LAO
The 2014-15 Budget: Evaluating FI$Cal Project Plan
Read the report at Legislative Analyst's Office ↗
The 2014-15 Budget:
Evaluating
FI$Cal Project Plan
MAC TAYLOR • L E G I S L A T I V E A N A L Y S T • MARCH 26, 2014
Summary
Over the last several years, the administration has been engaged in the design, development,
and implementation of the Financial Information System for California (FI$Cal) Project, which
will replace the state’s aging and decentralized information technology (IT) financial systems.
The project intends to implement FI$Cal in five waves, with more departments and budgetary/
financial functions added with each wave. The project deployed Pre-Wave—the first of the five
implementation waves—on July 1, 2013 successfully and without incident. The next stage of the
project—Wave 1—is scheduled to begin in July 2014.
Over the last two years since the vendor was selected and the development of the system began,
project staff reports coming to a better understanding of the magnitude and complexity of FI$Cal.
Drawing on lessons learned over this period, the project determined a different approach would
be necessary moving forward in order to mitigate the risk of a significant disruption to the project
in future years. In January 2014, the Department of Technology approved special project report
(SPR) 5, which updates the project plans. The SPR 5 results in a 12-month schedule extension (to
2017-18) and increases the project cost by $56 million—to a total cost of $673 million.
We believe that the time and effort that project staff has spent in updating the project plan has
reduced overall risk and strengthened FI$Cal’s likelihood of success. Nevertheless, significant risk
remains. To enhance legislative oversight, we recommend changes to the timing and content of the
project’s statutorily mandated annual report. In addition, we recommend that the Legislature direct
the administration to consider establishing a recruitment and retention benefit for project staff to
help the project maintain appropriate staffing levels through the completion of the project. Finally,
we recommend approval of the Governor’s budget proposal that reflects a reasonable funding plan to
implement the updated project plan.
2014-15 BUDGET
Background the project’s steering committee. After continued
planning and a lengthy procurement that used an
The FI$Cal Project. Over the last several years,
innovative procurement approach, a vendor was
the administration has been engaged in the design,
selected in 2012 to configure existing financial
development, and implementation of the FI$Cal
management software applications to address the
Project, which will replace the state’s aging and
state’s needs. (Refer to our April 30, 2012 report,
decentralized IT financial systems. The FI$Cal
The 2012-13 Budget: Evaluating FI$Cal, for a more
Project will transform state government processes
comprehensive description of the project’s history.)
in the areas of budgeting, accounting, procurement,
and cash management by (1) eliminating the need FI$Cal Project Status
for over 2,500 department-specific applications
and (2) enabling the state systems and workforce Pre-Wave Deployment Successful
to function in an integrated financial management
The project deployed Pre-Wave—the first of
system environment. The project is managed by
the five implementation waves—on July 1, 2013.
a partnership of control agencies: Department of
Pre-Wave deployed procurement functionality—
Finance (DOF), Department of General Services
including requisitions, purchase orders, and
(DGS), State Controller’s Office (SCO), and State
receiving—in seven state entities. The project also
Treasurer’s Office (STO). The project intends to
implemented a vendor master file for Pre-Wave
deploy FI$Cal in five waves, with more departments
entities, the first step in developing a single list of
and functionality added with each wave.
all vendors that do business with the state.
Evolution of the Project. The planning for the
The Pre-Wave deployment also triggered the
FI$Cal Project began in 2005 when DOF proposed
establishment of the FI$Cal Services Center (FSC).
an IT project that would implement an internal
The center serves as the project’s point of contact
financial system for the department. The Budget
with departments using the system. Ultimately,
Information System, as this system would have
the FSC will be responsible for maintaining and
been called, was envisioned to better meet DOF’s
operating the entire FI$Cal system, including
budget development and administrative needs. In
offering supportive services to departments. The
2006, project staff proposed an updated project
FSC will be deployed incrementally through each
plan that significantly changed the scope and
of the project deployment waves. All components of
governance of the project. Rather than building
Pre-Wave were deployed successfully and without
a new system exclusively for DOF, project staff
incident.
