FACILITIES MANAGEMENT
Summary of Findings and Recommendations
The Facilities Management and Planning Division has made some progress since the last review
in addressing the recommendations in the Assessment and Recovery Plan. Most of the progress
has occurred with respect to planning for changes and documenting policies and procedures. The
Facilities Division also has been actively involved in restructuring to address the district's budget
shortfalls.
Among the major changes that have occurred since the September 2003 review was the
elimination of approximately 70 custodial positions; identification of five school sites for
potential closure at the end of the 2003-04 school year; reallocation of general fund resources
from facilities to other district needs; and shifting to a results-based budgeting approach, giving
principals responsibility for allocating resources for maintenance and operations.
Custodial staff reductions were made based on industry standards for the ratio of custodians to
building square footage. The five schools that were selected for closure were selected based on
their small enrollment, low educational performance, and proximity to other schools. The district
estimates that the closure of these proposed sites would result in a savings of $2 million as a
result of reductions in maintenance, operations, and staffing costs. The proposal has been met
with concern from the community, board members, and school site staff. However, the district's
financial problems necessitate the consideration of dramatic changes such as staff reduction and
building closures.
The Facilities Division staff is working diligently to meet the district's facilities and maintenance
needs with fewer resources. Division managers understand that they must develop processes and
policies to allow staff to work more efficiently, but must also mandate that all staff members do
their jobs well. Consequently, the division is working to develop custodial and inspection
standards that site teams can use to guide their work; providing principals with control over site
resources and holding them accountable for the appearance and cleanliness of their sites; and
modifying staff evaluation criteria and procedures.
Although the Facilities Division is making important improvements, the condition of the district's
facilities remains poor. For example, at more than one-half of the sites visited for this review,
bathrooms were unclean and without toilet paper, exterior and interior spaces suffered from
vandalism, and fire safety equipment was damaged or missing. Facilities Division staff continue
to work in a reactive mode and appear unable to catch up with the wear, tear, and damage that is
inflicted on the buildings and grounds of the district’s facilities. The Facilities Division is doing a
reasonable job addressing most of the district’s maintenance needs. However, Facilities Division
staff alone can not make the district’s buildings clean, safe and productive learning environments.
A significant amount of the district's maintenance funding goes towards repairing preventable
damage. Attention must be given to developing and implementing proactive measures to prevent
vandalism and graffiti and to ensure that collective bargaining agreements permit staff to be held
accountable for meeting meaningful job and performance standards. Unless and until such actions
are taken, the district will be hampered in its efforts to improve its facilities to ensure that all
students in the district are welcomed by safe, clean and productive learning environments, and
will continue to expend limited resources on preventable repairs.
1
The following are priority areas for the Facilities Department to address and will require the
support of the State Administrator, the executive cabinet and the school board to fully address
these areas.
Develop a comprehensive Graffiti and Vandalism Abatement Plan and approach.
This plan must include participation from local law enforcement, Executive Directors,
principals, students, custodians, maintenance staff, parents, and community members.
The plan should be proactive and outline procedures, consequences, and specific
responsibilities for all involved parties. It will necessitate campuswide beautification and
pride-building activities, as well as increased supervision in “problem areas.” The district
may consider implementing a pilot at one or two schools to test various approaches and
develop models for success.
Update the Facilities Master Plan. In the absence of an up-to-date Facilities Master
Plan, the district lacks a blueprint for guiding facility decisions. The plan must include
priorities, time lines, costs, and suggested funding sources for all projects. Guidelines or
“rules” for how projects are to be prioritized and approved must be developed. This
should include a ranking system that assigns scores to both individual projects and entire
school sites. The plan also should be coordinated with the district's deferred maintenance
plan.
Update evaluation instruments and implement maintenance and custodial
standards. The district maintains custodial cleaning standards, but they are not currently
followed or enforced. The district needs to develop an evaluation instrument and process
that is linked to performance standards. Collective bargaining agreements should be
renegotiated to allow for their use. The staff must also be trained on how to meet the
standards and supervisors trained on how to use the standards to evaluate employees.
Similar standards and evaluation processes are also needed for the staff in the Buildings
and Grounds Department.
Acquire a more sophisticated Computerized Maintenance Management System
(CMMS). The district should consider replacing the existing CMMS system to support
results-based budgeting. The current system does not support the following functions:
tying work orders to inventory and payroll (necessary for job costing); identification of
areas in need of preventive maintenance; generating work orders based on a preventive
maintenance schedule; allowing principals to track the status, time estimates, parts and
materials linked to a particular work order; or integrating equipment inventory with
equipment life expectancies, costs, and replacement schedules. Investing in a new system
will allow the district to allocate resources more appropriately, position itself for
preventive maintenance, and support a results-based budgeting process.
2
1.7 School Safety – Installation and Operation of Outside Security
Lighting
Professional Standard
Outside lighting is properly placed and monitored regularly to ensure the
operability/adequacy of such lighting to ensure safety while activities are in progress in
the evening hours. Outside lighting should provide sufficient illumination to allow for the
safe passage of students and the public during after-hours activities. Lighting should also
provide security personnel with sufficient illumination to observe any illegal activities on
campus.
Progress on Implementing the Recommendations of the Recovery Plan
1. District lighting is checked and serviced twice annually, when the buildings and
grounds staff changes light timers for daylight savings. Buildings and grounds staff
members replace all nonfunctional exterior light fixtures that are reported as work
orders, although this process can be delayed when dependent on special-order light
bulbs. According to the buildings and grounds staff, the school site staff has become
accustomed to nonfunctioning lights, and problems with exterior lighting are not
always regularly reported. The Director of Buildings and Grounds is working with the
Director of Custodial Services to encourage custodians to replace light bulbs that are
accessible by a six-to-eight foot ladder.
