LAO
The Administration’s Sacramento Office Building Construction Strategy: Ensuring Robust Oversight
Read the report at Legislative Analyst's Office ↗
The Administration’s Sacramento
Office Building Construction Strategy:
Ensuring Robust Oversight
YEARS OF
SERVICE
MAC TAYLOR • L E G I S L A T I V E A N A L Y S T • DECEMBER 2016
AN LAO REPORT
2 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
EXECUTIVE SUMMARY
$1.3 Billion Approved in 2016-17 Is First Step in Administration’s Larger Strategy. In adopting
the 2016-17 budget package, the Legislature established the State Project Infrastructure Fund
(SPIF), which is continuously appropriated for state projects. The Legislature further provided
$1.3 billion to the SPIF over two years for three specific state office building construction projects
in Sacramento. These projects reflect the first step of the administration’s larger regional strategy
to construct or renovate a total of 11 state office buildings in the Sacramento area over the next ten
years. We expect that in the coming years the administration will come forward with more than
$1 billion in additional funding requests to continue to carry out this strategy.
Administration’s Approach to Strategy Raises Some Specific Concerns. Assessing the
condition of the state’s office buildings and taking a regional approach to maintaining these assets
makes sense and is consistent with legislative direction. However, we identify some specific areas of
concern for the Legislature as it faces decisions about (1) whether to move forward with additional
state building projects and (2) how best to oversee the projects funded with the $1.3 billion provided
in 2016-17. Specifically, we find the following:
• Strategy Lacks Adequate Analysis. The administration’s strategy lacks basic information
necessary to determine its merits, including its costs, benefits, and potential alternative
approaches—such as addressing a different mix of buildings from the 11 state office
buildings that are proposed.
• Strategy Is Ambitious. The strategy includes an ambitious construction and renovation
schedule, which the administration is already falling behind. Additionally, while the
administration has not provided cost estimates, the strategy is likely to be expensive and
appears to be growing more so.
• Existing SPIF Process Is Problematic for Future Projects. The administration indicates
that it plans to continue to use the SPIF funding process—including the use of continuous
appropriations—for future projects. This process—which allows the administration to
establish and fund projects without legislative approval—greatly reduces legislative control
and oversight compared to the traditional budget process. Furthermore, the weaknesses of
the process are magnified when more funds are added to the SPIF because the additional
funds increase the monies available for the administration to fund projects that were not
envisioned by the Legislature.
Recommend Legislature Provide Clear Direction to Administration on Strategy. We
recommend that the Legislature take the following actions to address the above concerns:
• Direct the administration to provide a robust analysis of its strategy. This should include
information necessary to evaluate the merits of the strategy, such as the strategy’s costs,
benefits, and other available approaches to addressing state office building deficiencies.
www.lao.ca.gov Legislative Analyst’s Office 3
AN LAO REPORT
• Closely monitor the expenditure of the $1.3 billion approved in 2016-17 through the use of
hearings at key points in project life cycles.
• Make it clear to the administration that any future funding provided for state office
building projects should go through the typical budget process rather than a continuous
appropriation under the current SPIF process.
We believe these recommendations would help ensure that the state has the information it needs
to move forward with the best available strategy for addressing its buildings in the Sacramento area
and that any funds provided are spent with adequate legislative oversight and accountability.
4 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
INTRODUCTION
In adopting the 2016-17 budget package, Additionally, the Legislature will have to decide
the Legislature established the State Project how to best oversee the projects funded with the
Infrastructure Fund (SPIF) and provided $1.3 billion provided in 2016-17.
$1.3 billion over two years for three specific This report is intended to help guide the
state office building projects in the Sacramento Legislature as it makes these decisions. We begin by
area. These projects reflect the first step of the providing background information on Sacramento
administration’s larger regional strategy to state office buildings and summarizing the actions
expand and improve state office buildings in the taken in the 2016-17 budget process. Next, we
Sacramento area over the next ten years. In the assess the administration’s regional strategy for
coming years, the Legislature will be presented state office buildings in the Sacramento area.
with important decisions related to this strategy. Finally, we provide recommendations to assist the
Specifically, the Legislature will have to determine Legislature as it faces key decision points related to
whether to proceed with the additional projects the administration’s strategy.
envisioned in the administration’s regional strategy.
BACKGROUND
The state, through the Department of approved a total of $2.5 million for DGS to
General Services (DGS), owns and maintains complete a long-range planning study (Long-Range
58 general purpose office buildings across the Study) of state-owned general purpose office
state. Thirty-four of these buildings—totaling space in the Sacramento area. The Long-Range
over 8 million square feet—are in the Sacramento Study was to include (1) an update of an earlier
area. These Sacramento area buildings are valued planning study identifying potential office space
at over $4 billion and house 35 state departments development opportunities in Sacramento (Office
and agencies, such as the Department of Water Planning Study); (2) condition assessments of
Resources and the Franchise Tax Board. The state all state office buildings in the Sacramento area
also leases about 8 million square feet of general (Sacramento Assessment Report); (3) a plan for
purpose office space in the Sacramento area. (We sequencing the renovation or replacement of state
note that some state departments other than DGS office buildings in Sacramento (Sequencing Plan);
operate office space for more specific purposes. and (4) a funding plan for undertaking these
For example, the Department of Motor Vehicles projects, including project cost estimates and an
operates field offices.) economic analysis (Funding Plan).
Chapter 451 of 2014 (AB 1656, Dickinson)
Legislature Required Analysis of
required that DGS complete this Long-Range Study
Sacramento Office Buildings
by July 1, 2015, as well as provided direction on the
DGS Directed to Perform Sacramento Office contents of the study and how it was to be used by
Planning Effort. As part of the 2014-15 budget, DGS. First, the legislation specified that the study
the administration proposed and the Legislature should guide the state’s actions on state buildings
www.lao.ca.gov Legislative Analyst’s Office 5
AN LAO REPORT
over the next 25 years. Second, it required that “good.” As shown in Figure 1, some of these sites
DGS use the information in the Long-Range Study are state-owned and some are privately owned.
as the basis for developing detailed cost and scope Additionally, the development time frames for
information to be considered in future budget these sites vary, with some potentially ready for
proposals. Finally, it directed DGS to issue requests development within five years—such as Downtown
for proposals to address the renovation and Block 204 (currently occupied by a parking lot and
replacement needs of Sacramento office buildings, the historic Heilbron House)—and others available
starting with the three buildings with the most for development within six to ten years—such as
significant and immediate facility needs. the State Printing Plant site. Many of these sites
Office Planning Study Identified Potential contain existing buildings that would have to
Office Development Sites. In 2015, DGS completed be demolished or moved to accommodate new
the Office Planning Study component of the development.
Long-Range Study, which identified and ranked Sacramento Assessment Report Identified
41 potential sites in Sacramento for future Buildings With Highest Needs. In July 2015, DGS
development over the next 40 years based on released the Sacramento Assessment Report portion
an evaluation of the feasibility of developing of the Long-Range Study. The report evaluated
the sites. Using criteria such as size, ownership 29 state-owned office buildings in Sacramento. (The
(state-owned versus privately owned), and access report excluded a few buildings that were vacant or
to transportation, the evaluation rated the seven that DGS did not consider to be typical office space,
best sites as “superior” and nine additional sites as such as the State Capitol Annex.)