recommended that because a majority of state
The activities necessary for deploying FI$Cal
departments were reliant on aged and inadequate
to departments are largely consistent over the
technology, there was a need to modernize and
various waves, such as engaging departments,
replace the state’s entire financial management
converting data from current technology systems
infrastructure. The updated project plan
to FI$Cal, training end users, and testing the
proposed increasing the scope of the project to
system. Pre-Wave was designed as a pilot to test
include developing a single integrated financial
these procedures. Although the scope of Pre-Wave
information system for the state. The project was
was narrow and only a few departments were
renamed FI$Cal and would be managed by a
impacted, Pre-Wave allowed the project to become
partnership of control agencies that would sit on
familiar with (1) the opportunities and challenges
2 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
associated with the technology; (2) control agency The state’s Department of Technology and a
and departmental technical and organizational third-party technical consultant recently identified
landscape; and (3) the project methodology that performance- and capacity-related concerns
will be used through the entire project lifecycle regarding FI$Cal’s long-term ability to meet the
to analyze, design, build, test, and deploy FI$Cal. state’s budget functionality needs. These oversight
As we discuss further below, this pilot allowed the entities are concerned that some of the budget
project to gain valuable expertise and draw lessons functions may not be ready for implementation
that can inform decisions moving forward. in July 2014, but they agree that the project has
made significant strides in the last several weeks to
Issues in Upcoming Wave 1
address the challenges associated with the budget
Merit Close Attention
functions. The oversight entities have not identified
Challenges With Wave 1 Budget Functions. significant concerns with the financial functions
The next stage of FI$Cal’s deployment—Wave 1—is included in Wave 1.
scheduled to begin in July 2014 and will deploy Project Prioritizing Workload for Wave 1.
financial and budgeting functions to the FI$Cal The project indicates that despite the concerns
partner agencies and a limited number of other of the oversight entities, it continues to make
departments. Specifically, Wave 1 is designed to progress towards accomplishing the objectives of
deploy (1) DOF’s budget control agency functions, Wave 1 and remains on schedule for deployment
establishing FI$Cal as the budget system of record in July 2014. Nevertheless, the project has also
(meaning that FI$Cal will maintain the official indicated that some of the budget functionality
record of the state’s budget); and (2) department- may not be ready (or necessary) for deployment on
level financial functions, including accounting, July 1. As a result, certain budget functionalities
cash management, and procurement. The project may be rolled out incrementally after July 1. The
is currently experiencing challenges developing project indicates that the delay would have little
the budget functions associated with Wave 1. impact on the budget process since certain budget
Challenges exist in (1) developing the interface functionality is not operationally required on
between the budget and financial functions, July 1 (such as certain functions associated with
which will be required to share information; the preparation of the Governor’s budget, which
and (2) configuring the budget IT solution to is released annually in January). The project
accurately reflect the state’s budget operations. is determining what activities for core budget
These challenges have caused delays in building the functions are priorities for Wave 1. This analysis
budget functions and are subsequently shortening will inform the development of a contingency plan,
the time available for the testing activities in if issues with Wave 1 cannot be addressed in time
Wave 1. Although IT projects typically identify for a July 1 deployment.
some defects upon initial deployment, testing
High Vacancy Rate and Staff Retention Issues
prior to deployment is intended to minimize the
scope and severity of system disruptions. The Project Has Had Difficulties Filling Vacant
FI$Cal Project could be negatively affected if these Positions and Retaining Staff. Staffing difficulties
challenges are addressed too close to deployment create risk that an IT project will not meet key
and the project hastens testing in order to meet the milestones that affect the project’s schedule and
scheduled July 2014 deployment. budget and can ultimately lead to a project failing.
www.lao.ca.gov Legislative Analyst’s Office 3
2014-15 BUDGET
For example, an independent assessment of the Resources manages the process to establish pay
terminated IT Modernization Project at the differentials.
