CSA
Summary
Read the report at California State Auditor ↗
San Francisco
Public Utilities
Commission:
Its Slow Pace for Assessing Weaknesses in Its
Water Delivery System and for Completing
Capital Projects Increases the Risk of Service
Disruptions and Water Shortages
February 2000
99124
The first copy of each California State Auditor report is free.
Additional copies are $3 each. You can obtain reports by contacting
the Bureau of State Audits at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
Permission is granted to reproduce reports.
C S A
ALIFORNIA TATE UDITOR
MARY P. NOBLE STEVEN M. HENDRICKSON
ACTING STATE AUDITOR CHIEF DEPUTY STATE AUDITOR
February 17, 2000 99124
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its audit report
concerning our evaluation of the methods employed by the San Francisco Public Utilities Commission
(commission) to assure an adequate, long-term, and reliable water supply for its Bay Area customers. This
report concludes that the commission has been slow to assess and upgrade its water delivery system to
enable it to survive catastrophic events such as earthquakes, fires, or floods. The commission has also been
slow to estimate the amount of water it will need to meet demand in the future and to seek additional sources
of water. As a result, the nearly 2.4 million customers in the City and County of San Francisco, and in
Alameda, San Mateo, and Santa Clara counties who rely on the commission for their drinking water are at
greater risk of disruptions and water shortages in the event of a catastrophe or a drought.
The commission’s capital improvement plan currently lists about 200 capital projects requiring more than
$3 billion to complete. The commission plans to complete most of these projects over the next 15 years. In
the past 10 years, however, the commission completed 54 capital projects at a cost of about $270 million.
Several factors contributed to the commission’s inability to complete capital projects more quickly. For
instance, the commission believes that insufficient staffing to manage the projects is a major factor. Other
deficiencies that contribute to the slowness are inefficient contracting procedures, outdated project
operations manuals, weak project monitoring, and inadequate project management training.
The commission acknowledges that it lacks the tools to streamline project development or to control such a
large capital improvement program. Therefore, it has taken several measures to address the deficiencies.
However, its ability to ensure a sufficient, long-term and reliable water system remains uncertain since most
of these measures are still in development or were recently finalized.
Respectfully submitted,
MARY P. NOBLE
Acting State Auditor
BUREAU OF STATE AUDITS
555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019
CONTENTS
Summary 1
Introduction 5
Audit Results
It Is Uncertain Whether the Actions of the
Public Utilities Commission Will Improve
the Water Delivery System’s Reliability 17
Recommendations 32
Appendix
Abbreviated Organizational Chart for the
San Francisco Public Utilities Commission 35
Response to the Audit
San Francisco Public Utilities Commission 37
California State Auditor’s Comments
on the Response From the
San Francisco Public Utilities Commission 43
SUMMARY
RESULTS IN BRIEF
T
he San Francisco Public Utilities Commission (commis-
Audit Highlights . . . sion) has been slow to assess and upgrade its water
delivery system so it can survive catastrophes such as
Our review of the
earthquakes, floods, and fires. It also has been slow to estimate
San Francisco Public
the amount of water it will need to meet future demand
Utilities Commission
(commission) disclosed: and to seek additional sources of water. As a result, the nearly
(cid:1) 2.4 million customers in four Bay Area counties who rely on the
The commission has
commission for their drinking water are at greater risk of
been slow to assess its
water delivery system disruptions and water shortages if an emergency or a
and has made little drought occurs.
progress in completing
capital projects aimed
The commission is part of the City and County of San Francisco.
at improving
system reliability. Among other responsibilities, it provides drinking water to retail
customers in San Francisco and to 28 wholesale suppliers serving
(cid:1)
Since 1994, the
parts of San Mateo, Santa Clara, and Alameda counties. Using a
commission has known
that it needs to identify complex system of dams, reservoirs, treatment plants, pump
additional sources of stations, tunnels, pipelines, and valves, the commission trans-
water, yet it did not begin
ports much of its water to the Bay Area from Hetch Hetchy
to develop a water supply
Reservoir in Yosemite National Park, almost 150 miles away.
plan until 1996;
completion of the plan
is not expected until Some parts of the commission’s water delivery system, such as
March 2000.
critical pipelines, are nearly 75 years old and are in dire need of
(cid:1) repair or replacement. In addition, parts of the water delivery
Several factors contribute
to the commission’s slow system do not meet modern seismic standards. However, the
pace for completing commission did not begin to study the system’s overall reliabil-
capital projects, including
ity until 1994 and has completed only two of the study’s three
shortages of project
managers; out-of-date planned phases, with a delay of nearly three years between the
procedures for planning, completion of the first phase and the start of the second. This
designing, and
delay was due to the commission’s failure to appoint promptly a
constructing capital
staff member to manage the project and to problems with the
projects; inadequate
systems to track progress; contracting process.
and the absence of formal
training for project
The commission also has been slow to develop its water
managers.
supply master plan, which will estimate the amount of water
(cid:1)
The success of its capital needed in the future and recommend ways of acquiring more
improvement program is water. Although the commission has known since 1994 that it
uncertain because it is still
eventually will need to find additional sources of water, it did
developing some plans
while it has only recently not actively begin to develop the water supply master plan until
implemented others. 1996, and the results are not expected until March 2000.
C A L I F O R N I A S T A T E A U D I T O R 1
Further, some customers have expressed concern regarding the
commission’s slow pace in completing capital projects aimed at
upgrading its aging water delivery infrastructure. Information
provided by the commission shows that it completed 54 capital
projects at a cost of about $270 million in the last 10 years,
resulting in an average of five capital projects at a cost of
$27 million annually. Given the size, complexity, age, and
declining condition of the commission’s water delivery system,
this project completion rate appears low.
There are many reasons for the apparent slow pace in complet-
ing capital projects, ranging from a shortage of project managers
on staff to operational deficiencies such as a lack of up-to-date
procedures for awarding contracts and for planning, designing,
and constructing capital projects. Until recently, project manag-
ers also lacked an adequate system to track the progress of
capital projects and preventive maintenance. Finally, although
ongoing development is crucial to ensuring that staff members
stay abreast of industry changes and that they improve their
technical expertise, the commission is not providing any formal
project management training to staff members who manage
capital projects.
Although the commission is addressing the concerns with its
more than $3 billion capital improvement program, its success is
uncertain because it is still developing some plans while it has
implemented others only recently. For instance, the commission
seeks to hire a program management consultant to provide the
management services, specialized technical expertise, and staff
development assistance it needs to undertake its huge capital
improvement program. However, San Francisco’s budget analyst
is reviewing the proposed contract, and approval of this consult-
ant by the commissioners and the board of supervisors is by no
means certain.
For each of its three drinking water-related divisions, the
commission is developing capital improvement plans to
evaluate and prioritize the projects necessary to improve the
reliability of the water delivery system. The plan for the Hetch
Hetchy Water and Power Division, however, does not yet
contain cost or schedule estimates for all identified capital
projects. In addition, the commissioners have not yet adopted
the three plans.
2 C A L I F O R N I A S T A T E A U D I T O R
The commission also is working on a long-range financing
plan for its Water Supply and Treatment and City Distribution
divisions. This plan intends to show how the commission will
finance the capital projects for these two divisions. However, a
January 2000 report from the commission’s consultant relies
heavily on using voter-approved revenue bonds to finance the
projects and does not sufficiently describe contingencies should
San Francisco’s voters reject the bond measures. A similar
report covering the Hetch Hetchy Water and Power Division is
not yet complete.
Executive-level turnover at the commission and the time it will
take to fill these positions also contribute to the uncertainties.
The absence of strong, consistent leadership greatly diminishes
the commission’s chances of success in meeting the significant
challenges it faces in the near future, including the need to
implement a large-scale capital improvement program and to
obtain additional water supplies. On the other hand, turnover
among the commission’s executives also presents a unique
opportunity to build a management team that will provide the
leadership and expertise necessary to implement a cohesive
capital improvement program.
RECOMMENDATIONS
To ensure that the commission follows through on its plans, it
should submit reports annually to the Legislature and its subur-
ban customers for the next five years. These reports should
describe the progress the commission has made in implement-
ing each of its plans and the accomplishments it has achieved.
To improve the reliability of its water delivery system, the
commission should continue to finalize, adopt, implement,
monitor, and as necessary revise the plans and actions it has in
progress. In particular, it should:
(cid:127) Complete its facilities reliability study and its water supply
master plan.
(cid:127) Continue to address its operational deficiencies, including its
contracting procedures, project operations procedures,
tracking of capital projects, and tracking of preventive
maintenance.
C A L I F O R N I A S T A T E A U D I T O R 3
(cid:127) Develop and implement a formal training program for
project managers and ensure that staff members receive
adequate training while this program is being developed.
(cid:127) Be prepared to take alternative action if the commission or
the board of supervisors decides not to approve the contract
for its program management consultant.
