Evaluation of the Statewide
Project Management Office
MAC TAYLOR
LEGISLATIVE ANALYST
DECEMBER 7, 2017
analysis full
gutter
AN LAO REPORT
LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
Executive Summary
Project Management Office (PMO). As part of the 2014-15 Budget Act, the Legislature approved
a Governor’s proposal to establish a centralized project management office within the California
Department of Technology (CDT) to improve the day-to-day management of information technology (IT)
projects and, eventually, overall IT project outcomes across the state. The PMO would address critical
state deficiencies in project management by consolidating a team of experienced project management
professionals within CDT. These project managers would provide their services to state IT projects as
needed. With support from the Legislature, CDT envisioned that the PMO would eventually manage
some of the state’s largest, most complex, and high-costing projects. Given that the PMO has been
directly involved with managing state IT projects for two years, we recently evaluated the performance of
the PMO to assess whether the office is meeting—or on track to meet—its original objectives.
Analysis of the PMO to Date. Thus far, six state IT projects have sought direct project management
services from the PMO. For the first six projects, the PMO selected projects likely to progress smoothly,
preferring smaller, less complex projects. This allowed the PMO to test the potential of the centralized
project management approach and build the reputation and capacity of the office gradually, with the
intention of scaling up to larger, more complex projects once the office was more established. Based on
our interviews with the six departments utilizing the direct PMO services, we found that the PMO was a
valuable asset to projects in need of project management services.
Significant Recent Developments. Although the PMO has been operating largely as intended with a
high level of satisfaction from departments, during our evaluation we learned of two recent developments
that significantly impact the operation of the PMO going forward. First, a reorganization of CDT creates a
potential conflict of interest as it places CDT oversight and project management responsibilities under the
same chief deputy director. Additionally, CDT implemented a policy change that significantly reduces the
number and complexity of IT projects eligible for PMO services.
LAO Findings and Recommendations. The Legislature approved the establishment of the PMO
with the expectation that the office would meet a critical need in the state for project management
expertise and help the state avoid the high-profile IT failures of the past. We found that the PMO was
showing success towards meeting the original legislative intent by first establishing the internal processes
and capacity to ultimately scale up to larger, more complex projects. However, under the recent policy
change, the PMO will now primarily serve smaller, low-complexity projects, which is not in line with the
Legislature’s intent when it established the office. Given recent developments, we have concerns about
the path forward for the PMO and its ability to succeed and meet the Legislature’s original expectations.
In light of our positive findings of the PMO’s operation under the original eligibility policy, we make the
following recommendations:
• Reassert PMO’s Mission. We recommend the Legislature reassert its original objectives for the
PMO in statute. Codifying the objectives of the office would provide CDT with legislative guidance
for the operation of the office and ensure that the goals and functions of the office remain aligned
with legislative intent.
www.lao.ca.gov 1
analysis full
gutter
AN LAO REPORT
• Establish Firewall. We recommend the Legislature require in statute that CDT maintain an
organizational “firewall” between its project management and oversight responsibilities. Requiring a
firewall would help address and mitigate potential conflicts between the two responsibilities.
• Express Intent Regarding PMO’s Independence. We recommend that the Legislature express
intent in statute that it expects the PMO to operate independently and serve in the best interests of
the projects. This would ease sponsoring departments’ concerns of inappropriate and unnecessary
information sharing between the PMO and CDT oversight and cultivate an open pathway of
communication between the PMO and sponsoring departments.
Additionally, we note that even with the continuation of the PMO as originally envisioned, there is still
room for departments with the capacity to manage their own projects to do so.
2 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
INTRODUCTION
As part of the 2014-15 Budget Act, the Legislature Given that the PMO has been directly involved
approved a Governor’s proposal to establish a with managing state IT projects for two years, we
centralized project management office within the recently evaluated the performance of the PMO to
California Department of Technology (CDT) to improve assess whether the office is meeting—or on track to
the day-to-day management of Information technology meet—its original objectives. In this report, we provide
(IT) projects and, eventually, overall IT project outcomes background regarding the objectives and operations
across the state. The Project Management Office (PMO) of the PMO, detail our findings in evaluating the PMO,
would address critical state deficiencies in project introduce two significant recent developments and
management by consolidating a team of experienced their impacts on the PMO, and make associated
project management professionals within CDT. These recommendations on how the Legislature should
project managers would provide their services to proceed to better align the office with the original
state IT projects as needed. With support from the legislative intent.
Legislature, CDT envisioned that the PMO would
eventually manage some of the state’s largest, most
complex, and high-costing projects.
BACKGROUND
What Is IT Project Management? IT project and Funding Process, to learn about CDT’s efforts
management is the application of skills, tools, and to address another major contributor to project
techniques to an IT project so that the project is challenges—poor project planning—by developing and
completed on time, within budget, and fulfilling its implementing a new project approval process.)
objectives. Project managers are the people trained Historical State Project Management
with the skill set to keep projects on track and address Structure. In the past, the state has primarily relied
issues when problems arise. on the individual departments to manage their own
State Challenges Implementing IT Projects. IT projects—using state staff, contractors, or a
Historically, the state has experienced considerable combination of the two. Under such a decentralized
challenges implementing IT projects. Despite some approach, project managers are expected to develop
successes, various high-profile state IT project failures, and implement project management processes and
resulting in either project suspension or termination, practices, and create a team to support the project
have received extensive legislative and media attention. implementation process. One of the primary challenges
In other cases, projects were ultimately completed, but of utilizing a decentralized project management
only after significant cost overruns and multiyear delays. approach can be the lack of experienced project
Given recent failures, the Legislature and administration management staff at the departmental level. Because
have expressed strong interest in reforming existing smaller departments generally undertake IT projects
processes to enhance the likelihood of IT project infrequently, these departments typically acquire staff
success. An internal review by CDT—the state’s central resources for project management on an as-needed,
IT organization—revealed that the challenges commonly case-by-case basis. These project managers also may
experienced by troubled projects largely connect back have a limited understanding of project management
to deficiencies in the project management process, processes and practices, as they may be unable to
which often fails to implement best practices to ensure draw from lessons learned in previous projects. There
that projects remain on track and are completed are some exceptions to this lack of experienced
successfully. (Please refer to our February 2017 report, project management staff at the departmental level.
