LAO
The 2016-17 Budget: Evaluating FI$Cal
Read the report at Legislative Analyst's Office ↗
The 2016-17 Budget:
Evaluating FI$Cal
M AC TAY LO R • L E G I S L A T I V E A N A L Y S T • M ARC H 2 016
2016-17 BUDGET
2 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
EXECUTIVE SUMMARY
An Integrated Financial Management System. Over the last several years, the administration
has been engaged in the design, development, and implementation of the Financial Information
System for California (FI$Cal) Project. This information technology (IT) project will replace the
state’s aging and decentralized IT financial systems with a new system integrating state government
processes in the areas of budgeting, accounting, cash management, and procurement. Since the
project began, it has changed in scope, schedule, and cost from what was initially anticipated. These
changes have been documented in special project reports (SPRs). The FI$Cal Project is currently
operating under its fifth SPR. While the project experienced early successes, subsequent challenges
have caused the project to fall behind schedule. Ultimately, these challenges caused the project
to deviate from the current SPR significantly enough to trigger the need for a new project plan—
SPR 6—on which the Governor’s 2016-17 budget proposals are based.
Governor’s 2016-17 FI$Cal Budget Proposals. The Governor’s 2016-17 budget includes two
FI$Cal-related proposals: the first allows the project to implement the changes proposed in SPR 6
and the second establishes a new state department to maintain and operate the FI$Cal System. The
proposed changes to the project reflected in SPR 6 result in a 24-month schedule extension and an
increase in the project cost (relative to SPR 5) by $237 million ($125 million General Fund). This
brings the total cost of the project to $910 million ($494 million General Fund). The administration
indicates that the budget proposals reduce the overall risk associated with the implementation of
FI$Cal and sets the foundation for maintaining and operating the FI$Cal System once it is complete.
The total cost for the project in 2016-17 is $135 million ($96.3 million General Fund).
Governor’s Proposed Project Changes Are Reasonable, but Project Risk Remains and Additional
SPR Likely. We find that the Governor’s budget proposal to implement the changes proposed in SPR 6
reflects a reasonable plan to implement the remaining functions and departments in FI$Cal. We therefore
recommend approval of this component of the Governor’s budget proposal. However, we note that
the FI$Cal Project involves the development of an extremely ambitious and complex IT system and
significant work remains before the system is fully implemented. Given the scope of the remaining work
and signals from oversight entities that some project activities continue to track behind schedule, we think
a future SPR is likely that would further extend the project schedule and increase costs. Should the project
make significant changes going forward, a new budget proposal would be submitted for legislative review.
Regardless of Entity Selected for Maintenance and Operation (M&O), Accountability Should
Be Strengthened. As for the administration’s proposal to establish a new state department for M&O
of the FI$Cal System, we agree with the administration that an entity is necessary to maintain and
operate FI$Cal. It is unclear to us, however, whether the establishment of a new department is the
best way to fulfill this function. Various options of administrative structures for maintaining and
operating the FI$Cal System are available for legislative consideration, each with its own potential
benefits and costs. Regardless of the entity ultimately selected for M&O, we think that actions are
needed to strengthen the Legislature’s ability to hold FI$Cal leadership accountable. We provide
options to the Legislature for doing this.
www.lao.ca.gov Legislative Analyst’s Office 3
2016-17 BUDGET
4 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
INTRODUCTION
Since 2005, the administration has been California Department of Technology (CDT) in
engaged in the design, development, and January 2014. While the project experienced early
implementation (DD&I) of the Financial successes, subsequent challenges have caused the
Information System for California (FI$Cal) Project. project to fall behind schedule. Ultimately, these
The FI$Cal Project is extremely ambitious and challenges caused the project to deviate from the
complex, resulting in it being the most costly current SPR significantly enough to trigger the
state information technology (IT) undertaking need for a new project plan—SPR 6—on which the
ever. The FI$Cal Project replaces the state’s aging Governor’s 2016-17 budget proposals are based.
and decentralized IT financial systems, with a In this report, we describe the FI$Cal Project,
new system that will integrate state government provide an update on the project’s status, and
processes in the areas of budgeting, accounting, describe the events that triggered the development
cash management, and procurement. Since 2005, of a new SPR. We also describe the Governor’s
the project has changed in scope, schedule, and cost 2016-17 budget proposals to: (1) allow the project
from what was initially anticipated. These changes to implement the changes proposed in SPR 6 and
have been documented in special project reports (2) establish a new state department to maintain
(SPRs). The FI$Cal Project is currently operating and operate the FI$Cal System. Finally, we make
under its fifth SPR, which was approved by the associated findings and recommendations.
OVERVIEW OF THE FI$CAL PROJECT
An Integrated Financial Management System. standardize the state’s financial practices. The
Over the last several years, the administration integrated system will be utilized in some way by
has been engaged in the DD&I of the FI$Cal every state department, the Legislature, and the
Project—an IT project that replaces the state’s public, allowing greater transparency of the state’s
aging and decentralized IT financial systems with financial data and management. Such transparency
a new system that will integrate state government currently does not exist given the state’s fractured
processes in the areas of budgeting, accounting, financial management infrastructure.
cash management, and procurement. The system Project Has Evolved. The planning for the
will eliminate the need for over 2,500 department- FI$Cal Project began in 2005 when the Department
specific applications and enable the state financial of Finance (DOF) proposed an IT project that
systems and workforce to function in an integrated would implement an internal financial system for
environment. The FI$Cal System will also automate the department. The Budget Information System, as
processes that are currently highly manual, the system would have been called, was envisioned
minimize manual reconciliations among control to better meet DOF’s budget development and
agencies and various separate financial systems, administrative needs. In 2006, the administration
make information more readily available to the proposed an updated project plan that significantly
public and the state’s business partners, generally changed the scope and governance of the project.
improve tracking of statewide expenditures, and Rather than building a new system exclusively for
www.lao.ca.gov Legislative Analyst’s Office 5
2016-17 BUDGET
DOF, the administration recommended that— among these partner agencies and other entities
because a majority of state departments were reliant with a formal role in the FI$Cal Project—known
on aged and inadequate technology—there was a collectively as “stakeholders” for purposes of this
need to modernize and replace the state’s entire analysis.
financial management infrastructure. The updated Project Governance Structure. The objective of
project plan proposed increasing the scope of the the FI$Cal Project’s governance plan is to delineate
project to include developing a single integrated the responsibilities and decision-making authority
financial management system for the state. The for key project stakeholders. We discuss the roles
project was renamed FI$Cal and would be managed and decision-making authority of key stakeholders
by a partnership of four control agencies that would below.
comprise the project’s steering committee. After
• Steering Committee. The Steering
continued planning and a lengthy procurement
Committee is the main governing body
that used an innovative procurement approach, a
for the FI$Cal Project. The Steering
contracted vendor—Accenture PLC—was selected
Committee has primary jurisdiction over
in June 2012 to customize existing off-the-shelf
decisions that affect the project’s scope,
software to address the state’s financial management
schedule, and/or cost. The committee is
needs. Since 2012, the project has periodically
comprised of the project sponsor (who
updated the project scope, schedule, and/or cost
also serves as the Chair of the Steering
from what was anticipated when the state initially
Committee, currently filled by DOF’s
contracted with the vendor. These updates have led
Chief Operating Officer), representatives
to schedule extensions and cost increases, but also
from each of the four partner agencies
modifications that have mitigated project risk and
(DOF, SCO, STO, and DGS), and a state
made it more likely that the project will ultimately
employee who represents the interest of all
meet its objectives. See Figure 1 for a description of
state departments. Additionally, the CDT
the evolution of the scope, schedule, and cost of the
is a nonvoting member of the Steering
project since it was proposed in 2005. (Also, refer
Committee. The committee operates under
to our April 30, 2012 report, The 2012-13 Budget:
a consensus decision-making model. If
Evaluating FI$Cal, for a more comprehensive
the committee cannot reach consensus,
description of the project’s history.)
