LAO
Supplemental Report of the 2016-17 Budget Package (Updated)
Read the report at Legislative Analyst's Office ↗
TO: AGENCY SECRETARIES
DEPARTMENT HEADS
BOARDS AND COMMISSIONS
The Supplemental Report of the 2016-17 Budget Package contains statements of legislative
intent that were adopted during deliberations on the 2016-17 budget package.
Please distribute your responses to the supplemental report, and any other report or document
you are required to submit, to the Joint Legislative Budget Committee (JLBC), as follows:
Two Hard Copies of the Report and Transmittal Letter to:
Hon. Holly J. Mitchell, Chair
Joint Legislative Budget Committee
1020 N Street, Room 553
Sacramento, CA 95814
Attention: Ms. Peggy Collins.
One Hard Copy of the Report and Transmittal Letter to:
Mr. Daniel Alvarez, Secretary of the Senate
Room 400, Sacramento, CA 95814.
An Electronic Copy of the Report and Transmittal Letter to Each of the Following:
Joint Legislative Budget Committee: Peggy.Collins@sen.ca.gov
for distribution to the JLBC Members.
Legislative Analyst's Office: Tina.McGee@lao.ca.gov
925 L Street, Suite 1000, Sacramento, CA 95814.
Office of the Chief Clerk of the Assembly:
Amy.Leach@asm.ca.gov and Dotson.Wilson@asm.ca.gov
Mr. E. Dotson Wilson, Chief Clerk of the Assembly
Room 3196, State Capitol, Sacramento, CA 95814.
Legislative Counsel Bureau: Jim.Lasky@lc.ca.gov
Ms. Diane Boyer-Vine, Legislative Counsel
925 L Street, Suite 900, Sacramento, CA 95814
Attention Mr. Jim Lasky.
In the report, as well as in your transmittal letter to Senator Mitchell, please cite the
11-digit budget item number(s) and the budget year or other statutory reference to which the
response relates.
If you have any questions, you may contact the Legislative Analyst’s Office at
(916) 445-4656.
Preprinted logo will go here
Supplemental Report of the
2016-17 Budget Act
Containing Statements of Intent
And Requests for Studies
Adopted by the Legislature
Compiled by the
L E G I S L A T I V E A N A L Y S T ’ S O F F I C E
Revised January 2017
Supplemental Report of the 2016-17 Budget Act
Table of Contents
L , J , e
egisLative udiciaL and xecutive
Item 0250‑301‑3138—Judicial Branch .....................................................................................3
Item 0530‑001‑9745—California Health and Human Services Agency ...................................3
Item 0840‑001‑0001—State Controller’s Office .......................................................................4
Item 0860‑001‑0001—State Board of Equalization ..................................................................5
Item 0890‑101‑0001—Secretary of State .................................................................................6
B , c s , H
usiness onsumer ervices and ousing
Item 1111‑001‑0767—Department of Consumer Affairs .........................................................7
Item 1700‑001‑0001—Department of Fair Employment and Housing ....................................7
t
ransportation
Item 2740‑001‑0044—Department of Motor Vehicles .............................................................9
n r
aturaL esources
Item 3540‑101‑XXXX—Department of Forestry and Fire Protection ...................................10
Item 3790‑101‑3001—Department of Parks and Recreation ..................................................10
Drought Response Outcomes (Various Departments) .............................................................10
Item 3790‑001‑0392—Department of Parks and Recreation ...............................ERRATA 10‑1
H H s
eaLtH and uman ervices
Item 4260‑001‑0001—Department of Health Care Services ..................................................12
Item 4265‑001‑0001—Department of Public Health ..............................................................17
Item 4440‑011‑0001—Department of State Hospitals ............................................................17
Item 5180‑001‑0001—Department of Social Services ...........................................................20
e
ducation
Item 6100‑001‑0001—California Department of Education ..................................................26
Item 6870‑101‑0001—California Community Colleges .........................................................26
Item 6980‑101‑0001—California Student Aid Commission ..................................................26
L W d
aBor and orkforce eveLopment
Item 7350‑001‑3152—Department of Industrial Relations ....................................................28
g g
eneraL overnment
Item 8660‑001‑0412—California Public Utilities Commission .............................................29
Item 8955‑001‑0001—Department of Veterans Affairs ..........................................................29
LEGISLATIVE ANALYST’S OFFICE 1
Supplemental Report of the 2016-17 Budget Act
c o
apitaL utLay
Item 0250‑301‑0668—Judicial Branch—Capital Outlay .......................................................30
Item 0250‑301‑3138—Judicial Branch—Capital Outlay .......................................................31
Item 0540‑301‑6051—California Natural Resources Agency—Capital Outlay .....................34
Item 0690‑301‑0001—Office of Emergency Services—Capital Outlay ................................34
Item 2665‑491—High‑Speed Rail Authority—Capital Outlay ...............................................35
Item 2720‑301‑0044—California Highway Patrol—Capital Outlay ......................................35
Item 2720‑491—California Highway Patrol—Capital Outlay ...............................................37
Item 2740‑301‑0044—Department of Motor Vehicles—Capital Outlay ................................37
Item 3125‑301‑XXXX—California Tahoe Conservancy—Capital Outlay ............................38
Item 3340‑301‑0001—California Conservation Corps—Capital Outlay ...............................38
Item 3340‑301‑0660—California Conservation Corps—Capital Outlay ...............................39
Item 3540‑301‑0001—Department of Forestry and Fire Protection—Capital Outlay ..........40
Item 3540‑490—Department of Forestry of Fire Protection—Capital Outlay .......................41
Item 3640‑302‑6029—Wildlife Conservation Board—Capital Outlay ..................................47
Item 3790‑301‑0001—Department of Parks and Recreation—Capital Outlay ......................47
Item 3790‑301‑0263—Department of Parks and Recreation—Capital Outlay ......................48
Item 3790‑301‑0392—Department of Parks and Recreation—Capital Outlay ......................48
Item 3790‑301‑6029—Department of Parks and Recreation—Capital Outlay ......................49
Item 3790‑301‑6051—Department of Parks and Recreation—Capital Outlay ......................49
Item 3790‑491‑0005—Department of Parks and Recreation—Capital Outlay ......................50
Item 3790‑491‑0263—Department of Parks and Recreation—Capital Outlay ......................50
Item 3790‑491‑0392—Department of Parks and Recreation—Capital Outlay ......................52
Item 3790‑491‑6051—Department of Parks and Recreation—Capital Outlay ......................52
Item 3790‑491‑XXXX—Department of Parks and Recreation—Capital Outlay ...................54
Item 3790‑XXX‑0516—Department of Parks and Recreation—Capital Outlay ....................54
Item 3790‑XXX‑6051—Department of Parks and Recreation—Capital Outlay ....................55
Item 3860‑301‑6083—Department of Water Resources—Capital Outlay ............................55
Item 4265‑490—Department of Public Health—Capital Outlay ............................................55
Item 4300‑301‑0001—Department of Developmental Services—Capital Outlay .................56
Item 4440‑301‑0001—Department of State Hospitals—Capital Outlay ................................56
Item 5225‑301‑0001—California Department of Corrections and Rehabilitation—
Capital Outlay ................................................................................................................58
Item 6100‑301‑0001—Department of Education—Capital Outlay .......................................59
Item 6440‑001‑0001—University of California—Capital Outlay ..........................................59
Item 6600‑301‑0660—Hastings College of the Law—Capital Outlay ...................................60
Item 6610‑001‑0001—California State University—Capital Outlay .....................................61
Item 6870‑301‑6049—California Community Colleges—Capital Outlay .............................77
Item 7760‑301‑0660—Department of General Services—Capital Outlay .............................78
Item 8940‑301‑0001 and 8940‑301‑0890—Military Department—Capital Outlay ...............78
Item 8940‑301‑0001—Military Department—Capital Outlay ...............................................79
Item 8940‑301‑0604—Military Department—Capital Outlay ...............................................80
Item 8955‑490 and 8955‑491—Department of Veterans Affairs—Capital Outlay ................80
2 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
L , J , e
egisLative udiciaL and xecutive
Item 0250‑301‑3138—Judicial Branch
1. Plan to Address Insolvency of the Immediate and Critical Needs Account (ICNA).
The judicial branch’s fiscal year 2016‑17 court construction plan results in ICNA
becoming insolvent in approximately 15 years. ICNA becomes insolvent even
faster if all projects that are not currently canceled or indefinitely delayed
complete construction as planned. Thus, no later than January 10, 2017, the
judicial branch shall submit to the Joint Legislative Budget Committee and the
Department of Finance a report addressing the long‑term solvency of ICNA
within existing resources. This report shall include the following:
(a) The judicial branch’s plan for ensuring ICNA remains solvent. This plan shall
include, but is not limited to, a discussion of planned changes to increase
revenues or reduce existing expenditures, an assessment of which construction
projects will continue to move forward, an explanation for why each project
is proposed to move forward, and a description of any alternative financing
agreements proposed to fund any of the projects.
(b) A long‑term fund condition for ICNA that demonstrates the fund has
sufficient resources to fully fund all of the construction projects the judicial
branch plans on moving forward. Revenues and expenditures (listed by
project) should be provided annually for all years until debt service on the
proposed projects are fulfilled.
Item 0530‑001‑9745—California Health and Human Services Agency
1. Case Management Information and Payrolling System (CMIPS II). The Department
of Social Services and the Office of Systems Integration, in collaboration with
stakeholders, including the CMIPS II system vendor and labor organizations
representing In‑Home Supportive Services (IHSS) providers, shall provide a cost
assessment to the Legislature by January 10, 2017, that includes the cost of options
for reprograming CMIPS II to allow managed care plans participating in the
Coordinated Care Initiative to pay IHSS providers for additional hours that the
managed care plan authorizes pursuant to Welfare and Institutions Code 14186 (b)
(6)(B). The assessment shall include a variety of options and their respective costs,
and identification of the least costly option for implementing the system change
noted above.
LEGISLATIVE ANALYST’S OFFICE 3
Supplemental Report of the 2016-17 Budget Act
2. Options for the Provision of Diaper Assistance to Low-Income Families. The
Department of Social Services, with the Office of Systems Integration and the
Department of Public Health, in collaboration with stakeholders, including the
County Welfare Directors Association of California and legislative staff, shall
consider and inform the Legislature of options to provide diaper purchase
assistance to low‑income families. Approaches for consideration shall include,
but not be limited to, the following: (a) options for delivering the benefit by way
of a paper voucher system or other distribution approach for the larger California
Work Opportunity and Responsibility to Kids (CalWORKs) population; (b) ways to
provide this as a supportive service to the CalWORKs welfare‑to‑work caseload,
potentially using a voucher or ancillary expense benefit approach; and (c) the
feasibility of providing this as an automated benefit long term, to include a range
of potential options based upon functionality for the commodity‑based delivery
of a CalWORKs benefit. The involved state agencies shall provide the Legislature
with a summary of the various approaches and automation options, and, to the
extent available, their initial estimated costs by February 1, 2017.
Item 0840‑001‑0001—State Controller’s Office
1. 21st Century Project. It is the intent of the Legislature to continue funding
assessment activities relating to the 21st Century Project efforts to replace
the state’s human resources and payroll management systems. No later than
March 31, 2017, the State Controller’s Office (SCO) shall provide to the Joint
Legislative Budget Committee (JLBC) and the fiscal committees of both houses a
report that details proposed assessment activities beginning in 2017‑18. The report
shall at a minimum detail:
(a) the results of assessments already completed; and
(b) alternatives to be considered as part of Stage 2 of the Project Approval
Lifecycle process before restarting efforts to replace the state’s payroll
system. Concerning the alternatives, the report shall address whether: (i) an
independent third party should conduct the alternatives assessment, (ii) the
assessment should consider incrementally replacing business processes
through a series of smaller projects, (iii) the assessment should consider a
decentralized model that integrates less complex payroll departments together
and considers alternative approaches for modernizing the payroll systems of
complex departments, and (iv) other state departments or agencies should be
involved in the project in addition to SCO. This reporting requirement may
be satisfied by the submission of a budget change proposal as part of the
Governor’s 2017‑18 budget that addresses the issues listed above.
4 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Item 0860‑001‑0001—State Board of Equalization
1. Physical Office Space. The State Board of Equalization (BOE), in consultation with
the Department of General Services, shall conduct a comprehensive strategic
review of its physical office space requirements and current office space usage.
No later than February 1, 2017, the BOE shall submit to the appropriate budget
committees of the Senate and the Assembly and to the Department of Finance a
report containing the following:
(a) A detailed inventory of all office space occupied by the BOE during the 2015‑16
fiscal year. For each office, this inventory shall provide (i) a description of
its purpose, (ii) the size in square feet, (iii) the terms of its lease, and (iv) the
total annual cost of leasing and using the space—including all necessary
operational expenses.
(b) Information about any office space the BOE owned or leased during 2015‑16
that was unoccupied and an explanation for why the space was not occupied.
(c) A list of the office space requirements of the BOE. It is the intent of the
Legislature that the BOE should minimize the total annual cost of physical
office space while satisfying its other requirements.
(d) A detailed strategic plan for satisfying the physical office space requirements.
2. Centralized Revenue Opportunity System (CROS) Project. No later than October 15,
2016, BOE shall provide a report to the appropriate budget subcommittees of the
Senate and the Assembly regarding the CROS Project. The report shall include,
but not be limited to: (a) details regarding the vendor awarded the CROS Project
contract, including the terms of the contract and updated cost, schedule, and
scope information for the project; (b) identification of any issues or risks the
project is tracking that may jeopardize the project’s completion or result in delays
and a description of efforts to resolve the issues; (c) a report of progress on and
projected completion dates for any significant upcoming project milestones; and
(d) discussion of challenges with recruiting and retaining qualified staff and a
description of efforts to resolve the issues.
3. State Responsibility Area (SRA) Fire Prevention Fee. No later than February 1,
2018, the BOE shall submit to the appropriate budget committees of the Senate
and the Assembly a report regarding the ongoing level of workload related to
the administration of the SRA fire prevention fee. The report shall include, but
not be limited to: (a) the annual number of fee‑payers of the SRA fire prevention
fee in each year since the fee was established; (b) the protest rate during fiscal
LEGISLATIVE ANALYST’S OFFICE 5
Supplemental Report of the 2016-17 Budget Act
years 2015‑16, 2016‑17, and to date and; (c) other statistics BOE considers relevant
to understanding the historical and ongoing level of workload regarding the
administration of the SRA fire prevention fee.
Item 0890‑101‑0001—Secretary of State
1. Reimbursement of Election Costs to County Governments. Chapter 11 of 2016
(AB 120, Committee on Budget) establishes a process through which as much
as $16.3 million can be reimbursed to counties that request assistance to pay for
identified costs incurred between April 26, 2016 and July 15, 2016 in conducting
the June 7, 2016 primary election simultaneously with completing statewide
initiative signature verifications in a timely manner. On or before January 10, 2017,
the Secretary of State shall submit to the Joint Legislative Budget Committee and
the fiscal committees of both houses of the Legislature a report that includes the
following information:
(a) The formula developed by the Secretary of State that was used to determine the
maximum amount of money counties seeking reimbursement were eligible to
receive as reimbursement pursuant to this item.
(b) For each county seeking reimbursement, the maximum amount of money
available for reimbursement under this item as determined by the formula
developed by the Secretary of State.
(c) For each county seeking reimbursement, the amount of money those counties
reported to the State Controller as costs incurred between April 26, 2016 and
July 15, 2016 in conducting the June 7, 2016 primary election simultaneously
with completing statewide initiative signature verifications in a timely
manner.
(d) For each county seeking reimbursement, the amount of money received
pursuant to this item.
6 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
B , c s ,
usiness onsumer ervices and
H
ousing
Item 1111‑001‑0767—Department of Consumer Affairs
1. Board of Pharmacy, Combatting Prescription Drug Abuse. No later than April 1,
2017, the Board of Pharmacy shall provide to the fiscal subcommittees of both
houses a narrative description of the preceding year’s activities related to
combatting prescription drug abuse, including: the total amount of funding
budgeted, allocated, and expended; the number of positions and their
responsibilities; the number of cases and disposition of those cases referred
to the Office of the Attorney General for prosecution that were a direct result
from findings from a coroner’s report; and the number of hours spent to combat
prescription drug abuse, including separately identifying the total number of
hours spent reviewing coroner reports and submitting public records act requests
for such information. The Legislature declares its intent to limit the board’s use of
coroner reports to circumstances that occur within the course of an investigation
related to specific pharmacies and/or pharmacists suspected of overprescribing
prescription drugs.
Item 1700‑001‑0001—Department of Fair Employment and Housing
1. Tracking Outcomes. On or before March 1, 2019, the Department of Fair
Employment and Housing shall submit a report to the Joint Legislative Budget
Committee that includes the following information for each calendar year,
January 1, 2017 through December 31, 2018:
(a) Average number of days between receipt of a pre‑complaint inquiry and the
intake interview.
(b) Number of cases for which the amount of time between receipt of a pre‑
complaint inquiry and the intake interview exceeds 30 days.
(c) Average number of days for complaints to be served on respondents,
differentiated by complaints dual‑filed with the U.S. Department of Housing
and Urban Development or U.S. Equal Employment Opportunity Commission
and those not dual‑filed.
(d) Number of dual‑filed cases not served within ten days.
LEGISLATIVE ANALYST’S OFFICE 7
Supplemental Report of the 2016-17 Budget Act
(e) Number of non‑dual‑filed cases not served with 60 days.
(f) Average number of days to close a case.
(g) Percentage of cases closed within 100, 180, 275, and 365 days.
(h) Number of cases rejected by the U.S. Equal Employment Opportunity
Commission for payment due to quality reasons.
(i) Number of cases remanded by the U.S. Department of Housing and Urban
Development because of incomplete or inadequate investigation.
8 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
t
ransportation
Item 2740‑001‑0044—Department of Motor Vehicles
1. Self-Service Terminals. The Department of Motor Vehicles (DMV) shall report to
the fiscal committees of both houses of the Legislature, the Legislative Analyst’s
Office, and the Department of Finance no later than January 10, 2019 with
information on its current and planned use of self‑service terminals. The report
shall include:
• A description of the number and location of self‑service terminals used by
DMV and the criteria used to select the locations.
• The number and type of annual transactions handled at self‑service
terminals from 2015‑16 through 2017‑18, including the number of
transactions by language and by payment method.
• An estimate of the number of customers using self‑service terminals who
would likely have visited a field office if the self‑service terminal was not
available and the associated savings. The department should also include
a description of the methodology it used to estimate and account for such
savings.
• DMV’s long‑term plans regarding the use of self‑service terminals and
the impact on overall DMV facilities needs and operations. For example,
how the use of self‑service terminals will affect the need for field offices.
This report should also discuss DMV plans to expand the use of self‑
service terminals, such as a multiyear sequencing plan for increasing the
functionality of self‑service terminals by offering additional languages or
transaction types.
LEGISLATIVE ANALYST’S OFFICE 9
Supplemental Report of the 2016-17 Budget Act
n r
aturaL esources
Item 3540‑101‑XXXX—Department of Forestry and Fire Protection
1. Professional Standards Program. No later than March 1, 2017, and for two years
thereafter, the Department shall provide a report to both budget committees of
the Legislature on the implementation of the Professional Standards Program
including, but not limited to:
(a) Detailed information on the consultations undertaken with appropriate labor
organizations.
(b) Hiring of key positions including a detailed description their classifications,
duties, and workload.
(c) The implementation plan for the program including any expected work
products, workload measurements, amount of training provided and
who received training, any curriculum developed for training, a plan for
implementation of additional training by class of employees, and any other
metrics that could be used to evaluate the program.
Item 3790‑101‑3001—Department of Parks and Recreation
1. Funding Beach Replenishment and Natural Sedimentation Projects. On or before
January 10, 2017, the Secretary of Natural Resources shall provide a report
to the budget committees of both houses on obstacles to funding both beach
replenishment projects and natural sedimentation projects—such as dam
removal—with the Public Beach Restoration Fund and the Harbors and Watercraft
Revolving Fund.
Drought Response Outcomes (Various Departments)
1. Outcomes of Drought Expenditures. By February 1, 2017, the Department of Finance
shall submit to the relevant fiscal and policy committees of the Legislature
and to the Legislative Analyst’s Office an update to the Drought Expenditures
report that was submitted in February 2016. This report shall compile
information regarding the outcomes and benefits associated with drought‑related
expenditures from 2013‑14 through 2016‑17. The report will address the drought‑
related appropriations included in Chapter 2 of 2014 (SB 103, Senate Budget and
Fiscal Review Committee); Chapter 3 of 2014 (SB 104, Senate Budget and Fiscal
Review Committee); the 2014‑15 Budget Act; Chapter 1 of 2015 (AB 91, Assembly
10 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Item 3790-001-0392—Department of Parks and Recreation
1. Operating Agreements. Pursuant to Public Resources Code Section 5080.40, the
following operating agreement proposals are approved as described below.
(a) Dockweiler State Beach Operating Agreement With the City of Los Angeles. The
department may enter into a new operating agreement for a term of up to
50 years with the City of Los Angeles for the operation and maintenance of the
Venice Beach portion of Dockweiler State Beach.
The operating agreement terms will require the public agency to develop,
operate, and maintain Dockweiler State Beach for public recreation, safety, and
enjoyment. As required by statute, the operating agreement terms will require
any fee or revenue collections be used to develop, operate, and maintain the
park unit, and any net profit remitted to the department.
The department anticipates negotiations for the new operating agreement to
be complete by June 2016.
