LAO
Supplemental Report of the 2011-12 Budget Package (Updated)
Read the report at Legislative Analyst's Office ↗
Date: August 30, 2011
To: Agency Secretaries
Department Heads
Boards and Commissions
The Supplemental Report of the 2011-12 Budget Package, dated August 30, 2011, is now
available on the Legislative Analyst’s Office’s website at: www.lao.ca.gov. This report contains
statements of legislative intent that were adopted during deliberations on the 2011-12 budget
package.
Please distribute your responses to the supplemental report, and any other report or
document you are required to submit, to the Joint Legislative Budget Committee (JLBC), as
follows:
Two Hard Copies of the Report and Transmittal Letter to:
Hon. Mark Leno, Chair
Joint Legislative Budget Committee
1020 N Street, Room 553
Sacramento, CA 95814
Attention: Ms. Jody Martin
One Hard Copy of the Report and Transmittal Letter to:
Mr. Gregory Schmidt, Secretary of the Senate
Room 400, Sacramento, CA 95814.
An Electronic Copy of the Report and Transmittal Letter to Each of the Following:
Joint Legislative Budget Committee: Jody.Martin@sen.ca.gov
for distribution to the JLBC Members.
Legislative Analyst's Office: Tina.McGee@lao.ca.gov
925 L Street, Suite 1000, Sacramento, CA 95814.
Office of the Chief Clerk of the Assembly: Amy.Leach@asm.ca.gov
Mr. E. Dotson Wilson, Chief Clerk of the Assembly
Room 3196, State Capitol, Sacramento, CA 95814.
Legislative Counsel Bureau: Jim.Lasky@lc.ca.gov
Ms. Diane Boyer-Vine, Legislative Counsel
925 L Street, Suite 900, Sacramento, CA 95814
Attention Mr. Jim Lasky.
2 August 30, 2011
In the report, as well as in your transmittal letter to Senator Leno, please cite the 11-digit
budget item number(s) and the budget year or other statutory reference to which the
response relates.
If you have any questions, you may contact our office at (916) 445-4656.
Sincerely,
Mac Taylor
Legislative Analyst
LAO
70 YEARS OF SERVICE
Supplemental Report of the
2011-12 Budget Package
Containing Statements of Intent
And Requests for Studies
Adopted by the Legislature
Compiled by the
L E G I S L A T I V E A N A L Y S T ’ S O F F I C E
REVISED October 5, 2011
Supplemental Report of the 2011-12 Budget Package
Table of Contents
L , J , e .......................................................................3
egisLative udiciaL xecutive
Item 0250‑101‑0932—Judicial Branch ...............................................................................3
Item 0502‑001‑0001—Office of the Chief Information Officer ..........................................3
Item 0502‑001‑0001—Office of the Chief Information Officer ......................ERRATA 3‑1
Item 0820‑001‑0001—Department of Justice .....................................................................3
Item 0840‑001‑0970—State Controller’s Office .................................................................3
Item 0840‑501‑0995—State Controller’s Office .................................................................4
Item 0860‑001‑0001—Board of Equalization .....................................................................4
B , t , & H ............................................................5
usiness ransportation ousing
Item 2400‑001‑0933—Department of Managed Health Care .............................................5
r .........................................................................................................6-1
esources
Item 3110‑101‑0140—Tahoe Regional Planning Agency ..............................ERRATA 6‑1
Item 3125 001 0140—California Tahoe Conservancy ....................................ERRATA 6‑1
Item 3360 001 0382—Energy Resources Conservation and
Development Commission ......................................................................ERRATA 6‑2
Item 3600‑001‑6051—Department of Fish and Game .......................................................7
Item 3790‑001‑0001—Department of Parks and Recreation ..............................................7
Item 3790‑001‑0392—Department of Parks and Recreation ..............................................7
Item 3860‑001‑0001—Department of Water Resources ....................................................8
Item 3860‑510‑0502—Department of Water Resources .....................................................8
Item 3760 001 0565—State Coastal Conservancy ..........................................ERRATA 8‑1
Item 3980 001 3056—Office of Environmental Health Hazard Assessment ..ERRATA 8‑1
H H s ............................................................................9
eaLtH and uman ervices
Item 4300‑001‑0001—Department of Developmental Services .........................................9
c r ...................................................................11
orrections and eHaBiLitation
Item 5225‑001‑0001— California Department of Corrections and Rehabilitation ...........11
Item 5225‑002‑0001—California Department of Corrections and Rehabilitation ...........11
e ..........................................................................................................13
ducation
Item 6420‑001‑0001—California Postsecondary Education Commission ......................13
g g ......................................................................................15
eneraL overnment
Item 8860‑001‑0001—Department of Finance .................................................................15
Item 8860‑001‑0001—Department of Finance .............................................ERRATA 15‑1
Item 8940‑001‑0001—Military Department .....................................................................15
Control Section 3.91 ..........................................................................................................15
LEGISLATIVE ANALYST’S OFFICE 1
Supplemental Report of the 2011-12 Budget Package
c o .................................................................................................17
apitaL utLay
Item 0250‑301‑3138—Judicial Branch—Capital Outlay ..................................................17
Item 2740‑301‑0044—Department of Motor Vehicles—Capital Outlay ..........................23
Item 3540‑301‑0668—Department of Forestry and Fire Protection—Capital Outlay ......23
Item 3790‑301‑0005—Department of Parks and Recreation—Capital Outlay ................24
Item 3790‑301‑0263—Department of Parks and Recreation—Capital Outlay ................24
Item 3790‑301‑6051—Department of Parks and Recreation—Capital Outlay ................25
Item 3860‑301‑6052—Department of Water Resources—Capital Outlay .......................26
Item 3860‑301‑6052/Reimbursements—Department of Water Resources—
Capital Outlay ..........................................................................................................26
Item 3860‑302‑6052—Department of Water Resources—Capital Outlay .......................28
Item 4300‑301‑0001—Department of Developmental Services—Capital Outlay ............28
Item 4440‑301‑0001—Department of Mental Health—Capital Outlay ............................28
Item 6610‑301‑0668—California State University—Capital Outlay ................................29
Item 6640‑302‑6048—University of California—Capital Outlay ....................................29
Item 6870‑301‑6049—California Community Colleges—Capital Outlay .......................30
2 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
L , J , e
egisLative udiciaL xecutive
Item 0250‑101‑0932—Judicial Branch
1. Judicial Branch Budget Display. No later than April 15, 2012, the Administrative
Office of the Courts shall submit to the appropriate budget committees of each
house a report detailing all expenditures, incurred and projected, during the
2011‑12 fiscal year that are a result of activities required by or related to the 2011
public safety realignment as specified in Chapter 15, Statutes of 2011 (AB 109,
Committee on Budget), Chapter 39, Statutes of 2011 (AB 117, Committee on Budget)
and Chapter 136, Statutes of 2011 (AB 116, Committee on Budget).
Item 0502‑001‑0001—Office of the Chief Information Officer
1. Unanticipated Costs for Information Technology (IT) Projects. It is the intent of the
Legislature that the California Technology Agency and the Department of Finance
jointly develop written criteria for determining when it may be appropriate to provide
departments with budget provisions permitting expenditures for unanticipated costs
for IT projects which exceed the amounts in approved project documents and/or the
budget act. The Legislature further intends that this written criteria be (a) developed
with consultation with the Legislative Analyst’s Office, (b) completed prior to October
1, 2012, so that it can be utilized if need be in developing the 2012‑13 budget, and
(c) shared with the Legislature upon completion. See Item 8860‑001‑0001.
Item 0820‑001‑0001—Department of Justice
1. Forensic Laboratories. No later than March 1, 2012, the Department of Finance
shall submit to the appropriate budget committees of each house a report on the
feasibility of realigning the Department of Justice’s forensic laboratories from a
state to a local responsibility.
