Summary
State Recently Initiated Planning for an for statewide scaling of the California College
Integrated “Cradle to Career” Data System. Guidance Initiative (CCGI), a college planning
In response to longstanding concerns that and advising tool currently used by some school
California lacked an integrated education data districts. The Governor’s proposals largely reflect
system that would allow policymakers, educators, the recommendations contained in the work
families, and others to answer key questions group’s first report. Notably, the Governor proposes
about student progression and outcomes, the to have GovOps manage the system and an
2019-20 budget package provided $10 million 18-member governing board—primarily consisting
non-Proposition 98 General Fund to create such a of data providers such as the California Department
system. The one-time funds were provided to the of Education and higher education segments—to
Office of Planning and Research (OPR) for initial oversee the system.
planning activities, including forming a multiagency Opportunities to Improve on Governor’s
work group tasked with making recommendations Approach. Though these budget proposals
on key components of the data system. The work have some meritorious aspects, we have several
group was to transmit its recommendations to concerns with them. Our main concerns are the
the Legislature through three statutorily required lack of justification for several proposals and the
reports. The Legislature received the first work lack of standard project review and oversight,
group report on December 31, 2020, with the which is typically provided through the California
second and third work group reports anticipated Department of Technology’s (CDT’s) Project
by April 1 and June 30, 2021, respectively. To Approval Lifecycle (PAL) process. Instead of the
date, approximately $4 million of the original Governor’s package of proposals, we recommend
appropriation has been spent, with $6 million still the Legislature take a more incremental approach—
available. approving a smaller amount of remaining 2019-20
Governor Proposes to Fund Several Work funding to hire GovOps staff to begin the PAL
Group Recommendations. In late January process, then wait to approve further budget
2021, the Governor notified the Legislature of requests until better cost estimates are available.
his intent to authorize the remaining 2019-20 Additionally, rather than funding CCGI expansion in
funds for specific start-up costs. Also in January, 2021-22, we recommend the Legislature provide
the Governor proposed providing $14.5 million one-time funding for an independent evaluation,
non-Proposition 98 General Fund ($11.5 million then use the results of the evaluation to inform the
ongoing, $3 million one time) for various other Legislature’s next steps in 2022-23. Finally, we
project costs in 2021-22, including creating a new recommend the Legislature increase the number of
“Cradle to Career” office within the Government public members on the governing board so as to
Operations Agency (GovOps). The Governor’s mitigate potentially negative incentives for the data
2021-22 budget request included an additional providers to control data decisions and use the
$3.8 million ongoing Proposition 98 General Fund system primarily for their own narrower interests.
2021-22 LAO Budget Series 1
analysis full
gutter
Introduction
In this post, we (1) provide background on system), (2) describe the Governor’s proposals to
progress to date toward creating an integrated fund the development of specific components of this
education data system and other related data tools system, (3) assess these proposals, and (4) make
(collectively referred to as the “Cradle to Career” data associated recommendations.
Background
In this section, we provide background on the in turn, can use the data to inform decisions
state’s education data systems and recent planning about admissions and course placement.
efforts to connect them. • eTranscript California. This platform transfers
California’s Extensive Education System Lacks student-level course, grade, and certain
Key Data Linkages. California’s education system is other data files (such as degrees earned)
made up of numerous segments and other entities. electronically across California’s higher
Specifically, the system includes early education education segments. Most of these electronic
programs, elementary and secondary schools, transcripts are for community college students
county offices of education, community colleges, applying for transfer admission to CSU or
and universities in both the public and private the University of California (UC). Using funds
sectors. Currently, each of these entities collects and provided by the state, the CCC Chancellor’s
maintains data on its students, but the data generally Office contracts with the CCC Technology
are not linked across the segments of education Center (located at Butte College) to manage
(such as from high school to community college). and operate the platform.
Not linking data limits the ability of policymakers, • Cal-Pass Plus. Most school districts, every
educators, researchers, parents, and others to get community college, and some public and
answers to many basic questions about student private four-year institutions voluntarily
progression from preschool through K-12 education, participate in Cal-PASS Plus, a project overseen
through higher education, and into the workforce. by the CCC Chancellor’s Office. Cal-PASS Plus
Some Cross-Segmental Data Sharing links data from participating institutions, then
Occurs in California. Although California has analyzes the data. It provides its findings to
no comprehensive integrated data system, some participating institutions—sharing outcomes
cross-segmental data efforts exist. Among the most with them so they may learn more about their
notable of these efforts are: students and how to improve their outcomes.