Figure 1
Potential Superior and Good Development Sites Identified in
Sacramento Office Planning Study
Development
Site Ownership Time Frame (Years) Location
Superior
Bonderson Building site State 0-5 Downtown Sacramento
CalPERS site State 0-5 Downtown Sacramento
Downtown Block 275 State 0-5 Downtown Sacramento
Downtown Blocks 203 and 204 State 0-5 Downtown Sacramento
Food and Agriculture Annex site State 0-5 Downtown Sacramento
Franchise Tax Board site State 0-5 County (near Rancho Cordova)
Richards Boulevard area Private 0-5 Railyards area/River District
Good
Resources Building site State 6-10 Downtown Sacramento
State Printing Plant site State 6-10 Railyards area/River District
Downtown Core Private 0-5 Downtown Sacramento
Bradshaw Landing Private 0-5 County (near Rancho Cordova)
Granite Park Private 0-5 Granite Regional Park area (near
Tahoe Park)
Railyards area Private 0-5 Railyards area/River District
Southport Business Park Private 0-5 West Sacramento
West Capitol Downtown Private 0-5 West Sacramento
Pioneer Bluff area Private 6-10 West Sacramento
6 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
Overall, the Sacramento Assessment Report SPIF Funds Are Continuously Appropriated.
noted that all of the buildings that were evaluated In adopting the 2016-17 budget package, the
were in a safe, serviceable, and functioning Legislature passed Chapter 31 of 2016 (SB 836,
condition. The report developed a Facility Committee on Budget and Fiscal Review),
Condition Index (FCI) score for each building, which governs the use of the SPIF. Chapter 31
which compared the estimated costs of repairing specifies that monies in the SPIF are continuously
versus replacing the building. (A high FCI score appropriated. It also authorizes the administration
means that a building’s repair costs are relatively to establish and move forward with projects
high compared to cost of replacement.) Based on without having to receive legislative approval
this analysis, the report ranked the 29 buildings, through the traditional state budget process, as is
identifying 9 in poor condition, 4 in fair condition, typically required for capital outlay projects. (Please
and 16 in good condition, as shown in Figure 2 see the box on page 9, for a detailed description
(see next page). The report ranked the Resources of the traditional state budget process for capital
Building, Personnel Building, and Bonderson outlay projects.)
Building as those in most critical need of renovation Certain Notifications Required for Funded
or replacement and recommended prioritizing Projects. Chapter 31 requires the administration
the needs of these buildings over other buildings, to provide the Legislature with quarterly reports
consistent with the direction provided in and notifications in order to establish and move
Chapter 451. The report also found that all of the forward with SPIF-funded projects. Figure 3 (see
buildings that were evaluated had FCIs well below page 9) summarizes the required notifications.
65, which is the industry standard for replacement. For example, at least 20 days before spending
This suggests that all of the buildings that were SPIF funds on project planning activities, the
evaluated are better candidates for repair rather administration must provide the Joint Legislative
than replacement. (As we discuss later, in September Budget Committee (JLBC) with a notice
2016 the administration completed assessments of identifying the purpose of the planning activity
the condition of general purpose office buildings in and its estimated costs. In September 2016, the
other parts of the state besides Sacramento.) administration provided the Legislature with
the first notification through this process—a
Funding Provided for First Three Projects
20-day notification regarding its intent to spend
2016-17 Budget Package Included $1.3 Billion $4.9 million on the development of the cost, scope,
Over Two Years. The 2016-17 budget package and delivery method for the O Street Building
provided $1 billion from the General Fund in and the new Resources Building. The notification
2016-17 and $300 million in 2017-18 to be deposited review periods for the Legislature range from 20 to
into a new fund, the SPIF. This funding is to be 60 days depending on the project and activity. We
used for three buildings in the Sacramento area: a note that, because of its unique characteristics,
new building at the current Food and Agriculture Chapter 31 created a separate process for the State
Annex site on O Street (O Street Building), a new Capitol Annex as described in the box on page 10.
Resources Building at a different site, and either As such, when we discuss state office buildings
replacement or renovation of the State Capitol in this report, we do not include the State Capitol
Annex. (Throughout this report, we refer to these Annex unless otherwise specified.
three projects as the “three initial projects.”)
www.lao.ca.gov Legislative Analyst’s Office 7
AN LAO REPORT
Figure 2
Condition of Buildings Evaluated in Sacramento Assessment Report
Resources
Personnel
Bonderson
EDD Annex
Poor
Unruh
Bateson
Justice
EDD Headquarters
Blue Anchor
Energy
FTB Phase I
Fair
Board of Equalization
Library and Courts II
Secretary of State
Agriculture
FTB Phase II
Attorney General
Buildings and Grounds
East End Block 225
Library and Courts
Campbell OES
Office Building 8 Good
Office Building 9
FTB Phase III
East End Block 171
East End Block 172
Rehabilitation
East End Block 174
East End Block 173
5 10 15 20 25 30 35 40
Facility Condition Indexa
a The Facility Condition Index represents a ratio of each building's estimated repair costs to the estimated replacement value.
EDD = Employment Development Department; FTB = Franchise Tax Board; and OES = Office of Emergency Services.
8 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
Figure 3
Required Notifications for State Projects Funded Through the
State Project Infrastructure Funda
Minimum
Number of Days
of Advanced
Activity Contents of Required Notice Notification
Expenditure of funds on planning activities Purpose of planning activity and estimates of costs 20
Establishment of scope, cost, and delivery Scope, budget, delivery method, expected tenants, and 45 or 60b
method schedule for any space to be constructed or renovated as part
of that state project
Approval of the project design of a state project Updated estimates of cost and schedule 30
by State Public Works Board
Contract or a lease arrangement for a state Updated estimates of cost and schedule 30
project that includes construction
Change to the scope of an approved project Change in the scope and any associated costs 20
Change in the cost of an approved project of Change in the cost 20
between 10 percent and 20 percentc
a
Excludes State Capitol Annex project, which is governed by a separate notification process.
b
Minimum of 45 days must be provided for the O Street and new Resources building projects. Minimum of 60 days must be provided for other state projects.
c
The administration indicates that it interprets the law to require them to seek legislative approval of cost increases over 20 percent.
Traditional State Budget Process for Capital Outlay Projects
Under the traditional state budget process, the administration proposes individual capital outlay
projects as part of the Governor’s proposed budget for the coming fiscal year. These capital outlay
budget change proposals generally include important details on the proposed projects—such as the
project scope, construction timeline, costs by project phase, funding sources, delivery method, and
a narrative justification. They also include an analysis of alternatives and an explanation of why the
alternatives were rejected in favor of the proposed project.
Typically, the administration submits proposals prior to being able to initiate certain design and
construction phases of a project. As part of its review of these proposals, the Legislature assesses
if projects are consistent with its funding priorities and the long-term programmatic needs of the
relevant department.
