CSA
Summary
Read the report at California State Auditor ↗
Departments:
Many Do Not Comply With
Consultant Contract Requirements
Table of Contents
Summary S-1
Introduction 1
Chapter 1
Many Consultant Contracts
Are Sole-Sourced 5
Recommendations 12
Chapter 2
Departments Do Not Always Comply
With Legal Requirements 13
Recommendations 18
Chapter 3
DGS Did Not Ensure That All
Required Audits Were Conducted 19
Recommendations 20
Chapter 4
California State University:
Deficiencies In Awarding and
Managing Consultant Contracts 21
Recommendations 25
Responses to the Audit
Business, Transportation and Housing Agency 27
California Community Colleges,
Chancellor’s Office 29
Department of Corrections 31
California State Auditor’s Comments
on the Response by the
Department of Corrections 35
Department of Developmental Services 37
California State Auditor’s Comments
on the Response by the
Department of Developmental Services39
Department of Education 41
Employment Development Department 43
California State Auditor’s Comments
on the Response by the
Employment Development Department4 5
Department of Health Services 47
Department of Mental Health 53
Department of Motor Vehicles 55
Department of Rehabilitation 57
Department of Social Services 59
State and Consumer Services Agency 61
Stephen P. Teale Data Center 67
California State Auditor’s Comments
on the Response by the
Stephen P. Teale Data Center 73
Transportation, Department of 75
Water Resources, Department of 77
Summary
Results in Brief
D
epartments do not always adhere to the requirements of the California Public Contract
Code and other state regulations that apply to consultant contracts. In fact, we found
significant areas of noncompliance.
Our review of 19 state departments found that:
55 percent of the 1,688 consultant contracts awarded were sole source;
Not all consultant contracts provide adequate documentation to justify the cost of
sole-sourcing;
Several departments’ annual reports for consulting contracts failed to disclose required
information, such as the type of bidding used or the justification for sole-sourcing;
Certain departments did not always adhere to legal requirements for consultant contracts,
such as approval prior to commencement of work, reviewing credentials of potential
contractors, and providing contractor evaluations after completion of work; and
Faithful performance bonds were not always obtained from contractors as required for certain
electronic data processing (EDP) or telecommunication goods and service contracts.
Further, the Department of General Services (DGS) did not ensure that departments complete
internal audits of their contracting programs and submit reports to DGS as required.
Finally, we found that California State University (CSU):
Is deficient in complying with its own requirements to provide adequate documentation to
justify contracts exempt from competitive bidding;
Does not always obtain approval before the contractor starts work; and
Does not provide adequate guidance in its State University Administrative Manual to ensure
that campuses award and manage contracts in the best interest of the State.
Specifically, we reviewed 19 state departments’ annual reports of their consultant contracts and
found that some failed to indicate the type of bidding used for certain contracts. The annual
reports did not always meet the requirement to identify sole-source contracts. In addition, 8
departments either did not submit a fiscal year 1993-94 annual report, as required, or submitted it
late to DGS.
A total of 12 sole-source contracts in our sample from 6 departments did not have adequate
documentation to justify the contract costs. We also found that 23 contracts from
12 departments did not have the necessary approval before work began.
Eight departments failed to review prior evaluations of contractors before approving 22 contracts
in our sample. Six departments did not prepare prompt post-evaluations for 6 of the contracts
reviewed. Two departments failed to obtain performance bonds from contractors when making
progress payments on certain types of contracts for EDP or telecommunication goods and
services.
Finally, DGS did not ensure that two departments met all of the conditions to retain the
contracting authority that was delegated to them.
DGS is responsible for providing administrative oversight of state departments entering into
consultant contracts to ensure they comply with applicable state laws and regulations. However,
DGS is not responsible for providing this type of administrative oversight to CSU.
We reviewed four contracts at CSU that were not competitively bid. None of the contracts
contained sufficient evidence to indicate that they were exempt from the competitive bidding
requirements. Further, one of the four did not have the necessary approval before contract work
began.
Recommendations
State departments should:
Obtain required approvals before a contractor begins work to ensure they do not expose the
State to potential financial liability for work performed if the contract is not approved;
Document that a review of the contractor’s prior evaluation was performed to ensure that
new contracts are not awarded to contractors whose prior work for the State was substandard;
Complete evaluations of contractor performance promptly so that information about
contractor performance and contract usefulness can be reviewed before other contracts are
awarded; and
Secure a performance bond when making progress payments on contracts for EDP or
telecommunication goods and services that are not suitable for sale to others to ensure the
State is protected from potential loss;
The Department of General Services should:
Re-emphasize the requirements of Section 10359 of the California Public Contract Code to
ensure that state departments provide all of the information required in their annual report of
consultant contracts;
Require departments to provide sufficient documentation to justify the costs of all
sole-source contracts before they are approved; and
Ensure that departments submit internal audit reports of contracting programs by the due
dates specified by DGS.
