SCO
California Energy Commission - Program Audit of the Clean Job Energy Creation Fund
Read the report at California Energy Commission - Program ↗
PROGRAM AUDIT OF THE
CALIFORNIA CLEAN ENERGY
JOBS ACT
Audit Report
PROPOSITION 39 PROGRAM
Chapter 29, Statutes of 2013
July 1, 2017, through June 30, 2018
BETTY T. YEE
California State Controller
June 2019
BETTY T. YEE
California State Controller
June 28, 2019
Adrienne Alvord, Chair
Citizens Oversight Board
1516 9th Street, MS 19
Sacramento, CA 95814
Dear Ms. Alvord:
The State Controller’s Office (SCO) audited a selection of completed projects related to the
California Clean Energy Jobs Act for the period of July 1, 2017, through June 30, 2018.
As of June 30, 2018, 114 local educational agencies (LEAs) reported $63,057,214 in completed
project costs and 37 community college districts (CCDs) reported $22,462,119 in completed
project costs. From the list of completed projects, we selected for audit 16 LEAs and three
CCDs, which reported expenditures of $24,233,274. Our audit found that:
Seven LEAs and three CCDs sole-sourced a portion of their project costs, resulting in
unallowable costs of $3,013,770;
Ten LEAs and three CCDs did not include the projected energy savings in the awarded
contracts;
One LEA and one CCD spent Proposition 39 funds on ineligible expenditures, resulting in
unallowable costs of $19,579 ($27,654 less $8,075 that was also sole-sourced); and
Five LEAs submitted their final project completion reports after the deadline.
We also identified an issue that is not significant to the audit objectives, but warrants the
attention of management. Specifically we found that four LEAs with unused planning funds
properly applied them to program implementation. However, as these funds were not included in
their approved energy expenditure plans, the amount of Proposition 39 funds paid to these LEAs
exceeded their approved energy expenditure plans by $26,238.
This final audit report identifies seven LEAs and three CCDs that sole-sourced a portion of their
project costs, in violation of Public Resources Code (PRC) section 26235(c). This final audit
report also identifies one LEA and one CCD that spent Proposition 39 funds on ineligible
expenditures, in violation of the California Energy Commission’s Proposition 39: California
Clean Energy Jobs Act – 2013 Program Implementation Guidelines and the California
Community Colleges Chancellor’s Office’s California Community Colleges Proposition 39
Implementation Guidelines.
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction shall require local
education agencies to pay back funds if they are not used in accordance with state statute or
regulations….”
Adrienne Alvord, Chair -2- June 28, 2019
PRC section 26240(h)(2) states, “The Chancellor of the California Community Colleges shall
require a community college to pay back funds if they are not used in accordance with state
statute or regulations….”
Findings 1 and 3 are both apportionment-significant for LEAs. If you disagree with either
finding, you have 30 days from the date the SCO emailed this report to request a summary
review of any apportionment-significant audit findings on the grounds of substantial compliance.
In addition, you have 60 days from delivery of this letter—or 30 days following the conclusion
of a summary review regarding the finding included in that review—to file a formal appeal of
any apportionment-significant audit findings on any one or more of the grounds set forth in
Education Code (EC) section 41344(d). The request for a summary review or formal appeal
should be submitted to the following address:
Executive Officer
Education Audit Appeals Panel
770 L Street, Suite 1100
Sacramento, California 95814
If you have any questions regarding the summary review process or the appeal process, please
see the Education Audit Appeals Panel (EAAP) website (www.eaap.ca.gov) or call EAAP at
(916) 445-7745.
LEAs working to resolve audit exceptions may request structured repayment plans under EC
section 41344. To request a repayment plan, the LEA must submit a letter to the California
Department of Education (CDE) within 90 days of receipt of this letter; within 30 days of
withdrawing or receiving a determination of a summary review if there is no appeal; or within 30
days of withdrawing or receiving a final determination regarding an appeal pursuant to EC
section 41344(a). More information on repayment plans can be found on the CDE’s website
(http://www.cde.ca.gov/fg/au/ag/resolution.asp) or by contacting the CDE, School Fiscal
Services Division, Categorical Allocations and Management Assistant Unit, at (916) 323-8068.
In addition, Findings 1 and 3 both have a fiscal impact on the affected CCDs. If you disagree
with these two findings, Title 5, section 59100, et seq. provides that the Chancellor for the
California Community Colleges has the authority to review audit findings involving CCDs. The
request for an appeal should be submitted to:
Tracy Britten, Specialist
Fiscal Accountability
College Finance and Facilities Planning Division
California Community Colleges Chancellor’s Office
1102 Q Street
Sacramento, CA 95811
You may also call the CCCCO’s Fiscal Accountability Office at (916) 324-9794 for more
information.
Adrienne Alvord, Chair -3- June 28, 2019
If you have any questions about the audit findings, please contact Lisa Kurokawa, Bureau Chief,
by telephone at (916) 327-3138.
Sincerely,
Original signed by
JIM L. SPANO, CPA
Chief, Division of Audits
JLS/as
cc: Jack Bastida, Contract Manager
Citizens Oversight Board
Jim Bartridge, Program and Policy Advisor
Citizens Oversight Board
Tony Thurmond, Superintendent of Public Instruction
California Department of Education
Kimberly Tarvin, Director of Audits and Investigation
California Department of Education
Caryn Moore, Director
School Fiscal Services Division
California Department of Education
David Hochschild, Chair
California Energy Commission
Drew Bohan, Executive Director
California Energy Commission
Kristen Driskell, Deputy Director
Efficiency Division
California Energy Commission
Bill Pfanner, Proposition 39 Project Manager
Efficiency Division
California Energy Commission
Elise Ersoy, Manager
Local Assistance and Finance Office
Efficiency Division
California Energy Commission
Tom Epstein, President
Board of Governors
California Community Colleges Chancellor’s Office
Eloy Ortiz Oakley, Chancellor
California Community Colleges
Christian Osmeña, Vice Chancellor
College Finance and Facilities Planning Division
California Community Colleges Chancellor’s Office
Carlos Montoya, Director of Facilities Planning and Utilization
College Finance and Facilities Planning Division
California Community Colleges Chancellor’s Office
Adrienne Alvord, Chair -4- June 28, 2019
Tracy Britten, Specialist
College Finance and Facilities Planning Division
California Community Colleges Chancellor’s Office
Mary Kelly, CPA, Executive Officer
California Education Audit Appeals Panel
Juan M. Tafolla, President
Board of Trustees
Armona Union Elementary School District
Xavier Piña, Ed.D., Superintendent
Armona Union Elementary School District
Susan Fagundes, Business Manager
Armona Union Elementary School District
William McGinnis, President
Board of Trustees
Butte-Glenn Community College District
Samia Yaqub, Ph.D., Superintendent/President
Butte-Glenn Community College District
William Nicholas, Director
Business Services
Butte-Glenn Community College District
Vicki Gordon, President
Governing Board
Contra Costa Community College District
Fred E. Wood, Ph.D., Chancellor
Contra Costa Community College District
Jonah Nicholas, Assistant Vice Chancellor/Chief Financial Officer
Finance Services
Contra Costa Community College District
Jennifer Cobian, President
Board of Education
El Monte City School District
Maribel Garcia, Ed.D., Superintendent
El Monte City School District
José Marcelino Herrera, Assistant Superintendent
Business Services
El Monte City School District
Bonnie Simas, President
Board of Education
Esparto Unified School District
Christina Goennier, Ed.D., Superintendent
Esparto Unified School District
Rebecca Spiva, Chief Business Officer
Business Services
Esparto Unified School District
Eric Swanson, President
Board of Trustees
Hesperia Unified School District
Adrienne Alvord, Chair -5- June 28, 2019
David Olney, Superintendent
Hesperia Unified School District
Dr. George Landon, Assistant Superintendent
Business Services
Hesperia Unified School District
Jade White, Administrator
High Tech High International Charter School
Amanda Wyatt, Chief Financial Officer
High Tech High International Charter School
Vincent Robinson, President
Board of Trustees
Luther Burbank School District
Christopher Ortiz, Ph.D., Ed.D., Superintendent
Luther Burbank School District
Rudy Avalos, Chief Business Official
Luther Burbank School District
Wayne Forsythe, President
Governing Board
Mariposa County Office of Education
Robin Hopper, Superintendent
Mariposa County Office of Education
Norma Dwyer, Chief Business Officer
Business Services
Mariposa County Office of Education
Kierstin Wight, Business Services Officer
Business Services
Mariposa County Office of Education
Diane Bateman, President
Board of Education
Mark Twain Union Elementary School District
Julia Tidball, Superintendent
Mark Twain Union Elementary School District
Roy Blair, Director
Business Services
Mark Twain Union Elementary School District
Charlene Metoyer, President
Board of Education
Newport-Mesa Unified School District
Dr. Frederick Navarro, Superintendent
Newport-Mesa Unified School District
Jeff Trader, Executive Director/Chief Financial Officer
Fiscal Services
Newport-Mesa Unified School District
Julia Lammatao, Financial Analyst
Fiscal Services
Newport-Mesa Unified School District
Adrienne Alvord, Chair -6- June 28, 2019
Eleanor Juanita Evans, President
Board of Education
Oceanside Unified School District
Julie A. Vitale, Ph.D., Superintendent
Oceanside Unified School District
Shannon Soto, Ed.D., Deputy Superintendent of Administrative Services
Business Services
Oceanside Unified School District
Cindy Farley, President
Board of Trustees
Pine Ridge Elementary School District
Christine Skinner, Superintendent/President
Pine Ridge Elementary School District
Peter J. Ottesen, President
Board of Education
San Joaquin County Office of Education
James Mousalimas, County Superintendent of Schools
San Joaquin County Office of Education
Scott Anderson, Deputy Superintendent
Business Services
San Joaquin County Office of Education
Leo Sheridan, President
Board of Education
San Leandro Unified School District
Mike McLaughlin, Ed.D., Superintendent
San Leandro Unified School District
Kevin Collins, Ed.D., Assistant Superintendent
Business and Operations
San Leandro Unified School District
T.J. Prendergast III, President
Board of Trustees
South Orange County Community College District
Kathleen F. Burke, Ed.D., Chancellor
South Orange County Community College District
Ann-Marie Gabel, CPA, Vice Chancellor
Business Services
South Orange County Community College District
Kim McCord, Executive Director
Fiscal Services/Comptroller
South Orange County Community College District
Richard Kudlik, Internal Auditor
South Orange County Community College District
Daniel C. Monarrez, President
Board of Education
West Covina Unified School District
Charles D. Hinman, Ed.D., Superintendent
West Covina Unified School District
Adrienne Alvord, Chair -7- June 28, 2019
John Ziegenhohn, Chief Fiscal Executive
Business Services
West Covina Unified School District
Alex Bowlds, President
Board of Trustees
Willits Unified School District
Mark Westerburg, Superintendent
Willits Unified School District
Nikki Agenbroad, Director of Fiscal Services
Willits Unified School District
Mark Ziegler, President
Board of Trustees
Yreka Union High School District
Mark Greenfield, Superintendent
Yreka Union High School District
Tony Joling, Chief Business Official
Yreka Union High School District
Raul Parungao, Associate Superintendent
Business Services
Alameda County Office of Education
Claudia C. Davis, Associate Superintendent
Administrative Services
Calaveras County Office of Education
Kevin Otto, Deputy Superintendent/Chief Financial Officer
Business Services
Fresno County Superintendent of Schools
Jamie Dail, Director
Business Services
Kings County Office of Education
Candi Clark, Chief Financial Officer
Business Services
Los Angeles County Office of Education
Dean West, CPA, Associate Superintendent
Business Services
Orange County Office of Education
Richard De Nava, Assistant Superintendent
Business Services
San Bernardino County Superintendent of Schools
Michael Simonson, Assistant Superintendent
Business Services
San Diego County Office of Education
Megan Reilly, Chief Business Officer
Business Services
Santa Clara County Office of Education
Deborah Pendley, Associate Superintendent
Business Services
Siskiyou County Office of Education
Adrienne Alvord, Chair -8- June 28, 2019
Crissy Huey, Associate Superintendent
Administrative Services
Yolo County Office of Education
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Contents
Audit Report
Summary ............................................................................................................................ 1
Background ........................................................................................................................ 1
Audit Authority.................................................................................................................. 4
Objectives, Scope, and Methodology ............................................................................... 4
Conclusion .......................................................................................................................... 6
Follow-up on Prior Audit Findings .................................................................................. 7
Views of Responsible Officials .......................................................................................... 7
Restricted Use .................................................................................................................... 8
Schedule 1 – Total Completed Proposition 39 Program Costs for
Local Educational Agencies .................................................................... 9
Schedule 2 – Total Completed Proposition 39 Program Costs for
Community College Districts .................................................................. 11
Findings and Recommendations ........................................................................................... 12
Observation and Recommendation ...................................................................................... 17
Appendix—Audit Results by Local Educational Agencies and
Community College Districts .................................................................. A1
Attachment A—Hesperia Unified School District’s Response to Audit Results
Attachment B—High Tech High International Charter School’s Response to Audit Results
Attachment C—Mark Twain Union Elementary School District’s Response to Audit
Results
Attachment D—Pine Ridge Elementary School District’s Response to Audit Results
Attachment E—Venture Academy Charter School’s Response to Audit Results
Attachment F—West Covina Unified School District’s Response to Audit Results
Attachment G—Butte Glenn Community College District’s Response to Audit Results
Attachment H—South Orange County Community College District’s Response to Audit
Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Audit Report
Summary The State Controller’s Office (SCO) audited a selection of completed
projects related to the California Clean Energy Jobs Act for the period of
July 1, 2017, through June 30, 2018.
