LAO
The 2023-24 Budget: California Department of Forestry and Fire Protection’s Major Capital Outlay Proposals
Read the report at Legislative Analyst's Office ↗
2023-24 BUDGET
The 2023-24 Budget:
California Department of Forestry and
Fire Protection’s Major Capital Outlay Proposals
GABRIEL PETEK | LEGISLATIVE ANALYST | FEBRUARY 2023
SUMMARY
In this brief, we analyze the California Department of Forestry and Fire Protection’s (CalFire’s) 2023-24
budget proposals related to two major capital outlay issues: a new training center and rebuilding an existing
conservation camp.
Initiate New Training Center. The Governor’s budget includes two related proposals focused on building
a new training facility: (1) funding for the study and acquisition phase of the proposed project to construct the
new facility, and (2) funding to support 12 new ongoing positions related to the center, as well as limited-term
funding to support costs associated with leasing and operating temporary training facilities. We recommend
the Legislature approve funding for the study—with a revised scope—to inform legislative decision-making
regarding whether and how to proceed with the project. We recommend rejecting the proposed funding for
the acquisition phase of the project since it would be premature to approve such costs before the project’s
study is complete and before a forthcoming master plan for one of the state’s main existing training centers
is available for legislative review. Additionally, we recommend rejecting the requested facility-related staff
positions since they are not adequately justified. Finally, we recommend approving some level of additional
funding for temporary training facilities but seeking additional information from CalFire to justify the
appropriate level.
Rebuild Growlersburg Conservation Camp. The Governor proposes funding the working drawings
phase of a capital outlay project to replace the facilities and infrastructure at the Growlersburg Conservation
Camp in El Dorado County. We recommend the Legislature reject the proposal for a few reasons. First,
the state may not need the Growlersburg Conservation Camp given the decline in the conservation camp
population and the existence of a California Conservation Corps (CCC) facility within close proximity. Second,
to the extent the state wants to retain a greater presence in the region than is provided by nearby CCC
facilities and conservation camps, whether a conservation camp would be the most appropriate facility is
not clear. Third, the costs of the project are much higher than anticipated. Fourth, the project is not a clear
priority—particularly in light of the General Fund condition—given that it currently is serviceable.
INTRODUCTION The Governor’s proposed budget for 2023-24
includes a total of $4 billion from various funds
CalFire Has Responsibilities for Both
to support CalFire, including $2.9 billion from
Wildland Fire Response and Forest
the General Fund. This represents an increase of
Management. CalFire has primary responsibility
about $150 million (roughly 4 percent) compared
for wildland fire response in State Responsibility
to the estimated expenditure level for 2022-23.
Areas, which are mostly privately owned wildlands
The Governor’s budget proposes to support
that encompass about one-third of the acreage of
11,500 authorized positions at CalFire in 2023-24,
the state. CalFire also has various responsibilities
which represents an increase of roughly 3 percent
for the management and protection of the state’s
from the estimated number in 2022-23.
forests. These include overseeing enforcement of
the state’s forest practices regulations, providing CalFire Operates Numerous Facilities.
grant funding for forest health and fire prevention CalFire operates more than 530 facilities statewide
projects, and regulating timber harvesting on to support its mission. These facilities include
private or state-owned forestland. 234 fire stations, 112 telecommunications
www.lao.ca.gov 1
2023-24 BUDGET
facilities, 8 fire crew camps, 21 unit headquarters, including firefighters, in recent years. For example,
16 administrative headquarters, 13 air attack the 2022-23 Budget Act added approximately
bases, and 10 helitack bases. As we discuss 1,500 positions (representing a 15 percent
in more detail in this brief, these facilities also increase compared to their previous staffing level),
include 30 conservation camps and two main approximately 850 of which the department reports
training centers. will require training prior to performing emergency
This Brief Includes Two Main response activities.
