Alameda Corridor-
East Construction
Authority:
Its Planning and Contracting Is Generally
Sound, but Proposed Changes in Rail Traffic
May Affect Its Construction Program
May 2000
99135
The first copy of each California State Auditor report is free.
Additional copies are $3 each. You can obtain reports by contacting
the Bureau of State Audits at the following address:
California State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, California 95814
(916) 445-0255 or TDD (916) 445-0255 x 216
OR
This report may also be available
on the World Wide Web
http://www.bsa.ca.gov/bsa/
Permission is granted to reproduce reports.
C S A
ALIFORNIA TATE UDITOR
MARY P. NOBLE STEVEN M. HENDRICKSON
ACTING STATE AUDITOR CHIEF DEPUTY STATE AUDITOR
May 10, 2000 99135
The Governor of California
President pro Tempore of the Senate
Speaker of the Assembly
State Capitol
Sacramento, California 95814
Dear Governor and Legislative Leaders:
As requested by the Joint Legislative Audit Committee, the Bureau of State Audits presents its
audit report concerning the management practices of the Alameda Corridor-East Construction
Authority (authority). This report concludes that the authority’s planning process and contracting
procedures are generally sound, but that proposed changes in rail traffic may affect its
construction program.
Respectfully submitted,
MARY P. NOBLE
Acting State Auditor
BUREAU OF STATE AUDITS
555 Capitol Mall, Suite 300, Sacramento, California 95814 Telephone: (916) 445-0255 Fax: (916) 327-0019
CONTENTS
Summary 1
Introduction 5
Chapter 1
Planning for the ACE Program Has
Generally Been Satisfactory but
May Require Adjustments if Railroad
Traffic Is Consolidated 9
Recommendations 16
Chapter 2
Contracting Policies and Implementation
Are Generally Adequate, but Several
Changes Would Strengthen Oversight
and Assure Compliance With Regulations 17
Recommendations 23
Response to the Audit
Alameda Corridor-East Construction Authority 25
SUMMARY
RESULTS IN BRIEF
T
he Alameda Corridor-East Construction Authority (ACE)
has generally used a sound process for planning its
construction program to mitigate anticipated traffic
Audit Highlights . . . problems at rail crossings throughout the San Gabriel Valley.
However, a proposal to consolidate rail traffic in the area
Our review found that the
of the program may affect ACE’s plans, leading it to delay and
planning and contracting
possibly eliminate some projects. In addition, it has generally
processes of the Alameda
Corridor-East Construction adopted and implemented appropriate contracting policies
Authority (ACE) are generally and procedures.
sound.
However, a proposal to ACE was created in 1998 to find ways to alleviate anticipated
consolidate railroad freight motor vehicle congestion caused by an expected increase in rail
traffic may significantly affect
freight traffic in eastern Los Angeles County. It has identified
ACE’s construction program.
construction projects, ranging from low-cost improvements in
In addition, some of ACE’s safety features and signal devices at rail crossings to expensive
contract award policies
grade separations, which involve building underpasses or
conflict with regulations, and
bridges so that rail and motor vehicle traffic no longer intersect.
its conflict-of-interest code
does not cover all persons on These projects have a total estimated cost of $912 million. ACE
its contractor selection has obtained various funding commitments amounting to
committees.
roughly $370 million from local, state, and federal agencies,
as well as from the Union Pacific Railroad (Union Pacific). It
is currently seeking additional government funding to finance
the remainder of the program’s cost. Although its current
funding sources do not require a cost-benefit analysis, we believe
ACE might improve its chances of receiving future funds by
quantifying expected program benefits in dollars and comparing
them to estimated costs. This type of analysis could give ACE
an advantage when competing with other agencies for limited
government funds.
ACE’s planning process included building upon a feasibility
study, creating a project implementation plan, performing
environmental assessments, and using a project scheduling
system. These procedures ensured that ACE was addressing
key elements of the construction planning and management
process. In addition, ACE has included the public and
local governments in its planning process. In some cases,
ACE has made major design changes based upon input from
the cities affected.
C A L I F O R N I A S T A T E A U D I T O R 1
Despite the quality of its efforts, ACE may have to substantially
alter its plans if Union Pacific agrees to consolidate the majority
of its freight traffic to the southern of two lines crossing the
San Gabriel Valley. If this happens, many of the grade separa-
tions planned for the northern line may no longer be necessary.
ACE should therefore delay further work on a portion of the
northern line until the disposition of freight consolidation
is known.
For the most part, the contracting policies and procedures that
ACE has adopted ensure that contracts will be properly awarded
and monitored. These policies include awarding contracts
through a competitive bidding process and requiring contractors
to provide detailed task schedules and monthly progress reports.
Nevertheless, one of ACE’s contract award policies expands on
state and federal regulations, another conflicts with federal
regulations, and a third requires clarification. In addition, its
conflict-of-interest code may inadequately protect against
possible real or perceived conflicts because it does not include
nonemployees who sit on its contractor selection committees.
ACE rescinded another policy allowing contractors to begin
work before contract execution when we pointed out that the
policy conflicted with California Department of Transportation
guidelines. Finally, ACE violated its procedures for changing a
contract’s scope of work by failing to commit to writing a
change in scope for its program management contract.
RECOMMENDATIONS
To improve its competitive position when seeking future
funding, ACE should consider quantifying program benefits
in dollars.
To avoid spending money on projects whose benefits may be
reduced by possible rail freight consolidation, ACE should delay
activities planned for a portion of the northern rail line until
Union Pacific makes a decision in July 2000.
To assure competitive contracting, ACE should make the follow-
ing changes to its policies and procedures:
•
Revise its policies regarding noncompetitive procurement to
conform to those established in state and federal regulations.
2 C A L I F O R N I A S T A T E A U D I T O R
•
Require construction contractors to provide evidence of
appropriate licenses only upon contract award.