Item 0840‑001‑0970—State Controller’s Office
1. Unclaimed Property Holder Compliance Initiative. The State Controller shall
report to the Legislature by November 1, 2012, and by November 1, 2013, on the
outcomes related to the 22.6 three‑year limited‑term positions authorized to
develop and implement a holder outreach and compliance program. The report to
the Legislature shall include but not be limited to: (a) the design of the outreach
program; (b) the effectiveness of the outreach program as measured by the dollar
value of property paid to owners and collected from holders in 2008‑09, 2009‑10,
2010‑11, and during the years of these resources; (c) a description of the audit plan
describing the criteria involved in selecting a business to be audited, the scope of
LEGISLATIVE ANALYST’S OFFICE 3
Supplemental Report of the 2011-12 Budget Package
L , J , e
egisLative udiciaL xecutive
Item 0502‑001‑0001—Office of the Chief Information Officer
2. Implementation and Reporting on Governor’s Reorganization Plan. It is the intent of
the Legislature that the California Technology Agency (Technology Agency) and
the Department of Finance (DOF) jointly develop reporting metrics that capture
additional information not already included in the Technology Agency’s statuto-
rily required annual reports. These metrics will include, but not be limited to, in-
formation on cost and risk avoidance and identified impediments to the continued
implementation of the Governor’s Reorganization Plan No. 1 (GRP).
It is the intent of the Legislature that these metrics be (a) developed in
consultation with the Legislative Analyst’s Office (LAO), (b) be completed in
time for the information to be incorporated, as appropriate, into the Technology
Agency’s 2012 annual reports, and (c) be shared with the Legislature.
It is also the intent of the Legislature that the Technology Agency convene an
annual meeting with legislative staff, DOF, and LAO to discuss the overall status
of the implementation of the GRP, lessons learned to date, and existing barriers
to the GRP’s completion. The timing of this meeting is to be determined by the
Technology Agency, but it is the intent of the Legislature that it occur after the
completion of the annual reports required by statute. (Also see Item 8860-001-0001.)
LEGISLATIVE ANALYST’S OFFICE ERRATA PAGE 3‑1
Supplemental Report of the 2011-12 Budget Package
the audits, and the outcomes of the audits; (d) the effectiveness of the audits as
measured by the dollar value of property remitted to the state in 2008‑09, 2009‑10,
2010‑11, and during the years of these resources; (e) a description of the follow‑up
activities to monitor businesses after an audit; and (f) the rate of return of investing
$1 into the outreach and audit functions of the initiative. The report shall be
provided to the fiscal committees of the Legislature, the Joint Legislative Budget
Committee, the Department of Finance, and the Legislative Analyst’s Office.
Item 0840‑501‑0995—State Controller’s Office
1. Local Government Oversight Initiative. The State Controller’s Office (SCO)
shall report to the Legislature by January 1, 2013, and by January 1, 2014, on the
workload and outcomes related to the 16.4 three‑year limited‑term positions
authorized for the purpose of increasing SCO capacity to review local government
financial transactions reports. The report to the Legislature shall include but
not be limited to: (a) the number of non‑filers and reports completed by SCO
in 2008‑09, 2009‑10, 2010‑11, and during the years of these resources; (b) the
number of investigations for false, incorrect, or incomplete information in annual
transaction reports and a summary of the outcomes of these investigations; and
(c) the dollar amount charged to local governments for SCO’s investigations and
reports compared with the amounts received and expended by SCO for these
purposes. The report shall be provided to the fiscal committees of the Legislature,
the Joint Legislative Budget Committee (JLBC), the Department of Finance (DOF),
and the Legislative Analyst’s Office (LAO).
2. Transportation Audits—Indirect Cost Allocation Plans. The SCO shall report
to the Legislature by March 1, 2012 on the necessity of continuing for fiscal year
2012‑13, 12.6 limited‑term audit positions to provide audit services for indirect
cost allocation plans for local government agencies pursuant to a request by the
California Department of Transportation. The report to the Legislature shall
include but not be limited to: (a) comparison of 2011‑12 estimated workload and
actual workload to date of the positions, (b) analysis of any changes in federal
audit requirements for the receipt of federal funds that could affect workload in
2012‑13, and (c) estimated workload for the positions in 2012‑13. The report shall
be provided to the fiscal committees of the Legislature, JLBC, DOF, and LAO.
Item 0860‑001‑0001—Board of Equalization
1. Statewide Compliance and Outreach Program. The Board of Equalization shall
report to the Legislature and the Department of Finance annually, not later than
March 1 of each year, on the performance of the Statewide Compliance and Outreach
Program. The report shall include, but not be limited to, a schedule of authorized
positions, vacant positions, expenditures, and revenues attributable to the program.
4 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
B , t , & H
usiness ransportation ousing
Item 2400‑001‑0933—Department of Managed Health Care
1. Analysis of Actuarial Review Options. On or before March 1, 2012, the
Department of Managed Health Care (DMHC) shall submit a report to the Joint
Legislative Budget Committee and the relevant policy committees that provides
(a) an analysis of different options for DMHC to conduct actuarial review with
state staff, rather than through contracts; and (b) a recommendation of one or
more options to implement. The analysis shall include sufficient detail regarding
the costs and other advantages or disadvantages of each option to allow the
Legislature to make an informed decision.
LEGISLATIVE ANALYST’S OFFICE 5
Supplemental Report of the 2011-12 Budget Package
6 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
R
esouRces
Item 3110‑101‑0140—Tahoe Regional Planning Agency
1. Status of Environmental Threshold Carrying Capacities. The Tahoe Regional
Planning Agency (TRPA) shall, by December 31, 2011, in coordination with
the California Natural Resources Agency and the Nevada Department of
Conservation and Natural Resources, report on its progress in developing and
adopting a five-year evaluation report, including peer review coordinated by
the Tahoe Science Consortium, on the status of TRPA’s environmental threshold
carrying capacities. To broaden scientific involvement, the peer review shall
include a majority of scientists from institutions or agencies who are not
participating as signatories to the memorandum of agreement that established the
consortium.
Item 3125‑001‑0140—California Tahoe Conservancy
1. Environmental Improvement Program: Coordination and Efficiencies. To
maximize the effectiveness of state resources and to better implement the Lake
Tahoe Environmental Improvement Program (EIP), by December 1, 2011, the
Conservancy, in coordination with the Department of Parks and Recreation; the
Lahontan Regional Water Quality Control Board; the California Department
of Transportation (Caltrans); the State Lands Commission; the Department of
Forestry and Fire Protection (CalFire); the Department of Fish and Game; and
other appropriate state, local, and federal agencies, shall report to the Legislature
on its progress in coordinating, integrating, and recommending efficiencies
in state agency planning and project implementation in the Tahoe basin. The
report shall include consideration of, but not limited to: joint use of staff, crews,
equipment, office space, and facilities; land exchanges that would increase
management efficiencies; and coordinated funding and implementation of
EIP projects and programs, Caltrans’ complete streets implementation action
plan, climate change mitigation and adaptation strategies, and an interagency
watershed-based approach to the Lake Tahoe Total Maximum Daily Load. This
report shall also identify programmatic or policy-based improvements that public
agencies could make to improve the effort described herein.
2. The EIP and Sustainable Communities Strategy: Progress Reports. The
Conservancy, in coordination with the Tahoe Regional Planning Agency (TRPA)
and other state and local agencies, shall report to the Legislature, by December 1,
2011, with a summary of:
LEGISLATIVE ANALYST’S OFFICE ERRATA PAGE 6‑1
Supplemental Report of the 2011-12 Budget Package
(a) State agency expenditures, accomplishments, priority projects and programs,
and other activities and resources needed to help achieve TRPA’s environmental
thresholds and to fulfill California’s responsibilities under the EIP.
(b) The agencies’ progress in developing a Sustainable Communities Strategy for
the Lake Tahoe basin, as required under Chapter 728, Statutes of 2008 (SB 375,
Steinberg), and Chapter 488, Statutes of 2006 (AB 32, Núñez and Pavley), and
any changes in state agency policies or practices needed to further develop and
accomplish the goals of the plan.
