INTRODUCTION
Background
The purpose of this report is to provide an assessment of the progress the Compton Unified School
District has made in the areas of school facilities and school safety. Included in the report are standards,
measurement tools, and a description of steps to be taken to achieve a full recovery.
The facilities and school safety portion of the RFA for Compton USD is a very broad, but also very deep
area. Our review centered on several important functional areas: School Safety, Facility Planning,
Facilities Improvement and Modernization, Construction of Projects, Compliance with Public Contract-
ing Laws and Procedures, Special Education Facilities, Implementation of Class-size Reduction, Facili-
ties Maintenance and Custodial, Instructional Program Issues, Community Use of Facilities, and Com-
munication. Each of these areas is presented separately in the tabbed recovery plan that is presented as
part of this report. We do want to point out, however, that the entire area we reviewed contains many
interdependencies and that our findings and recommendations should be taken in the context of the
entire area. Implementation of our recommendations in one finding statement may correct deficiencies
in related areas as well.
In evaluating each of the functional areas listed above, we developed a meaningful standard, selected
appropriate sources and documentation for measurement of performance against the standard, conducted
those measurements, and produced findings and recommendations in each
area. These recommendations are the heart of the recovery plan.
In each functional area we employed experts with practical knowledge and experience in the area. We
asked that the standards and measurements not be tailored to Compton, but that they instead be appropri-
ate for application in any school district. Implementation of our recommendations, as listed in the recov-
ery plan, should enable Compton USD to perform on a par with other districts in the state.
Our reviewers, exercising their best professional judgement, determined how many and which sites
should be visited in order to gather data and provide supporting information for each finding. Each of
our findings identifies the conditions we found and our recommendations are designed to correct any
deficiencies noted and to enable the district to sustain the corrective action.
Study Team
Ron Bennett, Vice President of SSC
Ken Hall, SSC President
Curt Pollock, SSC Director of Management Consulting Services
Bob Blattner, SSC Director
Fred Good, Principal, PJHM Architects Southwest, Inc.
Benjamin Dolinka, Vice President, David Taussig and Associates (DTA)
Arturo Taboada, Luster Construction Management
Greg Norman, Chief Operating Officer/Executive Vice President
Facilities Management Introduction i
Study Guidelines
We have divided the assessment and recovery plan into several sections to better represent the categories
of findings noted and to facilitate the development of cohesive recovery steps. Each of the area group-
ings includes assessment elements that, in our professional judgement, pertain to that general area of our
investigation. In the end, all of these areas and individual elements are inescapably interrelated; the
findings and recommendations for individual elements must be taken together when evaluating progress.
For each individual assessment element we have formulated and provided a standard and a description
of the measurement tools we used to evaluate progress toward that standard. We then completed the field
work necessary to evaluate progress, develop findings, and determine the recommendations we believe
must be implemented to complete recovery plan. Our investigation included substantial field work by
professional experts qualified to evaluate each of the areas and elements of the project. Evaluation of
elements which were common to many schools entailed the use of judgmental and/or stratified samples
which we believe were sufficient to support the conclusions we reached.
In many areas we found that substantial progress had been made. We have detailed the success we found
equally as diligent as the deficiencies. We found the majority of the people we worked with in Compton
to be dedicated to the performance of their duties. They were cooperative and helpful as we added our
requests for their time and talents to their workload. In some cases, we found people who were not
representative of this group of dedicated people and who will require significant redirection if they are to
become facilitators rather than barriers to progress.
Our assessments of how much progress has been made and whether or not it is sustained are to some
extent subjective; however, we believe our judgements are supported by the factual evidence we re-
viewed and reported. It is, however, certain that substantial progress has been made in the past two years
by the current leadership team. Nearly all of the areas in which we found that substantial sustained
progress had been made had shown that improvement during the tenure of the current leadership team. It
is perhaps beyond the scope of this report to comment on the necessity of maintaining the momentum
established by the current leadership team. However, it is important that we note that the intangible as
well as the tangible aspects of leadership that have facilitated the current improved situation will be
essential to moving forward to a full recovery.
Summary of Findings and Recommendations
Our review of the conditions related to facilities and safety in Compton Unified School District required
us to review 104 specific assessment elements in 11 functional areas. After our evaluation we rated each
area using the following rating format which was supplied by FCMAT.
• Fully Implemented - Sustained
• Fully Implemented - Substantially
• Partially Implemented
• Not Implemented
We found that 15 assessment elements were Fully Implemented - Sustained. These elements have
reached a satisfactory or better level of performance and, in our judgement, this level can be sustained
without extraordinary intervention.
We also found that 22 assessment elements were Fully Implemented - Substantially. These elements
appeared to have attained the standard at the time of our review, but the support structure we believe
ii Facilities Management Introduction
necessary to ensure they remain at that level was not in place.
There were 43 assessment elements that were Partially Implemented. These elements will require further
action before they can be considered Fully Implemented.
We found that 24 of the assessment elements were Not Implemented.
The following recommendations have been drawn from the 11 facilities and safety functional areas.
These recommendations generally characterize the nature of deficiencies found in the district. Although
we have noted deficiencies, it is important to point out that significant progress has been made during
the past two years.
School Safety
• All buildings and grounds staff, Plant Managers, and employees should receive in-service training
on hazardous substances in their work area at the time of their initial assignment and whenever a
new hazard is introduced into their work area. Pursuant to Code of Regulations, Title 8, Section
5194 (e) (1) (A), a complete list of hazardous substances must be provided within the written
hazard communication program, preferably with an indication of the work area where the sub-
stances are found. Outside contractors should be informed of hazardous substances that are
present on the site. It is the contractor’s responsibility to disseminate this information to their
employees and subcontractors.
• All buildings should be inspected periodically to ensure compliance with fire codes. Eighty
percent (80 percent) of the sites visited had the appropriate fire extinguishers existing in each
building. All current inspection information was available and on file. Approximately 20 percent
of the sites investigated did not have appropriate fire extinguishers or the current inspection
information available.
• All students and employees should continue to receive regular instruction regarding emergency
plans. At least one staff member at each school site should hold a valid certificate in first aid and
cardiopulmonary resuscitation.
Facility Planning
• The District should retain professional consulting services to develop a long-range school facili-
ties master plan. The long-range school facilities master plan should project student enrollment
and identify school facility needs on an annual basis for a period of fifteen (15) to twenty (20)
years.
• The District should create a facility planning committee. Members of the committee should
include District staff (e.g., Director of Facilities, principals, teachers, etc.) City staff (e.g., Director
of Planning, Planning Commissioner, Director of Public Works, etc.), parents, members of the
community, and District consultants (e.g., financial consultant, architect, demographer, etc.).
Facilities Improvement and Modernization
• All facilities department staff should receive training to ensure that there is uniform understanding
of State Program regulations and how they specifically apply to applications for funding for
CUSD.
• All Facilities Department staff should participate in professional training related to project and
construction management. It would be ideal if this training could be uniform for all staff.
• In order to ensure that distractions to the instructional program at any given site being modernized
Facilities Management Introduction iii
or receiving substantial facility additions, at a minimum, the CUSD should consider the following
factors related to the provision and use of an interim housing plan:
a.Include the site level administrator/s in discussions focusing upon construction phasing plans
and the need for the provision and placement of interim housing.
b.Make a consistent commitment to providing uniform communication among all involved
parties relative to project scheduling elements at each respective site.
c.Improved adherence to project schedules will minimize the effectiveness of interim housing
plans. It is acknowledged that this requires improvement in the construction administration
phase of the project and that the project architect, the general contractor’s representative, the
District construction representative, and other responsible parties will need to operate
through a more cohesive approach toward project and construction management.
• In order to ensure the use of furniture and equipment funding in ways which serve to better
facilitate the delivery of instruction and promote the effectiveness of educational programs and
student learning, it is suggested that CUSD implement the following:
a.Furniture and equipment expenditure proposals should be developed by a site-based group.
The development of these proposals should be managed by a site-level administrator/s.
b.All site-based proposals for the expenditure of furniture and equipment funds should be
reviewed and ultimately approved for implementation by a District-level oversight committee
which includes representation from the respective school site, the District’s instructional
services division and the District’s facilities services department.
Construction Of Projects
• The CUSD needs to better review plans and specifications prepared by their project architects/
engineers prior to bidding and contract award to ensure their completeness, accuracy and appro-
priateness. Any required changes to plans and/or specifications need to be incorporated prior to
award of contract.
Compliance with Public Contracting Laws and Procedures
• To improve the “bid-ability” of plans and specifications for future projects it is suggested that the
CUSD consider the following strategies:
a.Prior to considering the establishment of a bid schedule for a respective construction project,
the CUSD should conduct coordination meetings between the project architect, the architect’s
engineering consultants and a CUSD representative(s). This meeting/s should serve to ana-
lyze and determine the quality and completeness of plans and specifications relative to
program needs and project budget. Revisions should be directed and made as required, as a
result of this meeting(s).
b.The District should consider the completion of a construct-ability review of each project’s
plans and specifications prior to the establishment of a bid schedule for each project. This
would clarify issues in advance of bidding and result in fewer change orders and attendant
cost over-runs.
Special Education Facilities
Due to the varying needs and evolving enrollment of special education students, it appears that the
locations for special education classrooms and programs is provided, to some degree, on a “transient”
basis. In some instances it appeared that space was “created” to accommodate special education stu-
dents, but that this space was not always suitable in comparison to program and student needs.
iv Facilities Management Introduction
Implementation of Class Size Reduction
The CUSD has, for the most part, implemented Class Size Reduction in spaces approximating 960
square feet. In some instances classes are being conducted in teaching stations that do not meet the
California Department of Education suggested areas. However, given the ongoing discussions which are
occurring throughout the state relative to suggested spaces for CSR vs. required spaces for CSR (espe-
cially in consideration of SB 50 legislative regulation development and the fiscal impacts associated
with space allocations for CSR implementation), it is suggested that any determination of the CUSD’s
adherence to CSR “standards” for implementation be postponed until a clear direction has been provided
through the State Legislature, the California Department of Education and/or the State Allocation Board-
Office of Public School Construction.
Facilities Maintenance and Custodial
• There is a great need for quality personnel. The district needs to recover from the previous hiring
practices of finding people jobs without regard to qualifications. This was most noted in the
maintenance of the schools, mainly the plant managers. Some functions appeared to be over-
staffed but under-skilled.
• Of the personnel interviewed, the majority needed training. The maintenance people, in particular,
needed training at their school sites for how to properly handle certain chemicals and basic clean-
ing practices and this was not limited to bathrooms.
• The area of maintenance work orders needs significant improvement. Consistency in the assign-
ment of priorities to work orders was lacking. Work orders reviewed did not have sections com-
pleted that reflected supplies used or time on task, as a result, neither time nor materials could be
accounted for.
• The district needs to establish consistent equitable procedures for providing maintenance services
to schools. It seems that the school that shouts the loudest and complains the most gets the quick-
est action. The squeaky wheel theory in action. This has caused great discrepancies in the quality
of the various school facilities. While some had well kept sites due to continuous complaints,
others were left waiting for basic maintenance needs.
• Employee accountability needs to be improved. Rank and file employees are not held accountable
for their actions or lack thereof. Some employees have the attitude that they have a job and no
matter how poor their performance, they cannot be fired. Other employees who are doing an
outstanding job do not get credit for what they do because the lack of accountability also causes
an inability to recognize excellence.
Instructional Program Issues
• Approximately 50 percent of the buildings inspected had malfunctioning or non-functioning
heating and ventilation systems. Approximately 40 percent had poor lighting. These two deficien-
cies have a major impact on instruction and must be corrected immediately.
• It is extremely difficult to assess the degree to which facilities within the CUSD reflect the stan-
dards and expectations established by the community. One of the most significant challenges
which exists within the CUSD is the tremendously inconsistent level of standards and expecta-
tions found within various areas of the district and its diverse constituency. There appears to be an
“arbitrary” and inconsistent set of standards and expectations which exist. It is believed that this
inconsistency is a major potential impediment toward the development and implementation of a
District Facilities Master Plan which should lead to widespread improvements within the
District’s instructional program and the learning outcomes of students.
• The district will need to actively manage the technology planning process if progress is to be
Facilities Management Introduction v
made. The technology plan specifies that the plan is for 1997-2002, but as 1999 approaches, it has
still not been finalized and adopted. The plan needs to be completed and adopted. Additionally,
the plan does not include the substantial upgrades which must be made to administrative com-
puter systems, nor is there an adequate plan to finance the needed improvements.
Community Use of Facilities
• The CUSD implementation of its Civic Center obligations is exceptional. Controls are numerous,
beginning with right-of-refusal given to site principals. Multiple checkpoints at each step ensure
compliance for such crucial items as insurance documents. Applications are first completely filled
out in quadruplicate at the site in question with principal’s approval and all required insurance
documentation. The request and supporting documentation is sent to the district office, where
three signatures are required for approval (including the facilities director and the CBO) and then
faxes are sent to the CUSD public safety department, the operations department, and the actual
school site. A single district staff member maintains records in a binder dedicated to that purpose.
All payments are made directly to CUSD’s fiscal department.
Communications
• Both for implementation and communications purposes, all staff, particularly site administrators,
needs to be more actively involved in the communication of standards and plans. This communi-
cation should not be the responsibility of the facilities department. Once standards and plans are
devised, complete distribution to all staff should become one of the responsibilities for the new
Public Information Officer.
vi Facilities Management Introduction
1.1 School Safety – CDE Civil Defense and Disaster Planning Guide
Legal Standard
All school administrators should be thoroughly familiar with the California Department of Education,
Civil Defense and Disaster Planning Guide for School Officials, 1972. [EC 32000-32004, 32040, 35295-
35297, 38051, 38132, 46390-46392, 49505, GC 3100, 8607, CCR Title 5 §550, 560, Title 19 §2400]
Sources and Documentation
1. Board Policy
2. Emergency Planning Procedures Section of District and School Portfolios
3. Copy of Emergency Preparedness Handbook
4. Visible Building Evacuation Plans
5. Emergency Exit Signage
6. School Building Disaster Plan
7. Evidence of Training of School Site Students and Staff
8. First Aid Kits
9. Management Resources
a. CDE Program Advisories
0224.94 Contingency Planning for School Campus Emergencies, CIL: 93/94-04
b. Governor’s Office of Emergency Services
Standardized Emergency Management System (SEMS) Guidelines, March 1995
Findings
1. All of the sites reviewed had the appropriate Civil Defense and Disaster Planning materials avail-
able.
2. All sites possessed a thorough comprehension of the legal aspects, responsibilities and require-
ments for disaster preparedness. These sites also included a disaster preparedness plan within their
overall “Comprehensive Safety Plan.”
3. Evacuation plans and exit signages were visible, with training and drill procedures in place.
Recommendations and Recovery Steps
Recommendations
1. Continue monitoring the annual update/revision of the “Civil Defense and Disaster Planning”
portion of the comprehensive safety plans at the district sites to ensure compliance.
2. As modernization or improvement funds become available, implement upgrades to exit signage.
3. Continue employee training so employees become more proficient in first aid.
4. Continue regular disaster preparedness exercises at school sites.
5. Continue community involvement.
6. Replentish supplies.
Facilities Management Assessment and Recovery Plan 1
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
2 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.2 School Safety – Appropriate Security Devices in Buildings
Legal Standard
The district includes the appropriate security devices in the design of new buildings as well as in mod-
ernized buildings. [EC 32020, 32211, 35294-35294.9, 39670-39675]
Sources and Documentation:
1. District Design Standards
2. Observation of Newly Constructed Buildings
3. Observation of Recently Modernized Buildings
4. Discussions with Facilities Staff
5. Discussions with Buildings and Grounds/Custodial Staff
6. Discussions with Site Supervisor/Support Staff
7. Management resources:
a. CDE Publications
Safe Schools: A Planning Guide for Action, 1995
b. CSBA Publications
Protecting Our Schools: Governing Board Strategies to Combat School Violence, 1995
Findings
1. Current district design guidelines and procedures incorporate appropriate security devices within
the design of new and modernized facilities.
2. Of the sites reviewed, those that were recently renovated were in general conformance with this
district’s design standards.
Recommendations and Recovery Steps
Recommendations
1. Annually review district design standards to ensure the continued incorporation of security devices
meets the various needs of the district.
2. Continue incorporating security devices as newly constructed and modernized facilities are com-
pleted.
3. Establish priority list of sites related to security issues in order to maximize cost/benefit relation-
ship when installing security devices.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 3
➤
0 1 2 3 4 5 6 7 8 9 10
1.3 School Safety – Plan for Protection of People and Property
Legal Standard
Demonstrate that a plan of security has been developed, which includes adequate measures of safety and
protection of people and property. [EC 32020, 32211, 35294-35294.9, 39670-39675]
Sources and Documentation:
1. Board Policy
2. Comprehensive Safety Plan
3. Intrusion Alarm system
4. Exterior Lighting
5. Perimeter Access and Fencing
6. Visitor’s Log
7. Trespassing Signage
8. Key Issuance Procedures
9. Management Resources
a. CDE publications
Safe Schools: A Planning Guide for Action
b. CSBA Publications
Protecting Our Schools: Governing Board Strategies to Combat School Violence, 1995
Findings
1. Current district design standards incorporate appropriate security devices within the physical
design of new and modernized facilities.
2. The typical remaining sites have developed campus security procedures which are consistent with
the goals and objectives of the comprehensive safety plan.
3. The majority of facilities have secure campus perimeters (campus fencing) and buildings (visitor
registration, identification tags and patrols of places used for congregating and loitering) discour-
aging outsiders from trespassing.
4. Buildings and grounds staff and the plant managers attempt to discourage vandalism and graffiti
by immediately covering and repairing the afflicted area.
5. The principal (or designee) typically controls access to school keys and inventory stock, and keys
are only issued to employees who regularly need them to carry out the normal activities of their
position.
6. Most sites have instituted anonymous crime reporting systems, analysis of school crime incidents,
and collaborate with local law enforcement.
Recommendations and Recovery Steps
Recommendation
1. Vendors and contractors shall be required to wear badges and identify workers.
4 Facilities Management Assessment and Recovery Plan
Recovery Steps
The district’s plan of security shall include strategies and methods for at least the following:
1. Secure the campus perimeter and school facilities in order to prevent criminal activity. These
strategies shall include an analysis of the building security system, lighting system and campus
fencing.
2. Develop procedures to ensure unobstructed views and eliminate blind spots caused by doorways
and landscaping.
3. Secure buildings from outsiders and discourage trespassing.
4. Control access to keys and other school inventory.
5. Detect and intervene with school crime.
6. Train all staff in building and grounds security procedures.
These procedures shall be regularly reviewed and updated in order to reflect changed circumstances and
to access progress in achieving safe school objectives.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 5
➤
0 1 2 3 4 5 6 7 8 9 10
1.4 School Safety – Restrictions on Flammable and Toxic Materials
Legal Standard
To ensure that the custodial and maintenance staff are regularly informed of restrictions pertaining to the
storage and disposal of flammable or toxic materials. [EC 49341, 49401.5, 49411, F&AC 12981, H&SC
25163, 25500-25520, LC 6360-6363, CCR Title 8 §5194]
Sources and Documentation
1. Board Policy
2. Hazard Communication Program
3. Availability of MSDS Copies
4. Evidence of Training Programs or Sessions
5. List of Hazardous Substances on Site
6. Appropriate Labeling on Pipes and Storage Areas
7. Contractor’s Notification
Findings
1. Most sites had the appropriate labeling and material safety data sheets (MSDS) available.
2. A few of the sites visited were in the process of periodic updates and the information, though
available, was not current.
3. Variances with the availability of the information were predominantly due to the on site plant
managers assessment of competing priorities.
Recommendations and Recovery Steps
Recommendations
1. All buildings and grounds staff, plant managers, and employees should receive in-service training
on hazardous substances in their work area at the time of their initial assignment and whenever a
new hazard is introduced into their work area.
2. Pursuant to Code of Regulations, Title 8, Section 5194 (e) (1) (A), a complete list of hazardous
substances must be provided within the written hazard communication program, preferably with
an indication of the work area where the substances are found.
3. Outside contractors should be informed of hazardous substances that are present on the site. It is
the contractor’s responsibility to disseminate this information to their employees and subcontrac-
tors.
4. As noted in Std. 1.11, the district should develop a written hazard communication program in
accordance with the California Code of Regulations, Title 8, Section 5194.
5. District should work closely with the fire department and environmental agencies.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
6 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.5 School Safety – Documented Process for Key Control
Professional Standard
The district has a documented process for the issuance of master and sub-master keys. A district-wide
standardized process for the issuance of keys to employees must be followed by all district administra-
tors.
Sources and Documentation
1. Board Policy
2. Key control cards
3. Site observations
4. Interviews with site administrators
Findings
1. The current Board policy 3517(a), which is undated, states that the principal is responsible for all
keys at the school site. The principal shall set up a key control system with a record of the number
of each key filed. The loaning of the master keys is prohibited.
2. Of the sites visited, no uniform system of key controls was in place. One school had small manila
envelopes with individual room keys that were picked up in the morning and returned in the
afternoon. Other schools had assigned the keys to each teacher at the start of the school year.
Another had a keyboard that had hooks with keys on them for all of the rooms.
3. There was no consistency among the sites for issuing keys for substitute teachers. One campus
had one of the plant staff escort the substitute to the room. Another had the substitute sign for the
key. A third site had the substitute take the key from the board once it was signed for by the
substitute.