Sections. In the first section of this brief, we CalFire Is Undertaking a Master Plan for
analyze two proposals related to building a new CFTC-Ione Facility. The 2022-23 budget provided
training center: (1) funding for the study and $150,000 from the General Fund for CalFire to
acquisition phases of the proposed project to conduct a master plan for the CFTC-Ione facility,
construct the new facility, and (2) funding to support which was built in 1967. This document—expected
12 new ongoing positions related to the center, to be completed by May 2023—is intended to
as well as limited-term funding to support costs identify a specific plan for future capital outlay
associated with leasing and operating temporary projects to expand and update the facility to meet
training facilities. In the second section, we analyze CalFire’s current operational requirements.
a proposal to replace the facilities and infrastructure
Governor’s Proposals
at the existing Growlersburg Conservation Camp in
Georgetown, El Dorado County. The Governor’s budget includes two related
proposals, as described below.
NEW CALFIRE Proposes Funding to Study and Acquire Site
TRAINING CENTER FACILITY for New Facility. The Governor’s budget includes
$19.2 million from the General Fund for two capital
Background outlay activities related to building a proposed new
training facility: (1) $545,000 for a study that is
CalFire Operates Two Main Training Facilities.
anticipated to be completed in June 2024, which
CalFire currently operates two main training centers
would identify potential parcels in the Sacramento
for its staff. The first is CalFire Training Center
area on which to construct the facility and develop
(CFTC)-Ione, a state-owned facility in Amador
a more refined cost estimate for the project, and
County that historically has served as the primary
(2) $18.7 million to acquire a property for the new
training center for the department. The second is
center. The department anticipates needing a
CFTC-South, which is a leased facility in Riverside
minimum of 50 acres for the facility.
County. In recent years, CFTC-South has become
an important ongoing, year-round location for Future planned project phases include the
CalFire training. In addition to these facilities, preparation of performance criteria and the
CalFire also provides training at various other construction of the new proposed training center
sites, such as Castle Training Center in Atwater. using the design-build delivery method. The
These centers offer a variety of types of training. administration anticipates it would complete these
For example, the CFTCs host the Firefighter phases using a combination of General Fund
Academy and the Company Officer Academy, which (which it would request in a future year) and lease
are training courses required for classifications of revenue bonds (to be repaid from the General
Firefighter II (permanent firefighters) and above. Fund). In total, the estimated cost of the project is
In total, CalFire’s training programs train an average $419 million and construction is anticipated to be
of 2,900 students per year. completed in 2030.
CalFire Staffing Has Increased Substantially Funds Temporary Facilities and Operations
in Recent Years, Necessitating More Training. Costs, as Well as Ongoing Staff for Project
In part due to the recent severe fire seasons and Management and Maintenance. In addition to
projections that these trends will continue, the the capital outlay proposal, the Governor’s budget
state has significantly increased CalFire’s staffing, also includes a related state operations proposal
2 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
that requests a net increase of $12.9 million from Uses Some Existing Funding to Help Support
the General Fund and 12 new positions in 2023-24 Near-Term Training Costs. In addition to the new
($12 million annually through the completion of funding, CalFire also proposes to use a total of
the new training center facility—anticipated to be $5.8 million from 2022-23 funding augmentations
2030—and $3.4 million ongoing thereafter). These to—on a one-time basis—support the full costs
proposed resources include: of similar temporary activities to those discussed
above, such as equipment, leased vehicles,
• New Positions for Capital Outlay
and other operational costs. This $5.8 million
Project Management and Maintenance
represents a portion of the $214 million ongoing
($3.9 Million in 2023-24, $3.4 Million
General Fund originally provided for 17 new
Ongoing). This funding would support
firefighter crews and for staffing to support CCC
the hiring of 12 new positions, including
and California Military Department (CMD) crews.
surveyors, engineers, and a right-of-way
agent. These positions are proposed
Assessment
to (1) coordinate and consult with the
Uncertainty About Future Training Needs
Department of General Services (DGS) as
Results in Unclear Need for New Facility.
it manages the construction of the new
In our view, CalFire has not adequately justified
training center facility; (2) support the
that its ongoing training needs are sufficient to
development of future capital outlay projects
justify the construction of the new proposed
that might result from the CFTC-Ione
facility. Specifically, CalFire argues that the facility
master plan; and (3) engage in maintenance
is needed because of recent increases in demand
activities at training centers, particularly after
for training, driven in large part by the significant
the new proposed training center facility
number of new authorized positions approved
is constructed.