2. Modernization plans encompass lighting; however these plans do not always include
the promotion of vandalism-resistant exterior lighting. The district should consider
installing light fixtures that discourage vandalism. For example, mounted exterior
lights that reflect light downward and are more difficult to shoot out as are fixtures
with protective cages. This is most important for sites that experience regular
problems with vandalism.
3. The school site staff and district project managers indicate that many schools lack
adequate exterior lighting to ensure safety and security. In some cases, this is due to
insufficient lighting. Currently, no resources are budgeted for more outside lighting.
At several campuses, exterior lighting has been disabled by vandalism. The district
should take action to prevent vandalism (see Standard 1.8). The district also should
work with the Oakland Police Department to determine whether night patrols can be
modified to increase police presence on campus. Currently, night patrols consist of
patrol cars that merely drive by campuses, leaving areas that are not visible from the
street largely unsupervised.
Standard Implemented: Partially Implemented
January 2000 Rating: 0
September 2003 Rating: 2
March 2004 Self-Rating: 3
March 2004 Rating: 3
Implementation Scale:
3
1.8 School Safety – Graffiti and Vandalism Abatement Plan
Professional Standard
The district has a graffiti and vandalism abatement plan. The district should have a
written graffiti and abatement plan that is followed by all district employees. The district
provides district employees with sufficient resources to meet the requirements of the
abatement plan.
Progress on Implementing the Recommendations of the Recovery Plan
1. The district has made little progress in this area during the past six months. Graffiti
and vandalism continue to be significant and demoralizing problems. In February
2004, the Assistant Superintendent of Facilities Planning and Management sent a
memorandum to the district’s executive cabinet discussing the need to increase site
monitoring, but no comprehensive Graffiti and Vandalism Abatement Plan has yet
been developed. Attention must be given at the district’s highest levels to developing
and implementing proactive measures to prevent rampant incidents of graffiti and
vandalism. Combating this challenge must become a districtwide responsibility, and
will necessitate active participation from executive directors, principals, custodians,
teachers, students, parents, and community members. The district staff must work
together to develop a plan that outlines procedures, consequences, and specific
responsibilities for all involved parties. It should then hold information or training
sessions to ensure that all staff members with responsibilities to support the plan
clearly understand their roles and responsibilities. For school sites that have
consistent problems with graffiti and vandalism, this will include improving
supervision in problem areas.
2. The Facilities Division staff is doing a reasonable job at keeping up with most of the
district’s maintenance needs, but the challenges of addressing graffiti and vandalism
are such that staff can only respond in a reactive manner. Until a coordinated effort is
made to implement proactive measures, the district will be limited in how much it can
improve its facilities. It may also want to consider creating a vandalism fund to
ensure that the Facilities Division has adequate resources to address site needs.
Additionally, the district should take steps to structure collective bargaining
agreements that allow the staff to be held accountable for meeting job and
performance standards (see Standards 8.6a and 8.6b). Until such actions are taken, the
district will continue to spend precious resources on preventable repair work.
3. The district has not yet implemented an incentive program to reward schools that are
able to decrease incidents of graffiti and vandalism. It also should encourage
campuswide beautification and pride-building activities. The district may consider
implementing a pilot program at one or two schools to test various approaches and
develop models for success.
4. Local law enforcement has not yet been consulted to develop a graffiti and vandalism
abatement plan. The plan should ensure that after-hours monitoring of school sites
includes yard areas that are not visible when police drive by campuses.
4
Standard Implemented: Partially Implemented
January 2000 Rating: 3
September 2003 Rating: 1
March 2004 Self-Rating: 4
March 2004 Rating: 1
Implementation Scale:
5
1.12 School Safety – Inspection and Correction of Unsafe Buildings
Professional Standard
Building examinations are performed, and required actions are taken by the Governing Board
upon report of unsafe conditions [EC 17367].
Progress on Implementing the Recommendations of the Recovery Plan
1. In conjunction with the Oakland Fire Department, the district annually inspects every
school site to ensure compliance with fire safety requirements. These inspections are
focused on safety and do not encompass all maintenance needs. A staff member from
the buildings and grounds department typically accompanies the Fire Inspector and
notes additional building maintenance needs. The Director of Custodial Services is
also training custodial field supervisors to conduct more thorough building
inspections, and is in the process of revising the custodial Site Inspection Form to
align with district maintenance and custodial standards. The director expects
custodians to inspect sites once or twice a month, and the central office will monitor
results. In addition, the district has adopted an Injury Illness Prevention Plan (IIPP)
that incorporates facility inspections to be completed by the site administration and
custodial staff. Training of the site administration and custodians is required to
support the IIPP’s implementation. In addition to training, the district must ensure
that all custodial, maintenance, and the site staff understand their responsibilities on
building inspections. The district’s decentralized approach to building inspections is
not as thorough as a trained tradesperson’s, but if successfully implemented, it will be
a substantial improvement from the current practice. The district should evaluate its
progress in implementing the IIPP and track what effect the inspection process may
have on work-order request volume. If the IIPP does not result in substantial
improvements, the district should consider designating an independent inspector to
supplement or replace the school-based inspection process. This inspector should be
skilled in all trade areas and be able to quickly assess each building to identify
maintenance needs.
2. The Director of Buildings and Grounds has documented a prioritization policy for
handling work orders and has prepared a handbook to be shared with principals so
they understand how their requests are handled (see Standard 8.12). The district
should consider acquiring a more sophisticated CMMS that will provide district staff
and principals with the capability of checking the status on their work requests (see
Standard 8.8).
