FCMAT
Comprehensive Review Facilities Management
Read the report at Berkeley Unified School District ↗
Berkeley
Unified School
District
Facilities Management
Comprehensive Review
July 2003
Administrative Agent
Larry E. Reider
Office of Kern County
Superintendent of Schools
Chief Executive Officer
Thomas E. Henry
Facilities Management
This summary provides some conclusions regarding the most significant conditions detailed in
FCMAT’s assessment of the facilities in the Berkeley Unified School District.
Board Policies
Most of the board policies FCMAT examined were deficient, either because they were out of date
or because they did not include certain components. The district has an aggressive program to
update board policies, and several of the facilities polices were updated and adopted during the
course of this review. This assessment should be helpful in completing the update of district poli-
cies. Included are recommendations for areas where policies are necessary.
School Safety and Security
The Findings detail several concerns related to school safety. Areas designated for loading and
unloading of students were often ignored by parents, and the school staff did not address the is-
sues. Unsupervised adults were observed on campus and were not challenged by school-site staff
( see standard1.6). Poor campus control and adult supervision are commonly observed.
Additionally, hallway and outside security lighting was a problem at many sites (standard 1.8).
The FCMAT study team also observed several fire hazards (standard 1.14), uncertified fire
extinguishers (1.16), and the absence of an employee safety training program (1.25, 1.26, 1.27).
Safety plans were not available at all school sites (1.3). Fire drills were not conducted or record-
ed properly at school sites (1.10). Boiler inspection and maintenance was not properly document-
ed (1.23).
Absence of a board policy on fingerprinting classified employees, required by law, creates a huge
amount of exposure for the district (1.3). Control, inventory and safety issues related to class-
room and custodial chemicals were also very evident (1.4, 1.11, 1.24).
Facility Planning
The district does not have a long-range facilities master plan (2.1), and lack of such a plan leads
to other planning and staffing (2.5) difficulties. However, the district does extremely well in
funding and constructing projects. Bond monies, coupled with aggressive efforts to capture state
funding and good oversight of the construction of individual projects, was evident.
In contrast, the district does not collect developer fees for which it is likely eligible now and in
the future (2.14). The district cannot afford to overlook this source of funding. More could also
be done with the district’s asset management plan for facilities (2.15).
Energy Management
Energy consumption in the district can be better managed, particularly heating and air condition-
ing systems. Some upgrades are being performed as part of modernization or other construction,
but many facilities could yield savings now. The district should create an energy-management
policy and an aggressive program for lower energy consumption and costs (8.1).
Facilities Managment 1
Class-Size Reduction Facilities
Implementation of the state-funded K-3 class-size reduction program imposed huge facility obli-
gations on the district. Berkeley Unified has done an unusually good job of providing appropriate
classrooms for those students (7.2).
Community Use of Facilities
There is extensive community use of district facilities, but neither the Business Department nor
the Facilities Departments appear to want to administer the function. The area is not appropri-
ately organized or staffed and is rife with internal control problems.
District Operations Building
The district operations building on Oregon Street is rundown, unsightly, and in need of major
restoration if it is to continue to house district functions, particularly those that serve the public.
There is some discussion about the future of the building and its site, and it seems that repairs
have been postponed until resolution of that issue. In the meantime, several district customer-ser-
vice functions operate out of a building that is unsightly from the outside and much worse on the
inside. The district should decide what it wants to do with the building and accomplish that goal.
District Technology Plan
The district has a good plan for incorporation of technology in the instructional program. The
plan, however, lacks an identifiable funding source. Therefore, expectations for technology are
tied to the efforts of individual schools to raise money for this purpose. Expectations are neces-
sarily low for near-term progress in the current funding environment (9.2).
Current Average Asessment
FCMAT’s initial assessment of the Berkeley Unified School District included 111 professional
and legal standards. The average rating of the standards is 5.75. Nineteen of these standards have
been targeted for review in the next six-month progress period and are identified below.
Standards Proposed for the First Six-Month Review
1.3 Plan for Protection of People and Property
1.4 Restrictions on Flammable and Toxic Materials
1.6 Monitoring of Bus Loading/Unloading Areas for Safety
1.21 Compliance with Federal AHERA Laws
1.23 Safety of Boilers and Fired Pressure Vessels
1.25 Maintenance of a Comprehensive Employee Safety Program
2.1 Maintenance of a Long-Range Facilities Master Plan
3.6 Maintenance of a System for Tracking Project Progress
4.3 Appropriate Project Records and Drawings are Maintained
5.3 Conflict of Interest Statements and Compliance
6.1 Compliance with CDE Regulations
6.2 Equity with Other Facilities, Appropriate to Educational Program
6.3 Adequacy for Instructional Program Needs
8.1 Energy Conservation Policy
8.2 Energy Accounting System
8.3 Completion of Energy Analyses
2 Facilities Managment Facilities Managment 3
8.6 Procedures for Evaluation of Maintenance and Operations Staff
8.11 Implementation of a Planned Program Maintenance System
10.3 Maintenance of Records and Cash Controls on Civic Center Funds
2 Facilities Managment Facilities Managment 3
4 Facilities Managment Facilities Managment 5
1.1 School Safety—CDE Civil Defense and Disaster Planning Guide
Professional Standard
All school administrators should be thoroughly familiar with the California Department of Edu-
cation, Civil Defense and Disaster Planning Guide for School Officials, 1972. [EC 32000-32004,
32040, 35295-35297, 38132, 46390-46392, 49505, GC 3100, 8607, CCR Title 5 §550, 560, Title
19 §2400]
Sources and Documentation
1. Board Policy
2. Emergency plan documentation (district-published documents)
3. Visible building evacuation plans
4. Emergency exit signage
5. Evidence of training of school site students and staff
6. First aid kits
Findings
1. Board policies were not provided. They are in the process of being updated.
2. Emergency and disaster planning guides are not consistently maintained at each
school site. Different sites had different levels of documentation.
3. Some staff members noted the lack of central district coordination and direction for
major emergencies.
4. Most sites reviewed had some civil defense and disaster planning materials available.
5. All sites reviewed had appropriate first-aid kits.
6. Some sites had missing exit signs.
7. Building evacuation plans are written rather than graphic and are posted in most class-
rooms, some offices, libraries, MPRs and other spaces.
8. Fire and disaster drills are not consistently reported to the district office, and the dis-
trict office does not follow up on delinquencies.
9. Most staff members could locate the School Crisis Plan.
Recommendations and Improvement Plan
1. Update board policies and administrative regulations regarding emergency, civil de-
fense and disaster planning.
2. Establish a common emergency operations plan that incorporates civil defense and
disaster planning.
3. Customize the emergency operations plan for each site’s unique conditions.
4. Adopt procedures to provide for an annual review, and update for the emergency op-
erations plan.
4 Facilities Managment Facilities Managment 5
5. Continue regular disaster preparedness exercises at school sites. Adopt procedures to
ensure the exercises take place, they are reported to the district office, and the district
office follows up on delinquent exercises.
6. As modernization or improvement funds become available, implement upgrades for
exit signage.
7. Provide annual training for all staff members regarding the location of the emergency
procedure documents and first-aid kits.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
6 Facilities Managment Facilities Managment 7
0 1 2 3 4 5 6 7 8 9 10
1.2 School Safety—Appropriate Security Devices in Buildings
Professional Standard
The district includes the appropriate security devices in the design of new buildings as well as in
modernized buildings. [EC 32020, 32211, 35294-35294.9, 39670-39675]
Sources and Documentation
1. Observation of buildings
2. Discussions with facilities staff
3. Discussions with maintenance and custodial staff
4. Discussions with site supervisor/support staff
Findings
1. The district has installed a variety of security devices (e.g., door sensors, motion de-
tectors) in offices, multipurpose rooms, computer labs and other sensitive areas.
2. The district has installed video cameras at the high school.
3. Staff reported that these systems were well maintained.
Recommendations and Improvement Plan
1. Annually review and update (as necessary) board policies and administrative regula-
tions regarding security devices, particularly the use of video cameras on campus.
2. Annually review district design standards to ensure that the continued incorporation of
security devices meets the various needs of the district.
3. As modernization funds are available, upgrade and expand the use of the security sys-
tems to cover most, if not all areas of each school site.
4. Establish a priority list of sites related to security issues in order to maximize the cost/
benefit relationship when installing security devices.
Standard Implemented: Partially
July1, 2003 Rating: 6
Implementation Scale
Not Fully
6 Facilities Managment Facilities Managment 7
0 1 2 3 4 5 6 7 8 9 10
1.3 School Safety—Plan for Protection of People and Property
Professional Standard
Demonstrate that a plan of security has been developed, which includes adequate measures of
safety and protection of people and property. [EC 32020, 32211, 35294-35294.9]
Sources and Documentation
1. Board policy
2. Safety plan documentation
3. Intrusion alarm system
4. Exterior lighting
5. Perimeter access and fencing
6. Visitor’s log
7. Trespassing signage
8. Key issuance procedures
Findings
1. Board policies were not provided. They are in the process of being updated.
2. The district did not have consistent safety plan documentation at all schools.
3. Intrusion alarms and exterior lighting appeared to be in place.
4. Elementary and middle school sites typically did not have complete perimeter fencing.
5. The high school site had perimeter fencing and restricted access gates, but security
was lax. Students opened a locked exterior door to allow access and gates were not
always monitored.
6. Visitor logs and ID stickers were fairly consistently maintained and issued.
7. Trespassing signage was inconsistent, and many signs need to be replaced.
8. Site staff and maintenance attempt to discourage vandalism and graffiti by immedi-
ately covering and repairing the afflicted area.
9. The Principal (or designee) typically controls access to school keys and inventory
stock, and keys are issued only to employees who regularly need them to carry out the
normal activities of their position. Substitute teachers receive keys and are required to
turn them in at the end of the day.
10. No board policy was found regarding fingerprinting of classified employees.
Recommendations and Improvement Plan
1. Increase enforcement of restricted access to sites.
2. Consider adding perimeter fencing to all sites.
3. Develop procedures to train all school personnel on the new plan.
8 Facilities Managment Facilities Managment 9
4. As modernization funds are available, upgrade lighting, signage and other security
measures.
5. Continue requiring visitors, vendors, and contractors to sign the visitor log and iden-
tify workers.
6. Continue use of visitor identification.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
8 Facilities Managment Facilities Managment 9
0 1 2 3 4 5 6 7 8 9 10
1.4 School Safety—Restrictions on Flammable and Toxic Materials
Professional Standard
Ensure that the custodial and maintenance staff are regularly informed of restrictions pertaining
to the storage and disposal of flammable or toxic materials. [EC 49341, 49401.5, 49411, F&AC
12981, H&SC 25163, 25500-25520, LC 6360-6363, CCR Title 8 §5194]
Sources and Documentation
1. Board policy
2. Hazard communication program
3. Availability of MSDS copies
4. List of hazardous substances on site
5. Evidence of training programs or sessions
6. Appropriate labeling on pipes and storage areas
Findings
1. Board policies were not provided.
2. The district does not have a hazard communication program.
3. The district does not have policies or procedures regarding MSDS copies.
4. Few custodial rooms had MSDS notebooks.
5. Few maintenance areas had MSDS notebooks.
6. There was no evidence of MSDS sheets or chemical inventory in the science rooms.
7. There is no way to tell when each MSDS notebook has been updated.
8. Some training of maintenance/custodial staff occurs each year.
9. Pipes in the boiler rooms are rarely labeled.
Recommendations and Improvement Plan
1. Develop board policies, administrative regulations and procedures regarding the col-
lection and dissemination of MSDS sheets.
2. Develop board policies, administrative regulations and procedures regarding the pur-
chase, storage and handling of hazardous materials.
3. All buildings and grounds staff, plant managers, and employees should receive in-
service training on hazardous substances in their work area at the time of their initial
assignment and whenever a new hazard is introduced into their work area.
4. Pursuant to Code of Regulations, title 8, section 5194 (e) (1) (A), a complete list of
hazardous substances must be provided within the written hazard communication pro-
gram, preferably with an indication of the work area where the substances are found.
10 Facilities Managment Facilities Managment 11
5. Provide the appropriate fire department for each school with a list of hazardous mate-
rials stored in science labs.
6. Outside contractors should be informed of hazardous substances that are present on
the site. It is the contractors’ responsibility to disseminate this information to their
employees and subcontractors.
7. Develop a written hazard communication program in accordance with the California
Code of Regulations, Title 8, Section 5194.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
10 Facilities Managment Facilities Managment 11
0 1 2 3 4 5 6 7 8 9 10
1.5 School Safety—Documented Process for Key Control
Professional Standard
The district has a documented process for the issuance of master and sub-master keys. A
districtwide standardized process for the issuance of keys to employees must be followed by all
district administrators.
Sources and Documentation
1. Board policy
2. Site observations and interviews
3. Interviews with site administrators
Findings
1. FCMAT was unable to obtain a copy of the current board policy relating to key con-
trol. The district is reportedly in the process of adopting a new policy.
2. Of the sites visited, no uniform system of key control was in place. One site had the
keys locked in the secretary’s desk. Another school had a locking key box, but it was
not fastened in a secure location behind closed doors. Another school had a locking
cabinet controlled by a single employee who signs all keys in and out.
3. There was no consistency among the sites for issuing keys to substitute teachers. One
school simply put the classroom key in the substitute teacher’s folder with the un-
derstanding that the key and folder would be returned at the end of the day. Another
school had the secretary physically issue the key to the substitute and had the substi-
tute teacher sign the key in and out in a log book.
4. The issuance of grand and great-grand master keys was not consistent. All interview-
ees were asked how many of these keys existed and who had control over them. In
most cases, the interviewee had to revise his/her initial count and who had each of the
high-level keys.
Recommendations and Improvement Plan
1. Develop a board policy stating specifically which administrators in the district are
allowed to issue, make, and inventory keys for each site, including the district admin-
istrative facilities.
2. Buy locking key boxes for all school sites, install them in secure places, and require
their use.
3. Establish a sign-out card system for all keys that shows who is issued a key, which
door it opens, who authorized the issuance of the key, and the date of issuance.
4. Only district and site administrators should be allowed to issue and carry high-level
keys. The district should annually verify those employees carrying grand or great-
grand master keys.
12 Facilities Managment Facilities Managment 13
Standard Implemented: Partially
July 1, 2003 Rating: 4
Implementation Scale
Not Fully
12 Facilities Managment Facilities Managment 13
0 1 2 3 4 5 6 7 8 9 10
1.6 School Safety—Monitoring of Bus Loading/Unloading Areas for Safety
Professional Standard
Bus loading and unloading areas, delivery areas, and parking and parent loading/unloading
areas are monitored on a regular basis to ensure the safety of the students, staff, and community.
Students, employees, and the public should feel safe at all times on school premises.
Sources and Documentation
1. On-site observation before, after, and during regular school hours
2. Bus schedules and routes
Findings
1. At the sites observed, the monitoring of student arrivals and departures was nonex-
istent. At one elementary school, a small loading/unloading area was designated, but
ignored by most parents. Parents stopped in the middle of the street, dropped off the
students, and left. Others stopped in the loading/unloading zone and parked to walk
their students to class. At this same site, AAA had provided free pamphlets to explain
proper student traffic management.
2. One team member was able to stand in the main hallway of one school without being
approached by an adult for more than one-half hour. Students passed by without adult
supervision.
3. At one of the elementary schools, a mother took off the chain around the gate, pushed
the stroller across the campus, and exited the gate on the other side of the campus.
No adult approached the mother, even though there were other small children on the
playground.
4. At the high school campus, a team member was able to stand in front of the adminis-
tration building without being questioned as to his purpose for being on the site.
5. Also at the high school, students were able to squeeze through the construction fenc-
ing in a hard-hat area. Even though new construction was occurring, the students
crossed the area without restriction or reprimand.
6. At the district office, parking for both handicapped and regular access is extremely
limited. Parents are unable to easily park to meet with the district staff. district staff
members are required to move their cars because of the time limitations on the nearby
parking spaces.
Recommendations and Improvement Plan
1. Increase adult supervision at student loading and unloading areas for all sites with K-8
students.
2. Assign adult supervision at all times when students are on campus.
14 Facilities Managment Facilities Managment 15
3. Increase security devices at all campuses to reduce the likelihood of public use of the
campuses as shortcuts to other areas of town.
4. Increase safety training at all employee training sessions.
5. Improve security fencing around construction areas.
6. Reprimand students using construction sites as shortcuts.
7. Priority should be given to obtaining sufficient parking at the new district office facili-
ties for all employees. A limited number of handicapped and visitor parking spaces
directly in front of the main entrance should be designated.
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
14 Facilities Managment Facilities Managment 15
0 1 2 3 4 5 6 7 8 9 10
1.7 School Safety—Installation and Operation of Outside Security Lighting
Professional Standard
Outside lighting is properly placed and monitored on a regular basis to ensure the operability/
adequacy of such lighting to ensure safety while activities are in progress in the evening hours.
Outside lighting should provide sufficient illumination to allow for safe passage of students and the
public during after-hour activities. Lighting should also provide security personnel with sufficient
illumination to observe any illegal activities on campus.
Sources and Documentation
1. On-site observation before, after, and during regular school hours
Findings
1. There was no current Governing Board policy available at the time of the study.
2. The majority of the school sites visited had some lighting, but still need additional
lighting, specifically for security during the evening hours.
3. Many of the hallways and courtyard areas have minimal lighting, usually limited to a
single light bulb behind a faded Plexiglass cover in the ceiling.
4. Some of the overhead lights were in need of repair or replacement of the Plexiglass
covers. Other had no bulbs in them.
5. Some of the campuses had tall tower lighting to provide good security lighting; how-
ever, they were not all operable at key times of the evening.
Recommendations and Improvement Plan
1. Develop a Governing Board policy regarding the amount of lighting that must be
installed at all school sites and the priority for funding to enforce this policy.
2. Replace and maintain existing hallway lighting that does not provide sufficient illumi-
nation.
3. Install additional exterior lighting in all hallways, courtyards, between buildings, and
fields.
4. Replace all hallway lighting, which consists of standard light bulbs, with more mod-
ern lighting, such as halogen bulbs or lighting as mentioned in Standard 8.3.
5. Replace all hallway light fixtures with clear, vandal-proof covers to allow for full il-
lumination of the hallways.
6. Install additional lighting in all courtyards that will allow for security during after-
school activities and security surveillance.
7. Install lighting between buildings, such as portable classrooms, for security purposes.
16 Facilities Managment Facilities Managment 17
8. Increase lighting in open field areas to reduce possibility of loitering and allow easier
surveillance by security.
Standard Implemented: Partially
July 1, 2003 Rating: 4
Implementation Scale
Not Fully
16 Facilities Managment Facilities Managment 17
0 1 2 3 4 5 6 7 8 9 10
1.8 School Safety—Graffiti and Vandalism Abatement Plan
Professional Standard
The district has a graffiti and vandalism abatement plan. The district should have a written
graffiti and abatement plan that is followed by all district employees. The district provides
district employees with sufficient resources to meet the requirements of the abatement plan.
Sources and Documentation
1. Copy of graffiti and vandalism plan
2. On-site observation before, after, and during regular school hours
Findings
1. A current board policy for graffiti abatement was not available. The board reportedly
is currently updating many of the policies relating to school safety, including graffiti
abatement.
2. The elementary schools had minor graffiti, but the amount was insufficient to com-
ment on in these recommendations.
3. The middle schools had differing amounts of graffiti.
4. During the high school campus observation, the bathrooms had heavy graffiti in more
than one layer. Staff members indicated that custodians and maintenance staff mem-
bers paint over all graffiti on a weekly basis.
Recommendations and Improvement Plan
1. Create a board policy that includes specific expectations for the staff and instructions
on how to handle graffiti in the schools.
2. All sites should work closely with local law enforcement groups in an attempt to re-
duce the graffiti problems, especially at the high school.
3. Site-operational personnel should receive ongoing training on graffiti abatement.
4. Site-operational personnel should also be provided with adequate supplies and equip-
ment to keep up with the graffiti challenges.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
18 Facilities Managment Facilities Managment 19
0 1 2 3 4 5 6 7 8 9 10
1.9 School Safety—School Site Emergency Procedures Plan
Professional Standard
Each public agency is required to have on file written plans describing procedures to be em-
ployed in case of emergency. [EC 32000-32004, 32040, 35295-35297, 38132, 46390-46392,
49505, GC 3100, 8607, CCR Title 8, §3220]
Sources and Documentation
1. Board policy
2. Emergency and disaster preparedness plan
3. Evidence of disaster preparedness drills
4. First-aid kits
Findings
1. Board policies were not provided. They are in the process of being updated.
2. Emergency procedures documentation was inconsistent at school sites.
3. Fire drill and disaster drill logs could not be located at most sites.
4. Fire drills and disaster drills were not consistently reported to the district office.
5. Fire departments are sometimes on site when fire drills occur.
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations regarding emergency procedures.