as part of the 2022-23 Budget Act. However, we
• Temporary Leased Facilities, Equipment,
expect that much of the corresponding increases
and Shifting of Staff ($8.9 Million
in training needs will be short term in nature,
in 2023-24, $8.6 Million Through
associated with preparing personnel to fill the
Construction). This funding would support
new authorized positions as they are onboarded.
various costs associated with leasing and
Once these new authorized positions have been
operating two temporary facilities that would
filled, attrition will lead to some ongoing training
be used for conducting training until the
needs, but those are likely to be much smaller than
proposed new center is completed (estimated
the current short-term demand. (CalFire currently
to be 2030)—one at Shasta College in
assumes a 10 percent attrition rate annually.)
Redding and one at a University of Phoenix
Moreover, the proposed new training facility
campus in Sacramento. Specifically, the
is not projected to be completed until 2030, well
proposal includes additional funding for
after the recently authorized positions will be
(1) facility leasing, utilities, and housing
filled. Accordingly, the state’s decision regarding
($3.7 million); (2) logistics and supplies
whether to construct this facility should be based
($1.6 million); (3) leasing of fire engines
not on the current training needs—which may
($1.3 million); and (4) vehicles and fuel
be temporarily high—but rather on a long-term
($845,000). The proposal also includes
assessment of training needs. Over the longer
roughly $1 million in new net costs to shift
term, the growth rate for CalFire staffing is
12 existing CalFire staff positions from the
unknown and, therefore, so is whether future
California Correctional Center in Susanville—
training needs will be consistently higher on an
which is scheduled to be deactivated by
ongoing basis.
June 30, 2023—to provide instruction and
administrative support.
www.lao.ca.gov 3
2023-24 BUDGET
Premature to Fund New Project When have been proposed thus far, requesting staffing now
CFTC-Ione Master Plan Is Still in Progress. to support unidentified projects is premature.
Uncertain training needs is not the only reason we We note that the department also plans to use
find this project proposal to be premature. Even if these positions to perform some maintenance
CalFire were to provide well-substantiated projections activities, particularly on an ongoing basis after the
of future training demand increases continuing new proposed training center is completed. However,
beyond 2030, whether the proposed new training we find this aspect of the proposal is also unjustified
center would be the most cost-effective solution for two key reasons. First, different classifications,
to address such needs is unclear. Specifically, the skills, and staffing levels likely would be needed to
CFTC-Ione master plan that the Legislature funded conduct maintenance activities as compared to
in the 2022-23 Budget Act is intended to provide the specific positions the Governor is proposing
insights into the expansion capacity at that facility. (such as land surveyors). Second, the facility is not
As noted above, this assessment is still in progress. anticipated to be completed until 2030. Accordingly,
While it is anticipated to be completed this spring, it would make sense for the department to request
it could be delayed and may not be available with appropriate maintenance staff if and when the new
sufficient time for careful legislative review before the proposed facility is completed rather than at the
adoption of the budget in June. Moving forward with initiation of the study phase. For these reasons, we
approving a new training center before the Legislature do not find a compelling need for the requested staff.
has adequate time to incorporate the findings of this
Some Funding for Temporary Training Needs
plan into its deliberations could result in a higher level
Warranted, but Specific Costs Not Yet Clear.
of state spending than ultimately necessary.
