AN LAO REPORT
Addressing Capital Renewal at UC and CSU
GABRIEL PETEK | LEGISLATIVE ANALYST | JANUARY 2023
SUMMARY
Capital Renewal Needs at the Universities Are Large and Growing. Capital renewal refers to the
replacement of building components (such as roofs and heating systems) that are at the end of their useful
life. Over the next ten years, the University of California (UC) projects $12 billion in capital renewal needs
will emerge across its academic facilities, while the California State University (CSU) projects $3.1 billion
in emerging capital renewal needs. If these needs are not addressed, the segments’ existing backlogs
of deferred maintenance will grow. These backlogs currently are estimated to total $7.3 billion at UC and
$6.5 billion at CSU.
No Plan Is in Place to Address Identified Capital Renewal Needs. Capital renewal spending at
UC and CSU has been insufficient to keep pace with emerging needs. Some campuses designate little,
if any, ongoing funding from their base budgets for capital renewal, instead relying heavily on one-time
state funding to address backlogs. State funding has been episodic, with large amounts provided in some
years and none in other years. In addition, as UC and CSU continue to expand their academic space,
no process is in place to account for the future capital renewal needs of new facilities. Absent a plan to
address these issues, backlogs very likely will continue to grow—leading to higher costs and greater risk of
programmatic disruptions.
Recommend Legislature Take Several Actions to Plan for Capital Renewal. First, we recommend the
Legislature develop a plan to address anticipated UC and CSU capital renewal needs as they emerge. Such
a plan would involve several key elements, including setting a funding target that is aligned with emerging
needs, sharing the cost between the state and the segments, and phasing in funding increases over time.
Second, we recommend the Legislature adopt a companion plan to reduce UC’s and CSU’s existing
backlogs to a target level within a set time period. Third, we recommend requiring UC and CSU to identify
funding for the future capital renewal costs of any proposed new academic facilities. Fourth, we recommend
requiring UC and CSU to report annually on their facility conditions, among other related topics.
Several Additional Issues for Legislature to Consider. Although the state likely will face budget
constraints in 2023-24, the Legislature can take important steps to begin the capital renewal planning
process. In doing so, we encourage the Legislature to consider the trade-offs between providing more
funding for capital renewal versus other purposes—including the segments’ operating costs, the construction
of new academic facilities, and support for nonacademic facilities (such as student housing). The Legislature
could also consider reassessing the need for UC and CSU to maintain their current footprints, particularly
given the recent expansion of online instruction. Finally, the Legislature may also wish to begin planning for
the capital renewal needs of other state agencies in addition to UC and CSU.
www.lao.ca.gov 1
AN LAO REPORT
INTRODUCTION frequent. In this brief, we first provide background
on capital renewal at the segments, next assess
The University of California (UC) and California
the current approach to addressing their capital
State University (CSU) have many academic
renewal needs, then make recommendations to
facilities. As these facilities age, their building
better plan and budget for capital renewal moving
components eventually need to be replaced.
forward, and finally raise other related issues for the
Replacing these components is commonly referred
Legislature to consider.
to as capital renewal. When capital renewal needs
are not addressed as they emerge, campuses
BACKGROUND
accumulate backlogs commonly referred to as
deferred maintenance. Capital renewal costs at In this section, we introduce information needed
UC and CSU are large and growing, with more to understand capital renewal at UC and CSU,
projects added to their backlogs each year. provide the segments’ estimates of their capital
Neither the state nor the segments currently renewal needs, and discuss how the segments
have a plan for covering these costs. Without a currently budget for capital renewal. The nearby
plan, facility conditions will likely deteriorate and box provides definitions of key terms used
programmatic disruptions could become more throughout this brief.
Glossary of Key Terms
In this brief, we use the following facility-related terms.
• Academic Facilities. Buildings that contain space supporting the segments’ core academic
missions. Examples of such space include classrooms, laboratories, and faculty offices.
• Infrastructure. Physical assets that support multiple facilities. Examples include central
plants, utility distribution systems, and pedestrian pathways.
• Capital Renewal. The periodic replacement of building components (such as roofs and
heating systems) that have reached the end of their useful life. Campuses can address
capital renewal in various ways, including replacing individual building components,
renovating an entire facility, or demolishing a facility and constructing a replacement for it.
• Deferred Maintenance. The backlog of capital renewal projects that accumulates when
building components are not replaced at the end of their useful life.
• Current Replacement Value (CRV). The estimated cost of replacing any given facility
or group of facilities today. CRV is a common measure of the value of a campus’s
physical assets.
• Facility Condition Index (FCI). A measure of the condition of any given facility or group of
facilities. The FCI for a facility is calculated by dividing its deferred maintenance backlog by
its CRV. For example, a facility with a $20 million backlog and a $100 million CRV would have
an FCI of 0.20. The smaller the FCI, the better the facility condition, with an FCI below 0.05
commonly considered good and an FCI above 0.10 considered poor.
