LAO
The 2014-15 Budget: Capital Outlay Support Program Review
Read the report at Legislative Analyst's Office ↗
The 2014-15 Budget:
Capital Outlay
Support Program Review
MAC TAYLOR • L E G I S L A T I V E A N A L Y S T • MAY 14, 2014
SUMMARY
The capital outlay support (COS) program at the California Department of Transportation
(Caltrans) provides the staff support necessary to deliver transportation infrastructure projects
(such as project design and management). In response to the Supplemental Report of the 2013-14
Budget Package, this brief presents our assessment of the existing COS program and makes a series
of recommendations to improve the efficiency and accountability of the program.
While we find that Caltrans has achieved some successes in delivering individual projects and
has made minor improvements to the COS program in recent years, the program generally lacks
accountability and is not operating efficiently. Specifically, we find that the COS program currently
(1) lacks performance data to adequately measure program effectiveness, (2) is experiencing a
substantial decline in workload that will result in significant overstaffing starting in 2014-15,
and (3) allows for limited legislative and external oversight. While the Governor’s budget makes
some proposals that reflect initial steps to address a few of these shortcomings, we find that the
proposals do not adequately address the COS program’s limited legislative and external oversight and
projected overstaffing. For example, the Governor’s proposals would result in the program being
overstaffed by about 3,500 full-time equivalents (FTEs) beginning in 2014-15, at a cost of more than
$500 million.
In view of the above, we make several recommendations to improve the program. First, we
recommend that the Legislature take a multiyear approach to significantly reduce the budget and
staffing levels, beginning with the 2014-15 budget. The freed up funds would then be available for
the Legislature to meet its transportation needs, such as repaving highways. We also recommend
that Caltrans improve its staffing projections and data quality. Lastly, we recommend the Legislature
take steps for the California Transportation Commission (CTC) to perform specific oversight and
project approval functions for projects that currently have limited external oversight.
2014-15 BUDGET
INTRODUCTION
In recent years, the largest share of state deliver some transportation projects. During the
infrastructure spending has been for transportation summer and fall of 2013, representatives from our
improvements and repairs. Caltrans spends much office, DOF, and Caltrans met on a regular basis,
of this funding for projects on the state’s highways. visited several Caltrans district offices, and talked to
Costs for these projects consist of capital outlay numerous stakeholders (such as local transportation
and COS. Capital outlay costs are incurred by agencies, construction contractors, and private
construction contractors for materials and labor consultants). Although the review group collected
to construct a project, while COS refers to the staff information about the program and reached general
support necessary to deliver the project (such as consensus on some initial steps to improve the
project design and management). efficiency and accountability of the COS program,
As part of the 2013-14 budget package, the the group was unable to reach consensus on all of
Legislature adopted supplemental report language the concerns identified in the review and solutions
directing our office and the Department of Finance to address them.
(DOF) to work with Caltrans to review its COS In this brief, we (1) provide an overview of the
program, in order to increase the accountability and COS program, (2) present our assessment of the
efficiency of the program. The review was primarily existing COS program, (3) discuss the Governor’s
prompted by legislative concerns over the years budget proposals related to the program, and
regarding the lack of information to fully support (4) make a series of recommendations to improve
the program’s annual staffing level and budget, as the efficiency and accountability of the COS
well as the increased cost and lengthy schedule to program.
OVERVIEW OF COS PROGRAM
COS Staffing and right-of-way agents. The remainder of state
staff are in the department’s headquarters and are
The 2013-14 budget includes a total of
responsible for coordinating and overseeing the
$1.8 billion to support 10,149 FTE staff resources
COS program, as well as the overall delivery of the
for the COS program at Caltrans. As shown in
department’s infrastructure projects. Specifically,
Figure 1, 90 percent of the program’s staff resources
COS headquarters staff provide guidance to
consist of state staff (meaning Caltrans employees)
Caltrans’ districts on technical issues, allocate
who work both regular time and overtime. The
resources to districts, and track program outcomes.
remainder consists of private consultants. The vast
Over the last several years, budgeted staffing
majority of the state staff is located in Caltrans’ 12
levels for the COS program have declined. As
districts, where they perform technical and project
shown in Figure 2, the budgeted staffing levels
management work to support transportation
declined 23 percent from 2005-06 to 2013-14.
projects for that district. Specifically, each district
While we would expect COS staffing levels to
employs several types of COS staff with specified
correlate with the total amount of funding available
skills, such as environmental planners, engineers,
2 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
for transportation projects in a given year (meaning proceed as planned, the project manager must work
an increase in transportation funding would result with the staff involved to determine what factors
Graphic Sign Off
in an increase in COS staffing), this has not always changed and how best to get the project back on
Secretary
been the case. For example, from 2007-08 through track. In some cases, the project manager may have
2013-14, despite significant increases in state bond to request a change to the project’s cost, scope, or Analyst
and federal transportation funding, COS budgeted schedule. For STIP projects, project managers are MPA
staffing levels actually declined. required to request cost, scope, or schedule changes Deputy
by submitting a project change request (PCR) to
COS Activities
Caltrans headquarters. Staff in headquarters review
The COS program staff provide varying the PCR and provide comments to the director
degrees of support for all state highway projects, of the Caltrans district managing the project.
with most of them in the State Highway Operation
and Protection Program (SHOPP) and the State Figure 1
Transportation Improvement Program (STIP). In State Staff Perform Most COS Work
addition, the COS program supported many of
Consultants
the programs funded by the one-time infusion of
transportation funds provided by Proposition 1B,
Graphic Sign Off
which was approved by voters in November 2006.