• Employment Outcomes. Each public higher
• CCGI. About 100 school districts participate
education segment has an agreement with the
in CCGI, which a nonprofit entity administers.
Employment Development Department (EDD)
The state currently funds CCGI as part of the
that allows it to identify the quarterly earnings
California Department of Education’s (CDE)
of its graduates. The data are matched using
budget. Partner districts can upload verified
social security numbers, which most students
academic transcript data into students’
provide when they apply to college.
accounts on CaliforniaColleges.edu. When
students from these partner districts apply State Recently Initiated Planning for an
to a California Community College (CCC) or Integrated Cradle to Career Data System. As part
California State University (CSU), certain high of the 2019-20 budget package, Chapter 51 of 2019
school data is shared. The college or university, (SB 75, Committee on Budget and Fiscal Review)
provided $10 million one-time non-Proposition 98
2021-22 LAO Budget Series 2
analysis full
gutter
General Fund to the OPR for initial work related on page 5 describes the state’s PAL and project
to developing an integrated data system. The oversight processes.
budget package included intent language that the Work Group Recommends Three Cradle to
data system be built to “advance academic and Career Data Projects. The planning facilitator—
governmental research on improving policies from which OPR selected to be WestEd, a nonprofit
birth through career” as well as “create direct support organization based in San Francisco—convened
tools for teachers, parents, advisors, and students.” the first work group planning meeting in January
Of the $10 million appropriation, about $4 million 2020. The Legislature received the first required
was for work group planning and related activities, work group report on December 31, 2020. The
with the remaining approximately $6 million available report was delayed by six months due to scheduling
for initial development of the
data system. The development
funds are contingent on (1) the Figure 1
Legislature’s receipt of three work
2019-20 Budget Package Required
group reports (discussed in the Three Data System Planning Reportsa
next paragraph), (2) approval
Reports to be Submitted by Work Group Planning Facilitator to the
of an expenditure plan by the Legislature and Department of Finance
Department of Finance (DOF),
and (3) notification to the Joint
Date Due: Required Content/Recommendationsb:
Legislative Budget Committee
July 1, 2020 Overall structure of the data system.
(JLBC). Chapter 51 identified a
First Report
total of 17 representatives from Received on December 31, 2020 Entity charged with managing the data system.
15 specified state entities to be Information to be available from the data system for policy
making purposes.
in the work group. The director of
OPR was charged with contracting
with an outside “planning
facilitator” to support the group.
October 1, 2020 Progress in preparing final report.
Three Planning Documents
Interim Report
Required to Be Submitted to the Anticipated April 1, 2021
Legislature. The budget package
required the planning facilitator
to submit three reports to the
Legislature and DOF that detail the January 1, 2021 How data providers will enter and correct data and
Final Report ensure data quality.
work group’s advice on matters
Anticipated June 30, 2021
such as the type of data system How to link data across participating segments/agencies.c
to create and the entity to operate How to address data security and privacy.
the system. Figure 1 highlights
How members of the public (including researchers) will
key information to be included in be able to access the data.c
each report. Though the Cradle
Plans for training/support of data system users.
to Career data system is an
An implementation time line, including recommended data
information technology (IT) project system expansions and enhancements.c
and the CDT was designated as
Statutory changes that may be needed for implementation.
a member of the work group,
Estimated costs, including ongoing costs.
Chapter 51 did not require OPR to
plan the data system through the
CDT’s Project Approval Lifecycle a Pursuant to Chapter 51 of 2019 (SB 75, Committee on Budget and Fiscal Review).
b Figure highlights key components of each report.
(PAL) process. The box that starts c Work group addressed in first report.
2021-22 LAO Budget Series 3
analysis full
gutter
disruptions resulting from the pandemic. To fulfill the proposed members of the governing board.
the requirements of Chapter 51, the work group The work group also recommends two advisory
recommends the state fund three data projects: boards—the Data and Tools Advisory Board and the
(1) an integrated education data system (referred Community Engagement Advisory Board. Whereas
to in the report as a “P20W” data system) that links the first advisory board would examine whether the
records from various state agencies, including CDE, data system is providing actionable information, the
the higher education segments, the Commission on second advisory board would examine whether the
Teacher Credentialing, EDD, and the Department of public is aware of the data system and knows how to
Social Services; (2) an expansion of CCGI to school use the information in it.
districts throughout the state; and (3) an upgrade ...And a Managing Entity. The governing board
to eTranscript California to, among other things, would be charged with hiring an executive director,
include specific skills students acquired through who would establish and operate a “Cradle to
competency-based education or other forms of Career” office within the state’s GovOps. GovOps
nontraditional learning. The report recommends would build and operate the data system, with
rolling out these projects over a five-year period, an evaluation after five years to determine if it or
starting with the integrated education data system another entity should have that role. The box on
and CCGI expansion project. page 7 provides an overview of GovOps.