Department of Motor Vehicles concluded that Vacancies Cited as Project Risk. Over the
staff turnover was a significant contributor to that past couple years, the State Auditor has flagged
project’s failure. For much of the FI$Cal Project’s the project’s vacancy rate as a risk that the project
history, FI$Cal management has contended with should mitigate. In its February 2014 report, the
recruitment and retention difficulties. State Auditor noted that the project has made
Many State Departments Have Vacant substantial progress in reducing its vacancy rate
Positions. The process of filling vacant positions from 22 percent in November 2012 to about
is a normal part of human resources management 14 percent in December 2013. More recently,
for employers of any size in both the public and however, the project reported its February 2014
private sectors. In California state government, vacancy rate to be about 17 percent. The project’s
departments generally have the responsibility to fill historically high and volatile vacancy rate can
vacant positions that have been authorized by the be attributed to (1) a relatively limited pool of
Legislature. The percentage of authorized positions applicants with necessary skill sets, (2) obstacles
that are vacant is known as the “vacancy rate.” At inherent in the existing civil service process to
any one time, a substantial number of authorized hiring qualified staff quickly after positions are
positions are vacant in state government. authorized by the Legislature, and (3) high turnover
According to data maintained by SCO, the vacancy rates among project staff (including at executive
rate for state positions in February 2014 was about levels). Even if the project’s overall vacancy rate
14 percent. Although vacancy rates vary widely were low, sustained vacancies or high turnover of
across departments—and can vary throughout key project positions can significantly compromise
the year for a single department—the statewide the project. The project has seen critical positions
vacancy rate has consistently been around this level remain vacant for sustained periods of time as
for at least the past decade. (Refer to our write-ups well as turnover in its leadership positions. A
entitled “Vacant Positions” in our Analysis of the pay differential has not previously been provided
2008-09 Budget Bill and Analysis of the 2003-04 to FI$Cal Project staff; however, the project has
Budget Bill for a more comprehensive discussion of suggested in the past that providing a retention pay
the state’s historical vacancy rate and past efforts to differential could increase the project’s ability to
address high vacancy levels.) attract and retain qualified staff.
Some positions are especially difficult to recruit
Major Components of the
or retain qualified employees. These difficulties may
Updated FI$Cal Project Plan
be due to the location of the job, the type of work
performed, low salaries relative to those offered by In California state government, a feasibility
other employers, or other factors. In some cases, study report documents the initial justification for
the state provides employees with these difficult- an IT project and lays out the project plan, while
to-fill positions additional pay on top of what is any significant subsequent changes to the project
established for the position’s classification in an plan—including project scope, schedule, and/
effort to improve a department’s recruitment and or budget—are documented in SPRs. In January
retention efforts. This additional pay is referred to 2014, the FI$Cal Project submitted, and the
as a “pay differential.” The Department of Human Department of Technology approved, an SPR that
4 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
updates the project plans. This was the fifth update departments included in each wave according to
(SPR 5) to the project plans since FI$Cal began its SPR 5.
planning phase in 2005. The project indicates the Expands Project Scope to Completely Include
proposed changes reflect lessons learned since the DGS. The project determined during its planning
previous project update (SPR 4) was approved in phase that if a department had an operational
March 2012. The last two years have been marked financial management system—or was in the
with significant accomplishments, most notably process of implementing such a system—it would
the selection of the primary vendor and the be designated as a “deferred department.” In order
successful deployment of Pre-Wave. Drawing on that the state’s financial information is centrally
lessons learned over this period, the project reports housed, deferred departments will interface their
coming to a better understanding of the magnitude current financial management systems with FI$Cal
and complexity of FI$Cal, particularly Wave 2 without being direct users of the new system.