(b) Robert Crown Memorial State Beach. The department may negotiate a new
operating agreement for a term of up to 30 years with East Bay Regional Park
District for the operation of Robert W. Crown Memorial State Beach.
The operating agreement terms will require the public agency to develop,
operate, and maintain the park unit for public recreation, safety, and
enjoyment. As required by statute, any fee or revenue collections will be used
to develop, operate, and maintain the park unit, and any net profit remitted
to the department. Any concessions proposed by the operating agency will
require the department’s approval.
The department anticipates negotiations for the new operating agreement to
be complete before the December 2016 expiration.
LEGISLATIVE ANALYST’S OFFICE ERRATA PAGE 10-1
Supplemental Report of the 2016-17 Budget Act
Committee on Budget); the 2015‑16 Budget Act; and the 2016‑17 Budget Act. For
each drought‑related appropriation that has been provided, the administering
department shall report on (1) the amount of encumbrances and expenditures,
(2) the benefits and outcomes achieved with those appropriations, and (3) the
metrics and methods it used to evaluate the success of the program or activity.
The report shall include information on appropriations provided to the following
departments:
• Item 0690‑001/101‑0001—Governor’s Office of Emergency Services.
• Item 2240‑XXX‑XXXX—Department of Housing and Community Development.
• Item 3340‑001‑0001—California Conservation Corps.
• Item 3540‑001‑0001/3063—Department of Forestry and Fire Protection.
• Item 3600‑001‑0001/0200—Department of Fish and Wildlife.
• Item 3860‑XXX‑XXXX—Department of Water Resources.
• Item 3940‑XXX‑XXXX—State Water Resources Control Board.
• Item 4700‑001/101‑0001—Department of Community Services and Development.
• Item 5180‑101‑0001—Department of Social Services.
LEGISLATIVE ANALYST’S OFFICE 11
Supplemental Report of the 2016-17 Budget Act
H H s
eaLtH and uman ervices
Item 4260‑001‑0001—Department of Health Care Services
1. Continuum of Care Reform (CCR). The Department of Social Services (DSS)
and the Department of Health Care Services (DHCS), in collaboration with
the California State Association of Counties, the County Welfare Directors
Association, the County Behavioral Health Directors Association, and the Chief
Probation Officers of California, shall provide monthly in‑person updates to the
Legislature on progress toward the implementation of CCR. Monthly updates
shall convert to quarterly updates once all finalized guidance listed under
paragraph (a) has been delivered to counties. Specific components of the updates
shall cease when notification of completion of a specific activity occurs and/or
when it is agreed by all parties that a component is no longer necessary for other
reasons.
Commencing July 2016, the monthly updates, unless otherwise noted, shall
include but not be limited to:
(a) Update on Guidance to Counties and Stakeholders. Status updates on the
delivery of interim and finalized guidance (including All County Letters,
Information Notices, and Fiscal Letters) to counties and stakeholders on, as
well as progress toward implementing, the following:
(i) The Child and Family Teaming process, including, but not limited
to, guidance on when children’s initial meeting must take place, the
frequency with which meetings occur, and the composition of the teams
(including the participation of mental health professionals on the team).
(ii) How the assessment tool(s) will inform placement and Level of Care
decisions made by the child and family team both during the pilot phase
and after a standard assessment tool has been selected and implemented.
(iii) How, and over what timeframe, the assessment tool will be evaluated
(including details on how the pilot will be used to eventually select an
assessment tool for statewide deployment).
(iv) The definition of, differences between, and use of assessments related to
each Level of Care.
12 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
(v) Resource Family Approval process.
(vi) County licensing and mental health program approval, including
Medi‑Cal Certification of Short‑Term Residential Therapeutic Programs
(STRTPs) and Medi‑Cal Certification of Foster Family Agencies (FFAs).
(vii) Access standards that apply to mental health services for children,
including children in STRTPs, FFAs, Therapeutic Foster Care (TFC)
homes, and Resource Families, and including what types of services are
required to be offered by county mental health and managed care plans
and the standards for timely access.
(viii) Status updates on county allocations of state and federal funding for all
other local assistance components of the CCR spending package. Data
reporting under this paragraph may occur quarterly rather than monthly.
(b) Tracking County Savings and Costs. A status update on the development and
communication with county departments of a methodology to track county
costs and savings related to CCR implementation.
(c) Systems Changes. A status update on the automation changes to the Child
Welfare Services Case Management System and licensing systems needed to
implement CCR (including the automation of foster care payments and the
automated implementation of the selected standard assessment tool). This can
include or be satisfied with a qualitative, high‑level description of the progress
made (for example, major milestones or percentage of progress toward
completion).
(d) U pdate on Child Welfare Provider Performance Outcomes Dashboard. Status
updates on the creation of a provider performance outcomes dashboard,
including:
(i) Until public, the anticipated release date of the public dashboard.
(ii) Individual measures, including any measures related to STRTPs and
FFAs, expected to be added to the dashboard and their anticipated date
of publication.
(e) Update on County Recruitment and Retention Efforts. Status updates on the
recruitment and retention of new resource families. Data reporting under this
LEGISLATIVE ANALYST’S OFFICE 13
Supplemental Report of the 2016-17 Budget Act
paragraph may occur quarterly rather than monthly, to the extent relevant data
is available, and shall include the following:
(i) County allocations of the recruitment and retention funding in the
2015‑16 and 2016‑17 fiscal years.
(ii) The most utilized county activities funded with 2015‑16 and 2016‑17
recruitment and retention funding.
(iii) Outcome measures to assist the Legislature in evaluating the
effectiveness of various recruitment and retention activities at the
county level. This includes the number of resource families recruited
and retained with the funding, and each county’s net change in such
placements.
Commencing January 2017, to the extent the relevant data is available and in
addition to the elements above, the quarterly updates shall include but not be
limited to:
(a) Update on the Transition of Providers to the CCR Service Model. With a focus
on changes over time, status updates on the transition of providers to the
CCR service model. Data reporting under this paragraph may occur quarterly
rather than monthly and shall include the following:
(i) Number of applications for STRTP and FFA licensure.
(ii) Status of accreditations of STRTPs and FFAs.
(iii) Number of licenses granted to STRTPs and FFAs.
(iv) Number of license extension requests from group homes received by
probation and child welfare agencies.
(v) Number of license extensions granted to group homes by probation and
child welfare agencies.
(vi) Primary reasons why group home license extensions are necessary.
(vii) Rate of FFAs and group homes not pursuing a new license under CCR
standards and the current licensed capacity of those providers.
14 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
(viii) Number and identification of counties with licensed temporary shelter
care facilities.
(b) Update on Capacity to Provide Mental Health Services. With a focus
on changes over time, status updates on the capacity of all involved
providers to provide mental health services. Data reporting under this
paragraph may occur quarterly rather than monthly and shall include
the following:
(i) Number of STRTPs with mental health plan contracts to provide mental
health services and identification of the counties with which the STRTPs
have contracts.
(ii) Number of FFAs with mental health plan contracts to provide mental
health services and identification of the counties with which FFAs have
contracts.
(iii) Number of FFAs electing to provide placements in TFC homes.
(c) Tracking Child Outcomes Over Time. With a focus on changes over time, and
to the extent data is available, status updates on the following child outcome
measures:
(i) Number of children in out‑of‑home care stratified by placement type,
Level of Care, and whether the supervising department is county child
welfare or probation.
(ii) Number of placements per child.
(iii) Proportion of placements that constitute a move to a less restrictive
setting.
(iv) Average length of stay per placement episode by placement type.
(v) Number of children receiving the FFA and services‑only rate, stratified
by county.
(vi) Number of children receiving specialty mental health services stratified
by service type, county, placement type, and Level of Care.
LEGISLATIVE ANALYST’S OFFICE 15
Supplemental Report of the 2016-17 Budget Act
(vii) Number of children receiving mental health services under the Medi‑
Cal managed care and fee‑for‑service systems stratified by service type,
county, placement type, and Level of Care.
(viii) Mental health provider (including STRTPs, FFAs, and managed care
plans) and county performance on timely access standards for mental
health for the foster care population.
(ix) Number and disposition of service complaints regarding specialty and
non‑specialty mental health service delivery for foster youth.
(d) Update on CCR-Related Costs and Savings. Once available, status updates on
CCR‑related costs and savings, including:
(i) Ongoing county costs and savings related to CCR implementation.
(ii) Other services and supplemental payments for which counties use
reinvested CCR‑related savings (including funding for FFA services‑only
rate).
(e) Update on the Assessment Tool Pilot. Status updates on the assessment tool pilot
shall include but not be limited to:
(i) Information on the assessment tool pilot evaluation and the ultimate
selection of a standardized assessment tool.
(ii) Ongoing information on how DSS is ensuring consistent statewide
outcomes of the new Level of Care assessment for children across
counties.
(f) Update on CCR Rates. Status updates on how DSS is evaluating the adequacy
of the new CCR rate structure, including:
(i) The extent to which the new STRTP and FFA rates are adequate to
compensate providers for meeting the new service requirements of CCR.
(ii) The extent to which each of the Level of Care rate levels provides
adequate resources to resource families caring for children at all assessed
levels of need.
16 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
(iii) County changes to Specialized Care Increments (SCI) programs,
including any changes in benefit levels and suspensions or terminations
of SCI programs.
Item 4265‑001‑0001—Department of Public Health
1. Options for the Provision of Diaper Assistance to Low-Income Families. The
Department of Social Services, with the Office of Systems Integration and the
Department of Public Health, in collaboration with stakeholders, including the
County Welfare Directors Association of California and legislative staff, shall
consider and inform the Legislature of options to provide diaper purchase
assistance to low‑income families. Approaches for consideration shall include,
but not be limited to, the following: (a) options for delivering the benefit by way
of a paper voucher system or other distribution approach for the larger California
Work Opportunity and Responsibility to Kids (CalWORKs) population; (b) ways to
provide this as a supportive service to the CalWORKs welfare‑to‑work caseload,
potentially using a voucher or ancillary expense benefit approach; and (c) the
feasibility of providing this as an automated benefit long term, to include a range
of potential options based upon functionality for the commodity‑based delivery
of a CalWORKs benefit. The involved state agencies shall provide the Legislature
with a summary of the various approaches and automation options, and, to the
extent available, their initial estimated costs by February 1, 2017.
Item 4440‑011‑0001—Department of State Hospitals
1. Patient Outcomes. Beginning January 10, 2017, and annually thereafter, the
Department of State Hospitals (DSH) shall submit to the Legislative Analyst’s
Office and the appropriate fiscal committees of both houses of the Legislature a
report detailing outcomes to measure successful treatment and progress toward
successfully treating its entire patient population. The report shall address the
following:
(a) Incompetent to Stand Trial.
• How many patients were discharged by DSH in the previous fiscal year?
• Of patients discharged, how many were restored to competency?
• How long did it take for those patients to be restored?
• Of the patients restored, how many completed their court case?
• Of the patients restored, how many were returned to DSH because of
decompensation of their mental health?
• Of the patients restored, how many have court proceedings still in
progress?
LEGISLATIVE ANALYST’S OFFICE 17
Supplemental Report of the 2016-17 Budget Act
(b) Not Guilty by Reason of Insanity.
• How many patients were discharged by DSH in the previous fiscal year?
• Of patients discharged, how many were restored to sanity, or were
discharged because they could be safely treated in the community?
• How long did it take those patients to be restored or released to
community treatment?
• Of those restored or released to community treatment three years ago, how
many committed another crime?
(c) Mentally Disordered Offender (MDO).
• How many patients were discharged by DSH in the previous fiscal year?
• Of patients discharged, how many were discharged because they no longer
fit the definition of an MDO?
• How long did it take to treat those discharged because they no longer fit
the definition of an MDO?
• Of those patients released three years ago, how many committed another
crime?
(d) Sexually Violent Predator (SVP).
• How many patients were discharged by DSH in the previous fiscal year?
• Of patients discharged, how many were discharged unconditionally
because they no longer fit the definition of an SVP?
• Of patients discharged, how many were discharged and sent to the
Conditional Release Program (CONREP) for SVPs?
• How long did it take to treat those discharged because they no longer fit
the definition of an SVP?
• Of those patients released three years ago, how many committed another
crime?
(e) Lanterman‑Petris‑Short Act.
• How many patients were discharged by DSH in the previous fiscal year?
• Of patients discharged, how many were discharged because they no longer
were classified as a threat to self or others?
• Of patients discharged because they were no longer a threat to self or
others three years ago, how many were readmitted to DSH?
18 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
• Of patients discharged because they were no longer a threat to self or
others three years ago, how many were convicted of a crime?
(f) Coleman Class Patients.
• How many patients were discharged by DSH from inpatient psychiatric
programs in the previous fiscal year?
• Of patients discharged, how many were discharged to the California
Department of Corrections and Rehabilitation (CDCR)?
• Of patients discharged, how many were discharged because they
completed their sentences?
• Of those patients discharged to CDCR three years ago, how many returned
to DSH?
(g) CONREP.
• How many patients were discharged by DSH from CONREP in the
previous fiscal year?
• For patients discharged, how long did those patients spend in CONREP?
• Of patients discharged, how many were discharged because they were no
longer classified as a threat to self or others?
• Of patients discharged because they were no longer classified as a threat to
self or others three years ago, how many were readmitted to DSH?
• Of patients discharged because they were no longer classified as a threat to
self or others three years ago, how many were convicted of another crime?
(h) CONREP‑SVP.
• How many patients were discharged by DSH from CONREP‑SVP in the
previous fiscal year?
• For patients discharged, how long did patients spend in CONREP‑SVP?
• Of patients discharged, how many were discharged because they no longer
fit the definition of an SVP?
• Of patients discharged three years ago because they no longer fit the
definition of an SVP, how many were readmitted to DSH?
• Of patients discharged three years ago because they no longer fit the
definition of an SVP, how many were convicted of another crime?
(i) If any of the above information cannot be provided, the department shall
explain (i) why the information cannot be provided and (ii) what resources
would be necessary to provide the requested information.
LEGISLATIVE ANALYST’S OFFICE 19
Supplemental Report of the 2016-17 Budget Act
Item 5180‑001‑0001—Department of Social Services
1. Case Management Information and Payrolling System (CMIPS II). The Department
of Social Services and the Office of Systems Integration, in collaboration with
stakeholders, including the CMIPS II system vendor and labor organizations
representing In‑Home Supportive Services (IHSS) providers, shall provide a cost
assessment to the Legislature by January 10, 2017 that includes the cost of options
for reprograming CMIPS II to allow managed care plans participating in the
Coordinated Care Initiative to pay IHSS providers for additional hours that the
managed care plan authorizes pursuant to Welfare and Institutions Code 14186 (b)
(6)(B). The assessment shall include a variety of options and their respective costs,
and identification of the least costly option for implementing the system change
noted above.
2. Options for the Provision of Diaper Assistance to Low-Income Families. The
Department of Social Services, with the Office of Systems Integration and the
Department of Public Health, in collaboration with stakeholders, including the
County Welfare Directors Association of California and legislative staff, shall
consider and inform the Legislature of options to provide diaper purchase
assistance to low‑income families. Approaches for consideration shall include,
but not be limited to, the following: (a) options for delivering the benefit by way
of a paper voucher system or other distribution approach for the larger California
Work Opportunity and Responsibility to Kids (CalWORKs) population, (b) ways to
provide this as a supportive service to the CalWORKs welfare‑to‑work caseload,
potentially using a voucher or ancillary expense benefit approach, and (c) the
feasibility of providing this as an automated benefit long‑term, to include a range
of potential options based upon functionality for the commodity‑based delivery
of a CalWORKs benefit. The involved state agencies shall provide the Legislature
with a summary of the various approaches and automation options, and, to the
extent available, their initial estimated costs by February 1, 2017.
3. Continuum of Care Reform (CCR). The Department of Social Services (DSS)
and the Department of Health Care Services (DHCS), in collaboration with
the California State Association of Counties, the County Welfare Directors
Association, the County Behavioral Health Directors Association, and the Chief
Probation Officers of California, shall provide monthly in‑person updates to the
Legislature on progress toward the implementation of CCR. Monthly updates
shall convert to quarterly updates once all finalized guidance listed under
paragraph (a) has been delivered to counties. Specific components of the updates
shall cease when notification of completion of a specific activity occurs and/or
when it is agreed by all parties that a component is no longer necessary for other
reasons.
20 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Commencing July 2016, the monthly updates, unless otherwise noted, shall
include but not be limited to:
(a) Update on Guidance to Counties and Stakeholders. Status updates on the
delivery of interim and finalized guidance (including All County Letters,
Information Notices, and Fiscal Letters) to counties and stakeholders on, as
well as progress toward implementing, the following:
(i) The Child and Family Teaming process, including, but not limited
to, guidance on when children’s initial meeting must take place, the
frequency with which meetings occur, and the composition of the teams
(including the participation of mental health professionals on the team).
(ii) How the assessment tool(s) will inform placement and Level of Care
decisions made by the child and family team both during the pilot phase
and after a standard assessment tool has been selected and implemented.
(iii) How, and over what timeframe, the assessment tool will be evaluated
(including details on how the pilot will be used to eventually select an
assessment tool for statewide deployment).
(iv) The definition of, differences between, and use of assessments related to
each Level of Care.
(v) Resource Family Approval process.
(vi) County licensing and mental health program approval, including
Medi‑Cal Certification of Short‑Term Residential Therapeutic Programs
(STRTPs) and Medi‑Cal Certification of Foster Family Agencies (FFAs).
(vii) Access standards that apply to mental health services for children,
including children in STRTPs, FFAs, Therapeutic Foster Care (TFC)
homes, and Resource Families, and including what types of services are
required to be offered by county mental health and managed care plans
and the standards for timely access.
(viii) Status updates on county allocations of state and federal funding for all
other local assistance components of the CCR spending package. Data
reporting under this paragraph may occur quarterly rather than monthly.
LEGISLATIVE ANALYST’S OFFICE 21
Supplemental Report of the 2016-17 Budget Act
(b) Tracking County Savings and Costs. A status update on the development and
communication with county departments of a methodology to track county
costs and savings related to CCR implementation.
(c) Systems Changes. A status update on the automation changes to the Child
Welfare Services Case Management System and licensing systems needed to
implement CCR (including the automation of foster care payments and the
automated implementation of the selected standard assessment tool). This can
include or be satisfied with a qualitative, high‑level description of the progress
made (for example, major milestones or percentage of progress toward
completion).
(d) U pdate on Child Welfare Provider Performance Outcomes Dashboard. Status
updates on the creation of a provider performance outcomes dashboard,
including:
(i) Until public, the anticipated release date of the public dashboard.
(ii) Individual measures, including any measures related to STRTPs and
FFAs, expected to be added to the dashboard and their anticipated date
of publication.
(e) Update on County Recruitment and Retention Efforts. Status updates on the
recruitment and retention of new resource families. Data reporting under this
paragraph may occur quarterly rather than monthly, to the extent relevant data
is available, and shall include the following:
(i) County allocations of the recruitment and retention funding in the
2015‑16 and 2016‑17 fiscal years.
(ii) The most utilized county activities funded with 2015‑16 and 2016‑17
recruitment and retention funding.
(iii) Outcome measures to assist the Legislature in evaluating the
effectiveness of various recruitment and retention activities at the
county level. This includes the number of resource families recruited
and retained with the funding, and each county’s net change in such
placements.
22 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Commencing January 2017, to the extent the relevant data is available and in
addition to the elements above, the quarterly updates shall include but not be
limited to:
(a) Update on the Transition of Providers to the CCR Service Model. With a focus
on changes over time, status updates on the transition of providers to the
CCR service model. Data reporting under this paragraph may occur quarterly
rather than monthly and shall include the following:
(i) Number of applications for STRTP and FFA licensure.
(ii) Status of accreditations of STRTPs and FFAs.
(iii) Number of licenses granted to STRTPs and FFAs.
(iv) Number of license extension requests from group homes received by
probation and child welfare agencies.
(v) Number of license extensions granted to group homes by probation and
child welfare agencies.
(vi) Primary reasons why group home license extensions are necessary.
(vii) Rate of FFAs and group homes not pursuing a new license under CCR
standards and the current licensed capacity of those providers.
(viii) Number and identification of counties with licensed temporary shelter
care facilities.
(b) Update on Capacity to Provide Mental Health Services. With a focus
on changes over time, status updates on the capacity of all involved
providers to provide mental health services. Data reporting under this
paragraph may occur quarterly rather than monthly and shall include
the following:
(i) Number of STRTPs with mental health plan contracts to provide mental
health services and identification of the counties with which the STRTPs
have contracts.
LEGISLATIVE ANALYST’S OFFICE 23
Supplemental Report of the 2016-17 Budget Act
(ii) Number of FFAs with mental health plan contracts to provide mental
health services and identification of the counties with which FFAs have
contracts.
(iii) Number of FFAs electing to provide placements in TFC homes.
(c) Tracking Child Outcomes Over Time. With a focus on changes over time, and
to the extent data is available, status updates on the following child outcome
measures:
(i) Number of children in out‑of‑home care stratified by placement type,
Level of Care, and whether the supervising department is county child
welfare or probation.
(ii) Number of placements per child.
(iii) Proportion of placements that constitute a move to a less restrictive
setting.
(iv) Average length of stay per placement episode by placement type.
(v) Number of children receiving the FFA and services‑only rate, stratified
by county.
(vi) Number of children receiving specialty mental health services stratified
by service type, county, placement type, and Level of Care.
