CSA
Summary
Read the report at California State Auditor ↗
Department of
Transportation:
Disregarding Early Warnings Has Caused
Millions of Dollars to Be Spent Correcting
Century Freeway Design Flaws
August 1999
99113
The first copy of each California State Auditor report is free.
Additional copies are $3 each. You can obtain reports by contacting
the Bureau of State Audits at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
Permission is granted to reproduce reports.
C S A
ALIFORNIA TATE UDITOR
KURT R. SJOBERG MARIANNE P. EVASHENK
STATE AUDITOR CHIEF DEPUTY STATE AUDITOR
August 25, 1999 99113
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its audit report
concerning the Department of Transportation(cid:146)s (CalTrans) management of the circumstances surrounding the
damage to the Century Freeway. This report concludes that CalTrans disregarded warning signs of potential
groundwater problems during the original design, planning, and construction of the Century Freeway.
In its efforts to resolve the resulting problems of cracked pavement and a damaged storm drain system, CalTrans
made emergency repairs and is continuing permanent repairs. As of May 1999, total repair costs are estimated
at $67 million, which does not include the cost to dispose of the groundwater pumped out from under the freeway.
CalTrans is currently reviewing options for the beneficial reuse of this groundwater and these options could add
millions of dollars more to the total cost of solving the freeway(cid:146)s problems. Further, CalTrans has taken appropri-
ate steps to review and revise its own procedures to avoid similar problems in future highway projects.
Respectfully submitted,
KURT R. SJOBERG
State Auditor
BUREAU OF STATE AUDITS
555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019
CONTENTS
Summary 1
Introduction 5
Audit Results 9
CalTrans Has Worked to Correct
Design Flaws on the Century Freeway
But Has Not Yet Solved Its Groundwater
Disposal Problem
Recommendations 25
Appendix 27
Responses to the Audit
Business, Transportation and
Housing Agency 31
Department of Transportation 33
California State Auditor(cid:146)s Comments
on the Response From the
Department of Transportation 39
SUMMARY
RESULTS IN BRIEF
A
fter nearly 30 years of controversy, court injunctions,
and delays, the California Department of Transportation
(CalTrans) opened the Century Freeway in Los Angeles
County in October 1993. In March 1995, problems again
arose for the freeway when, less than two years after the
Audit Highlights . . . opening, CalTrans discovered cracking and sunken sections in
the shoulder areas of the freeway that it had constructed below
Our review of the
ground level. Although it originally thought the problems
damaged Century Freeway
involved maintenance issues, by January 1996 CalTrans became
and the Department of
Transportation(cid:146)s (CalTrans) aware that matters were far worse: it had not designed the
response found that: lowered section of the freeway to compensate sufficiently for the
(cid:254) effects of rising groundwater beneath the pavement.
CalTrans did not
adequately test for
groundwater conditions During the planning, design, and construction phases for the
and the design lacked
Century Freeway, CalTrans disregarded warning signs that could
needed elements to
have prevented design flaws in the freeway’s 3.5-mile lowered
counteract the effects of
rising groundwater. section. Most significantly, CalTrans disregarded the 1968
recommendation of its staff to test extensively the soils and the
(cid:254)
Emergency and
groundwater levels in the area planned for the lowered section,
permanent repairs will
even when it designed the modified storm-drain system for the
cost $67 million, not
including the cost to freeway in 1973. Further, in late 1981, CalTrans agreed to extend
dispose of the water. the length of the lowered section of the freeway west toward the
(cid:254) Los Angeles River, and the department apparently designed this
Options under
consideration for reuse extension without adequate research and consideration, such as
of the water could add additional testing of the soil and groundwater conditions in
another $50 million in
the area. If CalTrans had performed these tests, it could have
one-time costs and up
realized the rising groundwater would threaten the freeway as
to $5 million in annual
expenses. designed, and it could have taken appropriate steps early in
the project.
CalTrans has documents from 1987 showing that groundwater
levels had risen substantially between 1985 and 1987 in the area
planned for the below ground level section of the freeway.
However, because this analysis was for determining bridge
foundations, it was not sent to the district unit designing the
lowered section. During construction of the drain system for the
lowered section in July 1990, CalTrans installed four dewatering
wells because it was encountering a lot of water. The ground was
C A L I F O R N I A S T A T E A U D I T O R 1
so wet that CalTrans halted construction for more than six
weeks. Another six years passed before CalTrans realized it had a
serious groundwater problem.
While CalTrans was struggling to move forward with the
Century Freeway project, another agency was taking action that
was to have important consequences for the freeway. The free-
way crosses over two groundwater basins. By the 1950s, the
groundwater of these basins had been overpumped, reducing
available groundwater supplies while demand for groundwater
was increasing. As part of the effort to restore the health of the
groundwater basins, a water replenishment district was estab-
lished in 1959 to return water to the basins. By early 1997, the
groundwater levels had increased over 30 feet. Although the
groundwater replenishment involves all the geological layers,
those layers closest to the surface, which are about 25 feet
below grade, are the ones affecting the lowered section of the
Century Freeway.
CalTrans may have pushed ahead without further analyzing
groundwater conditions because it was under some pressure to
begin construction of the freeway after the 1981 lifting of a
court injunction that had halted progress for many years. To
qualify for federal highway funding for this project, CalTrans
had to meet certain construction deadlines.
In January 1996, once CalTrans acknowledged that the cracking
and sinking were more than ongoing maintenance problems, it
spent $22 million in emergency repairs and planned to use
another $45 million for permanent repairs to the drainage
system. CalTrans engaged both in-house engineers and outside
consultants from academia and private practice to evaluate the
underlying causes of the problems and develop options to
resolve them.
Although it is working to remedy the situation, CalTrans must
still determine what it will do with the groundwater it pumps
from beneath the freeway. As of May 1999, CalTrans had paid,
under protest, more than $370,000 in taxes to pump out the
groundwater. The department is currently diverting the water
into the Los Angeles and San Gabriel rivers: thus the water is not
available for other uses. CalTrans is, on the other hand, review-
ing proposals with two local cities to find beneficial uses for
the extracted water so that it does not waste the water or
undermine the efforts of the local water replenishment district.
Because CalTrans has not determined the best resolution to the
2 C A L I F O R N I A S T A T E A U D I T O R
groundwater disposal problem, it has no firm estimates of
the costs related to the reuse of the extracted water. However,
preliminary estimates suggest that the additional costs could be
more than $50 million for initial costs and from $370,000 to
$5 million in annual costs.
In responding to concerns that CalTrans withheld information
about the problems it was experiencing on the Century Freeway,
CalTrans acknowledged it could have done more to inform the
Legislature. However, CalTrans did include some information
related to the Century Freeway problems in its normal commu-
nications with local legislators, the public, and the California
Transportation Commission.
Since the groundwater problems became apparent, CalTrans
has reassessed some of its policies and procedures and convened
an in-house review of the circumstances leading to the problems
at the lowered section of the Century Freeway. The review
panel made numerous recommendations for new or revised
procedures and most units have responded appropriately. How-
ever, CalTrans has not monitored some units, which were slow
to implement changes.
RECOMMENDATIONS
CalTrans should inform the Legislature, through its Senate and
Assembly Transportation committees, as well as the California
Transportation Commission about the department’s progress in
determining an environmentally sound and cost-effective
method for reusing the groundwater pumped from under the
Century Freeway.
CalTrans should continue working with the Water Replenish-
ment District of Southern California to coordinate actions so
that neither agency jeopardizes the other’s efforts to fulfill its
organizational mission.
To ensure that it properly puts into practice the recommenda-
tions from special in-house staff reports, CalTrans should ensure
that the unit designated to implement these recommendations
periodically reports its progress to department management.
C A L I F O R N I A S T A T E A U D I T O R 3
AGENCY COMMENTS
The Business, Transportation and Housing Agency and CalTrans
agreed with our recommendations. In addition, the department
suggested several wording changes to the draft report. We have
accepted some of the department’s suggestions in developing
our final report. n
4 C A L I F O R N I A S T A T E A U D I T O R
INTRODUCTION
BACKGROUND
I
n October 1993, the California Department of Transporta-
tion (CalTrans) opened the Century Freeway (Interstate 105)
to the public after nearly 30 years of controversy, court
injunctions, and numerous delays. The Century Freeway extends
17 miles across Los Angeles County from the Los Angeles
International Airport in the west to the city of Norwalk in the
east. As it crosses the county, the freeway changes elevation.
