CSA
Summary
Read the report at California State Auditor ↗
Department of
Transportation:
Seismic Retrofit Expenditures Are Generally
in Compliance With the Bond Act
October 1999
99022
The first copy of each California State Auditor report is free.
Additional copies are $3 each. You can obtain reports by contacting
the Bureau of State Audits at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
Permission is granted to reproduce reports.
C S A
ALIFORNIA TATE UDITOR
KURT R. SJOBERG MARIANNE P. EVASHENK
STATE AUDITOR CHIEF DEPUTY STATE AUDITOR
October 7, 1999 99022
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As required by Chapter 310, Statutes of 1995, the Bureau of State Audits presents its audit report
concerning the Department of Transportation’s (department) revenues and expenditures authorized by the
Seismic Retrofit Bond Act of 1996 (Bond Act). This report concludes that the department, in general, has
ensured that seismic retrofit projects funded with bond proceeds are consistent with the purpose of the
Bond Act. In fiscal year 1999-2000, the department plans to begin reimbursing the State Highway
Account and the Consolidated Toll Bridge Fund for expenditures incurred during fiscal years 1994-95
and 1995-96.
Respectfully submitted,
KURT R. SJOBERG
State Auditor
BUREAU OF STATE AUDITS
555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019
CONTENTS
Summary 1
Introduction 3
Audit Results
Although Seismic Retrofit Projects Were
Valid, Not All Expenditures Were Eligible
for Bond Act Funding 9
Appendix A
Status of the Seismic Retrofit Program 13
Appendix B
Bond Act Expenditures as of June 30, 1999 15
Response to the Audit
Business, Transportation and Housing Agency 17
SUMMARY
RESULTS IN BRIEF
L
egislation passed in 1995 requires the California State
Auditor to ensure that projects funded by the Seismic
Retrofit Bond Act of 1996 (Bond Act) are consistent with
that measure’s purposes, which are to reconstruct, replace, or
retrofit state-owned highways and bridges, including toll
bridges. This is the fourth in a series of annual reports on the
Department of Transportation’s (department) revenues and
expenditures, authorized by the Bond Act, for retrofitting
California’s highways and bridges.
As of June 30, 1999, the department had spent $1.14 billion for
projects on more than 1,100 bridges and 7 state-owned toll
bridges, completing 96 percent of the retrofitting for highway
bridges and having all of the toll bridges either in retrofit design
or under construction. In general, the department has done a
good job of ensuring that seismic retrofit projects do meet the
criteria for funding under the Bond Act. However, we found that
not all expenditures charged to those projects were eligible for
such funding. Through minor recording errors, the department
incorrectly charged approximately $38,000 for expenses not
allowed under the Bond Act.
Also, the department has not resolved a long-standing issue of
reimbursing other accounts for interim funding obtained during
fiscal years 1994-95 and 1995-96. During those years, the State
Highway Account (highway account) and the Consolidated Toll
Bridge Fund (toll bridge fund) provided a total of $114 million
in expenditures and commitments for retrofitting California’s
bridges. The Bond Act requires that the department use bond
proceeds to reimburse the highway account and the toll bridge
fund for these prior expenditures.
In attempting to make the reimbursements, however, the depart-
ment discovered two objections: one by the State Treasurer’s
Office, which pointed to a possible loss of the bonds’ tax-exempt
status; and a second by the Department of Finance, which
objected that the department’s source of reimbursement funds
C A L I F O R N I A S T A T E A U D I T O R 1
could be used only for current expenditures. Although both of
these objections were removed by provisions in 1997 legislation,
the department had not taken any action as of June 30, 1999, to
reimburse the expenses.
AGENCY COMMENTS
In their response, the department addressed the current status
of reimbursing other accounts for interim funding obtained
during fiscal years 1994-95 and 1995-96. The department
acknowledged that it originally planned to reimburse the high-
way account and toll bridge fund during fiscal year 1998-99.
