LAFCO
Iid 2025 10 17 25 Final No 3 Clean Service Area Plan
Read the report at Local Agency Formation Commissions ↗
2025 Service Area Plan
Prepared for Imperial County LAFCO
Table of Contents
I. INTRODUCTION ..................................................................................................................................... 1
A. IID GOVERNANCE .............................................................................................................................. 1
B. SERVICE AREA PLAN INTRODUCTION & PURPOSE ............................................................................ 2
C. SERVICE AREA PLAN REQUIREMENTS ............................................................................................. 11
D. ORGANIZATIONAL STRUCTURE OF SERVICE AREA PLAN ................................................................ 11
II. EXECUTIVE SUMMARY ........................................................................................................................ 13
A. AREA GROWTH SUMMARY ............................................................................................................. 13
B. SUMMARY OF FINDINGS ................................................................................................................. 14
III. GROWTH AND POPULATION PROJECTIONS.................................................................................... 23
A. REGIONAL SETTING AND CHARACTERISTICS ................................................................................... 23
B. GROWTH PROJECTIONS .................................................................................................................. 27
C. IMPACTS FROM LAND USE CHANGES .............................................................................................. 34
IV. PUBLIC FACILITIES AND SERVICES ................................................................................................... 37
A. IRRIGATION WATER FACILITIES ....................................................................................................... 38
B. IRRIGATION DRAINAGE FACILITIES................................................................................................. 53
C. POWER FACILITIES ........................................................................................................................... 62
D. EFFICIENCY & CONSERVATION PROGRAMS AND SERVICES ........................................................... 84
E. ADMINISTRATION SERVICE AND SUPPORT FACILITIES ................................................................. 113
V. FINANCING PLAN .............................................................................................................................. 131
A. EXISTING REVENUE SOURCES ....................................................................................................... 131
B. CURRENT FACILITY FINANCING AND RECOMMENDATIONS ......................................................... 137
C. POTENTIAL ADDITIONAL REVENUE SOURCES FOR CAPITAL NEEDS ............................................. 150
i
Tables
Table I- 1 Communities within Service Areas .............................................................................................. 7
Table EX- 1 Service Area Population Projections ...................................................................................... 14
Table G- 1 Disadvantaged Communities within Service Areas ................................................................. 26
Table G- 2 Imperial Region Population Projections .................................................................................. 27
Table G- 3 Coachella Valley Region Population Projections ..................................................................... 28
Table G- 4 Service Area Populations .......................................................................................................... 28
Table G- 5 Non-Agricultural Water Demand Projections .......................................................................... 30
Table G- 6 Agricultural Water Demand Projections as AFY ...................................................................... 31
Table G- 7 Water Demand Projections in AFY ........................................................................................... 31
Table G- 8 Annual Energy Demand and 1 in 10 Peak Load Forecasts ....................................................... 34
Table W- 1 2024 Water Distribution System ............................................................................................. 43
Table W- 2 IID 2024 Reservoir Specifications ............................................................................................ 43
Table W- 3 IID 2024 Flow Monitoring and Control Devices ...................................................................... 44
Table W- 4 IID Metering Equipment .......................................................................................................... 45
Table W- 5 Planned Operation Reservoirs ................................................................................................ 49
Table W- 6 IRWMP Non-Agricultural Water Demand Projections ........................................................... 87
Table W- 7 Agricultural Water Demand Projections & Total Water Demand ......................................... 87
Table D- 1 IID Drainage System .................................................................................................................. 55
Table D- 2 IID Drain Monitoring Practices ................................................................................................. 58
Table P- 1 IID Hydroelectric Generation Plants/units, January 2023 ....................................................... 68
Table P- 2 IID Thermal Generation Plants/Units, January 2023 ............................................................... 69
Table P- 3 Solar Photovoltaic Generation, January 2023 .......................................................................... 71
Table P- 4 2023 Energy Load Forecast for Low, Mid and High Demand ................................................... 77
Table CW- 1 System Conservation Program Conservation Yield History ................................................. 94
Table CW- 2 TLCFP Conservation Yield History ......................................................................................... 95
Table CW- 3 On-Farm Efficiency Conservation Program Conservation Yields History ............................ 96
Table CW- 4 Water Conservation Programs Distribution Schedule ......................................................... 96
Table CW- 5 Anticipated Water Conservation Planning Targets .............................................................. 97
Table CW- 6 Planned Operational Reservoirs & Estimated Conservation Yields ..................................... 99
Table CW- 7 Planned Intertie Project and Conservation Yields .............................................................. 100
Table CE- 1 IID Board Adopted Energy Savings Targets .......................................................................... 110
Table A- 1 Administration and Support Facilities Inventory ................................................................... 122
Table A- 2 2024 Office Space Adequacy for Administrative and Support Staff ..................................... 125
Table A- 3 Administrative Facilities Future Demand............................................................................... 127
ii
Table F- 1 2024 Interim Water Supply Policy Development Fee ............................................................ 133
Table F- 2 2024 Interim Water Supply Policy Reservation Fee ............................................................... 134
Table F- 3 SCIA System Conservation Water Payment Rate ................................................................... 137
Table F- 4 Adopted 2024 Water Rate Schedule ....................................................................................... 138
Table F- 5 Planned Water Capital Project Costs* .................................................................................... 139
Table F- 6 Charge for Drainage Service .................................................................................................... 141
Table F- 7 Projected Drainage Facilities Costs ......................................................................................... 142
Table F- 8 Limited Schedule of Energy Rates ........................................................................................... 143
Table F- 9 Planned Capital Energy Project Costs (1,000's) ...................................................................... 144
Table F- 10 Planned Water Transfer Capital Project Costs (1,000's) ...................................................... 146
Table F- 11 Planned Administrative Facilities Capital project Costs (1,000's) ........................................ 149
Figures
Figure 1 Imperial Irrigation District Boundary............................................................................................. 4
Figure 2 IID Water Service Area Boundary .................................................................................................. 5
Figure 3 IID Energy Service Area .................................................................................................................. 6
Figure 4-IID Service Population .................................................................................................................. 25
Figure 5 Imperial Unit Canal Network ....................................................................................................... 42
Figure 6 Water Quality Monitoring Sites ................................................................................................... 57
Figure 7 IID's Generation’s Resource Portfolio ......................................................................................... 67
iii
iv
ACRONYMS AND ABBREVIATIONS
Acronym/Abbreviation Definition
AAC All American Canal
AAEE Additional Achievable Energy Efficiency
AAFS Additional Achievable Fuel Substitution
AC Acre
AF Acre-feet
AFY Acre-feet per year
AGC Automatic Generation Control
AMI Advanced Metering Infrastructure
AMR Automated Meter Reading
BA Balancing Authority
BECC Border Environment Cooperation Commission
BEIF Border Environmental Infrastructure Fund
BESS Battery Energy Storage System
BHE Berkshire Hathaway Energy
BIA Bureau of Indian Affairs
BIA Bureau of Indian Affair
BMP Best Management Practice
BOD Biochemical Oxygen Demand
Ca+ Calcium ion
CAISO California Independent System Operator
CAP Community of Assistance Program
CCRLF Climate Catalyst Revolving Loan Fund
CDP Census Designated Place
CDPH California Department of Public Health
CDWR California Department of Water Resources
CEC California Energy Commission
CEDU California Energy Demand Update
CESP Custom Energy Solutions Program
CI Chemical ionization
CIP Capital Improvement Plan
CLEEN California Lending for Energy and Environmental Needs
CMUA California Municipal Utilities Association
CO Carbon Dioxide
2
CO Carbon Trioxide
3
COP Certificate of Participation
CP Coincident Peak
CPI Consumer Product Index
CPS Control Performance Standard
CRA Community Reinvestment Act
CRWDA Colorado River Water Delivery Agreement
CSP Customer Service Proposal
CTR Controlled Thermal Resource
CU Consumptive use
CVWD Coachella Valley Water District
v
CWA Clean Water Act
CWA Clean Water Act
CWSRF Clean Water State Revolving Fund
DFA Division of Financial Assistance
DIP Deficit Irrigation Program
District Imperial Irrigation District
DNV GL Det Norske Veritas
DO Dissolved Oxygen
DOF Department of Finance
DP Dewatering Pump
DSM Demand-side Management or Design side management
DWQIP Drain Water Quality Improvement Plan
E. coli Escherichia coli,
EC Electrical Conductivity
EEC Energy Efficiency and Conservation
ECA Energy Cost Adjustment
ECGS El Centro Generating Station
ECSS El Centro Switching Station
EE Energy Efficiency
EHL East Highline Canal
EIR Environmental Impact Report
EIS Environmental Impact Statement
EPA Environmental Protection Agency
ET Evapotranspiration
EV Electric Vehicles
FEMA Federal Emergency Management Agency
FERC Federal Energy Reliability Commission
FIT Feed-in tariff
FT Feet
FTE Full time employee
GE General Electric
GHG Greenhouse Gas
GPS Global Positioning System
GW Gigawatt
GWh Gigawatt hour
HCO Bicarbonate
3
HVAC Heating, Ventilation and Air Conditioning
HWY Highway
I Interceptor
IBank California Infrastructure and Economic Development Bank
ICFB Imperial County Farm Bureau
ICS Intentionally Created Surplus
IEPR Integrated Energy Policy Report
IID Imperial Irrigation District
IPP Independent Power Producers
IRP Integrated Resource Plan
IRWMP Integrated Regional Water Management Plan
ISRF Infrastructure State Revolving Fund
vi
IT Information Technology
IT/OT Infrastructure and Operations
ITP Incidental Take Permit
IWSP Interim Water Supply Policy
JPA Joint Power Agreement
KAF Thousand Acre-feet
KAFY Thousand Acre-feet per year
kV Kilovolt
KWH Kilowatt hour
LAFCO Local Agency Formation Commission
LAN Local Area Networks
Lbs Pounds
LED Light-emitting diode
M2C Meter-to-Cash
MAF Million Acre-feet
MAFY Million acre-feet per year
Mg Magnesium
mg/L Milligrams per liter
MM Millimeter
Mt Metric tons
MVA Mega volt-amperes
MW Megawatt
MWD Metropolitan Water District
MWh or MWhr Megawatts per hour
N Nitrogen
Na+K Sodium-Potassium
NADBank North American Development Bank
NAFTA North American Free Trade Agreement
NCPA Northern California Power Agency
NEL Net Energy for Load
NEM Net Energy Metering
NERC North American Energy Reliability Corporation
NGVIDD North Gila Valley Irrigation and Drainage District
NH Ammonia
3
NO Nitrogen Dioxide
2
NO Nitrate
3
NPDES National Pollutant Discharge Elimination System
NSP Nonpoint Source Pollution
O&M Operation and Maintenance
OFECP On-Farm Efficiency Conservation Program
P Phosphorus
PBC Public Benefit Charge
PDAP Project Development Assistance Program
pH Potential of hydrogen
PPA Power Purchase Agreement
PPR Present Perfected Rights
PV Photo-voltaic
PVNGS Palo Verde Nuclear Generating Station
vii
QSA Quantification Settlement Agreement
R Regulating
RPS Renewable Portfolio Standard
SAP Service Area Plan
SCADA Supervisory Control and Data Acquisition
SCAG Southern California Association of Governments
SCE Southern California Edison
SCIA System Conservation Implementation Agreement
SCPPA Southern California Public Power Authority
SDG&E San Diego Gas and Electric
SDCWA San Diego County Water Authority
SF Square Feet
SJGS San Juan Generating Station
SO Sulfate Ion
4
SOC System Operations Center
STEP Strategic Transmission Expansion Plan
SWRCB State Water Resource Control Board
TDS Total dissolved solids
TLCFP Temporary Land Conversion Fallowing Policy
TMDL Total maximum daily load
TSS Total Suspended Solids
US United States
USBR United States Bureau of Reclamation
USDA United States Department of Agriculture
V Volts
VoIP Voice Over Internet Protocol
VPN Virtual Private Networks
WAN Wide Area Networks
WAPA Western Area Power Administration
WECC Western Electricity Coordinating Council
WFL Western Farm Lands
WIS WMO Information System
WISKI Water Management Information Systems
WLAN Wireless Local Area Networks
WMID Western Meadows Irrigation District
YA Yuma Area
YID Yuma Irrigation District
YMIDD Yuma Mesa Irrigation and Drainage District
viii
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
I. INTRODUCTION
The Imperial Irrigation District (“IID”) is a public entity organized in 1911 pursuant to the Irrigation
District Law (California Water Code sections 20500 et. seq.). IID is empowered to provide irrigation
and energy related services to customers within its district boundaries and, through service
contracts, to customers outside of its district boundaries. The district has the powers of eminent
domain and is authorized to contract, to construct works, to fix rates and charges for commodities
or services furnished, and to incur indebtedness related to its functions and purposes.
A. IID GOVERNANCE
The governing structure of the IID consists of an elected five-member Board of Directors that
meet the first and third Tuesday of every month at 1285 Broadway, in El Centro, California
and semiannually in La Quinta, California. IID is managed by a board appointed general
manager. IID’s general counsel and auditor also report directly to the board. The board is
composed of five individuals who are elected by registered voters from the geographic
divisions in which they reside within the district. All of the district political divisions are
located within Imperial County.
The Imperial Irrigation District has two primary operational departments, the Water
Department and the Power Department, which are overseen by the general manager’s
Executive Department and supported by four additional service departments: General
Services, Information Technology, Finance, and Human Resources and also manages
governmental affairs and communications (internal and external). The IID Board of Directors
receives critical administrative support from the Executive Department, which oversees
energy reliability compliance, real estate and risk management functions as discussed under
the Administrative Section of this Service Area Plan (the “SAP”).
IID Operational Resources and Budget
The adopted IID 2024 Budget Plan demonstrates an overall operation with 1,446 regular
position employees with an almost equal distribution of employees within the Water
Department (466 FTE or 32 percent), Power Department (478 FTE or 34 percent) and all other
Executive and Administrative/Support Departments (502 FTE or 34 percent). The 2025
Budget Plan reflects revenues and funding estimated at $813 million from the Power
Department and $335 million from the Water Department (including transfer funds). The
current financial resources utilized by the district are discussed under the Finance Plan Section
of this SAP (see website for full IID Budget Plan.)
IMPERIAL IRRIGATION DISTRICT
1
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
B. SERVICE AREA PLAN INTRODUCTION & PURPOSE
The Board of Directors and the general manager are committed to the overall mission of
providing reliable, efficient and cost-effective water and energy services to the communities
IID serves. The specific powers that are exercised by the district include, but are not limited
to the following:
• Supply of raw water for beneficial purposes including the construction, operation
and maintenance of canals, pipelines, and water conveyance infrastructure;
• Provision of drainage functions made necessary by the irrigation services provided
for and by the district;
• Construction, operation and maintenance of dams, reservoirs, conjunctive use,
reclamation, and other water management projects and works owned and/or
operated by the district;
• Generation, purchase, or lease of electric power, including the acquisition,
operation, and control of plants for the generation, transmission, and provision of
electric power;
This SAP examines all of the services provided by IID, the current service demand and the
projected future service needs within the district’s service area(s). Consistent with the
Cortese-Knox-Hertzberg Local Government Reorganization Act of 20001, this SAP is
structured to provide a basis and framework for current and future service assessments and
planning.
Purpose of the SAP under AB 1484
In 1997, Assembly Bill (AB) 1484 established the Commission of Local Governance for the 21st
Century. The role of the Commission of Local Governance was to evaluate local government
organization and operational issues, develop a statewide vision, and determine how the State
should grow. The Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000 was
subsequently put in place and established procedures for local government changes of
organization. This SAP aims to identify and assess current and future public facilities owned,
operated, and/or maintained by IID for the provision of services as part of Imperial County
LAFCO’s Municipal Service Review process. Mitigation recommendations are incorporated in
the respective sections to offset any potential impacts to IID facilities or services.
Geographic Location, District Boundary and Service Areas
IID headquarters are located in southern California, approximately 120 miles east of San Diego
and just north of the U.S./Mexico International border in Imperial County. The district’s
1 The Cortese-Knox-Hertzberg (CKH) Local Government Reorganization Act of 2000 is Government Code §§ 56000 et seq. that
provides LAFCO with its authority, procedures and functions to “approve or disapprove with or without amendment, wholly,
partially or conditionally” proposals concerning the formation of cities and special districts, annexation or detachment of
territory to cities and special districts, and other changes in jurisdiction or organization of local government agencies.
IMPERIAL IRRIGATION DISTRICT
2
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
boundary was originally established in 1911 under the Irrigation District Law (California Water
Code Sections 20500 et. Seq.). As of 2025, IID’s legal district boundary is entirely contained
within Imperial County, but is not coterminous with Imperial County lines. IID provides raw
water services entirely within Imperial County while energy services extend into Riverside
County and into Borrego Springs in San Diego County (for emergency responses only). IID has
successfully provided electricity to service areas outside of its district boundaries since 1943
through independent service agreements.
The district’s legal boundaries were greatly influenced by the Boulder Canyon Project Act of
1928 and the Boulder Canyon Project Act Agreement of 1932, which together authorized and
orchestrated the construction of Hoover Dam and the All-American Canal. According to the
1932 Boulder Canyon Act Agreement between the United States Department of the Interior
and IID, changes in the district boundaries, beyond those authorized under the Agreement,
shall not be made unless approved by Congress. The district’s water service area is thus
defined by the limits authorized under the Boulder Canyon Project Act Agreement. Figure 1
identifies the legal boundaries of the Imperial Irrigation District as per record annexations
(inclusions into the district) and
Figure 2 that follows, reflects the water service area boundary (also known as the All-
American Canal Water Service Area) within Imperial County as authorized by the Secretary of
the Interior.2
In contrast, IID’s energy service area has been extended beyond the district boundaries and
Imperial County boundaries, pursuant to service contracts approved by California regulatory
authorities. These contracts include IID’s 1934 Compromise Agreement with CVWD and the
US Bureau of Reclamation, and the 1943 Purchase and Sale Agreement with California Electric
Power Company, the predecessor to Southern California Edison. The 1943 Purchase and Sale
Agreement has been modified and extended over the years by several Service Boundary
Agreements and was approved by the California Public Utilities Commission. Figure 3
identifies the IID energy service area.
In addition, IID was certified by the North American Electric Reliability Corporation (NERC) as
one of 34 Balancing Authorities in the Western United States. As a federally certified Balancing
Authority IID must ensure the reliability of the electric system within its geographical
boundaries by, among other requirements, maintaining a continual balance between electric
resources and electricity demands. IID is subject to the reliability, safety and security
regulations promulgated by the North American Electrical Reliability Corporation, an agent of
the Federal Energy Regulatory Commission (FERC) and enforced by the Western Electricity
Coordinating Council (WECC).
2 Figures 1, 2, and 3 are not to scale and are for assessment and planning purposes only.
IMPERIAL IRRIGATION DISTRICT
3
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
Figure 1 Imperial Irrigation District Boundary
IMPERIAL IRRIGATION DISTRICT
4
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
Figure 2 IID Water Service Area Boundary
IMPERIAL IRRIGATION DISTRICT
5
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
Figure 3 IID Energy Service Area
IMPERIAL IRRIGATION DISTRICT
6
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
In summary, the District’s water service area is determined by its congressionally authorized
district expansion limits while the energy service area is determined by contracts and both
state and federal regulatory authorities. For example, IID’s electrical service to the Coachella
Valley is governed by the 1934 Compromise Agreement with the Coachella Valley Water
District and the US Bureau of Reclamation, as well as the long-standing Service Boundary
Agreement with Southern California Edison, which were approved and sanctioned by federal
and state regulators. Further, IID’s energy service area is subject to the strict reliability, safety
and security standards promulgated and enforced by the Western Electricity Coordinating
Council and the Federal Energy Regulatory Commission. Finally, IID’s service areas for energy
utilities remain under the purview of the California Public Utilities Commission, and according
to California state law, IID’s service boundaries can only be modified with the concurrence of
IID.
Communities in Service Areas
IID covers an irrigation service area of 1,658 square miles and an energy service area of
6,471 square miles, which partially overlap. Communities that are provided with either raw
water services, or energy services, by IID are identified under Table I- 1 by county (continued
on the next page). Not all of the communities in Imperial County are within the water service
area and not all Riverside County communities are within the energy service area. Borrego
Springs (in San Diego County) only receives incidental IID energy services and is therefore
not reflected on the table.
Table I- 1 Communities within Service Areas
Imperial County Communities Raw Water Energy Service
Service
Bombay Beach CDP X
Brawley, City of X X
Calexico, City of X X
Calipatria, City of X X
Desert Shores CDP X
El Centro, City of X X
Heber CDP X X
Holtville, City of X X
Imperial, City of X X
Niland CDP X X
Ocotillo CDP X
IMPERIAL IRRIGATION DISTRICT
7
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
Imperial County Communities Raw Water Energy Service
Continued Service
Palo Verde CDP X
Salton City CDP X
Salton Sea Beach CDP X
Seeley CDP X X
Westmorland, City of X X
Winterhaven X
Riverside County Communities Raw Water Energy Service
Service
Bermuda Dunes, CDP X
Coachella, City of X
Desert Hot Springs, City of X
Indian Wells, City of (portion) X
Indio, City of X
Indio Hills, CDP X
La Quinta, City of X
Mecca CDP X
Palm Desert, City of (portion) X
Rancho Mirage, City of (portion) X
Sky Valley, CDP X
Thermal, CDP X
Thousand Palms CDP X
IID’s Sphere of Influence
The Cortese, Knox, Hertzberg Local Government Reorganization Act of 2000 requires the
LAFCO to determine and update the spheres of influence for all applicable jurisdictions
within the county. A sphere of influence is defined by Government Code §56076 as “a plan
for the probable physical boundary and service area of a local agency, as determined by the
commission.” Although Government Code §56425 governs LAFCO’s role in adopting and
updating sphere of influences, changes to IID service area would require congressional
action. According to state law and court precedent, Imperial County LAFCO has the exclusive
jurisdiction to conduct IID’s municipal service review. This is because IID’s legal district
boundaries are entirely within Imperial County and there are no agreements transferring
IMPERIAL IRRIGATION DISTRICT
8
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
jurisdiction from Imperial County LAFCO to other LAFCOs.
As of the date of this 2025 Service Area Plan, IID had no plans to expand its current water
service area, which is contained entirely within Imperial County, or to expand its energy
service area, which extends beyond Imperial County into Riverside and San Diego counties.
IID intends to continue providing quality, and economical water and energy service to all of
the areas it currently provides with those services. Imperial County LAFCO approved IID’s
sphere of influence, according to California Government Code §56076, in October 2020,
based on IID’s established service areas. The Imperial Irrigation District’s boundaries and
service areas are depicted in the previously introduced in Figure 2 and Figure 3.
Figure 2IID Procedures for Extending Water Service Outside of District Boundaries
The delivery of water to lands within the Imperial County must meet certain requirements.
Lands within the legal district boundaries are subject to an administrative process prior to
water delivery services. Lands outside the legal boundary of the district, but within the
authorized service area as described in IID’s 1932 Agreement with the Bureau of Reclamation,
may receive conserved water or file a petition for inclusion (annexation) into the district. All
annexations are at the discretion of the IID Board of Directors. The decision for annexation of
lands within the water service area is made by the IID Board of Directors based on a variety
of considerations such as water supply and demand, hydrology, access to irrigation and
drainage facilities, method of irrigation, and other limitations imposed by virtue of Section
206 of Public Law 100-6753 (“Protection of Existing Water Uses”). Any proposed legal district
boundary change would require further action from Imperial County LAFCO. The following is
a brief overview of water delivery service requirements under three distinct scenarios:
Scenario 1-Lands that are included within the legal district boundary
➢ Ensure water availability charges have been paid (annual per acre fee)
➢ Certificate of Ownership and Authorization Form is completed
➢ Associated capital costs are paid by the proponent
➢ Subject to IID Water Rules and Regulations
Scenario 2-Lands are outside the district boundary but within the AAC service area
➢ Option 1-Purchase conserved water from IID
➢ Option 2-File a petition with IID/LAFCO for inclusion (annexation) into the district,
then Scenario 1
Scenario 3-Lands are outside the district boundary, outside the AAC service area, but within
Imperial County
➢ Option 1-Purchase conserved water from IID
3 An Act to provide for the settlement of water rights claims, to authorize the lining of the All-American Canal, and
other purposes as detailed in the 1988 Settlement Agreement.
IMPERIAL IRRIGATION DISTRICT
9
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
➢ Option 2-Seek congressional authorization for expansion of district boundaries
beyond the limits established by the Secretary of the Interior in 1932
As noted above, lands that are unable, or unwilling, to be annexed into the district, but that
are located within Imperial County, may have an option to purchase conserved water from
IID. The transfer of wholesale conserved water outside of the district boundary is also at the
discretion of the IID Board and must meet a number of conditions, including but limited to:
1. Authorization by the State Water Resources Control Board
2. Environmental Compliance
3. Subject to the 2003 Quantification Settlement Agreement provisions4
As of the date of this Service Area Plan, there were no known, or likely, requests for water
service area extensions.
Restrictions on Extending Water Service Within District Boundaries to Federal Lands
The priority of water to federal lands within the IID water service area is restricted under the
1988 San Luis Rey Indian Water Rights Settlement Act. The federal legislation was passed
before the settlement agreement was developed. The United States, the Bands, and the Local
Entities have been unable to agree on a settlement implementing the 1988 Act due to
conflicting interpretations of the intent of the Act. Nonetheless, under SEC 206. PROTECTION
OF EXISTING WATER USES, the following is stated, thus requiring formal interpretation from
the respective federal agency authorizing the use of federal land subject to the water supply
inquiry.
“As of the effective date of this Act, any action of the Secretary to use, sell, grant, dispose,
lease or provide rights-of-way across Federal public domain lands located within the All-
American Canal Service Area shall include the following conditions:
(1) those lands within the boundary of the Imperial Irrigation District as of July 1, 1988, as
shown in Imperial Irrigation District Drawing 7534, excluding Federal lands without a history
of irrigation or other water using purposes;
(2) those lands within the Imperial Irrigation District Service Area as shown on General Map
of Imperial Irrigation District dated January 1988 (Imperial Irrigation District No. 27F 0189)
with a history of irrigation or other water using purposes; and
(3) those land within the Coachella Valley Water District's Improvement District No. 1 shall
have a priority for irrigation or other water using purposes over the lands benefiting from the
action of the Secretary . . . . .”
4 2003 QSA are a set of interrelated contracts that resolve certain disputes among the United States, the State of
California, IID, MWD, CVWD and SDCWA, for a period of 35 to 75 years, regarding the reasonable and beneficial use
of Colorado River water and the ability to conserve, transfer and acquire conserved Colorado River water.
IMPERIAL IRRIGATION DISTRICT
10
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
C. SERVICE AREA PLAN REQUIREMENTS
IID Service Area Plan Context
Service area plans support Imperial County LAFCO’s Municipal Service Review process, which
by state law occurs every five years. The 2019 IID Service Area Plan was the first service area
plan prepared by the Imperial Irrigation District for submission to Imperial County LAFCO,
making this 2025 SAP the first update.
Minimum Contents of Service Area Plans
The required contents of an up-to-date Service Area Plan are determined by Imperial County
LAFCO Guidelines and reviewed by the LAFCO for sufficiency. Per Government Code Section
56430, the LAFCO, in undertaking its periodic municipal service review, shall prepare a written
statement of its determinations with respect to each of the following requirements:
1. Growth and population projections for the affected area;
2. The location and characteristics of any disadvantaged unincorporated communities
within, or contiguous to, the sphere of influence;
3. Present and planned capacity of public facilities, adequacy of public services, and
infrastructure needs or deficiencies;
4. Financial ability of agencies to provide services;
5. Status of, and opportunities for, shared facilities;
6. Accountability for community service needs, including governmental structure and
operational efficiencies;
7. And any other matter related to effective or efficient service delivery, as required by
commission policy.
Role of the Imperial County Local Agency Formation Commission
The Imperial County LAFCO is charged with the review and approval of the IID Service Area
Plan. Imperial County LAFCO conducts this municipal service review because IID’s legal
boundaries are entirely within Imperial County and there are no agreements transferring
jurisdiction from Imperial County LAFCO to any other LAFCO.
D. ORGANIZATIONAL STRUCTURE OF SERVICE AREA PLAN
This Service Area Plan discusses the services provided by the Imperial Irrigation District,
identifies the service demands existing at the time of Plan’s preparation, and estimates the
future demand for such facilities and services. In doing so, it considers new planned, or
projected, development from local urban areas and increased agricultural water use demand.
An approximate 20-year planning period is used to forecast population growth, and the
IMPERIAL IRRIGATION DISTRICT
11
2025
SERVICE AREA PLAN INTRODUCTION & BACKGROUND
estimated facility and service demands are based on population projections in five-year
increments through 2040.
This Service Area Plan provides the information necessary for LAFCO to conduct a municipal
services review in compliance with Section 56430, and is organized into the following six
sections that satisfy the Guidelines adopted by the Imperial County LAFCO:
I. INTRODUCTION AND BACKGROUND: Provides a brief description of the Imperial
Irrigation District, Service Area Plan requirements, including the overall content of the
Service Area Plan presented herein.
II. EXECUTIVE SUMMARY: Provides an overview and summary of the service
assessments and conditions identified regarding existing facilities, demand,
mitigation, and costs.
III. GROWTH AND POPULATION PROJECTIONS/DEMAND: Provides a discussion on
existing and projected populations within the district’s service area and describes
potential impacts to agricultural water demand (agricultural land) associated with
population growth and projected transition of service demand.
IV. PUBLIC FACILITIES AND SERVICES: Provides a thorough description of existing and
planned IID facilities and services, their current and projected adequacy, and any
opportunities for shared facilities, or services, with other agencies. The following
facilities and services are included in the review:
A. Water Services and Facilities
B. Irrigation Drainage Services and Facilities
C. Energy Services and Facilities
D. Conservation Programs and Services
1. Water Conservation Programs
2. Energy Efficiency Programs
E. Administrative Services and Facilities
V. FINANCIAL PLAN: The financial section identifies and discusses existing and potential
future sources of revenue and financing mechanisms for public facilities and services
that may be available to the Imperial Irrigation District.
A. Existing Revenue Sources
B. Current Facility Financing & Recommendations
C. Potential Additional Revenue Sources for Capital Needs
IMPERIAL IRRIGATION DISTRICT
12
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
II. EXECUTIVE SUMMARY
This Service Area Plan illustrates IID’s long-term strategic objectives consistent with other IID
adopted plans. A number of uncertainties facing the IID in the next several years are mitigated,
within limitations. These external issues include, but are not limited to 1) the protection of water
rights held in trust for water uses within the district; 2) the increasing use of efficiency-based
water conservation measures ; 3) compliance with state and federal water quality programs; 4)
future hydrologic water supply conditions and federal Colorado River operational guideline
changes 5) the emerging and changing State and Federal mandates impacting renewable energy
portfolio standards and emission reduction targets; 6) significant high-voltage electric
transmission development to augment the export of locally produced renewable resources; 7)
regulatory and reliability compliance requirements from energy oversight agencies; and 8) the
1934 Agreement of Compromise between IID and Coachella Valley [County] Water District
contains provisions anticipating a 99 year lease of hydroelectric opportunities on the All-American
Canal which are scheduled to sunset on January 1, 2033. The full 1934 Agreement of Compromise
will remain in place.
The remaining term of the Agreement of Compromise raises a number of uncertainties that may
be evolving during the next ten-year planning period. A study was commissioned in 2022 by
Imperial County LAFCO and Riverside County LAFCO for an analysis regarding the potential for
alternative electrical service governance structures for the Coachella Valley territory.5 The
formation of a Joint Powers Authority took place in 2025 composed of the city of La Quinta, city
of Indio and county of Riverside. It is anticipated that an IID-CVPA Cooperation Agreement will be
developed to detail how the District may support or interface with the newly formed JPA.
A. AREA GROWTH SUMMARY
The population and growth projections presented herein provide a context for the analysis
and findings introduced for each individual public service facility in terms of the performance
standard, inventory of existing facilities, existing service demand versus projected future
demand, adequacy and mitigation. Per the Department of Finance data, it is estimated that
the 2025 population in Imperial County is 185,550, while the service area population in the
Coachella Valley communities within Riverside County, that are currently served, is estimated
at 249,560 for 2025 (adjusted for partially served communities using DOF and US Census Data
population estimates). The following Table EX- 1 displays the projected population of Imperial
Irrigation District’s service areas through Year 2040, in five-year increments.
5 “Alternative Governance Structures and Alternative Electricity Service Provisions: Imperial Irrigation District,”
sponsored by the California State Water Resources Control Board, specifically to IID’s extended electrical service
territory in the Coachella Valley. State Grant Agreement No. D2118003. For a copy of the most current report, see
https://www.iclafco.com/projects/iid.
IMPERIAL IRRIGATION DISTRICT
13
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Table EX- 1 Service Area Population Projections
Year Imperial County Coachella Valley Total Service Area
Projected Projected Projected Population
Population Population
2025 185,550 249,560 437,135
2030 193,326 250,937 446,293
2035 199,157 252,623 453,815
2040 203,470 254,217 459,727
Source: Department of Finance Estimated and projected Population for Imperial County, May 2025; and for
Riverside select communities, using the Department of Finance growth rate for Riverside County as a whole was
applied to the 2020 baseline population as presented by Census Dots using Census Data for unincorporated areas
that have no DOF projections.
This Service Area Plan uses population and growth projections for the region based on
Department of Finance projections growth rates. This was an adjustment from the previous
service area plan under which more aggressive numbers tied to the Imperial Regional Water
Management Plan had been applied and are no longer representative of the growth demand.
Population does peak in the winter months in Imperial Valley due to a modest influx of winter
visitors. The population variation is much steeper in the Coachella Valley. Population projection
estimates in the Coachella Valley communities apply the DOF established growth rate which
ranges from .35% to .67% for five-year intervals. The Coachella Valley’s population, as a whole,
tends to fluctuate aggressively, reaching over 500,000 (valley-wide) briefly during select winter
months and balancing around 300,000 during the summer months. Energy demand projections
allow for these flexibilities.
In brief, the projected raw water demand for agricultural use in the Imperial Valley is
projected to remain the same unless there is substantial permanent irrigated land retirement
as a result of planned land use changes (conversion of farmland to urban use). Non-
agricultural water demands are anticipated to increase over the planning period, consistent
with population projections and an unpredictable new demand tied to increased interest in
geothermal and lithium development in the Imperial Valley.
Conversely, the projected energy demand to meet population and commercial/industrial
growth is expected to grow substantially, particularly in the Coachella Valley service areas,
but consistent with the population projects. Non-residential energy demand in both service
areas is anticipated to be offset by the very same, and aforementioned, energy generation
facilities and new solar development.
B. SUMMARY OF FINDINGS
The service review findings in this Service Area Plan are based on information obtained from
existing IID reports and adopted plans, adopted budgets, annual reports, and verifications
IMPERIAL IRRIGATION DISTRICT
14
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
through IID staff. IID facilities and services reviewed include: water facilities, drainage
facilities, power facilities, conservation/efficiency programs and services and administrative
facilities. Findings for each facility and/or service are summarized in the proceeding tables
and introduced by a respective, brief narrative. The tables in this section summarize the
relevant performance standard for the desired level of service and a description of the
corresponding facilities’ assessment to meet current and future demands.
Irrigation Water Supply, Storage and Conveyance Facilities
IID’s sole source of water is Colorado River water. The District’s annual consumptive use is
capped at 3.1 million acre-feet per year (MAFY) during the term of the 2003 Quantification
Settlement Agreement (QSA). Of that water supply 2.6 MAFY is allocated to IID under present
perfected rights. These PPR’s are entitlements essentially established under state law, and
have priority over later contract entitlements. Under the QSA IID voluntarily transfers close
to 500,000 AFY of Colorado River water conserved for the benefit of urban areas participating
under the QSA. The QSA was enacted in 2003 as the nation’s largest agriculture-to-urban
water conservation and voluntary transfer program between the Secretary of Interior,
Imperial Irrigation District, Coachella Valley Water District (CVWD), The Metropolitan Water
District of Southern California (MWD), San Diego County Water Authority (SDCWA) and other
affected parties. Please see Water Conservation Programs and Services for more information.
IID owned water conveyance and operational storage facilities are all located within the
County of Imperial and are reviewed in context with IID’s water distribution system which is
entirely gravity flow. These facilities include reservoirs, irrigation canals, laterals, intertie
systems, pipelines, and flow equipment that convey and measure raw water for irrigation to
agricultural operations, rural residences, municipalities and water districts and/or water
companies for treatment to potable water users and businesses within the service area.
Water facilities also include SCADA control systems and system equipment necessary for the
efficient operation and conveyance of water. These water services are managed and operated
by the IID Water Department with the goal of meeting the established performance standards
within IID’s consumptive use of 2.6 MAFY.
All operational water storage facilities within IID are intended for water management and
regulating purposes. The District does not own any long-term water storage facilities,
however, under the current guidelines6, the total amount of Efficiency Conservation
Intentionally Created Surplus that IID may store within its Lake Mead ICS account in any year
is maximized for an annual creation of 25,000 AF and a cumulative limit of 50,000 AF total.
IID also makes use of conserved water storage agreements through other partner agencies.
The total IID ICS storage balance at the end of 2023 was 340,472 AF.
6 The 2007 Guidelines are under review as they are set to expire in December 2025 for planned implementation
through 2026.
IMPERIAL IRRIGATION DISTRICT
15
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Irrigation Water Facilities
Performance Standard* Consumptive Use: 2.6 MAFY
Agricultural water supply: 5.1 AFY/Acre
Non-Ag water supply: .50 AFY/Acre
Operational Water Storage: 7,750 AF Goal
Existing Facilities (2024) Water distribution canals: 1,668 Miles
Operational reservoirs: 4,665 AF
Farm delivery gates: 4,790
Non-Ag delivery gates: 336
Canal/Lateral controls: 470
Automated systems: 300+
Mobile metering: 17
Existing Demand (2024) Total Consumptive Use: 2.6 MAF/Year
• Agricultural water demand: 2.2 MAF/Year on Average
• Non-Ag water demand: 97,000 AF/Year on Average
• All other water delivery:* 285,000 AF/Year on Average
Total conservation for transfer purposes: 477,200 AF
Adequacy 2024: Sufficient
Future Demand 2030: 2.6 MAFY in-valley/487 KAF for transfer purposes
2040: 2.6 MAFY in-valley/487 KAF for transfer purposes
Mitigation Continue to protect Colorado River water rights held in trust
for IID water uses within the district.
Funding Sources Current funding – Water sales and water transfer revenues
Future funding – Water sales and water transfer revenues;
grant funding, as available.
2025 Budget $88.3 million for water operation and maintenance
$39.6 million for water capital projects
(Excludes Drainage & Water Transfer Projects)
* Water uses for environmental, recreational, canal seepage, operational discharge, mitigation, evaporation, and
miscellaneous uses are included as Other Operational Demand. Table does not include conserved water volumes
created for water transfer purposes. Please see Water Conservation Section.
IMPERIAL IRRIGATION DISTRICT
16
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Irrigation Drainage Facilities & Services
IID operates a comprehensive irrigation drainage collection system with the primary purpose
of transporting water from agricultural irrigated lands in Imperial Valley into the Salton Sea.
IID drainage facilities include facilities that convey agricultural discharges from the fields to
the Alamo River, the New River or directly to the Salton Sea. IID drains, as a matter of
necessity, also collect treated wastewater discharge, and surface runoff from non-agricultural
uses. Although municipalities and other point source dischargers are allowed to discharge into
IID’s drain facilities, the IID drainage system is not intended to, nor designed to, collect or
convey, urban or stormwater runoff. IID drainage facilities may include pumps when
necessary due to drain elevations and/or depth challenges in order to maintain obligations to
growers. These drainage facilities are managed and operated by the IID Water Department.
