The 2026-27 Budget: Judicial Branch
Read the report at Legislative Analyst's Office ↗
analysis full
2026-27 BUDGET
The 2026-27 Budget:
Judicial Branch
GABRIEL PETEK | LEGISLATIVE ANALYST | FEBRUARY 2026
SUMMARY
In this brief, we provide an overview of the proposed funding for the judicial branch in 2026-27. We also
analyze the Governor’s budget proposals related to court construction and facility modification projects.
Governor Proposes Funding for Ten Court Facility Projects. The Governor’s budget includes
$320 million in lease revenue bond authority, $130 million from the General Fund, and reimbursement
authority for ten court facility projects. This would support eight existing construction projects, a new project
to relocate 24 courtrooms within Los Angeles County, and additional funding to address cost increases for
the Orange Central Justice Center (CJC) facility modification project.
No Concerns With Requested Amounts… The state’s multiyear deficits means that any new General
Fund spending comes at the expense of other programs, meaning new spending must meet a higher bar for
approval. However, we find the proposed projects meet this higher bar as they seek to address critical health,
safety, and other needs in buildings frequented by the public and their costs and scope seem reasonable.
…But Various Factors Raise Questions About Long-Term Plan for Addressing Court Facility
Needs. The state’s slow pace at initiating construction projects, as well as increasing costs, raise questions
about the long-term plan for fully addressing court facility needs. Delays in initiating projects could result in
significant, unexpected costs occurring simultaneously if facilities worsen to the point of needing immediate
replacement. As such, it could be reasonable to consider whether the state should concurrently or
alternatively prioritize facility modification projects to extend and/or improve the usability of existing facilities.
Recommend Legislature Direct Judicial Branch to Report on Long-Term Plan for Facilities Based
on Legislative Direction. Given the magnitude of the judicial branch’s facility needs and deficits facing the
state General Fund, it cannot fully address such needs in the short run. Accordingly, we recommend the
Legislature instead consider how much General Fund to dedicate annually to court facility needs. We also
recommend it direct the judicial branch to provide by January 2028 a long-term plan for addressing facility
needs. This should include an assessment of how the annual funding amount chosen by the Legislature
should be divided between new construction and facility modification projects to maximize the life of existing
facilities. Additionally, given the cost and scope changes for the CJC project, we recommend the Legislature
consider increasing oversight of facility modification projects receiving one-time General Fund support to
help ensure it receives accurate and complete data and that state funds are used cost-effectively.
www.lao.ca.gov 1
analysis full
2026-27 BUDGET
OVERVIEW increased during this period—from 46 percent in
2016-17 to a high of 59 percent in 2022-23 and
Background 2023-24, before decreasing slightly to 56 percent in
Roles and Responsibilities. The judicial 2025-26. Since 2019-20, the majority of the judicial
branch is responsible for the interpretation of branch budget has been supported by the General
law, the protection of people’s rights, the orderly Fund. This growth is due to various reasons,
settlement of all disputes, and the adjudication including increased operational costs.
of accusations of legal violations. The branch Governor Proposes $5.5 Billion in State
consists of statewide courts (the Supreme Court Funds for Judicial Branch. For 2026-27, the
and the Courts of Appeal), trial courts in each Governor’s budget includes $5.7 billion from all
of the state’s 58 counties, and state entities of fund sources in support for the judicial branch.
the judicial branch (Judicial Council, Judicial This amount includes about $5.5 billion from all
Council Facility Program, and the Habeas Corpus state funds (General Fund and special funds), an
Resource Center). The branch receives support increase of $152 million (2.8 percent) above the
from several funding sources including the state revised amount for 2025-26, as shown in Figure 2.
General Fund, civil filing fees, criminal penalties and (These totals do not include expenditures from
fines, county maintenance-of-effort payments, and local reserves or trial court reserves.) Of this
federal grants. amount, about $3.3 billion (60 percent) is from the
Majority of Support From General Fund. As General Fund. This is a net increase of $220 million
shown in Figure 1, total operational funding for the (7 percent) from the revised 2025-26 General Fund
judicial branch has steadily increased from 2016-17 amount. This net increase reflects various changes,
through 2025-26. The percent of total operational including increased operational costs and facility
funding from the General Fund has also steadily modification costs.
Figure 1
Total Judicial Branch Fundingª
(In Billions)
$6
Local Revenues
State Special Funds
5
General Fund
4
3
2
1
2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27
(estimated) (proposed)
ª State law requires excess property tax revenues collected by county offices of education beyond their annual funding allotment be used to offset
state General Fund support of trial courts. This chart reflects these revenues as state special funds.