The 2017-18 Budget: The New IT Project Approval For instance, some larger departments, such as the
www.lao.ca.gov 3
analysis full
gutter
AN LAO REPORT
Franchise Tax Board, often simultaneously manage management, whereby individual departments assume
multiple IT projects of high complexity and have full responsibility of managing their own projects. CDT
demonstrated strong project management capacity. envisioned that the PMO would eventually manage
Nevertheless, inadequate project management some of the state’s largest, most complex, high-cost
expertise remains a challenge for most other projects.
departments. Primary PMO Services. To achieve its objectives,
The Statewide Project Management Office Is the PMO has two primary functions: (1) to provide
Created. To address state deficiencies in project direct project management services to departments not
management, in 2014-15 the Governor proposed capable of managing projects independently (referred to
establishing a centralized PMO within CDT. The PMO as direct services for purposes of this report) and (2) to
would create a team of skilled project management develop project management tools to indirectly support
professionals, who would provide project management departments in need of some assistance (referred
services to departments that are not equipped to to as indirect services for purposes of this report).
handle this responsibility independently. Specifically, Departments may engage the PMO for direct services
in 2014-15 the Governor requested two positions through three pathways: (1) the department undertaking
and $208,000 (General Fund) to establish the initial the IT project (known as the sponsoring department)
elements of the PMO. Subsequently, the Governor’s can request PMO services, (2) CDT can require PMO
2015-16 budget requested 11 additional positions engagement as a condition of project approval, and
(13 positions total) and $1.5 million (special fund) (3) CDT can intervene to provide PMO services for
to continue implementation activities—including at-risk projects under development.
establishing standards, tools, and guidelines, and to Regardless of the pathway for direct services, PMO
begin providing project management services to three offers three distinct service models based on the
projects. The Legislature adopted the Governor’s sponsoring department’s existing capacity to manage
proposals and in 2015-16 the PMO began managing IT projects. These service models, in ascending order
state IT projects. of degree of PMO engagement, include: (1) short-term
Objectives of the PMO. Specific objectives consulting services, whereby the PMO provides
envisioned for the PMO in the Governor’s budget assistance on specific issues (such as testing) to
proposal included: (1) successfully managing a wide support the sponsoring department’s existing project
range of projects, including large, high-complexity manager; (2) providing the department a designated
projects, for departments lacking capacity and/or CDT project manager, who would be absorbed into
expertise; (2) recruiting and retaining a team of qualified, and work alongside the sponsoring department’s
trained project management professionals to allocate project team to manage the project; and (3) providing
to projects as needed; and (3) establishing and sharing a project manager and a full project management team
best practices and project management standards to assume day-to-day management of the project in
that better equip departments to manage their own lieu of the sponsoring department’s staff resources.
projects successfully. The potential benefits of creating (Our analysis focuses on the extended support CDT
a centralized project management office include: provides in the latter two service models. Consequently,
making information sharing among project managers hereafter consulting services are excluded when we
more feasible, allowing IT project-related training to refer to direct services.) Project managers from the
be applied in a more uniform fashion, and allowing PMO remain employees of CDT but are loaned to
the staff resources utilized for project management to sponsoring departments. Which service model is
become experienced professionals who are capable selected, and the terms of the direct services to be
of managing complex projects—all of which may provided by the PMO, are set in a memorandum of
better position projects to succeed. While the PMO understanding between CDT and the sponsoring
would attempt to address project management department. Following completion of their project work,
deficiencies on projects engaged with the office, IT the project manager returns to the PMO to be allocated
projects not engaged with the PMO would continue to another project in need of services.
to operate under the decentralized model of project
4 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
The PMO also provides indirect project management under two different branches of the department, each
services. The office develops and shares general project with its own chief deputy director. The idea behind
management tools—including frameworks, templates, the firewall is that it would separate CDT’s oversight
and trainings—that are available to all departments. and project management responsibilities, allowing it to
These resources allow departments to build internal continue performing its oversight functions even with
project management expertise and positions them to the PMO responsibilities. As the two functions are still
more effectively manage projects independently. part of the department, this design does not eliminate—
Organizational Firewall Between CDT’s Oversight but rather mitigates—possible conflicts of interest.
and Project Management Roles Is Created. CDT Current PMO Project Portfolio. Although originally
has oversight responsibilities over IT projects as part approved by the Legislature to provide direct project
of its control agency functions—chiefly to evaluate managements services to three projects, CDT
the management of IT projects and make associated determined that the PMO worked well enough to
recommendations. Establishing the PMO created expand direct services to three additional projects
the possibility that CDT could be evaluating the in 2016. Four of the six projects range in estimated
effectiveness of its own project management, thereby project cost from $4 million to $7 million. The smallest
creating a potential conflict of interest between CDT’s project is estimated to cost $165,000, while the largest
current oversight responsibilities and its proposed is estimated to cost $69.1 million. Figure 2 (see next
project management responsibilities. As shown in page) identifies key characteristics of the six projects
Figure 1, the Governor’s proposal included a strategy currently receiving direct PMO services.
for preventing potential conflicts by creating a “firewall” These six projects share common characteristics,
between CDT’s oversight and project management particularly related to the circumstances of PMO
responsibilities. The proposed, and ultimately engagement. Thus far, all projects have independently
implemented, solution placed these two functions requested direct services (with the exception of one
Figure 1
California Department of Technology’s Organizational Firewall
Between Project Management and Oversight Rolesa
Director of Technology
Other Offices Policy Operations
(Legal Services, Chief Deputy Director Chief Deputy Director
External Affairs,
IT Services)
Statewide Technology Administration Office of Technology
Enterprise Solutions
Procurement Division Services
Office of Information State Geographic Broadband/Digital
Project Oversight
Security Information Literacy
Office of Professional
Customer Delivery
Development
Project Management Office
a The organization chart has been simplified to highlight only the aspects relevant for this report.