However, the department states that the criteria it developed to
select the projects to facilitate this reimbursement process was
complex and required additional time. Therefore, the depart-
ment currently anticipates that it will accomplish this
reimbursement in fiscal year 1999-2000. n
2 C A L I F O R N I A S T A T E A U D I T O R
INTRODUCTION
BACKGROUND
S
ince the 1971 Sylmar earthquake struck the Los Angeles
area, the Department of Transportation (department) has
been engaged in a statewide seismic retrofit program for
bridges. Seismic retrofit involves structural analysis to determine
a bridge’s potential vulnerability during earthquakes and a
strategy meeting with engineers to discuss the extent and nature
of retrofit approaches and to determine the final retrofit design.
Current retrofit work includes strengthening the columns of
existing bridges by encircling them with a steel casing, enlarging
and strengthening some of the bridge footings by placing addi-
tional pilings in the ground or by using steel tie-down rods to
better anchor the footings to the ground, and enlarging the
hinges that connect sections of bridge decks to help prevent
them from separating during severe ground movement.
Before the January 1994 Northridge earthquake, the department
classified all state-owned highway bridges (except toll bridges)
into two groups: single-column bridges and multiple-column
bridges. After the Northridge earthquake, the department reclas-
sified the bridges into Phase I and Phase II categories. Phase I
includes bridges determined in the strategy process to have
required retrofitting as of January 1, 1994; these bridges are thus
not eligible for funding from the Seismic Retrofit Bond Act of
1996 (Bond Act). Phase II includes all of the remaining state-
owned bridges (excluding toll bridges), for which no retrofit
strategy was in place by January 1, 1994.
In March 1996, California voters approved the Bond Act, which
authorized the State to sell $2 billion in state general-obligation
bonds to reconstruct, replace, or retrofit Phase II bridges and
state-owned toll bridges. The Bond Act will remain in effect until
all construction activities for the seismic retrofit of state-owned
toll bridges are complete or until June 30, 2005, whichever is
sooner. Figure 1 depicts the State’s continuing seismic retrofit
activity and its relationship to the Bond Act.
C A L I F O R N I A S T A T E A U D I T O R 3
FIGURE 1
Retrofit Activity: 1971 to the Present
C O N T I N U I N G R E T R O F I T A C T I V I T Y
Phase II and
toll bridge retrofitting
Interim funding from Interim funding from
State Highway Account Pooled Money
and Investment Account loan
Consolidated Toll Bridge Fund
1971 1989 1994 1996 1997 1998 1999
Bond Act Bonds issued in Bonds issued Bonds issued
Sylmar Loma Prieta Northridge
approved March and October in October in February,
earthquake earthquake earthquake
April, and June
Phase II
category established
ACTIVITIES FUNDED WITH BOND PROCEEDS
The Bond Act initially required the department to use $650 mil-
lion of the bond proceeds for seismic retrofit of toll bridges and
the remaining $1.35 billion for Phase II retrofits. However, on
August 20, 1997, the governor signed into law Chapter 327,
Statutes of 1997, which effectively shifted the allocation of
expenditures in the Bond Act to $790 million for toll bridges
and $1.21 billion for Phase II retrofits. Since the estimate to
retrofit or replace the state-owned toll bridges is $2.62 billion,
the legislation also authorized additional funds from various
state and toll bridge revenue accounts for retrofitting the seven
toll bridges.
The Bond Act also requires the department to use bond proceeds
to reimburse the State Highway Account and the Consolidated
Toll Bridge Fund, which, along with other state funds, provided
approximately $114 million in interim funding for fiscal years
1994-95 and 1995-96 expenditures for Phase II and toll
bridge retrofits.
In fiscal year 1996-97, the Seismic Retrofit Bond Fund of 1996
was created to account for seismic retrofit expenditures and
revenues. Before bonds can be issued, this fund uses loans from
the State Pooled Money Investment Account to cover expendi-
tures made by the seismic retrofit program. As Figure 2 indicates,
the funding of these expenditures is very complex, involving
temporary funding until bonds are issued.