the objector may choose to recuse himself
Four Control Agencies Manage Project. The
or herself, in which case the committee
project is managed by a partnership of four control
can move forward. Alternatively, the
agencies—DOF, State Controller’s Office (SCO),
governance structure provides for a process
State Treasurer’s Office (STO), and the Department
to escalate issues for which the Steering
of General Services (DGS). These partner agencies
Committee is unable to reach consensus.
have unique constitutional and/or statutory
responsibilities over the state processes that will be • Project Directorate. While the Steering
integrated through FI$Cal—budgeting, accounting, Committee is the main governing body for
cash management, and procurement. State law the project, issues that cannot be resolved
mandates these partner agencies to collaborate in by the Steering Committee are elevated
the development of FI$Cal. The project developed to the Project Directorate—the highest
a governance plan to guide the relationships decision-making authority for the project.
6 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
Figure 1
Evolution of the FI$Cal Project Scope, Schedule, and Cost
(In Millions)
Final
Total Estimated Implementation
Project Plan Project Cost Date Summary of Project Plan
Initial Project $138 July 2011 The initial IT project was much more modest in scope than the current
Plan (FSR) project. The Budget Information System, as the project was then
July 2005 known, was envisioned to better meet DOF’s budget development and
administrative needs.
SPR 1 $1,334 June 2015 The administration realized there was a need to modernize and replace
December 2006 the state’s entire financial management infrastructure. SPR 1 proposed
increasing the scope of the project to include developing a single
integrated financial information system for the state. The project
would integrate the budgeting, accounting, cash management, and
procurement functions of the state. Four partner agencies were
identified—DOF, SCO, STO, and DGS—and the project was renamed
FI$Cal. The SPR extended the schedule by four years and increased
the cost by nearly $1.2 billion.
SPR 2 $1,620 June 2017 SPR 2 analyzed advantages and disadvantages of various FI$Cal
December 2007 alternatives but proposed maintaining the project’s expanded scope
to integrate the state’s financial management processes. The SPR
extended the schedule by two years and increased the cost by nearly
$300 million, relative to SPR 1.
SPR 3 Unspecified Unspecified SPR 3 established the use of a multistage procurement approach. The
November 2009 multistage procurement strategy would assist the project in eliciting
more qualified vendors and more responsive proposals for building
the FI$Cal System. The total cost and schedule for the project was left
unspecified. At the conclusion of the procurement, when the software
application and vendor would be selected, the project would submit
SPR 4.
SPR 4 $617 July 2016 SPR 4 updated the project cost and schedule based on the contract with
March 2012 the selected vendor. The total project cost for the FI$Cal System was
estimated at about $620 million, about $1 billion less than estimated
in SPR 2. The cost reduction is attributed to (1) updated estimates
and (2) the move to a more phased implementation approach that
resulted in lower overall project costs through reduced risk to the
vendor and lower state staffing costs. The system would be completely
implemented in July 2016.
SPR 5 $673 July 2017 SPR 5 made various changes to the project’s implementation approach
January 2014 to reflect lessons learned over the two years since the vendor was
selected and the development of the system began. The SPR resulted
in a 12-month schedule extension and increased the total project cost
by $56 million, relative to SPR 4.
SPR 6 $910 July 2019 SPR 6 made various changes to the project’s implementation
February 2016 approach to reflect lessons learned since SPR 5. SPR 6 resulted in a
24-month schedule extension and increased the total project cost by
$237 million, relative to SPR 5.
Fi$Cal = Financial Information System for California; FSR = Feasibility Study Report; IT = information technology; DOF = Department of Finance; SPR = Special Project Report;
SCO = State Controller’s Office; STO = State Treasurer’s Office; and DGS = Department of General Services.
www.lao.ca.gov Legislative Analyst’s Office 7
2016-17 BUDGET
The Project Directorate includes the FI$Cal Service Center (FSC) Maintains and
Director of Finance, the State Controller, Operates System. There are a total of 195 FI$Cal
the State Treasurer, and the Director of Project staff who support various functions—one
DGS. Like the Steering Committee, the of which is the FSC. The center, operated by a
directorate operates under a consensus combination of state staff and vendor staff, was
decision-making model. established in July 2013—after the first system
functions of the FI$Cal Project were implemented
• Project Leadership Team. The Project
in a small number of departments—to (1) perform
Leadership Team is led by the Executive
maintenance and operation (M&O) for the FI$Cal
Partner (like an executive officer) and is
System, (2) provide support services to the users of
comprised of state staff who (1) review the
the system, and (3) manage internal administrative
project’s performance, (2) make day-to-day
functions. Under SPR 5, the FI$Cal Project and FSC
decisions on issues affecting the project
operate simultaneously during the implementation
or escalate issues to higher levels of the
of the system. The FSC will incrementally
governance structure if the issue exceeds
assume additional responsibility as functions and
the Project Leadership Team’s authority,
departments come on line. Once the system is fully
and (3) oversee all FI$Cal Project staff. The
implemented, the project will end and the FSC will
Executive Partner is also the key advisor
assume complete responsibility on an ongoing basis
to the Steering Committee, oversees the
for maintaining and operating the FI$Cal System.
development of the system, and advocates
The FSC is also managed through a partnership
for statewide support of the project.
among the four control agencies—DOF, SCO, STO,
and DGS. The state’s financial management policies
• Project Oversight Entities. The project
remain within the respective purview of the
is independently overseen by CDT and
partner agencies, while the FSC operates the system
a third-party technical consultant.
in accordance with the policies set by the partners.
These entities present their findings
and recommendations to the Steering
Committee.
CURRENT PROJECT STATUS
Information technology projects often change SPR 5, which was approved by CDT in January
in scope, schedule, and/or cost from what was 2014. The associated budget proposal was approved
initially anticipated because of the complexity by the Legislature as part of the 2014-15 Budget
of such projects. Significant changes to state Act. It calls for the implementation of the FI$Cal
IT projects are documented in SPRs. At a high System in a series of “waves” that add departments
level, SPRs document a project’s change in and functionality—specific tasks related to
scope, schedule, and/or costs to reflect updated budgeting, accounting, cash management, and
information. The SPRs are prepared by the project procurement—to FI$Cal incrementally over time.
and submitted to CDT for review and approval. (When a department joins FI$Cal, it will be able to
The FI$Cal Project is currently operating under access all functionality that has been implemented
8 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
to date. As additional functionality is implemented, ultimately caused the project to deviate from the
it will become available to all departments using schedule proposed in the most recent project
FI$Cal.) Specifically, SPR 5 calls for the system plan—SPR 5. Compared with Pre-Wave, Wave 1
to be rolled out through a “Pre-Wave” planning and Wave 2 deployed significantly more complex
phase followed by four implementation waves over functions to a larger number of departments.
five years. While the project experienced early Wave 1. The fifth SPR called for Wave 1 to
successes, subsequent challenges have caused the implement in July 2014 a significant portion
project to fall behind schedule. Ultimately, these of FI$Cal’s budget functions and some of the
challenges caused the project to deviate from the accounting, cash management, and procurement
current SPR significantly enough to trigger the functions to the four partner agencies and to
need for a new project plan—SPR 6—on which the a limited number of other state departments,
Governor’s 2016-17 budget proposals are based. including the State Board of Equalization
Before describing the Governor’s budget proposals, (BOE) and the Department of Justice (DOJ).
we provide an update on the project’s status and Instead, the FI$Cal Steering Committee made
describe the events that triggered the development several significant last minute changes to the
of a new SPR. implementation approach just prior to Wave 1
going live that resulted in a substantially reduced
Pre-Wave Successful
number of departments—and therefore a reduced
The project deployed Pre-Wave—the first of the number of system users—and the deferral of
five implementation waves—in July 2013. Pre-Wave certain functions and departments to later waves.
deployed a portion of the FI$Cal procurement Below, we describe the primary reasons for the
functions to a small subset (five departments) of delay in the implementation of Wave 1.