•
Clarify its procedure for handling cases in which ACE’s
board rejects the recommendation of its contractor selection
committee.
•
Amend its conflict-of-interest code to include members of
contractor selection committees.
To ensure that contractors complete all elements of scopes of
work, ACE and its contractors should agree in writing to any
changes in scopes of work.
AGENCY COMMENTS
The Alameda Corridor-East Construction Authority agreed
with our recommendations for the most part and will seek
guidance from its board and funding authorities on how to
best implement them. (cid:1)
C A L I F O R N I A S T A T E A U D I T O R 3
Blank page inserted for reproduction purposes only.
4 C A L I F O R N I A S T A T E A U D I T O R
INTRODUCTION
BACKGROUND
T
he Alameda Corridor-East Construction Authority (ACE)
was created in September 1998 by the San Gabriel Valley
Council of Governments (council) to manage a construc-
tion program intended to mitigate anticipated traffic problems
at rail crossings in eastern Los Angeles County. The program was
established because of concerns that an increase in railroad
freight traffic in the area would lead to problems with motor
vehicle congestion and to long delays at railroad crossings.
An increase in railroad freight traffic is expected with the
completion of major rail corridor improvements between
the ports of Los Angeles and Long Beach and downtown
Los Angeles. Recognizing that the completion of these
improvements in 2002 would trigger an increase in rail traffic
through the San Gabriel Valley, the council commissioned a
feasibility study (study) in 1997 to assess the condition of
55 rail crossings between downtown Los Angeles and Pomona.
The study predicted that an expected 60 percent increase in
train traffic and a 40 percent increase in roadway traffic would
cause the length of daily vehicle delays at rail crossings to
triple by 2020. It also forecast a dramatic increase in rail
crossing accidents, air pollution, and noise if no steps were
taken to improve traffic flows. To solve these problems, the
study proposed improving safety and signal devices at all rail
crossings, increasing queuing capacity by widening roads at
some crossings, and constructing grade separations at those
crossings expected to experience long traffic delays. A grade
separation is an underpass or bridge that separates rail and
vehicle traffic to keep it from intersecting.
The council created ACE to implement the projects proposed
in the study. ACE is governed by a seven-member board of
directors (board) consisting of a designee of the council;
representatives from the cities of El Monte, Industry,
Montebello, Pomona, and San Gabriel; and a representative
from Los Angeles County. The board meets each month and sets
overall policy for the program, including approving the
program’s scope and budget as well as any contracts greater than
C A L I F O R N I A S T A T E A U D I T O R 5
$250,000. The council can dissolve the ACE board by a majority
vote of its own board of directors. In this case, the council
would assume all the rights and responsibilities of ACE.
Because ACE is a special-purpose organization of limited
duration, the council planned for it to maintain a minimal
staff and to rely heavily on outside contractors. In May 1999,
ACE hired its first employee, a chief executive officer, and in
September 1999, after a competitive contract award process, it
contracted with the consulting joint venture Bechtel/Korve to
provide program management services. As of April 2000, ACE
had a staff of six, and the consultant’s program management
team included five full-time and four part-time employees.
Collectively, they will plan and manage the program.
The estimated cost of the program is $912 million; its estimated
time for completion is eight years. Roughly $824 million, or
90 percent of the total, is budgeted for grade separation projects.
Projects are planned for two separate rail lines, both run by the
Union Pacific Railroad (Union Pacific) since its merger with the
Southern Pacific Railroad in 1996. ACE has split the program
into two phases. Phase I includes relatively inexpensive
safety-and-signal and road-widening projects that will address
the needs at most of the rail crossings, as well as five grade
separations on the northern line and six grade separations on
the southern line. This phase is set for completion in 2003 at a
cost of $418 million. Phase II includes a signal project plus
seven grade separations on the northern line and two grade
separations on the southern line. Phase II is scheduled for
completion in 2007 at a cost of $494 million. The map in
Figure 1 shows the major project locations.
ACE has secured roughly $370 million in funding from local,
state, and federal governments and from Union Pacific. It has
also applied for $58 million in grants and other funding and has
identified another $57 million for which it plans to apply.
6 C A L I F O R N I A S T A T E A U D I T O R
C
A
L
I
F O R N I
A
S T
A
T E
A
U
D
I
T
O
R
7
AN L G O E V S L all E ey S B lvd ALHAMB R a R m A o M n i a ss S io D t n e l D M S r a a n r A G v a e b S ri A el N B lvd B ald w in A v R e am o n a B lvd BA P L A D R W K IN POMONA L os A n g el e S s a C n o B u e n r t n y ar di n o C o u nt y
GABRIEL Ave WALNUT
REDONDO MONTEREY MO
E
N
L
TE P
ue
nte
nset
Ave
WEST
ONTARIO
JUNCTION PARK S u COVINA
INDUSTRY i MONTEBELLO DIAMOND
BAR To ports PICO RIVERA
Los Angeles County
Orange County
Phase 1 grade separation
Phase 2 grade separation
Safety and signal only N
Union Pacific Railroad lines
Section of Union Pacific Railroad
line where freight traffic may be
reduced if consolidation occurs
tS selagoN
N o g ales
St
rD yawriaF
FIGURE 1
Railroad Crossing Projects Planned by ACE
605 210 T em
p
10
le
A ve
57
57 R eserv E
o
as
ir
t
S
E
t
n
d A ve T
710 M o n teb ello
B lvd
R o se H ills R d C an yo u n rn R b d u ll Fairw ay
D r
57 B rea C an yo n R d 71
5
Note: All grade separation sites are scheduled for safety-and-signal work and some are also scheduled for road widening. A grade separation for Seventh Avenue, proposed in the
feasibility study, has been completed by the City of Industry and is not shown here. For ease of reading, we have excluded the names of rail crossings where ACE has planned
only safety-and-signal work, and one rail crossing slated for both road-widening and safety-and-signal work.
