CITY OF CALEXICO
SERVICE AREA PLAN
UPDATE 2018
Final
October 2018
THE HOLT GROUP, INC.
PHONE (760) 337-3883 FAX (760) 337-5997
1601 N. Imperial Ave, El Centro, CA 92243
TABLE OF CONTENTS
I. INTRODUCTION ..................................................................................................................................... 1
A. INTRODUCTION & PURPOSE ............................................................................................................. 1
B. SERVICE AREA PLAN REQUIREMENTS ............................................................................................... 3
C. CALEXICO SERVICE AREA ................................................................................................................... 4
II. EXECUTIVE SUMMARY ........................................................................................................................ 10
A. POPULATION PROJECTIONS ............................................................................................................ 10
B. FINDINGS ......................................................................................................................................... 10
III. LAND USES, GROWTH PROJECTIONS AND PHASING .......................................................................... 22
A. LAND USES AND ANNEXATION AREAS ............................................................................................ 22
B. GROWTH PROJECTIONS .................................................................................................................. 30
C. PHASING OF EQUIVALENT DWELLING UNITS & BUILDOUT ............................................................ 34
IV. PUBLIC FACILITIES AND SERVICES ....................................................................................................... 37
A. ADMINISTRATION SERVICE AND FACILITIES ................................................................................... 38
B. LAW ENFORCEMENT ....................................................................................................................... 45
C. FIRE PROTECTION ............................................................................................................................ 54
D. PARKS & RECREATION ................................................................................................................. 62
E. LIBRARY & CULTURAL ARTS ............................................................................................................ 70
F. CIRCULATION & TRANSPORTATION ................................................................................................ 78
G. STORMWATER AND DRAINAGE ...................................................................................................... 94
H. WATER FACILITIES ......................................................................................................................... 105
I. SANITARY SEWER FACILITIES......................................................................................................... 117
J. AIRPORT FACILITIES ....................................................................................................................... 128
K. EDUCATIONAL FACILITIES ............................................................................................................. 137
L. SUPPORT SERVICES PROVIDED BY OTHERS .................................................................................. 148
V. FINANCING PLAN .............................................................................................................................. 154
Resources and References ........................................................................................................................ 179
EXHIBITS
Exhibit 1 - City of Calexico Geographic Location ........................................................................................... 2
Exhibit 2 - City Limits and Sphere of Influence Boundaries .......................................................................... 6
Exhibit 3 - General Plan Land Use Map ....................................................................................................... 23
Exhibit 4 - Infill and Development Areas..................................................................................................... 29
Exhibit A-1 Administration Facilities ........................................................................................................... 40
Exhibit B-1 Existing Law Enforcement Facilities .......................................................................................... 47
Exhibit C-1 Existing and Proposed Fire Station Facilities ............................................................................ 56
Exhibit D-1 Existing Park Facilities ............................................................................................................... 64
Exhibit E-1 Library & Cultural Arts Facilities ................................................................................................ 72
Exhibit F-1 Major Circulation Routes .......................................................................................................... 80
Exhibit F-2 Traffic Signals and Bridges ........................................................................................................ 85
Exhibit G-1 Retention Facilities and Drainage Zones .................................................................................. 97
Exhibit G-2 Planned Drainage Facilities .................................................................................................... 101
Exhibit H-1 Water Facilities ....................................................................................................................... 107
Exhibit I-1 Wastewater Facilities ............................................................................................................... 120
Exhibit J-1 Airport Facilities ....................................................................................................................... 129
Exhibit J-2 Airport Facilities ....................................................................................................................... 132
Exhibit K-1 Calexico School Facilities ........................................................................................................ 138
Exhibit L-1 Healthcare Services & Facilities .............................................................................................. 150
TABLES
Table E-1 City of Calexico Population Projections ...................................................................................... 10
Table LU-1 Developable Land by Land Use ................................................................................................. 24
Table LU-2 Land Use Designation Build Out Density .................................................................................... 25
Table LU-3 Annexation History ................................................................................................................... 25
Table LU-4 A Planned Infill Development ................................................................................................... 26
Table LU-4 B Non-Residential Infill Development Area .............................................................................. 27
Table LU-5 Parcels for Potential Infill Residential ....................................................................................... 27
Table LU-6 Infill and Development Areas as Phased Development ............................................................ 30
Table LU-7 Existing Non-Residential Development .................................................................................... 32
Table LU-8 Equivalent Dwelling Unit Conversion ....................................................................................... 33
Table LU-9 Planned Non-Residential Within City Limits ............................................................................. 34
Table LU-10 Infill and Development Areas as Phased Development .......................................................... 35
Table LU-11 EDU Projections from Active Residential and Non Residential Development........................ 36
Table LU-12 EDU Projections for All Phased Development ........................................................................ 36
Table A-1 Administration Facilities at City Hall ........................................................................................... 39
Table A-2 Administrative Facilities Demand ............................................................................................... 41
Table A-3 Administrative Facilities Increase in Demand ............................................................................. 42
Table A-4 Projected Administrative Costs .................................................................................................. 44
Table B-1 - Support Staff ............................................................................................................................. 48
Table B-2 - Projected Law Enforcement Service Demand .......................................................................... 49
Table B-3 Projected Law Enforcement Phased Demand ............................................................................ 51
Table B-4 Projected Law Enforcement Service Costs ................................................................................. 52
Table C-1 Projected Fire Service Demand ................................................................................................... 58
Table C-2 Projected Phasing of Fire Service Demand ................................................................................. 59
Table C-3 Projected Fire Service Costs ........................................................................................................ 61
Table D-1 Park Facilities City of Calexico Park Space .................................................................................. 63
Table D-2 Projected Parkland Demand ....................................................................................................... 65
Table D-3 Phased Parkland Demand ........................................................................................................... 66
Table D-4 Projected Recreation Cost .......................................................................................................... 68
Table E-1 Projected Library Facility Demand .............................................................................................. 74
Table E-2 Projected Library Construction Cost Demand ............................................................................. 75
Table E-3 Projected Library Item Cost Demand .......................................................................................... 75
Table E-4 Projected Library Service Costs ................................................................................................... 77
Table F-1 Roadway Performance Standard ................................................................................................ 78
Table F-2 City of Calexico Roadway Classifications Standards .................................................................... 79
Table F-3 Roadway Segment Traffic Forecast ............................................................................................. 90
Table F-4 Projected Street Maintenance Costs .......................................................................................... 93
Table G-1 Stormwater Retention Basin Inventory ...................................................................................... 96
Table G-2 Projected Drainage Facilities Costs ........................................................................................... 104
Table H-1 Water Distribution & Fire Flow Standards ............................................................................... 106
Table H-2 Water Treatment Plant Components/Capacity ........................................................................ 108
Table H-3 Water Pipelines ........................................................................................................................ 109
Table H-4 Fire Flow Deficiencies ............................................................................................................... 111
Table H-5 Residential Water Demand Projections ................................................................................... 112
Table H-6 Daily Water Demand Projections with All EDU’s ...................................................................... 113
Table H-7 Projected Water Costs .............................................................................................................. 116
Table I-1 Pipeline Design Criteria .............................................................................................................. 118
Table I-2 Wastewater Treatment Facility ................................................................................................. 119
Table I-2 Sewer Pipelines .......................................................................................................................... 121
Table I-3 Pump Station Inventory ............................................................................................................. 122
Table I-4 Pump Station Adequacy ............................................................................................................. 123
Table I-5 Daily Residential Sewer Flow Projections .................................................................................. 124
Table I-6 Daily Sewer Flow Projections with EDU’s .................................................................................. 124
Table I-8 Projected Sewer Costs ............................................................................................................... 127
Table J-1 Airside Performance Standard ................................................................................................... 130
Table J-2 Landside Performance Standard................................................................................................ 130
Table J-3 Airport Facilities Demand .......................................................................................................... 134
Table K-1 Public School Inventory and Capacity Level .............................................................................. 140
Table K-2 Private School Enrollment and Capacity Level .......................................................................... 140
Table K-3 SDSU Facilities ........................................................................................................................... 141
Table K-4 Services Provided at SDSU ........................................................................................................ 142
Table K-5 Public School Enrollment and Capacity Level ........................................................................... 143
Table K-6 Projected Demand and Unhoused Students ............................................................................. 144
Table K-7 Student Yield ............................................................................................................................. 144
Table K-8 SFNA Factor Student Projections .............................................................................................. 145
Table K-9 Impact Fee Comparison ............................................................................................................ 146
Table FP-1 Administrative Facilities Development Impact Fees ............................................................... 157
Table FP-2 Police Facilities Development Impact Fees ............................................................................. 158
Table FP-3 Fire Facilities Development Impact Fees ................................................................................ 159
Table FP-4 Parks & Recreation Facilities Development Impact Fees ........................................................ 160
Table FP-5 Library Facilities Development Impact Fees ........................................................................... 161
Table FP-7 Potable Water Facilities Development Impact Fees ............................................................... 166
Table FP-8 Potable Water Rates & User Fees ........................................................................................... 166
Table FP-9 Water Impact Fee Comparison ............................................................................................... 167
Table FP-10 Wastewater Facilities Development Impact Fees ................................................................. 168
Table FP-11 Wastewater Rates & User Fees ............................................................................................. 168
Table FP-12 Wastewater Impact Fee Comparison .................................................................................... 169
Table FP-13 Per Capita Comparison .......................................................................................................... 171
FIGURES
Figure 1-A Historic Population Growth 1950-2017 ....................................................................................... 7
Figure 2-B Population Forecast ................................................................................................................... 31
Figure 3-C Peak Factor Graph ...................................................................................................................118
APENDICES
Appendix A - Service Account Calculations
Appendix B - EDU Methodology
Appendix C - Approved Budget 2017/2018
Appendix D - 2018 Water Facilities Master Plan
Appendix E- 2018 Wastewater Facilities Master Plan
Appendix F- 2017 Annual Financial Report
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
I. INTRODUCTION
A. INTRODUCTION & PURPOSE
The City of Calexico was incorporated in 1908 and is loc ated in Imperial County,
California. Calexico is ideally situated on the international border with Mexicali,
Baja California, Mexico which extends unlimited potential for economic growth and
overall development. Calexico’s port of entry is a major entrance point for
thousands of persons as well as large amounts of goods traveling between the two
countries. The City capitalizes on the trade, commerce, culture and energy that
comes with its unique status as an International Gateway City. The staff, City
Manager and City Council, are committed to maintaining a full-service City at
excellent levels of service with high quality facilities and infrastructure. Thus, this
Service Area Plan is structured to provide a basis and framework for current and
continuous service assessment and planning.
Geographic Location
The City of Calexico is located in southern California, 120 miles east of San Diego
and situated directly along the U.S./Mexico International border. The Calexico
community is traversed by two major transportation corridors: Highway 98 at an
east/west orientation and Highway 111 at a north/south orientation. The Southern
Pacific Railroad is also an active transportation corridor that provides for the
international transport of goods and also passes through the City at a north/south
orientation. Please refer to Exhibit 1 - City of Calexico Geographic Location.
Calexico’s geographic situation contributes to a unique sphere of influence and
service demand from temporary residents, permanent residents and travelers alike.
Purpose of the Calexico Service Area Plan
In 1997, Assembly Bill (AB) 1484 established the Commission of Local Governance
for the 21st Century. The role of the Commission of Local Governance was to
evaluate local government organization and operational issues and develop a
statewide vision and determine how the State should grow. In this vein, the Cortese-
Knox-Hertzberg Local Government Reorganization Act of 2000 was put in place and
established procedures for local government changes of organization. The Local
Agency Formation Commission’s (LAFCO’s) powers were expanded for active
participation in regional growth and planning forums and required that spheres of
influences be regularly updated via periodic regional municipal service reviews.
1 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
Exhibit 1 - City of Calexico Geographic Location
2 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
The Calexico Service Area/Municipal Service Review contained herein intends to
assess current service demand and future service needs within the agency’s sphere
of influence, based on anticipated growth. The assessment aims to demonstrate that
future public facilities, for the provision of services, have been identified in
accordance with the Cortese-Knox-Hertzberg Act.
B. SERVICE AREA PLAN REQUIREMENTS
Minimum Contents of Service Area Plans
The requirements of the contents of an up to date service area plan are determined
by the State’s Government Code. Per Government Code Section 56430, LAFCO
shall prepare a written statement of its determinations with respect to each of the
following plan requirements:
1. Growth and population projections for the affected area.
2. The location and characteristics of any disadvantaged unincorporated
communities within or contiguous to the sphere of influence.
3. Present and planned capacity of public facilities, adequacy of public services,
and infrastructure needs or deficiencies including needs or deficiencies
related to sewers, municipal and industrial water, and structural fire protection
in any disadvantaged, unincorporated communities within or contiguous to
the sphere of influence.
4. Present and planned capacity of public facilities and adequacy of public
services, including infrastructure needs or deficiencies.
5. Financial ability of agencies to provide services.
6. Status of, and opportunities for, shared facilities.
7. Accountability for community service needs, including governmental structure
and operational efficiencies.
8. Any other matter related to effective or efficient service delivery, as required
by commission policy.
Disadvantaged Communities
Government Code Section 56430 further requires the identification of location and
characteristics of any disadvantaged unincorporated communities within or
contiguous to the sphere of influence. The capacity and adequacy of infrastructure,
public facilities, and public services must be analyzed for disadvantaged
unincorporated communities, which is defined as an area of inhabited territory
located within an unincorporated area of a County in which the annual median
household income is less than 80% of the area median household income.
According to the State Department of Housing and Community Development (HCD),
Imperial County’s area median income is $59,900 and the disadvantaged household
3 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
income is $47,920 for 2017. A survey of aerial photographs via Google Earth shows
that there are six country homes within the City of Calexico’s sphere of influence and
approximately 22 country homes within a mile of the sphere of influence. These
homes are dispersed from each other and do not meet the definition of an
unincorporated community.
Role of the Imperial County Local Agency Formation Commission
The Imperial County Local Agency formation Commission (IC LAFCO) is charged
with the review and approval of the Calexico Service Area Plan. The Imperial County
LAFCO is comprised of two County Supervisors appointed by the Board of
Supervisors, two City Council members appointed by the City Selection Committee
and one public member approved by LAFCO, for a total of five members. LAFCO
has the authority to review, approve or deny boundary changes, city annexations,
consolidations, special district formations, incorporations for cities and special
districts, and to establish local spheres of influence. The Imperial County LAFCO
must be able to ascertain that there will be sufficient capacity and public facilities,
beyond services provided by the City, to include those services deemed essential but
provided by other, within the requested sphere of influence or any proposed
annexation consistent with the following:
a) In conducting a service review, the Commission shall comprehensively
review all of the agencies that provide the identified service or services within
the designated geographic area.
b) The Commission shall conduct a service review before, or in conjunction with,
but no later than, the time it is considering an action to establish a sphere of
influence in accordance with Section 56425 or Section 56426.5 or to update a
sphere of influence pursuant to Section 56425.
C. CALEXICO SERVICE AREA
The administrative offices of the City of Calexico are located at 608 Heber Avenue in
Calexico. The governing structure consists of a five-member City Council elected by
the public. A City Manager reports directly to the City Council and is charged with
overseeing the City’s operation and employees. The City also has a legal counsel
that reports to the Council and the City Manager. As of 2018, the City operates with
134 employees and had a 2017/2018 Fiscal Year City Wide Budget of approximately
$63 million: General Fund budget of approximately $13.6 million in addition to
Enterprise Funds for Water of $3.9 million and Wastewater of $3.3 million (Source:
City of Calexico Adopted Municipal Budget FY 2017-2018).
Having a comprehensive and reliable Service Area Plan is of utmost importance for
orderly growth and development. The City of Calexico provides a full range of
public services including administration, law enforcement, fire protection, parks and
recreation, library and cultural arts, circulation facilities, stormwater and drainage,
4 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
sanitary sewer, domestic water and airport facilities, all of which are addressed in
this update. Educational services are provided by others but are also addressed in
this Service Area Plan as an essential service for growth and development. Other
incidental services such as solid waste and utility services which are provided by
outside agencies will also be addressed in summary. The proceeding section
provides the organization and structure of material presented.
Status of the City of Calexico 2006 Service Area Plan
The last comprehensive City of Calexico Service Area Plan (SAP) was prepared in
2006 by Albert A Webb and Associates and Hoffman Planning Associates. An
Amendment was subsequently prepared in 2008 which addressed anticipated
changes to the Sphere of Influence to the northeast of Calexico. However, those
projects never advanced and LAFCO did not approve the expanded sphere. There
have been modest changes to growth patterns within the proposed City of Calexico
service area. The 2018 Service Area Plan Update provides a more current analysis
of projected demands and existing public facilities and services in the City of
Calexico and indicates how the demand created by future developments within the
City’s service area would be met for each service and facility within the adopted
sphere of influence.
Calexico City Limits and Existing Sphere of Influence
The legal City limits is uniquely shaped and may be generally described as bounded
by the International Border to the south, All-American Canal and Southern Pacific
Railroad to the west, Jasper Road to north and along the Central Main Canal and JA
Rodney Avenue and All-American Canal to the east side. The City Limits boundary
consists of approximately 5,211 acres (8.1 square miles). The adopted Sphere of
Influence is restricted to the south by the Mexico border and instead expands west to
Hammers Road, north to Jasper Road (with the exception of a narrow strip along
Highway 111 which extends to Heber Road and east to Bowers Road and along the
All-American Canal (refer to Exhibit 2 – City Limits and Sphere of Influence
Boundaries). The entire 2018 Service Area/Sphere of Influence consists of
approximately 10,050 acres of land, 4,311 of which are outside of the City limits.
There are no immediate boundary changes proposed under this 2018 Service Area
Plan Update.
Population History and Demographics
Based on population data available from the US Census Bureau and the State
Department of Finance, the City of Calexico has experienced tremendous population
growth since the 1960’s compared to other local jurisdictions. The City of Calexico
was incorporated in 1908 and had a recorded population of 797 by 1910, and by
1960 the population had grown to 7,992 people per the Decennial Census. During
the period between 1950 through 1990, the average annual growth rate was 4.74%.
5 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
Exhibit 2 - City Limits and Sphere of Influence Boundaries
6 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
The population doubled in the last two decades, going from 18,633 people in 1990 to
38,752 in 2010. The historic 20-year average growth rate, however, has been
3.11%, per the Department of Finance. Figure 1-A depicts historic population
growth within the incorporated city limits from 1950-2017.
Figure 1-A Historic Population Growth 1950-2017
Source: California Department of Finance Population Estimates 2011-2017
Housing sublets and a consistent and robust housing market has been a major factor
to the massive population growth in the City of Calexico. Another significant factor
contributing to the population growth may be attributed to population demographics.
Over 96% of the Calexico population is Latino, according to US Census figures.
Culturally, Latinos tend to share households with extended family members. The
City’s average household size of 4.08 persons per household is significantly larger
than the State’s average household size at 2.97 persons per household (Department
of Finance, Table E-5 Population and Housing Estimates). These statistics are
important in determining the service needs of the Calexico community.
The population growth, however, slowed down since 2010, experiencing only a
0.85% average annual growth rate, according to data from the California Department
of Finance. The Demographic Unit of the Department of Finance releases an annual
estimate of cities’ populations based on the number of building permits issued, as
reported by City staff, for new housing units. In the past seven years, the City only
grew by 2,349 residents from 38,572 people to 40,921. The City of Calexico had a
slower growth average that most other communities in the Imperial County for the
same time period. The County as a whole grew at an average annual growth rate of
1.1% during the same past seven years. El Centro grew by 0.99% per year, while
Brawley grew by 1.09%, and the unincorporated areas of Imperial County grew by
7 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
0.9%. The City of Imperial remained the fastest growing city in the County at an
average rate of 3.41% per year.
As noted, Calexico served an estimated population of 40,921 as of January 2017,
according to the Department of Finance. However, based on actual water service
connections in March of 2018 of 10,224 residential accounts and 4.08 persons per
households, the 2018 population may be best estimated at 41,714 (See Appendix
A-Service Account Calculations). There is only one planned annexation within the
Sphere of Influence as of the date of this Service Area Plan, but the City will continue
to grow as additional residential units are being built within the City Limits in
previously annexed property, not fully built out.
It is projected that by 2040 the City’s population will be 81,770 based on a 20-year
average historic rate of 3.11% which is substantially higher than Southern California
Association of Governments 2016-2040 Regional Transportation Plan estimate for
Calexico of 62,200. These numbers could be augmented after considering the
aforementioned planned annexation and other major infill development projects.
Detailed population trends and projections are further discussed under Growth and
Phasing Projections section of this Service Area Plan.
D. ORGANIZATION AND STRUCTURE OF SERVICE AREA PLAN
The intent of this 2018 Service Area Plan is to demonstrate the City’s ability to
provide adequate services within the sphere of influence boundaries and in response
to new development within the City Limits or from new annexations. An approximate
20-year planning period is used to forecast growth and the estimated facility and
service demands are based on population projections in five-year increments
through 2040. This Service Area Plan discusses the services currently provided by
the City of Calexico, identifies the current demands and estimates the future demand
for such facilities and services, and identifies any need for new facilities and services
to meet population demands.
This document complies with the requirements of Section 56653(b) regarding the
preparation of a plan for providing services (Service Area Plan) and provides the
information necessary for LAFCO to conduct a municipal services review in
compliance with Section 56430. This Service Area Plan document is further
organized into the following six sections that satisfy the Guidelines adopted by the
Imperial County LAFCO:
I. INTRODUCTION AND BACKGROUND: Provides a brief description of the City
of Calexico as well as the general characteristics of the community, Service
Area Plan requirements, including overall content of the Service Area Plan.
II. EXECUTIVE SUMMARY: Provides a brief overview and summary of the services
assessment and conditions identified in the plan and highlights critical
8 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INTRODUCTION & BACKGROUND
information regarding existing facilities, demand, mitigation, their costs, and
anticipated methods of financing.
III. LAND USES AND GROWTH PROJECTIONS: Provides a detailed discussion on
existing and planned land uses in the City’s service areas and describes
potential impacts associated with population growth and projected service
demand.
Buildout and Phasing is also discussed within the 20-year planning period.
The intent of this section is to provide an additional planning tool that may
allow the City to anticipate future public facility needs directly driven by new
development that may be tied to future impact fees.
IV. PUBLIC FACILITIES AND SERVICES: Provides a thorough description of
current and planned facilities and services, and their current and projected
adequacy. The following facilities and services are included in the review:
A. Administrative Services and Facilities
B. Law Enforcement Services and Facilities
C. Fire Protection Services and Facilities
D. Parks and Recreation Services and Facilities
E. Library and Cultural Arts Services and Facilities
F. Circulation and Transportation Services and Facilities
G. Stormwater and Drainage Facilities
H. Water Treatment and Distribution Services and Facilities
I. Sanitary Sewer Collection and Treatment Services and Facilities
J. Airport Services and Facilities
K. Educational Services and Facilities
L. Incidental Services Provided by Others
V. FINANCING PLAN: Identifies and discusses existing and potential sources of
revenue and financing mechanisms for public facilities and services available
to the City. In addition, this section would identify cost saving opportunities in
shared facilities.
9 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
II. EXECUTIVE SUMMARY
This Executive Summary provides a brief overview of population and service demand
findings. The population projections presented herein provide a context for the analysis
and findings introduced for each individual public facility in terms of the performance
standard, existing facilities, existing facility demand versus anticipated future demand,
adequacy and mitigation. Funding sources, annual budget and cost per capita is also
noted in brief, while detailed discussions are held elsewhere within this Service Area
Plan.
A. POPULATION PROJECTIONS
This Service Area Plan uses population projections based on the recent and active
planned development given that anticipated annexations are considered only under
long term development beyond the planning period. Full detail is provided under the
Growth Projections section of this document. The City of Calexico’s 2018 population
was estimated at 41,714 and an average household size of 4.08 persons per
household. The population is expected to increase to 66,912 by 2030 and is
expected to grow to just over 90,000 by the year 2040 when taking into account
approved and active development and not just a historic growth rate of 3.11 percent.
The following table projects the future population of the City of Calexico through Year
2040 in five-year increments under both scenarios. The population would jump to
92,402 by 2040 if all major infill planned development is taken into account and not
just active projects.
Table E-1 City of Calexico Population Projections
Population Projections
Population Projections
Year Including Active Planned
At 3.11% Growth Rate1
Development2
2020 44,346 46,639
2025 51,676 57,421
2030 60,218 66,912
2035 70,171 77,972
2040 81,770 90,860
1 Growth rate based on historic 20 year average per the Department of Finance.
2 Calculated by inserting into natural projected growth realistic number of dwelling units from two
active planned development projects and multiplying by 4.08 person per household.
B. FINDINGS
The service review findings are based on information obtained from existing
reports such as Preliminary Engineering Reports (PER’s), Master Plans,
Infrastructure Studies, Specific Plans, Adopted Budgets, Capital Improvement
10 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Plans, Environmental Studies and discussions with City Staff. The following
facilities and services were reviewed: Administrative Facilities, Law Enforcement
Facilities, Fire Protection, Parks & Recreation Facilities, Library & Cultural
Facilities, Circulation & Transportation Facilities, Storm-water & Drainage Facilities,
Water Facilities, Sanitary Sewer Facilities, Airport Facilities and Educational
Facilities. Findings for each facility/service are summaries in the proceeding tables
with the respective performance standard for the desired level of service and
subsequently describes the corresponding facilities assessment to meet current and
future demands.
Administrative Facilities
Administrative facilities include buildings that house administrative staff and that
provide general administrative services to Imperial residents and the business
community. Examples of administrative services include utility billing and collection,
services to the City Council, planning and development services and other similar
administrative functions of the city.
Administrative Facilities
Performance Standard 500 SF of Building Space/1,000 Population
Existing Facilities City Clerk/Legislative
City Hall/Administration 16,750 SF
HR & Finance
Planning & Engineering
Housing & Development
PW Office Facilities 724 SF
Total 17,474 SF
Existing Demand 2018: 20,857 SF
Adequacy 2018: 17,474 SF Deficient -3,383 SF
Future Demand 2030: 33,456 SF 2040: 45,430 SF
Mitigation By 2040, 27,954 SF shall be added.
Funding Sources Current: Property tax, sales tax, license & permit fees, fines
& penalties, general taxes, service fees and assessments,
and Impact Fees and Measure H.
Future: Continue existing sources
Annual Budget $2,731,541 FY 17/18
Cost Per Capita (2018) $22.43
11 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Law Enforcement Facilities
Police facilities include the police station, and other support facilities and equipment
including patrol vehicles which are owned by the City of Calexico. Police facilities
further includes the staffing level needed to provide law enforcement, traffic control
and crime prevention services.
Law Enforcement Facilities
Performance Standard 1.50 patrol officers per 1,000 population
0.25 volunteers per 1,000 population
1.00 support staff member per six sworn officers
1 vehicles per 2.3 patrol officer
250 SF of building area per FTE
Response Time Under 5 Minutes
26 patrol officers
Existing Facilities &
17 volunteers
Personnel
18 support staff
38,302 SF Police Station(s)
Existing Demand 2018: 62.5 Officers/10 Volunteers/11,000 SF Building
Adequacy 2018: Deficient 36.5 Patrol Officers
Adequate Vehicles/6 Extra Volunteers /
6,444 SF Excess Building Space
Future Demand 2030: 100 Police Officers/44 Vehicles/25,092 SF Facility
2040: 136 Police Officers/59 Vehicles/34,073 SF Facility
Mitigation Continue to monitor the response time and explore
potential for new police or joint station with fire
department. Continue to obtain grants for crime prevention
measures.
Funding Sources Current: General Fund, Meters and Parking Division
Fines, State Funded Programs, and Development Impact
Fees as well as grant funds.
Future: Continue existing sources.
Annual Budget $5,069,530 FY 17/18
Cost Per Capita (2018) $121.53
12 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Fire Protection Facilities
Fire Protection facilities include the fire station, and other support equipment
including firefighting equipment such as fire engines, water tenders, and other
firefighting units. Fire facilities also include the staffing level needed to man and
operate the aforementioned equipment and deliver emergency and fire-protection
services. The City of Calexico also provides ambulance services which are included
as part of emergency response and the overall fire service facilities.
Fire Protection Facilities
Performance Standard Station: 6,500 square feet per 17,900 population
Firefighter: 1.5 firefighter per 1,000 residents
Response Time/Medical Emergencies: <8 Minutes
Response Time/Structural Fires: <7 Minutes
Fire Protection Facilities: 9,238 SF
Existing Facilities &
Fire Firefighters: 24
Personnel
Response Time: Met
Existing Demand 2018: Facility:15,147 SF/Firefighters: 62.5
Adequacy 2018 Deficiency: 2018 Adequacy:
-5,909 SF Facility Response Time < 6 Minutes
-38.5 Fire Fighters
Future Demand 2030: 24,298 SF Facility/100 Fire Fighters
2040: 32,994 SF Facility/136 Fire Fighters
Mitigation To address increased demand, new personnel should be
incrementally added, and an additional fire station planned
for. A Master Plan for Fire Protection Facilities should be
initiated, and a Volunteer Firefighter Program considered.
The City should also move forward with approved
increases to ambulance service and paramedic staffing.
Funding Sources Current: General Fund, property tax, sales tax, Measure
H, Development Impact Fees and State Grant Sources.
Future: Continue existing sources and explore a special
fire suppression assessment district.
Annual Budget $4,242,864 FY 17/18
Cost Per Capita (2018) $101.71
13 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Park and Recreation Facilities
Parks and recreation facilities include open space areas, both improved and
unimproved for the purpose of recreational use. Facility amenities within the parks
may include swings, slides, picnic areas and shade structures for the use of the
public. Ball fields and open Space areas that serve a dual use as retention basin and
thus owned and maintained by the City of Calexico are also included under this
discussion.
Park & Recreational Facilities
Performance Standard 3 Acres of Parkland/1,000 Population
Existing Facilities 77.73 Acres
Existing Demand 125.14 Acres
Adequacy 2018: -47.41 Acre Deficiency
Future Demand 2030: 201 Acres
2040: 273 Acres
Mitigation Continue to allow developers to dedicate parkland and/or
pay the applicable Development Impact Fees. Also
continue to pursue State and Federal Grant resources and
advance plans to improve the New River open space area.
Funding Sources Current: General Fund, property tax, sales tax,
Development Impact Fees and Measure H.
Future: Continue existing sources and explore a
Community Facilities District, and State Grants.
Annual Budget $744,909 FY 17/18
Cost Per Capita (2018) $17.85
14 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Library & Cultural Arts Facilities
Library facilities include the library space and technological center as well as all the
contents of the library and center, as well as the Staff that manages the facilities and
services provided. It also includes any support equipment such as computers, copy
machines, and other office equipment that may be available to the general public.
Library & Cultural Arts Facilities
Performance Standard Facility: 0.55 SF of Building Space per resident
Personnel: One (1) librarian/(2) clerical per 6,000 residents
Inventory: Three (3) items per resident
Existing Facilities Facility: 17,164 SF
Personnel: Five (5) staff members
Inventory: 58,652 library items
Existing Demand Facility: 22,942 SF
Personnel: 20 staff members
Inventory: 125,142 library items
Adequacy 2018 Deficiency: -5,778 SF Facility Deficit
- 15 Staff Members Deficit
- 66,490 Inventory Deficit
Future Demand 2030: 36,802 SF Facility/200,736 items
2040: 49,973 SF Facility/272,580 items
Mitigation The City of Calexico should pursue grant funding from
State, Federal, and non-profit programs to address
deficiencies.
Funding Sources Current: Grant funds, Property tax, sales tax, nominal late
fees, Measure H and Development Impact Fees.
Future: Continue existing sources and pursue grant
sources for capital needs.
Annual Budget $754,903 FY 17/18
Cost Per Capita (2018) $18.09 per capita
15 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Circulation and Transportation Facilities
Transportation facilities consist primarily of roadways (including pedestrian facilities),
bridges and traffic lights, including all local and state-owned roadways.
Transportation facilities may also include transit facilities such as bus stops and other
transit stations. The City of Calexico maintains over ninety-seven (97) miles
(Source: 2018 ICTC records) of roadways and strives to maintain a level of service
above a “C” Service level which at minimum operates with average delays occurring
but having stable operation. The City also has minimum adopted standards and any
roadways not meeting the standards would be earmarked for improvement to
designed capacity.
Circulation and Transportation Facilities
Performance Standard Level of Service “C” or Better
97+ Lineal Miles of Roadway
Existing Facilities
22 Bridges
9 Traffic Signals at Controlled Intersections
Existing Demand All facilities operating at LOS C or better
Roadway Operation: All operating at LOS C or Better.
Adequacy
Roadway Deficiency: PCI index of 50-60 (AT Higher Risk).
Traffic Signals: All Operating at LOS C or Better.
Bridge Deficiency: Seven (7) in Poor Condition.
Pedestrian Facilities: Sidewalk Gaps Exist.
Future Demand 2030: Street Widening and Improvements Needed
2040: Street Widening and Signalization Needed
Mitigation Continue to require fair share contributions from
developers and offsite improvements. Require a traffic
study where new development will generate over 5,000
vehicle trips per day to determine fair share.
Current: Local Transportation Funds, Local Sales Tax,
Funding Sources
State Highway Funds, and Federal Highway Funds as well
as Development Impact Fees, Motor Vehicle In-Lieu Fee,
LTA Measure D, and Transportation Development Act
Article 3/Article 8e.
Future: Continue existing sources and explore the use
of a variety of transportation grant funding programs.
Annual Budget $597,480 FY 17/18
Cost Per Capita (2018) $14.32
16 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Storm-Water & Drainage Facilities
Storm-water and drainage facilities include facilities that carry off excess water and
more specifically for the purpose of conveying stormwater during storm events.
These include curb and gutter along streets, catch basins within improved
developments, retention basins, and canal drains. Drainage facilities on occasion
may include pump stations. These facilities are largely City owned facilities that
convey stormwater runoff into the main water drainage system managed by the
Imperial Irrigation District (IID).
Stormwater and Drainage Facilities
Performance Standard City of Calexico Design Standards, NPDES Requirements,
IID Discharge Requirements, FEMA and Colorado River
Basin Water Quality Control Plan.
Existing Facilities 8 Pump Stations
11 Retention Basins
Existing Demand Developer Driven
Adequacy According to the City of Calexico Public Works
Department Manager the current stormwater system
provides adequate conveyance of stormwater for events
up to a 50-year storm.
Future Demand To be determined based on the rate and type of new
development assessed at the time of plan review.
Mitigation All future development shall be required to construct storm
drain facilities in accordance with the design standards of
the Engineering Department and the IID. The City should
establish a policy for the collection of assessments via a
CFD or CSD for the ongoing operation and maintenance
cost of retention basins.
Funding Sources Current: General fund, sales tax, property tax, developer
investment.
Future: Continue existing sources and implement
Community Facility Districts as necessary.
Annual Budget $10,000 FY 17/18
Cost Per Capita (2018) $0.24
17 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Water Treatment and Distribution Facilities
Water treatment and distribution facilities include the City of Calexico’s Water
Treatment Plant and the distribution pipelines that convey potable water to
residences and business within the service areas and all necessary storage tanks
and pump stations to accommodate flow demand. Water facilities also includes fire
hydrants throughout the community to adequately address fire flows.
Water Treatment and Distribution Facilities
Performance Standard Water Treatment: 125 per person per day
Water Storage: Maximum Day Demand + 25%
Distribution: Minimum Pressure of 20 psi
Maximum Velocity 8fps
Flow Criteria: SF Residential 1,000 GPM
Commercial 2,000 GPM
Industrial 2,500 GPM
Existing Facilities 12 MG Water Treatment Plant
16 MG Treated Water Storage Tanks
103 Miles of Water Distribution Pipelines (2”-30” diameter)
Existing Demand 7.15 MGD (2017 average daily flow demand)
10.60 MGD Peak Demand (2017)
11.25 MGD Storage Demand
Adequacy Water Treatment Operating at 88% Peak Capacity
Water Storage Tanks at 70% Capacity
Distribution Line Deficiencies Exist
Future Demand 2030: 11.2 MGD ADD (16.8 MGD MDD)
2040: 14.2 MGD ADD (21.3 MGD MDD)
Mitigation Capital Improvements identified in the Water Master Plan
should be properly planned for.
Significant revenue loss shall be addressed (difference
between treated water and metered water).
Funding Sources Current: Water service charges and water capacity
(impact) fees.