(Please see the box on the next page, for more Secretary
detailed information on the state’s major Analyst
transportation infrastructure programs.) MPA
During each phase of a project— State Staff Deputy
environmental, design, right of way, and
construction—Caltrans performs COS activities. Total: 10,149 Full-Time Equivalent Staff
Figure 3 (see page 5) provides some examples of the COS = capital outlay support.
types of COS activities performed in each phase of
a project. For example, in the design phase COS
staff perform engineering analyses and develop
Figure 2
plans and drawings. CTOeSm Bpuladtgee_teLdA SOtRafefp Roersto_usrmce.asi tHaAveR DTeWclOineRdK #140052
Caltrans’ COS program is also responsible
Full-Time Equivalents
for ensuring that the technical work of a project
14,000
led by the department is completed in a manner
12,000
that delivers the project’s planned cost, scope,
10,000
and schedule. In order to achieve this, the
8,000
program employs project managers in each
6,000
Caltrans district office to manage each phase of a
4,000
project. Specifically, project managers coordinate
staff, workload, and funding, and are responsible 2,000
for monitoring and mitigating risks to a project.
05-06 06-07 07-08 08-09 09-10 10-11 11-12 12-13 13-14
When a project experiences challenges (such as a COS = capital outlay support.
delay in environmental permitting) and cannot
www.lao.ca.gov Legislative Analyst’s Office 3
Template_LAOReport_sm.ait ARTWORK #140052
2014-15 BUDGET
Major State Transportation Programs
Currently, the state has two major ongoing programs to fund transportation projects, with
each program having different goals and processes for selecting and delivering projects. These two
programs are:
• State Highway Operation and Protection Program (SHOPP). The SHOPP is the state’s
program for repairing and reconstructing the highway system. Projects generally include
pavement and bridge rehabilitation, major reconstruction, and safety improvements. The
California Department of Transportation (Caltrans) selects SHOPP projects based on
statewide repair and safety needs, and performs project support work through the capital
outlay support (COS) program. Currently, Caltrans spends about $2.3 billion annually
from state fuel excise taxes and federal funds for the SHOPP, making it the state’s largest
transportation program.
• State Transportation Improvement Program (STIP). The STIP is the state’s program for
enhancing and expanding the capacity of state highways. Local road and transit projects
are also eligible for STIP funding. State law allocates 75 percent of STIP funds to counties
by formula for projects selected by the counties. Counties can choose to complete support
work on STIP projects by using Caltrans COS program staff, their own staff, or private
consultants. Caltrans is responsible for selecting projects for the remaining 25 percent of
STIP funds, with the COS program performing most of the support work for these projects.
Currently, Caltrans spends about $700 million for the STIP each year, primarily from state
fuel excise taxes and federal funds.
Recent One-Time Funding Sources. In addition to the ongoing programs identified above, the
state has also received certain one-time state and federal funding to support transportation projects.
For example, Proposition 1B (approved by voters in November 2006) authorized the state to sell
about $20 billion in general obligation bonds to fund a variety of transportation projects, including
those that improve state highways and modernize and expand transit systems. Proposition 1B
created certain new transportation programs, many of which are administered by the California
Transportation Commission. Depending on the type of project and the lead agency for the project,
support work is performed by Caltrans’ COS program, local agency staff, or private consultants.
To date, the majority of Proposition 1B funds have been allocated and most of the projects are
either under construction or completed. In addition, Caltrans received about $2.9 billion for
transportation projects from the 2009 federal American Recovery and Reinvestment Act. These
one-time federal funds generally augmented existing state transportation infrastructure programs,
with a majority of them allocated to projects on local roads and the state’s highways.
4 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
The district director then determines whether to includes a placeholder for the COS program based
approve or reject the PCR. Project managers are on the current-year budget for the program.) The
not required to submit a similar type of PCR for development of this request involves several steps.
SHOPP projects. Currently, the department does First, according to staff in Caltrans headquarters,
not have a statewide process to control and account each district compiles information on all of their
for cost, scope, or schedule changes to SHOPP current and planned projects, including the
projects. It is unclear how each district deals with estimated number of hours needed to complete
such changes. project tasks (such as conducting environmental Graphic Sign Off
In addition to performing the above activities field studies or developing draft design plans) and
Secretary
directly, the COS program oversees state highway the planned start and end date of each task. This
Analyst
projects that are led by local agencies rather than information is then entered into the department’s
Caltrans. These local agencies use their own staff, project management system—Project Resourcing MPA
private consultants, or Caltrans’ staff to perform and Schedule Management (PRSM). Districts Deputy
COS activities. generally perform this step during the fall of
each year for the development of the COS budget
COS Funding Process
request for the coming fiscal year. Based on the
After a project is adopted
into one of the state’s
Figure 3
transportation programs
Examples of COS Work That Occurs in
(such as SHOPP and STIP), Phases of Transportation Infrastructure Projects
Caltrans can begin the
above COS work. Funding to
Environmental
support this work involves
(cid:127) Obtain environmental permits.
the (1) development of the (cid:127) Conduct NEPA and CEQA analysis.
annual budget request
for the COS program,
Design
(2) appropriation of funds in
(cid:127) Perform engineering analyses.
the annual state budget, and (cid:127) Develop plans and drawings.
