FCMAT
Comprehensive Review Facilities Management
Read the report at West Contra Costa Unified School District ↗
West Contra Costa
Unified School
District
Facilities Management
Comprehensive Review
January 2002
Administrative Agent
Larry E. Reider
Office of Kern County
Superintendent of Schools
Chief Executive Officer
Thomas E. Henry
1.3 School Safety—Plan for Protection of People and Property
Legal Standard
Demonstrate that a plan of security has been developed, which includes adequate measures of
safety and protection of people and property. [EC 32020, 32211, 35294-35294.9]
Progress on Recommendations and Improvement Plan:
1. The district has completed the development of the Comprehensive Safety Plan. The
plan has been put into a large binder covering a wide range of possible safety viola-
tions and emergency situations and the district’s guidance on how to handle each
situation. Each situation noted in the binder has a checklist showing the specific step-
by-step process to properly meet the needs of the school.
2. The district currently is training each school site staff on the use of the plan. The
district is approximately halfway through training the staff.
3. With the awarding of the contract to the Master Architect, one of the requirements in
the development of modernization drawings is the inclusion of security lighting,
proper signage, and any additional security measures required by the district.
4. & 5. The district is still requiring all visitors and volunteers to sign in upon arrival at
the school sites, and to wear identification badges at all times.
Standard Implemented: Partially
June 2001 Rating: 4
December 2001 Self-Rating: 6
December 2001 New Rating: 6
Implementation Scale:
Facilities Management 1
1.6 School Safety—Monitoring of Bus Loading/Unloading Areas for Safety
Professional Standard
Bus loading and unloading areas, delivery areas, and parking and parent loading/ unloading areas
are monitored on a regular basis to ensure the safety of the students, staff, and community.
Students, employees, and the public should feel safe at all times on school premises.
Progress on Recommendations and Improvement Plan:
1. The district has begun the process of painting traffic directions and erecting signage at
the school entrances and the parking areas to direct traffic. The consideration of
student safety, in loading and unloading from vehicles, is included in the specifica-
tions being developed by the Master Architect. The plans are to include additional
parking spaces and revised traffic patterns.
2. While the district is working with local law enforcement to increase student safety, the
city and county cannot provide crossing guard funding. As a result, most of the assis-
tance provided by the city and county is in increased striping and signage for street
crossings.
3. The only crossing guards provided by the district are volunteers. There is no district
funding available for additional crossing guards.
Standard Implemented: Partially
June 2001 Rating: 3
December 2001 Self-Rating: 3
December 2001 New Rating: 3
Implementation Scale:
2 Facilities Management
1.7 School Safety—Installation and Operation of Outside Security Lighting
Professional Standard
Outside lighting is properly placed and monitored on a regular basis to ensure the operability/
adequacy of such lighting, and to ensure safety while activities are in progress in the evening
hours. Outside lighting should provide sufficient illumination to allow for the safe passage of
students and the public during after-hour activities. Lighting should also provide security person-
nel with sufficient illumination to observe any illegal activities on campus.
Progress on Recommendations and Improvement Plan:
1. The district has begun a major overhaul of the exterior lighting of all schools. The
overhaul is in response to many circumstances, ranging from employee grievances
regarding safety to unsafe instances observed during the initial FCMAT site visita-
tions. More than 20 schools have either had existing lighting upgraded or had addi-
tional exterior lighting installed.
2. Once the Measure M remodeling and construction is complete, the district plans to
include exterior lighting as a part of the planned program maintenance system.
Planned program maintenance will be an important key to maintaining well-lit cam-
puses for maximum security.
3. All of the lighting in all schools eventually will be upgraded or replaced as a result of
Measure M funding, if the funds are sufficient to meet all of the district’s needs.
Standard Implemented: Partially
June 2001 Rating: 2
December 2001 Self-Rating: 4
December 2001 New Rating: 4
Implementation Scale:
Facilities Management 3
1.8 School Safety—Graffiti and Vandalism Abatement Plan
Professional Standard
The district has a graffiti and vandalism abatement plan. The district should have a written
graffiti and abatement plan that is followed by all district employees. The district provides dis-
trict employees with sufficient resources to meet the requirements of the abatement plan.
Progress on Recommendations and Improvement Plan
1. The district continues to aggressively perform daily graffiti abatement. Custodians are
trained on the proper use of paint and supplies to meet this need. They are also in-
structed that if they cannot fully abate the graffiti, they are to notify the paint shop
immediately for assistance.
2. As schools are remodeled using Measure M funding, additional storage space for the
custodians has been requested. This storage space will include room for paint and
supplies.
