LAO
The 2023-24 Budget: Broadband Infrastructure
Read the report at Legislative Analyst's Office ↗
2023-24 BUDGET
The 2023-24 Budget:
Broadband Infrastructure
GABRIEL PETEK | LEGISLATIVE ANALYST | MARCH 2023
SUMMARY
Significant Changes to Original 2021 Broadband Infrastructure Spending Plan. Since July 2021, the
administration and the Legislature have made substantive changes in the amounts and sources of funding for
the original broadband infrastructure spending plan—a $6 billion ($4.3 billion American Rescue Plan [ARP] fiscal
relief funds, $1.7 billion General Fund) multiyear plan enacted in 2021. While the total amount of the spending
plan has increased only by $550 million, the source of funding for the majority of the spending plan is now
General Fund. Out of the revised total $6.55 billion, $3.64 billion is General Fund and $2.91 billion is federal
ARP fiscal relief funds.
Major Federal and State Broadband Programs and Projects Reaching Critical Milestones and
Deadlines. The administration is making important decisions as it moves from planning into development
and implementation across the state’s broadband programs and projects. Middle-mile network architecture
decisions and final contract awards are expected within the calendar year. Last-mile project grant rounds are
opening midyear, ending with awards early next year. Project financing through the Broadband Loan Loss
Reserve Fund also is expected in 2023-24. Furthermore, key federal broadband infrastructure programs will
announce more federal funding midyear, with the state’s initial allocation of funding expected by the end of
2023-24. The status of each of these programs and projects also highlights important upcoming deadlines,
such as the federal ARP fiscal relief fund deadline to enter contracts by December 31, 2024 and spend funds
by December 31, 2026.
Governor’s Proposed Delays Help Address Budget Problem… The Governor’s 2023-24 budget proposes
to delay $1.125 billion in General Fund appropriations—$575 million for the Broadband Loan Loss Reserve
Fund and $550 million for last-mile projects—from 2022-23 and 2023-24 to 2024-25, 2025-26, and 2026-27 to
address the projected budget problem in 2023-24. We find the proposed delays to be prudent and worthy of
legislative consideration for three main reasons: (1) the delays (if approved) represent a relatively small portion
of the funding in the original spending plan—$1.125 billion of the $6 billion—across two programs; (2) starting in
2023-24, a significant amount of additional federal funding for broadband infrastructure is expected; and (3) the
administering programs remain in planning or early implementation, and the remaining appropriations from
2021-22 to 2023-24 will continue to fund program awards in the near term.
…But Larger Budget Problem Likely at May Revision, With Proposed Future Spending Likely
Unaffordable. We anticipate the budget problem to be about $7 billion larger at May Revision. Moreover, we
find that the state likely will be unable to afford the overall spending levels in 2024-25, 2025-26, and 2026-27
proposed in the Governor’s 2023-24 budget, including the resumption of delayed one-time spending for
broadband infrastructure. As a result, the delayed broadband infrastructure spending likely will not be affordable
in future years without reductions in other areas.
Recommend Spending Federal ARP Fiscal Relief Funds First, Evaluating Remaining General Fund in
Spending. We recommend the Legislature direct the administration through trailer bill language to spend federal
ARP fiscal relief funds first. We also recommend including increased encumbrance and expenditure reporting.
We also recommend the Legislature evaluate the updated spending plan to consider (1) how anticipated
additional federal funds could supplement existing and/or planned appropriations; (2) how General Fund
spending might be prioritized among existing programs and projects to achieve statutory goals; and (3) how,
based on this prioritization, spending delays and/or reductions (including delays in the Governor’s proposed
budget) could be made with the least adverse impact on meeting these statutory goals.
www.lao.ca.gov 1
2023-24 BUDGET
BACKGROUND
BROADBAND INFRASTRUCTURE Unserved Households Do Not Have Access to
Broadband. Unserved households can be defined
Various Components of Broadband
as those without access to broadband (as defined
Infrastructure. Broadband infrastructure allows
by FCC). According to the California Public Utilities
internet service providers (ISPs) and other
Commission (CPUC), there are 353,494 unserved
entities to provide high-speed internet access to
households in California as of December 31, 2020.
communities and households. This infrastructure
(CPUC expects updated data to be published
can be categorized into three groups based on the
in April 2023.)
distance covered, from longest to shortest distance:
Underserved Households Do Not Have
• Backbone or Long-Haul. Backbone
Access to Faster Broadband. Underserved
or long-haul infrastructure often uses
households can be defined as those with access to
high-capacity fiber-optic cables laid over
broadband, but not at 100 Mbps download speed
hundreds or thousands of miles to connect
and 20 Mbps upload speed. Faster broadband
different countries, states, and/or regions to
gives consumers the ability to, for example, do
the internet.
various internet activities simultaneously across
• Middle-Mile. Middle-mile infrastructure multiple devices. According to CPUC, there are
also often consists of fiber-optic cables laid
743,387 underserved households in California as of
over tens or hundreds of miles that, once
December 31, 2020.