as planned under SPR 4. Specifically, the project Over time, a deferred department will transition
determined the risk associated with the project to FI$Cal as its current system exceeds its useful
was too large and decided a different approach life. Other departments are statutorily exempt
would be necessary moving forward in order to from ever becoming users of FI$Cal. Figure 2 (see
mitigate the risk of a significant disruption to the next page) lists departments that are deferred or
project in future years. The project indicates that entirely exempt from FI$Cal under SPR 5. Under
the revised plan, outlined below, reduces the overall SPR 4, DGS’s internal financial management
risk associated with the implementation of FI$Cal. system was deferred, but the department’s control
See Figure 1 for a summary of functionality and agency procurement functions were included in the
Figure 1
Departments and Functionality of FI$Cal Waves Under Special Project Report 5a
Number of
Additional
Departments Additional Functionality
Pre-Wave 7 Chart of accountsb
Master vendor filec
Requisition to purchase order
Wave 1 23 Department of Finance control agency functions
Department-level accounting, budget, cash management, and procurement
Wave 2 3 Department of General Services (DGS) control agency functions
50 contracted
fiscal services
departmentsd
Wave 3 2 State Controller’s Office control agency functions
State Treasurer’s Office control agency functions
Wave 4 68 Public transparency website
a
Functionality implemented in earlier waves is deployed to new departments as they join the Financial Information System for California (FI$Cal).
Functionality implemented after a department originally joined FI$Cal will be deployed to that department as part of the subsequent wave
deployments.
b
Establishes a unique identification number for each business unit, project/grant, and account.
c
A statewide central source of vendor information that will be used by all departments for procurement, receiving, and payment functions.
d
DGS offers accounting, budgeting, and financial services to state entities on a fee-for-service basis. These departments are known as contracted
fiscal service departments.
www.lao.ca.gov Legislative Analyst’s Office 5
2014-15 BUDGET
FI$Cal Project scope. The DGS’s internal financial internal financial management system and
management system has reportedly reached its 50 contract fiscal services departments that
end of life sooner than expected. Consequently, rely heavily on procurement functionality.
per SPR 5, the project proposes to accommodate Wave 2 will begin three months earlier
a request by DGS to replace its existing internal than previously planned to allow for
financial management system with FI$Cal. The 15 months of design and development
new updated project plan expands FI$Cal’s scope to of the procurement functions, however,
accommodate this. its deployment date is still planned for
Revises Deployment Schedule for Final Three July 2015.
Waves. The project proposes to change the system
• Wave 3. With the updated plan shifting
deployment by shifting the bulk of departments
SCO and STO control agency functions
to the final wave (Wave 4) so that control agency
from Wave 2 to Wave 3, Wave 3 is
functionality is deployed before departments come
expected to (1) begin six months earlier
on line. Specifically, the revised project plan makes
than previously anticipated and (2) end
the following changes to Waves 2, 3, and 4.
six months later. These changes allow for
• Wave 2. The updated plan decreases the
a 24-month design period and align the
scope of Wave 2 by shifting the SCO
deployment with the start of 2016-17.
and STO control functions previously in
Wave 2 to Wave 3. The focus of Wave 2 • Wave 4. Under the new plan, all other
becomes DGS’s control agency functions, departments previously in Wave 2 and
but also includes the replacement of DGS’s Wave 3 are shifted to Wave 4. The final
wave of the project will
Figure 2
also implement a public
Departments Deferred or Exempt From FI$Cal
transparency website.
Under Special Project Report 5
The plan delays Wave 4’s
Deferred
deployment from
Board of State and Community Corrections July 2016 to July 2017 to
California State Lottery Commission
allow a full 24 months for
Department of Corrections and Rehabilitation
Department of Motor Vehicles design and development.
Department of Transportation
Schedules Expected
Department of Water Resources
State Teachers’ Retirement System FI$Cal Software Upgrade.
