CHAPTER 3 – CUTLER PUD MUNICIPAL SERVICE REVIEW
EXECUTIVE SUMMARY
This section provides an overview of the written determinations of the Cutler Public Utility District
(PUD) Municipal Service Review (MSR). As part of its review of municipal services, the Tulare County
Local Agency Formation Commission (LAFCO) is required to prepare a written statement of its
determination with respect to each of the following: 1) Growth and population projections for the affected
area; 2) Infrastructure needs and deficiencies; 3) Financing constraints and opportunities; 4) Cost
avoidance opportunities; 5) Opportunities for rate restructuring; 6) Opportunities for shared facilities; 7)
Government structure options; 8) Evaluation of management efficiencies; and 9) Local accountability and
governance. These requirements are established by AB 2838, the Cortese-Knox-Hertzberg Local
Government Reorganization Act of 2000. The Cutler PUD MSR identifies the following written
determinations:
Written Determinations
1) Growth and Population
1. Between 1990 and 2000, Cutler experienced an average annual population growth rate of
approximately 0.1%, compared to 0.6% for the unincorporated areas of Tulare County, and
2.9% for the adjacent unincorporated community of Orosi.
2. Assuming no development constraints, it can be expected that Cutler will experience growth
at an average annual rate between 2% and 3%, indicating the community would reach a year
2025 population between 7,400 and 9,400 residents.
3. Consistent with the Urban Boundaries element of the Tulare County General Plan, the Cutler-
Orosi UDB is, with minor exceptions, consistent with the external SOI for Cutler and Orosi.
2) Infrastructure Needs and Deficiencies
Domestic Water
1. The Cutler PUD’s water supply is derived from two existing deep underground wells that
have a total maximum production efficiency of approximately 2,100 GPM, or 3.024 MGD.
The District also has an elevated water storage tank with a capacity of approximately 50,000
gallons.
2. Two test wells have been drilled, have proven successful, and the District has awarded a
contract for drilling of the first (well #8) of two new wells. The District is also securing
funding for a water system rehabilitation project, and a blending tank project.
3. Water supplied from one of the new wells (well #9) would be mixed with water derived from
two existing wells (wells #3 and #4) which are currently inactive to high nitrate levels as a
part of the blending tank project. By mixing the water supply from wells that produce
acceptable water quality with those which have contaminant levels which exceed maximum
levels, the District’s water supply capabilities will be increased, while bringing the water
quality to within acceptable standards before entering the distribution system.
Cutler Public Utility District MSR Page 3-1
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
4. Lovell High School, which is operated by the Cutler-Orosi Joint Unified School District, has
requested water capacity from the Cutler PUD. The District plans to provide the school with
water service pending the approval and implementation of the blending tank project. The
school is located at the northwest quadrant of Avenue 392 and State Route 63, which is
currently outside of the Cutler PUD boundary and SOI. It is anticipated that the District
would provide water service to the school on a contractual basis.
5. The Cutler PUD water system supports 1,032 total connections including three industry
packing houses, and one box plant.
6. Currently, the District charges a flat rate for water service in the community. The District
should consider installing water meters on all connections to their water system. A
cost/benefit analysis resulting form the installation of water meters should be performed. A
fully metered water system will help with water conservation, and minimize over usage
and/or wasting of water.
7. District staff has indicated that they are working with Alta Irrigation District officials to study
the feasibility of constructing a regional water treatment facility that would use water from
the Kings River by exchange out of the Friant-Kern Canal. The regional facility would
potentially provide domestic water to the City of Dinuba, Cutler, Orosi, and other
unincorporated communities in the region. A feasibility study would be a three to five year
process, and project implementation could be ten to fifteen years out.
8. Assuming 1,100 equivalent dwelling units (EDUs), in order to meet Tulare County
Improvement Standards the Cutler PUD water system would need to be capable of delivering
a combined flow rate (from all source and storage facilities) of 2,700 GPM (1,500 GPM fire
flow, and 1,200 GPM domestic demand) for a period of two hours while maintaining a
minimum pressure of 25 PSI to each lot served; The District’s water system is capable of
delivering a combined source flow of 2,515 GPM indicating that the system falls short of
meeting the Tulare County Improvement Standards. After accounting for the required
domestic demand, the District’s water system would be capable of supplying a fire flow of
approximately 1,315 GPM, which meets the residential fire flow requirement. The water
system would need to be tested at actual system pressure to determine the actual amount of
available capacity for domestic and fire flow. The District could increase its fire flow
capacity by adding wells, or adding storage capacity to the system.
9. Based upon a calculation performed in accordance with General Order 103, published by the
California Public Utilities Commission, it is concluded that the District’s water system is
currently operating at or near its capacity, and cannot support additional connections at this
time.
10. The amount of developable land available, including the availability of infrastructure, are two
factors that have limited community growth from occurring, including affordable housing
objectives, and commercial enterprise. The District’s plans to construct several upcoming
water system improvement projects will significantly increase its ability to provide service to
proposed development projects.
Sanitary Sewer
1. According to District staff, the District’s sanitary sewer collection system is very old and pipe
leaks and breaks cause significant problems including groundwater inflow/infiltration and
Cutler Public Utility District MSR Page 3-2
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
cross contamination with groundwater. The District should consider the preparation and
implementation of a pipeline replacement program, perhaps as a part of a sanitary sewer
master plan.
2. Treatment and disposal of the collected effluent is provided at the Cutler-Orosi WWTF,
jointly owned and operated by the Cutler PUD and Orosi PUD. The Cutler-Orosi WWTF
serves the communities of Cutler, Orosi, East Orosi, Yettem, Seville, and Sultana.
3. The Cutler-Orosi WWTF operates under the provisions of Waste Discharge Requirements
(WDR) Order No. 97-106, issued by the California RWQCB. According to JPWA staff, the
WWTF has been certified by a registered civil engineer, and has a permitted capacity of 2.0
MGD.
4. As of March 2006, the Cutler-Orosi WWTF is operating under a Cease and Desist Order
according to the RWQCB file. The RWQCB indicated that the Cutler-Orosi JPWA has
complied with the requirements of the Cease and Desist Order, and an order to rescind the
Cease and Desist Order is expected to be completed in April 2006.
5. The average dry weather flow at the WWTF is approximately 1.40 MGD, with a historical
high flow of 1.89 MGD. Flow at the WWTF is greater during winter months than in summer
months due to inflow/infiltration of storm water into the collection system during winter
months, and ex-filtration during dry summer months. The District will be able to more
accurately predict the remaining capacity at the WWTF once repairs are made to leaking
pipes throughout the collection system.
6. The Cutler PUD is currently allocated 1,255 equivalent dwelling units of capacity at the
WWTF. The Cutler PUD is currently under a building moratorium, and has a waiting list for
additional sewer connections.
7. The Cutler PUD and Orosi PUD are working with the Tulare County Redevelopment Agency
to secure funding that will be used to correct deficiencies that would increase the capacity of
the WWTF. Proposed improvements will modernize the facility and add capacity to bring the
serviceable operational limits to 2.4 MGD.
3) Financing Constraints and Opportunities
1. The District prepares a comprehensive and thorough annual budget that clearly describes the
services provided to residents and the funds expended for those services.
2. The District’s operating budgets (excluding reserve funds) for fiscal year 2004-05 totaled
$448,300 for sanitary sewer and $1,176,629 for water service. The District’s budget included
contingency funds of $15,000 and $10,000 for sanitary sewer and domestic water service,
respectively.
3. A review of the District’s budget indicates that the District is in stable financial condition.
The District’s annual revenues cover the annual operating expenses of the District including
reserve allocations and contingency appropriations. Currently, the District does not have any
long term debt obligations.
Cutler Public Utility District MSR Page 3-3
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
4. It is likely that development within the District’s SOI will rely on infrastructure available
form the District. To increase its preparedness when such development is proposed, it is
recommended that the District prepare and implement water and sewer system master plans.
4) Cost Avoidance Opportunities
1. The District avoids excessive overhead costs by operating with part-time and full-time staff,
which provides adequate levels of service to the community. The District also avoids
unnecessary costs by contracting out professional services including engineering, legal
services, and other consulting services, and using these services on an as needed basis.
2. The District should continue to work with the development community to fund the
construction of water and sewer infrastructure improvements that would serve new
development sites as a way of avoiding unnecessary costs.
3. Master planning could help the District avoid unnecessary costs by allowing the District
sufficient time to set aside funding needed for future capacity improvements that would allow
for development within the community.