SCOPE AND METHODOLOGY
The Joint Legislative Audit Committee (committee) requested
that the Bureau of State Audits perform an audit of ACE’s
management practices. The committee was generally interested
to learn how ACE’s policies and procedures are aligned to meet
program goals. It placed special emphasis on a review of ACE’s
policies and procedures for contracting.
To assess whether ACE has identified and implemented critical
steps contributing to sound planning, we reviewed the Federal
Highway Administration guidelines for feasibility studies, the
National Corridor Planning and Development Program require-
ments, the Caltrans Local Assistance Procedures Manual
(Caltrans manual), and the Department of Transportation’s
(Caltrans) guidelines on managing highway projects. We
compared these guidelines and requirements to steps included
in the council’s study, ACE’s Project Implementation Plan, and
its Project Management Guidelines and Procedures. We also
reviewed program cost estimates to determine whether they
were based on detailed support and included adjustments for
inflation. We found that they were. We then determined the
amount and firmness of various funding sources identified for
the program. Finally, we reviewed Caltrans’ manual and federal
regulations related to environmental studies and documents
and compared these to ACE’s environmental work to
determine whether ACE has fulfilled all requirements in this
area of planning.
To determine whether ACE has developed and implemented
proper contracting policies and procedures, we reviewed
applicable federal and state laws, regulations, and guidelines and
compared them to those in ACE’s Procurement Manual and its
Project Management Guidelines and Procedures. For large
contracts, we reviewed ACE’s requests for proposals, awards
process, and contract provisions. Finally, we interviewed ACE
and project management consultant staff regarding contract
monitoring procedures and reviewed the monitoring activities
for ACE’s program management contract. (cid:1)
8 C A L I F O R N I A S T A T E A U D I T O R
CHAPTER 1
Planning for the ACE Program Has
Generally Been Satisfactory but May
Require Adjustments if Railroad
Traffic Is Consolidated
SUMMARY
T
he Alameda Corridor-East Construction Authority (ACE)
satisfactorily planned for its construction program.
Nevertheless, ACE may need to change these plans due to
a potential consolidation of railroad freight traffic. ACE has
effectively planned for grade separation and railroad safety
projects by building upon the San Gabriel Valley Council of
Governments’ (council) feasibility study (study), and developing
a project implementation plan and environmental documents.
In addition, ACE has exceeded basic funding requirements by
establishing an outreach program designed to seek public
comment and support. At the same time, ACE has gained
significant funding commitments from local, state, and federal
governments. Although ACE’s current funding does not require
a rigorous cost-benefit analysis, ACE could improve its chances
of obtaining future funding by comparing program costs to
benefits quantified in dollars.
ACE has proposed a consolidation of railroad freight traffic that
may seriously alter the assumptions on which some of the
projects were based. ACE’s current plan was based on Union
Pacific Railroad (Union Pacific) projections of rail freight traffic
on the two main rail lines crossing the San Gabriel Valley and
reflects similar rates of growth in rail traffic on both lines. If the
majority of rail freight traffic is consolidated to one line, the
grade separations planned along the other line, which make up
about 44 percent of the program’s total costs, may no longer be
necessary. Because of this possibility, ACE should review the
current program schedule and delay any spending on poten-
tially unnecessary grade separations until the consolidation issue
is resolved.
C A L I F O R N I A S T A T E A U D I T O R 9
ACE HAS ADEQUATELY ADDRESSED CRITICAL
PLANNING STEPS
ACE has met critical planning requirements for its construction
program. The 1997 study commissioned by the council identi-
fied a need for the program and proposed viable solutions; ACE’s
1999 Project Implementation Plan outlined basic strategies and
objectives necessary for satisfactory completion of the project.
Detailed policy and procedure manuals and a program sched-
uling system give staff concrete methods for implementing the
overall plan.
The 1997 study addressed key elements described in the Federal
Highway Administration’s guidelines for conducting feasibility
studies. It identified a need for the program, discussed proposed
Although the feasibility alternatives, considered environmental constraints, and
study provided a schedule provided a funding strategy. In addition, the study provided a
for program completion, it schedule for program completion, preliminary cost estimates,
did not quantify program and expected benefits. The council did not, however, quantify
benefits in dollars. program benefits in dollar terms and thus did not provide a
complete analysis of costs and benefits. Such analyses are impor-
tant because they are generally considered the most objective
and credible evidence of a program’s economic benefit. Although
not required by ACE’s current grants, this type of analysis could
provide a compelling argument in favor of the program when
ACE competes with other agencies for future grants.
The 1999 Project Implementation Plan successfully built on
the study by providing an updated master schedule, an imple-
mentation strategy, a description of the funding status, and
project management controls to ensure that the project stays
on schedule and within budget. These project management
controls relate to the project’s budget, work scope, cost,
schedules, contracts, and reporting. ACE’s plan also includes
procedures for establishing quality control. In addition, ACE
identified activities that are critical to ensuring that the project
remains on schedule. The activities include issuing design and
engineering contracts, completing geotechnical testing, and
obtaining an owner-controlled insurance program to provide
umbrella coverage for ACE and its contractors.
ACE adequately defined the roles and responsibilities of program
managers in its Project Management Guidelines and Procedures.
The guidelines define the specific responsibilities of project
managers, include methods of accomplishing project tasks,
establish administrative reporting procedures, set forth limits
10 C A L I F O R N I A S T A T E A U D I T O R
of authority and approval, establish a capital project accounting
system, and discuss how to coordinate activities with other
agencies.
ACE will rely heavily on contractors. However, by segmenting
activities and projects within the program, it has reduced its
reliance on any one contractor, thus minimizing the risks associ-
ated with contractor failure. For example, ACE issued separate
contracts for environmental, disadvantaged business, and
program management tasks. In addition, it divided the design
needs for its near-term safety projects into three packages, which
it intends to award to three separate contractors. Finally, ACE
plans to hire a separate construction manager, rather than
relying on its program manager to perform this function. This
contractor will monitor progress at construction sites and over-
see the adequacy and timeliness of the work.
