The 2021-22 Budget:
California State Payroll System
IT Project
FEBRUARY 2021
The State Controller’s Office (SCO) is responsible Budget Proposals
for issuing pay to the state workforce, and the
Budget Requests $5.7 Million ($3.4 Million
California Department of Human Resources (CalHR)
General Fund) for SCO and CalHR to Start
supports state human resources (HR) and labor
Project Procurement and Change Management
relations policies and practices. In 2016, SCO
Activities. SCO requests $5.5 million ($3.1 million
started planning a replacement for the state’s
General Fund) and 7 positions to complete CDT’s
current payroll system—the California State Payroll
PAL. SCO plans to release a solicitation for vendors
System (CSPS). The 2021-22 Governor’s Budget
to bid, conduct a procurement process with
proposes to continue CSPS planning efforts with
multiple phases (described below), and select one
requests totaling $5.7 million ($3.4 million General
or more vendors for the final contract award. CalHR
Fund) in 2021-22 for SCO and CalHR to begin
requests $230,000 General Fund and 1 position to
project procurement and change management
hire an Enterprise HR Project Director to support
activities. This post evaluates the two budget
the implementation of state HR and labor policies
proposals for the proposed CSPS information
and practices in CSPS.
technology (IT) project and provides associated
Phased Procurement Process Planned. SCO,
recommendations.
with technical guidance from CDT, plans to conduct
Background a procurement process with three phases over
a six-month period. (A recent change in SCO’s
Proposed CSPS in Stage 2 Alternatives
procurement strategy shortened the procurement
Analysis of PAL Process. The California
process from two years, as reflected in SCO’s
Department of Technology’s (CDT’s) Project
budget proposal, to six months.) Phase 1 will
Approval Lifecycle (PAL) process is divided into four
involve the release of a solicitation for vendors to
consecutive stages: the Stage 1 Business Analysis,
bid, meetings to answer vendor questions, and
Stage 2 Alternatives Analysis, Stage 3 Solution
state evaluation of vendor bids with likely no more
Development, and Stage 4 Project Readiness
than three vendors selected for Phase 2. Phase 2
and Approval. The proposed CSPS IT project is in
will require vendors to build proofs of concept—that
the Stage 2 Alternatives Analysis, which requires
is, working models of their technical solutions that
entities that propose projects to conduct market
are based on business scenarios defined by SCO—
research and identify available technical solutions
for state evaluation. ($3 million of the $5.5 million
to the business needs they identified in the Stage 1
that SCO requests in its budget proposal is to pay
Business Analysis. Entities then recommend one
vendors for their proofs of concept in Phase 2.)
or more solutions to CDT for approval and (once
This proof-of-concept evaluation, and other
approved) set a preliminary baseline project cost,
information that SCO will gather from vendor
schedule, and scope. SCO submitted their Stage 2
meetings and responses, will help the state select
Alternatives Analysis documentation last year,
one or more “best value” vendors for Phase 3.
and CDT approval is expected to be forthcoming.
Phase 3 will end with a contract award after the
SCO anticipates the proposed CSPS IT project will
state finishes its negotiations with the vendor(s)
complete the PAL process and start development
and interviews project staff. Throughout the
and implementation in 2022-23.
procurement process, SCO will submit Stage 3
2021-22 LAO Budget Series 1
analysis full
gutter
Solution Development and Stage 4 Project office, on behalf of the Legislature, to review this
Readiness Approval documentation, which will information before action is taken on the CSPS
culminate in CDT approval of the CSPS IT project budget proposals. We expect CDT approval of the
through the PAL process. proposed CSPS IT project through Stage 2 of the
PAL process in the next couple of months.