4. The District could also avoid unnecessary costs associated with the maintenance of capital
infrastructure by promoting development in infill areas, and areas where infrastructure is
already in place.
5) Opportunities for Rate Restructuring
1. The Cutler PUD charges monthly user fees and capacity rights fees for water and sewer. The
District’s fiscal year 2004-05 budget estimates revenues of $309,000 and $262,000 to be
generated from water and sewer customer sales, respectively.
2. The monthly user fees and capacity rights fees charged by the Cutler PUD for domestic water
service are below average compared to other domestic water service providers in Tulare
County. The District has opportunities to install water meters, and begin billing under a
metered rate structure for water service, which would promote water conservation in the
community.
3. The District Engineer for the Cutler PUD indicated that water rates will be increased by $7.00
per month in the near future as a result of Proposition 218 requirements. A $7.00 rate
increase would result in a flat water rate of $25.00 per month, which is slightly above average
compared to other domestic water service providers in Tulare County. This would result in a
rate to income ratio of approximately 1.23%, which is slightly above the average of 1.11%.
4. The monthly sewer rates charged by the Cutler PUD are above average compared to
surrounding sewer service providers. The capacity rights fee charged by the Cutler PUD for
connections to its sewer system is more than twice the average of other sanitary sewer service
providers throughout the County. The high sanitary sewer fees are likely attributable to the
cost of improving the Cutler-Orosi WWTF, and repairing the collection system.
5. The District Engineer for the Cutler PUD indicated that sewer rates will be increased by
$9.00 per month in the near future as a result of Proposition 218 requirements. A $9.00 rate
increase would result in a flat sewer rate of $31.00 per month, and a rate to income ratio of
Cutler Public Utility District MSR Page 3-4
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
1.53%, both significantly above average, compared to other sewer service providers in Tulare
County.
6. The District should periodically review its monthly user fees and capacity rights fees to
ensure that quality service will continually be provided to existing and future residents. Any
rate increases should be substantiated and adopted through a public hearing process.
7. Fees paid by developers are placed into a restricted reserve account, funds which are
ultimately used by the District to construct capital capacity improvements to the District’s
water and sewer systems. User fees are used for the operations of the District and the
operation and maintenance of the District’s infrastructure, including capital replacement
costs.
6) Opportunities for Shared Facilities
1. The Cutler PUD and Orosi PUD take advantage of shared infrastructure by operating a single
WWTF through a JPWA comprised of three Board members from each District.
2. If the communities of Cutler and Orosi eventually become an incorporated City, the Districts
will need to consider combining the existing infrastructure for domestic water and sanitary
sewer service. The District’s will also need to consider adopting a uniform rate structure for
all services of the City, should the District’s ultimately incorporate as a single City entity.
7) Government Structure Options
1. If the communities of Cutler and Orosi become an incorporated City, it is likely that a single
SOI which incorporates the areas within each District’s current SOI would be established as a
starting point. Incorporation would ultimately result in the dissolution of the Cutler PUD, as
well as the Orosi PUD. Any changes in organization should be completed in accordance with
LAFCO policies and procedures.
2. Prior to development within its SOI area the District should complete master planning to
address the infrastructure needs of affected areas and funding mechanisms to meet those
needs.
3. The District should continually expand and improve its domestic water and sanitary sewer
infrastructure to accommodate development within its current District Boundary and SOI
areas zoned for development with developer assistance.
8) Evaluation of Management Efficiencies
1. Based upon information made available, it appears that the provision of domestic water
service and sanitary sewer collection is managed in an efficient manner and meets the needs
of the community and ratepayers.
2. The age of the District’s sewer infrastructure is becoming an issue that the District needs to
address in the short-term. The District has plans to implement a phased collection system
improvement project, based upon the availability and timing of funding anticipated through
various grant/loan programs, and the availability of local revenue.
Cutler Public Utility District MSR Page 3-5
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3. The Cutler PUD is governed by a five member Board of Directors elected at large from
within its boundaries and is responsible for setting policy and general administrative
procedures.
4. The District currently operates with a part-time and full-time staff and contracts out for other
services, including engineering, legal counsel, accounting, and other consulting services.
5. The District’s answering message provides contact information in case of emergencies, as
well as the District’s hours of operation.
9) Local Accountability and Governance
1. The District complies with the Brown Act open meeting law by holding regularly scheduled
meetings in which the public is invited. Regularly scheduled meetings are held on the third
Tuesday of each month. at the District office. Agendas for Board meetings are posted on-site
at the District office.
2. The District adopts budgets and rate changes at hearings where the public is notified and
invited.
3. The District should work with the Tulare County Resource Management Agency (RMA)
and/or Tulare County LAFCO to have information regarding District affairs posted on the
Tulare County RMA and/or LAFCO website. The District could provide information such as
meeting times and locations, budgets, rates, ordinances, agendas, completed/upcoming
projects, and other District affairs to Tulare County for posting on the County’s (RMA and/or
LAFCO) website.
Cutler Public Utility District MSR Page 3-6
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.0 CUTLER PUBLIC UTILITY DISTRICT
3.0.1 Background
The requirement for LAFCO to conduct reviews of local municipal services was established with the
passage of AB 2838 known as the Cortese-Knox-Hertzberg Local Government Reorganization Act of
2000. The bill passed the legislature, and was signed into law by Governor Davis on September 26, 2000.
MSRs provide LAFCO with an additional tool to fulfill their statutory responsibilities of promoting
orderly growth and development, preserving the States finite open space and agricultural land resources,
and working to ensure that high quality public services are provided to all Californians in the most
efficient and effective manner. MSRs are a requirement of State annexation law and are required to be
completed before the consideration of a Sphere of Influence (SOI) amendment or once every five years
when a SOI amendment is not being considered.
In July 2003 Tulare County LAFCO adopted an MSR exemption policy that identifies the agencies that
would be subject to a review and the extent of that review. The agencies in Tulare County were divided
into three (3) categories: agencies subject to a full comprehensive study; agencies subject to a
questionnaire study; and agencies exempt from an MSR study. The Cutler PUD is subject to a full
comprehensive study. The policy further identifies that the services subject to review shall be:
• Police protection
• Fire protection
• Water and wastewater
• Solid waste collection and disposal
• Streets and traffic circulation
• Power generation and distribution
• Health Care
Cutler, an unincorporated community in Tulare County, is located in the northern portion of the County,
approximately five miles east of Dinuba and nine miles north of Visalia. The Cutler PUD, which was
formed in June 1922, has a primary function of providing sanitary sewer and domestic water service for
the community. Sanitary sewer and domestic water service are the primary services provided by the
Cutler PUD that are subject to an MSR. The Cutler PUD also provides street lighting service, which is
not subject to the MSR requirement.
Cutler is located south of and adjacent to the community of Orosi. Cutler is an agriculturally oriented
service community surrounded on the south, west and east by lands in agricultural production, vacant
lands, and scattered residential homes. Cities and communities surrounding Cutler include Visalia to the
south; Dinuba to the west; the community of Orosi to the north; and the community of East Orosi to the
northeast. The Tulare County/Fresno County Line is located approximately 3.3 miles northwest of
Cutler. The current District Boundary and the currently adopted SOI for Cutler are illustrated on Figure
3-1. Figure 3-1 also shows the Cutler-Orosi Urban Development Boundary and the Boundary of the
Cutler-Orosi Joint Powers Authority wastewater treatment facility. These boundaries are further
explained in subsequent sections of this report.
Cutler Public Utility District MSR Page 3-7
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
FIGURE 3-1 – CUTLER PUD BOUNDARY, SOI, AND URBAN DEVELOPMENT BOUNDARY (UDB)
Source: Tulare County GIS Database
Cutler Public Utility District MSR Page 3-8
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
The following excerpt from the Tulare County LAFCO website (www.co.tulare.ca.us/lafco/info.asp)
defines a SOI and the purpose it serves.
A “Sphere of Influence” is the physical boundary and service area that a local
governmental agency is expected to serve. Establishment of this boundary is necessary to
determine which governmental agencies can provide services in the most efficient way to
the people and property in any given area. The Sphere of Influence requirement also
works to discourage urban sprawl by preventing overlapping of jurisdictions and
duplication of services.
The following discussions address the nine legislative factors required by the Cortese-Knox-Hertzberg
Act; 1) Growth and population; 2) Infrastructure needs and deficiencies; 3) Financial constraints and
opportunities; 4) Cost avoidance opportunities; 5) Opportunities for rate restructuring; 6) Opportunities
for shared facilities; 7) Government structure options; 8) Evaluation of management efficiencies; and 9)
Local accountability and governance.