2. Establish procedures to annually update the emergency procedures.
3. Establish procedures to ensure that all staff members are trained for emergencies.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
18 Facilities Managment Facilities Managment 19
0 1 2 3 4 5 6 7 8 9 10
1.10 School Safety—Conduct of Required Fire Drills
Professional Standard
Each elementary and intermediate school at least once a month, and in each secondary school not
less than twice every school year, shall conduct a fire drill. [EC 32000-32004, 32040, CCR Title
5 §550]
Sources and Documentation
1. Board policy
2. Visible building evacuation plan
3. Evidence of fire drills
4. Fire life-safety devices
5. Emergency exit signage
6. First-aid kits
Findings
1. Board policies were not provided.
2. Conducting of fire drills was not consistent. Not all elementary and intermediate
schools had drills at least once each month, and it was unclear whether the secondary
schools held drills not less than twice every school year.
3. In most cases, the fire drill logs could not be found.
4. School sites did not always report drills to the district office.
5. An occasional exit sign was missing.
6. Evacuation plans were posted in each classroom. These plans consist of written direc-
tions, not maps.
7. Each site visited had first-aid kits and disaster supplies. The quantity of kits per site
varied.
8. Each site had identified general procedures and assembly areas.
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations regarding fire drills.
2. Adopt procedures to ensure proper timing of fire drills.
3. Adopt procedures to ensure reporting for fires drills to the central office.
4. Establish procedures to ensure that the district office follows up with sites that do not
report drills.
5. Establish procedures to evaluate the minimum quantity and type of first aid kits re-
quired for each site.
20 Facilities Managment Facilities Managment 21
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
20 Facilities Managment Facilities Managment 21
0 1 2 3 4 5 6 7 8 9 10
1.11 School Safety—Knowledge of Chemicals and Potential Hazards
Professional Standard
Maintenance/custodial personnel have knowledge of chemical compounds used in school pro-
grams that include the potential hazards and shelf life. [EC 49341, 49401.5, 49411, F&AC
12981, H&SC 25163, 25500-25520, LC 6360-6363, CCR Title 8 §5194]
Sources and Documentation
1. Board policy
2. Hazard communication program
3. Availability of MSDS copies
4. List of chemical materials and shelf life
5. Observation of laboratories
6. Interviews with maintenance/custodial staff
Findings
1. Board policies were not provided.
2. A hazard communications program does not exist.
3. Some science chemical storage areas had been upgraded with earthquake rails and
storage bind.
4. Some chemical storage areas were in disarray.
5. School sites could not produce an inventory of chemicals.
6. Fire departments did not have a list of chemicals.
7. Only some sites had Material Data Safety Sheets (MSDS) available in science and
custodial areas.
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations regarding hazardous chemicals.
2. All buildings and grounds staff, plant managers, and faculty should receive in-service
training on chemical compounds and hazardous substances in their work area at the
time of their initial assignment and whenever a new hazard is introduced into their
work area. Additional training on the methods to lessen or prevent exposure to hazard-
ous substances as follows:
• Well-delineated work practices
• Use of protective equipment
• Instruction on how to read labels and MSDS files
• The steps the district has taken to lessen or prevent exposure to hazardous
substances
3. The district should develop a written hazard communication program in accordance
with the California Code of Regulations, Title 8, section 5194 that requires all school
22 Facilities Managment Facilities Managment 23
districts to have a written hazard communication program addressing each of the pro-
gram categories enumerated below.
• Material Safety Data Sheet (MSDS) List of Hazardous Substances
• Hazardous nonroutine tasks
• Hazardous substances in unlabeled pipes
• Employee information and training including:
• An overview of the requirement of California’s Hazard Communication
Regulation (Code of Regulations, title 8, section 194), including employ-
ee rights described therein.
• The location, availability and content of the district’s written hazardous
communication program.
• Information as to any operations in the employees’ work area where haz-
ardous substances are present.
• The physical and health effects of the hazardous substances in the work
area.
• Techniques and methods of observation that may determine the presence
or release of hazardous substances in the work area.
• Methods by which employees can lessen or prevent exposure to these
hazardous substances, such as appropriate work practices, use of personal
protective equipment and engineering controls.
• Steps the district has taken to lessen or prevent exposure to these
substances.
• Instruction on how to read labels and review the MSDS for appropriate
information.
• Emergency and first-aid procedures to follow if exposed to the hazardous
substances.
4. The written hazard communication program should be available upon request to all
employees and their designated representatives. (Code of Regulations, Title 8, Section
5194).
5. Teachers shall instruct students about the importance of proper handling, storage, dis-
posal and protection when using any potentially hazardous substance.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
22 Facilities Managment Facilities Managment 23
0 1 2 3 4 5 6 7 8 9 10
1.12 School Safety—Inspection and Correction of Unsafe Conditions
Professional Standard
Building examinations are performed, and required actions are taken by the Governing Board
upon report of unsafe conditions. [EC 17367]
Sources and Documentation
1. Board policy
2. Work orders
3. Interviews with maintenance/custodial staff
4. Site reviews
Findings
1. Board policies were not provided.
2. Work orders are used to report unsafe conditions.
3. Unsafe conditions receive the highest priority for work order completion, however, the
response time from the Maintenance Department varied between sites.
4. Several substandard and potentially unsafe conditions were discovered on site visits.
(Possible mold growth, missing wallboard, and improper storage in boiler and electri-
cal rooms.)
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations regarding reporting unsafe condi-
tions.
2. Evaluate the effectiveness of the current work-order system to address safety items
immediately.
3. Develop procedures for an annual inspection of facilities to ensure that site staff mem-
bers are reporting all unsafe conditions.
4. Ensure that the district has submitted the appropriate modernization funding applica-
tions to the Office of Public School Construction (OPSC)and are ready to proceed
expeditiously, as funds become available.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
24 Facilities Managment Facilities Managment 25
0 1 2 3 4 5 6 7 8 9 10
1.13 School Safety—Emergency Fire and Police Access to Campuses
Professional Standard
Each school which is entirely enclosed by a fence or partial buildings must have a gate of suf-
ficient size to permit the entrance of ambulances, police and fire fighting equipment. Locking
devices shall be designed to permit ready entrance. [EC 32020]
Sources and Documentation
1. Site observation of gates and locking devices
2. Interviews with maintenance/custodial Staff
3. Interviews with fire department personnel
Findings
1. All district sites inspected had access gates of sufficient size to permit the entrance of
emergency vehicles, equipment and apparatus.
2. The gates are designed to permit the ready entrance by the use of chain or bolt-cutting
devices.
Recommendations and Improvement Plan
1. Continued compliance with Education Code Section 32020, and conformance review
with law enforcement and fire protection agencies.
Standard Implemented: Fully -Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
24 Facilities Managment Facilities Managment 25
0 1 2 3 4 5 6 7 8 9 10
1.14 School Safety—Sanitation is Maintained and Fire Hazards are Corrected
Professional Standard
Sanitary, neat, and clean conditions of the school premises exist and the premises are free from
conditions that would create a fire hazard. [CCR Title 5 §633]
Sources and Documentation
1. Board policy
2. Copy of facilities construction plan
3. On-site observation before, after, and during regular school hours
Findings
1. While no board policy was provided during the visits, these policies usually state
something similar to the following, “An effective educational program requires clean,
healthful, safe, businesslike, and attractive physical facilities. The maintenance and
custodial staff is charged with the responsibility of caring for and protecting these
facilities. In order to carry out an efficient maintenance program, the custodians must
receive the cooperation of the pupils, the teachers, and administration.”
2. Some of the fire hazards noticed during the site observations included:
• Boiler rooms with storage around the boilers.
• Fire extinguishers blocked from easy access.
• Electrical boxes housing circuit breakers were unlocked and doors were open.
• Fire extinguishers missing from designated areas.
• Large storage areas had no fire extinguishers or designated extinguisher areas.
Recommendations and Improvement Plan
1. The Governing Board should develop and adopt a board policy delineating that all
sanitation hazards are corrected immediately.
2. Provide on-site in-service training for all site operational personnel in the area of site
safety and cleanliness.
3. Develop on-site in-service training using the job descriptions.
4. Supervisors should periodically review the progress site personnel are making in
keeping campuses safe and clean.
5. Supervisors should also emphasize the area of safety and cleanliness in the employee’s
annual evaluation.
6. Prioritize hazards according to the greatest need or greatest hazard to the students and
the public.
7. Provide incentives and recognition for clean campuses for both students and employ-
ees
26 Facilities Managment Facilities Managment 27
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
26 Facilities Managment Facilities Managment 27
0 1 2 3 4 5 6 7 8 9 10
1.15 School Safety—Injury/Illness Prevention Program Inspections are Done
Professional Standard
The Injury and Illness Prevention Program (IIPP) requires periodic inspections of facilities to
identify conditions. [CCR Title 8 §3203]
Sources and Documentation
1. Board policy
2. IIPP handbook
3. Interviews with staff
Findings
1. Board policies were not provided. They are in the process of being updated.
2. The Prevention Program (IIPP) manual is being updated.
Recommendations and Improvement Plan
1. Complete the update to the IIPP.
2. Emphasize to all staff the importance of the document. The site administrator should
know the location, purpose and use of the document and its contents.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
28 Facilities Managment Facilities Managment 29
0 1 2 3 4 5 6 7 8 9 10
1.16 School Safety—Fire Extinguishers and Inspection Information Available
Professional Standard
Appropriate fire extinguishers exist in each building and current inspection information is avail-
able. [CCR Title 8 §1922(a)]
Sources and Documentation
1. On-site observation of extinguishers and tags
2. Evidence of inspections
3. Interviews with maintenance/custodial staff
Findings
1. All sites visited had the appropriate fire extinguishers existing in most buildings/
rooms.
2. Many fire extinguishers in visible, public areas had not been certified within the past
12 months.
3. Most fire extinguishers in less visible areas such as stages or kitchens or mechanical
areas had not been certified within the past 12 months.
4. A minor number of mechanical or support areas did not have appropriate fire extin-
guishers or the current inspection information available.
Recommendations and Improvement Plan
1. Update current recharging and replacement procedures to ensure that all extinguishers
on each site receive the required annual servicing.
2. Install appropriate fire extinguishers in each building so that they are visible with easy
access and have current inspection information available.
3. Provide a back-up extinguisher whenever an extinguisher is removed for service.
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
28 Facilities Managment Facilities Managment 29
0 1 2 3 4 5 6 7 8 9 10
1.17 School Safety—All Exits are Free of Obstructions
Professional Standard
All exits are free of obstructions. [CCR Title 8 §3219]
Sources and Documentation
1. On-site observation of exits
2. Verification of door operation
3. Discussions with local fire officials
Findings
1. All sites inspected had working door hardware and no obstruction at the fire exits.
2. Exit devices were operational as exits. Some doors were in poor condition.
3. Fire departments now are reviewing sites for compliance.
Recommendations and Improvement Plan
1. Ensure that all site staff members are knowledgeable about the need to keep exits
unlocked and free of obstructions.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 9
Implementation Scale
Not Fully
30 Facilities Managment Facilities Managment 31
0 1 2 3 4 5 6 7 8 9 10
1.18 School Safety—Plan for Prevention of Campus Crime and Violence
Professional Standard
A comprehensive school safety plan exists for the prevention of campus crime and violence. [EC
35294-35294.9]
Sources and Documentation
1. Board policy
2. School safety plan
3. Observation of sites
4. Discussion with district and site staffs
Findings
1. Board policies were not provided. They are in the process of being updated.
2. School safety plans were incorporated in emergency procedures documentation and
were inconsistent at school sites.
Recommendations and Improvement Plan
1. Adopt board policies and administrative procedures related to school safety plans.
2. Ensure the annual updating, training of staff and the utilization of information ac-
quired for the plans and reports developed pursuant to Education Code sections
35294-35294.9, to maintain the comprehensive school safety plan.
3. All plans must include the following key code requirements for a comprehensive
school safety plan:
• Status of school crimes committed on district campuses during district func-
tions
• Dangerous pupil notification procedures
• Strategies and programs for the maintenance of high levels of school site
safety
• Access procedures for students
• Educational environment requirements
• School discipline procedure
• Sexual harassment policy
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
30 Facilities Managment Facilities Managment 31
0 1 2 3 4 5 6 7 8 9 10
1.19 School Safety—An Emergency Action Plan Exists
Professional Standard
Each public agency is required to have on file written plans describing procedures to be em-
ployed in case of emergency. [EC 32000-32004, 32040, 35295-35297, 38132, 46390-46392,
49505, GC 3100, 8607] [CCR Title 8, §3220]
Sources and Documentation
1. Board policy
2. Emergency and disaster preparedness plan
3. Evidence of disaster preparedness drills
4. First-aid kits
Findings
1. Board policies were not provided. They are in the process of being updated.
2. The emergency action plans were not consistent at all sites.
3. First-aid kits were generally available.
4. Fire departments are on site when fire drills occur.
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations regarding school crisis plans.
2. Develop a procedure for each site to annually review the school crisis plan.
3. Incorporate the school crisis plan with emergency and disaster planning.
4. Ensure that the school crisis plan is customized to meet the unique needs of each site.
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
32 Facilities Managment Facilities Managment 33
0 1 2 3 4 5 6 7 8 9 10
1.20 School Safety—Compliance for Under/Above Ground Storage Tanks
Professional Standard
Requirements are followed pertaining to underground storage tanks. [H&SC 25292, CCR Title
26 §477, Title 23 §2610]
Sources and Documentation
1. Board policy
2. Discussions with district staff
Findings
1. Board policies were not provided.
2. On or before December 22, 1998 the district was to replace or upgrade (to prevent
leaks due to corrosion, spills or overfills) its underground storage tanks (USTs), and
equip all existing underground-pressurized piping with automatic line-leak detectors
and a secondary containment.
3. It appears that no underground fuel tanks remain. Tanks at seven sites were removed
around 1994/95, and tanks were removed at three sites during construction or modern-
ization.
4. Tanks were suspected, but not found at two other sites.
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations to ensure that, on and after Janu-
ary 1, 1999, no person or agency shall deposit petroleum into an UST system unless
the system meets the requirements of section 25291 or subdivisions (d) and (e) of sec-
tion 25292 and related regulations adopted pursuant to section 25299.3.
2. Remove or replace tanks if discovered on other sites.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
32 Facilities Managment Facilities Managment 33
0 1 2 3 4 5 6 7 8 9 10
1.21 School Safety—Compliance with Federal AHERA Laws
Professional Standard
All asbestos inspection and asbestos work completed in the US is performed by Asbestos Hazard
Emergency Response Act (AHERA) accredited individuals. [EC 49410.5, 40 CFR Part 763]
Sources and Documentation
1. Board policy
2. AHERA inspection reports
3. Interviews with the maintenance staff
Finding
1. Maintenance has the AHERA log books.
2. No school site could locate their copy of the AHERA log book.
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations to ensure compliance with
AHERA laws.
2. Provide each site with copies of the asbestos management plan and three-year recerti-
fication.
3. Maintenance/custodial staff should be trained on the location, identification, proper
cleaning, and ongoing maintenance of asbestos-containing materials.
4. Maintenance and custodial staff should be trained in the removal and decontamina-
tion of small amounts of such materials when needed to repair pipes or perform small
scope projects.
5. Any extensive asbestos abatement work must be done by state certified asbestos
abatement contractors in compliance with state and federal standards.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
34 Facilities Managment Facilities Managment 35
0 1 2 3 4 5 6 7 8 9 10
1.22 School Safety—Playground Equipment is Inspected and Safe
Professional Standard
All playground equipment meets safety code regulations and is inspected in a timely fashion
as to ensure the safety of the students. [EC 44807, GC 810-996.6, H&SC 24450 Chapter 4.5,
115725-115750, PRC 5411, CCR Title 5 §5552]
Sources and Documentation
1. On-site observation of playground equipment
Findings
1. All playground equipment appeared to have been replaced within the past few years.
2. The district appeared to be in general conformance with prevailing codes and regula-
tions.
3. Site custodians reported that they check for loose bolts on the equipment at least annu-
ally.
Recommendations and Improvement Plan
1. Continue the annual monitoring of playground equipment for loose bolts and mainte-
nance needs.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
34 Facilities Managment Facilities Managment 35
0 1 2 3 4 5 6 7 8 9 10
1.23 School Safety—Safety of Boilers and Fired Pressure Vessels
Professional Standard
Safe work practices exist with regards to boiler and fired pressure vessels. [CCR Title 8 §782]
Sources and Documentation
1. On-site observation of boilers and fired pressure vessels
2. Maintenance logs
Findings
1. No site had a log of boiler maintenance.
2. Most of the district’s boiler and fired pressure systems have been upgraded.
3. Site plant managers did not have maintenance knowledge about the boilers.
4. All boiler maintenance was performed by the district maintenance staff.
5. Some boiler rooms are also being used for storage.
Recommendations and Improvement Plan
1. The district should develop work practices and procedures for boilers as follows:
• On-site maintenance logs that contain complete descriptions of the mainte-
nance of all system components including sensors, controllers, actuators, etc.
• The maintenance log descriptions should include the dates of inspections,
periodic preventative maintenance and suggestions, and system/component
failure diagnosis.
• The maintenance log descriptions should include procedures for the repair or
replacement of defective components.
• Ongoing training for maintenance/custodial staff should continue on the gen-
eral industry safety orders.
• On start-up dates the district should have on-site qualified field technicians to
place the systems in operation. Making such tests, adjustments, and changes
as may be found necessary to ensure the safe and successful operation of the
equipment and systems.
2. The district should eliminate all storage in boiler rooms.
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
36 Facilities Managment Facilities Managment 37
0 1 2 3 4 5 6 7 8 9 10
1.24 School Safety—Maintenance of Material Safety Data Sheets
Professional Standard
Maintenance of Materials Safety Data Sheets. [EC 49341, 49401.5, 49411, F&AC 12981, LC
6360-6363, CCR Title 8 §5194]
Sources and Documentation
1. Board policy
2. Hazard communication program
3. MSDS documentation
4. List of chemical materials and shelf life
5. Observation of laboratories
6. Interviews with maintenance/custodial staff
Findings
1. Board policies were not provided.
2. Few sites had the appropriate labeling and MSDS available.
3. Some science storage rooms were in disarray.
4. There is no method to determine when each MSDS notebook has been updated.
Recommendations and Improvement Plan
1. Adopt board policies and administrative regulations regarding MSDS sheets.
2. When the district receives a hazardous substance or mixture, the district representa-
tives shall ensure that the manufacturer has also furnished a Material Safety Data
Sheet as required by law. In the event the MSDS is missing or incomplete, the district
shall request a new MSDS from the manufacturer and shall notify the California Oc-
cupational Safety and Health Division (Cal/OSHA) if a subsequent completed MSDS
is not received.
3. The district representative shall maintain copies of the MSDS for all hazardous sub-
stances and ensure that they are kept up to date and available to all affected employ-
ees.
4. The district shall review each incoming MSDS for new and significant health and
safety information and disseminate this information to all affected employees.
5. Should the district elect to convert to a computerized or fax-on-demand program, the
district must ensure that up-to-date copies of the MSDS for all hazardous substances
are available to all affected employees. The affected employees must be trained to
operate the computers or fax machines that provide access to MSDS files.
6. All buildings and ground staff, plant managers, and employees should receive in-
service training on hazardous substances in their work area at the time of their initial
assignment and whenever a new hazard is introduced into their work area.
36 Facilities Managment Facilities Managment 37
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
38 Facilities Managment Facilities Managment 39
0 1 2 3 4 5 6 7 8 9 10
1.25 School Safety—Maintenance of a Comprehensive Employee Safety
Program
Professional Standard
The district maintains a comprehensive employee safety program. Employees should be aware
of the district safety program, and the district provides in-service training to employees on the
requirements of the safety program.
Sources and Documentation
1. Board policy
2. Copies of collective bargaining agreements
3. Copy of employee safety handbook
4. Interviews with sampling of employees
5. Observation of employees and safe practices
Findings
1. FCMAT was unable to obtain a copy of the board policy regarding a comprehensive
employee safety program or any related training materials.
2. The bargaining unit agreement articles contained wording regarding safety training
and the requirements of the district.
3. Team members were unable to verify which of the district administrators is the pri-
mary party responsible for safety training.
Recommendations and Improvement Plan
1. Update and expand current board policy.
2. Establish a districtwide safety committee that includes representatives from all bar-
gaining units and administration.
3. Create a periodic safety newsletter for distribution to employees and the public.
4. Designate which circumstances must be handled immediately and cannot be ignored
due to the district’s financial condition.
5. Designate by position, the district administrator responsible for meeting the board
policy requirements.
6. The district should assign one administrator for coordinating the safety committee
meetings, as well as following up on the recommendations made by the committee.
38 Facilities Managment Facilities Managment 39
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
40 Facilities Managment Facilities Managment 41
0 1 2 3 4 5 6 7 8 9 10
1.26 School Safety—Conduct of Periodic Safety Training for Employees
Professional Standard
The district conducts periodic safety training for employees. district employees should receive
periodic training on the safety procedures of the district.