As of June 30, 2018, 114 local educational agencies (LEAs) reported
$63,057,214 in completed project costs and 37 community college
districts (CCDs) reported $22,462,119 in completed project costs. From
the lists of completed projects, we selected for audit 16 LEAs and three
CCDs, which reported total expenditures of $24,233,274. Our audit found
that:
Seven LEAs and three CCDs sole-sourced a portion of their project
costs, resulting in unallowable costs of $3,013,770;
Ten LEAs and three CCDs did not include the projected energy
savings in the awarded contracts;
One LEA and one CCD spent Proposition 39 funds on ineligible
expenditures, resulting in unallowable costs of $19,579 ($27,654 less
$8,075 that was also sole-sourced); and
Five LEAs submitted their final project completion reports after the
deadline.
We also identified an issue that is not significant to the audit objectives,
but warrants the attention of management. Specifically we found that four
LEAs with unused planning funds properly applied them to program
implementation. However, as these funds were not included in their
approved energy expenditure plans (EEPs), the amount of Proposition 39
funds paid to these LEAs exceeded their approved EEPs by $26,238.
A separate summary of the audit results for the 16 LEAs and three CCDs
selected for audit is included as an Appendix to this report.
Background The California Clean Energy Jobs Act was created with the approval of
Proposition 39 (Chapter 29, Statutes of 2013) in the November 2012
statewide election. The statute changed the corporate income tax code to
allocate projected revenue from the General Fund to the Clean Energy Job
Creation Fund for five fiscal years, beginning with fiscal year
(FY) 2013-14. Under the initiative, it is estimated that up to $550 million
is available annually to be appropriated by the California State Legislature
for purposes of funding eligible projects that create jobs in California
while improving energy efficiency and expanding clean energy
generation.
Senate Bill 73 requires that 89% of the funds deposited annually into the
Clean Energy Job Creation Fund be made available to LEAs for energy
efficiency and clean energy projects, and 11% be made available to CCDs
for energy efficiency and clean energy projects.
An eligible energy project is an installation at or modification to a school
site that improves energy efficiency or expands clean energy generation.
-1-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Energy efficiency measures include heating, ventilation, and air
conditioning (HVAC) system retrofits and various interior and exterior
retrofits; clean energy generation measures include photovoltaic (solar)
panels. All facilities within an LEA are eligible for Proposition 39 program
funding.
Citizens Oversight Board
Proposition 39 also established the Citizens Oversight Board (COB) to
review expenditures, audit the Clean Energy Job Creation Fund, and
maintain transparency and accountability of the Fund. Members of the
COB are appointed by the California Treasurer, Attorney General, and
State Controller with two ex officio members from the California Energy
Commission (CEC) and the California Public Utilities Commission
(CPUC).
California Department of Education
The California Department of Education (CDE) is responsible for
distributing Proposition 39 funding to LEAs that serve grade K-12
students. CDE allocates funds based on the following formula:
85% based on average daily attendance reported as of the second
principal apportionment for the prior year (P-2); and
15% based on the number of students eligible for free and reduced-
priced meals in the prior year.
These funds may be used by LEAs for energy efficiency and clean energy
projects, as well as related energy planning, energy training, and energy
management. LEAs are required to submit an EEP to the CEC for
consideration and approval. An EEP includes a technical description and
project specifications for the proposed eligible energy measures. Funds are
released to an LEA only after the CEC approves the EEP.
LEAs with prior-year average daily attendance of 1,000 or lower are
eligible to receive funding for both the current year and the following year
in the current year. LEAs that select this option do not receive a funding
allocation in the following year.
LEAs whose first year of eligibility was FY 2013-14 also had the option
of requesting a portion of that year’s award allocation for energy planning
activities without submitting an EEP to the CEC. The energy planning
funds can be spent only on the following four activities:
Energy audits and energy surveys/assessments;
Proposition 39 program assistance;
Hiring or retaining an energy manager; and
Energy-related training.
Any unused energy planning funds must be applied toward implementing
energy projects from an LEA’s approved EEP.
-2-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
California Energy Commission
The CEC is the primary state agency responsible for energy policy and
planning. Public Resources Code (PRC) section 26235(a) requires the
CEC to establish guidelines in consultation with the State Superintendent
of Public Instruction, the Chancellor of the California Community
Colleges, and the CPUC.
On December 19, 2013, the CEC adopted the Proposition 39: California
Clean Energy Jobs Act – 2013 Program Implementation Guidelines
(Proposition 39 Program Implemenation Guidelines). These guidelines
provide direction to LEAs on the types of awards and the required
proposals, explain the screening and evaluation criteria, describe the
standards to be used to evaluate project proposals, and outline the award
process.
Included in Proposition 39 Program Implemenation Guidelines is a
savings-to-investment ratio (SIR) calculation. To be approved for
Proposition 39 funding, the eligible energy project must achieve a SIR
above 1.0. For example, for every dollar invested in the eligible energy
project, the LEA must accrue over $1 in savings. The SIR calculation is
based on the present value of the savings divided by project installation
costs, subtracting rebates and other grant funding sources. The
Proposition 39 Program Implemenation Guidelines also include a formula
for estimating job creation benefits, pursuant to PRC section 26235(e)(10).
The CEC also developed an Proposition 39: California Clean Energy Jobs
Act – 2015 Energy Expenditure Plan Handbook (EEP Handbook), which
includes step-by-step instructions to assist LEAs in completing the
required forms.
California Community Colleges Chancellor’s Office
The California Community Colleges Chancellor’s Office (CCCCO) is the
state agency that oversees the California community college system. The
CCCCO is responsible for distributing Proposition 39 funding to
individual CCDs. The funds may be used by CCDs for energy efficiency
and alternative energy projects, along with related improvements and
repairs, that contribute to reducing operating costs and improving health
and safety conditions in the community college system.
The CCCCO developed its Proposition 39: Clean Energy Jobs Act of
2012 – California Community Colleges Energy Project Guidance (Energy
Project Guidance) to assist CCDs with implementing projects that meet
the Proposition 39 requirements. Projects must be consistent with the
State’s energy loading order, which guides the State’s energy policies and
decisions according to the following priority order: 1) decreasing
electricity demand by increasing energy efficiency and reducing energy
usage in periods of high demand or cost, 2) meeting new energy supply
needs with renewable resources, and 3) meeting new energy generation
needs with clean fossil-fuel generation.
-3-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
CCDs have been pursuing and implementing energy efficiency and
renewable energy projects for many years through such programs as the
CPUC-administered California Community Colleges/Investor Owned
Utilities Energy Efficiency Partnership. This public-private partnership
has been working on behalf of CCDs since 2006 and has aggressively
reduced energy usage, resulting in over $12 million in costs savings for
the community college system.
Audit Authority Government Code (GC) section 12410 and PRC section 26210 provide the
legal authority to conduct this audit.
GC section 12410 states that the Controller shall superintend the fiscal
concerns of the State and audit the disbursement of any state money for
correctness, legality, and for sufficient provisions of law for payment.
The SCO’s interagency agreement with the COB, pursuant to PRC
section 26210(d)(2), commissions the SCO to review a selection of
completed projects to assess the effectiveness of the expenditures in
meeting the objectives of the California Clean Energy Jobs Act.
Objectives, Scope, On June 15, 2016, we entered into an agreement with the COB to conduct
an audit to assess the CEC’s control over implementation and
and Methodology
administration of the Clean Energy Job Creation Fund to ensure that the
expenditure and accounting of funds complied with applicable statutes.
Our agreement also included auditing a selection of completed projects
(80% LEA projects and 20% CCD projects) to determine whether the
energy projects were consistent with the Clean Energy Job Creation
Fund’s program guidelines. We selected 16 LEAs and three CCDs for
audit. We did not audit their financial statements.
We conducted this audit in accordance with generally accepted
government auditing standards. Those standards require that we plan and
perform the audit to obtain sufficient, appropriate evidence to provide a
reasonable basis for our findings and conclusions based on our audit
objectives. We believe that the evidence obtained provides a reasonable
basis for our findings and conclusions based on our audit objectives.
To achieve our audit objectives for the LEA K-12 Proposition 39 Program,
we:
Reviewed the CEC’s Proposition 39 Program Implementation
Guidelines (issued in December 2014 and revised in Novemeber
2017) and the EEP Handbook (issued in June 2015) to ensure
compliance with the applicable provisions of the Public Resources
Code;
Reviewed the controls established by the CEC to ensure the
completeness of EEPs, annual project expenditure reports, and close-
out project completion forms submitted by LEAs;
Selected 16 of 114 LEAs with project costs totaling $20,158,851 and
determined whether:
o Planning funds were expended in accordance with program
-4-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
requirements and unused planning funds were applied towards
implementing eligible energy projects approved by the CEC;
o The LEA submitted an EEP to the CEC consistent with the LEA’s
priority of eligible projects;
o The CEC approved the EEP in compliance with the CEC’s
Proposition 39 Program Implementation Guidelines and EEP
Handbook;
o The approved EEP included:
A signed utility data release form from the LEA allowing the
CEC to access both historical and future utility billing data;
A benchmarking process established by the CEC to determine
a prioritized plan for implementing the eligible energy
projects;
An identification of eligible energy projects according to any
one of the three methods available to LEAs (these include an
energy survey; an American Society of Heating, Refrigerating
and Air-Conditioning Engineering Level 2 energy audit; or
data analytics);
A SIR that adheres to the cost-effectiveness determination set
forth by the CEC; and
A job-creation benefits estimation that adheres to the formula
set forth by the CEC.
o The final report to the CEC contained the information outlined in
PRC section 26240(b)(1) through 26240(b)(7);
o The LEA did not use a sole-source process to award funds;
o The LEA had a signed contract that identified project
specifications, costs, and projected energy savings;
o The LEA supported project costs; and
o The LEA paid back Proposition 39 funds if the project was torn
down, remodeled, or deemed surplus and sold prior to the payback
of the project.
Errors found in the selected samples were not projected to the intended
(total) population.
To achieve our audit objectives for the CCD Proposition 39 Program, we:
Selected three of 37 CCDs with completed project costs totaling
$4,074,423 and determined whether:
o The CCD submitted a Proposition 39 Funding Application to the
CCCCO, and the CCCCO approved the application consistent
with its Proposition 39: Clean Energy Jobs Act of 2012 –
California Community Colleges Proposition 39 Implementation
Guidelines (issued in May 2013 and revised in April 2015);
o The CCD submitted a Call for Projects form that identified
projects as energy efficiency or renewable energy generation;
o The Proposition 39 Close-out Project Completion form and the
-5-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Annual Project Expenditure Report submitted to the CCCCO
contained the following information:
The estimated amount of energy saved, accompanied by
specific energy consumption and utility bill cost data for the
individual facility where the project is located;
The nameplate rating of the new clean energy generation
method installed;
The number of trainees resulting from the project;
The amount of time between awarding financial assistance
and completing the project or training activities;
The entity’s energy intensity before and after project
completion, as determined by an energy rating or benchmark
system; and
The number of direct full-time equivalent employees created
by each project and the average number of months or years of
utilization of each of these employees.
o The CCD did not use a sole-source process to award funds;
o The CCD had a signed contract that identified project
specifications, costs, and projected energy savings;
o The CCD supported project costs; and
o The CCD paid back the Porposition 39 Program funds if the
project was torn down, remodeled, or deemed surplus and sold
prior to the payback of the project.
Errors found in the selected samples were not projected to the intended
(total) population.
Conclusion As a result of conducting the audit procedures, we found instances of
noncompliance with the audit objectives outlined in the Objectives, Scope,
and Methodology section. These instances are quantified in the Schedules
and described in the Findings and Recommendations section of this report.
We selected 16 LEAs and 3 CCDs with completed projects for audit.
These 19 agencies reported total completed project costs of $24,233,274
($20,158,851 for LEAs and $4,074,423 for CCDs). Our audit found:
Seven LEAs and three CCDs sole-sourced a portion of their project
costs, resulting in unallowable costs of $3,013,770;
Ten LEAs and three CCDs did not include the projected energy
savings in the awarded contracts;
One LEA and one CCD spent Proposition 39 funds on ineligible
expenditures, resulting in unallowable costs of $19,579 ($27,654 less
$8,075 that was also sole-sourced); and
Five LEAs submitted their final project completion reports after the
deadline.
-6-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
We also identified an issue that is not significant to the audit objectives,
but warrants the attention of management. Specifically we found that four
LEAs with unused planning funds properly applied them to program
implementation. However, as these funds were not included in their
approved EEPs, the amount of Proposition 39 funds paid to these LEAs
exceeded their approved EEPs by $26,238. This issue is described in the
Observation and Recommendation section of this report.
Follow-up on We previously conducted an audit of 20 LEAs and CCDs with completed
projects between December 19, 2013, and June 30, 2016, and issued an
Prior Audit
audit report on June 30, 2017. We conducted a second audit of another 20
Findings
LEAs and CCDs with completed projects between July 1, 2016, and
June 30, 2017, and issued an audit report on July 13, 2018. The report
issued on July 13, 2018, found that:
Seven LEAs sole-sourced all or a portion of their project costs, totaling
$557,645;
Twelve LEAs and three CCDs did not include projected energy
savings in their awarded contracts;
Two LEAs applied Proposition 39 funding, totaling $277,987, toward
project costs incurred prior to the eligibility period of December 19,
2013;
Four LEAs submitted their final project completion reports after the
deadline; and
The CEC did not properly review one EEP out of the 16 that we
reviewed.
The 20 LEAs and CCDs identified in the June 30, 2017 audit report are
not the same 20 LEAs and CCDs identified in the July 13, 2018 audit
report, and they are not the same 19 LEAs and CCDs selected for the
current audit; however, we found that all three audits identified the same
issues.