(vii) Number of children receiving mental health services under the Medi‑
Cal managed care and fee‑for‑service systems stratified by service type,
county, placement type, and Level of Care.
(viii) Mental health provider (including STRTPs, FFAs, and managed care
plans) and county performance on timely access standards for mental
health for the foster care population.
(ix) Number and disposition of service complaints regarding specialty and
non‑specialty mental health service delivery for foster youth.
24 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
(d) Update on CCR-Related Costs and Savings. Once available, status updates on
CCR‑related costs and savings, including:
(i) Ongoing county costs and savings related to CCR implementation.
(ii) Other services and supplemental payments for which counties use
reinvested CCR‑related savings (including funding for FFA services‑only
rate).
(e) Update on the Assessment Tool Pilot. Status updates on the assessment tool pilot
shall include but not be limited to:
(i) Information on the assessment tool pilot evaluation and the ultimate
selection of a standardized assessment tool.
(ii) Ongoing information on how DSS is ensuring consistent statewide
outcomes of the new Level of Care assessment for children across
counties.
(f) Update on CCR Rates. Status updates on how DSS is evaluating the adequacy
of the new CCR rate structure, including:
(i) The extent to which the new STRTP and FFA rates are adequate to
compensate providers for meeting the new service requirements of CCR.
(ii) The extent to which each of the Level of Care rate levels provides
adequate resources to resource families caring for children at all assessed
levels of need.
(iii) County changes to Specialized Care Increments (SCI) programs,
including any changes in benefit levels and suspensions or terminations
of SCI programs.
LEGISLATIVE ANALYST’S OFFICE 25
Supplemental Report of the 2016-17 Budget Act
e
ducation
Item 6100‑001‑0001—California Department of Education
1. Interim and Formative Assessment Tools. The Superintendent of Public Instruction
shall report to the Legislature no later than January 15, 2017 on the development
and availability of assessment tools pursuant to Section 60642.6 of the Education
Code. The report shall include, at a minimum, a description of the tools available
to local education agencies (LEAs), the extent to which the tools have been
accessed and used by LEAs, and feedback from LEAs on the value and efficacy of
the tools. In addition, the report shall describe how classroom teachers can use the
formative assessment tools as defined in subdivision (m) of Section 60603 of the
Education Code and interim assessments as defined in subdivision (o) of Section
60603 of the Education Code to match specific standards, or clusters of standards,
contained within the Common Core State Standards with sample or illustrative
test items that are aligned with the Smarter Balanced assessments and that can be
used by teachers and pupils to provide timely feedback to adjust instruction and
improve learning. If this capability does not exist, the department shall provide a
plan or recommendations to develop or acquire and offer these tools at no cost to
LEAs as required by Section 60642.6.
Item 6870‑101‑0001—California Community Colleges
1. Adult Education Data Systems. No later than January 1, 2017, the Chancellor of the
California Community Colleges and the Superintendent of Public Instruction
shall submit to the Director of Finance, the State Board of Education, and
the appropriate policy and fiscal committees of the Legislature a report on
their progress in meeting the requirements of Education Code Section 84920,
subdivisions (b) and (e). The report shall describe the agreements, policies,
procedures, and data systems planned, developed, or implemented to comply
with these requirements.
Item 6980‑101‑0001—California Student Aid Commission
1. Debt Free College Education. On or before January 1, 2017, the Legislative
Analyst’s Office (LAO) shall review California financial aid programs and report
to the relevant budget subcommittees and policy committees of the Legislature
on options to phase in financial aid increases to reduce and eliminate low‑
and middle‑income students’ dependence on student debt to attend college.
In developing the options, the LAO shall consider, among other options,
the consolidation of existing financial aid programs, including: Cal Grants,
Middle Class Scholarships, institutional aid at the California State University
26 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
and University of California, and Board of Governor’s Fee Waivers, into one
entitlement grant program that takes into account the total cost of college
attendance, including: tuition and fees, books and supplies, transportation,
and room and board. The intent is to establish options that ensure that, once
fully phased in, every student will be able to cover the costs of college with an
appropriate family contribution for middle‑ and higher‑income families, earnings
from a part‑time job, federal financial aid for eligible students, and a new state
entitlement program. The options shall include the estimated additional state
costs needed for each year of the phase‑in period for each option presented. The
LAO may convene a group of stakeholders to provide input in the development of
the recommendations.
LEGISLATIVE ANALYST’S OFFICE 27
Supplemental Report of the 2016-17 Budget Act
L W d
aBor and orkforce eveLopment
Item 7350‑001‑3152—Department of Industrial Relations
1. Labor Law Violations in the Nail Salon Industry. No later than March 31, 2017, the
Department of Industrial Relations shall examine workplace labor violations within
the nail salon industry and report its findings to the appropriate fiscal and policy
committees of both houses. Specifically, the report shall include the following:
(a) An assessment of nail salon owner/employers’ and worker/employees’
knowledge of existing labor laws, including, but not limited to:
(i) misclassification of an employee as an independent contractor; (ii) wage and
hour laws (including minimum wage, overtime compensation, meal periods,
rest periods, tip or gratuity distribution, and how to report violations of the
law); and (iii) protections from retaliation.
(b) Strategies for outreach and education of nail salon owner/employers and
worker/employees regarding labor laws per (a) above, including, but not limited
to, community workshops and town hall meetings, ensuring that outreach and
education is conducted in the language(s) that the workers can understand.
(c) The frequency of investigations of nail salons, including the number of
nail salons investigated to date, the number of violations, and the types of
violations that have occurred to date.
In addition, the department shall conduct the following and report to the appropriate
fiscal and policy committees of both houses no later than March 31, 2017:
(a) An assessment, conducted in consultation with the State Board of Barbering
and Cosmetology, of the gaps and opportunities for increased posting of
notices similar to those required to be posted by Section 1183 of the Labor
Code, but that are simplified and printed in languages other than English
spoken by the employers and employees in nail salons. The board may use the
information it collects when it conducts an inspection pursuant to Section 7353
of the Business and Professions Code to inform this assessment.
(b) The results of this assessment shall be shared with the Legislature, in
conjunction with any recommendations on how to improve posting of
notices to better communicate labor rights and obligations to employers and
employees in nail salons on an ongoing basis.
28 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
g g
eneraL overnment
Item 8660‑001‑0412—California Public Utilities Commission
1. Regulatory Enforcement of Household Goods Carriers. The California Public
Utilities Commission shall report by January 1, 2017 on the following: (1) the
number of investigators conducting enforcement of household goods carriers,
(2) past and current enforcement efforts, (3) planned future enforcement efforts,
and (4) options to provide adequate funding for enforcement activities.
Item 8955‑001‑0001—Department of Veterans Affairs
1. Veterans Homes. The Legislative Analyst’s Office, with assistance from the
California Department of Veterans Affairs and the Department of Finance, shall
report to the Legislature, by March 15, 2017, on the role of Veterans Homes in
the 21st century. To the extent feasible, topics of the report shall include, but are
not limited to: demographics of the state’s veterans; an analysis on whether the
services provided at the Homes align with veterans’ needs in the community,
such as housing, employment assistance, or behavioral or mental health services;
options to improve federal funding; and the implications of various funding
scenarios.
LEGISLATIVE ANALYST’S OFFICE 29
Supplemental Report of the 2016-17 Budget Act
c o
apitaL utLay
Item 0250‑301‑0668—Judicial Branch—Capital Outlay
1. Glenn County—Renovation and Addition to Willows Historic Courthouse. The
amount of $33,182,000 is provided for the construction phase of the renovation
and addition of the existing Willows Branch Main Courthouse in Glenn
County. The addition to the existing 15,798 gross square feet (gsf) courthouse
will be 26,069 gsf, for a revised total 41,867 gsf building which will house three
courtrooms. Total estimated project cost is $40,953,000 without financing:
$1,539,000 for acquisition, $2,021,000 for preliminary plans, $2,600,000 for working
drawings, and $34,793,000 (CCCI 5804) for construction. The construction amount
includes $29,290,000 for the construction contract, $2,095,000 for contingency,
$1,394,000 for architectural and engineering fees, and $2,014,000 for other project
costs. Acquisition was completed in February 2011 and preliminary plans in
May 2014. Construction is scheduled to begin in November 2016 and be completed
by December 2018.
2. Imperial County—New El Centro Courthouse. The amount of $39,277,000 is
provided for the construction phase of the New El Centro Courthouse in
Imperial County. The new 47,512 gsf building will house four courtrooms. Total
estimated project cost is $47,277,000 without financing: $1,939,000 for acquisition,
$2,717,000 for preliminary plans, $3,344,000 for working drawings, and $39,277,000
(CCCI 6055) for construction. The construction amount includes $33,398,000 for
the construction contract, $1,706,000 for contingency, $892,000 for architectural
and engineering fees, and $3,281,000 for other project costs. Acquisition was
completed in December 2011 and preliminary plans in April 2015. Construction is
scheduled to begin in November 2016 and be completed by January 2019.
3. Riverside County—New Indio Juvenile and Family Courthouse. The amount of
$42,446,000 is provided for the construction phase of the New Indio Juvenile and
Family Courthouse in Riverside County. The new 53,255 gsf building will house
five courtrooms. Total estimated project cost is $52,865,000 without financing:
$3,423,000 for acquisition, $2,174,000 for preliminary plans, $3,194,000 for working
drawings, and $44,074,000 (CCCI 6055) for construction. The construction amount
includes $37,922,000 for the construction contract, $1,937,000 for contingency,
$953,000 for architectural and engineering fees, and $3,262,000 for other project
costs. Acquisition was completed in January 2011 and preliminary plans were
completed in June 2015. Construction is scheduled to begin in April 2017 and be
completed by August 2019.
30 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
4. Shasta County—New Redding Courthouse. The amount of $133,077,000 is provided
for the construction phase of the New Redding Courthouse in Shasta County.
The new 165,296 gsf building will house 14 courtrooms. Total estimated project
cost is $154,671,000 without financing: $4,590,000 for acquisition, $6,028,000
for preliminary plans, $8,675,000 for working drawings, and $135,378,000
(CCCI 6055) for construction. The construction amount includes $117,051,000 for
the construction contract, $5,980,000 for contingency, $2,352,000 for architectural
and engineering fees, and $9,995,000 for other project costs. Acquisition was
completed in June 2012 and preliminary plans were completed in December 2015.
Construction is scheduled to begin in July 2017 and be completed by March 2020.
5. Tuolumne County—New Sonora Courthouse. The amount of $55,445,000 is
provided for the construction phase of the New Sonora Courthouse in Tuolumne
County. The new 61,537 gsf building will house five courtrooms. Total estimated
project cost is $64,157,000 without financing: $1,597,000 for acquisition, $3,049,000
for preliminary plans, $4,066,000 for working drawings, and $55,445,000
(CCCI 6055) for construction. The construction amount includes $47,734,000 for
the construction contract, $2,439,000 for contingency, $1,046,000 for architectural
and engineering fees, and $4,226,000 for other project costs. Acquisition was
completed in April 2012 and preliminary plans were completed in December
2015. Construction is scheduled to begin in July 2017 and be completed by
November 2019.
Item 0250‑301‑3138—Judicial Branch—Capital Outlay
1. El Dorado County—New Placerville Courthouse. The amount of $3,696,000 is
provided for completion of the preliminary plans phase to construct the New
Placerville Courthouse in El Dorado County. The new 77,559 gsf building
will house six courtrooms. Total estimated project cost is $81,719,000 without
financing: $2,795,000 for acquisition, $3,696,000 for preliminary plans, $4,918,000
for working drawings, and $70,310,000 (CCCI 6106) for construction. The
construction amount includes $60,925,000 for the construction contract, $3,113,000
for contingency, $1,325,000 for architectural and engineering fees, and $4,947,000
for other project costs. Acquisition is scheduled to be completed in September 2016
and preliminary plans are scheduled to be completed by February 2018.
Construction is scheduled to begin in February 2020 and be completed by
February 2022.
2. Los Angeles County—New Hollywood Courthouse. The amount of $14,729,000
is provided for the design‑build phase of the New Hollywood Courthouse in
Los Angeles County. The new 61,603 gsf building will house four courtrooms.
Total estimated project cost is $60,268,000 without financing: $936,000 for
acquisition and $59,332,000 (CCCI 6106) for design‑build. The design‑build
LEGISLATIVE ANALYST’S OFFICE 31
Supplemental Report of the 2016-17 Budget Act
amount includes $44,178,000 for the construction contract, $2,257,000 for
contingency, $4,061,000 for architectural and engineering fees, and $8,836,000
for other project costs. Acquisition was completed in June 2014. The design‑build
began in July 2014 and is scheduled to be completed by January 2019.
3. Mendocino County—New Ukiah Courthouse. The amount of $6,068,000 is provided
for completion of the working drawings phase to construct the New Ukiah
Courthouse in Mendocino County. The new 90,206 gsf building will house
eight courtrooms. Total estimated project cost is $94,455,000 without financing:
$5,673,000 for acquisition, $4,550,000 for preliminary plans, $6,068,000 for working
drawings, and $78,164,000 (CCCI 6055) for construction. The construction amount
includes $67,337,000 for the construction contract, $3,440,000 for contingency,
$1,726,000 for architectural and engineering fees, and $5,661,000 for other project
costs. Acquisition was completed in October 2015 and preliminary plans are
scheduled to be completed by November 2016. Construction is scheduled to begin
in March 2018 and be completed by June 2020.
4. Riverside County—New Indio Juvenile and Family Courthouse. The amount of
$1,628,000 is provided for the construction phase of the New Indio Juvenile and
Family Courthouse in Riverside County. The new 53,255 gsf building will house
five courtrooms. Total estimated project cost is $52,865,000 without financing:
$3,423,000 for acquisition, $2,174,000 for preliminary plans, $3,194,000 for working
drawings, and $44,074,000 (CCCI 6055) for construction. The construction amount
includes $37,922,000 for the construction contract, $1,937,000 for contingency,
$953,000 for architectural and engineering fees, and $3,262,000 for other project
costs. Acquisition was completed in January 2011 and preliminary plans were
completed in June 2015. Construction is scheduled to begin in April 2017 and be
completed by August 2019.
5. Riverside County—New Mid-County Civil Courthouse. The amount of $5,666,000
is provided for the working drawings phase of the New Mid‑County Civil
Courthouse in Riverside County. The new 89,690 gsf building will house nine
courtrooms. Total estimated project cost is $89,985,000 without financing:
$5,563,000 for acquisition, $4,259,000 for preliminary plans, $5,666,000 for working
drawings, and $74,497,000 (CCCI 6055) for construction. The construction amount
includes $64,330,000 for the construction contract, $3,287,000 for contingency,
$1,633,000 for architectural and engineering fees, and $5,247,000 for other
project costs. Acquisition was completed in June 2015 and preliminary plans are
scheduled to be completed by October 2016. Construction is scheduled to begin in
November 2018 and be completed by February 2021.
6. Sacramento—New Sacramento Criminal Courthouse. The amount of $16,000,000
is provided for the working drawings phase for the New Sacramento Criminal
32 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Courthouse in Sacramento County. The new 538,000 gsf building will house
53 courtrooms. Total estimated project cost is $489,957,000 without financing:
$12,656,000 for acquisition, $11,000,000 for preliminary plans, $16,000,000
for working drawings, and $450,301,000 (CCCI 6106) for construction. The
construction amount includes $389,345,000 for the construction contract,
$19,892,000 for contingency, $7,478,000 for architectural and engineering fees, and
$33,586,000 for other project costs. Acquisition was completed in June 2013 and
preliminary plans are scheduled to be completed by July 2017. Construction is
scheduled to begin in April 2019 and be completed by July 2022.
7. Santa Barbara County—New Santa Barbara Criminal Courthouse. The amount
of $5,894,000 is provided for completion of the working drawings phase and
$400,000 is provided for demolition work for the construction phase of the New
Santa Barbara Criminal Courthouse in Santa Barbara County. The new 92,331 gsf
building will house eight courtrooms. Total estimated project cost is $99,409,000
without financing: $10,568,000 for acquisition, $4,411,000 for preliminary plans,
$5,894,000 for working drawings, and $78,536,000 (CCCI 6106) for construction.
The construction amount includes $67,707,000 for the construction contract,
$3,459,000 for contingency, $1,660,000 for architectural and engineering fees, and
$5,710,000 for other project costs. Acquisition was completed in July 2011 and
preliminary plans are scheduled to be completed by October 2016. Construction is
scheduled to begin in November 2018 and be completed by February 2022.
8. Shasta County—New Redding Courthouse. The amount of $2,301,000 is provided
for demolition work for the construction phase of the New Redding Courthouse
in Shasta County. The new 165,296 gsf building will house 14 courtrooms.
Total estimated project cost is $154,671,000 without financing: $4,590,000 for
acquisition, $6,028,000 for preliminary plans, $8,675,000 for working drawings,
and $135,378,000 (CCCI 6055) for construction. The construction amount includes
$117,051,000 for the construction contract, $5,980,000 for contingency, $2,352,000
for architectural and engineering fees, and $9,995,000 for other project costs.
Acquisition was completed in June 2012 and preliminary plans were completed in
December 2015. Construction is scheduled to begin in July 2017 and be completed
by March 2020.
9. Sonoma County—New Santa Rosa Criminal Courthouse. The amount of $11,252,000
is provided for completion of the working drawings phase of the New Santa
Rosa Criminal Courthouse in Sonoma County. The new 169,342 gsf building
will house 15 courtrooms. Total estimated project cost is $174,784,000 without
financing: $6,698,000 for acquisition, $7,670,000 for preliminary plans, $11,252,000
for working drawings, and $149,164,000 (CCCI 6106) for construction. The
construction amount includes $125,995,000 for the construction contract, $6,437,000
for contingency, $3,710,000 for architectural and engineering fees, and $13,022,000
LEGISLATIVE ANALYST’S OFFICE 33
Supplemental Report of the 2016-17 Budget Act
for other project costs. Acquisition was completed in April 2012 and preliminary
plans are scheduled to be completed by July 2016. Construction is scheduled to
begin in January 2018 and be completed by December 2020.
10. Stanislaus County—New Modesto Courthouse. The amount of $15,252,000 is
provided for completion of the working drawings phase and $2,066,000 is
provided for demolition work for the construction phase of the New Modesto
Courthouse in Stanislaus County. The new 308,964 gsf building will house
27 courtrooms. Total estimated project cost is $262,709,000 without financing:
$13,766,000 for acquisition, $11,026,000 for preliminary plans, $15,252,000
for working drawings, and $222,665,000 (CCCI 6106) for construction. The
construction amount includes $192,382,000 for the construction contract, $9,829,000
for contingency, $4,021,000 for architectural and engineering fees, and $16,433,000
for other project costs. Acquisition was completed in December 2014 and
preliminary plans are scheduled to be completed by March 2017. Construction is
scheduled to begin in April 2018 and be completed by February 2021.
Item 0540‑301‑6051—California Natural Resources Agency—
Capital Outlay
1. Calexico New River Parkway Project Reappropriation. The budget provides a
reappropriation of $800,000 for the state‑funded portion of the Calexico New
River Parkway Project. The total estimated project cost is $19,000,000 including
preliminary plans ($1,500,000) and construction ($3,500,000). The City of Calexico
is in the final stages of the planning and design phase for the project. The project
began in 2011, and construction is estimated to begin in 2016. The project is
expected to be completed by 2019.
Item 0690‑301‑0001—Office of Emergency Services—Capital Outlay
1. Relocation of Red Mountain Communications Site, Del Norte County—Working
Drawings. The budget provides a reappropriation of $1,261,000 for working
drawings to relocate the Red Mountain public safety communications site
in Del Norte County to three new locations: Rattlesnake Mountain, Alder
Camp, and Rodgers Peak. The total estimated project cost is $20,009,000,
including preliminary plans ($2,683,000), working drawings ($1,261,000), and
construction ($16,065,000) (CCCI 5796). The amount for construction includes
$10,271,000 for construction contracts, $514,000 for contingency, $1,068,000 for
architectural and engineering services, $2,526,000 for agency retained items,
and $1,686,000 for other project costs. Construction is scheduled to begin in
October 2018 and be completed in April 2021.
34 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
2. Headquarters Complex, Rancho Cordova: Public Safety Communications Network
Operations Center—Preliminary Plans and Working Drawings. The budget
provides a reappropriation of the remaining balance necessary to complete the
preliminary plans phase, approximately $380,000, and $92,000 for the working
drawings phase to design and construct a new Public Safety Communications
Network Operations Center, which includes a microwave path and 120 foot
communications tower at the Office of Emergency Services’ headquarters
complex in Rancho Cordova. The total estimated project cost is $6,229,000,
including preliminary plans ($609,000), working drawings ($92,000), and
construction ($5,528,000) (CCCI 6109). The amount for construction includes
$1,869,000 for construction contracts, $131,000 for contingency, $308,000 for
architectural and engineering services, $2,837,000 for agency retained items, and
$383,000 for other project costs. Construction is scheduled to begin in August 2017
and be completed in November 2018.
Item 2665-491—High-Speed Rail Authority—Capital Outlay
1. California High-Speed Rail System Planning. The amount of $145,174,000 is
reappropriated for the acquisition and design phases to continue environmental and
preliminary engineering work for Phase I of the high‑speed rail system as defined in
Proposition 1A. The last environmental report for Phase I is expected to be completed in
December 2017.
