LAFCO
City Of El Centro Service Area Plan
Read the report at Local Agency Formation Commissions ↗
FebruarY 2016
serViCe area
PLan (saP)
Cit Y oF
eL Centro
5620 Friars road
san d iego, Ca 92110
t: 619.291.0707
riCkengineering. Com
TABLE OF CONTENTS
SECTION PAGE
SECTION 1 – EXECUTIVE SUMMARY..................................................................................... 1
1.1 Introduction ...................................................................................................................... 1
1.2 Public Service and Facilities ............................................................................................ 1
1.3 Financing Summary ....................................................................................................... 10
SECTION 2 – INTRODUCTION ................................................................................................ 13
2.1 Background on the City of El Centro ............................................................................ 13
2.2 Purpose of the Service Area Plan................................................................................... 13
2.3 Organization of the Service Area Plan........................................................................... 14
SECTION 3 – GROWTH AND PHASING PROJECTIONS .......................................................17
3.1 Existing Land Use .......................................................................................................... 17
3.2 Planned Land Use .......................................................................................................... 17
3.3 Projected Population Increase ........................................................................................ 20
3.4 Theoretical Buildout Projections ................................................................................... 21
SECTION 4 – PUBLIC FACILITIES AND SERVICES..............................................................29
4.1 General Governement Facilities .................................................................................... 31
4.2 Drainage Facilities ......................................................................................................... 37
4.3 Fire Facilities ................................................................................................................. 41
4.4 Law Enforcement Facilities ........................................................................................... 51
4.5 Library Facilities ............................................................................................................ 59
4.6 Parks and Recreation Facilities ...................................................................................... 65
4.7 Transportation Facilities ................................................................................................ 75
4.8 Wastewater Facilities ..................................................................................................... 83
4.9 Water Facilities .............................................................................................................. 87
4.10 School Facilities ............................................................................................................. 91
SECTION 5 – FINANCING ......................................................................................................... 97
5.1 Introduction .................................................................................................................... 97
5.2 Existing Revenue Sources.............................................................................................. 97
5.3 Future Revenue Sources .............................................................................................. 100
5.4 Existing Financing Mechanisms .................................................................................. 101
5.5 Future Financing Mechanisms ..................................................................................... 102
5.6 Facility Financing ........................................................................................................ 103
El Centro Service Area Plan Table of Contents
February 2016 Page i
LIST OF TABLES
TABLES PAGE
3-1 Projected Population Increase ..........................................................................................21
3-2 Theoretical Buildout Population by Development Tier ...................................................22
4.1-1 General Government Facilities ........................................................................................33
4.3-1 Fire Personnel ..................................................................................................................42
4.3-2 Fire Equipment .................................................................................................................42
4.3-3 Average Response Times per Station ..............................................................................43
4.4-1 Police Personnel (Sworn) .................................................................................................52
4.4-2 Police Personnel (Non-sworn) .........................................................................................53
4.4-3 Police Vehicles .................................................................................................................53
4.4-4 Police Demand .................................................................................................................55
4.6-1 List of Park Facilities and Acreage ..................................................................................66
4.6-2 List of Recreation & Community Center Facilities and Acreage ....................................66
4.6-3 List of School Recreation Facilities and Acreage ............................................................67
4.6-4 Park and Recreation Facility Demand..............................................................................68
4.6-5 Park and Recreation Facilities Planned ............................................................................69
4.7-1 Circulation Performance Criteria (LOS) ..........................................................................76
El Centro Service Area Plan Table of Contents
February 2016 Page ii
LIST OF FIGURES
FIGURES FOLLOWS PAGE
3-1 Sphere of Influence Map ....................................................................................................23
3-2 Land Use Map ....................................................................................................................25
3-3 Urban Development Tiers Map .........................................................................................27
4.3-1 Fire Facilities Map .............................................................................................................49
4.6-1 Park and Recreational Facilities Map ................................................................................73
El Centro Service Area Plan Table of Contents
February 2016 Page iii
LIST OF ACRONYMS AND ABBREVIATIONS
ADD average day demand (water)
ADT average daily traffic
CEQA California Environmental Quality Act
CFD Community Facilities District
City City of El Centro
CIP Capital Improvement Program
County County of Imperial
CSD Community Services Department
CUHSD Central Union High School District
DPR Department of Parks and Recreation
ECESD El Centro Elementary School District
ECFD El Centro Fire Department
ECPD El Centro Police Department
EIFD Enhanced Infrastructure Finance Districts
FY fiscal year
GHG greenhouse gas emissions
gpd gallons per day
gpm gallons per minute
HCD State Department of Housing & Community Development
HCDA Housing and Community Development Act of 1974
HCM Highway Capacity Manual
I-8 Interstate 8
ICAPCD Imperial County Air Pollution Control District
ICFD Imperial County Fire Department
ICOE Imperial County Office of Education
ICTC Imperial County Transportation Commission
IID Imperial Irrigation District
LAFCo Local Agency Formation Commission
LCFF Local Control Funding Formula
LLMD Landscape and Lighting Maintenance Districts
LOS level of service
MDD maximum daily demand
mg million gallons
mgd million gallons per day
MPD Master Plan of Drainage
MUESD McCabe Union Elementary School District
NAAQS national ambient air quality standards
NAT No action taken
NFPA National Fire Protection Association
Non-res. non-residential
NPDES National Pollution Discharge Elimination System
PAX Police Auxiliary
PLF Public Library Fund
RTP Regional Transportation Plan
El Centro Service Area Plan Table of Contents
February 2016 Page iv
RWQCB Regional Water Quality Control Board (Colorado River Basin)
SAP Service Area Plan
SB Senate Bill
SSAB Salton Sea Air Basin
SCAG Southern California Association of Governments
SCS Sustainable Communities Strategy
STIP state transportation improvement program
sf square feet
SOI sphere of influence
SWPPP stormwater pollution prevention plan
TDA Transportation Development Act
TDS total dissolved solids
TMDL total maximum daily load
TOT transient occupancy tax
UDP Urban Development Program
USDA United States Department of Agriculture
VLF vehicle license fee
WDF water demand factors
WTP Water Treatment Plant
WWTP Wastewater Treatment Plant
El Centro Service Area Plan Table of Contents
February 2016 Page v
This Page Intentionally Left Blank.
El Centro Service Area Plan Table of Contents
February 2016 Page vi
SECTION 1 - EXECUTIVE SUMMARY
1.1 INTRODUCTION
The City of El Centro (City) is home to approximately 45,000 residents and serves as the center
of commercial, general government, recreational, and cultural activities for much of the
surrounding Imperial Valley region. Undeveloped land within the City’s boundaries and the
City’s sphere of influence (SOI) boundaries is currently being developed for residential,
commercial, public, and industrial uses. The City of El Centro General Plan (General Plan)
guides the City’s growth.
This Service Area Plan (SAP) outlines the City’s existing public services and facilities, estimates
the current and future anticipated demand for such facilities and services, and describes how
necessary facilities and services will or may be developed and extended to meet demands. The
SAP is intended to demonstrate the City’s intent and ability to provide adequate services to the
SOI boundaries at the time of annexation. An approximately 10-year planning horizon is used to
forecast growth, and the estimated demands and provision to meet demands are based on
population projections for 2025.
The following is a brief summary of the existing resources, demands, financing mechanisms, and
mitigation measures related to the nine public services and facilities areas examined in this SAP.
It should be noted that the following discussion is substantially abbreviated from that contained
in the rest of the document and is not meant to replace the comprehensive discussion provided in
Sections 2 through 5 of this SAP.
1.2 PUBLIC SERVICES & FACILITIES
General Government Facilities
The City’s general government facilities are comprised of approximately 26,800 square feet of
building area in a centralized location on Main Street that is easily accessible to many City
residents. The existing City general government facilities are in acceptable condition and
spacious enough to accommodate the scope and scale of general government services and future
needs. Increased growth, however, will present an increased demand on the City’s general
government facilities and personnel. As a result, the City will be presented with the need to hire
additional general government personnel and expand services. It is not likely that growth within
the SOI will require additional facilities in new locations, as the current central location will
remain accessible to new development throughout the SOI. In addition, improvements in
technology, amount of general government personnel, and other facility enhancements can be
used by the City to accommodate population growth. When needed, future demands will be met
by expanding existing structures. Should this not prove to be a feasible option, the City may
consider purchasing additional land within the immediate vicinity of the City Hall, especially
land within the adjacent Civic Center zone.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 1
Mitigation
• Comply with the performance standards for City general government facilities and
personnel.
• Continue to periodically review the general government facilities and personnel of the
City through the preparation of annual reports.
• Review the user fees and implement recommended increases to the fee structure.
Funding
• General Fund
• User Fees
• Development Impact Fees
Drainage Facilities
The City owns, operates, and maintains a system of drains that conveys storm water and urban
runoff. The system is managed by the wastewater division of the Department of Public Works,
and the City does not maintain a separate budget for drainage maintenance or improvements.
Drainage issues are reviewed on a project-by-project basis. As a general policy, the City
approves of the installation of retention basins on development projects. Several of the existing
storm drains have inadequate capacity to convey the runoff produced by a ten-year design storm
event. The Drainage Master Plan identified ten locations that require improvements at existing
deficient drainage facilities which includes extensions to the existing storm drains, the
installations of a parallel storm drain, and the replacement of existing undersized systems. These
facilities will need improvement to accommodate increased demand as the City’s population
grows.
Mitigation
• Continue implementation of the Master Plan of Drainage (MPD).
• Continue to require new roadways within the City boundaries and the City SOI
boundaries to meet City requirements for provision of gutter features and slopes to
properly convey storm flow.
• Continue to require that new development projects address potential drainage issues and
provide adequate facilities to convey storm flow.
• Require compliance with new Phase II Small Municipal Separate Storm Sewer System
(MS4) Permit program for stormwater quality.
Funding
• New facilities funded and installed by developers
• Wastewater Enterprise Fund
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 2
• General Fund
Fire Facilities
The City manages the El Centro Fire Department (ECFD), which provides fire response,
suppression, prevention, and investigation; emergency medical response and advanced life
support; community disaster preparedness; hazardous materials response and mitigation;
confined space rescue services; and water rescue services within the City boundaries as well as
to other jurisdictions pursuant to a mutual aid agreement. The ECFD has three fire stations; one
located in the center of the City, the other in the northwestern part, and the third near the
southeastern boundary. In all, the ECFD has 41 uniformed personnel, four non-uniformed
personnel, and various vehicles and pieces of equipment.
Increased development within the City boundaries and City SOI boundaries will continue to
place strain on the services, personnel, and equipment of the ECFD. As calls become more
numerous with the increased density of the City and as land is annexed into the ECFD service
area, the ECFD will experience an increase in emergency and non-emergency response times. As
development occurs, the City plans to develop a third and fourth ECFD fire station to house fire
and emergency response personnel, equipment, and vehicles.
Mitigation
• In conformance with General Plan Public Facilities Policy 5.2, continue the periodic
review of number of calls and response times to determine the adequacy of existing
service and any need for improvement or additional resources.
• Design and implement a year-long workload monitoring program to determine the
adequacy of the existing staffing standard of providing ten sworn and uniformed
personnel to be available to respond to calls at any given time throughout the day or
night.
• Review the existing mutual aid agreement that exists between the ECFD and the Imperial
County Fire Department (ICFD) as well as other jurisdictions in Imperial County and
California for the provision of emergency services.
• Pursue additional funds for additional personnel, equipment, and vehicles for the ECFD
as identified in the workload monitoring program.
• When the City determines the need, purchase land and construct Fire Station No. 4.
• Review existing development impact fees for ECFD services, identify necessary
improvements to the current fee structure, and implement a revised fee structure.
• Periodically review the mutual aid agreement with the ICFD for service within the SOI to
maintain adequate and efficient protection to all areas within the City, the SOI, and the
remainder of the unincorporated County land.
• Periodically review service area boundaries and service goals to maintain adequate and
efficient protection to all areas within the City.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 3
Funding
• General Fund
• User Fees
• Development Impact Fees
Law Enforcement Facilities
The El Centro Police Department (ECPD) is the primary law enforcement agency that serves the
citizens of the City and land within City boundaries. The ECPD primarily operates out of one
main police station located within the Civic Center zone. Sworn officers of the ECPD patrol the
City and respond to calls reporting crimes and emergencies and requesting law enforcement
services within ECPD jurisdiction. Non-sworn personnel of the ECPD are responsible for
various administrative tasks, animal control, and parking enforcement. Volunteer personnel of
the ECPD supplement regular officers and non-sworn members of the Citizens in Police Services
(CIPS) provide assistance in other areas of ECPD jurisdiction.
As development continues to occur in the northern, western and southern portions of the City
SOI and as City boundaries are extended, new stations or substations will be developed in the
vicinity of new development to assure adequate patrol coverage and call response times. All
stations must be adequately staffed by ECPD personnel. Prior to the construction of new stations
or substations, the ECPD must hire new officers and staff to demonstrate adequate staffing.
Mitigation
• Continue the periodic review of number of calls and response times to determine the
adequacy of existing service and any need for improvement or additional resources.
• Continue the periodic review of personnel, vehicles and equipment, and facilities to
determine the adequacy of existing service and any need for additional resources.
• Establish a performance standard or performance goal for response times.
• Pursue additional funds for additional personnel, equipment, and vehicles of the ECPD.
• Obtain additional sworn personnel, non-sworn personnel, and vehicles to meet the
existing and future deficit of officers identified according to the performance standard.
• Continue to promote the volunteer officer program to aid in meeting staffing needs.
• When the ECPD is able to acquire additional personnel, the traffic enforcement unit will
be instated.
• Locate land in the northern portion of the City SOI for an additional station or substation
to accommodate anticipated development. Adequate staffing must be available in order to
open such a station.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 4
• Locate land in the southern portion of the City SOI for an additional station or substation
to accommodate anticipated development. Adequate staffing must be available in order to
open such a station.
• Review existing development impact fees for ECPD services, identify necessary
improvements to the current fee structure, and implement a revised fee structure.
• Review the Cost Recovery Study Findings prepared for the City in May 2003 and
implement recommended improvements to the ECPD user fee structure.
Funding
• General Fund
• User Fees
• Development Impact Fees
• Grants
Library Facilities
The City owns and operates the El Centro Public Library system. This system includes one main
library and one satellite facility that is open to the public and used by a broad spectrum of
community members. Services provided by the library include circulation of library materials
such as books, magazines and video and audio recordings; reference service; internet access;
word processing stations; copy machines; a publicly available conference room; children’s
reading programs; vocal, acting, and speaking workshops for children and adults; and tax
preparation assistance for senior citizens.
The existing main facility is considered an interim facility and pending the completion of a needs
assessment study. The process to decide on the location and design of the new main library will
begin after the needs assessment is completed, anticipated in the fall of 2015.
Increased development within the City boundaries and the SOI will present an increased demand
on the personnel, services, and facilities of the public library. This increased demand will be
thoroughly addressed in the needs assessment study.
Mitigation
• Continue to periodically review the facilities and personnel of the El Centro Public
Library system through the preparation of annual reports.
• Continue to utilize General Fund revenue as the primary source of financing for the El
Centro Public Library System. Review the allocation of General Fund finances in light of
State recommendation that local libraries receive five percent of local general fund
resources.
• Continue to apply for all possible library funding opportunities from the State.
• Re-apply for certification in the State Public Library Fund (PLF) program.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 5
• Review existing development impact fees for library services, identify necessary
improvements to the current fee structure, and implement a revised fee structure.
• Continue to accept donations of money and supplies as a means of augmenting library
services while conserving allocated finances.
Funding
• General Fund
• Development Impact Fees
• User Fees
• Donations
• Grants
Park and Recreation Facilities
The Community Services Department (CSD) is responsible for overseeing City park facilities
and services. Parks within the jurisdiction of the City are used by the public for various
recreational activities. Parks include amenities such as athletic fields, hard court playgrounds,
open space areas, picnic areas, swimming facilities, gymnasia, and skateboard facilities.
The City is currently operating with a deficit of parkland per its parkland performance standard.
To catch up to the existing parkland demand and to accommodate the anticipated population
increase, the City will continue to require that new development include the provision of
additional public parks and recreational facilities.
Mitigation
• Continue to require the provision of parkland or the payment of a park development fee,
in accordance with Section 24, Article V of the City of El Centro Code of Ordinances.
• Continue to periodically review the performance of CSD through the preparation of
annual reports.
• Review existing development impact fees for CSD services, identify necessary
improvements to the current fee structure, and implement a revised fee structure.
Funding
• Developer contribution of parkland and construction of parks
• General Fund
• Development Impact Fees
• Donations
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 6
• Grants
• Legacy Ranch and Buena Vista Landscape and Lighting Maintenance Districts (LLMDs)
Transportation Facilities
The City is responsible for the development and maintenance of a system of public roadways and
bicycle routes within its jurisdiction. The City’s transportation system also links to various State
and County facilities that traverse the City. The development of new roads or improvement of
existing roads is often accomplished by private developers when physical improvement of the
City’s circulation system is deemed necessary due to anticipated increases in traffic from various
development projects. The General Plan includes a Circulation Element that discloses the City’s
goals, policies, and performance criteria with respect to the circulation system, identifies the
minimum design standards for City streets, and provides a Circulation Plan showing the
projected development of the system as growth occurs within the City.
The existing circulation system is generally adequate to accommodate the current needs of the
City. Paved roadways properly link existing residential, commercial, and industrial development.
The City has identified several specific roadway improvement projects that will be necessary in
the future, including extensions of existing roadways and maintenance of existing streets. In
addition to these improvement projects, extending and creating other roadways will likely be
needed as development continues to occur within the City Limits and the SOI boundaries.
Mitigation
• Implement identified circulation system projects to improve circulation and
accommodate growth within the City.
• Continue to periodically review the list of approved roadway capital improvement
projects slated for implementation by the City to determine project status, need for
revision of the program schedule, and budgetary needs.
• Review the existing development impact fees schedule for circulation and roadway
projects, identify necessary improvements to the current fee structure, and implement a
revised fee structure.
Funding
• General Fund
• Development Impact Fees
• Local Transportation Authority (Imperial County Transportation Commission)
• State Transportation Improvement Program
• State Gas Tax
• Legacy Ranch and Buena Vista LLMDs
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 7
• Transportation Development Act – Article 3 Fund
Wastewater Facilities
The City owns, operates, and maintains a system of approximately 120 miles of wastewater
collection pipelines, pump stations, and treatment facilities that serves approximately 8,000
residences, businesses, and public facilities within the City and the City SOI. Facilities within
this system are developed and maintained by the Department of Public Works. The existing
wastewater service facilities are adequate to meet existing demands within the service area. The
Wastewater Treatment Plant and delivery system will meet demand of growth for the next ten
years.
Growth within the City will require repairs and improvements to the wastewater facilities
throughout the City, including the extension of existing lines, construction of new loop lines, and
construction or relocation of lift stations.
Mitigation
• Implement improvement projects recommended in the Sewer Master Plan Amendment as
funds become available and as deemed necessary by the Director of the Department of
Public Works.
• Implement wastewater system improvement projects included in the City’s budget and
capital improvement project reports.
• Continue to periodically review the wastewater rate and financing structure to assure
adequate funding for the implementation of new projects and the maintenance of existing
facilities.
Funding
• Wastewater Capacity Fee Fund
• Wastewater Enterprise Fund
• Wastewater Stabilization Fund
• Legacy Ranch and Buena Vista LLMDs
Water Facilities
The City owns, operates, and maintains a system for the treatment, storage, and distribution of
potable water resources that serves residences, businesses, and public facilities within the City
and the City’s SOI. The City purchases all of its untreated water from the Imperial Irrigation
District (IID), which is conveyed to City facilities from the Colorado River via the district’s
canal system. City facilities are developed and maintained by the Department of Public Works.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 8
The existing storage and conveyance capacity of 21 million gallons per day is sufficient for
existing daily water demand and peak flow requirements. The system also has adequate capacity
to accommodate anticipated near term development. Periodic improvements have been made to
modernize the facilities and materials. The system has never faced serious capacity concerns, but
will continue to require periodic improvements to accommodate growth in the City and the
City’s SOI.
Mitigation
• Implement improvement projects recommended in the Water Master Plan, as funds
become available and as deemed necessary by the Director of the Department of Public
Works.
• Update the Water Master Plan by 2018.
• Implement water system improvement projects identified in the City’s annual budgets
and the updated Water Master Plan.
• Continue to periodically review the water rate and financing structure to assure adequate
funding for the implementation of new projects and the maintenance of existing facilities.
• Require that system improvements conducted by the City or a private developer shall be
designed to conform to relevant Federal, State, and local regulations.
Funding
• Water Enterprise Fund
• Water Capacity Fee Fund
• Water Stabilization Fund
School Facilities
Residents within the City of El Centro are served by three school districts that serve
approximately 11,400 students in a total of 18 schools geographically dispersed throughout El
Centro. These districts include the El Centro Elementary School District (ECESD), the McCabe
Union School District (MUSD), and the Central Union High School District (CUHSD).
The adequacy of existing facilities is determined by comparing school year student enrollment
with student teaching station (classroom) capacity. Per this analysis, several schools are over-
capacity. To accommodate future population growth and increases in student enrollment, each
school district prepares a school facility needs assessment/facility fee justification report. This
report evaluates the number of potential new students generated from approved residential units
from the City of El Centro within their respective district boundaries to determine the future
demand for facilities. The phasing of new schools will be directly linked to the approval of new
development and the issuance of building permits.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 9
Mitigation
• Support the local school districts by working with them to determine the most appropriate
location and distribution for school facilities to serve the educational needs of the
community and encourage equitable access.
• Collaborate with school districts to determine suitable locations for new school sites that
are equitable, safe, healthy, technologically-equipped, aesthetically pleasing, sustainable,
and support optimal teaching and learning environment.
• Encourage the joint use of school facilities to provide a range of recreational and
educational opportunities for residents.
• Provide opportunities for students to attend schools within their residential
neighborhoods as well as choices in educational settings outside their neighborhoods.
Funding
• General Obligation Bonds from property taxes
• State funding
• Development Impact Fees
1.3 FINANCING SUMMARY
Existing Revenue Sources
• Sales Tax
• Property Tax
• Motor Vehicle In-Lieu Fee
• Development Impact Fees
• User Fees
• Gasoline Tax
• Local Bonds
• State Circulation/Roadway Funding Sources
• Community Development Block Grants
• Landscape and Lighting Maintenance Districts
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 10
Future Revenue Sources
• Updated User Fees
• Updated Development Impact Fees
• State and Federal Funding
Existing Financing Mechanisms
• General Fund
• Capacity Fee Funds
• Enterprise Funds
• Developer/Builder Contributions
• Local/State/Federal Grants
Future Financing Mechanisms
• Special Assessment Districts
• Community Facilities Districts
• Enhanced Infrastructure Financing Districts
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 11
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 12
SECTION 2 – INTRODUCTION
2.1 Background on the City of El Centro
The City of El Centro (City) is located in the south-central portion of the County of Imperial
(County), State of California (State). The City is located along Interstate Route 8 (I-8) between
San Diego, California and Yuma, Arizona, and is situated approximately 10 miles north of the
United States-Mexico border. State Route 86 (SR-86) traverses the City in a north-south
direction. Rail lines of the Southern Pacific Railroad traverse the city in a northwest-southeast
direction.