ACE has also developed schedules that cover the entire scope of
the project. A master project schedule provides the framework
for completing various phases of the project within eight years.
This schedule identifies completion dates for critical project
components such as design work and right-of-way acquisition.
ACE has staged projects so that nearby sites will not be under
construction simultaneously, thereby limiting the effects on
motor vehicle traffic. Because each grade separation project is
independent of other projects, each one offers its own benefits.
The program will therefore reduce traffic delays and improve
air quality in proportion to the number of projects completed,
even if the entire program cannot be finished because of a
shortfall in funding.
FUNDING COMMITMENTS COVER ONLY PART OF
TOTAL PROGRAM COSTS
Like many construction programs in their start-up phase, ACE
lacks commitments for the majority of its estimated costs. It has
ACE has secured obtained funding commitments totaling nearly $370 million, or
$370 million of approximately 41 percent of its estimated program costs of
the estimated $912 million, as shown in Figure 2. The Metropolitan Transpor-
$912 million needed tation Authority (MTA) is the largest participant, providing
to fund the program. 17 percent of project costs, or $155 million. It is followed by the
federal government, which is providing $135.5 million through
its High Priority Projects Program, and the California Transpor-
tation Commission, which is supplying $39 million through its
Interregional Transportation Improvement program (ITIP). In
C A L I F O R N I A S T A T E A U D I T O R 11
addition, under federal regulation, Union Pacific must provide
5 percent of the cost of the grade separations, or about
$40 million. ACE has also applied for $58 million in Federal
Highway Administration grants and state surplus funds and has
identified another $57 million in grants and other funds for
which it plans to apply. ACE is competing with other agencies
for the pending grants and surplus funds, and therefore this
funding is by no means certain. Funding sources for the remain-
ing $427.5 million in estimated costs remain unidentified. As we
mentioned earlier, ACE might improve its chances of gaining
additional funding by completing a cost-benefit analysis of its
program.
FIGURE 2
ACE Funding Sources
(In Millions)
Committed Funding Not Yet
Funding Secured
State
Union Pacific
$39
$40
Unidentified
Federal funding
$427.5
$135.5
$155
MTA
Funds $58 $57
applied for
Funds
identified
The California Transportation Commission has only provided
ITIP funds for the southerly rail line because it views this line as
the main freight corridor through the San Gabriel Valley. ACE
has acknowledged this restriction by planning to use ITIP fund-
ing only for its projects on the southern line.
ENVIRONMENTAL WORK HAS NOT REVEALED
SIGNIFICANT IMPACTS BUT MUST STILL BE
REVIEWED AND APPROVED
ACE is on track to complete required environmental documents
for projects under its administration that are scheduled for
design work in July 2000. It has produced individual documents
12 C A L I F O R N I A S T A T E A U D I T O R
for the safety-and-signal, road-widening, and grade separation
projects, along with technical reports that apply to the overall
program. This work includes studies of how the projects will
affect air quality and motor vehicle traffic, and whether they
will require property relocations and hazardous materials
cleanup. Some of this work has revealed the need for mitigation
to reduce environmental impacts. For instance, ACE has
identified special precautions its contractors must take during
construction to reduce dust and exhaust fumes caused by their
work. It also plans to use best management practices to avoid
soil erosion that could pollute water supplies.
Based on its studies, ACE believes the environmental impact of
its projects will not be significant. It has therefore characterized
its projects as needing categorical exclusions or environmental
assessments, a level of environmental clearance requiring less
analysis and public involvement than environmental impact
reports. ACE has submitted many of its environmental docu-
ments to the California Department of Transportation (Caltrans)
and is waiting for Caltrans to determine whether it agrees with
the conclusions that ACE reached. Ultimately, the Federal
Highway Administration must approve environmental clearance
for road-widening and grade separation projects. ACE cannot
start final design work for such projects until it receives
environmental clearance.
Although federal regulations do not usually require public
hearings for projects that do not require environmental impact
reports, ACE has made a point of seeking the input of local
governments and the public. It has been particularly receptive to
suggestions made by the cities affected. This has led ACE to
make major changes in the design concept for particular grade
ACE has made major separations. For example, the City of Industry requested that an
changes to several elevated track project be scaled back, but that one of two re-
grade separation projects maining grade separations be moved up in the schedule. It
based on input from reasoned that completing a scaled-back project earlier in the
neighboring cities. program would be preferable to completing a larger project at
the end of the program. ACE adopted the suggestion in its
project implementation plan. The City of Industry also
expressed concern that an elevated track near a residential
district would cause significant problems with noise and
impaired aesthetics. ACE is currently in the process of consider-
ing less-intrusive grade separations for this area.
C A L I F O R N I A S T A T E A U D I T O R 13
ACE has also undertaken a public outreach program. So far,
ACE’s staff and its environmental consultant have held meetings
with government officials, businesses, and residents in cities
along the rail corridor. The consultant has recorded the public
comments and will summarize them at the conclusion of the
first round of meetings, expected in mid-May 2000. ACE plans
to use these summaries to update its environmental documents
as necessary. In addition, it will give the comments and
summaries to design consultants before they begin their work
on individual projects. As design progresses, ACE plans to gain
further comments through more public meetings.
RAILROAD CONSOLIDATION COULD ELIMINATE THE
NEED FOR SOME GRADE SEPARATIONS
Based on a request by ACE, Union Pacific has undertaken a
simulation study to determine the feasibility of consolidating
freight traffic from a portion of its northern line to its southern
line. Union Pacific is undertaking the study despite prior
statements that it intended to maintain a steady ratio of freight
traffic on the two main rail lines crossing the San Gabriel Valley.