Future: Continue to use existing sources as explore State
and Federal loan programs.
Annual Budget $4,880,322 FY 17/18
Cost Per Capita (2018) $116.99
18 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Sanitary Sewer Collection and Treatment Facilities
Wastewater treatment and sewer facilities include the City of Calexico Wastewater
Treatment Plant and the sewer collection system that collects and conveys the
wastewater to the wastewater treatment plant. Sanitary Sewer Facilities also
includes various sewer lift stations that are owned and maintained by the City of
Calexico.
Sanitary Sewer Collection and Treatment Facilities
Performance Standard Treatment Not To Exceed NPDES Permit Limits
Meet all Discharge Requirements of RWQCB.
Collection Pipeline Flow < 75% of Design Capacity
Existing Facilities Wastewater Treatment: 4.3 MGD
Pumping/Lift Stations: 11 Stations
Conveyance System: 483,849+ Lineal Feet of Pipelines
Existing Demand Average Flow: 2 MGD (2017)
Peak Flow: 3.1 MGD (2017)
Adequacy Wastewater Treatment: 72% Peak Capacity.
Existing facilities and equipment are over thirty years old
and at the end of their service life.
Collection Line Deficiencies Exist
Future Demand 2030: 5.69 MGD Flow Demand
2040: 7.72 MGD Flow Demand
Mitigation The City shall complete a Wastewater Master Plan to
assess alternative treatment methods and
recommendations for capital investment.
Funding Sources Current: The primary sources of revenue are development
impact fees and user fees.
Future: Continue to use existing sources.
Annual Budget $5,359,465 FY 17/18
Cost Per Capita (2018) $128.48
19 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Airport Facilities
The Calexico International Airport (CXL) is a 257-acre, publicly-owned facility and
serves the needs of local and county-wide population. Airport facilities are those
facilities owned by the City of Calexico and managed by the Public Works
Department for the Calexico International Airport. Airport facilities include
components such as runways, taxiways, terminals, gates, and access roads.
Airport Facilities
Performance Standard None Established
Landside Facilities
Existing Facilities
• One 1,200 SF Terminal Building
• One 2,160 SF Public Restaurant
• 20,000 Gallons of Underground Fuel Tanks
• Two Tanker Fuel Trucks to Serve Aircraft
• 16 Spaces/23,675 SF of Hanger Buildings
• 17 Hanger Tie Downs/84 Paved Aircraft Tie Downs
Airside Facilities
• One (1) Asphalt Runway 4,679 LF in Length
• One 400’-wide Taxiway A
• Four (4) Right-angle Exit Taxiways
Existing Demand 2018: 26 Based Aircraft
85 Aircraft operations per week (4,420 per year)
Adequacy Adequate
Future Demand 2030: 29 Based Aircraft
4,902 Aircraft operations per year
2040: 31 Based Aircraft
5,309 Aircraft operations per year
Mitigation The City is to develop goals to guide policy related to the
growth of the airport and update the 2002 Airport Master Plan.
Funding Sources Current: The Airport is a self-budgeted facility operated by the
Calexico Public Works Department using revenue from product
sales, fees collected and State grants.
Future: State Grant programs through the Department of
Transportation Aeronautics Division. Local Airport Loan
Account through the California Department of Transportation.
Annual Budget $358,000 was budgeted 17/18 for operating costs
Cost Per Capita (2018) No per capita costs/self-budgeted
20 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EXECUTIVE SUMMARY
Educational Facilities
Educational facilities are not owned and maintained by the City of Calexico.
Educational facilities and services are primarily provided by the Calexico Unified
School District and the local San Diego State University Branch. The total
educational facilities in Calexico consist of seven elementary schools, two junior high
schools, two high schools, one continuation school, three private schools, and a
State university branch. The Calexico Unified School District is over capacity at the
junior high and high school levels and is under capacity at the elementary school
level by 295 students. Under these conditions, construction of a new middle school
and high school is recommended by the School Facility Needs Assessment
completed in 2017. However, there were no current approved plans for new facilities
or construction of classrooms as of the date of this 2018 Service Area Plan.
Healthcare
The City of Calexico did not have an operational hospital as of 2018, however,
numerous healthcare services and facilities are extended to Calexico residents,
including two urgent care centers. Currently, the demand for care is significantly
increasing due to a growing consumer base, an aging population, and a changing
marketplace. These conditions obligate residents to travel outside of the City for
extended hospital services to one of the two hospitals in the Imperial County. The
City of Calexico has plans for a Mega Park Development consisting of 156 acres of
mixed use commercial and industrial and is to include 166,000 square feet of
healthcare service facilities. This planned Health Services Center is anticipated to
meet the much-needed demand of the Calexico Community if and when it comes
into fruition.
21 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
III. LAND USES, GROWTH PROJECTIONS AND PHASING
The City of Calexico would like to continue to foster the aggressive yet orderly growth and
development in the City and throughout its Sphere of Influence. It is the intent of the City
to plan for growth in a sustainable manner planning for both the extension of services and
facilities within the City’s Sphere of Influence. Orderly development is accomplished
through planned improvements, phasing of service expansion consistent with phased
development projects. This section of the Service Area Plan identifies the existing land
uses, the availability of developable land, the planned land uses, and the anticipated
population growth, all of which are critical factors on how the City will adequately service
the community.
A. LAND USES AND ANNEXATION AREAS
Land Uses
A land use overview was conducted for all areas within the City Limits and within
the City’s Sphere of Influence in 2018 by The Holt Group, Inc and in consultation
with City staff for the assessment of potential residential land use development
opportunities. This document incorporates those land use findings and an inventory of
additional non-residential land use designations available for development. The City of
Calexico 2015 General Plan land use designations were used to determine the
available acreage for each type of land use and the future development potential for
all vacant and underutilized land. These land use designations are the basis for
establishing ultimate service demand. Please Refer to Exhibit 3 - General Plan Land
Use Map, which depicts the City’s adopted land use designations. There was one
recent General Plan Land Use Amendment which was updated and noted in the Land
Use Map.
Findings determined that within the established City of Calexico jurisdiction and
Sphere of Influence, there is ample opportunity for land development. Over 1,300
acres are vacant and undeveloped within the incorporated City limits with infill
potential. This inventory includes, but is not limited to, proposed developments such
as La Jolla Palms (a residential/commercial use development which was only at 50%
built out in 2018), Palazzo Subdivision (a residential/commercial development), Las
Palmas (residential land use, currently under construction), and a number of other
developments previously approved by the City but pending construction. Additionally,
another estimated 3,900 acres of vacant and undeveloped land are within potential
annexation areas in the Sphere of Influence for over 5,000 acres of developable land.
22 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Exhibit 3 - General Plan Land Use Map
23 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Approximately 2,720 acres of developable areas are classified as Residential Specific
Plan Areas in the Sphere of Influence. Specific Plan Areas allow for a more
comprehensive approach to land use planning. This section will further inventory the
available by residential and non-residential acreage and by land use designation
within the City Limits and outside the City boundaries and within the Sphere of
Influence. Table LU-1 identifies the full inventory of land available within the City of
Calexico Service Area.
Table LU-1 Developable Land by Land Use
Total
Available Available
Available
Acres Acres
Land Use Designation Acres in
Within Outside City
Service
City Limits Limits/SOI
Area
Airport 0 0 0
Commercial Highway 224 300 524
Commercial Neighborhood 3 0 3
Commercial Core Mixed Use 2 0 2
Industrial 545 0 545
Industrial Specific Plan 0 0 0
Public Facility 58 170 220
Business Park 34 0 34
Open Space 30 188 218
OS w/Airport Expansion Overlay 0 565 565
Low Density Residential 349 0 349
Medium Density Residential 37 0 37
High Density Residential 84 0 84
Residential Specific Plan 0 2,720 2,720
TOTALS 1,366 3,943 5,301
Source: City of Calexico General Plan Land Use Map used for Land Use Designations and Record General Plan
Amendments Google Earth and Field Survey used for Acreage calculations-April 2018.
Land Use Densities
Land Use restrictions are a significant factor affecting population growth and service
demand. The City’s residential land use designations provide for a wide range of
development opportunities. Density limits support single-family dwellings, mobile
homes, manufactured housing, condominiums, and multi-family units. These
opportunities are offered at various densities as noted in the proceeding Table LU-2.
Under High Density Residential, the City plans for Residential Condominium (RC) and
Residential Apartment (RA).
24 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Table LU-2 Land Use Designation Build Out Density
Maximum Dwelling
Land Use Designation
Units Per Acre
Low Density Residential 7.26
Medium Density Residential 5.1-12
High Density Residential (RC) 12-30
High Density Residential (RA) 20-30
Source: City of Calexico Land Use Element, 2015
Annexation History
The City experienced significant annexations during the housing boom of the 2000’s
which were captured under the 2006 Service Area Plan. According to the Imperial
County Local Agency Formation Commission (LAFCO), four (4) annexations have
been approved and recorded for the City of Calexico since the 2006 Service Area
Plan. Although several applications were filed during this timeframe, seven
applications were withdrawn. The current and historic annexation applications through
LAFCO are depicted in Table LU-3. Only one annexation application is pending
processing, which is Palazzo.
Table LU-3 Annexation History
Year Approximate Annex Year
Proposed Annexation Area
Filed Acreage¹ or Status
2004 El Portal (CX 1-04) 154 acres 2007
2004 Venezia (CX 2-04) 137 acres 2007
2004 Los Lagos (CX 3-04) NA Closed
2004 Clifford Douglas (CX 5-04) NA Closed
2004 Las Ventanas (CX 6-04) NA Closed
2004 Riverview Condos (CX 7-04) 33 acres 2008
2005 La Estrella (CX 1-05) 150 acres 2010
2006 Palazzo Subdivision (CX 1-06) 155 acres Pending
2006 Rancho Diamante (CX 2-06) NA Closed
2006 Esmerelda (CX 3-06) NA Closed
2006 Viva Calexico (CX 4-06) NA Closed
2007 Calexico USD (CX 2-07) AN Closed
Source: Imperial County Local Agency Formation Commission, April 2018.
¹Acreages may include non-residential areas such as parks and schools.
25 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
According to LAFCO all of the annexation applications previously filed are now
closed, with the exception of Palazzo Development. LAFCO anticipates that the
Palazzo Development annexation will be processed as soon as the Calexico Service
Area Plan 2018 Update is approved by the City and LAFCO. The Palazzo
Development will continue to be discussed under future annexation areas and
considered for development and growth projections as appropriate.
a) Planned In-Fill Development and Future Annexation Areas
Planned Infill Development
As previously noted, the City of Calexico has ample opportunities for infill
development within the City limits with over 700 acres designated for residential
development and over 650 acres planned for non-residential development
(commercial/industrial/institutional). Table LU-4 A below identifies all current, or
previously planned development within incorporated areas that could come into
fruition if a change in the housing market results in an increase demand for infill
residential development. Table LU-4 B follows with non-residential infill potential.
Table LU-4 A Planned Infill Development
Approximate Anticipated
A. Residential Infill Development Area1
Acreage Buildout
Remaining
Las Palmas Subdivision Single Family 62.90 3-5 years
La Jolla Palms 56.31 20+ years
Palazzo Subdivision Single Family 37.47 20+ years
Palazzo Multi Family 59.24 20+ years
Tierrasanta Single Family Homes 21.60 20+ years
Tierrasanta Multi-Family Home 12.90 20+ years
Venezia 40.00 20+ years
Remington Condominiums 20.00 20+ years
Las Palmas MHP 11.00 3-5 years
El Portal Subdivision Single Family 146.38 3-5 years
El Portal Multi-Family 17.50 5-10 years
Riverview Condominiums 24.50 20+ years
Estrella Subdivision Single Family 96.51 20+ years
Estrella Multi Family 20.05 20+ years
Estrada Trust Residential Development 33.09 5-10 years
Las Praderas Development 3.01 3-5 years
Total 662.46
Source: Adopted 2006 Service Area Plan, 2015 Land Use Element, Calexico Planning Department (2018)
26 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Table LU-4 B Non-Residential Infill Development Area
Approximate
Anticipated
B. Non-Residential Infill Development Area Acreage
Buildout
Remaining
Gran Plaza Phase 23 100.00 3-5 years
La Jolla Palms (Commercial Portion) 26.00 20+ years
Hallwood Place 232.00 10-20 years
Riverview Condominiums (Commercial Portion) 6.14 20+ years
Venezia (Commercial Portion) 12.67 20+ years
Town Center Industrial Park4 132.00 20+ years
Calexico Mega Park (Scaroni)5 157.00 20+ years
West End Port of Entry 7.30 3-5 years
Estrada Commercial Development 3.96 3-5 years
Open Space/Parkland Related to Subdivisions 36.40 10-20 years
Total 719.87
Source: Adopted 2006 Service Area Plan, 2015 Land Use Element, Calexico Planning Department (2018)
Many of the noted developments have expired Tentative Tract Maps that may or
may not fall within the statute of limitations for extensions. Development areas
that have not been previously planned or officially approved under a specific
development are included in the following table and were identified under the
2015 Land Use Element by assessor parcel only, and as “In-Fill Sites.”
Table LU-5 Parcels for Potential Infill Residential
Other Residential Infill Area Approximate Projected
By Assessor Parcel Number Acreage Buildout
059-455-001; 059-455-002 4.22 20+ years
058-832-016 6.53 20+ years
058-853-001; 058-853-002 9.85 20+ years
059-180-025; 059-180-029; 059-180-035 79.40 20+ years
059-010-032; 059-010-037 76.10 20+ years
Total 176.10
Source: 2015 Land Use Element & 2018 City of Calexico Planning Staff
These vacant parcels, however, have not been identified by the Calexico Planning
Department as having a reasonable infill potential within the 20-year planning
period of this Service Area Plan (Mr. Mark Vasquez, May 2018.
27 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Future Annexation Areas
Outside of the current City limits there is only one area assumed for potential
annexation and development although other annexations may be requested within
the next twenty (20) years depending on the development market. The proposed
annexation area is Palazzo Development which has an open application through
LAFCO. The Palazzo Annexation was initiated in 2006 but is pending annexation
upon completion of the 2018 Service Area Plan. The City no longer considers this
project as being active, but LAFCO does consider the project as open given that
the developer has not withdrawn the project and may proceed with annexation
upon approval of the 2018 Service Area Plan update. For the purposes of
determining future demand, the same number of dwelling units as originally
proposed have been used, however, the buildout timeline was projected to be
beyond 20 years and not factored to demand within this planning period.
b) Phasing of Development
The phasing of multiple growth areas provides a pattern and estimate for where
and when development within the areas of infill and annexation may occur.
This section provides City leadership with an estimated phased growth and
pattern that can be strategically planned for. For the purpose of this
assessment growth areas have been distinguished by short term development
(under five years), midterm development (five to ten years) and long-term
development (ten to twenty years).
Although phasing is difficult to predict with precision, projecting is critical for the
adequate planning of public facilities to ensure that the level of service
standards is continually met. It becomes more difficult to predict phasing beyond
the ten-year mark, thus in summary most of the residential growth was projected
within the 10-year plan or beyond 20 years. The phasing of dwelling units of all
planned development is further summarized under Table LU-6 by infill or
annexation area and phasing term. All development areas within a 20-year time
frame are also depicted in Exhibit 4 - Infill and Development Areas.
Of all of the identified infill projects, only two are currently active projects: El Portal
Subdivision and Las Palmas Subdivision. El Portal, which is proposed as 627
single-family homes and 17.5 acres of multi-family residential, is currently going
through the entitlement process. Las Palmas is currently under construction with
330 single-family homes and 136 mobile-home units. The City anticipates a
buildout horizon for the single-family homes is five years and the multi-family
homes projected to be completed in 10 years. The West Port of Entry is the only
non-residential active project. These active projects will be considered for all
realistic service demand projections above the 3.11% growth rate, while all other
planned infill development will be referred to only under unlikely scenarios.
28 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Exhibit 4 - Infill and Development Areas
29 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Table LU-6 Infill and Development Areas as Phased Development
Development/
Area Phasing
General Land Use
1 El Portal Subdivision SF 3-5 yrs.
2 Las Palmas MHP 3-5 yrs.
3 Estrada Commercial Development 3-5 yrs.
4 Las Praderas Development 3-5 yrs.
5 Gran Plaza Phase 23 Comercial 3-5 yrs.
6 West End Port of Entry 1-2 yrs.
Short Term Subtotal <5 Years
2 Las Palmas Subdivision SF 5-10 yrs.
7 Estrada Trust Development 5-10 yrs.
8 Town Center Industrial Park4 5-10 yrs.
9 El Portal Multi-Family 5-10 yrs.
Mid Term Subtotal 5-10 Years
10 Mega Park (Scaroni) 10-20 yrs.
11 Hallwood Place 10-20 yrs.
Long Term Subtotal 10-20 Years
Source: 2015 Land Use Element Updated in 2018 via Calexico Planning Department Staff
B. GROWTH PROJECTIONS
It is projected that future growth for Calexico during the 2018 SAP planning will largely
occur within the incorporated City Limits. The housing market is so unpredictable that
projections will again largely rely on the historic growth rate and the three active
development projects, more heavily than on all planned infill development. The
proceeding sections provide an overview of the City’s growth projections for
development areas keeping these factors in mind.
1. Residential Growth Projections
The residential growth projections for the two active residential projects provide
the anticipated future residential development based on the most current land use
designations and their allowable densities, as previously discussed. Residential
growth projections have assumed the maximum densities allowed. Additionally,
an 80% realistic maximum development ratio has been applied for population
projections within single-family residential zones (R-1 and Residential Specific
Plan Areas). This discounted density is a conservative calculation in order to
discount for land areas that will not have residential use because those areas
more than likely will be used for public improvements such as roadways, parks,
retention basins, and other similar facilities that impact the developable land ratio.
Each dwelling unit was then multiplied by the average household size. An average
household size of 4.08 persons per household was used as per the most recent
30 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Department of Finance Data. The growth projection scenarios were evaluated: 1)
population based on natural growth rate or 3.11% as per the 20-year average
historic growth; 2) population projections based on active development projects
and the natural growth rate of 3.11%; and 3) population projections based on all
planned infill development projects within planning period as phased.
Figure 2-B Population Forecast
Source: The Holt Group analysis, based on average growth rate over the last 20 years and currently active
projects. Active Development is that under entitlement/construction as of June 2018. All planned development is
based on 2015 Land Use Element Infill Potential and Calexico Planning Department 2018 Updates.
2. Non-Residential Development Growth Projections
Non-Residential growth projections are important factors for service demand to
water and sewer facilities. Non-residential projects include government
operations, industrial, business/office use, and commercial land uses which
although impact most community facilities and services, directly impact water
demand and sewer service demand. The methodology for obtaining existing and
future non-residential square footage is similar to that of the residential projections
in that a coverage factor is assigned to account for roadway dedication in
undeveloped parcels.
a) Existing Non-Residential Development
Inside City Limits - Nearly half of all land (2,202 acres) in the City of Calexico
is zoned for non-residential land uses, and only 60% (1,316 acres) of those
are developed. The following is a tabulation of all developed non-residential
uses within the existing city boundaries.
31 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Table LU-7 Existing Non-Residential Development
Non-residential Zoning Total Developed Acres
CH Commercial Highway 336.4
CN Commercial Neighborhood 17.1
CS Commercial Specialty 37.1
IND Industrial 197.1
IR Industrial Rail Served 141.7
IL Light Industrial 0
BP Business Park 0
Government/Open Space 3.6
Other Unmetered/Open Space 583.0
Total 1,316
Source: Calexico Zoning Map including 2018 Amendments.
Outside City Limits - The City does not provide any services outside its
current incorporated boundaries except for Camarena Junior High School on
East Rivera Avenue. However, there are a number of industrial areas within
the Sphere of Influence just outside the City’s western limits totaling 134 acres
that may be connected to City facilities in the future and receive City services.
b) Non-Residential Development Conversion to Equivalent Dwelling Units
All non-residential development must be assessed on an equal level as
residential development, thus Equivalent Dwelling Units (EDU) are established
as a means of measurement. An equivalent dwelling unit is a unit of measure
for the water consumed or sewer discharged from a particular structure or use.
The volume/value of one equivalent dwelling unit is equal to the same amount
of water consumed or sewer discharged by a single dwelling unit. The EDU
value was determined by assessing the actual daily volume of gallons for all
dwelling units and dividing by the total number of dwelling units. The average
daily water consumption for each land use was based on actual meter
readings in 2017. The usage was then converted to EDU usage. (See
Appendix B - EDU Methodology).
All residential accounts were calculated based on water meter readings
provided by the City of Calexico for single family and multi-family residential.
These readings were then added together to come up with the average water
consumption of 430 gallons per EDU The water consumption figures for all
non-residential uses was calculated based on the total acreage of all non-
residential uses to determine an EDU per acre for each non-residential zone
as shown in the Table LU-8. Please note that there is a significant
discrepancy between total gallons of water treated at the water plant and
water meter readings. Thus, there is a significant revenue loss of
approximately 1.99 million gallons of water per day. (See Appendix B - EDU
Methodology).
32 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Table LU-8 Equivalent Dwelling Unit Conversion
Total Total Total
Non-residential Zoning Gallons in Developed Existing EDU/acre¹
2018 Acres EDU’s
CH Commercial Highway 188,122 336.4 437.5 1.3
CN Commercial Neighborhood 15,708 17.1 36.5 2.1
CS Commercial Specialty 65,001 37.1 151.2 4.1
IND Industrial 45,329 197.1 105.4 0.5
IR Industrial Rail Served 49,966 141.7 116.2 0.8
IL Light Industrial 0 0 0 0
BP Business Park 0 0 0 0
Open Space/Government 28,648 3.6 66.6 18.5
Other Unmetered/Open Space 1,988,840 583.0 4,625.2 7.9
Total 2,381,614 1,316.0 5,538.6
¹One EDU is equivalent to 430 gallons (Refer to Appendix B)
c) Future Non-Residential Growth Projections
Most of the non-residential parcels are considered planned infill projects and
are readily available for development given the proximity and availability of
infrastructure such as water lines and sewer lines. In those cases where no
further subdivision of parcels is required, the total area is multiplied by the
equivalent dwelling unit to determine future demand. This is particularly true of
all commercial zones and light industrial zones. In large tracts of industrially
zoned properties where parcels may be further subdivided, a vacant coverage
factor of 30% is utilized. This accounts for reductions of buildable land area
for street and utility land dedications that essentially decrease the amount of
square footage that can be developed. There is only was non-residential
project considered active which is the West Port of Entry.
Future Non-Residential Acreage in City Limits
The future nonresidential acreage within the City limits was estimated to
be over 1,500 acres. The current active projects contain 7.30 acres of
Commercial Highway development and 1.95 acres of open space park. It is
further estimated that another 692.07 acres of future non-residential acreage
should be planned for as per the previously noted Planned Infill Development
Areas which includes parkland tied to subdivisions or City open space projects.
Table LU-9 identifies the total EDU’s attributed to the Planned Infill
Development Areas, however, only the 7.3 acres at the West Port of Entry and
1.95 acres of parkland will be factored when projecting demand under water
services and sewer services as active development.
33 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Table LU-9 Planned Non-Residential Within City Limits
Acres In Total EDU’s
Planned EDU’s for All Active
Total
Zone Infill & Per & Planned
Acres
Active Acre Infill
Development Development
Commercial Highway 521.13 417.301 1.3 542.5
Commercial
82.51 3.96 2.1 8.3
Neighborhood
Commercial Specialty 74.00 0.00 4.1 0.0
Light Industrial 63.00 63.00 0.5 31.5
Industrial 320.00 0.00 0.5 0.0
Industrial Rail Served 502.00 132.00 0.8 105.6
Business Park 16.00 16.00 0.8 12.8
Open Space/Government 3.60 0.00 18.5 0.0
Parkland for Future
583.00 69.062 7.9 545.57
Development Projects
Total 2,165.24 701.32 1,246.28
Source: The Holt Group, Inc EDU Conversion per Appendix B.
1 Includes 7.3 acres of active development.
2 Includes 1.95 acres of parks and other open space areas as part of active development with the
remainder for future, planned infill development related to planned subdivision projects and City-
owned undeveloped parkland to be built out during the 20-year planning period.
Future Non-Residential Acreage in Annexation Areas
As previously noted, the only annexation anticipated during the planning
period is the Palazzo Annexation. According to the LAFCO documents the
Palazzo annexation proposed to include 5.31 acres of commercial use (office
and retail space) and a 21.53-acre Regional Park. According to the Calexico
Planning Department, construction of the Palazzo Development is not
anticipated to occur within the 20-year planning period and thus will not be
factored into any of the future demand projections.
C. PHASING OF EQUIVALENT DWELLING UNITS & BUILDOUT
In order to adequately project demand on services, all planned residential and
non-residential development needs to be phased as equivalent dwelling units.
This is particularly true when projecting water demand and sewer treatment and
demand.
1. Phasing of Equivalent Dwelling Units
All reasonable planned development needs to be phased as equivalent
dwelling units in order to adequately forecast demand on services. Table LU-
10 depicts the timing of planned development for both residential and non-
34 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
residential development within the next 20 years.
Table LU-10 Infill and Development Areas as Phased Development
Development/ Realistic
Area General Land Use Acres Phasing EDU’s ¹
1 El Portal Subdivision SF 146.38 3-5 yrs 627.00
2 Las Palmas MHP 11.00 3-5 yrs 136.00
3 Estrada Commercial Development 3.96 3-5 yrs 8.32
4 Las Praderas Development 3.01 3-5 yrs 60.00
5 Gran Plaza Phase 23 Commercial 100.00 3-5 yrs 130.00
6 West End Port of Entry 7.30 1-2 yrs 9.49
Short Term Subtotal 271.65 <5 Years 970.81
2 Las Palmas Subdivision SF 62.90 5-10 yrs 330.00
7 Estrada Trust Development 33.09 5-10 yrs 318.00
8 Town Center Industrial Park4 132.00 5-10 yrs 105.60
9 El Portal Multi-Family 17.50 5-10 yrs 315.00
Mid Term Subtotal 245.49 5-10 Years 1,068.60
10 Mega Park (Scaroni) 157.00 10-20 yrs 145.70
11 Hallwood Place 232.00 10-20 yrs 301.60
Open Space 69.06 10-20 yrs 545.57
Long Term Subtotal 458.06 10-20 Years 992.87
GRAND TOTAL 975.20 3,032.28
¹Methodology: For the acreage in each development was multiplied by the maximum density allowed for the
corresponding land use and by 80% to discount roadways, landscape (or parks for residential) and retention
basins. Non-Residential development was calculated as EDU’s (See Appendix B).
As noted in Table LU-11, the total residential Equivalent Dwelling Units for
each planning period, planned residential population growth, is converted to
Equivalent Dwelling units at a ratio of 4.08 persons per household. For future
projections, 125 gallons per capita per day (gpcd) or 510 gallons per EDU
were applied to allow a buffer from the current water demand of approximately
105 gpcd or 430 gallons per EDU. This number was used instead of the
industry standard of 150 gpcd to account for water savings resulting from
ongoing water conservation efforts.
35 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAND USE & GROWTH PROJECTIONS
Table LU-11 EDU Projections from Active Residential and Non Residential
Development
EDU’s From Non
Population at
EDU’s From Residential
3.11% Growth Total
Residential Natural Existing and
Year Rate, plus Natural/Active
and Active Active
Active EDU’s
Development Development +
Development
Unmetered¹
2018 41,714 10,224 914 + 4,625 15,763
2020 46,639 11,431 939 + 4,625 16,995
2025 57,421 14,074 939 + 4,625 19,638
2030 66,912 16,400 939 + 4,625 21,964
2035 77,972 19,111 939 + 4,625 24,675
2040 90,860 22,270 939 + 4,625 27,833
¹Based on 125 gallons per capita per day for all projections and incorporates 4,625 EDU’s (1.99 MGD) for
unmetered/unaccounted water use as a constant demand.
Demand should also be calculated for the unlikely scenario that all future infill
development comes into fruition over and above the existing population and
non-residential EDU development. Table LU-12 – EDU Projections for All
Existing and Phased Development combines EDU projections from both
residential and non-residential developments while phasing them in five-year
intervals, after considering existing development (including active) and all of
the projected infill planned development projects using the same methodology.
Table LU-12 EDU Projections for All Phased Development
2017 Existing
Total Equivalent
EDU Planned All
Planned All Infill Dwelling Units
Residential and Infill Non-
Year Residential for Existing and
Non Residential Residential
EDU’s² Planned Infill
Including Active EDU’s ³
Development
Projects¹
2018 15,763 - - 15,763
2020 16,995 0 0 16,995
2025 19,638 60 193 19,890
2030 21,964 378 329 22,671
2035 24,675 378 475 25,527
2040 27,833 378 1,221 29,433
1 Includes 4,626 EDU’s (1.99 MGD) for unmetered/unaccounted water use as a constant demand.
²Residential infill development includes Las Padreras and Estrada Trust Development.
³ Non-residential infill development includes Estrada Commercial Development, Gran Plaza Phase 2,
Town Center Industrial Park, Calexico Mega Park, Halwood Place and future City-owned parkland areas.
36 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PUBLIC FACILITIES AND SERVICES
IV. PUBLIC FACILITIES AND SERVICES
This Service Area Plan will address how public facilities and services will be provided
to the City of Calexico and the Annexation Areas over the course of the 20-year
planning period. An analysis of the following facilities and services are provided in this
document:
• Administrative Facilities - City of Calexico
• Law Enforcement - City of Calexico
• Fire Protection Facilities - City of Calexico
• Park and Recreational Facilities - City of Calexico
• Library & Cultural Arts Facilities - City of Calexico
• Circulation & Transportation Facilities - City of Calexico
• Stormwater & Drainage Facilities - City of Calexico/IID
• Water Facilities - City of Calexico
• Sanitary Sewer Facilities - City of Calexico
• Airport Facilities- City of Calexico
• Educational Facilities- Calexico Unified School District
San Diego State University
Each facility is analyzed in detail based on the standards developed by LAFCO for
Service Area Plans. Each section provides a description of the nature of each service to
be provided, a description of the service level capacity and demonstrate that adequate
services will be provided within the demanded time frame. Each facility analysis is
divided into four sections as follows:
Performance Standard: A description of the desired level of service that a public facility
must provide.
Facility Planning and Adequacy Analysis: A description of the existing facilities, the
current adequacy of the facilities, the future demand for facilities and the phasing of the
demand for facilities as follows:
➢ Inventory of Existing Facilities
➢ Adequacy of Existing Facilities
➢ Inventory of Approved Facilities
➢ Growth Demand for Facilities
➢ Buildout/Phasing of Facilities
Mitigation: As applicable, recommendations to ensure that adequate facilities will be
provided for are addressed under the respective section.
Financing: An explanation and identification of how the service and facilities are
currently being funded, including a per capita cost, and how future services and facilities
may be funded.
Presentations of maps that clearly indicate the location of existing and proposed facilities
are provided. Discussion of any conditions which may be imposed or required within the
affected territory are also noted.
37 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN ADMINISTRATION SERVICE AND FACILITIES
A. ADMINISTRATION SERVICE AND FACILITIES
City of Calexico administrative facilities include City Hall and office buildings that
house administrative staff and provide general administrative services to Calexico
residents and the business community. Examples of administrative services include
municipal service management, clerk services, promotions of special events,
management and direction of planning and development services, utility billing and
collection, and other administrative functions of the City.
1. Performance Standard
The performance standard for administrative services was reassessed during
the preparation of this Service Area Plan. The 2006 performance standard for
administrative services was based on the 2006 existing administrative facilities
square footage, and the existing population at the time of the preparation of the
2006 Service Area Plan. It was determined that the building area available was
efficient and appropriate at 536 square feet per 1,000 in population. Generally, a
performance standard for administrative facilities range from 500-600 square feet
per 1,000 residents. For the purpose of this analysis, a modest adjusted
performance standard is presented due to significant reductions in administrative
positions and thus a reduced need for office space. The performance standard is
therefore set at 500 square feet per 1,000 in population.
In addition to the amount of square footage, the performance standard for
providing personnel is established at a range of 0.50 to .75 full-time equivalent
(FTE) per 1,000 residents. This standard is based on the current level of
administrative staff (22.5 FTE) per 1,000 residents while allowing for modest
adjustments as fiscally prudent.
2. Facility Planning and Adequacy Analysis
This analysis provides an inventory of the existing City Administrative Facilities
owned by the City of Calexico, the existing and future demand for facilities as
well as a projected phasing schedule. The purpose of this analysis is to
determine if the existing facilities are adequate for the existing and future
demand, and if not adequate, to identify approximately when additional facilities
will be needed in order to meet future demand within a 20-year time frame.
a) Inventory of Existing Facilities
The City of Calexico City Hall is located at 608 Heber Avenue. There is a
total of 22.5 FTE employees under administrative services. The existing
administrative facilities consist of a total of 16,750 square feet with an
additional 14,519 square feet of underground parking with an additional
89,670 square feet at the City Yard/Shop which is located at 640 Pierce
Avenue.
38 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN ADMINISTRATION SERVICE AND FACILITIES
The City Hall and
administrative offices were
constructed in 1994 and the
facilities are in good
condition. City Hall and the
vast majority of
administrative staff is
centrally located as noted in
Exhibit A-1 Administration
Facilities Map. There is
some administrative space at
the Public Works Office/City
Yard. The square footage is broken down into the table that follows by square
feet.
Table A-1 Administration Facilities at City Hall
Administrative Services Square Feet
City Manager
City Clerk/Legislative
16,750 SF
Finance
Planning & Engineering
Housing & Redevelopment
PW/City Yard/Shop (89,670 SF) 724 SF
Total 17,474.00 SF
b) Adequacy of Existing Facilities
As previously noted, there are a total of 22.5 Full Time Equivalent Employees
operating under 17,474 SF of administrative facilities. That is an equivalent
of 776 SF of building space per employee and .54 FTE per 1,000 in
population. Using the performance formula established and calculation
below, the existing demand for administrative facilities is 20,857 square feet.
Existing Population x Performance Standard = Current Demand
41,714 Population x 500 SF / 1,000 population = 20,857 SF.
Existing Facilities – Current Demand = Adequacy
17,474 SF. – 20,857 SF = -3,383 SF.
The existing administrative service facilities identify a deficiency of 3,383 SF
in administrative space, however the level of square feet of administrative
space per employee is adequate at 776 SF per FTE.
39 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN ADMINISTRATION SERVICE AND FACILITIES
Exhibit A-1 Administration Facilities
40 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN ADMINISTRATION SERVICE AND FACILITIES
c) Future Demand for Facilities & Planned Facilities
For the purpose of calculating future demand, and as previously noted, both
historic growth rates and active planned development is also considered to
project population demand. Using the existing performance standard
formula of 500 SF per 1,000 in population, the City of Calexico will need
45,430 square feet of administrative space by the year 2040. If all
development is constructed as projected, the City would need an additional
27,956 square feet by 2040 as projected in Table A-2.
Table A-2 Administrative Facilities Demand
Projected
Year Demand
Population
2020 46,639 23,320 SF
2025 57,421 28,711 SF
2030 66,912 33,456 SF
2035 77,972 38,986 SF
2040 90,860 45,430 SF
As the population increases, there will be an inherent need for additional City
administrative facilities. As of the date of this Service Area Plan, there were
no planned capital improvements projects for Administrative Facilities.
d) Opportunities for Shared Facilities
The City of Calexico provides for all of its City administrative needs using full-
time, part-time and contract workers. Assistance from other jurisdictions for
administrative services is not provided nor anticipated within the planning
period. Cross-utilization of services within the jurisdiction is facilitated. There
are many staff members who provide their expertise in public facilities and
services that are outside of the administrative services arena such as in
circulation, water and wastewater. For example, the City Manager, Economic
Development Director and several other employees of the City will complete
tasks that are not a part of the administrative services but are directly
related to the specific needs of various public services that the City
provides. These tasks are funded through the individual budgets of the
various departments for which the tasks are being completed. This
method of cross-utilization is an efficient use of existing resources.
e) Phasing
The City of Calexico does not currently have any planned facilities over the
next 20 years. As the City grows and economic conditions improve, the City
will increase staff and expansion of administrative service facilities will need
41 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN ADMINISTRATION SERVICE AND FACILITIES
expansion. Expansion at the Public Works Yard may be a viable option.
