CSA
Summary
Read the report at California State Auditor ↗
State Architect: Contracting Practices
Need Improvement
March 1995
94024
Table of Contents
Summary S-1
Introduction 1
Chapter 1
The State Architect Did Not Always
Comply With State Requirements When
Procuring Architectural, Engineering,
Construction, and Other Services 5
Recommendations 16
Chapter 2
State Laws and Regulations Give the
State Architect Broad Discretion To
Manage a Major Construction Project 19
Appendix
Funding Sources for Architectural and
Engineering Expenditures for the Demolition
of the Ahmanson Building and Construction
of the New Museum Facility 33
Response to the Audit
Department of General Services 35
California State Auditor’s Comments
on the Response From the
Department of General Services 43
Summary
Results in Brief
The Division of the State Architect (DSA) within the
Department of General Services is partially responsible for
the design and construction of state facilities (capital outlay
program). Under the capital outlay program, the DSA is
responsible for designing a project, selecting architectural
and engineering consultants, bidding and awarding
construction contracts, supervising and inspecting
construction, preparing the project budget, and managing
the overall project. To carry out its responsibility, the DSA
awards three types of contracts—architectural and
engineering contracts, construction contracts, and
contracts for retainer services.
Our review focused on whether the DSA complied with the
state contracting laws and regulations in awarding its
contracts. Additionally, the DSA was responsible for a
major construction project that involved the seismic
upgrading of the Armory and Ahmanson buildings owned
by the California Museum of Science and Industry (CMSI).
We reviewed whether the DSA followed the appropriate
building codes and consulted with the required advisory
boards before making decisions that resulted in the
demolition of a major building. Specifically, we noted the
following:
The DSA awarded $1.2 million of new work by simply
amending ongoing contracts rather than taking the
steps necessary to award this work through a
competitive process.
The DSA did not always prepare independent estimates
before it negotiated fees with its consultant contractors.
1
It awarded one contract for a project manager without
properly advertising for it.
The DSA did not obtain the required approvals before
some consultant contractors performed services for a
contract.
It did not always obtain approvals when it exceeded its
sole source and delegated authority limits for some of
its contracts.
Even though the Legislature, in Chapter 757, Statutes
of 1992, directed that both the Ahmanson and the
Armory buildings be replaced, the CMSI and the DSA
intended to replace the Ahmanson building and leave
the Armory building. However, according to the state
architect, it was appropriate to use the funds only for
construction of the Ahmanson building because the
CMSI was replacing the two original CMSI buildings
with one that equalled the size of both.
The state architect recommended that the CMSI employ
the more restrictive Field Act codes as the design
standards for the CMSI project. The CMSI agreed with
the DSA’s recommendation and approved the use of
the more restrictive codes. However, according to an
opinion of the Legislative Counsel, the building
standards of the Field Act do not apply to the
construction of the new museum at the CMSI and,
instead, the CMSI should use building standards under
the California State Building Standards Code.
Further, even though cost estimates were based on the
use of the Field Act standards, the DSA took the
necessary steps to obtain a cost comparison and
recommended the reconstruction of an expanded
museum based on the lower of the cost estimates.
As required, the CMSI consulted with two historical
boards before submitting the budget package for the
new museum to the Department of Finance.
The DSA used the funds of the Earthquake Safety and
Rehabilitation Bond Act of 1990 to pay for expenditures
that, according to the state architect, were a necessary
and integral part of the new museum facility.
2
Recommendations
The DSA should take full advantage of the benefits that are
realized when contract work is awarded through a
competitive process. Before simply adding significant new
work to existing contracts, the DSA should thoroughly
assess whether or not it would be more prudent to seek
competitive bids or proposals first.
To ensure that it receives a fair and reasonable price, the
DSA should prepare an estimate of services before
negotiations and not rely on the consultant contractor’s cost
proposals.
To ensure that it does not limit competition in selecting its
consultant contractors, the DSA should advertise all
contracts in the California Contracts Register and through
publications of professional societies.
To ensure that it does not expose the State to potential
financial liability for work performed if the contract is not
approved, the DSA should take the following steps:
Ensure that its consultant contractors do not perform
work or provide services before the DSA obtains
approvals for its contracts; and
Require its consultant contractors to submit invoices
that include specific service dates.
Agency Comments
In its response, the DGS states that it will take appropriate
actions to address our recommendations. However, the
DSA also responds that it disagrees with some of the
conclusions of our report. For example, the DSA contends
that its decisions to amend existing contracts, instead of
performing a new selection process, were in the best
interest of the State. In addition, the DSA disagreed that it
exposed the State to potential monetary liability when its
consultant contractors started work before the contract was
approved.
3
4
Blank page inserted for reproduction purposes only.
5
Introduction
T
he Department of General Services (DGS) is
responsible for planning, acquiring, designing,
constructing, maintaining, and operating state-owned
facilities for state offices and employees. Until fiscal
year 1986-87, the DGS' Office of the State Architect (OSA)
had overall responsibility for the design and construction of
state facilities (capital outlay program). Under the capital
outlay program, the OSA was responsible for designing a
project, selecting architectural and engineering consultants,
bidding and awarding construction contracts, supervising
and inspecting construction, preparing the project budget,
and managing the overall project schedule.
During 1986, the DGS reorganized project management
responsibilities. It did so by combining the long-range
planning and environmental review function of the Office of
Facilities Planning and Development with the project
management activities of the OSA. The DGS planned to
combine these functions into a newly formed Office of
Project Development and Management (OPDM) by
gradually shifting the project management responsibilities
from the OSA to the OPDM. However, the DGS has only
partially accomplished this shift, and the OSA and OPDM
continue to share responsibility for administering the State's
capital outlay program.
In July 1993, to improve services for its clients, the OSA
reorganized. The OSA became the Division of the State
Architect (DSA) comprising three offices: Office of Design
Services, Office of Construction Services, and Office of
Regulation Services. Each of the three offices has a chief
who reports directly to the state architect on operational
and technical issues. The Office of Design Services is
responsible for managing the design of new projects,
overseeing improvements to existing facilities, and
managing special programs such as seismic and toxic
6
programs. The Office of Construction Services manages
and inspects state building and correctional projects
performed by contract and ensures that the construction
conforms with approved plans and specifications. The
Office of Regulation Services is responsible for plan
checking and inspection services, particularly those
aspects of a project involving structural safety, access for
the handicapped, and fire and life safety for state buildings
and public schools.
To fulfill its responsibilities, the DSA typically awards three
types of contracts. These are architectural and
engineering contracts, construction contracts, and
contracts for retainer services. From July 1992 through
October 1994, the DSA awarded approximately
$174 million for contracts.
Scope and Methodology
The Budget Act of 1994 (budget act) required the Bureau of
State Audits to conduct a management review of the DSA
to evaluate the degree to which the state architect provides
oversight, coordination, and leadership in meeting the
State's property management goals. More specifically, the
budget act required us to review whether the DSA complies
with the California Government Code and the Public
Contract Code for awarding work related to state
construction projects. In addition, the budget act required
us to determine whether the DSA complies with the
requirements for the participation of minority-, women-, and
disabled veteran-owned business enterprises in state
contracts. Further, the budget act requires us to review
whether the DSA coordinates with local government
development plans.
We reviewed laws, regulations, and the DSA’s procedure
manuals, and we interviewed DSA and other staff of the
DGS to identify the degree to which the state architect
provides oversight, coordination, and leadership in meeting
the State's property management goals. Our review
indicated that the DGS has not assigned the DSA any
significant property management responsibilities. Instead,
the OPDM and the Office of Real Estate and Design
Services (OREDS) share this responsibility.