• Routine Maintenance. Maintenance activities that occur on a regular basis, including
inspecting, servicing, and undertaking minor repairs of building components. Inadequate
routine maintenance can lead building components to reach the end of their useful life
prematurely, thereby increasing capital renewal needs and costs.
• Operations and Maintenance (O&M). The day-to-day activities required to use facilities
and keep them in good condition. Examples of O&M costs include routine maintenance,
utilities, and custodial services.
2 LEGISLATIVE ANALYST’S OFFICE
AN LAO REPORT
Understanding Capital Renewal When campuses do not adequately address routine
maintenance, building components can reach the
UC and CSU Have Many Academic Facilities,
end of their useful life prematurely, further increasing
Along With Associated Infrastructure.
capital renewal needs. Routine maintenance and
Traditionally, the state has funded the segments’
other day-to-day facility costs (such as utilities and
academic facilities, including classrooms,
custodial services) are commonly referred to as
laboratories, and faculty offices. UC has about
“operations and maintenance” (O&M) costs. UC and
63 million square feet of academic facilities across
CSU campuses fund O&M costs from their operating
its ten campuses and other sites. The current
budgets. Campuses often plan for increased O&M
replacement value (CRV) of those facilities totals
costs when adding new academic space. For
about $39 billion. CSU has about 43 million
example, CSU annually designates a portion of its
square feet of academic facilities across its
state General Fund base budget augmentation for
23 campuses, and the CRV of those facilities
the O&M of new facilities, allocating these funds to
totals about $23 billion. In addition to academic
campuses based on their share of newly opened
facilities, the state funds a notable amount of
square footage. While UC does not centrally
campus infrastructure, such as central plants, utility
designate a portion of its base budget augmentation
distribution systems, and pedestrian pathways.
for O&M, campuses may choose to use some of
(Though not a focus of this brief, campuses also
their allocation for this purpose.
have self-supporting facilities, such as student
housing, parking structures, certain athletic facilities, UC and CSU Report Certain Information on
and student unions. These types of facilities typically Capital Projects. Under state law, UC and CSU
generate their own fee revenue, which covers are to submit capital outlay plans to the Legislature
associated capital and operating costs.) by November 30 each year. Specifically, these
plans are to identify the projects proposed for each
Facilities Require Periodic Capital Renewal.
campus over the next five years. Depending on
UC reports that nearly 60 percent of its academic
the segments’ objectives over any given five-year
space is at least 30 years old. Similarly, CSU reports
period, these plans might have a different mix of
that more than half of its academic facilities are at
capital renewal and new construction projects.
least 40 years old. As facilities age, their building
Though these plans specify projects proposed
components eventually reach the end of their useful
over the near term, they are not required to include
life and need to be replaced. For example, within
a comprehensive estimate of the segments’
a given facility, a roof might need to be replaced
capital renewal needs, including their backlogs.
after 30 years. The cost of capital renewal projects
In addition to requiring the five-year capital outlay
can vary widely, with costs ranging from tens of
plans, state law requires UC and CSU to submit
thousands of dollars for smaller projects to tens
detailed proposals for any capital outlay projects
of millions of dollars for larger projects. If aged
they intend to fund in the next year using their main
building components are not replaced, they can
General Fund appropriation. The administration and
start malfunctioning or stop working altogether. In
Legislature generally review these proposals during
some cases—such as a leaking roof—not replacing
the annual budget process.
an aged building component can result in new
problems that increase costs. When campuses
Identifying Capital Renewal Needs
do not address capital renewal as the need
UC Is Developing a Systemwide Facility
emerges, they accumulate a backlog of deferred
Condition Assessment Program. Historically,
maintenance projects.
UC campuses each measured their capital renewal
Facilities Also Require Routine Maintenance.
needs using their own approaches. Several years
Whereas capital renewal refers to the periodic
ago, UC began developing the Integrated Capital
replacement of key building components, routine
Asset Management Program (ICAMP) to obtain more
maintenance refers to activities that tend to occur on
comprehensive and consistent data systemwide.
a more regular basis. For example, these activities
Under ICAMP, both external consultants and
may include inspection, servicing, and minor repairs.
www.lao.ca.gov 3
AN LAO REPORT
campus staff maintain UC’s facility
condition assessment data, with the
Figure 1
specific responsibilities of the external
consultants and internal staff varying by Projected Capital Renewal Needs Vary by Campus
campus. Though ICAMP currently includes
Average Annual Renewal Needs (In Millionsª)
data on UC’s academic facilities, UC
remains in the midst of collecting data Different Scales Used for UC and CSU Charts
on related infrastructure (such as central UC
plants). In December 2021, UC submitted
Berkeley
a one-time report to the Legislature on
Los Angeles
its capital renewal needs for academic
Davis
facilities. The UC data in this section San Diego
comes from that report. Irvine
Santa Barbara
CSU Also Has a Systemwide Facility
Santa Cruz
Condition Assessment Program.