Table A-3 Identifies the increase in demand phased in 10-year increments to
facilitate a capital improvement plan.
Table A-3 Administrative Facilities Increase in Demand
Year Demand Additional SF
2020 23,320 SF 5,846 SF
2025 28,711 SF 5,391 SF
2030 33,456 SF 4,746 SF
Subtotal Year 2030 15,983 SF
2035 38,986 SF 5,531 SF
2040 45,430 SF 6,444 SF
Subtotal Year 2040 11.975 SF
TOTAL SF 27,958 SF
3. Mitigation for Administration Facilities & Services
On a yearly basis, the City of Calexico should review the personnel level and
facility space available against the demand for facilities based on the established
performance standards and consider amending these standards in the future given
the high level of service outsourcing by the City which in-turn reduces the overall
demand for general government facility space. This measure is further lined with
Statewide goals of reducing the carbon footprint by continuing to maintain all City
services consolidated in one location. Additional facilities should be planned for and
provided on an as needed basis. The City should implement the following mitigation
measures for administrative facilities:
A-1 The City of Calexico shall develop of a Facility Master Plan to inventory
available real-estate and resources to meet future demand of all City
owned buildings.
A-2 By the year 2030 (10-year time period), a minimum of 15,983 additional
square feet of administrative facilities shall be planned for in order to
meet demand through 2030 if and when government employee staff has
substantially increased from current levels.
A-3 The 2008 Administrative Development Impact Fees shall be updated to
reflect share of costs for the identified general government facility
needs.
42 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN ADMINISTRATION SERVICE AND FACILITIES
A-4 The City of Calexico shall review the user fees charged for Planning,
Building and Engineering services and implement an adequate fee
structure.
4. Financing
Information regarding Project costs was determined by using the most current
adopted budget (See Appendix C- 2017/2018 Approved Budget). The current
revenue source for administrative facilities includes property tax and sales taxes,
licenses and permits, fines and penalties, charges for services, development
impact fees, assessments and other miscellaneous sources, including rents and
concessions. The City of Calexico also approved Measure “H” in 2010 which is a .05
cent sales tax to be used for general government purposes which is scheduled to
sunset in 2040.
a) Funding Sources and Per Capita Cost
Total General Fund Costs were budgeted at $13,657,707 for the 2017-2018
Fiscal Year. The City of Calexico Budget identifies approximately 20% of the
General Fund, for the continued operation of administrative facilities. There
are approximately $1,796,000 in functional revenues (charges for services,
licenses, franchise fees, rents and concessions) used to help pay for the
administrative services. The remaining gap is met through one-time Interfund
Transfers and One-time Revenues. These functional revenues must be
subtracted from the expenditures in order to determine the true costs to the
general public. Therefore, the cost to the general public through taxation
for administrative services is $935,541 ($2,731,541 - $1,796,000).
$935,541 / 41,714 population = $22.43 per capita
Using the City’s current population, and a constant per capita cost of $22.43,
the future costs are noted in the following table in five-year increments. These
estimations assume a constant cost per capita in the year 2017 dollars and
the provided population projections.
43 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN ADMINISTRATION SERVICE AND FACILITIES
Table A-4 Projected Administrative Costs
Projected/Planned Administrative
Year
Population Costs
2020 46,639 $1,046,113
2025 57,421 $1,287,953
2030 66,912 $1,500,836
2035 77,972 $1,748,912
2040 90,860 $2,037,990
b) Future Funding Sources
The City of Calexico will continue to use the existing funding sources for the
maintenance and operation of City administrative facilities. However, due to
the future growth anticipated, other funding sources for capital improvements
will be needed. It is recommended that the Development Impact Fees for
Administrative Facilities be updated and increased to address projected
facility demand. The current impact fees are extremely low and have not
been increased in over a decade. Other funding sources that may be
available for capital improvements include general obligation bonds or a City-
wide community facilities district. Further descriptions of the financing
mechanisms are provided in the Financing section of this Service Area Plan.
44 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
B. LAW ENFORCEMENT
Police services are provided by the Calexico Police Department. The police station
is located at 420 East 5th Street in Calexico which is the main headquarters. The
Calexico Police Department provides services to the entire City of Calexico. There is
an Administration Section and Operations Division and a Mission Support Division.
The Calexico Police Department will also provide backup for the County Sheriff if
necessary. Services in the City of Calexico include patrol, criminal investigations,
civil services, traffic control, crime prevention, and animal control.
1. Performance Standard
The performance standard for police protection and law enforcement facilities
was determined upon approval of the 2001 Service Area Plan. The performance
standard for personnel is 1.5 officers per 1,000 population with a target ratio of 2
per 1,000 in population, four dispatchers per shift (two shifts per day), one support
staff member per six sworn officers, and one detective per five uniformed officers.
Additionally, the number of marked patrol vehicles shall equal six per shift (two
shifts per day) which is the equivalent of 2.3 sworn officers per each marked unit
as the established performance standard under the 2006 Service Area Plan. The
number of unmarked administrative vehicles will equal the number of sworn
officers divided by five. Volunteers are also established at .25 per 1,000 in
population. There are no adopted standards for facility size, however, 250 SF of
building area per fulltime employee is an acceptable industry standard.
2. Facility Planning and Adequacy Analysis
The Calexico Police Department provides police protection, law enforcement,
traffic control and community safety and support services. General duties
include crime prevention, criminal investigation, suspect apprehension, traffic
control, accident investigation, and animal control services. Personnel are
available 24-hours a day, seven days a week. The proceeding section provides
an inventory of the facilities, equipment and personnel to support these services
and their adequacy in order to meet future demand.
a) Inventory of Existing Facilities
According to the Police Chief, law enforcement personnel have been reduced
over time. Available data demonstrates a slight decrease from the staffing
level noted under the 2015 Public Facilities Element of the Calexico General
Plan (58 police department personnel/43 sworn officers) and drastically
reduced from those noted in the 2006 Service Area Plan (53 police
department personnel/43 sworn officers) to current levels as of July 2018 of
forty-four (44) full-time employees and twenty-six sworn (26) officers. The
45 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
current statistics regarding law enforcement facilities, equipment, and
personnel were communicated by the Interim Police Chief as provided for the
Calexico community as of May 2018 and noted as follows:
Police Department Personnel (44 FTE):
• One (1) Interim Police Chief
• One (1) Lieutenant
• Four (4) Patrol Sergeants
• One (1) Administration Sergeant
• Two (2) Detectives
• One (1) School Resource Officers
• Sixteen (16) Patrol Officers
• Five (5) Reserve Police Officers (two level I and three Level II)
• Two (2) Animal Control Officers
• Eight (8) Dispatchers (Including Supervisor)
• Two (2) Record Assistants/Support Staff
• One (1) Administrative Assistant
Existing Police Department Facilities (See Exhibit B-1):
• Main Police Station at 420 East 5th Street (16,142 SF)
• Meadows Traffic Division Office at 1095 Camellia Street (Closed)
• International Traffic Meter/Controller Office at 100 Paulin Ave (1,302 SF)
• PAL/Nosotros Park Substation at 601 Kloke Avenue (Closed)
Police Department Equipment:
• Twenty-Eight (28) marked patrol vehicles
• Three (3) two-wheel motorcycle units
• Seven (7) unmarked vehicles
• Two (2) three-wheel motorcycle units (Cushman)
• One (1) four-wheel motorcycle units (Kawasaki Mule)
• One (1) GEO electric vehicles
• Four (4) Bicycles
46 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
Exhibit B-1 Existing Law Enforcement Facilities
47 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
b) Adequacy of Existing Facilities
Based on the performance standard for personnel of 1.5 officers per 1,000
population, the City is also deficient in sworn officers. The City of Calexico
received an influx of daily commuters from Mexicali. The Calexico Police
Department estimates an average of 75,000 commuters pass through or
make trips to/from Mexicali/Calexico daily. This represents a significant daily
non- resident population increase that may warrant a more ideal performance
standard and staffing ratio of 2 officers per 1,000 residents.
Prior municipal service reviews have noted that the staff levels at the
Calexico Police Department have been declining. In 2006 the Department
had 43 sworn officers compared to the current 26 sworn officers. The Police
Department currently has a staffing level of 26 sworn officers, five reserve
officers and seventeen (17) volunteers. Two volunteers serve in the records
division and fifteen under the Police Explorers team. The current facilities are
17,444 square feet.
Facility Demand
Existing FTE x Performance Standard = Current Facility Demand
44 FTE x 250 SF = 11,000 SF
Staff Level
Existing Population x Performance Standard = Current Officer Demand
41,714 population x 1.5 Officers / 1,000 population = 62.5 Sworn Officers.
Volunteers
Existing Population x Performance Standard = Current Volunteer Demand
41,714 population x 0.25 Volunteers / 1,000 population = 10 Volunteers
There is a current deficiency of -36.5 officers. The department meets the four
dispatchers per shift performance ratio previously adopted but has insufficient
support staff. The number of detectives per ratio of sworn officers is also
below established standard noted in the table below.
Table B-1 - Support Staff
Support
Dispatchers Detectives
Staff
Performance 1 per 6 1 per 5
4 per shift
Standard Officers Officers
Existing 4 per shift 2 2
1
Required Staffing 4 per shift 3 4
Deficiency 0 1 2
1
Represents the support staffing necessary to meet the performance standard based on
the existing 23 Sworn Officers, which is also below the performance standard.
48 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
The number of marked patrol vehicles does exceed the standard of six per
shift (two shifts per day) and the number of unmarked administrative vehicles
is also sufficient. The existing police department facilities however, although
adequate for the current number of officers, do not adequately serve the
community.
Based on information provided by the Calexico Police Department, the
current police station locations/facilities are not adequate to accommodate
the Department’s future growth of personnel through the year 2040. It should
be noted, that two previously used substations (PAL/Nosotros Park and
Meadows) were located in trailers which have since been closed. As the city
develops outward into the Sphere of Influence areas, there will be future need
to construct new facilities/substations in order to maintain quick response
times and have adequate space.
c) Future Demand for Facilities & Planned Facilities
The City is estimated to have a population of 90,860 people by the year
2040, using planned active development figures. Using the established
performance standard, the City will need an additional 110 sworn officers to
meet future demand by the year 2040. In order for the Police Department
to meet the performance standard in the future, there will also be a need
for an additional six volunteers and an additional 16,629 square feet of
building space by the year 2040.
Table B-2 - Projected Law Enforcement Service Demand
Project/Planned
Year Police Service Demand
Population
17,490 SF Facility
2020 46,639 70 Police Officers/30 Vehicles
12 Volunteers
21,533 SF Facility
2025 57,421 86 Police Officers/37 Vehicles
14 Volunteers
25,092 SF Facility
2030 66,912 100 Police Officers/44 Vehicles
17 Volunteers
29,240 SF Facility
2035 77,972 117 Police Officers/51 Vehicles
19 Volunteers
34,073 SF Facility
2040 90,860 136 Police Officers/59 Vehicles
23 Volunteers
49 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
As of this 2018 Service Area Plan major capital improvements are planned
for the Police Department. No expansion of facilities are proposed at this
time. As the City continues to grow, the City of Calexico will continue to
explore a nine-acre site in the northeast area of the City for a Public Safety
Center that could house both the Calexico Police Department and Fire
Department. The public safety building is currently in the due diligence
phase, so the exact location, size, number of people needed to adequately
serve the station, and the cost is unknown at the time of preparation of
this Service Area Plan update.
d) Opportunities for Shared Facilities
The City of Calexico owns and maintains its own Police Department;
however, it fully utilizes facility sharing opportunities. The Calexico Police
Department also provides dispatch services to the Calexico Fire Department.
Personnel operates the Dispatch Center in the Police Department 24 hours a
day, seven days a week.
Additionally, the Calexico Police Department participates in joint ventures
with other agencies to undergo cooperative policing efforts. Cooperative
efforts include involvement through the Imperial Valley Street Interdiction
Team (SIT), the Federal Drug Enforcement Agency (DEA) Task Force and
School Resource Officer deployment services. The participation into shared
services enables access to State and Federal grant funding to cover service
cost.
There is further a future opportunity to share facilities with the Calexico Fire
Department under a joint use Public Safety Building. Absent a regional
safety building Fire Stations may be constructed with additional opportunities
for joint use as well.
e) Phasing
As the City’s population increases, adequate Police Department staff and
patrol vehicles can be added, as necessary, in order to meet the current
level of service standards. The following Table B-3 represents the demand
for police department staff, vehicles and square footage for the next 20
years in 5-year increments. A more detailed service demand is noted on
Table B-3 which includes reserves and other personnel.
50 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
Table B-3 Projected Law Enforcement Phased Demand
Additional
Additional Facility Expansion or
Year Projected/Planned
Equipment Need in Phases
Population
1,846 SF Facility
2020 4,925 7 Police Officers/3 Vehicles
1 Volunteers
4,043 SF Facility
2025 10,782 16 Police Officers/7 Vehicles
3 Volunteers
3,559 SF Facility
2030 9,491 14 Police Officers/6 Vehicles
2 Volunteers
4,148 SF Facility
2035 11,060 17 Police Officers/7 Vehicles
3 Volunteers
4,833 SF Facility
2040 12,888 19 Police Officers/8 Vehicles
3 Volunteers
3. Mitigation for Law Enforcement Facilities & Services
Temporary buildings, vehicles and personnel can be added incrementally as
demand for police protection service demand increases with population growth
and until the permanent capital investments can be made. The following is a list
of mitigation recommendations for Police Protection:
P-1 The Calexico Police Department shall continue to monitor the response
times for priority 911 calls to ensure adequate public safety.
P-2 The City of Calexico shall continue its due diligence regarding feasibility of
a joint Public Safety Building to be shared by the Police Department and
Fire Department.
P-3 The 2008 Police Facilities Development Impact Fees shall be updated
to reflect share of costs for the projected public safety building or law
enforcement facility needs.
P-4 The Police Department shall continue to obtain grants and other funds
to combat crime through proactive preventative measures.
P-4 The City Council shall firmly commit an increasing percentage of
Measure H funds for the purpose of permanently increasing law
enforcement services.
51 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
4. Financing
The Calexico Police Department is the largest General Fund Department in the
City, employing over 50 sworn officers and civilian personnel. The current
revenue sources for police protection services include property and sales tax
from the City’s general. The Meters and Parking Division also generates
revenue for the Department. It is estimated that approximately $350,000 is
generated each year.
The City also approved Measure “H” in 2010 which is a .05 cent sales tax to be
used for general government purposes and is scheduled to sunset in 2040. As
new development is approved development impact fees are also collected for
police mitigation. Other revenue is derived from special revenue sources
including the State C.O.P.S. Grant (1584 COPS Grant), Homeland Security
Grant Program (HSGP) -Operation Stoneguard, School Partnership Grant, Office
of Emergency Services State FEMA Grant and asset forfeitures. Please refer to
Financing Section of this SAP for additional details.
a) Current and Per Capita Costs
The 2017-2018 City of Calexico budget provided approximately 35% of
General Funds, or $5,069,530, for police, parking and animal control
services. Using the City’s current population of 41,714, law enforcement
service costs $121.53 per resident. This cost was determined by dividing
the funds appropriated from the general fund for police protection services
by the existing population. A cost estimate for future police services is
provided in Table B-4 below.
$5,069,530 / 41,714 population = $121.53 per capita
Table B-4 Projected Law Enforcement Service Costs
Project/Planned
Year Police Service Cost
Population
2020 46,639 $5,668,038
2025 57,421 $6,978,374
2030 66,912 $8,131,815
2035 77,972 $9,475,937
2040 90,860 $11,042,216
52 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LAW ENFORCEMENT
b) Future Funding Sources
The City of Calexico will continue to use the existing funding sources and
revenue from Measure “H” Sales Tax for Law Enforcement Services. Measure
“H” funds, however, should be specifically budgeted for police enforcement
services and not just be a part of the General Fund. Additionally, due to the
future growth anticipated, other funding sources for a new police station
and additional vehicles and equipment may be needed. The City may want
to consider a bond measure to fund phases of a joint use Public Safety
Building. It is recommended that, at minimum, the Development Impact Fees
for Police Facilities be updated and increased to address the projected facility
demand. The current impact fees have not been increased in over a decade
and don’t account for new facility demand.
53 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
C. FIRE PROTECTION
The City of Calexico operates and manages a full-service Fire Department. The Fire
Department headquarters is located on 415 East Fourth Street. The Calexico Fire
Department provides fire suppression, rescue services, emergency medical
response, fire prevention services, and community education and outreach. The
Fire Department further maintains a mutual aid agreement with other governmental
agencies and will provide services into unincorporated areas. The Calexico Fire
Department further participates in the Hazardous Emergency Response team
(HEAT) under a joint power agreement (JPA) with Imperial County.
1. Performance Standard
The City of Calexico has adopted a performance standard for fire station
facilities, firefighting equipment, and department personnel. Fire station
construction/need is based on 6,500 square feet per 17,900 population in
addition to acceptable response times which is targeted at under seven
minutes. On equipment, it will be necessary to retire and replace one fire
engine every 15 years and one ambulance every 0-7 years of service
depending on the wear and tear it receives in its lifetime. With regards to
personnel, the City shall maintain a standard ratio of 1.5 firefighters per 1,000
residents, and 2 administrative support staff per 27,000 persons. Based on
current population and existing equipment, one (1) firefighting vehicle is needed
for every 8,150.
The Calexico Fire Department also provides Emergency Paramedic Services
throughout the City Limits and in some cases into the Sphere of Influence. A
general rule-of-thumb for ambulance services is one ambulance for every
30,000 population, but that ratio should be adjusted based on age composition,
traffic patterns, and access to trauma centers. (Kuehl, 2002). The National Fire
Protection Association (NFPA) 1710 further recommends a response time of
eight minutes or less for emergency medical services.
2. Facility Planning and Adequacy Analysis
The Calexico Fire Department will continue to provide service to the
incorporated City Limits and future annexation areas, as well as response to
unincorporated areas under the mutual aid agreement. This analysis provides
an inventory of existing fire station facilities, equipment and personnel to
determine adequacy and phasing in response to projected demand.
54 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
a) Inventory of Existing Facilities
According to the 2015 Public Facilities Element of the Calexico General Plan,
most recent adopted budget and inventory amendments provided by the City
of Calexico Fire Department, the following facilities, equipment, and
personnel are provided for the Calexico community:
Existing Fire Protection Facilities (See Exhibit C-1):
• Fire Department Headquarters at 415 East 4th Street (3,000 SF)
• Fire Station #1/Headquarters at 430 East 5th Street (3,330 SF)
• Fire Station #2 at 900 Grant Street (2,908 SF)
Fire Department Equipment
Station #1
• California OES USAR Trailer
• County Wide Hazardous Material Support Trailer
• One (1) 1996 Emergency One Quint Engine (3891)
• One (1) 2012 Pierce Triple Combination Engine (3811)
• One (1) Quint Truck (3891)
Station #2
• One (1) 2007 KME Triple Combination Fire Engine (3821)
Emergency Medical Equipment
Station #1
• One (1) Emergency Ambulance (2670)
• Two (2) Reserve Ambulances (2672 and 2675)
Fire Department Personnel (25 FTE):
• One (1) Fire Chief
• Six (6) Fire Captains (two are limited term)
• One (1) Fire Inspector
• Nine (9) Fire Fighters
• Seven (7) Firefighter Engineers (one is limited term)
• One (1) Administrative Assistant/Support Staff
Station 1 has five fire fighters on duty at all times and an additional three day
personnel. Station 2 has two fire fighters on duty at all time. The total 2018
staff levels were seven per shift. The ambulance is staffed with a combination
of Firefighter Paramedics, and Firefighter Emergency Medical Technicians
who have been cross-trained in both firefighting and emergency medical
techniques for advanced life support.
55 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
Exhibit C-1 Existing and Proposed Fire Station Facilities
56 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
b) Adequacy of Existing Facilities
The Fire Department Station #1 is in need of major capital improvements.
Measure “H” funds have been reserved to rehabilitate the Station. Expansion
is not a project component. The current area of the Fire Department
Facilities is 9,238 SF. There is a current deficiency in fire protection facilities
of 5,909 SF. The facility demand is based on the performance ratio
established and calculated as follows:
Facility Demand
Existing Population x Performance Standard = Current Facility Demand
41,714 population x 6,500 SF / 17,900 population = 15,147 SF.
The fire department currently provides average response times of under six
(6) minutes. However, as development continues to occur, there may be
occasional delays due to traffic. Please refer to Exhibit 7 - Existing Fire
Station Facilities for a depiction of the regional location of the existing fire
station and service area.
Based on historic municipal service reviews, the staff levels at the Calexico
Fire Department have been declining. In 2006 the Department had 33
professional fire fighters. The Fire Department currently has a staffing
level of 24 fire fighters, no reserve officers and no volunteers. Thus a
deficiency of -38.5 fire fighters currently exists per demand as calculated
below in addition to being deficient one additional support staff member.
Staff Level
Existing Population x Performance Standard = Current Officer Demand
41,714 population x 1.5 Officers / 1,000 population = 62.5 Fire Fighters.
The Calexico Fire Department owns and operates four firefighting vehicles.
The City does not have an adequate number of fire protection vehicles.
Vehicle Need
Existing Population x Performance Standard = Current Vehicle Need
41,714 population x 1 vehicle / 8,150 population = 5 Vehicles.
Calexico is the only City in Imperial County that provides its own prehospital
emergency medical services. The City uses a combination of first responder
paramedic engine and truck, which operate from two fire stations, and one
Advanced Life Support (ALS) Medic Unit. Gold Cross provides mutual aid
coverage when a second call requires a response. According to the 2015
EMS System Assessment Report completed by Fitch and Associates for the
County of Imperial, there were a total of 2,787 responses and 1,746
transports in Calexico in 2014. The Report further stated that additional
staffing is required to meet its call volume demand. Given the City’s
57 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
geographic size and physical layout, emergency medical response time is
sufficient, but in cases when there are simultaneous calls, additional staffing
is necessary. The City’s equipment inventory includes two reserve
ambulances.
c) Future Demand for Facilities and Planned Facilities
The City is estimated to reach a population of 90,860 by the year 2040.
Based on the demand projections provided in this Service Area Plan, it is
apparent that another fire station is needed. A master plan for fire protection
facilities has not been prepared by the fire department and future needs
for additional firefighting equipment and another fire station have yet to be
fully determined. However, there are preliminary indications that a shared
fire/police substation is desired.
The City of Calexico was exploring a joint facility to the northeast area of the
City for a Public Safety Center that would house both the Calexico Police
Department and Fire Department. A Master Plan for Fire Protection Facilities
could explore the financial feasibility of this option. Currently grant funds
available are limited to target lower income communities and the northeast
section of Calexico may not be able to meet this criterion. The service
demand including firefighting personnel and paramedics is noted in Table C-1.
Table C-1 Projected Fire Service Demand
Project/Planned
Year Fire Service Demand1
Population
16,936 SF Facility
2020 46,639
70 Fire Fighters/6 Vehicles
20,851 SF Facility
2025 57,421
86 Fire Fighters /7 Vehicles
24,298 SF Facility
2030 66,912
100 Fire Fighters /8 Vehicles
28,314 SF Facility
2035 77,972
117 Fire Fighters /10 Vehicles
32,994 SF Facility
2040 90,860
136 Fire Fighters /11 Vehicles
Currently, the only planned improvements to the Calexico Fire Department
are associated with a $6.1 million renovation project of Station #1. The
project, however is still in the preliminary phases.
In regards to increases to service, in June of 2018, the Calexico City Council
approved a new EMS Rate Study that will increase the current levels of
emergency medical service. The City intends to increase the City ambulance
service to two (2) fully staffed full time ambulance units with a third
58 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
ambulance on standby. There will be a total of six paramedics staffed per
ambulance unit. It is expected that the new services and staffing will be in
place well before the end of 2018.
d) Opportunities for Shared Facilities
The Calexico Fire Department is a member of the Imperial Valley
Firefighters Strike Force which is responsible to respond to fire
emergencies throughout California. The fire department further maintains a
mutual aid agreement with other governmental agencies in order to gain
access to specialized equipment and resources. As previously noted, the
City of Calexico was exploring a nine-acre site along Highway 98 in the
northeast area of the City for a Public Safety Center that would house both
the Calexico Police Department and Fire Department. Another potential site
could be just south of Cesar Chavez Park on a City owned parcel, also to
the northeast of the City.
There is also the Imperial Valley Fire Service and Rescue Mutual Aid
Plan in place to ensure that emergency needs will be met. The intent
of the mutual aid plan is to meet the anticipated needs of local agencies
within their zones, to access resources of adjacent agencies within the
area of the County, and to access the resources of other jurisdictions
within Region VI or beyond, if necessary, to meet the needs of emergency
incidents.
e) Phasing
As the City’s population increases, additional fire department staff can be
hired when necessary in order to meet the demand created by future
development. The following Table C-2 Projected Fire Service Demand
represents the demand for fire protection services for the next 20 years in
five-year increments.
Table C-2 Projected Phasing of Fire Service Demand
Additional
Fire Service Phased Demand in
Year Project/Planned
Addition to Current Deficiency
Population
1,788 SF Facility
2020 4,925
7 Sworn Officers/1 Vehicles
3,915 SF Facility
2025 10,782
16 Fire Fighters /1 Vehicle
3,446 SF Facility
2030 9,491
14 Fire Fighters /1 Vehicle
4,016 SF Facility
2035 11,060
17 Fire Fighters /1 Vehicle
4,680 SF Facility
2040 12,888 19 Fire Fighters /
2 Vehicles
59 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
3. Mitigation of Fire Protection Facilities & Services
The City of Calexico should continually monitor the existing fire department
facilities, staffing levels and response times for both fire protection and
emergency response services in order to ensure that adequate levels of
service are provided. Mitigation recommended is as follows:
F-1 Fire protection personnel should be incrementally added as
demand increases inclusive of hiring reserves. Measure “H”
Funds should be incrementally increased and reserved to
exclusively address fire protection services.
F-2 An additional fire station should be proactively planned for. The
2008 Fire Facilities Development Impact Fees shall be
updated to reflect share of costs for the projected public safety
building or independent fire facility demand.
F-3 All major developments proposed within the City of Calexico
shall be forwarded to the fire department for review and
comment.
F-4 A Master Plan for Fire Protection Facilities to address
development northeast of the City should be initiated.
F-5 A Volunteer Firefighter Program should be considered. The
Ratio of Volunteer Firefighters should be considered at 0.25
Volunteers / 1,000 population.
F-6 Beginning in 2018 the City Council shall raise the ambulance
rates to cover the full cost of staffing, equipment, and
maintenance of ambulances.
F-7 Every three years, the City will re-evaluate participating in a
county-wide ambulance program and whether it would result in
a substantial savings for the provision of emergency services
without adversely impacting dual service availability (fire-
fighter/paramedic).
4. Financing
The current revenue sources for tire protection services include property and
sales tax from the City’s General Fund. The City also approved Measure “H” in
2010 which is a .05 cent sales tax to be used for general government purposes
and is scheduled to be available until 2040. As new development is approved
development impact fees are also collected for police mitigation. Other
revenue is derived from special revenue and State grant sources including
60 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FIRE PROTECTION
Prop 172 sales tax Public Augmentation Funds, Transient Occupancy Tax
Funds, and Fire Act Grants.
a) Per Capita Costs
For the fiscal year 2017-2018, the City of Calexico budgeted $4,242,864 for
fire protection services. Using the City’s estimated 2018 population of
41,714, fire protection service per capita cost for the 2017-2018 fiscal year
was $101.71 per resident. This data was calculated by dividing the annual
budget of the fire department by the existing population. The projected cost
over the next twenty years is projected in the following table.
$4,242,864 / 41,714 residents = $101.71 per capita
Table C-3 Projected Fire Service Costs
Project/Planned
Year Fire Service Cost
Population
2020 46,639 $4,743,653
2025 57,421 $5,840,290
2030 66,912 $6,805,620
2035 77,972 $7,930,532
2040 90,860 $9,241,371
b) Future Funding Sources
The City of Calexico will continue to use the existing funding sources of
property and sales tax, including development impact fees for Fire Protection
Services, Equipment and Facilities. The Development Impact Fees shall be
updated from the 2008 Schedule which is not reflective of current demand.
Measure “H” funds, furthermore, should be specifically budgeted for fire
protection services and not just be a part of the General Fund. Other
funding sources that may be available in the future include a Fire
Suppression Assessment, formation of a Citywide Community Facilities
District, or grant funding. Further descriptions of these and other financing
mechanisms are provided under the Financing section of this Service Area
Plan.
61 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
D. PARKS & RECREATION
Parks and Recreational facilities owned and operated by the City of Calexico are split
under the Community Services Department (for recreational facilities and services) and
under the Public Works Department (for parks, ball fields and open space). There are a
number of parks and recreational facilities within the City of Calexico including open
space areas that serve dual use as retention basins. Park and recreational facilities
include sport fields, passive parks or “pocket parks,” some may be equipped with
basketball courts, baseball fields, playground equipment, picnic tables and benches,
soccer fields, walking and running trails, restrooms and numerous other amenities.
1. Performance Standard
The City of Calexico has adopted the Performance Standard of 3.0 acres
parkland/1,000 population consistent with the Quimby Act. This standard is applied
to developer impacts and further stipulated as a Goal in the Parks and Recreation
Element of the City of Calexico General Plan. This ratio is typically enforced upon
permitting of new development via the dedication of parkland.
2. Facility Planning and Adequacy Analysis
The City of Calexico Parks Department strives to ensure an adequate provision of
park facilities. The Calexico Recreation Department is located at 707 Dool Avenue.
The recreation department has a total of three (3) employees that report to the
Community Services Director which also oversees library services and cultural arts.
The recreation staff consists of one (1) Administrative Assistant, one (1) Community
Sport Coordinator, and one (1) Community Recreation Coordinator. The inventory of
City owned facilities are identified as follows:
a) Inventory of Existing Facilities
Recreational Buildings - The City of Calexico Recreation Department Building
is also the Calexico Community Center Building. The Center has a total area of
3,900 square feet and has a capacity of 320 persons. Many leisure services and
recreation classes are available to residents of all ages at the Community
Center. Additionally, the Senior Hall is located adjacent to the Community
Center with a total area of 2,376 square feet and a capacity of 160 persons.
Parks - Many of Calexico’s existing parks and sports fields are located within
stormwater retention basins and over the years maintenance concerns have
been raised by community residents. It is important to note that although the
current inventory may contain dual use (storm-water basin/park) this practice has
been restricted by the City of Calexico to no more than 50% of the total park
area for dual use and further requires all retention basins to be landscaped.
62 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
The City of Calexico currently has over 27 parks consisting of over 77 acres of
parkland as denoted in Exhibit D-1 Park Facilities. Those parks that have a dual
use as stormwater retention basin are further identified as “Dual Basin.” The park
space is further noted in the table below.
Table D-1 Park Facilities City of Calexico Park Space
Public Park or Recreational Space Acres Dual Basin
Adrian C. Cordova Park (Cesar Chavez) 5.65 NO
Alex Rivera Field 1.72 NO
American Legion Field 2.11 NO
Border Friendship Park (International) .78 NO
Community Park (Community Center Area) 1.45 NO
Crummett Park 2.45 NO
Daniel Guitierrez Field (Villa Santa Fe) 4.50 90%
El Dorado Park (Joel Reisen Field) 6.05 90%
Friendship Park (Grand Plaza Park) 1.17 NO
Heber 2.35 NO
Kennedy Gardens Small Park 1.49 NO
Kennedy Gardens Large Park 4.27 100%
Kennedy Gardens Park #3 1.10 NO
Park
Las Casitas Park 6.00 80%
Lioness Park 3.08 NO
Meadows Park North 1.02 90%
Meadows Park South 2.05 90%
Miguel Cortez Park .47 NO
Nosotros Park and Little League Field 5.90 NO
Rancho Elegante Park 3.42 90%
Rancho Frontera Park 4.80 90%
Rio Vista Park 0.87 NO
Rockwood Plaza Park 2.56 NO
Rodriguez Park and Field 3.80 NO
Valle De Oro Park 3.60 NO
Williams Greenbelt Park 1.40 NO
Zapata Park 3.67 NO
Total Acreage 77.73
Source: Calexico 2015 General Plan Parks and Recreation Element and Google Earth Pro
Prior Service Area Plans had inventoried Emerson Field (3.4 acres) which is
a school owned park. Prior SAP’s and the City’s 2015 Parks and Recreation
Element also counted the vacant 9-acre parcel south of Adrian C. Cordova
Park as Cesar Chavez Park.
63 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
Exhibit D-1 Existing Park Facilities
64 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
b) Adequacy of Existing Facilities
Using the goal of 3.0 acres per 1,000 population, there should be a
minimum of 125 acres of parkland. Based on the existing park acreage of
77.73 acres, there is an existing deficit of 47.41 acres. The adequacy is
calculated as follows:
Existing Population x Performance Standard = Current Demand
41,714 Population x 3.0 Acres / 1,000 population = 125.14 Acres
Existing Facilities – Current Demand = Adequacy
77.73 Acres – 125.14 Acres = 47.41 Acre Deficit
This indicates that the City needs to obtain or develop an additional 47.41
acres of recreational open space in order to meet the current demand.
c) Future Demand for Facilities & Planned Facilities
Based on a 2040 population projection of 90,860 the City of Calexico will
need 273 acres of recreational open space in order to be consistent with
the performance standard objective of the General Plan.
Table D-2 Projected Parkland Demand
Project/Planned Parkland Demand in
Year
Population Acres
2020 46,639 140 Acres
2025 57,421 172 Acres
2030 66,912 201 Acres
2035 77,972 234 Acres
2040 90,860 273 Acres
It is important that adequate park facilities be provided to serve the existing
and future residents of the City of Calexico. The City actively requires the
development community to provide parkland either through the payment of
the development impact fee or through parkland donations or improvements
as a part of the development approval process. The City maximizes the use
of available space for recreational services to levels that are equal to, or
higher than most other county City’s that even have a higher population level,
decreasing overall capital demand for new facilities.
65 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
The City of Calexico has a Capital Improvement Program that was last
adopted under the 17/18 FY Budget. The City had $1,509,744 budgeted over
a five-year period for parks and recreation improvements. The funds,
however, are for improvements to existing parks and would not help offset a
future demand. The City does have, however, several new projects under
development including a two-mile rural trail planned along the New River.
When this plan comes into fruition, an estimated total of 20 acres will be
added to open space/recreation.
d) Opportunities for Shared Facilities
As previously noted, there are a number of retention basins that are used as
ball fields thus serving a dual purpose. The City and the School District also
have a Joint Use Agreement that covers 12 schools and approximately 43.52
acres of parkland. There are 12 school sites within the Calexico Unified
School District that could provide for recreational opportunities during the
summer, after school hours and on weekends. Additional discussions may
occur between the School District and the City regarding additional joint use
agreements for use of school facilities for recreation purposes.
e) Phasing
Based on the 3.0 acres per 1,000 population performance standard for
parkland, the following Table D-3 represents the demand for additional
recreational land/parkland acreage for the next 20 years in five year
increments for phased improvements in addition to the current deficiency of
47 acres.
Table D-3 Phased Parkland Demand
Project/Planned Population Phased Additional
Year
Population Increase Parkland Demand
2018 41,714 - -
2020 46,639 4,925 15 Acres
2025 57,421 10,782 32 Acres
2030 66,912 9,491 28 Acres
2035 77,972 11,060 33 Acres
2040 90,860 12,888 39 Acres
66 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
3. Mitigation of Park & Recreation Facilities & Services
The City of Calexico should continue to pursue various means by which
to obtain and provide for adequate park facilities targeting acquisition and
capital investment for the existing and future residents of the City. The
following are mitigation recommendations to achieve adequacy for park
facilities.
PR-1 Continue to require developers of new subdivisions to dedicate
parkland and/or pay the development impact fee to ensure that
future residents pay their fair share for impacts on park
facilities.
PR-2 Pursue federal and state grants and aid funds to ensure there
are sufficient parks in the future.
PR-3 Continue to advance plans and improve the 20-acre New
River trail area to meet the current deficiencies and consider
park impact agreements for developers to improve an
equivalent amount of park space instead of requiring
dedication at their project sites as permitted by proximity.
PR-4 Develop the 9-acre Cordova Park into three baseball fields by
matching limited measure “H” funds and existing land value to
available grant resources.
