CSA
Summary
Read the report at California State Auditor ↗
Summary
T
his is the fourth report in a series of annual reports that
we are required to submit by Chapter 16 of the Statutes
of 1990. The 1989 Transportation Blueprint Legislation
(Transportation Blueprint) contains provisions increasing
transportation taxes, fees, and bond proceeds and requires
the State to allocate and spend these increased revenues
(blueprint revenue) on specified transportation programs.
Based on our review for fiscal year 1994-95, we found that
although half of the ten-year Transportation Blueprint period
has elapsed, the total revenues and expenditures are less
than half of the total amounts anticipated by the legislation.
Furthermore, we found that the revenue sources provided by
the Transportation Blueprint may not produce the total
revenue of $18.5 billion anticipated by the legislation. The
potential shortfall includes $2 billion due to voters turning
down two $1 billion bond issues. Additionally, if fuel tax and
vehicle weight fee revenue collections continue for the next
five years at the same rate as collections for fiscal year
1994-95, there will be an additional shortfall of approximately
$1.4 billion for a total shortfall of approximately $3.4 billion.
We also found that the projects we examined are included in
the specified transportation programs and adhere to statutory
requirements for their respective programs. Furthermore, the
California Transportation Commission (commission) allocated
the blueprint revenue in accordance with applicable program
statutes and guidelines. Further, the State spent the
blueprint revenue in accordance with statutory requirements
and correctly calculated its formula-based disbursements of
these funds to cities and counties. Included in the allocations
and expenditures were state matching and exchange funds
authorized by the Streets and Highways Code,
Sections 182.6(g) and (h) and 182.9. These sections do not
specify whether blueprint revenues or other state revenues
are to be used for the match and exchange.
Background
In 1989, the Legislature and the governor approved
Chapters 105, 106, and 108 of the Statutes of 1989. These
statutes contain various provisions for generating an
estimated increase of $18.5 billion in revenue for designated
transportation programs over a ten-year period beginning in
fiscal year 1990-91. However, the voters turned down two of
three bond acts proposed by Chapter 108, reducing the
amount of the estimated increase in blueprint revenue to
$16.5 billion. In June 1990, California voters approved
Proposition 111 (the Traffic Congestion Relief and Spending
Limitation Act of 1990) and Proposition 108 (the Passenger
Rail and Clean Air Bond Act of 1990). These two
propositions increased fuel taxes and commercial weight fees
and authorized the State to raise $1 billion in bond proceeds
by amending various transportation-related sections of the
Government Code, the Revenue and Taxation Code, the
Streets and Highways Code, and miscellaneous other codes.
The codes, as amended by these two propositions and
Chapters 105, 106, and 108 of the Statutes of 1989, and as
subsequently amended, are collectively referred to in this
report as the Transportation Blueprint.
The Transportation Blueprint specifies the sources that will
generate the blueprint revenues for the State to allocate and
expend for transportation programs. Table 1 shows the
sources of these funds and the estimated amounts expected
from each source.
Table 1
Estimated Blueprint Revenue
by Source (in Thousands)
Estimated
Amount of
Source of Revenue Revenue
Fuel taxes $13,000,000
Sales and use taxes 500,000
Commercial weight fees 2,000,000
Rail bond proceeds 3,000,000
Total $18,500,000
Source: The California Transportation Commission’s 1994 Annual
Report.
In addition to generating revenue for transportation projects,
the Transportation Blueprint requires the State to expend the
revenue only on specified programs. The appendix to this
report provides a brief description of these programs.
The State Transportation Improvement Program (STIP)
covers a seven-year period and includes all major
transportation projects to which the commission intends to
allocate funds during the period. Section 14529 of the
Government Code requires the commission to adopt the STIP
every two years. When the commission adopts the STIP, it
represents an intent to allocate transportation funds to specific
projects in the adopted program. The Transportation
Blueprint specifies certain factors, such as geographic areas,
designated highways and rail corridors, and types of projects
that the commission may approve for allocations of the
blueprint revenue.
After the commission allocates funds to the projects in the
STIP, the Department of Transportation (department) spends
the funds on the adopted transportation projects. The
department’s expenditures include payments for costs that it
has incurred for transportation projects, as well as payments
to local governments for reimbursements of costs the local
government incurred for transportation projects.
In addition to the department’s expenditures, the
Transportation Blueprint requires the State Controller’s Office
to disburse a portion of the blueprint revenue to cities and
counties in accordance with formulas prescribed by state law.