7
The OPDM is responsible for planning the development of
state office facilities, forecasting future space requirements
for agencies, and initiating the first steps toward
constructing, financing, and purchasing a state building.
Additionally, the OREDS is responsible for allocating space
in state-owned and leased office buildings, negotiating
leases, selecting and acquiring real estate, maintaining the
statewide property inventory, and managing state property.
The DSA's role within the DGS is to provide architectural,
engineering, and construction services to state
departments and agencies for the design and construction
of buildings and other facilities. Therefore, our review is
limited to the DSA's administration of contracts related to
the architectural services it provides.
To determine whether the DSA complies with the California
Government Code and the Public Contract Code for
awarding work related to state construction projects, we
reviewed the state laws, regulations, and departmental
policies and procedures related to contracts for
construction, architectural and engineering services, and
construction project management. In addition, for
comparison purposes, we obtained the contracting policies
and procedures for both architectural and engineering
services and construction contracts of the California
Department of Transportation. We determined the DSA's
compliance with these laws and policies by reviewing
contracts for architectural and engineering services,
retainer contracts, and contracts for construction that the
department awarded from July 1, 1992, through October
31, 1994. Because we reviewed contracts related to the
California Museum of Science and Industry (CMSI) project,
we also reviewed one contract that the DSA awarded in
June 1991.
To review whether the DSA complies with the requirements
for the participation of minority-, women-, and disabled
veteran-owned business enterprises, using the previously
selected sample of contracts, we assessed whether the
DSA either is meeting the participation goals or can
document that it is making a good faith effort to meet them.
To determine whether the DSA coordinates with local
government development plans, we reviewed the laws and
8
regulations the state architect is required to follow,
interviewed DSA staff, and reviewed DSA procedures
manuals. Our review disclosed that the DSA’s
responsibilities are to provide architectural, engineering,
and construction services to state departments for the
design and construction of buildings and other facilities.
The DSA’s role does not extend to coordinating with local
government development plans. Therefore, we did no
audit work in this area.
During the audit, concerns were raised that the DSA did not
follow state contracting procedures when it awarded
contracts for the retrofitting or new construction of the
Armory and Ahmanson buildings in Exposition Park at the
CMSI in Los Angeles. To address these concerns, we
included all six contracts related to the CMSI project in our
sample of contracts. We discuss our findings related to
these contracts and others that we reviewed in Chapter 1.
Other concerns were raised regarding the use of monies
from the Earthquake Safety and Rehabilitation Bond Act of
1990 (1990 seismic bond act) to upgrade or reconstruct the
Armory and Ahmanson buildings. To address these
issues, we reviewed the DSA’s process for evaluating state
buildings, in addition to its methodology for developing the
occupancy statistics used in its evaluation.
Additional concerns were raised that, although the DSA
was directed to use the 1990 seismic bond act monies to
Many concerns have been retrofit both the Armory and Ahmanson buildings of the
voiced about the CMSI’s CMSI, the plan ultimately adopted by the DSA and the
project to build a new
CMSI intends only to use these funds to demolish the
museum facility.
Ahmanson building and replace it with a much larger
building. Other concerns focused on the proposed
demolition of two other CMSI buildings—the Mark Taper
Hall of Economics and the IMAX Theater. To address
these concerns, we reviewed the legislation that
appropriated funds for this project, reviewed the master
planning study of the Exposition Park developed for the
CMSI, interviewed the DSA staff, and reviewed the minutes
of the meetings of the Public Works Board at which the
project to construct a new museum facility was approved.
A further concern was raised that the DSA relied on an
incorrect seismic standard when it decided it would be
9
more prudent to replace rather than restore the Ahmanson
building. A related issue was that retrofitting the
Ahmanson building would be less expensive than replacing
the building. To determine whether the DSA has the
authority to determine the seismic standard to be used, we
requested an opinion from the Legislative Counsel.
Additionally, we reviewed cost estimates associated with
retrofitting versus replacing the Ahmanson building.
Finally, a concern surfaced that the DSA and the board of
the CMSI approved the demolition of the historic
Ahmanson building without sufficiently consulting with the
Office of Historic Preservation and the State Historic
Building Safety Board. To determine whether the DSA is
required to consult with these agencies, we reviewed
portions of the California Government Code, the California
Code of Regulations, and the State Historic Building Code.
Finally, we interviewed staff and reviewed documents of
the Office of Historic Preservation and the State Historic
Building Safety Board.
10
Chapter 1
The State Architect Did Not Always
Comply With State Requirements When
Procuring Architectural, Engineering,
Construction, and Other Services
Chapter Summary
W
e reviewed the Division of the State Architect's
(DSA) method of awarding contracts for designing
and constructing state facilities and found that the
DSA does not always comply with state contracting policy
when it awards these contracts. For example, for 12
amendments to architectural and engineering contracts, the
DSA added significant changes to the contracts that neither
the consultant contractors nor the DSA had contemplated
for the original contracts. By adding large additional
projects through amendments, rather than separate
contracts, the DSA has denied other firms the opportunity
to compete for more than $1.2 million awarded through
these amendments.
Additionally, we found that the DSA did not always prepare
independent estimates before it negotiated fees with its
consultant contractors. Also, the DSA awarded one
contract without proper advertising, and it did not obtain the
required approvals before some consultant contractors
performed services for their contracts. Finally, the DSA
did not adequately monitor all reimbursable costs, could not
always support its competitive process, and did not always
obtain approvals when it exceeded its sole source and
delegated authority limits.
Background
Of the three types of contracts the DSA awards, it uses
architectural and engineering contracts to obtain
architectural services, engineering services, land
surveying, or construction project management services.
11
It uses construction contracts to obtain services related to
the erection, construction, alteration, repair, or
improvement of state buildings. Lastly, the DSA awards
retainer contracts on an “on-call” basis. For example, the
DSA uses retainer contracts to hire outside expertise when
DSA employees cannot accomplish a particular portion of a
project in the time allotted for it.
When it awards construction contracts, the DSA is required
to follow the Public Contract Code, Section 10140. On the
other hand, when awarding contracts for architectural and
engineering services, the DSA follows the California
Government Code, Sections 4525 through 4529. The
essential difference in awarding a contract for architectural
and engineering services versus awarding a contract for
construction services is how the cost of the contract is
determined and at what point in the process the
qualifications of the competing consultant and construction
Different rules apply to
contractors are considered. In selecting a consultant to
each type of contract.
provide architectural and engineering services, a state
department first reviews the demonstrated competence and
professional qualifications of the candidates. Once a top
candidate is selected, the department and the candidate
attempt to reach agreement on a reasonable cost for the
contract. For construction contracts, the department also
reviews the qualifications of potential consultant
contractors, but only allows those contractors who are
deemed qualified to bid on the project. The department
then determines the lowest responsible bid from among all
bids submitted and that bid becomes the cost for the
contract.
To select a consultant to provide architectural and
engineering services, the DSA appoints a panel to
measure, using specified criteria, the qualifications
competing firms have submitted. From this initial review,
the DSA selects a number of firms and invites them to
answer questions regarding their qualifications and their
approach to the pending project. Another panel then
conducts the interviews and ranks the finalists based on
specified criteria. The California Government Code,
Section 4527, requires the DSA to identify no less than
three firms as being the most highly qualified to provide the
services the DSA requires. The government code further
requires the DSA to negotiate for a fair and reasonable
12
price with the firm that is ultimately determined to be the
most qualified. The DSA follows a similar process when it
selects consulting firms for the retainer contracts.