California State University should:
Comply with the requirements in the State University Administrative Manual regarding
adequate justification on contracts exempt from competitive bidding requirements to ensure
that state funds are protected from misuse and to stimulate competition in a manner
conducive to sound fiscal practices;
Submit contracts to the appropriate CSU officials in time for contracts to be reviewed and
approved before work is begun; and
Re-evaluate and improve its guidelines for contracting included in its State University
Administrative Manual.
Agency Comments
In its response to this report, the DGS states that it has a firm commitment to provide efficient
and effective oversight of the State’s consultant contracting program. As a part of its continuing
efforts to improve policies over this program, the DGS will take appropriate actions to address
the issues presented in the report.
Twelve of the 19 departments whose contracts we reviewed also responded to this report. The
Chancellor of the California State University also provided a response to the report. These
departments and the California State University generally concur with the findings and
recommendations of the report and have agreed to take corrective action.
Introduction
T
he State Administrative Manual, Section 1280, specifies that a consultant contract calls for
a product of the mind, rather than the use of mechanical skills, and may include anything
from providing answers to specific questions to the design of a system or conducting
seminars, workshops, and conferences. This section also identifies certain types of contracts
that do not fit into the consultant category, including contracts between state agencies and the
federal government, contracts with local agencies, and contracts for architectural and engineering
services. The California Public Contract Code, Section 10356, describes consultant contracts as
providing services of an advisory nature, such as providing a recommended course of action.
Consultant contracts usually result in the delivery of a report that is related to the governmental
functions of state agency administration and management. Consultant contracts are obtained by
awarding a procurement-type contract, a grant, or any other form of payment for services of the
above type.
California law places additional requirements on state departments when using consultant
contracts. For example, departments must prepare an annual report on their consultant
contracts, disclosing the amount of each contract, the method of bidding, the reasons for any
sole-source consultant contracts, and other information. In addition, consultant service
contractors are explicitly prohibited from rendering services before the contract is approved,
unlike other contractors who must only be notified they are at risk.
The California Public Contract Code and the State Administrative Manual establish basic
guidelines and procedures that state contracting and oversight agencies and departments must
follow when entering into or approving consultant contracts. For example, departments must
comply with requirements for advertising the availability of contracts, soliciting bids from
potential contractors, evaluating the bids, writing the contracts in conformity with state
requirements, obtaining the appropriate approvals, approving payment for services, and
completing an evaluation when the contract is completed.
The California Public Contract Code generally assigns to the Department of General Services
(DGS) the duty of reviewing and approving contracts entered into by state departments for
consultant services. Although the law assigns these duties to DGS, the State Administrative
Manual generally exempts consultant contracts under $15,000.
In addition to its responsibilities for ensuring compliance with legal provisions for each contract
submitted for its approval, DGS has broader oversight responsibilities. For example, its Office
of Legal Services is responsible for developing the standard contracting procedures contained in
the State Administrative Manual. These procedures are designed to aid public officials in the
efficient and, to the maximum extent possible, uniform administration of public contracting for
consultant services. In addition, DGS periodically performs management audits of contracting
units in other state departments. DGS also maintains a central depository of negative contractor
evaluations and makes them available to other departments upon request.
DGS, however, does not provide oversight responsibility for the contracting program of
California State University (CSU), nor does it review or approve its contracts. Because of a
change in law effective January 1994, CSU is no longer required to submit consultant contracts
worth more than $100,000 to DGS for review and approval. Instead, CSU’s Chancellor’s Office
provides contract management guidance to its campuses as directed in Sections 2400 and 2500 of
its State University Administrative Manual, which generally mirrors requirements in the State
Administrative Manual. However, we noted several deficiencies within the State University
Administrative Manual that we discuss in Chapter 4 of this report.
Scope and Methodology
This audit fulfills the fiscal year 1993-94 requirements of Chapter 1044, Statutes of 1990.
These statutes require the Office of the Auditor General to evaluate the State's compliance with
state laws and regulations for consultant contracts annually. The Bureau of State Audits
assumed the responsibility for these audits pursuant to the Government Code, Section 8546.8.
To evaluate the State's compliance with the laws and policies governing consultant contracts, we
reviewed the California Public Contract Code and the State Administrative Manual and
identified the provisions and policies pertaining to this type of contract. We determined
compliance with these laws and policies by reviewing consulting contracts at 19 state
departments. The 19 departments entered into a total of 1,688 consultant service contracts
during 1993-94 totaling approximately $91.2 million. We reviewed some of these contracts for
appropriate contract language and provisions, supporting documentation, and approvals. We
reviewed both contracts departments had classified as consultant services and other services to
determine if the departments had appropriately classified the contracts.
We reviewed the California Public Contract Code and the State Administrative Manual and
identified those provisions and policies applicable to sole-source contracts. We also interviewed
department personnel to identify additional policies for approving sole-source contracts. We
examined sole-source contracts (55 percent of total consultant contracts reported for the year) at
19 state departments and assessed the propriety of approval and cost justification.
To determine whether DGS had fulfilled its responsibilities to oversee state departments with
delegated authority to purchase consultant services, we reviewed the California Public Contract
Code and the State Administrative Manual and identified provisions and policies applicable to
this delegated authority. Further, we obtained status reports of the state departments’ internal
audits from DGS and determined the timeliness of the internal audits as of the date of our review.
