LAO
Maximizing State Benefits from Public-Private Partnerships
Read the report at Legislative Analyst's Office ↗
Maximizing State Benefits
From Public-Private Partnerships
MAC TAylor • l e g i s l A T i v e A nA l y s T • nove MBer 8, 2012
An LAO RepOR t
2 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
ExEcutivE SuMMary
In recent years, the state has partnered with the private sector to finance, design, construct,
operate, and maintain two state infrastructure projects—the Presidio Parkway transportation
project in San Francisco and the new courthouse in Long Beach. Both the California Department of
Transportation (Caltrans) and the Administrative Office of the Courts (AOC) entered into a public-
private partnership (P3) for these projects in order to achieve benefits that they might not have
obtained under a more traditional procurement approach (such as design-bid-build). These potential
benefits include greater price and schedule certainty and the transfer of various project risks to a
private partner.
Our analysis, however, generally indicates that the P3 practices of Caltrans and AOC are
not necessarily aligned with the P3 best practices identified in the research. For example, these
departments did not use clear P3 processes and appear to have selected projects not well suited for a
P3 procurement. In addition, we find that the analyses done to compare project costs under different
procurement options were based on several assumptions that are subject to significant uncertainty
and interpretation, and tended to favor the selection of a P3 approach.
Based on our review and findings, we have identified several opportunities for the state to
further maximize its benefits when deciding to procure a state infrastructure project as a P3.
Specifically, we recommend that the Legislature:
• Specify P3 project selection criteria in state law in order to provide for greater
consistency across departments in terms of how P3s are selected.
• Require a comparative analysis of a range of procurement options (including
design-bid-build, design-build, and P3) for all potential P3 infrastructure projects
in order better determine which procurement option would most effectively
benefit the state, as well as allow the state to better balance the potential benefits of
increased private sector involvement with the potential risks unique to each project.
• Require the existing Public Infrastructure Advisory Commission (PIAC) to approve
state P3 projects in order to improve the consistency of the state’s P3 approval
process.
• Require PIAC to (1) have a broad mix of expertise related to P3 and state finance
and procurement, (2) develop additional best practices for the state’s use of P3s, and
(3) evaluate other state departments to determine if they would benefit by having P3
authority.
www.lao.ca.gov Legislative Analyst’s Office 3
An LAO RepOR t
introduction
A partnership between the state and the Francisco (also known as Doyle Drive) and to
private sector is sometimes used to finance, build and maintain a new courthouse in Long
design, construct, operate, and maintain state Beach. Each of these agreements is for a period
infrastructure projects (such as highways, mass of about 30 years. The combined estimated cost
transportation systems, and state buildings). Such to the state for both of these projects is about
a P3 requires the state and the private sector to $3.4 billion. Given their significant cost and
collaborate when making decisions about a project. the limited experience the state has had in such
By bringing external resources and specialized partnerships, we identify in this report best
expertise to a project, the state is expected to practices for the state to follow when using P3s
achieve certain benefits from a P3 that typically and present recommendations for maximizing
are not achievable when using a more traditional, the benefits to the state. In preparing this report,
public sector procurement approach. we met with representatives from various state
In recent years, California has entered into P3s departments about their experiences with P3s, as
with private partners for two state infrastructure well as numerous P3 experts. We also reviewed the
projects. Specifically, to build and operate the literature regarding best practices for implementing
Presidio Parkway transportation project in San such partnerships.
Background
State Procures infrastructure of multiple reviews and approvals as a project’s
Projects in various Ways development moves from concept to environmental
review and preliminary engineering, and then to
State law specifies the processes for reviewing
design and construction.
and approving proposed state infrastructure
State law specifies three general types of
projects. In most instances, such as for court
procurement approaches—design-bid-build,
facilities and state office buildings, the Legislature
design-build, and P3—that state departments can
must approve and appropriate funds for a state
use to deliver infrastructure projects that have
project. (They also must receive approval from the
been approved for construction. As summarized
State Public Works Board at various subsequent
in Figure 1, each of these procurement approaches
stages.) However, the California Transportation
involves varying ways of contracting with the
Commission (CTC) approves most state projects
private sector for a project. We discuss each
related to transportation. The review and approval
approach in more detail below.
process for state projects generally involves
Design-Bid-Build. State departments can use
determining (1) the need for the project, (2) how
a design-bid-build approach to procure all types
the project fits into existing infrastructure systems,
and sizes of infrastructure. Under this approach,
(3) the project’s priority relative to other state
the work for each stage of a project is performed
infrastructure projects, and (4) how the project
separately. For example, a state department will
will be funded. This process typically consists
4 Legislative Analyst’s Office www.lao.ca.gov
Graphic Sign Off
Secretary
Analyst
Director
Deputy
An LAO RepOR t
Figure 1
State Procurement Approaches
Design-Bid-Build Design-Build Public-Private Partnerships
Environmental Environmental Environmental Environmental
Review Review Review Review
Financing Financing
(if necessary) (if necessary) Financing Financing
Design Design Design Design
Construction Construction Construction Construction
Operation Operation Operation Operation
Maintenance Maintenance Maintenance Maintenance
generally first award an architectural/engineering contracts with a private general contractor to both
contract to design the project based on subjective design and build the infrastructure project. The
criteria of qualifications and experience of the department does not separately contract with an
architect/engineer. In some cases, however, architect/engineer for design. Rather, the general
state staff may design the project. After detailed contractor is responsible for subcontracting with
project plans and drawings are completed, the other entities for design and various construction
department then selects a contractor to perform work. The state awards a design-build contract
the construction work. Construction contracts are through a competitive bidding process that
awarded objectAivelyR baTsedW on cOompRetitKive b#idd1ing1, 06ev2alu3ate/s Ffacitogrs suucrh aes p1ric.ea, deisign features,
with the contract going to the qualified bidder construction schedule, and community or
who submits the lowest price. Once construction is environmental outcomes. Under design-build,
completed, the state department is responsible for the state maintains responsibility for financing,
operating and maintaining the facility. The state operating, and maintaining the project.
pays for the cost of design-bid-build projects either Alternatively, another type of design-build
up front with state funds or over time by selling involves the state transferring design and
general obligation bonds or lease-revenue bonds. construction risks to a specialized construction
Design-Build. Under existing state law, certain manager, rather than a general contractor. This
departments can use design-build procurement. approach is commonly referred to as “construction
With design-build, the department typically manager at risk procurement.” With construction
www.lao.ca.gov Legislative Analyst’s Office 5
An LAO RepOR t
manager at risk, the state awards a contract based Under a P3 approach, the state can transfer a
on a fee. The construction manager designs the significant amount of responsibility associated with a
project and solicits bids from subcontractors and project to the private sector. For example, the private
suppliers. The sum of these bids, along with a partner will generally make design and construction
surcharge, determines the total price the state pays decisions and be responsible for paying the costs to
for the project. resolve any construction issues in order to ensure
P3s. Current state law authorizes three state that the project is completed on time. In addition,
departments—Caltrans, AOC, and the High-Speed the partner will often be required to finance the
Rail Authority (HSRA)—to use some form of a project, which generally includes the costs of design
P3. While there can be varying degrees of P3s, the and construction staff, materials, and construction
type of P3 often discussed and most recently used equipment. However, in order for a private partner
in California is when a single contract is entered to be willing to finance these costs, the contract
into with a private partner (often a consortium of must specify a mechanism for repaying the partner.
several companies) for the design, construction, In many cases, this involves a revenue source
finance, operation, and maintenance of an created by the project (such as a toll or user fee on
infrastructure facility. For the purpose of this the infrastructure facility), with the private partner
report, we generally define a P3 as the contracting taking on the risk that the projected revenues will
with the private sector to design-build-finance- materialize at the level anticipated. Alternatively,
operate-maintain an infrastructure project. (As the state can commit to making annual payments
we discuss in the nearby box, the state can also to the partner from an identified funding source,
enter into partnerships with other public entities, such as tax revenues. Since it can take many years
such as counties, for the procurement of state for a revenue source (such as a toll on a road) to pay
infrastructure.) off the private financings, the terms of P3 contracts
generally range between 25 years to 100 years.