Some sections are at ground level, others are elevated, and some
are below ground level. A 3.5-mile portion of the Century
Freeway built below ground level is the subject of this report.
Figure 1 shows that the freeway lies roughly in the area between
the Los Angeles and San Gabriel rivers and runs through the
cities of South Gate, Downey, Paramount, and Bellflower.
FIGURE 1
Lynwood
Downey
South
Gate
Norwalk
Paramount Bellflower
C A L I F O R N I A S T A T E A U D I T O R 5
CalTrans recommended a route for the Century Freeway in
1968. Also during this year, the federal government added the
Century Freeway to the interstate highway system, a decision
that meant federal highway money would pay for a portion of
the freeway’s construction. CalTrans’ Los Angeles district office,
known as District 7, was responsible for the planning, design,
and construction of the freeway. Designing the freeway took
from 1968 to 1972. Then, in 1972, a class action lawsuit was
filed against CalTrans to block the freeway’s construction. Under
the preliminary injunction, CalTrans had to satisfy a number of
requirements, which included preparing a formal environmental
impact statement and conducting public hearings and further
studies examining the effects of the proposed freeway on air
pollution and housing availability.
The timeline in the Appendix shows the lawsuit froze all work
on the freeway project until 1979, when a settlement, called a
consent decree, was reached. Because of the delays, the revised
estimates of construction costs were substantially higher than
the costs CalTrans originally estimated. To salvage the project,
CalTrans, the federal government, and the parties to the lawsuit
agreed to reduce the scope of the freeway project, eliminating
2 traffic lanes, 11 local freeway interchanges, and 500 units of
replacement housing. The court approved this agreement by
issuing an amended consent decree in 1981. Before CalTrans
could begin construction, it had to revise the freeway’s design to
reflect the reduced size and other changes. CalTrans also needed
to negotiate new freeway agreements with the local govern-
ments, obtain any remaining right-of-way properties, and
begin advertising the contracts for construction. By this time,
however, CalTrans was facing additional pressure from critical
deadlines imposed by federal law that required states to have
new interstate routes substantially under construction by
September 1986. The law also stated that the federal government
would give the last funding authorizations for the final contracts
no later than September 1990. Further, the amended consent
decree required that before freeway construction could begin,
CalTrans had to meet certain objectives related to replacing the
residences lost to the freeway.
While CalTrans was struggling to move forward with the
Century Freeway project, another agency, the Water Replenish-
ment District of Southern California, was taking action
that was to have important consequences for the freeway. The
freeway crosses over two groundwater basins. By the 1950s, the
groundwater in these basins had been overpumped, reducing
6 C A L I F O R N I A S T A T E A U D I T O R
available groundwater supplies while demand for water was
increasing. The entities that pumped water from the basins went
to court to have the rights to the groundwater apportioned and,
thus, limit the withdrawal of water from the basins. As part of
the effort to restore the health of the groundwater basins, a
water replenishment district was established in 1959 to return
water to the basins. By early 1997, the groundwater levels had
increased over 30 feet. The groundwater basins consist of several
layers of aquifers1 and aquicludes2 that extend to a depth of at
least 1,000 feet. Although the groundwater replenishment
involves all the geological layers, those layers closest to the
surface, which are about 25 feet below grade, are the ones
affecting the lowered section of the Century Freeway.
Actual construction on the Century Freeway began in 1982, but
construction of the drainage system began in 1990 for the
lowered section of the freeway. A drainage system is necessary
for all freeways, but is even more important when a freeway lies
below ground level in an area of high groundwater because the
system removes groundwater from the surrounding area so the
water does not erode or weaken the roadbed. In 1973, CalTrans
modified the design of its standard drain system for this project
to add an underdrain to control groundwater. This underdrain
consisted of a six-inch perforated pipe wrapped in filter fabric,
placed at least six feet below the freeway pavement, and located
directly above the storm-drain pipes. The underdrain and
storm-drain pipes then channeled the water to one of four pump
houses, where the water was pumped up to ground level and
discharged into the county storm-drain system.
By March 1995, areas of the lowered 3.5 miles of freeway began
to crack, and sunken sections of pavement developed. CalTrans
originally attributed the road degradation to the major storms of
1995, but by January 1996, CalTrans realized that the problems
only began with storm damage—the drainage system under the
freeway shoulders had also been damaged. The pressure associ-
ated with the significant rise in the groundwater level under the
freeway forced the surrounding soil to flow into the damaged
system, which eroded the soil under and around the freeway
and caused portions of the freeway shoulder pavement to sink.
1 An aquifer is an underground layer of sand and gravel through which water can easily
flow.
2 An aquiclude is an underground layer of clay or silt that can hold water but through
which water cannot easily flow.
C A L I F O R N I A S T A T E A U D I T O R 7
As it became evident that a major problem had occurred with
the Century Freeway, CalTrans assembled a team of its staff to
investigate why the freeway failed. This independent analysis
team focused on the department’s processes and procedures and
made several recommendations for improvements.
SCOPE AND METHODOLOGY
The Joint Legislative Audit Committee asked the Bureau of State
Audits to perform an audit of the circumstances surrounding the
damage to the Century Freeway. Specifically, the Legislature was
concerned that design errors, and the construction projects
intended to correct the structural defects, could lead to even
more costly repairs and long-term safety problems.
To understand the construction and rehabilitation work that
CalTrans performed on the Century Freeway, we reviewed and
assessed the available analyses and reports prepared to identify
both the causes of the freeway failure and the options available
to rehabilitate the freeway. This review, in conjunction with
interviews of CalTrans staff, allowed us to assess the methodol-
ogy CalTrans used to develop and implement corrective action.
We reviewed records at CalTrans and at the California Transpor-
tation Commission to determine the total cost of the original
construction of the freeway and the cost of emergency and
permanent repairs. We also reviewed press releases, newspaper
articles, briefing documents, and other records to assess the
information that CalTrans had communicated to other agencies
and to legislators concerning the extent of the problems it was
experiencing on the Century Freeway.
Finally, we reviewed the steps CalTrans is taking to determine
what to do with the groundwater it is pumping from under the
freeway. As part of this work, we reviewed the tests CalTrans is
performing on the water to ensure it is clean enough to dis-
charge to the Los Angeles and San Gabriel rivers. n
8 C A L I F O R N I A S T A T E A U D I T O R
AUDIT RESULTS
CalTrans Has Worked to Correct
Design Flaws on the Century
Freeway But Has Not Yet Solved
Its Groundwater Disposal Problem
SUMMARY
D
espite recommendations from its professional staff
to perform extensive testing of the area where it
was planning to build a section of the Century Freeway
below ground level, the California Department of Transporta-
tion (CalTrans) did not perform this testing. As a result, the
design of this freeway did not have sufficient engineering
elements to counteract the effects of rising groundwater in
the area. CalTrans had dealt with the water it encountered
during the construction of the freeway, but at that time did not
believe the water was an indicator of a serious problem. CalTrans
estimates it will spend $67 million to repair and rehabilitate the
3.5-mile lowered section of the Century Freeway caused by
groundwater problems. Although still exploring the available
options, CalTrans estimates it will need another $50 million in
capital costs to pipe groundwater away from the site and treat it
so the water can be used for a beneficial purpose.
In pumping out the water, CalTrans must also be sure it does not
reverse the efforts of the local water replenishment district to
restore groundwater to an acceptable level. The demands of the
area’s rapidly growing population had seriously depleted
groundwater stores in the past. An effect of the district’s water
replenishment project is the rise in groundwater at the Century
Freeway site; therefore, these agencies must work together on a
permanent plan to avoid undermining each other’s efforts.
To keep the State and the public informed of the problems it
was experiencing with the Century Freeway, CalTrans briefed
the California Transportation Commission (commission) and
conducted annual briefings with the legislators whose districts
the damaged section of the freeway crosses. It also sent out press
releases and responded to requests for information from the
general public. In addition to providing updates to the State and
the public, CalTrans has taken appropriate steps to review its
C A L I F O R N I A S T A T E A U D I T O R 9
own procedures to determine how it could improve them.
CalTrans commissioned an in-house independent analysis
team to recommend improvements. Although the department
evaluated how it can avoid similar problems in the future, it
should have ensured all of its units promptly complied with
the team’s proposals.