2 LEGISLATIVE ANALYST’S OFFICE
analysis full
2026-27 BUDGET
Figure 2
Judicial Branch Budget Summary—All State Funds
(Dollars in Millions)
Change From 2025-26
2024-25 2025-26 2026-27
Actual Estimated Proposed Amount Percent
State Trial Courts $3,885 $4,037 $4,090 $53 1.3%
Supreme Court 53 58 57 -1 -2.5
Courts of Appeal 283 298 312 14 4.8
Judicial Council 281 283 280 -4 -1.3
Judicial Branch Facility Program 585 654 743 89 13.6
Habeas Corpus Resource Center 18 20 20 — 0.2
Totals $5,105 $5,350 $5,502 $152 2.8%
Trial Courts Report $405 Million in Reserves facilities. In a November 2019 assessment of its
at End of 2024-25. Trial courts have a limited facilities, the judicial branch identified a need for a
ability to keep and carry over any unspent funds total of 80 construction projects—56 new buildings
(also known as “reserves”) from one fiscal year to and 24 renovations—totaling $13.2 billion. These
the next. Specifically, trial courts are only allowed projects were categorized into five groups—
to carry over funds equal to 3 percent of their and ranked within each group—in the following
operating budget from the prior fiscal year under descending priority order: 18 immediate need
current law. However, certain funds held in the projects ($2.3 billion), 29 critical need projects
reserve—such as those that are encumbered, ($7.9 billion), 15 high need projects ($1.3 billion),
designated for statutory purposes, or funds held 9 medium need projects ($1.6 billion), and 9 low
on a court’s behalf by Judicial Council for specific need projects ($100 million). Additionally, in August
projects—are not subject to this cap, meaning they 2024, the judicial branch identified 22,396 deferred
also can generally be carried over. At the end of maintenance projects totaling around $5.4 billion.
2024-25, trial courts reported having $405 million in Of this estimated cost, the state would be
reserves. Of this amount, $310 million (76 percent) responsible for around $4 billion (74 percent).
is not subject to the cap. This amount consists of (The remaining amount would generally be the
funds that are encumbered ($152 million), statutorily responsibility of counties that share space in
excluded ($124 million), designated for prepayments court facilities.)
or other purposes ($16 million), or held by Judicial Existing Construction Account Insolvent.
Council on behalf of the trial courts for specific State law authorizes Judicial Council to construct
projects ($18 million). This leaves $95 million trial court facilities and established a state special
(24 percent) in reserves subject to the cap. This is fund—the State Court Facilities Construction
less than the $106 million the trial courts could have Fund (SCFCF) to support construction and other
retained under the current 3 percent cap. facility-related expenses. (A second construction
account was consolidated into the SCFCF in
COURT FACILITIES 2021-22.) The SCFCF is used to support both the
construction and maintenance of court facilities
Background
and is mainly supported by criminal and civil fines
Judicial Branch Has Extensive Facility Needs. and fees. The amount of revenue deposited into
The judicial branch currently manages around 430 the fund steadily declined over the past years,
facilities across all 58 counties. Its facility program resulting in expenditures routinely exceeding
is responsible for various activities including revenues. Additionally, since 2009-10, nearly
maintaining these facilities, managing leases, and $1.7 billion has been transferred from the judicial
constructing new courthouses to replace outdated branch’s construction accounts to the General
www.lao.ca.gov 3
analysis full
2026-27 BUDGET
Fund or to support trial court operations. These “beyond rated life but serviceable”). Annual funding
transfers were originally made to help address the typically is used to address projects in the highest
fiscal difficulties then facing the state. This led to two priority categories, such as major flooding or
the fund becoming insolvent and required various substantial roof damage. Any unaddressed projects
actions be taken—most notably the cancelation essentially add to the judicial branch’s deferred
and suspension of projects supported by the maintenance list. In recent years, some one-time
construction account. Currently, the fund remains funding has been also provided from the General
insolvent and is estimated to require a General Fund Fund to support specific, larger facility modification
backfill in the tens of millions of dollars annually projects. These are typically higher-priority projects
through 2036-37 to maintain existing facility-related whose costs would have otherwise required a
activities and to pay the debt service for completed significant portion of the discretionary funding
construction projects. in one or more years. Such projects typically go
New Construction Supported by the General through the annual budget review process as an
Fund. For a period, the SCFCF’s insolvency operations request rather than a capital outlay
halted the judicial branch’s construction program. request. In other words, these projects do not
However, after the fiscal difficulties facing the necessarily undergo the same review as the new
state subsided, the state shifted support for construction projects. For example, some of these
the construction program to the state General projects may not go through formal review by
Fund. Specifically, the 2018-19 budget included Department of Finance (DOF) staff that focus on
$1.3 billion in lease revenue bond authority backed capital outlay.