(cid:127) Complete the capital improvement plans for its three
water-related divisions and seek formal approval from the
commissioners.
•
Develop a formal comprehensive plan to outline the
staffing requirements necessary to complete its capital
improvement plans.
•
Complete and adopt a long-range financial plan for the
Water Supply and Treatment Division, City Distribution
Division, and Hetch Hetchy Water and Power Division. In
addition, it should develop contingencies for its long-term
financial plan in case the voters fail to approve the bonds for
financing the capital improvements.
(cid:127) Given the size and complexity of the challenges it faces
in the near future, the commission should seize the opportu-
nity to appoint individuals who have effectively imple-
mented large-scale capital improvement programs. Further,
it should take measures to ensure that it fills available
positions promptly.
COMMISSION COMMENTS
The San Francisco Public Utilities Commission agrees with most
of our recommendations and did not fully address others. Our
comments follow the commission’s response. (cid:1)
4 C A L I F O R N I A S T A T E A U D I T O R
INTRODUCTION
BACKGROUND
T
he United States government enacted the Raker Act in
1913. This act granted to the City and County of
San Francisco certain rights of way and the use of public
lands in California to, among other things, construct, operate,
and maintain dams, reservoirs, and other structures for convey-
ing water for domestic uses. Under this act, San Francisco
obtained the right to build the Hetch Hetchy Reservoir in
Yosemite National Park to supply the city and county with
drinking water. San Francisco began receiving water from the
reservoir in 1934.
The San Francisco Public Utilities Commission (commission) is
part of the City and County of San Francisco. Its mission is to
supply its customers with reliable, high-quality, and affordable
water while responsibly managing the human, physical, and
natural resources entrusted to its care. The commission provides
retail drinking water to 770,000 San Francisco customers and
wholesale water to delivery agencies serving 1.6 million custom-
ers in Alameda, Santa Clara, and San Mateo counties. The Hetch
Hetchy Reservoir provides 85 percent of the commission’s
drinking water, while five Bay Area reservoirs in the Alameda
and Peninsula watersheds provide the remaining 15 percent.
Figure 1 depicts the sources and distribution of water for the
commission’s customers. The commission reports that it
delivers a daily average of about 260 million gallons of water to
its customers.
THE COMMISSION’S ORGANIZATIONAL STRUCTURE
The mayor of San Francisco appoints five commissioners to
four-year terms to govern the commission. The mayor also
appoints the commission’s general manager. The commission
C A L I F O R N I A S T A T E A U D I T O R 5
FIGURE 1
An Overview of the San Francisco Public Utilities Commission’s Water System
Hetch Hetchy Watershed Alameda Watershed Peninsula Watershed
Crystal Springs, Pilarcitos,
Hetch Hetchy Reservoir San Antonio and Calaveras Reservoirs and San Andreas Reservoirs
Sunol Valley Water Harry W. Tracy
Treatment Plant Water Treatment Plant
15% Bay Area
sources
85%
Hetch Hetchy
sources
1/3 City and County
of San Francisco
customers
2/3 suburban
customers
6 C A L I F O R N I A S T A T E A U D I T O R
has about 1,700 employees and an annual budget of about
$400 million. The principal operation and support units within
the commission include:
•
Bureau of finance, which coordinates the development
and monitoring of the commission’s annual operating and
capital project budgets, issues financial statements and
revenue bonds, and establishes retail and wholesale
water rates.
•
Bureau of personnel and training, which maintains
employee files, conducts examinations, manages the
grievance and discipline process, and ensures compliance
with employment laws and regulations.
•
Utilities engineering bureau, which provides the
commission with engineering and project management
services, designs the construction or repair of facilities to
meet operating needs, and assesses the condition of
commission facilities and recommends necessary repairs
and improvements.
•
Bureau of systems planning, environment and compliance,
which provides medium- and long-range planning for the
commission and monitors the commission’s compliance
with environmental laws and regulations.
The Appendix contains an abbreviated organizational chart
showing the placement of these bureaus within the commission
and the key water distribution units.
Key Water Distribution Units
Three divisions within the commission bear primary responsibil-
ity for the delivery of water to its customers: Hetch Hetchy
Water and Power, Water Supply and Treatment, and City
Distribution. The Hetch Hetchy Water and Power Division
collects and stores drinking water from watersheds in Yosemite
National Park and the Stanislaus National Forest and transports
it from the mountains and across the San Joaquin Valley. This
division operates five dams and reservoirs, four hydroelectric
plants, and more than 180 miles of tunnels and pipelines. Water
from the Hetch Hetchy Reservoir is so pure that it is exempt
C A L I F O R N I A S T A T E A U D I T O R 7
from state and federal filtration requirements. However, the
commission does treat the water with chlorine before providing
it to its customers.
The Water Supply and Treatment Division takes responsibility
for the drinking water at the Tesla Portal on the east side of the
Coast Ranges in San Joaquin County. From there, it transports
the water through about 40 miles of tunnels and 228 miles of
pipelines to the commission’s San Francisco and suburban
customers. Along the way, the Water Supply and Treatment
Division adds treated water from reservoirs in Bay Area water-
sheds. This division operates and manages five reservoirs, two
water treatment plants, and five pump stations, among
other facilities.
The City Distribution Division operates and maintains
the drinking water system within the City and County of
San Francisco, including 12 reservoirs, 14 water tanks, 22 pump
stations, approximately 1,240 miles of pipelines, and more than
15,500 shutoff valves. On an average day, it delivers about
80 million gallons of water to its San Francisco customers. The
map in Figure 2 depicts the commission’s water delivery system.
THE COMMISSION’S SUBURBAN CUSTOMERS
In addition to providing retail water to its San Francisco
customers, the commission provides retail water to a few other
customers and wholesale water to 28 water delivery agencies.
The commission refers to these purchasers collectively as subur-
ban customers. The commission’s retail customers outside
San Francisco include Stanford University and Lawrence
Livermore National Laboratory. The water delivery agencies
include cities, water districts, and a private water supplier.
Suburban wholesale customers are located on the San Francisco
peninsula and in the South and East Bay. They include the cities
of Hayward, Santa Clara, San Jose, and Daly City; the California
Water Service Company, which serves South San Francisco and
San Mateo; the Alameda County Water District; and the
Coastside County Water District, which serves the Half Moon
Bay area. These customers are responsible for operating and
maintaining their own local distribution systems.
8 C A L I F O R N I A S T A T E A U D I T O R
FIGURE 2
The San Francisco Public Utilities Commission’s Water Delivery System Stretches From the Sierra Nevada Mountains to the Pacific Ocean
SIERRA
NEVADA
MOUNTAINS
LAKE LLOYD (CHERRY LAKE)
LAKE ELEANOR
CHERRY TUNNEL HETCH HETCHY
RESERVOIR
Tuolumne
FRA
S
N
A
C
N
ISCO
SAN
V A
JO
LL
A
E
Q
Y
UIN River
T U N
N EL C
TU
A
N
N
N
YO
EL
N POWER
YOSEMITE
BAY FOOTHILL MOUNTAIN
SAN
Stanislaus River TUNNEL
M
PR
O
IE
C
S
C
T
A
R
S
E
I
S
N
E R
R
V
ES
O
E
I
R
R
VOIR
NA
P
T
A
IO
R
N
K
AL
FRANCISCO
WA H T A E R R R T Y R W EA . T P T M L R A A EN N C T T Y IRVINGTON C R S O A E A S N S E T R A R V N A O T N I O G R E N T IO UN NE T L ESLA SAN JOA 1 Q , U 2, I N an P d IP 3
ELINES
Tuolumne River
TUNNEL
PORTAL
SAN ANDREAS
P
R
I
E
L
S
A
E
R
R
C
V
IT
O
O
IR
S CRYSTAL
PIPELINES 1
and 2
CALAVERAS
RESERVOIR SPRINGS RESERVOIR
RESERVOIR COAST
BAY DIVISION
RANGES
SUNOL VALLEY WATER
PIPELINES3and 4 TREATMENT PLANT
PACIFIC
OCEAN
Source: San Francisco Public Utilities Commission
Blank page inserted for reproduction purposes only.