The City is home to approximately 45,000 residents and serves as the center of commercial,
general government, recreational, and cultural activities for much of the surrounding Imperial
Valley region. Land within City boundaries comprises approximately 12 square miles. The
City’s SOI contains land outside the existing boundaries of the City that is currently in the
jurisdiction of the County but is planned for incorporation into the City boundaries at some time
in the future. The City and the City’s SOI encompass approximately 25 square miles, or about
16,000 acres of land.
The existing General Plan provides a structure for development and planning within the City and
the City’s SOI. To guide planning within the area, the Land Use Element includes four major
land use groupings: Residential, Commercial, Industrial, and Community Facilities. While the
General Plan does not contain a specific agricultural land use designation, the City shares in the
rich agricultural heritage of the surrounding region, and much of the land within the City’s SOI
is still used for various agricultural purposes. The maintenance of agricultural uses is allowed
within the General Plan’s Rural Residential land use designation. The General Plan does not
foresee the permanent retention of large-scale agricultural operations within City limits, but the
City generally maintains a policy of allowing continued agricultural activity on certain land as it
is transitioned from agricultural uses to other urban uses.
The City provides many public facilities and services to residents and businesses within its
boundaries. The General Plan Public Facilities Element outlines the existing systems and future
plans for the public provision of facilities and services such as parks, schools, libraries, fire
protection, law enforcement, water and wastewater, and general government facilities. The
General Plan Circulation Element discusses the system of public roadways maintained by the
City and outlines future plans for the system’s expansion and improvement.
In addition, El Centro Regional Medical Center is a governmental agency of the City and is
governed by a seven-member Board of Trustees. El Centro Regional Medical Center is an acute-
care medical center that serves the health care needs of Imperial County with services that
include (but are not limited to) emergency services, intensive care, outpatient/inpatient care,
radiology and surgery.
2.2 Purpose of the Service Area Plan
This SAP has been prepared for the City in accordance with the Cortese-Knox-Hertzberg Local
Government Reorganization Act of 2000, which requires that a plan identifying the existing and
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 13
projected demand for public facilities and services be prepared by all incorporated cities and
special districts within the State. The 2000 legislation is implemented by Imperial County Local
Agency Formation Commission (LAFCo), whose policy states that a city within the jurisdiction
of Imperial County LAFCo must prepare an SAP in order for any formal annexation of land into
the city’s boundaries take place.
2.3 Organization and Use of the Service Area Plan
This SAP outlines the City’s existing public services and facilities, estimates the current and
future anticipated demand for such facilities and services, and describes how necessary facilities
and services will or may be developed and extended to meet demands. The SAP is intended to
demonstrate the City’s intent and ability to provide adequate services to the SOI boundaries at
the time of annexation. An approximately 10-year planning horizon is used to forecast growth,
and the estimated demands and provision to meet demands are based on population projections
in five-year increments until 2025. The population projections used in this document was
provided by the Southern California Association of Governments (SCAG). Projected population
growth was placed into the structure and policies of the land use plan presented in the General
Plan.
The document is organized into the following six chapters that satisfy the requirements set forth
in the LAFCo guidelines:
Chapter 1.0 EXECUTIVE SUMMARY: Provides a brief summary of the SAP,
highlighting key information regarding demand and financing.
Chapter 2.0 INTRODUCTION: Outlines the purpose and intent of the SAP and
presents its layout to help the reader use the document. This chapter also provides
background information on the City and of the planning documents that enabled the
preparation of the SAP.
Chapter 3.0 GROWTH PROJECTIONS: Provides general information about
projected population, current and future land use trends in the City and the City’s SOI,
and the implications of these trends for the development of City services and facilities.
Chapter 4.0 FACILITIES AND SERVICES: Details the current and planned facilities
and services, their current and projected adequacy, measures to ensure adequacy, and
how such measures will be achieved and financed. An analysis of the following facilities
and services are provided:
• Administration
• Drainage
• Fire
• Law Enforcement
• Library
• Parks and Recreation
• Circulation
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 14
• Wastewater
• Water
Analysis for each public service and facilities area in the SAP is based on the standards
developed by LAFCo. Each subchapter of Chapter 4 contains the following four sections:
• Performance Standard: A description of any standards or goals that have been
adopted by the City to the review of the adequacy of service within the existing and
future timeframes.
• Facility Planning and Adequacy Analysis: An inventory of the existing facilities,
the adequacy of the facilities when compared to existing demands, the anticipated
demand for facilities pursuant to growth of the City, and the phasing of the demand
for facilities.
• Financing: An explanation and identification of how services and facilities are
currently being funded, including a per capita cost where available and applicable,
and how future services and facilities may be funded.
• Mitigation: A series of recommendations to ensure that adequate facilities will be
provided and proper levels of service will be maintained.
Figures are often provided within the various sections of Chapter 4 that show City maps and the
relationship of existing and planned facilities to anticipated growth within City boundaries and
the SOI. Figures for each service and facilities area are presented at the end of each section.
Chapter 5.0 FINANCING: Identifies all of the potential funding mechanisms for public
services and facilities provision that are available to the City. This section presents potential
funding sources and then identifies how each service or facility sector is currently funded and
appropriate future funding opportunities, as well as cost saving opportunities.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 15
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 2 – Executive Summary
February 2016 Page 16
SECTION 3 – GROWTH AND PHASING PROJECTIONS
3.1 Existing Land Use
The City has a population of 43,856 residents and is the regional center for the greater Imperial
Valley region, which has an estimated population of approximately 180,666. As the regional
center for the surrounding area and the seat of the County, the City provides general government
services and many opportunities for shopping, dining, health care, recreational, and cultural
activities. In addition to its residential, commercial, and general government uses, the City
includes various agricultural and industrial operations.
The City’s incorporated and Sphere of Influence (SOI) boundaries are shown in Figure 3-1. In
all, the City’s SOI consists of approximately 16,000 acres of land bound on the north by the
Central Drain/Treshill Road, the south by McCabe Road, the east by State Route 111, and the
west by Austin Road. The City of Imperial is located directly north of the City’s northern SOI
boundary. The unincorporated township of Heber is located directly south of the City’s southern
SOI boundary.
Existing land use in the City is governed by the provisions of the City of El Centro Zoning
Ordinance and is guided by the goals and policies presented in the General Plan. By
implementing the language of the General Plan Land Use Element, the City dictates what type of
land uses are allowed throughout specific areas within its boundaries. The General Plan Land
Use Element lists the following land use designations: Rural Residential, Low Density
Residential, Medium Density Residential, High Medium Density Residential, General
Commercial (includes Neighborhood Commercial, Office Commercial, and Heavy Commercial),
Tourist Commercial, Downtown Commercial, General Industrial (includes Light Manufacturing
and General Manufacturing), Planned Industrial, Civic, and Public. Land use designations within
the City and SOI boundaries are shown in Figure 3-2. In addition to the land use designations,
the Land Use Element includes a Single Family Neighborhood Overlay that is placed on certain
residential areas of the City.
Much of the land surrounding the City is involved in agricultural uses, as farming has historically
been a principal component of the region’s economy. The General Plan does not contain an
exclusive agricultural land use designation, but agricultural uses are allowed within the Rural
Residential designation. It is generally the City’s policy to allow continuation of existing
agricultural activity on land while planning for the development of this land for other uses.
3.2 Planned Land Use
Planning and development within the City and its SOI boundaries is guided by the goals and
policies of the General Plan Land Use Element. Through the implementation of this element and
the application of the land use designations detailed above, the City is able to foresee where and
to what extent growth would occur within its boundaries and the SOI boundaries. Generally
speaking, the City’s land use policy encourages infill development within the boundaries of
existing developed areas instead of new development of agricultural lands or vacant lands in
order to best utilize existing facilities and services. Additional development in the outlying areas
is not, however, precluded by any City policy and development often occurs as such.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 17
There are several areas outside of the City boundaries and within the jurisdiction of the County
that are planned for future development and annexation into the City. It is assumed that all of the
land within the City’s SOI will one day be annexed into the City proper. Some of the areas
planned for annexation have already been developed for residential, industrial, or public uses, but
remain unincorporated land within the County jurisdiction. The existing levels of public service
and facilities provided in the potential annexation areas are identified by their categorization into
one of the three growth level tiers of the Urban Development Program (UDP), which is described
below. The General Plan does not provide a specific schedule for the annexation of land to the
City.
3.2.1 Urban Development Program
El Centro adopted an Urban Development Plan (UDP) to facilitate residential, industrial, and
business growth in those areas where public services are available and to provide a variety of
growth locations so that an adequate supply of developable land will maintain reasonable
housing costs and promote economic development. The UDP is designed to create a community
that is compact, pedestrian- and transit-oriented, that avoids the premature removal of land from
agricultural production, and that enables the City to meet the public service and infrastructure
needs of the existing and future residents.
The UDP divides the City and the SOI into three tiers of growth areas and delineates availability
of land for growth, identifies the areas that will require more extensive planning, and ensures the
provision of adequate public services and facilities, as described below. The three growth levels
are not necessarily meant to provide a sequence of development, but to delineate areas where
different levels of planning efforts would be necessary due to the greater or lesser extent of
existing services and facilities.
The UDP includes a requirement that a Community Facilities Study be prepared for certain
projects under review within the development areas. Community Facilities Studies, prepared at
the expense of the project applicant, address existing conditions, anticipated needs, and financing
plans for city sewer, water, drainage/flood control, and Circulation Element roadways affected
by the prospective development. A Community Facilities Study is not required when: 1) an
Environmental Impact Report or Mitigated Negative Declaration prepared for the project
discusses the existing conditions and impacts to the relevant public services and utilities; 2) the
project is a subdivision of five or fewer lots or a commercial or industrial development of five
acres or less and the owner/subdivider does not own or control other contiguous property within
the same Development Tier Subarea; and 3) the Initial Study prepared for the project does not
conclude that the project may have a significant impact of public services and facilities or the
project does not require sewer or water facilities. Reimbursement agreements, improvement
districts, and other public finance strategies may be used to cost-effectively provide needed
public infrastructure, as deemed necessary by the City Council.
As identified in the General Plan Land Use Element, the three tiers of the UDP are as follows:
Development Tier I – Current Urban Service Area includes land within and adjacent to the
present City Limits. In most cases, new development within this area can be served by gravity
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 18
sewer lines to existing trunk sewers. Generally, existing water lines and reservoirs are also
adequate to serve new development; however, easements and financial contributions to improve
the ultimate wastewater and water systems may be required by developments within this tier.
Existing facilities for fire, police, schools, parks, library, medical, roads, and other City services
are also in proximity to these areas, though service capacities are likely to be limited and
improvements to existing facilities and/or new facilities may be needed to adequately
accommodate new development. Subdivisions of land and commercial or industrial development
within this area would usually follow existing standard procedures for zoning, subdivision, and
environmental review, and, due to the general availability of services and facilities, would
usually not require the preparation of a Community Facilities Study.
Development Tier II – Planned Urban Service Area includes land both within and adjacent to
the City limits, but differs from Development Tier I in that public infrastructure to serve new
development is more limited. Essential required improvements may include wastewater and
water pump stations, water storage reservoirs, and sewer trunk lines or force mains. New
schools, parks, roadway improvements, and fire stations may also be required to adequately
serve development within Tier II areas. As with Tier I areas, additional service capacity for
police, library, medical, and other City services may also be needed to accommodate new
development. Preparation of a Community Facilities Study would be required for most
development projects within Tier II areas unless otherwise exempted as described in the
Community Facilities Study Requirements and Exemptions.
Development Tier III – Future Urban Service Area encompasses unincorporated lands that
are generally not planned for development within at least the next ten years. However,
identification of a parcel as Tier III does not necessarily preclude development within this
timeframe. Rather, the Tier III label indicates that services and facilities are usually not available
in the area and that subdivision of land and subsequent commercial or industrial development
within this area would require that a Community Facilities Study be prepared, unless otherwise
exempted.
The three development tiers and their geographical association with the City and SOI boundaries
are shown on Figure 3-3. There is some overlap between the City boundaries and the
development tiers, as portions of the existing City proper are indicated as Tier I and Tier II areas.
The area within the City limits that is considered developed and thus is not within any of the
development tiers is shown on Figure 3-3 in white.
3.2.2 Approved, Planned, and Proposed Development
While the General Plan identifies the general areas of the UDP that are planned for development
as the City grows, there are several specific projects that either are under construction, have been
approved by the City, are currently in the planning stages for implementation within the 2025
horizon, or which the City expects to be developed in the future. These future projects present an
anticipated demand on some or all of the City’s services. The projects are listed below and are
located within the City’s current boundaries.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 19
Residential
Citrus Grove is a proposed 150-single family residential development located on approximately
47 acres north of McCabe Road and east of SR-86. This site is outside of the City’s incorporated
boundaries, and an annexation would accompany development of the project.
Courtyard Villas is a proposed project involving 54 single-family units and a park on 21.5
acres, east of Austin Road and South of Orange Avenue.
Lotus Ranch is a proposed 213-acre project that consists of 609 single-family units, a 10.8-acre
park, and offsite improvements on La Brucherie Avenue south of Interstate 8. The site is outside
of the City’s incorporated boundaries and an annexation is required.
Town Center Village Apartments is a project located approximately 1,000 feet east of North
Imperial Avenue situated between Cruickshank drive and Bradshaw Drive. The project entails
construction of 240 multi-family residential units on 12.75 acres of land.
Mixed Use
8th Street Residential and Industrial is a multi-family residential and industrial development
on an approximately 21.7-acre site in the north-central portion of the City. The site is bound by
8th Street to the west, the Union Pacific Railroad and the North Date Canal to the west, and
agricultural land to the south. The project includes 8 industrial lots totaling 4.59 acres and 72
units.
Linda Vista is a proposed 232 single-family residential subdivision located south of the I-8 and
west of the SR 86 outside the City’s incorporated boundaries. The project totals 80 acres and also
includes 4.6 acres of commercial land and a school site.
Commercial
Imperial Valley Commons consists of approximately 780,000 square feet of commercial/retail
space located in the southeastern portion of the City south of the I-8 on Danenberg Drive and
Dogwood Avenue.
3.3 Projected Population Increase
In 2015 the Southern California Association of Governments (SCAG) prepared the Profile of the
City of El Centro that provides current information and data on population, housing,
transportation, and employment. For population growth and projected increase, SCAG
completed the 2016 RTP/SCS Growth Forecast that was developed based on local input,
historical growth trends, household size trends, projected natural increase, projected migration
and projected jobs. SCAG’s forecast used years 2020, 2035, and 2040, but for the purposes of
this SAP, a 10-year time horizon is used, from 2015 to 2025 (see Table 3-1). Since the forecast
years did not include 2025, that year was estimated by taking the population difference between
2020 and 2035, then dividing that by the number of years (15) to get a year-to-year average.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 20
Table 3-1 Projected Population Increase
Year Population
2015 43,856
2020 53,176
2025 55,100
2035 58,948
2040 60,993
Source: SCAG
State law specifies that the City must assess housing needs by reviewing the current housing
market and identifying programs that will meet housing needs as part of the required Housing
Element of the General Plan. Included in this evaluation is the City’s “Regional Housing Needs
Allocation” (RHNA) which provides an estimate of the number of housing units that should be
provided in the City to meet its share of new households in the region. The RHNA cycle period
for compliance began on January 1, 2014 and extends through October 31, 2021 (before the 10-
year time horizon for this SAP ends in 2025). SCAG is responsible for allocating the RHNA to
individual jurisdictions based on the following State Department of Housing & Community
Development (HCD) household income categories and Area Median Income (AMI):
• Very Low Income – Up to 50 percent of AMI
• Low Income – 51 to 80 percent of AMI
• Moderate Income – 81 to 120 percent of AMI
• Above Moderate Income – greater than 120 percent of AMI
It should be noted that the current RHNA cycle utilized the most recent AMI, which was $39,402
in 2011. Therefore, SCAG assigned a RHNA of 1,924 units, in the following income
distribution:
• Very Low Income: 487 units
• Low Income: 300 units
• Moderate Income: 297 units
• Above Moderate Income: 840 units
3.4 Theoretical Buildout Projections
Unlike a forecast, the theoretical build-out scenario does not have a time horizon, nor does it
include transportation, demographic, existing land use, or economic assumptions typically used
by a forecasted model to provide more realistic land use planning data. Therefore, due to
regulatory constraints, physical constraints, and foreseeable market conditions, realization of this
scenario is highly unlikely. The SAP includes an analysis of this scenario because the General
Plan land use categories do provide the theoretical capacity for residential units and non-
residential building square feet to allow the build-out estimates.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 21
The General Plan applies the Land Use Plan to the three development tiers and presents
estimated buildout projections of the number of dwelling units (households), square footage (sf)
of non-residential space, and population capacity in each of the tiers. No timeframe is presented
for the development of land within the three development tiers. Such buildout projections are
presented below. Developable acreages listed in the table below comprise 85 percent of the
relevant development area, as the remainder is assumed for the development of roadways,
utilities, and the associated rights of way. The General Plan projects the number of households to
be approximately 34,826. The number of households was determined by reviewing the types and
densities of residential development that would be respectively allowed within the rural
residential, low density residential, medium density residential and high-medium density
residential land uses occurring within each development area. An average household occupancy
of 3.22 persons per household was assumed, based on the SCAG 2015 Profile number of
households and total population. Non-residential square footage was determined by reviewing
the development densities respectively allowed within the general commercial, tourist
commercial, downtown commercial, general industrial, planned industrial, civic, and public land
uses occurring within each development area.
Table 3-2 Theoretical Buildout Population by Development Tier
Development Area Households Non-Res. sf Population
City (developed)* 13,607 22,894 43,856
Tier I 4,413 1,209 14,210
Tier II 14,135 13,082 45,515
Tier III 16,278 3,907 52,415
TOTALS
City + Tier I 18,020 24,103 58,024
City + Tier I/II 32,155 37,185 103,539
City + Tier I/II/III 48,433 41,092 155,954
* City (developed) is the area within the City boundaries and not included in the
development tiers. Source: City of El Centro General Plan, SCAG
It should be noted that the total projected population capacity for the City and the Development
Tier I, which is estimated to be 58,024, is similar to the forecasted 2025 population of 55,100, as
estimated by SCAG. Accordingly, it can be assumed that the City would be able to develop
within its boundaries and within the Tier I development area between now and 2025 to
accommodate the population increase that is projected for the area. It is not likely that future
development would be limited to occurring within the City and Tier I boundaries, but the
population accommodation figures presented in the General Plan are useful tools to quantify the
general growth potential and accommodation for such within the City and the City’s SOI. As
such, it can be assumed that growth within the City boundaries and within the City’s SOI, in
accordance with the General Plan and the UDP, is warranted to accommodate existing and
probable future needs.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 22
Legend
Service Layer Credits: Source: Esri,
City of El Centro DigitalGlobe, GeoEye, i-cubed, Earthstar
Geographics, CNES/Airbus DS, USDA,
Sphere of Influence
USGS, AEX, Getmapping, Aerogrid, IGN, IGP,
swisstopo, and the GIS User Community
Sphere of Influence Map
Figure 3-1
dxm.ecneulfnIerehpS_1-3_46471\SIG
,otohP
etiS
,noitcelloC
ataD\PAS
ortneC
lE
46471\gninnalP\:N
[
Scale in Feet
0 2,250 4,500 North
Date of Exhibit: 12/3/2015
Source: ESRI Aerial Basemap (Microsoft 5/29/2011)
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 24
Legend
Sphere of Influence
City of El Centro
Land Use Designation
Rural Residential
Low Density Residential
Medium Density Residential
High-Medium Density Residential
Tourist Commercial
General Commercial
Downtown Commercial
General Industrial
Planned Industrial
Civic
Public
Source: City of El Centro Land Use, 2015
dxm.paMesUdnaL_2_1-3_46471\SIG
,otohP
etiS
,noitcelloC
ataD\PAS
ortneC
lE
46471\gninnalP\:N
[
Scale in Feet
Land Use Map
0 3,000 6,000 North Figure 3(cid:16)2
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 26
Legend
City of El Centro
Sphere of Influence
Tier I Growth Areas
Tier II Growth Areas
Tier III Growth Areas
Source: City of El Centro, 2004
dxm.htworGreiT_2-3_46471\SIG
,otohP
etiS
,noitcelloC
ataD\PAS
ortneC
lE
46471\gninnalP\:N
[
Scale in Feet
Urban Development Tier Map
0 3,000 6,000 North Figure 3-(cid:22)
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 3 - Growth and Phasing Projections
February 2016 Page 28
SECTION 4 – PUBLIC FACILITIES AND SERVICES
The following chapter provides a detailed account of the various public services and facilities
that are developed, maintained, and operated by the City. This section covers facilities and
services for City administration, drainage, fire, law enforcement, library, parks and recreation,
circulation and roadways, wastewater treatment and sewer, and water. For each of these
facilities, an inventory of existing facilities is given and performance standards are identified
(where applicable) to gauge the effectiveness and adequacy of the existing facilities. Demands
for future facilities are discussed relative to projected growth outlined in Chapter 3. Where
applicable, plans for future facilities are discussed. Discussion is presented regarding the current
funding methods for each facilities area and the prospective sources of funding that could be
used in the future. Finally, mitigation measures are presented that would aid the City in ensuring
future adequacy and efficiency.
El Centro Service Area Plan Section 4 – Public Facilities and Services
February 2016 Page 29
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4 – Public Facilities and Services
February 2016 Page 30
4.1 General Government Facilities
The City owns and operates buildings that house general government services. These general
government facilities are located in several centrally located buildings collectively known as City
Hall, located at 1275 Main Street. There are currently three buildings in City Hall. The
southeastern building houses the City Manager’s Office, City Attorney’s Office, and Human
Resources. The northeastern building houses the Finance Department, City Clerk’s Office,
Engineering Division and the Community Development Department. The northwestern building
consists of the recently renovated Council Chambers. The City is divided into the following
Departments: City Manager’s Office, City Attorney’s Office, Human Resources, City Clerk’s
Office, Finance, Community Development, Community Services, and Public Works. Additional
government offices and buildings that provide specialized functions are located at various
locations throughout the City.
A brief description of each Department follows:
City Manager’s Office: The City Manager’s Office oversees the entire organization, with
policy direction from City Council. The City Manager’s Office is also responsible for the
preparation of the City’s periodic newsletter, social media accounts and the City’s
website.
City Attorney’s Office: The City Attorney’s Office and its staff provide legal services to
the City Council and all City departments. The Office provides a wide assortment of
services to the City, such as representing the City in litigation, preparing ordinance and
resolutions, reviewing and preparing contracts, advising the City on all legal affairs, and
other legal matters as necessary.
Human Resources: The office of Human Resources is responsible for human resources
programs, including employee recruitment, benefits administration, training and
development, and labor relations.
City Clerk’s Office: The City Clerk’s office and its staff are under the direction of the
City Council. The Office is generally charged with fulfilling public records requests,
preparing agendas and minutes for the City Council, Successor Agency, and the Finance
Authority.
Finance: The Finance Department is responsible for the preparation of the annual budget,
purchasing, accounting, and payroll.
Community Development: The Community Development Department is responsible for
coordinating long range planning and regulating private development in the City, which
includes planning, zoning, code enforcement, and building inspections. The Department
also issues building permits. This Department also coordinates the activities of the City’s
Planning Commission. The Commission meets once monthly to review development
projects and makes recommendations to the City Council.