Drainage Facilities
Performance Standard IID Design Guidelines, NPDES requirements, IID discharge
requirements and any FEMA requirements.
Existing Facilities (2024) All-American Drains: 50 Miles
Drains (Earthen): 1,296 Miles
Drains (Concrete Lined): 1 Mile
Drains (Piped): 109 Miles
Existing Demand (2024) Capacity: Capacity to receive irrigation run-off
Quality: Operational and regulatory monitoring
Adequacy Capacity: Sufficient capacity to receive irrigation run-off
Quality: Ag Waiver Under Board Order R7-2021-0050-03
Monitoring of Total Suspended Solids (main drains):
• Eight of 16 drain sites achieved TSS goal
Future Demand Capacity: Consistent capacity to receive irrigation run-off
Quality: Final sediment TMDL numeric target of 200 mg/L
Total Suspended Solids (TSS) goal of 200 mg/l
Mitigation Continual monitoring, implementation of Best
Management Practices and nine (9) drainage quality
mitigation measures recommended.
Funding Sources Current: Water sales/Drainage fees
Future: Water sales/Drainage service fees
2025 Budget $2 million for capital costs for drains
IMPERIAL IRRIGATION DISTRICT
17
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Power Facilities & Services
IID power facilities and services cover the entire Imperial County and extend into portions of
the Coachella Valley in Riverside County and eastern portions of San Diego County (as an
emergency response operation). Power facilities include generation facilities, energy storage
facilities and energy transmission and distribution lines. Since IID is not a member of the
California Independent System Operator (CAISO) as a Balancing Authority, IID must be able to
provide reliable energy services even during extreme events and is regulated by the Western
Electricity Coordinating Council (WECC). The operation and management of power facilities
and services are all under the IID’s Power Department.
Power Facilities & Services
Performance Standard IID must match generation to load as a Balancing Authority.
Existing Facilities (2024) Generation Facilities 2,782,250 MWh
Generation Facilities from Power Purchase 1,116,175 MWh
Energy storage facilities: 60 MW/140MWh
Energy transmission lines: Over 1,800 Miles
Substations: 128
Distribution lines: Over 4,400 miles of overhead lines
(Primary) Over 1,700 miles of underground lines
Existing Demand (2024)* 2024 Annual Demand 3,755,413 MWh
Peak Load 1,152 MW
Adequacy Sufficient: Resources to cover load plus reserve
Future Demand* 2030 Annual Mid Energy Demand 4,306 GWh
1-in-10 Mid Peak Load 1,229 MW
2035 Annual Mid Energy Demand 4,412 GWh
1-in-10 Mid Peak Load 1,268 MW
2040 Annual Mid Energy Demand 4,567 GWh
1-in-10 Mid Peak Load 1,309 MW
Mitigation Continued implementation of the Energy Integrated Resource
Plan and corresponding recommendations.
Funding Sources Current: Energy sales Future: Energy sales
2025 Budget $602.9 million for power operation and maintenance
$126.5 million for power capital projects
* Demand and projected data are from the 2024 Integrated Resource Plan and IID Power Department staff contact.
IMPERIAL IRRIGATION DISTRICT
18
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Conservation Programs and Services
IID is responsible for implementing both water and energy efficiency/conservation efforts. IID
is located at the heart of many available natural resources to develop renewable generation
facilities as well as energy efficiency and conservation but has only one source for its water
supply, the Colorado River. Consequently, water conservation is key to meeting local water
supply demand for new growth. Summarized findings are independently presented for water
conservation and energy efficiency as follows:
Water Conservation - As a party to the QSA, the nation’s largest agriculture-to-urban water
conservation and transfer agreement, IID is implementing numerous efficiency-based
conservation programs to create just under 500,000 AFY of conserved water (from 2003
baseline numbers). IID adopts and implements a Water Conservation Plan (2021) that outlines
its water use and conservation programs used to meet the district’s water transfer
commitments and obligations. Water conservation projects and programs are managed by
the IID Water Department via system conservation and with the District’s agricultural partners
via on-farm-efficiency water conservation.
The Colorado River Basin is entering its third decade of drought. In June 2022, the Department
of the Interior called for the Basin states to develop a plan before the end of the year to reduce
demands by 2-4 million acre-feet per year, through 2026, or the Secretary of the Interior
would take regulatory action to force these reductions in order to protect the Colorado River
system. California Colorado River contractors submitted a voluntary conservation proposal to
Reclamation to conserve up to 400,000 AFY through 2026 as the State’s commitment to Lake
Mead and the Colorado River System. IID entered into a System Conservation Implementation
Agreement in 2024 for its share of the California proposal under a voluntary plan for a not to
exceed conservation volume of 250,000 AFY (through 2026). This amount would be over and
above IID’s existing QSA water transfer obligations.
Other factors to consider during the SAP five-year planning period include anticipated
changes to the 2007 Colorado River Interim Guidelines for the Lower Basin Shortages and
Coordinated Operations for Lake Powel and Lake Mead which are set to expire at the end of
2025, for 2026 water year implementation. The post 2026 operating conditions are not
expected to be finalized any earlier than summer of 2026 and are anticipated to affect all
Colorado River users during times of shortage. IID’s water entitlement is significant at 3.1
MAFY, of which 2.6 MAFY are present perfected rights. These vested rights are not subject to
reclamation law limitations and in times of shortage, PPRs must be satisfied first. IID is
working diligently with federal agencies and Colorado River contractors to minimize impacts
to the local community while simultaneously ramping up water conservation programs in an
effort to augment local water supplies and meaningfully contribute to the protection of the
Colorado River System. The following table provides a summary of those efforts.
IMPERIAL IRRIGATION DISTRICT
19
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Water Conservation & Efficiency Programs/Services
Performance Standard Water Conservation Target: 482,200 – 487,200 AFY
Maintaining agricultural production with increased water use
efficiencies that require less water than totals in history. Water
conservation volumes shall further be consistent with the targets
under the Quantification Settlement Agreement and any other
System Conservation Implementation Agreements entered into
between IID and Reclamation7.
Existing Programs (2024) Water Use Efficiency Programs
• On-Farm Water Conservation Programs
• Deficit Irrigation Program
• System Conservation Projects & Programs
Renewable Energy Water Efficiency Program Standards
Urban Water Use Efficiency Program Standards
Existing Demand (2024) 2024: 477,200 AFY of conservation water
250,000 AFY or less for SCIA Implementation
Adequacy 2024 Conservation Yield: Sufficient
2025: 482,200 AFY of conserved water
Future QSA Demand
2030: 487,200 AFY of conserved water
2035: 487,200 AFY of conserved water
2025: Up to 250,000 AFY of conserved water
Future SCIA Demand8
2026: Up to 250,000 AFY of conserved water
Mitigation Continue to implement IID’s Water Conservation Plan.
Continue to implement SCIA approved efficiency programs.
Funding Sources Water transfer revenues; Federal grant funding
2025 Budget $98.3 million for O&M for water transfer projects
$20.9 million for capital projects for water conservation
7 Conservation targets included in the suite of QSA Agreements include the 1988 IID/MWD Transfer, IID/SDCWA Transfer,
IID/CVWD Transfer, the All-American Canal Lining Project as well as the satisfaction of Miscellaneous PPR’s. Amounts are
independent of increases and reductions in conformance with the Intentional Overrun and Payback Policy and Intentionally
Created Surplus program.
8 2024 System Conservation Implementation Agreement for Calendar Year 2024 Through 2026 Between the Unites States Bureau
of Reclamation and the Imperial Irrigation District to Implement the Lower Colorado River Basin System Conservation and
Efficiency Program.
IMPERIAL IRRIGATION DISTRICT
20
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Energy Efficiency- IID implements a comprehensive energy conservation portfolio consistent
with AB 2021 and SB 350 including new measures under SB100 for greenhouse gas emission
reductions. Energy efficiency standards are detailed under the most recently adopted 2024
Integrated Resource Plan and programs are managed under the IID’s Power Department.
Energy Conservation & Efficiency Programs/Services
Performance Standard Energy Efficiency Savings 26,960 MWh by 2030
Renewable Energy Portfolio to reach 60% by 2030
Emission Reductions of 40% below 1990 Levels (7% for IID)
Existing Programs (2024) Energy Efficiency Programs
• Residential Programs (4)
• Commercial Programs (3)
Renewable Energy Programs
• Green Energy Rate Program
• Net Energy Metering Program
• Net Billing Program
• Feed-In Tariff Program
Emission Reductions Program (E-Green Program)
Existing Demand (2024) 2024 Efficiency Savings: 38,693 MWh target
2024 Renewable: 44% target
2024 Emission Reduction: 5 24,000-667,000 metric tons
Efficiency Savings (2019-21): 35,000 MWh Low Satisfactory
Adequacy
Renewable (2023): 41% Satisfactory
Emission Allowance: 1,200,000 mt Above Satisfactory
Future Demand 2025 Efficiency: 37,997 MWh target
2030 Efficiency: 26,960 MWh target
2025 Renewable: 52% target
2030 Renewable: 60% target
2025 Emission Reduction: 40% Below 1990 levels
2030 Emission Reduction: 5 0 % to 60% Below 1990 levels
Mitigation Continue to implement the adopted Integrated Resource Plan and
adopted programs.
Funding Sources Current funding – Energy sales
Future funding- Energy sales; grant funding
2025 Budget $ 94.7 million for renewable requirements
$10.7 million for efficiency programs
IMPERIAL IRRIGATION DISTRICT
21
2025
SERVICE AREA PLAN EXECUTIVE SUMMARY
Administrative Facilities & Services
Administrative facilities include buildings that house administrative and general service staff
and that provide internal support services and general services to IID clients, governmental
affairs and the business community, as well as the water and power departments. Five IID
departments oversee and deliver administrative services as follows: Executive Department,
General Services Department, Information Technology (IT) Department, Finance Department,
and Human Resources Department.
Administrative Facilities
Performance Standard .75 Admin FTE/1,000 in population served
450 SF of building space/1,000 in population served
125 SF of office space per FTE
Existing Facilities Executive Department 14,375 SF
General Services Department 25,465 SF
Information Technology Department 25,486 SF
Finance Department 16,195 SF
Human Resources Department 15,934 SF
Subtotal 97,455 SF
Common Areas (Exclusively Admin) 93,987 SF
TOTAL ADMIN AREAS 191,442 SF
Existing Demand 2024 FTE: 315 Admin FTE (420 in population/.75)
2024 Space: 191,442 SF (418,833 in population)
Adequacy 2024 Admin FTE: 401 Meets/Exceeds Demand
2024 Admin Area: 180,450 SF Meets Demand
Future Demand 2030: 438 Admin FTE and 262,917 SF of space
2040: 546 Admin FTE and 328,063 SF of space
Mitigation By 2030, 71,475 SF of additional admin space may be
needed or the conversion of shared common areas.
Funding Sources Current: Water and Power Department revenues
Future: Water and Power Department revenues
2025 Budget $100 million for Operation Expenditures
IMPERIAL IRRIGATION DISTRICT
22
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
III. GROWTH AND POPULATION PROJECTIONS
IID operations consist of two primary departments, the Water Department and the Power
Department with additional support services. Future water service demand will be determined by
existing water transfer agreements (including any voluntary water conservation agreements with
Reclamation for the benefit of Lake Mead), trends in the Imperial Valley farming community,
industrial development in the geothermal industry and the level of urban growth that will reduce
acreage of irrigated farmland. Energy service demand will largely be determined by population
growth and economic trends in the Imperial Valley and the Coachella Valley and the pace of
industrial growth. Both the water and energy service sectors are poised to greatly benefit from
aggressive efficiency and conservation efforts to offset some of the projected growth demands.
IID intends to continue to serve agricultural operations in the Imperial Valley and support the
orderly growth and development of urban areas throughout its respective water and energy
service areas in both counties. It is the IID’s intent to encourage cities and the respective counties
to plan for growth in a sustainable and orderly manner. Collaborative development will enable IID
to adequately plan for infrastructure improvements, phase service expansion consistent with the
jurisdictions anticipated growth, while sustaining the historical agricultural demand and meeting
outstanding commitments. This section of the Service Area Plan provides an overview of the
district’s irrigation characteristics in Imperial County and identifies the anticipated population and
economic growth throughout its principal two-county service area, both of which are critical
factors on how the IID will adequately serve the communities with water and/or energy services.
A. REGIONAL SETTING AND CHARACTERISTICS
Regional Setting
IID water service area is primarily in the Imperial Valley, entirely within the boundaries of the
County of Imperial, but the district’s energy services extend into the Coachella Valley and
eastern section of Riverside County. Limited forms of energy service are also provided to San
Diego County. The Imperial Valley and Coachella Valley have a strong agricultural economy.
Although this region is naturally a desert, with high temperatures and low average rainfall of
less than three inches (75 mm) annually, the economy has a rich history based on agriculture
production due to irrigation. Imperial Valley’s water supply is wholly from the Colorado River.
Colorado River water is channeled through the All-American Canal and Coachella Canal.
IID Water Department maintains an annual inventory of areas receiving water. As of 2023, an
estimated 520,347 acres are serviced by IID with irrigation water in Imperial County. IID does
not provide irrigation water services outside of Imperial County. The district’s 2023 Annual
Inventory of Areas Receiving Water indicated that the total net area irrigated for crops was
447,798. Another 23,594 were farmable acres, but temporarily out of production (fallowed
IMPERIAL IRRIGATION DISTRICT
23
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
or under a temporary fallowing program), while an additional 48,955 acres received irrigation
water for rural home sites, feed lots, solar and industrial areas as well as municipal uses.
The Imperial County Agricultural Commissioner’s Office estimated the county’s agricultural
production value in 2023 was $2.8 billion9. Vegetable and Melon Crops were the single largest
production category by dollar value ($1.2 billion), comprising 43% of the county total. Three
products dominated this category: leaf lettuce ($141 million), broccoli ($93 million), and head
lettuce ($216 million). At 30%, Livestock represented the second largest category ($821
million) and consisted mostly of feedlot cattle ($477 million). Field Crops ranked third at $467
million and 17%. Together, these three super categories accounted for 90% of the county's
direct farm production values. Agricultural customer water deliveries were at 2,149,900 AF in
2023 per the Provisional Water Balance Report10 and the District reported a total consumptive
water use for all customers of 2,437,024 AF for the same calendar year.
Approximately 61 percent of the 163,807 electric customer accounts served by the IID were
outside of Imperial County and in the Riverside County energy service area. Coachella Valley
communities served by IID include the cities of Coachella, Desert Hot Springs, Indio and La
Quinta, and portions of the cities of Palm Desert, Rancho Mirage and Indian Wells. There are
also a number of unincorporated areas in Riverside County that receive energy services from
IID as well as Borrego Springs and some isolated home-sites in east San Diego County (during
storm events as emergency response). The dynamics of the Power Department are largely
driven by new growth and development demand coupled with aging infrastructure in both
counties while the dynamics in the Water Department are largely driven by water transfer
agreements and urban growth in the Imperial Valley.
Population History
The Imperial County population discussed herein encompasses the entire water service area,
and includes all of the cities in Imperial County and all of the unincorporated communities
under the jurisdiction of Imperial County. Riverside County population data is restricted to
the communities (incorporated and un-incorporated) that are within the energy service area
boundaries (as delineated in Figure 3 of this SAP), specifically Coachella, Indio, La Quinta,
Mecca, Thousand Palms, Thermal and small portions of Indian Wells, Palm Desert, and Rancho
Mirage. Based on population data available from the California Department of Finance and
the US Census Bureau, the Imperial County and service area communities in Riverside County
have experienced moderate population growth since the 1980s with the Riverside County
communities experiencing aggressive growth between 2000 and 2010 that has tapered during
the last decade for the Coachella Valley and experienced a slight drop in Imperial Valley. The
2023 service area population in Imperial County was estimated at 179,790, while the service
9 As per the 2017 Crop and Livestock Report.
10 WISKI Provisional Water Balance Report run 3/25/24.
IMPERIAL IRRIGATION DISTRICT
24
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
area population (actively served by IID) in the Coachella Valley communities within Riverside
County is estimated at 240,988 as denoted in Figure 4.
Figure 4-IID Service Population
Population History for IID Service Areas by County
300,000
250,000
200,000
150,000
100,000
50,000
0
1980 1990 2000 2010 2018 2023
Imperial County Riverside County Service Area Communities
Source: Department of Finance for incorporated communities and US Census for Census Designated Places.
Disadvantaged Unincorporated Communities
Government Code Section 56430 (a) (2) requires the identification of location and
characteristics of any disadvantaged unincorporated communities within, or contiguous to, a
sphere of influence. The capacity and adequacy of infrastructure, public facilities, and public
services must be identified for disadvantaged unincorporated communities, which are
defined as areas of inhabited territory located within an unincorporated area of a county in
which the annual median household income is less than 80 percent of the statewide area
median household income.
According to the California Department of Housing and Community Development (HCD),11the
Statewide area median income in 2023 was $91,550 and thus the disadvantaged household
income was $73,240 or less for 2023. There are approximately thirteen disadvantaged
unincorporated communities within the IID water and energy service area boundaries that
fall within this definition. The communities of Heber, Niland and Seeley are the only
disadvantaged unincorporated communities located within the district boundaries. Table G-
1 identifies all of the unincorporated disadvantaged communities within the IID water and
energy service areas and their most current economic statistic regarding poverty level for all
unincorporated, Census Designated Place (CDP) identified under the American Community
Five-Year Survey.
11 Department of Housing and Economic Development, Income Limits 2023 (ca.gov)
IMPERIAL IRRIGATION DISTRICT
25
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
Table G- 1 Disadvantaged Communities within Service Areas
Imperial County Poverty Water Service Energy
Unincorporated Community Level Area Service Area
Bombay Beach CDP 69.4% X
Desert Shores CDP 21.4% X
Heber CDP 16.1% X X
Niland CDP 50.3% X X
Ocotillo CDP 43.8% X
Palo Verde CDP NA* X
Salton City CDP 12.2% X
Salton Sea Beach CDP 62.0% X
Seeley CDP 22.2% X X
Winterhaven, CDP 73.6% X
Riverside County Poverty Water Service Energy Service
Unincorporated Community Level Area Area
Mecca CDP 15.3% X
Thermal CDP 23.1% X
Thousand Palms CDP 13.1% X
Source: US Census, American Community Survey, 5-Year Estimates, Quick Facts/July 2023 Percentage
of Persons in Poverty.
* Palo Verde community data for population in poverty is not available.
The percentage of the population living in poverty in Imperial County is one of the highest in
the state of California and has remained constant over the last four decades. According to the
US Census Bureau, Imperial County had a 1990 poverty rate of 23.8 percent, a 2000 poverty
rate of 22.6 percent and a 2010 poverty rate of 23 percent. According to the 2023 US Census
Quick Facts, the most recent statistics show the County of Imperial at a 21.2 percent poverty
rate. The State of California poverty rate was 11.5 percent for the same report period.
Although statistics for Riverside County as a whole are not applicable given the limited area
served in 2023 by IID, two of the unincorporated communities in Riverside County far
exceeded the State poverty rate as noted in Table G-1.
IID offers Financial Assistance Programs through the Power Department that are income-
qualified assistance programs for economically disadvantaged households designed to help
customers meet their energy needs. Rate discounts are offered to income-qualified
customers and a special rate is offered for those using critical medical equipment or who were
affected by the COVID-19 epidemic. A financial assistance program is offered to customers
facing financial crisis that are at risk of disconnection for nonpayment. For rural residents that
are enrolled under the Energy Financial Assistance Programs, eligibility for potable water
services (bulk or bottled water from qualified agency) may also be arranged through the
Water Department. This assistance is provided for alternative potable water services for
IMPERIAL IRRIGATION DISTRICT
26
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
drinking and cooking for residents in the IID water serve area who do not receive treated
water. This is done in order to avoid water disconnect and to ensure IID maintains compliance
with Environmental Health Services requirements, as administered through the California
Department of Public Health12(CDPH).
B. GROWTH PROJECTIONS
It is projected that future population growth will largely occur within the unincorporated areas
via annexations by local municipalities given the limited opportunities available for infill
development in most cities within Imperial County and Riverside County Service Areas. Other
factors that affect service demand include economic stagnation caused by inflation and
California’s ongoing out-migration. This chapter provides an overview of population projections
as well as growth projections adjusting service demand from other factors to project water
demand and energy service demand.
1. Population Projections for Service Demand
a) Imperial County Population Growth Projections
The Department of Finance (DOF) has prepared population projections for the County
of Imperial. DOF estimates the Imperial County 2025 population of 185,550 and
expected to reach 203,470 by 2040. Adjustments have been made to Imperial County
population projections communicated under the 2020 Service Area Plan and carried
over for 2025 through 2040. The population projections noted on Table G- 2, are
reflective of the most current Department of Finance data for Imperial County.
Table G- 2 Imperial Region Population Projections
Year Imperial County Projected Population
2025 185,550
2030 193,326
2035 199,157
2040 203,470
Source: Department of Finance, May 2025.
b) Riverside County Population Growth Projections
Population projections in the Riverside County service area are limited to the
communities of Coachella, Desert Hot Springs, Indio and La Quinta, including portions
of the cities of Palm Desert, Rancho Mirage and Indian Wells, consistent with the
12 IID strictly enforces enrollment with an alternative potable water service purveyor. IID maintains a compliance database and
provides an annual update to CDPH.
IMPERIAL IRRIGATION DISTRICT
27
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
district’s energy service territory. The following unincorporated communities are also
included: Bermuda Dunes, Indio Hills, Mecca, Sky valley, Thermal and Thousand
Palms. These areas represent an estimated population of 249,560 in 2025 which is
projected to reach 254,217 by 2040. The population projections noted on Table G- 3
use the annual average growth history rate ranging from .35% to .67% percent,
applied to five-year periods consistent with county-wide growth rates used by DOF
for Riverside county.
Table G- 3 Coachella Valley Region Population Projections
Riverside County Coachella Valley Energy
Year
Projected Population Service Area Population
2025 2,464,950 249,560
2030 2,533,895 250,937
2035 2,620,176 252,623
2040 2,703,895 254,217
Source: Department of Finance, May 2025 for County-wide population and incorporated cities and
Census Dot for unincorporated areas using ACS source and applying the following five-year period
growth rates: 2020-2025 at .35%, 2026-2030 at .55%, 2031-2035 at .67%, 2036-2040 .63%. .
c) Total Service Area Population Growth Projections
The combined population growth projections for both service regions is displayed in
Table G- 4. Population affecting water demand is applicable only in Imperial County,
while population affecting energy demand encompasses both the Imperial County
region and the Coachella Valley Region in Riverside County.
Table G- 4 Service Area Populations
Imperial County Coachella Valley Total Service Area
Year
Projected Water/Energy Projected Energy Projected Population
Service Population Service Population for Power
2025 185,550 249,560 437,135
2030 193,326 250,937 446,293
2035 199,157 252,623 453,815
2040 203,470 254,217 459,727
Source: For Imperial County, 2012 Imperial Integrated Regional Water Management Plan and for Riverside County
Communities, the Department of Finance twenty-eight-year annual average growth history rate of 2.7 percent
(based on the population history for the specified communities as a whole, 2018).
IMPERIAL IRRIGATION DISTRICT
28
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
2. Growth Projections and Impacts on Service Demand
As previously noted, population projections are not the only factors affecting water
service demand and energy service demand. Agricultural intensity affects water service
demand, but may have little impact on energy demand. Non-residential/Non-agricultural
land uses resulting from urban sprawl (e.g. industrial development) may result in a decline
for water demand, but may result in an increased demand for energy services or
transmission facilities when tied to the renewable energy industry.
a) Water Demand Projections
Non-Agricultural Water Demand- Approximately 96 percent of all IID water demand
is from agricultural land uses with the remaining four percent serving non-agricultural
land uses. Non-agricultural uses include municipal, industrial, feedlots/dairies,
environmental resources, recreation, rural service pipes and other non-agricultural
uses. Industrial demand includes lithium, geothermal, including solar, energy
production. The aforementioned population growth projections for the Imperial
County contribute to the non-agricultural water demand projections by an estimated
28 percent. Riverside County has no demand on water services from IID.
Future agricultural water service demand will vary from current service demand as a
result of changes in economic, land use, and hydrologic conditions. Trends over
history show agricultural land conversion to urban uses, often results in less irrigated
crop land in production. Cities with potential, permanent agricultural land
conversions in Imperial County include Imperial, Brawley, Calexico, Holtville and El
Centro. This conversion generally results in a decreased irrigation water demand in
Imperial County since agricultural operations used an average of 5.1 AF Water/Acre
annually (prior to implementation of water conservation programs) while municipal
uses use an average of 0.50 AF Water/Acre annually.
Imperial Valley 2015 and forecasted 2020 to 2055, non-agricultural water demands
were projected under the adopted Imperial Integrated Regional Water Management
Plan (IRWMP) in 2012 and continue to be adequate. These water demand projections
are applied in Water Supply Assessments for new development projects in Imperial
Valley and applied consistently throughout this Service Area Plan.
Table G- 5 provides the 2015 and 2020 non-agricultural water use history and 2025-
2040 projected water demand in five-year increments, without conservation efforts
which are discussed under the Conservation Chapter of this Service Area Plan. Total
water demand for non-agricultural uses is projected to be 165.7 KAF in the year 2040.
This is a forecasted increase in the use of non-agricultural water from 58.3 KAF from
2015 to 2055, despite the nominal 7.7 KAF increase documented over the five-year
period between 2015 and 2020.
IMPERIAL IRRIGATION DISTRICT
29
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
Table G- 5 Non-Agricultural Water Demand Projections
2015 2020 2025 2030 2035 2040
Water Use
KAFY KAFY KAFY KAFY KAFY KAFY
Municipal 30.0 30.9 36.8 39.8 41.5 46.3
Industrial 26.4 28.7 39.8 46.5 53.2 59.9
Other 5.5 5.5 5.5 5.5 5.5 5.5
Feedlots/Dairies 17.8 19.0 20.0 20.0 20.0 20.0
Environmental Resources 8.3 9.5 12.0 12.0 12.0 12.0
Recreation 7.4 9.5 10.0 10.0 10.0 10.0
Service Pipes 12.0 12.0 12.0 12.0 12.0 12.0
Total Non Ag Water Demand 107.4 115.1 136.1 145.8 154.2 165.7
Source: These water demands are from IID Provisional Water Balance rerun in 2022 and modified from
2012 Imperial IRWMP projections to incorporate a reduction of three percent based on IID 2020 delivery
data.
Agricultural Water Demand- Agricultural water use accounts for approximately 96%
of IID’s total consumptive use. In 2023, gross agricultural production for Imperial
County was valued at $2.8 billion USD, of which the vast majority was produced within
the IID water service area.13 Although the agriculture-based economy is expected to
continue, land use is projected to modestly change somewhat over the years as
industrial and/or renewable energy development (i.e. solar) and urbanization occur
in rural areas and in areas adjacent to existing urban centers, respectively. Population
growth, inevitably results in urban sprawl, which in turn results in the conversion of
farm ground.
Agricultural water demands were also projected under the adopted Imperial IRWMP
of 2012.
Table G- 6 provides the 2015 and 2020 history and 2025-2040 forecasted agricultural
consumptive use and delivery demand within the IID water service area, which is
entirely within Imperial County. Agricultural evapotranspiration (ET) demand of
approximately 1,475.7 KAF in 2015 decreased to around 1,442.3 KAF with termination
of fallowing programs that provided 105.3 KAF of water for Salton Sea mitigation in
2017 and 46.5 KAF in 2019. Forecasted agricultural ET remains constant, as reductions
in water use are to come from efficiency conservation not reduction in agricultural
production. Forecasted total agricultural delivery demand is around 1 KAFY higher
13
http://www.co.imperial.ca.us/ag/docs/spc/crop_reports/2017_Imperial_County_Crop_and_Livestock_R
eport.pdf 2023 Imperial County Crop and Livestock Report.
IMPERIAL IRRIGATION DISTRICT
30
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
than the CU demand due to subsurface flow to Salton Sea.
Table G- 6 Agricultural Water Demand Projections as AFY
2015 2020 2025 2030 2035 2040
KAFY KAFY KAFY KAFY KAFY KAFY
Ag ET from Delivered & 1,476.4 1,442.2 1,567.5 1,567.5 1,567.5 1,567.5
Stored Soil Water
A g Tailwater to Salton Sea 282.9 312.9 268.0 218.0 218.0 218.0
A g Tilewater to Salton Sea 398.6 410.2 423.0 423.0 423.0 423.0
Total Ag CU Demand 2,157.9 2,165.4 2,258.5 2,208.5 2,208.5 2,208.5
Subsurface Flow to Salton Sea 1.0 1.0 1.0 1.0 1.0 1.0
Total Ag Delivery Demand 2,158.9 2,166.4 2,259.5 2,209.5 2,209.5 2,209.5
Notes: 2015 record from IID 2015 Provisional Water Balance rerun 06/28/2019; 2020 record from IID 2020
Provisional Water Balance rerun 01/25/2021; 2020-2055 forecasts from spreadsheet used to develop Figure 19,
et seq. in Imperial IRWMP Chapter 5 (Data provided by IID staff).
Water demand is projected to remain constant for agricultural use between 2030 and
through 2055 for the purpose of this Service Area Plan. These figures are conservative
as there is a probability that agricultural water demand will likely decrease due to
permanent urban sprawl and other water conservation efforts related to IID’s Interim
Water Supply Policy for Non-Agricultural Uses. These factors may result in a
permanent decrease on agricultural water demand as discussed further throughout
this Service Area Plan. Other uses accounted for in demand projections include water
delivery for environmental, recreational, canal seepage, operational discharge,
mitigation, evaporation, and approximately 35 KAFY of unaccounted water. Table G-
7 has a summary of total projected water demand for both agricultural and non-
agricultural uses in the Imperial Valley.
Table G- 7 Water Demand Projections in AFY
Non-Agricultural Agricultural Total Projected
Year
Water Demand Water Demand Water Demand
2025 136,100 2,259,500 2,395,600
2030 145,800 2,209,500 2,355,300
2035 154,200 2,209,500 2,363,700
2040 165,700 2,209,500 2,375,200
Source: 2012 Imperial Integrated Regional Water Management Plan.
NOTE: Conservation efforts under Agricultural Water Demand are not accounted for
under these projections.
b) Energy Demand Projections
Population forecasts, on their own, are unable to project energy demand. Non-
residential energy sales accounts for slightly under 50 percent of all IID electrical
IMPERIAL IRRIGATION DISTRICT
31
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
energy sales. Commercial sales accounted for about 40 percent of IID’s total energy
sales. Energy sales demonstrated a 5% decrease in 2023 from 2022 sales, however
the 2023 peak energy demand represented an increase of 5.7% over 2022 peak
demand. New and rapidly increasing industrial loads are anticipated in the Coachella
Valley.
Economic Data is a clear driving factor for energy demand. Economic data used in the
energy load forecast regression models are population, total employment, farm
employment, retail employment, personal income, and gross regional product. The
projected energy demand from non-residential commercial/industrial growth is
expected to grow substantially, particularly in the Riverside County service area.
The IID Power Department has prepared system load term load forecasts of peak
demands, net energy requirements and energy sales to customers for its service
territory with support from Ascend Analytics. Ascend’s load model uses the California
Energy Commission (CEC) 2021 Integrated Energy Policy Report (IEPR) Mid Demand /
Mid AAEE-AAFS Case as the starting point for the CAISO peak demand and total
energy forecasts, using the 1-in-10 coincident case for peak demand.14 The load
forecast relies on industry accepted standards of practice, as well as rigorous, detailed
and thorough analysis, critical to obtaining results that are both realistic and
statistically sound. In this load forecast, an econometric approach was utilized to
forecast IID’s total retail sales. The Net Energy for Load (NEL) forecast was derived
from the total retail sales forecast and the average difference of NEL and retail sales
over history; Coincident Peak (CP) forecast was derived from NEL forecast and
representative load factor history. The forecast is primarily driven by several key
variables that have an impact on hourly/daily/monthly/yearly loads and the forecast
incorporated into the load impact resulting from these variables including, but are
not limited to:
- Weather changes
- IID Energy Efficiency (EE) programs
- IID Rooftop Photo-voltaic (PV) Solutions Programs
- Electric Vehicles programs (EV)
- New Industrial Load Impact
- Regulatory Requirement Changes
Since the forecast variables are uncertain, the severity of their impact on load
depends on how each of these variables transpire. Generally, these variables can
either encourage load growth or deter it. Below is a diagram that illustrates which
14 2021 Integrated Energy Policy Report
IMPERIAL IRRIGATION DISTRICT
32
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
variables encourage load growth and which variables deter load growth.
The California Energy Commission (CEC) releases demand forecasts periodically for
IID and other BAs in California as part of the Integrated Energy Policy Report (IEPR).
The most current IEPR is the 2022 Update, which included the 2022 California Energy
Demand Update (CEDU), only released a “Mid” case scenario. Under the Power
Department’s IRP, for the 2024 IRP forecast, three main cases were used to represent
the potential outcomes using the prior 2021 IEPR for Low and High scenarios: 1) High
Case Scenario- Combining severe weather conditions, high industrial growth, high
electric vehicle penetration, low energy efficiency, and low rooftop/customer solar
penetrations; 2) Mid Case Scenario (Expected) – Combining normal weather, normal
industrial growth, average electric vehicle penetration, average energy efficiency, and
average rooftop/customer solar penetrations; and 3) Low Case Scenario–Combining
mild weather conditions, normal economic industrial growth, low electric vehicle
penetration, high energy efficiency, high rooftop/customer solar penetrations. The
assumed monthly energy and 1-in 10 peaks load forecasts are provided in
IMPERIAL IRRIGATION DISTRICT
33
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
Table G- 8.
Table G- 8 Annual Energy Demand and 1 in 10 Peak Load Forecasts
Annual energy Demand (GWH) 1-in-10 Peak Loan (MW)
Low Mid High Low Mid High
2025 3,966 4,094 4,233 1,168 1,167 1,215
2026 3,988 4,139 4,297 1,183 1,181 1,234
2027 4,028 4,186 4,361 1,198 1,194 1,254
2028 4,058 4,232 4,426 1,214 1,209 1,276
2029 4,076 4,271 4,482 1,226 1,219 1,294
2030 4,088 4,306 4,537 1,239 1,229 1,313
2031 4,087 4,337 4,581 1,249 1,240 1,330
2032 4,078 4,365 4,624 1,254 1,250 1,345
2033 4,059 4,387 4,666 1,257 1,258 1,360
2034 4,026 4,403 4,702 1,258 1,264 1,374
2035 3,981 4,412 4,734 1,254 1,268 1,387
2036 3,988 4,438 4,780 1,259 1,276 1,400
2037 3,999 4,470 4,830 1,266 1,284 1,413
2038 3,009 4,503 4,880 1,272 1,293 1,427
2039 4,019 4,535 4,929 1,278 1,301 1,441
2040 4,030 4,567 4,979 1,284 1,309 1,455
Source: 2024 Energy Integrated Resource Plan: IID.com/home/2024 IRP
C. IMPACTS FROM LAND USE CHANGES
The transition from agricultural land use typically results in a net decrease in water demand
for municipal, commercial, and solar energy development; and a net increase in water
demand for geothermal energy or other industrial development. Local energy resources
include geothermal, hydro, wind, biomass and solar. The County General Plan provides for
development of energy production centers or energy parks within Imperial County.15
Alternative energy facilities will help California meet its statutory and regulatory goals for
15 Imperial County General Plan, Geothermal/Alternative and Transmission Element, revised 2006 and
2015.
IMPERIAL IRRIGATION DISTRICT
34
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
increasing renewable power generation and use and decrease water demands in Imperial
County.
The IID Board has adopted several policies and programs to address how to accommodate
water demands and minimize potential negative impacts on agricultural water uses.
Conservation Programs are independently assessed under its respective chapter of this
Service Area Plan and are consistent with the following policies that have been adopted by
the district:
Imperial Integrated Regional Water Management Plan: adopted by the IID Board on
December 18, 2012, and by the County and the City of Imperial, to meet the basic requirement
of California Department of Water Resources (CDWR) for an IRWM plan. In all, 14 local
agencies adopted the 2012 Imperial IRWMP. Changes in the State law that came into effect
in 2016 have made the 2012 IRWMP non-compliant with State standards, restricting local
jurisdictions from many of the CDWR financial resources.
Interim Water Supply Policy for Non-Agricultural Projects: adopted by the IID Board on
September 29, 2009, to ensure sufficient water will be available for new development, in
particular, anticipated renewable energy projects until the board selects and implements
capital development projects such as those considered in the Imperial IRWMP. New non-
agricultural development must coordinate with IID for the generation of conserved water.
Temporary Land Conversion Fallowing Policy: adopted by the IID Board on May 8, 2012, and
revised on March 29, 2016, to provide a framework for a temporary, long-term fallowing
program to work in concert with the IWSP and IID’s coordinated land use/water supply
strategy. Although water generated from the TLCFP is limited by policy for use towards
transfer or environmental purposes, by satisfying multiple district objectives the TLCFP also
serves to reduce the conservation and water use demands on other IID water users.
Equitable Distribution Plan: revised plan adopted by the IID Board on July 26, 2023, to provide
a mechanism for IID to administer apportionment of the district’s quantified annual supply of
Colorado River water; The 2023 revisions established a water exchange clearinghouse to
facilitate the movement of water supply within water user categories.
If, and when, a new development is proposed within IID’s service area, the district coordinates
a predevelopment review during the land use authority’s CEQA review process, and
permitting phase, to ensure energy and water supply needs have an opportunity to be
satisfactorily addressed. Generally, water infrastructure improvements that are tied to
population growth are the responsibility of the retail service provider (entity providing
treated water services to the new population). Energy infrastructure related to residential
housing (tied to population growth) is the developer’s responsibility.
IMPERIAL IRRIGATION DISTRICT
35
2025
SERVICE AREA PLAN GROWTH & POPULATION PROJECTIONS
IMPERIAL IRRIGATION DISTRICT
36
2025
SERVICE AREA PLAN PUBLIC FACILITIES AND SERVICES
IV. PUBLIC FACILITIES AND SERVICES
This Service Area Plan will address public facilities, services, and programs provided by the
Imperial Irrigation District to its service areas over the course of a 5-year planning period.
Although the Imperial Irrigation District has two primary departments for water and energy service
delivery (the Water Department and the Power Department), IID offers other related services that
are carried out by these two departments and supported through five other administrative
departments: Executive, General Services, Information Technology, Finance and Human Resources
(hereafter, Administrative Services). For the purpose of this Service Area Plan, facilities and services
are presented in the following areas:
A. Irrigation Water Services & Facilities - Imperial Irrigation District
B. Drainage Facilities - Imperial Irrigation District/Municipalities
C. Power Facilities - Imperial Irrigation District
D. Conservation Programs - Imperial Irrigation District
E. Administrative Facilities - Imperial Irrigation District
An analysis of the listed facilities and services are provided under this chapter. Each facility is
analyzed in detail based on the guidelines developed by LAFCO for Service Area Plans and on
the performance standards established by the Imperial Irrigation District. Each respective service
area provides a description of the nature of each service to be provided, a description of the service
level capacity and a determination on whether adequate services are and will be provided within
the projected demand and twenty-year planning time frame. Each facility’s service analysis is
presented in three detailed sections as follows:
1. Performance Standard: A description of the desired level of service that the
respective public facility must provide.
2. Facility Planning and Adequacy Analysis: A description of the existing facilities,
the current adequacy of the facilities, the future demand for facilities and the
phasing of the demand for facilities as follows:
a) Inventory of Existing Facilities
b) Adequacy of Existing Facilities
c) Future Demand and Planned Facilities
d) Opportunities for Shared Facilities/Services
e) Phasing of Facilities/Services
3. Mitigation: As applicable, recommendations to ensure that adequate facilities
and services will be provided for are addressed under the respective service area.