(3) the allocation of funds to
Caltrans districts.
Right of Way
Caltrans Develops
(cid:127) Identify right-of-way needs.
Budget Request. Each year, (cid:127) Acquire necessary parcels.
Caltrans submits a request to
DOF for resources to support
its COS program, which Construction
(cid:127) Inspect construction work.
is subsequently reflected (cid:127) Review change orders.
(cid:127) Monitor compliance with environmental permits.
in the Governor’s May
Revision to the Legislature
for the upcoming fiscal year. COS = capital outlay support; NEPA = National Environmental Policy Act; and
CEQA = California Environmental Quality Act.
(The Governor’s January
budget proposal essentially
www.lao.ca.gov Legislative Analyst’s Office 5
ARTWORK #140052
Template_LAOReport_mid.ait
2014-15 BUDGET
information entered in PRSM, headquarters staff specific appropriation for each project, but rather
estimate in early January the total level of staff makes a single appropriation to Caltrans to fund
resources that Caltrans will need to work on each the COS work for projects in all transportation
project in the coming fiscal year. From January infrastructure programs. This is primarily intended
to March, headquarters staff review the estimated to provide Caltrans with the flexibility to manage
staffing needs and compare these estimates with changes that can occur on individual projects.
projected workload trends and the number of Caltrans Allocates COS Funds. After funding
positions currently maintained at each district. for the COS program is appropriated by the
Based on the resulting estimate of staff resources Legislature, funds are then allocated by Caltrans
needed, headquarters staff then calculates the level to districts based on their COS resource needs. We
of funding needed to support the program in the note, however, that for many of the transportation
coming year. projects funded with Proposition 1B funds, the
Legislature Appropriates Funds. The CTC—rather than Caltrans—was delegated the
Legislature reviews the annual COS budget responsibility for allocating funding for COS
request in order to determine the level of funding costs. Currently, for projects not funded with
to appropriate for the program in the annual Proposition 1B funds (such as those in the SHOPP
state budget. The Legislature does not provide a and STIP), CTC only allocates project funding for
capital costs.
LAO ASSESSMENT OF COS PROGRAM
As discussed earlier, the Legislature directed Data Challenges Limit Ability to
our office and DOF to work with Caltrans to Evaluate Program Effectiveness
review the accountability, efficiency, and staffing
During our review, we found that workload
resources of the COS program. While we find
and expenditure data used by the COS program
that Caltrans has achieved some successes in
and provided to the Legislature—as part of the
delivering individual projects and has made
program’s annual budget request—contains errors
minor improvements to the program in recent
and appears largely unreliable. In addition, we
years, the COS program continues to experience
found that Caltrans does not collect certain basic
certain challenges. This is because the program
information necessary to review the efficiency and
generally lacks accountability and is not operating
effectiveness of the COS program (such as detailed
efficiently. Specifically, we find that the COS
staffing information). As we discuss below, these
program currently (1) lacks performance data to
data challenges limited our review of the program.
adequately measure program effectiveness, (2) is
experiencing a substantial decline in workload COS Data Appears Largely Unreliable
that will result in significant overstaffing starting
Currently, Caltrans maintains a fairly large
in 2014-15 absent corrective actions, and (3) allows
amount of COS data related to individual projects
for limited legislative and external oversight. Our
that is available to both district and headquarters
specific findings are summarized in Figure 4 and
staff. For example, Caltrans tracks the budget,
described in detail below.
schedule, and past expenditures of each project.
6 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
However, based on our review of the available data, • A small sample of projects was selected by
we find that it appears largely unreliable due to the Caltrans and discussed in depth during
prevalence of errors and inaccuracies. Examples of our district site visits with DOF. For four
poor data quality include: of the sample projects, the department
provided specific data from PRSM (such
• In the workload information that Caltrans
as project cost and level of completion of
provided for 2012-13 and 2013-14, several
current tasks). However, some of the PRSM
projects reported in 2013-14 a lesser
data was inconsistent with the information
amount of total expenditures than what
presented by the project manager for
was reported previously as spent in
each of the four projects. During the
2012-13. Since total expenditures on a
site visits, Caltrans acknowledged that
project would either increase or remain
PRSM contained inaccurate data for
the same for each subsequent year as the
these projects. These inaccuracies include
project is completed, the data appears to
out-of-date information that overstated the
contain errors.
level of staff needed for the project.
• Caltrans reported for 2013-14 that
Potential Reasons for Poor Data Quality.
330 projects have exceeded their approved
Our review identified a couple of potential reasons
COS budget. When we asked Caltrans staff
for the poor quality of Caltrans’ COS data. First,
about these particular projects, they were
the department currently lacks sufficient internal
unable to verify why these projects were
controls to ensure the accuracy of the data in both
overbudget and instead indicated that the
its current and previous project management
data reported might be incorrect.
systems. In other words, Caltrans does not have any
Figure 4
Summary of LAO Findings
9
Data Challenges Limit Ability to Evaluate Program Effectiveness. Workload and expenditure data
used by the capital outlay support (COS) program and provided to the Legislature contains errors and
appears largely unreliable. In addition, the program does not collect certain basic information necessary
to review its efficiency and effectiveness.