4 C A L I F O R N I A S T A T E A U D I T O R
FIGURE 2
The Use of Funds for Bond Fund Expenditures
State Treasurer's Office
Commercial Bonds
paper sold sold
D F
Commercial Bonds
Paper
Loan
E G Liability paid off
PPoooollede dM oMnoenyey reimbursed
IInnvvesetsmtemnetnt
AAccccoouunntt
Loan Expenditures
established B reimbursed C
Transportation
Revolving Account
Seismic Retrofit
Bond Fund
Contractor
A
paid
Contractor
A Seismic retrofit expenditures are originally paid from the Transportation Revolving Account.
B The State's Pooled Money Investment Account (PMIA) loan program provides interim financing to Bond Act
projects. As of June 30, 1999, the department had received PMIA loans totaling $1.3 billion, all of which were
approved by the Pooled Money Investment Board.
C The department uses PMIA loan funds and submits a monthly transfer letter, based on a Plan of Financial
Adjustment, to the State Controller's Office to reimburse the Transportation Revolving Account from the
Seismic Retrofit Bond Fund for the month's expenditures.
D The State Treasurer's Office sells commercial paper in the amount of the previous period's expenditures
recorded in the Seismic Retrofit Bond Fund. Commercial paper is simple, short-term promissory notes with
maturities ranging from 1 to 270 days.
E The proceeds of these commercial paper sales are used to pay down the outstanding balance of the PMIA loan
to the department.
F The State Treasurer's Office sells general obligation bonds when the market is favorable.
G The State Treasurer's Office uses the proceeds from bond sales to pay off the liability for the commercial paper.
C A L I F O R N I A S T A T E A U D I T O R 5
STATUS OF THE BOND ISSUANCES
Since the inception of the seismic retrofit program, the State has
issued six general obligation bonds under the Bond Act. Table 1
shows the date and amount of each issuance.
TABLE 1
Seismic Retrofit Bond Act:
General Obligation Bond Issuances
Bond Series Date Sold Amount Sold
Series A 03/18/97 $ 50,005,000
Series B 10/08/97 300,000,000
Series C 10/07/98 344,850,000
Series D 02/23/99 100,000,000
Series E 04/07/99 76,000,000
Series F 06/09/99 20,000,000
Total $890,855,000
SCOPE AND METHODOLOGY
Chapter 310, Statutes of 1995, requires the California State
Auditor to annually audit revenues and expenditures authorized
by the Bond Act to ensure that the projects funded are consis-
tent with the act’s purpose.
To gain an understanding of the seismic retrofit program, we
reviewed the Bond Act’s provisions and the related policies and
procedures developed by the department for expenditures
charged to the Seismic Retrofit Bond Fund of 1996. We also
interviewed administrators and staff to determine their responsi-
bilities for implementing provisions of the Bond Act and their
manner of meeting those responsibilities.
To determine how fully the department complied with the
requirements of the Bond Act, we reviewed a sample of seismic
retrofit projects for fiscal year 1998-99 and assessed whether the
projects were eligible for funding. In addition, we reviewed a
sample of the $1.14 billion in seismic retrofit expenditures
recorded as of June 30, 1999, for all years combined.
6 C A L I F O R N I A S T A T E A U D I T O R
We also followed up on the issues raised by the State Treasurer’s
Office and the Department of Finance regarding the federal tax
and fiscal implications of using bond proceeds to reimburse
fiscal years 1994-95 and 1995-96 Phase II seismic retrofit expen-
ditures. We reviewed the department’s records and interviewed
administrators to determine whether any reimbursement has
taken place.
Finally, we reviewed bond-issuance records available through
August 1999 to determine their status and use. n
C A L I F O R N I A S T A T E A U D I T O R 7
Blank page inserted for reproduction purposes only.