State Partnerships With other Public Entities
In addition to the private sector, the state can utilize other public entities (such as a county
or other public authorities) for the design, construction, operation, and maintenance of an
infrastructure project. In such cases, however, these entities typically subcontract (either through a
single contract or multiple contracts) with the private sector to perform much of the actual work on
a project. For example, the public partner could finance a project with municipal financing, contract
with a private company for design and construction work, and have separate contracts with other
companies to maintain and operate the infrastructure facility.
An example of a public-public partnership project is “The Toll Roads” in Southern California—a
50 mile network of tolled state highways in southern Orange County built by the Transportation
Corridor Agencies (TCAs), which are led by locally elected officials. In 1987, the Legislature
authorized the TCAs to design, construct, finance, operate, and maintain a portion of the state’s
highways and to fund the cost of the project with tolls. The TCAs contracted with private companies
to perform most of the work on the project.
6 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
The P3 procurement approach is typically follow-up legislation, Caltrans built ten miles of
more complex than design-bid-build and design- tolled express lanes in the median of the existing
build. For instance, under a P3 approach, the state State Route (SR) 91 in Orange County. In addition,
must first evaluate a pool of potential bidders to the department built SR 125 in San Diego County
determine if they have the qualifications necessary that connects the area near the Otay Mesa border
to design, build, finance, operate, and maintain crossing with the state highway system. For each
the infrastructure facility. Then, qualified bidders project, Caltrans used a single contract with a
submit proposals that the state evaluates in order private partner to design, construct, finance,
to select a preferred bidder. A P3 contract is often operate, and maintain the facility. (We discuss
awarded to the bidder deemed to provide the best these two projects in more detail later in this
value. report.)
In 2009, Caltrans’ authority to enter into P3
three State departments authorized
agreements was expanded. Specifically, Chapter 2,
to use P3s for certain Projects
Statutes of 2009 (SB 2X 4, Cogdill), authorizes
As shown in Figure 2, existing state law Caltrans and regional transportation agencies
authorizes the use of P3s for certain transportation (such as the Los Angeles County Metropolitan
and court construction projects. (State law also Transportation Authority) to enter into an
authorizes certain local governments to use P3s for unlimited number of P3 agreements for a broad
local infrastructure projects.) Below, we discuss in range of highway, road, and transit projects through
more detail the specific P3 authority provided to December 31, 2016. However, the legislation specifies
state departments. that such P3 projects must achieve one or more
Caltrans. Chapter 107, Statutes of 1989 objectives as determined by the CTC, which is
(AB 680, Baker), authorized Caltrans to enter into responsible for programming and allocating funds
P3 agreements for up to four projects. Under this for the construction of highway, rail, and transit
authorization, as well as that provided in related improvements. These objectives include:
Figure 2
Summary of State Public-Private Partnership (P3) Authority
State Type of Projects
Department Infrastructure State Law Brief Description To Date
Caltrans Highways Chapter 107, Statutes of Allowed Caltrans to enter State Route (SR) 91
1989 (AB 680, Baker) into up to four P3s. and SR 125
Caltrans and regional Highways, local Chapter 2, Statutes of Allows Caltrans and regional Presidio Parkway
transportation agencies roads, and transit 2009 (SB 2X 4, Cogdill)a agencies to enter into an
unlimited number of P3s
through 2016.
High-Speed Rail Authority High-speed rail Chapter 796, Statutes of Allows HSRA to enter into High-speed train
(HSRA) 1996 (SB 1420, Kopp) P3 contracts for the system
proposed rail system.
Administrative Office of the Court facilities Chapter 176, Statutes of Establishes process for Long Beach
Courts (AOC) 2007 (SB 82, Committee review of AOC P3 projects. Courthouse
on Budget and Fiscal
Review)
a
Replaced the P3 authority previously provided to Caltrans under Chapter 107.
www.lao.ca.gov Legislative Analyst’s Office 7
An LAO RepOR t
• Improve travel times or reduce vehicle Judicial Council and AOC. Under current
hours of delay. law, the judicial branch is authorized to use
P3s. In addition, state law requires the Judicial
• Improve transportation operation or safety.
Council (the policy making body for the judicial
branch) and their staff in the AOC to develop
• Provide quantifiable air quality benefits.
performance standards to facilitate the review of
• Meet a forecasted demand of P3s and requires the Department of Finance (DOF)
transportation. to review projects that include a P3 component.
The legislation also specifies that AOC may only
In addition, the above agreements are subject to
proceed with a P3 if the Legislature does not object
a 60-day review by the Legislature and PIAC before
to the performance standards adopted for the
Caltrans can sign them. The PIAC is an advisory
project.
commission created by Chapter 2 and chaired by
The 2007-08 Budget Act directed AOC to
the Secretary of the Business, Transportation, and
gather information regarding the possible use
Housing (BT&H) Agency. Specifically, PIAC is
of a P3 for the replacement of the Long Beach
charged with assembling research, best practices,
courthouse. In December 2010, AOC entered
and lessons learned from transportation P3s
into a P3 that requires a private developer to
around the world. The commission can, upon
finance, design, build, operate, and maintain
request, assist Caltrans and regional transportation
the Long Beach courthouse over a 35-year
agencies with P3 project selection, evaluation,
period in exchange for payments from the state
procurement, and implementation. Currently,
totaling $2.3 billion. At this time, the Long Beach
PIAC consists of about 20 volunteer members and
courthouse is the only project that the AOC has
is staffed within existing BT&H Agency resources.
procured using a P3.
In January 2011, Caltrans entered into its
The HSRA. Chapter 796, Statutes of 1996
first P3 under Chapter 2 for the Presidio Parkway
(SB 1420, Kopp), created the HSRA and authorized
project. This particular P3 requires the private
it to use P3 procurement for the development of
partner to complete the second phase of the design
a high-speed train system connecting northern
and reconstruction of the southern approach to the
and southern California. However, state law does
Golden Gate Bridge and to operate and maintain
not establish a specific process for reviewing or
the roadway for 30 years. In exchange, the state
approving P3s for HSRA. State law requires capital
will make payments estimated to total roughly
expenditures by HSRA to be approved by the
$1.1 billion to the private partner over the life of the
Legislature. Based on the authority’s 2012 business
contract.
plan, the HSRA would not award its first P3
contract until 2023.
BEnEFitS and LiMitationS oF P3S
Government entities typically use P3s to (such as design-bid-build). However, P3s can also
achieve benefits that they may not be able to obtain introduce new limitations and costs as summarized
under a more traditional procurement approach in Figure 3 and described in detail below.