Riverside
CSU has measured its systemwide capital
San Francisco
renewal needs for many years. In 2017-18,
Merced
it improved its approach by incorporating
50 100 150 200 250 300 $350
more granular data on facility conditions.
CSU
Under this approach, consultants from an
external vendor are expected to conduct San Jose
on-site facility condition assessments Long Beach
at each campus once every five years. Northridge
Between external assessments, campus Fullerton
staff are expected to update their San Diego
facility condition assessment data on San Luis Obispo
a regular basis. In contrast to UC, CSU Pomona
already has collected data not only on San Francisco
San Bernardino
its academic facilities but also on related
Fresno
infrastructure. CSU annually reports
Sacramento
its capital renewal needs for academic
Sonoma
facilities and infrastructure in its five-year
Los Angeles
capital outlay plan. The CSU data in this
Chico
section comes from the five-year capital
San Marcos
outlay plan submitted to the Legislature in
Humboldt
November 2022.
Dominguez Hills
UC and CSU Project Large Capital Channel Islands
Renewal Needs Emerging Annually. Stanislaus
UC projects $12 billion in capital renewal Monterey Bay
needs will emerge across its academic Bakersfield
facilities over the next ten years, equating East Bay
to an average of $1.2 billion in capital Maritime
renewal projects emerging each year. 5 10 15 20 25 30 35 $40
CSU projects $3.1 billion in capital
a The segments calculate their average annual renewal needs across the next ten years. We use the most recently
renewal needs will emerge across its available data from each segment. UC data comes from a December 2021 report and it includes academic facilities
only. (UC's infrastructure assessment is still in progress.) CSU data comes from a November 2022 report, and it
academic facilities and infrastructure includes both academic facilities and infrastructure.
over the next ten years, equating to an
average of $313 million annually. Figure 1
4 LEGISLATIVE ANALYST’S OFFICE
AN LAO REPORT
shows projected annual renewal
needs by campus. Across all UC and
Figure 2
CSU campuses, annual renewal needs
range from about $1 million (at UC Many UC and CSU Campuses
Merced) to $318 million (at UC Berkeley).
Have Poor Facility Conditions
This variation likely reflects differences
Estimated Facility Condition Index by Campusª
among campuses in the number, size,
age, complexity, and location of their
UC
facilities, among other factors. For
example, a large campus with older San Francisco
facilities and extensive research space is Los Angeles
likely to have costlier renewal needs than Irvine
Riverside
a small campus with newer facilities and
Santa Cruz
little research space.
Santa Barbara
UC and CSU Also Have Large Davis
Existing Backlogs of Capital Renewal San Diego
Projects. At both segments, the renewal Berkeley
Merced
needs emerging each year are on top of
large backlogs of deferred maintenance 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40
Good Fair Poor
projects. UC estimates it has a
$7.3 billion backlog associated with its CSU
academic facilities and infrastructure,
East Bay
while CSU estimates it has a $6.5 billion
San Francisco
backlog. Figure 2 shows each campus’s
San Jose
backlog for academic facilities,
Humboldt
divided by the CRV of those facilities. Bakersfield
This metric is commonly known as Sacramento
the facility condition index (FCI), with Chico
a lower index score reflecting better Fresno
facility conditions. We estimate more Los Angeles
Pomona
than half of UC campuses and nearly
San Diego
all CSU campuses have an FCI above
San Luis Obispo
0.10, which is typically considered an
Sonoma
indication of poor facility conditions.
Long Beach
Backlogs Have Grown Significantly Fullerton
in Recent Years. From 2017-18 to Northridge
2022-23, CSU’s backlog for academic Maritime
facilities and infrastructure grew by San Bernardino
Dominguez Hills
$2.4 billion (60 percent). UC indicates
Stanislaus
that its backlog has also grown over
San Marcos
time, though data tracking these
Monterey Bay
changes was not available. In recent
Channel Islands
years, three main factors have driven
0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40
growth in the segments’ backlogs.
Good Fair Poor
First, additional building components
a Reflects deferred maintenance backlog for academic facilities divided by their current replacement value (CRV).
have reached the end of their useful life. The backlog and CRV estimates exclude infrastructure. We use the most recently available data from each
segment. UC data comes from a December 2021 report. CSU data comes from a November 2022 report.