Item 2720‑301‑0044—California Highway Patrol—Capital Outlay
1. Sawtooth Ridge Tower Replacement. The California Highway Patrol (CHP) shall
report to the appropriate fiscal committees of the Legislature, the Legislative
Analyst’s Office, and the Department of Finance no later than January 1, 2019
on the feasibility of a conservation easement with a state, federal, or nonprofit
conservation organization for the remainder of the property acquired for the CHP
Enhanced Radio System Tower Replacement project at Sawtooth Ridge and any
mitigation lands required by the analysis conducted pursuant to the California
Environmental Quality Act. The report should include a discussion of how
future maintenance would be conducted at Sawtooth Ridge so as to not affect the
ecological integrity of the area.
2. El Centro—Area Office Replacement. The amount of $4,332,000 is provided
for the acquisition and performance criteria phases of this project to acquire
approximately 6.5 acres and provide a new 34,000 square foot (sf) area office and
auto service building. The facility will also include public and secured parking, a
radio antenna tower and vault, a fuel island with an above‑ground storage tank
and canopy, and an emergency generator with the building. The total project cost
of $34,745,000 includes $2,855,000 for acquisition, $1,477,000 for the performance
LEGISLATIVE ANALYST’S OFFICE 35
Supplemental Report of the 2016-17 Budget Act
criteria phase, and $30,413,000 for the design‑build phase. Acquisition is expected
to occur in March 2017, with performance criteria completed in September 2017.
The design‑build contract is scheduled to be executed February 2018, and the
construction is scheduled to be completed September 2019.
3. Hayward—Area Office Replacement. The amount of $15,038,000 is provided
for the acquisition and performance criteria phases of this project to acquire
approximately 6 acres and provide a new 48,000 sf area office and auto service
building. The facility will also include public and secured parking, a radio
antenna tower and vault, a fuel island with an above‑ground storage tank and
canopy, and an emergency generator with the building. The total project cost of
$53,141,000 includes $13,383,000 for acquisition, $1,655,000 for the performance
criteria phase, and $38,103,000 for the design‑build phase. Acquisition is expected
to occur in January 2017, with performance criteria completed in September 2017.
The design‑build contract is scheduled to be executed February 2018, and the
construction is scheduled to be completed December 2019.
4. Ventura—Area Office Replacement. The amount of $5,642,000 is provided
for the acquisition and performance criteria phases of this project to acquire
approximately 6.3 acres and provide a new 47,000 sf area office and auto service
building. The facility will also include public and secured parking, a radio
antenna tower and vault, a fuel island with an above‑ground storage tank and
canopy, and an emergency generator with the building. The total project cost of
$42,717,000 includes $4,019,000 for acquisition, $1,623,000 for the performance
criteria phase, and $37,075,000 for the design‑build phase. Acquisition is expected
to occur in December 2016, with performance criteria completed in September
2017. The design‑build contract is scheduled to be executed February 2018, and the
construction is scheduled to be completed December 2019.
5. San Bernardino—Area Office Replacement. The amount of $5,369,000 is provided
for the acquisition and performance criteria phases of this project to acquire
approximately 5.5 acres and provide a new 44,000 sf area office and auto service
building. The facility will also include public and secured parking, a radio
antenna tower and vault, a fuel island with an above‑ground storage tank and
canopy, and an emergency generator with the building. The total project cost of
$38,523,000 includes $3,867,000 for acquisition, $1,502,000 for the performance
criteria phase, and $33,154,000 for the design‑build phase. Acquisition is expected
to occur in January 2017, with performance criteria completed in September 2017.
The design‑build contract is scheduled to be executed February 2018, and the
construction is scheduled to be completed September 2019.
36 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Item 2720‑491—California Highway Patrol—Capital Outlay
1. Santa Barbara—Replacement Facility. The amount of $32,415,000 is reappropriated
for all phases of this project to acquire approximately 5.7 acres and provide a
new 25,000 sf area office and auto service building. The facility will also include
public and secured parking, a radio antenna tower and vault, a fuel island with
an above‑ground storage tank and canopy, and an emergency generator with the
building. The total project cost of $32,415,000 includes: $8,359,000 for acquisition,
$1,517,000 for the performance criteria phase, and $24,316,000 for the design‑
build phase. Acquisition is expected to occur in January 2017, with performance
criteria completed in September 2017. The design‑build contract is scheduled to
be executed February 2018, and the construction is scheduled to be completed
September 2019.
Item 2740‑301‑0044—Department of Motor Vehicles—Capital Outlay
1. Delano—Field Office Replacement. The amount of $1,483,000 is provided for
the preliminary plans and working drawings phases of this project to acquire
approximately 1.9 acres to provide a new 10,718 sf field office. This facility will
include adequate parking for staff and customers, an attached drive test canopy,
a motorcycle testing area, and will also be a Zero Net Energy building. The
total project cost of $11,825,000 includes $1,022,000 for acquisition, $688,000
for preliminary plans, $795,000 for working drawings, and $9,320,000 for
construction. Acquisition is expected to be completed February 2017, with
preliminary plans completed May 2017. Construction is anticipated to begin
August 2018 and be completed February 2020.
2. Santa Maria—Field Office Replacement. The amount of $1,811,000 is provided for
the preliminary plans and working drawings phases of this project to acquire
approximately 2.4 acres to provide a new 13,342 sf field office. This facility
will include adequate parking for staff and customers, an attached drive test
canopy, a motorcycle testing area, and will also be a Zero Net Energy building.
This facility will house the driver license and vehicle registration programs as
well as the occupational licensing program. The total project cost of $16,021,000
includes $2,637,000 for acquisition, $897,000 for preliminary plans, $914,000 for
working drawings, and $11,573,000 for construction. Acquisition is expected
to be completed February 2017, with preliminary plans completed May 2017.
Construction is anticipated to begin August 2018 and be completed February 2020.
3. Inglewood—Field Office Replacement. The amount of $1,027,000 is provided for the
working drawings phase of this project to demolish the existing Inglewood field
office and replace it with a new 15,043 sf facility on the same site. This facility will
include adequate parking for staff and customers, an attached drive test canopy,
LEGISLATIVE ANALYST’S OFFICE 37
Supplemental Report of the 2016-17 Budget Act
a motorcycle testing area, and will also be a Zero Net Energy building. The total
project cost of $15,159,000 includes $1,017,000 for preliminary plans, $1,027,000
for working drawings, and $13,115,000 for construction. The preliminary plan
phase is expected be completed October 2016. Construction is anticipated to begin
November 2017 and be completed September 2019.
4. San Diego—Normal Street Field Office Replacement. The amount of $1,318,000 is
provided for the preliminary plans phase of this project to demolish the existing San
Diego Normal Street field office and replace it with a new 18,540 sf facility on the same
site. This facility will include adequate parking for staff and customers, an attached drive
test canopy, a motorcycle testing area, and will also be a Zero Net Energy building. The
total project cost of $19,257,000 includes $1,318,000 for preliminary plans, $1,295,000
for working drawings, and $16,644,000 for construction. The preliminary plan phase is
expected to be completed July 2017. Construction is anticipated to begin January 2019 and
be completed May 2020.
Item 3125‑301‑XXXX—California Tahoe Conservancy—Capital Outlay
1. Implementation of the Lake Tahoe Environmental Improvement Program. The
budget provides $8,691,000 for implementation of the Lake Tahoe Environmental
Improvement Program. The total estimated project cost is $8,691,000, which is all
construction cost.
Item 3340‑301‑0001—California Conservation Corps—Capital Outlay
1. Napa: New Residential Center. The budget provides $200,000 to conduct a site
evaluation for a new residential center in the Napa area. The total estimated
project costs include $200,000 for site acquisition, $1,000,000 for preliminary plans,
$2,000,000 for working drawings, and $24,800,000 for construction. The project
would be approximately 48,150 sf which will include nine buildings consisting of
an administration building (3,000 sf); four dormitories (15,000 sf); an education
building (5,500 sf); a recreation building (5,000 sf); a multipurpose with kitchen
and dining (9,000 sf); warehouse with work area (10,500 sf); a hazardous materials
storage room (150 sf); and paved surface for service and staging areas, walkways,
driveways, and parking (100,000 sf). Preliminary plans are scheduled to be
approved in July 2019. The contract is scheduled to be awarded in August 2020
and construction is scheduled to be completed in February 2022. This center will
be designed to accommodate 80 corpsmembers.
2. Pomona: New Residential Center. The budget provides $100,000 to conduct a site
evaluation for a new residential center in the Pomona area. The total estimated
project costs include $100,000 for site acquisition, $1,000,000 for preliminary plans,
$2,000,000 for working drawings, and $24,920,000 for construction. The project
38 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
would be approximately 48,150 sf which will include nine buildings consisting of
an administration building (3,000 sf); four dormitories (15,000 sf); an education
building (5,500 sf); a recreation building (5,000 sf); a multipurpose with kitchen
and dining (9,000 sf); warehouse with work area (10,500 sf); a hazardous materials
storage room (150 sf); and paved surface for service and staging areas, walkways,
driveways, and parking (100,000 sf). Preliminary plans are scheduled to be
approved in July 2019. The contract is scheduled to be awarded in August 2020
and construction is scheduled to be completed in February 2022. This center will
be designed to accommodate 80 corpsmembers.
3. Ukiah: New Residential Center. The budget provides $100,000 to conduct a site
evaluation for a new residential center in the Ukiah area. The total estimated
project costs include $300,000 for site acquisition, $1,000,000 for preliminary plans,
$2,000,000 for working drawings, and $24,720,000 for construction. The project
would be approximately 48,150 sf which will include nine buildings consisting of
an administration building (3,000 sf); four dormitories (15,000 sf); an education
building (5,500 sf); a recreation building (5,000 sf); a multipurpose with kitchen
and dining (9,000 sf); warehouse with work area (10,500 sf); a hazardous materials
storage room (150 sf); and paved surface for service and staging areas, walkways,
driveways, and parking (100,000 sf). Preliminary plans are scheduled to be
approved in July 2019. The contract is scheduled to be awarded in August 2020
and construction is scheduled to be completed in February 2022. This center will
be designed to accommodate 80 corpsmembers.
4. Auburn Campus: Kitchen, Multipurpose Room, and Dorm Replacement. The amount
of $1,297,000 is reappropriated from 2015‑16 for working drawings for a new
kitchen, multipurpose room, and dormitory to replace the current facilities at
the Auburn campus. The budget provides $19,666,000 for the construction phase.
The total estimated project costs are $22,321,000, including preliminary plans
($1,358,000), working drawings ($1,297,000), and construction ($19,666,000). The
new approximately 11,300 sf multipurpose building will contain a commercial
kitchen and food service line, dining hall, and recreational auditorium. The new
approximately 18,000 sf dormitory will provide sleeping quarters for 58 male
corpsmembers; 28 female corpsmembers; and approximately 45 corpsmember
orientation, motivation, education, and training corpsmembers. Completion of
working drawings is rescheduled from March 2017 to November 2017. Completion
of construction is rescheduled from May 2019 to May 2020.
Item 3340‑301‑0660—California Conservation Corps—Capital Outlay
1. Tahoe Base Center: Equipment Storage Relocation—Phase II—Facility Acquisition
and Improvements. The amount of $1,560,000 is reappropriated from 2015‑16 for
working drawings and renovation of an equipment storage facility at the Tahoe
LEGISLATIVE ANALYST’S OFFICE 39
Supplemental Report of the 2016-17 Budget Act
Base Center. The total estimated project costs include $875,000 for site acquisition,
$75,000 for preliminary plans, $245,000 for working drawings, and $1,315,000
for construction. The project would add a total of 12,473 sf, replacing 8,576 sf of
existing storage space. Completion of construction is rescheduled from June 2016
to May 2018.
Item 3540‑301‑0001—Department of Forestry and Fire Protection—
Capital Outlay
1. Potrero Forest Fire Station: Replace Facility—Acquisition. The budget provides
$400,000 General Fund for the acquisition phase to relocate and replace the
Potrero Forest Fire Station. The project includes acquiring a suitable site for the
construction of a standard two‑engine fire station, including a 14‑bed barracks/
messhall, three‑bay apparatus building, and a generator/pump storage building
with a generator. Total project costs are estimated at $12,782,000, including
acquisition ($400,000), preliminary plans ($865,000), working drawings ($920,000),
and construction ($10,597,000). The construction amount includes $7,543,000
for the construction contract, $435,000 for contingency, and $2,619,000 for other
project costs. The current project schedule estimates preliminary plans will
begin January 2018 and be completed in January 2019. The working drawings are
estimated to begin January 2019 and be completed in January 2020. Construction
is scheduled to begin May 2020 and to be completed in November 2021.
2. Statewide: Replace Communications Facilities, Phase V—Preliminary Plans. The
budget provides $1,677,000 General Fund for preliminary plans to replace the
existing telecommunication infrastructure at six sites and add an additional tower
at a seventh location. Total project costs are estimated at $21,338,000, including
preliminary plans ($1,677,000), working drawings ($1,067,000), and construction
($18,594,000). The construction amount includes $14,616,000 for contracts, $762,000
for contingency, $60,000 for agency retained items, and $3,156,000 for other
project costs. The current project schedule estimates preliminary plans will
begin January 2017 and be completed in January 2018. The working drawings are
estimated to begin January 2018 and be completed in January 2019. Construction
is scheduled to begin May 2020 and to be completed in November 2020.
3. Mount Bullion Conservation Camp: Emergency Sewer. The budget provides
$833,000 General Fund for construction to replace the sewage disposal system
at Mount Bullion Conservation Camp. Total project costs are estimated at
$833,000, including preliminary plans ($28,000), working drawings ($28,000), and
construction ($777,000). The construction amount includes $693,000 for contracts,
$35,000 for contingency, $28,000 for architectural and engineering services, and
$21,000 for other project costs. The current project schedule estimates preliminary
plans will begin July 2016 and be completed in December 2016. The working
40 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
drawings are estimated to begin December 2016 and be completed in May
2017. Construction is scheduled to begin August 2017 and to be completed in
February 2018.
Item 3540‑490—Department of Forestry of Fire Protection—Capital
Outlay
1. Statewide Construct Communication Facilities, Phase III. The budget reappropriates
$15,893,000 General Fund for the construction phase of this project which
constructs new radio towers, vaults, and generators at nine sites statewide to
replace older existing communications facilities. Upon completion of the new
facilities, the old towers and vaults will be demolished. The total estimated project
cost is $17,068,268, including preliminary plans ($905,966), working drawings
($1,611,752), and construction ($14,550,550). The current project schedule estimates
construction to be completed in August 2016.
2. Fawn Lodge Fire Station—Replace Facility and Install New Well. The budget
reappropriates $5,814,000 lease revenue bond financing authority for the
construction phase of this project which is to construct a standard 12‑bed,
barracks/messhall, and three‑bay apparatus building for a two‑engine fire
station. Construction includes a new generator/pump/storage building, new
fueling facilities, hazardous materials building, and vehicle wash rack, and
demolishing existing buildings, drill and develop new domestic water well, install
20,000‑gallon water storage tank and associated plumbing, install fire sprinkler
system in buildings, replace existing access bridge to the facility, install new
leach field with lift station, utilities, paving, fencing, drainage, landscaping, and
other appurtenances necessary for the project. The total estimated project cost is
$6,664,000, including preliminary plans ($674,000), working drawings ($176,000),
and construction ($5,814,000). The current project schedule estimates construction
to be completed in August 2016.
3. Garden Valley Fire Station—Replace Facility. The budget reappropriates $6,511,000
lease revenue bond finance authority for the construction phase of this project
which includes construction of a 12‑bed barracks/mess hall, three‑bay apparatus
building with a battalion chief complement, and a generator/storage building
with generator. This project also includes a fuel dispensing system, fuel tanks,
hose wash rack, and demolishing and removing existing buildings on site. Site
work includes clearing, grading, drainage, paving, walkways, curbs, hook‑up to
public water, new septic system, electrical, telephone, irrigation, lighting, fencing,
landscaping, all utilities, and associated appurtenances. The total estimated
project cost is $7,701,000, including preliminary plans ($629,000), working
drawings ($561,000), and construction ($6,511,000). The current project schedule
estimates construction to be completed in November 2016.
LEGISLATIVE ANALYST’S OFFICE 41
Supplemental Report of the 2016-17 Budget Act
4. South Operations Area Headquarters—Relocate Facility. The budget reappropriates
$45,464,000 lease revenue bond finance authority for the working drawings
and construction phases of this project which constructs a new Riverside
Essential Services Headquarters Facility consisting of an office/command center,
administration building, construction/engineering office building, electrical
shop, mechanical shop, auto shop, warehouse, training center, groundskeeper and
generator/hazardous materials building, communications tower, and emergency
command center/vault equipment. The existing facility will be surplused. The
total estimated project cost is $50,197,270, including acquisition ($1,320,359),
preliminary plans ($803,000), working drawings ($3,719,700), and construction
($44,354,211). The current project schedule estimates working drawings to be
completed in August 2016. Construction is scheduled to begin August 2016 and to
be completed in September 2018.
5. Paso Robles Forest Fire Station—Replace Facility. The budget reappropriates
$7,548,000 lease revenue bond finance authority for the working drawings
and construction phases of this project which is to replace the existing facility
including the demolition of the existing structures, and the design and phased
construction of a standard 16‑bed barracks/messhall, three‑bay apparatus storage
building, two‑office administration building, vehicle wash rack with treatment/
recycling equipment, generator/pump/storage building with generator, transfer
switch and fuel supply, hose wash rack and fuel storage tank canopy. Included
in the project are site perimeter fencing, gates, grading, landscaping, irrigation,
replacement and connections for all utilities, paving, curbing, sidewalks,
and appurtenances. The total estimated project cost is $8,115,000, including
preliminary plans ($567,000), working drawings ($491,000), and construction
($7,057,000). The current project schedule estimates working drawings to be
completed in August 2016. Construction is scheduled to begin September 2016
and to be completed in June 2018.
6. Badger Forest Fire Station—Replace Facility. The budget reappropriates
$4,926,000 lease revenue bond finance authority for the working drawings and
construction phases of this project which constructs a new single‑engine fire
station. Construction includes an eight‑bed barracks/messhall building; two‑
bay apparatus building; pump house/generator building; and all associated
utilities, paving, and appurtenances. The total estimated project cost is $5,309,000,
including preliminary plans ($580,000), working drawings ($367,000), and
construction ($4,362,000). The current project schedule estimates working
drawings to be completed in August 2016. Construction is scheduled to begin
August 2016 and to be completed in October 2017.
7. Westwood Forest Fire Station—Replace Facility. The budget reappropriates
$6,612,000 lease revenue bond finance authority for the working drawings
42 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
and construction phases of this project which constructs a prototypical single‑
building fire station and generator/pump/storage building with generator.
Site improvements include demolition of the existing facility, grading, paving,
new utilities including fiber optic extension and septic system, hose wash rack,
wharf hydrant, above ground fuel vaults, site fencing, concrete masonry unit
(CMU) wall, flagpoles, trash enclosure, site/curb/gutter/sidewalks, site lighting,
landscaping/irrigation, and storm drainage. The total estimated project cost is
$7,068,000, including preliminary plans ($456,000), working drawings ($362,000),
and construction ($6,250,000). The current project schedule estimates working
drawings to be completed in December 2016. Construction is scheduled to begin
December 2016 and to be completed in December 2018.
8. Vina Helitack Base—Replace Facility. The budget reappropriates $13,062,000 lease
revenue bond finance authority for the preliminary plans, working drawings,
and construction phases of this project which constructs a new helitack base
consisting of a 22‑bed barracks, three‑bay apparatus, training tower, renovation of
existing hanger, and paving and landscaping. The total estimated project cost is
$15,260,000, including preliminary plans ($934,000), working drawings ($939,000),
and construction ($13,387,000). The current project schedule estimates working
drawings to be completed in February 2017. Construction is scheduled to begin
February 2017 and to be completed in August 2018.
9. Altaville Forest Fire Station—Replace Automotive Shop. The budget reappropriates
$7,961,000 lease revenue bond finance authority for the working drawings and
construction phases of this project which constructs a new five‑bay automotive
shop, generator/pump/storage building with generator, retaining walls, retention
pond, walkways, curbs, fencing, and landscaping. The total estimated project
cost is $10,098,000, including preliminary plans ($827,780), working drawings
($627,800), and construction ($8,642,420). The current project schedule estimates
working drawings to be completed in December 2016. Construction is scheduled
to begin December 2016 and to be completed in May 2018.
10. Butte Unit Fire Station/Unit Headquarters—Replace Facility. The budget
reappropriates $34,537,000 lease revenue bond finance authority for the
preliminary plans, working drawings, and construction phases of this project
which replaces the existing unit headquarters facility with a new 20‑bed barracks,
three‑bay apparatus building, administration building, five‑bay automotive
shop, two‑bay dozer shed, physical fitness building, service center/warehouse
building, maintenance building, radio repair facility, and generator building, and
includes demolition of existing buildings and abatement of hazardous materials.
The total estimated project cost is $34,537,000, including preliminary plans
($1,643,000), working drawings ($2,110,000), and construction ($30,784,000). The
current project schedule estimates working drawings to be completed in January
LEGISLATIVE ANALYST’S OFFICE 43
Supplemental Report of the 2016-17 Budget Act
2017. Construction is scheduled to begin January 2017 and to be completed in
August 2018.
11. San Mateo/Santa Cruz Unit Headquarters—Relocate Automotive Shop. The budget
reappropriates $10,334,000 lease revenue bond finance authority for the working
drawings and construction phases of this project which constructs a new
automotive shop facility consisting of a five‑bay vehicle repair facility, generator/
fire pump building, storage building, site demolition, grading and paving,
covered test pit, new fuel tanks, and fire suppression water storage tank. The total
estimated project cost is $12,135,000, including preliminary plans ($1,043,690),
working drawings ($868,690), and construction ($10,222,620). The current
project schedule estimates working drawings to be completed in January 2017.