Cutler Public Utility District MSR Page 3-9
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.1 GROWTH AND POPULATION
The purpose of this section is to present historical and projected growth patterns and population
projections to establish a baseline for the evaluation of the service needs of Cutler.
3.1.1 Historical Data
The Census Bureau, on a decennial basis, identifies and provides detailed information on all incorporated
Cities along with several smaller unincorporated communities (termed Census Designated Places –
CDPs). In each Census, community profiles are developed and provide a wide range of information
pertaining to population, demographics, housing information, household data, education and employment,
income and poverty, and historical trends.
Census 2000 data indicates that Cutler had a population of 4,491 as of January 2000. Census 1990 data
indicates that Cutler had a population of 4,450 corresponding to an average annual growth rate between
1990 and 2000 of approximately 0.1%. The unincorporated areas of Tulare County grew from a
population of 133,222 in 1990 to a population of 141,150 in 2000, corresponding to an average annual
growth rate of approximately 0.6%. The adjacent community of Orosi experienced an average annual
growth rate of approximately 2.9% between 1990 and 2000. Assuming no development constraints, it
can be expected that Cutler will experience growth at a similar rate as the nearby Orosi community over
the next 20 years. Using an average annual growth rate between 2% and 3%, the Cutler community
would reach a year 2025 population between 7,400 and 9,400 residents.
3.1.2 Planning Boundaries
In addition to a SOI, which is defined by LAFCO as the “…physical boundary and service area that a
local government agency is expected to serve…” an urban development boundary (UDB) has been
established and designates the Cutler-Orosi urban area. Figure 3-1 shows the District Boundary and SOI
in comparison to the District’s UDB. The UDB is, for the most part, coterminous with the external SOI
boundary of each District.
The Tulare County General Plan contains an Urban Boundaries Element which establishes goals for
designating realistic planning areas around cities and unincorporated communities which could be used to
help determine boundaries for community service districts and County service areas, in areas where
differing levels of service are required, and within which corporate annexations may take place. The
following are excerpts from the County of Tulare General Plan Policy Summary Section 1UB.C.1 –
Unincorporated Communities Policies.
“Urban Development Boundaries are established around the following unincorporated
communities in the County to serve as official urban planning areas for these
communities: Cutler-Orosi, Ducor, Earlimart, East Orosi, Goshen, Ivanhoe, Lemon
Cove, London, Pixley, Plainview, Poplar-Cotton Center, Richgrove, Strathmore, Terra
Bella, Tipton, Traver, Woodville, Alpaugh, and Springville.”
“A land use plan is to be developed for each community with an Urban Development
Boundary, specifying desired densities and land use categories, with particular attention
to defining suitable areas for the full range of urban development and rural residential
development. Such plans shall include the entire area within the Boundary and shall
recognize the short and long term ability of each community to provide necessary urban
services within its Urban Development Boundary.”
Cutler Public Utility District MSR Page 3-10
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
Furthermore, the County of Tulare General Plan Policy Summary Sections 1UB.F.1. and 1UB.F.2. set
forth policies with regard to “Boundary Consistency”, and “Review and Revision of Boundaries.”
Excerpts from these sections of the County General Plan Policy Summary relating to special districts are
reiterated below.
“In areas where special districts provide rural as well as urban services, LAFCo should
distinguish between “urban” and “rural” service areas for the purpose of establishing
Spheres of Influence for such districts. If an unincorporated community is served by a
special district, the Urban Development Boundary should be consistent with the district’s
“urban” Sphere of Influence.”
“County census boundaries should be as consistent as possible with Urban Development
Boundaries.”
“Urban Area Boundaries and Urban Development Boundaries shall be reviewed at least
once every five years to determine if boundary changes are justified, or if additional
boundaries are needed for communities not included herein. However, a review may be
conducted at any time on request of the affected city or agency.”
As indicated on Figure 3-1, the Cutler-Orosi UDB is, with minor exceptions, consistent with the external
SOI for Cutler and Orosi. The County census boundary does not cover the entire area incorporated within
the Cutler UDB area. Generally, the census boundary does not cover areas south of the railroad tracks, or
areas north of Avenue 408, which are within the Cutler UDB area.
3.1.3 Written Determinations
1. Between 1990 and 2000, Cutler experienced an average annual population growth rate of
approximately 0.1%, compared to 0.6% for the unincorporated areas of Tulare County, and
2.9% for the adjacent unincorporated community of Orosi.
2. Assuming no development constraints, it can be expected that Cutler will experience growth
at an average annual rate between 2% and 3%, indicating the community would reach a year
2025 population between 7,400 and 9,400 residents.
3. Consistent with the Urban Boundaries element of the Tulare County General Plan, the Cutler-
Orosi UDB is, with minor exceptions, consistent with the external SOI for Cutler and Orosi.
Cutler Public Utility District MSR Page 3-11
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.2 INFRASTRUCTURE NEEDS AND DEFICIENCIES
The purpose of this section is to evaluate the infrastructure needs and deficiencies of the Cutler PUD in
terms of availability of resources, capacity to deliver services, condition of facilities, service quality, and
levels of service.
3.2.1 Domestic Water
The Cutler PUD is responsible for providing domestic water service within the District’s Boundary.
Cutler’s water supply, which is chlorinated but not treated, is derived from two deep underground wells,
referred to as well #5 and well #6. District staff indicated the total production efficiency for well #5 is
1,100 GPM and 1,000 GPM for well #6, for a total production capability of 2,100 GPM, or 3.024 MGD.
The District also has an elevated water storage tank with a capacity of approximately 50,000 gallons.
Currently, two wells (wells #3 and #4) are not in service due to high nitrate levels.
Two test wells have been drilled, have proven successful, and the District has awarded a contract for
drilling of the first (well #8) of two new wells. The District has three active grant/loan funding
applications being processed, including an SRF Loan for which an NOAA has been issued. The District
is securing funding for a water system rehabilitation project, a blending tank project, and to bring
additional wells on-line. The blending tank project would mix water from one of the new wells (well #9)
with wells #3 and #4 (which are currently not in service due to high nitrate levels). By mixing the water
supply from wells that produce acceptable water quality with those which have contaminant levels which
exceed maximum levels, the District’s water supply capabilities will be increased, while bringing the
water quality to within acceptable standards before entering the distribution system.
Lovell High School, which is operated by the Cutler-Orosi Joint Unified School District, has requested
water capacity from the Cutler PUD. The District plans to provide the school with water service pending
the approval and implementation of the blending tank project. The school is located at the northwest
quadrant of Avenue 392 and State Route 63, which is currently outside of the Cutler PUD boundary and
SOI. It is anticipated that the District would provide water service to the school on a contractual basis.
The District indicated the community water system (as of September 2004) supports 1,032 total
connections to their system, including three industry packing houses and one box plant. District staff has
indicated there are only thirteen connections that have a water meter; the District currently charges a flat
rate for residential water service connections. While Census data indicates that there are approximately
4.9 people per dwelling unit, Cutler PUD staff believes it could be much greater. Since the District does
not bill on a metered basis, the demand on the water system can be much greater than the system can
support. Table 3-1 contains the well productions for 2003, provided in millions of gallons per month.
Cutler Public Utility District MSR Page 3-12
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
TABLE 3-1
CUTLER PUD GROUNDWATER WELL PRODUCTIONS (YEAR 2003)
Month Well #5 Well #6
January 16.729 mg 0.448 mg
February 15.220 mg 1.337 mg
March 20.062 mg 0.933 mg
April 19.050 mg 1.330 mg
May 28.800 mg 3.410 mg
June 34.179 mg 10.567 mg
July 36.838 mg 11.252 mg
August 35.046 mg 8.453 mg
September 32.158 mg 4.497 mg
October 28.355 mg 1.133 mg
November 18.480 mg 0.001 mg
December 16.507 mg 0.000 mg
Total Annual Production 301.424 mg 43.361 mg
Notes: 1) mg = million gallons
2) Source: Cutler PUD
As shown in Table 3-1, July had the highest water production at 48.090 MG for the entire month or an
average peak day flow of 1.55 MGD. The District currently has a water conservation plan that limits
when residents can water lawns and wash vehicles. Residents who violate the water conservation rules
are warned on the first offense and fined for any additional offenses. The District should consider
installing meters on all connections to their water system. It is recommended that the District pursue
funding for the installation of water meters, including state federal grant/loan programs. A cost/benefit
analysis resulting from the installation of water meters should be performed. A fully metered water
system will help with water conservation, and minimize over usage and/or wasting of water.