Wave 1 departments. The FSC—discussed earlier—
• Technical Difficulties Caused Deferral of
was established with Pre-Wave deployment.
Some Functions to Series of Subsequent
All components of Pre-Wave were deployed on
Small Deployments—Wave 1.x. Because
schedule and without incident.
of technical difficulties with completing
Although the scope of Pre-Wave was narrow
certain FI$Cal functions, the project
and only a few departments were impacted, the
moved the implementation of certain
lessons learned during this planning phase were
functions from Wave 1 to a series of
of great value to the project and informed future
subsequent small deployments, collectively
decisions. The activities necessary for deploying
known as Wave 1.x. Wave 1.x included
FI$Cal to departments are largely consistent across
functions necessary for the development
the various waves. These activities include engaging
of the state’s budget that were not
departments, converting data from current
immediately necessary in July 2014 when
technology systems to FI$Cal, training end users,
Wave 1 was scheduled for implementation.
and testing the system. Pre-Wave was designed to
The Wave 1.x functions were deployed
serve as a pilot to test these procedures.
in 2014-15. The FI$Cal System was
successfully used in the development of the
Wave 1 and Wave 2 Encountered Road Bumps
2015-16 budget, making FI$Cal the budget
Despite the lessons learned from Pre-Wave,
system of record for the state. Despite these
subsequent waves encountered road bumps that
successes, additional modifications and
www.lao.ca.gov Legislative Analyst’s Office 9
2016-17 BUDGET
enhancements are planned to improve anticipated. The SCO and STO began
usability and end-user satisfaction. using FI$Cal accounting functions
in December 2014 and August 2015,
• Departments Required More Support
respectively. Finally, implementation of
Than Anticipated. Even though the
the system at the California Department
number of system users was reduced
of Aging was deferred by one year because
significantly—by deferring some
the department had not completed tasks
departments to later waves—Wave 1
necessary to transition to FI$Cal.
departments required more support
Wave 2. The fifth SPR called for Wave 2
than anticipated. Most significantly,
to implement a significant portion of FI$Cal’s
Wave 1 departments needed support
procurement functions and some of the budgeting,
with month-end and year-end close-out
accounting, and cash management functions in
activities associated with the new
July 2015 to about 50, mostly small, departments.
accounting functions. The project
Although the development of these functions was
provided additional training sessions as
falling behind schedule for many months leading
well as individual support to the Wave 1
up to July 2015, the project was optimistic that it
departments. As of February 2016, all
would be able to catch up and meet the scheduled
Wave 1 departments have completed
milestone. When the project was ultimately unable
year-end close-out activities for 2014-15.
to catch up, the Steering Committee made a last
• Various Challenges Caused Project to minute decision to split Wave 2 into two different
Defer Several Departments and Certain releases, scheduled for August 2015 and December
Functions to Later Waves. The project 2015. The primary reasons for the delays in Wave 2
went live in July 2014 with only a portion were:
of the planned Wave 1 departments and
• Concurrent and Competing Priorities
functions. The deployment of FI$Cal’s
Created Schedule Delays. The project
accounting function at BOE and DOJ was
planned to transition staff tasked with
deferred for three years. Both departments
Wave 1 activities to Wave 2 activities
cited that the workarounds that the vendor
following the deployment of Wave 1 in July
proposed for known system defects were
2014. The unanticipated workload resulting
too time consuming. The intent of the
from the Wave 1 road bumps created
deferral was to allow time for the defects
concurrent and competing priorities. The
to be resolved. Additionally, a decision
ongoing Wave 1-related work eroded the
was made to delay the implementation
availability of staff time originally set aside
of the accounting functions for SCO
for Wave 2-related activities and caused the
and STO in order to perform additional
project to miss milestones leading up to the
testing. Although the project and the two
July 2015 Wave 2 deployment.
departments had tentatively anticipated
completion of the additional testing • Testing Delays and Requested
and deployment of FI$Cal’s accounting Enhancements Caused Splitting of Wave 2
function to SCO and STO by September Into Multiple Parts. In June 2015, testing
2014, testing continued longer than delays and requests for enhancements
10 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
to procurement functions caused the all aspects of FI$Cal to the approximately
Steering Committee to approve splitting 70 remaining departments in July 2017.
the implementation of Wave 2 into two According to the project’s oversight
separate and delayed releases. The first entities, Wave 4 activities were tracking
release was scheduled for August 2015 and three months behind the schedule provided
rolled out the budgeting, accounting, and in SPR 5 as of November 2015. Given the
cash management functions. The second domino effect prior delays have had on the
release was scheduled for December 2015 project’s schedule, further delays in Wave 4
and rolled out the procurement functions. seem likely.
As in Wave 1, some departments were
Large Number of Departments in Final Wave
deferred to later waves, resulting in Wave 2
Continued to Create Risk. The fifth SPR deferred
bringing 45 of the roughly 50 originally
the implementation of FI$Cal for the bulk of
planned departments onto the FI$Cal
departments until the last wave—Wave 4. Given
System.
the large quantity of departments transitioning
onto FI$Cal in the final wave, we questioned in
Challenges in Prior Waves, Issues in Upcoming
our analysis of SPR 5 whether the project’s staffing
Waves Spur Development of SPR 6
would be at an adequate level to actively engage
Past Project Road Bumps Affect Schedule. departments as needed for Wave 4 to succeed
The FI$Cal Project—as proposed in SPR 5—has within the proposed time frame. (Please refer to
two remaining waves to implement (Wave 3 and our March 26, 2014 report, The 2014-15 Budget:
Wave 4). The project anticipated rolling out these Evaluating FI$Cal Project Plan, for additional detail
waves in July 2016 and July 2017. However, the regarding our Wave 4 concerns.) Additionally, since
delays in prior waves have created significant the approval of SPR 5, the Steering Committee
schedule delays for future waves and have made the has taken several actions to defer additional
time line proposed in SPR 5 unrealistic. departments (such as BOE and DOJ) until the final
wave of the project. While deferring deployment
• Wave 3 Delays. Under SPR 5, the third
when a department is not ready is prudent, this
wave would implement the most significant
action has grown the already large, final wave.
portion of FI$Cal’s accounting and cash
Moreover, the project has witnessed firsthand that
management functions to two large
departments require intensive support following
departments. Wave 3 has fallen significantly
their transition onto the FI$Cal System. The
behind schedule because the project
time-intensive engagement is necessary to ensure
redirected resources needed for Wave 3
departments are ready to use the system when
development to instead focus on delayed
it becomes available. Collectively, these issues
Wave 1 and Wave 2 activities. According
make the risks associated with the large number
to the project’s oversight entities, Wave 3
of departments in Wave 4 more acute today than
activities were tracking 14 months behind
when we first noted it in our analysis of SPR 5.
schedule as of November 2015.