El Centro Service Area Plan Section 4.1 – General Government Facilities
February 2016 Page 31
Community Services: This Department offers a wide variety of community services and
oversees an extensive array of City-owned facilities. The Community Services
Department contains the following Divisions: Economic Development, Public Library,
Parks and Recreation, Adult Center, Community Center, and Youth Center. The
Economic Development Division is responsible for the City’s economic development and
housing activities. The Public Library Division is tasked with managing the City’s public
library and public library activities. The Parks and Recreation Division manages the
City’s public parks and landscaping within City-owned right of ways. The Community
Services Department is located at 1249 West Main Street, located directly east of City
Hall and neighboring City Hall.
Public Works: The Department of Public Works is the largest department in the City.
Public Works is organized into various Divisions as follows that provide a wide range of
services needed by residents and businesses: Engineering, Wastewater, Water Treatment,
and General Services. The Engineering Division is tasked with overseeing and regulating
private development and roadway maintenance. The Wastewater Division ensures that
wastewater is treated effectively and ensures compliance with state and federal water
treatment requirements. The General Services Division is tasked with the maintenance of
underground utilities and traffic signals. The Public Works Yard is located at 307 West
Brighton Avenue.
I. Performance Standard
The Local Agency Formation Commission (LAFCo) requires that the general government
facilities section of the SAP include a performance standard that measures demand generated for
square feet of facility. The performance standard is a range of 500 to 600 square feet of general
government facility space per 1,000 residents. In interviews with City general government staff
as part of the SAP process, it was determined that the current space is adequate to serve the staff
and population. In November 2014 the City completed a $1.2 million dollar renovation of the
City Council Chambers that included upgrades to meet Americans with Disabilities Act (ADA)
requirements, new ventilation, enhanced lighting, and technology upgrades. The renovation
allowed the City to improve existing general government facilities without having to add
additional space. The performance standard range allows the City the flexibility to accommodate
future growth and provide adequate service through a variety of enhancements without having to
necessarily add additional space.
In addition to the amount of square footage, the performance standard for providing personnel is
a range of 0.75 to 1.0 full-time equivalent staff members per 1,000 residents. This standard is
based on the current ratio of general government personnel employed at the City of El Centro to
the current population.
El Centro Service Area Plan Section 4.1 – General Government Facilities
February 2016 Page 32
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
The City’s general government facilities are located within what is known as the Civic Center
zone; encompassing several blocks with a central location along Main Street, State Street and
Broadway between Imperial Avenue and 8th Street. Along with City Hall and the Community
Services Building, the Civic Center zone also includes the El Centro Police Department (ECPD),
whose facilities are discussed in Section 4.4 of this SAP. Several County buildings, including the
Courthouse and general government facilities, as well as the headquarters of the Imperial
Irrigation District are also located in Civic Center, although these structures are not operated by
the City. The following list provides an inventory of the square footage of the City general
government facilities.
Table 4.1-1 General Government Facilities
Facility Size (Square Feet)
City Hall 10,700
Public Works Building 4,700
City Manager/Personnel Building 4,800
City Council Chambers 2,500
Community Services Building 4,100
Total 26,800
The square footage totals listed above include the recent remodeling of the City Council
Chambers completed in November 2014.
Adequacy of Existing Facilities
The existing City general government facilities are in acceptable condition and spacious enough
to accommodate the scope and scale of City general government services. The existing amount
of office and meeting space is acceptable to accommodate the current employees, customers, and
other users of the City’s general government facilities, as well as to accommodate future needs.
Although the City was deeply affected by the recession that began in 2008, it did not layoff any
City employees, thereby, continuing to provide adequate levels of service to the community.
There are currently 37 full-time equivalent general government employees including the City
Clerk’s office, City Manager’s office, Human Resources, City Attorney’s office, Facility
Maintenance, Successor Agency, Economic Development, and Planning. With a population of
43,856 in 2014, the current staffing ratio is 0.84 employees per 1,000 residents, satisfying the
performance standard range of 0.75 to 1.0 full-time equivalent employees per 1,000 residents.
Future Demand for Facilities
Additional building space was created to expand the general government facilities to
accommodate anticipated near-term needs through at least 2020. Increased development within
El Centro Service Area Plan Section 4.1 – General Government Facilities
February 2016 Page 33
the City boundaries and the sphere of influence (SOI) will present increased demands on the
City’s general government facilities as programs and personnel are added to serve the increase in
population to 53,176 in 2020 and 55,100 in 2025.
The existing general government facilities are centrally located in an area that is easily accessible
to many City residents. Maintaining a centrally located City Hall within the Civic Center zone is
an effective way to administer City programs and services, and is in conformance with General
Plan Public Services Policy 6.1. It is not likely that growth within the SOI will demand that
additional facilities be constructed in new locations, as the current central location will remain
accessible to new development throughout the SOI. In addition, improvements in technology,
amount of general government personnel, and other facility enhancements can be used by the
City to accommodate population growth.
When needed, future demands can be met by expanding existing structures. Should this not
prove to be a feasible option, the City may consider purchasing additional land within the
immediate vicinity of the City Hall, especially land within the adjacent Civic Center zone.
Opportunities for Shared Facilities
A publicly available conference room located in the City of El Centro Public Library is
occasionally used to house meetings when conference space is not available in the City Hall
buildings.
Phasing
The City does not currently have any plans for the expansion of the general government facilities
within the Civic Center.
As the City grows, the expansion of general government facilities would likely occur within the
existing City Hall building complex or the adjacent Civic Center zone. Maintaining a single,
centrally located Civic Center will allow efficient operation of general government programs and
services.
III. Mitigation
In order for the City to provide residents adequate general government services and to assure that
future demands for services and facilities are properly identified and addressed, the City will
implement the following measures:
• Comply with the performance standards for City general government facilities and
personnel.
• Continue to periodically review the general government facilities, services and personnel
of the City through the preparation of annual reports. Such review will identify staffing
El Centro Service Area Plan Section 4.1 – General Government Facilities
February 2016 Page 34
and budgetary concerns as City growth continues to increase the demand on facilities,
services and staff.
• Continue to periodically review the user fees charged for services of the Planning,
Building and Engineering Divisions and implement recommended increases to the fee
structure.
IV. Financing
Current Funding
The maintenance and operation of the City’s general government facilities and staffing for
general government services is financed by the General Fund. The City charges user fees for the
performing various general government tasks, as well. The funds from these fees are deposited
into the General Fund. The General Fund is further described in Section 5 of this SAP.
The City charges development impact fees for “other public facilities.” These fees may be
partially used to fund large-scale development and improvement projects related to general
government facilities. The City’s development impact fees program is further described in
Section 5 of this SAP.
Cost Avoidance Opportunities
There are no cost savings opportunities for the City.
Recommended Funding
The City will continue to use the General Fund for the maintenance and operation of the general
government facilities and general government staff. As the City continues to grow, any necessary
expansion of the facilities or acquisition of additional property for general government facilities
could be financed by issuing bonds or collecting development impact fees.
An update to the Cost Recovery Study (study that focuses on short and long-term
implementation strategies to enhance services and efficiency in City operations) and the City’s
user fees would provide increased revenue that could be used for operational improvements and
expansion of general government facilities. An updated development impact fee study will also
bring such fees up to date and align revenues with capital projects that mitigate new growth. Any
increase in development impact fees for general government facilities would increase the funds
available to pay for specific large-scale development or improvement projects related to such
facilities.
El Centro Service Area Plan Section 4.1 – General Government Facilities
February 2016 Page 35
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4.1 – General Government Facilities
February 2016 Page 36
4.2 Drainage Facilities
The City owns, operates, and maintains a system of drains that conveys storm water and urban
runoff. The majority of the drainage system was constructed in “piecemeal” fashion. As areas in
the City developed and streets were improved, the drainage system was extended or retrofitted to
convey surface runoff from the development and streets. The system is managed by the
wastewater division of the Department of Public Works, and the City does not maintain a
separate budget for drainage maintenance or improvements.
I. Performance Standard
In April of 2009 the City drafted a Master Plan of Drainage (MPD) to establish drainage design
criteria, identify the existing drainage deficient areas subject to localized flooding, and
recommend drainage improvements that eliminate or reduce existing deficiencies to a level of
insignificance, and present cost estimates and schedules for the design and construction of the
recommended drainage improvements.
The performance standard for drainage facilities is to prevent flood conditions that would
adversely affect residences, businesses, and facilities during a ten-year frequency storm event.
The General Plan Circulation Element includes the specific design standards for roadways, which
include gutters and proper slopes from the centerline to the edge of the roadway to address
drainage and prevent pooling.
Beginning in 2014, the City is implementing new storm water quality standards to comply with
the Phase II Small Municipal Separate Storm Sewer System (MS4) requirements. The new
program will identify new development and reporting requirements, as well as new storm water
quality design standards.
The drainage system must also conform to the specific standards set forth by National Pollutant
Discharge Elimination System permit requirements, MS4 Permit, Federal Emergency
Management Agency requirements, and Imperial Irrigation District requirements.
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
In general, the City of El Centro drains in a north easterly direction and is tributary to the Salton
Sea. The City prepared a master plan for the drainage system in April of 2009. Underground
drainage facilities primarily exist in the downtown portion of the City. Some City-operated
facilities drain into irrigation drains owned and operated by the Imperial Irrigation District.
Major improvements were last made to the drainage system in the 1980s. Gutters are required in
new streets within the City, with curbs required along the outside edges of the streets and a two
percent slope required from the roadway’s center line to the curb. These gutters convey storm
water and keep water from pooling in the roadway.
El Centro Service Area Plan Section 4.2 – Drainage Facilities
February 2016 Page 37
Drainage issues are reviewed on a project-by-project basis. As a general policy, the City
approves of the installation of retention basins on development projects. Projects developed
within the City often contain grass fields or vegetated areas into which development-related
flows drain and seep into the ground. Thus, drainage within the City is often self-contained
within specific developments and does not flow into one large, City-operated system.
Adequacy of Existing Facilities
According to the Master Plan of Drainage (MPD), several of the existing storm drains have
inadequate capacity to convey the runoff produced by a ten-year design storm event. Ten storm
drain projects are recommended to mitigate drainage deficiencies for the highest priority projects.
The entire storm drain system that is owned by the City was analyzed using the HYDRA routing
software and the following criteria to determine if a system is deficient:
1. Where a problem area has been identified by City maintenance crews.
2. Where a 10-year storm exceeded the full capacity of the existing mainline storm
drain.
3. Where 10-year frequency storm exceeds the top of curb elevation.
Ten segments of drainage facilities located throughout the City were identified as inadequate and
needing improvements to meet the ten-year storm event performance standard.
Future Demand for Facilities
The Master Plan of Drainage identified ten locations that require improvements at existing
deficient drainage facilities. These improvements include extensions to the existing storm drains,
the installations of a parallel storm drain, and the replacement of existing undersized systems.
These facilities will need improvement to accommodate increased demand as the City’s
population grows. In addition, as the City continues to grow, additional impervious surface will
be constructed over agricultural land or otherwise undeveloped land, disenabling storm water and
urban runoff from seeping into the ground in its natural drainage pattern. This will require
consideration for additional drainage facilities to prevent flood conditions. It is most likely that
the City would continue to allow the construction of drainage facilities in each development that
contains the flows from the development. Such facilities would be constructed by the developer,
which would prevent the City from needing to construct further major improvements in most
parts of the City boundaries and SOI boundaries.
Opportunities for Shared Facilities
The City requires retention basins be landscaped and include pedestrian pathways. Thus,
retention basins also serve recreational purposes. Lotus Park is an example of a retention basin
that also includes soccer fields for use by the public. However, these retention basins are not
officially included as City park space since their primary function is for drainage, and they
become inaccessible during rainstorms.
El Centro Service Area Plan Section 4.2 – Drainage Facilities
February 2016 Page 38
Phasing
Phasing of storm drain improvements is outlined in the ten-year storm drain Capital
Improvement Program (CIP) from the Master Plan of Drainage. The proposed CIP has scheduled
the design and construction of the top ten Priority 1 projects over a twenty-year period. As
development continues within the City boundaries and the SOI, consideration will be given for
storm water drainage issues in order to prevent water quality and flood conditions. Newly
constructed roads associated with new development will be engineered to City standards and will
include gutters and adequate slope from the centerline to allow the proper conveyance of storm
water.
III. Mitigation
In order for the City to assure the adequate provision of storm water and urban runoff drainage
within the City boundaries and within the SOI, the City will implement the following measures:
• Continue implementation of the 2009 City of El Centro Master Plan of Drainage and the
identified drainage improvement projects.
• Continue to require new roadways within the City boundaries and the City SOI
boundaries to meet City requirements for provision of gutter features and slopes to
properly convey storm flow.
• Continue to require that new development projects address potential drainage issues and
provide adequate facilities to convey storm flow. If developments would drain into
facilities of the City’s system, require that the developer consult with the Department of
Public Works to assure that improvements are engineered and constructed to City
standards.
• Require compliance with new MS4 permits for stormwater quality.
IV. Financing
Current Funding
Within the City and the SOI, these facilities are typically installed and funded by developers as
projects are implemented. Development impact fees charged on new development for drainage
facilities are also collected. An existing rate structure is charged to City customers for storm
water service.
According to the 2009 Master Plan of Drainage, the top ten Priority 1 projects were ranked from
1 to 10 with an estimated total cost of approximately $25 million (2009 dollars). The
construction costs were based on 2009 unit costs. The design costs were estimated at 10% of the
construction cost and the construction administration and inspection was also estimated at 20%
El Centro Service Area Plan Section 4.2 – Drainage Facilities
February 2016 Page 39
of the construction cost. An additional 35% was added for catch basin inlets, manholes, junction
structures, and other direct costs while a 20% contingency was added for unknowns such as
utility relocation or subsurface conditions.
Construction costs and fees should be reviewed in the future for potential escalation of the costs
based on the Engineering News Record’s Construction Cost Index (ENR-CCI). Because most of
the recommended facilities are located in the existing public right-of-way or easements, right-of-
way acquisition costs were not included.
Cost Avoidance Opportunities
The City is able to avoid costs for the development of drainage facilities by requiring developers
to construct adequate facilities and retention basins on their projects.
Recommended Funding
Funding responsibilities for project-related facilities shall remain with the developers and secured
prior to construction. Improvements to the centrally located City-maintained facilities shall
remain under the guidance of the wastewater division of the Department of Public Works.
Given the high cost of the drainage improvements identified in the Master Plan of Drainage
(MPD), it is likely that no single funding method will be sufficient to fully implement the MPD
and the identified capital improvement projects. Therefore, it is recommended that the City
consider various combinations of funding methods to implement the program, including General
Fund monies, drainage fees, and grants from the HCDA, special assessments, highway
improvement projects, and general obligation bonds. Funding responsibilities for project-related
facilities shall remain with the developers and secured prior to construction. Improvements to the
centrally located City-maintained facilities shall remain under the guidance of the wastewater
division of the Department of Public Works. Each of these proposed funding sources are subject
to extensive community debate and discussion. The number and timing of development projects
is largely beyond the control of the City and, thus, the availability of funds is difficult to assure.
In addition, a Water, Wastewater and Storm Water Rate Study Update was completed in 2012
that determined the adequacy of the existing rate structure charged to City customers for storm
water service and recommended rate changes and other revenue sources to pay for storm water
facilities.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as flood control and drainage projects.
El Centro Service Area Plan Section 4.2 – Drainage Facilities
February 2016 Page 40
4.3 Fire Facilities
The City manages the El Centro Fire Department (ECFD). The ECFD provides emergency and
disaster response to mitigate fire, emergency medical (EMS), hazardous materials (hazmat), and
other incidents within its boundaries as well as to other jurisdictions pursuant to a mutual aid
agreement. The mission of the ECFD is to protect life, property, and environment through
mitigation, preparedness, response, and recovery actions.
I. Performance Standard
The Public Facilities Element of the General Plan includes Public Facilities Goal 5, which states
that the City “strives to ensure that adequate standards of fire protection are met by providing the
ECFD with personnel, equipment, and facilities.”
The ECFD has adopted standards for fire and emergency response performance based on the
National Fire Protection Association Standard 1710 (2010 Edition) – Standard for the
Deployment of Fire Suppression Operations, Emergency Medical Operations, and Special
Operations to the Public by Career Fire Departments. The ECFD standards require that they meet
the response times listed below at least 90% of the time. All times are from the receipt of a
dispatch notification for emergency service:
Turnout Times:
EMS 60 Seconds
Fire 60 Seconds
Special Operations 80 Seconds
Response Times*:
First Arriving Engine: 240 Seconds
Full Alarm Assignment: 480 Seconds
Basic Life Support with AED**: 240 Seconds
Advanced Life Support: 480 Seconds
* -
Fire response times are for single family residences.
** -
Automated External Defibrillator.
The ECFD also maintains a staffing standard providing that ten sworn and uniformed personnel
will be available to respond to calls at any given time throughout the day or night. The ECFD
provides services for a significant number of visitors and residents from nearby and distant
jurisdictions that are conducting business, accessing public or private services, or just passing
through El Centro.
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 41
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
The ECFD provides service within the City limits and, pursuant to a mutual aid agreement with
other jurisdictions, other parts of Imperial County and California. The ECFD has three fire
stations as shown in Figure 4.3-1. Fire Station No. 1 is centrally located within the City at 775
West State Street. Fire Station No. 2 is located near the City’s eastern boundary at 900 South
Dogwood. Fire Station No. 3 is situated near the City’s Northwestern boundary at 1910 North
Waterman Avenue.
The ECFD currently has 41 sworn uniformed personnel, 3 non-sworn or non-uniformed
personnel, and several vehicles and pieces of equipment, as detailed below. In the following list,
a breakdown of sworn uniformed personnel is presented that indicates the staffing of department
positions and any relevant specializations within the department, or “collateral assignments”.
Table 4.3-1 Fire Personnel
Staff Number
Uniformed Personnel 41
Department Position Assignments:
Fire Chief 1
Battalion Chiefs 3
Fire Captains 10
Fire Engineers 9
Firefighters 18
Collateral Assignments:
Advanced Life Support Personnel 15
Hazardous Materials Tech. Specialists 13
Non-Uniformed Personnel (admin.) 3
Table 4.3-2 Fire Equipment
Apparatus/Fleet: Number
Fire Engines 4
Ladder Truck 1
Rescue Squad 1
Mobile Air Machine 1
Incident Command Vehicle 2
Hazardous Materials Unit* 1
Urban Search and Rescue Type II** 1
*
- Shared through the Joint Powers Authority
**
- Shared through Office of Emergency Services
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 42
A mutual aid agreement exists between the ECFD and the other jurisdictions in Imperial County
and California for the provision of emergency services. ECFD responds to calls within the City
limits and a portion of the SOI boundaries. The mutual aid agreement also includes that the
ECFD and Imperial County Fire Department (ICFD) would provide backup assistance within
other jurisdictions as needed.
Adequacy of Existing Facilities
The ECFD prepares an annual report that includes response calls for the various services
performed throughout the year. The annual report aids the City and the ECFD in periodically
reviewing its performance and determining where additional resources are needed. Most recently,
the ECFD logged an average response time of 4:08 for all emergency calls. The ECFD responded
to 4,122 calls for service in 2014.
Table 4.3-3 Average Response Times per Station
Station EMS Fire
Station No. 1 3:43 4:03
Station No. 2 4:26 5:18
Station No. 3 4:34 4:25
Fire Station No. 1 is the centrally-located. This facility is 7,300 square feet and is staffed with 3
to 5 personnel and houses 1 engine, 1 truck, and 1 rescue squad.
Fire Station No. 2 is located near the eastern border. The facility is 5,670 square feet and staffed
with 3 personnel and houses 1 engine.
Fire Station No. 3 is located near the northwestern border and also serves as headquarters for
administration. The facility is 18,000 square feet and is staffed by 4 personnel and houses 1
engine, 1 USAR trailer, 1 mobile air machine, and 1 command vehicle. The Chief, 1
administrative captain and 3 non-uniformed personnel are assigned to this facility Monday
through Friday.
Future Demand for Facilities
Increased development within the City boundaries, SOI and jurisdictions within the mutual aid
agreement will place additional demands on the services, personnel, and equipment of the ECFD.
As calls become more numerous with the increased density and intensity of development, the
ECFD will experience an increase in demand for emergency and non-emergency service
responses; making it more difficult for the ECFD to meet their performance standards.
Annexation of land beyond the existing service area would increase the response time for
emergency and non-emergency calls due to the increase in distance required to arrive at the
location of the emergency.
Residential and commercial growth is anticipated within the northern and southern portion of the
City SOI, within Development Tiers I and II. Fire Station No. 3 was constructed and located in
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 43
the northwestern portion of the City in anticipation of growth in the northern SOI. Development
in the southern SOI area would include annexations to the City and to the service area of the
ECFD, and would place new homes and businesses outside an area in which the ECFD is able to
provide services. As development occurs in these areas, the City plans to develop a fourth ECFD
fire station to house fire and emergency response personnel, equipment, and vehicles. The future
provision of new fire stations is discussed in the General Plan Public Facilities Element.
Opportunities for Shared Facilities
The ECFD maintains a mutual aid agreement with local agencies and the state for service within
the SOI and other jurisdictions in Imperial County and California. The ECFD and other local
agencies share the Hazardous Materials Unit. The City shall continue to pursue this relationship
with these agencies and the jurisdictions shall periodically review their service area boundaries
and their service goals to maintain adequate and efficient protection to all areas within the City,
the SOI, and the remainder of Imperial County.
The ECFD operates and shall continue to operate under mutual aid agreements with other
agencies as-needed for assistance and backup. This method helps the ECFD avoid costs while
assuring that people and property within the City, the SOI, and the rest of the County are covered
by adequate fire and emergency response. The ECFD participates in a multi-agency JPA which
provides and maintains a hazardous materials emergency response unit. The ECFD is also in a
JPA with other agencies including Imperial Valley College (IVC) that provides a Live Burn
Trailer for training. The ECFD has an agreement with State Office of Emergency Services (OES)
that provides a Type II Urban Search and Rescue trailer. These agreements allow multiple
agencies to utilize the equipment and share maintenance which aids in avoiding costs for all
agencies involved.
Phasing
As development occurs in the southwestern portion of the City SOI, Fire Station No. 4 is to be
developed. This new station would be located east of La Brucherie Avenue and south of Wake
Avenue.
Developing this new station would help prevent development from overloading the personnel,
equipment, and facilities of both the ECFD and the ICFD, and would keep response time low in
accordance with Public Facilities Goal 5. The new station will also require additional personnel
and equipment to staff and outfit the ECFD facilities and continue to provide an adequate level of
service.
III. Mitigation
In order for the City to assure adequate fire and emergency response service within its boundaries
as development continues within the City boundaries and within the SOI, the City will implement
the following measures:
• In conformance with General Plan Public Facilities Policy 5.2, continue the periodic
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 44
review of number of calls and response times to determine the adequacy of existing
service and any need for improvement or additional resources.