District staff has indicated that they are working with Alta Irrigation District officials to study the
feasibility of constructing a regional water treatment facility that would use water from the Kings River
by exchange out of the Friant-Kern Canal. The regional facility would provide domestic water to the
communities of Cutler and Orosi, and potentially the City of Dinuba and other unincorporated
communities in the region. District staff indicated that a feasibility study would be a three to five year
process, and that implementation of the project could be ten to fifteen years out.
Tulare County Improvement Standards require that the construction of water source facilities shall
comply with the requirements of Bulletin No. 74, “Water Well Standards” prepared by the State of
California Department of Water Resources. The Tulare County Improvement Standards also establish
specific requirements for quantity and quality of water to be delivered to a system. Some of these
requirements are summarized below.
• The quantity of water delivered to the distribution system within a subdivision from all
source and storage facilities for a period of two hours shall be the maximum domestic
demand plus a fire flow quantity of not less than 500 GPM for single family residential, 1,500
GPM for multi-family residential, commercial, and light manufacturing, and 2,500 GPM for
heavy manufacturing.
Cutler Public Utility District MSR Page 3-13
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
• For systems up to 625 customer units (equivalent dwelling units) the domestic quantity shall
not be less than Q = 100 + 25 * √N, and Q = 100 + N for more than 625 customer units at
sufficient pressure to provide a minimum pressure of 25 PSI to each lot served; where Q
equals the rate of flow in GPM delivered from the combined source facilities to the
distribution system, and N equals the total number of customer units where each customer
unit is equivalent to one for a single family dwelling on a normal subdivision lot. Other types
of development shall be assigned appropriate customer unit values by the Engineer as
experience with the distribution system or locality indicates.
• The minimum source and domestic demand storage design requirements shall be in
accordance with Plate No. WS-11 of Section IV of the Tulare County Improvement
Standards.
• The quality of water supplied for human consumption shall conform to Sections 3, 4 and 5 of
the latest United States Public Health Service Drinking Water Standards. Samples will be
taken and tests made by the County Department of Health Services for bacteriological
determination of potability.
• Chemical and physical tests for potability shall be performed by a commercial laboratory
certified by the State Department of Health Services for performance of chemical and
physical analysis and the costs thereof shall be borne by the sub-divider.
Assuming 1,100 equivalent dwelling units (EDUs), in order to meet Tulare County Improvement
Standards the Cutler PUD water system would need to be capable of delivering a combined flow rate
(from all source and storage facilities) of 2,700 GPM (1,500 GPM fire flow, and 1,200 GPM domestic
demand) for a period of two hours while maintaining a minimum pressure of 25 PSI to each lot served;
The District’s water system is capable of delivering a combined source flow of 2,515 GPM
(approximately 415 GPM could be delivered for two hours from a 50,000 gallon elevated storage tank,
assuming the tank is full), indicating that the may fall short of meeting the Tulare County Improvement
Standards. After accounting for the required domestic demand, the District’s water system would be
capable of supplying a fire flow of approximately 1,315 GPM, which meets the residential fire flow
requirement. The water system would need to be tested at actual system pressure to determine the actual
amount of available capacity for domestic and fire flow. The District could increase its fire flow capacity
by adding wells, or adding storage capacity to the system.
An estimate of water system capacity can be calculated by using General Order 103, published by the
California Public Utilities Commission. For the estimated water system capacity, the total supply source
available is compared to a calculated total supply source required. Other factors that may affect the
capacity of water systems, including but not limited to, water quality, low pressures, required storage, age
of system, and pipeline restrictions, are not considered. The estimated supply source required is
calculated using the following equation,
Q = (N)*(C)*(F) where,
Required
N = Number of customers served
C = Gallon per minute constant: 5 to 9 for flat rate systems, 2 to 5 for metered systems
F = Factor to reflect diversity (inversely proportional to the number of customers)
Using an N value of 1,032, a C factor of 8.0, and an F factor of 0.30, the estimated total supply source
required is calculated to be 2,477 GPM. With a total supply source available of 2,515 GPM, it is
concluded that the District’s water system is currently operating at or near its capacity, and cannot support
Cutler Public Utility District MSR Page 3-14
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
additional connections at this time. The capacity of the water system could be increased by adding wells,
or adding storage capacity to the system.
The amount of developable land available, including the availability of infrastructure, are two factors that
have limited community growth from occurring, including affordable housing objectives, and commercial
enterprise. The District’s plans to construct several upcoming water system improvement projects will
significantly increase its ability to provide service to proposed development projects.
3.2.2 Sanitary Sewer
The Cutler PUD is also responsible for providing sanitary sewer collection to residents within its
Boundary. According to District staff, the sewer collection system is very old and pipe leaks and breaks
cause significant problems including groundwater inflow/infiltration and cross contamination with
groundwater. The District should consider the preparation and implementation of a pipeline replacement
program, perhaps as a part of a sanitary sewer master plan.
Treatment and disposal of the collected effluent is provided by the Cutler-Orosi Joint Powers Wastewater
Authority (JPWA). In March 1980, the Cutler PUD entered into the Joint Wastewater Treatment and
Disposal Facilities Agreement with the Orosi PUD, forming the Cutler-Orosi JPWA for the purpose of
operating a wastewater treatment and disposal facility. Under the terms of the agreement, the Cutler PUD
owns 50% of the property and 40% of the plant and equipment used by the Authority. Each District is
charged for its share of the costs to the Authority based upon its pro-rata share of gallonage flows into the
facility. The governing board of the JPWA is made of three appointed members from the Orosi PUD
Board of Directors and three appointed members from the Cutler PUD Board of Directors. The JPWA
Board of Directors controls its own operations, including selection of management and approval of
operating budgets. The separate boards of the Orosi PUD and Cutler PUD must approve capital
expenditures.
The construction of the WWTF, completed in 1983, was funded 75% from a cost grant from the
Environmental Protection Agency, 12.5% from a cost grant from the State Water Resources Control
Board, and 12.5% from proceeds of revenue bonds sales. The Joint Wastewater Treatment and Disposal
Facility Amended Agreement between the two Districts states that all assets accumulated by the JPWA
(other than cash, accounts receivable, prepaid expenses, and motor vehicles) shall be treated as owned by
the Districts and in accordance with their participation in the JPWA. In addition, each District’s allocated
share of JPWA fixed assets is recorded and depreciated as part of property, plant and equipment, and its
share of cash and all other assets are recorded as investment in the Cutler-Orosi JPWA.
The Cutler-Orosi WWTF serves the communities of Cutler, Orosi, East Orosi, Yettem, Seville, and
Sultana. The WWTF operates under the provisions of Waste Discharge Requirements (WDR) Order No.
97-106 issued by the California Regional Water Quality Control Board (RWQCB), Central Valley
Region. Based upon discussions with the RWQCB, the Cutler-Orosi WWTF is also operating under a
Cease and Desist (C&D) Order (No. 97-107), which is still in effect as of March 2006 according to the
RWQCB file. According to the RWQCB, the Cutler-Orosi JPWA has complied with the requirements of
the Cease and Desist Order, and the Board is in the process of preparing an order to rescind the Cease and
Desist Order, which is expected to be completed in April 2006.
According to JPWA staff, the plant has been certified by a registered civil engineer, and has a permitted
capacity of 2.0 MGD. According to the District Engineer, the historical high flow recorded at the WWTF
was 1.89 MGD, and the average dry weather flow is approximately 1.40 MGD. The District Engineer
also noted that during dry months, the sewer collection system experiences ex-filtration and during winter
months, the collection system experiences inflow/infiltration of storm water. The District will be able to
Cutler Public Utility District MSR Page 3-15
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
more accurately predict the remaining capacity at the WWTF once repairs are made to leaking pipes
throughout the collection system. The Cutler PUD entered into an agreement with the WWTF and is
allowed to transport effluent to the treatment facility not to exceed 1,255 equivalent dwelling units. The
Cutler PUD is currently under a building moratorium, and has a waiting list for additional sewer
connections.