IT = information technology.
www.lao.ca.gov 5
analysis full
gutter
AN LAO REPORT
Figure 2
Current Project Portfolio for Statewide Project Management Office
(In Millions)
Estimated Estimated
Completion Project
Sponsor Department Project Project Description Datea Cost
Department of Conservation Well Statewide Tracking and Well management system to meet state June 2020 $69.1
Reporting (WellSTAR) and federal requirements
Department of Fair California Civil Rights System Case management system for October 2017 6.5
Employment and Housing (CCRS) discrimination complaints
Commission on Teacher Streamline and Strengthen the Data collection system for CTC June 2017b 6.5
Credentialing (CTC) Accreditation Process (SSAP) accreditation process
California Workforce Cross-System Analytics and Data repository and analytics platform December 2018 4.2
Development Board Assessment for Learning and for workforce development activities
Skills Attainment (CAAL-Skills)
Department of Insurance Fraud Data Analytics System Analytics tools to identify fraud May 2018 4.1
(FDAS)
Office of Traffic Safety Grant Electronic Management Automating paper-based grants January 2018 0.2
System (GEMS) application process
a
Estimated completion date as of summer 2017.
b
Actual project completion date.
project that was encouraged by CDT to use PMO approach and build the reputation and capacity of
services). CDT has not required direct PMO services the office gradually, with the intention of scaling up to
as a strict condition of project approval or intervened larger, more complex projects once the office was more
to provide services due to project underperformance, established.
although CDT originally envisioned both of these PMO Funding Structure. Most of CDT is funded
scenarios for engaging the PMO. Additionally, the office through the Technology Services Revolving Fund
has yet to exercise the highest level of engagement, (TSRF), which collects fees paid by departments for
whereby the PMO provides a full project management services provided by CDT, including those charged
team to assume day-to-day management of the for PMO services. The PMO service rate charged to
project in lieu of the sponsoring department’s staff. a sponsoring department is largely set based on the
All six projects currently receive a designated PMO salary and benefits of the designated project manager,
project manager, who is expected to integrate into while other PMO responsibilities are excluded from the
the department’s project team for the duration of the service rates, including indirect PMO services (such as
project. For the first six projects, the PMO selected the development of frameworks, methodologies, and
projects likely to progress smoothly, preferring smaller, other tools) and various administrative responsibilities.
less complex projects. This allowed the PMO to test The 2017-18 budget provides the PMO with
the potential of the centralized project management 14 positions and $2.5 million (special fund).
6 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
ANALYSIS OF THE PMO TO DATE
We recently evaluated the performance of the PMO In contrast, other departments requesting PMO
to date to assess whether the office is meeting—or services claimed to have the expertise to manage
on track to meet—its original objectives and to better projects independently but temporarily lacked available
understand the strengths and limitations of the PMO, staff. These larger departments had established
as implemented. Specifically, our evaluation focuses on IT project management operations, including their
the direct, rather than consulting and indirect, services own departmental PMO, and were simultaneously
offered by the PMO. For this work, we interviewed managing several projects of varying complexity. These
key staff members of the six sponsoring departments departments turned to CDT’s PMO to provide project
receiving direct PMO services, as well as executive management services on a new project when internal
staff at CDT. Given that the PMO has only been directly IT staff were already fully dedicated to ongoing projects.
involved with managing state IT projects for two years, Without adequate project management, the new project
we acknowledge that the PMO is in the early stages may have experienced delays until resources were
of establishing its capacity and processes as an office, secured, or the department would need to reassign
especially as the PMO is intended to scale up to resources from other projects, potentially jeopardizing
eventually manage larger, more complex projects. As a other project work, or contract for services. Under such
result, this analysis has limitations that we acknowledge circumstances, departments found the PMO helpful
more fully later. Below, we discuss our findings from the in addressing internal capacity deficiencies. These
evaluation of the PMO as the office is operating to date. departments aim to have sufficient internal capacity in
the future to manage their projects independently, but
Departments Had Several
would leverage the PMO should capacity constraints
Motivations for Engaging PMO arise again. (We discuss later why this may change
moving forward.)
Departments Sought PMO Services Due to Lack
Departments Identified Several Benefits of
of Internal Expertise and/or Capacity. According
PMO Over Other Alternatives. Departments largely
to the departments we interviewed, the needs that
prioritized successful project implementation when
motivated department requests for PMO services
considering their options for project management, and
depended on the expertise and capacity of the
viewed PMO services as one option among several—
department’s internal IT operation and the complexity
including using state resources or contracting—to
of the project. We found that departments with less
achieve project success. However, sponsoring
established IT operations requested PMO services to
departments provided several reasons for preferring
address gaps in both expertise and capacity. Because
PMO services:
they take on projects so infrequently, most small
departments, and some larger departments, have
• Perceived Advantage Navigating CDT. Since
limited opportunity and need to develop the internal
PMO project managers are CDT employees,
operations necessary to effectively complete complex
departments believed that using direct services
IT projects. For instance, a smaller department may
from the PMO facilitates smoother navigation
be capable of managing small scale IT projects, such
of CDT processes, including initial project
as hardware replacements or application updates,
approval, procurement, approval of revised
but may lack expertise beyond these routine projects.
project plans, and project oversight. The project
Hence, on the rare occasion when the department
managers would be more familiar with CDT’s
pursues a more significant IT project, they require
processes and help departments manage these
additional project management services to successfully
processes successfully. If challenges were to
complete the project. Many of the departments that
arise, departments believed the PMO project
engaged the PMO because of expertise and capacity
managers could leverage their direct access to
issues anticipate returning to the PMO for direct project
CDT colleagues, as appropriate, to remedy issues
management services in the future for similar reasons.
more expeditiously. Those CDT employees may
www.lao.ca.gov 7
analysis full
gutter
AN LAO REPORT
be more understanding when interacting with a success or failure of state IT projects. Ultimately,
CDT colleague (the project manager assigned to projects managed by the PMO are still the
the project) than with a non-CDT project manager. responsibility of the sponsoring departments.