• Design and implement a year-long workload monitoring program to determine the
adequacy of the existing staffing standard of providing ten sworn and uniformed
personnel to be available to respond to calls at any given time throughout the day or
night. The monitoring program should analyze and measure the actual workload of
uniformed personnel, including chiefs, captains, engineers and firefighters for each on-
duty period or shift. In addition to reviewing the number of calls and response times that
are currently tracked, the monitoring program should be designed to measure the time
actually used for the following:
incident documentation
o
apparatus and station maintenance
o
training
o
various administrative tasks
o
The monitoring program should be used to evaluate the following:
response time goals for calls for emergency service
o
use of overtime to backfill minimum staffing slots due to personnel vacancies or
o
personnel who are on various types of leave
ability to cover the absence of one shift worker without requiring overtime
o
need to use budgeted overtime to cover staff vacancies when needed
o
The monitoring program should be used to make adjustments to staffing levels, either
increasing or decreasing uniformed personnel for various shifts based on actual measured
workloads.
• Review the existing mutual aid agreement that exists between the ECFD and the Imperial
County Fire Department (ICFD) as well as other jurisdictions in Imperial County and
California for the provision of emergency services. The mutual aid agreement should be
reviewed to determine if sharing of fire apparatus and uniformed personnel can be
increased in a manner that reduces the need for both total vehicles as well as for
specialized apparatus. This increased sharing of apparatus and personnel should not be
relied on for the initial call for service. Sharing of apparatus and personnel would only be
appropriate after evaluation of the event by the first responding unit. A request for
additional apparatus and personnel from other nearby fire agencies could reduce the need
for staffing during times of day requiring low workloads for personnel and equipment.
• Pursue additional finances to fund additional personnel, equipment, and vehicles for the
ECFD as identified in the workload monitoring program.
• When the City determines the need, purchase land and construct Fire Station No. 4.
• Review existing development impact fees for ECFD services, identify necessary
improvement to the current fee structure, and implement revised fee structure.
• Periodically review the mutual aid agreement with the ICFD for service within the SOI to
maintain adequate and efficient protection to all areas within the City, the SOI, and the
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 45
remainder of the unincorporated County land.
• Periodically review service area boundaries and service goals to maintain adequate and
efficient protection to all areas within the City.
IV. Financing
Current Funding
The El Centro Fire Department operational and maintenance costs for facilities, equipment and
personnel are financed by the General Fund. Revenues from user fees charged by the ECFD go
into the General Fund and used to fund the ECFD programs. Development impact fees required
of development projects generate revenue that is used for large-scale improvement and
development projects related to fire facilities as a result of increased capacity.
Cost Avoidance Opportunities
The ECFD operates and shall continue to operate under a mutual aid agreement with the County
of Imperial County Fire Department for as-needed assistance and backup. This assures that
people and property within the City, the SOI, and the rest of the County are covered by adequate
fire and emergency response. The two agencies also share a hazardous materials emergency
response unit. The ECFD participates in a countywide joint purchase program. Further, ECFD
conducts fire inspections while a private vendor conducts plan review of new structures which
enables ECFD staff to focus on additional priorities. The fire and police departments also plan to
study a regional dispatch center that can result in cost savings.
Recommended Funding
The General Fund is used to account for all revenues and expenditures necessary to carry out the
Fire Department services. Expansion or additions to the existing inventory of facilities could be
funded through issuance of new bonds backed by the general fund to meet fire service protocol.
As discussed above, an update to the Cost Recovery Study could include new or revised user fees
for services performed by the ECFD. Increased user fees for the department would increase
department contribution to the General Fund. The Fire Department indicated the potential for
developing a subscription based EMS fee that could be part of the fee study update. Also, there
could be study of receiving reimbursement from insurance carriers for fire department response
to incidents.
An update to the development impact fees study will bring such fees up to date and potentially
increase revenue for the City based on development patterns. Any increase in development
impact fees for ECFD service or facilities would increase funds available for large-scale
development and improvement projects.
The City also may consider the establishment of a community facilities district for the ECFD to
centralize funding for the Department and allow an efficient and effective means of financing
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 46
Department needs.
Funding and resources for the future Fire Station No. 4 would come from a combination of
impact fee funds and donation of land by developers undertaking projects in the relevant areas of
the City.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as fire facilities.
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 47
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 48
Legend
Service Layer Credits: Source: Esri,
City of El Centro DigitalGlobe, GeoEye, i-cubed, Earthstar
Geographics, CNES/Airbus DS, USDA,
Sphere of Influence
USGS, AEX, Getmapping, Aerogrid, IGN, IGP,
Fire Station Zones
swisstopo, and the GIS User Community
Zone 1
Zone 2
Zone 3
Fire Station No. 3
Fire Station No. 1
Fire Station No. 2
Fire Facilities Map
Figure 4.3-1
dxm.seitilicaFeriF_1-3.4_46471\SIG
,otohP
etiS
,noitcelloC
ataD\PAS
ortneC
lE
46471\gninnalP\:N
Scale in Feet
0 2,250 4,500 North
Source: City of El Centro, 2015
ESRI Aerial Basemap (Microsoft, 2011)
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4.3 – Fire Facilities
February 2016 Page 50
4.4 Law Enforcement Facilities
The City operates the El Centro Police Department (ECPD), which is the primary law
enforcement agency that serves the residents of the City as well as the property and business
owners, government and private business employees and customers, and visitors within City
boundaries. Sworn officers of the ECPD patrol the City and respond to calls for crimes,
emergencies, and other law enforcement services within their jurisdiction. Non-sworn personnel
of the ECPD are responsible for various administrative tasks, animal control, and parking
enforcement. Volunteer personnel of the ECPD provide assistance and supplement regular
officers and non-sworn members of the Citizens in Police Services (CIPS).
I. Performance Standard
The General Plan for the City contains the goal of maintaining a staffing goal of 1.75 sworn
officers per 1,000 City residents. In addition, the ECPD staffing goal is to have a minimum of
five police personnel on duty, including four responding officers and one supervising sergeant or
officer-in-charge at any given period throughout the day and night. However, sworn officer per
1,000 staffing goals lead to a one size fits all type analysis that has limited use in making
comparisons with other cities and evaluating the adequacy of the actual effectiveness of law
enforcement.
Traditional law enforcement staffing level models have measured crime trends, officer’s per-
capita, minimum staffing levels per shift, authorized/budgeted levels, and workload-based
models to make staffing decisions. El Centro currently uses a combination of officer’s per-capita
and minimum staffing levels per shift, as described above. However, a better evaluation of law
enforcement staffing adequacy is to analyze and measure the actual workload of sworn patrol
officers.
Officer workload measures the amount of time that an officer is able to spend on discretionary
patrol time while not responding to calls for service and mandatory administrative activities.
Discretionary patrol time allows officers to make self-initiated stops to investigate suspicious
activity when observed, talk with citizens to recommend crime prevention measures when
appropriate and act as a deterrent to crime by just being visible on patrol. The measurement of
officer workload allows for the City to determine the actual levels of demand for police services
and matches that demand with the supply of police resources. Use of this performance
evaluation would require a complex data analysis that may be beyond the capacity of the ECPD,
but it would provide a more accurate and reliable predictor of police staffing levels.
As a general guideline, law enforcement staffing levels should result in 60% of total sworn
officers available for patrol activities and not more than 60% of patrol resources are used on
calls for service and mandatory administrative activities.
The ECPD does not maintain response time goals but tracks and reviews response times on an
annual basis to determine the adequacy of their service and any possible alterations or
improvements to their methods that would reduce response time.
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 51
The current response time for the various categories of calls for service is:
• Crimes in progress: 3 - 5 minutes
• Crimes just occurred: 10 - 11 minutes
• Crimes past occurred: 15 - 16 minutes
The ECPD performance standard for the number of non-sworn personnel is one non-sworn
employee for every two sworn officers in order to adequately serve the City. This goal is used to
assess the existing and future desired staffing levels of the ECPD in this document.
The ECPD performance standard for the number of vehicles is one patrol car (including both
marked and unmarked cars) for every two sworn officers. This goal is used to assess the existing
and future desired number of vehicles needed by the ECPD in this document.
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities and Staff
The main station of the ECPD is located within the Civic Center zone at 150 North 11th Street.
The station consists of several buildings, constructed at different times for different purposes that
have been remodeled and interconnected to house the various functions needed.
There are currently only two sworn officers in the volunteer Police Reserve Program, and only a
few volunteers participating in the CIPS Program. The City does not pay salaries for volunteers
but ECPD supplies volunteers with equipment, uniforms, weapons, vehicles, and communication
equipment. ECPD also assumes costs for training volunteers and maintaining acceptable training
levels.
The following is a detailed list of the Department’s sworn personnel, non-sworn personnel, and
vehicles:
Table 4.4-1 Sworn Personnel
Title Personnel
Chief of Police 1
Executive Commander 1
Commanders 2
Sergeants 8
Police Officers 37
School Resource Officers 3
Total 52
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 52
The ECPD also employs 24 non-sworn personnel that are assigned to various services including
records, communication, evidence, animal control, community service, computer information
services, and parking enforcement.
Table 4.4-2 Non-sworn Personnel
Title Number
Supervisor 2
Dispatcher 9
Animal Control Officer 2
Community Service Officer 3
Parking Enforcement 1
Staff Assistant 2
Maintenance 1
Records Clerk 4
Total 24
Table 4.4-3 Vehicles
Type Number
Marked Patrol Car 20
Unmarked Car 12
Scooter 1
Truck 3
SWAT Utility Van 1
Total 37
Adequacy of Existing Facilities and Staff
With 52 sworn officers, the ECPD is currently staffed at a ratio of approximately 1.2 officers per
1,000 residents. This rate was calculated as follows:
52 sworn officers / 43,856 residents X 1,000 = 1.2 officers per 1,000 residents
This existing sworn officer ratio is below the established goal of 1.75 officers per 1,000
residents. To meet the City’s established goal, the ECPD would need to employ 77 sworn
officers. Accordingly, the ECPD is currently operating at a deficit of 25 sworn officers when
compared to the established goal.
Applying the goal of one non-sworn personnel for every two sworn officers, the projected
existing demand of 77 sworn officers would necessitate 39 non-sworn personnel. As such, the
ECPD is currently in deficit of 15 non-sworn employees.
Similar to the desired ratio of non-sworn staff to sworn officers, the ECPD would need one patrol
vehicle for every two officers. That means that 39 patrol vehicles would be needed to
accommodate 77 sworn officers. As the department currently has 32 patrol cars, they are in a
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 53
deficit of 7 vehicles. The 2014-2015 Budget funds the purchase of 6 patrol vehicles, two K-9
vehicles and 2 general service vehicles, which will exceed the desired number of patrol vehicles.
Due to inadequate staffing and funding, the ECPD has closed down the substation that it had
previously operated at Posada del Sol (1400 North Imperial Avenue at Pico Avenue). This deficit
in staffing has compromised the ability of the department to proactively serve the City by
providing traffic enforcement, Community Oriented Policing (COPS), expanding the K-9 unit
and participating in the activities of local task forces. In addition, the 11th Street station’s
structure is aging and in need of repair or replacement.
Crime data is useful in tracking public safety over time, as well as the effectiveness of prevention
and response efforts on regional crime rates. Crimes are classified as violent crimes (burglary,
larceny-theft, motor vehicle theft, arson) and property crimes (murder, manslaughter, rape,
robbery, aggravated assault). Overall reported crimes increased from with 2,423 in 2007 to 2,650
in 2012, an increase of 9.4%. Although reported incidents in violent crime decreased by 50.7%,
this was offset by a 19.5% increase in property crimes, which make up 93% of the total reported
incidents of crime.
Future Demand for Facilities and Staff
The ECPD is currently understaffed and does not meet its staffing goal. In addition to
supplementing the staff required to meet its staffing goal, the ECPD will require more patrol
vehicles to provide adequate services to the City as the population grows. The projected 2025
population of 55,100 residents would necessitate 96 sworn officers, 48 non-sworn personnel and
48 patrol vehicles if the ECPD were to meet its staffing and patrol vehicle goals.
A new station is needed to accommodate the facilities needed by the ECPD to provide law
enforcement services to the residents, property and business owners, government and private
business employees and customers, and visitors of El Centro. The City will need to complete a
needs assessment that will determine the new station location and design. The estimated cost of a
new Police Building is $20 million.
The 2014-2015 Budget states the need for three major capital projects; a new library, new police
building and a new aquatic center. Approximately $8.5 million in funds has been reserved for the
construction of these new facilities; however, the priority of these projects will determine the
timing and phasing of design and construction. It is anticipated that the City will need to issue
bonds to pay for the design and construction of the new station if the reserved funds are not used.
As development continues to occur in the northern, western, and southern portions of the City
SOI and as the City boundaries are extended, new stations or substations will be developed in the
vicinity of new development to assure adequate patrol coverage and response to calls. Stations
must be adequately staffed by ECPD personnel, and the ECPD must hire new officers and staff
and demonstrate that staffing is available prior to the construction of new stations or substations.
It should be noted that the ECPD provides services for a significant number of visitors and
residents from nearby and distant jurisdictions that are conducting business, accessing public or
private services, or just passing through El Centro.
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 54
Opportunities for Shared Facilities
When necessary, the ECPD cooperates with the Imperial County Sheriff’s Department for the
provision of emergency backup services, but the two agencies do not currently share any
facilities and would not share any facilities in the future.
Phasing
Table 4.4-4 below shows the numbers of sworn officers, non-sworn personnel, and patrol cars
that would be required to meet the staffing and patrol vehicles goals pursuant to projected
population increase through the 2025 planning horizon.
Table 4.4-4 Police Demand
Year Population Officers Non-Sworn Patrol Cars
2015 43,856 77 39 39
2020 53,176 93 47 47
2025 55,100 96 48 48
As development occurs in the northern portion of the City and the City SOI, the City will open a
substation in a central northern location to serve additional development in this area.
As development occurs in the southern portion of the City and the City SOI, the City will
consider developing a station or substation to serve additional development in this area.
III. Mitigation
In order for the City to assure adequate law enforcement service within its boundaries as
development continues within the City boundaries and within the SOI, the City will implement
the following measures.
• Continue the periodic review of number of calls and response times to determine the
adequacy of existing service and any need for improvement or additional resources.
• In conformance with General Plan Public Facilities Policy 4.1, continue the periodic
review of personnel, vehicles and equipment, and facilities to determine the adequacy of
existing service and any need for additional resources.
• Design and implement a year-long workload monitoring program to determine the
adequacy of the existing staffing standard of 1.75 sworn officers per 1,000 residents and
to have a minimum of five police personnel on duty, including four responding officers
and one supervising sergeant or officer-in-charge at any given period throughout the day
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 55
and night. The monitoring program should analyze and measure the actual workload of
sworn officers, including chiefs, commanders, sergeants and patrol officers for each on-
duty period or shift. In addition to reviewing the number of calls and response times that
are currently tracked, the monitoring program should be designed to measure amount of
time that an officer is able to spend on discretionary patrol time while not responding to
calls for service and mandatory administrative activities. Discretionary patrol time allows
officers to make self-initiated stops to investigate suspicious activity when observed, talk
with citizens to recommend crime prevention measures when appropriate and act as a
deterrent to crime by just being visible on patrol.
The monitoring program should be used to evaluate the following;
response time goals for calls for emergency service,
o
percentage of discretionary patrol time per shift and per year,
o
use of overtime to backfill minimum staffing slots due to personnel
o
vacancies or personnel who are on various types of leave.
ability to cover the absence of one shift worker without requiring
o
overtime; or
need to use budgeted overtime to cover staff vacancies when needed.
o
The monitoring program should be used to make adjustments to staffing levels that allow
patrol officers to use 40% of their time for discretionary patrol time on their various shifts
based on actual measured workloads.
• Pursue additional finances to fund additional personnel, equipment, and vehicles for the
ECPD.
• Obtain additional sworn personnel, non-sworn personnel, and vehicles to meet the
existing and future deficit of officers identified according to the workload monitoring
program.
• Continue to promote the volunteer officer program to aid in meeting staffing needs.
• When the ECPD is able to acquire additional personnel, the traffic enforcement unit will
be instated. This would allow the ECPD to acquire additional vehicles.
• Identify land in the northern portion of the City SOI for an additional station or substation
to accommodate anticipated development. Adequate staffing must be available in order to
open such a station.
• Identify land in the southern portion of the City SOI for an additional station or substation
to accommodate anticipated development. Adequate staffing must be available in order to
open such a station.
• Review existing development impact fees for ECPD services, identify necessary
improvement to the current fee structure, and implement revised fee structure.
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 56
IV. Financing
Current Funding
Funding for law enforcement is derived from many funding sources. They include the general
fund, developer fees, and grants. The General Fund is used to account for all revenues and
expenditures necessary to carry out the Police Department services. As part of the revenue, the
City receives Proposition 172 public safety tax revenue based on sales tax receipts, as well cost
recovery for judicial court appearances to provide testimony on cases. Revenue from user fees
charged by the ECPD is paid into the General Fund. Parking enforcement revenue is also
deposited for funding of police activities. Development impact fees required of development
projects generate revenue that is used for large-scale improvement and development projects
related to police facilities and services.
The ECPD received a grant in 2014 from the Department of Homeland Security to conduct
enforcement operations, and a grant from the Office of Traffic Safety to conduct additional DUI
enforcement. Other grant funding comes from the Department of Justice to conduct narcotics
enforcement. According to the Police Department, grant funding is not adequate to fully pay for
personnel expenditures related to the grant funds. Maintaining the city policy ratio of 1.75 sworn
officers per 1,000 capita remains a challenge due to factors such as competitiveness of retention
pay relative to other areas.
Cost Avoidance Opportunities
While the ECPD cooperates with the Imperial County Sheriff’s Department for the provision of
as-needed emergency backup services, the two agencies do not currently share any facilities and
would not share any facilities in the future. Although there are no substantial cost avoidance
opportunities for the ECPD, the department achieves cost savings through the leasing of
equipment including computers and phone system.
Non-sworn department staff is used where feasible in place of a sworn officer to conduct city
business to reduce personnel cost. The police and fire departments also plan to study a regional
dispatch center that can result in cost savings.
Further, school districts share the cost of School Resource Officers with the City.
Recommended Funding
The ECPD will continue to be funded by the General Fund, public safety grants and other
sources. The general fund remains a flexible funding source for both operations and maintenance,
and capital expenses. Expansion or additions to the existing inventory of facilities could be
funded through issuance of new bonds backed by the general fund to meet police service
protocol. Grants such as those identified above, if capacity permits it, can be procured for
specific operations while general fund and developer fees are available for capital facilities.
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 57
An update to the Cost Recovery Study could include new or revised user fees for services
performed by the ECPD. Increased user fees increase the revenues that are available for the
General Fund to carry out the Police Department services. The Police Department indicated the
potential to recoup the cost for restitution involving Driving Under the Influence (DUI). Parking
enforcement fees could also be updated through the Cost Recovery Study.
An update to the development impact fees study will bring such fees up to date and potentially
increase revenue for the City based on development patterns. Any increase in development
impact fees for ECPD service or facilities would increase funds available for large-scale
development and improvement projects.
The City also may consider the establishment of a community facilities district for the ECPD to
centralize funding for the Department and allow an efficient and effective means of financing
Department needs. Land based funding mechanisms such as Mello-Roos Community Facilities
Districts are possible for new development where there are few voters required to help fund
police infrastructure and/or police protection services.
The 2015-2016 Budget states the need for three major capital projects; a new library, new police
building and a new aquatic center. Approximately $8.5 million in funds has been reserved for the
construction of these new facilities; however, the priority of these projects will determine the
timing and phasing of design and construction. It is anticipated that the City will need to issue
bonds to pay for the design and construction of the new police building if the reserved funds are
not used.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as police facilities.
El Centro Service Area Plan Section 4.4 – Law Enforcement Facilities
February 2016 Page 58
4.5 Library Facilities
The City owns and operates the El Centro Public Library system. This system includes one main
library and one satellite facility that is open to the public and used by a broad spectrum of
community members. Services provided by the library include circulation of library materials
such as books, magazines and video and audio recordings; reference service; internet access;
word processing stations; copy machines; a publicly available conference room; children’s
reading programs; vocal, acting, and speaking workshops for children and adults; and tax
preparation assistance for senior citizens.
I. Performance Standard
The Local Agency Formation Commission (LAFCo) requires that the library facilities section of
the SAP maintain a performance standard measured in demand for square feet (sf). The
performance standard for the City is a range of is 300 to 600 sf of library facility space per 1,000
residents (0.30 to 0.50 sf of library facility space per capita). This standard is based on the
current total square footage of library facilities and population and is consistent with the
American Library Association’s (ALA) previous recommendation of 500 to 600 sf of library
space per 1,000 residents. The range provides the City the flexibility in addressing current and
future facility needs while considering changing demographics and increasing influence of
technology. It should be noted however, that the ALA no longer sets quantitative, prescriptive
standards for square footage and focuses instead on processes to develop outcome-based
measures for libraries based on each community’s needs.
The performance standard for number of volumes is a range of 2,500 to 2,750 per 1,000 residents
(2.5 to 2.75 volumes per capita).
The performance standard for the number of public access computer is 0.50 computers per 1,000
residents.
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
The City maintains the Main Branch of the El Centro Public Library, which is located at 1140 N.
Imperial Avenue in a former shopping center building with 13,600 sf leased by the City. The
original Main Branch of the public library was constructed in 1910, and will be demolished due
to the structural damage it incurred during the 2010 Easter Earthquake.
The library consists of approximately 213,762 volumes including books, magazines, and
audio/visual materials, and 24 public access computers for internet access or general word
processing uses, and 70 reader seats. The library employs a total of five full time permanent
positions and five temporary positions. There is one staff member who holds a Master’s Degree
in Library Science.
El Centro Service Area Plan Section 4.5 – Library Facilities
February 2016 Page 59
The satellite library is a room of 900 square feet located in the El Centro Community Center on
375 South First Street with a collection of 6,204 volumes and 6 computers.
Adequacy of Existing Facilities
The existing facility is considered an interim facility pending the completion of a needs
assessment study currently being undertaken. Completion of the study and start of the process for
deciding on the location and design of the new library is anticipated in the summer of 2016. The
estimated cost of a new library is $8.6 million. Although the current facility meets the
performance standards for square footage, number of volumes, and number of computers based
on the current population of 43,856, the interim facility lacks amenities that the original library
had such as community room space that was used for teen programs and special events.
Future Demand for Facilities
Increased development within the City boundaries and the SOI will present an increased demand
on the personnel, services, and facilities of the public library. This increased demand will be
thoroughly addressed in the needs assessment study. The original Main Branch was centrally
located in a high traffic area that was easily accessible to many City residents.
According to the Southern California Association of Governments (SCAG) the City’s population
is expected to increase from 43,856 to 55,100 residents by 2025. This growth will present the
need for additional space, volumes, and computers. To accommodate the projected population
and meet the library facilities performance standard, the City would need at least 16,500 sf of
total library facility square footage, 137,750 volumes, and 28 computers.
The City may consider the expansion and addition of branch libraries in order to increase service
as growth continues on the outskirts of the existing boundaries, placing new residents further
away from the existing facilities
Opportunities for Shared Facilities
Through inter-library loan programs, the library shares resources with other libraries in the
region. The public library will continue to pursue this opportunity for shared facilities in order to
keep costs low while providing acceptable services to City residents. The original main library
operated a publicly available conference room that was used for meetings and presentations
associated with the City administration.
Phasing
The 2015-2016 Budget states the need for three major capital projects; a new library, new police
building and a new aquatic center.