Project Staffing Challenges an Ongoing
• Wave 4 Delays. According to SPR 5, the Problem. During 2015, the project continued
fourth wave would make available the to experience difficulties in recruiting staff for
public transparency website and deploy vacant positions and retaining staff. Of particular
www.lao.ca.gov Legislative Analyst’s Office 11
2016-17 BUDGET
concern, the project experienced turnover in six of service process to hiring qualified staff quickly
eight executive positions in 2015. As of December after positions are authorized by the Legislature,
2015, the project reported its overall job vacancy and (3) high turnover rates among project staff
rate was roughly 13 percent of total authorized (including at executive levels). Even if the project’s
positions, which amounts to 38 vacancies among overall vacancy rate were to remain relatively low,
the 288 authorized positions. This is a significant sustained vacancies or high turnover of executive
improvement from other periods, when the positions can significantly compromise the success
project’s vacancy rate exceeded 20 percent. While of the project.
relatively low now, the project’s historically high The schedule delays and these other issues
and volatile vacancy rate can be attributed to (1) a facing the project ultimately spurred the
relatively limited pool of applicants with necessary development of a sixth SPR, which we describe in
skill sets, (2) obstacles inherent in the existing civil more detail in the following sections.
GOVERNOR’S 2016-17 BUDGET
PROPOSALS FOR FI$CAL
The Governor’s budget includes two FI$Cal- for maintaining and operating the FI$Cal System
related proposals: the first allows the project to once it is complete. The total cost for implementing
implement the changes proposed in SPR 6 and FI$Cal as proposed by the budget in 2016-17—
the second establishes a new state department including costs for a new proposed Department
to maintain and operate the FI$Cal System. The of FI$Cal discussed later—is $135 million
administration indicates that these proposals ($96.3 million General Fund). The remainder
would reduce the overall risk associated with the of this report outlines the Governor’s budget
implementation of FI$Cal and set the foundation proposals and presents our associated comments.
THE FI$CAL PROJECT PLAN—SPR 6
In this section we describe the Governor’s project update was approved in January 2014. The
budget proposal related to the changes proposed in last two years have been marked with significant
SPR 6 and provide our assessment. activities, most notably the deployment and
implementation of Wave 1 and Wave 2. Drawing
Governor’s Budget Proposal on
on lessons learned over this period, the project
Project Changes Included in
reports it now has a better understanding of the
SPR 6
magnitude and complexity of FI$Cal. Specifically,
In February 2016, CDT approved an SPR the administration determined the risk of moving
that updates the project plan for FI$Cal. This was forward with an unrealistic project schedule was
the sixth update (SPR 6) to the project plan since too large and decided a different approach would
FI$Cal began in 2005. The project indicates that be necessary in order to mitigate the risk of a
SPR 6 reflects lessons learned since the previous significant disruption to the project in future years.
12 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
The Governor’s budget includes funding to support These principal releases would take place in July
the project, pursuant to the changes included in 2016, 2017, and 2018. In contrast to waves, the
SPR 6 and as outlined below. release approach allows for functionality and
Does Not Propose to Change Project Objectives. departments that are not quite ready to implement
The sixth SPR does not propose changes to the at the scheduled date to roll out later. These
statutory objectives of the project. The intent of the intermediate releases would take place quarterly,
SPR is to mitigate project risk—by changing the as needed, if functionality is not ready at the time
implementation approach, discussed below—so that of the principal release. If a department is not
the project objectives can be successfully fulfilled. ready to transition onto the system at the time of
Extends Schedule and Increases Cost Relative the principal release, the project could have until
to SPR 5. The proposed changes to the project October of that year to transition. If the project
reflected in SPR 6 result in a 24-month schedule requires additional time, the project would defer
extension and an increase in the project cost the department to a later release. Figure 3 (see
(relative to SPR 5) by $237 million ($125 million next page) provides a comparison of the FI$Cal
General Fund). This brings the total cost of the implementation time lines under SPR 5 and SPR 6.
project to $910 million ($494 million General As shown in the figure, SPR 6 allows for the
Fund). The increase in project cost is largely deployment of departments and functionality after
attributable to increased contract costs and costs a scheduled principal implementation date—we
to hire additional staff and retain staff over the refer to this as delayed deployment.
additional 24 months that the SPR extends the The release approach is more reflective of what
project. The budget-year impact of these changes the project has actually experienced in prior waves.
is $92.5 million ($71.9 million General Fund). See In practice, the project has deployed functions after
Figure 2 for project costs
incurred to date and the
Figure 2
future costs proposed in
Costs for FI$Cal Under Special Project Report 6
SPR 6.
(In Millions)
Transitions From
Fiscal Year General Fund Total Funds
“Wave” to “Release”
2005-06 $0.5 $0.9
Implementation
2006-07 2.2 5.0
Approach. Under the 2007-08 6.2 6.2
new plan, the project 2008-09 2.1 5.6
2009-10 2.1 12.3
transitions from a
2010-11 1.8 25.8
wave implementation 2011-12 1.9 21.8
approach to a release 2012-13 — 82.0
2013-14 3.4 75.3
implementation approach.
2014-15 95.6 100.1
Like waves, releases
2015-16 103.7 153.9
deploy functionality 2016-17 proposed 96.3 135.1
2017-18 proposed 87.7 129.7
and departments to
2018-19 proposed 50.4 85.8
FI$Cal incrementally
2019-20 proposed 40.1 70.4
over time on scheduled Totals $494.0 $909.9
implementation dates. FI$Cal = Financial Information System for California.
www.lao.ca.gov Legislative Analyst’s Office 13
2016-17 BUDGET
their scheduled implementation date, as is proposed releases. See Figure 4 for a listing of the functions the
in the new release implementation approach. project will roll out and number of departments the
However, rather than not meeting milestones set project will implement over the remaining releases.
in a rigid schedule and having to make last minute Establishes New Program to Ease
changes to the implementation schedule, as was the Departments’ Transition. The project proposes
case in SPR 5, the release approach anticipates that to establish a new program to ease departments’
additional time beyond scheduled implementation transition onto FI$Cal. The new program
Graphic Sign Off
dates will likely be needed for some activities. emphasizes communication and collaboration
Staffing resources are allocated up front on the between the project and departments. As part of
Secretary
basis that some staff will be needed to stay on to determining which departments will be included
Analyst
complete work past a scheduled implementation in each release, the project will spend time to
MPA
date while other staff are working on the subsequent better understand, analyze, and group state
Deputy
release. The project’s objective in transitioning from entities into deployment cohorts with similar
ARTWORK #160031
a wave to a release implementation approach is to financial management needs. The project will
maximize its flexibility, whTielem repdluactien_gL tAhOe pRoetpenotriat_l largaet.taeimtpt to optimize support for departments by
for unplanned, negative schedule impacts for future grouping them into implementation cohorts based
Figure 3
Comparison of FI$Cal Implementation Timeline Under Special Project Reports (SPRs) 5 and 6
Calendar Years
2012 2013 2014 2015 2016 2017 2018 2019
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Pre-Wave —12 Months
Wave 1 — 20 Months
Wave 2 — 15 Months
Wave 3 — 24 Months
SPR 5
Wave 4 — 24 Months
Pre-Wave —12 Months
Wave 1 — 20 Months
Wave 1.x Releases — 32 Months
Wave 2 August Release
— 17 Months
Wave 2 Dec. Release — 21 Months
July 2016 Release
— 16 Months
July 2017 Release — 36 Months
SPR 6 July 2018 Release — 30 Months
Public Transparency Website — 24 Months
Knowledge Transfer
— 12 Months
= preparing for implementation = go live date = delayed deployment = maintenance and operation
FI$Cal = Financial Information System for California.
