LAO
The 2023-24 Budget: Proposed Energy Policy Changes
Read the report at Legislative Analyst's Office ↗
2023-24 BUDGET
The 2023-24 Budget:
Proposed Energy Policy Changes
GABRIEL PETEK | LEGISLATIVE ANALYST | MARCH 2023
SUMMARY
In this brief, we assess the Governor’s proposed changes to how the state procures and pays for reliable
clean energy. The Governor proposes to (1) establish a new central procurement role for the state to
secure energy resources that would be used by electric utilities, for which costs would be recovered from
ratepayers, and (2) require electric utilities that experience energy deficiencies to make payments in support
of a new state-operated program that provides emergency backup electricity resources. These proposals
would represent significant changes in state-level energy policy, as electric utilities have historically been
responsible for procuring and paying for energy resources and reliability. As such, the proposals raise a
number of key questions for the Legislature to consider, including: (1) how these policy changes might
impact electricity rates; (2) whether these proposals are necessary in light of existing state procurement
requirements and significant funding provided for electric reliability in the 2022-23 Budget Act; (3) what risks
the proposed new procurement role might pose to the state; and (4) the degree to which the proposals are
needed now, as opposed to in a future year. We also recommend the Legislature weigh whether it may want
to consider these proposals as part of the policy process, rather than the budget process, which could allow
for more time for thoughtful deliberation.
BACKGROUND The Legislature set interim targets on the path to
this goal via Chapter 361 of 2022 (SB 1020, Laird),
Greenhouse Gas and which requires that zero-carbon sources make up
Clean Energy Goals 90 percent of statewide electricity sales by 2030
and 95 percent by 2035. As discussed next, the
State Has Established Ambitious
electricity sector has been a driver of statewide
Greenhouse Gas (GHG) and Clean Energy
emissions reductions thus far, but continued
Goals. Chapter 488 of 2006 (AB 32, Núñez/Pavley)
reductions are needed to meet these future goals.
established the goal of limiting GHG emissions
statewide to 1990 levels by 2020. In 2016, Electricity Sector Has Made Progress in
Chapter 249 (SB 32, Pavley) extended the limit to Reducing Emissions Through Transitioning
40 percent below 1990 levels by 2030. Emissions to Cleaner Sources. Over the last decade,
have decreased since AB 32 was enacted and the the electricity sector has been a primary driver
state achieved its 2020 goal a year early. However, of statewide emissions reductions, as shown
the rate of reductions needed to reach the SB 32 in Figure 1 on the next page. Reductions
target are much greater. Chapter 337 of 2022 mostly have resulted from changes in the mix
(AB 1279, Muratsuchi) established an additional of resources used to generate electricity—
objective, requiring the state to achieve carbon primarily increases in resources characterized
neutrality by 2045. In addition to these overall as “renewables” (such as solar and wind) along
GHG reduction goals, the state has adopted with a decline in coal generation. A wide variety
particular emissions reduction goals for the of factors have contributed to this shift, including
electricity sector. Specifically, Chapter 312 of technological advancements, federal policies,
2018 (SB 100, de León) established a state policy and state policies. As shown in Figure 2 on the
that 100 percent of retail electricity come from next page, nearly 60 percent of retail electricity
zero-carbon sources by 2045. sales came from zero-carbon resources in 2020,
including 36 percent from resources that qualify
as renewable.