The new Main Branch of the City library is anticipated to still be centrally located. A Request
for Qualifications was released in early 2015 to solicit the preparation of a Needs Assessment
and Feasibility Study for a new El Centro Public Library Facility. The Study will assist the City
in deciding the future location, design and timing for the construction of the new facility. The
El Centro Service Area Plan Section 4.5 – Library Facilities
February 2016 Page 60
new facility is expected to be designed to accommodate the population growth until at least
2025, and potentially to meet the needs for the estimated 2040 population.
As development continues in the outskirts of the existing City boundaries and within the City’s
SOI, the City will need to develop one or more additional branches that would accommodate
residents of the outlying area. In conformance with Public Facilities Element Policy 3.1, any
additional branches would be located near major activity centers such as retail areas to provide
the most convenient accessibility to the most residents.
III. Mitigation
In order for the City to provide its residents adequate library services and to assure that the
library system is sufficiently expanded to accommodate growth within the City and the
boundaries of the SOI, the City will implement the following measures.
• Continue to periodically review the facilities and personnel of the El Centro Public
Library system through the preparation of annual reports. Such review will identify
staffing and budgetary concerns as City growth continues to increase the demand on
library facilities and staff. Such review should also involve research and coordination
with organizations such as the American Library Association, who have numerous
resources and guidelines on the library facility, staff, the library’s collection, and
technology.
• Continue to utilize General Fund revenue as the primary source of financing for the El
Centro Public Library System. Review the allocation of General Fund finances in light of
State recommendation that local libraries receive five percent of local general fund
resources.
• Continue to apply for all possible library funding opportunities from the State.
• Re-apply for certification in the State Public Library Fund (PLF) program when funds are
allocated by the State.
• Review existing development impact fees for library services, identify necessary
improvement to the current fee structure, and implement revised fee structure.
• Continue to accept donations of money and supplies as a means of augmenting library
services while conserving allocated finances.
IV. Financing
Current Funding
The General Fund is used to account for all revenues and expenditures necessary to carry out the
El Centro Service Area Plan Section 4.5 – Library Facilities
February 2016 Page 61
Library services. Development impact fees are levied for library facilities. Revenue generated by
development impact fees are not placed in the General Fund, but are used for specific library
improvement projects.
The library also accepts private donations material and funding grants to offset the costs of
operation and to implement improvement projects.
Cost Avoidance Opportunities
The current library is housed in an interim facility since the original library was destroyed in the
2010 Easter Earthquake. The original El Centro Public Library contained a conference room that
was used for meetings and community space and meeting space could be incorporated into the
new library that could be rented out and help generate revenue for the library.
Through inter-library loan programs, the library shares resources with other libraries in the
region which keep costs low while providing acceptable services to City residents.
The El Centro Public Library offers Zip Books. Zip Books is a new patron-driven model for
securing the books a customer wants to read. For speed and cost-efficiency, the patron’s request
is delivered by Amazon directly to their home mailing address. When finished reading the item,
the patron returns it to the library. The library also offers e-book service for customers to
download digital copies of reading materials.
Recommended Funding
The General Fund will continue to cover the expenditures necessary to carry out the Library
services. The library will continue to apply for all possible funding opportunities from the State,
and will continue to accept donations of money or materials.
An update to the Cost Recovery Study could recommend improvements to the library user fee
structure. Updating the relevant user fees will provide increased revenue for the General Fund
that could be used for improvements and expansion of library facilities.
An update to the development impact fees study will bring such fees up to date and increase
revenue for the City. Any increase in development impact fees for library facilities would
increase funds available for large-scale development and improvement projects related to library
facilities and services. The City has established a Library Task Force in partnership with the
Library Board to develop and implement a plan for new permanent library.
The 2015-2016 Budget states the need for three major capital projects; a new library, new police
building and a new aquatic center. Approximately $8.5 million in funds has been reserved for the
construction of these new facilities; however, the priority of these projects will determine the
timing and phasing of design and construction. It is anticipated that the City will need to issue
bonds to pay for the design and construction of the new library building if the reserved funds are
not used. The original main library contained a public conference room and such a space could
be included in the design of the new library and rented out for special events in order to generate
El Centro Service Area Plan Section 4.5 – Library Facilities
February 2016 Page 62
additional revenue.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as libraries.
El Centro Service Area Plan Section 4.5 – Library Facilities
February 2016 Page 63
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4.5 – Library Facilities
February 2016 Page 64
4.6 Parks and Recreation Facilities
The City provides parks and recreation facilities to the public within its boundaries. Park
facilities are typically provided by developers of residential property in accordance with Section
24, Article V of the City of El Centro Code of Ordinances. This ordinance was established in
accordance with Section 66477 of the California Government Code (commonly known as the
Quimby Act), which provides local jurisdictions throughout the State with the authority to
establish provisions for the acquisition of parkland in association with new development.
Payment of a park development fee is often accepted in lieu of land dedication. The acreage of
land required for dedication or amount of park development fee is determined by the density of
residential development dictated by the residential zoning designation applied to the site.
The Community Services Department (CSD) is responsible for overseeing City park facilities
and services. Parks within the City jurisdiction are used by the public for various recreational
activities, and include such amenities as athletic fields, hard court playgrounds, open space areas,
picnic areas, swimming facilities, gymnasia, and skateboard facilities. City parks often contain
restrooms and irrigation systems that are maintained by the Department.
In addition to operation and maintenance of facilities, CSD sponsors many youth and adult
recreational programs at the City’s park facilities. Existing programs include swimming lessons,
day camps, and various educational and recreational activities offered at the community centers.
Programs sponsored by the Department are offered to the public and often entail a participation
fee to help pay for expenses.
I. Performance Standard
The Public Facilities Element of the General Plan presents a parkland goal for City parks and
recreational facilities of five acres of developed public parkland per 1,000 residents. The policies
of the Public Facilities Element also present goals to provide facilities within a one-half mile
distance of all residential areas, expand existing facilities to meet Statewide and City standards,
orient facilities toward special ethnic and age groups within the City and efficiently maintain the
facilities.
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
The current inventory of park and recreation facilities includes parks, recreation, community
center facilities, and school facilities that are available for limited public recreation use.
Stormwater retention basins are not counted in parkland acreage. School recreation facilities with
which the City has joint-use agreements for limited public use are counted at 25% of the
developed recreational acreage. There are currently a total of approximately 154.62 acres of
developed parkland, in the 18 parks, 7 recreation and community center facilities and 14 school
recreation facilities within the City’s jurisdiction. The following list presents the names, acreages
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 65
and building areas of the City’s park and recreation facilities, as shown in the General Plan
Public Services Element and further described in the City of El Centro Parks & Recreation
Facilities Master Plan (2008).
Table 4.6-1 Park Facilities and Acreage
RETENTION
PARK
PARK BASIN
ACREAGE
ACREAGE
Adams Park 9.33 0.0
Bucklin Park 20.0 0.0
Buena Vista Park 0.0 8.0
Carlos Aguilar Park 4.75 0.0
Countryside Park 2.0 5.9
Debbie Pitman Park 4.73 0.0
Desert Village Park 0.0 3.5
Farmer’s Park 1.29 0.0
Frazier Field 3.55 0.0
Gomez Park 2.66 0.0
Leeper Park 3.71 3.7
Legacy Ranch Memorial Plaza 1.5 0.0
Lotus Park 3.85 3.9
McGee Park 5.31 0.0
Stark Field 11.44 0.0
Sunflower Park 13.0 0.0
Swarthout Field 15.49 0.0
Town Square 0.5 0.0
Wildflower Park 0.0 3.96
Subtotal 103.11 28.96
Table 4.6-2 Recreation and Community Center Facilities and Acreage
RECREATION & COMMUNITY FACILITY FACILITY SQ.
CENTER FACILITY ACREAGE FT
Dr. Martin Luther King Jr. Sports
2.35 22,950
Pavilion
Conrad Harrison Youth Center 0.68 11,000
El Centro Adult Center 0.2 4,173
El Centro Community Center 2.5 8,450
Sidewinder Skate Park 2.24 24,000
Martin Luther King Jr. Sport
0.67 29,200
Complex
Old Post Office Pavilion 0.23 10,000
Subtotal 8.87 109,773
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 66
Table 4.6-3 School Recreation Facilities and Acreage
FACILITY
FACILITY
SCHOOL RECREATION ACREAGE
ACREAGE
FACILITY NOT
AVAILABLE
AVAILABLE
Central Union High School 17.5 0.0
De Anza Elementary School 14.7 0.0
Desert Garden
13.3 0.0
Elementary School
Harding School 8.1 0.0
Hedrick Elementary 10.9 0.0
Kennedy Elementary/Middle School 16.7 0.0
King Elementary School 0.0 12.2
Lincoln School 7.7 0.0
McKinley School 10.9 0.0
Southwest High School 16.5 0.0
Sunflower Elementary School &
0.0 4.2
Field
Sunflower Park 16.7 0.0
Wilson Jr. High School 14.4 0.0
Washington Elementary School 9.4 0.0
subtotal 156.8 16.4
25% joint-use 39.2 4.1
TOTAL 154.62
To administer and maintain the parks system, CSD currently employs nine full time staff
members. Approximately 30 temporary staff members work for the department to offer
recreational activities at various times throughout the year. The administrative offices of CSD are
located at 1249 W. Main Street. CSD contracts with private companies for some maintenance
work in City parks.
Adequacy of Existing Facilities
Applying the parkland goal of 5 acres per 1,000 population, the City’s current population of
43,856 would require a parkland area of 219.28 acres, which exceeds the existing parkland
acreage of 103.11. Thus, the City operates with a parkland deficit of approximately 116.17 acres.
The deficit was calculated as follows:
43,856 existing residents x 5.0 acres / 1,000 population = 219.3 acres
103.11 existing acres – 219.3 demand acres = 116.17 deficit acres
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 67
Future Demand for Facilities
The City currently operates at a deficit of parkland within its jurisdiction. In addition to the
parkland required to meet current demands, future growth of the City will require acquisition of
additional parkland to meet its performance standard. The projected 2025 population of 53,176
residents would necessitate 265.88 acres or 162.77 additional acres of public parkland than
currently exists in the City’s jurisdiction.
Parkland is generally provided by developers as part of large residential or commercial
developments within the City, and it is anticipated that this future demand would be met by such
provision. CSD will also require funding throughout the planning period for maintenance and
administration of the facilities and the various programs offered by the department. Demand for
such funding will increase as additional parkland is developed and as existing parks experience
increased utilization as a result of population growth within the City.
Opportunities for Shared Facilities
The City currently maintains joint-use agreements with the local school districts for the use and
maintenance of athletic field and park facilities associated with most of the schools in these
districts. Such joint-use parks are available to students of these districts and City residents alike.
Whenever possible, CSD will maintain such existing relationships and will pursue similar
relationships with these districts and other jurisdictions.
Phasing
Table 4.6-4 below presents a breakdown of parkland demand phasing over the SAP planning
period.
Table 4.6-4 Parkland Demand
Year Population Total Demand Difference
2015 43,856 219.3 acres 116.17 (deficit)
2020 53,176 265.9 acres 162.79 (deficit)
2025 55,100 275.5 acres 172.39 (deficit)
To catch up to the existing parkland demand and to accommodate the anticipated population
increase, the City will continue to require that new development include provision of additional
public parks and recreational facilities to the maximum extent allowed by law, in accordance
with Public Facilities Policy 1.2 of the General Plan. When developments are approved and
processed within the City, particular attention should be paid to this policy and to Section 24,
Article V of the City of El Centro Code of Ordinances in light of the fact that the City currently
operates at a deficit of public parkland. Provision of adequate parkland meeting the City’s
existing and future demand will require strict adherence to these parkland provision
requirements.
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 68
The El Centro Park and Recreation Facilities Master Plan identified seven park and recreation
facilities that are pending completion:
Table 4.6-5 Planned Facilities
Facility Facility Acreage Status
Aquatic Center 2.24 Under design
Athletic Sports Complex 40-60 Incomplete
(Tournament Quality)
Toddler Center TBD Incomplete
Environmental Education Facility TBD Incomplete
Adventure Playground
Cultural and Performing Arts Center TBD Incomplete
Discovery Center for TBD Incomplete
Dog Park TBD Incomplete
Trails and Connectivity In progress
III. Mitigation
In order for the City to provide to its residents adequate parkland that is efficiently managed and
maintained as growth continues within the City and within the boundaries of the SOI, the City
will implement the following measures:
• Continue to require the provision of parkland or the payment of a park development fee,
in accordance with Section 24, Article V of the City of El Centro Code of Ordinances. In
light of the current deficit of public parkland, particular attention should be paid to this
requirement when developments are processed within the City. Provision of adequate
parkland meeting the City’s existing and future demand will require strict adherence to
these parkland provision requirements.
• Apply for grant funding from both public and private sources.
• Offset operation costs by charging used fees where appropriate.
• Continue to periodically review the performance of CSD through the preparation of
annual reports. Such review will identify staffing and budgetary concerns as the amount
of City parkland continues to grow.
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 69
• Review existing development impact fees for CSD services, identify necessary
improvement to the current fee structure, and implement revised fee structure.
IV. Financing
Current Funding
The City receives funding for parks and recreation facilities including from the general fund,
development impact fees, user fee charges, fundraisers and donations, and regional, state and
federal grants. Proposition 84 (The Safe Drinking Water, Water Quality and Supply, Flood
Control, River and Coastal Protection Bond Act of 2006) funds were used to build a skate park.
Maintenance fees for landscaping improvements along street rights-of-way are also collected
from the Legacy Ranch Landscape and Lighting Maintenance District (LLMD), as well as from
the Buena Vista LLMD. The LLMD was created for maintenance and improvements for assets
including drainage, sidewalks, and medians. In the case of Legacy Ranch, the LLMD can be
used for park maintenance of the open space dedicated to the city by the developer. Maintenance
includes landscaping, open grass field, playground equipment, and structural amenities like a
covered picnic area and furnishings.
On December 11, 2014, El Centro celebrated with an official Grand Opening and Ribbon Cutting
Ceremony for the new Dr. Marin Luther King, Jr. Sports Pavilion. The new multi-sports complex
cost $6.6 million to complete. Funding was provided by a Redevelopment Agency Bond of $4.6
million, Community Development Block Grant Entitlement of $970,000, Community
Development Block Grant Program Income of $664,728, Parks and Recreation Impact Fees of
$320,230, and a donation from Rabobank for $25,000.
Cost Avoidance Opportunities
The City currently maintains joint-use agreements with the local school districts for the use and
maintenance of athletic field and park facilities associated with most of the schools in these
districts. These joint-use agreements save the City some of the operations and maintenance costs.
City policy requiring private developers to dedicate parkland and construct parks in conjunction
with development projects eliminates substantial cost to the City for undertaking the purchase or
dedication of land or the construction costs. The City will continue this cost avoidance measure.
Recommended Funding
The General Fund will continue to cover the expenditures necessary to carry out the Parks and
Recreation services. To reduce the current parkland deficit and to accommodate the anticipated
population increase, the City will continue to require that new development include provision of
additional public parks and recreational facilities to the maximum extent, in accordance with
Public Facilities Policy 1.2.
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 70
An update to the Cost Recovery Study could include new or revised user fees for services
performed by the Parks & Recreation Department. Increased user fees would increase
department contribution to the General Fund. Updating the relevant user fees will provide
increased revenue for the General Fund that could be used for improvements and expansion of
parks and recreation facilities.
An update to the development impact fees study will bring such fees up to date and increase
revenue for the City. Any increase in development impact fees for parks and recreation facilities
would increase funds available for large-scale development and improvement projects related to
parks and recreation. Development of a Capital Improvement Program for parks will provide
guidance for the capital projects that will be needed, their timing of implementation, and the
possible funding sources and mechanisms.
Land based funding mechanisms such as Mello-Roos Community Facilities Districts are possible
for new development where there are few voters required to help fund park facilities and/or
maintenance of parks, parkways and open space.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as parks and child care facilities.
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 71
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 72
Aguilar
Park Frazier
Field
!
!
Swarthout
Park
Sunflower
Park
Lotus McGee
Park Park
Pitman
Park
Stark
Field Gomez
Park
Lotus
Park
Bucklin
Park
Farmer's
Park
Countryside
Park
Legacy
Park
!
Legend
City of El Centro
Sphere of Influence
Elemen
K
ta
in
r
g
y McKinley
School Elementary
School Parks and Recreational Facilities Imagine Kennedy
School ! Middle School ")
C Community Center
MLK. Jr.
Sunflower Skate
Sports
Elementary Park
Pavilion
School Park
! ! Washington
Lincoln Adams Park Elementary Schools
! Elementary School
School
Town
Ballington Square Sports Facility
Academy ! Central Union
High School
! Community
Harding Center
Hendrick ! ! Elementary
Elementary
School School
Wilson Jr.
St. Mary's High School
School
Desert
De Anza Oasis High
Elementary School
School
Desert Gardens
Southwest Elementary
High School School
Source: City of El Centro, 2015
ESRI World Imagery Basemap (Microsoft, 2011)
dxm.seitilicaF&kraP_1-6.4_46471\SIG
,otohP
etiS
,noitcelloC
ataD\PAS
ortneC
lE
46471\gninnalP\:N
[
Miles
Parks and Recreational Facilities Map
0 0.5 1 North Figure 4.6-1
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4.6 – Parks and Recreation Facilities
February 2016 Page 74
4.7 Transportation Facilities
The City is responsible for the development and maintenance of a system of public roadways and
bicycle routes within their jurisdiction. The City’s transportation system links to those of the
State and the County, as facilities of these other jurisdictions traverse the City. Development of
new roads or improvement of existing roads is often accomplished by private developers when
physical improvement of the City’s circulation system is deemed necessary due to anticipated
increases in traffic from various development projects.
The General Plan includes a Circulation Element that discloses the City’s goals, policies, and
performance criteria with respect to the circulation system, that presents the minimum design
standards for City streets, and that provides a Circulation Plan that shows the anticipated
development of the system as growth occurs within the City.
I. Performance Standard
The Circulation Element of the General Plan identifies performance criteria for the various types
of roadways found in the local system. The criteria, which are summarized below in Table 4.7-1,
are based on the graded scale “level of service” (LOS) classification system. The LOS system
quantifies the effective operation of a particular roadway by determining the average daily traffic
(ADT) capacity and how changes in ADT affect roadway service. LOS A represents effective
service with little traffic congestion, while LOS F represents ineffective service with a great deal
of traffic congestion.
The Circulation Policy 1.3 states the City’s goal of maintaining a performance standard of LOS
C for all roadways in the local circulation system. If a development project is anticipated to
present traffic conditions in excess of this threshold, the project would be required to implement
physical improvements that would address project-related traffic impacts to the circulation
system.
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 75
Table 4.7-1 Circulation System Performance Criteria
Roadway
Class Lanes LOS A LOS B LOS C LOS D LOS E LOS F
30,001- 40,001- 50,001- 60,001- >
Freeway* 4 < 30,000 40,000 50,000 60,000 70,000 70,000
Primary 14,801- 24,701- 29,601- 33,401- >
Arterial* 4 < 14,800 24,700 29,600 33,400 37,000 37,000
Secondary 13,701- 22,801- 27,401- 30,801- >
Arterial 4 < 13,700 22,800 27,400 30,800 34,200 34,200
Two-lane 2,001- 4,501- 7,701- 11,801- >
Arterial 2 < 2,000 4,500 7,700 11,800 17,500 17,500
1,901- 4,101- 7,101- 10,901- >
Collector 2 < 1,900 4,100 7,100 10,900 16,200 16,200
Residential
Street 2 * * 1,500 * * *
Residential or
Cul-de-Sac
2 * * 200 * * *
Loop Street
* Freeways and certain primary arterials identified in the Circulation Element are not facilities of
the City.
** LOS is not applied to residential streets since their primary purpose is to serve abutting lots, not carry through traffic. The
number for residential streets is a generally accepted ADT threshold for LOS C operation.
In September 2013, the California state legislature adopted SB 743, which requires the
development of an alternative transportation metric other than Level of Service (LOS). LOS,
which is typically based upon vehicle delays at intersections during peak travel periods, is the
standard transportation metric used in the Circulation Element. The alternative transportation
metrics are intended to promote the reduction of greenhouse gas emissions, the development of
multimodal transportation networks, and a diversity of land uses. Vehicle Miles Traveled (VMT)
is an alternative that other jurisdictions are using in response to SB 743 that is based on the
number of additional trips the development is anticipated to generate.
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
The circulation system within the City is oriented in a north/south and east/west grid system. The
major circulation facilities located within City limits include one freeway and several highways
that are operated by the State through the Department of Transportation (Caltrans).
The State facilities traversing the City are Interstate 8 and State Route 86. State Route 111 is
outside of the City limits, but currently serves as the eastern boundary of the City’s SOI.
Interstate 8 is independent of City streets but includes on-ramps and off-ramps at Imperial
Avenue, 4th Street, and Dogwood Avenue. Unlike Interstate 8, the State Routes within the City
boundaries are intertwined with the grid of City-operated roadways. While the City is not
responsible for maintaining these State roadways, upkeep and adequate circulation on such
facilities affects traffic throughout the City-operated system.
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 76
City-operated roadway facilities include principal arterials, secondary arterials, two-lane
arterials, collector streets, residential streets, and alleys. Principal and secondary arterials are
typically four-lane roadways, with principal arterials having wider dimensions and the ability to
accommodate more trips than secondary arterials. Two-lane arterials can be principal or
secondary arterials that have only two lanes rather than the designed four lanes. Residential lots
do not usually have direct access onto City-maintained arterials. Collector roads include
residential streets, residential loop streets, and cul-de-sacs. Collectors are usually two-lane roads
that are smaller than arterials. Their primary purpose is to collect and distribute traffic to and
from major highways and larger local streets. Residential streets and alleys provide direct access
to property by local traffic, and are not meant to serve through traffic. At one time, alleys were
required within all residential, commercial, and industrial development in the City. This is no
longer the case, but the City plans to maintain the existing alley network.
The City operates and maintains signalized and unsignalized intersections that control the flow
of traffic.
Adequacy of Existing Facilities
The City utilizes cumulative traffic analysis through the environmental review process for
proposed large-scale development projects to assess the existing and long-term impacts to
circulation facilities. The existing circulation system is adequate to accommodate the current
needs of the City in that paved roadways properly link existing residential, commercial, and
industrial development.
As discussed in detail as follows, the City has determined the need to implement circulation
system improvements in the El Dorado Colonia area. This would accommodate anticipated
development. In addition to this improvement project under consideration, extension of
roadways and creation of additional roadways will be needed as development continues to occur
within the City limits and SOI boundaries.
Future Demand for Facilities
As residential, commercial, and industrial development continues within the City boundaries and
SOI, the City will need to continue to upgrade and improve existing roadways and create new
roadways in order to maintain a service level that is in keeping with the goals established in the
General Plan. Streets required to serve new development are typically provided by the
developers as the project is constructed. The City has reviewed anticipated demands of increased
traffic according to the three development tiers and has created the Circulation Master Plan.
In addition to the Circulation Master Plan that is designed to accommodate the build-out traffic
within the development tiers, the Circulation Element of the General Plan includes a specific
roadway improvement program that the City identified for implementation. This project, which
is detailed below, is a large-scale improvement that would be undertaken by the City to meet its
goals of providing safe and efficient transportation facilities. The City has also approved specific
capital improvement projects, which are listed below under the “Phasing” heading in this section.