Recommendations and Recovery Steps
Recommendation
1. Standardize key control policy for all school sites.
Recovery Steps
1. Revise existing Board policy stating specifically which administrators in the district are allowed to
issue, make and inventory keys for each site including the district administrative facilities.
2. Buy locking key boxes for all school sites and require their use.
3. Establish signout card system for all keys stating who is being issued a key, which door it opens,
who authorized the issuance of the key and the date of issuance.
4. Only allow site administrator to carry grand masters.
Standard Implemented: Not
Implementation Scale:
Facilities Management Assessment and Recovery Plan 7
1.6 School Safety – Monitoring of Bus Loading/Unloading Areas for Safety
Professional Standard
Bus loading and unloading areas, delivery areas, and parking and parent loading/unloading areas are
monitored on a regular basis to ensure the safety of the students, staff and community. Students, employ-
ees and the public should feel safe at all times on school premises.
Sources and Documentation
1. Board Policy
2. On-site observation during regular school hours
3. Job descriptions for school bus monitors
4. Bus schedules and routes
Findings
1. Board policy 3541, as adopted August 31, 1982, “asks” the superintendent to administer the
transportation program. The first guideline for the superintendent is to “provide for maximum
safety of pupils.”
2. Board policy 3541.22(a) assigns the responsibility of the orderly conduct of the students to the
school bus driver. During the site observations made on September 8 and 9, numerous unsafe bus
loading and unloading practices were observed which included:
• Children crossing a busy four-lane highway unescorted after school. There was no attendant
or crosswalk available for the children to cross safely.
• Parents parked in the bus loading zone, and in some cases double-parked, requiring chil-
dren to weave between cars to get to parent’s car.
• Buses were required to honk horns at parents parked in bus loading zones and received
various levels of cooperation.
• Regardless of the posted speed limit, many of the drivers exceeded the speed limit even
though children were obviously present.
• Bus monitors or teachers were observed only when the special-education buses were
loading or unloading.
• Some buses would use yellow flashing lights instead of red flashing lights when they were
waiting at a bus stop. Regardless of what lights were displayed, most cars ignored them
and passed to unload their children.
3. Regarding the parking for parents and community during school hours, the following challenges
were observed:
a. At some school sites, parking is almost nonexistent. Parents are either required to park on the
street or in a small parking lot that is normally occupied by employees. The small parking lots
created major congestion during student pick-up hours requiring the campus police to close
the incoming gate as well as provide traffic control for incoming buses.
b. Some campuses lock the parking lots so that vehicles cannot be stolen or vandalized requir-
ing district police or campus security to unlock the gates during school hours.
Recommendations and Recovery Steps
Recommendations
1. Have monitored crosswalks for all sites with K-8 students.
8 Facilities Management Assessment and Recovery Plan
2. Establish a safe zone for the buses to enter and exit the loading zones.
3. Expand available parking at some campuses.
.
Recovery Steps
1. Work with the City of Compton to have additional crosswalks painted on the streets and signage
erected adjacent to the school zones.
2. Assign or hire district staff to escort students across the streets.
3. Have the monitors keep records on violators of speed limit and crosswalk violation for reporting
to the proper legal authority.
4. Request assistance from the police in ticketing violators.
5. Set out orange cones 30 minutes prior to the scheduled arrival of school buses. This will deter
parents from obstructing the loading area.
6. At least one school employee should monitor the bus loading area prior to and during the loading
of the buses.
7. Use some of the surplus, undeveloped land, to create additional overflow parking.
8. Provide drop off and pick up areas at every site.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 9
➤
0 1 2 3 4 5 6 7 8 9 10
1.7 School Safety – Installation and Operation of Outside Security Lighting
Professional Standard
Outside lighting is properly placed and monitored on a regular basis to ensure the operability/adequacy
of such lighting to ensure safety while activities are in progress in the evening hours. Outside lighting
should provide sufficient illumination to allow for the safe passage of students and the public during
after hour activities. Lighting should also provide security personnel with sufficient illumination to
observe any illegal activities on campus.
Sources and Documentation
1. Board Policy
2. On-site observation during regular school hours
Findings
1. Board Policy 3517, as adopted August 31, 1982, states: “Buildings constitute one of the greatest
investments of the school district. It is in the best interest of pupils and taxpayers to protect that
investment adequately. It continues, “Security also means protecting against vandalism and
burglary.” Proper lighting is an integral part of security.
2. The majority of the school sites visited had insufficient lighting not to mention the need for
additional lighting specifically for security during the evening hours.
3. Many of the hallways and courtyard areas have minimal lighting usually limited to a single light
bulb behind a faded plexiglass cover in the ceiling. Some of the overhead lights were in need of
repair or replacement of the plexiglass covers. Other had no bulbs in them.
Recommendations and Recovery Steps
Recommendations
1. Replace and maintain existing hallway lighting that does not provide sufficient illumination.
2. Install additional exterior lighting in all hallways, courtyards, between buildings and fields.
3. Use battery operated units where wiring is not in place.
Recovery Steps
1. Replace all hallway lighting that consists of standard lightbulbs with more modern lighting such
as halogen bulbs or lighting as mentioned in Std. 8.1.
2. Replace all hallway light fixtures with clear vandalproof covers to allow for full illumination of
the hallways.
3. Add lighting to preventive maintenance checklist for regular replacement and verification of
proper lighting in all campus areas.
4. Install new lighting in all courtyards that will allow for security during after school activities and
security surveillance.
10 Facilities Management Assessment and Recovery Plan
5. Install additional lighting in all hallways that have not been properly illuminated by replacing
existing light fixtures.
6. Install lighting between buildings such as portable classrooms for security purposes.
7. Increase lighting in open field areas to reduce possibility of loitering and allow security easier
surveillance.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 11
➤
0 1 2 3 4 5 6 7 8 9 10
1.8 School Safety – Graffiti and Vandalism Abatement Plan
Professional Standard
The district has a graffiti and vandalism abatement plan. The district should have a written graffiti and
abatement plan that is followed by all district employees. The district provides district employees with
sufficient resources to meet the requirements of the abatement plan.
Sources and Documentation
1. Board Policy
2. Copy of graffiti and vandalism plan
3. On-site observation during regular school hours
Findings
1. Board policy 5131.5, adopted April 27, 1982, states, “It is the intention of the governing board to
seek redress of any individual in the amount of the damage for any act of vandalism committed by
that individual, or from the parents of that individual if a minor.”
2. The Facilities and Grounds Handbook gives graffiti removal the highest priority for the mainte-
nance teams. Graffiti removal and vandalism are considered an emergency and are to be reported
to the security office as soon as possible. Included in the handbook is Bulletin No. 98/99-1004
dated November 5, 1997, which states that the high schools and middle schools will receive
graffiti abatement on Monday, Wednesday and Friday without request. Elementary schools and
administrative offices must request the removal of extensive graffiti.
3. One of the main expectations of school plant managers is the daily battle with graffiti. While the
plant managers and staff are expected to keep graffiti to a minimum, not all staff are given the
appropriate equipment to meet the challenge.
4. During the site observations, the large areas of graffiti had been painted over while the smaller
areas on hallway columns, sidewalk rails and doorjambs were not. Also, with the emphasis placed
on abatement and not on the appearances of the schools, many of the abatements were using
different colors of paint.
Recommendations and Recovery Steps
Recommendations
1. Provide school plant managers with adequate supplies, equipment and training to manage the
minor graffiti abatement.
2. Provide adequate storage areas for graffiti abatement materials and equipment.
3. Consider graffiti resistant materials during construction and modernization.
Recovery Steps
1. Plant managers receive all supplies and equipment, such as sandpaper, scrapers, brushes or rollers,
and paint necessary to keep up with the graffiti at the campus.
12 Facilities Management Assessment and Recovery Plan
2. Plant managers receive inservice training on all aspects of graffiti abatement to receive a better
understanding of how to reduce abatement time.
3. Included in the evaluation of the plant manager is the ability to keep up with the graffiti problem
at their site.
4. Storage facilities with locking mechanisms and proper ventilation should be made available at
each school site.
5. Inventories of supplies used and equipment purchased must be kept by plant managers and veri-
fied by the supervisor or site administrator.
6. Included in the evaluation of the plant manager is the ability to keep up with the graffiti problem
at their site and maintaining and adequate inventory of abatement materials on hand at all times.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 13
➤
0 1 2 3 4 5 6 7 8 9 10
1.9 School Safety – School Site Emergency Procedures Plan
Legal Standard
Each public agency is required to have on file written plans describing procedures to be employed in
case of emergency. [EC 32000-32004, 32040, 35295-35297, 38132, 46390-46392, 49505, GC 3100,
8607]
Sources and Documentation
1. Board Policy
2. Emergency and Disaster Preparedness Plan
3. Evidence of Disaster Preparedness Drills
4. First Aid Kits
5. Management Resource
a. CDE Program Advisories 0224.94 Contingency Planning for School Campus Emergencies,
CIL:93/94-04
Findings
1. Eighty percent (80 percent) of the sites visited had on file complete written plans describing
procedures to be employed in case of emergency.
2. All of the plans incorporated personnel duties, signal process and general procedures to be fol-
lowed to protect the students and staff on the school site.
3. The plans typically are developed by an emergency preparedness committee and require that
everyone on site (parents/community, students and staff) be responsible and involved in the safety
process.
4. Approximately 20 percent of the sites investigated did not have portions of their plan completed.
5. The incomplete plans required minor editing to an existing plan predominantly due to recom-
mended committee changes or the reproduction of the plan itself for distribution.
Recommendations and Recovery Steps
Recommendations
1. A checklist of required plans and response procedures should be established for all district sites to
facilitate administrative follow-up and to ensure that all district sites have the completed plan in
place prior to the start of the school calendar year. The checklist should include:
a. Administrator responsible for the implementation of the plan.
b. What are the steps to be followed in an emergency.
c. Specific response procedures for various emergencies.
d. Communication procedures.
2. In order to saves lives and protect property, school districts are mandated to formulate individual
civil defense and disaster preparedness plans. The district and site plans shall address at least the
following situations:
14 Facilities Management Assessment and Recovery Plan
a. Fire on or off school grounds which endangers students.
b. Natural or man-made disasters.
c. Bomb threat or actual detonation.
d. Attack or disturbance by individuals or groups.
3. Education Code Section 35292-35297 require the establishment of an earthquake emergency
procedure system for each school building with more than one classroom or with a capacity of 50
or more students. This procedure system shall include at least the elements listed below, and
should be incorporate within each sites comprehensive emergency and disaster preparedness plan.
a. The school building disaster plan.
b. A “drop” procedure for students and staff members.
c. Protective measures to be taken before, during and after an earthquake.
d. A training program to ensure that all students and staff are aware of, and properly skilled in,
the earthquake emergency procedure system.
4. Disaster preparedness exercises shall be held regularly at each school site and shall demonstrate
how safety procedures may be applied to various types of emergencies. All students and employ-
ees shall receive instruction regarding emergency plans.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 15
➤
0 1 2 3 4 5 6 7 8 9 10
1.10 School Safety – Conduct of Required Fire Drills
Legal Standard
Each elementary and intermediate school at least once a month, and in each secondary school not less
than twice every school year, shall conduct a fire drill. [EC 32000-32004, 32040, CCR Title 5 §550]
Sources and Documentation
1. Board Policy
2. Visible Building Evacuation Plan
3. Evidence of Fire Drills
4. Fire Life-Safety Devices
5. Emergency Exit Signage
6. First Aid Kits
Findings
1. All of the sites visited confirmed each elementary and intermediate school at least once a month,
and in each secondary school not less than twice every school year, conducted a fire drill.
2. Each site had identified general procedures and assembly areas.
Recommendations and Recovery Steps
Recommendation
1. Continue conducting fire drills as noted above.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
16 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.11 School Safety – Knowledge of Chemicals and Potential Hazards
Legal Standard
Maintenance/custodial personnel have knowledge of chemical compounds used in school programs that
include the potential hazards and shelf life. [EC 49341, 49401.5, 49411, F&AC 12981, H&SC 25163,
25500-25520, LC 6360-6363, CCR Title 8 §5194]
Sources and Documentation
1. Board Policy
2. Hazard Communication Program
3. Availability of MSDS Copies
4. Evidence of Training Programs or Sessions
5. List of Chemical Materials and Shelf Life
6. Observation of Laboratories
7. Interviews with Maintenance/Custodial Staff
Findings
1. During the classroom observations in the high schools, some sites had appropriate labeling and
material safety data sheets (MSDS) available. However, some of the containers were unmarked,
and therefore, it was impossible to determine the content and shelf life.
2. Both sites visited were in the process of starting the school year, and information was not readily
available.
3. Variances with the availability of the information were predominantly due to the on-site plant
manager’s assessment of competing priorities and the fact that the faculty seems to be responsible
for the management of laboratory materials.
Recommendations and Recovery Steps
Recommendations
1. All buildings and grounds staff, plant managers, and faculty should receive in-service training on
chemical compounds and hazardous substances in their work area at the time of their initial assign-
ment and whenever a new hazard is introduced into their work area. Additional training on the
methods to lessen or prevent exposure to hazardous substances is as follows:
a. Well-delineated work practices.
b. Use of protective equipment.
c. Instruction on how to read labels and Material Safety Data Sheets (MSDS) files.
d. The steps the district has taken to lessen or prevent exposure to hazardous substances.
2. The district should develop a written hazard communication program in accordance with the
California Code of Regulations, Title 8, section 5194 that requires all school districts to have a
written hazard communication program addressing each of the program categories enumerated
below.
a. Material Safety Data Sheet (MSDS) List of Hazardous Substances.
b. Hazardous Nonroutine Tasks.
c. Hazardous Substances in Unlabeled Pipes.
Facilities Management Assessment and Recovery Plan 17
d. Employee Information and Training including:
• An overview of the requirement of California’s Hazard Communication Regulation (Code of
Regulations, Title 8, Section 194), including employee rights described therein
• The location, availability and content of the district’s written hazardous communication
program
• Information as to any operations in the employees’ work area where hazardous substances
are present
• The physical and health effects of the hazardous substances in the work area
• Techniques and methods of observation that may determine the presence or release of
hazardous substances in the work area
• Methods by which employees can lessen or prevent exposure to these hazardous substances,
such as appropriate work practices, use of personal protective equipment and engineering
controls
• Steps the district has taken to lessen or prevent exposure to these substances
• Instruction on how to read labels and review the MSDS for appropriate information
• Emergency and first aid procedures to follow if exposed to the hazardous substance(s)
3. The written hazard communication program should be available upon request to all employees and
their designated representatives. (Code of Regulations, Title 8, Section 5194)
4. Teachers shall instruct students about the importance of proper handling, storage, disposal and
protection when using any potentially hazardous substance.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
18 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.12 School Safety – Inspection and Correction of Unsafe Conditions
Legal Standard
Building examinations are performed, and required actions are taken by the governing board upon report
of unsafe conditions. [EC 173679(a)]
Sources and Documentation
1. Board Policy
2. Work Control Emergency Request Logs
3. Emergency Work Completion Tags
4. Interviews with Maintenance/Custodial Staff
Finding
1. No school buildings currently used by the district for K-12 educational purposes have been identi-
fied by the Department of General Services, a licensed structural engineer, or a licensed architect,
as unsafe for school use.
2. In cases where the buildings were identified as unsafe, the district has abandoned the building and
labeled it for demolition and replacement.
3. Plant managers and site administrators pointed out that the facilities department has become more
responsive to site requests, and for the most part, additional funding seems to be the predominant
problem.
Recommendations and Recovery Steps
Recommendations
1. Continue utilizing information acquired from the examination and reports developed pursuant to
Education Code section 17367(a), to maintain and/or establish a system of priorities to repair,
replace or reconstruct unsafe district school buildings.
2. Ensure that the district has submitted the appropriate applications to OPSC and is ready to proceed
expeditiously as funds become available.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 19
➤
0 1 2 3 4 5 6 7 8 9 10
1.13 School Safety – Emergency Fire and Police Access to Campuses
Legal Standard
Each school which is entirely enclosed by a fence or partial buildings must have a gate of sufficient size
to permit the entrance of ambulances, police and fire fighting equipment. Locking devices shall be
designed to permit ready entrance. [EC 32020]
Sources and Documentation
1. Site Observation of Gates and Locking Devices
2. Interviews with Maintenance/Custodial Staff
3. Interviews with Fire Department Personnel
Findings
1. All district sites inspected had access gates of sufficient size to permit the entrance of emergency
vehicles, equipment and apparatus.
2. The gates are designed to permit the ready entrance by the use of chain or bolt-cutting devices.
Recommendations and Recovery Steps
Recommendation
1. Continued compliance with Education Code Section 32020, and conformance review with law
enforcement and fire protection agencies.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
20 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.14 School Safety – Sanitation is Maintained and Fire Hazards are Corrected
Legal Standard
Sanitary, neat and clean conditions of the school premises exist and the premises are free from condi-
tions that would create a fire hazard. [CCR Title 5 §633]
Sources and Documentation
1. Board Policy
2. Copy of graffiti and vandalism plan
3. On-site observation during regular school hours
Findings
1. Board policy 3510, adopted August 31, 1982, states “An effective educational program requires
clean, healthful, safe, businesslike, and attractive physical facilities. The maintenance and custo-
dial staff is charged with the responsibility of caring for and protecting these facilities. In order to
carry out an efficient maintenance program, the custodians must receive the cooperation of the
pupils, the teachers and administration.”
2. During the site inspections, lunch periods were not confined to specific areas on campus. This led
to lunch refuse being spread campuswide.
3. Unsafe conditions were noted during the site observations. Numerous cases of exposed hazards
were observed in areas of common student access. Hazards observed included:
a. Exposed bolts protruding from the ground next to student walkways
b. Damaged concrete covers exposing 18-inch drops to a water shutoff valve
c. An improperly manufactured 24 feet by 48 inch quarter inch metal cover over a sprinkler
valve shutoff that could not sit flat to the ground resulting in a sharp metal corner protruding
from the ground.
Recommendations and Recovery Steps
Recommendations
1. Provide on-site inservice training for all site operational personnel in the area of site safety and
cleanliness.
2. Create a safety committee of non-administrative, non-maintenance personnel to review the school
sites for safety hazards.
3. Provide incentives and recognition for clean campuses for both students and employees.
Recovery Steps
1. Develop on-site inservice training using the job descriptions and the guidelines provided in the
Facilities and Grounds handbook.
2. Supervisors will periodically review the progress site personnel are making in keeping campuses
safe and clean.
Facilities Management Assessment and Recovery Plan 21
3. Supervisors will also emphasize the area of safety and cleanliness in the employee’s annual
evaluation.
4. Establish a small committee, not exceeding eight people, to review the sites for observed safety
and fire hazards.
5. Have the committee submit a list of the hazards observed to the superintendent for review at an
administrative meeting.
6. Prioritize the hazards according to the greatest need or greatest hazard to the students and the
public.
7. Submit the list of hazards to be repaired to the maintenance department for inclusion in the next
maintenance schedule.
8. Adopt a Board Policy supporting the concept of a clean campus being a learning campus. Include
in the policy an incentive or reward for the student body to keep the campus clean.
9. Establish an annual recognition at the Board meeting for the top three clean campuses with before
and after pictures for the community to see.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
22 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.15 School Safety – Injury/Illness Prevention Program Inspections are Done
Legal Standard
The Injury and Illness Prevention Program (IIPP) requires periodic inspections of facilities to identify
conditions. [CCR Title 8 §3203]
Sources and Documentation
1. Board Policy
2. IIPP Handbook
3. Evidence of Inspections
4. Interviews with Maintenance/Custodial Staff
Findings
1. During January 1998, the district completed the Three-Year AHERA Re-inspection Report and
Injury and Illness Prevention Program (IIPP) through an independent third party. This document
was found at all sites.
2. In some cases, the staff in charge did not recognize the document by name; however, upon further
conversation and description, the documents were located.
Recommendations and Recovery Steps
Recommendations
1. Continue updating the documents as required.
2. Emphasize to all staff the importance of the document. The site administrator should know the
location, purpose and use of the document and its contents.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 23
➤
0 1 2 3 4 5 6 7 8 9 10
1.16 School Safety – Fire Extinguishers and Inspection Information Available
Legal Standard
Appropriate fire extinguishers exist in each building and current inspection information is available.
[CCR Title 8 §1922(a)]
Sources and Documentation
1. On-Site Observation of Extinguishers and Tags
2. Evidence of Inspections
3. Interviews with Maintenance/Custodial Staff
Findings
1. Eighty percent (80%) of the sites visited had the appropriate fire extinguishers existing in each
building.
2. All current inspection information was available and on file.
3. Approximately 20 percent of the sites investigated did not have appropriate fire extinguishers or
the current inspection information available.
4. The predominant portion of sites without extinguishers resulted from removal by a vendor, ac-
cording to a service agreement.
5. The servicing vendor had removed the extinguishers to inspect, re-charge or replace them.
Recommendations and Recovery Steps
Following a natural disaster or widespread fires, public services may be unavailable or overwhelmed.
Fire extinguishers are an effective tool for fire fighting in these circumstances.
Recommendations
1. Appropriate fire extinguishers should exist in each building, be visible with easy access and have
current inspection information available.
2. The extinguishers should be serviced or replaced once every two years and immediately after each
use.
3. All current or new vendors should be required to provide a back-up extinguisher while they
remove the site ones for service.