The State Controller’s Office calculates the amounts of these
disbursements and distributes them to cities and counties.
Scope and Methodology
The Government Code, Section 14525.6, requires the Office
of the Auditor General to perform an annual review of the
State’s allocation and expenditure of the funds generated by
the Transportation Blueprint. According to Section 8546.8 of
the code, the Bureau of State Audits is responsible for the
activities formerly performed by the Office of the Auditor
General.
During our review for fiscal year 1994-95, we evaluated the
policies, procedures, and guidelines that the commission and
the department developed for the allocation and expenditure
of the revenue generated by the Transportation Blueprint.
We found these policies and procedures appropriate and
adequate to comply with the requirements of the
Transportation Blueprint. We also reviewed the
commission’s allocations for transportation projects to
determine if the commission allocated the blueprint revenues
for the programs specified by
the Transportation Blueprint. In addition, we reviewed the
department’s expenditures for a sample of transportation
projects covered by the Transportation Blueprint to determine
if the projects meet legislated program requirements. We
also reviewed the distributions of the blueprint revenues that
the State Controller’s Office made to cities and counties.
Further, we determined the total amount of blueprint revenue
collected each year since the passage of the legislation and
the annual amount of these revenues state agencies
expended or distributed for each of the various Transportation
Blueprint programs.
Allocations and Expenditures Meet
Statutory Requirements
We reviewed 65 transportation projects for which the
commission allocated blueprint revenue when it was
required and for which the department expended blueprint
revenue in fiscal year 1994-95. These projects are included
in Transportation Blueprint programs such as the Flexible
Congestion Relief, Traffic Systems Management, and Intercity
Rail Programs. Based on our review, we determined that the
commission and the department complied with the
requirements of the Transportation Blueprint. For example,
we found that each of the four Flexible Congestion Relief
projects that we reviewed would reasonably be expected to
reduce or avoid congestion by increasing the capacity of the
transportation system as required by legislation. Additionally,
each of the five Traffic Systems Management projects that we
reviewed is for traffic operations control systems, such as
television surveillance systems, turn lanes, traffic signals, and
high-occupancy vehicle lanes, as required by legislation.
Further, the 15 Intercity Rail, Interregional Road System, and
Commuter and Urban Rail Transit Program projects that we
reviewed are located on highways and rail corridors that
legislation specifies for these programs.
In addition to reviewing the commission’s allocations for
specific projects, we verified the commission’s calculations of
the minimum level of total project funding that the commission
must allocate to each county based on “North/South” split
legislation. Specifically, the “North/South” split legislation
requires the commission to allocate 40 percent of the total
estimated program funding to northern California counties and
60 percent to southern California counties. The commission
calculates the minimum levels for each county based on the
county’s population and the total road miles in the county.
We found that the commission calculated these levels
correctly.
Total Transportation Blueprint
Revenues and Expenditures
Are Less Than Expected
As shown in Table 2, the amount of blueprint revenue
generated in the first five years of the ten-year period of
the Transportation Blueprint is approximately $7 billion.
This amount is approximately 38 percent of the Transportation
Blueprint estimate of $18.5 billion. However, voters rejected
two of the three $1 billion rail bond issues proposed in the
Transportation Blueprint. In addition to this $2 billion, if the
volume of fuel sold in the remaining five years of the program
remains at fiscal year 1994-95 levels, there will be a further
revenue shortfall of approximately $800 million. Also, if
commercial weight fee revenue remains constant at fiscal
year 1994-95 levels for the next five years, there will be a
further revenue shortfall of approximately $600 million,
resulting in a total shortfall from these two revenue sources of
approximately $1.4 billion. The potential shortfall from these
three sources could be approximately $3.4 billion.
Table 2
Comparison of Estimated to Actual
Revenue Collected Under the
Transportation Blueprint
(in Thousands)
Source of Funds
Sales Commercial Rail Bond Total
Fuel Taxes and Weight Proceedsa Revenue
Use Tax Fees
Fiscal Year
1990-91b $ 690,277 $ 31,530 $ 120,182 $ 43,800 $ 885,789
1991-92 957,840 39,735 118,726 465,300 1,581,601
1992-93 1,106,771 46,175 131,997 15,000 1,299,943
1993-94 1,260,054 52,677 134,438 169,000 1,616,169
1994-95 1,358,346 55,937 141,135 121,000 1,676,418
Blueprint Revenue
Collected $ 5,373,288 $226,054 $ 646,478 $ 814,100 $ 7,059,920
Remaining Blueprint
Revenue to Be
Collected 7,626,712 273,946 1,353,522 2,185,900 11,440,080
Estimated Blueprint
Revenue by $13,000,000 $500,000 $ 2,000,000 $3,000,000 $18,500,000
Sourcec
Percentage of
Revenue
Collected Through 41.33% 45.21% 32.32% 27.14% 38.16%
Fiscal Year 1994-95
a Although the Transportation Blueprint estimated that $3 billion would be raised with three
separate $1 billion rail bond issues, voters approved only one of the three rail bond issues placed
on the ballot.