Union Pacific plans to make a decision regarding ACE’s request
by July 2000. A partial freight consolidation to the southern
line could greatly reduce traffic delays at grade crossings on a
portion of the northern line, eliminating the need for many
of the grade separations that ACE has planned on that line.
The cost of all the grade separations along the portion of the
northern line track where traffic congestion could be reduced
total $397 million, or 44 percent of the total program costs.
Figure 1 in the Introduction shows those grade separations.
Although building fewer grade separations would obviously lower
Consolidation of railroad the total cost of the ACE program, a rail freight consolidation
freight traffic might would incur other related costs that would partially offset any
reduce the need for up to savings. Prime among these would be the cost of expanding
$397 million in grade capacity on the southern rail line to accommodate the extra rail
separations, but will likely traffic. According to ACE, Union Pacific has indicated that it will
entail other costs. look to ACE to finance the costs of such capital improvements as
additional track and widened bridges. In addition, extra rail traffic
on the southern line may increase motor vehicle traffic delays at
rail crossings not currently scheduled for grade separations, mak-
ing new grade separations necessary. Finally, increased rail traffic
on this line could have other environmental impacts, such as
increased noise, that would call for mitigation. Nevertheless, ACE
believes that freight consolidation is worth considering.
14 C A L I F O R N I A S T A T E A U D I T O R
Given the potential for railroad freight consolidation, ACE must
soon consider the effect that such consolidation might have on
its near-term activities. One of the projects ACE has planned
and one being managed by the city of Los Angeles located on
the northern line are set to begin work close to the time that the
railroad expects to complete its consolidation simulation study
in July 2000. Specifically, design of the Ramona Boulevard grade
separation is scheduled to begin in fall 2000, while the Valley
Boulevard grade separation is already under way, according to its
original funding timetable. The Valley Boulevard project is
included in the ACE construction program and is fully funded
by the MTA as part of its 17 percent matching commitment to
ACE, but the project is administered by the city of Los Angeles.
We estimate that work scheduled for the Ramona Boulevard and
Valley Boulevard projects between April 2000 and March 2001
will cost a total of $5 million.
When we inquired about the scheduling for these projects,
ACE’s chief executive officer stated that if a freight consolidation
is in fact promising, he will recommend to local officials and his
board that work be deferred on the Ramona Boulevard project.
He also indicated that he plans to contact the city of Los Angeles
to inform them that the railroad may consolidate freight traffic
to the southern line. He stated that the Valley Boulevard project
is not under ACE’s administration, but that he believes it may
warrant grade separation even if a freight consolidation occurs,
to eliminate motor vehicle traffic delays created by a nearby
freight switching yard. The chief executive officer further stated
that he had heard that the Valley Boulevard project was not
close to construction so that it was unlikely that major spending
would occur before Union Pacific reached a conclusion on the
feasibility of consolidating freight traffic. However, when we
inquired with the MTA about whether the Valley Boulevard
project was behind schedule, we were told that funding for the
first phase of the project had actually been accelerated, indicat-
ing that work may be ahead of schedule.
If Union Pacific finds that railroad freight consolidation is
feasible, ACE will have to take immediate steps that will affect
the program in both the short- and long-term. First, it will have
to suspend all planned activities along the northern rail line
until it can determine the likely effect of freight consolidation.
Second, it will have to estimate this effect. For example, if Union
Pacific proposes to decrease freight traffic on the northern line
by 80 percent, ACE would probably find that its revised estimate
of traffic delays would no longer warrant many of its planned
C A L I F O R N I A S T A T E A U D I T O R 15
projects along this line. If, however, Union Pacific proposes
decreasing freight traffic on this route by only 10 percent, ACE
would probably find that most, if not all, of its planned projects
are still needed. Third, ACE will have to calculate any additional
If freight consolidation is costs associated with consolidation, such as railway improve-
deemed feasible, ACE will ments and environmental mitigation activities, and compare
need to take immediate these to the cost savings from planned projects that can be
steps that will affect the eliminated. To determine additional costs, ACE will have to
program. negotiate with Union Pacific concerning the portion of railroad
improvement costs that ACE will finance. ACE will also have to
revisit its environmental analyses of the program and determine
the affects of freight consolidation and identify necessary miti-
gations. At the same time, ACE will have to determine whether
funds earmarked for northern line projects can be shifted to new
or existing projects on the southern line and if other financing
for new projects is feasible. Finally, based on all of these factors,
it will have to decide whether or not to pursue the rail freight
consolidation option.
RECOMMENDATIONS
To improve its competitive position when applying for future
funding, ACE should consider quantifying expected program
benefits in dollars and comparing them to estimated costs.
To avoid spending money on projects whose benefits may be
vastly reduced by rail freight consolidation, ACE should delay
activities planned for a portion of the northern rail line until
Union Pacific makes a decision about the feasibility of consoli-
dation and ACE can weigh the effects on the program. ACE
should also keep the city of Los Angeles informed as to the
status of its ongoing railroad consolidation discussions. (cid:1)
16 C A L I F O R N I A S T A T E A U D I T O R
CHAPTER 2
Contracting Policies and
Implementation Are Generally
Adequate, but Several Changes
Would Strengthen Oversight and
Assure Compliance With Regulations
SUMMARY
T
he Alameda Corridor-East Construction Authority (ACE)
has generally adopted and implemented policies and
procedures that assure the proper awarding and monitor-
ing of contracts. Moreover, external government agencies,
such as the California Department of Transportation (Caltrans)
and the Metropolitan Transportation Authority (MTA), provide
added oversight of large contracts and certain expenditures.
Nevertheless, one of ACE’s contract award policies expands upon
state and federal regulations, another conflicts with federal
regulations, and a third requires clarification. In addition,
ACE’s conflict-of-interest code may not adequately cover all
persons who sit on its contractor selection committees. When
we began our audit, ACE’s contracting policies included a
provision that put at risk cost reimbursement from local, state,
and federal agencies by allowing contractors to start work before
final contract approval. Finally, ACE failed to commit to writing
changes in the scope of a consultant contract, a violation of
contract provisions and good management practices.