• Administrative Ease. According to departments, Nevertheless, departments may perceive it
requesting PMO services is less administratively valuable to engage CDT, particularly when they
burdensome than the other available options. For can shift responsibility for project challenges to
example, contracting for project management CDT.
services requires completing the state
procurement process, which may be lengthy PMO Was Positioned to Hire
and result in project delays. Hiring for a new High Quality Project Managers
temporary or permanent position may require
The project managers hired by the PMO came from
formal budget approval. Alternatively, reassigning
a range of backgrounds, including within CDT, from
internal resources is only a viable solution if
other departments, and from the private sector. In
adequate expertise already exists internally and
recruiting, the PMO looked for candidates who were
the reassignment does not result in delays on
certified as project managers, had experience on
other work.
projects of different sizes, and maintained knowledge
• Cost-Effectiveness. For the projects currently
in a variety of project management-related disciplines,
using direct PMO services, PMO rates generally
including organizational change and various software
have ranged from $15,000 to $18,000 per
development models. Below, we outline the tools in
month, depending on the complexity of the
place that have positioned the PMO to recruit high
project. Departments considered these rates
quality project managers and discuss sponsoring
more cost-effective than contracting for project
departments’ experiences with the project managers to
management services, indicating that PMO
date.
service rates were either competitive or lower than
Several Factors Positioned PMO to Recruit
contractors’ rates. As we discuss below, because
Qualified Project Managers. When the PMO was
these rates do not fully reflect CDT’s cost for
initially proposed, we noted that recruiting and retaining
operating the PMO, other fees paid to CDT
qualified project managers would be critical to the
subsidize the operation of the office.
success of the PMO. We stated at the time that while
• Cultivate In-State Expertise. Some
the state would likely continue to have problems
departments’ interest in the PMO was partially
competing with the private sector for qualified IT staff,
driven by an interest in building and retaining
CDT may be better positioned than departments to
project management expertise for the benefit of
recruit and retain staff resources through the PMO
the state. They viewed engaging PMO services
because of the career pathway the office could offer.
as a means to contribute to the state’s long-term
We found that several factors enabled the PMO
project management capacity, as the expertise
to attract, and ultimately hire, experienced project
and experience that the PMO project manager
managers:
developed through the project would remain
in-state. These departments noted that, in • Career Advancement. According to the PMO,
contrast, outside contractors would leave the many project manager candidates viewed the
state after completing their contractual project PMO as an opportunity for career advancement
management responsibilities and take with them by working on high-visibility, complex, and
any added expertise. challenging projects which were not available at
• Sharing Responsibility With CDT. One their previous position. For candidates from the
department noted that its interest in PMO services private sector, the PMO offered an opportunity
was partially motivated by an interest to share to manage projects that could affect the entire
responsibility for any project with CDT. As the state of California, a scale and impact level
state’s central IT organization, this department incomparable to most projects seen in the private
believed CDT should be accountable for the sector. Depending on the department, candidates
8 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
within state government may have reached their project manager a strong asset, as they helped
the top of their professional development, with mitigate project delays and were able to act as a
limited opportunities to work on more complex IT neutral mediator when issues arose. For instance, when
projects. For these candidates, the PMO provided projects involved collaboration across entities—such
the possibility of more challenging and engaging as data sharing across departments or convening
project work that would better leverage their skill teams within the department—and disagreements
set and expertise. Although the PMO intended to arose over project changes or next steps, project
start with smaller projects, the appeal of working managers attempted to resolve the conflict as a neutral
in the future on state projects that were large in party. One department noted that when an unforeseen
scale and intellectually challenging positioned the issue arose, the project manager leveraged his/her
PMO to attract strong candidates. knowledge of the state procurement process to
• Pay Differential for Complex Projects. Through contract with the necessary technical specialists in a
an arrangement between CDT and the California short time frame. Thus far, there has been no turnover
Department of Human Resources, CDT secured of project managers on any of the six projects receiving
a 7.5 percent to 15 percent pay increase, or PMO services.
differential, for project managers working on We note that the project manager selection process
the most complex projects. While none of the may have played a role in the high department
projects currently receiving PMO services qualifies satisfaction with PMO services. Because these were
for the pay differential, the possibility of the pay the first projects the PMO undertook, after initially
differential in the future allowed the PMO to be a screening candidates, the PMO worked collaboratively
competitive employer. (We note that one project with most sponsoring departments to hire candidates
manager initially qualified for the pay differential. considered a good match for the project needs and
However, a reassessment of the project’s department culture. Departments had the opportunity
complexity resulted in an adjustment down and a to review candidate resumes, interview candidates, and
removal of the pay differential.) select their preferred candidate—who would then be
• Job Security. For project managers already hired by the PMO. Through this process, departments
in state government, the PMO was better were able to provide the PMO substantial input on
positioned to provide job security than other project manager selection, which was likely critical in
departments. Typically, IT projects are short-term high department satisfaction with their PMO resource.
endeavors, whereby project managers would
Progress of PMO Projects
find themselves in need of employment after
a project is completed. However, under the Projects Largely Progressing as Expected.