Sources and Documentation
1. Board policy
2. Copies of agendas for training
3. Copies of materials used in training
4. Interviews with sampling of employees
5. Observation of employees and safe practices
Findings
1. FCMAT was unable to obtain a copy of the board policy regarding a comprehensive
employee safety program or any related training materials.
2. The bargaining unit agreement articles contained wording regarding safety training
and the requirements of the district.
3. FCMAT was unable to verify which of the district administrators was the primary
party responsible for safety training.
Recommendations and Improvement Plan
1. Update and expand current board policy.
2. Establish a districtwide safety committee that includes representatives from all bar-
gaining units and administration.
3. Create a periodic safety newsletter for distribution to employees and the public.
4. Designate which circumstances must be handled immediately, and cannot be ignored
due to the district’s financial condition.
5. Designate by position the district administrator responsible for meeting the board
policy requirements.
6. The district should assign one administrator for coordinating the safety committee
meetings, as well as following up on the recommendations made by the committee.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
40 Facilities Managment Facilities Managment 41
0 1 2 3 4 5 6 7 8 9 10
1.27 School Safety—Conduct of First Aid Training for School Site Personnel
Professional Standard
The district should conduct periodic first aid training for employees assigned to school sites.
Sources and Documentation
1. Board policy
2. Copies of agendas for training
3. Copies of materials used in training
4. Interviews with sampling of employees
5. Observation of employees and safe practices
Findings
1. Assessment team members were unable to obtain a copy of the board policy regarding
a first-aid training program or any related training materials.
2. The bargaining unit agreement articles contained wording regarding safety training
and the requirements of the district.
3. FCMAT was unable to verify which of the district administrators was the primary
party responsible for first-aid training.
Recommendations and Improvement Plan
1. Update and expand current board policy.
2. Designate which circumstances must be handled immediately and cannot be ignored
due to the district’s financial condition.
3. Designate by position the district administrator responsible for meeting the board
policy requirements.
4. The district should assign one administrator for coordinating the first aid training.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
42 Facilities Managment Facilities Managment 43
0 1 2 3 4 5 6 7 8 9 10
2.1 Facility Planning—Maintenance of a Long-Range Facilities Master Plan
Professional Standard
The district should have a long-range school facilities master plan.
Sources and Documentation
Discussions with Director of Facilities
Findings
1. The district does not possess a long-range school facilities master plan.
Recommendations and Improvement Plan
1. The district should have a long-range school facilities master plan prepared. In addi-
tion, the long-range school facilities master plan should be prepared in a manner that
permits updates to occur every three to five years, with minimal cost.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
42 Facilities Managment Facilities Managment 43
0 1 2 3 4 5 6 7 8 9 10
2.2 Facility Planning—CDE Facilities Planning and Construction Guide
Professional Standard
The district should possess a California State Department of Education Facilities Planning and
Construction Guide (dated 1991).
Sources and Documentation
1. District documentation
Findings
1. The district does currently possess a Facilities Planning and Construction Guide pre-
pared by the California State Department of Education.
Recommendations and Improvement Plan
1. The district should periodically check the internet Web page of the California State
Department of Education to see whether the Facilities Planning and Construction
Guide has been updated, as well as to see whether other guides associated with facili-
ties planning and school construction have been created or updated.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
44 Facilities Managment Facilities Managment 45
0 1 2 3 4 5 6 7 8 9 10
2.3 Facility Planning—Efforts to Seek State and Local Matching Funds
Professional Standard
The district should seek State and local funds.
Sources and Documentation
1. Discussion with Director of Facilities
2. State Allocation Board forms 50-01, 50-02, 50-03, and 50-04
3. Ballot language for Measure A (General Obligation Bond)
4. Ballot language for Measure AA (General Obligation Bond)
5. District documentation
Findings
1. On June 2, 1992, by a vote in excess of two-thirds of the voters voting, the district
received authorization to issue $158 million of general obligation bonds (Measure A).
Measure A authorized the district to construct new school facilities, retrofit and mod-
ernize existing school facilities, and replace deteriorating building systems.
2. In November 1986, a parcel tax program named “Berkeley Schools Enrichment Pro-
gram” was approved by a vote in excess of two-thirds of the voters voting. A measure
to renew the parcel tax program for 12 years was passed in November 1994. Another
measure to extend the parcel tax for a period of four years was passed in November
1998.
3. On November 7, 2000, by a vote in excess of two-thirds of the voters voting, the dis-
trict received authorization to issue $116.5 million of general obligation bonds (Mea-
sure AA). Measure AA authorized the district to repair, upgrade, and add new class-
rooms to address overcrowding and facilitate reduced class sizes at Berkeley High
School, King Middle School, and other Berkeley schools.
4. The district has submitted and the State Allocation Board has approved Forms 50-01,
50-02, 50-03, and 50-04. Since the enactment of the School Facilities Program, the
district has received funds from the state for the modernization of six facilities. In
addition, the district has submitted 50-04 forms to receive modernization funding for
other facilities.
5. The district has been successful in receiving Federal Emergency Management Act
(FEMA) income for hazard mitigation.
Recommendations and Improvement Plan
1. The district should continue to submit forms 50-04 to the State Allocation Board for
eligible projects.
2. The district should pursue all other local funds (e.g., redevelopment tax increment,
mitigation payments/alternative fees/statutory school fees, etc.) to the fullest extent
possible.
3. The district should continue to seek FEMA income for hazard mitigation.
44 Facilities Managment Facilities Managment 45
4. The district should prepare residential and commercial/industrial school fee justifica-
tion studies and impose statutory school fees on new construction projects.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
46 Facilities Managment Facilities Managment 47
0 1 2 3 4 5 6 7 8 9 10
2.4 Facility Planning—Existence of a district Facility Planning Committee
Professional Standard
The district should have a functioning facility planning committee.
Sources and Documentation
1. Discussion with Director of Facilities
2. District Web page
Findings
1. At Berkeley Unified, the functions and roles that would typically be found within a fa-
cility planning committee actually occur within two separate and distinct committees,
the Citizens Construction Advisory Committee (CCAC) and the Maintenance and Se-
curity Advisory Committee (MAC). Based upon district staff comment, it appears that
the two distinctive committees operate somewhat separately and autonomously from
each other. There also appear to be functional discrepancies relative to the effective-
ness of each committee.
Recommendations and Improvement Plan
1. It is commendable that the district is seeking and obtaining community involvement
through the two aforementioned committees, but it may be more effective to merge
the two groups into one structured committee. The new committee’s roles, functions
and purposes would then be redefined. The presence of the two distinct advisory com-
mittees may actually fracture the desired overall result.
Standard Implemented: Fully - Susbstantially
July 1, 2003 Rating: 9
Implementation Scale
Not Fully
46 Facilities Managment Facilities Managment 47
0 1 2 3 4 5 6 7 8 9 10
2.5 Facility Planning—Properly Staffed and Funded Facility Planning
Function
Professional Standard
The district should have a properly staffed and funded facility planning department.
Sources and Documentation
1. Discussion with Director of Facilities
2. Review of district staffing/organizational chart
3. Discussion with OPSC and CDE staff
Findings
1. The district Facilities Department is seriously understaffed. While the current Director
of Facilities’ knowledge and skills are commendable, his current range of responsibili-
ties and involvement far exceed those found for directors in similar California public
school districts. These responsibilities include overseeing the district’s highly aggres-
sive, far-reaching and long-term facilities improvement program.
2. While the district has contracted with outside project management/construction man-
agement services in the past to support the construction implementation program, it is
evident that the facilities planning role and functions fall solely within the responsibil-
ity of the Director of Facilities.
3. A staffing funding augmentation may be possible through the allocated use of ei-
ther Measure BB or AA funds (as permitted by ballot language and/or bond counsel
review/authorization).
Recommendations and Improvement Plan
1. The district should perform a self-analysis to determine the types and numbers of
additional staffing positions that are required in order to effectively meet its facilities-
related challenges and opportunities. While past practices have tended to focus upon
program implementation and construction support, the facilities planning area of the
department needs staff augmentation.
2. Job descriptions, roles and responsibilities should be carefully developed and articu-
lated. A system of ongoing assessment and evaluation is needed to determine whether
the Facilities Department is properly staffed and funded to meet evolving project
servicing requirements, which depend upon current projects and needs.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
48 Facilities Managment Facilities Managment 49
0 1 2 3 4 5 6 7 8 9 10
2.6 Facility Planning—Implementation of an Annual Capital Planning Budget
Professional Standard
The district should develop and implement an annual capital planning budget.
Sources and Documentation
1. Discussion with Director of Facilities
2. District documentation
Findings
1. With the passage of Measure A, Measure AA, and Measure BB, the district develops
annual capital planning budgets that identify the school facilities improvements that
require immediate attention in a given school year.
Recommendations and Improvement Plan
1. The district should continue to develop annual capital planning budgets and present
them to the board of education.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
48 Facilities Managment Facilities Managment 49
0 1 2 3 4 5 6 7 8 9 10
2.7 Facility Planning—Standards for Real Property Acquisition and Disposal
Professional Standard
The district should have standards for real property acquisition and disposal. [EC 39006, 17230-
17233]
Sources and Documentation
1. Discussion with Director of Facilities
2. District documentation
Findings
1. The district has retained the services of a firm to assist in determining which school
properties should be asset managed. The schools properties identified in the facilities
study prepared by California Financial Services were selected based on location of
students to facilities and potential value of the property.
Recommendations and Improvement Plan
1. The district should develop and modify its standards for real property acquisition and
disposal as the California State Department of Education modifies its guidelines.
2. The district should consider long-range enrollment projections in determining proper-
ties to be disposed of. facilities master plan prepared.
3. The district should contact the City of Berkeley to assist in determining which school
properties are the most appropriate for disposal.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
50 Facilities Managment Facilities Managment 51
0 1 2 3 4 5 6 7 8 9 10
2.8 Facility Planning—State Allocation Board Waivers for Non-Conforming
Facilities
Professional Standard
The district seeks and obtains waivers from the State Allocation Board for continued use of its
non-conforming facilities. [EC 17284, 17285]
Sources and Documentation
1. Interview with OPSC Project Manager
2. Interviews with district staff
3. Review of State Allocation Board agendas
4. Personal inspection of district sites/facilities
Findings
1. The district has not pursued waivers from the State Allocation Board for authorized/
continued use of any nonconforming facilities. The district has done an exceptional
job of identifying and addressing structural deficiencies within its permanent school
facilities, primarily as a result of the Loma Prieta earthquake. Actions related to this
remedial structural work were not prompted by nonconforming facilities. Rather
they were prompted by desires from the district and community to remedy identified
structural code discrepancies or structural deficiencies that were identified in physical
inspections. However, the district has some older relocatable classrooms that probably
require approval by the Division of the State Architect (DSA) and should be classified
as nonconforming.
Recommendations and Improvement Plan
1. The district should finalize its efforts to either obtain DSA approval for any of its non-
conforming facilities or seek to replace the nonconforming classrooms with DSA-ap-
proved facilities.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
50 Facilities Managment Facilities Managment 51
0 1 2 3 4 5 6 7 8 9 10
2.9 Facility Planning—Selection of Licensed Architect/Engineering Services
Professional Standard
The district has established and utilizes a selection process for the selection of licensed
architectural/engineering services. [GC 17302]
Sources and Documentation
1. Interviews with district staff
2. Review of district records
Findings
1. The district has successfully completed the selection processes to identify approved
architectural/engineering/design firms that may be utilized in one or more district-
identified facilities projects.
2. There is relatively focused participation by district staff within the architectural selec-
tion process—although there is also significant local (site-based) involvement in the
selection of an architectural firm for site-specific projects.
3. The district is to be commended for developing a selection process that is based upon
meaningful criteria, strong inclusion of local participants and an overall comprehen-
sive approach toward selection. However, the overall selection process may be im-
proved through greater/stronger direction by the district staff. This approach may en-
sure a more broad-based perspective rather than one that is parochial and based upon
factors that may not greatly improve the end result. Nonetheless, the current selection
process is better than what is used at many other California public school districts.
Recommendations and Improvement Plan
1. The district should consider making the above modifications to its procedures for
selecting architectural/engineering services.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 9
Implementation Scale
Not Fully
52 Facilities Managment Facilities Managment 53
0 1 2 3 4 5 6 7 8 9 10
2.10 Facility Planning—Assessment of Local Bonding Capacity
Professional Standard
The district should assess its local bonding capacity. [EC 15100]
Sources and Documentation
1. Discussion with Director of Facilities
2. District documentation
Findings
1. The district has retained the services of credible legal and financial advisory firms to
assist in assessing the local bonding capacity. This is evident with the passage of Mea-
sure A and Measure AA.
Recommendations and Improvement Plan
1. The district should continue to work with its legal and financial advisors to access lo-
cal bonding capacity.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
52 Facilities Managment Facilities Managment 53
0 1 2 3 4 5 6 7 8 9 10
2.11 Facility Planning—Process to Determine Debt Capacity
Professional Standard
The district should develop a process to determine debt capacity.
Sources and Documentation
1. Discussion with Director of Facilities
2. District documentation
Findings
1. With the assistance of a financial advisor, the district has developed a process to deter-
mine debt capacity.
Recommendations and Improvement Plan
1. The district should continue to work with a financial advisor whose expertise is mu-
nicipal finance for school districts in the state.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
54 Facilities Managment Facilities Managment 55
0 1 2 3 4 5 6 7 8 9 10
2.12 Facility Planning—Awareness and Monitoring of Assessed Valuation
Professional Standard
The district should be aware of and monitor the assessed valuation of taxable property within its
boundaries.
Sources and Documentation
1. Discussion with Director of Facilities
Findings
1. Under the guidance of a financial advisor, the district has been made aware of, and
has developed a procedure for, monitoring the assessed valuation of taxable property
within its boundaries.
Recommendations and Improvement Plan
1. The district should continue to work with a financial advisor whose expertise is mu-
nicipal finance for school districts in the state.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
54 Facilities Managment Facilities Managment 55
0 1 2 3 4 5 6 7 8 9 10
2.13 Facility Planning—Monitor Legal Bonding Limits
Professional Standard
The district should monitor its legal bonding limits. [EC 15100, 15330]
Sources and Documentation
1. Discussion with Assistant Superintendent, Operational Support Facilities
Findings
1. With the assistance of a financial advisor, the district has developed a procedure for
monitoring its legal bonding limits.
Recommendations and Improvement Plan
1. The district should continue to work with a financial advisor whose expertise is mu-
nicipal finance for school districts in the state.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
56 Facilities Managment Facilities Managment 57
0 1 2 3 4 5 6 7 8 9 10
2.14 Facility Planning—Collection of Statutory Developer Fees
Professional Standard
The district should collect statutory school fees. [EC 17620, GC 65995, 66000]
Sources and Documentation
1. Discussion with Director of Facilities
Findings
1. The district has not performed any studies to justify a residential and commercial/
industrial development school fee. As a result, the district does not collect any statu-
tory school fees on residential development or commercial/industrial development.
2. The district does not have a school facilities need analysis. As a result, the district
does not collect alternative school facility fees on residential development per Section
65995.5 of the Government Code.
Recommendations and Improvement Plan
1. The district should retain a consultant to prepare studies for justification of residential
and commercial/industrial development school fees and prepare a school facilities
needs analysis.
2. The district should communicate with departments of the City of Berkeley to identify
the amount of residential and commercial/industrial development that is expected to
occur within district boundaries over the next five to 20 years.
3. The district should begin to charge school fees on new development to pay for school
facility impacts directly or indirectly generated by such development.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
56 Facilities Managment Facilities Managment 57
0 1 2 3 4 5 6 7 8 9 10
2.15 Facility Planning—Consideration of an Asset Management Plan
Professional Standard
The district should consider developing an asset management plan.
Sources and Documentation
1. Discussion with Director of Facilities
2. District documentation
Findings
1. The district has many schools that could be combined. By combining schools, the dis-
trict could reduce maintenance and operation costs and generate surplus school sites
that could be asset-managed.
Recommendations and Improvement Plan
1. While the district has an Asset Management Plan, no surplus school sites should be
disposed of until a long-range school facilities master plan is prepared. The district
needs documentation that demonstrates existing school sites and facilities will not be
needed to accommodate students in the future.
2. The district and its consultant should work closely with the staffs of the various cities
in developing an asset management plan. By doing so, the district could maximize the
value of schools that are closed.
3. The district should proceed cautiously in determining which schools should be closed.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
58 Facilities Managment Facilities Managment 59
0 1 2 3 4 5 6 7 8 9 10
2.16 Facility Planning—Application for Funding for Joint Use Projects
Professional Standard
The district has pursued State funding for joint-use projects through the filing of applications
through the Office of Public Construction and the State Allocation Board.
Sources and Documentation
1. Interview with OPSC Project Manager
2. Review of OPSC project tracking for the district.
3. Interviews with district staff
4. Review of district records
Findings
1. The district was successful in obtaining funding for a joint-use project at Longfellow
School under the State’s previous Leroy Greene Lease-Purchase Program (state ap-
plication #22/61143-00-01).
2. The district has not pursued joint use funding opportunities under the current authori-
zation for joint use projects identified as part of AB 47 and the current School Facili-
ties Program.
Recommendations and Improvement Plan
1. At this time, funding for future joint-use projects continues to be available and it ap-
pears that the conceptual program may be a part of a March, 2004 ballot measure. As
such, the district would be well-advised to continue to monitor opportunities to lever-
age locally generated funds from other public agencies through the potential pursuit
of joint-use projects and, it is hoped, joint-use funding through the School Facilities
Program.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
58 Facilities Managment Facilities Managment 59
0 1 2 3 4 5 6 7 8 9 10
2.17 Facility Planning—Priorities and Scheduling of Projects
Professional Standard
The district has established and utilizes an organized methodology of prioritizing and scheduling
projects.
Sources and Documentation
1. Interviews with district staff
2. Review of district records and reports
Findings
1. The district staff works diligently to plan and schedule projects in a manner that corre-
sponds to priorities established by the board of education. Clear-cut recommendations
from staff appear to be presented to the board of education for their review, approval
and direction for implementation.
2. The district has maintained a moderately effective working relationship with a profes-
sional project manager. This relationship has been partially beneficial to the district, its
projects and the overall progress of respective projects.
Recommendations and Improvement Plan
1. The district has been effective in scheduling projects, given the very limited staff-
ing that currently exists and the strong competing demands that exist from various
in-house constituencies. The district should continue to utilize the services of a pro-
fessional project manager (a new selection process is scheduled to occur in the very
near future) to assist with scheduling of projects. Facilities Department staffing levels
should be enhanced. A higher staffing level would help in prioritizing and scheduling
efforts that are required to effectively implement such a broad-based facilities im-
provement program.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
60 Facilities Managment Facilities Managment 61
0 1 2 3 4 5 6 7 8 9 10
2.18 Facility Planning—School Site Size and Loading Capacity
Professional Standard
The district complies with California Department of Education (CDE) recommendations relative
to school site sizing.
Sources and Documentation
1. Interviews with district staff
2. Review of district facilities records
3. Physical inspection of district sites/facilities
Findings
1. The district currently maintains a wide variety of school grade level configurations on
sites of varying size and enrollment capacities. The district’s school sites are generally
constructed on very small and somewhat constrained sites.
2. The district has a range of site sizes and configurations upon which to conduct the
various educational programs and instructional services offered to its approximately
9,000 students.
Recommendations and Improvement Plan
1. The district is extremely limited in its ability to modify existing site sizes given the
“built out” condition that generally exists within its boundaries.
2. If and when the district plans for any future new school sites (which is extremely un-
likely), the district should carefully utilize the resources within the California Depart-
ment of Education’s School Facilities Planning Division to analyze and “size” future
school sites in accordance with the guidelines included within the “Guide to School
Site Analysis and Development—2000 edition.”
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
60 Facilities Managment Facilities Managment 61
0 1 2 3 4 5 6 7 8 9 10
2.19 Facility Planning—Equity of Distribution of Facility Funding
Professional Standard
The district should distribute facility funding in an equitable manner to all communities served
and all school levels.
Sources and Documentation
1. Discussion with Director of Facilities
2. District documentation
Findings
1. The district recognizes that the funding of school facilities needs to be distributed
throughout its boundaries at all school levels.
2. The district prepares a maintenance yearly plan and facilities division goals that are
presented to the board of education.
3. The district prepares annual facilities construction plan updates that are presented to
the board of education.
4. The district has a Citizens Construction Advisory Committee and a Maintenance and
Security Advisory Committee.
Recommendations and Improvement Plan
1. The district should continue preparing annual plans that are presented to the Govern-
ing Board and involving the community by meeting with the Citizens Construction
Advisory Committee and the Maintenance and Security Advisory Committee
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
62 Facilities Managment Facilities Managment 63
0 1 2 3 4 5 6 7 8 9 10
3.1 Facilities Improvement and Modernization—Appropriate Use of the
Deferred Maintenance Fund
Professional Standard
The district has a restricted deferred maintenance fund and those funds are expended for
maintenance purposes only. The deferred maintenance fund should be a standalone fund reflecting
the revenues and expenses for the major maintenance projects accomplished during the year.