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 77
El Dorado Colonia Circulation System:
The General Plan Land Use Element identifies El Dorado Colonia as an area that would benefit
from redevelopment. This area is listed as a Tier 1 Growth Area slated for Low Density
Residential development. The Colonia is currently bisected by the east/west streets of El Dorado
Avenue and Pico Avenue and the north/south streets of 12th Street and 8th Street. In order for
development to occur within this area, a street system connecting to the surrounding grid system
needs to be improved. The Circulation Element shows a plan to improve five east/west
residential streets and one north/south street through the colonia to serve future residences. This
project is multi-phased.
Opportunities for Shared Facilities
While there are no real opportunities to share roadway facilities with any adjacent jurisdiction,
the City’s system does not exist independently, and circulation within and through the City is
mutually affected by the operation of the State and County circulation system. In order to
maintain the best possible circulation within City limits, throughout the SOI, and within the
County and the greater region as a whole, the City will continue to cooperate with the State, the
County, and adjacent cities in monitoring the operation of the regional system and the
implementation of necessary improvements. In accordance with General Plan policy, the City
will also continue to cooperate with the Imperial County Transportation Commission to ensure
that adequate bus service is available for all segments of the community.
Phasing
Improvement of the City’s circulation system will occur as needed in concurrence with
development. The City will continue to require of developers the necessary roadway and
intersection improvements to account for project-related trips and congestion. Necessary
roadway infrastructure would be installed prior to the completion of development projects.
The following list includes transportation projects that have been identified as capital
improvements to improve circulation and accommodate growth within the City.
1. El Dorado Colonia Street Improvement: Install off-site improvements to the El Dorado
Colonia, including installation of curbs and gutters, creation of asphalt right-of-ways, and
relocation of utilities.
2. Eastern Extension of Bradshaw Avenue: Extend Bradshaw Avenue between 12th Street and
8th Street.
3. Roadway Repaving and Enhancement: Slurry and overlay several unspecified roadways
within the City.
4. Interstate 8 and Imperial Avenue Interchange: Design and construct bridge improvements at
the interchange to allow for development of Imperial Avenue south of Interstate 8.
5. Extension of Imperial Avenue South to McCabe: Design and construct the extension of
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 78
Imperial Avenue south of Interstate 8 to McCabe Road.
6. Dogwood Avenue Bridge Improvements: Construction to widen the Dogwood Avenue
overpass of Interstate 8 to four lanes is currently underway.
7. Disabled Access Ramps: Repair, replace, and install disabled access ramps at unspecified
curb and intersection locations throughout the City.
8. La Brucherie Avenue Roadway Widening: Widen La Brucherie Avenue from Adams
Avenue to Orange Avenue.
9. Ross Avenue Roadway Widening: Acquire right-of-way and widen Ross Avenue between 1st
and 3rd Street and align the railroad crossing with Ross Avenue.
10. Wake Avenue Extension: Engineer, design, acquire right-of-way, and construct Wake
Avenue between 12th Street and La Brucherie Avenue.
11. Undergrounding of North Date Canal: Underground the North Date Canal along Villa
Avenue from 17th Street to 8th Street.
12. Traffic Signs: Install signs for street names, radar feedback, and directional indicators at
unspecified locations throughout the City.
13. 8th Street Bridge Renovation: Design, engineer, and construct improvements to the 8th Street
overpass bridge over Interstate 8 to widen from the current 2 lanes to 4 lanes.
III. Mitigation
In order for the City to maintain adequate circulation and provide roadways that are sound and
efficient, the City will implement the following measures.
• Implement identified circulation system projects to improve circulation and
accommodate growth within the City.
• Continue to periodically review the list of approved roadway capital improvement
projects slated for implementation by the City to determine project status, need for
revision of the program schedule, and budgetary needs.
• Review the existing development impact fees schedule for circulation and roadway
projects, identify necessary improvement to the current fee structure, and implement
revised fee structure.
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 79
IV. Financing
Current Funding
The General Fund is used to account for all revenues and expenditures necessary to carry out the
Street & Maintenance services. Funding sources include development impact fees, local
transportation authority, and the State gas tax. The gas tax is used for roadway maintenance and
improvement and is allocated to local jurisdictions based on formulas that account primarily for
population. The Imperial County Transportation Commission (ICTC) allocates Article 3 revenue
from the Transportation Development Act (TDA) to each local jurisdiction in the County for
non-motorized transportation such as bicycle and pedestrian projects. Street and road funding
from TDA is not provided.
The Imperial County Local Transportation Authority administers the local transportation sale tax
(Measure D) that provides street and road funding for maintenance and capital improvement.
LTA revenues bonds were issued for street related expenditures. Traffic fines and forfeitures are
collected by the City for traffic control supplies and equipment. Capital roadway projects are
funded from state transportation improvement program (STIP) revenue that are programmed by
ICTC and submitted to the California Transportation Commission. STIP revenue is comprised of
state and federal highway revenue sources and projects that receive funding are voted upon by
the CTC. Many of these projects are tied to highway capacity, highway intersections and related
projects.
Landscape and Lighting Maintenance Districts (LLMDs) are created for maintenance and
improvements for assets including drainage, sidewalks, and median walkways. The City has two
existing LLMDs created for Legacy Ranch and Buena Vista developments. The Legacy Ranch
development also created a Mello-Roos Community Facilities District NO. 2007-1 to issue
bonds for the purpose of financing certain public improvements (streets, sewers, storm drains).
Cost Avoidance Opportunities
While there are no real opportunities to share roadway facilities with any adjacent jurisdiction,
the City’s system does not exist independently, and circulation within and through the City is
mutually affected by the operation of the State and County circulation system. In order to
maintain the best possible circulation within City limits, throughout the SOI, and within the
County and the greater region as a whole, the City will continue to cooperate with the State, the
County, and adjacent cities in monitoring the operation of the regional system and the
implementation of necessary improvements. In accordance with General Plan policy, the City
will also continue to cooperate with the Imperial County Transportation Commission to ensure
that adequate public transportation service is available for all segments of the community.
Application to State and federal programs to receive funding for circulation and roadway
projects also provides a significant opportunity to avoid direct cost to the City for large-scale
development and improvement projects.
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 80
Recommended Funding
Growth in core transportation funding sources for future transportation projects are closely
linked to economic growth. Economic stability and growth highly influence revenue sources
such as the gas tax, Transportation Development Act Article 3, Measure D transportation funds,
development impact fees, and State transportation revenue. Active Transportation Program
(ATP) funds from Caltrans could be available for pedestrian and bicycle projects. The City’s
ability to leverage local sources for additional State and Federal funds improves its ability to
fund additional facilities.
An update to the development impact fees study will bring such fees up to date and increase
revenue for the City. Any increase in development impact fees for transportation facilities would
increase funds available for large-scale development and improvement projects.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including transportation facilities such as roads and
highways, bridges, parking facilities, transit stations, and transit oriented development projects.
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 81
This Page Intentionally Left Blank.
El Centro Service Area Plan Section 4.7 – Transportation Facilities
February 2016 Page 82
4.8 Wastewater Facilities
The City owns, operates, and maintains a system of approximately 120 miles of wastewater
collection pipelines, pump stations, and treatment facilities that serves approximately 8,000
residences, businesses, and public facilities within the City and the City SOI. Facilities within
this system are developed and maintained by the Department of Public Works. The City
budgeted an update to the Sewer Master Plan with a goal for adopting the update by 2016.
I. Performance Standard
In general, the City’s goal in the operation and maintenance of its wastewater facilities is to
provide adequate service to every customer. The City utilizes several engineering criteria to
determine the adequacy of existing wastewater facilities and the need for improvements to the
system. These criteria consider the accommodation of flow volume and velocity, lift station
capacity, and technical specifications that assure a properly designed system.
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
The City wastewater facilities include a collection of over 125 miles of sewer lines and pipelines
that carry wastewater from residences and businesses to the Wastewater Treatment Plant located
in the northern portion of the City along La Brucherie Avenue between the Central Drain and
Cruickshank Drive. Treated water is carried east and discharges into the New River. The City
operates 13 pump stations within the collection system, including a station at the treatment
facility and the Orange Avenue Regional Lift Station.
The City’s Wastewater Treatment Plant (WWTP) is a conventional primary/secondary plant
followed by disinfection by ultraviolet (UV) irradiation. The original plant consisted of primary
clarifiers followed by ponds. An activated sludge process replaced the ponds in 1972. The
aeration basins have been further modified to replace mechanical turbine aeration with fine
bubble aeration. The plant was originally constructed with a chlorine contact basin for
disinfection. The chlorination system has since been removed and replaced with UV facilities.
The rated capacity of the plant is 8.0 million gallons per day (mgd). This flow is for any 30-day
reporting period. The maximum month flow in 2014 was 3.3 mgd. The average annual flow for
this same period was 3.1 mgd. The treated wastewater is discharged to the Central Main Drain,
which ultimately discharges into the Salton Sea.
The City maintains an agreement with the County that limits the acreage of development south
of I-8 that would contribute flow to the gravity pipeline along La Brucherie Avenue to 900 acres.
El Centro Service Area Plan Section 4.8 – Wastewater Facilities
February 2016 Page 83
Adequacy of Existing Facilities
The Wastewater Treatment Plant (WWTP) has the capacity to accommodate eight million
gallons per day (mgd). Current generation from City wastewater customers averages
approximately 3.40 mgd, and existing peak flow is approximately six mgd. The WWTP
consistently meets Secondary Treatment standards and has adequate capacity to handle existing
flows, and because the facility is operating at approximately 50 percent capacity, no expansions
to accommodate additional capacity are planned.
Future Demand for Facilities
The WWTP and delivery system will meet demand of growth for the next ten years. Planning
must begin for the next expansion when the monthly flow reaches 6.4 mgd, or 80 percent of the
plant’s capacity of the 8.0 mgd. Planned improvements to expand the WWTP and delivery
system will be considered during the anticipated 2016 update of the Sewer Master Plan.
Low density housing that is planned to surround the City and minor industrial and commercial
developments within the eastern portion of the City SOI will present additional demand on the
City’s wastewater system.
The La Brucherie trunk sewer line has adequate capacity to serve future development in the
southwestern portion of the service area. Other trunk sewers generally do not have available
capacity to serve future development outside of the existing service area and improvements will
be made on a project-by-project basis by developers. Capital Improvement Projects (CIP) are
being constructed by the City.
It is anticipated that provision of wastewater collection to the ultimate service area will require
additional treatment capacity and extension of the wastewater collection and transmission
system. The existing wastewater treatment plant is anticipated to be adequate treatment capacity
for future demand.
In addition, all new development that occurs outside of the existing wastewater service area will
require the developer to provide expanded wastewater services, primarily trunk sewers.
Opportunities for Shared Facilities
The City does not share wastewater treatment, storage, or distribution facilities with other
jurisdictions, and there is no opportunity to share such facilities.
Phasing
All of the proposed improvements would be conducted within the City’s SOI boundaries. The
proposed location of the lift station is within the boundaries of the City. Portions of the proposed
pipeline are within the City boundaries and portions are outside the City boundaries.
El Centro Service Area Plan Section 4.8 – Wastewater Facilities
February 2016 Page 84
III. Mitigation
In order for the City to assure adequate service to its wastewater customers as development
continues within the City boundaries and within the SOI, the City will implement the following
measures:
• Implement improvement projects recommended in the Sewer Master Plan as funds
become available.
• Implement wastewater system improvement projects identified in the City’s budget and
capital improvement project program.
Continue to periodically review the wastewater rate and financing structure to assure adequate
funding for the implementation of new projects and the maintenance of existing facilities.
IV. Financing
Current Funding
Dynamic Consulting Engineers prepared a Water, Wastewater and Storm Water Rate Study
Update in 2012 that determined the adequacy of the existing rate structure charged to City
customers for wastewater service and recommended rate changes and other revenue sources to
pay for wastewater facilities.
The City’s wastewater funds are operated as business enterprises with revenue generated through
monthly service charges that fund wastewater projects and maintenance. Revenue accrued by
such billing is placed in the Wastewater Fund to help finance personnel, maintenance, and
improvements.
Operations, maintenance, salaries, and equipment purchases are funded by the City’s Wastewater
Enterprise Fund. This fund is used to account for revenues and expenses associated with the
collection and treatment of wastewater. Enterprise funds are used to account for operations that
are financed and operated in a manner similar to private business enterprises. The City receives
money in this fund by charging connection fees and maintenance fees to its wastewater
customers.
The Wastewater Enterprise Fund is separate from the Wastewater Capacity Fee Fund and is not
used to finance the engineering or construction of major improvement projects. The City receives
money for the Wastewater Capacity Fee Fund used for major improvement projects by charging
wastewater capacity fees for development projects and by receiving interest earned from such
fees.
The Wastewater Stabilization fund receives excess revenues from the Wastewater Enterprise
Fund. Monies deposited into this fund can be withdrawn to assist the City in covering its income
to debt service ratios.
El Centro Service Area Plan Section 4.8 – Wastewater Facilities
February 2016 Page 85
The Legacy Ranch development also created a Mello-Roos Community Facilities District NO.
2007-1 to issue bonds for the purpose of financing certain public improvements (streets, sewers,
storm drains).
Cost Avoidance Opportunities
The City often requires developers to construct wastewater-related infrastructure that will
connect the specific development with the existing City wastewater system. This requirement
helps the City avoid substantial costs associated with infrastructure development.
Recommended Funding
The City will continue to use the existing financing mechanisms described above to finance the
City’s wastewater engineering, construction, operation, and maintenance. Bond measures may
continue to be required to finance the large-scale improvements recommended within the full
buildout timeframe. The City recently issued a large revenue bond that is backed by customer
charges. Current funding sources, especially customer fees, will remain the largest source for
wastewater treatment and sewer facility maintenance, improvements, and possible expansions.
An updated wastewater study will be conducted that will identify funding sources to pay for the
recommended improvements to the wastewater facility. Also, an update to the development
impact fees study will bring such fees up to date and potentially increase revenue for the City
based on development patterns. Any increase in development impact fees for wastewater
facilities would increase funds available for large-scale development and improvement projects.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as sewage facilities.
El Centro Service Area Plan Section 4.8 – Wastewater Facilities
February 2016 Page 86
4.9 Water Facilities
The following section of the SAP contains information published in the Water Master Plan
prepared by Carrollo Engineers in February 2008; and the Water, Wastewater and Storm Water
Rate Study Update from 2012 prepared by Dynamic Consulting Engineers, Inc. The City budget
includes funds for an update to the Water Master Plan and expects adoption by 2016.
The City owns, operates, and maintains a system for the treatment, storage, and distribution of
potable water that serves 9,537 residences, businesses, and public facilities within the City and
the City SOI. The City purchases all of its untreated water from the Imperial Irrigation District,
which is conveyed to City facilities from the Colorado River via the District’s canal system. City
facilities are developed and maintained by the Department of Public Works.
I. Performance Standard
In general, the City’s performance goal in the operation and maintenance of its water facilities is
to provide adequate potable water service to every customer. Potable water must meet or exceed
water quality standards promulgated by the State Water Board.
The City utilizes several engineering evaluation criteria for determining the adequacy of water
facilities to provide adequate quantity and quality of water service within the City and the need
for improvements to the system. These criteria consider water system pressure, pipeline
velocities, storage capacity, supply requirements, and booster station requirements. The criteria
are developed using the typical planning criteria used in the systems of similar water utilities,
local codes, engineering judgment, commonly accepted industry standards, and input from City
of El Centro Staff. The “industry standards” are typically ranges of values that are acceptable for
the criteria in question, and therefore, are used more as a check to confirm that the values being
developed are reasonable.
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
The current capacity of the City’s water system is approximately 21 million gallons per day
(mgd). The water system includes the Water Treatment Plant, four treated water storage tanks,
two booster pumping stations, and approximately 148 miles of pipeline. The City serves water to
about 9,537 connections with an average day demand (ADD) of approximately 8.6 mgd.
The Water Treatment Plant is located south of I-8 at S. 8th Street and Danenberg Drive. Three of
the four potable water storage tanks and a pumping facility consisting of four booster pumps are
located at the treatment facility. The three storage tanks have a total capacity of 10 million
gallons, and each of the four pumps have a capacity of 4,000 gallons per minute (gpm).
The water system also includes a fourth water storage tank and pumping facility located at La
Brucherie Avenue and Barbara Worth Drive The water storage tank has a four-million gallon
El Centro Service Area Plan Section 4.9 – Water Facilities
February 2016 Page 87
capacity and the two booster pumps have a 4,000 gpm capacity. This site has space reserved for
the installation of a second four million gallon storage tank.
Potable water is distributed from these treatment and storage facilities throughout the City by a
system of large diameter pipelines. Principal pipelines range in diameter from 30” to 18” and are
mostly contained within existing streets. Smaller pipelines with diameters of eight to 12 inches
splitting off from these principal pipelines make up a majority of the distribution system.
Adequacy of Existing Facilities
According to the Water, Wastewater and Storm Water Rate Study Update, the average daily
demand (ADD) on the City’s water system is approximately 8.6 million gallons per day and the
maximum daily demand (MDD) is approximately 13.8 million gallons per day. The existing
storage and conveyance capacity of 21 million gallons per day is sufficient for existing daily
water demand and peak flow requirements. The system also has adequate capacity to
accommodate anticipated near term development. Periodic improvements have been made to
modernize the facilities and materials since the system was overhauled in the 1950s, including a
major modification of the pumping system in 1994. The system has never faced serious capacity
concerns. The system will continue to require periodic improvements in addition to the
expansion necessary to accommodate growth in the City and the City’s SOI, as discussed below.
Future Demand for Facilities
Future water demand was determined in the Water Master Plan of 2008 using Water Demand
Factors (WDFs) used to estimate the ADD for existing and potential development areas. Future
water demand was determined by multiplying the WDF with the total number of acres of each
land use category. Although WDFs are typically determined from a combination of geo-coded
billing records and land use information using spatial GIS analysis, billing records were not
available at the time of the Water Master Plan’s development. In place of billing records,
existing water production and current population was used to calculate the WDFs.
According to the Water, Wastewater and Storm Water Rate Study Update, connections to the
water system will increase an estimated 1.0% each year beginning in 2012. The projected
planning horizon scenario of a population of 55,100 for the year 2025 that includes infill growth
within the City boundary and anticipated growth within the SOI. The existing storage and
conveyance capacity of 21 million gallons per day is sufficient for the daily water demand and
peak flow requirements through the planning horizon year 2025.
Opportunities for Shared Facilities
The City does not share water treatment, storage, or distribution facilities with other
jurisdictions, and there is no opportunity to share such facilities other than for emergency cross-
connection.
El Centro Service Area Plan Section 4.9 – Water Facilities
February 2016 Page 88
Phasing
The existing Water Treatment Plant site has the capacity to be expanded in 21 mgd-increments to
provide the MDD of 42 mgd and ultimately 63 mgd. This expansion will be considered when the
MDD approaches 21 mgd.
III. Mitigation
In order for the City to assure adequate service to its water customers as development continues
within the City boundaries and within the SOI, the City will implement the following measures.
• Implement improvement projects recommended in the Water Master Plan, as funds
become available and as deemed necessary by the Director of the Department of Public
Works.
• Update the Water Master Plan by 2018.
• Implement water system improvement projects identified in the City’s annual budgets
and the updated Water Master Plan.
• Continue to periodically review the water rate and financing structure to assure adequate
funding for the implementation of new projects and the maintenance of existing facilities.
• Require that system improvements conducted by the City or a private developer are
designed to conform to relevant Federal, State, and local regulations.
IV. Financing
Current Funding
Dynamic Consulting Engineers prepared a Water, Wastewater and Storm Water Rate Study
Update in 2012 that determined the adequacy of the existing rate structure charged to City
customers for water service and recommended rate changes and other revenue sources to pay for
water facilities.
The City’s water funds are operated as business enterprises with revenue generated through
monthly service charges that fund water projects and maintenance. Revenue accrued by such
billing is placed in the Water Fund to help finance personnel, maintenance, and improvements.
Operations, maintenance, salaries, equipment purchases, and capital projects are funded by the
City’s Water Enterprise Fund. This fund is used to account for revenues and expenses associated
with the collection and treatment of water. Enterprise funds are used to account for operations
that are financed and operated in a manner similar to private business enterprises. The City
receives money in this fund by charging connection fees and maintenance fees to its water
El Centro Service Area Plan Section 4.9 – Water Facilities
February 2016 Page 89
customers.
The Water Enterprise Fund is separate from the Water Capacity Fee Fund and is not used to
finance the engineering or construction of major improvement projects. The City receives money
for the Water Capacity Fee Fund used for major improvement projects by charging water
capacity fees for development projects and by receiving interest earned from such fees.
The Water Stabilization Fund receives excess revenues from the Water Enterprise Fund. Monies
deposited into this fund can be withdrawn to assist the City in covering its income to debt service
ratios.
Cost Avoidance Opportunities
The City often requires developers to construct water-related infrastructure that will connect the
specific development with the existing City water system. This requirement helps the City avoid
substantial costs associated with infrastructure development.
Recommended Funding
Current funding sources, especially customer fees, will remain the largest source for water
facility maintenance, improvements, and possible expansions. Bond issued against customer
charges may continue to be required to finance the large-scale improvements recommended
within the full buildout timeframe.
An update to the development impact fees study will bring such fees up to date and potentially
increase revenue for the City based on development patterns. Any increase in development
impact fees for water facilities would increase funds available for large-scale development and
improvement projects.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects and other capital
infrastructure such as water facilities.
In addition, it is recommended that the City maintain the required reserve funds so as to provide
working capital for unscheduled repair and replacement of capital infrastructure. The 2012 Water
Rate Study update specifically concluded that the City maintain a cash reserve in its Water
Enterprise Fund is to pay for repair and replacement of portions of the system as they age and
deteriorate. The study also suggested the City continue to increase its cash balance in the
enterprise fund to accumulate appropriate levels for future repairs to treatment, storage and
distribution infrastructure.
El Centro Service Area Plan Section 4.9 – Water Facilities
February 2016 Page 90
4.10 School Facilities
Residents within the City of El Centro are served by three school districts that serve
approximately 11,400 students in a total of 18 schools geographically dispersed throughout El
Centro. These districts include the El Centro Elementary School District (ECESD), the McCabe
Union School District (MUSD), and the Central Union High School District (CUHSD). Two
charter schools are also located within the City and operated by the ECESD. The Imperial
County Office of Education (ICOE) serves the City’s alternative education needs and severely
handicapped student population. The school districts and ICOE work together on classroom
placements for these students. Although the school districts operate independent of the City
government, cooperation between the City and school districts is essential in land use issues,
shared use of facilities, and determining the location of future school sites.
I. Performance Standard
Although school districts are required to comply with numerous state and federal education
performance standards that consider student test scores, teacher-to-student ratios, etc., the SAP
focuses on performance standards that pertain to the land use and physical development of
schools within the City. These performance standards originate from the School Facility Needs
Assessments (SFNAs, also known as the School Facility Fee Justification Reports) that are
prepared for the school districts by qualified consultants to determine development impact fees
for residential, commercial, and industrial development projects.
Classroom student capacity is the basis to defining the other performance standards in the report.
Capacity is determined by multiplying the number of classrooms in each district by the district
student loading standard. The classroom counts comply with the District’s State Allocation
Board-approved capacity for purposes of School Facility Program new construction eligibility.
This capacity standard is then compared to the number of enrolled students per school. For the
specific capacity numbers for each school district, please see the Adequacy of Existing Facilities
section.
