process for negotiating change orders with M-K, and the ownership
rights of Caltrans of the design drawings produced by M-K during this
contract. Legislative Counsel also analyzed for us the matter of
whether federal or state requirements for the participation of
disadvantaged businesses should apply to the M-K contract.
4
Chapter 1 Responsibilities of the Contractor for
Creating Jobs in California
Chapter In February 1992, the state Department of Transportation (Caltrans)
Summary awarded a contract for the acquisition of standard passenger railcars to
Morrison Knudsen Corporation (M-K). (Throughout this report, we
refer to this project as the California Car Project.) Since then, the
Legislature has requested information about what obligations M-K is
under to create jobs in California by having some part of the
manufacture and assembly of the railcars take place in the State. (We
use the term "California content" to refer to the planned use of
resources such as materials and labor that are used to manufacture the
railcars in California.) In this chapter, we provide information on this
issue.
To summarize, Caltrans sought to create jobs in California through the
California Car project by having some part of the railcar production
occur in California. In its Request for Proposals (RFP), Caltrans
encouraged potential proposers to maximize the California content of
the railcars in their proposals. Because of previous court decisions and
an Attorney General opinion on the matter of preference for California
or American companies that had found requiring such preferences
unenforceable, Caltrans "encouraged," but did not "require" that
proposers maximize California content in their proposals for the
California Car.
In its initial proposal to Caltrans, M-K did not indicate any
commitment concerning California content, and, consequently, Caltrans
sought assurances from M-K of M-K's intent to maximize California
content. During the negotiation of the original contract in
January 1992, M-K informed Caltrans that it intended to maximize
California content. But it was not until November 1993, when
Caltrans exercised an option to have M-K produce an additional 25
railcars, that Caltrans and M-K agreed to more specific and enforceable
provisions regarding California content. The change order that
outlines M-K's responsibility to produce the 25 additional cars also
defines the amount of California content that Caltrans expects M-K to
provide, both for the 25 additional railcars as well as for the 88 railcars
to be provided under the original contract. Among the provisions of
this change order is a requirement that M-K create the equivalent of
about 580 full-time jobs at its Pittsburg, California facility doing the
assembly and final testing on 66 railcars, 45 from the original order and
21 from the additional order.
5
Background
Caltrans issued an RFP in August 1991 to all parties interested in
proposing on a contract to furnish standard passenger railcars for
intercity and commuter service throughout the State. The RFP
requested that proposers include per car and total prices for a base
purchase of from 48 to 60 commuter cars as well as per car prices for
options to purchase up to 40 additional commuter cars in each of the
two years following the contract award. In addition, proposers were
asked to include per car and total prices for a base purchase of from 24
to 40 intercity cars and per car prices for options to purchase up to 40
additional intercity cars in each of the two years following the contract
award. Among the provisions included in the RFP was a clause
encouraging interested proposers to maximize the California content of
the end product supplied under the contract.
Caltrans determined that M-K submitted the only responsive proposal,
and awarded the contract for the acquisition of California Cars to M-K
in February 1992. The contract's production schedule called for the
delivery of the first car in August 1993. However, because of a variety
of causes (see Chapter 2 for a discussion of these), delivery of the first
car is now scheduled for August 1994.
California The RFP for the California Car contained a provision encouraging
Content interested proposers to maximize the California content of the end
Provisions in product supplied under the contract terms. However, the RFP did not
contain any provision for awarding preference points based on
the Request
proposers' inclusion of California content in their proposals.
for Proposals
According to the deputy director for rail and transit, Caltrans based its
decision not to include preference points on its understanding of an
opinion from the Attorney General.
By encouraging proposers to maximize California content in the
production of railcars, Caltrans believed it was not in a position to
require the winning proposer, M-K, to manufacture some or all of the
railcars in California. Or, stated another way, the original contract
between Caltrans and M-K included no provisions that Caltrans could
have enforced to require M-K to manufacture some or all of the railcars
in California.
We reviewed a copy of the Attorney General's opinion that Caltrans
relied on in making its decision. This opinion, dated February 11,
1970, was originally sought by the Department of General Services
(DGS) on whether the California Buy American Act and the California
Preference Law were constitutional, and if unconstitutional, what effect
that would have on contracts previously executed by the State. The
6
Attorney General concluded that both the act and the law were
unconstitutional.
The California Buy American Act generally provided that any public
officer or entity authorized to enter into a contract for the construction,
alteration, or repair of public works or for the purchase of materials for
public use award such contracts only to persons who agreed to use or
supply materials produced in the United States or who manufactured
articles from materials produced substantially in the United States.
The California Court of Appeal held that the California Buy American
Act, in effectively placing an embargo on foreign products, usurped the
power of the federal government to conduct foreign trade policy, and
was therefore, unconstitutional as an intrusion into an exclusively
federal domain.
The California Preference Law, as it pertained to contracts, permitted
public officers and entities responsible for awarding contracts for
public work, the construction of public bridges, buildings and other
structures, and the purchase of supplies intended for public use to
award such contracts to California manufacturers or suppliers under
certain conditions. These conditions were (1) that the bids received
from California manufacturers or suppliers not exceed by more than 5
percent the lowest bids of out-of-state manufacturers or suppliers, (2)
that the majority of any manufacturing occur within the State, and (3)
that, in the opinion of the person or entity awarding the contract, the
public good would be served.
The Attorney General concluded that, since the California Court of
Appeal found the California Buy American Act unconstitutional and
the California Preference Law was similar in its effect on foreign
commerce, the preference law was also unconstitutional. The
Attorney General contended, therefore, that all calls for bids and
contracts entered into by public agencies after the date of the Court of
Appeal's decision must be devoid of any requirement for compliance
with either the California Buy American Act or the California
Preference Law.
We asked the Legislative Counsel to review the constitutional
implications of a California content requirement contained in the RFP
for this contract. In contrast to the Attorney General's opinion, the
Legislative Counsel concludes that a contractual provision requiring
California content would not have been unconstitutional. The
Legislative Counsel focused his analysis on two clauses contained in
the United States Constitution. The first clause, known as the
Commerce Clause, gives Congress the power to "regulate commerce
with foreign nations and among the several states..." The second
7
clause, called the Privileges and Immunities Clause, provides that "the
citizens of each State shall be entitled to all the privileges and
immunities of citizens in the several states." It was the Legislative
Counsel's conclusion, based on the case law precedents he reviewed
centering on both the clauses, that Caltrans would not have violated
either of these clauses of the United States Constitution had it included
a requirement that railcars be assembled in California.
Other As M-K's original proposal did not indicate any commitment
Correspondence concerning California content, Caltrans instructed Booz-Allen &
Hamilton, Inc. (Booz-Allen), the consultant that Caltrans hired to
Between Caltrans
administer the California Car contract, to contact M-K and request
and Morrison
assurances of M-K's intent to maximize California content. Before
Knudsen
Caltrans awarded the contract to M-K, Booz-Allen sent a letter to M-K
Regarding dated January 23, 1992, indicating that Caltrans required an assurance
California that if substantial subsequent orders of California Cars were exercised
Content under the option provisions of the contract, that M-K would pursue
every reasonable means to maximize the California content of the cars
and perhaps assemble them in California. Caltrans required this
assurance as part of M-K's final proposal.
In a cover letter accompanying M-K's final proposal to Caltrans dated
January 27, 1992, the M-K's president stated that the company was
committed to establishing a car assembly facility in California for the
California Cars. The letter went on to say that initial production of the
first 72 cars would be performed at the company's New York facility to
meet the schedule to deliver the first cars 18 months after the date
Caltrans notified M-K to proceed with the contract. The president
further advised that "some final assembly of the cars would be phased
in" for the original cars ordered, and if an option for additional cars
followed, M-K would maximize the California content on those cars.