CONTRACT AWARD POLICIES ARE GENERALLY
ADEQUATE, BUT SOME POLICIES SHOULD BE
REVISED OR ELIMINATED
ACE’s contract award policies generally comply with the
Caltrans Local Assistance Procedures Manual (Caltrans manual).
This manual summarizes relevant federal and state laws and
regulations and is the basic reference used by local agencies
receiving federal or state funding for transportation programs.
For instance, ACE policies require the use of a request-for-
proposals process to solicit offers for professional or technical
C A L I F O R N I A S T A T E A U D I T O R 17
services worth more than $25,000 from competing contractors.
In addition, requests for proposals must be advertised, must
identify the factors to be evaluated in awarding the contract,
and must allow contractors a minimum of 20 days to respond.
Despite the general adequacy of ACE’s contract award policies,
we found three instances in which ACE should change or clarify
ACE has expanded these policies to ensure adequate competition. First, ACE has
the conditions for expanded the circumstances under which noncompetitive
noncompetitive procurements of goods or services are allowed beyond those
contracting beyond permitted in federal and state regulations. Federal and state
those allowed in regulations generally allow noncompetitive procurements in
regulations. the following cases: (1) when only one responsible source of
supply is available, (2) when there is an unusual or compelling
urgency, or (3) when the public’s interest would not be served
by competitive procurement. In contrast, ACE allows for non-
competitive procurements in the following situations:
•
An emergency situation, as defined in ACE’s Emergency
Procedures, exists.
•
Only one responsible source of supply is available.
•
ACE’s need is of a unique and compelling urgency.
•
The equipment to be purchased is of a technical nature and
the procurement thereof without advertising is necessary to
ensure standardization of equipment and interchangeability
of parts.
•
The goods are for testing or experimental purposes.
We asked ACE’s senior project manager why the policy for
noncompetitive procurements was broader than that presented
in federal and state regulations. He told us that ACE would only
make noncompetitive procurements where the ultimate owner
of improvements, either Union Pacific Railroad (Union Pacific)
or the cities, require ACE to buy from a specific vendor for
purposes of standardization. If the broader policy is therefore
designed to allow for situations where only one responsible
source of supply is available, we believe that the three additional
circumstances shown in the policy are unnecessary and will
only create confusion. If the broader policy is meant to provide
for situations where more than one responsible source of supply
is available, but selection is limited to one vendor, it conflicts
with state and federal regulations. Noncompetitive procure-
ments should rarely occur, and when they do they should be
18 C A L I F O R N I A S T A T E A U D I T O R
limited to those circumstances contained in federal and state
regulations. Otherwise, ACE may not receive the highest quality
of goods and services at the lowest cost. Moreover, ACE risks
losing federal funding if procurements are subsequently deter-
mined to violate regulations.
Second, ACE requires that a construction contractor have
appropriate state licenses when it submits its contract proposal.
In contrast, the Caltrans manual specifies that agencies can
require state licensure only at the time of contract award. This
requirement stems from a federal regulation designed to
ensure that out-of-state contractors are not unfairly barred
from competition. Although this policy conflicts with
regulations, it has not had an adverse effect on ACE’s
largest contract selections. Specifically, since the project
has not yet reached its construction phase, ACE has not barred
any construction contractors from submitting proposals based
on this requirement.
Third, ACE should clarify its policy governing selection commit-
tee recommendations to the board of directors (board) for the
awarding of contracts. The existing policy permits the board
ACE’s policy for rejecting to reject the selection committee’s recommendation and
selection committee return it to the committee for further consideration and
recommendations is resubmission to the board. However, the current policy does
unclear. not require that the board indicate what criteria it used to reject
the recommendation, so that the selection committee can
reconsider only those areas the board found unacceptable.
Since the selection committee has an important role in ensuring
a fair and competitive process, it is important that the board
limit and clearly define the terms under which it returns a
recommendation for further consideration.
In addition, we found that ACE’s conflict-of-interest code
may not adequately cover all persons involved in making or
influencing significant agency decisions. ACE’s code covers its
board members, its staff, and certain employees of its project
management consultant team, but does not include all persons
sitting on its contract selection committees. Committee mem-
bers include persons from outside ACE, such as representatives
from cities, Caltrans, and the Metropolitan Transit Development
Board of San Diego. According to ACE’s Conflict-of-Interest and
Disclosure Code, board members, employees, and consultants
who participate in making construction authority decisions that
could foreseeably have a material effect on their own financial
interests should fall under its conflict-of-interest code and
C A L I F O R N I A S T A T E A U D I T O R 19
should file statements of economic interest. Likewise, an
opinion issued by the Fair Political Practices Commission states
that all persons on committees that have made recommenda-
tions affecting the final outcome of an agency’s decision over an
extended period of time should be included in the agency’s
conflict-of-interest code. We believe that ACE’s selection
committees should be viewed as part of a system that has
historically had and will have a significant effect on decision
making. Persons participating in this system should therefore be
included in the conflict-of-interest code.
Instead of including selection committee members within its
conflict-of-interest code, ACE distributes a letter to committee
members that discusses conflict-of-interest standards in general
ACE does not require and requires members to sign a copy of the letter and return
nonemployees on its it to ACE at the first meeting of the selection committee.
contract selection Although this letter provides some guidance for situations in
committees to disclose which conflicts may arise, it does not require that selection
economic interests they committee members publicly disclose any economic interests
may have. they have that could pose conflicts. Since the contract award
process relies to a significant extent on the recommendations of
committee members, it is imperative that ACE assure that
decisions made by each member are free of real or perceived
conflicts of interest, to protect itself from future criticism by
unsuccessful contract bidders.