3. Plant managers and site custodians are being evaluated for many areas, one of which
is the timeliness of graffiti abatement.
4. While the district has an aggressive graffiti abatement program, it is not seen as a
project that will ever end. There are some schools that can keep up with removing
graffiti within 24 hours, while others struggle to meet the 24-hour requirement for
removal. The graffiti problem is not one that is solved simply with money and muscle.
5. As mentioned in Standard 1.7, the district is upgrading and installing exterior lighting
in an effort to provide safe campuses. At the same time, it is hoped that the additional
lighting also will be a deterrent to graffiti vandals.
Standard Implemented: Partially
June 2001 Rating: 4
December 2001 Self-Rating: 4
December 2001 New Rating: 4
Implementation Scale:
4 Facilities Management
1.12 School Safety—Inspection and Correction of Unsafe Conditions
Legal Standard
Building examinations are performed and required actions are taken by the Governing Board
upon report of unsafe conditions. [EC 17367]
Progress on Recommendations and Improvement Plan
1. Work orders to correct unsafe working conditions continue to be a top priority for the
site and district maintenance staff. As the maintenance staff receive safety work
orders, they are inserted into the maintenance schedule to eliminate the unsafe condi-
tions as quickly as possible.
2. The district is developing an annual inspection schedule for validation of unsafe
conditions and scheduling of repairs.
3. The district has submitted applications to the OPSC for modernization funding;
however, the state currently is short of funds to support the program. Until such time
as the state passes another school bond, the district will have to pay for the moderniza-
tion through use of local bond funds.
The substandard and potentially unsafe conditions noted in the initial site visitations
still exist in some of the schools and will require long-term solutions. This is one of
the assignments given to the Master Architect in developing the reconstruction plans
for the district. In some cases, the existing schools are in such need of repair that it is
more cost effective to demolish the schools and build new ones. The timeline to build
these new schools is between five and seven years, so the unsafe conditions will not
be eliminated for some time.
Standard Implemented: Partially
June 2001 Rating: 3
December 2001 Self-Rating: 6
December 2001 New Rating: 5
Implementation Scale:
Facilities Management 5
1.23 School Safety—Safety of Boilers and Fired Pressure Vessels
Legal Standard
Safe work practices exist with regard to boiler and fired pressure vessels. [CCR Title 8 §782]
Progress on Recommendations and Improvement Plan
1. The newly hired Maintenance Supervisor has implemented an annual boiler preven-
tive maintenance program to assure that all boilers are safe before firing them up for
the new school year. With only two HVAC technicians to perform the preventive
maintenance, this consumes the majority of their time during the summer break.
2. Measure M funding will be designated to replace all boilers and fired pressure vessels
as the schools are remodeled.
3. The district has begun a regular schedule of site visits to verify that inappropriate
materials have been removed from the boiler areas.
Standard Implemented: Partially
June 2001 Rating: 2
December 2001 Self-Rating: 4
December 2001 New Rating: 4
Implementation Scale:
6 Facilities Management
1.24 School Safety—Maintenance of Materials Safety Data Sheets
Legal Standard
Maintenance of Materials Safety Data Sheets. [EC 49341, 49401.5, 49411, F&AC 12981, LC
6360-6363, CCR Title 8 §5194]
Progress on Recommendations and Improvement Plan
1. The district now receives Materials Safety Data Sheets on CDs from all vendors for
hazardous substances or mixtures.
2. The district contracted with a consultant to review all of the MSDS books maintained
at the school sites and the custodial areas, to verify that the books were current. If the
consultant observed outdated materials in the book, he replaced them with updated
sheets. As of the date of the interview, the district had just completed the latest round
of updating the MSDS books at all sites.
3. The Director of Maintenance and Operations receives all of the original MSDS sheets
and CDs as soon as new supplies are received. He reviews them to decide how to train
employees on the proper use and storage of the materials. He also updates the custo-
dial training program to reflect the new requirement.
4. The district has not opted for the fax-on-demand program yet. It has opted for MSDS
on CDs instead.
5. All staff that come in contact with any hazardous substances or mixtures are trained
annually, at a minimum, in the proper handling of the substances.
Standard Implemented: Partially
June 2001 Rating: 3
December 2001 Self-Rating: 6
December 2001 New Rating: 6
Implementation Scale:
Facilities Management 7
3.9 Facilities Improvement and Modernization—All Relocatables Meet Statu-
tory Requirements
Legal Standard
All relocatables in use throughout the district meet statutory requirements. [EC 17292]
Progress on Recommendations and Improvement Plan
1. Since the initial review of the relocatables earlier this year, the district has
received approval for 147 relocatable classrooms from the Division of the State
Architect (DSA). This is more than two-thirds of the total number of relocatable
classrooms in the district. The balance of the relocatables is being analyzed for demo-
lition, improvement, or replacement.