Work Group Also Recommends a Governance Legislature Is Likely to Receive Remaining
Structure... The work group also recommends Work Group Reports Later This Year. OPR
that the data system be overseen by a governing indicates that the work group’s required interim
board made up of 18 members, consisting report on the status and progress of the final report
of: (1) 12 agencies contributing data to the will be provided to the Legislature by April 1, 2021.
integrated education data system and (2) 6 public OPR indicates that the third and final report, which
members—4 appointed by the Governor and will include an estimate of ongoing costs for the data
2 appointed by the Legislature. The work group system and recommendations on issues such as
recommends that decisions by the governing protecting privacy and security, will be submitted to
board be made by two-thirds vote. Figure 2 shows the Legislature by June 30, 2021.
Figure 2
Data Providers Make Up Two-Thirds of
Proposed 18-Member Governing Board
Data Providers (12) Public Membersa (6)
California Department of Education K-12 practitionerb
California Community Colleges K-12 practitionerb
California State University Public memberc
University of California Public memberc
Association of Independent California Colleges and Universities Public memberd
Bureau of Private Postsecondary Education Public membere
California Student Aid Commission
Commission on Teacher Credentialing
California Labor and Workforce Development Agency
Employment Development Department
California Health and Human Services Agency
California Department of Social Services
a
Public members are to “represent the public beneficiaries of the Data System, including but not limited to, practitioners,
families, students, adult learners and workers, community organizations, research organizations or advocates.”
b
Appointed by the Governor. Practitioner is “to serve as a representative of K-12 educators, counselors, and
administrators.”
c
Appointed by the Governor.
d
Appointed by the Speaker of the Assembly.
e
Appointed by the President pro Tempore of the Senate.
2021-22 LAO Budget Series 4
analysis full
gutter
Governor’s Proposals
In this section, we describe the Governor’s Provides Both Ongoing and One-Time Funds
proposals to fund the work group’s to Begin Development and Implementation
recommendations. Phase. Specifically, the Governor’s budget
Closely Follows Work Group’s includes:
Recommendations. The Governor’s trailer bill
• $14.5 million non-Proposition 98 General
language largely reflects the recommendations
Fund ($11.5 million ongoing, $3 million one
in the work group’s first report, including the
time) to GovOps. A portion of the funds
composition of the governing board, the creation of
would support 12 staff (including an executive
two advisory groups, and identification of GovOps
director) in 2021-22 at a newly created
as the managing entity to incubate the Cradle to
Cradle to Career office within GovOps. (The
Career project. The trailer language generally defers
administration proposes increasing staff to
to the governing board to determine a specific time
16 in 2022-23 and providing an additional
line for implementing Cradle to Career projects.
$500,000 ongoing funding for GovOps at
California Has a Process for Approving Information Technology (IT)
Projects
State Has Had Challenges Implementing IT Projects. Over the past few decades, the
state has experienced considerable challenges successfully implementing IT projects. Various
factors can contribute to project challenges, with one such factor being poor project planning.
Several years ago, the California Department of Technology (CDT) implemented a new IT
project approval process—known as the Project Approval Lifecycle (PAL)—with the goal of
helping to bolster project planning and reduce the likelihood of project challenges or failure.
The PAL process improves legislative oversight by requiring state entities to conduct specific
planning activities, submit associated planning documents to CDT for assessment, and then
share approved documents with the Legislature. These documents can give the Legislature a
better understanding of, and more confidence in, the project cost, schedule, and scope prior to
approving funding through the annual budget process.