Standard Implemented: Partially Implemented
January 2000 Rating: 2
September 2003 Rating: 1
March 2004 Self-Rating: 4
March 2004 Rating: 4
Implementation Scale:
6
1.14 School Safety – Sanitation is Maintained and Fire Hazards are
Corrected
Professional Standard
Sanitary, neat, and clean conditions of the school premises exist and the premises are free
from conditions that would create a fire hazard [CCR Title 5 Section 633].
Progress on Implementing the Recommendations of the Recovery Plan
1. The district is currently undergoing comprehensive inspections by the Oakland Fire
Department to ensure that sites are free from fire hazards. It is also working to
implement regular inspections by custodians and principals (see Standard 1.12). The
review team observed that at several middle and high school sites, fire extinguishers
and hoses had been removed and alarms had been disabled because of repeat
incidents of vandalism. There is still a need to implement new procedures to reduce
vandalism (see Standard 1.8). The Custodial Services Department is implementing
new bathroom cleaning procedures (see Standard 8.9/8.10), but still needs to
implement and enforce custodial cleaning standards (see Standard 8.6a).
2. Not all appropriate personnel have been trained in the topics outlined in the IIPP (see
Standard 1.24).
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 1
March 2004 Self-Rating: 4
March 2004 Rating: 4
Implementation Scale:
7
1.16 School Safety – Fire Extinguishers and Inspection Information
Available
Professional Standard
Appropriate fire extinguishers exist in each building and current inspection information is
available [CCR Title 8 Section 1922(a)].
Progress on Implementing the Recommendations of the Recovery Plan
1. The district has a contract with a private firm to inspect and refill fire extinguishers
annually. Current inspection information is available for all fire extinguishers.
Despite these measures, the review team observed at some sites extinguishers that
were expired or in need of refilling.
2. The Custodial Services Department plans to implement a system providing for
custodial site supervisors to check fire extinguishers, alarm pulls and sensors
monthly. These inspections will be recorded on a form and require the signature of
the principal. Copies will be kept on site and in the custodial services office. This
system has not yet been implemented.
3. Extinguishers are usually serviced or replaced annually and immediately after each
use. However, at some sites, vandalism of extinguishers is pervasive. Extinguishers
are regularly stolen or discharged, or are removed and hidden by the site staff to
prevent these types of incidents. The review team visited several sites where the
majority of hoses and extinguishers had been removed. This is a serious safety issue
and is outside of the Facilities Division’s control. Improving site supervision and
preventing vandalism of fire safety equipment should be a high priority for site level
and district staff (see Standard 1.8).
Standard Implemented: Partially Implemented
January 2000 Rating: 5
September 2003 Rating: 4
March 2004 Self-Rating: 6
March 2004 Rating: 4
Implementation Scale:
8
1.24 School Safety – Conduct of Periodic Safety Training for Employees
Professional Standard
The district conducts periodic safety training for employees. District employees should
receive periodic training on the safety procedures of the district.
Progress on Implementing the Recommendations of the Recovery Plan
1. The district’s Risk Management Department now oversees the Environmental Health
and Safety Manager position. The person filling this position is still responsible for
implementing a comprehensive safety program throughout the district.
2. The district has adopted an Injury Illness Prevention Plan (IIPP) that requires safety
training for all the district staff. The district is still working to ensure that all staff
members receive appropriate training. The Environmental Health and Safety Manager
is trying to work with principals to ensure compliance, however it does not seem to be
a priority at the site level. The district should instruct executive directors and
principals to make this safety training and implementation of the IIPP a priority.
3. The Environmental Health and Safety Manager has conducted extensive safety
training with buildings and grounds managers with the expectation that the managers
will train their own staff. This seems to be occurring with some regularity. The
Director of Custodial Services is still working with the Environmental Health and
Safety Manager to schedule and implement a comprehensive training plan for
custodial staff. The modules on which custodians will be trained have been
developed, but training sessions have not yet been initiated. Custodial field
supervisors will conduct and oversee most training sessions, and principals will be
involved as well.
Standard Implemented: Partially Implemented
January 2000 Rating: 2
September 2003 Rating: 3
March 2004 Self-Rating: 4
March 2004 Rating: 3
Implementation Scale:
9
2.1 Facility Planning – Maintenance of a Long-Range Facilities Master
Plan
Professional Standard
The district should have a long-range school facilities master plan.
Progress on Implementing the Recommendations of the Recovery Plan
1. The district’s current Facilities Master Plan was last updated in 2001 and is in need of
new revisions. The district has selected an outside consultant to update the plan, a
process that will take approximately six to12 months. As previously recommended,
the updated Facilities Master Plan should include:
• Priorities, time lines, costs, and suggested funding sources for all projects.
• Guidelines or rules for how projects are to be prioritized and approved. This
should include a ranking system that assigns scores to both individual projects
and entire school sites.
• An accounting for projects that may be completed in multiple steps over
several years as additional funding becomes available. Facility improvement
projects for each individual school should be sequenced and planned so that
each project builds on the other toward a final goal. This will prevent one
from requiring that another be demolished because of lack of foresight and
staged planning.
• A meaningful public involvement component. The current plan is to involve
the Citizen’s Oversight Committee that was originally assembled to oversee
bond spending (see Standard 2.4).
2. The district is also working to develop general, prototypical educational
specifications at all school levels. A model for educational specifications at the
elementary school level has already been completed, and the district is working
with an outside consultant to develop similar plans for middle and high schools.