All new relocatables are required to receive DSA approval prior to placement at a
school site.
Standard Implemented: Partially
June 2001 Rating: 2
December 2001 Self-Rating: 6
December 2001 New Rating: 6
Implementation Scale:
8 Facilities Management
3.10 Facilities Improvement and Modernization—Plan for Maintenance and
Modernization Exists
Legal Standard
The district maintains a plan for the maintenance and modernization of its facilities.
[EC 17366]
Progress on Recommendations and Improvement Plan
1. With the awarding of the contract to the Master Architect, the facilities master plan, as
updated by the bond election documentation, continues to be implemented by the
district. The Master Architect has clear marching orders for timelines for completion,
and for which school sites are the first, second, and third priority for completion.
2. The facilities master plan will be updated as projects are completed and as new needs
are recognized.
Standard Implemented: Partially
June 2001 Rating: 4
December 2001 Self-Rating: 6
December 2001 New Rating: 6
Implementation Scale:
Facilities Management 9
4.3 Construction of Projects—Appropriate Project Records and Drawings are
Maintained
Professional Standard
The district maintains appropriate project records and drawings.
Progress on Recommendations and Improvement Plan
1. The district is moving all construction records to a central office as noted in #2 below.
A part of the new storage program is to shift from paper to imaging so that the district
does not have to store tons of paper. Instead, all of the current documentation is being
scanned to imaging, and all new documentation is initially developed using imaging.
2. The district has made great strides in the storage and maintenance of the facilities
records. A new central storage facility at 1300 Portero Avenue has been established
for all blueprints and construction documents.
3. As soon as the new storage cabinets have been installed, the district will establish an
issuance or checkout procedure for all documents. With the movement to an imaging
process, some documents will not need to be checked out since they will be able to be
transmitted via the Internet or e-mail.
Standard Implemented: Partially
June 2001 Rating: 3
December 2001 Self-Rating: 6
December 2001 New Rating: 6
Implementation Scale:
10 Facilities Management
6.3 Special Education Facilities—Adequacy for Instructional Program Needs
Professional Standard
The WCCUSD provides facilities for its special education programs that provide appropriate
learning environments in relation to educational program needs.
Progress on Recommendations and Improvement Plan
1. – 5.With the awarding of the contract to the Master Architect, the assessment of special
education facilities and the need to reconfigure the schools during the modernization
and reconstruction is a top priority. ADA compliance for students with special needs is
also a part of the Master Architect’s responsibilities.
The district’s fiscal needs are being considered as the local bond funds are prioritized.
As additional special education classroom needs are recognized, the funding is also
being designated to make sure that the schools have adequate special education class-
rooms.
Standard Implemented: Partially
June 2001 Rating: 4
December 2001 Self-Rating: 5
December 2001 New Rating: 5
Implementation Scale:
Facilities Management 11
7.4 Implementation of Class-Size Reduction—Plans for Permanent Facilities
Professional Standard
The district has developed a plan for the provision of permanent facilities in which to house its
CSR programs.
Progress on Recommendations and Improvement Plan
1. An assessment of district facilities for CSR programs has been completed and a plan
is being developed.
2. The Master Architect is following the CDE space allocation guidelines in developing
the specifications for the remodeled and new schools.
3. The district has included the possibility of replacing portable classrooms with perma-
nent buildings as a part of its total facility plan. However, without adequate state
resources for CSR facilities, with the lack of any state funding for new construction of
CSR facilities, and with only local bond funds to meet the facilities needs of the
district, the replacement of CSR portables with permanent facilities is not a high
priority at this time. The district is considering replacing old portables with permanent
facilities where possible.
Standard Implemented: Partially
June 2001 Rating: 2
December 2001 Self-Rating: 3
December 2001 New Rating: 3
Implementation Scale:
12 Facilities Management
8.7 Facilities Maintenance and Custodial—Procedures for Evaluation of Cus-
todial Staff
Professional Standard
Major areas of custodial and maintenance responsibilities and specific jobs to be performed have
been identified. Custodial and maintenance personnel should have written job descriptions that
delineate the major areas of responsibilities that they are expected to perform, and on which they
will be evaluated.
Progress on Recommendations and Improvement Plan
1. The new contract provisions cited in the initial report do not apply directly to the
evaluation of the custodial staff. The custodians are represented by the Local 1 con-
tract.