8 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
Potential P3 Benefits
Figure 3
Transfers Project
Summary of Benefits and
Risks to Private Partner.
Limitations of Public-Private Partnerships
The P3s can transfer risks
associated with a project
9
from a government entity Potential Benefits
to a private partner. • Transfer project risks to private partner.
• Greater price and schedule certainty.
Figure 4 (see next
• More innovative design and construction techniques.
page) summarizes the
• “Free up” public funds for other purposes.
major risks that could
• Quicker access to financing for projects.
potentially be transferred,
• Higher lever of maintenance.
such as those related to • Keep project debt off government’s books.
financing, operation, 9
Potential Limitations
and maintenance. As
• Increased financing costs.
indicated in the figure,
• Greater possibility for unforeseen challenges.
the most significant risks • Limits government’s flexibility.
are associated with the • New risks from complex procurement process.
design and construction • Fewer bidders.
of a project. For example,
under a P3 approach, the Administration (FHWA), governments around
private developer would bear the risks and costs the world reported that P3s can provide better
if the design of the project were changed to fit price and schedule certainty for the design and
certain site conditions (such as soil quality or the construction of a project compared to a more
discovery of archeological artifacts). Similarly, the traditional procurement approach (such as design-
private partner would be responsible for project bid-build). In part, this is because P3s allow a
cost overruns, which can be very expensive. The government entity to share certain risks with a
transfer of this risk could reduce or eliminate the private developer who has more experience with
need for additional public funds to complete a a particular type of project and has developed
project. Moreover, the partner would bear the risk strategies to mitigate potential cost increases that
if the actual revenue collected from any tolls or user could result from such risks. The government
fees are less than projected, which depending on can also achieve greater price certainty from
the project, can be significant. In order to ensure P3s because, as is the case with design-build and
adequate compensation, private developers attempt construction manager at risk contracts, the contacts
to estimate the anticipated costs of resolving issues often have a maximum price. This means that the
on the risks they assume and factor these costs into private partner must pay for any cost increases
their bid. However, in some cases, the developer above the agreed upon price. In addition, the
may be better equipped to manage certain risks at government typically sets up a streamlined process
a lower cost than if the government retained all of to review the design and construction decisions
the project risks. made by the partner, which can help prevent delays
Greater Price and Schedule Certainty. Based in the project schedule. Moreover, P3s that include
on a survey conducted by the Federal Highway financing can incentivize the partner to complete
www.lao.ca.gov Legislative Analyst’s Office 9
An LAO RepOR t
the construction of
Figure 4
other infrastructure
Major Risks Transferred in
in the near-term and,
Public-Private Partnership Agreements
thus, provide the public
with access to improved
9
Financing Risks
infrastructure sooner than
• Changes in financing costs.
planned. In addition, the
• Estimated and actual inflation.
9 developer’s financing can
Design and Construction Risks
sometimes provide more
• Interface between design and construction.
advantageous repayment
• Discovery of endangered species.
• Discovery of archeological, paleontological, or cultural resources. terms than a government
• Discovery of hazardous materials.
might typically obtain
• Unknown utility lines.
under a more traditional
• Delays in getting permits approved.
9 public financing approach.
Operation and Maintenance Risks
For example, if repayment
• Facility requires more maintenance than planned.
were extended over a
• Facility is more costly to operate than planned.
• Standards or requirements imposed in the future. longer period of time than
9
the government typically
Revenue Risks
• Usage of the facility is lower than predicted. has to repay borrowed
• Public less willing to pay user fees than projected. funds, it could reduce
the amount that must be
the project on time and receive the necessary
repaid each year. Such
funding (such as payments from the government or
freed-up public funds could then be allocated for
revenues from project user fees) to repay the private
other purposes.
loans taken out to finance the project.
Quicker Access to Financing for Projects. In
More Innovative Design and Construction
addition, by making a private developer responsible
Techniques. Experts in P3s generally believe that
for financing a particular project, a government
the private sector is often better able to develop
might be able to access financing in cases where
innovative project designs and construction
it does not yet have the authority to borrow. For
techniques than government entities. In part,
example, California’s constitution requires voter
this may be due to the specialized expertise that
approval prior to selling certain types of bonds
a private partner can bring to a project. Greater
to finance infrastructure projects, which could
design and construction innovation could result
delay the state from accessing financing for certain
in a variety of potential benefits, including lower
projects. However, projects financed through a
project costs, a higher quality project, shorter
P3 would not require voter approval, potentially
construction schedules, and enhanced project
allowing some projects to start construction sooner.
features.
Higher Level of Maintenance. Due to
“Free Up” Public Funds for Other Purposes.
insufficient funding for maintenance, as well as
In general, using a private developer’s access to
how existing maintenance funding is prioritized,
capital can free up government funds to advance
some governments currently do a poor job in
maintaining their infrastructure. For example, due
10 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
to a lack of regular maintenance, only 28 percent 1 percentage point higher on loans compared to
of California’s highways are in good condition. the governmental cost of borrowing. In times of
As a result, many highways require costly major limited access to financial markets (such as the
rehabilitation or replacement. Under a P3 approach, financial crisis of 2008), the cost difference between
a government could require the private partner private and public borrowing was 2 percentage to
to maintain the constructed infrastructure to 3 percentage points. In addition, private companies
specified standards. Essentially, this means that will often seek to earn a profit of roughly 10 percent
P3 facilities could remain in good condition to 25 percent when loaning funds to a government,
over longer periods of time, thus allowing the which can further increase P3 financing costs.
government to delay the cost of major rehabilitation Greater Possibility for Unforeseen Challenges.
or replacement. As previously discussed, in comparison to
Keeps Project Debts Off the Government’s design-bid-build and design-build contracts, P3
“Books.” Another benefit of P3 financing is that contracts cover a much longer time period and
the debt incurred by a private partner for a project scope of activities (such as maintenance of the
may not be counted as government debt. In other infrastructure facility). Thus, there is a greater
words, P3 financing may not appear as debt on possibility for unforeseen issues to arise under a
government balance sheets. According to recent P3 approach. Such issues could include disputes
studies by the FHWA and the United Nations regarding certain terms in the contract, as well
Economic Commission for Europe, this is one of as the private partner being acquired by another
the reasons why some countries in the European company or going out of business, effectively
Union have chosen to use P3s. While the benefit resulting in project schedule delays and additional
of debt not appearing on the government’s balance costs to the government.
sheet is probably more important to governments Limits Government’s Flexibility. The
subject to strict limitations on debt, it could also long-term nature of P3s can also “lock in”
improve the overall ability of some governments to certain government funding priorities based on
borrow funds for other purposes. However, since operational needs determined at the time the
California does not have such strict debt limitations contract is negotiated. This can make it difficult to
that restrict its options for financing infrastructure change funding allocations to reflect changes in
projects this benefit does not currently apply to the government priorities. For example, a P3 contract
state. may require litter and graffiti to be removed from
a highway within three days. Renegotiating the
Potential P3 Limitations
terms of this contract to use the funds designated
Increased Financing Costs. Financing a for prompt litter and graffiti removal to support
project through a P3 is likely to be more expensive another activity or project could be very difficult.
than the financing options typically used under In addition, by bundling multiple phases of a
the more traditional procurement approaches project into a single contract, P3s can make it more
(such as obtaining state and federal loans). This difficult for the government to change how a project
is because private companies typically pay higher is managed. For example, if the government wanted
interest rates than government entities to borrow to make changes to how a private partner handled
money. For example, a study of P3 projects in customer complaints and questions on a toll road,
Canada found that private partners typically pay it would likely need to propose amendments to the
www.lao.ca.gov Legislative Analyst’s Office 11
An LAO RepOR t
contract, which could increase the project’s overall Some Benefits achieved to date
cost.