PR-5 The City shall identify and work with the Imperial Irrigation
District to designate existing easements with underground
pipelines as running and walking trails to be identified as open
space/recreation areas and incorporate distance markers.
PR-6 The City shall work with the Imperial Valley Pioneers Museum
and explore the possibility of developing the Old Armory Guard
site as a Cultural Open Space/Park Area.
PR-7 The City of Calexico should incorporate all park facilities
capital improvement projects into their Capital Improvement
Program even when no funding has been identified. The
facilities should be listed as “pending programming” so they
remain in the forefront of leadership.
4. Financing
The current revenue sources used to pay for park facilities include property and
sales taxes from the general fund, user fees for recreational activities and
67 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
park impact fees collected from new residential developments. The City collects
approximately $12,000 annually from leases. The City also approved Measure
“H” in 2010 which is .05 cent sales tax to be used for general government
purposes and is scheduled to be available until 2040. The City of Calexico will
continue to use these funding sources for the continued maintenance and
operation of parks and recreational facilities.
a) Per Capita Costs
The adopted budget for Parks and Recreation in the City of Calexico is not
combined. The Park System is budgeted under Public Works while
Recreation is budgeted under Community Services. According to the adopted
budget and confirmed by the Public Works Director, an estimated $744,909 is
budgeted for operation and maintenance of facilities (Parks $331,738 and
Recreation $413,171). Using the City’s current population of 41,714, parks
and recreation facilities cost $17.85 per resident. This cost was determined
by dividing the funds appropriated for parks and recreation facilities by the
existing population. Table D-4 Projected Recreation Cost, provides a cost
for park operation and maintenance based on 2018 dollars and in five-year
increments.
$744,909 / 41,714 population = $17.85 per capita
Table D-4 Projected Recreation Cost
Project/Planned
Year Recreation Cost
Population
2020 46,639 $832,506
2025 57,421 $1,024,965
2030 66,912 $1,194,379
2035 77,972 $1,391,800
2040 90,860 $1,621,851
b) Future Funding Sources
The City of Calexico will continue to use the existing funding sources for the
continued maintenance and operation of the park and recreation facilities.
However, due to existing facility deficiencies, other funding/matching
sources will be needed in order to adequately serve residents. There are
several other funding sources available for park facilities such as
community facilities district, special assessment district, as well as
68 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN PARKS & RECREATION
Community Development Block Grants and other state and federal grants.
Further descriptions of these and other financing mechanisms are
provided under the Financing Plan section of this SAP. The City shall further
examine a joint partnership with the Imperial Irrigation District for joint use of
existing easements to be doubled as walking and jogging trails.
69 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
E. LIBRARY & CULTURAL ARTS
The City of Calexico established the Library, Arts, and Historical Board for the
purpose of supporting local libraries and library services, supporting a variety of arts
in the City, and aiding in the identification of historical landmarks and structures. The
City of Calexico owns and operates the Camarena Memorial Library and a second
branch library to further these efforts. Both City libraries provide resources to meet
the educational, recreational, informational, and cultural needs of the community to
encourage lifelong learning.
1. Performance Standard
The performance standard for library facilities was determined during the
preparation of the City of Calexico General Plan Update approved by the City
Council in 2006. It was determined that the performance standards for library
facilities in the City of Calexico would be 0.55 square feet of library space per
resident. Additionally, library facilities should be available within two miles or ten
minutes driving time, whichever is less, and staffing should include one (1)
librarian and two (2) clerical staff per 6,000 residents. A performance factor for
library inventory was also established at three (3) items per resident including
books, computers, tapes, CD’s, periodicals, and similar resources. No
performance standard has been set for cultural arts.
2. Facility Planning and Adequacy Analysis
This analysis provides an inventory of the existing library facility owned by the
City of Calexico, the existing and future demand for facilities, as well as a
projected phasing schedule. Additional library facilities available in the City of
Calexico are provided by the San Diego State University Imperial Valley
Campus, not a part of this analysis. The purpose of this analysis is to determine
if the existing City owned facilities are adequate to meet the needs of the current
population and to identify approximately when additional facilities will be
needed in order to meet future demand.
a) Inventory of Existing Facilities
Library Facilities - As noted above, the City of Calexico operates and
maintains its own public library. The Camarena Memorial Library is located
at 850 Encinas Avenue. The main library has a total area of 12,000 square
feet of service area and there is another 2,164 square feet at the historic
Carnegie Library Building as a technology center and further discussed under
Cultural Facilities.
70 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
The library staffing includes: One (1) Service Director, two (2) Reference
Librarians, one (1) Executive Assistant, and one (1) Library Assistant II. The
library has over twenty volunteers that dedicate time to assist students and
residents. Services at the library include internet access, word processing
equipment, copy machines and meeting rooms. The library further houses
over 58,000 resource items as follows:
Library Collection
• 56,870 books
• 750 audio materials
• 900 video items
• 56 serial subscriptions
Library Computers and Equipment
• 2 copiers for staff/public use
• 40 public use computers
• 6 library catalog computers
• 15 library staff computers
• 2 black/white laser printers and
• 1 fax machine for staff use
Cultural Arts Facilities - Ancillary library and cultural services are provided
throughout other cultural art centers within the community. The former
Carnegie Library building located at 420 Heber Avenue was rehabilitated to
serve as a technology center for residents and to augment the Library’s
capabilities. The Carnegie building is now the Technology Center Branch
and has a total service area of 2,164 square feet. Additionally, the Carmen
Durazo Cultural Arts Center location at 421 Heffernan hosts artistic and
cultural events for both visual and performing arts. The Cultural Arts Center,
however, is owned by the De Anza Hotel Limited Partnership.
71 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
Exhibit E-1 Library & Cultural Arts Facilities
72 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
b) Adequacy of Existing Facilities
Using the performance formula provided above of 0.55 square feet per
resident, the existing demand for library facilities is 22,942 square feet based
on current population. Based on the performance standard formula, there is
only 14,160 square feet of building space between the library and Carnegie
Building, thus there a is a deficit of -8,782 square feet of library building
space.
Existing Population x Performance Standard = Current Facility Demand
41,714 population x 0.55 SF / 1 population = 22,942 SF
It is preferred that library facilities be available within two miles or ten minutes
driving time, whichever is less. As noted in Exhibit E-1, there is currently no
library within two miles for residences north of the All-American canal. New
development north of these areas will need new library facilities at a closer
proximity than currently exist. Additionally, staffing should include one (1)
librarian and two (2) clerical staff per 6,000 residents. The City of Calexico
does not currently meet the performance ratio for level of staffing as
calculated before as it currently only has five staff members while the demand
is for 20.
Existing Population x Performance Standard = Staffing Demand
41,714 population x 3 staff member / 6,000 population = 20 staff members
It should be noted however, that the library does actively use volunteers to
assist with clerical support and other service delivery needs. A performance
factor for library inventory was also established at three (3) items per resident
including books, computers, tapes, CD’s, periodicals, and similar resources.
The Calexico Library System currently has slightly over 58,642 library items in
its inventory. There is a current resource inventory deficiency of over 50%
based on the following performance standards:
Existing Population x Performance Standard = Inventory Demand
41,714 population x 3 items / 1 population = 125,142 library inventory items
c) Future Demand for Facilities & Planned Facilities
As the City of Calexico continues to grow, so does the need for library
facilities. With a planned population expected to reach 90,860 by the year
2040, additional library facilities will be needed to serve the future residents.
In order to meet this future demand, an additional 27,031 square feet of
library facilities would be needed by 2040.
73 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
In addition, the City is considering another historic structure located near
Bowker Road and Anza Road for a museum. Construction of new or
expanded facilities should be targeted within the 20-year planning period.
The total yearly demand for library facilities is shown on the Projected
Library Facility Demand Table E-1 in five-year increments over the 20 years.
Table E-1 Projected Library Facility Demand
Project/Planned Library Facility
Year
Population Demand
2020 46,639 25,651 SF Facility
2025 57,421 31,582 SF Facility
2030 66,912 36,802 SF Facility
2035 77,972 42,885 SF Facility
2040 90,860 49,973 SF Facility
The City of Calexico has a Capital Improvement Program that was last
adopted under the 17/18 FY Budget. There were no capital improvements
funded for library facilities. However, the desired planned construction and
expansion of library facilities are noted as follows:
1) The expansion of the Camarena Memorial Library (24,000 SF)
2) The construction of a new branch library to serve northwest side of
Calexico
3) The construction of a new branch library to serve northeast side of
Calexico
d) Opportunities for Shared Facilities
The City of Calexico participates in the SERRA Cooperative System that
includes libraries from Imperial County and San Diego County for inter-library
loan program, the library shares resources with other libraries in the region.
The public library will continue to pursue this opportunity for shared resources
in order to keep costs down while providing acceptable services to City
residents. The library system further has meeting and conference rooms that
are used by local groups and organizations and could further be used for
public meetings if other City administrative facilities are occupied.
Additionally, library services are available in the City of Calexico through the
San Diego State University, Imperial Valley Campus. The City of Calexico
intends to continue to network and share services with other libraries or
create joint use agreements with schools for joint beneficial arrangements.
74 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
e) Phasing
Costs and construction of projected facilities shall be phased. The yearly
increase in demand for library facilities is shown on the Projected Library
Cost Demand Table E-2 and E-3 below which provides the additional square
footage needs for the library over a 20-year period in five-year increments.
Consistent with the projected demand, costs for construction of facilities and
for items needed to address service demand are phased accordingly beyond
any existing deficit.
Table E-2 Projected Library Construction Cost Demand
Increase in Additional Library Estimated
Year
Population Facility Demand Construction Cost¹
2018 - 8,782 - SF Deficit $3,073,700
2020 4,925 2,709 SF Facility $948,063
2025 10,782 5,930 SF Facility $2,075,535
2030 9,491 5,220 SF Facility $1,827,018
2035 11,060 6,083 SF Facility $2,129,050
2040 12,888 7,088 SF Facility $2,480,940
¹Costs for Construction are estimated at $350 SF, in 2018 dollars.
Table E-3 Projected Library Item Cost Demand
Increase in Estimated Item
Year Library Item Demand
Population Cost¹
2018 - 66,490- Item Deficit $1,861,720
2020 4,925 14,775 Items $413,700
2025 10,782 32,346 Items $905,688
2030 9,491 28,473 Items $797,244
2035 11,060 33,180 Items $929,040
2040 12,888 38,664 Items $1,082,592
¹Costs per item are estimated at an average of $28 per each item, in 2018 dollars. This includes traditional
books, audio books, subscriptions, computers etc.
75 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
3. Mitigation for Library & Cultural Arts Facilities & Services
The City shall support the continuation of library services as a necessary
and desirable community service facility. The following mitigation is
recommended:
LC-1 The City of Calexico should include all library facilities capital
improvement projects into their Capital Improvement Program
even when no funding has been identified. The facilities
should be listed as “pending programming” so they remain on
the forefront of leadership.
LC-2 The City of Calexico should pursue grant funding from State,
Federal, and non-profit programs to continue providing
adequate library services to City residents.
LC-3 The City of Calexico should consider volunteer programs to
expand literacy and cultural services.
LC-4 The 2008 Library Facilities Development Impact Fees shall be
updated to reflect share of costs for the projected library
expansion needs.
LC-5 The City shall work with the IV Pioneers Museum on
developing the Old Armory Guard site as a Cultural Open
Space Area with Arts Projects dedicated from different
immigrant communities.
LC-6 The 2008 Library Facilities Development Impact Fees and Art
in Public Places Development Impact Fees shall be updated to
reflect share of costs for the projected improvement demand.
4. Financing
The current revenue sources for library facilities and services include property
and sales taxes from the City’s general fund. The City also approved Measure
“H” in 2010 which is a .05 cent sales tax to be used for general government
purposes and is scheduled to be available through until 2040. Additionally the
City receives limited grant monies for library materials, supplies and services and
a nominal amount from fines. The City further has an Art in Public Places fund
supported by Development Impact Fees. The 2017-2018 budget allocated
$754,903 for Library Service and $50,000 for Art in Public Places.
76 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN LIBRARY & CULTURAL ARTS
a) Per Capita Costs
The 2017-2018 City of Calexico budget identifies approximately $754,903
for continued operation of library and cultural services. Using the City’s
current population of 41,714 library services cost $18.09 per resident. This
cost was determined by dividing the funds appropriated form the
general fund for library services by the existing population. A cost estimate for
future library services is provided in the Table E-4 below. Note that the table
uses 2018 dollars, and based on the following:
$754,903/ 41,714 population = $18.09 per capita
Table E-4 Projected Library Service Costs
Project/Planned Library Service
Year
Population Cost
2020 46,639 $843,700
2025 57,421 $1,038,746
2030 66,912 $1,210,438
2035 77,972 $1,410,513
2040 90,860 $1,643,657
b) Future Funding Sources
The City of Calexico will continue to use the existing funding sources for
the continued maintenance and operation of the Library system, but will
need to increase the adopted Impact Fees for both Library Facilities and Art
in Public Places. Due to future growth anticipated, other funding sources
should be considered for capital needs and to maintain an adequate level of
library service for both existing and future residents. There are several
funding sources for library facilities such as community facilities district,
special assessment district, as well as Community Development Block
Grants. Further descriptions of these and other financing mechanisms are
presented in the Financing Plan of this Service Area Plan.
77 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
F. CIRCULATION & TRANSPORTATION
The City of Calexico is a main port of entry for both people and goods and as such the
existing modes of transportation are critical for international, interstate, regional and
local travel. The information contained in this section is based on the City of Calexico
Circulation Element which was last updated in 2015, the City of Calexico 2018 Bicycle
Master Plan and other transit documents. Calexico’s roadways and pedestrian
facilities are maintained by the Public Works Department with the exception of Highway
86 and Highway 98, which are State Routes maintained by Caltrans.
1. Performance Standard
The Circulation Element of the Calexico General Plan was created to sustain
safe and efficient vehicular travel throughout the City. The Circulation Element
is consistent with the Land Use Element which dictates that no land use will
be approved that will increase the traffic on planned or existing City streets
above the street’s existing design capacity at a “level of service” of “C” or
above. This “level of service” criterion is the most traditional method used to
determine the current and future needs for adequate circulation facilities with
an assignment of A to F as noted below.
Table F-1 Roadway Performance Standard
Level of Service Roadway Performance Standard
Represents free flow. Individual drivers have a high degree of
LOS “A” freedom to select their travel speeds and are unaffected by other
vehicles. Delays at intersections are minimal
Represents stable flow, but individual drivers are somewhat
LOS “B”
affected by other vehicles in determining travel speeds.
Represents stable flow, but the selection of the speeds of
LOS “C” individual drivers is significantly affected by other drivers and
longer queues are experienced at intersections.
Represents a condition of high density, stable traffic flow in which
LOS “D” speed and freedom of movement are severely restricted by the
presence of other vehicles with increased delays.
Represents operating conditions at or near capacity with severe
congestion. Individual vehicles have little free to maneuver within
LOS “E”
the traffic stream and any minor disruptions can cause a
breakdown in the flow of traffic.
Represents breakdown conditions. At this level of service, speeds
LOS “F” are low, delays are high, and there are more vehicles entering the
roadway than can be accommodated.
78 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
The City of Calexico, similar to many other jurisdictions, has begun examining
different performance standards known as Complete Streets. Complete Streets
is a transportation policy and design approach that requires streets to be
planned, designed, operated, and maintained to enable safe, convenient, and
comfortable travel and access for users of all ages and abilities regardless of
their mode of transportation. Modes of transportation in the City of Calexico
include pedestrians, bicycles, cars, trucks, buses, trains and emergency vehicles.
2. Facility Planning and Adequacy Analysis
The City of Calexico contains a circulation system which is predominantly
oriented in a north/south and east/west grid system. The major north/south
arterial system consists of Highway 111/Imperial Avenue, Andrade Avenue,
and Cesar Chavez Boulevard. The major east/west arterial system consists
of Highway 98 and Cole Road. These streets have independent classifications
in accordance with the Calexico General Plan Circulation Element and updated
structural section guidelines are as follows:
Table F-2 City of Calexico Roadway Classifications Standards
CLASSIFICATION ROW/PAVED WIDTH FT NO. OF LANES
Freeway/Expressway 210/172 4
Highway 148-178/120-124 4
Primary Arterial 100-126/60-80 4
Major Arterial 80-126/60-80 4
Secondary Arterial 75/55 2
Source: City of Calexico 2015 Circulation Element
a) Inventory of Existing Facilities - The City of Calexico maintains over ninety-
seven (97) lineal miles of roadway (Source: ICTC, 2018). The major existing
circulation facilities, identified per the noted classifications are depicted in
Exhibit F-1 Major Circulation Routes. A more detailed discussion for each
of the facilities identified follows:
Freeway - Article 2 of the California Streets and Highways Code outlines the
definition and identification of freeways and expressways throughout the
State. Section 257 defines a freeway as a “divided arterial highway for
through traffic with full control of access and with grade separations at
intersections”. Section 253 et sequential specifically enumerates which
roadway segments are classified as freeways and expressways and there are
no official freeways within the Calexico Service Area/Sphere of Influence.
79 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
Exhibit F-1 Major Circulation Routes
80 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
• Highway 111 - the Calexico General Plan Circulation Element
identifies a 1.5-mile section of Highway 111 within the City’s Sphere of
Influence between Jasper Road and Heber Road as a Freeway.
Section 253, et sequential, classifies Highway 111 as an expressway.
Highway 111 is a four-lane State-owned highway beginning at the US-
Mexico border extending north through Imperial County. Highway 111
is generally a divided highway, but the portion between West Birch
Street (Highway 98) and 5th Street is undivided. All portions of
Highway 111 are owned, maintained and managed by the California
State Department of Transportation.
Expressway - Section 257 of the Streets and Highways Code defines
expressway as an “arterial highway for through traffic which may have partial
control of access, but which may or may not be divided or have grade
separations at intersections.” The Calexico General Plan Circulation Element
only identifies a small segment of expressway.
• Highway 111 - the Calexico General Plan Circulation Element
identifies a 0.5-mile section of Highway 111 between Jasper Road
and Cole Road as expressway. All portions of Highway 111 are
owned, maintained and managed by the California State Department
of Transportation.
State Highway - Highways are main roads that typically connect major towns
or cities and are designed for high speed traffic. Highways collect a large
volume of traffic with speed limits from 55 to 70 miles per hour. The City of
Calexico has approximately 4.4 lineal miles of highway within its incorporated
City Limits and there is an additional 1.5 miles outside of City Limits within the
Sphere of Influence.
• Highway 111 - The one-mile section of Highway 111 between Cole
Road and Highway 98 continues on as four-lane divided highway. As
previously mentioned, all portions of Highway 111 are owned,
maintained and managed by the California State Department of
Transportation.
• State Highway 98 - Highway 98 is a four-lane undivided highway
that generally runs in an east-west orientation through Calexico.
Raised center medians occur at Estrada Boulevard and between
Rancho Frontera and Andrade Avenue. The Circulation Element calls
for the realignment of Highway 98 north to Jasper Road and
connecting to Dogwood before continuing on to its existing path. All
portions of Highway 98 are owned, maintained and managed by the
California State Department of Transportation.
81 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
Primary Arterials - The Federal Highway Administration (FHWA) defines a
primary (principal) arterial as a roadway that carries the major portion of trips
entering and leaving urban areas. Primary arterials serve significant intra-
area travel, such as between major inner-city communities, central business
district and residential areas, or between major suburban centers. The
Calexico General Plan Circulation Element further defines primary arterials as
roadways designed to have four travel lanes with limited vehicular access
from driveways and streets. The roadways usually have a raised or painted
median with separate left-turn lanes, and intersect with other primary
roadways, major arterials, and secondary arterials at approximately one-
eighth mile intervals.
The City of Calexico has approximately seven lineal miles of primary arterials
within its incorporated City Limits and an additional 3.98 miles within the
sphere of influence. Per the 2015 Circulation Element, the following is a list
of primary arterials with length of miles within the incorporated City Limits:
• Andrade Avenue/Meadows Road (2.0 Lineal Miles)
• Cole Road (1.7 Lineal Miles)
• Cesar Chavez (0.5 Lineal Miles)
• Anza Road (1.8 Lineal Miles)
• Highway 111 (Imperial Avenue) (1.0 Lineal Mile)
Major Arterials - Major arterials move traffic through a City from one
point to another. Speed limits on major arterials are typically 45 mph and are
designed with four lanes. On-street parking should be limited and
residential lots should not have direct access onto major arterials. The City of
Calexico has approximately 1.7 lineal miles of major arterials within its
incorporated City Limits and an additional 6.6 miles within the entire Sphere
of Influence. Per the 2015 Circulation Element, the following is a list of major
arterials with length of miles within the incorporated City Limits:
• Kloke Road (0.8 Lineal Miles)
• Cole Road (1.6 Lineal Miles)
• Bowker (0.5 Lineal Miles)
• 2nd Street (1.4 Lineal Miles)
• Rockwood Avenue (2.6 Lineal Miles)
• Andrade Avenue (0.9 Lineal Miles)
• Rancho Frontera (0.9 Lineal Miles)
• Sapphire Street (0.2 Lineal Miles)
• 5th Street (1.7 Lineal Miles)
82 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
It is important to note that not all roadways meet the roadway width, number
of lanes and speed limit requirements of each classification. The City’s most
principal determinant for classifying a roadway is its relationship to the
hierarchy of the entire circulation systems. For instance, 2nd Street is a one-
way roadway through Downtown Calexico before it becomes a two-way, two-
lane road in other parts of the City. Rancho Frontera, Sapphire Street and 5th
Street are all two-lane roads but are designated as Major Arterials in the 2015
Circulation Element.
Secondary Arterials - Secondary arterials move traffic in a similar manner
as major arterials, except they are designed with two lanes instead of four
lanes. These arterials carry a lower volume of traffic and typically have a
35-mph speed limit. On-street parking should be limited and residential
lots should not have direct access onto secondary arterials. The City of
Calexico has approximately 4.7 lineal miles of secondary arterials within its
incorporated City Limits and an additional 0.5 miles within the sphere of
influence. Per the 2015 Circulation Element, the following is a list of
secondary arterials with length of miles within the incorporated City Limits:
• Grant Street (1.5 Lineal Miles)
• 7th Street (1.4 Lineal Miles)
• Encinas Avenue (0.9 Lineal Miles)
• Rivera Avenue (0.9 Lineal Miles)
Collectors - Local collectors collect a smaller volume of traffic from a
smaller area. Streets are usually two lanes wide with a speed limit of 25 to
30 miles per hour. Access is not restricted and on-street parking is available.
The City of Calexico has over 12 lineal miles of collectors within its
incorporated City Limits. The following is a list of collector streets identified in
the Circulation Map of the 2015 Calexico General Plan:
• Navarro Avenue (0.6 Lineal Miles)
• Williams Avenue (0.4 Lineal Miles)
• Harold Avenue (0.5 Lineal Miles)
• Imperial Avenue (1.0 Lineal Miles)
• Scaroni Avenue (1.0 Lineal Miles)
• Heber Avenue (0.9 Lineal Miles)
• Blair Avenue (0.9 Lineal Miles)
• Beach Avenue (0.6 Lineal Miles)
• King Street (0.4 Lineal Miles)
• Perry Avenue (0.3 Lineal Miles)
• Meadows Drive (0.8 Lineal Miles)
83 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
• Zapata Street (0.5 Lineal Miles)
• Harrington Street (0.5 Lineal Miles)
• Sapphire Street (0.8 Lineal Miles)
• Holdridge Street (0.2 Lineal Miles)
• First Street (0.9 Lineal Miles)
• Belcher Street (0.3 Lineal Miles)
• Sunset Street (0.3 Lineal Miles)
Other transportation facilities that need to be budgeted and planned for are
signalized intersections and bridge facilities. The following is a listing of both
while Exhibit F-2 Traffic Signals and Bridges depicts the location of these
facilities within the City’s Circulation System.
Signalized Intersections - The City of Calexico contains 23 signalized
intersections within the City Limits of which 14 are operated and maintained
by Caltrans. The traffic signals at Highway 111 and Heber Road and Highway
98 and Cole Road are just outside of Calexico’s Sphere of Influence. The
following is an inventory of the nine (9) signalized intersections within the City
that are maintained by the City while an additional fourteen are within Caltrans
Right of Way (ROW) along Highway 98 and Highway 111:
City Owned Traffic Signals
1) 2nd Street and Gran Plaza Way
2) 2nd Street and Gran Plaza Circle
3) Cole Boulevard and Sunset Boulevard
4) Cole Boulevard and Portico Boulevard
5) Cole Boulevard and Rockwood Avenue
6) Cole Boulevard and Yourman Road/Rockwood Avenue
7) Cole Boulevard and Rancho Frontera Avenue
8) Cole Boulevard and Andrade Avenue
9) Cole Boulevard and Van De Graaff Road
Bridges - According to the Transportation for America California Bridges
Report, there are 428 bridges in Imperial County. There are a total of 19
bridges within the City including those owned and maintained by Caltrans and
Bureau of Reclamation. There are an additional five bridges within the Sphere
of Influence. These bridges are largely for, but not limited to, the purpose of
carrying traffic over irrigation channels, drainage channels, rivers, streams, or
highways.
84 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
Exhibit F-2 Traffic Signals and Bridges
85 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
Capital needs for bridges may include lane widening, installation of railing,
abutment retrofit, deck replacement, and reconstruction, etc. The following is
an inventory of all 11 existing bridges within the City Limits as identified by the
Federal Highway Administration National Bridge Inventory as owned by the
City (there are an additional six bridges owned by Caltrans, six by the County
and the All-American Canal at Pruett Road/Railroad Tracks which is owned by
the Bureau of Reclamation):
Bridges Owned & Maintained by the City of Calexico
1) Scaroni Road over Central Main Canal
2) Yourman Road over Central Main Canal
3) Rockwood Avenue over All-American Canal
4) West 2nd Street over New River
5) Anza Road (at west City limits) over All-American Canal
6) Andrade Avenue over All-American Canal
7) Cole Road over Briar Canal
8) Cole Road over Central Main Canal
9) Bowker Road over Briar Canal
10) Bowker Road over Central Main Canal
11) Imperial Avenue East over All-American Canal
Transit & Pedestrian Services and Facilities -There are three IV Transit
bus routes serving the City of Calexico. Line 1 connects Calexico with El
Centro; Line 21 is an express line that connects Calexico with Imperial Valley
College during school days only; and Line 31 is a direct connection between
Calexico and Brawley. There are a total of eight bus stops equipped with bus
shelter facilities within the City Limits as noted:
86 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
• Hacienda Street between Imperial and Ollie (lines 1 and 21)
• Ollie Avenue at Post Office (line 21)
• 3rd Street and Paulin Avenue (lines 1, 21, and 31)
• Rockwood Avenue at Robert Kennedy (line 1)
• Grant Street at Cesar Chavez (line 21)
• Encinas Avenue at Library (line 21)
• Encinas Avenue at 7th Street (line 21)
• Cole Road west of Rockwood Avenue (line 21)
The City of Calexico had adopted offsite standards to require sidewalks of all
new development. The standard requirement is a five-foot-wide sidewalk. A
cursory review of aerial photographs through 2016 Google Earth shows that a
majority of developed areas of Calexico are served with existing sidewalks,
especially within residential areas. There are a few non-continuous sidewalks
within various industrial areas such as Cesar Chavez Boulevard south of
Grant Street, Harold Avenue between Lincoln Street and Sheridan Street, and
Van de Graaf Avenue south of Robinson Avenue.
b) Adequacy of Existing Facilities
Roadway Adequacy - The existing circulation system is adequate to
accommodate the current needs of the City. Existing roadways properly link
existing land uses. A thorough analysis of the Calexico pavement system had
not been completed as of the date of this SAP. Under typical Roadway
Analysis a report is established which creates a single score that represents
the overall condition of the pavement known as the Pavement Condition
87 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
Index (PCI). The PCI adds 33% of the roughness index and 67% of the
surface distress index to provide a range. PCI ranges are divided into the
following six descriptions: 85-100 are described as excellent, 70-85 are
described as very good, 60-70 are described as good, 40-60 are described
as fair to marginal, 25-40 are described as poor, and 0-25 are described as
very poor. Roadways with an index lower than 40, are considered to require
major investment and in need of major rehabilitation or reconstruction. In
October of 2016 the Rural Counties Task Force commissioned a Report
through the League of Cities under which NCE Consultants in collaboration
with Quincy Engineering completed a Final Report on California Statewide
Local Streets and Roads Needs Assessment. The City of Calexico’s streets
and roads were estimated an overall PCI Index of 50-60 (At Higher Risk).
Additional traffic generated as a result of new development also impact
roadway adequacy. The Gran Plaza Phase 2 Power Center Environmental
Impact Report identified Highway 111 between Highway 98 and Grant
Street/8th Street as operating at Level of Service (LOS) E. The cumulative
impacts resulting from the buildout of all residential development projects
would further decrease the operating condition of Highway 111 between
Highway 98 and Grant Street/8th Street to LOS F.
Bridge Facilities Adequacy - According to the Federal Highway
Administration’s National Bridge Inventory (NBI) and Caltrans Structure
Maintenance and Investigations (SM&I), all bridges within the State Highway
system owned and maintained by Caltrans are in good condition. The April
2018 Local Agency Bridge List from SM&I, however, shows eight out of
eleven bridges owned by the City of Calexico as structurally deficient.
• Bowker Road over Briar Canal (Bridge #58C0030) - Poor
• Bowker Road over Central Main Canal (Bridge #58C0031) - Poor
• Yourman Road over Central Main Canal (Bridge #58C0036) - Poor
• Scaroni Road over Central Main Canal (Bridge #58C0037) - Fair
• Andrade Avenue over All-American Canal (Bridge #58C0097) - Poor
• Anza Road over All-American Canal (Bridge #58C0104) - Poor
• Cole Road over Briar Canal (Bridge #58C0109) - Poor
• Cole Road over Central Main Canal (Bridge #58C110) - Poor
Caltrans either classifies bridges as acceptable or structurally deficient, but
also provides a Bridge Health Rating which identifies the structural condition
of the bridge or culvert based on condition ratings. The rating is listed as
“Good,” “Fair,” or “Poor” based on the lowest condition rating of the deck,
superstructure or substructure for bridges and the culvert condition rating
88 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
identifies the overall condition of the culvert. The Scaroni Road Bridge over
the All-American canal although fair, was also noted as structurally deficient.
Traffic Signal Facilities Adequacy -
The Environmental Impact Report (EIR) for Gran Plaza 2 (certified in June
2015) examined the cumulative impacts of all planned development outlined
in this Service Area and projects just outside of Calexico’s Sphere of
Influence. The EIR noted the need for a new signalized intersection at
Rockwood Avenue and 2nd Street to accommodate future traffic from all
development projects.
A complete traffic signal system for a typical four-way intersection within City
right-of-way may cost about $250,000 to $300,000 while routine maintenance
and part replacement including ongoing costs for electricity, painting, re-
lamping, and other minor improvements can be minimally budgeted for. The
Manual of Uniform Traffic Control Devices recommends periodic replacement
of signal heads, controller upgrade every ten years, and timing service
updates every three to five years, or more frequently depending on growth
and changes in traffic patterns.
Pedestrian Facilities Adequacy - The Imperial County Transportation
Commission (ICTC) prepared a Regional Safe Routes to School Master Plan
which includes pedestrian and bicycle routes to all schools in Calexico. A full
inventory of sidewalks was not done as part of the study, but deficiencies were
identified through a series of stakeholder meetings held at each school.
Deficiencies noted in the Safe Routes to School Master Plan were mainly
related to crosswalks and bicycle routes, but the Plan did identify the lack of
sidewalks at the following locations;
• Enrique Camarena Junior High School vicinity on the east side of
Rivera Avenue from Birch Street to Paseo Camino Real for a distance
of approximately 1,580’. It is important to note however, that
Camarena Junior High School is currently located just outside of the
City limits and no other developments exist on the east of Rivera
Street.
c) Future Demand of Facilities & Planned Facilities
As the City of Calexico continues to grow, future improvements will be
required to build streets in accordance with the design standards set
forth by the City of Calexico Engineering Department and with a Complete
Street focus. In some instances, new development will demand new
roadways, traffic signals or other improvements altogether.
89 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
Planned Roadway Facilities - Future roadway improvements should be
designed to provide a circulation network that prioritizes and provides safe
and convenient, and attractive facilities for all users of the system. As a
result of cumulative impacts from future growth of the City, the Circulation
Element and the 2015 Gran Plaza 2 EIR calls for the following improvement
shown in Table F-3.
Table F-3 Roadway Segment Traffic Forecast
Future Average Future Level Project
Street
Daily Traffic of Service Description
Bowker Road
35,200 E Road Widening
(Heber Road to SR-98)
Cole Road
31,090-35,000 D/E Road Widening
(Kloke Road to Bowker Road)
2nd Street
19,600 D Road Widening
(Dogwood to Cesar Chavez)
2nd Street Increase Number
25,830 F
(Highway 111 to Andrade) of Lanes
Cesar Chavez Road
46,700-49,300 F Road Widening
(2nd Street to SR-98)
Rockwood Avenue
NA F Signalization
(at 2nd Street)
Source: General Plan Circulation Element and 2015 Gran Plaza 2 Environmental Impact Report
Planned Bridge Facility Improvements
The June 2016 SM&I Bridge List shows the West 2nd Street bridge as
structurally deficient and the City has earmarked the 2nd Street Bridge
Replacement Project for near-term improvement, at a budget of $2.6 million
in Successor Agency and Measure D funds.
The Kloke Avenue Bridge at the All-American Canal although not rated as
deficient, is targeted by the City for Capital Improvement. Specifically, Bridge
Widening to accommodate increased traffic flow is proposed.
d) Opportunities for Shared Facilities
While there are no real opportunities for shared roadway facilities with an
adjacent jurisdiction, the City’s system links to the State and with the County
roadway system. The City continues to work with local and State government
agencies to monitor the operation of the regional system for implementation of
90 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
necessary improvements.
e) Phasing
Capacity-enhancing roadway improvements will be constructed as each new
development occurs. Each new development project will be responsible for
the improvements to roadway segments and intersections to address project-
related impacts to the transportation system. Developers are also required to
pay transportation development impact fees to address cumulative and city-
wide impacts. Roadway improvement projects to be undertaken within the
next five years, as outlined in the 2017-2022 Capital Improvement Program
are listed below.
Short Term (< 5 Years)
• Widen 2nd Street Bridge (Airport Road to Cesar Chavez Boulevard)
• Improve Various Streets within La Jolla Palms (Hearthstone) Subdivision
• Widen Meadows Road north of Cole Road (for El Portal Subdivision)
• Widen/Extend Cleveland Ave (for El Portal & Las Palmas Subdivisions
• Widen Cesar Chavez Road from 2nd Street to Highway 98
Long Range (10-20 Years)
• Widen Bowker Road (Heber Road to Highway 98)
• Widen Cole Road (Kloke Road to Bowker Road)
• Widen 2nd Street (Dogwood Road to Cesar Chavez Road)
• Widen 2nd Street (Highway 111 to Andrade Road)
• Install New Traffic Signal at Rockwood Avenue and 2nd Street
3. Mitigation for Circulation & Transportation Facilities
Most of the circulation improvements identified will be constructed by the future
developers as development occurs. The following are the recommended
mitigation measures:
C-1 For all collectors, the developer shall be responsible for
street improvements to .05 width or minimum of one travel
lane, curb, gutter, and sidewalk constructed to City
standards for all land fronting on said collectors.
C-2 For Major and Secondary Arterials, the developer shall be
responsible for frontage improvements including two
medians, one travel lane, curb, gutter, and sidewalk.
C-3 New development that results in increased traffic impacts
that exceed 5,000 vehicles per day on local streets shall
91 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
provide for a traffic study to outline needed improvements
to mitigate the increased traffic levels.