by the General Fund—rather than the SCFCF—
Governor’s Proposal
to finance ten previously planned projects. This
The Governor’s budget includes $320 million
commitment effectively backfilled the $1.4 billion
in lease revenue bond authority, $130 million from
transferred from the SCFCF to the General Fund to
the General Fund, and reimbursement authority for
help address the state’s budget condition between
ten courthouse facility projects. These projects are
2009-10 and 2017-18. The 2021-22 budget formally
described in more detail below.
shifted support for the construction of any future
courthouses to the General Fund. When proposing Existing Construction Projects. The budget
new projects, the administration generally follows proposes $320 million in lease revenue bond
the ranked project priority list identified in the authority for the design-build phase of the new
judicial branch’s 2019 assessment of facility needs. San Luis Obispo Courthouse project. (While this
Since 2021-22, the construction or renovation of would not result in immediate General Fund costs,
12 of the highest ranked immediate need projects the lease revenue payments will come from the
have commenced. General Fund.) In addition, it proposes $47.6 million
one-time General Fund for the continuation of the
Some Facility Modification Projects
following construction projects:
Supported by General Fund. In addition to
construction projects, the judicial branch manages • $18.1 million reappropriation of funds for the
smaller facility modification projects. These performance criteria phase of the New Fresno
are projects that involve physical changes to a Courthouse project, which had been delayed
facility (or its building components) that improve due to an extended site selection process.
its designed level of functionality. The judicial
• $14.1 million for the construction phase of
branch currently receives about $80 million
projects to build out two courtrooms to
annually—$65 million from the SCFCF and
accommodate new judgeships in Kings and
$15.4 million from the General Fund—for use at
Sutter Counties.
Judicial Council’s discretion. Judicial Council
• $6.4 million for the working drawings and
maintains a list of modification projects and
construction phase of a project to build
categorizes them into one of six priority categories
out one courtroom to accommodate a new
(such as “immediately or potentially critical” or
judgeship in San Joaquin County.
4 LEGISLATIVE ANALYST’S OFFICE
analysis full
2026-27 BUDGET
• $5.1 million reappropriation of funds for greater scrutiny and must meet a higher bar for
the performance criteria phase of the New approval as it would reduce General Fund spending
Solano Hall of Justice project, which had elsewhere. Such a higher bar can include spending
been delayed due to an extended site to address critical infrastructure issues. We find that
selection process. the identified projects meet this higher threshold
• $2.3 million for the performance criteria phase as they seek to address critical health, safety, and
of the New Quincy Courthouse project in other facility needs in buildings frequented by the
Plumas County. public. Additionally, the costs and scopes of these
identified projects generally seem reasonable.
• $1.5 million for the performance criteria phase
The existing construction projects were largely
of the New Nevada City Courthouse project in
selected based on the judicial branch’s 2019 ranked
Nevada County.
list of facility project needs and require funding
Relocation of Los Angeles Spring Street
to continue moving forward. The projects related
Courtrooms. The budget proposes $11 million
to the relocation of the Los Angeles Spring Street
one-time General Fund to relocate 24 courtrooms
courthouses are also necessary as the landlord is
out of leased space in Los Angeles County. The
terminating the state’s lease of space. Without this
lease will not be extended as the building is
funding to build or modify space to relocate the
expected to be sold. Of this amount, $4.6 million
courtrooms into existing courthouses, service levels
would be used to relocate 17 courtrooms into six
would be impacted. Finally, the Orange CJC project
existing courthouses. The remaining $6.3 million
is already in progress and addresses key safety
would be used for the preliminary plans and
issues in a building with large numbers of people
working drawings phase of a project to renovate
visiting on a daily basis.
the existing Chatsworth Courthouse to build out
…But CJC Proposal Raises Questions About
six courtrooms.