14 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
on the size of the department, complexity of the schedule by shifting the bulk of the remaining
department’s funding structure, and the similarity work to later releases so that the project has more
of departments’ financial processes. The project time before certain functions and departments are
anticipates that adjustments to the departmental implemented. Specifically, the revised project splits
implementation cohorts may be necessary as the the remaining two waves into three releases as
project learns more about department needs and follows:
challenges. A decision to move a department from
• July 2016 Release. The updated project
one release to another will include an evaluation
plan decreases the scope of what was
of (1) the department’s readiness and (2) the
previously known as Wave 3 by shifting the
project’s ability to manage the release size and
most significant portion of the accounting
scope. The intent of this process is to help ensure
and cash management functions to the
that departments transition onto the FI$Cal
July 2017 release. Instead, for the July
System successfully in all three releases. This
2016 release the project plans to deploy
approach will be used to transition the remaining
additional budget functions, replace DGS’s
125 departments onto FI$Cal.
current internal financial management
Revises Implementation Schedule for
system (previously planned for July 2015),
Remaining Releases. In line with SPR 6, the
and schedule software upgrades to the
project proposes to change the implementation
system. The fifth SPR anticipated some
Figure 4
Departments and Functionality of FI$Cal Releases Under Special Project Report 6
Number of Departments Functionalitya Implementation Date
Pre-Wave (actual) 5 (a subset of Wave 1) Some procurement functions. July 2013
Wave 1 (actual) 11 Significant budget functions. Throughout 2014-15
Some accounting, cash management, and
procurement functions.
Wave 2 (actual) 45 mostly CFS Additional budgeting, accounting, and cash August 2015
departmentsb management functions.
Remaining significant procurement functions. December 2015
July 2016 Releasec 10 Financial management functions specific to July 2016
the Department of General Services.
Additional budget functions.
Software upgrades.
July 2017 Releasec 50 Remaining significant accounting functions. July 2017
Remaining significant cash management functions.
July 2018 Releasec 65 Public transparency website. July 2018
a
Functionality implemented in earlier waves is deployed to new departments as they join FI$Cal. Functionality implemented after a department originally joined FI$Cal will be
deployed to that department as part of the subsequent wave deployments.
b
The Department of General Services offers accounting, budgeting, and financial services to state entities on a fee-for-service basis. These departments, typically smaller entities,
are known as contracted fiscal service departments.
c Per the administration’s proposal, functionality and departments may be deployed in intermediate release over the 12 months following the principal implementation date.
FI$Cal = Financial Information System for California and CFS = contracted fiscal services.
www.lao.ca.gov Legislative Analyst’s Office 15
2016-17 BUDGET
software upgrades in July 2016; however, departments transition onto FI$Cal. The fifth
additional upgrades not previously scoped SPR did not include any knowledge transfer after
within the project have been identified. the system was fully deployed. The expanded
This release also deploys the system to ten knowledge transfer opportunity is intended to
departments (one large, two medium, and prepare the state to maintain the system with
seven small). (Unlike SPR 5, SPR 6 does minimal support from the vendor on an ongoing
not identify the specific departments that basis. To date, the vendor has taken primary
will transition onto FI$Cal over the various responsibility for DD&I and M&O. The project
releases. Instead, SPR 6 lists the total indicates that during the final year allotted for
number of departments and the relative knowledge transfer, the vendor and project staff
size of those departments.) It is the intent will switch roles, with the state taking primary
of the project to test its new program to responsibility of FI$Cal and the vendor supporting
ease departments’ transition onto FI$Cal the project staff.
(described above) to a limited number of Does Not Reflect Final Agreement With
departments before deploying the system Vendor. While the sixth SPR makes significant
to a larger quantity of departments in later assumptions regarding the vendor’s role, it does not
releases. reflect a final agreement between the project and
the vendor, and instead includes estimates of what
• July 2017 Release. The sixth SPR
the costs will ultimately be. The SPR assumes that
implements the most significant portion
the vendor commits to (1) remain engaged on the
of the accounting and cash management
FI$Cal Project for an extended period of time and
functions one year later than what was
(2) take on additional responsibilities stipulated in
anticipated in SPR 5. The project indicates
SPR 6. The SPR also estimates the increased cost
that this change will allow more time to
to the state for the vendor taking on these new
build and test these functions. In addition,
commitments. We note that the project has not yet
this release deploys functions to 50 state
finalized the cost of these new commitments with
departments (14 large, 14 medium, and
the vendor.
22 small).
LAO Assessment of FI$Cal
• July 2018 Release. As previously planned, Project Plan and Related
the final release includes the development Budget Proposal
of a public transparency website. However,
Ultimately, we believe that the benefits of
the website will not become available to the
proceeding with FI$Cal development outweigh
public until July 2019, after the system has
the risk and therefore recommend approval of
captured a full year of financial data. In
the Governor’s budget proposal to implement
addition, the final release deploys FI$Cal
project changes pursuant to SPR 6. (We discuss
to the remaining 65 state departments
the administration’s proposal to establish the
(24 large, 11 medium, and 30 small).
Department of FI$Cal in the next section of this
Expands Knowledge Transfer Opportunities
report.) However, the FI$Cal Project involves
From Vendor to State. The sixth SPR provides
the development of an extremely ambitious and
one full year for knowledge transfer after all
complex IT system and significant work remains
16 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
before the system is fully implemented. Given or setting unrealistic schedule expectations,
the scope of the remaining work, signals from the release approach provides the project some
oversight entities that some project activities flexibility that prior experience has shown is
continue to track behind schedule, and the needed. Additionally, prior decisions to stagger
inherent risk associated with an IT project of this the deployment of functions after the scheduled
complexity, we think a future SPR is likely that implementation date have been the result of last
would further extend the project schedule and minute changes to the implementation approach,
increase costs. Below, we describe our findings rather than deliberate decisions made in advance.
and recommendations related to the Governor’s These last minute changes to the implementation
proposal to implement the changes included in approach have proven problematic for the FI$Cal
SPR 6. Project and departments. The project was not
prepared to keep staff engaged when workload
LAO Findings on FI$Cal Project Status
persisted beyond the planned implementation
and Plan to Move Forward
date, as occurred in Wave 1 and Wave 2. These
Contract Negotiations May Change Cost delays made it difficult to transition staff to other
and Schedule Projections. As noted earlier, the workload, as anticipated, and caused delays in
project and vendor have not yet reached final other aspects of the project. Under the new release
agreement regarding the cost of various new vendor approach, the project plans to keep resources
commitments assumed in SPR 6. The negotiations engaged to support a release after the principal
with the vendor may result in significant changes release rather than assume the resources will be
to the scope of the vendor’s responsibilities relative immediately freed up and available for subsequent
to the scope included in SPR 6. Additionally, the releases. In this regard, SPR 6 reflects lessons
project cost estimated in SPR 6 may not accurately learned from prior SPRs—namely that there may be
reflect the vendor price for the specific activities some functionally or departments that need to be
once final negotiations are complete. Until the delayed—and plans accordingly. The project should
project and the vendor reach a final agreement, it therefore be better able to allocate resources more
is uncertain if the schedule and cost described in effectively to mitigate negative impacts on future
SPR 6 are accurate. If the final negotiations result in releases.
significant changes to the scope, schedule, and/or Release Approach Provides Flexibility to
costs included in SPR 6, the project will require an FI$Cal Project . . . The proposed implementation
additional SPR. approach provides the project the flexibility to delay
New Release Approach More Realistic roll-out of functions and shift the implementation
Going Forward. Despite SPR 5 setting a strict of added departments based on their readiness.