According to District staff, Tulare County Redevelopment Agency (TCRA) is working with the Cutler
PUD and Orosi PUD to correct deficiencies that would increase the capacity of the treatment facility. The
TCRA, on behalf of the Cutler-Orosi JPWA has submitted an application for Federal Assistance to
construct improvements and additions at the Cutler-Orosi WWTF. The proposed project funding
amounts to $4,657,900, with a start date of February 2006, and an ending date of October 2009. The
project represents the combined efforts by the Cutler PUD and the Orosi PUD to improve and upgrade the
jointly operated WWTF, which involves:
• Improvements and additions to the plant headworks
• Improvements to the existing secondary clarifier
• Construction of a new secondary clarifier
• Construction of sludge drying beds
• Electrical improvements and installation of UV disinfection
• Effluent pump station capacity increase
• Land preparation and irrigation system
• Construction safety, mobilization and miscellaneous work
Several issues have caused the WWTF to reach its serviceable limits including age of system components,
leaks in the collection system, and community growth. Until improvements at the WWTF are completed,
both the Cutler PUD and Orosi PUD have restricted development within each community. The
improvements will modernize the facility and add capacity to bring the serviceable operational limits to
2.4 MGD. Improving the wastewater treatment capabilities of the District will allow the community to
expand its affordable housing stock and promote economic development opportunities.
3.2.3 Written Determinations
Domestic Water
1. The Cutler PUD’s water supply is derived from two existing deep underground wells that
have a total maximum production efficiency of approximately 2,100 GPM, or 3.024 MGD.
The District also has an elevated water storage tank with a capacity of approximately 50,000
gallons.
2. Two test wells have been drilled, have proven successful, and the District has awarded a
contract for drilling of the first (well #8) of two new wells. The District is also securing
funding for a water system rehabilitation project, and a blending tank project.
3. Water supplied from one of the new wells (well #9) would be mixed with water derived from
two existing wells (wells #3 and #4) which are currently inactive to high nitrate levels as a
part of the blending tank project. By mixing the water supply from wells that produce
acceptable water quality with those which have contaminant levels which exceed maximum
levels, the District’s water supply capabilities will be increased, while bringing the water
quality to within acceptable standards before entering the distribution system.
Cutler Public Utility District MSR Page 3-16
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
4. Lovell High School, which is operated by the Cutler-Orosi Joint Unified School District, has
requested water capacity from the Cutler PUD. The District plans to provide the school with
water service pending the approval and implementation of the blending tank project. The
school is located at the northwest quadrant of Avenue 392 and State Route 63, which is
currently outside of the Cutler PUD boundary and SOI. It is anticipated that the District
would provide water service to the school on a contractual basis.
5. The Cutler PUD water system supports 1,032 total connections including three industry
packing houses, and one box plant.
6. Currently, the District charges a flat rate for water service in the community. The District
should consider installing water meters on all connections to their water system. A
cost/benefit analysis resulting form the installation of water meters should be performed. A
fully metered water system will help with water conservation, and minimize over usage
and/or wasting of water.
7. District staff has indicated that they are working with Alta Irrigation District officials to study
the feasibility of constructing a regional water treatment facility that would use water from
the Kings River by exchange out of the Friant-Kern Canal. The regional facility would
potentially provide domestic water to the City of Dinuba, Cutler, Orosi, and other
unincorporated communities in the region. A feasibility study would be a three to five year
process, and project implementation could be ten to fifteen years out.
8. Assuming 1,100 equivalent dwelling units (EDUs), in order to meet Tulare County
Improvement Standards the Cutler PUD water system would need to be capable of delivering
a combined flow rate (from all source and storage facilities) of 2,700 GPM (1,500 GPM fire
flow, and 1,200 GPM domestic demand) for a period of two hours while maintaining a
minimum pressure of 25 PSI to each lot served; The District’s water system is capable of
delivering a combined source flow of 2,515 GPM indicating that the system falls short of
meeting the Tulare County Improvement Standards. After accounting for the required
domestic demand, the District’s water system would be capable of supplying a fire flow of
approximately 1,315 GPM, which meets the residential fire flow requirement. The water
system would need to be tested at actual system pressure to determine the actual amount of
available capacity for domestic and fire flow. The District could increase its fire flow
capacity by adding wells, or adding storage capacity to the system.
9. Based upon a calculation performed in accordance with General Order 103, published by the
California Public Utilities Commission, it is concluded that the District’s water system is
currently operating at or near its capacity, and cannot support additional connections at this
time.
10. The amount of developable land available, including the availability of infrastructure, are two
factors that have limited community growth from occurring, including affordable housing
objectives, and commercial enterprise. The District’s plans to construct several upcoming
water system improvement projects will significantly increase its ability to provide service to
proposed development projects.
Sanitary Sewer
1. According to District staff, the District’s sanitary sewer collection system is very old and pipe
leaks and breaks cause significant problems including groundwater inflow/infiltration and
Cutler Public Utility District MSR Page 3-17
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
cross contamination with groundwater. The District should consider the preparation and
implementation of a pipeline replacement program, perhaps as a part of a sanitary sewer
master plan.
2. Treatment and disposal of the collected effluent is provided at the Cutler-Orosi WWTF,
jointly owned and operated by the Cutler PUD and Orosi PUD. The Cutler-Orosi WWTF
serves the communities of Cutler, Orosi, East Orosi, Yettem, Seville, and Sultana.
3. The Cutler-Orosi WWTF operates under the provisions of Waste Discharge Requirements
(WDR) Order No. 97-106, issued by the California RWQCB. According to JPWA staff, the
WWTF has been certified by a registered civil engineer, and has a permitted capacity of 2.0
MGD.
4. As of March 2006, the Cutler-Orosi WWTF is operating under a Cease and Desist Order
according to the RWQCB file. The RWQCB indicated that the Cutler-Orosi JPWA has
complied with the requirements of the Cease and Desist Order, and an order to rescind the
Cease and Desist Order is expected to be completed in April 2006.
5. The average dry weather flow at the WWTF is approximately 1.40 MGD, with a historical
high flow of 1.89 MGD. Flow at the WWTF is greater during winter months than in summer
months due to inflow/infiltration of storm water into the collection system during winter
months, and ex-filtration during dry summer months. The District will be able to more
accurately predict the remaining capacity at the WWTF once repairs are made to leaking
pipes throughout the collection system.
6. The Cutler PUD is currently allocated 1,255 equivalent dwelling units of capacity at the
WWTF. The Cutler PUD is currently under a building moratorium, and has a waiting list for
additional sewer connections.
7. The Cutler PUD and Orosi PUD are working with the Tulare County Redevelopment Agency
to secure funding that will be used to correct deficiencies that would increase the capacity of
the WWTF. Proposed improvements will modernize the facility and add capacity to bring the
serviceable operational limits to 2.4 MGD.
Cutler Public Utility District MSR Page 3-18
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.3 FINANCING OPPORTUNITIES AND CONSTRAINTS
The purpose of this section is to evaluate the jurisdictions capability to finance needed improvements and
services.
3.3.1 Annual Budget
LAFCO should consider the ability of the District to pay for improvements or services associated with
annexed sites. This planning can begin at the SOI stage by identifying what opportunities there are to
identify infrastructure and maintenance needs associated with future annexation and development, and
identifying limitations on financing such improvements, as well as the opportunities that exist to construct
and maintain those improvements.
The fiscal year 2004-05 budget for the Cutler PUD is organized into two separate funds: one for sanitary
sewer and the other for domestic water. Based upon a review of the District’s fiscal year 2004-05 budget,
the District is in sound financial condition. The District’s budget is well organized, thorough, and clearly
articulates the District’s future financial performance plans. The District prepares a traditional line item
budget for each fund (sewer and water) that is divided into the following categories.
• Fund Balances
• Revenues
• Reserve Funds
• Expenses
o Salaries and Employee Benefits
o Services and Supplies
o Other
o Fixed Assets
o Contingencies
The District adopts the budget each year and it is used as the spending plan for the District. The budget
provides a framework for the District to address the following issues: reserves, revenues, expenditures,
investments, and rates and fees.
The District’s sanitary sewer budget for fiscal year 2004-05 identifies a beginning cash balance of
$778,886 and anticipated revenues of $309,000 to be generated primarily from customer sales. Of the
total resources available, $639,586 is in restricted reserves leaving $448,300 in total available funds.
Restricted reserves are established by depreciation of equipment and facilities owned and operated by the
District. Restricted reserves are not necessarily used annually, but instead they are used when specific
equipment has depreciated to the point of needing replacement. The specific items for which restricted
reserves are allocated are identified below.
• Wastewater Capital Reserve Fund
• Pickup & Service Truck Replacement
• Line Cleaning Machine Depreciation
• Deductible Reserves
After accounting for restricted reserves from the District’s budget, the remaining resources of $448,300
covers salaries and employee benefits totaling $77,000; services and supplies totaling $203,700; fixed
assets totaling $131,500; other charges totaling $21,100; and a contingency appropriation of $15,000.