To determine whether the DSA was complying with all state
contracting procedures, we reviewed 60 construction,
architectural, and engineering contracts it awarded
between July 1992 and October 1994. Because we
reviewed contracts related to the California Museum of
Science and Industry (CMSI) project, we also reviewed one
contract that the DSA awarded in June 1991. We
reviewed documents related to 26 architectural and
engineering contracts, 18 retainer contracts, and 16
construction contracts. We also reviewed 70 amendments
issued for the architectural and engineering contracts, 30
amendments issued for the retainer contracts, and 52
change orders for the construction contracts.
The DSA Amended Contracts Rather
Than Using a Competitive Process
Based on our review of 70 amendments to architectural
and engineering contracts, we found 12 amendments
adding significant changes to four contracts. These 12
amendments were not envisioned for the original contracts.
The DSA originally awarded the four contracts for a total of
approximately $859,000. The 12 amendments increased
the original contracts by approximately $1.2 million. For
these 12 amendments, we believe that the DSA should
have followed the State’s competitive process and awarded
these amendments as separate contracts, rather than
simply amending the existing contracts.
One of the architectural and engineering contracts in our
sample was awarded to an architectural firm to develop a
One contract was
amended six times, master planning study of Exposition Park in the city of Los
increasing the total 179 Angeles. The DSA and the architectural firm originally
percent. negotiated a fee for this contract of approximately
$287,000. However, $513,000 was added to the cost of
the contract via six contract amendments for an increase of
approximately 179 percent. For example, the DSA
approved two amendments totaling approximately
$256,000 that required the architectural firm to prepare an
Environmental Impact Report (EIR). This increased the
13
original negotiated contract price by 89 percent. The DSA
approved two other amendments totaling approximately
$207,000 for exhibit design work and another two
amendments totaling $50,000 for a traffic study. These
four amendments increased the original contract by an
additional 89 percent. Each of the six amendments
required the architectural firm to provide entirely new and
discrete work not needed as an extension to the original
contract.
Discussions between the DSA and the architectural firm
indicated that, during the initial negotiations in April 1991,
the DSA did not plan to have the architectural firm prepare
the EIR. In fact, the DSA indicated at that time that the
EIR would be the responsibility of the Office of Planning
Development and Management (OPDM). Eventually, the
OPDM informed the DSA that it would need to obtain the
services of an outside consultant contractor to perform the
EIR. Subsequently, in December 1991, six months after
the contract between the DSA and the architectural firm
was approved, the DSA approved an amendment that
directed the architectural firm to prepare the EIR. Thus,
we concluded that it was clearly not the DSA's intent for the
architectural firm to prepare the EIR when the DSA
originally negotiated for this contract. Because the six
amendments were for three discrete projects, we believe
the DSA should have competitively bid separate contracts.
According to the state architect, the DSA chose to amend
the contract to incorporate the preparation of the EIR
because the process to select an outside consultant
contractor would have taken approximately 4 to 6 months
and would have involved the considerable efforts of its own
staff. However, the DSA first knew that an outside
consultant would be needed in May 1991, and the
architectural firm was not required to have its draft EIR
complete until 24 months later, in May 1993. In our view,
24 months would have allowed sufficient time for the DSA
to select an outside consultant through a competitive
process, while leaving enough time for the consultant to
complete the work.
14
The DSA approved two additional amendments to its
contract with the architectural firm to provide exhibit design
Amendments were for
services. Documents included in the DSA’s project file
discrete projects not
indicated that this work was beyond the original intent of
envisioned in the original
the contract. A memo dated October 7, 1991, indicates
contract.
that the DSA considered using a certain consultant
contractor on a sole source contract to perform the
additional exhibit design services. Subsequently, it chose
to amend the contract, and the architectural firm hired the
consultant contractor discussed in the memo as a
subcontractor to perform the work.
Two other contracts that we reviewed originally procured
services for the removal of asbestos at specific sites. The
DSA approved amendments to both contracts to add sites
not specified in the original contract. We believe the DSA
should have awarded the additional work through a
competitive process rather than simply amending the
contract of the existing consultant contractor. In the first
contract, the DSA required the consultant contractor to
remove asbestos at two sites at a cost of approximately
$142,000. It ultimately approved four amendments,
adding two sites and increasing the original contract cost
by approximately $225,000 or 158 percent. We believe
this amount should have been awarded through new
contracts. Similarly, the DSA approved two amendments
for the second contract that added two sites and increased
the original contract by approximately $85,000 or
123 percent.
Another contract we reviewed required a consultant
contractor to deal with groundwater contamination at Los
Alamitos Armed Forces Reserve Center. The DSA obtained
the approval of the Department of General Services (DGS)
to award the original contract as an emergency sole
source. It was given such approval with the understanding
that the work on this contract was for interim emergency
services not to exceed $750,000 until the DSA was able to
obtain the services of a long-term consultant contractor
Emergency sole source
through the normal competitive process. The DSA
approval exceeded by
eventually awarded the original contract for a total of
$398,000.
$361,000.
15
In addition to the original contract, it approved two
amendments to the contract that increased the total cost of
the contract by approximately $787,000, exceeding the
original sole source approval by approximately $398,000.
The first amendment added new work not included in the
original contract. The second amendment also added new
work and extended the time of services until
September 1995, making the duration of the contract
approximately two and one-half years. Based on the sole
source approval, the DSA’s original intention was to award
this contract using a competitive process. Instead, it
chose to avoid the competitive process by simply amending
the original sole source contract.
The California Government Code and the Public Contract
Code do not provide state agencies with specific guidance
regarding contract amendments. For example, the law
does not provide guidance regarding when it is appropriate
to amend a contract versus when it would be more
appropriate to submit the new work to a competitive
process. The DSA’s procedures for amendments state that
the DSA and the consultant contractor, by written mutual
agreement, may adjust the consultant contractor’s
compensation in a reasonable amount if the amount of
work is changed from the original agreement. While the
DSA’s procedures allow for amendments to its contracts,
there are no established guidelines for the types of contract
changes that would be considered reasonable.
To determine how other departments consider contract
changes, we reviewed the Department of Transportation’s
procedures. We found that the Department of
Transportation’s procedures state clearly that an
amendment should not materially alter the overall scope of
the contract, and for major changes, the department should
complete a new contract. The Department of
Transportation’s procedures define a scope change as any
change to the project standards, deliverables, or
milestones that the Department of Transportation and the
consultant contractor did not contemplate in the original
contract.
By adding large projects through amendments rather than
separate contracts, the DSA is foregoing the advantages of
awarding these pieces of work through a competitive
16
process. By using the State’s competitive process, the
DSA has a better opportunity to contract with the most
qualified firms and obtain the most reasonable prices. In
addition, the DSA has denied other firms the opportunity to
compete for the more than $1.2 million of new work that
was awarded through the amendments to the contracts we
reviewed.
The DSA Does Not Always Prepare
Estimates Before Negotiating Fees
The DSA did not always prepare independent estimates
before it negotiated fees with consultant contractors. An
independent estimate should provide individuals
negotiating on the State’s behalf with information to ensure
they are fully prepared to obtain a reasonable price. The
California Government Code, Section 4528, requires that
state agency heads contract with firms for architectural,
landscape architectural, engineering, and environmental
services, land surveying, or construction management
services at a fair and reasonable price. The California
Code of Regulations, Title 21, Subchapter 4, Article 2,
Section 1313, requires that before the DSA discusses fees
with a firm, the director of the DGS prepare an estimate of
the value of such services. This estimate must remain
confidential until the contract is awarded or the negotiations
are abandoned. Further, the director must not award a
contract when the total fee negotiated with the consultant
contractor would exceed the estimate by 10 percent.