Item 3360‑001‑0382—Energy Resources Conservation and
Development Commission
1. Funding for Renewables Portfolio Standard (RPS) Program. The commission
shall report to the Legislature, on or before January 10, 2012, with a proposal for
long-term funding of (a) the additional permanent positions for the RPS program
included in the 2011-12 Budget Act, if the public goods charge supporting the
Renewables Resource Trust Fund is not extended beyond its current statutory
sunset date of January 2012, and (b) the statutory requirements of the state’s RPS
law—Chapter 1, Statutes of 2011 (SBx1 2, Simitian).
ERRATA PAGE 6‑2 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
r
esources
Item 3600‑001‑6051—Department of Fish and Game
1. Salton Sea Restoration. The Department of Water Resources and the Department
of Fish and Game shall jointly submit a report to the Legislature, on or before
December 31, 2011, documenting expenditures from all fund sources and agency
staff time by both departments on Salton Sea mitigation or restoration efforts
since the inception of the Salton Sea Restoration Fund. This report shall also
document actions that both departments have taken to (a) disburse grants to local
governmental and non‑governmental entities for on‑the‑ground work for habitat
restoration at the sea and (b) complete the environmental review and permitting
of the Species Conservation Habitat ponds project. The report shall also discuss
efforts of the Natural Resources Agency to establish the Salton Sea Restoration
Council and hire the council’s executive director. See Item 3860‑001‑0001.
Item 3790‑001‑0001—Department of Parks and Recreation
1. Park Unit Budget and Revenues and Safety Statistics.
(a) The department shall, by January 10, 2012, report its estimated budget to the
Legislature on a park‑unit basis. This shall include an estimate of distributed
shared costs on a pro rata basis (personnel, materials, and services) shared by
sectors or across districts.
(b) The department shall, by March 1, 2012, submit a report to the Legislature on
estimated revenues by park unit and visitor data (by park unit, aggregated on a
district basis). The report shall compare these data to those of the National Parks
System and other state park systems.
(c) The department shall, by March 1, 2012, submit a report to the Legislature on
(i) statistics on peace officers’ use of weapons in state parks to deter crime or to
respond to crimes in process and (ii) the department’s enforcement of non‑parks
related crimes and provision of mutual aid, including information on the number
of park rangers not assigned to any park unit.
Item 3790‑001‑0392—Department of Parks and Recreation
1. Fleet Emissions Retrofit. It is the intent of the Legislature that the department
shall bring the issue of the amount of expenditures in 2011‑12 required to comply
with the Air Resource Board’s on‑road, heavy‑duty diesel vehicle regulations
LEGISLATIVE ANALYST’S OFFICE 7
Supplemental Report of the 2011-12 Budget Package
back at a future legislative budget hearing if the Administration identifies a fleet
reduction and related savings to the department as a result of Executive Order
B‑2‑11 (which requires state agencies to conduct an analysis of their fleets and
equipment and sell or transfer non‑essential vehicles).
Item 3860‑001‑0001—Department of Water Resources
1. Salton Sea Restoration. The Department of Water Resources and the Department
of Fish and Game shall jointly submit a report to the Legislature, on or before
December 31, 2011, documenting expenditures from all fund sources and agency
staff time by both departments on Salton Sea mitigation or restoration efforts
since the inception of the Salton Sea Restoration Fund. This report shall also
document actions that both departments have taken to (a) disburse grants to local
governmental and non‑governmental entities for on‑the‑ground work for habitat
restoration at the sea and (b) complete the environmental review and permitting
of the Species Conservation Habitat ponds project. The report shall also discuss
efforts of the Natural Resources Agency to establish the Salton Sea Restoration
Council and hire the council’s executive director. See Item 3600‑001‑6051.
Item 3860‑510‑0502—Department of Water Resources
1. Biological Opinions. The Department of Water Resources shall, starting in Au‑
gust 2011, make available on its public website all studies and analyses required
by or requested by the U.S. Fish and Wildlife Service, National Marine Fisheries
Service, or the California Department of Fish and Game, including those actions
as required by the Biological Opinions.
8 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
Item 3760‑001‑0565—State Coastal Conservancy
1. Long-Term Plan. On or before January 10, 2013, the State Coastal Conservancy
shall submit a long-term plan for the conservancy spanning a ten-year period
starting in 2013-14. The plan shall include funding needs should no new bond
funds be made available, staffing reduction plans, and options for continued
funding support for core functions (including the Ocean Protection Council).
Item 3980‑001‑3056—Office of Environmental Health Hazard
Assessment
1. Funding for Proposition 65 Program. The Office of Environmental Health
Hazard Assessment shall report to the Legislature, by January 10, 2012, on the
appropriateness of using the Toxic Substances Control Account or other special
fund sources—as alternatives to the Safe Drinking Water and Toxic Enforcement
Fund—to fund the office’s program to implement Proposition 65 (the Safe
Drinking Water and Enforcement Act).
LEGISLATIVE ANALYST’S OFFICE ERRATA PAGE 8‑1
Supplemental Report of the 2011-12 Budget Package
H H s
eaLtH and uman ervices
Item 4300‑001‑0001—Department of Developmental Services
1. Prevention Program Transition. It is the intent of the Legislature that the
Department of Developmental Services (DDS) assess and report to the Legislature
on the implementation of the transfer of services of the Prevention Program
to the Family Resource Centers. No later than January 15, 2013, DDS shall
submit a report. The report shall include, but not be limited to, the following:
an assessment of the Family Resource Center’s ability to provide information,
outreach, and referral to generic resources, and to make referrals to the Regional
Center for reassessment; caseload trends in the 0 through 2 population beginning
one year prior to the establishment of the Prevention Program; numbers of
children evaluated but not referred to the Early Start or Lanterman Services
Programs; and an assessment in referral to the Early Start or Lanterman Services
Programs of any disparities based on race, ethnicity, or geography.
LEGISLATIVE ANALYST’S OFFICE 9
Supplemental Report of the 2011-12 Budget Package
10 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
c r
orrections and eHaBiLitation
Item 5225‑001‑0001— California Department of Corrections and
Rehabilitation
1. Public Safety Realignment. During the 2011‑12 fiscal year, and beginning on
October 1, 2011, the California Department of Corrections and Rehabilitation
(CDCR) shall submit to the appropriate budget committees of each house quar‑
terly reports on actions taken to implement and savings achieved related to the
2011 public safety realignment as specified in Chapter 15, Statutes of 2011 (AB 109,
Committee on Budget), Chapter 39, Statutes of 2011 (AB 117, Committee on
Budget), and Chapter 136, Statutes of 2011 (AB 116, Committee on Budget).
2. Workforce Cap. During the 2011‑12 fiscal year, and beginning on October 1, 2011,
CDCR shall submit to the appropriate budget committees of each house quarterly
reports on actions taken and savings achieved pursuant to Control Section 3.93 of
the 2011 Budget Act.
Item 5225‑002‑0001—California Department of Corrections and
Rehabilitation
1. Medication Management. No later than April 1, 2012, the California Prison
Health Care Services shall submit to the appropriate budget committees of each
house a report on the savings attributed to Licensed Vocational Nurse positions
hired during the 2010‑11 and 2011‑12 fiscal years, by prison.
LEGISLATIVE ANALYST’S OFFICE 11
Supplemental Report of the 2011-12 Budget Package
12 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
e
ducation
Item 6420‑001‑0001—California Postsecondary Education
Commission
1. Structure and Duties of Coordinating Body. On or before January 1, 2012,
the Office of the Legislative Analyst shall submit a report to the Legislature
that includes the recommendations of the Legislative Analyst with respect to
the structure and duties of a statewide higher education coordinating body
for California. In developing its recommendations, the Legislative Analyst
may consult with the Assembly and Senate policy and budget committees, the
Administration, the Postsecondary Education commission, the Student Aid
Commission, the Bureau of Private Postsecondary Education, the Superintendent
of Public Instruction, the Chancellor’s Office of the California Community
Colleges, the University of California, the California State University, and
appropriate postsecondary education stakeholders. It is the intent of the
Legislature that the report examine statewide coordination of educational
institutions in other states, and identify effective policies, practices, and structures
from these examples.