Second, as the segments improve their
facility condition assessment programs,
some building components that were
www.lao.ca.gov 5
AN LAO REPORT
not previously tracked have been newly added UC and CSU Also Debt Finance Capital
to their data systems. Third, the backlogs have Renewal Projects. Since 2013-14 and 2014-15,
been adjusted upward to reflect construction cost respectively, the state has authorized UC and
escalation, which—reflecting broader inflationary CSU to issue university bonds for capital outlay
pressures—has been particularly high over the projects, then pay the associated debt service
past two years. Growth from these three factors from their main General Fund appropriations.
has outpaced the rate at which the segments are These debt-service payments are in addition to
completing capital renewal projects, as this is other base funding that the segments decide to
limited by available funding and other factors. As use for capital renewal projects in any given year.
a result, the segments have seen net increases in While the segments may use debt financing for
their backlogs over time. smaller projects (such as roof replacements), they
often also use it for larger projects. For example,
Budgeting for Capital Renewal
the segments typically debt finance entire facility
Campuses Have Discretion Over Capital renovation projects as well as projects that entail
Renewal Budgeting. State law does not require demolishing an aging facility and replacing it.
UC and CSU to budget certain amounts for capital Such projects often address capital renewal while
renewal each year. Moreover, UC does not have also making other facility improvements, such as
an internal systemwide policy on how much its seismic upgrades or classroom enhancements.
campuses are to budget annually for capital We estimate UC has used university bonds to
renewal, effectively leaving these decisions to finance roughly $1.1 billion in projects that renew or
the discretion of the campuses. Under CSU’s improve existing facilities since 2013-14, equating
internal systemwide policy on facility maintenance, to an average of about $110 million in projects
campus presidents are responsible for ensuring annually. Similarly, we estimate CSU has used
that “appropriate resources” are directed toward university bonds to finance roughly $1.8 billion in
capital renewal. The long-term goal of CSU’s policy projects that renew or improve existing facilities
is to eliminate deferred maintenance. CSU’s policy, since 2014-15, equating to an average of about
however, does not set a minimum level of spending $200 million annually. Based on the available data,
for capital renewal or otherwise specify what we cannot determine the share of these funds that
amount of resources is considered appropriate at went specifically for capital renewal versus other
each campus. facility improvements.
Campuses Use Some Ongoing Base Funding UC and CSU Also Use Reserves for Capital
for Capital Renewal Projects. Some campuses Renewal. UC and CSU maintain reserves for
choose to designate annual funding for capital various purposes, including to save for large future
renewal projects from their base budgets (that is, expenses and prepare for economic downturns.
their ongoing, unrestricted core funding). At both Campuses commonly use a portion of their
segments, these funds primarily consist of state reserves to support capital renewal. Campuses
General Fund and student tuition revenue, with may use their reserves to pay for a planned capital
a small portion coming from other fund sources. renewal project or an emergency repair. They also
Systemwide data is not available on how much may use their reserves to provide matching funds
UC and CSU campuses are spending annually from for a major project financed through university
their base budgets on capital renewal projects. bonds. (CSU encourages campuses to cover about
Based on conversations with both segments, the 10 percent of the cost of these projects using
amounts vary from campus to campus and tend reserves.) Systemwide data is not available on how
to be much smaller than their emerging capital much UC and CSU are spending annually from their
renewal needs. The amounts that campuses reserves on capital renewal.
dedicate to capital renewal also can fluctuate with
CSU Recently Began Using Investment
fiscal conditions. Notably, campuses may choose
Earnings for Capital Renewal. UC and CSU
to reduce capital renewal spending from their base
place some unspent funds in various investment
budgets in years when the state reduces funding for
accounts. In 2018, CSU established a new
UC and CSU.
6 LEGISLATIVE ANALYST’S OFFICE
AN LAO REPORT
investment account called the Total Return maintenance projects in 2020-21, when it was
Portfolio (TRP). Funds in this account are invested anticipating a significant budget problem due to
in certain types of assets (such as mutual funds) the COVID-19 pandemic. The state then provided
in which CSU did not previously invest. Under $325 million in one-time funds to each segment just
state law, CSU may only use TRP earnings for one year later in 2021-22, when it had a significant
one-time capital expenses, including renewal. budget surplus.
Since CSU began distributing TRP earnings in
2019-20, it has allocated an average of $40 million ASSESSMENT
annually to campuses for capital expenses,
In this section, we assess the current approach
with distributions varying somewhat from year
to addressing capital renewal at UC and CSU.
to year based on investment performance. UC
Data on UC and CSU Capital Renewal Needs
has a similar investment account called the Total
Has Improved. Over the past several years,
Return Investment Pool (TRIP). However, state law
both segments have taken steps to improve the
does not restrict the use of UC TRIP earnings to
consistency and comprehensiveness of their facility
capital expenses, and data is not available on how
condition assessment data. The state now has data
much funding from this source has gone toward
from UC and CSU quantifying their capital renewal
capital renewal.
needs for academic facilities and (to a lesser extent)
State Has Provided Significant One-Time
infrastructure. Compared to the previously available
Funding to Address Backlogs. Despite the
data, the current data is more useful for planning
various fund sources the segments are using for
and budgeting. Opportunities remain for both the
capital renewal projects each year, backlogs have
state and the segments to use the data for these
accumulated over time. Over the years, the state
purposes. For example, the state could use the
has sometimes provided General Fund to UC
data to better align funding with identified needs as
and CSU to address these backlogs. In 2015-16,
well as monitor the segments’ progress in improving
after several years of providing no new funding
facility conditions.
for deferred maintenance projects, the state
State Lacks Comprehensive Data on Capital
resumed providing one-time funds for this purpose.