9
Program Overstaffed Due to Declining Workload. The COS program is experiencing a substantial
decline in workload that will result in significant overstaffing absent corrective actions.
9
Legislative Oversight Hampered. The annual COS budget request currently limits the ability of the
Legislature to effectively oversee the COS program. This is because the budget request is often based
on poor estimates of projected staffing needs and is not provided to the Legislature in a timely period to
allow for sufficient review.
9
Limited Project-Level External Oversight of the State Highway Operation and Protection Program
(SHOPP). A significant portion of COS staff work on projects in the SHOPP. However, the state lacks
external oversight of these projects. This is because the California Transportation Commission lacks
the authority to approve individual projects and to allocate COS funds for the SHOPP.
www.lao.ca.gov Legislative Analyst’s Office 7
2014-15 BUDGET
statewide processes to regularly update and verify environmental studies) and the extent to
the accuracy of project-level data, such as periodic which such staff currently is on board.
audits of project data. The absence of such internal Caltrans, however, was unable to provide
controls increases the likelihood for inaccurate data this type of information during our review.
to remain in the system. Second, it appears that As such, we were unable to conduct a
project managers at the districts actually have an detailed and conclusive analysis of how the
incentive to sometimes report inaccurate data. As program’s staffing aligns with its various
we learned, this is because in some cases project types of workload—particularly whether
managers intentionally leave incorrect schedules in individual districts currently have too
the system in order to demonstrate that a particular much or too little of certain types of staff.
project will be completed earlier than planned
• Actual Staff Resources Used. Headquarters
(rather than enter into the system an updated
staff is responsible for allocating resources
schedule reflecting an earlier completion date).
to districts based on their estimated
Similarly, the budgets for certain projects may not
staffing needs for each project. However,
be updated to reflect more precise and lower costs,
headquarters staff does not require districts
so that project managers can show that the projects
to report on how the staff resources
were completed below the approved budget. While
provided were actually spent. Without this
it is important for project managers to document
data, the department lacks the information
their project delivery successes, the incentive to
necessary to evaluate the accuracy of the
keep out-of-date information in the PRSM system
staffing requests submitted by districts for
is contributing to the department’s poor data
each project.
quality.
• Initial Project Estimates. A key
Some Essential Information
measurement for evaluating overall
Not Collected or Maintained
effectiveness of the COS program is
In reviewing the data that Caltrans
whether it is delivering projects as they
headquarters currently collects, we found that
were initially approved in terms of cost,
there are certain pieces of data necessary to
scope, and schedule. Such information
evaluate the overall efficiency and effectiveness
would in turn help determine the
of the COS program that are not currently being
reasonableness of the initial estimates
collected. We note that such data would also assist
provided by Caltrans for each project.
Caltrans in managing the program. Specifically,
However, Caltrans does not maintain the
the department does not collect or maintain the
initial project estimates on a long-term
following:
basis. This is because Caltrans overwrites
• Detailed Staffing and Workload Data. the initial project data in its PRSM system
In order to ensure that the COS program when updates to a project are approved and
is appropriately staffed, detailed data is entered into the system.
necessary on the type and number of
• Updated Project Estimates. Similarly,
staff necessary to complete the program’s
updated project estimates that occur
workload (such as a certain number
at various points during a project are
of environmental planners to conduct
8 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
overwritten in PRSM each time the other factors (such as increasing environmental
project’s approved cost, scope, and regulations) can impact workload, a reduction
schedule are changed. Keeping these in funding generally results in a corresponding
estimates would allow for valuable decline in workload.
analysis of projects. For example, the COS Program Will Be Substantially
estimates updated upon completion of the Overstaffed Absent Corrective Actions. The
project’s environmental phase are useful projected 40 percent decline in workload translates
for measuring the overall performance into a corresponding decline of roughly 4,000 FTEs
of Caltrans at delivering projects. This is to the level of COS staff needed. In recognition
because major changes to a project should of a projected workload decline, the Governor
not occur after the completion of the and Legislature reduced the COS program as
environmental phase. part of the 2013-14 budget by 256 FTEs. Despite
this minor reduction in staff, the COS program
Program Overstaffed Due
will be substantially overstaffed in 2014-15 if no
to Declining Workload
additional actions are taken (such as staff layoffs or
a significant infusion of funding for transportation
While Caltrans was unable to provide detailed
infrastructure projects). Specifically, we estimate
staffing and workload data, some limited data was
that the COS program will be overstaffed by
provided that allowed us to make observations
roughly 3,700 FTEs.
about the COS program’s overall staffing levels.