LEGISLATIVE ANALYST’S OFFICE 13
Supplemental Report of the 2011-12 Budget Package
14 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
g g
eneraL overnment
Item 8860‑001‑0001—Department of Finance
1. Unanticipated Costs for Information Technology (IT) Projects. It is the intent of the
Legislature that the California Technology Agency and the Department of Finance
jointly develop written criteria for determining when it may be appropriate to provide
departments with budget provisions permitting expenditures for unanticipated costs
for IT projects which exceed the amounts in approved project documents and/or the
budget act. The Legislature further intends that this written criteria be (a) developed
with consultation with the Legislative Analyst’s Office, (b) completed prior to
October 1, 2012, so that it can be utilized if need be in developing the 2012‑13 budget,
and (c) shared with the Legislature upon completion. See Item 0502‑001‑0001.
Item 8940‑001‑0001—Military Department
1. California Cadet Program. By January 10, 2012, and each year thereafter until
January 10, 2013, the department shall report to the Joint Legislative Budget
Committee on the status of the California Cadet Corp Program. The report shall
include the following information:
(a) The number of cadets currently enrolled in the program and the number of
program sites and, as a baseline comparison, the number of cadets enrolled in
the program and the number of program sites on July 1, 2011.
(b) A description of the department’s expenditures on the Cadet Program,
including how the department has expended, or plans to expend, the $300,000
augmentation for the program included in the 2011‑12 budget.
LEGISLATIVE ANALYST’S OFFICE 15
Supplemental Report of the 2011-12 Budget Package
g g
eneraL overnment
Item 8860‑001‑0001—Department of Finance
2. Implementation and Reporting on Governor’s Reorganization Plan. It is the intent of
the Legislature that the California Technology Agency (Technology Agency) and
the Department of Finance (DOF) jointly develop reporting metrics that capture
additional information not already included in the Technology Agency’s statuto-
rily required annual reports. These metrics will include, but not be limited to, in-
formation on cost and risk avoidance and identified impediments to the continued
implementation of the Governor’s Reorganization Plan No. 1 (GRP).
It is the intent of the Legislature that these metrics be (a) developed in
consultation with the Legislative Analyst’s Office (LAO), (b) be completed in
time for the information to be incorporated, as appropriate, into the Technology
Agency’s 2012 annual reports, and (c) be shared with the Legislature.
It is also the intent of the Legislature that the Technology Agency convene an
annual meeting with legislative staff, DOF, and LAO to discuss the overall status of
the implementation of the GRP, lessons learned to date, and existing barriers to the
GRPs completion. The timing of this meeting is to be determined by the Technology
Agency, but it is the intent of the Legislature that it occur after the completion of the
annual reports required by statute. (Also see Item 0502-001-0001.)
LEGISLATIVE ANALYST’S OFFICE ERRATA PAGE 15‑1
Supplemental Report of the 2011-12 Budget Package
16 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
c s
ontroL ections
Control Section 3.91
1. Government Reorganization and Consolidation. It is the intent of the
Legislature that, as the Department of Finance reviews boards, commissions,
and task forces for elimination, reorganization, and consolidation, it examine
eliminating or reducing (a) salaries for members of boards and commissions
and (b) other board and commission costs, as alternative actions to achieve state
savings instead of eliminating a board or commission that provides important
public services.
LEGISLATIVE ANALYST’S OFFICE 17
Supplemental Report of the 2011-12 Budget Package
18 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
c o
apitaL utLay
Item 0250‑301‑3138—Judicial Branch—Capital Outlay
1. Butte County—New North County Courthouse. The amount of $4,358,000
is provided for the working drawings phase to construct a new courthouse
in Butte County. The new 67,443 gross square foot (gsf) building will house
five courtrooms. Total estimated project cost is $76,947,000 without financing:
$8,150,000 for acquisition, $3,339,000 for preliminary plans, $4,358,000 for working
drawings, and $61,100,000 (CCCI 5264) for construction. The construction amount
includes $53,863,000 for the construction contract, $2,693,000 for contingency,
$1,096,000 for architectural and engineering fees, and $3,448,000 for other project
costs. Acquisition was completed in December 2010 and preliminary plans are
scheduled to be completed by October 2011. Construction will begin in
August 2012 and be completed by February 2014. The current schedule is under
review and may be amended as a result of the 2011‑12 one‑time redirections and
loans from the Immediate and Critical Needs Account.
2. Fresno County—Renovate Fresno County Courthouse. The amount of $6,142,000
is provided for the working drawings phase to renovate the existing 28 courtroom
courthouse of approximately 213,687 gsf in the city of Fresno. Total estimated
project cost is $113,348,000 without financing: $4,302,000 for preliminary plans,
$6,142,000 for working drawings, and $102,904,000 (CCCI 5264) for construction.
The construction amount includes $89,521,000 for the construction contract,
$6,266,000 for contingency, $3,101,000 for architectural and engineering fees, and
$4,016,000 for other project costs. Preliminary plans are scheduled for completion
by May 2012. Construction will begin in February 2013 and be completed by
November 2015. The current schedule is under review and may be amended as
a result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
3. Imperial County—New El Centro Family Courthouse. The amount of $3,496,000
is provided for the working drawings phase to construct a new courthouse in
Imperial County. The new 53,983 gsf building will house four courtrooms. Total
estimated project cost is $59,484,000 without financing: $2,683,000 for acquisition,
$2,717,000 for preliminary plans, $3,496,000 for working drawings, and $50,588,000
(CCCI 5264) for construction. The construction amount includes $44,658,000 for
the construction contract, $2,233,000 for contingency, $892,000 for architectural
and engineering fees, and $2,805,000 for other project costs. Acquisition will
be completed in November 2011 and preliminary plans are scheduled to be
completed by June 2012. Construction will begin in June 2013 and be completed
LEGISLATIVE ANALYST’S OFFICE 19
Supplemental Report of the 2011-12 Budget Package
by December 2014. The current schedule is under review and may be amended
as a result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
4. Kern County—New Delano Courthouse. The amount of $2,533,000 is provided
for the working drawings phase to construct a new courthouse in Kern County.
The new 39,780 gsf building will house three courtrooms. Total estimated project
cost is $41,425,000 without financing: $1,620,000 for acquisition, $1,892,000 for
preliminary plans, $2,533,000 for working drawings, and $35,380,000
(CCCI 5296) for construction. The construction amount includes $31,255,000 for
the construction contract, $1,563,000 for contingency, $621,000 for architectural
and engineering fees, and $1,941,000 for other project costs. Acquisition will
be completed in December 2011 and preliminary plans are scheduled to be
completed by June 2012. Construction will begin in June 2013 and be completed
by January 2015. The current schedule is under review and may be amended as
a result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
5. Kings County—New Hanford Courthouse. The amount of $8,342,000 is provided
for the working drawings phase to construct a new courthouse in Kings County.
The new 144,460 gsf building will house 12 courtrooms. Total estimated project
cost is $136,460,000 without financing: $6,260,000 for acquisition, $6,231,000 for
preliminary plans, $8,342,000 for working drawings, and $115,627,000
(CCCI 5296) for construction. The construction amount includes $102,249,000 for
the construction contract, $5,112,000 for contingency, $2,045,000 for architectural
and engineering fees, and $6,221,000 for other project costs. Acquisition was
completed in May 2011 and preliminary plans are scheduled to be completed
by February 2012. Construction will begin in March 2013 and be completed by
January 2015. The current schedule is under review and may be amended as a
result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
6. Lake County—New Lakeport Courthouse. The amount of $3,646,000 is provided
for the working drawing phase to construct a new courthouse in Lake County.