PMO model, project managers are hired into As of June 2017, of the six projects receiving PMO
permanent positions and are assured to receive services, three projects are under development, and
a new project assignment after the previous one the other three projects are in the planning phase. Two
concludes, allowing for continuous work and of the three projects under development are generally
employment without having to apply for jobs in progressing as expected based on the approved
other departments. project plans. The third project noted project delays
largely due to external vendor challenges. Despite
Departments Highly Satisfied With Project
the delays, the department noted that they were
Managers. All of the sponsoring departments that we
pleased with the project manager’s proactive approach
interviewed were highly satisfied with the qualifications
to mitigating any further delays. One department
and performance of their project manager. Project
acknowledged their project manager as the main
managers integrated with department project staff and
reason for the project staying on schedule. There is not
managed daily operations of the project. According to
as much information available to fully assess the three
departments, project managers were able to develop
projects still in the planning phase. However, projects
a working understanding of programmatic needs and
engaged with the PMO during the planning phase may
departmental culture. Several departments considered
find their project manager provides critical support that
www.lao.ca.gov 9
analysis full
gutter
AN LAO REPORT
positions it for success. For example, one department services without growing the office too large and leaving
attributed being farther along in the planning phase PMO staff underutilized during times of lesser demand
than otherwise expected due to the work of the project for their services.
manager.
Alignment With Legislative Intent
Perceived Conflict Between
PMO Operated Largely as Legislature Intended.
CDT’s Oversight and
When the PMO was first proposed, CDT asserted that
Project Management Roles Remained statutory authority for a PMO already existed, citing
statute that broadly laid out the Director of Technology’s
Some Departments Concerned About Adequacy
authority to perform project management activities,
of CDT Firewall. Despite CDT’s organizational firewall,
but the statute was never modified to explicitly lay
some sponsoring departments expressed some
out the role and objectives for a statewide PMO.
concern that a conflict of interest still existed. For
Despite the fact that the PMO was not explicitly
example, there was concern that the PMO project
established in statute, we generally found the PMO
manager would expose the department’s internal
to be operating in line with legislative intent, based
deliberative process to other CDT staff. Departments
on the budget proposal approved by the Legislature.
had concerns that such exposure would result in
The PMO had already expanded direct services from
stricter or more involved oversight than was warranted.
three projects to six projects, and was positioned to
These departments asked their CDT project manager
potentially expand services to larger, more complex
to refrain from sharing any project information, beyond
projects. The office was meeting, if not surpassing,
what was necessary, with other units within CDT,
sponsoring departments’ expectations, both in
including oversight. In effect, these departments
regards to project manager qualifications and project
attempted to strengthen the firewall between the
progress under the CDT project manager. With the
project managers and the rest of CDT to maintain
exception of one project delayed due to external vendor
control over the information given to CDT.
challenges, the remaining five projects are progressing
Additionally, when CDT suggests that a project seek
as expected. Although the PMO encountered some
project management services, sponsoring departments
initial challenges—including limited PMO capacity and
may perceive some pressure to use PMO services
departments’ internal concerns about CDT oversight—
over other options, such as contracting from a third
we found the PMO to be largely meeting or working to
party. Given the authority of CDT over project approval
meet its original objectives.
and oversight, departments may have concerns that
not accepting PMO services, even when not required, PMO May Encounter Future Limitations
would invite a different level of CDT oversight.
Although our analysis thus far indicates a high level
PMO Capacity Limitations of satisfaction with the PMO to date, there are some
significant limitations to these findings, which we
Unable to Fully Meet Demand for Services. The
highlight below.
PMO was unable to fulfill requests for direct services
High Department Satisfaction May Be Difficult to
from at least seven departments, largely because
Maintain. Because a department’s ability to interview
PMO staff was already engaged on other IT projects.
and select its project manager was a critical factor in
Although it is unclear whether these departments would
high department satisfaction, department satisfaction
have pursued direct PMO services should project
with PMO services may differ moving forward. In
managers have been available, it is an indicator of
the future, because the PMO will be fully staffed
interest in direct project management services through
(barring any intermittent vacancies), new projects
the PMO. We also note there is a tension between
requesting PMO services will have limited options
serving all interested departments and developing
based on the project managers available at the time
excess capacity. The PMO needs to continuously
of request. Additionally, as previously mentioned, the
balance the trade-offs between permanently expanding
PMO intentionally started with smaller projects that
the office to address requests for project management
requested PMO services and were likely to progress
10 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
smoothly. Hence, the projects currently receiving PMO the costs associated with the salary and benefits for
services are not fully representative of the projects project managers. However, to keep rates competitive
the PMO will likely engage in the future. If the office with contractor rates and to increase initial take-up for
continues to operate as today, we would anticipate services, CDT was incentivized to keep rates below
that the PMO will engage a broader range of projects what was necessary for full cost recovery of the PMO.
under varied circumstances, including engagement For instance, the service rates exclude key aspects
as a requirement of project approval and on projects of the PMO’s responsibilities, including indirect PMO
already underway considered at-risk. While we found services (such as the frameworks and methodologies
that departments that invited PMO involvement through made available to all departments) and various
request were satisfied with CDT’s service, it is unclear administrative responsibilities. As a result, CDT relies
whether department satisfaction would remain high on surplus balances in the TSRF, which, as previously
when CDT requires a department to use direct project discussed, collects fees paid by departments for CDT
management services from the PMO. services, to fully cover the cost of operating the PMO.
Future PMO Service Rates May Be Less In the future, CDT may need to increase service rates
Competitive. Although the PMO was expected to fully to factor in the cost of indirect PMO services and office
recover the cost of its operation through the collection administration to work towards full cost recovery, as
of fees for PMO services paid by departments, CDT was originally envisioned. If direct service rates were
indicated to us that the PMO has not been able to fully to increase, the PMO might be a less attractive project
recover costs since the office was established. The management option for departments moving forward,
PMO service rates are largely calculated to recover especially if the PMO were no longer able to compete
with contractor rates.
SIGNIFICANT RECENT DEVELOPMENTS
Although the PMO has been operating largely policy and the other focused on operations. The
as intended with a high level of satisfaction from reorganization collapsed the department’s functions
departments, during our evaluation we learned of and responsibilities under one chief deputy director.
two recent developments that significantly impact the Figure 3 (see next page) illustrates the new
operation of the PMO: (1) a reorganization of CDT that organizational structure of CDT.
eliminates the firewall between CDT’s oversight and Potential Conflict of Interest Between CDT’s
project management roles and (2) a policy change that Oversight and Project Management Roles
narrows the number of IT projects eligible for PMO Resurfaces. To address the potential conflict of
services. Below, we describe the recent developments interest between the project management and
and discuss the relevant potential implications they may oversight functions of CDT, the two responsibilities
have on the PMO going forward. were previously placed under separate branches.