10 C A L I F O R N I A S T A T E A U D I T O R
FIGURE 3
Member Agencies of the Bay Area Water Users Association
City and County
of San Francisco
Lawrence
Daly 3 Livermore
City 11 National
8 5d San Francisco Alameda Laboratory
County
Bay
12
29
Hayward
23 SFO
19
16
San Antonio
San 4
Reservoir
Andreas
Reservoir 13 San 10 1
Pilarcitos Mateo
Reservoir 5c
6 S C p r r y i s n t g a s l 2 Calaveras
Reservoir Reservoir
5b 22 15
5e 9
7
Half
Moon 20
Bay 5a Palo San Jose 17
26 27 Alto 18
15
24
25
28
21
14
Santa Clara
San Mateo
County
County
20
Agency No. Agency Name Agency No. Agency Name
1 Alameda County Water District 12 City of Hayward
2 Belmont County Water District 13 Town of Hillsborough
3 City of Brisbane 14 Los Trancos County Water District
4 City of Burlingame 15 City of Menlo Park
5a Bear Gulch - Cal Water Service Co. 16 City of Millbrae
5b City of San Carlos - Cal Water Service Co. 17 City of Milpitas
5c City of San Mateo - Cal Water Service Co. 18 City of Mountain View
5d City of South San Francisco - 19 North Coast County Water District
Cal Water Service Co. 20 City of Palo Alto
5e Palomar County Water District #3 - 21 Purissima Hills Water District
Cal Water Service Co. 22 City of Redwood City
6 Coastside County Water District 23 City of San Bruno
7 Cordilleras Mutual Water Association 24 City of San Jose
8 City of Daly City 25 City of Santa Clara
9 East Palo Alto Water District 26 Skyline County Water District
10 Estero Municipal Improvement District 27 Stanford University
11 Guadalupe Valley Municipal 28 City of Sunnyvale
Improvement District 29 Westborough Water District
Source: San Francisco Public Utilities Commission and the Bay Area Water Users Association.
Note: Lawrence Livermore National Laboratory is an associate member of the Bay Area Water Users Association.
Blank page inserted for reproduction purposes only.
12 C A L I F O R N I A S T A T E A U D I T O R
In 1958, the commission’s suburban customers formed the
Bay Area Water Users Association (BAWUA) to represent their
collective interests in working with the commission. The
BAWUA administers contractual matters on behalf of its mem-
bers, works closely with commission staff and management, and
participates with commission personnel on studies. The map in
Figure 3 shows the location of those suburban customers who
are members of the BAWUA.
The commission’s suburban customers receive approximately
two-thirds of the water provided by the water delivery system;
they count on the system for dependable and
reliable service. Most of the 28 suburban wholesale
According to the commission, it meets the
customers typically receive all or a large portion of
water needs of:
their water from the commission. Twenty-three of
•
100 percent of its San Francisco these customers receive at least 80 percent of their
customers. drinking water from the commission. Although
• some suburban customers have access to limited
91 percent of its San Mateo County
quantities of water from alternate sources (such as
customers.
well water that must be treated before delivery),
•
58 percent of its Santa Clara County 10 do not have such options. These 10 customers
customers.
include Brisbane, Hillsborough, and San Mateo. If
• the commission’s system were unable to provide
44 percent of its Alameda County
customers. water to these customers, they would have to rely
on their own local storage capacities. Suburban
customers without sufficient storage capacities or
alternate water sources would face severe water shortages until
measures such as trucking in bottled water could be taken.
THE COMMISSION’S FUNDING SOURCES
As a self-supporting operation of San Francisco, the water delivery
system is expected to pay its own way. The revenue generated
from water sales is the primary source of annual funding for the
commission’s water delivery system. The commission’s final
budget for fiscal year 1999-2000 indicates that 76 percent of the
funds to operate the City Distribution and Water Supply and
Treatment divisions will come from retail rates charged to
San Francisco customers and wholesale rates charged to subur-
ban customers.1 An agreement between the suburban customers
and the commission establishes the method for calculating the
1The commission anticipates that the remaining funds for these two divisions will come
from unspent prior-year money (16 percent) and other miscellaneous sources
(8 percent), such as rents and interest income.
C A L I F O R N I A S T A T E A U D I T O R 13
suburban rates. Generally, because the suburban customers use
about two-thirds of the commission’s water, they pay about two-
thirds of the costs of operating and maintaining the water
delivery system.
FIGURE 4
Comparison of Average Monthly Water Charges of Some
Single-Family Residences in the Bay Area
$35
30
25
20
15
10
5
0
Sa U n t i F li r t a ie n s c i C sc o o m P m ub is l s A i i c o l a n m W e a d te a r C D o is u t E n ri a t c s y t t W Ba a y te M r D un is i t c r i i p ct a M l a W rin a t M er u D n i i s c t ip ric a t l C W on a t t r e a r C D o is s t t r a ict
Source: San Francisco Public Utilities Commission’s November 1999 Draft Water
Enterprise Long-Range Financial Report
14 C A L I F O R N I A S T A T E A U D I T O R
22.21$
41.41$
40.81$
85.32$
06.13$
The commission reports that its customers have among the Bay
Area’s lowest water rates. Figure 4 compares the average monthly
water charges for some single-family residences served by the
commission with the average charges paid by residential cus-
tomers of other Bay Area water suppliers.
Regarding the Hetch Hetchy Water and Power Division, the
commission’s fiscal year 1999-2000 final budget shows that
92 percent of its revenue will come from a transfer from the
other two water-related divisions and the sale of power
and energy.2
Funding of Capital Projects
The commission uses proceeds from bond sales to fund most of
its nonrecurring capital projects. Generally, the commission
must receive approval from San Francisco’s voters before selling
bonds. Two types of bonds do not need voter approval—water
revenue bonds for reconstruction and replacement of existing
facilities or for complying with state and federal law, and bonds
issued to reduce the commission’s payments for existing debt.
Although they do not require San Francisco voters’ approval,
bonds for reconstruction and replacement of existing facilities or
for complying with state and federal law must be approved by a
three-fourths vote of the San Francisco Board of Supervisors. The
commission has $238 million outstanding in these two types of
bonds. They were issued in 1991, 1992, and 1996. In 1997,
San Francisco’s voters approved $147 million in bonds to
improve water quality and $157 million in bonds to improve
system reliability and seismic safety.
In 1998, San Francisco’s voters passed a proposition that
prevents the commission from raising their water rates until
July 1, 2006, except for certain purposes. Those purposes include
generating funds to retire the 1997 bonds or to pay for future
voter-approved bonds. The rate freeze also can be suspended if
San Francisco’s mayor declares an emergency. This proposition
essentially requires the commission to seek voter approval from
its San Francisco customers for any debt it would incur that
would be retired by rate increases.
SCOPE AND METHODOLOGY
The Joint Legislative Audit Committee asked the Bureau of State
Audits to evaluate the methods the commission is employing to
ensure an adequate, long-term, and reliable water supply for its
Bay Area customers.
2The commission anticipates that the remaining funds for this division will come from
unspent prior-year money (6 percent) and other miscellaneous sources (2 percent),
such as interest income.
C A L I F O R N I A S T A T E A U D I T O R 15
Regarding its efforts to plan a reliable water delivery system and
to ensure an adequate supply of water, we reviewed the
commission’s efforts to develop its facilities reliability study and
its water supply master plan. Specifically, we determined the
current status of these tasks, whether the commission began
working on these tasks without unnecessary delay, and whether
the commission completed the tasks promptly.
To evaluate the commission’s progress in identifying, initiating,
and completing needed capital projects, we reviewed the
commission’s capital improvement plans for its water-related
divisions, project operations manual, long-range financial
report, contracting procedures, project monitoring reports, and
the training given to project managers. In addition, we inter-
viewed key managers, project managers, engineers, and other
staff. However, because the commission did not maintain
adequate records, we were unable to determine how long the
commission took to complete capital projects or whether the
length of time was appropriate.
To assess the adequacy of the preventive maintenance proce-
dures of the Hetch Hetchy Water and Power Division and the
Water Supply and Treatment Division, we examined how they
operated their preventive maintenance systems. We also
reviewed a 1994 report by San Francisco’s budget analyst
criticizing the preventive maintenance system of the Water
Supply and Treatment Division. Finally, we assessed whether the
commission’s new automated preventive maintenance system
will address the faults within the old system. (cid:1)
16 C A L I F O R N I A S T A T E A U D I T O R
AUDIT RESULTS
It Is Uncertain Whether the Actions
of the Public Utilities Commission
Will Improve the Water Delivery
System’s Reliability
SUMMARY
T
he San Francisco Public Utilities Commission (commis-
sion) has been slow to assess the ability of its water
delivery system to survive catastrophic events such as
earthquakes, floods, or fires and to identify additional water
sources. Delays in performing these studies have led to delays in
improving the water system. The commission also has made
slow progress in completing capital projects aimed at improving
system reliability for reasons that include insufficient staff to
manage the projects and operational inefficiencies in its
contracting and project monitoring procedures. Although the
commission has several plans to improve its water delivery
system, it is too soon to determine whether they will succeed
because most are still in development.