After an individual capital outlay project is approved, the Legislature maintains oversight of
certain changes related to the project. Specifically, if the scope of a project changes substantively or
if the project’s costs increase by more than 20 percent, the administration is generally required to
seek legislative approval through the traditional budget process before being able to proceed. (If the
project’s scope changes minimally or its costs increase by between 10 percent and 20 percent, the
typical process requires the administration to notify the Joint Legislative Budget Committee.) If
the Legislature has concerns about the administration’s proposed changes, the Legislature has the
opportunity to reject them or to direct the administration to make changes to address the concerns.
www.lao.ca.gov Legislative Analyst’s Office 9
AN LAO REPORT
Administration’s Sequencing Plan Strategy departments with similar functions in order to
achieve operational and programmatic efficiencies.
Administration Released Sequencing Plan
The Sequencing Plan also states a preference for
for Next Ten Years. In March 2016, DGS released
state ownership of office space in high-cost areas
the Sequencing Plan portion of the Long-Range
(rather than leasing), under the assumption that
Study. The Sequencing Plan represents the
state-ownership is more cost-effective.
administration’s proposed strategy for addressing
Administration’s Strategy Proposes Various
the facility needs of Sacramento office buildings—
Projects. In total, the strategy would result in
including the three initial projects—over the next
constructing three new state office buildings
ten years. (We also refer to this Sequencing Plan as
consisting of about 2 million square feet—the new
the administration’s “strategy” in this report.) We
Resources Building, the O Street Building, and a
note that the administration indicates that it no
new building at the State Printing Plant site—and
longer plans to complete the remaining portion of
reducing leased space by a roughly equivalent
the Long-Range Study, the Funding Plan.
amount. (The funding provided in 2016-17 is for
Administration’s Strategy Articulates Certain
the new Resources and O Street Buildings, as well
Principles. While addressing building condition
as the State Capitol Annex.) The strategy also
needs is a primary motivation for the strategy, the
proposes to renovate eight existing state office
administration indicates that the strategy is also
buildings consisting of about 2 million square
intended to serve other goals, such as consolidating
feet. These activities would occur over a ten-year
department office space to colocate staff working
period. Nearly all of the buildings proposed to be
on similar topics and reducing the use of leased
constructed or renovated are within the downtown
space by constructing additional state-owned office
core of Sacramento, as shown in Figure 5 (see
space. Consistent with those goals, the strategy
page 12). In total, the strategy would address
articulates the administration’s principles for state
one of the three worst buildings identified in the
office projects, which are summarized in Figure 4.
Sacramento Assessment Report—the Resources
For example, one principle is to consolidate
State Capitol Annex Project Governed by Separate Process
The State Capitol Annex (Annex) is a unique building owned by the state. Built in 1952, the
Annex is attached to the east side of the historic Capitol building, which was constructed in 1874.
In order to make room for the Annex, the original design of the east side of the Capitol, including
a distinctive semi-circular architectural structure known as an apse, was destroyed. Today, the
Annex provides roughly 365,000 square feet of space for legislative and gubernatorial offices as well
as a variety of committee rooms. Additionally, more than one million visitors are estimated to visit
the State Capitol and its Annex annually. Because of its distinctiveness, Chapter 31 of 2016 (SB 836,
Committee on Budget and Fiscal Review) creates a separate process to guide the project that will
replace or renovate the Annex. The separate process for this project envisions a collaborative
approach between the administration and the Legislature’s Joint Committee on Rules (JCR). It also
specifically requires the Department of General Services to report to JCR on the scope, budget,
delivery method, and schedule for the Annex project.
10 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
Building. We note that the administration proposes their original buildings after those buildings are
the design-build delivery method—in which a renovated. Limiting the number of staff relocations
single contractor designs and constructs a project— can be worthwhile because relocations can affect
for all of the planned projects. department operations and result in significant
Strategy’s Projects Are Closely Interrelated. costs, including costs to lease temporary space
In most cases, the proposed projects in the during renovations and move office equipment and
administration’s strategy are interrelated. This is files.
because the administration is generally proposing As shown in Figure 6 (see page 13), under
to strategically sequence the building renovations the administration’s plan, the construction of
by successively conducting staff moves and the new Resources Building is the first step in
building renovations. Consistent with its stated the renovation or construction of many other
goals, strategically sequencing building renovations interrelated state buildings. Once the new
would allow DGS to reduce the number of Resources Building is constructed, staff from the
relocations that departments must undergo existing Resources Building will be relocated to
since department staff would not move back into the new space. The vacated Resources Building will
Figure 4
Administration’s Principles for Sequencing Sacramento Office Space
9
The state prefers to own buildings in areas with high lease costs in order to reduce space costs for state
departments.
9
The state shall first consider building on state property before pursuing construction on commercial
sites.
9
The state will design new construction and renovation projects with a goal towards achieving Zero Net
Energy by incorporating the latest proven materials, designs, technologies, and construction practices.
9
The state prefers that new buildings be built in proximity to public transit.
9
When feasible, the state will offer mixed use development in new office buildings to better meet our
tenant and larger community needs.
9
To generate operational and programmatic efficiencies, the state will aim to consolidate departmental
space and colocate departments within the same agencies and/or similar functions between
departments.
9
The state will use more standardized office configurations to minimize tenant improvement costs and
allow for the greatest flexibility when filling space with state tenants.
9
To avoid disruption and minimize costs, the Department of General Services (DGS) will strive to
minimize the number of moves a department must make.
9
DGS will coordinate its facility sequencing strategy with its review of state leased space to generate
more competitive lease rates in private sector facilities.
9
DGS will continue to meet the programmatic needs of tenants in state buildings but will not complete
significant building improvements in buildings it plans to completely renovate, demolish, or sell within the
next five years.
www.lao.ca.gov Legislative Analyst’s Office 11
then be renovated, and staff from the Employment envisioned related to the construction of the new
Development Department (EDD) Headquarters O Street Building and State Printing Plant site.
and Annex Buildings will be relocated to the
Assessments of Office Buildings in
renovated space. That, in turn, will leave the EDD
Other Parts of State
Headquarters and Annex Buildings vacant and
available for renovation and the relocation of In addition to assessing the condition
the staff from the Energy Commission Building. of Sacramento area buildings as required by
Through the ten-year planning window covered Chapter 451, DGS released an assessment of
by the plan, this chain will continue until the state 21 office buildings totaling about 5.1 million
ultimately moves staff from existing leased space square feet in other parts of the state (Statewide
into newly renovated state office space. Similar Assessment Report). This assessment was
sequencing of staff moves and renovations is completed in September 2016 and developed
L Street
Capitol Mall Capitol Park
N Street
O Street
P Street
Roosevelt
Park
Q Street
teertS
ht5
teertS
ht01
teertS
ht51
AN LAO REPORT
Figure 5
Location of Sacramento Office Buildings to Be Renovated or Constructed
Richards
Blvd.
Renovated Building
Printing
Plant e et New Building
Site Str
h
7t
N
Railyards
Unruh
EDD
EDD
Annex HQ
Solar
BOE E An D ne D x Existing Blue Anchor
Resources
O Street
New
Resources CEC
Bateson
Downtown
BOE = Board of Equalization; EDD = Employment Development Department; and CEC = California Energy Commission.