Renewal Spending. In contrast to the improved
Since then, the state has provided an average
data on UC and CSU capital renewal needs, the
of $86 million annually to UC and $98 million
segments’ data on capital renewal spending still
annually to CSU for deferred maintenance projects
has notable limitations that make it difficult to use
and related purposes (such as energy efficiency
for planning and budgeting. Most significantly,
projects and seismic upgrades). As Figure 3
the segments do not comprehensively track their
shows, these allocations have varied significantly
capital renewal spending across all fund sources.
from year to year, partly reflecting changes in the
For example, CSU’s data on capital renewal
state’s budget condition. For example, the state
spending does not include bond funding for major
provided no funds to UC and CSU for deferred
capital renewal projects, while UC’s data does not
Figure 3
State Funding for Deferred Maintenance Projects Varies From Year to Year
One-Time General Fund (In Millions)
2015-16 2016-17 2017-18 2018-19 2019-20a 2020-21 2021-22b 2022-23c
UC $25 $35 — $35 $144 — $325 $125
CSU 25 35 — 35 239 — 325 125
a Amount for CSU was provided for deferred maintenance or campus-based child care facilities. The 2020-21 budget package allowed UC and CSU to
repurpose unspent 2019-20 deferred maintenance funds for other operational purposes.
b Amounts for UC and CSU were provided for deferred maintenance or energy efficiency projects.
c Amounts for UC and CSU were provided for deferred maintenance, seismic upgrades, or energy efficiency projects.
www.lao.ca.gov 7
AN LAO REPORT
include smaller projects supported by one-time Without Additional Planning, Backlogs Will
state funding or campus base budgets. Without Very Likely Continue to Grow. Although the
this information, the Legislature cannot measure data on capital renewal spending at UC and CSU
the gap between the segments’ emerging capital is limited, it suggests that current spending is
renewal needs and their current spending. Because insufficient to keep pace with capital renewal needs
the spending data is not tracked by fund source, as they emerge. Moreover, the continued expansion
the Legislature also cannot determine how much of academic space will further add to capital
campuses are relying on one-time state funding for renewal needs in the long term. Absent a plan to
capital renewal versus ongoing amounts designated address the future capital renewal costs associated
from their base budgets. Moreover, the segments’ with both existing and new facilities, backlogs very
spending data does not allow the Legislature likely will continue to grow moving forward.
to separate spending on capital renewal from As Backlogs Grow, Fiscal and Programmatic
spending on other facility improvements (such as Consequences Could Become More Serious.
seismic upgrades or classroom enhancements). At campuses with growing backlogs, aged building
No Plan Is in Place to Address Identified components could require more frequent servicing,
Capital Renewal Needs. Although both segments as well as costly emergency repairs. Moreover,
have notable capital renewal needs in any given building components past their useful life can
year, neither the state nor the segments have a create poorer learning and working conditions,
plan to address these needs as they emerge. with the potential for programmatic disruptions
Some campuses indicate little, if any, ongoing funds when systems fail. Based on conversations with the
are dedicated in their base budgets for capital segments and stakeholders, some programmatic
renewal, suggesting they rely heavily on one-time disruptions already are occurring. Recent examples
state funding. Meanwhile, one-time state funding include inadequate ventilation leading to overheated
for capital renewal has been episodic, with large classrooms as well as frequent flooding within
amounts sometimes provided when the state buildings affecting faculty research. These types
budget has a surplus versus no funds provided in of facility issues could affect the recruitment
other years. With such volatility, campuses have and retention of students, faculty, and staff. Left
difficulty planning for capital renewal projects in unaddressed, these types of issues could also pose
advance and putting in place adequate staffing to health and safety concerns.
implement those projects.