Views of We discussed our audit results with representatives of the 16 LEAs and
three CCDs selected for testing during audit fieldwork via email at the end
Responsible
of the audit. All responses have been included in the Appendix and
Officials
Attachments A through H.
-7-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Restricted Use This report is solely for the information and use of the COB, the CDE, the
CEC, the CCCCO, Armona Union Elementary School District, Butte-
Glenn Community College District, Contra Costa Community College
District, El Monte City School District, Esparto Unified School District,
Hesperia Unified School District, High Tech High International Charter
School, Luther Burbank School District, Mariposa County Office of
Education, Mark Twain Union Elementary School District, Newport-
Mesa Unified School District, Oceanside Unified School District, Pine
Ridge Elementary School District, San Leandro Unified School District,
South Orange County Community College District, Venture Academy
Charter School, West Covina Unified School District, Willits Unified
School District, Yreka Union High School District, and the SCO; it is not
intended to be and should not be used by anyone other than these specified
parties. This restriction is not intended to limit distribution of this report,
which is a matter of public record, and is available on the SCO website at
www.sco.ca.gov.
Original signed by
JIM L. SPANO, CPA
Chief, Division of Audits
June 28, 2019
-8-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1—
Total Completed Proposition 39 Program Costs
for Local Educational Agencies
July 1, 2017, through June 30, 2018
Program Planning Amount
Local Educational Agency Implementation Funds 1 Total Unallowable Reference 2
Completed projects selected for audit:
Armona Union Elementary School District $ 287,683 $ 28,005 $ 315,688 $ -
El Monte City School District 2,017,022 144,797 2,161,819 (3,819) Finding 2, 3
Esparto Unified School District 301,745 - 301,745 - Finding 2
Hesperia Unified School District 4,798,481 260,000 5,058,481 - Finding 4
High Tech High International Charter School 246,555 15,000 261,555 (50,000) Finding 1, 2
Luther Burbank School District 266,798 10,767 277,565 - Finding 2
Mariposa County Office of Education 62,563 15,919 78,482 - Finding 2, 4
Mark Twain Union Elementary School District 276,203 7,600 283,803 (16,368) Finding 1, 2
Newport-Mesa Unified School District 4,799,573 - 4,799,573 -
Oceanside Unified School District 937,052 34,787 971,839 (45,449) Finding 2
Pine Ridge Elementary School District 62,028 15,507 77,535 - Finding 2, 4
San Leandro Unified School District 2,015,425 58,500 2,073,925 - Finding 4
Venture Academy Charter School (San Joaquin Office of Education) 620,039 - 620,039 4 (26,447) Finding 1
West Covina Unified School District 1,891,376 136,277 2,027,653 (2,027,653) Finding 1, 2, 3
Willits Unified School District 544,280 29,259 573,539 - Finding 2
Yreka Union High School District 255,353 20,257 275,610 (20,257) Finding 1, 2, 4
Total, completed projects selected for audit $ 19,382,176 $ 776,675 $ 20,158,851 3 $ (2,189,993)
Completed projects not selected for audit:
Acalanes Union High School District $ 8 97,787 $ 130,000 $ 1,027,787
Ackerman Elementary School District 2 44,314 17,500 261,814
Alexander Valley Union Elementary 1 93,000 50,000 243,000
Allensworth Elementary School District 5 8,996 4,183 63,179
Alta-Dutch Flat Union Elementary 5 4,792 15,745 70,537
Alta Loma Elementary School District 3 51,465 130,000 481,465
Anaheim Union High School District 5 35,853 17,860 553,713
Antelope Elementary School District 1 75,907 17,801 193,708
Antelope Valley Union High School District 1 ,185,286 25,000 1,210,286
Ballard Elementary School District 1 46,813 33,197 180,010
Bella Vista Elementary School District 2 15,144 53,786 268,930
Bert Corona Charter School 2 46,789 14,300 261,089
Big Pine Unified School District 2 50,000 - 250,000
Buckeye Union Elementary School District 7 24,480 - 724,480
Burnt Ranch Elementary School District 5 8,622 9,475 68,097
Caliente Union Elementary School District 7 2,191 - 72,191
Calipatria Unified School District 5 48,293 8,500 556,793
Castaic Union School District 4 92,103 60,000 552,103
Castle Rock Union Elementary School District 2 8,306 5,698 34,004
Central Union High School District 8 43,990 130,000 973,990
Chatom Union School District 2 02,795 18,823 221,618
Chicago Park Community Charter School 2 6,606 11,427 38,033
Chrysalis Charter School 1 00,243 - 100,243
Chula Vista Elementary School District 1 ,223,834 - 1,223,834
Coachella Valley Unified School District 4 ,638,411 - 4,638,411
Corona-Norco Unified School District 1 ,942,642 - 1,942,642
Crossroads Charter School 1 04,787 5,510 110,297
Cucamonga School District 1 25,009 - 125,009
Cutler-Orosi Joint Unified School District 6 92,377 41,795 734,172
Empire Union Elementary School District 5 98,381 50,232 648,613
Fresno Unified School District 1 ,294,341 14,999 1,309,340
Glendora Unified School District 7 53,682 25,000 778,682
Grant Elementary School District 3 5,986 4,652 40,638
Gridley Unified School District 5 76,122 - 576,122
Hanford Joint Union High School District 1 58,249 7,950 166,199
Hornbrook Elementary School District 2 2,289 5,700 27,989
Hughson Unified School District 9 9,399 - 99,399
Hydesville Elementary School District 1 02,990 50,633 153,623
Igo, Ono, Platina Union Elementary School District 7 8,099 - 78,099
Julian Union Elementary School District 2 42,059 52,947 295,006
Kingsburg Elementary Charter School 5 25,789 37,296 563,085
Larkspur-Corte Madera School District 3 50,000 - 350,000
Lennox School District 2 84,694 - 284,694
-9-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1—(continued)
Program Planning Amount
Local Educational Agency Implementation Funds 1 Total Unallowable Reference 2
Completed projects not selected for audit:
Lindsay Unified School District 4 39,980 47,315 487,295
Little Shasta Elementary School District 2 7,822 2,400 30,222
Livermore Valley Joint Unified School District 1 65,835 159,280 325,115
Los Alamitos Unified School District 1 ,291,135 101,500 1,392,635
Madera County Office of Education 8 4,587 15,535 100,123
Maple Elementary School 1 38,059 - 138,059
Mariposa County Unified School District 5 44,227 22,306 566,533
Mary Collins Charter School at Cherry Valley 2 33,011 21,463 254,474
Mid Valley Alternative Charter School 3 7,328 15,063 52,391
Monarch Learning Center 4 0,470 51,172 91,642
Monson-Sultana Joint Union Elementary School District 2 64,796 16,993 281,789
Montague Elementary School District 2 07,160 51,790 258,950
Monterey County Home Charter School 6 2,955 949 63,904
Nevada Joint Union High School District 3 65,514 - 365,514
Northern Humboldt Union High School District 1 49,391 10,802 160,192
Oak Grove Elementary School District (EEP #550) 8 50,000 75,000 925,000
Oak Grove Elementary School Districtb (EEP #1791) 1 ,486,316 153,059 1,639,375
Ocean View School District 1 07,907 65,700 173,607
One.Charter School 2 58,663 - 258,663
Orange County Educational Arts Academy 1 59,000 7,500 166,500
Oroville City Elementary School District 2 36,972 - 236,972
Palisades Charter High School (EEP #629) 1 77,261 24,845 202,106
Palisades Charter High School (EEP #1083) 1 06,619 - 106,619
Penngrove Elementary School 2 56,679 - 256,679
Petaluma City Elementary School District 4 86,742 46,784 533,526
Planada Elementary School District 9 1,376 30,000 121,376
Pollock Pines Elementary School District 1 81,034 - 181,034
Pomona Unified School District 3 06,840 404,635 711,475
Redondo Beach Unified School District 1 56,434 - 156,434
Rialto Unified School District (EEP #103) 1 ,357,000 34,000 1,391,000
Rialto Unified School District (EEP #2566) 8 82,502 34,000 916,502
Rio Bravo-Greeley Union Elementary School District 2 82,737 57,414 340,151
Roseville City Elementary School District 3 71,828 58,500 430,328
Round Valley Joint Elementary School District 2 12,181 - 212,181
San Antonio Union Elementary School District 2 55,545 - 255,545
San Joaquin Building Futures Academy 2 58,663 - 258,663
San Joaquin County Office of Education 6 95,112 - 695,112
San Jose Charter Academy 5 02,530 35,000 537,530
Santa Ynez Valley Union High School District 2 69,960 - 269,960
Savanna Elementary School District 3 89,926 13,430 403,356
Science & Technology Academy at Knights Landing 4 5,272 - 45,272
Semitropic Elementary School District 2 42,391 - 242,391
Shasta Union Elementary School District 2 49,057 5,101 254,158
Snowline Joint Unified School District 2 84,111 130,000 414,111
Solvang Elementary School District 2 17,627 - 217,627
Stellar Charter School 2 02,472 50,618 253,090
Temecula Preparatory School 6 5,762 - 65,762
Temecula Valley Charter School (EEP #619) 4 6,470 - 46,470
Temecula Valley Charter School (EEP #2613) 5 9,925 - 59,925
Trinity County Office of Education 4 5,334 15,075 60,409
Tustin Unified School District 7 09,015 - 709,015
Twin Ridges Home Study Charter School 2 5,830 2,260 28,090
University Preparatory School 2 64,000 - 264,000
Upper Lake Unified School District 1 06,055 54,594 160,649
Wheatland Charter Academy 1 4,089 15,467 29,556
Wheatland Elementary School District 4 52,819 78,054 530,873
Willits Charter School 1 25,208 10,000 135,208
Willows Unified School District 5 52,070 21,000 573,070
Woodlake Unified School District 2 75,231 32,000 307,231
Total, completed projects not selected for audit 39,877,750 3,020,612 42,898,362
Total completed projects $ 59,259,926 $ 3,797,287 $ 63,057,214
_________________________
1 The planning funds are requested directly from CDE before an EEP is submitted.
2 See the Findings and Recommendations section.
3 We tested 100% of the costs reported, totaling $20,158,851, for the 16 LEAs selected for audit.
4 Venture Academy received apportionments totaling $573,704, $46,335 less than the total amount requested of
$620,039.
-10-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 2—
Total Completed Proposition 39 Program Costs
for Community College Districts
July 1, 2017, through June 30, 2018
Program Amount
Community College District Implementation Unallowable Reference 1
Completed projects selected for audit:
Butte-Glenn Community College District $ 1,244,954 $ (156,130) Finding 1, 2
Contra Costa Community College District 1,253,496 (664,114) Finding 1, 2
South Orange County Community College District 1 ,575,973 ( 23,112) Finding 1, 2, 3
Total, completed projects selected for audit $ 4,074,423 2 $ (843,356)
Completed projects not selected for audit:
Cabrillo Community College District 145,883
Cerritos Community College District 244,173
Coast Community College District 1,459,306
Compton Community College District 156,404
Copper Mountain Community College District 34,965
Desert Community College District 615,113
El Camino Community College District 246,429
Feather River Community College District 11,816
Gavilan Joint Community College District 71,753
Grossmont-Cuyamaca Community College District 1,013,495
Imperial Community College District 76,725
Kern Community College District 110,507
Los Rios Community College District 672,433
Mt. San Jacinto Community College District 516,367
Ohlone Community College District 285,458
Palo Verde Community College District 53,638
Peralta Community College District 300,744
Rancho Santiago Community College District 1,096,152
Redwoods Community College District 90,630
Rio Hondo Community College District 295,253
Riverside Community College District 638,537
San Diego Community College District 3,275,626
San Francisco Community College District 1,184,852
San Joaquin Delta Community College District 308,189
San Jose/Evergreen Community College District 155,625
San Luis Obispo County Community College District 537,511
San Mateo County Community College District 1,047,041
Santa Monica Community College District 196,492
Shasta-Tehama-Trinity Joint Community College District 731,956
Siskiyous Community College District 189,314
Sonoma County Junior College District 432,484
Southwestern Community College District 1,745,677
Ventura County Community College District 104,490
West Valley-Mission Community College District 342,658
Total, completed projects not selected for audit $ 18,387,696
Total completed projects $ 22,462,119
______________________
1See the Findings and Recommendations.
2We tested 100% of the costs reported, totaling $4,074,423, for the three CCDs selected for the audit.
-11-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Findings and Recommendations
FINDING 1— We found that seven LEAs and three CCDs sole-sourced a portion of their
project costs, totaling $3,013,770, as follows:
Sole-sourced project
costs
El Monte City School District $ 3 ,819
High Tech High International Charter School 5 0,000
Mark Twain Union Elementary School District 1 6,368
Oceanside Unified School District 4 5,449
Venture Academy Charter School 2 6,447
West Covina Unified School District 2,027,653 1
Yreka Union High School District 2 0,257
Subtotal, Local Educational Agencies $ 2 ,189,993
Butte-Glenn Community College District $ 156,130
Contra Costa Community College District 664,114
South Orange County Community College District 3,533
Subtotal, Community College Districts $ 823,777
Total $ 3 ,013,770
_____________
1For West Covina Unified School District, we found that of the $2,027,653 that
was sole-sourced, $8,075 was also applied to ineligible expenditures (see
Finding 3).
These seven LEAs and three CCDs did not provide supporting
documentation to show that they considered other vendors before
awarding contracts.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
We have interpreted the requirement to “not use a sole source process to
award funds” as the necessity for a competitive process. Competitive
processes improve cost-effectiveness, prevent favoritism, and make the
procurement process transparent.