Construction is scheduled to begin January 2017 and to be completed in June 2018.
12. Pine Mountain Forest Fire Station—Relocate Facility. The budget reappropriates
$10,576,000 lease revenue bond finance authority for the preliminary plans,
working drawings, and construction phases of this project which is to construct
a prototypical single‑building, one‑engine fire station and generator/pump/
storage building with generator and transfer switch and fuel supply, and a water
treatment building. Site improvements include fuel vault with cover and fueling
equipment, water storage tank, well housing and pressure distribution system,
septic tank and leach field, and all utilities, and site work including grading
(which may include blasting subsurface rock), paving, hose wash rack, wharf
hydrant, site fencing, flagpoles, trash enclosure, site/curb/gutter/sidewalks, site
lighting, landscaping/irrigation, storm drainage, entrance, and all appurtenances.
The total estimated project cost is $10,969,000, including acquisition ($393,000),
preliminary plans ($582,000), working drawings ($724,000), and construction
($9,270,000). The current project schedule estimates working drawings to be
completed in May 2017. Construction is scheduled to begin May 2017 and to be
completed in July 2019.
13. Soquel Fire Station—Replace Facility. The budget reappropriates $11,111,000
lease revenue bond finance authority for the preliminary plans, working
drawings, and construction phases of this project which constructs a prototypical
single‑building, one‑engine fire station and generator/pump/storage building
with generator and office/education center/storage building for the Soquel
Demonstration State Forest. The existing forestry trailer will be relocated
within a 25‑mile radius to a new site and provided with utility hook‑ups. Site
improvements will include demolition of the existing facility, grading, paving,
new utilities including fiber optic extension, septic system, hose wash rack,
wharf hydrant, above‑ground fuel vaults, site fencing, CMU wall, flagpoles, trash
enclosure, site/curb/gutter/sidewalks, site lighting, landscaping/irrigation, storm
drainage, entrance, and all appurtenances. The total estimated project cost is
44 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
$11,111,000, including preliminary plans ($763,000), working drawings ($768,000),
and construction ($9,580,000). The current project schedule estimates working
drawings to be completed in May 2017. Construction is scheduled to begin
May 2017 and to be completed in June 2019.
14. Academy—Construct Dormitory and Expand Messhall. The budget reappropriates
$9,406,000 lease revenue bond financing authority for the working drawings
and construction phases of this project which constructs a new three‑story,
85‑bed dormitory, located at the California Department of Forestry and Fire
Protection (CalFire) Academy in Ione, California. The new construction will
consist of 41 two‑person living units and three one‑person living units with
complete restroom facilities, meeting rooms, student lounge/recreation room,
site improvements, and covered patio and walkway. Demolition of three 1940’s
era modular buildings is part of the scope of work. The total estimated project
cost is $14,784,000, including preliminary plans ($1,183,000), working drawings
($977,000), and construction ($12,624,000). The current project schedule estimates
working drawings to be completed in November 2016. Construction is scheduled
to begin November 2016 and to be completed in May 2018.
15. Cayucos Fire Station—Replace Facility. The budget reappropriates $11,019,000
lease revenue bond finance authority for the preliminary plans, working
drawings, and construction phases of this project which designs and constructs
a prototypical eight‑bed barracks/messhall building; one‑engine, two‑bay
apparatus building; generator/pump/storage building with emergency generator
and transfer switch; and a self‑contained breathing apparatus (SCBA) repair,
refill/storage room. This project includes replacement/upgrade of underground
community utilities and/or connections (water, sewer, electric, gas, telephone/
radio), fuel facility (above ground storage tanks/dispensing system, canopy),
security system (security lighting, motion detectors w/phone alarm to Calfire
dispatch), vehicle wash pad and a hose wash rack and demolition and removal of
existing buildings on site. Site work includes grading, paving, curbs, walkways,
gutters, drainage/landscaping, retaining walls, fencing, entrance gate, and all
associated appurtenances. The total estimated project cost is $11,019,000, including
preliminary plans ($777,000), working drawings ($668,000), and construction
($9,574,000). The current project schedule estimates preliminary plans will be
completed in July 2016. The working drawings are estimated to begin July 2016
and be completed in June 2017. Construction is scheduled to begin June 2017 and
to be completed in December 2018.
16. Rincon Fire Station—Replace Facility. The budget reappropriates $13,890,000 lease
revenue bond finance authority for the preliminary plans, working drawings,
and construction phases of this project which will design and construct a 12‑bed
barracks/messhall building, three‑bay apparatus building with a battalion
LEGISLATIVE ANALYST’S OFFICE 45
Supplemental Report of the 2016-17 Budget Act
chief office, generator/pump building with emergency generator and transfer
switch, storage/self contained breathing apparatus building, wash rack with
canopy and equipment building, fuel island with canopy, communications
tower with telephone/radio upgrades, trash enclosure, and hose wash rack. The
scope includes phased demolition and hazmat abatement of existing buildings,
site drainage, erosion control, landscaping/irrigation, storage tank, upgrading
or replacing underground utilities (septic, water, propane), paving, parking,
security fencing, gates, lighting and all associated appurtenances. The total
estimated project cost is $13,890,000, including preliminary plans ($947,000),
working drawings ($943,000), and construction ($12,000,000). The current project
schedule estimates preliminary plans would begin June 2016 and be completed
in September 2017. The working drawings are estimated to begin September 2017
and be completed in September 2018. Construction is scheduled to begin
September 2018 and to be completed in May 2020.
17. Parkfield Fire Station—Relocate Facility. The budget reappropriates $8,077,000
lease revenue bond finance authority for acquisition, preliminary plans, working
drawings, and construction phases of this project which is to acquire a suitable
site, design and construct a prototypical single engine station, a generator/pump
building with emergency generator and transfer switch, a storage building, and
a vehicle wash rack. Demolition of existing buildings with hazmat abatement is
included in the project. Project includes new underground community utilities
and/or connections (water, sewer, electric, gas, telephone/radio), fuel facility
(storage tanks/dispensing system, canopy), hose wash rack, grading, paving,
walkways, and landscaping, propane system, septic system, potable water well,
water treatment system, potable water storage, security fencing, lighting, and
associated appurtenances. The total estimated project cost is $8,077,000, including
acquisition ($283,000), preliminary plans ($609,000), working drawings ($458,000),
and construction ($6,727,000). The current project schedule estimates acquisition
to be complete in December 2016. Preliminary plans will begin December 2016
and will be completed in December 2017. The working drawings are estimated to
begin December 2017 and will be completed in December 2018. Construction is
scheduled to begin December 2018 and to be completed in October 2020.
18. Baker Fire Station—Relocate Facility. The budget reappropriates $11,187,000 lease
revenue bond finance authority for the acquisition, preliminary plans, working
drawings, and construction phases of this project which is to acquire a suitable
site, design and construct a prototypical twelve‑bed barracks/messhall building,
two‑engine three‑bay apparatus building, generator/pump/storage building with
emergency generator and transfer switch, fuel facilities, hose rack, vehicle wash
rack, underground utilities, grading, paving, walkways, landscaping, propane
system, septic system, potable water well, water treatment system, potable
water storage, security fencing, gates, lighting, staging area, and associated
46 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
appurtenances. Demolition of existing buildings with hazmat abatement is
included in the project. The total estimated project cost is $11,187,000, including
acquisition ($200,000), preliminary plans ($774,000), working drawings ($742,000),
and construction ($9,471,000). The current project schedule estimates acquisition
to be complete in September 2016. Preliminary plans will begin September 2016
and will be completed in November 2017. The working drawings are estimated to
begin November 2017 and will be completed in December 2018. Construction is
scheduled to begin December 2018 and to be completed in July 2020.
19. Bieber Forest Fire Station/Helitack Base—Relocate Facility. The budget
reappropriates $24,196,000 lease revenue bond finance authority for acquisition,
preliminary plans, working drawings, and construction phases of this project
which is to relocate the Bieber Helitack Base. Project includes site acquisition,
design, and construction of a 36‑bed barracks/messhall, three‑bay apparatus
building, dozer/transport shed, helicopter facilities, office building, four‑bay
utility parking garage and 25,000 gallon water storage tank. The total estimated
project cost is $24,196,000, including acquisition ($230,000), preliminary plans
($1,274,000), working drawings ($1,452,000), and construction ($21,240,000). The
current project schedule estimates acquisition to be complete in August 2016.
Preliminary plans will begin August 2016 and will be completed in June 2017.
The working drawings are estimated to begin June 2017 and will be completed in
June 2018. Construction is scheduled to begin June 2018 and to be completed in
March 2019.
Item 3640‑302‑6029—Wildlife Conservation Board—Capital Outlay
1. San Joaquin River Conservancy Acquisitions and Projects. The budget appropriates
$2.5 million for the San Joaquin River Conservancy to implement its public
access, recreation, and environmental restoration capital improvement program.
(The Wildlife Conservation Board helps administer the conservancy’s funding
and programs.) This total consists of $1.5 million unspent from a previous
appropriation of Proposition 40 (water and parks bond of 2002) and $1 million in
reimbursement authority. The funding will be used to continue land acquisitions
and restoration and recreation projects in development of the San Joaquin River
Parkway.
Item 3790‑301‑0001—Department of Parks and Recreation—
Capital Outlay
1. Angel Island State Park—Immigration Station Hospital Rehabilitation. The budget
provides $2,952,000 for Phase 4 construction to finish the interior building
improvements to complete the rehabilitation of the United States Immigration
Station Hospital building. The total estimated project cost is $2,952,000, consisting
LEGISLATIVE ANALYST’S OFFICE 47
Supplemental Report of the 2016-17 Budget Act
of construction only. Design documents were donated. Construction is scheduled
to begin December 2016 and be completed November 2017.
2. Malakoff Diggins State Historic Park—Solar Panel Generator. The budget
provides $700,000 for preliminary plans, working drawings, and construction to
install a solar panel generator to replace the existing old diesel generator no longer
able to meet the power needs of this remote park. The total estimated project cost
is $700,000, including preliminary plans ($75,000), working drawings ($40,000),
and construction ($585,000). Construction is scheduled to begin December 2016
and be completed June 2017.
Item 3790‑301‑0263—Department of Parks and Recreation—
Capital Outlay
1. Heber Dunes State Vehicular Recreation Area—Water System Upgrades. The budget
provides $1,086,000 for working drawings and construction to develop a new
water treatment and distribution system to meet current demand for potable
water, meet health department standards, provide secure storage to comply with
the California Department of Health Services—Drinking Water Field Operations
Branch water security guidelines, and protect the new water treatment system
from the harsh desert climate. The total estimated project cost is $1,170,000,
including preliminary plans ($84,000), working drawings ($96,000), and
construction ($990,000). Construction is scheduled to begin March 2017 and be
completed March 2018.
2. Prairie City State Vehicular Recreation Area—Initial Erosion Control. The budget
provides $275,000 for preliminary plans to address erosion issues caused by storm
water runoff, as required by the Federal Clean Water Act. The total estimated
project cost is $5,522,000, including preliminary plans ($275,000), working
drawings ($298,000), and construction ($4,949,000). Construction is scheduled to
begin October 2018 and be completed February 2020.
Item 3790‑301‑0392—Department of Parks and Recreation—
Capital Outlay
1. McArthur-Burney Falls Memorial State Park—Group Camp Development. The
budget provides reimbursement authorization of $62,000 for preliminary plans
and working drawings to develop two adjoining group camps expected to
increase the park’s group camping capacity by 100 campers. The total estimated
project cost is $928,000, including preliminary plans ($39,000), working drawings
($23,000), and construction ($866,000). Construction is scheduled to begin
October 2017 and be completed April 2018.
48 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Item 3790‑301‑6029—Department of Parks and Recreation—
Capital Outlay
1. McGrath State Beach—Campground Relocation and Wetlands Restoration. The
budget provides $1,029,000 for preliminary plans to relocate the existing
campground, maintenance yard, employee housing, campfire center, and day
use parking due to yearly flooding. The total estimated project cost is $27,790,000,
including preliminary plans ($1,029,000), working drawings ($1,302,000), and
construction ($25,459,000). Construction is scheduled to begin March 2017 and be
completed February 2019.
Item 3790‑301‑6051—Department of Parks and Recreation—
Capital Outlay
1. El Capitan State Beach—Construct New Lifeguard Operations Facility. The budget
provides $8,345,000 for construction and equipment to demolish the existing
lifeguard tower located in the El Capitan State Beach campground and construct
a new lifeguard operations facility adjacent to the existing El Capitan State Beach
maintenance facility. The total estimated project cost is $9,737,000, including
preliminary plans ($773,000), working drawings ($619,000), construction
($8,247,000), and equipment ($98,000). Construction is scheduled to begin
March 2017 and be completed February 2019.
2. El Capitan State Beach—Entrance Improvements. The budget provides $358,000
for preliminary plans to provide an alternate safe route for pedestrians and
bicyclists, provide increased space for today’s larger vehicles on the park road and
entrance area, replace a culvert with a bridge to allow the endangered steelhead
trout a barrier free passage, and replace the aging and damaged kiosk. The total
estimated project cost is $3,430,000, including preliminary plans ($358,000),
working drawings ($378,000), and construction ($2,694,000). Construction is
scheduled to begin March 2019 and be completed June 2020.
3. Gaviota State Park—Main Water Supply Upgrades. The budget provides $142,000
for working drawings to provide a consistent water supply for the public, staff,
and fire suppression; to ensure the health and safety of park occupants; and
avoid significant annual repair costs and intermittent water supply outages. The
total estimated project cost is $1,879,000, including preliminary plans ($215,000),
working drawings ($142,000), and construction ($1,522,000). Construction is
scheduled to begin September 2017 and be completed December 2018.
4. Malibu Creek State Park—New Stokes Creek Bridge. The budget provides $233,000
for working drawings to replace an existing, undersized arch culvert with a
LEGISLATIVE ANALYST’S OFFICE 49
Supplemental Report of the 2016-17 Budget Act
bridge. The total estimated project cost is $2,055,000, including preliminary
plans ($232,000), working drawings ($233,000), and construction ($1,590,000).
Construction is scheduled to begin September 2017 and be completed
December 2018.
5. Topanga State Park—Rebuild Trippet Ranch Parking Lot. The budget provides
$316,000 for preliminary plans to rehabilitate the Trippet Ranch parking lot and
surrounding area damaged by erosion and storm water. The total estimated
project cost is $3,798,000, including preliminary plans ($316,000), working
drawings ($219,000), and construction ($3,263,000). Construction is scheduled to
begin March 2019 and be completed June 2020.
Item 3790‑491‑0005—Department of Parks and Recreation—
Capital Outlay
1. San Elijo State Beach (SB)—Replace Main Lifeguard Tower. The budget provides
a reappropriation of $5,014,000 for construction and equipment to construct
a replacement lifeguard headquarters in a new location at San Elijo SB, and
remove the temporary tower currently in use. The total estimated project cost is
$5,756,000 including, preliminary plans ($223,000), working drawings ($519,000),
construction ($5,011,000), and equipment ($3,000). Preliminary plans have
been approved and working drawings are nearing completion. The current
project schedule estimates working drawings will be completed in July 2016.
Construction is estimated to begin October 2016 and to be completed June 2017.
Item 3790‑491‑0263—Department of Parks and Recreation—
Capital Outlay
1. Statewide—Southern California Opportunity Purchase Acquisition. The budget
provides a reappropriation of $2,460,000 for acquisition of identified parcels
throughout the off highway vehicle (OHV) districts located in Southern California
allowing for expansion of OHV recreational activities and protection of natural
and cultural resources found in the areas.
2. Carnegie State Vehicular Recreation Area—Road Reconstruction. The budget
provides a reappropriation of $7,813,000 to reconstruct and rehabilitate
approximately eight miles of unpaved roads to meet current emergency access
and Clean Water and public use standards. The total estimated project cost is
$8,280,000, including preliminary plans ($227,000), working drawings ($240,000),
and construction ($7,813,000). The project is pending permit approvals and the
current project schedule estimates construction to begin April 2017 and to be
completed December 2018.
50 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
3. Hungry Valley State Vehicular Recreation Area—Vehicle Wash Station. The budget
provides a reappropriation of $1,034,000 for construction to design, engineer, and
construct a vehicle wash station to replace the existing non‑functioning system
which does not meet current local runoff/discharge water standards. The total
estimated project cost is $1,064,000, including preliminary plans ($2,000), working
drawings ($28,000), and construction ($1,034,000). Preliminary plans have been
approved and working drawings are in progress. The current project schedule
estimates working drawings will be completed in August 2016. Construction is
estimated to begin in November 2016 and be completed in July 2017.
4. Carnegie State Vehicular Recreation Area—Vehicle Wash Station. The budget
provides a reappropriation of $1,338,000 for construction to design, engineer, and
construct a new wash station with a water recovery system to efficiently wash
vehicles and large equipment. The total estimated cost is $1,368,000, including
preliminary plans ($2,000), working drawings ($28,000), and construction
($1,338,000). Preliminary plans have been approved and working drawings are
in progress. The current project schedule estimates working drawings will be
completed in August 2016. Construction is estimated to begin in November 2016
and be completed in July 2017.
5. Oceano Dunes State Vehicular Recreation Area—Pismo State Beach Sediment
Track-Out Prevention. The budget provides a reappropriation of $95,000 for
working drawings to construct several dirt track‑out prevention measures at
park exits to help ensure dirt from vehicles does not track‑out onto public roads.
The total estimated cost is $707,000, including preliminary plans ($80,000),
working drawings ($95,000), and construction ($532,000). The current project
schedule estimates preliminary plans will be completed in January 2017. The
working drawings are estimated to begin in February 2017 and to be completed
in February 2018. Construction is estimated to begin in May 2018 and to be
completed in June 2019.
6. Hollister Hills State Vehicular Recreation Area—Waterline Expansion. The budget
provides a reappropriation of $1,367,000 for working drawings and construction
to install a new potable water pipeline from the holding tanks near the Gran
Prix track. The total estimated cost is $1,441,000, including preliminary plans
($74,000), working drawings ($62,000), and construction ($1,305,000). The current
project schedule estimates preliminary plans will be completed in May 2016. The
working drawings are estimated to begin in September 2016 and to be completed
in February 2017. Construction is estimated to begin in May 2017 and to be
completed in May 2018.
LEGISLATIVE ANALYST’S OFFICE 51
Supplemental Report of the 2016-17 Budget Act
Item 3790‑491‑0392—Department of Parks and Recreation—
Capital Outlay
1. Leo Carrillo State Park—Steelhead Trout Barrier Removal. The budget provides
a reappropriation of $286,000 in reimbursement authority for construction to
provide two free‑span bridges to replace two existing in‑stream crossings located
on Arroyo Sequit Creek to enhance habitat and increase spawning opportunity
for a federally listed endangered fish species. The total estimated project cost is
$3,069,000. Plans and specifications were gifted to the department by an outside
association and the project is currently in construction. The current project
schedule estimates construction will be completed in December 2016.
2. Mendocino Headlands State Park—Big River Watershed Restoration. The budget
provides a reappropriation of $1,645,000 in reimbursement authority for working
drawings and construction to remove two culvert crossings and surrounding
fill material on the Big River Haul Road located in the park. The culvert
crossings will be replaced by bridges able to accommodate vehicles, pedestrians,
and bicycles. The total estimated cost is $1,741,000, including preliminary
plans ($96,000), working drawings ($199,000), and construction ($1,446,000).
Preliminary plans have been approved and working drawings are in progress.
The current project schedule estimates working drawings will be completed in
August 2016. Construction is estimated to begin in June 2017 and to be completed
in November 2017.
Item 3790‑491‑6051—Department of Parks and Recreation—
Capital Outlay
1. Old Sacramento State Historic Park—Boiler Shop Renovation. The budget provides
a reappropriation of $726,000 for preliminary plans to make critical improvements
addressing hazardous material abatement, structural seismic stabilization,
improvements to the building exterior shell, interior core improvements, and
related utilities, as needed, to bring the historic Boiler Shop located in the
Downtown Sacramento Railyards to a level considered clean and safe. The total
estimated project cost is $11,664,000, including preliminary plans ($726,000),
working drawings ($423,000), and construction ($10,515,000). The current
project schedule estimates preliminary plans will begin in January 2017 and
be completed in January 2018. The working drawings are estimated to begin in
February 2018 and to be completed in February 2019. Construction is estimated to
begin in May 2019 and to be completed in May 2020.
52 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
2. Fort Ord Dunes State Park—New Campground and Beach Access. The budget
provides a reappropriation of $19,176,000 for construction to develop initial
permanent public facilities, including camping and day use beach access, at
the Fort Ord Dunes State Park in Monterey County. The total estimated project
cost is $22,375,000, including preliminary plans ($1,198,000), working drawings
($2,001,000), and construction ($19,176,000). Preliminary plans are approved
and working drawings are in progress. The current project schedule estimates
working drawings will be completed in September 2016. Construction is
estimated to begin in July 2017 and to be completed in November 2018.
3. Old Town San Diego State Historic Park—Building Demolition and Immediate
Public Use Facilities. The budget provides a reappropriation of $7,344,000 for
construction to abate, demolish, and remove the former California Department
of Transportation (Caltrans) office buildings and construct immediate public
use facilities at the southwest corner of Juan and Taylor Streets in Old Town
San Diego state historic park. The total estimated project cost is $8,079,000,
including preliminary plans ($436,000), working drawings ($299,000), and
construction ($7,344,000). Preliminary plans are approved and working drawings
are in progress. The current project schedule estimates working drawings will be
completed in January 2017. Construction is estimated to begin in June 2017 and to
be completed in April 2018.