To evaluate CSU’s compliance with the laws and policies governing the use of sole-source
contracts, we reviewed the State University Administrative Manual and identified the provisions
and policies pertaining to entering into and approving sole-source contracts. We determined
compliance with these policies by reviewing four sole-source consultant contracts and examining
approvals and justifications for using sole-source contracts.
Finally, to determine if the campuses had adequate guidance to enable them to conduct
contracting practices that are in the best interest of the State, we compared the policies and
guidelines for consultant contracts in the State University Administrative Manual to the policies
in the State Administrative Manual.
Blank page inserted for reproduction purposes only.
Chapter 1
Many Consultant Contracts
Are Sole-Sourced
Chapter Summary
The California Public Contract Code and the State Administrative Manual permit the limited use
of sole-source contracts, which are exempt from competitive bidding and, frequently, advertising
requirements. At the 19 departments we visited, 55 percent of the 1,688 consultant contracts
awarded were sole-source. The departments cited a variety of reasons for using a sole-source
for the contract. The most commonly cited reason was that the contract required specialized
services from the contractor.
Each year state departments are required to prepare a report of consultant contracts, indicating
the type of bidding used for each contract. In this report, the departments are to identify the
sole-source contracts entered into during the year along with an explanation of why only one
vendor was considered to provide the required services. We found that state departments do not
always comply with these reporting requirements. Specifically, some departments did not
clearly disclose the type of bidding used for each contract, and other departments did not clearly
indicate why some contracts were sole-source.
The California Public Contract Code allows the Department of General Services (DGS) to
establish conditions under which a contract may be awarded without competition. One such
condition is that the departments justify the appropriateness or reasonableness of the cost of a
sole-source contract. This condition is included in the State Administrative Manual. We found
that 12 of the 74 sole-source contracts we reviewed did not contain adequate documentation to
justify the cost.
Reasons for Sole-source Contracting
The California Public Contract Code and the State Administrative Manual permit the limited use
of sole-source contracts, which are exempt from competitive bidding and, frequently, advertising
requirements. The following are examples of contracts exempt by the State Administrative
Manual:
Contracts solely for obtaining expert witnesses for litigation;
Contracts for legal defense, legal advice, or legal services;
Contracts that can only be performed by a public entity as defined in the State's
Unemployment Insurance Code;
Contracts with auxiliary organizations of California State University (CSU) or the California
Community Colleges or with a foundation organized to support the Board of Governors of
the California Community Colleges;
Proprietary software contracts; and
Medical care services with physicians, local community hospitals, and medical groups.
Figure 1 shows the California Public Contract Code's provisions for allowing sole-source
contracting.
The California Public Contract Code, Sections 10373 and 10380, also allows DGS to establish
additional conditions under which a contract may be awarded without competition. Figure 2
depicts these additional conditions.
Finally, the State Administrative Manual, Section 1236, requires
state departments to justify to DGS the appropriateness or
Departments are required reasonableness of the costs of contracts awarded without
to justify the cost of all competition. Specifically, the manual indicates that the following
sole-source contracts.
factors will be used in determining whether costs are justified: cost
information in sufficient detail to support and justify the contract;
cost information for similar services, with differences noted and
explained; and special factors affecting the costs under the contract.
Figure 1
Criteria for Sole-source Contracting
California Public Contract Code
Section 10373
A contract can only be awarded without a minimum
of three bids when it meets one of the following
criteria:
- In cases of emergency when a contract is
necessary for the immediate preservation of the
public health, welfare, safety, or protection of
state property;
- When the department awarding the contract has
advertised the contract in the California State
Contracts Register and has solicited all potential
contractors known to the department but has
received less than three bids or proposals; and
- When the contract is with another state
department or with a local government entity.
Figure 2
Additional Criteria for Sole-source
Contracting Prescribed by DGS
DGS agrees there is only a single source for
the services and approves a request for
exemption from competitive bidding.
The director of DGS determines that the
State's best interests are better served by
exempting a contract from competitive
bidding.
As Table 1 on page 10 indicates, the 19 departments we selected for review reported that 1,688
consultant contracts were entered into during the fiscal year. Of these, 924 (55 percent) were
sole-source contracts. Departments use sole-source contracting for a variety of reasons.
However, as Figure 3 indicates, they frequently use similar justifications. For example, 29 of
the 74 sole-source contracts (39 percent) we reviewed were justified as specialized services that
could only be provided by one contractor. In addition, 17 of the 74 sole-source contracts
(23 percent) were successfully justified on the basis that services rendered were for expert
witnesses for litigation, legal defense, legal advice, or legal services. The State Administrative
Manual specifically exempts contracts for obtaining expert witnesses for litigation, legal defense,
legal advice, or legal services from competitive bidding requirements.