CalFire also requests funding to support various
Premature to Fund Acquisition Phase Before costs associated with leasing and operating two
Completing Study Phase. Even if the Legislature temporary facilities until the new training center
were to feel sufficiently confident that a new training is constructed. As described above, some of the
facility is needed, providing funding for acquisition funding for these costs is requested as part of this
before the proposed study is complete still would proposal ($8.9 million in 2023-24 and $8.6 million
be premature. The study is anticipated to provide until the new center is built). CalFire would also
information on available sites, as well as develop support some of these one-time costs using a portion
refined scope and cost estimates for the project. ($5.8 million) of the funding already authorized in
This would be important information for the the 2022-23 budget package. Given its elevated
Legislature to have before deciding whether it makes near-term training needs—resulting from the
sense to move forward with the project, as well as significant recent increases in firefighter staffing—the
to more accurately estimate how much funding is department’s intent to pursue temporary leases and
specifically needed for the site acquisition. to support other costs associated with operating
Staffing Component Not Adequately Justified. temporary training facilities is justified. Moreover,
As noted above, the Governor’s request includes using some of the funding appropriated in last year’s
$3.9 million in 2023-24 (decreasing to $3.4 million budget to help offset these costs is reasonable,
annually beginning in 2024-25) for 12 facility staff to since those funds were provided to help support
consult with DGS as it manages the training center the staffing augmentations. However, at this time,
project, as well as other potential capital outlay the department has not adequately substantiated
projects at CFTC-Ione that may be identified in the the need for the specific amount of new funding
forthcoming master plan. For a department to request proposed. For example, CalFire proposes $1.3 million
staffing—much less 12 positions—to coordinate with to lease fire engines for training purposes until the
DGS on a capital outlay project is highly unusual. permanent engines funded in the 2022-23 Budget
Rather, departments typically absorb this type of Act arrive in 2024 or 2025. Why these needs could
workload, which generally is modest. Additionally, not be met at a lower cost, such as by using older
since the CFTC-Ione master plan has not yet been fire engines that the department would otherwise
completed and no corresponding specific projects sell, is unclear. We believe the Legislature needs
4 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
more information that explains and justifies the costs will need to weigh the importance and value of the
of operating the temporary training centers before proposed new activities against the activities to which
taking action on the Governor’s request. it has already committed. Essentially, it will want
Commits the State to Significant—and to consider whether it wants to make reductions—
Unknown—Amount of Out-Year Costs. Together, either those proposed by the Governor or equivalent
the Governor’s training center proposals would alternatives—to free up resources for this project. In
commit the state to significant costs over the coming our view, this proposal does not meet that higher bar.
years, including about $400 million to construct
Recommendations
the new proposed facility, as well as ongoing costs
associated with its operations and maintenance. Approve Proposed $545,000 for a Facility
We note that these ongoing costs may not be fully Study With Revised Scope to Be Completed
reflected in the proposals. Specifically, the only costs After CFTC-Ione Master Plan. We recommend
the Legislature approve the proposed funding to
proposed to be funded on an ongoing basis are for
study options for a new training center. However, we
the 12 facility-related staff mentioned above. Potential
recommend that the Legislature require that CalFire
remaining costs—such as for utilities, vehicles, and
modify the scope of this study to include (1) estimates
costs associated with the shift of personnel from
of future growth in CalFire staffing and associated
Susanville—are only proposed to be funded through
training needs and (2) an evaluation of multiple
the end of construction of the facility. We would
potential alternatives for meeting those training needs
expect that many of these types of activities would
(with constructing a new training center as one but
need to be funded even after the new facility is
not the only option considered). We recommend the
complete, however. Accordingly, the $3.4 million in
Legislature require that CalFire incorporate the results
ongoing funding requested as part of these proposals
of the master plan for CFTC-Ione—anticipated to be
likely understates the full costs associated with
completed by May 2023—into this study to ensure the
operating the facility in the out-years.
assessment is comprehensive.
Higher Bar for Approving New Proposals
Reject Proposed $18.7 Million for Site
Given General Fund Condition. These proposals
Acquisition. We recommend the Legislature reject
would commit the state to significant discretionary
the $18.7 million proposed for site acquisition until
General Fund expenditures in not only the budget
after the completion of the CFTC-Ione master plan
year but also in the out-years. Importantly, the state
and the aforementioned facility study. The additional
currently is experiencing a budget problem, where
information from these reviews can help inform the
revenues already are insufficient to fund existing
Legislature’s deliberations by providing clarity on the
commitments. In this context, every dollar of new
options available to meet CalFire’s long-term training
spending in the budget year comes at the expense
needs, as well as a more refined cost estimate for the
of a previously identified priority and requires finding
potential construction of a new training center should
a commensurate level of solution somewhere within
it be determined to be necessary.
the budget. The Governor “makes room” for this
Reject Proposed $3.9 Million in 2023-24
(and other) proposed new spending by making
and $3.4 Million Ongoing for Facility Staffing.