Finally, ACE adopted a contracting policy that would have
allowed contractors to begin work before the final contract was
signed if ACE’s chief executive officer believed the contract
negotiations would be successfully concluded and if it was
important that the start of work not be delayed. In these cases,
the policy authorized the chief executive officer to give a
contractor a Notice to Proceed, permitting the contractor to
begin work before the contract had been executed. This policy
contradicted the Caltrans manual, which prohibits reimburse-
ment for work performed before a contract is signed. After we
informed ACE that this policy could put its federal and state
reimbursements at risk, ACE revised the policy to state that
contractors will not be authorized to start work until a contract
has been fully executed.
20 C A L I F O R N I A S T A T E A U D I T O R
CONTRACTS AWARDED FOR THE ACE PROGRAM
HAVE FOLLOWED ESTABLISHED PROCEDURES AND
HAVE BEEN REVISED ACCORDING TO EXTERNAL
RECOMMENDATIONS
Since 1996, the San Gabriel Valley Council of Governments
(council) has executed 9 contracts and ACE has executed
another 4 contracts related to the construction program, all for
consulting work. We reviewed the 3 largest of these 13 contracts,
1 contract executed by the council and 2 executed by ACE, and
found that both the council and ACE adhered to proper award
procedures. For example, the process for obtaining project
management services included a detailed request for proposals,
sufficient advertising, selection based on published criteria, and
adequate contract terms. ACE reviewed proposals from 6 firms
and awarded the contract to the highest-rated contractor,
Bechtel/Korve.
Following requirements in the Caltrans manual, ACE requested
ACE amended its that Caltrans conduct an audit of the Bechtel/Korve contract. At
standard provisions for the time of our fieldwork, Caltrans provided this service for
consulting contracts in consulting contracts exceeding $75,000. The purpose of the
response to the audit was to alert ACE to any potential problems relative to the
recommendations of a provisions contained in the contract, the cost/price proposal,
Caltrans audit. and the contractor’s cost-accounting system. Caltrans’ results
were basically positive, although its auditors found some
deficiencies. For example, the contract included no provisions
setting a ceiling on the amount of the contract or requiring
ACE’s approval of the use of subcontractors; it included a
cost-plus-a-percentage-of-cost fee structure prohibited by federal
regulation; and it contained some relatively small cost items
that were either unallowable or unwarranted. ACE corrected
these deficiencies with the Bechtel/Korve contract and incorpo-
rated Caltrans’ recommendations in its standard provisions for
future consulting contracts.
The MTA will provide another form of external control
over project expenditures. For example, a memorandum of
understanding between ACE and the MTA states that ACE
must submit quarterly progress and expense reports. The MTA
reviews, approves, and reconciles these reports to the budget
before it reimburses the funds. In addition, the MTA has the
authority to conduct audits of the project as needed to ensure
that ACE is using MTA grant funds appropriately as defined in
the scope of work. The MTA is currently in the process of con-
ducting two administrative audits of ACE’s subcontractors, with
findings to be issued by the end of May 2000.
C A L I F O R N I A S T A T E A U D I T O R 21
CONTRACT MONITORING POLICIES ARE GENERALLY
SOUND, BUT ACE MUST BETTER ABIDE BY ITS CHANGE
ORDER POLICY
ACE’s contract monitoring policies and procedures are basically
sound. They require that contractors provide detailed schedules
for task completion, monthly progress reports, and detailed
invoices; that contracts include specific deliverables; and that
ACE project managers review contractor deliverables, progress
reports, and invoices. For example, ACE has used industry
standards to segment the construction program into logical
components. By adopting such standards, ACE will require
contractors to provide details on the staff, equipment, and
materials to be used during the design and construction of its
projects. ACE will use this information in conjunction with
contractor-provided activity schedules to track the progress of
program components. It will also use the information to develop
what is called a critical path plan that schedules the project,
coordinates the work, and monitors and analyzes progress to
identify potential schedule delays. ACE will update the auto-
mated schedule using progress reports and information gained
from weekly status meetings with contractors.
To determine whether ACE follows its monitoring policies and
procedures, we reviewed ACE’s monitoring of its project man-
agement consultant, Bechtel/Korve. During the first six months
of the contract, we found that ACE monitored consultant
progress by holding weekly status meetings, maintaining a
listing of deliverables due during the phase and those received,
and reviewing invoices. However, during this period, neither
ACE nor Bechtel/Korve developed a detailed schedule for when
contract tasks and deliverables were to be completed. Instead,
ACE accepted contract deliverables, mostly made up of draft
reports and policies, by reviewing the deliverables, returning
them to the consultant for revision, and filing them after
modifications were completed. In a few cases, ACE formally
accepted deliverables, as witnessed by the approval of ACE’s
As it begins to contract
board. ACE has since improved its monitoring in this area.
for design and
Specifically, during the next six-month scope of work that began
construction services,
February 4, 2000, Bechtel/Korve gave ACE a detailed schedule
ACE must assure that all
indicating expected completion dates for specific deliverables.
changes in the scope of
work be in writing.
As the agency and its program management consultant monitor
the progress of a project, they may become aware of a need for
changes in the contractor’s scope of work. ACE included a
provision in the Bechtel/Korve contract stating that it would not
22 C A L I F O R N I A S T A T E A U D I T O R
compensate the consultant for any services in addition to those
listed in the scope of work unless ACE authorized the services in
writing. In December 1999, however, ACE and Bechtel/Korve
verbally agreed to change the scope of services to include one
new task and one redefined task, reallocating about 900 hours,
or 8 percent of the contracted hours, from old to new tasks.
Although the change was relatively small in this case and did
not add to the time or cost of the original contract provisions, it
is essential for ACE to properly control the change order process
as it begins to contract for design and construction services.