connected to by an ISP, can deliver local
internet access. STATE’S 2021 BROADBAND
• Last-Mile. Last-mile infrastructure relies
INFRASTRUCTURE SPENDING PLAN
on antennae, cables, poles, wires, and
Administration and Legislature Reached
other components to connect middle-mile
Three-Year, Multibillion Dollar Broadband
infrastructure to individual communities
Infrastructure Agreement in 2021. In July 2021,
and households.
the administration and the Legislature agreed to
spend $6 billion over three fiscal years (starting
UNSERVED AND
in 2021-22) on broadband infrastructure. Out of
UNDERSERVED HOUSEHOLDS the $6 billion in the 2021 agreement, $4.3 billion
came from federal ARP fiscal relief funds and
Federal Communications Commission
(FCC) Provides Broadband Definition. The $1.7 billion came from the General Fund. (ARP
FCC defines broadband as high-speed internet fiscal relief funds must be encumbered [that is,
access that provides a minimum of 25 Megabits obligated or under contract] by December 31, 2024
per second (Mbps) download speed and 3 Mbps and expended [that is, spent on costs incurred] by
upload speed. (Mbps measures how much data December 31, 2026.)
can be downloaded or uploaded over a network Three Broadband Infrastructure Programs
connection.) Internet access at these speeds and Projects Funded by Spending Plan. The 2021
allow consumers to use the internet for a variety of agreement, now spending plan, funds three related
activities such as accessing information, studying broadband infrastructure programs and projects:
online, and working remotely. (Other factors such
• Statewide Open-Access Middle-Mile
as latency—how long it takes data to travel—and
Network. The state is building, leasing, and
reliability—how long a connection is maintained—
purchasing middle-mile infrastructure to
also affect whether consumers can access internet
create a network deployed primarily along
service at these speeds.)
the state’s highways and other rights of way.
2 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
The middle-mile network is expected to be Chapter 112 of 2021 (SB 156, Committee
available to ISPs, public entities, and other on Budget and Fiscal Review) Implements the
organizations that can deliver broadband, Broadband Infrastructure Agreement. The
particularly to unserved and underserved Legislature also passed (and the Governor signed)
communities and households. The 2021 SB 156 in July 2021 to implement the broadband
spending plan appropriated $3.25 billion infrastructure agreement. Senate Bill 156
in ARP fiscal relief funds in 2021-22 for the establishes the roles and responsibilities of state
middle-mile network. government entities involved in implementation,
• Last-Mile Projects. The state is providing including the Department of Technology (CDT), the
grants to ISPs, public entities, and other California Department of Transportation (Caltrans),
organizations to fund last-mile infrastructure and CPUC; requires the $2 billion appropriation for
projects that connect unserved and last-mile infrastructure projects to be evenly split
underserved communities and households to between rural and urban counties; and provides
middle-mile infrastructure. The 2021 spending some prioritization of program and project activities,
plan appropriated $2 billion ($1.1 billion such as identification of priority middle-mile
ARP fiscal relief funds and $900 million network locations that will enable last-mile projects
General Fund) across three fiscal years for to connect unserved communities and households.
last-mile project grants through CPUC’s (The rural-urban allocation split only is required until
California Advanced Services Fund (CASF) June 30, 2023, but we understand from CPUC that
program’s Federal Funding Account (FFA). this split will be maintained thereafter.)
• Broadband Loan
Loss Reserve Fund. Figure 1
The Broadband Loan Loss Original 2021 Broadband Infrastructure Spending Plan
Reserve Fund will be a
(In Millions)
program within CPUC’s CASF
program that will provide Funding Source
local government entities Fiscal General Federal Total
and nonprofit organizations Program or Project Year Fund Funds Funds
with grants to help them, for Middle-Mile Network 2021-22 — $3,250a $3,250
example, pay the costs of 2022-23 — — —
2023-24 — — —
debt issuance and establish
Subtotals (—) ($3,250) ($3,250)
and fund reserves for
Last-Mile Projects 2021-22 — $1,072b $1,072
broadband infrastructure
2022-23 $125 — 125
projects. The 2021 spending 2023-24 803 — 803
plan appropriated $750 million Subtotals ($928) ($1,072) ($2,000)
General Fund over three fiscal Broadband Loan Loss Reserve 2021-22 $50 — $50
years for the Broadband Loan Fund 2022-23 125 — 125
2023-24 575 — 575
Loss Reserve Fund.