We reviewed 26 architectural and engineering contracts, 18
retainer contracts, and 73 amendments to determine
Nine amendments whether the DSA prepared independent estimates before it
awarded without an negotiated fees with its consultant contractors. However,
independent estimate. we found that nine estimates were dated later than the fee
proposals the consultant contractors submitted to the DSA.
The DSA awarded the nine amendments related to these
estimates for the same amounts the consultant contractors
submitted as their fee proposals. We could not locate any
estimates for 6 amendments and 3 retainer contracts, and
one additional estimate was not dated.
When the DSA does not prepare the estimate before it
receives the consultant contractor’s cost proposal, the
17
consultant contractor may have an advantage. Without an
independent estimate, the DSA does not have guidelines to
measure the reasonableness of the consultant contractor's
cost proposal or to determine what a more reasonable
proposal might be. By determining an estimated amount,
the DSA can assess whether a consultant contractor
proposes a fair and reasonable price for services to the
State.
The DSA Did Not Advertise
as Required for One Contract
During our review of architectural and engineering
contracts, we found one contract that the DSA awarded to
a private consultant contractor without advertising. The
California Government Code, Section 4527, requires that
the DSA publish in publications of respective professional
societies statewide announcements of all projects for which
it needs to retain outside consultant contractors for
architectural and engineering services. Also, the DSA’s
own procedures require the advertisement in the California
Contracts Register of all DSA contracts of more than
$1,000.
The DSA hired a private consultant contractor to serve as a
project manager for the demolition and construction of a
state building for the CMSI. The DSA approved the
contract in October 1992 for a total of $85,000. To
continue the services of this consultant contractor beyond
the period of the original contract, the DSA has amended
the contract three times as of January 1995.
For most projects assigned to the DSA, DSA staff act as
the project managers. However, according to the state
architect, the CMSI demolition and construction project
was larger than most projects the DSA is usually assigned.
The state architect states that the DSA did not have
qualified civil service employees who could spend the
amount of time required for this project; therefore, it
obtained the services of an outside consultant contractor.
During our review of the DSA’s process to award this
contract for a project manager, we found that the DSA did
not properly advertise the contract, nor did it advertise the
18
contract in the California Contracts Register or in the
professional society publication, as required. However,
the DSA did contact a professional society, the California
Council, American Institute of Architects (AIA), which it
normally uses for advertising. The AIA provided the state
architect with a list of approximately 8 to 12 potential
consultant contractors.
The DSA’s usual method of advertising requires the
publication of the request for qualifications in the AIA
newsletter sent to its members. Instead, the executive
vice president of the AIA developed a list of potential
candidates based on discussions with the state architect
about the qualifications the state architect desired.
According to the state architect, the list was limited to
Rather than advertising,
candidates in the Los Angeles area because the CMSI
contractor was chosen
project was for a limited term and it was not realistic to
from a list of 8 to 12
provided by the American expect someone to relocate. Eventually, the state
Institute of Architects. architect narrowed the list to three individuals. From this
point on, the DSA followed its selection process and
awarded the contract to the candidate with the highest
score after a review of each of the three candidates’
qualifications.
Because the DSA did not appropriately advertise this
contract in the California Contracts Register and the
professional societies’ publications, the DSA has limited the
competitive selection process. When competition is
limited, the contracting organization reduces the likelihood
that it has obtained the most qualified consultant contractor
and reduces the possibility that it has obtained the work at
the most reasonable price.
Consultant Contractors Began Work
Before Contract Approval
The Public Contract Code, Section 10295, states that all
contracts entered into by state agencies are void unless
and until approved by the DGS. However, in seven
instances, the DSA did not obtain the required approvals
before the consultant contractors performed services for a
contract.
19
We reviewed 44 consultant contracts and the related
amendments. We found that for three contracts and four
amendments, the consultant contractor performed services
State architect suggests before obtaining the approval of the DGS. We were
that its consultant unable to determine whether the consultant contractor
contractors omit dates on provided services before contract approval for 96 of 230
invoices. invoices that we reviewed because the consultant
contractor did not include specific service dates on these
invoices. The DSA suggested to its consultant contractors
that it is preferableto omit dates and include a statement
that “the work was performed after the execution date and
within the performance period of the contract” on their
invoices.
When the consultant contractor does not include specific
service dates on its invoices, the DSA is unable to
determine whether the consultant contractor provided
services before approval of the contract or amendment. In
addition, without service dates, the DSA may not have the
information it needs to ensure there are no duplicate
billings for services. Although services may have been
provided before the approval of the contracts or
amendments, the DSA did not make any payments to the
consultant contractors until after the contracts were
approved. However, by failing to ensure that approval was
obtained before work began, the department exposed the
State to potential financial liability for work performed if the
contract or amendment had not been approved.
The DSA Did Not Adequately Monitor
All Consultant Contractors’ Reimbursable Costs
Before reimbursing its consultant contractors for "out of
pocket" expenses, the DSA has not always obtained
receipts, as required. Also, in several instances, the DSA
has over-reimbursed its consultant contractors. Because
many contracts the DSA enters into run at least several
months or, in some cases, years, the DSA usually makes
periodic progress payments to the consultant contractors.
Most of the consultant contractors submit monthly invoices
to the DSA. Before paying the invoice, someone familiar
with the work produced by the consultant is required to
review the invoice to determine the accuracy and
reasonableness. Typically, the consultants bill for their
20
services in two categories—payment for the hours spent
providing services to the DSA and reimbursement for
out-of-pocket expenses incurred while providing services to
the DSA. Typical out-of-pocket expenses include travel,
long-distance telephone calls, and photocopying. The
DSA’s instructions to consultant contractors require that the
consultants submit receipts for all reimbursable expenses
or the DSA will return the invoices to the consultants and
request that receipts be provided. Additionally, the DSA
stipulates that its consultant contractors be reimbursed for
travel expenses at no more than the same rates as for
state employees.
We found that the DSA paid three consultant contractors
for reimbursable expenses without obtaining the supporting
receipts. More specifically, the DSA paid reimbursable
expenses without supporting receipts for 12 invoices,
totaling approximately $37,000 for one consultant
Expenses of $38,650 were
paid without required. contractor; 7 invoices, totaling approximately $1,400 for a
receipts. second consultant contractor; and 4 invoices, totaling
approximately $250 for a third consultant contractor. We
also found that for 9 invoices we reviewed, the DSA paid
rates for lodging and meals that exceeded the State’s
reimbursement rates. The 9 invoices exceeded the State's
rates by a total of $231.
By not requiring that the consultant contractors always
provide receipts, the DSA may not detect inappropriate or
duplicate expenses. Additionally, because the DSA did
not adequately monitor invoices, it paid $231 more than the
amount authorized by state rules.
Inadequate Documentation
Supporting the Contracting Process
Contrary to state requirements, the DSA could not always
provide evidence that its consultant contractors had made
a good faith effort to identify subcontractors that were
qualified businesses owned by minorities, women, and
disabled veterans. The State Administrative Manual,
Section 1266, requires that a contractor provide
documentation of self-certification or good faith effort to
qualify as a minority, women, or disabled veteran/business
enterprise (M/W/DVBE). The DSA’s procedures state that
a certification obtained from the Department of
21
Transportation or the Office of Small Business and Minority
Business also is acceptable as evidence of qualification as
a M/W/DVBE. A good faith effort includes identifying
potential M/W/DVBEs, advertising in trade papers focusing
on M/W/DVBEs, and sending solicitations to potential
M/W/DVBEs with sufficient lead time to fully entertain and
consider the responding bids. In addition, the Public
Contract Code, Section 10180, requires that the DSA
award its construction contracts to the lowest responsible
bidder whose proposal complies with all guidelines.