2. Site principals are encouraged to use the special evaluation option available in the
contract. The Custodial Supervisor works closely with the principals to validate the
quality of the work performed by the custodians so that the assessment can be in-
cluded in the evaluation.
3. The district is in the process of updating all of the classified job descriptions. As
vacancies arise, job descriptions are reviewed by the Director of Maintenance and
Operations, updated, and presented to the collective bargaining group with final
approval by the Governing Board of the district. In addition, a consultant has been
hired by the district to update all job descriptions by June 2002.
Standard Implemented: Partially
June 2001 Rating: 4
December 2001 Self-Rating: 5
December 2001 New Rating: 5
Implementation Scale:
Facilities Management 13
8.11 Facilities Maintenance and Custodial—Implementation of a Planned
Program Maintenance System
Professional Standard
The district has implemented a planned program maintenance system, but it should have a writ-
ten planned program maintenance system that includes an inventory of all facilities and equip-
ment that will require maintenance and replacement. This program should include purchase
prices, anticipated life expectancies, anticipated replacement timelines, and budgetary resources
necessary to will be needed to keep the facilities in good condition can be established. Until such
time, no financial plan can be created.
Progress on Recommendations and Improvement Plan
1. A board policy has not been developed. It is anticipated that the policy will be devel-
oped as the Measure M funds are spent and planned program maintenance becomes a
part of the total facilities maintenance package.
2. While a formal inventory of the facilities is not yet available, creating an inventory at
this time would not be helpful. The inventory would have to be completely revised
once the reconstruction is complete.
3. Once the schools are reconstructed and the inventory is completed, the dollar amount
that will be needed to keep the facilities in good condition can be established. Until
such time, no financial plan can be created.
4. The newly hired Maintenance Manager has begun the development of a planned
program maintenance system. The first portion of the system has been implemented in
the area of boiler maintenance.
Standard Implemented: Partially
June 2001 Rating: 0
December 2001 Self-Rating: 2
December 2001 New Rating: 2
Implementation Scale:
14 Facilities Management
9.4 Instructional Program Issues—Bathroom Facilities are Clean and Oper-
able
Legal Standard
The Governing Board of every school district shall provide clean and operable flush toilets for
the use of pupils. [EC 17576, CCR Title 5 §14030]
Progress on Recommendations and Improvement Plan
1. One of the areas that Measure M funds are going to be used for is the overhaul of the
existing restroom facilities. These funds are being used in conjunction with other
district funds, such as Deferred Maintenance.
2. A comprehensive restroom cleaning plan has been developed. The first area of the
district to receive the higher standards is in the Pinole area. Based on input from the
40 participants of the Bathroom Cleaning Standards Committee of the Pinole area
schools, the new standards for restroom cleaning were established and implemented.
The district intends to provide the same availability for input in all of the communities
of the district. As the new standards are implemented, custodial staff is trained to use
the new cleaning standards.
3. The supervisory staff and vendor representatives train custodial staff members in the
proper use of cleaning products to reduce and eliminate unsanitary conditions or
potential health and safety issues.
4. Until the schools are modernized and the actual square footage of classroom space and
restroom facilities established, it is premature to evaluate custodial staffing levels.
This area will be reviewed in a follow-up to this report.
5. The Master Architect was hired by the district to develop all new school specifics in
full compliance with the Americans with Disabilities Act. Some of the plans devel-
oped already include the installation of elevators in multi-story schools and replace-
ment of narrow door enclosures.
Standard Implemented: Partially
June 2001 Rating: 3
December 2001 Self-Rating: 5
December 2001 New Rating: 5
Implementation Scale:
Facilities Management 15
9.10 Instructional Program Issues—Environment Conducive to High-Quality
Teaching and Learning
Professional Standard
The learning environments provided within respective school sites within the district are condu-
cive to high-quality teaching and learning.
Progress on Recommendations and Improvement Plan
1. As noted in the district’s publication, “Measure M Action Plan Presentation,” the
Master Architect receives input from a wide range of people, including technology,
safety, M&O, food services, and the Bond Oversight Committee representing the
public. Based on the input from these people, the Master Architect is developing
school specifications to meet the needs of the students.
2. The teaching staff is included in the discussions at each school that is scheduled to be
remodeled or reconstructed.
3. Educational specifications are included in the documents developed by the Master
Architect.
Standard Implemented: Partially
June 2001 Rating: 3
December 2001 Self-Rating: 4
December 2001 New Rating: 4
Implementation Scale:
16 Facilities Management
9.11 Instructional Program Issues—Facilities Reflect Community Standards
and Expectations
Professional Standard
Facilities within the district reflect the standards and expectations established by the community.