In order to determine whether the state has
New Risks From Complex Procurement
achieved some of the intended benefits of P3s, we
Process. As discussed earlier, the procurement
reviewed the two completed P3 projects procured
process for P3s is more complex than the
by the state—SR 91 Express Lanes and SR 125
procurement processes traditionally used for
Tollway. At the time of this analysis, however,
state infrastructure projects (such as design-bid-
Caltrans was unable to provide us with the
build and design-build). In addition to a project’s
necessary data to evaluate whether the P3 projects
design, construction price, and schedule, under
completed by the state—SR 91 and SR 125—
P3 approach, the government entity must also
resulted in greater price and schedule certainty
evaluate proposals based on financing, operations,
than if the projects were procured under a more
and maintenance. In addition, P3 procurements
traditional approach. As a result, we reviewed
can also involve complex negotiations between
recent state projects that, while not considered
the government and the private developers who
P3s, transferred certain risks and responsibilities
bid on the project. As a result, P3s can require the
to the private sector. Specifically, we reviewed
government to perform new activities and take
those projects procured under design-build and
on certain risks that it may not be experienced at
construction manager at risk contracts. These
handling. For example, if the state does a poor job
particular projects are summarized in Figure 5.
of drafting agreements or fails to address relevant
Price and Schedule Certainty Generally
issues in these agreements, it could experience
Achieved. In terms of the projects reviewed, most
unexpected costs or receive lower levels of service
of them were generally successful at staying on
than planned.
budget and schedule. When there were schedule
Fewer Bidders. According to the research,
and cost overruns, they were typically relatively
infrastructure projects that are relatively expensive
small. For example, three-fourths of the projects
and complex tend to be more ideal candidates
opened to users on schedule or within one month
for P3s. In addition, private partners tend to be
of the planned deadline. Three-fourths of the
comprised of multiple companies who coordinate
projects were also completed on budget or with
efforts to develop a P3 bid—each with expertise in a
less than 5 percent in cost overruns. While there
particular component of the project (such as design
is no way of knowing what the price and schedule
and construction, financing, or maintenance). As
outcomes would have been if these projects were
a result, few private developers have the financial
procured differently (such as a design-bid-build
resources and technical skills to compete for P3
project), the projects were generally successful at
projects, especially on their own. According to
meeting the goal of price and schedule certainty.
experts, P3 projects typically receive between one
Mixed Results During Operations. The
and three bids. In comparison, similarly sized
SR 91 Express Lanes and the SR 125 Tollway both
projects procured under traditional public sector
experienced problems during the operational
approaches typically receive a greater number of
phases of their P3 contracts. Specifically, while both
bids. Less competition for a project procured as
facilities remained open to the public, Caltrans
a P3 could be detrimental to the government, as
incurred additional costs resulting from disputes
more competition for a project generally reduces
with its private partners. For example, the SR 91
the price of a project while increasing its quality.
contract contained a “non-compete clause” that
12 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
prohibited Caltrans or other public agencies that Caltrans, as a partner in the agreement, was
from competing with the tolled lanes built by the partially liable for losses claimed by some of the
private partner. Thus, if public agencies made private companies involved in the project. The
any improvements to transportation facilities in private partner ultimately declared bankruptcy,
the SR 91 corridor (including minor projects to with the court awarding the rights to the remainder
improve the safety of the general-purpose lanes of of the P3 to a group of lenders who had financed
the highway), the private partner believed that the the project. This group subsequently sold the
state would be required to compensate for the loss agreement to the San Diego Association of
of toll revenue if fewer people drove on the tolled Governments.
P3 lanes due to these improvements. The issue was Given the nature of design-build and
litigated in court, but was ultimately settled when construction manager at risk contracts, the other
the private partner agreed to sell the rights of the projects we reviewed did not transfer responsibility
express lanes to the Orange County Transportation for operating the infrastructure facility to a
Authority (OCTA), a local public transportation private partner after it was built. However, the
agency. Since OCTA assumed control of SR 91, toll road projects involving SR 73, SR 241, SR 261,
Caltrans has not had any conflicts regarding the and SR 133 did involve other public entities
non-compete clause. being responsible for operating the facilities. This
The SR 125 project experienced legal challenges network of tolled public highways in Orange
that delayed its completion. Such challenges County (commonly referred to as “The Toll Roads”)
made the partnership less profitable for the are managed by the Transportation Corridor
private partner. Specifically, the lawsuit alleged Agencies (TCAs), which are public agencies led
Figure 5
Design-Build and Construction Manager at Risk: Cost and Schedule Outcomes
Percentage
Implementing Type of Project Price Increase
Project Agency Procurement Completion From Contracta
SR 73 Toll Road TCAs Design-build 4 months early —
SR 241, SR 261, and SR 133 Toll Roads TCAs Design-build 14 months early —
SR 22 Carpool lanes OCTA Design-build 1 week late 4.6%
Contra Costa Justice Center AOC Construction 1 week early 1.2
manager at risk
Fresno Court Facility Renovation AOC Construction 1 month late 0.2
manager at risk
State Office Building in Oakland DGS Design-build On schedule —
San Francisco Civil Center DGS Design-build On schedule 1.2
State Office Building in Los Angeles DGS Design-build 3 months late 7.3
State Office Buildings in Sacramento DGS Design-build On schedule 10.4
Caltrans Office Building in Los Angeles DGS Design-build 15 months late 5.2
Caltrans Office Building in Marysville DGS Design-build On schedule 3.0
Central Plant Renovation in Sacramento DGS Design-build 4 months late 0.6
a
Excludes cost of changes requested by the implementing agencies, such as increases to the contractors’ scope of work.
SR = State Route; TCAs = Transportation Corridor Agencies; OCTA = Orange County Transportation Authority; AOC = Administrative Office of the Courts; and
DGS = Department of General Services.
www.lao.ca.gov Legislative Analyst’s Office 13
An LAO RepOR t
by locally elected officials. While the TCAs may not meeting expectations and later rebid the work
contract with private companies to operate the toll to a different company. Using separate contracts
roads, they are ultimately responsible for making and retaining more responsibility for making key
key decisions and directly managing the contracts. decisions helped avoid some of the unforeseen costs
When the TCA’s encountered problems after the (such as legal costs) that were incurred with the
highways became operational, they were able to state’s P3 projects.
end a contract with a private operator who was
P3 BESt PracticES
As part of our examination of the P3 approach, having a transparent process so that potential
we reviewed international research and interviewed partners are aware of the specific requirements
experts in the field. Based on our review, we that must be satisfied to bid on a project and how
identified a set of best practices that have been long the procurement process will likely take. Such
found to maximize the potential benefits of P3s transparency also helps stakeholders and the public
and minimize its potential limitations. These best understand how and why a government entity
practices are summarized in Figure 6 and discussed selected a private company to build or operate public
in more detail below. infrastructure. For example, Virginia created the
Office of Transportation Public-Private Partnerships
Establish overall P3 Policy and
to develop a consistent institutionalized process for
implement transparent Processes
P3 procurements, in order to help attract qualified
Experts recommend that governments adopt developers and contractors.
an overall P3 policy to (1) guide decision-makers
adopt criteria to determine good
when evaluating different procurement options and
candidates for P3 Projects
(2) inform potential private partners and the public
of the process. For example, experts recommend International research also finds that it is
good practice for governments to adopt criteria for
Figure 6
determining whether projects would be a good fit
Public-Private Partnership (P3)
for P3 procurement, as not all public infrastructure
Best Practices
projects would benefit from a P3 approach. For
example, as we discuss later in this report, the
9
Establish overall P3 policy and implement Legislature could establish criteria that provide a
transparent processes.
reasonable means of screening potential P3 projects.