For the Proposition 39 program, LEAs and CCDs hired contractors to
perform critical functions for energy upgrades. However, despite their
reliance on contractors, these LEAs and CCDs used noncompetitive
processes to contract for these vital services and, thus, did not ensure the
cost-effectiveness of these services.
Recommendation
We recommend that:
The CDE take appropriate action in response to funds paid to LEAs
that did not meet the sole-source requirement; and
The CCCCO take appropriate action in response to funds paid to
CCDs that did not meet the sole-source requirement.
-12-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
No recommendation for LEAs and CCDs is applicable to this finding, as
the Proposition 39 program has ended.
LEAs’ and CCDs’ Response
We notified the seven LEAs and three CCDs of this finding during audit
fieldwork and at the end of the audit via email. Findings and
Recommendations for individual LEAs and CCDs are included in the
Appendix; their complete responses are included as attachments.
FINDING 2— We found that 10 LEAs and three CCDs did not include the required
projected energy savings in the awarded contracts, as follows:
Projected energy
savings not identified
Local Education Agency
in awarded contracts
Armona Union Elementary School District
El Monte City School District
High Tech High International Charter School
Luther Burbank School District
Mariposa County Office of Education
Mark Twain Union Elementary School District
Oceanside Unified School District
Pine Ridge Elementary School District
Willits Unified School District
Yreka Union High School District
Community College District
Butte-Glenn Community College District
Contra Costa Community College District
South Orange County Community College District
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
We found that many of the awarded contracts include generic statements
that energy savings will be realized; however, these contracts do not
identify the amount of projected energy savings.
In discussing this issue with agency representatives during audit
fieldwork, many representatives commented that the approved energy
plans and board documents identified the required projected energy
savings amounts. We agree that these documents included the projected
energy savings amounts; however, the guidelines require projected energy
savings amounts to be identified in awarded contracts.
Recommendation
No recommendation for LEAs and CCDs is applicable to this finding, as
the Proposition 39 program has ended.
LEAs’ and CCDs’ Response
We notified the 10 LEAs and three CCDs of this finding during audit
fieldwork and at the end of the audit via email. Findings and
-13-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendations for individual LEAs and CCDs are included in the
Appendix; their complete responses are included as attachments.
FINDING 3— We found that one LEA and one CCD applied Proposition 39 funds to
Proposition 39 funds project costs not approved by the CEC or by the CCCCO, resulting in
applied to ineligible ineligible costs of $19,579 ($27,654 less $8,075 that was also sole-
sourced).
expenditures
West Covina Unified School District
We reviewed the invoices from Associated Environmental Management
for storm water pollution prevention services, and determined that the
services were not related to the approved project costs in the district’s EEP.
Therefore, we found that $8,075 for storm water pollution prevention
services is ineligible for Proposition 39 funding. However, we found that
this amount was also sole-sourced (see Finding 1).
The district self-certified in its EEP that “The LEA commits to use the
funds for the eligible energy project(s) approved in its energy expenditure
plan.”
The CEC’s Proposition 39 Program Implementation Guidelines state,
“LEAs can only use Proposition 39 funding for the eligible energy projects
approved in their energy expenditure plans.”
South Orange County Community College District
We found that South Orange County Community College District applied
Proposition 39 funds from application SOUTHO-1516-001-05 to project
costs not included in the application approved by the CCCCO. The district
improperly paid $19,579 to vendor Clear Blue Energy for an interior
lighting project that was not identified in the application.
The district signed and certified in its application that the funding would
be used for the energy projects identified in its application.
Recommendation
We recommend that:
The CDE take appropriate action in response to ineligible project
costs; and
The CCCCO take appropriate action in response to ineligible project
costs.
No recommendation for LEAs and CCDs is applicable to this finding, as
the Proposition 39 program has already ended.
LEA’s and CCD’s Response
We notified the LEA and the CCD of this finding during audit fieldwork
and at the end of the audit via email. Findings and Recommendations for
-14-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
individual LEAs and CCDs are included in the Appendix; their complete
responses are included as attachments.
FINDING 4— We found that five LEAs submitted their final project completion reports
Final project after the deadline. LEAs are required to submit a final project completion
completion reports report to the CEC 12 to 15 months after the EEP is completed. An EEP is
submitted after the considered complete when the LEA has completed all measures in the
approved EEP.
deadline
The following table identifies the number of months the final report was
submitted after the project was completed:
District Months
Hesperia Unified School District 26
Mariposa County Office of Education 19
Pine Ridge Elementary School District 22
San Leandro Unified School District 28
Yreka Union High School District 16
PRC section 26240(b) states, in part:
As a condition of receiving funds from the Job Creation Fund, not sooner
than one year but no later than 15 months after an entity completes its
first eligible project with grant, loan, or other assistance from the Job
Creation Fund, the entity shall submit a report of its project expenditures
to the Citizens Oversight Board….To the extent practical, this report
shall also contain information on any of the following:
1. The total final gross project costs before deducting any incentives or
other grants and the percentage of total project costs derived from
the Job Creation Fund.
2. The estimated amount of energy saved, accompanied by specified
energy consumption and utility bill cost data for the individual
facility where the project is located, in a format to be specified by
the Energy Commission.
3. The nameplate rating of new clean energy generation installed.
4. The number of trainees.
5. The number of direct full-time equivalent employees and the
average number of months or years of utilization of each of these
employees.
6. The amount of time between awarding of the financial assistance
and the completion of the project or training activities.
7. The entity’s energy intensity before and after project completion, as
determined from an energy rating or benchmark system…
Recommendation
No recommendation for LEAs is applicable to this finding, as the
Proposition 39 program has ended.
-15-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
LEAs’ Response
We notified the five LEAs of this finding during audit fieldwork and at the
end of the audit via email. Findings and Recommendations for individual
LEAs and CCDs are included in the Appendix; their complete responses
are included as attachments.
-16-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Observation and Recommendation
We found that four LEAs with unused planning funds properly applied
Unused planning
them to program implementation. However, as these funds were not
funds
included in their approved EEPs, the amount of Proposition 39 funds paid
to these LEAs exceeded their approved EEPs by $26,238, as follows:
Program Planning Total Total Unused
Local Educational Agency Implementation Funds EEP Approved CDE Apportionment Planning Funds
A B C = B - A
Armona Union Elementary School District $ 287,683 $ 28,005 $ 3 15,688 $ 3 17,912 $ 2,224
Luther Burbank School District 266,798 10,767 2 77,565 2 87,614 10,049
San Leandro Unified School District 2,015,425 58,500 2 ,073,925 2 ,079,178 5,253
Willits Unified School District 544,280 29,259 5 73,539 5 82,251 8,712
Total $ 3 ,114,186 $ 126,531 $ 3 ,240,717 $ 3 ,266,955 $ 26,238
We reviewed the districts’ ledgers and found that these LEAs received
funds in excess of the total amounts indicated in the EEPs approved by the
CEC because these LEAs applied their unused planning funds to project
implementation.
LEAs had the option of requesting planning funds for energy planning
activities in FY 2013-14 without submitting an EEP to CEC. The funds
were intended to be used for planning activities for FY 2013-14 through
FY 2017-18. Any unused planning funds can be applied toward
implementing energy projects that are part of an approved EEP.
The four LEAs in our sample opted to use only a portion of their planning
funds, and were able to apply the remaining funds toward project
implementation. However, the unspent planning funds were not included
in an approved EEP. CDE releases program implementation funds based
solely on the amounts requested in approved EEPs; as a result, these LEAs
received program implementation funds in excess of their approved EEP
amount.
PRC section 26235(f) states:
The Superintendent of Public Instruction shall not distribute funds to an
LEA unless the LEA has submitted to the Energy Commission, and the
Energy Commission has approved, an expenditure plan that outline the
energy projects to be funded. An LEA shall utilize a simple form
expenditure plan developed by the Energy Commission. The Energy
Commission shall promptly review the plan.…A portion of the funds
may be distributed to an LEA upon request for energy audits and other
plan development activities prior to submission of the plan.
The CEC’s Proposition 39 Program Implementation Guidelines state:
LEAs whose first year of eligibility was fiscal year 2013-14, the first year of
the program, had the option of requesting a portion of that year’s award
allocation for energy planning activities in 2013-14 without submitting an
energy expenditure plan(s) to the Energy Commission. This option was
available only for the fiscal year 2013-14 award allocation of the Proposition
39 program and was intended to be used for planning activities for subsequent
fiscal years (2013-14 through 2017-18).
The CEC’s Proposition 39 Program Implementation Guidelines also state
-17-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
that “Any unused energy planning funds shall be applied toward
implementing eligible energy project(s) approved as part of an LEA’s
energy expenditure plan(s).”
Recommendation
We recommend that:
CDE take appropriate action in response to unused planning funds
identified in this audit; and
CDE and CEC account for unspent planning funds that were applied
to program implementation without being included in an approved
EEP.
CDE’s Response
We initially communicated the results of our observation to a CDE
representative via email on January 30, 2019. After subsequent email
exchanges to further explain our observation, we received an email
response on March 15, 2019, stating:
I was able to vouch your numbers and agree that the 4 districts audited
had unused planning funds that should be returned to the state. However,
I do not consider them to be “overpaid EEP funds” per the payment
process established for this program, but rather “unused planning funds”
that should be returned to the state. We will proceed to bill for return of
unused planning funds once a finding is issued.
-18-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Appendix—
Audit Results by Local Educational Agencies and
Community College Districts
Local Educational Agencies
Armona Union Elementary School District ..................................................................................... A2
El Monte City School District ......................................................................................................... A4
Esparto Unified School District ....................................................................................................... A6
Hesperia Unified School District ..................................................................................................... A7
High Tech High International Charter School ................................................................................. A9
Luther Burbank School District ....................................................................................................... A12
Mariposa County Office of Education ............................................................................................. A14
Mark Twain Union Elementary School District .............................................................................. A16
Newport-Mesa Unified School District ........................................................................................... A19
Oceanside Unified School District................................................................................................... A20
Pine Ridge Elementary School District ........................................................................................... A22
San Leandro Unified School District ............................................................................................... A24
Venture Academy Charter School (San Joaquin County Office of Education) ............................... A26
West Covina Unified School District .............................................................................................. A29
Willits Unified School District ........................................................................................................ A33
Yreka Union High School District ................................................................................................... A35
Community College Districts
Butte-Glenn Community College District ....................................................................................... A37
Contra Costa Community College District ...................................................................................... A41
South Orange County Community College District ........................................................................ A43
-A1-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Armona Union Elementary School District
Proposition 39 Program
Background The California Energy Commission (CEC) approved Armona Union
Elementary School District’s energy expenditure plan (EEP) for $287,683,
consisting of $12,000 for energy management services and $275,683 for
program implementation. The district used its program implementation
funds for the following energy efficiency measures:
Proposition 39 Energy Reported
Share Used Efficiency Annual Cost
School Site at School Site Measures Savings
Armona Elementary $ 4 4,804 Lighting retrofit $ 3 ,282
Parkview Middle 2 30,879 HVAC and lighting retrofit 8 ,401
Total $ 275,683 $ 1 1,683
With these energy efficiency measures, the district reported a combined
savings-to-investment ratio (SIR) of 1.74 and the creation of 1.54 direct
job-years.
In addition, the district received $28,005 in planning funds directly from
the CDE, which was used for screening and audits, and program
assistance.
Audit Results
We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39: California Clean Energy Jobs Act – 2013 Program
Implementation Guidelines (Proposition 39 Program Implementation
Guidelines) and Proposition 39: California Clean Energy Jobs Act – 2015
Energy Expenditure Plan Handbook (EEP Handbook). We identified the
following audit issue:
Projected energy savings not identified in awarded contracts
We reviewed the district’s contract with Indoor Environmental Services
(IES) and determined that the contract does not identify the projected
energy savings.
Public Resource Code (PRC) section 26206(d) states, “All projects shall
require contracts that identify the project specifications, costs, and
projected energy savings.”
We also identified the following observation:
Unused planning funds
We found that the district applied unused planning funds to program
implementation. However, these funds were not included in its approved
EEP. As a result, the district received funding that exceeded its approved
EEP by $2,224. We informed the CDE of our observation via email on
January 30, 2019.
-A2-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that the CDE take appropriate action in response to the
unused planning funds identified in this audit.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit finding and observation via email on
February 26, 2019. We did not receive a response from the district.
-A3-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
El Monte City School District
Proposition 39 Program
Background The CEC approved El Monte City School District’s EEP for $2,017,022,
consisting of $160,000 for energy management services and $1,857,022
for program implementation. The district used its program
implementation funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Asher Facility $ 14,651 Lighting and HVAC controls $ 524
Barton Center 9,872 Lighting and HVAC controls 1,141
Byron Thompson/Durfee 156,150 Lighting and HVAC controls 12,968
Central Kitchen 22,266 Lighting and HVAC controls 1,120
Cherrylee Elementary 95,936 Lighting and HVAC controls 7,052
Child Development 9,110 Lighting and HVAC controls 383
Cleminson Elementary 79,038 Lighting and HVAC controls 5,347
Columbia Elementary 177,101 Lighting and HVAC controls 12,773
Cortada Elementary 88,254 Lighting and HVAC controls 8,793
District Office 59,462 Lighting and HVAC controls 3,694
Gidley Elementary 109,875 Lighting and HVAC controls 9,331
Legore Elementary 149,040 Lighting and HVAC controls 12,986
Loma Center 55,104 Lighting and HVAC controls 6,482
New Lexington Elementary 63,163 Lighting and HVAC controls 4,484
Potrero Elementary 133,529 Lighting and HVAC controls 13,265
Rio Hondo Elementary 148,012 Lighting and HVAC controls 8,359
Rio Vista Elementary 116,087 Lighting and HVAC controls 10,322
Shripser Elementary 117,792 Lighting and HVAC controls 9,985
Wilkerson Elementary 107,783 Lighting and HVAC controls 12,017
Wright Elementary 144,797 Lighting and HVAC controls 12,695
Total $ 1,857,022 $ 1 53,721
With these energy efficiency measures, the district reported a combined
SIR of 1.22 and the creation of 10.40 direct job-years.