CALTRANS OVERLOOKED WARNING SIGNS THAT
MAY HAVE AFFECTED THE DESIGN OF THE
CENTURY FREEWAY
Although preliminary analyses in 1968 showed groundwater
would affect construction, CalTrans disregarded its own
professional staff’s recommendations to test the soil and
groundwater extensively where it planned to build the section
Although preliminary below ground level. In 1981, 13 years later, CalTrans agreed to
analyses showed extend the lowered section, but it did not perform any soil or
groundwater would groundwater tests to see if any of the conditions had changed.
affect construction, Beyond incorporating a modified drainage system into the
CalTrans disregarded design that it believed would address the groundwater condi-
staff recommendations tions, CalTrans did not sufficiently take into account the
for testing. changing groundwater levels under that freeway section.
Another decade passed when, during construction of the
drainage system and the pump houses in 1990, CalTrans
encountered groundwater that halted construction until crews
installed dewatering wells to pump out the groundwater. In
one instance, CalTrans encountered saturated ground in July
and August, which are typically very dry months in Southern
California and during which groundwater levels are usually at
their lowest. However, at the time, CalTrans staff thought the
wet ground indicated that the drain system was working as
intended even though the saturated ground held up construc-
tion for over six weeks.
CalTrans Did Not Update Its Analyses of
Groundwater Conditions
Memos sent in 1968 from the materials and drainage units of
CalTrans’ District 7 informed the District 7 design unit that
groundwater could be a problem in the eastern portion of the
freeway route, which lies in the groundwater basin known as
the Central Basin. At this time, groundwater levels were esti-
mated to be 30 feet or more below the expected pavement level
of the freeway. However, the drainage unit noted in August 1968
10 C A L I F O R N I A S T A T E A U D I T O R
that the groundwater in the area had been rising since 1961 due
In August 1968, the to three factors. First, a court order assigned water rights to
drainage unit noted water users in the groundwater basin. Additionally, Los Angeles
that groundwater County was replenishing groundwater near Whittier Narrows
levels in the freeway Dam and the area had also experienced a few wet years.
area had been rising for
the prior seven years. The drainage unit’s memo also recognized that the groundwater
could rise to levels near the historic high, so construction of a
freeway below ground level would need to rely heavily on
dewatering facilities. In September 1968, a memo from the
materials unit detailed the results of the preliminary soil and
water investigation. The unit concluded that, because of the
possibility of rising groundwater in the area, construction of a
section below ground level was not feasible along a specific
portion of the right of way. The memo further stated that the
soil conditions would allow groundwater to penetrate the
aquiclude and seep into any section constructed below ground
level if the groundwater levels approached their historic highs.
An internal CalTrans memo to the design file in October 1968
summarized the conclusions of a meeting of District 7 staff from
the materials, drainage, and design units. The group concluded
that, even though it did not anticipate any insurmountable
problems, CalTrans would need to construct major facilities to
control the groundwater. The group also recommended exten-
sive testing to determine the extent of groundwater present
throughout the area. In response to the group’s conclusions, in
1973 CalTrans modified its standard design for freeway drain
systems to incorporate for this project an underdrain system to
capture water welling up from below the roadway. A June 1973
memo from the materials unit to the project design unit warned
that this system would not be completely effective if very high
groundwater levels occurred. Nevertheless, in June 1996, the
independent analysis team, which CalTrans formed to review
the problems it was experiencing with the Century Freeway,
concluded that this underdrain system is the only component to
control groundwater conditions that CalTrans included in its
original freeway design.
When it negotiated a new freeway agreement with the City
of Paramount in December 1981, CalTrans agreed to extend
the lowered section of the freeway westward through the
city. Because the final materials report for that section, dated
February 1983, does not mention additional groundwater testing
but only references the 1968 and 1973 work, we assume that
CalTrans did no further testing before designing the extension.
C A L I F O R N I A S T A T E A U D I T O R 11
This section, which includes the Garfield Avenue pump house, is
where CalTrans is currently operating the greatest number of
dewatering wells.
Groundwater levels in the Central Basin began rising in the
Efforts to replenish early 1960s as area users reduced their pumping of groundwater
groundwater in the and as artificial replenishment activity continued. This artificial
area produced a replenishment adds imported water to man-made ponds, where
substantial rise in the it gradually percolates into the aquifers lying beneath. Although
groundwater level since groundwater levels will fluctuate because of factors such as the
the initial design of amount of pumping from the area or drought conditions, as a
the freeway. result of the artificial replenishment, groundwater levels
around the Century Freeway site rose about 12 feet between
1968 and 1981. If CalTrans had performed the testing its staff
recommended in 1968 and then retested when it designed
the extension, CalTrans could have adjusted the final freeway
design accordingly.
Before constructing the lowered section of the Century Freeway,
CalTrans did in fact have some information about the higher
groundwater levels from a number of test borings a headquarters
unit made to determine foundation levels for bridges and pump
houses. The independent analysis team found that the project
design staff at District 7 received most, but not all, of the test
results. However, one memo, a May 1987 report chronicling a
5.2-foot rise in groundwater over the preceding two years,
apparently was not sent to the district unit. Evidently, since the
district project design unit was unaware of the most recent
information, it made no proposals to counteract the changing
groundwater conditions.
CalTrans Felt a Sense of Urgency to Begin Construction So
the Project Would Not Lose Federal Funding
In 1979, when the court issued a consent decree, discussed in
this report’s introduction, that allowed CalTrans to resume
design and construction of the Century Freeway, several factors
had changed. Because the estimated cost for the freeway had
risen from $250 million to between $1.6 billion and $2.2 billion,
the viability of the project was now in question. Consequently,
the federal government and the parties to the lawsuit agreed to a
much smaller project, which the court approved in the amended
consent decree issued in 1981. The agreement eliminated from
the original design 2 traffic lanes, 11 local freeway interchanges,
and 500 units of replacement housing.
12 C A L I F O R N I A S T A T E A U D I T O R
Because the lawsuit delayed freeway construction for so many
years, CalTrans now found itself rushing to meet a federal
requirement that new interstate routes be substantially under
construction by September 1986. The federal government would
also give no funding authorizations after September 1990 for the
final contracts. However, before CalTrans could begin actual
construction, it needed to revise the design of the freeway to
comply with the amended consent decree, negotiate new
freeway agreements with Los Angeles County and the nine
corridor cities, obtain any remaining right-of-way properties,
and begin advertising bidding for contracts. Further, the
amended consent decree also mandated that CalTrans establish
a replacement housing program in conjunction with the
Department of Housing and Community Development, a
project requiring additional time and resources.
Several memos and letters indicate that CalTrans had established
a project timeline of tasks it needed to complete to meet the
federal participation requirements. According to these docu-
ments, December 1981 was a critical time, and the documents
also convey the sense of urgency staff felt to reach these goals.
Further, since many of the local governments had felt the effects
of the long-stalled project in their jurisdictions, they were
anxious for CalTrans to begin construction.
CalTrans Encountered Groundwater During
Freeway Construction
In 1990 when CalTrans began constructing the drainage system
for the Century Freeway’s lowered section, crews encountered
groundwater. When, in 1996, the independent analysis team
reviewed the construction diaries, it had two primary concerns:
CalTrans relied heavily on dewatering wells to remove the water
during construction, and it probably penetrated the aquiclude
In one instance, when building the pump houses, thus providing a conduit for
construction crews the rapid upward flow of groundwater.
halted freeway work
for six weeks because To illustrate how much groundwater that construction crews
the ground was too encountered, the June 1996 report by the independent analysis
saturated(cid:151)an unusual team used the example of the Ardis pump house site. When
event during the dry digging at the site, CalTrans had to install four dewatering wells
summer months. to remove large amounts of groundwater. Although it is not
unusual for construction crews to encounter groundwater when
excavating, in this case, work was halted between July 6, 1990,
and August 21, 1990—more than six weeks—because the
ground was too saturated to continue work. This amount of
C A L I F O R N I A S T A T E A U D I T O R 13
groundwater was an unusual event during what is historically a
very dry period in Southern California and a time when ground-
water levels are generally at their lowest.