Standard Implemented: Partially Implemented
January 2000 Rating: 4
September 2003 Rating: 2
March 2004 Self-Rating: 4
March 2004 Rating: 3
Implementation Scale:
10
2.4 Facility Planning – Existence of a District Facility Planning
Committee
Professional Standard
The district has created a Citizens Oversight Committee to ensure the appropriateness of
expenditures related to the recent passage of the district's local school bond measure. In
essence, this committee will function as an advisory/facility planning type of committee.
Progress on Implementing the Recommendations of the Recovery Plan
1. A Citizens Oversight Committee once more has been formed and has met several
times since the last review period. At this time the committee is primarily charged
with overseeing projects related to bond expenditures, however, there are plans for its
involvement in the master planning process. The district has not yet documented
goals and objectives for the Citizens Oversight Committee, and should do so. It is
important for the committee to be well informed of the scope of its responsibilities.
2. The Citizens Oversight Committee is currently made up of school board members and
their appointed representatives. In the future, the district should solicit a broad
representation of staff and community members to serve on this committee. It should
include representatives from various regions within the district, as well as a cross-
section of ethnic and economic backgrounds, including parents of students at different
grade levels.
3. The Citizens Oversight Committee members are currently chosen by the school
board. In the future, committee representatives should be recommended by the
Assistant Superintendent of Facilities Management and Planning and/or the Director
of Facilities and selected by the State Administrator/Superintendent.
4. The Assistant Superintendent of Facilities Management and Planning is currently
coordinating committee activities. This responsibility could eventually be passed on
to the Director of Facilities if the district decides this would be helpful.
Standard Implemented: Not Implemented
January 2000 Rating: 1
September 2003 Rating: 0
March 2004 Self-Rating: 3
March 2004 Rating: 4
Implementation Scale:
11
2.6 Facility Planning – Implementation of an Annual Capital Planning
Budget
Professional Standard
The district should develop and implement an annual capital planning budget.
Progress on Implementing the Recommendations of the Recovery Plan
1. The Facilities Department has established an annual capital budget to manage
available cash on-hand and future revenues. This allows the department to track
expenditures and ensure that they do not exceed available funds. The Facilities
Management and Planning Division has not yet developed and documented a policy
for prioritizing deferred maintenance and modernization needs on a districtwide basis.
It is expected that this will be included in the updated Facilities Master Plan (see
Standard 2.1).
2. The capital construction and renovation projects budget has not yet been coordinated
with the deferred maintenance projects budget. While some deferred maintenance
projects have been included in capital planning, the district has not yet developed a
systematic approach to integrating the two planning and funding processes.
Implementation of deferred maintenance projects should be consistent with the
Facilities Master Plan (see Standard 2.1).
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 2
March 2004 Self-Rating: 6
March 2004 Rating: 3
Implementation Scale:
12
2.17 Facility Planning – Priorities and Scheduling of Projects
This standard has been added since the 2000 report.
Professional Standard
The district has established and utilizes an organized methodology of prioritizing and
scheduling projects.
Progress on Implementing the Recommendations of the Recovery Plan
1. The district has not yet identified and documented a methodology for prioritizing and
scheduling projects. It is expected that this will be included in the updated Facilities
Master Plan. As recommended previously, this procedure should be written in a
manner that limits special interests from influencing funding decisions and requires
strict adherence by the school board (see Standard 2.1).
2. The district has continued to focus on projects that can provide state matching dollars
and leverage bond funds. Following the existing Facilities Master Plan, last updated
in 2001, the Facilities Department prepared a list of 18 modernization projects with
the eligibility to generate $17.4 million in state funding.
3. The Facilities Department prioritized and modified existing board-approved projects
to a list of 15, which the State Administrator has approved for initiation. These
include renovation and demolition projects. The district should continue to pay
attention to buildings that need minor maintenance because they can become
increasingly costly and problematic in the future.
Standard Implemented: Partially Implemented
September 2003 Rating: 1
March 2004 Self-Rating: 5
March 2004 Rating: 3
Implementation Scale:
13
2.18 Facility Planning – Equity of Distribution of Facility Funding
This standard has been added since the 2000 report.
Professional Standard
The district should distribute facility funding in an equitable manner to all communities
served and to all school levels.
Progress on Implementing the Recommendations of the Recovery Plan
1. The district has not yet documented a procedure for prioritizing and distributing
facility funding. It is still working from the 2001 version of the Facilities Master Plan
and a list of board-approved projects. To ensure equity, the district still needs a
documented policy on how funding distribution decisions will be made. It is expected
that this will be included in the updated Facilities Master Plan (see Standard 2.1).
2. The district is working to develop general, prototypical educational specifications at
all school levels. A model for educational specifications at the elementary school
level has already been completed, and the district is working with an outside
consultant to develop similar plans for middle and high schools. Prototypical
educational specifications will ensure equity across school sites.
3. The district has continued to focus on projects that can provide state matching dollars
and leverage bond funds. Following the existing Facilities Master Plan, last updated
in 2001, the Facilities Department prepared a list of 18 modernization projects with
the eligibility to generate $17.4 million in state funding.
Standard Implemented: Partially Implemented
September 2003 Rating: 1
March 2004 Self-Rating: 5
March 2004 Rating: 3
Implementation Scale:
14
3.10 Facilities Improvement and Modernization – Plan for Maintenance
and Modernization Exists
Professional Standard
The district maintains a plan for the maintenance and modernization of its facilities [EC
17366].