Apparently, Caltrans needed further clarification regarding the phasing
in of final assembly work discussed in M-K's January 27, 1992, cover
letter because M-K's president sent another letter on January 29, 1992,
clarifying the company's position. The president stated that, because
of the short initial delivery requirement, the first 10 cars had to be
entirely assembled at the company's New York facility. However, for
the remainder of the order, the president stated that M-K would
perform up to 25 percent of the final assembly at the newly established
facility in California. Additionally, the president stated that, if
Caltrans were to
8
award substantial follow-on contracts for similar cars, M-K would
further increase the California content of final assembly labor to a 50 to
75 percent range.
California Content On November 30, 1993, Caltrans executed a contract change order with
Provisions in the M-K to provide 25 additional California Cars under the option
provision contained in Caltrans' RFP. Section III of this contract
Contract Change
change order specifies the amount of California content that Caltrans
Orders
expects M-K to provide, both for the 25 additional cars as well as for
the 88 cars to be provided under the original contract.
Specifically, Section III of the change order requires M-K to create the
equivalent of approximately 580 person-year (PY) jobs at its assembly
facility in Pittsburg, California. These jobs would be for assembly and
final testing on 66 cars, 45 cars from the original order and 21 from the
additional order. A person-year equates to approximately 2,088 hours
of work a year, less any vacation, holidays, sick leave, or other time
taken off.
To ensure adherence by M-K with Section III of the change order, the
change order also stipulates that liquidated damages in the amount of
$20,000 per car will be assessed if M-K fails to use California labor in
the assembly and final testing of at least 66 cars.
We sought an opinion from the Legislative Counsel regarding Caltrans'
ability to enforce the California content provisions contained in the
RFP, contract, and change orders to the contract. It was the
Legislative Counsel's opinion that, until Caltrans executed the
November 1993 change order for the purchase of the additional
railcars, there were no enforceable provisions for California content.
However, once the contract change order containing the more explicit
provision for the inclusion of California content was executed and
became part of the contract, the additional provisions are enforceable.
In other words, the amended contract between Caltrans and M-K now
requires M-K to create the equivalent of about 580 jobs in California
for the assembly and final testing on 66 of the railcars.
According to M-K's program manager for the California Car contract,
as of December 1993, 60 employees had been hired at M-K's Pittsburg
assembly facility. The program manager stated that these employees
are currently working on or supporting a contract that M-K has with the
Bay Area Rapid Transit (BART) to assemble 80 cars. M-K's program
manager estimates that by July 1995, M-K will employ approximately
300 California workers during peak production in assembling the
BART cars and the 66 California Cars. Furthermore, according to the
9
M-K project manager, M-K will use approximately 618 California
person-years associated exclusively with the California Cars during the
contract's life.
Changes Imposed Through Contract Change
Orders Have Affected the Overall Cost
and Delivery Time of the Railcars
Chapter 2
Chapter After the Morrison Knudsen Corporation (M-K) was awarded the
Summary contract in February 1992, the state Department of Transportation
(Caltrans) issued the Notice To Proceed authorization to begin the
California Car Project on March 2, 1992. The contract called for the
production of 88 railcars at a total cost of $153.7 million. The delivery
schedule established for the production of the 88 railcars called for the
delivery of the first car by August 1993. However, because of the
impact of added costs and schedule delays imposed by individual
change orders, the original cost of the contract has increased to
$214 million and the scheduled delivery dates of the first railcars have
been delayed from August 1993 to August 1994.
Several factors contributed to the changes in this contract that have
added to the cost and delivery time of the railcars. First, as is typical
in the railcar building industry, Caltrans and M-K entered into a
contract that only spelled out in general terms the design characteristics
of the California Car. After first obtaining input from the Rolling
Stock Advisory Committee (RSAC), which was established to provide
input to the design of the railcars in accordance with Proposition 116,
Caltrans developed a Request for Proposals (RFP) based on general
parameters or "performance specifications" rather than detailed design
specifications. According to the chief of the Office of Rail Equipment
for Caltrans, it is not surprising that there were change orders on this
type of contract, since not all of the design characteristics of the
California Car were spelled out in detail in the performance
specifications. So, as the design characteristics of the California Car
became more detailed, change orders became necessary.
A second factor that has added cost and time to this contract is that
Caltrans exercised a contract option to have M-K produce an added
10
25 cars to the original 88-car order. By exercising this option, Caltrans
added $54.6 million to the contract cost and extended the delivery
schedule two months. A third factor that has contributed to the added
cost and extended delivery is that in overseeing the design of the
railcars, Caltrans has had to be responsive to the input of local
transportation agencies and railroad operators. One of the change
orders that we discuss in this chapter was the result of negotiations
between local transportation agencies and Caltrans about the internal
configuation of the commuter car. These negotiations led to a
five-month delay in the original delivery schedule.
As of January 1, 1994, the contract total has increased by
approximately $60.7 million. Change orders also affected the
scheduled delivery of the California Cars. The first railcar had been
scheduled for delivery in August 1993. Because of changes and
modifications brought on by a variety of factors, the delivery date of
the first car has been delayed by a total of 12 months and is currently
scheduled for delivery in August 1994. The final car of the original
88-car order originally scheduled for delivery October 1994 is now
scheduled for delivery by December 1995. The last car of the
additional 25-car order is scheduled for delivery in April 1996.
Background Caltrans issued an RFP to procure the California Cars based on general
performance specifications rather than detailed design specifications.
When issuing an RFP for the design and assembly of complicated
machinery or equipment, the procuring entity can require that potential
contractors submit proposals based on either detailed specifications or
performance specifications. Detailed specification contracts are used
when the procuring entity's objective is essentially to reproduce an
existing product, with design elements, drawings, and specifications
being available to bidding contractors at the time of bid. In contrast,
performance specification contracts are used when the awarding entity
intends to produce a new product and existing designs are not available.
Performance specification contracts provide proposers with the general
parameters of the project to be constructed, leaving the actual design
details to the winning proposer.
Provisions in Proposition 116 required Caltrans to establish an advisory
committee to assist Caltrans in developing specifications for
standardized California commuter and intercity railcars and
locomotives. The committee was to consist of one consumer
representative and representatives from all affected local transportation
agencies, as well as the department's Division of Mass Transportation.
To meet this requirement, Caltrans established the RSAC, which
included representatives from the Legislature, Amtrak, and a variety of
11
regional transportation agencies throughout the State. The RSAC
provided information for the specific criteria the California Car needed
to meet. Caltrans used this input to develop the performance
specifications that the RSAC eventually approved and that were
included in the RFP.
According to the chief of the Office of Rail Equipment for Caltrans, a
contract based on performance specifications typically leads to
modifications after the award of the original contract. Since only
general parameters are established at the beginning of the process,
modifications become necessary as the specifications and designs are
developed in more detail. While some change orders are merely
technical in nature, such as clarifying design wording, a change order
can also have an effect on the overall cost of the work done, the
initially agreed upon product delivery schedule, or both.
Although changes can result from normal design modifications agreed
to by the purchaser and contractor, external influences may also
contribute to contract changes. For the California Car project, Caltrans
is in the unique position of not being the actual operator of the
completed railcars, but rather is acting as a purchasing agent for other
California transportation agencies. Because of this arrangement, these
other transportation agencies can influence changes that are to be
adopted. For instance, Caltrans has an agreement with the Southern
California Regional Rail Authority (SCRRA) and the Peninsula
Commute Rail Service (Caltrain) to procure 47 California Cars for use
by these local commuter service providers. Therefore, Caltrans, acting
as a purchasing agent, had to be responsive to the needs of these two
entities. One change order we reviewed resulted from discussions
with these two transportation agencies as to the type of railcars that best
served their needs. This change order led to a delay in the delivery
schedule. (We discuss this change order further on pages 20 through
22 of this report.)