Without written and signed change order agreements, even for
changes involving no additional time or cost, ACE opens itself
up to misunderstandings with its contractors and reduces its
chances for receiving all the services it expects.
RECOMMENDATIONS
To ensure competitive contracting, ACE should make the follow-
ing clarifications and changes to its policies and procedures:
•
Revise its policies regarding noncompetitive procurement to
mirror those contained in federal and state regulations.
•
Require construction contractors to provide evidence of
appropriate licenses only upon contract award.
•
Clarify its policy to require the board, when it rejects the
recommendations made by its selection committees, to
specify those aspects of the original evaluations that it found
deficient.
•
Amend its conflict-of-interest code to state that members of
contractor selection committees be required to disclose
economic interests in the same manner as ACE employees.
To ensure that contractors complete all elements of scopes of
work, ACE should write out detailed descriptions for all changes
in scope, including any agreed-to deliverables. Both parties
should sign these change orders.
C A L I F O R N I A S T A T E A U D I T O R 23
We conducted this review under the authority vested in the California State Auditor by
Section 8543 et seq. of the California Government Code and according to generally accepted
government auditing standards. We limited our review to those areas specified in the scope
section of this report.
Respectfully submitted,
MARY P. NOBLE
Acting State Auditor
Date: May 10, 2000
Staff: Doug Cordiner, Audit Principal
Jim Sandberg-Larsen, CPA
Theresa Gartner, CPA
Vikram Mandla
24 C A L I F O R N I A S T A T E A U D I T O R
Agency’s comments provided as text only.
Alameda Corridor-East Construction Authority
3871 East Colorado Boulevard, Suite 100
Pasadena, CA 91107
April 28, 2000
Ms. Mary P. Noble
Acting State Auditor
Bureau of State Audits
555 Capitol Mall, Suite 300
Sacramento, CA 95814
Dear Ms. Noble:
On behalf of the Alameda Corridor-East Construction Authority, I am providing comments on your
draft audit report on the management practices of our agency.
First, I want to commend the State Auditor's office for a thorough and professional job the team did
on this audit. Your staff has done its best to understand our project and how we are organizing to
implement it. In light of the thoroughness of your audit, we are encouraged by the positive findings
included in your report and the relatively few and straightforward recommendations for improve-
ments on our part.
As to the recommendations contained in the report for the most part we agree with them. Once the
report is public we will present it to our Board of Directors with a suggested response to each
recommendation. There are three areas that the audit report focuses on that we believe we should
comment on at this point, however.
Delaying Project Elements While Awaiting Rail Freight Consolidation Studies - The report
recommends delaying elements of the project whose justification may be diminished by a consoli-
dation of Union Pacific Railroad (UPRR) freight traffic until a consolidation study now in process is
completed. As we've shared with the audit staff, the ACE Construction Authority, it's parent agency
the San Gabriel Valley Council of Governments, and the Southern California Association of Gov-
ernments have proposed freight consolidation of varying degrees on many occasions over the last
five years. On each occasion, the UPRR dismissed consolidation over capacity and future traffic
growth concerns. Notwithstanding this history, as the report indicates, we have raised the matter
once again with the UPRR and they are currently considering it. Unfortunately, even if the railroad's
response is neutral-to-positive, it will leave many unanswered questions as to whether such a plan
offers net benefits. The report acknowledges unknowns about the public cost for necessary rail-
road capacity expansion, sources of funding for those improvements, the impacts of consolidation
and costs to mitigate them. Simply stopping work on certain elements of the project in the face of
such major uncertainties may not be the best approach for the Authority to take. Nevertheless, the
point raised in the report is valid and the Authority will have to continue to weigh its options as it
moves forward.
C A L I F O R N I A S T A T E A U D I T O R 25
Revised Policies on Noncompetitive Procurement - The report states that the Authority's
policies permitting non-competitive procurement in certain circumstances expand on federal and
state regulations and should be restricted to cover fewer circumstances. We believe the provision
in our policies questioned by the report are explicitly permitted by the Federal Acquisition Regula-
tions and not prohibited by state regulations. The provisions were included in our policy in anticipa-
tion of the Authority being required by the UPRR or local jurisdictions (the ultimate owners and
maintainers of the improvements) to install specific materials or equipment for standardization
purposes. In any event, if the Authority finds a non-competitive procurement necessary to meet
these specific railroad or city requirements, it will seek advance guidance from the appropriate
funding authorities.
Expanding our Conflict of Interest Code to Cover Technical Evaluation Committee (TEC)
Members from Outside Public Agencies - The report states that our current practice requiring
TEC members from other public agencies to certify compliance with conflict of interest regulations
does not go far enough to protect against real or perceived improprieties. We are more than willing
to address the deficiency in our existing certification process cited in the report, though we are not
sure the specific recommendation to cover employees of other public agencies under our Conflict
of Interest is the most effective way of doing so. As we have indicated to your staff, our TECs are
formed separately for individual procurements, vary in membership from procurement to procure-
ment and typically are only in existence for 1-2 months. Conversely, our economic disclosure
policy (which is governed by the County of Los Angeles) is oriented around annual filings of Board
members, employees and consultants who have longstanding, ongoing involvement in the organi-
zation. I will review your recommendations with my Board and will use their guidance along with
your recommendations to develop some additional procedures to address your concerns.
In conclusion, the ACE Construction Authority appreciates the constructive comments included in
the audit. Please feel free to contact me should you have any questions regarding this matter.
Sincerely,
(Signed by: Rick Richmond )
Rick Richmond
Cheif Executive Officer
26 C A L I F O R N I A S T A T E A U D I T O R
cc: Members of the Legislature
Office of the Lieutenant Governor
Milton Marks Commission on California State
Government Organization and Economy
Department of Finance
Attorney General
State Controller
State Treasurer
Legislative Analyst
Senate Office of Research
California Research Bureau
Capitol Press
C A L I F O R N I A S T A T E A U D I T O R 27