CDT Role Spans From Project Planning to Approval and Oversight. The PAL process has
multiple stages. Each stage requires departments to conduct specific planning-related analyses
and submit an associated planning document to CDT. Collectively, the planning documents from
these stages form a comprehensive plan for implementing a proposed IT project. Once CDT
approves a department’s proposed project, CDT’s role typically changes to providing project
oversight. Specifically, CDT provides independent review of the project—monitoring whether it
remains within budget, on schedule, and on track to achieve its established objectives. In its
project oversight reports, CDT identifies any issues of concern, shares lessons learned from
other projects, and recommends strategies to reduce project risks and fix identified issues. Most
projects also contract with independent verification and validation service providers to monitor
the technical implementation of the project, including code reviews and system testing. The
figure on the next page shows the development of the PAL phases through project oversight.
Current law generally requires the California Department of Education and the California
Community Colleges Chancellor’s Office (as well as most other state agencies) to use the CDT
planning process for IT projects costing more than $1 million. The California State University and
University of California are not required to go through CDT’s process. (Continued on next page.)
2021-22 LAO Budget Series 5
analysis full
gutter
that time.) The remaining funds in 2021-22 Notifies JLBC of Intent to Spend Remaining
would be used to cover various operating and 2019-20 Funds. In addition, in January 2021, DOF
technology acquisition costs related to the sent notification to JLBC of the administration’s
integrated data system, including funds to intent to spend the remaining $6 million from the
upgrade CDE’s K-12 database. 2019-20 appropriation for initial costs related to
• $3.8 million ongoing Proposition 98 General the integrated education data system and CCGI
Fund to increase the number of CCGI expansion. Specifically, the administration would
partner school districts. To support statewide begin to use the funds in the current year to (1) hire
expansion, funding is also provided to allow interim staff at GovOps, (2) commence a pilot
CCGI to receive data directly from CDE’s (proof of concept) for the integrated education data
K-12 database. (CCGI currently receives data system, (3) begin to scale CCGI (primarily in the
directly from each partner school district.) Central Valley), and (4) support various one-time
Stages of the PAL Process and Post-Approval Project Oversight
State Process for Planning and Overseeing IT Projects
Stage 1 Stage 2 Stage 3 Stage 4
Business Alternatives Solution Project Readiness
Analysis Analysis Development and Approval
Identify Programmatic Assess Existing Solution Requirements Solicitation Release
Problem/Opportunity Programming Processes
Solicitation Development Select Vendor
Establish Business Market Research
Case/Need Contract Management
Develop Mid-Level
Identify Objectives Solution Requirements Baseline Project
Assess Departmental Identify Solution CDT Decision
Readiness Alternatives
Recommend Solution
CDT Decision
CDT Decision Financial Analysis
CDT Decision Concurrent
Upon approval, entities
can request planning Project Oversight
funds to complete the AAwwaarrdd CCoonnttrraacctt
PAL processa Independent project oversight aanndd SSttaarrtt PPrroojjeecctt
Upon approval, entities (typically provided by CDT)
can request funds
DDeevveellooppmmeenntt aanndd
for project development Independent verification and validation IImmpplleemmeennttaattiioonncc
= Reject and implementationb (typically provided by a vendor)
= Rethink and Resubmit
= Approve
a Budget requests can be for a single stage (particularly for complex and costly IT projects) or for multiple stages. In either case, legislative approval is required.
b Budget requests for starting development and implementation can be submitted before completing the PAL process (after Stage 2 or Stage 3) or upon
completing the PAL process (after Stage 4). Regardless of when requested, legislative approval is required.
c After the contract is awarded and the project begins, the Legislature often considers and approves budget requests for further development and implementation
on an annual basis.
PAL = Project Approval Lifecycle; IT = information technology; and CDT = California Department of Technology.
2021-22 LAO Budget Series 6
analysis full
gutter
Government Operations (GovOps) Agency Oversees Various
Departments
GovOps, which was created in 2013, oversees 10 state departments employing a total of
about 15,000 state employees. The departments GovOps oversees include the Department
of General Services, the Franchise Tax Board, and the Public Employees’ Retirement System,
as well as the Department of Technology. GovOps itself consists of 57 authorized positions.
One of its core functions is to coordinate cross-departmental projects and assist other
departments that are experiencing significant operational challenges. For example, in recent
years, GovOps has managed efforts to improve services at the Department of Motor Vehicles
and identified the causes of unemployment insurance payment delays at the Employment
Development Department.
technology and software acquisition costs. In Cradle to Career data system projects (consisting
February 2021, DOF agreed to give JLBC until April of the integrated education data system as well
15, 2021 to decide whether to concur with this as CCGI and eTranscript California expansions).
expenditure request. To the extent such estimates are available in
2021-22 Budget Proposal Could Change at time (such as in the April 1, 2021 interim report),
May Revision. As mentioned earlier, the work DOF has indicated it would consider revisions to
group’s final legislative report is required to include the Governor’s budget proposals as part of the
estimates of ongoing costs for its recommended May Revision.