Effect of Since February 1992, when M-K was awarded the California Car
Change Orders contract, various design modifications and associated changes have
been implemented. Caltrans has approved and executed the change
on Overall Cost
orders that it determined were necessary for the proper completion of
the project. Caltrans originally contracted with M-K for the
production of 88 California Cars for an amount totaling approximately
$153.7 million. Since the signing of the original contract, dated
February 20, 1992, Caltrans has executed a total of 19 separate change
orders and has 2 more change orders that are currently pending
approval. Of the 19 executed and 2 pending change orders, 11 have or
will affect the overall cost of the contract, increasing it by a net total of
12
approximately $60.7 million. However, one of these change orders in
the amount of approximately $54.6 million, added 25 cars to the order,
increasing the number of cars purchased from M-K from the original 88
to 113 cars. The remaining 10 change orders have or will increase the
original contract amount by a net total of approximately $6.1 million,
or 4 percent of the original $153.7 million contract total. Thus, the
total amount that Caltrans has currently committed to the M-K contract
for the production of 113 railcars is approximately $214 million
including two change orders totaling approximately $1.1 million that
are pending approval. (Figure 1 on page 15 shows the cost changes to
the California Car contract.)
13
Insert Figure 1
The Provisions in the California Car contract allow Caltrans to make such
Negotiation alterations or additions to the contract and to require any extra work
that the Caltrans engineer considers necessary or advisable for the
of Contract
proper construction or completion of the contracted work. The
Change Orders engineer is Caltrans' designated representative in deciding all questions
that may arise as to the acceptability of materials furnished, work
performed, compensation made, and requirements met. In addition,
the contract also allows Caltrans to negotiate any price changes
resulting from legislation or regulations that become effective between
the time of the contractor's original proposal and the date of
manufacture of the railcars.
All changes are formalized into a contract change order that specifies
the work to be done in connection with the change made. A change
order will also specify the basis of compensation for such work.
If the engineer for Caltrans determines that new or unforeseen work is
necessary and that such work is not covered under the specifications of
the contract, it is classified as extra work and compensated accordingly.
Contract provisions reserve the right of Caltrans to "make such
alterations or additions to, or deviations and omissions from, contract
documents as its engineer considers necessary or advisable." The
contract limits the compensation to be paid to the contractor for any
extra work performed to actual costs plus an agreed upon overhead
rate.
Occasions may arise when the contractor and Caltrans disagree as to
what constitutes extra work. On these occasions, the contract
stipulates that if a change order specifies work to be done that the
contractor considers extra work, the contractor must agree to the work
within the change order and serve written notice to the engineer within
72 hours. The written notice must state why the contractor considers
the work specified in the change order to be extra work, and the
contractor must furnish all time slips and other memoranda as may be
required by the engineer during the performance of such work. This
enables Caltrans to cancel or modify the change order or take other
appropriate action to reach agreement with M-K.
Based on the contract provisions, it is our opinion that for significant
change orders occurring after the award of the contract, Caltrans has no
discretionary authority under the contract to unilaterally determine
M-K's compensation for complying with those change orders.
However, Caltrans does have authority under the contract to negotiate
price adjustments for other types of change orders, such as those
mandated by legislation or regulations that take effect between the date
14
Caltrans opened M-K's technical proposal and the date the railcars are
manufactured. In addition, Caltrans has the authority to modify,
disapprove, or cancel a change order.
Examples of Change Orders
Individual change orders resulted in price increases to the contract
ranging from a low of $33,600 to a high of $54.6 million. Although
not all change orders affected the contract's cost, the types of changes
that occurred included major changes, such as exercising a contract
option to purchase an additional 25 railcars to a relatively minor change
for the purpose of adjusting the production ratio of intercity to
commuter cars. In another change order, Caltrans exercised an option
to include an interlocking system between the door control and the
propulsion and traction system to prevent any train motion when the
doors of the cars are opened for all 88 of the railcars included in the
original contract. The inclusion of this optional system on all 88
California Cars resulted in an increase in the contract's cost of
$407,616.
Not all change orders increased the contract's cost. For instance, one
change order resulted in an overall cost savings to the California Car
project. The purpose of the change was to exercise an accelerated
payment schedule option offered by M-K in its original proposal. The
option had the effect of reducing the price of the car order by
$2.2 million. The original contract included a payment schedule
requiring Caltrans to make progress payments to M-K amounting to
34 percent of the total contract price before the delivery of the first
California Car. In exchange for the $2.2 million price reduction,
Caltrans agreed to substitute a payment schedule requiring Caltrans to
make progress payments to M-K totaling 44 percent of the total
contract amount before the delivery of the first California Car.
To determine the reasonableness of paying M-K 44 percent of the
contract price before the delivery of the first California Car, we
obtained an analysis performed by the consultant Caltrans hired to
administer the contract of milestone payment schedules for several
other vehicle construction projects, including light railcars and tri-level
commuter cars. The analysis included seven vehicle construction
projects undertaken in the United States between 1988 and 1992.
Although different construction projects may structure milestone
payment schedules based on different assumptions and factors, a
general comparison can be made between projects concerning the
percentage of the total contract amount advanced to the contractor
before product delivery. According to the consultant's analysis, new
vehicle construction contracts have provided for progress payments
15
varying from 21 percent to 51 percent of the total contract price before
the construction of the first vehicle. In view of similar practices
throughout the industry, Caltrans' decision to execute a change order to
increase its progress payments to M-K by 10 percentage points appears
reasonable.
Also, although Caltrans has agreed to implement various changes and
modifications during the course of the California Car project, Caltrans
still has the means to guarantee the faithful performance by the
contractor. Specifically, the contract required M-K to post a
performance bond of at least 50 percent of the total contract price to
ensure M-K's performance on this project. In addition, this same
contract provision also requires the bond to be increased to offset price
increases caused by exercising contract options, such that the
performance bond at all times equals at least 50 percent of the total
outstanding contract price. Therefore, Caltrans has a mechanism to
enforce M-K's performance on the construction of the California Car.
Effect of Various factors contributed to delays in the original schedule of the
Change Orders in California Car. Each of the delays in the scheduled delivery dates are
reflected in the form of change orders. As of January 1994, the
Producing Delays
schedule for the delivery of the California Car has slipped by
12 months since the contract was originally signed. The delivery
schedule established after Caltrans signed the contract for the
production of the 88-car order called for the delivery of the first
California Car by August 1993 with the last of the cars to be delivered
by October 1994. The most recent schedule now calls for the delivery
of the first car by August 1994 with the last of the cars scheduled for
delivery by April 1996. The latest schedule also reflects the delivery
of an additional 25 railcars.
To ensure the timely delivery of the railcars, Caltrans included
liquidated damages provisions in the contract. These provisions
require M-K, in lieu of actual damages, to pay the State an agreed upon
amount for each calendar day delay in finishing the work in excess of
the prescribed delivery requirements. For example, if M-K does not
deliver the first railcar by the latest schedule, that is, by August 1994,
then Caltrans can penalize M-K by requiring a cash payment from M-K
for each day beyond the deadline that M-K is late. The provisions of
the damages clause take into consideration the changes in the delivery
requirements established after Caltrans signed the contract for the
production of the 88-car order, imposed by executed change orders.
16
Change Order for the Modification of Railcar
Floor Height Caused Five-Month Delay
The first delay affecting the delivery schedule was associated with a
design change to the floor height of the California Car, causing a delay
of five months. To increase passenger accessibility, Caltrans intended
the California Cars to have the lowest possible floor height within the
parameters specified in the RFP.