Sources and Documentation
1. Board policy
2. District’s general ledger for deferred maintenance fund
3. Copies of J-205 deferred maintenance fund budget and unaudited actuals document
4. Copies of purchase orders and contracts
5. Copy of five-year deferred maintenance plan
Findings
1. No board policy exists stating the district’s goals for the use of the deferred mainte-
nance funds or the facilities that will carry the highest priority for the deferred mainte-
nance program.
2. The district updates the five-year deferred maintenance plan regularly and submits it
to the Office of Public School Construction for approval.
3. The district makes the annual transfer into the deferred maintenance fund from the
bond proceeds.
Recommendations and Improvement Plan
1. Establish board policy stating the district’s goals for using deferred maintenance
funds, and prioritize deferred maintenance sites and projects.
2. Continue to update the five-year deferred maintenance plan annually to remove main-
tenance completed during the year, and include projects that have become eligible for
funding. While state funding will never reach the level necessary to cover the total
district needs, the district should have a plan in place for all available funding.
3. Any projects included in the five-year plan that have become a safety hazard should
be considered for critical hardship funding, and the appropriate application filed with
the Office of Public School Construction.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
62 Facilities Managment Facilities Managment 63
0 1 2 3 4 5 6 7 8 9 10
3.2 Facilities Improvement and Modernization—Use of Deferred Maintenance
Extreme Hardship Applications
Professional Standard
The district has pursued state funding for deferred maintenance—critical hardship needs by filing
an application/s through the Office of Public School Construction and the State Allocation Board.
[State Allocation Board Regulation §1866]
Sources and Documentation
1. Interview with OPSC staff
2. Interviews with district staff
3. District facilities records
4. State Allocation Board agendas
Findings
1. The district has not pursued deferred maintenance-critical hardship funding through
the State Allocation Board.
Recommendations and Improvement Plan
1. The district should continue to pursue deferred maintenance-critical hardship fund-
ing opportunities through the State Allocation Board, although it is recognized that
the state’s Deferred Maintenance Program is severely hampered because of the state’s
budget crisis.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
64 Facilities Managment Facilities Managment 65
0 1 2 3 4 5 6 7 8 9 10
3.3 Facilities Improvement and Modernization—Application to State
Allocation Board for Facilities Funding
Professional Standard
The district applies to the State Allocation Board for facilities funding for all applicable projects.
Sources and Documentation :
1. Interview with OPSC Project Manager and other staff members
2. OPSC project tracking for the district.
3. Interviews with district staff
4. District facilities records
5. State Allocation Board agendas
Findings
1. The district has made a concerted effort within recent years to qualify for the State
School Facility Program for potential funding of modernization, growth and deferred
maintenance needs. This was also true through the previous state program, the Lease-
Purchase Program.
Recommendations and Improvement Plan
1. The district should continue to monitor potential funding opportunities that may be
available through the current state program, the School Facilities Program. While
the district probably will never be eligible for new construction, it should continue to
monitor opportunities for either additional modernization or even potential joint use
funding.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
64 Facilities Managment Facilities Managment 65
0 1 2 3 4 5 6 7 8 9 10
3.4 Facilities Improvement and Modernization—Determination of Maximum
Eligibility for State Funding
Professional Standard
The district consistently reviews and monitors its eligibility for state funding so as to capitalize
upon maximal funding opportunities.
Sources and Documentation
1. Interviews with district staff
2. Interview with OPSC Project Manager
3. District facilities records
Findings
1. The district has made efforts within recent years to improve its chances for funding
through the State School Facility Program for modernization, growth and deferred
maintenance needs.
2. The current Director of Facilities appears to be knowledgeable about the School
Facilities Program (SFP) and fairly diligently assesses the district’s likely opportunity
to access various funding programs within the SFP. However, a more consistent and
proactive approach toward state program participation and monitoring may need to be
established and maintained.
Recommendations and Improvement Plan
1. The district should increase efforts to participate in the State School Facility Program.
Under the current regulations of the states’ School Facilities Program, it is important
to move individual projects through the DSA approval phase to ensure they are in the
best position for potential state funding.
2. Future Facilities Department staff members should receive training to ensure they
uniformly understand state program regulations and how they specifically apply to ap-
plications for funding for the district.
3. When additional Facilities Department staffing is provided, specific district staff mem-
bers should be responsible for monitoring the state program and serving as a liaison
with appropriate state program representatives.
4. Regularly scheduled coordination meetings should be conducted (district staff, archi-
tects, etc.) to track completion of the activities necessary to enhance state program
funding potential.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
66 Facilities Managment Facilities Managment 67
0 1 2 3 4 5 6 7 8 9 10
3.5 Facilities Improvement and Modernization—Interim Plans for Student
Housing During Construction
Professional Standard
The district establishes and implements interim housing plans for use during the construction
phase of modernization projects and/or additions to existing facilities.
Sources and Documentation
1. Interviews with district staff
2. Review of district records
Findings
1. Multiple modernization projects have been completed and others remain in process.
Typically, the district has not used interim housing for its modernization projects
because they were either completed when school was not in session or the scope of
the projects was so small, interim housing was not required. However, the district staff
was receptive to using interim housing for upcoming modernization as one way to
minimize disruptions to the schools’ instructional programs.
Recommendations and Improvement Plan
1. In order to minimize distractions to the instructional program at sites being modern-
ized or receiving substantial facility additions, the district should consider the follow-
ing
• Include the site-level administrators in discussions focusing upon construction
phasing plans and the need for providing and placing interim housing.
• Make a commitment to providing uniform communication between all in-
volved parties concerning project scheduling.
• Maximize the effectiveness of the interim housing plan by strictly adhere to
project schedules. This requires strong leadership during the construction
administration phase of the project. The project architect, general contractor’s
representative, the district construction representative, and other responsible
parties will need to operate through a cohesive approach toward project and
construction management.
Standard Implemented: Fully-Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
66 Facilities Managment Facilities Managment 67
0 1 2 3 4 5 6 7 8 9 10
3.6 Facilities Improvement and Modernization—Maintenance of a System for
Tracking Project Progress
Professional Standard
The district has established and maintains a system for tracking the progress of individual proj-
ects.
Sources and Documentation
1. Interviews with district staff
2. District facilities records
Findings
1. The district has a wide variety of projects in various phases of planning and construc-
tion.
2. The district is currently utilizing the services of a project management firm. It appears
that a somewhat effective working relationship exists between the project manage-
ment firm and the district staff, however, the district is currently in the process of
selecting an additional and/or different firms.
3. Because of Measures AA and BB and the large number of facilities projects that are
anticipated, the district definitely appears to be understaffed.
4. Aside from the understaffing, the Facilities Department leadership is very knowl-
edgeable, interested in project tracking and appears to have the requisite skills for the
overall management of projects.
Recommendations and Improvement Plan
1. The district should consider the significant project management and project-tracking
needs that will be associated with the aggressive list of future facilities projects. The
district should become better prepared to track the progress of individual projects.
2. All Facilities Department staff members should participate in professional training on
project management. Training should be uniform for all staff.
3. The district should continue to regularly schedule and hold project status meetings
between all involved parties to promote project articulation and to develop a more
uniform understanding of the status of individual projects. Future project managers
should attend these meetings, bringing concise and up-to-date written reports that
reflect the status and needs of projects for which they are responsible.
4. The district should seriously evaluate and remedy understaffing in the Facilities De-
partment.
5. A careful staffing assessment should consider the district’s past and anticipated future
use of outside project management.
68 Facilities Managment Facilities Managment 69
Standard Implemented: Partially
July 1, 2003 Rating: 4
Implementation Scale
Not Fully
68 Facilities Managment Facilities Managment 69
0 1 2 3 4 5 6 7 8 9 10
3.7 Facilities Improvement and Modernization—Furniture and Equipment
Included in Modernization Program
Professional Standard
Furniture and equipment items are routinely included within the scope of modernization projects.
Sources and Documentation
1. Interview with OPSC Project Manager
2. Interviews with district and site staff.
3. District records
Findings
1. An important element within any modernization project is the inclusion of furniture
and equipment.
2. The district has done an admirable job in two areas: (1) Obtaining the passage of local
bond elections for facilities and (2) Seeking and obtaining state funding to supplement
funds generated through successful local bond measures. These collective efforts have
enabled the district to find ways to include furniture and equipment allowances within
modernization projects.
Recommendations
1. The district should continue to ensure that furniture and equipment are routinely in-
cluded in the scope of all modernization projects.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
70 Facilities Managment Facilities Managment 71
0 1 2 3 4 5 6 7 8 9 10
3.8 Facilities Improvement and Modernization—Approval of Plans and
Specifications Prior to Contract Award
Professional Standard
The district obtains approval of plans and specifications from the Division of the State Architect
and the Office of Public School Construction (when required) prior to the award of a contract to
the lowest, responsible bidder. [EC 17263, 17267]
Sources and Documentation
1. Interviews with district staff
2. Review of the district project documents
Findings
1. The district obtains Division of the State Architect and Office of Public School Con-
struction approvals prior to the award of a contract to the lowest, responsible bidder.
2. A few times, the district awarded a construction contract before agency approvals, but
this has only occurred when scheduling needs absolutely necessitated such action.
Recommendations and Improvement Plan
1. The district should continue to require approval of all construction plans prior to
commencement by the Division of the State Architect and the Office of Public School
Construction to maintain maximum funding eligibility.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
70 Facilities Managment Facilities Managment 71
0 1 2 3 4 5 6 7 8 9 10
3.9 Facilities Improvement and Modernization—All Relocatables Meet
Statutory Requirements
Professional Standard
All relocatables in use throughout the district meet statutory requirements. [EC 17292]
Sources and Documentation
1. Inspection of district sites
2. Interviews with district staff
3. Review of district records
4. Review of Division of the State Architect records
Findings
1. It appears that the district has a number of relocatable facilities that may not meet
statutory requirements.
Recommendations and Improvement Plan
1. The district must make an ongoing commitment to systematically install relocatables
only after all required approvals are obtained by the district.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
72 Facilities Managment Facilities Managment 73
0 1 2 3 4 5 6 7 8 9 10
3.10 Facilities Improvement and Modernization—Plan for Maintenance and
Modernization Exists
Professional Standard
The district maintains a plan for the maintenance and modernization of its facilities. [EC 17366]
Sources and Documentation
1. Interviews with district staff
2. Review of district records
Findings
1. A plan exists to guide the district’s facilities program. Consistent and extensive reports
are prepared and present to the district board.
2. The district has filed its five-year deferred maintenance plan with the State Allocation
Board.
3. The district is in the implementation phase of providing improvements to its facilities
through funding approved by local voters and the successful access to state funding.
4. Significant ongoing facility-related improvements need to be addressed .
Recommendations and Improvement Plan
1. The district should continue to follow is schedule for project implementation in the
facilities Department’s periodic report.
2. The district should continue to update its Facilities Department periodic report on a
consistent basis as individual projects are completed and additional facility needs are
identified.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
72 Facilities Managment Facilities Managment 73
0 1 2 3 4 5 6 7 8 9 10
3.11 Facilities Improvement and Modernization—Annual Deferred
Maintenance Contribution is Made Correctly
Professional Standard
The annual deferred maintenance contribution is made correctly. The district should annually
transfer the maximum amount that the district would be eligible for in matching funds from the
state.
Sources and Documentation
1. District’s general ledger for deferred maintenance fund
2. Copies of J-205 deferred maintenance fund budget and unaudited actuals document
3. State correspondence for maximum funding
4. County correspondence regarding possible funding levels
5. Copy of transfer certification document
Findings
1. The district annually transfers sufficient funding from the bond proceeds to the de-
ferred maintenance fund to ensure maximum state funding.
Recommendations and Improvement Plan
1. At a minimum, the district should continue transferring the maximum amount possible
to match the State Deferred Maintenance Apportionment.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
74 Facilities Managment Facilities Managment 75
0 1 2 3 4 5 6 7 8 9 10
3.12 Facilities Improvement and Modernization—Deferred Maintenance
Projects are Actively Managed
Professional Standard
The district actively manages the deferred maintenance projects. The district should review the
five-year deferred maintenance plan annually to remove any completed projects and include any
newly eligible projects. The district should also verify that the expenses performed during the year
were included in the state-approved five-year deferred maintenance plan.
Sources and Documentation
1. District’s general ledger for deferred maintenance fund
2. Copies of purchase orders and contracts
3. Copy of five-year deferred maintenance plan
Findings
1. The district’s 1997-98 deferred maintenance fund general ledger reflected the majority
of the expenditures paid for roofing repair and replacement, which were a part of the
five-year deferred maintenance plan.
2. Since these projects were for large amounts, they were required to go to bid.
3. Verification that the bids were indeed let was obtained from the Purchasing Depart-
ment.
Recommendations and Improvement Plan
1. The district should continue using deferred maintenance funding for those projects
that require immediate attention.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
74 Facilities Managment Facilities Managment 75
0 1 2 3 4 5 6 7 8 9 10
0
3.13 Facilities Improvement and Modernization—Knowledge of Office of
Public School Construction Procedures
Professional Standard
Staff within the district is knowledgeable of procedures within the Office of Public School Con-
struction (OPSC).
Sources and Documentation
1. Interview with OPSC Project Manager
2. Interviews with district staff
Findings
1. Upper-level management is knowledgeable of procedures within the Office of Public
School Construction (OPSC).
Recommendations and Improvement Plan
1. The district Facilities Department (once additional staffing is retained) should receive
training on proven methodologies to work effectively with the OPSC staff and to fully
understand OPSC procedures, especially with the implementation and ongoing refine-
ment of SB 50 regulations.
2. district personnel could provide the training, but it should be augmented with outside
professionals who have experience in working with OPSC staff and who are well-
versed in OPSC procedures. This type of training will be especially important if and
when Facilities Department staffing is increased.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
76 Facilities Managment Facilities Managment 77
0 1 2 3 4 5 6 7 8 9 10
3.14 Facilities Improvement and Modernization—Knowledge of Division of
State Architect Procedures
Professional Standard
Staff within the district is knowledgeable of procedures within the Division of the State Architect
(DSA).
Sources and Documentation
1. Interview with DSA staff
2. Interviews with district staff
Findings
1. Upper-level management is knowledgeable of procedures within the Division of the
State Architect (DSA).
2. The current construction-related staff within the Facilities Department is very familiar
with DSA procedures.
Recommendations and Improvement Plan
1. If and when additional district Facilities Department staff members are employed,
they should receive extensive training to fully understand DSA procedures. This train-
ing should be provided by outside professionals who have experience in working with
DSA and who are well-versed in DSA policies, procedures and regulations.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
76 Facilities Managment Facilities Managment 77
0 1 2 3 4 5 6 7 8 9 10
4.1 Construction of Projects—An Appropriate Project Management Structure
Exists
Professional Standard
The district maintains an appropriate structure for the effective management of its con-
struction projects.
Sources and Documentation
1. Interviews with district staff
2. Review of district records
3. Interviews with contractors from respective construction projects
Findings
1. The district is managing its current construction projects fairly well, but there is a
significant concern that low staffing in the Facilities Department will impede broader-
scale project management once Measure AA and BB projects begin.
2. The district has contracted with a project manager and this working relationship is
moderately effective. However, the district is implementing an additional selection
process for project/construction management services.
Recommendations and Improvement Plan
1. The district should carefully plan for upcoming project management needs, consider-
ing the large number of Measure AA and BB projects scheduled.
2. The district should establish procedures to evaluate the ongoing effectiveness of its
district/project management relationship. The results of this evaluation should guide
the degree to which outside project management services will be used in the future.
3. All future Facilities Department staff members who are retained for the construction
phase of projects should participate in professional training in project and construction
management.
4. Provisions for team building/training should be made for the various in-house and out-
side professionals involved in facilities-related projects to ensure that effective project
coordination and articulation occurs. This will be especially important to enhance the
most efficient use of local funds as the district continues to pursue future state fund-
ing.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
78 Facilities Managment Facilities Managment 79
0 1 2 3 4 5 6 7 8 9 10
4.2 Construction of Projects—Change Orders are Processed and Received
Prior Approval
Professional Standard
Change orders are processed and receive prior approval from required parties before being
implemented within respective construction projects.
Sources and Documentation
1. Interview with inspector/s of record
2. Interviews with district staff
3. Interviews with respective contractors
4. Review of district records
Findings
1. The district has generally obtained all required approvals for change orders prior to
their implementation. Current written procedures exist to guide the change-order
process within district projects. The importance of this practice cannot be overstated
due to the financial implications that can result through a haphazard adherence to this
practice.
2. The district has had mixed experiences with respect to its inspectors of record. The
inspector is an important participant in the change-order review/approval process.
Recommendations and Improvement Plan
1. The district should clearly communicate to all project participants its standard of ob-
taining all necessary approvals for change orders prior to implementation.
2. Establish procedures and standards for selecting and employing inspectors of record
and cover within their initial training the standard of obtaining all necessary approvals
for change orders prior to implementation.
Standard Implemented: Fully - Susbtantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
78 Facilities Managment Facilities Managment 79
0 1 2 3 4 5 6 7 8 9 10
4.3 Construction of Projects—Appropriate Project Records and Drawings are
Maintained
Professional Standard
The district maintains appropriate project records and drawings.
Sources and Documentation
1. Interview with Inspector/s of Record
2. Interviews with district staff
3. Review of district records
Findings
1. Like many California public school districts, Berkeley Unified is somewhat disorga-
nized and inconsistent in maintaining project records and drawings.
2. The district needs an improved system of storing and maintaining project records and
drawings to support future needs regarding facilities repairs and/or modifications.
Recommendations and Improvement Plan
1. The district should improve its process of storing and maintaining records and draw-
ings by establishing internal systems for this purpose.
2. The district should designate an area and develop a system to maintain project draw-
ings and specifications. This area should be close to the Director of Facilities’ office
to ensure monitoring of plan check out and to ensure as-built plan availability and
utilization.
3. The district should communicate to parties involved in facilities projects that there is a
system to record plan checkout, and that those who check documents out will be held
responsible for their return.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
80 Facilities Managment Facilities Managment 81
0 1 2 3 4 5 6 7 8 9 10
4.4 Construction of Projects—Inspector of Record Assignments are Properly
Approved
Professional Standard
Each Inspector of Record (IOR) assignment is properly approved.
Sources and Documentation
1. Interview with DSA staff
2. Interviews with district staff
3. Review of district records
Findings
1. The district employs its inspectors of record, and each assignment is properly ap-
proved. The district has expressed some level of dissatisfaction regarding the quality
of inspection services it has received on some occasions. There is a shortage of quali-
fied inspectors throughout the state.
Recommendations and Improvement Plan
1. The district should analyze its process for employing inspectors of record. Based upon
the previous level of satisfaction for services received, the district should modify the
criteria used to select and employ inspectors of record.
Standard Implemented: Fully - Susbtantially
July 1, 2003 Rating: 9
Implementation Scale
Not Fully
80 Facilities Managment Facilities Managment 81
0 1 2 3 4 5 6 7 8 9 10
5.1 Compliance with Public Contracting Laws and Procedures—Compliance
with Formal Bidding Procedures
Professional Standard
The district complies with formal bidding procedures. [GC 54202, 54204, PCC 20111]
Sources and Documentation
1. Board policy
2. Copy of bid processing documents
3. Sample bid documents including ads, bid packets, awards, and correspondence
Findings
1. A board policy for the bidding process was not available. The board is updating many
of the policies relating to contracting for services and the bid process.
2. The district has a well-documented bid process as verified by the Director or Facili-
ties. Sample bid document #836.9601 for the construction of the new alternative high
school provided a clear understanding of what is required of the bidders, including
minimum documentation required for a bid to be considered, the deductive alterna-
tives to the bid, the composition of the company bidding on the project, and lengthy
details of the work being considered.
3. The process is well documented and adhered to according to the files. The Purchasing
Department maintains the files for the process, and works closely with the Facilities
Department in the progress of each bid.
4. Since the district initiated the current bid procedure, there has been a reduction in the
number of appeals.
5. The district has implemented the uniform-cost accounting program, which allows the
Maintenance Department to perform more projects without going to bid as often.
Recommendations and Improvement Plan
1. The district should develop board policy for the bid process, detailing what the Gov-
erning Board expects of the staff.
2. The district should continue with the current bid process and the related documenta-
tion.
3. Include the board policy should be included as a portion of the bid document.
4. district administration should support the implementation of the uniform-cost account-
ing program to provide quicker turnaround of maintenance needs.
82 Facilities Managment Facilities Managment 83
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
82 Facilities Managment Facilities Managment 83
0 1 2 3 4 5 6 7 8 9 10
5.2 Compliance with Public Contracting Laws and Procedures—Procedures for
Requests for Quote/Proposals
Professional Standard
The district has a procedure for requests for quotes/proposals. [GC 54202, 54204, PCC 20111]
Sources and Documentation
1. Board policy
2. Sample requests for proposals
Findings
1. A current board policy for the bidding process was not available. The board is cur-
rently updating many of the policies relating to contracting for services and the bid
process.
2. The district has a well-documented bid process as verified by the Director or Facili-
ties. This process includes guidelines to determine when the district will request
quotes or bids for projects. The Purchasing Department maintains files for this process
and works closely with the Facilities Department.