No Process Is in Place for Assessing RECOMMENDATIONS
the Full Cost of New Facilities. The current In this section, we make recommendations
process for proposing new academic facilities at related to planning and budgeting for UC’s and
UC and CSU does not fully account for the future CSU’s ongoing capital renewal needs, existing
costs associated with those facilities. Although backlogs, and future needs associated with new
campuses commonly plan for the increased facilities. We then focus on improving how the
day-to-day O&M costs of opening new academic Legislature monitors progress in addressing UC’s
space, they generally do not plan for the capital and CSU’s capital renewal needs.
renewal costs that will emerge in future years as
building components age. This contrasts with the Addressing Ongoing
approach taken with self-supporting facilities. When Capital Renewal Needs
campuses propose new student housing facilities,
Adopt Funding Plan to Address UC and
for example, they are often expected to develop
CSU Capital Renewal on Ongoing Basis.
a plan to cover future capital renewal costs using
We recommend the Legislature develop a plan for
project revenues. In recent years, a few other states
the state and the segments to fund capital renewal
(including Florida and Nebraska) have also begun
needs as they emerge. Below, we describe the
to require public universities to identify funding for
key elements of such a plan. Figure 4 shows an
the future capital renewal costs of academic capital
illustrative plan incorporating these elements.
outlay projects.
8 LEGISLATIVE ANALYST’S OFFICE
AN LAO REPORT
Set Ongoing Funding Target. The Legislature UC projects its average annual renewal needs
could consider setting the annual ongoing funding are $1.2 billion, which is somewhat higher than
target based on the CRV of each segment’s the illustrative target. CSU projects its average
facilities—a metric that UC and CSU are already annual renewal needs are $313 million, which is
tracking. Under a commonly cited best practice, somewhat lower than the illustrative target. The
campuses are to allocate an amount equal to main advantage of using a funding target linked to
2 percent to 4 percent of their CRV annually for a percentage of CRV is the consistency it provides
capital renewal and routine maintenance. In the not only across the segments but also over time.
illustrative plan in Figure 4, we set the annual Linking to a percentage of CRV also would better
funding target for capital renewal at 2 percent of facilitate planning activities and could reduce
each segment’s CRV. (We assume the segments volatility in capital renewal funding from year to year.
would fund routine maintenance separate from Share Cost Between State and Segments.
this target.) We estimate that 2 percent of CRV Given the magnitude of their capital renewal needs,
is $839 million at UC and $474 million at CSU in UC and CSU very likely would need additional state
2023-24, with the amount increasing annually due support to address these needs as they emerge.
to construction cost escalation. (Our estimates After setting a capital renewal funding target, the
assume 3.4 percent annual cost escalation, based Legislature could provide ongoing General Fund
on the historical annual average growth rate in the augmentations to cover a certain share of that
California Construction Cost Index since 1979, target, then set an expectation that the segments
a sufficiently long period to encompass spans cover the remaining share from other sources.
of high and low inflation rates.) For comparison,
Figure 4
Illustrative Funding Plan for UC and CSU Capital Renewal
(Dollars in Millions)
2023-24 2024-25 2025-26 2026-27 2027-28
UC
Funding Level
Funding target (2 percent of CRV)a $839 $868 $897 $928 $960
Phase-in percentage 20% 40% 60% 80% 100%
Totals $168 $347 $538 $742 $960
Funding by Sourceb
General Fund augmentation (45 percent) $76 $156 $242 $334 $432
UC share (55 percent) 92 191 296 408 528
Totals $168 $347 $538 $742 $960
CSU
Funding Level
Funding target (2 percent of CRV)a $474 $490 $507 $524 $542
Phase-in percentage 20% 40% 60% 80% 100%
Totals $95 $196 $304 $419 $542
Funding by Sourceb
General Fund augmentation (60 percent) $57 $118 $182 $251 $325
CSU share (40 percent) 38 78 122 168 217
Totals $95 $196 $304 $419 $542
a Assumes CRV increases by 3.4 percent annually, based on historical average growth in California Construction Cost Index.
b These illustrative cost shares are based on the approximate share of each segment’s total ongoing core funding that comes from state General Fund versus
other sources.
CRV = current replacement value.
www.lao.ca.gov 9
AN LAO REPORT
Any current ongoing funding designated by the from the building industry to perform the design and
segments from their base budget or other sources construction work. The illustrative plan in Figure 4
could count toward the segments’ share. To meet phases in funding increases evenly over five
the remaining expectation, the segments could years—reaching the funding targets the last year
increase the amount designated from their base of the period. (Though the illustrative plan phases
budget, either by (1) allocating new revenue from in funding increases beginning in 2023-24, the
General Fund base augmentations and any tuition Legislature could schedule the phase in to begin at
increases or (2) redirecting existing funding from a later time.) Once the funding targets are reached,
other purposes. The segments could use these the illustrative plan assumes the state would
ongoing funds to pay for capital renewal projects maintain funding for capital renewal (with annual
in cash or to debt finance these projects using adjustments for cost escalation) moving forward.
university bonds. In addition, the segments could To avoid future funding reductions, the state could
continue to fund some projects using reserves, build up its reserves sufficiently such that it could
investment earnings, or other sources (such as continue providing its share of the capital renewal
donor funds). funding target even during a recession.