To assist in determining suitable future school locations, the City and school districts should
agree to require the inclusion of a school site into a development or identify a site within City
limits if a certain threshold number of units of new residential development is surpassed. Schools
are typically built for a school year enrollment of 600 students. The three school districts have
their own student yield rates (average number of students per dwelling unit) that range from 0.21
to 0.66 students per dwelling unit. The State yield rate according to the Office of Public School
Construction is 0.69 students per dwelling unit. In order to standardize the student yield rate, the
SAP utilizes the state rate of 0.69 students per dwelling unit. Therefore, each school of 600
students supports an estimated 870 residential units. The estimated 870 units serves as the
threshold number that would trigger a development to incorporate a school within the project site
or identify a site within City limits.
El Centro Service Area Plan Section 4.10 – School Facilities
February 2016 Page 91
II. Facility Planning and Adequacy Analysis
Inventory of Existing and Approved Facilities
El Centro Elementary School District (ECESD)
The ECESD serves over 6,000 students in twelve campuses for grades K-8. The campuses
consist of eight elementary schools, two middle schools, and one magnet school. These schools
include Desert Garden, Harding, Hedrick, Lincoln, Martin Luther King Jr., McKinley,
Sunflower, and Washington elementary schools; Kennedy Middle and Wilson Junior High
schools; and De Anza Magnet School.
McCabe Union Elementary School District (MUESD)
The MUESD serves over 1,400 students in grades K-8 and operates one contiguous campus
(Corfman School) with students distributed in grades K-3 and 4-8.
Central Union High School District (CUHSD)
The CUHSD currently serves over 4,000 students in four campuses for students in grades 9-12.
The campuses consist of two high schools, one continuation school, and one adult school. These
schools include Southwest and Central Union high schools; Desert Oasis High School; and
Central Union Adult School.
Adequacy of Existing Facilities
Adequacy of existing facilities is determined by comparing school year student enrollment with
the student teaching station (classroom) capacity according to methodology specified by the
State Department of Education (Education Code Sections 17071.10, 17071.25). Portable
classrooms are generally not included in the official calculation of space except when they meet
the criteria specified in the State Education Code Section 17071.30. For kindergarten through 6th
grade the student capacity is 27 students per teaching station. For Grades 7th through 12th the
student capacity for each teaching station is 27 students per teaching station.
El Centro Elementary School District
Based on the State methodology as outlined in the 2014 School Facility Needs Assessment, the
capacity for the ECESD is 5,249 K-8th grade students. With a 2013/2014 school year enrollment
of 6,094 students (845 students, 16% beyond capacity), the ECESD’s existing facilities are
inadequate.
McCabe Union Elementary School District
According to the 2012 School Facility Fee Justification Report, the MUESD’s total student
capacity is 1,270 students, and the enrollment for the 2012/13 school year was 1,267 students,
just shy of total capacity. However, MUESD categorizes classrooms into three grade tiers (K-3,
4-6, 7-8) with three respective student loading standards of 20, 25, and 27. (The K-3 and 4-6
grade groups of students are respectively 7.2% and 26.5% beyond capacity, while the 7-8 grade
groups are 68.4% below capacity).
El Centro Service Area Plan Section 4.10 – School Facilities
February 2016 Page 92
Central Union High School District
According to the 2013 School Facility Fee Justification Report, CUHSD’s total capacity is 2,970
students. With a 2012/13 school year enrollment of 4,052 students (1,082 students, 36.4%
beyond capacity), the CUHSD’s existing facilities are inadequate.
Future Demand for Facilities
According to the Southern California Association of Governments, the population of El Centro is
expected to increase from the current 43,856 (year 2014) to 55,100 by 2025, a projected growth
of 20.4%. To accommodate this growth in population, each district evaluates the number of
approved residential units within their respective district boundaries to determine the future
demand for facilities in their school facility needs assessments/facility fee justification reports.
The acreage of elementary, middle and high school sites are calculated according to School Site
Analysis and Development, January, 1998, California Department of Education guidelines as
follows: 10 acres for an elementary school of 500 students, 20 acres for a middle school of 900
students, and 40 acres for a high school (less than 1,500 students).
El Centro Elementary School District
Based on the 2014 School Facility Needs Assessment, the total residential square footage
estimated to be built in the ECESD boundaries in the next five years is approximately 1,113
single family units (1,952,202 square feet) and 1,728 Multi-Family units (1,902,528 square feet).
Based on this square footage of residential space, future students are projected to be a total of
844 additional K-8th grade students in the next 5 years.
McCabe Union Elementary School District
According to the 2012 School Facility Fee Justification Report, 5,166 new residential units are
projected to be built within MUESD boundaries in the next five years. Based on this number of
additional new units, the school projects a total enrollment of 4,793 students, 178.3% above the
current capacity of 1,270 students. To accommodate this growth, the District plans to build
additional Elementary and Middle Schools. In addition, the District may purchase or lease
portable classrooms to use on existing campuses for interim student housing while permanent
facilities are being constructed on new school sites.
Central Union High School District
According to the 2013 School Facility Justification Report, 6,466 new residential units are
projected to be built within CUHSD boundaries. CUHSD is currently 1,082 students over-
capacity. In order to provide facilities for current students and accommodate for future growth,
the District plans to construct a new high school campus. In addition, the District may lease
additional portable classrooms to use for interim housing on the existing campus while
permanent school facilities are being constructed. The total capacity of the new High School
would be 2,200 students.
El Centro Service Area Plan Section 4.10 – School Facilities
February 2016 Page 93
Opportunities for Shared Facilities
The City and the School Districts have entered into Joint Use Agreements to allow for mutually
beneficial use of playgrounds, sports fields and other amenities that serve the El Centro
community. These agreements maximize the value of the public facilities that serve El Centro.
The 2008 El Centro Parks & Recreation Facilities Master Plan describes the joint use agreements
between the City and the El Centro Elementary School District that allow each party to program
activities for both City and school-owned facilities. For example, a 2007 joint use agreement
between the District and the City allows public use of the gymnasiums at Wilson Junior High
School and Kennedy Middle School and multipurpose rooms, playing fields, restrooms and
classrooms at various other schools within the District. The City in turn agrees to provide the
Youth Center Parks and Sports Facilities for use by the District.
With the December 2014 opening of the Dr. Marin Luther King, Jr. Sports Pavilion by the City
of El Centro and the commitment of a larger infrastructure investment that will include a skate
park and aquatics center, the City and school districts may consider future joint use agreements.
Phasing
The phasing of new schools will be directly linked to the approval of new development and the
issuance of building permits.
III. Mitigation
In order for the City to provide its residents adequate school facilities and to ensure that the
school system is sufficiently expanded to accommodate growth within the City, the City will
work with the school districts to:
• Support the local school districts by working with them to determine the most appropriate
location and distribution for school facilities to serve the educational needs of the
community and encourage equitable access.
• Collaborate with school districts to determine suitable locations for new school sites that
are equitable, safe, healthy, technologically-equipped, aesthetically pleasing, sustainable,
and support optimal teaching and learning environment.
• Encourage the joint use of school facilities to provide a range of recreational and
educational opportunities for residents.
• Provide opportunities for students to attend schools within their residential
neighborhoods as well as choices in educational settings outside their neighborhoods.
El Centro Service Area Plan Section 4.10 – School Facilities
February 2016 Page 94
IV. Financing
Current Funding
State funding and associated state school construction bond funds provide a basis for school
facility funds. Local property tax shares, developer fees dedicated to schools, and local school
district general obligation bonds provide the balance of facility financing. The ratio of state to
local funding is approximately 35% state/65% local.
In July 2013, Governor Brown signed into law a new funding model for school finance known as
the Local Control Funding Formula (LCFF). The FY 2013–14 State budget packages replaced
the previous K–12 finance system with a new LCFF. For school districts and charter schools, the
LCFF creates base, supplemental, and concentration grants in place of most previously existing
K–12 funding streams, including revenue limits and most state categorical programs. Until full
implementation, local educational agencies will receive roughly the same amount of funding
they received in the prior year plus an additional amount each year to bridge the gap between
current funding levels and the new LCFF target levels. The State projects the time frame for full
implementation of the LCFF to be eight years.
Just as important to the fiscal piece, a school district is mandated by legislation to create a Local
Control and Accountability Plan to explain how it will meet annual goals for all students with
specific activities to address state and local priorities. This includes specifically supporting
underperforming pupils by attaching funds to meet the needs of a school district’s population of
low income, English learner and foster youth students.
The districts need to meet pertinent requirements of State law regarding the collection of
developer fees. State law gives school districts the authority to charge fees on new residential
and commercial/industrial developments if those developments generate additional students and
cause a need for additional school facilities. Government Code Section 65995 authorizes school
districts to collect fees on future development of no more than $3.20 per square foot for
residential construction and $0.51 for commercial/industrial construction (Level 1 fees). Level 1
fees are adjusted every two years according to the inflation rate for Class B construction as
determined by the State Allocation Board. Government Code Section 66001 requires that a
reasonable relationship exist between the amount and use of the fees and the development on
which the fees are to be charged. In order to collect the Level II and Level III Fees in excess of
the statutory Level I Fee for constructing school facilities, the school district must meet the
requirements listed in Government Code Section 65995.5.
Cost Avoidance Opportunities
School infrastructure and facilities are planned and funded independently from City of El Centro.
Schools that have been under-built in terms of meeting student to teacher ratios will remain a
concern for funding. However, the school districts and the City have executed joint use
agreements to share facility use and reduce costs for overlapping facilities. The school district
also has specific lease agreements with the City that were enacted in 1997 and 2003.
El Centro Service Area Plan Section 4.10 – School Facilities
February 2016 Page 95
In addition, a Joint Powers Agreement was adopted on July 18, 2007 between the City and the
Central Union High School District regarding the joint operation and use of Recreation Facilities
and a Facilities Use Request Agreement between the City and Central Union High School
provides for the shared us of recreation facilities. It should be noted that the City pays the school
district for operations and maintenance costs for use of the school facilities under the joint use
agreement; however, the school districts do not pay for operations and maintenance costs for use
of the City facilities.
With the December 2014 opening of the Dr. Marin Luther King, Jr. Sports Pavilion by the City
and the commitment of a larger infrastructure investment that will include a skate park and
aquatics center, the City and the school districts may consider future joint use agreements. The
City has re-evaluated the joint use agreements and its engagement in these agreements.
Recommended Funding
In addition to development impact fees outlined by the State, the school districts can obtain other
potential sources:
• General Obligation Bonds – are paid for out of property taxes and require approval of
two-thirds or 55 percent of its voters.
• Parcel Tax – revenues are historically minor, used to supplement operating budgets and
require approval by two-thirds of voters.
• Mello-Roos Community Facility Districts – uses a tax on property owners within a
defined area to pay long-term bonds issued for specific public improvements and requires
approval from two-thirds of the voters (or land owners if fewer than 12).
El Centro Service Area Plan Section 4.10 – School Facilities
February 2016 Page 96
SECTION 5 – FINANCING
5.1 Introduction
This section of the SAP lists and describes the revenue sources and financing mechanisms that
are currently utilized by the City to fund the development and operation of the various facilities
and services discussed within Chapter 4 of this SAP. Revenue sources and financing mechanisms
that are not currently used but that are being reviewed and considered by the City for future
funding are also described.
5.2 Existing Revenue Sources
The following list presents various sources of revenue that are currently utilized by the City to
accumulate finances necessary to develop and operate the various facilities and services
discussed within the SAP. The revenues are separated between general fund revenue and special
revenue, meaning they are typically restricted for specific uses. Complete budgetary information
is available for viewing at the City Finance Department.
General Fund
Sales Tax
The City receives one percent of State sales tax charged for point-of-sale purchases made at
businesses within the City boundaries. City general sales tax revenue is deposited into the
General Fund, which is further discussed below. The City Finance Department estimates that
approximately $11.0 million in sales tax revenue will be deposited into the General Fund during
fiscal year (FY) 2014-15.
A separate countywide sales tax increase of one-half of one percent was originally approved by
voters in 1989 for a 20-year duration. About 95% of the funds collected go directly to the cities
and County to pay for critical road repair projects, and the remaining 5% is targeted for regional
projects. The Measure D program is managed and administered by the Local Transportation
Authority, and was overwhelmingly approved by voters for an additional 40-years in November
2008. The City estimated that approximately $2.6 million in Measure D funds is available in FY
2014-15.
Property Tax
The City levies a tax to owners of property within the City. This tax, collected annually by the
Imperial County Treasurer-Tax Collector's Office, is deposited into the General Fund. The City
Finance Department estimates that approximately $3.0 million in property tax revenue will be
deposited into the General Fund during fiscal year 2014-15. Pursuant to a master tax agreement
entered into between the City and the County, these two jurisdictions exchange property tax
revenue when an annexation from the County to the City occurs.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 97
Property Tax In-Lieu of Vehicle License Fee (VLF)
The State backfills reduced motor vehicle license fees (VLF) with property tax revenue. Revenue
growth is tied to the change in assessed property values through market activity and Proposition
13 guiding increases in annual assessed values. The City Finance Department estimates that
approximately $3.7 million in in-lieu VLF revenue will be deposited in the General Fund during
FY 2014-15.
Transient Occupancy Tax
Transient occupancy taxes (TOT) are levied on all individuals occupying their dwelling for 30
days or less. This is generally most applicable to room rentals at motels and hotels. The TOT rate
is 10% of the room rental rate. Although the tax is collected for the City by the operators, it is a
tax on the occupant, not the hotel or motel. The City Finance Department estimates that
approximately $1.7 million in TOT revenue will be deposited in the General Fund during FY
2014-15.
Other General Fund Revenue
The City collects other fees and taxes that are deposited in the general fund. They include
Franchise Fees (FY 2014-15 estimate of $312,000), Business License Tax (FY 2014-15 estimate
of $350,000), Fine and Forfeitures (FY 2014-15 estimate of $107,500), User Fees (FY 2014-15
estimate of $189,000) and other taxes (FY 2014-15 estimate of $49,000).
Certain public services and facilities operated by the City entail various user fees that are
charged to patrons or other users on a fee-for-service basis. User fees are charged for services
such as vehicle impound and release (ECPD), fire permit inspection and issuance (ECFD),
summer day camp (Parks & Recreation), and late or damaged book fees (El Centro Public
Library). Revenue generated by these fees is deposited into the General Fund. City services
provided through the Planning Department, Building Department, and Engineering Department
regarding project processing, permitting, and review also incur user fees that are deposited into
the General Fund. A Cost Recovery Study was prepared for the City Finance Department that
examined how the City could more efficiently utilize user fees to increase revenue and recover
the costs of operating City facilities and services. It has been several years since that study has
been updated.
Special Revenue
Development Impact Fees
Jurisdictions often charge private developers various development impact fees to assure that the
demand for and physical and financial impacts to public services and facilities caused by
development projects are adequately addressed. Mitigation of project impacts can be satisfied
through imposition of development impact fees.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 98
The City adopted a development impact fee program in 1989 and included fees for the following
categories:
• General Government Facilities
• Fire
• Library
• Parks and Recreation
• Police
• Streets
• Water and Wastewater Treatment
The fee structure is outlined in the Development Impact Fee Report, which was prepared in 1989
and revised in 1994. The report was further updated by Tischler-Bise in June 2006. Development
impact fees are used to fund the capital costs of facilities borne by the impacts from new
development. The fees cannot be used to fund an existing infrastructure deficiency. This revenue
stream has declined significantly since the recession due to the slowdown in residential
construction. However, this revenue stream has seen an increase the last two years and revenue
for FY 2014-2015 is projected to be $792,000.
Gasoline Tax
The State levies a tax on all in-state sales of gasoline. A portion of the revenue derived from this
State tax is distributed by formula to local jurisdictions. The formula distribution is complex due
to State budget activity making this revenue stream uncertain. Gas tax revenues are restricted by
the State for street purposes only, therefore the City deposits money into a special fund.
Projected revenue is $1.15 million in FY 2014-15.
Local Bonds
Bonds are issued for Governmental Activities and for the Enterprise funds. The governmental
activity bonds have been issued for specific capital projects whose revenue sources to repay the
bonds are sales tax (Measure D) or Successor Agency – Debt Service Property Tax. The bonds
for the Enterprise funds are used to finance the design, engineering, acquisition, and construction
of certain repairs, renovations, extension, betterments and improvements to the City’s municipal
water and wastewater system. The revenue sources to pay for these bonds are the water and
wastewater user fees.
Other Transportation Funding Sources
The City receives funding for specific circulation and roadway projects from several state and
federal programs. They include the following:
• State Transportation Improvement Program (STIP): Funds from this program are
allocated for specific projects by programming of funds through the Imperial County
Transportation Commission (ICTC).
• Federal Highway Administration: Grant funds from this revenue program are applied to
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 99
improve major thoroughfares in the City. They include the Highway Safety Improvement
Program and Congestion Mitigation and Air Quality Program. Current roadway capital
projects include Adams/La Brucherie, Euclid Avenue, and Buena Vista Avenue, as well
as lighting and sidewalks.
• Transportation Development Act – Article 3: Article 3 funds are allocated by ICTC for
specific projects related to pedestrian and bicycle mobility.
Community Development Block Grants
Housing and Urban Development (HUD) Entitlement funds are a revenue stream from
Community Development Block Grant Entitlement Communities Grant. These funds are
allocated by the federal government to eligible entitled local agencies for housing and
community development purposes and for expanding economic opportunities for low and
moderate income persons. These revenues are subject to adjustment both in the total amount and
in the amount allocable for costs by the federal government in the future. Revenues for the City
are estimated to be $820,000 in FY 2014-15.
5.3 Future Revenue Sources
The following list presents sources of revenue that the City Finance Department could consider
to increase their available financial resources.
Updated User Fees
The last Cost Recovery Study was prepared for the City in May 2003. The study identifies
potential increases to existing fees and also identified user fees that do not currently exist but that
could feasibly be charged to increase revenue for the City and recover costs. Specific user fees
included for services are provided by city administration, planning, public works and
engineering, public library, ECPD, ECFD, and Parks & Recreation.
Updated Development Impact Fees
While the City currently charges development impact fees for administration, library, law
enforcement, fire protection, streets, parks, recreation, and public facilities, the fee structures and
the nexus analysis upon which the fees are based are dated. A new nexus evaluation and
subsequent updated impact fees provide a source of revenue for the City to offset the
infrastructure impact from new development.
State and Federal Funding
Various government programs are available at the state and federal levels to assist local
jurisdictions in financing public facilities and services. The City will continue to seek out such
sources of revenue in the future. Most funding sources at the state level require an application
requesting assistance and specifying the projects or purposes for which the funds can be used.
Financial assistance from the state can include grants, low interest loans, and matching funds.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 100
An example of a new State program is the cap-and-trade program that funds various projects that
reduce greenhouse gas emissions. Energy efficiency and clean energy projects include low-
income weatherization and solar programs; while water use efficiency grants to local agencies
help fund water conservation measures intended to reduce the amount of energy used to move,
treat, and heat water. The State Proposition 1 water bond that passed in November 2014, along
with recent emergency drought funding package is available for funding for drought relief and
critical water infrastructure projects.
At the federal level, financial assistance includes grants and federal matching funds for state run
assistance programs.
For funding programs that include both federal and state components, the Active Transportation
Program (ATP) administered by Caltrans consolidates several programs related to improvement
projects for pedestrians and bicycles. The Active Transportation Program was created in 2013
by Senate Bill 99 and Assembly Bill 101 to encourage increased use of active modes of
transportation, such as biking and walking. The ATP consolidates various transportation
programs; including the federal Transportation Alternatives Program, state Bicycle
Transportation Account, and federal and state Safe Routes to School programs into a single
program.
5.4 Existing Financing Mechanisms
The following are financing mechanisms currently utilized by the City.
General Fund
The General Fund is used to account for all revenues and expenditures necessary to carry out the
basis governmental activities of the City that are not accounted for through other funds. For the
City, the General Fund includes activities such as public protection, public works and facilities,
parks and recreation, and community development.
Capacity Fee Funds
The City maintains capacity fee funds for the water and wastewater systems. These funds are
comprised of charges to developers for implementing projects that would contribute to demand
on the City’s water and wastewater facilities. The revenue is used to finance improvement
projects for the respective facilities, and is not used for personnel or other operational costs.
Enterprise Funds
The City maintains two major Enterprise Funds, the Water Fund and the Wastewater Fund. The
Water Fund accounts for revenues and expenses associated with the treatment and distribution of
potable water. The Wastewater Fund accounts for revenue and expenses associated with the
collection and treatment of wastewater. Revenues come from water/wastewater user fees,
connection fees, maintenance fees and interest. Bonds have been issued against the Enterprise
funds for infrastructure improvements.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 101
Developer/Builder Contributions
Many of the improvements to municipal water, wastewater, drainage, and circulation systems
that are required to serve new development within the City can be directly funded and
constructed by the developer and/or builder through private funding sources and are not the
responsibility of the City. Facilities earmarked for developer/builder funding are typically those
that normally would have been imposed as a condition of approval of a tentative map under the
City’s existing development review process. Requiring such contribution through a developer
agreement can save the City significant amounts of expenses.
Special Assessment Districts
Jurisdictions often form special assessment districts to achieve financial and operational
efficiency in implementing improvements for a particular geographical location or a certain type
or types of improvement. One type of assessment district is a Landscape and Lighting
Maintenance District (LLMD) that is created for maintenance and improvements for assets
including drainage, sidewalks, and median walkways. The City has two existing LLMDs created
for Legacy Ranch and Buena Vista developments, both commencing in FY 2014-15. The City
expects to receive revenues of $7,150 and $4,650 from these assessment districts, respectively.
Community Facilities Districts
The 1982 Mello-Roos Community Facilities Act allows a district to establish community
facilities districts that provide funding for provision of services and development of facilities.
Such districts often involve taxes levied on the public that generate revenue that is deposited into
special funds specifically for the respective service or facility instead of into the jurisdiction’s
general fund. Land based funding mechanisms such as Mello-Roos Community Facilities
Districts are possible for new development where there are few voters required to help fund
public infrastructure and/or services. The Legacy Ranch development created Mello-Roos
Community Facilities District NO. 2007-1 to issue bonds for the purpose of financing certain
public improvements (streets, sewers, storm drains).
5.5 Future Financing Mechanisms
In addition to the existing financing mechanisms listed above that the City will continue to
utilize, a new financing mechanism was developed through recent legislation to recapture certain
aspects of the former redevelopment fund process. SB 628 (Beall) was signed into law in
November 2014 allowing for the creation of Enhanced Infrastructure Financing Districts or
EIFDs. EIFDs are empowered to provide financing for a broad range of infrastructure work so
long as a direct connection can be made between the needed infrastructure and its users. Projects
can include traditional public works such as roads and highways, bridges, parking facilities,
transit stations, sewage and water facilities, flood control and drainage projects, solid waste
disposal, parks, libraries, and child care facilities. EIFDs may also finance other items including
brownfield restoration and environmental mitigation, military base reuse projects, affordable
housing, private industrial buildings, transit oriented development projects, and projects carrying
out sustainable communities strategies.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 102
The current law requires a two-thirds vote to form an Infrastructure Financing District; an EIFD
can be formed without a vote. The legislative body of a city or county may designate one or
more proposed EIFDs including areas which are not contiguous as well as any portion of a
former redevelopment project area. Once an EIFD is established, SB 628 would require the
creation of a public financing authority responsible for putting together an infrastructure
financing plan. The financing plan would specify whether the district would be funded through
tax increment financing, public or private loans, grants, bonds, assessments, fees or some
combination thereof. The issuance of tax increment bonds would require a voting threshold of
only 55 percent for passage rather than the two-thirds majority now required except for school
bonds.