For 2 of 16 construction contracts we reviewed, the DSA
could not provide us with documents to indicate that the
construction contractors had met the M/W/DVBE
requirements. Specifically, for one contract, the
construction contractor did not sign the self-certification.
For the second construction contract, the DSA could not
provide us with evidence that the contractor had advertised
for M/W/DVBEs.
For 3 of 16 construction contracts we reviewed, we were
unable to determine whether the DSA awarded the contract
to the proper bidder because the DSA did not maintain the
bid submittals for the construction contracts.
Exceeding Sole Source
and Delegated Authority Limits
The DSA’s procedures require that it obtain the approval of
the DGS for all architectural or engineering contracts that
exceed the DSA’s delegated authority of $300,000.
Additionally, the DSA must obtain approval from the DGS
for all sole source contracts.
We noted three instances in which the DSA amended
contracts above its delegated authority of $300,000 without
obtaining the required DGS approvals. Specifically, for
one contract, the second amendment exceeded the DSA’s
delegated authority by $55,246 and the third amendment
by an additional $12,000. The DSA did not obtain DGS
approval for either amendment. For a second contract, the
DSA exceeded its delegated authority by $45,742 when it
approved the contract’s fourth amendment. Again, the
DSA did not obtain the approval of the DGS for the fourth
22
amendment, but it did obtain approval for subsequent
amendments.
Additionally, the DSA obtained sole source approval
totaling $78,000, yet it did not obtain additional authority
when it awarded the contract and amendments for
$134,000, which is $56,000 greater than the original
approval.
Conclusion
The DSA added significant changes to existing contracts
that neither the consultant contractors nor the DSA had
contemplated for the original contract. However, it did not
competitively bid for this additional work. As a result, the
DSA has denied other firms the opportunity to compete for
more than $1.2 million awarded through 12 amendments.
Additionally, the DSA did not always prepare independent
estimates before it negotiated fees with its consultant
contractors. Also, it awarded one contract without proper
advertising. Further, the DSA did not obtain the required
approvals before some consultant contractors performed
services for a contract. Finally, the DSA did not
adequately monitor all reimbursable costs, could not
always support its competitive process, and did not always
obtain approvals when it exceeded its sole source and
delegated authority limits.
Recommendations
The DSA should begin to take full advantage of the benefits
realized when contract work is awarded through a
competitive process. Before simply adding significant new
work to existing contracts, the DSA should thoroughly
assess whether or not it would be more prudent to seek
competitive proposals.
To ensure that it receives a fair and reasonable price, the
DSA should prepare an estimate of services before
negotiations and not rely on the consultant contractor’s cost
proposals.
23
To ensure that it does not limit competition in selecting its
consultant contractors, it should advertise all contracts in
the California Contracts Register and in the publications of
professional societies.
To ensure that it does not expose the State to potential
financial liability for work performed if the contract is not
approved, the DSA should take the following steps:
Ensure that its consultant contractors do not perform
work or provide services before the DSA obtains
approvals for its contracts.
Require its consultant contractors to submit invoices
that include specific service dates.
To ensure that its expenditures for contracts are
appropriate and reasonable, the DSA should take the
following steps:
Pay for only those expenses allowed within the contract
provisions and supported by receipts.
Review invoices that it has already paid and recover all
travel costs exceeding the State’s allowable
reimbursement rates.
Review all future invoices, before payment, to ensure
that payments for travel costs do not exceed the State’s
reimbursement rates.
The DSA should ensure that it receives and retains the
documents necessary to show that a construction
contractor has met the M/W/DVBE requirements and that a
contract has been properly awarded.
The DSA should ensure that it obtains all required
approvals when it exceeds its delegated authority and sole
source limits.
24
Blank page inserted for reproduction purposes only.
25
Chapter 2
State Laws and Regulations Give the
State Architect Broad Discretion To
Manage a Major Construction Project
Chapter Summary
The Division of the State Architect (DSA) is responsible for
managing a major construction project that involves the
seismic upgrading of the Armory and Ahmanson buildings
owned by the California Museum of Science and Industry
(CMSI) and located in Exposition Park in the city of
Los Angeles. The Earthquake Safety and Rehabilitation
Bond Act of 1990 (1990 seismic bond act) requires that
eligibility for seismic upgrading of state buildings or facility
projects be based upon criteria established by the state
architect. The DSA developed a five-step process for
determining which of the State’s buildings or facilities
should be considered top priority for correction of seismic
and related fire and life safety hazards. The DSA’s
evaluation, which was completed in October 1994, placed
the Armory and Ahmanson buildings in the top 15 of 400
buildings that exhibit the highest potential risk from a
damaging earthquake.
One step in the DSA’s five-step process involved a
comparative analysis of the average number of people
using each of the buildings. The DSA acknowledged that
it would have preferred to use actual occupancy data for
these analyses, but chose not to. Instead, it chose to use
a method that inflated the attendance figures but, according
to the state architect, provided a more consistent method
by which to compare the relative populations at risk for the
various buildings.
Legislation required that approximately $39.9 million from
the 1990 seismic bond act be used for the correction of all
seismic and other fire and life safety problems identified in
both the Armory and Ahmanson buildings. However, the
26
current project, as approved by the Public Works Board in
March 1994, will replace the Ahmanson building and leave
the Armory building. According to the state architect, it
was appropriate to use the funds for construction related
only to the Ahmanson building because the DSA was
replacing the two original CMSI buildings with one much
larger building.
The state architect recommended that the CMSI employ
the more restrictive Field Act codes as the design
standards for the CMSI project. The CMSI agreed with the
DSA’s recommendation and approved the use of the more
restrictive codes. However, according to an opinion of the
Legislative Counsel, the building standards of the Field Act
do not apply to the construction of the new museum facility
at the CMSI and, instead, the building standards under the
California State Building Standards Code should apply.
Further, even though cost estimates were prepared based
on the use of the Field Act standards, the DSA took the
necessary steps to obtain a cost comparison and
recommended the reconstruction of an expanded museum
facility based on the lower cost.
As required, the CMSI consulted with two historical boards
before submitting the budget package for the museum
facility to the Department of Finance. Finally, the DSA
used the 1990 seismic bond act funds to pay for
expenditures that, according to the state architect, were a
necessary and integral part of the new museum facility.
Background
The CMSI is located in Exposition Park, a state-owned
104-acre tract just south of the central part of Los Angeles.
The Exposition Park also contains the Natural History
Museum of Los Angeles County, the California
African-American Museum, the Los Angeles Memorial
Coliseum, and the Sports Arena (a swim stadium and
recreational center) as well as open space and landscaped
areas. Until October 1990, the CMSI housed exhibits and
programs focusing on the scientific and industrial
development of the State within nine buildings located in
Exposition Park: the Aerospace Hall, Armory Building,
Hall of Health, Science Wing, Ahmanson Building, Mark
27
Taper Hall of Economics and Finance, IMAX Theater, and
California Afro-American Museum.
In October 1990, the CMSI closed the Armory and
Ahmanson buildings to the public based on the
recommendation of the state architect because the
buildings did not meet “current seismic design standards.”