PARTS OF THE WATER DELIVERY SYSTEM ARE
VULNERABLE TO FAILURE
Nearly 2.4 million customers in the City and County of
San Francisco and in Alameda, San Mateo, and Santa Clara
counties rely on the commission for their drinking water. The
commission uses an aging system of dams, reservoirs, tunnels,
pipelines, pumps, and valves to move the water to and through-
out the Bay Area. Portions of the water delivery system are in
dire need of repair or replacement; some parts of it are nearly
The commission estimates 75 years old. For example, two of the four pipelines that carry
it will cost more than water from the East Bay to the South Bay and the San Francisco
$3 billion to complete peninsula are more than 70 years old. The commission states
about 200 capital that no major work has been done on these two pipelines since
improvement or their construction. These pipelines are above ground on wooden
replacement projects. trestles in Bay marshlands. The commission considers them
extremely vulnerable to failure, especially because they cross the
Hayward Fault many times. The commission knows that its
system needs rehabilitation and estimates that it will cost more
than $3 billion to complete about 200 capital improvement or
replacement projects.
C A L I F O R N I A S T A T E A U D I T O R 17
THE COMMISSION IS SLOW TO UPGRADE
ITS WATER SYSTEM
Some customers, uneasy about the possibility of lengthy inter-
ruptions in service, have expressed concerns regarding the
commission’s slow pace in completing the capital projects
necessary to ensure a reliable water delivery system. They believe
that such slowness increases the risk that portions of the water
delivery system may fail due to age and deterioration or may not
survive a natural disaster such as an earthquake. Further, they
fear that the system may not be able to deliver enough water to
accommodate growth or to compensate for droughts.
The Commission Has Been Slow to Assess Its
System’s Weaknesses
The commission has been slow to assess the ability of its
water delivery system to survive catastrophic events and to
identify additional sources of water. Delays in conducting
these studies consequently contribute to delays in improving
system reliability.
The commission recognizes that some portions of its water
delivery system are susceptible to failure. Components of the
system suffer wear and tear, exposure, corrosion, and other
deteriorating effects. Older segments are nearing the end of their
expected lives and must be rehabilitated or replaced soon.
However, the commission’s rate of rehabilitation or replacement
has not kept pace with the aging process.
Since at least mid-1993, staff members also have raised concerns
about the ability of portions of the water delivery system to
survive a major earthquake. The system crosses or is near several
active faults. Although much of the commission’s water delivery
Some components of system escaped serious damage from the Loma Prieta earthquake
the system were not in October 1989, the commission later observed that some
designed to withstand sections “showed signs of distress.” Further, it knows that some
major earthquakes. system components were not designed to meet modern seismic
standards. Given the aging, the deterioration the water delivery
system has experienced in the last 10 years, and the risks posed
by earthquakes, the commission should have acted earlier to
identify significant weaknesses in its system.
It was not until 1994 that the commission, in collaboration with
the Bay Area Water Users Association that represents its subur-
ban customers, embarked on its first comprehensive review of
18 C A L I F O R N I A S T A T E A U D I T O R
the system’s reliability. In January 2000, the commission
released a report that represents the second phase of its three-
phase study.3 Aimed at describing the nature of the threats the
system faces from catastrophes such as earthquakes, floods, and
fires, the report, prepared by a consultant, recommends
19 improvements that are urgently needed to address critical
weak links in the commission’s system. These improvements
include strengthening pipelines that cross the Hayward Fault,
increasing the treatment capacity of one water treatment plant,
and installing isolation or shutoff valves to prevent water losses.
This review took only seven months to complete. However, its
Improvements necessary startup was delayed until December 1998, almost three years
to address critical weak after the first phase of the study was completed, because the
links in the system include commission did not consider it a priority and thus did not
strengthening pipelines promptly assign staff to manage the project. Contracting
that cross the Hayward problems that were beyond its control also contributed to the
Fault and increasing the delay. The commission modified the scope of the project and
capacity of one of its reissued its request for proposals because the costs proposed by
water treatment plants. vendors responding to its original request were too high. Also,
one vendor selected to work on the project had trouble comply-
ing with all the contract requirements.
The third and final phase of the facilities reliability study will
include a more detailed analysis of the system’s reliability. As
part of this phase, the commission’s consultant will develop,
evaluate, and prioritize alternatives for improving the water
delivery system, including capital projects that address the
system’s weak links and problem areas. The manager of this
project expects this phase of the study to be completed within
18 months after the consultant receives a notice to proceed. The
manager also believes the commission will issue a request for
proposals for this project by March 2000 and start the contract
by October 2000.
Creation of a Comprehensive Water Supply
Master Plan Has Been Slow
The commission also should have developed its comprehensive
water supply master plan earlier. This plan, also a joint effort
with the Bay Area Water Users Association, has taken several
3During the first phase of this study, completed in January 1996, the commission
assessed the vulnerability of individual facilities, relying on information from its staff
members who were familiar with the facilities’ condition. The commission created a list
of critical facilities ranked in order of importance to water delivery.
C A L I F O R N I A S T A T E A U D I T O R 19
years to develop. Its purpose is to ensure that the commission
will continue to provide its customers with a reliable supply of
high-quality water. The plan will estimate the amount of water
necessary to meet future demand and recommend methods for
acquiring additional water supplies. Delays in identifying and
agreeing on sources from which to acquire additional water may
lead to delays in actually acquiring the water, especially if the
commission must implement capital improvements to move the
newly acquired water to the Bay Area.
Droughts in the late 1970s and the one ending in 1992 revealed
Despite knowing since that the commission could provide only 242 million gallons of
1994 that it would need water per day during drought conditions rather than its previous
to identify additional assumption of 300 million gallons per day. Because average
water supplies, the water demands during the summer exceed 300 million gallons
commission did not per day and demands from suburban customers are expected to
actively start work on the continue to grow, additional supplies will be necessary.
water supply master plan
until 1996. Although the commission knew by 1994 that it would need to
identify additional water supplies, information provided by its
staff shows that it did not actively start working on the water
supply master plan until early 1996. Phase 1 tasks, completed by
September 1997, included establishing basic planning assump-
tions and characterizing existing commission water supplies.
Phase 2, a preview of which was provided during a public meet-
ing of the commission in November 1999, will estimate that the
commission will need an additional 67 million to 71 million
gallons of water per day by 2030 to meet customer demands. It
also will review alternatives for increasing the water supply, such
as using groundwater or recycled water or buying water rights
held by others. If the commission opts to purchase water rights,
it may need to construct new facilities or upgrade existing ones
to move this water to the Bay Area.
The staff member responsible for developing the plan states that
progress on the water supply master plan was impaired by a
lengthy process to select a consultant to work on the first phase
of the master plan and by an inability to obtain funding to
create the plan. The steering committee overseeing the develop-
ment of the master plan anticipates completing the work in
March 2000, nearly eight years after the last major drought, and
presenting its recommendations to the commissioners the
following month.
20 C A L I F O R N I A S T A T E A U D I T O R
OPERATIONAL DEFICIENCIES HINDER PROGRESS
The commission also appears slow to complete capital projects.
Although it did not provide us with sufficient information
regarding its completion of capital projects, such as the total
number of capital projects funded or the start and completion
date of most of its projects, the commission did tell us that
during the past 10 years it has completed 54 capital projects at a
cost of about $270 million. On average, the commission com-
pleted about five capital projects and spent $27 million annually.
Given the size, complexity, age, and declining condition of the
commission’s water delivery system, this project completion rate
appears to be low.
Several factors contribute to the commission’s inability to
complete capital projects more quickly. The commission believes
that insufficient staffing to manage the projects is a major factor.
Other deficiencies are inefficient contracting procedures,
outdated project operations procedures, weak project monitor-
ing, and inadequate project management training.
When the commission does not complete capital projects
promptly, it exposes the water delivery system to failure during a
The slow pace of project natural disaster. Further, the slow pace of project completion
completion interferes with interferes with the commission’s ability to begin recouping the
the commission’s ability projects’ costs from suburban customers. An agreement with the
to recoup costs from its suburban customers specifies that the commission generally
suburban customers. cannot raise rates to help pay for a capital project until it has
been in service for one year, so delays in completing those
projects increase the time that the commission must finance the
project itself.
A Staff Shortage Contributes to Project Delays
The commission’s former general manager stated that a shortage
of qualified personnel to manage projects has led to delays in
past and current project schedules. As we discussed earlier, the
lack of someone to manage the facilities reliability study contrib-
uted to the commission’s delay in starting the second phase. The
former general manager explained that the staffing shortages
existed because it took nearly three years for engineering exami-
nations to be given and certified through San Francisco’s civil
service system, and permanent positions could not be offered
during that time. Further, when the commission attempted to
C A L I F O R N I A S T A T E A U D I T O R 21
obtain temporary help, its professional services contracts were
scrutinized by the labor unions and the commissioners, creating
additional delays in obtaining engineers.
The commission has taken some measures to address its staff
shortages. For instance, the manager of its bureau of personnel
and training states that she has made great strides in improving
the commission’s personnel practices by increasing the number
of personnel staff and providing them with training on
San Francisco’s personnel processes. The commission also has
suggested improvements to the hiring procedures for engineers
used by San Francisco’s department of human resources. It also
has received approval for several contracts that will supplement
its engineering staff.