4. Financing
The existing funding sources for circulation improvements, maintenance and
operation come from Motor Vehicle In-Lieu Tax, State Gas Tax, FHWA
Grants, and LTA Measure D as well as developers via Development Impact
Fees. The City of Calexico also has Community Facility Districts that collect for
Street Improvements for the limited serviced area. The City of Calexico budgets
an estimated $2.5 to $3.5 million annually for capital improvements and an
estimated $200,000 for Roadway Maintenance and Rehabilitation. Pedestrian
and transit amenities also have a steady annual stream of approximately $75,000
in total. Revenue generated by development impact fees, CFD’s, grant
resources, and other taxing mechanisms which are reserved for roadways are
placed in a separate fund and are used for specific circulation system and
roadway capital improvement projects.
a) Current Costs and Per Capita Costs for Operation & Maintenance
Public Works Department Administration has an annual General Fund Cost
of $1,128,379 and as of 2018 oversees the Calexico Airport, Engineering,
Street Operation and Maintenance, Park Maintenance, Water and
Wastewater operations, Solid Waste and Transit. These cost sharing
responsibilities have demonstrated to result in substantial savings for the
City of Calexico. It is difficult to approximate the costs that are directly tied to
the operation and maintenance of street facilities given that only Park
Maintenance costs are identified independently at $331,738. The actual
annual cost for the continued operation and maintenance of the circulation
system in the City of Calexico that is funded through the General Fund
would be a proportion of the remaining $796,641.
According to the historic per capita cost under the 2006 SAP, a per capita
cost of $95.30 had been used by the City for the purpose of projecting street
maintenance costs. Assuming 75% of the remaining Public Works Budget
(remaining after park costs are extracted), a total of $597,480 may be
applied for a per capita of $14.32.
$597,480/41,714 population = $14.32 per capita
Although this figure is substantially lower than per capita costs previously
used, this figure is closely comparable to the City of Imperial which has a per
capita cost of $17.72 and operates under a similar administrative structure.
Table F-4 that follows applies the projected street Maintenance Costs at the
92 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN CIRCULATION & TRANSPORTATION
$14.32 per capita cost.
Table F-4 Projected Street Maintenance Costs
Year Project Population Street Maintenance Cost
2020 46,639 $667,870
2025 57,421 $822,269
2030 66,912 $958,180
2035 77,972 $1,116,559
2040 90,860 $1,301,115
b) Future Funding Sources
The City of Calexico will continue to use some of the same funding sources
as it has used in the past. Objective 9 of the General Plan Circulation
Element states “the financing of expansion to the City circulation system
made necessary by development shall be borne by the proposal applicants,
while the maintenance and improvements of the existing street system shall
be borne by the City and its residents.”
Policy 9of the Circulation Element, Section b. requires that the City
implement appropriate fee ordinances, including financing districts or other
mechanisms for developers to pay their fair share. The existing circulation
system can continue to be funded with established sources and new grant
opportunities as they become available through Caltrans or FHWA. These
would include the Highway Safety Improvement Program, The Safe,
Accountable, Flexible, and Efficient Transportation Equity Act (SAFETEA),
the Surface Transportation Program (STP), and other state and federal
grants. Further descriptions of these and other financing mechanisms are
provided in the Financing section of this Service Area Plan.
93 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
G. STORMWATER AND DRAINAGE
The primary purpose of maintaining, planning, designing and constructing drainage
facilities is to control flooding. Drainage facilities in the entire Imperial Valley are
within the jurisdiction of the Imperial Irrigation District (IID). In conjunction with an
irrigation network that includes more than 1,600 miles of canals, IID operates and
maintains an agricultural drainage system consisting of more than 1,400 miles of
surface drains. The City of Calexico discharges into IID drains which ultimately drain
into the New River, a tributary to the Salton Sea. It should be noted, however, that
the primary drainage system managed by IID is not designed to convey all
stormwater runoff from urbanized areas. Therefore, new development must provide
for on-site retention of stormwater to mitigate against stormwater impacts to
properties and the IID system.
1. Performance Standard
Adequacy of drainage facilities is based on conformance with the City of
Calexico design guidelines for stormwater runoff and management as
incorporated into the 2005 Design Procedures and Improvement Standards. All
new development is required to comply with these standards and to retain
stormwater on site for a minimum of 72-hours prior to releasing it into an
approved stormwater conveyance system. Conveyance out of the retention
basins is restricted by the use of 12" pipes. The outflow restriction into IID drains
can result in detention times in excess of 72-hours (three days). Detention for
longer than 3 days requires the implementation of a mosquito abatement
program in order to comply with the County Health Department standard. The
stormwater detention basin criterion is based on a 50-year storm event or rainfall
maximum of 3.0 inches over a 24 hour period.
Conformance with the City’s National Pollution Discharge Elimination System
(NPDES) requirements is also implemented for all development projects within
the City. As authorized by the Clean Water Act (CWA), the NPDES Permit
Program controls water pollution by regulating point sources that discharge
pollutants into waters of the United States through Best Management Practices.
The requirements of the Colorado River Basin Water Quality Control Plan,
Federal Emergency Management Agency and the requirements established by
the IID and the City’s Design and Improvement Standards adopted in 2005 for
stormwater runoff are also applicable.
94 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
2. Facility Planning and Adequacy Analysis
Catch basins are the entrance into the City’s Storm Drain System. The City of
Calexico’s stormwater drainage facilities include many ditches, pipes, and
detention basins which function to divert storm runoff and standing water away
from residences and business within the City. These facilities convey
stormwater runoff into the main water drainage system managed by the IID
and the majority ultimately drains to the New River, northwest of the City. Some
drains will flow easterly, and ultimately to the Alamo River all via IID drains.
However, the IID has communicated interest in abandoning all facilities within
incorporated areas and for each City to take over the respective systems.
Additionally, as future development occurs and drainage facilities are no longer
used for agricultural drainage, the IID will abandon those facilities to the City, so
that the IID only manages drains used for agriculture.
a) Inventory of Existing Facilities
Stormwater management within the City of Calexico utilizes a combination of
surface flow, storm drain piping within roadway right-of-ways and detention
basins which serve specific areas of development before it is released into
the IID system. Not all retention basins within the Sphere of Influence and
official City Limit boundary are owned by City of Calexico. Some of the
retention basins identified within the Sphere of Influence and owned by the
City of Calexico or under a City managed CFD are listed in Table G-1.
95 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
Table G-1 Stormwater Retention Basin Inventory
Pump
Acres APN Location Owner
Station
Sam Ellis Street
2.80 058-861-023 City of Calexico
(next to Raw Water Reservoir)
Kennedy Garden Large Park
2.73 058-917-002 City of Calexico
(SW Corner Zapata & Granero St)
Southeast Corner of Rancho
2.00 058-832-020 City of Calexico
Frontera and Meadows Drive
Meadows Drive
2.92 059-488-028 YES City of Calexico
(near Yturralde Street)
058-782-001 Rancho Frontera Park
4.01 YES City of Calexico
058-781-002 (Rancho Frontera & Harrington St)
Meadows North Park
1.05 058-756-001 City of Calexico
(Meadows St & Holdridge St)
Meadows South Park
2.05 058-751-029 YES City of Calexico
(Andrade Street and Rosas Street)
058-702-017
YES Valle de Oro Park
058-692-005
1.12 (Avenida de Oro between E. Calle City of Calexico
058-582-043
de Oro and Holdridge Street)
058-582-025
Northwest Corner 2nd Street and
6.53 058-904-036 City of Calexico
Rodney Avenue
YES
059-010-049 La Jolla Palms Subdivision La Jolla Palms
15.0
059-010-050 (City Pump Station)
El Dorado Park
6.05 059-353-001 City of Calexico
(Sapphire St and Meadows Rd)
YES
Zapata Park
3.67 059-411-033 City of Calexico
(Zapata & All-American Drain)
YES
Hems Brothers
0.31 058-570-032 Behind Hems Bros Mortuary
City Pump Station
Jose Zyman
12.82 059-170-005 YES Bowker Road & Central Main
(City Pump Station)
Source: Public Works Department, Calexico Storm Drain Lines Map, and Caltrans Right-of-Way Maps
The City stormwater facilities are located throughout several drainage zones.
The City of Calexico is divided into eleven existing drainage zones with
varying sizes of tributary area as denoted in Exhibit G-1 Retention Facilities
and Drainage Zones. This system ultimately discharges into surface
drainage ditches to ultimately convey stormwater to the IID drains. The IID
maintains an extensive gravity flow drainage system that serves the entire
Imperial Valley. The native material and concrete lined lateral drain system
was designed to provide a drainage outlet for each governmental subdivision
of approximately 160 acres. The IID allows a single 12’’ diameter pipe for
96 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
every 160 acres.
Exhibit G-1 Retention Facilities and Drainage Zones
97 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
The IID is obligated to provide its drains at sufficient depth, generally 6-10
feet deep in order to be able to accept tile drain discharge. Where the drain
cannot be maintained at sufficient depth, a sump and pump are provided and
maintained by the IID.
The primary drainage facilities receiving the City of Calexico’s stormwater,
and managed by the IID, include the Strout Drain No. 2 to the north, the All-
American Drain No. 7 and No. 8 (with extension to both) as well as the New
River. The eleven existing drainage zones that tie into these drains depicted
in Exhibit G-1 are further described below.
➢ Drainage Zone 1 (Downtown): This area is bounded by Highway 98/Birch
Street to the north, Andrade Avenue to the east, U.S. Border to the south
and the All-American Canal to the west. Drainage within this boundary is
conveyed by a network of small storm drain piping (8” to 36”) and
ultimately discharged into the New River.
➢ Drainage Zone 2 (Kennedy Gardens/Kloke Tract/Rockwood Village
Area): This boundary area is defined with Cole Road to the north, Vega
Street to the south, City limit to the east, and Ollie Avenue to the west.
The area is served via a 60” RCP storm drain from the Kennedy Gardens
Subdivision crossing Highway 111, traveling westerly adjacent to
Camacho Road and ultimately discharging west of the Union Pacific Rail
Road tracks. Connected to this system are the Rockwood storm drain and
the Calexico Industrial Park drainage systems.
➢ Drainage Zone 3 (Wal-Mart Super-Center/Toy’s “R” Us Area): This area
is adjacent to Highway 111 between Cole Road and the Central Main
Canal. It includes an on-site retention basin and discharges into the IID
Strout Drain.
➢ Drainage Zone 4 (Rancho Frontera Subdivision North): This area is
located east of the Kennedy Gardens and north of the All-American
Canal. It includes an on-site detention basin and discharges into the IID
All-American Drain No. 7.
➢ Drainage Zone 5 (Rancho Frontera Subdivision South): This area is west
of Meadows Road, between the All-American Canal and Highway 98, and
discharges into IID All-American Drain 8.
➢ Drainage Zone 6 (Meadows Subdivision/Villa Hermosa Condos): This
area is east of Meadows Road and north of Highway 98. It includes on-
site retention and discharges into All-American Drain 8-A No. 1 and No. 2.
98 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
➢ Drainage Zone 7 (Valle Real/Villa Santa Fe Subdivision): This area is
east of Andrade Avenue, between Seventh Street and Highway 98. It
includes an on-site detention basin and discharges into 16” storm drain
systems in Andrade Avenue northbound to IID All-American Canal Drain
8-A No.1 at Highway 98.
➢ Drainage Zone 8 (Rancho Elegante Subdivision): This area is east of
Andrade Avenue, north of the International Boundary line. It includes an
on-site detention basin and discharges into the 24” First Street storm
drain system.
➢ Drainage Zone 9 (Tierrasanta Subdivision): This area is bounded by
Highway 98 at the east, All-American Canal at the north, and All-
American Canal Drain 8-A No. 2 to the west. It includes on-site detention
and discharges into All-American Canal Drain 8-A No.2.
➢ Drainage Zone 10 (Las Brisas Subdivision): This area is bounded on the
north by Highway 98, on the west by Andrade Avenue, on the east by E.
Rivera, and on the south by Second Street. It is designed to be self-
contained with a detention basin within the development tract.
➢ Drainage Zone 11 (Bravo/Rodiles/Las Palmas, El Portal, and La Jolla
Palms Area) This drainage area uses the Regional Drainage Concept
design but built individually by the separate developments. The retention
basin is located between the Central Main Canal and the northern
boundary of the development tracts with three separate basins
interconnected and will be connected with the IID Strout Drain.
b) Adequacy of Existing Facilities
The existing primary drainage system managed by the IID is not designed to
convey all stormwater runoff from urbanization. Therefore, recent and new
development must provide for on-site retention of stormwater to mitigate
against stormwater impacts. These retention facilities are designed to control
stormwater flows into the IID drains per the previously stated standards.
The City of Calexico Public Works Department Water Pollution Control
Section provides the maintenance of the City stormwater drainage system.
The public works crews monitor the flow within the drainage ditches,
make minor repairs and clean the ditches on an as needed basis. Street
sweeping occurs throughout the City, which is a preventative method that
assists in keeping the drainage ways clean of some debris and sediment.
Additionally, park maintenance staff maintains the dual use park/detention
basins. According to the City of Calexico Public Works Department Manager
the current stormwater system provides adequate conveyance of
stormwater for events up to a 50-year storm.
99 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
c) Future Demand for Facilities and Planned Facilities
As future development occurs, stormwater drainage systems must be
installed and constructed into the project area to ensure adequate collection
and conveyance of runoff. The type and extent of the development
proposed will affect the demand of facilities. A significant increase in the
amount of impervious surfaces will result in a greater amount of surface
runoff. The exact size and location of future facilities will be determined at
the time development is proposed and processed through the City of
Calexico. All future development must continue to comply with IID policies
regarding temporary retention of stormwater to reduce the impacts to the IID
drains.
Stormwater runoff as well as other contributing factors has degraded
both the New River and Alamo River. The recently updated Water
Quality Control Plan for the Colorado River Basin Region prepared by the
California Regional Water Quality Control Board contains strict
requirements for the water quality conveyed into these rivers. Future
facilities must be designed to adhere to the latest pollution control devices
and NPDES requirements. Consistent with proposed development, Drainage
Zone Areas proposed to be annexed and improved in conformance with the
City’s Sub-Regional Drainage Concept design requirements as noted in
Exhibit G-2 -Planned Drainage Facilities and further described below:
➢ Drainage Zone 12 This drainage area is bounded to the west by E.
Rivera Street and Highway 98, to the north by the All-American Canal,
and to the south by Anza Road (Second Street) along the U.S. –
Mexico International Border.
➢ Drainage Zone 13 (Jasper/Bowker Road Corridor Area): This
drainage area is bounded to the west by Highway 111, to the south by
the Central Main Canal (CMC) and Cole Road, to the north at
Heber/Fawcett Road, and to the east at approximately one mile east
of Bowker Road.
➢ Drainage Zone 14 (West Jasper Road Area): The basin area for this
area is Jasper Road to the north, Central Main Canal to the south,
Highway 111 to the east, and Dogwood Canal to the west. This
tributary area can utilize IID facilities of the Strout Drain/Drain No. 1,
Alder Drain, Alder Drain No. 2 and Central Drain No. 3-F.
100 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
Exhibit G-2 Planned Drainage Facilities
101 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
➢ Drainage Zone 15 (Dogwood/Kloke Road Area): This area is
bounded by Jasper Road to the north, Highway 98/All-American
Canal to the south, Union Pacific Railroad to the east, and Dogwood
Road to the west. This tributary area can utilize IID facilities of the
Beech Drain, AA Drain No. 9, and possible off-site Birch Drain No. 3.
➢ Drainage Zone 16 (Southwest Area): This area is bounded by
Highway 98 to the north, U.S. - Mexico International border to the
south, All-American Canal to the east, and Hammers Road to the
west. This tributary area can utilize IID facilities and/or discharges into
the New River.
Although less common than the use of detention basins, other portions of
Calexico utilize storm drain piping that discharges into the New River.
Increased use of the New River for handling drainage is constrained by the
fact that new underground piping would have to be installed at considerable
expense and involving multiple agencies in the permitting process. For these
reasons, extensive use of new storm drains to the New River is not
anticipated.
d) Opportunities for Shared Facilities
As previously noted, some of the stormwater detention facilities serve a dual
purpose as park facilities, thus staff and maintenance costs are shared for
those dual-purpose basins. The City of Calexico expects to manage and
restrict these dual uses based on trial and error and best management
practices. The City of Calexico will continue to maintain all storm drain
facilities within the incorporated City limits using full-time and part-time staff.
Assistance from other jurisdictions for drainage services is not provided or
necessary beyond the maintenance provided by IID for IID Drains. The City of
Calexico and IID maintain different aspects of the total drainage system. As
previously noted, the primary drainage system is managed by IID but it is
not intended to convey stormwater All-American generated by urban
runoff. However, some urban stormwater does flow into the IID drainage
system. At this time, the management of these facilities is effective and is
not expected to change in the near future.
e) Phasing
The construction of future stormwater drainage facilities is based on the
rate of new development within the City of Calexico or as new areas are
annexed into the City. Additional stormwater drainage facilities will be
needed in the proposed annexation areas in order to convey stormwater into
the IID drainage system. The future stormwater management systems for
the annexation areas will be designed during the Tentative Map and Final
Map stage of development and constructed concurrent to specific
102 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
development projects. Some new developments may be able to drain into
the Sub-Regional basins, so a combination of construction of drains or impact
payment in lieu of fee may be applicable.
3. Mitigation for Stormwater & Drainage Facilities
The City of Calexico should continually monitor the existing storm drain
facilities to ensure the facilities are operating at an adequate level. Specifically,
the City should implement the following mitigation measures for drainage
facilities:
D-1 All future development in the City of Calexico shall be required to
construct storm drain facilities in accordance with the design
standards of the Engineering Department and the IID necessary to
convey stormwater into existing drains managed by IID.
D-2 All future development shall retain stormwater on-site or within
existing retention basins to restrict stormwater flow for a minimum
period of 72 hours before discharging into IID facilities.
D-3 All future development shall ensure compliance with all local, state
and federal rules and regulations related to the discharge of
stormwater.
D-4 All development shall provide improvements constructed pursuant to
best management practices as referenced in the California
Stormwater Best Management Practices Handbook.
D-5 The City of Calexico should establish a policy for the collection of
assessments via a CFD or CSD for the continued operation and
maintenance cost resulting from new development.
4. Financing
Future stormwater drainage facilities will be installed at the developer’s expense
at the time of project construction. Maintenance of existing and future public
drainage facilities will be financed by the City of Calexico General Fund. The City
also approved Measure “H” in 2010 which is a .05 cent sales tax to be used for
general government purposes and is scheduled to be available through 2040 that
may be used for operation and maintenance of City owned drainage facilities.
a) Funding Sources and Per Capita Costs
The current revenue sources for stormwater drainage facilities include
property and sales taxes, licenses and permits, and other miscellaneous
general fund sources. The City uses Measure “H” funds to some extent since
some of the storm drain facilities are dual use park/detention basin. The City
does not segregate out the maintenance and operation costs for storm
drain facilities. Thus, the maintenance and operation costs of the
stormwater drainage system could not be accurately determined.
103 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN STORMWATER & DRAINAGE
However, based on information provided by the City Public Works
Department, it is estimated that approximately $10,000 per year is spent
on maintenance and operation costs. The amount fluctuates depending on
the amount of rain that is received on any given year.
The average per capita cost for the continued maintenance and
operation of the stormwater drainage system was determined by the City’s
current population and the estimated $10,000 per year amount for
maintenance and operation. The per capita cost for drainage facilities is
assumed to be $0.24.
$10,000 / 41,714 population = $0.24 per capita
A cost estimate for future continued maintenance and operation of the
stormwater drainage facilities is provided in Table G-2-Drainage Facilities
Costs. These estimations assume a constant cost per capita in 2018
dollars and the provided population projections.
Table G-2 Projected Drainage Facilities Costs
Project/Planned Drainage Facility
Year
Population Costs
2020 46,639 11,193
2025 57,421 13,781
2030 66,912 16,059
2035 77,972 18,713
2040 90,860 21,806
b) Future Funding Sources
The City of Calexico will continue to use the existing funding sources for the
maintenance and operation of City stormwater drainage facilities which
include property and sales taxes, licenses and permits, and other
miscellaneous sources. Most storm facilities are incorporated into the street
system thus the City should ensure that all transportation projects adequately
address stormwater flow and impacted areas. In order to accommodate
future growth anticipated, other funding sources for capital stormdrain
improvements will be needed.
The City collects development impact fees; however, there is currently no
impact fee for drainage facilities. Other funding sources that could be made
available are a City wide community facilities district, special assessment
districts or a community services district. These mechanisms should be
further explored, at minimum for independent drainage zones. Further
descriptions of these and other financing mechanisms are provided in the
Financing section of this Service Area Plan.
104 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
H. WATER FACILITIES
The City of Calexico owns, operates and maintains a system for the treatment,
storage and distribution of potable water resources. Raw water from the Colorado
River is delivered to the City of Calexico by the Imperial Irrigation District (IID)
through the All-American Canal which primarily runs in an east-west orientation
through the City. The raw water is then treated, stored, and disturbed through the
City’s Water Distribution System which is owned and operated by the City of
Calexico Water Operations. The maintenance and operation is financed through an
Enterprise Fund.
The City of Calexico’s Water Treatment Plant and Water Distribution System
operates as Water System No. 1310002, via Water Supply Permit No. 05-14-02P-
011 as issued by the Division of Drinking Water. Permit No. 05-14-02P-011 was
issued on May 27, 2003 and it does not expire until such time the Water Plant is
upgraded and an amended permit is issued by the Division of Drinking Water. All
information for this section was acquired from the Water Supply Permit and from the
Water Master Plan in progress by The Holt Group, Inc. in June of 2018. For
additional details, the Water Master Plan should be consulted (See Appendix D).
1. Performance Standard
Treatment - Potable water must meet or exceed the requirements set forth in the
California Safe Drinking Water Act, California Health and Safety Code, California
Code of Regulations Titles 17 and 22, and any regulations, standards, or orders
adopted thereunder. The requirements and standards for potable water are set
and regulated by State Water Resources Control Board, Division of Drinking
Water (Division of Drinking Water) and the US Environmental Protection Agency.
105 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
The design criteria are based on Maximum Day Demand (MDD) plus fire flow.
The potable water system must be able to adequately treat and provide 125
gallons per person per day as well as fire flow minimums. The plant must be able
to treat 11.2 million gallons per day (MGD).
Storage - Storage required is the maximum day demand plus the fire flow
demand.
Distribution - The Performance Standards for water distribution are set from
California Code of Regulations Titles 17 and 22. There are design criteria that
must be met to ensure that adequate potable water supply and fire flow needs
are provided. System pressures for the water distribution system must be
maintained under normal and peak demand conditions. The design criteria are
based on the Maximum Day Demand @ Peak Hour plus fire conditions
(MDPHF). Peaking factor is 2.0. The design criteria acceptable by the City of
Calexico is noted in the proceeding Table H-1:
Table H-1 Water Distribution & Fire Flow Standards
Item Criteria
Pipe Criteria
Maximum Diameter and Velocity 4” Diameter/8 fps
Minimum Pressure at meter/ hydrant (Max Day + Fire) 20 psi
Fire Flow Criteria
Single Family Residential¹ 1,000 GPM/20 psi
Commercial 2,000 GPM
Industrial 2,500 GPM
¹Multi-Family Residential fire flow criteria is based on construction type and size of structure.
Source: The Holt Group Inc, 2018 Water Master Plan
2. Facility Planning and Adequacy Analysis
The City of Calexico pumps raw water via a 42-inch diameter intake pipeline and
stocks a 25 million gallon raw water reservoir with water for a short period of time
(less than a week). A total capacity of 35,755 acre-feet per year (approximately
31.6 MGD) of raw water can currently be supplied to the City via the pipeline and
reservoir system. The raw water reservoir acts as the holding tank for the City’s
water treatment plant for treatment and distribution. The City utilizes a number of
facilities to treat water to an acceptable level of compliance as further discussed
below. Exhibit H-1-Existing Water Facilities illustrates the various water
treatment, storage and distribution facilities owned and operated by the City.
106 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
Exhibit H-1 Water Facilities
107
CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
a) Adequacy of Existing Facilities
Water Treatment Plant - The City of Calexico has been treating water from
the All-American Canal and providing potable water to its customers since
1910. The City’s total raw water storage capacity is 25 million gallons (MG) in
an open reservoir. Raw water is treated using a sedimentation, filtration and
disinfection process in compliance with the California Safe Drinking Water
Act.
As previously noted, the design criteria are based on Maximum Day Demand
(MDD) plus fire flow. The potable water system must be able to adequately
treat and provide 125 gallons per person per day as well as fire flow
minimums. Based on the 2018 Water Master Plan, the MDD is 10.60 MGD.
The water treatment plant must be able to treat 11.2 million gallons per day
(MGD). The following Table H-2 is a summary of the inventory and capacity
of individual plant components:
Table H-2 Water Treatment Plant Components/Capacity
Component Capacity
Raw Water Transfer Pump Station (Canal to Reservoir) 30 MGD
Raw Water Reservoir 25 MGD
Raw Water Transfer Pump Station (Reservoir to WTP) 26 MGD
30” Raw Water Line 25 MGD
Clarifiers 14 MGD
Filters 12 MGD
WTP Transfer Pump Station 16 MGD
Finished Water Reservoir Tanks 10 MGD
Distribution Pump Station 26 MGD
Disinfection 16 MGD
Source: 2018 Water Master Plan
Water Storage - The City’s total raw water storage capacity is 25 million
gallons (MG) in an open reservoir. After treatment the City pumps a total of
10 MG of finished water into two (2) above-grade, fabricated steel tanks (6.0
MG and 4.0 MG) located at the treatment plant. The City also has a
distribution reservoir with a capacity of 6.0 MG above-grade, fabricated steel
tank storage located on Cole Boulevard approximately 1/3 mile east of
Bowker Road for a total storage capacity of 16 MG.
Pump Stations - The City has one distribution water pump station at the
treatment plant which maintains water pressure in the City. As previously
noted, the City lacks gravity pressure due to its flat terrain and a total of
108 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
seven (7) pumps transfer potable water from the storage tanks to the City’s
distribution system. The pumps have a combined total capacity of 18,200
GPM (gallons per minute) or 26 MGD and discharge at a pressure of about
62 pounds per square inch (PSI). Aside from the water treatment plant’s
distribution pump station there is a distribution pump station at the East Side
Reservoir which assist in maintaining water pressure within the northeast
section of the water distribution system. The pump station has two (2) pumps
with a capacity of 6,000 GPM or 8.5 MGD.
Water Pipelines - The existing water distribution system includes 103 miles
of pipelines ranging in size from 2” to 30” as provided on Table H-3. The
pipeline system is composed of cast iron pipes and polyvinylchloride (PVC)
pipes. The cast iron pipes are the oldest and account for only 11% of all
pipelines. All new pipelines are required to be PVC.
Table H-3 Water Pipelines
Size of Pipeline Length LF Pipeline Material
2” 3,400 Cast Iron
2” 6,700 PVC
4” 15,800 Cast Iron
4“ 14,700 PVC
6’ 27,500 Cast Iron
6” 59,400 PVC
8” 2,700 Cast Iron
8” 231,300 PVC
10” 9,200 PVC
12” 8,700 Cast Iron
12” 131,700 PVC
18” 2,300 Cast Iron
24” 30,700 PVC
30” 1,200 PVC
Source: The Holt Group, Inc. 2018 Water Master Plan
b) Adequacy of Existing Facilities
Water Treatment Plant - The City’s Water Treatment Plant was completely
rebuilt in 1950. It has received upgrades throughout the years with the most
recent major improvements in 2002 to include a Plant C clarifier and new
Plant B dual media filters. Since 2002, the total finished water reservoir tanks
at the water treatment plant were upgraded to 10 million gallons and a 6.0
million gallon remote reservoir tank was also added.
There have been no incidents of effluent quality violations in the past four
years. A citation was issued in October 2014 for exceedances in total
trihalomethanes (TTHM). The City was able to comply with the directives
outlined in the citation and no other enforcement actions were taken since
2014.
109 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
Although the Calexico Water Treatment Plant is designed as a 16 MGD
Plant, in its current condition it is only capable of producing up to 12 MGD of
drinking water. This is largely attributed to damages resulting from the 2010
Easter Earthquake which damaged one clarifier and one filter unit. With an
existing capacity of 12 MGD, the treatment plant is operating at 60% capacity
based on an average daily demand of 7.15 MGD, and 88% capacity based
on a maximum day demand of 10.6 MGD. The City needs to take proactive
measures for Water Treatment Plant Improvements.
Water Storage - The current water storage demand for the City is 11.2 MGD.
This number is based on a 10.60 MGD maximum daily demand (MDD),
derived from the actual readings of the amount of treated water leaving the
treatment plant in 2017, plus 600,000 gallons for fire flow. The existing water
storage capacity of 16.0 MG (inclusive of the water distribution reservoir) is
more than sufficient for a 24 hour day of storage.
Pump Stations - Both pump stations are operating efficiently to deliver water
pressure throughout the City with a maximum output of 74 pounds per square
inch (psi) per the 2018 Water Master Plan. There are times during the day
where a portion of the system experiences a drop in pressure to
approximately 46 psi when the East Side Reservoir is being filled during the
hours of 12:00-4:00 p.m. A minimum of 20 psi is required to meet fire flow,
and as such, sufficient pressure is available in the system.
Water Distribution System - A computer model of the existing water
distribution system was developed as part of the 2018 Water Master Plan
using available data for the existing facilities and the demand estimates
stated above. The capacity of the existing system was evaluated under
Maximum Day Demand at Peak-Hour plus fire conditions (MDPHF). The
result of the modeling indicates that the existing system provides adequate
pressure for the Average Annual Demand (AAD) condition, but that during
MDPHF conditions many areas of the City experience inadequate
pressures. The existing water distribution system is therefore not
adequate to serve future development areas outside of the present service
area.
The minimum water pipeline size for new development is generally 8” and
existing pipelines smaller than 4” are recommended for replacement. There
are approximately 10,100 lineal feet of 2” pipelines (3,400 lineal feet of cast
iron and 6,700 lineal feet of polyvinylchloride pipes) primarily located in the
areas south of 4th Street between Encinas Avenue and Andrade Avenue as
previously noted in Exhibit H-1.
110 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
Table H-4 Fire Flow Deficiencies
Hydrant Deficiencies in Single Family Residential Areas
ID# Location Notes
1021 Northeast corner of 2nd Street Meets Residential 1,000 GPM
and Encinas Avenue Does Not Meet 2,000 GPM for the
existing non-conforming commercial use
1023 Northeast corner of 2nd Street Does not meet 1,000 GPM
and Beach
Hydrant Deficiencies in Multi-Family Residential Areas
ID# Location Notes
1087 Northeast corner of 5th and Mary Does Not Meet 2,000 GPM for the
Avenue existing Police and Fire Department and
multi-family residential
1037 Encinas Avenue between Second Does Not Meet 2,000 GPM for the
1021 and Third Street existing multi-family residential complexes
1039 Beach Avenue between 2nd Does Not Meet 2,000 GPM for the
1071 Street and 4th Street existing multi-family residential complexes
1050 Blair Avenue between 3rd and 4th Does Not Meet 2,000 GPM for the
Street existing Calexico Neighborhood House
and multi-family residential complexes
2150 Vega Street, east of Rockwood Does Not Meet 2,000 GPM for the
Avenue existing multi-family residential complexes
5061 Rockwood Avenue between Does Not Meet 2,000 GPM for the
5094 Banagas and Annos Courts existing multi-family residential complexes
Hydrant Deficiencies in Commercial Areas < 2,000 GPM
ID# Location
3030 Airport
3014 Airport
1005 Alley behind US Port of Entry
1195 Southeast Corner of Emerson and Lincoln
1215 South side of McKinley between Emerson and Highway 111
1246 South side of Sheridan between Emerson and Highway 111
¹Fire flow minimums are targeted at 1,000 GPM for residential, 2,000 GPM for commercial, and 2,500
GPM for industrial. Actual fire flow requirements for multi-family residential are based on type of
construction and size of the building. The presence of multi-family buildings and other larger buildings
(churches, police station, etc.) could require a minimum of 2,000 GPM.
Fire-flow Adequacy- A hydraulic model was completed as part of the 2018
Water Master Plan update and the model showed that 24 fire hydrants in
predominantly commercial locations were not able to meet the minimum fire
flow requirements. The model simulated flows at 1,000 GPM and 2,000 GPM
sustained for a period of two hours. The following hydrant locations were
identified in the 2018 Water Master Plan as being deficient. There were no
deficiencies noted in industrial areas.
111 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
c) Future Demand for Facilities & Planned Improvements
A previously noted, the 2017 average water demand per person based on
household consumption data (Appendix B) is 105 gallons per person per day.
For future projections it is always best to use a conservative number of 125
gallons per person per day, which is below the historic industry average of 150
gallons per person per day. This is justified by recent trends for water
conservation measures and existing demands. Thus, assuming the
conservative demand of approximately 125 gallons of potable water per day
per capita, the City’s average annual projected water use is as follows:
Table H-5 Residential Water Demand Projections
Projected
Year Average Daily Flow
Population
2020 46,639 5.8 MGD
2025 57,421 7.2 MGD
2030 66,912 8.4 MGD
2035 77,972 9.7 MGD
2040 90,860 11.4 MGD
Demand is based on an assumed impact of 125 gallons per day per capita.
As previously noted, the existing capacity of the Calexico Water Plant is 12
MGD. The water treatment plant can provide an adequate supply of potable
water through 2040 based on historic growth rate plus active planned
developments for residential uses only. The treatment plant would be at 95%
of treatment capacity by 2040 for residential demand only. This is based on
an average demand of 125 gallons per person per day.
An equivalent dwelling unit was also established as per the household size in
Calexico of 4.08 persons per household, thus each dwelling unit consumes
an average of 510 gallons per day (GPD). Assuming an impact of 510 GPD
per Equivalent Dwelling Unit (EDU) on the water treatment facilities, the City
was able to further project non-residential impacts to water facilities from
commercial and industrial operations beyond residential demand as noted in
Table H-6.
112 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
Table H-6 Daily Water Demand Projections with All EDU’s
113FF
Total Projected Total Existing
Population & & Active Non- Average
Total
Year Active Residential Residential Daily
EDU’s
Development EDU’s Demand
EDU’s
2017 10,030 5,539 15,569 6.69 MGD
2018 10,224 5,539 15,763 7.15 MGD
2020 11,431 5,564 16,995 8.67 MGD
2025 14,074 5,564 19,638 10.02 MGD
2030 16,400 5,564 21,964 11.20 MGD
2035 19,111 5,564 24,675 12.58 MGD
2040 22,270 5,564 27,833 14.20 MGD
Average Daily Flow is based on an assumed impact of 510 gallons per day per EDU. Year 2017 Average
Daily Demand is based on actual meter reading at the water treatment plant from November 2016 to
October 2017.
With the existing capacity of the Calexico Water Plant at 12 MGD, the water
treatment plant is unable to provide an adequate supply of potable water
through 2020 based on historic growth rate plus planned developments for
both residential and non-residential land uses. The projected maximum
demand in 2020 is projected to be 13.00 MGD (8.67 average daily demand x
1.5). The 1.5 factor is based on the proportional peak demand for 2017. This
represents 108% of the treatment plant’s current capacity. The City of
Calexico has already hired a civil team to prepare a Preliminary Engineering
Report on interim and/or long-term improvements.
d) Opportunities for Shared Facilities
The City does not share water treatment, storage, or distribution facilities with
other jurisdictions. It is possible that in the future, as Calexico continues to
grow easterly, the City of Calexico may be able to serve the unincorporated
development at the East Port of Entry.
e) Phasing
In order to maintain an adequate water service for the existing population as
well as provide for future development, the following improvements and
future facilities are recommended and further detailed under the 2018 Water
Master Plan. Please note that design of a Water Treatment Plant Expansion
project would also need to be initiated by the end of the 20-Year Planning
Term.
113 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
Short Term Improvements (Under 5 Years)
• Replace 22,300 lineal feet of undersized water pipelines to
address fire flow issues.
• Replace 60,264 lineal feet of cast iron pipelines.
• Replace filter control system at Water Treatment Plant
5-10 Year Improvements
• Install new 18” water supply pipeline along All-American Canal
to service Eastside Storage Tank.
• Upgrade outdated fire hydrants to meet current standards/
10-15 Year Improvements
• Install backbone trunk lines at various locations to serve future
expansion areas.
3. Mitigation for Water Treatment & Distribution Facilities
The City of Calexico should continue to pursue various means by which to
obtain funding for and to provide for adequate water distribution facilities for
the existing and future residents of the City of Calexico. The following are
recommendations to achieve adequacy for water service facilities:
W-1 Facilities identified in the 2018 Water Master Plan update shall
be constructed with enterprise and impact fee monies as needed
and as new development and annexation of land occurs.