The floor height of the railcar is measured in a design specification as
the height from the top of the railroad tracks to the railcar's floor. In
the RFP, Caltrans had originally issued a performance specification that
was approved by the RSAC for the lowest feasible floor height within
clearance requirements and the general structure of the railcar. The
clearance requirement outlined in the performance specification merely
required the cars to be capable of operating within clearances for
restricted operation, as defined by the California Public Utilities
Commission diagram and Amtrak's Western Operations clearance
diagram. In the design process, clearance diagrams provide guidelines
that railcar builders use to develop a design such that no part of the
railcar will be obstructed by the rail tracks or objects external to the
railcar. For instance, a clearance diagram provides measured limits to
the design of any equipment attached below the railcar floor. These
underfloor limits ensure that the railcar can safely pass over the railroad
tracks without obstruction.
Despite not knowing the minimum floor height the clearance diagrams
could accommodate, Caltrans suggested a 14 inch floor height as a goal
in the RFP. While not presented as a contractual requirement, the
specifications implicitly suggested that proposers should explore
designing the railcars with a 14 inch floor height, as long as the height
was within the parameters of the clearance diagrams. However,
Amtrak operates railcars with a minimum floor height of 18 inches
from the top of the railroad tracks. In response to the RFP, M-K's
initial proposal specified an 18 inch floor height that was within
Amtrak's existing Western Operations clearance diagram parameters.
However, Caltrans continued to pursue the possibility of a lower floor
height to increase passenger accessibility, particularly for those
passengers with physical disabilities. Then, in November 1991, after
Caltrans had issued the RFP, the Association of American Railroads, a
trade organization that sets clearance standards for railcars, adopted a
new "plate H" clearance diagram with less restrictive clearance
requirements. M-K initially expressed reservation about designing the
cars with a 14 inch floor height but it agreed it could technically design
and build the cars with a lower floor height if the recently adopted
"plate H" diagram were included in the specifications. Caltrans and
M-K agreed to substitute this newer diagram for the Amtrak clearance
17
diagram in the specifications. After Caltrans made this modification,
M-K committed to the 14 inch floor height and began designing to this
criteria.
At a meeting in May 1992, to discuss the progress of the California
Car, Amtrak indicated that if the California Car were built to the
existing Amtrak clearance diagrams it would have no problem
operating the cars. However, Amtrak asserted that if the cars were
built to design guidelines other than its own, the design would need to
be submitted to Amtrak for review and approval before the cars could
be permitted to run on Amtrak lines. Amtrak was uncertain as to how
long the review process would take but stated that it might be lengthy.
Consequently, to avoid any delays associated with obtaining approvals
for operating the railcars from Amtrak and other host railroads, M-K
and Caltrans agreed to use the 18 inch floor height specifications from
existing Amtrak Superliner equipment. As a result, a change order
was executed to use the higher floor height specification for the
California Car design. The discussions among the interested parties
over this proposed change to the railcar's design caused a delay in
M-K's design effort. To accommodate this, Caltrans and M-K agreed
to a delay in the delivery schedule of up to five months. (Figure 2 on
page 21 shows the delay in the delivery schedule because of the change
in the floor height specifications.)
18
Insert Figure 2
19
Change Order To Reconfigure Interior of the
California Car Caused Five-Month Delay
Caltrans also agreed to another five-month delay in the California Car
delivery schedule when it executed a change order that converted the
design for the commuter car portion of the order from a bi-level to a
tri-level design. This change resulted from negotiations between
Caltrans and several commuter service providers.
The bi-level commuter car design in M-K's proposal complied with the
intent of the California Car concept to develop a standard railcar that
could be used in intercity and commuter services throughout the State.
The proposed M-K bi-level commuter car design provided a commuter
car using a car shell with most of the major systems, subsystems, and
components placed in the same location as in the intercity cars.
Although M-K's design complied with the RSAC specifications, some
of the Southern California members of the RSAC stated that they did
not want to operate the bi-level car in their services because they did
not like the interior arrangement of the stairs. During a progress
review meeting in November 1992, Caltrans and M-K agreed that the
commuter agencies had a strong preference for a tri-level commuter
car.
During negotiations between Caltrans and the SCRRA, M-K
introduced the possibility of converting the bi-level commuter design
into a tri-level configuration. In particular, the SCRRA expressed its
desire to have a commuter car produced similar to the tri-level design
built by another railcar producer, the Urban Transit Development
Corporation. However, M-K learned that the Portugal-based company
it had contracted with to produce the California Car shells was not
interested in producing the car shells with a tri-level design. M-K
eventually found a Brazil-based car shell producer who could
accommodate the production of the tri-level design, but it would cost
M-K an additional $7.5 million to cancel the commuter car portion of
its contract with the original car shell producer. M-K eventually
agreed to absorb the cost associated with canceling the commuter car
part of its original order with the Portuguese car shell producer. But in
exchange for M-K making this and other concessions, Caltrans agreed
to exercise a contract option to purchase an additional 25 intercity cars.
Another of the concessions that M-K made as part of obtaining the
additional 25-car order was discussed on pages 9 and 10 of this report,
where M-K agreed to more specific and enforceable provisions for
California content on this project.
When the SCRRA was satisfied with Caltrans' and M-K's
commitment to produce the commuter car with a tri-level design, it
formalized its agreement with Caltrans for the procurement. After the
20
"no cost" change order for the conversion to a tri-level railcar was
executed in July 1993, the SCRRA signed a formal agreement in
September 1993 to have Caltrans act as its purchasing agent to procure
24 tri-level commuter cars. Even though Caltrain had already signed
an agreement with Caltrans for up to 24 bi-level commuter cars, it, too,
expressed its preference for the tri-level design. Consequently,
because the design was changed anyway, Caltrain will also receive
tri-level railcars.
Caltrans incurred no additional cost in changing the design for the type
of commuter car from a bi-level to a tri-level car but did agree to a
five-month delay in the delivery of the cars as a result of the
negotiation process between Caltrans, M-K, and the local commuter
service providers. (Figure 3 on page 24 shows the delay in the
delivery schedule because of the change to a tri-level design.)
21
Insert Figure 3
22
Changes Needed To Correct Structural Design
Flaws Caused an Overlapping Delay of Five Months
Along with the five-month schedule delay associated with the
conversion of the commuter car to a tri-level design, structural design
problems caused an overlapping delay of five months. According to
correspondence between Caltrans and M-K, it is standard practice in
the railcar industry to perform a structural stress analysis of the car
shell design early in the design process. This analysis is known as a
finite element analysis. However, before performing this analysis of
the car shell, M-K had completed the design for other structural
portions of the car and ordered raw materials for their manufacture.
When M-K eventually performed its first finite element analysis in
November 1992, it found several high stress concentrations in the car
shell design that would render it unstable under higher weight loads.
As part of the structural redesign that these stress concentrations
necessitated, M-K determined it also needed to use a higher strength
steel for portions of the car shell. The redesign process, coupled with
the time needed to order the higher strength steel, resulted in a delay of
approximately five months.
Despite repeated statements of concern issued by Caltrans to M-K as
early as July 1992 regarding M-K's approach to testing the car's
structural design, M-K waited until late in the design sequence to begin
the finite element analysis of the car shell. According to a letter to
M-K from the chief of the Office of Rail Equipment for Caltrans, the
delay associated with the design problem would have been mitigated
had the finite element analysis been initiated earlier in the car shell
design process. However, because the delay associated with this
problem ran concurrently with another delay, no additional time was
added to the overall delivery schedule and no added costs were incurred
by Caltrans. Therefore, Caltrans did not penalize M-K for causing the
delay.
Change Order To Acquire 25 Additional Cars
Resulted in a Two-Month Delay
The most recent delay in the delivery schedule occurred in
November 1993. This delay was accepted by Caltrans when it
executed the change order to authorize the acquisition of an additional
25 intercity cars. The revised schedule projected the delivery of the
first railcar to August 1994, extending by two months the delivery
schedule that was in effect before the change order. (Figure 4 on page
26 shows the delay in the delivery schedule because of the additional
25 cars.)