We were unable to substantiate the claim that a shortage of
project managers exists because the commission did not provide
all the data we requested. Nevertheless, the commission must
continue to seek ways to ensure that it has adequate staff to
complete its projects.
Contracting Procedures Are Inconsistent
Contracting is critical to the execution of the commission’s
projects. It requires compliance with numerous regulations and
approval processes, as well as involvement with a number of
agencies within and outside San Francisco. The impact on a
capital project can be exceedingly disruptive if the complex
requirements of contracting are not met.
As early as May 1997, a consultant hired by the commission
reported that the commission’s contracting process was inefficient.
Specifically, the consultant found that it took 6 to 12 months to
complete the contracting process, beginning with the request for
A May 1997 report proposal development and ending with the awarding of the
prepared by its contract. This was twice as long as the process used by
consultant highlights San Francisco’s Department of Public Works. The consultant
inefficiencies in the noted that problems with the decision-making process contrib-
commission’s contracting uted to delays in the contracting process. For example, the
practices. commission did not have a structure and process to deal with
problems, and there were no written policies, guidelines, or
standards for tasks critical to decision making, such as defining
the scope of work, choosing selection criteria, and negotiating
contracts. The consultant also noted that the commission’s
22 C A L I F O R N I A S T A T E A U D I T O R
contracting procedures were confusing, with contracting func-
tions scattered throughout many of its departments, and were
not overseen by any central body.
The commission has begun to address the concerns raised by its
consultant. For instance, in May 1999 it established a policy that
clarifies its expectations and approval process for professional
service contracting. In addition, in September 1999 the contract-
ing unit within the utilities engineering bureau was centralized.
This unit has since tripled its staff and, among other things, is
producing weekly reports of outstanding issues, developing
contract procedures, and instituting a process to resolve contract
protests promptly.
Finally, the commission has submitted a budget proposal for
fiscal year 2000-01 requesting the creation of a commissionwide
The commission’s project contracting unit and the addition of more staff to expedite the
operations manual is internal handling of contracts. Although the commission has
outdated. In fact, the begun to address inefficiencies in its contracting process, it will
manual has received few continue to experience difficulties until its actions are finalized.
updates since it was Some commission staff members told us that the contracting
developed in 1988. process is still slow, adding unnecessarily to the time required to
complete projects.
Steps for Completing Projects Lack Uniformity
The commission could improve its management of capital
projects by updating its project operations procedures. These
procedures provide a guideline for consistent performance by
commission staff; some of them, however, are outdated and
are no longer used. Implementing common procedures will
enhance the consistency, coordination, and effectiveness of the
commission’s operations.
The commission lacks current project operations procedures.
Many staff members told us that the project operations manual
is outdated and that many forms and templates in the manual,
such as those for contracting and procurement, are no longer
used. In fact, the manual has received few updates since it was
developed in 1988.
The commission is updating the project operations manual
and expects the final version to be completed by June 2000.
Until then, project managers will be left to rely upon their own
expertise to complete capital projects. Although some project
managers and teams can succeed in this type of environment, it
C A L I F O R N I A S T A T E A U D I T O R 23
is important for the commission to ensure that its staff members
are following similar procedures. Creating common procedures
and expectations will increase the overall consistency, coordina-
tion, and effectiveness of its operations.
Oversight Requires Better Tracking Systems
The absence of an effective tracking system to monitor the
progress of capital projects and the completion of preventive
maintenance makes it difficult, if not impossible, for manage-
ment to ensure that commission staff complete the numerous
capital projects and preventive maintenance requirements
on time.
The commission did not use a formal tracking system to
monitor the status of its capital projects from 1995, when it
abandoned its previous system, until February 1999, when it
again began using a system to track capital project milestones.
During that time, project managers were left to monitor their
projects using their own systems, potentially leading to inconsis-
tencies in how and what information was tracked. The manager
of the capital program management division was unable to
explain why it took so long to start using the new system. This
system, which establishes estimated dates for project initiation,
and the completion of major steps such as planning, design, and
construction, should assist commission staff in monitoring
capital projects to ensure that project schedules are met and that
any delays are addressed quickly.
The commission also does not have an adequate method for
tracking preventive maintenance. Routine preventive mainte-
nance is essential for ensuring that existing water delivery
system components last as long as possible. In 1994,
San Francisco’s budget analyst criticized the Water Supply and
Treatment Division for performing “practically no preventive
maintenance” on some facilities, thereby causing those facilities
to deteriorate more rapidly than if they had received proper
Although an automated maintenance. The analyst stated that the primary reason for the
system exists, commission lack of maintenance was that staff members within the Water
staff use manual systems, Supply and Treatment Division were not fully implementing the
such as logbooks and division’s automated maintenance management system.
card files, to track
preventive maintenance. More than five years later, we find that division staff still are not
using the automated system’s tracking component because some
of its managers have been reluctant to spend the time required
to develop a complete list of equipment and the preventive
24 C A L I F O R N I A S T A T E A U D I T O R
maintenance requirements. Instead, staff are using manual
systems, such as entering data in logbooks and card files, to
track preventive maintenance. As a result, commission manage-
ment may have difficulty assessing whether staff members are
performing required preventive maintenance on time.
The commission is in the midst of implementing a new automated
system to, among other things, track preventive maintenance
requirements. If used properly, this system should resolve these
concerns, making the commission better able to identify and
schedule preventive maintenance for its pipelines, valves,
and pumps. According to one of its information systems’
managers, the commission’s implementation of the new system
for the Water Supply and Treatment Division is nearly complete.
He also expects implementation of the new system to be com-
pleted by mid-February 2000 for the Hetch Hetchy Water and
Power Division. The manager expects implementation of the
new system at the City Distribution Division to start by
March 2000.
Project Managers Receive Little Training
Ongoing development is crucial for ensuring that commission
staff members stay abreast of industry changes and that
they improve their technical expertise. However, the commis-
The commission has not sion does not routinely provide formal training to its
provided formal project project managers.
management training in
the past 10 years. Although project managers typically receive on-the-job training,
the commission does not have a formal program to train them.
In fact, the commission has not provided formal project
management training in the past 10 years. Some project
managers use their own techniques to manage projects, so the
commission cannot control or ensure the adequacy of the
on-the-job training its new employees receive. Formal, ongoing
training would ensure that staff members develop and improve
their technical proficiency and project leadership abilities.
One reason the commission cites for the lack of formal training
for project managers is insufficient staff to plan or coordinate
the training. Its bureau of personnel and training did not have a
training officer until last year. One manager told us that short-
ages of professional staff have made it difficult to divert staff
from projects to receive formal training. The commission is
planning to develop a program to train project managers
on how to handle all phases of a project. In the meantime,
C A L I F O R N I A S T A T E A U D I T O R 25
however, the commission must ensure that its professional staff,
including project managers, receive some formal training to
improve their skills, especially in light of the huge capital
improvement program it faces.
UNCERTAINTIES REMAIN
The commission acknowledges that it lacks the tools to
streamline capital project development or to control such a
large capital improvement program. It also acknowledges that it
needs standard procedures for project management and design
protocols and needs to expedite its contracting procedures. It
has undertaken many projects and actions, in addition to those
already mentioned, to address these deficiencies. However,
because many of these plans or actions are not yet finalized, the
commission’s ability to ensure a sufficient, long-term, and
reliable water supply remains uncertain.
A Management Consultant Would Bring Needed Expertise
Recognizing that its water delivery system has significant
weaknesses that will require large-scale improvements, the
commission is obtaining approval to contract for the services of
The commission is a program management consultant. The consultant is expected
counting on a consultant to provide program management services and specialized techni-
to perform a major cal expertise to manage workload peaks and to provide a staff
overhaul of its development program. For example, the proposed program
engineering and manager would perform services such as designing a capital
construction operations. program framework document, organizing the overall capital
program, and developing a long-term implementation plan.
Other proposed services include designing performance mea-
sures, providing a project management information system,
devising protocols to expedite contracting and procurement,
and developing a public information program to engender
public confidence in the commission’s long-range plans. This
last item is important to build voter confidence and gain
approval for the financing of its capital improvements. Basically,
the commission is counting on the program management
consultant to perform a major overhaul of its engineering and
construction operations so it can implement the capital
improvements necessary to ensure system reliability.
However, the commissioners and the San Francisco Board of
Supervisors must approve this contract, and it remains unclear
whether they will do so. The commissioners’ vote on the contract
26 C A L I F O R N I A S T A T E A U D I T O R
is not expected to occur before May 2000; the board of supervi-
sors’ vote would occur after that. At the board of supervisors’
request, San Francisco’s budget analyst is reviewing the proposed
contract to determine whether contracting out management
functions will save money or result in increased or decreased
oversight of expenditures, and whether it will provide other
benefits over commission management of the capital
improvement program. Should the commissioners or the board
of supervisors opt not to approve the contract, commission staff
may be ill equipped to handle such a large, complex capital
improvement program.