Progress on Implementing the Recommendations of the Recovery Plan
1. The district has prepared a Deferred Maintenance Plan that is valid through fiscal
year 2005-06. All current deferred maintenance projects are referenced in the existing
Facilities Master Plan (2001). The district is currently in the process of updating the
Facilities Master Plan. As recommended, the Facilities Master Plan should identify,
prioritize, and coordinate all modernization projects, deferred maintenance projects,
and all other projects (see Standard 2.1). The district also should ensure that deferred
maintenance funds are used properly and not redirected to inappropriate applications.
2. The Facilities Department has developed districtwide design standards to guide
construction projects. Representatives from the department of buildings and grounds
were involved in modifying these standards to ensure that ongoing facility
maintenance is a consideration in all construction and modernization plans.
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 1
March 2004 Self-Rating: 4
March 2004 Rating: 3
Implementation Scale:
15
3.12 Facilities Improvement and Modernization – Deferred
Maintenance Projects are Actively Managed
Professional Standard
The district actively manages the deferred maintenance projects. The district should
review the five-year Deferred Maintenance Plan annually to remove any completed
projects and include any newly eligible projects. The district should also verify that the
expenses performed during the year were included in the state-approved five-year
Deferred Maintenance Plan.
Progress on Implementing the Recommendations of the Recovery Plan
1. The Director of Facilities and the Director of Buildings and Grounds have discussed
the status of current deferred maintenance planning, but the division has not yet
established a clear system for managing and funding deferred maintenance projects.
This system should include a procedure for clearly identifying major maintenance
items and including them in the project prioritization process.
2. The current Deferred Maintenance Plan is valid through fiscal year 2005-06. The plan
is reviewed annually. Currently, the Director of Buildings and Grounds is updating
the plan for the current year and projecting through fiscal year 2007-08.
3. The Director of Buildings and Grounds is responsible for annually updating the
Deferred Maintenance Plan.
4. The Director of Buildings and Grounds has not yet presented the updated report to the
Facilities Committee for review and approval. This should be accomplished annually.
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 1
March 2004 Self-Rating: 5
March 2004 Rating: 5
Implementation Scale:
16
6.3 Special Education Facilities – Adequacy for Instructional Program
Needs
Professional Standard
The district provides facilities for its special education programs that provide appropriate
learning environments in relation to educational program needs.
Progress on Implementing the Recommendations of the Recovery Plan
1. A review of district plans and interviews with the staff including, the Director of
Special Education and the Director of Facilities, indicate that in general, the district’s
facilities adequately meet the needs of its special education programs. This is
especially true at newer and modernized facilities. At some older sites, special
education classrooms are still removed from mainstream facilities. The district is
working to update and improve these conditions.
2. The Director of Special Education has been actively involved in Site Utilization
Committee meetings. The director and representatives from the department should
also be included in the updating of the Facilities Master Plan to ensure that it
addresses the needs of special education students.
3. The district is working to address the needs of special education students who have
not traditionally been accommodated within district facilities. It is investigating the
possibility of using as special education sites (including an autism center) the
campuses of schools projected to close in fall 2004. It is also negotiating with the
county office of education regarding a possible restructuring of some sites. These
actions would decrease the district’s costly dependence on outsourcing students with
serious disabilities.
4. The district’s educational specifications show that new construction and
modernization projects integrate spaces for meeting the needs of special education
students. The district should conduct a review of post-occupancy data to ensure that
the number and size of those spaces is appropriate.
Standard Implemented: Partially Implemented
January 2000 Rating: 2
September 2003 Rating: 3
March 2004 Self-Rating: 5
March 2004 Rating: 4
Implementation Scale:
17
8.3 Facilities Maintenance and Custodial – Tracking Energy
Consumption
This standard has been added since the 2000 report.
Professional Standard
Create and maintain a system to track utility costs and consumption, and to report on the
success of the district’s energy program.
Progress on Implementing the Recommendations of the Recovery Plan
1. At the time of the last review in August 2003, the district had no means of tracking
utility usage or attributing usage and costs to specific sites. Since then, the district has
made great strides towards implementing such a system. Actions taken as of February
2004 include:
• Producing a report that summarized facility energy use and costs for 127 sites.
• Researching and evaluating energy management software options that can
help track and monitor utility usage. The district should select and implement
software that can track usage at the site level and should ensure that adequate
support is allocated for successful implementation, including appropriate
staffing and funding levels.
• Preparing to pilot an energy education curriculum at one elementary school
site. The district should work towards districtwide implementation.
• Preparing to conduct comprehensive energy audits at 10 school sites.
• Utilizing grant and city/county funding options to initiate an energy program.
2. The district has identified an energy management software package that seems to
meet its needs, but there are several concerns that need to be addressed before a final
decision is made, including how utility information will be uploaded/entered into the
software. The Director of Buildings and Grounds is researching several options for
effective implementation.
3. The district would benefit from developing procedures to regularly review usage
trends, as well as policies for follow-up actions. These could include incentives for
sites that show effective or improving practices, and enhanced education for sites that
show need for improvement.
Standard Implemented: Partially Implemented
September 2003 Rating: 0
March 2004 Self-Rating: 3
March 2004 Rating: 2
Implementation Scale:
18
8.5 Facilities Maintenance and Custodial – Adequate Maintenance
Records and Inventories
Professional Standard
Adequate maintenance records and reports are kept, including a complete inventory of
supplies, materials, tools, and equipment. All employees required to perform maintenance
on school sites should be provided with adequate supplies, equipment, and training to
perform maintenance tasks in a timely and professional manner. Included in the training
is how to inventory supplies and equipment and when to order or replenish them.
Progress on Implementing the Recommendations of the Recovery Plan
1. Safety training is overseen by the Risk Management Department, now located within
the Business Division. It appears that many maintenance staff members have been
trained in common safety practices. The Custodial Services Department is still
working to implement a training curriculum, and school site custodians report that
they have not received recent training (see Standard 1.24).