This Service Area Plan further contains a Financial Plan. The Financial Plan offers information of how
the facilities, services and programs extended by the Imperial Irrigation District are currently being
funded and identifies opportunities of how future services, facilities and programs may be funded.
IMPERIAL IRRIGATION DISTRICT
37
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
A. IRRIGATION WATER FACILITIES
IID diverts water from the Colorado River and delivers it to over 520,000 acres within its water
service area in Imperial Valley. Imperial Dam, located about 20 miles north of Yuma, Arizona,
is a diversion structure for the river, All-American Canal and Gila Canal water deliveries,
serving southeastern California, Arizona and Mexico. The operations of IID's River Division
Office at Imperial Dam, as well as water delivery to other contractors in Arizona, California
and the Republic of Mexico, all fall under the direction of the US Bureau of Reclamation.
The IID’s only source of water is its Colorado River entitlement. IID has a “present perfected”
right to 2.6 million acre-feet (MAF). Because these vested rights preempt the 1902
Reclamation Law and are not subject to reclamation law limitations, in times of water
shortage, present perfected rights must be satisfied first. Under the 2003 execution of the
QSA and Related Agreements signed by the Secretary of Interior, Imperial IID, CVWD, MWD
and the SDCWA, IID’s annual consumptive use is capped at 3.1 million acre-feet (MAF) for a
minimum 45-year term, with possible extension for another thirty-years. This Service Area
Plan will consider the 3.1 MAF water resource to meet anticipated demands during this
planning period.
Of the water that the IID conveyed in 2023, approximately 96 percent was used for agriculture
purposes in the Imperial Valley to serve a total of 5,131 farm accounts. The remaining 4
percent was delivered to six cities, two special districts and a private water company that
treat the water to safe drinking water standards and sell it to their residential and commercial
clients through their independent distribution systems in addition to water deliveries to rural
service pipes.
1. Performance Standards for Water Delivery
Water for Agricultural Use- IID must be able to deliver to the agricultural community
water to irrigate approximately 475,000 acres of farm ground that has had a demand
history of approximately 2.3 MAFY. This includes lands that have been fallowed or not
farmed. The district has not adopted a performance standard for agricultural use, but has
identified an annual average of 5.1 AF of water per acre of farmable land. This standard
would be consistent with the 10-year average, water use history, per acre, of all fields in
IID. The 5.1 AF/Acre will continue to be the desired maximum average for performance
assessment of agricultural water use.
Water for Non-Agricultural Use- Other in-valley areas that receive water from IID are
classified as industrial/urban uses for the purpose of this Service Area Plan. These uses
include municipalities, feedlots, cattle yards, managed marsh land, recreation areas, rural
service pipes and similar non-agricultural uses. The State of California adopted emergency
measures during the last drought in 2013‒2017. State-wide water conservation goals
called for urban areas statewide to reduce their water use by 25 percent. These uses
IMPERIAL IRRIGATION DISTRICT
38
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
encompassed 49,034 acres in 2017 and had an annual demand of 92,214 AF for the same
year, averaging .53 AFY/AC. IID’s performance standard for water availability to existing
non-agricultural uses was set at a conservative .50 AFY/AC under the 2020 Service Area
Plan. All new non-agricultural development would need to coordinate with IID for water
supply available through water conservation programs and/or system conservation
projects consistent with the district’s IWSP as further described in Section D of this Service
Area Plan.
Operational Water Storage- The use of operational reservoirs allows for increased
delivery flexibility and provides conservation opportunities within the district. In 2019 IID
set a goal to attain 8,750 AF of raw water storage for the operational efficiency of the
475,000 total farmable acreage served. Since not all irrigated farm-ground can benefit
from an operational reservoir, the standard is not set per acre, but is hereby established
as a set target district-wide. During the next planning period, the district is targeting a
10,000 AF water storage capacity for operational purposes.
2. Water Facility Planning and Adequacy Analysis
All water services and facilities are managed through the IID Water Department. The
Water Department contains an administrative section and eight operational sections: 1)
Engineering Services, 2) Agricultural Water Resources, 3) Water Quality Programs 4)
Water Environmental Mitigation, 5) All-American Canal/Dam Operations & Maintenance,
6) System Control and Monitoring, 7) Operational Reporting, and 8) Southend O&M and
Northend O&M. Two of these sections, the Agricultural Water Resources and the Water
Environmental Mitigation Section have a primary focus on water conservation and
environmental mitigation efforts and are therefore discussed in more detail under the
Conservation Programs chapter of this Service Area Plan. The remaining Water
Department sections with primary functions for water facilities operations and water
delivery services are summarized below:
• Water Administration Section is responsible for the oversight of all
operations, maintenance, engineering services, budgetary process and
accountability for the Water Department. This section interfaces with the
Board of Directors, general manager and the public to ensure effective
communication and proper administration of policies and procedures. Water
Administration also ensures that the sections and units within the Water
Department are meeting goals and objectives established by and for the
Water Department in their Strategic Plan.
• Water Engineering Services Section has three primary functions: 1) Provides
engineering services for the water department, other agencies, developers,
miscellaneous power and other capital maintenance and planning projects;
2) Manages the Capital Improvement Program (CIP), and 3) Serves as a liaison
IMPERIAL IRRIGATION DISTRICT
39
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
for the district and provides protection of district interests through planning
and commenting on technical and legal documents and/or policies
procedures, operation and maintenance.
• Water Quality Programs Section is comprised of the Water Quality and
Water Biological Control units. This section is responsible for collecting,
maintaining, and reporting water quality data for regulatory compliance
purposes as well as coordination of Water Department weed spray activities.
Areas of responsibility include TMDL/Ag Waiver, Safe Drinking Water, Title 22
Joint Monitoring and Vegetation Management Programs. This section is also
responsible for the biological control of invasive species within the IID canal
system by use of grown and raised grass carp.
• The All-American Canal/Dam O&M Section is responsible for transporting
irrigation, industrial and municipal water through the main canals for
scheduled deliveries. This section also plans, organizes, directs, prioritizes
and implements comprehensive strategies and programs for the
construction, maintenance and repair of Senator Wash, Imperial Dam, the
main canals, and related structures.
• Operational Reporting Section estimates and orders Colorado River water
for Imperial Valley irrigation distribution. The section makes the irrigation
water available to the water divisions for delivery to farmland and cities by
routing the available irrigation water through the main canal system using
IID’s SCADA system. This section prepares water analysis reports and water
accounting from the All-American Canal Station 1117 to Station 4242 which
becomes part of the USBR Colorado River accounting.
• South-End & North-end O&M Section has the primary responsibility of
delivering irrigation water to its Southend and Northend customers,
respectively, in the most economical and efficient manner. This section is
responsible for the district’s irrigation and drainage systems including the
maintenance of open channel canals, pipeline canals, water deliveries, and
open channel drains. The office staff interfaces with water customers
involving water orders, water card process requests, service pipes and small
acreage accounts.
a) Inventory of Existing Water Facilities
Water is diverted at the Imperial Dam through the 80-mile-long All-American Canal
and into a vast gravity-flow water distribution system, which the district owns,
operates and maintains. There are 11 main canal scheduling areas supported by 11
raw water storage reservoirs ranging in capacity from 200 to 1,251 AF. A smaller, 42
IMPERIAL IRRIGATION DISTRICT
40
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
AF capacity, mid-lateral reservoir was constructed in 2023 for a combined capacity of
over 4,300 AF. The reservoirs help absorb flow mismatches from the main canal reach
upstream of the reservoir and allow delivery of scheduled flows into the next reach
downstream. These operational measures constitute a supply-control process, where
flows to meet scheduled water deliveries are released into canals and routed from
upstream to downstream according to the operations schedule. A summary inventory
of IID water facility system follows:
Imperial Dam- The Imperial
Dam is IID’s point of diversion
from the Colorado River. It
overlaps the California-Arizona
border and AAC trash-rack and
head-gates located adjacent to
the California abutment of the
dam. Three desilting basins
(design capacity 4,000 cubic
feet per second each) remove
the sand and silt from the river
water before it passes to the
AAC. The sand and silt removed
are continuously returned to
the river at the California
Sluiceway Channel. The Imperial
Dam and Gila Headworks are operated and maintained by IID with costs shared by
the Bureau of Reclamation and the California and Arizona water agencies also served
by the facilities at a smaller share.
Water Distribution Facilities-The AAC is a federal canal that IID operates and
maintains under contract for Reclamation. While the Bureau of Reclamation owns the
physical structure, IID owns the AAC capacity and as such, operated and maintained
by the district with share of costs from USBR and all the state water agencies it serves.
Within the Imperial Valley, three main canals receive water from the AAC: the East
Highline, Central Main, and Westside Main Canals, which are owned and operated by
IID. From these main canals, the irrigation water is distributed through an extensive
network of supply and lateral canals to numerous IID customers. Please see
Figure 5 Imperial Unit Canal Network. The main and supply canals have diversions to
lateral canals, and from lateral canals into customer’s head ditches. The extensive
network of irrigation conveyance facilities includes over 1,641 miles of open channel
canals. IID maintains earthen, concrete lined and piped sections as noted
Table W- 1.
IMPERIAL IRRIGATION DISTRICT
41
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
Figure 5 Imperial Unit Canal Network
IMPERIAL IRRIGATION DISTRICT
42
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
Table W- 1 2024 Water Distribution System
System Earthen Concrete Lined Piped Total Length Miles
All-American Canal¹ 56.720 23.000 .071 79.791
Main Canals 128.218 22.072 0.00 150.290
Lateral Canals 306.173 1,100.751 30.204 1,437.128
TOTAL 491.111 1,145.823 30.275 1,667.138
NOTE: The data is as of January 1, 2024
¹ The AAC is a federal canal that IID operates and maintains under contract for Reclamation. The New
River Siphon is a 374-foot piped portion of the AAC.
Operational Reservoirs- Raw water storage is an integral component of the water
distribution system for operational purposes. Operational reservoirs are important
for water system delivery and control delivery efficiency and have grown increasingly
critical to accommodate water transfers. IID’s water distribution system includes
seven regulating (R) and four interceptor (I) reservoirs and one mid-lateral reservoir
with a combined water storage capacity of 4,414 acre-feet.
Table W- 2 provides an inventory of existing reservoir specifications as of January
2024.
Table W- 2 IID 2024 Reservoir Specifications
Reservoir Surface Storage Maximum Flow Capacity
Area Capacity, AF Depth, FT Inlet Outlet
Singh (R) 32 323 11.0 100 100
Sheldon (R) 50 476 10.0 100 100
Fudge (R) 38 300 10.0 100 100
Sperber (R) 64 470 9.0 100 200
Carter (R) 32 350 11.3 150 50
Galleano (R) 40 425 21.0 150 75
Bevins 37 253 12.9 165 50
Young 47 275 9.0 100 100
Russell 29 200 8.3 100 50
Wiley 51 300 7.0 190 51
AAC Off-line Storage (R) 74 1,000 13.6 400 400
Lloyd Allen 15 42 9.0 40 20
TOTAL 509 4,414
Source: IID Reservoir Webpage.
IMPERIAL IRRIGATION DISTRICT
43
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
Water Control Center- In September 1993, IID completed the construction of a $3
million Water Control Center. The 10,000 square-foot building constructed at IID
Headquarters houses hardware and software used to regulate automated gates for
water control and to collect the information needed to verify efficiency. The building
is equipped with a backup generator that ensures uninterrupted power service to the
control system. Other technology at the Water Control Center includes earthquake
disaster recovery features, computer generated screens displaying control room
information and changeover procedures to allow for continuous 24-hour water
delivery service. The district has numerous flow monitoring and control devices
comprised of elements depicted on Table W- 3. IID has over 5,000 delivery gates
serving agricultural, municipal and industrial water users, including some recreational
uses.
Table W- 3 IID 2024 Flow Monitoring and Control Devices
Element Approximate Number
Manual Farm Delivery Gates¹ 4,790
Manual Non-Ag Delivery Gates (including 51 feedlot) 336
Lateral Headings (55% automated) 233
Discharge/Flow Monitoring 208
Main & Supply Canal Check Gates (90% automated) 76
Non-Leak Gates 20
TOTAL
Source: IID System Control/Monitoring and Data Management Section Staff, 2024
¹ Excludes 452 Inactive Gates
Water Measuring & Accounting Equipment- IID measures and records all water
deliveries to users except for service pipes and small parcels. Flow is also measured
and recorded throughout the water transportation system (and at key points in the
drainage system) using SCADA technology by means of IID’s WISKI which is an Oracle-
based system to collect and process flow data in support of water management. IID
has over 350 automated measurement systems and performs manual measurement
on all delivery gates. While there are a number of meters at delivery gates serving
industrial and municipal uses, the metered facilities are privately owned and not
integrated into IID’s SCADA system. The district also owns other miscellaneous
metering equipment for efficient water accounting as noted in Table W- 4 IID
Metering Equipment.
IMPERIAL IRRIGATION DISTRICT
44
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
Table W- 4 IID Metering Equipment
Equipment Type Number
All-American Propeller Meter 10
Flow Tracker/Point Velocity 2
ADCP (Rivercat-Sontek) 5
ADCP (Stream Pro RDI) 2
Marsh-McBurney 2
TOTAL 21
Source: 2021 Water Conservation Plan updated in 2024 by IID Staff.
Personnel and Vehicles-The Water Department (excluding the Agricultural Water
Resources Section, and the Environmental Mitigation Section) is supported by a staff
of 444 employees and 353 company owned vehicles. The particulars under each
respective Water Department Section are noted below.
Water Department Personnel 2024 (444 Total FTE):
• Water Administration Section (6 FTE)
• Engineering Section (113 FTE)
• Water Environmental (9 FTE)
• Water Quality Programs (12 FTE)
• AA Canal/Dam O&M Section (34 FTE)
• Operational Reporting Section (34 FTE)
• Southend O&M Section (127 FTE)
• Northend O&M Section (109 FTE)
Water Department Vehicles in 2024 (353 Total):
• Water Administration (3 Vehicles)
• Engineering Section (130 Vehicles)
• Water Environmental (8 vehicles)
• Water Quality Programs (9 vehicles)
• AA Canal/Dam O&M Section (28 Vehicles)
• Operational Reporting Section (11 Vehicles)
• Southend O&M Section (91 Vehicles)
• Northend O&M Section (73 Vehicles)
b) Adequacy of Existing Water Facilities
IID’s Colorado River 3.1 MAFY water entitlement is significant, and as the agency
entrusted with these water rights, IID continues to responsibly manage Imperial
Valleys Colorado River water supply and related resources in an efficient manner. Per
the district’s Provisional Water Balance, IID has a generally consistent, consumptive
agricultural use water demand of 2.2 MAF/Year, on average (based on volume
history). Total Non-Agricultural Water delivery is under 93,000 AFY. Including all other
IMPERIAL IRRIGATION DISTRICT
45
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
water deliveries16 (385,000 AFY) the total volume is 2.6 MAFY. IID water supply is
discussed in more detail under the Conservation Section of this Service Area Plan. This
section is strictly for assessment of the facilities needed to deliver IID’s consumptive
use in an efficient and reliable manner.
Imperial Dam – Water for the Imperial Valley is diverted at Imperial Dam. Diversion
services at Imperial Dam benefit a number of other water contractors and is adequate
in size and capacity, however, the facility was constructed over 80 years ago and much
of the original equipment is experiencing deterioration. A number of the dam’s
assembly equipment is aging and in need of replacement or refurbishment. As such,
a rigorous capital improvement plan will be continued and be coordinated among the
U.S. Bureau of Reclamation, IID and all of the other benefitting agencies that have a
cost share.
Operational Reservoirs- As previously noted, the district owns and operates twelve
reservoirs system wide. Given the increased demand for water order delivery
flexibility, the 4,414 acre-feet of reservoir capacity for operational flexibility has
demonstrated to be insufficient to maximize the growers service demand within the
district’s water service area. The district has initiated the construction of a series of
smaller (< 50 AF) mid lateral reservoirs and planning the development of a 2,100 AF
capacity reservoir upstream of the district’s distribution system. An additional 2,500
AF of operational water reservoirs are projected to be constructed over the next five
years to accommodate the current agricultural system and irrigation clients.
Operational reservoirs serve a dual purpose of regulating or intercepting water orders,
accommodating grower cancellations and/or water order changes and subsequently
reducing operational discharge and conserving water.
Water Distribution Facilities- IID’s extensive water distribution system is sufficient to
meet the needs of the district’s water service area via its 1,660+ miles of gravity flow
distribution channels. There are no water service expansions proposed, or anticipated
that would necessitate the extension of water distribution facilities. New non-
agricultural development is predominantly proposed to be located within the
irrigated Imperial Unit. As new non-agricultural growth is contemplated, capacity of
the distribution system is assessed by the proposed new development and the
district, on a case by case basis, considering the project’s water supply demand.
Incorporation of mitigation measures, as may be necessary would be considered at
the time and be the sole responsibility of the project developer. However, in support
of water conservation efforts, the district strategically and continuously improves its
16 Includes water delivery for environmental, recreational, canal seepage, operational discharge, mitigation, and
evaporation.
IMPERIAL IRRIGATION DISTRICT
46
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
water distribution facilities with the concrete lining of canals and construction of
lateral interties throughout the IID irrigation system, as feasible. These projects are
discussed under the conservation chapter of this SAP.
Water Control Center- The Water Control Center became operational in 1993 and is
approximately 30 years old. In early 1998, IID was awarded the International Award
of Excellence for Innovation Technology of its System Automation Program (Water
Control Center and remove flow monitoring sites), which provides improved water
management utilizing modern control technology. SCADA system upgrades, including
computer and processing unit installations, are continuously budgeted and upgraded.
IID is in the process of completing the final phase of a system-wide automated lateral
headings for SCADA integration. The SCADA system allows the district to remotely
monitor and control the automated lateral heading gates throughout the district.
Through the SCADA system IID is able to also collect data for reporting and analysis,
enabling real-time decision making.
Water Measuring & Accounting
Equipment- IID has consistently
invested in the installation of
solar driven, 12-volt automated
Rubicon Sonaray slipmeters to
replace existing, manually
operated gates at selected lateral
headings throughout the IID
distribution system and service
area. The automated lateral
headings allow for reduction of
operational discharge, which is
being monitored at the end of
Manual Lateral Heading
each lateral. As previously noted,
an estimated 120 sites have been
automated to date with an
additional 42 sites scheduled for
completion prior to the end of 2026. The current measurement and accounting
equipment are sufficient to meet the rigorous water accounting and reporting that
IID publishes annually for the State Water Resources Control Board, U.S. Bureau of
Reclamation and its QSA partners.
c) Future Demand for Water Facilities & Planned Improvements
Water Supply - The adopted 2012 Imperial Integrated Regional Water Management
Plan addresses the region’s water supply and demand, including baseline and
IMPERIAL IRRIGATION DISTRICT
47
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
forecasted values through 2050. In-valley water demand is separated from two
sources of demand: 1) agricultural, and 2) non-agricultural (municipal /treated water
providers), industrial (including commercial and solar). IID implements a water
apportionment method for the distribution of water within its water service area. In
efforts to address any potential water supply/demand imbalances, on June of 2022,
IID adopted a revised Equitable Distribution Plan17 for the apportionment of water to
all water user categories. Apportionment is allocated based on water use history. The
water supply that is apportioned annually is consistent with IID’s
consumptive/operational use of 2.6 million acre-feet per year, the water supply
available after IID meets its water transfer obligations for the respective year.
Approximately 96 percent of water is distributed for agricultural uses while 4 percent
of raw water is distributed for non-agricultural uses. During 2023, approximately one
percent (1%) of the non-agricultural water demand went to public agencies for
treatment to potable water standards. Any water supply demand resulting from new
development must be satisfied in compliance with IID’s Interim Water Supply Policy18
for Non-Agricultural Uses via implementation of water conservation measures. The
Water Conservation & Efficiency Section of this SAP describes the conservation and
efficiency measures implemented by the district.
Planned Water Facilities- No new water facilities are anticipated as a result of the
projected water supply demand, considering IID does not expect to expand its water
service footprint nor does IID expect an increase in its water supply entitlement
beyond its authorized consumptive use. By contrast, IID plans to implement a number
of water reduction measures for overall water conservation and to accommodate
water transfers (please refer to water conservation section.) Some of the existing
water facilities, however, are planned for retrofit and rehabilitation for more efficient
operation, as per the 5-Year Capital Improvement Plan of the Water Department (last
revised July 2018) which may be modified from time to time. Any relevant water
conservation data associated with capital projects is discussed under the
Conservation Programs section of this Service Area Plan.
Imperial Dam Capital Improvements- A number of Imperial Dam projects are
also projected to be completed within a five-year timeframe. Improvements
under consideration at Imperial Dam are as follows.
• AAC Section 1-Basin Gallery Sludge Pipes Replacement
• AAC Section 1-Repair & Replace Clarifier Training Wall Caps
• AAC Section 1-Refurbish Station 48+50 Check Gates
• AAC Section 1-Refurbish Two Bypass & 14 Clarifier Inlet Gates
17 Equitable Distribution Workshops and Presentations | Imperial Irrigation District (iid.com)
18 https://www.iid.com/water/municipal-industrial-and-commercial-customers
IMPERIAL IRRIGATION DISTRICT
48
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
• AAC Section 1-Repair California Trash Screen Railway
• AAC Section 1-Replace 588 Valves on Clarifiers
• AAC Section 3-Construct Floating Bulkhead for Pilot Knob
• AAC Section 1-California Sluiceway- Motor and Gate Replacement
• Common Works-Repair Unused Radial Gate
• Gila Headworks Motor & Gearbox Replacement
• Gila Headworks-Rebuild Diversion Motor, Gates and Gearbox Replacement
• Gila Headworks Diversion Gate Refurbishment
• Laguna Dam-Refurbish and Install Gate
Water Reservoirs- Operational reservoir storage capacity is critical in
maximizing water management and efficiency. As previously noted, the
district is in the planning and design phase of constructing an upstream
reservoir almost twice as large as the largest reservoir in its distribution
system at a 2,100 AF capacity that will be able to manage up to 365,000 AF of
water per year. The following is a list of the planned main canal and mid-
lateral reservoirs:
Table W- 5 Planned Operation Reservoirs
Main Canal Operational Reservoirs Mid-Lateral Reservoirs
East Highline/AAC Reach Reservoir East Highline Lateral
Trifolium 10 Reservoir Rose Lateral
Westside Main Reservoir E Lateral
Water Distribution Facilities- An estimated fifteen (15) miles of concrete
lining is planned for the IID Canal System within the next five years. These
improvements are continuous efforts expected to facilitate maintenance by
replacing deteriorated segments or installing new concrete on earthen
sections. Other planned capital improvements to the existing IID canal system
include check structures and gate replacements for both Northend and
Southend laterals. IID will also undertake customer initiated and customer
financed projects for pipelining and undergrounding laterals in response to
urban sprawl and new development.
Water Control Center-The Water Control Center recently underwent a
number of annual upgrades during the last five years and through 2023 of
approximately $120,000 annually. The improvements consisted of new
computers and processing unit installations. No additional improvements are
anticipated over the next five years.
Water Measuring & Accounting Equipment- IID continuously invests and
upgrades water measurement towards the most advanced automation
IMPERIAL IRRIGATION DISTRICT
49
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
equipment a total of five new automated check structures were installed within
the last five years. IID anticipates numerous automation equipment purchases
within the next five years proposed to be paid from water transfer revenues.
Automation and measurement improvements are budgeted at approximately
$675,000 per year. IID system projects also include the following:
• Automation of New Briar Check 4
• Automation of Turnip HAG Check
• Automation of East Highline Reservoir Gate Checks at E, H, J, K and Niland
• Automation of East Highline 37 and 46 Checks
• Automation of the Wistaria Heading Actuators and Hoists
• Automation of the Trifolium Extension Heading Actuators and Hoists
IID continues to advance into the next phase of modernized measurement at the
delivery gate level. Currently, IID uses field pressure measurements to calculate
water use at the point of delivery. There are over 5,550 delivery gates system-
wide covering approximately 520,000 acres of irrigated land which make this
method labor intensive and not as precise as metered deliveries. IID is assessing
the feasibility of implementing automated SCADA integrated metered delivery
systems. The right system may also be able to be adapted to integrate with other
agriculture technologies.
IID is a wholesale irrigation water provider with existing facilities meeting the service area
demands for the delivery of its full water entitlement. The District’s water supplies are
not expected to increase given the limitations of the Colorado River hydrology. Thus, IID’s
infrastructure is adequate for the water supply it will be managing over the course of the
5-year SAP planning period and beyond. Any shift in water demand location, that may
result in changes to infrastructure capacity limitations, would be addressed during the
CEQA review process and/or permitting phase of the proposed new development.
d) Opportunities for Shared Water Facilities
Numerous facilities under which IID has share of costs for operation and maintenance
are also shared by and for the benefit of other water agencies. At the point of water
diversion, Imperial Dam and associated costs are shared by numerous water agencies
including Yuma Mesa Irrigation District, North Gila Valley Irrigation and Drainage
District, Yuma Irrigation District (South Gila), Wellton Mohawk Irrigation District, Yuma
Auxiliary Project, Valley Division, Bard Water District, Bureau of Indian Affairs and
Coachella Valley Water District. IID’s cost share of the common works at Imperial Dam
is approximately 77%.
Another major facility under which IID has a share of cost for operation and
maintenance is the All-American Canal. The AAC identifies seven distinct channel
IMPERIAL IRRIGATION DISTRICT
50
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
sections, four of those sections continue to benefit some of the aforementioned water
agencies which in turn share in the costs associated with the respective section
operation and maintenance. Specifically, AAC use and costs are shared with Valley
Division, Bard, BIA and CVWD. IID is responsible for approximately 76% to 88% of the
costs within those four respective sections and is responsible for 100% of the costs
under the remaining three sections.
IID does not share owned operational reservoirs but the District does make use of
water storage opportunities in federally owned reservoir facilities as limited under the
2007 Interim Guidelines. Storage is limited by the Intentionally Created Surplus
Forbearance Agreement19. Without an amendment, the total amount of Efficiency
Conservation Intentionally Created Surplus that IID may store within its Lake Mead
ICS account in any given year is an annual creation of 25,000 AF and a cumulative limit
of 50,000 AF total. IID also makes use of conserved water storage via agreements
through other partner agencies. As the post 2026 operating guidelines are
negotiated, it is possible that in the future, the District will increase storage of water
at Lake Mead for mutual shared benefits.
e) Phasing of Water Facilities
All of the district’s short-term construction projects and major capital purchases are
included in the Water Department’s Capital Improvement Plan which spans over a
five-year period. Proposed facilities beyond the five years are derived by the Water
Departments’ 2040 Capital Improvement Plan under development. Some of the
operational projects identified under this section have a multi-benefit of water
conservation and will be discussed further in the corresponding section of this SAP.
Short Term Improvements (Under 5 Years)
• Imperial Dam Upgrades
• Upstream Operational Reservoir at East Highline Canal
• Annual Concrete Lining of Canal and Lateral Segments
• Annual Replacement of Control Structures, Inlets, Outlets
• Automation Projects at Checks
• Automated Measurement Equipment
5-10 Year Improvements
• Imperial Dam Upgrades
• Multiple in-line operational reservoirs
• Annual Concrete Lining and/or pipelining
19 An Agreement between State of Arizona, the Palo Verde Irrigation District, the IID, the City of Needles, the Coachella Valley
Water District, the Metropolitan Water district of Southern California, the southern Nevada Water Authority and the Colorado
River Commission of Nevada to encourage efficient use and management of Colorado River water, help avoid shortages in the
Lower Basin, and benefit Lake Mead and Lake Powell.
IMPERIAL IRRIGATION DISTRICT
51
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
• Annual Automation & Measurement Equipment projects
• Delivery Gate Metering Project Phasing
10-15 Year Improvements
• Continue Imperial Dam Upgrades
• Continue Development of Multiple in-line Operational Reservoirs
• Annual Concrete Lining and/or Pipelining
• Annual Automation & Measurement Equipment projects
• Delivery Gate Metering Project Phasing
3. Water Facilities and Services Mitigation
Imperial Irrigation District’s water distribution is entirely gravity flow from the point of
diversion throughout its extensive canal system with very isolated exceptions. The
District’s overall water supply goal is to live within its consumptive use by maximizing
water use efficiency throughout its water service area. IID will continue to protect the
Districts’ water rights to ensure a long-term, verifiable, reliable and sustainable water
supply to meet current and future agricultural, municipal, commercial, industrial, and
environmental demands and to do so in a cost-effective manner. In this vein, IID will
continue to pursue various means by which to provide for the efficient delivery of
water service. The following are mitigation measures to achieve adequacy for water
service facilities and service delivery:
W-1 Continue to implement projects, or programs, that will provide a firm,
verifiable, and sustainable water supply of 50 to 100 thousand acre-
feet per year (KAFY) for new municipal, commercial or industrial
demands.
W-2 Ensure equitable and appropriate cost sharing among water users
who would receive benefits from any proposed water management
project.
W-3 Continue to protect Colorado River water rights in trust for its water
users.
W-4 Optimize and sustain use of Colorado River entitlements through
reservoir storage partnerships and strategies.
W-5 Ensure new development covers a fair share-of-cost associated with
infrastructure capacity improvements necessary to accommodate any
increase in demand.
W-6 Develop and implement a long-range capital improvement plan for
aging water delivery system infrastructure.
W-7 Review, on a regular basis, the cost of water delivery service for water
rate adequacy.
IMPERIAL IRRIGATION DISTRICT
52
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
B. IRRIGATION DRAINAGE FACILITIES
Irrigation drainage facilities in the Imperial Valley are within the jurisdiction of the IID. The
district operates and maintains an agricultural drainage system consisting of more than 1,450
miles of surface drains. The primary purpose of planning, designing, constructing and
maintaining drainage facilities is to collect runoff from irrigated lands. Water entering the IID
drainage system may originate from the following five sources: 1) irrigation system seepage
from canals and laterals intercepted by IID drains; 2) operational discharge which is unused
water that travels through the delivery system); and 3) on-farm tailwater (water passing tile
drains for the purpose of leaching), 4) on-farm tailwater runoff (surface water runoff that
exceeds infiltration), and 5) storm water runoff which is surface storm water that exceeds soil
infiltration rate or storage capacity. IID’s drains, as a matter of necessity, also collect treated
wastewater discharge, and surface runoff from some non-agricultural uses. IID drains are not
designed or intended to collect stormwater from urban land uses. The design and operation
of urban stormwater and flood control lies within the respective jurisdiction with the land use
authority. IID drainage facilities are designed to collect irrigation run-off and are not designed
or intended to collect and transport stormwater.
IID has an extensive drainage collection system of nearly 1,300 miles. The drains collect
irrigation water and discharge into the New River, Alamo River or directly into the Salton Sea.
Highly contaminated waters from Mexico (five-year average of 150,000 acre-feet annually)
also enter the Imperial Valley via the New River. All drainage flows ultimately discharge into
the Salton Sea, averaging just under 1,000,000 AFY and can contribute to the degradation of
water quality both within IID drains and within the Salton Sea without proper management.
IID initiated a voluntary TMDL Compliance Program to monitor the levels of pollutants within
Imperial Valley watersheds.
1. Performance Standard for Drainage Facilities
Drainage Facility Standard-For the purpose of collecting and conveying agricultural
discharge, the district is obligated to provide drains at a sufficient depth, generally four
to ten feet, to accept subsurface discharge from over 32,000 miles of tile drains
underlying nearly 475,000 acres of farmland in the Imperial Valley. Where a drain cannot
be maintained at sufficient depth, the district provides and maintains a sump and pump.
The limit on drainage received by IID facilities is set at five percent of the total volume of
water received within a billing period. The maximum allowable flow rate is to be ten
percent of the maximum flow rate of the water received, but shall not exceed 672 gallons
per minute (1.5 cfs). These limitations are set as guidelines and individual contracts may
be written with a water customer.
Discharge Drainpipe
IMPERIAL IRRIGATION DISTRICT
53
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
For non-agricultural discharges into IID drains, the requirements of the Colorado River
Basin Water Quality Control Plan, Federal Emergency Management Agency and
requirements established by the Imperial Irrigation District for storm water runoff are
applicable. As authorized by the Clean Water Act (CWA), the NPDES Permit Program
controls water pollution by regulating point sources that discharge pollutants into waters
of the United States through Best Management Practices. All new development is
required to comply with these standards and to retain storm water on site for a minimum
of 72 hours prior to releasing it into an approved storm water conveyance system.
Conveyance out of the retention basins is restricted by IID via the use of 12" diameter
pipes. The outflow restriction into IID drains can result in detention times in excess of 72
hours (three days). Detention for longer than three days requires the implementation of
a mosquito abatement program in order to comply with the County Health Department
standard.
Water Quality Standard- IID has a Drain Water Quality Improvement Plan (DWQIP) that
was prepared in 1994. The Plan was updated in 2016 to address Total Maximum Daily
Loads (TMDLs) per the Federal Clean Water Act in order to improve the water quality of
impaired surface waters (i.e. streams, rivers, lakes, etc.) that do not meet water quality
objectives and revamped in 2022 as the Surface Water Monitoring Program and Quality
Assurance Project Plan. A TMDL is the amount of a particular material that a water body
can absorb while remaining safe for people and wildlife. A Board Order20 of the discharge
requirements was issued in 2021 by the Regional Water Quality Control Board for
agricultural dischargers and drain maintenance operators in the Imperial Valley. The
Order requires IID to implement a water quality monitoring and reporting program
(please refer to the IID Drain Water Quality Improvement Plan for more detailed
information).
A total of six TMDLs have been adopted for surface water bodies in the Imperial Valley.
Four of them are for the New River to address pathogens, sedimentation/siltation, trash,
and dissolved oxygen. One is for the Alamo River to address sedimentation/siltation.
Another is for Imperial Valley Drains to address sedimentation/siltation. TMDL reporting
began in July 1, 2004 and additional independent reporting under the Imperial Valley
Coalition will begin in July 1, 2024. The final Sediment TMDL Numeric Target is as follows:
➢ New River total suspended solids (TSS) concentration of 243 mg/L
➢ Alamo River total TSS concentration of 180 mg/L
➢ Imperial Valley Drains total TSS concentration of 200 mg/L
20 In December of 2021, the Regional Water Quality Control Board adopted Order R7-2021-0050-03, “General Waste Discharge
Requirements for Discharges of Waste from Irrigated Agricultural Lands for Dischargers That Are Members of a Coalition Group
in the Imperial Valley, Imperial County”.
IMPERIAL IRRIGATION DISTRICT
54
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
2. Irrigation Drainage Facility Planning and Adequacy Analysis
Water flows from the irrigation distribution system to farmland and then discharged into
IID’s drainage system. IID’s agricultural drainage facilities were not designed for, and are
not managed for, non-agricultural discharges, flood, or storm water management
purposes. As previously noted, all non-agricultural urban areas in the Imperial Valley,
through a permit process, may be allowed to discharge into IID drains when sufficient
capacity exists. Discharge may drain into the New River or Alamo River, both of which are
tributaries to the Salton Sea and where strict regulations apply.
a) Inventory of Existing Irrigation Drainage Facilities
IID operates and maintains an agricultural drainage system consisting of more than
1,450 miles of surface, gravity flow drains as referenced in Table D- 1 IID Drainage
System. The drainage system is designed to collect IID’s operational discharge,
agricultural tilewater and tailwater from thousands of miles of subsurface (tile) drains
that growers have installed and operate independently. To that end, 750 surface and
subsurface drainage pumps, and approximately 430 control structures are installed
along the drainage system.
Table D- 1 IID Drainage System
Total Length in
System Earthen Concrete Lined Piped
Miles
All-American Drains 37.410 0.000 12.700 50.11
Drains 1,296.264 1.180 108.996 1,405.44
Total Drains 1,333.674 1.180 121.696 1,456.55
Source: 2021 Water Conservation Plan and Pipeline Projects MWA from Water Department 2021-2023.
IMPERIAL IRRIGATION DISTRICT
55
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
The All-American drains are designed to collect seepage water from the All-American
Canal rather than irrigation discharge. The All-American drains initiated construction
in 1947 as part of a seepage recovery program. The program returns seepage water
with sufficiently low salinity levels back into the respective main canals. The East
Highline Canal began this program in 1967 and it is further discussed under
Conservation Programs of this Service Area Plan.
Personnel and Vehicles-The Water Department personnel and vehicles (excluding
the Agricultural Water Resources Section and Environmental Mitigation Section)
support all irrigation drainage system operation and maintenance, to some level. The
Southend O&M Section personnel (127 FTE) and Northend O&M Section personnel
(109 FTE) inclusive of their 164 vehicles, are assigned to either the water distribution
system or drainage collection system operations. Additionally, the Water Quality
Programs section (12 employees and 9 vehicles) plays a critical role in drain adequacy.
b) Adequacy of Existing Irrigation Drainage Facilities
Drain Capacity Adequacy-The current IID drain facilities are adequate and able to
satisfy the service demand from existing agricultural farmland runoff. Since IID has no
intention of expanding raw water territories beyond the existing agricultural service
footprint, and industrial/commercial development is restricted from discharging into
District drain facilities, IID has no plans for additional drainage facilities to meet the
current and projected services demands.
IID has further communicated to local jurisdictions an interest in abandoning all
facilities within incorporated urban areas which do not actively provide a service to
agricultural operations. Under these circumstances each city would take over the
respective drain systems. Compliance with the regulatory requirements of new
development discharge and storm water facilities are solely borne to the
developer/permittee in order to ensure new urban development provides for
adequate on-site retention of storm water to mitigate against storm water impacts
to properties and the IID system consistent with their respective flood control plans.
Drain Water Quality- IID monitors drain quality at fixed sampling sites. IID performs
monthly water quality monitoring constituents of concern at 17 locations – incoming
flow at All-American Canal Drop 4, and drainage water in nine river and seven drain
sites throughout the water service area. (Please refer to Figure 6). IID reports the
results to the Regional Board and provides flow data for 56 sites – incoming flow at
AAC Mesa Lateral 5, and drainage flow for seven river and 48 drain sites throughout
the Imperial Valley. IID also supplies the Regional Board with a list of current owners
and tenants of agricultural land on a semi-annual basis. Table D- 2 summarizes IID’s
monitoring practices as of 2024.
IMPERIAL IRRIGATION DISTRICT
56
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
Figure 6 Water Quality Monitoring Sites
IMPERIAL IRRIGATION DISTRICT
57
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
Table D- 2 IID Drain Monitoring Practices
Drain Water Location 1 Practice Frequency
Alamo River Outlet at Salton Sea TDS, pH, Ca+, Mg, Na+K, CO , HCO , SO , Cl,
3 3 4 Monthly
New River Outlet at Salton Sea Temperature
TMDL Drain Water Location² Practice Frequency
Major drains:
5 to Alamo River DO, EC, pH, selenium, TSS, NH -, NO -, NO ,
3 2 3
2 to New River Kjeldahl-N, Total N, Total P, Total Hardness, Ca+,
Monthly
River locations: Mg, Total Alkalinity, HCO 3 +CO 3, Cl-, SO 4 , E. Coli,
6 in Alamo River BOD, TDS
3 in New River
1 Collected by IID; analysis by ATS Labs, Inc. Brawley, CA
² Collected by IID; analysis by BABCOCK Labs, Inc., Riverside, CA.
Field measurements were collected (water temperature, pH, dissolved oxygen,
electrical conductivity, and turbidity), and water samples collected and analyzed for
general chemistry (TSS, turbidity, hardness, and alkalinity), as well as chemical species
of nutrients (nitrogen, phosphorus, sulfur). This monitoring program and the data
generated from it is utilized to verify that individual drains meet water quality
standards, identify problematic areas, and to model and calculate the concentration
of various chemical species.