The independent analysis report also states that CalTrans’
construction diaries recorded that large amounts of sediment
and water were flowing into the pump houses. At the time,
staff assumed that the large amount of water was evidence that
Although staff thought the drainage system was working as designed and that the
sediment and water sediment was soil washed from the bare slopes graded during
found in pumphouses construction. Maintenance staff also found sediment and water
would diminish, these in the pump houses after the freeway was opened to the public
later were found to be in October 1993. They, too, believed the sediment was soil
indicators of larger eroding from the freeway slopes and would diminish over time
problems. as the slopes stabilized. It was not until the 1996 independent
analysis team investigation that the water and sediment were
seen as indicators of a larger problem with the underground
drainage system.
Both State and Federal Oversight Were Present
During Original Construction
During the original construction of the Century Freeway, both
CalTrans and a federal agency performed inspections to ensure
that the project complied with contract and construction stan-
dards. Because it provided funding for the freeway, the Federal
Highway Administration (FHWA) conducted inspections of work
at the construction site. In addition, CalTrans used its normal
process for managing and inspecting projects; the department
subdivided the large job into smaller projects with specific
geographical boundaries. For example, the 3.5-mile lowered
section of the Century Freeway between Interstate 710 and
Interstate 605 became three projects. CalTrans then assigned
each smaller project to an engineer, designated the resident
engineer, who was responsible for coordinating and approving
all work performed on the project.
Some of the resident engineers on these projects were CalTrans
employees, while others were contract employees, who were
responsible for following all CalTrans policies and procedures
in performing resident engineer duties. As part of their duties,
resident engineers were on the construction site full-time
coordinating the work performed by the various contractors,
making decisions about how to proceed when unexpected
situations arose, and ensuring that the project was proceeding
14 C A L I F O R N I A S T A T E A U D I T O R
appropriately. Resident engineers prepared daily construction
diaries that recorded events occurring on the project, decisions
reached, change orders approved, and other noteworthy items.
CalTrans inspections included tests of the materials used on the
project, interim inspections of work done by contractors, and
final inspections of the work in order to develop a list of items
that the contractor needed to correct before CalTrans formally
accepted the work. When specified in the contract, either
CalTrans or the contractor performed testing of materials used
on the project. However, final acceptance of the project’s materi-
als remained the responsibility of the resident engineer, who
monitored the acceptance testing of these materials. The desig-
nated resident engineer was responsible for the interim and final
inspections. CalTrans formally accepted the three projects
located in the lowered section of the freeway.
In addition, the FHWA inspectors routinely visited the Century
Freeway construction site to inspect the work that had been
completed. The FHWA prepared inspection reports covering
each visit, which covered the project status, construction details,
processes that the inspectors had examined, deficiencies, and
follow-up inspections of deficiencies noted in previous reports.
Generally, FHWA performed these inspections at the start of the
project, at different phases during the construction of the
project, and at the end of the project. For two of the three
projects that became the freeway’s lowered section, we were able
to obtain FHWA’s final inspection reports in which it deemed
acceptable the work performed by the contractor. However, as of
August 1999, FHWA has been unable to provide the final inspec-
tion for the third project.
EVEN THOUGH CALTRANS FOLLOWED A
LEGITIMATE PROCESS TO DECIDE HOW TO CORRECT
THE PROBLEMS, SIGNIFICANT ISSUES REMAIN
In March 1995, CalTrans’ maintenance unit discovered an open
At first, CalTrans depression on the Bellflower Boulevard on-ramp in the lowered
believed that pavement section of the freeway. At that time, the pavement failure along
failures were isolated the freeway shoulder and subsidence of the drainage inlets was
occurrences due to attributed to recent heavy rains. CalTrans investigated to deter-
heavy rains. mine the extent of the damage and to develop an appropriate
method of repair by contracting for ground-penetrating radar
tests and subsurface video inspections. In addition, five pits were
excavated to allow crews to inspect the damage.
C A L I F O R N I A S T A T E A U D I T O R 15
Soon after the first depression appeared, maintenance crews
noticed similar depressions at three other locations on the
westbound side of the freeway. However, not until January 1996
did CalTrans realize that its drainage problems and the
pavement’s cracking were more than isolated occurrences; in
addition to the failure of the storm-drain system, high levels of
groundwater were present. Because the pipe joints were not
designed to withstand the amount of pressure associated with
the rising groundwater, the combination of these conditions
allowed sandy, silty soil to flow into the system, eroding the soil
and developing voids in the ground beneath the pavement.
CalTrans began several emergency repairs intended to prevent
further damage to the freeway, while District 7 and headquarters
units also began designing changes to the freeway drainage
system to counteract the effects of the high groundwater present
throughout this 3.5-mile section of freeway.
CalTrans Investigated Problems and Sought Expert Advice
for Possible Solutions
In its efforts to identify and address the problems it had
encountered on the Century Freeway, CalTrans used the
expertise of both in-house staff and outside consultants. In
1996, CalTrans initiated an in-house independent analysis
team, which was charged with determining the reasons behind
the roadway failure and recommending procedural changes to
prevent a recurrence of this type of failure. In addition, it
contracted with outside consultants to perform a value analysis
study and to identify possible solutions for the freeway
problems. This team, consisting of professional engineers from
CalTrans used a academia and industry, issued three value analysis reports.
combination of CalTrans also had its Engineering Service Center in Sacramento
in-house staff and prepare a geotechnical design report to evaluate the most viable
outside consultants options to remedy the groundwater problems.
to decide on the best
way to repair and CalTrans assembled the independent analysis team to evaluate
rehabilitate the freeway. the freeway’s design and construction. Its report, issued in
June 1996, identified the reasons behind the roadway’s failure,
and was critical in its acknowledgment of failures in the original
design, planning, and construction of the freeway. The team,
which consisted of members from a variety of CalTrans units,
including project development, maintenance, construction, and
roadway geotechnical engineering services, recommended
improved procedures to prevent a recurrence of this type of
failure. After its review of project documents and its discussions
with personnel from headquarters, District 7, and industry, the
16 C A L I F O R N I A S T A T E A U D I T O R
team identified the presence of groundwater as the main cause
of the roadway’s failure. In addition, the team recommended
that CalTrans obtain external experts to help identify and
analyze the possible solutions.
Following the team’s recommendations, CalTrans contracted
with outside consultants to explore the alternatives for repairing
the freeway. This consultant team issued three separate value
analysis reports from September 1996 through September 1997.
The studies evaluated the short-term corrective measures and
discussed the alternatives for a long-term solution. The first
report focused on determining the problems in the lowered
section of the freeway, and the repairs needed to the storm-drain
system. Building on this information, the second value analysis
report provided a strategy for controlling the rising groundwater
levels and the final report reviewed the recommendations in
CalTrans’ geotechnical design report on controlling groundwater
and devising a long-term strategy to the storm-drain problem.
Caltrans’ Engineering Service Center prepared the geotechnical
design report in September 1997 to represent its approach to
assessing and correcting groundwater problems. Once it received
comments from the value analysis team, CalTrans began the
permanent repairs in April 1998.
CalTrans Audits and Investigations Division Conducted a
Limited Review
In late 1998, CalTrans directed its Audits and Investigations
Division to survey the drainage system repair and replacement
Although not project. During the initial work, which took place while
contributing to the CalTrans was excavating and replacing the drainage system, the
failure of the freeway(cid:146)s auditor found two instances in which improper construction
original drainage methods may have been used in the original construction of the
system, a CalTrans freeway. In one of the instances, workers had applied concrete
auditor found one over sandbags during construction of a drain inlet. The other
instance of an improper instance was the possible use of improper joint fasteners on the
construction technique. pipes in the drainage system.
According to District 7 staff’s research of the sandbag issue, the
concrete poured over sandbags was not an acceptable construc-
tion technique, and, presumably, the concrete was not visible to
inspectors during original construction because of the depth of
the trench in which the sandbags lay. The sandbags should only
have supported the form into which the workers were to pour
the concrete. District 7 staff also noted that when repair workers
fixed this portion of the drainage system and excavated this
C A L I F O R N I A S T A T E A U D I T O R 17
portion of the freeway, the burlap or containers showed
signs of deterioration. However, the chunks of sand under the
concrete wall did not exhibit the erosion, dislocation, or dis-
placement that they would have shown if the structure had
failed. Therefore, District 7 staff concluded that, although this
work did not meet CalTrans construction standards, it did not
contribute materially to the failure of the drainage system.
In investigating the possible use of improper joint fasteners,
District 7 staff found that the contractor had used, with the
approval of the resident engineer, an accepted alternative
technique to connect the pipes. According to evidence provided
by District 7, CalTrans staff had inspected the material at the
manufacturer and the resident engineer had approved its use on
the project. Since the material was inspected and approved in
accordance with established procedures, CalTrans concluded
that it needed to take no further action.