However, the reorganization under new CDT
REORGANIZATION OF CDT leadership consolidated the project management
and oversight functions under the same office—the
CDT Reorganized. In spring 2016, a new
Office of Statewide Project Delivery—with both
director assumed leadership of CDT and, shortly
functions reporting to the same chief deputy director.
thereafter, proposed an organizational realignment
This effectively eliminated the firewall, making it so
of the department. The reorganization sought to
that the two responsibilities are in potential conflict.
achieve organizational efficiencies across a variety
Consequently, the current departmental structure may
of CDT’s functions, not specific to the PMO.
be thought to compromise CDT’s ability to maintain
Formerly, the functions of CDT were divided between
independent and objective oversight for projects
two chief deputy directors, one that focused on
managed by the PMO.
www.lao.ca.gov 11
analysis full
gutter
AN LAO REPORT
Figure 3
California Department of Technology’s Revised Organization
Director of Technology
Chief Deputy Director
Other Offices
Office of Statewide
(Digital Innovation,
Project Delivery
Enterprise Architecture,
Technology Services,
Customer Engagement,
Information Security,
Administrative Services,
Project Project Statewide Technology
Professional Development,
Approvals and Oversight Management Office Procurement
Governmental Affairs)
a The organization chart has been simplified to highlight only the aspects relevant for this report.
CDT NARROWED ELIGIBILITY FOR approval or oversight. (Please refer to the nearby box
for a detailed definition of reportable IT projects.) In
DIRECT PMO SERVICES
summer 2016, CDT instituted a new policy that makes
Change in Project Eligibility for Direct PMO most reportable projects under the oversight of CDT—
Services. State IT projects are either “reportable” or that is, generally the larger, more complex projects—
“non-reportable.” Reportable projects are generally ineligible for PMO direct services. Accordingly,
more complex and costly, and as such, they require combined with other aspects of the policy discussed
approval and oversight from CDT. Non-reportable below, the new eligibility policy significantly limits the
projects, on the other hand, can be independently types of projects directly served by the PMO. In fact,
managed by sponsoring departments without CDT under the narrowed eligibility policy, a majority of the
Reportable State Information Technology Projects
Reportable projects generally face a higher level of scrutiny, as they are approved by and under
the oversight of the California Department of Technology (CDT), whereas non-reportable projects are
completely within the authority of sponsoring departments to manage. Projects that meet one or more of
the following characteristics are considered reportable:
• Estimated project cost exceeds departmental delegated cost threshold authority assigned by CDT.
The delegated cost thresholds generally range from $200,000 to $2 million.
• Projects for which the costs are not absorbable by the sponsoring department and therefore
require an appropriation.
• Projects that are specifically mandated by the Legislature.
• Projects that meet previously imposed conditions for reportability set by CDT.
Non-reportable projects either do not meet these criteria or are sponsored by state entities outside of
CDT’s jurisdiction, such as Covered California.
12 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
previously eligible projects could no longer use direct consulting and indirect services—that may position
project management services. This group of projects departments to successfully manage their own projects
collectively represent about $3 billion, or the vast independently. CDT noted that departments primarily
majority of the state’s IT project costs. (We note that, view its role as a control agency, and that departments
despite the narrowed eligibility criteria for direct PMO with adequate resources would prefer to keep project
services, all departments and projects remain eligible management internal, limiting their interactions with a
for PMO consulting services, which provides short-term control agency and building their own long-term project
project assistance.) management capacity. According to CDT, the narrowed
Specifically, CDT’s new eligibility policy narrows eligibility policy addresses these concerns by allowing
direct PMO services to (1) all non-reportable projects, centralized project management services, through
(2) reportable projects only during the project approval the PMO, for smaller projects that are likely to lack
process (known as the Project Approval Lifecycle internal capacity or expertise but otherwise relying on
[PAL]), and (3) reportable projects that have completed a decentralized approach for project management for
the PAL process but are determined by CDT to be most large, complex projects.
“low-complexity,” and therefore receive very limited CDT’s decision to strictly limit direct PMO services
oversight from CDT. Figure 4 shows whether or not in cases where projects are under the oversight of CDT
the six projects currently engaged with the PMO would has the practical effect of reducing the potential for
still qualify under the new eligibility requirements. Even a conflict of interest. CDT reported that departments
among these smaller projects, only three of them would repeatedly raised concerns about CDT’s ability to
meet the narrowed eligibility requirement for direct maintain independent oversight while providing
PMO services. The other three projects, despite finding project management services on a project. As
PMO services valuable, would be ineligible under the discussed previously, we heard similar concerns from
narrowed eligibility policy. (We note that the current departments.
projects receiving direct PMO services will continue to In the following sections, we discuss the practical
do so despite the policy change.) implications of the narrowed eligibility policy, the office’s
Finally, because PMO staff were already fully ability to continue meeting its original objectives, and
dedicated to projects when the policy change went into the relevant legislative considerations under the new
effect, the PMO has not yet engaged any new projects policy.
under the narrowed eligibility policy. (The first project
managed by the PMO was completed
in summer 2017. However, the project Figure 4
manager has not been assigned to
Eligibility of Six Currently Engaged Projects for
a new project for direct services;
PMO Services if Under New Eligibility Policya
instead, the project manager is being
Reportable IT Projects
used for another internal effort.)