To the extent that the COS program has more
Specifically, we found that the program is
staff than needed to complete available workload,
experiencing a substantial decline in workload
the program would not be expending limited
that will result in significant overstaffing absent
transportation funding in the most effective and
corrective actions.
efficient manner. This is because funding would
COS Program Workload Declining
support unnecessary staff with no immediate
Substantially. Workload for the COS program is
workload rather than supporting additional
directly related to the level of funding available
transportation improvements. For example, in
to develop and construct transportation
recent years, national surveys have found that
infrastructure projects. While ongoing
California has some of the worst pavement
transportation revenues from state and federal gas
conditions in the nation. Such funding could be
taxes have been relatively stable in recent years,
redirected to repair highways and fill potholes. We
the COS program experienced a period of peak
estimate that supporting 3,700 unnecessary staff
workload from 2007-08 through 2013-14, resulting
would cost the state roughly $600 million each
from the infusion of one-time transportation funds
year.
made available from Proposition 1B and the federal
American Recovery and Reinvestment Act. During Legislative Oversight Hampered
this time period, the level of funding available
We also find that the annual COS budget
to award new construction projects averaged
request currently limits the ability of the
$4.4 billion annually. However, Caltrans forecasts
Legislature to effectively oversee the COS program.
that funding available to award new construction
First, the budget request provided is often based on
projects will decline by about 40 percent to
poor estimates of projected staffing needs. Second,
$2.6 billion annually beginning in 2014-15. While
www.lao.ca.gov Legislative Analyst’s Office 9
2014-15 BUDGET
since the request is not provided to the Legislature expended. Specifically, we looked at how many of
until the Governor’s May Revision, it has very the projects in our sample spent within 25 percent
limited time to review the request as part its budget above or below their requested resources. While
deliberations. We discuss each of these concerns in we recognize that actual expenditures could
more detail below. reasonably differ from estimates based on several
factors (such as changing conditions on the
Annual Budget Request Appears to
ground or scope changes to meet environmental
Be a Poor Estimate of Staffing Needs
requirements), we believe that a 25 percent range
As discussed above, Caltrans headquarters does in both directions was a reasonable way to account
not evaluate the accuracy of the data provided by for some of these changes. As shown in Figure 5,
the districts to develop the COS program’s annual we found that 60 percent of the projects in our
budget request. Moreover, the department does not sample overestimated staffing needs by more
sufficiently collect the detailed project information than 25 percent, with 23 percent underestimating
necessary to perform such an analysis for all staffing needs by more than 25 percent.
projects. For example, although Caltrans does We also note that the projects in our sample
collect information from districts on the amount that either overestimated or underestimated the
of dollars expended on COS work, the department level of staffing resources by more than 25 percent
does not collect the amount of FTE resources accounted for the majority of the total requested
that districts spent on each project. This makes staff in the sample, as shown in Figure 6. Projects
it difficult to compare requested FTEs with what that overestimated staff needs by more than
the department actually expended. However, with 25 percent requested funding for a total of 3,168
information the department collects on the dollars FTEs but only expended funding for 1,115 FTEs.
expended on each project, we were able to make Similarly, projects that underestimated staff needs
some general observations regarding the accuracy by more than 25 percent requested 579 FTEs but
of the annual budget request based on the average expended funding for 1,460 FTEs.
cost of one FTE in the COS program. For example, In view of the above, it appears that the
our analysis of a sample of 1,241 projects from annual COS budget request appears to be a poor
the 2,409 projects in the COS program in 2012-13 estimate of actual staffing needs. However, it is
finds that the annual budget request appears to be unclear if the poor estimates are due to a flaw in
a poor estimate of total COS staffing needs. This is the overall budget development process, or because
because Caltrans requested funding for a total of inaccurate data is inputted into Caltrans’ PRSM
4,559 FTEs for the projects in our sample, but only system. Without reasonably accurate estimates,
spent funding for 3,337 FTEs (or 73 percent) of the the Legislature lacks the information necessary to
requested amount. This suggests that even during budget the program at the appropriate level and
the peak workload period the department was hold Caltrans accountable for the funds that are
overestimating its total COS staffing needs in the provided to the COS program.
annual budget request. Late Submittal of Annual Budget Request
In addition to analyzing total COS resources, Limits Legislative Oversight. As discussed above,
we also examined the extent to which the level the Legislature currently receives the annual
of resources requested for an individual project COS budget request as part of the Governor’s
were higher or lower than what was actually May Revision, rather than with the Governor’s
10 Legislative Analyst’s Office www.lao.ca.gov
Graphic Sign Off
2014-15 BUDGET
Secretary
January budget proposal. By submitting the budget the department typically performs both roles, Analyst
request for the COS program so late in the budget resulting in a lack of separation and the type of MPA
process, the Legislature has limited opportunities contractual arrangement necessary to provide a Deputy
to perform oversight of the program as part of its system of checks and balances. Given this lack
budget deliberations. Specifically, only a few weeks of built-in accountability, external project-level
remain from the May Revision until the Legislature oversight of Caltrans is important. With regard
must adopt the annual state budget. Conversely, the to the STIP, a local partner is typically involved
Legislature has several months to request more
information, hold hearings, evaluate, and modify
Figure 5
budget proposals when they are included in the Annual Budget Request Poorly
Estimates Staffing Needs for Most Projects
Governor’s January budget.
Limited Project-Level
Estimated within
External Oversight of SHOPP 25 percent above
or below Graphic Sign Off
Caltrans relies primarily on its own
Secretary
staff to perform much of the COS work on
Analyst
projects, such as designing and engineering
MPA
projects. In contrast, other state departments Underestimated
by more than Deputy
of transportation and other types of 25 percent Overstimated
by more than
infrastructure projects in California use 25 percent
separate entities (such as other public agencies
or private consultants) to perform a large
portion of this type of work.