23
Insert Figure 4
FIGURE 1
Cost Changes to the California Car Contract
24
25
sralloD
Cost of additional 25-car opt
$250,000,000 ($54,555,684)
Other change order costs
($7,084,895)
Original contract amount
($153,660,088)
$200,000,000
$150,000,000
$100,000,000
$50,000,000
$0
Original Contract Contract and Contract, Changes,
Changes and 25-Car Option
According to the chief of the Office of Rail Equipment, Caltrans agreed
to M-K's request for an additional two-month delay in the delivery
schedule in exchange for more comprehensive provisions for liquidated
damages in the agreement between Caltrans and M-K. These added
provisions applied to the additional 25 intercity cars and to the first two
cars of the original 88-car order. These provisions for liquidated
damages were included in a Memorandum of Agreement attached to
the change order authorizing the production of the additional 25
intercity cars. These provisions stipulate that for the two cars of the
original order, M-K will be assessed $50,000 for the first late day
beyond the scheduled delivery dates of August 31, 1994, and
September 20, 1994, respectively, and $1,000 for each late day
thereafter up to $80,000 per car.
In addition, with respect to the additional 25 intercity cars, a
$300 liquidated damages assessment will be levied upon M-K for each
day's delay beyond the scheduled delivery date of each car, but only if
the car is delivered on or after May 30, 1996. According to the
Legislative Counsel, these added contract provisions do not limit the
provisions for liquidated damages that existed before these changes.
Consequently, M-K can also be charged $300 for each car for each
day's delay beyond the final delivery date of December 31, 1995, for
the remaining 86 cars included in the original purchase.
26
Page Left Intentionally Blank
27
Chapter 3 A Change in the Participation Goals for
Disadvantaged Business Enterprises and
Its Effect on the California Car Contract
Chapter The Legislature requested information about the efforts of the state
Summary Department of Transportation (Caltrans) and the Morrison Knudsen
Corporation (M-K) to meet participation goals for disadvantaged
businesses in the California Car Project. Both state and federal law
contain provisions encouraging increased participation of
disadvantaged businesses in the fulfillment of contracts with
governmental entities. Originally, Caltrans included California's
statewide goals for the participation of disadvantaged businesses in the
railcars project. But by the time the contract for designing and
producing the railcars was awarded to M-K, Caltrans had substituted
the less rigorous federal goals for the statewide goals. This
substitution took place because of the involvement of $5 million of
federal dollars on this project. However, Caltrans changed course
again, eight months after the award of the contract to M-K. At this
time, Caltrans negotiated a change order with M-K that reiterated that
the federal goals were to apply for this contract, but also required that
M-K make a "good faith effort" to attain the state's goals throughout
this contract. However, the change order does not outline M-K's
responsibilities in making a "good faith effort" in seeking the
participation of disadvantaged businesses in the event it is unsuccessful
at meeting the participation goals.
We recommend that M-K's responsibilities to make a good faith effort
be clearly specified in the event that M-K is ultimately unable to meet
the statewide goals for the participation of disadvantaged businesses.
In their original proposal, M-K expressed reservation about their ability
to meet statewide participation goals for this contract.
Background Both state and federal law contain provisions encouraging increased
participation of disadvantaged business enterprises in the fulfillment of
contracts with governmental entities. Specifically, Section 10115 of
the California Public Contract Code requires state agencies that award
contracts for construction, professional services, materials, supplies,
equipment, alteration, repair, or improvement to have statewide
participation goals of at least 15 percent for minority businesses and at
least 5 percent for women's businesses. In addition, beginning
January 1, 1993, Section 10115 was amended to include a statewide
28
participation goal of 3 percent for disabled veteran business enterprises.
These statewide participation goals apply to the overall dollar amount
each state agency spends for the contracts it awards during the year.
In addition, Section 10115.2 of the code requires agencies awarding
contracts to consider the efforts of bidders to meet the participation
goals established for the business enterprises of minorities, women and
disabled veterans. The code requires agencies to award contracts to
the lowest responsive bidder either meeting the statewide participation
goals by including the requisite percentage for the businesses of
minorities, women and disabled veterans as subcontractors or suppliers
or by making a good faith effort at meeting the goals.
The code defines a good faith effort as a bidder's ability to prove to the
awarding agency's satisfaction that the bidder took all the following
actions:
Contacted the awarding department, other state and federal
agencies, and local business organizations of minorities, women
and veterans to identify these business enterprises;
Advertised in papers focusing on these types of businesses; and
Submitted invitations to bid to these businesses and gave them
consideration as subcontractors.
Furthermore, the Code of Federal Regulations, Title 49, Section 23.67,
requires each entity receiving federal funds to ensure that transit
vehicle manufacturers, as a condition of being authorized to bid on
transit vehicle procurements in which federal funds are used, formulate
their goals for obtaining the participation of disadvantaged businesses.
The goals established by the transit vehicle manufacturers are approved
by the Federal Transit Administration of United States Department of
Transportation, formerly called the Urban Mass Transit Administration
(UMTA). The participation goal is expressed as a percentage and is
calculated using, as its base, the amount of UMTA funds that will be
spent within the United States on transit vehicle contracts undertaken
by the vehicle manufacturer during the fiscal year of the bid. If the
goal the vehicle manufacturer projects is less than 10 percent of the
base, Section 23.65 requires the manufacturer to justify to the UMTA
administrator why it feels it will not be able to meet 10 percent
participation.
29
Unlike state law, federal law makes no distinction between minorities'
and women's businesses, including both under the category of
disadvantaged business enterprises. In addition, federal law does not
set any participation goals for the businesses of disabled veterans.
Participation Although Caltrans had originally established state goals for the
Goals Contained participation of disadvantaged businesses in the railcars contract, by the
time the contract was awarded Caltrans had substituted federal goals
in the Request
for obtaining the participation of disadvantaged businesses. Caltrans'
for Proposals
original Request for Proposals (RFP), dated August 16, 1991, contained
a section relating to disadvantaged business enterprise goals. In its
original form, this section of the RFP informed proposers that Caltrans
had established a disadvantaged business enterprise (DBE)
participation goal for the California Car contract of 15 percent for
minority business enterprises (MBE) and 5 percent for women's
business enterprises (WBE). The RFP stated that the DBE
requirements would apply to the total price of all work performed on
the contract within the United States. The RFP also required interested
proposers to identify proposed MBE and WBE subcontractors and the
proportion of the total proposal value to be allocated to each.
Additionally, the extent to which proposals met or exceeded the
participation goals specified in the RFP was listed by Caltrans as one of
the criteria used in selecting the winning proposal for the California Car
contract. However, the RFP did not specify what constituted a good
faith effort or make any reference to the Public Contract Code section
that does define such efforts.
According to the chief of the Office of Rail Equipment, M-K submitted
the only responsive proposal for the railcar project. In its proposal,
M-K established disadvantaged business enterprise goals projected at
2.5 percent for MBE content and .4 percent for WBE content. Further,
in its proposal for disadvantaged businesses M-K included a statement
about the participation goals for disadvantaged businesses in the RFP.
M-K stated that, because of the unique nature of the California Car
project and the fact that the design was only in the preliminary stages, it
was not possible to firmly identify all minority and women's business
participation at that time. M-K went on to say that it would be very
difficult to fulfill the aggressive 15 percent MBE and 5 percent WBE
participation goals established in the RFP but that M-K was committed
to achieving the maximum level of participation. M-K also stated that
it intended to use as many qualified minority firms as possible once the
designs and workscopes were further defined. However, M-K did not
present any evidence in its proposal as to the good faith efforts it had
made to obtain the participation of disadvantaged businesses in this
project.