4. El Capitan State Beach—Construct New Lifeguard Operations Facility. The budget
provides a reappropriation of $619,000 for working drawings to demolish the
existing lifeguard tower and construct a new lifeguard operations facility next
to the existing maintenance facility. The total estimated project cost is $9,737,000,
including preliminary plans ($773,000), working drawings ($619,000), and
construction ($8,247,000). The current project schedule estimates preliminary
plans will be completed in October 2016. The working drawings are estimated
to begin in November 2016 and to be completed in October 2017. Construction is
estimated to begin in January 2018 and to be completed in July 2018.
5. MacKerricher State Park—Replace Water Treatment System. The budget provides a
reappropriation of $2,474,000 for working drawings and construction to upgrade
the drinking water collection and treatment equipment to allow safe and reliable
year‑round production of potable water for the park. The total estimated project
cost is $3,055,000, including preliminary plans ($581,000), working drawings
($251,000), and construction ($2,223,000). The current project schedule estimates
preliminary plans will be completed in January 2017. The working drawings
are estimated to begin in February 2017 and to be completed in March 2018.
Construction is estimated to begin May 2018 and to be completed in June 2019.
LEGISLATIVE ANALYST’S OFFICE 53
Supplemental Report of the 2016-17 Budget Act
Item 3790‑491‑XXXX—Department of Parks and Recreation—
Capital Outlay
1. South Yuba River State Park—Historic Covered Bridge. The budget provides a
reappropriation of $1,125,000 for working drawings and construction to stabilize,
rehabilitate, and restore the historic covered bridge to prevent it from collapsing
into the South Yuba River, and so it can be reopened to the visiting public. The
total estimated project cost is $1,318,000 including preliminary plans ($193,000),
working drawings ($163,000), and construction ($962,000). The current project
schedule estimates preliminary plans will be completed in July 2017. The working
drawings are estimated to begin in August 2017 and to be completed in July 2018.
Construction is estimated to begin in September 2018 and to be completed in
September 2019.
Item 3790‑XXX‑0516—Department of Parks and Recreation—
Capital Outlay
1. McArthur-Burney Falls Memorial State Park—Ramp and Boarding Float
Replacement. The budget provides a reappropriation of $53,000 for working
drawings to reconstruct the launching ramp and boarding float located within
the park. The budget also provides $618,000 for construction to reconstruct
the dilapidated boat launching ramp and boarding float at this location. The
total estimated project cost is $716,000 including preliminary plans ($45,000),
working drawings ($53,000), and construction ($618,000). The current project
schedule estimates preliminary plans will be completed in August 2016. The
working drawings are estimated to begin in September 2016 and to be completed
in December 2016. Construction is estimated to begin in March 2017 and to be
completed in September 2017.
2. Angel Island State Park—East Garrison Mooring Field. The budget provides
a reappropriation of $38,000 for working drawings to restore the abandoned
mooring field at the East Garrison location of the park and to clean up the site
by removing debris from the bay floor, as needed. The budget also provides
$582,000 for construction to restore the abandoned mooring field consisting of
approximately 32 buoys at the East Garrison location of the park and remove
old concrete block anchors, chains, and debris from the bay floor as needed. The
total estimated project cost is $651,000 including preliminary plans ($31,000),
working drawings ($38,000), and construction ($582,000). The current project
schedule estimates preliminary plans will be completed in March 2017. The
working drawings are estimated to begin in April 2017 and to be completed in
March 2018. Construction is estimated to begin in June 2018 and to be completed
in December 2018.
54 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Item 3790‑XXX‑6051—Department of Parks and Recreation—
Capital Outlay
1. Torrey Pines State Natural Reserve—Sewer and Utility Modernization. The
budget provides a reappropriation of $127,000 for working drawings and a new
appropriation of $2,149,000 for construction to connect the park to the local
sewer system and to upgrade the aging water and utility infrastructure. The
total estimated project cost is $2,436,000, including preliminary plans ($160,000),
working drawings ($127,000), and construction ($2,149,000). The current project
schedule estimates preliminary plans will be completed in October 2016. The
working drawings are estimated to begin in November 2016 and to be completed
in October 2017. Construction is estimated to begin in December 2017 and to be
completed in December 2018.
Item 3860‑301‑6083—Department of Water Resources—Capital Outlay
1. Salton Sea Management Plan. The budget provides $60 million from Proposition 1
(water bond of 2014) to develop and begin implementing a new habitat
restoration and air quality mitigation plan at the Salton Sea. Funding would
support development and permitting of this plan; development, permitting, and
construction of individual restoration projects to meet short term goals of 9,000
to 12,000 acres of restoration; and assist in the ongoing construction management
for projects at the sea. Overall costs include $8 million for study, $6 million for
acquisition, $1 million for performance criteria, $9 million for preliminary plans,
$6 million for working drawings, and $30 million for construction.
2. San Joaquin River Settlement Project. The budget provides $15 million from
Proposition 1 (water bond of 2014) to design and implement flow conveyance
and fish passage improvements for the San Joaquin River Restoration Program.
These improvements—part of a larger restoration project being coordinated by
the U.S. Bureau of Reclamation—will help support the reintroduction of Chinook
salmon to the San Joaquin River. Overall costs include $100,000 for study, $100,000
for acquisition, $150,000 for performance criteria, $650,000 for preliminary plans,
$2 million for working drawings, and $12 million to contract for construction.
The department estimates that the feasibility investigation will be completed in
2016‑17, design will begin in 2016‑17, and construction will be begin in 2018‑19.
Item 4265-490—Department of Public Health—Capital Outlay
1. Richmond: Viral and Rickettsial Disease Laboratory Enhanced Upgrade—
Reappropriation of Construction. The budget provides a reappropriation of
$3,799,000 for construction to upgrade the California Department of Public
Health’s Richmond Laboratory, Viral and Rickettsial Disease Laboratory,
LEGISLATIVE ANALYST’S OFFICE 55
Supplemental Report of the 2016-17 Budget Act
to meet the Centers for Disease Control and Prevention Biosafety Level 3
Enhanced requirements. Total project costs are estimated at $4,815,000, including
preliminary plans ($241,000), working drawings ($775,000), and construction
($3,799,000).The construction amount includes $2,796,000 for the construction
contract, $196,000 for contingency, $351,000 for architectural and engineering
services, and $456,000 for other costs. The current project schedule estimated
preliminary plans would begin July 2007 and be completed in April 2008.The
working drawings were estimated to begin April 2008 and again in July 2015 and
be completed in July 2016. Construction is scheduled to begin October 2016 and to
be completed in September 2017.
Item 4300-301-0001—Department of Developmental Services—
Capital Outlay
1. Porterville Upgrade Fire Alarm System—Construction. The budget provides
$6,512,000 for construction to upgrade the fire alarm system at Porterville Developmental
Center. The project includes the design, purchase, and installation of a new code
compliant and integrated fire alarm system for the Secure Treatment Program
and the Administration building. Total project costs are estimated at $7,314,000,
including preliminary plans ($309,000), working drawings ($493,000), and
construction ($6,512,000). The construction amount includes $4,639,000 for the
construction contract, $325,000 for contingency, $820,000 for architectural and
engineering services, and $728,000 for other project costs. The current project
schedule estimated preliminary plans would begin December 2015 and be
completed in June 2016.The working drawings were estimated to begin June 2016
and be completed in March 2017. Construction is scheduled to begin August 2017
and to be completed in April 2019.
Item 4440-301-0001—Department of State Hospitals—Capital Outlay
1. Atascadero State Hospital—East West Corridor Seismic Upgrade—Construction.
The budget provides $5,288,000 for construction to seismically retrofit the East
West Corridor at Atascadero state hospital. Total project costs are estimated at
$6,055,000, including preliminary plans ($325,000), working drawings ($442,000),
and construction ($5,288,000). The construction amount includes $3,632,000 for
the construction contract, $254,000 for contingency, $578,000 for architectural and
engineering services, and $824,000 for other project costs. The current project
schedule estimated that preliminary plans would begin January 2014 and be
completed in June 2016. The working drawings were estimated to begin June 2016
and be completed in March 2017. Construction is scheduled to begin August 2017
and to be completed in August 2018.
56 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
2. Statewide Enhanced Treatment Units—Reappropriation of Working Drawings and
Construction. The budget provides a reappropriation of $12,336,000 for working
drawings and construction to renovate existing facilities at two state hospitals in
order to provide 49 Enhanced Treatment Units at Atascadero state hospital and
Patton state hospital. Total project costs are estimated at $13,570,000, including
preliminary plans ($1,234,000), working drawings ($869,000), and construction
($11,467,000). The construction amount includes $8,412,000 for the construction
contract, $589,000 for contingency, $1,138,000 for architectural and engineering
services, and $1,328,000 for other project costs. The current project schedule
estimated that preliminary plans would begin July 2014 and be completed in
October 2016. The working drawings were estimated to begin October 2016 and to
be completed in August 2017. Construction is estimated to begin November 2017
and to be completed in December 2018.
3. Metropolitan State Hospital—Increase Secure Bed Capacity—Construction and
Reappropriation of Working Drawings. The budget provides $31,182,000 for
construction to increase the secure bed capacity and add a security fence at
Metropolitan State Hospital. Total project costs are estimated at $34,818,000,
including preliminary plans ($1,930,000), working drawings ($1,706,000), and
construction ($31,182,000). The construction amount includes $25,533,000 for the
construction contract, $1,287,000 for contingency, $1,974,000 for architectural and
engineering services, and $2,388,000 for other project costs. The current project
schedule estimated that preliminary plans would begin May 2015 and to be
completed in June 2016. The working drawings were estimated to begin June 2016
and be completed in August 2016. Construction is estimated to begin November
2016 and to be completed in February 2018. In addition, the working drawings
were reappropriated to allow the expiration of the California Environmental
Quality Act (CEQA)‑required waiting period prior to preliminary plan approval;
CEQA is estimated to be filed on June 24, 2016.
4. Patton State Hospital—Fire Alarm System Upgrade—Working Drawings. The budget
provides $554,000 for working drawings to upgrade the fire alarm system at
Patton state hospital. Total project costs are estimated at $7,425,000, including
preliminary plans ($731,000), working drawings ($554,000), and construction
($6,140,000). The construction amount includes $3,554,000 for the construction
contract, $249,000 for contingency, $774,000 for architectural and engineering
services, and $1,563,000 for other project costs. The current project schedule
estimated that preliminary plans would begin July 2015 and be completed in
September 2016. The working drawings were estimated to begin September 2016
and be completed in July 2017. Construction is estimated to begin December 2017
and to be completed in February 2020.
LEGISLATIVE ANALYST’S OFFICE 57
Supplemental Report of the 2016-17 Budget Act
5. Coalinga State Hospital—Courtyard Expansion—Working Drawings. The budget
provides $603,000 for working drawings to expand the courtyard at Coalinga
State Hospital. Total project costs are estimated at $6,560,000, including
preliminary plans ($219,000), working drawings ($603,000), and construction
($5,738,000). The construction amount includes $4,515,000 for the construction
contract, $226,000 for contingency, $505,000 for architectural and engineering
services, and $492,000 for other project costs. The current project schedule
estimated that preliminary plans would begin July 2015 and be completed in
June 2016. The working drawings were estimated to begin June 2016 and be
completed in October 2017. Construction is estimated to begin March 2018 and to
be completed in March 2019.
Item 5225‑301‑0001—California Department of Corrections and
Rehabilitation—Capital Outlay
1. California Correctional Center, Susanville: Arnold Unit and Antelope Camp Kitchen/
Dining Facility Replacements—Construction. The budget provides $15,353,000
for construction to replace the kitchen/dining facility for the minimum security
Arnold Unit and a replacement kitchen/dining facility for the Antelope Camp. Total
project costs are estimated at $17,392,000, including preliminary plans ($1,042,000),
working drawings ($997,000), and construction ($15,353,000). The construction
amount includes $11,288,000 for the construction contract, $790,000 for contingency,
$1,030,000 for architectural and engineering services, $856,000 for agency retained
items, and $1,389,000 for other project costs. The preliminary plans began July 2014
and were completed in July 2015. The working drawings began July 2015 and are
estimated to be completed in September 2016. Construction is scheduled to begin
January 2017 and to be completed in March 2018.
2. Deuel Vocational Institution, Tracy: Solid Cell Fronts—Construction. The budget
provides $11,617,000 for construction to replace the existing barred cell fronts/
doors with solid cell front doors in the Administrative Segregation Unit at Deuel
Vocational Institution. Total project costs are estimated at $12,814,000, including
preliminary plans ($405,000), working drawings ($792,000), and construction
($11,617,000). The construction amount includes $8,626,000 for contracts, $604,000
for contingency, $949,000 for architectural and engineering services, $338,000 for
agency retained items, and $1,100,000 for other project costs. The preliminary
plans began September 2007 and were completed in December 2015. The working
drawings began April 2008 and are estimated to be completed in December 2016.
Construction is scheduled to begin March 2017 and to be completed in June 2018.
3. Deuel Vocational Institution, Tracy: New Boiler Facility—Construction. The budget
provides $4,041,000 for construction to replace the existing boiler facility at Deuel
Vocational Institution. Total project costs are estimated at $4,414,000, including
58 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
design ($373,000 previously funded with support funds) and construction
($4,041,000). The construction amount includes $3,301,000 for contracts, $231,000
for contingency, $248,000 for architectural and engineering services, and $261,000
for other project costs. The preliminary plans began August 2014 and are
estimated to be completed in July 2016. The working drawings are estimated to
begin July 2016 and be completed in August 2016. Construction is scheduled to
begin October 2016 and to be completed in September 2017.
Item 6100‑301‑0001—Department of Education—Capital Outlay
1. California School for the Deaf, Fremont—Middle School Activity Center. The budget
provides $1,749,000 to construct a 2,160 gsf middle school activity center at the
California School for the Deaf, Fremont. The project scope includes removing an
old modular building and constructing a new building on the same site. The new
building will contain a large game room, video‑viewing area, snack bar, bathrooms,
storage, refrigerator and freezers, data‑equipment cabinet, and a patio area with a
barbeque. The costs and schedule for the entire project are shown in the figure below.
California School for the Deaf, Fremont—
Middle School Activity Center
State Funds Start Date Finish Date
Preliminary plans $70,000 July 2016 October 2016
Working drawings 196,000 October 2016 April 2017
Construction 1,480,000a July 2017 March 2018
Equipment 3,000
Total $1,749,000
a
Includes $1,130,000 for the construction contract (CCCI 5969), $79,000 for contingency, $141,000 for
architectural and engineering fees, $3,000 for agency-retained items, and $130,000 for other project
costs. The construction cost is $685 per gross square foot.
Item 6440‑001‑0001—University of California—Capital Outlay
1. Merced Campus—State 2020 Project. Pursuant to Education Code 92495, the
University of California (UC) is authorized to use its General Fund support
appropriation for preliminary plans, working drawings, construction, and
equipment to add 414,409 assignable square feet (asf) (667,620 gsf) of facility space
to the Merced campus. The scope of the project includes new classrooms and
teaching laboratories (69,805 asf, 116,342 gsf), research laboratories (181,020 asf,
301,700 gsf), faculty and administrative offices (144,564 asf, 222,406 gsf), and
temporary space for environmental health and public safety (19,020 asf, 27,172 gsf).
UC will enter into a partnership with a private partner for major parts of the
project. The partner will design and construct the facilities. Once construction
is completed in 2020, UC and the partner will share the maintenance of the
LEGISLATIVE ANALYST’S OFFICE 59
Supplemental Report of the 2016-17 Budget Act
facilities. Specifically, the partner will be responsible for performing major
upgrades to infrastructure and building systems, whereas UC will perform more
routine maintenance work. Pursuant to Chapter 22 of 2015 (SB 81, Committee on
Budget and Fiscal Review), UC is required to use its own employees for routine
maintenance work.
Under the partnership agreement, UC will use $527 million General Fund for the
project. Of this amount, $400 million will come from UC‑issued bond funds and
$127 million will come from debt issued by the partner. UC will make annual
payments to the partner for the partner’s associated debt service and maintenance
costs. UC anticipates annual costs of $21 million for debt service on its bonds,
$7.3 million for its portion of maintenance, and $18 million in payments for the
partner’s portion of debt service ($13 million) and maintenance ($5.4 million). In
2055, the contract with the partner will end and UC will assume responsibility for
all operations and maintenance of the facilities. The costs and schedule for the state‑
funded aspects of the project are shown in the figure below. (In addition to the state‑
funded aspects of the project, UC plans to spend $616 million in nonstate funds for
nonstate‑supportable facilities, such as dormitories and parking structures.)
Merced Campus—State 2020 Project
State Funds Nonstate Funds Total Cost Start Date Finish Date
Preliminary plans $18,857,000 — $18,857,000 5/1/2016 8/1/2016
Workings drawings 43,999,000 — 43,999,000 5/1/2016 7/1/2019a
Construction 428,343,000 — 28,343,000b 8/1/2016 8/1/2020
Equipment 36,101,000 — 36,101,000c 5/1/2018 8/1/2020d
Totals $527,300,000 — $527,300,000
a
Schematic design for the third delivery facilities will not be completed until summer 2019.
b
CCCI 6392. The construction cost per square foot is $1,034 (assignable) and $642 (gross).
c
Includes fixed equipment that may need to be incorporated into construction.
d
First procurement of equipment will coincide with the opening of first delivery facilities (summer 2018).
Item 6600‑301‑0660—Hastings College of the Law—Capital Outlay
1. Hastings Campus—Snodgrass Hall Replacement. The 2015‑16 budget authorized
$36,846,000 in lease revenue bond funds for a replacement academic facility
at the Hastings College of the Law (Hastings). Of this amount, $1,958,000 was
designated for performance criteria and $34,888,000 for design build. The 2016‑17
budget provides an additional $18,750,000 in lease revenue bond funds for the
design build phase of the project. This brings total project funding to $55,596,000.
The existing facility, Snodgrass Hall, consists of 45,000 asf (76,000 gsf) of main
space, with additional space in an annex. The new facility is intended to replace
Snodgrass Hall’s main space. (Hastings’ five‑year capital outlay plan shows a
renovation of the annex beginning in 2017‑18.) The new facility will contain
48,395 asf (57,000 gsf) and be built on a vacant site located at 333 Golden Gate
60 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Avenue, a site owned by Hastings on its existing campus in San Francisco. The
costs and schedule for the entire project are shown in the figure below.
Snodgrass Hall Replacement Building
Non‑State
State Funds Fundsa Total Funds Start Date Finish Date
Performance Criteria $1,958,000 — $1,958,000 July 2015 October 2016
Design Build 53,638,000 — 53,638,000b May 2017 December 2019
Equipment — — —
Totals $55,596,000 — $55,596,000
a
The budget authorizes Hastings to supplement state funds appropriated for the project with legally available non-state institutional funds and
private gifts, grants, and donations. To date, $2.2 million in donations have been raised. The final amount of non-state funds Hastings will use
toward the project will depend on future fundraising efforts.
b
Includes $47,569,000 for the contract (CCCI 6284), $1,427,000 for project contingency, and $4,642,000 for other project costs. The contract cost
per square foot is $983 (assignable) and $835 (gross).
Item 6610‑001‑0001—California State University—Capital Outlay
1. 2016-17 Infrastructure Improvements. Pursuant to Education Code 89772,
the California State University (CSU) is authorized to use its General Fund
appropriation to fund preliminary plans, working drawings, and construction
for 73 projects totaling $138 million across the system’s 23 campuses. Campus
reserves will fund an additional $19 million of project costs. The 73 projects
include (a) heating, ventilation, and air conditioning (HVAC) replacements;
(b) upgrades to electrical systems; (c) repairs and upgrades to gas, sewage,
and water lines; (d) roof replacements; (e) seismic improvements to academic
buildings; and (f) demolition of specified buildings. The individual projects are
shown in the figure below (through page 66).
2016-17 Infrastructure Improvements
(Funding in Thousands)
Systemwide Campus
Campus Project Phase Revenue Bonds Reserves Total Cost
Bakersfield Replace transformers in electrical distribution C $1,500 — $1,500
at 18 buildings, including the central plant.
This project was initiated in 2015 and is being
implemented in three phases.
Bakersfield Repair corroding chilled water piping joints. P,W — $166 166
Bakersfield Various upgrades to natural gas lines, including P,W,C 300 — 300
relocation of existing utility meter, replacement
of high pressure line to the central plant with a
medium pressure line, and installment of isolation
and earthquake valves.
(Continued)
LEGISLATIVE ANALYST’S OFFICE 61
Supplemental Report of the 2016-17 Budget Act
Systemwide Campus
Campus Project Phase Revenue Bonds Reserves Total Cost
Channel Islands Phase 2 of project to remove travel barriers P,W,C 350 — 350
campuswide.
Channel Islands Replace existing, noncompliant fire alarm and P,W,C 327 — 327
electrical systems campuswide.
Channel Islands Replace HVAC systems in Aliso Hall (#32) and P,W,C 489 11 500
Arroyo Hall (#7), and connect the two buildings to
existing heating hot water loop.
Channel Islands Replace existing underground sanitary sewer from P,W,C 389 11 400
Lindero Hall (#26) to Santa Cruz Village (#13).