8 C A L I F O R N I A S T A T E A U D I T O R
AUDIT RESULTS
Although Seismic Retrofit Projects
Were Valid, Not All Expenditures
Were Eligible for Bond Act Funding
SUMMARY
W
e reviewed a sample of 32 projects and 50 expendi-
tures charged to these projects by the Department of
Transportation (department) for fiscal year 1998-99.
We found that while the projects and most of the expenditures
were appropriate under the Seismic Retrofit Bond Act of 1996
(Bond Act), some expenditures were in error. Specifically, we
found that the department erroneously charged approximately
$38,000 to Bond Act projects for expenses it should have
recorded elsewhere.
As reported in our last two audits, the department encountered
difficulties with the Bond Act requirement to reimburse the State
Highway Account (highway account) and the Consolidated Toll
Bridge Fund (toll bridge fund) for funds the department used for
seismic retrofit expenditures in fiscal years 1994-95 and 1995-96.
Specifically, the State Treasurer’s Office and the Department of
Finance had raised valid objections to the department’s method
of reimbursement. In 1997, new legislation removed those
objections, allowing the department to use Bond Act revenues to
reimburse the highway account and the toll bridge fund, and
the department indicated that it would begin payments in fiscal
year 1998-99. However, our review of the department’s records
through June 30, 1999, found that it had not begun the
reimbursement process.
BACKGROUND
As of June 30, 1999, department records showed that 559 active
seismic retrofit projects related to 1,155 Phase II bridges and
7 toll bridges were eligible to use Bond Act revenues. The depart-
ment has retrofitted 96 percent of the Phase II bridges. The
department has also completed 2 of the 13 construction con-
tracts that it currently has for retrofitting 6 of the state-owned
C A L I F O R N I A S T A T E A U D I T O R 9
toll bridges. In addition, the department projects that it will
award all contracts for the San Francisco-Oakland Bay Bridge,
the seventh state-owned toll bridge, by 2001. Appendix A shows
the status of the seismic retrofit program. As of June 30, 1999,
the department had recorded over $1.14 billion in expenditures
for both types of projects funded with Bond Act revenues.
Appendix B shows the breakdown of these expenditures.
NOT ALL EXPENDITURES WERE ELIGIBLE
FOR BOND ACT FUNDING
Although most of the expenditures we reviewed were properly
charged to the Seismic Retrofit Bond Fund of 1996, we found
allocation and coding errors that caused inappropriate charges.
For one of the 50 expenditure transactions we reviewed, the
department incorrectly charged approximately $6,700 to a
Phase II project that should have been charged to a Phase I
project. This error occurred because the department failed to
identify that, unlike most of its contracts, this contract for
professional services benefited several projects, thus requiring
the department to allocate the $392,262 that it paid for these
services to a combination of Phase I, Phase II, and toll bridge
seismic retrofit projects. After we discussed this allocation with
the department, it corrected its mistake by transferring approxi-
mately $6,700 from Phase II to Phase I projects.
In addition, we found that the department erroneously charged
to a seismic retrofit project a total of $31,066 for legal services to
defend the department in a right-of-way lawsuit related to a
nonseismic project. This mistake occurred because the depart-
ment made a keying error when entering the project code. The
department did not identify the error because it failed to follow
its review procedures for right-of-way capital outlay expenditures.
After we discussed this coding error with the department, it made
an adjusting entry to charge the expenditure to the correct project.
These two errors seem to be the result of isolated breakdowns
in the department’s system of ensuring that only eligible expen-
ditures are charged to the Bond Act and are not pervasive
throughout the seismic retrofit expenditures.
10 C A L I F O R N I A S T A T E A U D I T O R
The Department Has Not Yet Reimbursed
Early Seismic Retrofit Expenditures
Article 2 of the Bond Act requires that bond proceeds be used to
reimburse the highway account and the toll bridge fund for
seismic retrofit expenditures during fiscal years 1994-95 and
1995-96. Department records show approximately $114 million
in expenditures and commitments for seismic retrofit during
these two fiscal years. This total included $103 million from the
highway account and $11 million from the toll bridge fund.