The 2023 Annual Monitoring Report for Total Suspended Solids (TSS) Levels showed
that five of the seven main drain sites achieved the 200 mg/L goal. Only three of the
nine river locations achieved the 200 mg/l goal. Moving forward, under
implementation of the new Board Order, members of the Imperial Valley Coalition
Group will need to submit a Report of Waste Discharge to the Colorado River Basin
Water Board and obtain individual Waste Discharge Requirements. This added layer
of accountability is expected to see improved drain water quality during the next
planning period.
c) Future Demand for Irrigation Drainage Facilities and Planned Facilities
Urban sprawl may result in a net decrease of IID owned and operated drainage
facilities designed to capture irrigation runoff. As future urban development occurs,
storm water drainage systems must be installed and constructed into the project
area by the developer/permittee to ensure adequate collection and conveyance of
runoff. The type and extent of the development proposed will affect the demand
of facilities. A significant increase in the amount of impervious surfaces will result
in a greater amount of surface runoff. The exact size and location of future facilities
will be determined at the time development is proposed and processed through
each respective city or the county. All future development must continue to comply
with IID policies regarding temporary retention of storm water to reduce the impacts
to the IID drains.
IMPERIAL IRRIGATION DISTRICT
58
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
Storm water runoff as well as other contributing factors has degraded both the
New River and Alamo River. The recently updated Water Quality Control Plan for
the Colorado River Basin Region prepared by the California Regional Water Quality
Control Board contains strict requirements for the water quality conveyed into
these rivers. Future facilities must be designed to adhere to the latest pollution
control devices and NPDES requirements.
According to the Water Department Five-Year Capital Improvement Plan, IID
continues to plan for and budget for the annual investment into irrigation drainage
facilities. Slightly over $3 million is budged for, on an annual basis, for capital
improvements to drain facilities.
d) Opportunities for Shared Irrigation Drainage Facilities
IID’s irrigation drainage facilities are also used by non-agricultural operations. The IID
drainage system provides a drainage outlet for each governmental subdivision of
approximately 160 acres, but is not designed to convey storm water runoff from
urbanized development. The District will continue to maintain all drain facilities that
have a dual purpose of serving the agricultural community and collecting storm-water
discharge from properly permitted entities. At this time, the management of these
shared drainage facilities is effective and is not expected to change in the near future.
Administrative services related to drainage operations is also shared. In 2014, as
previously noted, the State Water Resources Control Board determined that the
existing Conditional Prohibition of Waste Discharges was not a sufficient mechanism
to address non-point source pollution in the state. Instead, they mandated the
implementation of Conditional Agricultural Waivers which were essentially the same
as a Prohibition, but included an annual fee (Ag Waiver fee) that would be imposed
upon the discharger. The Ag Waiver fees could be paid directly by the discharger
($1.27/acre or more), or, a voluntary coalition could be created (as approved by the
state), and implemented by a local entity, which would reduce the mandatory fee
rate substantially ($0.75/acre) for all coalition participants. In 2015, after discussion
between the Imperial County Farm Bureau and the IID, it was agreed that the two
entities would form the Imperial Irrigation District/Imperial County Farm Bureau
Coalition Group Compliance Program. As a service to the Coalition, the District agreed
to invoice all Imperial Valley land owners within the Salton Sea drain shed that were
required to pay discharge fees. The IID fees are collected as a pass-through service (at
no charge), and submits the collected funds to the State to fulfill the land owners’ fee
obligations at the discounted rate.
IMPERIAL IRRIGATION DISTRICT
59
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
e) Phasing of Irrigation Drainage Facilities
The Imperial Irrigation District has no plans of expanding its irrigation service area
thus there is no need for new expanded drainage facilities. IID, however, does
continue rehabilitating, or replacing, some of its existing drainage facilities, control
structures, inlets, and outlets on a continuous basis.
Short Term Improvements (Under 5 Years)
• Several Inlet and Outlet Drain Control Structures
• Vail 5A Drain Pump Station
• Mulberry Drain Pipeline
• Drain Crossing over HWY 115
• Several Large Drainage Projects
5-10 Year Improvements
• Redwood over Rose Outlet Drain Flume Replacement
• Control Structures, Inlets and Outlets
• Continuance of Large Drainage Projects
10-15 Year Improvements
• Continuance of Drainage Control Structures
• Continuance of Large Drainage Projects
3. Mitigation for Irrigation Drainage Facilities
The Imperial will continually monitor the existing irrigation drainage facilities to ensure
the facilities are operating at an adequate level. The Imperial Irrigation District should
further implement the following mitigation measures for drainage facilities:
D-1 All future non-agricultural development shall be required to construct
storm drain facilities in accordance with the design standards of the
respective jurisdiction and the Engineering Section of the IID Water
Department and obtain an encroachment permit from IID before it is
allowed to convey storm water into existing irrigation drains owned and
managed by IID.
D-2 All future non-agricultural development shall retain storm water on-site,
or within existing retention basins, to restrict storm water flow for a
minimum period of 72 hours before discharging into IID facilities.
D-3 All future non-agricultural development shall ensure compliance with all
local, state and federal rules and regulations related to the discharge of
storm water.
IMPERIAL IRRIGATION DISTRICT
60
2025
SERVICE AREA PLAN IRRIGATION DRAINAGE FACILITIES
D-4 All future non-agricultural development shall provide improvements
constructed pursuant to best management practices as referenced in
the California Storm Water Best Management Practices Handbook.
D-5 IID shall continue to implement the Drain Maintenance Checklist prior
to scheduling drain maintenance to reduce unnecessary drain cleaning
which contribute to re-suspension of the drain’s bottom sediments.
D-6 Continue to enforce the Vegetation Management Plan developed to
train equipment operators and weed spray contractors on the proper
control of vegetation within drains to help maintain drain bank
stability, reduce suspended sediment, and reduce unnecessary
cleaning.
D-7 Encourage excavator-mounted GPS Units which allow excavator
operators to conduct drain cleaning operations from upstream to
downstream to filter nuisance vegetation before the vegetation is
removed and help eliminate over-excavation.
D-8 Actively enforce Regulation No. 39 requiring that water users maintain
a properly functioning tailwater box to prevent erosion at the tail end
of their field and in the receiving drain.
D-9 Continue to monitor delivery and tailwater under the On-Farm
Conservation Verification Program to ensure that excessive tailwater
discharge does not occur during irrigation events and that tailwater
boxes are in good condition.
D-10 Any need for drain abandonment will be addressed by the land use
authority and IID during the CEQA review process and/or permitting
phase of any new non-agricultural development and approved by the
governing bodies.
IMPERIAL IRRIGATION DISTRICT
61
2025
SERVICE AREA PLAN ENERGY SERVICES
C. POWER FACILITIES
IID entered into the electrical power business in 1936 to utilize the hydroelectric generation
potential of the All-American Canal. By 1943, the district had acquired the electrical system
and certain properties of the California Electric Company in Imperial County and parts of
Riverside County becoming the source of electric energy for a 6,471 square-mile service area,
including all of the Imperial Valley, parts of the Coachella Valley in Riverside County and a
small portion of San Diego County as an emergency response partner. IID’s Power
Department, as of January 2024, provides electric power to more than 163,000 accounts (an
increase of approximately 5% over five years when compared to 154,465 accounts reported
in 2019) As the sixth largest utility in California, by peak load, IID Power controls more than
1,100 megawatts of energy derived from a diverse resource portfolio that includes its own
generation, as well as long- and short-term power purchases.
As a Balancing Authority, IID must ensure the reliability of the electric system within its
geographical boundaries by, among other requirements, maintaining a continual balance
between electric resources and electricity demands. IID is subject to the reliability, safety and
security regulations promulgated by the Federal Energy Regulatory Commission (FERC) and
enforced by the Western Electricity Coordinating Council (WECC).
As a consumer-owned utility, IID Power works to efficiently and effectively meet customers’
demands at the best possible rates, tying the IID area’s low-cost of living directly with low-cost
utilities. This must be met while making regulatory compliance-based decisions and strategic
expansion-based decisions, currently and in the future, with system reliability as a foundational
driving factor.
Due to the nature of the organization and interdependency of IID as a local organization along
with numerous federal, state and local agencies and business entities, IID is cognizant and
sensitive to the various and often differing goals of these external entities. Both federal and
state-level policy drivers must be successfully integrated into every goal and objective. These
policy and macro drivers form a fundamental foundation for the rest of the modeling
assumptions of build-out, price formation and outputs used in energy resource planning. The
district contracted Ascend Analytics to complete the energy resource planning modeling using
the PowerSIMM™ stochastic modeling software platform for IID’s 2024 Integrated Resource
Plan. These macro-level drivers are noted in the proceeding diagram which are further
detailed under IID’s 2024 IRP.
IMPERIAL IRRIGATION DISTRICT
62
2025
SERVICE AREA PLAN ENERGY SERVICES
Figure P 1 Fundamental Modeling Framework (Ascend Analytics)
1. Performance Standards for Power Facilities
Complying with energy efficiency laws and environmentally related requirements is an
important objective for IID and a factor on the performance standards for energy
generation, transmission and distribution facilities. Detailed discussion on energy
conservation and emission reduction standards, however, are not discussed in this
chapter, but rather located under the Conservation Programs chapter of this SAP.
Since IID is not a part of the CAISO, IID has the responsibility to provide reliable power to
all of its customers, even in extreme events. This is a challenge, since IID is interconnected
to several other Balancing Authorities, and this has an impact on the physical flow of
electricity within the IID service area. IID works conscientiously to assure that the system
operates properly under all conditions to the best of its ability. The effectiveness of the
power system reliability is disturbed by many operational characteristics of generation
facilities, transmission/ distribution interconnection strategies and other uncontrollable
factors, thus system reliability is a foundational driving factor for all decisions made by
IID. As a BA, the district has the obligation to:
• Match generation to load;
• Maintain scheduled interchanges with other Balancing Authorities;
• Maintain the frequency in real-time of the power system;
• Help/cooperate interconnection regulate and stabilize alternating current
frequency;
• Avoid overloading transmission segments;
• Avoid inadvertent exchange of energy.
IMPERIAL IRRIGATION DISTRICT
63
2025
SERVICE AREA PLAN ENERGY SERVICES
Reliability Standards- Reliability Standards are the planning and operating rules that IID
follows to ensure the most reliable system possible. These standards are developed by
the industry using a balanced, open, fair and inclusive process managed by the NERC
Standards Committee. NERC develops and enforces reliability standards; assesses
adequacy annually via a 10-year forecast, and summer and winter forecasts; monitors the
bulk power system; and educates, trains and certifies industry personnel. IID’s ability to
balance its load and resources in the current environment with the solar resources on-
line must be compliant with NERC balancing reliability standards. Specifically, Control
Performance Standard No 1 and 2 (CPS1 and CPS2) measures21.
Power Generation Facilities- IID produces power supply locally, using efficient, low-cost
hydroelectric facilities, steam-generation facilities, as well as several natural-gas turbines
and some solar photovoltaic projects. The design life of a typical energy generation facility
is 30 years. The desired performance standard for IID is to match its generation level to
its service load. IID does not have any planned generation targeted for export as all energy
export is for reliability or emergency purposes and is developer driven.
As a balancing authority, the IID is required to have generation resources providing
spinning reserves, non-spinning reserves, operating reserves and planning reserves,
totaling about 15 percent of the forecasted load. The actual load within the IID service
area has experienced a slight decrease over recent years. In 2023, IID had approximately
3,422 GWh in energy sales, a decline from 2022, and a modest decrease when compared
to 3,738 GWh sales in 2017. The energy requirements consist of sales to end use
customers and make-up energy for any system losses. IID is set to procure additional solar
resources in response to forecasted loads based on projected growth.
Power Storage Facilities- AB 2514 (Skinner, Chapter 469, Statues of 2010), as amended
by AB 227 (Bradford, Chapter 606, Statures of 2012) and as codified at Public Utilities
Code Sections 2835-2839 and Section 9506, requires local publicly owned electric utilities,
such as IID, to determine targets for procurement of viable and cost-effective energy
storage. California’s three investor-owned utilities are required to procure at least 1,325
MW of battery storage and to be installed no later than 2024. Although IID is a publicly
owned facility, energy storage is becoming an important resource as variable generation
resources such as solar and wind are increasingly adopted and integrated into the
district’s portfolio. Energy storage availability can address the district’s concern regarding
overgeneration and critical for capacity expansion.
Power Transmission Facilities-The Federal Energy Regulatory Commission (FERC)
requires each public utility transmission provider to offer intra-hourly transmission
21 CPS is a frequency-sensitive evaluation of how well a Balancing Authority’s demand requirements were met for all control
areas in an interconnection. CPS1 is based on a 12-moth rolling average and should not be less than 100 percent. CPS2 takes
over a clock ten minute period (six non-overlapping periods per hour) and should not be less than 90%.
IMPERIAL IRRIGATION DISTRICT
64
2025
SERVICE AREA PLAN ENERGY SERVICES
scheduling to ensure charges for energy imbalance services are just and reasonable. The
intra-hour scheduling provisions provide opportunity for variable energy resources to
align the energy schedules with forecasted production as conditions change within the
hour.
Power Distribution Facilities- Power distribution facilities standards are based on
reliability and ability to support future load growth from new development. A system’s
effectiveness, stability and reliability in providing power services is critical as a balancing
authority. Reliability is the consistency of a measure of service when it produces similar
results/uninterrupted services under consistent conditions.
2. Power Facility Planning and Adequacy Analysis
In an effort to align the Power Department in a manner that more efficiently accomplishes
the goals of the Strategic Plan, the Power Department has undergone reorganization
which resulted in the reallocation of resources and numerous positions to various units
across separate energy sections. These changes resulted in the Power Department’s
addition of numerous sections and units, with responsibilities as follows:
• Power Administration Section is responsible for the oversight and management
of all operations, maintenance, engineering services, reliability and accountability
for the Power Department. This section interfaces with the Board of Directors,
general manager, and the public to ensure effective communication and proper
administration of policies and procedures and oversees the Power Department
Strategic Plan and ensures that all other sections and units within the department
are meeting the established goals and objectives.
• Power Transmission Planning Section is responsible for identifying the need for
new transmission, including upgrades and maintenance of existing transmission
facilities. The unit is also responsible for design of new facilities.
• Power Operations & Resources Section is responsible for the safe and reliable
operation and dispatch of the district’s generation, transmission, and distribution
systems. This unit consists of seven sub-sections:
1) Public Benefits and Regulatory -is responsible for the development of
strategic business relationships to promote growth/change and support
renewable energy development and to protect the balancing authority
by leveraging existing assets. This section designs and implements
programs to encourage customer conservation as a cost-effective
alternative.
2) Project Management and Substation Operations- is responsible for
managing and overseeing all capital projects and assisting the
IMPERIAL IRRIGATION DISTRICT
65
2025
SERVICE AREA PLAN ENERGY SERVICES
department with planning and development initiatives in order to meet
schedules, cost and quality of deliverables. This sub-section is responsible
for existing substation construction, maintenance and repairs.
3) System Operations - is responsible for the safe and reliable operation and
dispatch of the district’s Balancing Authority, generation, transmission
and distribution systems. System Operations is also responsible for
monitoring NERC and WECC reporting requirements and submission of
compliance filings.
4) System Engineering & Protection- identifies the need for new
transmission and distribution resources, upgrades and maintenance of
existing transmission and distribution facilities. Additional responsibilities
include the designing of communications networks for system protection
circuits and relay protection devices on all district transmission,
distribution and generation equipment.
5) Power Supply & Trading - is responsible for aligning the Power
Department’s financial goals with its customer and system operations
requirements.
6) Energy Production- is responsible for providing cost competitive, reliable
and environmental compliant bulk electricity.
7) Office of Emergency Services provides emergency and disaster
preparedness services for all district department. Those services include
emergency and disaster preparedness, mitigation and recovery through
emergency operation plan development, training, exercises and mutual
aid implementation.
• Infrastructure and Customer Project Services Section is responsible for
maintaining the integrity and reliability of existing transmission and distribution
facilities and construction of new overhead and underground assets including
customer projects. The section is comprised of two subsections: 1) Construction
& Maintenance and 2) Power Troubleshooting.
• Customer Operations La Quinta Section is responsible for maintaining the
integrity and reliability of existing distribution facilities and construction of new
overhead and underground assets including customer projects. This Section is
comprised of five sub-sections as follows:
1) Construction and Maintenance -is responsible for the physical
construction or maintenance of transmission and distribution systems.
2) Power Troubleshooting- is responsible for first response to system
disturbances and restoration.
IMPERIAL IRRIGATION DISTRICT
66
2025
SERVICE AREA PLAN ENERGY SERVICES
3) Meter Shop- is responsible for installation, maintenance and testing of
meters.
4) Distribution Planning & Engineering – ensures the availability of reliable
distribution resources to deliver energy to customers and identifies the
need for new distribution resources, upgrades and maintenance of
existing distribution facilities. Additional responsibilities include the
design of new facilities.
5) C&M Safety & Compliance is responsible for developing, preparing,
implementing and providing training in regards to standard operating
procedures and work practices to ensure the Power Department
complies with state and federal safety rule and regulations.
a) Inventory of Existing Power Facilities
The district owns and operates the electrical system, which includes generation,
storage, transmission and distribution facilities. Substations and transformer
components are also an integral part of the energy system.
Power Generation Facilities- IID maintains a steady focus on diversifying its portfolio
of resources to serve load, including purchases and internal generation. The following
subsections are a brief overview of IID’s generation resource portfolio, which is in
excess of 1,100 MW inclusive of hydroelectric, thermal, geothermal, biomass, nuclear
and solar generation and are anticipated to occur requiring the addition of new
resources to meet such demand. Figure 7 below details the distribution which are
further described in the sub-sections that follow.
Figure 7 IID's Generation’s Resource Portfolio
IMPERIAL IRRIGATION DISTRICT
67
2025
SERVICE AREA PLAN ENERGY SERVICES
• AAC Hydroelectric Resources- IID has a number of small hydroelectric
facilities located on the All-American Canal and nearby branches. The
hydroelectric units have a combined rating of about 85MW, although, due to
seasonal water flows the summer capacity rating is around 32MW as they are
directly dependent upon the needs of the local area agricultural crops.
Therefore, production will vary from season to season, but over the course of
the year, the average hourly output from the hydroelectric facilities is about
32MW. IID’s hydroelectric projects are considered green resources and the
annual energy production from these units is approximately 270,000-280,000
MWh. The unit names, technology and performance are summarized in Table
P- 1 IID Hydroelectric Generation Plants/units, January 2023.
• 13FF
Table P- 1 IID Hydroelectric Generation Plants/units, January 2023
Operating/
Generator
Commercial Project Operator/ Contracted
Name Nameplate
Operation Location Capacity
(MVA)
(MW)
Drop 1 Unit 1 1984 Not Listed IID/All-American 2
Drop 1 Unit 2 1984 Not Listed IID/All-American 2
Drop 1 Unit 3 1984 Not Listed IID/All-American 2
Drop 2 Unit 1 1953 6.25 IID/All-American 5
Drop 2 Unit 2 1953 6.25 IID/All-American 5
Drop 3 Unit 1 1941 5 IID/All-American 5
Drop 3 Unit 2 1966 5 IID/All-American 5
Drop 4 Unit 1 1950 12.5 IID/All-American 10
Drop 4 Unit 2 2006 12.5 IID/All-American 11
Drop 5 Unit 1 1982 2.5 IID/All-American 2
Drop 5 Unit 2 1982 2.5 IID/All-American 2
East Highline Unit 1 1984 3.019 IID/All-American 2.4
Pilot Knob Unit 1 & 2 1957 20 IID/All-American 16.5
Double Weir Unit 1 2005 0.226 IID/Central Main 0.18
Double Weir Unit 2 2005 0.226 IID/Central Main 0.18
Turnip Unit 1 1964 Not Listed IID/Westside Main 0.42
Boulder Canyon 1936 2,080* WAPA/Hoover Dam 5
Parker Davis 1954 240* WAPA/Parker Dam 26-32
TOTAL 106 MW
Source: IID 2021 Service Area Plan and updates from Integrated Resource Plan 2024; *U.S.B.R. is in MW
IMPERIAL IRRIGATION DISTRICT
68
2025
SERVICE AREA PLAN ENERGY SERVICES
• Western Area Power Administration (WAPA) Parker-Davis Dam- IID was
allotted a portion of the upgraded Hoover Dam/Boulder Canyon Project
equivalent to 2 MW. IID also has an entitlement of 32.6MW (summer) in the
Parker-Davis Hydroelectric Project (Parker-Davis) in western Arizona. Energy
from Parker-Davis is provided by WAPA at the rate of 3,679 MWh per MW of
capacity per month. Parker-Davis energy can be primarily used during the on-
peak periods, although a small portion of the energy must be scheduled
during the off-peak periods due to water management requirements of the
Parker and Davis dams by WAPA. While Parker-Davis is a hydroelectric
project, it is not considered a renewable project by the state for RPS
requirements. Hydroelectric projects must be less than 30MW to qualify as
renewable projects. Parker-Davis capacity is a source of inexpensive capacity
and energy.
• Internal Thermal Generation- IID owns thirteen thermal generation units
within its service territory, the Yucca generation facility in Yuma and also nine
multi-unit hydroelectric facilities. The unit names, technology and
performance are summarized in Table P- 2 IID Thermal Generation
Plants/Units, January 2023. The Units produce just under 600 MW.
Table P- 2 IID Thermal Generation Plants/Units, January 2023
Generator
Commercial
Unit Name Nameplate Fuel Type Location
Operation
(MVA)
ECGS Unit 2-1 1993 75.8 Dual Fuel El Centro, CA
ECGS Unit 2-2 1993 105.20 Dual Fuel El Centro, CA
ECGS Unit 4 1968 67.60 Natural Gas El Centro, CA
ECGS Unit 30 2013 77.5 Natural Gas El Centro, CA
ECGS Unit 31 2012 54.00 Natural Gas El Centro, CA
ECGS Unit 32 2012 54.00 Natural Gas El Centro, CA
EC Mobile Mall* 2021 21.00 Diesel El Centro, CA
EC Mobile Terminal* 2021 21.00 Diesel El Centro, CA
Bravo Mobile* 2021 21.00 Diesel Calexico, CA
Niland Unit 1 2008 43.70 Natural Gas Niland, CA
Niland Unit 2 2008 42.60 Natural Gas Niland, CA
Rockwood Unit 1 1979 23.20 Dual Fuel Brawley, CA
Rockwood Unit 2 1980 23.00 Diesel Brawley, CA
Coachella Unit 1 1973 18.60 Dual Fuel Coachella, CA
Coachella Unit 2 1973 19.00 Dual Fuel Coachella, CA
Coachella Unit 3 1974 18.3 Dual Fuel Coachella, CA
Coachella Unit 4 1976 18.00 Dual Fuel Coachella, CA
Yucca CT 21 1979 18.90 Diesel Yuma, AZ
Yucca Steam 1959 74.00 Natural Gas Yuma, AZ
Source: IID 2021 Service Area Plan and updates from Integrated Resource Plan 2024. The Power
Purchase Agreement for the mobile units expire in September of 2025.
IMPERIAL IRRIGATION DISTRICT
69
2025
SERVICE AREA PLAN ENERGY SERVICES
• Geothermal Generation Resource- IID is uniquely located to take advantage
of geothermal generation within the IID service territory. Since 2016 IID has
contracted with four geothermal projects in the Imperial Valley for a total of
117 MW: CalEnergy Operations (BHE); Heber 1 Geothermal; Hell’s Kitchen
Geothermal Project; and Ormat Ormesa. These facilities are either
operational or expected to be operational within the five-year planning
period.
• Yucca Steam Plant -One of IID’s most important units is the Yucca Plant in
Yuma, Arizona. This steam unit has a nominal rating of 75MW (an operational
rating of 70MW) and has been used for energy and ancillary services,
including regulation, on the IID’s system. There is also an associated gas-fired
turbine (19.7MW) at Yuma that is seldom used due to the poor heat rate of
the unit. The Arizona Public Service electric company operates the Yucca
Plant under an operating agreement with IID. In 2024, the district was in the
process of retiring its owned portion of the aging Yucca Steam Plant.
• Palo Verde Nuclear Generating Station- IID has a small entitlement of
capacity in each of three units at the Palo Verde Nuclear Generating Station
(PVNGS). IID’s total (delivered) capacity is 14 MW (5 MW from each of the
three PVNGS units less losses). One of the greatest benefits of nuclear
generation is the lack of any greenhouse gas emissions. Energy from PVNGS
is expensive compared to current market prices although the reduction in
greenhouse gas emissions helps the IID’s efforts to meet GHG emission levels.
• Solar Photovoltaic Generation Resources- The Imperial Valley is one of the
best places in California to install solar panels, many of which have been
constructed and are under operation.
• Table P- 3 identifies solar projects under, contracted to provide energy to the
IID system and now a part of the district’s portfolio.
IMPERIAL IRRIGATION DISTRICT
70
2025
SERVICE AREA PLAN ENERGY SERVICES
• 113FF
Table P- 3 Solar Photovoltaic Generation, January 2023
Nameplate
Commercial California
Name Power Factor Capacity
Operation Location
(MW)
Augustine Solar Energy 2009-2012 Coachella PPA (20 yr.) 3.30
Citizens 2019 Calipatria PPA (23 yr.) 30.00
El Centro Solar Park 2013 El Centro PPA (25 yrs.) 20.00
Imperial Solar 2014 Heber PPA (20 yr.) 10.00
Imperial Valley College Solar 2017 Imperial IID Owned 2.54
Midway solar II 2017 Calipatria PPA (25 yrs.) 30.00
SDSU PV 1 2014 Brawley PPA (25 yrs.) 5.00
SEPV East 2017 Dixieland FIT PPA (20 yr.) 2.00
SEPV West 2017 Dixieland FIT PPA (20 yr.) 3.00
Seville No. 2 2016 Ocotillo Wells PPA (25 yrs.) 30.00
IVSC Sun Peak 1 2012 Niland IID Owned 23.00
IVSC Sun Peak 2 2015 Niland PPA (30 yrs.) 20.00
Valencia 1 2017 Westmorland FIT PPA (20 yr.) 3.00
Valencia 2 2020 Brawley FIT PPA (20 yr.) 3.00
Valencia 3 2021 Imperial FIT PPA (20 yr.) 3.00
TOTAL 188 MW
Source: 2024 Integrated Resource Plan
Power Storage Facilities- IID has installed a Battery Energy Storage System (BESS).
The BESS facility is located on the outskirts of El Centro on the site of IID’s El Centro
Generating Station and the adjacent Sol Orchard Solar Farm. BESS is a high power,
low energy resource rated at 30 MVA of power and 20 MWh of energy and consists
of the following components:
- 30 separate battery banks made up of 16 strings of battery modules and
components containing 5,760 Samsung lithium ion battery trays, and associated
battery management system controls and monitoring equipment.
- 30 GE Brilliance inverters rated at 1.25 MVA up to 45 degrees centigrade and 1.1
MVA up to 55 degrees centigrade, with a rated power factor of +/-0.93.
- 30 GE Prolec 1.25 MVA isolation transformers
- GE Mark VIe controllers.
- 8 Trane, 30 ton heat pumps and 4 Trane, 25 ton air conditioning units.
- 34.5kV/92kV substation that interconnects the BESS to IID’s transmission grid.
- BESS building that houses the lithium batteries.
IMPERIAL IRRIGATION DISTRICT
71
2025
SERVICE AREA PLAN ENERGY SERVICES
El Centro Battery Energy Storage System Facility
A Second battery storage facility was constructed within the City of Holtville and
became operational in mid-2024. The Greenbacker Capital Management facility in
Holtville has a 30 MVA capacity and a 120 MWh storage capacity. IID procured those
services under a Power Purchase Tolling arrangement. Tolling agreements are a
common feature of the energy industry. Through these agreements, a buyer will
supply fuel to an electric generator and, in return, the generator will provide power
back to the buyer.
Power Transmission Facilities-The Imperial Irrigation District transmission and sub
transmission system includes over 1,800 miles of overhead transmission lines. IID’s
transmission system consists of 500kV, 230kV, 161kV and 92kV transmission lines.
Whenever IID purchases energy from outside its service territory, it may be required
to purchase transmission capacity. The transmission system is used to wheel bulk
power supplies into the IID’s balancing authority.
• 500kV Transmission system- IID owns a portion of the Southwest Power Link
500kV line that connects the Palo Verde Substation to the North Gila 500kV-
69kV substation near Yuma, Arizona. The line continues from North Gila to the
Imperial Valley 500kV-230kV Substation in El Centro. IID also owns a portion of
the 500kV HANG2 line that connects Hassayampa to North Gila 500kV
substations.
• 230kV Transmission system-There are two major components that comprise
IIDs 230kV transmission system. The first is a single circuit line between IID’s El
Centro Switching Station in El Centro and the Imperial Valley Substation which
is jointly owned by IID and SDG&E. The second is a double-circuit transmission
line that runs south to north through the IID’s service territory and with SCE at
the Mirage substation (KN/KS lines).
IMPERIAL IRRIGATION DISTRICT
72
2025
SERVICE AREA PLAN ENERGY SERVICES
• 230kV Collector system- Also known as KN/KS and runs south to north across
the IID’s service area to SCE’s Mirage Substation. The lines were constructed in
1983 for the primary purpose of delivering over 500MW of “power generating
facilities,” mostly consisting of renewable resources in the IID system and
contracted to SCE at that time.
• 161kV Transmission System -The 161kV transmission system consists of two
separate lines across the IID service area that interconnects several 161kV/92kV
transmission stations. It also provides interconnection to WAPA through two
161kV transmission lines, from IIDs Niland Substation to WAPA’s Blythe
substation and from IIDs Pilot Knob Substation to WAPA’s Knob Substation and
one interconnection from IID’s Pilot Knob to the Arizona Public Service Yucca
Substations.
• 92kV Transmission System-The 92kV transmission/sub-transmission system
consists of multiple transmission lines that provide interconnection to the
distribution substations (92kV/13.2kV) that are periodically constructed and
upgraded to provide transformation capacity to the distribution system.
Substations- IID continued to operate 128 substations in 2023 to serve a 6,471 square
mile electric service territory. The substations transform voltage from high to low, or
the reverse, or perform any of several other important functions for efficient
operation. Although no new substations were constructed over the last five years, a
number of substations implemented capacity improvements.
Power Distribution Facilities-The IID distribution system includes over 4,400 miles
of overhead distribution lines and over 1,700 miles of underground lines.
Power Department Personnel 2024 (474 Total FTE):
• Energy Administration Section (3 FTE)
• Transmission Planning Section (9 FTE)
• Energy Operations & Resources (252 FTE)
• Infrastructure & Customer Project Services (85 FTE)
• Customer Operations La Quinta (125 FTE)
Power Department Vehicles in 2024 (279 Total Vehicles):
• Energy Administration Section (6 Vehicles)
• Transmission Planning Section (0 Vehicles)
• Energy Operations & Resources (96 Vehicles)
• Infrastructure & Customer Project Services (78 Vehicles)
• Customer Operations La Quinta (99 Vehicles)
IMPERIAL IRRIGATION DISTRICT
73
2025
SERVICE AREA PLAN ENERGY SERVICES
IID Hydro Plant – Drop 2
b) Adequacy of Existing Power Facilities & Planned Facilities
Reliability Standards Adequacy- As concluded in IID’s 2024 IRP, the district’s ability
to balance its load and resources in the current environment with the solar resources
on-line is compliant with NERC balancing reliability standards. IID is highly compliant
based on Control Performance Standard No 1 and 2 (CPS1 and CPS2) measures. With
the expectation that IID will add additional solar resources to its portfolio, IID’s ability
to comply with NERC balancing standards may be more of a challenge in the future.
IID limits existing ramping capability for its resources to effectively integrate the
committed solar projects while maintaining reliable operation.
Power Generation Facilities Adequacy – IID’s energy generation of 2,782,233 MWhr
and purchase of 1,116,175 MWhr in 2023 matched the service demand for that year.
IID Generation Hydroelectric and thermal assets are maintained and operated
according to the original equipment manufacturers recommendations.
Improvements are made to each unit based on an identified need for improved
safety, environmental and regulatory compliance, reliability, or efficiency. While IID
has made significant investments in recent years to upgrade its generation assets,
three IID Automatic Generation Control capable units (Yucca Steam Unit, El Centro
Unit 4 and El Centro Unit 2) are 55 years old, 46 years old and 21 years old,
respectively. With a typical plant design life of 30 years and the five plus years to
design, develop and construct a new plant more than 100MW, consideration of future
generation assets is ongoing.
IMPERIAL IRRIGATION DISTRICT
74
2025
SERVICE AREA PLAN ENERGY SERVICES
With the exception of the Niland Units, El Centro Generation Station Unit 2 and the
newly repowered El Centro Generation Station Unit 3 (which are the most modern of
IID’s thermal resources), the rest of IID’s thermal resources are less efficient but
continue to contribute to system reliability. However, IID’s existing resources and
power purchase agreements were sufficient to meet the load for 2022. Portfolio
modeling revealed a capacity shortfall for 2023 and 2024 which was mitigated
through term energy purchases Such shortages are regularly caused by seasonal
peeks and satisfied by seasonal purchases and are anticipated to occur unless new
resources to meet these demands are secured. Identifying the right mix of new
resources to meet IID’s 2024 resource deficit and future demand is critical. IID must
balance with a correct resource mix to maintain compliance with regulatory
requirements and attempting to minimize annual costs. Any needed facilities would
be constructed within IID’s existing Balancing Authority service area.
Power Storage Facilities Adequacy- The existing 20MWh/30 MVA battery storage
facility (BESS) has greatly reduced the volatility of impact from intermittent resources.
The addition of the 120 MWh provides for a combined storage capacity of 140 MWh
and power capacity of 60 MW. IID’s ability to balance its load and resources in the
current environment with the solar resources on-line is compliant with NERC
balancing reliability standards. In fact, IID is highly compliant based on Control
Performance Standard No 1 and 2 (CPS1 and CPS2) measures. With the expectation
that IID will add additional solar resources to its portfolio, IID’s ability to comply with
NERC balancing standards may be more of a challenge in the future. The battery has
an efficiency ratio of 1:.85, so the dispatch price must be at least 15 percent better
when strategically dispatching the battery to address system needs.
Power Transmission Facilities- Consistent with NERC/WECC planning standards, IID
performed an IID Transmission Assessment. This five year and 10-year assessment of
the IIDs electric system was performed to ensure IID has enough generation and
transmission resources to serve its load reliably and to ensure grid reliability at all
demand levels over a 10-year planning horizon under normal and contingency
operating conditions. Below is an overview of findings (see 2024 IRP for more details).
o 92kV CN and CL Transmission System-The 92kV transmission/sub-
transmission system consists of multiple transmission lines that are
constantly constructed and upgraded in order to provide transformation
capacity to the distribution system.
o 92kV ECSS Breakers - Most breakers were found to be overburdened during
the Transmission Planning Assessment requiring replacement.
o 230kV Ramon – Mirage 2 Transmission Circuit- Reliability and system
stability issues were discovered during the Transmission Planning
IMPERIAL IRRIGATION DISTRICT
75
2025
SERVICE AREA PLAN ENERGY SERVICES
assessment. The installation of a second 230kV circuit between Ramon and
Mirage would increase the resiliency of the system and bring performance
within IID and WECC criteria.
o Transmission System- The existing transmission system would not be able to
adequately support the interconnection of merchant generation with the IID
Balancing Authority without transmission system upgrades.
Power Distribution Facilities – As previously stated, the IID distribution system
covers a service territory of over 6,471 square miles and includes over 4,400 miles of
overhead distribution lines and over 1,700 miles of underground lines. The Coachella
Valley area continues to receive a large number of energy requests forecasted at 816
MVA within the next 10-20 year period. Challenges in the Coachella Valley are related
to new loading requirements in addition to the standard development load.
The Imperial Valley has a significant number of potential clients who are seeking
interconnection at the transmission level. The projected load of these potential
customers falls within the range of 25 MW to 40 MW and new substations will be
required since this level of energy demand cannot be adequately met through
distribution feeders alone.
There has been significant interest from residents and businesses in the IID service
territory in distributed/ on-site generation projects. As of October 2023, 131 MW of
distributed capacity has already been installed: an estimated 6,000 systems totaling
83 MW in Coachella Valley and 2,600 systems totaling 48 MW in the Imperial Valley.
IID continues to face some challenges over the impact of these distributed generation
on system losses. IID continues to manage and identify losses found in its power
system. Reduction of these losses allows IID to provide a more efficient, more reliable
and higher quality electric service.
c) Future Demand for Power Facilities & Planned Improvements
The 2023 energy load for IID was 3,755,413 MWh. Three California Energy Commission
load forecasts were presented and the Mid Demand/Mid AAEE-AAFS Case was used
as the starting point for the CASIO peak demand and total energy forecasts applied
under the 2024 IRP. The model Baseline scenario used the Mid load scenario in
comparison with Low load and High load forecasts. A Low Load considers a flatter
future demand consistent with fewer resources needed to satisfy capacity and energy
constraints while the High load scenario considers additional capacity needed to
satisfy the capacity and energy constraints. Annual values for the IID system
demand forecast are provided in Table P- 4 2023 Energy Load Forecast for Low,
Mid and High Demand. The one in ten peak load forecast expectations during the
same time period ranged between 1,167 MW to 1,455 MW.
IMPERIAL IRRIGATION DISTRICT
76
2025
SERVICE AREA PLAN ENERGY SERVICES
Table P- 4 2023 Energy Load Forecast for Low, Mid and High Demand
Annual Energy Demand (MWh)
Year
LOW MID HIGH
2024 3,937,000 4,050,000 4,179,000
2025 3,966,000 4,094,000 4,233,000
2026 3,998,000 4,139,000 4,297,000
2027 4,028,000 4,186,000 4,361,000
2028 4,058,000 4,232,000 4,426,000
2029 4,076,000 4,271,000 4,482,000
2030 4,088,000 4,306,000 4,537,000
2031 4,057,000 4,337,000 4,581,000
2032 4,078,000 4,365,000 4,624,000
2033 4,059,000 4,387,000 4,666,000
2034 4,026,000 4,403,000 4,702,000
2035 3,981,000 4,412,000 4,734,000
2036 3,988,000 4,438,000 4,780,000
2037 3,999,000 4,470,000 4,830,000
2038 4,009,000 4,503,000 4,880,000
2039 4,019,000 4,535,000 4,929,000
2040 4,030,000 4,567,000 4,979,000
Source: 2024 Energy Integrated Resource Plan
Planned Power Generation Facilities- IID has been exploring the currently existing
water infrastructure to develop small hydroelectric facilities. IID is considering the
construction of two low head hydroelectric plants at the West Side Main Check No. 8
and at the Foxglove canal heading.
IID is also investigating several local geothermal projects, both existing facilities and
to be newly developed generating facilities. Additionally, IID continues to assess the
possibility of a public-private partnership with geothermal developers to develop IID-
owned lands with a geothermal potential located near the Salton Sea.
Planned Substations- There are near-term plans for electrical substations throughout
the IID service territory. In response to new development proposed, IID anticipates
up to eighteen (18) new substations, with the majority of the substations in the
Riverside County service area. Any substation and/or related facilities resulting from
growth demand would be constructed within the IID service area and within its the
IMPERIAL IRRIGATION DISTRICT
77
2025
SERVICE AREA PLAN ENERGY SERVICES
balancing authority boundaries. Over the 10- to 20-year horizon, it is anticipated that
approximately 22 new substations will be needed.
Planned Power Transmission Lines- A major new transmission line continues to be
needed in the Imperial Valley with a number of new 500kV transmission lines
proposed by private and public entities. IID will work with a merchant project sponsor
to develop a line that maximizes the benefits to the IID and its ratepayers. IID will
oppose any new lines that threaten its balancing authority rights, or which could
result in stranding the IID’s investment in transmission resources.