Progress on Recommendations and Improvement Plan
1. & 2. The district has begun making strides to reflect the community standards for the
individual schools. During the recent modernization of Cesar Chavez School, district
personnel met with the students and community regarding the colors that the school
should be painted. As a result of this input, a school that was tagged routinely is now
relatively tag free because the colors used for the exterior paint of the school reflect
the colors of the students’ heritage. The students and community members take pride
in the school and respect it.
3. & 4. As noted in the district’s publication, “Measure M Action Plan Presentation,” the
Master Architect receives input from a wide range of people, including technology,
safety, M&O, food services, and the Bond Oversight Committee representing the
public. Based on the input from these people, the Master Architect is developing
school specifications to meet the needs of the students. Educational specifications are
included in the documents developed by the Master Architect.
Standard Implemented: Partially
June 2001 Rating: 3
December 2001 Self-Rating: 4
December 2001 New Rating: 4
Implementation Scale:
Facilities Management 17
18 Facilities Management
Chart of
Facilities Management Standards
Progress Ratings Toward Implementation of the Improvement Plan
Facilities Management 19
○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○
20 Facilities Management
Facilities Management
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
All school administrators should be thoroughly familiar
with the California Department of Education, Civil
Defense and Disaster Planning Guide for School
1.1 3 NR ❑
Officials, 1972. [EC 32000-32004, 32040, 35295-35297,
38132, 46390-46392, 49505, GC 3100, 8607, CCR Title
5 §550, 560, Title 19 §2400]
The district includes the appropriate security devices in
the design of new buildings as well as in modernized
1.2 5 NR
buildings. [EC 32020, 32211, 35294-35294.9, 39670-
39675]
Demonstrate that a plan of security has been
developed, which includes adequate measures of safety
1.3 4 ❑ 6
and protection of people and property. [EC 32020,
32211, 35294-35294.9]
Ensure that the custodial and maintenance staff are
regularly informed of restrictions pertaining to the
1.4 storage and disposal of flammable or toxic materials. 2 NR ❑
[EC 49341, 49401.5, 49411, F&AC 12981, H&SC 25163,
25500-25520, LC 6360-6363, CCR Title 8 §5194]
The district has a documented process for the issuance
of master and sub-master keys. A district-wide
1.5 standardized process for the issuance of keys to 7 NR
employees must be followed by all district
administrators.
Bus loading and unloading areas, delivery areas, and
parking and parent loading/unloading areas are
monitored on a regular basis to ensure the safety of
1.6 3 ❑ 3
the students, staff and community. Students, employees
and the public should feel safe at all times on school
premises.
Outside lighting is properly placed and monitored on a
regular basis to ensure the operability/adequacy of
such lighting to ensure safety while activities are in
progress in the evening hours. Outside lighting should
1.7 provide sufficient illumination to allow for the safe 2 ❑ 4
passage of students and the public during after-hours
activities. Lighting should also provide security
personnel with sufficient illumination to observe any
illegal activities on campus.
Facilities Management NR not reviewed 21
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district has a graffiti and vandalism abatement
plan. The district should have a written graffiti and
abatement plan that is followed by all district
1.8 4 ❑ 4
employees. The district provides district employees
with sufficient resources to meet the requirements of
the abatement plan.
Each public agency is required to have on file written
plans describing procedures to be employed in case of
1.9 emergency. [EC 32000-32004, 32040, 35295-35297, 3 NR ❑
38132, 46390-46392, 49505, GC 3100, 8607] [CCR Title
8, §3220]
Each elementary and intermediate school at least once
a month, and in each secondary school not less than
1.10 7 NR
twice every school year, shall conduct a fire drill. [EC
32000-32004, 32040, CCR Title 5 §550]
Maintenance/custodial personnel have knowledge of
chemical compounds used in school programs that
1.11 include the potential hazards and shelf life. [EC 49341, 2 NR ❑
49401.5, 49411, F&AC 12981, H&SC 25163, 25500-
25520, LC 6360-6363, CCR Title 8 §5194]
Building examinations are performed, and required
1.12 actions are taken by the governing board upon report 3 ❑ 5
of unsafe conditions. [EC 17367]
Each school which is entirely enclosed by a fence or
partial buildings must have a gate of sufficient size to
1.13 permit the entrance of ambulances, police and fire 9 NR
fighting equipment. Locking devices shall be designed
to permit ready entrance.