However, as we stated in previous reports, the department
found two problems that prevented it from complying with
this requirement.
First, the State Treasurer’s Office raised the concern that reim-
bursing these past expenditures with bond proceeds would
jeopardize the bonds’ federal tax-exempt status, potentially
obligating the State, if the tax-exempt status were lost, to pay
bond purchasers a higher interest rate to compensate them for
paying federal taxes on interest earnings. According to the
State’s bond counsel, under treasury regulation, an issuer
wanting to use the proceeds of tax-exempt bonds to reimburse
expenditures must adopt a resolution of official intent no later
than 60 days after the payment of the original expenditures,
indicating that it expects to reimburse the expenditures with
bond proceeds. Because the 60-day window for the early retrofit
expenditures has long since passed without the required official
resolution, the reimbursement of expenditures does not meet
the requirements for tax exemption.
Further, because of fiscal considerations, the Department of
Finance objected to using Pooled Money Investment Account
loans to provide interim reimbursement to the highway account
and the toll bridge fund for fiscal years 1994-95 and 1995-96
seismic retrofit expenditures. Loan provisions require that
this possible source of reimbursement be used for current
expenditures only.
In August 1997, new legislation offered a solution to the prob-
lem of preserving the tax-exempt status of the bonds, while
meeting the legal reimbursement requirements. Chapter 327,
Statutes of 1997, authorizes the use of $745 million from the
highway account to finance seismic retrofit projects for toll
bridges. According to the chief of the department’s Office of
Finance and Capital Budgets, because the new legislation
requires highway account contributions for toll bridge retrofits,
C A L I F O R N I A S T A T E A U D I T O R 11
the department plans to use $103 million of bond proceeds to
pay for future costs of this type. In addition, the department
intends to fund $11 million of future toll bridge fund projects
with Bond Act revenues. This allows the department to use Bond
Act proceeds to reimburse the highway account and the toll
bridge fund for the $114 million in seismic retrofit expenditures
incurred during fiscal years 1994-95 and 1995-96. Furthermore,
the 1997 legislation also addresses the Department of Finance’s
concerns because it allows Pooled Money Investment Account
loans to temporarily fund future seismic retrofit projects until
bonds are issued.
The Seismic Retrofit Finance Committee, which is responsible
for the administration of Bond Act financing programs, approved
the department’s use of these funds on November 19, 1997. Yet,
when we reviewed the department’s records, we determined that
no actual reimbursement had taken place as of June 30, 1999.
According to the department, it has not begun the reimburse-
ment because selecting the best possible projects to facilitate this
reimbursement is a complex process. More specifically, the
department is currently reviewing its project inventory to select
only projects that are scheduled for construction and comple-
tion within the life of the Bond Act, which ends on June 30, 2005.
The department intends to complete the selection of projects by
the end of fiscal year 1999-2000.
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
KURT R. SJOBERG
State Auditor
Date: October 7, 1999
Staff: Denise L. Vose, CPA
Nasir Ahmadi, CPA
Anna Escuadro
12 C A L I F O R N I A S T A T E A U D I T O R
APPENDIX A
Status of the Seismic Retrofit Program
T
ables 2 and 3 depict the status of the seismic retrofit
program for both Phase II bridges and toll bridges as
of July 1, 1999.
TABLE 2
Status of Phase II Bridges as of July 1, 1999
Retrofit Under
District Complete Construction Design Total
1 63 1 5 69
2 12 0 0 12
3 34 2 0 36
4 131 11 9 151
5 100 4 3 107
6 77 0 0 77
7 288 3 2 293
8 124 1 5 130
9 7 0 0 7
10 40 0 0 40
11 172 0 0 172
12 61 0 0 61
Totals 1,109 22 24 1,155
Source: Seismic Retrofit Program: Summary Status, issued by the Department
of Transportation.