Subtotals ($750) (—) ($750)
Figure 1 provides appropriations All Programs and Projects 2021-22 $50 $4,322 $4,372
by fiscal year and allocations by 2022-23 250 — 250
program or project as approved in 2023-24 1,378 — 1,378
Totals $1,678 $4,322 $6,000
the state’s original 2021 broadband
a The $3.250 billion in federal funds for the middle-mile network in 2021-22 was appropriated to
infrastructure spending plan.
the California Department of Technology out of the state’s American Rescue Plan (ARP) fiscal relief
allocation.
b The $1.072 billion in federal funds for last-mile projects in 2021-22 was appropriated to the
California Public Utilities Commission, of which $550 million was the state’s allocation from the
ARP’s Coronavirus Capital Projects Fund and $522 million was out of the state’s ARP fiscal relief
allocation.
www.lao.ca.gov 3
2023-24 BUDGET
CHANGES TO STATE’S 2021 Information Administration (NTIA) through four new
and existing broadband programs described below.
SPENDING PLAN
Majority of Funding Allocated to Broadband
Two Significant Changes to Spending
Equity, Access, and Deployment (BEAD)
Plan. Since July 2021, the administration and
Program. The BEAD program received
the Legislature have changed the state’s 2021
$42.45 billion of the $65 billion total, nearly all
broadband infrastructure spending plan in two
of which is to provide states, territories, and
main ways:
other jurisdictions with allocations for broadband
• $1.4 Billion Shift From Federal ARP adoption and deployment projects (primarily
Fiscal Relief Funds to General Fund in last-mile projects). State allocations from the
2021-22. Pursuant to Control Section 11.96 BEAD program are described below. (This brief
of the 2022-23 Budget Act, the fund source focuses on the federal BEAD program and Digital
for appropriations totaling $1.4 billion in Equity Act programs due to the significant amount
2021-22 shifted from ARP fiscal relief funds of additional federal funding available to the state
to the General Fund—$887 million for the for broadband programs or projects.)
middle-mile network and $522 million for
• Initial Allocation of $100 Million to Each
last-mile projects. (This shift was made
State ($5.3 Billion of Total Program Funds).
due to increased flexibility in the use of a
Each state will receive an initial allocation
portion of ARP fiscal relief funds.) After the
of $100 million, of which $5 million will be
shift, there is $2.9 billion in ARP fiscal relief
provided at the program outset to support
funds (as compared to $4.3 billion in the
state planning efforts.
2021 spending plan) allocated in 2021-22 for
• Additional Allocation to States Based on
broadband infrastructure.
Unserved Locations in High-Cost Areas
• $550 Million General Fund Added Across
($4.245 Billion of Total Program Funds).
2023-24 and 2024-25 for Increased
Each state will receive an allocation based on
Middle-Mile Network Costs. In June 2022,
the number of unserved locations in high-cost
the Legislature passed (and the Governor
areas of their state as a percentage of all such
signed) Chapter 48 of 2022 (SB 189,
locations nationwide.
Committee on Budget and Fiscal Review).
• Allocation of Remaining Funds to
In SB 189, the Legislature stated a goal to
States Based on Unserved Locations
appropriate an additional $550 million General
($32.056 Billion of Total Program Funds).
Fund ($300 million in 2023-24 and $250 million
Each state will receive an allocation from
in 2024-25) for increased costs to build, lease,
remaining program funds based on the
and purchase the state’s middle-mile network.
number of unserved locations in their state as
Figure 6 on page 11 reflects these significant
a percentage of all such locations nationwide.
changes (as well as the proposed delays in the
Digital Equity Act Programs Funding. The
2023-24 Governor’s Budget).
Digital Equity Act programs received $2.75 billion
for three grant programs to improve digital equity
RECENT MAJOR FUNDING
across specific populations such as low-income
INCREASE FOR FEDERAL
households, racial and ethnic minorities, and
BROADBAND PROGRAMS
rural communities:
Federal Infrastructure Investment and Jobs
• State Digital Equity Planning Grant
Act (IIJA) Included $65 Billion for Broadband
Program ($60 Million of Total Program
Programs Nationwide. In November 2021, the
Funds). Each state will receive an allocation
federal IIJA was signed into law providing $65 billion
to support its development of a digital equity
for broadband programs. A majority of the funding is
plan, which will identify barriers to digital
managed by the National Telecommunications and
equity and plan how to address related
4 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
outcomes across program areas such as STATUS OF MAJOR FEDERAL AND
education and health care.
STATE BROADBAND PROGRAMS
• State Digital Equity Capacity Grant
AND PROJECTS
Program ($1.44 Billion of Total Program
In this section, we provide high-level updates
Funds). Each state will receive annual
on the status of each state broadband program
allocations over five calendar years to support
and project in the spending plan, as well as on
implementation of their digital equity plans,
the federal BEAD program and Digital Equity Act
including related projects.
programs. Figure 2 on the next page and Figure 3
• Digital Equity Competitive Grant Program
on page 7 provide estimated time lines for each
($1.25 Billion of Total Program Funds).
program and project, with specific dates and other
Specific types of state entities could receive
details provided under each program or project
annual allocations over five calendar years to
section. (The time lines below are subject to change
implement digital equity projects.
based on, for example, administrative delays and
Enabling Middle Mile Broadband funding changes.)