www.lao.ca.gov 1
2023-24 BUDGET
Reliability Challenges and
Recent Funding
Figure 1
State Facing Some Energy
Emissions From Electricity Have Declined Significantly
Reliability Challenges. Climate
Million Metric Tons of Carbon Dioxide Equivalent change is contributing to demands
on the state’s electric grid, with
140 warmer temperatures leading
120 to more calls for electricity
during peak evening hours in the
100
summer months. In August 2020,
80
California experienced rolling
60
power outages due to a heatwave
40 and accompanying strain on the
20 electric grid. The state avoided
outages in 2021 and 2022, but
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020
energy resources were strained
Source: California Air Resources Board (2022). California Greenhouse Gas Emission Inventory - 2022 Edition. during summer heatwaves. A major
Data available at: https://ww3.arb.ca.gov/cc/inventory/data/data.htm
heatwave in September 2022
caused the state to send an
emergency text message alert
to 27 million Californians to encourage energy
Figure 2 conservation—the first time such a measure had
been deployed. While the state has experienced
Nearly 60 Percent of Retail Electricity
significant growth in renewable energy sources in
Sales Are From Zero-Carbon Resources
recent years, solar resources are not well-positioned
2020
to supply energy during peak evening hours after
the sun has gone down. Greater development of
energy storage technology will be needed to help
Natural Gas address the misalignment challenge of growing
and Other Renewables demand during times that a key renewable energy
Fossil Fuel
source is not available.
Significant Growth in New Energy Resources,
but Also Project Delays. In recent years, the
number of clean energy projects across the state
has increased exponentially, with the amount of
renewable energy supply more than tripling since
2005. Between 2020 and 2022, 130 new clean
energy projects came online to serve customers
Large Hydro
Nuclear in the California Independent System Operator
network, which provides electricity to 80 percent
of California. However, some projects also have
experienced delays due to issues with the supply
chain, permitting, and connecting new resources
to the electric grid. While the state is on track to
continue to develop new clean energy resources
over the next decade, such delays in bringing these
projects online could pose challenges in meeting the
state’s clean energy, emissions, and reliability goals.
2 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
Recent Budgets and Policy Actions Provided • Distributed Electricity Backup Assets
Significant Funding for Clean Energy and ($700 Million). This new program,
Reliability. The 2022-23 budget package planned administered by the California Energy
for $9.6 billion over five years for clean energy Commission (CEC), provides incentives for
programs and reliability efforts. The administration certain distributed energy resources that
indicates that California also has received federal can be used to support the state’s electrical
funds to support various energy efficiency efforts grid during extreme events. The CEC is still
through the Inflation Reduction Act and the developing the program, which is intended
Infrastructure Investment and Jobs Act, but has not to fund zero- or low-emissions technologies
yet provided specific details on the status of this such as fuel cells and energy storage at both
funding or what types of projects it could support. existing energy facilities and new facilities.
The Governor’s budget proposes some reductions
In addition to these budget actions, Chapter 239
to state energy activities, but would maintain
of 2022 (SB 846, Dodd) authorized the extension
the majority of the planned funding ($8.7 billion).
of the Diablo Canyon Power Plant (DCPP)—which
Moreover, a large share of this funding—$3.3 billion
was scheduled to retire by 2025—through 2030.
across five years—is for three programs intended to
Diablo Canyon is California’s last remaining
increase statewide electricity reliability, which the
nuclear power plant, and the state has identified
Governor does not propose reducing. Together, the
it as a valuable near-term source of zero-carbon
administration refers to these three programs as the
energy during the transition to greater renewable
“Strategic Reliability Reserve,” and they include:
resources. While the legislation authorized an
• Electricity Supply Strategic Reliability extension, DCPP still has to receive required
Reserve Program (ESSRRP, $2.3 Billion). permits at the local, state, and federal levels
This program funds the Department of in order to continue operations. SB 846 also
Water Resources (DWR) to secure additional authorized the following expenditures:
electricity resources to help ensure summer
• Loan to Pacific Gas & Electric (PG&E) (up
electric reliability. So far, these activities have
to $1.4 Billion). The Legislature specified
included extending the life of gas-fired power
intent to provide a General Fund loan
plants that were scheduled to retire, and
of up to $1.4 billion to PG&E to support
procuring temporary diesel power generators
extended operations at Diablo Canyon.
and new energy storage. The ESSRRP
Of this total amount, the Legislature has
provided between 554 megawatts (MW) and
authorized $600 million so far. The potential
1,416 MW of energy during last September’s
remaining $800 million is subject to a
extreme heat event. For context, the rotating
future appropriation. PG&E was awarded
outages in 2020 were caused by a shortfall of
a $1.1 billion federal grant from the U.S.
about 500 MW.