12 Legislative Analyst’s Office www.lao.ca.gov
ARTWORK #160511 Graphic Sign Off
Template_LAOReport_large.ait Secretary
Analyst
MPA
AN LAO REPORT Deputy
Figure 6
Strategy Includes Sequencing of Interrelated Projects
CDCR
DWR, Parks, Leases
N C R al F A ir g e e , n D c F y, W Under Renovation EDD Under Renovation
Energy Commission
Existing Resources EDD Headquarters
and Annex
Under Renovation Unknown
DWR
Energy Commission Leases
New Resources
STO Transportation, Government Operations
and BCSH Agency Swing Space
Unknown
Building Type
Bonderson
Under Renovation
New State Building
Unruh
Board of
Chiropractic
Examiners
Leases
Leased Building
BCSH Agency
Government
Ops Agency
BOE Renovated State Building
New Printing Plant Site
HCD, DBO,DCA, BOE
Under Renovation SPB Under Renovation
State Personnel
BOE
DGS, CalHR, Caltech, Existing State Building
OAL, CalVCB (Future Use Unspecified)
Leases
Leases
DDS,
H
Ag
H
e
S
n cy,
Under Renovation C
C
D
D
C
FA
DSH
New O Street Bateson Leases
G
O
o
ff
v
ic
e
e
r
,
n
O
or
P
’s
R
Under Renovation
Leases Blue Anchor
BCSH = Business, Consumer Services, and Housing; BOE = Board of Equalization; CalFire = Department of Forestry and Fire Protection; CalHR = Human Resources;
Caltech = Department of Technology; CalVCB = California Victim Compensation Board; CDC = Department of Conservation; CDFA = Department of Food and Agriculture;
DBO = Department of Business Oversight; DCA = Department of Consumer Affairs; DDS = Department of Developmental Services; DGS = Department of General
Services; DPR = Department of Parks and Recreation; DSH = Department of State Hospitals; DWR = Department of Water Resources; DFW = Department of Fish and
Wildlife; EDD = Employment Development Department; HCD = Housing and Community Development; HHS = Health and Human Services; NR Agency = Natural
Resources Agency; OAL = Office of Administrative Law; OPR = Office of Planning and Research; and STO = State Treasurer’s Office.
www.lao.ca.gov Legislative Analyst’s Office 13
AN LAO REPORT
the FCI for each of these buildings. As shown in Sacramento. Specifically, based on their current
Figure 7, this assessment identified 2 additional condition, two buildings—the San Diego State
buildings in poor condition, 5 in fair condition, and Building and the Stockton State Building—ranked
14 in good condition. In some cases, these buildings among the ten state office buildings most in need of
were rated in worse condition than buildings in repair.
LAO ASSESSMENT
Overall, the concept of addressing state office the strategy is ambitious—both in terms of cost and
building needs as part of a regional strategy— schedule—and that the existing SPIF process does
rather than on an ad hoc basis—makes sense. not facilitate adequate legislative oversight.
However, we identify below several specific
Taking a Regional Approach Makes Sense
areas where the administration has not provided
adequate information and a robust analysis to The state needs to take care of its office
ensure that the Legislature can assess whether its buildings in order to ensure that they can
strategy is a good approach, much less the best continue to provide services for years to come.
approach available to the state to address these Additionally, addressing state office buildings as
buildings in the future. Additionally, we find that part of a regional strategy makes sense. We find
Figure 7
Ranking of Office Buildings Outside of Sacramento
Facility Statewide
Age Condition Condition
Building City (Years) Condition Index Ranking
San Diego State Building San Diego 53 Poor 17.3 4
Stockton State Building Stockton 52 Poor 12.9 10
Fresno Water Resources Building Fresno 49 Fair 9.9 12
Hugh Burns State Building Fresno 56 Fair 8.0 13
Santa Ana State Building Santa Ana 40 Fair 6.9 15
Redding State Building Redding 53 Fair 6.1 16
Van Nuys State Building Los Angeles 32 Fair 6.0 17
Mission Valley State Building San Diego 16 Good 4.3 22
Justice Joseph A. Rattigan Building Santa Rosa 33 Good 4.3 23
Ronald Reagan State Building Los Angeles 25 Good 4.0 24
Wadie P. Deddeh State Office Building San Diego 10 Good 2.8 27
Red Bluff State Building Red Bluff 47 Good 2.8 28
Ronald M. George State Office Complex/Earl Warren San Francisco 94 Good 2.5 29
California Tower Riverside 44 Good 2.0 32
Alfred E. Alquist Building San Jose 33 Good 1.8 33
Governor Edmund G. “Pat” Brown Building San Francisco 32 Good 1.2 35
4th District Court of Appeal Riverside 17 Good 0.9 38
Junipero Serra Office Building Los Angeles 102 Good 0.7 39
Elihu M. Harris State Building Oakland 18 Good 0.4 40
Ronald M. George State Office Complex/Hiram Johnson San Francisco 18 Good 0.3 43
Leo J. Trombatore Building Marysville 6 Good 0.1 49
14 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
that a regional strategy—informed by data on much of the key information necessary to make
building needs from recent facility assessments—is such an assessment. Specifically, the strategy
important for a few reasons. lacks basic information on its costs, its benefits,
and potential alternatives that are available. It is
• First, it allows the state to get a more
particularly important for the Legislature to have
complete understanding of the condition of
this information given the scale and costs of the
the state office buildings across the region,
identified projects.
rather than focusing only on certain
No Analysis of Costs. The administration has
buildings. This can better enable the state
not provided any estimate of the costs of its strategy.
to prioritize resources to higher-need
We would typically expect the administration to
buildings.
prepare such an analysis as part of the development
• Second, a regional strategy allows the state of its strategy, just as we would expect the
to assess Sacramento-area building needs in administration to provide cost estimates for any
the context of other state goals. For example, proposal. This type of information is necessary for
the administration identified colocating the Legislature to be able to weigh the merits of the
department staff. A regional strategy enables proposed projects against its other priorities for
the state to consider those types of goals, limited state resources.
along with identified facility needs, as it Recognizing this importance, the 2014-15 budget
directs resources within the region. provided DGS with funds to undertake the Funding
Plan component of the Long-Range Study, which
• Third, a regional strategy can enable the
was to include cost estimates of planned projects
state to take advantage of opportunities to
the administration proposed to pursue. However,
strategically sequence building renovations
the administration indicates that it no longer plans
in the region. This can help to reduce the
to complete this Funding Plan. (It is unclear how
number of required building relocations
the funding provided was used.) We note that an
and their associated costs.
overall cost estimate for the strategy—rather than a
Given the advantages of a regional approach, piecemeal approach that only provides cost estimates
we find that the Governor’s efforts so far to address for individual projects when they are proposed—is
this important topic in a systematic way is a step particularly important because of the interrelated
in the right direction, including his release of a nature of the projects within the strategy. It is difficult
strategy outlining the timing of future state office for the Legislature to make an informed decision
projects in Sacramento. about any individual future project without even a
rough understanding of the costs (and benefits) of the
Administration’s Strategy
related projects in the strategy.