9
Adopt certain criteria to determine good Such criteria should not be too prescriptive or
candidates for P3 projects.
cumbersome. Experts recommend that the screening
9
criteria include the following:
Conduct a rigorous value for money
analysis.
• Government Benefit From Using
9
Adopt and implement a project approval Nonpublic Financing. The screening
process. process should determine if there is a benefit
9
(such as completing the project sooner) to
Establish government expertise in P3s.
14 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
the government from financing the project • Revenue Source to Repay Financing. As
with a private partner, rather than using discussed above, P3s require a revenue
public funds upfront to pay for the project. source to repay the financing provided by
Typically, relatively expensive projects—with the private partner. Ideally, a project would
costs ranging from the hundreds of millions have a dedicated revenue source (such
to billions of dollars—are more likely to as a toll or user fee) to repay the money
benefit from private financing, as it can take borrowed from the partner. The government
several years to save up enough funds to entity, however, could commit to make
build a large project without financing or to payments to the partner from government
get approvals for public financing. funding sources, such as tax revenues.
• Technically Complex. Generally, projects
conduct a rigorous value for Money analysis
that are technically complex are more likely
Once it is determined that a particular project
to benefit from the innovation or specialized
is a good P3 candidate, experts recommend that
expertise that is typically associated with
the government entity perform a detailed analysis
P3s. For example, a private partner with
that compares the project’s costs using a P3 to
extensive experience designing and building
using a more traditional procurement approach.
tunnels or bridges may be able to construct
A commonly used analysis is a “value for money”
a complex tunnel or bridge more quickly
(VFM) analysis, which identifies all the costs of
and/or at a lower cost. On the other hand,
a project (such as the design, construction, and
projects that are very simple (such as
operation and maintenance of the facility) over
repaving a road) are not as well suited for
the life of the project or the term of the lease
the P3 approach because they are less likely
with the private partner. These costs are then
to benefit from innovation and specialized
“discounted” over time to determine the project’s
expertise.
cost in net present value. In other words, because
• Ability to Transfer Risks to Partner.
the expenditures take place over several decades
Projects that are good candidates for P3s and the timing of the expenditures differ between a
generally have significant known risks that P3 approach and the more traditional procurement
the government can transfer to a private approach, the comparisons are adjusted to account
partner. For example, a project that is in for the fact that money available at the present time
the very early stages of development and is worth more than money available in the future.
does not have a completed environmental Specifically, the VFM analysis should compare
review may lack sufficient information to the cost of the different procurement approaches
allow for an effective transfer of risk. Given in net present value terms of delivering the same
these unknown risks, potential partners level of service—both in terms of the quality of the
may be hesitant to bid on the project or infrastructure constructed and the quality of the
may incorporate large premiums into their maintenance and operation services provided.
bid. Alternatively, a project with clearly The VFM analyses can be complex and the
identified risks (such as if a toll road will underlying assumptions can significantly influence
generate enough revenue to finance the the outcomes. Thus, most experts recommend
project) would be more well-suited as a P3.
www.lao.ca.gov Legislative Analyst’s Office 15
An LAO RepOR t
specifying parameters for the assumptions (such as Establish government Expertise in P3s
for the discount rate) so that all potential projects
Another P3 best practice is for government
are evaluated with similar criteria.
entities to develop expertise regarding P3s, in
order to better protect public resources when
adopt and implement Project
entering into large contracts with private partners.
approval Process
Experienced departmental staff can make it easier
Experts recommend maintaining a process
for the state to handle P3 workload quickly and
to approve projects for P3 procurement that
thoroughly, as well as effectively communicate with
allows good candidates to proceed. The approving
the private sector. Governments could use private
entity (such as the Legislature or an independent
consultants to help with this workload.
board), which is typically separate from the
Our research also found that P3 expertise
agency sponsoring the project, should verify that
can reside at multiple levels of government. For
(1) the project satisfies most of the established P3
example, PPP Canada provides information and
criteria and (2) the VFM analysis shows that a P3
assistance to Canada’s provincial and municipal
procurement is the best option. In addition, P3
governments on the use of P3s. At the provincial
experts recommend obtaining project approval
level, Partnerships BC in British Columbia provides
prior to having potential partners bid on the
specialized services, such as managing projects and
project. This is because private developers may
facilitating communication with the private sector.
not bid on a project if they are unsure whether
In addition, experts recommend reviewing the
the approving entity might stop it from moving
outcomes of P3 projects at various stages to allow
forward.
a government entity to determine what worked
well and what problems were encountered on each
project. The lessons learned can be used to inform
future P3 procurements.
StatE’S uSE oF P3S FaLLS
Short oF BESt PracticES
As we discussed earlier in this report, a P3 procurement—meaning the Presidio Parkway
existing state law authorizes Caltrans, AOC, and project and the Long Beach courthouse project.
the HSRA to use P3s to procure certain types Our findings regarding each of these projects are
of infrastructure. In analyzing their use of this summarized in Figure 7 and described in detail
authority, we generally found that the practices below.
of Caltrans and AOC are not necessarily aligned
State Lacks transparent P3 Processes
with P3 best practices. (At the time of this report,
HSRA had not entered into any P3 contracts.) As discussed above, having clearly defined
For example, our analysis indicates that these and transparent P3 processes is considered a best
departments did not use clear P3 processes and practice. However, our review found that the state’s
appear to have selected projects not well suited for use of P3 procurement for the Presidio Parkway
16 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
and Long Beach courthouse projects lacked Similarly, AOC did not use a transparent
transparent frameworks and clear processes. For framework in selecting the Long Beach courthouse
example, when Caltrans used a P3 procurement to be a P3 project. For example, AOC did not
for the Presidio Parkway, the department lacked develop guidelines for selecting potential P3
a transparent framework for selecting the project projects and conducting VFM analyses. More
and conducting a VFM analysis. It did not release importantly, at the time of this report, AOC had
a draft P3 program guide until December 2011, not developed transparent criteria or processes
one year after signing the agreement for Presidio for determining potential P3 projects in the
Parkway. While the guide addresses many future. For example, it is unclear how AOC will
procedural questions regarding the department’s identify projects that are likely to benefit from a P3
future use of P3s, it does not establish a consistent approach and evaluate potential projects through
process for evaluating potential P3 projects the use of VFM analyses.
through the use of a VFM analysis. We think this
Selection criteria for recent Projects
is a significant shortcoming of the guide because
not aligned to Best Practices
establishing VFM processes and parameters is
important to ensure that projects are evaluated on Our analysis indicates that the processes
a consistent basis using reasonable assumptions. used to identify the two recent state projects for
The Caltrans draft P3 program guide also does P3 procurement—the Presidio Parkway and the
not address how project evaluation, review, and Long Beach courthouse—included few of the best
procurement responsibilities will be carried out practice criteria.