Department of Energy in November 2022 and
• Demand Side Grid Support ($295 Million).
is expected to use this award to pay back the
This new program, administered by the
state for loans it ultimately receives.
California Public Utilities Commission (CPUC),
• Clean Energy Reliability Investment Plan
provides customer incentives to reduce net
(CERIP, $1 Billion). Senate Bill 846 also
electricity load during extreme events. In the
included legislative intent to provide a total
summer of 2022, utilities began enrolling
of $1 billion General Fund from 2023-24
participants in the program, which pays
through 2025-26—$100 million in 2023-24,
customers to reduce their energy usage
$400 million in 2024-25, and $500 million
during summer peak evening hours when the
in 2025-26—to support the CERIP, which
electric grid is strained.
CEC recently developed. The legislation
www.lao.ca.gov 3
2023-24 BUDGET
required the plan to support investments Procuring Reliable
that address near- and mid-term reliability Clean Energy Resources
needs and the state’s GHG and clean energy
State Generally Determines What Levels of
goals. In accordance with the legislation,
Energy Resources Are Needed, Then Requires
the administration proposes to provide
Regulated Local Entities to Procure Them.
$100 million in 2023-24 for CERIP-identified
With regard to CPUC-regulated electric utilities,
activities. Specifically, the Governor proposes:
the state generally has assumed responsibility for
(1) $32 million for DWR to develop a proposed
determining (1) how much energy will be needed to
new central procurement role described
reliably meet statewide demand, and (2) what share
below; (2) $33 million for extreme event
of those resources must be from renewable sources
support (including additional funding for the
to meet the state’s GHG reduction and clean energy
Demand Side Grid Support and Distributed
goals. After the state determines these needs, it
Electricity Backup Assets programs);
then requires local energy providers—known as
(3) $20 million for various administrative,
Load Serving Entities, or LSEs—to procure them.
community engagement, and planning
(As described below, this process works slightly
expenditures; and (4) $15 million to help new
differently for publicly owned utilities [POUs].) LSEs
energy resources come online.
can procure energy through purchasing contracts
or by developing the resources themselves (such as
by building solar arrays). Please see the nearby box
for more background about LSEs.
Load Serving Entities (LSEs) in California
LSEs are entities that provide electricity to customers. They include the following types of
organizational structures:
• Investor Owned Utilities (IOUs): The territory of California’s six privately owned IOUs covers
about 75 percent of the state’s electricity needs. The three largest IOUs in the state are Pacific
Gas & Electric, Southern California Edison, and San Diego Gas & Electric. The California
Public Utilities Commission (CPUC) regulates IOUs by setting their electricity rates for
customers and requiring them to procure and maintain a certain amount of energy resources.
• Community Choice Aggregators (CCAs). The CCA program allows cities, counties, and
other government entities within the service area of an IOU to purchase and/or generate
electricity for their residents and businesses. The intention of this program is to increase
options for customers. The IOU continues to deliver the electricity through its transmission
and distribution system and provides meter reading, billing, and maintenance services for
CCA customers. CCA energy resource needs are regulated by CPUC. There currently are
25 CCAs in California.
• Electric Service Providers (ESPs). ESPs are non-utility companies that provide electricity to
large electric users within the service territory of an existing electric utility. They are regulated
by CPUC and there are 20 ESPs in California.
• Publicly Owned Utilities (POUs): POUs are regulated by locally elected governing boards
such as municipal utility districts, which govern POU energy resource needs and rates. The
state has some authority over POU energy resources. POUs provide about 25 percent of the
state’s electric services. Examples of large POUs include Sacramento Municipal Utility District
and Los Angeles Department of Water and Power. There are 47 POUs in California.