Sanitary, neat and clean conditions of the school
premises exist and the premises are free from
1.14 4 NR
conditions that would create a fire hazard. [CCR Title 5
§633]
The Injury and Illness Prevention Program (IIPP)
1.15 requires periodic inspections of facilities to identify 5 NR
conditions. [CCR Title 8 §3203]
22 Facilities Management NR not reviewed
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
Appropriate fire extinguishers exist in each building
1.16 and current inspection information is available. [CCR 5 NR
Title 8 §1922(a)]
1.17 All exits are free of obstructions. [CCR Title 8 §3219] 9 NR
A comprehensive school safety plan exists for the
1.18 prevention of campus crime and violence. [EC 35294- 6 NR
35294.9]
Each public agency is required to have on file written
plans describing procedures to be employed in case of
1.19 emergency. [EC 32000-32004, 32040, 35295-35297, 3 NR ❑
38132, 46390-46392, 49505, GC 3100, 8607] [CCR Title
8, §3220]
Requirements are followed pertaining to underground
1.20 storage tanks. [H&SC 25292, CCR Title 26 §477, Title 5 NR
23 § 2610]
All asbestos inspection and asbestos work completed in
the US is performed by Asbestos Hazard Emergency
1.21 6 NR
Response Act (AHERA) accredited individuals. [EC
49410.5, 40 CFR Part 763]
All playground equipment meets safety code regulations
and is inspected in a timely fashion as to ensure the
1.22 safety of the students. [EC 44807, GC 810-996.6, H&SC 8 NR
24450 Chapter 4.5, 115725-115750, PRC 5411, CCR
Title 5 §5552]
Safe work practices exist with regard to boiler and fired
1.23 2 ❑ 4 ❑
pressure vessels. [CCR Title 8 §782]
Materials Safety Data Sheets are maintained. [EC
1.24 49341, 49401.5, 49411, F&AC 12981, LC 6360-6363, 3 ❑ 6
CCR Title 8 §5194]
The district maintains a comprehensive employee safety
program. Employees are made aware of the district
1.25 safety program and the district provides in-service 9 NR
training to employees on the requirements of the safety
program.
The district conducts periodic safety training for
1.26 employees. District employees should receive periodic 8 NR
training on the safety procedures of the district.
Facilities Management NR not reviewed 23
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district should conduct periodic first aid training
1.27 6 NR
for employees assigned to school sites.
The district should have a long-range school facilities
2.1 8 NR
master plan.
The district should possess a California State
2.2 Department of Education Facilities Planning and 10 NR
Construction Guide (dated 1991).
2.3 The district should seek state and local funds. 10 NR
The district is in the process of finalizing a Citizens
Oversight Committee to ensure the appropriateness of
expenditures related to the recent passage of the
2.4 6 NR
district's local school bond measure (Measure M). In
essence, this committee will function as an
advisory/facility planning type of committee.
The district should have a properly staffed and funded
2.5 2 NR ❑
facility planning department.
The district should develop and implement an annual
2.6 6 NR
capital planning budget.
The district should have standards for real property
2.7 10 NR
acquisition and disposal. [EC 39006, 17230-17233]
The district seeks and obtains waivers from the State
2.8 Allocation Board for continued use of its non- 4 NR ❑
conforming facilities. [EC 17284, 17285]
The district has established and utilizes a selection
2.9 process for the selection of licensed 6 NR
architectural/engineering services. [GC 17302]
The district should assess its local bonding capacity.
2.10 6 NR
[EC 15100]
The district should develop a process to determine debt
2.11 10 NR
capacity.
The district should be aware of and monitor the
2.12 assessed valuation of taxable property within its 10 NR
boundaries.
24 Facilities Management NR not reviewed
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district should monitor its legal bonding limits. [EC
2.13 10 NR
15100, 15330]
The district should collect statutory school fees. [EC
2.14 5 NR
17620, GC 65995, 66000]
The district should consider developing an asset
2.15 4 NR
management plan.
The district has pursued state funding for joint-use
projects through the filing of applications through the
2.16 4 NR
Office of Public School Construction and the State
Allocation Board.
The district has established and utilizes an organized
2.17 5 NR
methodology of prioritizing and scheduling projects.
The district complies with California Department of
2.18 Education (CDE) recommendations relative to school 3 NR ❑
site sizing.
The district should distribute facility funding in an
2.19 equitable manner to all communities served and to all 8 NR
school levels.
The district has a restricted deferred maintenance fund
and those funds are expended for maintenance
purposes only. The deferred maintenance fund should
3.1 6 NR
be a stand-alone fund reflecting the revenues and
expenses for the major maintenance projects
accomplished during the year.