Another financing tool recently signed into law is SB 614 (Wolk), which authorizes a city to
include in its resolution of application an annexation development plan that would form or
reorganize a special district to improve or upgrade structures, roads, sewer or water facilities, or
other infrastructure to serve a disadvantaged, unincorporated community (DUC). A DUC is
defined as a community with an annual median household income that is less than 80% of the
statewide annual median household income. The financing plan would be included in the
existing LAFCO process. As a condition of annexation until January 1, 2025, tax increment
financing could be used by the special district, such as a community services district, to fund
infrastructure improvements in a DUC.
5.6 Facility Financing
The following section provides a brief discussion of the funding sources used for the specific
services and facilities included in Chapter 4 of the SAP. Any sources of funding that are not
currently being utilized, as well as opportunities for cost avoidance, are identified.
General Government Facilities
Current Funding
The City receives funding for general government facilities primarily from the General Fund and
development impact fees. The impact fees pay for capital costs of facilities while the General
Fund pays for the maintenance and operations of the facilities.
Cost Avoidance Opportunities
There are no a cost savings opportunities for the City.
Recommended Funding
The City will continue to use the General Fund for the maintenance and operation of the general
government facilities. As the City continues to grow, any necessary expansion of the facilities or
acquisition of additional property for general government facilities could be financed by issuing
bonds or by collecting development impact fees.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 103
An update to the Cost Recovery Study and the City’s user fees would provide increased revenue
that could be used for operational improvements and expansion of general government facilities.
An updated development impact fee study will also bring such fees up to date and align revenues
with capital projects that mitigate new growth. Any increase in development impact fees for
general government services or facilities would increase the funds available to pay for specific
large-scale development or improvement projects related to such facilities.
Drainage Facilities
Current Funding
Within the City and the SOI, these facilities are mostly installed and funded by developers as
projects are implemented. Development impact fees charged on new development for drainage
facilities are also collected. An existing rate structure is charged to City customers for storm
water service.
Cost Avoidance Opportunities
The City is able to avoid some costs for the development of new drainage facilities by requiring
developers to construct adequate facilities and retention basins on their projects.
Recommended Funding
Funding responsibilities for project-related facilities shall remain with the developers and
secured prior to construction. Improvements to the centrally located City-maintained facilities
shall remain under the guidance of the wastewater division of the Department of Public Works.
The 2008 Drainage Master Plan identified a number of existing and potential funding sources for
maintenance and capital expenditures. They include the following:
• General Fund
• Drainage Fees
• Federal Housing and Community Development Act of 1974 – Community Development
Block Grants (CDBG)
• Special Assessments
Municipal Improvement Act of 1913
o
Benefit Assessment Act of 1982
o
• Highway Improvement Projects
• Mello-Roos Community Facilities Act of 1982
• General Obligation Bonds
Some funding mechanisms like special assessments and Mello-Roos require voter approval from
affected land owners to take effect, while others such as CDBG and highway funds may be used
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 104
for drainage if there is a general relationship established between the project and program intent
of the funds. Mello-Roos funding can be for flood and storm protection services, including, but
not limited to, the operation and maintenance of storm drainage systems, and sandstorm
protection services. In addition, a Water, Wastewater and Storm Water Rate Study Update was
completed in 2012 that determined the adequacy of the existing rate structure charged to City
customers for storm water service and recommended rate changes and other revenue sources to
pay for storm water facilities.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as flood control and drainage projects.
Fire Facilities
Current Funding
The El Centro Fire Department operational and maintenance costs for facilities, equipment and
personnel are financed by the General Fund. Revenues from user fees charged by the ECFD go
into the General Fund and used to fund the ECFD programs. Development impact fees required
of development projects generate revenue that is used for large-scale improvement and
development projects related to fire facilities as a result of increased capacity.
Cost Avoidance Opportunities
The ECFD operates and shall continue to operate under a mutual aid agreement with the County
of Imperial Fire Department for as-needed assistance and backup. This assures that people and
property within the City, the SOI, and the rest of the County are covered by adequate fire and
emergency response. The two agencies also share a hazardous materials emergency response
unit. The ECFD participates in a countywide joint purchase program. Further, ECFD conducts
fire inspections while a private vendor conducts plan review of new structures which enables
ECFD staff to focus on additional priorities. The fire and police departments also plan to study a
regional dispatch center that can result in cost savings.
Recommended Funding
The General Fund is used to account for all revenues and expenditures necessary to carry out the
Fire Department services. Expansion or additions to the existing inventory of facilities could be
funded through issuance of new bonds backed by the general fund to meet fire service protocol.
As discussed above, an update to the Cost Recovery Study could include new or revised user
fees for services performed by the ECFD. Increased user fees for the department would increase
department contribution to the General Fund. The Fire Department indicated the potential for
developing a subscription based EMS fee that could be part of the fee study update. Also, there
could be study of receiving reimbursement from insurance carriers for fire department response
to incidents.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 105
An update to the development impact fees study will bring such fees up to date and potentially
increase revenue for the City based on development patterns. Any increase in development
impact fees for ECFD service or facilities would increase funds available for large-scale
development and improvement projects.
Land based funding mechanisms such as Mello-Roos Community Facilities Districts are possible
for new development where there are few voters required to help fund fire infrastructure and/or
fire protection services as well as ambulance and paramedic services.
Funding and resources for the future Fire Station No. 4 would come from a combination of
impact fee funds and donation of land by developers undertaking projects in the relevant areas of
the City.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as fire facilities.
Law Enforcement
Current Funding
Funding for law enforcement is derived from many funding sources. Sources include the general
fund, developer fees, and grants. The General Fund is used to account for all revenues and
expenditures necessary to carry out the Police Department services. As a part of the revenue, the
City receives Proposition 172 public safety tax revenue based on sales tax receipts, as well as
cost recovery for judicial court appearances to provide testimony on cases. Revenue from user
fees charged by the ECPD is paid into the General Fund. Parking enforcement revenue is also
deposited for funding of police activities. Development impact fees required of development
projects generate revenue that is used for large-scale improvement and development projects
related to police facilities and services.
The ECPD received a grant in 2014 from the Department of Homeland Security to conduct
enforcement operations, and a grant from the Office of Traffic Safety to conduct additional DUI
enforcement. Other grant funding comes from the Department of Justice to conduct narcotics
enforcement. According to the Police Department, grant funding is not adequate to fully pay for
personnel expenditures related to the grant funds. Maintaining the city policy ratio of sworn
officers per 1,000 capita remains a challenge due to factors such as competitiveness of retention
pay relative to other areas.
Cost Avoidance Opportunities
While the ECPD cooperates with the Imperial County Sheriff’s Department for the provision of
as-needed emergency backup services, the two agencies do not currently share any facilities and
would not share any facilities in the future. Although there are no substantial cost avoidance
opportunities for the ECPD, the department achieves cost savings through the leasing of
equipment including computers and phone system. Non-sworn department staff are used where
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 106
feasible in place of a sworn officer to conduct city business to reduce personnel cost. The police
and fire departments also plan to study a regional dispatch center that can result in cost savings.
Further, school districts share the cost of School Resource Officers with the City.
Recommended Funding
The ECPD will continue to be funded by the General Fund, public safety grants and other
sources. The general fund remains a flexible funding source for both operations and
maintenance, and capital expenses. Expansion or additions to the existing inventory of facilities
could be funded through issuance of new bonds backed by the general fund to meet police
service protocol. Grants such as those identified above, can be procured for specific operations
while general fund and developer fees are available for capital facilities.
An update to the Cost Recovery Study could include new or revised user fees for services
performed by the ECPD. Increased user fees increase the revenues that are available for the
General Fund to carry out the Police Department services. The Police Department indicated the
potential to recoup the cost for restitution involving Driving Under the Influence (DUI). Parking
enforcement fees could also be updated through the cost recovery study.
An update to the development impact fees study will bring such fees up to date and potentially
increase revenue for the City based on development patterns. Any increase in development
impact fees for ECPD service or facilities would increase funds available for large-scale
development and improvement projects.
The City also may consider the establishment of a community facilities district for the ECPD to
centralize funding for the Department and allow an efficient and effective means of financing
Department needs. Land-based funding mechanisms such as Mello-Roos Community Facilities
Districts are possible for new development where there are few voters required to help fund
police infrastructure and/or police protection services.
The 2015-2016 Budget states the need for three major capital projects; a new library, new police
building and a new aquatic center. Approximately $8.5 million in funds has been reserved for the
construction of these new facilities; however, the priority of these projects will determine the
timing and phasing of design and construction. It is anticipated that the City will need to issue
bonds to pay for the design and construction of the new police building if the reserved funds are
not used.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as police facilities.
Library Facilities
Current Funding
The General Fund is used to account for all revenues and expenditures necessary to carry out the
Library services.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 107
Development impact fees are levied for library facilities. Revenue generated by development
impact fees are not placed in the General Fund, but are used for specific library improvement
projects.
The library also accepts private donations material and funding grants to offset the costs of
operation and to implement improvement projects.
Cost Avoidance Opportunities
The current library is housed in an interim facility since the original library was destroyed in the
2010 Easter Earthquake. The original El Centro Public Library contained a conference room that
was used for meetings and community space and meeting space could be incorporated into the
new library that could be rented out and help generate revenue for the library.
Through inter-library loan programs, the library shares resources with other libraries in the
region which keeps costs down while providing acceptable services to City residents.
The El Centro Public Library offers Zip Books. Zip Books is a new patron-driven model for
securing the books a customer wants to read. For speed and cost-efficiency, the patron’s request
is delivered by Amazon directly to their home mailing address. When finished reading the item,
the patron returns it to the library. The library also offers an e-book service for customers to
download digital copies of reading materials.
Recommended Funding
The General Fund will continue to cover the expenditures necessary for library services. The
library will continue to apply for all possible funding opportunities from the State, and will
continue to accept donations of money or materials.
An update to the Cost Recovery Study could recommend improvements to the library user fee
structure. Updating the relevant user fees will provide increased revenue for the General Fund
that could be used for improvements and expansion of library facilities.
An update to the development impact fees study will bring such fees up to date and increase
revenue for the City. Any increase in development impact fees for library facilities would
increase funds available for large-scale development and improvement projects related to library
facilities and services. The City has established a Library Task Force in partnership with the
Library Board to develop and implement a plan for new permanent library.
The 2015-2016 Budget states the need for three major capital projects; a new library, new police
building and a new aquatic center. Approximately $8.5 million in funds has been reserved for the
construction of these new facilities; however, the priority of these projects will determine the
timing and phasing of design and construction. The City will evaluate the possibility of issuing
bonds to pay for the design and construction of the new library building if the reserved funds are
not used.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 108
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as libraries.
Parks and Recreation Facilities
Current Funding
The City receives funding for parks and recreation facilities including from the general fund,
development impact fees, user fee charges, fundraisers and donations, and regional, state and
federal grants. Proposition 84 (The Safe Drinking Water, Water Quality and Supply, Flood
Control, River and Coastal Protection Bond Act of 2006) funds were used to build a skate park.
Maintenance fees for landscaping improvements along street rights-of-way are also collected
from the Legacy Ranch Landscape and Lighting Maintenance District (LLMD), as well as from
the Buena Vista LLMD. The LLMD was created for maintenance and improvements for assets
including drainage, sidewalks, and median walkways. In the case of Legacy Ranch, the LLMD
can be used for park maintenance of the open space dedicated to the city by the developer.
Maintenance includes landscaping, open grass field, playground equipment, and structural
amenities like a covered picnic area and furnishings.
On December 11, 2014, El Centro celebrated with an official Grand Opening and Ribbon Cutting
Ceremony for the new Dr. Marin Luther King, Jr. Sports Pavilion. The new multi-sports complex
cost $6.6 million to complete. Funding was provided by a Redevelopment Agency Bond of $4.6
million, Community Development Block Grant Entitlement of $970,000, Community
Development Block Grant Program Income of $664,728, Parks and Recreation Impact Fees of
$320,230, and a donation from Rabobank for $25,000.
Cost Avoidance Opportunities
City policy requiring private developers to dedicate parkland and construct parks in conjunction
with development projects eliminates substantial cost to the City for undertaking the purchase or
dedication of land or the construction costs. The City will continue this cost avoidance measure.
The school districts and the City have formed joint use agreements to share facility use and
reduce costs for overlapping facilities. The 2008 El Centro Parks & Recreation Facilities Master
Plan describes the use of joint agreements between the City and the El Centro Elementary School
District that allow each agency to program activities on both park and school grounds. These
agreements allow a wider array of facilities use for the community with funding provided by
both the city and school district for their respective facilities. For example, a joint-use agreement
between the District and the City was agreed to on June 13, 2007. Under the agreement, the
District allows public use of the Gymnasiums at Wilson Junior High School and Kennedy
Middle School, multipurpose rooms, playing fields, restrooms and classrooms at the various
schools within, and the City agrees to provide the City Plunge, Youth Center Parks and Sports
Facilities for use by the District. The school district also has specific lease agreements with the
City that were enacted in 1997 and 2003.
A Joint Powers Agreement was adopted on July 18, 2007 between the City and the School
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 109
District regarding the joint operation and use of Recreation Facilities. In addition, a Facilities
Use Request Agreement between the City and Central Union High School provides the
community access to the gymnasiums at Southwest and Central, the track and field facilities,
swimming pool at Central as well as multipurpose rooms, playing fields, tennis courts and
classrooms at the various schools within the district. The City in turn agrees to provide the use of
the City Plunge, Youth Center, parks and sport facilities. It is noted that the City pays the school
district for operations and maintenance costs for use of the school facilities under the joint use
agreement; however, the school districts do not pay for operations and maintenance costs for use
of the City facilities. With the recent construction and opening of the Dr. Marin Luther King, Jr.
Sports Pavilion by the City of El Centro in December 2014 as part of a larger infrastructure
investment that will include a skate park and aquatics center, the city and the school districts may
evaluate future joint use agreements.
Recommended Funding
The General Fund will continue to cover the expenditures necessary to carry out the Parks and
Recreation services. To reduce the current parkland deficit and to accommodate the anticipated
population increase, the City will continue to require that new development include provision of
additional public parks and recreational facilities to the maximum extent, in accordance with
Public Facilities Policy 1.2.
An update to the Cost Recovery Study could include new or revised user fees for services
performed by the Parks & Recreation Department. Increased user fees would increase
department contribution to the General Fund. Updating the relevant user fees will provide
increased revenue for the General Fund that could be used for improvements and expansion of
parks and recreation facilities.
An update to the development impact fees study will bring such fees up to date and increase
revenue for the City. Any increase in development impact fees for parks and recreation facilities
would increase funds available for large-scale development and improvement projects related to
parks and recreation. Development of a Capital Improvement Program for parks will provide
guidance for the capital projects that will be needed, their timing of implementation, and the
possible funding sources and mechanisms.
Land based funding mechanisms such as Mello-Roos Community Facilities Districts are possible
for new development where there are few voters required to help fund park facilities and/or
maintenance of parks, parkways and open space.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects and other capital
infrastructure such as parks and child care facilities.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 110
Transportation Facilities
Current Funding
The General Fund is used to account for all revenues and expenditures necessary to carry out the
Street & Maintenance services. Funding sources include development impact fees, local
transportation authority, and the State gas tax. The gas tax is used for roadway maintenance and
improvement and is allocated to local jurisdictions based on formulas that account primarily for
population. The Imperial County Transportation Commission (ICTC) allocates Article 3 revenue
from the Transportation Development Act (TDA) to each local jurisdiction in the County for
non-motorized transportation such as bicycle and pedestrian projects. Street and road funding
from TDA is not provided.
The Imperial County Local Transportation Authority administers the local transportation sale tax
(Measure D) that provides street and road funding for maintenance and capital improvement.
LTA revenues bonds were issued for street related expenditures. Traffic fines and forfeitures are
collected by the City for traffic control supplies and equipment. Capital roadway projects are
funded from state transportation improvement program (STIP) revenue that are programmed by
ICTC and submitted to the California Transportation Commission. STIP revenue is comprised of
state and federal highway revenue sources and projects that receive funding are voted upon by
the CTC. Many of these projects are tied to highway capacity, highway intersections and related
projects.
Landscape and Lighting Maintenance Districts (LLMDs) are created for maintenance and
improvements for assets including drainage, sidewalks, and median walkways. The City has two
existing LLMDs created for Legacy Ranch and Buena Vista developments. The Legacy Ranch
development also created a Mello-Roos Community Facilities District NO. 2007-1 to issue
bonds for the purpose of financing certain public improvements (streets, sewers, storm drains).
Cost Avoidance Opportunities
While there are no real opportunities to share roadway facilities with any adjacent jurisdiction,
the City’s system does not exist independently, and circulation within and through the City is
mutually affected by the operation of the State and County circulation system. In order to
maintain the best possible circulation within City limits, throughout the SOI, and within the
County and the greater region as a whole, the City will continue to cooperate with the State, the
County, and adjacent cities in monitoring the operation of the regional system and the
implementation of necessary improvements. In accordance with General Plan policy, the City
will also continue to cooperate with the Imperial County Transportation Commission to ensure
that adequate public transportation service is available for all segments of the community.
Application to State and federal programs to receive funding for circulation and roadway
projects also provides a significant opportunity to avoid direct cost to the City for large-scale
development and improvement projects.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 111
Recommended Funding
Growth in core transportation funding sources for future transportation projects are closely
linked to economic growth. Economic stability and growth highly influence revenue sources
such as the gas tax, Transportation Development Act Article 3, Measure D transportation funds,
development impact fees, and state transportation revenue. Active Transportation Plan funds
from Caltrans could be available for pedestrian and bicycle projects. The City’s ability to
leverage local sources for additional state and federal funds improves its ability to fund
additional facilities.
An update to the development impact fees study will bring such fees up to date and increase
revenue for the City. Any increase in development impact fees for transportation facilities would
increase funds available for large-scale development and improvement projects.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including transportation facilities such as roads and
highways, bridges, parking facilities, transit stations, and transit oriented development projects.
Wastewater Facilities
Current Funding
Dynamic Consulting Engineers prepared a Water, Wastewater and Storm Water Rate Study
Update in 2012 that determined the adequacy of the existing rate structure charged to City
customers for wastewater service and recommended rate changes and other revenue sources to
pay for wastewater facilities.
The City’s wastewater funds are operated as business enterprises with revenue generated through
monthly service charges that fund wastewater projects and maintenance. Revenue accrued by
such billing is placed in the Wastewater Fund to help finance personnel, maintenance, and
improvements.
Operations, maintenance, salaries, and equipment purchases are funded by the City’s Wastewater
Enterprise Fund. This fund is used to account for revenues and expenses associated with the
collection and treatment of wastewater. Enterprise funds are used to account for operations that
are financed and operated in a manner similar to private business enterprises. The City receives
money in this fund by charging connection fees and maintenance fees to its wastewater
customers.
The Wastewater Enterprise Fund is separate from the Wastewater Capacity Fee Fund and is not
used to finance the engineering or construction of major improvement projects. The City receives
money for the Wastewater Capacity Fee Fund used for major improvement projects by charging
wastewater capacity fees for development projects and by receiving interest earned from such
fees.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 112
The Wastewater Stabilization fund receives excess revenues from the Wastewater Enterprise
Fund. Monies deposited into this fund can be withdrawn to assist the City in covering its income
to debt service ratios.
The Legacy Ranch development also created a Mello-Roos Community Facilities District NO.
2007-1 to issue bonds for the purpose of financing certain public improvements (streets, sewers,
storm drains).
Cost Avoidance Opportunities
The City often requires developers to construct wastewater-related infrastructure that will
connect the specific development with the existing City wastewater system. This requirement
helps the City avoid substantial costs associated with infrastructure development.
Recommended Funding
The City shall continue to use the existing financing mechanisms described above to finance the
City’s wastewater engineering, construction, operation, and maintenance. Bond measures may
continue to be required to finance the large-scale improvements recommended within the full
buildout timeframe. The City recently issued a large revenue bond that is backed by customer
charges. Current funding sources, especially customer fees, will remain the largest source for
wastewater treatment and sewer facility maintenance, improvements, and possible expansions.
An updated wastewater study will be conducted that will identify funding sources to pay for the
recommended improvements to the wastewater facility. Also, an update to the development
impact fees study will bring such fees up to date and potentially increase revenue for the City
based on development patterns. Any increase in development impact fees for wastewater
facilities would increase funds available for large-scale development and improvement projects.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects but also other
capital infrastructure such as sewage facilities.
Water Facilitates
Current Funding
Dynamic Consulting Engineers prepared a Water, Wastewater and Storm Water Rate Study
Update in 2012 that determined the adequacy of the existing rate structure charged to City
customers for water service and recommended rate changes and other revenue sources to pay for
water facilities.
The City’s water funds are operated as business enterprises with revenue generated through
monthly service charges that fund water projects and maintenance. Revenue accrued by such
billing is placed in the Water Fund to help finance personnel, maintenance, and improvements.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 113
Operations, maintenance, salaries, equipment purchases, and capital projects are funded by the
City’s Water Enterprise Fund. This fund is used to account for revenues and expenses associated
with the collection and treatment of water. Enterprise funds are used to account for operations
that are financed and operated in a manner similar to private business enterprises. The City
receives money in this fund by charging connection fees and maintenance fees to its water
customers.
The Water Enterprise Fund is separate from the Water Capacity Fee Fund and is not used to
finance the engineering or construction of major improvement projects. The City receives money
for the Water Capacity Fee Fund used for major improvement projects by charging water
capacity fees for development projects and by receiving interest earned from such fees.
The Water Stabilization fund receives excess revenues from the Water Enterprise Fund. Monies
deposited into this fund can be withdrawn to assist the City in covering its income to debt service
ratios.
Cost Avoidance Opportunities
The City often requires developers to construct water-related infrastructure that will connect the
specific development with the existing City water system. This requirement helps the City avoid
substantial costs associated with infrastructure development.
Recommended Funding
Current funding sources, especially customer fees, will remain the largest source for water
facility maintenance, improvements, and possible expansions. Bonds issued against customer
charges may continue to be required to finance the large-scale improvements recommended
within the full buildout timeframe.
An update to the development impact fees study will bring such fees up to date and potentially
increase revenue for the City based on development patterns. Any increase in development
impact fees for water facilities would increase funds available for large-scale development and
improvement projects.
Enhanced Infrastructure Financing Districts (EIFDs) are empowered to provide financing for a
broad range of infrastructure work, including traditional public works projects and other capital
infrastructure such as water facilities.
In addition, it is recommended that the City maintain the required reserve funds to provide
working capital for unscheduled repair and replacement of infrastructure. The 2012 water rate
study update specifically concluded that the City maintain a cash reserve in its Water Enterprise
Fund is to pay for repair and replacement of portions of the system as they age and deteriorate.
The study also suggested the City continue to increase its cash balance in the enterprise fund to
accumulate appropriate levels for future repairs to treatment, storage and distribution
infrastructure.
El Centro Service Area Plan Section 5 – Financing
February 2016 Page 114