30
In addition to its participation goals and statement, M-K's original
response to the RFP also included a letter from the UMTA. The letter
stated that the UMTA had reviewed and approved M-K's
corporate-wide goal of 10.7 percent for the participation of
disadvantaged businesses projected for federal fiscal year 1991-92.
The letter further stated that, to comply with UMTA requirements, all
disadvantaged businesses counted as part of a participation goal must
be certified as eligible.
The Code of Federal Regulations, Title 49, Section 23.45, requires that,
in determining whether a business qualifies as an eligible
disadvantaged business, the certifying entity must take at least the
following steps:
Perform an on-site visit of the enterprise to obtain resumes or work
histories of the principal owners and conduct interviews with these
individuals;
Analyze stock ownership if the enterprise is a corporation;
Assess the bonding and financial capacity of the enterprise;
Determine the work history of the enterprise, including contracts
received and work completed;
Compile a list of the equipment to be used, the licenses issued to
the enterprise, and the key personnel pertaining to the work to be
performed as a disadvantaged enterprise; and
Obtain a statement from the enterprise regarding the type of work it
is seeking as a disadvantaged business enterprise.
The letter from the UMTA to M-K further advised that certifications of
eligibility could be obtained from a recipient of federal funds, other
transit vehicle manufacturers, or the Small Business Administration, so
long as M-K kept proper documentation in its files. Alternatively, the
letter stated that M-K could certify as to the eligibility of disadvantaged
businesses if M-K first conducted and documented eligibility
investigations in conformity with the Code of Federal Regulations,
Title 49, Section 23.45.
31
Participation
By the time M-K and Caltrans entered the contract on
Goals
February 20, 1992, the provision concerning participation goals had
Contained in the
been changed. As discussed previously, in the RFP Caltrans specified
Contract the State's participation goals of 15 percent for MBEs and 5 percent for
WBEs. However, the contract was drafted so that this procurement
would now be governed by federal requirements concerning the
participation goals for disadvantaged enterprises. The revised
provision further required that M-K submit an annual corporate-wide
participation goal for disadvantaged business enterprises to the federal
government and to provide evidence of federal approval or disapproval.
M-K had already fulfilled the requirement of providing federal
approval of its participation goal by resubmitting a letter provided to
Caltrans before as part of M-K's original proposal. Although the
federal goals are less stringent than the state goals, at this point we
cannot evaluate the impact this change could have on the actual
participation of disadvantaged businesses. Up to now, most of the
production work on the railcars has occurred outside the United States.
However, by using the federal requirements, M-K was allowed to
establish a participation goal of 10 percent for disadvantaged
businesses, with both minority and women's businesses falling under
the same designation of disadvantaged businesses. Furthermore, under
federal requirements, the participation goal is computed using the
amount of federal funds that will be spent within the United States on
all of M-K's transit contracts undertaken within a given fiscal year.
Therefore, if M-K had other large federal contracts it would be
theoretically possible for M-K to attain the 10 percent federal
participation goal without ever attaining any participation from
minority, women's or veteran's businesses on the California Car
contract.
Facts Proposition 116, passed by the voters of California in June 1990,
Surrounding the provided funding for the procurement of intercity and commuter
railcars. The proposition allowed either Caltrans or local agencies to
Use of Federal
apply to the California Transportation Commission (CTC) for the
Funds for the
allocation of state funding for an initial equipment procurement. In
California Car
February 1992, Caltrans applied for, and the CTC approved, an
Contract allocation of $100 million for the acquisition of commuter and intercity
railcars. Part of that allocation was on behalf of the Peninsula
Corridor Joint Powers Board (PCJPB), for whom Caltrans was acting
as a negotiator and purchasing agent in the procurement of 23
commuter cars for use on the Peninsula Commute Service.
In addition to the funding provided by the Proposition 116 allocation,
Caltrans also intends to use a $5 million federal grant to help pay for
32
the 23 California Cars purchased on behalf of the PCJPB. The grant is
offered by the Federal Transit Administration (FTA), formerly known
as the UMTA, for improved passenger accessibility to commuter
railcars. However, as of January 1, 1994, Caltrans had not received
the $5 million in grant funds. Instead, Caltrans has obtained a Joint
Statement of Understanding from the FTA allowing Caltrans to
continue to incur costs associated with improved railcar accessibility
until June 30, 1995, or until the FTA approves the grant without
Caltrans jeopardizing the possible future federal reimbursement of
those costs.
By intending to use federal funding along with state funds as the means
of paying for the M-K California Car contract, Caltrans contends that
federal, rather than state, participation goals apply for disadvantaged
business enterprises. As a result, Caltrans chose to require that M-K
adhere to federal participation goals. According to a legal counsel for
Caltrans, the department's position regarding federal regulations taking
precedence over state law is based on a legal analysis prepared by the
legal division for Caltrans. Caltrans had the chief counsel at the
Department of General Services review this legal analysis. The chief
counsel agreed that federal regulations could take precedence over state
regulations in the establishment of participation goals for
disadvantaged businesses, but only if Caltrans could demonstrate that
in attaining its goals under federal regulations that it also attained the
statewide goals.
The legal analysis was prepared in November 1990 in response to the
implementation of AB 1933, Chapter 61, Statutes of 1988, which
revised the Public Contract Code to require state agencies to establish
statewide participation goals for minority and women's businesses in
the awarding of contracts. The analysis argued that the State's
requirement for the inclusion of minority and women's participation
goals in construction and service contracts conflicted with federal laws
and regulations governing Caltrans contracts that were funded partially
or wholly with federal money. The two areas of state law cited by
Caltrans as conflicting with federal law concerned the establishment of
goals and the method of achieving the goals, once established.
Specifically, the analysis stated that, while state law requires setting
separate participation goals of 15 percent for minorities and 5 percent
for women's businesses, federal law sets a single minimum
participation goal of 10 percent for "disadvantaged businesses," defined
as encompassing both minority and women's businesses.
Another difference between the state law and federal law cited in the
analysis is that the state law requires a bidder to either meet minority
and women's businesses participation goals or demonstrate a good faith
33
effort to meet those goals for each contract. According to the state
law, if bidders cannot demonstrate good faith efforts, they risk being
declared nonresponsive by the agency awarding the contract. Federal
law, on the other hand, requires that the recipient of federal funds set an
overall organization-wide goal of 10 percent or more for the
participation of disadvantaged businesses on contracts awarded or
justify establishing a projected goal of less than 10 percent.
We sought an opinion by the Legislative Counsel on whether the
federal participation requirements for disadvantaged businesses
supersede the State's participation requirements when a portion of the
funding for a procurement comes from a federal source. It was the
Legislative Counsel's opinion that, for the purposes of a federally
assisted contract for the procurement of railcars, state requirements for
the participation of disadvantaged businesses are not superseded by the
federal requirements.
The Legislative Counsel based his opinion on the fact that, although the
federal and state programs for the participation of disadvantaged
businesses in public contracts differ significantly, it does not appear
that a state agency that was in compliance with the requirements of the
state program would necessarily be unable to comply with the federal
requirements applicable to that contract. Therefore, according to the
Legislative Counsel, Caltrans should apply both federal and state
standards in this project, not one standard or the other. Under this
scenario, M-K would be expected to strive for the higher state standard
and by doing so would also be attempting to meet the federal standard.
Participation Caltrans executed a contract change order in October 1992, eight
Goals Contained months after the original contract became effective, modifying the
section of its contract with M-K regarding the participation of
in Contract
disadvantaged businesses. The change order still required M-K to
Change Orders
comply with federal requirements concerning participation; however, it
also required M-K to make a good faith effort to attain state
participation goals throughout the life of the contract. State
participation goals for the following business enterprises were
specified:
15 percent for minority-owned businesses;
5 percent for women-owned businesses; and
3 percent for disabled veterans' businesses.