4. A master checklist of required servicing and replacement could be established for all district sites.
The maintenance department should maintain the list of all fire extinguishers, when they were last
serviced, the next scheduled service, and follow-up on this schedule. This checklist would facili-
tate administrative follow-up to ensure that all district sites have the appropriate fire extinguishers
existing in each building and have current inspection information available, prior to the start of
the school calendar year.
24 Facilities Management Assessment and Recovery Plan
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 25
➤
0 1 2 3 4 5 6 7 8 9 10
1.17 School Safety – All Exits are Free of Obstructions
Legal Standard
All exits are free of obstructions. [CCR Title 8 §3219]
Sources and Documentation
1. On-Site Observation of Exits
2. Verification of Door Operation
Findings
1. The majority of sites inspected had working door hardware and no obstruction at the fire exits.
2. A few of the sites visited were in the process of opening the new school year. As a result, condi-
tions occurred at the time of inspection that inhibited the continuous flow of safety and health
information.
3. Variances with the availability of the information were predominantly due to the on-site plant
managers assessment of competing priorities.
Recommendations and Recovery Steps
Recommendations
1. All buildings and grounds staff, plant managers, and employees should receive additional in-
service training on health and safety issues that are essential to an injury-free, productive work
place.
2. Additional training related to the arrival and departure of the staff and students, should be imple-
mented in the following areas:
a. New worker orientation.
b. Work Place Safety Training Sessions.
c. Health Training Programs.
e. Regularly Scheduled Safety Meetings.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
26 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.18 School Safety – Plan for Prevention of Campus Crime and Violence
Legal Standard
A comprehensive school safety plan exists for the prevention of campus crime and violence. [EC 35294-
35294.9]
Sources and Documentation
1. Board Policy
2. School Safety Plan
Findings
1. Every site interviewed has developed a comprehensive school safety plan.
2. A few of the sites visited were in the process of printing and/or distributing the plan.
Recommendations and Recovery Steps
Recommendations
1. Continue annual updating, training of staff and the utilization of information acquired for the plans
and reports developed pursuant to Education Code Sections 35294-35294.9, to maintain the
comprehensive school safety plan.
2. All plans must include the following key code requirements for a comprehensive school safety
plan:
a. Status of school crimes committed on district campuses during district functions.
b. Dangerous pupil notification procedures.
c. Strategies and programs for the maintenance of high levels of school site safety.
d. Access procedures for students.
e. Educational environment requirements.
f. School discipline procedure.
g. Sexual harassment policy.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 27
➤
0 1 2 3 4 5 6 7 8 9 10
1.19 School Safety – An Emergency Action Plan Exists
Legal Standard
An emergency action plan exists. [CCR Title 8, §3220]
Sources and Documentation
1. Board Policy
2. Emergency and Disaster Preparedness Plan
3. Evidence of Training
Findings
1. A review of several school sites indicated most of emergency action plans are incorporated within
each school sites comprehensive safety plan.
2. Students and employees receive regular instruction regarding emergency plans.
Recommendations and Recovery Steps
Recommendations
1. All students and employees should continue to receive regular instruction regarding emergency
plans since the continuous repetition of drills increases the likelihood of a structured response by
a trained team of staff members in the event of a crisis or emergency.
2. All emergency action plans, completed independently or in conjunction with the comprehensive
school safety plan, should include the following:
• Procedures for personnel safety and security.
• Ways to ensure smooth administrative control of operations during a crisis.
• Procedures to establish a clear, effective communications system.
• Guidelines for law enforcement involvement including specific steps for law enforcement
intervention depending upon the intensity of the crisis.
3. The district must also ensure that at least one staff member at each school site holds a valid certifi-
cate in first aid and cardiopulmonary resuscitation (CPR).
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
28 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.20 School Safety – Compliance for Under/Above Ground Storage Tanks
Legal Standard
Requirements are followed pertaining to underground storage tanks. [H&SC 25292, CCR Title 26 §477,
Title 23 § 2610])
Sources and Documentation
1. Board Policy
2. UST Removal Program
3. Deferred Maintenance Plan
4. Review of Contract Files for Certification
5. Review Local Agency Records
Findings
1. On or before December 22, 1998 the district was to replace or upgrade (to prevent leaks due to
corrosion, spills or overfills) its underground storage tanks (USTs), and equip all existing under-
ground-pressurized piping with automatic line leak detectors and a secondary containment.
2. The records are not kept in sufficient detail to determine whether the monitoring, testing, repair-
ing, and closure the UST system within the district is in compliance with the applicable provisions
of law including Health and Safety Code Section 25292, Board regulations, and the permit issued
for the operation of the tank system.
Recommendations and Recovery Steps
Recommendations
1. The district’s facilities and maintenance departments must ensure on and after January 1, 1999, no
person or agency shall deposit petroleum into an UST system unless the system meets the require-
ments of Section 25291 or subdivisions (d) and (e) of Section 25292 and related regulations
adopted pursuant to Section 25299.3.
2. The district must complete the gradual replacement and upgrade of aged USTs as funds become
available through modernization projects, deferred maintenance, or other miscellaneous funds.
3. Maintenance/custodial/cafeteria staff should continue to be trained on the general industry testing,
monitoring and inspection orders.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 29
➤
0 1 2 3 4 5 6 7 8 9 10
1.21 School Safety – Compliance with Federal AHERA Laws
Legal Standard
All asbestos inspection and asbestos work completed in the US is performed by Asbestos Hazard Emer-
gency Response Act (AHERA) accredited individuals. [EC 49410.5, 40 CFR Part 763]
Sources and Documentation
1. Board Policy
2. AHERA Inspection Reports
3. Contract Files for Accreditation
Finding
1. In some cases, the district’s complete, updated management plans for material containing asbestos
in the school site buildings were not available for inspection in the school offices.
Recommendations and Recovery Steps
Recommendations
1. The district’s complete, updated management plans for material containing asbestos in the school
buildings should always be available for inspection in the district and school offices.
2. Maintenance/custodial staff should be trained on the location, identification, proper cleaning, and
ongoing maintenance of asbestos-containing materials.
3. Maintenance and custodial staff should be trained in the removal and decontamination of small
amounts of such materials when needed to repair pipes or perform small scope projects.
4. Any extensive asbestos abatement work must be done by state certified asbestos abatement con-
tractors in compliance with state and federal standards.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
30 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.22 School Safety – Playground Equipment is Inspected and Safe
Legal Standard
All playground equipment meets safety code regulations and is inspected in a timely fashion as to ensure
the safety of the students. [EC 44807, GC 810-996.6, H&SC 24450 Chapter 4.5, 115725-115750, PRC
5411, CCR Title 5 §5552])
Sources and Documentation
1. On-Site Observation of Playground Equipment
2. Review of Maintenance Logs
Findings
1. An inspection of playground equipment at several school sites indicated that the district is in
general conformance with prevailing codes and regulations.
2. Given the age and condition of some of the playground equipment, including matting, some of the
equipment needs to be upgraded or replaced in order to meet code compliance and accessibility
concerns.
3. The gradual upgrade of existing playground sites and the installation of new equipment to mini-
mize accidents, will have a significant impact towards reducing overall district liability risk.
Recommendations and Recovery Steps
Recommendations
1. Playground equipment should be carefully selected and installed, so it minimizes accidents and
presents no unseen safety hazards. Safety of playground equipment and adequate supervision
should receive primary consideration when the playgrounds are planned or upgraded. The follow-
ing playground equipment standards should be followed:
• The play equipment should be galvanized metal structure (painted metal corrodes within five
years; wood deteriorates at the base and is a source of splinters in future years).
• No moving parts such as swings or loops on chains or overhead ladders (this minimizes part
breaking and repair).
• All installed play equipment should have safety matting of non-toxic rubber (square rubber
tiles, poured in place rubber matting, or ground rubber).
• Tan bark and sand should not be acceptable for future installations for health reasons (hides
broken glass, needles, animal feces, etc.).
• Safety matting should be glued or mechanically fastened with recessed and covered anchor
bolts.
• Edges to safety matting should be beveled to permit wheelchair access.
• Safety matting should extend 8 feet beyond the edge of play equipment.
2. The district’s facilities and maintenance departments should continue to develop and update
playground equipment standards in accordance with the above recommendations.
Facilities Management Assessment and Recovery Plan 31
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
32 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.23 School Safety – Safety of Boilers and Fired Pressure Vessels
Legal Standard
Safe work practices exist with regards to boiler and fired pressure vessels. [CCR Title 8 §782]
Sources and Documentation
1. On-Site Observation of Boilers and Fired Pressure Vessels
2. Maintenance Logs
Findings
1. Completed maintenance logs and an inspection of boiler and fired pressure vessels indicated that
the district is in general conformance with CCR Title 8: Section 782.
2. Some of the district’s boiler and fired pressure systems, primarily due to the age and condition,
need to be upgraded.
3. Plant managers are generally familiar with the appropriate work practices.
Recommendations and Recovery Steps
Recommendations
1. The district should plan for the gradual replacement and upgrade of aged boilers and fired pressure
vessels as funds become available through modernization projects, deferred maintenance, or other
miscellaneous funds. We recommend the district develop/augment its work practices and proce-
dures for boilers as follows:
• Maintenance logs contain complete descriptions of the maintenance of all system components
including sensors, controllers, actuators, etc.
• The maintenance log descriptions should include the dates of inspections, periodic preventative
maintenance and suggestions, and system/component failure diagnosis.
• The maintenance log descriptions should include procedures for the repair or replacement of
defective components.
• Ongoing training for maintenance/custodial staff should continue on the general industry safety
orders.
• On start-up dates the district should have on-site qualified field technicians to place the sys
tems in operation. Making such tests, adjustments, and changes as may be found necessary to
insure the safe and successful operation of the equipment and systems.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 33
➤
0 1 2 3 4 5 6 7 8 9 10
1.24 School Safety – Maintenance of Material Safety Data Sheets
Legal Standard
Maintenance of Materials Safety Data Sheets. [EC 49341, 49401.5, 49411, F&AC 12981, LC 6360-
6363, CCR Title 8 §5194]
Sources and Documentation
1. Board Policy
2. Hazard Communication Program
3. MSDS Documentation
4. Evidence of Training Programs or Sessions
5. List of Chemical Materials and Shelf Life
6. Observation of Laboratories
7. Interviews with Maintenance/Custodial Staff
Findings
1. Most Sites had the appropriate labeling and material safety data sheets (MSDS) available.
2. A few of the sites visited were in the process of periodic updates and the information, though
available, was not current.
3. Variances with the availability of information were predominantly due to the on site plant manag-
ers assessment of competing priorities.
Recommendations and Recovery Steps
Recommendations
1. When the district receives a hazardous substance or mixture, the district representatives shall
ensure that the manufacturer has also furnished a Material Safety Data Sheet as required by law.
In the event the MSDS is missing or incomplete, the district shall request a new MSDS from the
manufacturer and shall notify the California Occupational Safety and Health Division (Cal/
OSHA) if a subsequent completed MSDS is not received.
2. The district representative shall maintain copies of the MSDS for all hazardous substances and
ensure that they are kept up to date and available to all affected employees.
3. The district shall review each incoming MSDS for new and significant health and safety informa-
tion and disseminate this information to all affected employees.
4. Should the district elect to convert to a computerized or fax-on-demand program, the district must
ensure that up-to-date copies of the MSDS for all hazardous substances are available to all af-
fected employees. The affected employees must be trained to operate the computers or fax ma-
chines that provide access to MSDS files.
5. All buildings and ground staff, plant managers, and employees should receive in-service training
on hazardous substances in their work area at the time of their initial assignment and whenever a
new hazard is introduced into their work area.
34 Facilities Management Assessment and Recovery Plan
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 35
➤
0 1 2 3 4 5 6 7 8 9 10
1.25 School Safety – Maintenance of a Comprehensive Employee Safety Program
Professional Standard
The district maintains a comprehensive employee safety program. Employees should be aware of the
district safety program and the district provides inservice training to employees on the requirements of
the safety program.
Sources and Documentation
1. Board Policy
2. Copies of collective bargaining agreements
3. Copy of employee safety handbook
4. Interviews with sample of employees
5. Observation of employees and safe practices
Findings
1. Board policy 3516, as adopted August 31, 1982, “seeks to ensure that every employee and student
is provided safe and healthful working and learning conditions. The superintendent shall maintain
rules and regulations necessary to implement and administer all aspects of this policy.”
2. The articles regarding safety included in the collective bargaining agreements mirror the wording
of the Board policy.
3. The articles also include language regarding the participation of the unit members on the district
safety committee.
4. Throughout the policy and the agreement is an escape clause relating to the district’s financial
condition and the availability of funds to pay for safety hazards.
Recommendations and Recovery Steps
Recommendations
1. Update and expand current board policy.
2. Develop a district-wide safety committee that includes representatives from all bargaining units
and administration.
3. Create a periodic safety newsletter for distribution to employees and the public.
Recovery Steps
1. Expand current Board policy 3516 to include those circumstances that are considered safety
related.
2. Designate which circumstances must be handled immediately and cannot be ignored due to the
district’s financial condition.
3. Designate by position the district administrator responsible for meeting the Board policy require-
ments.
36 Facilities Management Assessment and Recovery Plan
4. While individual bargaining agreements may have specific representation included in the agree-
ment, the district should create a safety committee from those agreements.
5. The district should assign one administrator for coordinating the safety committee meetings as
well as following up on the recommendations made by the committee.
6. With safety being a high priority for the district, communication to the employees and the public
is critical.
7. As a part of the duties of the safety committee, require them to assist with the development of the
periodic newsletter.
8. The newsletter should include accomplishments for the past time period, planned improvements,
and the opportunity for input from the reader.
9. Subsequent issues of the newsletter should include input received and what was the outcome of
the meeting.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 37
➤
0 1 2 3 4 5 6 7 8 9 10
1.26 School Safety – Conduct of Periodic Safety Training for Employees
Professional Standard
The district conducts periodic safety training for employees. District employees should receive periodic
training on the safety procedures of the district.
Sources and Documentation:
1. Board Policy
2. Copies of agendas for training
3. Copies of materials used in training
4. Interviews with sample of employees
5. Observation of employees and safe practices
Findings
1. Board policy 3516, as adopted August 31, 1982, “seeks to ensure that every employee and student
is provided safe and healthful working and learning conditions. The superintendent shall maintain
rules and regulations necessary to implement and administer all aspects of this policy.”
2. The articles regarding safety included in the collective bargaining agreements mirror the wording
of the Board policy.
3. The articles also include language regarding the participation of the unit members on the district
safety committee.
4. Throughout the policy and the agreement is an escape clause relating to the district’s financial
condition and the availability of funds to pay for safety hazards.
5. SSC was unable to obtain specific agendas or materials used for safety training.
Recommendations and Recovery Steps
Recommendation
1. Include safety training in staff development programs during the year.
Recovery Steps
1. As a part of developing the agenda for staff development for both certificated and classified
employees, a portion should be set aside for the updates to changes in the safety program as well
as changes to state and federal regulations.
2. Include in the staff development any changes made to the district’s safety plan and how it affects
the staff and the students.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
38 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
1.27 School Safety – Conduct of First Aid Training for School Site Personnel
Professional Standard
The district should conduct periodic first aid training for employees assigned to school sites.
Sources and Documentation
1. Board Policy
2. Copies of agendas for training
3. Copies of materials used in training
4. Interviews with sample of employees
5. Observation of employees and safe practices
Findings
1. Compton USD personnel were unable to locate any Board Policies, procedures, or records of first
aid training for school site personnel.
2. SSC was unable to obtain specific agendas or materials used for safety training.
Recommendations and Recovery Steps
Recommendations
1. Develop Board Policies and procedures requiring first aid training for school site personnel.
Include in the policies and procedures specific training requirements including basic first aid, site
safety procedures, CPR and other first aid programs that the district sees as minimum require-
ments.
2. Include first aid training in staff development programs during the year.
3. Maintain records of training including names, dates, subjects, agendas, and materials used.
4. Review all records of training for currency of training and the need for retraining as necessary.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 39
➤
0 1 2 3 4 5 6 7 8 9 10
2.1 Facility Planning – Maintenance of a Long-Range Facilities Master Plan
Professional Standard
Compton Unified School District should have a long-range school facilities master plan.
Sources and Documentation
1. District documentation
Findings
1. The district does not currently have a long-range school facilities master plan.
Recommendations and Recovery Steps
Recommendation
1. The district should develop or retain professional consulting services to develop a long-range
school facilities master plan. The long-range school facilities master plan should project student
enrollment and identify school facility needs on an annual basis for a period of fifteen (15) to
twenty (20) years.
Recovery Steps
1. Issue a Request For Qualifications (RFQ) for preparation of a long-range school facilities master
plan.
2. Review responses, interview qualified consultants, and negotiate a contract with a suitable con-
sultant.
3. Contract for preparation of a long-range school facilities master plan.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
40 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.2 Facility Planning – CDE Facilities Planning and Construction Guide
Professional Standard
Compton Unified School district should possess a California State Department of Education Facilities
Planning and Construction Guide (dated 1991).
Sources and Documentation
1. District documentation
Findings
1. The district does not currently possess a Facilities Planning and Construction Guide prepared by
the California State Department of Education.
Recommendations and Recovery Steps
Recommendation
1. The district should contact the California State Department of Education and request that a
Facilities Planning and Construction Guide be sent to the Director of Facilities.
2. District should comply with new playground regulations when these are published.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 41
➤
0 1 2 3 4 5 6 7 8 9 10
2.3 Facility Planning – Efforts to Seek State and Local Matching Funds
Professional Standard
Compton Unified School District should seek state and local funds.
Sources and Documentation
1. Discussion with State Administrator
2. Discussion with Associate Superintendent, Business and Administrative Services
3. Forms SAB 760
Findings
1. The State Administrator and district staff make frequent trips to Sacramento to seek State funds.
This includes having active State applications, conversing with members of the State Allocation
Board and staff of the Office of the Public School Construction, and retaining a professional
lobbyist.
2. The district placed a general obligation bond measure on the November 3, 1998 ballot. The bond
received more than 66% yes votes, but failed because it did not reach the 66 2/3 required for
passage. This was the second unsuccessful bond measure that the district has placed before its
electorate in the last nine months.
Recommendations and Recovery Steps
Recommendation
1. Continue to attempt to pass a local general obligation bond and continue actions underway to
obtain state funding for facility projects.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
42 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.4 Facility Planning – Existence of a District Facility Planning Committee
Professional Standard
Compton Unified School District should have a facility planning committee.
Sources and Documentation
1. Discussion with Associate Superintendent, Business and Administrative Services
Finding
1. The district currently does not have a facility planning committee.
Recommendations and Recovery Steps
Recommendation
1. The district should create a facility planning committee.
Recovery Steps
1. Solicit qualified members for the committee. These should include district staff (e.g., Director of
Facilities, principals, teachers, etc.) City staff (e.g., Director of Planning, Planning Commissioner,
Director of Public Works, etc.), parents, members of the community, and district consultants (e.g.,
financial consultant, architect, demographer, etc.).
2. Develop operating procedures for the committee, establish meeting schedules, and ensure that
minutes are taken and retained.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 43
➤
0 1 2 3 4 5 6 7 8 9 10
2.5 Facility Planning – Properly Staffed and Funded Facility Planning Function
Professional Standard
Compton Unified School District should have a properly staffed and funded facility planning depart-
ment.
Sources and Documentation
1. Discussion with State Administrator
2. Discussion with Associate Superintendent, Business and Administrative Services
3. Discussion with Senior Director, Department of Facilities and Operations
Findings
1. The facilities department of the district is currently staffed with nine (9) individuals. Compared to
other school districts in the state with comparable number of students, a facilities department
comprised of nine (9) individuals should be adequate for CUSD.
2. Some individuals in the facilities department do not possess adequate skills to perform duties and
assignments typically cared-out by such a department. It is, therefore, difficult to determine at this
time whether the facilities department is properly funded. It is our opinion that the department is
overstaffed and underskilled.
Recommendations and Recovery Steps
Recommendations
1. This district should evaluate all individuals in the facilities department and determine that each
individual possesses adequate educational training or experience and skills required to perform
duties. CUSD needs to recover from previous hiring practices of finding people jobs without
regard to qualifications.
2 Employee performance should be evaluated on an on-going basis against performance standards to
ensure that duties and assignments that are typically performed by a facilities department are
being completed correctly and accurately on time.
3. A system of on-going assessment and evaluation is needed to determine whether the facilities
department is properly staffed and funded to meet evolving project levels.
4. Employees who do not meet the minimum qualifications for a particular assignment should be
considered for reassignment to an appropriate position.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
44 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.6 Facility Planning – Implementation of an Annual Capital Planning Budget
Professional Standard
Compton Unified School District should develop and implement an annual capital planning budget.
Sources and Documentation
1. Discussion with Associate Superintendent, Business and Administration Services
Findings
1. The district does develop an annual capital planning budget which identifies the facilities im-
provements that require immediate attention in order to provide a safe and healthy learning
environment.
2. The capital planning budget has not been fully implemented because funds have not been avail-
able to finance the plan.
Recommendations and Recovery Steps
Recommendations
1. The district needs to receive a combination of State and local funds in order to provide school
facilities that are truly safe and healthy.
2. Until such time as funds are available and the school facilities are modernized and enhanced with
improvements that are required in the district, CUSD should continue to develop annual capital
planning budgets to address the most urgent school facility crises.
3. The capital planning budget should be consistent with the district master plan.
Recovery Steps
1. Continue to attempt to pass a local general obligation bond for school facilities modernization and
improvement.