Assessment
In this section, we provide our assessment of disaggregated by gender, racial/ethnic group,
the Governor’s proposals (for both current- and and other demographics—after leaving their
budget-year spending). While we agree with the particular education segment, thereby providing
Governor that having an integrated education greater insight into the effectiveness of current
data system would be an asset for the state and practices. Figure 3 on the next page provides
GovOps is a reasonable managing entity for that examples of the kinds of crosscutting policy
system, we have a number of concerns with the questions the Legislature, educators, and others
administration’s proposed approach. Below, we could answer with an integrated data system.
identify the meritorious aspects of the Governor’s Tasking GovOps With Managing System
proposals, then turn to our concerns. Could Further State Synergies. GovOps does
An Integrated Education Data System not have any particular experience or expertise
Could Have Significant State- and Local-Level with developing and implementing data systems.
Benefits. The administration’s goal to create an Charging GovOps with managing the Cradle to
integrated education data system for California is in Career data system, however, does have some
line with a longstanding priority of the Legislature. potential advantages. In particular, GovOps
Such a data system could give the Legislature a is working to improve how the state collects,
more holistic view of the state’s education system manages, and uses data through its Statewide Data
and allow policymakers to make more informed Strategy. This initiative, which is led by the state’s
budget and policy decisions. An integrated data Chief Data Officer, is focused on aligning other
system also could provide more information to integrated data system development efforts in the
educators about what happens to their students— state, standardizing interagency data exchange
2021-22 LAO Budget Series 7
analysis full
gutter
agreements, and developing a statewide approach asserts that given CCGI and eTranscript California
to data literacy and data skills training. We believe are managed by nonstate entities that would
opportunities exist to create synergies between enter into a contractual relationship with the
these existing state efforts and the proposed Cradle to Career governing board, those projects
education data system. A new office within GovOps are not subject to the PAL process. Given the
thus could be a reasonable place to incubate the administration identifies potential data flows and
Cradle to Career data system. information sharing between the three projects,
Several Concerns With Project Planning however, we believe CCGI and eTranscript
and Oversight Processes. CDT’s PAL process California also should go through the PAL process.
was designed to improve the quality of IT projects Proposed Budget Makes Number of
and provide the Legislature with a more complete Unsubstantiated Assumptions, Lacks Basic
plan and set of cost estimates before funding the Details. The Governor’s estimates of one-time and
project. As noted earlier, the Cradle to Career data ongoing project costs use a number of assumptions
system currently is not being planned through PAL. that are based on incomplete information.
The administration has indicated that it expects Typically, agencies undertake market research to
the integrated education data system project to identify what technical solutions are available for
use the PAL process, but the administration is a project and determine how much it would cost
unclear at what point the project will enter that to implement those solutions consistent with a
process. In addition, the administration is not clear project’s system requirements. The administration
whether there will be independent project oversight conducted some market research to estimate some
and independent verification and validation of the one-time costs, but other one-time and ongoing
project, which also are typical for state IT projects. project costs appear to be rough estimates based
Furthermore, the administration has indicated it on one other state data system. For example, the
does not expect CCGI or eTranscript California to administration indicates that some of its estimates
go through the PAL process. The administration were based on what it cost the state to develop
Figure 3
Questions That Could Be Answered With an Integrated Eduction Data System
• Which early education programs and services have the greatest effect on reading and comprehension in elementary
school?
• What are the demographic, program, and course-taking profiles of K-12 students who enroll or do not enroll in
postsecondary education?
• What are the characteristics and educational paths of students who drop out of high school but eventually enroll in a
postsecondary institution?
• What specific high school programs are associated with better postsecondary outcomes for low-income students?
• What are the postsecondary enrollment and completion patterns of students in high school career technical education
(CTE) pathway programs compared with similar students not in a CTE pathway?
• Does dual (concurrent) enrollment by high school students in college courses promote more timely and efficient
completion of associate and bachelor’s degree programs?
