LAFCO
Amador Municipal Service Review Progress Report Feb 18, 08
Read the report at Local Agency Formation Commissions ↗
Amador Municipal Service Review Progress Report
By Burr Consulting
Feb. 18, 2008
Summary
All but one of the local agencies are cooperating with the MSR project. The majority of the service
providers have not been as quick to respond to LAFCO and consultant requests as was originally
anticipated. The MSR was originally expected to be presented to LAFCO in May 2008. At this
time, the MSR is not expected to be adopted by LAFCO until its June or July 2008 meeting.
MSR Steps and Timing
1. Outreach
• Presentation delivered and outreach materials were disseminated Nov. 5, 2007
2. Initial Request for Information (RFI)
• Questionnaire was mailed Nov. 6, 2007
• Requested liaison, service configuration, agency documents
• Agency responses were requested within 2 weeks
• Median agency response time was 5.5 weeks, arriving just before the holidays
3. Interview
• Consultant reviewed documents provided in response to Step 2 for information of
interest, and interviewed for remaining questions
• Cities, fire districts and AWA were interviewed Jan. 16-17, 2008
• Other districts and providers were interviewed Jan. 28-30
4. Agencies Respond to Requests Made at Interviews
• Cities and AWA responses have been slower than anticipated. LAFCO letters on
Feb. 14 requested response by Feb. 22.
• Other districts have mostly responded within 2 weeks, but some have not provided
information (as of 3 weeks post-interview)
• Some responses have been incomplete
• Substantial water and wastewater information has not yet been provided
5. Agency Profiles Prepared
• Fire, police, streets, drainage, parks, cemetery services reviewed
• Profiles for fire districts were prepared (except Sutter Creek FPD)
• Portions of profiles for cities and the County have been prepared
• Consultant target date for completion of profiles is March 10
6. Agency Review of Profiles
• Agencies will be asked to review the profiles within a 2-week period
• Consultant target date for completion of this step is March 24
7. Administrative Draft MSR
• The administrative draft MSR is due to LAFCO within 40 days of Step 6 (May 3)
• Consultant will attempt to complete this step more quickly
8. Public Review Draft MSR
• The public review draft MSR is due to be released within 14 days of LAFCO review
and comment on the Administrative Draft MSR (by May 24)
• The public review comment period will be 3 weeks
9. Draft Final MSR
• The draft final MSR is due to be released within 10 days of the close of the public
review comment period (by June 25)
10. LAFCO Presentation
• Consultant is expected to present findings to LAFCO at the next LAFCO
presentation (June 19 or July 17)
• LAFCO may adopt the MSR resolution at that meeting
11. Final MSR
• The final MSR will be released within 10 days of LAFCO adoption
MSR Status by Service Provider
Interview
RFI Part 1 RFI Part I Requests
Local Agency Sent Received Interview Received Status Note
Backbone Service Providers - Major
Amador 11/5/2007 11/21/2007 1/16/2008 Some pending interview requests
Ione 11/5/2007 11/21/2007 1/16/2008 Some pending interview requests
Jackson 11/5/2007 12/3/2007 1/16/2008 No pending interview requests
Plymouth 11/5/2007 12/30/2007 1/17/2008 Some pending interview requests
Sutter Creek 11/5/2007 12/14/2007 1/17/2008 Mostly pending interview requests
Amador Water Agency 11/5/2007 11/14/2007 1/17/2008 No pending interview requests
Amador Fire Protection District 11/5/2007 11/26/2007 1/17/2008 Yes profile drafted
Jackson Valley Fire Protection 11/5/2007 1/20/2008 1 1/16/2008 Need financials pending 11/2007 document request
Lockwood Fire Protection 11/5/2007 1/20/2008 1/17/2008 Yes profile drafted
Sutter Creek Fire Protection 11/5/2007 No No No agency no-show at interview 1/2007
CAL FIRE 1/10/2008 1/16/2008 1/16/2008 Yes profile drafted
Backbone Service Providers - Minor
Drytown County Water 11/5/2007 12/14/2007 1/29/2008 No pending interview requests
Fiddletown Community Services 11/5/2007 11/13/2007 1/29/2008 No pending interview requests
Jackson Valley Irrigation 11/5/2007 11/19/2007 1/28/2008 Mostly pending interview requests
Kirkwood Meadows PUD 11/5/2007 1/8/2008 2/12/2008 No pending interview requests
Mule Creek State Prison 1/9/2008 1/28/2008 1/28/2008 No pending interview requests
Pine Grove Community Services 11/5/2007 11/28/2007 1/29/2008 Mostly pending interview requests
Rabb Park Community Services 11/5/2007 11/16/2007 1/30/2008 En Route pending interview requests
River Pines Public Utility 11/5/2007 1/7/2008 1/28/2008 No pending interview requests
Volcano Community Services 11/5/2007 12/18/2007 1/30/2008 Mostly pending interview requests
Non-Backbone Service Providers
Amador Resource Conservation 12/7/2007 1/29/2008 1 1/29/2008 No pending 12/2007 document request
Ione Memorial District 11/5/2007 12/19/2007 1/29/2008 Yes profile draft in progress
Pine Acres Community Services 11/5/2007 11/24/2007 1/30/2008 Yes profile draft in progress
Ranch House Estates Community Services 12/7/2007 1/4/2008 1/30/2008 Yes profile draft in progress
Ridgewood Acres Community Services 12/7/2007 1/28/2008 1/28/2008 Yes profile draft in progress
Sunset Heights Community Services 11/5/2007 12/14/2007 1 1/29/2008 Need financials pending 11/2007 document request
Township Cemetery No. 2 11/5/2007 12/24/2007 1/28/2008 Yes profile draft in progress
County of Amador 1/24/2008 1/29/2008 1/29/2008 No profile draft in progress
County Service Areas 11/5/2007 11/16/2007 2/15/2008 Pending pending interview requests
U.S. Forest Service 1/10/2008 1/20/2008 NA Yes profile drafted
Note: 1) Partial response with missing documents to RFI Part I to date.