schedule, in practice, the project has begun the Specifically, the new SPR does not identify specific
implementation of new functions and departments departments that will transition onto FI$Cal
between waves, as is proposed in the new release over the various releases, but instead lists the
implementation approach. The release approach is total number of departments and the relative size
a recognition by the project that some functions of those departments that are anticipated to be
or departments may need additional time beyond deployed on a scheduled implementation date. The
the principal implementation date before they are sixth SPR also sets up a new program that supports
ready to deploy. Rather than going live prematurely departments leading up to implementation to help
www.lao.ca.gov Legislative Analyst’s Office 17
2016-17 BUDGET
ensure that departments transition onto FI$Cal with the prior plan. This is because the previous
only when they are ready. These new features in plan, which included a more aggressive schedule,
SPR 6 help the project maximize its flexibility. could have resulted in rolling out system functions
Given the magnitude of the FI$Cal Project, project and adding new departments prematurely. Strictly
staff are likely to continue to experience challenges following the aggressive schedule of SPR 5 would
developing some functions or engaging some have resulted in costly rework and disruptions to
departments. The new implementation approach the state’s financial systems. However, the project
gives the project additional time to overcome these did not strictly follow the SPR 5 schedule. Instead,
challenges without delaying the progress of the the unreasonable expectations created resulted in
project due to staffing being held back to address the project falling behind schedule. The oversight
issues from prior waves. entities are already tracking the project’s progress
. . . While Maintaining Some Uncertainty based on the SPR 6 schedule. While SPR 6 makes
for Departments. The administration’s proposed it more likely that the project will be able to
release approach and its new program to ease successfully implement these releases, the oversight
department transition allows for the shifting entities have noted that some of these activities are
of functions and departments in the schedule, already behind schedule. While a step in the right
depending on their readiness. While this flexibility direction, perhaps SPR 6 may not go far enough in
provides the project benefits described above, some extending the project schedule.
uncertainty remains for departments. Because . . . But Substantial Risk Remains. While we
departments do not know when the project will think the modifications to the FI$Cal schedule in
exercise this flexibility, departments may be less SPR 6 reduce overall project risk and strengthen
able to adjust resources to reflect the change in FI$Cal’s likelihood of success, substantial risk
schedule and may find the change disruptive to remains, especially in the final release planned for
their workload. July 2018. This is because SPR 6 plans to transition
Plan Mitigates Some Project Risk . . . The a large number of departments onto FI$Cal in the
revised plan attempts to reduce risks associated with final release. The fifth SPR also anticipated that the
the project and improve the likelihood of FI$Cal’s final wave—Wave 4 scheduled for implementation
success by allowing additional time to build and test in July 2017—would be large. In our analysis of
certain functions. The proposed changes reportedly SPR 5, we raised a concern that the final wave was
reflect lessons learned in the two years since the last too expansive in size and may prove too difficult for
SPR. Notably, the modifications to the project reveal the project’s resources to implement. Subsequent
the project’s improved understanding of the work decisions by the Steering Committee deferred
required to implement complex functions specific some departments to later waves, growing the size
to DOF, SCO, STO, and DGS while simultaneously of Wave 4. While SPR 6 spreads the transition of
addressing the needs of the diverse departments departments onto FI$Cal over more years than
currently using or preparing to use the FI$Cal SPR 5, the final release continues to include a
System. much larger number of departments than have
While SPR 6 is associated with an extension been rolled out at any other time in the project’s
of the project’s schedule and an increase in the history. Moreover, the project has previously
project cost relative to SPR 5, these changes could delayed departments with issues that make them
potentially be less costly than moving forward challenging to transition onto FI$Cal (such as
18 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
BOE and DOJ). These prior actions mean the final Under the prior project plan—SPR 5—many
release will be comprised of the largest number of the positions would be eliminated after the final
of departments of any wave/release as well as the wave. Under this prior approach, we would expect
departments that are most likely to have challenges it to become increasingly difficult for the project
transitioning onto FI$Cal. We therefore remain to maintain a constant level of staff as the end
concerned that the final release continues to be of the project approaches because (1) employees
large, making it potentially difficult for the project would look for other employment opportunities
to maintain its proposed schedule under SPR 6. in anticipation of their project job ending and
Reasonable to Hire Staff Now to Allow for (2) fewer qualified candidates would apply for
Knowledge Transfer. The oversight entities have vacant positions that would soon be eliminated.
consistently raised concerns that the state may These staffing difficulties increase the risk that
face significant difficulty maintaining FI$Cal after an IT project will not meet key milestones that
implementation without the vendor’s or some other affect the project’s schedule and budget and can
M&O contractor’s assistance. Extending knowledge ultimately lead to a project failing. For much
transfer opportunities enhances the likelihood of the project’s history, FI$Cal management
that the state will be fully prepared to maintain has contended with recruitment and retention
FI$Cal after its implementation. That being said, difficulties. Transitioning the vast majority of staff
the oversight entities report that only a small to the M&O of the system as they are no longer
percentage of organizations successfully assume required for DD&I would likely help to mitigate
M&O responsibilities of an IT system of this future recruitment and retention challenges.
type—that integrates various complex management However, if turnover in executive positions
functions—and a majority of organizations continues, it may pose challenges to maintaining
ultimately sign long-term M&O contracts with a the continuity and consistency of the vision and
vendor. While the additional year of knowledge execution of the project.
transfer is a step in the right direction, some Uncertain if Current Facility Can
contractual relationship with the vendor or another Accommodate Future Requirements of Project.
contractor may be necessary on an ongoing basis to The FI$Cal Project staff and many vendor staff are
fill gaps in skill sets not available among state staff. currently located in leased space in Sacramento,
New Staffing Plan Seems to Address California. The FI$Cal Project is currently
Recruitment and Retention Challenges Associated evaluating if the current facility can accommodate
With Limited-Term Positions. The administration the requirements of the project in future years.
proposes transferring most FI$Cal Project staff Any facility would have to accommodate the nearly
to the Department of FI$Cal as DD&I workload 100 new positions proposed in the Governor’s
comes to end. The administration has often budget proposals for the project and department
asserted that it is difficult to recruit and retain over the next several years. Additionally, the
employees for limited-term positions in part facility would have to accommodate training
because workers prefer the security that is afforded space to support current users of the system and
employment in a permanent position. Especially the 125 remaining departments. According to
in the case of IT projects, the use of limited-term the project, the limited space currently available
positions is cited as a major hindrance to recruiting for this purpose may jeopardize the project’s
and retaining qualified candidates. ability to support current and future FI$Cal
www.lao.ca.gov Legislative Analyst’s Office 19
2016-17 BUDGET
departments. This problem would become more significant changes going forward, a new budget
acute as additional departments are scheduled for proposal would be submitted for legislative review.
deployment in future years. The DGS is currently . . . But Project Still Risky and Significant
conducting an ongoing facilities evaluation to Work Remains. The FI$Cal Project involves
identify whether changes are needed—either the development of an extremely ambitious and
modifications to the current facility or a move to complex IT system and significant work remains
a different facility—in order to accommodate the before the system is fully implemented. In its
requirements of the project. review of the Governor’s proposal and its ongoing
oversight of the FI$Cal Project, the Legislature
LAO Bottom Line on Proposed
should be aware of and monitor factors that not
FI$Cal Project Changes
only contribute to general risk inherent in all IT
Governor’s Proposed Project Changes Are projects, but also the shifting of risks to the end of
Reasonable . . . The Governor’s budget proposal the project schedule due to the substantial number
reflects a reasonable plan to implement the of departments rolled onto the system in the July
remaining functions and departments in FI$Cal. 2018 release. The Legislature may want to ask the
We believe that the time and effort that project project at budget hearings to (1) indicate if the
staff has spent in updating the project plan has project is on schedule for the July 2016 release based
reduced overall risk and strengthened FI$Cal’s on the scope proposed in SPR 6 and (2) identify the
likelihood of success. The administration’s decision steps it is taking to address the risks inherent in the
to delay the implementation of some functions and large July 2018 release.