The new 50,158 gsf building will house four courtrooms. Total estimated project
cost is $55,967,000 without financing: $2,610,000 for acquisition, $2,830,000 for
preliminary plans, $3,646,000 for working drawings, and $46,881,000
(CCCI 5264) for construction. The construction amount includes $40,393,000 for
the construction contract, $2,020,000 for contingency, $812,000 for architectural
and engineering fees, and $3,656,000 for other project costs. Acquisition was
completed in January 2011 and preliminary plans are scheduled to be completed
by February 2012. Construction will begin in April 2013 and be completed by
20 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
December 2014. The current schedule is under review and may be amended as
a result of the 2011‑20 one‑time redirections and loans from the Immediate and
Critical Needs Account.
7. Merced County—New Los Banos Courthouse. The amount of $1,974,000 is
provided for the working drawings phase to construct a new courthouse in
Merced County. The new 29,511 gsf building will house two courtrooms. Total
estimated project cost is $32,208,000 without financing: $1,727,000 for acquisition,
$1,474,000 for preliminary plans, $1,974,000 for working drawings, and $27,033,000
(CCCI 5296) for construction. The construction amount includes $23,882,000 for
the construction contract, $1,194,000 for contingency, $484,000 for architectural
and engineering fees, and $1,473,000 for other project costs. Acquisition will
be completed in November 2011 and preliminary plans are scheduled to be
completed by May 2012. Construction will begin in March 2013 and be completed
by March 2014. The current schedule is under review and may be amended as
a result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
8. Monterey County—New South Monterey Courthouse. The amount of $2,985,000
is provided for the working drawings phase to construct a new courthouse in
Monterey County. The new 47,223 gsf building will house three courtrooms. Total
estimated project cost is $49,061,000 without financing: $686,000 for acquisition,
$2,288,000 for preliminary plans, $2,985,000 for working drawings, and $43,102,000
(CCCI 5264) for construction. The construction amount includes $37,334,000 for
the construction contract, $1,867,000 for contingency, $1,539,000 for architectural
and engineering fees, and $2,362,000 for other project costs. Acquisition was
completed in May 2011 and preliminary plans are scheduled to be completed
by January 2012. Construction will begin in March 2013 and be completed by
March 2015. The current schedule is under review and may be amended as a
result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
9. Riverside County—New Indio Juvenile and Family Courthouse. The amount
of $3,789,000 is provided for the working drawings phase to construct a new
courthouse in Riverside County. The new 67,933 gsf building will house five
courtrooms. Total estimated project cost is $65,682,000 without financing:
$4,419,000 for acquisition, $2,834,000 for preliminary plans, $3,789,000 for working
drawings, and $54,640,000 (CCCI 5264) for construction. The construction amount
includes $48,273,000 for the construction contract, $2,414,000 for contingency,
$953,000 for architectural and engineering fees, and $3,000,000 for other project
costs. Acquisition was completed in January 2011 and preliminary plans are
scheduled to be completed by May 2012. Construction will begin in August 2013
and be completed by January 2015. The current schedule is under review and may
LEGISLATIVE ANALYST’S OFFICE 21
Supplemental Report of the 2011-12 Budget Package
be amended as a result of the 2011‑12 one‑time redirections and loans from the
Immediate and Critical Needs Account.
10. Sacramento County—New Sacramento Criminal Courthouse. The amount
of $22,924,000 is provided for the working drawings phase to construct a new
courthouse in Sacramento County. The new 405,500 gsf building will house
44 courtrooms. Total estimated project cost is $437,516,000 without financing:
$33,939,000 for acquisition, $17,124,000 for preliminary plans, $22,924,000 for working
drawings, and $363,529,000 (CCCI 5264) for construction. The construction amount
includes $324,581,000 for the construction contract, $16,229,000 for contingency,
$5,621,000 for architectural and engineering fees, and $17,098,000 for other project
costs. Acquisition will be completed in February 2013 and preliminary plans are
scheduled to be completed by February 2012. Construction will begin in July 2013
and be completed by January 2016. The current schedule is under review and may
be amended as a result of the 2011‑12 one‑time redirections and loans from the
Immediate and Critical Needs Account.
11. San Diego County—New Central San Diego Courthouse. The amount of
$32,367,000 is provided for the working drawings phase to construct a new
courthouse in San Diego County. The 704,000 gsf building will house
71 courtrooms in downtown San Diego. Total estimated project cost is $642,596,000
without financing: $8,633,000 for acquisition, $21,559,000 for preliminary plans,
$32,367,000 for working drawings, and $580,037,000 (CCCI 5263) for construction.
The construction amount includes $502,286,000 for the construction contract,
$25,614,000 for contingency, $7,754,000 for architectural and engineering fees, and
$44,383,000 for other project costs. Acquisition was completed in March 2011 and
preliminary plans are scheduled to be completed by March 2012. Construction will
begin July 2013 and be completed by December 2015. The current schedule is under
review and may be amended as a result of the 2011‑12 one‑time redirections and
loans from the Immediate and Critical Needs Account.
12. San Joaquin County—Renovate and Expand Juvenile Justice Center. The
amount of $3,633,000 is provided for the working drawings and construction
phases to renovate and expand the existing Juvenile Justice Center in the city
of French Camp. The one courtroom expansion is approximately 4,000 gsf.
Total estimated project cost is $3,877,000 with $244,000 for preliminary plans,
$259,000 for working drawings, and $3,374,000 (CCCI 5264) for construction. The
construction amount includes $2,880,000 for the construction contract, $202,000
for contingency, $127,000 for architectural and engineering fees, and $165,000
for other project costs. Preliminary plans are scheduled to be completed by
September 2011. Construction will begin in September 2012 and be completed by
December 2013. The current schedule is under review and may be amended as
22 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
a result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
13. Santa Clara County—New Family Justice Center. The amount of $14,637,000 is
provided for the working drawings phase to construct a new courthouse in
Santa Clara County. The 233,906 gsf building will house 20 courtrooms in the
city of San Jose. Total estimated project cost is $241,950,000 without financing:
$6,205,000 for acquisition, $11,111,000 for preliminary plans, $14,637,000
for working drawings, and $209,997,000 (CCCI 5309) for construction. The
construction amount includes $184,966,000 for the construction contract, $9,248,000
for contingency, $4,375,000 for architectural and engineering fees, and $11,408,000
for other project costs. Acquisition was completed in May 2011 and preliminary
plans are scheduled to be completed by June 2012. Construction will begin
June 2013 and be completed by March 2015. The current schedule is under review
and may be amended as a result of the 2011‑12 one‑time redirections and loans
from the Immediate and Critical Needs Account.
14. Shasta County—New Redding Courthouse. The amount of $9,055,000 is provided
for the working drawings phase to construct a new courthouse in Shasta County.
The new 173,351 gsf building will house 14 courtrooms. Total estimated project
cost is $170,598,000 without financing: $7,871,000 for acquisition, $6,394,000 for
preliminary plans, $9,055,000 for working drawings, and $147,278,000 (CCCI 5264)
for construction. The construction amount includes $130,941,000 for the construction
contract, $6,547,000 for contingency, $2,352,000 for architectural and engineering
fees, and $7,438,000 for other project costs. Acquisition will be completed in
October 2011 and preliminary plans are scheduled to be completed by April 2012.
Construction will begin in April 2013 and be completed by April 2015. The current
schedule is under review and may be amended as a result of the 2011‑12 one‑time
redirections and loans from the Immediate and Critical Needs Account.