2. Continue aggressive efforts to obtain state hardship and deferred maintenance funds.
3. Establish joint private and public partnerships to provide funding for joint use projects.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 45
➤
0 1 2 3 4 5 6 7 8 9 10
2.7 Facility Planning – Standards for Real Property Acquisition and Disposal
Legal Standard
Compton Unified School District should have standards for real property acquisition and disposal. [EC
39030, 39290, 39295, 39360, 39390, 39480] )
Sources and Documentation
1. Discussion with State Administrator
2. Discussion with Associate Superintendent, Business and Administrative Services
Finding
1. The State Administrator and district staff has developed a conceptual plan to acquire and dispose
of real property. This informal plan is based on simplistic demographic trends of the district and
input provided by the Planning Department of the City of Compton.
Recommendations and Recovery Steps
Recommendations
1. The district needs to prepare, or have prepared, a long-range school facilities master plan before
developing standards for real property acquisition and/or disposal.
2. The long-range school facilities master plan should determine optimum capacity of existing
school facilities, project long-range student enrollments, analyze locations of surplus school sites,
and identify potential future school sites.
3. Only after having a long-range school facilities master plan completed should CUSD consider the
acquisition and/or disposal of real property.
Recovery Steps
1. Complete preparation of a long-range school facilities master plan.
2. Develop policies for property acquisition and disposal that are consistent with that plan.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
46 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.8 Facility Planning – State Allocation Board Waivers for Non-conforming Facilities
Legal Standard
The Compton Unified School District (CUSD) seeks and obtains waivers from the State Allocation
Board for continued use of its non-conforming facilities.
[EC 17284, 17285]
Sources and Documentation
1. Interview with OPSC Project Manager
2. Interviews with CUSD staff
3. Review of district records
4. Review of State Allocation Board agendas
Findings
1. The CUSD has pursued and received waivers from the State Allocation Board for authorized/
continued use of all non-conforming facilities. Of greater importance, however, the CUSD has
worked with OPSC to obtain 55 relocatables to replace the majority of its non-conforming facili-
ties.
2. The CUSD is to be commended for its recent efforts to obtain “replacement” facilities for 55 non-
conforming facilities. Ongoing cooperative efforts were required by the district with and through
OPSC to finalize the acquisition and placement of these facilities.
Recommendations and Recovery Steps
Recommendation
1. None required at this time.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 47
➤
0 1 2 3 4 5 6 7 8 9 10
2.9 Facility Planning – Selection of Licensed Architect/Engineering Services
Legal Standard
The CUSD has established and utilizes a selection process for the selection of licensed architectural/
engineering services. [GC 17302]
Sources and Documentation
1. Interviews with CUSD staff
2. Review of district records and Board Policy
Findings
1. The CUSD is currently engaged in the selection process for architectural services. A well-con-
ceived/multi-phase process is being implemented. The process has included multiple opportuni-
ties and methods for the CUSD to evaluate the professional strengths and weaknesses of the firms
being considered.
2. There is relatively broad participation by CUSD staff within the architectural selection process -
this will be of benefit as the process moves toward a successful conclusion.
3. It did not appear that a Board Policy had been modified to reflect the “in-place” architectural
selection process.
4. The CUSD is to be commended for its development of a process that is based upon meaningful
criteria and a comprehensive approach toward selection. The selection process that is currently
being utilized is a significant improvement from past practices of the district.
Recommendations and Recovery Steps
Recommendation
1. The CUSD Board Policy Manual should be modified to reflect “in-place” procedures for the
selection of architectural/engineering services.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
48 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.10 Facility Planning – Assessment of Local Bonding Capacity
Legal Standard
Compton Unified School District should assess its local bonding capacity. [EC 15100]
Sources and Documentation
1. Discussion with State Administrator
2. Discussion with Associate Superintendent, Business and Administrative Services
Findings
1. The district had developed procedures to accurately assess bonding capacity.
2. Measure A, a general obligation bond measure of $107,000,000, was put before the voters in
March 1998 and Measure C, a general obligation bond measure identical to that of Measure A,
was put before the voters on November 1998.
Recommendations and Recovery Steps
Recommendations
1. The district should hire a financial advisor or consultant to annually assess their local bonding
capacity.
2. The district should develop a long-term school facilities financing plan that is predicated on
providing school facilities that facilitate educational programs in an efficient manner.
3. The long-term school facilities financing plan should compliment the long-term school facilities
master plan of CUSD.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 49
➤
0 1 2 3 4 5 6 7 8 9 10
2.11 Facility Planning – Process to Determine Debt Capacity
Professional Standard
Compton Unified School District should develop a process to determine debt capacity.
Sources and Documentation
1. Discussion with Associate Superintendent, Business and Administrative Services
Findings
1. The Associate Superintendent, Business and Administrative Services is aware that the school
facility needs of the district are significant and that CUSD does not possess the local debt capacity
to meet all of the needs.
2. The district does not have in place any policies/guidelines establishing self-imposed debt capacity
limitations.
Recommendations and Recovery Steps
Recommendations
1. The district should develop policies/guidelines establishing self-imposed debt capacity limitations.
2. The plan should identify whether the debt is an obligation of the district that is obligated debt
backed by the general fund or is a limited obligation that is not backed by the general fund. It is
imperative that CUSD focus on obligated debt since it has the ability of directly impacting opera-
tions and maintenance of the district.
Recovery Steps
1. The district should establish procedures to determine the impact of current debt service on the
general fund.
2. The district should establish policies to govern the issuance of future debt that limit the exposure
of the general fund.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
50 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.12 Facility Planning – Awareness and Monitoring of Assessed Valuation
Professional Standard
Compton Unified School District should be aware of and monitor the assessed valuation of taxable
property within its boundaries.
Sources and Documentation
1. Discussion with Associate Superintendent, Business and Administrative Services.
Findings
1. The district is aware and has been monitoring the assessed valuation of taxable property within
CUSD.
2. The district received assessed value information from Los Angeles County Office of Education
and used the information in placing general obligation bonds measures on the March 1998 and
November 1998 ballots.
Recommendations and Recovery Steps
Recommendation
1. The district should annually contact the Division of Business Advisory Services of the Los Ange-
les County Office of Education and request an assessed valuation worksheet for CUSD.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 51
➤
0 1 2 3 4 5 6 7 8 9 10
2.13 Facility Planning – Monitor Legal Bonding Limits
Legal Standard
Compton Unified School District should monitor its legal bonding limits. [EC 15100, 15330]
Sources and Documentation
1. Discussion with State Administrator
2. Discussion with Associate Superintendent, Business, and Administrative Services
Finding
1. In determining the authorization amount for Measures A and C, the district, working with its
financial consultant, calculated the legal bonding limits of CUSD.
Recommendations and Recovery Steps
Recommendation
1. The district should continue to calculate, or have calculated, its legal bonding limits.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
52 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.14 Facility Planning – Collection of Statutory Developer Fees
Legal Standard
Compton Unified School District should collect statutory school fees. [EC 17620, GC 65995, 66000]
Sources and Documentation:
1. Discussion with Associate Superintendent, Business and Administrative Services
2. Compton Unified School District Developer Fees Justification Document (April 1992)
Findings
1. The last Residential Development School Fee Justification Study and the last Commercial/ Indus-
trial School Fee Justification Study was prepared for CUSD in April 1992.
2. The district is currently collecting $1.72 per square foot for residential development and $0.28 per
square foot of commercial/industrial development.
3. The amount the district is currently collecting is below the maximum amount established by the
State.
Recommendations and Recovery Steps
Recommendations
1. The district should ensure that fee justification studies are performed every 2 years concurrent
with State inflation adjustments.
2. The district should endeavor to collect the maximum fee allowed under the law.
Recovery Steps
1. CUSD needs to have an updated Residential Development School Fee Justification Study and an
updated Commercial/Industrial Development School Fee Justification Study prepared.
2. Should these studies document that the district could increase the fees for residential development
and commercial/industrial development to $1.93 and $0.31, respectively, CUSD should hold the
required public hearing as soon as possible.
3. The district should raise its fee schedule to reflect the results of the study.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 53
➤
0 1 2 3 4 5 6 7 8 9 10
2.15 Facility Planning – Consideration of an Asset Management Plan
Legal Standard
Compton Unified School District should consider developing an asset management plan. [EC 39030,
39290, 39295, 39260, 39480]
Sources and Documentation
1. Discussion with State Administrator
2. Discussion with Associate Superintendent, Business and Administrative Services
3. Discussion with Mayor of the City of Compton
Findings
1. The district does possess surplus school sites that could be asset managed to develop funds for the
modernization and/or expansion of existing school facilities, acquisition of additional school sites
located elsewhere in the district, and/or the construction of new school facilities.
2. The district and/or its consultant should work closely with staff of the City of Compton in devel-
oping the asset management plan.
Recommendations and Recovery Steps
Recommendations
1. The district should develop an asset management plan for its real estate assets.
2. The district and/or its consultant should work closely with staff of the City of Compton and other
public agencies in developing the asset management plan.
Recovery Steps
1. Prior to CUSD developing an asset management plan, it is imperative that the district staff pre-
pare, or have prepared, a long-range school facilities master plan.
2. The long-range school facilities master plan should validate whether unused existing sites are truly
surplus to current and projected needs.
3. To the extent that the long-range facilities master plan validates that the district possesses surplus
sites, CUSD should proceed in developing an assets management plan that adheres to the Educa-
tion Codes listed above.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
54 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
2.16 Facility Planning – Application for Funding for Joint Use Projects
Professional Standard
The CUSD has pursued State funding for joint-use projects through the filing of applications through the
Office of Public Construction and the State Allocation Board.
Sources and Documentation
1. Interview with OPSC Project Manager
2. Review of OPSC Project Tracking for CUSD
3. Interviews with CUSD staff
4. Review of district records
5. Review of State Allocation Board agendas
Findings
1. The CUSD filed an application in 1997 for a proposed joint-use project. Unfortunately, the de-
mand for funding through this one-time program exceeded available resources. As such, a “lot-
tery” process was utilized by the State Allocation Board to award funding.
2. The district did not receive funding through the “lottery.”
Recommendations and Recovery Steps
Recommendation
1. At this time funding for future joint-use projects is not anticipated through Senate Bill 50 and the
regulations that are being developed. However, it is believed that the concept of State funding for
joint-use projects is a prudent one and may be re-instituted at a future date. Therefore, it is sug-
gested that the CUSD continue to monitor opportunities through any available funding source to
fiscally support any proposed joint-use project(s).
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 55
➤
0 1 2 3 4 5 6 7 8 9 10
3.1 Facilities Improvement and Modernization – Appropriate Use of the Deferred
Maintenance Fund
Professional Standard
The district has a restricted deferred maintenance fund and those funds are expended for maintenance
purposes only. The deferred maintenance fund should be a stand-alone fund reflecting the revenues and
expenses for the major maintenance projects accomplished during the year.
Sources and Documentation
1. Board policy
2. District’s general ledger for Deferred Maintenance Fund 27
3. Copies of J-205 Deferred Maintenance Fund Budget and Unaudited Actuals document
4. Copies of purchase orders and contracts
5. Copy of five year deferred maintenance plan
Findings
1. No Board policy exists stating the district’s goals for the use of the deferred maintenance funds of
the facilities that will carry the highest priority for the deferred maintenance program.
2. The district is continuing to use the 1996-97 deferred maintenance plan which includes all school
sites and all categories excluding underground tank removal.
Recommendations and Recovery Steps
Recommendations
1. Establish Board policy stating the district’s goals for the use of deferred maintenance funds and
prioritize the sites and projects of deferred maintenance.
2. Update the five year deferred maintenance plan annually to remove maintenance completed
during the year and include projects that have become eligible for deferred maintenance funding.
While state funding will never reach the level necessary to cover the total district needs, the
district should have a plan in place for all available funding.
3. The long range facility master plan should incorporate deffered maintenance projects.
Recovery Steps
1. The governing board should review the needs of the individual school sites for all aspects of
deferred maintenance and prioritize them to obtain the district’s goals. The prioritization should
be based on the safety of the students and community, the educational benefit to the student, and
the availability of funds in the future.
2. The Board should adopt a policy directing the district to concentrate all funding for deferred
maintenance on the needs as prioritized.
3. The policy should be reviewed annually as a part of the budget development process for possible
revision and readoption.
56 Facilities Management Assessment and Recovery Plan
4. Once the governing board has established the priorities for the deferred maintenance program, the
district must incorporate the priorities into the five year deferred maintenance plan filed with the
State.
5. The district should review the projects included in the five-year plan to verify that estimated costs
for each project and whether to keep the project on the plan.
6. If a project was completed during the prior year, it should be removed from the plan.
7. If a project became eligible for deferred maintenance, it should be included in the plan.
8. All projects should be update annually to cover the increased costs for completing the project.
9. Any projects included in the five-year plan that have become a safety hazard should be considered
for critical hardship funding and the appropriate application filed with the Office of Public School
Construction.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 57
➤
0 1 2 3 4 5 6 7 8 9 10
3.2 Facilities Improvement and Modernization – Use of Deferred Maintenance Ex-
treme Hardship Applications
Professional Standard
The CUSD has pursued State funding for deferred maintenance - critical hardship needs by filing an
application/s through the Office of Public Construction and the State Allocation Board. [State Allocation
Board Regulation §1866]
Sources and Documentation
1. Interview with OPSC staff
2. Interviews with CUSD staff
3. District facilities records
4. State Allocation Board agendas
Findings
1. The CUSD has pursued deferred maintenance-critical hardship funding through the State Alloca-
tion Board.
2. To date, these efforts have been largely unsuccessful due to an inability to meet all funding re-
quirements.
3. Staff has expressed a desire to continue to pursue this funding source to meet the overwhelming
deferred maintenance needs which exist throughout the district.
Recommendations and Recovery Steps
Recommendation
1. The CUSD should continue to pursue deferred maintenance-critical hardship funding opportuni-
ties through the State Allocation Board.
Recovery Steps
1. Ensure that staff training is provided so that “decision-makers” within the CUSD Facilities and
Maintenance Departments clearly understand program elements and participation requirements
for the Deferred Maintenance - Critical Hardship Program.
2. Monitor program elements, opportunities and requirements for critical hardship funding at least on
a quarterly basis - analyze these elements in relation to CUSD needs.
3. The CUSD should proactively seek funding solutions for eligible needs by establishing quarterly
contacts with appropriate State-level staff (currently OPSC). These contacts should keep CUSD
current with current program requirements and to make State staff aware of CUSD needs.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
58 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
3.3 Facilities Improvement and Modernization – Application to State Allocation
Board for Facilities Funding
Professional Standard
The CUSD applies to the State Allocation Board for facilities funding for all applicable projects.
Sources and Documentation
1. Interview with OPSC Project Manager
2. OPSC Project Tracking for CUSD
3. Interviews with CUSD staff
4. District facilities records
5. State Allocation Board agendas
6. CUSD Board agendas
Findings
1. The CUSD has made a concerted effort within recent years to access the State School Building
Program for potential funding of modernization, growth and deferred maintenance needs.
Recommendations and Recovery Steps
Recommendation
1. The district should increase the effort to participate in the State School Building Program.
2. The district should make use of outside specialists who deal with state applications to maintain
and enhance the district’s applications.
Recovery Steps
1. All facilities department staff should receive training to ensure that there is uniform understanding
of state program regulations and how they specifically apply to applications for funding for
CUSD.
2. Specific CUSD staff should be responsible for monitoring the state program and serving as a
liaison with appropriate state program representatives.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 59
➤
0 1 2 3 4 5 6 7 8 9 10
3.4 Facilities Improvement and Modernization – Determination of Maximum Eligi-
bility for State Funding
Professional Standard
The CUSD consistently reviews and monitors its eligibility for State funding so as to capitalize upon
maximal funding opportunities.
Sources and Documentation
1. Interviews with CUSD staff
2. Interview with OPSC Project Manager
3. District facilities records
Findings
1. The CUSD has made a concerted effort within recent years to improve its chances for funding
through the State School Building Program for modernization, growth and deferred maintenance
needs.
2. It appears that a more consistent and proactive approach toward State Program participation and
monitoring needs to be established and maintained
Recommendations and Recovery Steps
Recommendation
1. The district should increase the effort to participate in the State School Building Program.
2. The district should make use of outside specialists who deal with state applications to maintain
and enhance the district’s applications.
Recovery Steps
1. All facilities department staff should receive training to ensure that there is uniform understanding
of state program regulations and how they specifically apply to applications for funding for
CUSD.
2. Specific CUSD staff should be responsible for monitoring the state program and serving as a
liaison with appropriate state program representatives.
3. Regularly scheduled coordination meetings should be conducted will parties (CUSD staff, archi-
tects, etc.) for the purpose of tracking the completion of activities necessary to enhance state
program funding potential.
4. A plan needs to be developed to determine how local funding requirements will be met in order to
access state funding (80/20 modernization funding, etc.)
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
60 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
3.5 Facilities Improvement and Modernization – Interim Plans for Student Housing
During Construction
Professional Standard
The CUSD establishes and implements interim housing plans for use during the construction phase of
modernization projects and/or additions to existing facilities.
Sources and Documentation
1. Interviews with CUSD staff
2. Observation of existing practices at “active” project site(s)
3. Review of district records
Findings
1. Multiple modernization projects are in the construction phase within CUSD.
2. In consideration of the district’s instructional delivery system and educational program require-
ments, it was witnessed that interim housing plans have been implemented at some sites to pro-
vide temporary housing for classrooms which are undergoing modernization.
3. Some concern was expressed at the site level relative to the timely provision for the temporary
housing.
4. Project schedule delays have caused interim housing costs to be excessive.
5. The excessive costs are seen an important program element within a successful overall moderniza-
tion program for the CUSD and, as such, deserves more specific attention and resources.
Recommendations and Recovery Steps
Recommendations
1. In order to ensure that distractions to the instructional program at any given site being modernized
or receiving substantial facility additions, the CUSD should consider the following factors related
to the provision and use of an interim housing plan:
• Include the site level administrators in discussions focusing upon construction phasing plans
and the need for the provision and placement of interim housing.
• Make a commitment to providing uniform communication amongst all involved parties relative
to project scheduling elements at each respective site.
• Improved adherence to project schedules will minimize the effectiveness of interim housing
plans. It is acknowledged that this requires improvement in the construction administration
phase of the project and that the project architect, the general contractor’s representative, the
district construction representative, and other responsible parties will need to operate through a
more cohesive approach toward project and construction management.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 61
➤
0 1 2 3 4 5 6 7 8 9 10
3.6 Facilities Improvement and Modernization – Maintenance of a System for Track-
ing Project Progress
Professional Standard
The CUSD has established and maintains a system for tracking the progress of individual projects.
Sources and Documentation
1. Interviews with CUSD staff
2. District facilities records
Findings
1. The CUSD currently has a wide diversity of projects in various phases of planning, construction
and close-out.
2. While it appears that improvements have occurred in the area of tracking individual projects, it is
obvious that further improvement is required in this area.
3. Problems and challenges within individual projects appear to dictate a “reactive” approach by
district staff and seem to continue to hinder a sense of organization and control over individual
projects and overall facilities department activities.
4. A uniform level of understanding and approach toward the planning and delivery of projects
within the department is missing.
5. It is believed that any lack of success in the area of project tracking may be the result of a larger
problem related to the lack of uniform understandings and articulation within the facilities depart-
ment relative to individual projects.
6. It is acknowledged that improvement in this area is difficult and time-consuming but the benefits
resulting from improvement in this area will provide a greater sense of professional accomplish-
ment for facilities department staff and will improve the end results of individual projects.
Recommendations and Recovery Steps
Recommendation
1. The district should improve the project tracking system.
Recovery Steps
1. All facilities department staff should participate in professional training related to project manage-
ment. Training should be uniform for all staff.
2. Regularly scheduled “project status” meetings between all involved parties should be conducted to
promote project articulation and to develop a more uniform understanding of the status of indi-
vidual projects. Project managers should attend these meetings with concise and up-to-date
written reports which reflect the status and needs of projects under their responsibility.
62 Facilities Management Assessment and Recovery Plan
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 63
➤
0 1 2 3 4 5 6 7 8 9 10
3.7 Facilities Improvement and Modernization – Furniture and Equipment Included
in Modernization Program
Professional Standard
Furniture and equipment items are routinely included within the scope of modernization projects.
Sources and Documentation
1. Interview with OPSC Project Manager
2. Interviews with CUSD staff
3. District records
4. State Allocation Board agendas
Findings
An important element within any modernization project is the inclusion of furniture and equipment.
While it is very beneficial to update the building structures, the “systems” within the building structure,
and exterior aspects of the building and school site, it is very important to also consider the upgrade of
furniture and equipment within any given school modernization project.
1. The CUSD routinely includes furniture and equipment within the scope of its modernization
projects.
2. A more uniform approach toward the utilization of allocated furniture and equipment funds should
occur.
3. There was no logical connection between furniture and equipment expenditures and educational
program improvement goals.
4. The concept of site-based control over such decisions is supported so long as a more clear-cut
connection can be made between purpose of expenditures and projected positive impacts upon
delivery of instruction and student learning.
Recommendations and Recovery Steps
Recommendation
1. The district should create a system to ensure the use of furniture and equipment in ways that serve
to better facilitate the delivery of instruction and promote the effectiveness of educational pro-
grams and student learning.
Recovery Steps
1. A site-based group should develop furniture and equipment expenditure proposals. A site-level
administrator should manage the development of these proposals.
2. All site-based proposals for the expenditure of furniture and equipment funds should be reviewed
and ultimately approved for implementation by a district-level oversight committee which in-
cludes representation from the respective school site, the district’s instructional services division
and the district’s facilities services department.