Capital Improvement Plans Are Not Complete
The commission’s staff and its consultant have developed capital
improvement plans for each of its water-related divisions, but
the commission has not adopted them. Further, the commission
has not integrated these plans to obtain an accurate picture of
the entire system’s needs. Without formal adoption and
integration of these plans, we are concerned that other issues
could divert the commission’s attention from its goal of improv-
ing the reliability of the water delivery system by focusing on
the most critical projects. Finally, the commission has yet to
develop a staffing plan for completing its capital improve-
ment program. Until this plan is complete, the commission
cannot ensure it has enough staff to complete its capital
improvement plan on schedule.
The commission developed the capital improvement plans to
evaluate and prioritize the capital projects necessary to improve
each of its three drinking water-related divisions: Hetch Hetchy
Water and Power, Water Supply and Treatment, and City Distri-
bution. Generally, it based these plans on information supplied
by the operating divisions and by staff from other support
bureaus such as utilities engineering and systems planning,
environment and compliance. The commission has grouped its
projects under several categories such as aging infrastructure,
water supply reliability, seismic vulnerability, system deficiencies,
operational efficiency, and regulatory compliance. To prioritize
these projects, the commission developed criteria to evaluate the
relative value of needed improvements. As shown in the
following table, the 1999 plans include 174 water-related capital
projects with estimated costs of more than $2.7 billion.
C A L I F O R N I A S T A T E A U D I T O R 27
TABLE
Water-Related Capital Projects Identified in 1999
Average
Total Estimated Cost
Number of Estimated Cost per Project
Division Capital Projects (In Millions) (In Millions)
Hetch Hetchy
Water and Power 28 $ 143 $ 5.11
Water Supply and
Treatment 90 1,637 18.19
City Distribution 56 953 17.02
Total 174 $2,733 $15.70
Source: San Francisco Public Utilities Commission 1999 Capital Improvement Plans.
Although the average project cost is about $16 million, seven
major projects make up approximately 41 percent, or nearly
$1.1 billion, of the total capital program costs. Five of these
projects, such as the improvements proposed for the Sunol
Valley Water Treatment Plant and the replacement of prestressed
concrete pipelines, are within the Water Supply and Treatment
Division. The other two major projects, the water main replace-
ment program and the seismic upgrades to city reservoirs, are
within the City Distribution Division.
The capital improvement plan for the Hetch Hetchy Water and
Power Division remains incomplete because it lacks cost esti-
The commission’s mates for some of the water-related projects.4 This is significant
proposed consultant because the Hetch Hetchy Reservoir supplies about 85 percent of
would develop a the commission’s water. According to one of its managers, the
comprehensive plan to commission expects to finalize these estimates by March 2000.
identify the staffing neces- We also found that the commission is continually identifying
sary to implement the new projects and adjusting its cost estimates. For example, its
capital improvement plan. most recent cost estimate, excluding missing estimates for the
projects discussed earlier, is more than $3 billion.
The commission has yet to develop a formal comprehensive
plan to outline its staffing requirements to implement its capital
projects. This is critical because, as we discussed earlier, shortages
of engineering staff have contributed to previous project delays.
The commission states that its proposed program management
4The plan for the Hetch Hetchy Water and Power Division also includes power-related
capital projects.
28 C A L I F O R N I A S T A T E A U D I T O R
consultant will develop this plan. However, as we already have
noted, the commission or the board of supervisors may not
approve this contract. If this occurs, the commission must
ensure that it develops this staffing plan itself.
The Commission’s Long-Range Financial Planning
Is Incomplete
One of the commission’s primary challenges is funding its large-
scale capital improvement plans. The commission developed a
long-range financial report to assess financing options for its
capital projects within the Water Supply and Treatment and City
Distribution divisions. However, its financial report, prepared by
a consultant, relies heavily on the commission’s ability to obtain
voter approval for revenue bonds and does not adequately
address contingencies should San Francisco’s voters reject future
bond measures.
The January 2000 financial report for the Water Supply and
The commission’s Treatment Division and the City Distribution Division analyzes
financial report places the funding of recommended capital projects and briefly dis-
heavy reliance on revenue cusses alternative financing methods. It also includes estimates
bonds that require voter of the timing and magnitude of possible water rate increases and
approval and does not future revenue bond issues, using the estimated costs of the capital
adequately address projects identified in the current capital improvement plans.
options if voters reject
such bond measures. Its consultant believes the commission has the financial capabil-
ity to implement the capital improvement plan for the two
divisions. However, the consultant also states that the time
period for implementation might be too short because the
commission is anticipating that spending levels for capital
projects will be three to four times that of recent levels. For this
reason, the consultant recommends that the commission con-
sider extending the scheduling of the capital projects over a
term closer to 25 years, which exceeds the commission’s 15-year
schedule for completing most of its capital projects. However,
the commission told us that it disagrees with this recommenda-
tion because it recognizes the need to complete the projects
sooner rather than later.
Additionally, the consultant places significant emphasis on
the commission’s ability to fund its capital program using
voter-approved revenue bonds and fails to adequately address
the options the commission would have if voters do not
approve its bond measures. This is important given the fact that,
based on recent voter turnouts, fewer than 100,000 voters in
C A L I F O R N I A S T A T E A U D I T O R 29
San Francisco could deny the commission’s future bond measures.
Ultimately, they control the fate of the financing future of the
commission’s capital improvement plans and the delivery of
water to 2.4 million customers in four Bay Area counties. Should
the voters reject future bond measures, the commission will be
forced to rely on other methods that could result in a slower
completion pace for its capital projects, which in turn will delay
improving the water delivery system.
One alternative financing method the consultant mentioned
was the creation of a joint powers authority. A joint powers
Although creating a joint authority could be set up between the public entities comprising
powers authority may the commission’s San Francisco and suburban customers. The
provide an alternative to governing board of this authority could then authorize the
issuing bonds, it may also issuance of non-voter-approved bonds. These bonds would
be problematic. not be approved by its San Francisco customers, so the terms of
the 1998 proposition would prevent the commission, until
July 1, 2006, from raising their water rates to retire the bonds.
The authority would have to rely on the suburban customers to
retire the bonds unless San Francisco’s voters authorize increases
in their water rates. So the creation of a joint powers authority
may provide an alternative to issuing voter-approved bonds, but
it also may be problematic.
The consultant provided no information about how the commis-
sion and its customers would go about setting up a joint powers
authority. Creating such an authority may be time-consuming
because it would require approval by the governing bodies
of each suburban water agency. There is no certainty
that each governing body would approve the creation of
the authority.
Finally, although the consultant believes the capital improve-
ment plan is within the commission’s financial capability, the
interest rates used in the projections were based on current
economic conditions. Changes in these rates could affect the
commission’s ability to accomplish this plan. The commission
contends that staff of its bureau of finance, along with a finan-
cial adviser, will monitor market fluctuations for warning signs
and will adjust the projections as necessary.
Financing Options for Hetch Hetchy Projects Remain Unclear
Although the long-range financial report is complete for the
Water Supply and Treatment Division and City Distribution
Division, the long-range financial report for the Hetch Hetchy
30 C A L I F O R N I A S T A T E A U D I T O R
Water and Power Division is still being developed. As a result,
although the commission has identified many capital projects
needed to upgrade its water delivery system, its plans remain
incomplete regarding exactly how it will fund these projects.
According to commission staff, recent changes in revenue and
expenditure projections for this division resulted in delays in
completing this report. Therefore, the commission does not
expect this financial report to be completed until February 2000.
The responsibility for using these financial reports and developing
and adopting a true long-range financial plan to finance its capital
improvement program ultimately lies with the commission.
Therefore, the commission must act quickly to complete its
financial plan and ensure that it has sufficient funding to com-
plete its capital improvement plans. Until this financial plan has
been completed and adopted, we will be unable to determine
whether it is adequate or whether the commission is committed
to implementing its capital improvement plans.
Executive Vacancies and Turnover Present a
Unique Opportunity
Final factors leading to our uncertainty about whether the
commission will improve its water delivery system are the
turnover at the executive level and the time it will take to fill
Significant challenges in these positions. As we indicated earlier, the commission faces
the near future require significant challenges in the near future, including the need to
strong, consistent, and implement a huge capital improvement program and to obtain
effective leadership. additional water supplies. Without strong, consistent, and
effective leaders, the chances that the commission will meet
these challenges diminish greatly.
The commission recently has experienced turnover among some
of its executive positions. For instance, from December 1995
through December 1998, the position of manager of the utilities
engineering bureau was filled by three different people and was
vacant for a total of 13 months. The current manager’s tenure is
14 months. This position leads more than 100 employees
responsible for the efficient performance of the commission’s
capital improvement projects. The utilities engineering bureau
provides engineering services to the commission, including
assessment of facilities; recommendations for repairs and
improvements; and design, construction, or repair of facilities. A
vacancy in this position contributed to the nearly three-year gap
between the end of the first phase and the start of the second
phase of the facilities reliability study.