C A L I F O R N I A S T A T E A U D I T O R 13
TABLE 3
Status of Toll Bridges as of July 1, 1999
Number of Current Retrofit
Toll Facility Projects Current Status Completion Date
San Francisco-Oakland Bay Bridge:
East Bay span To be determined Design Spring 2005
West Bay span 7 Construction/design Summer 2005
Benicia-Martinez Bridge 2 Under construction Summer 2001
San Mateo-Hayward Bridge 4 Under construction/design Spring 2001
Richmond-San Rafael Bridge 1 Design Winter 2004
Carquinez Bridge (eastbound) 1 Under construction Summer 2000
Vincent Thomas Bridge 1 Under construction Winter 2000
San Diego-Coronado Bridge 4 Under construction/design Winter 2002
Source: Seismic Retrofit Program: Summary Status, issued by the Department of Transportation.
14 C A L I F O R N I A S T A T E A U D I T O R
APPENDIX B
Bond Act Expenditures as of
June 30, 1999
T
able 4 shows the breakdown of seismic retrofit expendi-
tures by fiscal year as of June 30, 1999.
TABLE 4
Breakdown of Seismic Retrofit Expenditures as of June 30, 1999
(in Thousands)
Fiscal Fiscal Fiscal Fiscal Fiscal
Year Year Year Year Year Total
Expenditures 1994-95 1995-96 1996-97 1997-98 1998-99 (All Years)
Phase II bridges
State operations
Administration $ 0 $ 0 $ 7,248 $ 18,314 $ 24,038 $ 49,600
Legal 0 0 0 0 0 0
Operations 0 0 0 0 1 1
Capital outlay—support 12,452 19,248 70,609 80,542 34,928 217,779
Subtotal 12,452 19,248 77,857 98,856 58,967 267,380
Capital outlay
Major construction 0 0 0 0 0 0
Major contracts 4,085 1,880 185,215 172,184 65,256 428,620
Minor construction (A&B) 0 0 0 0 0 0
Minor contracts (A&B) 1,043 1,961 4,615 1,718 219 9,556
Right-of-way 57 259 562 1,118 443 2,439
Subtotal 5,185 4,100 190,392 175,020 65,918 440,615
Total Phase II 17,637 23,348 268,249 273,876 124,885 707,995
Toll bridges
State operations
Administration 0 0 3,490 11,789 15,694 30,973
Legal 0 0 0 0 0 0
Operations 0 0 0 0 0 0
Capital outlay—support 14,978 48,447 44,548 47,511 7,339 162,823
Subtotal 14,978 48,447 48,038 59,300 23,033 193,796
Capital outlay
Major construction 0 0 0 0 0 0
Major contracts 877 7,285 5,938 39,572 161,658 215,330
Minor construction (A&B) 0 0 0 0 0 0
Minor contracts (A&B) 0 0 0 0 0 0
Right-of-way 2 0 492 7,334 15,512 23,340
Subtotal 879 7,285 6,430 46,906 177,170 238,670
Total toll bridges 15,857 55,732 54,468 106,206 200,203 432,466
Grand Total $33,494 $79,080 $322,717 $380,082 $325,088 $1,140,461
C A L I F O R N I A S T A T E A U D I T O R 15
Blank page inserted for reproduction purposes only.
16 C A L I F O R N I A S T A T E A U D I T O R
(Agency’s response provided as text only:)
Business, Transportation and Housing Agency
980 9th Street, Suite 2450
Sacramento, California 95814-2719
September 29, 1999
Kurt R. Sjoberg, State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Dear Mr. Sjoberg:
Attached is the Department of Transportation’s (Caltrans) response to your report
entitled “Department of Transportation: Seismic Retrofit Expenditures Are Generally in
Compliance with the Bond Act,” report #99022. As identified in your report, I am
pleased to report that Caltrans has done a good job of ensuring that seismic retrofit
projects are meeting the criteria for funding under the Seismic Retrofit Bond Act of
1996.