Non-Reportable Low Higher
Administration’s Reasons
IT Projects Complexity Complexity
for Narrowing Eligibility. In
our discussions with CDT, the Eligible GEMS SSAP
CAAL-Skills
administration expressed an interest
in continuing to build project Ineligible WellSTAR
management capacity within CCRS
FDAS
individual departments as opposed
a
to maintaining a centralized PMO as Although the six projects managed by the PMO were engaged under the original eligibility policy,
this figure shows that three projects would be ineligible for PMO services beyond the planning
original envisioned. The administration stage because they are reportable and higher complexity.
thereby expressed its preference for PMO = Project Management Office; IT = information technology; GEMS = Grant Electronic
Management System; CAAL-Skills = Cross-System Analytics and Assessment for Learning
a decentralized approach to project
and Skills Attainment; SSAP = Streamline and Strengthen the Accreditation Process;
management, whereby CDT provides WellSTAR = Well Statewide Tracking and Reporting; CCRS = California Civil Rights System; and
FDAS = Fraud Data Analytics System.
departments support—such as
www.lao.ca.gov 13
analysis full
gutter
AN LAO REPORT
Practical Implications of of services to include project implementation after
Narrowed Eligibility Policy anticipating that the change would be disruptive. This
suggests that mainly departments with projects likely to
Reportable, Higher-Complexity Projects
be non-reportable would engage PMO services during
Unlikely to Engage PMO Services if Solely for
the planning phase, because only these projects have
Project Planning. As discussed above, reportable,
the certainty of retaining the same project manager
higher-complexity projects can only use direct
through project completion under the narrowed
PMO services during the planning phase. Generally,
eligibility policy.
departments have a sense of whether their projects
Pathways for Engaging PMO Limited. As discussed
are likely to be reportable prior to initiating project
previously, the new eligibility policy significantly limits the
planning. Whether a project is actually reportable
projects eligible for PMO services. The new policy also
and its complexity level is determined by CDT
limits the pathways CDT can utilize to support projects
through the planning process. (Refer to the nearby
in need of project management services. CDT originally
box for a detailed definition of “complexity” for state
envisioned three pathways for engaging PMO services:
IT projects.) Although reportable, higher-complexity
(1) by department request; (2) as a CDT requirement
projects are eligible for project management services
for project approval; and (3) through CDT intervention
during the planning phase, the challenges associated
on at-risk projects, likely at the recommendation of
with finding new project management services once
CDT oversight. We note that the latter two pathways
planning is complete may discourage these projects
could be used by CDT as tools to intervene and ensure
from seeking PMO services solely for the planning
projects are managed appropriately. (Thus far, only the
phase. Even though the PMO may help reportable,
first pathway has been used.) The projects that would
higher-complexity projects more efficiently navigate
be eligible for direct PMO services under the new policy
the project approval process, losing a project
have little or no approval and oversight requirements
manager after receiving project approval also means
from CDT. In effect, this means CDT would seldom be
losing the valuable insight and knowledge gained
in a position to require PMO services as a condition of
during planning—such as a better understanding of
project approval or intervene based on issues identified
programmatic needs or anticipated risks and mitigation
through its oversight. Without these tools, CDT is unable
strategies. One department currently receiving PMO
to intervene with direct PMO services on the largest,
services originally intended to use PMO services solely
most complex projects that are potentially troubled or
for project planning, but then extended the duration
proven to be troubled. As a result, we anticipate most, if
Complexity of State Information Technology (IT) Projects
The California Department of Technology (CDT) determines the level of complexity for each state
IT project after assessing both the programmatic and technical components of the project. The
programmatic complexity takes into consideration factors such as the stability of the program needs,
the clarity of project objectives, the political sensitivities, and the financial risk to the state. The technical
complexity incorporates factors such as whether the software or hardware has proven effective through
its use, the level of system integration, and the security requirements associated with the project.
The complexity level enables CDT to determine the appropriate level of oversight to provide on the
project. For instance, a project of the lowest complexity—which may rely on established technology
solutions, have a clear business objectives and requirements, pose little financial risk to the state, and
be routine in nature—would receive very limited oversight from CDT. In contrast, a higher-complexity
project may be larger in scale, have higher visibility, face multiple contentious issues, and employ new
technological solutions that must be integrated with multiple existing systems. These projects require
much closer oversight from CDT. Generally, a CDT employee is embedded full time on a project and
routinely reports on the project’s status.
14 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
not all, future projects to engage PMO services through projects in need of project management services would
a request to CDT by the sponsoring department. This have to find support elsewhere. These projects would
pathway depends on departments accurately assessing likely revert to the same project management options
the adequacy of their internal IT project management available prior to the establishment of the PMO—such
capacity, which is something departments have as contracting or reassigning staff internally—which
struggled with historically. were inadequate in some cases and originally prompted
the need for a statewide PMO.
Issues With the
Potential Challenges Recruiting and Retaining
Narrowed Eligibility Policy
Project Managers. According to the departments
receiving PMO services, the current PMO project
Unclear Whether Smaller Projects Stand to
managers are highly qualified, experienced, and
Benefit Most From PMO Services. Given that
knowledgeable. However, it seems likely that the
non-reportable projects tend to be less costly, smaller
narrowed eligibility policy will create significant
in scope, and lack the need for direct CDT oversight,
recruitment and retention challenges. The narrowed
we can infer that these projects are considered to
eligibility policy eliminates two key factors that attracted
be less risky and therefore less likely to need project
project managers to the PMO: (1) the possibility of
management services. Of the six projects the PMO
working on complex, high-visibility, and professionally
currently engages, three projects would remain
challenging projects that could advance their careers
eligible for PMO services under the new eligibility
and (2) a favorable pay differential for working on
policy, suggesting some need for services among
projects that are more complex. The loss of these
small projects. However, the need for PMO services
incentives may make it difficult to retain the current
on non-reportable or low-complexity projects may be
project managers. Further, the less complex projects
limited, suggesting that dedicating state resources and
still eligible for direct PMO services may require
funding to provide direct PMO services to these types
less experienced and skilled project managers than
of projects is likely not the best use of these resources.