departments reflects the project’s commitment Additional SPR Likely. We note that given
to a quality product rather than strictly adhering the scope of the remaining work and signals from
to predetermined milestones. While this strategy oversight entities that some project activities
ultimately does extend the project’s schedule continue to track behind schedule, we think a
and increases its cost, we believe this approach future SPR is likely. Additionally, as SPR 6 does
is prudent given the negative impacts to the state not reflect a final negotiation with the vendor,
should functions and departments be brought additional changes may be necessary once final
on line prematurely. On balance, we believe that negotiations are complete. Finally, we note that
the benefits of proceeding with FI$Cal development the Legislature may see a facilities-related request
outweigh the risks, and therefore recommend in future years based on the findings from the
approval of the Governor’s budget proposal in ongoing analysis of the current facilities’ capacity.
regards to project changes. Should the project make
DEPARTMENT OF FI$CAL
In this section we outline the Governor’s Governor’s Budget Proposal to
budget proposal to establish a new state department Establish a New Department
to maintain and operate the FI$Cal System and
In addition to the changes in the project
provide our comments on the proposal.
described previously, the Governor’s budget
proposes to establish the Department of FI$Cal
20 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
to provide the ongoing M&O function for the to meet the needs of departments anticipated in the
FI$Cal System and support services for users of three remaining releases, (2) make system changes
the system—roles currently provided by FSC. In in response to department needs and/or changes in
the following section, we describe the mission, state and federal laws and regulations, (3) engage
governance structure, funding mechanism, and deferred departments (see the box below for a
staffing for the proposed department. description of deferred and exempt departments),
Mission. The Department of FI$Cal would be (4) add new functions to the system as deemed
responsible for the implementation and ongoing necessary in future years, and (5) provide a
M&O of the FI$Cal System. The Governor’s permanent administrative structure for FI$Cal.
proposal indicates that in fulfilling this mission, Governance Structure. The proposed
the department would (1) expand support services department would be led by the Director of the
Deferred and Exempt Departments
The current scope of the Financial Information System for California (FI$Cal) Project excludes
deferred and exempt departments. Deferred departments are defined as departments that have
implemented or are in the process of implementing their own financial management system. As these
departments’ systems require upgrades or as departments desire expanded functionality, they will
move onto FI$Cal. Under the Governor’s proposal, the Department of FI$Cal will be responsible for
bringing deferred departments onto FI$Cal as needed. Deferred departments will not use FI$Cal in
the interim, but will exchange necessary information with FI$Cal to support the constitutional and/
or statutory responsibilities of the partner agencies. Exempt departments have statutory authority
to use systems
other than FI$Cal Departments Deferred or Exempt From FI$Cal
Under Special Project Report 6
for their financial
management. Deferred
Exempt departments California State Lottery Commission
will not use FI$Cal Department of Corrections and Rehabilitation
Department of Motor Vehicles
directly, but will
Department of Transportation
exchange necessary Department of Water Resources
information with State Teachers’ Retirement System
Department of Technology
FI$Cal to support
Exempt
the constitutional
and/or statutory Legislature
Legislative Counsel Bureau/Legislative Data Center
responsibilities of
Judicial Branch
the partner agencies.
State Auditor’s Office
See the figure for University of California
California State University
a complete list of
Hastings College of the Law
deferred and exempt
Public Employees’ Retirement System
departments. State Compensation Insurance Fund
www.lao.ca.gov Legislative Analyst’s Office 21
2016-17 BUDGET
Department of FI$Cal, to be appointed by the • Funding. The cost of operating the
Governor and confirmed by the Senate. While the Department of FI$Cal would be funded
director would be responsible for overseeing the 57 percent from the General Fund and
day-to-day operation of the FI$Cal System, the 43 percent from the Central Service Cost
director would have limited authority over policy Recovery Fund (CSCRF). The CSCRF
decisions affecting the system. This is because, as portion would be paid for by allocating
in the current structure of the FI$Cal Project, the the operational cost to departments based
Steering Committee would continue to set polices on their share of use. The annual cost of
relative to their constitutional and/or statutory operating the department will increase
responsibilities over the state financial management in future years as new functions and
processes integrated through FI$Cal—budgeting, departments come onto the FI$Cal System.
accounting, cash management, and procurement. The cost of operating the department is
Instead, the director’s responsibilities would expected to level off in 2019-20, at which
include (1) setting and monitoring administrative point the annual ongoing cost is expected to
policies; (2) reporting department achievements be $70.4 million ($40 million General Fund).
and status to the partner agencies; and (3) acting
• Staffing. As noted above, the proposed
as spokesperson for the department to the
department would include 122 positions
Legislature, external stakeholders, and the public—
to support the FI$Cal M&O function.
responsibilities that the Executive Partner has
This position total for M&O will grow
under the existing governance structure. As in
over time as the FI$Cal System becomes
the current governance structure, issues outside
more mature and as other staff working
the director’s authority, such as policy decisions
on DD&I activities and finishing up the
regarding the state’s financial processes, would be
implementation work for the project—
decided by the Steering Committee. Initially, the
totaling 121 under the Governor’s proposal
department would report directly to the Governor.
and nominally considered to be part of the
The project envisions that the Department of
department—shift to M&O activities. By
FI$Cal eventually would be realigned under the
2019-20, it is estimated that the department
California Government Operations Agency.
will be comprised of 274 ongoing
Department Funding and Staffing. The
positions, primarily dedicated to M&O
Governor’s budget proposes $42.6 million
of the FI$Cal System. The departmental
($24.3 million General Fund) and 122 positions in
positions mentioned herein do not include
2016-17 to support the proposed M&O functions
positions in the partner agencies dedicated
within the Department of FI$Cal. This position
to FI$Cal—estimated to be around
total includes 99 existing project positions that
60 positions in 2019-20.
will shift from DD&I to M&O responsibilities plus
23 proposed new positions. When the department Implementing Legislation Establishes
assumes complete responsibility for maintaining Department of FI$Cal. The Governor proposes
and operating the FI$Cal System in 2019-20, legislation to update the existing statute for the
the department is expected to cost $70.4 million FI$Cal Project to reflect the department-related
annually and include 274 permanent positions. budget proposal. Among other things, the language
(1) replaces the FSC and the FI$Cal Project
22 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
office with the Department of FI$Cal and makes the Department of FI$Cal will need
conforming changes and (2) eliminates the FI$Cal 37 administrative positions for 274 total
Executive Partner and establishes the Director of authorized positions. This is a larger
the Department of FI$Cal, who would be appointed administrative infrastructure than that
and serve at the pleasure of the Governor. found in other similarly sized departments.