reductions to funds committed for other programs,
We recommend the Legislature reject the funding
including many in the climate and natural resources
proposed for additional facility-related staffing. These
areas. Moreover, because these training center
positions are not needed to oversee the completion
proposals also have significant out-year costs, they
of the revised study, which is the only portion of the
would contribute to projected future budget deficits
proposal that we recommend the Legislature approve
and would require finding additional solutions in the
at this time. However, even if the Legislature were to
coming years. We therefore think the Legislature
approve the Governor’s proposed funding for both
likely will want to apply a higher bar to its review
the study and acquisition, we still would recommend
of new spending proposals such as these than
against authorizing these positions, as we find the
it might in a year in which the General Fund had
department’s justification for their need to be lacking.
more capacity to support new commitments, as it
www.lao.ca.gov 5
2023-24 BUDGET
Approve Some Level of Funding to Meet various changes to sentencing laws that have
Temporary Needs, but Seek Additional significantly reduced the state prison population,
Information. We recommend the Legislature particularly those individuals who can be housed in
approve some level of funding to help meet the low-security environments. This, in turn, has reduced
short-term training needs associated with CalFire’s the population housed at conservation camps and
recent increase in authorized positions. Because the available to serve on hand crews. Specifically, as
specific amount of funding needed is still unclear, of January 2023, 1,689 people were housed in
we recommend the Legislature seek additional conservation camps, compared to 3,980 people in
justification from CalFire in the coming months to January 2010.
help determine the appropriate level of resources Population Declines Have Resulted in the
to provide. Closure of Eight Conservation Camps. In response
to the declines in the population at conservation
GROWLERSBURG CONSERVATION camps, the state initiated the closure of eight camps
CAMP REPLACEMENT in 2020-21, consolidating the remaining crews into
the other 35 camps. The locations of these remaining
Background camps, five of which are operated by Los Angeles (LA)
Conservation Camps Provide a Key Source of County rather than CalFire, are shown in Figure 1.
Hand Crews. Hand crews support fire response by As highlighted, the Growlersburg facility is located in
constructing fire lines, assisting fire engine crews with the northern part of the state in proximity to several
the deployment of fire hoses over long distances, other camps.
providing logistical operational
support, and extinguishing hotspots Figure 1
to help contain fires. These crews
Conservation Camps Are Located Across the State
also do fire mitigation work, such
as hazardous fuels reduction and
vegetation management projects.
Historically, the majority of the hand
crews utilized by CalFire have been
operated through agreements with the
California Department of Corrections
and Rehabilitation (CDCR) for use of
labor performed by people committed
to state prison. These people are
Growlersburg Conservation Camp
housed at conservation camps
located in or near forests throughout
the state. They generally qualify for
voluntary placement in camps if
CDCR has determined they (1) can
be safely housed in a low-security
environment, (2) can work outside a
secure perimeter under relatively low
supervision, and (3) are medically
fit for conservation camp work.
Conservation camp hand crews are
compensated for their work.
State Prison Population
Has Decreased in Recent
Years, Resulting in Declines at
Conservation Camps. Over the past
dozen years, the state has enacted
6 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
Remaining Camps Operating Below Governor’s Proposal
Design Capacity. Even with the closure of eight
Proposes Replacing Growlersburg
conservation camps, the remaining sites continue
Conservation Camp at Existing Site. The
to operate well below capacity. Specifically, as
Governor’s budget proposes $4.5 million from the
of January 2023, 1,689 people are housed at
General Fund in 2023-24 to restart a previously
facilities that have a combined total capacity of
paused project that would replace the existing
3,368. (Excluding the LA County-operated camps,
facilities and infrastructure at the Growlersburg
1,612 people are housed at CalFire-operated
Conservation Camp site in Georgetown (El Dorado
facilities that have a combined total capacity of
County). (As we discuss in further detail below, this
3,040—which represents an occupancy rate of just
project was initiated in the 2007-08 Budget Act.)
over 50 percent.)