W-2 Prior to the recordation of a final map within any of the
annexation areas, a development agreement shall be in place
to ensure that adequate water pressures will be provided
during the MDPHF conditions for the water distribution system
being utilized by said annexation area.
W-4 Adequate fire flow, subject to the approval of the fire
department, shall be provided for all annexation areas.
W-5 All system improvements shall be designed and constructed in
accordance with Federal, State and local regulations and
standards.
W-6 By the end of 2018, the City of Calexico shall install water
meters to all users, including at all City properties to ensure
the proper accountability of water usage and loss.
114 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
W-7 The City shall budget a minimum of $1 Million annually to
replace aging water distribution pipeline infrastructure.
W-8 The City shall continue to adopt user fees/rates that can
adequately address the water treatment and distribution
system’s operation and maintenance needs.
W-9 The City shall examine the 2008 Water Development Impact
Fees to determine adequacy and whether an increase in water
impact fees should be imposed for the projected future
capacity demand.
4. Financing
The primary sources of revenue for water treatment and distribution facilities are
the water service charges, water capacity fees and water turn on fees. The
water capacity fee is based on the EDU impact created and funds planned
capital improvements. As of the 2017/2018 Fiscal Year, the City had $9.8 million
planned for capital improvements, consistent with the available enterprise fund
budget, and will continue to utilize these funding sources in addition to
searching for other sources to improve the existing system in order to meet
future demand.
a) Current Costs and Per Capita Costs
Capital costs in the amount of $9.8 million are not factored into the Per Capita
Costs in this analysis. The current annual cost for the continued
maintenance and operation of the water system in the City of Calexico is
approximately $116.99 per capita. The 2017-2018 City of Calexico Water
Fund budget allocated $4,880,322 for water services. Using the city’s
current population of 41,714 residents, operation, maintenance and debt
service of the water facilities cost per resident per year are noted
below.
$4,880,322 / 41,714 population = $116.99 per capita
Using the City’s current population, the per capita cost of $116.99 for the
continued maintenance and operation of the water facilities are noted below
in five-year increments.
115 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN WATER TREATMENT & DISTRIBUTION
Table H-7 Projected Water Costs
Projected/Planned
Year Water Costs
Population
2020 46,639 $5,456,297
2025 57,421 $6,717,683
2030 66,912 $7,828,035
2035 77,972 $9,121,944
2040 90,860 $10,629,711
b) Future Funding Sources
The water service charge collected by the City is the primary funding
source for operation and maintenance costs. These are charges based on
the actual water usage that may or may not need to be adjusted once proper
water accountability is assessed.
The primary sources of revenue for water treatment and distribution facilities
are the water service charges, water capacity fees and water turn on fees.
The City will continue to utilize these funding sources in addition to searching
for other sources to improve the existing system and in order to meet future
demand. The current fees were last adopted in 2008 and will need to be
reviewed annually and during proposed annexations to ensure that there is
sufficient funding to supply adequate water service to new development.
The City has sufficient enterprise funds to meet the capacity demands.
Additionally, there are a number of financing mechanisms available to
assist in the funding for capital facilities related to the delivery of potable
water. Special assessment districts, community facilities districts, local bond
issuance, developer contributions and development impact fees can be
used to fund water treatment and distribution facilities. Also, there are a
number of State and Federal grant and loan programs available for Water
Facilities through the State Water Resource Control Board Drinking Water
State Revolving Fund. Further descriptions of these and other financing
mechanisms are provided under the Financing section of this study.
116 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION
I. SANITARY SEWER FACILITIES
The City of Calexico owns, operates, and maintains a wastewater treatment system
consisting of collection pipelines, pump stations and a treatment plant to service the
entire City. The Wastewater System is owned and operated by the City of Calexico
Wastewater Operations. The maintenance and operation of the system is financed
through an Enterprise Fund. The most recent Wastewater Master Plan was adopted
in 1991. All information for this section was acquired from the 1991 Water Master
Plan and a focused Master Plan prepared for the Jasper Corridor in 2007. The
information provided herein is not for detailed engineering. The City is in the process
of updating the Wastewater Master Plan (Appendix E). For additional details relating
to water facilities, the most current Wastewater Master Plan should be consulted.
1. Performance Standard
Wastewater Treatment Plant - The Performance standards and requirements
for the Calexico Wastewater Treatment Plant are governed by the California
Regional Water Quality Control Board, Colorado River Basin Region (Regional
Board) and US EPA. The City operates under a National Pollution Discharge
Elimination System (NPDES) discharge permit. The City’s NPDES discharge
permit number CA 7000009 adopted by the California Regional Water Quality
Control Board, Colorado River Basin Region on May 8, 2014, by Board Order
Number ORDER R7-2014-0004. The NPDES permit expires on May 31, 2019.
The NPDES permit establishes the Waste Discharge Requirements for the
Calexico Wastewater Treatment Plant. The NPDES permit establishes the rated
capacity of the wastewater plant, discharge prohibitions, effluent limitations and
discharge specifications, receiving water limitations, standard provisions for the
operation of the wastewater treatment plant, monitoring and reporting program
requirements, compliance requirements, and special provisions. The NPDES
discharge permit also establishes minimum standards and criteria by which the
wastewater treatment plant operates.
Sewer Collection System- The City of Calexico considers standards
established by the California Department of Public Health, the Water
Environment Federation (WEF) and American Water Works Association (AWWA)
to establish performance standards and criteria for the wastewater collection
system. The City of Calexico also adopted standards, details, and specifications
addressing the Technical requirements for the sanitary sewer collection system
as new development occurs.
Design capacity of a pipeline is the general calculated capacity of the pipeline
using the Manning formula. For system analysis, peak dry weather flow (PDWF)
117 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION
does not exceed 75% of the design capacity of the pipeline. Accordingly, 25% of
the pipeline capacity is reserved to accommodate peak wet weather flow
(PWWF) incurred during wet weather conditions. The 25% reserve is therefore
provided to account for groundwater infiltration and rainfall dependent inflow, plus
additional sewer capacity reserve allowance. This 25% reserve contingency
factor is a commonly used allowance in evaluating wastewater utilities. The
2006 Calexico Service Area Plans adopted the following design criteria for
determining sewer pipeline capacity and as depicted on Table I-1:
• Average daily flow (ADF) = 85 gallons per capita per day (gpcd)
• Infiltration and Inflow (I/I) = 10% of ADF
• Manning’s roughness coefficient “n” = 0.012
• Flow velocities shall be no greater than 20 feet per second (fps)
• Flow velocities shall be no less than 2 fps
• Depth to Diameter Ratio (d/D) as follows:
Table I-1 Pipeline Design Criteria
Pipe Diameter Design Criteria
6” to 12” .50 Full @ Peak Flow
15” to 18” .75 Full @ Peak Flow
21” or greater .93 Full @ Peak Flow
Pipelines that cannot reach this minimum flow velocity should be assisted with
pump stations. Pump station adequacy is based on two criteria: 1) the ability of
the pump station to pump the PWWF and 2) wet well adequacy for pump cycling.
Peaking factors are shown on the following graph (Figure 3-C):
Figure 3-C Peak Factor
Graph
118 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION
2. Facility Planning and Adequacy Analysis
The Calexico wastewater treatment plant occupies an area of approximate 18
acres co-located within the same parcel as the Calexico Airport at 298 West 2nd
Street The wastewater treatment plant was first built in 1967 with various system
additions occurring in 1974, 1991, 1994 and 1996. Treated effluent is discharged
into the New River.
a) Inventory of Existing Facilities
Wastewater Treatment Plant - The City operates the wastewater treatment
plant at a permitted capacity of 4.3 million gallons per day (MGD) under
NPDES Permit No. CA 7000009 and regulated under ORDER R7-2014-0004.
As of October 2017, the wastewater plant treats an average flow of 2 MGD
with a peak flow of 3.1 MGD.
Exhibit I-1- Wastewater Facilities identifies the location of the Calexico
Wastewater Treatment Plant, the primary conveyance system and pump
stations. According to the NPDES Permit, Calexico’s wastewater treatment
plant provides secondary treatment through two treatment trains: an activated
sludge treatment system with a design capacity of 2.5 MGD, referred to as
Plant #1 (originally constructed in 1967) and an aerated lagoon treatment
system with a design capacity of 1.8 MGD, referred to as Plant #2 (originally
constructed in 1994). The various wastewater treatment facility’s components
are listed in the Table (Table I-2) below:
Table I-2 Wastewater Treatment Facility
Component Capacity
Influent Pump Stations (Two: 2.5 MGD & 1.8 MGD) 4.3 MGD
Primary Clarifiers (2) 49,600 cf
Secondary Clarifiers (3) 89,650 cf
Grit Chamber 12,620 gals
Aeration Basins (3) 360,000 gals
Digesters (2) 238,000 gals
Aerated Lagoons (Two: 1.8 & 2.6 MG) 4.4 MGD
UV Treatment System 5.0 MGD
Source: Calexico Public Works Department, May 2018.
119 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION
Exhibit I-1 Wastewater Facilities
120 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION & TREATMENT
Wastewater Conveyance System - According to the City’s 2015 Sewer
Collection System Map, the City is serviced by a network of sewer pipelines
ranging in size from 4” to 30”. City Lateral and trunk sewer lines discharge
into one of two interceptor sewers. The following is a brief inventory of over
91 miles of wastewater collection pipelines owned and maintained by the City
of Calexico. The City collection system contains both, aged clay pipeline
segments and newer PVC pipeline segments. The following Table (Table I-
2) identifies total pipeline sizing throughout the City as delineated in Exhibit I-
1 Sewer Facilities.
Table I-2 Sewer Pipelines
Length
Size of Pipeline
Lineal Feet
4” 2,800
6” 129,141
8” 270,424
10” 16,325
12” 24,455
15” 6,261
18” 16,010
21” 1,206
24” 8,665
27” 5,313
30” 3,249
Total Lineal Feet 483,849
Source: The Holt Group CAD Measurement of 2015 Sewer Collection Map
pipelines-- adjusted to reflect actual size of pipeline along Olive Avenue between
Highway 111 and the downstream 18” diameter pipeline.
Wastewater Pumping Stations - As previously noted, the topography of the
City is fairly flat, thus lift/pumping stations are necessary in order to receive
flows and pump them through force-main pipelines located throughout the
incorporated City limits. Table I-3 details the eleven pump stations noted in
Exhibit I-1 and available throughout the City to assist with sewer conveyance.
121 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION & TREATMENT
Table I-3 Pump Station Inventory
Pump
Lift Station Location
Station
1 2nd Street behind California Mayoreo y Menudeo
2 SE Corner of Robinson Avenue and Portico Boulevard
3 Estrada Boulevard north of Camacho
4 Rosas at Amada Street
5 Anaya Avenue at Sereno Drive
6 SW Corner of Andrade and Highway 98
7 SW Corner of Cabana Street and Meadows Road
8 Spud Moreno Street (La Jolla Palms Subdivision)
9 Estrada Pump Station (NW Corner of Cole and Scaroni)
11 Coppel Pump Station (Scaroni Avenue, 690’ north of Camacho Road)
Source: 2015 Calexico Sewer Collection Map.
b) Adequacy of Existing Facilities
Wastewater Treatment Plant- The existing Wastewater Treatment Plant
existing facilities and equipment are over 30 years old and at the end of their
service life, with the exception of some minor replacements that have
occurred over the years. The City is currently in the process of updating the
Master Plan for its Wastewater Treatment Plant and the findings of that
Master Plan should take precedence. As previously noted, in 2017 the
wastewater plant treated an average flow of 2 MGD with a peak flow of 3.1
MGD. The 2 MGD average flow rate is well below the limited operational and
permitted capacity of 4.3 MGD.
Conveyance System- Over the years, conveyance system infiltration has
been suspected and several pipeline segments have been replaced as
funding became available. The 2017 average flow at the Wastewater
Treatment Plant was 2 MGD, flows that were lower than previously reported
flows of 2.7 MGD in 2006, despite the increase in population. This suggests
that much of the historic infiltration challenges may have been taken care of.
This is also true for the peak flows which were 3.1 in 2017 (lower than the
reported peak flows of 2006 of 3.5 MGD).
Most sewer lines have been constructed at minimum slopes and the
interceptors are relatively deep, as much as 20-feet because of the relative
flat terrain of the region. A hydraulic analysis was conducted as part of the
2006 Service Area Plan (SAP) and specific recommendations were made to
address existing deficiencies in the collection system. The 2006 SAP
122 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION & TREATMENT
recommended that the existing 12” pipeline on Ollie Avenue between
Hacienda Drive and West Canal Street be upgraded to 18”. According to
Public Works staff, the pipeline along Ollie Avenue was upgraded to a 15”
diameter pipeline. The 2006 SAP also recommended that the 15” gravity
pipeline along 5th Street between Highway 111 and the downstream 18”
pipeline be upgraded to accommodate the full flow observed on this portion of
the pipeline. The 2015 Sewer Collection Map identifies this pipeline as still
being the same size (15” and 18”). There is also one sub-sized 4” line in the
City that is substandard and in need of replacement and that collection
pipeline services those parcels on 1st Street between Encinas Avenue and
Andrade Avenue.
The percentage needing replacement due to aging material or capacity
deficiency is currently unknown. However, the 2,800 lineal feet of 4” diameter
pipelines should be replaced.
Wastewater Pumping Stations - Sewer Lift Stations have a useful life
expectancy of 50 years. Small sewage lift-stations have been constructed
throughout the City as a result of the flat topography to provide service to new
developments. Following is Table I-4 which lists the adequacy of operation
for existing flows. At least two of these pump stations located to the
northwest of town require rehabilitation and are not sized large enough to
meet any significant additional demand. The City has a study to determine
proper sizing and shared cost of contributing developments.
Table I-4 Pump Station Adequacy
Pump
Area/Development Serviced by Station 2018 Condition
Station
1 2nd Street behind California Mayoreo y Menudeo Unknown
2
SE Corner of Robinson Avenue and Portico Adequate
Boulevard
3
Estrada Boulevard north of Camacho Unknown
4
Rosas at Amada Street Adequate
5
Anaya Avenue at Sereno Drive Adequate
6
SW Corner of Andrade and Highway 98 Adequate
7
SW Corner of Cabana Street and Meadows Road Needs Upgrade:
From 150 to 400 GPM
8
Spud Moreno Street (La Jolla Palms Subdivision) Adequate
9
Estrada Pump Station (NW Corner of Cole and Adequate
Scaroni)
11
Coppel Pump Station (Scaroni Avenue, 690’ north Adequate
of Camacho Road)
Source: 2008 Master Plan for Sanitary Sewer Collection System & 2015 Interview with Public Works
123 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION & TREATMENT
Director.
c) Future Demand for Facilities & Planned Improvements
Assuming an impact of 85 gallons per capita per day (gpcd) on the
wastewater treatment facilities, the City projected residential Average Daily
Flow demand is noted in Table I-5. The forecasted discharge is based on the
industry average flow of 85 gallons per capita per day (gpcd), consistent with
the City’s current peak flow of 74 gpcd.
Table I-5 Daily Residential Sewer Flow Projections
Projected
Year Average Daily Flow
Population
2020 46,639 3.96 MGD
2025 57,421 4.88 MGD
2030 66,912 5.69 MGD
2035 77,972 6.63 MGD
2040 90,860 7.72 MGD
Demand is based on an assumed impact of 85 gallons per day per capita.
113F
As previously noted, the City of Calexico’s average household size is 4.08
persons per household. Assuming an impact of 347 gallons per day per
Equivalent Dwelling Unit (EDU) on the wastewater treatment facilities, the City
was able to further project non-residential impacts to water facilities from
commercial and industrial operations. The projected average daily wastewater
flow demand for all “units,” including non-residential equivalent dwelling units,
is therefore projected in the following Table I-6. It is anticipated that capacity
will be reached prior to 2020 based on the projected demand of 85 gpcd.
Table I-6 Daily Sewer Flow Projections with EDU’s
113FF
Total Existing Total Existing
& Projected and Active
Total Average
Population & Non-Residential
Year Equivalent Daily
Active EDU’s
EDU’s Flow
Development
EDU’s
2018 10,224 914 11,138 3.86 MGD
2020 11,431 939 12,370 4.29 MGD
2025 14,074 939 15,013 5.21 MGD
2030 16,400 939 17,339 6.02 MGD
2035 19,111 939 20,050 6.96 MGD
2040 22,270 939 23,208 8.05 MGD
Average Daily Flow is based on an assumed impact of 347 gallons per day per EDU. Excludes un-
metered/unaccounted water which is assumed to be used for irrigation and does not end up in the sewer
124 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION & TREATMENT
system.
The City is in the process of adopting a Watewater Master Plan and has over
$24 million in capital improvements programmed for the Wastewater
Treatment Plant. The improvements would likely consist of the possible
replacement of the existing wastewater treatment plant from the current
process to a new activated sludge plant. The planned improvements include
a capacity expansion to meet the projected demand. The existing headworks
and UV equipment would be rehabilitated or replaced . These improvements
are under preliminary engineering assessment and are expected to be
solidified before the end of 2018.
d) Opportunities for Shared Facilities
The City of Calexico does not have any neighboring cities, within the United
States, which are immediately adjacent to the existing Sphere of Influence.
Therefore, the opportunity to share wastewater facilities with other cities is
limited. The County of Imperial does own a much smaller sewer treatment
facility east of Calexico to serve the Gateway of the Americas County Service
Area, which includes the East Port of Entry, however, the County Facility
would not be able to support the demand generated by the Calexico
community. It is possible that in the future, as Calexico continues to grow
easterly, the City of Calexico may be able to serve the unincorporated
development at the Gateway of the Americas County Service Area.
e) Phasing
Based on the results of the analysis performed by Lee & Ro
Engineering, the Wastewater Treatment Plant improvements may require to
be phased depending on overall costs. It is anticipated that the preliminary
engineering report will be completed with full recommendation by the end of
2018.
3. Mitigation of Sanitary Sewer Collection & Treatment
The City of Calexico should continue to pursue various means by which to
obtain funding and provide for adequate wastewater conveyance facilities for the
existing and future residents of the City of Calexico. The following are
recommendations to maintain adequacy for wastewater treatment and
conveyance facilities:
S-1 The City shall adopt a comprehensive Wastewater Master
Plan and implement recommended improvements.
125 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION & TREATMENT
S-2 Prior to the recordation of a final map within any of the
annexation areas, a development agreement must be in
place to ensure that adequate wastewater facilities will be
provided during the PWWF conditions for the wastewater
conveyance system being utilized by said annexation area.
S-3 All system improvements shall be designed and constructed in
accordance with Federal, State, and local regulations.
S-4 The City shall continue to adopt user fees/rates that can
adequately address the wastewater collection and treatment
system’s operation and maintenance needs.
S-5 The City shall continue to reevaluate the 2008 Sewer
Development Impact Fees to adequately meet the projected
capacity demand.
4. Financing
The primary sources of revenue for wastewater treatment and conveyance
facilities are the sewer service charges and sewer capacity fees with modest
investment earnings. The sewer service charges function to subsidize off-site
facilities such as sewer interceptors and sewer treatment plant operation and
maintenance. The sewer capacity fee is based on the equivalent dwelling
unit (EDU) impact created and funds planned expansions of the Calexico
Wastewater Treatment Plant. The City will continue to utilize these funding
sources in addition to searching for other sources to improve the existing
system in order to meet future demand.
a) Current Costs and Per Capita Costs
A total of $15.8 million was budgeted for capital improvements and is not a
part of this analysis. The current annual cost for the continued
maintenance and operation of the sewer system in the City of Calexico
is approximately $128.48 per capita. The 2017-2018 City of Calexico
budgeted $5,359,465 for wastewater operations and debt service. Using
the City’s current population of 41,714 residents, maintenance and
operation of the wastewater facilities cost per resident per year was
calculated as follows:
$5,359,465 / 41,714 population = $128.48 per capita
Using the City’s current population, the per capita cost of $128.48 for the
continued maintenance and operation of the sewer facilities are noted below
in Table I-8 in five-year increment projections.
126 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN SANITARY SEWER COLLECTION & TREATMENT
Table I-8 Projected Sewer Costs
Project/Planned
Year Sewer Cost
Population
2020 46,639 $5,992,179
2025 57,421 $7,377,450
2030 66,912 $8,596,854
2035 77,972 $10,017,843
2040 90,860 $11,673,693
Future cost estimates are based on current cost per capita for wastewater
operations and debt service.
b) Future Funding Sources
The sewer service charge collected by the City is the primary funding source.
The current fees were last updated in 2008 and will need to be reviewed
annually. There is currently a rate increase under consideration which is
expected to be adopted before the end of 2018. Development Impact fees will
need to be further assessed for adequacy based on capacity expansion
demand. Evaluation of revenue sources should take place during all
proposed annexations to ensure that there is sufficient funding to provide
wastewater service to increased demand.
There are a number of financing mechanisms available to assist in the
funding for capital facilities related to the treatment and conveyance of
wastewater. Special assessment districts, community facility districts, local
bond issuance, developer contributions and development impact fees can
be used to fund wastewater treatment and conveyance facilities. Also, there
are a number of State and Federal grant and loan programs available
such as Regional Water Quality Control Board Clean Water State Revolving
Fund. Further descriptions of these and other financing mechanisms are
provided under the Financing section.
127 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
J. AIRPORT FACILITIES
The City of Calexico owns and operates the Calexico International Airport as an
alternative mode of transportation to and from the City. The Calexico International
Airport (CXL) is a 257-acre, publicly-owned facility and serves the needs of local
and county-wide population. As a general aviation airport, CXL does not receive
scheduled commercial air service, but it is designated as an international airport of
entry due to its proximity to US/Mexico border. Please refer to Exhibit J-1 Airport
Location.
The airport is operated by the Department of Public Works. The City is the fixed
base operator (FBO) and provides airport management, aviation fuel, and aircraft
parking. The following information provides an overview of the airport facilities and
their adequacy in meeting current and future needs of the City with data derived
from the City Website, Calexico International Airport Master Plan (P&D Aviation,
August 2002) and other available resources, as noted.
1. Performance Standard
There are currently no adopted performance standards for airport services and
facilities, but airport capacity can be divided into two categories: landside
capacity and airside capacity. Airside capacity includes components like the
runway, taxiway system, and adjacent airspace to the airport. Capacity is
affected by the layout of the runways, configuration of taxiways, navigation aids,
and air traffic control rules and procedures. Landside capacity includes the
terminal, gate, and access roads. Landside capacity also includes the ground
transportation system.
The other portion of the equation in establishing a performance standard is the
demand. Unlike other services and facilities discussed in this Service Area Plan,
airport facilities are not based on population growth but rather market driven
based on private aircraft ownership. The 2002 Airport Master Plan projected a
relatively low demand of based aircraft and aircraft operations. The Master Plan
outlined standards to accommodate a B-II airport classification to satisfy
operational requirements of an aircraft with a stalling speed of 91 knots or more
but less than 121 knots and a wingspan of at least 49 feet up to but not including
79. These standards balance a variety of interests including safe operations,
increased efficiency, reduction in delay, economic viability, noise reduction, and
environmental protection. A summary of planning standards for Airside and
Landside Facilities is presented in the proceeding tables CXL-1 and CXL-2.
128 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
Exhibit J-1 Airport Facilities
129 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
Table J-1 Airside Performance Standard
Airside Facility Requirement
Runway Centerline to Parallel Taxiway Separation 200 feet
Runway Width 75 feet
Taxiway Width 35 feet
Runway Length (accommodate airplanes <10 passenger seats) 4,550 feet
Pavement Strength 30,000 LBS/
(single wheel loads)
Source: FAA AC 150/5300-13A, September 28, 2012
Table J-2 Landside Performance Standard
Landside Facility Requirement
Administration/Terminal Building 49 SF/Per Peak Hour
Occupant
Aircraft Parking Apron Sized to accommodate 25% of
Transient Operations
Based Aircraft Storage (per based aircraft)
Single Engine/Helicopter 1,620 SF
Multi-Engine 3,150 SF
Business Jet/Turboprop 4,500 SF
Aircraft Maintenance Facilities 100 SF/Per Based Aircraft
Automobile Parking 1.3 Spaces Per Peak Hour
Pilot/Passenger
Source: 2002 Calexico International Airport Master Plan
2. Facility Planning and Adequacy Analysis
The 257-acre facility is an active airport. According to the Airport Master
Record (Form 5010-1) submitted to the Federal Aviation Administration (FAA)
for the CXL, there was an average of 85 airport operations per week during the
12-month period ending November 30, 2017. For comparison, Imperial County
Airport (IPL) had an average of 266 airport operations per week and Brawley
Municipal Airport (BWC) has an average of 64 airport operations per week for
the same time period. Aircraft operations consist of 90% transient operation
and the remaining 10% is local general aviation. There are 26 aircraft based at
CXL which is comprised of 16 single-engine airplanes, 8 multi-engine airplanes
and 2 helicopters.
130 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
a) Inventory of Existing Facilities
The single-runway airport is located in the southwest quadrant of the City at
801 West 2nd Street approximately 950 feet north of the Mexico border. The
Airport was first activated on October 1, 1947 and various changes and
improvements have occurred during its 70+ years of existence. During the
1990’s, the runway and taxiway were extended with 390 feet of usable
pavement. The following is a list and discussion of all facility elements within
the airport which are grouped into landside components and airside
components. Exhibit J-2 Airport Facilities further delineates their location.
Landside Facilities
• One 1,200 SF Terminal Building
• One 2,160 SF Public Restaurant
• 20,000 Gallons of Underground Fuel Tanks
• Two Tanker Fuel Trucks to Serve Aircraft (1,200 gallons each)
• 16 Spaces/23,675 SF of Hanger Buildings
• 17 Hanger Tie Downs
• 84 Paved Aircraft Tie Downs
• 41,000 Square Feet of Apron Area
Airside Facilities
• One (1) Asphalt Runway 4,679 LF in Length
• One 400’-wide Taxiway A
• Four (4) Right-angle Exit Taxiways
The single asphalt runway (Runway 8/26) is equipped medium intensity
runway edge lights (MIRL) and visual markings and aiming points at each
end of the runway. The single-wheel weight bearing limit is 30,000 pounds
which allows for small commuter aircraft including business jets. Runway 26
has a displaced threshold of 160’. The runway is served Taxiway A
providing access to all aircraft service, parking and hangar areas and
facilities on the south side of the runway.
b) Adequacy of Existing Facilities
The runway system is one of the most critical components in determining
airside capacity. The City recently rehabilitated runway 08/26 at a $3.9
million investment. However, Calexico’s airspace is surrounded on three
sides with urban development and agricultural fields to the west and
expansion potential is restricted. The airport is bounded to the north by the
City’s water treatment plant and the Alamo River which curves to the
southeast. To the south is the Gran Plaza Outlet Center and the US-Mexico
border is approximately 950 feet to the south of the airport.
131 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
Exhibit J-2 Airport Facilities
132 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
The 2002 Airport Master Plan indicated that the runway and taxiway system
was adequate to meet the needs of general aviation (GA) utilizing the airport
and given that the levels of operations have not changed since 2002, this
continues to be sufficient. At an average of 85 aircraft operations per week
(landings and takeoffs) and at an average of 55 gallons per aircraft, the
20,000 gallons of fuel stored in underground tanks is sufficient to meet the
fuel demand. Likewise, the 117 total aircraft parking spaces can sufficiently
meet the needs of the 26 based aircraft and the transient general aviation.
The 2002 Master Plan did identify the need to rehabilitate terminal building
due to age. The aircraft parking apron is also identified as being undersized
and does not have adequate distance separation from the airfield to meet the
requirements for commuter air service.
c) Future Demand for Facilities & Planned Facilities
There is currently no scheduled commercial air service at Calexico
International, and as such, demand does not correlate to population growth.
Instead, demand is based on external market forces such as the number of
aircraft owned within Calexico’s market area and usage of private aircraft.
The 2002 Master Plan noted there would be an increase in demand for based
aircraft of 56 aircraft through the year 2020, up from the 21 based aircraft in
1998. The actual number of aircraft has only increased by 5 aircraft since
1998. Based aircraft is defined as an aircraft that is permanently stationed at
an airport.
The Master Plan also originally forecasted 27,200 aircraft operations per year
in 2020, but there was only a total of 4,420 operations for the 12-month
period ending in November 30, 2017. Because the use and demand of the
airport has not significantly increased, the size and layout of the existing
airport facilities is sufficient to meet the current needs of the general aviation
users. However, expansion of the terminal building is recommended to
accommodate commuter service and/or increased usage by small business
jets.
According to the FAA Aerospace Forecast for Fiscal Years 2018-2038 there
were increases in General Aviation industry and the number of general
aviation hours flown is forecast to increase an average of 0.8% per year
throughout the nation through 2038. Based on this forecasted growth, Table
J-3 shows the future demand and operational capacity at the Calexico
International Airport. Operational capacity is based on FAA Advisory Circular
150/5060-5 as calculated in the 2002 Master Plan.
133 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
Table J-3 Airport Facilities Demand
Aircraft
Based Operational
Year Operations Adequacy
Aircraft Capacity
(per year)
2020 27 4,527 230,000 Adequate
2025 28 4,710 230,000 Adequate
2030 29 4,902 230,000 Adequate
2035 30 5,101 230,000 Adequate
2040 31 5,309 230,000 Adequate
Source: The Holt Group, Inc. Analysis. Operational Capacity is based on capacity identified
in the 2002 Calexico Airport Master Plan
The City has several capital improvement programs planned for the Calexico
International Airport. The City is working on a new airport layout plan and
has budgeted $250,000 for a study. Another near-term investment is the
City’s rehabilitation of the existing Taxiway and has budgeted $2.2 million for
design and construction.
d) Opportunities for Shared Facilities
There are other airports in the region such as Imperial County Airport (IPL)
and Brawley Municipal Airport (BWC) that provide general aviation operations
and aviation fueling facilities. However, one of the most important features of
the Calexico International Airport is that it is designated as an international
airport of entry with an office staffed by US Customs and Border Protection
(CBP). CXL’s status as an international airport of entry is specifically listed in
Title 19 of the US Code of Federal Regulations Part 122 due to its location
adjacent to the US-Mexico border and land ports of entry. As an international
airport of entry, the US Customs and Border Patrol occupies approximately
600 square feet of the building to conduct its operations at the airport.
e) Phasing
The 2002 Airport Master Plan identified a phased approached for
improvements should the City wish to expand the airport to attract commuter
air service or enhance airport operations. Three phases of improvements
were recommended based on a high-growth forecast. Phased improvements
can be stretched out over a much longer time period depending on actual
growth in the demand.
134 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
Near Term Capital Improvements (1-5 years)
• Realignment of 2nd Street (Anza Road)
➢ Land Acquisition for Relocation of East Anza Road, Phase I
➢ Acquire Land for East Anza Road Relocation, Phase II
• Replace Segmented Circle and Wind Cone
• Acquire Land for Airport Expansion
• Pave Access Road to North Hangar Area
• Construct Utilities to Coincide with Realignment of 2nd Street
• Construct New Terminal Apron and Connecting Taxiway
• Install Automated Weather Observation System (AWOS)
• Construct Phase 1 T-Hangars (10 spaces) and Apron
• Construct Terminal/Administration Building
• Construct Automobile Parking for Terminal Building
Mid Term Capital Improvements (5-10 years)
• Realignment of 2nd Street (Anza Road)
➢ Relocation of East Anza Road, Phase I
➢ East Anza Road Relocation, Phase II
• Widen Runway to 100 feet
• Construct 500-foot Runway Extension
• Construct Sun Shades for Aircraft Tie Down Areas
• Rehabilitate Existing Parking Apron
• Install Runway End Identifier Lights (REIL)
• Construct Phase 2 T-Hangars (10 spaces) and Apron
• Construct Bridge over New River
• Utility Improvements
Long Term Capital Improvements (10-20 years)
• Extend Partial Parallel Taxiway on North Side of Runway
• Rehabilitate Existing Airfield Improvements
• Construct Dust Control System
• Construct Phase 3 T-Hangars (15 spaces) and Apron
• Construct Conventional Hangar and Apron
2. Mitigation
Although certain items listed for improvement during the near term were
completed, later phases rely on the acquiring additional property to the south to
accommodate airport expansion after realigning Second Street closer to the
Mexican Border. However, the City approved the development of Gran Plaza
Retail Outlets in April 2012 along the only developable area south of the airport.
A 285,000 square foot portion of the Outlet Center has already been
constructed and is currently open for business.
135 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN AIRPORT
It is important to note that demand for Airport facilities are not directly related to
the City’s population growth. The following are key mitigation measures to meet
the Airports continued objectives:
CX-1 The City shall develop overarching goals to guide policy decisions
related to the growth and development of the airport.
CX-2 The City shall update the Airport Master Plan to determine the
extent, type, and schedule of development needed to
accommodate market demands on the Airport.
CX-3 The City shall update the Land Use Element of the General Plan
to minimize land use conflicts thereby ensuring the viability of the
Airport.
3. Financing
The current revenue sources for airport facilities are generated by the CLX
with some access to grant resources. The airport has been successful in
obtaining State and Federal grant funding for improvements. The Airport’s
operation and maintenance is further self-budgeted through sales for fuel, oil,
fuel additives, aeronautical charts, and books. Additionally, tie-down fees, ramp
fees, and hanger rentals provide a revenue source for the operation and
maintenance of the airport.
a) Current Costs and Per Capita Costs for Operation & Maintenance
A total of $358,000 was budgeted for operating costs and another $1.3
million for Capital Projects. As previously noted the Airport is self-budgeted
and there are not per capita costs to the Calexico community.
b) Current Estimated Costs for Capital Improvements
The 2002 Calexico International Airport Master Plan is an ambitious
document that was meant to address best-case forecast of increased airport
demand and accommodating scheduled passenger commuter services.
Improvements for all three phases of expansion was estimated to cost $24.6
million in public investments and $6.6 million in private investments (adjusted
to 2018 dollars).
c) Future Funding Sources
The City should consider State Grant programs through the Department of
Transportation Aeronautics Division. The Local Airport Loan Account could
be accessed for capital needs. The Program is a revolving loan fund through
the California Department of Transportation. This Program provides
discretionary State loans that enhance an airport’s ability to provide general
aviation services (hangars, terminals, utilities, fueling facilities, etc.). Interest
rates are per the latest State General Obligation Bond sales interest rates.
136 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
K. EDUCATIONAL FACILITIES
Educational facilities and services in the City of Calexico are primarily provided by
the Calexico Unified School District (CUSD) which covers an area of approximately
59.2 square miles. All of the City of Calexico’s current incorporated boundaries and a
significant portion of its sphere of influence is within CUSD’s boundaries. The portion
of Calexico’s sphere of influence north of Jasper Road is within the Heber
Elementary School District and the Central Union High School District. There are
also private schools in Calexico that offer K-12 education and there is the San Diego
State University, Calexico Branch that also provides higher education services to the
region and to Mexico residents that commute.
1. Performance Standard for School Facilities
Performance standards for school facilities are based on student capacity per
classroom. The schools’ capacity is determined according to the methodology
specified by Education Code Section 41376 and 41378. These calculations
determine that kindergarten shall be at a maximum of 33 students per classroom,
first through third grade classrooms at 32 students per classroom and fourth
through eighth grade classrooms at 29 students per classroom.
2. Facility Planning and Adequacy Analysis
The Calexico Unified School District office is located at 901 Andrade Avenue, in
Calexico. According to the Human Resources and Risk Management Division,
the Calexico School District employs 490 certificated fulltime teachers, 209 full-
time classified teachers, 202 part-time classified teachers, 205 certificated temps,
and 356 classified temps. The District operates nine campuses as of 2018.
There are also three private schools and one State University branch which
serves a much broacher region (please refer to Exhibit K-1 Calexico School
Facilities Map). Information contained in this section was derived from School
Facility Needs Assessment was completed in February 23, 2017.
a) Inventory of Existing School Facilities
The City of Calexico is home to a number of public and private school
facilities that serve not just the community, but the region as a whole. The
Calexico School District, however, is a public district serving only Calexico
residents residing within the District boundaries. Calexico Unified School
District operates a total of seven elementary schools, two junior high schools,
two high schools, and one continuation school distributed into nine
campuses. Please refer to Table K-1 for inventory breakdown.