According to a structural investigation and analysis
conducted by the Office of the State Architect, the Armory
and Ahmanson buildings were structurally inadequate to
resist the lateral forces of earthquakes as required by the
California Building Code. At the time, structural engineers
and the Office of the State Architect estimated renovation
costs for both buildings at a total of approximately $41.3
million.
In June 1990, before the closure of the Armory and
Ahmanson buildings, the voters of the State of California
approved the 1990 seismic bond act, which authorized
$300 million in state general obligation bonds for the
reconstruction, repair, replacement, relocation, or seismic
retrofitting of buildings owned by local governments and the
State. Additionally, the 1990 seismic bond act required
that eligibility for retrofitting, reconstruction, repair,
replacement, relocation, or other seismic hazard abatement
for state buildings or facility projects be based upon criteria
established by the state architect.
In July 1991, the governor and the Legislature appropriated
$41.3 million from the 1990 seismic bond act fund for the
correction (through repair, retrofitting, or new construction)
of all seismic and other fire and life safety problems
identified with the Armory and Ahmanson buildings.
Again, in September 1992, the governor and the
Legislature approved Chapter 757, Statutes of 1992
(Chapter 757), which reappropriated approximately
$39.9 million from the 1990 seismic bond act for the
correction of all seismic and other fire and life safety
problems identified with the Armory and Ahmanson
buildings, whether through repair or replacement, including
the cost of preliminary plans, working drawings, and
construction.
Finally, in Chapter 139, Section 1100-301-660 of the
Budget Act of 1994 (budget act), the sources of funding for
28
the CMSI project changed. In the budget act, the governor
and the Legislature approved approximately $29.4 million
from the Public Buildings Construction Fund for
construction of the new museum. However, because the
Legislature and the governor approved an alternative
source of funds for the CMSI project, Chapter 139,
Sections 1100-495, also returned to the 1990 seismic bond
act fund approximately $24.9 million of the funds originally
appropriated by Chapter 757. As of March 1995, other
than the north facade wall, the Ahmanson building has
been demolished.
We reviewed whether the DSA followed state contracting
laws and regulations when it awarded contracts related to
this major construction project; whether the DSA followed
the appropriate building codes and consulted with the
required advisory boards before making decisions that
resulted in the demolition of a major building; and whether
the DSA accurately followed the directives of the
Legislature and the governor, who placed conditions on
how this project was to proceed.
The Armory and Ahmanson
Were Eligible To Receive
Seismic Bond Monies
The 1990 seismic bond act required the DSA to establish
criteria that would be used to determine whether a state
building or facility is eligible for the 1990 seismic bond act
funds. In response, the DSA, in consultation with the
Seismic Safety Commission (commission) and its
Professional Advisory Committee, evaluated approximately
one-half of the 14,000 state buildings to determine their
susceptibility to earthquakes. According to the DSA’s
State Building Seismic Program report (seismic report), the
DSA and the commission believe that this evaluation
included all of the most significant buildings in terms of
population at risk and type of use.
29
For its evaluation, the DSA established a five-step
evaluation process. At the conclusion of each step,
buildings that exhibited the highest level of potential risk
The Armory and were forwarded to the next step for further evaluation.
Ahmanson buildings were Steps one and two of the process considered the structural
added to the eligible
characteristics of a building to identify those with major
building list in 1994.
structural deficiencies. Step three brought into the
analysis those buildings with higher populations or
functional use. Step four included a benefit cost analysis
for correcting the deficiencies for each building included in
step three. Finally, step five resulted in a list that reflects
the buildings that the DSA recommended should be
considered highest priority for retrofitting or replacement.
The DSA released its first list of state buildings it
recommended to receive 1990 seismic bond act funds in
April 1994. When the DSA developed the first list, it did
not include the Armory and Ahmanson buildings in its
five-step process. According to the state architect, the
DSA did not initially evaluate the Armory and Ahmanson
buildings because the Legislature and the governor had
already approved the allocation of seismic bond act funds
for the two buildings. In July 1991, approximately three
years before the release of the seismic report, funding had
been approved for the two buildings. Therefore, the state
architect noted, it seemed appropriate to include only those
state buildings for which there was no previous
appropriation of funds.
Subsequently, the Legislative Analyst’s Office requested
that the state architect apply the criteria it used to evaluate
other state buildings to the Armory and Ahmanson
buildings. After doing so, the DSA’s evaluation placed the
Armory and Ahmanson buildings in the top 15 of 400
buildings that exhibit the highest potential risk from a
damaging earthquake. Based on the DSA’s evaluation of
the Armory and Ahmanson buildings, they were eligible to
receive 1990 seismic bond act monies.
The DSA Used Inflated Occupancy
Figures for All Buildings
In developing the list of buildings that it considered the
highest priority for the 1990 seismic bond funds, the DSA
30
combined a ranking for the structural deficiencies in a
building from step two of its evaluation process with a
ranking for those buildings with a higher population and
functional use from step three. To determine population,
the DSA requested information from state departments
about how many people use each state building at any
given time. According to the state architect, the DSA staff
found that, in many instances, the departments’ occupancy
figures were inaccurate. As a result, the DSA staff chose
not to use the occupancy information that state agencies
provided on the questionnaires. Instead, it used a factor
called “code occupancy” to represent each building’s
occupancy level.
The DSA defines code occupancy as the gross area of a
building divided by the “occupant load factor.” The
Uniform Building Codes, Table 33-A.1, establishes
occupant load factors based on a building’s type of use and
represents the maximum number of occupants allowable in
a building. For example, the state architect classified the
Ahmanson building as an assembly area with less
concentrated use, containing exhibit rooms. Table 33-A.1
of the Uniform Building Codes establishes the occupant
load factor for the Ahmanson building based on its use as
15 square feet per occupant. When the DSA divides the
square footage of 131,783 for the Ahmanson building by
the occupant load factor of 15, the resultant figure of 8,786
represents the code occupancy for the Ahmanson building.
However, in its response to the original questionnaire, the
CMSI estimated the number of persons occupying the
building at any given time during the day as between 501
and 5,000. As this indicates, the DSA’s use of code
occupancy appears to inflate the building’s occupancy
statistics. The DSA also calculated the code occupancy of
the Armory building to be 9,896. The response to the
original questionnaire indicated that the Armory may
contain between 50 to 250 people at any given time,
significantly less than the code occupancy.
According to the state architect, using a code occupancy
factor rather than actual occupancy figures does inflate a
building’s usage. However, the DSA consistently used this
methodology for all 400 buildings it evaluated in step three
of its process, thus consistently inflating the occupancy
statistics for all buildings. According to the state architect,
31
this methodology is not perfect but is valid because it
provides a more consistent method by which to compare
the relative population at risk for the various buildings
rather than the inaccurate occupancy figures included by
state departments.
Use of Seismic Bond Funds for
the Ahmanson Building Only
Chapter 757 required that approximately $39.9 million from
the 1990 seismic bond act be used for the correction of all
seismic and other fire and life safety problems identified
with the Armory and Ahmanson buildings, whether through
repair or replacement. When asked why both buildings
are not being replaced, the state architect told us that the
specific language of Chapter 757 allowed the DSA some
latitude as to how the two buildings were to be repaired or
replaced. In the opinion of the state architect, the word
Nearly $40 million “replace,” as used in Chapter 757, did not mean that the
appropriated for two Armory and the Ahmanson buildings had to be replaced
buildings was used for one with two new buildings of the same size and square
new facility of comparable
footage. Rather, the state architect and the CMSI agreed
size.
on a plan to replace the old Armory and Ahmanson
buildings by constructing a significantly larger new museum
facility. According to the state architect, the size of the
new museum facility would be increased to equal
approximately the square footage of the two original
buildings to accommodate the loss of the exhibit space.