Consider Various Factors When Setting Cost Provide Guidance on Project Prioritization
Shares. In determining an appropriate expectation During Phase In. During the phase-in period,
for the segments’ share of the capital renewal annual funding for capital renewal would not keep
funding target, the Legislature could consider pace with emerging needs, and some projects
each segment’s capital renewal needs, other cost would continue to be added to the backlog. To
pressures, access to nonstate funds, and debt mitigate the negative consequences of a growing
capacity. Based on these factors, the state could backlog, the Legislature could direct UC and
potentially set different expectations for UC and CSU to prioritize certain types of projects with
CSU. In the illustrative plan in Figure 4, state available funding. For example, the segments
General Fund augmentations cover 45 percent could be directed to prioritize projects that address
of the funding target at UC and 60 percent of the potential health and safety issues, reduce the risk
funding target at CSU, with the segments covering of programmatic disruptions, avoid the need for
the remaining share from other sources. These costlier repairs in the future, and reduce ongoing
illustrative amounts are based on the approximate operational costs.
share of each segment’s total ongoing core
Addressing Existing Backlogs
funding that comes from state General Fund versus
other sources. Use Additional One-time Funding to Reduce
Existing Backlogs. Beyond developing a plan to
Phase In Funding Increases Over Several
address emerging capital renewal needs at UC and
Years. In light of broader budget conditions and
CSU, we recommend the Legislature adopt a
other cost pressures, the state and the segments
companion plan to reduce the existing backlogs to
very likely will not have sufficient resources to reach
a target level within a set time period. For example,
the capital renewal funding targets in the first year
the Legislature could set the target level at an
of the plan. The Legislature could phase in funding
FCI of 0.05—the threshold below which facilities
increases to reach the targets over several years.
are commonly considered to be in good condition.
Such an approach would give the state and the
To reduce the backlogs to this level, the Legislature
segments more time to identify available funding
could continue using one-time state funding. If the
and make other budget adjustments. Phasing in
UC and CSU backlogs were reduced to a target
funding increases gradually would also allow the
FCI of 0.05 over a ten-year period, we estimate the
segments more time to build the administrative
average annual cost would be about $935 million
capacity to complete a higher volume of projects
and $750 million, respectively. (Consistent with
each year. This additional capacity would likely
our illustrative ongoing funding plan, our one-time
entail campuses increasing their staffing for project
funding estimates assume 3.4 percent annual cost
management as well as identifying additional labor
10 LEGISLATIVE ANALYST’S OFFICE
AN LAO REPORT
escalation, as well as growth in the backlog due to • Projected additional capital renewal needs
the ongoing funding target being phased in over over the next ten years, by campus.
five years.) These costs to address the existing • Total annual spending on capital renewal, by
backlogs would be on top of the ongoing funding fund source.
target. As with the ongoing funding target, costs
• Total reserves for future capital renewal, by
to address the existing backlog could be similarly
fund source.
shared between the state and the segments.
Require UC and CSU to Report Annually on
Addressing Capital Renewal Use of State Capital Renewal Funds. As the
Needs of New Facilities Legislature provides additional funding to UC and
CSU to address their capital renewal needs,
Require UC and CSU to Plan for Future Costs
we recommend it adopt provisional language
of New Facilities. We recommend the Legislature
requiring the segments to report on the projects
require the segments to identify funding for the
they undertake with those funds. The Legislature
future capital renewal and O&M costs of proposed
typically has adopted this type of language when
new academic facilities. These components
providing funding for deferred maintenance
could become a required part of the capital outlay
projects. Adopting similar language moving forward
project proposals that the segments submit to
would help the Legislature ensure that state funds
the state each year. The segments might plan to
go towards what it deems the highest priority
cover capital renewal costs of new facilities in
projects. This is particularly important if funding for
various ways. For example, a campus could plan
capital renewal remains insufficient to fully address
to reserve funding annually from its base budget
needs, as the segments would need to triage
during the lifecycle of the facility, or it could raise
among potential projects.
additional donor funds at the outset of the project.