On a regional level, IID has established plans with state and regional transmission
planning agencies under the Strategic Transmission Expansion Plan (STEP) that have
materialized, while in other instances separate smaller projects have evolved. The
transmission expansion plans aim to provide plans to achieve diversity, sustainability
and resilience to the bulk transmission system, distribution system and local
communities while improving reliability. The following is a sampling of projects
nearing completion or planned improvements identified through its ten-year
reliability assessment (please see IID’s IRP for detailed listing).
o 92kV CN and CL Transmission System Upgrades -Continued upgrades are
planned to provide transformation capacity to the distribution system. These
consist of reconductoring approximately five circuit miles of wood poles, the
reinforcement of one mile of existing double circuit lattice towers and the
installation of 3.5 miles of fiber optic cable.
o 92kV Grapefruit Switching Station - The Grapefruit Switching Station Project
consists of the design and construction of a new switching station and the
rerouting six transmission lines from the Coachella Switching Station to the
new switching station. The Grapefruit Switching Station will functionally
replace the existing Coachella Switching Station.
o 92kV Avenue 52 Capacitor Bank- A new 92kV capacitor bank will be needed
to cover the NERC standard.
o 92kV ECSS Breaker Replacement- A breaker replacement plan has
incorporated the necessary updates
o 230kV Ramon – Mirage 2 Transmission Circuit- A new 230kV Transmission
circuit between IID's Ramon Substation and SCE's Mirage Substation is being
planned for due to reliability and system stability issues discovered during
Transmission Planning assessment.
o Miscellaneous Network Updates to Transmission System- In addition to the
IMPERIAL IRRIGATION DISTRICT
78
2025
SERVICE AREA PLAN ENERGY SERVICES
projects listed above, numerous network upgrades will be triggered by the
interconnection of merchant generation with the IID Balancing Authority.
These include the following:
✓ 230kV S-line Upgrade of 18.6 miles of transmission line that spans
between the El Centro Substation and the Imperial Valley Substation;
✓ 230kV ECSS Bank No. 5 transformer to be installed in parallel to the
existing Bank No. 4 at the El Centro Switching Station.
✓ 230kV Salton Sea Transmission Line consisting of new construction
for the interconnection of three new geothermal plants in Calipatria
up to the Coachella Valley Substation, with a combined output of
approximately 350 MW.
✓ 92kV R-Line Upgrade of approximately 33.8 miles of transmission line
from Dixieland to Anza Substation.
o Transmission Planning over the next five years anticipates ramped up
coordination with private geothermal developers for an energy export
solution via a new transmission line originating in Imperial Valley with the
goal of maximizing IID’s ability to export energy generated by Independent
Power Producers (IPP’s) out of the District’s BA.
Transmission Facility In Coachella Valley
IMPERIAL IRRIGATION DISTRICT
79
2025
SERVICE AREA PLAN ENERGY SERVICES
Planned Power Distribution Facilities - As previously noted, project needs were
identified for system reliability, customer interconnections associated with
forecasted growth, and new generation distribution demand from residential and
business operations. Much of the previously planned development did not fully
materialize and continue to be identified as planned or removed altogether due to
lack of developer progress. Some of the distribution projects identified by IID within
the 2025-2030 five-year time frame for the Riverside County Service area include the
following in addition to nine energy banks throughout the Coachella Valley:
o (2-28 MVA) Northgate Substation/Majestic Project
o (3-28 MVA) Indio Downtown Substation
o (2-28 MVA) Rio Del Sol Substation
o (2-28 MVA) Gerald Ford Substation
o (2-50 MVA) Classic Club 1 Substation
o (2-28 MVA) Avenue 40 Substation
o (2-50 MVA) Equestrian Substation
o (2-28 MVA) Thermal Airport Substation
o (2-50 MVA) North Indio Substation
o (2-50 MVA) The Ranch Substation
o (2-40 MVA) Cannabis #1 AWZ Coachella Substation
o (2-28 MVA) Avenue 44 Substation
o (2-28 MVA) Old Highway 86 Substation
o (2-28 MVA) Classic Club 2 Substation
o (2-28 MVA) Dinah Shore Substation
o (2-28 MVA) La Entrada North Substation
Similarly, a handful of previously identified substation projects did not materialize
within the Imperial County during the last planning period because no progress was
made by the respective developer. Some of the distribution projects identified by IID
within the 2025-2030 five-year time frame for the Imperial County Service area
include the following substations in addition to two, 25 MVA expansions at the
Gateway Subdivision and at the Heber Subdivision:
o 25 MVA Kloke Substation
o 25 MVA Victoria Ranch Substation
o 25 MVA Lucky Ranch Substation
o 25 MVA Lavinge Distribution Substation
With the implementation of Advanced Metering Infrastructure finalized in 2024, the
District is able to collect data at the customer and panel level, including demand,
voltage, power factor, and billing data. This information is becoming increasingly
important for distribution system planning to determine service levels, loading at
IMPERIAL IRRIGATION DISTRICT
80
2025
SERVICE AREA PLAN ENERGY SERVICES
panels, transformers, loading factors, coincident factors, and voltage levels on circuits
with distributed generation. This data can be studied in combination with SCADA
demand, voltage levels for feeders, and transformer banks at substations. IID expects
to have all AMI meter data available and integrated with DNV GL software for
distribution system planning circuit analysis by the end of 2024.
With current and projected power demands evolving and increasing for residential
and commercial units as well as new industrial proposals and interconnection or
transmission services within IID’s power service area, it is important for developers
to work with IID to establish a comprehensive development plan. IID offers a
Developer Planning Guide and a detailed Customer Project Application in order to
coordinate and respond to residential and commercial project needs: The District
also has a dedicated contracts team for transmission and interconnection services.
Staff collaborates extensively with transmission and distribution planning teams to
ensure the forecast incorporates accurate modeling of anticipated load variations,
system expansion requirements, and demand-side developments within IID’s service
territory. These resources support existing and planned power facility adequacy.
d) Opportunities for Shared Energy Power Facilities
IID has two allotments of large, zero-carbon eligible hydroelectric power through
Western Area Power Administration (WAPA): the first is a 3 MW share of the Boulder
Canyon project and the second is a share of the Parker Davis hydroelectric project,
which is a capacity share that varies between 32 MW in the summer and 26 MW in the
winter. The Imperial Irrigation District also utilizes interregional partnerships in efforts
to plan for extreme events. This includes shared transmission projects that provide
access to various energy markets. IID has a share of the Hassayampa – North Gila 500
kV line No. 2 (HANG2) in Arizona which terminates at North Gila (N. Gila) substation.
This share can provide access to the Palo Verde market.
IID is currently exploring the possibilities of participating in the North Gila – Imperial
Valley 2 project. This project would allow IID to take advantage of its 20% share on the
HANG2 line as well as provide additional reliability benefits. This project would most
likely increase the allowable flow on HANG2 from 500MW to over 1000MW which
would allow IID to move over 200MW through HANG2. IID, in collaboration with other
transmission developers to submit proposals into the CAISO competitive solicitation
process.
IID is also able to participate in Southern California Public Power Authority (SCPPA)
projects. The SCPPA acts as a funding entity for transmission, generation, fuel and
energy efficiency projects. The SCPPA will issue debt for the construction of new
resources and then secure this debt with take-or-pay contracts with project
participants. When IID is a party in a transaction with SCPPA and member utilities, the
IMPERIAL IRRIGATION DISTRICT
81
2025
SERVICE AREA PLAN ENERGY SERVICES
debt falls on SCPPA and therefore there are minimal impacts to the IID’s credit ratings
(an unequivocal advantage of being a member of SCPPA). Another advantage is that
joint action entities like SCPPA allow small entities the opportunity to participate in
larger, cost-effective generation resources.
e) Phasing of Power Facilities
In order to maintain an adequate energy supply to IID customers, IID analyzed and
evaluated all of the relevant supply-side and demand-side resource impacts to the
current and future financial health of the District. The following projects (not all-
inclusive) are anticipated to be implemented during the twenty-year planning period:
Short Term Improvements (Within 5 Years)
• Phased transmission improvements via implementation of STEP
• Coachella Valley Routine Overhead Distribution Program
• Fifteen (15) new substations in Riverside County
• Imperial Valley Distribution Grid Program
• Four (4) new substations in Imperial County
• Two (2) substation expansion in Imperial County (25 MVA each)
• Nine (9) energy storage banks in Riverside County
• Distribution Reliability Enhancements in Imperial Valley
• Multiple Hydroplant Power Generation Unit Refurbishment
• Ongoing El Centro Generation Station Rehabilitation Projects
• El Centro Generation Station Major Wastewater Mitigation
• Yucca Steam Plant Repower
Mid-Term 6-10 Year Improvements
• Phased transmission improvements via implementation of STEP
• Continued Coachella Valley Routine Overhead Distribution Program
• Continued Imperial Valley Distribution Grids Program
• Continued El Centro Generation Station Component Replacement
• Continued Multiple Hydroplant Refurbishment Projects
• Imperial Valley-Strategic Transmission Line Project
• Coachella Valley- Strategic Transmission Line Project
• Yucca Steam Plant Multi-Component Replacement
• Multiple Distribution Projects in Imperial Valley and Coachella Valley
Long Term 10-15 Year Improvements
• Continued Reliability & Distribution System Enhancement
• Continued Coachella Valley Strategic Transmission
• New Resource Development for Future Generation
• IID Comisión Federal de Electricidad 230kV Transmission Project
IMPERIAL IRRIGATION DISTRICT
82
2025
SERVICE AREA PLAN ENERGY SERVICES
3. Mitigation of Power Facilities
IID has a comprehensive Integrated Resource Plan (IRP) prepared for the Power
Department, adopted in 2024. The goals in the IRP provide the Power Department an
integrated approach to identifying the generation and power system resources needed
to sustain IID’s service to the communities in a fiscally responsible, reliable, efficient and
affordable manner. The IRP should be reviewed for more detailed information; however,
the following are summary recommendations to achieve adequacy of energy service
facilities:
P-1 Continue to implement the goals identified under the IID Integrated
Resource Plan regarding Cost and Operation, Efficiency, Regulatory
Compliance and Regional Development.
P-2 Explore and implement potential energy loss reduction strategies
such as installing additional distribution capacitor banks, extending
existing transmission lines to improve service to concentrated loads,
and establish a distribution line re-conductor program.
P-3 Complete all necessary distribution system upgrades.
P-4 IID should diversity its generation resource mix in all things and all
approaches thus reducing various risks.
P-5 Continue to invest in IID-based and region-wide transmission
infrastructure.
P-6 Study and explore the location and technology type of a peaking
generator to be installed and operating in the near-term to provide
the necessary support the IID system needs to maintain reliability in
the wake of a heavy influx of intermittent renewable resource
integration.
P-7 IID shall continue to work on the development of a capital
replacement plan to address the aging fleet of thermal generation
units.
IMPERIAL IRRIGATION DISTRICT
83
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
D. EFFICIENCY & CONSERVATION PROGRAMS AND SERVICES
IID is located at the heart of many available natural resources to develop renewable energy
generation facilities as well as energy efficiency and conservation. The same can’t be said
about IID’s water supply considering the District’s Colorado River entitlement is IID’s sole
source of water supply. IID’s extensive rights to the use of Colorado River water are based on
state law appropriation history that are senior to most other Colorado River contractors.22
These water and energy factors drive IID’s decision-making process since many of the laws
that have been developed over the past several years, for the protection of both of these
resources, change the entire dynamic of strategic resource planning and the integration of
resources.
Water Efficiency & Conservation Overview
Challenges presented by new in-valley water demands and land use changes are intensified
by the annual cap on Imperial Region’s Colorado River water supply of 3.1 million acre-feet of
annual entitlement, while the near 500,000 AFY transfers under the 2003 Quantification
Settlement Agreement is in effect. Challenges beyond these limits is the unpredictability
associated with varying annual demands and competing uses within the Imperial Region. The
2012 Imperial Integrated Regional Water Management Plan (IRWMP) is the result of
stakeholders, who represent a wide array of interests, working together to formulate and
support implementation of long-term water management solutions many of which are
represented under IID’s water conservation programs described in more detail in IID’s Water
Conservation Plan. These water conservation programs are what enable the District to be a
party to the nation’s largest agriculture-to-urban water conservation and transfer agreement,
implementing efficiency-based conservation programs in coordination with its agricultural
water users that create just under 500,000 acre-feet annually of conserved water (from 2003
baseline year) for use by its funding partners under the 2003 QSA.
Another challenge to water supplies continues to be an increasing uncertainty associated with
drought conditions at the Colorado River Basin level. In June 2022, the U.S. Department of
Interior called for the Basin states to develop a plan before the end of the year to reduce
demands by 2-4 million acre-feet per year, through 2026, or the Secretary of the Interior
would take regulatory action to force these reductions in order to protect the Colorado River
system in light of the prolonged drought conditions and climate change impacts. California
submitted a voluntary conservation proposal in 2023 to Reclamation to conserve up to
400,000 AFY through 2026 as its commitment to Lake Mead and the Colorado River System.
IID is working diligently with federal agencies and Colorado River contractors to minimize
impacts to the local community while simultaneously ramping up water conservation
22 IID holds legal title to all its water and water rights in trust for landowners within the district: California Water Code §20529
and §22437; and Bryant v. Yellen, 447 U.S. 352, 371 (1980), fn. 23.
IMPERIAL IRRIGATION DISTRICT
84
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
programs in an effort to augment local water supplies, to some degree, should future Basin-
wide cuts be unavoidable. IID’s Board of Directors proposed to increase its conservation
targets to build elevation at Lake Mead by up to 250,000 AFY through 2026, bringing the
districts cumulative conservation goals up to 750,000 AFY (24% of its total entitlement).
Energy Efficiency & Conservation Overview
California has shown aggressive decarbonization and renewable energy efforts. Senate Bill
350, the Clean Energy and Pollution Reduction Act, passed in the 2015 California Legislative
Session, requires IID compliance with renewable portfolio standards laws and emissions laws.
IID must achieve a target range of between 524,000 and 667,000 metric tons of CO₂ per year
by 2030. Greenhouse Gas Emission reductions, under SB100 which in 2018 established the
100% zero-carbon electricity by 2045 target, are also planned for by IID in order to avoid
having to purchase emission credits. The passage of Senate Bill 1020 in 2022 established
intermediate zero-carbon energy targets of 90% and 95% in 2035 and 2040, respectively.
IID is always on the forefront of compliance with emerging and changing State and Federal
mandates impacting renewable energy portfolio standards. IID implements a comprehensive
energy conservation portfolio similar to California which leads the nation in energy efficiency
and renewable energy programs. Assembly Bill (AB) 2021 requires each publicly owned utility
to identify all potentially achievable cost-effective electricity efficiency savings and to
establish annual targets for energy efficiency savings and demand reduction for the next 10-
year period. IID has joined California Municipal Utilities Association (CMUA) in partnership
with Northern California Power Agency (NCPA) and the Southern California Public Power
Authority (SCPPA) to collaborate on the development of individual utility energy efficiency
and demand-reduction targets. IID implements an aggressive energy-efficiency portfolio with
the goal of reducing both energy consumption and peak demand. Energy-efficiency programs
may be classified as either conservation programs, or demand-side management (DSM)
programs. Conservation programs attempt to reduce the total amount of energy required by
consumers while DSM programs attempt to change the timing of energy use.
The information provided in this Section of the SAP is a comprehensive summary of the
numerous water and energy programs implemented by the District in efforts to maximize
efficiency and conservations of these valuable resources. For more detailed information,
interested parties are encouraged to visit iid.com and review IID’s most current Water
Conservation Plan for water and most current Integrated Resource Plan for energy.
IMPERIAL IRRIGATION DISTRICT
85
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
WATER EFFICIENCY & CONSERVATION
Under California state law, water must be distributed equitably as determined by the IID
Board of Directors. On November 28, 2006 the IID Board of Directors adopted Resolution No.
22-2006 approving the development and implementation of an Equitable Distribution Plan to
better manage IID’s annual Colorado River water supply. The District apportions its full water
supply based on water use history of Potable Water Users, Industrial/Commercial Water
Users and Agricultural Water Users after setting aside Operational and System Water. Given
that IID’s 3.1 MAFY water entitlement does not increase over time, the District has to maximize
the water use efficiency of existing uses, not only to meet transfer obligations but also to
conserve water that in turn will meet water supply demands for new growth and development
within its water service area. No service requests outside the water service area are pending.
Water Supply Demand
Operation and System Water. Water used by the district for system operations and
maintenance including operational carriage and discharge water, system losses, seepage,
evaporation, or other losses in the District’s distribution system such as unmetered small
parcel and pipe water services, recreational lakes and feedlots are adjusted for calculated
allocation every year and not available for apportionment. This water operational water
pool also includes water conserved by IID’s System Conservation Projects/Programs that
would have otherwise remained unavailable for apportionment but for the conservation
projects/programs (in turn available for transfer obligations). Annual operational water
demand fluctuates from year to year based on factors such us level of conservation
projects in place, cropping changes, delivery flexibility from farmers and responsive water
management by IID. The general range of operational water is 200,000 AFY to 300,000
AFY.
Non-Agricultural Uses Demand. Industrial, commercial and similar urban (Non-
agricultural) water demands are anticipated to increase over the planning period. The
Imperial Integrated Regional Water Management Plan determined a per capita municipal
raw water demand history of .23 AFY (weighted average) which is equal to 205 gallons per
day, per capita, and accounts for all municipal water use and not just residential, prior to
treatment and distribution. As of 2023, the Municipal Water Demand (for treated water
purveyors) was approximately 32,000 AFY and accounted for approximately 33 percent of
the total (97,000 AFY) non-agricultural water delivery throughout the Imperial Valley
averaging less per capita.
The same per-capita measure will be applied to future population projections. This
measure is conservative considering the increasing water conservation measures being
employed by the respective cities and water agencies in respond to state mandates for
IMPERIAL IRRIGATION DISTRICT
86
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
conservation. Table W- 6 projects Municipal water demand separate from the projected
demand from other non-agricultural uses within rural areas not being serviced by a water
treatment agency. Water demand from these other non-agricultural areas is anticipated
to increase modestly throughout the planning period. These estimates are conservative
enough to cover the anticipated geothermal and lithium development and any indirect
inducement of population. It is important to note that water is apportioned based on water
use history only. Although new industries are accounted for under water supply demand
projections, water supplies to meet the new demands must come from conservation
efforts, as described in IID’s Interim Water Supply Policy under the water conservation
programs section of this SAP. The water demand specifically tied to lithium is unknown as
no actual lithium plants are in operation to establish a basis for water demand per plant.
Table W- 6 IRWMP Non-Agricultural Water Demand Projections
Projected Municipal Industrial Other Non-Ag All Non-
Year Population Demand (AFY) Demand Demand (AFY) Agricultural
Projections Projections Demand AFY
2025 185,550 36,800 39,800 59,500 136,100
2030 193,326 39,800 46,500 59,500 145,800
2035 199,157 41,500 53,200 59,500 154,200
2040 203,470 46,300 59,900 59,500 165,700
Source: Imperial Integrated Regional Water Management Plan 2012.
Agricultural Uses Demand. As has been the case historically, annual agricultural demands
are expected to modestly fluctuate from year-to-year based on commodity markets,
rainfall, temporary (or long-term) fallowing and other factors. The projected raw water
demand for agricultural use is expected to remain constant between 2025 and 2030.
Should non-agricultural development in rural areas occur, the agricultural demand would
be expected to decrease. These permanent changes would be directly correlated to the
increase in population, via urban sprawl and conversion of farmland to urban uses. Table
W- 7 combines Agricultural Water Demand & Non-Agricultural Water Demand for a total
water demand during the planning period.
Table W- 7 Agricultural Water Demand Projections & Total Water Demand
Agricultural All Non-Agricultural Total
Year AFY Demand AFY Demand Projected
Projections Projections AFY Demand
2025 2,259,500 136,100 2,395,600
2030 2,209,500 145,800 2,355,300
2035 2,209,500 154,200 2,363,700
2040 2,209,500 165,700 2,375,200
Source: 2012 Imperial Integrated Regional Water Management Plan.
IMPERIAL IRRIGATION DISTRICT
87
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Transfer Obligations. As previously noted, the District is a party to the nation’s largest
agriculture-to-urban water conservation and transfer agreement. As such, implementing
efficiency-based conservation programs in coordination with its agricultural water is
essential for the creation of just under 500,000 acre-feet annually of conserved water
(from 2003 baseline year) to meet the 2003 QSA transfer obligations. In this vein, IID has
spent the last two decades setting up a robust, district-wide Efficiency Conservation
Program which includes System Conservation and On-Farm Efficiency Conservation
measures in order to meet its transfer commitments. Transfer commitments, and thus
conservation efforts, are expected to temporarily hike for years 2024, 2025 and 2026 in
direct response to a System Conservation Implementation Agreement with Reclamation
for up to 250,000 AFY and then remain constant through year 2030 and beyond.
1. Performance Standards for Water Efficiency & Conservation
Water Conservation Standard-The Imperial Irrigation District does not have any
performance standards adopted for water conservation, however, the district’s Water
Department, consistent with the Imperial Integrated Regional Water Management Plan
(2012) and IID’s Water Conservation Plan (2021), does implement several strategies to
manage in-valley water demand to live within the established consumptive use history.
IID’s Equitable Distribution Plan, adopted in 2022, intends to satisfactorily address any
potential water supply/demand imbalances. Water is apportioned to all water user
categories which is calculated by the calendar year average of the water use history for
that Water User Category as a whole during the years 2003 to 2012, eliminating the
highest calendar year and lowest calendar year of water use history
The performance standard is therefore established as performing the same activities,
operations and crop yields, but more efficiently and with less water use than totals over
history. The minimum conservation target shall be conservation yields consistent with all
IWSP Water Supply Agreements in place for the given year, the Quantification Settlement
Agreement (QSA) and any other System Conservation Implementation Agreements
entered into between IID and Reclamation to implement the Lower Colorado
Conservation and Efficiency Program. The IWSP is currently capped at 25,000 AFY. The
QSA specified 487,200 AFY of water will need to be conserved by 2026 by the IID
considering all IID Quantification and Transfers. Any additionally voluntary transfers
under a SCIA would have an annual cap of 250,000 AFY. These limits are the maximum IID
would conserve on any given year during the next five-year planning period under existing
and anticipated water supply and transfer agreements.
IMPERIAL IRRIGATION DISTRICT
88
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Linear Irrigation System Under On-Farm Efficiency Conservation
2. Water Efficiency & Conservation Program Planning and Adequacy Analysis
Water Department Conservation Programs
IID generates just under 500,000 AFY of conserved water to meet the needs of the QSA
water transfers by making water efficiency improvements in its delivery system and by
partnering up with the agricultural community for the implementation of on-farm
efficiency conservation measures. Non-agricultural water demand under the IWSP was
nominal in 2023 with an operational demand of 1,800 AFY, albeit other commitments
amounting to just under 6,000 AFY may become operational within the 5-year planning
period. IID’s established water conservation programs are designed on best management
practices and water accounting principles with ample resources to be able to fulfill these
existing and projected water supply demands under existing and planned water
conservation programs.
Water conservation efforts are entirely managed and delivered in-house through IID’s
Water Department. The Water Department is comprised of eight sections all of which
support conservation measures to some extent, however, two sections and one
department are primarily and/or solely dedicated to Water Conservation efforts and
Water Conservation Program implementation. Additionally, the Water Department
oversees the Water Transfer Operation and Maintenance Section, that has multiple sub-
sections all responsible for water conservation support services. A description of the
primary duties of each respective section follows:
IMPERIAL IRRIGATION DISTRICT
89
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
• Agricultural Water Resources Section is responsible for long-term implementation of
water conservation and transfer programs between IID and other agencies. Areas of
responsibility include the management of fallowing, apportionment, and agricultural
water clearinghouse and on-farm conservation programs. Staff sets program
objectives, develops budgets, provides short and long-term planning and implements
the work developed for each individual program. Staff provides regular updates to
the IID Board of Directors as well as stakeholder agencies regarding budget,
expenditures and program schedules and objectives.
• Environmental Mitigation Section is responsible for Water Department and QSA
water transfer environmental mitigation implementation. This section includes
wildlife species monitoring and conservation, managed marsh complex construction,
operation and maintenance, desert pupfish refugium construction, and Salton Sea air
quality mitigation. This section is responsible for compliance with QSA EIR/EIS,
biological opinion, Incidental Take Permit (ITP 2081) and other environmental permits
for various projects.
• Water Transfer Operation & Maintenance Unit provides for the operation and
maintenance activities necessary to accomplish the conservation of water.
(1) Water Transfer Operation & Maintenance Mitigation Section is responsible
for the QSA-Joint Power Agreement mitigations tasks under the JPA.
Mitigation covers QSA agreement payment for the Salton Sea Restoration
Fund and QSA-JPA, other non-QSA environmental permits and non-QSA
mitigation projects which will be granted and state funded.
(2) Water Transfer Operation & Maintenance Efficiency Section covers operation
and maintenance of system conservation projects, such as the seepage pump
interceptors and also includes the development and implementation of the
on-farm conservation program.
(3) Water Transfer Operation & Maintenance Program Management Section
includes the general support and administration of Water Transfer related
activities. The planning, oversight and direction of general activities,
including budgeting and reporting needs for the Water Transfer activities.
(4) Western Farm Lands Operation & Maintenance Land Management Section is
responsible for the management of the Western Farm Lands owned by the
District. The activities for this section include the maintenance, rental and
any costs associated with the sale of these properties.
IMPERIAL IRRIGATION DISTRICT
90
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
a) Inventory of Existing Water Efficiency & Conservation Programs/Resources
Water Conservation Programs & Resources- Water Resource Management under the
Water Department are focused on three areas of efficiency: 1) System Efficiency, 2)
Agricultural Water use Efficiency, and 3) Non-Agricultural Water Use Efficiency. A
brief overview of the existing programs and services is described under each focus
area below.
Photo of Lateral Heading Automation
1) System Efficiency - IID has a very successful System Conservation Program which
implements numerous system conservation measures that generated just under
60,000 acre-feet of conserved water in 2024, with the goal of reaching 103,000
acre-feet in 2026 and annually thereafter. System efficiency involves major capital
investment in IID’s distribution system. Every year, the district invests in the
development of Main Canal Seepage Interception Projects, Operation Discharge
Reduction Projects, Mid-Lateral Operational Reservoirs and/or Main Canal System
Reservoirs as well as numerous automation projects. Under system
improvements, IID has constructed and operates twelve operational reservoirs
throughout its distribution system to maximize water management flexibility. IID
has installed telemetry system with automated structures on upper reaches of
main canals and SCADA system with computers, radio and microwave
communication for all Zanjeros. In 1993 IID constructed a state-of-the-art Water
Control Center and numerous SCADA controlled water management projects
IMPERIAL IRRIGATION DISTRICT
91
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
throughout its distribution system. Water measurements for all automated flow
structures are stored in IID’s WISKI, where quality assurance and quality control is
performed.
2) Agricultural Water Use Efficiency- Improving water use efficiency in close
collaboration with the agricultural industry has been an important goal for the
District and the Imperial Valley farming community. IID and Imperial Valley
growers have worked aggressively to implement on-farm water conservation
efficiency measures. Under IID’s On-Farm Efficiency Conservation Program,
payment is made to participants for efficiency improvements that in turn
conserve water. Contracts are issued for individual crop seasons which correlates
to the time period over which a specific crop is grown on a specific acreage, based
on plant and harvest dates. This is a successful on-farm efficiency program that
generates over 200,000 acre-feet in 2023. The primary conservation measures
are drip irrigation systems, tailwater return systems, sprinkler irrigation systems,
field reconfiguration and land leveling.
3) Non-Agricultural Water Use Efficiency- Non-Agricultural development,
particularly in the renewable energy industry and potential lithium extraction
represents a significant economic development opportunity within the IID Water
Service Area and has the largest forecasted increase in future water demand,
requiring a reliable long-term supply that that needs to be structured in a manner
that would not adversely impact agricultural productivity. The 2009 IID IWSP
provides for up to 25,000 AFY of conservation potential for new demands
generated by new development of renewable energy industries. The policy adopts
an established water rate structure that is adjusted annually, consistent with the
CPI, to cover the costs of implementing conservation projects and/or programs for
the benefit of the new development. The following are additional Best
Management Practices that IID considers when reviewing new non-agricultural
projects or expansions:
• Support the use of dry or hybrid cooling.
• Consider use of recycled municipal water for cooling.
• Consider use of desalinated brackish water for cooling.
• Consider groundwater bank as a water supply.
• Require appropriate water use efficiency BMP’s per the California Urban
Water Conservation Council, California Energy Commission, and those
adopted by IID.
In order to advance all of these water conservation programs, objectives and
measures, the Imperial Irrigation District has allocated the following resources within
the two sections in the Water Department implementing water conservation efforts:
IMPERIAL IRRIGATION DISTRICT
92
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Water Conservation Programs Personnel 2024 (97 Total FTE):
• Agricultural Water Resources (22 FTE)
• Water Environmental Section (9 FTE)
• Water Transfer O&M Mitigation Section (20 FTE)
• Water Transfer O&M Efficiency Section (45 FTE)
• Western Farm Lands Land Management (1 FTE)
Water Conservation Program Department Vehicles 2024 (52 Vehicles):
• Agricultural Water Resources Section (7 Vehicles)
• Water Environmental Section (8 Vehicles)
• Water Transfer O&M Mitigation Section (10 Vehicles)
• Water Transfer O&M Efficiency Section (26 Vehicles)
• Western Farm Lands Land Management (1 Vehicle)
b) Adequacy of Existing Water Efficiency & Conservation Programs
IID has been successful in meeting its water transfer obligations pursuant to the
agreements in place through 2023 which included QSA obligations and a 2023 SCIA
with Reclamation for the benefit of Lake Mead. IID further entered into three IWSP
Water Supply Agreements between 2022 and 2023, under which one of the projects
was operational and two others under development. The numerous conservation
projects and programs that have been implemented by the District are considered
adequate as they have resulted in quantifiable water conservation and reliability to
meet existing water supply demands and transfer obligations. The following is a brief
summary of program results.
System Conservation Programs – IID continues to implement numerous system
conservations programs and projects under the 1988 IID/Metropolitan Water District
of Southern California (MWD) Water Conservation Agreement. Since implementation
of the IID/MWD Conservation Program the associated water savings has fluctuated
between 97,150 AFY to 113,000 AFY. In 2003, IID amended the agreement to align
the agreement end date with the Quantification Settlement Agreement and a 2014
Letter of Agreement provides that effective January 2016, the total amount of
conserved water for transfer to MWD is fixed at 105,000 AFY.
IID continues to perform numerous system upgrades to meet the additional needs of
the QSA Water Transfers by making water efficiency improvements in its delivery
system on an annual basis. Components of the System Conservation Program include:
• System Discharge Reduction Program
o Communication upgrades (100% complete)
o Installation of automated lateral headings
o Design and installation of monitored discharge sites
o Laptop computers for Zanjeros (100% complete)
IMPERIAL IRRIGATION DISTRICT
93
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
o SCADA integration and monitoring
o Additional Operational Labor (14 Zanjero positions)
• Other Operational Discharge Reduction Projects
o Main Canal Seepage Recovery Pumps
o Lateral Interties
o Interceptor Channels
o Main Canal Operational Reservoirs
o Mid-Lateral off-line operational reservoirs
o Mid-Lateral Regulating Reservoirs
In addition to the 1988 IID/MWD Water Conservation Agreement and AAC Lining
Project yields, IID system efficiency conservation measures are expected to generate
an additional 103,000 AFY by 2026 to meet the QSA obligations. Monitoring results
for System Conservation have demonstrated adequate, increasing annual
conservation yields. Table CW-1 identifies the conservation yields that IID has
conserved over the last ten years, in 3-year intervals, under system efficiency
conservation projects and programs.
Table CW- 1 System Conservation Program Conservation Yield History
System Conservation Program 2014 2017 2020 2023
AFY AFY AFY AFY
1988 IID/MWD Conservation 104,100 105,000 105,000 105,000
All-American Canal Lining 67,700 67,700 67,700 67,700
Seepage Recovery 32,231 35,026 39,034 38,648
Other System Efficiency 0 29,186 33,973 35,530
TOTAL SYSTEM CONSERVATION 204,031 236,912 245,707 246,878
Source: IID Internal Water Accounting Records from WIS/WISKI Verified Savings History at River.
Temporary Land Conversion Fallowing Program-The IID Board adopted a Temporary
Land Conversion Fallowing Policy (TLCFP) on May 8, 2012, and revised it on March 29,
2016. Fallowing is the practice of temporarily taking active farmland out of
production. Water, which under normal circumstances would have gone to the land
to produce crops, is considered conserved under the fallowing program. Conserved
water from fallowing is transferred to the San Diego County Water Authority, used
for delivery to the Salton Sea (through 2017) to mitigate the environmental impacts
of these transfers, and for payback or storage purposes. The water transfer schedules
called for the district to generate 150,000 acre-feet annually through fallowing from
2013 through 2017, concluding IID’s required fallowing.
IMPERIAL IRRIGATION DISTRICT
94
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
The fallowing program revisions of March 29, 2016, provided a framework for a
temporary, long-term fallowing program to work in concert with the IWSP and IID’s
coordinated land use/water supply strategy. IID concluded that certain lower water
use projects, such as solar power facilities, may still provide benefits to local water
users, albeit temporary. Water demands for certain non-agricultural projects can be
less than water required for agricultural production; this reduced demand allows
water to be made available for other users under IID’s annual consumptive use cap.
Table CW- 2 identifies the solar fallowing conservation yield over the last 10 years.
Table CW- 2 TLCFP Conservation Yield History
Implementation Participating Documented AF
Year Acres Conservation Yield
2014 6,912 36,265
2015 7,104 37,320
2016 7,864 38,717
2017 10,146 48,040
2018 12,354 66,034
2019 12,404 65,791
2020 12,404 65,964
2021 13,165 69,623
2022 13,177 69,898
2023 13,177 69,898
Source: Fallowing Conservation Reports at IID TLCFP. Volumes in table reflect acre-feet
at Imperial Dam
These TLCFP water conservation yields provide the district some relief during the
term of the QSA/Transfer Agreements from having to create conserved water
through projects that may require capital investment or traditional financing. This
conserved water can be used to satisfy some of the district’s water transfer
obligations or free up conserved water for new non-agricultural demands.
On-Farm Efficiency Conservation Program - One of the most successful water
conservation programs is the On-Farm Conservation Program which is in partnership
with the local grower community. The OFECP allows for broad farmer participation
on a variety of crops and growing seasons. Landowners and tenants voluntarily
propose conservation measures, delivery reduction volume, contract duration, and a
cropping plan for IID consideration. After review and consultation, IID accepts
proposals until conservation obligations are fulfilled. Water conservation is measured
relative to a ten-year history baseline specific to each field and crop participating. IID
has an on-farm conservation target that is set every year by the IID Board of Directors.
Monitoring results have demonstrated increasing annual conservation yields as noted
in Table CW- 3.
IMPERIAL IRRIGATION DISTRICT
95
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Table CW- 3 On-Farm Efficiency Conservation Program Conservation Yields History
Implementation Year Participating Documented Conservation
Acres Yield
2014 54,345 44,371 AF
2015 115,173 87,721 AF
2016 189,823 138,585 AF
2017 250,022 151,750 AF
2018 318,193 190,969 AF
2019 238,764 178,742 AF
2020 201,335 177,552 AF
2021 196,180 163,069 AF
2022 328,786 179,620 AF
2023 317,546 215,382 AF
NOTE: Participating Acres includes all acres enrolled in the OFECP for the applicable year the crop was
harvested including acres without water savings. Volumes in acre-feet at Imperial Dam.
IID maintains annual water accounting summaries. The Annual Water & QSA
Implementation Report23 provides water accounting for conservation efficiency relative
to the transfer obligations and system efficiency as well as all other IID water
conservation initiatives. Table CW- 4 provides a summary of the reported conservation
volumes, depicting the generated conservation for the last five years, meeting all
obligations and conserving additional volumes as Intentionally Created Surplus or for
the benefit of Lake Mead, thus demonstrating an adequate conservation performance.
Table CW- 4 Water Conservation Programs Distribution Schedule
Purpose 2019 2020 2021 2022 2023
AFY AFY AFY AFY AFY
1988 IID/MWD Transfer 105,000 105,000 105,000 105,000 105,000
SDCWA Transfer 160,000 192,500 205,000 202,500 150,000
CVWD Transfer 68,000 73,000 78,000 83,000 88,000
AAC Lining Project Transfer 67,700 67,700 67,700 67,700 67,700
Intentionally Created Surplus* 43,405 51,023 30,008 13,365 0
Lake Mead Voluntary Conservation NA NA NA 25,000 106,111
TOTAL CONSERVATION 444,105 489,223 485,708 496,565 516,811
*Intentionally Created Surplus is water conserved by the District using efficiency measures and stored at Lake Mead for
future availability to the District (within IID’s storage limits). Conserved water beyond these limits left for the benefit of
the system and not credited to IID was in excess of 90,000 AF (2019- 41,826 AF; 2020-49,444; 2021-1,762).
23 QSA Annual Reports | Imperial Irrigation District (iid.com)
IMPERIAL IRRIGATION DISTRICT
96
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
c) Future Demand for Water Efficiency & Conservation Facilities/Improvements
As the Imperial Valley grows, and as its economy diversifies, so do the functions and
role of IID’s Water Department. By implementing extraordinary conservation
projects, developing innovative efficiency measures and utilizing progressive
management tools, the Water Department is working to ensure both the reliability of
water for agriculture, new in-valley growth and the continued protection of water
resources for long-term sustainability.
Water Conservation Targets – IID has existing water transfer obligations and
commitments under the QSA through the next 20-year planning period. By 2026, IID
will need to conserve 487,200 to satisfy the QSA water transfer agreements in place.
For years 2025 through 2027, it is expected that IID will conserve up to an additional
250,000 AFY under a System Conservation Implementation Agreement with
Reclamation. The planned water conservation targets for the Imperial Valley service
area are noted in Table CW- 1 System Conservation Program Conservation Yield
History.
Table CW- 5 Anticipated Water Conservation Planning Targets
Year Entitlement QSA SCIA IID Net For
Amount AFY Conservation Conservation Consumptive Use
Targets AFY Targets AFY AFY
2025 3,100,000 482,200 ≤ 250,000 2,367,800
2030 3,100,000 487,200 0 2,612,800
2035 3,000,000 487,200 0 2,612,800
2040 3,100,000 487,200 0 2,612,800
2045 3,000,000 487,200 0 2,612,800
Source: CRWDA Exhibit B and System Conservation Implementation Agreement with Reclamation.
113F
As previously noted, IID has a system conservation target of 103,000 AFY to meet QSA
Transfer obligations. An additional 105,000 AFY is conserved under the IID/MWD
Water Conservation Program (MWD investment into construction, operation and
maintenance projects that conserve water) and 67,600 AFY from All-American Canal
Lining for transfer to the Coachella Valley Water District. All of the measures utilized
for conservation under these programs are completed and in place thus not included
in future projects and only requiring operation and maintenance activities. The
remaining reduction of up to 11,500 AFY for miscellaneous and Indian present
perfected rights is not required to be from efficiency conservation and is satisfactorily
met by the District every year. IID has several projects planned to help meet the water
conservation goals over the next five-year planning period.
IMPERIAL IRRIGATION DISTRICT
97
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Planned New Voluntary Water Conservation Programs
IID will continue to implement its existing system and on-farm water conservation
programs. In efforts to address new and additional conservation goals under the SCIA
with Reclamation, the District adopted a hybrid seasonal, or rotational, fallowing
program. The “Deficit Irrigation Program” was adopted by the IID Board of Directors in
2024 and began in August 2024. The DIP incentivizes growers to engage in the seasonal,
deficit irrigation of forage crops over a 45-day to 60-day time period during the summer
months of June through September, under normal implementation. The DIP is expected
to be temporary, over a three-year period (2024-2026). Specifically, Alfalfa, Bermuda
grass and Klein grass would be encouraged to delay irrigation for a minimum of 45 days
and maximum of 60 days during a single, specified summer growing period.