when the state partners with local transportation Presidio Parkway Selection Was Problematic.
agencies. Specifically, the guide does not lay out how According to Caltrans staff, the Presidio Parkway
the lead agency will be determined and which entity project was selected as a P3 candidate primarily
is responsible for certain tasks, such as review and based on two criteria: (1) an estimated project cost
oversight. As a result, various local agencies that we of more than $100 million and (2) a completed
talked to appear to have different understandings of environmental impact review. However, according
what will be required of them for P3 projects. to the identified best practices, these two factors
Figure 7
State Not Meeting Many Public-Private Partnership (P3) Best Practices
Long Beach
Best Practice Presidio Parkway Courthouse
Establish transparent P3 processes
Adopt certain criteria to determine good P3 candidates
Conduct rigourous value for money analysis
Implement thorough project approval process
Establish state expertise in P3s
Not meeting
Mixed results
www.lao.ca.gov Legislative Analyst’s Office 17
An LAO RepOR t
alone do not constitute a robust set of screening project, the selection process for the Long Beach
criteria. In other words, the selection process for courthouse project did not include much of the
the project did not include such recommended recommended best practice criteria. For example,
criteria as the ability to transfer risk to the private the selection process did not evaluate whether the
sector and whether the state would benefit from project is technically complex. While the ideal
using non-state financing. While the selection level of complexity for a P3 is difficult to define in
process for a P3 project does not need to include all specific terms, the Long Beach courthouse project
of the best practice criteria, including such criteria lacks unique or complex features that would likely
does help ensure that the intended P3 benefits are benefit from innovative design and construction
achieved. Our analysis indicates that if Caltrans techniques. Accordingly, our analysis indicates that
utilized such criteria in its selection process, the if AOC utilized best practice criteria in its selection
Presidio Parkway project would have been found to process, the Long Beach courthouse project
be inappropriate for P3 procurement. would have been found to be inappropriate for P3
For example, the Presidio Parkway project was procurement.
too far along to transfer many of the project’s risks
vFM analyses Based on assumptions
to a private partner. This is because the Presidio
that Favored P3 Procurement
Parkway’s first phase of construction was already
underway using a design-bid-build procurement As described above, VFM analyses can help
when the second phase of the project was selected decision-makers compare the cost of a project under
for P3 procurement. As a result, potential private different procurement options. Both Caltrans and
partners had limited access to the construction AOC contracted with private consultants to perform
site, which in turn made them less willing to such analyses for the Presidio Parkway and Long
take on many of the project’s construction risks. Beach courthouse projects. Specifically, the analyses
For example, the state retained significant risks compared the costs of constructing the project under
regarding the discovery of archeological artifacts a more traditional approach to a P3 approach. The
and endangered species. In addition, Caltrans had VFM analyses found that the state would benefit
already designed about half of the project’s second financially if the Presidio Parkway and Long Beach
phase prior to awarding the P3 contract. Thus, courthouse projects were procured as P3s—meaning
the winning bidder may be limited in its ability to it would be cheaper to have a private developer build
find cost-savings through innovative design and and operate the planned facility. Our review of these
construction techniques because it must adhere to particular analyses, however, indicates that both
certain specifications it did not design. VFM analyses were based on several assumptions
Long Beach Courthouse Selection Was that are subject to significant uncertainty and
Problematic. According to AOC staff, the Long interpretation and tended to favor a P3 procurement.
Beach courthouse project was selected as a P3 If a series of different assumptions were made,
candidate based primarily on two criteria: (1) it the VFM analyses would have shown that the P3
was one of the largest court construction projects procurement on the Presidio Parkway and Long
considered at that time and (2) the Long Beach Beach courthouse projects would be more expensive
area has a competitive market for the type of in the long run than a more traditional procurement.
property management staff needed to operate a P3. Assumptions in Presidio Parkway Analysis
Similar to the selection of the Presidio Parkway Favored P3. Some of the key assumptions made
18 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
by Caltrans in the VFM analysis of the Presidio would need to be paid for at the start of
Parkway project that tended to favor P3 procurement construction. However, such overages do
include: not typically occur at the start of a project,
but rather as a project progresses through
• Relatively High Discount Rate. In order to
construction. While some consideration
calculate the net present cost of the project,
of the potential for cost overages is
Caltrans’ VFM analysis discounts the cost
reasonable, Caltrans’ method relies on
of the project under a traditional approach
subjective judgment rather than objective
and a P3 procurement by 8.5 percent per
evidence. Consequently, the chosen method
year. As discussed above, this adjustment
has the effect of overstating the net present
is intended to reflect that money spent
cost of the project under a traditional
in the near term is more valuable than
procurement approach, thereby favoring a
money spent in the future. In the past,
P3 procurement approach for the project.
our office has suggested that a 5 percent
discount rate be used for such analyses,
• Failed to Account for Competitive
but acknowledges there is no one “right”
Bidding Environment. The Caltrans’ VFM
discount rate. We also note that the state’s
analysis, which was prepared in February
long-term borrowing rate is currently less
2010, also did not take into account
than 5 percent.
the competitive construction bidding
environment that occurred around that
• Unjustified Tax Adjustment. The VFM
time. During this period, Caltrans awarded
analysis for this project also included
construction contracts that were on average
a $167 million adjustment in order to
30 percent below the project’s original
account for increased tax revenues (such
cost estimate. While it is not possible to
as from corporate taxes) that the private
know exactly what the bids would have
developer would pay to the state under
been if the Presidio Parkway project had
the P3 approach. The analysis assumed
been procured using a more traditional
that if the project was not procured as
procurement, it appears reasonable to
a P3, the state would not receive these
assume that the project could have been
additional revenues. However, we found
awarded at a much lower cost than the
the adjustment included mostly revenues
engineer’s cost estimate.
related to potential federal taxes, which
would not directly benefit the state. Thus, Our analysis indicates that utilizing a
the adjustment made a P3 approach look different set of assumptions (such as a discount
more favorable than is warranted. rate of 5 percent and excluding the assumed
tax adjustment) would result in the cost of the
• Assumed Early Payment of Cost
Presidio Parkway project being less—by as much
Overruns. Under a more traditional
as $140 million in net present value terms—in the
procurement approach (such as design-
long run under a traditional procurement approach
bid-build), Caltrans assumed the Presidio
than the chosen P3 approach.