3. The purchasing agent is the primary party responsible for handling the informal quotes
and bids to provide a clean internal control break. The process is well documented and
adhered to per the files.
4. Since the district initiated the current bid procedure, there has been a reduction in the
number of appeals.
Recommendations and Improvement Plan
1. The district should develop board policy for the bid process detailing what the Gov-
erning Board expects of the staff.
2. The district should continue with the current bid process and the related documenta-
tion.
3. The board policy should be included as a portion of the bid document.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
84 Facilities Managment Facilities Managment 85
0 1 2 3 4 5 6 7 8 9 10
5.3 Compliance with Public Contracting Laws and Procedures—Conflict of
Interest Statements and Compliance
Professional Standard
The district maintains files of conflict of interest statements and complies with legal
requirements. Conflict of interest statements should be collected annually by the superintendent
and kept on file.
Sources and Documentation
1. Board policy
2. Copies of sample conflict of interest statements on file
Findings
1. Board policy 9270 had last been revised in 1982 and did not reflect current practices.
2. The positions listed in the policy were outdated and had not been revised to reflect
changes in organizational structure and job titles.
3. Annual recertifications for positions that require conflict-of-interest statements to be
filed with the county were inaccurately certified as being correct, but they were incor-
rect.
4. For both 2000 and 2002, follow-up letters from the county indicated that filings had
not been made on time and were made only after follow-up by the county.
5. Conflict-of-interest statements for the year 2000 and earlier were on file in the Super-
intendent’s office and appeared to be complete, except that there was no statement on
file for the Superintendent for the year 2000.
6. Assessment team members were not able to examine statements filed for 2001, 2002,
and 2003 because they could not be located at the time of FCMAT’s visit.
Recommendations and Improvement Plan
1. Board policy 9270 should be revised to reflect current positions and procedures.
2. The district should update certification to the county regarding which positions had
been designated by the board.
3. The district should ensure that in the future, the board designates positions correctly
before providing certifications to the county.
4. The filing of conflict-of-interest statements and recertifications should be completed
on time and without additional prompting by the county.
5. Annual collection and filing of conflict of interest statements for 2001, 2002, and 2003
should be verified as having actually occurred and that the statements are on file for
those years.
84 Facilities Managment Facilities Managment 85
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
86 Facilities Managment Facilities Managment 87
0 1 2 3 4 5 6 7 8 9 10
5.4 Compliance with Public Contracting Laws and Procedures—Development
of Biddable Plans and Specifications
Professional Standard
The district ensures that biddable plans and specifications are developed through its licensed
architects/engineers for respective construction projects.
Sources and Documentation
1. Interviews with district staff
2. Review of district records
3. Interviews with project contractors
4. Interviews with inspectors of record
Findings
1. The district has expressed some concern about prior difficulties with the quality of
plans and specifications prepared and utilized during respective project bid periods.
2. As a result of inadequate or poorly prepared plans and specifications, the district may
have sometimes been exposed unnecessarily to project cost and time line overruns.
Recommendations and Improvement Plan
1. The district should consistently analyze the “bidability and constructability” of plans
and specifications for future projects.
2. Before establishing a bid schedule for a construction project, the district should con-
duct coordination meetings between the project architect, the architect’s engineering
consultants and district representatives to address “bidability and constructability” of
plans and specifications.
3. These meetings should discuss plans and specifications relative to program needs and
project budget.
4. The district should consider completing a constructability review of each project’s
plans and specifications.
5. Required revisions as recommended through the project constructability review
should be made to the plans and specifications prior to bid authorization.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
86 Facilities Managment Facilities Managment 87
0 1 2 3 4 5 6 7 8 9 10
5.5 Compliance with Public Contracting Laws and Procedures—Evaluation of
Requests for Progress Payments
Professional Standard
The district ensures that requests for progress payments are carefully evaluated.
Sources and Documentation
1. Interviews with district staff
2. Interviews with project managers and contractors
3. Review of district records
Findings
1. The district has a system in which progress payment requests within respective proj-
ects are carefully evaluated.
2. Individuals interviewed stated that significant improvement has been made within this
area over the past couple of years.
3. The staff noted that improvements in the selection and utilization of architectural/
engineering firms and inspection services will enhance the team approach required to
fairly and successfully evaluate progress payment requests.
Recommendations and Improvement Plan
1. The district should take steps to continue to address the effective and systematic
review of progress payments. This is even more important given the responsibility as-
sociated with the efficient implementation and utilization of Measure AA/BB and state
funds.
2. The district should continue its recent efforts to enhance the selection and employment
of qualified architectural/engineering firms and to improve its selection and retention
of qualified inspectors of record.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
88 Facilities Managment Facilities Managment 89
0 1 2 3 4 5 6 7 8 9 10
5.6 Compliance with Public Contracting Laws and Procedures—Contract
Award Appeal Procedures
Professional Standard
The district maintains contract award/appeal processes. [GC 54202, 54204, PCC 20111]
Sources and Documentation
1. Board policy
2. Interview with Director of Facilities and Director of Maintenance
Findings
1. A current board policy for the appeal process was not available. The board is currently
updating many policies relating to the appeal process and the bid process.
2. The district has a well-documented bid process as verified by the Director or Facili-
ties. While the district has had some appeals and litigation regarding recent awards of
contracts, the district has successfully defended all challenges. Much of this success is
attributed to bid documents that are solid.
3. Since the district initiated the current bid procedure, there has been a reduction in the
number of appeals.
Recommendations and Improvement Plan
1. The district Governing Board should adopt a board policy that delineates the appeal
process.
2. The district should continue the current bid and appeal process.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
88 Facilities Managment Facilities Managment 89
0 1 2 3 4 5 6 7 8 9 10
5.7 Compliance with Public Contracting Laws and Procedures—Internal
Control of Bidding Process
Professional Standard
The district maintains internal control, security, and confidentiality over the bid submission and
award processes. [GC 54202, 54204, PCC 20111]
Sources and Documentation
1. Board policy
2. Interview with Director of Facilities and Director of Maintenance
Findings
1. A current board policy for the proper internal control of the bidding process was not
available. The board is updating many of the policies relating to the bid process.
2. The district has a good internal control procedure over the bidding process. While the
Facilities Department initiates the request for the proposal, the Purchasing Department
is a key partner in the process. According to the Director of Facilities, the Purchas-
ing Department has the primary responsibility for coordinating and disseminating the
documents. The Purchasing Department is also responsible for issuing the contract
once the bid has been awarded. This provides a very good internal control procedure.
Recommendations and Improvement Plan
1. The district Governing Board should adopt a board policy that delineates the proper
internal control process.
2. The district should continue the current bid process, which includes a sound internal
control standard.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
90 Facilities Managment Facilities Managment 91
0 1 2 3 4 5 6 7 8 9 10
6.1 Special Education Facilities—Compliance with CDE Regulations
Professional Standard
The district complies with California Department of Education (CDE) requirements relative to
the provision of Special Education facilities.
Sources and Documentation
1. Interviews with CDE staff
2. Interviews with district staff
3. Inspection of District sites/facilities
Findings
1. The district generally understands the requirements for special education facilities and
provides them accordingly, within given physical constraints.
2. The district provides appropriate physical spaces for its less severely handicapped
students (direct-service programs) through district-administered programs.
3. Facilities and services for more severely handicapped students are provided through
special education programs generally operated within district facilities. In some
instances, adjunct special education services (speech therapy, psychological services,
etc.) are provided in “substandard” spaces.
Recommendations and Improvement Plan
1. The district should develop a plan to ensure that adequate spaces are provided for all
special education programs and services.
2. A facilities inventory/assessment should be completed to determine the actual space
allocations for current special education programs (within both relocatable and perma-
nent facilities).
3. The information in this analysis should be compared with program needs and expecta-
tions to ensure that the delivery of quality special education programs is not inhibited
due to space and/or location limitations.
4. The analysis Findings should be compared with recommendations provided through
the California Department of Education, the Office of Public School Construction and
the State Allocation Board relative to suggested areas for programs.
5. A plan should be developed to correct any space and/or location deficiencies that exist
within district school sites concerning the delivery of instructional services and pro-
grams for special education students.
6. The fiscal impact associated with the implementation of this plan should be developed
and considered within the broader context of facilities-related needs.
90 Facilities Managment Facilities Managment 91
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
92 Facilities Managment Facilities Managment 93
0 1 2 3 4 5 6 7 8 9 10
6.2 Special Education Facilities—Equity with Other Facilities, Appropriate to
Educational Program
Professional Standard
The district provides facilities for its Special Education programs that ensure equity with other
educational programs within the district and provides appropriate learning environments in rela-
tion to educational program needs.
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with district staff
Findings
1. The district provides special education facilities in a manner that is similar to many
California public school districts. Because of the fewer numbers of students that are
typically included within special education programs, services are sometimes pro-
vided within physical spaces smaller and/or different than spaces provided for other
educational programs.
2. It appears that this practice may have been further affected in recent years because
of additional space requirements created through the implementation of Class Size
Reduction.
Recommendations and Improvement Plan
1. The district should develop a plan to ensure equity between facilities provided for all
special education students and special education program services and for students
within other educational programs.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
92 Facilities Managment Facilities Managment 93
0 1 2 3 4 5 6 7 8 9 10
6.3 Special Education Facilities—Adequacy for Instructional Program Needs
Professional Standard
The district provides facilities for its Special Education programs that provide appropriate learn-
ing environments in relation to educational program needs.
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with district staff
Findings
1. Due to the varying needs and evolving enrollment of special education students, it
appears that the locations for some special education services are provided, to some
degree, on a “transient” basis. This especially appears to be more apparent in those
programs and services provided on an adjunct basis.
2. In some instances, it appeared that spaces were created to accommodate special
education students, but that these spaces were not always suitable in comparison to
program and student needs.
Recommendations and Improvement Plan
1. In order to develop a plan to ensure special education students are provided with spe-
cial education spaces and facilitate the delivery of high-quality programs and services,
the district should complete a facilities inventory/assessment.
2. The facilities inventory/assessment should be completed to determine the actual space
allocations for current special education programs (within both relocatable and perma-
nent facilities).
3. The analysis of existing space allocations should be compared with program needs
and expectations to ensure that the delivery of quality special education programs is
not inhibited because of space and/or location limitations.
4. The Findings of the analysis should be compared with recommendations provided
through the California Department of Education, the Office of Public School Con-
struction and the State Allocation Board relative to suggested areas for respective
programs.
5. A plan should be developed to correct any space and/or location deficiencies that exist
within respective district school sites relative to the delivery of instructional services
and programs for special education students.
6. The fiscal impact associated with the implementation of this plan needs to be devel-
oped and considered within the broader context of facilities-related needs.
94 Facilities Managment Facilities Managment 95
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
94 Facilities Managment Facilities Managment 95
0 1 2 3 4 5 6 7 8 9 10
7.1 Implementation of Class-Size Reduction—Application for Funding
Professional Standard
The district applies for state funding for class-size reduction facilities. The district should apply
for class-size reduction facilities funding annually.
Sources and Documentation
1. 2002-03 CSR operational application
2. State apportionment for class size reduction operations
Findings
1. For the 2002-03 fiscal year, no funding was made available for K-3 class-size reduc-
tion facilities.
2. The district did apply for and received funding for the 2002-03 operations, which can
be used for both operational and facilities expenses.
Recommendations and Improvement Plan
1. The district should continue to apply annually for class-size reduction facilities fund-
ing in years when funding is available. These applications may also make the district
eligible for future state bond funds for class-size reduction.
2. The district should also continue to annually apply for class-size reduction operations
funding.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
96 Facilities Managment Facilities Managment 97
0 1 2 3 4 5 6 7 8 9 10
7.2 Implementation of Class-Size Reduction—Adequacy of Facilities for
Additional Classes
Professional Standard
The district has provided adequate facilities for the additional classes resulting from the imple-
mentation of Class-Size Reduction (CSR).
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with district staff
3. Review of district Web page
Findings
1. The district and its constituency have done a remarkable job in implementing a Class
Size Reduction program. This program has generally been made possible through the
passage of the Berkeley Schools Educational Enrichment Act of 1986 (BSEP). The
voter-approved tax program helps to fund class sizes of 25 to one at the elementary
level and 27 to one at the secondary level. Additionally, the district has maintained ex-
tremely small enrollments at respective schools (from a relative standpoint throughout
the state of California).
2. The district has provided facilities for additional classes that have resulted through
the implementation of CSR. This has been accomplished through the reallocation/
modified use of existing spaces, as well as through the acquisition of additional relo-
catable teaching stations.
Recommendations and Improvement Plan
1. The district should maintain an ongoing goal to ensure fully equitable teaching and
learning environments are provided for its CSR classes.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
96 Facilities Managment Facilities Managment 97
0 1 2 3 4 5 6 7 8 9 10
7.3 Implementation of Class-Size Reduction—Compliance with CDE Space
Requirements
Professional Standard
The district has complied with CDE suggested space requirements relative to the provision of
educational environments for the implementation of Class Size Reduction (CSR).
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with district staff
Findings
1. The vast majority of the CSR classes are being conducted in teaching stations that
comply with CDE recommendations.
2. In some very limited instances, classes are being conducted in teaching stations that
do not meet the California Department of Education suggested square footage require-
ments.
Recommendations and Improvement Plan
2. The district should maintain an ongoing goal to ensure fully equitable teaching and
learning environments are provided for its CSR classes.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
98 Facilities Managment Facilities Managment 99
0 1 2 3 4 5 6 7 8 9 10
7.4 Implementation of Class-Size Reduction—Plans for Permanent Facilities
Professional Standard
The district has developed a plan for the provision of permanent facilities in which to house its
CSR programs.
Sources and Documentation
1. Interviews with district staff
2. Review of district records/plans
3. Inspection of district sites/facilities
Findings
1. While the district had done a remarkable job in providing adequate space for the im-
plementation of Class Size Reduction, there appears to be no finalized plan to provide
permanent facilities to house all of its CSR programs.
Recommendations and Improvement Plan
1. Although it is financially burdensome, the district should develop a plan to ensure the
provision of permanent facilities as a result of the district’s extensive and broad-based
implementation of Class Size Reduction programs. The district and its oversight com-
mittees should evaluate the relative importance of implementing this plan in consid-
eration of other district facilities-related needs. This consideration should be included
within the district’s self-evaluation of its overall number of operating school facilities
and any future change to the district’s current grade-level organizational structure.
2. A facilities inventory/assessment should be completed to determine the actual space
allocations for current Class Size Reduction programs and to identify which of those
programs are being implemented in “nonpermanent” facilities vs. permanent facilities.
3. The Findings of the inventory/assessment should be compared with suggested guide-
lines from the California Department of Education concerning suggested room size.
4. A plan should be developed to correct any space and “permanency” deficiencies that
exist within respective district school sites concerning the delivery of instruction
services and programs for Class Size Reduction programs. A fiscal impact associated
with plan implementation should be considered within the broader context of facili-
ties-related needs.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
98 Facilities Managment Facilities Managment 99
0 1 2 3 4 5 6 7 8 9 10
8.1 Facilities Maintenance and Custodial—Energy Conservation Policy
Professional Standard
An energy conservation policy should be approved by the Board of Education and implemented
throughout the district.
Sources and Documentation
1. Energy policy for school design
2. Review of materials provided by the district staff
3. Interviews with district staff
Findings
1. The district has approved an energy resolution for state funding and an energy policy
for design professionals working with the district. However, there is no comprehen-
sive board-approved energy policy.
Recommendations and Improvement Plan
1. The district should create a board policy and implement it districtwide.
2. The district should include, at least the following items in the policy:
• Board commitment to energy efficiency.
• Direction to administrators to aggressively implement the policy.
• Energy management shall be a high priority in new construction, moderniza-
tion, equipment replacement or repair project.
• A list of energy design criteria will be produced for use by design teams work-
ing for the district.
• All sites not part of state funded modernization shall be made energy efficient
through alternate funding.
• Identify specific items for implementation.
• All heating and ventilation systems will be turned off at the close of the school
day (when classes end).
• All systems will be kept off on weekends and holidays.
• After-school and weekend meetings will take place in portable classrooms so
large centralized systems do not have to run for a meeting in one classroom.
• Lights are to be shut off whenever a room becomes unoccupied.
• Morning warm up of a school site should begin at the latest possible time in
order to properly heat classrooms.
• All rooms will be checked at appropriate times in order to ensure lighting,
heating and ventilation are turned off.
• Each site should have a designated energy coordinator to implement the
policy.
• Stadium lights (football, soccer, baseball) shall not be turned on during day-
time hours except for repairs and lamp replacement.
• Principals shall be responsible and held accountable for the results of the en-
ergy program at their site.
• An energy education curriculum shall be included at all levels and disciplines.
100 Facilities Managment Facilities Managment 101
• The district shall implement an energy-accounting system, review bills month-
ly and annually, and track the success of the program.
• The district shall share savings with individual school sites based on their suc-
cess in an operational energy-saving program.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
100 Facilities Managment Facilities Managment 101
0 1 2 3 4 5 6 7 8 9 10
8.2 Facilities Maintenance and Custodial—Energy Accounting System
Professional Standard
Create and maintain a system to track utilities costs, consumption and report on the success of
the district’s energy program.
Sources and Documentation
1. Review of materials provided by the district staff
2. Interviews with the district staff
Findings
1. The district has not implemented a system to account for energy use and utilities ex-
pense.
2. The district has several utilities bills, but is unsure which site incurred them or wheth-
er they are actually district bills.
3. There is currently no way to track the results of recently completed energy projects
and energy-efficient design measures.
Recommendations and Improvement Plan
1. A system should be established in the business office with assistance from facilities to
log consumption and cost as part of the bill-paying process. Reports should be created
and sent to facilities for review and possible action.
2. Items for review include billing errors, review of billing tariffs, drastic changes in
consumption and cost, monitoring of projects effect on consumption and tracking of
the energy program.
Standard Implemented: Partially
July 1, 2003 Rating: 2
Implementation Scale
Not Fully
102 Facilities Managment Facilities Managment 103
0 1 2 3 4 5 6 7 8 9 10
8.3 Facilities Maintenance and Custodial—Completion of Energy Analyses
Professional Standard
An energy analysis should be completed for each site.
Sources and Documentation
1. Review of materials provided by district staff
2. Interviews with district staff
Findings
1. The district has received proposals from an Energy Service Company (ESCO) to per-
form a number of services including lighting retrofit, upgrade and recommissioning of
the Allerton EMS at different sites. A great majority of district sites that have received
lighting retrofits are now energy efficient in that area. However, the control of HVAC
systems and outside lighting is sorely lacking.
The district should consider replacing the Allerton EMS. Allerton continues to install
its IBEX system at district sites, and the system is relatively inexpensive, but it uses
10-year old technology and communicates over phone lines instead of being Internet
based. Current EMS should be Internet-based and easier to operate. FCMAT was able
to access only a few systems while at the maintenance office. Some phone lines did
not work.
Instead of recommisioning existing systems, it may be better to explore what other
systems are available at a relatively low cost range. Some examples are Automated
Logic, Carrier and Non-Proprietary Lon Based Systems. Once concern with Lon
Based Systems is that ease of use of the software package is extremely important.
There is no advantage to Lon Works over BacNet. FCMAT estimates that districtwide
implementation of EMS would save the district 10 percent-15 percent from current
electric consumption.
Recommendations and Improvement Plan
1. The district should complete an energy analysis at all district sites.
2. The cost-effective Findings of the analyses should be implemented.
3. ESCO should not be hired. to implement energy-saving projects because their man-
agement fees are usually twice that of traditional design professionals. Consider an
energy consultant, engineer or the district architect as more cost-effective alternatives.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
102 Facilities Managment Facilities Managment 103
0 1 2 3 4 5 6 7 8 9 10
8.4 Facilities Maintenance and Custodial—Energy Efficient Design Criteria
for New Construction and Modernization
Professional Standard
Cost-effective, energy-efficient design should be a top priority for all district construction proj-
ects.
Sources and Documentation
1. District policy
2. Review of materials provided by district staff
3. Interviews with district staff
Findings
1. In 1994 the district published an energy design standards policy for design profession-
als working with the district. In it are goals to improve the energy efficiency by 40
percent before the year 2000 and to exceed Title 24 energy efficiency standards in new
construction and modernization by at least 40 percent. Other district responsibilities
are not being implemented and are addressed in other sections of this document.
Recommendations and Improvement Plan
1. The district should continue to actively implementing this policy in its facilities con-
struction program.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
104 Facilities Managment Facilities Managment 105
0 1 2 3 4 5 6 7 8 9 10
8.4a Facilities Maintenance and Custodial—Take advantage of State and
Local Program for energy assistance and partial funding of energy efficiency
Professional Standard
The district should be in discussion and working as a team with agencies that can provide profes-
sional assistance and funding.
Sources and Documentation
1. Review of materials provided by district Staff
2. Interviews with district Staff
Findings
1. District teachers have applied for and received more than $3,000 from the State Con-
sumer Services Agency for Energy Education.