Figure 3
Reasons for Sole-source
Contracting
Another common
Expert Witness, Legal
Other
justification for Services
9%
23%
sole-source contracting
was prior experience
with a particular project
Continuation of
Proprietary Software
that made the contractor Project/Prior Experience
Contracts
uniquely qualified to 7% 22%
continue. For 16 of the
74 sole-source contracts
(22 percent) we
reviewed, the reason
Specialized Services
used to justify
39%
sole-source contracting
was the contractor’s
prior experience or continuation of prior services.
Failure to Comply With
Reporting Requirements
The California Public Contract Code, Section 10359, requires each state department to prepare
an annual report that lists the consultant contracts it has entered during the fiscal year and the
type of bidding
used for each contract. State departments are also required to identify those contracts that were
not competitively bid and indicate why the contracts were sole-source.
As Table 1 indicates, 5 of the 19 departments did not disclose in
their annual reports the type of bidding entered into for certain
consultant contracts. For example, of the 100 consultant contracts
Departments do not that the Department of Developmental Services entered into during
always comply with fiscal year 1993-94, the department did not indicate the type of
reporting
bidding used for 80 contracts. Furthermore, 3 of the 19
requirements.
departments that did indicate the type of bidding used for their
consultant contracts did not provide justification for 26 sole-source
contracts. For example, of the 49 sole-source consultant contracts
DGS entered into during the fiscal year, it did not indicate why 24 were sole-source awards.
If departments do not disclose the type of bidding used for each contract or the reason for using
sole-source contracts in their annual reports, the State cannot be assured that departments are
using the most effective type of bidding or that contracts awarded without competition are in the
best interest of the State.
Lack of Cost Justification
Departments did not always provide adequate documentation to justify the costs of sole-source
contracts. We reviewed 99 consultant contracts for fiscal year 1993-94 at 19 departments. As
Table 2 below indicates, 74 were sole-source contracts, and the departments did not have
sufficient documentation to justify the costs for 12 of them.
The State Administrative Manual, Section 1236, requires departments to justify the
appropriateness or reasonableness of the costs of all sole-source contracts. In spite of this, 10 of
the 12 sole-source contracts that lacked cost justification were approved by DGS. The
remaining 2 contracts were exempt from DGS approval and were approved by officials within
the contracting departments.
Table 1
Consulting Contracts Entered Into
During Fiscal Year 1993-94 as
Reported by Departments Reviewed
Total Number of
Number Number of Contracts
of Number of Sole-source With Type
Consultant Contracts Contracts of Bidding
Contracts Reported as Lacking an Not
Departments Reported Sole-Source Explanation Disclosed
California Community Colleges,
Chancellor's Office 16 10
Conservation, Department of 12 4
Corrections, Department of 19 12 1
Developmental Services,
Department of 100 15 80
Education, Department of 476 33* 1
Employment Development 18 12
Department
Franchise Tax Board 12 9
General Services,
Department of 154 49 24 1
Health Services, Department of 19 16
Health & Welfare Data Center 1 1
Justice, Department of 392 392
Mental Health, Department of 36 29 2
Motor Vehicles, Department of 7 4
Rehabilitation, Department of 1
Social Services, Department of 55 25
State Controller’s Office 7 3 2
Stephen P. Teale Data Center 5 5
Transportation, Department of 322 282
Water Resources, Department of 29 23 1
Total 1,688 924 26 91
Note: The information in this table is based on the departments’ annual consultant contract reports.
The information reflects data reported for contracts entered into during fiscal year 1993-94
only and excludes amended and completed contracts that were entered into in prior years.
We did not audit the accuracy of the departments’ reports.
* The Department of Education did not provide a list that clearly identified its sole-source contracts
for fiscal year 1993-94. As a result, we estimated the number of sole-source contracts based on
information provided to us by the department’s contract manager.
Table 2
Lack of Cost Justification for
Sole-source Contracts
Lack of Cost
* The 11 contracts reviewed at the
Number Number of Justification
Board of Governors includes 6
of Sole-source for
sole-source contracts which we
Contracts Contracts Sole-source
reviewed only for compliance with
Departments Reviewed Reviewed Contracts
laws and policies applicable to
sole-source contracts.
California Community Colleges,
Chancellor’s Office 11* 10 4
Conservation, Department of 5 3 2
Conclusion
Corrections, Department of 5 3 1
Developmental Services,
Department of 5 4
The 19 departments we
Education, Department of 5 3
reviewed used sole-source
Employment Development
contracting approximately Department 5 2
Franchise Tax Board 5 4
55 percent of the time.
General Services, Department of 8 6 1
Similar justifications for
Health Services, Department of 8 7
using sole-source contracts Health & Welfare Data Center 1 1
Justice, Department of 5 5
were often used. The most
Mental Health, Department of 5 5 3
commonly used
Motor Vehicles, Department of 5 4
justifications were: Rehabilitation, Department of 1
Social Services, Department of 5 3
State Controller’s Office 5 3 1
The contract required Stephen P. Teale Data Center 5 5
specialized services; Transportation, Department of 5 2
Water Resources,
Department of 5 4
The contract was for
Total 99 74 12
expert witnesses for
litigation, legal defense, legal advice, or legal services; or
The contractor had prior experience.