64 Facilities Management Assessment and Recovery Plan
Standard Implemented: Partially
mplementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 65
➤
0 1 2 3 4 5 6 7 8 9 10
3.8 Facilities Improvement and Modernization – Approval of Plans and Specifica-
tions Prior to Contract Award
Legal Standard
The CUSD obtains approval of plans and specifications from the Division of the State Architect and the
Office of Public School Construction (when required) prior to the award of a contract to the lowest,
responsible bidder. [EC 17263, 17267] )
Sources and Documentation
1. Interviews with CUSD staff
2. CUSD Board policy manual
Findings
1. The CUSD obtains Division of the State Architect and Office of Public School Construction
approvals prior to the award of a contract to the lowest, responsible bidder.
2. In selected instances, the district proceeded with the award of a construction contract prior to
agency approvals.
Recommendations and Recovery Steps
Recommendations
1. Establish a Board policy and administrative regulations which clarify the procedures to be used in
the award of a construction contract.
2. Require the approval of all construction plans prior to commencement by the Division of the State
Architect and the Office of Public School Construction to maintain maximum funding eligibility.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
66 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
3.9 Facilities Improvement and Modernization – All Relocatables Meet Statutory
Requirements
Legal Standard
All relocatables in use throughout the district meet statutory requirements. [EC 17292]
Sources and Documentation:
1. Inspection of district sites
2. Interviews with CUSD staff
3. Review of district records
4. Review of Division of the State Architect records
Findings
1. The CUSD has done an excellent job recently in replacing non-conforming facilities, as evidenced
by the recent replacement of 55 non-conforming facilities with DSA-approved relocatables.
2. The district has procedures in place to ensure that new facilities are processed in ways which meet
all statutory requirements.
Recommendations and Recovery Steps
Recommendation
1. The district must make an ongoing commitment to systematically install relocatables only after all
required approvals are obtained by the district.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 67
➤
0 1 2 3 4 5 6 7 8 9 10
3.10 Facilities Improvement and Modernization – Plan for Maintenance and Modern-
ization Exists
Legal Standard
The CUSD maintains a plan for the maintenance and modernization of its facilities. [EC 17366]
Sources and Documentation
1. Interviews with CUSD staff
2. Review of district records
Findings
1. No facilities master plan exists to guide the district’s facilities program.
2. The district has filed its five-year deferred maintenance plan with the State Allocation Board.
3. The CUSD is in a “reactive” mode with respect to providing badly-needed improvements to its
facilities.
4. There are significant health and safety needs which continue to go unmet.
Recommendations and Recovery Steps
Recommendation
1. The CUSD must develop a facilities master plan.
Recovery Steps
1. A format for the facilities master plan must be developed through the cooperative planning efforts
of in-district representatives and out-of-district professionals with significant expertise in the area
of educational facility master plan development.
2. Once a format and scope for the facilities master plan has been developed, the district should seek
assistance from out-of-district professionals.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
68 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
3.11 Facilities Improvement and Modernization – Annual Deferred Maintenance
Contribution is Made Correctly
Professional Standard
The annual deferred maintenance contribution is made correctly. The district should annually transfer
the maximum amount that the district would be eligible for in matching funds from the State.
Sources and Documentation
1. District’s general ledger for Deferred Maintenance Fund 27
2. Copies of J-205 Deferred Maintenance Fund Budget and Unaudited Actuals document
3. State correspondence for maximum funding
4. County correspondence regarding possible funding levels
5. Copy of transfer certification document
Finding
1. The district made numerous transfers into the Deferred Maintenance Fund during the 1997-98
fiscal year including the amount needed to match the State’s Deferred Maintenance Apportion-
ment.
Recommendations and Recovery Steps
Recommendation
1. As a minimum, the district should continue transferring the maximum amount possible to match
the State Deferred Maintenance Apportionment.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 69
➤
0 1 2 3 4 5 6 7 8 9 10
3.12 Facilities Improvement and Modernization – Deferred Maintenance Projects are
Actively Managed
Professional Standard
The district actively manages the deferred maintenance projects. The district should review the five-year
deferred maintenance plan annually to remove any completed projects and include any newly eligible
projects. The district should also verify that the expenses performed during the year were included in the
State approved five-year deferred maintenance plan.
Sources and Documentation
1. District’s general ledger for Deferred Maintenance Fund 27
2. Copies of purchase orders and contracts
3. Copy of five-year deferred maintenance plan
Findings
1. The district’s 1997-98 deferred maintenance fund general ledger reflected the majority of the
expenditures paid for roofing repair and replacement which were a part of the five-year deferred
maintenance plan.
2. Since these projects were for large dollar amounts, they were required to go to bid.
3. Verification that the bids were indeed let was obtained from the Purchasing Department.
Recommendations and Recovery Steps
Recommendation
1. The district should continue the current practice of using deferred maintenance funding for those
projects that require immediate attention.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
70 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
3.13 Facilities Improvement and Modernization – Knowledge of Office of Public School
Construction Procedures
Professional Standard
Staff within the CUSD is knowledgeable of procedures within the Office of Public School Construction
(OPSC).
Sources and Documentation
1. Interview with OPSC Project Manager
2. Interviews with CUSD staff
Findings
1. Upper-level management within the CUSD is knowledgeable of procedures within the Office of Public
School Construction (OPSC).
2. The staff within the facilities department is not uniformly aware of OPSC procedures.
Recommendations and Recovery Steps
Recommendations
1. The CUSD facilities department staff should receive additional training on proven methodologies to work
effectively with the OPSC staff and to better understand OPSC procedures, especially with the implemen-
tation of SB 50 regulations.
2. Training could occur through selected in-district personnel but it is suggested that this training be aug-
mented through the use of outside professionals who have experience in working with OPSC staff and
who are well-versed in OPSC procedures.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 71
➤
0 1 2 3 4 5 6 7 8 9 10
3.14 Facilities Improvement and Modernization – Knowledge of Division of State
Architect Procedures
Professional Standard
Staff within the CUSD is knowledgeable of procedures within the Division of the State Architect (DSA).
Sources and Documentation
1. Interview with DSA staff
2. Interviews with CUSD staff
Findings
1. Upper-level management within the CUSD is knowledgeable of procedures within the Division of
the State Architect (DSA).
2. The staff within the facilities department is not as uniformly aware of DSA procedures.
Recommendations and Recovery Steps
Recommendation
1. The CUSD facilities department staff should receive additional training to better understand DSA
procedures. This training should occur through the use of outside professionals who have experi-
ence in working with DSA and who are well-versed in DSA policies, procedures and regulations.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
72 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
4.1 Construction of Projects – An Appropriate Project Management Structure Exists
Professional Standard
The CUSD maintains an appropriate structure for the effective management of its construction projects.
Sources and Documentation
1. Interviews with CUSD staff
2. Review of district records
3. Interviews with contractors from respective construction projects
Findings
1. It is our observation that the district is experiencing difficulty in managing its construction
projects.
2. Much of this difficulty can be attributed to plans and specifications for current projects that are, in
some cases, less than ideal. This deficiency creates additional work and unnecessary complexities
within the construction phase of a project.
3. Some of the difficulty the district is experiencing in project/construction management, however, is
due to inadequate and/or varying levels of training for facilities department staff.
Recommendations and Recovery Steps
Recommendations
1. The district needs to improve construction project management.
2. The quality of plans and specifications needs to be improved before bidding of projects.
3. Training of facilities department staff needs improvement.
4. Develop educational specifications for each project.
Recovery Steps
1. The district should establish procedures to better review plans and specifications prepared by their
project architects/engineers prior to bidding and contract award.
2. The review should ensure that plans are complete, accurate and appropriate for the particular
project goals. Any required changes to plans and/or specifications should be incorporated prior to
award of the construction contract.
3. All facilities department staff should participate in professional training related to project and
construction management. It would be ideal if this training could be uniform for all staff.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 73
➤
0 1 2 3 4 5 6 7 8 9 10
4.2 Construction of Projects – Change Orders are Processed and Received Prior Ap-
proval
Professional Standard
Change orders are processed and receive prior approval from required parties before being implemented
within respective construction projects.
Sources and Documentation
1. Interview with Inspector/s of Record
2. Interviews with CUSD staff
3. Interviews with respective contractors
4. Review of district records
Findings
1. The district has consistently obtained all required approvals for change orders prior to their imple-
mentation. The importance of this practice cannot be overstated due to the financial implications
which can result through a haphazard adherence to this practice.
2. We found that the district has had mixed experiences with respect to its Inspectors of Record
(IOR). The IOR is an important participant in the change order review/approval process.
Recommendations and Recovery Steps
Recommendations
1. To ensure continued compliance with the practice of obtaining all change order approvals prior to
implementation the district should clearly articulate to all project participants the district standard
of obtaining all necessary approvals for change orders prior to implementation of the change
order.
2. Establish procedures and standards for the selection and employment of Inspectors of Record and
include within their initial district training reinforcement of the standard for all change order
approvals prior to implementation.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
74 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
4.3 Construction of Projects – Appropriate Project Records and Drawings are Main-
tained
Professional Standard
The CUSD maintains appropriate project records and drawings.
Sources and Documentation
1. Interview with Inspector/s of Record
2. Interviews with CUSD staff
3. Review of district records
Findings
1. The district, not unlike many California public school districts, is somewhat disorganized and
inconsistent in the maintenance of project records and drawings. Improvement could be made in
the district’s maintenance in both of these areas (records and drawings).
2. An improved system of storage and maintenance of project records and drawings is needed to
support future needs at district sites for repair and/or modifications to existing facilities.
Recommendations and Recovery Steps
Recommendations
1. The district should improve its storage and maintenance of records and drawings through an
organized effort to establish internal systems for the creation and maintenance of project records.
2. The district should create an area and system adequate to maintain project drawings and specifica-
tions.
3. A system for the recordation of plan/s check-out and responsibility/accountability for returns
should be implemented.
4. Records and drawings should be required in all contracts.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 75
➤
0 1 2 3 4 5 6 7 8 9 10
4.4 Construction of Projects – Inspector of Record Assignments are Properly Ap-
proved
Professional Standard
Each Inspector of Record (IOR) assignment is properly approved.
Sources and Documentation
1. Interview with DSA staff
2. Interviews with CUSD staff
3. Review of district records
Finding
1. The CUSD employs its Inspectors of Record (IOR) and each assignment is properly approved. It
should be noted, however, that the district has expressed some level of dissatisfaction regarding
the quality of inspection services it has received in selected instances.
Recommendations and Recovery Steps
Recommendations
1. We have no recommendations related to the legal employment of inspectors.
2. We do suggest that the district analyze its selection methodologies for the employment of Inspec-
tors of Record and, based upon some previous level of dissatisfaction about the services that have
been received, modify the criteria they have used to select and employ Inspectors of Record.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
76 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
5.1 Compliance with Public Contracting Laws and Procedures – Compliance with
Formal Bidding Procedures
Legal Standard
The district complies with formal bidding procedures. [GC 54202, 54204]
Sources and Documentation
1. Board policy
2. Copy of draft purchasing handbook
3. Sample bid documents including ads, bid packets, awards and correspondence
Findings
1. Board policy 3323, revised February 9, 1988, is boilerplate language regarding when the district
will go to bid and when they will request proposals. It does not establish any directions for the
Purchasing Department to follow. It also lacks specific regulations relative to major construction
or renovation of buildings.
2. The district has a well-documented bid process in place as verified with interview with Director of
Purchasing. An integral part of the process is the “Handbook for Purchasing - Warehouse 1997/
98”. The draft purchasing handbook includes a section on competitive bidding. Included in this
section are specific guidelines by dollar amount as to when quotes for supplies and equipment are
required. The handbook states: “For purchases ranging from $1,000 - 5,000, at least two quota-
tions confirmed orally or in writing. Construction type jobs will not require more than one quote.
For purchases ranging from $5,000 - $50,000, written quotations from at least three viable ven-
dors. $51,000 and up “Formal” bids including advertising and Board approval.”
3. Sample bid documents were reviewed from the files of the Purchasing Department that included
bid advertising, sample bid packets, log of bids received and each bid amount, all bids received,
and associated paperwork.
4. The process is well documented and adhered to per the files. With the number of bids let and the
constant conflicts with bidding contractors, the workload placed on the purchasing department is
overwhelming. If a single project meant a single bid that could be trusted to completion of the
project, the workload would be reduced. However, the current quality of contractors bidding on
projects has required the district to monitor the quality of the work more closely than would be
expected in a normal situation.
5. Since the district put in place the current bid procedure, there has been a reduction in the number
of appeals. The district still faces the challenge of surviving the history of the district. When
contractors can be assured that invoices will be paid in a timely manner and the public will not
interrupt work in progress, the district will be able to utilize the bid process to the district’s advan-
tage.
Recommendations and Recovery Steps
Recommendations
1. Update Board Policy to include specific regulations for the Purchasing Department.
Facilities Management Assessment and Recovery Plan 77
2. The district should continue with the current bid process and the related documentation.
Recovery Steps
1. Rewrite Board Policy 3323 to provide specific direction to the Purchasing Department including:
• Who is the designated district person responsible for bid conflicts
• When penalties shall be levied on non-responsive bidders/contractors
• What the penalties shall be and when
2. Incorporate the board policy into the draft purchasing handbook.
3. Include the board policy as a portion of the bid document.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
78 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
5. 2 Compliance with Public Contracting Laws and Procedures – Procedures for Re-
quests for Quote/Proposals
Legal Standard
The district has a procedure for requests for quotes/proposals. [GC 54202, 54204]
Sources and Documentation
1. Board policy
2. Copy of draft purchasing handbook
3. Sample requests for proposals
Findings
1. Board policy 3323, revised February 9, 1988, is boilerplate language regarding when the district
will go to bid and when they will request proposals. It does not establish any directions for the
Purchasing Department to follow. It also lacks specific regulations relative to major construction
or renovation of buildings.
2. The draft purchasing handbook includes a section on competitive bidding. Included in this section
are specific guidelines by dollar amount as to when quotes for supplies and equipment are re-
quired. The handbook states: “For purchases ranging from $1,000 - 5,000, at least two quotations
confirmed orally or in writing. Construction type jobs will not require more than one quote. For
purchases ranging from $5,000 - $50,000, written quotations from at least three viable vendors.
$51,000 and up “Formal” bids including advertising and Board approval.”
Recommendations and Recovery Steps
Recommendation
1. Update Board Policy to include specific regulations for the Purchasing Department.
Recovery Steps
1. Rewrite Board Policy 3323 to provide specific direction to the Purchasing Department including:
• Who is the designated district person responsible for bid conflicts.
• When penalties shall be levied on non-responsive bidders/contractors.
• What the penalties shall be and when.
2. Incorporate the board policy into the draft purchasing handbook.
3. Include the board policy as a portion of the bid document.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 79
➤
0 1 2 3 4 5 6 7 8 9 10
5.3 Compliance with Public Contracting Laws and Procedures – Conflict of Interest
Statements and Compliance
Professional Standard
The district maintains files of conflict of interest statements and complies with legal requirements.
Conflict of interest statements should be collected annually by the superintendent and kept on file in the
superintendent’s office.
Sources and Documentation:
1. Board policy
2. Copies of sample conflict of interest statements on file
Finding
1. Conflict of interest statements were on file in the state administrator’s office and appeared to be
complete and current.
Recommendations and Recovery Steps
Recommendation
1. Continue annual collection of conflict of interest statements.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
80 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
5.4 Compliance with Public Contracting Laws and Procedures – Development of
Biddable Plans and Specifications
Professional Standard
The CUSD ensures that biddable plans and specifications are developed through its licensed architects/
engineers for respective construction projects.
Sources and Documentation
1. Interviews with CUSD staff
2. Review of district records
3. Interviews with project contractors
4. Inerviews with Inspectors of Record
Findings
1. The CUSD has expressed concern about prior difficulties with the quality of plans and specifica-
tions prepared and utilized during respective project bid periods.
2. As a result of inadequate or poorly prepared plans and specifications, the district has been exposed
unnecessarily to project cost and timeline overruns.
3. These difficulties have created additional and unnecessary work efforts for CUSD staff.
Recommendations and Recovery Steps
Recommendation
1. The District should analyze the “bid-ability” of plans and specifications for future projects.
Recovery Steps
1. Prior to establishing a bid schedule for a construction project, the CUSD should conduct coordina-
tion meetings between the project architect, the architect’s engineering consultants and CUSD
representatives.
2. These meetings should discuss specifications relative to program needs and project budget.
3. Revisions should be should serve to analyze and determine the quality and completeness of plans
and directed and made as required, as a result of this meeting(s).
4. The district should consider the completion of a constructability review of each project’s plans and
specifications prior to the establishment of a bid schedule for each project.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 81
➤
0 1 2 3 4 5 6 7 8 9 10
5.5 Compliance with Public Contracting Laws and Procedures – Evaluation of Re-
quests for Progress Payments
Professional Standard
The CUSD ensures that requests for progress payments are carefully evaluated.
Sources and Documentation
1. Interviews with CUSD staff
2. Interviews with project architect(s)
3. Interviews with project contractors
4. Review of district records
Findings
1. The CUSD has a system in place in which progress payment requests within respective projects
are carefully evaluated.
2. The CUSD staff stated that significant improvement has been made within this area over the past
couple of years.
3. The staff views this as a critically important area that the district should focus its efforts to ensure
that the district is receiving the maximum value for its budgeted construction funds. This will
ensure that respective project retention is adequate to successfully complete each project.
4. The staff also viewed any improvements in the selection and utilization of architectural/engineer-
ing firms and inspection services will enhance the “team approach” required for effectiveness in
fairly and successfully evaluating progress payment requests.
Recommendations and Recovery Steps
Recommendations
1. The district should take steps to address the effective and systematic review of progress payments.
2. The district should continue the efforts to improve the selection and employment of qualified
architectural/engineering firms and Inspectors of Record.
Recovery Steps
1. A written procedure stating the specific steps of the approval process must be established. This
procedure must include:
• Who is authorized to approve progress payments,
• The flow of paperwork in the approval process
• The timeline that must be maintained to release funds in a timely manner.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
82 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
5.6 Compliance with Public Contracting Laws and Procedures – Contract Award Ap-
peal Procedures
Professional Standard
The district maintains contract award/appeal processes. [GC 54202, 54204]
Sources and Documentation
1. Board policy
2. Interview purchasing director for number of appeals filed and how many required litigation
Findings
1. In reviewing the contract binders that contained sample bid documents and the documentation
generated by the district, the district has developed a very clear bid process that documents all of
the steps taken in developing, advertising, opening, and awarding each bid. The bid binder con-
tains samples or originals of all documents in the bid process to assist with the possible appeal of
a bid.
2. Ever since the district put in place the current bid procedure, there has been a reduction in the
number of appeals. The district still faces the challenge of surviving the history of the district.
When contractors can be assured that invoices will be paid in a timely manner and the public will
not interrupt work in progress, the district will be able to utilize the bid process to the district’s
advantage
Recommendations and Recovery Steps
Recommendation
1. The district should continue the current bid process.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 83
➤
0 1 2 3 4 5 6 7 8 9 10
6.1 Special Education Facilities – Compliance with CDE Regulations
Professional Standard
The CUSD complies with California Department of Education (CDE) requirements relative to the
provision of Special Education facilities.
Sources and Documentation
1. Interviews with CDE staff
2. Interviews with CUSD staff
3. Inspection of district sites/facilities
Findings
1. The CUSD understands the facility requirements related to the provision of special education
facilities and provides facilities accordingly.
2. The district provides appropriate physical spaces for its less severely handicapped students
through district-administered programs.
3. Facilities and services for more severely handicapped students are provided through special
education programs operated on CUSD sites by the Los Angeles County of Education.
Recommendations and Recovery Steps
Recommendation
None required at this time.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
84 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
6.2 Special Education Facilities – Equity, Appropriate to Educational Program
Professional Standard
The CUSD provides facilities for its Special Education programs which ensure equity with other educa-
tional programs within the district and provides appropriate learning environments in relation to educa-
tional program needs.
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with CUSD staff
Findings
1. The CUSD provides special education facilities in a manner that is similar to many California
public school districts. It was observed that, because of the relative fewer numbers of students that
are typically included within special education programs, services are often provided within
physical spaces smaller and/or different than spaces provided for other educational programs.
2. This practice has occurred more frequently because of additional space requirements created
through the implementation of Class size Reduction.
Recommendations and Recovery Steps
Recommendation
1. The district should develop a plan to ensure equity between facilities provided for special educa-
tion students and for students within other educational programs.
Recovery Steps
1. Conduct a facilities inventory/assessment to determine the actual space allocations for current
special education programs.
2. Conduct an analysis of existing space allocations in comparison with program needs and expecta-
tions to ensure that the delivery of quality special education programs are not inhibited due to
space and/or locational limitations.
3. Measure the findings of the aforementioned analysis with recommendations provided through the
California Department of Education, the State Allocation Board, and the Los Angeles County
Office of Education relative to suggested areas for respective programs.
4. Develop a plan to correct any space and/or locational deficiencies which exist within respective
CUSD school sites relative to the delivery of instruction services and programs for special educa-
tion students.
5. The fiscal impact associated with the implementation of this plan needs to be developed and
considered within the broader context of facilities-related needs within the CUSD.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 85
➤
0 1 2 3 4 5 6 7 8 9 10
6.3 Special Education Facilities – Adequacy for Instructional Program Needs
Professional Standard
The CUSD provides facilities for its Special Education programs which provide appropriate learning
environments in relation to educational program needs.