Exempt The previous project plan
Legislature (SPR 4) indicated a need
Legislative Counsel Bureau/Legislative Data Center to upgrade the FI$Cal
Judicial Branch
software but assumed
State Auditor’s Office
University of California the upgrade would take
California State University place after all waves were
Hastings College of the Law
implemented. (Oracle—
California Housing Finance Agency
Public Employees’ Retirement System the developer of the IT
State Compensation Insurance Fund system that FI$Cal will
6 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
implement—has released a newer version of the this level for the duration of the project seems
software since the project began.) The new plan reasonable given the more complex nature of
proposes to schedule the necessary upgrade to the control agency functions that will be deployed in
FI$Cal software as part of Wave 3. Wave 2 and Wave 3.
Does Not Change Wave 1. The new plan Affects Project Cost and Schedule Relative
proposes no changes for Wave 1—scheduled to to SPR 4. The proposed changes to the project
deploy in July 2014. reflected in SPR 5 result in a 12-month schedule
Requires Longer Period of Heightened extension, as shown in Figure 3, and increase the
Staffing Levels. The SPR 4 provided for a project cost by $56 million—to a total project
ramp-down of project staff—from the peak level— cost of $673 million. (The increase in project
due to a decrease in workload in later waves. As cost is mostly attributed to the proposed levels of
a result of Wave 4 expanding in scope, SPR 5 project staff over the additional 12 months.) These
requires sustaining the peak level of staff through additional costs also include an increase in project
Graphic Sign Off
the duration of the project (through 2017-18). vendor cost of $14 million—to a total vendor
Under the new plan, total staffing will peak in contract cost of $226 million. The actual project
Secretary
2014-15 at 294 positions and is sustained at that costs over the last seven years—from 2005-06
Analyst
level through the deployment of Wave 4. Staffing through 2012-13—were $160 million. In 2013-14,
MPA
then decreases in 2018-19 when FI$Cal enters budgeted expenditures are $85 million. See Figure 4
Deputy
its first full year of maintenance and operation (next page) for project costs (including planning
(M&O). Although the bulk of departments are and other predevelopment expenditures incurred to
shifted to the last wave under SPR 5, reaching date) by fiscal year through 2018-19.
a peak level of staff in 2014-15 and sustaining
Figure 3
Comparison of FI$Cal Implementation Timeline Under Special Project Report (SPR) 4 and 5
Calendar Years
2012 2013 2014 2015 2016 2017
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Pre-Wave — 12 Months M&O
Wave 1 — 20 Months M&O
Wave 2 — 12 Months M&O
Wave 3 — 12 Months M&O
SPR 4
Wave 4 — 12 Months M&O
Pre-Wave —12 Months M&O
Wave 1 — 20 Months M&O
Wave 2 — 15 Months M&O
Wave 3 — 24 Months M&O
SPR 5
Wave 4 — 24 Months M&O
M&O = maintenance and operation. = go live date.
www.lao.ca.gov Legislative Analyst’s Office 7
ARTWORK #140158
Template_LAOReport_large.ait
2014-15 BUDGET
LAO Findings
Figure 4
Costs for FI$Cal Plan Attempts to Mitigate Project Risk for
Under Special Project Report 5
Wave 2 Through Wave 4. Typically, project staff
(In Millions) update plans in response to negative project
Fiscal Year General Fund Total Funds indicators, such as a project consistently missing
2005-06 $0.5 $0.9 established milestones or tracking expenditures
2006-07 2.2 5.0 above its budget. This is not the case for FI$Cal, as
2007-08 6.2 6.2
the project is on schedule and within budget, per
2008-09 2.1 5.6
2009-10 2.1 12.3 SPR 4. Instead, the update (SPR 5) is an attempt
2010-11 1.8 25.8 by project staff to reduce the risk associated with
2011-12 1.9 21.8
the project and improve the likelihood of FI$Cal’s
2012-13 — 82.0
2013-14 estimated 3.4 85.1 success. The proposed changes reportedly reflect
2014-15 proposed 94.4 106.5 lessons learned in the nearly two years since the
2015-16 proposed 108.6 134.0
vendor was selected and the development of the
2016-17 proposed 79.0 90.0
system began. For example, the modifications to
2017-18 proposed 40.9 59.8
2018-19 proposed 25.6 37.6 the project are described as reflecting the following
Totals $368.7 $672.6
lessons.