4 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
State Has Adopted Numerous Requirements then required to use CPUC’s model to develop
for LSEs to Help Ensure Reliability and their own individual IRPs. CPUC ultimately
Procurement of Clean Energy Resources. approves each LSE’s IRP and the process is
CPUC is responsible for a number of programs and updated every two years. The IRP process is
activities designed to (1) grow the share of renewable CPUC’s primary planning tool to ensure that
resources used to generate electricity and (2) ensure the state is meeting its emissions reductions
regulated LSEs are procuring enough energy to both goals from the electricity sector. CPUC initiated
serve demand and meet state GHG goals. These a related process, the IRP Procurement
programs and initiatives include: Track, in 2019. The IRP Procurement Track
orders LSEs to undertake additional resource
• Resource Adequacy (RA) Program.
procurement beyond the normal IRP planning
The RA program was established in 2004 to
time line, recognizing that some newer clean
promote electric reliability. CPUC establishes
energy resources have longer lead times (such
RA obligations for all LSEs within its jurisdiction,
as offshore wind and long duration storage).
including Investor Owned Utilities (IOUs),
Community Choice Aggregators (CCAs), and Recognizing that the state’s growing electricity
Electric Service Providers. LSEs are required to needs and emissions reduction goals will necessitate
demonstrate compliance with RA requirements new resources, CPUC has used these processes
on both a monthly and annual basis and must to mandate unprecedented expansions in energy
pay penalties if they do not comply. The current procurement in recent years. For example, between
RA program mandates a 16 percent planning 2020 and 2022, CPUC’s IRP procurement orders
reserve margin (that is, the amount of resulted in more than 11,000 MW of new energy
resources an LSE must have on reserve, as resources, most of which are coming from solar,
a percentage of peak total electricity load, in wind, and battery storage projects. CPUC also
case of extreme events). The planning reserve has expanded its allowed time lines for LSEs to
margin will increase to 17 percent in 2024. This secure new energy resources in recognition of the
margin is also known as the planning standard timing difficulties in bringing these resources online.
or RA margin. For instance, in February 2023, CPUC extended
• Renewable Portfolio Standard (RPS). its deadline for a new procurement order that
The RPS was established by Chapter 516 totals 4,000 MW of additional energy capacity from
of 2002 (SB 1078, Sher) with the initial 2026 to 2028.
requirement that 20 percent of retail electricity Public Utilities Also Subject to Some
must be provided by renewable energy State Requirements for Energy Resource
resources by 2017. The RPS program is Procurement. Because POUs are outside of
overseen jointly by CEC and CPUC and has CPUC’s jurisdiction, some—although not all—of their
been updated numerous times. Senate Bill 100 reliability requirements differ from those of other
increased the RPS requirement to 60 percent LSEs, and their compliance with state requirements
of retail electricity coming from renewable largely is overseen by CEC. Like other LSEs, POUs
sources by 2030. All LSEs, including POUs, are are subject to the RPS requirements for renewable
required to comply. energy procurement. Additionally, the state’s largest
• Integrated Resource Planning (IRP) POUs (which account for 94 percent of POU electric
Process. The IRP process was established load and customers) are required to submit an IRP
in 2015 through Chapter 547 (SB 350, de every five years to CEC. In addition, Chapter 251 of
León) to plan for how LSEs could meet 2022 (AB 209, Committee on Budget) required CEC
mid- and long-term energy procurement to develop updated planning reserve requirements
and GHG goals while maintaining reliability. for POUs that account for the increased frequency
As part of this process, CPUC conducts of extreme weather events and reliability challenges
modeling that sets out a path for the state the state has experienced in recent years. CEC
to meet its energy needs while reaching its is required to develop these requirements by
emissions reduction goals. Regulated LSEs are December 2023.