While the report also identified that Caltrans has not yet reimbursed the State Highway
Account (SHA) and the Toll Bridge Fund for temporarily providing $114 million for
seismic retrofit expenditures to California bridges from Proposition 192 funds, Caltrans
will accomplish the reimbursement in fiscal year 1999-2000. Caltrans has chosen to
select specific projects consistent with Bond Act timeframes and also projects which
are 100% SHA or Toll Bridge funded to reduce the complexities of cost allocation. This
process requires additional time to select specific projects meeting these criteria.
If you have any questions, please let me know.
Sincerely,
(Signed by: Maria Contreras-Sweet)
MARIA CONTRERAS-SWEET
Secretary
Attachment
C A L I F O R N I A S T A T E A U D I T O R 17
Department of Transportation
Office of the Director
1120 N Street
P. O. Box 942873
Sacramento, CA 94273-0001
September 29, 1999
MARIA CONTRERAS-SWEET, Secretary
Business, Transportation and Housing Agency
980 - 9th Street, Suite 2450
Sacramento, CA 95814
Dear Secretary Contreras-Sweet:
I am pleased to provide our response to the State Auditor’s report on Seismic Retrofit
Expenditures for fiscal year 1998/99. The audit report noted that seismic retrofit expen-
ditures were generally in compliance with the Bond Act. Two minor recording errors
totaling approximately $38,000 were noted, which amount was immaterial when com-
pared to total seismic retrofit expenditures of $1.14 billion.
The State Auditor also reported on the status of the reimbursement of fiscal year 1994/
95 and 1995/96 expenditures to the State Highway Account and Consolidated Toll
Bridge Fund. The reimbursement issue was originally reported by the State Auditor in
December 1997, in their audit report on seismic retrofit expenditures. Caltrans would
like to provide the following clarifying information on the current status of these reim-
bursements.
Caltrans intended to accomplish the reimbursement of State Highway Account (SHA)
and Toll Bridge Accounts from Proposition 192 funds during fiscal year 1998-99. How-
ever, in developing the criteria for choosing projects to be funded with Proposition 192
funds, it became apparent that selecting very specific types of projects would greatly
benefit the management of the reimbursement process. Two key criteria for selecting
SHA and Toll Bridge projects for funding with Proposition 192 funds are:
Construction complete by June 30, 2005, the sunset date of Proposition 192 funds
Initially, large projects were considered to reduce the number of non-seismic retrofit
projects funded with Proposition 192 funds. However, many of the large projects that
were considered are not scheduled to begin construction until close to the sunset date
of Proposition 192.
Projects initially programmed as 100% SHA or Toll Bridge funded
18 C A L I F O R N I A S T A T E A U D I T O R
Projects with a combination of funding sources such as state, federal and reimburse-
ment funds create a more complex process for monitoring the Proposition 192 “share”
of expenditures. Projects that include federal and reimbursement funding often require
expenditure adjustments at the time of completion. This is attributable to the project
close out process when final eligibility of expenditures for reimbursement by either the
federal government or local entities is determined.
The above selection criteria made it more difficult than anticipated to develop the
candidate list of projects for funding with Proposition 192 funds. However, Caltrans has
nearly completed development of an inventory of SHA and Toll Bridge projects and will
accomplish the reimbursement in fiscal year 1999-00.
If we can provide any further information, or if you have any questions, please do not
hesitate to contact me.
Sincerely,
(Signed by: Tony V. Harris for Jose Medina)
JOSE MEDINA
Director
C A L I F O R N I A S T A T E A U D I T O R 19
cc: Members of the Legislature
Office of the Lieutenant Governor
Attorney General
State Controller
Legislative Analyst
Assembly Office of Research
Senate Office of Research
Assembly Majority/Minority Consultants
Senate Majority/Minority Consultants
Capitol Press Corps
20 C A L I F O R N I A S T A T E A U D I T O R