• Do students who earn an associate degree for transfer (ADT) at a community college end up taking fewer total units to
earn a bachelor’s degree than students who transfer without an ADT?
• Are students receiving Cal Grant competitive awards more likely to enroll and graduate from college than those
eligible students who just missed the cut-off for getting awards?
• What are the employment outcomes of graduates from CSU and UC teacher preparation programs?
• Which health and social service programs are most closely associated with improved educational outcomes of K-12
and college students?
2021-22 LAO Budget Series 8
analysis full
gutter
a data system on homelessness, scaled up to • What are the reasons why non-partner school
take into account the much larger scope of the districts have chosen not to participate in
integrated education data system. This approach CCGI to date?
to estimating costs is not standard practice and • What is the impact of CCGI on student
can result in inaccurate cost estimates. Other data outcomes? For example, to what extent are
systems can have significantly different technical students who use CCGI more likely to enroll
requirements resulting in different project solutions in college than their peers who do not use
that have much higher or lower costs than the CCGI? To what extent do differences exist
proposed project. Also a departure from standard among students by gender or from certain
state budget practices, the Governor’s budget does racial/ethnic groups?
not provide workload justification for the requested
The administration has indicated that while its
GovOps positions. The administration indicates
current proposal is to provide $3.8 million ongoing
that it expects the work group to provide workload
for CCGI, at full implementation ongoing costs
justification later in the spring. Much of this basic
could be about $20 million annually. (The final
cost and staffing information, however, would have
legislative report is expected to include updated
been made available to the Legislature had the
cost estimates for the project.) We believe the
work group used CDT’s PAL process.
Legislature should have answers to the above
Premature to Scale CCGI Without Evaluation.
types of questions before embarking on a costly
CCGI has a number of features designed to help
expansion of CCGI.
students, parents, and counselors. For example,
Insufficient Role for Non-Data Providers
CCGI provides students with information about the
and Legislature on Governing Board. While
college and financial aid application process, and it
proposing to reserve one-third of governing board
provides an education planner that allows students
seats for public members is a good start, we
and high school counselors in partner districts to
believe having greater public representation would
track progress toward meeting CSU and UC course
have certain benefits. Most notably, having more
eligibility requirements. Though these types of
public representation on the governing board is an
features have the potential to be beneficial, to date,
important way to mitigate the possibility of data
the Legislature has not provided funding specifically
providers using the system primarily to further
for an independent, comprehensive evaluation
segment-specific interests. This is a particularly
and CCGI has not used its base funding for such
important issue given that the Governor’s proposed
an evaluation. As a result, the Legislature lacks
trailer bill language tasks the governing board
basic information on CCGI’s usage and outcomes.
with developing the data-request process used by
For example, the Legislature cannot answer the
education researchers and other members of the
following questions:
public. Historically, certain segments have been
• To what extent are CCGI’s various features reluctant to approve such requests and share data.
currently used by students, schools, We also believe the Legislature should have a larger
community colleges, and universities? role in selecting members of the governing board.
• Which particular features or services do they Under the Governor’s proposal, the Governor would
find most valuable? get to select four public members while the Senate
• If certain features are not widely used, why and Assembly combined would get to select only
not? Could modifications be made to CCGI two public members.
so these features are more useful for students
and other potential users?
2021-22 LAO Budget Series 9
analysis full
gutter
Recommendations
In this section, we make several recommendations the staff necessary to begin the PAL process. The
designed to improve on the Governor’s proposals. next paragraph provides an illustration of what an
Require Administration to Use Standard alternative 2021-22 budget might look under our
Approval and Oversight Processes. Given the recommended approach.
state’s mixed track record with IT projects, we LAO Budget Alternative Funds Some Staff
recommend the Legislature specify in statute and Start-Up Activities While Awaiting Better
(such as through trailer bill language) that the Information. Figure 4 on the next page compares
administration use the PAL process to plan the entire the Governor’s budget proposals with an LAO
Cradle to Career data system (including CCGI and budget alternative. Our alternative would designate
eTranscript California), as well as have independent $1.2 million in remaining 2019-20 funds for board
oversight, verification, and validation of the system meetings and some GovOps project staff as well
upon completing the PAL process. We note that the as knowledge transfer activities from WestEd to
administration can submit the project through the GovOps. (As discussed in the next paragraph, our
PAL process now, and CDT can use the project’s LAO alternative also includes a small amount of
prior planning efforts to help it decide at what stage 2019-20 funds for CCGI.) At this time, the alternative
of the PAL process the project should begin. The would not fund the costs of the pilot or technology
project therefore would not be significantly delayed procurement activities, as these components would
because of the requirement to use the PAL process. be undergoing further analysis as part of the PAL
Furthermore, CDT could determine that CCGI and process. Upon completing the PAL process, better
eTranscipt California are largely updates to existing estimates of these costs, as well as other potential
IT systems that are low risk. In this case, CDT could project costs, would be available. We recommend
delegate those projects back to their respective the administration submit a future budget request on
administering entities to complete the planning these project components once more reliable cost
phase. If the Legislature subsequently approved and estimates are available.