The proposed funding would support the working
Prison Population Projected to Continue to drawings phase. CalFire estimates the total cost of
Decline. The administration currently projects that the project—including $93 million for construction—
the state’s prison population will decline by roughly to be $100 million, and that it would be completed
7 percent between 2023-24 and 2025-26. These in 2028. The administration anticipates funding
declines, should they materialize, likely would result the construction phase of this project with lease
in further reductions to the population housed revenue bonds, which ultimately would be repaid
at conservation camps. To address the existing from the General Fund over about 25 years.
and projected declines, CalFire has expanded
Assessment
its partnerships with other agencies, including
CCC and CMD, to provide staff for hand crews. Population in Conservation Camps Has
Additionally, the state has provided CalFire with Changed Substantially, Raising Questions
funding to hire additional firefighters to help backfill About Need for Remaining Camps. As described
for these losses. in the nearby box, the Legislature first approved
this project 16 years ago, in 2007. Since that time,
the population housed in conservation camps—and
Need for Growlersburg Project Has Been Questioned Since its Inception
in 2007
The California Department of Forestry and Fire Protection’s (CalFire’s) Growlersburg
Conservation Camp project has a long history of stops and starts, beginning roughly 16 years
ago. Key steps of the project include:
2007: Project Initiated. The 2007-08 Budget Act authorized $46 million for the completion
of all the phases of the project, including preliminary plans, working drawings, and construction.
Construction on the project was originally anticipated to be completed by 2013.
2016: Funding Expired, Project Halted. CalFire allowed the expenditure authority for this
project to expire in June 2016 due to funding and department workload constraints and differing
priorities. At that time, only the preliminary plans phase had been completed.
2021: Funding Provided for Working Drawings. The 2021-22 Budget Act included $3 million
to complete working drawings for the project.
2022: Funding Reverted, Project Halted. The administration decided to halt the project after
completion of the preliminary plans phase due to cost increases and uncertainty over whether
Growlersburg might be a good candidate for closure to help reduce the conservation camp
program. Accordingly, the 2022-23 Budget Act reverted the 2021-22 Budget Act appropriation
for working drawings.
2023: Funding Proposed Again. The administration proposes to restart the project
in 2023-24.
www.lao.ca.gov 7
2023-24 BUDGET
the associated need for facilities—has changed trends in prison populations and other nearby
dramatically. Even within the two years since the facilities but also because the state might identify
Legislature last considered providing funding for potential other, more effective uses of the site.
this project in 2021, the prison population has To the extent the state wants to retain a greater
declined faster than previously anticipated. Notably, presence in this region than is provided by the
the Growlersburg Conservation Camp has a CCC’s Greenwood Center and other nearby
capacity of 120 but currently houses 81 people, and conservation camps, it is not clear whether a
several nearby camps also are currently operating conservation camp would be the most appropriate
below capacity. For example, the Washington Ridge facility. Yet investing $100 million in replacing
Conservation Camp in Nevada City has capacity Growlersburg Conservation Camp facilities would
for 100 but currently houses only 52 people. make it impractical to then depopulate this site as
The current overall 50 percent occupancy rate at part of a potential future plan to reduce the number
CalFire-managed conservation camps together of conservation camps. We think eliminating that
with projections for further declines in the state option now is unwise, because the best future
prison population call into question whether all uses of the Growlersburg site still are unclear.
of the remaining camps are needed or whether For example, the site could be a reasonable
some additional closures may be appropriate candidate for permanent closure, or perhaps it
in the coming years. As trends become clearer could be repurposed for other non-inmate hand
over the next few years, we expect the state will crews in the future. In the coming years, the state
have a better picture about the ongoing need for may decide that another type of crew—such as
these camps. a CalFire firefighter hand crew—might be more
State May Not Need Growlersburg Facility. appropriate for firefighting activities in this area
Part of the administration’s proposed justification (particularly given the trends in prison populations).
for this project is Growlersburg’s strategic location If a different type of crew were to ultimately occupy
in the Sierra Nevada region and close proximity the Growlersburg site, it would necessitate different
to sawmills. While this is true, the Sierra Nevada facilities (for example, to provide more space and
region is home to other conservation camps as to accommodate those who identify as females).
well, such as Washington Ridge in Nevada City, Accordingly, proceeding with a large replacement
that could provide similar situational benefits. project such as the one proposed does not make
Furthermore, to truly understand the need for sense until the optimum long-term use of the site
this facility, the state needs to consider not only is clearer.