In addition, the district received $144,797 in planning funds directly from
the CDE, which it used for screening and audits, and energy management
services.
We audited the Proposition 39 program costs to ensure compliance with
Audit Results
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issues:
Sole-sourced project costs
We found that the district sole-sourced its contract with Alsaleh Project
Management, Inc. for construction management services for a district-
wide exterior lighting fixtures maintenance project – A1803. The district
did not provide supporting documentation to show that it considered other
vendors before awarding the contract to Alsaleh Project Management, Inc.
-A4-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Therefore, we found that the district sole-sourced its Proposition 39
contract, totaling $3,819.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the district’s contracts with RDM Electric Co., Inc. and
Anderson Air Conditioning, L.P. and determined that the contracts do not
identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Recommendation
We recommend that the CDE take appropriate action in response to funds
paid that did not meet the sole-source requirement.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District Response
We informed the district of the two audit findings via email on
February 14, 2019. We did not receive a response from the district.
-A5-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Esparto Unified School District
Proposition 39 Program
Background The CEC approved Esparto Unified School District’s EEP for $301,745.
The district used its implementation funds for the following renewable
energy generation measure:
Proposition 39 Renewable Energy Reported
Share Used Generation Annual Cost
School Site at School Site Measures Savings
Esparto K-8 $ 301,745 Photovoltaic (solar) panels $ 8,002
$ 301,745 $ 8,002
With this renewable energy generation measure, the district reported a
combined SIR of 0.25 and the creation of 1.27 direct job-years.
Audit Results We audited the Proposition 39 program costs and found that all costs
reported were compliance with the Job Creation Fund program guidelines,
as well as the CEC’s Proposition 39 Program Implementation Guidelines
and EEP Handbook.
District’s Response
We informed the district via email on February 26, 2019, that all costs
reported for Esparto Unified School District were in compliance with the
program guidelines. We did not receive a response from the district.
-A6-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Hesperia Unified School District
Proposition 39 Program
Background The CEC approved Hesperia Unified School District’s EEP for
$4,798,481. The district used its program implementation funds for the
following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Carmel Elementary $ 111,328 Interior/exterior lighting retrofit and plug loads $ 8,347
Cedar Middle 455,678 HVAC controls, interior/exterior lighting retrofit, and plug loads 27,967
Cottonwood Elementary 82,886 Exterior lighting retrofit and plug loads 5,964
Cypress School of the Arts 344,084 HVAC controls, interior/exterior lighting retrofit, and plug loads 21,712
Eucalyptus Elementary 212,585 HVAC, exterior lighting retrofit, and plug loads 12,397
Hesperia High 1,011,224 HVAC controls, interior/exterior lighting retrofit, and plug loads 61,042
Hollyvale Elementary 229,410 HVAC controls, interior/exterior lighting retrofit, and plug loads 13,092
Juniper Elementary 51,128 HVAC, exterior lighting retrofit, and plug loads 3,892
Mission Crest Elementary 53,634 Interior/exterior lighting retrofit and plug loads 5,756
Ranchero Middle 795,878 HVAC, interior/exterior lighting retrofit, and plug loads 50,958
Sultana High 1,312,181 HVAC, interior/exterior lighting retrofit, and plug loads 77,902
Topaz Preparatory Academy 138,465 Interior/exterior lighting retrofit and plug loads 9,325
Total $ 4,798,481 $ 2 98,354
With these energy efficiency measures, the district reported a combined
SIR of 1.22 and the creation of 26.87 direct job-years.
In addition, the district received $260,000 in planning funds directly from
the CDE, which it used for screening and audits.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issue:
Final project completion reports submitted after the deadline
The district’s final report was submitted on September 6, 2017, 26 months
after the reported project completion date of June 24, 2015.
PRC section 26240(b) states, in part:
As a condition of receiving funds from the Job Creation Fund, not sooner
than one year but no later than 15 months after an entity completes its
first eligible project with grant, loan, or other assistance from the Job
Creation Fund, the entity shall submit a report of its project expenditures
to the Citizens Oversight Board ….
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
-A7-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
District Response
We informed the district of the audit finding via email on February 14,
2019. Dr. George Landon, Assistant Superintendent of Business Services,
and Virginia Gutierrez, Director of Purchasing, Facilities, and Warehouse,
responded by letter dated February 14, 2019, and via email on March 6,
2019. The district’s response letter is included as Attachment A.
The district’s February 14, 2019 response to this finding is as follows:
The District was contracted with Climatec to administer our Prop 39
project, which included the filing of all mandatory reports with the
California Energy Commission (CEC). On May 11, 2017, the California
Energy Commission notified the District via email that our final report
was never received and was now past due. At which point the District
contacted our consultant to confirm that the final report had indeed been
filed with the CEC within the required timelines. The District’s
consultant confirmed that the report had been submitted a “while ago”.
Ultimately, the final report was submitted on the District’s behalf on
September 6, 2017.
SCO Comment
Our finding remains unchanged.
We emailed the district on February 20, 2019, requesting that the district
submit additional documentation showing that its consultant (Climatec)
had submitted the final report within 15 months of the reported project
completion date. On March 6, 2019, Ms. Gutierrez sent an email stating
that Climatec had confirmed that it submitted the final report on the date
we have on record, and that the district would not be submitting any further
documentation.
-A8-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
High Tech High International Charter School
Proposition 39 Program
Background The CEC approved High Tech High International Charter School’s EEP
for $246,555, consisting of $2,083 for energy management services and
$244,472 for program implementation. The district used its program
implementation funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
High Tech High International $ 244,472 Lighting and HVAC controls, and spray foam roof coating $ 35,788
$ 244,472 $ 35,788
With these energy efficiency measures, the charter school reported a
combined SIR of 2.86 and the creation of 1.37 direct job-years.
In addition, the charter school received $15,000 in planning funds directly
from the CDE, which it used for screening and audits, and energy
management services.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issues:
Sole-sourced project costs
We found that the charter school sole-sourced its contract with Ari-Thane
for implementation of its spray foam “cool roof” project. The district did
not provide supporting documentation to show that it considered other
vendors before awarding the contract to Ari-Thane. Therefore, we found
that the district sole-sourced its Proposition 39 contract, totaling $50,000.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the charter school’s contracts with Fess Energy, Facility
Dynamics Engineering, and Jackson and Blanc, and determined that the
contracts do not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
-A9-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that the CDE take appropriate action in response to funds
paid to the charter school that did not meet the sole-source requirement.
No additional recommendation is applicable, as the Proposition 39
program has ended.
Charter School’s Response
We informed the charter school of the audit finding via email on
February 4, 2019. Paul Dooley, Director of Facilities, responded on
February 12, 2019. The response letter is included as Attachment B.
The charter school’s response is as follows:
1. Sole-sourced funds
With regard to the cool roof project installed by Ari-thane Foam
Products, Inc. at High Tech High International, HTH did not solicit bids
from other vendors for the following reasons:
In 2007, extensive research and study was done to find a
product that provided a lightweight, cool roof, which could also
add R-value [heat resistance] to our new and existing buildings
at an affordable price. Multiple bids and product specifications
were submitted and HTH concluded that [Ari-Thane] Foam
Products best demonstrated they could meet our requirements.
After testing the product on one small building, High Tech High
then decided that all of its buildings, new and existing, would
utilize the Ari-thane Foam so that future warranty, inspections,
maintenance, and repairs could all be performed by one vendor.
This approach provides economies of scale that represents best
value in the utilization of HTH’s funding.
[Therefore], HTH began using [Ari-Thane] for installation of
cool roofs on all of its new buildings and reroofing projects in
approximately 2007.
The High Tech High International building was the last of 11
HTH buildings to be reroofed. Accordingly, Ari-thane Foam
was utilized on that building so that it would match the roofs
within the HTH inventory.
Our understanding is that, having demonstrated similar value to
other LEAs, Ari-Thane has also been the successful bidder on
several other Prop 39 roofing projects throughout Southern
California.
2. Projected energy savings not included in the contracts
HTH was one of the early adopters of the program and we attended
several early public outreach meetings in order to fully understand the
program and to establish internal best practices. High Tech High
International’s EEP was among the first approved in the state and the
contracts represented our nascent understanding of the program
requirements at the time. While our future contracts included language
related to the energy savings component, such language had no yet been
developed at the time these projects were bid.
-A10-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The approved EEP for HTHI included energy savings calculated through
Trace™ Energy Modeling software – an industry standard [that] exceeds
the program requirements. All bidding parties were notified that projects
were funded by Prop 39 Clean Energy and the energy savings component
was discussed throughout the bidding and contracting processes.
Purchase order documents show the reduced wattages of the proposed
LED lamps, for instance, and likewise cut-sheets for the HVAC
equipment show minimum efficiency ratings – both of which are directly
related to energy savings. These documents were included as part of the
contracts.
HTH is a leader in energy efficiency across its portfolio of owned
campuses, and six of our schools currently have a LEED certification.
Our organization has a dedicated facilities staff and a reasonably robust
operations and maintenance budget, which ensures our schools are
operated as efficiently as possible. The Prop 39 program provided
funding for an initiative that has been an organizational focus for HTH
since our inception in 2000. We are aligned in ideology and in practice
with the goals of Prop 39 and we certainly believe we participated in the
program to the best of our ability.
SCO Comment
Our findings and recommendation remain unchanged.
The charter school states, “While our future contracts included language
related to the energy savings component, such language had not yet been
developed at the time these projects were bid.” We disagree. The
Proposition 39: California Clean Energy Jobs Act – 2013 Program
Implementation Guidelines, which cite PRC section 26206(d), were
formally adopted by the CEC on December 19, 2013. The charter school
entered into contracts with Fess Energy, Facility Dynamics Engineering,
and Jackson and Blanc in 2015, over a year after the adoption of the
Proposition 39 Program Implementation Guidelines.
Although we recognize that the charter school participated in the program
to the best of its ability, the scope of our audit is to ensure compliance with
state statutes and regulations, which require that the projected energy
savings be identified in the awarded contract.
-A11-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Luther Burbank School District
Proposition 39 Program
Background The CEC approved Luther Burbank School District’s EEP for $266,798.
The district used its program implementation funds for the following
energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Lighting retrofit/controls, HVAC system, plug
Luther Burbank Elementary $ 266,798 loads, building envelope, domestic hot water heater $ 16,362
$ 266,798 $ 16,362
With these energy efficiency measures, the district reported a combined
SIR of 1.24 and the creation of 1.49 direct job-years.
In addition, the district received $10,767 in planning funds directly from
the CDE, which it used for screening and audits, and program assistance.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issue:
Projected energy savings not identified in awarded contracts
We reviewed the district’s contract with Highlands Energy, and
determined that the contract does not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
We also identified the following observation:
Unused planning funds
We found that the district applied unused planning funds to program
implementation. However, these funds were not included in its approved
EEP. As a result, the district received funding that exceeded its approved
EEP by $10,049. We informed the CDE of our observation via email on
January 30, 2019.
Recommendation
We recommend that the CDE take appropriate action in response to the
unused planning funds identified in this audit.
No additional recommendation is applicable, as the Proposition 39
program has ended.
-A12-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
District’s Response
We informed the district of the audit finding and observation via email on
February 14, 2019. We did not receive a response from the district.
-A13-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Mariposa County Office of Education
Proposition 39 Program
Background The CEC approved Mariposa County Office of Education’s (COE) EEP
for $62,563. Mariposa COE used its program implementation funds for
the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Mariposa County Office of Education $ 45,995 Lighting retrofit $ 2,864
Monarch Academy 16,568 Lighting retrofit 1,945
$ 62,563 $ 4,809
With these energy efficiency measures, Mariposa COE reported a
combined SIR of 1.45 and the creation of 0.35 direct job-years.
In addition, Mariposa COE received $15,919 in planning funds directly
from the CDE, which it used for screening and audits.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issues:
Projected energy savings not identified in awarded contracts
We reviewed Mariposa COE’s contract with IES and determined that the
contract does not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion reports submitted after the deadline
Mariposa COE submitted its final report on January 2, 2018, 19 months
after the reported project completion date of June 6, 2016.
PRC section 26240(b) states, in part:
As a condition of receiving funds from the Job Creation Fund, not sooner
than one year but no later than 15 months after an entity completes its
first eligible project with grant, loan, or other assistance from the Job
Creation Fund, the entity shall submit a report of its project expenditures
to the Citizens Oversight Board ….
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
-A14-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
COE’s Response
We informed Mariposa COE of the two audit findings via email on March
11, 2019. We did not receive a response from Mariposa COE.
-A15-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Mark Twain Union Elementary School District
Proposition 39 Program
Background The CEC approved Mark Twain Union Elementary School District’s EEP
for $276,203. The district used its program implementation funds for the
following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Copperopolis Elementary $ 62,064 Lighting retrofit $ 6,683
Mark Twain Elementary 214,139 Lighting retrofit 14,431
$ 276,203 $ 21,114
With these energy efficiency measures, the district reported a combined
SIR of 1.47 and the creation of 1.55 direct job-years.