Also, the CMSI is currently considering a proposal to
transfer the Armory building to the Los Angeles Unified
School District.
The state architect and the CMSI proceeded with this plan,
and in February 1994, the plan was submitted for review to
the Public Works Board, as required. With a complete
description of how the old Armory and Ahmanson buildings
were to be replaced by a new and expanded museum
facility, the Public Works Board approved this project.
Along with the construction of a new and enlarged museum
facility, the CMSI had proposed that the area of the
Exposition Park housing the Armory Building and the IMAX
Theater be considered for the site of a new elementary
school. This proposal suggested that the Los Angeles
32
Unified School District, in collaboration with the CMSI and
the University of Southern California, be responsible for the
design, construction, and operation of this school. The
project, as it was approved, also called for the demolition of
the Taper Hall of Economics, a building that had been
constructed approximately 10 years ago to make room for
an expanded new museum facility.
Field Act Standards and
Reconstruction of the CMSI Buildings
The state architect recommended that the CMSI employ
the more restrictive Field Act codes as the design
standards for the CMSI project. The CMSI agreed with the
Legislative Counsel:
DSA’s recommendation and approved the use of the more
“Field Act Standards do
restrictive codes. However, according to an opinion of the
not apply.”
Legislative Counsel, the building standards of the Field Act
do not apply to the construction of the new museum facility
at the CMSI, and instead, the building standards under the
California State Building Standards Code should apply.
The state architect does not have the authority to apply the
building standards under the Field Act to the construction of
the new museum facility at the CMSI. However, the state
architect may recommend the application of the Field Act
standards, although this recommendation is advisory in
nature. To provide the CMSI with a recommendation, the
DSA considered using three different building codes. First,
the DSA considered the California Building Standards
Code, which is the normal code governing the design and
construction of all state buildings. The second code it
considered was the Field Act, which is a more restrictive
code that governs the design and construction of all public
school buildings. According to the state architect, the Field
Act increases the level of safety of design and construction
standards as compared to the California Building
Standards Codes and will generally cause more change to
the historical elements of a building. Last, the DSA
considered the California Historical Building Code, which is
a code that governs historic structures. According to the
state architect, this code will generally cause less change
to the historical elements of a building.
33
After considering these three codes, the state architect
recommended to the CMSI that it use the Field Act as the
design standards for the CMSI project. According to the
state architect, the Field Act was recommended because,
although the CMSI is not a public school, the CMSI is
routinely used in the curriculum of hundreds of public
schools as an “off campus” learning center for more than
1,000 children every school day. Therefore, the state
architect believed that it was appropriate to apply the
higher than normal code safety standards of the Field Act
to the CMSI project.
As a result, in a letter to the design architect dated
September 1992, the state architect directed that the
design of all new CMSI buildings will use the Field Act
standards. A letter dated March 1994 from the executive
director of the CMSI to the state architect indicates that the
President of the Board of Directors and the executive
director were in full agreement with the state architect’s
recommendation to design the new building using the Field
Act standards. Consequently, the design architect used
the Field Act standards when it developed the estimated
costs to renovate the Armory and Ahmanson buildings in
comparison with the costs to replace the Ahmanson
building with a new larger building.
To determine the propriety of applying the Field Act
standards to the CMSI project, we requested a legal
opinion from the Legislative Counsel. The Legislative
Counsel found that, for the purposes of the Field Act, the
CMSI buildings are not school buildings and are, therefore,
not subject to the Field Act standards. The primary
purpose of the new museum facility is to offer a museum of
science and industry for the general benefit and education
of the public. Consequently, while pupils may visit the
building as part of their school day, any educational use by
the pupils is incidental to the primary purpose of the
building. As a result, the Field Act does not apply to the
CMSI buildings and, instead, the California State Building
Standards Code governs the CMSI project.
Based on a 1993 comparison of the estimated cost to
replace the Armory and Ahmanson buildings with the
estimated cost to renovate the two buildings, the DSA
recommended that the CMSI proceed to construct a new
34
expanded museum facility. The cost estimates are based
on the application of the Field Act standards, which, as we
discussed above, should not have been applied to the
Armory and Ahmanson buildings. However, aside from
that, the DSA took the necessary steps to obtain a cost
comparison of reconstructing or renovating the buildings.
The DSA relied on a cost comparison prepared by an
architectural consultant in March 1993. The architectural
firm estimated the costs to renovate the Armory and
Ahmanson buildings at approximately $36.5 million.
However, the estimated cost to replace both buildings with
an expanded museum facility was approximately $32.9
million. The DSA recommended the replacement option,
which is estimated to cost less than renovating the
buildings.
In 1991, the DSA had used a consultant to prepare a
structural investigation and report of the Armory and
Ahmanson buildings. The consultant estimated the costs
associated with the structural retrofitting of the Armory and
Ahmanson buildings at approximately $8.4 million.
However, the consultant qualified this estimate, noting that
the calculations and the recommended modifications were
preliminary in nature and should be treated accordingly.
Furthermore, our cursory comparison of this estimate with
the March 1993 estimate confirms that the March 1993
estimate was much more comprehensive. The March
1993 estimate included the costs associated with
architectural, mechanical, electrical, plumbing, handicap
accessibility, heating, ventilation, air conditioning, museum
planning layout, and other costs that make the buildings
habitable. The 1991 estimate did not address all of these
costs.
The DSA Consulted With
the Required Historical Boards
We have concluded that, as required, the state architect
and the CMSI consulted with the State Historic
Preservation Officer (SHPO) and the State Historic Building
Safety Board (historical board) before submitting the
budget package for the new museum facility to the
Department of Finance.
35
Various state laws require that state agencies consult with
the SHPO and the historical board before proposing to
demolish a building designated as historic. The SHPO
determined that the Ahmanson building is a qualified
historical building since it is eligible for listing on the
National Register of Historic Places.
Early in the planning processes, the Public Resources
Code, Section 5024.5, requires state agencies to first give
notice and a summary of the proposed action before
altering the original or significant historical features or fabric
of a building, or before transferring, relocating, or
demolishing historical resources on the master list
maintained by the SHPO. The SHPO has 30 days after
receipt of the notice and summary for review and comment.
Similarly, Section 8878.50(b) of the Government Code
requires that if a state building or facility is designated as a
historic building, the state architect consult with the SHPO
before proposing to demolish the building or facility. The
State Administrative Manual requires the state agency that
owns the historic building to notify the SHPO before it
submits its capital outlay budget package for the project to
the Department of Finance. Finally, the Health and Safety
Code, Section 18961, requires that all state agencies
acting or making decisions on variances or appeals that
affect historical buildings consult with the historical board to
obtain its review.
Our review of correspondence and interviews with staff at
the Office of Historic Preservation and the DSA disclosed
that the acting SHPO first requested an opportunity to
comment on an early draft of the master plan for Exposition
Park on August 12, 1992. On January 4, 1993, the CMSI
sent a letter to the acting SHPO to confirm a meeting and
to “formally notify the State Office of Historic Preservation
that pursuant to Section 5024.5 of the Public Resources
Code, this meeting will serve as the initiation of the
consultation process for the Exposition Park Master Plan
and any changes to structures within the Park, including,
but not limited to, the Armory and Ahmanson buildings.” In
our view, this event marked the beginning of the
consultation process between the project sponsors, that is,
the state architect, the CMSI, and the SHPO.