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with CUSD staff
3. Review of district records
Findings
1. Due to the varying needs and evolving enrollment of special education students, it appears that the
locations for special education classrooms and programs are provided, to some degree, on a
“transient” basis.
2. In some instances it appeared that space were “created” to accommodate special education stu-
dents, but that this space was not always suitable in comparison to program and student needs.
Recommendations and Recovery Steps
Recommendation
1. In order to develop a plan to ensure the provision of educational spaces for the district’s special
education students which facilitates the delivery of high quality programs and services the district
should conduct a facilities inventory/assessment to determine the actual space allocations for
current special education programs.
Recovery Steps
1. Conduct an analysis of existing space allocations in comparison with program needs and expecta-
tions to ensure that the delivery of quality special education programs are not inhibited due to
space and/or locational limitations.
2. Measure the findings of the aforementioned analysis with recommendations provided through the
California Department of Education, the State Allocation Board, and the Los Angeles County
Office of Education relative to suggested areas for these programs.
3. Develop a plan to correct any space and/or locational deficiencies that exist within respective
CUSD school sites relative to the delivery of instruction services and programs for special educa-
tion students.
4. The fiscal impact associated with the implementation of this plan needs to be developed and
considered within the broader context of facilities-related needs within the CUSD.
5. Identify available funding sources that may be used to implement the plan. Funding options
should include, but not be limited to, state Proposition 1a funds, including State Class Size Re-
duction bond funds for unfunded and displaced facilities.
86 Facilities Management Assessment and Recovery Plan
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 87
➤
0 1 2 3 4 5 6 7 8 9 10
7.1 Implementation of Class Size Reduction – Application for Funding
Professional Standard
The district applies for state funding for class size reduction facilities. The district should apply for class
size reduction facilities funding annually.
Sources and Documentation
1. 1997-98 CSR Operational Application
2. 1997-98 CSR Facilities Application
3. State apportionment for class size reduction operations
4. State apportionment for class size reduction facilities
5. Any correspondence from School Facilities Department relating to application
Findings
1. The district filed applications for both the 1997-98 class size reduction operations and facilities
programs.
2. The district did not fully implement K-3 class size reduction due to the lack of facilities and
available qualified teachers as stated in the district’s application.
3. The district received $2,520,000 for 1997-98 class size reduction facilities as a result of unused
operational funding. This apportionment funded 63 teaching stations. The total available funding
from unexpended operational funds was $4,200,000.
Recommendations and Recovery Steps
Recommendations
1. The district should continue to apply annually for class size reduction facilities funding. Until the
time the district is able to fully implement all four grade levels of class size reduction, unused
class size reduction operational funding should be available to fund a portion of the class size
reduction facilities costs. These applications may also make the district eligible for future state
bond funds for class size reduction.
2. If applicable, apply for Class Size Reduction displaced facilities funds made available from
Propisition 1a.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
88 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
7.2 Implementation of Class Size Reduction – Adequacy of Facilities for Additional
Classes
Professional Standard
The CUSD has provided adequate facilities for the additional classes resulting from the implementation
of Class Size Reduction (CSR).
Sources and Documentation:
1. Inspection of district sites/facilities
2. Interviews with CUSD staff
3. Review of district records
Findings
1. The CUSD has implemented Class Size Reduction (CSR) for its students in grades one through
three and the district is considering additional implementation for kindergarten in the 1998-99
school year.
2. The district has provided adequate facilities for additional classes which have resulted through the
implementation of CSR within grades one through three. This has been accomplished through the
reallocation/modified use of existing space as well as the acquisition of additional relocatable
teaching stations.
Recommendations and Recovery Steps
Recommendation
1. Apply for Class Size Reduction displaced facilities funds made available from Propisition 1a.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 89
➤
0 1 2 3 4 5 6 7 8 9 10
7.3 Implementation of Class Size Reduction – Compliance with CDE Space Require-
ments
Professional Standard
The CUSD has complied with CDE suggested space requirements relative to the provision of educa-
tional environments for the implementation of Class Size Reduction (CSR).
Sources and Documentation:
1. Inspection of district sites/facilities
2. Interviews with CUSD staff
3. Review of district records
Findings
1. The majority of the CSR classes were in teaching stations with approximately 960 square feet.
2. In some instances classes are being conducted in teaching stations which do not meet the Califor-
nia Department of Education suggested square footage requirements.
Recommendations and Recovery Steps
Recommendations
1. It is not possible for the district to develop “standards” at this time.
2. The district should continue to monitor CDE regulations and comply with any new requirements.
It is not possible for the district to develop “standards” at this time.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
90 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
7.4 Implementation of Class Size Reduction – Plans for Permanent Facilities
Professional Standard
The CUSD has developed a plan for the provision of permanent facilities in which to house its CSR
programs.
Sources and Documentation
1. Interviews with CUSD staff
2. Review of district records
Findings
1. While the CUSD had done a commendable job in providing adequate space for the implementa-
tion of Class Size Reduction, no plan exists for the provision of permanent facilities in which to
house all of its CSR programs.
Recommendations and Recovery Steps
Recommendations
1. The district should develop a plan to ensure the provision of permanent facilities as a result of the
district’s implementation of Class Size Reduction programs.
2. Identify available funding sources that may be used to implement the plan. Funding should in-
clude but not be limited to, state Proposition 1a State Class Size Reduction bond funds provided
for unfunded and displaced facilities.
Recovery Steps
1. Conduct a facilities inventory/assessment to determine the actual space allocations for current
Class Size Reduction programs and to identify which of those programs are being implemented in
“non-permanent” facilities vs. permanent facilities.
2. Measure the findings of the aforementioned inventory/assessment with recommendations that are
forthcoming from the State Legislature, California Department of Education and the State Alloca-
tion Board-Office of Public School Construction relative to suggested room size.
3. Develop a plan to correct any space and “permanency” deficiencies that exist within respective
CUSD school sites relative to the delivery of instruction services and programs for Class Size
Reduction programs. A fiscal impact associated with the implementation of this plan needs to be
developed and considered within the broader context of facilities-related needs within the CUSD.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 91
➤
0 1 2 3 4 5 6 7 8 9 10
8.1 Facilities Maintenance and Custodial – Implementation of An Energy Conserva-
tion Program
Professional Standard
The district should have an adopted policy for energy conservation and should take steps to implement
an effective energy conservation program.
Sources and Documentation
1. Board Policy
2. Examination of district records
3. Physical inspection of school site condition
Findings
1. The district did not have an effective policy for incorporation of energy conservation.
2. The district had not implemented the policy effectively to ensure that corrective action was taken
during construction or modernization of facilities.
3. High efficiency lighting system that incorporates high efficiency T8 lamps with electronic ballast
and an active day lighting system. The active day lighting system must be a sun tracking system
utilizing mirrors, reflective light ducts and efficient diffusing lenses combined to create the most
technologically advanced interior day lighting system. The district had not effectively completed
this initiative.
4. Light-emitting diodes (LED) exit lamps 120/277 dual voltage with nicad emergency power pack,
tamperproof head screws, vandal-resistant shield (1/8" thick polycarbonate), flashing emergency
operation (one flash/second). The district had not effectively completed this initiative.
5. High-efficiency electric cooling/gas heating single-package rooftop units. AC systems have
enthalpy control air economizers. When the ambient conditions permits, based on the temperature
and humidity conditions of the outdoor air, the economizers will modulate outside are and return
air dampers to supply 100% of the supply air as outside air. The district had not effectively com-
pleted this initiative.
6. Occupancy sensors that have the capability of simulating space lighting levels from both natural
and artificial sources. To provide automatic control of the lighting level, from the artificial source,
the designer must specify a light sensor location and lighting level control set-point. Occupancy
sensors will turn off the lights during the day when the space is not occupied. The district had not
effectively completed this initiative.
7. Installation of a simplified energy management system that has 365 day calendar scheduling
functions, and optimized start/stop. The system shall be used to control each of the HVAC equip-
ment on a separate channel. An outside temperature sensor shall be used to provide the analog
input data used by the software to develop optimized start/stop times for equipment based on
historical temperature data. The district had not effectively completed this initiative.
92 Facilities Management Assessment and Recovery Plan
8. Roof insulation should be R-30. The district had effectively completed this initiative.
9. Wall insulation should be R-19. The district had effectively completed this initiative.
10.Wall infill should be R-11 with 2" X 2" studs @ 16" O.C. The district had effectively completed
this initiative.
11. Double pane wintergreen 38 laminated sunbrella with shading coefficient of 0.47 and U-value
winter of 0.71. The district had not effectively completed this initiative.
12. Operational training for maintenance and operation’s staff and energy conservation program for
all employees once a year. The district had not effectively completed this initiative.
Recommendations and Recovery Steps
Recommendations
1. Establish a districtwide policy to install high efficient electrical and mechanical equipment.
2. Hold semi-annual meetings with school site and administrative staff on how to be energy efficient.
3. This assessment element cannot be fully implemented without infusion of substantial resources.
The district operating budget cannot fund the improvements needed. An appropriate source of
capital funding must be identified.
4. Seek passage of a local school facilities bond for school repair/upgrade and apply for matching
funds (dollars) from the state. Hire an energy consultant to help implement an effective energy
conservation plan.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 93
➤
0 1 2 3 4 5 6 7 8 9 10
8.2 Facilities Maintenance and Custodial – Preparation of Energy Analyses
Professional Standard
The district should have a comprehensive analysis of their utility bills (all sites) as it relates to their
energy consumption.
Sources and Documentation
1. Board Policy
2. Interviews with Facility Staff
Findings
1. The energy analysis report should reflect the annual cost of utilities for each site.
2. The energy analysis report should also give a detailed report of the energy efficiency of the exist-
ing equipment at each site.
3. The energy analysis report should provide recommendations for energy conservation (savings)
that can be accomplished with the existing equipment (environment).
4. The recommendations contained in the energy analysis report should provide comprehensive
detail of how to achieve any projected savings.
5. The district does not have an energy analysis report (existing, projected or otherwise) for the sites.
Recommendations and Recovery Steps
Recommendations
1. Establish board policy that requires the district to develop a comprehensive energy analysis every
10 years or as changes in circumstances warrant.
2. The district should analyze utility bills every 2-3 years to ensure that the energy conservation
measures (recommendations) are working effectively (savings).
3. Hire an energy consultant to perform the energy analysis.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
94 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8.3 Facilities Maintenance and Custodial – Determination of Eligibility for State
Funding
Professional Standard
The district should have identified all eligible sites for state funding and should have filed an application
for each eligible site with the Office of Public School Construction.
Sources and Documentation
1. Board Policy
2. Interview with Business and Facility Staff
3. Review of the State Allocation Board Agenda Items
Finding
1. The district has made application to the Office of Public School Construction and the State Alloca-
tion Board for all eligible sites.
Recommendations and Recovery Steps
Recommendations
1. The district should continue to try and pass a local facility bond to meet the State’s requirement of
“matching funds.”
2. The district should continue to apply for hardship funding from the State in the interim.
3. Outside consultants should be considered in order to maximize the district’s chances of receiving
funds.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 95
➤
0 1 2 3 4 5 6 7 8 9 10
8.4 Facilities Maintenance and Custodial – Incorporation in Applications for Mod-
ernization/Construction
Professional Standard
The district should have a policy that incorporates the Energy Conservation Recommendations into its
modernization and construction projects.
Sources and Documentation
1. Board Policy
2. Interview with Business and Facility Staff
3. Office of Public School Construction and Southern California Utility program (energy) informa-
tion
Findings
1. There are currently no Board policies regarding the incorporation of energy conservation into
construction projects.
2. The district’s business and facilities staff are aware of the energy conservation incentives provided
by the state and local utility companies.
Recommendations and Recovery Steps
Recommendations
1. Adopt a board policy that provides direction for the inclusion of energy conservation into all
construction projects.
2. Establish board policy that, when a funding source has been identified, to hire an architect and
energy consultant for modernization/construction.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
96 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8. 5 Facilities Maintenance and Custodial – Adequate Maintenance Records and
Inventories
Professional Standard
Adequate maintenance records and reports are kept, including a complete inventory of supplies, materi-
als, tools and equipment. All employees required to perform maintenance on school sites should be
provided with adequate supplies, equipment and training to perform maintenance tasks in a timely and
professional manner. Included in the training is how to inventory supplies and equipment and when to
order or replenish them.
Sources and Documentation
1. Work orders
2. Inventory records
3. Purchase orders for supplies and equipment
4. Site observation of actual inventory
Findings
1. During the site observations and interviews, some site personnel felt that they had adequate access
to supplies for cleaning and maintaining the facilities. A review of the supply closet and the
maintenance rooms showed ample supplies for cleaning however it was not apparent that the
proper supplies needed were available.
2. In some cases, the products used to cleaning some areas were actually solvents for cleaning other
types of spills. While not an immediate danger to the employee, students or faculty, economy of
skill and efficiency in maintaining the sites is a concern.
3. The Maintenance Request form contains lines for the date and signature of the employee perform-
ing the maintenance work. It also includes a line for the supervisor to sign and date the form
signifying the completion of the work. The final signature is that of the site administrator concur-
ring that the job is completed. Of the work orders reviewed and the administrators interviewed,
some work orders did not have all of the signatures or dates of when the work was completed.
4. There is a portion of the maintenance request that asks for the materials used to be delineated. In
many cases, the lines to report the supplies and materials used in the maintenance project were
blank. This does not allow the maintenance department to maintain a proper inventory.
Recommendations and Recovery Steps
Recommendations
1. Require maintenance requests to be completed in total by maintenance worker for all maintenance
work prior to final signoff by any district administrator.
2. Include in the evaluation of maintenance personnel the completeness of maintenance records.
Recovery Steps
1. Revise the “Materials Used” portion of the Maintenance Request so that all maintenance person-
nel are required to account for all materials used on a job.
Facilities Management Assessment and Recovery Plan 97
2. The materials to be included on the maintenance request should only include those that are a part
of the normal inventory.
3. The maintenance department should maintain a computerized inventory of materials.
4. The maintenance of an accurate supply inventory is important to the productivity of the mainte-
nance department. Employees should be held accountable for their part in keeping the inventory
accurate. This is best done in the evaluation process.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
98 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8.6 Facilities Maintenance and Custodial – Procedures for Evaluation of Mainte-
nance and Operations Staff
Standard
Procedures are in place for evaluating the work quality of maintenance and operations staff. The quality
of the work performed by the maintenance and operations staff should be evaluated on a regular basis
using a board adopted procedure which delineates the areas of evaluation and the types of work to be
evaluated.
Sources and Documentation
1. Board Policy
2. Bargaining Group Agreements
3. Job descriptions
4. Sample employee evaluations
5. Interview sampling of employees and supervisors
Findings
1. Article X “Performance Evaluation Procedures” contained in the agreement between the Compton
Unified School District and CSEA Compton Chapter 30 for July 1, 1996 - June 30, 1999, includes
the process for evaluating probationary and permanent classified personnel. This includes the
maintenance and operations staff. It requires that permanent employees be evaluated annually
during April.
2. Section 10.3.3 of the agreement requires the supervisor to expand on an employees evaluation if
the employee is found to be “below competent.” The supervisor must make a statement of the
problem or concern, the desired improvement, suggestions for improvement, and provisions for
assisting the unit member.
3. The Maintenance Request form contains lines for the date and signature of the employee perform-
ing the maintenance work. It also includes a line for the supervisor to sign and date the form
signifying the completion of the work. The final signature is that of the site administrator concur-
ring that the job is completed. Of the work orders reviewed and the administrators interviewed,
some work orders did not have all of the signatures or dates of when the work was completed.
This would be one area of improvement noted in the unit member’s evaluation.
Recommendations and Recovery Steps
Recommendations
1. Require all supervisory personnel responsible for evaluating classified staff to record all cases of
outstanding work, unsatisfactory work, and incomplete maintenance requests as a part of the
evaluation process.
2. Include in the evaluation of maintenance personnel the completeness of maintenance records.
Recovery Steps
1. The district should provide inservice training for all supervisory personnel in the proper documen-
tation of personnel standards.
Facilities Management Assessment and Recovery Plan 99
2. Administrative staff should periodically review evaluations for adherence to the personnel stan-
dards.
3. The maintenance of an accurate supply inventory is important to the productivity of the mainte-
nance department. Employees should be held accountable for their part in keeping the inventory
accurate. This is best done in the evaluation process.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
100 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8.7 Facilities Maintenance and Custodial – Identification of Maintenance and Cus-
todial Responsibilities
Professional Standard
Major areas of custodial and maintenance responsibilities and specific jobs to be performed have been
identified. Custodial and maintenance personnel should have written job descriptions that delineate the
major areas of responsibilities that they will be expected to perform and will be evaluated on.
Sources and Documentation
1. Board Policy
2. Bargaining Group Agreements
3. Job descriptions
4. Handbooks given to M&O employees
5. Interview sampling of employees and supervisors
Findings
1. There is a clear delineation of maintenance and operations staff responsibilities contained in the
employee job descriptions.
2. Between the job descriptions, the Facilities and Grounds Handbook and other related maintenance
manuals, there are very clear descriptions of the expectations of the maintenance and operations
personnel.
Recommendations and Recovery Steps
Recommendation
1. Consolidate all correspondence into one handbook that supports the job descriptions.
Recovery Steps
1. Rewrite individual job descriptions to include references to specific job requirements delineated in
Facilities and Grounds Handbook.
2. Rewrite Facilities and Grounds Handbook to include job responsibilities that are clearer and are
specifically assigned to a type of employee.
3. If graffiti and vandalism are indeed the number one priority for maintenance and operations
personnel, move this item from Item M to Item A in the handbook.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 101
➤
0 1 2 3 4 5 6 7 8 9 10
8.8 Facilities Maintenance and Custodial – Availability of Custodial Supplies and
Equipment
Professional Standard
Necessary supplies, tools and equipment for the proper care and cleaning of the school(s) are available
to staff. Operational staff should be expected to keep the campuses clean. In order for the staff to meet
these expectations, they must be provided with the necessary supplies, tool and equipment as well as the
training associated with the proper use of such.
Sources and Documentation
1. Inventory records
2. Purchase orders for supplies and equipment
3. Site observation of actual inventory
Findings
1. During the site observations, the majority of the site maintenance personnel stated that they had
sufficient supplies and equipment to perform the duties expected of them. This was verified in
most cases by the observer.
2. After observing the classrooms, hallways, lunch areas and bathrooms, even with the proper sup-
plies and equipment, cleanliness of the campuses was inconsistent across the district.
Recommendations and Recovery Steps
Recommendation
1. In-service training for all site personnel regarding the proper use of all cleaning supplies and
equipment.
Recovery Steps
1. All site personnel responsible for the cleaning of the site should receive training at the site for a
complete understanding of what chemicals and equipment must be used to maintain a clean and
safe campus.
2. Maintenance supervisors should evaluate the proper use of the supplies and equipment on a
regular basis to verify that the site personnel are following the training given to them.
3. If the supervisors find misuse or noncompliance with the training given to the site personnel, the
findings must be included in the employee’s evaluation.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
102 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8.9 Facilities Maintenance and Custodial – Implementation of a Preventive Mainte-
nance Program
Professional Standard
The district has an effective preventive maintenance program. The district should have a written preven-
tive maintenance program that is scheduled and followed by the maintenance staff. This program should
include verification of the completion of work by the supervisor of the maintenance staff.
Sources and Documentation
1. Inventory records
2. Copies of preventive maintenance schedules
3. Copies of preventive maintenance checklists
4. Purchase orders for supplies and equipment
5. Site observation of actual program being implemented
Findings
1. Board policy 3510, adopted August 31, 1982, states “An effective educational program requires
clean, healthful, safe, businesslike, and attractive physical facilities. The maintenance and custo-
dial staff is charged with the responsibility of caring for and protecting these facilities.” It con-
cludes by stating “A preventive maintenance program shall be a part of this policy.”
2. The Facilities and Grounds handbook includes a section dedicated specifically to preventive
maintenance. It outlines the conditions that maintenance work will be performed under the pre-
ventive maintenance program. It also describes the new mobile maintenance shop and how it will
handle preventive maintenance tasks. Sample tasks listed include repair or replacement of bal-
lasts, desks, chairs, benches and tables. Sample tasks that will not be done by the mobile unit
include motors and fans, doors, locks, or door closers.
3. Make the preventive maintenance program a part of every employees workday. During the site
observations, some portable classrooms had the air conditioning on and both doors open causing
an unnecessary strain on the unit. This could result in the unit requiring additional maintenance
above the normal maintenance schedule.
Recommendations and Recovery Steps
Recommendations
1. Evaluate the effectiveness of the mobile maintenance shop.
2. Develop an annual report to the Board and administration on the progress of the preventive main-
tenance program.
Recovery Steps
With the major investment the district has made in a mobile maintenance shop, the district must analyze
the benefit of the shop.
1. Interview site administrators for their input of the effectiveness and timeliness of the repairs
requested of the maintenance personnel using the mobile maintenance shop.
Facilities Management Assessment and Recovery Plan 103
2. Review the work orders assigned to the shop to verify that the work requested has been completed
to the satisfaction of the requestor and finished in a timely manner.
3. Include positive or negative findings in the appropriate employee’s evaluation and personnel
folder.
4. Using the information contained in the maintenance requests, develop an annual report to the
Board and administration showing the progress made by the preventive maintenance program.