For example, one department we queried
Evaluating Options for an
has 22 administrative staff for 285 total
Administrative Structure for
authorized positions, while another
FI$Cal M&O
department has 35 administrative positions
While we agree with the administration for 340 total authorized positions. That
that an entity is necessary to maintain and said, some level of administrative support
operate FI$Cal, it is unclear to us whether the will be needed to maintain and operate
establishment of a new department is the best the FI$Cal System, regardless of the entity
way to fulfill this function. We identify a range of selected for M&O. On the benefits side,
options for maintaining and operating FI$Cal and creating a new department to maintain and
propose questions that the Legislature may want operate the FI$Cal System would establish
to ask the administration in order to get a better a dedicated entity in state government for
understanding of the merits and challenges of maintaining and operating the system,
establishing the Department of FI$Cal, as proposed increasing its visibility and perhaps
by the Governor, versus other options. signaling that maintenance of the system is
a priority.
Range of Administrative Structure Options
for Maintaining and Operating FI$Cal • Preserve FSC. The FSC has maintained and
operated FI$Cal since July 2013, when the
A range of options of administrative structures
first system functions were implemented
for maintaining and operating the FI$Cal System
in a small number of departments. It is
are available for legislative consideration. Below, we
unclear why a new state department is
describe three options—the Governor’s proposal
necessary when an infrastructure already
and two other basic options—and discuss the
exists to maintain and operate the FI$Cal
relative merits and drawbacks of each option.
System. The responsibility for FI$Cal M&O
• Create a New Department. As the
could remain at the FSC. Although this is
administration proposes, responsibility
an option the Legislature could consider,
for supporting the state’s integrated
we find it to be substantially similar to the
financial management system could be
Governor’s proposal to establish a new
delegated to a newly created department.
department. The main potential difference
This approach could be more costly than
is that the FSC may be able to maintain
other options given the administrative
the system with lower administrative
costs associated with establishing and
costs. This is because the FSC would not
operating a department, especially a
necessarily have the added administrative
department of a few hundred employees.
infrastructure necessary to operate a new
The administration proposes that
department because it could continue to
once the system is fully implemented,
www.lao.ca.gov Legislative Analyst’s Office 23
2016-17 BUDGET
obtain contracted administrative services • What authority would the Director of the
from DGS, as is current practice. However, Department of FI$Cal have independent
according to the project, the FSC does not of the partner agencies? How would the
provide the system with the visibility a authority of the director differ from the
department would provide the system. authority of the current Executive Partner
at the FSC? How would the Director of the
• Delegate Responsibility to One of the
Department of FI$Cal be held accountable?
Four Partner Agencies. Alternatively,
the Legislature could delegate the • Are there any administrative costs
M&O responsibilities to one of the associated with the creation of a new
four partner agencies. This approach department that would not exist if the
utilizes the partners’ familiarity with the M&O for the project continued to be with
system, without building an extensive the FSC or were placed within one of the
administrative infrastructure to support partner agencies?
a new department. Although this option
Regardless of the model used to maintain and
would be less costly than creating a new
operate the state’s integrated financial management
department because it would utilize
system, the Legislature may wish to take steps to
an already existing administrative
address the muddled accountability inherent in the
infrastructure, partner agencies have
current governance structure and likely to continue
existing constitutional and/or statutory
regardless of the entity selected for M&O unless
responsibilities that may result in their
addressed. In the next section we present options
prioritizing existing responsibilities over
for strengthening accountability.
FI$Cal M&O.
A Need to
Strengthen Accountability
Questions for Legislative Consideration
in Evaluating M&O Options
Muddled Accountability Under Current
When balancing the benefits and trade-offs of Governance Structure. The current governance
these options, the Legislature should consider such model spreads accountability across the Executive
criteria as (1) how the option affects accountability Partner and the members of the Steering
to the Legislature, (2) the cost and potential Committee, rather than empowering a single point
economies of scale of the option, and (3) the of authority for decision making who can be clearly
capacity of the entity under the option to maintain held accountable.
and operate the FI$Cal System. The Legislature may Accountability Continues to Be Problematic
want to direct the following questions to the FI$Cal Under Governor’s Proposal. The Governor’s
Project during budget hearings in order to get a proposal does not address the existing muddled
better understanding of the merits and challenges accountability and would continue to jeopardize
of establishing the Department of FI$Cal versus the Legislature’s ability to hold FI$Cal leadership
other options. accountable. As proposed, the Department of
• How does establishing a department FI$Cal would not have a single point of authority
for decision making. Instead, authority would be
improve the services already provided by
diffused across the department’s director and the
the FSC?
24 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
partner agencies. Typically in state government, generally be making less frequent and less
a department director would have authority over critical decisions about the automation of
the policy and administrative issues of his or the state’s financial management processes.
her department. In the case of the Department As a result, the existing role of the partner
of FI$Cal, however, the director would have no agencies—directing the course of the
authority over the state’s financial management project through the Steering Committee—
policies. These activities would remain within the might no longer be necessary for the
respective purview of DOF, SCO, STO, and DGS. success of the system once it enters M&O.
The director’s authority would largely be limited to Instead, the leader of the entity selected
administrative issues facing the department, even to maintain and operate the system could
though changes in the state’s financial management solicit advice from partner agencies on an
policies could directly affect the FI$Cal System. as-needed basis. Transitioning the partner
Should issues regarding FI$Cal’s performance arise agencies to an advisory role would establish
in the future, this governance structure would the leader of the selected entity as the single
make it difficult for the Legislature to hold decision point of authority for decision-making over
makers accountable for any actions that disrupted issues affecting FI$Cal. The Legislature
FI$Cal. would therefore be able to hold the leader
Options for Strengthening Accountability, accountable for changes in policies that
Regardless of M&O Entity Chosen. Each option threaten the stability of the system.
for an administrative structure to maintain and
• For the Short Term, Elevate Leader
operate the FI$Cal System potentially presents
of Entity Selected for M&O to Voting
problems with accountability. Therefore, regardless
Member of the Steering Committee.
of the administrative structure chosen, we
Because the FI$Cal System will not fully
think that steps should be taken to enhance the
enter M&O until 2019-20, the Legislature
Legislature’s ability to hold FI$Cal leadership
may wish to take incremental steps to
accountable. The following options could
increase accountability in the short term.
strengthen accountability regardless of the entity
This would preserve the more formal role
chosen to maintain and operate the system, with
of the partner agencies until the system
the second option being a more incremental step to
is fully implemented. The Legislature
strengthen accountability for the short term.
could increase the accountability of the
• Discontinue Formal Role of Partner
leader selected to maintain and operate
Agencies, Instead Establish Advisory
the system by establishing the leader as a
Role. During the planning and DD&I
voting member of the Steering Committee
phases of the FI$Cal Project, intensive
and Project Directorate. Because the
engagement by the partner agencies was
Steering Committee operates under the
necessary. Critical decisions were being
consensus decision-making model—where
made regularly during these phases
all voting members must agree to a course
regarding the automation of processes over
of action—the leader of the selected entity
which the partners have constitutional
could be held accountable for changes in
and/or statutory responsibility. During the
policies that threaten the stability of the
M&O phase, the Steering Committee will
www.lao.ca.gov Legislative Analyst’s Office 25
2016-17 BUDGET
system. While this model would empower policy changes he or she believes would
the leader to block policy changes that he benefit the system. Instead, the leader
or she believes would negatively impact would need to seek the support of the full
the FI$Cal System, it would not necessarily Steering Committee.
allow the leader to independently pursue
26 Legislative Analyst’s Office www.lao.ca.gov
2016-17 BUDGET
www.lao.ca.gov Legislative Analyst’s Office 27
2016-17 BUDGET
LAO Publications
This report was prepared by Lourdes Morales, with assistance from Nick Schroeder, and reviewed by Ginni Bella Navarre.
The Legislative Analyst’s Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to
the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service,
are available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000,
Sacramento, CA 95814.
28 Legislative Analyst’s Office www.lao.ca.gov