Implementation of the program requires environmental clearance and mitigation
monitoring, as assessed under the California Environmental Quality Act and National
Environmental Policy Act, a federally initiated environmental assessment. The
anticipated conserved water would remain in Lake Mead for the benefit of the reservoir’s
elevation. In exchange, IID will receive funding for program participant compensation and
other conservation initiatives. The local farming community has expressed their support
of these temporary, voluntary measures.
Planned Water Efficiency & Conservation Projects
• Main Canal, Upstream Operational Reservoir
• Mid-lateral Operational Reservoir/Interceptor Projects (2 total)
• Lateral Intertie Projects (10 total)
• New & Rehabilitation of Seepage Recovery Sites
• Advance Automation of Flow Control and Measurement
Operational Reservoir Projects- Operational reservoirs allow for the temporary storage
of water to accommodate changes in demand from canceled water order, rain events or
other unexpected conditions. Since IID is unable to return any water previously ordered
from Hoover Dam, the reservoirs function as a temporary “parking lot” until the water is
needed again downstream. These operational facilities are able to manage and balance
supply and demand in a manner that reduces operational discharge and conserves water.
Reservoirs stabilize water delivery and make IID’s delivery system more efficient. IID has
a number of planned operational reservoirs, including small in-line facilities, mid-lateral
reservoirs that are a part of an interceptor system and a regional main canal system
reservoir that is proposed to be located upstream of IID’s distribution system. These
projects are expected to result in district-wide water conservation. Table CW- 6 identifies
the planned reservoirs expected to be completed within a five-year time frame and the
estimated annual conservation yield.
IMPERIAL IRRIGATION DISTRICT
98
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Table CW- 6 Planned Operational Reservoirs & Estimated Conservation Yields
Operational Reservoir Reservoir Estimated
Timeframe Maximum AF Conservation
Capacity Yield (AFY)
Upstream East Highline & AAC Near-term 2,100 AF 15,000
East Highline North Near-term 250 AF 1,500
Trifolium 11 Near-term 300 AF 1,500
West Side Main Near-term 500 AF 3,000
Fern Canal Reservoir Mid-term 250 AF 1,000
Central Main Reservoir Mid-term 350 AF 1,500
Wisteria Canal Reservoir Mid-term 250 AF 1,000
Multiple Mid-Lateral Reservoirs Mid-term (8 x 12 AF) TBD
TOTAL 4,096 AF 23,500 AFY
NOTE: Near-term is under five years; Mid-term is 5-10 years.
Intertie Projects -IID has multiple intertie projects planned for near-term and mid-
term development that may, or may not, be tied to the aforementioned planned
reservoirs. An intertie is a connection between two existing canals/laterals to prevent
one of them from continuing into an operational discharge, or drain system. Interties
may be lined canals or pipelines and may or may not be connected to temporary
storage facilities (operational reservoirs).
Peach to Plum Intertie Construction, 2024
IMPERIAL IRRIGATION DISTRICT
99
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Planned inter-tie projects are mostly constructed as piped connections to facilitate
metering and monitoring of conserved water. Although there are over forty intertie
opportunities, only the near-term projects with a completion date of under five years
are listed in Table CW- 7 and the estimated conservation yield annually.
Table CW- 7 Planned Intertie Project and Conservation Yields
Proposed Intertie Timeframe Estimated
Conservation Yield
(AFY)
EHL Lateral 7 to Pear Main Near-term 420
EHL Lateral 8 to Pear Main Near-term 400
Orient to Plum-Oasis Near-term 800
Rose Canal to Rockwood Mid-term 15,000*
Acacia Lateral 7 to Acacia Lateral 11 Near-term *
Lilac to Rose Canal Near-term *
Acacia Lateral 9 to Roselle Near-term *
Estimated Total Yield 16,620 AFY
*The Rose Canal to Rockwood Canal Project is a large cluster of interties with a 250 AF reservoir that as a group are
anticipated to save a minimum of 15,000 AFY.
Source: IID Water Department, System Conservation.
Seepage Recovery Projects – The recovery of canal seepage from earthen main canals
due to permeable soils, is accomplished through strategically placed dewatering
pump (DP) systems. Implementation of seepage recovery projects within IID’s
distribution system began as early as 1947 along the AAC and along the East Highline
Canal in 1967. Seepage recovery projects to meet QSA/Transfer Agreement
obligations began in 2009. Through a process of seepage recovery, a vertical pump
recovers the water and injects it back in to the main canal. The project sits are
equipped with Siemens Flow Meters on discharge tubes. The metered discharge data
is transmitted to the WISKI via IID’s SCADA system. IID currently implements a total
of 32 seepage interception sites for canal seepage recovery.
As of 2023, the 32 operational seepage recovery sites were producing 38,648 AFY of
conservation efficiency savings. The total costs, through 2023, for all seepage
recovery projects is estimated at $16 million with an annual operation and
maintenance cost of $623,000, providing an attractive cost per acre-foot of
approximately $36/AF. IID is planning for two additional seepage recovery projects
with the next 5-year planning period.
IMPERIAL IRRIGATION DISTRICT
10 0
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Seepage Recovery Project, Before and After
d) Opportunities for Joint Water Efficiency & Conservation Programs/Services
Joint Agency Program and Project Partnerships. IID makes every effort to involve
multiple stakeholders in its water efficiency projects and water conservation
programs with a very successful track record. As previously noted, water efficiency
projects and programs implemented throughout the District are paid for by, and in
collaboration with, multiple stakeholders, including, but not limited to the
Metropolitan Water District of Southern California (which is a multi-agency
organization), San Diego County Water Authority, Coachella Valley Water District, and
other related agencies for the generation of just under 500,000 AFY of conserved
water. The U.S. Bureau of Reclamation has also entered into system conservation
agreements with IID for the benefit of Colorado River system.
Joint Partnership with Private Developers. IID also partners with multiple in-valley
non-agricultural project owners for the development of conserved water.
Industrial/commercial water users may contract with IID for the development of
conserved water. Under the IWSP, Developers may implement their own water
conservation projects or agree to an annual Water Supply Development Fee for the
contracted water volume of water projected to be needed for their development
project. The collected funds are used solely to assist in funding new water supply
projects to fulfill the projects’ demands.
Joint Partnership with Agriculture Growers. The District, in partnership with the local
grower community, responds to water supply requests from transfer commitments
and new development, beyond what can be accommodated through system
conservation and the existing TLCFP. The difference between available conservation
and actual demand is assessed annually and fulfilled with a strategic budget to fund
IMPERIAL IRRIGATION DISTRICT
10 1
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
the annual implementation of the OFECP. These joint opportunities provide farmers
with capital to invest in water efficiency measures with long-term benefits in Imperial
Valley and the broader region.
Joint Partnership with Power Department. Joint efficiency and water conservation
opportunities are not just limited to water users. The IID Board of Directors developed
a joint energy and power partnership for rural energy system distribution expansion
into areas not previously served with power, for the benefit of on-farm efficiency
conservation projects. The District has been collecting backfeed power service
payments for a number of years from generating facilities located within IID’s service
area. These generators are interconnected to the transmission system operated by
the California Independent System Operator and receive backfeed power service at
transmission voltage-levels of 34.5 kV or higher to operate its generating facilities on
the transmission system under the operational control of the CAISO instead of IID.
Since the District has given up its exclusive right to serve these generators within IID’s
electrical service area, the Power Department assesses a backfeed power service
charge for all energy produced by the generator. In addition to the backfeed power
service payments, generators that opt out of receiving distribution station power
service from IID are required to pay a one-time $1,000,000 limited waiver fee.
On March 4, 2014, the board directed that both the limited waiver fee and backfeed
power service payments be held in a cash account and utilized solely to fund the
expansion of the rural energy distribution system in support of on-farm water
conservation projects. The benefit is both an increase in electrical service revenue
from agricultural customers and an increase in conserved water from OFECP
participation. The annual funding cap is limited to $200,000 per farm-unit and IID’s
cost-share is 85% of the electrical upgrade (not to exceed $170,000)
e) Phasing of Water Conservation Projects/Programs
All of the district’s conservation projects are included in the Capital Improvement Plan
which spans over a five-year period. Conservation programs and projects beyond five
years are subject to change or expand depending on funding opportunities and
availability.
Short Term Improvements (Under 5 Years)
• Upstream Operational Reservoir at East Highline Canal Project
• Canal Intertie and Interceptor Projects
• Automation of Check Structure Projects
• Deficit Irrigation Program
• On-Farm Efficiency Conservation Program
• Solar Temporary Land Conversion Fallowing Program
IMPERIAL IRRIGATION DISTRICT
10 2
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
5-10 Year Improvements
• Multiple in-line operational reservoirs
• Continuance of OFECP and Solar TLCFP
10-15 Year Improvements
• Continue Development of Multiple in-line Operational Reservoirs
• Continuance of OFECP and Solar TLCFP
1. Mitigation for Water Efficiency & Conservation Efforts
IID should continue to pursue various means by which to maximize water use
efficiency and conservation while maintaining adequate water services to the IID Water
Service Area as a priority. The following mitigation measures are recommended for Water
Efficiency and Conservation (WC):
WC-1 Continue to implement key elements of the Integrated Regional
Water Management Plan and System Conservation Program as
actions planned under the adopted Water Conservation Plan to fulfill
obligations under the Quantification Settlement Agreement/Transfer
Agreements.
WC-2 Explore financing mechanisms to construct the “not built”
Quantification Settlement Agreement projects as a near-to-mid-term
solution to provide up to 8,000 AFY for future non-agricultural uses.
WC-3 Review and track development of the in-valley, voluntary fallowing
program that expands on, or modifies the Fallowing Program that
ended in 2017.
WC-4 IID should continue to provide support to municipal purveyors
responsible for developing their urban water conservation programs
and coordinating regional efforts when resources are provided for
this purpose.
IMPERIAL IRRIGATION DISTRICT
10 3
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
ENERGY EFFICIENCY & CONSERVATION
IID is a longtime proponent of renewable energy. The Imperial Valley has abundant resources
of solar, geothermal, hydroelectric, wind and other renewable potential. Recognizing that
there are many choices and ways to procure renewable energy, the district procures almost
all of its renewable energy from local resources as they contribute jobs and economic
development in the communities served by IID. In this vein, IID has exceeded that target goals
and the Power Department has a suite of ongoing energy efficiency and demand response
programs with a record of helping both residential, commercial, and industrial customers be
more efficient, avoid wasted electricity and save money.
1. Performance Standards for Energy Efficiency
Energy Efficiency & Conservation Standards- Consistent with Senate Bill 350, the Clean
Energy and Pollution Reduction Act, passed in the 2015 California Legislative Session, the
IID Power Department adopted energy efficiency standards under its 2018 Integrated
Resource Plan which continue to be in effect under the 2024 IRP. The new IID adopted
Energy Savings Target requires 100% of retail electricity sales to be zero-carbon by 2045,
with interim targets of 44% by 2024, 52% by 2027, and 60% by 2020. The district’s energy
target contains the two categories MWh from Market Potential from Programs and MWh
from Codes and Standards. The district must increase energy efficiency achievement in
buildings by 50 percent (with special emphasis on participation from low-income
communities).
Renewable Energy Standards- To reduce the carbon footprint caused by utility-wide
emissions, California’s Renewables Portfolio Standard was established by legislation in
2002. The mandate requires that all electric utilities procure energy generated by
renewable resources into their portfolio. The district must meet Renewable Portfolio
Standards which are targeted to reach 50 percent of total retail energy sales by 2030. This
is equivalent to 50-75 MW of baseload energy and around 100-150MW of solar
generation, or some other intermittent resource such as wind, with an annual capacity
factor around 30 percent.
Emission Reduction Standards-The Global Warming Solutions Act (AB 32) mandates
public utilities, such as IID, to reduce total company wide emissions to 1990 levels by 2020
and an 80 percent of 1990 levels reduction by 2050 – a state reduction of about 30
percent and a reduction of about 7-10 percent for IID. Greenhouse Gas Emission (GHG)
standards also have to be complied with by the IID. The district adopted the target goal
of GHG emission reduction to 40 percent below the 1990 levels. To meet this goal, IID
must reduce GHG emissions to 1,100 lbs./MWh, on average. In the case of the IID, the
reduction of overall organizational emissions will be mainly rendered through a rigorous
renewable portfolio program already in progress by the IID Energy Resource Planning
Unit.
IMPERIAL IRRIGATION DISTRICT
10 4
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
2. Energy Efficiency Program Planning Adequacy and Analysis
Power Department Conservation Program
The 2003 SB 1037 requires public and private gas and electric utilities to first acquire all
available energy efficiency and demand reduction resources that are cost effective,
reliable and feasible before conventional generation, or other resources. IID offers a
variety of energy conservation and design side management (DSM) programs intended,
in part, to alleviate electric generation requirements and avoid expensive peak purchases
of power on the market. Energy conservation programs are designed to reduce the total
amount of energy used while DSM programs are designed to shift energy use from high
cost periods to low cost periods and reduce the cost of supplying customers.
Most programs within IID’s portfolio are conservation programs with the goal of reducing
the customer’s consumption and cost of energy. However, future programs may be
designed to shift customer on-peak use to off-peak hours. Energy conservation efforts are
managed and delivered through IID’s Power Department. The following sections actively
support energy efficiency, conservation and greenhouse gas emission reductions.
• Power Administration Section is responsible for the oversight and management
of all operations, maintenance, engineering services, reliability and accountability
for the Power Department. This section interfaces with the Board of Directors,
general manager, and the public to ensure effective communication and proper
administration of policies and procedures and oversees the Power Department
Strategic Plan and ensures that all other sections and units within the department
are meeting the established goals and objectives.
• Power Operations & Resources Section is responsible for the safe and reliable
operation and dispatch of the district’s generation, transmission, and distribution
systems. Sub-sections focused on supporting energy efficiency, conservation or
greenhouse gas emission reductions are as follows:
1) Public Benefits and Regulatory -is responsible, amongst other duties, to
support renewable energy development and to protect the balancing
authority by leveraging existing assets. This sub-section designs and
implements programs to encourage customer conservation as a cost-
effective alternative.
2) System Operations - is responsible for the safe and reliable operation and
dispatch of the district’s generation, transmission and distribution
systems. System Operations is also responsible for monitoring NERC and
WECC reporting requirements and submission of compliance filings.
3) Power Supply & Trading - is responsible for aligning the Power
Department’s financial goals with its customer and system operations
requirements.
IMPERIAL IRRIGATION DISTRICT
10 5
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
4) Power Production- is responsible for providing cost competitive, reliable
and environmental compliant bulk electricity.
a) Inventory of Existing Energy Efficiency & Conservation Programs &
Resources
Energy efficiency and conservation programs are designed to reduce the total amount
of energy used while design side management programs are structured to shift energy
use from high cost periods to low cost periods and reduce the cost of supplying
customers. A brief overview of the existing programs and services is described under
each focus area follows.
1) Energy Efficiency Programs- Improving energy use efficiency has been an
important goal for the IID and in line with Statewide objectives. IID has worked
aggressively to implement system-wide energy conservation measures to meet
the needs of all client categories. The following is a list of some of the energy
efficiency programs currently in place under the district’s overall energy
Conservation and Energy Efficiency Programs for residential and commercial rate
customers:
Residential Programs
• Residential Weatherization Program- allows participating IID energy,
residential customers to receive up to $1,000 in recommended energy
saving services and equipment for their residence. The program is open to
all IID residential customers on a first-come, first-serve basis. IID partners
with a service provider that can evaluate and suggest a home’s energy
efficiency improvements.
• Energy Rewards Rebate Programs- This program offers residential
prescriptive rebates for qualified energy efficient measures such as air
conditioners, ENERGY STAR® refrigerators, windows, attic insulation and
pool pumps.
• Tree for All program- provides customers with a free shade tree, planted
to maximize energy savings.
• ReCharge! EV Charger Program – IID now offers rebates of $500 to
customers who purchase and install a Level 2 (240V) plug-in electric
vehicle home charger. IID dedicates a web-page to the Program where
interested parties can explore other potential incentives and tax credits as
well: IID EVolve | Home.
IMPERIAL IRRIGATION DISTRICT
10 6
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Commercial Programs
• Customer Energy Solutions Program (CESP)-CESP offers financial
incentives to commercial customers intended to offset the cost to
purchase and install qualifying energy efficiency measures. The measures
must retrofit, replace, or upgrade, old equipment with new, energy-
efficient technologies. IID offers technical assistance.
• Green Grants Program- is offered to non-profit organizations located in
IID's service area. Funding is limited to energy efficiency/management
upgrades and investments in renewable resources that are not covered
under any other existing public benefit program offered by IID.
• Energy Rewards Rebate Program- IID offers nonresidential customers
prescriptive rebates for qualified energy-efficient measures. Measures
must retrofit, replace, or upgrade, old equipment with new, energy-
efficient technologies that meet and exceed the Title 24 standards.
Qualifying product categories include programmable thermostats, HVAC
equipment and motors.
2) Renewable Energy Program - The renewable energy industry represents a
significant economic development opportunity within the IID service area. The
bulk availability of renewable energy generation comes from intermittent
resources such as solar and wind-based generation. Since IID’s service territory has
sufficient supply of available land, transmission, and sunshine, solar-based
generation facilities are expected to increase over the next 10-20 years. Figure 7
provided a breakdown of IID’s current renewable resources.
To help customers fully benefit from investments in various renewable options,
IID currently offers the following retail renewable programs for customers
interested in meeting all, or a portion, of their load with a renewable resource:
• Green Energy Rate Program-The Green Energy Rate Program will allow
customers to designate how much renewable energy they wish to be
served with. Any customers (with exception of those who have installed
on-site renewable systems, or wholesale power customers receiving
standby service) who elect participation in the new Green Energy Rate
Program, can choose to be served with an even greater percentage of
renewables, up to 100 percent. The program had its full first year of
operation at end of 2019. It is estimated that the program will increase
customers’ per kilowatt-hour rate by 0.05 to 0.2 cents (June 2025). The
monthly rate will fluctuate based on IID’s cost to procure renewable
resources. As of June 2025, no customers were actively enrolled, thus
there are no current contributions to IID’s renewable portfolio.
IMPERIAL IRRIGATION DISTRICT
10 7
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
• Net Energy Metering Program- Net Energy Metering (NEM) is a program
that was designed to benefit IID customers who generate their own
electricity using solar, wind, biogas, fuel cell, or a hybrid of these
technologies. The program included generating facilities up to 1MW and
was offered on a first-come, first-served basis. IID’s NEM program capacity
is 50.2MW, five percent of IID’s peak demand. As of the end of 2023, the
NEM program was fully subscribed.
• Net Billing Program-The Net Billing Program, successor to the Net
Metering Program, extended the Net Metering Program by an estimated
9.6MW to allow for additional customer participation. The program paves
the way for new solar development while at the same time reducing cross-
customer subsidization between those with and without solar.
• Feed-In Tariff Program- The tariff provides a simple mechanism for small
renewable generators (less than 3MW) to sell power to the utility at
predefined terms and conditions, without engaging in contract
negotiations. The Program cap is estimated at approximately 14 MW;
Generating Facilities participating in the Feed-in Tariff program may not
offset load at the site/facility nor are they eligible for any other IID for
renewable technologies program (i.e., net metering rate, virtual net
metering rate, etc.). As of the end of 2023, there were five projects in the
FIT program.
3) Emission Reduction Program-The proposed Cap-and-Trade Program establishes
a declining annual aggregate emissions limit for regulated sources and provides
rules for the sale of emission allowances pursuant to AB 32. The Program then
allows utilities, manufacturers and other emitters to “trade” pollution permits, or
allowances, among themselves. IID’s amount of allowed emissions is not
decreasing. This is mainly due to the methodology that was used by the state and
Southern California Public Power Authority (SCPPA) members. The SCPPA is a
joint action agency comprised of the cities of Los Angeles, Glendale, Burbank,
Cerritos, Vernon, Pasadena, Anaheim, Riverside, Azusa, Banning and Colton and
the IID (the only non-municipal member of SCPPA). The distribution of allowances
factors in growth and utility resource portfolio trends. Therefore, IID’s allowances
are fairly flat and this is mainly due to IID’s higher than normal forecasted load
growth rate and the associated resources that are in place to supply the energy
for that growth. The following is an emission reduction program initiated in 2018:
E-Green Program-The IID initiated a process to bring inexpensive utility scale solar
to its low-income residents and the ability to “go-green” to individual households.
The eGreen Program was customized to bring solar energy to low-income families
IMPERIAL IRRIGATION DISTRICT
10 8
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
while benefiting from IID’s ability to acquire attractive energy pricing. eGreen
allows IID’s customers to reap the benefits of clean, renewable solar power
without the need for on-site installation. The eGreen Program will allow all IID
customers to benefit from solar without concern of property ownership, structural
integrity, or financial ability. It enhances the ability for all IID customers to benefit
from solar. IID entered into a 23-year power purchase agreement with Citizens
Energy Corporation for 30 Megawatts of solar energy to serve approximately
15,000 low-income electric customers with a beginning cost of $29.75 per MWhr
and a start date of June 2019. Citizens Solar is contributing approximately 10
additional MWhrs to IID under a Low-Income solar Contribution Agreement,
bringing the blended cost of the 30MW to approximately $20 per MWhr.
b) Adequacy of Energy Conservation & Emission Reduction Programs
Energy Conservation Program Adequacy-The numerous energy efficiency programs
implemented by the IID over recent years have proven popular and successful in
contributing to energy conservation. Gross savings reported from conservation
programs implemented by the district in 2019-2021 saved participating customers
over 35,000,000 kWh and a cumulative verified net savings of over 35,000 MWh. The
most successful programs, in terms of energy saved, has been the Custom Energy
Solutions Program (CESP) and the Energy Rewards Rebate Program. Overall reported
savings were a result of various measures within the residential and commercial
sectors. Overall verified gross savings realized through the projects were at 92
percent of expected savings. It is recognized, however, that the Weatherization
Programs were not evaluated during this time period.
Renewable Energy Program- Since 2018 IID has contracted with four geothermal
projects for a total of 105 MW. IID has met the mandate to achieve California’s RPS
target of 33% of delivered energy coming from renewable resources by 2020 and is on
target to reach 60% of delivered energy sales by 2030 and beyond as required under
SB350. This is equivalent of approximately 370 MW by 2030, increasing to 960 MW by
2035 of solar generation, or some other intermittent resource such as wind. In 2018,
the district was within the 35 percent target for IID’s overall energy generation delivery
to customers coming from renewable energy sources. IID was on target (41%) in 2023
to meet the 2025 goal of 44% of its total energy deriving from renewable resources.
Emission Reduction program Adequacy-In an effort to meet annual GHG emission
standards IID retired its ownership in a portion of the San Juan Generating Station,
Unit 4 (SJGS) in 2018, reducing emissions throughout the last planning period. This was
a coal-fired plant in New Mexico that had relatively high GHG per MWh of generation,
approximately 2,400 lbs. per 1MWh compared to the legislated standard of 1,100
lbs./MWh. The 106 MW baseload capacity from San Juan has been fully replaced with
IMPERIAL IRRIGATION DISTRICT
10 9
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
renewable generation. In 2024, the district initiated the process of also retiring its
owned portion of the aging Yucca Steam Plant in Arizona and repowering it within the
next five years. Repowering options include hybrid solutions such as fast-start gas
turbines with or without battery storage. By 2035, all thermal units are expected to
operate on a blend of hydrogen and natural gas. These changes in addition to new
renewable energy and storage contracts have been procured by IID to facilitate
compliance with existing and upcoming clean energy targets of 90 percent of retail
sales by 2035.
c) Future Demand for Energy Efficiency & Conservation Facilities/Improvements
Energy Conservation Targets - By 2030, IID expects to reach new energy efficiency
targets of 26,960 MWh. The planned energy efficiency targets for the next seven
years are noted in Table CE- 1 IID Board Adopted Energy Savings Targets IID expects
to accomplish these targets with incorporation of at least three new energy savings
programs within the planning period.
Table CE- 1 IID Board Adopted Energy Savings Targets
MWh MWh New EE
(Market Potential (Codes & Targets
Year
Programs) Standards) (MWh Total)
2024 12,941 25, 752 38,693
2025 13,156 24,841 37,997
2026 13,172 22,933 36,105
2027 13,256 21,152 34,408
2028 13,098 18,740 31,838
2029 13,163 16,398 29,561
2030 13,167 13,793 26,960
Source: 2024 Draft Energy Integrated Resource Plan.
13
Renewable Energy Targets
As previously noted, future renewable energy targets are at 370 MW by 2030,
increasing to 960 MW by 2035 and 1,225 MW by 2045. IID plans to increase its
renewable energy portfolio predominantly with solar due to wind and solar
limitations within the near- and mid-term planning periods. New solar capacity is
expected to steadily increase from 2027 through the mid-2030s. The planned solar
capacity, when added to the portfolio would meet the 2030 RPS target of 60%
(measured as a percentage of retail sales) and the subsequent zero-carbon targets of
90% retail sales by 2035, 95% of retail sales by 2040, and 100% of retail sales by 2045.
IMPERIAL IRRIGATION DISTRICT
11 0
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
Emission Reduction Targets. Implementation of the aforementioned programs and
initiatives will enable IID to also meets its emission reduction targets. As noted, the
fossil fuel capacity in IID’s overall proposed IRP can run on renewable hydrogen
blended with natural gas. Further, El Centro Generating Station (ECGS) is developing
project alternatives to treat and reuse wastewater generated from power generation
operations, aiming to eliminate surface water discharge and approach a zero liquid
discharge facility.
Planned Energy Efficiency & Renewable Energy Projects
• Hell’s Kitchen Geothermal Project (50 MW)
• Brawley Solar (49.9 MW)
• Big Rock Solar Farms (200 MW)
Planned, New Energy Efficiency & Emission Reduction Programs
• Refrigerator Recycle Program
• Light the Way Program (LED Lighting for Sports Facilities Replacement)
• Festival of Lights Program (LED Lighting for Holiday Lighting Replacement)
d) Opportunities for Joint Energy Conservation Programs/Services
IID’s Path 42 Transmission Line Rebuild Project will rebuild two existing 20.6-mile
transmission lines in the Coachella Valley. The rebuild of the Coachella Valley-Ramon
transmission line, in conjunction with neighboring Southern California Edison’s
upgrade of its portion of Path 42, will address the “most restrictive” element in
transmission in renewable energy-rich Southern California. By upgrading from single
to double conductor per phase, the increased transmission capacity will reduce
congestion and enable the efficient flow of green energy to and from IID’s service
area.
Additional opportunities exist with private renewable energy developers. As
previously noted, IID anticipates coordination with private geothermal developers for
an energy export solution via a new transmission line originating in Imperial Valley
with the goal of maximizing IID’s ability to export energy generated by Independent
Power Producers (IPP’s) out of the District’s BA.
e) Phasing of Energy Efficiency & Conservation Projects/Programs
Short Term Improvements (Under 5 Years)
• Multiple Transmission Lines in IV to Accommodate Solar Generation
• Additional grid scale storage devices
• Geothermal Strategic Transmission (CTR)
IMPERIAL IRRIGATION DISTRICT
11 1
2025
SERVICE AREA PLAN CONSERVATION FACILITIES
• Hydroplant Refurbishment Drops 1, 2, 3, 4, & 5
• Yucca Steam Plant Repowering
• El Centro Unit 4 Repowering
• Electric Vehicle Investment
Mid-Term 5-10 Year Improvements
• Pilot Knob Hydroplant Rehabilitation and Major Refurbishment
• New Resource Assessment and Development
• Salton Sea Strategic Transmission
Long Term 10-15 Year Improvements
• Salton Sea Renewable Energy Initiative
3. Mitigation for Energy Efficiency & Conservation Efforts
IID should continue to pursue various means by which to maximize energy efficiency
and conservation benefits while maintaining adequate energy services to the IID Service
Area as a priority. The following mitigation measures are recommended for both Energy
Efficiency and Conservation (EC):
EC-1 Explore seasonally based resources, especially renewable resources
as much as possible.
EC-2 Continue to implement conservation and demand-side energy
management activities.
EC-3 IID should further investigate the option of self-managing a “build
and own” structure for a solar plant and other generation facility
technologies on IID-owned land as opposed to paying a developer to
manage the project development.
EC-4 Continue to implement IID’s hedging program to mitigate risks
anticipated from expected natural rise of energy and gas costs as well
as emissions and renewable costs.
EC-5 Develop a program for emissions trading and renewable energy
products under the Risk Management Policy to empower IID to
further ensure budgetary certainty and stabilize consumer rates.
EC-6 Continue to enter into power supply agreements from geothermal
generation and solar generation to meet Renewable Portfolio
Standards and Green House Gas emission goals.
IMPERIAL IRRIGATION DISTRICT
11 2
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
E. ADMINISTRATION SERVICE AND SUPPORT FACILITIES
As previously noted, the Imperial Irrigation District has two primary departments, the Water
Department and the Power Department. IID operates five additional support service
departments: Executive, General Services, Information Technology, Finance and Human
Resources. IID administrative facilities include all office buildings that house administrative
staff and provide general administrative and support services for the efficient delivery of
water services and energy services to its client base. Examples of administrative services
include management staff, clerk services, promotions of special events, management and
direction of planning and development services, utility billing and collection, procurement
and contract administration and other administrative functions of the district described under
these five support departments as summarized below along with their corresponding
business sections:
Executive Department-The Executive Department supports internal and external public
relations and contains nine executive sections, each with numerous administrative
responsibilities as noted below:
• Board of Directors Section performs major district functions such as defining IID goals
and objectives, acting as the custodian of IID property and resources, establishing IID
policies, reviewing all IID operations and employing IID executive management.
• Internal Audit Section is in charge of the district’s audit and at times the investigation
functions. The audit schedule is prepared by the Chief Internal Auditor during the
fourth quarter for the following year. Audits can also be requested at any time by the
Board of Directors.
• General Manager’s Section operates under the direction of the Board of Directors.
This section develops and implements overall goals, objectives, plans, policies and
organization of the Imperial Irrigation District.
• General Counsel’s Office Section serves as the General legal Counsel for the district
and directs and controls all legal functions, claims and litigation activities, and
activities of retained outside counsel.
• Public Affairs & Legislative Activity Section works under the guidance of the general
manager’s office to ensure the district’s public affairs and legislative activities are
representative of the board’s policy priorities and programs and oversees all
communication to its customers and key stakeholders and local, state and federal
elected officials as well as membership associations.
• Reliability Compliance Section is responsible for monitoring North American Electric
Reliability Corporation (NERC) and Western Electricity Coordinating Council (WECC)
reporting requirements as they relate to the district.
IMPERIAL IRRIGATION DISTRICT
11 3
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
• Enterprise Risk Management Section is responsible for the administration of a
comprehensive risk management program, including risk identification and
evaluation and the design and implementation of appropriate risk mitigation
strategies. This section has risk oversight for projects, operations, the merchant
function, insurance, and new initiatives. It also provides redundancy for the treasury
function.
• Real Estate Section is responsible for the administration of all district real estate
activity. Functions consist of the acquisition, disposition, and maintenance of
sustainable activities of district lands and facilities, including Western Farm Lands.
Services include right-of-way and easements, building leases and agreements,
encroachments and permissions, quitclaims and deeds and Salton Sea issues. This
Section is also responsible for ownership records as well as maintaining records of the
district boundary and service area.
General Services Department-The General Services Department provides numerous support
services, primarily to internal staff, and contains nine sections, each with responsibilities as
noted below.
• GS Administration Section provides overall support and management of the activities
of General Services’ Department; Facilities Management, Fleet Services, General
Services Asset Management, and Supply Chain Management: Purchasing, Contracts
and Materials and Stores. General Services provides management and maintenance
of district physical and rolling assets, and is responsible in accordance with policy for
the central procurement of goods and services in addition to the storage and
distribution of materials which support all IID operations.
• Fleet Services Section consists of four support units: Machine/Welding Shop, Heavy
Equipment Shop, Auto Shop, and Service Station. They provide the services that
support the company’s transportation needs for the rolling stock of fleet vehicles, off-
road heavy equipment, sump pumps, generators, compressors, portable pumps,
utility and equipment trailers and tools.
• Facilities Management Section is responsible for the administration, engineering,
planning, maintenance, construction and repair of over 700,000 SF of gross building
space which includes offices, shops, warehouses, service stations and other use
buildings throughout the district. The section is responsible for all levels of logistics
including HVAC, plumbing, construction, fire protection system, doors, keys, locks
and network cat 5 installations. This Section is also responsible for janitorial and
landscape services throughout district facilities.
IMPERIAL IRRIGATION DISTRICT
11 4
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
• Purchasing Section procures the district’s materials and outside service needs
directed by the Purchasing Policy. This Section processes requisitions and reservation
needs for Imperial and La Quinta network projects, maintenance orders and overhead
expense cost centers. They create, standardize, disseminate and administer formal
bids, requests for quotations/proposals, and informal quotes consistent with
established solicitation process, purchasing policy and IID procedures and applicable
laws.
• Contract Administration Section provides services to departmental personnel in
drafting, negotiating, and administering resource contract needs, professional service
agreements, and construction contracts. They assist departments in assembling and
evaluating formal solicitation packages, performing project risk assessment and
ensuring all requirements are met in accordance with IID policies and procedures.
• Asset Management Section is responsible for managing the General Services Asset
Management Program, primarily for Facilities Management and Fleet Services
sections. This section provides strategic direction, reporting on program initiatives
and manages the department’s capital projects, facilities and equipment by
promoting proactive maintenance and capital renewal.
• Materials Resources and Dispersal Section is responsible for the receipt, issuance
and storage of all materials purchased by the district. Material Resources staff are
responsible for “first responder” hazmat responses, and dispose of all obsolete, scrap
and other materials that are deemed to be of no further use to the district.
• Regulatory and Environmental Compliance Section provides regulatory compliance
development, implementation and monitoring services that meets the expected
goals of complying with mandated regulatory agency requirements. This Section
provides environmental assessment and permitting for all district projects and
reviews external environmental documents for potential impacts to the district and
consults with outside agencies on behalf of the district.
• Hazmat Section provides regulatory compliance services for all district departments.
These services include regulatory assessments, oversight and auditing for all district
facilities and projects, consultation with regulatory and resource agencies, hazardous
materials and waste identification, including handling, storage and disposal,
emergency response and regulatory training.
Information Technology Department-The Information Technology Department
implemented strategic organization and now contains thirteen sections, all in support of IID
operations and each with responsibilities as noted below.
• Information Technology Management Administration Section - The primary
responsibility of this group is to manage the department’s resources and to provide
IMPERIAL IRRIGATION DISTRICT
11 5
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
strategic direction, report on department initiatives and manage the district’s
Information Technology Systems.
• IT/OT Infrastructure & Operations Section - This section is comprised of the Network
Support unit which provides IID technology users support services for desktop PCs,
laptops, tablets, IP telephones, multifunction printers, smartphones, TV/monitors
and projectors along with network connection and firewall protection services.
Specialists provide design, configuration, administration, maintenance and support
of Local Area Networks (LAN), Wide Area Networks (WAN), Wireless Local Area
Networks (WLAN), Virtual Private Networks (VPN), Voice over Internet Protocol (VoIP)
technologies, Water Control Center network and Energy Management Systems
network support. Focused attention is also towards network resiliency and meeting
reliability compliance security measures for documenting NERC CIPS standards.
Evidential documentation and monitoring for pertinent Compliance standards are all
maintained up to date for Western Electrical Coordinating Council (WECC) audits.
• Information Technology Services Support Section – The major area of responsibility
for this section is to serve as a first point of contact for the district’s information
technology needs. A Service Desk is a strategic asset to the district, and is used to
identify areas of improvement to help keep IID employees performing at the highest
possible level.
• GIS Section – This section is responsible for developing and adhering to consistent
business practices and processes throughout the organization to meet customers’
needs. The unit's mission is to: 1) Develop strategies to align IID with enterprise goals
set by board and general manager; 2) Develop and adhere to consistent business
practices and processes throughout IID to meet customers’ and staff needs; 3)
Provide a robust and high-quality geographic information system that empowers
users to efficiently access, manage, maintain and share accurate reliable and
consistent geographic data , easily and quickly analyze and obtain information in
various formats on demand; and 4) Create and implement an applications strategy
to address specialized application requirements including real time, mobile and
responsive application design.
• EMS/CIPS Compliance Section - This section is responsible for the operation of the
computer systems used for the control, operation and scheduling of the electric
system including the operation of the automatic generation control (AGC), energy
trading and accounting systems, NERC electronic tagging system and other computer
hardware and software. EMS is responsible for NERC CIPS compliance for Power
Department's System Operations Center (SOC).
• Customer Applications Section- The Customer Applications Support section is
IMPERIAL IRRIGATION DISTRICT
11 6
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
responsible for providing Functional and Technical IT support to the Meter-To-Cash
(M2C) business processes in the context of SAP and other Third-Party system
applications. This section is also responsible for the Analysis, Design, Configuration,
Development and Testing of application solutions such as, but not limited to Billing,
Credit and Collections, Payment Processing, Call Center Operations, Field Services and
Device Management to support our AMI/AMR infrastructure. This section also plays
a critical role in Continuous Process Improvement initiatives and the associated
project implementations in order to meet the needs of ongoing Business Unit
operations.
• Development & Portals Support Section provides management support, standards,
methods, and coordination of application development to help improve, or automate
business processes. The section proposes testing methods for new or enhanced
applications and design application solutions and interconnections improvements to
enhance functional area processes and reduce costs. This section diagnoses, fixes,
maintains, designs, installs, tests, and develops computer applications and interfaces
between different computer systems.
• Corporate Infrastructure Engineering Section is responsible for the engineering
design, strategic alignment, lifecycle management, security and administration of all
server-based computing and network systems. This Section is also responsible for the
management of the data center and for the delivery of technical support to IID
technology users and to certain contracted partners utilizing IID’s technology
infrastructure. The section also provides tier two and above desktop support, which
includes deployment and support of applications, workstations, monitors, laptops,
UPS devices, and other associated peripherals. Enterprise systems/environments
include SAP, GIS, Netweaver, WIS, SharePoint, Intranet, Oracle, File & Print services,
servers, email system, backup & recovery, user identity management, physical access
systems, and other application servers located in the IID's IT data centers. this section
additionally provides technical, architectural engineering and systems engineering
support to the Power Systems Operations Center and associated facilities.
• Work and Asset Management Applications Section – This section provides
management support, standards, methods and coordination to support Work & Asset
Management related applications. The section also develops testing methods,
process improvements, SAP configuration, and design of application improvements
to enhance functional area processes and reduce costs. This section also diagnoses,
fixes, maintains, designs, installs, tests, and develops computer applications,
document management and third-party computer applications.
• Enterprise Applications Section – This section manages the definition, design,
configuration, development, testing, implementation and on-going support of new,
IMPERIAL IRRIGATION DISTRICT
11 7
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
or improved, existing enterprise applications and systems. This section provides
management support, business analysis, operational assessments, process
documentation, technological and functional solutions, recommendations, training
and change management to support the design and implementation of application
and/or process improvements to enhance productivity.
• Finance & HR Applications Section -This section provides management support,
business analysis, process documentation, technological and training for the
development, maintenance and support of existing and new business systems and
applications to help improve the district’s processes and enhance productivity.
• Telecommunications Section provides SCADA and data communications for
substations, generation facilities and interconnections, and the water department
canal systems; provides communication networks for system protection circuits;
installs and maintains generation and interconnect meters; upgrades and maintains
the advanced metering infrastructure field area networks; upgrades and maintains
the two-way radio system, telephone, video surveillance and substation security
systems.