Lacked Adequate Analysis
Benefits of Strategy Not Identified. The
The administration’s specific sequencing administration has also failed to clearly articulate
strategy for addressing Sacramento office buildings the benefits that it expects to achieve from the
could be a good strategy, or even potentially proposed strategy and to quantify them where
the best strategy, available to the state over the feasible. As with any proposal, it is important
coming years. However, it is impossible to assess for the Legislature to receive information on
whether this is the case because the strategy lacks the expected benefits of the strategy in order to
www.lao.ca.gov Legislative Analyst’s Office 15
AN LAO REPORT
determine whether it is justified. We recognize that an analysis that evaluates the advantages and
in many cases, these benefits are not likely to be disadvantages of the alternatives and explains why
quantifiable. For example, it is probably impossible the administration ultimately rejected them in
to fully value the benefits associated with providing favor of the proposal. Such an analysis is necessary
modern office space to employees. Additionally, it for the Legislature to effectively understand the
is difficult to fully assess the operational savings various options available and assess whether the
achieved from colocating department staff. administration’s proposal is not only a good option,
However, even if these benefits are not quantifiable, but the best option available.
it is still valuable for the administration to fully We note that there are two main alternatives
identify and describe them in order to support its that are available to the state that the
rationale for proceeding with the strategy. administration should have included it its analysis.
We also note that there are some benefits that First, the administration should have analyzed
could be quantified. In those cases, we would options for addressing a different mix of state office
expect the administration to estimate and report buildings than the 11 state office buildings that are
them. For example, one of the administration’s proposed. This should have included an alternative
stated principles is to make both the new and that addresses the three Sacramento office
renovated facilities in the strategy Zero Net buildings assessed to be in the worst condition,
Energy—that is, to have them generate as much consistent with the legislative direction provided
energy on-site as they use on an annual basis. in Chapter 451. As shown in Figure 8, two of the
Given the reduced energy use that this goal implies, three buildings in worst condition—the Personnel
we would expect the administration to include Building and the Bonderson Building—are not
an estimate of the resulting financial savings addressed in the administration’s strategy. It also
(as well as the costs to achieve these benefits). should have included an option that addresses other
Additionally, the strategy involves building high-need, “poor condition” buildings, as three of
2 million square feet of new state office space that the nine poor condition buildings in Sacramento
will ultimately replace state leases—resulting in are not included in the administration’s strategy.
some state savings associated with fewer leases. We Second, the administration should have
would expect the administration to quantify the evaluated the most cost-effective way to address
savings from fewer leases and compare them to the needs of these buildings. For example, it should
the costs of constructing this new space. We note have included an analysis of whether it is more
that when we conducted this type of comparison cost effective to construct new buildings versus
based on available data and using some standard pursue other approaches, such as purchasing or
assumptions, we found that it could take over leasing existing privately owned office buildings.
100 years for the savings from lower lease costs We note that this type of evaluation is particularly
to offset the construction and operating costs important for informing the Legislature’s future
associated with the new buildings proposed. By decision about whether to fund the new building
that point, these buildings likely would be well at the Printing Plant site because there is growing
beyond their useful lives. evidence that the new buildings that were funded
No Analysis of Alternatives. The in 2016-17 are likely to be expensive compared to
administration’s strategy also fails to include an other available options. Specifically, based on the
analysis of available alternatives. Specifically, administration’s preliminary estimates, we expect
16 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
the new Resources and O Street buildings to cost would be more than double current market rents in
roughly $1,000 per square foot. This is well above the downtown area.
the estimated cost of building a new high-rise
Proposed Strategy Is Ambitious
in downtown Sacramento—about $400 to $500
per square foot—and far exceeds the recent sales The proposed strategy is likely to be a
prices of existing office buildings in the downtown significant General Fund expense and includes an
area—generally under $300 per square foot. Also, ambitious construction and renovation schedule.
when the opportunity costs of capital are taken into There are also early indications that the strategy’s
account, we estimate that the state’s annual costs costs and timelines are already increasing for some
of constructing and operating these new buildings of the three initial projects. Furthermore, given the
Figure 8
Condition of Sacramento Area Office Buildingsa
Facility Condition Age Renovated or
Building Condition Condition Index Ranking (Years) Replaced in Plan
Resources Building Poor 38.0 1 52 Yes
Personnel Building Poor 24.5 2 62 No
Bonderson Building Poor 22.6 3 33 No
EDD Annex Poor 16.5 4 33 Yes
Jesse M. Unruh Building Poor 16.4 5 87 Yes
Gregory Bateson Building Poor 15.7 6 35 Yes
Justice Building Poor 14.5 7 34 No
EDD Headquarters Poor 14.1 8 61 Yes
Blue Anchor Building Poor 10.6 9 84 Yes
California Energy Commission Building Fair 8.0 10 34 Yes
FTB Phase I Fair 6.0 11 32 No
Board of Equalization Headquarters Building Fair 5.8 12 24 Yes
Library and Courts II Building Fair 5.0 13 22 No
Secretary of State/Archives Building Good 4.6 14 21 No
Agriculture Building Good 3.7 15 80 No
FTB Phase II Good 3.0 16 24 No
Attorney General Building Good 2.4 17 21 No
Buildings and Grounds Headquarters Good 2.4 18 23 No
East End Complex Block 225 Good 1.7 19 14 No
Stanley Mosk Library and Courts Building Good 1.0 20 88 No
Campbell Building—Office of Emergency Services Good 0.9 21 14 No
Office Building 8 Good 0.4 22 47 No
Office Building 9 Good 0.4 23 47 No
FTB Phase III Good 0.2 24 11 No
East End Complex Block 171 Good 0.2 25 13 No
East End Complex Block 172 Good 0.2 26 13 No
Rehabilitation Building (OB10) Good 0.2 27 66 No
East End Block 174 Good 0.1 28 13 No
East End Block 173 Good 0.1 29 13 No
a
Sacramento Assessment Report did not include buildings that were not considered to be suitable or available as typical office space, such as the Food and Agriculture Annex,
the State Printing Plant, and the State Capitol Building and Annex.
EDD = Employment Development Department and FTB = Franchise Tax Board.
www.lao.ca.gov Legislative Analyst’s Office 17
AN LAO REPORT
interrelated nature of the projects in the strategy, constructed on Block 204, which is owned by the
these types of changes to initial projects have the state. This change in project delivery method and
potential to alter the schedule and associated costs location is anticipated to cost at least an additional
of other projects in the strategy. $70 million over the original rough estimate of
Cost of Strategy Unclear, but Could Total $530 million because there will be additional project
Almost $3 Billion. As previously indicated, the management costs and a longer construction period.
administration has not provided the Legislature The administration also indicates that it may increase
with a cost estimate for the strategy. Additionally, the size of the O Street Building, which would almost
it has failed to define the scope of each of the certainly increase construction costs.
projects included in the strategy, which makes it Strategy Has Ambitious Timeline. The strategy
difficult to develop an independent cost estimate. proposes to complete 11 state office buildings
However, based on the best information available, projects (including both the EDD Headquarters
we estimate that the administration’s strategy could and Annex) within the ten-year planning window,
cost a total of almost $3 billion. This estimate is as shown in Figure 9. Most of the individual
based on the conceptual costs for new buildings construction projects are anticipated to be
provided in the administration’s 2016-17 budget completed in four or five years from start to finish.
proposal and the Office Planning Study. It also This timeline is significantly faster than other state
incorporates cost estimates for building renovations building projects. While DGS has not initiated the
based on the ten-year facility needs identified in the construction or major renovation of any state office
Sacramento Assessment Report. (We augmented buildings over the past ten years, it has generally
the costs identified in the Sacramento Assessment taken the department at least six years to complete
Report by about 50 percent to account for various new state office building and major renovation
costs that were not included in the report, such projects in recent decades.
as labor and project management costs.) We The relatively short time frame for the
note that it is possible that the actual costs could projects in the strategy leaves little additional
be different from our estimates. For example, time for contingencies once a project is initiated.
the administration could propose to undertake To the extent that the administration encounters
different—and in some cases possibly more unanticipated circumstances that create project
significant—renovations than the ten-year facility delays—such as unanticipated site conditions—it is
needs we assume. unlikely that these delays could be accommodated
Additionally, this $3 billion estimate includes the without making changes to a project’s schedule.