In addition, the district received $7,600 in planning funds directly from the
CDE, which it used for screening and audits, and program assistance.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issues:
Sole-sourced project costs
We found that the district sole-sourced its contract with Freedom Energy
Corporation for energy planning and services, and for project management
and implementation services. The district did not provide supporting
documentation to show that it considered other vendors before awarding
the contract to Freedom Energy Corporation. Therefore, we found that the
district sole-sourced its Proposition 39 contract, totaling $16,368.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the district’s contracts with Gold Electric Inc. and EMCOR
Services and found that the contracts do not identify the projected energy
savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
-A16-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that the CDE take appropriate action in response to funds
paid to the district that did not meet the sole-source requirement.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the two audit findings via email on February 5,
2019. Roy Blair, Director of Business Services, responded by letter dated
February 22, 2019. We included the district’s response as Attachment C.
The district’s response related to the sole-source finding is as follows:
As relayed to you during your audit the District did in fact consult with
other vendors and had at least one vendor give us a proposal at the
District office. All vendors contacted were at least an hour travel time
from our location. We contacted other Districts in our county and finally
were given a recommendation by the Calaveras County Joint Power
Authority to inquire [with] Freedom Energy. Their proposal was
substantially less than any we had been given and therefore we obtained
their services. After your exit conference, we began a search for
documentation that would substantiate our claim that “we had in fact
contacted and consulted with other vendors”. We were unable to obtain
the documentation you had suggested. Emails from 2014-15 were
expunged from the county computer services after three years. Parties
involved in the process at the time had not kept notes or could not
remember contacts from three years previous. We understand that
[therefore, you] could not substantiate our process for selecting a
consultant.
Obviously, the District is not happy about possibly having to refund the
$16,838 we paid for services that we believe were the best option to
obtain consulting services. I have attached an excel spreadsheet to help
explain my following request. If we were to amend claims to show that
the Freedom Energy [expenditures] were claimed against the Calaveras
County Power Authority and not State funds, could we amend the claims
and remove them from repayment? I am currently on the Governing
Board of the Authority and believe this scenario would be acceptable to
the Authority.
The district’s response related to the lack of projected energy savings is as
follows:
We now understand that to include savings in the individual contracts
was the requirement. We thought that including the projected savings in
proposals and the project application were meeting the requirements, as
we understood them for this new program. It was our understanding that
this would be a finding but without monetary consequences.
I sincerely request that you consider the uniqueness of this grant and the
lack of experienced personnel to implement it. We appreciate the manner
in which your auditor conducted the audit and the assistance she
provided at its conclusion.
-A17-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
SCO Comment
Our finding and recommendation remain unchanged.
The SCO does not have the authority to approve or deny the district’s
request to reclassify funds used for consulting services to another grant
program. The district should consult with its project manager at the CEC
for further guidance, or consider filing an appeal with the Education Audit
Appeals Panel. We describe the process for filing an appeal earlier in this
report.
Although we recognize that the district participated in the program to the
best of its ability, the scope of our audit is to ensure compliance with state
statutes and regulations. These requirements state, in part, that districts
cannot use a sole-source process to award funds for energy management,
planning, or implementation services and that districts must identify
projected energy savings in the awarded contracts.
-A18-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Newport-Mesa Unified School District
Proposition 39 Program
The CEC approved Newport-Mesa Unified School District’s EEP for
Background
$4,799,573. The district used its program implementation funds for the
following renewable energy generation measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Abraham Lincoln Elementary $ 164,944 Photovoltaic (solar) panels $ 10,656
Adams Elementary 115,656 Photovoltaic (solar) panels 7,506
Back Bay High 117,817 Photovoltaic (solar) panels 11,233
California Elementary 115,860 Photovoltaic (solar) panels 8,687
Charles W. Tewinkle Middle 161,918 Photovoltaic (solar) panels 9,358
College Park Elementary 117,146 Photovoltaic (solar) panels 6,853
Eastbluff Elementary 162,733 Photovoltaic (solar) panels 12,795
Estancia High 1,594,903 Photovoltaic (solar) panels 119,624
Everett A. Rea Elementary 138,785 Photovoltaic (solar) panels 8,476
Harbor View Elementary 70,690 Photovoltaic (solar) panels 5,153
Harper Pre-Adult School 212,070 Photovoltaic (solar) panels 18,077
Heinz Kaiser Elementary 117,817 Photovoltaic (solar) panels 6,920
Killybrooke Elementary 117,104 Photovoltaic (solar) panels 8,775
Mariners Elementary 117,383 Photovoltaic (solar) panels 7,059
Maude B. Davis Elementary 485,753 Photovoltaic (solar) panels 34,513
Newport Coast Elementary 164,004 Photovoltaic (solar) panels 9,034
Paularino Elementary 115,656 Photovoltaic (solar) panels 11,595
Pomona Elementary 117,104 Photovoltaic (solar) panels 7,296
Roy O. Andersen Elementary 141,380 Photovoltaic (solar) panels 7,947
Victoria Elementary 117,104 Photovoltaic (solar) panels 8,353
Whittier Elementary 117,104 Photovoltaic (solar) panels 7,079
Wilson Elementary 115,656 Photovoltaic (solar) panels 7,106
Woodland Elementary 100,986 Photovoltaic (solar) panels 7,861
$ 4,799,573 $ 341,956
With these renewable energy generation measures, the district reported a
combined SIR of 1.15 and the creation of 20.16 direct job-years.
Audit Results We audited the Proposition 39 program costs and found that all costs
reported were in compliance with the Job Creation Fund program
guidelines, as well as the CEC’s Proposition 39 Program
Implementation Guidelines and EEP Handbook.
District’s Response
We informed the district via email on February 8, 2019, that all costs
reported for Newport-Mesa Unified School District were in
compliance with the program guidelines. Julia Lammatao, Financial
Analyst responded via email on February 13, 2019, stating that the
district does not wish to provide a response.
-A19-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Oceanside Unified School District
Proposition 39 Program
The CEC approved Oceanside Unified School District’s EEP for
Background
$937,052. The district used its program implementation funds for the
following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Martin Luther King Jr. Middle $ 937,052 HVAC system/controls and lighting retrofit $ 64,872
$ 937,052 $ 64,872
With these energy efficiency measures, the district reported a combined
SIR of 1.29 and the creation of 5.25 direct job-years.
In addition, the district received $34,787 in planning funds directly from
the CDE, which it used for screening and audits, and program assistance.
We audited the Proposition 39 program costs to ensure compliance with
Audit Results
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and the EEP
Handbook. We identified the following audit issues:
Sole-sourced project costs
The district contracted Ninyo & Moore for hazardous inspection services;
Program Management Group for consulting services; and Ameresco for
planning services. The district did not provide supporting documentation
to show that it considered other vendors before awarding the contracts to
Ninyo & Moore, Program Management Group, and Ameresco. Therefore,
we found that the district sole-sourced these Proposition 39 contracts,
totaling $45,449.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the district’s contracts with Global Power Group and K&J
Air Conditioning and determined that the contracts do not identify the
projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Recommendation
We recommend that the CDE take appropriate action in response to funds
paid to the district that did not meet the sole-source requirement.
-A20-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the two audit findings via email on February 4,
2019. Shannon Soto, Ed.D., Deputy Superintendent, responded via email
on February 14, 2019.
The district’s response to these findings is as follows:
Unfortunately as I’m still new to OUSD, I’m discovering gaps in our
internal procedures for the Prop 39 expenditures. Moving forward we
will adhere to the competitive [bidding] process and contract procedures.
SCO Comment
Our findings and recommendation remain unchanged.
-A21-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Pine Ridge Elementary School District
Proposition 39 Program
Background The CEC approved Pine Ridge Elementary School District’s EEP for
$62,028. The district used its program implementation funds for the
following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Pine Ridge Elementary $ 62,028 Lighting controls and retrofit $ 4,044
$ 62,028 $ 4,044
With these energy efficiency measures, the district reported a combined
SIR of 1.29 and the creation of 0.35 direct job-years.
In addition, the district received $15,507 in planning funds directly from
the CDE, which it used for screening and audits.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issues:
Projected energy savings not identified in awarded contracts
We reviewed the district’s contract with IES and determined that the
contract does not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion reports submitted after the deadline
The district’s final report was submitted on September 29, 2017, 22
months after the reported project completion date of November 20, 2015.
PRC section 26240(b) states, in part:
As a condition of receiving funds from the Job Creation Fund, not sooner
than one year but no later than 15 months after an entity completes its
first eligible project with grant, loan, or other assistance from the Job
Creation Fund, the entity shall submit a report of its project expenditures
to the Citizens Oversight Board ….
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
-A22-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
District Response
We informed the district of the two audit findings via email on
February 26, 2019. Christine Skinner, Superintendent/Principal,
responded by letter dated March 8, 2019. The district’s response letter is
included as Attachment D.
The district’s response to the findings is as follows:
1. Projected Energy Savings Not Included in the Contract
The 2014-15 Energy Expenditure Plan was approved by the
California Energy Commission (CEC) in July of 2015. A different
administrator was assigned to the district that year. When I spoke
to IES [indoor environmental services] about this finding, I was told
that at the time Pine Ridge’s project was approved that Projected
Energy Savings was not yet required for project approval.
2. Final Report not Submitted within 12-15 Months Following Project
Completion [Date]
Pine Ridge Elementary School District missed the Final Report
submission due to critical administration turn over in the 2016-17
school year. The Superintendent left and an interim was installed
until June 2017.
When I came on to run the district in July 2017, I inquired about our
Proposition 39 funds and project. Justin Payton from IES visited the
campus on September 19, 2017 to collect the information that he
needed to submit the final CEC report. Unfortunately, we missed
the deadline.
SCO Comment
Our findings remain unchanged.
The requirement that contracts identify projected energy savings is
pursuant to PRC section 26206(d), and has been in place since the
Proposition 39 program began. In addition, the CEC’s Proposition 39
Program Implementation Guidelines, and all subsequent revisions to those
guidelines, include the same requirements for Proposition 39 contracts.
-A23-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
San Leandro Unified School District
Proposition 39 Program
Background The CEC approved San Leandro Unified School District’s EEP for
$2,015,425. The district used its program implementation funds for the
following renewable energy generation measure:
Proposition 39 Renewable Reported
Share Used Energy Generation Annual Cost
School Site at School Site Measure Savings
San Leandro High School $ 2,015,425 Photovoltaic (solar) panels $ 218,731
$ 2,015,425 $ 218,731
With this renewable energy generation measure, the district reported a
combined SIR of 1.06 and the creation of 8.46 direct job-years.
In addition, the district received $58,500 in planning funds directly from
the CDE, which it used for screening and audits.
We audited the Proposition 39 program costs to ensure compliance with
Audit Results
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issue:
Final project completion reports submitted after the deadline
The district submitted its final report in August 2017, 22 months after the
reported project completion date of March 2015.
PRC section 26240(b) states, in part:
As a condition of receiving funds from the Job Creation Fund, not sooner
than one year but no later than 15 months after an entity completes its
first eligible project with grant, loan, or other assistance from the Job
Creation Fund, the entity shall submit a report of its project expenditures
to the Citizens Oversight Board ….
We also identified the following observation:
Unused planning funds
We found that the district applied unused planning funds to program
implementation. However, these funds were not included in its approved
EEP. As a result, the district received funding that exceeded its approved
EEP by $5,253. We informed the CDE of our observation via email on
January 30, 2019.
Recommendation
We recommend that the CDE take appropriate action in response to the
unused planning funds identified in this audit.
-A24-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit finding and observation via email on
February 6, 2019. Kevin Collins, Assistant Superintendent of Business and
Operations, responded via email on February 6, 2019, stating that the
district had no issues with the finding and observation.
-A25-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Venture Academy Charter School
(San Joaquin County Office of Education)
Proposition 39 Program
The CEC approved Venture Academy Charter School’s EEP for $620,039.
Background
The district used its program implementation funds for the following
energy efficiency and renewable energy generation measures:
Proposition 39 Energy Efficiency and Reported
Share Used Renewable Energy Annual Cost
School Site at School Site Generation Measures Savings
Venture Academy $ 620,039 Lighting retrofit/controls and photovoltaic (solar) panels $ 4 1,625
$ 620,039 $ 41,625
With these energy efficiency and renewable energy generation measures,
the charter school reported a combined SIR of 1.10 and the creation of
3.05 direct job-years.
We determined that the charter school received CDE apportionments
totaling of $573,704, $46,335 less than the total amount requested
($620,039) on the schools’ final project completion report. Therefore, we
only audited the amount received in Proposition 39 funding, which totaled
$573,704.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issue:
Sole-sourced project costs
The charter school contracted with Capitol Public Finance for consulting
services, Dickinson Welding & Inspection for inspection services, Iomlan
Construction Services for inspection services, Terracon Consultants for
materials testing services, and Odyssey Landscaping Co. for irrigation
system repairs. The school did not provide supporting documentation to
show that it considered other vendors before awarding contracts to Capitol
Public Finance, Dickinson Welding & Inspection, Terracon Consultants
and Odyssey Landscaping Co. Therefore, we found that the charter school
sole-sourced these Proposition 39 contracts, totaling $26,447.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Recommendation
We recommend that the CDE take appropriate action in response to funds
paid to the charter school that did not meet the sole-source requirement.
-A26-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
No additional recommendation is applicable, as the Proposition 39
program has ended.
Charter School’s Response
We informed the LEA of the audit finding via email on February 5, 2019.
Scott Anderson, Deputy Superintendent of Business Services, responded
by letter on February 6, 2019. The LEA’s response letter is included as
Attachment E.