• Records Management Section is responsible for the administration of company-wide
records management activities, mail services and electronic document management
services and provides efficient and excellent service to IID’s internal and external
customers.
Finance Department- The Finance Department contains six sections, providing services for IID
operations as well as internal and external customers. The responsibilities of each section are
noted as follows:
• Chief Financial Officer Administration Section is responsible for the administration
of the Finance Department including controlling, accounting, treasury, financing,
budgeting and enterprise risk management.
• Business Systems & Support Section provides business analysis, operational
assessments, process documentation, technological and functional solutions
recommendations, training and change management to support the design and
implementation of applications and for process improvements to enhance
productivity to the Finance Department.
• Treasury Section is responsible for IID’s cash management and investment and
objectives include investing IID’s cash safely and in conformance with IID’s investment
policy and Government code through monitoring, managing, projecting and reporting
the district’s operating cash requirements to ensure the district’s liquidity needs are
met.
IMPERIAL IRRIGATION DISTRICT
11 8
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
• General Accounting Section is responsible for IID’s general accounting, payroll,
accounts payable and objectives include creating, maintaining, balancing and
reporting the district’s general ledger and financial statements, disbursing accounts
payable and payroll funds accurately and in a timely manner.
• Enterprise Budget, Financial Performance & Rates Section is responsible for
budgeting, financial and economic analysis, controlling and process analysis and rates
and contracts functions. All study findings and recommendations are made to the
Board of Directors and public.
• Customer Service Section is responsible for the meter to cash processes, including
bill print, mail, call center, credit and collections. This section also handles court
subpoenas, liens, bankruptcies, bad debt, works with agencies for customer funding
and monitors/contacts delinquent commercial accounts for payment or disconnect.
Human Resources Department-The Human Resources Department contains nine sections,
primarily with internal support services. The Human Resource responsibilities are noted
below for each section.
• HR Administration Section manages functions, activities and personnel engaged in
employment and compensation, training and employee development, employee
benefits and workers’ compensation, human resource records and employee
relations, conducts human resources research studies and directs the maintenance
of personnel files.
• Employee Relations Section is responsible to provide professional human resources
services to both internal and external customers. In addition to employment relations
and training they are responsible for compensation management, Affirmative Action
and labor compliance with state and federal regulations. The section is responsible
for payroll records, statistical reporting, mandated reports and surveys and
responding to discrimination complaints and assisting legal with litigation and
responding to unemployment insurance claims.
• Recruitment and Selection Section is responsible for the administration of all
recruitment and selection activities including screening applications, reviewing
personnel files, administering tests, interviews, reference checks and detailed
background checks to all initial hires.
• Business Processes Unit has the main responsibility to lead business project
assignments and analyze business functions to determine computer system
application requirements, and improve business processes, application design, test
and implementation as well as payroll records including HRIS, statistical reporting,
costing and controlling of District staffing, submitting mandated reports and surveys
to state and federal agencies providing documentation to implement and support the
Human Resources Department.
IMPERIAL IRRIGATION DISTRICT
11 9
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
• Employee Benefits and Disability Services Section is responsible for the
administration of all district health, retirement and benefit plans along with the
Integrated Disability Management Program. The staff works with plan administrators,
carriers, consultants, advisory groups, management, the Board of Directors,
employees, supervisors, retirees, dependents, legal counsel and others to provide
information and services.
• Personnel Development Section administers and coordinates all personnel
development functions for the district. The section is responsible for tuition
reimbursement, software instruction, apprentice programs, academic and career
counseling and planning and similar services.
• Safety Services Section is responsible for workplace safety, minimizing district liability
as it relates to accidents, illnesses and injuries and reducing accidents and injuries.
This section assists and trains supervisor in performance of their safety related duties
and coordinates Safety committee activities and over 100 mandated programs and
over 100 certifications.
• Security Services Section ensures the district meets physical security portions of the
applicable policies and regulations, it investigates all incidents involving property
damage, theft, vandalism, or any other activity requiring investigations, and oversees
and maintains drug and alcohol testing programs. It also emphasizes the Revenue
Protection program on meter tampering/energy theft.
1. Performance Standards for Administration Services & Facilities
Administrative Personnel-Most public agencies/jurisdictions adopt administration
service standards based on personnel (full-time employee or FTE) per population served.
The performance standard for providing administrative personnel is generally established
at a range of 0.50 to .75 FTE per 1,000 in population served. IID’s performance standard
for administrative personnel has been pre-established at .75 FTE per 1,000 residents
served. Based on the 2023 estimated population of 420,778, a total of 315 FTE is required
in order for IID to meet this performance standard, calculated as follows:
.75 FTE x Population Served /1,000 = Total 2024 FTE Demand
.75 FTE x 420,778/1,000 = 315 FTE
IMPERIAL IRRIGATION DISTRICT
12 0
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
Administrative Facility Space-Generally, a performance standard for administrative
facilities ranges from 500-600 square feet per 1,000 in population served. Management
determined that the 2018 facility space was adequate to serve the existing populations
and therefore, the performance standard for administrative facilities for IID was
established at that time at 450 square feet of building space per every 1,000 of population
served. Based on this pre-established standard, the current demand for administrative
facilities is 189,350 SF as calculated below.
450 SF x Population Served/1,000 = Total 2024 Admin Space Demand
450 SF x 420,778/1,000 = 189,350 SF
The building area available per full-time employee must also be adequate. The general
rule of thumb is to allow anywhere between 125 and 225 square feet of usable office
space per person. IID completed an assessment of space requirements in July of 201224
which recommends a range of space between 120 and 360 square feet of usable office
space per employee that varies by position and/or title. The Standard for IID
administrative staff was thereby established at 125 SF of usable office space per
administrative/support FTE which includes all of staff within the Executive, Human
Resources, Information Technology, Finance and General Services Departments. This
performance ratio will be applied when examining each of the departments
independently, but not to the section levels.
125 SF x Admin FTE = Building Space Demand/Department
2. Administration/Support Facility Planning and Adequacy Analysis
An inventory of the existing IID Administrative and Support Facilities owned, or leased,
by the Imperial Irrigation District is presented herein, as well as the future demand for
administrative facilities and their projected phasing schedule. The purpose of this
analysis is to determine if the existing facilities are adequate in size for the existing and
projected future demand. The condition of the existing facilities is not examined in this
Service Area Plan.
a) Inventory of Existing Administrative/Support Facilities
IID Administrative and Support Facilities are located in numerous communities
throughout Imperial and Riverside counties. The administrative facilities in 2018
consisted of a total of 189,912 square feet and increased to 191,442 square feet by
2024 as noted in Table A- 1. The facilities support a total of 500 employees in 2024, a
24 Final Report of Space Requirements HQ Facilities Development Program Management Project by Griffin-Lyon
Program and Construction Managers, LLC., July 18, 2012.
IMPERIAL IRRIGATION DISTRICT
12 1
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
difference of approximately -13% from the 463 full-time equivalent employees in
2018. There are additional common areas that are shared with the Water and/or
Power Departments and those are excluded from assessment.
Table A- 1 Administration and Support Facilities Inventory
Department 2018 2024 2024
Total Dedicated Total SF Total Dedicated
Office Space SF Office Space SF
Executive 11,167 14,375 12,058
General Services 19,098 25,465 24,988
Information Technology 24,469 25,486 24,691
Finance 15,398 16,195 15,398
Human Resources 15,421 15,934 14,191
Total SF 85,553 97,455 91,326
Exclusive Admin Common Areas 0 93,987 0
Total Administration SF 85,553 191,442 91,326
Source: IID General Services staff, Building Inventory and Dedicated Office Space March 2024.
Total Administrative Personnel per 2024 Budget by Department (500 FTE)
Executive Department Personnel 2024 (48 Total Positions):
• Board of Directors (5 positions)
• Internal Audit Section (4 FTE)
• General Manager’s Section (4 FTE)
• General Counsel’s Office Section (8 FTE)
• Public Affairs Section (13 FTE)
• Reliability Compliance Section (4 FTE)
• Enterprise Risk Management (1 FTE)
• Real Estate Section (9 FTE)
General Services Department Personnel 2024 (147 Total Positions):
• Administration Section (4 FTE)
• Fleet Services (50 FTE)
• Facilities Management Section (32 FTE)
• Purchasing Section (13 FTE)
• Contract Administration Section (6 FTE)
• Asset Management Section (9 FTE)
• Materials Resources and Disposal Section (24 FTE)
• Regulatory & Environmental Compliance Section (4 FTE)
• Hazmat Section (5 FTE)
IMPERIAL IRRIGATION DISTRICT
12 2
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
Information Technology Department Personnel 2024 (129 Total Positions):
• Management Administration Section (8 FTE)
• Networks & PC Support Section (10 FTE)
• GIS Section (10 FTE)
• EMS CIPS Compliance (15 FTE)
• Customer Support Center Section (5 FTE)
• Customer Applications Section (4 FTE)
• Development & Portal Support Section (7 FTE)
• Corporate Infrastructure Engineering Section (13 FTE)
• Work and Asset Management Applications Section (5 FTE)
• Enterprise Applications Section (2 FTE)
• Finance & HR Applications Section (4 FTE)
• Telecommunications Section (33 FTE)
• Records Management Section (13 FTE)
Finance Department Personnel 2024 (133 Total Positions):
• Chief Finance Office Administration Section (5 FTE)
• Business System Support Section (3 FTE)
• Treasury Section (2 FTE)
• General Accounting Section (11 FTE)
• Enterprise Budget, Financial Performance & Rates (9 FTE)
• Customer Service Section (103 FTE)
Human Resources Department Personnel 2024 (41 Total Positions):
• Administration Section (2 FTE)
• Employee Relations Section (7 FTE)
• Recruitment and Selection Section (5 FTE)
• Employee Benefits & Disability Section (7 FTE)
• Personnel Development Section (4 FTE)
• Safety Services Section (6 FTE)
• Risk Management/Security, Claims and Investigations Section (10 FTE)
Total Admin/Support Vehicles per 2024 Budget (169 Total Vehicles):
• Executive Department - 13 Total Vehicles
• General Services Department - 60 Total Vehicles
• Information Technology Department - 42 Total Vehicles
• Finance Department - 26 Total Vehicles
• Human Resources Department - 19 Total Vehicles
b) Adequacy of Existing Administrative/Support Facilities
Administrative Personnel- The performance standard for providing administrative
personnel was established at a minimum of .75 FTE per 1,000 in population served.
Evaluation of this standard would then be based on the current level of administrative
staff (500 FTE) per population served by the district (420,778), divided by 1,000. The
total population within the IID Service areas (water and energy service areas) was
calculated using Department of Finance data and discounted proportional share of
IMPERIAL IRRIGATION DISTRICT
12 3
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
Coachella Valley communities not entirely served by the IID. Per 2024 conditions, IID
exceeded the established performance standard for administrative personnel of .75
FTE per 1,000 in population served as noted below:
Total Admin Staff ÷ Population Served/1000 = Performance Level
500 FTE 420,778/1,000 1.19 FTE
Administrative Facility Space-The performance standard for administrative facility
space was established at 450 square feet of building space per every 1,000 of
population served. The existing and dedicated administrative space of 97,455 SF
coupled with an additional 93,987 square feet of common areas that are shared only
by administrative staff, slightly exceeds the established performance level. Not all
common areas were accounted for under this assessment (power department and
water department administration facilities) because they are not exclusive to
administration/support departments.
Total Building Area ÷ Population Served/1,000 = Performance Level
191,442 420,778/1,000 455 SF
Office Space per Full-Time Employee- Adequacy of building area is supported by the
level of dedicated (usable) office space per full-time employee. The dedicated and
usable office space available per full-time employee was assessed against the 125 SF
per FTE standard, District-wide for administrative facilities as a whole. It has been
determined that the office space available for the 500 administrative support
employees exceeded the established standard in 2024 providing an average of 183 SF
per FTE. The findings were determined by taking all Administrative/Support Services
Department office space in 202425, excluding all common areas, and dividing it by the
full tally of administrative/support staff for the respective year:
Total Usable Office Space ÷ Total Admin Staff = Space Per FTE
91,326 SF 500 FTE 183 SF/FTE
The available office space per employee standard was has also been applied to each
independent administrative department, at its respective staff level, to identify the
adequacy of office space within each given unit. The Finance Department is the only
unit demonstrating a slight deficiency at an average of 116 SF per employee. The 2024
findings are summarized in Table A- 2 and in the narrative that follows.
25 Office Space was provided by General Service Staff after discounting unusable space and storage facilities from
total building area. The feasibility of future space conversion is not taken into account at this time.
IMPERIAL IRRIGATION DISTRICT
12 4
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
Table A- 2 2024 Office Space Adequacy for Administrative and Support Staff
Total SF of Total SF of Usable
Dedicated Department Office Space
Department
Office Space FTE Available Per
FTE
Executive 12,058 48 251
General Services 24,988 147 170
Information Technology 24,691 129 191
Finance 15,398 133 116
Human Resources 14,191 41 346
Total 2024 SF 91,326 498
Source: IID General Services staff, Building Inventory 2024 and Dedicated Office Space
March 2024 and FTE Data from Adopted 2024 Budget.
Executive Department (48 Total Positions):
There are 48 Full Time Equivalent Employees in the Executive Department operating
under 14,375 SF of administrative facilities. Of this space, only 12,058 SF is usable
office space, which is the equivalent of 251 SF of office space per employee. Using
the performance formula established of 125 SF of office space per FTE, the Executive
Department facilities are adequate containing a substantial surplus of administrative office
space to accommodate future growth.
Existing Executive Department Office Space – Current Demand = Adequacy
12,058 SF – 6,000 SF Demand = 6,058 SF Surplus
General Services Department (149 Total Positions):
There are 147 Full Time Equivalent Employees operating in the General Services
Department under 25,465 SF of administrative facilities. Of this space, only 24,988 SF
is dedicated office space which is the equivalent of 168 SF of building space per
employee. Using the performance standard of 125 SF of usable office space per FTE,
the existing demand for General Services administrative office space is above
satisfactorily and demonstrated a 2024 surplus of 6,613 square feet. This department also
shares over 29,000 SF of common areas exclusive to administrative services.
Existing General Service Office Space – Current Demand = Adequacy
24,988 SF – 18,375 SF Demand = 6,613 SF Surplus
IMPERIAL IRRIGATION DISTRICT
12 5
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
Information Technology Department (129 Total Positions):
There are 129 Full Time Equivalent Employees operating in the Information
Technology Department under 25,486 SF of administrative facilities. Of this space,
only 24,691 SF is dedicated office space which is the equivalent of 191 SF of dedicated
office space per employee. Using the performance standard of 125 SF of office space
per FTE, the existing demand for administrative office space in the IT Department is
being satisfied and has a moderate surplus that may accommodate future growth.
Existing Information Technology Office Space – Current Demand = Adequacy
24,691 SF – 16,125 SF Demand = 11,597 SF Surplus
Finance Department (133 Total Positions):
There are 133 Full Time Equivalent Employees operating in the Finance Department
under 16,195 SF of administrative facilities. Of this space, only 15,398 SF is usable
office space, which is the equivalent of 116 SF of office space per employee. Applying
the performance standard of 125 SF/FTE, results in modest office space deficiencies
for the Finance Department as follows.
Existing Finance Office Space – Current Demand = Adequacy
15,398 SF – 16,625 SF Demand = -1,227 SF Deficiency
A contributing factor to the reduced SF per FTE of the Finance Department is the call
center under which 29 personnel work off of a smaller work area not commensurate
to a traditional office. Another factor is finance personnel dedicated to Water
Department and finance personnel dedicated to Power Department have dedicated
space within the respective Water and Power department offices. These findings do
not warrant the need for expanded facilities to accommodate Finance staff.
Human Resources Department (41 Total Positions):
There is a total of 41 Full Time Equivalent Employees operating in the Human
Resources Department under 15,934 SF of administrative facilities. Of this space, only
14,191 SF is usable office space which is the equivalent of 335 SF of building space
per employee. Using the performance formula of 125 SF of office space per FTE as
calculated below, the existing demand for administrative facilities is 5,125 square feet
resulting in a 2024 surplus of office space for the Human Resources Department.
Existing Human Resource Office Space – Current Demand = Adequacy
14,191 SF – 5,125 SF Demand = 9,066 SF Surplus
IMPERIAL IRRIGATION DISTRICT
12 6
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
c) Future Demand for Administrative Facilities & Planned Facilities
Future Demand-For the purpose of calculating future demand, and as previously
noted, growth rate history is applied to current population estimates to project
population demand. Using the existing performance standard formula of 450 SF
per 1,000 in population served, IID may need 328,063 square feet of administrative
space by the year 2040. Facilities can be expanded and/or planned for as new hires
are projected, or as noted under Table A- 3 Administrative Facilities Future Demand.
It is worth noting, however, that the current population (2024) is estimated at
420,778, substantially below what was originally projected through 2040. A
projection adjustment will likely be warranted in 2030 for another 20-year outlook.
Table A- 3 Administrative Facilities Future Demand
Year Population Administrative Space
Projections All Service Demand
Areas
2025
523,890 235,890 SF
2030
584,260 262,917 SF
2035
643,749 289,687 SF
2040
729,028 328,063 SF
The total amount of space available for administrative facilities in 2024 was 191,442
square feet (an increase from 189,912 square feet in 2018). As the served population
increases, there will be an inherent need for additional administrative facilities.
Planned Administrative Facilities- All of the district’s construction projects and major
capital purchases are included in the Capital Improvement Plan which is incorporated
into the district’s annual budget as a two-year plan. As of the date of this 2025 Service
Area Plan, there continues to be a consistent $2 to $5 million annual budget of capital
investment for building upgrades but no new planned Administrative Facilities for
personnel given that the available space largely meets and/or exceeds the adopted
standards. It is anticipated, however, that within the next five-year timeframe design
and planning costs will be budgeted for a new System Operations Center facility with
construction tentatively scheduled to initiate in 2028. The Southend Consolidation
would also initiate during this upcoming planning period for the benefit of the Water
Department. A major undertaking will also be the design and development of new
Administrative Building consolidation is also expected to initiate within the next five-
year planning period.
IMPERIAL IRRIGATION DISTRICT
12 7
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
d) Opportunities for Shared Administrative Facilities & Services
The majority of IID building facilities are shared by multiple departments internally
and inclusively have an estimated 594,258 square feet of common areas. While only
93,987 are common areas exclusive to administration and support departments,
there are over 500,000 square feet of common areas that are shared facilities with
other departments, aside from administration. This space can be evaluated and
considered for reconfiguration in the future to accommodate additional need for
space or exclusive office use.
IID provides for all of its administrative needs using full-time, part-time and contract
workers. Cross-utilization of services within the District departments and Service
Sections is facilitated throughout the organization. Senior staff members in the Water
Department and Power Department provide their expertise for administrative
functions and services. For example, the Water Department Managers and several
other employees of the Water Engineering section will complete tasks that are
administrative in nature, and indirectly related to the needs of various water
facilities and services. These tasks are funded through the respective section budgets
of the various departments from which the tasks are being completed. This
method of cross-utilization is an efficient use of existing resources.
IID will often provide administrative services to regional groups and organizations
that will provide a beneficial service to the communities served by the District. For
example, IID provides administrative and technical support to the Imperial County
Farm Bureau (ICFB) for TMDL reporting efforts. Regulatory fees imposed by the State
Water Resources Control Board are collected by IID from agricultural land owners on
behalf of the ICFB (representing the Imperial Valley Coalition) and administratively
accounted for and paid to the SWRCB. Additionally, IID subsidizes the cost of ICFB
staff for the administration and implementation of the TMDL program. Since 2000,
IID has provided over $2 million in funding to the ICFB for program implementation,
and in 2024 contributed $421,605.
e) Phasing of Administrative Facilities
Other than the planned design of a new System Operations Center facility over the
next five-year timeframe design IID has two other planned facilities, one of which is
the planned designed and development for consolidated administrative support
services in the latter part of the planning period. It is noted, however, that there is
ample building space within all District facilities to explore the possibilities of
reorganization and relocation, if necessary.
IMPERIAL IRRIGATION DISTRICT
12 8
2025
SERVICE AREA PLAN ADMINISTRATION SERVICES
3. Mitigation for Administrative Facilities
IID will continue to review the personnel level and facility space available against the
demand for facilities based on the established performance standards. Additional facilities
will be planned for and provided on an as needed basis. The following are mitigation measures
for administrative facilities:
A-1 IID should consider updating the Headquarters Space Assessment & Strategic
Business Plan Summary last modified in May 28, 2013.
A-2 By the year 2030 a reassessment of the population growth shall be updated and
incorporated (over a 20-year time period), a at which time additional square
feet of administrative facilities should be planned for, or reconfigured, in order
to meet the projected service demand through 2050.
IMPERIAL IRRIGATION DISTRICT
12 9
2025
SERVICE AREA PLAN FINANCING PLAN
IMPERIAL IRRIGATION DISTRICT
13 0
2025
SERVICE AREA PLAN FINANCING PLAN
V. FINANCING PLAN
The most current available Financial Statement for the Imperial Irrigation District was reviewed
for 2022 and 2023 calendar years. As of December 31, 2023, the assets and deferred outflows of
resources of the District exceeded its liabilities and deferred inflows of resources by $2.01 billion
(net position); made up by Energy $1.08 billion and Water $0.93 billion. The Financial Statements
show that IID reported positive balances in net position of which approximately 75.1% and 77.2%,
(2022 and 2023, respectively), were in capital assets. The district’s total 2023 unrestricted portion
of its net position had a slight (1.2%) increase from prior year ending at $441 million. The district’s
total outstanding debt from Revenue Bonds, Pension Obligation Bonds, and Capital Leases, as
long-term debt, was $614.9 million as of December 31, 2023 (decrease by $31.1 million in 2023).
This data represents a snapshot of the district’s overall financial health. A complete copy of the
December 31, 2023 and 2022 Audited Financial Report may be found at: Reports | Imperial
Irrigation District (iid.com) and included as Appendix A.
IID’s 2025 budget of $1.1 billion is primarily funded through established rate structures but also
supported via numerous financing mechanisms. This Financing Plan section of the Service Area
Plan lists and describes existing and potential revenue sources and the various financing
mechanisms that may be available to the District in efforts to continue to meet the projected level
of service and facility demands identified earlier in this document. Content describes existing
facilities and services, their current finance source(s) and how future financial demands for these
facilities and services may be secured.
A. EXISTING REVENUE SOURCES
The following list presents sources of revenue that are currently utilized by the Water
Department and/or the Power Department to satisfy finances necessary to develop and
operate the various facilities and services discussed within the Service Area Plan. For context,
it shall be noted that the Power Department has an annual revenue budget of over $813
million, which is more than double of the Water Department’s annual revenue budget of $320
million, as per the adopted 2025 Budget. Complete budgetary information for financing
mechanisms currently utilized is available on-line for viewing at IID Budget Plan | Imperial
Irrigation District.
Water Department Revenue Sources
The District’s goal is to deliver irrigation water cost effectively, efficiently and reliably to its
water users. Revenues for the Water Department come from the following sources:
1. Water Sales- Local water sales accounts for an estimated 14% of the Water Department
Budget as documented for 2023. Direct water sales to service area customers had an
average cost of $21.13 per acre-foot, generating over $50 million in water sales revenue.
IMPERIAL IRRIGATION DISTRICT
13 1
2025
SERVICE AREA PLAN FINANCING PLAN
This revenue source will continue to be available through the next five-year planning
period.
2. Water Transfer Revenues- The primary sources (57%) of revenue for the Water
Department are the water transfer sales. Water Transfer sales were documented at $176
million in 2023. Water Transfer sales are anticipated to continue throughout the planning
period and increase in volume and value through the planning period and be augmented
in years 2024 through 2026 under a temporary System Conservation Implementation
Agreement with the U.S. Bureau of Reclamation. These revenues are generated from
water transfers to the San Diego County Water Authority (SDCWA), the Metropolitan
Water District (MWD), the Coachella Valley Water District (CVWD) and, temporarily, to
Reclamation.
3. All-American Canal Reimbursements- The Water Department receives slightly under 4%
of its annual revenue from All-American Canal Reimbursements. The District received
over $12.6 million in reimbursements during 2023 from agencies for the costs of
construction and annual charges for the operation and maintenance of the canal.
4. Water Availability Fees- The Water Department receives approximately .5% of its
revenue from Water Availability Fees. The Water Availability fee is a $4 ($3.80 net) per
acre fee charged to water customers. The Water Availability Fee is charged annually,
generated $1.9 million in 2023, and is anticipated to stay fairly constant throughout the
planning period.
5. Rental Income (Leased Lands)- An estimated 1% of all Water Department revenues come
from Rental Income. That amount is derived from Western Farm Lands (WFL) leased for
agricultural production and from land leased to geothermal interests. IID purchased
41,761 acres of agricultural land, WFL’s, in 2004 in order to facilitate the District’s ability
to perform transfer obligations, should fallowing be unavoidable. In 2015, 185.4 acres
were sold and the remaining acreage is leased to local growers. The District received $1.6
million in lease revenue from WFL’s in 2023. The amount of revenue derived from
geothermal leases around the Salton Sea area was approximately $1.1 Million for the
same calendar year. The District anticipates a modest increase for subsequent years to
compensate for inflation.
6. Capital Contribution Proceeds Support & Customer Projects- This revenue source
consists of prefunded and reserved resources. This source of revenue may be loans tied
to vehicle purchases or capital projects funded by others. As part of the water transfer
agreements, there are a number of capital projects that have been prioritized and paid
for by the SDCWA. Other capital contributions come from customers projects including
cities and private developers. This revenue is restricted and carries over when a project
is not carried out.
7. Lost Water Sales- Approximately 1.9% of the annual revenue is from Lost Water Sales,
IMPERIAL IRRIGATION DISTRICT
13 2
2025
SERVICE AREA PLAN FINANCING PLAN
amounting to $5.7 million in 2023. Reduced water sales (attributed to water transfers)
result in IID’s operation and maintenance costs being spread over a smaller sales base.
Normally, this would result in an increase in water rates. However, rather than allow rates
to rise to the detriment of the local agricultural economy, lost water sales revenues
attributable to water transfers are allocated to the general Water Department operations
from water transfer revenues.
8. Quantification Settlement Agreement/JPA Revenues- IID receives an estimated 5% of
Water Department Revenue from the Joint Powers Agreement under the QSA. These
revenues, which amounted to $14.9 million in 2023, are reimbursements for costs
incurred for Environmental Mitigation and for Salton Sea Restoration beyond IID’s
stipulated share between the Coachella Valley Water District, IID and San Diego County
Water Authority. Any costs beyond the JPA limitations would be satisfied by the State
(Department of Fish and Wildlife).
9. Water Supply Development Fees- The Water Department receives just under $2 million
annually from private developers via Water Supply Development Fees. These funds are
placed in a reserve account for the development of water conservation projects in
support of the development’s water supply demand. This fund resource is developer
driven and thus projected to remain constant, but with a potential to increase depending
on the building market. The annual fee is applicable for new non-agricultural projects as
established under the Interim Water Supply Policy. A project is subject to the
Development fee when 1) the water demand for the municipal use project is in excess of
the project’s estimated population multiplied by the district-wide per capita usage; 2) a
project will require water for an industrial use in an unincorporated area of the County of
Imperial; or 3) mixed use projects. The calculation is based on a tiered fee schedule as
noted in Table F- 1 below, charged per acre-foot, annually.
Table F- 1 2024 Interim Water Supply Policy Development Fee
Annual Demand (Acre-Feet) Development Fee*
0-500 $355.07
501-1000 $499.94
1001-2500 $627.76
2501-5000 $775.47
*To be adjusted annually in accordance with the consumer Price Index (CPI)
10. Water Reservation Fees-The Water Reservation Fee is also a developer driven fee that is
a non-refundable fee charged by the District when an application for water supply for a
non-agricultural project is deemed complete and approved. This fee places the projected
water supply in a queue up to the start-up of construction, by which time IID will need to
have the water demand volume available from conservation efforts. The reservation
IMPERIAL IRRIGATION DISTRICT
13 3
2025
SERVICE AREA PLAN FINANCING PLAN
period is for a maximum period of two years (renewable for another two years subject to
an additional fee per renewal). The Water Department receives a nominal amount of
revenue from Water Reservation Fees and is typically not a projected income. This
revenue may become an important source of income if an influx of new development is
experienced during the planning period. The following table depicts the applicable
reservation fee calculated per acre-foot demand annually.
Table F- 2 2024 Interim Water Supply Policy Reservation Fee
Annual Demand (Acre-Feet) Reservation Fee*
0-500 $88.77
501-1000 $124.98
1001-2500 $156.94
2501-5000 $193.87
*To be adjusted annually in accordance with the Consumer Price Index (CPI)
11. Federal and State Grant Programs- IID is eligible to apply for state and federal grant
funding to augment and supplement local revenues earmarked for capital improvements
or special programs. IID has been successful in obtaining some level of grant funding for
Water Department projects with the most recent award in 2023 for a total of $16.5
million. Grant revenues are unpredictable and it is estimated that a very small percentage
of IID’s budget will be generated from grant sources at any given time.
Power Department Revenue Sources
As a consumer-owned utility, IID works to efficiently, and effectively, meet its customers’
energy demands at the best possible rates, tying the area’s low-cost of living directly with low-
cost utilities. The Power Department utilizes the following sources for revenues:
1. Energy Sales— Energy sales accounted for approximately 76% of the Power Department
Budget in 2023. Retail sales are concentrated in the commercial and residential sector
with less than 3% of the revenue coming from industrial operations.
2. CSP Capital Contributions- Customer Service Proposal (CSP) revenues account for an
estimated 3% to 5% of the Energy Budget. IID has an adopted CSP pricing sheet for
construction, material, inspection, metering and installation services requested. CSP
contributions were an estimated at $26 million or 3.4% of the 2023 budget. Generally,
these contributions are prefunded private developer or customer funded.
3. Energy Cost Adjustment Factor Revenues-The Energy Cost Adjustment (ECA) was
adopted in 2015 and is applicable to all electric customers served by the District and
applied to all kilowatt-hours (kWh) billed under all rate schedules and applicable special
contracts. The ECAF recovers the costs of, fuel, energy, capacity, transmission, purchased
IMPERIAL IRRIGATION DISTRICT
13 4
2025
SERVICE AREA PLAN FINANCING PLAN
power and transmission costs, and revenues from wholesale sales not recovered in the
base energy charge of the District.
4. Dispatching and Wheeling Charges- Fees for the third-party transportation of energy
(wheeling) on the IID transmission system are also collected by the District. IID Power
Department may average up to 4% of its annual revenue in dispatching and wheeling
charges. The 2023 budget accounted for $26.4 in income from these sources (3.4%).
5. Certificates of Participation Proceeds-A Certificate of Participation (COP) is a financial
instrument (a form of financing), used by IID, which allows an individual to buy a share of
the lease revenue (unlike a bond) of an agreement entered by IID. This source includes
capital loans for capital loans for support services. COP Proceeds accounted for an
estimated 2.5% of the Power Department Budget in 2023 ($20 million).
6. Wholesale Power and Gas Sales- Wholesale rates are established for industrial,
commercial and agricultural purpose subject to special conditions such as standby or
breakdown service where the entire electric power requirements are not regularly
supplied by the District. That Power Department received less than 2% from Wholesale
Power and Gas Sales in 2023, an estimated $6.9 million.
7. Capital Loans (Support Services)-Over $9 million was budgeted in 2023 from capital loans
representing an estimated 1.2% of total revenues for the Power Department.
8. Government/Other Reimbursements- Over $48 million was budgeted for special
Government and/or Generator Customer funded projects representing 6.2% of total
revenues and funding for the Power Department. These reimbursements may be
associated with Generator Interconnection Agreements and similar capital projects that
are largely dependent on the market.
9. Public Benefit Charge (PBC) -The PBC (Public Goods Charge AB 1890) is a legal charge
under which each IID Customer pays an adjustment amount (2.85%) applicable to all rate
schedules and special contracts. Proceeds are to be used to fund public benefits programs
as mandated by Assembly Bill 1890. An estimated $16.5 million was collected in 2023 with
a combined total over the last five years of $90.3 million supporting the energy efficiency
programs described under chapter IV. D of this service area plan as well as the following
community assistance programs and grants:
• READY-Residential Energy Assistance Designed for You
• CARE-Customer Assistance for Residential Emergencies
• EASE-Energy Assistance for Special Equipment
• SHIELD-Senior Health & Income Energy Lifeline Discount
• Non-Residential Lighting Grants
• School or Non-Profit HVAC Grants
IMPERIAL IRRIGATION DISTRICT
13 5
2025
SERVICE AREA PLAN FINANCING PLAN
10. Interest Income- IID may earn interest on investments, savings accounts, bonds, etc.
Interest income was less than 1% of the total annual energy revenues in 2023, accounting
for $6 million of total Power Department revenue.
Unlike the Water Department, the Energy Department must respond to volatility in the fuel
and purchased power markets. The District, through its Power Risk Management Policy,
continues to employ structured hedging strategies to minimize exposure to key market and
operational risks. These strategies are designed to mitigate uncertainties related to:
• Load fluctuations
• Generation and production variability
• Fuel price volatility
• Capacity costs
• Wholesale energy market price volatility
By proactively managing these risks, the District enhances rate stability and ensures more
predictable energy procurement costs for its customers.
To maintain rate stability and protect customers from market volatility, the District continues
to maintain a Rate Stabilization Fund. In addition, the Energy Cost Adjustment (ECA) factor
remains available as a flexible tool to address unexpected increases in fuel and purchased
power costs. Together, these mechanisms help the District respond effectively to unforeseen
financial pressures while minimizing impacts on customers.
These financial mechanisms allow IID to respond to market conditions effectively via rate
changes. By updating its rate structures, the District in not only ensuring cost recovery but
also securing funding for capital improvement needs in support of aging infrastructure. This
approach helps maintain system reliability and support long-term improvements while
keeping financial resilience strong.
IMPERIAL IRRIGATION DISTRICT
13 6
2025
SERVICE AREA PLAN FINANCING PLAN
B. CURRENT FACILITY FINANCING AND RECOMMENDATIONS
1. Water Facility Financing
a) Current Water Facilities Funding Mechanisms
The Water Department is anticipated to generate over $347 million in total revenue
during the 2024 calendar year from all revenue sources. The primary funding source
(57%) of revenue for the Water Department are the water transfer sales which are
anticipated to increase in volume and value and peak at year 2026. Although these
funds are predominantly used for conservation projects and programs, the balance
of the funds are reinvested in IID O&M expenses, relieving monies for capital
investments.
Over 47% of the total Water Department revenue budgeted for 2025 was from water
transfer revenue ($97.6 million). By far, the largest water transfer revenue comes
from water transfers to the Sand Diego County Water Authority which is anticipated
to generate over $164 million in 2025 (an average of $662.13 per acre-foot). Water
transfers to the Metropolitan Water District are expected to generate approximately
$18 million in revenue in 2025 and over $18 million in revenue is expected from the
Coachella Valley Water District.
Another temporary revenue source (for years 2024-2026) is expected to be generated
under the Lower Colorado River Basin System Conservation and Efficiency Program,
SCIA which IID entered into with Reclamation for up to 250,000 AFY of conserved
water. The proposed SCIA conservation payments to IID for water conserved are
based on the 2023 SDCWA transfer pricing of $776.97/AF with a 4% annual inflation
adjustment as noted in Table F- 3, resulting in the following annual payment rates for
conserved water to remain in Lake Mead.
Table F- 3 SCIA System Conservation Water Payment Rate
Year System Conservation Water Rate
2024 $808.05/AF
2025 $840.37/AF
2026 $873.99/AF
Direct local water sales to service area customers generate an estimated 14% of the
Water Department revenue. Water sale revenues are collected for the continued
operation and maintenance of the water distribution and drainage system. The last
comprehensive update of fees was in 2009 and a Cost of Service study was underway
IMPERIAL IRRIGATION DISTRICT
13 7
2025
SERVICE AREA PLAN FINANCING PLAN
in 2024 and 2025, consistent with Proposition 218, and any resulting rate increases
would be expected to be implemented before the end of the 5-year planning period
of this SAP. Cost of Service findings are expected to be publicly available in early 2026.
The current water sale costs, as adopted by the IID Board, are shown in Table F- 4.
Please refer to the respective full schedule for detailed conditions under each
respective service.
Table F- 4 Adopted 2024 Water Rate Schedule
Customer Classification Flat Rate Water Tiered Water Rates Applicable
Rates 6 AFY/ 6-8AFY/ >8AFY/
Per AF ACRE ACRE ACRE
General Agricultural¹ $20.00
Mesa Agricultural² $20.00 $40.00 $80.00
Pump Service³ $20.00
Pipe & Small Parcel Tier 1⁴ $250.00/YR
Pipe & Small parcel Tier 2⁴ $100/YR $100/YR $100/YR
Wholesale Service Tier 1 $20.00
Wholesale Service Tier 2⁵ $105/YR $105/YR $105/YR
General Industrial⁶ $85.00
Municipal Service $20.00
Stand-by-Service⁷ $4.00/AC
Penalty for Gate Adjustment⁸ $100.00/EA
Conserved Water⁹ $542.85/AF
NOTE: At the end of 2024, IID was in the process of conducting a Cost of Service Study. It is anticipated
that a rate adjustment will occur within the five-year planning period.
¹ For properties within Imperial Unit. There is a Stock Water Charge of $10/day minimum.
² Mesa lands are all lands located above the 1030 foot contour line with Mean Sea Level being
referenced at the 1,000 foot elevation. There is a Stock Water Charge of $10/day minimum.
³ Up to $120/Year.
⁴ Tier 1 for diameter ≤ 2 inch and Tier 2 is for diameters over 2 inch but < 6 inch (2 acre minimum)
⁵ Annual Rate Based on Gross Acreage: Where customer facilities make it impractical for IID to install
measuring equipment, annual charge per acre shall apply (2 acre minimum)
⁶ Temporary Water Service has a minimum charge of $425/Year and excess discharge into IID will
also have a $258/AF charge.
⁷ Applicable to all lands within Imperial Unit that are entitled to water whether water was used or
not. (After 5% allowance for any right-of-way, net charge is $3.80/AC)
⁸ Applicable to anyone who adjusts a delivery gate which results in a change in the amount of water
delivered, without prior authorization from IID.
⁹ Applicable to water delivered outside of the district boundary but inside the Imperial County. To be
adjusted annually after 1988 in accordance with the Consumer Price Index (CPI)
b) Planned Capital Water Project Costs
IID has several planned water capital projects under the Water Department’s 5-Year
Capital Improvement Plan estimated between $50 to $60 million per year. The 2025-
2029 planning period includes an extraordinary expense associated with a partially
grant funded operational reservoir (EHL Reservoir) which is anticipated to double the
normal range to $103.4 million in year 2026. Table F- 5 has a summary of the
projected capital improvements between 2025 and 2029.
IMPERIAL IRRIGATION DISTRICT
13 8
2025
SERVICE AREA PLAN FINANCING PLAN
Table F- 5 Planned Water Capital Project Costs*
Water Capital Year 2025 Year 2026 Year 2027 Year 2028 Year 2029
$12,905,000 $20,084,000 $16,200,000 $16,300,000 $13,145,000
Imperial Dam
$624,000 $640,000 $655,000 $671,000 $688,000
Automation
$4,865,000 $4,663,000 $5,212,000 $6,771,000 $5,486,000
Lateral Canals
$15,726,000 $18,288,000 $19,506,000 $21,096,000 $21,392,000
Concrete Lining
$6,625,000 $7,000,000 $7,500,000 $7,500,000 $10,000,000
Customer Projects
EHL Reservoir** $11,300,000 $52,700,000 $8,000,000 $0 $0
TOTAL $52,045,000 $103,375,000 $57,073,000 $52,338,000 $50,711,000
*Costs are rounded up to the nearest $1,000
**EHL Reservoir is a special project which will be partially funded with $16.5 million from grant funds and water transfer
revenues, as appropriate.