Infrastructure Program Funding. The Enabling
Middle-Mile Network
Middle Mile Broadband Infrastructure Program
received $1 billion to build, improve, and/or Estimated Length of 10,000 Miles at Total
purchase middle-mile infrastructure. (We do not Cost of More Than $4.5 Billion. In May 2022,
have any information as to whether or not the state CDT presented a network map that spans an
applied for and/or receive a notice of award from estimated 10,000 miles across the state. Caltrans
this program.) uses the map to guide its pre-construction
Tribal Broadband Connectivity Program work on individual network segment projects,
Funding. The Tribal Broadband Connectivity which Caltrans expects to complete by the end
Program received $2 billion, in addition to of 2024. CDT estimates that the total cost to
the $980 million appropriated by the federal build the network (that is, the cost of standalone
Consolidated Appropriations Act of 2021, to provide construction projects without, for example, any
tribal governments with allocations for broadband leasing or purchasing of middle-mile infrastructure)
adoption and deployment. is more than $4.5 billion. However, Caltrans’
pre-construction work could determine that at
Remainder of Funding Overseen by FCC
least some segments are not needed to complete
Through Affordable Connectivity Program
the network.
(ACP). The remaining funding for broadband
programs under IIJA is overseen by FCC Decisions to Finalize Network Architecture
through the ACP, which provides low-income Expected in Next Few Months. CDT expects to
households with monthly subsidies to pay for finish its review of network construction contract
internet service and one-time subsidies to pay for bids and lease and purchase agreements in the
internet-connected devices. According to data from next few months. Once its review is finished,
the Universal Service Administrative Company, CDT will finalize the network architecture as a
which administers the ACP as directed by FCC, combination of joint-build construction projects,
33 percent of eligible households in California are leases and purchases of existing middle-mile
enrolled in the ACP as of March 6, 2023. (There are infrastructure, and standalone construction
almost 6 million eligible households in California.) projects. This combination will allow CDT to reduce
the total cost of the network from the more than
$4.5 billion needed for a standalone network
build to within the $3.8 billion appropriated by
the Legislature.
www.lao.ca.gov 5
2023-24 BUDGET
Figure 2
Estimated Major State Broadband Program and Project Time Linesª
2023 2024 2025 2026 2027 2028 2029
Pre-Construction Work Continues
Majority of Construction Starts Completed
Federal Deadline
Final Network Architecture Decisions
Signed Contracts to Build and Lease Network
Middle-Mile
Network Pre-Construction Work Completed
Federal ARP Fiscal Relief Funds Encumbrance Deadline
Federal ARP Fiscal Relief Funds Federal Expenditure Deadline
Construction Completed
CASF FFA Grant Round #1 Applications
CASF FFA Grant Round #1 Application Review
CASF FFA Grant Round #1 Awards
CASF FFA Grant Round #2 Applications
CASF FFA Grant Round #1 Project Construction Starts
Last-Mile CASF FFA Grant Round #2 Application Review
Projects
CASF FFA Grant Round #2 Awards
Federal ARP Fiscal Relief Funds Encumbrance Deadline
CASF FFA Grant Rounds #1 and #2 Project Construction
CASF FFA Grant Rounds #1 and #2 Project Construction Completed
Federal ARP Fiscal Relief Funds Expenditure Deadline
Proposed Decision
Broadband
Loan Loss
Broadband Loan Loss Reserve Fund Round #1
Reserve Fund
a Approximate time lines based on information available as of March 20, 2023.
ARP = American Rescue Plan and CASF FFA = California Advanced Services Fund Federal Funding Account.
6 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
Figure 3
Estimated Major Federal Broadband Program and Project Time Linesª
2023 2024b 2025 2026 2027 2028 2029
FCC Publishes Final Map
NTIA Announces Program Allocations
California's Five-Year Action Plan Due to NTIA Completed
Initial Proposals Due to NTIA
State Challenge Process
BEAD Initial Proposal Approval and 20 Percent Funding Release
Program
Implementation Starts With 20 Percent Funding
Final Proposals Due to NTIA
Final Proposal Approval and Remaining Funding Release
Implementation Starts With All Funding
State Digital Equity Plan Due to NTIA
State Capacity Program - Application and Awards
Competitive Program - Application and Awards
State Capacity Program - Implementation Starts
Digital Equity Act
Programs Both Programs - Implementation Starts
Competitive Program - Implementation Completed
State Capacity Program - Implementation Continues
State Capacity Program - Implementation Completed
a Approximate time lines based on information available as of March 20, 2023.
b Full-year time lines in 2024 and future years do not indicate specific dates or time lines. Rather, they indicate time frames within which specific dates or time lines will be forthcoming.
BEAD = Broadband Equity, Access, and Deployment; FCC = Federal Communications Commission; and NTIA = National Telecommunications and
Information Administration.
www.lao.ca.gov 7
2023-24 BUDGET
Signed Contracts to Build, Lease, and
Figure 4
Purchase Network Expected by End of 2023.