www.lao.ca.gov 5
2023-24 BUDGET
IOUs Sometimes Play Centralized state’s clean energy goals and satisfy electricity
Procurement Role. LSEs generally are required demand. The state’s electricity planning agencies
to procure new energy resources themselves, but anticipate that demand will grow significantly
IOUs are legally authorized—and, in some cases, over the next decade due not only to climate
required—to procure resources on behalf of other change and higher temperatures, but also to a
LSEs. For example, a 2019 CPUC decision ordered shift towards zero-emission vehicles and more
LSEs to procure additional RA-qualifying resources electric-powered appliances and heating. This
and allowed IOUs to act as a procurement likely will necessitate adding larger “long-lead time”
backstop. In response to this order, between 2020 resources (such as offshore wind, long duration
and 2022, 15 LSEs elected to have an IOU procure storage, and geothermal electric generation) to the
energy resources on their behalf. CPUC also has state’s portfolio. However, such resources typically
compelled IOUs to procure resources on behalf are more expensive and take longer to develop.
of other LSEs, because the relatively small size of Moreover, fewer of these projects currently exist
some LSEs—in particular, many CCAs—can make in California, so local entities do not have a proven
procuring larger resources somewhat difficult. history to rely upon when seeking to develop or
Over the past few years, IOUs have experienced procure them. Because of the expense and general
challenges in centrally procuring resources due to risk associated with newer, large technologies,
associated costs, as they have simultaneously been smaller LSEs face particular challenges in procuring
facing growth in other types of costs such as those these types of resources.
related to wildfire mitigation.
State Has Some Limited History of GOVERNOR’S PROPOSALS
Undertaking Procurement Activities. While Governor Proposes Two Major New Energy
the state mostly tasks LSEs with procurement Policy Changes. The Governor has put forward
responsibilities, it has occasionally stepped in two major proposals related to procuring sufficient
to undertake these activities in the past. For clean energy resources to meet reliability and
example, during the energy crisis of the early GHG reduction goals. These proposals are
2000s, California experienced electricity supply contained in budget trailer legislation. The
shortages and utilities struggled to attain capital for proposals include: (1) establishing a new centralized
energy projects. In response, DWR financed energy energy procurement role for the state, for which
purchases on behalf of IOUs and entered into costs could be recovered from ratepayers, and
long-term contracts for electricity valued at over (2) requiring “capacity payments” from LSEs that
$40 billion. The last of these contracts terminated experience energy resource deficiencies during
in 2015. In addition, as mentioned above, the months when the state utilizes the ESSRRP.
2022-23 budget package committed $2.3 billion Figure 3 describes each proposal in detail.
over five years for DWR to secure additional
Some Initial Funding to Come From the
electricity resources intended to ensure summer
General Fund. As described in the figure, the
electric reliability. So far, ESSRRP activities have
Governor proposes to fund the ongoing support
mostly extended the life of natural gas plants that
and operational costs for DWR’s new procurement
supply electricity—these plants are only turned on
role from new charges to ratepayers. These charges
when the electric grid is experiencing major strain.
also would be used to pay off any bonds that DWR
The administration indicates that the ESSRRP
might issue for large capital costs. In addition, the
also provided financing support to IOUs for their
Governor proposes using General Fund in 2023-24
procurement of electricity imports last summer.
to help “stand up” the new procurement function
Clean Energy Goals and Growing Electricity at DWR. Specifically, the CERIP that CEC recently
Demand Will Necessitate Procuring New Types submitted to the Legislature includes $32 million—
of Resources. While California has brought a of the intended $100 million budget-year amount—
significant amount of clean resources online in to help establish this new central procurement
recent years, including wind and solar projects, office and process.
new resources still will be needed to meet the
6 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
Figure 3
Summary of Governor’s Major New Energy Policy Proposals
New Centralized Procurement Role for the State
9
New Central Energy Procurement Authority. The proposal provides the California Public Utilities Commission (CPUC) with
the option to identify either an Investor Owned Utility (IOU), the Department of Water Resources (DWR), or both to procure energy
resources through a centralized procurement process on behalf of Load Serving Entities (LSEs) that provide electricity services
to customers. The proposal primarily focuses on establishing requirements for DWR, as DWR does not yet have the authority to
centrally procure electricity resources in the way that IOUs currently do. Any resources that DWR procures through this process
would be available for IOUs, Publicly Owned Utilities (POUs), and other types of LSEs to use. DWR would utilize its new Strategic
Reliability Reserve office and staff to manage the procurement.