Chico Replace existing fire alarm control panels and fire P,W,C 992 110 1,102
alarm devices and upgrade egress protection at
Acker and Shurmer Gymnasiums.
Chico Repair leaks and install drainage and sump system P,W,C 4,626 513 5,139
for basement at Meriam Library.
Dominguez Hills Install arc flash and shock hazard measures on P,W,C 262 18 280
noncompliant electrical equipment throughout the
campus’s electrical distribution system.
Dominguez Hills Upgrade electrical service equipment at the P,W,C 2,048 120 2,168
Central Plant (#87), including a new transformer,
switchboard, and associated duct banks and
feeders. These upgrades will support the
replacement of an existing gas absorption chiller
with an electrical chiller.
Dominguez Hills Replace 250 feet of aging piping and 25 fire hydrant P,W,C 281 19 300
shut-off valves.
Dominguez Hills Install four gas leak detection devices throughout P,W,C 403 21 424
the utility tunnel and connect the devices to
campus’s building management system.
East Bay Third phase of project to replace space heating C — 500 500
and domestic water heating boilers with new
energy efficient condensing boilers at Music (#3),
Robinson Hall (#10), Science (#1), Health Center
(#18), and Physical Education (#7).
East Bay Replace water pressure regulators. P,W,C $815 — $815
East Bay Install fire suppression system in telecommunica- P,W,C 105 $45 150
tion main point of entry located at the lower mall
east side of the Library (#12).
East Bay Replace chillers and air handling units at Music P,W,C 2,850 440 3,290
(#3), Robinson Hall (#10), Theatre (#11), Student
Health Center (#18), Meiklejohn Hall (#9), and
the Contra Costa off-campus center.
Fresno Replace existing fire alarm systems in older P,W,C 5,133 279 5,412
buildings with code compliant systems.
(Continued)
62 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Systemwide Campus
Campus Project Phase Revenue Bonds Reserves Total Cost
Fullerton Construct detention basins and infiltration basins at P,W — 100 100
three sites on campus.
Fullerton Remove last segment of overhead electrical lines P,W,C 495 55 550
and replace lines with approximately 1,000 linear
feet of underground lines.
Fullerton First of two phases of project to convert Corporation P,W,C 3,000 1,000 4,000
Yard (#1) from 16 temporary buildings to
consolidated permanent structures as part of
Physical Services Complex (#34).
Humboldt Replace existing emergency generator in Natural P,W,C 3,045 — 3,045
Resources Building (#40) with diesel-fueled
generator with a belly tank.
Humboldt Replace boilers and pumps, connect distribution P,W,C 300 — 300
systems, and consolidate equipment into one
boiler plant to service Van Matre Hall (#26),
Library (#41), and Student Health Center (#42).
Long Beach First of two phases of project to replace air han- P,W,C 6,008 550 6,558
dlers on four floors in Microbiology (#41).
Los Angeles Second phase of project to provide seismic C 10,000 10,000 20,000
upgrades to Physical Sciences (#12).
Los Angeles Install new 1,200-ton electric chiller with new P,W,C 2,506 211 2,717
primary pump, condenser water pump, and
cooling tower at Chiller Plant (#4). A future
project will install another 1,200-ton chiller.
Maritime Repair 400 feet of Faculty Drive road from campus P,W,C 1,400 — 1,400
Academy entry to residential and administrative facilities.
Maritime Install steam boiler for Golden Bear ship and P,W,C 432 48 480
Academy expand existing structure to house the new boiler.
Maritime Replace approximately 2,200 linear feet of domes- P,W,C 594 66 660
Academy tic water piping.
Monterey Bay Third phase of three-phase project to abate P,W,C 9,580 — 9,580
hazardous materials and demolish structures
remaining from the former Fort Ord military base.
Monterey Bay Replace electrical substations, transformers, P,W,C 1,800 — 1,800
cables, fire alarm panels in older buildings, and
isolation valves.
Northridge Third phase of three-phase project to replace C 2,100 — 2,100
leaking heating hot water lines with new insulated
lines.
Northridge Four phases of project initiated in 2015 to replace W,C $5,505 — $5,505
electrical distribution boards at the end of their
useful lives. (Affected buildings not specified.)
Northridge Replace existing electrical substations and P,W,C 1,698 $60 1,758
transformers.
(Continued)
LEGISLATIVE ANALYST’S OFFICE 63
Supplemental Report of the 2016-17 Budget Act
Systemwide Campus
Campus Project Phase Revenue Bonds Reserves Total Cost
Northridge Replace transite and asbestos concrete water P,W — 238 238
piping campuswide. Replace existing isolation
valves and add new valves.
Pomona Second phase of project to replace campuswide C 2,354 — 2,354
de-ionized water piping and roof and deck drain
piping.
Pomona Repair some natural gas distribution lines, replace P,W,C 2,394 — 2,394
others, and conduct hydrostatic testing.
Pomona Replace HVAC system and fume hood in Building P,W,C 5,175 575 5,750
8.
Pomona Repair sewer pipes, including manholes, storm P,W,C 1,800 200 2,000
drains, and extensions that connect various
campus buildings to the sewer piping.
Sacramento Second of three-phase project to replace P,W,C 1,052 — 1,052
noncompliant fire alarm system and provide
ability to report to a central monitoring station.
Sacramento First phase of electricity upgrade project that would P,W,C 1,750 — 1,750
replace substations and air switches in older
buildings.
Sacramento First phase of project to remove travel barriers P,W,C 795 — 795
campuswide.
Sacramento Re-line existing sewer pipes in three sections of P,W,C 1,000 — 1,000
campus system and replace undersized storm
drainage lines near the University Union.
Sacramento Third of three-phase project to replace P,W,C 1,170 130 1,300
noncompliant fire alarm system and provide
ability to report to a central monitoring station
through the existing campus network.
San Bernardino Replace roof of Chaparral Hall (#3). P,W,C 445 72 517
San Bernardino Replace roof of Performing Arts (#20). P,W,C 854 107 961
San Bernardino Replace roof of Sierra Hall (#2). P,W,C 388 70 458
San Bernardino Replace roof of Visual Arts (#32). P,W,C 1,361 133 1,494
San Diego Replace roof of Peterson Gym (#16). P,W,C 700 — 700
San Diego Upgrade HVAC, heat exchanger, circulation pumps, P,W,C 2,893 207 3,100
and controls in Professional Studies and Fine
Arts (PSFA) (#27).
San Diego Upgrade single elevator, including controls and P,W,C 459 41 500
communication devices, in PSFA (#27).
San Diego Upgrade fire alarm system in PSFA (#27). P,W,C 271 29 300
Improvements will include code compliant pull
stations, signage, and fire suppression system.
(Continued)
64 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Systemwide Campus
Campus Project Phase Revenue Bonds Reserves Total Cost
San Diego Upgrade electrical service switchboard, switches, P,W,C 2,328 172 2,500
transformer, lighting, and emergency generator in
PSFA (#27).
San Francisco Various upgrades to Central Plant (#26)and P,W,C $1,094 $91 $1,185
campus infrastructure, including installing new
plate and frame heat exchanger in Central
Plant to hydraulically separate the primary
and secondary loops, upgrading gas piping
infrastructure, installing redundant valves for
firewater loop and post indicator valves at various
buildings, replacing existing PVC piping with
galvanized steel piping, and replacing building
and loop valves.
San Francisco Replace existing emergency generator at the P,W,C 264 27 291
Student Health Center (#27).
San Francisco Install new 60-ton air-cooled condenser to serve P,W,C 231 26 257
the Data Center.
San Francisco Replace water lines running around or under trees, P,W,C 1,105 105 1,210
install automatic high-flow sensors and valves
on each building main service entrance, replace
existing PVC piping with galvanized steel piping,
and replace building and loop valves.
San Francisco Provide sewer and storm drain upgrades P,W,C 262 27 289
campuswide by regrading and installing storm
drain inlets and installing a sump pump in the
vault near Humanities and Social Sciences (#3)
San Francisco Upgrade noncompliant fire alarm system at P,W,C 1,106 97 1,203
Thornton Hall (#51) with new alarm panels,
including speakers, horns, strobes, and voice
annunciation.
San Francisco Upgrade noncompliant restrooms in academic P,W,C 1,498 116 1,614
buildings and Administration (#30).
San Jose Second phase of project to upgrade underground P,W,C 5,502 611 6,113
utility infrastructure by creating loop system that
extends water line. The project also consolidates
gas services at the southeast quadrant, rein-
forces telecom pathways, and replaces existing
water well.
San Luis Obispo Third of three-phase project to replace direct varied C 2,407 — 2,407
heating hot water piping with new welded steel
piping. Also replace existing hot and chilled water
isolation valves and boxes.
San Luis Obispo Replace upper substation switchgear and P,W,C 3,942 257 4,199
transformer at Mustang Substation (#75).
San Marcos Replace noncompliant HVAC system at Craven Hall P,W,C 3,064 248 3,312
(#1).
(Continued)
LEGISLATIVE ANALYST’S OFFICE 65
Supplemental Report of the 2016-17 Budget Act
Systemwide Campus
Campus Project Phase Revenue Bonds Reserves Total Cost
San Marcos Install diesel emergency generator and associated P,W,C 1,463 115 1,578
gear to support Utilities Plant (#43).
Sonoma Replace existing Central Plant (#12) wooden P,W,C 869 — 869
cooling tower with metal cooling tower.
Sonoma Replace chiller in Central Plant (#12) with new P,W,C 1,071 81 1,152
1,200-ton electric centrifugal chiller.
Sonoma Replace evaporative cooling units in Darwin Hall P,W,C $1,976 $71 $2,047
(#2) and Salazar Hall (#6) with HVAC units
supplied with hot and cold water from the Central
Plant (#12),
Stanislaus Replace existing boilers and expansion tanks P,W,C 2,600 — 2,600
in Central Plant (#3) along with the addition
of an air separator to the distribution system,
refrigerant monitoring system and exhaust fan,
and separating wall between the boilers and
chillers.
Stanislaus Correct ADA deficiencies campuswide, including P,W,C 451 49 500
noncompliant building entrance ramps, exterior
and interior entryways, and restroom facilities.
Stanislaus Replace five air handling units and associated P,W,C 828 77 905
equipment in Drama (#7).
Stanislaus Replace portion of campus hot water pipes, valves, P,W,C 1,923 214 2,137
and joints.
Systemwide Various projects systemwide to install, upgrade, or P,W,C 10,000 214 10,214
replace building controls and energy manage-
ment systems.
Totals $138,178 $18,743 $156,921
ADA = American Disabilities Act and HVAC = heating, ventilation, and air conditioning.
66 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
2. Bakersfield Campus—Humanities Classroom. Pursuant to Education Code 89772,
CSU is authorized to use its General Fund appropriation for preliminary plans
($109,000) and construction ($4.3 million) to add two new 120‑seat classrooms
to the Humanities Office Building (#57A) complex. The project will add
5,600 asf/9,000 gsf space to the existing facility and accommodate 652 additional
full‑time equivalent (FTE) students. Campus reserves will fund workings
drawings and equipment totaling $215,000. The costs and schedule for the entire
project are shown in the figure below.
Bakersfield Campus—Humanities Classroom
Systemwide Campus
Revenue Bonds Reserves Total Cost Start Date Finish Date
Preliminary plans $109,000 — $109,000 January 2017 May 2017
Working drawings — $143,000 143,000 June 2017 July 2017
Construction 4,277,000 — 4,277,000a October 2017 November 2018
Equipment — 72,000 72,000
Totals $4,386,000 $215,000 $4,601,000
a
Includes $3.8 million for construction contracts (CCCI 6255), $145,000 for contingency, $256,000 for project administration, and $56,000 for
architecture and engineering. The construction cost per square foot is $764 (assignable) and $475 (gross).
3. Channel Islands Campus—Gateway Hall. Pursuant to Education Code 89772,
CSU is authorized to use its General Fund appropriation for preliminary plans
($2 million) for a project to renovate and expand Gateway Hall (#9). The scope
of the project will include renovating 18,090 asf (45,225 gsf) of existing space and
constructing 34,150 asf (56,917 gsf) of new space. The project will accommodate
an additional 1,485 FTE students and 80 faculty offices. CSU anticipates working
drawings, construction, and equipment costs to total $68 million. The costs and
schedule for the entire project are shown in the figure below.
Channel Islands Campus—Gateway Hall
Systemwide
Revenue Bonds Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,983,000 — $1,983,000 February 2017 October 2017
Working drawings — $2,038,000 2,038,000 November 2017 June 2018
Construction — 63,581,000 3,581,000a October 2018 October 2020
Equipment — 2,063,000 2,063,000
Totals $1,983,000 $67,682,000 $69,665,000
a
Includes $55.3 million for construction contracts (CCCI 6255), $4.8 million for project administration, $2.4 million for contingency, and $986,000 for
architecture and engineering. The construction cost per square foot is $1,217 (assignable) and $622 (gross).
LEGISLATIVE ANALYST’S OFFICE 67
Supplemental Report of the 2016-17 Budget Act
4. Chico Campus—Siskiyou II Science Replacement Building. Pursuant to Education
Code 89772, CSU is authorized to use its General Fund appropriation to fund
preliminary plans ($2.6 million) and construction ($71 million) of a 57,700 asf
(96,300 gsf) replacement physical sciences building (#103). The scope of the new
facility includes classrooms, wet lab space, faculty office space, a data center, and a
vivarium. Campus reserves will fund working drawings and equipment totaling
$6.9 million. The costs and schedule for the entire project are shown in the figure
below.
Chico Campus—Siskiyou II Science Replacement Building
Systemwide Campus
Revenue Bonds Reserves Total Funds Start Date Finish Date
Preliminary plans $2,606,000 — $2,606,000 October 2016 May 2017
Working drawings — $2,414,000 2,414,000 June 2017 December 2017
Construction 71,045,000 — 71,045,000 June 2018 February 2018
Equipment — 4,521,000 4,521,000a
Totals $73,651,000 $6,935,000 $80,586,000
a
Includes $61.3 million for construction contracts (CCCI 6255), $6.3 million for project administration, $2.5 million for contingency, and $877,000 for
architecture and engineering. The construction cost per square foot is $1,227 (assignable) and $738 (gross).
5. Dominguez Hills Campus—Center for Science and Innovation. Pursuant to
Education Code 89772, CSU is authorized to use its General Fund appropriation to
fund working drawings ($1.5 million), construction ($61 million), and equipment
($3.2 million) for a 52,300 asf (86,800 gsf) replacement science laboratory and
classroom building (#51). The scope of the project includes construction of
teaching laboratories (23,625 asf), graduate research space (6,773 asf), laboratory
support (7,881 asf), faculty offices (4,630 asf), and administrative support
(9,391 asf). Campus reserves will fund preliminary plans and a portion of the
working drawings phase totaling $2.2 million. The costs and schedule for the
entire project are shown in the figure below.
Dominguez Hills Campus—Center for Science and Innovation
Systemwide Campus
Revenue Bonds Reserves Total Cost Start Date Finish Date
Preliminary plans — — — February 2017 August 2017
Working drawings $1,526,000 $500,000 $2,026,000 September 2017 March 2018
Construction 60,547,000 — 60,547,000a September 2018 March 2020
Equipment 3,248,000 — 3,248,000
Totals $65,321,000 $500,000 $65,821,000
a
Includes $52.9 million for construction contracts (CCCI 6255), $3.3 million for architecture and engineering, $2.1 million for contingency, and
$2.1 million for project administration. The construction cost per square foot is $1,158 (assignable) and $698 (gross).
68 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
6. East Bay Campus—Library Seismic Renovation. Pursuant to Education Code
89772, CSU is authorized to use its General Fund appropriation for preliminary
plans ($1.5 million) and construction ($49 million) to renovate the 166,800 asf
(237,700 gsf) library building (#12). The scope of the project includes correcting
seismic deficiencies, upgrading fire and life safety systems, and replacing
building systems. Campus reserves will fund working drawings and equipment
totaling $4.6 million. The costs and schedule for the entire project are shown in
the figure below.
East Bay Campus—Library Seismic Renovation
Systemwide Campus
Revenue Bonds Reserves Total Cost Start Date Finish Date
Preliminary plans $1,541,000 — $1,541,000 February 2017 October 2017
Working drawings — $1,571,000 1,571,000 November 2017 April 2018
Construction 48,714,000 — 48,714,000 July 2018 June 2020
Equipment — 3,000,000 3,000,000
Totals $50,255,000 $4,571,000 $54,826,000
a
Includes $41.9 million for construction contracts (CCCI 6255), $2.9 million for contingency, $2.9 million for project administration, and $1.1 million
for architecture and engineering. The construction cost per square foot is $291 (assignable) and $204 (gross).
7. Fresno Campus—Central Plant Replacement, Phase 1. Pursuant to Education
Code 89772, CSU is authorized to use its General Fund appropriation to fund
preliminary plans ($1.4 million) and construction ($22 million) to replace existing
chillers, boilers, cooling towers, and HVAC systems at the Central Plant and other
facilities throughout the campus. Campus reserves will fund working drawings
and equipment totaling $6.5 million. The costs and schedule for the entire project
are shown in the figure below.
Fresno Campus—Central Plant Replacement, Phase 1
Systemwide Campus
Revenue Bonds Reserves Total Cost Start Date Finish Date
Preliminary plans $1,428,000 — $1,428,000 October 2016 July 2017
Working drawings — $5,601,000 5,601,000 August 2017 April 2018
Construction 21,659,000 — 21,659,000a October 2018 March 2021
Equipment — 851,000 851,000
Totals $23,087,000 $6,452,000 $29,539,000
a
Includes $15.6 million for construction contracts (CCCI 6255), $3 million for project administration, $2.3 million for contingency, and $695,000 for
architecture and engineering.
LEGISLATIVE ANALYST’S OFFICE 69
Supplemental Report of the 2016-17 Budget Act
8. Fullerton Campus—McCarthy Hall Science Renovation, Phase 1. Pursuant to
Education Code 89772, CSU is authorized to use its General Fund appropriation
to fund construction ($12.7 million) for fire and life safety corrections, code
upgrades, and electrical upgrades to McCarthy Hall (#2). Campus reserves will
fund preliminary plans and working drawings totaling $2 million. The costs and
schedule for the entire project are shown in the figure below.
Fullerton Campus—McCarthy Hall Science Renovation, Phase 1
Systemwide Campus
Revenue Bonds Reserves Total Cost Start Date Finish Date
Preliminary plans — $1,646,000 $1,646,000 February 2017 April 2017
Working drawings — 393,000 393,000a May 2017 November
2017
Construction $12,726,000 — 12,726,000 May 2018 November
2019
Equipment — — —
Totals $12,726,000 $2,039,000 $14,765,000
a
Includes $10.9 million for construction contracts (CCCI 6255), $737,000 for architecture and engineering, $654,000 for contingency, and $433,000
for project administration. The construction cost per square foot is $510 (assignable) and $257 (gross).
9. Fullerton Campus—Pollak Library Renovation, Phase 1. Campus reserves will
fund preliminary plans, working drawings, construction, and equipment totaling
$13 million to renovate the entire first floor (48,000 asf, 68,500 gsf) and the fourth
and fifth floors (96,000 asf, 137,000 gsf) of the south wing of Pollak Library (#5).
This is the first of four phases. The costs and schedule for the first phase are
shown in the figure below.
Fullerton Campus—Pollak Library Renovation, Phase 1
Campus Reserves Total Cost Start Date Finish Date
Preliminary plans $320,000 $320,000 February 2017 March 2017
Working drawings 385,000 385,000 March 2017 March 2017
Construction 11,295,000 11,295,000 August 2017 February 2019
Equipment 748,000 748,000
Totals $12,748,000 $12,748,000
a
Includes $8.8 million for construction contracts (CCCI 6255), $1.4 million for contingency, $709,000 for architecture and engineering, and
$355,000 for project administration.
70 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
10. Humboldt Campus—Jenkins Science Hall Renovation. Pursuant to Education
Code 89772, CSU is authorized to use its General Fund appropriation to fund
preliminary plans ($333,000) and construction ($11.1 million) to renovate and
repurpose Jenkins Science Hall (#7). The scope of the project includes upgrading
the building’s systems and correcting code deficiencies. Campus reserves will
fund working drawings and equipment totaling $580,000. The costs and schedule
for the entire project are shown in the figure below.
Humboldt Campus—Jenkins Science Hall Renovation
Systemwide Campus
Revenue Bonds Reserves Total Cost Start Date Finish Date
Preliminary plans $333,000 — $333,000 February 2017 August 2017
Working drawings — $368,000 368,000 September March 2018
2017
Construction 11,056,000 — 11,056,000a September March 2020
2018
Equipment — 212,000 212,000
Totals $11,389,000 $580,000 $11,969,000
a
Includes $9.3 million for construction contracts (CCCI 6255), $711,000 for architecture and engineering, $640,000 for contingency, and $437,000
for project administration. The construction cost per square foot is $961 (assignable) and $636 (gross).
11. Long Beach Campus—Student Success Building/Peterson Hall 2. Pursuant to
Education Code 89772, CSU is authorized to use its General Fund appropriation
for construction ($38 million) to renovate Peterson Hall 2 (#38). The scope of
the project includes addressing seismic deficiencies and repurposing space to
accommodate academic advising, disabled student services, and instruction.
Campus reserves will fund preliminary plans, working drawings, and equipment
totaling $5.2 million. The costs and schedule for the entire project are shown in
the figure below.