2. The district’s experience with the California Energy Commission was not as helpful as
hoped.
3. The district is working with PG&E to identify electric meters and meter locations to
set up an energy accounting system.
Recommendations and Improvement Plan
1. The district should continue working with PG&E, South Bay MUD and the P.U.C. to
gain incentives for energy efficiency on all projects where energy costs are affected.
2. The district should continue working with SCSA to gain free services.
Standard Implemented: Fully - Sustained
July 1, 2003 Rating: 10
Implementation Scale
Not Fully
104 Facilities Managment Facilities Managment 105
0 1 2 3 4 5 6 7 8 9 10
8.4b Facilities Maintenance and Custodial—Implement Energy Projects at
sites not funded by the local bond
Professional Standard
The district should act towards improving the energy efficiency of all sites, including those not
included in the local bond.
Sources and Documentation
1. Review of materials provided by district staff
2. Interviews with district Staff
Findings
1. The district has aggressively upgraded lighting at district sites. Some areas still require
this change.
2. The existing energy management system does not serve all sites and does not serve
any sites well.
3. The project information from the Energy Service Company did not show unit costs.
Generally ESCO charges 35 percent-to 50 percent or more as its management fee.
This is extreme and not in the district’s best interests. This can cost hundreds of thou-
sand of additional dollars with no benefit to the district.
Recommendations and Improvement Plan
1. The district should continue to upgrade the energy efficiency of the facilities and con-
sider hiring an engineer, the district architect, using in-house design or the state. Each
of these options is less expensive than an Energy Service Company.
3. The district should plan to replace the existing energy management system and install
a Web-based system districtwide.
4. The district should continue to upgrade efficiency as part of bond-funded projects.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
106 Facilities Managment Facilities Managment 107
0 1 2 3 4 5 6 7 8 9 10
8.4c Facilities Maintenance and Custodial—Generation and Purchase of
Utilities
Professional Standard
The district should analyze the possibility of using alternative energy sources as a means to
reducing the financial impact of utilities on the district.
Sources and Documentation
1. Interviews with district staff
Findings
1. The district has not looked into generation options.
Recommendations and Improvement Plan
1. The district may want to approach generation options in a few ways. First, the dis-
trict can analyze solar, wind and micro turbines just as they would analyze an energy
project. However, these technologies have specific sensitivities in the areas of noise,
durability, space and cost.
2. The district may want to look into third-party programs, which allow a company to
build a small generation facility on district-owned land and purchase power on a long-
term basis.
3. The district may want to investigate a JPA with other entities to purchase power at a
relatively low rate.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
106 Facilities Managment Facilities Managment 107
0 1 2 3 4 5 6 7 8 9 10
8.5 Facilities Maintenance and Custodial—Adequate Maintenance Records
and Inventories
Professional Standard
Adequate maintenance records and reports are kept, including a complete inventory of supplies,
materials, tools, and equipment. All employees required to perform maintenance on school sites
should be provided with adequate supplies, equipment, and training to perform maintenance tasks
in a timely and professional manner. Included in the training is how to inventory supplies and
equipment and when to order or replenish them.
Sources and Documentation
1. Work orders
2. Inventory records
3. Site observation of actual inventory
Findings
1. During the site observations and interviews, some site personnel felt that they had
adequate access to supplies for cleaning and maintaining the facilities. A review of the
supply closet and the maintenance rooms showed ample supplies for cleaning, how-
ever, it was not apparent that the proper supplies needed were available.
2. Some of the schools had small inventories of minor maintenance supplies for the cus-
todial staff to assist the maintenance staff.
3. The inventory available in the Maintenance Department was smaller than expected.
However, with multiple vendors and open purchase orders available, the need for a
larger inventory does not seem necessary.
4. All work orders are on a districtwide computer system that allows the site administra-
tors to see which requests are still pending. It also allows the maintenance staff and
administration to anticipate the materials needs for future projects to determine if large
materials orders could be made to reduce down time in picking up necessary supplies.
Recommendations and Improvement Plan
1. The district should continue with the current inventory of supplies and materials at the
main maintenance yard.
2. The district should establish a minimum inventory level of both custodial and main-
tenance supplies for each school. If a school’s custodial staff can assist with graffiti
abatement, adequate supplies of cleaning and painting supplies and materials should
be provided in a timely manner.
3. The district should continue to monitor the work order system to determine whether
cost savings are possible by making bulk purchases in anticipation of large or similar
work orders in the system.
108 Facilities Managment Facilities Managment 109
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
108 Facilities Managment Facilities Managment 109
0 1 2 3 4 5 6 7 8 9 10
8.6 Facilities Maintenance and Custodial—Procedures for Evaluation of
Maintenance and Operations Staff
Professional Standard
Procedures are in place for evaluating the work quality of maintenance and operations staff. The
quality of the work performed by the maintenance and operations staff should be evaluated on a
regular basis using a board-adopted procedure that delineates the areas of evaluation and the types
of work to be evaluated.
Sources and Documentation
1. Board policy
2. Job descriptions
3. Interview sampling of employees and supervisors
Findings
1. Under the current evaluation process, the Director of Maintenance evaluates the
maintenance supervisors. The maintenance supervisors evaluate their workers, and the
Director of Maintenance reviews the evaluations prior to submission to the Personnel
Department.
2. The evaluation process is complicated, since there are three different unions that are
a part of the Maintenance and Operations Department. The district recently reached
agreement with the newest of the bargaining units, Local 21.
3. Evaluations are to be performed annually at a minimum. Evaluations are performed
more often if an employee is performing at a less-than-acceptable level.
4. Some employees were not sure of the last time they received an evaluation. A review
of the personnel files confirmed that some employees had not been evaluated in the
past few years.
Recommendations and Improvement Plan
1. The district should require all supervisory personnel responsible for evaluating clas-
sified staff members to record all cases of outstanding work, unsatisfactory work, and
incomplete maintenance requests as a part of the evaluation process.
2. The completeness of maintenance records should be included in the evaluation of
maintenance personnel.
3. The district should provide in-service training for all supervisory personnel in the
proper documentation of personnel standards.
4. Administrative staff should periodically review evaluations for adherence to personnel
standards.
5. The maintenance of an accurate supply inventory is important to the productivity of
the Maintenance Department. Employees should be held accountable for their part in
keeping the inventory accurate. This is best done in the evaluation process.
110 Facilities Managment Facilities Managment 111
Standard Implemented: Partially
July 1, 2003 Rating: 4
Implementation Scale
Not Fully
110 Facilities Managment Facilities Managment 111
0 1 2 3 4 5 6 7 8 9 10
8.7 Facilities Maintenance and Custodial—Identification of Maintenance and
Custodial Responsibilities
Professional Standard
Major areas of custodial and maintenance responsibilities, and specific jobs to be performed, have
been identified. Custodial and maintenance personnel should have written job descriptions that
delineate the major areas of responsibilities that they will be expected to perform and on which
they will be evaluated.
Sources and Documentation
1. Board policy
2. Bargaining group agreements
3. Job descriptions
4. Interview with sampling of employees and supervisors
Findings
1. The site personnel interviewed felt that they had a good understanding of what was
expected of them in order to perform their jobs properly. While some felt that they
could do more if allowed, they accepted the job duties as explained to them.
2. There is some confusion about when the custodial staff can perform minor mainte-
nance projects and when they need to wait until the maintenance staff can do them
3. The custodial staff members who were interviewed commented that they had the
resources necessary to perform their duties. When they needed supplies, they received
them if they could show the need existed and that previous inventories had been de-
pleted.
Recommendations and Improvement Plan
1. The district should annually review with all Maintenance and Operations staff their
job descriptions and anticipated duties so that there is a clear understanding of what is
expected of them and how they will be evaluated.
2. The district should discuss with the staff which areas may be considered for the future
to be covered by either operational or maintenance staff, and how other duties will be
assigned and approved.
3. The positive communication between the Director of Maintenance and the mainte-
nance crews should be continued.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
112 Facilities Managment Facilities Managment 113
0 1 2 3 4 5 6 7 8 9 10
8.8 Facilities Maintenance and Custodial—Availability of Custodial Supplies
and Equipment
Professional Standard
Necessary staff, supplies, tools, and equipment for the proper care and cleaning of the schools
are available. In order to meet expectations, schools must be adequately staffed and staff must be
provided with the necessary supplies, tools, and equipment as well as the training associated with
the proper use of such.
Sources and Documentation
1. Inventory records
2. Purchase orders for supplies and equipment
3. Site observation of actual inventory
Findings
1. Some of the site staff interviewed commented they had all of the necessary chemicals
to perform the various cleaning needs of the schools. However, some of them felt that
they could use additional training on cleaning practices.
2. Some of the staff observed seemed less-than-motivated to do anything more than the
minimum required tasks. One staff person was seen passing by a trash-covered area
while pushing his empty custodial barrel across campus.
3. During the site observations and interviews, the majority of the site custodial person-
nel stated that they had sufficient supplies and equipment to perform the duties expect-
ed of them. This was verified in most cases.
4. After observing the classrooms, hallways, lunch areas, and bathrooms, even with the
proper supplies and equipment, cleanliness of the campuses was inconsistent across
the district. Some schools were spotless while others were in need of some deep clean-
ing.
Recommendations and Improvement Plan
1. Provide in-service training for all site personnel regarding the proper use of all clean-
ing supplies and equipment.
2. All site personnel responsible for the cleaning of the site should receive training at the
site for a complete understanding of what chemicals and equipment must be used to
maintain a clean and safe campus.
3. Supervisors should evaluate the proper use of the supplies and equipment on a regular
basis to verify that the site personnel are following the training given to them.
4. If the supervisors find misuse or noncompliance with the training given to the site
personnel, the Findings must be included in the employee’s evaluation.
112 Facilities Managment Facilities Managment 113
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
114 Facilities Managment Facilities Managment 115
0 1 2 3 4 5 6 7 8 9 10
8.9 Facilities Maintenance and Custodial—Implementation of a Preventive
Maintenance Program
Professional Standard
The district has an effective Preventive Maintenance Program. The district should have a written
Preventive Maintenance Program that is scheduled and followed by the maintenance staff. This
program should include verification of the completion of work by the supervisor of the mainte-
nance staff.
Sources and Documentation
1. Interview with Director of Facilities and Director of Maintenance
2. Site observation of actual program being implemented
Findings
1. The district has two maintenance crews. The day shift concentrates on routine work
orders while the night crew performs preventive maintenance. This provides less dis-
ruption to the classroom which is commendable.
2. While the primary responsibility for the preventive maintenance program is the night
shift, this shift also performs some of the routine maintenance work orders if they
cannot be completed during the day. This reduces the effectiveness of the preventive
maintenance program.
3. During the site observations, some portable classrooms had the HVAC units on, with
the doors open, causing an unnecessary strain on the units. This could result in the unit
requiring additional maintenance above the normal maintenance schedule.
Recommendations and Improvement Plan
1. Site administrators should be interviewed for their comments on the effectiveness
and timeliness of the repairs requested of the maintenance personnel using the mobile
maintenance shop.
2. The work orders assigned to the shop should be reviewed to verify that the work
requested has been completed to the satisfaction of the requestor and was finished in a
timely manner.
3. Positive or negative Findings should be included in the appropriate employee’s evalu-
ation and personnel folder.
4. Using the information contained in the maintenance requests, the district should de-
velop an annual report to the board and administration showing the progress made by
the Preventive Maintenance Program.
5. Long-range estimates of the financial needs of the program should be determined.
6. The projects in line for preventive maintenance in the coming years should be dis-
played.
114 Facilities Managment Facilities Managment 115
7. The preventive maintenance program should be made a part of every employee’s
workday.
8. Examples should be provided of how other district employees can help reduce emer-
gency repairs by following some simple steps like:
• Closing the windows and doors when the air conditioning is operating
• Turning off lights when they leave
• Turning down thermostats after hours
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
116 Facilities Managment Facilities Managment 117
0 1 2 3 4 5 6 7 8 9 10
8.10 Facilities Maintenance and Custodial—Adequate Repair and Supervision
of School Buildings
Professional Standard
Toilet facilities shall be adequate and maintained. All buildings and grounds are maintained. [CCR
Title §631]
Sources and Documentation
1. Board policy
2. Site observations verifying conditions of facilities
3. Interview with sampling of employees and supervisors
Findings
1. A current board policy for the adequate repair and maintenance of the schools was
not available. The board is currently updating many of the policies related to the bid
process.
2. The influx of locally approved bond funding, coupled with state funding, is providing
the district with funding to modernize and construct school facilities.
3. During the site visitations, both ends of the spectrum in plant conditions were noted.
While the district is spending millions on the construction of the new high school
wing, the grounds are in disrepair. Some of the older buildings are in need of an exte-
rior cleaning.
4. Also at the high school, while the bathrooms had a considerable amount of graffiti, all
the fixtures were in place and operable.
5. At the sites visited, all but one of the drinking fountains were in place and operable.
6. One school was in need of painting, but was not scheduled for painting this year,
while another school was receiving the final touches as a result of modernization fund-
ing. The other campuses spanned the spectrum, with some on the “needs-work” end of
the spectrum.
Recommendations and Improvement Plan
1. A board policy should be developed that clearly directs the district in the area of facili-
ties maintenance. This should include the areas the board sees as the highest priorities.
Once the policy is adopted, the board must provide adequate funding to implement the
policy.
2. Site administrators and the public should be updated regularly on the progress of the
work. Rather than a massive annual report, a simple summary of projects underway
and in the works can provide support for future needs.
3. The district should continue to implement an aggressive facilities recovery plan.
116 Facilities Managment Facilities Managment 117
4. School administrators should be informed of scheduled improvements, such as paint-
ing, so that they can in turn inform the public of the anticipated work.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
118 Facilities Managment Facilities Managment 119
0 1 2 3 4 5 6 7 8 9 10
8.11 Facilities Maintenance and Custodial—Implementation of a Planned
Program Maintenance System
Professional Standard
The district has implemented a planned program maintenance system. The district should have
a written planned program maintenance system that includes an inventory of all facilities and
equipment that will require maintenance and replacement. This program should include purchase
prices, anticipated life expectancies, anticipated replacement time lines, and budgetary resources
necessary to maintain the facilities.
Sources and Documentation
1. Interview with Director of Facilities and Director of Maintenance
Findings
1. The Governing Board does not have a board policy regarding planned program main-
tenance.
2. The planned program maintenance system is a part of the district’s facility master
plan.
3. The planned program maintenance system is still in the development stage.
Recommendations and Improvement Plan
1. A board policy should be developed that delineates the various aspects of the planned
program maintenance system.
2. The district should establish in the board policy a minimum funding level that the
district should budget annually to support the planned program maintenance system.
3. Priorities should be established for which maintenance projects receive first priority in
case of a financial crisis.
4. The district should establish a separate financial account for the planned program
maintenance system.
5. A database should be created in chronological order by date, showing when the repair
or replacement must occur.
6. The funding necessary to accomplish the repairs for the year should be established.
7. The district should place the projects on the calendar to determine whether contracting
may be necessary to accomplish all the maintenance projects.
8. The district should present the financial plan to the board and administration for inclu-
sion in the initial budget discussions for the coming year.
9. The district should designate where the funding will come from to accomplish the
maintenance requirements.
118 Facilities Managment Facilities Managment 119
Standard Implemented: Partially
July 1, 2003 Rating: 3
Implementation Scale
Not Fully
120 Facilities Managment Facilities Managment 121
0 1 2 3 4 5 6 7 8 9 10
8.12 Facilities Maintenance and Custodial—Priorities for assignment of
routine repair work orders
Professional Standard
The district has a documented process for assigning routine repair work orders on a priority
basis.
Sources and Documentation
1. Interview with Director of Facilities and Director of Maintenance
Findings
1. Work orders are submitted by the sites to the Maintenance Department via the net-
work.
2. The maintenance supervisors review the work orders and determine whether the prior-
ity submitted by the site is accurate.
3. All health and safety or emergency repairs are given top priority.
4. All other work orders are prioritized by the supervisors and distributed to the staff.
5. Any work orders that may be more than existing staff can handle are presented to the
Director of Maintenance to determine if the repair may need to be sent out to be com-
pleted by a private contractor.
6. If it is determined that a project is too large for current staff to handle, the bid/quote
process will be implemented.
7. The hesitancy of the Purchasing Department to implement the uniform cost account-
ing program is one of the roadblocks in performing the larger projects.
Recommendations and Improvement Plan
1. The district should continue the current work order prioritizing process.
2. The district should continue training site personnel and maintenance personnel on how
to use the computerized work order system.
3. Both the positive and negative comments received from the sites regarding the main-
tenance staff should be documented and included them in the employee evaluations.
4. Support from the administration should be received to implement the uniform cost ac-
counting program.
120 Facilities Managment Facilities Managment 121
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
122 Facilities Managment Facilities Managment 123
0 1 2 3 4 5 6 7 8 9 10
9.1 Instructional Program Issues—Plan for Attractive Landscaped Facilities
Professional Standard
The district has developed a plan for attractively landscaped facilities.
Sources and Documentation
1. Interviews with district staff
2. Review of district records
3. Inspection of district school sites
Findings
1. The district has developed a plan for landscape improvements within most of the
district’s recently bid construction projects. The district staff has acknowledged a link
between school site appearance and positive effects upon students’ desire and interest
to attend school.
2. The staff acknowledged that improved landscaping can have positive effects upon
staff and community morale and support for the school.
3. Any lack of commitment toward the development of a plan for attractively landscaped
plans appears to be solely based upon funding deficiencies, physical site limitations
and potential impacts upon district grounds staffing and its current ability to maintain
improved school sites/landscaping.
4. The staff generally displayed a positive attitude toward the development of a land-
scaping improvement plan, but has reiterated the staffing deficiencies that currently
exist within the Grounds Department.
Recommendations and Improvement Steps
1. The district should consider developing a plan to continue to improve the landscaping
at the individual district facilities in consideration of staffing realities that exist within
the district’s Grounds Department.
2. An inventory/assessment should be conducted to determine the actual landscaping
conditions that exist within individual district sites.
3. The district should develop standards of landscaping that are desired at various types
of schools (elementary, junior high, high school, special program sites, etc.).
4. The district should measure the Findings of the inventory/assessment with the stan-
dards developed to put together a determination of needs and deficiencies.
5. The district should develop a broad-based set of potential funding sources to assist in
the implementation of a district landscaping plan.
122 Facilities Managment Facilities Managment 123
6. A plan should be developed to correct any landscaping needs and deficiencies that
exist within respective district school sites. A fiscal impact associated with the im-
plementation of this plan needs to be developed and considered within the broader
context of facilities-related needs, as well as in consideration of potential additional
staffing requirements within the Grounds Department.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
124 Facilities Managment Facilities Managment 125
0 1 2 3 4 5 6 7 8 9 10
9.2 Instructional Program Issues—districtwide Technology Plan to Benefit
all Sites
Professional Standard
The goals and objectives of the technology plan should be clearly defined. The plan should
include both the administrative and instructional technology systems. There should be a
summary of the costs of each objective and a financing plan should be in place.
Sources and Documentation
1. District technology plan
2. District technology financial plan
3. District policies and administrative regulations
Findings
1. Technology Plan: The district has a districtwide plan for implementation of instruc-
tional technology. The parts of the plan dealing with staff development, teaching and
learning, network infrastructure, and classroom hardware and software are well done.
The plan addresses networking standards and site-level student information as well
as acceptable use policies for both employees and students. The plan also addresses
equal access issues and availability of appropriate technology at each school site.
2. Tracking and Reporting Progress: Major goals are well defined, and the plan includes
milestones to provide tracking and reporting of progress. The plan for 2002-2005 was
recently approved by the board of education to ensure compliance with goals for the
Federal No Child Left Behind program. It is anticipated that there will be annual up-
dates and progress reports, but at the time of FCMAT’s review, the plan adoption was
recent enough that none had been performed.
3. Financing Plan: The district did not have a complete financing plan listing specific
funding streams for implementation of technology. The district, because of its fi-
nancial condition, is unable to invest significant general fund resources in technol-
ogy. Most of the funding for past purchases and for repair and maintenance has been
provided by a parcel tax. Within the technology plan, tables suggest funding sources
that individual departments and schools might investigate for use in implementing the
plan.
4. Staffing Considerations: The district relies on a very small staffing augmentation in
the central office to lead its technology planning, operation, and execution. Planned
addition of a Technology Director has, necessarily, been delayed due to the district’s
financial condition. As a result, the technology area is not organized or led in the man-
ner anticipated by the technology plan.
Recommendations and Improvement Plan
1. The district will need to actively manage the technology planning process if progress
is to be made. The district should develop a formal tracking system, separate from
plan revisions, to assess progress toward major goals. The results should be reported
and the goals should be revised periodically, at least annually.
124 Facilities Managment Facilities Managment 125
2. In order to implement the instructional technology plan, the district should identify
sources of revenue that are reasonably certain, sufficient to meet plan goals, and which
are committed to this purpose. A formal financing plan should be adopted. The financ-
ing plan should include total dollars required, when the district will need funds, sourc-
es of funding, and cash flow projections supporting the availability of funding. During
the budget development each year, the board should consider the need for financing
the plan and make an appropriate decision as to the level of funding. Expectations for
implementation should be adjusted accordingly.