15. Siskiyou County—New Yreka Courthouse. The amount of $5,861,000 is provided
for the working drawings phase to construct a new courthouse in Siskiyou
County. The new 86,163 gsf building will house six courtrooms. Total estimated
project cost is $95,370,000 without financing: $2,543,000 for acquisition, $4,378,000
for preliminary plans, $5,861,000 for working drawings, and $82,588,000
(CCCI 5296) for construction. The construction amount includes $73,124,000 for
the construction contract, $3,656,000 for contingency, $1,437,000 for architectural
and engineering fees, and $4,371,000 for other project costs. Acquisition will
be completed in November 2011 and preliminary plans are scheduled to be
completed by June 2012. Construction will begin in July 2013 and be completed
by December 2014. The current schedule is under review and may be amended
as a result of the 2011‑12 one‑time redirections and loans from the Immediate and
Critical Needs Account.
LEGISLATIVE ANALYST’S OFFICE 23
Supplemental Report of the 2011-12 Budget Package
16. Sutter County—New Yuba City Courthouse. The amount of $4,693,000 is provided
for the working drawings phase to construct a new courthouse in Sutter County.
The new 78,701 gsf building will house seven courtrooms. Total estimated project
cost is $73,906,000 without financing: $1,059,000 for acquisition, $3,543,000 for
preliminary plans, $4,693,000 for working drawings, and $64,611,000 (CCCI 5264)
for construction. The construction amount includes $56,873,000 for the construction
contract, $2,844,000 for contingency, $1,181,000 for architectural and engineering
fees, and $3,713,000 for other project costs. Acquisition was completed in
April 2011 and preliminary plans are scheduled to be completed by December 2011.
Construction will begin in February 2013 and be completed by August 2014. The
current schedule is under review and may be amended as a result of the 2011‑12
one‑time redirections and loans from the Immediate and Critical Needs Account.
17. Tehama County—New Red Bluff Courthouse. The amount of $3,982,000 is
provided for the working drawings phase to construct a new courthouse in
Tehama County. The new 62,033 gsf building will house five courtrooms in the
city of Red Bluff. Total estimated project cost is $72,313,000 without financing:
$7,791,000 for acquisition, $3,106,000 for preliminary plans, $3,982,000 for working
drawings, and $57,434,000 (CCCI 5264) for construction. The construction amount
includes $50,673,000 for the construction contract, $2,534,000 for contingency,
$1,019,000 for architectural and engineering fees, and $3,208,000 for other project
costs. Acquisition will be completed in October 2011 and preliminary plans are
scheduled to be completed by May 2012. Construction will begin in July 2013
and be completed by March 2015. The current schedule is under review and may
be amended as a result of the 2011‑12 one‑time redirections and loans from the
Immediate and Critical Needs Account.
18. Tuolumne County—New Sonora Courthouse. The amount of $4,268,000 is
provided for the working drawings phase to construct a new courthouse in
Tuolumne County. The new 66,724 gsf building will house five courtrooms in
the city of Sonora. Total estimated project cost is $69,236,000 without financing:
$2,252,000 for acquisition, $3,188,000 for preliminary plans, $4,268,000 for working
drawings, and $59,528,000 (CCCI 5296) for construction. The construction amount
includes $52,664,000 for the construction contract, $2,633,000 for contingency,
$1,046,000 for architectural and engineering fees, and $3,185,000 for other project
costs. Acquisition will be completed in November 2011 and preliminary plans are
scheduled to be completed by July 2012. Construction will begin in August 2013
and be completed by March 2015. The current schedule is under review and may
be amended as a result of the 2011‑12 one‑time redirections and loans from the
Immediate and Critical Needs Account.
19. Yolo County—New Woodland Courthouse. The amount of $9,639,000 is provided
for the working drawings phase to construct a new courthouse in Yolo County.
24 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
The new 163,066 gsf building will house 14 courtrooms in the city of Woodland.
Total estimated project cost is $167,374,000 without financing: $9,094,000 for
acquisition, $7,371,000 for preliminary plans, $9,639,000 for working drawings,
and $141,270,000 (CCCI 5264) for construction. The construction amount includes
$124,650,000 for the construction contract, $6,233,000 for contingency, $2,505,000
for architectural and engineering fees, and $7,882,000 for other project costs.
Acquisition was completed in June 2011 and preliminary plans are scheduled
to be completed by January 2012. Construction will begin in April 2013 and be
completed by February 2015. The current schedule is under review and may
be amended as a result of the 2011‑12 one‑time redirections and loans from the
Immediate and Critical Needs Account.
Item 2740‑301‑0044—Department of Motor Vehicles—Capital Outlay
1. Grass Valley Field Office Replacement. The amount of $648,000 (CCCI 5591)
is provided for the preliminary plans phase of this project to replace the Grass
Valley field office. The scope includes the demolition of the old facility and
construction of a new 7,583 square foot Department of Motor Vehicles customer
service field office, with adequate public parking, a carport with a vehicle staging
area, and a motorcycle testing area. The total project cost is estimated to be
$7,831,000 which includes $648,000 for preliminary plans, $531,000 for working
drawings, and $6,652,000 for construction. The amount for construction includes
$5,210,000 for construction contracts, $260,500 for contingency, and $1,181,500
for project administration. Preliminary plans are scheduled to be completed
in August 2012, working drawings completed in July 2013, and construction
completed in July 2015.
Item 3540‑301‑0668—Department of Forestry and Fire Protection—
Capital Outlay
1. Shasta-Trinity Unit Headquarters—Relocate Facility. The budget provides
$200,000 to secure a purchase option agreement to relocate the Shasta‑Trinity
Unit Headquarters in Shasta County. The purchase option includes a 33,073 gsf
building on 6.63 acres of land to house the Shasta‑Trinity Unit Headquarters. The
cost includes the appraisal and appraisal review, preparation and negotiation of
the option agreement, and Public Works Board approval.
2. Blanchard Fire Station—Acquisition. The budget provides $300,000 for the
acquisition of the Blanchard Fire Station’s two‑acre leasehold and an additional
adjacent eight acres of vacant land. The current owner is unwilling to renew the
current lease and has listed the property for sale at $200,000.
LEGISLATIVE ANALYST’S OFFICE 25
Supplemental Report of the 2011-12 Budget Package
Item 3790‑301‑0005—Department of Parks and Recreation—
Capital Outlay
1. Statewide, State Park System Minor Projects. The budget provides $508,000 for
construction to provide enhancements or improvements to address critical issues
at Emerald Bay State Park. Total estimated project cost is $508,000.
Item 3790‑301‑0263—Department of Parks and Recreation—
Capital Outlay
1. Heber Dunes State Vehicular Recreation Area—Initial Development. The budget
provides $5,339,000 for construction and equipment for the initial development
of Heber Dunes State Vehicular Recreation Area to include new administrative,
maintenance, and recreational facilities. Total project cost is $5,923,000 (CCCI 5194)
including preliminary plans ($223,000), working drawings ($361,000), construction
($5,142,000), and equipment ($197,000). The amount for construction includes
$4,591,000 for construction contracts, $230,000 for contingency, $277,000 for project
administration, and $44,000 for agency‑retained items. Construction is scheduled to
begin August 2011 and be completed June 2012.
2. Statewide, Off-Highway Vehicle Minor Capital Outlay. The budget provides
$9,012,000 for construction projects that will enable or enhance program delivery at
various state vehicle recreation areas. Total project cost is $9,012,000 (CCCI 5270).
3. Statewide, Opportunity Purchase Pre-Budget Schematics. The budget provides
$250,000 for purchase of real property in‑holdings, preparation of appraisals,
cost estimates, and schematics for future acquisition and development projects
supported by the Off‑Highway Motor Vehicle Recreation Program.
4. Hollister Hills State Vehicular Recreation Area—Infrastructure and
Rehabilitation. The budget provides $416,000 for working drawings to provide
improvements to basic infrastructure and visitor facilities. Total project cost is
$6,504,000 (CCCI 5296) including preliminary plans ($153,000), working drawings
($416,000), and construction ($5,935,000). The amount for construction includes
$5,267,000 for construction contracts, $369,000 for contingency, $263,000 for project
administration, and $36,000 for agency‑retained items. Working drawings are
scheduled to begin July 2011 and be completed July 2012.