137 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
Exhibit K-1 Calexico School Facilities
138 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
139 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
Table K-1 Public School Inventory and Capacity Level
Elementary Schools Location
Blanche Charles Elementary 1201 Kloke Road
Cesar Chavez Elementary 1251 East Zapata Street
Dool Elementary 800 Encinas Avenue
Jefferson Elementary 1120 East 7th Street
Kennedy Gardens Elementary 2300 Rockwood Avenue
Mains Elementary 655 West Sheridan Avenue
Rockwood Elementary 1000 Rockwood Avenue
Total Capacity 4,876 Students
Junior High Schools Location
Enrique Camarena Junior High 800 East Rivera Street
William Moreno Junior High 1202 Kloke Road
Total Capacity 1,160 Students
High Schools Location
Aurora Continuation High School 1391 Kloke Rd
Calexico High School 1030 Encinas Ave
Total Capacity 2,237 Students
Source: Calexico Unified School District Website; Capacity was derived from the 2017 School Facility
Needs Assessment
Private Schools-There are three private schools located in Calexico. Private
schools provide an alternative to the public school system and can meet the
educational needs of Calexico residents. All three private schools were
operating under capacity as noted in the following table.
Table K-2 Private School Enrollment and Capacity Level
Grade School
School Students Capacity
Levels Year
Calexico Mission School
K-12 17/18 249 350
601 East 1st Street
Our Lady of Guadalupe Academy
K-8 17/18 440 600
535 Rockwood Avenue
Vincent Memorial Catholic HS
9-12 17/18 263 300
525 Sheridan Street
Source: Jonathan Saravia, Business Manager, Calexico Mission School, 06/05/2018
Carolina Madrigal, Secretary, Vincent Memorial High School, 5/23/2018
Melinna Gallardo, Administrative Secretary, Our Lady of Guadalupe Academy 06/11/2018
140 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
No oversight is required for private schools. The California Education Code
merely requires the filing of a Private School Affidavit with the California
Department of Education which exempts its students from compulsory public
school attendance. Although private school accreditation is not required, all
three private schools in Calexico are accredited through the Western
Association of Schools and Colleges.
Public Universities - San Diego State University (SDSU) opened a local
campus in Calexico in 1959. The Calexico branch is located at 720 Heber
Ave in Calexico on an eight acre site. In 2004, SDSU opened an additional
campus in Brawley that allows to better serve the needs of the north end of
Imperial Valley. The SDSU Calexico branch serves an estimated 850 full-time
equivalent students per Miguel Rahiotis, Assistant Dean for Student Affairs.
The total on-site capacity of the campus is 850 full-time equivalent students.
The SDSU Calexico branch campus is comprised of fourteen structures in the
heart of Calexico’s civic center. The following table provides an overview of
the buildings’ service purpose approximate square footage at the Calexico
Campus .
Table K-3 SDSU Facilities
Building Type Square Footage
Classrooms 12,233 sq. ft.
Faculty Facilities 19,376 sq. ft.
Student Facilities 5,740 sq. ft.
Academic Facilities 35,391 sq. ft.
Source: Imperial County Assessor’s Office GIS – Estimated Square Footage
141 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
The SDSU Imperial Valley curricula includes over 50 courses offered,
comprised of 12 undergraduate degrees, eight minor degrees, three
certificate programs, seven teaching credentials programs, and three
graduate degree. The following table provides an overview of services.
Table K-4 Services Provided at SDSU
Under- Other
Field Minor Graduate
Graduate Programs
Business Administration Certificate
Criminal Justice X
Educational Leadership X
English (single subject cred.) X X Credential
History X X
International Business X
Latin American Studies X
Liberal Studies X
Mathematics X X Certificate/
(single subject cred.) Credential
Nursing RN-BSN X
Nursing MSN X
Political Science X
Psychology X X
Public Administration X X Certificate
Small Business Management X
Social Science X Credential
Social Work X
Spanish X X Credential
Teaching Credentials Multiple Credential
Subject
Teaching Credentials Single Credential
Subject
Special Education Credential
Bilingual Education (Single Credential
Subject or Multiple Subject )
Source: Miguel Rahiotis, Assistant Dean, SDSU Imperial Valley, April 2018
142 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
b) Adequacy of Existing School Facilities and Planned Facilities
As of the 2016/2017 academic year, there were a total of 9,252 students
enrolled in all schools within the Calexico Unified School District. The School
Facility Needs Assessment was completed in February 23, 2017 which
evaluated the combined capacity of all schools as 8,086 K-12th grade
students.
The District is over capacity by 293 students, primarily, in junior high schools
and by 981 students in high schools. There is, however, additional capacity
for 295 students in the various elementary schools. Due to the deficiencies in
junior high schools and high schools, the school district enacted Level II
impact fees on new residential development to fund the expansion of existing
school sites. Please refer to Table K-5 for breakdown of existing capacities.
Table K-5 Public School Enrollment and Capacity Level
Enrollment
Seven Elementary Schools
(Academic Year 2016-17)
Total Elementary School Enrollment 4,581
Total Capacity of Elementary Schools 4,876
REMAINING ELEMENTARY CAPACITY 295 Students
Two Junior High Schools Enrollment
(Academic Year 2016-17)
Total Junior High School Enrollment 1,453
Total Capacity of Junior High School 1,160
REMAINING JUNIOR HIGH CAPACITY -293 Students
High Schools Enrollment
(Academic Year 2016-17)
Total High School Enrollment 3,218
Total Capacity of High Schools 2,237
REMAINING HIGH SCHOOL CAPACITY -981 Students
Source: CUSD Facility Needs Assessment, 2017
c) Demand for School Facilities
Information from the California Department of Education shows that
enrollment within the Calexico Unified School District system has increased
at an annual growth rate of 2.7% over the past 20 years (since 1997). Table
K-6 shows the number of unhoused students through the year 2040 if the
student population continues to increase annually by 2.7%.
143 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
Table K-6 Projected Demand and Unhoused Students
Projected
Projected District 2018
Year Unhoused
Enrollment Capacity
Students
2020 9,958 8,086 1,872
2025 11,364 8,086 3,278
2030 12,968 8,086 4,882
2035 14,798 8,086 6,712
2040 16,887 8,086 8,801
Source: The Holt Group analysis based on historic CUSD enrollment rates since 1997 as reported
through ED Data.
The aforementioned projections are somewhat inconsistent with figures used
by the Calexico Unified School District. The School District prepared a
School Facilities Needs Assessment (SFNA) in February 2017 to determine
the demand for new school facilities as a result of unhoused students from
new residential development. The SFNA shows that a typical single-family
housing unit will result in a student generation factor of the following yields:
Table K-7 Student Yield
Grade Level Yield
K-6 0.350
7-8 0.125
9-12 0.325
Total 0.800
The SFNA is restricted to only include demand projections based on those
residential units expected to be constructed within the next five years. At the
time the SFNA was prepared, the Las Palmas Subdivision project was the
only residential development listed with 200 future single-family units and the
rest of the subdivision being built out in later years. The Las Palmas
Subdivision would result in 25 unhoused 7-8th grade students and 65
unhoused 9-12th grade students by the year 2022. Construction of a new
middle school and a new high school is recommended by the SFNA.
144 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
Additional demand from the El Portal Subdivision project will result in more
students. The El Portal subdivision is currently in the entitlement process with
single family and multi-family homes expected to be built out by 2025. More
homes are also expected to be built in conjunction with the historic population
growth rate of 3.11% per year. Table K-8 shows the student forecast based
current development trends utilizing the School District’s student generation
factors. It should be noted, however, that the Facility Needs Analysis did not
address the conditions of the existing buildings and classrooms and need for
rehabilitation or replacement of those units.
Table K-8 SFNA Factor Student Projections
New Student Forecast
Year Housing Elementary Junior High High
Units School School School
2020 562 197 70 183
2025 201 70 25 65
2030 645 226 81 210
2035 0 0 0 0
2040 0 0 0 0
Total 1,408 493 176 458
Source: The Holt Group analysis based on generation factors used in the Calexico School Facility Needs
Assessment of 2017.
d) Phasing of School Facilities
The School District does not currently have any approved plans for new
facilities or construction of classrooms. As new development comes into
fruition, the Calexico School District may be forced to address the demand in
temporary modular facilities, unless a large enough development is required
to dedicate land concurrently for new school facilities. This size of a
development is not projected within the twenty-year planning period.
3. Mitigation for School Facilities
The City of Calexico does not have any oversight over the Calexico Unified
School District and any mitigation measures would only be in support of School
District policies and objectives. The reliability of the demand generation factors
should be raised with District officials in efforts to address a realistic student
145 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
demand. Additionally, City Planning Staff should invite the school district to all
pre-development meeting to ensure proper coordination of services and potential
need for new school sites to be incorporated into developer plans.
4. Financing
The current revenue sources for the Calexico Unified School District are
property tax and Development Impact Fees. The School District receives an
approximate $6.4 Million in taxes annually as reported through the Calexico
Unified School District Audit Report June 30, 2017. Additionally, the School
District received Development Impact Fees per new single-family development
and commercial development in the amount of $3.48 per square foot $0.56 per
square foot, respectively. Table K-9 provides a comparison of the Calexico
School District Impact fees in comparison to other school districts in the Imperial
Valley.
Table K-9 Impact Fee Comparison
Residential Commercial
City Year School District
Fee/SF Fee/SF
Imperial Unified
Imperial 2018 $4.57 $0.61
School District1
Calexico Unified
Calexico 2017 $3.48 $0.56
School District2
Calipatria Unified
Calipatria 2008 $2.97 $0.47
School District3
Holtville Unified
Holtvile 2017 $2.97 $0.47
School District4
El Centro
El Centro 2016 Elementary School $2.41 $0.39
District5
Central Union High
El Centro 2018 $1.74 $0.17
School District6
Brawley Union High
Brawley 2018 $1.07 $0.17
School District7
Note: The Calexico Unified School District has established a Level II fee of $4.79 per SF of residential
development.
1Imperial Unified School District (2018)
2 Facility Needs Assessment for Calexico Unified School District (2017)
3 City of Calipatria Adoption (2008)
4 Holtville Unified School District Unaudited Actuals Budget Revision (2017)
5 El Centro Elementary School District Administrator (2016)
6 Central Union High School District Website (2018)
7 Brawley Union High School District – Kathlyn DuBose, Manager (2018)
146 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN EDUCATIONAL
School Developer Fees vary between school districts. Calexico Unified
School District has the second highest School Developer Impact Fee out of
seven compared school districts in the Imperial County, and only lower than
the Imperial Unified School District. Their populations, however, are not
comparable. The two cities that have the largest school districts in the County
are Calexico and El Centro. However, El Centro School Districts have some
of the lowest School Developer Fees in the County.
The City of Calexico does have a comparable population of 40,351 to that of
the City of El Centro’s 44,364 per American Fact Finder 2017 Population
Estimates. The children under 18 years of age in households were an
estimated 11,659 for Calexico and 12,539 for El Centro in 2016, comprising
of 29.3% and 28.7% of the total population respectively. Calexico is
operating over capacity while El Centro is operating within capacity. New
Development was comparable among the two. The City of Calexico’s
population growth, since 2010, has experienced only a 0.85% average
annual growth rate, according to data from the California Department of
Finance. The City of El Centro also grew at an annual average of 0.99% for
the same time period.
A possible challenge unique to the Calexico community is the likely influx of
school age children from across the border for the sole purpose of school
attendance, statistics of which are unknown. The Calexico Unified School
District requires Residency Verification prior to enrollment, which makes this
factor unverifiable. Calexico’s slow development growth and unpredictable
demand from non-resident students have resulted in the inability of the
Calexico School District to collect sufficient revenues, thus no investment
expansion or capital needs have been satisfactorily addressed. The result
has been overcrowded classroom conditions with limited resources.
147 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INCIDENTAL SERVICES
L. SUPPORT SERVICES PROVIDED BY OTHERS
There are additional services provided within the Calexico Service Area by agencies
other than the City of Calexico, but that may be coordinated through the City of
Calexico. These special services include healthcare facilities and other utility
services from various purveyors. The sections that follow will discuss these services
in in brief overview as follows:
• Healthcare Facilities - A health facility is, in general, any location where
healthcare is provided. Health facilities range from small clinics and doctor's
offices to urgent care centers and hospitals.
• Solid Waste Facilities - Solid Waste services consist of the collection and
transport of solid waste generated by households and businesses and
transported to a landfill for disposal.
HEALTHCARE SERVICES AND FACILITIES
As of this 2018 Service Area Plan, the City of Calexico did not have an operational
hospital, however, numerous healthcare services and facilities are extended to
Calexico residents, including two urgent care centers. The Heffernan Memorial
Healthcare District, a local hospital district, was formed in 1951 to serve the City of
Calexico, but closed in 1997 and does not operate any medical facilities at this time.
The Heffernan Memorial District extends outreach services out to the community and
offers grants to non-profit organizations.
1. Performance Standards for Healthcare Services
The healthcare system is dealing with a serious supply-demand crisis. The
demand for care is significantly increasing due to a growing consumer base, an
aging population, and a changing marketplace. Meanwhile, the supply of
adequate care is insufficient. Healthcare costs for consumers have steadily risen,
and patients are becoming increasingly dissatisfied with the care they're
receiving. While there are no minimum regulatory standards, there are a few
things the medical field can do to help stabilize the service while performing
within acceptable performance levels.
2. Facility Planning and Adequacy Analysis
Although there are a number of healthcare facilities within the City of Calexico,
residents of the City have to travel outside of the City for extended hospital
services and stays at either El Centro Regional Medical Center (9.5 miles north)
or Pioneers Health Center in Brawley (22 miles north).
148 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INCIDENTAL SERVICES
a) Inventory of Existing Healthcare Facilities
The City of Calexico has seven (7) privately operated medical facility centers
serving the local community in addition to numerous other physician offices
as identified in Exhibit L-1 Healthcare Facilities. The following is a general
overview of each facility and the type of services they offer:
➢ El Centro Regional Medical Center Calexico Outpatient Center - The
outpatient center is centrally located at 495 Birch Street in Calexico and
offers many medical services, including laboratory and radiology testing.
Services provided include:
• Cardiology • Pediatrics
• Gastroenterology • Podiatry
• General laboratory services • Primary Care
• General radiology services • Ophthalmology
• Gynecology • Surgery
➢ Pioneers Memorial Healthcare District Calexico Healthcare Center -
The outpatient center is centrally located at 450 East Birch Street in
Calexico and offers a full-time health clinic with an urgent care center.
Services provided include wellness and preventive care, vaccinations,
and routine physicals.
➢ Clinicas De Salud Del Pueblo - The health clinic is located at the north
end of town at 223 West Cole Road in Calexico and offers a broad range
of healthcare services for both adults and children. The facility operates
Monday through Friday from 7:30 to 5:30.
➢ Fresenius Kidney Care- The care facility in Calexico is located at 351 E
Birch Street and offers hemodialysis and peritoneal dialysis services to
people with chronic kidney disease. The hours of operation are Monday
through Friday 9:00 to 5:00.
➢ Valley Orthopedics- The Calexico facility offers orthopedic services and
is located at 352 East 1st Street. The facility operates 9:00 to 5:00,
Monday through Friday.
➢ Imperial Valley Family Care Medical Group- The Imperial Valley Family
Care Medical Group, APC is a multi-specialty group of physicians
established in 1995 to serve the entire Imperial Valley. The Calexico
facility is located at 251 West Cole Road and operate 8:00 to 5:00
Monday through Thursday and 8:00 to 2:00 on Fridays. An acute care
facility is located in the City of El Centro that opens Monday through
Friday 9:00 also opens on weekends.
149 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INCIDENTAL SERVICES
Exhibit L-1 Healthcare Services & Facilities
150 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INCIDENTAL SERVICES
➢ Imperial Valley Methadone Clinic- the Imperial Valley Methadone Clinic
(IVMC) provides health services related to heroin addiction. This clinic is
an outpatient non-profit organization located at 535 Caesar Chavez in
Calexico and has limited hours of operation from 6:00 a.m. to 3:00 during
weekdays and 6:00 a.m. to noon on weekends.
b) Adequacy of Healthcare Services and Facilities
There are numerous regulatory agencies that protect and regulate public
health facilities services to ensure adequacy. There are also several non-
profit organizations that serve as watchdogs and accreditation institutions for
health care such as the Joint Commission on Accreditation of Health Care
Organizations (JCAHO) which works to ensure that health care organizations
provide quality care. JCAHO employs a system in which health care
organizations are examined and then given a score of 1-100, with higher
scores being better. These scores are important as they are a factor when
determining reimbursement from Medicare. Essentially, all areas of health
care, including but not limited to physicians, medical directors, health care
computer technology companies, health care facilities and pharmaceutical
companies, are subject to regulatory review and compliance.
c) Inventory of Approved Healthcare Facilities & Build-Out Demand
The City has approved a Mega Park Development, at the southeast corner of
Highway 111 and Jasper Road consisting of 156 acres of mixed use
commercial and industrial. The development is to include 166,000 square
feet for healthcare services. The Health Services Center is to include
professional offices, medical offices, recovery facilities, convalescent homes
and or hospitals, group care facilities, and similar uses.
The planned Health Services Center is anticipated to meet the demand of the
Calexico community and a much wider service area. Existing facilities are
unable to meet the current and wide range needs of the community, but
should be able to be satisfactorily addressed under the new planned facilities.
d) Opportunity for Shared Healthcare Services and Facilities
The planned Health Services Center would share facilities with many other
health care providers to serve the entire Imperial County. There may be
opportunities for the Heffernan Memorial Healthcare District to make
meaningful contributions to help Calexico residents.
151 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INCIDENTAL SERVICES
SOLID WASTE SERVICES AND FACILITIES
Currently there are three companies that provide solid waste services throughout the
Imperial County: 1) Republic Services (Allied Waste Services), 2) Lucky Tire Inc.,
and 3) CR&R. The City of Calexico outsources solid waste services through Allied
Waste Services. On December 2, 1997, the City of Calexico entered into an
agreement with Republic Services for waste collection and disposal services. The
City Council voted on November 20, 2007, to extend the current franchise agreement
for an additional ten years, beginning on January 1, 2010.
1. Performance Standards for Solid Waste Services
The State regulates solid waste via laws such as the California Integrated Waste
Management Act (AB 939) which requires solid waste reduction, recycling and
composting and environmentally safe transformation and land disposal.
Municipalities will typically enter into a franchise agreement with solid waste
collection purveyor and performance standards are outlined in the franchise
agreements. Franchise agreements will also detail regarding compliance with
recycling, source separation, and other State requirements. The City of Calexico
is responsible for ensuring compliance with AB 939.
2. Existing and Planned Facilities
There are both local and regional facilities that are available to the Calexico
community. Collection services include solid waste containers, bulky item pick-
up, electronic waste, green waste, and commercial roll-off provisions as typically
spelled out in any franchise agreement to ensure orderly pick-up and disposal of
solid waste to authorized waste sites. The following is an overview of the
facilities and services available to the Calexico community:
a) Inventory of Solid Waste Facilities
There is a Calexico Landfill located at 133 W Highway 98 (New River &
Highway 98), three miles west of Calexico. The Calexico Landfill has a
closure date of 2022 based on site capacity and the daily permitted rate of
disposal. Republic Services transports waste collected from Calexico
residents, generally to the Allied Waste Land Fill in a privately-owned landfill,
located at 104 East Robinson Road in Calexico, within an unincorporated
area. The Allied Waste Landfill was recently expanded and has a disposal
area of 162 acres and an expected closure date of December 31, 2040. Allied
Waste can decide to deposit solid waste at any of the nine landfills in the
county: Calexico Landfill, Holtville Landfill, Hot Spa Landfill, Imperial Landfill,
Niland Landfill, Ocotillo Landfill, Palo Verde Landfill, Picacho Landfill, or
Salton City Landfill.
152 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN INCIDENTAL SERVICES
b) Adequacy of Solid Waste Services and Planned Facilities
Residents within the service area are provided with three receptacles: one
residential cart is for recyclable materials, one residential cart is for green
waste and one residential cart is for refuse. Residents are offered weekly
bulky item pick-up and four free landfill passes.
The current demand for solid waste facilities is based on the collection of
solid waste by Allied Waste. As previously noted, the Calexico Landfill is
expected to reach capacity in 2020 and closure in 2022. However, other
existing solid waste facilities are adequate, and no additional facilities are
necessary. As development occurs, developers are required to ensure that
solid waste facilities are adequate and in place before any new development
is approved.
Construction of the Mesquite Regional Landfill was completed in 2011 and is
located approximately 39 miles north of the City of Calexico. The landfill was
designed as a sanitary landfill to meet all local, state and federal
requirements with a capacity of 600 million tons of waste and a projected life
of approximately 100 years. The site is permitted to receive up to 1,000 tons
per day by truck from Imperial County. There are no additional Solid Waste
Facilities proposed at this time.
c) Buildout Demand for Solid Waste Facilities and Services
As development occurs, through the entitlement process, developers are
required to ensure that solid waste facilities are adequate and in place before
any new development is approved. However, as a result of the economic
recession in 2008 and increased recycling in California, the amount of waste
requiring disposal has significantly gone down since the completion of the
Mesquite Regional Landfill. Operation of the Mesquite Landfill has yet to
commence and use of the facility is available should the demand arise.
Existing landfills will therefore be able to support the additional demand from
Calexico planned development through the twenty year planning period.
d) Opportunity for Shared Solid Waste Services and Facilities
The landfills are shared facilities with many other jurisdictions in Imperial
County. No additional opportunities for shared services are being explored.
3. Phasing of Solid Waste Facilities
Allied Waste is not in the process of constructing additional solid waste facilities
to support the demand anticipated from the City of Calexico.
153 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
V. FINANCING PLAN
The Financing Plan section of the Service Area Plan lists and describes potential
revenue sources and various financing mechanisms available to the City of Calexico in
efforts to meet the projected service and facility demands identified earlier in this
document. This section also describes how each existing facility and service is currently
financed and how future financial demands for these facilities and services may be
secured. The City of Calexico had a 17/18 City-wide budget of $63 Million of which
$13,657,707 were General Fund monies.
The City of Calexico’s audited Financial Statement showed that the General Fund had a
negative fund balance of $3 million at the end of the fiscal year. The total assets
exceeded liabilities by over $95 million at the close of Fiscal Year ending June 30, 2017.
The City’s unrestricted net position increased to $99 million. The latest Financial
Statement shows that the City of Calexico reported positive balances in net position. The
amount of net position in capital assets less related outstanding debt used to acquire
those assets is $99 million. A copy of the June 30, 2017 Annual Financial Report is
included as Appendix F.
Finance plans and available financing options are also discussed in this section.
Enterprise Funds and are largely subject to the guidelines of Proposition 218 which was
enacted in 1996. Proposition 218 clearly defines general taxes and special taxes and
sets guidelines on the issuance, use, and implementation of taxes. Proposition 218
states that general taxes must be approved by a majority of voters before they can be
imposed, extended or increased and special taxes require approval by a two-thirds vote.
A. EXISTING REVENUE SOURCES
This section provides a summary of the revenue sources available to finance the
necessary public facilities and services within the City of Calexico or as areas within
the Sphere of Influence are annexed. The following list presents sources of revenue
that are currently utilized by the City in order to accumulate finances necessary to
develop and operate the various facilities and services discussed within the SAP.
Complete budgetary information for financing mechanisms currently utilized is
available for viewing at the City of Calexico Finance Department.
1. Property Tax
Property taxes generate revenue that can be used to support various
improvements and services including general City expenses. Property taxes in
California are governed by Proposition 13 which limits the property tax rate to
1%. Other voter approved bonds and assessment districts may also generate
tax revenue. The County of Imperial, collects the property tax, and shares the
tax revenue collected from property owners within the City. Property taxes are
154 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
distributed to various entities including, Imperial County, other cities, and special
districts according to formulas and procedures established by California law and
consistent with the “Teeter Plan” for distribution of delinquent taxes owed. Each
eligible tax jurisdiction receives a base amount of property tax that increases or
decreases based on the growth of that district. According to Property Tax
Information issued by the County Controller’s Office (2017), taxes are allocated
as follows: schools receive 59%, Cities receive 22%, County receives 12%,
Special Districts share 3%, Fire Protection receives 3%, and Libraries receive
1%.
The City of Calexico may, and has entered into specific tax sharing agreements
for tax revenue over new annexations. There is however, no official master tax
share agreement in place and each must be negotiated as annexations are
considered. Similar to other jurisdictions in the Imperial County, the City of
Calexico has suffered a decline in property tax due to reduction in assessed
values. The Calexico Finance Department estimates that approximately $1.9
million in property tax revenue may be collected for the fiscal year 2018/19 and
beyond. This tax, which may be collected annually, is utilized by the City to
cover general expenses for all City owned and operated public facilities except
for potable water facilities and wastewater facilities which are stand-alone
enterprise funds. As infill development within the City develops, the anticipated
property tax revenue is also expected to increase.
Expansion outside of the current City limit boundary is not expected to
automatically generate any new tax surplus for the City since the tax base has to
be shared with Imperial County, while facility demand and services in those
areas are borne 100% to the City. Annexation agreements between the County
and the City stipulate that all future tax increment of the annexed property shall
be distributed in the amount of 50% of the increment to the City and 50%million
of the increment to the County effective in the fiscal year following the calendar
year in which annexation was completed. This distribution of future tax revenue
has been historically viewed by the City’s as unfair and each jurisdiction seeks to
secure a more advantageous master tax share agreement with the County.
2. Development Impact Fees
Development Impact Fees are charges to private developers to assure that the
demand of physical and financial impacts to public services and facilities are
adequately addressed. Development Impact Fees can be a significant funding
source to finance large scale capital improvements to public facilities.
Development impact fees are used exclusively to fund the capital costs of new
and improved facilities specifically related to the category for which fees are
charged. The City has adopted impact fees from all new development for the
following services: Corporate Facilities, Library, Police, Fire, Parks & Recreation,
Traffic Transportation, Water, Sewer and Art in Public Places and Administration.
155 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
The most recent adjustment to the impact fees was in 2006. The City of Calexico
adopted Ordinance 1036 in 2006 as development impact fees and collects the
fees from developers prior to the issuance of any building permits. The level of
Development Impact Fees collected on any given year is driven by the level of
new development demand.
3. User Fees
Certain public services and facilities operated by the City of Calexico entail
various user fees that are charged to patrons or other users on a fee-for-service
basis. User fees are typically applied to on a monthly service. Charges for
services such as water, sewer, and trash to residential uses, commercial uses,
industrial uses, and/or public agencies may have incidental user fees charged for
reconnections, penalties, and late fees. The community center and some park
facilities are also charged user fees. The fees are typically used as a revenue
source to maintain the systems in proper operating condition and for the
construction of facilities needed to meet demand.
4. Developer/Builder Contribution
Much of the infrastructure improvements such as sewer, water, drainage, and
roadway improvements required as a result of new development can be directly
funded and constructed by the developer/builder. These required improvements
would be in addition to Developer Impact Fees and User Fees. Developers may
however, construct park space in lieu of the established park fees, or a
combination thereof.
5. Community Facilities District
A Community Facilities District (CFD), not to be confused with a Community
Services District (CSD), falls under the 1982 Mello-Roos Community Facilities
Act. This Act allows a CFD to be established by cities, counties, special districts
and school districts to fund a variety of facilities and services. Note that the
boundaries of a CFD are not required to be contiguous as they are for a CSD. In
order for a CFD to be formed, a public hearing must occur, and an election held
to authorize the specified tax levy to either provide direct funding or pay off
bonds. These mechanisms are more successfully applied to new subdivisions or
groups of development concurrent with annexation. The City of Calexico has
three active CFD’s within its City limit boundary.
6. Federal State and Local Grant Programs
The City of Calexico, like many other jurisdictions must rely on grant funding
programs to augment and supplement local revenues earmarked for capital
156 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
improvements. The City of Calexico has been successful in obtaining some level
of grant funding for all of their community facilities and some community services,
however, the City does not meet some of the prevalent funding criteria to
prioritize small communities at State level or rural communities under USDA. It is
estimated that a very small percentage of the City’s $63 million Budget is from
grant sources.
B. CURRENT FACILITY FINANCING & RECOMMENDATIONS
1. Administrative Service and Facilities
a) Current Funding
The existing administrative facilities are owned and operated by the City of
Calexico. Funding for Administrative Facilities are currently provided by the
General Fund. Specific sources include property and sales taxes, licenses
and permits, fines and penalties, general taxes, service fees and
assessments. The City also approved Measure “H” in 2010 which is a .05
cent sales tax to be used for general government purposes and is scheduled
to sunset in 2040. Similar to other jurisdictions there are special revenue
transfers to the General Fund from other funds or enterprise funds when
direct or indirect fund administrative services are provided. The current
Administration Budget for administrative personnel is $1.5 million or 9% of the
General Fund. Although not a significant source, capital costs for
administrative facility expansion or new development can be offset by the
collection of Impact Fees from new development as noted in the following
table.
Table FP-1 Administrative Facilities Development Impact Fees
Administrative Development Impact Fees Impact Fee Collected
Single Family Unit $87
Multifamily Unit/Mobile Home Unit $74
Commercial Acre $246
Industrial Acre $157
Source: Ordinance 1036
b) Cost Avoidance Opportunities
Administrative service costs may be further reduced by outsourcing some
administrative services including Planning, Legal, Engineering, and special
Project Managers. Another successful practice is cross administration
between departments such as an engineering manager overseeing public
works, wastewater and water facilities and operations.
157 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
c) Recommended Funding
Existing funding sources will continue to be used to support administrative
services and facilities. Development Impact fees may become a key source
of funding for capital facilities in the future as deemed necessary by the City
for the development of a new administrative office space. If substantial
monies are needed, General Obligation Bonds can be issued or a City Wide
Community Facilities District can be formed.
2. Law Enforcement
a) Current Funding
A portion of financing for police protection and law enforcement is currently
financed by property and sales taxes from the General Fund. The City also
approved Measure “H” in 2010 which is a .05 cent sales tax to be used for
general government purposes and is scheduled to sunset in 2040. Other
funding sources include the following State Funded Programs: ABC Grant
through the Department of Alcoholic Control, School Partnership Grant,
Homeland Security Grant Program, Operation Stonegarden Grants, Narcotics
Task Force, State C.O.P.S. Grant, Prop 172 Public Augmentation Funds, and
others as they become available. The current Law Enforcement Budget is
approximately $5 million and includes a contribution of 35% of the General
Fund. Development impact fees are also used for larger capital investments
and equipment.
Table FP-2 Police Facilities Development Impact Fees
Police Facilities Development Impact Fees Impact Fee Collected
Single Family Unit $684
Multifamily Unit/Mobile Home Unit $588
Commercial Acre $2,205
Industrial Acre $1,411
Source: Ordinance 1036
b) Cost Avoidance Opportunities
The Police Department and Fire Department already share dispatching
services and the City has been historically exploring the possibility of a joint
use Public Safety Building. New facilities to the northeast of the community
will be needed in the future as the community continues to grow. Increasing
use of volunteers from IVC/SDSU enrolled in criminal justice programs for
traffic control may also be a viable cost avoidance opportunity.
158 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
c) Recommended Funding
Current General Fund and impact fee sources for police protection and law
enforcement should continue to be used. The development impact fees
being collected will ensure future development contributes its proportional
share to the future demand created. It is also recommended that the Police
Chief continue to pursue grant funding sources as opportunities become
available.
3. Fire Protection
a) Current Funding
Costs for the Calexico Fire Department to provide fire protection services to
the Calexico community are currently financed by property, Transient
Occupancy Tax Funds and sales taxes from the General Fund. The City also
approved Measure “H” in 2010 which is a .05 cent sales tax to be used for
general government purposes and is scheduled to sunset in 2040. Other
revenue is derived from special revenue and State grant sources including
Prop 172 sales tax Public Augmentation Funds and Fire Act Grants. The
current Fire Department Budget is $4.2 million and includes a contribution of
approximately 25% of the General Fund. The City of Calexico also collects
development impact fees from new development.
Table FP-3 Fire Facilities Development Impact Fees
Fire Facilities Development Impact Fees Impact Fee Collected
Single Family Unit $712
Multifamily Unit/Mobile Home Unit $612
Commercial Acre $2,295
Industrial Acre $1,469
Source: Ordinance 1036
b) Cost Avoidance Opportunities
The fire department maintains a mutual aid agreement with other
governmental agencies in order to gain access to specialized equipment and
resources. As previously noted, the Police Department and Fire Department
are exploring options for a joint Public Safety Building which may reduce
operation and maintenance costs via shared facilities in the future. There are
no other cost avoidance opportunities known at this time.
159 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
c) Recommended Funding
Current use of General Fund as a funding source for fire facilities should
continue to be used. In addition, development impact fees have been
implemented to ensure costs of future demand created by future
development can fund major capital investments. A special fire suppression
assessment district or a special tax can also be implemented to assist in
the financing of fire facilities costs.
4. Parks and Recreations
a) Current Funding
The primary sources of revenue for park facilities are property taxes, and the
General Fund followed by Measure H funding and Development Impact Fees.
The City approved Measure “H” in 2010 which is a .05 cent sales tax to be
used for general government purposes and is scheduled to sunset in 2040
and is used for park and recreation improvements. Measure H however, only
brings in about $1.2 million annually. Other revenue is derived from grant
sources. Parks are budgeted under the Public Works Department while
recreation is budgeted under Community Services. The current Park &
Recreation Budget is an estimated $744,909 or 5.5% of the General Fund,
excluding capital projects. The City of Calexico also collects development
impact fees from new development in lieu of park dedication.
Table FP-4 Parks & Recreation Facilities Development Impact Fees
Park & Recreation Facilities Impact Fees Impact Fee Collected
Single Family Unit $1,517
Multifamily Unit/Mobile Home Unit $1,303
Commercial Acre $2,888
Industrial Acre $1,848
Source: Ordinance 1036
b) Cost Avoidance Opportunities
Currently, all new residential development must incorporate park facilities as
a development standard pursuant to the Quimby Act adopted under the Park
& Recreation Element of the Calexico General Plan. The City has further
entered into Joint Use Agreements with park and recreation facilities owned
by the Calexico Unified School District. There are no other cost avoidance
opportunities at this time.
160 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
c) Recommended Funding
The City of Calexico will continue to use the existing financing mechanisms
described above to finance the continued improvement, operation and
maintenance of parkland and recreational facilities. The collected and
contributed property tax may not be significant enough for the capital
improvement needs or continued maintenance costs of the aging parkland in
the community. As new development occurs, the formation of additional
CFD’s may be needed to reduce future operation and maintenance costs.
The City should seek grant funding opportunities through the State
Department of Parks and Recreation, the Department of Conservation, the
California Natural Resource Agency, and other State agencies including HCD
under their Community Development Block Grant Program to improve
established park areas in need of improvement.
5. Library Facilities
a) Current Funding
Library facilities are currently financed by property and sales taxes from the
General Fund. The City approved Measure “H” in 2010 which is a .05 cent
sales tax to be used for general government purposes and may be used for
library improvements. Additional monies are in the form of small grant funds
for service delivery and specific revenue sources including licenses and
permits. The library also accepts private donations of books and material and
collects nominal late fees. Limited grant funding has been made available
through the Veterans Connect at the Library Grant Program, Leamos Literacy
Link Grant Program, Imperial County Community Benefit Fund and the
California State Library Grant Programs. The current Library Budget is
approximately $750,000 plus $1 million for capital improvements. The budget
is almost entirely supported by the General Fund and Measure “H” funding.
However, Development Impact Fees for Library Facilities are also collection
from new residential development.
Table FP-5 Library Facilities Development Impact Fees
Library Facilities Development Impact Fees Impact Fee Collected
Single Family Unit $766
Multifamily Unit/Mobile Home Unit $658
Commercial Acre $0
Industrial Acre $0
Source: Ordinance 1036
161 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
b) Cost Avoidance Opportunities
Although the amounts received are small, the library charges fees for
miscellaneous services such as copies of documents or publications. Through
inter library programs, the library also shares resources with other libraries in
the region to maximize benefit and savings.
c) Recommended Funding
The City should continue using the General Fund as a primary funding
source for library facilities. Additional funding sources such as community
facilities district, special assessment district, Community Block
Development Grants, and other State Grant Resources should be pursued for
capital needs.