Parkway project would exceed its budget by
Assumptions in Long Beach Courthouse
$125 million and that such cost overruns
Analysis Favored P3. Some of the key assumptions
www.lao.ca.gov Legislative Analyst’s Office 19
An LAO RepOR t
in the VFM analysis of the Long Beach courthouse used by the court. The VFM analysis also
that tended to favor P3 procurement include: assumes this additional space would be
needed by the court in Long Beach in
• Unjustified Tax Adjustment. Similar to
the future, and builds the cost of leasing
the Presidio Parkway project, the VFM
this additional space into its estimates.
analysis for the Long Beach courthouse
This factor adds $260 million in costs to a
project included a $232 million adjustment
traditional procurement of the Long Beach
to account for increased tax revenues
courthouse project, but only $69 million
that would be paid for by the private
to the cost of the P3. The higher cost
developer under the P3 approach. A
under a traditional approach assumes
major component of this adjustment
that a separate building would be leased
reflects revenues from federal taxes. Since
and that the leased building would need
additional federal tax revenues would not
substantial modifications. The analysis for
directly benefit the state, there appears to
the traditional procurement also assumes
be little to no justification for increasing
increased costs for security officers to
the cost of using a traditional procurement
monitor the leased building. While there is
approach to reflect the federal taxes that
some basis for estimating a higher cost for
would be paid by a private developer.
the potential need to lease additional space
• Overstated Cost Overruns. The VFM under a traditional procurement approach,
analysis assumed that using AOC’s more the AOC has not conclusively demon-
traditional procurement approach of strated that all of this additional space
construction manager at risk—rather would be needed by the court in Long
than a P3 procurement approach—would Beach. Moreover, AOC’s other courthouse
result in construction cost overruns construction projects ordinarily do not
for the Long Beach courthouse project include this kind of extra space.
totaling $128 million (about 30 percent
• Project Completion. The AOC’s VFM
of the project’s estimated cost). However,
analysis assumes that it would take
given that AOC has procedures in place
14 months longer to complete the Long
to prevent such cost overages and has
Beach courthouse under construction
not experienced them with recent court
manager at risk procurement than as
construction projects, this assumption
a P3 project. Accordingly, the analysis
has the effect of overstating the cost of the
uses different timelines to discount the
project under a construction management
costs of the project under each type of
at risk approach.
procurement. The way the VFM analysis
• Leasing of Additional Space. The AOC’s adjusts for these assumed differences in
VFM analysis assumes that under the timing effectively increases the cost of a
P3 approach, the courthouse project traditional procurement in net present
would include space that would initially value terms. However, it is not evident that
be leased by the private developers to such a procurement would necessarily take
other entities, but could eventually be 14 months longer—especially in view of the
20 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
considerable flexibility state law gives AOC state law does not require that Caltrans address any
with respect to its construction contracting of the concerns raised in these reviews.
methodology. For court construction projects, state law
authorizes the Joint Legislative Budget Committee
Our analysis indicates that utilizing a different
and DOF to review a potential P3 project before
set of assumptions than those discussed above
AOC can fully develop the project’s concept.
(such as excluding the assumed federal tax
Accordingly, the Legislature reviewed and
adjustment and leasing costs) would result in the
approved the general criteria used by AOC to select
cost of the Long Beach courthouse project being
the private partner for the Long Beach courthouse
less—by as much as $160 million in net present
project. However, the Legislature did not have an
value terms—in the long run under a traditional
opportunity to review and comment on the VFM
procurement approach than the chosen P3
analysis before it was finalized and the contract was
approach.
signed with the private developer.
State Law Lacks thorough
State Lacks P3 Expertise
Project approval Processes
As previously discussed, experts recommend
Our analysis found that for both the Presidio
that government entities develop expertise
Parkway and Long Beach courthouse projects, the
regarding P3s in order to better protect public
state did not utilize a thorough process for selecting
resources when entering into large contracts with
P3 projects. Having thorough processes in place
private developers. Our review, however, finds that
could have prevented Caltrans and AOC from
such expertise within state government has not
entering into a P3 agreement for each project, or
been sufficiently developed in California.
at least required changes to negotiate lower prices
PIAC Has Limited P3 Expertise. The PIAC
and better ensure that the intended P3 benefits are
was established in 2009 to assemble and share
achieved.
research on best practices and lessons learned
For P3 transportation projects, state law
from transportation P3s around the world.
requires the CTC to conduct a limited review
However, based on our discussions with staff at
of the basic features of each project sponsored
the BT&H Agency and our review of various PIAC
by Caltrans or a regional transportation agency.
documents (including the minutes from the seven
(We note that in reviewing the Presidio Parkway
PIAC meetings that have taken place), we find that
project, CTC extended its evaluation beyond the
PIAC has done little to implement best practices
basic requirements to further review the project’s
for transportation P3s. The only steps that PIAC
financing.) However, state law does not require
appears to have taken in this regard are to post
the commission or another entity to conduct an
reports containing information on P3 best practices
overall review of whether (1) the state would benefit
on its website and to contract for two reports on
from procuring a particular project as a P3 and
P3s. We also note that the commission currently
(2) whether a particular P3 contract is structured
lacks members with in-depth expertise on issues
to maximize the state’s benefits. Moreover, while
such as state financing, state procurement, and state
state law does provide a 60-day period for the
labor issues. Perspectives on these issues could help
appropriate legislative fiscal and policy committees
to ensure that the state maximizes its benefits when
and PIAC to review P3 proposals before Caltrans
using P3s.
can sign an agreement with a private developer,
www.lao.ca.gov Legislative Analyst’s Office 21
An LAO RepOR t
No Systematic Approach for Reviewing past P3 projects in order to maximize benefits and
Lessons Learned. Our review also finds that avoid repeating past mistakes. We understand
the state does not have a systematic process for that AOC is currently developing a review and
identifying and applying lessons learned from prior reporting process for the Long Beach courthouse
P3 projects. Although Caltrans is the only state project. Once completed, these reports may provide
agency to have entered into multiple P3 agreements, helpful lessons learned about AOC’s use of P3
it currently lacks a formal process for reviewing procurement.
rEcoMMEndationS to
MaxiMizE StatE BEnEFitS FroM P3S
In this report, we reviewed the state’s authority utilize certain criteria when evaluating
experience with P3s and identified several instances whether a particular project should be procured as a
where the best practices identified in existing P3 P3. According to the research, these selection criteria
research have not necessarily been followed. Based should not be highly prescriptive, but rather should
on our review and findings, we have identified provide general guidance regarding the selection
several opportunities for the state to further of potential P3 projects. Such an approach would
maximize its benefits when deciding to procure provide for greater consistency across departments
a state infrastructure project as a P3. Our specific in terms of how P3 projects are selected. The
recommendations are summarized in Figure 8 and selection criteria should include being a technically
discussed in detail below. complex project, as well as a project that can transfer
risks to a private partner and benefit from non-state
Specify P3 Project Selection criteria
financing. In addition, the Legislature may want to
As previously mentioned, the state’s processes specify whether P3 projects must have a revenue
for selecting P3 projects are inadequate and not source, such as a user fee.
necessarily based on selection criteria identified
require analysis of a range of
in the research as best practices. Accordingly, we
Procurement options
recommend that the Legislature adopt legislation
requiring that each state department with P3 In order to determine which procurement
approach would most
Figure 8 effectively benefit the
LAO Recommendations to Maximize Public-Private state, we recommend
Partnership (P3) Benefits
that the Legislature adopt
legislation requiring
9 a comparative VFM
Specify P3 project selection criteria.
9 analysis of a range of
Require analysis of a range of procurement options.
procurement options
9
Modify structure and responsibilities of Public Infrastructure Advisory (including design-bid-
Commission.
build, design-build,
9
Improve consistency of state’s P3 approval process. and P3) for all potential
22 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
P3 infrastructure projects. Evaluating a range Modify Structure and responsibilities of Piac
of procurement options would allow the state to
In order to help ensure that PIAC effectively
better balance the potential benefits of increased
assembles and shares research, best practices, and
private sector involvement with the potential risks
lessons learned from transportation P3s around
unique to each project. In contrast, the benefit of
the world, we recommend the Legislature adopt
evaluating only two procurement approaches—as
legislation to:
was done by Caltrans and AOC—can be limited.