C A L I F O R N I A S T A T E A U D I T O R 31
The recent retirements of the general manager and the assistant
general manager for operations also present a challenge to the
commission. According to the commission’s former general
manager, it can take 6 to 12 months to fill these positions. On
the other hand, these vacancies also present an opportunity to
build a management team that will provide the strong leader-
ship and expertise necessary to implement a cohesive capital
improvement program and meet the other enormous challenges
the commission faces.
RECOMMENDATIONS
To ensure that the commission follows through on plans that it
is developing or that it has recently developed, it should report
annually to the Legislature for the next five years. The reports
should include descriptions of the progress the commission has
made in implementing each of its plans and the accomplish-
ments it has achieved. The commission also should provide
these reports to the Bay Area Water Users Association.
To improve the reliability of its water delivery system, the
commission should continue to finalize, adopt, implement,
monitor, and as necessary revise the plans and actions it has in
progress. Specifically, it should:
(cid:127) Complete its facilities reliability study and the water supply
master plan.
(cid:127) Continue pursuing ways to attract and retain qualified
engineering staff.
(cid:127) Continue its efforts to improve its contracting procedures
and to train staff to understand the new procedures. It also
should establish a commissionwide contracting unit.
(cid:127) Continue updating the manual its staff members are supposed
to use for guidance during planning, design, or construction of
capital projects and ensure that applicable employees receive
training and understand the new procedures.
(cid:127) Complete the implementation of its new automated mainte-
nance management system at all three water-related divisions.
32 C A L I F O R N I A S T A T E A U D I T O R
The commission also should train its staff on this new
system and ensure that they use it consistently and properly.
(cid:127) Develop and implement a formal training program for
project managers and ensure that project managers receive
adequate training while this program is being developed.
(cid:127) Complete and adopt a long-range financial plan for the
three water-related divisions. It also should continue to
monitor and adjust this plan as necessary. The plan should
include more detailed descriptions of the steps the commis-
sion will take if the voters fail to approve the bonds or if
economic conditions change.
(cid:127) Be prepared to take alternative action if the commissioners
or the board of supervisors decide not to approve the
contract for its program management consultant. For example,
it should develop a formal comprehensive plan that
outlines the staffing requirements necessary to complete
its capital improvement program without a program
management contract.
(cid:127) Integrate the capital improvement plans for the three water-
related divisions into one cohesive plan and seek formal
approval from the commissioners.
(cid:127) Complete the missing cost and schedule estimates for the
Hetch Hetchy Water and Power Division’s capital improve-
ment plan.
(cid:127) Given the extent and complexity of the challenges it faces in
the near future, the commission should seize the opportu-
nity to appoint to leadership positions individuals who have
efficiently and effectively implemented large-scale capital
improvement programs. Further, it should take measures to
ensure that it fills available positions promptly.
C A L I F O R N I A S T A T E A U D I T O R 33
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the audit
scope section of this report.
Respectfully submitted,
MARY P. NOBLE
Acting State Auditor
Date: February 17, 2000
Staff: Joanne Quarles, CPA, Audit Principal
Dale A. Carlson, CGFM
Tyler Covey, CPA, CMA
Fernando Valenzuela
34 C A L I F O R N I A S T A T E A U D I T O R
C
A
L
I
F
O
R
N
I
A
S
T
A
T
E
A
U
D
I
T
O
R
35
APPENDIX
Abbreviated Organizational Chart for the San Francisco
Public Utilities Commission
San Francisco Board of
San Francisco Mayor
Supervisors
Public Utilities
Commission
Commissioners
General Manager
Bureau of Systems Assistant Manager
Assistant Manager Utilities Engineering
Planning, Environment for Finance and
for Operations Bureau
and Compliance Administration
Hetch Hetchy Water Bureau of Finance
and Power Division
Water Supply and Bureau of Personnel
Treatment Division and Training
City Distribution Division
Blank page inserted for reproduction purposes only.
36 C A L I F O R N I A S T A T E A U D I T O R
Agency’s comments provided as text only.
City and County of San Francisco
Public Utilities Commission
1155 Market Street, 4th Floor
San Francisco, CA 94103
February 10, 2000
Mary P. Noble
Acting State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
Dear Ms. Noble:
Thank you for this opportunity to respond to the report from the Bureau of State
Audits on the Water Delivery System of the San Francisco Public Utilities Commission.
The San Francisco Public Utilities Commission (SFPUC) is pleased to note that the
1*
Bureau of State Audits acknowledges and supports our on-going efforts to
implement improvements to the water delivery system serving 2.4 million residents
of the San Francisco Bay Area. Planning for a $3.5 billion long-range capital
improvement program is near completion. A total of $567 million has already been
appropriated to specific projects in this program and $350 million has been spent on these
projects. The Bureau of State Audits report validates our own conviction that
the San Francisco Public Utilities Commission is on the right track.
During the decade of the 1990's, the SFPUC faced immediate and long-range
2
challenges. The 1989 Loma Prieta Earthquake increased concerns about seismic
reliability. A seven-year drought extended through 1995 raising concerns about
supply sufficiency. When the drought ended in 1995 major storms overwhelmed
one of the water system's two treatment plants.
In response to these challenges, the SFPUC appropriated nearly $400 million during
the 1990's for capital improvement projects to address specific seismic, reliability
and water quality issues. Planning for a long-range capital improvement program
also began in 1994 when the San Francisco Municipal Railway was established as an
*California State Auditor’s comments begin on page 43.
C A L I F O R N I A S T A T E A U D I T O R 37
independent agency and the SFPUC was reorganized as a utility focusing exclusively
on water and power issues. Within two years (in 1996), the first ten-year capital
improvement plan for the water system was completed. This plan identified
approximately $2 billion in needed improvements. This plan has been updated
annually and now contains projects with costs totaling approximately $3.5 billion. In
1995 the first phase of a system reliability study was produced. In 1996 a bond issue was
approved which provided $68 million in repair and renovation funds for the water system. In
1997 the San Francisco voters approved $304 million in water revenue bonds to address water
quality and system reliability needs identified in the capital improvement plan. Throughout this
time, the SFPUC was able to meet its responsibility to provide high quality potable water to all
2
of its customers while at the same time planning for expanded capacity and increased reliability
to meet future demands and to protect against anticipated seismic events.
The Bureau of State Audits report addresses the ability of the SFPUC to complete its capital
improvement program for the water system. In the early 1990's the SFPUC completed four
major projects which substantially improved quality of the water supply and the reliability of the
water delivery system. These projects included major improvements to the Harry Tracy Water
Treatment Plant, replacement of the Calaveras Pipeline, improvements to the San Antonio
Pump Station and major renovations to San Andreas Pipeline #3. Spending on capital projects
3
during the 1990's totaled approximately $350 million. In the 1999-2000 fiscal year, the SFPUC
appropriated $145 million for capital improvements to its water system and an additional $131
million is included in the capital improvement budget for fiscal year 2000-01. This level of
funding demonstrates the commitment of the SFPUC to address the capital needs of the water
system.
The Bureau of State Audits report makes twelve specific recommendations. The SFPUC's
responses to these recommendations are as follows:
Recommendation #1 - regular reporting on progress and accomplishments. The report
recommends that the SFPUC submit annual reports to the Legislature and its suburban cus-
tomers on its plans, progress and accomplishments.
SFPUC Response: The SFPUC will provide an annual report to the Legislature and our subur-
ban customers on its capital improvement plans, progress and accomplishments. The SFPUC
meets with our suburban customer agencies on a regular basis. Suburban Advisory Group
(SAG) meetings are held with all customer agencies each year. Suburban Representatives
meetings (five customer agencies plus the general manager of the Bay Area Water Users
Association) are held at least quarterly. The SFPUC will continue to convene these meetings to
discuss issues of mutual concern including its plans and accomplishments regarding the
implementation of the capital improvement program for the water delivery system.
38 C A L I F O R N I A S T A T E A U D I T O R
Recommendation #2 - facilities reliability study and water supply master plan. The report
recommends that the SFPUC complete its facilities reliability study and water supply master
plan.
SFPUC Response: The Water Supply Master Plan is near completion and is scheduled to be
released next month (March 2000). The first phase of a system reliability plan was completed
in 1995. The second phase of the Reliability Study was completed in 1999 and released in
January 2000. Phase three of the reliability study is due to be completed in approximately two
years. Over $25 million has already been appropriated for projects identified in the Reliability
Study and an additional $32 million is included for these projects in the SFPUC capital budget
for FY 2000-01 to address priority needs.
Recommendation #3 - engineering staff. The report recommends that the SFPUC continue
to pursue ways to attract and retain qualified engineering staff.