This approach provides for
Figure 6
effective project controls Majority of Staff Requested Were Not Needed
Template_LAOReport_sm.ait ARTWORK #140052
through a clear contractual
Full-Time Equivalents (FTEs)
arrangement between the
lead agency for the project 3,500
and the entity performing FTEs Used
3,000
FTEs Requested
the work on the project.
2,500
Having a contract and the
separation of roles between 2,000
the two entities creates
1,500
checks and balances, with
the lead agency holding the 1,000
other entity accountable
500
to deliver the promised
project on time, on
Overestimated Estimated within Underestimated
budget, and within scope. by more than 25 percent above by more than
25 percent or below 25 percent
However, under Caltrans’
current delivery model,
www.lao.ca.gov Legislative Analyst’s Office 11
ARTWORK #140052 Template_LAOReport_mid.ait
2014-15 BUDGET
in the management of the project, thereby delivering the planned scope and quality of a
providing greater oversight of Caltrans and SHOPP project on time and on budget.
making state provided external accountability Furthermore, as previously indicated, the
less of a concern. However, as we discuss below, commission allocates funds for the capital
the state currently has limited external oversight costs of individual SHOPP projects and in
of projects led by Caltrans in the SHOPP—the the process is able to provide some oversight
state’s largest transportation infrastructure regarding capital expenditures on projects
program. during construction (such as by controlling
Although CTC could potentially provide what are allowable expenditures). However, the
external oversight of the department’s SHOPP CTC does not allocate funding to Caltrans for
projects, its role as established in current state COS costs on SHOPP projects and is therefore
law limits its ability to provide such oversight. unable to monitor and control allowable COS
First, under existing state law, the CTC does not spending, which comprises a significant portion
have the authority to approve or reject individual of the total cost of projects. In addition, because
SHOPP projects when they are initially the allocation of SHOPP funds happens once a
proposed for funding by Caltrans. Instead, the project is ready to start construction, this process
commission must either approve or reject all does not enable the CTC to conduct oversight
of the SHOPP projects proposed by Caltrans as of SHOPP projects prior to construction. This
a single package. In addition, the commission results in a significant gap in oversight because
usually has very limited information about each many changes can occur prior to the start of
project to make informed decisions about the construction, including cost increases and
entire package. For example, project descriptions schedule delays.
are often vague in scope and location. This As mentioned earlier, the CTC had a greater
lack of authority and information limits the role in oversight of projects authorized in
CTC’s ability to hold Caltrans accountable for Proposition 1B. (Please see the nearby box for
developing reasonable project estimates and detailed information regarding CTC’s oversight
of Proposition 1B projects.)
GOVERNOR’S PROPOSALS
FALL SHORT IN IMPROVING PROGRAM
Based on the information collected during adequately address the COS program’s projected
the review of the COS program that was recently overstaffing.
conducted by our office, DOF, and Caltrans,
Governor’s COS Proposals
the Governor’s budget makes several proposals
regarding the program. While some of the COS Funding and Staffing Request. On
proposals appear reasonable and reflect initial May 1, 2014, the Governor submitted a request
steps to address a few of the shortcomings we to the Legislature for a total of $1.7 billion and
discussed above, we find that the proposals do not 9,894 FTEs for the COS program in 2014-15. This
12 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
Increased Oversight Provided for Proposition 1B Projects
While the California Transportation Commission (CTC) has a minimal role in oversight of
the State Highway Operation and Protection Program (SHOPP), CTC was authorized to perform
increased oversight of the Proposition 1B projects (including SHOPP projects specifically supported
with Proposition 1B bond funds). Specifically, for several of the largest Proposition 1B programs,
CTC had a substantial role in the oversight of individual projects and the allocation of state funds
for both capital and capital outlay support costs. Because CTC had the authority to evaluate each
Proposition 1B project when it was initially proposed, CTC staff were able to obtain detailed project
information from Caltrans to determine if the initial cost, scope, and schedule for projects were
reasonable. The CTC then entered into agreements with Caltrans that specified the level of bond
funding CTC would commit to each project and the specific scope and schedule of work that
Caltrans would complete. Any deviations from the agreed upon cost, scope, and schedule required
CTC approval. In addition, having the responsibility for allocating funding for both capital and
support costs provided CTC a greater level of control over project spending. As projects progressed,
CTC was able to limit project changes and ensure that the full project scope was delivered.
May 1 request reflects the Governor’s plan going in 2014. The workload projections would
forward to propose an annual COS budget two show the type of work planned for each
weeks prior to the May Revision. The revised level district, including environmental, design,
for 2014-15 is $27.1 million and 258 FTEs less than construction, right of way, surveys, and
the level in 2013-14, which amounts to a roughly engineering services. The department
3 percent decline. Specifically, the May 1 request would also compare this estimated
reflects the reduction of 243 state staff through workload to the type and location of the
attrition, reduction of overtime by 12 FTEs, and staff currently on board. At the time of this
reduction of consultants by 3 FTEs. analysis, Caltrans had not provided the
Proposed Improvements to COS Program. In above staffing and workload projections.