CDT expects all contracts necessary to build, lease, CASF FFA Allocations for
and purchase individual network segments will be Rural Counties
signed by the end of 2023, which will encumber (In Millions)
both the federal ARP fiscal relief funds and General
Fund. However, of the $3.8 billion appropriated by County Allocation
the Legislature, only $2.4 billion is federal ARP fiscal Alpine $7.0
relief funds that must be encumbered by December Amador 57.2
Calaveras 30.8
31, 2024 and expended by December 31, 2026.
Colusa 29.0
(General Fund is not subject to the same
Del Norte 10.3
encumbrance and expenditure deadlines.) El Dorado 111.9
Glenn 25.1
Estimated Network Maintenance and
Humboldt 59.5
Operations Costs Not Yet Available. Once the
Inyo 13.2
network is completed, it will need to be maintained Kings 37.7
and operated as ISPs and other entities connect to Lake 28.4
Lassen 24.9
the network and provide broadband to communities
Madera 66.6
and households. While CDT, GoldenStateNet
Mariposa 40.8
(the network’s third-party administrator), and Mendocino 57.4
other entities have outlined considerations for the Modoc 23.9
Mono 10.6
network’s business model once completed, no
Nevada 74.9
estimate of the costs to maintain and operate the
Plumas 42.3
network is available at this time. San Benito 10.4
Sierra 12.5
Last-Mile Projects Siskiyou 45.8
Sutter 20.4
CPUC CASF FFA Rulemaking Procedure
Tehama 74.8
Complete. In April 2022, CPUC finished its Trinity 29.7
rulemaking procedure for the new FFA within Tuolumne 15.5
Yuba 39.4
the commission’s CASF program. The decision
Total $1,000.0
adopted rules and guidelines for the new FFA,
CASF FFA = California Advanced Services Fund Federal Funding
including county designations as rural or urban
Account
and calculated allocations for each county in
compliance with SB 156. Each county receives
First CASF FFA Grant Application Round
an initial allocation of $5 million. The remainder
Expected to Open in June, Second Round in
of the allocation is calculated based on the
January. CPUC expects to open its first CASF FFA
county’s share of California households, as a
grant application round in June, receive all grant
proportion of either all rural counties or all urban
applications by August, review the applications
counties, without access to broadband with at
from August to December, and award grants in
least 100 Mbps download speed. As previously
January 2024. A second round also is expected to
mentioned, while the rural and urban funding split is
open in January 2024, receive all grant applications
only maintained through June 30, 2023 by SB 156,
by March, review the applications from March
we understand from CPUC that they will maintain
to November, and award grants in December
this split thereafter. Figure 4 and Figure 5 provide
2024. In each round, construction is expected
the allocations by county, divided by rural or urban
to continue through the ARP fiscal relief funds
county designations.
expenditure deadline of December 31, 2026. Of the
$2 billion in previous or planned last-mile project
appropriations, only $550 million is ARP fiscal relief
funds subject to the deadline.
8 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
Broadband Loan Loss Reserve Fund
Figure 5
CPUC Broadband Loan Loss Reserve Fund
CASF FFA Allocations for
Rulemaking Procedure Remains Active. The
Urban Counties
CPUC rulemaking procedure for the Broadband
(In Millions)
Loan Loss Reserve Fund remains active, with a
revised staff proposal and proposed decision to
County Allocation
implement the fund expected by July 1. Both CPUC
Alameda $24.5 and the California Infrastructure and Economic
Butte 19.2
Development Bank entered into an interagency
Contra Costa 16.1
agreement on the Broadband Loan Loss Reserve
Fresno 61.2
Imperial 14.0 Fund in November 2022, and plan to continue
Kern 31.3 working together on its implementation.
Los Angeles 104.7
First Broadband Loan Loss Reserve Fund
Marin 11.5
Merced 27.3 Application Round in 2023-24. While the first
Monterey 17.3 application round of the Broadband Loan Loss
Napa 10.7
Reserve Fund is expected to open in 2023-24, the
Orange 92.0
exact time line to receive and review applications
Placer 30.3
Riverside 50.6 and award funds remains unknown. While the
Sacramento 38.7 total amount of grants available in the first round
San Bernardino 59.7
is also unknown, the Governor’s budget proposes
San Diego 81.3
$175 million in 2023-24 with the remaining balance
San Francisco 10.4
San Joaquin 29.4 of $575 million delayed to 2024-25 ($300 million) and
San Luis Obispo 22.3 2025-26 ($275 million).