Cutler Public Utility District MSR Page 3-19
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
The District typically requires developers to pay the cost of installing the local piping infrastructure to
serve proposed developments.
Reviewing the District’s budget for the current and previous fiscal years indicates that the District is
financially stable with regard to its sewer fund. The District’s annual revenues cover the annual operating
expenses of the District including reserve allocations and contingency appropriations. It should also be
noted the District currently does not have any long term debt obligations. The District currently has three
grant/loan applications pending that could result in long term debt obligations.
It is likely that development within the SOI will rely on infrastructure available from the District. For this
reason the District should be prepared to accommodate such growth. The Cutler PUD should continue to
work closely with the Orosi PUD to implement improvements that would increase the capacity of the
WWTF, which would increase the District’s ability to serve development within its SOI. The preparation
and implementation of a sewer system master plan would also increase the District’s preparedness when
development within its SOI is proposed. A master plan would also identify existing deficiencies and
make recommendations to correct such deficiencies. The District could potentially obtain funding
assistance to prepare a master plan by applying for available State and/or Federal grants.
The District’s water budget for fiscal year 2004-05 identifies a beginning cash balance of $938,386 and
anticipated revenues of $262,000. Of the total resources available $23,739 is in restricted reserves
leaving $1,176,629 in total available funds. Restricted reserves are established by depreciation of
equipment and facilities owned and operated by the District. Restricted reserves are not necessarily used
annually, but instead they are used when specific equipment has depreciated to the point of needing
replacement. The specific items for which restricted reserves are allocated are identified below.
• Pickup and Service Truck Replacement
• Service Deposits
• Tank Repair
• Deductible Reserve
• Well Construction
• Pipeline Replacement
• Connection Fee Reserve
After accounting for restricted reserves from the District’s budget, the remaining resources of $1,176,629
covers salaries and employee benefits totaling $137,700; services and supplies totaling $173,000; fixed
assets totaling $855,929; and a contingency appropriation of $10,000.
Reviewing the District’s budget for the current and previous fiscal years indicates that the District is
financially stable with regard to its water fund. It is likely that development within the SOI will rely on
infrastructure available from the District. For this reason the District should be prepared to accommodate
such growth. It is recommended that the District prepare and implement a water system master plan,
which would increase its preparedness when development within its SOI is proposed.
The District’s financial constraints involve the governmental structure and the desires of the people in the
community to fund certain activities by establishing assessment districts or fees. The laws under which a
Public Utility District is governed provide the structure for funding activities. Key revenue sources for
the Cutler PUD include monthly sewer and water fees, connection fees, interest on reserves, and pass
through monies. One-time revenues, that are pass-through funds, account for the increases and decreases
in revenue from year to year. On the expenditures side, the District budgets for the services paid for by
residents and provides for capital expenses using restricted reserve accounts.
Cutler Public Utility District MSR Page 3-20
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.3.2 Written Determinations
1. The District prepares a comprehensive and thorough annual budget that clearly describes the
services provided to residents and the funds expended for those services.
2. The District’s operating budgets (excluding reserve funds) for fiscal year 2004-05 totaled
$448,300 for sanitary sewer and $1,176,629 for water service. The District’s budget included
contingency funds of $15,000 and $10,000 for sanitary sewer and domestic water service,
respectively.
3. A review of the District’s budget indicates that the District is in stable financial condition.
The District’s annual revenues cover the annual operating expenses of the District including
reserve allocations and contingency appropriations. Currently, the District does not have any
long term debt obligations. The District currently has three grant/loan applications pending
that could result in long term debt obligations.
4. It is likely that development within the District’s SOI will rely on infrastructure available
form the District. To increase its preparedness when such development is proposed, it is
recommended that the District prepare and implement water and sewer system master plans.
Cutler Public Utility District MSR Page 3-21
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.4 COST AVOIDANCE OPPORTUNITIES
The purpose of this section is to identify practices or opportunities that may help to eliminate unnecessary
costs.
3.4.1 Fiscal Structure
The Districts budget process is designed to screen out unnecessary costs. A base budget is completed by
the District Engineer for review and discussion by the Board of Directors. Each year, the District
Engineer ensures that the District continues to operate within the limits of its financial resources.
The District has adequate staff resources and administrative capabilities to provide the needed level of
services to the residents within its boundaries. The District avoids excessive overhead costs by operating
with a part-time and full-time administration, which provides adequate levels of service to the
community. The District also avoids unnecessary costs by contracting out professional services including
engineering, legal services, and other consulting services.
Generally, the District requires development projects to pay for their own infrastructure (water lines,
sewer lines, fire protection, and lighting) to serve their projects. The District requires development
projects to pay capacity rights fees currently set at $1,500 and $3,520 per equivalent dwelling unit (EDU)
for water and sewer service connections, respectively. Capacity rights fees are used by the District to
construct infrastructure capacity improvements (new wells, WWTF improvements, etc). The District
should continue to work with the development community to fund the construction of water and sewer
infrastructure improvements that would serve new development sites as a way of avoiding unnecessary
costs.
The preparation of water and sewer system master plans could help the District avoid unnecessary costs
associated with the construction of emergency system improvements to meet demands. Master plans
identify infrastructure improvements that will be needed in the future, including an improvement timeline
that would allow the District adequate time to set aside and/or obtain funding for those future
improvements before the absence of such improvements begins to delay or halt proposed development.
Master plans typically identify funding sources for their implementation.
If the SOI were expanded in the future, the District would assume fiscal responsibilities to construct or
maintain the sewer and domestic water infrastructure associated with the SOI and any territories that were
annexed. LAFCO should consider the relative financial and operational burden of new annexations to the
District when it comes to its ability to provide water and sewer service, as well as capital maintenance and
replacements required as a result of expanding the District Boundary. Opportunities exist at the time of
annexation and development to introduce alternative methods of construction and maintenance of public
or semi-public infrastructure to serve the future SOI/annexation areas.
3.4.2 Written Determinations
1. The District avoids excessive overhead costs by operating with part-time and full-time staff,
which provides adequate levels of service to the community. The District also avoids
unnecessary costs by contracting out professional services including engineering, legal
services, and other consulting services, and using these services on an as needed basis.
2. The District should continue to work with the development community to fund the
construction of water and sewer infrastructure improvements that would serve new
development sites as a way of avoiding unnecessary costs.
Cutler Public Utility District MSR Page 3-22
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3. Master planning could help the District avoid unnecessary costs by allowing the District
sufficient time to set aside funding needed for future capacity improvements that would allow
for development within the community.
4. The District could also avoid unnecessary costs associated with the maintenance of capital
infrastructure by promoting development in infill areas, and areas where infrastructure is
already in place.
Cutler Public Utility District MSR Page 3-23
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.5 OPPORTUNITIES FOR RATE RESTRUCTURING
The purpose of this section is to identify opportunities to positively impact rates without decreasing
service levels.
3.5.1 Fee Structure
The Cutler PUD charges a monthly flat rate for water service, currently set at $18.00 per month for a
typical single family dwelling. The Cutler PUD also charges a monthly flat rate for sewer service,
currently set at $22.00 per month. The District’s fiscal year 2004-05 budget estimates revenues of
$309,000 and $262,000 to be generated from water and sewer customer sales, respectively. Tables 3-2
and 3-3 show a comparison of water and sewer rates and connection (capacity rights) fees, respectively,
for all applicable service providers being reviewed. The tables also show the relationship between
monthly service charges and average household incomes within the respective communities. Since some
of the service providers charge a metered rate for water, it is necessary to calculate an average monthly
bill based upon a specific amount of usage taken as 2,005 cubic feet, or approximately 15,000 gallons per
month for this analysis.