CalTrans Is Spending $67 Million to Correct Design Flaws on
the Century Freeway But Will Need Millions More to Solve Its
Groundwater Disposal Problem
Between March 1995 and December 1997, CalTrans spent
$22 million on emergency repairs to keep the Century Freeway
open. Although the emergency repairs are now complete, the
last of the three phases of the permanent repairs awaits imple-
mentation. The first phase involved the installation of 17 pump
wells on the north side of the freeway. Each pumping well has a
corresponding control well used to monitor groundwater levels
Emergency repairs to near the pavement surface, along the shoulders. If the ground-
keep the Century water comes within three feet of the pavement surface, the
Freeway open cost pump wells automatically pump water until it drops below the
$22 million. three-foot threshold. To date, CalTrans has only had to use five
of the pump wells.
The second phase encompassed compaction grouting in the
freeway median. Compaction grouting uses a stiff mixture of
cement mortar pumped through small holes in the freeway, and
this mixture fills the voids in the soil and establishes a stable
base below the surface of the freeway and the median. Workers
completed additional grouting around the drainpipes to seal the
drainage system from further soil and water infiltration.
CalTrans completed this phase in December 1998.
18 C A L I F O R N I A S T A T E A U D I T O R
In the final phase of the permanent repairs, CalTrans will
use high-density polyethelene pipe in constructing a new
storm-drain system at a higher elevation than the old system.
According to CalTrans, this pipe is highly flexible and can be
welded, characteristics that eliminate the need for joint seals.
The department believes this pipe has an advantage over the old
system of corrugated steel and reinforced concrete pipes because
water or soil cannot permeate the joints. The storm drains
will be replaced in three phases. Workers will replace the
storm drains around the Ardis pump plant first. At the end
of May 1999, this work was near completion. The next replace-
ment of the storm drains is around the Downey pump plant.
Construction was scheduled to begin June 1999. The drains
at the last two pump plants, Woodruff and Garfield, will be
replaced last. CalTrans has scheduled construction at these
plants to begin April 2000. See Figure 1 on page 5 for the
locations of the pump plants.
We determined that CalTrans has spent $10 million for the
Emergency and permanent repairs completed thus far, with another $1.4 million
permanent repairs available to spend. In addition, CalTrans recently requested
will total $67 million(cid:151) that the California Transportation Commission (commission)
13 percent of the approve an allocation of $7.6 million for the second of the
original cost to storm-drain replacement projects. CalTrans estimates it will need
construct the 3.5-mile another $26 million for the final phase of the storm-drain
section. replacement. The cost of repairs has added about $67 million to
the $2.4 billion cost to construct the entire freeway. We estimate
that CalTrans spent, on average, $137 million per mile to con-
struct the Century Freeway; therefore, the 3.5-mile lowered
section could have cost roughly $480 million. The costs to repair
this lowered section of the Century Freeway are approximately
13 percent of the original cost of its construction.
Since September 1996, CalTrans has requested Emergency Relief
funds from the FHWA for repairs on the freeway. In a letter
dated June 30, 1999, FHWA denied the request from CalTrans for
Emergency Relief funds for the permanent repairs. The agency
approved the eligibility of the emergency repairs for funding
through Emergency Relief funds. FHWA informed CalTrans that
the new storm-drain system could be constructed using conven-
tional federal highway funding. As of July 21, 1999, CalTrans
had not received funding from FHWA for the emergency repairs.
C A L I F O R N I A S T A T E A U D I T O R 19
The Problem of Groundwater Disposal Remains Unresolved
and Will Add to CalTrans’ Costs
CalTrans has yet to determine what it will do with the ground-
water it pumps from beneath the lowered section of the Century
Freeway. CalTrans is currently identifying the specific options
available, their feasibility, and the costs associated with each. In
order to maintain the integrity of the roadway, CalTrans must
CalTrans is currently keep groundwater levels three feet below the pavement.
identifying specific CalTrans is using 5 of its 20 dewatering wells to keep the levels
options available, their down. The wells pump the water into the Los Angeles County
feasibility, and storm-drain system, which flows into the San Gabriel and
associated costs of Los Angeles rivers. In developing a permanent diversion system
each. for the water, CalTrans must acquire its own or partner with an
entity that has water rights, assure the quality of the water, and
arrange for proper disposal.
In the early 1960s, water rights in the Central Basin were legally
assigned to specific entities to halt excessive pumping. Each
pumper received the rights to a certain number of acre-feet of
water per year. Currently, the State has rights to 50 acre-feet of
water per year but it has assigned none of these rights to
CalTrans. Although CalTrans lacks water rights in the Central
Basin, it continues to pump the water to stabilize the roadway
and ensure public safety. As of May 1, 1999, CalTrans had paid,
under protest, more than $370,000 in pump taxes to the Water
Replenishment District of Southern California on the 2,428 acre-
feet of groundwater it has pumped out from under the freeway.
Because CalTrans is pumping water, which eventually discharges
into a public waterway, it must have a National Pollutant
Discharge Elimination System permit. In September 1996, the
Los Angeles Regional Water Quality Control Board issued this
permit to CalTrans for the four initial pump test wells. To draw
down the groundwater levels, CalTrans turned on 2 of the 4
original wells in October 1997. The board extended the dis-
charge permit in December 1997 to include the construction of
17 new wells. Since installation of the wells, CalTrans has used
only five wells when water levels exceeded the three-foot buffer
zone.
According to our review of water quality data and discussion
notes provided by CalTrans’ Audits and Investigations Division,
Tricholroethylene and other pollutants contaminate the water
being discharged from some wells. In order to comply with the
requirements of its discharge permit, CalTrans began treating
20 C A L I F O R N I A S T A T E A U D I T O R
this water with temporary filters in February 1999. However, in
The significant amount February and March 1999, CalTrans performed no testing of the
of water pumped from treated water to determine if the contaminant levels were within
beneath the freeway is acceptable levels for disposal. In May, the department installed
currently discharged two permanent filters, one on either side of the freeway at the
into the county storm- Garfield pump house. During the filter installation, CalTrans
drain system and lost. analyzed the water it pumped before and after it was treated.
However, water analysis from one of the five wells indicated
that the Tricholroethylene levels were still not within
acceptable standards even after treatment. Effective May 1999,
the treated water is tested at the point of discharge. Even though
the water from one of the wells is contaminated, by the time
CalTrans discharges it to the county storm-water system, the
water has blended with water from uncontaminated wells. It is
at this point that CalTrans now tests the water for contaminates.
Testing the water quality in this way meets the requirements of
the long-term discharge permit issued by the Regional Water
Quality Control Board in July 1999.
A more difficult problem for CalTrans to resolve is what to
do with the groundwater that was part of the basin recharge
activity. CalTrans is currently evaluating three options for
disposal of this water. One option is to acquire water rights to
pump the water. Using figures for the most recent amount of
groundwater CalTrans has pumped, we estimate that CalTrans
will extract nearly 2,700 acre-feet of water annually. Thus the
projected cost to purchase water rights would be $7.2 million,
and the annual pump tax would be more than $370,000. This
option presumes CalTrans would propose discharging ground-
water into the river systems as a long-term solution. However,
CalTrans has always proposed the reuse of this water as a
long-term solution and has no plans to pursue this option.
Another option is for CalTrans to construct a water treatment
facility in partnership with the City of Downey. CalTrans is
currently working with the City of Downey to prepare a feasibil-
ity study for this facility. According to CalTrans, capital costs
for building a water treatment facility could be $40 million to
$50 million, with operating costs of $5 million annually. Under
this option, the City of Downey would use its water rights to
extract the groundwater and then pay the pump tax.
The third option is for CalTrans to construct a pipeline to carry
water from the Century Freeway to Long Beach. Like the City of
Downey in the second option, Long Beach would use its water
rights and pay the pump tax. CalTrans is in the process of
C A L I F O R N I A S T A T E A U D I T O R 21
reviewing this proposal, which could require that the quality of
the water CalTrans delivers be of the same quality as the water
the city currently extracts with its own wells. In addition,
Long Beach might require CalTrans to deliver the same amount
of water in the summer as in the winter, regardless of the
amount needed to keep the groundwater three feet below the
freeway pavement.