We found that some departments failed to prepare annual reports on consultant contracts that
include information on the type of bidding, which ones are sole-source, and an explanation for
considering only one contractor, all required by the California Public Contract Code. In
addition, we found that departments did not always provide adequate documentation to justify
the costs of sole-source contracts as required. If departments do not sufficiently justify the
appropriateness or reasonableness of the costs of contracts that are awarded without competition,
the State could be paying more for services than necessary.
Recommendations
DGS should re-emphasize the requirements of Section 10359 of the California Public Contract
Code to ensure that departments clearly identify in their annual reports on consulting contracts
the type of bidding entered into for all consultant contracts and explain why only one contractor
was considered for each sole-source contract.
To ensure that the costs of sole-source contracts are adequately justified, DGS should require
departments to provide sufficient documentation before they are approved.
Chapter 2
Departments Do Not Always Comply
With Legal Requirements
Chapter Summary
W
e found that certain state departments did not always adhere to legal requirements for
reviewing and approving consulting contracts. Specifically, some departments failed
to comply with the requirements that: contracts be approved before work is begun;
contracting departments review prior evaluations of contractors being considered for new
contracts and review resumes of persons expected to perform contract work; departments prepare
contractor evaluations within 60 days of the completion of the contract; and annual reports be
submitted promptly to the Department of General Services (DGS). Table 3 on page 14 lists the
19 state departments at which we reviewed consultant contracts and indicates the areas of
noncompliance that apply to each.
We also found that certain state departments failed to comply with the requirement for obtaining
performance bonds when making progress payments on some contracts for electronic data
processing (EDP) or telecommunication goods and services.
Lack of Contract Approval
Before Start of Work
Of the 93 contracts we reviewed, 23 were not approved before contract work began. Of these
23 contracts, 17 did not have the required approval by DGS before contract work began. The
remaining 6 contracts were exempt from DGS approval but did not have the appropriate
department personnel approval before the contractor began work. For example, 3 of the 5
contracts reviewed at the Department of Justice did not have the required approval before work
began. In fact, one of the 3 contracts was approved more than four months after the contractor
began work. In addition, at the Department of Corrections, a contract was approved more
than six months late and one contract at the Employment Development Department was
approved almost seven months after services began.
Table 3
Noncompliance With Requirements
for Consultant Contracts
No Review No Review
Lack of of Post- of Resumes No Annual
Number Dollar Approval Evaluation Before Report or
of Amount of Before Before Contract Late Report
Contracts Contracts Start of Contract Approval Post- Submitted
Departments Reviewed Reviewed Work Approval Evaluations Late
California Community Colleges,
Chancellor’s Office 5 $ 698,275 2 1
Conservation, Department of 5 725,245 3 3 3
Corrections, Department of 5 421,374 1 1
Developmental Services,
Department of 5 1,494,908 2 1
Education, Department of 5 252,500 1
Employment Development
Department 5 838,277 2 1
Franchise Tax Board 5 1,195,415 1 1
General Services, Department of 8 385,340 1 2
Health Services, Department of 8 892,470 1 3 3 1 1
Health & Welfare Data Center 1 3,283,500
Justice, Department of 5 39,100 3 5 1 1
Mental Health, Department of 5 1,287,763 1 1 1
Motor Vehicles, Department of 5 604,247 2 1
Rehabilitation, Department of 1 100,000
Social Services, Department of 5 128,965 2
State Controller’s Office 5 497,000
Stephen P. Teale Data Center 5 900,790 3 1
Transportation, Department of 5 780,095 5
Water Resources,
Department of 5 8,415,000 2 1
Total 93 $22,940,264 23 22 6 6 8
The State Administrative Manual, Section 1215, requires DGS approval for all contracts worth
more than $15,000. In addition, the California Public Contract Code, Section 10371(d), and the
State Administrative Manual, Section 1209, require that, except in an emergency, work on a
consultant contract not be started before DGS or appropriate contracting department personnel
grant formal approval. In this context, Section 10371(d) defines an emergency as a situation in
which the use of contracted services appears to be reasonably necessary, but, as determined by
DGS, time does not allow prior formal approval of the contract. Section 10360 is more
emphatic in defining the effective date of consulting services, stating that all consultant contracts
are of no effect unless and until approved by DGS.
The Bureau of State Audits reported this weakness for fiscal years 1991-92 and 1992-93, and the
Office of the Auditor General has reported similar findings about the State's administration of all
types of contracts for several years.
By not ensuring that contracts are approved before services begin, departments cannot be assured
that state interests are protected. For example, a department’s failure to obtain contract approval
before the contractor begins work exposes the State to potential financial liability for work
performed if the contract is never approved.
Failure To Review Contractor
Evaluations and Resumes and
Late Preparation of Post-Evaluations
Some state departments fail to comply with requirements to review prior evaluations of
contractors being considered for new contracts and to review resumes of persons expected to
perform the work.