• Align Deployments With Start of Fiscal
Governor’s Budget Proposal
Year. The project reports that it has come
The Governor’s budget proposes an increase to understand that the deployment of
of $4.3 million in 2014-15 to expand the project’s waves in July, at the start of the fiscal year,
scope to include DGS’s internal financial minimizes the disruption to departments
management system as part of FI$Cal. This brings associated with a mid-fiscal year
the total 2014-15 request for the FI$Cal Project deployment.
to $107 million ($94 million General Fund).
• Establish Stabilizing Control Agency
Beyond the 2014-15 budget proposal, the Governor
Functions as a Priority. Minimizing
identifies funding for the project through 2018-19,
the number of departments in Wave 2
which includes the design, development, and
and Wave 3 is intended to focus project
implementation of the project as well as the first
resources on control agency functions.
year of M&O as outlined in SPR 5. Approval of the
These changes may reduce the overall
Governor’s proposal allows the project to effectuate
project risk because these functions
the proposed changes in the new project plan. The
are more complex than departmental
total cost of the project for 2015-16 through 2018-19
implementations.
is $321 million ($254 million General Fund). As
shown in Figure 4, this brings the total cost of the
• Reduce Repeated Deployments to
project (including the first full year of M&O) to
Departments. Because control agencies
$673 million.
affect every other agency and department,
there is substantial risk of rework to
8 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
departments by not having control agency wave, we question whether FI$Cal Project staffing
functions implemented and stabilized prior will be at adequate levels at that time to actively
to bringing on the bulk of departments. engage departments as needed for Wave 4 to
The updated plan dramatically expands succeed within the proposed time frame.
the scope of Wave 4 by shifting to Wave 4 Under New Schedule, Staff Turnover a Bigger
most departments previously planned Risk at Final Wave of Project. Under the revised
for implementation in Wave 2 and project schedule, the final wave is more critical
Wave 3. This transition and the Wave 3 because of the number of departments included in
system upgrade may further reduce risk the wave. In order to stay on schedule while rolling
and eliminate the need for retraining out the system to the increased number of users
departments’ staff and the adverse impacts in the final wave, the project plans to maintain its
of repeated deployments. peak staffing levels through the end of the project.
After the final wave, many of these positions will
While the updated project plan is associated
be eliminated. We expect it will be increasingly
with an extension of the project’s schedule and
difficult for the project to maintain a constant level
an increase in the project cost relative to SPR 4,
of staff—let alone at peak levels—as the end of the
these changes could potentially be less costly
project approaches because (1) employees will look
than moving forward with the prior plan. This is
for other employment opportunities in anticipation
because the previous plan, especially the significant
of their project job ending and (2) fewer qualified
workload in Wave 2, could have resulted in costly
candidates will apply for vacant positions that
rework that likely would have disrupted the state’s
will soon be eliminated. The likelihood of greater
financial systems.
turnover and increasing vacancy rates towards
Plan Potentially Shifts Some Project Risk
the end of the project creates greater risk that the
to Wave 4. While we think the modifications to
project will not successfully maintain the proposed
FI$Cal in SPR 5 reduce overall project risk and
schedule and budget in the final wave. Improving
strengthen FI$Cal’s likelihood of success, SPR 5
the project’s ability to retain qualified employees—
potentially shifts some of the implementation
especially towards the end of the project—would
risk from earlier waves to Wave 4. Because SPR 5
mitigate this risk.