San Mateo 10.4
Santa Barbara 15.9 Federal BEAD Program
Santa Clara 36.0
Santa Cruz 10.3 Initial Planning Funds Awarded in November
Shasta 32.4 2022. NTIA awarded the state $5 million in initial
Solano 17.0
planning funds from the state’s initial allocation of
Sonoma 19.2
$100 million in November 2022. These funds must
Stanislaus 25.4
Tulare 45.1 be used to support state planning efforts, including
Ventura 20.4 the preparation and submission of a five-year action
Yolo 15.9
plan. The five-year action plan will, for example,
Total $1,000.5a
provide information about the state’s approach to and
a Difference from $1 billion total allocation due to rounding.
goals for broadband access, adoption, affordability,
CASF FFA = California Advanced Services Fund Federal Funding
Account and equity. NTIA expects the five-year action plan to
inform the state’s initial proposal on how it will use the
$1 Billion in Awards Available in First Round. first 20 percent of its BEAD program allocation. The
CPUC also estimates the total amount of grants state must submit a five-year action plan to NTIA no
available in the first CASF FFA grant application later than August 28.
round will be $1 billion (including all $550 million in State’s Program Allocation Expected by End
ARP fiscal relief funds). While CPUC has indicated of June. NTIA will announce each state’s program
that the total amount of grants available in the allocation from the BEAD program by the end of
second round will be $1 billion, we would note that June. Once NTIA announces program allocations,
the Governor’s 2023-24 budget proposes to delay each state must submit an initial proposal that
at least $350 million of the $1 billion that is available describes how the state plans to use program
(after first round awards) from 2023-24 to 2025-26 funds for grants to ISPs, public entities, and other
($200 million) and 2026-27 ($150 million). (We provide organizations within 180 days. Based on NTIA’s time
more detail on the proposed delays in the “2023-24 line, initial proposals will need to be submitted to NTIA
Governor’s Budget” section later in this brief.) before the end of 2023. Once approved, the state will
www.lao.ca.gov 9
2023-24 BUDGET
receive no less than 20 percent of the state’s program Federal Digital Equity Act Programs
allocation. All remaining funds will be available
State Digital Equity Planning Grant Program
once the state submits, and NTIA approves, a final
Award Received in November 2022. NTIA awarded
proposal (no later than one year after NTIA approves
the state $4 million from the State Digital Equity
the initial proposal).
Planning Grant Program to support its development
CPUC Federal BEAD Program Rulemaking of a digital equity plan. California’s State Digital
Procedure Now Active. The CPUC rulemaking Equity Plan must be submitted to NTIA no later
procedure for the state’s implementation of the than November 30.
federal BEAD program is now active. An order
More Information Forthcoming on Capacity
instituting rulemaking provides initial issues to
and Competitive Grant Programs. NTIA will provide
address including specific program definitions,
more information on the Capacity and Competitive
prioritization of proposed broadband projects, and
Grant Programs to states and other jurisdictions over
the implementation of a challenge process. According
the next several months.
to the order instituting rulemaking, CPUC intends to
complete its rulemaking procedure within 18 months.
GOVERNOR’S 2023-24 BUDGET
PROPOSAL ASSESSMENT
Governor’s 2023-24 Budget Proposes Delay Governor’s Proposed Spending Delays Help
of $1.125 Billion General Fund in Previous Address Current Budget Problem… In The
and Planned Appropriations. To help address 2023-24 Budget: Overview of the Governor’s
the projected budget problem in 2023-24, the Budget, our office evaluated the proposed budget
Governor’s 2023-24 budget proposes to delay solutions in the Governor’s 2023-24 budget.
$575 million General Fund for the Broadband Loan We found that the administration’s proposed
Loss Reserve Fund and $550 million General Fund spending-related delays and reductions, including
in last-mile project funding—otherwise scheduled broadband infrastructure spending delays, were
for 2022-23 and 2023-24—to 2024-25, 2025-26, a prudent alternative to tapping into the state’s
and 2026-27. If approved by the Legislature, the reserves. However, we also recommended the
proposed delays would maintain $175 million Legislature use specific criteria to evaluate which
General Fund for the Broadband Loan Loss Reserve recent augmentations to maintain versus which
Fund and $253 million General Fund for last-mile ones to reduce or delay, potentially considering
projects in 2023-24. different spending-related solutions than proposed
Administration Maintains $300 Million in the Governor’s 2023-24 budget. Based on
General Fund in 2023-24 for Increased these criteria, we consider the proposed delays
Middle-Mile Network Costs. Consistent with the of broadband infrastructure spending worthy
legislative goal in SB 189, the Governor’s 2023-24 of legislative consideration. First, the delays (if
budget includes $300 million General Fund in approved) would maintain the planned schedule for
2023-24 and $250 million General Fund in 2024-25 spending the bulk of the federal and state funding
for increased costs to build, lease, and purchase from the original spending plan—$4.875 billion
the state’s middle-mile network. of the $6 billion—across the three programs and
projects. Second, starting in 2023-24, a significant
Figure 6 shows the updated spending plan,
amount of additional federal funding from the BEAD
incorporating the previously discussed changes
program (which we discuss in more detail below) is
already made as well as the Governor’s proposed
expected. Third, CPUC’s CASF FFA grant program
spending delays.
and Broadband Loan Loss Reserve Fund program
remain in planning or early implementation, and
10 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
the remaining appropriations from
Figure 6
2021-22 to 2023-24 will continue
Updated Broadband Infrastructure Spending Plan,
to facilitate program funding and
Incorporating Delays Proposed in Governor’s Budget
grant awards.