The district has pursued state funding for deferred
maintenance - critical hardship needs by filing an
3.2 application(s) through the Office of Public School 6 NR
Construction and the State Allocation Board. [State
Allocation Board Regulation §1866]
The district applies to the State Allocation Board for
3.3 5 NR
facilities funding for all applicable projects.
The district consistently reviews and monitors its
3.4 eligibility for state funding so as to capitalize upon 6 NR
maximal funding opportunities.
Facilities Management NR not reviewed 25
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district establishes and implements interim housing
plans for use during the construction phase of
3.5 modernization projects and/or additions to existing 3 NR ❑
facilities.
The district has established and maintains a system for
3.6 6 NR
tracking the progress of individual projects.
Furniture and equipment items are routinely included
3.7 2 NR ❑
within the scope of modernization projects.
The district obtains approval of plans and specifications
from the Division of the State Architect and the Office
3.8 of Public School Construction (when required) prior to 5 NR
the award of a contract to the lowest responsible
bidder. [EC 17263, 17267]
All relocatables in use throughout the district meet
3.9 2 ❑ 6
statutory requirements. [EC 17292]
The district maintains a plan for the maintenance and
3.10 4 ❑ 6
modernization of its facilities. [EC 17366]
The annual deferred maintenance contribution is made
correctly. The district should annually transfer the
3.11 6 NR
maximum amount that the district would be eligible for
in matching funds from the state.
The district actively manages the deferred maintenance
projects. The district should review the five-year
deferred maintenance plan annually to remove any
completed projects and include any newly eligible
3.12 6 NR
projects. The district should also verify that the
expenses performed during the year were included in
the state approved five-year deferred maintenance
plan.
Staff within the district is knowledgeable of procedures
3.13 6 NR
within the Office of Public School Construction (OPSC).
Staff within the district is knowledgeable of procedures
3.14 6 NR
within the Division of the State Architect (DSA).
The district maintains an appropriate structure for the
4.1 3 NR ❑
effective management of its construction projects.
26 Facilities Management NR not reviewed
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
Change orders are processed and receive prior approval
4.2 from required parties before being implemented within 4 NR
respective construction projects.
The district maintains appropriate project records and
4.3 3 ❑ 6
drawings.
Each Inspector of Record (IOR) assignment is properly
4.4 3 NR ❑
approved.
The district complies with formal bidding procedures.
5.1 9 NR
[GC 54202, 54204, PCC 20111]
The district has a procedure for requests for
5.2 6 NR
quotes/proposals. [GC 54202, 54204, PCC 20111]
The district maintains files of conflict of interest
statements and complies with legal requirements.
5.3 7 NR
Conflict of interest statements should be collected
annually and kept on file.
The district ensures that biddable plans and
specifications are developed through its licensed
5.4 4 NR
architects/engineers for respective construction
projects.
The district ensures that requests for progress payments
5.5 5 NR
are carefully evaluated.
The district maintains contract award/appeal processes.
5.6 8 NR
[GC 54202, 54204, PCC 2011]
The district maintains internal control, security, and
5.7 confidentiality over the bid submission and award 7 NR
processes. [GC 54202, 54204, PCC 20111]
The district complies with California Department of
6.1 Education (CDE) requirements relative to the provision 4 NR
of Special Education facilities.
The district provides facilities for its Special Education
programs which ensure equity with other educational
6.2 programs within the district and provides appropriate 4 NR
learning environments in relation to educational
program needs.
Facilities Management NR not reviewed 27
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district provides facilities for its Special Education
6.3 programs which provide appropriate learning 4 ❑ 5
environments in relation to educational program needs.
The district applies for state funding for class size
7.1 reduction facilities. The district should apply for class 9 NR
size reduction facilities funding annually.
The district has provided adequate facilities for the
7.2 additional classes resulting from the implementation of 5 NR
Class Size Reduction (CSR).
The district has complied with CDE suggested space
requirements relative to the provision of educational
7.3 5 NR
environments for the implementation of Class Size
Reduction (CSR).
The district has developed a plan for the provision of
7.4 permanent facilities in which to house its CSR 2 ❑ 3
programs.
An Energy Conservation Policy should be approved by
8.1 the board of education and implemented throughout 4 NR
the district.
Create and maintain a system to track utility costs and
8.2 consumption and to report on the success of the 4 NR
district's energy program.
8.3 An energy analysis should be completed for each site. 2 NR ❑
Cost-effective, energy-efficient design should be a top
8.4 5 NR
priority for all district construction projects.
28 Facilities Management NR not reviewed
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district should be in discussion and working as a
8.4a team with agencies that can provide professional 10 NR
assistance and funding.