Source: 2024 Budget Plan & Water Department Five Year Improvement Plan for years 2025-2029. Operational
Reservoirs & Water Transfer Projects are excluded from this table and discussed under Conservation.
Capital projects that generate conserved water, such as Seepage Recovery Projects,
Interties and Operational Reservoirs are paid strictly from water transfer revenues
and presented under the Conservation section of this Finance Chapter.
c) Cost Avoidance Opportunities for Water Facilities
IID requires all developers, private, or public, that require raw water services to new
facilities to cover all costs for the adequate conveyance and metering to their
respective project site(s). The proposed development also incurs costs associated
with any corresponding engineering services and studies. It is noted that Customer
Projects within the District’s service area are paid 100% by private customers or the
requesting public agency. These include projects such as those requested by industrial
operations, geothermal operations, and similar non-agricultural uses.
As previously noted, Imperial Dam facilities are also shared by and provide benefit to
other water agencies. IID avoids incurring costs that correspond to associated capital
improvement costs that are shared by other benefitting water agencies, including
YMIDD, NGVIDD, YID (South Gila), WMID, YA Project, Valley Division, Bard, BIA and
CVWD. IID’s cost share of the common works at Imperial Dam is approximately 77%.
Another major facility under which IID avoids costs beyond its fair share if for the
operation and maintenance of the ACC. The AAC identifies seven distinct channel
sections, four of those sections continue to benefit some of the aforementioned water
agencies which in turn share in the costs associated with the respective sections of the
AAC’s operation and maintenance. Specifically, AAC use and costs are shared with
IMPERIAL IRRIGATION DISTRICT
13 9
2025
SERVICE AREA PLAN FINANCING PLAN
Valley Division, Bard, BIA and CVWD. IID is responsible for approximately 76% to 88%
of the costs within those four respective sections and is responsible for 100% of the
costs under the remaining three sections.
IID was able to secure over $16.5 million in grant funding between 2019 and 2024
through the Water Department. Funds were awarded for water measurement
equipment, design and construction of the EHL operational reservoir and for planning
and design of metered delivery gates. All funding came from grant programs offered
through the U.S. Bureau of Reclamation. This demonstrates that IID is competitive
and able to subsidize local projects, avoiding full project costs to better serve its
customer base.
d) Recommended Funding for Water Facilities
IID will continue to utilize the funding sources currently in place in addition to
searching for other sources to improve the efficiency of the water distribution system
and for planned investment in development of additional operational reservoirs.
Water sales are the primary funding source of revenue used for capital investments
and for operation and maintenance costs. Reduced water sales (attributed to changes
in water transfers) can result in IID’s operation and maintenance costs being spread
over a smaller sales base. Generally, this would result in an increase in water rates.
Consistent with recommendations of the last SAP, IID is reviewing water service fees
under a Cost of Service study that was commissioned in 2024. Findings will be taken
into consideration prior to implementation of any necessary rate adjustments.
Although there are a number of financing mechanisms already applied by the
District in order to assist in the funding for capital facilities, there are, a number of
State and Federal grant and loan programs available for public utility districts
through a number of public and private agencies that the District should pursue.
Further descriptions of these opportunities are provided at the end of this chapter.
2. Irrigation Drainage Facility Financing
a) Current Drainage Facility Funding
The current revenue sources for drainage facilities also come from Water
Department Revenue sources. As previously noted, direct water sales to service
area customers generate an estimated 14 percent of the Water Department revenue
and applied to the continued operation and maintenance of both the water
distribution and drainage collection system. Similarly, to water facilities, drainage
improvements, operation and maintenance is also substantially subsidized by water
transfer revenues. Another major source of revenue for drainage facilities may be
customer driven (and thus customer funded) projects deriving for a need to abandon
IMPERIAL IRRIGATION DISTRICT
14 0
2025
SERVICE AREA PLAN FINANCING PLAN
or underground segments of the drain collection facilities due to urbanization and
development sprawl.
There are no costs for drain collection services within the Imperial Unit, which
generally includes all IID water users, with few exceptions. Under IID’s Water Rules
and Regulations (No. 45), IID may levy assessment against excess surface agricultural
discharge water as a means of control. Irrigation farm land discharge amount equal
or greater than 15% of the water being delivered and measured may be subject to
the levy.
Discharge from industrial uses is generally limited to controlled stormwater discharge
as allowed by the laws of the respective regulating agencies. Consistent with
Regulation No. 46, the limit on drainage is set at 10 percent of the maximum flow rate
for the water received, but shall not exceed 672 gallons per minute (1.5 cfs). Excess
water is charged at the $750 per acre-foot rate. Assessment fees for drain discharge
are negligible, if applicable and noted under Table F- 6. Please refer to the respective
full schedule for detailed conditions.
Table F- 6 Charge for Drainage Service
Facilities Outside the Flat Rate Service Rates
Imperial Unit Per AF of Discharge
Drainage Service NA $250.00
Assessment Charge (excess) NA $750.00
Drain Outlet Construction $30/AC
Note: a minimum drainage charge per month is set at $200 per discharge point.
b) Planned Capital Project Costs for Drainage Facilities
IID has a continuous operation and maintenance budget for the IID drainage system.
The entire drainage is system is gravity flow, substantially earthen drains that flow
into the New River or Alamo River with a handful of drains directly discharging into
the Salton Sea. For these reasons, annual capital drain improvement costs are
nominal in comparison to the overall Water Department budget and range between
$3.3 to $3.8 million. Planned drainage capital projects under the approved 2024
Capital Improvement Plan are identified in Table F- 7 Projected Drainage Facilities
Costs as a summary of the planned costs for control structures, inlets and outlets
proposed to be improved between 2025 through 2029 district-wide. The costs are
separated by Northern and Southern Divisions.
IMPERIAL IRRIGATION DISTRICT
14 1
2025
SERVICE AREA PLAN FINANCING PLAN
Table F- 7 Projected Drainage Facilities Costs
Northend Southend Total Planned
Year
Division Division Drainage Facility
Costs
2025 $1,914,000 $1,853,000 $3,767,000
2026 $1,338,000 $1,913,000 $3,251,000
2027 $1,943,000 $1,942,000 $3,885,000
2028 $1,973,000 $1,973,000 $3,946,000
2029 $2,053,500 $2,053,500 $4,107,000
Source: 2024 Water Department Capital Improvement Five Year Projections.
c) Cost Avoidance Opportunities for Drainage Facilities
IID is able to avoid costs resulting from new development that will necessitate new
drainage facilities by requiring developers to construct adequate facilities and
retention basins for their projects, inclusive of undergrounding open drains when
they may pose a risk to residents from the proposed new land use(s).
Additionally, local cities and the county have been able to access grant funds when
necessary drain improvements are within eligible transportation route extensions
and or shared rights-of-way. Design and construction are often prepared in
collaboration with local municipalities and in response to urban sprawl. This may
include funding for bridges over drains, drain culverts or drain piping and
undergrounding implemented to IID standards while avoiding costs.
d) Recommended Funding for Drainage Facilities
IID will continue to use the existing funding sources for the maintenance and
operation of irrigation drainage facilities. However, the established drain fees have
not been updated since 1987 and are negligible sources of revenue since they don’t
apply to the Imperial Unit, the Districts primary water service area. Considering the
emerging challenges with vegetation control, undergrounding of drains may be more
cost effective in certain areas. Thus, revisiting the drainage rate schedule may be
warranted.
IID has entered into a Master Agreement with the Department of Transportation in
2025 to enable the District access to transportation funds to cover capital costs
associated with drain infrastructure relocation, underground or modification within
planned public streets and roadways, bike routes or pedestrian facilities. Joint
partnerships with local jurisdictions should be pursued.
IMPERIAL IRRIGATION DISTRICT
14 2
2025
SERVICE AREA PLAN FINANCING PLAN
3. Power Facilities & Services Financing
a) Current Energy Facilities Funding
Energy sales accounts for over 75% of the Power Department Budget. IID maintains a
rate schedule that covers over twenty customer classifications from General
Wholesale Power Service to Residential Service and a diverse set of categories in
between. The following provides a limited overview of some of the more common
schedule rates as of 2025:
Table F- 8 Limited Schedule of Energy Rates
2025 Demand Energy Tiered Charge Energy
Customer Classification Customer Charge Charge per kWh Cost
Charge per kW per kWh Adjust-
First 1001- >7,000
ment
1,000 6,000 kWh
kWh kWh
ECA Energy Cost Adjustment Actual*
ECA-R ECA Renewable Actual*
D Residential $10.50 19.76¢ X
MH Master Meter (MH Park) $10.50 18.84¢ X
GS Small General $17.50 19.60¢ 19.19¢ 18.61¢ X
GL Large General $140.00 $11.00 13.95¢ X
AG Agricultural General $140.00 $4.75 15.65¢ X
A-2 General Wholesale $90 $3.20 15.23¢ X
PA Agricultural Pumping $40.00 $3.90 15.33¢ X
PM Municipal Service $17.50 17.23¢ X
*ECA: The Energy Cost Adjustment is the amount computed in accordance with Schedule ECA and ECA-
R. The ECA is added to the base rate calculation for the actual cost of power. The ECA recovers the costs
of fuel, energy, capacity, transmission, purchased power and transmission costs netted against revenues
from wholesale sales not revered in the base energy charge by the District. Similarly the ECA-R is
applicable to all rates associated with renewable portfolio market purchase pursuant to SB X1-2. Please
see full schedule for details and special conditions under IID Energy Rates. For 2025 the ECA is zero.
A Power Factor Adjustment is also Applicable-A charge of $0.26 per kilovar of reactive demand as
measured by the incoming kilovar demand meter for each kilovar in excess of .60 times the kilowatt
demand measured and supplied by the district.
IID also charges energy costs for outdoor lighting and street and highway lighting,
categorized by lamp rating (lumens) and wattage. IID maintains respective fee
schedules for Outdoor Area Lighting, Street and Highway Lighting, State Highway
Lighting and Street and Highway Lighting. Services are furnished from dusk to dawn
where this service can be supplied from existing secondary overhead facilities of the
district of suitable voltage.
It is noted that approximately 6.9% of the total energy accounts receive energy
assistance discounts. The total amount of discounts applied in calendar year 2024 was
$7.9 million to residential customers. These subsidies are entirely funded by the
Public Benefit Charge applicable to all rate schedules. In March of 2025, the IID Board
IMPERIAL IRRIGATION DISTRICT
14 3
2025
SERVICE AREA PLAN FINANCING PLAN
approved the deployment of $10 million in Public Benefits funding to enhance and
expand the current programs.
b) Planned Capital Energy Project Costs
IID has several planned capital projects under the approved 2025-26 Budget Plan for
2025, amounting to $410 million. Table F- 9 Planned Capital Energy Project Costs
(1,000's)has a summary of the approved budget allocation for 2025 and anticipated
budgets for the years that follow. These figures, in total, are comparable to allocation
history and anticipated to remain comparable in 2026 and beyond to support the
planned energy projects.
Table F- 9 Planned Capital Energy Project Costs (1,000's)
Generation Transmission Distribution General Plant Total Budget
2025
$151,872 $192,000 $51,274 $15,326 $410,472
2026
$139,482 $130,379 $47,629 $8,274 $325,764
2027
$104,293 $127,954 $48,974 $6,671 $287,891
2028
$28,575 $151,410 $50, 025 $5,974 $235,984
2029
$24,225 $127,541 $51,752 $6,264 $209,782
Source: Energy Business Internal Controls
An additional amount is budgeted annually for aging infrastructures within Power
Generation, Transmission and Distribution. Over the five-year planning period, it is
anticipated that up to $148 million will be budgeted for Generation, up to $88 million
for Transmission and up to $276 million for Distribution.
c) Cost Avoidance Opportunities for Power Facilities
The district imposes an Energy Cost Adjustment (ECA), applicable to all electric
customers served by the district and applied to all kilowatt-hours (kWh) billed under
all rate schedules and applicable special contracts. The ECA recovers the costs of, fuel,
energy, capacity, transmission, purchased power and transmission costs, and
revenues from wholesale sales not recovered in the base energy charge of the district.
The district targets a minimum level of $100 million in the rate stabilization fund to
be utilized as an emergency fund to mitigate, or partially offset, unexpected fuel and
purchased power costs.
Additionally, the majority of the transmission projects are customer funded projects.
There is over $1 billion dollars projected for strategic energy transmission during the
next five-year planning period to accommodate new development. Routine
distribution lines are also developer funded.
IMPERIAL IRRIGATION DISTRICT
14 4
2025
SERVICE AREA PLAN FINANCING PLAN
d) Recommended Funding for Power Facilities
The Imperial Irrigation District will continue to use the existing funding sources for
energy facilities and services. It should be noted, however, that coordinated
scheduling with a broader region might bring revenue to California by selling more
solar to other states that in turn would save money. To the degree that regionalization
benefits California, IID could also benefit due to efficiencies and increased renewable
energy contributions to serving load. If IID generation is the lowest cost generation to
serve its load, then effectively, IID will continue to serve its load using its existing
generation, and any excess generation beyond IID’s load will be offered into the
market to serve other’s load and IID will be paid the market price for the excess
generation, thereby, providing an additional revenue stream for IID.
The Power Department has also begun to pursue grant funding resources and most
recently secured a $23.8 million grant to improve system resiliency. State and federal
funding are a significant resource to the IID given its operational capacity and
demographics of its customer base.
In late 2024 IID secured an additional $18.3 million award from the U.S. Department
of Energy’s Grid Resilience and Innovation Partnerships (GRIP) Program. This federal
funding, when matched with $18.3 million provided by IID, will enable IID to deploy
$36.7 million for an Advanced Distribution Management System (ADMS) to
modernize its electrical grid and enhance reliability for its 165,000 customers across
both Imperial and Riverside Counties, with special emphasis on the Imperial and
Coachella valleys, as well as parts of San Diego county.
4. Efficiency & Conservation Program Financing
a) Current Efficiency & Conservation Project Funding
Water Efficiency & Conservation Project Funding-With few exceptions, system
efficiency projects and/or programs are paid for with water transfer sales which are
anticipated to increase in volume and value and peak at year 2026. A temporary
increase by up to 50% is anticipated during plan years 2025 and 2026 due to
implementation of the SCIA that was entered into in 2024 between Reclamation and
IID for the conservation water for the benefit of Lake Mead.
Energy Efficiency Project Funding- IID will at times incur debt for large capital
projects. IID is a member of the Southern California Public power Authority (SCPPA).
The SCPPA is a joint action agency comprised of the cities of Los Angeles, Glendale,
Burbank, Cerritos, Vernon, Pasadena, Anaheim, Riverside, Azusa, Banning and Colton
and IID (the only non-municipal member of SCPPA). SCPPA acts as a funding entity for
transmission, generation, fuel and energy efficiency projects. SCPPA will issue debt
IMPERIAL IRRIGATION DISTRICT
14 5
2025
SERVICE AREA PLAN FINANCING PLAN
for the construction of new resources and then secure this debt with take-or-pay
contracts with project participants. Renewable energy costs account for
approximately 23% if the Power Department’s budget.
When IID is a party in a transaction with SCPPA and member utilities, the debt falls
on SCPPA and therefore minimally impacts the IID’s credit ratings. This is an
unequivocal advantage of being a member of SCPPA. Joint action entities like SCPPA
allow small entities the opportunity to participate in larger, cost-effective generation
resources. A publicly-owned utility that is too small to buy an entire project can enter
into a take-or-pay contract with SCPPA that will aggregate the needs of all its
members. SCPPA will then issue debt to construct, or purchase, the generation
resource and recover its debt service costs through take-or-pay contracts with the
project participants. This means that the participants pay the cost even if no energy
is produced, or they choose not to dispatch the generation project.
Energy Efficiency Program Funding- The Public Benefit Charge collected covers all
costs related to the energy efficiency and renewable programs as well as customer
assistance programs and non-residential grants. Generally, the funding is allocated
evenly between Imperial and Riverside County regardless of customer class, while
prescriptive rebate programs vary in geographic region as they are distributed on a
first-come, first-serve basis. The refrigerator exchange program is based on customer
class, as it is tailored exclusively to income-qualified customers.
b) Planned Capital Efficiency & Conservation Project Costs
Water Conservation Projects-IID has several planned projects to help meet the target
water conservation goal of 487,200 AFY. The projects are programmed over a five-
year plan period and include the projects noted in Table F- 10.
Table F- 10 Planned Water Transfer Capital Project Costs (1,000's)
Year 2025 Year 2026 Year 2027 Year 2028 Year 2029
Discharge Monitoring $725 $255 $125 125 125
Lateral Headings $4,800 $1,200 $0 $0 $0
Interties $2,995 $5,900 $12,400 $17,200 $5,200
SCADA Upgrades¹ $0 $0 $0
Operational Reservoirs² $13,500 $65,900 $28,900 $16,700 $28,200
Seepage Recovery $1,600 $0 $0 $0 $0
TOTAL $23,620.00 $73,255.00 $41,425.00 $16,700.00 $28,200.00
Source: Adopted 2024 Budget Plan & Water Department Five Year Improvement Plan for years 2025 through 2027.
¹ SCADA upgrades have been an ongoing system conservation project that came into completion in 2024.
² IID initiated in 2024 the design and construction of a 2,100 AF capacity operational reservoir.
IMPERIAL IRRIGATION DISTRICT
14 6
2025
SERVICE AREA PLAN FINANCING PLAN
Energy Efficiency Projects- Renewable energy and energy efficiency are integrated
into the overall budget for the Power Department as previously identified in Table F-
9. For example, included within the five-year planning period are some of the
following capital investments: Yucca Steam Plan Generation Repower ($260 million);
Hydro Plant Refurbishment and Upgrades ($50 million).
Energy Efficiency Programs-All of the existing energy efficiency programs, customer
service programs and non-residential grants supported by the Public Benefit Charge
are anticipated to continue through the planning period. Additional programs under
development that may be launched during the planning period include an Online
Marketplace and a Virtual Power Plant demand response program. The Online
Marketplace would be an IID branded eCommerce website to provide energy savings
products with customer validation and instant rebate processing. VPP would launch
as a program to allow the positioning of new and existing customer resources as load
flexibility tools for IID. The VPP has the potential for EE Savings, Peak Demand
Reduction, Reduced Fuel Purchase and Decarbonization.
c) Cost Avoidance Opportunities for Efficiency & Conservation Projects
Water Conservation Cost Avoidance- The Imperial Irrigation District has water
transfer agreements in place that ensure all capital projects that will result in water
conservation for the purpose of water transfer benefits are paid by the benefitting
partners. IID has also adopted an Interim Water Supply Policy for Non-Agricultural
Projects. The District’s IWSP for new Non-Agricultural Projects provides a mechanism
and process to develop a water supply agreement for any appropriately permitted
project in the IID water service area. The policy establishes the framework and set of
fees necessary to ensure that the water supplies used to meet any new water
demands do not adversely affect existing users by funding water conservation or
augmentation projects in support of that new demand.
Under the IWSP, up to 25,000 acre-feet of IID’s annual Colorado River water supply
may be conserved and made available for these new non-agricultural projects. All
new industrial-use projects are subject to a development fee, while new municipal
and mixed-use projects may be subject to the fee if the projects’ water demands
exceed certain district-wide average-per-capita use standards. The applicable
reservation fee and development fee are discussed under Water Fees No. 9 and No.
10 of this Finance chapter and a nominal revenue is collected as of 2024. New users
would continue to be subject to the established service charges on the fee schedule.
Energy Efficiency Cost Avoidance- Within IID’s region, there is an ample supply of
local renewable resource generation that can be developed, and under development,
at a reasonable cost and, in turn, sold at a reasonable price to IID customers. Further,
IMPERIAL IRRIGATION DISTRICT
14 7
2025
SERVICE AREA PLAN FINANCING PLAN
if IID chooses, there is an ample supply of renewable resources that qualify as
Category 1 renewable resources in and surrounding the state of California. IID is
currently going a step further by placing a priority on locally generated resources,
since they can directly connect to the IID system and, theoretically, generate a cost
savings for both the developer and IID.
Costs associated with new strategic capital transmission projects to address power
generation from solar and/or geothermal are also borne to the customer/developer
of the generation facilities. Some of the transmission costs from these planned
developments may be shared from facilities in the Imperial Valley region and into the
facilities in the Coachella Valley region.
d) Recommended Funding for Efficiency & Conservation Efforts
Recommended Funding for Water Conservation-IID will continue to use the same
resources for Water Conservation and Efficiency Projects and is accessing new
resources, including federal grant funding. IID received a grant award of over $16.5
million that will be expended 2024-2027 for an operational reservoir that will
conserve up to 15,000 AFY. However, IID has not had the need to bond or borrow for
capital costs and loans should be explored as a potential opportunity. A number of
potential agencies and funding programs are identified at the end of this chapter.
Recommended Funding for Energy Conservation-Given current funding levels of the
energy efficiency portfolio, and absent additional funding, the Power Department
should consider reallocation of a larger portion of the overall energy efficiency public
program budget toward the Customs Energy Solutions program to capture savings
from a customer segment with the largest potential. The District should also continue
to pursue state and federal grant resources for energy efficiency and renewable
energy projects as opportunities arise.
5. Administrative Service and Facilities Financing
a) Current Administrative Facilities Funding
Administrative Facilities and Services are funded by both the Water Department and
Power Department revenues. Approximately $100 million is budgeted for all
administrative support service costs. Support Service costs are shared between the
Energy and Water Departments. Factors considered for level of contribution include:
1) the level of service demanded by the respective department in the preceding year,
and 2) projected service demand as anticipated by management. All of the District’s
support services are initially accounted and budgeted for in their own departments
and then linked to functions of either the Water or Energy (or both) Departments.
The percentage share by the two respective departments may vary from year to year.
IMPERIAL IRRIGATION DISTRICT
14 8
2025
SERVICE AREA PLAN FINANCING PLAN
See Appendix B – 2024 Budget Plan, Amended April 1, 2025 (Summary of Support
Services Expenditures Allocation Assumptions on pages H-9 to H-10). Cost allocation
from Power Department and water department for support services is based on
criteria established by policy. Please see Appendix C-Policy and Procedures 2450 for
a detailed description.
b) Planned Administrative Capital Project Costs
There are a number of Capital Improvement Projects budgeted for
administrative/support facilities as noted in Table F- 11. However, it should be noted
that none of the capital projects are for expansion of facilities with the exception of
new construction associated with a System Operations Control building for the Power
Department and a new Southend Consolidation project for the Water Department.
Over $1 million is budgeted annually in support of zero emission vehicle transition.
Table F- 11 Planned Administrative Facilities Capital project Costs (1,000's)
2025 2026 2027 2028 2029
Department/Unit
New Facilities $0 $0 $6,000 $25,582 $37,417
Facility Upgrades $2,597 $1,259 $1,840 $656 $674
EV Infrastructure $1,000 $1,100 $1,265 $1,518 $1,898
Parking Lots/Fencing $0 $3,998 $11,379 $7,023 $12,116
Source: 2025 Draft Capital Budget General Services
c) Cost Avoidance Opportunities for Administrative Facilities
Administrative service costs may be further reduced by outsourcing some
administrative services including planning, legal, engineering, and special project
managers. Another successful practice is cross administration between departments.
d) Recommended Funding for Administrative Facilities
Existing funding sources from the Water Department and the Power Department will
continue to be used to support administrative services and facilities. Support staff will
continue to share facilities with these two departments as appropriate.
IMPERIAL IRRIGATION DISTRICT
14 9
2025
SERVICE AREA PLAN FINANCING PLAN
C. POTENTIAL ADDITIONAL REVENUE SOURCES FOR CAPITAL NEEDS
IID is eligible to apply for numerous funding sources as a public utility district and also as a
conservation district, when necessary. Not only is the District able to apply for numerous
funding sources, IID is also within a highly competitive position given its performance capacity
as the sixth largest utility district in the nation and as an essential service provider to an area
which is predominantly composed of economically distressed and disadvantaged
communities most of which hold some of the highest pollution burdens and vulnerabilities in
the State of California26. This section of the SAP identifies a small sampling of potential
resources.
1. Private Financial Institutions Under CRA Objectives
A financing opportunity for IID may be via competitive revenue bonds through private
financial institutions as part of a banks Community Reinvestment Act (CRA) obligations.
The Community Reinvestment Act was enacted by the U.S. Congress in 1977 to encourage
depository institutions to help meet the credit needs of the communities in which they
operate, with special emphasis on low- and moderate-income neighborhoods, consistent
with safe and sound banking operations. The Community Reinvestment Act requires
federal financial supervisory agencies to use their authority when examining financial
institutions subject to supervision, to assess the institution's record of meeting the credit
needs of its entire community, including low- and moderate-income neighborhoods.
Financial institutions must keep a good standing in order to continue to merge, acquire
or grow, thus investment opportunities into small community capital improvements or
community financing are actively sought by responsible financial institutions. Ratings can
range from Outstanding, High Satisfactory, Satisfactory and Needs to Improve. The
District has opportunities to work with local community banks to set up low interest loan
programs for its customers wishing to invest in residential solar, agricultural customers
wishing to invest in irrigation efficiency equipment, and other similar investments. The
following local lending institutions have CRA obligations, noting a potential opportunity
for local investment:
• Bank of America
• Community Valley Bank
• Mechanics Bank
• Union Bank of California
• Wells Fargo Bank
26 CalEnviroScreen 4.0 from Office of Environmental Health Hazard Assessment.
IMPERIAL IRRIGATION DISTRICT
15 0
2025
SERVICE AREA PLAN FINANCING PLAN
2. Public Financial Institutions
California Infrastructure and Economic Development Bank (IBank)-The California
Infrastructure and Economic Development Bank (IBank) is the State of California’s only
general-purpose financing authority. The Legislature created IBank in 1994 to finance
public infrastructure and private development that promote a healthy climate for jobs,
contribute to a strong economy, and improve the quality of life in California communities.
IBank offers a Bond Financing Program and an Infrastructure Loan Program.
• Infrastructure State Revolving Fund (ISRF) Program provides low-cost financing
to public agencies for a wide variety of infrastructure projects. ISRF Program
funding is available in amounts ranging from $1 million to $65 million, with loan
terms of up to 30 years (or useful life of the project, whichever is less). Interest
rates are set on a monthly basis.
• Climate Catalyst Revolving Loan Fund (CCRLF) was created by IBank with
guidance from the California Lending for Energy and Environmental Needs Center
– CLEEN Center – to help meet the State’s Greenhouse Gas Reduction Goals. The
loan program provides flexible low-cost credit and credit support. The program
can fund:
o Clean Energy Transmission project infrastructure and other necessary
elements such as environmental planning, permitting and
prec9onstruction costs for projects are eligible.
o Climate Smart Agriculture supports projects that promote climate-smart
technologies, including but not limited to on-farm renewable energy,
including electricity and fuels; energy, water and materials efficiency,
energy storage and equipment replacements.
North American Development Bank (NADBank)-NADBank is a binational financial
institution capitalized and governed equally by the United States and Mexico for the
purpose of financing environmental projects and has now merged with the Border
Environment Cooperation Commission (BECC). The two institutions work together with
communities and project sponsors in both countries to develop and finance infrastructure
necessary for a clean and healthy environment for border residents. The team can make
grants and loans to public and private borrowers for the implementation of
environmental infrastructure projects located in the U.S.-Mexico border region. Funding
is available for the implementation of projects in all environmental sectors in which the
NADBank operates. See BECC grant program details under Federal Grant Agencies.
IMPERIAL IRRIGATION DISTRICT
15 1
2025
SERVICE AREA PLAN FINANCING PLAN
3. Federal Funding Agencies
U.S. Bureau of Reclamation-The Bureau of Reclamation was established in 1902 and has
grown to become a contemporary water management agency with a strategic plan and
numerous programs and initiatives that will help the Western States, Native American
Tribes and others meet new water needs and balance the multitude of competing uses of
water in the West. The Bureau of Reclamation has a number of grant programs in place
and has awarded numerous water and energy efficiency grants.
• WaterSMART -Through the Water SMART programs, states, tribes, and local
entities can plan for and implement actions to increase water supply through
investments to modernize existing infrastructure and attention to local water
conflicts. The projects funded with these grants may include installation of flow
measurement devices and automation technology, canal lining, or piping to
address seepage, municipal meter upgrades, and other capital projects to
conserve water or improve resiliency to drought conditions. There are a number
of funding programs offered through WaterSMART with varying objectives and
funding limits. Below is a sampling of grant programs that may benefit IID:
o Water and Energy Efficiency Grants -This funding is for projects that
conserve and use water more efficiently; increase the production of
hydropower; mitigate conflict risk in areas at a high risk of future water
conflict; and accomplish other benefits that contribute to water supply
reliability in the western United States. As much as $5 million may be
applied for and Reclamation may fund between 50% to 75%, depending
on the type of project.
o Environmental Water Resource Program- Provides funding for projects
that focus on environmental benefits and that have been developed as
part of a collaborative process to help carry out strategies that increase
reliability of water resources. Up to $3 million in funding may be applied
for with a cost share minimum of 25% required.
o Small Program Storage– Provides funding for water storage capacity that
increases surface water or groundwater storage. Up to $30 million may
be available per project up to 25% of total project costs.
o Planning Project Design Grants - Up to $100,000 is available per project
and funding to conduct project-specific planning and design for projects
to improve water management. A 50% local cost share is required for
participation.
o Small-Scale Water Efficiency Program- Funding is provided under this
program in a 50/50 cost share for small water efficiency improvements
IMPERIAL IRRIGATION DISTRICT
15 2
2025
SERVICE AREA PLAN FINANCING PLAN
that have been identified through previous planning efforts. Projects
eligible for funding include installation of flow measurement or
automation in a specific part of a water delivery system, lining of a section
of a canal to address seepage, in amounts up to $75,000.
o Water Strategy Grants- Up to $400,000 is available per project and
funding to conduct planning to support water supply and management
solutions (e.g., domestic water supply projects for disadvantaged
communities, water marketing, water conservation, drought resilience,
and ecological resilience). Funding can be up to 100% under the Inflation
Reduction Act.
U.S. Department of Agriculture-The USDA has a number of funding resources to facilitate
economic growth for all rural Americans under its Rural Development offices. Some of the
funding opportunities that may be in line with IID’s mission are listed below:
• Community Facilities Direct Loan & Grant Program- This program provides
affordable funding to develop essential community facilities in rural areas. An
essential community facility is defined as a facility that provides an essential
service to the local community for the orderly development of the community in
a primarily rural area, and does not include private, commercial or business
undertakings. Project that benefit a population of 5,000 or fewer have a grant
limit of up to 75% of project costs when the median household income of the
service area is below 60% of the state’s median income.
• Distributed Generation Energy Project Financing can work in partnership with
energy producers in the area. The program can provide loans and loan guarantees
to energy project developers for distributed energy projects including renewables
that provide wholesale or retail electricity to existing Electric Program borrowers
or to rural communities served by other utilities. The program requires a
minimum 25% cash equity. The typical loan term is 20 years (for solar) and
interest rates are typically Treasury + 1/8.
• Electric Infrastructure Loan & Loan Guarantee Program makes insured loans and
loan guarantees to non-profits, including utilities to finance the construction of
electric distribution facilities in rural areas. The guaranteed loan program has
been expanded and is now available to finance generation, transmission, and
distribution facilities including system improvements and replacement required
to furnish and improve electric service in rural areas, as well as demand side
management, energy conservation programs, and on-grid and off-grid renewable
energy systems. The maximum repayment schedule is 35 years and also tied to
Treasury + 1/8. Hardship Loans may be used (fixed at 5%), at the sole discretion
IMPERIAL IRRIGATION DISTRICT
15 3
2025
SERVICE AREA PLAN FINANCING PLAN
of the Rural Utilities Service, to assist applicants in rural areas that are either
economically distressed.
U.S. Environmental Protection Agency (EPA) - USEPA’s mission is to protect human
health and the environment. Nearly half of their budget goes towards grants to state
environmental programs, non-profits, educational institutions, and others. The funds are
used for a wide variety of projects, from scientific studies that assist in EPA making
decisions to community cleanups. Overall, grants assist EPA in achieving their overall
mission: protect human health and the environment. EPA’s Border Water Infrastructure
Program provides grant assistance to communities along the U.S./Mexico border to
develop and construct infrastructure to provide safe drinking water and adequate
sanitation, and to improve water quality in shared and trans-boundary waters. EPA funds
grant programs through the Border Environmental Cooperation Commission created in
1993 under a side agreement to the North American Free Trade Agreement (NAFTA) for
the purpose of enhancing the environmental conditions of the US-Mexico border region.
BECC and NADBank work closely with other border stakeholders including federal, state,
and local agencies, the private-sector and civil society to identify, develop, finance and
implement environmental infrastructure projects on both sides of the US-Mexico border.
Three Grant Programs available through BECC are the Community Assistance Program
(CAP), the Project Development Assistance Program (PDAP) and Border Environmental
Infrastructure Fund (BEIF) as follows:
• BECC Community Assistance Program (CAP): The Community Assistance
Program is administered through BECC and funds smaller shovel-ready projects
up to $500,000. Funded with NADB’s retained earnings, this program offers grant
financing to support the implementation of projects sponsored by public entities
in all environmental sectors. The objective of this program is to support the
implementation of critical environmental infrastructure projects for sponsors
with limited capacity to incur debt. Projects must be located within 100
kilometers (62 miles) of the international border. Eligible projects, include, but
are not limited to:
1) Potable water supply, wastewater treatment/reuse, water conservation,
storm drainage & flood control
2) Clean/renewable energy-Solar, wind biogas, biofuels, hydroelectric,
geothermal
• BECC Project Development Assistance Program (PDAP): Funding is available for
project development activities necessary for certification of potential NADBank
funded projects including, but not limited to, planning studies, environmental
assessment, final design, financial feasibility, community participation, and
IMPERIAL IRRIGATION DISTRICT
15 4
2025
SERVICE AREA PLAN FINANCING PLAN
development of sustainability elements. Funding is available for project
benefitting areas within 100 kilometers of the U.S./Mexico border.
• BECC/NADBank Border Environmental Infrastructure Fund (BEIF): Grants are
intended to supplement funding from other sources in order to complete a
project’s financial package. The objective of the program is to make water
infrastructure project affordable where utility customers would face undue
financial hardship and/or otherwise projects would not otherwise be
implemented. Applicants must seek other sources of funding since BEIF is
considered to be the funding of last resort. Actual BEIF participation is considered
on a project-by-project basis and determined according to funding availability
and based on an affordability analysis to be conducted by BECC/NADBank during
project development.
4. State Agencies
State Water Resources Control Board- The mission of the State Water Resources Control
Board is to preserve, enhance, and restore the quality of California’s water resources. The
Division of Financial Assistance (DFA) administers the implementation of the State Water
Resources Control Board’s (State Water Board) financial assistance programs that include
loan and grant funding for construction of public sewage and water recycling facilities,
remediation for underground storage tank releases, watershed protection projects,
nonpoint source pollution control projects, and other similar projects. An overview of
Program information is noted below.
• Nonpoint Source Pollution (NPS) Grant Funding- This Program administers grant
money it receives from United States Environmental Protection Agency through
Section 319 of the Federal Clean Water Act. These grant funds can be used to
implement projects, or programs, that will help to reduce NPS pollution. Projects
that qualify for funding must be conducted within the state's NPS priority
watersheds. Project proposals that address TMDL implementation and those that
address problems in impaired waters are favored in the selection process. The
maximum grant amount is $1,000,000 for implementation projects. Planning
projects can apply for up to $250,000. All funding requires a minimum 25 percent
match.
• Clean Water State Revolving Fund Program (CWSRF) - The Clean Water State
Revolving Fund Program accepts applications on a continuous basis. The Federal
Water Pollution Control Act (Clean Water Act or CWA), as amended in 1987,
established the Clean Water State Revolving Fund (CWSRF) program. The CWSRF
program offers low interest financing agreements with some interest free
options. They offer loan forgiveness for disadvantaged communities and
IMPERIAL IRRIGATION DISTRICT
15 5
2025
SERVICE AREA PLAN FINANCING PLAN
stormwater, sustainability or conservation projects. There is no minimum or
maximum project size and typical funding range is $50,000 to $25 million. Using
a combination of State and EPA funding, the CWSRF funds projects that may be
beneficial to IID as follows:
1) Stormwater management
2) Water conservation, efficiency, and reuse
3) Agricultural/silvicultural best management practices
4) Habitat protection and restoration
5) Surface water protection, and
6) Publicly owned treatment works projects.
Department of Water Resources provides funding under its Integrated Regional Water
Management (IRWM) Grant Program. The program encourages a collaborative effort to
manage all aspects of water resources in a region. IRWM crosses jurisdictional,
watershed, and political boundaries; involves multiple agencies, stakeholders, individuals,
and groups; and attempts to address the issues and differing perspectives of all the
entities involved through mutually beneficial solutions. To access the program and
applicant must work through the IRWM that covers IID’s water service area which is the
Imperial IRWM. There are a number of funding opportunities, including but not limited
the following:
• Proposition 1 IRWM Implementation – A total of $222 million was made available
under the last round. Projects require a 50% cost share.
• Sustainable Groundwater Management Proposition 68 – Between $2 and $5
million in grant funding requiring a 25% cost share.
• CalConserve Water Use Efficiency Loan Program – Up to $7 million in loan funding
available requiring a 50% cost share.
IMPERIAL IRRIGATION DISTRICT
15 6
2025
SERVICE AREA PLAN FINANCING PLAN
Resources and References
Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000, Government Code §§
56000 et seq. (2000).
Governor's Office of Planning and Research. (2003). Local Agency Formation Commission Municipal
Service Review Guideline.
Governor's Office of Planning and Research. (2013). Technical Advisory. SENATE BILL 244: Land Use,
General Plans, and Disadvantaged Communities (ca.gov)
Imperial County Planning and Development Services. (2015). Imperial County Renewable Energy
and Transmission Element. El Centro, CA.
Imperial Irrigation District. 2024. IID: Website. https://www.iid.com.
Imperial Irrigation District 2021 Water Conservation Plan. Imperial Irrigation District Website:
Water Conservation Plan.
Imperial Irrigation District. (2023). QSA Annual Reports | Imperial Irrigation District (iid.com),
Imperial, CA.
Imperial Irrigation District 2018 and 2024 Integrated Resource Plans. Power Department, Imperial
Irrigation District Website: Integrated Resource Plan | Imperial Irrigation District (iid.com)
Imperial Irrigation District 2025-2026 Budget Plan (Amended April 2025)
Imperial Water Forum and GEI Consultants, Inc. 2012. Imperial Integrated Regional Water
Management Plan. October 2012. Final Imperial IRWMP: Vol. 1 & 2 – Imperial IRWMP.
North American Development Bank, Infrastructure Financing. 2024 Website: Infrastructure
Financing | NADB: North American Development Bank
State of California, Department of Finance (2024). E-1 Population Estimates of Cities, Counties and
the State-January 1, 2023 and 2024 Sacramento, CA.
State of California, Department of Water Resources. Grants and Loans. 2024 DWR Website: Grants
and Loans (ca.gov)
United States Bureau of Reclamation. WaterSMART. 2024 USBR Website: WaterSMART | Bureau of
Reclamation (usbr.gov)
United States Census Bureau.“Summary File.” July 2023 American Community Survey. U.S. Census
Bureau’s American Community Survey Office. (n.d.).
United States Department of Agriculture. Rural Development, Federal Funding Opportunities. 2024
USDA Website: Federal Funding Opportunities | Rural Development (usda.gov)
IMPERIAL IRRIGATION DISTRICT
15 7
2025
SERVICE AREA PLAN FINANCING PLAN
IMPERIAL IRRIGATION DISTRICT
15 8
2025