The LEA’s response to the finding, in part, is as follows:
There is no definition of sole source in statute of in any Prop 39 guidance
we are aware of. As such, LEA’s are left to interpret this requirement in
combination with any additional guidance provided, such as the FAQ’s
referenced above. The guidance in the FAQ response highlighted above
indicates [that] LEA’s are to refer to their own procurement regulations
in certain circumstances. If a competitive process were required for any
and all contracts regardless of type or amount (which is a significant
departure from normal requirements for LEA’s), that runs counter to this
guidance which we relied upon. As such, we understood the sole
sourcing prohibition to the aimed exclusively at Gov. Code Sec. 4217.12
which allows “sole sourcing” under certain conditions for energy
services contracts. Other than the sole sourcing prohibition mentioned
above pertaining to Gov. Code Sec. 4217.12, we followed our local
regulations, consistent with the guidance provided by CDE in the cited
FAQs.
The Capital Public Finance, Dickinson Welding & Inspection, Iomian
Construction Services and Terracon Consultants are all professional
services which are not subject to competitive bidding.
The Odyssey Landscaping Co. contract (above) was less than the public
works bid limit of $15,000 and, therefore, was not subject to competitive
bidding.
Notwithstanding the preceding, the San Joaquin County Office of
Education spent $6,203,056.87 on all Prop 39 projects. Of this amount,
$1,675,535 [was] Prop 39 funds and the balance [was] local funds. Of
the $6.2 million spent on all Prop 39 projects, SJCOE paid Johnson
Controls, Inc. a total of $5,094,411.59, of which $1,419,338.67 is
attributable to the Venture Academy Family of Schools. By virtue of
simple journal accounting entries, all of the Venture Prop 39 funds
received ($573,704) could have been used to fund part of the Venture
share of the Johnson Controls Inc. energy contract. Rather, we chose to
use the Prop 39 funds for Venture’s pro rata share of all contracts needed
to complete the projects as described above, and then use a significant
amount of additional, local funds for the balance of the necessary
contracts. Stepping back from the detailed accounting methodology we
elected, the Prop 39 funds received prompted a significant local (non-
Prop 39) investment and were highly effective in achieving their
intended purpose.
SCO Comment
Our finding and recommendation remain unchanged.
-A27-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The district states that there is no definition of sole source in statute or in
Proposition 39 guidance. Although we concur that the Proposition 39
guidelines do not define the term sole source, we disagree that there is no
definition of the term in statute. Our review of other California code
sections and regulations that use the phrase “sole source” indicates that
when the phrase is used for contracting, it describes a non-competitive
bidding process of awarding contracts—in other words, a process where
contracts are awarded without advertising or bidding.
The scope of our audit is to ensure compliance with state statutes and
regulations. Therefore, although the charter school may have followed its
own procurement regulations, it did not follow the minimum standards of
PRC section 26235(c) which states, in part, “A community college district
or LEA shall not use a sole source process to award funds pursuant to this
chapter.”
-A28-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
West Covina Unified School District
Proposition 39 Program
Background The CEC approved West Covina Unified School District’s EEP for
$1,891,376, consisting of $130,573 for energy management services,
$31,468 for training, and $1,729,335 for program implementation. The
district used its program implementation funds for the following energy
efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
California Elementary $ 98,643 Lighting retrofit and relamping $ 7,255
Cameron Elementary 89,839 Lighting retrofit and relamping 7,139
Coronado Alternate 95,442 Lighting retrofit and relamping 10,631
District Office 88,838 Lighting retrofit and relamping 8,179
Edgewood Middle School 261,789 Lighting retrofit, relamping, and fixture replacement 21,804
Hollencrest Middle School 106,846 Lighting retrofit and relamping 10,573
Merced Elementary 108,647 Lighting retrofit 13,097
Merlinda Elementary 97,642 Lighting retrofit and relamping 9,463
Monte Vista Elementary 79,835 Lighting retrofit and relamping 8,987
Orangewood Elementary 108,722 Lighting retrofit and relamping 13,652
Vine Elementary 81,436 Lighting retrofit, relamping, and fixture replacement 6,648
Walnut Grove Intermediate 104,046 Lighting retrofit, relamping, and fixture replacement 8,312
Wescove Elementary 64,028 Lighting retrofit, relamping, and fixture replacement 8,248
West Covina High School 343,582 Lighting retrofit, relamping, and fixture replacement 38,804
$ 1,729,335 $ 172,792
With these energy efficiency measures, the school district reported a
combined SIR of 1.60 and the creation of 9.68 direct job-years.
In addition, the district received $136,277 in planning funds directly from
the CDE, which it used for screening and audits, and energy management
services.
We audited the Proposition 39 program costs to ensure compliance with
Audit Results
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issues:
Sole-sourced project costs
The district contracted IES for implementation and energy management
services, as follows:
Implementation costs $ 2,096,481
Energy management costs 109,022
Total costs $ 2,205,503
The district did not provide supporting documentation to show that it
considered other vendors before awarding these contracts to IES.
Therefore, we found that the district sole-sourced these Proposition 39
contracts, totaling $2,205,503. However, only $2,027,653 of the contracts
was approved by the CEC. Because we audited only the amount approved
-A29-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
by the CEC in the district’s final project completion report, we found that
the district sole-sourced a total of $2,027,653.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Proposition 39 funds applied to ineligible expenditures
The district used Proposition 39 funds to pay Associated Environmental
Management $8,075 for storm water pollution prevention services. We
found that these services were not related to approved project costs in the
district’s EEP.
The district self-certified in its EEP that “The LEA commits to use the
funds for the eligible energy project(s) approved in its energy expenditure
plan.”
The CEC’s Proposition 39 Program Implementation Guidelines state,
“LEAs can only use Proposition 39 funding for the eligible energy projects
approved in their energy expenditure plans.”
Recommendation
We recommend that the CDE take appropriate action in response to funds
paid to the district that did not meet the sole-source requirement, and funds
spent on ineligible project costs.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District Response
We informed the district of the findings via email on February 4, 2019.
Drew Passalacqua, Ed.D., Assistant Superintendent of Business Services,
responded via letter on February 14, 2019. We included the district’s
response letter as Attachment F.
The district did not respond to the finding regarding ineligible
expenditures. The district’s response to the sole-source finding, in part, is
as follows:
Without offering supporting evidence or explanation, the auditor
concludes the following: “We found that the district sole-sourced its
implementation and energy manager services, totaling $2,205,503.” The
auditor further claims, “The district did not provide documentation to
support that it considered other vendors when it awarded the contracts to
Indoor Environmental Services (IES) as [follows]:
• Implementation costs - $2,096,481
• Energy manager costs - $109,022
• Total costs - $2,205,503”
-A30-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The auditor references Public Resource Code (“PRC”) section 26235(c),
which states, in part, “A community college district or LEA shall not use
a sole source process to award funds pursuant to this chapter.” The
California Legislature has never defined “sole source process” as it
relates to Prop 39. Further, as of 2014-15, when the District went through
its RFQ [request for qualifications] process, the California Energy
Commission had not yet released any definition or parameters on the
“sole source” prohibition in its Prop 39 Guidelines or Frequently Asked
Questions. The Prop 39 Guidelines merely deferred to each educational
agency’s own “procurement regulations and procedures, as long as they
reflect applicable state and local laws and regulations and are not in
conflict with the minimum legal standards specified in [Public Resource
Code section 26235].”
Even the State Controller’s own Prop 39 audit reports provide a broad
definition of “no sole source” and have established a relatively low
standard for school districts to meet in their Prop 39 audits. For example,
in the 2017-18 PROGRAM AUDIT OF THE CALIFORNIA CLEAN
ENERGY JOBS ACT (“2017-18 SCO Audit Report”), the California
State Controller’s Office stated:
We have interpreted the requirement to ‘not use a sole source
process to award funds,’ as the need to use a competitive process.
Competitive processes promote competition, prevent favoritism,
and make the procurement process transparent.
(Program Audit of the Clean Energy Jobs Act, Fiscal Year 2017-18,
https: // www.sco.ca . gov/Files -AUD/07 2018ca ceja .pdf, at 12,
emphasis added.)
Thus, we disagree with the auditor’s finding that the District has
provided “no documentation” to prove that the District did not sole
source funds. The District has already submitted a number of records
showing a competitive RFQ process, where multiple vendors were
considered by the District. So, it is difficult for the District to understand
what exactly the auditor is looking for in making such a determination.
Any further guidance from the auditor on this standard, and the
documentation that would suffice to show compliance, would be most
helpful to the District prior to any negative audit finding.
In its response (see Attachment F) the district explained that language in
the original RFQ documents included project implementation services.
SCO Comment
Our findings and recommendation remain unchanged.
We agree that the district submitted documentation supporting $55,000 in
planning services; however, the district did not provide supporting
documentation to show that it considered more than one vendor before
awarding contracts for implementation and energy management costs,
totaling $2,205,503.
-A31-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The district indicates that further guidance on the sole-source requirement
would be helpful. Four months before we contacted the district about our
audit findings, we provided the following guidance in an email to the
district’s Chief Fiscal Executive on October 25, 2018:
The district provided a board agenda requesting approval of the RFP
[request for proposals] bid No. 11:1415 for Implementation Services
inclusive of district energy manager and training services for the award
of contract to IES totaling $2,216,483 (please see attached board
agenda). We do not have documentation to support that more than one
vendor was considered when awarding this contract. Please provide
documentation for the award of contract to IES for Implementation
Services inclusive of district energy manager and training services.
On November 7, 2018, we received a response from the Chief Fiscal
Executive asserting that RFQ No. 10:1314 covered the district’s award for
Proposition 39 planning and implementation services, including energy
management and training services. The response quoted sections of RFQ
No. 10:1314 to support this position.
We disagree with the district’s conclusions. We noted that the district
issued separate RFQs for project planning and implementation. If the
district had intended for RFQ No. 10:1314 to be inclusive of all activities,
then there would not have been an additional, separate RFQ for
implementation, and energy management and training services (RFQ
No. 11:1415). In its response, the district does not explain why it did not
provide supporting documentation for RFQ No. 11:1415, such as a copy
of the RFQ, communications to vendors requesting bids, or bids
subsequently received from various vendors, when the district’s board
document identified RFQ No. 11-1415 for implementation services and
stated that bids had been received for this RFQ. We found reference to
RFQ No. 11:1415 in a district board agenda dated May 15, 2015, stating
“RFP bids were received from various contractors with the following
result of the lowest bidder”; the agenda then identifies IES as the chosen
vendor for implementation services. Had the district provided any
evidence supporting this statement other than RFQ No. 10:1314, we might
not have identified an audit finding.
-A32-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Willits Unified School District
Proposition 39 Program
Background The CEC approved Willits Unified School District’s EEP for $544,280,
consisting of $45,000 for energy management services, and $499,280 for
program implementation. The district used its program implementation
funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Baechtel Grove Middle $ 80,800 Lighting retrofit $ 6,110
Blosser Lane Elementary 88,276 Lighting retrofit 3,722
Brookside Elementary 118,959 Lighting retrofit 3,943
Sanhedrin High 15,236 Lighting retrofit 1,269
Sherwood Elementary 7,589 Lighting retrofit 660
Willits High 188,420 Lighting retrofit 18,242
$ 499,280 $ 33,946
With these energy efficiency measures, the district reported a combined
SIR of 1.33 and the creation of 2.80 direct job-years.
In addition, the district received $29,259 in planning funds directly from
the CDE, which it used for energy management services.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issue:
Projected energy savings not identified in awarded contracts
We reviewed the district’s contracts with IES and determined that the
contracts do not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
We also identified the following observation:
Unused planning funds
We found that the district applied unused planning funds to program
implementation. However, these funds were not included in its approved
EEP. As a result, the district received funding that exceeded its approved
EEP by $8,712. We informed the CDE of our observation via email on
January 30, 2019.
Recommendation
We recommend that the CDE take appropriate action in response to the
unused planning funds identified in this audit.
-A33-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit finding and observation via email on
February 7, 2019. Nikki Agenbroad, Director of Fiscal Services,
responded via email stating that the district did not need to include a
response.
-A34-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Yreka Union High School District
Proposition 39 Program
Background The CEC approved Yreka Union High School District’s EEP for
$255,353, consisting of $19,540 for energy management services, and
$235,813 for program implementation. The district used its program
implementation funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Yreka High 235,813 HVAC system, chiller/boiler replacement 12,469
$ 235,813 $ 12,469
With these energy efficiency measures, the district reported a combined
SIR of 1.63 and the creation of 1.32 direct job-years.
In addition, the district received $20,257 in planning funds directly from
the CDE, which it used for screening and audits, and program assistance.
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CEC’s
Proposition 39 Program Implementation Guidelines and EEP Handbook.
We identified the following audit issues:
Sole-sourced project costs
The district contracted IES for planning services. The district did not
provide supporting documentation to show that it considered other
vendors before awarding the contract to IES. Therefore, we found that the
district sole-sourced its Proposition 39 contract, totaling $20,257.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the district’s contracts with IES and determined that the
contracts do not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion reports submitted after the deadline
The district’s final report was submitted on February 1, 2018, 16 months
after the reported project completion date of September 30, 2016.
PRC section 26240(b) states, in part:
As a condition of receiving funds from the Job Creation Fund, not sooner
than one year but no later than 15 months after an entity completes its
-A35-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
first eligible project with grant, loan, or other assistance from the Job
Creation Fund, the entity shall submit a report of its project expenditures
to the Citizens Oversight Board ….
Recommendation
We recommend that the CDE take appropriate action in response to funds
paid to the district that did not meet the sole-source requirement.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the three audit findings via email on
February 13, 2019. We did not receive a response from the district.