36
Consultation on this project continued when, in May 1993,
the SHPO and the historical board were given 45 days to
review and comment on a copy of the draft Environmental
Impact Report (EIR) for the CMSI. The draft EIR
addressed both the general impact of the master planning
study and the specific impact of individual development
projects, especially the demolition and reconstruction of the
new museum facility. Correspondence from the SHPO,
dated September 1993, indicated that the DSA and the
CMSI responded in part to concerns raised by the SHPO
by adopting some modifications that partially preserved the
Ahmanson Building as compared with the original proposal.
However, correspondence from the historical board
indicated dissatisfaction.
In August 1993, the DSA submitted the budget package for
the new museum facility to the Department of Finance.
Subsequently, in February 1994, the DSA submitted the
preliminary plans for Phase I of the new museum facility to
the Public Works Board for its approval. Phase 1 included
incorporating the renovated historic facade of the
Ahmanson building. The Public Works Board decided in
the February meeting to hold over a decision regarding the
preliminary plans until its March meeting to allow the
historical board and the SHPO additional time to discuss
their concerns with the DSA and the CMSI. According to
the minutes of the Public Works Board meeting for March
4, 1994, it was satisfied that discussions or “consultation”
between the various interest groups had occurred, and it
approved the preliminary plans by a vote of 3 to 0.
Since the March 1994 Public Works Board meeting, we
found evidence that the CMSI and the DSA have continued
to consult with the SHPO. In a letter dated May 16, 1994,
the SHPO continues to urge the CMSI to retain other
portions of the Ahmanson building. However, the SHPO
did state that upon receipt and review of detailed drawings
documenting the proposed changes in the final design, she
was prepared to conclude her consultation on this project.
1990 Seismic Bond Act
Expenditures Were Allowable
37
As part of our review of expenditures, we tested whether
1990 seismic bond act funds were used to fund the
planning or design of exhibits. We found that the act’s
funds were used to pay the CMSI’s architect to integrate
into the new museum facility exhibits that had been
previously designed using other funds. According to the
state architect, these expenditures were a necessary and
integral part of the new museum facility.
The 1990 seismic bond act, Section 8878.55(a)(1),
specifies that appropriations made from these funds be
used to finance the costs of retrofitting, reconstructing,
repairing, replacing, or relocating state buildings or facilities
that are seismically unsafe or have other safety
deficiencies. For these projects, allowable costs include
the cost of abating falling hazards; the cost of engineering,
architectural, financial, and legal services; the cost of
preparing plans, specifications, studies, surveys, and
estimates; administrative expenses; the cost of land
acquisition for replacement projects, direct construction, or
rehabilitation; and the costs necessary or incidental to the
project.
We reviewed the expenditures approved by the DSA
related to the six contracts the DSA awarded between June
1991 and October 1994 for the CMSI project. The
appendix presents a general description of the types of
services the DSA acquired through these contracts using
the 1990 seismic bond act funds. We found that the DSA
approved expenditures for such items as the design and
development of food service programming, architectural
and engineering services to incorporate the exhibit design
elements into the new museum facility, the design and
development of the new museum security system, and the
architectural and engineering services to integrate security
and telecommunication into the new museum. According
to the state architect, the use of the 1990 seismic bond act
funds for these types of expenditures was appropriate
since these expenditures were necessary and an integral
part of the new museum facility. Also, the state architect
stated that the funds were used merely to incorporate the
elements of the exhibits and the food services into the new
museum facility and were not used for the actual design
and development of the exhibits. Similarly, the funds were
also used for the planning of the programmatic needs of
38
the basic security and voice communication system so they
also may be properly incorporated into the new museum
facility.
Conclusion
To comply with the 1990 seismic bond act, the DSA
developed a five-step process for determining which of the
State’s buildings or facilities should be considered top
priority for correction of seismic and related fire and life
safety hazards. The DSA’s evaluation placed the Armory
and Ahmanson buildings of the CMSI in the top 15 of 400
state buildings that exhibit the highest potential risk from a
damaging earthquake. During one step of its evaluation,
which requires that the DSA perform a comparative
analysis of the average attendance for the various state
buildings, the DSA chose to use a method that inflated
attendance figures. According to the state architect, this
method provided more consistent information by which to
compare the relative populations at risk for the various
buildings.
Even though the current project will replace the Ahmanson
building and leave the Armory building, legislation indicated
that funds appropriated for this project should be used for
both the Ahmanson and Armory buildings. However,
according to the state architect, it was appropriate to use
the funds for construction related only to the Ahmanson
building because the DSA was replacing the two original
CMSI buildings with one building equal to the two smaller
ones.
Additionally, the state architect recommended that the
CMSI employ the more restrictive Field Act codes as the
design standard for the CMSI project. However, according
to an opinion of the Legislative Counsel, the building
standards of the Field Act do not apply. Also, based on a
1993 comparison of the estimated cost to replace the
Armory and Ahmanson buildings with the estimated cost to
renovate the two buildings, the DSA recommended that the
CMSI proceed to construct an expanded Ahmanson
building, based on a lower cost. As required, the CMSI
consulted with two historical boards before submitting the
budget package for the new museum facility to the
39
Department of Finance. Finally, the DSA used the 1990
seismic bond act funds to pay for expenditures that,
according to the state architect, were expenditures that
were a necessary and integral part of the new museum
facility.
40
We conducted this review under the authority vested in the
state auditor by Section 8543 et seq. of the California
Government Code and according to generally accepted
governmental auditing standards. We limited our review to
those areas specified in the audit scope of this report.
Respectfully submitted,
KURT R. SJOBERG
State Auditor
Date: March 30, 1995
Staff: Steve Hendrickson, Audit Principal
Denise L. Vose, CPA
Tammy Bowles, CPA
Regina Harmonson
Kevin Malm
1
Blank page inserted for reproduction purposes
only.
2
Appendix
Funding Sources for Architectural and
Engineering Expenditures for the Demolition
of the Ahmanson Building and Construction
of the New Museum Facility
Amount of Contract or
Amendment and Its
Related Funding Source
Exposition
Seismic Park
Description of Bond Act Improvemen
Expenditure of 1990 t
Fund
Preparation of complete architectural
drawings for all phases of design and
development $2,576,300 $ 486,118
Design and development of food
service programming for the new
museum facility 29,700
Design and development of energy
saving technology 25,000
Design and development of the new
museum’s security and
telecomunications systems 14,000
Architectural, engineering, and
consulting services to accommodate
the retention of the north wall and roof
elements 147,476
Food service design services and
consultation on relocating the
McDonalds restaurant to the west
side of the first floor of the museum 73,388
Architectural and engineering
services for a thermal energy storage 59,219
system
Architectural and engineering
3
Amount of Contract or
Amendment and Its
Related Funding Source
Exposition
Seismic Park
Description of Bond Act Improvemen
Expenditure of 1990 t
Fund
services for off-site electrical
improvements in coordination with the
local utility company 24,550
Analyze and design parking facilities,
landscaping, lighting, etc. for
Exposition Park 249,860
Architectural and engineering
services to integrate the security and
telecommunication elements into the
new museum facility 43,200
Architectural and engineering
services to incorporate the exhibit
design elements into the new 144,000
museum facility
Structural and architectural
coordination required to integrate the
Hoberman Art Piece into the museum 12,000
atrium space
Geological survey of the subsurface
soil on the new museum site 21,000
Environmental impact report and
traffic study for the Exposition Park as 306,040
a whole
Development of the master plan,
including the conceptual exhibit
program, for CMSI 559,465
Boundary survey and mapping of the
new museum 110,100
Consultant project managing services 243,900
Total $3,829,873 $1,295,443
4
5