3. The technology plan carries substantial policy implications for the district. It specifies
policies for student access to technology, establishment of new positions, duties of
those positions, commitments of staff development time, and specific learning out-
comes, among other things. These are major policy questions that should be consid-
ered before they automatically become effective with adoption of the district technol-
ogy plan.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
126 Facilities Managment Facilities Managment 127
0 1 2 3 4 5 6 7 8 9 10
9.3 Instructional Program Issues—Lunch Areas are Warm, Healthful and Safe
Professional Standard
The Governing Board shall provide a warm, healthful place in which children who bring their
own lunches to school may eat their lunch. [EC 17573, CCR Title 5 §14030]
Sources and Documentation
1. On-site observation of cafeterias, lunch areas, and multipurpose rooms
2. Discussions with site staffs
3. Discussions with maintenance/operations staff
Findings
1. The comfort level of lunch areas was inconsistent. Most schools had adequate, warm
areas, however, some schools lacked adequate HVAC for the lunch area.
2. Most cafeterias and multi-purpose rooms did not have appropriate capacity signage.
3. Some lighting levels were low due to old light fixtures.
4. Eating areas were generally clean, however some facilities were very old, which made
it difficult to be perceived as appropriately clean.
Recommendations and Improvement Plan
1. In addition to Education Code 17573, all facilities plans should conform to state stan-
dards as specified in the Code of Regulations, Title 5, Section 14030. These standards
are briefly and partially summarized below:
• Auxiliary areas such as multipurpose cafeterias, administrative offices and
library/media centers shall be adequately sized to accommodate the student
population, and allow adaptation for changing uses.
• Lighting shall be designed to provide comfortable and adequate levels of il-
lumination.
• Delivery and service areas shall be located so as to provide vehicle access
without jeopardizing the safety of students and staff.
2. Plans shall also comply with the Americans with Disabilities Act and its regulations
that require that facilities be designed and constructed so that they are readily acces-
sible to and usable by individuals with disabilities. (42 USC 12101 – 12213, 28 CFR
35).
3. The district must complete the gradual replacement and upgrade of aged cafeteria
facilities as funds become available through modernization projects, deferred mainte-
nance, or other miscellaneous funds.
4. Maintenance/custodial/cafeteria staff should continue to be trained on the general
industry cleaning and safety orders.
126 Facilities Managment Facilities Managment 127
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
128 Facilities Managment Facilities Managment 129
0 1 2 3 4 5 6 7 8 9 10
9.4 Instructional Program Issues—Bathroom Facilities are Clean and
Operable
Professional Standard
The Governing Board of every school district shall provide clean and operable flush toilets for
the use of pupils. [EC 17576, CCR Title 5 §14030]
Sources and Documentation
1. On-site observation of student restrooms
2. Discussions with site staffs
3. Discussions with maintenance/operations staff
Findings
1. Nearly all district fixtures were in working order.
2. Some restrooms need to be upgraded (primarily due to handicapped accessibility and
age of the structure).
3. Some restrooms in modernized schools were not upgraded and still had old tile with
“restroom smells” embedded in the grout. Even when clean, these restrooms did not
seem clean.
4. Some restrooms had been closed and converted to storage.
Recommendations and Improvement Plan
1. Restrooms should be sufficient to accommodate the maximum planned enrollment and
located on campus to allow for supervision.
2. The district must complete the gradual replacement and upgrade of aged restroom
facilities as funds become available through modernization, deferred maintenance, or
other miscellaneous sources.
3. Maintenance/custodial staff should continue to be trained on the general industry
cleaning and safety orders.
4. Sanitary measures should be enforced, buildings should be regularly cleaned, and mi-
nor repairs completed, in order to prevent infestations, and eliminate potential health
and safety issues.
5. The district should evaluate custodial staffing ratios to ensure that enough staff is
available to provide clean and safe restrooms.
6. Future site improvement and new construction plans must comply with the Americans
with Disabilities Act and its implementing regulations which require that facilities be
designed and constructed so that they are readily accessible to and usable by individu-
als with disabilities. (42 USC 12101 - 12213, 28 CFR 35)
128 Facilities Managment Facilities Managment 129
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
130 Facilities Managment Facilities Managment 131
0 1 2 3 4 5 6 7 8 9 10
9.5 Instructional Program Issues—Facility Plans Include Space for Extended
Day Programs
Professional Standard
The district has plans for the provision of extended day programs within its respective school
sites. [EC 17264]
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with district staff
3. Review of district records
Findings
1. The district maintains extended day/child development programs at selected existing
school sites. These programs appear to be utilized by the students and are a definite
benefit as a supplemental program service for school sites.
2. While these types of programs are not currently available at all district elementary
school sites, it is believed that the district has done a partially effective job in develop-
ing opportunities for families to have access to these types of programs within subre-
gions of the district’s boundaries.
Recommendations and Improvement Plan
1. While no improvement plan steps appear to be required at this time, it is strongly
suggested that the district continue to investigate ways to broaden the implementation
of its extended day/child development programs as the benefits for additional student
participation appear to be significant.
Standard Implemented: Partially
July 1, 2003 Rating: 5
Implementation Scale
Not Fully
130 Facilities Managment Facilities Managment 131
0 1 2 3 4 5 6 7 8 9 10
9.6 Instructional Program Issues—Plan to Maintain Equality/Equity of
District Facilities
Professional Standard
The district has developed and maintains a plan to ensure equality and equity of its facilities
throughout the district. [EC 35293]
Sources and Documentation
1. Interviews with district staff
2. Review of district records
3. Meetings with selected community representatives
4. Inspection of district school sites
Findings
1. There is a fairly consistent level of equality and equity for the facilities provided
throughout the district, although there are definitely varying socioeconomic levels
that exist within the district and likely affect the makeup of respective school student
populations.
2. It appears that there have been concerted efforts to provide facility improvements at
schools within the four quadrants of the district and, hence, to avoid favoritism for
any schools located within any given geographic region. Nonetheless, future facility
improvements at selected sites are still required in order to further improve the equal-
ity and equity of facilities.
Recommendations and Improvement Plan
1. More clearly identified and understood district-level standards need to be developed
with respect to the numbers and quality of facilities required in order to accommodate
the delivery of instruction to students. However, it is believed that activities are begin-
ning to occur in this area.
2. Specific facility discrepancies that exist at respective sites need to be identified, and
costs estimated. This type of information will continue to form the basis for future
development and refinement of the district’s facilities master plan.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
132 Facilities Managment Facilities Managment 133
0 1 2 3 4 5 6 7 8 9 10
9.7 Instructional Program Issues—Adequate Heating and Ventilation Exists
in all Schools
Professional Standard
All schools shall have adequate heating and ventilation
Sources and Documentation
1. School sites observations to assess the condition of the facilities, including heating and venti-
lation systems
2. Discussions with site staffs
3. Discussions with maintenance/operations staff
Findings
1. Most facilities appeared to have operational heating and ventilating systems (HVAC).
2. Due to age, many systems need to be upgraded.
3. Some instances of uneven heating and cooling were observed.
Recommendations and Improvement Plan
1. As modernization funds become available, the district should upgrade all HVAC sys-
tems.
2. The district should ensure that central energy management systems are operations.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
132 Facilities Managment Facilities Managment 133
0 1 2 3 4 5 6 7 8 9 10
9.8 Instructional Program Issues—Adequate Lighting and Electrical Service
is Provided
Professional Standard
All schools shall have adequate lighting and electrical service.
Sources and Documentation
1. School site inspections to assess the condition of the facilities including lighting and electrical
systems
2. Discussions with site staff
3. Discussions with maintenance/operations staff
Findings
1. School sites appeared to have adequate power and lighting.
2. Some lighting still needs to be upgraded for better lighting and energy efficiency.
Recommendations and Improvement Plan
1. As modernization funds are available, the district should increase electrical capacity
as necessary for each site.
2. As modernization funds are available, the district should upgrade lighting.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
134 Facilities Managment Facilities Managment 135
0 1 2 3 4 5 6 7 8 9 10
9.9 Instructional Program Issues—Classrooms are Free of Noise and Other
Barriers to Instruction
Professional Standard
Classrooms are free of noise and other barriers to instruction. [EC 32212]
Sources and Documentation
1. Board policy
2. Observation of classrooms
3. Interviews with district Staff
Findings
1. Board policies were not provided.
2. At the sites visited, classrooms were generally free of noise and other barriers to in-
struction.
Recommendations and Improvement Plan
1. The district should adopt a policy concerning Education Code 32212, which expresses
the Legislature’s intent that all Governing Boards formally address the problem of
classroom interruptions and adopt a policy to control them.
2. During any construction, the use of the site by contractors should be limited as fol-
lows:
• The contractor shall confine operations at the site to areas permitted by law,
ordinances, permits and the contract documents, and shall not unreasonably
encumber the site with materials or equipment.
• Notwithstanding the designation of contract limits or the indication of tempo-
rary fences or barricades, the provisions of the contract documents governing
certain portions or phases of the work may require that certain operations be
carried out beyond such designated limits.
• Pumping, draining and control of the designated site shall be carried out so as
to avoid endangering the work or any adjacent facility or property, or inter-
rupting, restricting or otherwise infringing or interfering with the districts use.
• The contractor shall keep the premises and surrounding areas free from accu-
mulation of waste materials.
• Consider specifying work hours that do not coincide with school hours.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 9
Implementation Scale
Not Fully
134 Facilities Managment Facilities Managment 135
0 1 2 3 4 5 6 7 8 9 10
9.10 Instructional Program Issues—Environment Conducive to High Quality
Teaching Learning
Professional Standard
The learning environments provided within respective school sites within the
district are conducive to high quality teaching and learning.
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with district staff
3. Interviews with district parents/community members
Findings
1. Learning environments, as currently provided within respective district school sites,
are generally conducive to high quality teaching by the instructional staff and efficient
learning by students. Significant facilities improvement efforts are in place or have
been made in large part because of voter support for recent facilities improvement
bonds. While additional improvements are required, there is evidence of a systematic
plan to address these needs over time.
Recommendations and Improvement Plan
1. Student learning and the delivery of quality instructional programs must form the
basis of any determination for modifications to existing facilities and the development
of new facilities, as future facility planning occurs within the district.
2. A commitment should be made toward the identification and articulation of district
standards for student learning and for suggested methods for delivery of instruction.
This commitment should form the basis for all deliberations and decisions regarding
modifications to existing facilities and the development of new facilities.
3. Instructional staff should be included as an integral and participating member of all
facilities planning efforts which lead to the development of plans for modifications
and/or additions to existing facilities and for any potential new school sites. It is sug-
gested that student representation be included within planning committees for second-
ary school facility projects.
4. The district should continue to foster the strong link between the planned expenditure
of capital facilities funds and the improvement of learning environments provided for
students and the staff. The delivery of high-quality instruction must be the overriding
concern when capital facility expenditure plans are being developed.
136 Facilities Managment Facilities Managment 137
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
136 Facilities Managment Facilities Managment 137
0 1 2 3 4 5 6 7 8 9 10
9.11 Instructional Program Issues—Facilities Reflect Community Standards
and Expectations
Professional Standard
Facilities within the district reflect the standards and expectations established by the community.
Sources and Documentation
1. Inspection of district facilities
2. Interviews with district staff
3. Interviews with district parents/community members
Findings
1. It is extremely difficult to assess the degree to which facilities reflect the standards and
expectations established by the entire community, primarily due to the fact that the
district is comprised of several distinct geographic/political areas. It is quite apparent,
however, that public education is important in Berkeley. The district and its residents
should be strongly commended for their support of multiple facility and educational
program improvement tax elections. These successful efforts should be viewed as
votes of confidence by the district’s constituency and support for ongoing improve-
ment within Berkeley’s public schools.
Recommendations and Improvement Plan
1. The district should continue to strengthen the connection between the facilities im-
provement plans and the standards and expectations established by the board for its
instructional programs and expected outcomes for students. A better understanding of
community standards and expectations for all district facilities should be developed to
enable the district to identify and quantify discrepancies that continue to exist between
existing and desired conditions.
Standard Implemented: Partially
July 1, 2003 Rating: 7
Implementation Scale
Not Fully
138 Facilities Managment Facilities Managment 139
0 1 2 3 4 5 6 7 8 9 10
7
10.1 Community Use of Facilities—Plan to Promote Community Involvement
in Schools
Professional Standard
The district should have a plan to promote community involvement in schools.
Sources and Documentation
1. Adopted district governing board policies
2. district civic center policy
3. district civic center implementation procedures
4. Site utilization records
5. district newsletters, press releases, community forum summary reports
Findings
Policy on use of facilities
1. The district actively promotes community use of facilities. Procedures, pricing and
implementation clearly favor such activity. The Superintendent and staff members
have aggressively marketed the need for improvement in district facilities. These ef-
forts culminated in passage of a local school bond and in unusually strong community
and political support for the district. The activity level directed toward community
involvement in facilities continues even after passage of the bond.
2. The civic center procedures/application/rules and regulations for community use of fa-
cilities foster such use. The policy is clear, easy to comprehend, and complete. A sum-
mary was available and helpful in guiding members of the public through the process.
3. The board had not adopted a formal policy on community use of facilities at the time
of FCMAT’s review.
4. The one-page application for use of facilities is usually initiated at the school site,
with district-level approval. The form itself is very comprehensive and complete, but
was still easy to use.
5. The district’s civic center program is well utilized by the community. Records reflect
that many community groups regularly access the district’s facilities. The participating
groups range from school-related groups to church groups, and youth athletic leagues.
Periods of use range from less than two hours to long-term use for weeks, months, or
even longer.
6. The district has in the past budgeted resources to provide these services, instituting
fees to cover supervision after school hours. Traditionally, the fees charged have been
much lower than actual allowable costs would justify. The district recently revised its
fee structure to a higher and more appropriate level.
7. Staffing for issuance of permits has been reduced, and the function has been trans-
ferred from the Business Department to the Facilities Department with no correspond-
ing transfer of staff. The staffing level provided for this function has declined from
two FTE to zero.
138 Facilities Managment Facilities Managment 139
Recommendations and Improvement Plan
1. The board should adopt a formal policy regarding the community use of district facili-
ties.
2. Application processing is labor intensive, time consuming and requires a person with
good interpersonal skills to interact with the public. Appropriate staffing should be
provided, and the cost of administration should be included in determining of allow-
able costs.
3. The district should consider making the civic-center application form available in
languages other than English.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
140 Facilities Managment Facilities Managment 141
0 1 2 3 4 5 6 7 8 9 10
10.2 Community Use of Facilities—Compliance with Civic Center Act for
Community Use
Professional Standard
Education Code Section 38130 establishes terms and conditions of school facility use by
community organizations, in the process requiring establishment of both “direct cost” and “fair
market” rental rates, specifying what groups have which priorities and fee schedules.
Sources and Documentation
1. District board policy
2. Internal accounting records
3. Policy and procedures for renting school district property
4. Facilities use permit
Findings
1. Implementation of the Civic Center Act: The district implementation of its civic center
obligations is adequate and unquestionably within the spirit and letter of the Education
Code. Distinction is appropriately made between types of groups (nonprofit vs. for
profit, school/youth vs. other, church association) and the appropriate fee schedules
(free, direct cost, fair market) are applied. A distinction is also made between occa-
sional short-term use and longer-term more permanent use.
2. Fee Schedules: Fee schedules have been extraordinarily low and are not supported
by current calculations of actual expense. The fees to be charged have recently been
revised to increase them to levels more reflective of actual costs incurred. The study
required by the Civic Center Act to justify fees had recently been completed and the
increases are justified by the study.
3. Rates Charged: The rates charge for both “direct cost” and “fair market”, which had
fallen far below established practical norms, have recently been increased. This means
that the general fund, which had been subsidizing public use of facilities by incurring
an encroachment due to community participation, should be made whole from in-
creased fees. Requests for waiver of charges are reviewed and approved by the Direc-
tor of Facilities.
4. School Site Involvement: School sites are contacted prior to finalization of facility use
permits to avoid schedule conflicts with school activities. Schools have veto power
over use of their facilities. Additionally, school related free use is now coordinated
primarily at the school site.
Recommendations and Improvement Plan
1. The district should prepare a comprehensive study of allowable costs and charges for
community use of facilities. The results of the study should be presented to the board
of education for discussion and adoption.
140 Facilities Managment Facilities Managment 141
2. The district should also consider raising rates periodically to accurately reflect current
costs of providing custodial services, utilities, and other services and to avoid a cycle
of encroachments followed by large increases.
3. Members of the public must make at least three and often more stops to secure a per-
mit to use district facilities. The district should streamline this process by initiating a
one-stop procedure for the user.
4. School sites should be given clear guidance as to when it is appropriate and legal for
them to veto community use of site facilities.
Standard Implemented: Partially
July 1, 2003 Rating: 6
Implementation Scale
Not Fully
142 Facilities Managment Facilities Managment 143
0 1 2 3 4 5 6 7 8 9 10
10.3 Community Use of Facilities—Maintenance of Records and Cash Con-
trols on Civic Center Funds
Professional Standard
The district should maintain comprehensive record and controls on civic center implementation
and cash management.
Sources and Documentation
1. District board policy
2. Internal accounting records
3. Policy and procedures for renting school district property
4. Facility use permit
Findings
1. Internal Control: Internal control problems are both numerous and serious.
• Permit forms are not prenumbered and there is no control on their use.
• Applications, invoices and payments are all handled by the same person; a
major breach of internal control.
• Checks are stored in a closet in the facilities area and are not remitted to ac-
counting promptly.
• Invoices are prepared after the fact and are not sent out promptly.
• The work area is inappropriate for storage of checks and sensitive documents.
• The employee involved had several other jobs and was not given time or train-
ing to do this one.
2. Handling of Payments: Payments, once remitted to accounting, appear to be handled
properly, however, until that point there is no control at all.
3. Records of Use and Charges: Site-by-site records are maintained of each facility use
permit. The records are, however, maintained by the same person who issues permits,
prepares invoices and receives payments.
4. Checkpoints at each step to ensure compliance for such crucial items as insurance
documents, which are appropriately prepared and filed.
Recommendations and Improvement Plan
1. The request and supporting documentation should be sent to a designated district of-
fice, where permits are approved and issued.
2. Invoices should be prepared and mailed by members of the accounting department.
3. Remittances, primarily checks, should be received and deposited by a different mem-
ber of the accounting department staff.
4. Payments should not be made directly to the same individual who either approves
permits or is responsible for billing the charges.
142 Facilities Managment Facilities Managment 143
5. The district should use prenumbered forms and activity logs to provide adequate
transaction history and to improve internal control.
6. The district should consider requiring payment in advance for facility use permits in
cases where costs are more predictable. This would eliminate the need for invoicing,
receiving and handling checks, and follow-up on late payments.
7. The district should recognize the opportunities this program presents for fraud and
abuse and provide additional oversight, staffing and safeguards accordingly.
8. The district should request that its independent auditors address the internal controls
in this area in each year’s annual audit.
Standard Implemented: Not
July 1, 2003 Rating: 0
Implementation Scale
Not Fully
144 Facilities Managment Facilities Managment 145
0 1 2 3 4 5 6 7 8 9 10
11.1 Communication—Communication of Facility Status Quo and Needs
Professional Standard
The districtʼs public information office should coordinate a full appraisal to students, staff, and
community of the condition of the districtʼs facilities.
Sources and Documentation
1. Staff bulletins
2. District website
3. Press release files
4. Distribution lists
5. Newsletters
6. Newspaper clip files
7. Radio and television new scripts
8. Public forum MS PowerPoint files
Findings
1. The district has, as a part of its recent bond and parcel tax campaigns, established an
effective public relations program, complete with internal and external district news-
letters, an active press release component, and regularly scheduled public forums. The
publications are distributed in English, but not in other languages. In all of these ef-
forts, the facilities situation is given high priority, second only to student achievement.
2. At the present time, the district is not actively engaged in a bond election, and the
level of effort directed toward public information is lower.
3. The district Web site is effectively used to communicate with the public. It was well
designed and had a wealth of information available.
4. There is evidence that the communications efforts have been successful in reaching
community members. Local bond campaign results can be viewed as the test of com-
munity support for school facilities. When judged by this standard, Berkeley Unified
has been quite successful, as evidenced by the earning of voter approval for both gen-
eral obligation bond and parcel tax elections.
5. Additionally, Berkeley Unified has two oversight committees that meet regularly and
are in support of rigorous standards and accountability for use of bond, maintenance
and facilities funding.
6. School site meetings, as well as board meetings are also used as an effective vehicle
for communicating facility condition and needs.
Recommendations and Improvement Plan
1. The district should consider producing at least some of its facilities related publica-
tions in a language other than English.