9
Requirements for Types of Resources Procured. The proposal requires DWR to conduct a competitive procurement
process and prioritize investments that do not compete with LSEs’ traditional procurement. According to the administration, the
DWR procurement is intended to be for long lead-time resources such as offshore wind, geothermal, and long duration storage.
The proposed statutory changes, however, do not explicitly limit this procurement option to those types of resources.
9
Authority for New Electricity Rate Charges to Cover Central Procurement Costs. The proposal gives CPUC the
authority to impose a non-bypassable charge to ratepayers to cover DWR’s procurement costs, should CPUC find that the
charge would not unreasonably increase costs to customers. A new Clean Energy Procurement Fund would receive the
customer charges and support the procurement activities.
9
Authority for DWR to Issue Bonds. The proposal gives DWR the authority to issue bonds, if necessary, to fund up-front costs
for its central procurement activities. These bonds would be repaid with the ratepayer charges noted above.
New Charges for LSEs That Do Not Procure Sufficient Energy Resources
9
Require Payments if LSEs Do Not Meet Energy Capacity Targets. To discourage LSEs (including POUs, which are outside
the CPUC’s jurisdiction) from over-relying on the Electricity Supply Strategic Reliability Reserve Program (ESSRRP), the proposal
would require utilities that do not procure sufficient energy capacity to make payments to help support the ESSRRP.
9
Payments Calculated Based on Energy Resource Deficiency. The state would assess a payment if an LSE does not meet
its reliability obligations in a month when the state had to access the ESSRRP. Specifically, the payment would be based on
a calculation that factors in the cost of the energy resource provided by the ESSRRP and the LSE’s deficiency in meeting its
monthly Resource Adequacy or planning reserve requirements. The payments would be calculated by CPUC and the California
Energy Commission.
9
Payments Would Be in Addition to Existing Integrated Resource Planning Enforcement Penalties. The proposed
new payments would be in addition to existing enforcement protocols. Specifically, an LSE that fails to meet its planning reserve
margin or Resource Adequacy requirements for the given month when the state used the ESSRRP would be subject to both this
new charge and existing penalty payments.
Other Technical Statutory Changes to of crosscutting questions that the Legislature
Existing Energy Policies and Programs. will want to consider as it weighs whether or
The proposed trailer legislation also includes not to adopt any of these changes. As such, we
various statutory changes for the three Strategic recommend the Legislature take sufficient time to
Reliability Reserve programs and DCPP which the engage with the administration and stakeholders
administration considers to be technical “clean up.” such that it feels confident it has answers to these
questions. The Legislature has a number of options
KEY QUESTIONS FOR for undertaking such deliberations, including
LEGISLATIVE CONSIDERATION oversight hearings and both formal and informal
information requests to the administration. Below,
The Governor’s proposed changes to the
we summarize the key questions that we find merit
way energy is procured and paid for in California
legislative consideration.
represent a significant new role for the state. As we
highlight below, the proposals raise a number
www.lao.ca.gov 7
2023-24 BUDGET
How Would Ratepayers Be Affected? Are Current Processes and Resources
How electric ratepayers would be affected by Insufficient? The administration states that the
the Governor’s proposals is unclear. In order to procurement option and capacity payments to the
understand the potential impacts, we recommend ESSRRP are necessary to avoid energy shortfalls
the Legislature consider the following issues when occurring among LSEs. However, these processes
evaluating the proposal: largely have been adequate thus far, and the state
has taken numerous other actions in pursuit of
• New Charges and Capacity Payments.
the same goals. Yet the extent to which existing
Under the proposal, LSEs that do not
reliability requirements and procurement processes
procure sufficient energy resources would
will be sufficient to meet future needs is uncertain.