TABLE 3-2
CUTLER PUD COMPARISON OF WATER RATES
Average
Household
Service Provider Sample Monthly Bill Connection Fee Income Rate/Income Ratio
Earlimart PUD $12.50 $1,500 $1,775/mo. 0.70%
Ivanhoe PUD $9.50 $1,700 $2,171/mo. 0.44%
Pixley PUD $20.00 $2,000 $1,942/mo. 1.03%
Teviston CSD $30.00 $800 $2,014/mo. 1.49%
Tipton CSD $24.00 $2,800 $2,198/mo. 1.09%
Alpaugh JPA $55.00 $1,500 $1,974/mo. 2.79%
Cutler PUD $18.00 $1,500 $2,028/mo. 0.89%
Orosi PUD $19.08 $2,400 $2,533/mo. 0.75%
Lemon Cove SD $10.01 $500 $2,361/mo. 0.42%
London CSD $18.00 $1,400 $1,807/mo. 1.00%
Lindsay-Strathmore ID $14.187 T&M $2,096/mo. 0.68%
Poplar CSD $25.00 $1,750 $2,043/mo. 1.22%
Richgrove CSD NA NA $1,907/mo. NA
Springville PUD $23.42 $2,800 $2,023/mo. 1.16%
Strathmore PUD $43.30 $1,150 $2,096/mo. 2.06%
Terra Bella ID $12.438 $2,908 $2,109/mo. 0.59%
Woodville PUD $27.28 $2,000 $2,123/mo. 1.28%
Average $23.17 $1,780 $2,080/mo. 1.11%
Notes: 1) Fee information obtained from service providers
2) Average household income based upon Census 2000 data
3) Rate/Income ratio calculated by dividing sample monthly bill by average household income
4) Sample monthly bill is calculated for a typical single family dwelling
5) NA=Not Available
6) T&M=Time and Material basis
7) Based on an average of four separate rates charged by the Lindsay-Strathmore Irrigation District
8) Based on potable water service provided by the Terra Bella Irrigation District
9) Richgrove CSD and Lindsay-Strathmore ID were omitted from the average calculations
Cutler Public Utility District MSR Page 3-24
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
As indicated in Table 3-2, the Cutler PUD charges monthly rates that are below average compared to
surrounding domestic water service providers. The cost of domestic water service within Cutler equates
to approximately 0.89% of the average household income within the community. The capacity rights fee
charged by the Cutler PUD for connection to its water system is also below average compared to other
domestic water service providers throughout the County. The District Engineer for the Cutler PUD
indicated that water rates will be increased by $7.00 per month in the near future as a result of Proposition
218 requirements. A $7.00 rate increase would result in a flat water rate of $25.00 per month, which is
slightly above average compared to other domestic water service providers in Tulare County. This would
result in a rate to income ratio of approximately 1.23%, which is slightly above the average of 1.11%.
TABLE 3-3
CUTLER PUD COMPARISON OF SEWER RATES
Average
Monthly Sewer Connection Household
Service Provider User Fee (1 EDU)1 Fee1 Income2 Rate/Income Ratio
Goshen CSD $32.00 $975 $2,359/mo. 1.36%
Earlimart PUD $7.50 $1,000 $1,775/mo. 0.42%
Ivanhoe PUD $9.50 $1,890 $2,171/mo. 0.44%
Pixley PUD $15.00 $1,800 $1,942/mo. 0.77%
Tipton CSD $8.00 $1,050 $2,198/mo. 0.36%
Cutler PUD $22.00 $3,520 $2,028/mo. 1.08%
Orosi PUD $22.97 $1,745 $2,533/mo. 0.91%
Lemon Cove SD $4.50 $500 $2,361/mo. 0.19%
London CSD $21.00 $1,990 $1,807/mo. 1.16%
Poplar CSD $25.00 $1,300 $2,043/mo. 1.22%
Richgrove CSD $18.00 $750 $1,907/mo. 0.94%
Springville PUD $35.06 $3,900 $2,023/mo. 1.73%
Strathmore PUD $14.70 $500 $2,096/mo. 0.70%
Terra Bella SMD $21.00 $500 $2,109/mo. 1.00%
Woodville PUD $17.25 $700 $2,123/mo. 0.81%
Average $18.23 $1,475 $2,098/mo. 0.87%
1) Source: Wastewater User Charge Survey Report FY 2004-05 (Cal EPA – SWRCB, May 2005)
2) Source: Census 2000
As indicated in Table 3-3, the Cutler PUD charges monthly rates that are above average compared to
surrounding sanitary sewer service providers. The cost of sanitary sewer service within Cutler equates to
approximately 1.08% of the average household income within the community. The capacity rights fee
charged by the Cutler PUD for connections to its sewer system is more than twice the average of other
sanitary sewer service providers throughout the County. The high sanitary sewer fees are likely
attributable to the cost of improving the Cutler-Orosi WWTF and repairing the collection system. The
District Engineer for the Cutler PUD indicated that sewer rates will be increased by $9.00 per month in
the near future as a result of Proposition 218 requirements. A $9.00 rate increase would result in a flat
sewer rate of $31.00 per month, and a rate to income ratio of 1.53%, both significantly above average,
compared to other sewer service providers in Tulare County.
Revenue generated from increased sewer fees will be used to implement a phased collection system
improvement project that will replace older leaky pipes in the system, thereby increasing its efficiency
Cutler Public Utility District MSR Page 3-25
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
and useful life. Collection system repairs will also improve operations at the WWTF by reducing the
amount of inflow/infiltration during seasonal high ground water levels (winter months).
The District should periodically review its monthly user fees, and capacity rights fees to ensure that
quality service will continually be provided to existing and future residents. Often it is necessary to
increase user fees and/or connection fees to keep pace with cost of living increases and rising material and
construction costs. Any rate increases should be substantiated and adopted through a public hearing
process. The District has opportunities to install water meters, and begin billing under a metered rate
structure for water service, which would promote water conservation in the community.
The District’s budget is structured to segregate costs associated with the construction of infrastructure to
accommodate new development. Fees paid by developers are placed into a restricted reserve account,
funds which are ultimately used by the District to construct capital capacity improvements to the
District’s water and sewer systems. User fees are used for the operations of the District and the operation
and maintenance of the District’s infrastructure, including capital replacement costs.
3.5.2 Written Determinations
1. The Cutler PUD charges monthly user fees and capacity rights fees for water and sewer. The
District’s fiscal year 2004-05 budget estimates revenues of $309,000 and $262,000 to be
generated from water and sewer customer sales, respectively.
2. The monthly user fees and capacity rights fees charged by the Cutler PUD for domestic water
service are below average compared to other domestic water service providers in Tulare
County. The District has opportunities to install water meters, and begin billing under a
metered rate structure for water service, which would promote water conservation in the
community.
3. The District Engineer for the Cutler PUD indicated that water rates will be increased by $7.00
per month in the near future as a result of Proposition 218 requirements. A $7.00 rate
increase would result in a flat water rate of $25.00 per month, which is slightly above average
compared to other domestic water service providers in Tulare County. This would result in a
rate to income ratio of approximately 1.23%, which is slightly above the average of 1.11%.
4. The monthly sewer rates charged by the Cutler PUD are above average compared to
surrounding sewer service providers. The capacity rights fee charged by the Cutler PUD for
connections to its sewer system is more than twice the average of other sanitary sewer service
providers throughout the County. The high sanitary sewer fees are likely attributable to the
cost of improving the Cutler-Orosi WWTF, and repairing the collection system.
5. The District Engineer for the Cutler PUD indicated that sewer rates will be increased by
$9.00 per month in the near future as a result of Proposition 218 requirements. A $9.00 rate
increase would result in a flat sewer rate of $31.00 per month, and a rate to income ratio of
1.53%, both significantly above average, compared to other sewer service providers in Tulare
County.
6. The District should periodically review its monthly user fees and capacity rights fees to
ensure that quality service will continually be provided to existing and future residents. Any
rate increases should be substantiated and adopted through a public hearing process.
Cutler Public Utility District MSR Page 3-26
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
7. Fees paid by developers are placed into a restricted reserve account, funds which are
ultimately used by the District to construct capital capacity improvements to the District’s
water and sewer systems. User fees are used for the operations of the District and the
operation and maintenance of the District’s infrastructure, including capital replacement
costs.
Cutler Public Utility District MSR Page 3-27
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.6 OPPORTUNITIES FOR SHARED FACILITIES
The purpose of this section is to evaluate opportunities for a jurisdiction to share facilities and resources,
thereby increasing efficiency.
3.6.1 Shared Facilities
Since the location of the Cutler SOI Boundary is immediately adjacent to the Orosi SOI Boundary,
opportunities for shared facilities and/or resources exist. The Cutler PUD and Orosi PUD take advantage
of shared infrastructure by operating a single WWTF through a JPWA comprised of three Board members
from each District.
In 2001, the communities of Cutler and Orosi submitted an application to Tulare County LAFCO to
become an incorporated City. It was subsequently determined to be infeasible at the time, on the basis of
insufficient tax revenues; however, should the two communities eventually become incorporated,
restructuring the provision of sanitary sewer and domestic water services will be necessary. The two
Districts will need to consider combining the existing infrastructure for domestic water service and
sanitary sewer service. The Districts will also need to consider adopting a uniform rate structure for all
services of the City, should the Districts ultimately incorporate as a single City entity.