(In Millions)
…But Larger Budget Problem
Likely at May Revision, With
Funding Source
Proposed Future Spending
Fiscal General Federal Total
Likely Unaffordable. However, in
Program or Project Year Fund Funds Funds
The 2023-24 Budget: Multiyear
Middle-Mile Network 2021-22 $887a $2,363b $3,250
Assessment, our office projects
2022-23 — — —
the budget problem to increase at 2023-24c 300 — 300
May Revision by about $7 billion. 2024-25c 250 — 250
2025-26 — — —
Moreover, we find that the state
2026-27 — — —
likely will be unable to afford the
Subtotals ($1,437) ($2,363) ($3,800)
overall spending levels in 2024-25,
Last-Mile Projectsd 2021-22 $522e $550f $1,072
2025-26, and 2026-27 proposed
2022-23 125 — 125
in the Governor’s 2023-24 budget, 2023-24 253 — 253
including the resumption of delayed 2024-25 200 — 200
2025-26 200 — 200
one-time spending for broadband
2026-27 150 — 150
infrastructure. Therefore, in order to
Subtotals ($1,450) ($550) ($2,000)
preserve the state’s reserves to pay
Broadband Loan Loss Reserve 2021-22 — — —
for core services if revenues decline Fundg 2022-23 — — —
further or in the event of a recession, 2023-24 $175 — $175
2024-25 300 — 300
we recommend the Legislature
2025-26 275 — 275
consider additional spending-related
2026-27 — — —
delays and reductions than currently Subtotals ($750) (—) ($750)
proposed by the Governor. As
All Programs and Projects 2021-22 $1,409 $2,913 $4,322
a result, the delayed broadband 2022-23 125 — 125
infrastructure spending likely will not 2023-24 728 — 728
2024-25 750 — 750
be affordable in future years without
2025-26 475 — 475
reductions in other areas.
2026-27 150 — 150
Additional Federal Funds Total $3,637 $2,913 $6,550
From BEAD Program Available a Pursuant to Control Section 11.96 of the 2022-23 Budget Act, the Department of Finance shifted
$887 million for the middle-mile network from American Rescue Plan (ARP) fiscal relief funds to
Starting in 2023-24. Though the
General Fund in 2021-22.
state’s BEAD program allocation b The remaining $2.363 billion in federal funds for the middle-mile network in 2021-22 is state ARP
fiscal relief funds.
will not be available until the end c The additional $550 million General Fund for the middle-mile network ($300 million in 2023-24 and
of June, the state likely will receive $250 million in 2024-25) is consistent with the legislative goal to provide these amounts (subsequent
to the submission of a statutory report) in Chapter 48 of 2022 (SB 189, Committee on Budget and
up to 20 percent of its allocation by Fiscal Review).
the end of 2023-24. We anticipate d All last-mile project amount and timing changes from the initial spending plan for 2023-24 through
2026-27 are proposed changes in the Governor’s 2023-24 budget.
this allocation to be in the tens if e Pursuant to Control Section 11.96 of the 2022-23 Budget Act, the Department of Finance shifted
not hundreds of millions of dollars. $522 million for last-mile projects from ARP fiscal relief funds to General Fund in 2021-22.
f The remaining $550 million in federal funds for last-mile projects in 2021-22 is the state’s allocation
A significant amount of additional
from the ARP’s Coronavirus Capital Projects Fund.
federal funds—at least in the g All Broadband Loan Loss Reserve Fund amount and timing changes from the initial spending plan
for 2021-22 through 2025-26 are proposed changes in the Governor’s 2023-24 budget.
hundreds of millions of dollars—is
expected thereafter by the end of
funds, the appropriations that remain for last-mile
2024-25, when the state will receive the remaining
projects in 2023-24 and that are delayed to 2024-25,
80 percent of its program allocation. While the IIJA
2025-26, and 2026-27 could be supplemented with
requires states use federal funds for broadband
funds from the state’s BEAD program allocation.
infrastructure to supplement and not supplant state
www.lao.ca.gov 11
2023-24 BUDGET
Delaying or Reducing General Fund for could be built with General Fund as they are
Increased Middle-Mile Costs in 2023-24 and deemed necessary to sufficiently complete
2024-25 Another Potential Solution to Budget the network. This approach would maintain
Problem. Consistent with the legislative goal in progress on the middle-mile network but,
SB 189, the Governor’s 2023-24 budget maintains in the near term, make available additional
$550 million General Fund across 2023-24 and General Fund in 2023-24 to solve the
2024-25 for the middle-mile network. However, budget problem.