CALTRANS EXERTED SOME EFFORTS TO INFORM
THE COMMISSION, LEGISLATORS, AND THE PUBLIC
ABOUT CENTURY FREEWAY PROBLEMS
To investigate concerns that it had withheld information about
its problems with the Century Freeway, we assessed CalTrans’
communications with legislators, the public, and the California
Transportation Commission (commission) and found that the
CalTrans acknowledges agency covered some information about these problems.
that it could have CalTrans, however, has acknowledged that it could have done
done more over the more over the past three years to inform the Legislature of
past three years to problems on the Century Freeway.
inform the Legislature
of what was happening. CalTrans informed Los Angeles area legislators about the freeway
problems during District 7’s annual legislative briefings. Accord-
ing to the acting district director, each year District 7 manage-
ment meets with area legislators or their staff to discuss projects
affecting their districts. Consequently, only those legislators
whose districts the freeway runs through would have received a
briefing. CalTrans’ records show that between May 1995 and
May 1999, it held meetings with area legislators; however, these
records do not consistently describe what participants specifi-
cally discussed at these meetings. In February 1998, CalTrans
held at least three meetings with legislators at which the
Century Freeway repair project was one of several projects listed
on the agenda.
In addition, we found that over the past three years, CalTrans
briefed local governments; issued press releases to local news
stations, radio stations, and local and major newspapers on
traffic lane closures; and responded to written requests for
information from the general public. Since the discovery of the
first cracking and sunken sections of the freeway, CalTrans has
issued 24 press releases notifying the public of the road closures
and problems.
22 C A L I F O R N I A S T A T E A U D I T O R
On the other hand, CalTrans was not always prompt when
notifying the commission about emergency allocations of
funding to repair the freeway. CalTrans did follow proper
protocol when it presented to the commission its requests for
funding allocations for repairs. The department used three
CalTrans was not always methods for requesting funds. For the emergency repairs,
prompt in notifying the CalTrans used authority delegated to its director by the commis-
commission of sion. This authority allows allocations of funds for emergency
emergency allocations projects with the understanding that CalTrans will report these
to repair the freeway. allocations to the commission at its next meeting. However,
CalTrans did not always notify the commission at its next
scheduled meeting. Although the commission reprimanded
the agency in May 1996, CalTrans continued to be late in
notifying the commission about emergency projects. According
to CalTrans and the commission, the department’s internal
process for requesting funds created the time lags. Most recently,
the commission instituted a new reporting process to improve
the timing of these notifications.
In addition, CalTrans must report to the commission’s executive
secretary any emergency project estimated to cost over $400,000
at the time the director approves the project. In all but one
instance, CalTrans properly notified the commission’s executive
secretary of these emergency projects.
The two other methods CalTrans used were the State Highway
Operations and Protection Program (SHOPP) and the SHOPP
amendment process. The SHOPP is a four-year program of
projects related to traffic safety, roadway rehabilitation, roadside
rehabilitation, or operations of the State highway system.
CalTrans prepared the SHOPP and presented it to the commis-
sion for approval. At any time after the commission approves
the four-year SHOPP, CalTrans may make necessary amend-
ments. CalTrans used the SHOPP and SHOPP amendment
processes to request allocations for the permanent repairs of the
Century Freeway, and the department presented all amendments
to the commission for approval.
CalTrans’ director appropriately informed the commission of
his requests, which included any amendments necessary for
requests for emergency repairs. In addition to notifying the
commission of the funding requests, CalTrans briefed the
commission at least twice about the problems with the Century
Freeway. The first briefing took place at the commission’s
meeting on March 28, 1996. CalTrans explained that it did not
know the extent of the problem but that it was encountering a
C A L I F O R N I A S T A T E A U D I T O R 23
substantial amount of groundwater. Further, CalTrans reported
initiating the emergency repairs needed to keep the freeway
open until it could find out what was causing the underlying
problem.
In the second briefing, which took place on May 5, 1999,
CalTrans gave the commission a presentation on the Century
Freeway groundwater issue, the department’s response, and the
additional work necessary to correct the problems. CalTrans
informed the commission that it was working on the permanent
repairs, with two more phases of the storm-drain replacement
to complete. CalTrans also briefed the commission about
the groundwater disposal dilemma. At the meeting, the commis-
sion requested that CalTrans give updates at each of the
commission’s monthly meetings. Our review of the next
meeting on June 6, 1999, indicated that CalTrans complied with
the commission’s request.
THE INDEPENDENT ANALYSIS TEAM PROMPTED
CALTRANS TO CHANGE SOME PROCESSES
In June 1996, the in-house independent analysis team assembled
by CalTrans concluded that inadequate procedures compounded
the problems with the lowered section of the Century Freeway.
Most importantly, CalTrans had not done extensive groundwa-
ter testing. In addition, CalTrans’ Highway Design Manual
contained inadequate procedures for the use of watertight joints,
and its Construction Manual lacked appropriate procedures to
follow when workers encounter groundwater during excavation.
Based on the investigation, the team made a series of recom-
mendations to avoid a recurrence of similar problems on future
projects.
In August 1996, the independent analysis team developed a
Although implementing plan to implement its recommendations, which identified the
all recommendations of planned action, the unit responsible for implementing the
the independent corrective action, and a target date for completion. As one of the
analysis team, changes first steps in responding to the recommendations, CalTrans
needed in the revised its Highway Design Manual to include the use of water-
construction and tight joints for submersible pipes. In addition, in May 1998, to
maintenance manuals improve communication among CalTrans’ various units, the
were delayed. Project Development Unit in Sacramento began holding
training and information seminars on the responsibilities of
various units within CalTrans.
24 C A L I F O R N I A S T A T E A U D I T O R
As of July 1999, CalTrans had implemented all the recommenda-
tions made by the independent analysis team. However, either
due to low priority or a lack of monitoring, CalTrans construc-
tion and maintenance units were neither prompt nor timely
in implementing their changes. Specifically, the construction
unit did not circulate revisions to the Construction Manual
regarding groundwater until July 1999, 2.5 years after the
targeted completion date for the manual revision. Also, until
May 1999, the maintenance unit had not completed a revised
policy related to obtaining support from other units even
though CalTrans targeted this item for completion two years
earlier. A lack of regular status reports by the CalTrans units
responsible for implementing new procedures compounded
the delays in the department’s putting the recommendations
into practice. By not closely monitoring its progress in complet-
ing the recommended changes, CalTrans risks the potential of
making similar mistakes on other projects.
RECOMMENDATIONS
CalTrans should inform the Legislature, through its Senate and
Assembly Transportation committees, as well as the California
Transportation Commission about the department’s progress in
determining an environmentally sound and cost-effective
method for reusing the groundwater pumped from under the
Century Freeway.
CalTrans should continue working with the Water Replenish-
ment District of Southern California to coordinate actions so
that neither agency jeopardizes the other’s efforts to fulfill its
organizational mission.
To ensure that it properly puts into practice the recommenda-
tions from special in-house staff reports, CalTrans should ensure
that the unit designated to implement these recommendations
periodically reports its progress to agency management.
C A L I F O R N I A S T A T E A U D I T O R 25
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
KURT R. SJOBERG
State Auditor
Date: August 25, 1999
Staff: Steven M. Hendrickson, Audit Principal
Nancy C. Woodward, CPA
Dawn Tomita
Vikram Mandla
26 C A L I F O R N I A S T A T E A U D I T O R
C
A
L
I
F
O
R
N
I
A
S
T
A
T
E
A
U
D
I
T
O
R
27
APPENDIX
Events Related to Construction and Repair of the Century Freeway
Initial Freeway Proposal Through Freeway Completion
Memo concluded that construction Materials unit recommended Headquarters Transportation Excavation halted at the
of a lowered section was possible underdrain system to control Lab report revealed higher Ardis pump house because of
with major drainage systems to groundwater, but warned that groundwater levels than groundwater; four deep
control groundwater and the the system would be ineffective earlier tests indicated. dewatering wells installed
memo recommended extensive against groundwater at to pump out water.
testing of area groundwater. historic high levels.
Geotechnical report focused Headquarters Transportation
on anticipated effects of Lab reported groundwater
earthquake activity on freeway rise of 5.2 feet during
site. No additional data on preceding two years.
Project added to groundwater provided.
Interstate system.
Lawsuit filed to Consent Freeway
Initial freeway block construction decree Actual construction of opened
proposal. of freeway. issued. the freeway began. to public.