34
The change order further required M-K to submit a quarterly report to
Caltrans identifying the percentage and specific substance of
participation attained by M-K's suppliers. However, although the
change order did mention that M-K make a good faith effort to obtain
participation of disadvantaged businesses, the change order did not
specify what constituted a good faith effort. Also, it did not make any
reference to the section of the Public Contract Code that defines such
efforts.
Because much of the early production work on the California Car is
performed outside of the United States, there has been limited
opportunity for participation by United States' businesses at this point
in the M-K contract. However, we obtained the most recent plan
prepared by M-K showing anticipated participation of disadvantaged
businesses under the California Car contract. The plan, as of January
1994, shows M-K's commitment to a total of 20 disadvantaged
businesses representing a participation value of approximately $5
million, or 2.3 percent of the value of the United States' portion of the
contract. Of the 20 disadvantaged businesses, 9 are minority owned
and 11 are women owned. The minority-owned businesses represent a
participation value of approximately $2.3 million (1.3 percent) and
women-owned businesses represent approximately $2.7 million
(1.5 percent).
However, not all of the 20 disadvantaged businesses that M-K lists
have been certified by Caltrans as disadvantaged businesses. Seven of
the businesses possess certifications of eligibility issued by Caltrans,
although one has expired; another 9 have certifications of eligibility on
file with other entities, and the remaining 4 have not yet been certified.
Effect That If Caltrans had retained the state requirements in its contract with M-K
Revision of rather than the less vigorous federal requirements regarding the
participation of minorities' and women's businesses, M-K's required
Participation
participation goals would have been higher. Using the amount M-K
Goal Had on the
identified in its proposal as the portion of the contract to be spent in the
California
United States, state participation goals for the initial contract would
Contract have been $17.7 million for minority businesses and $5.9 million for
women's businesses (participation goals for disabled veterans'
businesses did not become effective until January 1, 1993). Moreover,
once Caltrans exercised its option in November 1993 to purchase an
35
additional 25 railcars from M-K, the participation goals would have
increased to $27.1 million for minority businesses, $9 million for
women's businesses and $5.4 million for disabled veteran's businesses.
Using the State's requirements, M-K would have had to either attain
each of these participation goals in fulfilling the contract or
demonstrate to Caltrans that it had made a good faith effort to attain
them.
Recommendation Caltrans needs to clearly specify M-K's responsibilities to make a good
faith effort in seeking the participation of disadvantaged businesses in
the event it is unsuccessful at meeting the statewide goals.
36
Page intentionally left blank.
Chapter 4 Caltrans' Ownership Rights to Design Plans and
Technical Specifications for the California Car
Chapter One of the purposes of this audit was to determine whether the state Department of
SummaryTransportation (Caltrans) could have entered into an agreement with a contractor
other than the Morrison Knudsen Corporation (M-K) to build the 25 railcars beyond
the initial 88 railcars called for in M-K's contract. Caltrans chose not to do this, instead
exercising an option in its contract with M-K to have M-K build the 25 cars. However,
if Caltrans had decided to seek a contractor other than M-K for the additional 25 cars,
Caltrans would have needed to obtain the design drawings prepared by M-K. This raises
the question of whether Caltrans would have had access to M-K's design drawings.
To address this question for the Legislature, we obtained a Legislative Counsel's opinion
on whether Caltrans could exercise a right to use design data developed by M-K during
the railcar contract and whether Caltrans could use such design data to solicit proposals
from other contractors to procure additional railcars. According to the Legislative
Counsel, at any time following the execution of the contract, Caltrans could exercise its
right to use design data developed by M-K. Further, it was the counsel's opinion that the
engineering data could be used by Caltrans in connection with the solicitation of
proposals for the procurement of additional railcars.
Another issue we were asked to address in this audit was whether it would have been less
costly for Caltrans to use a contractor other than M-K to build the 25 additional railcars.
However, it is not possible for us to conclude whether the State would have saved money
doing this without actually going through the process of advertising for this work and
receiving proposals from competing firms. According to the consultant for Caltrans, the
design drawings are refined over the life of the contract. However, the closer the plans
are to the as-built phase, the more value the plans have to other contractors who might
bid on the production of additional railcars.
BackgroundCaltrans issued Requests for Proposals (RFP) to procure the California Car project
based on approved performance specifications. An entity issuing an RFP can request
potential contractors to submit proposals based on either detailed specifications or
performance specifications. Detailed specification contracts are used when the awarding
entity's objective is essentially to reproduce an existing product, with design elements,
drawings, and specifications available to contractors at the time of proposal. In contrast,
performance specification contracts are used when the awarding entity intends to produce
a new product and existing designs are not available. Performance specification
contracts provide proposers with the general parameters of the project to be constructed,
leaving the actual design details to the prospective proposers.
37
ProvisionsI n its RFP, Caltrans included a provision regarding its rights to designs and tooling
Contained in thedeveloped under the California Car contract. In that provision, Caltrans reserved the
right to use the design and tooling developed during the course of the contract,
Request for
including any drawings, layouts, and relevant engineering data. Further, the RFP
Proposals
stated that the contractor selected would be responsible for maintaining this material
and tooling in good order for a minimum of ten years after the delivery of the last car
under the contract. In addition, the RFP stipulated that all plans, drawings, diagrams,
schematics, and specifications become the property of the State and that the contractor
will transfer such material to the State on demand, at no cost to the State.
On February 20, 1992, Caltrans executed a contract with M-K incorporating all the
provisions included in the RFP, including the provision regarding design and tooling
rights.
LegislativeO ne of the purposes of this audit was to determine whether Caltrans could have
Counsel's entered an agreement with a contractor other than M-K to build the 25 railcars beyond
the 88 railcars called for in M-K's contract. Caltrans chose not to do this, instead
Opinion
exercising an option in its contract with M-K to have M-K build the 25 cars.
However, if Caltrans had decided to seek a contractor other than M-K for the additional
25 cars, Caltrans would have needed to obtain the design drawings prepared by M-K.
This raises the question of whether Caltrans would have had access to M-K's design
drawings. To address this question for the Legislature, we obtained a Legislative
Counsel's opinion on whether Caltrans could exercise a right to use design data
developed by M-K during the railcar contract and whether Caltrans could use such design
data to solicit bids from other contractors to procure additional railcars. According to
the Legislative Counsel, at any time following the execution of the contract, Caltrans
could exercise its right to use design data developed by M-K. Further, it was the
counsel's opinion that the engineering data could be used by Caltrans in connection with
the solicitation of bids for the procurement of additional railcars.
Design Plans According to a senior associate at Booz-Allen & Hamilton Incorporated
Have Relative (Booz-Allen), the consulting firm hired by Caltrans to administer the California Car
contract, the detailed design for the railcar will be developed and refined over the life
Value
of the contract with M-K. The senior associate identified the following types of
plans as already developed or to be developed under the contract with M-K:
Initial plans are plans based on the performance specifications contained in the RFP
and only present broad concepts of the railcars' design;
Reviewed plans are the initial plans reflecting refinements made as a result of plan
reviews by both Caltrans and Booz-Allen;
Prototype plans are plans reflecting changes made after tests, such as structural
stress tests, on prototypes of the railcar;
38
Construction-in-progress plans are plans reflecting any changes made during the
assembly line production of the railcars; and
As-built plans are the final plans for the finished railcars after all acceptance testing
has been completed.
According to the senior associate, as M-K progresses toward the as-built plan phase
under the contract, the value and accuracy of plans increase as does the ability of Caltrans
to effectively use the plans to solicit bids for the production of additional railcars. The
senior associate stated that Caltrans was the owner of all the plans developed for the
railcar by M-K. However, the senior associate also stated that the closer the plans are to
the as-built plan phase, the more value the plans have to contractors bidding on the
production of additional railcars.