5. Carnegie State Vehicular Recreation Area—Road Reconstruction. The budget
provides $6,617,000 for construction to reconstruct approximately eight miles of
unpaved roads to meet current emergency access, Clean Water, and public use
standards. Total project cost is $7,084,000 (CCCI 5296) including preliminary
26 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
plans ($227,000), working drawings ($240,000), and construction ($6,617,000).
The amount for construction includes $5,813,000 for construction contracts,
$408,000 for contingency, $389,000 for project administration, and $7,000 for
agency retained items. Construction is scheduled to begin February 2012 and be
completed April 2013.
Item 3790‑301‑6051—Department of Parks and Recreation—
Capital Outlay
1. Statewide, Volunteer Enhancement Program. The budget provides $638,000 to
fund the construction and/or rehabilitation of volunteer facilities and camp host
sites within the state park system. Total estimated project cost is $638,000.
2. Statewide, Recreational Trails Minor Projects. The budget provides $380,000
to fund minor improvement projects including rerouting trails, improving safety,
and completing environmental work within state parks property. Total estimated
project cost is $380,000.
3. Statewide, Budget Development. The budget provides $150,000 for study to fund
initial investigations and studies for future projects, preparation of budget cost
estimates, schematic drawings, and other information for projects, and to contract
with other state agencies and/or consultants to provide various surveys necessary
in advance of project design. Total project cost is $150,000.
4. Donner Memorial State Park—Enhance Museum Exhibits. The budget provides
$169,000 for preliminary plans to provide durable, long‑lived interpretive,
educational exhibit enhancements for the new museum building. Total estimated
project cost is $1,050,000 including preliminary plans ($169,000), working
drawings ($463,000), and construction ($418,000). The amount for construction
includes $418,000 for agency retained items. Preliminary plans are scheduled to
begin July 2011 and be completed May 2012.
5. Marshall Gold Discovery State Historic Park—Park Improvements. The budget
provides $1,128,000 for working drawings and construction to make various
improvements to enhance the visitor’s educational and interpretive experience.
Total estimated project cost is $4,466,000 (CCCI 4871) including preliminary plans
($340,000), working drawings ($735,000), and construction ($3,391,000). The
amount for construction includes $2,275,000 for construction contracts, $159,000 for
contingency, $261,000 for project administration, and $696,000 for agency‑retained
items. Working drawings are scheduled to begin July 2011 and be completed
April 2012. Construction is scheduled to begin August 2012 and be completed
August 2013.
LEGISLATIVE ANALYST’S OFFICE 27
Supplemental Report of the 2011-12 Budget Package
Item 3860‑301‑6052—Department of Water Resources—Capital Outlay
1. Frazier Creek/Strathmore Creek—Feasibility Study. The budget provides
$225,000 from Section 5096.821(a) of Proposition 1E and $65,000 reimbursement
authority to fund the non‑federal share of a feasibility study of the Frazier and
Strathmore Creeks to improve the level of flood protection for the community of
Strathmore, State Route 28, State Route 65, bridges, railroads, and surrounding
agricultural lands.
2. White River/Deer Creek—Feasibility Study. The budget provides $237,000 from
Section 5096.821(a) of Proposition 1E and $65,000 reimbursement authority to
fund the non‑federal share of a feasibility study of the Whiter River and Deer
Creek to improve the level of flood protection for the community of Earlimart,
State Route 99, railroads, the federal aqueduct, and 300 square miles of farmland
in Tulare County.
3. Merced County Streams Project, Bear Creek Unit. The budget provides $426,000
from Section 5096.821(b) of Proposition 1E and $250,000 reimbursement authority
for the non‑federal share of the General Reevaluation Report, which will identify
alternatives and improvements to bring the level of protection for the city of
Merced up to at least a 200‑year level.
4. Lower San Joaquin River Regional Project. The budget provides $1,280,000 from
Section 5096.821(b) of Proposition 1E and $1,000,000 reimbursement authority
for the non‑federal share of the Lower San Joaquin River Feasibility Study to
indentify a feasible project for flood damage reduction along the Lower
San Joaquin River.
Item 3860‑301‑6052/Reimbursements—
Department of Water Resources—Capital Outlay
1. American River Flood Control Project—Common Elements. The budget
provides $6,822,000 from Section 5096.821(b) of Proposition 1E and $2,835,000
reimbursement authority to continue the reevaluation, design, and construction of
the American River (Common Elements) Project.
2. West Sacramento Project. The budget provides $2,242,000 from Section
5096.821(b) of Proposition 1E and $700,000 reimbursement authority to fund the
non‑federal share of design and construction for the north slip repair sites of the
West Sacramento Project.
28 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
3. West Sacramento Project (General Reevaluation Report). The budget provides
$1,120,000 from Section 5096.821(b) of Proposition 1E and $875,000 reimbursement
authority to fund the non‑federal share of development of the West Sacramento
Project General Reevaluation Report.
4. Mid-Valley Area Levee Reconstruction Project. The budget provides $2,855,000
from Section 5096.821(b) of Proposition 1E and $1,095,000 reimbursement
authority to fund the non‑federal share of the Mid‑Valley Area Levee
Reconstruction Project, which restores levee sections of the Sacramento River
Flood Control Project in reclamation districts between the Tisdale Bypass and the
Sacramento Bypass to original design standards.
5. Yuba River Basin Project. The budget provides $583,000 from Section 5096.821(b)
of Proposition 1E and $145,000 Reimbursement Authority for completion of the
General Reevaluation Report of the feasible flood protection alternatives which fit
into the State Plan of Flood Control and provide at least 200‑year flood protection.
6. Marysville Ring Levee Reconstruction Project. The budget provides $1,457,000
from Section 5096.821(b) of Proposition 1E and $575,000 reimbursement authority
for the design and construction of Phases 2 through 4.
7. South Sacramento County Streams. The budget provides $3,766,000 from
Section 5096.821(b) of Proposition 1E and $1,614,000 reimbursement authority to
continue construction of the South Sacramento County Streams Project, which
will protect the City of Sacramento from high‑water events in the Delta and
from flooding associated with Morrison Creek, Florin Creek, Elder Creek, and
Unionhouse Creek.
8. Sutter County Feasibility Study. The budget provides $780,000 from
Section 5096.821(b) of Proposition 1E and $500,000 reimbursement authority to
continue the Sutter County Feasibility Study, which will investigate measures to
improve the level of flood protection for the Yuba City Basin from a 100‑year event
to the maximum level feasible.
9. Rock Creek/Keefer Slough—Feasibility Study. The budget provides $225,000
from Section 5096.821(a) of Proposition 1E and $65,000 reimbursement authority
to fund the non‑federal share of a feasibility study of the Rock Creek and Keefer
Slough in order to improve the level of flood protection for the communities of
Chico and Nord, State Route 99, Route 32, and surrounding agricultural land.
10. Folsom Dam Modifications Project. The budget provides $27,408,000 from
Section 5096.821(b) of Proposition 1E and $11,655,000 reimbursement authority to
LEGISLATIVE ANALYST’S OFFICE 29
Supplemental Report of the 2011-12 Budget Package
continue design and construction of the Folsom Dam Modifications Project, which
will enhance the flood release capability of Folsom Dam and increase the level of
protection from flooding to Sacramento.
Item 3860‑302‑6052—Department of Water Resources—Capital Outlay
1. Systemwide Levee Evaluations and Repairs. The budget provides $38,000,000
from Chapter 3, Section 5096.821 of Proposition 1E in order to continue the repair of
known levee defects and erosion sites and new sites where deficiencies are found.
2. Feather River Early Implementation Project. The budget provides $11,150,000
from Section 5096.821(b) of Proposition 1E for state cost share funding for
construction of the Sutter Butte Flood Control Agency’s Feather River Levee
Strengthening Early Implementation Project, which will restore 100‑year flood
protection for significant portions of the Sutter‑Yuba City Basin and will constitute a
first phase in achieving the Area Plan objective of 200‑year flood projection by 2025.