b Annual revenues as reported by the department and the Board of Equalization.
c Source: California Transportation Commission’s 1994 Annual Report.
The blueprint revenue collected for the five-year period,
beginning with fiscal year 1990-91 and ending with fiscal year
1994-95, is less than 50 percent of the anticipated collections
if each of the revenue sources generated constant annual
amounts over the ten-year period of the Transportation
Blueprint. However, the annual revenue amounts are not
constant. For example, as shown in Table 2, the major
source of revenue
is fuel taxes. The Transportation Blueprint increased fuel
taxes by nine cents per gallon in increments over the
period from August 1990 to January 1994. Specifically, the
tax increased by five cents per gallon in 1990 and by one cent
per gallon in each of the next four years. Therefore, fuel tax
revenue will be less in the first five years than in the last
five years of the Transportation Blueprint. Another reason
that revenue is less than 50 percent is that the Transportation
Blueprint contains provisions for a two-step increase in
commercial weight fees. The first increase took effect in
June 1990 and the second in January 1995.
Table 3 presents the total amount of blueprint revenue that
the Transportation Blueprint estimated the State would
expend on each of the transportation programs over the
ten-year period of the Transportation Blueprint. The
Transportation Blueprint recognizes that this estimate was the
best available at the time of the legislation and, in a changing
environment such as California, that periodic reviews and
revisions would be necessary. Since the passage of the
Transportation Blueprint, certain events have changed the
revenue basis established by the legislation and new
legislation changed the Transportation Blueprint itself. For
example, as previously discussed, revenue and bond
proceeds may be as much as $3.4 billion less than the
original Transportation Blueprint estimate. Additionally, as
discussed later, new legislation requires the department to
use funds appropriated for the Traffic Systems Management
program for matching federal funds for certain projects.
Table 3 also shows the amount of actual expenditures
incurred and commitments to expend (obligations) for each of
the Transportation Blueprint programs for the first five years of
the ten-year period. As shown in the table, the State
expended approximately 35 percent of the $18.5 billion of
expenditures estimated by the Transportation Blueprint. The
table also shows that there is considerable variance between
programs in the rate of expenditures and obligations.
However, the legislation does not require proportionate
expenditure rates among programs nor does it require
expenditures for individual programs to be in equal amounts
each year of the ten-year period.
According to the executive director of the commission, these
variances are due to the priorities the commission establishes
for the projects in the STIP. The commission sets a higher
priority within STIPs for older projects and allocates funds
to projects only when they are ready for construction. The
projects included in the 1988 STIP, therefore, have a higher
priority than projects added in the 1990 and later STIPs which
were adopted subsequent to the Transportation Blueprint.