3.6.2 Written Determinations
1. The Cutler PUD and Orosi PUD take advantage of shared infrastructure by operating a single
WWTF through a JPWA comprised of three Board members from each District.
2. If the communities of Cutler and Orosi eventually become an incorporated City, the Districts
will need to consider combining the existing infrastructure for domestic water and sanitary
sewer service. The District’s will also need to consider adopting a uniform rate structure for
all services of the City, should the District’s ultimately incorporate as a single City entity.
Cutler Public Utility District MSR Page 3-28
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.7 GOVERNMENT STRUCTURE OPTIONS
The purpose of this section is to consider the advantages and disadvantages of various government
structures to provide public services.
3.7.1 Development within SOI Areas
One of the most critical elements of LAFCO’s responsibilities is in setting logical service boundaries for
communities based on their capability to provide services to affected lands. According to the LAFCO
Municipal Service Review Guidelines, elimination of overlapping boundaries that confuse the public and
cause service inefficiencies should be considered to avoid unnecessary increases in the cost of
infrastructure. Currently there are no foreseeable conditions that would indicate that development within
the District’s SOI would result in a change in government structure.
It should be noted that although the current SOI boundary for the Orosi PUD and Cutler PUD are
adjacent, there are no boundary conflicts between the Districts (reference Figure 3-1). In 2001 the
communities of Orosi and Cutler submitted an application to LAFCO to become an incorporated City;
however, it was subsequently determined to be infeasible because the combined tax revenue between the
communities was insufficient to maintain the minimally acceptable un-appropriated reserve fund required
for incorporation. However, incorporation may be feasible in the future for both communities and the
procedures for incorporation are clearly identified in LAFCO guidelines.
Tulare County LAFCO has adopted specific policies for reviewing proposals for a change in organization,
reorganization, incorporations, dissolution and other proposals processed by Tulare County LAFCO.
Tulare County LAFCO policy C-1 identifies factors and standards to be considered in review proposals
including additional requirements for City annexations, standards for annexation to special districts,
standards for the formation of special districts, and standards for City incorporation.
Tulare County LAFCO policy C-2 outlines general procedures for changes in boundaries or organization
to be processed by LAFCO. Generally, proposals for changes in boundaries, formations, or changes of
organization can be submitted for the consideration of LAFCO by petition of the registered voters or
affected landowners; however, prior to the circulation of any petition, a “Notice of Intent to Circulate”
must be presented to the LAFCO Executive Officer. A proposal may also be initiated by a resolution
adopted by the governing body of any related public body (county, city or special district). The proposal
must be submitted on forms available from the LAFCO staff office, or on the LAFCO website, along with
the applicable number of maps, legal descriptions, and filing fees to cover the proposal submitted.
Prior to development within its SOI area, the District should complete infrastructure planning – including
master plans – to address the infrastructure needs of affected areas and funding mechanisms to meet those
needs. The District and/or County could also require developers to prepare specific plans prior to
approving development within the District’s SOI. The District should continually expand and improve its
water and sewer infrastructure to accommodate development within its current District Boundary and SOI
expansion areas with developer assistance.
3.7.2 Written Determinations
1. If the communities of Cutler and Orosi become an incorporated City, it is likely that a single
SOI which incorporates the areas within each District’s current SOI would be established as a
starting point. Incorporation would ultimately result in the dissolution of the Cutler PUD, as
well as the Orosi PUD. Any changes in organization should be completed in accordance with
LAFCO policies and procedures.
Cutler Public Utility District MSR Page 3-29
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
2. Prior to development within its SOI area the District should complete master planning to
address the infrastructure needs of affected areas and funding mechanisms to meet those
needs.
3. The District should continually expand and improve its domestic water and sanitary sewer
infrastructure to accommodate development within its current District Boundary and SOI
areas zoned for development with developer assistance.
Cutler Public Utility District MSR Page 3-30
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.8 EVALUATION OF MANAGEMENT EFFICIENCIES
The purpose of this section is to consider the management structure of the jurisdiction.
3.8.1 Organizational Structure
Based upon a review of information provided by the Cutler PUD, it appears that the provision of domestic
water service and sanitary sewer collection is managed in an efficient manner, meeting the needs of the
community and ratepayers. The Cutler PUD has accounting and finance functions, current personnel
regulations and resolutions. The District undergoes annual audits in compliance with auditing standards.
The age of the District’s sewer infrastructure is becoming an issue that the District needs to address in the
short-term. The District has plans to implement a phased collection system improvement project, based
upon the availability and timing of funding anticipated through various grant/loan programs, and
availability of local revenue.
The Cutler PUD is governed by a five-member Board of Directors elected at large from within its
boundaries that is responsible for setting policy and general administrative procedures. It should be noted
that three of these board members also serve on the Cutler-Orosi JPWA. The District currently operates
with part-time and full-time staff, and contracts out for other services, including engineering, legal
counsel, accounting, and other consulting services. The District operates from 8:00 a.m. to 5:00 p.m.,
Monday through Friday. The District’s answering message provides the public with the operational hours
of the District and contact information in case of emergencies.
Based upon the District’s 2004-05 budget approximately $25,000 was appropriated for contingencies.
Contingency funds can be used for emergency improvements and/or unforeseen replacement or
rehabilitation costs.
3.8.2 Written Determinations
1. Based upon information made available, it appears that the provision of domestic water
service and sanitary sewer collection is managed in an efficient manner and meets the needs
of the community and ratepayers.
2. The age of the District’s sewer infrastructure is becoming an issue that the District needs to
address in the short-term. The District has plans to implement a phased collection system
improvement project, based upon the availability and timing of funding anticipated through
various grant/loan programs, and the availability of local revenue.
3. The Cutler PUD is governed by a five member Board of Directors elected at large from
within its boundaries and is responsible for setting policy and general administrative
procedures.
4. The District currently operates with a part-time and full-time staff and contracts out for other
services, including engineering, legal counsel, accounting, and other consulting services.
5. The District’s answering message provides contact information in case of emergencies, as
well as the District’s hours of operation.
Cutler Public Utility District MSR Page 3-31
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01
3.9 LOCAL ACCOUNTABILITY AND GOVERNANCE
The purpose of this section is to evaluate the accessibility and levels of public participation associated
with the Cutler PUD’s decision-making processes.
3.9.1 Public Access and Information Methods
LAFCO may consider the agency’s record of local accountability in its management of community affairs
as a measure against the ability to provide adequate services to the SOI and annexation areas.
The Cutler PUD has a five member Board of Directors elected by voters residing within the Districts
Boundary. Regularly scheduled Board meetings, which are open to the public, are held on the third
Tuesday of each month at 6:30 PM at the District office located at 40526 Orosi Drive in Cutler. Agendas
for Board meetings are posted and notices provided consistent with public meeting requirements (i.e., the
Brown Act) including posting on-site. The District adopts budgets and rate changes at hearings where the
public is notified and invited.
The District should work with the Tulare County Resource Management Agency (RMA) and/or Tulare
County LAFCO to have information regarding District affairs posted on the Tulare County RMA and/or
LAFCO website. The District could provide information such as meeting times and locations, budgets,
rates, ordinances, agendas, completed/upcoming projects, and other District affairs to Tulare County for
posting on the County’s (RMA and/or LAFCO) website. It would make sense to post information
regarding District affairs on County websites, since Cutler is an unincorporated community within Tulare
County, and there is a mutual interest in the community.
The internet is a relatively low-cost yet powerful method of involving the general
public/customers/ratepayers in District affairs. Greater dissemination of information can lead to greater
interest in attending Board meetings and participating in elections. It also allows the public, some of
whom are not physically able to attend Board meetings, to follow District activities remotely from their
home or business.
3.9.2 Written Determinations
1. The District complies with the Brown Act open meeting law by holding regularly scheduled
meetings in which the public is invited. Regularly scheduled meetings are held on the third
Tuesday of each month at the District office. Agendas for Board meetings are posted on-site
at the District office.
2. The District adopts budgets and rate changes at hearings where the public is notified and
invited.
3. The District should work with the Tulare County Resource Management Agency (RMA)
and/or Tulare County LAFCO to have information regarding District affairs posted on the
Tulare County RMA and/or LAFCO website. The District could provide information such as
meeting times and locations, budgets, rates, ordinances, agendas, completed/upcoming
projects, and other District affairs to Tulare County for posting on the County’s (RMA and/or
LAFCO) website.
Cutler Public Utility District MSR Page 3-32
Tulare County LAFCO MSR G2_3 Cutler Apr06.DOC/55-7301-01