Item 4300‑301‑0001—Department of Developmental Services—
Capital Outlay
1. Developmental Centers—Automatic Fire Sprinkler Systems, Preliminary
Plans, and Working Drawings. The amount of $2,043,000 is provided for
preliminary plans and working drawings to design and install automatic fire
sprinkler systems in 13 buildings providing Nursing and General Acute Care
services at three developmental centers (Fairview, Porterville, and Sonoma). The
project cost is $13,426,000 (CCCI 5270), including $1,032,000 for preliminary plans,
$1,011,000 for working drawings, and $11,383,000 for construction. The amount
of construction includes $7,997,000 for the construction contract, $559,800 for
contingency, $2,219,200 for architectural and engineering fees, and $2,650,000 for
other project costs. The project is to begin preliminary plans July 2011, working
drawings are scheduled to begin December 2011, and construction should start
October 2012, with project completion August 2013.
Item 4440‑301‑0001—Department of Mental Health—Capital Outlay
1. Replace Fire Alarm Systems—Napa State Hospital. The amount of $2,210,000
is provided for preliminary plans and working drawings to replace existing fire
alarm systems in six buildings (numbers 168, 195, 196, 197, 198, and 199). The total
estimated project cost is $17,559,000 (CCCI 5265), including $1,054,000 for preliminary
plans, $1,156,000 for working drawings, and $15,349,000 for construction. The
amount of construction includes $10,575,000 for the construction contract, $740,000
for contingency, $2,033,700 for architectural and engineering fees, and $2,000,000
for other project costs. The project is to begin preliminary plans July 2011, working
30 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
drawings are scheduled to begin December 2011, and construction is scheduled to
start October 2012, with project completion August 2013.
2. Fire Sprinklers for Skilled Nursing Facility (SNF) Buildings at Metropolitan
State Hospital and Napa State Hospital. The amount of $2,092,000 is provided
for preliminary plans and working drawings for installation of fire sprinkler
systems in existing buildings that contain SNF programs at Metropolitan State
Hospital and Napa State Hospital. The project cost is $16,208,000 (CCCI 5596),
including $1,008,000 for preliminary plans, $1,084,000 for working drawings, and
$14,116,000 for construction. The amount of construction includes $8,160,000 for
the construction contract, $572,000 for contingency, $1,029,000 for architectural
and engineering fees, and $4,355,000 for other project costs. The project is to begin
preliminary plans July 2011, working drawings are scheduled to begin
December 2011, and construction is scheduled to start October 2012, with project
completion August 2013.
Item 6610‑301‑0668—California State University—Capital Outlay
1. East Bay—Warren Hall Replacement Building. The amount of $48,975,000 is
provided for preliminary plans ($1,247,000), working drawings ($1,417,000), and
construction ($46,311,000). The total estimated project cost is $49,975,000 (CCCI
5732) including future costs of $1,000,000 for equipment (EPI 3016) for a 40,000
assignable square feet (asf)/67,000 gross square feet (gsf) replacement facility (#29)
which will accommodate 113 administrative and faculty offices. This project will
also demolish the E. Guy Warren Hall Building 77,596 ASF/114,000 gsf (#13), and
a two‑story bridge element that spans over West Loop Road and connects to the
Library Building (#12). The total area to be demolished is 84,800 ASF/141,500 gsf.
The project will also relocate the basement level Warren Hall telecommunications
switch to the Student Services Replacement Building. Construction costs include
$40,972,000 for construction and demolition contracts, $1,860,000 for contingency,
and $2,896,000 for project administration. Preliminary plans were scheduled to
begin in July 2011 and to be completed by December 2011. Working drawings are
scheduled to begin December 2011 and to be completed by July 2012. Construction
is scheduled to begin January 2013 and to be completed by April 2015.
Item 6640‑302‑6048—University of California—Capital Outlay
1. Irvine Campus—Business Unit 2. The amount of $39,595,000 is provided for
preliminary plans ($836,000), working drawings ($1,846,000), and construction
($36,913,000) for a new building for the Paul Merage School of Business. This
project is expected to use the design‑build delivery method to build instruction,
research, and office space. The estimated total project cost is $48,371,000
(CCCI 5732), including non‑state costs of $280,000 for preliminary plans, $95,000
LEGISLATIVE ANALYST’S OFFICE 31
Supplemental Report of the 2011-12 Budget Package
for working drawings, $4,281,000 for construction, and future state costs of
$1,030,000 and future non‑state costs of $3,090,000 for equipment. The amount
for construction includes $37,072,000 for construction contracts, $1,483,000 for
contingency, and $2,639,000 for project administration. The building construction
cost is $41,194,000. Preliminary plans are scheduled to begin in August 2011 and
be completed by November 2011. Working drawings are scheduled to begin in
December 2011 and be completed by May 2012. Construction is scheduled to
begin by May 2012 and be completed by October 2014.
Item 6870‑301‑6049—California Community Colleges—Capital Outlay
1. Coast Community College District, Orange Coast College—Music Buildings
Modernization. The amount of $3,489,000 is provided for the construction phase to
modernization two buildings, Music Building #3 and #4. The modernized buildings
will have 11,886 assignable square feet (asf) comprised of 8,700 asf lab space, 752 asf
office space, 726 asf tutorial space, and 1,708 asf of other music support space. Total
estimated project cost is $8,008,000 (CCCI 5394 and EPI 3016) including preliminary
plans ($369,000; $185,000 state funds and $184,000 non‑state funds), working
drawings ($315,000; $158,000 state funds and $157,000 non‑state funds), construction
($6,979,000; $3,489,000 state funds and $3,490,000 non‑state funds), and equipment
($345,000 non‑state funds). The amount for construction includes $428,000 for
contingency, $435,000 for project administration, and $6,116,000 for construction
contracts. Working drawings are complete. Construction is scheduled to start
December 2011 and be completed by February 2013.
2. San Francisco Community College District, City College of San Francisco—
Performing Arts Complex. The amount of $38,274,000 is provided for the
construction and equipment phases of the Performing Arts Complex project. The
project will erect a 59,354 asf performing arts instructional facility consisting of
2,058 asf lecture, 21,382 asf laboratory, 3,204 asf office, 2,212 asf library, 29,872 asf
theatre, and 625 asf other space. Total estimated project cost is $151,212,000
(CCCI 5394 and EPI 3016) including preliminary plans ($5,170,000 non‑state
funds), working drawings ($5,848,000 non‑state funds), construction ($133,647,000;
$35,156,000 state funds and $98,491,000 non‑state funds), and equipment ($6,547,000;
$3,118,000 state funds and $3,429,000 non‑state funds). The amount for construction
includes $6,086,000 for contingency, $5,849,000 for project administration,
and $121,712,000 for construction contracts. Working drawings are complete.
Construction is scheduled to start January 2012 and be completed by January 2014.
3. Santa Clarita Community College District, College of the Canyons—
Administration and Student Services Building. The amount of $6,855,000 is
provided for the construction and equipment phases for the project. The project
will renovate the 20,544 asf Administration/Student Services Building consisting
32 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2011-12 Budget Package
of 1,130 asf laboratory space, 13,825 asf office space, and 5,589 asf other space. Total
estimated project cost is $14,007,000 (CCCI 5394 and EPI 3016) including preliminary
plans ($455,000; $143,000 state funds and $312,000 non‑state funds), working
drawings ($494,000; $93,000 state funds and $401,000 non‑state funds), construction
($12,501,000; $6,576,000 state funds and $5,925,000 non‑state funds), and equipment
($557,000; $279,000 state funds and $278,000 non‑state funds). The amount for
construction includes $554,000 for contingency, $669,000 for project administration,
and $11,278,000 for construction contracts. Working drawings are complete.
Construction is scheduled to start July 2011 and be completed by August 2012.
LEGISLATIVE ANALYST’S OFFICE 33