2. The Buildings and Grounds Department has moved to a drop-shipment purchasing
system, where supplies are purchased when needed and charged to each project. As a
result, few supplies are stored in the district warehouse, and no comprehensive
inventory is necessary. Similarly, no central inventory of custodial supplies exists, as
these supplies are now purchased at the site level.
3. The State Administrator recently approved a $200,000 expenditure to purchase new
maintenance equipment for the district. The Buildings and Grounds Department has
completed maintenance for: district vehicles (including life expectancy), district
elevators, department equipment, and employee tools. An inventory of district
equipment by site is in progress. The Director of Buildings and Grounds should
ensure that these inventories are updated annually.
4. The State Administrator recently approved a $300,000 expenditure to purchase new
custodial equipment for the district. The Custodial Services Department does not
currently have an accurate inventory of what equipment the district has or where it is
located. The department is preparing to implement a check-off form for all
supervising custodians accepting promotions or taking transfers. This would create an
inventory of all supplies and equipment in the custodial closet when a supervising
custodian enters a school site, to be compared with what exists when that custodian
prepares to leave. This check-off form should be implemented immediately at all
school sites, even if there is no planned promotion or transfer. This would give the
district a baseline inventory of its custodial equipment.
Standard Implemented: Partially Implemented
January 2000 Rating: 2
September 2003 Rating: 1
19
March 2004 Self-Rating: 3
March 2004 Rating: 3
Implementation Scale:
20
8.6a Facilities Maintenance and Custodial – Procedures for Evaluation
of Custodial Staff
Professional Standard
Procedures are in place for evaluating the work quality of custodial staff. The quality of
the work performed by the custodial staff should be evaluated regularly using a board-
adopted procedure that delineates the areas of evaluation and the types of work to be
evaluated.
Progress on Implementing the Recommendations of the Recovery Plan
1. The Custodial Services Department has been occupied with layoffs and reassignments
for most of the fall semester, so no significant progress has been made on this
standard. The existing evaluation process is antiquated, is not tied to performance
standards, and is not performed regularly. The district should implement an
evaluation system that includes clear standards and rubrics for assessing the
performance of custodial staff. Evaluation forms should be revised so that they relate
to the district’s custodial cleaning standards, and should be reviewed with the staff
before the evaluation period so that expectations are understood. To support results-
based decision-making, principals should be trained in custodial evaluation criteria.
Evaluations should be conducted annually, reviewed by the Field Supervisor and
principal, and kept on file either within the Custodial Services Department or in the
personnel office.
2. Custodial cleaning standards and custodial policies and procedures handbooks have
been distributed, but are not being utilized. Until they are tied to evaluations, it is
likely that this will continue to be the case. Field supervisors’ observation rounds
should include a check to ensure that appropriate standards and procedures are being
followed. When they are not, disciplinary action should be taken.
3. Promotions are still based on seniority. The district should work with AFSCME, the
custodial collective bargaining group, to negotiate promotion criteria that include a
merit-based component. This will also involve consideration of changes resulting
from the soon-to-be-implemented decision-making process, which is site based.
Attendance and performance should be factors in promotion decisions.
4. The Custodial Services Department has not had the opportunity or resources to
implement a comprehensive training program, but plans are underway to do
accomplish this. As recommended previously, custodial training sessions should
provide supervisory personnel with the appropriate knowledge, skills, and abilities to
evaluate employees. Custodial field supervisors should mentor, advise, and monitor
the evaluation process at each site (see Standard 1.24).
5. The district has not yet formed a custodial advisory committee, but it should still
consider forming such a group. The committee would be composed of principals,
field supervisors, head custodians, and union representatives to provide advice on
matters related to the provision of custodial services. The Custodial Advisory
21
Committee would make recommendations on an effective evaluation system that is
based on firsthand knowledge of the work being performed.
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 1
March 2004 Self-Rating: 3
March 2004 Rating: 1
Implementation Scale:
22
8.6b Facilities Maintenance and Custodial – Procedures for Evaluation
of Maintenance Staff
Professional Standard
Procedures are in place for evaluating the work quality of maintenance staff. The quality
of the work performed by the maintenance staff should be evaluated regularly using a
board-adopted procedure that delineates the areas of evaluation and the types of work to
be evaluated.
Progress on Implementing the Recommendations of the Recovery Plan
1. The Director of Buildings and Grounds and his managers are working to develop
maintenance standards. In the future, these standards will correspond to a rubric and
link to a revised evaluation form. Currently, the department staff is evaluated using
the existing district form. The department should continue to develop and implement
performance standards, and ensure that they are well communicated to the
maintenance staff throughout the district. As recommended previously, these
standards should be used to create evaluation forms that are appropriate for the trades
and professions within the Buildings and Grounds Department. Evaluation forms
should be reviewed with the staff before the evaluation period so that expectations are
understood. The standards-based evaluation forms should, at a minimum, include the
following elements;
• Evaluation of general work habits
• Evaluation of specific trade skills
• Recommendations for specific needed improvements
• A proposed improvement plan agreed to by the evaluator and the staff member
• Staff comments
2. In November 2003, buildings and grounds managers were trained to evaluate the
employees they supervise. The department director also sent the managers a
memorandum outlining criteria to consider when evaluating, including attendance,
interpersonal skills, work ethic, and disciplinary records.
3. The Buildings and Grounds Department is working to comply with the evaluation
schedule established by the Human Resources Division. Evaluations are conducted
annually, reviewed by the appropriate supervisor, and kept on file either within the
department or in the personnel office.