addition, the Governor’s January budget includes
• Conduct Hindsight Review on a Sample of
several proposals intended to improve the COS
Projects. The Governor also proposes that
program, based on the recent review of the COS
Caltrans monitor the accuracy of the COS
program. These proposals primarily include
budget request by annually evaluating a
changes that Caltrans has agreed to implement and
sample of projects from the prior year. In
do not require any specific budgetary changes. The
the current year, DOF randomly selected
Governor’s major COS proposals are to:
95 projects from the 2013-14 budget request
• Require Detailed Staffing and Workload
(excluding projects that requested fewer
Projections. The Governor proposes that
than one FTE). For each project, Caltrans
Caltrans annually develop a three-year
compared budgeted amounts for COS
COS workload projection and provide this
to actual COS expenditures. Caltrans
to the Legislature each May 1 beginning
www.lao.ca.gov Legislative Analyst’s Office 13
2014-15 BUDGET
submitted this hindsight review to our projections, evaluate the actual use of COS
office on May 2, 2014. According to the resources on a sample of projects, and develop
department, it expended 68 percent of a plan to improve data quality. While these
all the FTEs requested for the 95 sample proposed improvements are a step in the right
projects. direction, they are unlikely to result in major
improvements to the COS program in the near
• Develop Quality Management Plan. In
term. For example, while the Governor proposes
addition, the Governor proposes that
to improve the quality of the COS program’s data,
Caltrans develop and implement a quality
these improvements could take many years before
management plan that would help ensure
they result in more accurate workload estimates.
the quality of the project data used for the
In addition, the Governor proposes to evaluate the
COS program. In developing the plan,
actual use of COS resources on only a small sample
the administration requests that Caltrans
of projects, rather than all projects in the program.
consider specifying that project managers
More importantly, the Governor’s proposals
are responsible for updating project data
do not address the issue of significant overstaffing
in PRSM and requiring them to ensure
in the COS program. As described previously,
on at least a monthly basis that the data
funding data from Caltrans shows that due to a
is accurate. The Governor also requests
substantial workload decline, the COS program
that Caltrans consider requiring district
will be overstaffed by roughly 3,700 FTEs
managers to establish quality control
beginning in 2014-15. However, for 2014-15 the
procedures to ensure project data is
Governor only proposes a reduction of 258 FTEs.
up-to-date in PRSM, as well as requiring
Thus, absent a significant, unexpected increase
COS headquarters staff to conduct monthly
in transportation funding for new projects, the
oversight of districts.
Governor’s proposal would result in COS program
overstaffing of about 3,500 FTEs beginning in
Governor’s Proposals Do Not
2014-15, at a cost of more than $500 million. One
Address Projected Overstaffing
reason that the Governor’s proposal is not aligned
The Governor’s proposals would make some with actual staffing needs is that it continues
minor improvements to the COS program by to use the same types of data and estimating
having Caltrans provide more detailed workload methodology that we found to overstate the level of
staff resources needed.
RECOMMENDATIONS TO IMPROVE COS
PROGRAM ACCOUNTABILITY AND EFFICIENCY
In view of our findings that the COS program significant reductions to the size of the program
continues to face challenges that limit the and increases in the level of external oversight are
program’s efficiency and accountability, we make necessary in order to ensure the state’s limited
several recommendations to the Legislature to transportation funds are used wisely. Our specific
improve the program. Specifically, we find that recommendations are described below.
14 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
Align Staffing Levels With Projected Workload (3) projected imbalances between existing staff and
workload, and (4) how Caltrans will use staffing
Begin to Reduce Staffing Levels. As indicated
strategies and workload management tools to align
above, our analysis finds that the COS budget
staff resources with workload.
request overbudgets the program by roughly 3,500
Take Steps to Improve Data Quality.
FTEs and more than $500 million beginning in
Improving the quality of Caltrans’ data will help
2014-15. While it would be difficult to completely
the department to develop better staffing and
address such a substantial problem in one year,
workload estimates in the future. The Governor
not addressing the issue at all will result in the
makes two proposals to improve data quality—the
inefficient use of transportation funding. In order
development of a data quality management plan
to balance the need for a thoughtful approach to
and a hindsight review of a sample of projects.
reducing the size of the program with the state’s
In order to ensure that the Governor’s proposals
need to spend transportation funds efficiently,
address the problems we identified with the
we think that a multiyear approach to reducing
department’s workload data, we recommend that
the COS budget and staffing levels is appropriate.
the Legislature adopt legislation to:
Accordingly, we recommend that the Legislature
take a first step to address this overstaffing problem • Specify that the proposed quality
in the 2014-15 budget by significantly expanding management plan include requirements to
the Governor’s proposed reduction of the COS (1) ensure that PRSM data is up to date and
program. For example, an additional reduction of accurate, (2) ensure consistent development
1,750 FTEs would address half of the problem. The of project budgets across districts,
“freed up” funds (roughly $250 million) would then (3) evaluate project data for accuracy, and
be available in future years for the Legislature to (4) evaluate employee time charging for
meet its transportation priorities, such as pavement accuracy. Moreover, in order to ensure that
maintenance. In order to determine how to best the plan is developed in a timely manner
address the remaining overstaffing after 2014-15, and to facilitate oversight, we recommend
we recommend below that the Legislature build that the Legislature require Caltrans to
upon the Governor’s proposals related to staffing submit a copy of the plan to the appropriate
projections, data quality, and the timing of the legislative committees by January 10, 2015.