given the budget problem, the Legislature might • Federal BEAD Program Permits Use of
consider whether this increased General Fund Allocations on Middle-Mile Infrastructure
spending could be delayed or reduced. Costs. Federal BEAD program rules allow
• Network Architecture Decisions and states to use some of their allocations for
Ongoing Pre-Construction Work Likely Will middle-mile infrastructure costs, if additional
Affect Total Network Cost. CDT maintains middle-mile infrastructure is required to
that all 10,000 miles of the middle-mile connect last-mile projects. While most of
network must be built, leased, and purchased the federal BEAD program allocation likely
to be available for last-mile projects (at will be used for last-mile projects, at least
least some of which will be funded by the some additional federal funds (though not
CASF FFA and federal BEAD programs), to the entire $550 million) could be used for the
increase competition among ISPs, and cover middle-mile network.
maintenance and operations costs. Whether
Budget Constraints Warrant Prioritizing
or not all 10,000 network miles are needed will
Among Goals and Projects. More than half
not be known, however, until final decisions
of the funding in the updated broadband
are made about the network’s architecture,
infrastructure spending plan—$3.637 billion out
pre-construction work is completed, and
of the $6.55 billion—is now General Fund. While
its maintenance and operations costs are
prioritizing the encumbrance and expenditure of
estimated. The absence of this information
ARP fiscal relief funds to meet federal deadlines is
cautions against making assumptions about
important, General Fund resources are more flexible
the required length of the middle-mile network
and can be reconsidered in order to address the
and its associated cost.
immediate budget problem. Moreover, considering
• Pre-Construction Work Also Will Determine whether the current prioritization of available
the Order and Sufficiency of Network General Fund will achieve the goals in SB 156 is
Segments. CDT expects pre-construction important. For example, the expeditious connection
work led by Caltrans to be completed by the of unserved and underserved communities (a
end of 2024. This pre-construction work will goal stated for the CASF FFA) might warrant
determine whether planned segments of the redirection of at least some available funding from
middle-mile network will be sufficient for its one program or project to another. The Broadband
completion, and in what order each of the Loan Loss Reserve Fund, for example, might help
segments should be built, leased, and/or local governments and nonprofit organizations
purchased. Without knowing which segments finance broadband infrastructure projects, but
are sufficient and in what order they should be current economic conditions might favor direct
completed, prioritizing the encumbrance and awards of last-mile project funding to some of those
expenditure of the $2.363 billion in ARP fiscal same entities.
relief funds by the federal deadlines to build,
lease, and purchase initial network segments
would be prudent. Subsequent segments
12 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
RECOMMENDATIONS Consider Delaying or Reducing General
Fund Appropriation for Increased Middle-Mile
Prioritize Use of ARP Fiscal Relief Funds to
Network Costs as One Potential Budget
Meet Federal Deadlines. We recommend the
Solution. We recommend the Legislature consider,
Legislature prioritize encumbrance and expenditure
as part of its evaluation of the updated spending
of the $2.363 billion in federal ARP fiscal relief
plan and prioritization of available General Fund,
funds appropriated for middle-mile network and
delaying or reducing the $550 million General Fund
$550 million for last-mile projects. The Legislature
across 2023-24 and 2024-25 for increased costs to
could consider whether to statutorily direct CDT
build, lease, and purchase the state’s middle-mile
and CPUC to use these funds before any General
network. While this delay or reduction could affect
Fund is encumbered and expended. We also
the architecture and length of the network, our
recommend the Legislature consider requiring more
assessment supports consideration of this funding
frequent updates on encumbrance and expenditure
as one potential solution to the budget problem.
information from DOF to ensure federal deadlines
To help inform its consideration of this potential
will be met. The United States Department of the
funding delay or reduction, we also recommend
Treasury currently requires the state to file quarterly
the Legislature request additional information
encumbrance and expenditure reports but, to avoid
about factors that could affect the total cost of the
the potential loss of federal funds, the Legislature
network such as the status of pre-construction
might consider requiring monthly reports until
work on network segments and the estimated
December 31, 2026.
ongoing maintenance and operations costs for
Evaluate Updated Spending Plan and
the network.
Prioritize Available General Fund to Achieve
Statutory Goals. We recommend the Legislature
evaluate the updated spending plan to consider
(1) how anticipated additional federal funding from
the IIJA could supplement existing and planned
appropriations; (2) how General Fund spending
might be prioritized among existing programs
and projects to achieve the goals of SB 156; and
(3) how, based on this prioritization, spending
delays and/or reductions (including delays in the
Governor’s proposed budget) could be made
with the least adverse impact on meeting these
statutory goals.
www.lao.ca.gov 13
2023-24 BUDGET
14 LEGISLATIVE ANALYST’S OFFICE
2023-24 BUDGET
www.lao.ca.gov 15
2023-24 BUDGET
LAO PUBLICATIONS
This report was prepared by Brian Metzker, and reviewed by Mark C. Newton and Carolyn Chu. The Legislative
Analyst’s Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service, are
available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000, Sacramento,
California 95814.
16 LEGISLATIVE ANALYST’S OFFICE