As Table 3 on page 14 indicates, 8 of the 19 departments we
reviewed did not consistently comply with statutory requirements
Departments failed to
to review contractor evaluations on file with DGS. Specifically,
review post-evaluations
the departments failed to review post-evaluations for 22 of the
for 22 of the 93 contracts
93 contracts reviewed. Two of the 8 departments had not
reviewed.
reviewed post-evaluations for any of the contracts reviewed. For
example, neither the Department of Transportation nor the
Department of Justice could provide us evidence that they had
looked at evaluations on any of the 5 contracts we reviewed in each department. When negative
evaluations are not reviewed, contracts may be approved even though prior work performed by
that contractor was substandard.
The California Public Contract Code, Section 10371(e), and the State Administrative Manual,
Section 1281, require that no consultant service contractor be awarded a contract totaling $5,000
or more unless the state department has reviewed any contractor evaluation on file with DGS and
has required, as part of the contract, a completed resume for each participant who will exercise a
major role in the completion of the contract. In addition, DGS
must notify departments seeking approval of a proposed contract within ten working days of any
negative evaluations in its files of a previous contract or contracts completed by this contractor.
The California Public Contract Code, Section 10369, and the State Administrative Manual,
Section 1283, also require each department to complete within 60 days of the end of the contract
a post-evaluation of each consultant contract totaling $5,000 or more. Negative evaluations are
to be submitted to DGS, which must keep copies on file for 36 months. DGS acts as the central
depository for all state agencies making negative evaluations or needing information on a
contractor's negative performance record with the State. The California Public Contract Code,
Section 10371(h), states that DGS must restrict or terminate the authority of a state department to
enter into consultant contracts if that department has consistently avoided the proper preparation,
retention, or submission of post-evaluations.
We also found that departments often do not prepare evaluations of
contractors’ performance promptly. Six of the 19 departments
Six of 19 departments did failed to complete all contractor evaluations within 60 days of
not complete all contractor contract completion. Evaluations help to protect the interests of
evaluations within the
the State in awarding contracts. A post-evaluation assesses the
required time limit.
contractor's performance in conducting the work or delivering the
services specified in the contract, evaluates the contract’s
usefulness, and provides state departments with information to
determine whether a potential contractor has satisfactorily completed previous state contracts.
Missing and Late
Annual Reports
The California Public Contract Code, Section 10359, requires each state department to prepare
an annual report that, among other things, lists the consultant contracts the department entered
into during the fiscal year. Copies of the report are to be submitted within 30 working days after
the end of the fiscal year to DGS, several other state departments, and legislative committees.
However, some state departments failed to comply with this requirement. For example, as
shown on Table 3 (page 14), 8 of the 19 state departments we reviewed either did not submit an
annual report or submitted it late.
Lack of Performance Bonds
Some departments did not always comply with the requirement to obtain performance bonds
from contractors when making progress payments on certain types of contracts for EDP or
telecommunication goods and services. The California Public
Contract Code, Section 12112, states that contracts for EDP or
telecommunication goods and services that are manufactured or
Certain EDP contracts
performed especially for the State and not suitable for sale to
require faithful
others may provide for progress payments if the following two
performance bonds.
conditions are met:
A department must withhold not less than 10 percent of the
contract price until final delivery and acceptance of the goods
or services; and
The contractor must submit a bond in a sum not less than one-half of the total amount
payable under the contract, securing faithful performance of the contract by the contractor.
Specifically, two departments failed to obtain a faithful performance bond from the contractor
for four of the ten contracts reviewed in those departments. Specifically, three out of the five
contracts reviewed at the Teale Data Center and one of the five contracts reviewed at the
Department of Developmental Services were for either EDP or telecommunication goods and
services and met the criteria for requiring performance bonds. However, the departments failed
to obtain faithful performance bonds on the four contracts.
Failure to obtain faithful performance bonds on EDP or telecommunication goods and service
contracts exposes the State to potential losses that could be substantial when contracting for these
types of goods and services.
Conclusion
State departments are not consistently complying with certain legal requirements for consulting
contracts. We found that some departments did not have all contracts approved before work
began, exposing the State to potential financial liability if the contract was not approved. We
also found that some departments did not review prior evaluations or resumes of contractors
being considered for new contracts. Contractors whose prior work for the State was substandard
could be awarded additional contracts.
In addition, state departments were deficient in completing timely contractor evaluations and in
preparing annual reports. Timely evaluations ensure that contractors have satisfactorily
performed the work and provide assessment on the usefulness of the contract.
Finally, two departments did not comply with the requirements for obtaining performance bonds
when making progress payments on certain types of contracts. Performance bonds protect the
State from potential losses on contracts for goods or services not suitable for sale to others.
Recommendation
To ensure that they do not expose the State to potential financial liability for work performed if
the contract is not approved, state departments should ensure that their consultant contractors do
not perform work or provide services before the contract is approved.
To ensure that contracts are not awarded to contractors whose prior work for the State was
substandard, departments should document that a review of the contractor’s prior evaluation was
performed.