The district should act toward improving the energy
8.4b efficiency of all sites, including those not included in 7 NR
the local bond.
The district should analyze the possibility of using
8.4c alternative energy sources as a means to reducing the 5 NR
financial impact of utilities on the district.
Adequate maintenance records and reports are kept,
including a complete inventory of supplies, materials,
tools and equipment. All employees required to perform
maintenance on school sites should be provided with
8.5 6 NR
adequate supplies, equipment and training to perform
maintenance tasks in a timely and professional manner.
Included in the training is how to inventory supplies
and equipment and when to order or replenish them.
Procedures are in place for evaluating the work quality
of maintenance and operations staff. The quality of the
work performed by the maintenance and operations
8.6 4 NR
staff should be evaluated on a regular basis using a
board-adopted procedure that delineates the areas of
evaluation and the types of work to be evaluated.
Major areas of custodial and maintenance
responsibilities and specific jobs to be performed have
been identified. Custodial and maintenance personnel
8.7 4 ❑ 5
should have written job descriptions that delineate the
major areas of responsibilities that they will be
expected to perform and will be evaluated on.
Necessary staff, supplies, tools and equipment for the
proper care and cleaning of the school(s) are available.
In order to meet expectations, schools must be
8.8 4 NR
adequately staffed and staff must be provided with the
necessary supplies, tools and equipment as well as the
training associated with the proper use of such.
Facilities Management NR not reviewed 29
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district has an effective preventive maintenance
program. The district should have a written preventive
maintenance program that is scheduled and followed by
8.9 2 NR ❑
the maintenance staff. This program should include
verification of the completion of work by the supervisor
of the maintenance staff.
Toilet facilities are adequate and maintained. All
8.10 buildings and grounds are maintained. [CCR Title 5 § 3 NR ❑
631]
The district has implemented a planned program
maintenance system. The district should have a written
planned program maintenance system that includes an
inventory of all facilities and equipment that will
8.11 require maintenance and replacement. This program 0 ❑ 2
should include purchase prices, anticipated life
expectancies, anticipated replacement timelines and
budgetary resources necessary to maintain the
facilities.
The district has a documented process for assigning
8.12 5 NR
routine repair work orders on a priority basis.
The district has developed a plan for attractively
9.1 2 NR ❑
landscaped facilities.
The goals and objectives of the technology plan should
be clearly defined. The plan should include both the
9.2 administrative and instructional technology systems. 5 NR
There should be a summary of the costs of each
objective and a financing plan should be in place.
The governing board shall provide a warm, healthful
place in which children who bring their own lunches to
9.3 6 NR
school may eat their lunch. [EC 17573, CCR Title 5
§14030]
30 Facilities Management NR not reviewed
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The governing board of every school district shall
9.4 provide clean and operable flush toilets for the use of 3 ❑ 5
pupils. [EC 17576, CCR Title 5 §14030]
The district has plans for the provision of extended day
9.5 5 NR
programs within its respective school sites. [EC 17264]
The district has developed and maintains a plan to
9.6 ensure equality and equity of its facilities throughout 3 NR
the district. [EC 35293]
All schools shall have adequate heating and
9.7 7 NR
ventilation.
All schools shall have adequate lighting and electrical
9.8 6 NR
service.
Classrooms are free of noise and other barriers to
9.9 8 NR
instruction. [EC 32212]
The learning environments provided within respective
9.10 school sites within the district are conducive to high 3 ❑ 4
quality teaching and learning.
Facilities within the district reflect the standards and
9.11 3 ❑ 4
expectations established by the community.
The district should have a plan to promote community
10.1 7 NR
involvement in schools.
Education Code Section 38130 establishes terms and
conditions of school facility use by community
organizations, in the process requiring establishment of
10.2 4 NR
both "direct cost" and "fair market" rental rates,
specifying what groups have which priorities and fee
schedules.
Districts should maintain comprehensive records and
10.3 controls on civic center implementation and cash 4 NR
management.
Facilities Management NR not reviewed 31
❑ targeted for review
Facilities Management (continued)
June Dec. Dec. June
Standard to be addressed 2001 2001 2001 2002
Rating Focus Rating Focus
The district's public information office should
11.1 coordinate a full apprisal to students, staff and 8 NR
community of the condition of the district's facilities.
The district should apprise students, staff and
11.2 community of efforts to rectify any substandard 9 NR
conditions.
The district should provide clear and comprehensive
11.3 8 NR
communication to staff of its standards and plans.
All stakeholder groups should be directly involved in a
11.4 7 NR
meaningful manner regarding the district's facilities.
32 Facilities Management NR not reviewed
❑ targeted for review