Furthermore, according to the executive director, it takes an
average of five years to complete environmental studies,
engineering work, right-of-way acquisition, and interagency
permit agreements to get a typical major transportation
improvement project ready for construction and,
consequently,
Table 3
Actual Five-Year Expenditures and Obligations of
Blueprint Revenue Compared to the Transportation
Blueprint’s Estimated Ten-Year Total Expenditures by Program
(In Thousands)
Percent of
Ten-Year
Estimated
Streets Ten-Year Expenditure
and Estimated s
Annual Expenditures by Fiscal Yearb
Highways Expenditure Through
Program Code Amounta 1990-91 1991-92 1992-93 1993-94 Total Fiscal Year
Section 1994-95 1994-95
1988 STIP shortfall 164(d)(1) $ 3,500,000 $393,641 $ 498,544 $ 547,565 $ 502,628 $ 172,392 $2,114,770 60.42%
Intercity Rail and Commuter and Urban
Rail Transit 164(d)(2) 3,000,000c 43,100 442,592 299,915 158,499 52,849 996,955 33.23
Interregional Road System 164(d)(3) 1,250,000 0 0 614 2,433 0 3,047 0.24
Traffic Systems Management 164(d)(4) 1,000,000 18,829 32,628 53,602 0 13,563 118,622 11.86
State Match for the Congestion Mitigation and
Air Quality and Surface Transportation Programs 182.4 d 27,200 (5) 27,195 N/A
Flexible Congestion Relief 164(d)(5) 3,000,000 0 0 18,613 102,674 138,099 259,386 8.65
State Controller’s Office Formula-Based Payments
to Cities and Counties 164(d)(6) 3,000,000 139,833 213,170 234,983 278,829 295,539 1,162,354 38.75
State-Local Transportation Partnership 164(d)(7) 2,000,000 61,429 198,789 126,549 163,950 128,996 679,713 33.99
Retrofit Soundwalls 164(d)(8) 150,000 0 0 259 1,499 12,244 14,002 9.33
Environmental Enhancement and Mitigation
Demonstration 164(d)(9) 100,000 0 9,880 9,880 8,075 9,667 37,502 37.50
Transit Operations and Capital Improvements 164(d)(10) 500,000 13,200 8,690 50,491 60,003 19,375 151,759 30.35
State Highway Operation and Protection 164(d)(11) 1,000,000 44,087 80,159 137,517 330,225 267,342 859,330 85.93
State Matching and Exchange for Federal Funds 182.6(g) d 0 0 0 19,535 74,738 94,273 N/A
and (h)
and 182.9
Other N/A N/A 0 0 0 554 32 586 N/A
Total $18,500,000 $714,119 $1,484,452 $1,479,988 $1,656,104 $1,184,831 $6,519,494 35.24%
a Column shows estimated expenditures on various transportation programs specified in the Streets and Highways Code, Section 164(d). The 1988 STIP shortfall represents the
difference between the resources projected to be available to pay for the 1988 STIP projects and the resources projected to be needed to pay for the 1988 STIP projects.
b The sources of the expenditure data are Department of Transportation and State Controller’s Office financial records.
c The blueprint legislation anticipated revenue of $3 billion to be funded by three $1 billion bond issues subject to voter approval. However, the voters approved only one of the three
bond issue propositions.
d Chapter 1177, Statutes of 1992, amended the Streets and Highways Code to require funds appropriated for the Traffic Systems Management Program to be used first for matching
federal funds provided for these programs. This statute also authorizes the commission to allocate state funds for matching other federal funds and exchanging federal funds for state
funds.
Letter Report 95014
Date
Page 11
few projects started in 1990 or later would be ready for
construction until 1995 or later. Therefore, according to the
executive director, the commission would expect expenditures
for projects in the 1988 STIP shortfall to be greater than
expenditures for projects in programs such as Flexible
Congestion Relief and the Interregional Road System which
are programmed in 1990 and later STIPs.
We could not determine expenditures for five transportation
programs directly from the accounting records because the
department does not use a unique program code to account
for the 1988 STIP shortfall expenditures. Instead, the
department records 1988 STIP shortfall project expenditures
using the program codes for the Interregional Road System,
Flexible Congestion Relief, Retrofit Soundwalls, Traffic
Systems Management, and the State Highway Operation and
Protection Program. As a result, some of the expenditures
recorded in these program codes are part of the 1988 STIP
shortfall, and some are part of subsequent STIPs. To
determine the portion of expenditures under these program
codes that is for the 1988 STIP shortfall and the portion that is
for subsequent STIPs, we used expenditure ratios that the
department provided to us to calculate the amounts expended
for these five programs and the amount expended for the
1988 STIP shortfall. For example, the Retrofit Soundwalls
Program expenditure of $12,244,000 for fiscal year 1994-95 is
based on the department’s determination that it expended
13 percent of its total fiscal year 1994-95 expenditures under
the Retrofit Soundwalls program code for 1988 STIP shortfall
projects.
The table also shows that expenditures for fiscal years
1993-94 and 1994-95 include state matching and exchange
funds authorized by Chapter 1177, Statutes of 1992. The
statutes added Section 182.4 to the Streets and Highways
Code to establish a priority for spending funds appropriated
for Traffic Systems Management (TSM). This section
requires the department to give first priority to providing the
amount of these funds necessary to match federal funds
available to local governments for the Congestion Mitigation
and Air Quality Program and for TSM projects in the Regional
Surface Transportation Program. As a result of this
legislation, the department provided over $27 million of
blueprint revenue to local governments for matching federal
funds for these programs.