annual COS budget request. In addition, we recommend that the
Require Staffing Plan. Better information Legislature require Caltrans to maintain
about the COS program’s staffing and workload in PRSM the initial project estimates
trends would help the Legislature make the and updated project estimates upon the
additional necessary reductions and appropriately completion of the environmental phase.
budget the program on an ongoing basis. This will ensure that sufficient data is
Accordingly, we recommend that the Legislature collected to assess the effectiveness of the
adopt legislation requiring Caltrans to annually COS program.
develop a multiyear staffing plan and submit the
• Expand the hindsight review of the annual
plan annually to the Legislature beginning on
COS budget request to include all projects,
January 10, 2015. Specifically, such a plan should
rather than just a sample of 95 projects.
provide for each district: (1) workload projections
Caltrans should submit the analysis
by type of workload, (2) staff on board by type,
www.lao.ca.gov Legislative Analyst’s Office 15
2014-15 BUDGET
annually with the budget request. This information about each project. Accordingly, we
more robust analysis would provide the recommend that the Legislature require CTC
Legislature with the information necessary to approve the proposed cost and schedule of
to understand the level of accuracy of each SHOPP project to ensure that the estimates
Caltrans’ staffing estimates and associated are reasonable for the identified transportation
budget request. need and project scope selected by Caltrans.
This change would ensure that proposed SHOPP
Require Earlier Submittal of Annual Budget
projects are based on reasonable estimates before
Request. As indicated above, the Governor’s plan
state transportation funds are committed to such
going forward is to propose an annual COS budget
projects. In addition, we recommend that deviations
on May 1 of each year—two weeks earlier than past
from the approved cost, scope, and schedule for
practices of including it as part of the May Revision.
SHOPP projects also be approved by CTC to
However, we find that the proposed timeline of
facilitate accountability throughout each phase of a
two weeks earlier still significantly limits the
project.
Legislature’s ability to adequately perform oversight
Require CTC to Allocate COS Funds for
of the COS program and make the changes to the
SHOPP. Since CTC currently only has the authority
program necessary to bring staffing levels in line
to allocate funding for the capital costs of SHOPP
with workload. Accordingly, we recommend that,
projects, no entity outside of Caltrans monitors or
beginning with the 2015-16 budget, the Legislature
controls COS costs on SHOPP projects. As such,
adopt statute requiring the administration to
we recommend that the Legislature enact statute
provide the annual COS budget request as part of
requiring CTC to allocate funds for each phase of
the Governor’s January budget proposal and update
a SHOPP project, including funding for COS costs.
the request as necessary as part of the Governor’s
Such a change would help create a more effective
May Revision.
and transparent system of checks and balances on
Increase CTC Oversight for SHOPP Projects Caltrans COS spending.
Require Caltrans to Provide Specific Data to
In view of the lack of external oversight for
CTC. In order for CTC to perform the oversight
SHOPP projects, we recommend that the Legislature
and approval functions that we recommend above,
take steps to establish an external framework for
the CTC will need to rely on data from Caltrans.
holding Caltrans accountable for the delivery of
Accordingly, we recommend that the Legislature
such projects. Specifically, we recommend below
require Caltrans to provide the CTC with any
that the Legislature take steps for CTC to perform
project information that the CTC or its staff thinks
specific oversight and project approval functions
is necessary for the oversight of Caltrans and the
for SHOPP. As we discussed earlier, SHOPP is
SHOPP projects.
the largest ongoing state transportation program
Require CTC to Report on Caltrans’ Project
and has the least amount of external and internal
Delivery Performance. With the changes we
oversight. In contrast, most STIP projects receive
recommend, we think CTC would be well-suited
additional oversight from a local partner.
to monitor and report on Caltrans’ overall
Require CTC to Review and Approve
performance at delivering projects. As such, we
Individual SHOPP Projects. As described above,
recommend requiring CTC to include in its annual
CTC can only approve or reject the entire program
report to the Legislature information on Caltrans’
of SHOPP projects and must do so based on limited
16 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
performance at delivering SHOPP projects, such staff resources to complete such workload. Thus,
as whether projects are completed within initial we recommend that the Legislature require CTC
estimates and within the estimates updated after to report at budget subcommittee hearings on
completion of the environmental phase. (Under the number and classification of staff it would
current state law, CTC is required to annually need in order to perform increased oversight for
report to the Legislature on the status of the state’s SHOPP projects as we recommend. While our
transportation programs.) recommendations might result in minor increased
We acknowledge that our recommendations state administrative costs in the short run, we
above would result in additional workload for think that this level of oversight would improve the
CTC and that CTC would likely need additional overall accuracy of Caltrans’ estimates and limit
unjustified cost increases on SHOPP projects.
www.lao.ca.gov Legislative Analyst’s Office 17
2014-15 BUDGET
18 Legislative Analyst’s Office www.lao.ca.gov
2014-15 BUDGET
www.lao.ca.gov Legislative Analyst’s Office 19
2014-15 BUDGET
LAO Publications
This brief was prepared by Jeremy Fraysse and Jessica Peters, and reviewed by Anthony Simbol. The Legislative Analyst’s
Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This brief and others, as well as an e-mail subscription service,
are available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000,
Sacramento, CA 95814.
20 Legislative Analyst’s Office www.lao.ca.gov