To ensure that a contractor has satisfactorily completed a contract and to assess whether a
contract was useful and delivered the services called for, departments should complete contractor
evaluations promptly.
To protect the State from potential substantial losses on contracts for EDP or telecommunication
goods and services that are not suitable for sale to others, departments should secure a
performance bond when making progress payments on these types of contracts.
Chapter 3
DGS Did Not Ensure That All
Required Audits Were Conducted
Chapter Summary
T
he Department of General Services (DGS) oversees the contracting practices of all state
departments. As part of this responsibility, DGS is able to delegate contracting authority
to those departments that it determines capable of the effective use of such authority.
Departments with delegated contracting authority may conduct the entire procurement process,
including final contract approval for competitive acquisitions of goods and services.
We found that DGS did not ensure that two departments met all of the conditions to retain the
contracting authority that has been delegated to them. For departments to retain the contracting
authority delegated by DGS, the California Public Contract Code requires departments to submit
copies of audit reports to DGS. The California Public Contract Code also states that delegated
authority may be withdrawn at any time if DGS finds that the department is not in compliance
with the conditions that accompany the delegated authority.
Two Departments Did Not Submit
Their Audit Reports, As Required
In a departure from control procedures over the State’s contracting process, the DGS did not
ensure that two departments conduct an internal audit of their contracting activity and report the
results of the audit to DGS as required by the California Public Contract Code, Section 10364.
This section states that DGS may exempt departments from the requirement that it approve their
consulting services contracts under $50,000. However, to retain the exemption, state
departments must fulfill all of the requirements of Section 10364, including conducting an audit
of their contracting program every two years and reporting the results to DGS. The California
Public Contract Code, Section 10365, requires DGS to conduct a quality control review of these
internal audits.
As of April 1995, DGS issued delegation authority for consulting contracts under $50,000 to
eight departments. However, two of the eight departments, the Departments of Food and
Agriculture and Pesticide Regulation, had not completed their internal audits and submitted a
copy of the audit report to DGS by March 31, 1994, the date specified by DGS. In June 1995,
after the end of our field work, DGS received the internal audit reports from both departments.
DGS cannot be assured that state departments are exercising effective use of delegated purchase
authority or procuring consulting contracts in the best interest of the State if the required audits
of the contracting programs are not conducted and submitted to DGS timely.
Recommendations
To ensure that departments are exercising the authority to purchase consulting services
effectively, DGS should promptly follow-up with those departments that have not submitted
their internal audit reports.
Chapter 4
California State University:
Deficiencies in Awarding and
Managing Consultant Contracts
Chapter Summary
W
e reviewed four sole-source contracts at a California State University (CSU) campus
and found the campus failed to comply with certain requirements of the State
University Administrative Manual. For example, none of the four contracts contained
evidence that they were exempt from the competitive bidding requirements in the State
University Administrative Manual, nor did the contracts contain a justification for only
considering a sole-source for services or a statement explaining why the State’s interests were
better served by approving a sole-source contract. In addition, one of the four contracts did not
have the appropriate approval before the contractor started work.
As part of our review, we compared the policies and guidelines for consulting contracts in the
State University Administrative Manual to the policies in the State Administrative Manual to
determine if the campuses had adequate guidance to conduct contracting practices in the best
interest of the State. We concluded that the State University Administrative Manual does not
provide guidance in several areas that in our view are important to ensure the campuses are
awarding and managing contracts in a prudent manner. For example, this manual does not
require CSU to justify the costs of sole-source contracts. However, the manual does require
CSU to provide information in sufficient detail to justify the approval of a sole-source for
services or a statement explaining why the State’s interests are better served by an exemption
from competitive bidding.
Except for specified types of contracts that require the CSU Chancellor’s Office’s approval, such
as sole-source contracts over $100,000, the State University Administrative Manual does not
require that CSU contract amendments be in writing. One of the four contracts we reviewed
was amended, but there was no documented evidence of the amendment in the contract file.
The manual also does not require the review of negative contractor evaluations prior to awarding
new contracts. Finally, the manual does not require campuses to prepare an annual report of
their consulting contracts identifying the type of bidding used and the sole-source contracts
entered into during the year.
Background
CSU is not required to comply with sections of the California
Public Contract Code that apply to consultant contracts. Instead,
it complies with the policies and procedures of its State University
CSU is not required to
Administrative Manual. Generally, the State University
comply with the Public
Administrative Manual policies and guidelines mirror those of the
Contract Code for
consultant contracts. State Administrative Manual. However, we found certain
sections of the State University Administrative Manual related to
awarding and managing contracts were deficient when compared
to the laws and policies in the California Public Contract Code and
State Administrative Manual governing other state departments.
Before January 1994, the Department of General Services’ (DGS) oversight responsibility for
CSU was to review and approve contracts of $100,000 or more. As of January 1994, CSU is no
longer required to submit any of its contracts to DGS. CSU’s Chancellor’s Office does,
however, require the campuses to submit contracts not competitively bid and worth $100,000 or
more, as well as other specific types of contracts, to its office for review and approval.