the location of other conservation camps, but Project Costs Have Grown Dramatically.
also other similar resources, such as hand crews The estimated costs of the Growlersburg project
operated by CCC and CMD. For example, CCC have more than doubled since the Legislature
is in the midst of replacing its Greenwood Center, first approved it in 2007—from $46 million to
which is less than three miles away from the $100 million. Notably, most of the estimated
Growlersburg Conservation Camp. The Greenwood increase in costs has occurred over just the
Center focuses specifically on forest management past two years (from $59 million in 2021-22
and emergency response. That CCC has a facility to $100 million in 2023-24). According to the
within close proximity and is playing an increasingly department, the cost increases have resulted from
important role in meeting the needs once filled by various factors, including supply chain delays and
conservation camp crews makes the continued inflationary pressures (such as increases in lumber
need for Growlersburg even less certain. costs, transportation costs, and construction
Premature to Decide That Conservation wages), and the update of several building code
Camp Is Best Long-Term Use of Growlersburg cycles. These higher costs further call into question
Site. We view the Governor’s proposal to rebuild whether the level of expenditure is warranted,
the Growlersburg site as a conservation camp particularly given uncertainty about the long-term
to be premature, not only given the existing need for this and other conservation camps.
8 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
Project Not a Clear Immediate Priority, Recommendation
Particularly Given General Fund Condition.
Reject Proposal. We recommend the
The existing Growlersburg Conservation Camp
Legislature reject the proposal to replace the
buildings were constructed in 1967 and thus are
Growlersburg Conservation Camp for several
over 50 years old. However, overall, the facility is
reasons. First, the state may not have long-term
still serviceable and well-maintained, as discussed
needs for the facility given the current conservation
in a recent external review conducted by the
camp population only fills about half of the existing
El Dorado County Grand Jury. (Such reviews of
capacity and that future declines in the inmate
prison facilities, including conservation camps, are
population are projected. Second, other existing
required annually under state law.) Additionally,
facilities housing various types of similar crews
we note that CalFire continues to rely on even
are located nearby. Third, the state may identify
older facilities, many of which have significant
other, more effective uses for the Growlersburg site
infrastructure needs. For example, CalFire indicates
in the coming years, so committing to rebuilding
that many of the state’s conservation camps were
it as a conservation camp now is premature.
built 70 to 80 years ago and are in dilapidated
Fourth, the costs of the project are higher than
condition. Similarly, many other departments
anticipated, raising additional questions about
have facilities that were built 50 or more years
its benefit-to-cost justification. Finally, given the
ago and have significant deficiencies. Why the
state’s budget problem, dedicating new General
administration views the Growlersburg project
Fund to this project would come at the expense
as a higher priority for funding than potential
of previously identified priorities, and we do not
alternative capital outlay projects that play a
find it sufficiently justified for prioritizing limited
central role in providing state services—by CalFire
state resources. We note that the Legislature could
or other departments—is unclear. Moreover,
always revisit the need for the project at some time
the administration itself has moved slowly on
in the future when the General Fund condition is
this project and the department has repeatedly
more robust and the state has more clarity on its
questioned its priority and merit (as described in the
firefighting needs and plans in the region.
box referenced earlier). As discussed above, given
the state’s budget problem, funding this proposal—
like other new General Fund spending proposals—
would come at the expense of previously identified
priorities. Given these trade-offs, we do not find a
compelling rationale for prioritizing this project at
this time. The Legislature could revisit the need for
this facility in a future year when the General Fund
condition is more robust and the key questions we
have raised about its merit have become clearer.
For example, revisiting this project at a future date
would provide more time for the Legislature to
glean more certainty on the extent to which the
conservation camp population continues to decline
and additional camp closures are necessitated.
www.lao.ca.gov 9
2023-24 BUDGET
10 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
www.lao.ca.gov 11
2023-24 BUDGET
LAO PUBLICATIONS
This report was prepared by Helen Kerstein, and reviewed by Rachel Ehlers and Anthony Simbol. The Legislative
Analyst’s Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service, are
available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000, Sacramento,
California 95814.
12 LEGISLATIVE ANALYST’S OFFICE