Oct Feb Jun Apr Oct May May Jul Oct
1958 1968 1969-70 1972 1973 1974 1979 1981 1982 1983 1985 1986 1987 1990 1993
Aug Sep Jul Sep Feb Sep Aug
Public hearings Consent Work resumed
held. decree at Ardis
Hydraulics report Court injunction required amended. Federal law required pump house.
warned of possible Environmental Impact new Interstate routes
rise in groundwater Study and additional to be substantially
to levels near public hearings. under construction.
historic high.
Caltrans concluded that a lowered Final Materials report did Construction of
section of freeway was not feasible not indicate additional testing drainage system began
east of Alameda Avenue for groundwater; design for for the freeway section
because of groundwater conditions. containing groundwater unchanged. below ground level.
Aug
28
C
A
L
I
F
O
R
N
I
A
S
T
A
T
E
A
U
D
I
T
O
R
Opening of Freeway Through Completion of Repairs
Memo from Caltrans Emergency repair order to
maintenance described Second emergency repair order expand scope of work to repair
the continued deterioration to replace pipe and pavement. damaged drainage systems.
of conditions.
Pumping at one of the pump
houses increased dramatically
even though no rainfall had occurred.
Sunken sections of
pavement developed at
Groundwater leakage through Bellflower on-ramp, and
pump house walls noted at four this problem lead to Four emergency repair orders
separate locations at Ardis site. pavement failure. requested to repair damage,
stabilize the base of the freeway,
and replace damaged
Freeway opened
drainage systems.
for traffic.
Oct Jul Dec Mar May Feb May
1993 1994 1994 1994 1994 1995 1995 1995 1995 1995 1996 1996 1996 1996
Jan Sep Jan - Mar Apr Oct Mar Jun
Northridge earthquake. Heavy periods of rain. Also, Third emergency repair order Three emergency repair
Inspection of pumps revealed Los Angeles Flood Control to clean drains, conduct orders requested
cracks in the pump house closed floodgates, causing video and radar inspection, repair of damage
walls at Ardis. storm system to backup. and grouting. on roadway.
Two emergency repair orders
Number of leaks at Ardis First emergency repair
requested identification and repair increased to eight and sediment order to repair the sunken
of damaged drainage systems
was being carried with the seepage. section of pavement.
and roadway.
C
A
L
I
F
O
R
N
I
A
S
T
A
T
E
A
U
D
I
T
O
R
29
Permanent Repairs
Compaction grouting
CalTrans' Engineering Service
of median began.
Center issued the final report
evaluating alternatives to Purchase and installation of
remediate conditions and two permanent filter systems
implement permanent repairs. along the freeway.
Cooperative agreement between
Independent analysis team Installation of temporary Caltrans and City of Downey prepared
published report on causes of Installation of pump filters to treat the for feasibility study on the reuse
Century Freeway failure. wells began. pumped groundwater. of groundwater from the freeway site.
Jun Sep Apr Sep Feb May Jul
1996 1996 - 1997 1997 1998 1998 1998 1998 1998 1999 1999 1999 1999 1999 2000
Aug Sep - Sep Apr Jul Dec Mar Jun Apr
Peer review team issued Phase 1 of the storm- City of Long Beach submitted Target date for beginning
series of three reports evaluating drain replacement began. conceptual proposal regarding Phase 3 of the storm-
Caltrans' repair strategies. reuse of the groundwater. drain replacement.
Independent analysis Initial meeting with City of Downey CalTrans began pumping Phase 2 of the storm-
team developed an to discuss groundwater issues. out groundwater. drain replacement began.
implementation plan.
30 C A L I F O R N I A S T A T E A U D I T O R
Agency’s response provided as text only.
Business, Transportation and Housing Agency
980 9th Street, Suite 2450
Sacramento, CA 95814-2719
August 18, 1999
Kurt R. Sjoberg, State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Dear Mr. Sjoberg:
As the Secretary of the Business, Transportation and Housing Agency, I am pleased to
receive and respond to your draft audit report entitled “Department of Transportation:
Disregarding Early Warnings Has Caused Millions of Dollars to Be Spent Correcting
Century Freeway Design Flaws.” While the origin of the Century Freeway issues date
back three decades, responsive and prudent action must be taken to address this issue.
Attached, please find the Department of Transportation’s (Caltrans) response to your
draft report. The Caltrans response indicates that they have reviewed the issues raised
in the audit report and concur with the report’s recommendations.
As you have pointed out in the report, Caltrans has not yet solved the groundwater
disposal problem. Because of the differing organizational missions of the local water
replenishment agency and Caltrans, options are being considered which meet their needs
while ensuring the safety of users of the Century Freeway. The options being considered
must also include a comprehensive cost analysis of each approach. The Business,
Transportation and Housing Agency will facilitate discussions among the key stakeholders
including the Water Replenishment District of Southern California, the California Resources
Agency, the State Water Resources Department, and other affected agencies to discuss
the issue of beneficial groundwater reuse and disposal and make recommendations to
the Governor.
C A L I F O R N I A S T A T E A U D I T O R 31
Page 2
State Auditor
Report No. 99113
I want to thank your audit staff for their professionalism and quality of their work. If you
have any questions, please let me know.
Sincerely,
(Signed by: Maria Contreras-Sweet)
MARIA CONTRERAS-SWEET
Secretary
Attachment
32 C A L I F O R N I A S T A T E A U D I T O R
Agency’s response provided as text only.
DEPARTMENT OF TRANSPORTATION
OFFICE OF THE DIRECTOR 1120 N STREET
P. O. BOX 942873
SACRAMENTO, CA 94273-0001
PHONE (916) 654-5267 FAX (916) 654-6608
August 17, 1999
MARIA CONTRERAS-SWEET, Secretary
Business, Transportation and Housing Agency
980 - 9th Street, Suite 2450
Sacramento, CA 95814
Dear Secretary Contreras-Sweet:
I am pleased to provide our response to the California State Auditor’s
report and adopt the following three recommendations:
1. To keep the Legislature and the California Transportation Commission
informed of CalTrans’ progress in determining an environmentally sound and
cost-effective reuse of the groundwater pumped from under the Century
Freeway.
2. To continue working with the Water Replenishment District of Southern
California to coordinate actions to avoid undermining each other’s efforts to
fulfill their organizational mission
3. To ensure in-house staff report recommendations are assigned to a
responsible unit for implementation and periodically reports the progress to
departmental management.
To add clarification to the report I suggest the following changes:
1*
1. The title of the audit report should be changed to read: “Unexpected
Occurrences Caused Millions of Dollars to be Spent on Corrective Measures
to the Century Freeway”. I believe this much more accurately characterizes
the facts detailed in the report.
2
2. In the Summary section, page 1, first paragraph, and second sentence change
from, “CalTrans discovered pavement cracking and sinkholes” to read,
“Caltrans discovered pavement cracking and depressions”.
*California State Auditor’s comments on this response appear on page 39.
C A L I F O R N I A S T A T E A U D I T O R 33
Secretary Contraeras-Sweet
August 17, 1999
Page 2
3. In the Summary section, page 1, first paragraph, last sentence change from,
3
“…it had not designed the lowered section of the freeway to” to read, “…it
had not incorporated enough design features in the lower section of the
freeway to”.
4. In the Summary section, page 1, second paragraph, first sentence change
4
from, “prevented design flaws in the 3.5-mile lowered section” to read, “the
problems in the 3.5-mile lowered section”.
5. In the Summary section, page 1, second paragraph, second sentence change
4
from, “CalTrans disregarded the 1968 recommendations of its staff ” to read,
“A CalTrans team evaluated recommendations from one member of its staff
and implemented those that were deemed reasonable at the time”.
6. In the Summary section, page 1, last paragraph, the last sentence should be
2
deleted. This sentence as worded makes an assumption of the results of
testing. The testing would have identified that the groundwater had risen,
but it’s not reasonable to assume that the rising ground water would have
threatened the freeway. Identification of rising groundwater would have
triggered more tests. Based on the results of these tests, other steps would
have been taken.
7. In the Summary section, page 2, first paragraph, and third sentence change
4
from, “encountering a lot of water” to read “encountering groundwater”.
8. In the Summary section, page 2, last paragraph, the third sentence should
4
be changed to read, “While CalTrans continues to adhere to the existing
National Pollution Discharge Elimination System Permits (NPDES), by treating
groundwater discharged to the Los Angeles and San Gabriel Rivers, it is
currently not beneficially being re-used”.