Letter Report 95014
Date
Page 12
In addition to this matching, Chapter 1177 added
Sections 182.6(g) and (h) that allow certain local governments
to exchange an apportionment of federal funds for state funds
and Section 182.9 that requires the commission to allocate
certain amounts of state funds for matching of federal funds in
addition to the authority provided by Section 182.4 or, if
excess, for any transportation purpose. These two sections
do not specify whether the State must expend blueprint
revenue or other state revenue for the match and exchange
funds. During fiscal year 1993-94 and 1994-95, the State
expended more than $94 million of blueprint revenue to
provide state funds for these two purposes. Table 3 shows
the $94 million as an unplanned expenditure because
legislation does not explicitly authorize the State to expend
blueprint revenue for these purposes.
According to the executive director, commission staff were
involved in the preparation of the legislation that resulted in
the addition of Sections 182.6(g) and (h) and 182.9 to the
Streets and Highways Code. According to the executive
director, although these sections do not specify that blueprint
revenue should be used for these match and exchange
purposes, the commission understood the intent of the
legislative package to mean that blueprint revenue would be
used for all sections of the legislation.
In addition to the State’s expenditures for transportation
programs, the Transportation Blueprint requires the State
Controller’s Office to distribute a portion of the blueprint
revenue directly to cities and counties. We found that the
State Controller’s Office distributed approximately
$296 million to counties in fiscal year 1994-95. Furthermore,
we determined that the State Controller’s Office calculated the
amount of these distributions to cities and counties in
accordance with the formulas provided in legislation.
Lastly, Table 3 shows that the State expended approximately
$600,000 of blueprint revenue for programs other than those
listed in the Transportation Blueprint. The expenditures in
this category include projects in the local assistance program
for bridge replacements and repairs. Expenditures for bridge
work are appropriate for Transportation Blueprint revenue
because although these projects were in the local assistance
program and not the SHOPP, bridge projects are one of the
types of projects included in the SHOPP, which is a
Transportation Blueprint program.
We conducted this review under the authority vested in the
Bureau of State Audits by the Government Code, Section
14525.6, as amended by the Government Code, Section
8546.8, and according to generally accepted government
auditing standards. We limited our review to those areas
specified in the audit scope section of this report.
Respectfully submitted,
KURT R. SJOBERG
State Auditor
Appendix
Programs for Which the State Uses
Transportation Funds Made Available by the
1989 Transportation Blueprint Legislation
State Transportation Improvement Program
A seven-year project delivery program updated every two
years limited to flexible congestion relief, interregional road
systems, retrofit soundwalls, intercity rail service, and
commuter and urban rail capital improvements.
Intercity Rail Program
A program to provide an efficient system of intercity rail
service in the state.
Commuter and Urban Rail Transit Program
A program to provide rail transportation for services operated
in metropolitan and suburban areas.
Interregional Road System Plan Program
A program to improve state highways outside urban areas
with populations of more than 50,000 on eligible routes
specified in Streets and Highways Code, Sections 164.10 to
164.20. Projects must be limited to meeting the needs of
interregional traffic, excluding traffic generated as a result of
local growth.
Traffic Systems Management Program
A program to provide solutions for congestion on the state
highways in urban areas. The program is designed to
increase the number of people who may use the highway
system in a peak period without significantly increasing the
designed capacity of the highway system when measured by
the number of vehicle trips and without increasing the number
of through traffic lanes.
Flexible Congestion Relief Program
A program to reduce or avoid congestion on existing
transportation systems by increasing their capacities. Funds
may be allocated to projects on city streets, county
highways, state highways, intercity rail corridors, and
commuter rail and urban rail corridors that are included in the
State Transportation Improvement Program.
State-Local Transportation
Partnership Program
A program intended to provide matching funding to local
governments for locally funded and constructed transportation
projects.
Retrofit Soundwalls Program
A program to place soundwalls along existing state freeways
to reduce noise levels.
Environmental Enhancement and
Mitigation Demonstration Program
A program to undertake environmental enhancement and
mitigation projects that are directly or indirectly related to the
environmental impact of modifying existing transportation
facilities or to the design, construction, or expansion of new
transportation facilities.
State Highway Operation and
Protection Program
A program that provides for capital improvements related to
the rehabilitation, safety, and maintenance of existing state
highways and bridges, which do not add a new traffic lane to
the system.