Standard Implemented: Partially Implemented
January 2000 Rating: 2
September 2003 Rating: 0
March 2004 Self-Rating: 4
March 2004 Rating: 3
Implementation Scale:
23
8.8 Facilities Maintenance and Custodial – Implementation of a
Preventative Maintenance Plan
Professional Standard
The district has an effective preventive maintenance program. The district should have a
written preventive maintenance program that is scheduled and followed by the
maintenance staff. This program should include verification of the completion of work by
the supervisor of the maintenance staff.
Progress on Implementing the Recommendations of the Recovery Plan
1. This district has not yet developed or documented a written preventative maintenance
plan that includes the number and types of equipment. As recommended previously,
the comprehensive plan should include the tasks to be completed, the responsible
staff position, and the schedule for completion. The plan also should include
procedures for tracking repairs to specific pieces of equipment.
2. The district maintains a CMMS (Computerized Maintenance Management System)
with relatively minimal capabilities. As recommended previously, the district should
consider allocating the funding to acquire a more sophisticated system, with the
capacity to track work orders that tie into inventory and payroll. This will help
identify areas in need of preventative maintenance, as well as areas of priorities. The
CMMS should automatically generate preventative maintenance work orders based
on a preventative maintenance schedule. These should become priority work orders if
the district is to move toward a more proactive maintenance system. A more
developed system also would allow principals to track the status, time estimates, parts
and materials linked to a particular work order. This is an increasingly important need
as the district moves to results-based site budgeting and oversight. Without such a
system, the district will be unable to accurately determine the cost of jobs, eliminating
the possibility of charging sites directly for the labor and materials they receive.
3. The Director of Buildings and Grounds has not yet had the opportunity to prepare an
annual report that projects anticipated equipment repairs and replacements five to 10
years into the future. The report should identify projected costs and other necessary
resources with a clear plan for making the identified improvements.
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 1
March 2004 Self-Rating: 3
March 2004 Rating: 1
Implementation Scale:
24
8.9/8.10 Facilities Maintenance and Custodial – All Buildings, Grounds
and Bathrooms are Maintained
This standard has been reworded/combined since 2000.
Professional Standard
Toilet facilities are adequate and maintained. All buildings and grounds are maintained
[CCR Title 5 Section 631].
Progress on Implementing the Recommendations of the Recovery Plan
1. The department of buildings and grounds is working to develop maintenance
standards. Once established, it should ensure that they are well communicated to and
implemented by maintenance staff throughout the district (see Standard 8.6b).
2. The Custodial Services Department recently has implemented a policy of conducting
bathroom inspections three times each day. Site custodians are expected to complete
an inspection check-off form for each student restroom, obtain the principal’s
signature, and fax the form to the department at the end of each week. The Director of
Custodial Services then reviews the forms and files disciplinary letters for site
supervisors who do not submit them as required. The department hopes that over
time, this process will become systematic and require less oversight. This policy
demands a significant amount of time from the director and custodians. However,
feedback from custodians and on-site observations indicate that this system is merely
a bureaucratic exercise that does not affect restroom cleanliness. The review team
observed unclean and unsanitary restroom conditions at several campuses, and
custodians reported that the check-off forms have not caused them to appreciably
change their routines. The district should reconsider this procedure and evaluate
whether it is having enough of a measurable affect on restroom facilities to justify its
continuation.
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 1
March 2004 Self-Rating: 4
March 2004 Rating: 2
Implementation Scale:
25
8.11 Facilities Maintenance and Custodial – Implementation of a
Planned Program Maintenance System
Professional Standard
The district has implemented a Planned Program Maintenance System. The district
should have a written Planned Program Maintenance System that includes an inventory
of all facilities and equipment that will require maintenance and replacement. This
program should include purchase prices, anticipated life expectancies, anticipated
replacement time lines, and budgetary resources necessary to maintain the facilities.
Progress on Implementing the Recommendations of the Recovery Plan
1. The buildings and grounds staff is currently in the process of identifying and tagging
all items of value within the district. The identification includes the serial number and
type of equipment, but does not demarcate age and repair history. That research and
documentation will need to take place once the initial identification is complete.
2. This list is being entered into a separate database because the current CMMS does not
have the capacity to maintain this type of information. The district also should
account for the projected life expectancy and replacement costs of the equipment. The
district should consider allocating the funding to acquire a more sophisticated CMMS
system that can integrate inventory with life expectancies, costs and replacement
schedules (see Standard 8.8).
3. The Director of Buildings and Grounds does not yet prepare an annual report that
projects needed equipment repairs and replacements for 10 years. This report should
identify projected costs and necessary budget resources.
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 1
March 2004 Self-Rating: 3
March 2004 Rating: 1
Implementation Scale
26
8.12 Facilities Maintenance and Custodial – Assignment of Work
Orders
This standard has been added since the 2000 report.
Professional Standard
The district has a documented process for assigning routine work orders on a priority
basis.
Progress on Implementing the Recommendations of the Recovery Plan
1. The Director of Buildings and Grounds has documented a prioritization policy for
handling work orders. Requests that relate to the health and safety of a site are given
highest priority. The Director of Buildings and Grounds has prepared an updated
handbook that will soon be shared with school sites so they understand how their
requests are handled.
2. The company that was contracted to provide the computerized work-request system
conducted districtwide training on the system several years ago when it was first
introduced to schools. The district’s work control department now conducts
individual training sessions for new staff as needed.
3. The district should consider allocating the funding to acquire a more sophisticated
CMMS that will provide district staff and principals the capability to check the status
on their work requests (see Standard 8.8).