9. In the Summary section, page 2, last paragraph, the fourth sentence should
4
be deleted due to the suggested changes in the third sentence (See
suggestion 8 above).
10.In the Summary section, page 3, second paragraph, second sentence change
4
from, “However, some information…” to read “However, information…”.
11.In regards to the Introductory - Background section, page 2 and last paragraph,
2
discussing WRD’s efforts. I believe WRD’s water restoration efforts should
also be discussed in the Summary section in the beginning of the report so
that all issues are addressed at the start. This would be of great benefit to
the reader of the report.
34 C A L I F O R N I A S T A T E A U D I T O R
Secretary Contraeras-Sweet
August 17, 1999
Page 3
12.In the Introductory - Background section, page 3, second paragraph, and
3
second sentence change from, “…a freeway is constructed below ground
level since it also removes groundwater from the surrounding area so it does
not erode or weaken the roadbed” to read, “…a freeway is constructed in an
area of high groundwater, since it also will be required to remove groundwater
from the surrounding area so it does not erode or weaken the roadbed”.
13.In the Introductory - Background section, page 3, second paragraph I
3
recommend adding the following statement, “To mitigate the effects of a natural
groundwater rise, Caltrans installed a 6” perforated pipe subdrain, located
above the storm drain pipes to collect and discharge the groundwater.”
14.In the Introductory - Background section, page 3, third paragraph, and first
2
sentence change from, “and sinkholes developed” to read “and depressions
developed”. Sinkholes never developed. At the Paramount on-ramp area, a
depression on the pavement developed, not a sinkhole.
15.In the Introductory - Background section, page 3, second paragraph, and
5
third sentence change from, “…to a depth of 30 feet.” to read “…to a depth of
30 feet below the freeway surface”.
16.In the Summary section, page 1, change from, “CalTrans Has Worked to
6
Correct Design Flaws on the Century Freeway, But Has Not yet Solved its
Groundwater Disposal Problem” to read, “Caltrans Has Worked on
Implementing Corrective Measures on the Century Freeway, and is Working
to Solve the Groundwater Disposal Problem”.
17.In the Summary section, page 1, and end of first paragraph, add the following,
7
“Much of this cost can be eliminated if an agreement can be reached with
WRD to maintain the water table elevation at a minimum of three feet below
the pavement surface. Maintaining this water level would eliminate the need
to pump groundwater”.
18.In the Summary section, page 1, second paragraph regarding WRD’s water
7
restoration efforts, it should be noted in this paragraph that at the Senate
Transportation Agency, WRD testified that the current water table elevation
is adequate, and they do not have any plans to continue to cause the
groundwater to rise.
19.In the Summary section, page 2, second paragraph, last sentence change
3
from, “Beyond incorporating a modified drainage system into the design,
CalTrans did not …” to read, “Beyond incorporating a modified drainage
system, to address the natural groundwater rises, Caltrans did not … ”
C A L I F O R N I A S T A T E A U D I T O R 35
Secretary Contraeras-Sweet
August 17, 1999
Page 4
20.In the Summary section, third paragraph, the third and fourth sentences should
3
be change from “groundwater levels rose substantially between 1968 and
1990. If CalTrans had performed the testing its staff recommended in 1968,
and retested when the extension was designed, CalTrans could have adjusted
the final freeway design accordingly” to read, “groundwater levels rose
substantially between 1968 and 1990; but, there were periods of decline as
well. Specifically between the mid-1980’s to 1990, there was a significant
decline in the level of groundwater. Additional testing may not have provided
information indicating a need for design adjustment.” It should be noted that
WRD indicated that it takes approximately seven years, after water
replenishment efforts, before the water reaches the Century Freeway corridor.
Therefore, as stated earlier, it is not reasonable to assume that the additional
testing would have identified and accounted for the unexpected occurrences
encountered.
21.In the Summary section, page 6, third paragraph, second sentence change
3
from, “When digging at the site, Caltrans had to install four dewatering wells”
to read “While it is not uncommon to encounter groundwater during
construction when digging at the site, Caltrans had to install four dewatering
wells”.
22.In the Summary section, page 10, first paragraph, second sentence, it should
3
be stated “September 1997” in lieu of “August 1997”.
23.In the Summary section, page 11, third paragraph, introductory heading
6
change from, “CalTrans is Spending $67 Million to Correct Design Flaws…”
to read “CalTrans is Spending $67 Million to Implement Corrective Measures”.
24.In the Summary section, page 13, second paragraph, second sentence
3
change from, “but approved the eligibility of the emergency repairs for funding”
to read “but approved the eligibility of the emergency Relief Funds”.
25.In the Summary section, page 13, third paragraph, fourth sentence change
3
from, “17 dewatering wells” to read “20 dewatering wells”.
26.In the Summary section, page 14, third paragraph, second sentence,
4
“However, from January through March 1999, CalTrans performed no
testing of the treated water to determine if the contaminate levels were
within acceptable levels of disposal” should be deleted since during that
time period, Caltrans did not have all five pumps operating. Only one
pump was essentially operating on an emergency basis to protect the
36 C A L I F O R N I A S T A T E A U D I T O R
Secretary Contraeras-Sweet
August 17, 1999
Page 5
pavement at the specific location. Within that time period, Caltrans was
working closely with the Regional Water Quality Control Board (RWQCB) to
implement a temporary water treatment system in order to turn on five pump
wells. Caltrans was able to place a temporary treatment system by March
1999. Caltrans began to monitor the water quality data of the treated water
on a monthly basis.
27.In the Summary section, page 15, second paragraph, the fifth and sixth
2
sentences should be deleted and replaced with the following: “This option
would presume Caltrans would propose discharging groundwater into the
river systems as a long-term solution. Caltrans has always proposed the
reuse of this water as a long-term solution and has no plans to pursue this
option”.
28.In the Summary section, page 15, third paragraph, first sentence change
3
from, “Another option is that CalTrans could construct a water treatment facility
in the City of Downey.” to read, “Another option is that Caltrans could partner
with the City of Downey to construct a water treatment facility.”
29.In the Summary section, page 15, last paragraph, I recommend that the
7
following statement be added: “CalTrans is actively working to reach an
agreement with WRD to manage the water basin in a manner to maintain the
groundwater level at three feet below the pavement. Assuming such an
agreement can be reached, the need to pump and dispose of groundwater
would be eliminated.”
30.In the Summary section, page 16, third paragraph I recommend that this
4
statement be included: “Specific letters about the groundwater issue were
received and CalTrans routinely answered those at the time.”
If we can provide any further information, or if you have any questions,
please do not hesitate to contact me.
Sincerely,
(Signed by: Jose Medina)
JOSE MEDINA
Director
C A L I F O R N I A S T A T E A U D I T O R 37
Page left blank intentionally.
38 C A L I F O R N I A S T A T E A U D I T O R
COMMENTS
California State Auditor’s
Comments on the Response From
the Department of Transportation
T
o provide clarity and perspective, we are commenting on
the Department of Transportation’s (CalTrans) response
to our audit report. The number corresponds to the
number we placed in CalTrans’ response.
1
We disagree with CalTrans suggestions to change the title. We
believe that the title accurately reflects the findings in our
report.
2
After considering CalTrans’ suggestion, we agreed to reword
these sentences.
3
As was previously discussed with CalTrans, we made some
modifications in the text, which is reflective in the report.
4
After considering CalTrans’ suggestion, we believe that clarifica-
tion is not necessary. Therefore, no modification was made to
the report.
5
During our editing of this report, we deleted the reference
“depth of 30 feet.”
6
We disagree with CalTrans’ suggestion to change the subhead-
ing. We believe that the subheading accurately reflects the
contents in the report.
7
As stated in our recommendations, CalTrans should continue
working with the Water Replenishment District to coordinate
actions so that neither agency jeopardizes the others’ efforts to
fulfill its organizational mission.
C A L I F O R N I A S T A T E A U D I T O R 39
cc: Members of the Legislature
Office of the Lieutenant Governor
Attorney General
State Controller
Legislative Analyst
Assembly Office of Research
Senate Office of Research
Assembly Majority/Minority Consultants
Senate Majority/Minority Consultants
Capitol Press Corps
40 C A L I F O R N I A S T A T E A U D I T O R