the current PMO team, given that the qualification
Further, the potential cost savings to the state from
requirements for working on smaller, less complex
more effective project management on these smaller,
projects will likely be lower. As a result, the state stands
low-costing projects is limited. The state stands to
to lose valuable project management expertise and
realize more benefits by focusing on complex reportable
capabilities formerly centralized at the PMO, especially
projects that risk significant cost increases without
as current project managers consider opportunities at
proper project management. These are the projects
other departments or outside of state government.
which the state has historically struggled with and which
the PMO was originally established to support. Misalignment With Legislative Intent. Given the
new eligibility policy, the PMO is no longer operating
Departments Have Lost a Project Management
as originally envisioned. The PMO will continue to
Option. In our analysis, we found an interest in
provide consulting and indirect services (such as
receiving direct project management services from the
project management frameworks) for all projects
PMO among departments that are no longer eligible.
while bolstering the successful management and
For instance, three projects currently receiving PMO
implementation of smaller projects through direct
services are under CDT oversight and would not be
PMO services. However, the original motivation
eligible for services under the new policy. Additionally,
behind the PMO focused on serving a wide range of
several of the unfulfilled requests noted previously
projects, including those most challenging to the state
would not be eligible for direct PMO services under the
historically. Now, the state’s highest-visibility, largest,
new policy. Finally, the PMO already declined a request
most complex projects may continue to face the same
for services from a project that is no longer eligible
project management challenges that first motivated
under the narrowed criteria. This indicates that some
the creation of the PMO. By only supporting smaller
departments prefer direct PMO services over other
projects that lack expertise or capacity, the initial
project management options—such as consultants—
problems that prompted the creation of the PMO may
but have lost the PMO as an option for direct project
go unaddressed.
management under this new policy. Newly ineligible
www.lao.ca.gov 15
analysis full
gutter
AN LAO REPORT
LAO FINDINGS AND RECOMMENDATIONS
Prior to the recent developments, we found the the office and the pathways through which projects
PMO to be operating as originally envisioned by the engage the PMO. A potential objective of the PMO is to
Legislature, with the office providing critical services to manage IT projects for departments that lack capacity
departments and in a position to potentially expand to and/or expertise, irrespective of a project’s oversight
larger, more complex projects. Departments receiving status. In other words, all IT projects would be eligible
direct PMO services were largely satisfied and noted to receive direct PMO services, including the largest
the significant contributions of their CDT project and most complex projects. Codifying the objectives of
manager in managing their projects efficiently and the office would provide CDT with legislative guidance
effectively. On balance, we found that the PMO was for the operation of the office and ensure that the
a valuable asset to departments in need of project goals and functions of the office remain aligned with
management services. However, under the recent legislative intent.
policy change, the PMO will now primarily serve smaller, Establish Strong Firewall Between
low-complexity projects, which is not in line with the CDT’s Oversight and Project Management
Legislature’s intent when it established the office. In light Responsibilities. We recommend the Legislature
of our positive findings of the PMO’s operation under require in statute that CDT maintain an organizational
the original eligibility policy, we make several findings firewall between its project management and oversight
and recommendations that assert the original intent of responsibilities—similar to the firewall that existed prior
the PMO and position the office to help state IT projects to the most recent reorganization. Requiring a firewall
succeed. would help address and mitigate potential conflicts
There Is a Role for Both Centralized and between the two responsibilities.
Decentralized Approaches to Project Management. Clarify Intent That PMO Act Independently.
As we have pointed out, CDT sees a continued role for Concerns raised by CDT and departments signal
the decentralized approach to project management, that the firewall between CDT’s oversight and project
and has used this to partially explain the recent change management responsibilities, even prior to the recent
in the eligibility criteria for direct PMO services. We reorganization, could be further strengthened to allow
agree that for some departments this approach makes the PMO to function in a way that relieves departments’
sense. However, we find that there can be a role for concerns about a potential conflict of interest between
both a centralized and decentralized approach to CDT’s project management and oversight functions.
project management, and that there is no need to To address this concern, we recommend that the
only have one or the other model available for state Legislature express intent in statute that it expects
departments. the PMO to operate independently and serve in
Reassert Original Objectives of PMO. The the best interests of the projects. This would ease
recent changes to the PMO have caused the office to sponsoring departments’ concerns of inappropriate
diverge from its original intent to provide direct project and unnecessary information sharing between the
management services to the most complex IT projects PMO and CDT oversight and cultivate an open
and to engage projects that may be or already are pathway of communication between the PMO and
challenged due to project management deficiencies. sponsoring departments. This recommendation also
We recommend the Legislature reassert its original would allow the department to continue to provide
objectives for the PMO in statute. The Legislature could project managers with the necessary information to
establish the types of projects under the purview of successfully manage a project.
16 LEGISLATIVE ANALYST’S OFFICE
analysis full
gutter
AN LAO REPORT
CONCLUSION
The Legislature approved the establishment of the meet the Legislature’s original expectations. Our
PMO with expectations that the office would meet recommendations enable the Legislature to reassert
a critical need in the state for project management the original intent of the PMO to centralize project
expertise and help the state avoid the high-profile management services and improve the state’s success
IT failures of the past. We found that the PMO was in implementing IT projects by equipping departments
showing success towards meeting the original with the necessary expertise and capacity. Additionally,
legislative intent by first establishing the internal we note that even with the continuation of the PMO
processes and capacity to ultimately scale up to as originally envisioned, there is still room to continue
larger, more complex projects. However, given recent the decentralized approach to project management for
developments, we have concerns about the path departments with the capacity to do so.
forward for the PMO and its ability to succeed and
www.lao.ca.gov 17
analysis full
gutter
AN LAO REPORT
LAO PUBLICATIONS
This report was prepared by Lourdes Morales and Amy Li, and reviewed by Ginni Bella Navarre. The Legislative Analyst’s Office
(LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service, are available on
the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000, Sacramento, CA 95814.
18 LEGISLATIVE ANALYST’S OFFICE