Assessment
Recommendations
Proposed CSPS Will Be a Complex and Costly
IT Project. Based on market research for their Withhold Action on Budget Proposals Until
recommended technical solution, SCO estimates CDT Approves Stage 2 Alternatives Analysis. We
the preliminary baseline cost for the proposed recommend the Legislature withhold action on the
CSPS IT project at approximately $750 million CSPS budget proposals in the 2021-22 Governor’s
(a majority of which will be General Fund). The Budget until CDT approves the proposed CSPS
complexity of a full replacement of the state’s IT project through Stage 2 of the PAL process.
current payroll system—which is what this IT The Stage 2 Alternatives Analysis documentation
project proposes—also requires a lot of time. The will allow our office to more fully assess and
preliminary baseline project schedule anticipates recommend action on these budget proposals.
system completion and initial deployment in Ask Administration Questions While Awaiting
2027-28—a five-year time frame to develop CDT Approval of Stage 2 Alternatives Analysis.
and begin implementation of the new system. Awaiting the availability of Stage 2 Alternatives
Throughout the project, change management Analysis documentation (once CDT approves the
activities also will be required to train staff at project through Stage 2), we recommend the
many state entities how to use the new system Legislature consider asking some of the following
and to review and modify their existing business questions during the budget subcommittee
processes. This statewide effort is comparable to process:
the change management required for the Financial
• Why is SCO proposing to replace the current
Information System for California (FI$Cal) IT
Uniform State Payroll System? Have these
project, which led to the creation of a new entity
reasons changed over time? If so, why?
(Department of FI$Cal) with ongoing operational
and training responsibilities. • What is the recommended solution for this
proposed project? Explain the costs and
Phased Procurement Process Reflects
benefits of this solution. What other solutions
Complexity and Risk of Project. The complexity
were considered?
and cost of the proposed CSPS IT project is also
reflected in the planned procurement process. A • In light of the state’s projected out-year
phased procurement in which vendors demonstrate deficits, is now an appropriate time to embark
their technical solutions with proofs of concept on such a costly project?
does have merit as a way of reducing project • What change management efforts will be
risk. It also underscores the risk of the proposed necessary to implement this proposed
project scope and the approach to development project? How will the project team coordinate
and implementation. To determine the viability these efforts to modernize how the state
of the project as scoped, state evaluation of the performs its payroll functions?
proofs of concept during the second phase of the • How will the administration mitigate risks and
procurement process will be critical. address issues to avoid the outcome of the
Stage 2 Alternatives Analysis Approval 21st Century Project, the predecessor to the
Presents Opportunity for Legislative Oversight. proposed CSPS IT project?
The Stage 2 Alternatives Analysis documentation
Require Reporting From Administration
will identify the administration’s preferred technical
to Allow for Evaluation of Proposed Project
solution(s) and set a preliminary baseline project
Cost, Schedule, and Scope. Once the Stage 2
cost, schedule, and scope. It is important for our
2021-22 LAO Budget Series 2
analysis full
gutter
Alternatives Analysis documentation is approved, Given the proposed project’s complexity and cost,
we also recommend the Legislature direct SCO, the Legislature could consider budget bill language
CalHR, CDT, and the Department of Finance that requires: (1) monthly oversight meetings
(DOF) to provide a report with all of the options with our office (on behalf of the Legislature),
and technical solutions considered during Stage 2 SCO, CalHR, CDT, and DOF to receive project
and their associated preliminary project cost, updates and review oversight documents such as
schedule, and scope (if known). This report could CDT independent project oversight reports and
help the Legislature consider options other than independent verification and validation reports
the proposed project scope and the approach to with the project team, and (2) quarterly briefings
development and implementation, and inform future to update other legislative staff on the proposed
hearings or meetings with the project team. project. The Legislature could revisit this oversight
Consider Options for Legislative Oversight. framework once the proposed project completes
We recommend the Legislature establish an the PAL process and begins development and
oversight framework for this proposed IT project. implementation.
LAO Publications
This report was prepared by Brian Metzker, and reviewed by Mark C. Newton and Carolyn Chu. The Legislative