Lack of Sole-Source Justification
and Appropriate Contract Approval
We reviewed four sole-source contracts entered into during the calendar year at one CSU
campus. The campus could not provide evidence that any of the four contracts were exempt
from competitive bidding requirements in the State University Administrative Manual, nor did
the contract file contain a justification for restricting the selection to a sole-source, or an
explanation why the State’s interests were better served by approving a sole-source contract.
The State University Administrative Manual, Section 2530, provides a list of the types of
contracts that are exempt from competitive bidding requirements. For example:
Cases of emergency where a contract is necessary for the immediate preservation of public
health, welfare or safety, or protection of state property;
To obtain expert witnesses for litigation; and
When the campus has determined there is but a single source for the service or an exemption
is in the best interest of the State.
To receive approval for a sole-source contract, the campus must explain why there is but a single
source for the service or why the State’s interests are better served by the exemption.
Without sufficient justification for the use of sole-source contracts, CSU could be restricting
competition for contracts. Because the State University Administrative Manual does not require
campuses to justify the costs of sole-source contracts, the State could be paying more for services
than necessary, and the services rendered may not be the best available.
The State University Administrative Manual, Section 2510.03, requires that work shall not
commence until the contract has been approved by the appropriate authority, except in cases of
emergency to protect human life or state property. However, one of the four contracts we
reviewed was not approved before the contractor started work. CSU’s failure to obtain contract
approval before the contractor begins work exposes the State to potential financial liability for
work performed if the contract is never approved.
Inadequate Guidance in the State
University Administrative Manual
We reviewed the policies and guidelines in the State University Administrative Manual for
consulting contracts and compared them to the policies in the State Administrative Manual to
determine if the campuses had adequate guidance to conduct contracting in the best interest of
the State. We concluded that the State University Administrative Manual is deficient in several
important areas that in our view would aid the campuses in awarding and managing contracts in
a prudent manner.
Except for specified types of contracts that require the CSU
Chancellor’s Office’s approval, such as sole-source over $100,000,
The State University the State University Administrative Manual does not require that
Manual does not require CSU contract amendments be in writing. The scope of work for
written
one of the four contracts we reviewed was changed without any
contract amendments.
written amendment. A letter from the contractor indicated that a
change in the scope of work occurred. Furthermore, a campus
official admitted that she verbally agreed to a change in the
contract performance requirements. However, the contract file did not contain a written
amendment authorizing the change to the contract.
Prudent business practices require that contract amendments be in writing. By not requiring
this, CSU may not be clear on the terms and conditions of any new agreement it has established
with the contractor. This in turn could expose CSU to financial losses by paying for contract
work never performed.
The State University Administrative Manual also does not require
that campuses review negative contractor evaluations prior to the
The University Manual awarding of new contracts. This could result in CSU contracting
also does not require with parties whose prior performance was substandard. By way
review of negative of comparison, the State Administrative Manual requires that no
contractor
consultant contractor be awarded a contract totaling $5,000 or
evaluations.
more unless the department has reviewed any negative contractor
evaluation on file with DGS.
Finally, the State University Administrative Manual does not
require campuses to prepare a report of consulting contracts
entered into during the year. As a result, oversight of campus
contracting practices by the Chancellor’s Office is limited. For
example, the Chancellor’s Office cannot determine whether the
number of contracts awarded without competition is reasonable or
justified, or whether campuses are contracting with firms or
individuals whose prior work was substandard. As discussed in
Chapter 1, state laws and regulations require other departments to prepare an annual report that
includes a list of the consultant contracts entered into during the fiscal year, identifies all
sole-source contracts entered into, and indicates the type of bidding used for other consultant
contracts.
Conclusion
Although the State University Administrative Manual does not require that campuses justify the
costs, the manual does require justification for the use of sole-source contracts. However, the
CSU campus we reviewed failed to comply with this requirement. In addition, CSU did not
always comply with the requirement to obtain contract approval before work started. Finally,
CSU does not provide adequate guidance in its State University Administrative Manual to help
ensure the campuses are awarding and managing contracts in the best interest of the State.
Recommendations
To ensure that state funds are protected from misuse, to stimulate competition in a manner
conducive to sound state fiscal practices, and to avoid favoritism, fraud, and corruption in the
awarding of state contracts, CSU should comply with the requirements in the State University
Administrative Manual regarding adequate justification of contracts that are exempt from
competitive bidding requirements.
Further, CSU should obtain approval of contracts before the contractor begins work.
Finally, to ensure that CSU campuses have sufficient guidance when procuring consultant
services, CSU should address the deficiencies in its State University Administrative Manual.
We conducted this review under the authority vested in the state auditor by Section 8543 et seq.
of the California Government Code and according to generally accepted governmental auditing
standards. We limited our review to those areas specified in the audit scope of this report.
Respectfully submitted,
KURT R. SJOBERG
State Auditor
Date: September 12, 1995
Staff: Steve Hendrickson, Audit Principal
Debbie Meador, CPA
Rupi Singh, CPA
Patrick Adams
William Anderson
Blank page inserted for reproduction purposes only.