$1.3 billion already approved in 2016-17 for the initial There are also early signs that schedule changes
three projects. To the extent that there are changes are occurring. Specifically, the administration
to the costs of these projects, it would also affect the indicates that the change to the location of the new
overall cost of the strategy. There are some initial Resources Building is expected to shift the schedule
indications that the costs of these buildings will grow. for the project back by more than a year compared
Specifically, the new Resources Building and O Street to the timeline outlined in the strategy. As this
Building are already undergoing revisions that are project and other projects progress and their scopes
anticipated to increase costs. The new Resources are further refined, there is risk that there could
Building was originally envisioned as a lease-purchase be other changes that could affect timelines and
on private property, but is now planned to be potentially associated costs.
18 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
Project Delays Would Likely Have Cascading Building and the Unruh Building. This is because
Effects. The interrelation between the different those construction projects will not be able to start
projects in the strategy means that delays that affect until the new building is constructed and staff can
one project would likely have sequential effects on be relocated into it. Additionally, to the extent that
other projects. For example, the one-year delay to the the delay affects the timeline for renovating the
construction of the new Resources Building would existing Resources Building and Unruh Building, it
affect the timelines of the other projects that are would also affect projects that are connected to those
connected to the new Resources Building project— projects—such as the EDD Headquarters and Annex
such as the renovations of the existing Resources Buildings and the Energy Commission Building.
Figure 9
Schedule of Major Activities for Projects Identified in Sequencing Plan
Project 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26
Consultant Lease Construction Construction
Build New
Selection Execution and Move In
Resources and
Buildinga
Construction
Consultant PC and Design-Build Construction Construction
Replace
Selection Award to and Existing and Move In
O Street and CEQA Design- Building
Building Builder Demolition
Consultant PC and PC and Design-Build Construction Construction
Replace Selection Award to Existing and Move In
Printing Plant and CEQA Design- Building
Builder Demolition
Consultant PC and Design-Build Construction Construction Construction
Renovate
Selection and Award to and Move In
Resources CEQA Design-
Building Builder
Consultant PC and Design-Build Construction Construction
Renovate Selection Award to and and Move In
Bateson and CEQA Design- Construction
Building Builder
Consultant PC and Design-Build Construction Construction
Renovate Selection Award to and and Move In
Unruh Building and CEQA Design- Construction
Builder
Consultant PC and Design-Build Construction Construction
Renovate Selection Award to and Move In
BOE Building and CEQA Design-
Builder
Consultant PC and Design-Build Construction Construction
Renovate EDD Selection Award to and Move In
HQ and Annex and CEQA Design-
Building Builder
Consultant PC and Design-Build Construction Construction
Renovate
Selection Award to and Move In
Blue Anchor and CEQA Design-
Building Builder
Consultant PC and Design-Build Construction
Renovate Selection Award to
CEC Building and CEQA Design-
Builder
aAfter the release of the Sequencing Plan, the administration modified the proposed delivery method to design-build. It now estimates that the
project will be delayed by a year and a half. This could also potentially affect the timeline of some additional projects.
CEQA = California Environmental Quality Act; PC = Performance Criteria; BOE = Board of Equalization; EDD = Employment Development
Department; HQ = Headquarters; and CEC = California Energy Commission.
www.lao.ca.gov Legislative Analyst’s Office 19
AN LAO REPORT
Existing SPIF Process Is Problematic projects. We also anticipate that any such delays
For Future Projects would not necessarily increase the real costs of
projects. This is because, in recent years, the cost of
The $1.3 billion provided in the 2016-17 budget
constructing buildings has increased at roughly the
package was deposited into the continuously
same rate as overall inflation.
appropriated SPIF. The administration indicates that
Rationale Is Particularly Weak For Future
it plans to continue to use the SPIF process for future
Projects. We find that the administration’s rationale
projects. However, as we discuss below, the rationale
for using a continuous appropriation—that the
for using the SPIF process—that it would result in a
traditional budget process could create potential
faster project timeline and thus reduce costs—is not
project delays and associated costs—is particularly
compelling, particularly for future projects. We also
weak for most future projects in the strategy.
find that the continuous appropriation that is part of
This is because the timing of the construction of
the existing SPIF process greatly reduces legislative
future projects is largely dictated by the timing of
oversight and that the notification process, while
the completion of the construction of the projects
helpful, does not serve as an adequate replacement
before them. For example, the renovation of the
for the traditional capital outlay process for future
Bateson Building cannot begin before its staff are
projects. We further find that the weaknesses of
moved into the new Resources Building. Under
the SPIF process are magnified with the addition of
the administration’s strategy, it does not anticipate
more funds.
beginning any initial planning activities for the
Rationale for Continuous Appropriation Is
renovation of the Bateson Building, including
Not Compelling. The administration’s rationale
any work to select consultants to develop
for the Legislature providing continuous
performance criteria, until 2018-19. However, if the
appropriations for projects is that it will enable
administration was concerned about the timing of
the state to complete projects faster, since project
this project, it could start these activities in 2017-18.
schedules will not have to align with the state
This would provide the administration with an
budget process. The administration maintains that
additional fiscal year to complete them without
a continuous appropriation allows it to proceed
affecting the construction timeline.
with projects without having to wait for legislative
Continued Use of Current SPIF Process
approval at the typical points in a project’s life
Greatly Reduces Legislative Oversight. We also
cycle. The administration further assumes that the
find that the use of the SPIF process for future
longer time frame that could result from relying on
projects would greatly reduce legislative oversight.
the typical capital outlay approval process would
In place of the annual budget process, the SPIF
result in additional project costs. However, the
requires quarterly reports and various notifications.
traditional capital budget process need not delay
We find that the reports and notifications are likely
projects significantly. Notably, a key reason for the
to include some important information to help the
administration to have a well-developed strategy
Legislature monitor projects at key project phases.
is that it would enable the state to coordinate the
In our view, however, the process does not serve as
timing of projects with the budget process, thus
adequate replacement for the typical capital outlay
avoiding any potential delays. Even if projects were
budget process, for a few reasons.