funded those projects, they then could proceed with Fund CCGI Evaluation. Instead of providing
development and implementation without needing to funding for CCGI expansion in 2021-22, we
complete the rest of the PAL process. recommend the Legislature provide one-time
Require Administration to Provide More funding for an evaluation and then use the results
Justification for Budget Requests. We also of the evaluation to inform the Legislature’s next
recommend the Legislature request that the steps in 2022-23. Based on our discussions with
administration provide additional information evaluation firms, we believe that about $250,000
that would support its budget proposals. At a would be sufficient for such a study. The study could
minimum, we recommend the Legislature request: commence some research activities in summer
(1) market research that evaluates available 2021, with other activities (especially those involving
technical solutions for the system and estimates student feedback) commencing in fall 2021, with
the one-time and ongoing project costs based on findings provided to the Legislature by spring 2022.
system requirements, (2) a schedule for completion Increase Public Representation on Governing
of project activities, and (3) workload justifications for Board. Finally, we recommend the Legislature
the requested GovOps positions. In the absence of increase the number of non-data providers (public
this information, we recommend the Legislature wait representatives) on the governing board so they are
to approve the Governor’s budget request until the at least equal to—if not greater than—the number
project completes at least Stage 2 (the Alternatives of seats held by the data providers. We further
Analysis) of the PAL process. In the meantime, the recommend specifying that the public members
Legislature could consider approving some amount include representatives from the administration as
of remaining 2019-20 funding for GovOps to hire well as bipartisan representation from the Legislature.
2021-22 LAO Budget Series 10
analysis full
gutter
Figure 4
Comparing Governor’s January Proposals With LAO Alternative
2021-22a (In Thousands)
January Proposalsb
Section Governor’s LAO
Letter Budget Total Alternative
One-Time Costs
Start-up administration $1,779 — $1,779 $1,159c
CCGI 1,596 — 1,596 250
Integrated education data system pilot 1,110 — 1,110 —
Other technology/development costs 1,514 $3,486 5,000 —
Totals $6,000 $3,486 $9,486 $1,409
Ongoing Costs
Technology/software — $6,590 $6,590 —
CCGI — 3,777 3,777 —
Admininstration/GovOps staffd — 2,473 2,473 —
CalPADS integratione — 1,702 1,702 —
Data staff for data providers — 750 750 —
Totals — $15,292 $15,292 —f
a
The section letter would authorize some spending in the last quarter of the 2020-21 fiscal year.
b
Costs would be supported with non-Proposition 98 General Fund, except for $3.8 million ongoing CCGI costs, which
would be supported with Proposition 98 General Fund.
c
Includes $100,000 for governing and advisory board meetings in 2021-22. Total funding for start-up administration
under this alternative approach could change depending on the specific staff and activities the Legislature were to
decide to authorize.
d
The administration proposes creating a “Cradle to Career” office within GovOps. Proposed funds would support
12 GovOps staff in 2021-22, growing to 16 staff in 2022-23.
e
The Department of Finance characterizes these costs as primarily related to the development of the integrated
education data system, with some funding supporting the CCGI project.
f
Under the LAO Alternative, ongoing costs would be funded once the project has entered the PAL process, better cost
estimates are available, and the administration has submitted a future corresponding budget request.
CCGI = California College Guidance Initiative; GovOps = Government Operations Agency; CalPADS = California
Longitudinal Pupil Achievement Data System; and PAL = Project Approval Lifecycle.
LAO Publications
This report was prepared by Paul Steenhausen, with major contributions from Brian Metzker, and additional support
from Chas Alamo and Amy Li. It was reviewed by Jennifer Pacella and Anthony Simbol. The Legislative Analyst’s Office
(LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
2021-22 LAO Budget Series 11