5. Include long-range estimates of the financial needs of the program.
6. Display the projects in line for preventive maintenance in the coming years.
7. Give examples of how other employees of the district can help reduce emergency repairs by
following some simple steps like:
• Closing the windows and doors when the air conditioning is operating.
• Turning off lights when they leave.
• Turning down thermostats after hours.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
104 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8.10 Facilities Maintenance and Custodial – Adequate Repair and Supervision of
School Buildings
Legal Standard
The governing board shall keep the school buildings in repair and supervised. [EC 17593]
Sources and Documentation
1. Board Policy
2. Sampling of maintenance work orders
3. Job descriptions
4. Work schedules for supervisors
5. Site observations verifying conditions of facilities
6. Interview sampling of employees and supervisors
Findings
1. Board policy 3510, adopted August 31, 1982, states “An effective educational program requires
clean, healthful, safe, businesslike, and attractive physical facilities. The maintenance and custo-
dial staff is charged with the responsibility of caring for and protecting these facilities. In order to
carry out an efficient maintenance program, the custodians must receive the cooperation of the
pupils, the teachers and administration.”
2. The site visitations showed both ends of the spectrum in plant conditions. One school was in need
of painting but was not scheduled for painting this year. Another was recently sandblasted for
painting in the near future. A third was receiving the final touches as a result of modernization
funding. The other campuses spanned the spectrum with the majority on the “needs-work” end of
the spectrum.
3. It is understood that this district is trying to recover from years of shifting funds from the mainte-
nance of facilities to other district priorities. It is also understood that because of the diversion of
these funds, it will take years of major maintenance at higher costs for the district facilities to
return to an acceptable level.
Recommendations and Recovery Steps
Recommendations
1. Fully implement an aggressive facilities recovery plan.
2. Get the public involved.
Recovery Steps
1. Establish the current condition of all facilities in the district.
2. Include in data collection of the condition of the facilities an estimated cost to bring them up to
current standards.
3. Develop a financing plan to fund the needs in a timely manner.
Facilities Management Assessment and Recovery Plan 105
4. Present the financing plan to the Board and administration for review.
5. Once the administration has established the funding needed to repair or replace the facilities,
begin a financing program that could include local bonds used jointly with state construction
revenues
6. The public should become an integral part of the recovery plan. Involvement can include:
• Bond campaigning.
• Facility beautification.
• Community activities after school hours.
• Neighborhood watch.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
106 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8.11 Facilities Maintenance and Custodial – All Buildings, Grounds and Bathrooms
are Maintained
Legal Standard
Toilet facilities are adequate and maintained. All buildings and grounds are maintained. [CCR Title 5 §
631]
Sources and Documentation
1. Board Policy
2. Sampling of maintenance work orders
3. Job descriptions
4. Work schedules custodians and supervisors
5. Site observations verifying conditions of facilities
Findings
1. Board policy 3510, adopted August 31, 1982, states “An effective educational program requires
clean, healthful, safe, businesslike, and attractive physical facilities. The maintenance and custo-
dial staff is charged with the responsibility of caring for and protecting these facilities.”
2. The site visitations showed both ends of the spectrum relating to plant conditions. One school was
recently sandblasted for future painting while others were receiving the final touches on modern-
ization including paint. The other campuses spanned the spectrum with the majority on the “needs
work” end of the spectrum.
3. Bathroom facilities topped the list in most urgent need for cleaning and replacement. Most of the
bathrooms that were operable were quite pungent. One bathroom facility had five toilets without
any privacy partitions. While operable, the fixtures were quite old and in need of repair. The
aroma of the bathrooms is a concern since the site visits were during the first and second days of
the school year when they should have been the cleanest before the students arrived.
Recommendations and Recovery Steps
Recommendations
1. Establish current conditions of toilet facilities and schedule appropriately for repair, replacement
or expansion.
2. Provide on-site inservice training for all district staff that are required to maintain toilet facilities.
Recovery Steps
1. Develop an inventory of all existing toilet facilities and their condition by school site.
2. Schedule repair, replacement or expansion of toilet facilities to bring all district toilet facilities up
to “like-new” condition.
3. Once a school site has toilet facilities in “like-new” condition, require plant managers to maintain
toilets in good working condition with the assistance of the maintenance staff when major mainte-
nance is required.
Facilities Management Assessment and Recovery Plan 107
4. Evaluate the plant manager’s success in maintaining toilet facilities in good working condition.
5. Revise the current job descriptions to include specific responsibilities of the site plant managers as
they relate to toilet facility maintenance. Included in the responsibilities is not only the cleaning
required but the level of minor maintenance that is allowed.
6. Using the revised job description, provide on-site training for the plant managers in the areas of
toilet cleanliness and maintenance.
7. Provide sufficient cleaning and maintenance supplies for the plant managers to meet these respon-
sibilities.
8. Periodically observe the cleaning and maintenance techniques used by the plant managers offering
both positive and negative comments where appropriate.
9. Include in the annual evaluation of the plant managers the specific level of adherence to the job
description.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
108 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
8.12 Facilities Maintenance and Custodial – Implementation of a Planned Program
Maintenance System
Professional Standard
The district has implemented a planned program maintenance system. The district should have a written
planned program maintenance system that includes an inventory of all facilities and equipment that will
require maintenance and replacement. This program should include purchase prices, anticipated life
expectancies, anticipated replacement timelines and budgetary resources necessary to maintain the
facilities.
Sources and Documentation
1. Inventory records
2. Copies of planned program maintenance
Findings
1. A written planned program maintenance system is integral in the proper maintenance of the school
district’s facilities and grounds. It should be seen as the umbrella encompassing the total facility
maintenance program which include emergency maintenance, scheduled preventive maintenance,
and daily routine maintenance.
2. The first key ingredient is clear direction from the Board and administration noting their expecta-
tions of the district staff in maintaining the district’s facilities and grounds.
3. The second key ingredient is the inclusion of these expectations in Board policy and employee job
descriptions.
4. The concept of planned program maintenance is mentioned occasionally in the Facilities and
Maintenance Handbook however it never discusses in detail the need for the program or the actual
implementation. It also does not designate who is responsible for the program success.
Recommendations and Recovery Steps
Recommendations
1. Adopt board policy regarding planned program maintenance system and funding.
2. Create an inventory of all facilities and equipment that require cyclical program maintenance.
3. Develop a planned program maintenance system financial plan.
4. Establish a separate financial account for the planned program maintenance system.
Recovery Steps
1. Develop a board policy that delineates the various aspects of the planned program maintenance
system.
2. Establish in the board policy a minimum funding level that the district should budget annually to
support the planned program maintenance system.
Facilities Management Assessment and Recovery Plan 109
3. Establish priorities for which maintenance projects receive first priority in case of a financial
crisis.
4. Develop an inventory of existing facility’s maintenance needs including roofing, plumbing,
electrical, HVAC, painting, and flooring.
5. Establish the age and most recent renovation or repair of each of the items on the inventory and
the estimated date that repair or replacement should occur and the estimated cost.
6. Create a database in chronological order by date that repair or replacement must occur.
7. Establish the funding necessary to accomplish the repairs for the year.
8. Calendar the projects to determine whether contracting out may be necessary to accomplish all
of the maintenance projects.
9. At a minimum, update the inventory annually for any changes that have occurred during the year
due to maintenance completed, addition of facilities or equipment, demolition of facilities, sale
of equipment, or any other change in status of the facilities or equipment.
10. Using the information developed in the inventory system noted above, establish a long-range
financial plan reflecting the possible fiscal impact of the planned program maintenance system.
11. Present the financial plan to the Board and administration for inclusion in the initial budget
discussions for the coming year.
12. Designate where the funding will come from to accomplish the maintenance requirements.
13. Once the funds have been designated for the planned program maintenance system, a separate
account should be established immediately.
14. All expenses that are charged to the system must receive approval of the Senior Director of
Fiscal Services.
15. This account must be monitored on a quarterly basis for verification of proper expenditures
being charged in the account.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
110 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.1 Instructional Program Issues – Plan for Attractive Landscaped Facilities
Professional Standard
The CUSD has developed a plan for attractively landscaped facilities.
Sources and Documentation
1. Interviews with CUSD staff
2. Review of district records
Findings
1. The CUSD has developed a plan for landscape improvements at approximately six of its existing
school sites.
2. CUSD staff has acknowledged a linkage between school site appearance and positive impacts
upon students’ desire and interest to attend school.
3. Staff acknowledged that improved landscaping can have positive impacts upon staff and commu-
nity morale within and support for the school.
4. Any lack of commitment toward the development of a plan for attractively landscaped plans
appears to be solely based upon funding deficiencies.
5. Implementation of any plan developed will be financially difficult due, in part, to the fact that
these types of improvements are typically not eligible costs for State-funded modernization
projects. Nonetheless, staff displayed a positive attitude toward the development of a landscaping
improvement plan.
Recommendations and Recovery Steps
Recommendation
1. The district should develop a plan to improve the landscaping at the individual CUSD facilities.
Recovery Steps
1. Conduct an inventory/assessment to determine the actual landscaping conditions which exist
within individual CUSD sites.
2. Develop standards of landscaping that are desired at various types of schools (elementary, junior
high, high school, special program sites, etc.).
3. Measure the findings of the aforementioned inventory/assessment with the standards developed to
develop a determination of needs and deficiencies.
4. Develop a broad-based set of potential funding sources to assist in the implementation of a district
Landscaping Plan.
5. Develop a plan to correct any landscaping needs and deficiencies which exist within respective
CUSD school sites. A fiscal impact associated with the implementation of this plan needs to be
developed and considered within the broader context of facilities-related needs within the CUSD.
Facilities Management Assessment and Recovery Plan 111
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
112 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.2 Instructional Program Issues – Districtwide Technology Plan to Benefit All Sites
Professional Standard
The goals and objectives of the technology plan should be clearly defined. The plan should be include
both the administrative and instructional technology systems. There should be a summary of the costs of
each objective and a financing plan should be in place.
Sources and Documentation
1. Determine the existence of a district technology plan.
2. Examine the plan to determine whether all essential elements are considered.
3. Review major goals and objective to determine feasibility and to determine if progress toward
implementation is as scheduled within the plan.
4. Review the existence and adequacy of the financing plan.
5. Review relevant district policies and administrative regulations.
Findings
1. Compton USD does have a draft of a district technology plan for implementation of instructional
technology. The parts of the plan dealing with, staff development, teaching and learning, network
infrastructure and classroom hardware and software are well done. The plan does not address
administrative system needs, beyond the networking standards, and there was no separate plan to
address those important needs.
2. Major goals are well defined, but since the plan is still in draft form, no formal adoption has
occurred. Also because the plan has not been adopted, there has been no tracking or reporting
system established to allow the district to track progress.
3. This district did not have a complete financing plan for implementation of technology. The draft
instructional technology plan relied upon an annual infusion of $2.5 million in funding from
desegregation grants, revenue that is uncertain and may or may not be sufficient to meet plan
goals. There was no financing plan in place for the substantial administrative system upgrades
required to deal with Year 2000 issues and the implementation of the Standardized Account Code
Structure (SACS).
Recommendations and Recovery Steps
Recommendations
1. The district will need to actively manage the technology planning process if progress is to be
made. The technology plan specifies that the plan is for 1997-2002, but as 1999 approaches, it has
still not been finalized and adopted. The plan needs to be completed and adopted.
2. Administrative technology needs should be incorporated into the existing plan or included in a
separate plan.
3. The district should develop a formal tracking system to assess progress toward major goals. The
results should be reported and the goals should be revised periodically.
Facilities Management Assessment and Recovery Plan 113
4. A formal financing plan should be adopted. The financing plan should address total dollars re-
quired, the timing of the need for funds, sources of funding must be identified and cash flow
projections supporting the availability of funding should be prepared.
5. The draft instructional technology plan carries substantial policy implication for the district. It
specifies policies for student access to technology, establishment of new positions, duties of those
positions, commitments of staff development time, and specific learning outcomes among other
things. These are major policy questions that should be considered before they become effective
be default with adoption of the district technology plan.
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
114 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.3 Instructional Program Issues – Lunch Areas are Warm, Healthful and Safe
Legal Standard
The governing board shall provide a warm, healthful place in which children who bring their own
lunches to school may eat their lunch. [EC 17573, CCR Title 5 §14030]
Sources and Documentation
1. On-Site Observation of Cafeterias, Lunch Areas, and Multipurpose Rooms
2. Review of Maintenance Logs
Findings
1. An inspection of several district sites and the lunch room/cafeteria/multi-purpose rooms, indicated
that the district is in general conformance with prevailing codes and laws.
2. The age and condition of some of the district’s cafeterias (primarily due to handicap accessibility
and age of the structure), need to be upgraded.
3. The gradual upgrade of existing cafeterias, and the installation of new electrical services and
equipment to establish economies of scale, reduce operational costs and minimize accidents,
could have a significant impact on the district’s cafeteria fund and reduce liability risk.
4. Eating areas were generally clean, however the aging of the facilities makes it difficult to be
perceived as appropriately clean.
Recommendations and Recovery Steps
Recommendations
1. In addition to Education Code 17573, all facilities plans should conform to state standards as
specified in the Code of Regulations, Title 5, Section 14030. These standards are briefly and
partially summarized below:
• Auxiliary areas such as multipurpose cafeterias, administrative offices and library/media cen
ters shall be adequately sized to accommodate the student population, and allow adaptation for
changing uses.
• Lighting shall be designed to provide comfortable and adequate levels of illumination.
• Delivery and service areas shall be located so as to provide vehicle access without jeopardizing
the safety of students and staff.
2. Plans shall also comply with the Americans with Disabilities Act and its regulations that require
that facilities be designed and constructed so that they are readily accessible to and usable by
individuals with disabilities. (42 USC 12101 - 12213, 28 CFR 35)
3. The district must complete the gradual replacement and upgrade of aged cafeteria facilities as
funds become available through modernization projects, deferred maintenance, or other miscella-
neous funds.
4. Maintenance/custodial/cafeteria staff should continue to be trained on the general industry clean-
ing and safety orders.
Facilities Management Assessment and Recovery Plan 115
Standard Implemented: Partially
plementation Scale:
➤
Not Fully
116 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.4 Instructional Program Issues – Bathroom Facilities are Clean and Operable
Legal Standard
The governing board of every school district shall provide clean and operable flush toilets for the use of
pupils. [EC 17576, CCR Title 5 §14030]
Sources and Documentation
1. On-Site Observation of Student Bathrooms
2. Review of Maintenance Logs
3. Interview On-Site district Personnel
Findings
1. An inspection of several district sites, completed maintenance logs and an inspection of restroom
facilities indicated that the district is in general conformance with prevailing codes and laws.
2. The age and sanitary condition of some of the district’s restrooms (primarily due to handicap
accessibility and age of the structure), need to be upgraded.
3. The gradual upgrade of existing restrooms, and the performance of regular routine maintenance
should help the district reduce over-all operational costs and minimize accidents. This could have
a significant impact on the district’s ability to reduce liability risk.
Recommendations and Recovery Steps
Recommendations
Restrooms shall be sufficient to accommodate the maximum planned enrollment and located on campus
to allow for supervision.
1. The district must complete the gradual replacement and upgrade of aged restroom facilities as
funds become available through modernization, deferred maintenance, or other miscellaneous
sources.
2. Maintenance/custodial staff should continue to be trained on the general industry cleaning and
safety orders.
3. Sanitary measures should be enforced, buildings should be regularly cleaned, and minor repairs
completed, in order to prevent infestations, and eliminate potential health and safety issues.
4. Future site improvement and new construction plans must comply with the Americans with Dis-
abilities Act and its implementing regulations which require that facilities be designed and con-
structed so that they are readily accessible to and usable by individuals with disabilities. (42 USC
12101 - 12213, 28 CFR 35)
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 117
➤
0 1 2 3 4 5 6 7 8 9 10
9.5 Instructional Program Issues – Facility Plans Include Space for Extended Day
Programs
Legal Standard
The CUSD has plans for the provision of extended day programs within its respective school sites. [EC
17264]
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with CUSD staff
3. Review of district records
Findings
1. The CUSD maintains extended day programs at several of its existing school sites. These pro-
grams appear to be utilized by the students and are a definite benefit as a “supplemental program
service” for facilities within the CUSD.
2. While these types of programs are not currently available at all CUSD elementary school sites, it
is believed that the district has done an effective job in developing opportunities for families to
have access to these types of programs within “sub-regions” of the district’s boundaries.
Recommendations and Recovery Steps
Recommendation
1. While no recovery plan steps appear to be required at this time, it is highly suggested that the
CUSD continue to investigate ways to broaden the implementation of its extended day programs
as the benefits for additional student participation appear to be significant.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
118 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.6 Instructional Program Issues – Plan to Maintain Equality/Equity of District
Facilities
Legal Standard
The CUSD has developed and maintains a plan to ensure equality and equity of its facilities throughout
the district. [EC 35293]
Sources and Documentation
1. Interviews with CUSD staff
2. Review of district records
Findings
1. There is a very sporadic level of equality and equity for the facilities provided throughout the
CUSD.
2. In many instances it appears that facilities serve to hinder, rather than facilitate, the delivery of
instruction.
3. It is believed that this sporadic level may be caused, in part, by the nonexistence of an overall
facilities master plan.
4. Improvements have been made to some facilities; however, these improvements don’t necessarily
correspond to an organized and well-articulated plan. These disparities contribute to low levels of
uniform understanding throughout the district as to how and why decisions are made regarding
the selection and prioritization of improvements to respective school sites and district properties.
5. Deficiencies in this area are one of the most troublesome problem areas within the district and
represent a significant challenge for the CUSD.
Recommendations and Recovery Steps
Recommendations:
1. The development of a process through which to address the implementation of facilities im
provements will be extremely difficult but very beneficial. The current system of somewhat
arbitrarily selecting improvements to be made should be exposed and modified to reflect an
implementation system which ultimately utilizes district resources in a systematic, well-articu
lated and more uniformly agreed-upon manner. While it is acknowledged that this process and
resultant changes will be very difficult, it is believed that this represents the most important
and imperative aspect of “recovery” within the district’s facilities program.
2. More clearly identified and understood district-level standards need to be developed with respect
to the numbers and quality of facilities required in order to accommodate the delivery of instruc-
tion to students.
3. The identification and documentation of “sub-areas” within CUSD boundaries is required. This
approach could simplify the task of identifying any facilities-related inequities which exist and
assist in the development of initial “needs” lists by sub-areas and respective schools within the
Facilities Management Assessment and Recovery Plan 119
district. This may be most easily accomplished through the use of high school attendance bound-
aries, although it is probably more important that the CUSD and its constituency work together to
identify the aforementioned “sub-areas.”
4. Specific facility discrepancies that exist at respective sites need to be identified and estimated
costs developed.
5. All of this information will form the basis of the development of a district Facilities Master Plan.
While the outcome of any Facilities Master Plan development will be critically important, it is
believed that the process utilized to develop the Facilities Master Plan will be more important and
offer significant opportunities for the district and its constituents to understand the following:
• The facilities-related needs which exist at all CUSD sites are overwhelming. While the ten
dency to focus upon the needs of individual sites is natural, it is very important for the “whole
picture” to be developed and understood by the CUSD’s constituents.
• The likely outcome of the facilities needs assessment will identify that, while inequities exist
from site to site, the generalized facilities needs throughout the district are uniformly large.
This may serve to diminish any feelings of “have” and have-nots.”
• The generation of costs associated with the of facilities inequities will, no doubt, be enlighten
ing and clarify and quantify the breadth of the problems which exist.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
120 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.7 Instructional Program Issues – Adequate Heating and Ventilation Exists in all
Schools
Professional Standard
All schools shall have adequate heating and ventilation.
Sources and Documentation
1. School sites observations to assess the condition of the facilities, including heating and ventilation
systems.
2. Interviews with plant management personnel and individual classroom users.
Findings
1. The district has evaluated various options regarding natural ventilation and light v.s. security and
property loss. Whenever possible, operable windows have been minimized to reduce risk and
HVAC systems are the prevailing mode of ventilation.
2. Approximately 50% of the rooms visited had malfunctioning, or non-functioning, heating and
ventilation systems. Natural ventilation opportunities have been minimized at various buildings
over time due to safety and security risk prevention measures. These conditions prevent the room
occupants from having adequate heating and ventilation, which are especially problematic during
the summer months.
3. Some of the conditions found include entire classroom wings that had the windows removed and
rooftop HVAC units or systems installed. However, when the units malfunction due to obsoles-
cence or lack of maintenance, the only means of ventilation is a single exterior door.
4. Other conditions observed include teaching and learning areas where HVAC systems were not
properly balanced. Some these problems resulted in room being heated while outside temperature
was above 80(cid:31) F degrees.
5. In some cases, the scope of work of modernized classrooms included a reduction of fenestration
area, replacement of HVAC systems, as well as new and efficient lighting systems.
Recommendations and Recovery Steps
Recommendation
1. Given that the natural light and ventilation is not a viable option to the district, at this time, the
district should continue to systematically repair, replace and maintain HVAC systems throughout
the school site.
Recovery Steps
1. Evaluate and prioritize HVAC needs throughout the district, and include HVAC replacement in all
state modernization projects and deferred maintenance plan when appropriate.
2. Create and/or adhere to a district standard to reduce the number of unit brands and types through-
out. This action will allow the district to standardize maintenance and component replacement.
Facilities Management Assessment and Recovery Plan 121
3. Whenever possible, include a maintenance and training service agreement with the purchase of the
unit.