Appropriate Oversight. While the CJC project
Additional Funding for the Orange Central
is necessary, the project’s cost has more than
Justice Center (CJC). The budget includes
doubled. Specifically, prior budgets included
$71 million limited-term General Fund ($36 million
$64.1 million for this project, which was estimated
in 2026-27 and $35 million in 2027-28) and
to cost a total of $70.2 million, with the county
$7.1 million SCFCF reimbursement authority
covering the remaining balance. The judicial
($3.6 million in 2026-27 and $3.5 million in 2027-28)
branch estimates that an additional $71 million will
for a previously approved facility modification
now be necessary to complete the project due to
project at the Orange CJC. (The reimbursement
various factors that were unidentified at the start
authority would allow the state to accept payment
of the project, including unanticipated asbestos
from Orange County for its portion of the project
remediation and the need to address new issues
costs as this is a shared facility.) This project
identified by the Office of the State Fire Marshall
generally addresses fire and egress safety issues.
(OFM). However, construction is currently only
This funding would be in addition to $64.1 million
25 percent complete and discussions with the
one-time General Fund provided in prior budgets.
OFM continue. This means that additional issues
could be identified that drive further cost increases.
Assessment
The sizeable increase in funding raises questions
No Concerns With Requested Amounts…
on whether sufficient oversight was in place to
As discussed in our January budget publication,
appropriately assess the scope of work and costs
The 2026-27 Budget: Overview of the Governor’s
before the project began. Sufficient oversight would
Budget, the state faces serious multiyear deficits
ensure the Legislature has the information it needs
that will need to be addressed. This means the
as it weighs court facility projects against its other
state lacks the necessary revenues to sustain
priorities. This is particularly important in tough
current expenditure levels. As such, any proposals
budget times with scarce General Fund resources.
that require new General Fund support require
www.lao.ca.gov 5
analysis full
2026-27 BUDGET
Total Costs of Court Facility Projects …Raising Questions About Long-Term Plan
Continue to Increase… As noted above, the for Addressing Court Facility Needs… The
judicial branch’s 2019 assessment estimated a slow pace in initiating construction projects, as
total of $13.2 billion would be needed to address well as the increasing costs, raises questions
80 projects. Of this amount, about $6.1 billion was about the long-term plan for fully addressing court
associated with 17 projects in Los Angeles County. facility needs. Delays in initiating projects means
In April 2024, the Los Angeles Superior Court that the facilities on the list could worsen to the
completed a reassessment of its facilities needs point where the state has no option but to replace
based on its operations. The estimated costs of them immediately. This could result in significant,
these 17 projects increased to around $14 billion. unexpected costs occurring simultaneously.
Similarly, while most of the remaining projects on For example, if multiple courthouse projects—
the 2019 list have not been reassessed, the costs including some large, multistory courthouses—
of projects in other parts of the state are likely needed to be started at the same time, it could
increasing. For example, the 2019 assessment require hundreds of millions of dollars in General
estimated the new Fresno Courthouse project Fund annually to pay for pre-construction costs
would cost $483 million. This project is currently or debt service. Under such a circumstance,
in the middle of pre-construction activities, the judicial branch and the state’s capacity to
which has resulted in an updated cost estimate appropriately conduct oversight of such projects
of $965 million—double the original estimate. In could be strained. At the same time, the condition
combination, as shown in Figure 3, it makes it of other facilities could worsen resulting in the
likely that at least $21 billion could be needed to need for new construction, facility modification, or
complete the list of 80 projects. These costs will deferred maintenance projects. As General Fund is
likely continue to increase over time due to inflation a major source of supporting these costs, it would
and various other factors. be prudent to have a long-term plan or strategy to
…And Pace of New Construction Projects Is address these needs while balancing other state
Slow… As shown in Figure 3, the state has only General Fund priorities.
initiated 12 (or 15 percent) of the construction …And Whether More Funds Should Be
projects identified in 2019. Additionally, the state’s Dedicated to Facility Modification Projects.
current plan is to initiate one new project a year. Given the current plan of starting one new
Absent any changes, this means the last immediate construction each year, it could be reasonable to
need project would be initiated in 2030-31. consider whether the state should concurrently or
Continuing at this pace means that it would take alternatively prioritize facility modification projects
decades to fully address the list. During this time, it to extend and/or improve the usability of existing
is likely that the condition of the facilities on the list facilities. This could prevent facility conditions from
will worsen and additional facilities could be added worsening—thereby delaying the need for a new
to the list. replacement courthouse or full-scale renovation.
It could also enable the state to
Figure 3 more slowly build new courthouses
Status of Trial Court Construction Projects and avoid a surge of unpredictable
facility costs. Finally, such an
Beginning in 2019-20a
approach could distribute the
Number of Estimated Project Number
monies across more facilities
Priority Group Projects Costs (in Billions) Initiated
throughout the state—thereby
Immediate Need 17 $2.0 12
increasing the number of people
Critical Need 26 10.6 —
High Need 17 4.7 — benefiting from improved facilities.