deferred the deployment of FI$Cal for the bulk of
Providing Retention Benefit Might Improve
departments until after control agency functions
Retention Efforts. In an effort to mitigate risk
are stabilized, the number of departments included
resulting from staff turnover, the state has provided
in Wave 4 has increased substantially under the
pay differentials for state workers employed by
new schedule. The large size of the final wave
one IT project in the past. In an effort to address
creates greater risk during this wave. The FI$Cal
recruitment and retention issues at SCO’s 21st
Project staff support departments throughout
Century Project (MyCalPays System), the state
implementation as the departments participate in
provided a pay differential to state workers
readiness activities related to changes in business
employed by the project. The state has no data to
processes and the technical aspects of using the
inform decision makers whether or not these pay
FI$Cal systems. This time-intensive engagement
differentials improved the 21st Century Project’s
is necessary to ensure departments are ready for
recruitment and retention efforts. We note that staff
system deployment. Given the breadth of the final
www.lao.ca.gov Legislative Analyst’s Office 9
2014-15 BUDGET
turnover is not considered a primary cause of that its completion. While the state may be limited in
project’s suspension. (Refer to our March 19, 2014 what types of retention benefits it could extend to
report, The 2014-15 Budget: 21st Century Project FI$Cal staff due to civil service rules (for example,
Update, for more information regarding that the state likely could not provide outgoing staff
project’s history.) hiring preferences upon the completion of the
project), we think the administration could explore
LAO Recommendations
various retention benefits. We recommend that
Monitor and Reassess Approach for Wave 4 any retention benefit for FI$Cal staff include an
Through Modified Annual Reporting. Currently, assessment of the benefit program’s impact on the
the project is required to provide the Legislature project’s ability to recruit and retain qualified staff.
an update in February of each year. As part of Measuring the outcomes of a retention benefit
this update, the project is required to provide a would help ensure that the benefit is set at an
discussion of lessons learned and best practices appropriate level and could be used to establish a
that will be incorporated into future changes best practice for future critical IT projects.
in project management activities. We think it is Approve 2014-15 Budget Proposal, While
important for the Legislature to remain apprised Understanding Inherent Project Risk. The
of project developments through the annual Governor’s budget proposal reflects a reasonable
report. However, we think the timing of the annual funding plan to implement the updated project
report to the Legislature should more closely plan (SPR 5). We believe that the time and effort
align with the deployment of FI$Cal waves. As that project staff has spent in updating the project
the February annual report is not available to the plan has reduced overall risk and strengthened
Legislature until seven months after the project’s FI$Cal’s likelihood of success. Nevertheless, FI$Cal
July deployments, too much time may have elapsed involves the development of the most ambitious
for the Legislature to address problems arising and complex IT system in the history of the state
from the deployment of a wave. We therefore and significant risk remains. In its review of the
recommend the Legislature revise the due date for Governor’s proposal and its ongoing oversight
the annual report from February 15 to October 15, of the FI$Cal Project, the Legislature should be
in better time for the administration and aware of and monitor not only the general risk
Legislature to make necessary budgetary changes. inherent in all IT projects but also the shifting of
We also recommend the Legislature direct the some risk to the latter end of the project due to
project after the completion of Waves 1, 2, and 3 to the substantial increase in Wave 4 departments.
identify—as part of the annual report—foreseeable We recommend the Legislature ask the project to
challenges with the implementation of future identify the steps it is taking to address the risks
waves, particularly Wave 4. inherent in the substantial broadening of the scope
Consider Retention Pay Program. Although of Wave 4. Ultimately, we believe that the benefits
it has not been conclusively proven that pay of proceeding with FI$Cal development outweigh
differentials improve staff recruitment and the risk and therefore recommend approval of the
retention on IT projects, we think the Legislature Governor’s budget proposal. Should the project
should consider directing the administration make significant changes going forward, a new
to develop a retention benefit that rewards state budget proposal would be submitted for legislative
workers for staying at the FI$Cal project through review.
10 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
www.lao.ca.gov Legislative Analyst’s Office 11
2014-15 BUDGET
LAO Publications
This brief was prepared by Lourdes Morales and Nick Schroeder, and reviewed by Mark C. Newton. The Legislative
Analyst’s Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This brief and others, as well as an e-mail subscription service,
are available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000,
Sacramento, CA 95814.
12 Legislative Analyst’s Office www.lao.ca.gov