-A36-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Butte-Glenn Community College District
Proposition 39 Program
Background The California Community Colleges Chancellor’s Office CCCCO
approved Butte-Glenn Community College District’s Proposition 39
Funding Application (Form B) for $1,244,954. The district used its
program implementation funds for the following energy efficiency and
renewable energy generation measures:
Proposition 39 Energy Efficiency and Year 1 Savings-to- Direct
Share Used Renewable Energy Cost Investment Job-Years
School Site at School Site Generation Measures Savings Ratio Created
Application No. BUTTEG-1415-001
Butte College – Main Campus $ 2 97,824 Monitoring-based commissioning
Butte College – Skyway Center 1 3,249 Monitoring-based commissioning
$ 3 11,073 $ 1 1,484 1.78 2.16
Application No. BUTTEG-1516-001
Butte College – Skyway Center 9 33,881 Photovaltaic (solar) panels
9 33,881 $ 5 0,635 2.01 5.04
$ 1,244,954 $ 62,119
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CCCCO’s
Proposition 39: Clean Energy Jobs Act of 2012 – California Community
Colleges Energy Project Guidance (Energy Project Guidance). We
identified the following audit issues:
Sole-sourced project costs
The district contracted with Dan’s Electric Supply to furnish and install
gas and electric meters as part of Application No. BUTTEG-1415-001
monitoring-based commissioning (MBCx) projects. The total amount of
Proposition 39 funds related to this contract is $92,660. The district also
contracted with Murley Consulting Group for Application No. BUTTEG-
1516-001 for solar consulting services totaling $63,470. The district did
not provide supporting documentation to show that it considered other
vendors before awarding contracts to Dan’s Electric Supply and Murley
Consulting Group. Therefore, we found that the district sole-sourced these
Proposition 39 contracts, totaling $156,130.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the district’s contracts with Direct Digital Controls, Inc.; All
Phase Mechanical; CW Electric; GRD Energy; and Hankins Electric, and
determined that the contracts do not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
-A37-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that the CCCCO take appropriate action in response to
funds paid to the district that did not meet the sole-source requirement.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the two audit findings via email on April 16,
2019. Kimberly Jones, Director of Facilities Planning and Management,
and Jim Nicholas, Director of Business Services, responded via letter
dated April 22, 2019. The district’s response letter is included as
Attachment G.
The district’s response to the sole-source finding is as follows:
BGCCD is a rural district and, historically, has faced challenges getting
numerous competitive bids when requests for proposals go out on
specific projects. The District has used the best value criteria on several
projects when necessary to ensure fiscal standards and required project
outcomes are met. When looking for engineering expertise for both Solar
and MBCx projects, GRD and Murley Consulting Group were
engineering consultants recommended to the District by the California
Community College Investor Owned Utilities Partnership (CCC/IOU
Partnership) due to Butte County's rural setting and lack of local
expertise.
The CCC/IOU Partnership was established in 2006 and created to
encourage energy efficiency investments and foster best practices in the
California Community College System. The state's four investor-owned
utilities (IOUs), including Pacific Gas & Electric (PG&E), Southern
California Edison (SCE), Southern California Gas Company (SCG), and
San Diego Gas & Electric (SDG&E), have partnered with the California
Community College (CCC) Chancellor's Office and the CCC Districts to
provide technical assistance, financial incentives, and project support for
energy efficiency improvements to the CCC system statewide. One of
the primary functions of the CCCIOU has been to support the community
colleges in the implementation of the California Clean Energy Jobs Act
of 2012 (Proposition 39) by leveraging the infrastructure of the
Partnership for the identification, installation, and timely close out of
energy projects to ensure program fiscal accountability.
The District awarded contracts under the basis of Government Code
53060 professional services agreement. For special services and advice
in financial, economic, accounting, engineering, legal or administrative
matters, Districts may award contracts without engaging in a competitive
bidding or proposal process per Government Code § 53060. Such
persons contracted under this provision must be specially trained,
experienced and competent to perform the services required. Contracts
for GRD and Murley Consulting Group were established individually
under the Public Contract Code section 20651 which eliminated the need
to competitively bid the work. GRD was a consultant for the MBCx
project with a contract of $62,270 and Murley Consulting Group was a
consultant for the Skyway Center Solar for $63,470.
-A38-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The MBCx project had two separate components to the project; one was
for gas meters and the other for electrical meters. The contracts that were
issued were done through an informal bidding process dictated by Public
Contract Code 22000 Uniform Public Construction Cost Accounting
Procedures (UPCCAP) that was approved by the BGCCD Board of
Trustees in January, 2013. The project required the purchase of
miscellaneous materials and supplies that were purchased from Dan's
Electric, a local supply house. The purchase orders to Dan’s Electric fall
under public contract code 20651 as the District only purchased
equipment and materials from them and each purchase was under the
required bid limit. By doing this the District saved the project markup
from the contractors. Portions of the project were self-performed, with
the materials and supplies being purchased and the project being
completed by existing staff.
The district’s response to the projected energy savings finding is as
follows:
BGCCD has followed existing law requiring all eligible energy projects
to achieve a minimum savings to investment ratio (SIR) of 1.01 (reduced
in 2016/2017 from the previous SIR of 1.05). All projects were
thoroughly researched to ensure adequate saving were present before the
project proposals were submitted to the California Community College
Chancellor's Office for approval. The District verified savings on all
completed projects and has been above the minimum SIR on all projects.
With SI rates included in the project proposals, the Request for
Proposals, and inclusion in Board of Trustee documents, and while
including project specifications and costs on all contracts, the District
did unknowingly omit inclusion of the SIR figures on the contracts. All
information is readily available for any project, and not has not been
omitted from the process. The District relied on the expertise of the
CCC/IOU Partnership and Newcomb Anderson McCormick for
analyzing each project to ensure energy saving requirements that were
submitted in each of the project applications was accurate. The District
entered into the consulting relationship with Newcomb Anderson
McCormick on the recommendation from the CCCIOU based upon their
use of the firm as professional experts in Prop 39 project development,
management, implementation, and project closings. The required Code
language appears to be intended to document projects savings and tie
them back to the projects that were submitted to ensure the savings was
accomplished. Accordingly, the District believes the substance of the
Prop 39 requirements have been met.
SCO Comment
Our findings and recommendation remain unchanged.
The scope of our audit is to ensure compliance with state statutes and
regulations. The district cites using best value criteria, Government Code
section 53060, and Public Contract Code section 20651 to support its use
of sole-sourced contracts. However, PRC section 26235(c) states, “A
community college district or LEA shall not use a sole source process to
award funds pursuant to this chapter. A community college district or LEA
may use the best value criteria as defined in paragraph (1) of
subdivision (c) of section 20133 of the Public Contract Code to award
funds pursuant to this chapter.
-A39-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
On December 12, 2013, the CCCCO published guidance on sole-source
requirements in its “Proposition 39 Contracting Fact Sheet” which states
“Proposition 39 defers to local contracting practices as long as the
prohibition of sole source contracts and all applicable law related to
contractor qualifications, licensing, and certification requirements related
to the project are met.” The Fact Sheet also notes that “To fully comply
with that “Best Value” criteria and the prohibition against sole source
contracting when utilizing their Prop 39 funds, a District will need to
engage in a two-step process…” The two-step process that the CCCCO
describes is for districts to use a comprehensive RFQ/RFP evaluation
process. However, the district did not follow this process for awarding the
contracts in question.
-A40-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Contra Costa Community College District
Proposition 39 Program
Background The CCCCO approved Contra Costa Community College District’s
Form B for $1,253,496. The district used its program implementation
funds for the following energy efficiency measures:
Proposition 39 Year 1 Savings-to- Direct
Share Used Energy Cost Investment Job-Years
School Site at School Site Efficiency Measures Savings Ratio Created
CONTRA-1314-011
Diablo Valley College $ 1 1,484 Lighting occupancy sensors
Diablo Valley College 6 41,051 Library boiler/chiller retrofit and pumping variable frequency drive
Los Medanos College 7 ,832 Recital Hall interior lighting retrofit
Los Medanos College 3 9,589 Gym lighting retrofit
Los Medanos College 7 ,326 Little Theater lighting retrofit
7 07,282 $ 5 6,136 1.09 7.31
CONTRA-1617-005
Diablo Valley College 5 46,214 Stadium lighting retrofit
5 46,214 2 9,727 1.09 3.22
$ 1,253,496 $ 85,863
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CCCCO’s
Energy Project Guidance. We identified the following audit issues:
Sole-sourced project costs
The district contracted with Alfatech Consulting to provide engineering
consultation and related professional services for the Stadium Lighting D-
1142 project. The Proposition 39 funds related to Alfatech Consulting total
$119,700. The district also contracted with Hallpass Capital, Inc., dba
Gonled, to purchase, install, and commission new stadium LED lighting
fixtures for the Stadium Lighting D-1142 project. The Proposition 39
funds related to Gonled total $544,414. The district did not provide
supporting documentation to show that it considered other vendors before
awarding contracts to Alfatech Consulting and Gonled. Therefore, we
found that the district sole-sourced these Proposition 39 contracts, totaling
$664,114.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the district’s contracts with Pacific Metro Electric, Integra
Construction, Star Energy Management, and Gonled, and determined that
the contracts do not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
-A41-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that the CCCCO take appropriate action in response to
funds paid to the district that did not meet the sole-source requirement.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the two audit findings via email on April 18,
2019. The district did not respond to the findings.
-A42-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
South Orange County Community College District
Proposition 39 Program
Background The CCCCO approved South Orange County Community College
District’s Form B for $1,575,973. The district used its program
implementation funds for the following energy efficiency measures:
Proposition 39 Year 1 Savings-to- Direct
Share Used Energy Cost Investment Job-Years
School Site at School Site Efficiency Measures Savings Ratio Created
SOUTHO-1415-001
Saddleback College $ 7 80,000 Exterior lighting controls and retrofit
$ 7 80,000 $ 8 4,386 1.36 4.37
SOUTHO-1516-001
Saddleback College $ 7 95,973 Exterior lighting controls and retrofit
$ 7 95,973 $ 6 6,699 1.33 4.59
$ 1,575,973
Audit Results We audited the Proposition 39 program costs to ensure compliance with
the Job Creation Fund program guidelines, as well as the CCCCO’s
Energy Project Guidance. We identified the following audit issue:
Sole-sourced project costs
The district contracted WSP (Parsons and Brinckerhoff) for labor
compliance services. The district did not provide supporting
documentation to show that it considered other vendors before awarding
the contract to WSP (Parsons and Brinckerhoff). Therefore, we found that
the district sole-sourced its Proposition 39 contract, totaling $3,533.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
Projected energy savings not identified in awarded contracts
We reviewed the district’s contract with Anderson & Howard Electric and
determined that the contract does not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Proposition 39 funds applied to ineligible project expenditures
We found that for South Orange County Community College District
applied proposition 39 funds from application SOUTHO-01516-001-05 to
project costs not included in the application approved by the CCCCO. The
district improperly paid $19,579 to vendor Clear Blue Energy for an
interior lighting project that was not identified in the application.
The district signed and certified in its application that the funding would
be used for the energy projects identified in its application.
-A43-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that the CCCCO take appropriate action in response to
funds paid to the district that did not meet the sole-source requirements,
and funds spent on ineligible project costs.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit finding via email on February 4,
2019. Kathleen Burke, Ed.D., Chancellor, responded via letter on
February 14, 2019. The district’s response letter is included as
Attachment H.
The district agreed with the projected energy savings finding, stating that
“The District has amended its contract templates to ensure that energy
evaluations are now also included in all such contracts prospectively.”
The district’s response to the sole-source finding is as follows:
As it relates to the contract with WSP (Parsons and Brinkerhoff), the
District followed Government Code Section 53060 which allows for the
hiring of contractors that provide specialized services without obtaining
multiple bids. The District believes that the labor compliance services
provided by WSP (Parsons and Brinkerhoff) constitute specialized
accounting and administrative services as allowed by this Government
Code. Furthermore, sole sourcing typically is a factor when we are
required to go out to bid for goods or services, when no bidding is
required, such as allowed within Government Code Section 53060, any
contract issued under this code would not be considered sole sourcing.
The district’s response to the ineligible expenditures finding is as follows:
During the 2015/2016 fiscal year, the District contributed $33,365 of
local funds above the allocated amount of Proposition 39 funding for that
fiscal year to complete the interior lighting project. The State
subsequently provided additional funding for the interior lighting project
in fiscal year 2016/2017, which was used to cover the overage from the
prior year. Project managers have been trained to communicate with the
Fiscal Services department to ensure that Proposition 39 funds are
charged according to the applications submitted.
SCO Comment
Our findings and recommendation remain unchanged.
On December 12, 2013, the CCCCO published guidance on the sole-
source requirements in the Proposition 39 Contracting Fact Sheet, which
states:
Proposition 39 defers to local contracting practices as long as the
prohibition of sole source contracts and all applicable law related to
contractor qualifications, licensing, and certification requirements
related to the project are met.
-A44-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Therefore, although the district followed its own procurement standards,
it did not follow the minimum standards of the sole-source requirement
for Proposition 39 funds contained in PRC section 26235(c).
Although the district may have contributed discretionary funds towards
the electric lighting project in question, the district’s approved application
for Proposition 39 funding did not include this project.
-A45-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment A—
Hesperia Unified School District’s Response to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment B—
High Tech High International Charter School’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment C—
Mark Twain Union Elementary School District’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment D—
Pine Ridge Elementary School District’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment E—
Venture Academy Charter School’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment F—
West Covina Unified School District’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment G—
Butte Glenn Community College District’s
Response to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment H—
South Orange County Community College District’s
Response to Audit Results
State Controller’s Office
Division of Audits
Post Office Box 942850
Sacramento, CA 94250-5874
http://www.sco.ca.gov
S19-39M-0001