be required to make a capacity payment
The following are existing processes and resources
to support the ESSRRP. In addition, LSEs
that are designed to support current and future
could be required to apply a non-bypassable
electric reliability:
charge to ratepayers to cover DWR’s central
procurement costs. The effects these charges • Existing IRP and Planning Processes.
would have on rates are unclear. Given that As described above, LSEs are required
California’s electricity rates already are among to demonstrate sufficient energy capacity
the highest in the nation and rising faster to the state through the IRP process,
than inflation, the Legislature will want to RA requirements, and—in the case of POUs
carefully consider the potential impacts on not subject to those requirements—separate
rates and whether the potential benefits merit planning reserve margin targets administered
those costs. by CEC. While the electric grid has been
• Market Effects of Central Procurement. strained in recent summers, whether LSEs
Under the proposal, DWR would be able to are actually at risk of a serious shortfall that
procure energy resources on behalf of the could lead to reliability issues is unclear.
state and LSEs if requested by CPUC. The The administration reports that no shortfalls
current market for energy resources is strained, have been identified by any LSE for IRP energy
with a large number of LSEs competing for resource procurement recently. CPUC has
a relatively small pool of projects that often recognized the need for more energy
will take years to develop. How the entrance capacity and has issued numerous orders in
of DWR—a large, well-resourced entity with recent years both for LSEs to procure more
the backing of the state—would influence the resources and to extend the time they have
market for new energy resources is unclear. to do so, recognizing the delays in permitting
The market for large, long-lead time resources, and building new energy projects described
which the administration says would be the above. In addition, as noted, efforts currently
priority for DWR’s procurement, is somewhat are underway at CEC to develop new planning
nascent and developing, as these types of reserve margin targets for POUs, which could
resources are newer technologies and very support additional reliability.
expensive to build. This makes it even more • Existing Collective Action. LSEs have
difficult to predict the potential effects of the successfully banded together to procure
central procurement proposal. Because DWR resources in the past. For example, CCAs and
likely would have more resources to expend POUs have formed joint powers authorities to
than other purchasers, it is also unclear how procure power on a collective basis. Taking
energy resource developers may alter prices. this approach to procure larger, long-lead time
Ultimately, how energy resources are priced will resources may prove more challenging, as
affect the rates customers are charged. these resources can be very expensive and
the market is limited. However, certain existing
locally based collective approaches may be
sufficient to meet reliability needs in the future.
8 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
• Existing IOU Central Procurement. What Are the Risks to the State?
IOUs have been directed to procure on behalf The administration has expressed concerns that
of other LSEs in the past, and CPUC has LSEs might be hesitant to procure large, long-lead
authorized them to recover their costs of time resources because of their high cost and
doing so. Additionally, last summer, the risk as newer technologies. The Governor’s
state provided financing support for IOUs to proposal to have the state pursue procuring
procure through the ESSRRP. Some IOUs these resources instead essentially shifts this
have reported challenges procuring energy risk from the privately owned utilities (and their
resources on behalf of others due to the high investors) to ratepayers and taxpayers. While this
capital costs of procuring larger resources could help facilitate the development of these
and a more diverse landscape with the important resources, additional information is
rise of CCAs. However, if the Legislature needed about the types of risks involved and their
was concerned about the potential risks magnitude for the Legislature to determine if they
of DWR acting as a central procurement are worth the potential benefits. Additionally, the
authority, expanding centralized procurement Legislature could explore whether it might be
undertaken by IOUs could be an alternative able to adopt statutory “guardrails” or protections
option worth exploring. If the state were to to help minimize potential risks to the state from
provide financing support to IOUs, similar to pursuing unproven technologies. For example,
how it did in the summer of 2022, cost issues this could include capping the amount of funding
could prove less of a barrier. DWR could invest in newer and more uncertain
• DCPP. As described above, the Legislature types of technologies. The Legislature also could
has authorized the extension of DCPP through require DWR to prioritize certain types of resources
2030, though the plant will have to overcome that it believes to be safer types of investments,
a number of regulatory hurdles before it such as long duration storage projects. While the
can continue operations past its originally Governor’s proposal would require DWR to utilize
scheduled sunset date of 2025. Accordingly, project evaluation criteria, whether these would
the administration is not accounting for the be sufficient to adequately assess and limit the
availability of DCPP-provided energy past potential risks to the state is unclear.