not well-coordinated with the budget process, any
delay would likely not be substantial given the • First, the notification process through
typical multiyear timeline for large construction the JLBC provides the Legislature with
20 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
significantly less time to review proposed For example, a COBCP typically includes
projects than the approval process through a narrative describing the justification for
the traditional capital outlay process. The the project. It also includes an evaluation of
JLBC review period is as little as 20 days in the other available alternatives. This type
some cases—far less than is necessary to of information is not a required part of the
complete a thorough evaluation of a large SPIF notifications, but would be valuable
project. to assist the Legislature in determining
whether the administration’s proposals
• Second, the notification process is
make sense.
less transparent to the public than the
Weaknesses of SPIF Magnified With
traditional capital outlay process, which
Additional Funding. The weaknesses of the
includes public hearings that enable the
existing SPIF process would be magnified if
Legislature to ask questions and the public
additional funds are added to the account in the
to provide input. For this reason, the JLBC
future. The statute governing the SPIF provides the
notification process is typically reserved
administration with the discretion to establish and
for minor, midyear changes to the budget
fund new projects with JLBC notification rather
rather than substantial actions such as the
than legislative approval. As the monies in the
approval of new projects costing many
fund increase, the potential for the administration
millions of dollars.
to exercise this authority to fund new projects not
• Third, the notification process does not envisioned by the Legislature also increases. For
require the same level of information that this reason, it is particularly problematic to add
would typically be required for a capital funding to the SPIF with its current authority for
outlay budget change proposal (COBCP). additional projects in the future.
LAO RECOMMENDATIONS
Based on our assessment, we make several $1.3 billion approved in 2016-17 through the
recommendations to help guide the Legislature use of hearings at key points in project life
as it faces key decisions points related to the cycles. Such hearings would help improve
administration’s strategy: transparency and ensure that funds are spent
consistent with legislative priorities.
• First, we recommend that the Legislature
direct the administration to provide
• Third, we recommend that any future
additional information and a robust
funding provided for state office building
analysis that will allow the Legislature to
projects go through the typical budget
assess if the strategy represents the best
process rather than a continuous
approach available to address aging state
appropriation under the current SPIF
office buildings.
process. Doing so would make it easier for
the Legislature to provide robust oversight
• Second, we recommend that the Legislature
over the administration’s ambitious strategy.
closely monitor the expenditure of the
www.lao.ca.gov Legislative Analyst’s Office 21
AN LAO REPORT
Require More Analysis of Strategy analysis should provide a clear description of the
Prior to Providing Additional Funds value of the benefits provided and why they are
important to justifying the strategy. Our analysis
The Legislature is likely to receive proposals
suggests that the administration’s strategy does not
requesting additional funding—likely totaling over
appear to make sense based solely on one of the
a billion dollars—for state office building projects
benefits that is most easy to quantify—the reduced
in Sacramento in the coming years. In order to
lease costs. Thus, it is particularly important for
help the Legislature in determining the approach
the administration to clearly articulate any other
it prefers to take to address these infrastructure
benefits provided by the strategy in order to make
issues, we recommend directing the administration
the case that it is worthwhile.
to provide an analysis of the overall strategy that
Require Analysis of Alternatives. We also
includes key information.
recommend that the Legislature direct the
Require Analysis of Costs and Benefits. Before
administration to provide an analysis of available
considering any new projects, we recommend
alternatives to its strategy. We think that the
that the Legislature direct the administration to
administration’s analysis should explore two main
provide information on the costs and benefits of the
types of alternatives: (1) different mixes of buildings
overall strategy. This information should include
to be addressed and (2) other available approaches
the anticipated costs of the strategy broken out
to address these buildings.
by individual project. A complete understanding
First, the administration’s analysis should
of these costs—even if it is rough—is critical to
evaluate alternative strategies that include a
enabling the Legislature to assess whether it is
different mix of buildings to address. Figure 10
comfortable with the financial commitment that
provides some examples of the types of alternative
is associated with implementing the strategy as
options that the administration could evaluate.
a whole. Furthermore, this information would
We also include rough cost estimates of these
inform decisions on individual future projects.
potential options. These estimates are intended to
This is because, given the interrelated nature of
provide a sense of the general scale of the potential
the individual projects in the strategy, legislative
choices available to the Legislature. (We note
decisions on one project affect the feasibility of
that these estimates are imprecise given the lack
other projects.
of scope and cost information provided by the
Additionally, the information provided by the
administration on these projects.) These options
administration should include the articulation
highlight that there are likely to be trade-offs in
of the benefits associated with the strategy and a
pursuing a different mix of buildings. For example,
quantification of these benefits, as feasible. Some of
the Legislature could choose not to fund any
the potential benefits of the strategy may be more
additional projects beyond those already approved.
easily quantified than others. For example, some
While this option would reduce construction
benefits—such as reduced lease costs—are readily
costs by roughly $1.4 billion compared to the
quantifiable. Estimates of the magnitude of these
administration’s strategy, it would also fail to
benefits should be included in the administration’s
directly address any of the existing state buildings
analysis. Other benefits—such as the value of
identified in the Sacramento Assessment Report.
having modern office spaces for state employees—
Alternatively, in addition to the three priority
may be very challenging if not impossible to fully
projects, the Legislature could choose to renovate
quantify. In these cases, the administration’s
22 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
some combination of the highest-need buildings, Second, the administration should evaluate
as identified in the Sacramento Assessment Report. whether other available approaches to addressing
For example, it could choose to renovate the three these office buildings—such as buying existing
highest-need buildings in Sacramento, consistent privately owned office buildings or leasing
with Chapter 451, or to address all the buildings additional space—are more cost-effective. For
identified in “poor” condition in the Sacramento example, as described previously, the estimated
Assessment Report. These options would both costs of building new office buildings are high
result in lower costs than the strategy proposed by compared to the costs of the state’s existing leases
the administration, but they also would total less and compared to the cost of purchasing existing
new and renovated state-owned office space. While buildings. While there would likely be benefits
not shown in the figure, another alternative would to constructing a new building rather than
be to include high-need buildings in other parts of purchasing or leasing an existing building—such
the state as identified in the Statewide Assessment as additional flexibility in designing the building—
Report. these benefits might be outweighed in some cases
Figure 10
Estimated Costs of Some Possible Optionsa
(Dollars in Millions)
Possible Options
Priority
Sacramento Entire Projects and Priority
Condition Sequencing Priority Three Poorest Projects and
Buildings Ranking Plan Projects Condition Poor Condition
Proposed in Sequencing Plan
Build new Resources Buildingb N/A $600 $600 $600 $600
Replace O Street Building N/A 225 225 225 225
Renovate or replace Capitol Annex/LOB II N/A 580 580 580 580
Replace Printing Plantc N/A 955 — — —
Renovate Resources Building 1 230 — 230 230
Renovate Bateson Building 6 45 — — 45
Renovate Unruh Building 5 25 — — 25
Renovate BOE Building 12 55 — — —
Renovate EDD Headquarters and Annex 4, 8 75 — — 75
Renovate Blue Anchor Building 9 5 — — 5
Renovate CEC Building 10 10 — — —
Not Proposed in Sequencing Plan — —
Renovate Personnel 2 — — 15 15
Renovate Bonderson 3 — — 20 20
Renovate Justice 7 — — — 40
Total Estimated Costs $2,805 $1,405 $1,670 $1,860
Total amount of new square footage, in thousandsd 1,900 900 900 900
Total amount of renovated square footage, in thousandsd 2,000 — 700 2,000
a
Assumes renovations will include the scope of work shown as the ten-year capital needs in the Assessment Report. About 50 percent was added to the estimates of the cost of
this work to account for expenses not included in this report.
b
Includes $70 million in additional costs compared to the original rough estimate due to revised project delivery method and building location.
c
Estimate is based on conceptual cost estimate provided in the Office Planning Study.
d
Capitol Annex/LOB II not listed in either new or renovated space, since plan for building is unknown.