Medium Need 10 3.5 —
Low Need 10 0.2 —
Totals 80 $21.0 12
a Reflects data from 2019 facility assessment, adjusted to include updated data from 2024
reassessment of Los Angeles facilities.
6 LEGISLATIVE ANALYST’S OFFICE
analysis full
2026-27 BUDGET
Recommendations dollars—or slightly more—depending on what the
Legislature asks for the reassessment to include.
Consider How Much General Fund to
Such a reassessment could also include direction
Dedicate to Court Facilities. Given the magnitude
to reconsider existing operations—such as the
of the judicial branch’s facility needs and deficits
impact of increased remote proceedings—and
facing the state General Fund, it is not possible for
whether existing projects should move up or
the state to fully address such needs in the short
down in the prioritization list. As costs seem to
run. Accordingly, we recommend the Legislature
be significantly increasing, having more recent
instead consider how much General Fund it would
information could provide the Legislature with more
like to dedicate annually to address court facility
accurate information on how much the full list of
needs. A stable commitment of funding would allow
construction projects will cost as well as which
the state and judicial branch to make short- and
projects are the most pressing.
long-term plans to maximize use of these funds.
For example, this would allow the judicial branch to Consider Additional Oversight of Facility
make choices between new construction or facility Modification Projects Receiving One-Time
modification projects. The specific amount would Funding. We recommend the Legislature consider
depend on its other General Fund priorities. This is increasing oversight of facility modification
because increased and consistent facility funding projects receiving one-time General Fund support.
would come at the expense of other General Fund As noted above, these project costs typically would
priorities given the multiyear deficits facing the use a significant portion of the judicial branch’s
state. If it is comfortable with the level of funding discretionary funding if they were not funded
proposed for facilities in 2026-27, we recommend it separately. The doubling of the Orange CJC project
approve the Governor’s proposals. If the Legislature from initial estimates, with the potential for even
would like to dedicate a different level of funding, more future costs as the project is only 25 percent
it could work with the judicial branch to prioritize complete, raises questions about whether state
how to use whatever level of funding the Legislature oversight of such larger or more complex projects
deems appropriate. is sufficient. It is possible that the Orange CJC
project faces unique factors based on the specifics
Direct Judicial Branch to Report on
of its existing condition that will not be an issue
Long-Term Plan for Facilities Based on
in other facility modification projects. However,
Legislative Direction. We recommend the
if the state prioritizes more General Fund for
Legislature direct the judicial branch to report by
facility modification projects, it becomes critical
January 2028 on a long-term plan for addressing
to ensure appropriate oversight is in place to
facility needs based on the Legislature’s direction
ensure the Legislature has sufficient information.
on the amount of annual General Fund that would
At a minimum, this information should include an
be prioritized for court facilities. This plan should
accurate assessment of the existing condition of
include an assessment of how the funding should
a facility, the scope of the project, and the costs
be divided between new construction and facility
to complete it. One way to accomplish this would
modification projects to maximize the amount of
be for the Legislature to require that such projects
time existing facilities may be safely used. It could
undergo review in the budget process by DOF in
also consider innovative ways to use the funding
a manner similar to new courthouse facility capital
to finance new construction or facility modification
outlay projects. This would mean that similar
projects. To enhance the plan, the Legislature could
construction expertise is applied by DOF in its
also consider whether it should provide funding for
assessment and monitoring of these larger facility
the judicial branch to reassess the total estimated
modification projects. This could help ensure the
costs of the construction project list—excluding
Legislature receives accurate and complete data to
Los Angeles facilities which were reassessed in
inform its decision-making and that state funds are
2024. We estimate this could cost several million
used cost-effectively.
www.lao.ca.gov 7
analysis full
2026-27 BUDGET
LAO PUBLICATIONS
This report was prepared by Anita Lee, and reviewed by Drew Soderborg and Ross Brown. The Legislative Analyst’s
Office (LAO) is a nonpartisan office that provides fiscal and policy information and advice to the Legislature.
To request publications call (916) 445-4656. This report and others, as well as an e-mail subscription service, are
available on the LAO’s website at www.lao.ca.gov. The LAO is located at 925 L Street, Suite 1000, Sacramento,
California 95814.
8 LEGISLATIVE ANALYST’S OFFICE