4. Work with plant managers to be properly informed about the operation of HVAC systems and to
troubleshoot minor problems.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
122 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.8 Instructional Program Issues – Adequate Lighting and Electrical Service is Pro-
vided
Professional Standard
All schools shall have adequate lighting and electrical service.
Sources and Documentation
1. School site inspections to assess the condition of the facilities including lighting and electrical
systems.
2. Interviews with plant management personnel and individual classroom users.
Findings
1. Most schools observed within the district have maximized their electrical capacity and in various
cases lighting levels are relatively low.
2. Modernized schools have allowed for increased capacity to accommodate new requirements as
well as appropriate lighting.
3. Approximately 40% of the rooms visited, especially in the older buildings, had low levels of
lighting. In various cases this condition was due to the fact that windows had been covered up
with dark opaque film or paint to deter viewers from outside. This condition is a result of certain
safety and risk reduction measures taken by the district.
4. A few of the older buildings still have incandescent light fixtures which are not energy efficient,
nor provide the necessary lighting levels for a conducive learning environment.
5. Modernized buildings have been equipped with the proper type and levels of lighting devices. The
scope of work also included some level of electrical service upgrades.
Recommendations and Recovery Steps
Recommendations
1. Given that natural light and ventilation are not viable options to the district, at this time, the
district should continue to systematically repair, replace and maintain lighting systems throughout
the school sites.
2. The district should continue to upgrade electrical services throughout the sites at every available
opportunity.
3. Evaluate and prioritize lighting needs throughout the district, and include light fixture replacement
in all state modernization projects and deferred maintenance plan when appropriate.
4. Create and/or adhere to a district standard to reduce the number of unit brands and types through-
out. This action will allow the district to standardize maintenance and component replacement.
5. Work with plant managers and electrical shop to stock the appropriate devices and fixtures.
Facilities Management Assessment and Recovery Plan 123
6. Identify and prioritize electrical service upgrades throughout the district.
7. Increase electrical capacity at necessary sites at every opportunity.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
124 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.9 Instructional Program Issues – Classrooms are Free of Noise and Other Barriers
to Instruction
Legal Standard
Classrooms are free of noise and other barriers to instruction. [EC 32212]
Sources and Documentation
1. Board Policy
2. Observation of Classrooms
3. District Project Specifications
4. Interviews with district Staff
Findings
1. Most sites that had the construction projects (renovation/modernization) occurring, had regular
working hours: 7:00 a.m. to 5:50 p.m., Monday through Friday, except district legal holidays.
2. The contractors confined their operations to designated areas of the site and did not appear to
unreasonably encumber the site with materials and equipment.
3. Variances between the projects observed were predominantly due to unforeseen conditions or
project timelines.
4. The district recognizes that student classroom time should be dedicated to learning. The district
also believes that classroom interruptions should be kept to a minimum. Correspondence to
teachers shall be distributed in writing.
Recommendations and Recovery Steps
Education Code 32212 expresses the legislature’s intent that all governing boards formally address the
problem of classroom interruptions and adopt a policy to control them.
Recommendations
1. The principal or designee shall keep announcements made through intercom or public address
systems to a minimum and limit announcements to specific times during the day. Announcements
that apply only to teachers shall be distributed in writing.
2. The principal shall establish a fixed time for the delivery of messages to students, except in the
case of emergencies.
3. School maintenance and facility operations, involving noise or classroom disruption, shall be
performed before or after school hours whenever possible.
4. School visitors and observers shall make appointments in advance.
5. Use of the site by vendors and contractors should be limited as follows:
• The contractor shall confine operations at the site to areas permitted by law, ordinances, per
Facilities Management Assessment and Recovery Plan 125
mits and the contract documents, and shall not unreasonably encumber the site with materials
or equipment.
• Notwithstanding the designation of contract limits or the indication of temporary fences or
barricades, the provisions of the contract documents governing certain portions or phases of
the work may require that certain operations be carried out beyond such designated limits.
• Pumping, draining and control of the designated site shall be carried out so as to avoid endan
gering the work or any adjacent facility or property, or interrupting, restricting or otherwise
infringing or interfering with the districts use.
• The contractor shall keep the premises and surrounding areas free from accumulation of
waste materials.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
126 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.10 Instructional Program Issues – Environment Conducive to High Quality Teach-
ing Learning
Professional Standard
The learning environments provided within respective school sites within the CUSD are conducive to
high quality teaching and learning.
Sources and Documentation
1. Inspection of district sites/facilities
2. Interviews with CUSD staff
3. Interviews with CUSD parents/community members
Findings
1. Learning environments provided within respective CUSD school sites are not necessarily condu-
cive to high quality teaching by the instructional staff and efficient learning by students.
2. Significant disparities exist from site to site and there are a number of health and safety issues
which exist throughout district facilities. These unresolved health and safety issues negatively
impact the quality of learning environments, staff and student morale, and hinder efforts toward
raising standards and expectations for students and staff.
3. There is a lack of uniformity relative to instructional methodologies and expected outcomes for
the district’s students.
Recommendations and Recovery Steps
Recommendation
1. Concurrent with the development of a district Facilities Master Plan should be improvements in
the identification and articulation of CUSD standards for student learning and for the suggested
methods for the delivery of instruction. Student learning and the delivery of instruction must form
the basis of any determination for modifications to existing facilities and the development of new
facilities.
Recovery Steps
1. A commitment should be made toward the identification and articulation of CUSD standards for
student learning and for the suggested methods for the delivery of instruction. This commitment
should form the basis r all deliberations and decisions regarding modifications to existing facili-
ties and the development of new facilities.
2. Instructional staff should be included as an integral and participating member of all facilities
planning efforts which lead to the development of plans for modifications and/or additions to
existing facilities and for any potential new school sites. It is suggested that student representation
be included within planning committees for secondary school facility projects.
3. A strong linkage needs to be developed between the planned expenditure of capital facilities funds
Facilities Management Assessment and Recovery Plan 127
and the improvement of learning environments provided for students and staff. Facilitation of the
delivery of high quality instruction must be the overriding concern when capital facility expendi-
ture plans are being developed. This concept needs to be formalized through Board policy.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
128 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
9.11 Instructional Program Issues – Facilities Reflect Community Standards and
Expectations
Professional Standard
Facilities within the CUSD reflect the standards and expectations established by the community.
Sources and Documentation
1. Inspection of district facilities
2. Interviews with CUSD staff
3. Interviews with CUSD parents/community members
Findings
1. It is extremely difficult to assess the degree to which facilities within the CUSD reflect the stan-
dards and expectations established by the community.
2. One of the most significant challenges which exist within the CUSD is the tremendously inconsistent
level of standards and expectations found within various areas of the district and its diverse constitu-
ency.
3. There is an arbitrary and inconsistent set of standards and expectations which exist. It is believed
that this inconsistency is a major potential impediment toward the development and implementa-
tion of a district Facilities Master Plan which should lead to widespread improvements within the
district’s instructional program and the learning outcomes of students.
Recommendations and Recovery Steps
Recommendation
1. Improve the connection between the facilities within the CUSD and the standards and expecta-
tions established by the community.
Recovery Steps
1. Due to the inconsistent level of standards and expectations found within various areas of the
district and its diverse constituency, the CUSD must develop a plan to identify and understand the
standards and expectations of its constituents. While these standards and expectations may not
necessarily coincide with the district’s standards and expectations, it is believed that completion
of a process to identify these issues will be very beneficial and will provide opportunities for the
district to more openly communicate with community members.
2. A better understanding of community standards and expectations for CUSD facilities must be
developed to enable the district to identify and quantify discrepancies which exist between exist-
ing and desired conditions.
3. An analysis needs to be conducted to determine the similarities and differences which exist between
Facilities Management Assessment and Recovery Plan 129
district standards and expectations and those of the community. Findings from this analysis can form
the basis of discussions between CUSD representatives and community members/leaders to determine
the methods and funding required to eventually implement a facilities improvement plan which ad-
dresses the needs of the district and its communities, as is financially feasible. Any areas of improve-
ment which are determined to not be financially nor programmatically feasible need to be articulated to
community members/leaders for their understanding and contemplation. Alternative methods of
implementation and/or funding may be the result of this additional contemplation by the community if
the “unmet need/s” warrant such consideration and have widespread support.
Standard Implemented: Not
Implementation Scale:
➤
Not Fully
130 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
10. 1 Community Use of Facilities – Plan to Promote Community Involvement in
Schools
Professional Standard
The district should have a plan to promote community involvement in schools.
Sources and Documentation
1. Adopted CUSD Governing Board Policies
2. CUSD Civic Center Policy
3. CUSD Civic Center Implementation Procedure
4. Site Utilization Records
5. CUSD district Newsletters, press releases, community forum summary reports
Findings
1. While the CUSD Board of Education has no direct policy about promoting community use of
facilities, general policy and implementation clearly favors such activity. (The closest actual
policy regarding this issue is part of the 9/8/98 “Community Relations 1000” Policy: “Staff
development/training will be provided for parents, teachers, paraprofessionals, volunteers and
other appropriate school personnel including those participating in other programs on site such as
Special Needs, Head Start, Children Centers, Free to Grow, etc.” emphasis added.)
2. The Civic Center policy/application/rules®ulations for community use of facilities foster such
use. The policy is clear, easy to comprehend and complete (although available only in English).
3. The one-page application for use of facilities is initiated at the site level, not at the district office,
increasing the capacity for community access of the program.
4. The district’s Civic Center program is well utilized by the community. July records show 20
community groups accessing CUSD facilities. The participating groups ranging from political
groups to church groups, to youth athletic leagues, to extension programs for academic and
vocational schools. Periods of use range from less than two hours to full-day use for a week or
more, with some use permits approaching the three-month maximum use window before reappli-
cation is required.
5. The district clearly, and appropriately, budgets its resources to providing these services, instituting
fees to cover supervision after school hours and recently requiring groups to provide portable
restroom facilities as needed because of the damage and wear to school lavatory facilities during
community-use periods.
6. Community Health Centers are based at schools. Comprehensive parent education programs have
enrolled more than 600 parents.
7. Whereas these programs are well publicized by the district, the more mundane - and more com-
mon - aspects of community use, such as the use of playing fields by youth soccer leagues, are not
highlighted in press releases, newsletters and community forums.
Facilities Management Assessment and Recovery Plan 131
Recommendations and Recovery Steps:
Recommendations
1. The Board should adopt a direct, guiding policy regarding the community use of district facilities.
2. To the extent that the district can bear more community use of its facilities, (bilingual) efforts
should be made to inform all community groups of the availability of district facilities for com-
munity use.
3. The Civic Center application form should be made available in Spanish.
4. District communication to the community should recognize this program.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
132 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
10. 2 Community Use of Facilities – Compliance with Civic Center Act for Commu-
nity Use
Professional Standard
Education Code Section 38130 establishes terms and conditions of school facility use by community
organizations, in the process requiring establishment of both “direct cost” and “fair market” rental rates,
specifying what groups have which priorities and fee schedules.
Sources and Documentation
1. CUSD Board Policies 91-92-328 and 98-99-020
2. Internal accounting records
3. CUSD “Civic Center Act Administrator Book”
4. CUSD “Request for Use of School Facilities”
5. SSC Survey of 139 Individual District Civic Center Act Policies (5/19/1995)
Findings
1. The CUSD implementation of its Civic Center obligations is faultless; district policy is clear and
direct, and unquestionably within the spirit and letter of the Education Code.
2. Distinction is appropriately made between types of groups (non-profit vs. for profit — school/
youth vs. other - church association) and the appropriate fee schedules (free, direct cost, fair
market) are applied even to the point of clarifying that nominal fees for refreshment do not qualify
as an entrance fee for categorical purposes.
3. Fee schedules are solidly supported by actual expense records in the “Administrator Book.”
4. The rates charged for both “direct cost” and “fair market” fall within established practical norms,
tending toward the high end (meaning less general fund encroachment due to community partici-
pation).
Recommendations and Recovery Steps
Recommendation
1. The district is to be commended for its implementation of this complex and unwieldy program.
Upon next printing of the request form, note should be made of the new Education Code sections
assigned to the program. Additionally, the district may want to acknowledge 1994 legislation
(Education Code Section 38134(c)) allowing for free use by church athletic leagues.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 133
➤
0 1 2 3 4 5 6 7 8 9 10
10. 3 Community Use of Facilities – Maintenance of Records and Support for Rea-
sonable Charges
Professional Standard
Districts should maintain comprehensive records and controls on civic center implementation and cash
management.
Sources and Documentation
1. CUSD Board Policies 91-92-328 and 98-99-020
2. Internal accounting records
3. CUSD “Civic Center Act Administrator Book”
4. CUSD “Request for Use of School Facilities”
5. SSC Survey of 139 Individual District Civic Center Act Policies (5/19/1995)
Findings
1. The CUSD implementation of its Civic Center obligations is exceptional.
2. Controls are numerous, beginning with right-of-refusal given to site principals. Multiple check-
points at each step ensure compliance for such crucial items as insurance documents.
3. Applications are first completely filled out in quadruplicate at the site in question with principal’s
approval and all required insurance documentation.
4. The request and supporting documentation is sent to the district office, where three signatures are
required for approval (including the facilities director and the CBO) and then faxes are sent to the
CUSD public safety department, the operations department, and the actual school site. A single
district staff member maintains records in a binder dedicated to that purpose.
5. All payments are made directly to CUSD’s fiscal department.
Recommendations and Recovery Steps
Recommendation
1. The district is to be commended for its implementation - yet should remain cognizant of the
opportunities this program presents for fraud and abuse.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
134 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
11. 1 Communication – Communication of Facility Condition and Needs
Professional Standard
The district’s public information office should coordinate a full apprisal to students, staff and community
of the condition of district’s facilities.
Sources and Documentation
1. Staff Bulletins
2. Press Release Files
3. Distribution Lists
4. Newsletters
5. Newspaper Clip Files
6. Radio and Television News Scripts
7. Public Forum Powerpoint Files
Findings
1. The district has an established an effective public relations program, complete with local access
cable program, internal and external district newsletters, an active press release component, and
regularly scheduled public forums (with more than 1,300 community members in attendance over
the past two years). The publications are distributed in English and Spanish, and simultaneous
Spanish translation is provided at the public forums. In all of these efforts, the facilities situation
is given high priority, second only to student achievement.
2. The press release distribution list includes dozens of print and electronic media outlets, as well as
the district’s board members, department heads and principals. A bulky “clip file” attests to the
efficacy of the media efforts.
3. We found that the several month ongoing vacancy at the position of Public Information Officer
(PIO) has had a negative effect on the district’s more ambitious and enterprising communications
activities (such as a publication hiatus for the 16-page bilingual tabloid “Our Schools/Nuestras
Escuelas) despite efforts to fill in made by a capable administrative assistant.
4. The procedures that were in place regarding press release distribution continue to be followed and
new programs such as “WeTip” are rolling forward, but the quantity, quality and direction of
efforts have declined. A new PIO has been selected and is scheduled to begin work in December,
and this situation should right itself.
5. Despite the PIO vacancy, there is evidence that the communications efforts have been successful
in reaching community members. Local bond campaign results can be viewed as the acid test of
community support for school facilities. And in this light, Compton has been quite successful,
increasing voter support from 55 percent to more than 66 percent in successive elections, with the
higher yield taking place despite a far higher voter turnout and the decision to forego hiring a
campaign consultant for the second attempt.
Facilities Management Assessment and Recovery Plan 135
Recommendations and Recovery Steps
Recommendations
1. The district should fill the Public Information Officer vacancy as soon as possible.
2. Assessment should be taken after three months service by the new Public Information Officer to
determine if the activity and enterprise levels have returned to earlier standards.
3. The public information officer should work closely with the facilites planning committee.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
136 Facilities Management Assessment and Recovery Plan
➤
0 1 2 3 4 5 6 7 8 9 10
11.2 Communication – Communication of Actions Taken, Planned, Progress Made
Professional Standard
The district should apprise students, staff and community of efforts to rectify any substandard condi-
tions.
Sources and Documentation
1. Staff Bulletins
2. Press Release Files
3. Distribution Lists
4. Newsletters
5. Newspaper Clip Files
6. Radio and Television News Scripts
7. Public Forum Powerpoint Files
Findings
1. Facilities are openly acknowledged by staff as one of the two “hot button” issues facing the
administration. Communications efforts reflect this priority.
2. Press releases mark significant achievements (safety and security upgrades, roofing work, a
facilities forums with Vice President Gore); many are subsequently covered by the local media.
3. The most recent “Our Schools” publication featured articles on the school bond, new relocatable
classroom acquisition and a $4.2 million renovation program.
4. The most recent “District Update” newsletter highlighted renovations, as did the “Community
Partnership Newsletter,” which targets the business and non-school Compton community.
5. In the most recent (October 7, 1998) community forum, for instance, the State Administrator
dedicated slides 10-15 and 18 &19 (out to 30 slides) to facilities.
6. Much of the information provided by the district has a distinctly districtwide perspective, dealing
with projects in clusters, while parents and community members tend toward parochial ownership
of their local schools alone. (One notable exception to this was the distribution to each school’s
parents the top-10 priority list for facilities improvements at that school.)
Recommendations and Recovery Steps
Recommendations
1. The district should consider site-by-site releases with site-specific detail for distribution by indi-
vidual site. This would respond to neighborhood interests in individual sites, and would foster
central office accountability as well as local loyalty.
2. The facilites planning committee should be utilized to communicate additional information.
Standard Implemented: Fully - Substantially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 137
➤
0 1 2 3 4 5 6 7 8 9 10
11.3 Communication – Communication of District Standards and Plans
Professional Standard
The district should provide clear and comprehensive communication to staff of its standards and plans.
Sources and Documentation
1. Interoffice memoranda
2. Department of Facilities and Operations Memoranda
3. CUSD Department Goals and Objectives
4. ACLU Response Items Task Assignment Grid
5. Staff Interviews
Findings
1. In many areas, the district facilities office has actively upgraded or implemented entirely new
facilities standards. These standards are clearly expressed in memoranda and board policies such
as:
• Prompt replacement of all plywood window coverings with glass or plexiglass
• Immediate hazardous electrical fixture inventory
• 24-Hour deadline for facility repair once reported
• Identification and removal of all hazardous playground equipment
• The “UNOCAL Standard” - whereby every restroom is inspected and cleaned if necessary at
least three times a day.
2. An entire Maintenance Department Goals & Objectives catalogue for 1998-99 including: more
timely filling of vacancies; two-day deadline on contracting out decision-making; establishment
of a restroom cleanliness and anti-vandalism special projects crew.
3. While these standards are clear and comprehensive, there often appears to be a communication
gap between the facilities office and the rest of the district staff - particularly site staff. The stan-
dards are meaningless unless publicized and acted upon.
Recommendations and Recovery Steps
Recommendations
1. Both for implementation and communications purposes, all staff - particularly site administrators -
needs to be more actively involved in the communication of standards and plans.
2. This communication should not be the responsibility of the facilities department. Once standards
and plans are devised, complete distribution to all staff should become one of the responsibilities
for the new PIO.
3. Site level staff needs to be apprised of all facilities standards and plans in order to both expedite
the projects and provide accountability as to results.
4. The facilities planning committee should be utilized to assist in the communication with staff.
138 Facilities Management Assessment and Recovery Plan
Standard Implemented: Partially
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 139
➤
0 1 2 3 4 5 6 7 8 9 10
11.4 Communication – Meaningful Involvement of All Stakeholder Groups
Professional Standard
All stakeholder groups should be directly involved in a meaningful manner regarding the district’s
facilities and their option.
Sources and Documentation
1. “7/11 Committee” Minutes
2. Operation School Watch documentation
3. WeTip documentation
4. Community Forum presentations
5. ACLU Findings
6. Staff Interviews
Findings
1. The district aggressively solicits community input regarding its facilities.
2. The district supports an official and active facilities advisory committee (named 7/11 for the
membership parameters) which advises on even such matters as property disposal.
3. Operation School Watch enrolls community support in monitoring sites for theft and vandalism.
4. “WeTip,” an anonymous 1-800 hotline — will soon be established (goal date 1/1/99) to provide
community members and staff with a way to identify unsafe working conditions, safety viola-
tions, property damage and facility problems. The draft pamphlet announcing the program states:
“Compton Unified School District is striving to improve the condition of its schools and educa-
tional facilities. While our district has a plan in place to address concerns about our existing
facilities, situations or conditions that we do not know about may arise and may need to be ad-
dressed immediately or on a prioritized basis.”
5. The CUSD director of facilities meets periodically with the CUSD student ASB membership to
discuss facilities and maintenance issues.
6. The manager of the Community Partnership Staff meets daily with community members. Facili-
ties remain an issue of crucial importance to the community, and their concerns are relayed back
to the district office.
7. When developing the project list for the school bond, a series of public hearings were held at each
school site, with teachers, parents, staff, site safety committees and others developed a three-
tiered priority list for each school that in turn provided the basis for the bond expenditures. (The
top-10 list from each school was later sent to each of that school’s parents.)
8. The November 3 bond results indicate that the district-community relationship is instilling confi-
dence in CUSD’s capability to manage its capital plant.
140 Facilities Management Assessment and Recovery Plan
Recommendations and Recovery Steps
Recommendation
1. The active solicitation of community input regarding facilities may be in response to a crisis - but
these efforts should remain in place once the crisis is over.
Standard Implemented: Fully - Sustained
Implementation Scale:
➤
Not Fully
Facilities Management Assessment and Recovery Plan 141
➤
0 1 2 3 4 5 6 7 8 9 10