6. Circulation and Transportation
a) Current Funding
Funding for circulation facilities is provided by Local Transportation Funds,
Local Sales Tax, State Highway Funds, and Federal Highway Funds as well
as from Traffic and Transportation Facility Development Impact Fees. The
following are the major sources for circulation facility funding:
Statewide Highway Users Tax Account (HUTA) – “Gas Tax” is the primary
source of funds for the overall county road maintenance and safety
improvement program. Costs include equipment purchase and personnel
costs. The State of California collects 30 cents for every gallon of gasoline
sold. The State distributes money back to California counties based on the
number of registered vehicles and miles of roads maintained. This money
becomes special revenue distributed to jurisdictions by the State Controller’s
Office. The City of Calexico receives an estimated $750,000 to $1 million
annually in HUTA funds (based over the last three years). Because there are
little restrictions, HUTA is largely used by the City of Calexico to cover the
administration and operation costs of the Public Words Streets Division
including equipment and material purchase and personnel expenses.
Measure D/LTA Funds- In 1989, Imperial County voters approved Measure
D, a one-half cent transportation sales tax which was scheduled to sunset in
2009. However, in 2008, Imperial County voters extended the sales tax by an
overwhelmingly 81%. The implementation of the 2008 measure began in
2010 and imposed the 0.5% sales tax for the next forty (40) years. On
average, the City of Calexico receives an estimated $1.2 million annually,
which is distributed on a monthly basis. The City of Calexico will bond
revenues as opportunities arise.
162 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
Development Impact Fees: The City of Calexico charges private developers
impact fees to assure that the demand for and physical and financial impacts
to public services and facilities caused by their respective development
projects are adequately addressed. The City adopted their current
transportation development impact fees in 2006. The impact fees from every
new residential unit or non-residential structures constructed within an
unincorporated area. This funding source is largely dependent on the
economy and has a fund balance of $1.6 million as of June 2016. These funds
are restricted for capacity enhancing projects and are not able to be used for
roadway maintenance.
Motor Vehicle In-Lieu Fee: Motor vehicle in-lieu fees (VLF) are levied by the
State for the ownership of automobiles within the State. Funds are then
returned to the County based on population and distributed by the County to
the various jurisdictions, again based on population, and keeping the
corresponding share of unincorporated population. The City of Calexico
receives an estimated $2.8 annually according to the City’s Budget Unit Detail
records through 2016-2017.
Transportation Development Act Article 3/Article 8e: Article 3 funds are
granted by the State Transportation Commission for specific projects related
to pedestrian, bicycle, and wheelchair mobility. The funds are allocated to the
jurisdictions by the Imperial County Transportation Council and Caltrans
through Local Transit Assistance Fund (LTA), and the State Transit
Assistance Fund (STA). The City of Calexico receives an estimated $35,000
of Article 3 funding according to the Imperial County Transportation
Commission Statements.
Additionally, under Article 8e, funding is given to the County and Cities for
transit services for projects meeting public transportation needs. Eligible
projects include, but are not limited to, the maintenance, improvement, and/or
installation of bus shelters and benches. The City of Calexico receives an
estimated $17,000 directly of Article 8e funding annually.
Competitive Grant Sources: The City is eligible to apply to a number of
federally funded grant programs that fund numerous transportation projects.
All grant sources, especially federal funds, come with numerous restrictions.
The majority of federal funds only fund non-local roadway projects as
identified in the California Roadway System (CRS). Projects administered
through Federally funded programs are also likely to increase the overall
project costs. The City of Calexico has over $6 million in transportation grant
funding committed and programmed for upcoming years from different grant
sources derived from federal programs.
163 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
Development Impact Fees: The City of Calexico adopted ordinance 1036
which adopted Traffic Transportation Impact Fees from all new development.
This impact fee is a significant source of funding only to offset new impacts
from new development. The following table provides a summary of the fees
collected.
Table FP-6 Transportation Facilities Development Impact Fees
Transportation Development Impact Fees Impact Fee Collected
Single Family Unit $1,121
Multifamily Unit/Mobile Home Unit $963
Commercial Acre $3,611
Industrial Acre $2,311
Source: Ordinance 1036
b) Cost Avoidance Opportunities
Although the City’s system does not exist independently from regional and
State circulation systems, there are minimal cost avoidance opportunities
known at this time. The City should be proactive in reaching out to Imperial
County for the improvement of County roadways so that when they are
annexed into the City the only borne costs are continued maintenance and not
rehabilitation or reconstruction. The city should continue to require new
development to prepare traffic analysis so that all project impacts are
addressed by the development.
c) Recommended Funding
Current funding sources for circulation facilities should continue to be
used. Additionally, there are several other funding mechanisms for
circulation facilities such as community facilities district and special
assessment district. There are also a number of additional grant funding
programs including the Safe, Accountable, Flexible, and Efficient
Transportation Equity Act (SAFETEA), Highway System Improvement
Program (HSIP), Active Transportation Program (ATP), as well as the
Highway Bridge Program to repair aging infrastructure within the circulation
and transportation system.
7. Stormwater and Drainage Facilities
a) Current Funding
Improvements and Maintenance of stormwater drainage facilities is currently
funded by the General Fund. The City approved Measure “H” in 2010 which
164 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
is a .05 cent sales tax to be used for general government purposes and may
be used for stormwater improvements. The City does not have any adopted
Stormwater Impact Fees. Within the City, drainage facilities are generally
installed and funded by developers as projects are constructed. Routine
maintenance, operation, and personnel costs are not currently tied to any
Community Facility District nor accounted for through any maintenance
agreements. These costs are rather borne under the parks and recreation
side (where joint use park/basins exist) or under the transportation side which
accommodate curb and gutter as well as storm-0water inlets alongside
roadways maintained by the City.
b) Cost Avoidance Opportunities
The City is able to avoid some costs for the development of new drainage
facilities by requiring developers to construct adequate facilities and retention
basins for their projects. Additionally, as the County of Calexico seeks street
funds it should address storm drain facilities within the right-of-way as eligible
costs under FHWA grant funded projects.
c) Recommended Funding
Funding responsibilities for project related facilities should continue to be the
responsibility of developers and secured prior to issuance of any “will serve”
letters for water and/or sewer services that may be requested by developers.
The City should consider making the costs for the ongoing operation and
maintenance of any drainage facilities including retention basins the
responsibility of the new development via the establishment of Assessment
Districts or Home Owners Associations. If for any reason a detention basin
is proposed to be dedicated to the City, it should be necessary to establish a
financing mechanism such as a Community Facilities District.
8. Water Facilities
a) Current Funding
The primary sources of revenue for water treatment and distribution facilities
are the water service charges, connection fees collected and development
impact fees all of which are part of the Water Fund. Water Impact fees were
adopted via Ordinance 1036 and became effective on January 1, 2008.
Development impact fees (capacity fees), which have been collected over the
years, are the only current revenue source for capital improvements to water
facilities and those are noted under Table FP-7.
165 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
Table FP-7 Potable Water Facilities Development Impact Fees
Water Development Impact Fees Impact Fee Collected
Single Family Unit $3,707
Multifamily Unit/Mobile Home Unit $3,185
Commercial Acre $11,943
Industrial Acre $7,644
Source: Ordinance 1036 Effective January 1, 2008
User fees are collected for the continued operation and maintenance of the
water treatment and distribution system. The current user fees are shown in
the following table and were last updated in 2008.
Table FP-8 Potable Water Rates & User Fees
Minimum Water Fee Over Water
Water Rates
Fee Allotment Allotment
(cubic feet) (per 100 cubic feet)
Dwelling Unit $43.89 3,000 $2.22
Each Additional Unit $21.94 1,000 $2.22
Schools $43.89 3,000 $2.22
Churches $43.89 3,000 $2.22
Non-Residential $48.89 1,000 $3.01
Note: One hundred cubic feet of water = 748 gallons
The City issued in 2007, through its Redevelopment Agency, revenue bonds
in the amount of $14,030,000 to fund upgrades to the water treatment plant
and distribution system. Debt service is paid from customer usage fees in an
annual amount of approximately $986,000. The bond matures in 2037.
The City’s Water Fund revenue is expected to be $6.4 million during the
2017-2018 fiscal year. Most of the revenue is from customer service charge
with minimal amounts from investment income and other fees and charges.
Additionally, there is in excess of $2.8 million in the Water Development
Impact Fee Fund which can only be used for capacity-enhancing projects
such as increasing the capacity of the water treatment plant or extending
back-bone water distribution infrastructure to serve future development.
Funds from this account are transferred into the Water Capital Improvement
Program Fund which had a 2018 balance of approximately $13.1 million.
Funds as set aside for phased improvement over the next five years.
166 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
b) Cost Avoidance Opportunities
The City of Calexico requires developers to construct water-related
infrastructure that will connect the specific development to the City’s water
distribution system and to pay Water Development Impact Fees. These
requirement help the City avoid substantial costs associated with new
infrastructure needs and capacity demand.
The water impact fees in general are comparable or lower to water collection
fees of other local jurisdictions. An attributing factor is the type of system from
one jurisdiction to another. When impact fees are substantially lower for
similar systems serving similar sized communities, then it suggests there may
be room for reassessment of fees to adequately address future demand. The
Table below provides an unassessed comparison of Water Impact Fees.
Table FP-9 Water Impact Fee Comparison
Water Impact Fee Comparison
Land Use Calexico HPUD El Centro Brawley
Classification
Single Family Unit $3,707 $3,087 $6,149
Varies by
Multifamily Unit or $3,185 Varies by $6,149
Water Meter
Mobile Home Unit Water Meter
Size
Size ($3,087
Commercial Acre $11,943 $6,149/EDU ($5,275.90 -
- $80,262)
$42,207.20)
Industrial Acre $7,644 $6,149/EDU
Source: Calexico Schedule of Development Impact Fees, HPUD Ordinance 2017-01, Brawley Water
Impact Fee Schedule, El Centro Water and Wastewater Connection Application as of May 2018
c) Recommended Funding
The City of Calexico will continue to utilize these funding sources in addition
to searching for other sources to improve the existing water treatment plant
and distribution system and to meet future demands and capital improvement
goals. Although not expected, any major capital investments associated with
the significant rehabilitation of equipment, or upgrade demands from the
Department of Public Health may require loan funding. The City of Calexico
may not generally qualify for grant funding but may be eligible for subsidized
financing from available State and Federal loan programs.
167 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
9. Sanitary Sewer Collection & Treatment Services
a) Current Funding
The primary sources of revenue for wastewater facilities are development
impact fees and user fees. Development impact fees (capacity fees) which
have been collected over the years are only a revenue source for capital
improvements to wastewater facilities and are currently established as noted
in the following table.
Table FP-10 Wastewater Facilities Development Impact Fees
Wastewater Development Impact Fees Impact Fee Collected
Single Family Unit $2,884
Multifamily Unit/Mobile Home Unit $2,478
Commercial Acre $9,291
Industrial Acre $5,947
Source: Ordinance 1036 Effective January 1, 2008
User fees are collected for operation and maintenance costs and to replace
smaller equipment. The current wastewater user fees were last updated and
became effective on August 1, 2008 and as of the date of the 2018 Service
Area Plan update, the City had no plans to increase the established rates.
Wastewater fees are based on the amount of water consumed and the fee
per customer class is as follows:
Table FP-11 Wastewater Rates & User Fees
Water Fee Over Water
Minimum
Wastewater Rates Allotment Allotment
Fee
(cubic feet) (per 100 cubic feet)
Dwelling Unit (per unit) $38.08 3,000 $3.81
Low Strength Commercial $38.08 1,000 $3.81
Medium Strength Commercial $42.91 1,000 $4.29
High Strength Commercial $47.63 1,000 $4.76
Source: Calexico Website Accessed May 2018.
Note: One hundred cubic feet of water = 748 gallons
The City’s Wastewater Fund balance is expected to be $17.9 Million during
the 2017-2018 fiscal year. The annual revenue is estimated at $5,437,000.
Most of the revenue is from customer service charge with minimal amounts
from investment income and other fees and charges. Additionally, there was
less than $100,000 in the Wastewater Development Impact Fee Fund which
can only be used for capacity-enhancing projects such as increasing the
capacity of the wastewater treatment plant or the primary wastewater
168 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
collection infrastructure to serve future development. Funds from this account
are transferred into the Wastewater Capital Improvement Program Fund
which had a 2018 balance of approximately $15.8 million.
b) Cost Avoidance Opportunities
The City of Calexico requires developers to construct wastewater-related
infrastructure that will connect the specific development with the existing
wastewater treatment system. Developers are also subject to Development
Impact Fees, as previously noted. These requirements help the City avoid
substantial costs associated with new infrastructure needs and capital
demand.
The sewer impact fees in general are lower than wastewater collection fees
of similarly sized jurisdictions. An attributing factor could be the type of
system from one jurisdiction to another. When impact fees are substantially
lower for similar systems serving similar sized communities, then it suggests
there may be room for reassessment of fees to adequately address future
demand. The Table below provides an unassessed comparison.
Table FP-12 Wastewater Impact Fee Comparison
Sewer Impact Fee Comparison
Land Use
Calexico HPUD El Centro Brawley
Classification
Single Family Unit $2,884 $6,660 $7,174
Multifamily Unit/ Varies by
$2,478 $6,660 $7,174/EDU
Mobile Home Unit Water
Commercial Acre $9,291 Varies by $7,174/EDU Meter Size
Industrial Acre Connection ($4,279 -
$5,947 Size ($6,660 $7,174/EDU $34,406)
- $26,642)
Source: Calexico Schedule of Development Impact Fees, HPUD Ordinance 2017-2, Brawley Wastewater
Impact Fee Schedule, El Centro Water and Wastewater Connection Application
c) Recommended Funding
The City will continue to use the financing mechanisms described above.
User fees will continue to finance the wastewater operation, maintenance,
salaries, and equipment costs. The City will continue to require developer
improvements and collect capacity fees to finance the City’s wastewater
service and capital improvement needs. Although not anticipated, any
additional, major capital investments associated with the rehabilitation of
equipment, or Regional Water Quality Board upgrade demands, are expected
to require financing assistance either in the form of bonds or State and
Federal Agency Funding Assistance.
169 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
10. Airport Services & Facilities
a) Current Funding
The Calexico International Airport is a self-budgeted facility operated by the
Calexico Public Works Department. Current revenue sources include sales
of fuel, oil, fuel additives, aeronautical charts and books. Other fees collected
include tie down fees, ramp fees and hanger rentals. There are no
development impact fees collected for Airport facilities or services, but the
City has made use of State planning grants. Specifically, the FAA Airport
Improvement Program was accessed to fund the Calexico International
Airport 20-Year Airport Master Plan.
b) Cost Avoidance Opportunities
There are no cost avoidance opportunities at this time.
c) Recommended Funding
For any capital needs, the City should consider State Grant programs through
the Department of Transportation Aeronautics Division. Other grant
programs that may assist the City with capital needs is the Local Airport Loan
Account which is a revolving loan fund through the California Department of
Transportation. This program provides discretionary State loans to eligible
airports for projects that enhance an airport’s ability to provide general
aviation services (hangars, terminals, utilities, fueling facilities, etc.). Interest
rates are per the latest State General Obligation Bond sales interest rates.
D. CURRENT FACILITY PER CAPITA COSTS AND COMPARISONS
A review of various Cities’ Service Area Plans in Imperial County was conducted to
determine the amount of funds each city spends on municipal services and facilities
on a per capita basis. The purpose of this exercise is to identify areas that should be
assessed further for more cost effective means of service delivery. Only three cities
provided the per capita costs as shown below. It is important to note that these costs
are based on a single year and that there may be various reasons for the varying
costs each city spends per capita, including the type of systems they operate and
outsourcing of services. It is beyond the scope of this Service Area Plan to determine
the variation in per capita cost and comparisons are provided for reference only.
Calexico’s per capita cost is significantly lower than those cities which provided costs
for administrative facilities. Fire protection costs is in the median range amongst the
larger cities, but Calexico spends significantly less for law enforcement facilities as
compared to Brawley and El Centro. Library costs is in the median range compared
to the larger cities, and Calexico spends the least in Parks & Recreation compared to
170 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
all Cities. Refer to Table FP-13 for complete comparison.
Table FP-13 Per Capita Comparison
City Calexico El Centro Brawley Imperial Calipatria
Plan Year 2018 2016 2012 2015 2018
Administrative $22.43 NA NA $134.08 $176.16
Fire Protection $101.71 $150.74 $77.40 $51.63 $103.80
Law Enforcement $121.71 $349.30 $237.03 $137.48 $125.09
Library $18.09 $31.33 $21.47 $12.17 $1.53
Parks and Recreation $17.85 $66.41 $63.05 $35.67 $22.53
Circulation $14.32 $29.67 $128.16 $17.72 $191.3
Sewer $128.88 $509.10 $103.21 $197.28 $109.07
Water $116.99 $320.82 $226.24 $256.42 NA
Stormwater Drainage $0.24 $3.43 NA $1.99 $0.54
Source: Brawley, Imperial, and Calipatria Service Area Plans. El Centro’s per capita cost was calculated based
on data extrapolated from their 2016 Service Area Plan and Municipal Budget.
E. POTENTIAL REVENUE SOURCES FOR CAPITAL NEEDS
There are a number of alternative resources that may be available to the City of
Calexico to address capital needs and to some extend service delivery. The following is
an overview of some of the more widely used sources and programs.
1. Private Financial Institutions Under CRA Objectives
A financing opportunity may be via revenue bonds through private financial
institutions as part of their Community Reinvestment Act (CRA) obligations. The
CRA was enacted by the U.S. Congress in 1977 to encourage depository
institutions to help meet the credit needs of the communities in which they
operate, including low- and moderate-income neighborhoods, consistent with
safe and sound banking operations. The CRA requires federal financial
supervisory agencies to use their authority when examining financial institutions
subject to supervision, to assess the institution's record of meeting the credit
needs of its entire community, including low- and moderate-income
neighborhoods. Local institutions keep a good standing in order to continue to
grow, thus investment opportunities into small community capital improvements
are actively sought be responsible financial institutions. Ratings can range from
Outstanding, Satisfactory and Low Satisfactory. The following lending institutions
have local CRA obligations most of which have had their ratings downgraded
from Outstanding to now Satisfactory, noting a potential opportunity for local
171 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
investment:
• Bank of America- Satisfactory rating as of 2015
• JP Morgan Chase Bank- Satisfactory Rating as of 2010
• Rabobank- Satisfactory Rating as of 2011
• Union Bank of California- Outstanding Rating as of 2015
• Wells Fargo- Satisfactory Rating as of 2013
2. Public Financial Institutions
North American Development Bank (NADBank) - NADBank is a binational
financial institution capitalized and governed equally by the United States and
Mexico for the purpose of financing environmental projects certified by the Border
Environment Cooperation Commission (BECC). The two institutions work
together with communities and project sponsors in both countries to develop and
finance infrastructure necessary for a clean and healthy environment for border
residents. NADBank can make loans to public and private borrowers, at market
and low-interest rates, for the implementation of environmental infrastructure
projects located in the U.S.-Mexico border region. Loans are available for the
implementation of projects in all environmental sectors in which the NADBank
operates.
California Infrastructure and Economic Development Bank (IBank) - The
Infrastructure State Revolving Fund (ISRF) Program provides low-cost financing
to public agencies for a wide variety of infrastructure projects. ISRF Program
funding is available in amounts ranging from $250,000 to $10,000,000, with loan
terms of up to 30 years. Interest rates are set on a monthly basis. Preliminary
applications are continuously accepted.
3. Federal Grant Agencies
U.S. Environmental Protection Agency (EPA) - EPA’s mission is to protect
human health and the environment. Nearly half of their budget goes is used
towards grants to state environmental programs, non-profits, educational
institutions, and others. The funds are used for a wide variety of projects, from
scientific studies that assist in EPA making decisions to community cleanups.
Overall, grants assist EPA in achieving their overall mission: protect human
health and the environment. EPA’s Border Water Infrastructure Program provides
grant assistance to communities along the U.S./Mexico border to develop and
construct infrastructure to provide safe drinking water and adequate sanitation,
and to improve water quality in shared and trans-boundary waters. EPA funds
grant programs through the BEEC created in 1993 under a side agreement to the
North American Free Trade Agreement (NAFTA) for the purpose of enhancing
172 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
the environmental conditions of the US-Mexico border region. BECC and
NADBank work closely with other border stakeholders including federal, state,
and local agencies, the private-sector and civil society to identify, develop,
finance and implement environmental infrastructure projects on both sides of the
US-Mexico border. BECC focuses on the technical, environmental, and social
aspects of project development, while NADBank concentrates on project
financing and oversight for project implementation. Three Grant Programs
available through BECC are the Community Assistance Program (CAP), the
Project Development Assistance Program (PDAP) and Border Environmental
Infrastructure Fund (BEIF) as follows:
• Community Assistance Program (CAP): The Community Assistance
Program is administered through BECC and funds smaller shovel-ready
projects up to $500,000. Funded with NADB’s retained earnings, this
program offers grant financing to support the implementation of projects
sponsored by public entities in all environmental sectors eligible for NADB
financing. The objective of this program is to support the implementation
of critical environmental infrastructure projects for sponsors with limited
capacity to incur debt.
• Project Development Assistance Program (PDAP): Funding is
available for project development activities necessary for certification of
projects including, but not limited to planning studies, environmental
assessment, final design, financial feasibility, community participation,
and development of sustainability elements. Final design grant assistance
is limited to 50% of the final design costs and cannot exceed $500,000.
• Border Environmental Infrastructure Fund (BEIF): Grants are intended
to supplement funding from other sources in order to complete a project’s
financial package. Applicants must seek other sources of funding since
BEIF is considered to be the funding of last resort. Actual BEIF
participation is considered on a project-by-project basis and determined
according to funding availability and based on an affordability analysis to
be conducted by NADBank during project development.
US Economic Development Administration: Grants for Public Works and
Infrastructure Development. The objective of this grant is to promote economic
development and assist in the construction of facilities needed to encourage the
creation and retention of permanent jobs in an area experiencing severe
economic distress. The facilities can include access roads to industrial parks, rail
road siding and infrastructures improvements for industrial parks. The basic grant
may fund up to 50% of the cost of the facilities. For communities that are
severely depressed, the grant may fund up to 80% of the construction of the
facilities.
173 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
Federal Highway Administration (FHWA) - The FHWA extends numerous
grant programs for eligible roadways. The FHWA identifies and maintains
functional classification as a key item in transportation data. Streets and
highways are grouped into classes according to the service they provide. The
California Road System (CRS) maps identifies functionally classified roadways
which is then used in determining eligibility for Federal funding to maintain the
roads. “Local Roadways” and streets that are not classified as Principal Arterials,
Minor Arterials, Major Collectors, or Minor Collectors on the California Road
System (CRS) Map, are generally not eligible for federal transportation funding.
The City may request from time to time, functional classification changes in an
effort to add roadways to the functional classification system. The last CRS Map
amendment for the City of Calexico was approved in March of 2016. The
following are a list of programs available for eligible roadways:
• State Transportation Improvement Program (STIP): STIP is
administered by Caltrans. The STIP is a multi-year capital improvement
program of transportation projects on and off the State Highway System.
Eligible projects include state highway improvements, regional highway
and transit improvements and non-local roadways as identified in CRS.
• Highway Safety Improvement Program (HSIP): HSIP is administered
by Caltrans and provides funding for safety improvements on public roads
and highways. The program goal is to reduce the number and severity of
traffic accidents at hazardous locations including open drains and canals
with accident history. The program is cost benefit based. The program is
highly competitive and project nominations are submitted to Caltrans for
ranking within each Caltrans district. A three year program is developed
based on the ranking and available funding for projects.
• Congestion Management & Air Quality (CMAQ) Program: CMAQ is
administered by the Federal Highway Administration, and allocated
through Caltrans. CMAQ is set to provide approximately $2.3 billion
dollars in funding per year from 2016 to 2020 nationwide. Each state has
to set aside within the CMAQ apportionment 2% for State Planning and
Research and for States that have a nonattainment or maintenance area
for fine particulate matter (PM2.5), an amount equal to 25% of the amount
of State’s CMAQ apportionment attributable to the weighted population of
such areas in the State which would be applicable to Imperial Valley.
CMAQ funds are to be used for transportation projects or programs that
would contribute to attainment or maintenance of national air quality
standard. Eligible projects includes pavement of dirt shoulders, sidewalk
installation that will reduce vehicle trips, pavement of parking lots and
similar transportation projects. Local Roadways as identified in CRS map
are not eligible for funding unless it is unpaved and ICTC supports it.
174 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
• Hazard Elimination Safety (HES) Program: Funds from this Caltrans-
administered program may be applied to specific projects that are
intended to correct or substantially improve an existing safety hazard,
such as the undergrounding of open canals near roadways or the
installation of traffic signals at busy intersections or intersections with a
history of accidents. This Program is under a competitive application
process and has a fiscal year funding cycle. Virtually any type of public
surface transportation facility improvement, including bicycle and
pedestrian facilities, may be approved.
• Safe Routes to School (SRTS): The SRTS programs administered by
Caltrans are competitive grant programs that utilize federal and state
funds for the purpose of reducing transportation related injuries and
fatalities among school children. Eligible activities include the construction
of pedestrian and bicycle facilities, traffic calming improvements, safety
and traffic control devices, and public outreach and education in
partnership with neighborhood groups and schools. The SRTS programs
are no longer stand-alone funding sources, and have been consolidated
under the Active Transportation Program described below.
• Active Transportation Program (ATP): The ATP is a Caltrans
Administered Program which was established in 2013 by SB99 which
encouraged the use of active transportation methods such as walking and
biking. The purpose of this program is to increase the proportion of active
transportation, increase safety and mobility and ensure that
disadvantaged share the benefits provided through this program.
• Highway Bridge Program (HBBR and HBP) is used to replace or
rehabilitate bridges. HBP is a safety program administered by Caltrans
and provides federal funds to replace and rehabilitate deficient locally
owned public highway bridges. Bridges on Local Roadways would be
eligible for funding. Applications are accepted by Caltrans on an on-going
basis. Projects must qualify based on a Caltrans inspection report and
rating on bridge facilities.
• Moving Ahead for Progress in the 21st Century ACT (MAP-21) signed
into law in 2012 streamlines performance-based, multimodal programs
that address challenges on the US transportation system. As provided in
the Summary of Highway Provisions prepared by the FWHA projects that
strengthen federal highways, establish performance-based programs,
create jobs and economic growth, address the Department of
Transportation’s safety agenda, streamlines Federal highway
transportation programs, and accelerates the project delivery and
provides innovation to our Highway system.
175 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
• The Safe, Accountable, Flexible, and Efficient Transportation Equity
Act (SAFETEA). The Safe, Accountable, Flexible, and Efficient
Transportation Equity Act: A Legacy for Users (SAFETEA-LU) puts its
emphasis in target investment with core programs similar to MAP-21.
Under this act, federal funding is available for highway, safety, and public
transportation programs and is administered by Caltrans.
• Western Federal Lands Access Program: The Federal Lands Access
Program was created by MAP-21 to improve access to federal lands. The
program is directed towards public highways, roads, bridges, trails and
transit systems that are under state, county, town, township, tribal,
municipal or local government jurisdiction or maintenance and provide
access to federal lands. The following activities are eligible for
consideration: preventive maintenance, rehabilitation, restoration,
construction and reconstruction; Adjacent vehicular parking areas;
provisions for pedestrian and bicycles; construction and reconstruction of
roadside rest areas, operation and maintenance of transit facilities.
Eligibility of land along the New River should be explored.
• Transportation Investment Generating Economic Recovery
Discretionary Grant (TIGER): The TIGER program provides a unique
opportunity for the US Department of Transportation to invest in road, rail,
transit and port projects that promise to achieve critical national
objectives. Projects that are eligible for TIGER Discretionary Grants are
capital projects that Include highway or bridge projects under Title 23,
public transportation projects eligible under chapter 53 of title 49,
passenger and freight rail transportation, port infrastructure investments,
and intermodal projects.
• FHWA Accelerated Innovation Deployment (AID) Demonstration
Program: AID provides funding as an incentive for eligible entities to
accelerate the implementation and adoption of innovation in highway
transportation. FHWA encourages the use of AID Demonstration funds to
improve highway planning, design, construction and operation. Eligible
projects may involve any aspect of highway transportation. Innovations
may include infrastructure strategies or activities that the applicant or sub-
recipient intends to implement and adopt as a significant improvement
from the conventional practice.
176 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
4. State Grant Agencies
State Water Resources Control Board- The Division of Financial Assistance
(DFA) administers the implementation of the State Water Resources Control
Board’s (State Water Board) financial assistance programs that include loan and
grant funding for construction of municipal sewage and water recycling facilities,
remediation for underground storage tank releases, watershed protection
projects, nonpoint source pollution control projects, and other similar projects.
The State Water Resource Control Board administers the Clean Water State
Revolving Fund (CWSRF), the Drinking Water State Revolving Fund and Small
Community Wastewater Grant (SCWG) Programs. More information on each
Program is found below.
• Clean Water State Revolving Fund Program (CWSRF)- The Clean
Water State Revolving Fund Program accepts applications on a
continuous basis. The Federal Water Pollution Control Act (Clean Water
Act or CWA), as amended in 1987, established the Clean Water State
Revolving Fund (CWSRF) program. The CWSRF program offers low
interest financing agreements for water quality projects. Annually, the
program disburses between $200 and $300 million to eligible projects.
• Drinking Water State Revolving Fund Program (DWSRF)- The
Drinking Water State Revolving Funds Program was established by the
1996 amendments to the Safe Drinking Water Act (SDWA). The DWSRF
is a financial assistance program to help water systems and states to
achieve the health protection objectives of the SDWA. The state
DWSRFs have provided more than $32.5 billion to water systems through
2016. Small disadvantaged communities can obtain up to 100% grant
funding for eligible projects.
California Department of Housing and Community Development - The State
Community Development Block Grant (CDBG) program was established by the
federal Housing and Community Development Act of 1974, as amended (42 USC
5301, et sequentia). The State CDBG program is implemented by California
Health and Safety Code section 50825, et sequentia, and the California Code of
Regulations (Title 25, Section 7050, et sequentia). Each year the program makes
funds available to eligible jurisdictions through several allocations. Under the
General Allocation, jurisdictions may apply for funding to subsidize public
facilities or special assessment districts for the community as a whole or for
target areas. The primary federal objective of the CDBG program is the
development of viable urban communities by providing decent housing and a
suitable living environment and by expanding economic opportunities, principally
for persons of low and moderate income. "Persons of low and moderate income"
177 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN FINANCING PLAN
or the "targeted income group" (TIG) are defined as families, households, and
individuals whose incomes do not exceed 80%t of the county’s median income,
with adjustments for family or household size.
California State Parks - The Office of Grants and Local Services (OGALS)
develops grant programs to provide funding for local, state, and nonprofit
organization projects under numerous programs as follows:
• Land and Water Conservation Fund - The LWCF is a local assistance
program administered by the Department of Parks and Recreation.
Projects under this grant program include acquisition or development of
outdoor recreation areas and facilities with an annual grant budget of
approximately $5 million.
• Recreation Trails Program - The RTP is administered through the
Federal Highway Administration and the Department of Parks and
Recreation. The RTP provides funds to develop and maintain
recreational trails. The Program allocates funds annually and budgets
approximately $3.5 million.
178 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN RESOURCES AND REFERENCES
Resources and References
Blodgett/Baylosis Environmental Planning. (June 8, 2015). Gran Plaza Phase 2 Power
Center Environmental Impact Report SCH#2014061070.
“Calexico Downtown Plan.” (July 2009). Compass Blueprint.
“Calexico – Your Strategic Border Site.” City of Calexico, California, www.calexico.ca.gov/
California Department of Transportation, Structure Maintenance and Investigations. (April
2018). Local Agency Bridge List, District 11, Imperial County.
Calexico Municipal Code Title 17 - Zoning. (2017).
Chelsea Investment Corporation. (2018). Las Padreras (Calexico Ramin) - 2018 Competitive
9% Tax Application for Low-Income Housing Tax Credits.
City of Calexico. Adopted Municipal Budget. (FY 2017-2018).
City of Calexico. (2006, May 31). Adopted Service Area Plan.
City of Calexico. (2002). Calexico International Airport Master Plan – Final Report.
City of Calexico. (2017). Capital Improvement Program.
City of Calexico. (2015). Circulation Element of General Plan Update.
City of Calexico. (2015). City of Calexico 2015 General Plan Update.
City of Calexico. (2018). Final Bicycle Master Plan Update.
City of Calexico. (2016). 5 Year Program Projects List 2016-2021.
City of Calexico. (2014, 21 January). Housing Element of General Plan 2013-2021.
City of Calexico. (2015, August). Land Use Element of General Plan Update.
City of Calexico. (2018). Wastewater Capacity for Plan Components. Wastewater System
Supervisor.
Classes of Airports 19 CFR Part 122, Subpart B - . (1988).
Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000, Government Code
§§ 56000 et sequentia. (2000).
Dynamic Consulting Engineers, Inc. (2011). Urban Water Management Plan Draft.
FAA Master Record Form 5010 for Calexico International Airport. (2018).
179 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN RESOURCES AND REFERENCES
General Services Administration. (2011) Final Environmental Impact Statement for
Expansion and Reconfiguration of the Land Port of Entry in Downtown Calexico, California
Hofman Planning and Engineering. (2008). City of Calexico Service Area Plan Amendment
“A”.
Huitt-Zollaes, Inc. “Calexico Border Intermodal Transportation Center Feasibility Study.”
(23 October, 2014).
The Imperial Valley Campus, www.ivcampus.sdsu.edu/the_sdsu_ivc/.
Imperial Valley Transit. (March 2018). Imperial Valley Transit Rider Guide.
Jack Schreder & Associates, Inc. (2017). Facility Needs Assessment for Calexico Unified
School District.
Lin, S. D. (2001). Water and Wastewater Calculations Manual. McGraw-Hill.
NCE. (October 2016). California Statewide Local Streets and Roads Needs Assessment.
(2014). NPDES Permit Number CA7000009, Order R7-2014-0004, Waste Discharge
Requirements for City Of Calexico Water Pollution Control Plant.
Palazzo Subdivision – LAFCO Application. (15 August, 2006). Imperial County LAFCO.
The Pun Group Accountants & Advisors. “City of Calexico Transportation Development Act
Article 3 and Article 8e.” (30 June, 2015-16).
The Pun Group Accountants & Advisors. “Basic Financial Statements and Independent
Auditors’ Report.” (30 June, 2017).
The Pun Group Accountants & Advisors. “City of Calexico Single Audit and Independent
Auditors’ Reports.” (30 June, 2016).
The Pun Group Accountants & Advisors. “City of Calexico Single Audit and Independent
Auditors’ Reports.” (30 June, 2017).
The Pun Group. (2017) City of Calexico – Transportation Development Act Article 3 and
Article 8e.
“Recorded Certificate of Completion – Riverview Condo (CX 7-04).” (30 January 2008).
Imperial County LAFCO.
“Recorded Certificate of Completion – Estrella Subdivison (CX 01-05).” (26 January 2010).
Imperial County LAFCO.
“Recorded Certificate of Completion – Salas/Colhoun Properties (CX 02-04).” (14 June
2007). Imperial County LAFCO.
180 CITY OF CALEXICO
October 2018
DRAFT SERVICE AREA PLAN RESOURCES AND REFERENCES
“Recorded Certificate of Completion – McMillin Homes-El Portal (CX 1-04).” (7 June
2007).Imperial County LAFCO.
Requirements for New Development City of Calexico Public Works/Engineering Dep
State of California, Department of Finance. (2017). E-1 Population Estimates of Cities,
Counties and the State - January 1, 2016 and 2017. Sacramento, CA.
2016-17 Student Demographic Data. (2017, October 19). Retrieved from Education Data
Partnership: https://www.ed-data.org/
Tallahasee Democrat. (2018, April 19). Bridge Inspections: Imperial (California). Retrieved
from Tallahasee Democrat: http://data.tallahassee.com/bridge/california/imperial/06025/
Transport Group. (2016). Imperial County Safe Routes for School Regional Master Plan.
U.S. Census Bureau. “Your Geography Selections.” American FactFinder - Results, 5 Oct.
2010,factfinder.census.gov/faces/tableservices/jsf/pages/productview.xhtml?pid=ACS_16_5
YR_B01003&prodType=table.
Webb Associates and Hofman Planning Associates. (2006). City of Calexico Service Area
Plan.
West & Associates. (2017). 2017 Urban Water Management Plan.
West & Associates. (2015). 2015 Urban Water Management Plan.
181 CITY OF CALEXICO
October 2018