2025 in its reliability planning and modeling What Is the Status and Effectiveness of
for the next decade. Given the remaining Recent Investments? The state invested heavily
uncertainty around whether the extension in reliability efforts in the 2022-23 budget package
will proceed, we find that this approach is and state departments still have not spent most of
reasonable. However, if DCPP continues the associated funds. While the ESSRRP appears
operations as intended, the plant would to have provided important reliability support
provide a significant contribution to helping during the September 2022 heat wave—primarily
the state meet its reliability goals—2,280 MW, through utilizing natural gas plants—how it might
which is more than double the reliability provide support in future years still is unclear.
benefits provided by the ESSRRP in 2023 and More broadly, the Strategic Reliability Reserve
nearly five times the MW shortfall that resulted programs have significant funds remaining in their
in the rotating outages of 2020. The availability balance. For example, as of February 2023, the
of DCPP from 2025 through 2030 could ESSRRP had committed $654 million for specific
significantly improve the state’s reliability expenditures, but $1.4 billion of funding the
outlook and reduce the urgency of the need Legislature appropriated for 2021-22 and 2022-23
that the administration has identified for these remained unspent. If the ESSRRP continues
new policy proposals. to be relatively slow to spend down its existing
funds, asking ratepayers to provide the program
with even more funds through the proposed
capacity payments seems potentially unnecessary.
www.lao.ca.gov 9
2023-24 BUDGET
Specifically, whether capacity payments in support Should the Governor’s Proposals Be
of the ESSRRP—which LSEs would pass down Considered as Part of the Budget Process?
to ratepayers—are needed seems questionable, The Governor’s proposals represent significant
given the availability of significant General Fund policy changes for the state and they do not
resources from the previous budget. Moreover, have a particularly strong nexus with the budget.
existing penalty requirements already are in place The Legislature will want to consider the most
to help discourage LSEs from under-preparing, so it appropriate venue for discussing and deliberating
is also not clear that these payments are needed to these proposed changes. For example, the
incentivize compliance with planning mandates. Legislature could consider these proposals through
Is a Central Procurement Function Necessary the policy process, rather than as part of the
Now? Should the proposals be adopted as budget budget process. Ultimately, ensuring it has the
trailer legislation, the new authorities they grant to time and opportunities for developing a greater
the state would take effect upon enactment of the understanding, sufficient input from stakeholders,
statute, even though the administration estimates and thoughtful deliberation will be vital to ensuring it
it would not utilize the procurement option in the can make an informed decision on these important
2023-24 fiscal year. A rationale could exist for the proposals. Given the policy implications of the
state to take on central procurement authority to Governor’s proposals and the fixed constitutional
support the procurement of larger, long-lead time time frame associated with adopting the annual
resources—particularly given that these are difficult budget—as well as the complicated fiscal decisions
for individual LSEs to procure on their own or the budget process will involve this year, in the
even banded together. However, whether this new context of the General Fund shortfall—the budget
authority is needed urgently this year is unclear. process may not be the best venue for deliberating
The Legislature may want to consider deferring a these proposals.
decision on these proposals beyond the coming
budget discussion time line or even beyond the
2023 session. Delaying action could sacrifice some
time that could be spent beginning to develop
these resources, but given the many questions that
remain about this proposal, taking more time to
weigh the trade-offs could be valuable.
10 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
www.lao.ca.gov 11
2023-24 BUDGET
LAO PUBLICATIONS
This report was prepared by Sarah Cornett, and reviewed by Rachel Ehlers and Anthony Simbol. The Legislative
Analyst’s Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service, are
available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000, Sacramento,
California 95814.
12 LEGISLATIVE ANALYST’S OFFICE