Beyond requiring the segments to identify funding,
OTHER ISSUES TO CONSIDER
the Legislature could further consider requiring
campuses to deposit the funds into a restricted In this section, we raise a few additional issues
account to ensure they are available when building for the Legislature to consider.
components need to be replaced. Even With Constrained State Budget,
Legislature Could Take Important Steps in
Monitoring Progress on Capital
2023-24. In The 2023-24 Budget: California’s
Renewal
Fiscal Outlook, we project the state faces a
Require UC and CSU to Report Annually $24 billion budget problem. Although this means
on Facility Conditions. We recommend the the Legislature would not have budget capacity to
Legislature require UC and CSU to annually report provide more funding to UC and CSU for capital
the data listed below for their academic facilities renewal, it still could take steps toward addressing
and infrastructure. This data would allow the the segments’ capital renewal needs. Without
Legislature to monitor the segments’ progress in up-front state costs, the Legislature could begin
addressing capital renewal as well as determine requiring UC and CSU to report annually on
whether the associated state funding is having their facility conditions so that it has up-to-date
the intended effect. The segments could report information for planning and oversight purposes.
this information as part of their existing five-year The Legislature also could begin requiring UC
capital outlay plans. (Though UC and CSU currently and CSU to plan for the future cost of any new
report some of this information, neither segment academic facilities that they propose to fund using
provides all this information regularly as part of its their main General Fund appropriations moving
five-year plan.) forward. Moreover, the Legislature could begin the
process of developing plans to address UC’s and
• Facility square footage and CRV, by campus.
CSU’s ongoing capital renewal needs and existing
• Deferred maintenance backlog and FCI,
backlogs, as this process would involve making
by campus.
www.lao.ca.gov 11
AN LAO REPORT
several key decisions (including setting the ongoing Legislature Could Revisit UC and CSU
funding target, the segments’ share of costs, the Footprints. Throughout this brief, we assume the
phase-in time line, and the target FCI) before any Legislature wants to keep UC’s and CSU’s existing
funding is provided to implement the plan. In the academic facilities in good condition—replacing
coming months, if the budget outlook were to their components at the end of their useful life.
improve such that some funding could be allocated The Legislature, however, could take a different
for new purposes in 2023-24, the Legislature approach and carefully reassess the need for each
could consider providing one-time funding to academic facility as it ages. Some of the impacts
UC and CSU to address their existing backlogs. of the pandemic on higher education, including the
Given the size of the backlogs and the growing greater reliance on online courses, will likely have
potential for programmatic disruptions, we would long lasting impacts on how UC and CSU use their
encourage the Legislature to make the segments’ facilities. Given these impacts, campuses might
deferred maintenance projects a high priority for not require the same amount or types of academic
one-time funds. space moving forward. (Beyond impacting capital
Funding UC and CSU Capital Renewal renewal costs, revisiting the amount and type of
Involves Difficult Trade-Offs. Even when the academic space at UC and CSU could lead to
state has budget capacity for new commitments, changes in the campus experience for students.)
the Legislature faces several key trade-offs in Decisions about future growth are particularly
planning for capital renewal. One trade-off involves significant given the magnitude of the outstanding
providing more funding for capital renewal versus capital renewal needs at UC and CSU. Just as
the segments’ other operating costs. These other adding new space eventually leads to increased
operating costs, including employee compensation, capital renewal costs, reducing existing space can
are also increasing. Importantly, decisions about lead to lower capital renewal costs in the long term.
both capital renewal and employee compensation Other State Agencies Also Have Capital
can affect student, faculty, and staff recruitment Renewal Needs. Like UC and CSU, many other
and retention. Another trade-off involves providing state agencies have notable deferred maintenance
more funding for projects that renew existing backlogs as well as emerging capital renewal needs
facilities versus add new space. This trade-off is in the coming years. Similar to UC and CSU, these
heightened because adding new space leads to other agencies likely will face higher costs, poorer
increased capital renewal needs and operating working conditions, and programmatic disruptions
costs over the long term. The Legislature also if their capital renewal needs go unaddressed.
faces a trade-off between funding academic The Legislature may wish to begin planning and
facilities versus traditionally self-supporting budgeting for the capital renewal needs of these
facilities, such as student housing. While funding other agencies too. With limited funding, the
facilities such as student housing can promote Legislature faces a trade-off between prioritizing
valuable policy objectives (such as a reduction in capital renewal at UC and CSU versus at other
student homelessness or an increase in student agencies (such as court houses and prisons).
engagement), it leaves less budget capacity to This trade-off is heightened because some other
support academic facilities. This trade-off is state agencies have less access to nonstate
heightened because academic facilities, unlike funding, suggesting an even greater reliance on
self-supporting facilities, do not directly generate state General Fund in addressing their capital
revenue to cover their capital and operating costs. renewal needs.
Given these trade-offs are difficult and perennial,
the Legislature will want to take them into account
when developing a long-term budget plan like the
one we lay out in the “Recommendations” section
of this brief.
12 LEGISLATIVE ANALYST’S OFFICE
AN LAO REPORT
www.lao.ca.gov 13
AN LAO REPORT
14 LEGISLATIVE ANALYST’S OFFICE
AN LAO REPORT
www.lao.ca.gov 15
AN LAO REPORT
LAO PUBLICATIONS
This report was prepared by Lisa Qing, and reviewed by Jennifer Pacella and Anthony Simbol. The Legislative
Analyst’s Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service, are
available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000, Sacramento,
California 95814.