SFPUC Response: The SFPUC personnel unit was increased in 1998 by twelve positions (a
growth of approximately thirty percent) to promote additional hiring. This investment has
enabled the SFPUC to increase staffing in its engineering bureau by over sixty percent (from
97 to 157) in the past year. This effort continues with the ultimate goal of a staffing level of 237
which is the estimated number of staff needed to implement the capital improvement program.
In addition to increased staff resources, the SFPUC has developed a program management
4
consultant contract to provide additional staff expertise and training with the goal of improving
staff capabilities, productivity and retention.
Recommendation #4 - contracting procedures. The report recommends that the SFPUC
improve its contracting procedures and establish a department-wide contracting unit.
SFPUC Response: The SFPUC began revising its contracting procedures in 1997. New
standards for financial reporting and auditing were introduced in 1997. Consultant contract
language was standardized in 1998. Revisions to construction contract procedures are now
being completed. The size of the contract administration unit was doubled this year with the
addition of six new staff members. Members of the contract administration staff are being
trained on new contracting procedures as they are revised. Reports are now being produced
which give the status of all SFPUC contracts on a weekly basis. Additional staff members are
included in next year's budget so that a department-wide contracting unit can be in place by
July 1.
Recommendation #5 - contracting manual. The report recommends that the SFPUC con-
tinue updating its contracting procedures manual.
SFPUC Response: The SFPUC revised and updated its contracting manual for
consultant services contracts in 1998. Revised construction contracting procedures
are now being incorporated in a new project operations manual to be completed in
July 2000. Related training is being provided to the contract administration staff
C A L I F O R N I A S T A T E A U D I T O R 39
and project managers in the engineering bureau. This training will be undertaken on a depart-
ment-wide basis in the next six months.
Recommendation #6 - maintenance management system. The report recommends that the
SFPUC complete the implementation of its new automated maintenance management system
and train staff on use of the system.
SFPUC Response: The SFPUC identified the need for a new automated maintenance man-
agement system in late 1995. The addition of the San Francisco Cleanwater Program to the
SFPUC in 1996 introduced new needs for the proposed maintenance management system.
Selection of a new system which met all the needs of the SFPUC was completed in 1998.
Implementation of the new automated maintenance management system began in 1999 and
will be completed by the end of June 2000. Staff training in maintenance management contin-
ues to be provided.
Recommendation #7 - training for project managers. The report recommends that the
SFPUC implement a formal training program for project managers and to ensure adequate
interim training while this formal training program is being developed.
4
SFPUC Response: The new program management contract, scheduled to be operational by
summer 2000, contains a major training module for project managers. A formal project man-
agement training program is also being developed by the SFPUC. Pending commencement of
the program management contract and completion of the new formal training program, informal
training is being provided by existing SFPUC managers and consultants. Project managers are
5
also being sent to training programs offered by outside providers such as the University of
California - Extension.
Recommendation #8 - long-range financial plans. The report recommends that the SFPUC
complete and adopt long-range financial plans for the water delivery system and that these
plans include financing alternatives.
SFPUC Response: In January 2000, the SFPUC released a long-range financial report for the
water system. Another report is due this year for the Hetch Hetchy Project which supplies
water to the water system. These reports will provide the basis for the development of long-
range financial plans which will support the capital improvement program for the water system.
The long-range plans are scheduled to be completed before the end of the year.
Recommendation #9 - program management. The report recommends that the SFPUC
develop an alternative plan for the management of its capital improvement program if the
proposed consultant contract is not approved.
40 C A L I F O R N I A S T A T E A U D I T O R
SFPUC Response: A consultant services contract to enhance the capital program manage-
ment capabilities of the SFPUC is scheduled to be presented to the commission in the next few
months. This proposed contract is the product of over a year of preparation including many
4
public hearings and intense scrutiny by the city attorney, the city's Human Rights Commission
and representatives of the city's labor organizations. The Public Utilities Commission has
unanimously supported the development of this contract to supplement and enhance the
existing capabilities of the SFPUC to implement the long-range capital improvement program
for the water system. The Commission fully expects to have this contract in place by the
summer of this year.
Recommendation #10 - comprehensive capital improvement program. The report recom-
mends that the SFPUC integrate its capital improvement plans into a comprehensive capital
improvement program and seek formal approval of this program from the commission.
SFPUC Response: The SFPUC began its long-range capital improvement planning in 1994.
In 1996 the first ten-year plan for the water delivery system was produced. That plan has been
updated annually. The capital improvement program for the water system is complemented by
a long-range capital improvement plan which has been developed for the Hetch Hetchy Project
(which supplies water to the water delivery system). These two plans are coordinated in the
6
capital improvement program for the SFPUC which is approved by the commission annually as
part of the normal budget process.
Recommendation #11 - cost and schedule estimates. The report recommends that cost
estimates and schedules be completed for all Hetch Hetchy capital improvement projects.
SFPUC Response: The long-range capital improvement plan for Hetch Hetchy includes sixty-
four separate projects. Cost estimates and project schedules have been developed for fifty-
three of these projects. Cost estimates and schedules for the remaining eleven projects are
now being developed and will be completed by the end of this year.
Recommendation #12 - leadership positions. The report recommends that SFPUC leader-
ship positions be filled with individuals who have successful track records in implementing
large-scale capital improvement programs.
SFPUC Response: The general manager of the SFPUC retired effective January 27,
2000 after seven years in that position and more than 18 years with the SFPUC. He
was widely respected in the water utility industry and was a leader in statewide
planning for water rights. An industry-wide national search for a new general
manager has been initiated. While this search is underway, the Commission has
C A L I F O R N I A S T A T E A U D I T O R 41
appointed a widely-respected interim general manager with over twenty years of experience in
the water utility industry. Other senior level positions are being filled on an expedited basis to
ensure that the new general manager has a team in place with the expertise necessary to
implement the long-range capital improvement program that has been developed for the water
delivery system.
We are pleased to note that the Bureau of State Audits has endorsed the direction that the
1
SFPUC has taken in our unwavering commitment to the reliable delivery of the highest quality
water possible to our customers. We appreciate the support that your staff has given to our
efforts.
Sincerely yours,
(Signed by: John Mullane)
John Mullane
General Manager
42 C A L I F O R N I A S T A T E A U D I T O R
COMMENTS
California State Auditor’s
Comments on the Response
From the San Francisco Public
Utilities Commission
T
o provide clarity and perspective, we are commenting on
the response to our audit report from the San Francisco
Public Utilities Commission (commission). The numbers
below correspond to those we have placed in the commission’s
response.
1
While the commission is correct in saying that we acknowledge
its efforts to improve its water delivery system, it is a stretch for
it to conclude that we support or endorse the specific direction it
is taking. Our review identified numerous weaknesses in the
commission’s operation of its water delivery system. Many of its
efforts to correct these weaknesses have just recently been
implemented or are still in development. Thus, as we state in
our report, it is too soon to determine whether the commission’s
efforts will successfully improve the water delivery system.
2
The commission incorrectly states that a seven-year drought
lasted through 1995. Numerous sources, including those pro-
vided by the commission, show that a six-year drought in
California lasted from 1987 through 1992. Therefore, we stand
by our conclusion that the commission should have started
identifying alternate water supplies earlier than 1996.
3
The commission states that spending on capital projects during
the 1990s totaled about $350 million. The $270 million figure
we report on page 21 refers to the amount the commission
reported spending on capital projects it completed during the
1990s.
4
Although the commission fully expects to have its program
management consultant contract in place by summer 2000, it is
only prudent that it have a backup plan. As we state on page 27
of our report, the City and County of San Francisco’s budget
analyst is reviewing the proposed contract. Should the
C A L I F O R N I A S T A T E A U D I T O R 43
commissioners or board of supervisors not approve the
contract, commission staff may be ill equipped to handle such a
large, complex capital improvement program on their own.
5
The commission offered no evidence that project managers
received training from programs offered by outside sources.
Moreover, it was not until August 1999 that the City and
County of San Francisco notified employees that they
could participate in an extension program offered by the
University of California, Berkeley.
6
In our view, the commission’s approval of annual appropriations
for capital projects is not sufficient. Capital projects can take up
to 15 years to complete. It is essential that the commissioners
review and approve an integrated long-range plan, thus demon-
strating their commitment to supporting the entire capital
improvement program. As we state in our report, the most
recent capital improvement plans for the three water-related
divisions include about 200 capital projects with estimated costs
totaling more than $3 billion. Further, an integrated, long-range
capital improvement plan can assist the commissioners in
identifying the more critical projects to fund in the annual
budget process.
44 C A L I F O R N I A S T A T E A U D I T O R
cc: Members of the Legislature
Office of the Lieutenant Governor
Attorney General
State Controller
Legislative Analyst
Assembly Office of Research
Senate Office of Research
Assembly Majority/Minority Consultants
Senate Majority/Minority Consultants
Capitol Press Corps
C A L I F O R N I A S T A T E A U D I T O R 45