144 Facilities Managment Facilities Managment 145
2. Most of the facilities related publicity material team members observed was generated
and distributed by the Facilities Department. The district should consider other means
of distribution as well, for example as part of an overall districtwide publicity effort,
especially during sensitive elections.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
146 Facilities Managment Facilities Managment 147
0 1 2 3 4 5 6 7 8 9 10
11.2 Communication—Communication of Activities to Rectify Substandard
Conditions
Professional Standard
The district should apprise students, staff, and community of efforts to rectify and substandard
conditions.
Sources and Documentation
1. Staff bulletins
2. Press release files
3. Distribution lists
4. Newsletters
5. Newspaper clip files
6. Radio and television news scripts
7. Public forum MS PowerPoint files
Findings
1. Communication with the Public: Communication of facility needs was very good. The
program used for informing the bond committee and other members of the community
of facility plans, needs, and progress was also very good.
2. Dissemination of Information: The district facilities construction plan is comprehen-
sive and well done. This plan is the primary vehicle for keeping the board and the
public aware of progress on facilities issues. During bond campaigns, various publica-
tions featured articles on the school bond, new projects begun under Measures A and
AA, and the status of the school renovation program. The district did not have copies
of the plan readily available to provide to the public.
3. Broad Target Audience: At this time, the primary vehicle for dissemination of facili-
ties information is the district facilities construction plan. The latest plan issued in
March, 2003, includes an annual review and update cycle. The information provided
has both a districtwide and an area focus, dealing with projects in particular areas of
the district. While parents and community members tend toward parochial ownership
of their local schools alone, the district’s efforts to provide balance in project approv-
als is warranted.
Recommendations and Improvement Plan
1. The district facilities construction plan is a good informational tool; it should be read-
ily available for access by the public. This plan should be made available through the
district Web site to avoid printing and storage costs.
2. The district should continue districtwide and site-by-site releases with site-specific
detail for distribution by individual sites. This would continue to respond well to
neighborhood/area interests in individual sites, and foster central office accountability.
146 Facilities Managment Facilities Managment 147
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
148 Facilities Managment Facilities Managment 149
0 1 2 3 4 5 6 7 8 9 10
11.3 Communication—Communication of district Standards and Plans
Professional Standard
The district should provide clear and comprehensive communication to staff of its standards and
plans.
Sources and Documentation
1. Facilities construction plan
2. Interoffice memoranda
3. Department of Facilities and Operations memoranda
4. District department goals and objectives
5. Materials provided to the Measure A and AA bond oversight committee
6. Staff interviews
Findings
1. Facility Standards: In some areas, the district facilities department has actively up-
graded or implemented entirely new facilities standards. These standards are clearly
expressed in the district facilities construction plan. Additionally, the district Web site
includes considerable information related to facilities.
2. Long-Range Planning: Continual review of needs and a comprehensive assessment of
long-range facility needs have put the district in a good position to communicate its
standards and condition. The district has a good array of facilities planning documents
and has taken care to present them to stakeholders groups such the Citizen’s Bond
Oversight Committee.
3. Communication of Plans and Standards: Standards are more meaningful when publi-
cized and acted upon, therefore, continued efforts at communication will be needed.
4. The district devotes its efforts to conducting and then communicating the planning
process to interested stakeholders. The Citizen’s Bond Oversight Committee packages
were excellent.
Recommendations and Improvement Plan
1. The district facilities construction plan is a very good informational tool. The district
should make this plan available through the district Web site to avoid printing and
storage costs.
2. The standards and plans are incorporated into one document. This promotes ease of
use, but site-level staff needs to be apprised in greater detail of all facilities standards
and plans in order to both expedite the projects and provide accountability as to re-
sults.
148 Facilities Managment Facilities Managment 149
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
150 Facilities Managment Facilities Managment 151
0 1 2 3 4 5 6 7 8 9 10
11.4 Communication—Meaningful Involvement of All Stakeholder Groups
Professional Standard
All stakeholder groups should be directly involved in a meaningful manner regarding the
districtʼs facilities.
Sources and Documentation
1. Facilities construction plan
2. School safety committee minutes
3. Measure A and AA oversight committee presentations
4. Community forum presentations
5. Staff interviews
Findings
1. Community Input: The district aggressively solicits community input regarding its
facilities. The district supports an official and active facilities advisory committee, the
Measure A Citizen’s Bond Oversight Committee, which advises on all facility matters.
The staff meets often with community members. Facilities remain an issue of crucial
importance to the community, and the community’s concerns are relayed back to the
district office.
2. Projects Lists: A project priority list for each school provides a basis for the bond
expenditures. The general obligation bond results indicate that the district-community
relationship is instilling confidence in the district’s capability to manage its capital
plant. Passage of the bond is a major vote of confidence for the district.
Recommendations and Improvement Plan
1. The active solicitation of community input regarding facilities may be in response to a
crisis, but these efforts should remain in place once the crisis is over. Maintenance of
community confidence and support is an ongoing pursuit.
Standard Implemented: Fully - Substantially
July 1, 2003 Rating: 8
Implementation Scale
Not Fully
150 Facilities Managment Facilities Managment 151
0 1 2 3 4 5 6 7 8 9 10
152 Facilities Managment Facilities Managment 153
Chart of
Facilities Management Standards
Progress Ratings Toward Implementation of the Improvement Plan
152 Facilities Managment Facilities Managment 153
154 Facilities Managment Facilities Managment 155
Facilities Management
July Focus for
Standard to be addressed 2003 January
rating 2004
1.1 All school administrators should be thoroughly familiar with the
California Department of Education, Civil Defense and Disaster Plan-
ning Guide for School Officials, 1972. [EC 32000-32004, 32040, 2
35295-35297, 38132, 46390-46392, 49505, GC 3100, 8607, CCR Title
5 §550, 560, Title 19 §2400]
1.2 The district includes the appropriate security devices in the design of
new buildings as well as in modernized buildings. [EC 32020, 32211, 6
35294-35294.9, 39670-39675]
1.3 The district should be able to demonstrate that a plan of security has
been developed, which includes adequate measures of safety and pro- 2 ❑
tection of people and property. [EC 32020, 32211, 35294-35294.9]
1.4 The district should ensure that the custodial and maintenance staff
are regularly informed of restrictions pertaining to the storage and
disposal of flammable or toxic materials. [EC 49341, 49401.5, 49411, 2 ❑
F&AC 12981, H&SC 25163, 25500-25520, LC 6360-6363, CCR Title 8
§5194]
1.5 The district has a documented process for issuing of master and sub-
master keys. A districtwide standardized process for the issuance of 4
keys to employees must be followed by all district administrators.
1.6 Bus loading and unloading areas, delivery areas, and parking and
parent loading/unloading areas are monitored on a regular basis to
ensure the safety of the students, staff and community. Students, em- 3 ❑
ployees and the public should feel safe at all times on school prem-
ises.
1.7 Outside lighting is properly placed and monitored on a regular basis
to ensure the operability/adequacy of such lighting and to ensure
safety while activities are in progress in the evening hours. Outside
lighting should provide sufficient illumination to allow for the safe 4
passage of students and the public during after-hours activities.
Lighting should also provide security personnel with sufficient illumi-
nation to observe any illegal activities on campus.
1.8 The district has a graffiti and vandalism abatement plan. The district
should have a written graffiti and abatement plan that is followed by
5
all district employees. The district provides district employees with
sufficient resources to meet the requirements of the abatement plan.
1.9 Each public agency is required to have on file written plans describ-
ing procedures to be employed in case of emergency. [EC 32000-
2
32004, 32040, 35295-35297, 38132, 46390-46392, 49505, GC 3100,
8607] [CCR Title 8, §3220]
154 Facilities Managment Facilities Managment 155
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
1.10 Each elementary and intermediate school at least once a month, and
in each secondary school not less than twice every school year, shall 3
conduct a fire drill. [EC 32000-32004, 32040, CCR Title 5 §550]
1.11 Maintenance/custodial personnel have knowledge of chemical com-
pounds used in school programs that include the potential hazards
2
and shelf life. [EC 49341, 49401.5, 49411, F&AC 12981, H&SC 25163,
25500-25520, LC 6360-6363, CCR Title 8 §5194]
1.12 Building examinations are performed, and required actions are taken
by the Governing Board upon report of unsafe conditions. [EC 17367] 6
1.13 Each school which is entirely enclosed by a fence or partial buildings
must have a gate of sufficient size to permit the entrance of ambu-
10
lances, police and fire fighting equipment. Locking devices shall be
designed to permit ready entrance.
1.14 Sanitary, neat and clean conditions of the school premises exist and
the premises are free from conditions that would create a fire hazard. 3
[CCR Title 5 §633]
1.15 The Injury and Illness Prevention Program (IIPP) requires periodic
inspections of facilities to identify conditions. [CCR Title 8 §3203] 2
1.16 Appropriate fire extinguishers exist in each building and current in-
spection information is available. [CCR Title 8 §1922(a)] 3
1.17 All exits are free of obstructions. [CCR Title 8 §3219]
9
1.18 A comprehensive school safety plan exists for the prevention of cam-
pus crime and violence. [EC 35294-35294.9] 3
1.19 Each public agency is required to have on file written plans describ-
ing procedures to be employed in case of emergency. [EC 32000-
3
32004, 32040, 35295-35297, 38132, 46390-46392, 49505, GC 3100,
8607] [CCR Title 8, §3220]
1.20 Requirements are followed pertaining to underground storage tanks.
[H&SC 25292, CCR Title 26 §477, Title 23 § 2610] 10
1.21 All asbestos inspection and asbestos work completed in the US is
performed by Asbestos Hazard Emergency Response Act (AHERA) ac- 2 ❑
credited individuals. [EC 49410.5, 40 CFR Part 763]
156 Facilities Managment Facilities Managment 157
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
1.22 All playground equipment meets safety code regulations and is in-
spected in a timely fashion as to ensure the safety of the students.
10
[EC 44807, GC 810-996.6, H&SC 24450 Chapter 4.5, 115725-115750,
PRC 5411, CCR Title 5 §5552]
1.23 Safe work practices exist with regard to boiler and fired pressure ves-
sels. [CCR Title 8 §782] 3 ❑
1.24 Materials Safety Data Sheets are maintained. [EC 49341, 49401.5,
49411, F&AC 12981, LC 6360-6363, CCR Title 8 §5194] 2
1.25 The district maintains a comprehensive employee safety program. Em-
ployees are made aware of the district safety program and the district
0 ❑
provides in-service training to employees on the requirements of the
safety program.
1.26 The district conducts periodic safety training for employees. District
employees should receive periodic training on the safety procedures 0
of the district.
1.27 The district should conduct periodic first aid training for employees
assigned to school sites. 0
2.1 The district should have a long-range school facilities master plan.
0 ❑
2.2 The district should possess a California State Department of Education
Facilities Planning and Construction Guide (dated 1991). 10
2.3 The district should seek state and local funds.
5
2.4 The district is in the process of finalizing a Citizens Oversight Com-
mittee to ensure the appropriateness of expenditures related to the
recent passage of the district’s local school bond measure (Measure 9
M). In essence, this committee will function as an advisory/facility
planning type of committee.
2.5 The district should have a properly staffed and funded facility plan-
ning department. 5
2.6 The district should develop and implement an annual capital planning
budget. 10
156 Facilities Managment Facilities Managment 157
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
2.7 The district should have standards for real property acquisition and
disposal. [EC 39006, 17230-17233] 5
2.8 The district seeks and obtains waivers from the State Allocation
Board for continued use of its nonconforming facilities. [EC 17284, 2
17285]
2.9 The district has established and utilizes a selection process for the
selection of licensed architectural/engineering services. [GC 17302] 9
2.10 The district should assess its local bonding capacity. [EC 15100]
10
2.11 The district should develop a process to determine debt capacity.
10
2.12 The district should be aware of and monitor the assessed valuation of
taxable property within its boundaries. 10
2.13 The district should monitor its legal bonding limits. [EC 15100,
15330] 10
2.14 The district should collect statutory school fees. [EC 17620, GC
65995, 66000] 0
2.15 The district should consider developing an asset management plan.
2
2.16 The district has pursued state funding for joint-use projects through
the filing of applications through the Office of Public School Con- 7
struction and the State Allocation Board.
2.17 The district has established and utilizes an organized methodology of
prioritizing and scheduling projects. 8
2.18 The district complies with California Department of Education (CDE)
recommendations relative to school site sizing. 0
2.19 The district should distribute facility funding in an equitable manner
to all communities served and to all school levels. 10
158 Facilities Managment Facilities Managment 159
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
3.1 The district has a restricted deferred maintenance fund and those
funds are expended for maintenance purposes only. The deferred
maintenance fund should be a stand-alone fund reflecting the rev- 7
enues and expenses for the major maintenance projects accomplished
during the year.
3.2 The district has pursued state funding for deferred maintenance -
critical hardship needs by filing an application(s) through the Office
0
of Public School Construction and the State Allocation Board. [State
Allocation Board Regulation §1866]
3.3 The district applies to the State Allocation Board for facilities fund-
ing for all applicable projects. 8
3.4 The district consistently reviews and monitors its eligibility for state
funding so as to capitalize upon maximal funding opportunities. 7
3.5 The district establishes and implements interim housing plans for use
during the construction phase of modernization projects and/or addi- 8
tions to existing facilities.
3.6 The district has established and maintains a system for tracking the
progress of individual projects. 4 ❑
3.7 Furniture and equipment items are routinely included within the
scope of modernization projects. 8
3.8 The district obtains approval of plans and specifications from the Di-
vision of the State Architect and the Office of Public School Construc-
8
tion (when required) prior to the award of a contract to the lowest
responsible bidder. [EC 17263, 17267]
3.9 All relocatables in use throughout the district meet statutory require-
ments. [EC 17292] 2
3.10 The district maintains a plan for the maintenance and modernization
of its facilities. [EC 17366] 8
3.11 The annual deferred maintenance contribution is made correctly. The
district should annually transfer the maximum amount that the dis- 10
trict would be eligible for in matching funds from the state.
158 Facilities Managment Facilities Managment 159
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
3.12 The district actively manages the deferred maintenance projects. The
district should review the five-year deferred maintenance plan annu-
ally to remove any completed projects and include any newly eligible
10
projects. The district should also verify that the expenses performed
during the year were included in the state approved five-year deferred
maintenance plan.
3.13 The staff within the district is knowledgeable of procedures within
the Office of Public School Construction (OPSC). 8
3.14 The staff within the district is knowledgeable of procedures within
the Division of the State Architect (DSA). 8
4.1 The district maintains an appropriate structure for the effective man-
agement of its construction projects. 7
4.2 Change orders are processed and receive prior approval from required
parties before being implemented within respective construction proj- 8
ects.
4.3 The district maintains appropriate project records and drawings.
0 ❑
4.4 Each Inspector of Record (IOR) assignment is properly approved.
9
5.1 The district complies with formal bidding procedures. [GC 54202,
54204, PCC 20111] 7
5.2 The district has a procedure for requests for quotes/proposals. [GC
54202, 54204, PCC 20111] 7
5.3 The district maintains files of conflict-of-interest statements and
complies with legal requirements. Conflict of interest statements 2 ❑
should be collected annually and kept on file.
5.4 The district ensures that biddable plans and specifications are devel-
oped through its licensed architects/engineers for respective con- 6
struction projects.
5.5 The district ensures that requests for progress payments are carefully
evaluated. 7
160 Facilities Managment Facilities Managment 161
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
5.6 The district maintains contract award/appeal processes. [GC 54202,
54204, PCC 2011] 8
5.7 The district maintains internal control, security, and confidentiality
over the bid submission and award processes. [GC 54202, 54204, PCC 7
20111]
6.1 The district complies with California Department of Education (CDE)
requirements relative to the provision of Special Education facilities. 6 ❑
6.2 The district provides facilities for its special education programs that
ensure equity with other educational programs within the district and
6 ❑
provide appropriate learning environments in relation to educational
program needs.
6.3 The district provides facilities for its special education programs that
provide appropriate learning environments in relation to educational 5 ❑
program needs.
7.1 The district applies for state funding for class size reduction facili-
ties. The district should apply for cass size reduction (CSR) facilities 10
funding annually.
7.2 The district has provided adequate facilities for the additional classes
resulting from the implementation of class size reduction. 10
7.3 The district has complied with CDE suggested space requirements
relative to the provision of educational environments for the imple- 10
mentation of class size reduction.
7.4 The district has developed a plan for the provision of permanent
facilities in which to house its CSR programs. 6
8.1 An energy conservation policy should be approved by the board of
education and implemented throughout the district. 2 ❑
8.2 The district should dreate and maintain a system to track utility costs
and consumption and to report on the success of the district’s energy 2 ❑
program.
8.3 An energy analysis should be completed for each site.
5 ❑
8.4 Cost-effective, energy-efficient design should be a top priority for all
district construction projects. 10
160 Facilities Managment Facilities Managment 161
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
8.4a The district should be in discussion and working as a team with agen-
cies that can provide professional assistance and funding. 10
8.4b The district should act toward improving the energy efficiency of all
sites, including those not included in the local bond. 8
8.4c The district should analyze the possibility of using alternative energy
sources as a means to reducing the financial impact of utilities on the 0
district.
8.5 Adequate maintenance records and reports are kept, including a
complete inventory of supplies, materials, tools and equipment. All
employees required to perform maintenance on school sites should be
provided with adequate supplies, equipment and training to perform 7
maintenance tasks in a timely and professional manner. Included in
the training is how to inventory supplies and equipment and when to
order or replenish them.
8.6 Procedures are in place for evaluating the work quality of mainte-
nance and operations staff. The quality of the work performed by the
maintenance and operations staff should be evaluated on a regular 4 ❑
basis using a board-adopted procedure that delineates the areas of
evaluation and the types of work to be evaluated.
8.7 Major areas of custodial and maintenance responsibilities and specific
jobs to be performed have been identified. Custodial and mainte-
nance personnel should have written job descriptions that delineate 5
the major areas of responsibilities that they will be expected to per-
form and will be evaluated on.
8.8 Necessary staff, supplies, tools and equipment for the proper care
and cleaning of the school(s) are available. In order to meet expecta-
tions, schools must be adequately staffed and staff must be provided 5
with the necessary supplies, tools and equipment as well as the train-
ing associated with the proper use of such.
8.9 The district has an effective preventive maintenance program. The
district should have a written preventive maintenance program that
is scheduled and followed by the maintenance staff. This program 7
should include verification of the completion of work by the supervi-
sor of the maintenance staff.
8.10 Toilet facilities are adequate and maintained. All buildings and
grounds are maintained. [CCR Title 5 § 631] 5
162 Facilities Managment Facilities Managment 163
Facilities Management Facilities Management
July Focus for July Focus for
Standard to be addressed 2003 January Standard to be addressed 2003 January
rating 2004 rating 2004
8.11 The district has implemented a planned program maintenance sys-
tem. The district should have a written planned program maintenance
system that includes an inventory of all facilities and equipment
that will require maintenance and replacement. This program should 3 �❑
include purchase prices, anticipated life expectancies, anticipated
replacement timelines and budgetary resources necessary to maintain
the facilities.
8.12 The district has a documented process for assigning routine repair
work orders on a priority basis. 6
9.1 The district has developed a plan for attractively landscaped facili-
ties. 6
9.2 The goals and objectives of the technology plan should be clearly
defined. The plan should include both the administrative and instruc-
7
tional technology systems. There should be a summary of the costs of
each objective and a financing plan should be in place.
9.3 The Governing Board shall provide a warm, healthful place in which
children who bring their own lunches to school may eat their lunch. 7
[EC 17573, CCR Title 5 §14030]
9.4 The Governing Board of every school district shall provide clean and
operable flush toilets for the use of pupils. [EC 17576, CCR Title 5 5
§14030]
9.5 The district has plans for the provision of extended day programs
within its respective school sites. [EC 17264] 5
9.6 The district has developed and maintains a plan to ensure equality
and equity of its facilities throughout the district. [EC 35293] 6
9.7 All schools shall have adequate heating and ventilation.
8
9.8 All schools shall have adequate lighting and electrical service.
8
9.9 Classrooms are free of noise and other barriers to instruction. [EC
32212] 9
162 Facilities Managment Facilities Managment 163
Facilities Management
July Focus for
Standard to be addressed 2003 January
rating 2004
9.10 The learning environments provided within respective school sites
within the district are conducive to high quality teaching and learn- 7
ing.
9.11 Facilities within the district reflect the standards and expectations
established by the community. 7
10.1 The district should have a plan to promote community involvement in
schools. 6
10.2 Education Code section 38130 establishes terms and conditions of
school facility use by community organizations, in the process requir-
6
ing establishment of both “direct cost” and “fair market” rental rates,
specifying what groups have which priorities and fee schedules. “
10.3 Districts should maintain comprehensive records and controls on civic
center implementation and cash management. 0 ❑
11.1 The district’s public information office should coordinate a full appri-
sal to students, staff and community of the condition of the district’s 8
facilities.
11.2 The district should apprise students, staff and community of efforts
to rectify any substandard conditions. 8
11.3 The district should provide clear and comprehensive communication
to staff of its standards and plans. 8
11.4 All stakeholder groups should be directly involved in a meaningful
manner regarding the district’s facilities. 8
164 Facilities Managment