LOB = Legislative Office Building; BOE = Board of Equalization; EDD = Employment Development Department; and CEC = California Energy Commission.
www.lao.ca.gov Legislative Analyst’s Office 23
AN LAO REPORT
by the additional costs. Thus, it is important would not serve all the purposes of the traditional
for the administration to provide this analysis budget process, it would provide some of the
to demonstrate that its preferred approach to benefits of this process. For example, it would
addressing buildings is the best available one. provide the Legislature with an opportunity to
review details of the projects in a public setting.
Closely Monitor Expenditure of
Such a hearing would also enable the Legislature
$1.3 Billion Already Approved
to address questions to the administration to
The scope and details of the two state building ensure that it is comfortable with them. This public
projects initially approved—the new Resources process is particularly important because based on
Building and O Street Building—are not well our discussions with the administration, we expect
defined. Furthermore, because the projects are that there will be notable changes to aspects of the
funded out of the SPIF, there is a greater chance projects—such as location and costs—compared
that these projects could change over time without to what the Legislature envisioned when the
legislative approval. Accordingly, it is important projects were funded. Additionally, the public
for the Legislature to maintain close oversight process is especially important because, based on
over these projects to ensure that funds are spent the preliminary cost estimates that are available,
in a manner consistent with its priorities. As such, these are expensive projects. Thus, these hearings
we recommend that the Legislature hold public would provide the Legislature with an opportunity
hearings—such as through the relevant budget to better understand the reasons for their apparent
subcommittees—at critical project decision points. high costs and ensure that it is still comfortable
Hold Hearings When Project Scope and Cost moving forward with them.
Are Defined. We recommend that the Legislature Hold Hearings When Project Scope and
hold a hearing when the scope and cost of each of Cost Change Substantially. We also recommend
the two new state building projects are defined. that the Legislature hold a hearing when the
Generally, scope and cost of capital outlay projects scope or cost of the two state office building
are defined when the Legislature initially approves projects change significantly. Specifically, given
the project—for example, when the Legislature the size of these projects, we recommend that
approves funding for performance criteria. the Legislature consider holding a hearing if
However, unlike typical capital outlay projects, the cost of an individual project changes by
the scope and cost of these projects were not well more than 10 percent. (We note that, although
defined in the administration’s proposal. Instead, there is some potential ambiguity in the law, the
the administration is currently in the process of administration has indicated to us that it interprets
solidifying their scope and cost, a process that we the law to require a new legislative appropriation
expect will be completed in early 2017. At that time, if a SPIF-funded project has total cost increases
we expect the administration to notify the JLBC. exceeding 20 percent.) Similarly, we recommend
When the JLBC receives these notifications, a hearing if key details about one of these projects
we recommend that the Legislature conduct a change—such as its location or proposed use. These
thorough review of them, including holding a hearings would provide the Legislature with a
public hearing. While a public hearing upon the valuable opportunity to ask the administration to
establishment of scope and cost of these projects articulate the reasons for changes in scope or cost.
24 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
Without such hearings, the administration could process, we recommend that the Legislature direct
make substantial changes to these projects without the administration to provide individual COBCPs,
the public review process provided by a hearing. or equivalent, for any future projects. Each of these
COBCPs should provide the type of information
Avoid Use of Current SPIF Process
that is typically included in such proposals,
for Any New Projects
including:
Rely on Traditional Budget Process. If the
• A description of the project scope and its
administration pursues its strategy as currently
justification.
envisioned, the Legislature should expect to receive
additional funding requests as soon as 2017-18. • The estimated project cost (by project
The administration indicates that it anticipates phase), funding source, timeline, and
continuing to use the SPIF process—including delivery approach.
its continuous appropriation—to fund additional
• An evaluation of project alternatives and a
projects. We strongly recommend that the
description of why the proposed approach
Legislature avoid putting additional funding into a
was selected over the alternatives.
continuously appropriated fund, including the SPIF
as currently structured. Instead, if the Legislature is This information should be sufficiently detailed
comfortable providing additional funding for state and reliable to enable the Legislature to understand
office buildings in the Sacramento area in future what it would be funding and to evaluate the
years, we recommend that it approve them through merits of the projects. This information is critical
the state budget process. The budget process in order to enable the Legislature to evaluate
provides the Legislature with the ability to use its whether cost estimates are reasonable and that
constitutionally granted appropriation authority to each of the proposed projects is the best way to
ensure that state funds are directed to its highest accomplish the goals associated with that building.
priorities and are spent with adequate legislative This information would also facilitate the future
oversight and accountability. Furthermore, while oversight of any projects that are subsequently
the administration’s rationale is that this approach approved by setting clear expectations of the initial
is necessary to expedite projects, this argument project costs, scope, and other critical project
generally is not compelling for future projects. details. We note that the administration failed
Such projects are more heavily constrained by the to provide this type of detailed information on
progress of the recently approved projects than by each of the three initial projects it proposed in
the time required for approval of proposals through 2016-17. This failure made it more difficult for the
the traditional budget process. Legislature to assess these projects.
Require Detailed Analysis and Information
in Future Proposals. Consistent with the typical
CONCLUSION
We expect that in the near future the $1 billion—for additional state office buildings.
administration will come forward with requests We anticipate that, absent clear direction from
for more funding—likely totaling more than the Legislature, the administration may submit
www.lao.ca.gov Legislative Analyst’s Office 25
AN LAO REPORT
proposals that—like its proposal in 2016-17—fail to process that facilitates more robust legislative
include key information and analyses. Additionally, oversight and control than the SPIF process.
we expect that the administration might continue Finally, since the SPIF process governs the funding
to propose using the SPIF process, which reduces for the state building projects funded in 2016-17,
legislative oversight and is particularly flawed we recommend that the Legislature use other tools
for future projects. Thus, we strongly encourage at its disposal—such as legislative hearings—to
the Legislature to provide clear direction to the closely monitor them. While these tools are not a
administration that it expects more complete replacement for the traditional budget process, they
information and a robust analysis to justify any can provide some additional legislative oversight
future project or funding proposals. Furthermore, that can help hold the administration accountable
we also strongly encourage the Legislature to and ensure that funds are used consistent with
make it clear to the administration that any future legislative priorities.
funding that is provided should be subject to a
26 Legislative Analyst’s Office www.lao.ca.gov
AN LAO REPORT
www.lao.ca.gov Legislative Analyst’s Office 27
AN LAO REPORT
LAO Publications
This report was prepared by Helen Kerstein and reviewed by Brian Brown. The Legislative Analyst’s Office (LAO) is a
nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service,
are available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000,
Sacramento, CA 95814.
28 Legislative Analyst’s Office www.lao.ca.gov