• Expand PIAC’s Authority. In order to
This is because it does not evaluate other options
provide a consistent review and approval
(such as design-build), which in some cases may be
process for the use of P3 procurement, we
the best option.
recommend expanding the PIAC’s role
We also recommend that the Legislature
to require the commission to approve all
specify in statute that such VFM analyses:
state P3 projects, as discussed in detail
• Exclude Federal Tax Adjustments.
later in this report. We also recommend
Increased federal tax revenues do not
expanding the scope of PIAC to all types
directly benefit the state and should not be
of infrastructure projects, rather than only
included in a VFM analysis.
those related to transportation. Having the
commission involved in all types of P3 will
• Apply Costs to Expected Year of
further the state’s P3 expertise. To reflect
Expenditure. Project costs should be
this broader scope, we also recommend
accounted for in the year they are likely to
making PIAC an independent commission,
be incurred, in order to effectively estimate
rather than part of the BT&H Agency.
the project’s likely total cost in the long
run.
• Direct PIAC to Evaluate Other
Departments for P3 Authority. We have
• Use Current Construction Cost
found that certain types of projects may
Estimates. Construction cost estimates
benefit the state if procured using a P3. It
should be based on the current bidding
is possible that state departments other
environment in the state.
than Caltrans, AOC, and HSRA will
• Include a Sensitivity Analysis. A have projects meeting these P3 criteria.
sensitivity analysis can help to indicate Accordingly, we recommend that the
how the results of the VFM analysis might Legislature direct PIAC to review the types
change with a different set of assumptions. of projects planned by other state depart-
Specifically, this analysis should evaluate ments and recommend to the Legislature
project costs and revenues with a range whether P3 authority should be granted to
of reasonable discount rates to show how additional state departments.
differing assumptions can influence the
• Broaden PIAC’s Expertise. In order
outcome of the VFM analysis. If a project
to ensure that PIAC has the expertise
will generate revenue, such as from tolls
necessary to advise state departments
or fares, a reasonable range of revenues
on all types of P3s, we believe it would
should also be evaluated in the sensitivity
be beneficial for the commissioners to
analysis.
www.lao.ca.gov Legislative Analyst’s Office 23
An LAO RepOR t
have a broad mix of expertise related improve consistency of State’s
to P3, as well as state finance and P3 approval Process
procurements. Specifically, we recommend
We recommend that the Legislature adopt
that the Legislature appoint some of the
legislation to make the process for reviewing and
commissioners and that, in addition to
approving P3 projects consistent and thorough
P3 experts, the commission include the
across those state departments authorized to
Director of the Department of General
pursue such projects. Specifically, we recommend
Services (or a representative), and the
requiring the use of the review and approval
State Treasurer (or a representative). The
process summarized in Figure 9 and discussed in
Legislature could also consider reducing
detail below.
the number of commissioners on PIAC to a
Require PIAC to Approve P3 Concept and
more manageable size.
VFM Analysis. Our above recommendations to
modify the structure and responsibilities of PIAC
• Require PIAC to Develop and Implement
would make it well-suited to review and approve
Best Practices. We recommend requiring
a department’s proposed use of P3 procurement.
PIAC to (1) develop a set of best practices
As shown in Figure 9, we recommend that the
for P3 projects in California, (2) provide
Legislature require departments to provide a VFM
state departments specific steps for
analysis and other relevant project information
implementing those best practices,
(such as draft procurement documents) on
and (3) provide technical assistance to
all proposed P3 projects to PIAC. Under our
state agencies planning to pursue a P3.
recommended process, if PIAC identifies concerns
Consistent with the research, it would
with a P3 proposal, the commission would require
benefit the state to have such expert advice
the department sponsoring the project to perform
provided from the initial project screening
additional analyses and resubmit the proposal
stage through the procurement and
for subsequent review. If a project does not
administration of a P3 contract. We also
satisfy the above P3 criteria, we recommend that
recommend that the Legislature require
PIAC have the authority to reject the use of a P3
periodic reports from PIAC in its efforts
approach, and direct the department to use another
in developing and implementing P3 best
procurement method. Thus, we recommend that
practices.
the Legislature adopt legislation directing PIAC to
implement a process to evaluate (1) whether a P3
project proposal is consistent with the scope and
cost approved in the state’s current capital outlay
processes (meaning either by the Legislature or
CTC) and (2) whether using a P3 approach would
be the best procurement option.
24 Legislative Analyst’s Office www.lao.ca.gov
Graphic Sign Off
Secretary
Analyst
Director
Deputy
An LAO RepOR t
Figure 9
A Uniform P3 Approval Process Likely to Ensure Better Outcomes for the State
Current Infrastructure
Project Approval Process
Legislature or CTC establishes
project’s scope and funding.
Department Evaluates
Potential P3 Project
Benefit from financing.
Technically complex.
Ability to transfer risks. P3 is not best choice
Revenue source.
Department Conducts Value
for Money (VFM) Analysis
Evaluate a range of
procurement options using
reasonable assumptions.
Modifications needed to PIAC Review
VFM analysis Review VFM analysis. Rejection
Ensure project is consistent
with established scope and
funding.
Verify P3 is best choice.
Approval
Procure Using More
Procure Using P3
Traditional Approach
P3 = Public-Private Partnership.
CTC = California Transportation Commission.
PIAC = Public Infrastructure Advisory Commission.
concLuSion
Based on our review of existing research, we (including private loans) may even be the only way
ARTWORK #110623
believe that P3 procurement—if done correctly— to build those projects that are both very complex
has merit and may be the best procurement option and expensive. For such projects, the use of P3
for some of the state’s infrastructure projects. In procurement can make the price and schedule
certain instances, sharing risks with a private more certain by transferring various project risks to
partner and using a diverse financing package a private partner. In addition, access to specialized
www.lao.ca.gov Legislative Analyst’s Office 25
An LAO RepOR t
expertise and private financing could have the such best practices are followed in developing and
effect of accelerating projects and providing other implementing future P3 projects. For example,
benefits to the state. However, the state does give we recommend specifying P3 project selection
up considerable control over the management and criteria and improving the state’s approval process
long-term funding priorities of a project that is to utilize an entity with expertise in P3s. More
constructed under a P3 approach. This limitation importantly, our proposals to develop P3 expertise
and others must be considered carefully when and better evaluate potential P3 projects would
considering a decades-long partnership. provide for a better understanding of the actual
We also find that implementing certain P3 benefits and limitations of P3 projects. Finally, as
best practices identified in the research can better the state gains experience with P3s, the Legislature
ensure that the intended benefits of P3s to the may want to consider whether the existing P3
state are achieved. Thus, in order to maximize the authorization provided to Caltrans and AOC
state’s benefits from P3s, we recommend that the should be expanded to other departments.
Legislature take a series of steps to ensure that
26 Legislative Analyst’s Office www.lao.ca.gov
An LAO RepOR t
www.lao.ca.gov Legislative Analyst’s Office 27
An LAO RepOR t
LAO Publications
This report was prepared by Jessica Digiambattista Peters, and reviewed by Farra Bracht and Anthony Simbol. The
Legislative Analyst’s Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the
Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service,
are available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000,
Sacramento, CA 95814.
28 Legislative Analyst’s Office www.lao.ca.gov