Long Beach Campus—Student Success Building/Peterson Hall 2
Systemwide Campus
Revenue Bonds Reserves Total Cost Start Date Finish Date
Preliminary plans — $1,084,000 $1,084,000 January 2017 June 2017
Working drawings — 1,355,000 1,355,000 July 2017 October 2017
Construction $38,156,000 — 38,156,000a June 2019 December
2020
Equipment — 2,762,000 2,762,000
Totals $38,156,000 $5,201,000 $43,357,000
a
Includes $32.7 million for construction contracts (CCCI 6255), $2.7 million for architecture and engineering, $1.4 million for project administration,
and $1.3 million for contingency. The construction cost per square foot is $763 (assignable) and $477 (gross).
LEGISLATIVE ANALYST’S OFFICE 71
Supplemental Report of the 2016-17 Budget Act
12. Los Angeles Campus—John F. Kennedy Library Seismic Renovation. Pursuant to
Education Code 89772, CSU is authorized to use its General Fund appropriation
for preliminary plans ($1.9 million) to correct seismic deficiencies at the
240,800 asf (401,300 gsf) John F. Kennedy Memorial Library (#7). CSU anticipates
working drawings, construction, and equipment costs to total $61 million. The
costs and schedule for the entire project are shown in the figure below.
Los Angeles Campus—John F. Kennedy Library Seismic Renovation
Systemwide
Revenue Bonds Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,900,000 — $1,900,000 October 2016 April 2017
Working drawings — $1,900,000 1,900,000 May 2017 November 2017
Construction — 53,931,000 53,931,000a May 2018 November 2019
Equipment — 5,021,000 5,021,000
Totals $1,900,000 60,852,000 $62,752,000
a
Includes $46.2 million for construction contracts (CCCI 6255), $3.7 million for architecture and engineering, $2.8 million for contingency, and $1.1
million for project administration. The construction cost per square foot is $185 (assignable) and $155 (gross).
13 Maritime Academy—Learning Commons. Pursuant to Education Code 89772,
CSU is authorized to use its General Fund appropriation for preliminary plans
($708,000) and working drawings ($750,000) to construct a new 35,000 asf
(50,000 gsf) building (#57) that will connect to the existing library facility (#5).
The project is intended to accommodate overall campus enrollment of 2,500 FTE
students. CSU expects construction and equipment costs to total $25 million. The
costs and schedule for the entire project are shown in the figure below.
Maritime Academy Campus—Learning Commons
Systemwide
Revenue Bonds Future Costs Total Cost Start Date Finish Date
Preliminary plans $708,000 — $708,000 October 2016 April 2017
Working drawings 750,000 — 750,000 May 2017 November 2017
Construction — $23,757,000 23,757,000 May 2018 November 2019
Equipment — 1,208,000 1,208,000
Totals $1,458,000 $24,965,000 $26,423,000
a
Includes $20.8 million for construction contracts (CCCI 6255), $1.4 million for architecture and engineering, $831,000 for contingency, and
$754,000 for project administration. The construction cost per square foot is $679 (assignable) and $475 (gross).
72 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
14. Monterey Bay Campus—Academic Building III. Pursuant to Education Code
89772, CSU is authorized to use its General Fund appropriation to fund working
drawings ($718,000) and construction ($34 million) of a new 31,800 asf (50,800 gsf)
academic building (#505) to accommodate 1,500 FTE students in the College of
Arts, Humanities, and Social and Behavioral Sciences. Campus reserves will
fund another $500,000 of the working drawings phase. CSU’s 2015‑16 bond funds
provided funding of $1.5 million for the project’s preliminary plans. The costs and
schedule for the entire project are shown in the figure below.
Monterey Bay Campus—Academic Building III
Systemwide Campus
Revenue Bonds Reserves Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,476,000 — — $1,476,000a September 2015 July 2016
Working drawings 718,000 $500,000 — 1,218,000 August 2016 March 2017
Construction 33,646,000 — — 33,646,000b September 2017 May 2019
Equipment — — $1,307,000 1,307,000
Totals $35,840,000 $500,000 $1,307,000 $37,647,000
a
Funding provided with 2015-16 systemwide revenue bonds.
b
Includes $29.1 million for construction contracts (CCCI 6255), $2.6 for project administration, $1.2 million for contingency, and $779,000 for architecture and engineering. The
construction cost per square foot is $1,057 (assignable) and $663 (gross).
15. Northridge Campus—Sierra Hall Renovation, Phase 1. Pursuant to Education
Code 89772, CSU is authorized to use its General Fund appropriation for
preliminary plans ($1.9 million) to renovate Sierra Hall (#6). The project will be
completed in two phases. Phase 1 will reconfigure and modernize lecture space
and teaching labs, as well as correct deficiencies in code compliance and fire and
life safety. Campus reserves will fund working drawings ($1.9 million). CSU
anticipates construction and equipment costs to total $54 million. The costs and
schedule for Phase 1 are shown in the figure below.
Northridge Campus—Sierra Hall Renovation, Phase 1
Systemwide Campus
Revenue Bonds Reserves Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,867,000 — — $1,867,000 October 2016 July 2017
Working drawings — $1,862,000 — 1,862,000 August 2017 March 2018
Construction — — $52,832,000 52,832,000a September 2018 August 2020
Equipment — — 1,280,000 1,280,000
Totals $1,867,000 $1,862,000 $54,112,000 $57,841,000
a Includes $46.2 million for construction contracts (CCCI 6255), $3.1 million for project administration, $2.7 million for contingency, and
$773,000 for architecture and engineering. The construction cost per square foot is $1,074 (assignable) and $678 (gross).
LEGISLATIVE ANALYST’S OFFICE 73
Supplemental Report of the 2016-17 Budget Act
16. Sacramento Campus—Utilities Infrastructure, Phase 1. Pursuant to Education
Code 89772, CSU is authorized to use its General Fund appropriation for
preliminary plans ($2 million) and working drawings ($1.7 million) for the first
phase of a project to upgrade the campus’s utility infrastructure. The scope of
the first phase includes extending the storm water collection system, irrigation
pumps, natural gas distribution system, chilled water system, and water
distribution system. CSU anticipates construction costs to total $34 million. The
costs and schedule for the entire project are shown in the figure below.
Sacramento Campus—Utilities Infrastructure, Phase 1
Systemwide
Revenue Bonds Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,996,000 — $1,996,000 February 2017 August 2017
Working drawings 1,728,000 — 1,728,000 September 2017 March 2018
Construction — $33,511,000 33,511,000a September 2018 March 2020
Equipment — — —
Totals $3,724,000 $33,511,000 $37,235,000
a Includes $29.2 million for construction contracts (CCCI 6255), $2.6 million for architecture and engineering,
$1.3 million for contingency, and $469,000 for project administration.
17. San Diego Campus—Utilities Upgrade, Phase 1. Pursuant to Education Code 89772,
CSU is authorized to use its General Fund appropriation for preliminary plans
($1.7 million) to correct campuswide utility infrastructure deficiencies, including
upgrading electrical systems, chiller plant systems, steam lines, and steam boilers.
CSU anticipates working drawings and construction costs to total $29 million. The
costs and schedule for the entire project are shown in the figure below.
San Diego Campus—Utilities Upgrade, Phase 1
Campus Reserves Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,730,000 — $1,730,000 October 2015 May 2017
Working drawings — $1,793,000 1,793,000 June 2017 January 2018
Construction — 27,127,000 27,127,000a September March 2020
2018
Equipment — — —
Totals $1,730,000 $28,920,000 $30,650,000
a
Includes $20.7 million for construction contracts (CCCI 6255), $4.1 million for contingency, $1.6 million for architecture and engineering, and
$598,000 for project administration.
74 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
18. San Diego Campus, Calexico Off-Campus Center—North Classroom Seismic
Renovations. Pursuant to Education Code 89772, CSU is authorized to use its
General Fund appropriation to fund preliminary plans ($58,000), workings
drawings ($83,000), and construction ($1.9 million) to renovate the North
Classroom Building (#1). The scope of the project includes correcting code
deficiencies. The costs and schedule for the entire project are shown in the figure
below.
San Diego Campus, Calexico Off‑Campus Center—
North Classroom Seismic Renovation
Systemwide
Revenue Bonds Total Cost Start Date Finish Date
Preliminary plans $58,000 $58,000 October 2016 May 2017
Working drawings 83,000 83,000 June 2017 January 2018
Construction 1,881,000 1,881,000a April 2018 April 2019
Equipment — —
Totals $2,022,000 $2,022,000
a
Includes $1.6 million for construction contracts (CCCI 6255), $100,000 for architecture and engineering, $100,000 for project administration, and
$89,000 for contingency.
19. San Jose Campus—Science Replacement Building. Pursuant to Education
Code 89772, CSU is authorized to use its General Fund appropriation to fund
preliminary plans ($2.8 million) for a project to construct a replacement building
(#112) for the Biology and Chemistry Departments in the College of Science. The
64,000 asf (107,600 gsf) replacement facility will include wet laboratories, faculty
offices, and graduate research space. CSU anticipates future projects to renovate
Duncan Hall (#52) and the old Science Building (#48), which currently house the
two departments. CSU anticipates costs for working drawings and construction
to total $81 million. The costs and schedule for the entire project are shown in the
figure below.
San Jose Campus—Science Replacement Building
Systemwide
Revenue Bonds Future Costs Total Cost Start Date Finish Date
Preliminary plans $2,755,000 — $2,755,000 October June 2017
2016
Working drawings — $2,676,000 2,676,000 July 2017 January
2018
Construction — 78,783,000 78,783,000a July 2018 June 2020
Equipment — — —
Totals $2,755,000 $81,459,000 $84,214,000
a
Includes $69.4 million for construction contracts (CCCI 6255), $4.3 million for architecture and engineering, $3.4 million for project administration,
and $1.7 million for contingency. The construction cost per square foot is $1,239 (assignable) and $732 (gross).
LEGISLATIVE ANALYST’S OFFICE 75
Supplemental Report of the 2016-17 Budget Act
20. Sonoma Campus—Professional Schools Building. Pursuant to Education Code
89772, CSU is authorized to use its General Fund appropriation for preliminary
plans ($1.1 million) and working drawings ($1.2 million) to construct a new
49,900 asf (62,300 gsf) building (#31) to house the business administration,
education, and nursing disciplines. The project will include lecture space to
accommodate 513 FTE students and 100 faculty offices. The costs and schedule for
the entire project are shown in the figure below.
Sonoma Campus—Professional Schools Building
Systemwide
Revenue Bonds Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,125,000 — $1,125,000 February 2017 August 2017
Working drawings 1,181,000 — 1,181,000 September 2017 March 2018
Construction — $35,946,000 35,946,000a September 2018 March 2020
Equipment — 2,060,000 2,060,000
Totals $2,306,000 $38,006,000 $40,312,000
a
Includes $31.3 million for construction contracts (CCCI 6255), $2 million for architecture and engineering, $1.3 million for contingency, and
$1.3 million for project administration. The construction cost per square foot is $721 (assignable) and $577 (gross).
21. Stanislaus Campus—Library Seismic Renovation. Pursuant to Education Code
89772, CSU is authorized to use its General Fund appropriation for preliminary
plans ($1.8 million) and working drawings ($1.7 million) to renovate the 94,300 asf
(123,00 gsf) library building (#1,1A). The scope of the project includes correcting
seismic and code deficiencies, upgrading fire and life safety systems, and
upgrading plumbing and mechanical equipment. CSU anticipates construction
costs to total $45 million. The costs and schedule for the entire project are shown
in the figure below.
Stanislaus Campus—Library Seismic Renovation
Systemwide
Revenue Bonds Future Costs Total Cost Start Date Finish Date
Preliminary plans $1,841,000 — $1,841,000 February 2017 August 2017
Working drawings 1,728,000 — 1,728,000 September March 2018
2017
Construction — $44,764,000 44,764,000a September September
2018 2020
Equipment — — —
Totals $3,569,000 $44,764,000 $48,333,000
a
Includes $38.3 million for construction contracts (CCCI 6255), $3 million for architecture, $2.3 million for contingency, and engineering, and
$1 million for project administration. The construction cost per square foot is $475 (assignable) and $363 (gross).
76 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
Item 6870‑301‑6049—California Community Colleges—Capital Outlay
1. El Camino Community College District, El Camino College Compton Center—
Instructional Building 1 Replacement. Due to a project delay, the budget
reappropriates $13,438,000 for construction to replace seismically unsound
instructional buildings at El Camino College Compton Center. The project
consists of demolishing one permanent building and parts of two other
permanent buildings; removing two portable instructional buildings; and
constructing a new, two‑story instructional building on the site of the demolished
structures. The new building will replace 32,117 asf in the current structures with
17,273 asf (26,430 gsf). The new building will consist of 9,651 asf classroom space,
4,163 asf laboratory space, 3,218 asf office space, and 241 other asf. The costs and
revised schedule for the entire project are shown in the figure below.
El Camino Community College District, El Camino College Compton Center—
Instructional Building 1 Replacement
State Funds Non‑State Funds Total Funds Start Date Finish Date
Preliminary plans $223,000 $399,000 $622,000 August 2014 March 2016
Working drawings 559,000 427,000 986,000 April 2016 July 2016
Construction 13,438,000 2,746,000 16,184,000a July 2017 July 2019
Equipment — — —
Totals $14,220,000 $3,572,000 $17,792,000
a
Includes $14,376,000 for construction contracts (CCCI 5901), $719,000 for contingency, and $1,089,000 for project administration. The
construction cost per square foot is $585 (assignable) and $382 (gross).
2. Redwoods Community College District, College of the Redwoods—Utility
Infrastructure Replacement. Due to a project delay, the budget reappropriates
$33,146,000 for construction to replace utility infrastructure at the College of the
Redwoods Eureka campus to mitigate seismic risks. The scope for the project
includes (1) seismic mitigation for campus utility infrastructure and (2) ensuring
environmentally sensitive areas are protected from the consequences of a seismic
event. The project will not change existing asf. The costs and revised schedule for
the entire project are shown in the figure below.
Redwoods Community College District, College of the Redwoods—
Utility Infrastructure Replacement
State Funds Non‑State Funds Total Funds Start Date Finish Date
Preliminary plans $2,063,000 — $2,063,000 August 2014 March 2015
Working drawings 1,349,000 — 1,349,000 March 2015 January 2016
Construction 33,146,000 — 33,146,000a August 2016 July 2018
Equipment — — —
Totals $36,558,000 — $36,558,000
a
Includes $29,740,000 for construction contracts (CCCI 5901), $1,487,000 for contingency, and $1,919,000 for project administration.
LEGISLATIVE ANALYST’S OFFICE 77
Supplemental Report of the 2016-17 Budget Act
Item 7760‑301‑0660—Department of General Services—Capital Outlay
1. Central Plant: Capitol Irrigation Project. The budget provides $1,692,000 to install
a reclaimed water system from the state’s downtown Sacramento Central Plant
to the State Capitol Park for purposes of providing irrigation water. The total
estimated project cost is $1,692,000, including abbreviated preliminary plans
($1,000), working drawings ($339,000), and construction ($1,352,000). The amount
for construction includes contract ($907,000), contingency ($64,000), architecture
and engineering ($238,000), and other project costs ($143,000). Working
drawings are scheduled to begin August 2016 and be completed February 2017.
Construction is scheduled to begin July 2017 and be completed April 2018.
Item 8940‑301‑0001 and 8940‑301‑0890—Military Department—
Capital Outlay
1. San Diego Readiness Center Renovation. The amount of $3,430,000 ($1,715,000
General Fund and $1,715,000 matching federal funds) is provided for the first
phase of construction to renovate the San Diego Readiness Center. Construction
of the project will be completed in three phases to: (a) eliminate the requirement
to relocate the 400 Soldiers that work in the building, and (b) allow for the proper
application of federal matching funds from the annual allocation that the Military
Department receives under the Sustainment, Restoration, and Modernization
program. Total project costs are $11,554,000 ($1,712,000 for design, $9,618,000 for
construction, and $224,000 for equipment). Working drawings are estimated to
be completed by June 2016 and the first phase of construction is estimated to be
completed by June 2017.
2. Sustainable Armory Renovation Program: Eureka. The amount of $5,656,000
($2,828,000 General Fund and $2,828,000 matching federal funds) is provided
for the performance criteria and design‑build phases to renovate the Eureka
armory. Total project costs include $390,000 for performance criteria, $5,216,000
for construction, and $50,000 for equipment. The amount for construction
includes $4,800,000 for the contract, $240,000 for contingency, and $176,000 for
project administration. Design is estimated to be completed by March 2017 and
construction is estimated to be completed by June 2018.
3. Sustainable Armory Renovation Program: Escondido. The amount of $4,128,000
($2,064,000 General Fund and $2,064,000 matching federal funds) is provided
for the performance criteria and design‑build phases to renovate the Escondido
armory. Overall project costs include $326,000 for performance criteria, $3,802,000
for construction, and $50,000 for equipment. The amount for construction
includes $3,454,000 for the contract, $173,000 for contingency, and $125,000 for
78 LEGISLATIVE ANALYST’S OFFICE
Supplemental Report of the 2016-17 Budget Act
project administration. Design is estimated to be completed by March 2017 and
construction is estimated to be completed by June 2018.
4. Sustainable Armory Renovation Program: Santa Cruz. The amount of $4,012,000
($2,006,000 General Fund and $2,006,000 matching federal funds) is provided
for the performance criteria and design‑build phases to renovate the Santa Cruz
armory. Overall project costs include $302,000 for performance criteria, $3,710,000
for construction, and $50,000 for equipment. The amount for construction
includes $3,358,000 for the contract, $168,000 for contingency, and $134,000 for
project administration. Design is estimated to be completed by March 2017 and
construction is estimated to be completed by June 2018.
5. Sustainable Armory Renovation Program: San Bernardino. The amount of
$4,802,000 ($2,401,000 General Fund and $2,401,000 federal matching funds) is
provided for the construction phase of the San Bernardino armory. Overall project
costs include $4,196,000 for construction and $606,000 for equipment. The amount
for construction includes $3,986,000 for the contract and $210,000 for contingency.
Construction is estimated to be completed by October 2017.
Item 8940‑301‑0001—Military Department—Capital Outlay
1. Consolidated Headquarters Complex. The amount of $6,889,000 General Fund
is provided for the performance criteria phase of the continuing Consolidated
Headquarters Complex (Complex) project in Sacramento. The Complex will
provide the Military Department with an operationally enhanced and secured
238,000 sf consolidated headquarters building, a 25,000 sf armory, and a 22,600 sf
storage facility. Per federal force protection criteria, physical security measures
such as protective window glazing and reinforced walls will be incorporated
into the design of the buildings. Total project costs are $113,759,000 ($6,889,000 for
performance criteria and $106,870,000 for design‑build). Design is estimated to
be completed by June 2017 and construction is estimated to be completed by May
2020.
2. Los Alamitos: Southern Region Emergency Operations Center Replacement. The
amount of $1,854,000 General Fund is provided for the preliminary plans
and working drawings phases of the Southern Region Emergency Operations
Center replacement project, to be located at the Joint Forces Training Base in Los
Alamitos. The project will construct an approximately 30,000 sf facility which will
serve as a Defense Support to Civil Authorities Center for the National Guard,
will support the day‑to‑day operations of the Office of Emergency Services (OES)
emergency management programs, and will provide a back‑up State Operations
Center and State Warning Center for both OES and the Military Department.
Overall estimated project costs are $25,724,000 ($570,000 for preliminary plans,
LEGISLATIVE ANALYST’S OFFICE 79
Supplemental Report of the 2016-17 Budget Act
$1,284,000 for working drawings, and $23,870,000 for construction). Design is
estimated to be completed by November 2017 and construction is estimated to be
completed by July 2019.
Item 8940‑301‑0604—Military Department—Capital Outlay
1. Discovery Academy Youth Challenge Program Dining Facility. The amount of
$2,600,000 Armory Fund is provided for the performance criteria and design‑
build phases to construct a joint‑use dining facility at the Army National Guard
Base in Lathrop. Overall project costs include $295,000 for performance criteria
and $2,305,000 for construction. The amount for construction includes $ 1,925,000
for the contract, $85,000 for contingency, and $295,000 for project administration.
Design is scheduled to be completed by August 2016 and construction is
estimated to be completed by June 2017.
Item 8955‑490 and 8955‑491—Department of Veterans Affairs—
Capital Outlay
1. Veterans Home of California, Yountville: Chilled Water Distribution System
Renovation—Reappropriation. The budget provides a reappropriation in the
amount of $3,665,000 Federal Trust Fund and $1,709,000 Lease Revenue Bond
Funds for the construction phase of the Chilled Water Distribution System
Renovation project at the Veterans Home of California, Yountville. The project
will provide added chiller capacity and replace failing mechanical equipment. In
addition, a new packaged 400 ton chilled water plant will be installed to meet the
increased demand on the chilled cooling system and to provide back‑up power in
case of emergency. Construction is scheduled to begin January 2017 and project
completion is scheduled for April 2018.
2. Veterans Home of California, Yountville: Steam Distribution System Renovation—
Reappropriation. The budget provides a reappropriation in the amount of
$4,095,000 Federal Trust Fund and $2,808,000 Lease Revenue Bond Funds
for the working drawings and construction phases of the Steam Distribution
System Renovation project at the Veterans Home of California, Yountville. The
project will repair underground steam distribution lines and provide for an
additional ten space Americans with Disabilities Act‑compliant parking lot
within the facility. Working drawings are scheduled for completion by April 2018,
and construction is scheduled to begin in October 2018. Project completion is
scheduled for September 2020.
80 LEGISLATIVE ANALYST’S OFFICE