4. The district should enhance the current documented work order policy to provide the
staff with detailed examples of the type of orders that fall into each level of priority.
This will standardize the procedures and facilitate the training of new work control
specialists.
5. The district should ensure that the updated Handbook for the Buildings and Grounds
Department is distributed to principals and administrative assistants. The director
and/or coordinator of buildings and grounds should call and/or visit school sites to
answer any questions principals and administrative staff may have about the process.
Standard Implemented: Partially Implemented
September 2003 Rating: 1
March 2004 Self-Rating: 4
March 2004 Rating: 4
Implementation Scale:
27
9.6 Instructional Program Issues – Plan to Maintain Equality/Equity of
District Facilities
Professional Standard
The district has developed and maintains a plan to ensure equality and equity of its
facilities throughout the district [EC 35293].
Progress on Implementing the Recommendations of the Recovery Plan
1. The district is in the process of contracting with an outside firm to update the
Facilities Master Plan (see Standard 2.1). This will include a districtwide assessment
of modernization needs. In the meantime, the district is utilizing the 2001 version of
the master plan and the list of board-approved projects. The district should be
commended for its recent efforts to focus on modernization projects that maximize
the potential for state matching funds (see Standard 2.17).
2. As noted elsewhere in this report, the district does not currently have a documented
policy to guide decisions regarding prioritization of facilities projects. This will be a
vital part of the updated Facilities Master Plan. Until a system is developed,
documented and implemented, there will be no way to ensure that facilities decisions
are made equitably. The Facilities Master Plan should include a ranking system that
prioritizes projects, and decisions on project funding should be based on need, not
location or political interests.
3. In the past, the school board used inconsistent criteria for prioritizing and approving
projects, which led to inequitable distribution of resources. To ensure equity and
unbiased decision-making, the district should consider revising board policy to
stipulate how facilities projects should be prioritized. The decision-making process
should be based on need, and guided by the ranking system to be outlined in the
Facilities Master Plan.
4. Facilities funding will become an issue for the district as the needs exceed available
bond and modernization funds. The district should research all potential funding
sources, including the possibility of an additional bond in the future.
5. The Citizens Oversight Committee has been re-established, and it will be charged
with reviewing the Facilities Master Plan and assisting with prioritizing future
projects to ensure equity and equality throughout the district. This committee
currently consists of school board members and their representatives. Eventually the
Assistant Superintendent and/or Director of Facilities should select community
members to serve (see Standard 2.4).
Standard Implemented: Partially Implemented
January 2000 Rating: 1
September 2003 Rating: 2
March 2004 Self-Rating: 5
28
March 2004 Rating: 3
Implementation Scale:
29
10.2 Community Use of Facilities – Compliance with Civic Center Act
for Community Use
Professional Standard
Education Code Section 38130 establishes terms and conditions of school facility use by
community organizations, in the process requiring establishment of both “direct cost” and
“fair market” rental rates, specifying what groups have which priorities and fee
schedules.
Progress on Implementing the Recommendations of the Recovery Plan
1. The Director of Custodial Services is now charged with overseeing civic center, or
community use, of district facilities. Rental rates have not been adjusted for many
years, and the district is just beginning to review the fee schedule. As recommended
in 2000, the district should ensure that a survey is conducted of similar facilities
available for rent in the Oakland area in order to establish current fair-market rental
rates. The district also should research the current direct costs to the district that are
associated with the use of facilities. If deemed appropriate, revised and approved
charges should be published.
2. The district has several joint facilities use agreements pertaining to several individual
properties and partners. The policies established in these agreements are often not
enforced and are in need of updating. The district should examine these policies,
modify them as necessary, and implement procedures to ensure that they are
enforced. The district may want to consider forming a Joint Powers Authority (JPA)
with the city of Oakland and other partners to oversee joint use projects.
3. As recommended in 2000, the district should establish a biannual schedule for review
of civic center policies, procedures and forms, including fees and charges. The district
should consider assigning this task to an individual other than the Director of
Custodial Services, given his many other responsibilities.
Standard Implemented: Partially Implemented
January 2000 Rating: 5
September 2003 Rating: 3
March 2004 Self-Rating: 6
March 2004 Rating: 3
Implementation Scale:
30
11.3 Communication – Communication of District Standards and Plans
Professional Standard
The district should provide clear and comprehensive communication to the staff of its
standards and plans.
Progress on Implementing the Recommendations of the Recovery Plan
1. Custodial cleaning standards have not yet been linked to annual evaluations.
Maintenance standards are still in the development stage, although a handbook
outlining buildings and grounds procedures has been updated. As recommended
previously, the district should finalize and implement standards for the custodial and
maintenance staff and provide feedback on job performance through annual
evaluations. Evaluation forms should be reviewed with the staff before the evaluation
period so that expectations are understood (see Standards 8.6a and 8.6b).
2. The custodial and maintenance staff has not yet been adequately trained to implement
standards. Supervisors should conduct regular check-in sessions with staff members
to ensure they understand what is expected of them and are implementing standards
as required.
3. The State Administrator has initiated a monthly districtwide staff newsletter entitled
Staff Connections that includes some facilities-related issues. The Facilities Division
also has a quarterly internal newsletter. The division and/or individual departments
should consider distributing more frequent correspondence to alert staff as to plans
and developments. This could also provide an opportunity to build morale by
highlighting division staff and departments for noteworthy accomplishments.
Standard Implemented: Partially Implemented
January 2000 Rating: 0
September 2003 Rating: 2
March 2004 Self-Rating: 4
March 2004 Rating: 3
Implementation Scale:
31