Should Caltrans One of the issues that we were asked to address in this audit was
Have Chosen whether it would have been less costly for Caltrans to use a contractor
other than M-K to build the 25 additional railcars. Without actually
Other Contractors
soliciting proposals from other contractors, we cannot conclude on
for Additional
whether the State would have saved money using other contractors.
Work?
However, M-K would enjoy certain advantages over other proposers if Caltrans were to
solicit proposals for additional railcars and M-K were one of the
proposers. These advantages include, but are not limited to, the
avoidance of start-up and infrastructure costs, tooling costs, and learning curve delays.
In addition, M-K already has secured suppliers and proven subcontractors.
Chapter 5 Incurred and Projected Overhead Associated
With the California Car Contract
Chapter One of the purposes of this audit was to assess the reasonableness and propriety of the
Summaryoverhead costs associated with managing the California Car contract. Overhead
includes the costs of approving and inspecting each of the deliverables produced by
the Morrison Knudsen Corporation (M-K), such as the designs, plans, and railcars.
Overhead also includes the costs of administering the M-K contract. Overhead for the
M-K contract is incurred by both the Division of Rail and the Office of Rail Equipment
within the state Department of Transportation (Caltrans) in addition to the consultant
hired to administer this contract, Booz-Allen & Hamilton, Incorporated (Booz-Allen).
The overhead costs associated with managing the M-K contract will total an estimated
$8.2 million, or 3.8 percent of the total cost of the M-K contract. This includes the
expenses of both the Office of Rail Equipment and the consultant, Booz-Allen. To
gauge the reasonableness of the $8.2 million that will be spent overseeing the M-K
contract, we contacted three entities that administer contracts of comparable size and
39
scope to the M-K contract. We requested from these entities their overhead costs for
managing their respective contracts. However, these entities were either unable or
unwilling to share this information with us. According to a Division of Rail planning
document, for other railcar procurements in the United States, the cost of overseeing the
project typically ranges between 5 percent and 8 percent of the total contract price.
To gauge the propriety of the amounts charged by Booz-Allen for overseeing the M-K
contract, we reviewed a sample of the supporting documentation for all billings received
to date by Caltrans. We ensured that the amounts being charged were allowable costs
according to the terms of Booz-Allen's contract with Caltrans. We found no improper
expenditures among the items we tested.
BackgroundCaltrans entered into a contract with Booz-Allen on January 29, 1992, to provide
consultant services for the oversight, support, and training of Caltrans employees in
administering the California Car contract between Caltrans and M-K. The total amount
of the Booz-Allen contract is $3.7 million, and unless it is extended, will end on June 30,
1995.
As the consultant chosen by Caltrans to oversee the M-K contract, Booz-Allen agreed to
provide support to Caltrans in the following primary areas:
Ensuring M-K complies with the specifications contained in its contract with
Caltrans;
Representing the interests of the State of California throughout the design,
development, production, assembly, and acceptance testing phases of Caltrans'
procurement of railcars from M-K;
Training Caltrans employees to oversee the manufacturing of the railcars produced by
M-K; and
Providing general engineering, administrative, and management support in solving
any problems that might arise during the course of the M-K contract.
The Office of Rail Equipment was assigned responsibility for determining the number of
commuter and intercity railcars needed throughout the State, developing a competitive
negotiation process for the acquisition of the railcars, evaluating proposals, awarding the
contract to the most competitive of the proposers, and establishing a delivery schedule for
the railcars that would best serve the needs of the operators of California's rail services.
Overhead costs of the California Car contract are paid from two different fund sources.
The Booz-Allen consulting contract is funded from Proposition 116 bond proceeds while
the overhead incurred by the Office of Rail Equipment is funded through the Caltrans
operating budget, except for out-of-state travel, which Caltrans pays for with $400,000 of
Proposition 116 bond proceeds allocated for that purpose.
40
Incurred andW e limited our analysis of overhead costs to only those costs directly related to
Projecteda dministering the M-K contract. Therefore, we excluded administrative costs
incurred by the Office of Rail Equipment for developing the Request for Proposals
Overhead
(RFP) for the California Car and for evaluating proposals. In addition, we excluded
Relating to the
any estimated post-contract activities, such as inspection and maintenance costs
California Car
occurring after M-K has completed the contract. Likewise, we excluded from our
Contractanalysis consultant fees paid to Booz-Allen by Caltrans for assistance in developing
the California Car RFP and any costs that may be incurred by Booz-Allen after the
completion of the M-K contract.
Managing the M-K contract is only one of the various responsibilities of the Office of
Rail Equipment. However, the Office of Rail Equipment does not account for its costs
associated with the M-K contract separately. Therefore, we were required to estimate
the Office of Rail Equipment's costs related to the M-K contract.
To estimate the annual labor component, we identified the number of personnel years
(PY) spent or budgeted within the Office of Rail Equipment for each year of the M-K
contract. Then, we multiplied each year's total PYs by $53,000, the amount Caltrans
uses to express the value of a person year for budgetary purposes. In estimating the
Office of Rail Equipment's overhead expense, we also included a portion of the costs of
Caltrans' Division of Rail.
As shown in Table 1 below, the total incurred and projected overhead associated with the
oversight of the California Car contract is approximately $8.2 million or 3.8 percent of
the total cost of the M-K contract. Moreover, of the $8.2 million, $1.9 million was for
the incurred or projected overhead costs of the Office of Rail Equipment and $6.3 million
was for the incurred and projected overhead costs of Booz-Allen. However, the $6.3
million figure also includes Booz-Allen's request for a $2.5 million increase in its
contract with Caltrans to compensate it for work beyond that covered in the original
contract and for administering the additional procurement of 25 more railcars.
Booz-Allen's request is currently under review by Caltrans but has not been approved as
of February 3, 1994.
Table 1
Overhead Costs for Oversight of
the California Car Contract
Fiscal Year
Total
1991-92 1992-93 1993-94 1994-95 1995-96 Contract
Actual Actual Budget Projected Projected Period
Caltrans $181,643 $ 307,913 $ 535,031 $ 546,056 $ 343,044 $1,913,687
Booz-Allen
Contract 277,723 1,413,075 1,004,173 1,004,173 2,548,283 6,247,427
Total Cost $459,366 $1,720,988 $1,539,204 $1,550,229 $2,891,327 $8,161,114
41
To determine if the incurred and projected costs for Booz-Allen's and Caltrans' oversight
of the California Car contract with M-K is reasonable, we contacted three other entities
that administered contracts of comparable size and type to the M-K contract and
attempted to obtain their costs for administration. However, we were unable to obtain
such information either because the entity did not keep records that segregated these costs
or because they were unwilling to share such information with us.
However, according to a Division of Rail planning document dated December 6, 1991,
the cost of oversight for most United States' railcar procurements typically ranges
between 5 percent and 8 percent of the total contract price, with 6 percent or 7 percent
being the average.
To determine the propriety of the amounts charged by Booz-Allen for overseeing the
M-K contract, we reviewed a sample of the supporting documentation for all billings
received to date by Caltrans. We ensured that the amounts being charged were
allowable costs according to the terms of Booz-Allen's contract with Caltrans and that
such charges agreed with the amounts shown in the summarized billings. We found no
exceptions during our testing. In addition, we reviewed all the allocations of Proposition
116 bond proceeds made as of December 1, 1993, by the California Transportation
Commission to ensure that all such allocations were in the amounts and for the purposes
intended by the proposition and stated in the California Public Utilities Code, Section
99620 et seq. Again, we found no exceptions.
We conducted this review under the authority vested in the state auditor by Section 8543
et seq. of the California Government Code and according to generally accepted
governmental auditing standards. We limited our review to those areas specified in the
audit scope of this report.
Respectfully submitted
KURT R. SJOBERG
State Auditor
Date:
Staff: Steven M. Hendrickson, Audit Principal
Douglas Cordiner
Paul Navarro
42
43